ENVIRONMENTAL IMPACT ASSESSMENT STUDY - … EIA/EMP study for Narmada-Malwa-Gambhir Link Project RS...
Transcript of ENVIRONMENTAL IMPACT ASSESSMENT STUDY - … EIA/EMP study for Narmada-Malwa-Gambhir Link Project RS...
ENVIRONMENTAL IMPACT ASSESSMENT STUDY for
NARMADA-MALWA-GAMBHIR LINK PROJECT MADHYA PRADESH
EXECUTIVE SUMMARY
April, 2015
Prepared for:
NARMADA VALLEY DEVELOPMENT AUTHORITY
Prepared by:
R. S. Envirolink Technologies Pvt. Ltd. 402, Radisson Suites Commercial Plaza,
B-Block, Sushant Lok-I, Gurgaon Ph: +91-124-4295383: www.rstechnologies.co.in
CONTENTS Page No.
1.1 AIM OF THE PROJECT 1
1.2 PROJECT PROFILE 1
1.3 LOCATION 1
1.4 WATER AVAILABILITY 1
1.5 LAND REQUIREMENT 2
1.6 STUDY AREA FOR EIA 3
1.7 ENVIRONMENTAL BASELINE DATA 3
1.8 SOCIAL ASPECTS 4
1.9 IMPACT ASSESSMENT 6
1.10 ENVIRONMENTAL MANAGEMENT PLAN 7
1.11 FINANCIAL REQUIREMENT 8
NVDA EIA/EMP study for Narmada-Malwa-Gambhir Link Project
RS Envirolink Technologies Pvt. Ltd. 1
1.1 AIM OF THE PROJECT The main objective of Narmada-Malwa-Ghambhir Link Project is to provide irrigation
facilities to the water-scare areas in upper reaches of Chambal basin where the level of
irrigation is only 5.54% of culturable area. The Narmada-Malwa- Ghambhir Link Project
has been conceived to cater irrigation water to about 50,000 ha of CCA in Indore and Ujjain
districts of Malwa region along with water for drinking and industrial purposes. 28 villages
of Sanwer Tehsil, 53 villages of Depalpur Tehsil of Indore district, 20 villages of Ujjain Tehsil,
33 villages of Ghatiya Tehsil, 17 villages of Barnagar Tehsil and 7 Villages of Khachrod Tehsil
of Ujjain district will be benefited by this scheme by way of irrigation & drinking water.
1.2 PROJECT PROFILE In the proposed scheme, 15 cumec of surplus water from existing Omkareshwar Project
Canal will be lifted through 3200 mm dia M.S. pipe rising main of about 34 km length up to
village Ambachandan of Mhow tehsil & will be further carried through 40 km of M.S. pipe
gravity main of 3200 mm dia upto Bhagoda village. This will further be bifurcated into two
piped lines namely Right Bank &left Bank Main pipe lines respectively of 75 km & 57.5 km
to irrigate 50,000 ha of CCA on both banks of Gambhir river in 158 villages of 6 Tehsils of
Indore & Ujjain districts. Provision of appropriate number/size of outlets at Ambachandan
village the origin of river Gambhir & at Yeshwant Sagar reservoir have been made to cater
the need of Industrial & domestic water usages. In the present proposal the irrigation disnet
system is completely designed as pipeline.
1.3 LOCATION The project area is spread in two regions of M.P. The lifting point, pump houses, rising main
and gravity main lie in Khargone and Indore District of Nimar region while the pipeline
system (and command area) lies in Indore and Ujjain districts of Malwa region. Location
map has been shown as Figure 1.
1.4 WATER AVAILABILITY The NWDT Award covers allocation of water to the party States, FRL of Sardar Sarovar and
Narmada Sagar Dams, Full Supply Level of Narmada Main Canal, sharing of cost and
benefits, regulated releases to be made by MP, apportionment of cost of Sardar Sarovar
dam between irrigation and power, setting up of machinery to implement the Award,
period of operation of certain clauses of the Award. The details of the above are:
1. Utilizable quantum of waters of Narmada at Sardar Sarovar Dam on the basis of 75%
dependability was assessed on 34537.44 Mcum (28 MAF).
