ENVIRONMENTAL IMPACT ASSESSMENT & RISK...
Transcript of ENVIRONMENTAL IMPACT ASSESSMENT & RISK...
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 1 ONGC
ENVIRONMENTAL IMPACT ASSESSMENT & RISK ASSESSMENT REPORT FOR EXPLORATORY DRILLING OF 22 WELLS (ONSHORE) IN RAMANATHAPURAM PML, RAMANATHAPURAM DISTRICT TAMILNADU
EIA Report
Prepared for:
ONGC
Prepared by:
SENES Consultants India Pvt. Ltd.
July, 2016
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 2 ONGC
Declaration by Experts contributing to the EIA
EIA coordinator: In House
Name: Debanjan Bandopadhaya (Oct-14- March 2015) and Mangesh Dakhore March 2015-
December 2015.
At Present, Mr. Sunil Gupta is Empanelled EC for this project (since February 2016)
Signature and Date:
Period of involvement: Bandopadhaya (Oct-14- March 2015) and Mangesh Dakhore March
2015- December 2015.
At Present, Mr. Sunil Gupta is Empanelled EC for this project (since February 2016)
Name: Shubhangi (Acted as a Team Member and assisted EIA Coordinator)
Signature and Date:
Period of involvement: Oct-14- March 2015
Contact information:
Functional area experts:
S. No. Functional areas Name of the
expert/s
Involvement
(period and
task**)
Signature and date
1 AP* Mangesh Dakhore
Oct’14 – Dec ‘15 Site visit, supervising the baseline monitoring, preparing
the Impact analysis and prepared the EMP
2 WP* Mangesh Dakhore Oct’14 – Dec’ 15 Site visit, Selection of sampling locations,
“Environmental impact assessment & risk assessment report for Exploratory drilling of 22 wells (onshore) in Ramanathapuram PML, Ramanathapuram district Tamil Nadu I, hereby, certify that I was a part of the EIA team in the following capacity that developed the above EIA.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 3 ONGC
S. No. Functional areas Name of the
expert/s
Involvement
(period and
task**)
Signature and date
Impact analysis, Preparing the EMP against possible water
Pollution aspects; Tendering technical support to other
Junior EIA personnel in WP section.
3 SHW* Mangesh Dakhore
Oct’14 – Dec ’15. Site visit, Impact analysis, Preparing
the EMP to mitigate SHW aspects
4 SE* Rajani Iyer
Oct’14 – contg..
Site visit, stakeholder meeting, need based analysis, baseline section preparation,
possible impact assessment and management and CSR
plan.
5 EB Abhishek Roy Goswami
Oct’14- Feb 15
Site visit and baseline E&B primary data collection, analysis, EMP.
EB Sanjukta Sarkar
Oct ’14- Done the baseline analysis
which was vetted by the FAE and also learnt a few lessons on E&B aspects.
6 HG* -----
7 GEO*
8 SC* V.V. Subbarao
Site visit, Impact analysis, Preparing the EMP to mitigate
SC aspects from the proposed project
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 4 ONGC
S. No. Functional areas Name of the
expert/s
Involvement
(period and
task**)
Signature and date
9 AQ* Debanjan
Bandopadhaya
Oct’14 – March’15 Site visit and selection of sampling sites,
ISCST3 modelling, Impact assessment and EMP
AQ Girish Shukla ( as team Member in AQ)
Oct’14 – Oct’15. , run the ISCST3 modelling under
supervision of Mr. Debanjan and also wrote the section
which was reviewed by Debanjan.
10 NV* Debanjan
Bandyopadhyay
Oct ’14 – March ‘15
11 LU* Debanjan
Bandyopadhyay
Oct ’14 – March ‘15
LU Girish Shukla ( as a
team member in LU)
Oct’14 – Oct ‘15
12 RH* Mangesh Dakhore
Oct’ 14– Dec’ 15, Site visit, analysing the possible Impacts,
Preparing the EMP against possible RH aspects; Tendering guidance to Junior EIA
personnel in RH section, so that she could developed as an
RH personnel.
*One TM against each FAE may be shown
**Please attach additional sheet if required
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 5 ONGC
S.
No. Functional Area Code Complete name of the Functional Areas
1 WP Water Pollution Prevention, Control & Prediction of
Impacts
2 SHW Solid Waste and Hazardous Waste Management
3 EB Ecology and Biodiversity
4 RH Risk Assessment & Hazard Management
5 SE Socio Economics
6 AQ Meteorology, Air Quality Modeling & Predication
7 LU Landuse
8 AQ Air Pollution Monitoring, Prevention & Control
Declaration by the Head of the Accredited Consultant Organization
I, Mainak Hazra, hereby, confirm that the above mentioned experts prepared the Environmenta l
Impact Assessment (EIA) for EIA & EC for O&G Exploration Project, Ramnathpuram Block,
Tamilnadu, India. I also confirm that I shall be fully accountable for any mis-leading
information mentioned in this statement.
Signature:
Name: Mr. Mainak Hazra
Designation: Director
Name of the EIA Consultant Organization: SENES Consultants India Pvt. Ltd.
NABET Certificate No. NABET/EIA/RA016/040
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 6 ONGC
QCI Accreditation Certificate – SENES Consultants India Pvt. Ltd.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 7 ONGC
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 8 ONGC
Abbreviation
ALARP As Low As Reasonably Practicable
BIS Bureau of Indian Standards
BOD Biological Oxygen Demand
BOP Blow out Preventor
Cd Cadmium
CGWB Central Ground Water Board
COD Chemical Oxygen Demand
CPCB Central Pollution Control Board
Cr Chromium
CSR Corporate Social Responsibility
Cu Copper
DFO Divisional Forest Officer
DG Diesel Generator
DGH Directorate General of Hydrocarbons
DMP Disaster Management Plan
DO Dissolved Oxygen
EC Environmental Clearance
ECO Environment Compliance Officer
EGIG European Gas Incident Group
EGIG European Gas Pipeline Incident Data Group
EIA Environmental Impact Assessment
EMC Environment Management Cell
EMP Environment Management Plan
EPIs Environmental Performance Indicators
EQIs Environmental Quality Indicators
ERT Emergency Response Team
ERT Emergency Response Team
ESDs Emergency Shut Down
ETP Effluent Treatment Plant
FC Forest Clearance
GGS Gas Compressor Station
GGS Group Gathering Station
GLC Ground Level Concentrations
GoI Government of India
HC Hydrocarbon
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 9 ONGC
HFL High Flood Level
HDD Horizontal Directional Drilling
HDPE High Density Polyethylene
HSD High Speed Diesel
HSE Health, Safety and Environmental
ITOPF International Tanker Owners Pollution Federation
IUCN International Union for Conservation of Nature & Natural Resources
KLD Kilo Liter per Day
KW Kilo Watt
LEL Lower Explosive Limits
LFL Lower Flammability Limit
LOC Level of Concern
LOC Level of Concern
MoEF Ministry of Environment and Forests
MSDS Materials Safety Data Sheets
NAAQS National Ambient Air Quality Standards
NABET National Accreditation Board for Education and Training
NABL National Accreditation Board for Testing and Calibration Laboratories
NELP New Licensing Policy
NH National Highway
NIHL Noise Induced Hearing Loss
NOx Oxides of Nitrogen
NRSA National Remote Sensing Agency
O&G Oil & Gas
OCS Oil Collection Station
OGP Oil and Gas Producers
JOGPL Oil and Natural Gas Corporation Limited
OREDA Offshore Reliability Data
OSHA Occupational Safety and Health Administration
Pb Lead
PEL Petroleum Exploration License
PM Particulate Matter
PMP Petroleum & Mineral Pipelines
PPAP Pollution Prevention and Abatement Plan
PPE Personnel Protective Equipments
PSC Production Sharing Contract
PUCC Pollution Under Control Certificate
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 10 ONGC
QCI Quality Council of India
QRA Quantitative Risk Assessment
RADD Risk Assessment Data Directory
RF Reserved Forest
RFCC Residual Fluid Catalytic Cracking
SAR Sodium Adsorption Ratio
SCADA Supervisory Control And Data Acquisition
SO2 Sulphur Dioxide
SOPs Safe Operating Procedures
SPCB State Pollution Control Board
SPL Sound Pressure Level
SWMP Storm Water Management Plan
TDS Total Dissolved Solid
TDS Total Dissolved Solids
TG Tea Garden
TSS Total Suspended Solids
UEL Upper Explosive Limits
UKOPA UK Onshore Pipeline Operators Association
VOC Volatile Organic Compound
WBM Water Based Mud
WLS Wild Life Sanctuary
WMP Waste Management Plan
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 11 ONGC
Table of Contents
Executive Summary ................................................................................................................. 19
1 Introduction .............................................................................................................. 19
2 Project ...................................................................................................................... 21
3 Project Activities...................................................................................................... 22
4 Project Cost .............................................................................................................. 22
5 Baseline Environment .............................................................................................. 22
1 Introduction ..................................................................................................................32
1.1 Background .................................................................................................................. 32
1.2 Objective of the study .................................................................................................. 32
1.3 Scope of the study ........................................................................................................ 33
1.4 Structure of the EIA report........................................................................................... 33
2 Description of the Project ............................................................................................39
2.1 Overview ...................................................................................................................... 39
2.2 Objectives and Benefits of Proposed Exploratory & Development Drilling Activities ..
2.3 Field Location & Description ...................................................................................... 40
2.3.1 Location ............................................................................................................... 40
2.3.2 Accessibility......................................................................................................... 40
2.4 Ramanathapuram PML Area ...................................................................................... 45
2.4.1 Environmental Settings of ONGC Onshore-PML Area ...................................... 45
2.4.2 Existing Activity in Gas Field.............................................................................. 47
2.5 Well Locations and Environmental Settings................................................................ 47
2.5.1 Location of Wells ................................................................................................. 47
2.5.2 Environmental Settings ........................................................................................ 49
2.6 Alternative Analysis..................................................................................................... 52
2.7 Project Activities And Schedule .................................................................................. 54
2.7.1 Pre-drilling Activity ............................................................................................. 55
2.7.2 Drilling Activity ................................................................................................... 57
2.7.3 Well Decommissioning........................................................................................ 61
2.8 Utilities & Resource Requirements ............................................................................. 62
2.8.1 Power Supply ....................................................................................................... 62
2.8.2 Water Consumption ............................................................................................. 63
2.8.3 Waste water.......................................................................................................... 63
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 12 ONGC
2.8.4 Fuel Consumption ................................................................................................ 63
2.8.5 Chemical Storage ................................................................................................. 65
2.8.6 Manpower / Employment..................................................................................... 65
2.8.7 Noise and Vibrations............................................................................................ 65
2.8.8 Air Emissions ....................................................................................................... 66
2.9 Drilling Hazards ........................................................................................................... 66
2.10 Project Cost .............................................................................................................. 67
2.11 HSE Policy ............................................................................................................... 67
3 Description of the Environment ...................................................................................70
3.1 Physical Environment .................................................................................................. 70
3.1.1 Climate & Meteorology ....................................................................................... 70
3.1.2 Ambient Air Quality ............................................................................................ 72
3.1.3 Ambient Noise Quality ........................................................................................ 81
3.1.4 Physiography and Geology .................................................................................. 84
3.1.5 Hydrogeology....................................................................................................... 87
3.1.6 Ground Water Quality.......................................................................................... 88
3.1.7 Drainage ............................................................................................................... 95
3.1.8 Surface water quality ........................................................................................... 98
3.1.9 Additional Surface Water Monitoring ............................................................... 100
3.1.10 Land-Use ........................................................................................................ 102
3.1.11 Soil Quality .................................................................................................... 104
3.1.12 Natural Hazards.............................................................................................. 106
3.2 Ecological Environment............................................................................................. 108
3.2.1 Methodology ...................................................................................................... 108
3.3 Forest Resources ........................................................................................................ 109
3.4 Habitat ........................................................................................................................ 109
3.4.1 Forest Habitat ..................................................................................................... 109
3.4.2 Inland Wetland Habitats..................................................................................... 109
3.4.3 Coastal and Marine Habitat................................................................................ 109
3.5 Vegetation .................................................................................................................. 110
3.6 Wildlife Habitat & Wildlife ....................................................................................... 110
3.6.1 Birds Sanctuary .................................................................................................. 110
3.6.2 Gulf of Mannar................................................................................................... 111
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 13 ONGC
3.7 Gulf of Mannar Marine National Park ....................................................................... 112
3.8 Gulf of Mannar Biosphere Reserve ........................................................................... 112
3.9 Marine Ecosystem: Gulf of Mannar........................................................................... 113
3.9.1 Off Shore Islands and Coral Reefs..................................................................... 113
3.9.2 Mangrove ........................................................................................................... 115
3.9.3 Sea Grass & Sea-weed habitat ........................................................................... 116
3.9.4 Biodiversity Profile of Biosphere Reserve ........................................................ 117
3.9.5 Planktons ............................................................................................................ 121
3.9.6 Agricultural Diversity ........................................................................................ 124
3.10 Socioeconomic Environment ................................................................................. 124
3.10.1 Methodology .................................................................................................. 124
3.10.2 General Socioeconomic Profile ..................................................................... 126
3.10.3 Demographic Profile ...................................................................................... 126
4 Environmental Impact Assessment ............................................................................130
4.1 Impact Assessment Methodology .............................................................................. 130
4.1.1 Impact Criteria and Ranking .............................................................................. 130
4.1.2 Impact Significance............................................................................................ 131
4.2 Impact Assessment..................................................................................................... 134
4.2.1 Visual Impacts & Aesthetics.............................................................................. 134
4.2.2 Impacts on Air Quality....................................................................................... 135
4.2.3 Impact on Noise Quality .................................................................................... 142
4.2.4 Potential Impact Transport and Traffic .............................................................. 145
4.2.5 Potential Impact on Land Use ............................................................................ 145
4.2.6 Impact on Soil Quality ....................................................................................... 145
4.2.7 Impact on Topography & Drainage ................................................................... 147
4.2.8 Impact on Surface Water Quality....................................................................... 149
4.2.9 Impact on Hydrogeology & Ground Water Quality .......................................... 150
4.2.10 Impact on Biological Environment ................................................................ 150
4.2.11 Impact on Socioeconomic Environment ........................................................ 152
4.2.12 Impact on Occupational Health and Safety.................................................... 154
5 Quantitative Risk Assessment....................................................................................159
5.1 Objective of the QRA Study ...................................................................................... 159
5.2 Risk Assessment Methodology .................................................................................. 160
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 14 ONGC
5.2.1 Hazard Identification.......................................................................................... 161
5.2.2 Frequency Analysis............................................................................................ 162
5.2.3 Consequence Analysis ....................................................................................... 163
5.2.4 Risk Evaluation .................................................................................................. 165
5.3 Risk Assessment of Identified Project Hazards ......................................................... 166
5.3.1 Blow Outs/Loss of Well Control ....................................................................... 166
5.3.2 Non-process fires/explosions ............................................................................. 177
5.3.3 Pipeline Failure .................................................................................................. 178
Individual Risk ............................................................................................................... 187
5.4 Disaster Management Plan......................................................................................... 188
5.4.1 Objective ............................................................................................................ 188
5.4.2 Purpose............................................................................................................... 189
5.4.3 Emergency Classification .................................................................................. 189
5.4.4 Level 1 - Emergency .......................................................................................... 190
5.4.5 Level 2 - Emergency .......................................................................................... 190
5.4.6 Level 3 - Emergency .......................................................................................... 191
5.4.7 ONGC Emergency Response/Crisis Management Team .................................. 191
5.4.8 Action Plan for Fire Fighting ............................................................................. 192
6 Environmental Management Plan & Monitoring Framework ...................................194
6.1 Environment Management Plans ............................................................................... 195
6.1.1 Pollution Prevention and Abatement Plan (PPAP) ............................................ 195
6.1.2 Waste Management Plan.................................................................................... 200
6.1.3 Storm Water Management Plan ......................................................................... 203
6.1.4 Wildlife Management Plan ................................................................................ 203
6.1.5 Road Safety & Traffic Management Plan.......................................................... 205
6.1.6 Occupational Health & Safety Management Plan ............................................. 207
6.1.7 Management of Social Issues and Concerns...................................................... 208
6.2 EMP Budget ............................................................................................................... 209
6.3 Environmental Monitoring Program .......................................................................... 213
7 Public Consultation ....................................................................................................217
8 Disclosure of Consultants ..........................................................................................219
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 15 ONGC
List of Tables
Table 1-1: Compliance to MoEF ToR .....................................................................................34
Table 2-1: Details of Well Locations ......................................................................................48
Table 2-2: Well Locations in CRZ area ...................................................................................52
TAble -2.3: well located within 10 Km of therthangali bird sanctuary ...................................53
TAble -2.4: wells located in Ecological Sensitive Zone of sakkarkottai bird sanctuary .........53
Table -2.5: wells located within 10 km gulf of mannar national park .....................................53
Table 3-1: Details of AAQMS .................................................................................................73
Table 3-2: Analytical / Measurement Methods .......................................................................73
Table 3-3: Ambient Air Quality Results - PreMonsoon ..........................................................76
Table 3-4: Ambient Air Quality Results – Post Monsoon .......................................................78
Table 3-4: Ambient Air Quality Results – HC and VOC ........................................................80
Table 3-5 Details of Noise Monitoring Locations ...................................................................81
Table 3-6: Ambient Noise Quality Results ..............................................................................81
Table 3-7: Sampling Locations of Ground Water....................................................................90
Table 3-8: Groundwater monitoring Results ...........................................................................92
Table 3-9: Sampling Location of Surface Water .....................................................................98
Table 3-10: Surface Water Quality Results .............................................................................99
Table 3-11: Additional Surface Water Monitoring Results ...................................................100
Table 3-12: Details of Soil Monitoring Locations .................................................................104
Table 3-13: Soil Analysis Results ..........................................................................................105
Table 3-14: Details of birds sanctuaries.................................................................................110
Table 3-15: Plankton Profile of Marine Surface Water .........................................................121
Table 3-16: Benthic Profile Of Sediment Sample .................................................................123
Table 3-17:Biodiversity Index for Phytoplankton & Zooplankton........................................123
Table 3-18: List of the study area villages in the ONGC Field .............................................126
Table 4-1: Impact Prediction Criteria ....................................................................................131
Table 4-2: Criteria based Significance of Impacts.................................................................132
Table 4-3: Impact Identification Matrix.................................................................................133
Table 4-4: Input Parameters Considered for Monitoring.......................................................136
Table 4-5: Predicted GLCs for Air Pollutants .......................................................................137
Table 4-6: Construction Equipment Noise Levels .................................................................142
Table 4-7: Drilling Rig & Equipment Noise Levels ..............................................................143
Table 4-8: Impact Significance Matrix (with mitigation) ......................................................156
Table 5-1: Frequency Categories And Criteria ......................................................................162
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 16 ONGC
Table 5-2: Severity Categories and Criteria...........................................................................163
Table 5-3: Risk Matrix ...........................................................................................................165
Table 5-4: Risk Criteria and Action Requirements................................................................166
Table 5-5: Blow Out Cause Distribution for Failures during Drilling Operations ................168
Table 5-6: Natural Gas Release Modeling Scenarios ............................................................171
Table 5-7: Zone of Flammable Vapour Cloud – Natural Gas Release Scenarios .................175
Table 5-8: Frequency of Occurrence - Non-Process Fires.....................................................177
Table 5-9: Scenarios for QRA Study .....................................................................................178
Table 5-10: Primary Gas Pipeline Failure Frequency............................................................179
Table 5-12: Natural Gas Connectivity - Probability of Jet Fire .............................................181
Table 5-13: Pipeline Design Specifications ...........................................................................182
Table 5-14: Threshold Values for each Effect Level .............................................................182
Table 5-15: Threat Zone Distance for Hypothetical Risk Scenarios .....................................186
Table 5-16: Individual Risk – Pipeline Rupture ....................................................................188
Table 6-1: Tentative Budget for EMP Implementation .........................................................209
Table 6-2: Environmental Management Matrix.....................................................................210
Table 6-3: Proposed Monitoring Requirements of the Project ..............................................214
List of Figures
Figure 2-1: Regional Setting Map of Ramanathapuram PML Area ........................................41
Figure 2-2: Ramanathapuram PML Field Location Map on Toposheet ..................................42
Figure 2-3: Ramanathapuram PML Field Location Map on Satellite Imagery .......................43
Figure 2-4: Ramanathapuram PML Field Accessibility Map ..................................................44
Figure 2-6: Typical Drilling Rig Configuration.......................................................................59
Figure 2-7: Drilling Waste Management .................................................................................60
Figure 2-8: Typical Drilling Fluid Circulation System............................................................61
Figure 2-9: Water Balance Diagram ........................................................................................64
Figure 2-10: Typical Noise Emissions from Construction Machinery ....................................66
Figure 3-1: Wind Rose Diagram ..............................................................................................72
Figure 3-2: Location of Air, Noise, Meteorology Locations within the ONGC Field ...........83
Figure 3-3: Topographic Map of ONGC Field ........................................................................86
Figure 3-4: Location of Groundwater, Surface Water and Soil Monitoring Locations within
the ongc Field...............................................................................................................94
Figure 3-5: Drainage Map within the Block ............................................................................97
Figure 3-6: Land Use Map within the ongc Field ..................................................................103
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 17 ONGC
Figure 3-7: Seismic Zone Map of India .................................................................................107
Figure 3-8: Gulf of Mannar....................................................................................................112
Figure 3.9: Ecological Sensitivity Map .................................................................................120
Figure 3.10: % of Sceduled caste population of the Villages of the study area ....................129
Figure 3.11: literacy of the Villages falling in the study area ................................................129
Figure 4-1: NO2 Plot (3x900 KW DG Set) .........................................................................138
Figure 4-2: PM Plot (3x900 KVA DG Set) ...........................................................................139
Figure 4-3: SOx Plot (3x900 KVA DG Set) ..........................................................................140
Figure 4-4: NOx Plot (Test Flaring) ......................................................................................141
Figure 4-4: Noise Attenuation Plot ........................................................................................144
Figure 5-1: Risk Assessment Methodology ...........................................................................161
Figure 5-2: Ignition Probability Vs Release Rate ..................................................................170
Figure 5-3: Scenario I - Risk Contour Map ...........................................................................173
Figure 5-4: Scenario II - Risk Contour Map ..........................................................................174
Figure 5-5: Scenario III - Risk Contour Map.........................................................................175
Figure 5-6: Scenario III (Worst Case) – Overpressure Risk Modeling Results ....................176
Figure 5.6: Natural Gas Pipeline Failure – Distribution of Incident & Causes .....................179
Figure 5.7: Threat Zone Plot for Jet Fire – 1” Dia Leak ........................................................184
Figure 5.8: Threat Zone Plot for Jet Fire - 4” Pipeline Rupture ............................................185
VCE Modeling Results for Overpressure ..............................................................................186
Figure 5.9: Tolerance Criteria For Individual Risks ..............................................................187
Figure 5-2: Emergency Classification “Decision Tree” ........................................................190
Figure 5-3: Emergency Response Levels .............................................................................191
List of Annexures
Annexure 1.1:Approved TOR by MOEF………………………………………………214
Annexure 3.1:Ambient air Quality Results…………………………………………….219
Annexure 3.2:Ambient Noise Quality Results………………………………………….227
Annexure 3.3: Metrological Data Monsoon-2014 ( July 30 th to September 3rd
2014)…………………………………………………………………………………….237
Annexure 3.4: Demographic Details ……………………………………………………270
Annexre 4-A:Flora&Fauna…………………………….............................................…...278
Annexre 4-B:Phytosociological study…………………...................................................288
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 18 ONGC
Annexure 5: Public hearing notice……………………………………………………….303
Annexure 6: Public hearing minutes of meeting………………………………………....306
Annexure 7: Coastal zone minutes of meeting………………………………………......327
Annexure 8: Application of Wild life clearance……………………………………….....330
Annexure 9: Nabet Certficate ………………………………………………………....332
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 19 ONGC
EXECUTIVE SUMMARY
1 Introduction
The Ramanathapuram PML block of Oil and Natural Gas Corporation (ONGC) is located in
Ramanathapuram District of Tamilnadu. ONGC is proposing to drill 22 wells in the district.
The Ramanathapuram PML block is located in Ramnad sub-basin which is in the southern part
of Cauvery Basin.
The exploratory and testing of hydrocarbons proposed in Ramanathapuram PML block is
included under activities specified in Schedule (Activity 1b) of the new EIA Notification dated
14th September 2006. It requires Environmental Clearance (EC) from the Ministry of
Environment and Forests (MoEF).
ONGC had submitted Form-1 of the EIA Notification, along with a Draft Terms of Reference
(ToR) for EIA study to MoEF. MoEF has issued approved ToR vide letter dated 5th November
2013F. No. J-11011/207/2013- IA II (I). TOR compliance is included in the EIA report as Table
1.1. Details of well locations finalized by ONGC after alternative analysis and geophysica l
studies is given in the following Table 1. The finalized locations fall in the same taluka.
TABLE 1: DETAILS OF WELL LOCATIONS
S.N
o
Well
No
District/T
aluka
Village
Name
Latitude Longitude Survey No.
1 W1
Ramanat
hpuram
Tiruppullan
i
9°16'41.67"N 78°49'7.38"E 236
2 W2 Periyapattanam
9°16'40.92"N 78°54'27.78"
E
26
3 W3**
Reghunathapuram
9°18'32.3"N 78°54'52.1"E 61/1C
4 W4* Panaikulam 9°22'4.8"N 78°56'12.4"E 81/1D
5 W5 Kalari 9°17'28.10"N 78°47'16.90"
E
6
6 W6 Pullandai 9°14'37.67"N 78°43'27.85"
E
3
7 W7*
*
Kalari 9°17'21.03"N 78°47'3.10"E 335/2B
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 20 ONGC
8 W8**
Puthendhal 9°20'57.81"N 78°47'32.46"
E
208/1B
9 W9 Tiruppullani
9°18'34.43"N 78°47'48.74"
E
24
10 W10 Utttarakosa
magai
9°18'44.24"N 78°44'24.88"
E
121/122
11 W11 Achadipirambu
9°18'55.57"N 78°49'49.55"
E
125
12 W12 Pattanamkattan
9°20'14.98"N 78°52'24.98"
E
375
13 W13 Pattanamka
ttan
9°21'16.79"N 78°52'3.12"E 150
14 W14**
Palangulam 9°24'17.54"N 78°52'7.16"E 103/104
15 W15
*
Chittarakott
ai
9°27'02.00"N 78°53'43.10"
E
180/1A5
16 W16 Devipattina
m
9°27'10.58"N 78°53'1.76"E 333
17 W17 Perunayal 9°28'25.26"N 78°51'41.43"
E
414
18 W18 Attiyuttu 9°24'39.49"N 78°55'19.31"
E
221/222
19 W19*
Athangarai 9°19'33.0"N 78°58'34.70"
E
113/2B
20 W20*
Kil Nagachi
9°18'46.69"N 78°59'31.12"
E
127/6A2
21 W21
*
Pirappanval
asai
9°18'12.80"N 79° 2'32.9"E 107/2A
22 W22 Sattakonvalasai
9°17'23.2"N 79°0 4'16.7"E 150/2B
Note:
Well locations marked with (*) are the updated locations. The previous locations were
within the CRZ area. These updated locations (after alternative analysis) are now
outside of CRZ area and does not require CRZ clearance.
Well locations marked with (**) are the locations updated on the basis of findings from
geological studies
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 21 ONGC
The awarded block falls within 10 km radius of wildlife sanctuaries, marine national park and
biosphere reserve. Most of the well location identified in the awarded block falls in the 10 km
radius of Therthangali and Sakkarkottai Bird Sanctuary, Gulf of Mannar Marine National park
and Biosphere Reserve. The drilling locations identified on the basis of updated geologica l
study findings were assessed with reference of CRZ area and ecological sensitivity by
superimposing the well lcoations on CRZ and ecological sensitivity maps and it was observed
that some of the well locations fall within 10 km radius of Wildlife Sanctuary, Marine National
Park and Biosphere Reserve. However, based on the analysis, no wells falls within the CRZ
area therefore CRZ clearance is not requried. Application for wild life clearance is already
filed by ONGC on 21.08.2015 to the Chief Wildlife Warden, Gulf of Mannar Park,
Ramnathpuram District, Tamilnadu.
2 Project
Location
The Ramanathapuram PML area of ONGC covers approximately 493.21 sq. km area and is
located in Ramanathapuram district of Tamilnadu. Proposed to drill 22 wells in the block area.
The geographic location of the Ramanathapuram PML area is included within the Survey of
India’s Topo- Sheet Nos. 58 K/11, 58 K/12, 58 K/15, 58 K/16, 58 O/3.
Accessibility
Roads
Ramanathapuram PML area can be reached by NH 49 & NH 210 which connects
Ramanathapuram through Madurai and Trichy cities from the state capital Chennai. The entire
portion of the Field can be accessed by these National Highways which branches off to
Periyapattanam, Thirupullani and Ervadi by PWD roads. Main settlements, industries and
educational institutions within the field can also be accessed by PWD roads. However, small
villages; remote areas, can be accessed by ‘kutcha’ roads.
Railway
Ramanathapuram is the major railway station within the field and is located at the Chennai-
Rameshwaram line of Southern railway.
Airport
The nearest airport to the Ramanathapuram PML area is located at Madurai, which is
approximately 210 km from Ramanathapuram.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 22 ONGC
3 Project Activities
The lifecycle of project activities for the exploration project has been divided into distinct steps
and each is described in detail in the subsequent sections and will take approximately three
months to complete drilling and testing activity at each well site.
The project lifecycle has been classified into three phases:
Pre-drilling activity
Site selection
Land acquisition
Site access road and drill site construction
Pre-drilling activities, mobilization and Rigging up
Initial well construction
Drilling activity
Drilling of wells
Well testing
Well decommissioning
Well abandonment
Site closure and decommissioning
Site Restoration
4 Project Cost
The anticipated cost of drilling of each well (which stacking of the location, land acquisit ion,
site preparation and drilling activity works out to Rs.20.00 crores for one well and the total
project cost is Rs.440Crores.
5 Baseline Environment
Attributes of the physical environment like air, water, soil, and noise quality in the surrounding
area were assessed primarily through monitoring and analysis of samples collected from field.
Air, noise, water and soil primary monitoring was carried out by Vitro Labs Pvt. Ltd,
Hyderabad (MOEF certified laboratory). All monitoring at field were undertaken under the
guidance and supervision of SENES personnel during premonsoon period 30th July- 3rd
September 2014
Climate
The block falls under the tropical climate zone.The district characterize a Tropical climate. The
period from May to June is generally hot and dry. The weather is pleasant during the period
from December to January. Usually mornings are more humid than afternoons. The relative
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 23 ONGC
humidity is on an average between 79 and 84%. The mean minimum temperature is 25.7°C
and mean maximum daily temperature is 30.6°C respectively (Source: CGWB Annual report
2009).
Primary meteorological monitoring conducted at Regunathapuram village within the block the
temperature profile, rainfall pattern relative humidity, wind speed and wind direction of the
region have been discussed below.
Wind Speed and Wind Direction
The wind speed and wind direction of an area influences the dispersal of pollutants from a point
and non point sources. As the proposed drilling and testing activities involve the operation of
both point (DG sets) and non point pollutant emissions sources, analysis of wind speed and
direction data is considered important for predicting the air quality impacts based on pollutant
dispersion. Meteorological monitoring weather station was placed at Regunathapuram village.
Interpretation of Primary Baseline Data
Hourly micro-meteorological data collected during primary monitoring has been analyzed to
generate the monsoon wind rose. The predominant wind direction was observed to be from
West for the study period. The average wind speed for the months was 4.12 m/s. The wind
speed was observed primarily in the range 0.67 – 12.2 m/s for the monitoring period. The calm
frequency was recorded as 5.2 %
Ambient Air Quality
Ambient air quality monitoring was conducted at 8 representative locations within the block
for 24 hours a day twice a week for paramaters PM10, PM2.5, Sulphur Dioxide (SO2), Nitrogen
di oxide (NO2), Carbon monoxide (CO) and HC & VOC during the premonsoon period of the
year 2014. Ambient air quality of Ramanathapuram, is found to be within the limits prescribed
by CPCB for residential area and represent rural environments with slight dust at kutcha roads.
Air Quality Results
Particulate Matter (PM10): The average concentration of 24 hourly PM10 at all the monitor ing
locations ranged between 35-57 μg/m3. 98 percentile PM10 values of the stations ranged
between 42.8-56.6 μg/m3. The average as well as 98 percentile PM10 concentrations were
observed to be in compliance to the NAAQS (100 μg/m3) at all air quality monitoring locations.
Particulate Matter (PM2.5): The average PM 2.5 concentration monitored at all the monitor ing
stations exist within the range of 18-27 μg/m3. The concentration of PM2.5 is also in compliance
with the NAAQ standard of 60 μg/m3.
Nitrogen dioxide (NO2): The average value of NO2 concentration is found within the range
of 9-16 μg/m3 at all the monitoring locations. The monitored concentration of NO2 complies
with the NAAQS (80 μg/m3) specified for nitrogen dioxide.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 24 ONGC
Sulfur dioxide (SO2): The average Sulfur dioxide concentration values at all the monitor ing
locations is observed in the range of 6-13 μg/m3 , which is well within the NAAQS (80 μg/m3)
limits specified for nitrogen dioxide.
The concentration of CO, MHC and NMHC observed within the range of 1.0-1.2 mg/m3, 1.51-
1.69 ppm and 0.43-0.58 ppm. Concentration of VOCs were found as below detectable limit
(BDL).
Ambient Noise Level
The ambient noise monitoring was conducted at 10 locations within the block. Noise stations
were selected near to the proposed well locations and settlements to understand the baseline
noise levels that could be impacted upon by the proposed drilling activities at the field during
the period from 1st August 2014 to 17th August 2014.
The results of the noise monitoring indicates that daytime noise levels are in the range of 44 –
54.2 dB(A) and fall within the NAAQS limit i.e. 55 dB(A) prescribed for the residentia l
landuse, at all the monitoring locations. The night time noise level 31.8 – 50.8 dB (A) is
observed as higher than the NAAQS limit of 45 dB(A) at three locations. This higher level of
noise may be attributed to ongoing traffic activities in the study area and high wind speed due
to sea shore region.
Ground Water Quality
Ground Water Sampling Points
A total of 6 nos. ground water samples were collected from shallow tube wells of the study
area prospect zone villages comprising of Enmanamkondan, Raghunathapuram,
Periyapattanam, Kilakkarai, Ervadi and Tirupalani. Samples were analyzed for
physicochemical and bacteriological parameters and results compared with IS: 10500 drinking
water standards to identify and interpret any deviation in the statutory limits set for parameters
under this standard.
Interpretation of Ground Water Quality Results
Turbidity
Turbidity values for range between 2.80 to 6.00 ground water.
Chlorides and Total Dissolved Solids
With respect to IS: 10500 standards the desirable limit of chloride is 250 mg/l while the
permissible limit of the said parameter (in absence of alternate source) is 1000 mg/l. The
chloride concentration in the ground water samples of the study area range between 199-425
mg/l.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 25 ONGC
The TDS values for the ground water samples analyzed varies in the range of 1001 mg/l to
1496 mg/l thereby conforming to the exceeding desirable limit of this ground water parameter.
Total Hardness
Total hardness values for the ground water samples analyzed ranged between 344 mg/l to 672
mg/l and were found to be exceeding standard of 300 mg/l specified under IS: 10500.
Iron and Fluoride
Iron concentration of ground water samples collected range 0.01 to 0.07 were found within the
desirable limit of IS: 10500 Standard.
Heavy Metals
The presence of heavy metals like mercury (< 0.001 mg/l), arsenic (< 0.01 mg/l), copper (<
0.02 mg/l), lead (<0.005 mg/l), hexavalent chromium (<0.05 mg/l) and cadmium (< 0.002
mg/l), in the ground water samples of all the six sources were found to be below detection
limits.
Coliforms
Total Coliform is analysed by Four plate method & Incubation Method as per IS:15185 - 2002.
Fecal Coliform is measured is analysed by Four plate method & Incubation Method as per
IS:15185 – 2002 method.
Surface water quality
Surface Water Sampling Points
Surface water samples were collected from all major water channels of the study area i.e. Vagai
river(Upstream & Downstream), Water body in periyapattanam, Water body/river near
Kanjirangudi, Water body near Sattakonvalasai to get an overview of the surface water quality
of the study area
Interpretation of Surface Water Quality Results
The pH of the surface water samples varied from 7.4-7.9. The total coliform count of the
surface water samples range between 15 to 35 MPN/100ml. The presence of contaminants in
the form of oil and grease and heavy metals viz. lead, iron, arsenic, chromium and mercury in
the surface waters of all sources were found to be negligible. The toxic organic component,
phenol, was also found be below detectable limit (<0.001 mg/l) in all the surface water samples
Soil Quality
Primary Soil Sampling and Analysis
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 26 ONGC
The soil characteristics within the study area, especially the physical quality and fertility of the
soil have been characterized by analyzing the soil samples collected from 5 locations namely,
Panaikkulam, Enmanamkondan, Sattakonvalasai, Raghunathapuram, Ervadi. Primary soil
monitoring includes analysis of the heavy metals with the objective of establishing baseline
values for such contaminants.
Interpretation of Soil Analysis Results
It has been observed that the pH of the soil in the study area ranged from 6.7 to 7.7 the maximum pH value of 7.7 was observed at village (Eravadi), where as the
minimum value of 6.7 was observed at Village (Panikulam).
The electrical conductivity was observed to be in the range of 143 µmhos/cm to 334
µmhos/cm, with the maximum observed at village (Eravadi) and minimum observed in Village (Regunathapuram).
The nitrogen values range between 32.2-177 kg/ha. The nitrogen content in the study area falls in very less to better category.
The phosphorus values range between 2.3 to 66.7 kg/ha, indicating that the phosphorus content in the study area falls in very less to sufficient category.
The potassium values range between 111.6 – 267.3 kg/ha. The potassium content
in the study area falls in less to more than sufficient category.
The chlorides were found to be in the range of 70.9– 301.3 mg/kg of soil.
Ecological Environment
The Ramanathapuram district is rich in biodiversity and has a number of sensitive ecosystems
comprising both terrestrial and coastal & marine components. In the study area important
wildlife habitat is Gulf of Mannar Marine National Park(GMMNP), Gulf of Mannar Biosphere
Reserve and Sakkarkotai Bird Sanctuary. Some of the well locations in awarded block falls
within 10km buffer zone of Gulf of Mannar Reserve and Sakkarkotai Bird Sanctuary.
Socioeconomic Environment
Stakeholders Identification
The local communities which would primarily be affected were identified based on the location
of the tentative exploratory and drilling operations as proposed by ONGC. The villages were
selected within 1-2 km radius of the proposed well location considering the fact that there might
be potential impacts on the socio-economic-cultural and environment of the local communit ies
residing in these villages.
Consultations
The stakeholder analysis was followed by discussions with some of the key stakeholders to
identify their dependence on the affected or shared resources, the extent of impact on them and
measure, which will be undertaken to mitigate these impacts.
Issues like land and resource damage, social disturbance, severance and increased congestion,
noise and air pollution, employment opportunities, need for development of basic
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 27 ONGC
infrastructure, safe drinking water, sanitation facilities in the surrounding villages were
discussed during the consultations so that they can be adequately addressed through the
environment management plans. The consultations also helped in developing preliminary
understanding of the requirement of social development initiatives, which are required in the
project village and may be undertaken as part of the ONGC’s CSR activity.
Action plan
ONGC has a CSR Policy. Based on the local area of project, CSR interventions will be finalized
by ONGC. During consultation two key areas for CSR interventions identified were drinking
water and educational services beyond primary school in some of the villages.
In terms of CSR interventions key concerns for some of the villages are with respect to drinking
water and education facilities for middle/secondary and further educational services. Currently
the education opportunities within the village are only till the primary school. For further
studies opportunities are available only at Ramanathapuram which is far from the villages.
While transport facilities are available these are not convenient for the students and the costs
are high for families sending their children to school. Villages adjacent to the coast have salt
water ingress due to which there is less availability of drinking water.
ENVIRONMENTAL IMPACT ASSESSMENT
The potential impacts of the project on different components of the environment was
systematically identified and evaluated for significance. The principal concerns that emerged
are:
Impact on air Quality
Development of drill sites and approach roads, operation of DG sets, movement of vehicles
and machineries during construction and drilling at drill sites will result in the generation of air
pollutants viz. PM, NO2 and SO2 which will affect the ambient air quality. Air pollutants like
NO2 will also be generated as a result of flaring of natural gas.
Impact on Noise Quality
Operation of heavy machinery/equipments and vehicular movement during site preparatory,
road strengthening/construction activities may result in the generation of increased noise levels.
Operational phase noise impacts are anticipated from operation of drilling rig and ancillary
equipment viz. shale shakers, mud pumps and diesel generators.
Impact on Soil Quality
Stripping of top soil will affect the soil fertility of the well sites. Potential impact on soil quality
may result from storage and handling of fuel, lubricants and from storage and handling of
drilling mud and drill cuttings.
Impact on Local Drainage & Physiography
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 28 ONGC
Well site preparation, sourcing of quarry material, widening/strengthening of access roads and
restoration of well facilities would potential impact on drainage and topography. This might
also lead to the flow of untreated waste water and excess rain water to the adjoining agricultura l
land thereby adversely impacting the fertility of the soil.
Impact on Biological Environment
Majority of the exploratory & development wells are located on agricultural land where there
are no prominent vegetation except prosopis trees. Further, no wells are located in the coastal
region which will prevent impact on vegetation in coastal area. Vegetation clearance
(prosopis/palm trees) in an area of 2.2 ha will be required for wells located in 22 wells for
construction of drill site.
ENVIRONMENTAL MANAGEMENT PLAN
Site-specific Environment Management Plans (EMP) has been developed to prevent and
mitigate significant adverse impacts and accentuate beneficial impacts will be implemented
by ONGC for the proposed project. The key mitigation measures specific for each
management plan have been discussed in the Table below:
Sl.
No
Environment
Management
Plan
Key Mitigation Measures
1 Pollution Prevention and Abatement Plan
The top soil generated from site clearance activities will be stored in designated area and stabilized to prevent fugit ive
dust emissions.
Preventive maintenance of DG sets to be undertaken.
All vehicles, equipment and machinery used for
construction will be subjected to preventive maintenance as per manufacturer norms.
Installation of acoustic enclosures and mufflers on engine exhaust of DG sets to ensure compliance with generator
noise limits specified by CPCB.
Fuel and chemical storage areas will be paved and properly
bunded.
Run-off discharges to natural drainage channels/water
bodies to conform to CPCB Inland Water Discharge Standards.
Proper casing and cementing of drilling well will be done to
prevent contamination of sub-surface aquifers.
Water based mud to be used as a drilling fluid
2 Waste Management Plan
Use of low toxicity chemicals for the preparation of drilling fluid.
Storage of drill cuttings in impervious HDPE lined pits
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 29 ONGC
Sl.
No
Environment
Management
Plan
Key Mitigation Measures
Disposal of wash water will be achieved after necessary treatment to comply with the CPCB onshore effluent discharge standard for oil and gas industry.
Necessary spill prevention measures viz. spill kit will be made available at the hazardous material storage area
The hazardous waste (waste and used oil) will be managed in accordance with Hazardous Waste (Management,
Handling & Transboundary Movement) Rules, 2008
Used batteries will be recycled through the vendors
supplying lead acid batteries as required under the Batteries (Management & Handling) Rules, 2001.
Recyclables will be periodically sold to local waste recyclers.
3 Road Safety &
Traffic Management Plan
Project vehicular movement involved in sourcing and
transportation of borrow material will be restricted to defined access routes.
Precautions will be taken to avoid damage to the public
access routes including highways during vehicular movement.
Clear signs, flagmen & signal will be set up at major traffic junctions and near sensitive receptors viz. primary schools
in discussion with Gram Panchayat and local villagers.
Movement of vehicles during night time will be restricted.
Speed limits will be maintained by vehicles involved in transportation of raw material and drilling rig.
Routine maintenance of project vehicles will be ensured to
prevent any abnormal emissions and high noise generation.
Adequate training on traffic and road safety operations will
be imparted to the drivers of project vehicles. Road safety awareness programs will be organized in coordination with
concerned authorities to sensitize target groups viz. school children, commuters on traffic safety rules and signage.
4 Occupational
Health & Safety Management Plan
All machines to be used in the construction will conform to
the relevant Indian Standards (IS) codes, will be kept in good working order, will be regularly inspected and properly
maintained as per IS provisions and to the satisfaction of the site Engineer.
Contractor workers involved in the handling of construction
materials viz. borrow material, cement etc. will be provided with proper PPEs viz. safety boots, nose masks etc.
No employee will be exposed to a noise level greater than 85 dB(A) for a duration of more than 8 hours per day.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 30 ONGC
Sl.
No
Environment
Management
Plan
Key Mitigation Measures
Provision of ear plugs, ear muffs etc. and rotation of workers operating near high noise generating areas.
All chemicals and hazardous materials storage container will
be properly labeled and marked according to national and internationally recognized requirements and standards.
Materials Safety Data Sheets (MSDS) or equivalent data/information in an easily understood language must be readily available to exposed workers and first-aid personnel.
The workplace must be equipped with fire detectors, alarm systems and fire-fighting equipments. Equipments shall be
periodically inspected and maintained to keep good working condition.
Adequate sanitation facilities will be provided onsite for the operational workforce both during construction and
operational phase of the project.
Training programs will be organized for the operational workforce regarding proper usage of PPEs, handling and
storage of fuels and chemicals etc.
Sensors and alarms to detect H2S will be installed at the
project site and nearby area. further, breathing apparatus will be made available at the site
5 Management of
Social issues and concerns
People from adjoining areas especially given job preference
through local contractors according to the skill sets possessed.
ONGC will analys the needs in the area and implement Corporate Social Responsibility (CSR) Plan.
During the drilling phase and for the rest of the project activities proper safety measures will be undertaken both for
transportation as well as the other operations.
The drill site would be fenced and gates would be constructed so that the children are refrained from straying
into the site.
7 Emergency Response Plan
Drilling rig and related equipments to be used for development drilling will be conformed to internationa l
standards specified for such equipment.
Blow-out preventers and related well control equipment
shall be installed, operated, maintained and tested generally in accordance with internationally recognized standards.
Appropriate gas and leak detection system will be made available at each of the drilling location.
Adequate fire-fighting equipment shall be provided at each drilling site
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 31 ONGC
The EMP has been designed with a flexibility so that it can be monitored and adapted to future
changes in project design, scope, or the environment and be seamlessly integrated and
implemented by ONGC.
Emissions from the proposed project will not degrade the ambient air quality of the surrounding areas. The impact on water, noise level, soil and land use is expected to be negligible. Impact
on ecology, socio-economics, amenities and infrastructure of the study area is expected to be positive. All necessary pollution control measures would be invisaged for minimizing any impact foreseen due to the proposed project.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 32 ONGC
1 Introduction
1.1 BACKGROUND
The Ramanathapuram PML block of Oil and Natural Gas Corporation (ONGC) is located in
Ramanathapuram District of Tamilnadu. ONGC is proposing to drill 22 exploratory wells in
the district. The Ramanathapuram PML block is located in Ramnad sub-basin which is in the
southern part of Cauvery Basin.
The exploratory and testing of hydrocarbons proposed in Ramanathapuram PML block is
included under activities specified in Schedule (Activity 1b) of the new EIA Notification dated
14th September 2006.It requires Environmental Clearance (EC) from the Ministry of
Environment and Forests (MoEF).
ONGC had submitted Form-1 of the EIA Notification, along with a Draft Terms of Reference
(ToR) for EIA study to MoEF. MoEF has issued approved ToR vide letter dated 5th Novembe r
2013, F. No. J-11011/207/2013- IA II (I). The approved ToR is attached as Annexure 1.1 and
is in compliance to ToR is presented at Table 1.1.
The awarded block falls within 10 km radius of wildlife sanctuaries, marine national park and
biosphere reserve. Most of the well location identified in the awarded block falls in the 10 km
radius of Therthangali and Sakkarkottai Bird Sanctuary, Gulf of Mannar Marine National park
and Biosphere Reserve. The drilling locations identified on the basis of updated geologica l
study findings were assessed with reference of CRZ area and ecological sensitivity by
superimposing the well lcoations on CRZ and ecological sensitivity maps and it was observed
that some of the well locations fall within 10 km radius of Wildlife Sanctuary, Marine National
Park and Biosphere Reserve. However, based on analysis, no wells falls within the CRZ area
therefore CRZ clearance is not requried. Application for wild life clearance is already filed by
ONGC on 21.08.2015 to the Chief Wildlife Warden, Gulf of Mannar Park, Ramnathpuram
District, Tamilnadu. The locations of four wells are also updated by ONGC based on recent
geological study findings. However, the updated locations are in the same village and Taluka.
There is no change in the village and taluka level.
1.2 OBJECTIVE OF THE STUDY
The objectives of the EIA study are as follows:
Establish the prevailing baseline environmental and socio-economic condition of the
Ramanathapuram PML block and its surroundings along with the compliance needs for
environmental approvals to carry out exploratory, development and testing of
hydrocarbons;
Assess environmental and socioeconomic impacts arising out of the proposed
exploratory and production testing activities;
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 33 ONGC
Assess impacts resulting from the proposed exploration project within the
Ramanathapuram PML block;
Conduct Risk Assessment study and propose disaster management plan
Recommend appropriate preventive and mitigation measures to eliminate or minimize
pollution, environmental & social disturbances during the life-cycle of the project,
ensuring compliance with environmental laws and regulation applicable ;
Integrate mitigative measures with existing ONGC’s environmental action plans and
management systems so that they can be implemented, monitored and suitable
corrective action can be taken in case of deviations;
Identify and propose alternative actions in terms of technology and practices that may
help in abating environmental or socio-economic impacts due to the project;
1.3 SCOPE OF THE STUDY
The basic scope for this study involves conducting of an EIA study of about 3 months duration
to understand the environmental and social impacts of the project and recommend suitable
preventive / mitigative actions through the Environment Management Plan (EMP). The scope
for the study finalized in close consultation with ONGC has been summarized below:
Understand the existing activities conducted by ONGC in the Field posing adverse
impacts on environment and socioeconomic integrity of the area;
Undertake site visits for collection of primary and secondary information on
environmental and social setting in the Ramanathapuram PML block;
Formulate primary environmental monitoring plan and supervision of the onsite
monitoring program as per plan;
Carry out public consultation and stakeholder analysis;
Asses environmental and social impacts; and
Conduct Risk Assessment study
Formulate EMP and DMP.
1.4 STRUCTURE OF THE EIA REPORT
The EIA report documents the results and findings of the EIA study undertaken by SENES.
Subsequent sections of the report present description of the project activities, environmental &
social baseline scenario and the outcome of assessment of the impacts and risks that may arise
during the lifecycle of the project. Subsequently, the environmental management plan
involving mitigation measures that will help in mitigating negative and unacceptable
environmental impacts has also been presented. The content of the report is structured as
follows:
Executive Summary
Chapter 1: Introduction
Chapter 2: Description of the Project
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 34 ONGC
Chapter 3: Description of the Environment
Chapter 4: Impact Assessment
Chapter 5 Risk Assessment
Chapter 6 Environmental Management Plan & Monitoring Framework
TABLE 1-1: COMPLIANCE TO MOEF TOR
Sl.
No ToR Points Issued Addressed at EIA
1. Executive summary of a project The executive summary is included in the EIA report
2. Project description, project objectives and project benefits.
Proposed project consist of drilling of 22 exploratory wells with an objective
to explore the potential of oil and gas reserves in the awarded block. The
details of project and its benefits is given in section 2.2
3.
Site details within 1 km of the each proposed well, any habitation, any
other installation/activity, flora and fauna, approachability to site, other
activities including agriculture/land, satellite imagery for 10 km area. All the geological details shall be
mentioned in the Topo sheet of 1:40000 scale, superimposing the
well locations and other structures of the projects.
The site detail within 1 km of each well is has been analyzed with the help of
satellite image and site visit. Findings of analysis is presented in the section 2.5.2
and 3.1.9
4.
Copy of CRZ map prepared by one of the agencies authorized by the
MoEF for carrying out the CRZ demarcation, on which the project
boundary and facilities are superimposed.
No wells fall under CRZ area
5.
CRZ clearance/ recommendation
from State Coastal Zone Management Authority, if applicable.
Not applicable
6.
Details of forest land involved in the
proposed project. A copy of forest clearance letter, if applicable.
Forest land is not involved in the
proposed project.
7.
Permission from the State Forest
Department regarding the impact of the proposed plant on the surrounding National Park/Wild life
Sanctuary/Reserve Forest/Eco sensitive area, if any. Approval
Application to obtain wildlife clearance
and Wildlife Management Plan has been submitted Chief Wildlife Warden on 21.08.2015.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 35 ONGC
Sl.
No ToR Points Issued Addressed at EIA
obtained from the State/Central
Government under Forest (Conservation Act, 1980) for the forestland shall be submitted.
8.
Distance from nearby
critically/severely polluted area as per Notification dated 13th January,
2010, if applicable.
No Critically/Severely Polluted areas
located in Ramanathapuram District.
9. Does proposal involves rehabilitation and resettlement? If yes, details thereof.
Rehabilitation and resettlement is not required.
10. Details of project cost. Total project cost is Rs. 440Crores
11.
Environmental considerations in the
selection of the drilling locations for which environmental clearance is being sought. Present any analysis
suggested for minimizing the foot print giving details of drilling and
development options considered.
The environmental considerations such
as location of sensitive ecologica l habitats, settlements, schools/ hospitals, water bodies, CRZ etc has been
considered for selection of the well sites. Details of site selection criterias have
been provided in Section 2.5.1.
12.
Baseline data collection for air, water and soil for one season leaving
the monsoon season in an area of 10 km radius with centre of Oil Field as
its centre covering the area of all proposed drilling wells.
The Baseline environmental data have been provided in Chapter 3 and detailed
data is provided as Annexure -3
(i) Topography of the project site. The topographic map is provided in Figure 3.3
(ii) Ambient Air Quality monitoring at 8 locations for PM10,
SO2, NOx, VOCs, Methane and non-methane HC.
Ambient Air Quality monitored at 8 locations and analysis is provided at Section 3.1.2. Analysis result shows that
all the parameters of ambient air quality is within the limit of NAAQS
(iii) Soil sample analysis (physical
and chemical properties) at the areas located at 5 locations.
Soil Quality monitored at 5 locations is
provided at Section 3.1.10
(iv) Ground and surface water
quality in the vicinity of the proposed wells site.
Groundwater and surface water quality monitored at 6 and 5 locations
respectively are provided at Sections 3.1.6 and 3.1.8
(v) Climatology and Meteorology
including wind speed, wind direction, temperature rainfall
relative humidity etc.
Climate and Meteorology of the project
area is provided at Section 3.1.1and the detailed results are presented at Annex
3.3
(vi) Measurement of Noise levels within 1 km radius of the proposed wells.
Ambient Noise Quality monitored at 10 near the proposed wells is provide at Section 3.1.3
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 36 ONGC
Sl.
No ToR Points Issued Addressed at EIA
(vii) Vegetation and land use;
Animal resources
The land use of the Field is provided at
Section 3.1.9. The Land use map is provided at Figure 3.5
13. Incremental GLC as a result of DG set operation.
Ambient air quality has been conducted to assess the increment GLC due to DG
set operation and gaseous flaring. Analysis result is provided at Section
4.2.2 and it shows that there is no significant increase in GLC due to DG set operationa and gaseous flaring.
14.
Potential environmental impact
envisages during various stages of project activities such as site
activation, development, operation/ maintenance and decommissioning.
Impact Assessment due to various phases
of project on surrounding atmosphere is done and presented in Chapter 4 of this
report
15.
Actual source of water and
‘Permission’ for the drawl of water from the Competent Authority. Detailed water balance, waste water
generation and discharge.
Detailed water requirement, waste
generation and waste discharge for the proposed project has been estimated and given in 2.8.2
16.
Noise abatement measures and
measures to minimize disturbance due to light and visual intrusions in
case coastally located.
Impact on ambient noise has been assessed in details during the EIA study
and based on the assessment, noise abatement measures has been provided in Section 4.2.3 Impact on Noise Quality
and Section 6.1.1 Pollution Prevention and Abatement Plan
17. Treatment and disposal of waste
water.
Refer Section 2.7.3 Waste water and
Disposal and Section 6.1.2 Waste Management Plan
18. Treatment and disposal of solid
waste generation.
Refer Section 2.7.3 Waste Streams and Disposal and Section 6.1.2 Waste
Management Plan
19. Disposal of spent oil and loose. Refer Section 2.7.5 Waste Streams and Disposal and Section 6.1.2 Waste
Management Plan
20. Storage of chemicals and diesel at site.
The chemicals for mud preparation would be stored at the drill site at a
secluded site while Fuel will be stored at onsite storage facility as per Petroleum Rules, 2002 in a paved and bunded area.
Refer Section 2.8.5 for Chemical storage and for Diesel storage
21. Commitment for the use of WBM
only
Refer Section 2.6.2 Drilling Activity and
for mud composition to be used at the wells
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 37 ONGC
Sl.
No ToR Points Issued Addressed at EIA
22.
Mud make up and mud and cutting
disposal – all options considered shall be listed with selective option.
Mud and cuttings disposal has been
provided at Section 2.7.2 Solid and Hazardous Waste Streams and Section 6.1.2 Waste Management plan
23. Hazardous material usage, storage accounting and disposal.
Refer Section 2.8 Hazardous materia l
usage, storage accounting and disposal and Section 6.1.2 Waste Management
Plan
24. Disposal of packaging waste from site.
Refer Section 6.1.2 Waste Management Plan
25. Oil spill emergency plans in respect of recovery/ reclamation.
Refer Section 2.8 Pollution Prevention
and Abatement Plan for emergency plans in case of oil spills. Oil spill emergency plans in case of a
blow-out have been presented at Section 5.3.1
26. H2S emissions control.
Natural gas produced from ONGC’s
existing producing Fields in the area is devoid of any H2S.
27. Produced oil handling and storage. Oil produced at the time of well testing operations will be collected in an Oil
tanker and taken to the nearest OCS
28.
Details of scheme for oil collection
system along with process flow diagram and its capacity.
Not applicable as this is exploratory
drilling project.
29.
Details of control of air, water and
noise pollution in oil collection system.
Not applicable as this is exploratory
drilling project.
30. Disposal of produced/formation water.
Not applicable as this is exploratory
drilling project.
31. Whether any burn pits being utilized for well test operations.
Burn pits will not be utilized for production test operations.
32.
Restoration and decommissioning
plans which shall include mud pits and wastage restoration also and
documentation and monitoring of site recovery.
Refer Section 2.7.3 Well
Decommissioning
33. Measures to protect ground water and shallow aquifers from
contamination.
Refer Section 6.1.1 Pollution Prevention and Abatement Plans- Groundwater
quality impacts
34.
Risk assessment and disaster management plan for independent
reviews of well designed construction etc. for prevention of blow out.
Refer Chapter-5 for Quantitative Risk Assessment
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 38 ONGC
Sl.
No ToR Points Issued Addressed at EIA
35. Environmental management plan. Refer Chapter-6 Environment
Management Plan
36. Documentary proof of membership of common disposal facilities, if any.
None
37.
Details of environmental and safety related documentation within the
company including documentation and proposed occupational health
and safety Surveillance Safety Programme for all personnel at site. This shall also include monitoring
programme for the environmental.
Refer Box 2.1 ONGC Corporate HSE Policy
Refer Box 6.1 ONGC Corporate Environment Policy
Refer Section 6.1.6 Occupational Health and Safety Management Plan Environmental Monitoring Programme
has been provided at Table 6.3
38. Total capital and recurring cost for environmental control measures.
Cost for environmental control measures have been provided at Table 6.2.
