Environmental Impact Assessment andEnvironmental Management Plan
(FINAL EIA/EMP REPORT)
Of
Proposed project for Manufacturing of Billets/Ingots
@ 2, 22,000TPA
For
M/s SAI INDUCTOMELT PRIVATE LIMITED
Survey no: 1020& 1021/1,Bhavnagar - Vallabhipur Highway,Village:Chamardi, Taluka: Vallabhipur, District: Bhavnagar
By:
Pollution and Ecology Control Services
Near Dhantoli Police Station, Dhantoli, Nagpur-12.
NABET No. 119
CONTENTS
Sr. No. Particulars Page No.
CHAPTER 1: INTRODUCTION 1-10
1.1 Preamble 1
1.2 Purpose of the Study 1
1.3 Identification Of Project & Project Proponent 2
1.4 Site Selection Criteria 2
1.5 Details of Project Site 3
1.6 Project Importance To The Country And/ Or Region 6
1.6.1 Steel Production in India 7
1.6.1 Steel Billet Industry 7
1.7 Need for the Project 8
1.8 Applicable Environmental Regulatory Framework 8
1.9 Scope Of The Study 9
1.10 EIA/EMP Report Scheme 9
CHAPTER2: THE PROJECT DESCRIPTION 11-24
2.1 Need of the Project and Magnitude of Operation 11
2.2 Plant Layout 11
2.3 Size or Magnitude of Operation 13
2.3.1 Raw Material Requirement 13
2.3.1.1 Characteristics of MS scraps 14
2.3.1.2 Proposed Infrastructure Facility 15
2.3.2 Water requirement & Waste Water Generation 16
2.3.3 Power Requirement 17
2.3.4 Man-Power Requirement 18
2.3.5 Land Requirement 18
2.3.6 Capital project cost projection 18
2.4 Proposed Schedule for Approval and Implementation 19
2.5 Technology and Project Description 19
2.6 Mitigation Measures 21
2.6.1 Air Pollution 21
2.6.2 Water Pollution 22
2.6.3 Noise Pollution 22
2.6.4 Solid waste Management 22
2.6.5 Green belt Development 22
2.6.6 Transportation 23
2.6.7 Fire Protection System 23
2.6.8 Occupational Health and Safety 23
2.7 Assessment of New & Untested Technology for the Risk ofTechnology Failure
24
CHAPTER 3: BASELINE ENVIRONMENTAL STATUS 25-66
3.0 Baseline Environmental Status 25
3.1 Methodology 26
3.2 Micrometeorology 27
3.3 Air Quality 30
3.3.1 Ambient Air Quality Monitoring 30
3.3.2 AAQ Monitoring Stations and Observation 32
3.4 Water Environment 37
3.5 Noise Environment 46
3.6 Soil Quality 49
3.7 Land Use Pattern 54
3.8 Socio-Economics of the Study Area 58
CHAPTER 4: ANTICIPATED ENVIRONMENTAL IMPACTS AND
MITIGATION MEASURES
67-83
4.1 Identification of Impacts 67
4.1.1 Issues Scoping / Pathway Analysis - Summary of MatrixValued Ecosystem Components of Concerns (VECs)
68
4.2 Construction Phase 69
4.3 Operation Phase 72
4.3.1 Impact on Air Quality 72
4.3.1.1 Prediction of Air quality 73
4.3.2 Noise Levels 79
4.3.3 Impact on Water 80
4. 3.4 Solid Waste Generation 81
4.3.5 Impact on Socio-Economic Environment 82
4.3.6 Prediction of Impacts on Occupational Health 82
4.3.7 Prediction of Impacts on Flora and Fauna 82
CHAPTER 5: ANALYSIS OF ALTERNATIVES FOR TECHNOLOGY AND
SITE
84-85
5.1 Alternate Technology 84
5.1.1 Details of Alternative Site Considered 85
CHAPTER 6: ENVIRONMENTAL MONITORING PROGRAM 86-88
6.1 Introduction 86
6.2 Environmental Monitoring Program 86
6.3 Budget Allocation for Environmental Monitoring 87
CHAPTER 7: ADDITIONAL STUDIES 89-116
7.0 Social Impact Assessment 89
7.1 Risk Assessment 89
7.1.1 Approaches to the Study 89
7.1.2 Hazards Identification 90
7.1.3 Occupational health impacts on the workers 93
7.1.4 Do’s & Don’ts of preventive maintenance 97
7.1.5 Personal Protective Equipment and Periodic Medical
Examination
99
7.2 Disaster Management Plan 100
7.2.1 On-Site Emergency Plan 102
7.2.2 Disaster Management Plan for Sai Inductomelt Pvt Ltd. 113
CHAPTER 8: PROJECT BENEFITS 117-120
8.1 Improvement in the Physical Infrastructure 117
8.2 Employment Potential 117
8.3 Improvement in Infrastructure 118
8.4 Education 118
8.5 Green Belt Development 119
8.6 Social Infrastructure 119
8.7 Other Tangible Benefits 119
8.8 Corporate Environment Responsibility Plan (Cer) 120
CHAPTER 9: ENVIRONMENTAL COST BENEFIT ANALYSIS 121
CHAPTER 10: ENVIRONMENT MANAGEMENT PLAN 122-133
10.0 Introduction 122
10.1 Purpose of Environmental Management Plan 122
10.2 Overview of the Pollution Control Management 123
10.2.1 Construction Phase 123
10.2.2 Operation Phase 125
10.3 Environment Management Policy & Environment Committee 131
CHAPTER 11: SUMMARY AND CONCLUSION 134-145
11.1 Project Description 134
11.1.1 Introduction 134
11.1.2 Project Location & Environment Sensitivity 134
11.1.3 Size or Magnitude of Operation 135
11.2 Description of Environment 136
11.3 Anticipated Environmental Impacts & Mitigation Measures 137
11.4 Environment Monitoring Programme 138
11.5 Environment Management Plan 139
11.6 Conclusion 145
CHAPTER 12: DISCLOSURE OF CONSULTANTS 146-149
LIST OF TABLES
Sr. No. Particulars Page No.
1.1 Details of Project Site (10 Km Radius) 3
2.1 Production Details 11
2.2 Land Distribution Details 13
2.3 Annual Raw Material Requirement 14
2.4 Material Balance 14
2.5 Plant Infrastructure 15
2.6 Water Requirements and Waste Water Generation 16
2.7 Energy Balance 17
2.8 Project Cost Projection 18
3.1 Onsite Meteorological Data (Period: October to December 2018) 28
3.2 Methodology of Ambient Air Quality Monitoring 32
3.3 Ambient Air Quality Monitoring Sampling Stations 33
3.4 Summarized Report of Ambient Air Quality 34
3.5 National Ambient Air Quality Standards 35
3.6 Water Sampling Location 37
3.7 Methodology for Sampling and Analysis of Water 38
3.8 Water Quality: Surface Water Samples 42
3.9 Water Quality: Ground Water Samples 44
3.10 Noise Level Sampling Stations 46
3.11 Measured Noise Levels at Monitored Stations 48
3.12 National Ambient Noise Level Standards 49
3.13 Analytical methodology for soil samples 50
3.14 Soil Sample Monitoring Station 50
3.15 Physio-Chemical Properties of Soil 52
3.16 Standard Soil Classification 53
3.17 Land use/Land Cover Analysis 57
3.18 Village wise Demographic Structure of the Study Area 63
3.19 Employment Pattern 65
4.1 Stacks & Emissions Details 73
4.2 Predicted 24 hourly Ground Level Incremental Concentrations 75
4.3 Resultant PM10 at Monitoring Locations, µg/m3 77
4.4 Estimation of Transportation of the Raw Material 78
4.5 Water Requirement and Waste Water Generation 81
4.6 Solid Waste Generation & Mitigation Measures 81
6.1 Proposed Environmental Monitoring Schedules 87
6.2 Proposed Budget for Environmental Monitoring Programme 88
LIST OF FIGURE
Sr. No. Particulars Page No.
1.1 Location Map of the Proposed Project Site 4
1.2 Topographical Map of Study Area (10 Km Radius) 5
1.3 Satellite Image of the Site 6
2.1 Plant layout 12
2.2 Water balance Flow Chart 17
2.3 Process Flow Chart of the Manufacturing Billets 21
3.1 Satellite Image of Project site showing 10 km study area 25
3.2 Windrose Diagram during study period (October –December 2018) 29
3.3 Ambient Air Quality Sampling Station 33
3.4 Map showing Ground and surface water sampling 38
3.5 Map showing Noise level Monitoring Station 47
3.6 Location of Soil sampling Stations 51
3.7 Satellite Imagery 56
3.8 Land Use/Land Cover map 57
3.9 Sex Ratio Comparison 60
3.10 Breakup of SC & ST in the study area (Census 2001) 60
3.11 Literacy rate in Study area (Census 2001) 61
3.12 Vocational Pattern of the Study Area 62
4.1 Predicted GLC of PM10 due to Propose Plant (With APCD) 75
4.2 Predicted GLC of PM10 due to Propose Plant (Without APCD) 76
10.1 Organizational Set-up for Environmental Committee 132
ANNEXURES
Sr. No ANNEXURE
I. TOR from SEAC Gujarat
II. Compliance of TOR
III. GWIL Letter
IV. Land Possession Documents
V. Technical Details of Induction Furnace
VI. One complete season base line ambient air quality data (Raw AAQ data)
VII. List of Flora and Fauna
VIII. Emergency Exit Gate
IX. Undertaking for Local Employment Generation
X. Source Specific Pollution Control Scheme
XI. Copy of Supply of Iron Ore agreement
XII. Mutual Agreement with Doctor
XIII. Details of firefighting Plan
XIV. Five Years Green Belt Development Plan
XV. Ownership of EIA
XVI. NABET Certificate
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 1:Introduction
Pollution and Ecology Control Services, Nagpur P a g e | 1
CHAPTER-1
INTRODUCTION
1.1 PREAMBLE
Sai Inductomelt Pvt. Ltd is a Private Company incorporated in 2004. It is classified as
Indian Non-Government Company and is registered at Registrar of Companies,
Ahmedabad. M/s Sai Inductomelt Pvt. Limited Corporate Identification Number is (CIN)
U35117GJ2004PTC044607 and its registration number is 044607. Its registered address
is plot no. 1497/B, Theosophical Lodge, Rupani Circle, Bhavnagar - 364001, Gujarat,
India.
M/s Sai Inductomelt Pvt. Ltd has proposed a project for manufacturing of Billets/Ingots
@ 2, 22,000TPA by installation of new induction furnace of capacity 2 x 25TPH and 2 x
12TPH The proposed project to be sited atSurvey no: 1020& 1021/1,Bhavnagar -
Vallabhipur Highway, Village:Chamardi, Taluka: Vallabhipur,District:Bhavnagar
(Gujarat). The total 13.29 Acre land has acquired for the proposed project.
Project activities falls category ‘B’ of the Schedule of EIA Notification dated 14th
September, 2006 and its subsequent amendments
1.2 PURPOSE OF THE STUDY
The proposed project involves manufacturing of Billets/Ingots @ 2, 22,000TPA, the
project fall under the Category ‘B’ of project activity 3(a) as per the Schedule of EIA
Notification, 2006 and needs to obtain prior environmental clearance from SEIAA.TORs
was issued vide 455th meeting of the SEAC, Gujarat held on 29th November, 2018, copy
of awarded TORs along with its compliance report is attached as Annexure I and
Annexure II with this report. The purpose of EIA study report is to assess the impacts of
proposed industrial activity on environment and to plan appropriate environmental
control measures to minimize adverse impacts and to maximize favorable impacts. The
following major objectives have been considered:
• To assess the existing status of environment
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 1:Introduction
Pollution and Ecology Control Services, Nagpur P a g e | 2
• To assess the impacts due to the project
• To suggest pollution control measures
• To prepare an action plan
1.3 IDENTIFICATION OF PROJECT & PROJECT PROPONENT
Sai Inductomelt Pvt. Ltd is a Private Company incorporated in 2004. It is classified as
Indian Non-Government Company and is registered at Registrar of Companies,
Ahmedabad. Sai Inductomelt Pvt. Limited Corporate Identification Number is (CIN)
U35117GJ2004PTC044607 and its registration number is 044607. Its registered address
is plot no. 1497/B, Theosophical Lodge, Rupani Circle, Bhavnagar - 364001, Gujarat,
India.
Company Details
Company’s name : M/s. Sai InductomeltPrivate Limited
Address : Survey no: 1020 & 1021/1,Bhavnagar-Vallabhipur
Highway, Village: Chamardi, Talluka:Vallabhipur, District:
Bhavnagar(Gujarat)
Telephone No.
E-mail Address
:
:
9825705700
Name of the Directors 1) Bidhichand Kakaram Bansal
2) Saroj Bidhichand Bansal
1.4 SITE SELECTION CRITERIA
• No National Park, Biosphere Reserve and Wildlife Sanctuary and Notified Eco
Sensitive Areas within 10 km radius.
• No archaeological monument, interstate boundary and defense installation.
• No notified critically polluted area within 10 km radius.
• No nallah/water body, public roads, forests within the project site.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 1:Introduction
Pollution and Ecology Control Services, Nagpur P a g e | 3
• Availability of Raw Material.
• Availability of Water (source: Gujarat Water Infrastructure Limited).
• Assured Power Supply.
• Market available for finished products.
• Availability of adequate man power.
• No R & R issue is involved.
1.5 DETAILS OF PROJECT SITE
The proposed project to be sited at Survey no: 1020& 1021/1,Bhavnagar - Vallabhipur
Highway, Village:Chamardi, Taluka: Vallabhipur,District:Bhavnagar (Gujarat). The
details of the project site (10 km radius) are presented in Table 1.1 and location map is
presented in Figure 1.1, Study Area (10 Km radius) is shown in Figure 1.2 and Google
Earth image of the proposed project site is given in Figure 1.3.
TABLE 1.1: DETAILS OF PROJECT SITE (10 KM RADIUS)
Sr No Particulars Details
1 Project Site Survey no: 1020 & 1021/1,Bhavnagar - Vallabhipur
HighwayVillage:Chamardi, Talluka :Vallabhipur,
District:Bhavnagar
2 Latitude Latitude : 210 48’ 30.29” N
3 Longitude Longitude : 710 54’ 07.37 E
4 Elevation above MSL 12 m
5 Topo sheet NF 42 - 12
6 Present landuse Vaccant land, NA is obtained7 Nearest National
Highway/State Highway
SH 36:1.3 km in East Direction
8 Nearest Airport/ Air Strip Bhavnagar 30.Km (ESE)
9 Nearest Village/Habitates Chamardi 2.5 kms South direction
10 Forest Blackbuck National Park 30 km in NE direction
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 1:Introduction
Pollution and Ecology Control Services, Nagpur P a g e | 4
Source: Maps of India
Figure 1.1:Location Map of the Proposed Project Site
11
Ecologically Sensitive
Zones like wild life
sanctuaries, national parks
and biospheres
Archaeological structures, Historical places, Sanctuaries
and Biosphere are not present within 10 km
12 Water Bodies Rangholi River 0.6Km South direction
Kalubar River 1.5Km NE direction
Gautameshwar Dam 13 Km SE Direction
Gulf of Khambhat 36.0Km in East Direction
Ghelo River 7.8 Km in North Direction
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 1:Introduction
Pollution and Ecology Control Services, Nagpur P a g e | 5
Source: SOI Toposheet
Figure 1.2: Topographical Map of Study Area (10 Km Radius)
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 1:Introduction
Pollution and Ecology Control Services, Nagpur P a g e | 6
Source: Google Earth
Figure 1.3: Satellite image of the site
1.6 PROJECT IMPORTANCE TO THE COUNTRY AND/ OR REGION
Global steel production grew enormously in the 20th century from a mere 28 million tons
at the beginning of the century to 1011 million tonnes at the end of 2005. That was the
period when the steel industry developed in Western Europe and the USA followed by
the Soviet Union, Eastern Europe and Japan. However, steel consumption in the
developed countries has reached a high stable level and growth has tapered off. Towards
the end of the last century, growth of steel production was in the developing countries
such as China, South Korea, Brazil and India. Steel production and consumption grew
steadily in China in the initial years but later it picked up momentum China produced
220.1 million tons in 2003, 272.2 million tons in 2004 and 349.36 million tons in 2005.
That is much above the production of Japan at 112.47 million tonnes, the USA at 93.90
million tons, Russia at 66.15 million tones and India around 42 million tons in 2005.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 1:Introduction
Pollution and Ecology Control Services, Nagpur P a g e | 7
India is the third-largest crude steel producer in the world. In FY18, India produced
104.98 million tonnes (MT) of finished steel. Crude Steel production during 2017-18
stood at 102.34 MT. Exports and imports of finished steel stood at 1.35 MT and 1.89 MT,
during Apr-Jun 2018.Steel consumption is expected to grow 5.7 per cent year-on-year to
92.1 MT in 2018. India’s steel production is expected to increase from 102.34 MT in
FY18 to 128.6 MT by 2021. The Government of India has allowed 100 per cent foreign
direct investment (FDI) in the steel sector under the automatic route. India’s per capita
consumption of steel grew at a CAGR of 3.96 per cent from 46 kgs in FY08 to 65.25 kgs
in FY17. The figure stood at 68 kgs during April-February 2017-18. National Steel
Policy 2017 seeks to increase per capita steel consumption to the level of 160 kgs.
1.6.1 Steel Production in India
India is one of the few countries where the steel industry is poised for rapid growth.
India's share in world production of crude steel increased from 1.5% in 1981 to around
3.5 % in 2004. While plant closures and privatization are rare in India, the private sector
is considered to be the engine of growth in the steel industry and technological changes
and modernization are taking place in both the public and the private sector integrated
steel plants in India. Steel production of India accounted for 14.33 million tons in 1990-
91, which gradually increased to 36.12 million tons in 2003-04, as shown in Table below.
The Indian steel industry got a giant importance in the recent past when the Tata Steel
purchased the Corus steel. Today India plays a significant role in the production of steel
in the world. The Indian steel industry is growing at 8.74 % of CAGR.
1.6.2 Steel Billet Industry
Steel billets are manufactured either by ingot casting and rolling through blooming &
billet mills or by forging or by continuous-casting of billets directly from liquid steel.
Billets manufactured by forging are mostly alloy or special steels. Pencil ingots of
smaller sizes, manufactured in mini steel plants are also used as substitute of billets. Due
to better yield, less energy consumption and capital investment, continuous-casting is
being practiced even for production levels of 25,000-30,000 TPA of billets. The billet
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 1:Introduction
Pollution and Ecology Control Services, Nagpur P a g e | 8
being a semi-finished product is used for further processing for production of suitable
products. It is used as a feedstock to rolling mills for production of long products like
wire rods, bars/rods and light structural. Billet is also used extensively in forge shops and
machine shops for production of engineering goods and also as feedstock for seamless
tubes.
While projecting all-India demand for steel billets, the requirement of the same for
integrated steel plants (primary producers) has not been considered, since their captive
requirement goes for finished steel production. The anticipated production of mild steel
bars and rods and structural from secondary producers during 2006-07 is of the order of
11.8 million tons. Billet requirement for producing the above products will be around
12.5 million tons. The production of pencil ingots/billets from secondary sector during
2006-07 is likely to be about 10 million tons, which includes mild steel, medium/high
carbon steel, alloy steels etc. This indicates that there is a lot of potential for increasing
the steel consumption in India. To meet the increasing demand and to stimulate economic
growth the Sai Inductomelt Private Limited has proposed the project.
1.7 NEED FOR THE PROJECT
The demand for steel in the country is currently growing at the rate of over 8% and it is
expected that the demand would grow over by 10% in the next five years. However, the
steel intensity in the country remains well below the world levels. Our per capita
consumption of steel is around 110 pounds as compared to 330 Pounds for the global
average. This indicates that there is a lot of potential for increasing the steel consumption
in India. To meet the increasing demand and to stimulate economic growth the M/s Sai
Inductomelt Private Limited has been proposed the project.