2. The shares of the 4 party States in the above quantity allocated as under:
- Madhya Pradesh … 22511 Mcum (18.25 MAF)
- Gujarat … ……………. 11101.32 Mcum (9 MAF)
EXECUTIVE SUMMARY
NVDA EIA/EMP study for Narmada-Malwa-Gambhir Link Project
RS Envirolink Technologies Pvt. Ltd. 2
- Rajasthan ……………. 616.74 Mcum (0.5 MAF)
- Maharashtra ………. 308.37 Mcum (0.25 MAF)
As mentioned above the Madhya Pradesh State was allotted 18.25 MAF of water by NWDT
and out of this 12 MAF has been utilized by Madhya Pradesh.
Capacity of the Canal
The capacity of the existing canal is 85 cumec out of this 36 cumec is committed for OSP
flow canal and 15 cumec are committed for OSP lift canal, therefore the total committed
water is 51 cumec and out of available balance 34 cumec a discharge of 15 cumec will be
utilized for Narmada-Malwa-Gambhir-Link Project.
Figure 1: Location map of the project
1.5 LAND REQUIREMENT The rising main shall be aligned in such a way, that it traverses minimum in forest area and
the total length from lifting to delivery point becomes shortest. The topo sheet study
reveals that out of total 34 km length of Rising Main, 16 km length shall be in forest area &
rest 18 km will be either in private or in government land. The affected forest land has
been assessed on the basis of topo-sheet studies and there is a possibility of changes in the
affected area especially in forest land.
NVDA EIA/EMP study for Narmada-Malwa-Gambhir Link Project
RS Envirolink Technologies Pvt. Ltd. 3
For laying of Rising main, Electrical lines and Establishing Pump Houses in forest area about
13.60 hectare will be required. The entire pipe line either gravity or rising main shall be laid
1.00 m below average ground level except in forest area where the pipe line will be passed
through the tunnel and or on the pedestal above the ground level.
For ancillary work such as construction of pump houses and where pipeline passes through
deep cutting, non-forest land of about 15 hectare shall also be required.
1.6 STUDY AREA FOR EIA Study area comprises of area within 500 m buffer on either side of pipeline. The study area
has been demarcated into Water Conductor System area and Command Area as follows:
Water Conductor System Area
The water conductor system is the area consisting lifting of water from existing canal to the
BPT structure. This area comes under Khargone and Indore districts.
Command Area
The command area is the area of Indore and Ujjain district covers 50,000 ha land which will
be irrigated by drip/sprinkler irrigation of the proposed project.
1.7 ENVIRONMENTAL BASELINE DATA
The data on baseline status of various environmental parameters in the study area was
collected through primary as well as secondary sources. Sampling locations for surface &
ground water, soils, flora & fauna, noise, traffic etc. along water conductor system and in
command area have been shown in Figure 2.
Data collected from various secondary sources cover following aspects:
- Meteorology
- Topography, seismology, geology and geo-morphology
- Water availability
- Ground water trends: have been analyzed using Ground water department data
which shows declining trends of ground water.
- Land use and land cover has been derived: Land use/ Land cover maps prepared
by National Remote Sensing Centre (NRSC), Indian Space Research Organisation
(ISRO) of Dept. of Space, Govt. of India with Remote Sensing Application Centre,
M P Council of Science & Technology, Govt. of Madhya Pradesh as partner
under Natural Resource Census (NRC) project of National Natural Resource
Repository (NRR) programme using Resourcesat-2 LISS III satellite data. Major
land use has been observed as crop land.
Data collected, generated and supplemented with the help of primary sources covers
following aspects in ascertaining environmental baseline status:
- Noise and traffic: primary survey data was collected at 15 locations. It was
observed that the major source of noise in the study area was traffic movement
NVDA EIA/EMP study for Narmada-Malwa-Gambhir Link Project
RS Envirolink Technologies Pvt. Ltd. 4
- Soils: Secondary data has been supplemented by primary surveys at 15 locations
(5 along water conductor system and 10 in command area)
- Water resources and quality (surface and ground water): Secondary data has
been supplemented by primary surveys at 15 locations for ground water, 6 for
surface water including 4 for various streams opposing water conductor system
and 2 of river monitored by SPCB.