39.
A copy of Corporate Environment
Policy of the ONGC as per the Ministry’s O.M. No. J-
11013/41/2006-IA.II(I) dated 26th April, 2011 available on the Ministry’s website.
Refer Box 2.1 ONGC Corporate HSE
Policy Refer Box 6.1 ONGC Corporate
Environment Policy
40.
Any litigation pending against the
project and or any direction/order passed by any court of law against
the project. If so details thereof.
No litigation is pending against the
project
41.
Public hearing issues raised and commitments made by the project proponent on the same shall be
included separately in EIA/EMP Report in the form of tabular chart
with financial budget for complying with the commitments made.
Included in Chapter 7- Public Consultation
42. A tabular chart with index for point-
wise compliance of above TORs.
Provided
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 39 ONGC
2 Description of the Project
2.1 OVERVIEW
Oil & Natural Gas Corporation (ONGC) obtained exploratory drilling PML lease for onshore
in Ramanathapuram district of Tamil Nadu under MoPNG, GOI, vide O.O F.No
12012/52/2003-ONG-II has approved Mining license for Ramanathapuram PML
(493.21Sq.KM) for a period of seven years with effect from the date of grant by Government
of Tamil Nadu. Application for grant of PML has been submitted to Government of Tamil
Nadu.
In the present exploratory drilling plan ONGC is planning to drill 22 wells in Ramanathapuram
PML area to determine more reserve and enhance production to meet the demand in the state.
2.2 OBJECTIVES AND BENEFITS OF PROPOSED EXPLORATORY & DEVELOPMENT
DRILLING ACTIVITIES
Based on detailed geological studies, 22 prospects have been identified in Ramanathapuram
PML area to test the prospects of Nannilam, Bhuvanagiri and Andimadam formations.
Project Objectives
Objectives of the proposed drilling activities are summarized below:
To drill and evaluate hydrocarbons’ prospects safely
To drill and evaluate prospects minimum impacts on the environment
To determine hydrocarbon potential of designated prospects
To decide optimum locations of next few wells to be drilled based on geological models
and Geotechnical investigations and Geological mapping.
Project Benefits
The project will benefit people living in neighboring villages in relation to direct & indirect
employment associated with various project activities and will boost the local economy.
The proposed project will also result in the improvement of existing road and/or bridge
condition thereby enabling the transportation of drilling rig and ancillary equipment.
Local economic development through contracts like vehicle supply, petty business.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/July 2016 40 ONGC
2.3 FIELD LOCATION & DESCRIPTION
2.3.1 Location
The Ramanathapuram PML area of ONGC covers approximately 493.21 sq. km area and is
located in Ramanathapuram district of Tamilnadu. Regional setting of the gas field is shown in
Figure 2.1. The geographic location of the Ramanathapuram PML area is included within the
Survey of India’s Topo- Sheet Nos. 58 K/11, 58 K/12, 58 K/15, 58 K/16, 58 O/3. The regional
setting map, Ramanathapuram PML area location map superimposed on Toposheet and
satellite imagery is shown in Figure 2.1 Figure 2.2 and Figure 2.3 respectively.
2.3.2 Accessibility
Roads
Ramanathapuram PML area can be reached by NH 49 & NH 210 which connects
Ramanathapuram through Madurai and Trichy cities from the state capital Chennai. The entire
portion of the Field can be accessed by these National Highways which branches off to
Periyapattanam, Thirupullani and Ervadi by PWD roads. Main settlements, industries and
educational institutions within the field can also be accessed by PWD roads. However, small
villages; remote areas, can be accessed by ‘kutcha’ roads.
Railway
Ramanathapuram is the major railway station within the field and is located at the Chennai-
Rameshwaram line of Southern railway.
Airport
The nearest airport to the Ramanathapuram PML area is located at Madurai, which is
approximately 210 km from Ramanathapuram. The accessibility map is shown in Figure 2.4.
D
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
_______________________________________________________________________________________________________________________________________________________________________________________________________________
SENES/H-20084/ July 2016 41 ONGC.
FIGURE 2-1: REGIONAL SETTING MAP OF RAMANATHAPURAM PML AREA
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
_______________________________________________________________________________________________________________________________________________________________________________________________________________
SENES/H-20084/ July 2016 42 ONGC.
FIGURE 2-2: RAMANATHAPURAM PML FIELD LOCATION MAP ON TOPOSHEET
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
_______________________________________________________________________________________________________________________________________________________________________________________________________________
SENES/H-20084/ July 2016 43 ONGC.
FIGURE 2-3: RAMANATHAPURAM PML FIELD LOCATION MAP ON SATELLITE IMAGERY
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
_______________________________________________________________________________________________________________________________________________________________________________________________________________
SENES/H-20084/ July 2016 44 ONGC.
FIGURE 2-4: RAMANATHAPURAM PML FIELD ACCESSIBILITY MAP
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 45 ONGC.
2.4 RAMANATHAPURAM PML AREA
2.4.1 Environmental Settings of ONGC Onshore-PML Area
The onshore PML area is located in Ramanathapuram district of Tamilnadu and spreads over
an area of about 493.21 sq. km. The block area is located in Kadaladi and Ramanathpuram
Taluk of Ramanathapuram District. The key physical features of the area have been described
below:
The block area is spread all over the district. The eastern boundary of the block area is
aligned with the coast of Bay of Bengal. The block boundary gradually steps down from
Ramanathapuram taluk towards the Southwest direction and ends near Idambadal
village of Kadaladi taluk of the Ramanathapuram district. NH-49 & NH-210 coming
from north direction lead to the well locations in the district. The southern boundary of
the block area spread along the south coast from Ervadi to Sattakonavalasai of the
district.
The main drainage traversing through the block area is Vagai River coming from
Paramkudi flows towards eastern side of the block and merges in to the sea at
Atrangarai. Two back water streams, one is at Kanjirangudi another at
Periyyapattanam, flows in southern side of the block.
Irrigation here is mainly carried with tanks (rain fed), tube wells and dug wells.
The entire district is dry throughout year; the district receives rain in retreat of
monsoons, i.e., in September, October and November months.
Agricultural Lands with in the PML Block Sakkarkottai Bird Sanctuary with in the PML
Block
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 46 ONGC.
NH-49 at Devipatnam Road
Vaigai River at Kil Nagachi
Prosopis within PML Block Palm Trees with in the PML Block
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 47 ONGC.
2.4.2 Existing Activity in Gas Field
The Ramanathapuram PML area has overlapping areas of other production fields of ONGC
which is being operated for a long time. The main activities conducted by ONGC at the field
are
Development and Production well drilling
Production of gas from producing wells
Transportation of gas to respective Gas Compressor Station (GCS) via. interconnec ting
pipelines
2.5 WELL LOCATIONS AND ENVIRONMENTAL SETTINGS
2.5.1 Location of Wells
The proposed well sites are selected based on environmental considerations viz. location of
sensitive ecological habitats, CRZ areas, settlements, schools/ hospitals, water bodies etc. Care
had been taken to located wells sites distantly from these receptors. Alternative analysis had
also been conducted to explore the well sites away from sensitive areas. However, some well’s
locations falls within ecological sensitive zone or 10 km buffer area of Sanctuaries and National
park. Application for wild life clearance is filed by ONGC dated 21.08.2015 to the Chief
Wildlife Warden, Gulf of Mannar Park, Ramnathpuram District , Tamilnadu .
Details of well locations finalized after alternative analysis and geophysical studies is given in
Table -2.1. After alternative analysis, no wells fall under the CRZ area as shown in Figure -
2.5. The wells which are proposed within the ecological sensitive zone/10 km buffer area have
been applied for wild life clearance. The adequate environmental and safety measures will be
adopted to minimize the footprint on ecological sensitive receptors. Primarily, agricultura l
lands have been identified for the drilling program and their survey numbers are given in
Table-2.1. Total 22 exploratory wells are proposed in the Ramanathapuram PML area during
the plan period. The well locations are shown in Figure 2.4.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 48 ONGC.
TABLE 2-1: DETAILS OF WELL LOCATIONS
S.N
o
Well
No
District/Tal
uka
Village Name Latitude Longitude Survey
No.
1 W1
Ramanathp
uram
Tiruppullani 9°16'41.67"N 78°49'7.38"E 236
2 W2 Periyapattana
m
9°16'40.92"N 78°54'27.78"E 26
3 W3** Reghunathapuram
9°18'32.3"N 78°54'52.1"E 61/1C
4 W4* Panaikulam 9°22'4.8"N 78°56'12.4"E 81/1D
5 W5 Kalari 9°17'28.10"N 78°47'16.90"E 6
6 W6 Pullandai 9°14'37.67"N 78°43'27.85"E 3
7 W7** Kalari 9°17'21.03"N 78°47'3.10"E 335/2B
8 W8** Puthendhal 9°20'57.81"N 78°47'32.46"E 208/1B
9 W9 Tiruppullani 9°18'34.43"N 78°47'48.74"E 24
10 W10 Utttarakosamagai
9°18'44.24"N 78°44'24.88"E 121/12
2
11 W11 Achadipiramb
u
9°18'55.57"N 78°49'49.55"E 125
12 W12 Pattanamkattan
9°20'14.98"N 78°52'24.98"E 375
13 W13 Pattanamkatta
n
9°21'16.79"N 78°52'3.12"E 150
14 W14**
Palangulam 9°24'17.54"N 78°52'7.16"E 103/104
15 W15* Chittarakottai 9°27'02.00"N 78°53'43.10"E 180/1A
5
16 W16 Devipattinam 9°27'10.58"N 78°53'1.76"E 333
17 W17 Perunayal 9°28'25.26"N 78°51'41.43"E 414
18 W18 Attiyuttu 9°24'39.49"N 78°55'19.31"E 221/22
2
19 W19* Athangarai 9°19'33.0"N 78°58'34.70"E 113/2B
20 W20* Kil Nagachi 9°18'46.69"N 78°59'31.12"E 127/6A
2
21 W21* Pirappanvalasai
9°18'12.80"N 79° 2'32.9"E 107/2A
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 49 ONGC.
22 W22 Sattakonvalasai
9°17'23.2"N 79°0 4'16.7"E 150/2B
Note:
Well locations marked with (*) are the updated locations. The previous locations were
within the CRZ area. These updated locations (after alternative analysis) are now
outside of CRZ area and does not require CRZ clearance.
Well locations marked with (**) are the locations updated on the basis of findings from
geological studies
2.5.2 Environmental Settings
As per ToR conditions, environmental setting around one km radius area (referred as study
area) of each well site was carried out during field survey and the same has been checked with
toposheet and satellite imagery. All 22 wells are falling in Ramanathapuram district. Well wise
environmental settings are described below and well wise land use is provided in Annex 2.5.
Well 1
The proposed well site is located at the private land of Thirupullani village. The well site is
located adjacent to an existing production well of ONGC KJ-15. Land use within the study area
primarily includes agricultural lands with palm and prosopis trees. A temple is located towards
northeast side of this well. Settlements of Thirupullani village are on NE side, at about 0.6 km
of the well.
Well 2
The proposed well site is located in Periyyapattanam. Major land use within the study area
includes water body, which usually contains water after heavy rains and accessible from kutcha
road. The Periyyapattanam village located at a distance of 0.8 km South west of the well site.
Well 3
The proposed well site is located in the agricultural lands of Reghunathapuram village. Nearest
settlements are located about 0.02 km on all sides except on west direction it is of 0.14 km from
the proposed well site. Land uses in the study area include agricultural lands and settlements.
The site is located near to the Reghunathapuram main road.
Well 4
Well no. 4 is located at an open place within the Panaikulam. Immediate landuse around the
well is of palm trees.Nearest settlement is Krishnapuram village located at a distance of 1.4km
East of well location.
Well 5
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 50 ONGC.
The well site is located at Kalari village. Landuse in the study area is open agricultural lands
with Prosopis trees. Anaikudi village is loacated on NE side from the well point at a distance
of 0.5km. Another village Pallamorrkulam is located 2.0km south of well location. Village
main road is near to this location but new access road has to make for this well point.
Well 6
The well site is located in the agricultural lands of Pullandai village, which is located at a
distance of 1.6 km SE of well point. Landuse is of agricultural lands with mainly Prosopis tress.
Well point is very near to road connecting Velanur to Ervadi. No immediate settlement for this
well, within radius of 1km.
Well 7
The proposed well site is located at Kalari village. Nearest settlement is Anaikudi village which
is 1.1 km .
Well 8
The proposed well site is located at the Puthendhal Village . Major land use within the study
area includes water body which is almost dry throughout the year. Nearest settlement is
Vannikkudi village located at SE direction at a distance of 2.0km from the well location.
Well 9
The proposed well site is located at the land ward side of a creek near to the Thirupallani village.
Land use classes within the study area creek (water body) and open land with Prosopis trees
and salt pans prepared from this creek water. Nearest settlement is around 1.7 km from the well
site which belongs to Anaikudi in SW direction to well point.
Well 10
The proposed well site is located at the Uttarakosamangai village. Major land use in the study
area includes agricultural lands and settlements. The settlement of Uttarakosamangai village is
located at about 0.06 km north of the proposed well site. A water body, which usually contain
water after heavy rain, is located on north side of well at a distance of 0.18 km which is also
near to well 7. Well No. 10 is not having approach road, but near to Ramanathapuram road at
a distance around 0.5km.
Well 11
The well is located at Achadipirambu village. The major land use within the study area includes
Prosopis trees in open scrub land. This well location is near to Kudakottai town at around 2.7
km.
Well 12
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 51 ONGC.
The well is located in the near Pattanamakattan village. The major land uses within the study
area are Prosopis trees. Nearest settlement is Skakarkotai village at around 1.1km. Sakkarkottai
Bird Sanctuary is at 3.55 km west of well location.
Well 13
The proposed well site is located in agricultural lands of Pattanamkattan village. This well is
surrounded by settlements of this village at a distance of 0.03km. Well is located near the
village road which ia conneted to Madurai-Rameshwaram road at distance of 0.14km.
Well 14
The proposed well site is located near Palangulam village. Major landuse is of open lands with
Prosopis trees and water bodies. Vaigai river is about 2.4km on east of the well location. The
nearest village is Kulasekarakal on NorthEast at a distance of 3.4km from the well location.
Well 15
The well site is located at Chittarakotai . Gokulanagar is located at distance of 1.0km towards
south of the well. No immediate settlements are located near to the well within 1km radius.
The Devipattinam to Athiyuthur road is at 0.81 km to west of the well location. The well is
located on coast of Bay of Bengal, which is on eastern direction at a distance of 2km.
Well 16
The well site is located at Devipatnnam village. The landuse is of open scrub land, with
Prosopis trees. Settlements of Sakkaranallur and Venurkulam hamlets of Kalayanur are located
at a distance of 1.6km towards west direction of the well. East Coast road is at distance of
0.2km on west the wets of the well location.
Well 17
This well is located at the open scrub lands of Peruvayal village. Another village, by name
vattukudi, is at distance of 1.1km on North East side of the well. Village road is at west direction
to the well location at a distance of 0.4km.
Well 18
The proposed well site is located at Athiyuthu village, at a distance of 2.1km towards SW
direction. But nearest settlements is of Palanivalasai village is at distance of 1.1 km in north
East of well locaton.Major land use around the well is covered with Prosopis trees.
Well 19
The proposed well site is located at Athagaraj village. Major landuse is with Prosopis trees.
Vagai river is located at distance of 0.48km to the west of the well location.
Well 20
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 52 ONGC.
The well site is located in Kil Nagachi village. Sea is at a distance of 3.0km to the east of the
well location. Nearest settlement is of Kalkenarvalasai village is at a distance of 0.5 km to
South of well location.
Well 21
The well site is located at the sea coast palm and prosopis tree lands of Pirappanvalasai village.
Sea is at a distance of 0.1km to the east of the well location. Nearest settlement is Irumeni
village is at a distance of 1.2km to the North West. Some fishermen hamlets are located very
near to the well location. Irumeni village road is at a distance of 0.8 km to the north of the well
location.
Well 22
The well site is located at the sea coast prosopis tree lands of Sattankonavalasai village, which
is at around 3km north of the well location. Sea is at a distance of 2.0km to the east of the well
location. Well location is located in marshy land. Nearest settlements is Pirpanvalasai village
are at a distance of 3.0km to the north west of well location.
2.6 ALTERNATIVE ANALYSIS
The awarded block in Ramnathpuram District falls under the following environmental sensitive
area:
Ecological sensitive zone of Sakkarakottal Sanctuary
Ecological sensitive zone of Therthangal wildlife sanctuary.
Buffer zone of Gulf of Mannar Marine National Park, Biosphere Reserve.
CRZ area
The detail of well locations falls under the environmental sensitive area is given in Table -2.2
to Table 2.5. This is to be noted that well locations given in following tables represent the
locations identified prior to alternative analysis. The updated locations finalized by ONGC after
alternative analysis is presented in Table 2.1
TABLE 2-2: WELL LOCATIONS IN CRZ AREA
S.No Well
No
District/Taluka Village Name Latitude Longitude
1. W4 Ramnathapuram Panaikulam 9°22'40.17"N 78°57'46.15"E
2. W15 Chittarkottai 9°26'44.59"N 78°54'37.94"E
3. W19 Athangaraj 9°20'2.25"N 79° 0'25.77"E
4. W20 Kil Nagachi 9°19'28.18"N 79° 1'15.18"E
5. W21 Pirappavalasai 9°18'38.93"N 79° 2'36.98"E
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 53 ONGC.
TABLE -2.3: WELL LOCATED WITHIN 10 KM OF THERTHANGALI BIRD SANCTUARY
Well
No
District/Taluka Village Name Latitude Longitude
W17 Ramnathapuram Peruvayal 9°28'25.26"N 78°51'41.43"E
TABLE -2.4: WELLS LOCATED IN ECOLOGICAL SENSITIVE ZONE OF SAKKARKOTTAI BIRD
SANCTUARY
Well
No
District/Taluka Village Name Latitude Longitude
W1
Ramanathpuram
Tiruppullani 9°16'41.67"N 78°49'7.38"E
W2 Periyapattanam 9°16'40.92"N 78°54'27.78"E
W3 Reghunathapuram 9°17'57.55"N 78°55'11.55"E
W5 Kalari 9°17'28.10"N 78°47'16.90"E
W7 Kalari 9°16'51.93"N 78°44'15.77"E
W8 Puthendhal 9°19'55.88"N 78°45'43.36"E
W9 Tiruppullani 9°18'34.43"N 78°47'48.74"E
W10 Utttarakosamagai 9°18'44.24"N 78°44'24.88"E
W11 Achadipirambu 9°18'55.57"N 78°49'49.55"E
W12 Pattanamkattan 9°20'14.98"N 78°52'24.98"E
W13 Pattanamkattan 9°21'16.79"N 78°52'3.12"E
W14 Palangulam 9°23'38.49"N 78°51'55.54"E
TABLE -2.5: WELLS LOCATED WITHIN 10 KM GULF OF MANNAR NATIONAL PARK
Well
No
District/Taluka Village Name Latitude Longitude
W1 Ramanathpuram Tiruppullani 9°16'41.67"N 78°49'7.38"E
W2 Periyapattanam 9°16'40.92"N 78°54'27.78"E
W3 Reghunathapuram 9°17'57.55"N 78°55'11.55"E
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 54 ONGC.
W5 Kalari 9°17'28.10"N 78°43'27.85"E
W6 Pullandai 9°14'37.67"N 78°43'27.85"E
W7 Kalari 9°16'51.93"N 78°44'15.77"E
W9 Tiruppullani 9°18'34.43"N 78°47'48.74"E
W11 Achadipirambu 9°18'55.57"N 78°49'49.55"E
W12 Pattanamkattan 9°20'14.98"N 78°52'24.98"E
W19 Athangarai 9°20'2.25"N 79° 0'25.77"E
W21 Pirappanvalasai 9°18'38.93"N 79° 2'36.98"E
W22 Sattakonvalasai 9°17'31.38"N 79° 4'18.14"E
As a result of alternative analysis, well locations falling under CRZ area have been shifted
outside of CRZ area and presented in Table -2.1. Further, four well locations namely W-3, W-
7, W-8 and W-14 have also been shifted to another locations as presented in Table -2.1. These
four locations have been finalized based on updated findings of geological studies. However,
well locations within 10 km area from wildlife sanctuary are unchanged. The application of
wild life clearance has been filed to Chief Wildlife Warden for obtaining Wildlife Clearance.
2.7 PROJECT ACTIVITIES AND SCHEDULE
The lifecycle of project activities for the exploration project has been divided into distinct steps
and each is described in detail in the subsequent sections and will take approximately three
months to complete drilling and testing activity at each well site.
The project lifecycle has been classified into three phases:
Pre-drilling activity
Site selection
Land acquisition
Site access road and drill site construction
Pre-drilling activities, mobilization and Rigging up
Initial well construction
Drilling activity
Drilling of wells
Well testing
Well decommissioning
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 55 ONGC.
Well abandonment
Site closure and decommissioning
Site Restoration
2.7.1 Pre-drilling Activity
The pre-drilling phase will involve the following activities:
Site Selection
All the locations were selected based on geological data available. Suitable drilling locations
were selected based on the physical (terrain and access) and technical suitability. Detailed drill
site and access road survey will be carried prior to land procurement and construction of drill
site.
Selecting drill site’s environmental considerations is as below:
Away from water bodies.
Away from organized human habitats.
Away from Bird Sanctuaries and sensitive ecological habitat
Land Acquisition
During the site selection process all the legal requirements in will be considered and surface
location finalized. Once the surface drilling location is finalized, land acquisition will be done
including crop compensation. After the finalization drill site, ONGC will take the land from
the land owners on lease. The estimated land required per drill site is approximately 2.2 ha.
All the proposed drill sites are away from human habitation; therefore any displacement will
not be required for this project. As displacement is not required, resettlement and rehabilita t ion
is not applicable for this project
Private Land
Generally, ONGC will get the required land, on lease, through private negotiation. In few cases
ONGC may apply the provision of Rule-189/190 of AL&RR, 1886, if private negotiation is
not successful. During the process of land acquisition standing crops will be compensated as
per the existing rules and lease rent shall be paid till the land is returned.
Access Road and Site Construction
Construction of Access Road
All the wells are located adjacent to the existing road; the distance of the proposed well pad
will be of 200 m (maximum) from existing road. Construction of site access road will not
require any forest land or involve displacement of any household. As far as possible, existing
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 56 ONGC.
roads will be used. Clearing of and cutting of trees will be avoided. If necessary, existing road
will be developed by widening, etc. Culvers and drainage channel will be maintained during
site preparation. The approach road will be constructed by a contractors appointed by ONGC.
Drill Site Construction
The ground is flat in the block area. Vegetation very less in the entire district. Wells located in
coastal side near to sea are on the private agricultural land have palm trees; whereas, wells
located in the interior land side are mainly covered prosopis trees.
After clearance of vegetation, top soil of the entire drill site will be scraped and stored in the
top soil storage area for future use. Once the top soil removal process completed, leveling and
compaction will be done with help of graders and mechanical rollers. Fill material required for
construction will be met from excavated material for pit required for drill site and balance
amount will be sourced from authorized quarry area.
Construction of a flat rectangular/square drilling site (pad) of 100m X 100 m (approximate) at
site to facilitate drilling and testing of hydrocarbons will be required. Reinforced Cement
Concrete (RCC) will be used for the construction of foundation system. For making
foundations of the main rig structure, cast in-situ bored under- reamed piles of specified lengths
will also be used. The proposed well site & campsite will be duly fenced to a height of about 2
m using chain link and barbed wires.
The transport of rig including ancillary equipments and camp facilities to the site is expected
to comprise around 100 trailer loads. Though the rig and related equipments will be directly
brought to site, spares, chemicals and other materials will be received at the warehouse located
at a suitable place in the district. Materials will be intermittently supplied from warehouse to
the drilling site, a provision will be kept for temporary storage of materials at the drilling site
itself.
Rig Mobilization and Rigging up
A rig building process will follow the site preparation activities. This process involves transport
of rig including auxiliary equipments and camp facilities, assembling of various rig parts and
equipment to drill a well. Once the drilling rig is assembled, thorough rig inspection will be
carried out to check equipment working capability and quality standards. The rig will have
various allied equipments like mud tanks, mud pumps, compressors, fuel tank, DG sets etc.
Details of the drilling rig proposed to be deployed is mentioned as below:
Type of rig Electrical Rig
Drilling mud composition Water based Drilling Fluid
Power generator type & Nos. 4x 900 KvA (1 DG will be standby at all the
time)
Diesel consumption 6M3/Day
Qty of fresh water requirement & Source
10 m3/day Transported from nearby source through contractor
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 57 ONGC.
Manpower on rig 25 per shift of 12 hrs. Two shifts/day
Material requirement & Mobilization From ONGC base Karaikal
Details of solids handling system on rig
Shale Shakers- 1200 GPM capacity Desander- 1200 GPM capacity
Desilter- 1200 GPM capacity
Waste Pit Availability & size 30’ x 33’ x 5’ – 2 Nos. 38’x 33’ x 5’ – 1 No. 23’ x 20 x 5’ – 1 No.
Oil Pit availability & size 3 ‘ x 3’ x 4’ – 1 No.
Initial Well Construction
Well spudding is the start of drilling activity. Top-hole section will be drilled to a desired depth
based on well design. After drilling top-hole section, it will be cased with a pipe called
“Casing”. Casing provides support to hole wall and secures hole section. Other than that, it
isolates problematic hole sections such as loss zones, shale sections, over pressurized
formations etc. After running casing, space between hole wall and “Casing” will be cemented.
This process of drilling and casing the hole section continues until the final well depth (target)
is achieved.
Lengths and diameters of each section of the well are determined prior to drilling and are
dependent on the geological conditions through which the well is to be drilled. Once each
section of the well is completed, the drill string is lifted and protective steel pipe or casing
lowered into the well and cemented into place.
2.7.2 Drilling Activity
ONGC will appoint a Drilling Contractor to carry out the drilling work. To support the drilling
operation, the following systems and services will be included at the rig package:
Portable Living Quarters – to house essential personnel on site on a 24 hr basis. These
units are provided with Bath/Washrooms.
Crane-age - cranes for loading/off loading equipment and supplies.
Emergency Systems - this includes fire detection and protection equipment.
Environmental Protection – Blow Out Prevention (BOP) system, wastewater treatment
unit, cuttings handling equipment.
The technical details of the proposed drilling activity are given below:
Duration of drilling 3-4 months for each location and likely to be taken up 2 locations at a time.
Qty. of drilling fluid 350 m3 for each well
Qty. of cuttings 300-400 m3 each well
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 58 ONGC.
Qty. drlg. Waste water 6KLD for each well
Depth 3000-4000 m
Distance of block boundary
from coast line
On-land locations are away from the coast line.
Development plan in case of strike
To be chalked out at the end of Appraisal programme
HC reserve (initial inplace) The provisional Initial Inplace Reserves have been
estimated for 30 BCM (O+OEG).
Formation pressure Hydrostatic
Test flaring duration 2 to 3 days
Drilling of Well
The exploration of hydrocarbons requires the construction of a conduit between the surface and
the reservoir. This is achieved by the drilling process. The exploration well will be drilled
using a standard land rig or a “Mobile Land Rig” with standard water based drilling fluid
treatment system. This rig will be suitable for deep drilling up to the desired depth of 3000--
4000 metres as planned for the project. The typical configuration of a Drilling Rig is shown in
the Figure 2.6.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 59 ONGC.
FIGURE 2-6: TYPICAL DRILLING RIG CONFIGURATION
Additionally, there will be other ancillary facilities like Drilling mud system, ETP, Cuttings
disposal, Drill Cementing equipment etc. and utilities to supply Power (DG sets), water, fuel
(HSD) to the drilling process and will be set up as a part of the project.
Mud System and Cuttings
Drilling of wells requires specially formulated muds which basically comprise in earth
materials like bentonite, barite in water with several additives to give mud weight, fluidity and
filter cake characteristics while drilling. The drilling muds have several functions like
lubrication and cooling of the drill bit, balancing subsurface formation, bringing out the drill
cuttings from the well bore, thixotropic property to hold cuttings during non-operations,
formation of thin cake to prevent liquid loss along well bore etc.
Several additives are mixed into the mud system to give the required properties. Water based
mud will be used to the possible extent in exploratory drilling but use of synthetic based mud
may require due to complexities associated with the geological formation and associated hold
stability problems.
During drilling operations, approx 300-400 m3 per well of wet drill cuttings are expected to be
generated from each well depending on the type of formation and depth of drilling. In addition
to the cuttings 6KLD of waste water is likely to be generated during well drilling. The waste
residual muds and drill cuttings which contain clay, sand etc. will be disposed into the waste
pit.
Mud used during the operation will flush out formation cuttings from the well hole. These
cuttings will be separated from the drilling mud using a solids-control and waste management
package. Cuttings will then be stored in the pits (of approximately 400 m3 capacity) and after
completion of the drilling activities, cuttings will be tested for hazardous nature and based on
nature of the drill cuttings, final disposal pathway will be finalized by ONGC. The total amount
of cuttings produced during the entire drilling period is projected to be about 300-400 m3.
The whole process by which the drilling fluid will be reused during the drilling operation and
is commonly known as a “closed loop system.” This system is ideal for drilling operations in
sensitive environments as it cuts down immensely on the total water consumption for the
formulation of drilling mud and also saves on the consumption of chemicals. Figure 2.7 shows
the schematic layout of the drilling waste management. Figure 2.8 shows the drilling fluid
circulation system which is designed to enable the drilling fluid to be recycled and mainta ined
in good condition throughout the operation.
Various components of the drilling mud will be selected carefully to be able to provide desired
properties to the mud. Mud chemicals will be added to the uniform mud system to adjust the
mud properties and ensure fluid loss control/circulation, lubricity, shale inhibition, pH control
and pressure control in the well during drilling.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 60 ONGC.
FIGURE 2-7: DRILLING WASTE MANAGEMENT
Drilling mud reused
Drill cuttings plus drilling mud
Drilling mud separation in
shale shaker
Drill cutting washing
Washed & free of oil drill cuttings
to drill cutting pit
Washed waste water to waste
water pit
Disposal after testing & treatment to
meet regulatory requirement
Disposal after testing & treatment to
meet regulatory requirement
Drilling Operation
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES 61 ONGC
FIGURE 2-8: TYPICAL DRILLING FLUID CIRCULATION SYSTEM
Cementing Programme
Cementing is a necessary aspect of drilling gas wells. Cement is used to
Secure/support casing strings
Isolate zones for production purposes
Solve various hole problems
Cementing generally utilizes Portland Cement with various additives in small quantities as
accelerators/retarders, density adjusters, dispersants, fluid loss additives, anti gas migrat ion
additives, etc.
Well Testing
Testing facilities will be available at drilling rig for separation of liquid phase and technica l
flare of all hydrocarbon gas during testing. The test flare boom will be located at a safe distance
from the drilling rig.
2.7.3 Well Decommissioning
Well Abandonment
On completion of activities, wells will be either plugged and suspended (if the well evaluat ions
indicate commercial quantities of hydrocarbons) or killed and permanently abandoned. In the
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES 62 ONGC
event of a decision to suspend the well, it will be filled with a brine solution containing very
small quantities of inhibitors to protect the well. The well will be sealed with cement plugs and
few wellhead equipment (Blind Flange) left on the surface (Cellar). If the well is abandoned,
it will be sealed with a series of cement plugs, all the wellhead equipment will be removed
leaving the surface clear of any debris and site will be restored.
Site Closure and Decommissioning
After completion of the drilling activity, partial de-mobilisation of the drilling rig and
associated infrastructure will be initiated. As discussed earlier, well testing may be carried out
immediately after the drilling is completed or about 3 months depending on initial evaluation
timing. The complete de-mobilisation of the facilities at site will happen after well-testing has
been completed. This will involve the dismantling of the rig, all associated equipments and the
residential camp, and transporting it out of the project area. It is expected that demobiliza t ion
phase will last about 10 days and will involve the trucking away of materials, equipments and
other materials from site to bring it back to original condition.
Subsequently, following steps will be typically involved to restore and rehabilitate the area:
The wellhead and all casing string will be cut off to a minimum depth of 3 m (10 ft) below
ground level.
All concrete structures will be broken up, and the debris disposed off as per the regulatory
requirements.
All other waste products, solid and liquid, will be disposed of in accordance with the
requirements of the EIA and will be treated to render them harmless.
All fencing and access gates will be removed.
All pits whose contents will show regulatory compliance for on-site disposal, at the time of
site closure, will be backfilled and closed out as per the legal requirements.
Restoration of unusable portion of the access track, removal of pilings and Landscaping.
Site Restoration
All abandoned drill sites will be restored back to its near original condition. After
decommissioning of site, it will be de-compacted and stored top soil will be overlaying on the
de-compacted site with certain moisture conservation measures and seeding of leguminous
plant for restoration soil nutrient level naturally.
2.8 UTILITIES & RESOURCE REQUIREMENTS
2.8.1 Power Supply
The drilling process requires movement of drill bit through the draw works which require
power. The power requirement of the drilling rig will be met by total 4 DG sets of 900 KVA
capacity. However, only three Diesel Generator sets will remain operational during peak load
and one DG set will be as standby.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES 63 ONGC
2.8.2 Water Consumption
The water requirement in a drilling rig is mainly meant for preparation of drilling mud apart
from washings and domestic use. While the former consumes the majority of water
requirement, the water requirement for domestic and wash use is very less. The daily water
consumption will be 25 m3/d of which 12 m3/d will be used for mud preparation, 9 m3/d in
other drilling activities and 4 m3/d will be used for domestic purposes including drinking. The
water balance diagram is shown in Figure 2-9.
2.8.3 Waste water
The operating personnel in the drilling rigs will operate from the onsite accommodation. It is
estimated that 2 m3/d waste water will be generated from the domestic consumption. Soak pits
and septic tank will be provided at the site for the disposal of domestic waste water. Approx.
6-8 m3/d waste water is estimated to be generated from drilling activities. Onsite ETP will be
provided for the treatment of waste water generated from drilling activities.
2.8.4 Fuel Consumption
Fuel consumed during the drilling phase will mainly be diesel used by rig used for exploratory
drilling, various equipments and vehicles operating to transport goods and supplies to site. It is
estimated that about 6 KL diesel will be required to operate the DG sets.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES 64 ONGC
FIGURE 2-9: WATER BALANCE DIAGRAM
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 65 ONGC.
2.8.5 Chemical Storage
The drilling rig will have normal storage facilities for fuel oil, required chemicals and the
necessary tubulars and equipment. The storagef places will be clearly marked with safe
operating facilities and practices.
2.8.6 Manpower / Employment
The drilling rig will be operated by approximately 25 persons on the rig at any time. The
manpower will operate in two shifts with continuous operations on the rig.
2.8.7 Noise and Vibrations
Noise will be emitted from exploratory drill site during site preparation, drilling and
decommissioning phases. The major noise generating operations from the proposed activity
during drilling, testing are operation of rotary drilling equipment as part of rig, diesel engines
for power generation, mud pumps and operation of vehicles. Noise during the site preparatory
phase will primarily be contributed by heavy construction machinery operating on site and
vehicular sources. Average noise emission ranges for different types of construction machinery
are shown in the Figure 2.10.
As drilling activity is continuous, part of the noise associated with functioning of the rig and
ancillaries will be generated throughout day and night.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 66 ONGC.
FIGURE 2-10: TYPICAL NOISE EMISSIONS FROM CONSTRUCTION MACHINERY
60 70 80 90 100 110
Earthmoving
Compactors (Rollers)
Front loaders
Backhoes
Tractors
Scrapers, Graders
Pavers
Trucks
Materials Handling
Concrete Mixers
Concrete Pumps
Cranes (Movable)
Cranes (Derrick)
Stationery
Pumps
Generators
Compressors
Pneumatic Wenches
Jackhammers and Rock Drills
Pile Drivers (Peaks)
Vibrators
Sows
Others
Noise Level (dBA) at 50 feet
CONSTRUCTION EQUIPMENT
Equipment Powered by Internal Combustion Engines
Impact Equipment
Source: USEPA
2.8.8 Air Emissions
Air emissions from point sources expected from the proposed exploratory drilling will be
mainly from combustion of diesel in the diesel engines and power generators which will be
operated to meet power requirement of the drilling rig and the campsite. The principa l
pollutants will comprise of Suspended Particulate Matter (SPM), Sulphur and Nitrogen
dioxides (SO2 and NO2) and other hydrocarbons (HC). The quantity of diesel consumed during
drilling will be in order of 6 KL /day/drilling site.
Additionally, the flaring and technical flare of oil during the testing of the well will also lead
to the release of some pollutants including un-burnt hydrocarbons to the atmosphere. Some
fugitive emissions of dust and air pollutants from vehicular exhaust will also happen during the
project lifecycle, mostly during the construction and decommissioning activities. Additiona lly,
there will be re-entrainment of dust from the approach road leading to the site mainly during
the dry season.
Analysis of natural gas generated from the well site reveals that, it is mostly methane, ethane
and propane without the presence of hydrogen sulfide.
2.9 DRILLING HAZARDS
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 67 ONGC.
Loss of well control / blow-out, fire, explosion and oil spills are the major potential hazards
associated with drilling for oil and gas. Effective response plans to foreseeable emergenc ies
will be developed by ONGC and communicated to the project teams. A risk assessment to be
carried out as part of this EIA will also contribute towards identification of hazards, risks and
formulating management plans for emergency response, blowout, oil spills.
2.10 PROJECT COST
The anticipated cost of drilling of each well (which stacking of the location, land acquisit ion,
site preparation and drilling activity works out to Rs.20.00 crores, for one well and the total
project cost is Rs.440Crores.
2.11 HSE POLICY
ONGC is committed to protecting environment, health and safety of the people who may be
affected, directly or indirectly by its operations. The Drilling Management System (DMS)
framework lays down the corporate Health, Safety and Environment Policy for the entire
organization and the range of operations it undertakes as a part of oil and gas exploration. The
overall corporate health environmental safety policy of ONGC may be supplemented by a local
policy document whenever so required. It is understood that ONGC will try to formulate a local
site level policy taking from the parent corporate policy of ONGC to adequately address the
environmental impacts of the proposed drilling projects in PML Field through the DMS. The
Corporate HSE policy of ONGC is presented below:
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 68 ONGC.
Box 2.1: ONGC HSE Policy
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 69 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 70 ONGC.
3 Description of the Environment
This chapter describes the existing environmental settings in the ONGC field and its immed iate
surroundings. This includes the physical environment comprising air, water and land
components, the biological environment, and socio-economic environment. Attributes of the
physical environment like air, water, soil, and noise quality in the surrounding area were
assessed primarily through monitoring and analysis of samples collected from field. Air, noise,
water and soil primary monitoring was carried out by Vitro Labs Pvt. Ltd, Hyderabad (MOEF
certified laboratory). Information about geology, hydrology, prevailing natural hazards like
floods, earthquakes etc. have been collected from literature reviews and authenticated
information made available by Government offices to understand the biological environment
prevailing in the area and the same were collected through interviews with respective
authorities and published information and literature. The socioeconomic environment has been
studied through the data collected from secondary sources and consultations with various
stakeholders in the villages within the study area. Additionally, socioeconomic data have been
obtained from the Census of India reports.
3.1 PHYSICAL ENVIRONMENT
3.1.1 Climate & Meteorology
Climate and meteorology of a place can play an important role in the implementation of any
developmental project. Meteorology (weather and climate) plays a key role in understanding
local air quality as there is an essential relationship between meteorology and atmospheric
dispersion involving the wind speed/direction, stability class and other factors. The block falls
under the tropical climate zone.
Seasons and rainfall
The sesason in the area comprise of summer, monsoon and winter. The main monsoon season
in the area comprise of north east monsoon which starts from October and remain till
December. As per the IMD Chennai, northeast monsoon is the major period of rainfall activit iy
over south peninsula. Coastal districts in Tamilnadu receives nearly 60% of the annula rainfa ll
during Oct – Dec. The northeast monsoon chiefly contributes to the rainfall in the district.
Most of the precipitation occurs in the form of cyclonic storms caused due to the depressions
in Bay of Bengal. Another monsoon period in the area is known as “Southwest Monsoon”
during which rainfall is highly inconsistent while summer rains are negligible. Rainfall data of
IMD Ramnathpuram stations for the period Oct – Dec 2014 shows the normal annual rainfa ll
over the district is 611 mm.
The Western Ghats acting as a barrier deprive the State of the full blast of South-west monsoon
winds. The Ramanathpuram District depends mainly on the North East Monsoon rains which
are brought by the troughs of low pressure establishing in south Bay of Bengal between October
and December.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 71 ONGC.
The district characterized by tropical climate. The period from May to June is generally hot
and dry. The weather is pleasant during the period from December to January. Usually
mornings are more humid than afternoons. The relative humidity is on an average varying
between 79 and 84%. The mean minimum temperature is recorded as 25.7°C and mean
maximum daily temperature is 30.6°C, respectively (Source: CGWB Annual report 2009).
Primary meteorological monitoring were conducted during July 2014 - September 2014 at
Regunathapuram village within the block, the temperature, rainfall, relative humidity, wind
speed and wind direction of the region have been mentioned in the following para. The detailed
meterological data collected from site is enclosed as Annexure 3.3.
Wind Speed and Wind Direction
The wind speed and wind direction of an area influences the dispersal of pollutants from a point
and non point sources. As the proposed drilling and testing activities involve the operation of
both point (DG sets) and non point pollutant emissions sources, analysis of wind speed and
direction data is considered important for predicting the air quality impacts based on pollutant
dispersion. Meteorological monitoring weather station was established at Regunathapuram
village.
Interpretation of Primary Baseline Data
Hourly micro-meteorological data collected during primary monitoring has been analyzed to
generate the wind rose. The predominant wind direction is from west followed by southwest
for the study period. The average wind speed for the months was 4.1 m/s. The wind speed was
observed in the range 0.67 – 12.22 m/s for the monitoring period. The calm frequency was
recorded as 5.2 %. The wind rose diagram generated for the primary monitoring study period
has been presented in Figures 3.1.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 72 ONGC.
FIGURE 3-1: WIND ROSE DIAGRAM
3.1.2 Ambient Air Quality
Primary monitoring of the existing air environment was undertaken in the field to establish
existing ambient air quality within the proposed field. Location of the proposed wells and the
predominant wind direction is important in selection of the ambient air quality sampling
stations as any gaseous and particulate emission from the project activities will disperse based
on the predominant wind directions and affect to the receptors located at that end. Thus the
analyzed values for the pre project environment can be compared during and after the project
activities. The major industrial sources of air emission at the field are gas based power
generation plant of Valathur, which is in north direction at 5.8 km from weather monitor ing
station, Regunathapuram village.
Ambient air quality monitoring was conducted by Vitro Lab (NABL and MoEF approved) at
8 representative locations during premonsoon period July –August 2014, prior to onset of
northeast monsoon. Air quality monitoring was carried out for PM10, Sulphur Dioxide (SO2),
Nitrogen di oxide (NO2), CO, HC & VOC. ONGC being a responsible corporate and concous
about the environment, wanted an additional air quality monitoring to be carried out to have a
better representation of the ambient air quality of the surrounding project area. The additiona l
ambient air quality monitoring was carried out by Netel India (NABL and MoEF approved
Laboratory) in the month of January and February 2016 (post monsoon period) to verify the
inconsistency of the results, if any. The result of air quality monitoring is presented in Table 3-
4 and 3-5.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 73 ONGC.
TABLE 3-1: DETAILS OF AAQMS
Sampling Numbers Monitoring Locations
AAQ1 Devipattanam
AAQ2 Panaikkulam
AAQ3 Enmanamkondan AAQ4 Sattakonvalasai
AAQ5 Raghunathapuram AAQ6 Periyapattanam AAQ7 Tirupalani
AAQ8 Ervadi
The monitoring was conducted for 24 hours a day twice a week for PM10 by Respirable dust
sampler, Particulate matter(PM2.5) by PM 2.5 Sampler, Sulphur Dioxide (SO2) by West & Gaeke
Method, Nitrogen dioxide (NO2) by Jacob and Hochheiser Method . VOC is monitored by VOC
analyser. Methane, Non-Methane Hydrocarbons were monitored using Gas Chromotography
as per IS 5182 Part -21. The analaytical measurements of each parameter is given below in
Table 3-2.
TABLE 3-2: ANALYTICAL / MEASUREMENT METHODS
POLLUTANTS
METHODS BIS CODES
Particulate matter(PM10) Respirable dust Sampler 5182 (Part - IV) - 1973
Particulate matter(PM2.5) PM2.5 Sampler 5182 (Part - IV) - 1973
Sulphur Dioxide ( SO2 ) West & Gaeke Method 5182 (Part - II) - 1973
Nitrogen Oxides( as NO2 ) Jacob and Hochheiser
Method 5182 (Part - VI) - 1975
Methane & Non Methane
Hydrocarbon Gas Chromatograph
IS 5182 Part -21
The concentrations of various pollutants were processed for different statistical parameters like
minimum concentration, maximum concentration and percentile values. A summary of
ambient air quality results is presented in Table 3.1 and the detailed results are presented in
Annexure 3.1.
Interpretation of Air Quality Results
Particulate Matter (PM10): The average concentration of 24 hourly PM10 at all the monitor ing
locations ranged between 35-57 μg/m3. 98 percentile PM10 values of the stations ranged
between 42.8-56.6 μg/m3. The average as well as 98 percentile PM10 concentrations were
observed to be in compliance to the NAAQS (100 μg/m3) at all air quality monitoring locations.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 74 ONGC.
Particulate Matter (PM2.5): The average PM 2.5 concentration monitored at all the monitor ing
stations exist within the range of 18-27 μg/m3. The concentration of PM2.5 is also in compliance
with the NAAQ standard of 60 μg/m3.
Nitrogen dioxide (NO2): The average value of NO2 concentration is found within the range
of 9-16 μg/m3 at all the monitoring locations. The monitored concentration of NO2 complies
with the NAAQS (80 μg/m3) specified for nitrogen dioxide.
Sulfur dioxide (SO2): The average Sulfur dioxide concentration values at all the monito r ing
locations is observed in the range of 6-13 μg/m3which is well within the NAAQS (80 μg/m3)
limits specified for nitrogen dioxide.
The concentration of CO, MHC and NMHC observed within the range of 1.0-1.2 mg/m3, 1.51-
1.69 ppm and 0.43-0.58 ppm. Concentration of VOCs were found as below detectable limit
(BDL).
Photographs of Ambient Air Quality Monitoring Stations
Air Monitoring at Devipatnam
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 75 ONGC.
Air Monitoring at Enamankonda
Air Monitoring at Ervadi
Air Monitoring at Periyapattnam
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 76 ONGC.
TABLE 3-3: AMBIENT AIR QUALITY RESULTS - PREMONSOON
Sl.
No
Monitoring
Locations
PM10
(μg/m3)
PM2.5
(μg/m3)
SO2
(μg/m3)
NO2
(μg/m3)
CO
(mg/m3)
HC as
CH4 in
ppm
NMHC
(ppm) VOC
(μg/m3)
1
Devipattanam Average 51.6 25.0 9.5 14.4 1.1 1.66 0.51 BDL
Max 57.0 27.0 12.0 16.0 1.2 2.0 0.8 BDL
Min 47.0 23.0 7.0 13.0 1.0 1.2 0.2 BDL
98 Percentile 56.6 27.0 11.8 16.0 1.2 1.2 0.2 BDL
2
Panaikkulam
Average 46.8 23.4 8.1 13.6 1.1 1.69 0.5 BDL
Max 53.0 26.0 11.0 15.0 1.2 2.1 0.7 BDL
Min 39.0 20.0 6.0 13.0 1.0 1.3 0.3 BDL
98 Percentile 52.8 26.0 10.8 14.8 1.2 1.3 0.3 BDL
3 Enmanamkondan
Average 50.3 24.6 8.1 12.4 1.1 1.56 0.46 BDL
Max 56.0 27.0 10.0 14.0 1.2 2.2 0.7 BDL
Min 45.0 22.0 6.0 10.0 1.0 1.2 0.1 BDL
98 Percentile 55.8 27.0 10.0 14.0 1.2 1.2 0.1 BDL
4 Sattakonvalasai
Average 43.8 21.8 7.8 10.9 1.1 1.63 0.52 BDL
Max 49.0 24.0 10.0 13.0 1.2 1.9 0.7 BDL
Min 38.0 19.0 6.0 9.0 1.0 1.2 0.1 BDL
98 Percentile 49.0 23.8 9.8 12.8 1.2 1.2 0.1 BDL
5 Raghunathapuram
Average 49.7 24.3 8.9 12.2 1.1 1.6 0.58 BDL
Max 55.0 27.0 11.0 14.0 1.2 1.9 0.8 BDL
Min 45.0 22.0 7.0 10.0 1.0 1.1 0.1 BDL
98 Percentile 54.6 26.8 10.8 13.8 1.2 1.1 0.1 BDL
6 Periyapattanam
Average 47.2 23.6 8.9 12.3 1.1 1.72 0.51 BDL
Max 53.0 27.0 11.0 15.0 1.2 2.1 0.9 BDL
Min 41.0 20.0 6.0 9.0 1.0 1.2 0.1 BDL
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 77 ONGC.
Sl.
No
Monitoring
Locations
PM10
(μg/m3)
PM2.5
(μg/m3)
SO2
(μg/m3)
NO2
(μg/m3)
CO
(mg/m3)
HC as
CH4 in
ppm
NMHC
(ppm) VOC
(μg/m3)
98 Percentile 52.6 26.6 11.0 14.8 1.2 1.2 0.1 BDL
7 Tirupalani
Average 38.7 19.4 10.7 13.6 1.1 1.51 0.46 BDL
Max 43.0 22.0 13.0 16.0 1.2 1.9 0.8 BDL
Min 35.0 18.0 8.0 12.0 1.0 1.1 0.1 BDL
98 Percentile 42.8 21.8 12.8 16.0 1.2 1.1 0.1 BDL
8 Ervadi
Average 46.2 22.9 10.0 13.7 1.1 1.53 0.43 BDL
Max 52.0 25.0 12.0 15.0 1.2 2.2 0.9 BDL
Min 39.0 19.0 8.0 13.0 1.0 1.1 0.1 BDL
98 Percentile 51.6 25.0 11.8 14.8 1.2 1.1 0.1 BDL
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 78 ONGC
TABLE 3-4: AMBIENT AIR QUALITY RESULTS – POST MONSOON
Sl.
No
Monitoring
Locations
PM10
(μg/m3)
PM2.5
(μg/m3)
SO2
(μg/m3)
NO2
(μg/m3)
CO
(mg/m3)
HC as
CH4 in
ppm
NMHC
(ppm)
VOC
(μg/m3)
1 Devipattanam Average 43.9 11.98 6.74 11.5 1.72 1.66 0.51 BDL
Max 51.2 16.1 10.3 17.8 2.14 2.0 0.8 BDL
Min 33.7 8.7 4.2 7.0 1.2 1.2 0.2 BDL
98 Percentile 50.97 16.10 11.8 17.3 2.14 1.2 0.2 BDL
2 Panaikkulam
Average 46.8 23.4 8.1 13.6 1.1 1.69 0.5 BDL
Max 53.0 26.0 11.0 15.0 1.2 2.1 0.7 BDL
Min 39.0 20.0 6.0 13.0 1.0 1.3 0.3 BDL
98 Percentile 52.8 26.0 10.8 14.8 1.2 1.3 0.3 BDL
3 Enmanamkondan
Average 50.3 24.6 8.1 12.4 1.1 1.56 0.46 BDL
Max 56.0 27.0 10.0 14.0 1.2 2.2 0.7 BDL
Min 45.0 22.0 6.0 10.0 1.0 1.2 0.1 BDL
98 Percentile 55.8 27.0 10.0 14.0 1.2 1.2 0.1 BDL 4 Sattakonvalasai
Average 43.8 21.8 7.8 10.9 1.1 1.63 0.52 BDL
Max 49.0 24.0 10.0 13.0 1.2 1.9 0.7 BDL
Min 38.0 19.0 6.0 9.0 1.0 1.2 0.1 BDL
98 Percentile 49.0 23.8 9.8 12.8 1.2 1.2 0.1 BDL
5 Raghunathapuram
Average 49.7 24.3 8.9 12.2 1.1 1.6 0.58 BDL
Max 55.0 27.0 11.0 14.0 1.2 1.9 0.8 BDL
Min 45.0 22.0 7.0 10.0 1.0 1.1 0.1 BDL
98 Percentile 54.6 26.8 10.8 13.8 1.2 1.1 0.1 BDL
6 Periyapattanam
Average 47.2 23.6 8.9 12.3 1.1 1.72 0.51 BDL
Max 53.0 27.0 11.0 15.0 1.2 2.1 0.9 BDL
Min 41.0 20.0 6.0 9.0 1.0 1.2 0.1 BDL
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 79 ONGC
Sl.
No
Monitoring
Locations
PM10
(μg/m3)
PM2.5
(μg/m3)
SO2
(μg/m3)
NO2
(μg/m3)
CO
(mg/m3)
HC as
CH4 in
ppm
NMHC
(ppm)
VOC
(μg/m3)
98 Percentile 52.6 26.6 11.0 14.8 1.2 1.2 0.1 BDL
7 Tirupalani
Average 38.7 19.4 10.7 13.6 1.1 1.51 0.46 BDL
Max 43.0 22.0 13.0 16.0 1.2 1.9 0.8 BDL
Min 35.0 18.0 8.0 12.0 1.0 1.1 0.1 BDL
98 Percentile 42.8 21.8 12.8 16.0 1.2 1.1 0.1 BDL
8 Ervadi
Average 46.2 22.9 10.0 13.7 1.1 1.53 0.43 BDL
Max 52.0 25.0 12.0 15.0 1.2 2.2 0.9 BDL
Min 39.0 19.0 8.0 13.0 1.0 1.1 0.1 BDL
98 Percentile 51.6 25.0 11.8 14.8 1.2 1.1 0.1 BDL
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 80 ONGC
TABLE 3-4: AMBIENT AIR QUALITY RESULTS – HC AND VOC
Sl.
No
Monitoring
Locations
HC as CH4
in ppm
NMHC
(ppm)
VOC
(μg/m3)
1 Devipattanam 3.80 <0.5 1.48
2 Panaikkulam
6.97 <0.5 0.69
3 Enmanamkondan
3.72 <0.5 <0.5
4 Sattakonvalasai
2.83 <0.5 <0.5
5 Raghunathapuram
3.11 <0.5 <0.5
6 Periyapattanam
4.32 <0.5 1.26
7 Tirupalani
5.82 <0.5 2.70
8 Ervadi
4.93 <0.5 <0.5
Analysis of Air Quality Results
Particulate Matter (PM10): The average concentration of 24 hourly PM10 at all the monitor ing
locations ranged between 37.08-46.84 μg/m3. The average PM10 concentrations were observed
to be in compliance to the NAAQS (100 μg/m3) at all air quality monitoring locations.
Particulate Matter (PM2.5): The average PM 2.5 concentration monitored at all the monitor ing
stations exist within the range of 9.41-12.84 μg/m3. The concentration of PM2.5 is also in
compliance with the NAAQ standard of 60 μg/m3.
Nitrogen dioxide (NO2): The average value of NO2 concentration is found within the range
of 8.70-12.53 μg/m3 at all the monitoring locations. The monitored concentration of NO2
complies with the NAAQS (80 μg/m3) specified for nitrogen dioxide.
Sulfur dioxide (SO2): The average Sulfur dioxide concentration values at all the monitor in g
locations is observed in the range of 5.34-7.0 μg/m3which is well within the NAAQS (80
μg/m3) limits specified for nitrogen dioxide.
Carbon Monoxide (CO): The average CO concentration values at all the monitoring locations
is observed in the range of 1.13-1.99 mg/m3which is well within the NAAQS (2 mg/m3) limits
specified for nitrogen dioxide.
The concentration of MHC observed within the range of 2.8-6.9 ppm while concentration of
NMHC and VOCs are less than 0.5 ppm.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 81 ONGC.
3.1.3 Ambient Noise Quality
The ambient noise monitoring was conducted during the August 2014 at 10 locations within
the ONGC Field. Noise stations were selected near to the proposed well locations to understand
the baseline noise levels that could be impacted upon by the proposed drilling activities at the
Field.
Sound pressure level (SPL) measurements in dB (A) were recorded for every hour continuous ly
for 24 hours at 15 minutes interval for the monitoring stations and equivalent noise levels in
the form of Leq day and Leq night was computed. The results obtained were compared with
National Ambient Air Quality Standards (NAAQS) with respect to noise. The ambient noise
quality monitoring locations within the study area are shown in Figure 3.2 and the rationale for
selection of the stations has been presented in Annexure 3.2.
TABLE 3-5 DETAILS OF NOISE MONITORING LOCATIONS
Sampling Numbers Monitoring Locations
N1 Panaikulam
N2 Enmanamkondam
N3 Sattakonvalasai N4 Regunathapuram N5 Periyapattinam
N6 Tirupalani
N7 Ervadi
N8 Tanichattanmadal
N9 Kodikulam
N10 Kilakkarai
TABLE 3-6: AMBIENT NOISE QUALITY RESULTS
LOCATION DAY TIME NIGHT TIME
Leq dB(A) Limit dB(A) Leq dB(A) Limit dB(A)
N1 45.8 55 41.6 45
N2 45.0 55 42.5 45
N3 44.6 55 42.5 45
N4 47.0 55 44.0 45
N5 45.3 55 42.2 45
N6 53.9 55 50.8 45
N7 53.8 55 49.8 45
N8 44.0 55 41.3 45
N9 45.9 55 31.8 45
N10 54.2 55 50.1 45
1. Daytime shall mean from 6.00 a.m. to 10.00 p.m.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 82 ONGC.
2 Night time shall mean from 10.00 p.m. to 6.00 a.m.
The results of the noise monitoring indicates that daytime noise levels are in the range of 44 –
54.2 dB(A) and fall within the NAAQS limit i.e. 55 dB(A) prescribed for the residentia l
landuse, at all the monitoring locations. The night time noise level 31.8 – 50.8 dB (A) is
observed as higher than the NAAQS limit of 45 dB(A) at three locations. This higher level of
noise may be attributed to ongoing traffic activities in the study area and high wind speed due
to sea shore region.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
_________________________________________________________________________________________________________________________________________________________________________________________________________________
SENES/H-20084/ July 2016 83 ONGC.
FIGURE 3-2: LOCATION OF AIR, NOISE, METEOROLOGY LOCATIONS WITHIN THE ONGC FIELD
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 84 ONGC.
3.1.4 Physiography and Geology
The physical features and geology are closely related. Most of the area is covered by the
unconsolidated sediments of Quaternary age except in the northwestern part, where isolated
patches of Archaen Crystallines and Tertiary sandstone are exposed. The Archaeans are mainly
represented by the Charnockite Group of rocks comprising garnetiferrous granulite and the
Khondalite Group of rocks made up of quartzite of genesses.
The Tertiary sandstone (Cuddalore Formation) comprise pinkish, yellowish, reddish
(variegated colours) medium to coarse grained sandstone and clay stone. It is overlain by thin
alluvium and exposed towards north of Vaigai River.
Detached exposures of laterite and lateritic soil are seen in the northwestern part of the district.
A major part of the district is covered with the fluvial, fuvio-marine, Aeolian and marine
sediments of Quaternary age. The fluvial deposits which are made up of sand, silt and clay in
varying degree of admixture occur along the active channels of Vaigai, Gundar, Manimuthar
and Pambar rivers. They have been categorized into levee, flood basin, channel bar/ point bar
and paleo-channel deposits. The paleo channel deposits comprise brown coloured, fine to
medium sands with well preserved cross-beddings.