1.8 APPLICABLE ENVIRONMENTAL REGULATORY FRAMEWORK
The proposed project will abide and function under the purview of the following Rules,
Acts & Regulations which are formulated by the Govt. of India to protect the
environment and development in a sustainable way.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 1:Introduction
Pollution and Ecology Control Services, Nagpur P a g e | 9
• The Water (prevention & Control of Pollution) Act, 1974
• The Air (Prevention & Control of Pollution) Act, 1981
• The Environmental (Protection) Act, 1986
• Environmental Impact Assessment Notification dated 14th September 2006 and
subsequent amendments
• The Hazardous & Other Waste (Management and Transboundary Movement)
Rules, 2016
• Solid Waste Management Rules, 2016
• Noise Pollution (Regulation and Control) Rules, 2000 and its amendments
• The Public Liability Insurance Act, 1991
1.9 SCOPE OF THE STUDY
This report represents environmental impact assessment and environmental management
plan of the proposed project of manufacturing of M.S. Billets/Ingots at Village:
Chamardi, Talluka Vallabhipur, District: Bhavnagar (Gujarat).As per the requirements
stated in the Environmental Impact Assessment Notification 2006 and its subsequent
amendments, Environmental Impact Assessment (EIA) study has been undertaken to
assess the environmental impacts of the proposed project and to develop a site specific
environmental management plan and risk mitigation measures. Subsequently, baseline
environmental studies have been conducted during October to December 2018 as per the
standard TOR issued via vide letter no SIA /GJ/IND/29097/2018 dated 29th November
2018 in 455thmeeting of the State Level Expert Appraisal Committee and accordingly
EIA report has been prepared.
1.10 EIA/EMP REPORT SCHEME
Chapter 1: Introduction- Provides a background to the M/s. Sai Inductomelt Private
Limited project, the project proponent, and the process of environmental impact
assessment.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 1:Introduction
Pollution and Ecology Control Services, Nagpur P a g e | 10
Chapter 2: The Project Description- Describes the characteristics of the proposed plant,
the processes, location details and operations associated with proposed manufacturing of
2, 22,000 TPA M.S. Billets/Ingots.
Chapter 3: Baseline Environmental Status- Describes the background environmental
characteristics and the other economic activities in the area.
Chapter 4: Anticipated Environmental Impacts and Mitigation Measures- The major
impacts both adverse and positive are predicted and the consequent mitigation measures
are provided in this chapter. The impacts are identified with respect to the present
environmental baseline conditions.
Chapter 5: Analysis of Alternatives for Technology and Site -The technology and
project site alternatives are discussed in the chapter five.
Chapter 6: Environmental Monitoring Program- The monitoring to be carried out in
the proposed plant will be described in detail along with the frequency and sampling
locations.
Chapter 7: Additional studies -This chapter will include outcomes of public
consultation, Identification of hazards and risk assessment and social impact assessment.
Chapter 8: Project Benefits - This chapter deals with improvements in the physical
infrastructure, social infrastructure employment potential and other tangible benefits due
to proposed project activity.
Chapter 9: Environmental Cost Benefit Analysis:
Chapter 10: Environment Management Plan –This chapter will include the description
of administrative aspects of ensuring that the mitigation measures suggested are
implemented and their effectiveness is monitored, after approval of the EIA
Chapter 11: Summary and Conclusion -The summary of the EIA report has been given
in this chapter along with conclusions.
Chapter 12: Disclosure of Consultants
Brief introduction of the consultancy organization involved in EIA report is given in this
chapter.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 2:Project Description
Pollution and Ecology Control Services, Nagpur P a g e | 11
CHAPTER 2
PROJECT DESCRIPTION
2.1 NEED OF THE PROJECT AND MAGNITUDE OF OPERATION
The proposed project of manufacturing of M.S. Billets/Ingots of M/s Sai Inductomelt
Private Limited is located at Survey no: 1020 & 1021/1, Bhavnagar-Vallabhipur
Highway, Village: Chamardi, Talluka:Vallabhipur, District: Bhavnagar, Gujarat.
The Bhavnagar region in Gujarat state is a potential zone for establishment of iron and
steel industries because of its accessibility, numbers of unit are comes in this region
hence, unit proposes to produce M.S. Billets/Ingots at the above said location.
In addition to this, easy availability of Scrap (MS scrap & Sponge iron, etc.) as raw
material, consistent electricity supply, availability of water, basic transportation facility
including good road network has motivated to establishment of new project at particular
site. In addition to this, consumption of finished product has increased day by day with
average Annual Growth Rate (CAGR) of 6%. This has given the opportunities for the
production of Steel in Private sector.
The proposed project will installed four induction furnace having capacity of 2 x 25 TPH
and 2 x 12 TPH. The total production capacity of M.S.Billtes /Ingots will be
2, 22,000TPA.
TABLE 2.1: PRODUCTION DETAILS
Sr. No Name of Product Quantity (TPA)
1 M.S.Billets/Ingots 2, 22,000
2.2 PLANT LAYOUT
The topography of site is plain and is suitable for construction of heavy structures,
buildings and foundations. The proposed capacity of manufacturing of M.S.
Billets/Ingots, has been proposed in Survey no: 1020 & 1021/1, Bhavnagar-Vallabhipur
Highway, Village: Chamardi, Talluka: Vallabhipur, District: Bhavnagar, Gujarat. All
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 2:Project Description
Pollution and Ecology Control Services, Nagpur P a g e | 12
facilities in the plant area will be identified so as to rationalise and minimize the extent of
land required. The layout will also facilitate movement of men and materials between the
various facilities during construction, operation and maintenance of the plant.
FIGURE 2.1: PLANT LAYOUT
Land Area 53781.00 Sq.M.1)
Green Land Area Sq.M.2)
Sq.M.
Sq.M.
Sq.M.
Sq.M.
1DRG.NO. :
DATE :28.11.2018
sr.no.1020 & 1021P
village :-CHAMAR DI, tal.: -VALLBHIPUR
dist :- bhaVnagar
SAI INDUCTOMELT PVT. LTD.
EnginEER
P.C.Pitroda & co.
134, First Floor Geetanjali Complex,
Kalanala, Near Municipal Corporat ion,
Bhavnagar
Mob. 9426918490
Road Center Line
Ad
j.S
r.N
o.1
019
Ad
j. Sr. N
o. 1018
Adj.Sr .No.1027
Marag
Boundary Of Navagam Village
H.L
.Lin
e
H.L
.Lin
e
18.01.2019
26.01.20191)
2)
3)
29.01.20194)
A rea = 71 57.96
A rea = 1401.55
A re a = 5372.44
3945.80
7157.96
1401.55
5372.44
17877.75
A rea = 3945 .80A
B
A
B
C
D
C
D
Factory Shed Area3) Sq.M.22259.29
Water Complex & Bag Filter4) Sq.M.2150.98
3
2
2
2
2
4
Electric Sub Station5) Sq.M.1923.38
Office Building6) Sq.M.116.37
Weighbridge7) Sq.M.62.93
5
6
7
Labour Quarter8) Sq.M.1033.23
8
Road and open Space8) Sq.M.8468.12
53781.00 Sq.M.
Emergency Exit
SINGLE HYDRANT VALVE
I NDEX
DOUBLE HYDRANT VALVE
PLANT AT IONDGSET
DG SET
A
B
C
D
EF
G
H
PLOT BOUNDARY DEM ARCATI ON
53781.00
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 2:Project Description
Pollution and Ecology Control Services, Nagpur P a g e | 13
The proposed project activity will be constructed in industrial land .The total plot area is
53781.0 Sq. m land. Out of total area approximately 33.24% i.e. 17877.75 area will be allotted
for green belt development. Detailed area statement is mentioned in below table
TABLE 2.2: LAND DISTRIBUTION DETAILS
Sr.No
Particular Proposed Area in(Sq. m)
1 Total Plot Area 53781.002 Factory Shed Area 22259.293 Green belt Area 17877.753 Water complex and bag filter 2150.984 Electric sub station 1923.385 Office building 116.376 Weighbridge 62.937 Clock Room 1033.238 Road & Open space 8468.12
2.3 SIZE OR MAGNITUDE OF OPERATION:
The company will manufacture M.S. Billets/Ingots by using sponge Iron and MS scrap
as raw materials with proposed capacity of 2,22,000 TPA. The three induction furnace
will be installed at plant with a capacity of 2X15 TPH and 1X 20 TPH. This will require
for the melting of sponge iron and scrap. Bag filter as an air pollution control system of
specified size with 30 m stack will be installed at discharge point of flue gases. The
company has acquired 53781.0 Sq. m of land for the proposed project.
2.3.1 Raw Material Requirement :
The annual raw material required for the production of M.S.Billets/Ingots is given in
Table 2.3 and Material balance is given in Table 2.4
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 2:Project Description
Pollution and Ecology Control Services, Nagpur P a g e | 14
TABLE 2.3: ANNUAL RAW MATERIAL REQUIREMENT
TABLE 2.4: MATERIAL BALANCE
S.N Input Quantity (T/T) Output Quantity (T/T)1 MS Scrap 1.00 M.S. Billet/Ingots 1.002 Sponge Iron 0.0504 Slag 0.0504Total 1.0504 Total 1.0504
2.3.1.1 Characteristics of MS scraps
All raw materials like Iron ore, MS scraps and sponge iron will be received and stored in
respected closed storage shed. Scrap from ship is low carbon and good quality. All raw
scraps is separated by magnetic separator to remove foreign particle. Separated scrap is
manually examined for removal of painted, oily and dirty residual scrap. Such scrap is
sorted out. After sorting scrap will be sent for cleaning section where scrap will be
cleaned manually by wire brush and compress air. Separated scrap is then crushed to
make homogeneous block. These block of metal finally feed to induction furnace for
melting. Maximum one month raw material inventory will be maintained in the plant for
continuous operation.
Name of Raw Materialas Input
TPAProposed Source
MS Scrap 2,20,000 Locally procured from the vendorsand imported- by road as the statehighway no. SH 36 at 1.3 kmaway from the project site
Sponge Iron 11,100 Procured from the open market- byroad
Additives(Silicon, Manganeseetc.)
As per productRequirement
Procured from the open market- byroad
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 2:Project Description
Pollution and Ecology Control Services, Nagpur P a g e | 15
2.3.1.2 Proposed Infrastructure Facility
The following infrastructure development and machinery will be installed in proposed
project.
Table 2.5 PLANT INFRASTRUCTURESr. No Facilities Proposed Quantity (Nos.)1 25TPH induction Furnace 2
2 12 TPH induction Furnace 2
3 Slag Crusher As required4 Bag Filter 15 Suction hood with Exhaust 45 Concast machine As required
EOT Crane
Magnet For
Scrap cleaning
Raw MS Scrap Stock 1 Removal of Plastic and Rubber material Raw MS Scrap Stock 2
Rejected ScrapClean and final Scrap Stock 3HydrolicBlockMaker
Final induction feeding MSScrap Block
Cleaning
Manual examination for removal of dirt, only and painted scrap
Raw Scrap Storage Shed No. 1
Transport to factory
Raw Scrap from Alang Ship Breaking Yard
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 2:Project Description
Pollution and Ecology Control Services, Nagpur P a g e | 16
2.3.2 Water Requirement & Waste Water Generation
In this production of M.S billets/Ingots plant, water will be basically required for concast
machine, domestic and other miscellaneous purpose. The total water requirement for
proposed project will be 150 KLD. The water requirement will be procured from Gujarat
Water Infrastructure Limited for which application has been made to GWIL (Copy of
Application is attached per Annexure III). The breakup of water requirement and waste
water generation for proposed plant is given in Table 2.6 and water balance chart is
presented in Figure 2.2
TABLE 2.6 WATER REQUIREMENTS AND WASTE WATER GENERATION
Maximum water is required in Concast machine used for molding of billets, due to high
temperature maximum water will get evaporated during molding & cooling process.
Hence, maximum industrial water requirement is for the make-up of water losses. No
waste water will be generated from the industrial activities. Domestic waste-water
is/will be disposed of through soak-pit system.
Sr.No.
Unit Total WaterRequirement
m3/day
WastewaterGeneration
m3/day
Mode of disposal of wastewater
1 Domestic 16.5 13 Domestic wastewater will bedisposed of through soak pit/septictank system
2 Gardening 5.5 - -
3 Industriala) Process Nil Nil -
b) Washing Nil Nil -c) Boiler NA - -d) Cooling 123 - Water will be used in concast
machine for moulding of moltenmetal through water spray. So thewater will gets evaporated due totemperature difference. The unitwill be zero discharge unit.
d) Others 5 - Dust Suppression within Premises
Total 150 13 -
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 2:Project Description
Pollution and Ecology Control Services, Nagpur P a g e | 17
FIGURE 2.2: WATER BALANCE FLOW CHART
2.3.3 Power Requirement:
The total power requirement for proposed project will be 20 MW and will be supplied by
Gujarat State Electricity Board. One DG set of 125 KVA capacity will be installed in
case of power failure.
TABLE 2.7: ENERGY BALANCE
Input/output Particular Percentage MW
Heat Input From transformer 100% 20
Total 100 % 20
Heat Output Heat transfer to
Metal 40 8
Slag 10 2
Furnace walls 10 2
Cooling system 20 4
Other Losses 20 4
Total 100 % 20
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 2:Project Description
Pollution and Ecology Control Services, Nagpur P a g e | 18
2.3.4 Man-Power Requirement:
The manpower requirements for the operational phase of the proposed project will be
about 325 people. In addition, there will be an indirect employment for skilled/ semi-
skilled people during project life. All attempts will be made to employ suitable, locally
available, skilled personnel from the nearby area. The undertaking for recruitment of
local employment is attached as Annexure IX
2.3.5 Land Requirement
The total plot area is 53781.0 Sq. m. Out of total area approximately 33.24% i.e.
17877.75 area will be allotted for green belt development. The land is owned by the
company and N.A. is obtained. Land document is attached herewith as Annexure V.
2.3.6 Capital project cost projection
The total Project cost required for the project is Rs 60 Crore. The details of cost
requirement is given in Table 2.8
TABLE 2.8: PROJECT COST PROJECTION
Sr. NoComponent Capital Cost
(Rs. in Crore)
1 Land & Building 10.77
2 Plant & Machinery 44.00
3 Electrification 3.23
4 Emission control Engineering 0.50
5 Water & Waste watermanagement
0.10
6 Solid Waste Management 1.00
7 Green Belt development 0.05
8 Environmental Monitoring 0.10
9 Other aspect 0.25
Total Rs. 60.0
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 2:Project Description
Pollution and Ecology Control Services, Nagpur P a g e | 19
2.4 PROPOSED SCHEDULE FORAPPROVAL ANDIMPLEMENTATION
The proposal was submitted under EIA notification, 2006 on dated 18-09-2018. The
proposal was appraised by SEAC, Gujarat in their 455thmeetingand standard TOR was
issued vide letter number SIA/GJ/IND/29097/2018 dated 29th November 2018.
The commissioning of the project will be taken up after receipt of environmental
clearance and consent to operate. It is estimated that the procurement of equipment,
engineering, construction of sheds, buildings and equipment foundations, erection of
equipment, piping and cabling work shall be completed in a period of 10 months from the
day of approval. Another 3-4 months will be required for Trials. There after the
commercial production shall commence. Thus, overall 12 months shall be required for
actual starting of the plant.
2.5 TECHNOLOGY AND PROJECT DESCRIPTION
The company will manufacture M.S. Billets/Ingots by using sponge Iron and scrap as raw
materials. Silicon & manganese will be added as alloying elements using medium
frequency induction furnace and continuous casting technology.
Sponge Iron and scrap are used as raw materials. Silicon & Manganese will be
added as alloying elements using medium frequency induction furnace and
continues casting technology.
In the Induction Melting Furnace where the iron melts at a temperature of about
16000C.
For production of billets/Ingots the molten material is poured into a ladle and then
transported to Continuous Casting machine.
In Continuous casting machine water is used to mold molten metal into
billets/ingots which results in water evaporation due to temperature difference
The Cut Billets/Ingots are transported by a handling crane and stored in the
Storage yard as per the Grade and Quality for dispatch.
Melting capacity of Furnace will be 25000Kg
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 2:Project Description
Pollution and Ecology Control Services, Nagpur P a g e | 20
Working of Induction Furnace
Induction Furnace is a device to melt the charge material using electrical power. It
consists of Crucible lined with water cooled induction coils, Electrical system to give
controlled power to induction coil, Hydraulic tilting system, Heat exchanger to cool the
circulating water, furnace transformer, Power Factor improvement system and surge
suppressor. Induction furnace consists of iron shunts which cover up to 60% of the outside of
the coil to ensure adequate control of the magnetic field and direct mechanical support of the
coil.
After the furnace is switched on; current starts flowing at a high rate and a comparatively
low voltage through the induction coil of the furnace, producing an induced magnetic
field inside the central space of the coils where the crucible is located. The induced
magnetic fluxes thus generate cut through the packed charge in the crucible. As the
magnetic fluxes cut through the scraps and complete the circuit, they generate an induced
current in the scrap. This induced current, as it flows through the highly resistive path of
the scrap mix, generates tremendous amounts of heat and melting of scrap starts. As soon
as the charge has melted clearly, any objectionable slag is skimmed off, and the necessary
alloying elements are added. When these additives have melted completely, the power
input may be increased to bring the temperature of metal up to the point most desirable
for pouring. The current is then turned off and the furnace is tilted for pouring into a
ladle. As soon as pouring has ceased the crucible is leaned completely from any slag or
metal droplets adhering to the wall of the crucible and the furnace is now ready for
charging again. Liquid Metal from Induction Furnace is carried in a ladle over the Con-
cast Machine. The technical details of Induction furnace is given in Annexure V. The
process flow chart of the manufacturing of Billet/ingots are shown in Figure 2.3 and
Plant layout is given in Figure 2.4
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 2:Project Description
Pollution and Ecology Control Services, Nagpur P a g e | 21
Figure 2.5: Process Flow Chart of the Manufacturing Billets/Ingots
2.6 MITIGATION MEASURES
2.6.1 Air Pollution
Air in and over the plant area and beyond its boundaries gets polluted with gases, fumes
and dust particles emitted from the stacks, transfer points of conveying and handling
equipment. The flue gases are generated during melting of scrap. Quantity and quality of
flue gases mainly depends upon type of scrap used in the furnace, i.e. with the degree of
contamination of scrap. These flue gases need proper treatment for removal of dust
particles before being discharged into the atmosphere. Dust and fumes will be collected
with the help of Bag filter as air pollution control system of specified size followed by 30
meter stack. Proper measures will be adopted by installing sprinkler, nozzles for control
of fugitive emission. Internal roads will be concreted to minimize fugitive emission due
to transportation. The raw material transporting vehicle will be regular checked
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 2:Project Description
Pollution and Ecology Control Services, Nagpur P a g e | 22
&maintained, it will be ensured that all trucks carrying raw material will be covered by
Tarpaulin.
2.6.2 Water Pollution
Requirement of water for proposed unit is only for cooling & domestic purpose; the same
will be recycled for cooling purpose through closed cooling circuit and there will not be
any effluent generation. However for domestic effluent Septic tank will be provided.
2.6.3 Noise Pollution
Noises from fans, centrifugal pumps, electrical motors etc. will be kept in control so that
the ambient noise level shall not exceed 75dBA during daytime and 70dBA during
nighttime. Noise pollution control measures will be provided in respective departments
by way of providing silencers soundproofs cubicles / covers and proper selection of less
noise prone machinery and by development of green belt. Necessary protective measures
will be taken to minimize the noise level as per the requirement of OSHA (Occupational
Safety and Health Administration) Standards
2.6.4 Solid waste Management
The solid waste generated will be in the form of slag. The total quantity of proposed slag
generation will be approx. 11,100 TPA. Slag crushers will be installed to recover iron
particles to be reused in Induction Furnace. Slag generated from Induction Furnace will
be used for hardening of working area, internal road, brick manufacturers and concreting.