- Terrestrial ecology:
- Forest types
- Flora
- Fauna
- Avifauna
- Herpetofauna
Predominant forest type in the study area is Tropical Dry Deciduous Forest. In the study
area 198 species of plants were recorded. These include 57 trees, 48 shrubs and 92 species
of herbs. None of the plant species reportedly found in the study area falls under any of the
IUCN Red list of Threatened Species Version 2014.3. Ecological survey has been undertaken
at 15 locations in the study area
As per IUCN Red list of Threatened Species of Version 2014.3, of mammals there are no
endangered or threatened animal species reported from the study area as all of them have
been listed under Least Concern (LC) category. According to WPA (1972) also six mammal
species are listed in Schedule-II, and two species are listed in Schedule-III while rest of the
species is Schedule-IV and V species. All the birds listed above in the study area fall under
Least Concern category of IUCN. As per the Wildlife (Protection) Act 1972 all bird species
are listed in Schedule IV.
1.8 SOCIAL ASPECTS The villages proposed to be getting full benefits of the Project were given priority for
collection of primary data for survey work. Total 15 villages were selected for survey work
in which 10 villages were located in Ujjain District and 5 villages were in Indore District.
Table 1: Sample survey village list S.No. District Tehsil Name of Villages
1
Ujjain
Ujjain Mangrola 2 Ujjain Ratnakhedi 3 Ghatiya Siloda Rawal 4 Ghatiya Ilaskhedi 5 Ghatiya Naikhedi 6 Ghatiya Raatdiya 7 Ghatiya Mohanpura 8 Badnagar Ingoriya 9 Badnagar Baledi
10 Khacharod Lekodiya Tonk 11
Indore
Depalpur Kakwa 12 Depalpur Karjoda 13 Depalpur Sunala 14 Sawer Naharkheda 15 Sawer Pipliya Kayasth
NV
DA
EI
A/E
MP
stu
dy
for
Nar
mad
a-M
alw
a-G
amb
hir
Lin
k P
roje
ct
RS
Envi
rolin
k Te
chn
olo
gie
s P
vt. L
td.
5
Fig
ure
1: S
tud
y ar
ea
map
sh
ow
ing
sam
plin
g si
tes
of
NM
GL
Pro
ject
NVDA EIA/EMP study for Narmada-Malwa-Gambhir Link Project
RS Envirolink Technologies Pvt. Ltd. 6
Total 540 respondents of 15 villages were asked that which crop they would like to
take if they have sufficient sources of irrigation. 144 said Rabi crop, 4 said Kharif,
156 said summer crop, 117 said that they would like to grow vegetables, 1 each said
fruit and masala and 117 said all the crops. But maximum farmers are interested in
summer crop which is not possible in the present scenario due to acute shortage of
water after December-January of every year.
When the respondents were asked that if they get sufficient water for irrigation
then what will be the cost of irrigation, then all the respondents expect that there
will be cost of reduction in irrigation if Government gives ample water for irrigation.
At present the cost of irrigation is quite high so if they will have water through
Canals / Pipelines the cost of the irrigation will certainly decrease.
The respondents were asked that if they get sufficient water then how many crops
they would be able to take. 2 respondents said one crop, 66 said two crops, 439
said three crops and 33 said more than three crops. The analysis indicates that
there is more demand for three or more crops specially the cash crop of vegetables.
The respondents were asked that if Government provides them water for 120 days
then how much they can pay. 260 respondents said Rs. 500 to 2000, 155 said Rs
2000 to 5000,102 said RS. 5000 to 10000 and 23 said 10000 to 20000. Therefore
48.15% of the population wants to pay Rs. 500 to Rs. 2000 for one hectare of
irrigation, 28.70% of population wants to pay 2000 to 5000, 18.89% population
wants to pay Rs. 5000 to 10000 and 4.25% of the population wants to pay Rs.10000
to Rs.20000.
The analysis of the data indicates that each and every farmer is willing to pay the
recurring cost of the proposed irrigation by Narmada Malwa Gambhir Link Project.