The fluvio-marine deposits are exposed in the Vaigai delta as deltaic plain, paleo-tidal and dune
flat deposits. The deltaic plain and dune flats comprise medium, Grey brown sands. The paleo
tidal flat deposits include black silty clay, black clay and mud. In Rameswaram Island, the
fluvio-marine deposits include indurated sand and dune sands.
The Aeolian deposits comprise red sands which are in nature of ancient dunes and occur over
a 3.2 km wide and 8 km long stretch and lie parallel to the sea coast. These are separated by
marshy deposits of black clays. The sands are underlain by calcareous hardpan. In
Rameswaram Island also brown sand deposits occur around Sambaimadam on either side of
NH 49 west of the town.
The marine formation comprises coastal plain deposits of sand and clay in varied proportion.
Marine calcareous hardpan occurs as low terraces and platforms, with admixture of quartz,
limonite and garnet concentration.
Ramanathapuram PML is in Ramnad sub-basin which is in the southern part of Cauvery Basin.
Ramnad sub-basin and its continuation into Palk Bay-Gulf of Mannar is bounded in the
northwest by Pattukottai-Mannargudi ridge and in the southeast by Mandapam-Delft ridge. The
sub basin holds sediments over 6000 m in thickness, ranging in age from Lower Cretaceous
and older to Recent. The synrift sedimentary column comprises mainly of shale and sandstone
in the Andimadam Formation. Sag phase sedimentation represented in the upper Cretaceous
Bhuvanagiri, Kudavasal Shale, Nannilam and Portonovo shale is predominantly sand shale
alternations with minor limestone development. Major part of the passive margin sequences
ranging from Paleocene to Recent were deposited on the eastern shelf-slope regime with
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 85 ONGC.
eastward prograding coast line. The siliciclastic sequences of the passive margin stage are
interspersed with major limestone intervals corresponding to Eocene and Miocene periods.
Two regional fault trends - older NNE-SSW curvilinear fault set intersected by a younger EW
fault set which are deep seated and Basement controlled play a vital role in the formation of
the structures, subsequent charging and entrapment in Ramnad Sub basin. The established
pools at upper Cretaceous reservoir levels are all located along or at the intersection of these
two trends.
The hydrocarbon potential of Upper Cretaceous reservoirs ranging in age from Turonian to
Campanian (Bhuvanagiri & Nannilam formations) is well established while the efforts to
establish hydrocarbon prospectivity of Lower Cretaceous & older sequences are still at the
nascent stage. About 55 exploratory & development wells were drilled in Ramanathapuram
PML, out of which 29 are gas bearing in Nannilam, Bhuvanagiri and Lower Kamalapuram
formations. The Lower Cretaceous being the source rocks, there is a fair chance of hydrocarbon
accumulation in these sequences at favourable places.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 86 ONGC.
FIGURE 3-3: TOPOGRAPHIC MAP OF ONGC FIELD
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 87 ONGC.
3.1.5 Hydrogeology
The district is underlain by both porous and fissured formations. The important aquifer systems
in the district are constituted by i) unconsolidated & semi consolidated formations and ii)
weathered and fractured crystalline rocks.
The porous formations can be grouped into three aquifer groups, viz., Cretaceous sediments,
Tertiary Sediments and Quaternary Sediments. The cretaceous aquifer is semi confined to
confined in nature and consists of two zones. The top unit comprises fossiliferous sandstone
red in colour and compact in nature, while the bottom is pinkish or grayish sandstone
intercalated with shales. The aquifers are characterized by freshwater and occurs at the depth
range of 116-407 and 205-777 m below ground level (bgl) and has thickness in the range of 68
to 535 m. The aquifer is made up of compact sandstone and the potential is limited. The wells
may yield a discharge of 5-10 liters per second (lps) and can sustain a pumping of 10-15 hours
a day. However, because of the presence of potential shallow tertiary aquifer, this aquifer has
not been extensively developed.
Cuddalore Sandstone of Tertiary sediments consists Sandstone, Clay & Conglomerate. They
are encountered at the depth of 15-75 m bgl with the thickness ranging from 20 to 70 m. The
groundwater occurs under unconfined condition with thickness varying from 15-20m and under
confined condition in deeper depths. The unconfined aquifer can be tapped by dug well/ dug
cum bore well and can yield about 10-15 lps and can sustain a pumping of 10-15 hours a day.
The deeper tube wells can yield about 15-20 lps and can sustain a pumping of 10-15 hours a
day.
Quaternary sediments comprises fluvial and coastal sands and laterites. The alluvium with
alternate layer of sand and clay with a thickness of 15-25 m and are characterized by floating
freshwater lenses limited to a depth 6-7 m bgl and can sustain a pumping of 2 – 3 hours and
can yield about 2-5 lps.
The water-bearing properties of crystalline formations which lack primary porosity depend on
the extent of development of secondary intergranular porosity . The occurrence and movement
of ground water in these rocks are generally confined to such spaces. These aquifers are highly
heterogeneous in nature due to variation in lithology, texture and structural features even within
short distances. Ground water generally occurs under phreatic conditions in the weathered
mantle and under semiconfined conditions in the fissured and fractured zones at deeper levels.
The thickness of weathered zone in the district is in the range of 4 to 15 m. The depth ofthe
wells ranged from 10.00 to 15.00 m bgl.
The yield of large diameter wells in the district, tapping the weathered mantle of crystalline
rocks ranges from 40 to 110 lpm and are able to sustain pumping for 2 to 6 hours per day. The
Specific capacity of large diameter wells tested in crystalline rocks ranges from 20.25 to 95
lpm / m. of drawdown. The yield characteristics of wells vary considerably depending on the
topographic set-up, litho logy and nature of weathering. The transmissivity of weathered
formations computed from pumping test data using empirical methods range < 1 m2/day.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 88 ONGC.
The yield of bore wells drilled down to a depth of 40 to 70 m, by various state agencies mainly
for domestic purposes ranged from 10 to 250 lpm.
The depth to water level in the district varied between 0.67 – 12.12 m bgl during pre monsoon
depth to water level (May 2006) and varied between 0.49 – 8.78 m bgl during post monsoon
depth to water level (Jan 2007). The seasonal fluctuation shows a rise in water level, which
ranges from 0.35 to 2.8m bgl. The piezometric head varied between 3.49 to 16.23m bgl (May
2006) during premonsoon and 1.29 to 8.06 m bgl during post monsoon. (Source: Annual
Report, April-2009, CGWB)
Ground Water Resources
The annual replenishable ground water resources of Ramanathpuram district as per the estimate
of Central Ground Water Board (as on 31st March 2004) is 48,943 hectare metre (ham) whereas
the net groundwater availability is found to be 33540 ham. The stage of ground water
development is 15%. Future provision (upto year 2029) for use of ground water resources in
domestic and industrial sector is 963 ham and net ground water availability for future irrigat ion
use is 21,143 ham.
Groundwater is primarily used for drinking and other domestic purposes. Groundwater is
primarily tapped by tube wells from depths ranging mostly between 40-70 m. District
Ramnathapuram is falling under Semi Critical category as per stage of ground water
development of the area.
3.1.6 Ground Water Quality
Primary monitoring of ground water quality was considered important in order to understand
the probable impacts of the proposed project activities on the sub surface aquifers. Potential
pollution of subsurface and unconfined aquifers may occur due to improper casing and
cementing of well leading to infiltration or seeping of drilling chemicals or mud into nearby
aquifer. Contamination of aquifers may also occur from disposal of drilling waste and mud in
an open/unpaved pit.
A monitoring network consisting of 6 locations for groundwater was selected and
representative sampling was carried out at each of the locations and the detailed results of
ground water analysis are presented in Table 3.8.
Ground Water Sampling Points
A total of 6 nos. ground water samples were collected from shallow tube wells of the study
area prospect zone villages comprising of Enmanamkondan, Raghunathapuram,
Periyapattanam, Kilakkarai, Ervadi and Tirupalani. Samples were analyzed for
physicochemical and bacteriological parameters and results compared with IS: 10500 drinking
water standards to identify and interpret any deviation in the statutory limits set for parameters
under this standard.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 89 ONGC.
Interpretation of Ground Water Quality Results
Turbidity
Turbidity values for range between 2.80 to 6.00 ground water. However, turbidity values of
groundwater collected from all the other sites were within the desirable limits of IS 10500
standards.
Chlorides and Total Dissolved Solids
With respect to IS: 10500 standards the desirable limit of chloride is 250 mg/l while the
permissible limit of the said parameter (in absence of alternate source) is 1000 mg/l. At
concentration above 250 mg/l chlorides renders a salty taste to water which may be considered
to be objectionable in terms of human consumption.
The chloride concentration in the ground water samples of the study area range between
199-425 mg/l.
The concentration of total dissolved solids (TDS) in ground water is a measure of its suitability
for domestic use. In general, TDS values at 500 mg/l or below is considered to be most
desirable for such purpose being specified under IS: 10500 drinking water standard. The TDS
values for the ground water samples analyzed varies in the range of 1001 mg/l to 1496 mg/l
thereby conforming to the exceeding desirable limit of this ground water parameter.
Total Hardness
Hardness of water is considered to be an important parameter in determining the suitability of
water for domestic uses particularly washing. Hardness of water is correlated to the presence
of bivalent metallic ions viz. calcium and magnesium. Total hardness values for the ground
water samples analyzed ranged between 344 mg/l to 672 mg/l and were found to be exceeding
standard of 300 mg/l specified under IS: 10500. Further as discussed above, the hardness values
recorded at each ground water monitoring station was found to be in correlation with the
calcium and magnesium ions analyzed for such samples. The concentration of calcium and
magnesium ions was found to be within exceeding permissible limits specified for the aforesaid
parameters as per IS: 10500 standards.
Iron and Fluoride
Iron is considered to be an important ground water parameter since at higher concentration it
interferes with laundering operations and imparts objectionable stains. Iron concentration of
ground water samples collected range 0.01 to 0.07 were found within the desirable limit of IS
:10500 Standard.
Heavy Metals
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 90 ONGC.
The presence of heavy metals like mercury (< 0.001 mg/l), arsenic (< 0.01 mg/l), copper (<
0.02 mg/l), lead (<0.005 mg/l), hexavalent chromium (<0.05 mg/l) and cadmium (< 0.002
mg/l), in the ground water samples of all the six sources were found to be below detection
limits.
Coliforms
Coliforms are indicators of contamination from sewage and feacal matter. Coliforms
werenpresent in all collected samples and in the concentration range between 2 to 4
MPN/100ml Absence of faecal coliform at all the samples. Total Coliform is analysed by Four
plate method & Incubation Method as per IS:15185 - 2002. Fecal Coliform is measured is
analysed by Four plate method & Incubation Method as per IS:15185 – 2002 method
TABLE 3-7: SAMPLING LOCATIONS OF GROUND WATER
Sampling Number Sampling Location
GW-1
Enmanamkondam
GW-2 Regunathapuram GW-3 Periyapattanam
GW-4 Kilakkarai
GW-5 Ervadi GW-6 Tirupalani
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 91 ONGC.
Groundwater sampling Enamankonda Groundwater sampling Ervadi
Groundwater sampling Kilkari Groundwater sampling Panipattnam
Groundwater sampling Regunathapuram Groundwater sampling Tirupalani
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 92 ONGC.
TABLE 3-8: GROUNDWATER MONITORING RESULTS
SL. No. Test Parameters Unit GW1 GW2 GW3 GW4 GW5 GW6
1. Colour Hazen <5.0 <5.0 <5.0 <5.0 <5.0 <5.0
2. Odour - Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable
3. Taste - Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable
4. Turbidity NTU 2.90 6.00 3.90 3.30 2.80 3.60
5. PH - 8.1 7.7 7.4 7.1 7.6 7.2
6. Temperature 0C 29 28 29 28 29 27
7. Total Solids mg/l 1291 788 1504 1435 1015 1670
8. Total Hardness as CaCO3
mg/l 344 200 624 672 496 592
9. Total Alkalinity
mg/l 300 140 320 280 140 480
10. Iron as Fe
mg/l Nil 0.07 0.01 0.01 0.01 0.02
11. Chlorides as Cl
mg/l 333 199 425 411 340 425
12. Residual Free Chlorine
mg/l Nil Nil Nil Nil Nil Nil
13. Total Dissolved Solids
mg/l 1278 1100 1496 1423 1001 1662
14. Calcium as Ca
mg/l 135 52 183 173 118 157
15. Magnesium as Mg
mg/l 2 18 40 58 48 48
16. Copper as Cu
mg/l <0.005 0.05 <0.005 <0.005 <0.005 <0.005
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 93 ONGC.
SL. No. Test Parameters Unit GW1 GW2 GW3 GW4 GW5 GW6
17. Manganese as Mn
mg/l 0.01 0.02 0.04 0.03 0.03 0.03
18. Sulphate as SO4
mg/l 170 108 179 286 188 233
19. Nitrate as NO2
mg/l 12 12 21 19 11 15
20. Flourides as F mg/l 0.45 0.44 0.86 0.92 0.78 0.83
21. Sodium as Na mg/l 279 158 226 225 160 345
22. Potassium as K
mg/l 6 4 6 5 3 6
23. Phenolic Compounds as C6H5OH mg/l Nil Nil Nil Nil Nil Nil
24. Mercury as Hg mg/l Nil Nil Nil Nil Nil Nil
25. Cadium as Cd Nil Nil Nil Nil Nil Nil
26. Selenium as Se mg/l BDL BDL BDL BDL BDL BDL
27. Arsenic as As mg/l BDL BDL BDL BDL BDL BDL
28. Cyanide as CN mg/l Nil Nil Nil Nil Nil Nil
29. Lead as Pb mg/l 0.04 0.04 0.06 0.07 0.04 0.06
30. Zinc as Zn mg/l 0.25 0.26 0.33 0.36 0.24 0.39
31. Anionic detergent as MBAS mg/l Nil Nil Nil Nil Nil Nil
32. Hexavalent Chromium as Cr+6 mg/l Nil Nil Nil Nil Nil Nil
33. Total Coliform Organism MPN/100ml 3 4 2 3 2 4
34. Faecal coliform/100ml MPN/100ml Absent Absent Absent Absent Absent Absent
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 94 ONGC.
FIGURE 3-4: LOCATION OF GROUNDWATER, SURFACE WATER AND SOIL MONITORING LOCATIONS WITHIN THE ONGC FIELD
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 95 ONGC.
3.1.7 Drainage
The Vaigai basin is an important basin among the 12 basins lying between the Cauvery and
Kanyakumari. The basin is bounded by the Varushanadu hills, the Andipatti hills, the
Cardaman hills and the Palani hills on the west and the Palk Strait and Palk Bay on the east.
The basin lies between 90 17' to 100 22' north latitudes approximately. This basin is divided
into two major topographical divisions namely (i) the hilly areas and (ii) the plains.The basin
is elongated in shape and drains into the Palk Bay. The Vaigai drains an area of 7,741 sq km
which entirely lies in the state of Tamil Nadu.
The Vaigai river on the western slopes of the Varushanadu hills at an elevation on 1,200m
above msl near Kottamalai in the Madurai district at a north latitude 90 32' and east longitude
770 23' and flows in the northernly and north easternly directions up to its confluence with the
Varushanadhi and then takes a turn towards east and south east to flow through Madurai,
Sivakangai and Ramanathapuram districts. After traversing about 258 km, the river Vaigai
discharges into Ramnad big tank and some other tanks. The surplus water from the tanks fina lly
discharges into the Palk Bay near Mandapam. On its way, the Vaigai receives two important
tributaries namely the Suruliyar and the Manjalar on its left bank, besides a large number of
small streams and rivulets. The river has been dammed downstream of its confluence with the
Suruliyar.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 96 ONGC.
The major part of Ramanathapuram district falls in Gundar-Vaigai river basin. Vaigai and
Gundar are the important rivers and in addition, Virusuli, Kottakariyar & Uppar are the othe r
rivers draining the district. The drainage pattern, in general, is dendritic. All the rivers are
seasonal and carry substantial flows during monsoon period. Vaigai., which is one of the
important rivers of the district, which is flow and drain in the Paramakudi, Bogalur, Tirupullani
and Mandapam blocks. The Gundar river originates in Kottamalai hills in the Saptura forest
and enters the district near Anankulam and flows in a south –eastern to due south direction and
enters the Bay of Bengal neare Mukaiyur. The river assumes the name of “ Reghunatha Cauveri
“ from Kamudhi.
The Kottakarai, Virusuli and Uppar are other rivers flowing in south easterly direction and
entering the Bay of Bengal. Major drainage in the study area is Manimuthar, Vaigai & Vaippar.
The drainage map within the block has been prepared and presented as Figure 3.5.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 97 ONGC.
FIGURE 3-5: DRAINAGE MAP WITHIN THE BLOCK
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 98 ONGC.
3.1.8 Surface water quality
Primary monitoring of surface water quality was given importance during scoping of the EIA
study as the effluent generated during the exploratory well drilling operations are likely to be
discharged to nearby surface water bodies/natural drainage channels/rivers after ensuring that
it meets prescribed norms of CPCB. Further, an effort has been made to establish the baseline
quality of the existing major watersheds and sub watersheds (comprising the major drainage of
the study area) to identify any possible contamination due to any current industrial activit ies.
A monitoring network consisting of 4 locations for surface water monitoring were selected.
Water sampling and analysis was done following CPCB standard guidelines for physical,
chemical and bacteriological parameters. The monitoring locations are shown in Figure 3.5.
Surface Water Sampling Points
Surface water samples were collected from all major water channels of the study area i.e. Vagai
river(Upstream & Downstream), Water body in Periyapattanam, Water body/river near
Kanjirangudi, Water body near Sattakonvalasai to get an overview of the surface water quality
of the study area. Surface water quality was finally assessed against water quality criteria as
per CPCB guidelines for water resources. Results of surface water samples have been discussed
below.
Interpretation of Surface Water Quality Results
The pH of the surface water samples varied from 7.4-7.9. The total coliform count of the
surface water samples range between 15 to 35 MPN/100ml. The presence of contaminants in
the form of oil and grease and heavy metals viz. lead, iron, arsenic, chromium and mercury in
the surface waters of all sources were found to benegligible. The toxic organic component,
phenol, was also found be below detectable limit (<0.001 mg/l) in all the surface water samples.
BOD is varied from 2.2-2.6mg/l. COD is varied from 32-42mg/l.
Detailed surface water analysis results have been provided at Table 3.10.As discussed in the
previous section the channels from which samples were taken and analyzed were primarily
used for irrigation, bathing, cleaning and for catching fish. The analyzed values of the samples
after comparing with the CPCB Water Use Criteria justifies their use in compliance to water
use criteria.
TABLE 3-9: SAMPLING LOCATION OF SURFACE WATER
Sampling Number Sampling Location
SW-1
Vagai river (up stream)
SW-2 Vagairiver(down stream) SW-3 Periyapattanam SW-4 Kanjirangudi
SW-5 Sattakonvalasai
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 99 ONGC.
TABLE 3-10: SURFACE WATER QUALITY RESULTS
SL. No.
Test Parameters Unit SW1 SW2 SW3 SW4 SW5
1. Colour Hazen <5.0 >5.0 >5.0 >5.0 >5.0
2. Odour
- Agreeable Not Agreeable
Not Agreeable
Not Agreeable
Not Agreeable
3. DO mg/l 5.3 5.4 5.2 5.7 5.6
4. BOD mg/l 2.2 2.4 2.4 2.6 2.3
5. COD mg/l 32 35 38 42 38
6. Turbidity NTU 5 9 14 8 12
7. PH - 7.6 7.8 7.4 7.6 7.9
8. Temperature 0C 26 28 29 27 28
9. Total Solids mg/l 365 29300 606 21400 382
10. Total Hardness as CaCO3
mg/l 112 3600 216 2800 128
11. Total Alkalinity mg/l 120 8600 180 7200 110
12. Iron as Fe mg/l 0.01 0.07 0.01 0.06 0.01
13. Chlorides as Cl mg/l 71 9042 106 7340 63
14. Residual Free Chlorine
mg/l Nil Nil Nil Nil Nil
15. Total Dissolved Solids
mg/l 338 28808 551 21120 345
16. Calcium as Ca mg/l 25 803 35 722 32
17. Magnesium as Mg
mg/l 11 390 31 244 12
18. Copper as Cu mg/l <0.005 0.05 <0.005 <0.005 <0.005
19. Manganese as Mn
mg/l BDL 0.08 0.04 0.06 0.03
20. Sulphate as SO4 mg/l 66 4850 106 4160 78
21. Nitrate as NO2 mg/l 13 72 22 44 18
22. Flourides as F mg/l 0.5 0.8 0.7 0.8 0.6
23. Sodium as Na mg/l 68 8087 108 7100 72
24. Potassium as K mg/l 3 22 2 16 2
25. Phenolic Compounds C6H5OH
mg/l Nil Nil Nil Nil Nil
26. Mercury as Hg mg/l Nil Nil Nil Nil Nil
27. Cadium as Cd Nil Nil Nil Nil Nil
28. Selenium as Se mg/l BDL BDL BDL BDL BDL
29. Arsenic as As mg/l BDL BDL BDL BDL BDL
30. Cyanide as CN mg/l Nil Nil Nil Nil Nil
31. Lead as Pb mg/l 0.05 0.09 0.04 0.07 0.03
32. Zinc as Zn mg/l 0.40 0.52 0.29 0.48 0.26
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 100 ONGC.
SL. No.
Test Parameters Unit SW1 SW2 SW3 SW4 SW5
33. Anionic detergent as MBAS
mg/l Nil Nil Nil Nil Nil
34. Hexavalent Chromium Cr+6
mg/l Nil Nil Nil Nil Nil
35. Total Coliform Organism
MPN/100ml
15 18 35 16 31
36. Faecal coliform/100ml
MPN/100ml
2 4 8 3 6
Surface water sampling Vaigai Down Stream
Surface water sampling Vaigai UP Stream
3.1.9 Additional Surface Water Monitoring
The additional surface water monitoring conducted in January 2016 to recheck the result of
BOD, COD and TDS at two locations i.e. Vagai River downstream and Kanjirangudi River.
In the study area month of January 2016 represent post monsoon period. The details of
monitoring result is represented in Table – 3.11.
TABLE 3-11: ADDITIONAL SURFACE WATER MONITORING RESULTS
SL. No.
Test Parameters Unit SW1 SW2
1. pH --- 8.35 8.15
2. Colour Hazen <5 <5
3. Turbidity NTU 9.7 4.5
4. Temperature ⁰C 23.3 22.9
5. Electrical Conductivity mS/cm 19.78 4.68
6. Total Suspended Solids mg/l 105 176
7. Total Dissolved Solids mg/l 16838 49101
8. Alkalinity mg/l 223 125
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 101 ONGC.
SL. No.
Test Parameters Unit SW1 SW2
9. Hardeness mg/l 2855.6 5121.2
10. Dissolved Oxygen mg/l 4.7 5.2
11. Biochemical Oxygen Demand mg/l 71 96
12. Chemical Oxygen Demand mg/l 191.84 253.28
13. Nitrate mg/l BDL BDL
14. Nitrite mg/l 0.049 0.014
15. Sulphate mg/l 1106.47 1017.04
16. Chloride mg/l 6792.93 14802.50
17. Phosphate mg/l <0.5 <0.5
18. Fluoride mg/l 1.34 1.56
19. Sodium mg/l 3922.5 6567.5
20. Potassium mg/l 85.33 235.2
21. Nitrogen mg/l 2.8 3.5
22. Phosphorus mg/l <0.5 <0.5
23. Calcium mg/l 387.04 368.16
24. Magnesium mg/l 453.12 1008.20
25. Silica mg/l 1.08 1.30
26. Oil & Grease mg/l BDL BDL
27. Phenolic Compounds mg/l 0.83 1.43
28. Lead mg/l 0.27 0.47
29. Arsenic mg/l BDL BDL
30. Mercury mg/l BDL BDL
31. Cadmium mg/l 0.60 0.05
32. Hexavalent Chromium mg/l BDL BDL
33. Total Chromium mg/l BDL BDL
34. Copper mg/l BDL BDL
35. Zinc mg/l 0.040 0.040
36. Iron mg/l 0.76 0.09
37. Total Coliform MPN/100ml 12 23
Analysis of Additional Monitoring Result
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 102 ONGC.
The analysis of result shows that BOD value at both the monitoring location is reported as 71
– 96 mg/l. This BOD value indicates the presence of higher organic content and therefore
higher demand of oxygen would be requried to degrade the organic content. The higher BOD
result monitored after monsoon may attribute to decaying of plant and other organic matter
due to Chennai flood incident. The Chennai flood incident also influenced this area. Further,
BOD/COD ration also lies in the range of 0.3 – 0.6 which indicates that presence of toxic
components and acclimated mircroorganism may be requried in stabilization of these water
bodies.
TDS result is observed as high in both the samples. TDS was also observed as high value in
the sample collected during the pre-monsoon season. The high value of TDS may attribute to
tidal influence in Vagai River (downstream) and increased water flow in Kanjirangudi River.
3.1.10 Land-Use
The land-use and land-cover of the study area has been interpreted from the satellite data
(Google Imagery), toposheet of the area, and subsequently by ground truthing during field
surveys. The study area land use shows that the land (48.0%) in the area is used Prosopi Jungle,
Agriculture ( 25.0%), Aquaculture (5%), Bird Sanctuary (0.3%), Settlements (15.0%),
Coconuts (6.1%), Mangroves Forest (0.2%), Bird Sanctuary (0.2%), Salt ponds (0.2%), Water
Body (0.2%). The land use analysis result is shown in the following Table. The land use map
of the study area is presented in Figure 3.5.
Type of Landuse Distribution
Prosopis Jungle
48 %
Agriculture 25 %
Aquaculture 5%
Bird Sanctuary 0.5%
Settlements 15.0 % Coconuts 6.1%
Mangroves Forest 0.2%
Salt ponds & Water Body 0.4 %
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
___________________________________________________________________________________________________________________________________
SENES/H-20084/ July 2016 103 ONGC.
FIGURE 3-6: LAND USE MAP WITHIN THE ONGC FIELD
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 104 ONGC.
3.1.11 Soil Quality
Soils in the area have been classified into i) Black Clayey soil, ii) Sandy soil and iii) Red –
ferruginous soil.
In the Ramanathapuram district, majority of the area is covered by Black Clayey soil type.
These soils are mostly black or black to brownish in colour and are found in parts of
Ramanathapuram, Paramakudi, Kamuthi, Tiruvadanai and Mudukulathur blocks. Sand occur
in flat elevation along the Rameshwaram and Kadaladi blocks, Alluvial soils occur along the
river courses of Vaigai and Gundar river covering in the blocks Paramakudi, Tiruvadanai and
Muthukulayhur. The Red ferruginous soil of the Chettinad plains occurs as few pockets around
Paramakudi and Tiruvadanai blocks.
As discussed above, since soils of the Ramanathpuram Taluka, of which the exploratory block
is a part is characterized by Black Clayey Soil. Major part of district soil is infertile in nature,
however the implementation of the proposed project may lead to the temporary change/loss of
soil fertility at the drilling site. The understanding of soil quality therefore assumes significance
considering the block soil fertility characteristics and also given the responsibility of the
proponent to restore the site back to its original condition following decommissioning. An
effort has been therefore been made to establish the soil quality of the block through primary
monitoring study as discussed in the section below.
TABLE 3-12: DETAILS OF SOIL MONITORING LOCATIONS
Sampling Numbers Monitoring Locations
S-1 Panikulam
S-2 Enmankondan
S-3 Sattakonvalsai S-4 Regunathapuram S-5 Ervadi
Primary Soil Sampling and Analysis
The soil characteristics within the study area, especially the physical quality and fertility of the
soil have been characterized by analyzing the soil samples collected from 5 locations namely,
Panaikkulam, Enmanamkondan, Sattakonvalasai, Raghunathapuram, Ervadi. Primary soil
monitoring includes analysis of the heavy metals with the objective of establishing baseline
values for such contaminants.
Interpretation of Soil Analysis Results
It has been observed that the pH of the soil in the study area ranged from 6.7 to 7.7
the maximum pH value of 7.7 was observed at village (S1), where as the minimum value of 6.7 was observed at Village (S5).
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 105 ONGC.
It has been observed that the pH of the soil in the study area ranged from 6.7 to 7.7
the maximum pH value of 7.7 was observed at village (Eravadi), where as the minimum value of 6.7 was observed at Village (Panikulam).
The electrical conductivity was observed to be in the range of 143 µmhos/cm to 334
µmhos/cm, with the maximum observed at village (Eravadi) and minimum observed in Village (Regunathapuram).
The nitrogen values range between 32.2-177 kg/ha. The nitrogen content in the study area falls in very less to better category.
The phosphorus values range between 2.3 to 66.7 kg/ha, indicating that the phosphorus content in the study area falls in very less to sufficient category.
The potassium values range between 111.6 – 267.3 kg/ha. The potassium content in the study area falls in less to more than sufficient category.
The chlorides were found to be in the range of 70.9– 301.3 mg/kg of soil.
TABLE 3-13: SOIL ANALYSIS RESULTS
Sr.
No.
Parameter Units S1 S2 S3 S4 S5
1 pH (1:5 Aq.Extract) ---- 6.7 7.0 6.8 7.1 7.7
2 Condutivity (1:5 Aq.Extract) scm 145 175 221 143 334
3 Texture ---- Clay Sandy Clay
Clay Sandy Clay
Sandy clay
4 Sand % 35 55 36 50 52
5 Silt % 22 15 24 12 11
6 Clay % 43 30 40 38 37
7 Bulk Density mg/cc 1 1.2 1.1 1 1
8 Exchangeable Calcium as Ca mg/kg 1598 839 1518 1479 1840
9 Exchangeable Magnesium as Mg
mg/kg 461 218 680 413 1312
10 Exchangeable Sodium as Na mg/kg 181.8 498.5 245.7 81 327
11 Available Potassium as K Kg/ha 155.6 223 111.6 122.4 267.3
12 Available Phosphorous as P Kg/ha 2.3 44.7 66.7 14 9.3
13 Available Nitrogen as N Kg/ha 161.6 32.2 177 134.6 107.2
14 Organic Matter % 1.67 0.28 1.66 1.39 1.11
15 Organic Carbon % 0.97 0.16 0.96 0.81 0.64
16 Water Soluble Chloride as Cl mg/kg 88.6 227.7 212.6 70.9 301.3
17 Water Soluble Sulphate as SO4 mg/kg 62.2 131.6 104.2 109.3 141.6
18 Sodium Absorption Ratio ---- 0.46 1.77 0.59 0.21 0.64
19 Aluminium % 1.77 1.82 1.43 0.97 0.75
20 Total Iron % 2.08 1.43 0.64 0.41 2.11
21 Manganese mg/kg 442.1 362 86.5 102.3 294.1
22 Boron mg/kg 14.5 12.9 16.2 11.9 14.8
23 Zinc mg/kg 44.2 61.8 56.3 37.3 46.5
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 106 ONGC.
Soil Sampling at Ervadi
Soil Sampling at Panikulam
Soil Sampling at Sttakonavalsai
Soil Sampling at Regunathapuram
3.1.12 Natural Hazards
A natural disaster during the life cycle of the project can have a significant effect on the
functioning of the project in addition to affecting the local environment in the area and stressing
the availability of resources for the project. Such disasters also sometimes create difficulties in
access through disruption of transportation links.
Seismicity & Earthquakes
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
__________________________________________________________________________________________
SENES/H-20084/ July 2016 107 ONGC.
The study area is located in Zone II as shown in the Bureau of Indian Standards (BIS) 2000
seismic zone map for India. Seismic Map of India is shown in Figure 3-6.
FIGURE 3-7: SEISMIC ZONE MAP OF INDIA
[Source : Amateur Seismic Centre www.asc-india.org]
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 108 ONGC.
3.2 ECOLOGICAL ENVIRONMENT
The Ramanathapuram district is rich in biodiversity and has a number of sensitive ecosystems
comprising both terrestrial and coastal & marine components. In the study area important
wildlife habitat is Gulf of Mannar Marine National Park(GMMNP) and Biosphere Reserve.
Sakkarkotai Bird Sanctuary, Gulf of Mannar National Park 10km buffer zone falls in ONGC
Ramanathapuram PML block area.
The primary objectives of the biological environment study are:
To assess the vegetation types
Phytosociological study of tree and herbs
To identify common flora & fauna in the study area
To find out rare and endangered floral and faunal species (if any)
To evaluate wildlife habitat of the area and assess impact of the proposed project on
wildlife & their habitats.
To assess impact of the proposed project on agriculture and domestic livestock.
3.2.1 Methodology
Study Area
The study area for terrestrial ecological surveys is considered taking the entire area of ONGC
block.
Desktop Review and Reconnaissance Survey
A desktop review (documents collected from GMMNP and other published documents, etc.)
was conducted to determine the area (Toposheet and Satellite imagery), vegetation type
(Champion and Seth, 1962), floral and faunal assemblage in the study area. A site
reconnaissance visit was conducted on July 30th – 7th August and 4th-11th September 2014 to
identify different ecological habitats, sensitive ecological habitat and also to identify the
targeted study area for baseline survey.
Baseline Survey
Baseline survey was carried out to determine the existing ecological conditions and was
designed to fill any data gaps, and to facilitate an adequate assessment of the project’s impacts
upon ecology and the development of appropriate mitigation measures. Baseline survey was
conducted on July 30th – 7th August and 4th-11th September 2014 for habitat survey, flora &
faunal assemblage, in the study area. Baseline survey has two parts- (i) Secondary data
collection and (ii) Primary Survey.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 109 ONGC.
Secondary Data Collection
Secondary baseline data regarding sensitive ecological habitat (National Park, Sanctuary,
Ecological Sensitive Area, Migratory Corridor, etc.), flora & fauna in the study area, published
and unpublished documents.
Primary Survey
Primary survey was carried out the targeted study area for habitat (terrestrial and aquatic), flora
and faunal survey (terrestrial and aquatic), phyto-sociological survey through transect and
quadrant method (natural forest), planktonic monitoring. Special attention was paid to those
areas, which will be directly impacted by proposed drilling activity.
3.3 FOREST RESOURCES
The district has only 273 sq km forest cover, i.e. 6.4% of the total geographical area of the
district. However, the ML area has no demarcated forest land. There some scrub land in the
ML area. In the study area has four types of habitat –forests (mostly scrub land), coastal habitat
and agricultural land.
3.4 HABITAT
3.4.1 Forest Habitat
When Tropical dry-mixed evergreen forests are destroyed, often, tropical thorn forests
(scrublands) grow in their place. Tropical thorn forests also grow in arid areas where the dry
season is very long. Plants in thorn forests have to conserve water, so they have small leaves
or thorns, to reduce water loss, or store water in fleshy leaves and stems. During the dry season,
leaves fall off.
3.4.2 Inland Wetland Habitats
Several streams and rivers drain into the Palk Strait and Gulf of Mannar. Rivers and streams
are bodies of water that move continuously in one direction. At the beginning of the stream the
channel is narrow and the water is pure and carries less sediment than downstream, as well as
only a few minerals. Many such streams (tributaries of a river) join together to form a larger
river.
3.4.3 Coastal and Marine Habitat
In this region there are also many coastal and marine habitats. They are
Mangroves: above Devipattanam, and small patch at Karanjigudi
Salt marshes: near to sea side creeks,
Sand dunes and beaches (including seashore vegetation): are mainly on east part of the
district,
Mud flats: are mainly on east part of the district,
Sea grass meadows, and
Coral Reefs.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 110 ONGC.
3.5 VEGETATION
Forest types occurring in this region are Tropical dry-mixed evergreen forests and Tropical
thorn forests (scrublands). The flora of the area is dominated by species like Acacia nilot ica,
Prosopis juliflora, Tamarindus indica, Azadirachita indica, Albizzia amara, Ficus bengalens is,
Ficus religiosa, Morinda tinctoria, Borassus flabellifer, Syzygium cumuni, Acacia planifons,
etc. About 45 plant angiosperm plant species were reported from this area.
Phytosociological study of terrestrial vegetation
The detailed phytosociological study of 9 wells of the study area are included in Annexure
4-B.
3.6 WILDLIFE HABITAT & WILDLIFE
The study area has important wildlife habitat – Gulf of Mannar Marine National Park and
Biosphere Reserve. The sanctuary and its adjoining forests are very rich in diversity.
Ramanathapuram district has also three bird sanctuaries, namely Chitrangudi Bird Sanctuary,
Kanjirankulam Bird Sanctuary and Melaselvanur - Kilaselvanur Bird Sanctuary.
3.6.1 Birds Sanctuary
The location and details of birds sanctuaries in the district is shown below:
TABLE 3-14: DETAILS OF BIRDS SANCTUARIES
Sanctuary Area of the
Sanctuary (sq.
km)
Location Distance from
ML area (km)
Chitrangudi Bird Sanctuary 0.48 9°19′48″N 78°29′23″E 22.5
Kanjirankulam Bird Sanctuary
1.04 9°20′N 78°29′E. 23.4
Melaselvanur - Kilaselvanur Bird Sanctuary
5.93 9°13’47” & 9°12’27” N and 78°32’29” & 78°34’28” E
10.8
Therthangal Bird Sanctuary 0.29 9°28'15.09"N& 78°47'15.19"E
4.0
Sakkarakottai Bird Sanctuary 16.50 09°22'00"N, 78° 52'00"E
Within the ML area
Melaselvanoor and Keelaselvanoor bird sanctuary
The area under present study is KMBS, Ramanathapuram lies between latitude which is
9°13’47” and 9°12’27” N and longtitude 78°32’29” and 78°34’28” E in Kadaladi taluk of
Ramanathapuram District in Tamil Nadu. This sanctuary was declared in the year 1998. This
is the biggest birds Sanctuary in Tamil Nadu. The total area of the Sanctuary is 593.08 ha. The
flora of the area is dominated by species like Acacia nilotica, Prosopis juliflora, Tamarindus
indica, Azadirachita indica, Albizzia amara, Ficus bengalensis, Ficus religiosa, Morinda
tinctoria, Borassus flabellifer, Syzygium cumuni, Acacia planifons, etc.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 111 ONGC.
The three different habitats i.e., aquatic fresh water habitat (FWH), shrubby habitat (SH) and
mixed forest habitat (MFH). A total of 116 species of birds belonging to 47 families was
reported from this sanctuary. Of the total 116 species of birds 51 species were mixed forest
residents, 18 species were reported to use more than one habitat, 26 species were reported to
be aquatic residents and 21 species of birds use only shrubby habitat. Major bird species were
Dater, Cormorant, Egret, Heron, Ibis, Spoonbill, Cotton Teal, Spot-Billed Duck, Plover,
Lapwing, Sandpiper, Wagtail, Kingfisher, etc.
Kanjirankulam Bird Sanctuary
Kanjirankulam Bird Sanctuary is a 1.04 sq. km Protected area near Mudukulathur,
9°20′N 78°29′E. It is adjacent to Chitrangudi Bird Sanctuary. It is notable as a nesting site for
several migratory Heron species that roost in the prominent growth of Babul trees there.
International name: Chitragudi and Kanjirankulam Bird Sanctuary, IBA Code: IN261, Criteria:
A1, A4i.
The sanctuary vegetation is mostly Tropical Dry Deciduous forest. It is dominated by Babul
along with Prosopis juliflora and the grasses Bermuda grass and Eremopogon foveolatus.
The invasive Prosopis is slowly encroaching on much of the sanctuary area, retarding growth
of Babuls. The irrigation tank bund and the area outside the tank
have Tamarind trees, Fig trees, Neem trees, Portia trees, Silk trees Drumstick trees and palms
3.6.2 Gulf of Mannar
The Gulf of Mannar lies between India and Sri Lanka. It encompasses the territorial waters of
the southeast coast of India, from Dhanushkodi in the north to Kanyakumari in the south
(Figure 3.7). It has a chain of 21 islands covering an area of 623 ha, with each island having an
area of 0.5 ha minimum and 129 ha maximum. They are located 2 to 10 km from the mainland
along the 140 km stretch between Tuticorin and Rameswaram (Lat 8°55'-9°15’N and Long
78°0'-79°16’E). The islands are occurring in 4 groups namely Mandapam group, Keezhakarai
group, Vembar group and Tuticorin group. There are no permanent inhabitants in these islands
and temporary camping by forest officials and fishermen for a few days is common in some of
the islands.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 112 ONGC.
FIGURE 3-8: GULF OF MANNAR
3.7 GULF OF MANNAR MARINE NATIONAL PARK
The government of Tamil Nadu in G.O. M.S. No 962 dated 10th September 1986 notified under
section 35(1) of the Wildlife (Protection) Act 1972 the intention to declare the 21 islands as
Gulf of Mannar Marine National Park (GOMMNP) for the purpose of protecting marine
wildlife and its environment including depths of 3.5 fathoms on the bay side to 5 fathoms on
the seaward side.
The primary objective of the establishment of the GOMMNP is to conserve the rich marine
biodiversity of the Gulf of Mannar region by providing protection and through management
and restoration of the degraded marine coral reef system, which have been historically mined
and exploited to an unsustainable level.
3.8 GULF OF MANNAR BIOSPHERE RESERVE
The GOMBR was set up as part of the UNESCO-MAB programme in 1989 through a
notification issued by the MoEF, following acceptance by the Government of Tamil Nadu. The
GOMBR was set up with the broad objectives of conserving representative samples of
ecosystems, providing long-term conservation of genetic diversity in situ, promoting basic and
applied research work and its monitoring, and disseminating experiences for education and
training. The GOMBR is the first marine biosphere reserve not only in India but also in all of
South and Southeast Asia.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 113 ONGC.
According to the notification, the area of the GOMBR is 10,500 sq km, running southwards
and parallel to the mainland coastline to a distance of about 170 nautical miles. It includes the
national park as the core area. The original notification includes the 21 islands, starting from
the northern-most Pamban island to Tuticorin (the pearl banks near and away from Tuticorin,
and between Tuticorin and Kanyakumari). The buffer zone includes the immediate sea between
Keezhakarai and Mukairyur, Valimunai, Poovarsanpatti, Van, Kasuwar, Karaichalli and
Vallanguchali islands and the remaining waters in the Tuticorin– Kanyakumari belt. Recent
reports from the GOMBRT office show that the reserve has a coastline of about 300 km and a
10-km wide buffer zone on either side of the coastline (Melkani et al., 2006). The buffer zone
comprises Gulf waters to the south and an inhabited coastline to the north, according to the
draft management plan prepared by the WII and submitted to the GOI.
The broad guidelines and principle of this biosphere reserve is to safeguard the traditional and
eco-friendly nature based livelihood practices of local communities as well as the ecologica lly
fragile Marine habitat within the GOMBR.
3.9 MARINE ECOSYSTEM: GULF OF MANNAR
The national park was declared to protect wildlife and its environment, because of its
ecological, faunal, floral and zoological association and importance. The GOM has coral reefs,
and mangrove and seaweed ecosystems, apart from rocky shores, sandy beaches, mud flats and
estuaries.
These ecosystems support a wide variety of fauna and flora including rare cowries, cones,
volutes, murices, whelks, strombids, chanks, tonnids, prawns, lobsters, pearl oysters, seahorses,
seacucumbers, etc. The biosphere reserve and particularly the Marine National Park of the Gulf
of Mannar also gains more importance because of the alarmingly declining population of the
endangered Dugongs.
3.9.1 Off Shore Islands and Coral Reefs
A chain of 21 low islands has been observed along the offshore region of GOM. All islands are
made up of a calcareous framework of dead reef and sand. They have a low and narrow sandy
coast and some of them have rocky coast. Around all offshore islands, well-developed coral
reefs have been noticed. Geomorphologically, coral reefs in this area are of fringing type,
though some patchy corals are also observed in between Appa Island and Pilliyarmuni Island,
and in some areas like Bharathinagar coast and southeast coast of Kariya Shuli Island. Two
islands namely Velanguchalli and Poovarasanpatti are now submerged in the seascape.
Based on biodiversity assessments made by the recent survey in 2013 conducted by Zoologica l
survey of India the fauna and flora known so far from our Indian reefs comprises 1097 species
under 254 families and 567 genera which includes 85 species of corals, 15 gorgonids,16 sea
anemones, 24 prawns, 3 lobsters, 21 crabs, 88 molluscs, 106 echinoderms, 2 hemichordates, 2
cephalochordates, 78 tunicates, 553 fishes, 6 reptiles, 63 birds, 6 mammals (Venkataraman et
al., 2002). Endemic Hemichordata Phycodera fluva flagship species such as Dugong, 3 species
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 114 ONGC.
of dolphins, 2 species of whales, at least 5 species of turtles and 68 elasmobranchs
(Venkataraman et al., 2002).
Threats
The anthropogenic factors such as industrialization, pollution and discharge of large quantit ies
of sewage into coastal areas, in addition to the over exploitation of reef resources and illega l
mining of corals by the local population are the major threat to coral reefs.
Coral mining: The majority of damage to coral reefs in the Gulf of Manar has been through
direct anthropogenic stress The human activity such as coastal development, destructive
fishing, over exploitation, marine pollution, runoff from deforestation and toxic discharge from
industrial and agricultural chemicals. Some of the factors affecting coral reefs growth are
regression of coral growth due to silt laden water with greater load of suspended matter during
monsoon flow, windblown sandy deposition, cyclone, quarrying for limestone, effect of
current, etc.
Seaweed collection: Seaweed collection was carried out around the islands as a source of
alternate livelihood for fishermen communities. Seaweed collections over coral reefs severely
threaten and destroy coral reefs causing the release of bottom sediments and smothering affect,
increase of turbidity and reducing the intensity of light; breaking and killing of coral.
Destructive Fishing Practices: Bottom trawlers and trap nets for crab and lobster are two of
the major destructive fishing practices in the region. This fishing practices churn up the sea
bottom releasing the sediments and casing turbidity, these silt laden waters are carried by
currents and wave action over reefs causing stress to the corals by reducing light penetration
or smothering the corals with sediment. These fishing activities are also destroying the corals.
Sedimentation: Sedimentation affects corals in three ways, photo-synthetically, physically and
chemically. Sedimentation is caused my many sources, both natural and anthropogenic. The
anthropogenic causes are through seaweed collection and by coral mining; the other sources of
sedimentation are from afforestation and removal of vegetation on sand dunes and coast
increases erosion by waves, wind and rainfall increases the sediment load in the water
Eutrophication: The release of sewage has resulted in heavy load of organics and low primary
production, which in turn would drastically affect the growth of the coral habitat
Industrial pollutants: The release of heated water and fly ash from thermal plant has an affect
the coral reefs.
Natural threats: During cyclones heavy wave actions uproots and break corals.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 115 ONGC.
3.9.2 Mangrove
Islands Mangrove
The Gulf of Mannar islands possess some unique type of mangrove vegetation. A total of 10
true mangrove species were reported belonging to 6 families of 6 order1. Mangrove species
was reported in 16 islands. The island Manoli ranks high in having 9 mangrove species and is
followed by Krusadai, Pullivasal, Poomarichan and Hare Island respectively. The mangrove
vegetation in Manoli is striking for its luxuriant growth and diversity. The islands Valai,
Pullimunai, Nallathanni, Upputhanni and Van islands have only one mangrove species each.
About 24 mangrove associated species were recorded from all the islands. The species
Salvadora persica and Sesuvium portulacastrum were the dominant associate flora found in
about 15 islands. Similarly, the species like Thespesia populnea and Scaevola taccada have
been recorded in 13 islands. Caesalpenia, Dalbergia, Pandanus, Pongamia, Salvadora and
Thespesia were found distributed well away from the upper reaches of high tide. The grass
species like Aleuropus, Fimbristylis, Spinifex and Tamarix were recorded at or near the upper
reaches whereas halophytes Salicornia, Scaevola, Sesuvium, Suaeda occupies the gaps between
the mangroves and in exposed areas in the mudflats. Clerodendrum, Ipomoea, and Spinifex
covers the periphery of the islands.
About 61 species belong to trees, herbs, shrubs etc. (other than mangroves and mangrove
associates), were identified at all islands of the Gulf of Mannar. Three alien invasive species
(Acacia eburnean, Acacia nilotica and Prosopis juliflora) were reported from these islands.
On-shore Mangroves
About 13 typical riverine-estuarine and canal have been recorded along coastline of the
Biosphere Reserve in the four coastal districts. Among them only Kanjirangudi of
Ramnathapuram; Vaipar, Buckil odai, Punakayal-Pazhayakayal complex of Tuticorin and
Manakudi of Kanyakumari district have mangrove distribution.
The Kanjirangudi estuary falls in the oil and gas block. The estuarine waters have largely been
utilized for aquaculture practice nearby. Avicennia marina is the only mangrove species found
along the muddy shoreline of the estuary and its distribution extents upto a1.5 km distance from
the coast.
Threats
There is no direct profound threat to mangrove ecosystem in the off-shore Islands.However,
the activities such as docking of small boats, cooking adjacent to the vegetation were pose very
little damage. Natural degradation of mangroves has been reported in few islands due to
increased anaerobic conditions, hyper salinity and sulfide stress at water-logged area over a
period of time has killed mangroves.
1 A study was conducted by the Wildlife Institute of India, National Institute for Coastal and Marine
Biodiversity Centre in 2006
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 116 ONGC.
3.9.3 Sea Grass & Sea-weed habitat
Sea-Grass
Sea-grasses occur in the intertidal and mid-tidal zones of shallow and sheltered areas of sea,
gulf, bays, backwaters and lagoons. They form a dense meadow on sandy and coral rubble
bottom and sometimes in the crevices under water.
The Gulf of Mannar is well known for its rich diversity of sea grasses along with dugong.
Various fishes, molluscs, crustaceans, and echinoderms form the predominant associated fauna
of the sea grass habitats. Under normal conditions, seagrasses maintain water clarity by
trapping silt, dirt, and other sediments suspended in the water column. These materials are then
incorporated into the benthic substratum, where they are stabilized by seagrass roots. However,
when sediment loading becomes excessive, turbidity in the water column increases and the
penetration of sunlight is inhibited. In extreme cases, excessive sediment loading can actually
smother seagrasses.
It was estimated that the total extent of seagrass beds around all islands of the Gulf of Mannar
Biosphere Reserve was 80.7 sq. km. The species composition of seagrass community in the
Gulf of Mannar region include Enhalus acoraides, Halophila ovalis, Halophila ovata, Halophila
beccari, Halophila stipulacea, Thalassia lemprichii, Cymadocea serrulata, Cymadocea
rotundata, Halodule uninervis and Syringodium isoetifolium etc .
Threats
The major threats which present in this region are mentioned below
Since the seagrass productivity is highly dependent on ideal salinity, water temperature ,
and turbidity, which are getting polluted by industrial and domestic wastes, which comes
from the near by coastal areas of the GOMMNP
Port and dredging related activities in the region churns up seagrass beds, increasing
turbidity and suspended sediments in the water column, which would have a long- term
impacts on seagrasses of this region.
Use of indiscriminate fishing technology especially trawling on these beds is also expected
to harm this habitat.
With increased agricultural activity on the nearby landscape is also posing a threat to the
sea grass beds because of its pollution.
Fishing in the seagrass beds and increase use of fishing vessels on the habitat are also
threatening this habitat.
Collection of sea grasses for fodder and fertilizers.
Sea-weeds
Seaweeds are marine plants belonging to lower Cryptogams. They occur in the intertida l,
shallow and deep waters of the sea upto 150m depth and also in estuaries 49 and backwaters.
These are large and diversified groups with size ranging from single cell such as
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 117 ONGC.
Chlamydomonas to several meters in length (Macrocystis). The four classes of seaweeds are
Chlorophyta (green algae), Phaeophyta (brown algae),
A total number of 147 species of algae comprising 42 species of green algae, 31 species of
brown algae, 69 species of red algae and 5 species of blue green algae distributed in Gulf of
Mannar islands.
3.9.4 Biodiversity Profile of Biosphere Reserve
About 3600 species of fauna and flora have been identified in the GOMBR by the Central
Marine Fisheries Research Institutes and other organizations. The fauna is said to be one of the
richest in the whole of Indo-west pacific region.
About 126 species of phytoplankton, 360 species of zooplankton, 51 species (2 endemic) of
foraminiferans, 275 species (31 endemic) of sponges, 128 species (42 endemic), 14 species of
Gorgonids, 75 species of Polychaeta, 9 species of Nematoda, 41 species Penaeid and Non-
Penaeid shrimps, 7 specise Lobster, 210 species of Crabs, 25 species of Stomatopod, 731
species of Molluscs (Bivalvia, Gastropods and Cephalopods), 264 species of Echinodermata
were reported from GOMMBR.
Corals
128 species (42 endemic) were recorded (Pillai, 1986, CMFRI, 1998). The dominant genera
were Pocillopora, Acropora, Montipora, Favia, Favites, Goniopora, Goniastrea, Platygyra,
Echinopora, Galaxea, Porites, Turbinaria, Leptoria, Pavona and Pachyseris.
Crabs and economically important
A total of 38 crab species belong to 21 genera and five families occur in the Gulf of Mannar
Biosphere Reserve, which is 5.6% of Indian crab germ plasm. Of the 11 important commercia l
crabs in India, six crab species occur in this region. Several species are considered to be
becoming rare and threatened, or having reduced over all size because of over exploitation and
their habitat destruction. Inter-tidal zone of Gulf of Mannar Marine National Park and the
Biosphere Reserve are considered to be good habitats for these crabs in this region.
Shrimps
Shrimps are abundant in the Gulf of Mannar. Penaeus semisulcatus, P. indicus and P. monodon
are commonly available. There are 18 species of shrimps of which 10 are heavily exploited.
The lobsters Panulirus homarus, P.ornatus, P. logipes and P. versicolor are abundant, of the 7
species of spiny and sand lobsters. The crabs Scylla serrata, Portunus pelagicus, and P.
sanguinolentus are the three commercially important species. The sacred chunk, Xancus
pyrum, forms an important fishery in the Gulf of Mannar. About 1,000 km2 area of inshore
waters of Gulf of Mannar have been identified as chunk grounds.
Fishes
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 118 ONGC.
A large number of finfish species are available in the Gulf of Mannar. This includes nearly 125
species of reef fishes. The common finfishes of Gulf of Mannar belong to Leiognathids,
Sardines, Lethrinids, Perches, Carangids, Anchovies, Seer fishes, Red mullets, Half beaks,
Needle fishes and Elasmobranchs such as sharks and rays. There are 15 species of silver bellies
in this region of which four species of Leiognathus are common. They are L.equulus, L.bindus,
L.dussumieri and L. splendens. As many as 20 species of lethrinids have been reported. The
commonly available species of Lethrinus are L. ornatus, L. varigatus, L. hark, L. lentjan, L.
nebulosus and L. microdon. The other major contributors to the fishery are Perches,
Nemipterids Haemulids, Serranids, Lutjanids and Epinephelids.
Avi-fauna
The Gulf of Mannar Marine National Park is also an Important Bird Area. About 187 species
of aquatic and terrestrial birds have been identified from this IBA (Balachandran 1990, 1995),
which is famous for waders and seabirds. Sometimes >50,000 water birds are found here.
Pelagic birds are also recorded (Balachandran 1990).
Sea turtles
Four of the seven species of sea turtles found worldwide are reported to occur in the Gulf of
Mannar Biosphere Reseves (Kar & Bhaskar, 1982; Bhupathy & Saravanan, 2003). These are
the olive ridley (Lepidochelys olivacea), green (Chelonia mydas), hawksbill (Eretmoche lys
mbricate) and leatherback (Dermochelys coriacea. All the four species of sea turtles that occur
in these coastal waters are protected under Schedule I of the Indian Wildlife Protection Act
(1972), as well as listed in Appendix I of Convention of International Trade in Endangered
Species of Wild Fauna and Flora (CITES) which prohibits trade in turtle products by signatory
countries.
Sea snakes
Sea snakes are considered to be the most successful marine reptiles in the world. 12 species of
sea snakes have been reported in the Gulf of Mannar region. Of which, nine species are true
sea snakes i.e. belong to the family Hydrophiinae. Studies shows that the sea snake population
in Indian seas are declining. It is understood that, incidentally captured sea snakes are released
back into sea but in several occasions the incidentally captured sea snakes are killed by the
fishermen due to fear.
Marine Mammals
11 species have been recorded (James and Lal Mohan, 1987, CMFRI, 1998) including 6 species
of whales, 4 species of dolphins and 1 species of Dugong. All are endangered species and
placed under schedule 1 of "The Wild Life (Protection) Act 1972.
Dugong
The Dugong (Dugong dugong) is one of the four surviving species in the Order Sirenia and it
is the only existing species of herbivorous mammal that lives exclusively in the sea (Heinsohn,
1972). The Dugong ranges along the coast of east Africa into the Red Sea, along the coast of
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 119 ONGC.
southern Asia to as far east as the Solomon Islands, and along the northern coasts of Australia
from southern Queensland to subtropical Western Australia (Marsh et al. 1999).
In India, the dugong occurs in the Gulf of Mannar and Gulf of Kutch, the Palk Bay and in the
Andaman and Nicobar Islands. All these areas have sea grass beds, which are good foraging
ground for the Dugongs.
The Gulf of Mannar had a good population of dugong but due to illega l off take of this species
caused the species to be threatened with local extinction.. However, since from 1988 the Tamil
Nadu Forest Department initiated awareness campaign to safeguard this species. Though, the
illegal off take of this species drastically reduced their population, information on current status
and distribution is not known in detail.
.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 120 ONGC.
FIGURE 3.9: ECOLOGICAL SENSITIVITY MAP
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 121 ONGC.
3.9.5 Planktons
Plankton are microscopic organisms that float freely with oceanic currents and in other bodies
of water. Plankton is made up of tiny plants (called phytoplankton) and tiny animals (called
zooplankton). The word plankton comes from the Greek word "planktos" which means
"drifting." Phytoplankton are primary producers (also called autotrophs). As the base of the
oceanic food web, phytoplankton use chlorophyll to convert energy (from sunlight), inorganic
chemicals (like nitrogen), and dissolved carbon dioxide gas into carbohydrates. Zooplankton
are microscopic animals that eat other plankton. Phytoplankton are the most important primary
producers in the ocean. Small zooplankton consume phytoplankton. Larger organisms eat the
small zooplankton. Larger predators eat these consumers.
To establish the profile of these planktons, marine surface water samples were analyzed at
Mandapam for presence of various species. The plankton profile observed indicates that:
Around 26 families of phytoplanktons were observed. Of the plankton families observed,
Zygnemataceae, Volvocaceae, Naviculaceae, Pyrocystaceae, Stephanopyxidaceae,
Rhizosoleniacea and Stephanopvxidaceae were found to be present in 15% or more
composition.
Phytoplankton count ranged between 19,000 to 21,000 cells/ml.
Of the zooplankton families observed, Bosminidae, Pontellidae, Lumbriculida, Calanoida,
Collothecidae and Asterigerinacea were found to present in 25% or more composition.
Fish Larvae, crustacean larvae & Eggs composition ranged between 10-20%.
Zooplankton count ranged between 1800 to 2000 cells/m3.
Table 3-15: PLANKTON PROFILE OF MARINE SURFACE WATER
Plankton Profile Family
Phytoplankton Bacillariaceae
Bellerocheaceae
Biddulphiaceae
Ceratiaceae
Chaetocerataceae
Chlorellaceae
Climacospheniaceae
Closteriaceae
Coscinodiscaceae
Cymbellacae
Euglenales
Eutreptiaceae
Hemiaulaceae
Leptocylindraceae
Microcystaceae
Naviculaceae
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 122 ONGC.
Pinnulariaceae
Pleurosigmataceae
Pyrocystaceae
Rhizosoleniaceae
Scenedesmaceae
Stephanopvxidaceae
Thalassiosiraceae
Ulotrichaceae
Volvocaceae
Zygnemataceae
Zooplankton Asterigerinacea
Bosminidae
Calanoida
Chitonophilidae
Collothecidae
Cypriclinidae
Lumbriculida
Misophrioida
Pontellidae
Sabellida
Serpulidae
Benthos
Benthos are living things on the ocean floor. Many benthic organisms attach themselves to
rocks and stay in one place. This protects them from crashing waves and other water
movements.