The used machine oil of 0.1 TPA will be sell to registered oil vendors only.
2.6.5 Green belt Development
The company have total 13.29 Acres land. Out of this,33% i,e 4.38 Acres (17748 Sq. m)
land will be developed as green belt. Locally available types of trees will be plant in
proposed project. The plantation will be done in a phased manner simultaneously to
commencement of operation of the Plant.
During plantation landscaping pattern will be considered. The plantation scheme covers
the plantation of ornamentals plants and some local fruit bearing species.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 2:Project Description
Pollution and Ecology Control Services, Nagpur P a g e | 23
2.6.6 Transportation
• The raw material will be transported by Road.
• Raw material & Finished Products will be transported by road.
• About 25 trucks of 30 T Capacity will be required Per Day.
• It will be ensure that all trucks carrying raw material are tarpaulin covered.
• Internal roads are being Tarred / Concreted with installation of water sprinklers to
suppress dust due to transportation.
2.6.7 Fire Protection System
The firefighting system will be designed in conformity with the recommendations of the
Tariff Advisory Committee (TAC) of Insurance Association of India. While designing
the fire protection systems for proposed facilities its extreme ambient conditions need
special attention. Codes and Standards of National Fire Protection Association (NFPA)
will be followed, as applicable.
2.6.8 Occupational Health and Safety
• The operating and maintenance personnel will be provided with all the necessary
safety equipment such as hand gloves, gum boots, aprons, helmets, protective
glasses, ear muffs etc.
• Workers training will focus on reduction of wastes, utilization of wastes and
generally maintaining a clean and healthy environment.
• At work place, first aid facilities will be maintained at a readily accessible place
where necessary appliances including sterilized cotton wool, disinfectants, bandages
etc. will be available.
• Emergency medical treatment will be facilitated at local hospital.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 2:Project Description
Pollution and Ecology Control Services, Nagpur P a g e | 24
2.7 ASSESSMENT OF NEW & UNTESTED TECHNOLOGY FOR THE RISK OF
TECHNOLOGY FAILURE
The production of M.S. Billets/Ingots using Induction Furnace technology is a globally
proven technology adopted by all for medium scale industry. It is latest technology with
advantage of low capital cost, low power consumption; low slag generation compared
with other technology. Its installation is relatively easier and its operation is simpler.
Among other advantages, there is very little heat loss due to rotation from the furnace as
the bath is constantly covered and there is practically no noise attending its operation.
The molten metal in an induction furnace is circulated automatically by electro-magnetic
action so that when alloy additions are made, a homogeneous product is ensured in
minimum time. In pursuance of this, the induction furnace based technology is proposed
for this project.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 25
CHAPTER 3
DESCRIPTION OF THE ENVIRONMENT
3.0 BASELINE ENVIRONMENTAL STATUS
The Baseline environmental status around the proposed activities indicates the exiting
quality of Air, Water, Noise, Soil, and Socio-economic environment. The baseline
environmental data were generated within 10 km radial distance area of proposed project
site. The satellite image is provided in Figure 3.1.
Figure 3.1: Satellite Image of Project site showing 10 km study area
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 26
The impact identification always commences with the collection of baseline data such as
Ambient Air Quality, Micro-Meteorology, Ground and Surface Water Quality, Noise
levels, Soil Quality, Land use pattern, Biological Environment and Socio-economic
aspects, Solid and Hazardous waste, and risk assessment within the study zone of 10 km.
radius. The baseline environmental study has been done for the period October to
December 2018 in accordance with the Guidelines for EIA issued by the Ministry of
Environment Forests and Climate Change, Govt. of India and CPCB, New Delhi.
Secondary data was also collected from different sources.
3.1 METHODOLOGY
The data was collected from both primary and secondary sources. The baseline
information on micro-meteorology, ambient air quality, water quality, noise levels, soil
quality and floristic descriptions were collected. Micrometeorological data at site was
recorded using automatic weather station. Apart from these, secondary data have been
collected from various governmental agencies.
For reconnaissance survey the sampling locations were identified based on:
• Existing topography and meteorological conditions
• Locations of water intake and waste disposal points.
• Location of human habilitation and other sensitive areas present in the vicinity of
the proposed project site.
• Representative areas for baseline conditions.
• Accessibility for sampling
The baseline studies started with reconnaissance survey and the site visits in the study
area for fixing the monitoring locations for collection of the primary data. Various
Government and other organizations were approached for getting information for the
secondary data generation. The various parameters surveyed and studied for the baseline
study are discussed in the following components:
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 27
3.2 MICROMETEOROLOGY
The meteorological data recorded during the study period was very useful for selection of
sampling locations as per upwind and down-wind directions for proper on-site
monitoring to be undertaken for various meteorological variables in order to generate the
site specific data. Data was collected for proposed project site on hourly basis
continuously during October to December 2018. Data of wind velocity, wind direction,
ambient temperature, relative humidity, cloud cover and rainfall data were recorded at
hourly intervals along with atmospheric pressure for 24 hours for the study period.
Wind velocity and wind direction were recorded using cup anemometer and wind vane
respectively. Ambient temperature was noted by wet and dry bulb thermometer. Relative
humidity was measured by hygrometer. An barometer was used for measuring
atmospheric pressure and a self-recording rain gauge was used for rainfall data collection.
Cloud cover data was collected by visual inspection. Apart from these, secondary data
have been collected from Census Handbook, Revenue Records, Statistical Department,
Soil Survey and Land use Organization, District Industries Centre, Forest Department,
Central Ground Water Authority, etc..
Windrose
The meteorological data was collected at the site by installing an automatic weather
station during winter season (October-December 2018). Wind Speed, Wind Direction,
Temperature and Relative Humidity were recorded for the total study period. Wind roses
on sixteen sector basis (N, NNE, NE, ENE, E, ESE, SE, SSE, S, SSW, SW, WSW, W,
WNW, NW, and NNW) have been drawn for 24 hours. The data on wind patterns are
pictorially represented by means of wind rose diagrams for study period October to
December 2018 as shown in Figure 3.1.The metrological data reflecting minimum,
maximum temperature in 0C, relative humidity in %, wind speed in m/s, for the year
2018-19 has been given Table 3.1.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 28
Table 3.1. Onsite Meteorological Data (Period: October to December2018)
Month Temperature
(0C)
Relative Humidity
(RH)
Wind Speed (km/hr)
Min Max Min Max Min Max
October 20.2 38.8 32.5 92.9 1.2 11.8
November 15.6 38.6 32.6 96 1.3 12.1
December 12.4 30.8 23 93 2.8 20.8
During the study period, average wind speed measured on site is 1.45 m/s. The
wind rose diagram indicates predominant wind direction is from NE with 7.25 % calm
condition
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 29
Figure- 3.1: Windrose Diagram during study period (October –December 2018)
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 30
3.3 AIR QUALITY
3.3.1 Ambient Air Quality Monitoring
The baseline status of the ambient air has been established through a scientifically
designed ambient air quality monitoring network. The following criteria were taken into
account during selection of the sampling stations:
• Topography of the area
• Human settlements within the study area
• Safety, accessibility and non-interference with general routine of the people
residing near the station
• Prediction of maximum concentration of the air pollutants through dispersion
modeling
• The impact of air pollutants release from the other nearby industry
• Prevailing meteorological conditions in this region
To assess the ambient air quality status, eight air quality monitoring locations were
identified on the basis of meteorology in the upwind and downwind direction as well as
to represent the cross sectional scenario of the project site.
Methodology Adopted for the Study
As per revised norms for Ambient air quality standards prescribed by Ministry of
Environment & Forest vide Notification No. “Schedule VII” of Rule 3(3B) of
Environment (Protection) Seventh Amendment Rules, 2009 from MoEF notification
dated 16 November 2009, five air pollutants viz. PM10, PM2.5, Sulphur dioxide (SO2),
Oxides of Nitrogen (NOX) were monitored on the basis of 24- hour sampling and twice in
a week at each and Carbon Monoxide (CO) were monitored twice in a month for three
month during study period at all locations. The ambient air quality samples were
collected during October to December 2018. The samples were preserved and analyzed
as per the standard methods recommended by Standard Operating Procedure (SOPs) of
the Central Pollution Board (CPCB).
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 31
PM10, PM2.5, SO2 and NOX
Respirable Dust Samplers of Envirotech Instruments (duly calibrated) with gaseous
sampling attachment have been used for monitoring of PM10, SO2, & NO2, Fine
particulate samplers of Envirotech Instruments (duly calibrated) have been used for
monitoring of PM2.5. PM10 and PM2.5 was analysed on electronic balance by Gravimetric
Method whereas, SO2& NO2 were analysed on UV – Visible Spectrophotometer (CPCB
guidelines 2011). The methodology adopted for sampling and analysis of ambient air
quality is as mentioned in Table 3.2
CARBON MONOXIDE
Samples for Carbon Monoxide (CO) were collected in gas bladder and analyzed by Gas
chromatography.
The techniques used for ambient air quality monitoring and minimum detectable level are
given in Table 3.2.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 32
TABLE 3.2
Methodology of Ambient Air Quality Monitoring
SamplingLocations& TimePeriod
Parameters Frequency Equipment
Sample Analysis
MethodologyAnalyticalInstrument
Sensitivity/DetectionLimit
8Locations
DuringOct’18 –Dec’18
PM10
Twice in aweek for12 weeks
RespirableDustSamplerwithCyclone &Flowmeasurement
Electronicbalance
10 µg/m3
IS 5182(Part23):2012(byGravimetry)
PM2.5
FineParticulateSampler
Electronicbalance
10 µg/m3
PL/SOP/120(40CFR 60byGravimetry)
SO2Gaseoussampler
UV-visiblespectro-photometer
5 µg/m3
IS 5182(Part2):2001ModifiedWest &Geakemethod
NO2Gaseoussampler
UV-visiblespectro-photometer
8 µg/m3
IS 5182(Part6):2006Jacob&Hochheissermethod
CarbonMonoxide
Twice inMonth
Gas bladder& pump
GasChromatography
0.1 mg/m3 Sensor/GCmethod
3.3.2 AAQ Monitoring Stations and Observation:
The Ambient Air Monitoring Stations are given in Table 3.3 and Figure 33. The
summary of results of Ambient Air Quality monitoring is given in Table 3.4. The
detailed ambient air quality results is given in Annexure VI. The Revised National
Ambient Air Quality Standards are given in Table 3.5
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 33
Table 3.3
Ambient Air Quality Monitoring Sampling Stations
Source: SOI ToposheetFigure 3.3 Ambient Air Quality Sampling Station
Sr.
No.
Description of monitored
stationsSample code
Distance from
proposed plantDirection
1. Project Site A-1 ---- ----
2. Dambhaliya A-2 2.5 Km. W
3. Bhangadh A-3 5.7 Km. E
4. Manglana A-4 5.0 Km. SE
5. Navagam A-5 4.0 Km. S
6. Ukharala A-6 4.5 Km. SW
7. Chamardi A-7 2.5 Km. N
8. Chogath A-8 4.5 Km. NW
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 34
TABLE – 3.4
SUMMARIZED REPORT OF AMBIENT AIR QUALITY
(OCTOBER-DECEMBER 2018)
Ambient Air
Quality StationParticulars
PM10 PM2.5 SO2 NOx *CO
µg/m3 mg/m3
A-1 Project Site
Minimum 70 23 10 14 0.81
Maximum 84 39 23 25 0.91
Average 78 31 17 20 0.87
A-2 Dambhaliya
Minimum 55 22 10 12 0.48
Maximum 76 33 17 18 0.62
Average 66 28 13 15 0.55
A-3 Bhangadh
Minimum 47 20 10 13 0.34
Maximum 68 29 19 22 0.67
Average 58 25 15 18 0.50
A-4 Manglana
Minimum 69 21 11 12 0.58
Maximum 83 38 21 26 0.90
Average 78 30 16 19 0.73
A-5 Navagam
Minimum 66 18 9 11 0.38
Maximum 81 30 17 20 0.63
Average 74 24 12 16 0.48
A-6 Ukharala
Minimum 56 21 10 13 0.20
Maximum 79 33 15 20 0.46
Average 67 27 12 16 0.31
A-7 Chamardi
Minimum 56 24 10 15 0.23
Maximum 77 32 14 21 0.52
Average 68 28 12 18 0.35
A-8 Chogath
Minimum 57 22 10 13 0.23
Maximum 76 30 19 22 0.72
Average 68 27 15 18 0.46
*CO was monitored twice in a month for three month during study period.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 35
TABLE – 3.5
NATIONAL AMBIENT AIR QUALITY STANDARDS
Pollutant UnitTime weighted
Average
Concentration in airIndustrial
Areas, residentialrural & other areas
Sensitiveareas
PM10 µg/m3 Annual Average24 hours
60.0100.0
60.0100.0
PM2.5 µg/m3 Annual Average24 hours
40.060.0
40.060.0
NitrogenDioxide (NOx)
µg/m3 Annual Average24 hours
40.080.0
30.080.0
Sulphur dioxide(SO2)
µg/m3 Annual Average24 hours
50.080.0
20.080.0
Carbonmonoxide (CO)
mg/m3 1 hours8 hours
4.02.0
4.02.0
Refer : GSR 826(E) dated 16th Nov. 2009
RESULT
On the basis of observations the parameter wise result of monitored parameters are
discussed below.
PM10 PARTICULATE MATTER (<10 μm)
PM10 is a measure of particles in the atmosphere with a diameter of less than 10 or equal
to a nominal 10 micrometers. PM10 is particulate matter with an aerodynamic diameter of
up to 10 µm, i.e. the fine and coarse particle fractions combined.
The Average PM10 concentration at all air quality monitoring stations A-1, A-2, A-3,A-4,
A-5, A-6, A-7, and A-8 are 78, 66, 58, 78, 74, 67, 68, and 68 µg/m3 respectively. All
monitored stations have PM10 concentrations well within stipulated 24 hours average
limit, 100 µg/m3 as prescribed for industrial, residential, rural and other areas as in
revised NAAQ Standards from MoEF. These values represent quite satisfactory condition
regarding PM10 concentration in ambient air.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 36
PM2.5 PARTICULATE MATTER (<2.5 μm)
Particulate Matter-2.5 particles are air pollutants with a diameter of 2.5 micrometers or
less, small enough to invade even the smallest airways. The average PM2.5 concentration
at all air quality monitoring stations A-1, A-2, A-3,A-4, A-5, A-6, A-7, and A-8 are 31,
28, 25, 30, 24, 27, 28, and 27 µg/m3 respectively. All monitored stations have PM2.5
concentrations well within stipulated annual 24 hours limit, 60 µg/m3 as prescribed for
industrial, residential, rural and other areas as in revised NAAQ Standards from MoEF.
These values represent quite satisfactory condition regarding PM2.5 concentration in
ambient air.
SULPHUR DIOXIDE (SO2)
The average SO2 concentrations at all sampling stations A-1, A-2, A-3,A-4, A-5, A-6, A-
7, and A-8 are 17, 13, 15, 16, 12, 12, 12, and 15 µg/m3 respectively. All monitored
stations have SO2 concentrations well within stipulated annual 24 hours limit, 80 µg/m3
as prescribed for industrial, residential, rural and other areas as in revised NAAQ
Standards from MoEF.
OXIDES OF NITROGEN (NOX)
The average NOx concentrations at all sampling stations A-1, A-2, A-3,A-4, A-5, A-6, A-
7, and A-8 are 20,15, 18, 19, 16,16, 18 and 18 µg/m3respectively. All monitored stations
have NOX concentrations well within stipulated annual 24 hours limit, 80 µg/m3 as
prescribed for industrial, residential, rural and other areas as in revised NAAQ Standards
from MoEF.
CARBON MONOXIDE (CO)
Samples of air were collected and analysed for CO content. The average CO concentrations
at all sampling stations A-1, A-2, A-3, A-4, A-5, A-6, A-7, and A-8 are 0.87, 0.55, 0.50,
0.73, 0.48, 0.31, 0.35, and 0.46 mg/m3respectively. All sampling stations have less CO
content than stipulated annual average 2 mg/m3 limit recommended for sensitive area as in
revised NAAQ Standards from MoEF&CC.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 37
3.4 WATER ENVIRONMENT
The water quality monitoring stations were selected with a view to represent the surface
and ground water sources in and around 10 kilometer radius of the study area of proposed
Project site. Sampling stations for water samples were selected taking all water sources
into account, as per MOEF norms. A total number of 10 including four surface water
&six ground water samples were collected and analyzed. Surface and ground water
sampling locations are presented in Table 3. 6 and are shown in Figure 3.4.