The only difference is that most of the population wants to give an approximate
amount of Rs. 2000 to Rs.5000 per hectare for getting the benefits of irrigation for
their agriculture land. The big land owners are willing to pay even Rs.10000-20000
per hectare for irrigation of their agriculture fields.
The findings of the Survey indicate that the needy farmers either have to pay a huge amount to purchase water for irrigation or they have to give their land on Adhiya (Hire) to resourceful persons having ample sources of irrigation. That way they are being deprived of half of their income of winter and summer Crop.
1.9 IMPACT ASSESSMENT Assessment of environmental and social impacts of any development activity is an important
component of EIA process. Following impacts have been studied as part of study:
Impacts on air quality
Impacts on noise
Impacts on water resources: Under this head, R.D. wise details of crossings falling on
route pipe line have also been given. In addition, impacts on downstream users, water
logging & salinity, and changes in water quality due to fertilizer uses, if any, have also
been covered.
NVDA EIA/EMP study for Narmada-Malwa-Gambhir Link Project
RS Envirolink Technologies Pvt. Ltd. 7
Impacts on land environment: Under this head, abstract of villages falling with 500 m
on either side of pipeline have been tabulated. There are 26 villages within 500 km
buffer of pipeline in Barwaha tehsil, 16 in Mhow and 18 in Indore tehsil.
Total quantity of muck to be disposed off with relation to the geographical area of the
project is not very large. The tentative quantity required to be disposed off shall be
nearly 437 thousand cum from rising main and gravity main while The tentative
quantity to be disposed off shall be nearly 431 thousand cum from Right Bank Main
Pipe line & Left Bank Main Pipe line
Changes in land use and cropping pattern
Impacts on terrestrial ecology
Impacts on socio-economic environment
Increased incidence of water related diseases
Impacts due to command area development
1.10 ENVIRONMENTAL MANAGEMENT PLAN
To ensure that all the negative environmental impacts are mitigated to have minimum
environmental impacts due to development of the project, it is important to have an
Environmental Management and monitoring plan in place. Mitigation and management
measures have been prepared in the form of various plans to be implemented during
construction and operation phase and are mentioned below:
Preventive measures for leakages, bursting, corrosion and siltation in the pipeline
Public health delivery system
Compensatory afforestation plan
Control of water logging and salinity
Land compensation
Air, water and noise management plan
Environmental monitoring programme
Following medical facility will be provided in the command to combat water and vector
borne diseases and also at construction site to ensure safety and health during the entire
construction phase:
One fully equipped ambulance need to be procured to provide pre-hospital care to
accident victims. The ambulance should always be stationed near major construction
sites or the sites where risky operations are taking place.
Two fully equipped ambulance cum testing mobile vans to meet any health related
problems in the command area.
Provisions have been made for strengthening existing PHCs and PHSCs in the area.
A medico will make regular visits to the villages and organize health promotional activities
with the active participation of the local village leaders, NGO’s and available local health
functionaries.
To improve green cover in the command, it is proposed that plantation in 100 hectare in
several patches in nonforest waste land will be done subject to availability of suitable land.
The species to be planted will be chosen in consultation with local villagers and will be site
specific. Suggested species for plantations are Teak, Khamher, Bamboo, Siras, Amaltas,
NVDA EIA/EMP study for Narmada-Malwa-Gambhir Link Project
RS Envirolink Technologies Pvt. Ltd. 8
Karanj, Aonla, Mahua, Khair, Babool etc. These plantations will be maintained for five years
& will be handed over to Panchayat for management. The plantations may be done by
forest wing of NVDA, forest department or local Panchyats.
1.11 FINANCIAL REQUIREMENT Financial requirement has been assessed for above aspects as Rs 600 lakh and same have
been tabulated below:
Table 2: Cost Estimates Activities Amount (lakh Rs)
Public Health Management Plan 140 Compensatory Afforestation & NPV 320 Plantations in command area 100 Environmental Monitoring
Surface & Ground Water 10 Land use/Land cover 5 Air Quality 8 Noise 2 Ecological monitoring 15
TOTAL 600