To establish the profile benthos in project area, sediment samples were analyzed at Mandapam
for presence of various species. The benthic profile observed indicates that:
Macro bethons formed 54-74% of total composition of benthos. Nephtyidae, Stylasteridae,
Ampharetidae, Stylasteridae, Sabellidae are the prominently observed families.
Meiobethos formed 17-33 % of total composition of benthos. Carterinidae, Centropagidae,
Ammodiscacea, Carterinidae, Acartiidae, Chaetonotidae and Misophriidae are the prominently
observed families.
Micro benthos formed 7-18% of total composition of benthos. Micro benthos showed presence
of Bacillariaceae, Cercomonadidae and Euglenaceae families.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 123 ONGC.
Table 3-16: BENTHIC PROFILE OF SEDIMENT SAMPLE
Benthic Profile Family
Macro Benthos Ampharetidae
Eucopidae
Eunicidae
Magelonidae
Milleporidae
Nephtyidae
Nereidae
Onuphidae
Prayidae
Sabellariidae
Sabellidae
Stylasteridae
Uncispionidae
Meio Benthos Acartiidae
Ammodiscacea
Cafterinidae
Centropagidae
Diaptomidae
Misophriidae
Pontellidae
Micro Benthos Bacillariaceae
Cercomonadidae
Euglenaceae
Biodiversity Index
A biodiversity diversity index is the measure of species diversity in a given
community.Shannon - Weineer (H) Diversity Index is a commonly used diversity index that
takes into account both abundance and evenness of species present in the community.
The details of Biodiversity Index and evenness for phytoplankton, zooplankton and benthos
are given in table below.
Table 3-17:BIODIVERSITY INDEX FOR PHYTOPLANKTON & ZOOPLANKTON
Location Phytoplankton Zooplankton Benthos
S-W Index Evenness S-W
Index
Evenness S-W
Index
Evenness
Mandapam 2.4419 0.953 1.694 0.946 2.79 0.95 S-W Index: Shannon -Weineer (H) Diversity Index
Biologists proposed a different scale of pollution in terms of phytoplankton community
diversity index, which states a negative correlation between Shannon and Wiener index and
pollution: of 0.0-1.0 for heavy pollution, 1.0-2.0 for moderate pollution, 2.0-3.0 for light
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 124 ONGC.
pollution, 3.0-4.5 for slight pollution (Shanthalaet al., 2009 Biligrami (1988)). It was
established that the diversity index value of a phytoplankton community in less polluted waters
would be higher. Shannon - Weineer Diversity Index for Phytoplankton for the project area
ranged between 2.2 to 2.6, indicating light pollution.
3.9.6 Agricultural Diversity
A major crop in the district is paddy followed by chillies. Other important crops are cultivated
are coconut, oilseeds, cotton, millets and pulses.
3.10 SOCIOECONOMIC ENVIRONMENT
This section discusses the baseline socio-economic environment of the Ramanathpuram district
Ramanathpuram Taluka with respect to ONGC’s proposed exploratory well drilling operations.
The following section discusses the methodology used for the socio-economic assessment. The
subsequent sections discuss the baseline profile of the district and the villages within the study
area. The information provided has been primarily derived from the secondary sources (Census
of India and District Statistical Handbook). In addition primary information was also collected
during the discussions at the villages with the local community members. The informal public
consultations have been used to validate the Census 20011 data. The village-wise secondary
data (obtained from Census, 20011 and presented) has been taken into consideration for
analyzing the socio-economic profile in a comparative manner for the exploratory block.
3.10.1 Methodology
A socio economic assessment of the positive and negative impacts on the people likely to be
directly and indirectly affected by the project was conducted along with other studies during
the EIA study. The assessment facilitated an understanding of the needs, demands, preferences,
capacities and constraints of the people in the vicinity of the project operation. It was
undertaken primarily to enhance the understanding of other relevant factors such as social
organizations and networks, livelihood patterns, social infrastructure etc and thus helped
prioritise ONGC’s commitment towards the CSR initiatives. Inputs from the social assessment
into the design phase facilitated in:
Tracking potential adverse effects over different time frames and different activities
Reviewing options to eliminate such negative impacts through design changes or
mitigate them through specific social protection or mitigation measures
Reviewing options to extend or enhance benefits for the population in the vicinity of
the project site.
The social assessment was primarily based on the analysis of the secondary data obtained from
the census survey (20011 and provisional data of 2011) and stakeholder consultations.
Considering the nature of the project operations and understanding of the demographic
characteristics of the area from the secondary data the following tools was used for the
gathering information and validating the secondary data to carry out the assessment.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 125 ONGC.
Stakeholders Identification
At the beginning of the EIA process, the SENES team conducted a preliminary identifica t ion
of probable stakeholders. An inventory of actual / potential stakeholders, including local groups
and individuals, local institutions like the panchayats which may be directly or indirect ly
affected by the project or with interest in the development activities of the region. This
inventory was arrived through discussions with ONGC personnel and members of the local
community. The local communities which would primarily be affected were identified based
on the location of the tentative exploratory and drilling operations as proposed by ONGC. The
villages were selected within 1-2 km radius of the proposed well location considering the fact
that there might be potential impacts on the socio-economic-cultural and environment of the
local communities residing in these villages. For further assessment of socioeconomic issues
and impacts on different stakeholders, detailed consultations with the community were
planned. The discussions focused on the issues of population/demography, education profile,
medical facilities and amenities like drinking water, transport and communication and also on
primary and secondary occupation of the villagers.
Consultations
Consultations with key stakeholders are a continuous process that was carried all through the
EIA process and would be continued during the construction and operation phases of the
project. The stakeholder analysis was followed by discussions with some of the key
stakeholders to identify their dependence on the affected or shared resources, the extent of
impact on them and measure, which will be undertaken to mitigate these impacts.
Issues like land and resource damage, social disturbance, severance and increased congestion,
noise and air pollution, employment opportunities, need for development of basic
infrastructure, safe drinking water, sanitation facilities in the surrounding villages were
discussed during the consultations so that they can be adequately addressed through the
environment management plans. The consultations also helped in developing preliminary
understanding of the requirement of social development initiatives, which are required in the
project village and may be undertaken as part of the ONGC’s CSR activity.
Action plan
ONGC has a CSR Policy. Based on the local area of project, CSR interventions will be finalized
by ONGC. During consultation two key areas for CSR interventions identified were drinking
water and educational services beyond primary school in some of the villages.
In terms of CSR interventions key concerns for some of the villages are with respect to drinking
water and education facilities for middle/secondary and further educational services. Currently
the education opportunities within the village is only till the primary school. For further studies
opportunities are available only at Ramanathapuram which is far from the villages. While
transport facilities are available these are not convenient for the students and the costs are high
for families sending their children to school. Villages adjacent to the coast have salt water
ingress due to which there is less availability of drinking water.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 126 ONGC.
3.10.2 General Socioeconomic Profile
The ONGC Field study area falls in the Ramanthapuram Taluka of district Ramanathpuram of
Tamilnadu state.
3.10.3 Demographic Profile
The study area for socio economic profiling was defined within block and surrounding areas
based on the proposed location of exploratory and development wells and its proximity to the
village and professional judgment. Of the study area defined, the baseline study focuses on
seventy one villages within the block. This Ramanathpuram Taluka of Ramanathpuram
district. The list of villages has been provided in the Table 3.6 below.
TABLE 3-18: LIST OF THE STUDY AREA VILLAGES IN THE ONGC FIELD
District Taluka Villages
Ramanathpuram Ramanthpuram Pandamangalam, Pamban, Valinockam, Andichiendal, Vennathur ,
Pathanendal, Naranamangalam, Alamalandal, Devipattinam ,
Peruvayal, Kumariyendal, Kavanur , Karendal, Pullangudi,
Chittrakkottai, Athyuthu, Palangulam, Toruvalur, Vannivayal,
Surankottai, Pattinamkattan , Thiruvolhiyakalugoorani , Terbhogi ,
Alagankulam , Attangarai, Perungulam , Valantaravai, Kusavankudi,
Sakkarakottai, Rajasuriamadai, Kooriyur , Achchundanvayal ,
Landai, Panaikkulam, Malangudi, Ekkakudi, Vellamarichchukkatti,
Achadipirambu, Kudakottai , Vannankundu , Raghunathapuram ,
Kumbaram, Rettaiyurani, Nagachi, Enmanamkondan,
Pirappanvalasai , Sattakkonvalasai, Mandapam , Nochiyurani ,
Pudumadam, Karan , Periapattinam, Kalimankundu , Tiruppullani ,
Kalari, Utrakosamangai, Mallal, Alagankulam, Nalirukkai,
Panaydiyendal, Valanur , Kulapatham, Pallamerkkulam,
Kanjirangudi , Keelakarai , Manikkaneri, Pullandai, Mayakulam,
Ramanathapuram , Keelakarai (TP), Mandapam (TP)
The study area for socio economic assessment was defined as an area within 1-2 km radius
around the 22 exploratory and development wells and is based primarily on reconnaissance
surveys, census data information, toposheet maps, understanding of the project and
professional judgment.
The demographic profile in terms of total population, household size, sex-ratio of the selected
villages in the block has been summarized in the sections below, while the detailed
demographic profile of the study area villages has been provided in Annexure 3.4.
Population and Household Size
Ramanthapuram District has an area of 4123 km² and nearly 271-km-long coastline (Palk Bay
130 kms and Gulf of Mannar 141 kms). The coastal areas stretch from the Palk straits to the
Gulf of Mannar in the South. The district contains the Pamban Bridge, an east-west chain of
low islands and shallow reefs that extend between India and the island nation of Sri Lanka, and
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 127 ONGC.
separate the Palk Strait from the Gulf of Mannar. The Palk Strait is navigable only by shallow-
draft vessels.
As of 2011, Ramanathapuram district had a population of 1,353,445 with a sex-ratio of 983
females for every 1,000 males. Presentation and depiction of the demography details of the
villages.
Ramanathapuram (M) (62050) is having the highest populations among all settlements within
the district and Andichiendal (80) with the lowest. All the above-mentioned villages belonged
to the Ramanthpuram Taluka. . The study area household size is 4.5. The average sex ratio for
the villages is 1060.
Sex Ratio
The average sex ratio of 1078 recorded for the study area villages. The highest sex ratio is
recorded for Pallamerkkulam (1414) . Of all the villages within the study area, 75% of the
villages have a sex-ratio of more than 900 and the lowest sex-ratio was been recorded at
Mayakulam (707).
Scheduled Caste (SC) & Scheduled Tribes (ST)
The overall demographic data of study area villages shows only 11 villages which consist of
some STs. Only in one Village Devipattinam, the ST population is 2.21 % and in the rest the
ST population was less than 1 %. There is a significant SC population in 58 % of the villages.
In five villages the SC population in proportion to the total population is between 75 to 100 %
and 10 villages the proportion of SC is more than 50 %. . The highest SC population is in
Achadipirambu (98.04%).
Education & Literacy
The study of the education and literacy profile in the region is relevant in order to have an
understanding whether the proposed project can utilize skilled human resources availab le
within the area.
According to 2011 census data, the literacy rate in the Ramnad district is 81.48% and
Ramanathpuram Taluka is 67.21%. The average literacy rate of the study area villages observed
as 61.36% . The highest literacy rate was observed in Pandamangalam (89.08%) and the lowest
in Panaydiyendal (35.61%).
Economic Activity & Livelihood Pattern
The relevance of economic activity and livelihood pattern is important in the context of the
study since depending on the existing situation one can predict the impact of the project activity
on the economy of the region.
The total cropped area in Ramanathapuram district is 183651 hectares of which the net rrigated
area is 66865 hectares (2014). Irrigation is mainly from tanks, tube and dug wells. The main
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 128 ONGC.
crops grown are paddy, red gram, green gram, cowpea, maize, chillies, cotton, mille ts,
groundnut etc. With a 34% share, the district is the top chilli pepper producer in Tamil Nadu.
In Ramanathanpuram district, as per the Census 2011, there were a total of 602,977 workers,
comprising 149,959 cultivators, 103,592 main agricultural labourers, 18,546 in house hold
industries, 214,053 other workers, 116,827 marginal workers, 23,808 marginal cultivators,
50,282 marginal agricultural labourers, 6,682 marginal workers in household industries and
36,055 other marginal workers. In the district there are a number of fishing villages whose
population is dependent on fishing and related activities for livelihood.
The total working population in the study area villages varies from 35.81%. Of the total
workforce, Andichiendal village revealed the highest percentage of workforce with 92.5%
workers while Alagankulam revealed the lowest workforce percentage (20.65%).
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 129 ONGC.
FIGURE 3.10: % OF SCEDULED CASTE POPULATION OF THE VILLAGES OF THE STUDY AREA
FIGURE 3.11: LITERACY OF THE VILLAGES FALLING IN THE STUDY AREA
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
Pan
dam
anga
lam
Val
ino
ckam
Ven
nath
ur
Nar
anam
anga
lam
Dev
ipat
tinam
Kum
ariy
enda
l
Kare
nd
al
Ch
ittr
akko
ttai
Ala
ngu
lam
Va
nn
iva
yal
Patt
inam
katt
an
Terb
hog
i
Att
an
gar
ai
Val
anta
rava
i
Sakk
arak
ott
ai
Koor
iyu
r
Lan
dai
Mal
angu
di
Vel
lam
aric
hch
ukka
tti
Ku
dako
ttai
Rag
huna
thap
uram
Ret
taiy
ura
ni
Enm
anam
kond
an
Satt
akko
nva
lasa
i
No
chiy
uran
i
Kara
n
Kalim
anku
ndu
Kala
ri
Mal
lal
Nal
iruk
kai
Va
lan
ur
Palla
mer
kkul
am
Kee
laka
rai
Pulla
ndai
Ram
anat
hapu
ram
(M)
Man
dap
am (T
P)
SC %
0.0010.0020.0030.0040.0050.0060.0070.0080.0090.00
100.00
Pand
aman
gala
m
Val
ino
ckam
Ven
nath
ur
Nar
anam
anga
lam
Dev
ipat
tinam
Kum
ariy
enda
l
Kare
ndal
Chit
trak
kott
ai
Ala
ngu
lam
Van
niva
yal
Patt
inam
katt
an
Terb
ho
gi
Att
anga
rai
Val
anta
rava
i
Sakk
arak
ott
ai
Koor
iyu
r
Land
ai
Mal
angu
di
Ve
llam
aric
hch
uk
katt
i
Kuda
kott
ai
Rag
huna
thap
uram
Ret
taiy
ura
ni
Enm
anam
kond
an
Satt
akko
nva
lasa
i
Noc
hiyu
rani
Kara
n
Kalim
anku
ndu
Kala
ri
Mal
lal
Nal
iruk
kai
Val
anu
r
Pa
llam
erk
ku
lam
Keel
akar
ai
Pu
llan
dai
Ram
anat
hapu
ram
(M)
Ma
nd
apam
(TP
)
Literacy %
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 130 ONGC.
4 Environmental Impact Assessment
The impact assessment section of the EIA study systematically identifies, characterizes and
evaluates the potential impacts arising out of the project and prioritizes them through a semi-
quantitative system so that they can be effectively addressed by Environment Management
Plans. Potential environmental impacts may arise out of various sequential activities to be
undertaken as part of proposed project exploratory drilling and development drilling
operations.
4.1 IMPACT ASSESSMENT METHODOLOGY
An environmental impact identification matrix has been developed to present an overview of
possible interactions between project aspects and components of the environment which may
get affected. The matrix structure takes into account physical, biological and socioeconomic
components of the environment on one axis (X axis) and activities / aspects of the proposed
exploratory well drilling project on the other side (Y axis). Aspects (based on phases of
activities like pre-drilling activities, drilling, decommissioning and potential accidental events)
and impacts on environmental components that have been taken into consideration were in line
with standard environment management system terminology. Environmental and
socioeconomic components were identified based on reviewing of applicable legislation and
baseline environment, site reconnaissance visits, discussions with stakeholders and SENES’
professional judgment.
Potential environmental and socio-economic impacts that may result from any of the identified
project aspects has been identified in a matrix based on activity-component interaction and has
subsequently been used to develop an impact evaluation matrix that list evaluation scores based
on significance criteria delineated in section 4.1.2.
4.1.1 Impact Criteria and Ranking
Once all project environmental aspects were comprehensively identified for the different
activities of the project, the level of impact that may result from each of the activity-component
interactions has been assessed based on subjective criteria.
For this, three key elements have been taken into consideration based on standard
environmental assessment methodologies:
Severity of Impact Degree of damage that may be caused to the environmenta l
components concerned;
Extent of Impact : Geographical spread of impact around project location and corridors
of activities; and
Duration of Impact: Time for which impact lasts taking project lifecycle into account.
These elements have been ranked in three levels viz. 1 (low), 2 (moderate) and 3 (high) based
on the following criteria provided in Table 4.1 below:
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 131 ONGC.
TABLE 4-1: IMPACT PREDICTION CRITERIA
Impact
Elements Criteria Ranking
Severity Regional impact resulting in long term and/ or medium damage to the
natural environment.
Major impact on community and occupational health (e.g. serious
injury, loss of life) on account of accidental events viz. well blow-outs
and related operational activities.
Adverse national media attention.
3
Local scale impact resulting in short term change and / or damage to
the natural environment.
Temporary loss of land, livelihood source of affected communities
Local scale impact on terrestrial habitat, endangered species, drainage
pattern and community resources.
Moderate impact on occupation and community health & well being
(e.g. noise, light, odour, dust, injuries to individuals)
Complaints from the public, authorities and possible local media
attention.
2
Limited local scale impact causing temporary loss of some species etc
Limited impact on human health and well-being (e.g. occasional dust,
odour, light, and traffic noise).
Public Perception/Concern
1
Extent Regional scale impact and including impacts to physical, biological
and socio-economic environment of the exploratory block 3
Largely local level impact limited to immediate vicinity of the
exploratory well site 2
Impact not discernable on a local scale 1
Duration The impact is likely to occur during the entire project life cycle at all
times.
3
The impact is likely to occur in some phases of project life under
normal operating conditions.
2
The impact is very unlikely to occur at all during project life cycle but
may occur in exceptional circumstances.
1
A positive or beneficial impact that may result from this project has not been ranked and has
been depicted in the form of ++.
4.1.2 Impact Significance
The significance of impact has been adjudged based on a multiplicative factor of three element
rankings. The Table 4.2 (below) depicts impact significance in a scale of LOW-MEDIUM-
HIGH and will be used for delineation of preventive actions, if any, and management plans for
mitigation of impacts.
Impact significance has been determined taking into account measures which have been
factored in the design and planning phase of the project. Legal issues have been taken into
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 132 ONGC.
account, wherever appropriate in the criterion sets, to aid in ONGC’s effort to comply with all
relevant legislation and project HSE requirements. Additionally, the results of quantitat ive
impact prediction exercise, wherever undertaken, have also been fed into the process.
TABLE 4-2: CRITERIA BASED SIGNIFICANCE OF IMPACTS
Severity of Impact
(A)
Extent of Impact
(B)
Duration of Impact
I
Impact Significance
(A X B X C)
1 1 1 1
Low
1 1 2 2
1 2 1 2
1 1 2 2
2 1 2 4
1 2 2 4
3 1 2 6 Medium
1 3 2 6
2 2 2 8
3 2 2 12
High
2 3 2 12
2 2 3 12
3 3 2 18
3 2 3 18
2 3 3 18
3 3 3 27 - Beneficial Impact - ++ Positive
To assist in determining and presenting significance of an impact, an impact evaluation matrix
(Table 4.3) has been developed based on the one developed for the impact identifica t ion
exercise. In addition to ranked weights, significance of impacts has been depicted using colour
codes for easy understanding. In case an environmental component be impacted by more than
one project activity, higher impact significance ranking has been taken as the significance
ranking for subject receptor. Impacts that have been determined to be having high significance
ranking of “>12” are considered significant and hence require examination in terms of
preventive actions and/or additional mitigation to reduce level of the potential impact.
Recommended additional mitigation measures and management plans are presented in
Chapter 6. A second evaluation matrix presents significance of impacts after considering that
proposed mitigation measures will be implemented.
The identified impacts are further discussed in detail in the following section with discussion
focusing on impacts of higher significance. This is followed by a point wise outline of
mitigation measures recommended.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 133 ONGC.
TABLE 4-3: IMPACT IDENTIFICATION MATRIX
Environment Activity
Physical Environment Biological Environment Socio-economic Environment
Aes
thet
ics
& V
isu
als
Air
Qu
alit
y
No
ise
Qu
alit
y
Tran
spo
rt &
Tra
ffic
Lan
d U
se
Soil
Qu
alit
y
Loca
l Dra
inag
e &
Phy
siog
raph
y
Surf
ace
Wat
er R
esou
rces
Surf
ace
wat
er q
ualit
y
Gro
und
Wat
er R
esou
rces
Gro
und
wat
er q
ualit
y
Flo
ra &
Flo
ral H
abit
at
Wild
life
Hab
itat
Fau
na
Thre
aten
ed &
En
dan
gere
d
spec
ies
Mig
rato
ry c
orr
ido
r &
ro
ut
Aq
uat
ic H
abit
at
Aq
uat
ic F
lora
& F
aun
a
Loss
of L
ivel
iho
od
Co
nfl
ict
on
Jo
b o
pp
ort
un
ity
Dis
rup
tio
n o
f In
fras
tru
ctu
re
Co
mm
on
Pro
per
ty R
eso
urc
es
Du
st &
No
ise
Dis
com
fort
Loss
of A
gric
ult
ura
l Pro
du
ctiv
ity
Infl
ux
of P
op
ula
tio
n
Cu
ltu
ral &
Her
itag
e Si
te
Job
& E
con
om
ic O
pp
ort
un
ity
Occ
up
atio
nal
Hea
lth
& S
afet
y
Co
mm
un
ity
Hea
lth
& S
afet
y
A. Pre-Drilling Activities
Site selection and land acquisition x x x
Site clearance and top soil removal X x x x X x X X x x x x + x
Well site& access road construction X x x x X x x x + x X
Sourcing & transportation of borrow material etc X x x x x X x X x x x + x X
Storage and handling of construction debris X x x
Transportation of drilling rig and ancillaries x x x x x x x X
Operation DG set x x
Workforce engagement & accommodation at construction site x x x + X
Consumption of water for construction & domestic use for labourer x x
Generation of domestic solid waste & disposal X x x x x X Generation of waste water & discharge from construction activity &
labour camp x x X
Surface run-off from construction site x X x x x x
B. Exploratory Well Drilling & Testing
Physical Presence of drill site X X
Operation of DG sets and machinery x x x X
Operation of drilling rig x X x x x
Storage and disposal of drill cuttings and mud X x x x x
Generation of process waste water & discharge x x x
Surface run-off from drill site x x x x
Generation of domestic waste water & discharge x x x x
Generation of Municipal waste & disposal X x x x
Workforce engagement & accommodation at drill site x x x + X
Flaring during production testing and process upset x x x X
Accidental events – blow out x x x x x X X x x x x X
Accidental events-spillage of chemical & oil x x x
C. Decommissioning and Reinstatement
Dismantling of rig and associated facilities x x x X
Transportation of drilling rig and ancillaries x x x X
Removal of well site construction materials & disposal x x X
Site Restoration + + +
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 134 ONGC.
4.2 IMPACT ASSESSMENT
This section discusses the impacts of the project activities (exploratory drilling) on the
environmental receptors that stand to get affected adversely by the project. It discusses
probable impacts during various phases of the project lifecycle on the environmental and
socioeconomic components. Rankings for every activity – component interaction is based on
the criterion set earlier and resulting environmental significance with necessary justifica t ion
that has been recorded below for every set of impacts and the same has been represented in
evaluation matrices. In broader context, it is however important to remember that operations
related to exploratory well drilling, testing and completion activities also include positive
socioeconomic impacts in terms of increase in local business opportunities and on a larger
perspective, by providing potential energy security at a national level.
4.2.1 Visual Impacts & Aesthetics
Ramanathapuram PML block is an operating gas field, which has gas producing wells, GCS.
In this gas field, drilling, geophysical survey is a regular activity about which people are very
aware. Visual impacts during proposed drilling operations is anticipated from site clearance
and well site preparation, vehicles involved in transportation of raw materials and personnel,
material stockpiles and physical presence of drilling rig and associated facilities.
During drilling site preparation nearly 2.2 ha land is to be cleared for construction of drill site.
During site construction activity, dust will be generated from transport of construction material,
machinery and personnel, haphazard dumping of construction waste, domestic waste from
labour camp may cause visual and aesthetic impacts. Such impacts likely to be particula r ly
experienced by communities residing in villages located in the vicinity of exploratory well.
However taking into account the temporary nature of site preparatory activities and necessary
mitigation measures to be implemented by the proponent with respect to the siting of well
locations ( borrow areas, use of existing infrastructure etc.) the impact is not major.
Visual impact due to the operation of drilling rig and presence of base camp is not considered
significance given the temporary nature of exploratory activities (about 60 days) provided the
well is not indicative of any commercial hydrocarbon reserve. Also with drilling waste and
process waste water is likely to be temporary stored in impervious pits no visual impact to this
regard is envisaged. Some visual impacts are also envisaged from light generated from flaring
events. However such activity is likely to be of intermittent in nature, to occur only during
process testing. Reinstatement of well site not indicative of any commercially exploitab le
hydrocarbon reserve is also likely to positively contribute to the site visual aesthetic.
Severity of Impact 1 Extent of Impact 2 Duration of Impact 1
Impact Significance = 2 i.e. Low
Mitigation Measures
All the construction activity will be restricted within the designated site
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 135 ONGC.
Dust nuisance from construction site will be suppressed through periodical water
spraying at disturbance area;
On completion of work all temporary structures, surplus materials and wastes will be
completely removed;
Construction wastes and municipal solid waste temporarily stored at the sites will be
transported to the designated disposal site/facility at regular intervals;
Domestic solid wastes temporarily stored in the collection point within the labour camp
or township and will be transported to designated solid waste disposal site at regular
intervals;
After decommissioning of rig and associated facilities, drill sites will be restored –drill
platform will be removed, pits & garland drains will be filled up, construction material
of will be removed & disposed;
Site will be rehabilitated through laying of top soil
4.2.2 Impacts on Air Quality
Operation of vehicles and construction machinery
Exhaust emission from operation of construction machinery is likely to contribute to air
pollutant load (primarily PM, NO2, SO2 etc.) in the ambient air near well site facilit ies.
However considering localized nature of impacts, temporary nature of construction and drilling
activities along with necessary mitigation measures is likely to be adopted by the proponent
and impact is considered to be of low significance.
Severity of Impact 1 Extent of Impact 2 Duration of Impact 2
Impact Significance = 4 i.e. Low
Construction material transport, storage and handling
During construction phase it is estimated that about 500 m3 of borrow material and 1000 m3
of aggregates will be required per well site location for road construction/strengthening and
site preparatory activities. Fugitive emission is therefore anticipated from transportation,
storage and handling by contractor personnel. However, generation of such fugitive dust is
likely to be governed by micro-meteorological conditions (wind speed and direction) and the
transportation route condition considering the exploratory drilling activity will be carried out
dry season and majority of internal roads are kutcha or degraded condition. Such impacts are
considered to be medium. However, the construction activity, rig mobilization and
decommissioning activity is a temporary and limited movement of project vehicles (5 nos.
/well) and adopting specific mitigation measures, no significant impact is therefore envisaged.
Severity of Impact 2 Extent of Impact 2 Duration of Impact 1
Impact Significance = 4 i.e. Low
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 136 ONGC.
Operation of Diesel Generator (DG) Sets
The proposed project will involve the operation of diesel driven 4 X 900 KW generators for
drilling of exploratory well. However, only three DG sets will be used at a time. One DG set
will be kept as standby. The operation of DG sets will therefore result in the generation of air
pollutants viz. PM, SO2 and NOx, thereby affecting the ambient air quality. The dispersion of
these air pollutants may affect the receptors viz. village settlements located in near vicinity of
the well site only under exceptional combination of meteorological conditions. It has been
already mentioned in baseline that PM10, SO2 and NOx concentrations in ambient air is well
within the NAAQS specified limits. Moreover, considering the temporary nature of drilling
phase (approx 45- 60 days), dry conditions prevalent in the Block region and provision of
adequate DG set stack height for effective dispersion of air pollutants, no significant impact to
this regard is envisaged. Additionally the proponent also plans to adopt and implement
necessary mitigation measures as discussed in the subsequent section to effectively address
potential air quality impacts from DG set operation. Impact due to flaring operation is also
assessed by modeling. The worst case scenario has been considered to run the ISCST3 model
for following activities:
3 DG sets of 900 KW capacity
Test Flaring
In order to predict the maximum worst case Ground Level Concentrations (GLCs) of the above
mentioned pollutants, air modeling has been undertaken with the following inputs.
TABLE 4-4: INPUT PARAMETERS CONSIDERED FOR MONITORING
Source
Stack
Height
(m)
Stack
Dia(m)
Stack gas
temp (K)
Stack gas
velocity
(m/s)
Emission Rate (g/sec)
PM NOx SO22
DG set operation
900 KW DG 9 0.30 773 17.0 0.05 1.0 0.06
Test Flaring
30 0.50 1273 20 - 2.0 -
Though, ISCST3 is a refined model, the model run was carried out based on micro -
meteorology to predict air quality impacts for a average 24 hr period that may be caused by
peak power utilization at the drill site. The model was run considering operation of three 900
KW DG sets simultaneously and intermittent flaring. Maximum back ground concentrations,
incremental and projected back ground concentrations for the pollutants are shown in the
following Table 4-5.:
2 Sulphur content in disel (BSIII) was taken as 0.035% or 350 ppm.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 137 ONGC.
TABLE 4-5: PREDICTED GLCS FOR AIR POLLUTANTS
Pollutants Predicted Maximum GLC (μg/m3)
Max. Baseline concentration
Predicted Incremental
GLC
Projected Worst Case
GLC
Distance
from well (m) Direction
DG set operation
NO2 (μg/m3) 13.00 11.70 24.70 532 E
PM10 (μg/m3) 57.00 0.59 57.59 532 E
SO2 (μg/m3) 16.00 0.70 16.70 532 E
Test Flaring
NO2 (μg/m3) 13.00 1.30 14.30 2046 E
Maximum monitored back ground concentration of NO2, PM and SO2 at all locations were
recorded to be maximum 13.00, 57.00 and 16.00 μg/m3, respectively. Silmilarely, maximum
predicted incremental concentration of NO2, PM and SO2 were found to be 11.70, 0.59 and
0.70 μg/m3, respectively. Projected worst case GLC’s of NO2 , PM10 and SO2 are predicted to be
24.70, 57.59, and 16.70 μg/m3, respectively. The distance and direction for the occerance of
incremental GLC’s are found to be 532 m from the source as shown in the above Table 4.5.
The predicted worst case background concentration of NO2, PM and SO2 are found to be well
within the stipulated standard of MOEFCC for the ambient air quality.
The incremental Ground Level Concentration (GLCs) of the pollutants (as discussed above),
do not exhibit any appreciable increase in the concentration of air quality. Therfore, impact on
ambient air quality due to operation of DG set and flaring is considered to be of low
significance.
Severity of Impact 1 Extent of Impact 2 Duration of Impact 2
Impact Significance = 4 i.e. Low
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 138 ONGC.
Incremental Isopleth for NO2 – AQ Modeling
FIGURE 4-1: NO2 PLOT (3X900 KW DG SET)
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 139 ONGC.
Incremental Isopleth for PM
FIGURE 4-2: PM PLOT (3X900 KVA DG SET)
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 140 ONGC.
Incremental Isopleth for SO2
FIGURE 4-3: SOX PLOT (3X900 KVA DG SET)
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 141 ONGC.
Incremental Isopleth for NO2
FIGURE 4-4: NOX PLOT (TEST FLARING)
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 142 ONGC.
Mitigation Measures:
All vehicles used for transportation of loose and friable materials will not be loaded
over the freeboard limit and will be covered.
Water spraying will be done on the access roads to control re-entrained dust during dry
season;
Equipment, machinery and vehicles having inbuilt pollution control devices will be
considered as a measure for prevention of air pollution at source
Engines and exhaust systems of all vehicles and equipment used for the project will be
maintained so that exhaust emissions are low and do not breach statutory limits set for
that vehicle/equipment type.
DG set will appropriate stack height will be utilized.
Providing Personnel Protective Equipments (PPEs) like mask to workers at site.
4.2.3 Impact on Noise Quality
Potential impact on noise quality is anticipated from noise vehicular movement, operation of
construction machinery during well site preparation and access road strengthening and
operation of drilling rig.
Operation of construction machinery/equipments
Operation of heavy machinery/equipments and vehicular movement during site preparatory
and road strengthening/construction activities may result in the generation of increased noise
levels as specified in the Table 4.6. The same can be used as a reference for calculat ing
probable noise pressure levels arising out of a number of such equipments.
TABLE 4-6: CONSTRUCTION EQUIPMENT NOISE LEVELS
Equipment Sound Level At Operator (in decibels)
Average Range
A. Earth Moving Equipment
Front End Loader 88.0 85-91
Back Hoe 86.5 79-89
Bull Dozer 96.0 89-103 Roller 90.0 79-93
Truck 96.0 89-103
B. Material Handling Equipment
Concrete Mixer <85.0 - Crane/Hydra <85.0 -
Derrick 100 97-102
Source: British Columbia, “Construction Noise,” Workers Compensation Board of BC
The noise related disturbance is likely to be experienced by communities residing in proximity
of the construction site and along material transportation routes. The environmental setting of
well sites reveals that settlements are very close to the proposed well site and site access road.
Distance of settlement varies between 50 m (W- 6) to 700 m (W-19) and 18 wells having
settlement within 250 m from proposed well site. Considering the construction phase activit ies
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 143 ONGC.
to be of temporary nature, limited daily movement of project vehicles (3-4 nos. vehicle for
transportation of personnel and 8-10 nos. for material transport) and adequate mitiga t ion
measures viz. equipment maintenance etc. to be implemented by the project proponent, impact
is not considered to be of significance.
Severity of Impact 1 Extent of Impact 2 Duration of Impact 2
Impact Significance = 4 i.e. Low
Operation of drilling rig
Operational phase noise impacts are anticipated from operation of drilling rig and ancillary
equipment viz. shale shakers, mud pumps and diesel generators. Studies indicated that noise
generated from operation of drilling rig generally varies in the range of 88-103 dB(A). Other
contributors of high noise level at the exploratory well site include shale shakers, mud pumps
and diesel generators. The average equivalent noise levels of drilling rig and ancillary
equipment has been provided in the Table 4.7 (below) for reference.
TABLE 4-7: DRILLING RIG & EQUIPMENT NOISE LEVELS 3
Equipment Equivalent noise levels in dB(A)
Average Range
Drilling Rig 96.9 88.0-103.0
Mud Pumps 76.9 73.3 -80.5
Diesel Generators 72.7 71.8-73.7 Shale Shakers 76.6 -
Further, considering drilling to be a continuous operation, noise generated from aforesaid
equipments has the potential to cause discomfort to the local communities residing in proximity
(within 500m) of the rig facility. All drill sites, except W-19 and W-21 having settlement within
500m from proposed well site. Occupational health and safety impacts viz. Noise Induced
Hearing Loss (NIHL) is also anticipated on personnel working close to such noise generating
equipment. However, considering short duration of drilling period (approx 60 days) and
necessary noise prevention and control measures viz. use of acoustic barriers, provisions for
proper PPEs, regular preventive maintenance of equipments etc. to be implemented by the-
proponent no significant impact to this regard is envisaged.
Noise Level Prediction
A noise modeling exercise has been undertaken based on standard noise attenuation equations
to predict noise levels from drilling rig near sensitive receptors within 200m. A noise
3 “Noise Report on Drilling Operation” – British Drilling & Freezing Ltd – Prepared by K A Worthington; AEC
Report: P852-2; 17th October 2002;
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 144 ONGC.
attenuation plot has been developed considering natural attenuation by distance with noise level
predictions only expected to help in planning and decision making.
The noise generated from drilling rig is considered to be about 95.0 dB(A) at a distance of 10m
from the rig location. Noise attenuation equations (without any noise barrier) show that the
normal attenuated noise at any receptor points located at a distance of about 100 m and 200 m
from the fence-line of the rig, will be in the range of about 75.0 dB(A) and 68.9 dB(A)
respectively. In the absence of an acoustic barrier, the predicted noise levels were found to
exceed the day time noise standard of i.e. 55 dB (A) leading to discomfort to neighbouring
communities. However, with the introduction of a noise barrier at the fence-line with a height
of 5 m the noise level may be controlled. This control measure will be enough to decrease noise
levels near sensitive receptors at 200m to about 56.9 dB (A). However a detailed noise
modelling exercise to look at option of noise reductions will be conducted at the design stage
to determine the barrier specifications. The noise attenuation plot with and without acoustic
barrier is presented in Figure 4.5 below.
FIGURE 4-4: NOISE ATTENUATION PLOT
Severity of Impact 2 Extent of Impact 2 Duration of Impact 2
Impact Significance = 8 i.e. Medium
Mitigation Measures
Typical mitigation measures for noise will include the following:
68.98
56.98
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
10 20 30 40 50 60 70 80 90
100
110
120
130
140
150
160
170
180
190
200
210
220
230
240
250Eq
uiv
ale
nt n
ois
e le
vel (
in d
eci
be
ls)
Distance (in metres)
Without acoustic barrier (decibels) With acoustic barrier (decibels)
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 145 ONGC.
Installation of sufficient engineering control on equipment and machinery (like
mufflers & noise enclosures for DG sets and PC pumps) to reduce noise and vibration
emission levels at source, carrying out proper maintenance and subjecting them to rigid
noise and vibration control procedures.
Re-locating noise sources to less sensitive areas to take advantage of distance and
shielding
Providing Personnel Protective Equipments (PPEs) like ear plugs/muffs to workers at
site.
Undertaking preventive maintenance of vehicles and machinery to reduce noise levels.
4.2.4 Potential Impact Transport and Traffic
The drill site access roads (i.e. village road) are not busy vehicular route. Only private/Govt.
buses vehicles ply at the internal village roads. Considering the movement of 100 trailer/truck
load material will be transported during site construction and decommissioning phase from
Ramanathapuram to each drill sites. In the transport route, there are schools and Hospitals.
Disturbance to traffic movement during school time is therefore anticipated from additiona l
traffic during school hour. With respect to increase in traffic movement the impact is
considered to be of medium significance considering low density traffic route.
Severity of Impact 2 Extent of Impact 2 Duration of Impact 2
Impact Significance = 8 i.e. Medium
4.2.5 Potential Impact on Land Use
To construct drill site, approximately 2.2 ha of agricultural land per well site will be required.
ONGC will purchase these private lands and same will be permanently converted into industr ia l
purposes for sites in which hydrocarbons are promising. Rest of the sites will be handed over
to the land owners after land restoration. The change of land use is considered to be medium
significance.
Severity of Impact 1 Extent of Impact 2 Duration of Impact 3
Impact Significance = 6 i.e. Medium
4.2.6 Impact on Soil Quality
Potential impact on soil quality is envisaged in the form of increase in soil erosion and loss of
soil fertility resulting site clearance and top soil stripping for exploratory well site preparation,
and accidental spillage resulting from storage and handling of mud chemicals Soil quality
impacts so identified have been assessed and evaluated in the section below.
Site clearance and stripping of top soil
The soils of Ramanathapuram District can be categorized into clay, coastal alluvium, sandy
loam, alluvium, sandy and red soil clay, black cotton soil, which is believed to have been
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 146 ONGC.
derived from the Archaen gneisses where calcareous formation are abundant. Calcium
carbonate concretions of various sizes and shapes are present in majority of the black soil area
and this affects the fertility of the soils. Stripping of top soil is therefore likely to affect the
soil fertility of the well sites. It is estimated that about 3300 m3 of top soil will be removed per
well site having an area of 2.2 ha considering 15 cm top soil. However, such impact is
considered to be temporary taking into account the fact the proper reinstatement of site will be
undertaken by the proponent in case the exploratory wells are not indicative of any
commercially exploitable hydrocarbon reserves. Necessary surface run-off control measures
need to be adopted by the proponent during construction phase to prevent contamination of
abutting agricultural land from discharge of surface run-off characterized by increased
sediment load. Further specific mitigation measures will be implemented by the proponent to
stabilize the top soil to preserve their fertility characteristics during site restoration. The impact
is therefore considered to be of medium significance.
Severity of Impact 2 Extent of Impact 2 Duration of Impact 2
Impact Significance = 8 i.e. Medium
Sourcing of borrow material
Site preparatory activities will involve the sourcing of earth-fill from borrow areas. Such
sourcing activity may lead to direct and indirect long-term major adverse impacts on the
environment due to loss of top soil if located on agricultural land. The loss of top soil may also
enhance the soil erosion potential of the area resulting in increased sediment load in surface
run-off. But terrain of Ramanathapuram district is flat, receives less rainfall, thus less soil
erosion is expected due to surface run-off. Since most of the construction materials would be
available from existing quarries nearby, relatively few new borrow areas will be required.
Further necessary mitigation measures will be implemented by the proponent with respect to
the borrow area reinstatement (particularly those located on agricultural land) and run-off
control to prevent any possible impact on soil quality. Considering above scenario the impact
is considered to be of low significance.
Severity of Impact 1 Extent of Impact 2 Duration of Impact 2
Impact Significance = 4 i.e. Low
Storage and disposal of drill cuttings and drilling mud
It is estimated that nearly about 400 m3 of drill cuttings and 20 m3/day of drilling mud is likely
to be generated from each well during exploratory drilling operation. Improper storage and
disposal of such process waste on open soil or unlined areas may therefore lead to the
contamination of soil onsite and abutting land if not properly managed. With the project design
planning taking into account construction of a HDPE lined impervious pits of capacity 1200
m3 each for temporary storage of drill cuttings and drilling fluid respectively and their disposal
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 147 ONGC.
in accordance with “CPCB Oil & Extraction Industry Standard – Guidelines for Disposal of
Solid Wastes”( The Environment (Protection) Rules, 1986-Schedule1) no significant impact to
this regard is envisaged. Further with the proponent catering to the use of water based mud the
drill cuttings and waste drilling mud generated are likely to be non-hazardous in nature and is
not anticipated to pose any potential threat to the soil environment. The impact is therefore
considered to be of low significance.
Severity of Impact 2 Extent of Impact 2 Duration of Impact 1
Impact Significance = 4 i.e. Low
Storage and handling of fuel and chemicals
Contamination of soil can result from the project activities if certain operations like storage of
chemicals and fuels, spent oil and lubricants are not managed efficiently. Storage of chemica ls
and fuels, spent lubricants on unpaved surfaces also have potential for contamination of soil.
Accidentally, if chemicals, oil and lubricants are spilled, either during transportation or
handling, on open soil may contribute to soil contamination. However, considering that
appropriate spill prevention and control measures to be implemented by the proponent the
impact is not considered to be of significance.
Severity of Impact 2 Extent of Impact 2 Duration of Impact 1
Impact Significance = 4 i.e. Low
Mitigation Measures
The following mitigation measures are proposed for reducing impact on soil quality:
Restricted project and related activities during monsoon season;
Carrying out adequate restoration of soil, to the extent possible;
Implementing adequate sediment control measures to prevent discharge of untreated
surface run-off characterized by increased sediment load to abutting agricultural land.
Ensuring proper storage of drill cutting and chemicals to prevent any potential
contamination from spillage.
Implementing appropriate spill prevention and control measures.
4.2.7 Impact on Topography & Drainage
Potential impact on drainage and topography viz. alteration of drainage pattern, water logging
etc. are anticipated during well site preparation, widening/strengthening of access roads and
restoration of exploratory well facilities. The impact details have been discussed below:
Site preparation and road construction/strengthening
Potential impact on drainage is primarily anticipated in the form of disruption of natural
drainage pattern during site preparation and approach road construction. Since site preparation
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 148 ONGC.
involves raising of acquired/leased land to about 0.25 m from the ground level it may lead to
alteration of onsite micro-drainage pattern leading to potential problems of water logging in
the agricultural land abutting the drill site. However agricultural practice is less in
Ramanathpuram, as the lands in the district are non-fertile lands.
The infrastructure in major portion of the block is characterized by paved and unpaved rural
roads which are adversely affected during rainfall received by the district. Effect of rainfall on
unpaved rural roads is more pronounced than the paved ones and sometimes could lead to
complete isolation of few villages from the other parts of the district. Well specific
environmental setting study shows that all the wells are located closed to existing road. Site
approach to be constructed for drill site varies to 0 to 40m only. However, widening of existing
road will be required for effective transportation of drilling rig and heavy equipments to the
well site. Widening/ new construction of roads could therefore result in the alteration of
drainage along water crossings and may lead to water-logging of adjacent lands and settlements
if not properly managed. However considering the provision of cross drainage structures viz.
culverts etc. at road embankments and stream crossings by the proponent to ensure
uninterrupted drainage flow the impact is considered to be of medium significance.
Severity of Impact 2 Extent of Impact 2 Duration of Impact 2
Impact Significance = 8 i.e. Medium
Well site restoration
Site restoration will be initiated for well site not indicative of any commercially exploitab le
hydrocarbon reserves. Unplanned restoration may lead to the long term disruption in natural
drainage pattern and water logging in neighbouring agricultural land abutting the site.
However, adequate care will be taken by the proponent to restore the site back to its origina l
condition based on the originally existing contours and predominant slope to prevent any such
adverse drainage impacts. The impact is considered to be of medium significance with onsite
drainage being dependent on the proper site restoration.
Severity of Impact 2 Extent of Impact 2 Duration of Impact 2
Impact Significance = 8 i.e. Medium
Mitigation Measure
Leveling and grading operations will be undertaken with minimal disturbance to the
existing contour, thereby maintaining the general slope of site;
Disruption/alteration of micro-watershed drainage pattern will be minimized to the
extent possible.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 149 ONGC.
Loss of micro-watershed drainage, if any, is to be compensated through provision of
alternate drainage.
4.2.8 Impact on Surface Water Quality
Impact on surface water quality of natural drainage channels and community water bodies may
arise from discharge of contaminated surface run-off, sewage and process waste water
generated during various phases of the proposed project.
Surface run-off discharge
Site clearance and stripping of top soil during site construction will result in an increase in soil
erosion potential leading to an increased sediment load in the surface run-off during monsoon.
Also, surface run off from drilling waste (cuttings and drilling mud), hazardous waste (waste
oil, used oil etc) and chemical storage areas may cause contamination, if allows to discharge in
the water bodies viz. natural drainage channels, ponds etc. However, taking into account the
provision of onsite drainage system and sediment control measures to be implemented by the
proponent in compliance with the CPCB Inland Water Discharge Standards, the impact is
considered to be of medium significance.
Severity of Impact 2 Extent of Impact 2 Duration of Impact 2
Impact Significance = 8 i.e. Medium
Discharge of drilling mud and process wash water
It is estimated that nearly about 350 m3/day of drilling waste and process waste water is likely
to be generated during drilling operation. The drilling waste so generated may be characterized
by the presence of oil & grease, barites and heavy metal which on discharge to nearby natural
drainage channels and/or rivers may lead to possible surface water contamination. However
considering usage of water based mud for the proposed project, temporarily storage of drilling
waste in an HDPE lined pit and subsequent treatment to ensure conformance with CPCB
Industry Specific Standards for Oil Drilling & Gas Extraction Industry and guidelines provided
by the MoEF under the Hazardous Wastes (Management, Handling & Transboundary
Movement) Rules, 2008 the impact is not considered to be of significance.
Severity of Impact 2 Extent of Impact 2 Duration of Impact 1
Impact Significance = 4 i.e. Low
Mitigation Measures
Following mitigation measures will be implemented for water pollution control:
Proper treatment of all wastewater and produced water discharges will be made to
ensure that they comply with criteria set by the regulatory body (MoEF and SPCB)
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 150 ONGC.
Drainage and sediment control systems at the well site will be efficiently designed
Construction activities viz. stripping, excavation etc during monsoon season will be
restricted to the extent possible.
All chemical and fuel storage areas, process areas will have proper bunds so that
contaminated run-off cannot escape into the storm-water drainage system. An oil-water
separator will be provided at the storm water drainage outlet, to prevent discharge of
contaminated run-off.
4.2.9 Impact on Hydrogeology & Ground Water Quality
Potential impacts on groundwater resources that could arise as a result of the proposed drilling
activities include the following:
Storage of drill cuttings and waste drilling mud
Possibility of contamination of subsurface and unconfined aquifers may exist if the casing and
cementing of the well is not carried out properly leading to infiltration or seeping of drilling
chemicals or mud into porous aquifer region. The same is also valid for disposal of drilling
waste and mud in an open/unpaved pit. However with the project proponent catering to the use
of water based mud and storage of drill cuttings and waste drilling mud in an HDPE lined pit,
impact is considered to be of low significance.
Severity of Impact 2 Extent of Impact 2 Duration of Impact 1
Impact Significance = 4 i.e. Low
Mitigation Measures
Proper engineering controls will be used for drilling and cementing operations
Water based, non hazardous type of drilling mud will be utilized for drilling operation
Drill cuttings & mud will be stored in HDPE lined pits
4.2.10 Impact on Biological Environment
The potential impacts on ecological habitat of the exploratory block region due to proposed
exploratory & development drilling operations are discussed below:
Loss of flora and floral habitat
Majority of the exploratory & development wells ( 18 wells ) are located on agricultural land
where there are no prominent vegetation except prosopis trees. Further, no wells are located in
the coastal region which will prevent impact on vegetation in coastal area. Vegetation clearance
(prosopis/palm trees) in an area of 2.2 ha will be required for wells located in 22 wells for
construction of drill site. Reviewing of ecological conditions of the exploratory block reveals
no flora or floral assemblages that are unique to the sites or are listed as protected or threatened
plant species or trees with important heritage values. Taking drilling activity into account, drill
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 151 ONGC.
site will be restored to near original condition and its impact on flora and floral habitat is
considered to be of less significance.
Severity of Impact 1 Extent of Impact 2 Duration of Impact 2
Impact Significance = 4 i.e. Medium
Impact of Fauna & Faunal Habitat
Majority of exploratory wells are located on open scrub land, private lands mainly covered
with plam and prosopis trees. However, some of the wells also falls within the 10 km radius of
ecological sensitive areas as mentioned in chapter 2 of this report and attracts wildlife clearance
as per Wildlife Protection Act 1972. In view of proposed sensitivities and proximity to the
Wildlife Sanctuary ONGC will prepare site specific Wildlife Management Plan and get it
approved from the Chief Wildlife Warden of the State of Tamilnadu. ONGC will also take
specific measures for implementation of the Wildlife Management Plan
Severity of Impact 2 Extent of Impact 2 Duration of Impact 2
Impact Significance = 6 i.e. Medium
.
Aquatic Habitat, Aquatic Flora & Fauna
The major river viz. Vaigai River, water body at Mandapam and creek near Kanjirgudi forms
the aquatic ecosystem in the study area. Since no well is proposed in CRZ area therefore impact
on aquatic habitat due to drilling of exploratory wells are not anticipated. However, precautions
will be taken for the wells located outside of CRZ area but near to any water body so that
impact on aquatic habitat can be prevented. It has been established in the baseline studies, that
existing water quality of the surface water bodies is quite favorable to support diverse range of
aquatic fauna and flora. Therefore, in case of any discharge of untreated waste water from
exploratory drilling site may result in the possible contamination of receiving streams and their
ecological habitat. Surface runoff during monsoon from the construction site of the wells has
the potential to contaminate receiving surface water bodies thereby impacting their aquatic
ecology. Again, all such process water to be discharged offsite will be undergoing adequate
treatment to comply with discharge standards specified by regulatory authorities. Adequate
treatment coupled with dilution factor of receiving water bodies will thus significantly
contribute in preventing any deleterious effect on the aquatic ecological habitat.
Severity of Impact 3 Extent of Impact 2 Duration of Impact 1
Impact Significance = 6 i.e. Medium
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 152 ONGC.
4.2.11 Impact on Socioeconomic Environment
Based on the nature and type of impacts, the assessment has been divided into broad categories
namely (i) Adverse impacts and (ii) Positive impacts.
Adverse Impact
Loss of Livelihood
The proposed tentative well location map shows that, out of 22 exploratory wells, all wells are
located in a private land. Approximately, 2.2 ha per well land will be required for proposed
drilling activity. The agricultural lands are covered with either prosopis or palm trees which
are helping local people in producing char coal. ONGC will procure this land through private
negotiation. In all cases, necessary payments will be made against purchase and crop
compensation to concerned land owners. The proposed project would not require any
displacement of villagers. The impact on livelihood is considered to be of medium significance.
Severity of Impact 1 Extent of Impact 2 Duration of Impact 3
Impact Significance = 6 i.e. Medium
Conflicts on Job Opportunity
Primary survey and public consultation showed that the local people desired to work in the
ONGC. Involvement of outside workers in proposed activity may possibly create conflict with
the local people, as most of the villagers are small scale cultivators, daily labours, small
businessmen. Local people are strongly objected to outsiders, and demanded that major
proportion of workers be involved from surrounding villages. Considering public opinion,
impact will be low.
Severity of Impact 2 Extent of Impact 2 Duration of Impact 1
Impact Significance = 4 i.e. low
Disruption on Infrastructure
Road network in the block area are observed that main roads are all weathered black top roads
and internal village roads are Kutcha road. Numbers of access roads passes through villages
are mostly Kutcha. Transportation of drilling rig and associated facilities to drill and
decommissioning of rig and associated structure will increase traffic movement. An abrupt
increase in vehicular fleet may damage road infrastructure if not properly maintained.
Severity of Impact 2 Extent of Impact 2 Duration of Impact 2
Impact Significance = 8 i.e. Medium
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 153 ONGC.
Dust and Noise Discomfort
Very less of wells are located in close proximity to settlement. Inhabitants residing close to
access roads will get affected due to noise and dust generated from vehicular movement during
site preparation, setting up of rig and associated facilities , decommissioning of rig and
associated facilities. Again, during drilling operation, inhabitants residing close to drill sites
(within 200 m) will get affected due to noise and emissions from DG sets and occasional flaring
activity. Considering proximity of human settlement and short term activity with proper
mitigation measures, impact will be of Medium significance.
Severity of Impact 2 Extent of Impact 2 Duration of Impact 2
Impact Significance = 8 i.e. Medium
Ecological Productivity of Agricultural Fields
Ecological productivity of the agricultural land taken up for exploratory drilling activity stands
temporarily affected during the entire lifecycle of the project. Reinstatement of ecologica l
productivity will be dependent on successful restoration of soils, their structure, chemistry
drainage characteristics and possibly other physical factors, such as micro-topography. These
will provide a basis for successful recovery of ecological populations, whether allowed to occur
naturally or aided by seeding and cultivation. However, considering necessary mitiga t ion
measures like top soil preservation, process water treatment, etc will be implemented by the
proponent. During various project phases any impact in this regard is considered to be of low
significance.
Severity of Impact 2 Extent of Impact 2 Duration of Impact 1
Impact Significance = 4 i.e. Low
Influx of Population
Influx of population is anticipated in all stages of the project cycle particularly during
exploratory drilling. The drill site will involve the operation of about 30 onsite workers. Hence
there might be an impact on the local communities due to the sharing of common resources
like space, drinking water, roads, etc. Interaction between workers with villagers of nearby
areas might give rise to various issues like conflict of workers with the local population,
nuisance caused by workers due to improper sanitation facilities, etc. However, taking into
account that workforce is likely to be sourced from nearby villages and adequate sanitation
facilities will be provided chances of such conflicts are negligible.
Severity of Impact 1 Extent of Impact 2 Duration of Impact 1
Impact Significance = 2 i.e. Low
Cultural & Heritage Site
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 154 ONGC.
Impact on cultural environment may occur due to site preparation, operation of drilling rig and
also during vehicular movement with respect to the proposed exploration activities. There are
no designated historical or cultural spots within block area. The project will however be
adopting following mitigation measures to prevent any adverse impact to properties/remains
of cultural and historical significance of any such remains accidentally encountered during
aforesaid activities.
Prior to commencement of site construction activities, location of cultural important properties
will be communicated to the contractor; and reporting of chance find of any properties/remains
of archeological significance by the contractor to the proponent. Thus any significant impact
due to project activities on cultural environment of the block is unlikely.
Severity of Impact 1 Extent of Impact 2 Duration of Impact 1
Impact Significance = 2 i.e. Low
Employment opportunities: Project will benefit people living in the neighboring villages by
giving preference to them in relation to direct & indirect employment associated with the
various project activities. Site preparation phase will involve certain number of laborers and
there is a possibility that local people can be engaged for this purpose. Drilling process will
involve a number of skilled and unskilled workers. There is a possibility that local people will
be engaged for this purpose to the extent possible and hence improve existing employment
scenario of the region.
However, most jobs will comprise technical involvement. Hence villagers can possibly be
employed only in certain non-technical or casual labor jobs and that too for a limited duration.
It is proposed that first preference be given to people whose land is acquired and to their
relations. Next preference will be given to the poorer people and subsequently the other
villagers.
4.2.12 Impact on Occupational Health and Safety
Occupational injuries and ill-health have huge socio-economic implications on individua ls,
their families and communities. They also have economic impacts in form of direct and indirect
costs for society as a whole. Major occupational health risks encountered in proposed drilling
activity include noise from drilling activity, operation of heavy vehicles and machinery,
handing of chemicals.
However, the proponent will adopt necessary control measures through implementation of
mitigation measures and provision of proper PPEs to workers operating in aforesaid area to
prevent and/or mitigate adverse health related impacts. Hence any possible occupational health
impact from exposure to such fugitive dust is not likely to be of major significance.
Impact Significance = ++ i.e. POSITIVE
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 155 ONGC.
Severity of Impact 2 Extent of Impact 2 Duration of Impact 2
Impact Significance = 8 i.e. Medium
Community Health & Safety: Community health and safety of inhabitants residing close to
the drilling site stands to get affected from frequent heavy vehicular movement along village
access roads and due to noise from drilling rig operations. Health and safety impact arising
from technological emergencies viz. well blow outs, explosions will be dealt separately in the
QRA section. Although the aforesaid activities are temporary in nature it may not adversely
affect community health and safety and hence is considered to be of medium significance.
Severity of Impact 2 Extent of Impact 2 Duration of Impact 2
Impact Significance = 8 i.e. Medium
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 156 ONGC.
TABLE 4-8: IMPACT SIGNIFICANCE MATRIX (WITH MITIGATION)
Environment
Activity
Physical Environment Biological Environment Socio-economic Environment
Aes
thet
ics
& V
isu
als
Air
Qu
alit
y
No
ise
Qu
alit
y
Tra
nsp
ort
& T
raff
ic
Lan
d U
se
So
il Q
ual
ity
Lo
cal D
rain
age
& P
hysi
ogra
phy
Su
rfac
e W
ater
Res
ou
rces
Su
rfac
e w
ater
qual
ity
Gro
un
d W
ater
Res
ou
rces
Gro
un
d w
ater
qual
ity
Flo
ra &
Flo
ral H
abit
at
Wil
dli
fe H
abit
at
Fau
na
Th
reat
ened
& E
nd
anger
ed
spec
ies
Mig
rato
ry c
orr
ido
r &
ro
ute
Aq
uat
ic H
abit
at
Aq
uat
ic F
lora
& F
auna
Lo
ss o
f L
ivel
iho
od
Co
nfl
ict o
n J
ob
oppo
rtu
nit
y
Dis
rup
tio
n o
f In
fras
tru
ctu
re
Co
mm
on
Pro
per
ty R
eso
urc
es
Du
st &
No
ise
Dis
com
fort
Lo
ss o
f A
gri
cult
ura
l P
rodu
ctiv
ity
Infl
ux
of
Po
pula
tion
Cu
ltu
ral &
Her
itag
e S
ite
Job
& E
con
om
ic O
pp
ort
unit
y
Occ
up
atio
nal
Hea
lth &
Saf
ety
Co
mm
un
ity H
ealt
h &
Saf
ety
Pre-Drilling Activities
Site selection and land acquisition M M L
Site clearance and top soil removal L L L M M M M L L + L
Well site& access road construction L L L M M L + L L
Sourcing & transportation of
borrow material etc L L L M L L M M L M L + L L
Storage and handling of construction debris L L L
Transportation of drilling rig and ancillaries L L M L M L L L
Operation DG set L L M M M
Workforce engagement & accommodation at
construction site L L L + L
Consumption of water for construction & domestic use for labourer L L
Generation of domestic
solid waste & disposal L L L L L L L
Generation of waste water & discharge from construction activity & labour camp L L L
Surface run-off from
construction site L M L L L L
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 157 ONGC.