Table 3.6
Water Sampling Location
Sr. No. Description of the sampling stationSample
code
Distance from
proposed plantDirection
Surface Water Samples
1. Mangalana (Pond) SW-1 5.0 Km. SE
2. Chamardi ( Pond) SW-2 2.5 Km. N
3. Rangholi river SW-3 3.5 Km. SE
4. Ukhrala SW - 4 4.5 Km. SW
Ground Water Sample
5. Navagam GW-1 4.0 Km. S
6. Dambhaliya GW-2 2.5 Km. W
7. Ukhrala GW-3 4.5 Km. SW
8. Manglana GW-4 5.0 Km. SE
9. Chogath GW-5 4.5 Km. NW
10. Pipaliya GW-6 6.0 Km. S
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 38
Source: SOI Toposheet
Figure 3.4: Map showing Ground and surface water sampling
The methodology for sample collection and preservation techniques was followed as per
the standard methods for the examination of water and wastewater, published by APHA,
AWWA, 22nd Edition, 2012 .Standard Procedure for Water and Wastewater Sampling are
presented in Table 3.7
Table 3.7
Methodology for Sampling and Analysis of Water
SamplingLocation& Period
SamplingParameters
SampleCollection
AnalysisEquipment
Sensitivity/Detection
Methodology
Groundwater– 6 locations
Surfacewater – 4locations
Grab
pH Manualsampling inCarboy/glassbottles
pH meter 2.0 APHA 22nd Ed. 4500pH, IS 3025(Part11):1983(RA 2002)
Temp (°C) Thermometer 5oC APHA 22ndEd.,2550B
Colour (pt.co.Scale)
Spectrophotometer
ColourUnit
APHA 22nd Ed.,2120 B & C
Odour Manual Qualitative APHA 22nd Ed.,2150
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 39
SamplingLocation& Period
SamplingParameters
SampleCollection
AnalysisEquipment
Sensitivity/Detection
Methodology
SamplingOctober to –December2018
Turbidity,(NTU)
Nephlometer 0.1 NTU APHA 22nd Ed.,2130 BIS 3025(Part10):1984, (RA 2012)
TotalDissolvedSolids
ElectronicBalance
5 mg/l APHA 22nd Ed. 2540CIS 3025(Part16):1984
EC ConductivityMeter
10 µS/cm APHA 22nd Ed.2510-B
Oil & Grease ElectronicBalance
0.2 mg/l APHA 22nd Ed.,5520 BIS 3025(Part39):1991 (RA 2003)
BOD Incubator,Titration
2.0 mg/l IS 3025(Part44):1993(RA 2009), Amds.1
COD Titration 5.0 mg/l APHA 22nd Ed.,5220BIS 3025(Part58):2006
Phenoliccompounds
Spectrophotometer
0.001 mg/l APHA 22nd Ed.,5530 CAPHA 22nd Ed.,5530 DIS 3025 (Part43)1992 (RA 2003)
TotalAlkalinity
Titration 5.0 mg/l APHA 22nd Ed. 2320B.IS 3025(Part23):1986
Total Hardness Titration 2.0 mg/l IS 3025(Part21):2009APHA 22nd Ed.2340 C.EDTA -TitrimetricMethod
Calcium Titration 2.0 mg/l APHA, 22nd Ed.,3500-B,EDTA TitrimetricMethod
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 40
SamplingLocation& Period
SamplingParameters
SampleCollection
AnalysisEquipment
Sensitivity/Detection
Methodology
IS 3025(Part40):1991 (RA 2003)
Magnesium Titration 2.0 mg/l APHA 22ndEd.,3500- Mg-BIS3025(Part46):1994(RA 2009)
Chlorides asCl
Titration 5.0 mg/l APHA 22nd Ed. 4500Cl. BIS 3025(Part32):1988
Nitrates asNO3
Spectrophotometer
0.1 mg/l APHA 22ndEd.,4500-NO3-B(UV Screeningmethod)
Sulphates asSO4
Spectrophotometer
1.0 mg/l APHA 22nd Ed.,4500SO42 –EIS 3025(Part24):1986 (1st Rev)(RA 1992) (TurbidityMethod)
Phosphates asPO4
Spectrophotometer
0.1 mg/l APHA 22nd Ed.,4500- P-DIS 3025(Part31):1988 (RA 2003)
Fluorides as F Ion Meter 0.1 mg/l EPA 340.2(By Ion SelectiveElectrode)
Sodium AAS 0.5 mg/l APHA, 22nd Ed.,3500-Na, B, IS3025(Part 45):1993
Potassium AAS 1 mg/l APHA22ndEd.,3500-K, BIS 3025(Part45):1993
Iron AAS 0.1 mg/l APHA, 22nd Ed.,3111-B,IS 3025(Part53):2003 (RA 2009)
Manganese AAS 0.05 mg/l APHA, 22nd Ed.3500-Mn, B,IS 3025(Part
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 41
SamplingLocation& Period
SamplingParameters
SampleCollection
AnalysisEquipment
Sensitivity/Detection
Methodology
59):2006Cyanide Ion Meter 0.02 mg/l APHA 22nd Ed.,
4500-CN- F(by ISE)IS 3025(Part27):1986 RA 2003
Copper AAS 0.02 mg/l APHA, 22nd Ed.,3111-BIS 3025(Part42):1992
Nickel AAS 0.01 mg/l APHA 22nd Ed.,3111BIS 3025 (Part54):2003 (RA 2009)
Lead AAS 0.001 mg/l APHA 22nd Ed.,3111BIS 3025(Part47):1994 (RA 2009)
Zinc AAS 0.2 mg/l APHA, 22nd Ed.,3111-BIS 3025(Part49):1994(RA 2009)
TotalChromium
AAS 0.02 mg/l APHA 22nd Ed.,3111BIS 3025(Part52):2003 (RA 2009)
Observations
The characteristics of surface water samples are presented in Table 3.8 and that of
ground water in Table 3.9. These tables have desirable as well as permissible limits of
Indian Standard for each parameter. It was observed that the characteristics of the surface
and ground water samples were found to be within the permissible limits of Indian
Standards except the total coliforms in surface water samples which may be due to the
human activities observed during sampling and requires disinfection before use for
drinking purpose.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 42
TABLE 3.8Water Quality: Surface Water Samples
Parameters
Units SW1 SW2 SW3 SW4 As Per IS 10500 of 2012
MangalanaPond
ChamardiPond
Rangholiriver
Ukhrala
Acceptable PermissiblePond Pond River stream pond
pH - 7.80 7.90 7.70 8.15 6.5-8.5 NR
Temperature °C 28 28 28 28 - -
Colour Hazan <5 <5 <5 <5 5 25
Odour - U/O U/O U/O U/O 5 10
Turbidity NTU 0.8 1.1 0.5 0.8 1 5
EC ms/cm 1.02 1.29 0.64 1.45 - -
Total Dissolved Solids mg/l 658 822 408 920 500 2000
Oil & Grease mg/l <0.1 <0.1 <0.1 <0.1 - -
COD mg/l 20 36 16 26 - -
Dissolved Oxygen mg/l 5.5 4.5 5.7 5.6 - -
BOD mg/l 9 12 5 8 - -
Phenolic compound mg/l <0.001 <0.001 <0.001 <0.001 - -
Total Alkalinity mg/l 123 143 34 66 200 600
Total Hardness mg/l 366 319 132 440 200 600
Calcium mg/l 47 78 22 40 75 200
Magnesium mg/l 18 12 5 13 30 100
Chloride mg/l 112 237 136 221 250 1000
Sulphates mg/l 60 80 32 86 200 400
Phosphates mg/l 6 8 3 9 0.05 NR
Fluorides mg/l <0.1 <0.1 <0.1 <0.1 1 1.5
Sodium mg/l 75 141 80 123 - -
Potassium mg/l 18 36 20 41 - -
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 43
Iron mg/l 0.3 0.2 0.2 0.3 0.3 1
Manganese mg/l <0.05 <0.05 <0.05 <0.05 0.1 0.3
Cyanide mg/l <0.02 <0.02 <0.02 <0.02 0.001 0.002
Copper mg/l <0.02 <0.02 <0.02 <0.02 0.05 1.5
Lead mg/l <0.01 <0.01 <0.01 <0.01 0.05 NR
Nitrates mg/l 34 36 16 6 45 NR
Nickel mg/l <0.01 <0.01 <0.01 <0.01 - -
Zinc mg/l <0.2 <0.2 <0.2 <0.2 5 15
Chromium mg/l <0.02 <0.02 <0.02 <0.02 0.05 NR
Total Coliform MPN/100ml 38 43 41 49 - -
Feacal Coliform(MPN/100ml)
MPN/100ml21 27 26 33
- -
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 44
TABLE 3.9WATER QUALITY: GROUND WATER SAMPLES
Parameters Unit GW 1 GW 2 GW 3 GW 4 GW 5 GW 6 As per IS 10500 OF 2012
Navagam Dambhaliya Ukhrala Manglana Chogath PipaliyaDesirable Permissible
pH - 7.95 7.8 8.1 7.25 7.82 7.33 6.5-8.5 NR
Temp °C 28 28 28 28 28 28 - -
Colour (CU) Hazan <5 <5 <5 <5 <5 <5 5 25
Odour - U/O U/O U/O U/O UO UO AG AG
Turbidity NTU 0.4 0.5 0.5 0.2 0.8 0.4 1 5
EC ms/cm 3.09 2.88 2.57 1.53 3.16 2.25 - -
Total Dissolved mg/l 1976 1860 1644 961 2027 1430 500 2000
Oil & Grease mg/l <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 - -
Phenoliccompound (mg/l)
mg/l<0.001 <0.001 <0.001 <0.001 <0.001 <0.001
- -
Total Alkalinity(mg/l)
mg/l273 272 136 159 178 106
- -
Total Hardness(mg/l)
mg/l480 450 492 210 532 488
- -
Calcium mg/l 152 145 107 52 75 98 - -Magnesium mg/l 24 28 54 19 35 10 200 600
Chloride mg/l 856 783 630 406 792 563 200 600
Sulphates mg/l 86 91 132 43 87 46 75 200Phosphates mg/l 0.6 1.6 0.8 2.4 0.85 0.1 30 100
Fluorides mg/l 0.3 0.2 <0.1 0.2 0.4 0.4 250 1000Sodium mg/l 487 440 297 262 428 289 200 400
Potassium mg/l 36 62 32 12 116 25 0.05 NR
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 45
Iron mg/l 0.9 0.3 0.22 0.4 0.35 0.8 0.3 1Manganese mg/l <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 0.1 0.3
Cyanide mg/l <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 0.001 0.002Copper mg/l <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 0.05 1.5Lead mg/l <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.05 NR
Nitrates mg/l 24 21 6 12 20 2 45 NRNickel (mg/l) mg/l <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 - -
Zinc (mg/l) mg/l 0.3 0.5 0 0.5 0.4 0.2 5 15
Chromium mg/l <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 0.05 NR
Total Coliform(MPN/100ml)
MPN/100mlAbsent Absent Absent Absent Absent Absent
- -
Feacal Coliform(MPN/100ml)
MPN/100mlAbsent Absent Absent Absent Absent Absent
- -
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 46
3.5 NOISE ENVIRONMENT
In this proposed project movement of raw materials, products, fuels, tools &tackles will
takes place for its manufacturing process. The movement of personnel from their
residence to industry would also result in a moderate increase in the traffic, which would
result in drastic change in existing traffic pattern and noise levels of the area. Noise level
monitoring was carried out using SLM100 Sound Level Meter (Envirotech Instrument
(type II) at eightlocations for 24 hours at hourly intervals, during the study period. The
day time limit is for 6 am to 10 pm and night time limit is for 10 pm to 6 am. The noise
sampling locations are given in Table 3.10 and shown in Figure 3.5.
Table3.10
Noise Level Sampling Stations
Sr.
No.
Description of monitored
stations
Sample
code
Distance from
proposed plantDirection
1. Project Site N-1 ---- ----
2. Dambhaliya N-2 2.5 Km. W
3. Bhangadh N-3 5.7 Km. E
4. Manglana N-4 5.0 Km. SE
5. Navagam N-5 4.0 Km. S
6. Ukharala N-6 4.5 Km. SW
7. Chamardi N-7 2.5 Km. N
8. Chogath N-8 4.5 Km. NW
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 47
Source: SOI Toposheet
Figure 3.5: Map showing Noise level Monitoring Station
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 48
TABLE 3.11Measured Noise Levels at Monitored Stations
Noise Level in dB(A)
Location ID N1 N2 N3 N4 N5 N6 N7 N8
Time Measured levels dB(A)
6:00 Day 56.6 52.2 52.2 50.7 52.0 53.1 48.9 48.0
7:00 60.1 53.5 53.5 52.7 54.5 56.8 52.6 52.0
8:00 64.5 55.2 55.6 56.4 58.1 60.5 55.6 54.1
9:00 60.2 55.7 57.8 55.8 59.2 58.5 56.5 56.9
10:00 67.4 59.8 64.4 57.3 59.7 64.6 57.3 57.8
11:00 62.9 56.7 66.5 58.6 60.1 59.9 52.7 55.8
12:00 68.8 57.7 65.8 58.8 61.8 66.1 60.0 55.9
13:00 66.1 55.8 60.6 57.6 59.8 62.6 58.8 57.8
14:00 69.0 57.8 63.5 60.4 62.5 66.5 59.3 55.4
15:00 67.1 59.0 60.7 56.5 58.6 63.5 61.2 53.6
16:00 65.9 56.0 62.5 59.6 57.8 61.2 60.2 55.8
17:00 64.0 52.0 59.7 57.8 55.2 60.5 59.9 49.2
18:00 66.9 55.4 60.4 58.6 57.8 59.0 57.8 49.3
19:00 62.5 53.2 58.9 52.6 55.6 57.8 52.9 47.8
20:00 63.5 51.6 57.8 51.5 53.6 54.6 55.5 49.8
21:00 Night 58.1 53.0 56.9 50.0 51.0 58.9 49.2 46.6
22:00 61.4 51.0 55.6 54.6 55.4 55.6 50.2 47.8
23:00 54.1 51.4 55.2 48.6 49.2 56.8 47.2 44.9
0:00 50.2 52.2 54.6 53.3 53.5 55.9 48.7 46.6
1:00 51.4 49.1 51.1 47.2 47.7 55.2 45.9 45.8
2:00 57.3 48.8 51.5 52.0 52.6 53.5 46.9 45.2
3:00 51.6 47.3 49.2 47.0 48.0 52.5 46.4 43.7
4:00 57.6 46.9 51.0 53.8 55.0 56.6 46.9 44.3
5:00 53.6 49.7 51.6 49.2 49.9 54.0 47.7 45.1
Ld 64.4 55.4 60.0 56.3 57.8 60.3 56.6 53.3Ln 55.0 49.9 53.0 50.6 51.4 55.4 47.7 45.6
Observation
The results of noise levels are given in Table 3.11. The results showed that noise levels
measured at all eight stations (N-1, N-2, N-3, N-4, N-5, N-6, N-7 and N-8) are low and
well within limit of either 65.0 dB(A) for Residential Area or 75.0 dB(A) for Industrial
Area as given in MoEF Gazette notification for National Ambient Noise Level Standard.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 49
Ambient Noise Level Standards
Ambient Air Quality standards in respect of noise have been notified by the Ministry of
Environment & Forests vide Gazette Notification Dated 26th December 1989. It is based
on a weighted equivalent noise level (Leq). National Ambient Noise Level Standards are
given below in Table 3.12.
Table 3.12
National Ambient Noise Level Standards
AreaCode
Category of AreaLimits in dB(A) Leq
Day time Night timeA Industrial Area 75 70
B Commercial Area 65 55
C Residential Area 55 45D Silence Zone** 50 40
**Silence zone is defined as area up to 100 meters around premises of hospitals,educational institutions and courts. Use of vehicle horns, loud speakers and burstingof crackers are banned in these zones.
3.6 SOIL QUALITY
The present study on soil quality establishes the baseline characteristics in the study area
surrounding the project site. The study has been addressed with the following objectives.
• To determine the base line characteristics
• To determine the soil characteristics of proposed project site.
• To determine the impact of industrialization/urbanization on soil characteristics
• To determine the impacts on soils from agricultural productivity point of view.
For studying the soil types and soil characteristics, 4 sampling locations were selected to
assess the existing soil conditions representing various land use conditions and geological
features. The methodology adopted for sampling and analysis of soil quality is as
mentioned in Table 3.13.Samples were collected form selected points by manually using
auger. Undisturbed top soil was collected in containers. The sampling locations are given
in Table 3.14 and shown in Figure 3.6. The physico-chemical characteristics of soil
samples are reported in Table 3.15.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 50
Table-3.13: Analytical methodology for soil samples
Table 3.14: Soil Sample Monitoring Station
Sr. No. Sampling Sites Station CodeDistance fromproposed plant
Direction
1. Dhambhaliya S – 1 2.5 Km. W
2. Bhangadh S – 2 5.5 Km. E
3. Navagam S – 3 4.0 Km. S
4. Ukharala S – 4 4.5 Km. SW
SamplingLocation& Period
SamplingParameters
AnalysisEquipment
Sensitivity/Detection
Methodology
4 soilsampleswerecollectedduringOctober toDecember2018
pH pH meter 1.0 IS 2720 (Part 26):1987 (RA2011)
ElectricalConductivity
Conductivity Meter 10 µS/cm IS 14767:2000 RA 2010
Nitrogen (as N) Spectrophotometer 5 mg/kg IS 14684:1999 (RA 2000)Phosphorous (as P) Spectrophotometer 5 mg/kg IS 10158-1982 (RA 2009)Potassium (as K) AAS 5 mg/kg USEPA 3050BOrganic Carbon Titrimetric 5 mg/kg IS 2720 (Part 22):2002Grain SizeDistribution
-- -- IS 2720(P-4):1985
Texture Class -- -- U.S. Texture TriangleBulk Density Glass ware -- IS 2720: Part 28/29: 1974
(By Cylinder method)Calcium Titrimetric 5 mg/kg USEPA 3050BMagnesium Titrimetric 5 mg/kg USEPA 3050BSodium AAS 5 mg/kg USEPA 3050BIron AAS 5 mg/kg EPA 3050B & EPA 7000BCopper AAS 5 mg/kg EPA 3050B & EPA 7000BManganese AAS 5 mg/kg EPA 3050B & EPA 7000BZinc Titrimetric 5 mg/kg USEPA 3050B
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 51
Source: SOI Toposheet
Figure 3.6: Location of Soil sampling Stations
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 52
Table 3.15
Physio-Chemical Properties of Soil
Parameters UnitS1 S2 S3 S4
Dhambhaliya Bhangadh Navagam Ukharala
Physical Properties
Texture - Clay Slit Clay Slit Clay Slit Clay
Sand % 42 23 21 24
Silt % 14 32 31 30
Clay % 44 45 48 46
Bulk Density (BD) gm/cm3 1.8 2.3 2.1 2.2Water Holding Capacity(WHC) % 26
3032
30
Chemical Properties
pH5%Slurry 8.34 8.22 7.8 7.82
Conductivity (EC) ms/cm 1.6 1.8 1.64 1.75
Organic Matter % 0.51 0.48 0.46 0.43
Organic Carbon % 0.68 0.62 0.65 0.65
Sodium as Na mg/kg 776 922 706 687Calcium as Ca mg/kg 748 936 468 832Magnesium as Mg mg/kg 294 299 316 371Zinc as Zn mg/kg 69.5 68.6 69.8 68.7
Copper as Cu mg/kg <5 <5 <5 <5
Manganese as Mn mg/kg <5 <5 <5 <5
Iron as Fe mg/kg 26 28 25 27
Nitrogen as N mg/kg 86 62 71 87
Phosphorus as P mg/kg 74 50 61 75
Potassium as K mg/kg 108 39 52 104
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 53
Standard Soil Classification
Standard soil classification regarding agriculture, in view of its test parameters, is
detailed below in Table 3.16. The use of soil for agriculture or for other use may be
decided on basis of soil characteristics.
Table 3.16
Standard Soil Classification
Sr.No.
Test Parameters Classification
1. pH
< 4.50 extremely acidic4.51-5.00 very strongly acidic5.01-5.50 strongly acidic5.51-6.00 moderately acidic6.01-6.50 slightly acidic6.51-7.30 neutral*
7.31-7.80 slightly alkaline*7.81-8.50 moderately alkaline8.51-9.0 strongly alkaline> 9.0 very strongly alkaline(*tolerable to crops)
2.
Salinity orElectricalConductivity(mmhos/cm)(1mmhos/cm = 640ppm)
upto 1.00 average1.01-2.00 harmful togermination2.01-3.00 harmful to crops> 3.00 sensitive to salts
3.Organic Carbon(%)
upto 0.30 very less0.31-0.40 less0.41-0.50 medium0.51-0.80 on an averagesufficient
0.81-1.00 sufficient> 1.0 more than sufficient
4. Nitrogen (kg/ha)upto 50 very less51-100 less101-150 good
151-300 better> 300 sufficient
5.Phosphorous(kg/ha)
upto 15 very less16-30 less31-50 medium
51-65 on an averagesufficient65-80 sufficient> 80 more than sufficient
6. Potassium (kg/ha)0 very less120-180 less181-240 medium
241-300 average301-360 better> 360 more than sufficient
Source: Hand book of Agriculture ICAR (Indian Council of Agriculture Research)
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 54
OBSERVATIONS
The observations of soil characteristics are discussed parameter wise below;
• Texture of soil samples in the study area are clay and slit clay nature
• The bulk density of soil samples collected from the all sampling locations are in
the range of 1.8 to 2.3 g/cc
• Soil samples have pH values between 7.8 to 8.34. The pH values are indicating
nature of soil samples is neutral to alkaline.
• Soil samples from agricultural land have conductivities between 1.6 to 1.8 ms/cm
• The organic matter present in the collected soil samples are in the range of 0.43 to
0.51%. These values represent moderate fertility of soils.
• The available Nitrogen values in the soil samples are ranged between 62-87 kg/ha
which indicate that the less content of available nitrogen the study area
• Soil sample from land have concentration of Available Phosphorous values ranged
between 50 to 75 kg/ha
• Soil sample from waste land have concentration of Available Potassium values
range between 39 to 105 kg/ha
Characteristic of sampling locations land soil is a little deficient in nutrients concentration.
3.7 LAND USE PATTERN
Satellite imagery based land use pattern studies have been carried out to analyze the
impacts on land due to the proposed expansion activities in the study area and to give
recommendations for optimizing the future land use pattern and associated Impacts.