Environment
Activity
Physical Environment Biological Environment Socio-economic Environment
Aes
thet
ics
& V
isu
als
Air
Qu
alit
y
No
ise
Qu
alit
y
Tra
nsp
ort
& T
raff
ic
Lan
d U
se
So
il Q
ual
ity
Lo
cal D
rain
age
& P
hysi
ogra
phy
Su
rfac
e W
ater
Res
ou
rces
Su
rfac
e w
ater
qual
ity
Gro
un
d W
ater
Res
ou
rces
Gro
un
d w
ater
qual
ity
Flo
ra &
Flo
ral H
abit
at
Wil
dli
fe H
abit
at
Fau
na
Th
reat
ened
& E
nd
anger
ed
spec
ies
Mig
rato
ry c
orr
ido
r &
ro
ute
Aq
uat
ic H
abit
at
Aq
uat
ic F
lora
& F
auna
Lo
ss o
f L
ivel
iho
od
Co
nfl
ict o
n J
ob
oppo
rtu
nit
y
Dis
rup
tio
n o
f In
fras
tru
ctu
re
Co
mm
on
Pro
per
ty R
eso
urc
es
Du
st &
No
ise
Dis
com
fort
Lo
ss o
f A
gri
cult
ura
l P
rodu
ctiv
ity
Infl
ux
of
Po
pula
tion
Cu
ltu
ral &
Her
itag
e S
ite
Job
& E
con
om
ic O
pp
ort
unit
y
Occ
up
atio
nal
Hea
lth &
Saf
ety
Co
mm
un
ity H
ealt
h &
Saf
ety
Exploratory Well Drilling & Testing
Physical Presence at drill site L
M M M
Operation of DG sets and machinery L M
M M M M M M
Operation of drilling
rig M
M M M M
M M
Storage and disposal of drill cuttings and mud L L L L
Generation of process waste water & discharge M L L L
Surface run-off from
drill site L L L L Generation of domestic
waste water & discharge L L L L L
Generation of Municipal waste & disposal L L L L
Workforce engagement
& accommodation at drill site L L L + M
Flaring during production testing and process upset L M M
M M M M
M M
Accidental events -
blow out L M M M M
M M M M
L L M M
Accidental events-spillage of chemical & oil M M M M M
Decommissioning and Reinstatement
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 158 ONGC.
Environment
Activity
Physical Environment Biological Environment Socio-economic Environment
Aes
thet
ics
& V
isu
als
Air
Qu
alit
y
No
ise
Qu
alit
y
Tra
nsp
ort
& T
raff
ic
Lan
d U
se
So
il Q
ual
ity
Lo
cal D
rain
age
& P
hysi
ogra
phy
Su
rfac
e W
ater
Res
ou
rces
Su
rfac
e w
ater
qual
ity
Gro
un
d W
ater
Res
ou
rces
Gro
un
d w
ater
qual
ity
Flo
ra &
Flo
ral H
abit
at
Wil
dli
fe H
abit
at
Fau
na
Th
reat
ened
& E
nd
anger
ed
spec
ies
Mig
rato
ry c
orr
ido
r &
ro
ute
Aq
uat
ic H
abit
at
Aq
uat
ic F
lora
& F
auna
Lo
ss o
f L
ivel
iho
od
Co
nfl
ict o
n J
ob
oppo
rtu
nit
y
Dis
rup
tio
n o
f In
fras
tru
ctu
re
Co
mm
on
Pro
per
ty R
eso
urc
es
Du
st &
No
ise
Dis
com
fort
Lo
ss o
f A
gri
cult
ura
l P
rodu
ctiv
ity
Infl
ux
of
Po
pula
tion
Cu
ltu
ral &
Her
itag
e S
ite
Job
& E
con
om
ic O
pp
ort
unit
y
Occ
up
atio
nal
Hea
lth &
Saf
ety
Co
mm
un
ity H
ealt
h &
Saf
ety
Dismantling of rig and associated facilities L L M M
Transportation of drilling rig and
ancillaries L L M M Removal of well site
construction materials & disposal L L M
Site Restoration + + +
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 159 ONGC.
5 Quantitative Risk Assessment
This section on Quantitative Risk Assessment (QRA) aims to provide a systematic analysis of
the major risks that may arise as a result of drilling of 22 exploratory well in in
Ramanathapuram PML area. The QRA process outlines rational evaluations of the identified
risks based on their significance and provides the outline for appropriate preventive and risk
mitigation measures. Results of the QRA provides valuable inputs into the overall project
planning and the decision making process for effectively addressing the identified risks. This
will ensure that the project risks stay below As Low As Reasonably Practicable (ALARP)
levels at all times during project implementation. In addition, the QRA will also help in
assessing risks arising from potential emergency situations like a blow out and develop a
structured Emergency Response Plan (ERP) to restrict damage to personnel, infrastructure and
the environment.
The risk study for the onshore exploratory drilling activities in Ramanathapuram PML area has
considered all aspects of operation of the drilling rig and other associated activities during the
exploration phase. Loss of well control / blow-out and process leaks constitute the major
potential hazards that may be associated with the proposed onshore exploratory drilling in
Ramanathapuram PML area.
The following section describes objectives, methodology of the risk assessment study and then
presents the assessment for each of the potential risk separately. This includes identification of
major hazards, hazard screening and ranking, frequency and consequence analysis for major
hazards. The hazards have subsequently been quantitatively evaluated through a criteria based
risk evaluation matrix. Risk mitigation measures to reduce significant risks to acceptable levels
have also been recommended as a part of the risk assessment study.
5.1 OBJECTIVE OF THE QRA STUDY
The overall objective of this QRA with respect to the proposed project involves identifica t ion
and evaluation of major risks, prioritizing risks identified based on their hazard consequences
and formulating suitable risk reduction/mitigation measures in line with the ALARP princip le.
Hence in order to ensure effective management of any emergency situations (with potential
individual and societal risks) that may arise during the exploratory drilling activities, following
specific objectives need to be achieved.
Identify potential risk scenarios that may arise out of proposed drilling and other associated
activities like operation of ancillary facilities and equipment’s, mud chemicals storage and
handling etc.
Analyze the possible likelihood and frequency of such risk scenarios by reviewing
historical accident related data for oil and gas industries.
Predict the consequences of such potential risk scenarios and if consequences are high,
establish the same by through application of quantitative simulations.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 160 ONGC.
Recommend feasible preventive and risk mitigation measures as well as provide inputs for
drawing up of Emergency Management Plan (EMP) for the project.
5.2 RISK ASSESSMENT METHODOLOGY
The risk assessment process is primarily based on likelihood of occurrence of the risks
identified and their possible hazard consequences particularly being evaluated through
hypothetical accident scenarios. With respect to the proposed project, major risks viz. blow
outs, process leaks and fires; non-process fires etc. have been assessed and evaluated through
a risk matrix generated to combine the risk severity and likelihood factor. Risk associated with
the exploratory drilling activities have been determined semi-quantitatively as the product of
likelihood/probability and severity/consequence by using order of magnitude data (risk ranking
= severity/consequence factor X likelihood/probability factor). Significance of such project
related risks was then established through their classification as high, medium, low, very low
depending upon risk ranking.
The risk matrix is a widely accepted as standardized method of quantitative risk assessment
and is preferred over purely quantitative methods, given that its inherent limitations to define
a risk event is certain. Application of this tool has resulted in the prioritization of the potential
risks events for the exploratory drilling, GCS and pipeline operations thus providing the basis
for drawing up risk mitigation measures and leading to formulation of plans for risk and
emergency management. The overall approach is summarized in the Figure 5.1
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 161 ONGC.
FIGURE 5-1: RISK ASSESSMENT METHODOLOGY
5.2.1 Hazard Identification
Hazard identification for the purposes of this QRA comprised of a review of the project and
associated activity related information provided by ONGC. In addition, guidance provided by
knowledge platforms/portals of the upstream oil & gas industry including OGP, ITOPF, EGIG
and DNV, Norwegian Petroleum Directorate etc. are used to identify potential hazards that can
arise out of proposed project activities.
Taking into account the applicability of different risk aspects in context of the exploratory
drilling operations in Ramanathapuram PML area, there are three major categories of hazards
that can be associated with proposed project which has been dealt with in detail. This includes :
Blowouts leading to pool fires/jet fires
Process leaks and fires
Non-process fires / explosions
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 162 ONGC.
Well control incident covers a range of events which have the potential of leading to blow-outs
but are generally controlled by necessary technological interventions. Hence, such incidents
are considered of minor consequences and as a result not well documented. Other possible
hazard scenarios like mud chemical spills, falls, etc. has also not been considered for detailed
assessment as preliminary evaluation has indicated that the overall risk that may arise out of
them would be low. In addition, it is understood that, causative factors and mitigation measures
for such events can be adequately taken care of through exiting safety management procedures
and practices of ONGC.
It must also be noted here that many hazards identified are sometimes interrelated with one
hazard often having the ability to trigger off another hazard through a domino effect. For
example, a large oil spill in most instances is caused by another hazardous incident like a
blowout or process leak. This aspect has been considered while drawing up hazard mitiga t ion
measures and such linkages (between hazards) has also been given due importance for
managing hazards and associated risks in a composite manner through ONGC’s Health, Safety
& Environmental Management System (HSEMS) and through the Emergency Management
Plan, if a contingency situation so arises.
5.2.2 Frequency Analysis
Frequency analysis involves estimating the likelihood of each of the failure cases identified
during the hazard identification stage. The analysis of frequencies of occurrences for the key
hazards that has been listed out is important to assess the likelihood of such hazards to actually
unfold during the lifecycle of the project. The frequency analysis approach for the proposed
project is based primarily on historical accident frequency data, event tree analysis and
judgmental evaluation. Major oil and gas industry information sources viz. statistical data,
historical records and global industry experience were considered during the frequency analys is
of the major identified risks4.
For QRA for the proposed project, various accident statistics and published oil industry
databases have been consulted for arriving at probable frequencies of identified hazards. Based
on the range of probabilities arrived at for different potential hazards that may be encountered
during the proposed drilling activities, following criteria for likelihood rankings have been
drawn up as presented in the Table 5.1.
TABLE 5-1: FREQUENCY CATEGORIES AND CRITERIA
Likelihood Ranking Criteria Ranking
(cases/year) Frequency Class
5 >1.0 Frequent
4 >10-1 to <1.0 Probable
4 It is to be noted that the frequency of occurrences are usually obtained by a combination ofcomponent
probabilities derived on basis of reliabilitydata and /or statistical analysis of historicaldata.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 163 ONGC.
3 >10-3 to <10-1 Occasional/Rare
2 >10-5 to <10-3 Not Likely
1 >10-6 to <10-5 Improbable
5.2.3 Consequence Analysis
In parallel to frequency analysis, hazard prediction / consequence analysis exercise assesses
resulting effects in instances when accidents occur and their likely impact on project personnel,
infrastructure and environment. In relation to the proposed project, estimation of consequences
for each possible event has been based either on accident experience, consequence modeling
or professional judgment, as appropriate.
Given the high risk perception associated with blow outs in context of onshore drilling
operation, a detailed analysis of consequences has been undertaken for blow outs taking into
account physical factors and technological interventions. Consequences of such accidental
events on the physical, biological and socio-economic environment have been studied to
evaluate the potential of the identified risks/hazards. In all, the consequence analysis takes into
account the following aspects:
Nature of impact on environment and community;
Occupational health and safety;
Asset and property damage;
Corporate image
Timeline for restoration of environmental and property damage
Restoration cost for environmental and property damage
The following criterion for consequence rankings (Table 5.2) is drawn up in context of the
possible consequences of risk events that may occur during proposed exploratory drilling
activities:
Table 5-2: Severity Categories and Criteria
Consequence Ranking Criteria Definition
Catastrophic 5 Multiple fatalities/Permanent total disability to
more than 50 persons
Severe violations of national limits for
environmental emission
More than 5 years for natural recovery
Net negative financial impact of >10 crores
Long term impact on ecologically sensitive areas
International media coverage
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 164 ONGC.
Consequence Ranking Criteria Definition
National stakeholder concern and media coverage
Major 4 Single fatality/permanent total disability to one or
more persons
Major violations of national limits for
environmental emissions
2-5 years for natural recovery
Net negative financial impact of 5 -10 crores
Significant impact on endangered and threatened
floral and faunal species
Loss of corporate image and reputation
Moderate 3 Short term hospitalization & rehabilitation leading
to recovery
Short term violations of national limits for
environmental emissions
1-2 years for natural recovery
Net negative financial impact of 1-5 crores
Short term impact on protected natural habitats
State wide media coverage
Minor 2 Medical treatment injuries
1 year for natural recovery
Net negative financial impact of 0.5 – 1 crore
Temporary environmental impacts which can be
mitigated
Local stakeholder concern and public attention
Insignificant 1 First Aid treatment with no Lost Time Incidents
(LTIs)
Natural recovery < 1year
Net negative financial impact of <0.5 crores.
No significant impact on environmenta l
components
No media coverage
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 165 ONGC.
5.2.4 Risk Evaluation
Based on ranking of likelihood and frequencies, each identified hazard has been evaluated
based on the likelihood of occurrence and the magnitude of consequences. Significance of risks
is expressed as the product of likelihood and consequence of the risk event, expressed as
follows:
Significance = Likelihood X Consequence
The Table 5.3 below illustrates all possible product results for five likelihood and consequence
categories while the Table 5.4 assigns risk significance criteria in four regions that identify the
limit of risk acceptability. Depending on the position of intersection of a column with a row in
the risk matrix, hazard prone activities have been classified as low, medium and high thereby
qualifying a set of risk reduction / mitigation strategies.
Table 5-3: Risk Matrix
Con
seq
uen
ce →
Likelihood →
Frequent Probable Remote Not
Likely
Improbabl
e
5 4 3 2 1
Catastrophi
c 5 25 20 15 10 5
Major 4 20 16 12 8 4
Moderate 3 15 12 9 6 3
Minor 2 10 8 6 4 2
Insignificant 1 5 4 3 2 1
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 166 ONGC.
TABLE 5-4: RISK CRITERIA AND ACTION REQUIREMENTS
Risk Significance Criteria Definition & Action Requirements
High (16 - 25) “Risk requires attention” – Project HSE Management need to ensure that necessary mitigation are adopted to ensure that possible risk remains within acceptable limits
Medium (10 – 15) “Risk is tolerable” – Project HSE Management needs to adopt necessary measures to prevent any change/modification of existing risk controls and ensure implementation of all practicable controls.
Low (5 – 9) “Risk is acceptable” – Project related risks are managed by well-established controls and routine processes/procedures. Implementation of additional controls can be considered.
Very Low (1 – 4) “Risk is acceptable” – All risks are managed by well-established controls and routine processes/procedures. Additional risk controls need not to be considered
5.3 RISK ASSESSMENT OF IDENTIFIED PROJECT HAZARDS
As already discussed in the previous section, three major categories risk have identified in
relation to proposed exploratory drilling activities. A comprehensive risk assessment study has
been undertaken to assess and evaluate significance of identified risks in terms of severity of
consequences and likelihood of occurrence. Risk assessment study details have been
summarized in the subsequent sections below:
5.3.1 Blow Outs/Loss of Well Control
Blow out is an uncontrolled release of well fluid (primarily hydrocarbons viz. oil and/or gas
and may also include drilling mud, completion fluid, water etc) from an exploratory or
development well. Blow outs are the result of failure to control a kick and regain pressure
control and are typically caused by equipment failure or human error. The possible blow out
cause events occurring in isolation or in combination have been listed below:
Formation fluid entry into well bore
Loss of containment due to malfunction (viz. wire lining)
Well head damage (e.g. by fires, storms, dropped object etc)
Rig forced off station (e.g. by anchor failure) damaging Blow Out Preventor (BOP) or
wellhead
The most common cause of blow out can be associated with the sudden/unexpec ted
entry/release of formation fluid into well bore that may arise as a result of the following events
as discussed in the Box 5.1 below.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 167 ONGC.
BOX 5.1: PRIMARY CAUSES OF BLOW OUTS
Shallow gas
In shallow formations there may be pockets of shallow gas. In these instances there is often
insufficient mud density in the well and no BOP is in place. If the hole strikes shallow gas the
gas may be released on the drilling rig very rapidly. Typical geological features which
suggest the presence of shallow gas can then be detected. Historically, striking of shallow gas
has been one of the most frequent causes of blowouts in drilling.
Swabbing
As the drill pipe is pulled upwards during trips out of the hole or upward movement of the
drill string, the pressure in the hole beneath the drill bit is reduced, creating a suction effect.
Sufficient drilling mud must be pumped down-hole to compensate for this effect or well
fluids may enter the bore. Swabbing is also a frequent cause of drilling blowouts.
High formation pressure
Drilling into an unexpected zone of high pressure may allow formation fluids to enter the
well before mud weight can be increased to prevent it.
Insufficient mud weight
The primary method of well control is the use of drilling mud; in correct operation, the
hydrostatic pressure exerted by the mud prevents well fluids from entering the well bore. A
high mud weight provides safety against well fluids in-flows. However, a high mud weight
reduces drilling speed, therefore, mud weight is calculated to establish weight most suitable
to safely control anticipated formation pressures and allows optimum rates of penetration. If
the required mud weight is incorrectly calculated then well fluid may be able to enter the
bore.
Lost Circulation
Drilling mud circulation can be lost if mud enters a permeable formation instead of returning
to the rig. This reduces the hydrostatic pressures exerted by the mud throughout the well
bore, and may allow well fluids from another formation to enter the bore.
Gas cut mud
Drilling fluids are denser than well fluids; this density is required to provide the hydrostatic
pressure which prevents well fluids from entering the bore. If well fluids mix with the mud
then its density will be reduced. As mud is circulated back to surface, hydrostatic pressure
exerted by the mud column is reduced. Once gas reaches surface it is released into the
atmosphere.
Source: A Guide to Quantitative Risk Assessment; John Spouge – DNVTechnica Publication 99/100a
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 168 ONGC.
For better understanding, causes of blow outs have been systematically defined in terms of loss
of pressure control (failure of primary barrier), uncontrolled flow of fluid or failure of
secondary barrier (BOP). The blow out incidents resulting from primary and secondary failures
for proposed operations as obtained through comprehensive root cause analysis of the Gulf
Coast (Texas, OCS and US Gulf of Mexico) Blow Outs 5 during 1960-1996 have been
presented in the Table 5.5 below.
TABLE 5-5: BLOW OUT CAUSE DISTRIBUTION FOR FAILURES DURING DRILLING OPERATIONS
Sl.No Causal Factors Blow Out Incidents (nos.)
A Primary Barrier
1 Swabbing 77
2 Drilling Break 52
3 Formation breakdown 38
4 Trapped/expanding gas 09
5 Gas cut mud 26
6 Low mud weight 17
7 Wellhead failure 05
8 Cement setting 05
B Secondary Barrier
1 Failure to close BOP 07
2 Failure of BOP after closure 13
3 BOP not in place 10
4 Fracture at casing shoe 03
5 Failure to stab string valve 09
6 Casing leakage 06
Thus, underlying blowout causes as discussed in the above table can be primarily attributed to
swabbing as the primary barrier failure which is indicative of insufficient attention given to trip
margin and controlling pipe movement speed. Also, it is evident from the above table that lack
of proper maintenance, operational failures and absence of BOPs as secondary barrier
contributed to majority of blowout incidents (approx 30 nos.) is recorded.
Blowout Frequency Analysis
Blow out frequency estimates is obtained from a combination of incident experience and
associated exposure in a given area over a given period. For the purpose of calculation of blow
out frequency analysis in context of the present study involving drilling operations, blow out
frequencies per well drilled have been considered.
5 “Trends extracted from 1200 Gulf Coast blowouts during 1960-1996” – Pal Skalle and A.L.Podio
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 169 ONGC.
For onshore blowouts, the Alberta Energy and Utilities Board (EUB) maintain a database of
onshore drilling incidents. The database includes drilling occurrence data for Alberta from
1975 till 1990 with a total of 87994 wells drilled. Taking the full number of blowouts gives a
frequency of 4.9 X 10-4 blowouts per well drilled.
Based on the given frequency and information provided by ONGC on the proposed exploratory
drilling project the blow out frequency is calculated as follows:
No of exploratory wells to be drilled = 22 (A)
Blow out frequency for onshore drilling = 4.9 X 10 -4 per well drilled (B)
Frequency of blow out occurrence for the proposed project = (A X B) = 22 X 4.9 X 10 -4
= 1.07 X 10-2 per well drilled
Thus, the blow out frequency for the proposed project is calculated at 1.07 X 10-2 per well
drilled i.e. the likelihood of its occurrence is “Occasional/Rare”
Blowout Ignition Probability
Review of SINTEF database indicates that a rounded ignition probability of 0.3 has been
widely used for the purpose of quantitative risk analysis arising from blow outs. As per this
database generally ignition occurred within first 5 minutes in approximately 40% of the
blowouts leading to either pool and/or jet fire. Blow out leading to flammable gas release has
a greater probability of ignition compared to liquid releases6 (Figure 5.2).
6 Fire and Explosion – Fire Risk Analysis by Daejun Change, Division of Ocean System and Engineering
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 170 ONGC.
FIGURE 5-2: IGNITION PROBABILITY VS RELEASE RATE
An alternative to the blowout ignition probabilities given by the UKOOA look-up correlations
can be obtained from Scandpowers’s interpretation of the blowout data provided by SINTEF
2. The most significant category is that for deep blowouts which indicates an early ignit ion
probability of 0.09. For the purpose of the QRA study this can be taken as occurring
immediately on release and calculation provided below:
No of exploratory wells to be drilled = 22 (A)
Blow out frequency for onshore drilling = 4.9 X 10 -4 per well drilled (B)
Blow out ignition probability = 0.09 (C)
Probability of Blow out ignition for the proposed project = (A X B X C) = 22 X 4.9 X 10 -4 X 0.09
= 0.97 X 10-3
Hence based on the aforesaid calculation the probability of ignition of blow out releases of
hydrocarbons for the proposed drilling project will be about 0.97 X 10-3 and can be considered
to be as negligible.
Blowout Consequence Analysis
Blow out from a hydrocarbon exploratory and/or development well may lead to the following
possible risk consequences:
a. Pool fires and smoke plumes resulting from ignited oil blow outs
b. Jet fires resulting from ignited gas blow outs
c. Oil slicks resulting from un-ignited oil pools.
However for the proposed project involving exploration of gas wells for natural gas releases
leading to jet fire, modeling has been based considering methane which has been identified as
the principal constituent (~ 95%) of natural gas.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 171 ONGC.
Ignition of Flammable Gas Release leading to Jet Fire
Jet fires are burning jet of gas or sprays of atomized liquids resulting from gas and condensate
release from high pressure equipment and blow outs. Jet fires may also result in the release of
high pressure liquid containing dissolved gas due to gas flashing off and turning the liquid into
a spray of small droplets. In context of the present study, formation of jet fires can be attributed
by the high pressure release and ignition of natural gas if encountered during exploration of
block hydrocarbon reserves.
Natural gas as recovered from underground deposits primarily contains methane (CH4) as a
flammable component, but it also contains heavier gaseous hydrocarbons such as ethane
(C2H6), propane (C3H8) and butane (C4H10). Other gases such as CO2, nitrogen and hydrogen
sulfide (H2S) are also often present. Methane is typically 70-90 percent, ethane 5-15 percent,
propane and butane, up to 5 percent. Thus, considering higher percentage of methane in natural
gas, the thermo-chemical properties of the same has been utilized in the jet fire blow out
consequence modeling. The following risk scenarios (Table 5.6) have been considered for
nature gas release consequence modeling:
TABLE 5-6: NATURAL GAS RELEASE MODELING SCENARIOS
Scenario Release Rate (kg/s) Release Type
Scenario - I 0.5 Small
Scenario - II 1 Medium
Scenario – III (Worst Case) 2 Large
As in the case of pool fire, modeling of nature gas releases has also been carried out using
ALOHA. A Flammable Level of Concern approach has been utilized for assessing safety risk
associated with the release of flammable gases (here methane) from well blow outs.
In ALOHA, a flammable Level of Concern (LOC) is a threshold concentration of fuel in the
air above which a flammability hazard may exist. While modeling the release of a flammab le
gas that may catch on fire—but which is not currently burning—ALOHA can predict the
flammable area of the vapor cloud so that flammability hazard can be established.
The flammable area is the part of a flammable vapor cloud where the concentration is in the
flammable range, between the Lower and Upper Explosive Limits (LEL and UEL). These
limits are percentages that represent the concentration of the fuel (that is, the chemical vapor)
in the air. If the chemical vapor comes into contact with an ignition source (such as a spark), it
will burn only if its fuel-air concentration is between the LEL and the UEL—because that
portion of the cloud is already pre-mixed to the right mixture of fuel and air for burning to
occur. If the fuel-air concentration is below the LEL, there is not enough fuel in the air to
sustain a fire or an explosion—it is too lean. If the fuel-air concentration is above the UEL,
there is not enough oxygen to sustain a fire or an explosion because there is too much fuel— it
is too rich.
When a flammable vapor cloud is dispersing, the concentration of fuel in the air is not uniform;
there will be areas where the concentration is higher than the average and areas where the
concentration is lower than the average. This is called concentration patchiness. Because of
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 172 ONGC.
concentration patchiness, there will be areas (called pockets) where the chemical is in the
flammable range even though the average concentration has fallen below the LEL. Because of
this, ALOHA's default flammable LOCs are each a fraction of the LEL, rather than the LEL
itself. ALOHA uses 60% of the LEL as the default LOC for the red threat zone, because some
experiments have shown that flame pockets can occur in places where the average
concentration is above that level. Another common threat level used by responders is 10% of
the LEL, which is ALOHA's default LOC for the yellow threat zone. The flammable LOC
threat zones for methane release are as follows:
Red : 26,400 ppm = 60% LEL = Flame Pockets
Yellow: 4,400 ppm = 10% LEL
Well site risk contour maps for worst case scenario prepared based on ALOHA modeling of
natural gas releases for flammable vapour cloud has been presented in Figure 5.3-5.5 below
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 173 ONGC.
FIGURE 5-3: SCENARIO I - RISK CONTOUR MAP
THREAT ZONE:
Threat Modeled: Flammable Area of Vapor Cloud
Model Run: Gaussian
Red : 45 meters --- (26,400 ppm = 60% LEL = Flame Pockets)
Note: Threat zone was not drawn because effects of near-field patchiness make dispersion
predictions less reliable for short distances.
Yellow: 114 meters --- (4,400 ppm = 10% LEL)
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 174 ONGC.
FIGURE 5-4: SCENARIO II - RISK CONTOUR MAP
THREAT ZONE:
Threat Modeled: Flammable Area of Vapor Cloud
Model Run: Gaussian
Red : 65 meters --- (26,400 ppm = 60% LEL = Flame Pockets)
Yellow: 163 meters --- (4,400 ppm = 10% LEL)
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 175 ONGC.
FIGURE 5-5: SCENARIO III - RISK CONTOUR MAP
THREAT ZONE:
Threat Modeled: Flammable Area of Vapor Cloud
Model Run: Gaussian
Red : 92 meters --- (26,400 ppm = 60% LEL = Flame Pockets)
Yellow: 228 meters --- (4,400 ppm = 10% LEL)
The zone of flammable vapour cloud calculated for hypothetical natural gas release under risk
scenarios discussed in the earlier sections have been presented in the Table 5.7 below.
TABLE 5-7: ZONE OF FLAMMABLE VAPOUR CLOUD – NATURAL GAS RELEASE SCENARIOS
Release
Type
Release Rate
(kg/s)
Red – 60%
LEL (m)
Yellow -10%
LEL (m)
Small 0.5 45 114
Medium 1 65 163
Large 2 92 228
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 176 ONGC.
Hence for a worst case scenario (2kg/s) the flammable vapor cloud zone/flame pockets’
resulting from accidental release of natural gas will be covering a radial zone of 92 m from
source with the flammable gas concentration within this zone being 26,400 ppm.
Based on the flammable vapour cloud concentration modeled for the worst case scenario (10
kg/s) an effort was made to establish the overpressure (blast force zone) that may result from
delayed ignition of vapour cloud generated from any such accidental release. For overpressure
risk modeling using ALOHA a delayed ignition time of 5 minutes was considered of the vapour
cloud mass. However the threat modeled revealed that Level of Concern (LOC) was never
exceeded that may possibly lead to damage to property or life within the blast radius. The
results have been provided in Figure 5.6 below
FIGURE 5-6: SCENARIO III (WORST CASE) – OVERPRESSURE RISK MODELING RESULTS
Risk Ranking – Blowout Natural Gas Release (Worst Case Scenario)
Likelihood ranking 3 Consequence ranking 4
Risk Ranking & Significance = 9 i.e. “Medium”
Preventive and Mitigation Measures
Blowouts being events which may be catastrophic to any well operation, it is essential to take
up as much a preventive measures as feasible. This includes:
Necessary active barriers (eg. Well-designed Blowout Preventor) be installed to control
or contain a potential blowout.
Weekly blow out drills be carried out to test reliability of BOP and preparedness of
drilling team.
Close monitoring of drilling activity be done to check for signs of increasing pressure,
like from shallow gas formations.
Installation of hydrocarbon detectors.
Periodic monitoring and preventive maintenance be undertaken for primary and
secondary barriers installed for blow out prevention, including third party inspection &
testing
An appropriate Emergency Response Plan be finalized and implemented by ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 177 ONGC.
Marking of hazardous zone (500 meters) around the well site and monitoring of human
movements in the zone.
Training and capacity building exercises/programs be carried out for onsite drilling
crew on potential risks associated with exploration drilling and their possible mitiga t ion
measures.
Installation of mass communication and public address equipment.
Good layout of well site and escape routes.
Additionally, ONGC will be adopting and implementing the following Safe Operating
Procedures (SOPs) developed as part of its Onsite Emergency Response Plan to prevent and
address any blow out risks that may result during drilling and work over activities:
Blow Out Control Equipment
Choke lines and Choke Manifold Installation with Surface BOP
Kill Lines and Kill Manifold Installation with Surface BOP
Control System for Surface BOP stacks
Testing of Blow Out Prevention Equipment
BOP Drills
5.3.2 Non-process fires/explosions
Non-process fires are any fires and explosions that involve material other than hydrocarbons
(e.g. electrical fires, diesel fires, accommodation fires, DG set fires, miscellaneous sources
etc.). Most non-process fires are small incidents which can be managed within the facility using
existing firefighting equipment’s. Such fires have however a higher frequency of occurrence
compared to process fires and explosions as recorded by HSE database. Due to the absence of
veritable data source recording non-process fire/explosion incidents for onshore installat ions
the aforesaid databases for upstream oil and gas sector have been referred in an effort to analyze
non-process fire/explosion risks with respect to the proposed onshore exploratory project.
Historically few fatalities have been reported from non-process fires and most of them have
been successfully managed at the installation level. Based on the WOAD 1996 statistical report,
the average fatality rate for non-process fires is estimated at 10-3 platform year. Again, these
fatalities have already been addressed under risks covered under personal accidents and need
not be considered for fatalities due to non-process fires. However, as they have a higher
probability to occur such incidents may cause inconveniences and come in the way of smooth
operation of the drilling activities. The frequency of occurrence of fires due to possible non-
process accident has listed in the Table 5.8 below:
TABLE 5-8: FREQUENCY OF OCCURRENCE - NON-PROCESS FIRES
Non-Process Accidents Frequency (per year)
Electrical fires 7.0 X 10-2
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 178 ONGC.
Diesel fires 9.2 X 10-3
Machinery fires 2.2 X 10-3
Miscellaneous fires 2.1 X 10-3
Source: WOAD
As a result, though the damage potential is low, it is important to take appropriate safeguard
measures to minimize their occurrence. Many of these measures can be implemented through
the stipulation of simple work instructions and procedures.
Risk Ranking for Non-Process Fires
Likelihood ranking 3 Consequence ranking 1
Risk Ranking & Significance = 3 i.e. “Low”
Preventive and Mitigation Measures
The preventive and mitigation measures for small non-process fires would be implemented by
delineating appropriate operational procedures through the existing safety management system.
5.3.3 Pipeline Failure
In addition to risk assessed with respect to the proposed project in the form of “Blow Outs”
efforts has also been made to understand the potential risks/hazards associated with respect to
existing industrial operations in the near vicinity. Based on the information made available by
ONGC and site visits undertaken it is understood that nearly 22 nos. Gas Collection Stations
(GCS) of ONGC along with integrated pipeline network (4” dia) is operational in the Ramanad
area. Hence potential risks have been identified in the form of loss of containment events for
each section of the pipeline, corresponding to the relevant process conditions, as listed in Table
5.9.
TABLE 5-9: SCENARIOS FOR QRA STUDY
Sl.
No Plant Section
Initiating
Event Risk Scenario
Potential Outcome
Scenario
1 Pipeline Rupture 4” pipeline rupture Jet fire, flash fire
Pipeline Failure Frequency Analysis
An effort has also been made to understand the primary failure frequencies of gas pipeline
which is the result of the number of incidents within a period divided by the corresponding
total system exposure. Based on the European Gas Pipeline Incident Data Group (EGIG)
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 179 ONGC.
database the evolution of the primary failure frequencies over the entire period and for the last
five years has been provided in Table 5.10below.
TABLE 5-10: PRIMARY GAS PIPELINE FAILURE FREQUENCY
Period No. of Incidents Total System
Exposure (km.yr)
Primary failure
frequency
(1000 km.yr)
1970-2007 1173 3.15.106 0.372
1970-2010 1249 3.55.106 0.351
1971-2010 1222 3.52.106 0.347
1981-2010 860 3.01.106 0.286
1991-2010 460 2.25.106 0.204
2001-2010 207 1.24.106 0.167
2006-2010 106 0.654.106 0.162
Source: 8h EGIG Report
As referred in the above table the overall failure frequency (0.35) of the entire period (1970-
2010) is slightly lower than the failure frequency of 0.37 reported in the 7 th EGIG report (1970-
2007). The failure frequency of the last 5 years was found to be half the primary failure
frequency over the entire period showing the improved performance over the recent years.
Incident Causes
Natural gas pipeline failure incidents can be attributed to the following major causes viz.
external interference, construction defects, corrosion (internal & external), ground movement
and hot tap. The distribution of incidents with cause has been presented in the Figure 5.6
below.
FIGURE 5.6: NATURAL GAS PIPELINE FAILURE – DISTRIBUTION OF INCIDENT & CAUSES
Source: 8th EGIG Report
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 180 ONGC.
The interpretation of the aforesaid figure indicated external interference as the major cause of
pipeline failure contributing to about 48.4% of the total failure incidents followed by
construction defects (16.7%) and corrosion related problems (16.1%). Ground movement
resulting from seismic disturbance, landslides, flood etc contributed to only 7.4% of pipeline
failure incident causes.
The pipeline failure frequency viz. leaks or rupture from natural gas transportation pipeline
with respect to the proposed project has been established based on the interpretation of the
database of European Gas Pipeline Incident Data Group (EGIG) representing almost 2 million
kilometer year of pipeline operations. The failure rate reported by EGIG for on-shore gas
pipeline with design pressure greater than 15 bar is 4.76 x 10-4 km/year. Full Bore Rupture
(FBR) represents 13% of the cases (6.188 x 10-5 failure /km/yr) and 87% of the cases
represents Leaks (4.14 x 10-4 failure /km/yr).
The frequency of pipeline failure computed for the proposed project based on EGIG failure
frequency is presented in the Table 5.11 below.
TABLE 5-11: NATURAL GAS PIPELINE FAILURE FREQUENCY
Sl. No Pipeline Failure Case
EGIG Failure
Frequency
(per km.year)
Longest
Pipeline
Length (km)
Project Pipeline
Failure Frequency
(per year)
1 Gas Pipeline Rupture 6.188 x 10-5 9.39 5.81 x 10-4
2 Gas Pipeline Leak 4.14 x 10-4 9.39 3.88 x 10-3
Pipeline Failure – Ignition Probability
In the period 1970-2010, only 4.4% of the gas releases recorded as incidents in the EGIG
database ignited. Ignition depends on the existence of random ignition sources. The EGIG
database gives the opportunity to evaluate the link between ignition and leak size.
The ignition probability of pipeline failure (rupture & leaks) with respect to the proposed
project is derived based on the following equations as provided in the IGEM/TD/2 standard
P ign = 0.0555 + 0.0137pd2; for 0≤pd2≤57
(Ignition Probability for pipeline ruptures)
P ign = 0.81; for pd2>57
P ign = 0.0555 + 0.0137(0.5pd2); for 0≤0.5pd2≤57
(Ignition Probability for pipeline leaks)
P ign = 0.81; for 0.5pd2>57
Where:
P ign = Probability of ignition
p = Pipeline operating pressure (bar)
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 181 ONGC.
d = Pipeline diameter (m)
The ignition probability of natural gas release from 4” pipeline leak or rupture is calculated
based on the above equations utilizing the following input parameters as discussed below.
Based on the aforesaid calculation the probability of jet fire occurring from accidental gas
release from pipeline leak or rupture and subsequent ignition has been presented in Table 5.12
below:
TABLE 5-12: NATURAL GAS CONNECTIVITY - PROBABILITY OF JET FIRE
Sl.
No Pipeline Failure Case
Project Pipeline Failure
Frequency (per year)
Ignition
Probability
Jet fire
Probability
1 4” Gas Pipeline Rupture 5.81 x 10-4 0.06 3.48 x 10-5
2 4” Gas Pipeline Leak 3.88 x 10-3 0.06 2.32 x 10-4
Pipeline Failure - Consequence Analysis
Pipeline generally contains large inventories of oil or gas under high pressure; although
accidental releases from them are remote they have the potential of catastrophic or major
consequences if related risks are not adequately analyzed or controlled. The consequences of
possible pipeline failure is generally predicted based on the hypothetical failure scenario
considered and defining parameters such as meteorological conditions (stability class), leak
hole & rupture size and orientation, pipeline pressure & temperature, physicochemica l
properties of chemicals released etc.
As discussed earlier, jet fire have been identified as the possible consequences resulting from
release and is dependent on the ignition time. Taking into account the gas gathering and
Pipeline Inlet Pressure (bar) = p= 70 kg/cm2 or ~68 bar
Pipeline diameter = d = 4 inches or 0.101 m
For 4” pipeline rupture pd2 = (68) X (0.101)2 = 0.693
For 4” pipeline leak 0.5 pd2 = 0.5 X (68) X (0. 101)2 = 0.346
Since 0≤pd2≤57 and 0≤0.5pd2≤57, the following equation has been utilized for deriving the
ignition probability for pipeline failure.
P ign for 4’ pipeline rupture = 0.0555 + 0.0137pd2 = 0.0555 + 0.0137 (0.693) = 0.065
P ign for 4” pipeline leak = 0.0555 + 0.0137(0.5pd2) = 0.0555 + 0.0137 (0.346) = 0.060
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 182 ONGC.
processing facilities and pipeline the hypothetical risk scenarios as provided in Table 5.7 have
been considered for failure consequence modeling with respect to proposed project. In addition
to the above the following design specifications as presented in Table 5.13 have been
considered for consequence modeling
TABLE 5-13: PIPELINE DESIGN SPECIFICATIONS
Sl.
No. Parameters Values
1 Pipeline diameter (inch) 4 inch
2 Longest Pipeline length (km) ~9.4 km
4 Design pressure (bar)* 68
5 Design temperature (in °C) 50
In the present study, we have estimated the consequence of each reference scenarios (as
mentioned in Table 5.7) in terms of fatality only. For each effect type (i.e. radiation,
overpressure and toxic release), a set of threshold values were considered having 1, 5, 10, 20
and 50% fatality. These threshold values were derived from Probit functions using the
following equations:
Thermal Radiation [1]: Pr = -14.9 + 2.56 x In (Q4/3 x t)......................................... Eq.
Overpressure [2]: Pr = 1.47 + 1.37 ln (p) ..................................................... Eq.
Toxic release [3]: Pr = a +b x In (Cn x t) ....................................................... Eq.
where,
Pr = Probit
Q = heat radiation (W/m2)
t = exposure time (s)
p = peak overpressure (psig)
a, b, n = constants describing the toxicity of a substance
C = concentration (mg/m3)
t = exposure time (minutes)
TABLE 5-14: THRESHOLD VALUES FOR EACH EFFECT LEVEL
Fatality (%) Radiation (kW/m2) Overpressure (psi)
50 26.50 13.10
20 20.78 7.15
10 18.25 5.20
5 16.42 3.95
1 13.42 2.40
[N. B. The values were derived using the above mentioned Probit equations]
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 183 ONGC.
Based on these threshold values, effect distances were calculated to delineate different threat -
zones for each reference scenario. The analysis made use of the ALOHA model, one of the
most commonly used effect models to generate the consequence effects showing the estimated
distances for each scenario considered to a specified hazard end-point. These zones are
displayed on a single Threat Zone plot displayed as red, orange and yellow with red
representing the worst hazard. The threat zone displayed by ALOHA represent thermal
radiation levels and also indicates the effects on people who are exposed to those thermal
radiation levels but are able to seek shelter within one minute.
Predominant local meteorological conditions and composition of the natural gas as provided
by ONGC was also considered for this study. Nearly about 91.5% of the natural gas is
constituted by methane with ethane representing the remaining 4%.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 184 ONGC.
Case I: Release of natural gas from valves/flanges of GCS – hole size (1”dia)
The jet fire threat zone plot for release and ignition of flammable natural gas from GCS
facility valves/flanges leak of size - diameter 1 inch is represented in Figure 5.7 below.
FIGURE 5.7: THREAT ZONE PLOT FOR JET FIRE – 1” DIA LEAK
THREAT ZONE:
Threat Modeled: Thermal radiation from jet fire
Yellow: 11 meters --- (13.42 kW/ (sq m) = 1% fatality
The worst hazard for release and ignition of natural gas from complete rupture of 1” dia
pipeline will be experienced to a maximum radial distance of 11m from the source with 1%
fatality.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 185 ONGC.
Case II: Ignition of natural gas from complete rupture of 4” pipeline
The complete rupture of 4” pipeline will result in the release of natural gas (in gaseous phase)
the ignition of which is likely to result in jet fire. The threat zone plot of jet fire resulting from
pipeline rupture is derived using ALOHA and represented in Figure 5.8.
FIGURE 5.8: THREAT ZONE PLOT FOR JET FIRE - 4” PIPELINE RUPTURE
THREAT ZONE
Threat Modeled: Thermal radiation from jet fire resulting from full bore rupture
Red : 11 meters --- (26.50 kW/ (sq m) = 50% fatality
Orange: 14 meters --- (18.25 kW/ (sq m) = 10% fatality
Yellow: 17 meters --- (13.42 kW/ (sq m) = 1% fatality
The worst hazard for release and ignition of natural gas from complete rupture of 4” dia
pipeline will be experienced to a maximum radial distance of 11m from the source with 50%
fatality.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 186 ONGC.
For various hypothetical scenarios considered with respect to proposed production project, the
threat zones calculated using ALOHA for defined thermal radiation intensities have been
presented in the Table 5.15 below.
TABLE 5-15: THREAT ZONE DISTANCE FOR HYPOTHETICAL RISK SCENARIOS
Case
No Pipeline Failure Case
Hole Size
(inch)
Distance to
26.50 kW/m2
(m) – 50%
fatality
Distance to
16.42 kW/m2
(m) – 10%
fatality
Distance to
13.42 kW/m2
(m) – 1%
fatality
I Valves/flanges leak 1.00 <10 <10 11
II 4” pipeline rupture 4.00 11 14 17
Modeling Risk of Overpressure from Vapour Cloud Explosion
A flash fire is the most likely outcome upon ignition of a dispersing vapour cloud from a natural
gas release. If ignited in open (unconfined) areas, pure methane is not known to generate
damaging overpressures (explode). However, if the gas is ignited in areas where there is
significant degree of confinement and congestion an explosion may result.
Although an unconfined explosion is considered to be unlikely for the proposed project an
effort has been made to establish the overpressure (blast force zone) that may result from
delayed ignition of vapour cloud generated from any such accidental release from ruptures. For
overpressure risk modeling using ALOHA a delayed ignition time of 15 minutes was
considered of the vapour cloud mass. However the threat modeled revealed that Level of
Concern (LOC) was never exceeded that may possibly lead to loss of life within the blast
radius. This is in agreement with the earlier assessment that no damaging overpressure is likely
to be generated from unconfined ignition of natural gas vapour cloud. The results have been
provided below
VCE MODELING RESULTS FOR OVERPRESSURE
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 187 ONGC.
Individual Risk
Individual risk is the probability at which an individual may be expected to sustain a given
level of harm from the realization of specified hazards. In simple terms it is a measure to assess
the overall risk of the area concerned thus to protect each individual against hazards involving
hazardous chemicals, irrespective of the size of the accident that may occur. Graphically it
represents as iso-risk contour which connects all of the geographical locations around a
hazardous activity with the same probability of fatality.
In order to generate different level of iso-risk curves for the area concerned, it is required to
estimate the respective contribution of each reference scenario. Accordingly, individual risk of
each scenario was estimated by combining the frequency of the initiating event, the conditiona l
probability of that scenario sequence and the Probit value of the effect footprints. In particular
following expression was used to estimate the Individual Risk (IR) at a given geographica l
location for each reference scenario:
IR(x, y, i) = fi. PFi ………………………………………………………………………………………………… (Eq. iv)
where:
- fi is the frequency of the accident scenario i (year-1); calculated as multiplicative factor of the
frequency of the initiating event and the probability that the sequence of events leading to the
accident scenario i will occur: fi = fincident i . Psequence i
- PFi is the probability of fatality that the accident scenario i will result at location (i.e. Probit).
The individual risk so obtained is then compared with the Tolerance Criteria of Individual Risk
as provided in the Figure 5.9below.
FIGURE 5.9: TOLERANCE CRITERIA FOR INDIVIDUAL RISKS
Hence for the proposed project the individual risk has been considered only for pipeline rupture
as no predicted fatality has been established for the consequence modeling undertaken for
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 188 ONGC.
natural gas release ignition from blow outs and/or valves/flanges of the GGS facility. Based
on the above equation the individual risk as calculated including the tolerance criteria has been
presented in the Table 5.16 below.
TABLE 5-16: INDIVIDUAL RISK – PIPELINE RUPTURE
Accident Scenario
Frequency Fatality Probability Individual Risk
Individual Risk
Criterion
A. 4 inch Pipeline Rupture
3.48 x 10-5 0.50 1.7 x 10-5 ALARP
3.48 x 10-5 0.10 3.5 x 10-6 Tolerable
3.48 x 10-5 0.01 3.5 x 10-7 Tolerable
B. GCS Leak
2.30 x 10-4 0.01 2.3 x 10-6 Tolerable
The individual risk resulting from proposed project particularly from nearby GCS and pipeline
operations in most cases is assessed to be within tolerable limits. The maximum off-site risk is
computed to be 1.7 x 10-5 which falls in the ALARP region of the individual risk criterion.
Likelihood ranking 3 Consequence ranking 3
Risk Ranking & Significance = 9 i.e. “Low”
5.4 DISASTER MANAGEMENT PLAN
5.4.1 Objective
The primary objective of the DMP is to provide a safe, timely, effective and coordinated
response by the onsite Emergency Response Team (ERT), along with the other local and
government agencies/departments to prevent or minimize any major emergencies that may
arise from possible failures/risks viz. blow outs, oil spill, fire & explosion etc. associated with
drilling.
The main objectives of this plan are:
To minimize the risk for human life, environment and common property resources, by
means of an effective and efficient intervention;
Protection of the environment;
Protection of public safety;
To initiate the early and efficient response throughout the utilization of all availab le
resources.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 189 ONGC.
5.4.2 Purpose
The purpose of the DMP is to effectively manage and control the emergencies occurring during
project operations. This DMP ensures,
Emergency response group is effective & adequate;
Clear roles and responsibilities of key personnel & support groups;
Availability and adequacy of emergency infrastructure & resources; and
Efficient emergency communication
5.4.3 Emergency Classification
Due consideration is given to the severity of potential emergency situation that may arise as a
result of storage tank as discussed in the Quantitative Risk Analysis (QRA) study. Not all
emergency situations call for mobilization of same resources or emergency actions and
therefore, the emergencies are classified into three levels depending on their severity and
potential impact, so that appropriate emergency response procedures can be effective ly
implemented by the Emergency/Crisis Management Team. The emergency levels/tiers defined
with respect to this project based on their severity have been discussed in the subsequent
sections with 'decision tree' for emergency classification being depicted in Figure 5-3.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 190 ONGC.
FIGURE 5-2: EMERGENCY CLASSIFICATION “DECISION TREE”
5.4.4 Level 1 - Emergency
An event that can be dealt with by on-site/location personnel and resources; the event does not
have any effect outside the site and external agencies are unlikely to be involved. There is
unlikely to be danger to life, to the environment, or to Company assets or reputation. The
Disaster Management Plan and relevant procedures are activated; the Site Head is notified.
5.4.5 Level 2 - Emergency
It is an event which may be dealt by the ONGC Emergency/Crisis Management Team but
requires involvement of wider Company support and external services. The initial event may
be “on-site”, having some effects outside the site or be “off-site”, and external emergency
services will be involved. There is likely to be a danger to life, the environment, or company
assets or reputation. The Disaster Management Plan and relevant procedures are activated;
EMERGENCY
Activate Disaster Management Plan
Mobilization of equipment/human resources
available onsite is sufficient to contain the
emergency
Containment of emergency requires
involvement of additional resources and local
emergency responder group’s viz. local police,
fire brigade etc
NO
YES LEVEL 1
EMERGENCY
YES LEVEL 2
EMERGENCY
Management of emergency requires the
involvement of District/State Disaster
Management Team
NO
YES LEVEL 3
EMERGENCY
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 191 ONGC.
local administrative bodies and Emergency Response Groups including ONGC India Corporate
are notified.
5.4.6 Level 3 - Emergency
It is a major event which requires the involvement of District or State Crisis Management
Group. For Company this may result from insufficient local resources and/or because the
incident has broader implications such as reputation, legal prosecution, financial loss etc. Under
such circumstances, the Disaster Management Plan is activated; ONGC India Corporate,
District/State Administrative Authorities and other Emergency Response Groups are notified.
The criterion for classification of various levels of emergencies and associated response has
been presented in the Figure 5-4 below.
FIGURE 5-3: EMERGENCY RESPONSE LEVELS
Level Type Criteria for Classification
Level 1 Small Minor medical or injury case requiring no external support
Equipment damage without any significant impact on operation
Minor fire without any personnel injury or plant damage
Net negative financial impact of <1 crores.
Small operational spills
No potential impact on flora and fauna of identified eco-sensitive areas.
Local stakeholder concern and public attention
Level 2 Medium Fire and explosion which requires external assistance
Requires evacuation of injured personnel and locals through assistance from
local emergency groups.
Loss of corporate image and reputation
Adverse impact on environmental sensitivities (if any) within a radius of
1km.
Medium sized spills
Net negative financial impact of 1 - 5crore
Level 3 Large
Incident leading to multiples injuries or fatalities
Requires assistance from District/State emergency responding groups.
Adverse impact on environmental sensitivities (if any) within a radius of
>1km.
Major oil spills
State/nationwide media coverage
Net negative financial loss of >5crore
5.4.7 ONGC Emergency Response/Crisis Management Team
ONGC has in place an Emergency Response/Crisis Management Team to respond to fire,
blow-out, spills, accidents and technical emergencies. These teams will be made up from
operations personnel, who can be called upon 24 hours a day, supported by senior management
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 192 ONGC.
field personnel as and when required. The emergency response teams will receive specific
training for their roles and exercise on a regular basis.
5.4.8 Action Plan for Fire Fighting
General
As soon as fire is noticed, shout “FIRE” “FIRE” “FIRE” or “AAG” “AAG” “AAG”. Try to
eliminate the fire by using proper portable fire extinguishers.
Installation Manager
He should ensure regularly the working status of fire equipment / its maintenance through fire
section and see that they are kept in their respective places as per the need. As soon as, the fire
accident is reported, rush to site and take charge of the situation. Inform Mines Manger besides
Area Manager as well Fire Manager.
Shift In-charge
If situation demands sound “Hooter”; call on the nearest Fire Services and Hospital attending
doctor. Inform Installation Manager / Field Manager / Surface Area Manager. Give instruct ions
to the assembled staff and get the best out of them.
Drilling Officials
Remove other inflammable materials to the safer distance. Remove important documents to a
safer place. The first aid trained persons should be ready to give first aid to the injured persons
and move them to the hospital if required. Get well acquainted with the location of the wells.
Electrical Officials
No naked flame should be allowed. Generator should be stopped. Electrical lines are required
to be de-energized. See that uninterrupted supply of water from tube well to the fire services.
Mechanical Officials
Get the instruction from the Shift In-charge to act accordingly to stop the equipment and ready
to carry out repair jobs if required like pump problems of fire services etc. Help production
officials in removing inflammable materials.
Transport Officials
Get vehicles parked at a safer distance. See that approach road is clear for fire services vehicle
to the approach the accident site.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 193 ONGC.
Security at Gate
To prevent unauthorized entry of persons / vehicles inside the area of responsibility and also to
ensure no abnormal activity by unauthorized persons is allowed.
Fire Officials
On arrival they fight fire with the assistance of site staff in extinguishing the fire. If the situation
still proves to be beyond control, then the help from the nearest agencies could be taken.
Fire Control Room
A fire control room will be set up for smooth functioning of firefighting/ rescue operations at
the site of incident. Manager (F.S)/ one fire officer or senior most person of fire section will be
I/C of that control room. Meanwhile one Fire officer will take charge of Control Room of
Central Fire Station to assist/ back support for required fire equipment / man power. In charge
control room of Central fire Station will be responsible for arranging of man power and
equipment if required at site.
Area Manager: (In Case of Major Fire)
Pre-identified source of additional water to be used for uninterrupted supply of water. If
situation demands, pits be dug to store sufficient water, pipeline be laid to carry water from the
sources to water pits. Maintenance party to remain to attend any problem. Besides special
maintenance team is immediately sought from the workshop. Arrangements to provide
flameproof lights at a safer distance.
Arrangements to provide mud and chemicals necessary to control situation. Arrangements for
food, water, temporary rest rooms or tents for the officials on the round the clock duty at site.
To keep ready fleet of jeeps, tractors, crane to meet demand
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 194 ONGC.
6 Environmental Management Plan & Monitoring Framework
This Environmental Management Plan and Monitoring Framework is a site specific document
for the exploratory, development and testing of hydrocarbons that has been developed to ensure
that ONGC can implement the project in an environmentally conscious manner and where all
contractors, understand the potential environmental risks arising out of the proposed project
and take appropriate actions to properly manage such risk.
This EMP will be an overview document that will guide environment management of all
aspects of ONGC’s activities within the block. This EMP will be backed up by more specific
Environmental Action Plans, Procedures and Bridging Documents with the progress of the well
site preparation, exploratory and development drilling, well testing and site decommissioning
activities.
The EMP describes the actions to be adopted in terms of:
National Policies and Regulations
Best Practices and guides
Local Environmental and Social Sensitivities
The Environment Policy of ONGC is presented at Box 6.1.
Box: 6.1: ONGC Corporate Environment Policy
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 195 ONGC.
6.1 ENVIRONMENT MANAGEMENT PLANS
The Environment Management Plan details out the mitigation measures to be implemented by
both ONGC and the Contractors during various stages of the exploratory and testing of
hydrocarbons within the PML block. The following environmental management plans have
been formulated in line with the proposed project activities viz. site preparation, exploratory
and development drilling, well testing and decommissioning
Pollution Prevention and Abatement Plan
Waste Management Plan
Storm Water Management Plan
Wildlife Management Plan
Road Safety and Traffic Management Plan
Occupational Health & Safety Management Plan
ONGC will ensure communication and implementation of the aforesaid management plans
prior to the commencement of site preparation and exploratory and development well drilling
operations in the field. In addition, the mitigation measures for social issues and concerns are
also separately presented in this report. An Emergency Response Plan to address technologica l
emergency situations viz. blow outs, fires, oil spill etc. etc. that may arise out of drilling
operations has already been discussed in previous chapter. In cases, where there are possible
overlaps, the plans have been cross-referenced to avoid repetition. Additional mitiga t ion
measures to ensure effective management of identified environmental aspects during various
phases of the proposed project have been discussed under the aforesaid plans in the subsequent
sections.
6.1.1 Pollution Prevention and Abatement Plan (PPAP)
Scope
The Pollution Prevention and Abatement Plan (PPAP) is applicable for and encompasses both
construction and operational phase activities for the proposed project which has the potential
to adversely impact ambient air and noise quality, surface and ground water quality and soil
quality of the Field.
Purpose
The PPAP establishes specific measures and guidelines aimed at effectively addressing and
mitigating the air, noise, water and soil quality impacts that may arise as result of well site
preparation and access road construction/strengthening, drilling operations, well testing and
decommissioning/site closure. The plan also details out roles and responsibilities of ONGC and
the contractors to ensure effective implementation of the plan.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 196 ONGC.
Mitigation Measures & Strategies
The following mitigation measures need to be adopted and implemented by ONGC and its
contractors during various phases of the proposed project to prevent and control air emissions
(both point and fugitive), high noise generation, soil contamination and fertility loss,
contamination and depletion of ground water resources and storm water discharge.
A. Control of fugitive and point source emissions
Project Phase Mitigation measures
Construction Siting of exploratory well and borrow areas away from human
settlement/habitation and sensitive receptors. Special care will be
taken for Wells 3,10, 13 as they were located very close ( around
200 m) to human settlement.
Vehicles delivering raw materials like soil and fine aggregates will
be covered to prevent fugitive emissions.
Storage and handling of raw material and debris will be carefully
managed to prevent generation of fugitive dust.
Sprinkling of water on earthworks, material haulage and
transportation routes on a regular basis during dry season.
All vehicles, equipment and machinery used for construction will
be subjected to preventive maintenance as per manufacturer norms.
All vehicles utilized in transportation of raw material and personnel
will have valid Pollution under Control Certificate (PUC).
Vehicular exhaust will be complying with the CPCB specified
emission norms for heavy diesel vehicles.
The top soil generated from site clearance activities will be stored
in designated area and stabilized to prevent fugitive dust emissions.
Drilling and well testing Locations of flare stack will be governed by the presence of
habitation and sensitive receptors. Special care will be taken for
Wells 3,10, 13 as they were located very close ( around 200 m) to
human settlement .
Duration of flaring will be minimized by careful planning;
Exhausts of engines on the drilling rig diesel generators will be
positioned at a sufficient height to ensure dispersal of exhaust
emissions; engines will not be left running unnecessarily.
Preventive maintenance of DG sets will be undertaken as per
manufacturers schedule to ensure compliance with CPCB specified
generator exhaust.