Remote Sensing’ has proved as a powerful tool in the field of Environment Impact
Assessment Studies in recent times. The Satellite data provides reliable and accurate
information on natural resource like water, soil, forest, etc. which forms the baseline
information; prerequisite for systematic assessment of various environmental impacts.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 55
Remotely sensed data provides information for systematic analysis of land use – land
cover characteristics using synoptic and multi spectral coverage of the terrain.
Geographical Information System (GIS) has been proved as a powerful tool in the field of
natural resources management over the years. GIS technologies having capability of data
storage, retrieval and manipulation can play an important role in evolving the suitable
methods of arriving at alternate scenarios for natural resources development and
environmental planning.
Recent advances in the fields of remote sensing and GIS provide useful tools in
environment impact assessment studies. These two new technological tools have emerged
to meet the ever increasing demand for more precise and near real time information. An
integrated element for generating map information is the combination and comparison of
variety of data derived from different sources such as remotely sensed imagery, ground
survey and existing topographic and other maps.
An attempt has been made to generate a land use/ land cover map of the study area using
SOI topographical sheets, remotely sensed images and field survey data. The generated
information has been integrated in GIS.
Data Used: In order to strengthen the baseline information on existing land use pattern,
the following data along Latitude: 210 48’ 30.29” Nand Longitude: 710 54’ 07.37 Eis
used.
Collateral Data: Survey of India Degree sheet No NF 42-12were also used to study the
Land use / Land cover of the study area.
Methodology
Salient features of the methodology adopted are given below:
Acquisition of satellite data.
Preparation of base map from Survey of India toposheets.
Data analysis using visual interpretation techniques.
Ground truth studies or field checks.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 56
Finalization of the map.
Digitization using heads up vectorisation method.
Area calculation for statics generation.
The interpretation of the satellite imagery was done by heads up vectorisation using
various interpretation keys. Tone, color, texture, structure, and association criteria are
used for categorization different Land use / Land cover classes to their respective units.
The various interpretation keys are cross verified on ground for refining the map.
Land Use / Land Cover Details:
The Satellite imagery procured is given in Figure 3.7. The land use / land cover map of
the entire study area are given Figure 3.8 whereas statically breakup of land use / land
cover classes is given Table 3.17.
Figure 3.6: Satellite Imagery
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 57
Figure 3.7: Land Use/Land Cover map
Table 3.17 Land use/Land Cover Analysis
Sr.
No
Land use/ Land cover Area in Ha. %
1 Coastal Wetland 175 1.2%2 Cropland 0 0.0%3 Fallow land 10833 73.1%4 Reservoirs/ Lakes/ Ponds 7 0.0%5 River/ Stream/ Canals 519 3.5%6 Rural 207 1.4%7 Scrub land 3016 20.4%8 Urban 63 0.4%
Total 14820 100
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 58
Geology
Regional Geology:
The state of Gujarat comprises an area of approximately 1,96,000 sq.km and is enclosed
within the North Latitude 20°10° to 24° 50° and East Longitude 68° 40° to 74° 40°.
Geologically Gujarat provides a wide spectrum of rock types of different ages. All the
important lithological types Ignious, Sedimentry and Metamorphic occur within the state.
Local Geology
Bhavnagar is a coastal city on the eastern coast of Saurashtra, also known
as Kathiawar. It has an average elevation of 24 metres (78 ft). It occupies an area of
3.3 km2 (20.6 sq mi). The general slope dips towards the northeast at the apex of Gulf of
Khambhat. The region of Saurashtra is a geologically active part of West India, and falls
in the seismic zone 3 of the Zoning Map of the Bureau of Indian Standards.
Flora and Fauna
Natural Flora and Fauna are important biotic components for environment. The various
terrestrial biological components which can be influenced by proposed activities in the
form of emissions.
No National Park, Sanctuary, Elephant or Tiger Reserve is situated within 10 km radius
area surveyed around the project site. No migratory route of wild animals has been
reported to have existed in the study area. The details of Flora and Fauna are attached as
Annexure VII
3.8 SOCIO‐ECONOMICS OF THE STUDY AREA
The socio-economic component of environment with reference to human interests.
Aesthetics and cultural attributes need to be studied while delineating Environmental
management Plan for achieving desired target without impairing the quality of life.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 59
The study area of 10 km radial zone mainly falls in the District Bhavnagar, Gujarat.
There are total 31 villages in study area. The latest available data has been complied to
generate the existing socio‐economic scenario of the study area. Information on
socio‐economic profile was collected from the Govt. Agencies, Census book, Statistical
abstract and health agencies.
Demographic Profile
Total Population of the Study area as per Census of India, 2011 is 63,191. The total
number of household being 12,006. Total Male Population of the Study area is 32,671
and total Female Population of the Study Area is 30,520. Village-wise details of
population are given in Table 3.18. The number of females per 1000 males is 934 as
compared Gujarat (919) and India (933) The Sex Ratio of the Study area found to be higher
than State and slightly higher than India (Figure 3.9). Out of the total population, 7%
populations are belongs to backward class in the study area (Figure 3.10).
Summary of Demographic Structures in Study Area
Description Total % of the total Population
Total Population 63191 -
No. of Households 1200619%
Male Population 3267152%
Female Population 3052048%
Schedule caste 41647%
Schedule Tribe 1420%
Male literates 2379238%
Female literates 1693427%
Total literates 4072664%
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 60
Literacy Rate
Literacy rate of the study area is 64.4% Distribution of male 77.82 % and female literacy
rate is 55.48% in the study zone. The comparative graph shown in Figure 3.10.This
indicates that the literacy rate is low for male as well as female in study area as compared
to Gujarat state.
Figure 3.9: Sex Ratio Comparison
Figure 3.10: Breakup of SC & ST in the study area (Census 2011)
910
915
920
925
930
935
Study Area Gujarat India
934.16
919
933
Sex Ration Comparision
93%
7% 0%
SC ST & Other PopulationComparision in %
Others
SC
ST
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 61
Figure 3.11: Literacy rate in Study area (Census 2011)
Economic Resource Base
The employment pattern mainly depends upon its economically active group i.e. the
working populations involved in different economically productive activities. The total
workers further categorized as main worker, cultivated worker, Agricultural labour,
marginal and the non-working population.
The workers coming under the main and marginal workers category are cultivators,
agricultural labors and those engaged in livestock, forestry, fishing, hunting, and
plantations, manufacturing, processing, servicing and repairs in household industry,
construction trade and commerce, transport, storage & communication, and other
services. Out of the total population 26% comes under the main workers category from
the villages near by proposed project site and majority are non-worker (43%). Main
workers are further classified into 4 categories viz., cultivators, agricultural laborers and
household workers and other main workers. The employment pattern of the study area is
depicted in Figure 3.12.
0
10
20
30
40
50
60
70
80
90
Literacy Male % Literacy Female %
Gujrat 85.75 69.68
Study Area 72.82 55.48
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 62
Figure 3.12: Vocational Pattern of the Study Area
26%
5%9%
0%
12%5%
43%
Vocational Pattern of the Study Area
Main Worker
Cultivator Worker
Agril Lab
HH industry
Other Worker
Marginal Worker
Non-Worker
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 63
Table 3.18Village wise Demographic Structure of the Study Area
S.N. VillageName
Taluka No. ofHouseholds
Population SC ST Literate
Total M F M F
1 Anandpur vallabhipura 69 333 161 172 0 0 136 123
2 Rajpara (Bhal) vallabhipura 99 435 233 202 23 6 209 157
3 Pati vallabhipura 100 569 296 273 30 0 185 161
4 Juna Rampar vallabhipura 237 1177 610 567 63 0 463 347
5 Chamardi vallabhipura 704 3658 1921 1737 99 0 1412 951
6Vallabhipur(M) vallabhipura 3025 15852 8183 7669 782 75 6278 4663
7 Rajpipala Gadhada 463 2360 1209 1151 155 22 744 526
8 Dhamnaka Umrala 89 524 274 250 34 0 180 121
9Chogath(Thapnath) Umrala 1352 7397 3772 3625 381 0 2641 1827
10 Dambhaliya Umrala 57 263 144 119 0 0 106 68
11 Timba Umrala 46 248 132 116 0 0 102 56
12 Dharuka Umrala 449 2106 1051 1055 149 2 687 510
13 Ratanpar Umrala 158 887 463 424 112 0 353 265
14 Golrama Umrala 232 1116 561 555 21 0 392 284
15 Bajud Umrala 644 3152 1621 1531 240 0 1228 887
16 Devaliya Bhavnagar 154 815 414 401 0 0 250 135
17 Paliyad Bhavnagar 182 997 532 465 0 0 358 193
18 Sendurda Shior 56 266 136 130 0 0 103 63
19 Ukharla Shior 162 919 482 437 87 0 323 189
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 64
20 Paldi Shior 285 1457 749 708 152 7 550 384
21Navagam(Mota) Shior 149 753 389 364 44 0 290 186
22 Maglana Shior 87 441 231 210 0 0 167 134
23 Ghanghali Shior 835 4462 2305 2157 197 12 1494 1028
24 Bhangadh Shior 74 443 236 207 0 0 177 152
25 Nesda Shior 675 4161 2241 1920 109 8 1681 1087
26 Bholad Shior 233 1412 736 676 126 0 483 319
27 Vadiya Shior 256 1478 755 723 279 0 595 426
28 Pipaliya Shior 416 1953 1005 948 590 10 769 548
29 Nana Surka Shior 361 1683 850 833 128 0 643 489
30 Kantodiya Shior 182 942 493 449 235 0 428 385
31 Vav Shior 175 932 486 446 128 0 365 270
Total 12006 63191 32671 30520 4164 142 23792 16934
(Source: Census 2011)
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 65
Table 3.19 : Employment Pattern
S.N.
NAME OF THEVILLAGE
TALUKA
TOTAL MAINWORKERS
CULTIVA-TORS
AGRILLAB
HHINDUSTRY
OTHERWORKERS
MARGINALWORKER
NONWORKERS
M F M F M F M F M F M F M F
1 Anandpurvallabhipura 104 17 45 4 8 9 0 0 51 4 1 18 56 137
2 Rajpara (Bhal)vallabhipura 135 3 72 0 0 0 0 0 63 3 19 11 79 188
3 Pativallabhipura 148 10 48 0 66 5 0 0 34 5 4 2 144 261
4 Juna Ramparvallabhipura 325 40 69 4 106 15 0 0 150 21 6 10 279 517
5 Chamardivallabhipura 1086 83 157 3 451 42 13 0 465 38 26 224 809 1430
6 Vallabhipur (M)vallabhipura 4537 742 471 8 811 358 34 2 3221 374 237 300 3409 6627
7 Rajpipala Gadhada 690 211 179 23 325 170 5 0 181 18 9 92 510 848
8 Dhamnaka Umrala 152 14 52 3 39 9 2 0 59 2 1 1 121 235
9Chogath(Thapnath) Umrala 2222 770 382 91 726 564 81 9 1033 106 102 358 1448 2497
10 Dambhaliya Umrala 56 4 23 0 0 0 0 0 33 4 3 1 85 114
11 Timba Umrala 55 1 30 0 13 0 0 0 12 1 1 8 76 107
12 Dharuka Umrala 638 98 108 3 425 85 1 0 104 10 22 475 391 482
13 Ratanpar Umrala 253 4 62 1 141 2 0 0 50 1 11 158 199 262
14 Golrama Umrala 282 9 111 1 26 3 80 2 65 3 48 57 231 489
15 Bajud Umrala 919 280 260 62 194 114 15 6 450 98 16 68 686 1183
16 DevaliyaBhavnagar 247 26 33 0 130 22 0 0 84 4 45 207 122 168
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 3:Description of the
Environment
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 66
17 PaliyadBhavnagar 318 184 59 6 166 167 0 0 93 11 7 21 207 260
18 Sendurda Shior 83 10 24 4 14 5 0 0 45 1 0 0 53 120
19 Ukharla Shior 266 78 48 2 96 62 1 1 121 13 12 9 204 350
20 Paldi Shior 377 99 26 2 58 54 1 0 292 43 4 3 368 606
21 Navagam (Mota) Shior 205 11 54 1 18 7 0 0 133 3 17 32 167 321
22 Maglana Shior 133 4 75 0 35 0 0 0 23 4 0 0 98 206
23 Ghanghali Shior 1352 557 160 107 408 289 0 1 784 160 20 321 933 127924 Bhangadh Shior 81 5 40 1 24 4 1 0 16 0 47 10 108 192
25 Nesda Shior 1157 124 284 7 305 65 25 2 543 50 14 184 1070 1612
26 Bholad Shior 425 221 58 22 54 50 1 1 312 148 39 137 272 318
27 Vadiya Shior 379 94 84 3 45 68 1 0 249 23 22 102 354 527
28 Pipaliya Shior 560 329 139 98 180 201 9 2 232 28 42 138 403 481
29 Nana Surka Shior 472 189 128 28 190 146 4 5 150 10 1 0 377 644
30 Kantodiya Shior 292 52 73 2 102 46 0 0 117 4 0 2 201 395
31 Vav Shior 267 73 102 3 60 67 5 0 100 3 0 21 219 352
Total 18216 4342 3456 489 5216 2629 279 31 9265 1193 776 2970 13679 23208Source: Census 2011
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 4:Anticipated Environmental
Impacts & MitigationMeasures
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 67
CHAPTER 4:ANTICIPATED ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
4.1 IDENTIFICATION OF IMPACTS
Identification and prediction of Impacts is the most important component in the
Environmental Impact Assessment studies. The environmental impacts can be
categorized as either primary or secondary. Primary impacts are those, which are
attributed directly due to the project and secondary impacts are those, which are
indirectly induced and typically include the associated investment and changed pattern of
social and economic activities due to proposed activities.
The environmental impacts have been assessed assuming that the pollution due to the
existing activities at Village: Chamardi, Taluka:Vallabhipur, District:
Bhavnagar(Gujarat), where the project site has been identified and covered under the
present environmental scenario established by the monitored baseline data. During
construction and operation phase of proposed activities various impacts on environmental
parameter will be studied to estimate the impacts on environment and apply mitigation
measures. Several scientific techniques and methodologies are available to predict
impacts of proposed activities on physical, ecological and socio-economic environments.
Such predictions are superimposed over the baseline (Pre-project) status of environmental
quality to derive the ultimate (Post-project) scenario of environmental conditions.
The Summary of Matrix Valued Ecosystem Components of Concerns (VECs) is given in
below .
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 4:Anticipated Environmental
Impacts & MitigationMeasures
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 68
4.1.1 Issues Scoping / Pathway Analysis - Summary of Matrix Valued Ecosystem
Components of Concerns (VECs)
EnvironmentalComponents of
Concern (ECCs)
Pathway ofConcern
PossiblePathways
VEC Rationale for Inclusion / Exclusion asValued Ecosystem Component (VECs)
Yes No Yes No
Air Quality √ Construction &Operation ofPlant
√ Included as a VEC – National standardsexist for ambient air quality. Potentialimpact on air quality during construction(dust, vehicle emissions) andoperations(Sponge Iron)
Water Quality √ Construction &operation plant
√ Included as VEC – Proper sanitationarrangement for construction workers.No discharge of waste water
GroundwaterResourcesIrrigation projects
√ Nil √ Excluded as a VEC – No ground waterwill be used for construction & operationof the plant. No irrigation project in studyarea. No discharge of waste water.Recharging of ground water by adoptingrain water harvesting system.
Soil Quality / Solidwaste.
√ Constructionand operationof plant
√ Included as a VEC – Preservation ofexcavated top soil during construction forplantation purpose.Use of construction debris in roadmaking.Disposal of solid waste generated duringoperations by reusing in process andother activities.Storage of solid waste in scientificmanner.
Fauna and Flora √ Nil √ Excluded as a VEC –No project site specific impact on flora &fauna.The marginal impact on the environment,if any will be taken care off by thedevelopment of the green belt / plantationby M/s K. B. Ispat Hence no impact dueto the proposed project.
EnvironmentallySensitive Areas
√ Nil √ Excluded as a VEC – Noenvironmentally sensitive areas in studyarea of proposed project.
Ambient Noise √ ConstructionandOperations ofPlant
√ Included as VEC – Marginal impact ofnoise on surrounding areas duringconstruction and operations, vehiclemovements.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 4:Anticipated Environmental
Impacts & MitigationMeasures
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 69
Land Use √ Nil √ Excluded as a VEC – No change inLand use.
Archaeological /Heritage Resources
√ Nil √ Excluded as a VEC – No archeologicalor heritage structures in study area ofproposed plant .
Traffic √ ConstructionandOperations ofPlant
√ Included as VEC – Marginal impactfrom construction and operations relatedtraffic on existing traffic patterns.
4.2 CONSTRUCTION PHASE
Air Environment
Impact on Air Quality
During construction phase, dust will be the main pollutant, which will be generated
from the site development activities and vehicular movement on the road. Further,
concentration of NOx and CO may also slightly increase due to increased vehicular
traffic. However, change in ambient concentrations of air quality will be insignificant
and temporary. As most of the construction equipment will be mobile, the emissions
are likely to be fugitive. The impacts will be localized in nature and the areas outside
the project boundary are not likely to have any significant adverse impact.
Air Pollution Control Measures
During dry weather conditions, it is necessary to control the dust generated by
excavation and transportation activities. This will be achieved by regular water
sprinkling. Ambient air concentrations of SO2 and NOx are expected to increase due to
operation of construction machineries such as bulldozers, pay loaders, trucks etc. These
levels are expected to be insignificant as these machines will be operated intermittently
and only day time. Most of the equipment and machineries will be mobile and hence, the
emissions will be mostly fugitive. It will be ensured that vehicles and machineries are
properly maintained to minimize smoke in the exhaust emissions. Additional air
pollution control measures include the following:
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 4:Anticipated Environmental
Impacts & MitigationMeasures
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 70
• Sprinkling of water at regular intervals preferably using truck-mounted sprinklers
along the roads and work zone areas;
• Electrical power shall be made available near to the site. Attempts to be made to
utilize the electrically powered machinery to the extent possible to minimize the
emissions of SO2 and NOx.
Noise Environment
Impact on Noise Levels
The major sources of noise during the construction phase are vehicular traffic,
construction equipment like dozers, scrapers, concrete mixers, cranes, pumps,
compressors, pneumatic tools, saws, vibrators etc. The operation of this equipment will
generate noise ranging between 85-90 dB (A) near the source. These noise levels will
be generated within the plant boundary and will be temporary in nature.
Noise Control Measures
Equipment will be maintained appropriately to keep the noise level within 85 dB(A).
Wherever possible, equipment will be provided with silencers and mufflers. Acoustic
enclosures will be provided to stationary machines like DG sets. High noise generating
construction activities will be restricted to day time only. Further, workers working in
high noise areas will be provided with necessary protective devices e.g. ear plug, ear-
muffs etc.
Water Environment
The water requirement during construction for the proposed plant will be met from
GWIL. Water will be required for construction activities, sprinkling on pavements for
dust suppression and domestic & non domestic usages. Runoffs from the construction
yards and worker’s camps during monsoon may affect the quality of water bodies in the
project area. Impact on water quality during the construction phase may arise due to non-
point discharges of sewage from the workers camp stationed at the project site.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 4:Anticipated Environmental
Impacts & MitigationMeasures
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 71
Mitigation Measures
The earth work (cutting and filling) will be avoided during rainy season and will
be completed during the winter and summer seasons only.
Stone pitching on the slopes and construction of concrete drains for storm water
to minimize soil erosion in the area will be undertaken.
The development of green belt will be undertaken during the monsoon season.
Soil binding and fast growing vegetation will be grown within the plant
premises to arrest the soil erosion.
Septic tanks followed by soak pit will be provided.
The overall impact on water environment during construction phase of the proposed plant
will be temporary and insignificant.
Solid Waste
During installation of new structure there may be some accumulation of scrap, boulders
and solid waste at site which will be removed by building material suppliers. Additional
work force deployed at site will generate garbage. Unless suitable disposal methods are
adopted, the accumulated garbage can have adverse primary impact on land environment
through fouls smell. This may lead to secondary impacts of health hazard to the workers.
The impact due to this will be overcome by good housekeeping. Top soil removed during
construction will be utilized for the green belt development.
Socio Economic Environment
The impact of the proposed plant on socio economic conditions of the local people of the
study area are expected to be positive during construction phase.
The local population will have employment opportunities due to the proposed
project. The local people will be preferred during the construction phase. This will
help in up-liftment of local people in terms of economy and social welfare
Benefits due to the civil construction and transportation companies to the local
people
All the applicable guidelines under the relevant Acts and Rules related to labour
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 4:Anticipated Environmental
Impacts & MitigationMeasures
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 72
welfare and safety shall be implemented during the construction phase;
The construction site will be secured with fencing and will have guards at the
entry points. Facilities to be provided by the Labor Contractor
The contractor shall be asked to provide following facilities to construction work force.
A. First Aid
At work place, first aid facilities will be maintained at a readily accessible place where
necessary appliances including sterilized cotton wool, disinfectants, bandages etc. will
be available. Emergency vehicles will be kept readily available at workplace to take
injured person to the nearest hospital. Reasonably equipped dispensary will be
established for the use of workers as well as local population.
B. Potable Water
Sufficient supply of drinking water will be provided from the filtered water storage tank.
C. Sanitary Facility
Latrines and urinals will be provided at accessible place to workers. These will be
cleaned at least twice during working hours and kept in a good sanitary condition.
D. Canteen
A canteen on a moderate scale will be provided.
4.3 OPERATION PHASE
4.3.1 Impact on Air Quality
The impacts on air quality due to source of the air pollutant in the proposed facilities have
been identified.
Sources of Emissions
Emissions released from the stack during operation phase will get dispersed in the
atmosphere and finally reach the ground at a specified distance from the sources. From
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 4:Anticipated Environmental
Impacts & MitigationMeasures
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 73
the proposed activities the possible environmental impact on air quality has been
envisaged due to the following sources.
Table 4.1
Stacks & Emissions Details
No. Description Capacity Fuel &ItsQuantity
No.ofStack
StackHeight&Dia
APCM Emission Rate(g/sec.)
WithoutAPCD
WithAPCD
1 4 No(InductionFurnace)
2 X 25TPH2X12TPH
Electricity 2 H:30mD:1.77m
HoodCover,BagFilterwithExhaustBlower
PM10
=0.286PM10 =0.581
2 DG set 125KVA
Diesel40 l/h
1 H: 5 mD: 0.1 m
- Not consider formodeling since its act
as a standby4.3.1.1 Prediction of Air quality
Simulation Model for Prediction using Industrial Source Complex AERMOD View
The pollutants released into the atmosphere will disperse in the down wind direction and
finally reach the ground at farther distance from the source. The concentration of ground
level concentrations mainly depends upon the strength of the emission source and
micrometeorology of the study area.
In order to estimate the ground level concentrations due to the emission from the
proposed project, EPA approved Industrial Source Complex AERMOD View Model has
been employed.
The mathematical model used for predictions on air quality impact in the present study is
ISC-AERMOD View. It is the next generation air dispersion model, which incorporates
planetary boundary layer concepts.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 4:Anticipated Environmental
Impacts & MitigationMeasures
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 74
The AERMOD is actually a modeling system with three separate components:
AERMOD (AERMIC Dispersion Model), AERMAP (AERMOD Terrain Preprocessor),
and AERMET (AERMOD Meteorological Preprocessor).
Special features of AERMOD include its ability to treat the vertical in homogeneity of
the planetary boundary layer special treatment of surface releases, irregularly-shaped area
sources, a plume model for the convective boundary layer, limitation of vertical mixing
in the stable boundary layer, and fixing the reflecting surface at the stack base.
The AERMET is the meteorological preprocessor for the AERMOD. Input data can come
from hourly cloud cover observations, surface meteorological observations and twice-a-
day upper air soundings. Output includes surface meteorological observations and
parameters and vertical profiles of several atmospheric parameters.
The AERMAP is a terrain preprocessor designed to simplify and standardize the input of
terrain data for the AERMOD. Input data include receptor terrain elevation data. Output
includes, for each receptor, location and height scale, which are elevations used for the
computation of airflow around hills.
Post Project Scenario
Predicted maximum ground level concentrations considering micro meteorological data
of October, November and December 2018 are superimposed on the maximum baseline
concentrations obtained during the study period to estimate the post project scenario,
which would prevail at the post operational phase.
Predicted 24 hourly Ground Level Incremental Concentrations for October, November,
and December 2018 is given in Table 4.2 and The overall scenario with predicted
concentrations over the maximum baseline concentrations is shown in the Table 4.3 and
isopleth with air pollution control and without control are given in Figures 4.1 and
Figure 4.2 respectively.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 4:Anticipated Environmental
Impacts & MitigationMeasures
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 75
Table 4.2 : Predicted 24 hourly Ground Level Incremental Concentrations
Monitoring Period Year
Maximum IncrementalLevels (µg/m3)
Distance (km) DirectionPM10
WithAPCD
PM10
WithoutAPCD
October, November
and December 20182018-19 0.26 0.53 3.3 SW
Figure 4.1: Predicted GLC of PM10 due to Propose Plant (With APCD)
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 4:Anticipated Environmental
Impacts & MitigationMeasures
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 76
Figure 4.2: Predicted GLC of PM10 due to Propose Plant (Without APCD)
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 4:Anticipated Environmental
Impacts & MitigationMeasures
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 77
TABLE 4.3
Resultant PM10 at Monitoring Locations, µg/m3(with APCD)
Location Sample
code
Back
ground
level
(µg/m3)
PM 10
Maximum
Incremental
Levels
(µg/m3)
Resultant
Concentration
(µg/m3)
Distance
of
Village
(km)
Direction
of
Village
Project Site A-1 78 <0.05 78.05 ---- ----
Dambhaliya A-2 66 0.11 66.11 2.5 Km. W
Bhangadh A-3 58 <0.05 58.05 5.5 Km. E
Manglana A-4 78 <0.05 78.05 5.0 Km. SE
Navagam A-5 74 <0.05 74.05 4.0 Km. S
Ukharala A-6 67 0.11 67.11 4.5 Km. SW
Chamardi A-7 68 <0.05 68.05 2.5 Km. N
Chogath A-8 68 0.05 68.05 4.5 Km. NW
The predicted ground level concentrations obtained when superimposed on the baseline
concentrations are within the prescribed NAAQ Standards for residential areas.
Air Pollution Mitigation Measures
M/s. Sai Inductomelt Pvt. Ltd. shall provide dust suction system which will control
fugitive emission due to material handling. Dust suppression system will be provided in
the form of water sprinklers. All vibrating screens and weigh feeders below the hopper;
day bins etc. are totally covered to prevent leakages of dust. Dust and fume extraction
system will be provided for Induction Furnace. Dust and fumes will be collected with the
help of bag filter as air pollution control system of specified size followed by 30 m stack.
Flue gases generated will be cleaned in the Bag Filters and discharged through stack, so
that the dust concentration will be well within the prescribed standard.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 4:Anticipated Environmental
Impacts & MitigationMeasures
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 78
Impacts Due to the Transportation of Raw Material
The major impact due to transportation of the raw material i.e. Sponge Iron, MS scrap..
All the raw material as well as the finished product will be transported through the Road.
The total material transportation includes 2,22,000 TPA input and output. Estimation of
transportation is given in Below Table 4.4
TABLE 4.4
Estimation of Transportation of the Raw Material
Mitigation Measures
• Traffic management to be done properly and parking space will be provided
within premises
• The vehicles used in transportation will comply norms as per the motor vehicle
act.
• The repair and maintains of vehicle will be taken care by transporter
• Particulate matter will be controlled below 50 mg/Nm3 by providing efficient
dust suppression system like water spray system shall be installed in the material
handling system transfer points
• Plantation along the internal roads in the plant premises will be strengthen
• All the internal roads shall be concreted / asphalted to reduce the fugitive dust
due to vehicular movement
• Water spraying will be practiced frequently
Sr.
No
Raw Material Quantity
(TPA)
Truck
Capacity
(Tonnes)
No of
Trucks/day
Total production of
Billets /Ingots
1 MS Scrap 2,20,000 30 23 2, 22, 000 TPA
2Sponge Iron 11,100 30 02
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 4:Anticipated Environmental
Impacts & MitigationMeasures
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 79
4.3.2 Noise Levels
Operation Phase
During operation, the major noise generating sources are crushing unit, auto loading
section, electric motors etc. These sources will be located far off from each other. Under
any circumstances the noise level from each of these sources will not exceed 85 dB (A).
Noise levels generated in the project site will be confined to the noise generating plant
units hence the impact of noise levels on surroundings will be insignificant
Mitigation Measures
The noise levels stipulated by Central Pollution Control Board at any point of time will
not exceed the standards. The equipment will have inbuilt noise control devices. The
measured noise level produced by any equipment will not exceed 85 dB(A) at a distance
of 1.0-m from its boundary in any direction under any load condition. The noise produced
in valves and piping associated with handling compressible and incompressible fluids
will be attenuated to 75 dB(A) at a distance of 1.0 m from the source by the use of low
noise trims, baffle plate silencers/line silencers, acoustic lagging (insulation), thick-
walled pipe work as and where necessary. The general mitigation for the attenuation of
the noise are given below:
By providing padding at various locations to avoid sharp noise due to vibration.
Encasement of noise generating equipment where otherwise noise cannot be
controlled
Providing noise proof cabins to operators where remote control for operating
noise generating equipment is feasible.
In all the design/installation precautions are taken as specified by the
manufacturers with respect to noise control will be strictly adhered to;
High noise generating sources will be insulated adequately by providing suitable
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 4:Anticipated Environmental
Impacts & MitigationMeasures
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 80
enclosures;
Use of lagging with attenuation properties on plant components / installation of
sound attenuation panels around the equipment
Other than the regular maintenance of the various equipment, ear plugs/muffs are
recommended for the personnel working close to the noise generating units;
All the openings like covers, partitions will be designed properly
Inlet and outlet mufflers will be provided which are easy to design and construct.
All rotating items will be well lubricated and provided with enclosures as far as
possible to reduce noise transmission. Extensive vibration monitoring system will
be provided to check and reduce vibrations. Vibration isolators will be provided
to reduce vibration and noise wherever possible;
The insulation provided for prevention of loss of heat and personnel safety will
also act as noise reducers.
4.3.3 Impact on Water
The total water requirement for the proposed activities is 150 KLD. There will not be any
impact on the water quality as no wastewater will be generated from the process. The
sewage generated from the toilets and bathroom of the proposed facility will be
13 m3/day which will be disposed through septic tank soak pit system. Water will be used
in concast machine for moulding of molten metal through water spray. So the water will
gets evaporated due to temperature difference. The unit will be zero discharge unit.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 4:Anticipated Environmental
Impacts & MitigationMeasures
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 81
Table 4.5: Water Requirement and Waste water Generation
4.3.4 Solid Waste Generation
The solid waste generation in the proposed activities is given in Table 4.6
Table 4.6
Solid Waste Generation & Mitigation Measures
Waste Quantity(TPA)
Category Mitigation Measures
Slag 11,100 Non-Hazardous
Slag Crushers will be installed to recoveriron particles to be reused in InductionFurnace. Slag generated from InductionFurnace will be used for hardening ofworking area, internal road, brickmanufacturers, concreting
Usedspent
oil
0.1 Hazardous Used to lubricate rotating parts withinpremises or will be sold to registeredrecyclers
Sr.No.
Unit Total WaterRequirement
m3/day
WastewaterGeneration
m3/day
Mode of disposal of wastewater
1 Domestic 16.5 13 Domestic wastewater will bedisposed of through soak pit/septictank system
2 Gardening 5.5 - -
3 Industriala) Process Nil Nil -
b) Washing Nil Nil -c) Boiler NA - -d) Cooling 123 - Water will be used in concast
machine for moulding of moltenmetal through water spray. So thewater will gets evaporated due totemperature difference. The unit willbe zero discharge unit.
d) Others 5 - Dust Suppression within Premises
Total 150 13 -
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 4:Anticipated Environmental
Impacts & MitigationMeasures
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 82
4.3.5 Impact on Socio-Economic Environment
The impacts of the proposed project, during its operation, on demography and socio-
economic condition can be identified as follows.
Negative impacts can be depletion of natural resources like water and land,
depletion in air quality if proper mitigative measures are not taken.
Increase in employment opportunities and Reduction in migrants to outside for
employment.
Growth in service sectors.
During operation phase 325 technical and nontechnical people will be employed.
Increase in consumer prices of indigenous produce and services, land prices,
house rent rates and Labor prices.
Improvement in socio-economic environment of the study area.
Improvement in transport, communication, health and educational services.
Increase in employment due to increased business, trade commerce and service
sector.
The overall impact on the socio economic environment will be significant.
The management of M/s Sai Inductomelt Pvt Ltd has proposed to give preference to local
people for recruitment in semi-skilled and unskilled categories.
4.3.6 Prediction of Impacts and Mitigation on Occupational Health
The damage risk criteria as enforced by OSHA (Occupational Safety and Health
Administration) to reduce hearing loss, stipulates that noise level upto 85 dBA are
acceptable for 8 hour working shift per day. Plant authorities will provide ear plugs to the
employees and will be enforced to be used by the employees.
4.3.7 Prediction of Impacts on Flora and Fauna
There are no forests and eco-sensitive area in the vicinity of the site. There are no
endangered flora and fauna species in the region. The project activities are restricted to
the factory site except the transportation of raw material and products. There is no
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 4:Anticipated Environmental
Impacts & MitigationMeasures
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 83
discharge of solid or liquid wastes to the environment. Green belt and greenery will be
developed in the premises covering more than 33% of area. The plantation will comprise
of fruit bearing trees, soil improving and air pollution abatement tress.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 5:Analysis of Alternatives
(Technology & Site)
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 84
CHAPTER 5:
ANALYSIS OF ALTERNATIVES (TECHNOLOGY & SITE)
5.1 ALTERNATE TECHNOLOGY
The manufacturing of M.S. Billets/Ingots using Induction Furnace technology is a
globally proven technology adopted by all for medium scale industry. It is latest
technology with advantage of low capital cost, low power consumption; low slag
generation provided compared with other technology. Its installation is relatively easier
and its operation is simpler. Among other advantages, there is very little heat loss due to
rotation from the furnace as the bath is constantly covered and there is practically no
noise attending its operation. The molten metal in an induction furnace is circulated
automatically by electro-magnetic action so that when alloy additions are made, a
homogeneous product is ensured in minimum time. The major advantages of Induction
Furnace over the other furnace system are as follows:
• Optimized Consistency: Induction heating eliminates the inconsistencies and
quality issues associated with open flame, torch heating and other methods.
• Maximized Productivity: Production rates can be maximized because induction
works so quickly; heat is developed directly and instantly (>20002 F. in < 1
second) inside the part. Startup is virtually instantaneous; no warm up or cool
down cycle is required.
• Environmentally Sound: Induction heating systems do not burn traditional fossil
fuels; induction is a clean, non-polluting process which will help protect the
environment. An induction system improves working conditions for your
employees by eliminating smoke, Waste heat, noxious emissions and loud noise.
Heating is safe and efficient with no open flame to endanger the operator or
obscure the process. Non-conductive materials are not affected and can be located
in close proximity to the heating zone without damage.
• Energy Conservation: Overall energy efficiency in induction melting ranges
from 55 to 75 percent, and is significantly better than combustion processes.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 5:Analysis of Alternatives
(Technology & Site)
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 85
• Higher Yield: The absence of combustion sources reduces oxidation losses that
can be significant in production economics.
• Faster Startup: Full power from the power supply is available, instantaneously,
thus reducing the time to reach working temperature. Cold charge-to-tap times of
one to two hours are common.
• Flexibility: No molten metal is necessary to start medium frequency coreless
induction melting equipment. This facilitates repeated cold starting and frequent
alloy changes
• Cleaner Melting: No by-products of combustion mean a cleaner melting
environment and no associated products of combustion pollution control systems.
• Compact Installation: High melting rates can be obtained from small furnaces.
• Reduced Refractory: The compact size in relation to melting rate means
induction furnace require much less refractory than fuel-fired units.
In pursuance of this, the induction furnace based technology is proposed for this project
and noother alternative technology is considered.
5.1.1 DETAILS OF ALTERNATIVE SITE CONSIDERED:
No alternative site is considered.
The following are the factors in favor of selection of site:
• No Rehabilitation/Resettlement required.
• No archaeological monument, interstate boundary and defense installation.
• No notified critically polluted area.
• No nallah/water body, public roads, forests within the project site.
• Availability of Raw Material.
• Availability of Water.
• Assured Power Supply.
• Market available for finished products.
• Availability of man power.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 6:Environmental
Monitoring Program
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 86
CHAPTER 6
ENVIRIONMENTAL MONITORING PROGRAM
6.1 INTRODUCTION
This chapter presents the details of environmental monitoring schedule, institutional
arrangements for pollution control and cost for environmental monitoring program for the
proposed project.
Monitoring of various environmental parameters will be carried out on a regular basis to
assess the pollutionlevel in the proposed plant and surrounding area. The main objectives
of the monitoring are as follow:
• State of pollution within the plant and in its vicinity;
• Generate data for predictive or corrective purpose in respect of pollution;
• Examine the efficacy of Pollution Control Systems installed in the complex
• To assess and monitor environmental impacts
• Evaluate the performance and effectiveness of mitigation measures proposed in the
Environment Management Plan (EMP) and suggest improvements in management
plan,if required.
6.2 ENVIRONMENTAL MONITORING PROGRAM
A detailed monitoring of emissions and effluent sources for different environmental
parameters will be carried out as per the present norms and any further notification /
direction from Gujarat Pollution Control Board (GPCB), Central Pollution Control Board
(CPCB) and MoEF & CC. Monitoring methodologies will follow standard methods
prescribed by Central Pollution Control Board (CPCB), Bureau of Indian Standards (BIS)
and USEPA.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 6:Environmental
Monitoring Program
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 87
The Environmental monitoring forthe proposed project of M.S. Billets/Ingots plant will be
conducted for following aspects
• Ambient Air Quality
• Ambient Noise level
• Stack Emission
• Surface water and Ground Water Quality,
• Soil Quality
The Monitoring schedule for the environmental parameters is suggested in Table 6.1
Table 6.1: Proposed Environmental Monitoring Schedules
Sr.No. Description of
Parameter
Location Parameters for
Monitoring
Schedule/Frequency
Monitoring
1 Ambient Air
Quality
Monitoring
Three direction of Plant
premises including
industrial and residential
area
PM10, PM2.5,
SO2NOx, and CO
Quarterly
2 Work zone
Monitoring
Process Area PM10,
Temperature
Quarterly
2 Stack Emission
Monitoring
All stacks PM and NOx Once in a month
3 Ambient Noise
level
Within Premises Noise level in dB
(A)
Quarterly
4 Drinking water
quality
- As per IS: 10500
2012 standards
Quarterly
5 CER activities Nearby village Implementation
status and need
based assessment
Annual
6 CC & A
compliance
- - Yearly
7 EC compliance - - Yearly
6.3 BUDGET ALLOCATION FOR ENVIRONMENTAL MONITORING
In order to maintain the environmental quality within the stipulated standards, regular
monitoring of various environmental components is necessary which will complied as per
conditions. Regular Monitoring of all the environmental parameters viz., air, water, noise
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 6:Environmental
Monitoring Program
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 88
and soil as per the formulated program based on CPCB and MoEF&CC guidelines will
be carried out every year. The location of the monitoring stations was selected on the
basis of prevailing micro meteorological conditions of the area like; wind direction and
wind speed, relative humidity, temperature. In order to implement Environmental
Monitoring Programme, M/s Sai Inductomelt Private Limited will assign separate budget.