Decommissioning/Site
Closure
Mitigation measures to address the air quality impacts resulting from
vehicular movement, operation of heavy construction machinery and
material handling are similar to those discussed above
B. Control of Noise and Vibration
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 197 ONGC.
Project Phase Mitigation measures
Construction Selection and use of low noise generating equipment equipped with
engineering controls viz. mufflers, silencers etc
All vehicles utilized in transportation of raw material and personnel
will have valid Pollution under Control Certificate (PUC)
Periodic preventive maintenance of vehicles as per manufacturer’s
schedule to ensure compliance with the vehicular noise limits
specified by CPCB
All high noise generating equipments will be identified and
subjected to periodic preventive maintenance.
No night time operation of vehicles and construction activities will
be undertaken.
Engines of vehicles and construction equipment will be turned off
when not in use for long periods.
Drilling Siting of drilling rig and facilities away from sensitive receptors
viz. schools, settlements etc. with all reasonable screening being
utilized where necessary. Special care will be taken for Wells 3,10,
13 as they were located very close ( around 200 m) to human
settlement .
Installing acoustic enclosures and muffler on engine exhaust of DG
sets to ensure compliance with generator noise limits specified by
CPCB.
Restrict all noise generating operations ,except drilling, to daytime;
Periodic monitoring of noise levels on site and nearby receptors to
ensure compliance with Noise Pollution (Regulation & Control)
Rules 2000.
Decommissioning/Site
Closure
Management measures to address noise impacts with respect to
operation of heavy equipments/machinery and movement of vehicles
during decommissioning/site closure phase are similar to those
discussed in the “Construction Phase” of this section
C. Prevention and Control of Soil Quality Impacts
Project Phase Mitigation measures
Construction
Site preparation and road strengthening/widening activities will be
restricted within defined boundaries.
Avoid construction activities during monsoon season as moist soil
is most susceptible to compaction.
Use appropriate machinery and/or protective boarding during top
soil stripping to ensure minimum compaction.
Debris and excavated material generated during construction
activities will be stockpiled in designated areas onsite. No material
will be disposed in adjacent land surrounding the site boundary.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 198 ONGC.
Project Phase Mitigation measures
For cleared areas, retain top soil in stockpile where possible on
perimeter of site for subsequent re-spreading onsite during
restoration.
Install and maintain effective run-off controls, including silt traps,
straw barriers etc. so as to minimize erosion.
Drip trays to be used during vehicular/equipment maintenance and
during refueling operations.
In case of a spill, the spilled soil is to be removed and stored in
hazardous waste storage area
Drilling All chemical and fuel storage areas will be designed considering
site slope.
Fuel and chemical storage areas will be paved and properly
bunded. Bunded areas will be designed to accommodate 110% of
the volume of spilled material.
Spill kits will be made available at all fuel and chemical storage
areas. All spills/leaks contained, reported and cleaned up
immediately.
Drip pans/trays will be used in areas identified having spillage
potential but not limited to drill rig engine; electric generator
engine; pumps or other motors; maintenance areas; fuel transfer
areas.
In case of a spill, the spilled soil is to be removed and stored in
hazardous waste storage area
Management of drill cuttings, waste drilling mud, waste oil and
domestic waste will be made in accordance with “Waste
Management Plan”
Decommissioning/Site
Closure
Decommissioning at the end of project life/drilling will have some
adverse impacts in terms of increase in soil erosion and would require
adequate mitigation measures to minimize any adverse impacts. The
mitigation measures will be similar to those outlined for construction
phase activities as discussed earlier.
D. Prevention and Control of Surface Water Quality Impacts
Project Phase Mitigation measures
Construction Minimize clearing and construction activities during monsoon
season (as far as practicable).
Construction work close to the creek or water bodies or coast to
be avoided during monsoon
During site preparation and construction, surface water run-off will
be managed through implementation of proper drainage system
and silt trap and sedimentation tank onsite.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 199 ONGC.
Project Phase Mitigation measures
Run-off discharges to natural drainage channels/water bodies to
conform to CPCB Inland Water Discharge Standards.
Regular inspection of surface water drainage/diversion system and
sediment controls will be undertaken.
Drilling Run-off from vehicular wash and chemical storage areas will be
channeled through closed drainage system provided with an oil-
water separator prior to silt trap and sedimentation tank to disposal
to nearby drainage channels/surface water bodies. Spill kits will be
made available in these areas.
Drip trays will be used during preventive maintenance of vehicles
and machinery.
Hazardous chemicals and fuel drum will be stored in bunded area
equipped with proper spill control equipment.
Management of drill cuttings, waste drilling mud, waste oil and
domestic waste will be made in accordance with “Waste
Management Plan”
Decommissioning/Site
Closure
No significant impacts to surface water quality can be associated with
activities during decommissioning/site closure phase. Any possible
impacts that may arise due to surface run-off will be mitigated in manner
similar to that discussed during construction phase activities.
E. Prevention and Control of Ground Water Quality Impacts
Project Phase Mitigation measures
Construction No significant impact on the ground water quality can be associated
with the construction phase activities
Drilling The exploratory wells will be sited at a sufficient distance away
from an existing tube well or open well.
Proper casing and cementing of exploratory well will be done to
prevent contamination of sub-surface aquifers.
Water based mud to be used as a drilling fluid for the proposed
project
Selection of low toxicity chemicals/additives in the preparation of
water based mud.
Periodic monitoring of ground water quality will be carried out for
village wells located outside the project boundary to assess the
level of ground water contamination, if any.
Storage and disposal of drill cutting and waste mud to be made in
accordance with “Solid & Hazardous Waste Management Plan”
Decommissioning/Site
Closure
No significant impacts to ground water quality can be associated with
activities during decommissioning/site closure phase
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 200 ONGC.
6.1.2 Waste Management Plan
Scope
The Waste Management Plan (WMP) is applicable for all process and non-process waste
streams which are generated during various phases of ONGC’s proposed exploratory,
development and testing of hydrocarbons in Field. The major waste streams covered under this
plan includes drill cuttings, waste drilling mud cuttings, wash water, kitchen waste and sewage.
In addition, waste oil and lead acid batteries generated from the proposed project operations
have also been dealt in this plan.
Purpose
The WMP establishes specific measures to ensure proper collection, storage, treatment and
disposal of the identified process and non-process waste streams in accordance with the
applicable national regulations and guidelines7 and also to ensure compliance with ONGC’s
corporate HSE Policy. The plan also outlines roles and responsibilities of both ONGC and the
contractors involved in the implementation of the plan.
Mitigation Measures
The following mitigation measures need to be adopted and implemented by ONGC and its
contractors for the major waste streams identified in the plan.
7 “Guidelines for Disposal of Waste – CPCB Oil & Gas Extraction Industry Standard” – EPA Notification [GSR
176(E), April 1996]
“Guidelines for disposal of Solid Waste, Drill Cuttings and Drilling Fluids for Offshore & Onshore Drilling
Operation” –MoEF Notification, 30th August 2005
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 201 ONGC.
Waste Quantity Mitigation Measure
Drill Cuttings 400 m3/well Drill cuttings separated from drilling fluid will be
adequately washed and temporarily stored and disposed
in an impervious pit lined by HDPE.
Design aspects of the impervious waste disposal pit will
be communicated/shared by ONGC with Tamilnadu
State Pollution Control Board (TNPCB).
The drill cuttings pit will be bunded.
Periodic monitoring and analysis of drill cuttings will be
undertaken to establish its nature and characteristics.
The waste pit after it is filled up over which a thick layer
of native top soil with proper top slope will be provided.
Feasibility study for use of drill cuttings as a road
construction material in consultation with nodal
authorities
Drilling Mud and wash water
12m3/day Use of water based mud as the drilling fluid.
Use of low toxicity chemicals for the preparation of
drilling fluid.
Barite used in the preparation of drilling fluid shall not
contain Hg>1mg/kg and Cd>3mg/kg
Recycling of drilling mud will be ensured to the
maximum extent possible.
Temporary storage of drilling fluid and wash waste
water will be done in an impervious pit lined with
HDPE.
The waste pit will be bunded to prevent water overflow
during heavy monsoon.
Disposal of drilling wash water will be achieved through
necessary treatment through onsite Effluent Treatment
Plant (ETP) to comply with the CPCB onshore effluent
discharge standard for oil and gas industry.
Kitchen Waste 10-20 kg/day The waste will be segregated and stored in designated
waste bins.
All such waste bins will be properly labeled and covered.
The kitchen waste will be disposed in nearest municipal
dumping site on a daily basis through approved waste
handling contractors
Waste oil Used oil
As generated The hazardous waste (waste and used oil) will be
managed in accordance with Hazardous Waste
(Management, Handling & Transboundary Movement)
Rules, 2008.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 202 ONGC.
Waste Quantity Mitigation Measure
The hazardous waste will be stored in properly labeled
and covered bins located in paved and bunded area.
Necessary spill prevention measures will be made
available at the hazardous material storage area
Storage details of onsite hazardous waste generated will
be maintained and periodically updated.
Adequate care will be taken during storage and handling
of such waste viz. use of proper PPEs by personnel
The hazardous waste so stored (not more than 3 months)
to be periodically sent to TNPCB registered used and/or
waste oil recyclers/ facilities.
Proper manifest as per HWMH rules to be maintained
during storage, transportation and disposal of hazardous
waste.
Sewage 2 m3/day per well
The sewage generated will be treated in a combination
of septic tank and soak pit.
Regular supervision will be undertaken for the domestic
waste treatment system to report any overflows, leakage,
foul odour etc.
Lead Acid Batteries 2-3 batteries per well
Will be recycled through the vendors supplying lead acid
batteries as required under the Batteries (Management &
Handling) Rules, 2001.
Proper manifest will be maintained as per Batteries
(Management & Handling) Rules, 2001.
Recyclables viz. paper, plastic, packaging waste etc.
Depending on usage
Proper segregation and storage of recyclable waste in
designated bins onsite.
Recyclables will be periodically sold to local waste
recyclers.
In addition to the management measures specified for the major waste stream, ONGC will
prepare and update periodically a waste management inventory of all waste streams identified
for the proposed project. Necessary measure will also be taken by ONGC to incorporate
appropriate waste management and handling procedures in the contractor work document and
conduct periodic training of personnel involved in waste handling onsite to ensure proper
implementation of the WMP. In this regard, necessary inspection, record keeping, training
program and monitoring procedures will be established by ONGC and made operational to
achieve proper management of all wastes generated on site.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 203 ONGC.
6.1.3 Storm Water Management Plan
Scope
The Storm Water Management Plan (SWMP) refers to the proper management of surface run-
off generated during monsoons for various phases of activities involved in the project.
Purpose
The purpose of Storm Water Management Plan (SWMP) is to ensure prevent and control any
adverse impact of discharge of storm water from the well site and road widening/strengthening
areas to nearby natural drainage channels and community water bodies. Proper management
of storm water runoff will minimize damage to public and private property, reduce effects of
development on land, control stream channel erosion, pollution and sediment deposition and
also reduce local flooding.
Mitigation Measures
Pipe drainages will be provided for diversion roads constructed for the construction of
new bridges and culverts.
Storm water from all longitudinal and cross drainage works will be connected to the
natural drainage courses.
Necessary measures will be undertaken during construction phase to prevent earth and
stone material from blocking cross drainage structures.
Periodic cleaning will be undertaken to cross drainage structures and road drainage
system to maintain uninterrupted storm water flow.
Obstructions that may cause temporary flooding of local drainage channels, during
construction phase will be removed.
Oil traps will be used to separate oil from runoff water
Sediment control measures in the form of silt traps and sedimentation tank will be
provided to treat surface run-off before disposal
6.1.4 Wildlife Management Plan
Scope
The proposed exploratory, testing of hydrocarbons in Ramanathpuram PML area may impart
potential impact on birds, as twelve wells Sakkarkottai bird sanctuaries within the Block area.
As the 6 exploratory wells out of 22 wells is located within the Eco-sensitive Zone of
Gulf of Mannar Marine National Park, 9 wells located within the ESZ of Sakkarakottai Bird
Sanctuary and one well located in ESZ of Therthangal Bird Sanctuary, Wildlife Management
Plan has been prepared to ensure minimum effects of oil & gas activities of Ramanathapurma
PML on wildlife and issue of No Objection Certificate (NOC) from the Standing Committee
of National Board of Wildlife.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 204 ONGC.
The likely impacts of the project activities on the ecological habitat have been addressed in
impact assessment chapter of this report and a Wildlife Management Plan is prepared to
safeguard sanctuary areas and their characteristic floral and faunal component.
Purpose
The purpose of Wildlife Management Plan is to minimize the impact on natural habitat (lakes
ecosystem) and control any adverse impact due to air and noise pollution from drilling and well
testing activities, discharge of untreated waste water from drilling operation, storm water runoff
from the well site and road widening/strengthening activities. The Management Plan details
out the mitigation measures and strategies to be adopted by ONGC and the Contractors during
each phase of the project, at the same time establishing a monitoring network to investigate the
effective implementation of the Management Plan.
Mitigation measures
Care should be taken during finalization of drilling sites and location should avoid the
ecologically sensitive areas like bird sanctuaries, coastal zone, Gulf of Mannar National
Park buffer zone. Permission from the State Wildlife Authority to be taken for proposed
drill sites as it is located within 10 km of Therthangal Bird Sanctuary and 10 km from
Sakkarkottai Bird Sanctuary. Permission also to be taken for well sites as they are
located within 10 km of the Gulf of Mannar National Park
The drill site will be properly fenced (chain-linked) to avoid straying of any outsider as
well as wildlife;
No temporary electric supply connection line from the grid will be laid for the proposed
project activity. All electric requirements will be supplied from the internal DG sets.
Noise Levels at the drill site will be controlled through selection of low noise generating
equipment and installation of sufficient engineering controls viz. mufflers, silencers etc.
Movement of heavy vehicles will be restricted at night time.
The borrow areas and quarries will be located away from ecologically sensitive areas.
Care would be taken while disposal drill cutting & other drilling waste and discharge
of waste water from the drilling site.
The following measures and strategies needs to be adopted to safeguard the natural habitat
from the possible impacts resulting from the project and its related activities. An
Environment Management Cell (EMC) will be developed for implementation of
environmental mitigation & management plan. The environment cell would look after the
following measures:
Any wild animal species if trapped during site development or operation of drilling
would be released into the suitable habitat;
Proper monitoring of indicator species will be carried out and compared to baseline to
understand any negative impacts;
The committee will review the mitigation measures and management plan
implementation.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 205 ONGC.
All sightings of sensitive species in and around the project site will be reported and
adequate steps will be taken with the help of forest personnel to reduce conflict between
such animals and project activities or people working at site.
6.1.5 Road Safety & Traffic Management Plan
Scope
The Road Safety & Traffic Management Plan is applicable to all operation pertaining to ONGC
and contractor vehicular movement viz. vehicle involved in the transportation of raw materia ls,
project and contractor personnel, drilling rig and heavy equipment transportation to well site
and decommissioning.
Purpose
The Road Safety & Traffic Management Plan outlines specific measures to be adopted and
implemented by ONGC to mitigate any potential impact on community health and safety that
may arise out of movement of vehicles and transportation of drilling rig and heavy equipments
during site preparation, drilling and decommissioning activities.
Mitigation Measures
Project vehicular movement involved in sourcing and transportation of borrow material
will be restricted to defined access routes to be identified in consultation with locals
and concerned authorities.
Proper signage will be displayed at important traffic junctions along the predefined
access routes to be used by construction and operational phase traffic. The signage will
serve to prevent any diversion from designated routes and ensure proper speed limits
are maintained near village residential areas.
The condition of roads and bridges identified for movement of vehicles and drilling rig
will be assessed by ONGC to ensure their safe movement.
Precautions will be taken to avoid damage to the public access routes includ ing
highways during vehicular movement.
Safe and convenient passage for vehicles, pedestrians and livestock to and from side
roads and property accesses connecting the project road will be provided. Work that
affects the use of side roads and existing accesses will not be undertaken without
providing adequate provisions.
Parking of project vehicles along village access roads prohibited. Signposted parking
facilities will be utilized for such purpose.
Any road diversions and closure will be informed in advance to the villagers who are
accessing the defined routes
Traffic flows will be scheduled wherever practicable during period of increased
commuter movement.
Personnel will be deployed at major traffic intersection for control of traffic
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 206 ONGC.
Clear signs, flagmen & signal will be set up at major traffic junctions and near sensitive
receptors viz. primary schools in discussion with Gram Panchayat and local villagers.
Movement of vehicles during night time will be restricted. Speed limits will be
maintained by vehicles involved in transportation of raw material and drilling rig.
Regular supervision will be done by contractor to control vehicular traffic movement
along defined traffic routes particularly near identified sensitive receptors
A Journey Management Plan will be formulated and implemented by the contractor to
control construction and operational phase traffic.
Routine maintenance of project vehicles will be ensured to prevent any abnormal
emissions and high noise generation.
Adequate training on traffic and road safety operations will be imparted to the drivers
of project vehicles. Road safety awareness programs will be organized in coordination
with concerned authorities to sensitize target groups viz. school children, commuters
on traffic safety rules and signage.
In addition, ONGC will ensure that all vehicles transporting hazardous substances (fuel oil,
chemicals, etc.) will be properly labeled in accordance with the specifications of the Motor
Vehicles Rules. The implementation of the Road Safety & Traffic Management Plan will be
monitored which will include keeping track of vehicular densities on the NH 49, NH 210,
Madurai-Rameshwaram Road and East Coast Road etc.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 207 ONGC.
6.1.6 Occupational Health & Safety Management Plan
Scope
The Occupation Health & Safety Management Plan (OHSMP) is applicable for all project
operations which have the potential to adversely affect the health and safety of contractors’
workers and onsite ONGC personnel.
Purpose
The Occupation Health & Safety Management Plan (OHSMP) has been formulated to address
the occupational health and safety related impacts that may arise from proposed project
activities viz. exploratory/development drilling and testing operation of construction
machinery/equipments, storage and handling of fuel and chemicals, operation of drilling rig
and associated equipment, during drilling and decommissioning/site closure.
Mitigation Measures
Contractor workers involved in the handling of construction materials viz. borrow
material, cement etc. will be provided with proper PPEs viz. safety boots, nose masks
etc.
No employee will be exposed to a noise level greater than 85 dB(A) for a duration of
more than 8 hours per day. Provision of ear plugs, ear muffs etc. and rotation of workers
operating near high noise generating areas.
Hazardous and risky areas, installations, materials, safety measures, emergency exits,
etc. shall be appropriately marked.
All chemicals and hazardous materials storage container will be properly labeled and
marked according to national and internationally recognized requirements and
standards. Materials Safety Data Sheets (MSDS) or equivalent data/information in an
easily understood language must be readily available to exposed workers and first -aid
personnel.
The workplace must be equipped with fire detectors, alarm systems and fire-fighting
equipments. Equipments shall be periodically inspected and maintained to keep good
working condition.
The sewage system for the camp must be properly designed, built and operated so that
no health hazard occurs.
Adequate sanitation facilities will be provided onsite for the operational workforce both
during construction and operational phase of the project.
Garbage bins will be provided in the camp and regularly emptied and the garbage
disposed off in a hygienic manner.
Training programs will be organized for the operational workforce regarding proper
usage of PPEs, handling and storage of fuels and chemicals etc.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 208 ONGC.
6.1.7 Management of Social Issues and Concerns
Mitigation measure have been outlined to address project related social issues and concerns in
order for ONGC to take proactive steps and adopt best practices, which are sensitive to the
socio-cultural setting of the region.
Providing Job Opportunities
During site construction non technical jobs will be generated. Most of the people employed
during this stage would be semi-skilled. People from adjoining areas especially given
preference through local contractors according to the skill sets possessed.
Ensuring Public Safety
Since the project involves the movement of heavy vehicles and machinery in the area, the issue
of public safety of the villagers, especially children, is an important concern. During the drilling
phase and for the rest of the project activities proper safety measures will be undertaken both
for transportation as well as the other operations. The drill site would be fenced and gates would
be constructed so that the children are refrained from straying into the site.
The movement of traffic is also likely to disrupt access conditions of the inhabitants residing
close to the approach road. The increase in traffic will have implications on their safety too, as
well as create congestion, potential delays and inconvenience for pedestrians. The mitiga t ive
measures in this regard have been discussed in detail under the Road Safety & Traffic
Management Plan.
Common Property Resources
During the project tenure there might be some sharing of resources viz. land, water, access
routes etc. by the villagers and the contractor workforce. Prior to the commencement of the
proposed activity, a consultation program will be conducted by ONGC with the target groups
and local authorities. The primary objective of such consultation will be to share with the
concerned villagers/stakeholders the objective of the proposed project associated impacts and
their mitigation. The movement of heavy vehicles and machinery might lead to conditions like
disruption of electric wires and telephone wires in the site area and along transportation routes.
These public utilities will be restored back to normal conditions, at the earliest.
Corporate Social Responsibility
ONGC has taken up various CSR initiatives in Ramanathapuram District. ONGC's operational
areas for the benefit of the educational institutes, village panchayats for various development
activities, hospitals, government departments like police, forest. Yearly expenditure done for
various CSR activities is mentioned below:
S.No. Year Expenditure (Rs.)
1 2014-2015 80,75,742
2 2013-2014 34,70,810
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 209 ONGC.
3 2012-2013 66,55,149
4 2011-2012 49,25,100
Following are the activites taken up in village Valantahravai. Yearwise expenditure is shown
in the following table:
S.No. Expenditure (Rs.)
1 Govt.High School 2.25 lakhs
2 President, Pannaikulam Grama Panchayat, Valantharavai,
1.00 lakhs
3 Panchayat President,
Valantharavai Panchayat, Valantharavai
4.00 lakhs
4 Valantharavai, Panchayat President
1.60 lakhs
6.2 EMP BUDGET
The tentative budget for implementation of the environmental management plans has been
provided below:
TABLE 6-1: TENTATIVE BUDGET FOR EMP IMPLEMENTATION
Sl. No Project head Name of the
work
Estimated Expenditure
/Budget
1 Environment Protection Waste pit
preparation and HDPE lining
Rs 6 lakhs per well
2 Environment Protection Restoration Rs 40 lakhs Per well
(Budgeted)
3 Environment protection Acoustic enclosure(Noise control for Gen
Set)
Rs 5 Lakhs per year
4 Environment Protection Garland Canal for drill sites
Rs 20 Lakhs per year
5 Environment
Monitoring
AAQM,SM,NM Rs6 lakhs per year
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 210 ONGC.
Table 6-2: Environmental Management Matrix
Sl. No Activity Potential Impact Mitigation
A. Pre-drilling Activities
B1 Siting of well site facility Potential adverse impact on environment in the vicinity of the drill
site
Potential safety issues to local people related to drill site
preparation and drilling operation
Selection of drill site taken into account of local environmental
vulnerability Sufficient distance maintained in between site and nearest habitation
B2 Procurement of land for well sites and related facilities
Loss of agricultural land and crop productivity
Loss of livelihood for affected communities
Providence of compensation for standing crops
Finalization of compensation package in consultation with revenue
authorities/collector
B3 Site preparation and road
strengthening/widening Loss of top soil and increase in soil erosion potential
Alternation in onsite drainage pattern
Minimal felling of trees and removal of vegetation through proper
and careful selection of site.
Site preparation and road strengthening/widening activities to be restricted within defined boundaries.
Avoidance of construction activities during monsoon season.
Top soil stockpiles to be stabilized and stored in designated areas
Provision of onsite drainage onsite.
B4 Sourcing and transportation of raw
materials Generation of fugitive emission
Community health and safety concerns
Contractor to source raw materials from approved/licensed quarries.
Proper covering of raw material during transportation to be ensured
Periodic water sprinkling along haulage routes near sensitive
receptors
Project vehicular movement be restricted to defined access routes to be identified in consultation with locals and concerned authorities.
Proper signage be displayed at important traffic junctions along the
predefined access routes.
Night time movement of vehicles to be restricted
B5 Operation of construction
machinery/equipments Fugitive emissions and high noise generation
Occupational health and safety concerns
Selection of low noise generating equipment
Installation of engineering controls viz. silencers, mufflers
Rotation of workers operating in high noise generating areas
Use of proper PPEs viz. ear plugs, ear muffs.
Periodic preventive maintenance of machinery/equipments
B6 Transportation of drilling rig and
ancillaries Disruption of public utilities
Community health and safety concerns
The public utilities viz. telephone and electrical wire to be restored
to its original condition at the earliest.
Movement of rig and heavy equipments to be carried out in
accordance with the Road Safety & Traffic Management Plan
formulated.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 211 ONGC.
Sl. No Activity Potential Impact Mitigation
B7 Discharge of surface run-off Increase in sediment load contributing to turbidity of receiving
water bodies Provision of onsite sediment control measures viz. silt traps,
sedimentation tank
Construction work close to the streams or water bodies be avoided during monsoon
Run-off discharges to natural drainage channels/water bodies made
to conform to CPCB Inland Water Discharge Standards.
B. Drilling and Testing
C1 Physical presence of drilling rig and
ancillaries
Temporary change in visual characteristics of the area Restoration of site to its original condition following decommissioning/site closure
C2 Operation of DG sets and machinery
and exploratory drilling Air emissions and high noise generation
Occupational health and safety concerns
Community discomfort
Siting of drilling rig and facilities away from sensitive receptors
Installing acoustic enclosures and muffler on engine exhaust of DG sets
Setting up effective noise barrier at the fence-line of the site;
Exhausts of engines on the drilling rig diesel generators be positioned at a sufficient height
Preventive maintenance of DG sets to be undertaken as per
manufacturer’s schedule.
C3 Casing & cementing of exploratory
well
Damage to subsurface aquifer
Use of low toxicity chemicals
Periodic monitoring of ground water quality be carried out for
village wells located outside the project boundary to assess the level of ground water contamination, if any
C4 Storage and disposal of drill cuttings,
mud and process wastewater
Soil and ground /surface water contamination
Use of water based mud as the drilling fluid.
Use of low toxicity chemicals for the preparation of drilling fluid.
Recycling of drilling mud to be ensured to the maximum extent
possible.
Use of HDPE lined pit for disposal of drill cuttings, process wastewater
Disposal of drill cuttings in accordance with CPCB and MoEF
guidelines on management of drilling wastes
C5 Discharge of surface run-off Soil and surface water contamination Run-off from vehicular wash and chemical storage areas be
channeled through closed drainage system provided with an oil-
water separator.
Drip trays be used during preventive maintenance of vehicles and
machinery.
Hazardous chemicals and fuel drum be stored with bund and lined
area equipped with proper spill control equipment.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 212 ONGC.
Sl. No Activity Potential Impact Mitigation
C6 Sewage treatment Occupational health problems of operational workforce Sewage be treated using a combination of septic and soak pits
The sewage treatment system (septic tank & soak pit) to be regularly
monitored for any possible overflows, leakages etc.
C7 Flaring during production testing and process upset
Air emission leading to discomfort to nearby communities Siting of flare stack considering nearest habitation and sensitive receptor.
Elevated flaring to be undertaken as per guidelines issued by CPCB
for Oil & Gas Extraction Industry.
Duration of flaring to be minimized by careful planning;
C. Decommissioning/Site Closure
D1 Dismantling of rig and associated
facilities
High noise generation and fugitive emissions causing discomfort to
locals Rotation of workers operating in high noise generating areas
Use of proper PPEs viz. ear plugs, ear muffs.
D2 Transportation of drilling rig and
ancillaries
Same as in B6 Same as in B6
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 213 ONGC.
6.3 ENVIRONMENTAL MONITORING PROGRAM
Monitoring is one of the most important components of a management system. Continuous
monitoring needs to be carried out for regulatory requirements, to monitor the environmenta l
quality and to determine performance of proposed mitigation measures. Monitoring indicators
have been developed for each of the activity considering the mitigation measures proposed.
Indicators have been developed for ascertaining the environmental quality and performance of
the EMP implementation through Environmental Quality Indicators (EQI’s) and
Environmental Performance Indicators (EPI’s) respectively which focus not only on
quantifying or indexing activity-environment interactions that may potentially impact the
environment but at the same time also help in comparing different components of
environmental quality against previously established baseline values. Monitoring results will
be to be documented, analyzed and reported internally to Head - HSE. Monitoring requirements
have been described in the following Table 6.3. Frequency of monitoring and responsibility of
carrying out the monitoring have also been presented in the table below.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 214 ONGC.
TABLE 6-3: PROPOSED MONITORING REQUIREMENTS OF THE PROJECT
A) Environmental Performance Monitoring
EPI
No.
Environmental
Performance Indicator
(EPI)
Monitoring Parameter Location Period &
Frequency Responsibility
A. Design & Planning
A.1 Proximity of sensitive
environmental habitat
Distance between the drill
site and sensitive
environmental habitat
Site Once in project
lifecycle
Civil supervisor
A.2 Proximity of nearest
habitation
Distance between the drill
site and nearest habitation
Site Once in project
lifecycle
Civil supervisor
A.3 Location and Size of
Land Leased
Number of land owners
affected
Total area leased for drill site (Ha)
Site Once in project
lifecycle
Civil Supervisor
A.4 Approval /
Authorization of
quarries
Validity of the Approval /
Authorization
Quarry Once in project
lifecycle
Civil Supervisor
A.5 Land use Land use Type Quarry/
Borrow
Area
Once in project
lifecycle
Civil Supervisor
A.6 Haul Routes Distance of quarry / borrow
area from project site
Condition of haul road
Quarry /
Borrow
Area
Once in project
lifecycle
Civil Supervisor
A.7 Undisrupted flow of
water in drainage
channels
Number of cross drainage
structures planned to number
of actual stream crossings
Site & Road Once in project
lifecycle
Civil Supervisor
B Approach Road & Site
Development
B.1 Local drainage pattern Number of Cross Drainage
structures constructed to
actual number of cross
drainage structures designed
Site & road Once in project
lifecycle
Civil Supervisor
B.2 Accident reporting
Number of casualties /
Number of fatalities
Site & Haul
Routes
During life
cycle of project
HSE Supervisor
B.3 Fugitive emission of
dust during material
handling and storage
Visual observation of dust in
air by haziness
Near
stockpiles
and storages
Daily during the
entire project
life-cycle
HSE Supervisor
C Drilling & Testing
C.1 Gaseous pollutant
emissions from DG Set
Pollutant concentrations in
gaseous emissions and
maintenance parameters (air,
fuel filters & air-fuel ratio) of
DG sets influencing air
emissions
Visual observation of exhaust
smoke characteristics
DG Stack Once during
drilling
operations
HSE Supervisor
through Drilling
contractor
C.2 Noise emission from
DG Sets
Noise pressure level in dB(A) Near noise
sources (5m)
Once during
drilling
operations
HSE Supervisor
through Drilling
contractor
C.3 Noise emission from rig
Noise pressure level in dB(A)
Number of cases of workers
not using PPE
On the rig
floor Near noise
sources (5m)
Once during
drilling operations
HSE Supervisor
through Drilling contractor
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 215 ONGC.
EPI
No.
Environmental
Performance Indicator
(EPI)
Monitoring Parameter Location Period &
Frequency Responsibility
Site
C.4 Accident reporting
Number of casualties /
Number of fatalities
Site
As and when
accident occurs
HSE Supervisor
through Drilling
contractor
C.5 Spilled Chemicals/Oil Area of Spill / Quantity
Spilled / Severity of Spill /
Characterization of Spilled
Substances for Contaminants
(Heavy Metals, Toxics, etc.)
Site As and when
spills occur
HSE Supervisor
through Drilling
contractor
C.6 Runoff from temporary
storage areas
Supervision of functioning of
conduits / drains, channels
Site As & When
required during
drilling phase
HSE Supervisor
C.7 Waste water quantity &
quality (Process water
viz. rig wash, formation
water etc)
Volume estimate
CPCB General discharge
parameters and Oil & Gas
Extraction Industry Standards
At discharge
point
Once during
drilling
HSE Supervisor
through Drilling
contractor
C.8 Storm water/wash down
water discharge
CPCB General discharge
parameters and Oil & Gas
Extraction Industry Standards
At discharge
point
Depending on
generation
particularly
during monsoon
HSE Supervisor
through Drilling
contractor
C.9 Drill cutting storage and
disposal
Total volume generated
Concentration of hazardous
constituents as per Hazardous
Waste Management and
Handling Rules
CPCB Onshore discharge
standards for Oil & Gas
Extraction Industry
At storage
location
Once during
drilling period
HSE Supervisor
through Drilling contractor
B) Environmental Quality Monitoring
EQI
No
Environmental
Quality Indicator
(EQI)
Monitoring Parameter Location Period &
Frequency Responsibility
A Approach Road &
Site Development
A1 Quality of water Analysis of Parameters as
per CPCB Use-class
Natural
drainage
channel
receiving run-
off discharges
Monthly during
site and road
works
HSE
Supervisor
A2 Ambient Air Quality Measurement of PM 10,
PM 2.5, NOx, SO2, CO, HC
using ambient air sampler
At Surrounding
receptor points
Monthly during
site and road
works
HSE
Supervisor
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 216 ONGC.
EQI
No
Environmental
Quality Indicator
(EQI)
Monitoring Parameter Location Period &
Frequency Responsibility
A3 Ambient noise quality Hearing / perception
Measurement of Noise
Pressure Level in dB(A)
At surrounding
receptor points
Monthly once in
site and road
works
Monthly site and
road works
HSE
Supervisor
B Drilling & Testing
B1 Ambient Air Quality Measurement of PM 10,
PM 2.5, NOx, SO2, CO, HC ,
using ambient air sampler
At Surrounding
receptor points
Once during
drilling
HSE
Supervisor
B2 Ambient noise quality Hearing / perception
Measurement of Noise
Pressure Level in dB(A)
At surrounding
receptor points
Once during
drilling
HSE
Supervisor
B3 Groundwater Quality Analysis of Parameters as
per IS:10500
Nearby wells Once during
drilling
HSE
Supervisor
B4 Soil Contamination Analysis for suite of
contaminants (heavy metals,
TPH, organics, pesticides).
Site, adjacent
areas and Waste
disposal site
Once during
drilling
HSE
Supervisor
B5
Quality of water Analysis of Parameters as
per CPCB Use-class
Natural
drainage
channel
receiving run-
off discharges
Once during
drilling
HSE
Supervisor
C Decommissioning /
Closure
C1 Ambient noise quality Hearing / perception
Measurement of Noise
Pressure Level in dB(A)
At surrounding
receptor points
Bi-Monthly
during
decommissioning
Monthly during
decommissioning
HSE
Supervisor
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 217 ONGC.
7 Public Consultation
“Public Consultation” refers to the process by which the concerns of local affected persons and
others who have plausible stake in the environmental impacts of the project or activity are
ascertained with a view to taking into account all the material concerns in the project or activity
design as appropriate. All Category ‘A’ projects are required to undertake Public Consultat ion
as per the EIA notification dated September 14, 2006.
The present project is a designated project under Schedule and falls under category A (Activity
1(b)-Any oil and gas exploration, development & production)).
The Public Consultation normally has two components comprising of:
a public hearing at the site or in its close proximity- district wise, to be carried out in
the manner prescribed in Appendix IV of EIA Notification, 2006, for ascertaining
concerns of local affected persons; (Reproduced in Appendix VI of EIA Report)
Obtain responses in writing from other concerned persons having a plausible stake in
the environmental aspects of the project or activity.
The public hearing at, or in close proximity to, the site(s) in all cases is conducted by the State
Pollution Control Board (SPCB) or the Union territory Pollution Control Committee (UTPCC)
concerned in the specified manner and forward the proceedings to the regulatory authority
concerned within 45(forty five ) of a request to the effect from the applicant.
In case the State Pollution Control Board or the Union territory Pollution Control Committee
concerned does not undertake and complete the public hearing within the specified period,
and/or does not convey the proceedings of the public hearing within the prescribed period
directly to the regulatory authority concerned as above, the regulatory authority will engage
another public agency or authority which is not subordinate to the regulatory authority, to
complete the process within a further period of forty five days.
If the public agency or authority nominated under the notification reports to the regulatory
authority concerned that owing to the local situation, it is not possible to conduct the public
hearing in a manner which will enable the views of the concerned local persons to be freely
expressed, it will report the facts in detail to the concerned regulatory authority, which may,
after due consideration of the report and other reliable information that it may have, decide that
the public consultation in the case need not include the public hearing.
For obtaining responses in writing from other concerned persons having a plausible stake in
the environmental aspects of the project or activity, the concerned regulatory authority and the
State Pollution Control Board (SPCB) or the Union Territory Pollution Control Committee
(UTPCC) shall invite responses from such concerned persons by placing on their website the
Summary EIA report prepared in the specified format, as given in Appendix IIIA of EIA
Notification, 2006 (Reproduced in Appendix VI of EIA Report), by the applicant along with
a copy of the application in the prescribed form , within seven days of the receipt of a written
request for arranging the public hearing . Confidential information includ ing non-disclosab le
or legally privileged information involving Intellectual Property Right, source specified in the
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 218 ONGC.
application shall not be placed on the web site. The regulatory authority concerned may also
use other appropriate media for ensuring wide publicity about the project or activity. The
regulatory authority shall, however, make available on a written request from any concerned
person the Draft EIA report for inspection at a notified place during normal office hours till the
date of the public hearing. All the responses received as part of this public consultation process
shall be forwarded to the applicant through the quickest available means.
After completion of the public consultation, the applicant will address all the material
environmental concerns expressed during this process, and make appropriate changes in the
draft EIA and EMP. The final EIA report, so prepared, shall be submitted by the applicant to
the concerned regulatory authority for appraisal. The applicant may alternatively submit a
supplementary report to draft EIA and EMP addressing all the concerns expressed during the
public consultation.
Public hearing was conducted by Tamil Nadu State Pollution Control Board at Audotorium,
District Collectorate, Ramanathapuram District 14th May, 2015. The queries rose by the public
and responses given by management of ONGC are given in the minutes of meeting. The
minutes of meeting and compliance report are given Annexure 6.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 219 ONGC.
8 Disclosure of Consultants
SENES Consultants India Private Limited
SENES Consultants India Private Limited (SENES India) is a professionally managed, fast
growing, wholly owned subsidiary of SENES Consultants Limited (SENES),Canada.
SENES specializes in the fields of energy, nuclear, environmental and social sciences with
offices spread across in Canada, United States, South America and India. SENES has been
operational in India for more than seven years having its head office in New Delhi with branch
offices in Kolkata, Hyderabad and Mumbai with all supporting infrastructure necessary for
project implementation.
SENES India was responsible for carrying out the EIA study of Ramanathapuram PML block
of Oil and Natural Gas Corporation (ONGC).
SENES has already obtained QCI Accreditation under the QCI-NABET Scheme for
Accreditation of EIA Consultant Organizations vide certificate no: NABET/EIA/RA016/040.
The QCI/NABET accreditation certification is provided in Annexure 8.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 220 ONGC.
ANNEXURES
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 221 ONGC.
ANNEXURE 1.1
Approved TOR by MOEF
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 222 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 223 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 224 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 225 ONGC.
Annexure-3.1
Ambient Air Quality Results – Premonsoon
AAQ1 Devipattnam
S.No Date PM 10 ( µg/m3) PM 2.5 ( µg/m3) SO2 ( µg/m3
) NO2 ( µg/m3
)
CO (mg/m3)
HC as
CH4
in
ppm
HC as
Non-
Methane
in ppm VOC (µg/m3)
I II III
1 30-07-2014 51 24 8 14
1.2 1.2 1.1 1.9 0.7
BDL
2 31-07-2014 50 25 9 15
1.2 1.1 1.2 2.0 0.2
BDL
3 05-08-2014 54
27 11 16
1.1 1.0 1.2 1.6 0.5
BDL
4 06-08-2014 47
23 12 14
1.0 1.1 1.1 1.4 0.4
BDL
5 11-08-2014 49
24 7 13
1.1 1.2 1.1 1.2 0.3
BDL
6 12-08-2014 51
24 10 14
1.2 1.2 1.2 1.6 0.6
BDL
7 17-08-2014 55
26 8 15
1.2 1.0 1.1 1.6 0.5
BDL
8 18-08-2014 49
24 9 13
1.2 1.1 1.2 1.8 0.8
BDL
9 23-08-2014 53
26 10 14
1.0 1.0 1.1 1.6 0.5
BDL
10 24-08-2014 57
27 11 16
1.1 1.0 1.2 1.9 0.6
BDL
Maximum 57.0 27.0 12.0 16.0 1.2 2.0 0.8
Minimum 47.0 23.0 7.0 13.0 1.0 1.2 0.2
Average 51.6 25.0 9.5 14.4 1.1 1.66 0.51
98 th Percentile 56.6 27.0 11.8 16.0 1.2 1.2 0.2
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 226 ONGC.
AAQ2 Panaikulam
S.No Date PM 10 ( µg/m3) PM 2.5 ( µg/m3) SO2 ( µg/m3) NO2 ( µg/m3)
CO (mg/m3)
I II III HC as CH4 in ppm HC as Non-Methane in ppm VOC ( µg/m3)
1 02-08-2014 44 25 8 13 1.0 1.2 1.1 1.7 0.6
2 03-08-2014 49 25 6 14
1.1 1.2 1.1 2.0 0.5
BDL
3 08-08-2014 51
26 7 13
1.1 1.0 1.2 2.1 0.3
BDL
4 09-08-2014 42
21 10 15
1.0 1.0 1.2 1.4 0.4
BDL
5 14-08-2014 46
22 11 13
1.2 1.2 1.1 1.3 0.3
BDL
6 15-08-2014 39
20 9 14
1.2 1.0 1.1 1.7 0.6
BDL
7 20-08-2014 52
25 8 14
1.2 1.2 1.1 1.8 0.5
BDL
8 21-08-2014 44
21 6 13
1.0 1.1 1.2 1.9 0.7
BDL
9 26-08-2014 53
26 7 14
1.0 1.1 1.2 1.5 0.5
BDL
10 27-08-2014 48
23 9 13
1.0 1.2 1.1 1.5 0.6
BDL
Maximum 53.0 26.0 11.0 15.0 1.2 2.1 0.7
Minimum 39.0 20.0 6.0 13.0 1.0 1.3 0.3
Average 46.8 23.4 8.1 13.6 1.1 1.69 0.5
98 th Percentile 52.8 26.0 10.8 14.8 1.2 1.3 0.3
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 227 ONGC.
AAQ3 Enmanamkondam
S.No Date PM 10 ( µg/m3) PM 2.5 ( µg/m3) SO2 ( µg/m3) NO2 ( µg/m3)
CO (mg/m3)
HC as CH4 in ppm
HC as Non-Methane in
ppm
VOC
( µg/m3) I II III
1 30-07-2014 55 27 6 10
1.0 1.0 1.2 2.2 0.5
BDL
2 31-07-2014 51 25 7 12
1.2 1.1 1.2 1.4 0.4
BDL
3 05-08-2014 48
23 9 13
1.0 1.0 1.2 1.3 0.3
BDL
4 06-08-2014 56
27 10 14
1.0 1.2 1.2 1.6 0.6
BDL
5 11-08-2014 45
22 8 11
1.0 1.2 1.0 1.7 0.7
BDL
6 12-08-2014 48
24 6 14
1.0 1.2 1.2 1.8 0.7
BDL
7 17-08-2014 53
26 8 12
1.2 1.1 1.0
1.6 0.5
BDL
8 18-08-2014 47
23 9 13
1.1 1.2 1.2
1.5 0.6
BDL
9 23-08-2014 49
25 10 13
1.0 1.0 1.1 1.2 0.1
BDL
10 24-08-2014 51 24 8 12 1.0 1.2 1.2 1.3 0.2
Maximum 56.0 27.0 10.0 14.0 1.2 2.2 0.7
Minimum 45.0 22.0 6.0 10.0 1.0 1.2 0.1
Average 50.3 24.6 8.1 12.4 1.1 1.56 0.46
98 th Percentile 55.8 27.0 10.0 14.0 1.2 1.2 0.1
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 228 ONGC.
AAQ4 Sattakonvalasai
S.No Date PM 10 ( µg/m3) PM 2.5 ( µg/m3) SO2 ( µg/m3) NO2 ( µg/m3)
CO (mg/m3)
I II III HC as CH4 in
ppm
HC as Non-
Methane in
ppm
VOC
( µg/m3)
1 02-08-2014
45 23 6 9 1.1 1.1 1.1 1.4 0.4
BDL
2 03-08-2014
48 23 7 11 1.2 1.0 1.2 1.3 0.3
BDL
3 08-08-2014
38 20 8 12 1.0 1.0 1.2 1.7 0.6
BDL
4 09-08-2014
40 21 9 13 1.1 1.2 1.1 1.8 0.5
BDL
5 14-08-2014
47 23 8 11 1.1 1.0 1.2 1.9 0.7
BDL
6 15-08-2014
39 19 7 10 1.2 1.2 1.1 1.7 0.7
BDL
7 20-08-2014
38 20 6 10 1.2 1.1 1.0 1.8 0.7
BDL
8 21-08-2014
45 22 9 11 1.0 1.1 1.2
1.6 0.5
BDL
9 26-08-2014
49 24 10 12 1.2 1.2 1.1
1.2 0.1
BDL
10 27-08-2014 49 23 8 10 1.1 1.0 1.0 1.9 0.7
Maximum 49.0 24.0 10.0 13.0 1.2 1.9 0.7
Minimum 38.0 19.0 6.0 9.0 1.0 1.2 0.1
Average 43.8 21.8 7.8 10.9 1.1 1.63 0.52
98 th Percentile 49.0 23.8 9.8 12.8 1.2 1.2 0.1
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 229 ONGC.
AAQ5 Regunathpuram
S.No Date PM 10 ( µg/m3) PM 2.5 ( µg/m3) SO2 ( µg/m3) NO2 ( µg/m3)
CO (mg/m3) HC as CH4 in ppm
HC as
Non-
Methane
in ppm VOC ( µg/m3)
I II III
1 04-08-2014
53 26 10 13 1.2 1.2 1.2 1.1 0.5
BDL
2 05-08-2014
55 27 8 12 1.0 1.1 1.0 1.4 0.6
BDL
3 10-08-2014
49 24 9 12 1.2 1.1 1.1 1.7 0.7
BDL
4 11-08-2014
45 22 7 10 1.2 1.1 1.0 1.9 0.8
BDL
5 16-08-2014
50 24 11 13 1.2 1.2 1.1 1.6 0.7
BDL
6 17-08-2014
47 23 10 12 1.0 1.1 1.1 1.7 0.8
BDL
7 22-08-2014
52 26 9 12 1.1 1.1 1.1 1.9 0.4
BDL
8 23-08-2014
46 23 8 11 1.0 1.2 1.2
1.5 0.6
BDL
9 28-08-2014
52 25 7 14 1.0 1.2 1.1
1.4 0.1
BDL
10 29-08-2014
48 23 10 13 1.1 1.0 1.2 1.8 0.6
BDL
Maximum 55.0 27.0 11.0 14.0 1.2 1.9 0.8
Minimum 45.0 22.0 7.0 10.0 1.0 1.1 0.1
Average 49.7 24.3 8.9 12.2 1.1 1.6 0.58
98 th Percentile 54.6 26.8 10.8 13.8 1.2 1.1 0.1
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 230 ONGC.
AAQ6 Periyapattinam
S.N
o Date
PM 10 (
µg/m3)
PM 2.5 (
µg/m3)
SO2 (
µg/m3)
NO2 (
µg/m3)
CO (mg/m3)
I II III HC as CH4 in
ppm
HC as Non-Methane in
ppm
VOC (
µg/m3)
1
01-08-
2014
44 22 6 9 1.0 1.1 1.0 1.8 0.5
BDL
2
02-08-
2014
48 23 7 10 1.2 1.0 1.2 1.9 0.7
BDL
3
07-08-
2014
51 25 8 11 1.2 1.0 1.2 1.7 0.7
BDL
4
08-08-
2014
49 24 9 12 1.1 1.1 1.0
2.1 0.8
BDL
5
13-08-
2014
53 27 10 13 1.1 1.2 1.2
1.2 0.1
BDL
6
14-08-
2014
42 22 11 14 1.1 1.2 1.1
1.6 0.4
BDL
7
19-08-
2014
47 24 8 12 1.0 1.1 1.1 1.6 0.3
BDL
8
20-08-
2014
47 25 9 14 1.2 1.1 1.0 1.5 0.6
BDL
9
25-08-
2014
41 20 10 13 1.0 1.1 1.2 1.8 0.9
BDL
10
26-08-
2014
50 24 11 15 1.0 1.2 1.1
2.0 0.1
BDL
Maximum 53.0 27.0 11.0 15.0 1.2 2.1 0.9
Minimum 41.0 20.0 6.0 9.0 1.0 1.2 0.1
Average 47.2 23.6 8.9 12.3 1.1 1.72 0.51
98 th Percentile 52.6 26.6 11.0 14.8 1.2 1.2 0.1
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 231 ONGC.
AAQ7 Tirupalani
S.N
o Date
PM 10 (
µg/m3)
PM 2.5 (
µg/m3)
SO2 (
µg/m3)
NO2 (
µg/m3)
CO (mg/m3)
I II III HC as CH4 in ppm
HC as Non-Methane
in ppm
VOC (
µg/m3)
1
04-08-
2014
41 20 9 13 1.0 1.0 1.1 1.7 0.7
BDL
2
05-08-
2014
38 19 10 12 1.2 1.0 1.1 1.9 0.8
BDL
3
10-08-
2014
36 18 11 13 1.1 1.0 1.0 1.6 0.7
BDL
4
11-08-
2014
40 20 12 14 1.0 1.1 1.0 1.7 0.8
BDL
5
16-08-
2014
37 19 8 13 1.1 1.1 1.0 1.1 0.7
BDL
6
17-08-
2014
43 22 11 16 1.2 1.0 1.1 1.5 0.2
BDL
7
22-08-
2014
35 18 10 13 1.1 1.0 1.0 1.2 0.1
BDL
8
23-08-
2014
38 19 12 13 1.0 1.1 1.0 1.6 0.2
BDL
9
28-08-
2014
42 21 13 16 1.0 1.0 1.1 1.7 0.3
BDL
10
29-08-
2014
37 18 11 13 1.0 1.1 1.1
1.1 0.1
BDL
Maximum 43.0 22.0 13.0 16.0 1.2 1.9 0.8
Minimum 35.0 18.0 8.0 12.0 1.0 1.1 0.1
Average 38.7 19.4 10.7 13.6 1.1 1.51 0.46
98 th Percentile 42.8 21.8 12.8 16.0 1.2 1.1 0.1
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 232 ONGC.
AAQ8 Ervadi
S.N
o Date
PM 10 (
µg/m3)
PM 2.5 (
µg/m3)
SO2 (
µg/m3)
NO2 (
µg/m3)
CO (mg/m3)
I II III
HC as CH4 in
ppm
HC as Non-Methane in
ppm
VOC
(
µg/m3)
1
01-08-
2014
43 22 9 13 1.
1
1.
2
1.
1 1.1 0.2
BDL
2
02-08-
2014
48 24 10 14 1.
1
1.
0
1.
0 2.2 0.2
BDL
3
07-08-
2014
50 25 11 13 1.
2
1.
0
1.
1 1.1 0.3
BDL
4
08-08-
2014
39 19 10 14 1.
2
1.
0
1.
1 1.2 0.4
BDL
5
13-08-
2014
44 21 12 14 1.
0
1.
1
1.
1 1.2 0.6
BDL
6
14-08-
2014
49 24 10 14 1.
0
1.
0
1.
2 1.9 0.9
BDL
7
19-08-
2014
41 21 9 13 1.
2
1.
1
1.
0 2.0 0.5
BDL
8
20-08-
2014
52 25 8 15 1.
0
1.
0
1.
2 1.8 0.1
BDL
9
25-08-
2014
47 23 10 13 1.
2
1.
1
1.
2 1.6 0.5
BDL
10
26-08-
2014
49 25 11 14 1.
0
1.
2
1.
0 1.2 0.6
BDL
Maximum 52.0 25.0 12.0 15.0 1.2 2.2 0.9
Minimum 39.0 19.0 8.0 13.0 1.0 1.1 0.1
Average 46.2 22.9 10.0 13.7 1.1 1.53 0.43
98 th Percentile 51.6 25.0 11.8 14.8 1.2 1.1 0.1
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 233 ONGC.
Annexure-3.1 (A)
Ambient Air Quality Results – Postmonsoon
Location : Devipattanam
Sr. No.
Date of Monitoring Week
Parameters
Sample Referance PM10
(μg/m 3) PM2.5
(μg/m 3) SO2
(μg/m 3) NOX
(μg/m 3)
CO (mg/m 3) HC (ppm) VOC
(μg/m 3) 0600 - 1400
1400 - 2200
2200 - 0600
Methane Non-
Methane
1 1/13/2016 I 43.8 13.9 7.6 13.9 1.71 1.45 1.71 3.80 <0.5 1.48 NIL/ABA/01/16/221
2 1/18/2016 I I
35.5 9.1 4.2 9.5 1.40 1.75 1.28 -- -- -- NIL/ABA/01/16/229
3 1/22/2016 33.7 8.7 5.0 7.0 1.56 1.42 2.09 -- -- -- NIL/ABA/01/16/237
4 1/25/2016 I I I
49.9 16.1 9.5 17.8 1.97 1.61 1.97 -- -- -- NIL/ABA/01/16/245
5 1/28/2016 39.9 11.7 7.2 8.9 2.05 1.57 1.54 -- -- -- NIL/ABA/02/16/005
6 2/3/2016 IV
49.5 16.1 10.3 15.0 2.09 1.81 1.92 -- -- -- NIL/ABA/02/16/108
7 2/4/2016 48.6 12.2 5.5 13.5 1.85 1.61 2.10 -- -- -- NIL/ABA/02/16/110
8 2/10/2016 V
51.2 13.0 6.3 12.8 1.28 1.75 1.30 -- -- -- NIL/ABA/02/16/209
9 2/13/2016 47.7 9.5 6.0 8.0 2.14 1.71 2.14 -- -- -- NIL/ABA/02/16/252
10 2/17/2016 VI 39.4 9.5 5.8 9.2 1.95 1.26 1.57 -- -- -- NIL/ABA/02/16/261
CPCB Limits 100 60 80 80 2 -- --
Minimum 33.7 8.7 4.2 7.0 1.26 -- --
Maximum 51.2 16.1 10.3 17.8 2.14 -- --
Average 43.92 11.98 6.74 11.56 1.72 -- --
98th Percentile 50.97 16.10 10.16 17.30 2.14 -- --
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 234 ONGC.
Location : Panaikkulam
Sr.
No. Date of Monitoring Week
Parameters Sample
Referance PM10
(μg/m 3) PM2.5
(μg/m 3) SO2
(μg/m 3) NOX
(μg/m 3)
CO (mg/m 3) HC (ppm) VOC
(μg/m 3) 0600 -
1400
1400 -
2200
2200 -
0600 Methane
Non-
Methane
1 1/13/2016 I 40.4 8.2 4.7 8.9 1.67 1.62 1.66 6.97 <0.5 0.639 NIL/ABA/01/16/222
2 1/18/2016 I I
43.2 9.1 4.6 7.1 1.32 1.93 1.98 -- -- -- NIL/ABA/01/16/230
3 1/22/2016 48.9 14.3 6.6 13.9 1.30 1.41 1.56 -- -- -- NIL/ABA/01/16/238
4 1/25/2016 I I I
44.8 14.8 8.5 12.3 1.55 1.72 1.39 -- -- -- NIL/ABA/01/16/246
5 1/29/2016 47.3 11.7 5.6 11.5 1.29 1.57 1.28 -- -- -- NIL/ABA/02/16/006
6 2/1/2016 IV
44.8 13.0 6.3 11.4 1.59 1.25 1.29 -- -- -- NIL/ABA/02/16/109
7 2/5/2016 50.5 13.0 7.3 12.4 2.02 1.56 1.76 -- -- -- NIL/ABA/02/16/111
8 2/8/2016 V
43.2 10.9 7.1 10.2 1.50 1.65 1.36 -- -- -- NIL/ABA/02/16/208
9 2/12/2016 32.3 9.1 4.2 8.0 2.00 1.99 1.31 -- -- -- NIL/ABA/02/16/253
10 2/15/2016 VI 39.2 12.6 6.9 9.5 1.37 1.64 1.49 -- -- -- NIL/ABA/02/16/260
CPCB Limits 100 60 80 80 2 -- --
Minimum 32.3 8.2 4.2 7.1 1.25 -- --
Maximum 50.5 14.8 8.5 13.9 2.02 -- --
Average 43.46 11.67 6.18 10.52 1.57 -- --
98th Percentile 50.21 14.71 8.28 13.63 2.01 -- --
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 235 ONGC.
Location : Enmanamkondan
Sr. No.
Date of Monitoring Week
Parameters
Sample Referance PM10
(μg/m 3) PM2.5
(μg/m 3) SO2
(μg/m 3) NOX
(μg/m 3)
CO (mg/m 3) HC (ppm) VOC
(μg/m 3) 0600 - 1400
1400 - 2200
2200 - 0600
Methane Non-
Methane
1 1/13/2016 I 42.6 12.2 6.4 10.6 1.84 1.84 1.85 3.72 <0.5 <0.5 NIL/ABA/01/16/223
2 1/18/2016 I I
36.6 11.3 6.3 11.1 2.02 1.58 1.67 -- -- -- NIL/ABA/01/16/231
3 1/22/2016 34.5 7.4 4.5 7.1 1.64 1.97 1.89 -- -- -- NIL/ABA/01/16/239
4 1/25/2016 I I I
32.4 7.4 4.0 7.3 1.44 1.64 2.15 -- -- -- NIL/ABA/01/16/247
5 1/28/2016 38.8 10.9 6.4 10.5 1.64 2.30 2.29 -- -- -- NIL/ABA/02/16/007
6 2/4/2016 IV
32.8 7.4 4.2 7.9 2.10 1.49 1.50 -- -- -- NIL/ABA/02/16/112
7 2/6/2016 32.8 8.7 5.0 9.4 2.06 2.28 1.78 -- -- -- NIL/ABA/02/16/116
8 2/9/2016 V
53.3 10.9 5.6 9.3 1.84 2.23 1.68 -- -- -- NIL/ABA/02/16/206
9 2/12/2016 32.8 8.7 4.6 9.9 2.28 1.40 1.92 -- -- -- NIL/ABA/02/16/213
10 2/16/2016 VI 43.9 15.2 9.4 12.4 2.04 1.90 1.39 -- -- -- NIL/ABA/02/16/258
CPCB Limits 100 60 80 80 2 -- --
Minimum 32.4 7.4 4.0 7.1 1.39 -- --
Maximum 53.3 15.2 9.4 12.4 2.30 -- --
Average 38.05 10.01 5.64 9.55 1.86 -- --
98th Percentile 51.61 14.66 8.86 12.17 2.29 -- --
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 236 ONGC.
Location : Sattakonvalasai
Sr. No.
Date of Monitoring Week
Parameters
Sample Referance PM10
(μg/m 3) PM2.5
(μg/m 3) SO2
(μg/m 3) NOX
(μg/m 3)
CO (mg/m 3) HC (ppm) VOC
(μg/m 3) 0600 - 1400
1400 - 2200
2200 - 0600
Methane Non-
Methane
1 1/16/2016 I 37.6 7.8 3.9 6.0 1.65 1.45 1.50 2.83 <0.5 <0.5 NIL/ABA/01/16/227
2 1/20/2016 I I
32.7 7.4 4.6 5.6 2.01 1.55 1.28 -- -- -- NIL/ABA/01/16/235
3 1/24/2016 30.1 8.2 5.3 6.5 1.29 1.52 1.14 -- -- -- NIL/ABA/01/16/243
4 1/27/2016 I I I
42.5 10.0 4.5 10.8 2.06 1.46 1.52 -- -- -- NIL/ABA/01/16/251
5 1/31/2016 28.6 8.2 4.5 7.7 1.67 1.38 1.86 -- -- -- NIL/ABA/02/16/011
6 2/3/2016 IV
42.5 11.3 7.3 10.0 1.40 1.46 1.29 -- -- -- NIL/ABA/02/16/014
7 2/7/2016 44.4 13.0 7.9 10.4 1.83 1.77 1.25 -- -- -- NIL/ABA/02/16/207
8 2/10/2016 V
34.6 7.8 4.9 8.3 1.96 1.77 1.29 -- -- -- NIL/ABA/02/16/214
9 2/14/2016 31.2 6.9 3.3 7.2 1.95 1.38 1.55 -- -- -- NIL/ABA/02/16/259
10 2/17/2016 VI 46.6 13.5 7.2 14.5 1.55 1.26 1.46 -- -- --
CPCB Limits 100 60 80 80 2 -- --
Minimum 28.6 6.9 3.3 5.6 1.14 -- --
Maximum 46.6 13.5 7.9 14.5 2.06 -- --
Average 37.08 9.41 5.34 8.70 1.55 -- --
98th Percentile 46.20 13.41 7.79 13.83 2.03 -- --
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 237 ONGC.
Location : Periyapattanam
Sr. No.
Date of Monitoring Week
Parameters Sample
Referance PM10
(μg/m 3) PM2.5
(μg/m 3) SO2
(μg/m 3) NOX
(μg/m 3)
CO (mg/m 3) HC (ppm) VOC
(μg/m 3) 0600 - 1400
1400 - 2200
2200 - 0600
Methane Non-
Methane
1 1/16/2016 I 43.2 14.3 8.8 13.1 1.16 1.07 1.10 4.32 <0.5 1.26 NIL/ABA/01/16/228
2 1/29/2016 I I
46.7 12.2 5.5 12.5 1.40 0.93 1.11 -- -- -- NIL/ABA/01/16/233
3 2/2/2016 43.6 11.7 6.0 10.4 1.11 1.13 0.85 -- -- -- NIL/ABA/01/16/241
4 2/5/2016 I I I
35.4 7.4 4.0 7.0 1.14 1.27 1.06 -- -- -- NIL/ABA/01/16/249
5 2/8/2016 51.0 13.0 6.2 12.9 0.95 0.91 1.30 -- -- -- NIL/ABA/02/16/009
6 2/11/2016 IV
47.1 16.1 10.0 18.2 1.22 1.06 1.02 -- -- -- NIL/ABA/02/16/106
7 2/15/2016 38.0 8.2 5.1 8.2 1.45 0.98 1.07 -- -- -- NIL/ABA/02/16/114
8 2/18/2016 V
45.4 13.0 7.0 13.3 0.90 1.20 1.03 -- -- -- NIL/ABA/02/16/203
9 1/19/2016 44.1 14.3 8.3 11.2 1.32 1.02 1.19 -- -- -- NIL/ABA/02/16/211
10 1/23/2016 VI
34.1 10.9 5.8 10.4 1.04 1.21 1.30 -- -- -- NIL/ABA/02/16/255
11 1/26/2016 48.6 12.2 6.8 13.8 1.39 1.71 0.68 -- -- -- NIL/ABA/02/16/264
CPCB Limits 100 60 80 80 2 -- --
Minimum 34.1 7.4 4.0 7.0 0.68 -- --
Maximum 51.0 16.1 10.0 18.2 1.71 -- --
Average 43.38 12.12 6.68 11.91 1.13 -- --
98th Percentile 50.52 15.74 9.76 17.32 1.54 -- --
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 238 ONGC.
Location : Tirupalani
Sr. No.
Date of Monitoring Week
Parameters
Sample Referance PM10
(μg/m 3) PM2.5
(μg/m 3) SO2
(μg/m 3) NOX
(μg/m 3)
CO (mg/m 3) HC (ppm) VOC
(μg/m 3) 0600 - 1400
1400 - 2200
2200 - 0600
Methane Non-
Methane
1 1/14/2016 I 44.8 12.2 6.6 12.6 1.24 1.30 0.96 5.82 <0.5 2.70 NIL/ABA/01/16/225
2 1/19/2016 I I
44.4 15.2 9.6 14.0 1.34 1.48 0.97 -- -- -- NIL/ABA/01/16/234
3 1/23/2016 54.7 16.1 8.1 15.2 1.33 0.98 1.13 -- -- -- NIL/ABA/01/16/242
4 1/26/2016 I I I
45.2 13.9 6.4 14.9 1.00 1.31 0.81 -- -- -- NIL/ABA/01/16/250
5 1/30/2016 47.9 13.0 7.7 9.8 1.33 1.43 0.85 -- -- -- NIL/ABA/02/16/012
6 2/1/2016 IV
49.7 12.6 6.0 10.0 1.54 1.00 0.86 -- -- -- NIL/ABA/02/16/014
7 2/6/2016 49.3 12.6 5.9 12.4 1.41 1.35 0.73 -- -- -- NIL/ABA/02/16/116
8 2/9/2016 V
36.7 8.7 4.2 8.7 0.98 1.21 0.91 -- -- -- NIL/ABA/02/16/205
9 2/12/2016 36.7 9.1 4.2 7.4 1.08 1.30 1.00 -- -- -- NIL/ABA/02/16/215
10 2/16/2016 VI
49.7 16.1 7.7 14.9 1.51 1.05 0.98 -- -- -- NIL/ABA/02/16/257
11 2/19/2016 53.4 11.7 7.2 16.3 1.80 1.11 1.27 -- -- -- NIL/ABA/02/16/265
CPCB Limits 100 60 80 80 2 -- --
Minimum 36.7 8.7 4.2 7.4 0.73 -- --
Maximum 54.7 16.1 9.6 16.3 1.80 -- --
Average 46.59 12.84 6.69 12.38 1.17 -- --
98th Percentile 54.44 16.10 9.30 16.08 1.63 -- --
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 239 ONGC.
Location : Raghunathapuram
Sr. No.
Date of Monitoring Week
Parameters
Sample Referance PM10
(μg/m 3) PM2.5
(μg/m 3) SO2
(μg/m 3) NOX
(μg/m 3)
CO (mg/m 3) HC (ppm) VOC
(μg/m 3) 0600 - 1400
1400 - 2200
2200 - 0600
Methane Non-
Methane
1 1/14/2016 I 48.1 16.5 10.0 16.6 2.10 2.63 1.23 3.11 <0.5 <0.5 NIL/ABA/01/16/224
2 1/19/2016 I I
55.8 14.8 8.2 13.0 1.66 2.10 1.09 -- -- -- NIL/ABA/01/16/232
3 1/23/2016 51.0 10.4 5.3 10.5 2.18 2.24 1.27 -- -- -- NIL/ABA/01/16/240
4 1/26/2016 I I I
41.8 12.2 6.9 10.4 1.85 2.08 1.23 -- -- -- NIL/ABA/01/16/248
5 1/29/2016 42.3 11.7 5.9 12.5 2.04 2.03 1.27 -- -- -- NIL/ABA/02/16/008
6 2/2/2016 IV
45.2 13.9 7.8 14.6 2.25 2.45 0.98 -- -- -- NIL/ABA/02/16/105
7 2/5/2016 45.2 14.8 7.6 16.5 2.35 2.05 1.50 -- -- -- NIL/ABA/02/16/113
8 2/8/2016 V
47.6 9.5 5.0 8.9 1.68 2.29 1.12 -- -- -- NIL/ABA/02/16/202
9 2/11/2016 36.1 8.7 5.5 9.8 1.74 2.13 1.25 -- -- -- NIL/ABA/02/16/210
10 2/15/2016 VI
43.8 12.2 6.4 10.9 2.25 3.10 1.48 -- -- -- NIL/ABA/02/16/256
11 2/18/2016 51.9 14.8 8.4 14.1 2.60 3.05 0.95 -- -- -- NIL/ABA/02/16/263
CPCB Limits 100 60 80 80 2 -- --
Minimum 36.1 8.7 5.0 8.9 0.95 -- --
Maximum 55.8 16.5 10.0 16.6 3.10 -- --
Average 46.25 12.68 7.00 12.53 1.89 -- --
98th Percentile 55.02 16.16 9.68 16.58 3.07 -- --
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 240 ONGC.
Location : Ervadi
Sr. No.
Date of Monitoring Week
Parameters
Sample Referance PM10
(μg/m 3) PM2.5
(μg/m 3) SO2
(μg/m 3) NOX
(μg/m 3)
CO (mg/m 3) HC (ppm) VOC
(μg/m 3) 0600 - 1400
1400 - 2200
2200 - 0600
Methane Non-
Methane
1 1/14/2016 I 45.3 10.9 5.4 10.3 2.30 2.19 1.62 4.93 <0.5 <0.5 NIL/ABA/01/16/226
2 1/20/2016 I I
38.1 9.1 4.6 7.7 2.35 1.71 1.75 -- -- -- NIL/ABA/01/16/236
3 1/24/2016 56.6 18.7 9.8 16.9 2.05 1.99 1.49 -- -- -- NIL/ABA/01/16/244
4 1/27/2016 I I I
35.8 7.4 4.7 5.7 2.14 1.69 1.56 -- -- -- NIL/ABA/01/16/252
5 1/29/2016 48.5 13.0 7.9 9.9 2.32 2.43 1.25 -- -- -- NIL/ABA/02/16/010
6 2/2/2016 IV
53.0 16.5 8.7 18.8 1.91 2.56 1.90 -- -- -- NIL/ABA/02/16/107
7 2/5/2016 35.3 10.4 6.5 9.4 2.53 2.41 1.90 -- -- -- NIL/ABA/02/16/115
8 2/8/2016 V
47.6 10.0 4.7 10.3 1.75 2.39 1.39 -- -- -- NIL/ABA/02/16/204
9 2/11/2016 48.5 10.9 6.6 12.0 2.83 2.74 1.28 -- -- -- NIL/ABA/02/16/212
10 2/15/2016 VI
52.1 13.0 8.0 10.8 2.42 2.61 1.28 -- -- -- NIL/ABA/02/16/254
11 2/18/2016 54.4 11.3 6.9 12.2 1.58 1.96 1.48 -- -- -- NIL/ABA/02/16/262
CPCB Limits 100 60 80 80 2 -- --
Minimum 35.3 7.4 4.6 5.7 1.25 -- --
Maximum 56.6 18.7 9.8 18.8 2.83 -- --
Average 46.84 11.93 6.71 11.27 1.99 -- --
98th Percentile 56.16 18.26 9.58 18.42 2.77 -- --
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 241 ONGC.
Annexure-3.2
Ambient Noise Quality Results
Location Name & Code: PANAIKULAM & N1
S.No. Date of
monitoring
Time of
monitoring
I II III IV
1 02-08-2014 06:00AM 50 48 47 45
2 02-08-2014 07:00AM 48 46 44 42
3 02-08-2014 08:00AM 45 42 43 48
4 01-08-2014 09:00AM 49 48 46 50
5 01-08-2014 10:00AM 48 46 49 52
6 01-08-2014 11:00AM 46 45 48 51
7 01-08-2014 12:00PM 51 48 49 53
8 01-08-2014 01:00PM 49 48 46 50
9 01-08-2014 02:00PM 48 46 49 52
10 01-08-2014 03:00PM 46 45 48 51
11 01-08-2014 04:00PM 46 45 48 51
12 01-08-2014 05:00PM 45 42 43 48
13 01-08-2014 06:00PM 49 48 46 50
14 01-08-2014 07:00PM 48 46 49 52
15 01-08-2014 08:00PM 46 45 48 51
16 01-08-2014 09:00PM 45 44 43 46
17 01-08-2014 10:00PM 45 42 43 48
18 01-08-2014 11:00PM 49 48 46 50
19 02-08-2014 12:00AM 48 46 49 52
20 02-08-2014 01:00AM 46 45 48 51
21 02-08-2014 02:00AM 49 48 46 50
22 02-08-2014 03:00AM 48 46 49 52
23 02-08-2014 04:00AM 46 45 48 51
24 02-08-2014 05:00AM 46 45 48 51
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 242 ONGC.
Location Name & Code: ENMANAMKONDAM & N2
S.No. Date of
monitoring
Time of
monitoring
I II III IV
1 03-08-2014 06:00AM 51 48 49 53
2 03-08-2014 07:00AM 49 48 46 50
3 03-08-2014 08:00AM 48 46 49 52
4 02-08-2014 09:00AM 46 45 48 51
5 02-08-2014 10:00AM 46 45 48 51
6 02-08-2014 11:00AM 45 42 43 48
7 02-08-2014 12:00PM 49 48 46 50
8 02-08-2014 01:00PM 48 46 44 42
9 02-08-2014 02:00PM 45 42 43 48
10 02-08-2014 03:00PM 45 48 46 49
11 02-08-2014 04:00PM 48 46 49 52
12 02-08-2014 05:00PM 46 45 48 51
13 02-08-2014 06:00PM 49 48 46 50
14 02-08-2014 07:00PM 48 46 49 52
15 02-08-2014 08:00PM 46 45 48 51
16 02-08-2014 09:00PM 45 44 43 46
17 02-08-2014 10:00PM 48 46 49 52
18 02-08-2014 11:00PM 46 45 48 51
19 03-08-2014 12:00AM 49 48 46 50
20 03-08-2014 01:00AM 48 46 49 52
21 03-08-2014 02:00AM 46 45 48 51
22 03-08-2014 03:00AM 44 43 42 45
23 03-08-2014 04:00AM 42 44 46 48
24 03-08-2014 05:00AM 40 42 44 46
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 243 ONGC.
Location Name & Code: SATTAKONVALASAI & N3
S.No. Date of
monitoring
Time of
monitoring
I II III IV
1 05-08-2014 06:00AM 45 42 43 48
2 05-08-2014 07:00AM 49 48 46 50
3 05-08-2014 08:00AM 48 46 44 42
4 04-08-2014 09:00AM 45 42 43 48
5 04-08-2014 10:00AM 45 48 46 49
6 04-08-2014 11:00AM 48 46 49 52
7 04-08-2014 12:00PM 48 46 44 42
8 04-08-2014 01:00PM 45 42 43 48
9 04-08-2014 02:00PM 49 48 46 50
10 04-08-2014 03:00PM 48 46 49 52
11 04-08-2014 04:00PM 46 45 48 51
12 04-08-2014 05:00PM 46 45 48 51
13 04-08-2014 06:00PM 44 45 46 47
14 04-08-2014 07:00PM 49 48 46 50
15 04-08-2014 08:00PM 48 46 49 52
16 04-08-2014 09:00PM 46 45 48 51
17 04-08-2014 10:00PM 44 43 42 45
18 04-08-2014 11:00PM 42 40 45 43
19 05-08-2014 12:00AM 40 41 42 44
20 05-08-2014 01:00AM 46 45 48 51
21 05-08-2014 02:00AM 44 43 42 45
22 05-08-2014 03:00AM 42 44 46 48
23 05-08-2014 04:00AM 46 48 47 49
24 05-08-2014 05:00AM 42 45 48 50
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 244 ONGC.
Location Name & Code: REGUNATHAPURAM & N4
S.No. Date of
monitoring
Time of
monitoring
I II III IV
1 07-08-2014 06:00AM 55 57 59 60
2 07-08-2014 07:00AM 51 52 55 58
3 07-08-2014 08:00AM 57 56 54 59
4 06-08-2014 09:00AM 60 61 55 59
5 06-08-2014 10:00AM 54 55 58 60
6 06-08-2014 11:00AM 55 58 60 61
7 06-08-2014 12:00PM 49 48 46 50
8 06-08-2014 01:00PM 48 46 49 52
9 06-08-2014 02:00PM 46 45 48 51
10 06-08-2014 03:00PM 46 45 48 51
11 06-08-2014 04:00PM 44 45 46 47
12 06-08-2014 05:00PM 58 56 59 60
13 06-08-2014 06:00PM 55 52 49 58
14 06-08-2014 07:00PM 52 54 55 54
15 06-08-2014 08:00PM 48 46 49 52
16 06-08-2014 09:00PM 46 45 48 51
17 06-08-2014 10:00PM 44 43 42 45
18 06-08-2014 11:00PM 42 40 45 43
19 07-08-2014 12:00AM 40 41 42 44
20 07-08-2014 01:00AM 46 45 48 51
21 07-08-2014 02:00AM 44 43 42 45
22 07-08-2014 03:00AM 42 40 45 43
23 07-08-2014 04:00AM 40 41 42 44
24 07-08-2014 05:00AM 43 44 47 48
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 245 ONGC.
Location Name & Code: PERIYAPATTINAM & N5
S.No. Date of
monitoring
Time of
monitoring
I II III IV
1 08-08-2014 06:00AM 48 46 49 52
2 08-08-2014 07:00AM 46 45 48 51
3 08-08-2014 08:00AM 46 45 48 51
4 07-08-2014 09:00AM 45 42 43 48
5 07-08-2014 10:00AM 49 48 46 50
6 07-08-2014 11:00AM 51 48 49 53
7 07-08-2014 12:00PM 49 48 46 50
8 07-08-2014 01:00PM 48 46 49 52
9 07-08-2014 02:00PM 46 45 48 51
10 07-08-2014 03:00PM 46 45 48 51
11 07-08-2014 04:00PM 45 42 43 48
12 07-08-2014 05:00PM 49 48 46 50
13 07-08-2014 06:00PM 48 46 49 52
14 07-08-2014 07:00PM 46 45 48 51
15 07-08-2014 08:00PM 46 45 48 51
16 07-08-2014 09:00PM 44 45 46 47
17 07-08-2014 10:00PM 49 48 46 50
18 07-08-2014 11:00PM 48 46 49 52
19 08-08-2014 12:00AM 46 45 48 51
20 08-08-2014 01:00AM 44 43 42 45
21 08-08-2014 02:00AM 42 40 45 43
22 08-08-2014 03:00AM 48 46 49 52
23 08-08-2014 04:00AM 46 45 48 51
24 08-08-2014 05:00AM 46 45 48 51
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 246 ONGC.
Location Name & Code: TIRUPALANI & N6
S.No. Date of
monitoring
Time of
monitoring
I II III IV
1 09-08-2014 06:00AM 60 61 55 59
2 09-08-2014 07:00AM 54 55 58 59
3 09-08-2014 08:00AM 55 56 62 58
4 08-08-2014 09:00AM 54 60 56 58
5 08-08-2014 10:00AM 58 61 61 59
6 08-08-2014 11:00AM 52 59 58 55
7 08-08-2014 12:00PM 58 58 59 57
8 08-08-2014 01:00PM 54 54 55 57
9 08-08-2014 02:00PM 53 56 52 53
10 08-08-2014 03:00PM 56 57 53 56
11 08-08-2014 04:00PM 55 53 59 53
12 08-08-2014 05:00PM 52 53 50 52
13 08-08-2014 06:00PM 55 52 52.6 52.9
14 08-08-2014 07:00PM 53 56 58 56
15 08-08-2014 08:00PM 56 53 57 57
16 08-08-2014 09:00PM 58 59 58 57
17 08-08-2014 10:00PM 59 54 59 57
18 08-08-2014 11:00PM 54 56 58 53
19 09-08-2014 12:00AM 58 60 54 56
20 09-08-2014 01:00AM 56 53 59 53
21 09-08-2014 02:00AM 53 52 59 52
22 09-08-2014 03:00AM 56 57 52 52
23 09-08-2014 04:00AM 54 56 58 56
24 09-08-2014 05:00AM 56 53 57 57
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 247 ONGC.
Location Name & Code: ERVADI & N7
S.No. Date of
monitoring
Time of
monitoring
I II III IV
1 12-08-2014 06:00AM 57 59 58 56
2 12-08-2014 07:00AM 59 60 58 59
3 12-08-2014 08:00AM 57 56 54 56
4 11-08-2014 09:00AM 59 58 55 58
5 11-08-2014 10:00AM 59 57 56 54
6 11-08-2014 11:00AM 54 54 55 57
7 11-08-2014 12:00PM 53 56 52 53
8 11-08-2014 01:00PM 56 57 53 56
9 11-08-2014 02:00PM 55 53 59 53
10 11-08-2014 03:00PM 52 53 50 52
11 11-08-2014 04:00PM 55 52 50 52
12 11-08-2014 05:00PM 52 55 56 50
13 11-08-2014 06:00PM 51 54 52 56
14 11-08-2014 07:00PM 55 59 57 54
15 11-08-2014 08:00PM 58 56 54 57
16 11-08-2014 09:00PM 52 54 52 57
17 11-08-2014 10:00PM 59 62 62 58
18 11-08-2014 11:00PM 58 61 58 56
19 12-08-2014 12:00AM 59 54 59 57
20 12-08-2014 01:00AM 54 56 58 53
21 12-08-2014 02:00AM 58 60 54 56
22 12-08-2014 03:00AM 56 53 59 53
23 12-08-2014 04:00AM 53 52 59 52
24 12-08-2014 05:00AM 52 54 52 57
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 248 ONGC.
Location Name & Code: TANICHATTANMADAL & N8
S.No. Date of
monitoring
Time of
monitoring
I II III IV
1 10-08-2014 06:00AM 45 42 43 48
2 10-08-2014 07:00AM 49 48 46 50
3 10-08-2014 08:00AM 48 46 49 52
4 09-08-2014 09:00AM 46 45 48 51
5 09-08-2014 10:00AM 51 48 49 53
6 09-08-2014 11:00AM 48 46 49 52
7 09-08-2014 12:00PM 46 45 48 51
8 09-08-2014 01:00PM 49 48 46 50
9 09-08-2014 02:00PM 48 46 49 52
10 09-08-2014 03:00PM 46 45 48 51
11 09-08-2014 04:00PM 45 44 43 46
12 09-08-2014 05:00PM 48 46 49 52
13 09-08-2014 06:00PM 46 45 48 51
14 09-08-2014 07:00PM 46 45 48 51
15 09-08-2014 08:00PM 44 45 46 47
16 09-08-2014 09:00PM 49 48 46 50
17 09-08-2014 10:00PM 48 46 49 52
18 09-08-2014 11:00PM 46 45 48 51
19 10-08-2014 12:00AM 44 43 42 45
20 10-08-2014 01:00AM 42 40 45 43
21 10-08-2014 02:00AM 44 43 42 45
22 10-08-2014 03:00AM 42 40 45 43
23 10-08-2014 04:00AM 46 45 48 51
24 10-08-2014 05:00AM 46 45 48 51
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 249 ONGC.
Location Name & Code: Kodikulam & N9
S.No. Date of monitoring Time of
monitoring
I II III IV
1 14-08-2014 06:00AM 46 45 48 51
2 14-08-2014 07:00AM 45 42 43 48
3 14-08-2014 08:00AM 49 48 46 50
4 13-08-2014 09:00AM 48 46 44 42
5 13-08-2014 10:00AM 45 42 43 48
6 13-08-2014 11:00AM 45 48 46 49
7 13-08-2014 12:00PM 48 46 49 52
8 13-08-2014 01:00PM 46 45 48 51
9 13-08-2014 02:00PM 49 48 46 50
10 13-08-2014 03:00PM 45 48 46 49
11 13-08-2014 04:00PM 48 46 49 52
12 13-08-2014 05:00PM 48 46 44 42
13 13-08-2014 06:00PM 45 42 43 48
14 13-08-2014 07:00PM 49 48 46 50
15 13-08-2014 08:00PM 46 45 48 51
16 13-08-2014 09:00PM 44 45 46 47
17 13-08-2014 10:00PM 49 48 46 50
18 13-08-2014 11:00PM 48 46 49 52
19 14-08-2014 12:00AM 46 45 48 51
20 14-08-2014 01:00AM 44 43 42 45
21 14-08-2014 02:00AM 42 40 45 43
22 14-08-2014 03:00AM 48 46 49 52
23 14-08-2014 04:00AM 46 45 48 51
24 14-08-2014 05:00AM 46 45 48 51
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 250 ONGC.
Location Name & Code: KILAKKARAI & N10
S.No. Date of monitoring Time of
monitoring
I II III IV
1 17-08-2014 06:00AM 59 58 55 58
2 17-08-2014 07:00AM 59 60 56 54
3 17-08-2014 08:00AM 54 54 55 57
4 16-08-2014 09:00AM 53 56 52 53
5 16-08-2014 10:00AM 56 57 53 56
6 16-08-2014 11:00AM 55 53 59 53
7 16-08-2014 12:00PM 52 53 50 52
8 16-08-2014 01:00PM 55 52 52.6 52.9
9 16-08-2014 02:00PM 52 55 56 50
10 16-08-2014 03:00PM 51 54 52 56
11 16-08-2014 04:00PM 55 59 57 54
12 16-08-2014 05:00PM 58 56 54 57
13 16-08-2014 06:00PM 60 62 63 67
14 16-08-2014 07:00PM 63 62 64 61
15 16-08-2014 08:00PM 64 58 59 62
16 16-08-2014 09:00PM 68 63 57 58
17 16-08-2014 10:00PM 63 61 56 62
18 16-08-2014 11:00PM 54 58 57 58
19 17-08-2014 12:00AM 53 53 52 52
20 17-08-2014 01:00AM 60 57 54 52
21 17-08-2014 02:00AM 57 58 54 53
22 17-08-2014 03:00AM 56 55 56 55
23 17-08-2014 04:00AM 53 54 59 55
24 17-08-2014 05:00AM 57 53 57 56
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 251 ONGC.
Annexure-3.3
Metrological Data Monsoon-2014 ( July 30 th to September 3rd 2014)
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 7 30 1
216 9.6
301
2014 7 30 2
198 10.2
301
2014 7 30 3
268 9.5
302
2014 7 30 4
234 12.4
302
2014 7 30 5
221 13.3
302
2014 7 30 6
185 15.5
303
2014 7 30 7
261 17.6
303
2014 7 30 8
255 19.4
303
2014 7 30 9
253 20
304
2014 7 30 10
264 20.2
304
2014 7 30 11
239 21.5
304
2014 7 30 12
199 21
305
2014 7 30 13
240 21.8
305
2014 7 30 14
267 23.2
306
2014 7 30 15
208 22.7
306
2014 7 30 16
231 23.8
305
2014 7 30 17
185 24.2
304
2014 7 30 18
237 23
304
2014 7 30 19
206 22.8
303
2014 7 30 20
246 24.4
303
2014 7 30 21
194 25.2
303
2014 7 30 22
269 21.7
303
2014 7 30 23
266 15.6
302
2014 7 30 24
247 7.8
301
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 252 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 7 31 1
234 17.4
301
2014 7 31 2
228 23.8
301
2014 7 31 3
259 19.6
302
2014 7 31 4
267 18
302
2014 7 31 5
197 13.5
302
2014 7 31 6
204 11.7
303
2014 7 31 7
213 9.8
303
2014 7 31 8
269 5.2
303
2014 7 31 9
248 3.6
304
2014 7 31 10
255 4.5
304
2014 7 31 11
237 7.8
304
2014 7 31 12
251 9.7
305
2014 7 31 13
228 10
305
2014 7 31 14
236 12.6
305
2014 7 31 15
187 15.7
306
2014 7 31 16
192 17.5
305
2014 7 31 17
249 14.9
305
2014 7 31 18
273 9.5
304
2014 7 31 19
185 13.6
303
2014 7 31 20
241 19.3
303
2014 7 31 21
265 15
303
2014 7 31 22
220 11.3
303
2014 7 31 23
253 8.8
302
2014 7 31 24
277 12.6
301
2014 8 1 1
276 0.8
301
2014 8 1 2
195 3.7
301
2014 8 1 3
203 1.9
301
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 253 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 1 4
209 2.7
301
2014 8 1 5
258 4.8
302
2014 8 1 6
269 7.5
302
2014 8 1 7
174 8.3
302
2014 8 1 8
244 10.1
303
2014 8 1 9
180 10.5
303
2014 8 1 10
212 11.8
303
2014 8 1 11
269 12.7
303
2014 8 1 12
217 13
304
2014 8 1 13
226 15.2
304
2014 8 1 14
275 17.2
304
2014 8 1 15
189 19.6
304
2014 8 1 16
270 19
303
2014 8 1 17
261 17.9
303
2014 8 1 18
209 20.4
303
2014 8 1 19
245 18.6
302
2014 8 1 20
266 16.7
302
2014 8 1 21
213 21.8
302
2014 8 1 22
193 17.1
302
2014 8 1 23
252 11.7
301
2014 8 1 24
224 2.4
301
2014 8 2 1
248 1.8
301
2014 8 2 2
183 0.2
301
2014 8 2 3
240 2.9
302
2014 8 2 4
266 3.3
302
2014 8 2 5
217 3.8
302
2014 8 2 6
172 4.4
303
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 254 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 2 7
254 5
303
2014 8 2 8
285 6.7
303
2014 8 2 9
249 7.2
304
2014 8 2 10
210 8.1
304
2014 8 2 11
267 10.3
304
2014 8 2 12
197 7.5
305
2014 8 2 13
190 7.8
305
2014 8 2 14
238 9.5
306
2014 8 2 15
224 8.6
306
2014 8 2 16
201 11.7
305
2014 8 2 17
267 10.2
304
2014 8 2 18
239 7.5
304
2014 8 2 19
247 8.5
303
2014 8 2 20
205 11
303
2014 8 2 21
250 9.8
303
2014 8 2 22
187 7.9
303
2014 8 2 23
288 7.3
302
2014 8 2 24
279 3.6
301
2014 8 3 1
266 2.8
301
2014 8 3 2
247 5.9
301
2014 8 3 3
184 3.6
302
2014 8 3 4
206 2.7
302
2014 8 3 5
249 2.3
302
2014 8 3 6
280 1.5
303
2014 8 3 7
191 0.8
303
2014 8 3 8
257 0
303
2014 8 3 9
234 2.5
304
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 255 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 3 10
221 4.6
304
2014 8 3 11
196 7.9
304
2014 8 3 12
175 8.4
305
2014 8 3 13
255 9.6
305
2014 8 3 14
208 10.5
305
2014 8 3 15
230 10.9
306
2014 8 3 16
268 12.2
305
2014 8 3 17
182 12.6
305
2014 8 3 18
244 10.6
304
2014 8 3 19
279 13.1
303
2014 8 3 20
233 11
303
2014 8 3 21
208 10.3
303
2014 8 3 22
185 9.7
303
2014 8 3 23
164 10.8
302
2014 8 3 24
218 7.4
301
2014 8 4 1
201 2.8
301
2014 8 4 2
250 3.3
301
2014 8 4 3
184 4.1
301
2014 8 4 4
226 3.9
301
2014 8 4 5
271 4.4
302
2014 8 4 6
203 4
302
2014 8 4 7
185 5.5
302
2014 8 4 8
166 5.3
303
2014 8 4 9
287 6.7
303
2014 8 4 10
269 4.2
303
2014 8 4 11
231 3.6
303
2014 8 4 12
260 5.4
304
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 256 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 4 13
248 3
304
2014 8 4 14
277 8.8
304
2014 8 4 15
213 7.6
304
2014 8 4 16
226 9.7
303
2014 8 4 17
215 11
303
2014 8 4 18
279 12.8
303
2014 8 4 19
178 15.9
302
2014 8 4 20
218 18.1
302
2014 8 4 21
263 20.4
302
2014 8 4 22
279 19
302
2014 8 4 23
210 13.5
301
2014 8 4 24
239 3.2
301
2014 8 5 1
287 7.8
301
2014 8 5 2
226 10.7
301
2014 8 5 3
259 16.5
302
2014 8 5 4
230 18.9
302
2014 8 5 5
182 13.4
302
2014 8 5 6
219 10.8
303
2014 8 5 7
187 13.1
303
2014 8 5 8
269 5.5
303
2014 8 5 9
243 6.4
304
2014 8 5 10
255 8.2
304
2014 8 5 11
213 5
304
2014 8 5 12
275 7.3
305
2014 8 5 13
209 8.6
305
2014 8 5 14
173 9.6
306
2014 8 5 15
211 11.5
306
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 257 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 5 16
197 5.4
305
2014 8 5 17
215 4.7
304
2014 8 5 18
285 1.8
304
2014 8 5 19
244 0.9
303
2014 8 5 20
261 0
303
2014 8 5 21
278 2.5
303
2014 8 5 22
209 2.1
303
2014 8 5 23
215 3.8
302
2014 8 5 24
211 11.1
301
2014 8 6 1
208 6.4
301
2014 8 6 2
276 6
301
2014 8 6 3
250 4.6
302
2014 8 6 4
248 5.1
302
2014 8 6 5
219 3.5
302
2014 8 6 6
211 1.9
303
2014 8 6 7
267 0.7
303
2014 8 6 8
195 0.3
303
2014 8 6 9
247 1.2
304
2014 8 6 10
206 1.8
304
2014 8 6 11
257 2.6
304
2014 8 6 12
249 4
305
2014 8 6 13
218 4.7
305
2014 8 6 14
237 5.5
305
2014 8 6 15
261 5.8
306
2014 8 6 16
201 6.4
305
2014 8 6 17
197 7.6
305
2014 8 6 18
213 9.7
304
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 258 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 6 19
250 8.9
303
2014 8 6 20
284 11.2
303
2014 8 6 21
204 12.1
303
2014 8 6 22
175 10.5
303
2014 8 6 23
244 7
302
2014 8 6 24
233 8.8
301
2014 8 7 1
249 3.6
301
2014 8 7 2
217 3.1
301
2014 8 7 3
230 5.7
301
2014 8 7 4
201 1.5
301
2014 8 7 5
285 1.8
302
2014 8 7 6
277 2.7
302
2014 8 7 7
245 0.6
302
2014 8 7 8
218 2.1
303
2014 8 7 9
184 4.9
303
2014 8 7 10
215 1
303
2014 8 7 11
190 3.2
303
2014 8 7 12
277 4.3
304
2014 8 7 13
236 5.5
304
2014 8 7 14
248 4.6
304
2014 8 7 15
219 7.6
304
2014 8 7 16
197 7.8
303
2014 8 7 17
166 9.4
303
2014 8 7 18
228 8
303
2014 8 7 19
244 9.1
302
2014 8 7 20
260 7.3
302
2014 8 7 21
210 7.7
302
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 259 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 7 22
237 8.2
302
2014 8 7 23
269 5.8
301
2014 8 7 24
186 2.9
301
2014 8 8 1
224 3.7
301
2014 8 8 2
273 1.4
301
2014 8 8 3
212 2.6
302
2014 8 8 4
254 7.8
302
2014 8 8 5
198 6.5
302
2014 8 8 6
191 6.1
303
2014 8 8 7
248 5.2
303
2014 8 8 8
263 3.6
303
2014 8 8 9
237 2.4
304
2014 8 8 10
208 4.7
304
2014 8 8 11
217 7.3
304
2014 8 8 12
195 5.2
305
2014 8 8 13
241 5.8
305
2014 8 8 14
281 4.1
306
2014 8 8 15
204 8.4
306
2014 8 8 16
213 6.4
305
2014 8 8 17
176 6
304
2014 8 8 18
229 5.6
304
2014 8 8 19
288 4.5
303
2014 8 8 20
238 2.6
303
2014 8 8 21
198 5.6
303
2014 8 8 22
277 4.8
303
2014 8 8 23
242 3
302
2014 8 8 24
180 8.4
301
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 260 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 9 1
249 2.5
301
2014 8 9 2
207 2.1
301
2014 8 9 3
268 1.8
302
2014 8 9 4
271 3.9
302
2014 8 9 5
213 2.6
302
2014 8 9 6
228 4.7
303
2014 8 9 7
164 3.3
303
2014 8 9 8
208 1.9
303
2014 8 9 9
220 5.2
304
2014 8 9 10
276 4.4
304
2014 8 9 11
264 3.4
304
2014 8 9 12
183 3.7
305
2014 8 9 13
250 2.8
305
2014 8 9 14
282 4.1
305
2014 8 9 15
189 5.3
306
2014 8 9 16
201 4.5
305
2014 8 9 17
257 1.6
305
2014 8 9 18
294 1.8
304
2014 8 9 19
212 2.7
303
2014 8 9 20
239 2.3
303
2014 8 9 21
214 2
303
2014 8 9 22
233 3.6
303
2014 8 9 23
199 3.9
302
2014 8 9 24
233 0.7
301
2014 8 10 1
280 3.2
301
2014 8 10 2
227 1.8
301
2014 8 10 3
208 0.3
301
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 261 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 10 4
238 1.7
301
2014 8 10 5
246 2.1
302
2014 8 10 6
267 5.2
302
2014 8 10 7
211 4.5
302
2014 8 10 8
179 3.7
303
2014 8 10 9
283 0.9
303
2014 8 10 10
277 2.4
303
2014 8 10 11
236 3.6
303
2014 8 10 12
221 1.6
304
2014 8 10 13
194 1.9
304
2014 8 10 14
183 2.8
304
2014 8 10 15
273 3.8
304
2014 8 10 16
243 4.3
303
2014 8 10 17
288 4
303
2014 8 10 18
218 3.4
303
2014 8 10 19
248 3.1
302
2014 8 10 20
206 4.6
302
2014 8 10 21
264 3
302
2014 8 10 22
197 1.3
302
2014 8 10 23
255 5.8
301
2014 8 10 24
261 2
301
2014 8 11 1
237 3.4
301
2014 8 11 2
205 3.1
301
2014 8 11 3
267 4.5
302
2014 8 11 4
261 4.2
302
2014 8 11 5
228 5.6
302
2014 8 11 6
219 2.5
303
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 262 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 11 7
208 4
303
2014 8 11 8
273 7.6
303
2014 8 11 9
260 7.8
304
2014 8 11 10
169 9.3
304
2014 8 11 11
274 6.7
304
2014 8 11 12
191 5.5
305
2014 8 11 13
228 4.3
305
2014 8 11 14
237 5
306
2014 8 11 15
261 2.6
306
2014 8 11 16
283 3.5
305
2014 8 11 17
274 3.9
304
2014 8 11 18
269 5.1
304
2014 8 11 19
249 5.7
303
2014 8 11 20
196 6.2
303
2014 8 11 21
187 7
303
2014 8 11 22
284 8.5
303
2014 8 11 23
267 7.6
302
2014 8 11 24
249 5.8
301
2014 8 12 1
208 7.7
301
2014 8 12 2
237 8.8
301
2014 8 12 3
190 2.6
302
2014 8 12 4
274 3.8
302
2014 8 12 5
260 4.7
302
2014 8 12 6
229 2.9
303
2014 8 12 7
207 2.2
303
2014 8 12 8
238 5.4
303
2014 8 12 9
269 3
304
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 263 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 12 10
204 3.8
304
2014 8 12 11
185 4.8
304
2014 8 12 12
234 5.3
305
2014 8 12 13
263 6.2
305
2014 8 12 14
213 6
305
2014 8 12 15
288 7.5
306
2014 8 12 16
193 7.9
305
2014 8 12 17
270 8.5
305
2014 8 12 18
246 9.6
304
2014 8 12 19
249 8
303
2014 8 12 20
212 9.4
303
2014 8 12 21
177 10.1
303
2014 8 12 22
283 7.8
303
2014 8 12 23
244 6.7
302
2014 8 12 24
267 2.9
301
2014 8 13 1
234 11.2
301
2014 8 13 2
260 10.8
301
2014 8 13 3
175 12.7
301
2014 8 13 4
266 10.4
301
2014 8 13 5
218 9
302
2014 8 13 6
202 9.5
302
2014 8 13 7
258 8.2
302
2014 8 13 8
245 9.9
303
2014 8 13 9
235 7.6
303
2014 8 13 10
196 7.1
303
2014 8 13 11
281 8.7
303
2014 8 13 12
174 9.6
304
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 264 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 13 13
182 7
304
2014 8 13 14
273 6.8
304
2014 8 13 15
239 6.1
304
2014 8 13 16
210 7.3
303
2014 8 13 17
227 8.3
303
2014 8 13 18
177 6.5
303
2014 8 13 19
165 7.9
302
2014 8 13 20
268 6.2
302
2014 8 13 21
189 7.7
302
2014 8 13 22
249 5.8
302
2014 8 13 23
220 6.7
301
2014 8 13 24
251 13.5
301
2014 8 14 1
230 3.7
301
2014 8 14 2
274 0.5
301
2014 8 14 3
245 2.6
302
2014 8 14 4
216 2.9
302
2014 8 14 5
193 0.7
302
2014 8 14 6
164 7.3
303
2014 8 14 7
257 5.8
303
2014 8 14 8
239 1.9
303
2014 8 14 9
260 8.1
304
2014 8 14 10
207 4.6
304
2014 8 14 11
219 10.3
304
2014 8 14 12
197 7.3
305
2014 8 14 13
182 9.5
305
2014 8 14 14
268 7.4
306
2014 8 14 15
257 8.7
306
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 265 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 14 16
231 10.2
305
2014 8 14 17
281 7.2
304
2014 8 14 18
188 15.9
304
2014 8 14 19
219 10
303
2014 8 14 20
210 12.3
303
2014 8 14 21
264 8.4
303
2014 8 14 22
206 13.8
303
2014 8 14 23
229 10.8
302
2014 8 14 24
188 -0.6
301
2014 8 15 1
174 1.5
301
2014 8 15 2
199 2.3
301
2014 8 15 3
258 4.1
302
2014 8 15 4
237 3.6
302
2014 8 15 5
249 4.4
302
2014 8 15 6
274 6.9
303
2014 8 15 7
207 7.7
303
2014 8 15 8
176 5.2
303
2014 8 15 9
235 5
304
2014 8 15 10
275 6.3
304
2014 8 15 11
208 7.5
304
2014 8 15 12
219 8.6
305
2014 8 15 13
277 7.4
305
2014 8 15 14
178 10.3
305
2014 8 15 15
182 6.8
306
2014 8 15 16
237 5.9
305
2014 8 15 17
244 5
305
2014 8 15 18
211 4.6
304
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 266 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 15 19
257 4.3
303
2014 8 15 20
260 3.7
303
2014 8 15 21
207 3.1
303
2014 8 15 22
230 2.5
303
2014 8 15 23
241 2.8
302
2014 8 15 24
233 1.5
301
2014 8 16 1
249 7.5
301
2014 8 16 2
266 6.8
301
2014 8 16 3
237 7.6
301
2014 8 16 4
189 8.8
301
2014 8 16 5
284 6.4
302
2014 8 16 6
181 6
302
2014 8 16 7
241 5.3
302
2014 8 16 8
129 5.7
303
2014 8 16 9
90 1.4
303
2014 8 16 10
169 2.9
303
2014 8 16 11
202 3.2
303
2014 8 16 12
229 2.5
304
2014 8 16 13
146 3.7
304
2014 8 16 14
197 5.8
304
2014 8 16 15
173 6.1
304
2014 8 16 16
221 5.6
303
2014 8 16 17
253 8.1
303
2014 8 16 18
195 8.8
303
2014 8 16 19
147 10.4
302
2014 8 16 20
208 9.6
302
2014 8 16 21
267 9.2
302
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 267 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 16 22
123 10.2
302
2014 8 16 23
181 7.7
301
2014 8 16 24
126 8
301
2014 8 17 1
276 10.5
301
2014 8 17 2
209 11.8
301
2014 8 17 3
194 7.9
302
2014 8 17 4
227 3.8
302
2014 8 17 5
254 6.2
302
2014 8 17 6
213 8.4
303
2014 8 17 7
185 7.7
303
2014 8 17 8
286 4.3
303
2014 8 17 9
217 4.6
304
2014 8 17 10
230 6.8
304
2014 8 17 11
241 9.1
304
2014 8 17 12
179 5.8
305
2014 8 17 13
193 7.2
305
2014 8 17 14
257 4.5
306
2014 8 17 15
219 4.3
306
2014 8 17 16
207 3.8
305
2014 8 17 17
168 3.2
304
2014 8 17 18
182 4.1
304
2014 8 17 19
274 3
303
2014 8 17 20
294 2.6
303
2014 8 17 21
227 2.2
303
2014 8 17 22
260 3.7
303
2014 8 17 23
285 5.8
302
2014 8 17 24
233 11.6
301
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 268 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 18 1
158 3.7
301
2014 8 18 2
241 7.4
301
2014 8 18 3
199 2.4
302
2014 8 18 4
175 2.9
302
2014 8 18 5
238 4.8
302
2014 8 18 6
207 3.5
303
2014 8 18 7
226 4.2
303
2014 8 18 8
285 6.3
303
2014 8 18 9
246 6
304
2014 8 18 10
218 3.4
304
2014 8 18 11
267 7.6
304
2014 8 18 12
249 1.7
305
2014 8 18 13
234 2
305
2014 8 18 14
216 5.8
305
2014 8 18 15
168 3.1
306
2014 8 18 16
239 3.4
305
2014 8 18 17
197 4.9
305
2014 8 18 18
240 4.2
304
2014 8 18 19
260 9.4
303
2014 8 18 20
180 10.8
303
2014 8 18 21
273 8
303
2014 8 18 22
243 8.9
303
2014 8 18 23
219 7.5
302
2014 8 18 24
287 0.9
301
2014 8 19 1
178 3.5
301
2014 8 19 2
166 1.5
301
2014 8 19 3
218 1.9
301
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 269 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 19 4
268 2.8
301
2014 8 19 5
249 1
302
2014 8 19 6
206 4.7
302
2014 8 19 7
230 3.9
302
2014 8 19 8
261 5
303
2014 8 19 9
241 5.2
303
2014 8 19 10
194 6.3
303
2014 8 19 11
267 7.2
303
2014 8 19 12
237 7.8
304
2014 8 19 13
264 6.7
304
2014 8 19 14
169 6.2
304
2014 8 19 15
291 7.1
304
2014 8 19 16
273 9
303
2014 8 19 17
219 8.6
303
2014 8 19 18
234 6.8
303
2014 8 19 19
227 7.6
302
2014 8 19 20
267 5.5
302
2014 8 19 21
201 13.4
302
2014 8 19 22
237 9.3
302
2014 8 19 23
183 6.8
301
2014 8 19 24
244 0.7
301
2014 8 20 1
190 11.8
301
2014 8 20 2
238 10.7
301
2014 8 20 3
210 9.5
302
2014 8 20 4
182 8.9
302
2014 8 20 5
246 11.3
302
2014 8 20 6
154 9.6
303
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 270 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 20 7
238 11.7
303
2014 8 20 8
267 7.8
303
2014 8 20 9
207 10.5
304
2014 8 20 10
260 11.2
304
2014 8 20 11
193 11.9
304
2014 8 20 12
155 11.6
305
2014 8 20 13
259 11
305
2014 8 20 14
281 10.7
306
2014 8 20 15
224 9.8
306
2014 8 20 16
264 10.5
305
2014 8 20 17
200 11.1
304
2014 8 20 18
240 10.6
304
2014 8 20 19
188 9.2
303
2014 8 20 20
246 11.8
303
2014 8 20 21
283 9.4
303
2014 8 20 22
249 7.3
303
2014 8 20 23
227 12.5
302
2014 8 20 24
199 10.8
301
2014 8 21 1
215 3.5
301
2014 8 21 2
231 2.9
301
2014 8 21 3
274 0.5
302
2014 8 21 4
206 1.9
302
2014 8 21 5
219 1.4
302
2014 8 21 6
185 3.1
303
2014 8 21 7
269 0.8
303
2014 8 21 8
213 3.6
303
2014 8 21 9
228 2.9
304
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 271 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 21 10
270 1.1
304
2014 8 21 11
192 2.7
304
2014 8 21 12
177 4.9
305
2014 8 21 13
269 5
305
2014 8 21 14
281 6.4
305
2014 8 21 15
237 9.5
306
2014 8 21 16
249 13.7
305
2014 8 21 17
260 10.9
305
2014 8 21 18
210 8.5
304
2014 8 21 19
276 10.1
303
2014 8 21 20
243 12
303
2014 8 21 21
288 10.3
303
2014 8 21 22
216 8.3
303
2014 8 21 23
224 7.8
302
2014 8 21 24
261 0.7
301
2014 8 22 1
189 0.9
301
2014 8 22 2
249 2.1
301
2014 8 22 3
203 -0.2
301
2014 8 22 4
173 0.6
301
2014 8 22 5
180 1.4
302
2014 8 22 6
241 1.9
302
2014 8 22 7
267 0.1
302
2014 8 22 8
294 0
303
2014 8 22 9
234 1.6
303
2014 8 22 10
217 2.7
303
2014 8 22 11
237 1.9
303
2014 8 22 12
247 3.2
304
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 272 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 22 13
233 1.2
304
2014 8 22 14
186 2.8
304
2014 8 22 15
276 8.2
304
2014 8 22 16
249 10.7
303
2014 8 22 17
277 9.9
303
2014 8 22 18
211 16.8
303
2014 8 22 19
238 23.4
302
2014 8 22 20
268 24
302
2014 8 22 21
185 25.4
302
2014 8 22 22
241 18.6
302
2014 8 22 23
261 19.9
301
2014 8 22 24
218 0.3
301
2014 8 23 1
234 27.4
301
2014 8 23 2
215 23.5
301
2014 8 23 3
228 25.7
302
2014 8 23 4
198 22
302
2014 8 23 5
264 24.2
302
2014 8 23 6
256 19.5
303
2014 8 23 7
223 15.1
303
2014 8 23 8
207 10.8
303
2014 8 23 9
183 10.2
304
2014 8 23 10
247 14.9
304
2014 8 23 11
268 16.6
304
2014 8 23 12
219 20.3
305
2014 8 23 13
230 23
305
2014 8 23 14
281 24.3
306
2014 8 23 15
183 23.6
306
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 273 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 23 16
276 20.8
305
2014 8 23 17
262 27.5
304
2014 8 23 18
228 28.6
304
2014 8 23 19
197 31.2
303
2014 8 23 20
168 25.7
303
2014 8 23 21
233 23.9
303
2014 8 23 22
259 26.9
303
2014 8 23 23
216 27.2
302
2014 8 23 24
296 29.6
301
2014 8 24 1
234 26.6
301
2014 8 24 2
216 29.7
301
2014 8 24 3
208 27.3
302
2014 8 24 4
174 28.9
302
2014 8 24 5
233 21.7
302
2014 8 24 6
192 25.6
303
2014 8 24 7
269 21.5
303
2014 8 24 8
244 29.8
303
2014 8 24 9
219 19.6
304
2014 8 24 10
250 15.5
304
2014 8 24 11
194 10.1
304
2014 8 24 12
166 9.7
305
2014 8 24 13
273 5.2
305
2014 8 24 14
248 1.7
305
2014 8 24 15
231 2.8
306
2014 8 24 16
281 5
305
2014 8 24 17
209 10.3
305
2014 8 24 18
237 13.5
304
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 274 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 24 19
241 18.9
303
2014 8 24 20
268 21.7
303
2014 8 24 21
259 25.4
303
2014 8 24 22
213 27.1
303
2014 8 24 23
262 23.6
302
2014 8 24 24
277 22.1
301
2014 8 25 1
247 23.4
301
2014 8 25 2
268 17.7
301
2014 8 25 3
215 13.6
301
2014 8 25 4
234 15.3
301
2014 8 25 5
208 12.7
302
2014 8 25 6
199 11.3
302
2014 8 25 7
174 10.8
302
2014 8 25 8
269 9.6
303
2014 8 25 9
233 10.5
303
2014 8 25 10
261 13.6
303
2014 8 25 11
246 15
303
2014 8 25 12
270 17.7
304
2014 8 25 13
259 19.7
304
2014 8 25 14
228 23.2
304
2014 8 25 15
183 24.6
304
2014 8 25 16
234 25.2
303
2014 8 25 17
266 30.5
303
2014 8 25 18
249 27
303
2014 8 25 19
281 25.7
302
2014 8 25 20
200 31.9
302
2014 8 25 21
237 30.1
302
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 275 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 25 22
219 27.4
302
2014 8 25 23
294 22.7
301
2014 8 25 24
194 19.2
301
2014 8 26 1
217 22.4
301
2014 8 26 2
168 28.6
301
2014 8 26 3
287 21.9
302
2014 8 26 4
269 19.7
302
2014 8 26 5
238 17.3
302
2014 8 26 6
271 23.9
303
2014 8 26 7
207 15.4
303
2014 8 26 8
239 14.3
303
2014 8 26 9
243 13.6
304
2014 8 26 10
282 12
304
2014 8 26 11
262 12.6
304
2014 8 26 12
215 10.7
305
2014 8 26 13
240 9.9
305
2014 8 26 14
196 6.5
306
2014 8 26 15
181 9.6
306
2014 8 26 16
271 13
305
2014 8 26 17
237 19.3
304
2014 8 26 18
264 22.1
304
2014 8 26 19
298 29
303
2014 8 26 20
194 31.5
303
2014 8 26 21
268 34.8
303
2014 8 26 22
233 36.2
303
2014 8 26 23
274 30.6
302
2014 8 26 24
244 18.9
301
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 276 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 27 1
277 39.6
301
2014 8 27 2
198 35.3
301
2014 8 27 3
237 32.1
302
2014 8 27 4
246 30.8
302
2014 8 27 5
281 29
302
2014 8 27 6
273 32.4
303
2014 8 27 7
225 29.8
303
2014 8 27 8
210 19.6
303
2014 8 27 9
182 28.9
304
2014 8 27 10
246 21.7
304
2014 8 27 11
239 25
304
2014 8 27 12
297 29
305
2014 8 27 13
280 30.4
305
2014 8 27 14
191 32.8
305
2014 8 27 15
251 30.9
306
2014 8 27 16
237 27.1
305
2014 8 27 17
207 25.4
305
2014 8 27 18
266 23.6
304
2014 8 27 19
217 22.1
303
2014 8 27 20
284 19.8
303
2014 8 27 21
279 17.9
303
2014 8 27 22
229 13.5
303
2014 8 27 23
249 16.8
302
2014 8 27 24
217 41
301
2014 8 28 1
256 11.5
301
2014 8 28 2
218 9.6
301
2014 8 28 3
274 7.9
301
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 277 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 28 4
194 11.1
301
2014 8 28 5
237 8.8
302
2014 8 28 6
266 9.1
302
2014 8 28 7
281 13.7
302
2014 8 28 8
234 6.2
303
2014 8 28 9
209 13
303
2014 8 28 10
193 15.4
303
2014 8 28 11
169 15.9
303
2014 8 28 12
267 19.3
304
2014 8 28 13
249 21
304
2014 8 28 14
218 21.6
304
2014 8 28 15
237 27.3
304
2014 8 28 16
264 29.1
303
2014 8 28 17
280 30.4
303
2014 8 28 18
197 29.5
303
2014 8 28 19
216 31
302
2014 8 28 20
259 32.4
302
2014 8 28 21
238 30.9
302
2014 8 28 22
227 22.7
302
2014 8 28 23
213 23.3
301
2014 8 28 24
290 12.7
301
2014 8 29 1
249 17.7
301
2014 8 29 2
218 26.8
301
2014 8 29 3
277 24.3
302
2014 8 29 4
230 24
302
2014 8 29 5
269 23.7
302
2014 8 29 6
257 23
303
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 278 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 29 7
194 19.4
303
2014 8 29 8
255 20.8
303
2014 8 29 9
238 25.3
304
2014 8 29 10
294 27.1
304
2014 8 29 11
206 30.2
304
2014 8 29 12
240 31.5
305
2014 8 29 13
191 33.9
305
2014 8 29 14
231 37.4
306
2014 8 29 15
262 38.7
306
2014 8 29 16
214 35.8
305
2014 8 29 17
292 37.3
304
2014 8 29 18
260 36
304
2014 8 29 19
227 34.7
303
2014 8 29 20
199 33.5
303
2014 8 29 21
273 31.6
303
2014 8 29 22
254 27.3
303
2014 8 29 23
251 22.5
302
2014 8 29 24
172 20.5
301
2014 8 30 1
267 31
301
2014 8 30 2
210 29.8
301
2014 8 30 3
238 27.1
302
2014 8 30 4
279 24.7
302
2014 8 30 5
187 23.1
302
2014 8 30 6
269 23
303
2014 8 30 7
217 19.5
303
2014 8 30 8
244 17.3
303
2014 8 30 9
273 16.7
304
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 279 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 30 10
214 13.8
304
2014 8 30 11
264 15.6
304
2014 8 30 12
239 14.6
305
2014 8 30 13
210 16.9
305
2014 8 30 14
192 18.1
305
2014 8 30 15
227 19.6
306
2014 8 30 16
268 17.3
305
2014 8 30 17
249 20.7
305
2014 8 30 18
299 19.9
304
2014 8 30 19
237 21.5
303
2014 8 30 20
281 20.6
303
2014 8 30 21
267 16.8
303
2014 8 30 22
284 19.1
303
2014 8 30 23
219 21.3
302
2014 8 30 24
222 22.7
301
2014 8 31 1
214 3.7
301
2014 8 31 2
284 5.8
301
2014 8 31 3
217 1.5
301
2014 8 31 4
197 3.6
301
2014 8 31 5
238 5
302
2014 8 31 6
267 11.6
302
2014 8 31 7
269 21
302
2014 8 31 8
247 19.3
303
2014 8 31 9
284 21.7
303
2014 8 31 10
286 22.8
303
2014 8 31 11
217 25.9
303
2014 8 31 12
230 27.1
304
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 280 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 8 31 13
192 29
304
2014 8 31 14
164 30.3
304
2014 8 31 15
234 31.7
304
2014 8 31 16
264 32.6
303
2014 8 31 17
279 27.7
303
2014 8 31 18
257 25.7
303
2014 8 31 19
248 19.6
302
2014 8 31 20
293 20.1
302
2014 8 31 21
213 24
302
2014 8 31 22
245 30.5
302
2014 8 31 23
277 24.8
301
2014 8 31 24
262 0
301
2014 9 1 1
216 26.3
301
2014 9 1 2
223 30.7
301
2014 9 1 3
274 24
302
2014 9 1 4
270 22.8
302
2014 9 1 5
234 19.8
302
2014 9 1 6
265 20
303
2014 9 1 7
184 15.7
303
2014 9 1 8
204 13.6
303
2014 9 1 9
236 15.1
304
2014 9 1 10
247 18.2
304
2014 9 1 11
267 21.6
304
2014 9 1 12
218 28.2
305
2014 9 1 13
203 30.5
305
2014 9 1 14
249 34.9
306
2014 9 1 15
221 35.4
306
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 281 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 9 1 16
193 33.2
305
2014 9 1 17
242 31
304
2014 9 1 18
266 32.3
304
2014 9 1 19
215 29.7
303
2014 9 1 20
201 27.5
303
2014 9 1 21
188 24.4
303
2014 9 1 22
165 20.6
303
2014 9 1 23
196 14.9
302
2014 9 1 24
251 23.4
301
2014 9 2 1
206 1.8
301
2014 9 2 2
184 0.6
301
2014 9 2 3
210 2.7
302
2014 9 2 4
268 3.9
302
2014 9 2 5
232 2.4
302
2014 9 2 6
199 5
303
2014 9 2 7
240 10.5
303
2014 9 2 8
246 12.3
303
2014 9 2 9
269 13
304
2014 9 2 10
187 17.1
304
2014 9 2 11
205 21.2
304
2014 9 2 12
219 24.3
305
2014 9 2 13
235 28.1
305
2014 9 2 14
190 29.5
305
2014 9 2 15
261 31
306
2014 9 2 16
231 31.5
305
2014 9 2 17
204 33.4
305
2014 9 2 18
289 27.3
304
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 282 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 9 2 19
173 30.7
303
2014 9 2 20
198 27.9
303
2014 9 2 21
245 21.8
303
2014 9 2 22
240 13.8
303
2014 9 2 23
271 19.6
302
2014 9 2 24
226 0.4
301
2014 9 3 1
254 10.2
301
2014 9 3 2
266 12.8
301
2014 9 3 3
175 7.9
301
2014 9 3 4
208 15.7
301
2014 9 3 5
259 14
302
2014 9 3 6
237 11.5
302
2014 9 3 7
215 9.3
302
2014 9 3 8
169 7.6
303
2014 9 3 9
274 11.2
303
2014 9 3 10
251 14.4
303
2014 9 3 11
232 15.1
303
2014 9 3 12
272 19.7
304
2014 9 3 13
248 21.6
304
2014 9 3 14
210 23
304
2014 9 3 15
268 24.5
304
2014 9 3 16
197 22.3
303
2014 9 3 17
226 20.7
303
2014 9 3 18
275 17.6
303
2014 9 3 19
250 17.9
302
2014 9 3 20
184 15.4
302
2014 9 3 21
217 13.6
302
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 283 ONGC.