The details are given in Table 6.2. The budget may be increased as per the
requirement/actual condition.
Table 6.2: Proposed Budget for Environmental Monitoring Programme
Sr.No
Component Description Capital CostRs. in Lacs
Operation &Maintenance CostRs. in Lacs
1. Emission controlEngineering
Bag filter, WaterSprinkler System, Stack
50 5
2. Water & Wastewatermanagement
Septic tank, soak pitsystem
10 1
3. Solid WasteManagement
Slag Crusher, Handlingand Disposing
100 10
4. Green Beltdevelopment
Plantation 5 1.00
5. EnvironmentalMonitoring
Air Quality, WaterQuality, Noise Level,Soil Quality
10 02
6. Other aspect Rainwater harvestingand fire-fighting systemetc.
25 1.00
Total Rs. 200 Lacs Rs. 20 Lacs
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 89
CHAPTER 7
ADDITIONAL STUDIES
7.0 SOCIAL IMPACT ASSESSMENT
The proposed project to be sited at NA obtained land. No displacement of peoples will
be needed hence R& R study not required for the proposed project
7.1 RISK ASSESSMENT
Hazard analysis involves the identification and quantification of the various hazards
(unsafe conditions) that exist in the plant. On the other hand, risk analysis deals with the
identification and quantification of risks. The workers are exposed to, accidents resulting
from the hazards due to accident occur in the plant area.
Risk analysis follows an extensive hazard analysis. It involves the identification and
assessment of risks the neighbouring populations are exposed to as a result of hazards
present. This requires a thorough knowledge of failure probability, maximum credible
accident scenario, vulnerability of population etc. Consequently, the risk analysis is often
confined to maximum credible accident studies.
In the sections below, the identification of various hazards, probable risks in the proposed
plant, maximum credible accident analysis, consequence analysis are addressed which
gives a broad identification of risks involved in the plant. Based on the risk estimation for
fuel and chemical storage Disaster Management Plan (DMP) has been prepared.
7.1.1 Approaches to the Study
Risk involves the occurrence or potential occurrence of some accidents consisting of an
event or sequence of events. The risk assessment study covers the following:
• Identification of potential hazard areas.
• Identification of representative failure cases.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 90
• Visualization of the resulting scenarios in terms of fire (thermal radiation) and
explosion.
• Assess the overall damage potential of the identified hazardous events and the
impact zones from the accidental scenarios.
• Assess the overall suitability of the site for hazard minimization and disaster
mitigation point of view.
7.1.2 HAZARDS IDENTIFICATION
S.No.
Operation/Process
Equipment/AreaPossible Hazards
Precautionary Measure tobe Done
Taken If Occurs
01 Belt ConveyorSystems forsponge iron, slagcrusher etc., Rawmaterial HandlingPlant
a) Jamming ofconveyor Belts
b) Breakage ofConveyor Belts
c) Splash of Materialfrom ConveyorSystem
a) All conveyors belts mustbe provided with tripwire system must beremoved
b) Head & Tail end areprovided by nip guard.
c) Movement below theConveyor belt duringoperation must be banned
d) A 750mm wide walk waymust be provided on bothside for movement
e) Drives are provided withcoupling guards
f) Stop switches with Lockmust be provided forsafety
The process to bestopped immediatelyand the cause of jam.The broken conveyorbelt to be replaced orrepaired. Reason forsplash to be rectified.
02. Induction Furnace a) Blast in Furnaceb) Furnace foundation
damaged due to heavymaterial fall orextreme temperature
c) Induction wiringdamaged/burn
a) Feeding material ischecked and sorted toavoid any explosive orpressurized material tointer in furnace
b) Temperature near furnaceis monitored
c) Structural barrier to beprovided to avoid fallout.
The plant operation tobe stoppedimmediately. The areato be sealed untilcooled forreinstallation.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 91
S.No.
Operation/Process
Equipment/AreaPossible Hazards
Precautionary Measure tobe Done
Taken If Occurs
d) The temperature of thefurnace to be maintainedproperly no overheatingto be allowed.
03. Oil TransformerOil, Diesel etc.
Fire hazard may possibleif come in direct contactwith fire.
a) Fire proof system madeavailable like foalextinguishers andhydrant system etc keepaccessible.
b) Stored in MS cylindertank & kept away fromany type of fire causedthings,
Proper care is to betaken in storing andkeeping the drum ofoil. Precautions shouldbe adopted and takenas mentioned inChapter-7.
04. Control Rooms Electrical shock possibledue to leakage
a) Earth leakage Circuitbreaker is installed.
b) Shock precaution &treatment chart aredisplayed.
c) Operator should beprovided with insulatedshoes.
d) All instruments areproperly earthed
e) Electrification layout &diagram is displayed
In the event of electricleakage main supplyshould be immediatelyshut off. ShockTreatment & medicalAid shall beimmediately provided.
05. E.O.T Crane Hoist Rope Breakagepossible
a) No movement of strangepeople in crane bay willbe permitted.
b) Frequent check of therope and other loadbearing material shall bedone
c) Light indicationmovement of crane shallbe provided.
d) Prescribed load shallonly be allowed
e) Crane operator to givealarm before movement
Weak rope shall beimmediately replaced.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 92
S.No.
Operation/Process
Equipment/AreaPossible Hazards
Precautionary Measure tobe Done
Taken If Occurs
06. Welding GasOxygen LPG and/Acetylenecylinders
Fire hazards caused byflames and leakage.
a. Emergency kit is keptreadily available in storeand working place.
b. Firefighting equipment’spowder / Foam typeextinguishers on vehicleand mounting on walls arekept readily available.
c. Hydrant system providedat conspicuous place.
d. Firefighting trained man isemployed.
e. Cylinders are handledcarefully without droppingor rolling.
f. Precaution to ensure thatcylinders are not allowedto dash with each other.
g. Sand bed cushionavailable for the purposeof unloading cylinders.
h. Periodic inspection doneto avoid accident of anykind.
• Installation of inertgas Nitrogen,Carbon dioxide.Equipment’s to takecare of fire hazardsin the factory arebeing installed.
•Hydrant point willbe for gas cylindersstores and pointwhere weldingoperation is done.
07.
Electricaltransformer
Electrical power Shock proof insulated PCCPlatform.
Immediate Cut off thepower supply, treat theinjured for electricalshock
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 93
S.No.
Operation/Process
Equipment/AreaPossible Hazards
Precautionary Measure tobe Done
Taken If Occurs
Fire Firefighting equipment
(i)Sand buckets.(ii)Fire extinguisher.
Immediately fight firewith availableresources, summonoutside help ifnecessary.
08. Lab Chemicals In case of bottlebreakage, causes burnsand damageto respirator systemsdue to inhalation.
a. Proper care should betaken while handling thechemicals.
b. First Aid Box should beavailable at Site with allnecessary and requiredmedicines.
c. Firefighting equipmentlike Extinguishers, sandbuckets should beavailable always.
Instruction Boards tobe displaced forknowledge of otherworkers to take care ofthe situation in theevent of occurrence.
7.1.3 Occupational health impacts on the workers
Hazards in heat treatment include burns and scalding, mechanical hazards from steel
handling, and hazards arising from the annealing gases, including nitrogen, hydrogen and
carbon monoxide. Furnace insulation wools can expose workers to hazardous fibers.
HEAT STRESS
Hazard description
In heat treating, steel products are heated and cooled in a controlled way to change their
physical or mechanical properties without changing their shapes. Heat treating is used to
relieve stresses in the metal created during cold rolling, to improve its hardness or
strength, or to change its electromagnetic properties. Some heat treating is done by
quenching, in which heated steel is plunged into a cold bath of water or oil to rapidly cool
it. The most common heat-treating process is annealing, in which the steel is slowly
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 94
heated, maintained at temperature, then cooled. Often this takes place in a closed furnace,
using an inert gas to prevent oxidation, or a gas that conveys desired properties to the
steel.
Hazards in heat treatment include burns and scalding, mechanical hazards from steel
handling, and hazards arising from the annealing gases, including nitrogen, hydrogen and
carbon monoxide. Furnace insulation wools can expose workers to hazardous fibers.
Heat radiation around the furnace is 480C to 550C temperature near the furnace.
Mitigation Measures Proposed to Avoid the Human Health Hazards
Hazard control
The work area and the flow of material through it shall be designed so as to
minimize the possibility of worker contact with hot steel, or to scalding in the
case of quenching operations.
Inert annealing gases shall be handled in a way that prevents their build-upon
enclosed spaces other than the furnace itself, so as to prevent asphyxiation.
Annealing furnaces shall be considered to be hazardous confined spaces.
The system for handling flammable annealing gases like oxygen shall be
minimize the possibility of an explosive build-up.
The safest practicable furnace insulation shall be used. In general, this means
using insulation wools with a low content of respirable fibres, and which do not
convert to silica when heated.
Adequate drinking water arrangement shall be provided for worker
Natural ventilation and air conditioner room is available for worker.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 95
Control strategies
Training
Personnel handling molten metal shall have been trained in the proper procedures
to adopt, and in the relevant safety and health precautions, including use of
appropriate PPE.
Completion of training shall be documented, and training repeated as necessary.
Persons who are untrained shall not be employed in the transport of molten metal.
Work practices
Only essential personnel shall be in the vicinity of pouring operations.
Moulds and tundishes shall not be damp, nor should there be any means whereby
water could enter the melt because of the risk of explosion.
The area shall be cordoned off prior to the transport of molten metal if there is a
possibility of spillage.
Safety inspection of ladles
A competent person shall regularly inspect ladle buckets and their supporting,
locking and tipping mechanisms.
Before each filling, the pouring of, or transport of slag ladles and their related
appliances should be visually inspected.
Test results, including remedies for cracks and other defects, shall be recorded.
Corrective repair measures that are recommended shall be planned and
implemented on a timely basis.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 96
There shall be a system for checking and ensuring that the corrective measures
have been completed.
Personal protective equipment
1. Appropriate PPE, such as helmets, gloves, aprons and boots shall be provided and
used. Where appropriate, molten metal resistant clothing should be provided and
used.
First aid
Injuries caused by molten metal, dross or slag or exposure to alkaline dust shall
receive immediate medical attention.
Ventilation
Proper ventilation will be provide.
Thermometer for work zone temperature monitoring will be place at appropriate
location
Drinking water
Water cooler will be provided.
Purified water will be made available.
General
Job rotation will be done for worker
Glucose and head relief drink will be made available for worker
Bath shower and hand wash will be provided at appropriate location
Air conditioning room will be provide for heat relief.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 97
7.1.4 Do’s & Don’ts of preventive maintenance
CLEANING THE FLOOR
Do’s
1. While Cleaning Use the mildest cleaning agent that does the job effectively.
2. Follow the polishing lines when using abrasive cleaners.
3. Rinse thoroughly after every cleaning operation.
4. Wipe dry to avoid water marks
5. Handle with clean gloves/cloths to guard against stains/finger print
Don’t
1. Do not use an ordinary steel scraper or knife to remove dirt.
2. Do not allow chemicals or bleaching agents to remain in prolonged contact¬
with stainless steel.
3. Avoid cleaning with chloride containing detergents/solvents.¬
4. Do not allow steel tools, containers or implements to lie on stainless¬ surfaces.
EOT CRANE
Do
1. Ensure that only authorized slingers/signaler attached or detached load, or
signal the crane operator
2. Discuss operation with the crane operator(special operation)
3. Ensure that the capacity of the crane is sufficient
4. Seek expert advice when using eye bolts, plate clam etc.
5. Use tag line always
Don’t
1. Don’t Wrap tag line around hand of body
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 98
2. Don’t leave a suspended load unattached
3. Don’t Pass load over people
4. Don’t ride of climb on suspended load
5. Don’t stand or walk beneath the loads
6. Don’t use pipe to support for landing the load
WORKING AT HEIGHT
Do
1. Do as much as work as possible from ground
2. Ensure worker can get safety to and from where they work at height
3. Ensure equipment is suitable , stable and strong enough for the job.
Maintained and checked regularly
4. Take precautions when working near hot surface
5. Provide protection from falling object
6. Consider emergency evacuation and rescue procedure
Don’t
1. Don’t overload the equipment or materials workers are carrying before
working at height. Check the pictogram or label on the lubber for information.
2. Don’t overreach on ladder or stepladders
TOOL BOX
Do
1. Use specific tool for specific work
2. Maintain proper tool box
3. Arrange tool in proper order
4. Keep tool in tool box after use
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 99
Don’t
1. Don’t leave tool box at work place
2. Don’t hammer with by tools
3. Don’t play with tools
4. Don’t carry tool in pockets or in hand
PERSONAL PROTECTIVE EQUIPMENT
Do
1. Use proper PPE
2. Al ways weal helmet in working premises
3. Use cotton cloth while working near furnace
4. Always follow the safety instruction
5. Take permission for use of PPE
Don’t
1. Don’t use other of PPE
2. Don’t place jock while working
3. Don’t wear polyester cloth while working near hot area.
7.1.5 Personal Protective Equipment and Periodic Medical Examination
LIST OF PPE
Protection Type Quantity
Head Helmet 350
Hand Gloves Asbestos 350 pair
Leather 350pair
Foot Safety Shoe 350Pair
Aluminized Heat
Protection
Fire Suit 1
Respirator 10
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 100
Hearing Protection Ear plug 350Pair
Ear muff 50 Pair
Safety Belts 150
Eye Goggles 325
Face shield 50
Medical First aid box 05
Body Protection Aprons 325
PLAN FOR PERIODIC EXAMINATION
1. Pre-employment medical examination will be done.
2. Post-employment medical examination plan is one in every year from government
authorized medical institute/ fractioned.
3. Every six month medical examination of worker working in suspicious condition.
4. Bronchitis and chest diagnostic of worker working near furnace, EOT crane
operator and smoky environment after every six month.
7.2 DISASTER MANAGEMENT PLAN
Installation of 2 x 25TPH and 2 x 12 Induction Furnace to manufacture 2,22,000TPA
Billets/Ingots.
The word 'disaster' is synonymous with 'emergency' as defined by the Ministry of
Environment and Forests & CC. An emergency occurring in proposed Installation of 2 x
25TPH and 2 x 12 Induction Furnace to manufacture 2,22,000TPA Billets/Ingots is one
that may affect several sections within it and/or may cause serious injuries, loss of lives,
extensive damage to environment or property or serious disruption outside the plant. It
will require the best use of internal resources and the use of outside resources to handle it
effectively. It may happen usually as the result of a malfunction of the normal operating
procedures.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 101
The project is in its formative stage and detail engineering is yet to be done, so the DMP
are based on the following concepts.
Capabilities of DMP
The emergency plan envisaged will be designed to intercept full range of hazards specific
'to proposed plant such as fire, explosion, major spill etc. In particular, the DMP will be
designed and conducted to mitigate those losses of containment situations, which have
potentials to escalate into major perils.
Another measure of the DMP's capability will be to combat small and large fires due to
ignition, of flammable materials either from storage or from process streams and
evacuate people from the affected areas speedily to safe locations to prevent irreversible
injury.
Emergency medical aids to those who might be affected by incident heat radiation flux,
shock wave overpressures and toxic exposure will be inherent in the basic capabilities.
The most important capability of this DMP will be the required speed of response to
intercept a developing emergency in good time so that disasters such as explosion, major
fire etc. are never allowed to happen.
Disaster Control Philosophy
The principal strategy of DMP is "Prevention" of identified major hazards. The
"Identification" of the hazards will employ one or more of the techniques [e.g. Hazard
and Operability Study (HAZOP), accident consequence analysis etc.]. Since these
hazards can occur only in the event of loss of containment, one of the key objectives of
technology selection, project engineering, construction, commissioning and operation is
"Total and Consistent Quality Assurance". The Project Authority will be committed to
this strategy right from the conceptual stage of the plant so that the objective of
prevention can have ample opportunities to mature and be realized in practice.
The DMP or Emergency Preparedness Plan (EPP) will consist of:
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 102
On-site Emergency Plan
Off-site Emergency Plan
Disaster Management Plan preparation under the headlines of On-site Emergency Plan
and Off-site Emergency Plan is in consonance with the guidelines laid by the Ministry of
Environment and Forests (MoEF) which states that the "Occupier" of the facility is
responsible for the development of the On-site Emergency Plan.
The off-site Emergency Plan should be developed by the Government (District
Authorities).
7.2.1 On-Site Emergency Plan
Objectives
The objective of the On-site Emergency Plan should be to make maximum use of the
combined resources of the plant and the outside services to
• Effect the rescue and treatment of casualties
• Safeguard other personnel in the premises
• Minimize damage to property and environment
• Initially contain and ultimately bring the incident under control
• Identify any dead
• Provide for the needs of relatives
• Provide authoritative information to the news media
• Secure the safe rehabilitation of affected areas
• Preserve relevant records and equipment for the subsequent enquiry into the
cause and circumstances of emergency
Action Plans
The Action Plan should consist of:
• Identification of Key Personnel
• Defining Responsibilities of Key Personnel
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 103
• Designating Emergency Control Centers and Assembly Points
• Declaration of Emergency
• Sending All Clear Signal
• Defining actions to be taken by non-key personnel during Emergency.
Key Personnel
The actions necessary in an emergency will clearly depend upon the prevailing
circumstances. Nevertheless, it is imperative that the required actions are initiated and
directed by nominated people, each having specified responsibilities as part of co-
ordinated plan. Such nominated personnel are known as Key Personnel.
The Key Personnel are:
• Site Controller (SC)
• Incidental Controller (IC)
• Liaison and Communication Officer (LCO)
• Fire and Security Officer (FSO)
• Team Leaders (TL)
Site Controller (SC)
In the emergency situation, decisions have to be taken which may affect the whole or a
substantial part of the plant and surrounding area. Many of these decisions will be taken
in collaboration with the other officers at the plant and the staff. It is essential that the
authority to make decision be invested in one individual. In this plan, he is referred to as
the 'Site Controller'. The Plant Manager (however called) or his nominated deputy will
assume responsibility as SC.
Incident Controller (IC)
In the emergency situation, someone has to direct the operations in the plant area and co-
ordinate the actions of outside emergency services at the scene of incident. The one who
will shoulder this responsibility is known as 'Incident Controller' in this plan.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 104
A Senior Operations Officer or an officer of similar rank of the unit may be nominated to
act as the IC.
Liaison and Communication Officer (LCO)
Operations Officer or any other officer of deputy rank will work as LCO and will be
stationed at the main entrance during emergency to handle Police, Press and other
enquiries. He will maintain communication with the IC
Fire and Safety officer (FSO)
The Fire and Safety Officer will be responsible for fire fighting. On hearing the fire alarm
he shall contact the fire station immediately and advise the security staff in the plant and
cancel the alarm. He will also announce on PAS (public Address System) or convey
through telephones or messengers to the SC, IC and LCO about the incident zone. He
will open the gates nearest to the incident and stand by to direct the emergency services.
He will also be responsible for isolation of equipment from the affected zone.
Team Leaders (TL)
A number of special activities may have to be carried out by specified personnel to
control as well as minimize the damage and loss. For this purpose designated teams
would be available. Each team will be headed by a Team Leader (TL).
Following teams are suggested:
• Repair Team
• Fire Fighting Team
• Communication Team
• Security Team
• Safety Team
• Medical Team
Responsibilities of Key Personnel
Site Controller (SC)
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 105
• On getting information about emergency, proceed to Main Control Centre
• Call in outside emergency services
• Take control of areas outside the plant, which are affected
• Maintain continuous communication, review situation and assess possible
course of events
• Direct evacuation of nearby settlements, if necessary
• Ensure that casualties are getting enough help
• Arrange for additional medical help and inform relatives
• Liaison with Fire and Police Services and Provide advice on possible effects on
outside areas
• Arrange for chronological recording of the emergency
• Where emergency is prolonged, arrange for relieving personnel, their catering
needs etc.