Year Month Day Hour Wd Ws (km/hr)
temp
(K)
2014 9 3 22
263 12
302
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 284 ONGC.
Annexure-3.4
Demographic Details
Sl
No
NAME No. HH TOT_P TOT_M TOT_F P_SC P_ST P_LIT P_ILL TOT_WORK_P
1 Pandamangalam 58 229 119 110 22 0 204 25 171 2 Pamban 8522 37819 19163 18656 503 3 28304 9515 13116 3 Valinockam 1067 6221 3177 3044 10 0 4139 2082 2069
4 Andichiendal 18 80 45 35 52 0 70 10 74 5 Vennathur 544 2218 1063 1155 508 0 1471 747 1390 6 Pathanendal 161 638 275 363 33 0 334 304 310
7 Naranamangalam 296 1342 654 688 352 0 715 627 985 8 Alamalandal 450 1961 956 1005 913 0 1106 855 1218 9 Devipattinam 2097 10166 4891 5275 1830 225 6779 3387 2987
10 Peruvayal 329 1394 681 713 1075 0 700 694 803 11 Kumariyendal 63 298 154 144 28 0 145 153 207 12 Kavanur 573 2379 1145 1234 981 0 1437 942 1531
13 Karendal 232 911 426 485 360 0 589 322 618 14 Pullangudi 323 1398 703 695 727 0 892 506 742 15 Chittrakkottai 1818 8111 3701 4410 754 0 5331 2780 2735
16 Athyuthu 491 2448 1151 1297 302 0 1555 893 775 17 Alangulam 201 941 439 502 304 0 614 327 258 18 Toruvalur 647 2474 1205 1269 1407 0 1553 921 1535
19 Vannivayal 407 1625 817 808 1019 0 851 774 920 20 Surankottai 1014 4445 2253 2192 1728 3 2857 1588 1330 21 Pattinamkattan 3310 14244 7122 7122 2605 1 10246 3998 4682
22 Thiruvolhiyakalugoorani 630 2960 1437 1523 325 0 1879 1081 1076 23 Terbhogi 1037 4685 2128 2557 112 0 2927 1758 1441 24 Alagankulam 2894 13754 6262 7492 500 0 9713 4041 2797
25 Attangarai 565 2764 1319 1445 0 0 1810 954 815
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 285 ONGC.
26 Perungulam 1134 5280 2616 2664 51 0 3336 1944 2514
27 Valantaravai 1689 7400 3665 3735 1354 0 4697 2703 3067 28 Kusavankudi 599 2728 1288 1440 727 0 1717 1011 1000
29 Sakkarakottai 3737 16014 7937 8077 3090 25 10667 5347 5787
30 Rajasuriamadai 844 3898 1958 1940 964 0 2069 1829 1386 31 Kooriyur 406 1831 889 942 637 0 1070 761 761
32 Achchundanvayal 329 1451 707 744 410 0 941 510 679
33 Landai 538 2136 1053 1083 1814 0 1324 812 1120 34 Panaikkulam 297 1127 543 584 538 0 565 562 631
35 Malangudi 455 1910 941 969 1276 0 997 913 1175
36 Ekkakudi 326 1370 611 759 482 0 734 636 462 37 Vellamarichchukkatti 358 1380 673 707 882 0 669 711 821
38 Achadipirambu 31 153 76 77 150 0 100 53 1
39 Kudakottai 705 3327 1588 1739 580 0 1660 1667 1216 40 Vannankundu 1515 6607 3061 3546 176 0 3717 2890 3690
41 Raghunathapuram 1529 6410 3052 3358 141 0 4159 2251 3189
42 Kumbaram 499 2027 1022 1005 0 0 1075 952 1354 43 Rettaiyurani 1521 6357 3173 3184 170 0 3881 2476 3366
44 Nagachi 723 3329 1710 1619 33 0 1955 1374 1245
45 Enmanamkondan 1418 6590 3293 3297 590 13 4630 1960 2066 46 Pirappanvalasai 1045 4687 2220 2467 198 7 3180 1507 1330
47 Sattakkonvalasai 533 2496 1226 1270 53 0 1721 775 1003
48 Mandapam 1720 8255 4166 4089 417 8 5924 2331 2359 49 Nochiyurani 554 2343 1149 1194 35 0 1642 701 886
50 Pudumadam 1751 7688 3419 4269 62 0 5375 2313 1713
51 Karan 790 3325 1637 1688 23 0 2097 1228 1851 52 Periapattinam 1799 9478 4793 4685 100 0 6442 3036 2596
53 Kalimankundu 1275 5338 2626 2712 118 0 2828 2510 2665
54 Tiruppullani 1440 6084 2895 3189 2020 0 3592 2492 2517 55 Kalari 391 1478 697 781 1187 0 799 679 846
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 286 ONGC.
56 Utrakosamangai 483 2084 1051 1033 278 0 1541 543 1090
57 Mallal 259 1046 488 558 677 0 441 605 596 58 Alagankulam 278 1173 603 570 746 0 571 602 685
59 Nalirukkai 285 1070 536 534 363 0 516 554 613
60 Panaydiyendal 310 1151 566 585 1015 0 410 741 782 61 Valanur 616 2322 1131 1191 1777 0 1237 1085 1258
62 Kulapatham 351 1447 659 788 545 0 754 693 724
63 Pallamerkkulam 532 2535 1050 1485 1312 0 1556 979 952 64 Kanjirangudi 1248 5533 2646 2887 676 0 3415 2118 1924
65 Keelakarai 593 2591 1294 1297 879 0 1385 1206 936
66 Manikkaneri 150 503 221 282 27 0 239 264 373 67 Pullandai 242 1101 515 586 703 0 711 390 676
68 Mayakulam 860 5842 3423 2419 490 1 4328 1514 1519
69 Ramanathapuram (M) 12952 62050 31111 30939 4742 580 48694 13356 18738 70 Keelakarai (TP) 5863 30412 14047 16365 1014 0 23116 7296 7462
71 Mandapam (TP) 3291 16343 8254 8089 1136 6 11679 4664 4732
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 287 ONGC.
Sl No NAME MAINWO
RK_P
MAI
N_
CL_
P
MAIN_A
L_P
MAI
N_
HH_
P
MAI
N_
OT_
P
MARGWO
RK_P
MAR
G_
CL_P
MAR
G_
AL_P
MARG_H
H_P
MAR
G_
OT_P
NON_WO
RK_P
1 Pandamangalam 167 86 24 7 50 4 2 0 0 2 58
2 Pamban 11937
209 127 264
1133
7 1179 295 110 52 722 24703
3 Valinockam
1119 7 13 9 1090 950 11 12 5 922 4152
4 Andichiendal 58 42 13 0 3 16 14 1 0 1 6
5 Vennathur 1236 756 201 37 242 154 63 81 3 7 828
6 Pathanendal 309 201 13 0 95 1 1 0 0 0 328
7 Naranamangalam 899 810 16 7 66 86 67 3 4 12 357
8 Alamalandal 828 735 13 14 66 390 39 347 0 4 743
9 Devipattinam 2508 98 106 129 2175 479 229 67 35 148 7179
10 Peruvayal 798 480 12 244 62 5 2 2 0 1 591
11 Kumariyendal 207 204 0 2 1 0 0 0 0 0 91
12 Kavanur 1136 657 307 5 167 395 221 156 1 17 848
13 Karendal 378 111 187 0 80 240 19 214 0 7 293
14 Pullangudi 612 270 69 4 269 130 49 70 0 11 656 15 Chittrakko
ttai 1954 179 118 40 1617 781 23 50 353 355 5376
16 Athyuthu 507 98 49 121 239 268 32 126 2 108 1673
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 288 ONGC.
17 Palangulam 162 1 2 0 159 96 1 91 3 1 683
18 Toruvalur 1034 249 340 0 445 501 22 454 1 24 939 19 Vannivaya
l 604 355 187 0 62 316 12 256 5 43 705 20 Surankotta
i 1300 234 190 48 828 30 11 6 2 11 3115
21 Pattinamkattan 3913 178 662 51 3022 769 186 327 31 225 9562
22 Thiruvolhiyakalugoorani 747 224 159 4 360 329 5 317 4 3 1884
23 Terbhogi 939 34 166 18 721 502 0 215 229 58 3244 24 Alagankul
am 2292 85 24 41 2142 505 4 0 183 318 10957
25 Attangarai 706 34 176 9 487 109 6 56 1 46 1949 26 Perungula
m 2236 97 194 651 1294 278 5 153 44 76 2766
27 Valantaravai 2121 114 1182 183 642 946 12 634 245 55 4333
28 Kusavankudi 721 175 207 5 334 279 11 129 90 49 1728
29 Sakkarakottai 4420 543 338 113 3426 1367 30 602 397 338 10227
30 Rajasuriamadai 1029 287 56 5 681 357 55 224 1 77 2512
31 Kooriyur 737 290 139 9 299 24 18 6 0 0 1070
32 Achchundanvayal 360 157 95 1 107 319 27 244 3 45 772
33 Landai 905 681 32 4 188 215 77 84 5 49 1016
34 Panaikkulam 350 237 50 1 62 281 95 178 1 7 496
35 Malangudi 740 496 190 1 53 435 198 217 0 20 735
36 Ekkakudi 175 66 3 9 97 287 17 245 2 23 908
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 289 ONGC.
37 Vellamarichchukkatti 787 734 5 0 48 34 32 1 0 1 559
38 Achadipirambu 1 1 0 0 0 0 0 0 0 0 152
39 Kudakottai 688 82 29 186 391 528 13 176 71 268 2111
40 Vannankundu 3040 848 799 811 582 650 50 225 306 69 2917
41 Raghunathapuram 2645 671 746 644 584 544 159 107 152 126 3221
42 Kumbaram 304 89 109 57 49 1050 43 418 574 15 673
43 Rettaiyurani 2352 511 711 309 821 1014 26 536 101 351 2991
44 Nagachi 986 43 76 115 752 259 3 30 213 13 2084 45 Enmanam
kondan 1888 159 63 103 1563 178 3 35 81 59 4524
46 Pirappanvalasai 1191 102 196 56 837 139 9 86 4 40 3357
47 Sattakkonvalasai 896 13 6 141 736 107 33 4 34 36 1493
48 Mandapam 1817 58 13 69 1677 542 28 75 269 170 5896
49 Nochiyurani 616 48 22 19 527 270 1 27 167 75 1457
50 Pudumadam 1318 79 133 8 1098 395 13 164 135 83 5975
51 Karan 898 64 291 51 492 953 5 217 650 81 1474 52 Periapattin
am 2521 35 167 262 2057 75 5 7 21 42 6882
53 Kalimankundu 2309 85 207 584 1433 356 11 18 61 266 2673
54 Tiruppullani 2235 830 122 107 1176 282 17 10 130 125 3567
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 290 ONGC.
55 Kalari 609 422 90 23 74 237 3 227 0 7 632
56 Utrakosamangai 842 496 33 16 297 248 1 238 0 9 994
57 Mallal 562 427 68 0 67 34 4 29 0 1 450
58 Alagankulam 653 405 131 12 105 32 6 11 1 14 488
59 Nalirukkai 604 245 285 0 74 9 2 7 0 0 457
60 Panaydiyendal 758 711 16 1 30 24 2 18 0 4 369
61 Valanur 783 356 286 3 138 475 4 416 2 53 1064
62 Kulapatham 582 9 496 7 70 142 2 137 1 2 723
63 Pallamerkkulam 489 112 3 34 340 463 47 356 2 58 1583
64 Kanjirangudi 1822 291 55 90 1386 102 3 61 4 34 3609
65 Keelakarai 755 135 66 26 528 181 45 73 31 32 1655
66 Manikkaneri 292 272 3 1 16 81 77 1 2 1 130
67 Pullandai 399 125 19 16 239 277 227 8 25 17 425
68 Mayakulam 1306 24 15 17 1250 213 1 8 2 202 4323
69 Ramanathapuram (M) 17603 98 45 237
17223 1135 11 22 57 1045 43312
70 Keelakarai (TP) 6916 40 14 207 6655 546 7 2 70 467 22950
71 Mandapam (TP) 4470 5 19 67 4379 262 4 12 27 219 11611
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 291 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 292 ONGC.
Annexure 4-A
Flora & Fauna
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 293 ONGC.
Checklist of Plant Species in Ramanathapuram ML Area
Sl No. Plant Species Local Distribution
A. Trees
1. Acacia eburnean Sporadic
2. Acacia nilotica Common
3. Acacia planifrons Sporadic
4. Syzygium cumuni Sporadic
5. Moginga oleifera Sporadic
6. Thespesia populnea Sporadic
7. Albizia lebbeck Common
8. Azadiracta indica Common
9. Borasus flabilifer Abundant
10. Buchannania axillaris Sporadic
11. Caesalpenia coriasia Sporadic
12. Casuarina equisetifolia Sporadic
13. Cocus nucifera* Abundant
14. Ficus benghalensis Sporadic
15. Ficus religiosa Sporadic
16. Merope angulata Sporadic
17. Pongamia glabra Common
18. Olax scandens Sporadic
19. Phoenix lourerii Common
20. Pithicellobium dulce Sporadic
21. Peltophorum pterocarpum Sporadic
22. Prosopis juliflora Abundant
23. Psidium guajava Sporadic
24. Odian wadia Sporadic
25. Tamarind sp. Common
26. Terminala catppa Sporadic
27. Siaminea saman Sporadic
28. Terminalia arjuna Sporadic
29. Ziziphus mauritiana Common
30. Ziziphus xylophyrus Common
B. Shrubs
31. Azima tetracantha Common
32. Cassia auriculata Common
33. Euphorbia tirucalli Sporadic
34. Hoya parasitica Sporadic
35. Jasminum angustifolium Sporadic
36. Jatropa sp Common
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 294 ONGC.
37. Lumnitzera racemosa Common
38. Manilkara hexandra Common
39. Opuntia monocanthus Sporadic
40. Tephrosia perpurea Common
C. Herbs and climbers
41. Allotropis cimicina Common
42. Aloe vera Sporadic
43. Aristida adscensiones Common
44. Aspargaus racemosus Common
45. Bulbostylis densa Common
46. Canavelia virosa Common
47. Capparis divaricata Common
48. Cassis obtusa Common
49. Catharanthus roseus Common
50. Chloris barbata Common
51. Cissus quandrangularis Common
52. Citronella sp. Common
53. Cleome aspera Common
54. Coccinia grandis Common
55. Crotolaria laburnifolia Common
56. Crotolaria verucosa Common
57. Cymbophogon gibarba Common
58. Cynadaon dactylon Common
59. Cyperus arenarius Common
60. Cyperus cartaneus Common
61. Cyperus rubicundus Common
62. Emilia scabra Common
63. Eragros unioloides Common
64. Eragrostis altrovirens Common
65. Hydrophylax maritime Common
66. Leucas maritinicensis Common
67. Lophopogon tridentatus Common
68. Rottboellia exaltata Common
69. Sporobolus diander Common
70. Veronica albicans Common
71. Vigna trilobata Common
[Source: SENES Primary Survey, September 2014 and Integrated Management Plan for the Gulf of
Mannar Marine National Park and Biosphere Reserve (2007-2016)]
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 295 ONGC.
Checklist of Birds in Study Area
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 296 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 297 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 298 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 299 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 300 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 301 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 302 ONGC.
[Source: Integrated Management Plan for the Gulf of Mannar Marine National Park and Biosphere
Reserve (2007-2016)]
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 303 ONGC.
Annexure 4-B
PhytoSociological Study
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 304 ONGC.
A. Flora
The study area (covering 22 oil wells) falls within the biogeographic province- 6E- Deccan
Peninsula- Deccan South (Rodgers, Panwar & Mathur, 2002). The Biogeographic province map
is presented in Figure as mentioned below:
Map showing Biogeographic Provinces of India
To analyse the Phytosociological significance of the study area, the survey was carried randomly
at 9 proposed oil well sites and its surrounding areas. The primary flora survey was conducted at
well nos- 1, 3, 6, 7, 11, 14, 17, 18, 22. The location of these sampling sites are indicated in the
Chapter 2 – Project Description. The phyto-sociological analysis was conducted for tree as well
ground cover species.
The major tree species recorded from these sites were Casuarina equisetifolia, Cocus nucifera,
Acacaia nilotica, Acacia eburnea, Pongamia glabra, Ficus benghalensis, Ficus religiosa,
Pithecellobium dulce, Borasus flabellifer, Peltophorum pterocarpum, Terminalia catappa,
Prosopis julflora etc.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 305 ONGC.
Methodology for Flora Study
Flora Survey
The Phytosociological analysis of the local vegetation (tree as well ground cover) was conducted
randomly in 9 well blocks within the proposed project site. Six transects at each well site were laid to
record the floral species. These plots were selected on the basis of similarity in vegetation
component. At each site a quadrat each of 10 m radius for tree species and 1 m radius for herbaceous
species were established to cover the survey. The Relative frequency, relative density, relative
abundance and Important Value Index (IVI) were computed from the primary survey.
Importance Value is a measure of how dominant a species is in a given forest area. It is a standard tool
used by foresters to inventory a forest/vegetation. Species diversity was also estimated as Shannon -
Weiner index following Shannon and Weaver (1963).
H = - SUM [(pi) × ln (pi)]
Where, “H” is the species diversity index; “S” the total number of species; “Pi” the proportion of total
sample belonging to ith species (i.e ni/N, n is the number of individuals of each species and N is the
number of individuals of all species).
Well no -1
From the analysis, it is found that, Cocus nucifera has the highest IVI index with 45.7 followed by
Casuarina equisetifolia 34.9 and Peltophorum pterocarpum 24.9, Borasus flabellifer 16.9 and
Thespesia populnea 16.8. Being near the coast, the species such as Cosus nucifera and Casuarina
equisetifolia is quite common and Peltophorum pterocarpum is considered as a most suitable fast
growing ornamental social forestry species. Borasus flabellifer is considered to be a most
commercial viable species of these area after Cocus nucifera and Casuarina equisetifolia.
The Shanon-Wiener Index (H) provides the status of how evenly the species are distributed as
wells as it gives clear picture of the abundance of the species in a particular community. The higher
“H” values states the more diverse communities. From the above analysis The Shanon-Wiener
Index (H) is found 2.5. The “H” value indicates the area is not well diversified.
As far as the ground cover is concerned, the grass/sedges were found to be more abundant and
dominant in comparison to other herbaceous species. Cyperus arenarius was having the highest
IVI with 36.6 followed by Cynodon dactylon 29.2, Aristida adscensiones 20.5. Cassia auriculata
was the most visible shrub of this study area. The “H” value was calculated 2.86 gives an
impression of less diversified ground cover.
Well No- 17
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 306 ONGC.
From the analysis, it is found that, Borasus flabilifer had the highest IVI value with 67.5 followed
by Peltophorum pterocarpum 34.2, Casuarina equisetifolia 30 and Thespesia populnea 28.6. The
“H” value was calculated as 2.42.
As far as the ground cover is concerned, the grass/sedges were also found to be more abundant
and dominant in comparison to other herbaceous species. Cynodon dactylon was having the IVI
value 49.6 followed by Cyperus arenarius 34.3, Sporobolus diander 29.8, Cassia auriculata 22.7.
The “H” value was calculated 2.1 which gives an impression that the ground cover was less
diversified.
Well Number 14
From the analysis, it is found that, Azadirachta indica had the highest IVI value with 70.5 followed
by Prosopis juliflora 65, Buchanania axillaris 32.5 and Thespesia populnea 31.9. In terms of
diversity the study area was found to be less diversified but the vegetation was dominated by
indigenous natural plant species like Azadirachta indica. The “H” value was calculated as 1.84
which was found to be one amongst the lowest diversified areas.
As far as the ground cover is concerned, Hydrophylax maritima had the highest IVI value with
58.9 followed by Cyperus arenarius 42, Cynodon dactylon 37.4 and Chloris barbata 31.2. The
“H” value was calculated 2.11 which once again gives an impression that the ground cover was
less diversified.
Well Number 7
From the analysis, it is found that, Casuarina equisetifolia had the highest IVI with 52.5 followed
by Borasus flabilifer 25.5. There were 24 plant species were recorded from the primary survey and
the diversity was recorded to be better in comparison to other sampled area. Other than Borasus
flabilifer the IVI of the rest of the plant species were recorded to be in range of 6.5 to 25.5. The
“H” value was calculated as 2.71.
As far as the ground cover is concerned, about 35 herbaceous species were recorded during the
primary flora survey. In terms of relative abundance, Cynodon dactylon was having the highest
percentage of 9.4 followed by Chloris barbata (5%). Cassia obtuse was recorded as having highest
IVI value with 21.2 followed by Cynodon dactylon 19, Chloris barbata 17.4 and Cyperus
arenarius 15.3. The “H” value was calculated 3.3 which found to be very well diversified.
Well Number 18
From the primary floral analysis in and around well block number -18, a mere 9 type of plant
species were recorded. Borasus flabilifer ws having the highest IVI value with 58.3 followed by
Thespesia populnea 39.2, Ziziphus mauritiana 36.5 and Azadirachta indica 35.6. The “H” value
was calculated as 2.07.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 307 ONGC.
About 15 species of herbs and shrubs were recorded during the primary floral survey. The Relative
frequency of Cissus quadrrangularis was recorded as 13.89 % followed by Emilia scabra, Chloris
barbata and Tephrosia purpurea with 11.11% each. Chloris barbata had the highest IVI value with
45.6 followed by Tephrosia purpurea 34.1, Cissus quadrangularis 33.3. The “H” value was
calculated 2.4.
Well Number 3
A meagre 6 species were recorded during the primary survey and the vegetative cover of the study
area was found to be highly degraded. Species such as Casuarina equisetifolia was the most
dominant species recorded from the survey followed by Borasus flabilifer. The rest of the species
were found scattered. The IVI of Casuarina equisetifolia was recorded as highest followed by
Borasus flabelifer 56.3, Terminalia catappa 37.8. The “H” value was calculated a poor 1.45.
About 7 species of herbs and shrubs were recorded during the primary floral survey. Cassia obtuse
was the most visible shrub of the area with IVI of 64, followed by Chloris barbata 53.9 and Cissus
quadrangularis 40.1. The “H” value was calculated 1.9.
Well Number 11
This oil well block and its surrounding areas was found to be most degraded site in comparison to
other sites. The tree species were found scattered and hence efforts were limited to analyse the
herbaceous ground cover to draw a conclusion on the vegetative cover of the site.
About 14 species were recorded during the primary survey. Cassia obtusa was the most dominating
species recorded from the floral survey. The other associated species were Cynodon dactylon,
Chloris barbata, Cyperus arenarius and Aristida adscensiones etc. Cassia obtusa was having the
highest IVI with 43 followed by Cynodon dactylon 37.8, Chloris barbata 35.1. The “H” value was
calculated 2.4.
Well no -22
Being located near the coast, Casuarina equisetifolia was the most dominant species recorded from
the flora survey. Borasus flabelifer was recorded the second highest dominant species and mostly
found towards inland. Casuarina equisetifolia was having the highest IVI with 84.7, followed by
Borasus flabelifer 41.9, Thespesia populnea 28.8 and Cocus nucifera 25.5. The Shanon-Wiener
Index (H) was calculated 1.95.
As far as the ground cover is concerned, the grass/sedges were found to be more abundant and
dominant in comparison to other herbaceous species. Cyperus arenarius was having the highest
IVI with 42.5 followed by Aristida adscensiones 36.3, Emilia scabra 26.1 and Eragrostis
altrovirens 25.4. The “H” value was calculated 2.5.
Well no -6
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 308 ONGC.
From the analysis, it is found that, Casuarina equisetiafolia was the most dominant species in and
around the proposed oil well block. It has the highest IVI value also. The IVI of Casuarina
equisetifolia was recorded 80.1, followed by Terminalia catappa 26.1 and Azadirachta indica
23.3. The Shanon-Wiener Index (H) was recorded as 2.18.
About 23 species of shrubs/herbs and grasses were recorded during the primary floral survey.
Cynodon dactylon was having the highest IVI with 32, followed by Cyperus arenarius 26.5,
Tephrosia purpurea 22.9, Aristida adscensiones 22.5. The “H” value was calculated 2.8.
From the above analysis, the diversity of species ws not impressive. A few dominant tree species
were almost exist in all theproposed oil well blocks. The most dominant as well as important tree
species were Casuarina equsetifolia, Borasus flabelifer, Azadirachta indica, and Cocus nucifera.
Among the herbaceous species Cassia obtusa, Cynodon dactylon, Cyperus arenarius, Chloris
barbata were the most dominant and frequently observed species.
Among the tree species, the Shanon-Wiener Index ranged between 1.45 to 2.71 and in case of
herbaceous species the “H” value ranged between 2.1 and 3.3.
TABLE 1 (A) Phytosociological Analysis of Tree species at Well Number 1
Name of the tree spp. RF RA RD IVI
Acacia eburnea 3.17 5.1 2.7 11.0
Acacia nilotica 6.35 3.2 3.4 12.9
Syzygium cumuni 3.17 2.6 1.3 7.1
Thespesia populnea 6.35 5.1 5.4 16.8
Azadiracta indica 4.76 5.1 4.0 13.9
Borasus flabilifer 3.17 7.7 6.0 16.9
Casuarina equisetifolia 4.76 14.7 15.4 34.9
Cocus nucifera 9.52 14.1 22.1 45.7
Ficus benghalensis 1.59 2.6 0.7 4.8
Ficus religiosa 4.76 2.6 2.0 9.3
Merope angulata 3.17 2.6 1.3 7.1
Pongamia glabra 6.35 3.2 3.4 12.9
Pithecellobium dulce 6.35 5.8 6.0 18.1
Peltophorum pterocarpum 9.52 6.0 9.4 24.9
Prosopis juliflora 4.76 5.1 4.0 13.9
Tamarindus indica. 3.17 5.1 2.7 11.0
Terminalia catappa 6.35 3.2 3.4 12.9
Samanea saman 6.35 2.6 2.7 11.6
Terminalia arjuna 6.35 3.8 4.0 14.2
H= 2.5
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 309 ONGC.
TABLE 1 (B) Phytosociological Analysis of the ground cover at Well Number 1
Name of Ephemeral spp RF RA RD IVI
Azima tetracantha 1.83 1.1 0.5 3.4
Cassia auriculata 5.50 3.3 4.3 13.1
Euphorbia tirucalli 1.83 2.6 1.1 5.5
Jatropa sp 3.67 4.5 3.8 11.9
Opuntia monocanthus 0.92 3.0 0.6 4.5
Tephrosia perpurea 4.59 4.9 5.2 14.7
Allotropis cimicina 1.83 4.8 2.1 8.7
Aristida adscensiones 4.59 7.7 8.2 20.5
Asparagus racemosus 2.75 3.0 1.9 7.6
Bulbostylis densa 2.75 2.5 1.6 6.8
Cassia obtusa 2.75 2.0 1.3 6.0
Catharanthus roseus 2.75 1.0 0.6 4.4
Chloris barbata 5.50 3.5 4.4 13.4
Cissus quandrangularis 3.67 1.9 1.6 7.1
Cleome aspera 3.67 2.0 1.7 7.5
Crotalaria laburnifolia 3.67 0.9 0.8 5.4
Cymbophogon gibarba 5.50 4.5 5.7 15.7
Cynodon dactylon 5.50 10.4 13.3 29.2
Cyperus arenarius 5.50 13.6 17.4 36.5
Emilia scabra 5.50 2.4 3.0 10.9
Eragrostis altrovirens 5.50 5.6 7.1 18.2
Leucas martinicensis 3.67 3.2 2.7 9.5
Lophopogon tridentatus 3.67 4.3 3.6 11.6
Rottboellia exaltata 5.50 2.7 3.5 11.7
Sporobolus diander 4.59 2.2 2.4 9.2
Veronica albicans 2.75 2.5 1.6 6.8
H= 2.86
Table 2 (A) Phytosociological Analysis of Tree species at Well Number 17
Name of the tree spp. RF RA RD IVI
Thespesia populnea 5.13 15.6 7.8 28.6
Albizia lebbeck 7.69 8.1 6.1 21.9
Borasus flabilifer 15.38 20.8 31.3 67.5
Casuarina equisetifolia 7.69 12.7 9.6 30.0
Cocus nucifera* 10.26 7.8 7.8 25.9
Pithicellobium dulce 12.82 6.9 8.7 28.5
Peltophorum pterocarpum 15.38 7.5 11.3 34.2
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 310 ONGC.
Name of the tree spp. RF RA RD IVI
Tamarindus indica. 7.69 5.8 4.3 17.8
Terminalia catappa 7.69 6.9 5.2 19.8
Samanea saman 10.26 7.8 7.8 25.9
H=2.42
Table 2 (B) Phytosociological Analysis of Ground cover species at Well Number 17
Name of the Ephemeral spp. RF RA RD IVI
Cassia auriculata 8.82 6.1 7.8 22.7
Euphorbia tirucalli 5.88 2.5 2.2 10.6
Jatropa sp 7.35 3.5 3.8 14.7
Opuntia monocanthus 1.47 5.1 1.1 7.6
Aristida adscensiones 4.41 9.3 5.9 19.6
Chloris barbata 4.41 6.7 4.3 15.5
Cissus quandrangularis 7.35 5.3 5.7 18.3
Cleome aspera 5.88 1.9 1.6 9.4
Crotalaria verucosa 7.35 3.0 3.2 13.6
Cynadon dactylon 8.82 17.9 22.9 49.6
Cyperus arenarius 8.82 11.2 14.3 34.3
Cyperus rubicundus 2.94 3.8 1.6 8.3
Emilia scabra 7.35 6.3 6.7 20.4
Eragrostis altrovirens 8.82 5.3 6.7 20.8
Leucas martinicensis 2.94 1.3 0.5 4.7
Sporobolus diander 7.35 10.9 11.6 29.8
H=2.1
Table 3 (A) Phytosociological Analysis of Tree species at Well Number 14
Name of the tree spp. RF RA RD IVI
Thespesia populnea 10.71 12.0 9.3 31.9
Azadirachta indica 17.86 23.0 29.6 70.5
Borasus flabilifer 7.14 8.4 4.3 19.8
Buchannania axillaris 14.29 9.0 9.3 32.5
Caesalpenia coriasia 10.71 9.6 7.4 27.7
Casuarina equisetifolia 10.71 8.8 6.8 26.3
Prosopis juliflora 17.86 20.6 26.5 65.0
Ziziphus xylopyrus 10.71 8.8 6.8 26.3
H=1.84
Table 3 (A) Phytosociological Analysis of Ground cover at Well Number 14
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 311 ONGC.
Name of the Ephemeral spp. RF RA RD IVI
Azima tetracantha 9.52 7.2 6.8 23.5
Tephrosia perpurea 9.52 8.3 7.9 25.7
Allotropis cimicina 7.14 5.2 3.7 16.0
Catharanthus roseus 9.52 7.2 6.8 23.5
Chloris barbata 11.90 8.9 10.5 31.2
Cleome aspera 11.90 7.5 8.9 28.3
Cynodon dactylon 4.76 22.1 10.5 37.4
Cyperus arenarius 14.29 11.4 16.2 42.0
Hydrophylax maritima 14.29 18.5 26.2 58.9
Vigna trilobata 7.14 3.7 2.6 13.5
H=2.11
Table 4 (A) Phytosociological Analysis of Tree species at Well Number 7
Name of the spp. RF RA RD IVI
Acacia eburnean 3.03 2.1 1.4 6.5
Acacia nilotica 3.03 4.3 2.8 10.0
Syzygium cumuni 3.03 2.1 1.4 6.5
Thespesia populnea 4.55 6.4 6.2 17.1
Albizia lebbeck 4.55 2.8 2.8 10.1
Azadiracta indica 7.58 3.0 4.8 15.4
Borasus flabilifer 4.55 10.6 10.3 25.5
Buchannania axillaris 6.06 2.1 2.8 10.9
Caesalpenia coriasia 4.55 2.1 2.1 8.7
Casuarina equisetifolia 6.06 20.2 26.2 52.5
Cocus nucifera* 6.06 3.7 4.8 14.6
Merope angulata 1.52 2.1 0.7 4.3
Pongamia glabra 1.52 2.1 0.7 4.3
Phoenix lourerii 3.03 2.1 1.4 6.5
Pithecellobium dulce 6.06 3.2 4.1 13.4
Peltophorum pterocarpum 3.03 3.2 2.1 8.3
Prosopis juliflora 4.55 3.5 3.4 11.5
Tamarindus indica. 6.06 2.1 2.8 10.9
Terminalia catappa 3.03 8.5 5.5 17.1
Samanea saman 4.55 4.3 4.1 12.9
Terminalia arjuna 4.55 2.8 2.8 10.1
Ziziphus mauritiana 6.06 4.3 5.5 15.8
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 312 ONGC.
Ziziphus xylopyrus 3.03 2.1 1.4 6.5
H=2.71
Table 4 (B) Phytosociological Analysis of Ground cover at Well Number 7
Name of the Ephemeral spp. RF RA RD IVI
Azima tetracantha 1.18 1.1 0.4 2.7
Cassia auriculata 2.35 1.1 0.9 4.3
Euphorbia tirucalli 2.35 1.1 0.9 4.3
Jasminum angustifolium 1.18 2.2 0.9 4.2
Jatropa sp 1.18 2.2 0.9 4.2
Opuntia monocanthus 1.18 1.1 0.4 2.7
Tephrosia perpurea 4.71 3.3 5.2 13.2
Allotropis cimicina 1.18 2.2 0.9 4.2
Aristida adscensiones 3.53 4.4 5.2 13.1
Aspargus racemosus 2.35 1.1 0.9 4.3
Bulbostylis densa 2.35 3.9 3.0 9.2
Canavalia virosa 3.53 2.9 3.4 9.9
Capparis divaricata 2.35 2.8 2.2 7.3
Cassia obtusa 7.06 4.2 9.9 21.2
Catharanthus roseus 3.53 3.7 4.3 11.5
Chloris barbata 4.71 5.0 7.8 17.4
Cissus quandrangularis 5.88 2.4 4.7 13.0
Cleome aspera 2.35 3.3 2.6 8.2
Crotalaria laburnifolia 3.53 1.5 1.7 6.7
Crotalaria verucosa 2.35 2.2 1.7 6.3
Cymbopogon gibarba 3.53 2.6 3.0 9.1
Cynadon dactylon 2.35 9.4 7.3 19.0
Cyperus arenarius 4.71 4.1 6.5 15.3
Cyperus cartaneus 1.18 2.2 0.9 4.2
Cyperus rubicundus 1.18 2.2 0.9 4.2
Emilia scabra 4.71 1.9 3.0 9.6
Eragros unioloides 2.35 2.8 2.2 7.3
Eragrostis altrovirens 3.53 3.3 2.6 9.4
Hydrophylax maritima 2.35 2.8 2.2 7.3
Leucas martinicensis 2.35 1.1 0.9 4.3
Lophopogon tridentatus 2.35 3.9 3.0 9.2
Rottboellia exaltata 2.35 2.8 2.2 7.3
Sporobolus diander 3.53 2.9 3.4 9.9
Veronica albicans 1.18 4.4 1.7 7.3
Vigna trilobata 3.53 2.2 2.6 8.3
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 313 ONGC.
H= 3.3
Table 5 (A) Phytosociological Analysis of Tree species at Well Number 14
Name of the spp. RF RA RD IVI
Thespesia populnea 10.71 14.2 14.3 39.2
Albizia lebbeck 10.71 6.3 6.3 23.4
Azadirachta indica 17.86 6.6 11.1 35.6
Borasus flabilifer 10.71 23.7 23.8 58.3
Terminalia catappa 7.14 19.0 12.7 38.8
Samanea saman 10.71 9.5 9.5 29.7
Terminalia arjuna 10.71 6.3 6.3 23.4
Ziziphus mauritiana 14.29 9.5 12.7 36.5
Ziziphus xylopyrus 7.14 4.7 3.2 15.1
H=2.07
Table 5 (B) Phytosociological Analysis of Ground cover at Well Number 14
Name of the Ephemeral spp. RF RA RD IVI
Jatropa sp 2.78 5.9 2.4 11.1
Opuntia monocanthus 2.78 3.0 1.2 6.9
Tephrosia perpurea 11.11 8.9 14.1 34.1
Allotropis cimicina 2.78 5.9 2.4 11.1
Chloris barbata 11.11 13.3 21.2 45.6
Cissus quandrangularis 13.89 6.5 12.9 33.3
Cleome aspera 5.56 8.9 7.1 21.5
Crotalaria laburnifolia 8.33 3.9 4.7 17.0
Cyperus cartaneus 2.78 5.9 2.4 11.1
Cyperus rubicundus 2.78 5.9 2.4 11.1
Emilia scabra 11.11 5.2 8.2 24.5
Eragros unioloides 5.56 7.4 5.9 18.8
Eragrostis altrovirens 8.33 8.9 7.1 24.3
Hydrophylax maritima 5.56 7.4 5.9 18.8
Leucas martinicensis 5.56 3.0 2.4 10.9
H=2.4
Table 6 (A) Phytosociological Analysis of Tree species at Well Number 3
Name of the tree spp. RF RA RD IVI
Borasus flabilifer 15.00 21.8 19.5 56.3
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 314 ONGC.
Casuarina equisetifolia 20.00 41.5 49.4 110.8
Cocus nucifera 20.00 7.6 9.1 36.7
Prosopis juliflora 15.00 7.3 6.5 28.8
Tamarindus indica 20.00 4.4 5.2 29.6
Terminalia catappa 10.00 17.5 10.4 37.8
H=1.45
Table 6 (B) Phytosociological Analysis of Tree species at Well Number 3
Name of the spp. RF RA RD IVI
Cassia obtusa 22.22 16.5 25.3 64.0
Catharanthus roseus 11.11 14.3 11.0 36.4
Chloris barbata 14.81 19.3 19.8 53.9
Cissus quandrangularis 18.52 9.4 12.1 40.1
Cleome aspera 7.41 12.9 6.6 26.9
Cyperus arenarius 14.81 16.1 16.5 47.4
Sporobolus diander 11.11 11.5 8.8 31.4
H=1.9
Table 7 Phytosociological Analysis of Ground cover at Well Number 11
Name of the Ephemeral spp. RF RA RD IVI
Aristida adscensiones 8.11 8.9 9.5 26.5
Aspargus racemosus 5.41 2.2 1.6 9.2
Bulbostylis densa 5.41 7.8 5.6 18.7
Canavalia virosa 8.11 5.9 6.3 20.4
Capparis divaricata 5.41 5.5 4.0 14.9
Cassia obtusa 16.22 8.5 18.3 43.0
Chloris barbata 10.81 10.0 14.3 35.1
Cleome aspera 5.41 6.7 4.8 16.8
Crotalaria laburnifolia 8.11 3.0 3.2 14.2
Cynodon dactylon 5.41 18.9 13.5 37.8
Cyperus arenarius 10.81 8.3 11.9 31.0
Cyperus cartaneus 2.70 4.4 1.6 8.7
Cyperus rubicundus 2.70 4.4 1.6 8.7
Hydrophylax maritima 5.41 5.5 4.0 14.9
H= 2.4
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 315 ONGC.
Table 8 (A) Phytosociological Analysis of Tree species at Well Number 22
Name of the tree spp. RF RA RD IVI
Acacia nilotica 6.06 6.8 4.3 17.1
Syzygium cumuni 6.06 3.4 2.1 11.6
Thespesia populnea 9.09 10.1 9.6 28.8
Albizia lebbeck 9.09 4.5 4.3 17.9
Borasus flabilifer 9.09 16.9 16.0 41.9
Caesalpenia coriasia 9.09 3.4 3.2 15.7
Casuarina equisetifolia 12.12 32.1 40.4 84.7
Cocus nucifera 12.12 5.9 7.4 25.5
Pongamia glabra 3.03 3.4 1.1 7.5
Phoenix lourerii 6.06 3.4 2.1 11.6
Pitheellobium dulce 12.12 5.1 6.4 23.6
Peltophorum pterocarpum 6.06 5.1 3.2 14.3
H=1.95
Table 8 (B) Phytosociological Analysis of Ground cover at Well Number 22
Name of the Ephemeral spp. RF RA RD IVI
Azima tetracantha 2.94 2.9 1.3 7.1
Cassia auriculata 5.88 2.9 2.7 11.4
Euphorbia tirucalli 5.88 2.9 2.7 11.4
Jasminum angustifolium 2.94 5.7 2.7 11.3
Jatropa sp 2.94 5.7 2.7 11.3
Opuntia monocanthus 2.94 2.9 1.3 7.1
Allotropis cimicina 2.94 5.7 2.7 11.3
Aristida adscensiones 8.82 11.5 16.0 36.3
Cymbopogon gibarba 8.82 6.7 9.3 24.9
Cyperus arenarius 11.76 10.8 20.0 42.5
Cyperus cartaneus 2.94 5.7 2.7 11.3
Cyperus rubicundus 2.94 5.7 2.7 11.3
Emilia scabra 11.76 5.0 9.3 26.1
Eragros unioloides 5.88 7.2 6.7 19.7
Eragrostis altrovirens 8.82 8.6 8.0 25.4
Hydrophylax maritima 5.88 7.2 6.7 19.7
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 316 ONGC.
Leucas martinicensis 5.88 2.9 2.7 11.4
H=2.5
Table 9 (A) Phytosociological Analysis of Tree species at Well Number 6
Name of the tree spp. RF RA RD IVI
Albizia lebbeck 6.82 4.4 4.2 15.4
Azadirachta indica 11.36 4.6 7.3 23.3
Buchannania axillaris 9.09 3.3 4.2 16.6
Caesalpenia coriasia 6.82 3.3 3.1 13.3
Casuarina equisetifolia 9.09 31.4 39.6 80.1
Merope angulata 2.27 3.3 1.0 6.6
Pongamia glabra 2.27 3.3 1.0 6.6
Pithecellobium dulce 9.09 5.0 6.3 20.3
Peltophorum pterocarpum 4.55 5.0 3.1 12.6
Prosopis juliflora 6.82 5.5 5.2 17.5
Tamarindus indica. 9.09 3.3 4.2 16.6
Terminalia catappa 4.55 13.2 8.3 26.1
Samanea saman 6.82 6.6 6.3 19.7
Terminalia arjuna 6.82 4.4 4.2 15.4
Ziziphus xylopyrus 4.55 3.3 2.1 9.9
H= 2.18
Table 9 (B) Phytosociological Analysis of Ground cover at Well Number 6
Name of the Ephemeral spp. RF RA RD IVI
Azima tetracantha 2.08 1.7 0.8 4.6
Cassia auriculata 4.17 1.7 1.6 7.4
Euphorbia tirucalli 4.17 1.7 1.6 7.4
Jasminum angustifolium 2.08 3.4 1.6 7.1
Jatropa sp 2.08 3.4 1.6 7.1
Opuntia monocanthus 2.08 1.7 0.8 4.6
Tephrosia perpurea 8.33 5.1 9.4 22.9
Allotropis cimicina 2.08 3.4 1.6 7.1
Aristida adscensiones 6.25 6.8 9.4 22.5
Cynadon dactylon 4.17 14.5 13.4 32.0
Cyperus arenarius 8.33 6.4 11.8 26.5
Cyperus cartaneus 2.08 3.4 1.6 7.1
Cyperus rubicundus 2.08 3.4 1.6 7.1
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 317 ONGC.
Name of the Ephemeral spp. RF RA RD IVI
Emilia scabra 8.33 3.0 5.5 16.8
Eragros unioloides 4.17 4.3 3.9 12.4
Eragrostis altrovirens 6.25 5.1 4.7 16.1
Hydrophylax maritima 4.17 4.3 3.9 12.4
Leucas martinicensis 4.17 1.7 1.6 7.4
Lophopogon tridentatus 4.17 6.0 5.5 15.6
Rottboellia exaltata 4.17 4.3 3.9 12.4
Sporobolus diander 6.25 4.5 6.3 17.1
Veronica albicans 2.08 6.8 3.1 12.1
Vigna trilobata 6.25 3.4 4.7 14.4
H=2.8
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 318 ONGC.
Annexure-5
PUBLIC HEARING NOTICE
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 319 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 320 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 321 ONGC.
Annexure-6
PUBLIC HEARING MINUTES OF MEETING
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 322 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 323 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 324 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 325 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 326 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 327 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 328 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 329 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 330 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 331 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 332 ONGC.
Minutes of the Public Hearing Conducted on 14.05.2015 at 10.30 AM at the Auditorium, District
Collectorate, Ramanathapuram District, for the project of proposed 22 numbers of exploratory
wells(Natural gas) by M/s. ONGC Limited in 21 Villages of Ramanathapuram Taluk and
Keelakarai Taluk of Ramanathapuram District
The District Collector, Ramathapuram District, has welcomed the gathering and requested M/s
ONGC Ltd., to give a presentation on the project.
The General Manager, ONGC Ltd., has given presentation about the project on Planning,
Execution, Environmental Impacts and Environment Management plan to the Public.
Then, the District Collector, Ramanathapuram District has requested the public to come and record
their views one by one. Accordingly the public have expressed their views as stated below.
S. No Issues Raised in Public Hearing Response of Project Proponent
1. Thiru. Karthick, Pamban Village President
Thiru.Karthick told that the Gulf of Mannar has 21
Islands and it is the place for Bio-diversity. Due to
this project there will be a threat for Gulf of
Mannar and its Bio-diversity. Also fisher men
region of Ervadi and Keelakarai may get affected
due to the proposed wells at Reghunathapuram
and Periyapattinam. He expressed his protest
against this proposed project in view of the above
said Environmental impacts.
Proposed wells are falling in buffer
zone of 10 Km from the coast line,
considering the Marine bio-reserve of
Gulf of Mannar. Wild life management
report has been submitted to wild life
warden and exploration shall be taken
up after getting EC, which shall be
given only after considering the wild
life clearance.
Exploratory drilling proposed is for
onshore, and is of temporary nature,
hence it will not affect the fishing
industry.
2. Thiru.Kalidass,Secretary,Rotary,
Ramanathapuram
Thiru .Kalidass told that this proposed project may
give threat to the normal life of the public. Even
though, there are natural gas wells located in
Ramanathapuram District already, it is of no use
Proposed drilling shall not affect day to
day life of the people as the locations
are normally chosen in places away
from residences and human activity.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 333 ONGC.
to the public of Ramanathapuram. He also told that
if the proposed 22 wells are drilled, agriculture
lands will become dry lands. Hence, he requested
to record his protest against to the project.
Gas from wells is used for power
generation. If gas is found and
commercially viable, this gas shall be
used for setting up of power plants or
other industries
After drilling wells if oil or gas is
found only those area will be acquired
on lease and development shall be
taken up after obtaining permission
from MoEF again. Those wells which
are dry shall be restored to near
original condition and shall be returned
to owners to continue with agriculture.
Hence agricultural lands will not
become dry lands.
3. Thiru.Kanianbu,FishermenRepresentative,
Rameshwaram.
Thiru.Kanianbu told that M/s ONGC Ltd, has not
done any goodwill to the public of
Ramanathapuram District. If this proposed project
be executed, impacts on the Environment and
Public will get increased. He requested to cancel
the project in view of Environmental Protection
For the Ramanathapuram District,
ONGC in the last four years has spent
for CSR Activities as under :
Year In Rupees
2014-2015 80,75,742 2013-2014 34,70,810 2012-2013 66,55,149
2011-2012 49,25,100
EIA study and the mitigation measures
has already been studied and report
submitted to TNPCB and shall be
submitted to MoEF also. After
examining the proposal and EIA report
MoEF may issue Environment
Clearance. Exploration shall take place
only after obtaining EC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 334 ONGC.
4. Thiru. Muhilan, TamilNadu Environment
Protection Group.
Thiru.Muhilan told that the public hearing is being
conducted without much participation of public
from the villages, where the wells are proposed.
He informed that the executive summary of the
project did not mention the names of the villages
where the wells are proposed. He requested the
District Collector to re-organize the public hearing
at each and every village separately. He also
expressed that Gulf of Mannar and Bird
Sanctuaries are located within 10 KiloMeters from
the project area which are not taken into
consideration.
Press notice for Public hearing on
14.05.15 for the proposed exploration
project, comprising of exploratory
drilling in 22 locations in Ramnad
district was given by TNPCB in “The
Indian Express” and “Dinamani “on
10.04.15.Besides as per their procedure,
this has been uploaded in their website
and it was mentioned in the press
notification that the EIA report and
executive summary were available for
reference in other Govt. offices like
Office of the district collector,
Ramanathapuram, Office of the Asst.
director(Panchayat), Ramanathapuam,
District Industries
Centre(DIC),Ramanathapuram, Office
of District Environment Engineer,
Sivagangai, Office of the
Commissioner/BDO, Ramanathapuram
Panchayat Union, Thirupullani
Panchayat Union, Thiruvadadana i
Panchayat Union in Ramanathapuram
District, Corporate Office, TNPCB,
Chennai, Office of the secretary to
Government, Environment and Forest
Department, Chennai and Ministry of
environment and Forest, New Delhi.
Subsequent to press notificat ion,
District Environment Engineer TNPCB
has sent the copies of Executive
summary, in local language, of the
proposed project to all the Panchayat
presidents of the villages falling in the
proposed 22 locations. Besides in every
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 335 ONGC.
panchayat office, TNPCB also
displayed a banner mentioning the
above Public Hearing details.
Proposed wells are falling in buffer
zone of 10 Km from the coast line,
considering the Marine bio-reserve of
Gulf of Mannar.
Wild life management report has been
submitted to wild life warden and
exploration shall be taken up after
getting EC, which shall be given only
after considering the wild life clearance.
5. Thiru.Pudhurnalar Prabhakaran, Maravan
Sena Organisation, Ramanathapuram
Thiru.Pudhumalar Prabhakaran told that this
project should not in Ramanathapuram District,
since the ground water level has gone down to 200
feet and below. When the natural gas is pumped
out, seawater intrusion may occur and hence the
ground water will become more saline.
Exploration activities are in zones
beyond 2000 metres, which is much
below the ground water table.
Exploration activities do not cause salt
water intrusions into the ground water.
6. Thiru.M.Madasamy, Puthiya Thamilagam,
Ramanathapuram
Thiru.Madasamy told that before selecting the
drilling points of the wells, the views of the public
of the villages should have been obtained. The
agriculture lands for a radius of 25Km will get
affected if a well is drilled which will affect the
normal life of the public. Further toxic substances
will come out of the well and will affect the public
health. This proposed natural gas wells may lead
to coal bed methane project. Hence, he wanted to
register his protests against the project.
Public Hearing conducted to obtain the
views of the public. Only 4 to 5 acres
of land shall be obtained on lease for
exploration activity. Land acquired
shall be within 0.13KM Radius of
drilling location.
After drilling wells if oil or gas is
found only those area will be acquired
on lease and development shall be
taken up after obtaining permission
from MoEF again. Those wells which
are dry shall be restored to near
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 336 ONGC.
original condition and shall be returned
to owners to continue with agriculture.
Proposed drilling shall not affect day to
day life of the people as the locations
are normally chosen in places away
from residences and human activity
No toxic substances are generated from
well and hence will not affect public
health
This proposal is only to explore oil and
natural gas from these wells and shall
not lead to coal bed methane
exploration.
7. Thiru Murugan, Advocate, Tamil National
People Front, Ramanathapuram.
Thiru Murugan told that the mineral resources in
the soil of District will get spoiled due to the
proposed natural gas well project., leading to
reduction in fertility of the soil.He also requested
the District Collector not to recommend this
project for environmental clearance.
Oil exploration activity in no way
spoils the mineral resources of the area,
nor the fertility of the soil.
8. Thiru Manikumar, Valantharavai village .
Thiru Manikumar told that already. ONGC has
established its gas collection center at
Valantharavai Village and hence agriculture has
vanished in this village. If ONGC established
another setup here, the public of valantharaya i
village has to move out for their livelihood. ONGC
has not given job opportunities to the local public
and due to the power plants, the public lost their
peacefullness due to noise pollution
ONGC has leased/ acquired land 22
acres (aaprox.) for GCS installation.
Except this area Agricultural activity,
can be done in other areas
If commercial viability is established
from the exploration activities , ONGC
may augment the existing facilities
only, hence loss of livelihood is not
there.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 337 ONGC.
Local labour isgiven preference in
temporary jobs by contractors during
the construction activities.
ONGC does not have any power plants
in this area.
9. Thiru. Javarullah, Environment Activists,
Madurai.
Thiru Javarullah told that, already ground water
was contaminated due to aquaculture units in
Ramanathapuram District. If this project comes up
the total water resources of this district will be
contaminated and hence he requested the District
Collector to take decision as per the opinion the
public of Ramanathapuram.
Exploration activities are in zones
beyond 2000 metres, which is much
below the ground water table.
Exploration activities do not
contaminate water resources of the
district
10. Thiru Appu Sulthan, Secretary, Tamilnadu
Mslim Munnetra Kalakam, Ramanathapuram
Thiru Appu Sulthan told that both Central and
State Government bringing such projects to this
district which are of no use to the the CSR works
done by ONGC are not satisfied. The lands of poor
are being takenaway by such projects. Hence he
requested the District Collector not to give
permission to this project.
ONGC is paying royalty/licence fee to
the state government, and these funds
are used for development purposes by
the state. In addition ancilliary
industries /businesse develop if oil and
gas reserves are established creating
employment opportunities for the local
public.
For the Ramanathapuram District,
ONGC in the last four years has spent
for CSR Activities as under :
Year In Rupees
2014-2015 80,75,742
2013-2014 34,70,810 2012-2013 66,55,149
2011-2012 49,25,100
Around 4.5 acres of land will be
acquired on lease for exploratory
activity. Compensation and lease rent
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 338 ONGC.
shall be paid as per norms decided by
Revenue authorities.
Those wells which are dry shall be
restored to near original condition and
shall be returned to owners to continue
with agriculture
11. Thiru Ramesh Karuppaya, Environmenta l
Activists, Cuddalur..
Thiru Ramesh Karuppaya told that ONGC has
obtained Petroleum Mining Lease for 493 Sq.km.
ONGC has proposed 22 natural gas wells. This is
only a starting and if this project comes, ONGC
will extend its operations all through the
Ramanathapuram District. This will result in
degradation of natural resources. He has also told
that there arc more than 3600 species in Gulf of
Mannar, which are in danger due to such projects.
No additional wells shall be taken up for
exploration unless a permission form
MoEF is obtained again.
Even in case if oil and gas found in the
proposed exploratory wells the
exploitation shall be carried out only
after obtaining EC for development
activities.
Proposed wells are falling in buffer
zone of 10 Km from the coast line,
considering the Marine bio-reserve of
Gulf of Mannar.
Wild life management report has been
submitted to wild life warden and
exploration shall be taken up after
getting EC, which shall be given only
after considering the wild life clearance.
12. Thiru Chinnathampi, All India Forward
Black, Ramanathappuram.
Thiru Chinnathampi has expressed that rare
species of (hilt' of Mannar will get affected due to
this project and hence he requested the District.
Collector not to permit this project.
Proposed wells are falling in buffer
zone of 10 Km from the coast line,
considering the Marine bio-reserve of
Gulf of Mannar.
Wild life management report has been
submitted to wild life warden and
exploration shall be taken up after
getting EC, which shall be given only
after considering the wild life clearance.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 339 ONGC.
13. Thiru Dhinesh Kumar, Joint Secretary
MDMK, Ramanathapuram
Thiru Dhinesh Kumar told that already people of
Valantharavai village has given their agriculture
lands to ONGC. However in town ONGC has not
done anything to the public of Valantharava i
village so far. Similarly ONGC will not do any
goodwill to the public of Ramanathapuram
District.
ONGC has leased/ acquired land of
….. sq.m /acres for GCS installation.
Except this area Agricultural activity,
can be done in other areas
Following are the activites taken up in
village Valantahravai………
Govt.High School 2.25 lakhs
President, Pannaikulam 1.00 lakhs
Grama Panchayat,
Valantharavai,.
Panchayat President, 4.00 lakhs
Valantharavai Panchayat,
Valantharavai,
Valantharavai, 1.60 lakhs
Panchayat President
For the Ramanathapuram District,
ONGC in the last four years has spent
for CSR Activities as under :
Year In Rupees
2014-2015 80,75,742 2013-2014 34,70,810 2012-2013 66,55,149
2011-2012 49,25,100
14. Thiru Vinoth Kumar, Secretary Tamilnadu
Valvurimai party
Thiru Vinoth Kumar has condemned the Central
Government for permitting ONGC to dig 22
natural gas wells in Raman.athaptirani District. He
No natural resources are taken away by
ONGC. Oil & gas if found shall be used
for the development activities for
state/country
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 340 ONGC.
expressed that ONGC should not take away the
natural resources of Tamilnadu.
15. Thiru Raju, Valenokkam,Naam Tamilar Party
Thiru Raju told that the public hearing is
conducted without proper intimation to the public
of Ramanathapuram. He expressed that his party
will not allow any project which will affect the
environment.
Press notice for Public hearing on
14.05.15 for the proposed exploration
project, comprising of exploratory
drilling in 22 locations in Ramnad
district was given by TNPCB in “The
Indian Express” and “Dinamani “on
10.04.15.Besides as per their procedure,
this has been uploaded in their website
and it was mentioned in the press
notification that the EIA report and
executive summary were available for
reference in other Govt. offices like
Office of the district collector,
Ramanathapuram, Office of the Asst.
director (Panchayat), Ramanathapuam,
District Industries
Centre(DIC),Ramanathapuram, Office
of District Environment Engineer,
Sivagangai, Office of the
Commissioner/BDO, Ramanathapuram
Panchayat Union, Thirupullani
Panchayat Union, Thiruvadadana i
Panchayat Union in Ramanathapuram
District, Corporate Office, TNPCB,
Chennai, Office of the secretary to
Government, Environment and Forest
Department, Chennai and Ministry of
environment and Forest, New Delhi.
Subsequent to press notificat ion,
District Environment Engineer TNPCB
has sent the copies of Executive
summary, in local language, of the
proposed project to all the Panchayat
presidents of the villages falling in the
proposed 22 locations. Besides in every
panchayat office, TNPCB also
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 341 ONGC.
displayed a banner mentioning the
above Public Hearing details.
16. Thiru Tamil Doss, Social Worker Madurai.
Thiru. Tamil Doss told more agriculture lands
will be acquired by the ONGC for its pipe line
conveyance. This will economically affect the
agriculturalists. Further he told that the CSR works
done by the ONGC are not satisfied.
This project is only an exploratory
phase. If commercial viability is
established, sustainable development
shall be made.
Pipelines shall be laid only when EC is
accorded for the project and land shall
be acquired after obtaining the consent
of the people affected, after paying
necessary compensation as fixed by
revenue authorities
For the Ramanathapuram District,
ONGC in the last four years has spent
for CSR Activities as under :
Year In Rupees
2014-2015 80,75,742 2013-2014 34,70,810 2012-2013 66,55,149
2011-2012 49,25,100
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 342 ONGC.
Annexure-6
Application of Wild Life Clearance
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 343 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 344 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 345 ONGC.
Annexure-7
NABET CERTIFICATE
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 346 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 347 ONGC.
EIA for exploration of hydrocarbons at Ramanathapuram PML Block
SENES/H-20084/ July 2016 348 ONGC.