• Inform higher officials in head office
• Ensure preservation of evidence
• Direct rehabilitation work on termination of emergency
Incident Controller (IC)
• On getting emergency information, proceed to Main Control Centre
• Activate emergency procedure such as calling in various teams
• Direct all operations within plant with following priorities:
a) Control and contain emergency
b) Secure safety of personnel
c) Minimize damage to plant, property and the environment
d) Minimize loss of material
• Direct rescue and repair activities
• Guide fire-fighting teams
• Arrange to search affected area and rescue trapped persons
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 106
• Arrange to evacuate non-essential personnel to safe area/assembly point
• Set up communications network and establish communication with SC
• Arrange for additional help/equipment to key personnel of various teams
• Consider need for preserving all records, information for subsequent enquiries
Liaison and Communications Officer
• To ensure that casualties receive adequate attention, arrange additional help if
required and inform relatives
• To control traffic movements into the plant and ensure that alternative
transport is available when need arises
• When emergency is prolonged, arrange for the relief of personnel and organize
refreshments/catering facility
• Advise the Site Controller of the situation, recommending (if necessary)
evacuation of staff from assembly points
• Recruit suitable staff to act as runners between the Incident Controller and
himself if the telephone and other system of communication fail. -Maintain
contact with congregation points
• Maintain prior agreed inventory in the Control Room
• Maintain a log of the incident on tape
• In case of a prolonged emergency involving risk to outside areas by windblown
materials - contact local meteorological office to receive early notification of
changes in weather conditions.
Fire and Safety Officer
• Announce over the PAS in which zone the incident has occurred and on the
advice of the Shift Officer informs the staff to evacuate the assembly
• Inform the Shift Officer In-charge, if there is any large escape of products
• Call out in the following order:
1) Incident Controller or his nominated deputy
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 107
2) Maintenance Officer
3) Personnel and Administrative Officer
4) Departmental Head in whose area the incident occurred
5) Team Leaders (TL)
Emergency Control Centre
The Emergency Control Centre will be the focal point in case of an emergency from
where the operations to handle the emergency are directed and coordinated. It will control
site activities.
Emergency management measures in this case have been proposed to be carried from
single control Centre designated as Main Control Centre (MCC)
MCC is the place from which messages to outside agencies will be sent and mutual aids
and other helps for the management of emergency will be arranged. It will be located in
the safe area. It will be equipped with every facility for external and internal
communication, with relevant data, personal protective equipments to assist hose
manning the centre to enable them to co-ordinate emergency control activities. CC will
be attended by SC.
Following facilities would be available in the MCC:
• P&T phones, mobile phones, intercoms, and wireless
• Emergency manuals
• Blown up area maps
• District telephone directories
• Emergency lights
• Wind direction and speed indicator
• Requisite sets of personal protective equipment such as gloves, gumboots and
aprons
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 108
MCC will be furnished with call out list of key persons, fire, safety, first aid, medical,
security, police and district administrative authorities. MCC will also contain safety data
pertaining to all hazardous materials likely to cause emergency and well-defined
procedures of firefighting, rescue operations, first aid etc.
Assembly Point
In an emergency, it will certainly be necessary to evacuate personnel from affected areas
and as precautionary measure, to further evacuate non-essential workers, in the first
instance, from areas likely to be affected, should the emergency escalate. The evacuation
will be effected on getting necessary message from i.e. on evacuation; employees would
be directed to a predetermined safe place called Assembly Point.
Proposed Location: Area opposite to service building will be the Assembly Point where
all non-key personnel would assemble on getting direction over Public-Address System.
Outdoor assembly points, predetermined and pre-marked, will also be provided to
accommodate evacuees from affected plant area(s). Roll call of personnel collected at
these assembly points, indoor and outdoor will be carried out by roll call crew of safety
team to account for any missing person(s) and to initiate search and rescue operations if
necessary.
Declaration of Emergency
An emergency may arise in the plant due to major leakage of oil or major outbreak of
fire/explosion. In case of major leak or major outbreak of fire the state of emergency has
to be declared by the concerned by sounding Emergency Siren.
Upon manual or sensor detection of a major loss of containment of volatile hazardous
substance, the DMP is activated by raising an audible and visual alarm through a network
of geographically dispersed gas/vapour and heat detectors and also "break glass" type fire
alarm call points with telephone handsets to inform the Central Control Room.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 109
A separate siren audible to a distance of 5 km range will be available for this purpose.
The alarm is coded such that the nature of emergency can be distinguished as a leakage or
major fire.
The Control Centre and Assembly point will be located at an area of the minimum risk or
vulnerability in the premises concerned, taking into account the wind direction, areas
which might be affected by fire/explosion, leakage etc.
After cessation of emergency, FSO will communicate to IC. After verification of status,
IC will communicate with SC and then announce
Alarms would be followed by an announcement over Public Address System (PAS).In
case of failure of alarm system, communication would be' by telephone operator who will
make announcement in the complex through PAS. Walkie-talkie system is very useful for
communication during emergency with predetermined codes of communication. If
everything fails, a messenger could be used for sending the information. To 5 km, range
variable pitch electric sirens (one in service and the other standby)will generate the main
alarm for the entire site as well as for the district fire brigade. The alarm is coded such
that the nature of emergency can be distinguished as a leakage or major fire. Fire and Gas
alarm matrices are provided at the Central Control room, security gate, on-site fire station
and main administrative office corridor to indicate location of the site of emergency and
its nature.
Mutual Aid
Procedure
All factories may not be equipped with an exhaustive stock of equipment/materials
required during an emergency. Further, there may be a need to augment supplies if an
emergency is prolonged.
It would be ideal to pool all resources available in the and nearby outside agencies
especially factories during an emergency, for which a formal Mutual Aid scheme should
be made among industries in the region.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 110
Essential Elements
Essential elements of this scheme are given below:
• Mutual aid must be a written document, signed by Location In-charge of all the
industries concerned
• It should specify available quantity of materials/ equipment that can be spared (not that
which is in stock)
• Mode of requisition during an emergency.
• It should authorize the shift-in-charge to quickly deploy available material/equipment
without waiting for formalities like gate pass etc.
• It should spell out mode of payment/replacement of material given during an emergency
• It should specify key personnel who are authorized to requisition materials from other
industries or who can send materials to other industries
• It should state clearly mode of receipt of materials at the affected unit without waiting
for quantity/quality verification etc.
• Revision number and validity of agreement should be mentioned.
• This may be updated from time to time based on experience gained.
Emergency Management Training
• The Key Personnel would undergo special courses on disaster management. This
may preferably be in-plant training. The Managers, Senior Officers and Staff
would undergo a course on the use of personal protective equipment.
• The Key Personnel belonging to various Teams would undergo special courses
as per their expected nature of work at the time of emergency.
• The plant management should conduct special courses to outside agencies like
district fire services to make them familiar with the plant layout and other
aspects, which will be helpful to them during an emergency.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 111
Mock Drills
It is imperative that the procedures laid in this Plan are put to the test by conducting
Mock Drills. To avoid any lethality, the emergency response time would be clocked
below 2 minutes during the mock drill.
• 1st Step: Test the effectiveness of communication system
• 2nd Step: Test the speed of mobilization of the plant emergency teams
• 3rd Step: Test the effectiveness of search, rescue and treatment of casualties
• 4th Step: Test emergency isolation and shut down and remedial measures taken
on the system
• 5th Step: Conduct a full rehearsal of all the actions to be taken during an
emergency
The Disaster Management Plan would be periodically revised based on experiences gained from
the mock drills.
Proposed Communication System
The instrument and control system will take care of the following operating philosophy
of the plant.
• The project will be provided with a control system located in a central control room.
• The shift engineer will operate the plant from his console panel.
• All operations will be represented in a graphic panel on the console and every operation
will be depicted as operating sequences.
• All operating parameters will be displayed in digital format.
• Alarms will be provided for all parameters, when they exceed set values.
• High-High/Low-Low alarms and trip functions will be provided to trip.
• Pumps/compressors to bring the entire system to a safe shutdown.
• Alarm signal code is set for process description.
Proposed Fire Fighting System
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 112
Elaborate firefighting system will be available for fighting fires in any corner of
the plant. A comprehensive fire detection and protection system is envisaged.
Underground Fire and Service water storage tanks of 650 KL will be provided.
Fire water pump house containing combination of diesel and electrically driven pumps.
Hydrant system complete with suitable size piping, valves, instrumentation, hoses,
nozzles, hose boxes/stations, monitors etc.
Foam injection system for fuel oil/storage tanks consisting of foam concentrate tanks,
foam pumps, in-line inductors, valves, piping and instrumentation etc.
Automatic high velocity water spray system consisting of detectors, deluge valves
projectors, valves, piping and instrumentation.
Automatic medium velocity water spray system consisting of QB.
Detectors/smoke detectors, linear heat sensing cable detectors, deluge valves, isolation
valves, nozzles, piping, instrumentation etc.
Portable and mobile extinguishers, such as pressurized water type, carbon dioxide type,
foam type, dry chemical powder (DCP) type located at strategic locations throughout the
plant.
Fire tenders/engines of water type, DCP type/foam type, trailer pump with fire jeep etc.
provided in the fire station.
Complete instrumentation and control system for the entire fire detection and protection
system for safe operation of the complete system.
Other safety Measures
Considering that fire and explosion is the most likely hazard in such installations, the
plant is being provided with systems to guard against such hazards. Salient among these
are:
A proper layout to prevent and minimize the effects of any hazardous situation
Design of storage vessels and all components to codes and standards to withstand the
rigorous duty
Provision of operating systems to conduct the process through well-established safe
operating procedures
A control system, which monitors all, plant parameters and give alarms
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 113
Control system, which has trip provisions to prevent hazard conditions escalating
A gas detection system which will provide early warning of any leaks
Provision of a fire protection system to control fire
Provision of flame-proof lighting system in the fire prone areas
First Aid and Medical Facilities
Mutual agreement with local hospital for emergency medical treatment has been done. It
will be fully equipped with emergency facilities. It will be open round the clock. A
Medical Officer with Compounder will always be available in the center. Emergency cars
will be available in all the shifts. Adequate number of first aid boxes will be kept at
strategic locations. Required stock of first aid medicines will be maintained. Trained first
aiders will be available in all departments.
Facilities to be kept in the Medical Room along with others will include: Oxygen
Cylinders, Injection Coramine, Glucose Saline, LV. Sets, Syringes, Injection Needles,
Stretchers and medicines.
Emergency Power Supply
Strategic areas will be provided with emergency lights fed through stationed battery
system. Portable emergency lamps will be also available at required points. A Diesel
Driven Generator of 125 KVA capacity is available to keep the operations running in
case of power failure. Diesel Engine operated fire pumps will be available.
7.2.2 Disaster Management Plan for Sai Inductomelt Pvt Ltd.
The main objectives of this disaster management plan are to:
• To identify type of major disaster which may occur in the plant
• To prepare an action plan to handle disaster.
Severity of accidents have been categorized as Category I - Operator Level and
Category II - Local / Community Level
Category—I
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 114
In category-I, disasters may occur due to fire, explosion, oil spillage, mall function of the
machines and spontaneous ignition of inflammable materials. The severity of this
category depends upon the disaster type and nature of it. It may affect the work force
health that involves the operation at that facility and even may be on the facilities of the
plant.
Category—II
In case of complete failure of all automatic control / warning systems of the different
units then it may leads to disaster which may have the high severity on inside work force
and facilities of its own and even may effects on the others facilities surrounding plant.
Probability of these disasters occurrences will be very less because of the plant
alternative systems and well qualified and trained work force which will be placed in
respective areas.
Disaster Preventive Measures
Design, construction of all facilities and machineries will be as per national and
international codes as applicable in specific cases and lay down by statutory
authorities
The operations of the plant will be as per applicable standards laid by the statutory
authorities
Provision of adequate access ways for the movement of equipment and work
force will provide
Minimum two numbers of gates for escape during disaster will take place
All the storage facilities will be marked properly and protected by providing the
fencing around to the storage systems
Water spraying in coal storage facility
Well established firefighting system
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 115
Safety and Training
In the plant all the workforce will be provided with necessary safety protective
equipments. Instrument the like safety valves, safety controls system. Safety department
will look after the safety awareness programs by different means like posters, messages
on the notice boards, etc and safety trainings in the plant as per requirement of the
criticality. Safety training and practical demos to the selected individuals in each
department will provided.
Functions of Disaster Controller
To declare “ Disaster Emergency ” after consulting the Sr. Officer available and
inform Fire Station Control Room to sound the sirens accordingly and arrange to
convey the message in public addresses system
To report to DCR immediately
To receive message from the communication centre
To take decision in consultation with the commanding Officer of different
services and convey them to the disaster point
To be responsible for planning and provision of assistance from township and
from local authorities
Decision of the Disaster Controller on any matter will be final to met the
objective of disaster control plan .
To assist Disaster Controller for provision of material and man power concerning
his services
To convey message to his services team through communication centre after
consulting Disaster Controller
To consult between themselves on matters related to more than one services and
to decide on the action to be taken
Repair Services
This section will look after mainly for the following areas after disaster takes place.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITEDChapter 7:
Additional Studies
Pollution and Ecology Control Services (PECS), Nagpur P a g e | 116
To take up quick repairs of the damaged machinery
To take up repair of damaged building roads and culverts.
To maintain essential public utility services viz. water, electricity and sewages
system.
Traffic Control
During the disaster, the movement of the safety vehicles and fire fighting vehicles will be
monitored and make the emergency ways to be free from vehicles to attend the disaster
works by the security of the plant. Persons arriving by motor transport at the location of
fire / emergency must not park their vehicle within 100 meters of fire, near fire hydrants,
at road junction and at access roads. The ignition key should be left in the vehicles.
Security Services
In the plant security department will be responsible for the plant security by keeping
security checks at different locations based on the sensitivity of the area. During the
disasters the functions of security will be follows:
Alert the all workforce about the disaster and its location
Update the developments and status of the disaster to the higher officials to take
necessary actions
Co-ordinate the disaster status to the local authorities to get necessary support from
them
Control the vehicular traffic inside the plant to get way to the safety and fire
fighting vehicles to attend the disaster works immediately
Assist the different divisions like fire fighting, safety, local authorities etc. to make
the process easy to handle the disaster works
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 8:Project Benefits
Pollution and Ecology Control Services, Nagpur P a g e | 117
CHAPTER 8
PROJECT BENEFITS
8.1 IMPROVEMENT IN THE PHYSICAL INFRASTRUCTURE
The beneficial impact of the proposed project on the public amenities will be significant
after the commencement of the project activities. The basic requirement of the
community needs will be strengthened by extending healthcare facilities to the
community, building/strengthening of existing roads and drinking water facility in the
area which will help in uplifting the living standards of local communities. Iron is the
most important metal to the mankind, which is widely used for domestic, agricultural,
industrial and defense purposes. Steel consumption is a major indicator of economic
status of any country. The growth of the steel industry significantly contributes to
economic growth as it generates employment both directly and also due to development
of the industries.
8.2 EMPLOYMENT POTENTIAL
Employment opportunities are moderate and not growing in accordance with growth of
education. Employment scenario of the study area is largely dependent on the agriculture
and Industrialization of the area. The major benefit due to the proposed project will be in
the sphere of generating employment for people of that area. The present proposed
project has employment generation potential by way of recruiting local people directly
for different activities of the project. The manpower requirements for the operational
phase after the proposed project will be about 325 people. In addition, there will be an
indirect employment for skilled/ semi-skilled people during project life. All attempts will
be made to employ suitable, locally available, skilled personnel from the nearby area.
Manpower for unloading of raw materials, loading of finished goods, plant cleaning,
hiring of vehicles, road maintenance, plant security, gardening / green belt development
etc. will be locally contracted out. Local people will be given the opportunity of
employment as per their capability and expertise. Priority will be given to scheduled tribe
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 8:Project Benefits
Pollution and Ecology Control Services, Nagpur P a g e | 118
families and women. This will enhance the present socio economic status of the local
people.
8.3 IMPOVEMENT IN INFRASTRUCTURE
M/s Sai Inductomelt Private Limited will provide the following infrastructure in the study
area of 10 km radius:
• Road Transport: There will be improved road communication due to the
proposed project and maintenance will also be done time to time.
• Market for product: Need for the proposed products are based on the demand
and supply gap in the current market. With increasing utilization of the current
products in future, to cater the requirement of all the products, it is essential to
have the proposed manufacturing unit.
• Market for Consumer Goods: With the implementation of the project and
development of the locality, existing demand pattern is likely to continue which
indicates more importance on consumer goods and quality products. This will
affect the local consumer goods market will grow, thus creating more income
opportunities to the local people. The proposed project is going to have positive
income effect and consequently, the multiplier effect is expected to lead to an
overall increase in average consumption of the people of the study area.
• Infrastructure: Creation of community assets (infrastructure) like Installation/
Repair of Hand Pumps/ Bore wells Gram Panchayat dug well de‐siltation and
deepening, as a part of corporate social responsibility.
8.4 EDUCATION
The local peoples’ interest towards education will increase due to the expectation of
getting jobs, especially from non-agricultural sources such as the industries in the vicinity
of M/s Sai Inductomelt Private Limited. Educational institutions will also come-up and
will lead to improvement of educational status of the people in the area. The general
awareness towards the importance of education is expected to increase as a result of the
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 8:Project Benefits
Pollution and Ecology Control Services, Nagpur P a g e | 119
proposed project. The project will have positive impact on the level of education of the
people.
8.5 GREEN BELT DEVELOPMENT
The plantation and green belt development will also be taken care in the plant and the
space reserved for plantation will be more than 33% of the total plant area. Adequate
plantation will substantially abate the dust pollution, filter the polluted air, reduce the
noise and ameliorate the plant environment.
8.6 SOCIAL INFRASTRUCTURE
With the implementation of the proposed plant, the increasing industrial activity will
boostup the commercial and economic status of the locality, to some extent the socio
economic status of the local people will improve substantially. The required skilled and
unskilled laborers will be utilized maximum from the local area. The land rates in the
area will improve in the nearby areas due to the proposed activity. This will help in
upliftment of the social status of the people in the area. Primary health the medical
facilities will certainly improve due to the proposed project.
8.7 OTHER TANGIBLE BENEFITS
This project is essential in-view of production of high value downstream products. The
present project is likely to accelerate such industrialization the study area. M/s Sai
Inductomelt Private Limited is equally conscious for the all-round socio-economic
development and is committed to raise the quality of life and social well-being of
communities where it operates. The activities under CER will be local need basis with
focus on Health, Education, Infrastructure Development, Drinking water, Sanitation and
Environment Conservation.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 8:Project Benefits
Pollution and Ecology Control Services, Nagpur P a g e | 120
8.8 CORPORATE ENVIRONMENT RESPONSIBILITY PLAN (CER)
As per the Notification dated 1.05.2018 issued by MOEF&CC, it is mandatory to prepare
Corporate Environment Responsibility Plan (CER) to spend 2 % (project cost≤ 100
Crores, Greenfield project) of total capital cost of the project on social, economical and
peripheral development activities. Hence, a detailed socio-economic analysis of pre-
project status of 10 km buffer zone villages is required so as to establish a bench mark for
measuring changes due to project’s CSR interventions over a period of time. As per the
above mentioned new office memorandum CER dated 1.05.2018, 2 % of total project
cost i.e Rs. 1.2 Crores will be allocated for CER based on public hearing issues (Total
cost of project is (60 crores). The CER for the proposed expansion is as follows.
S.N Task
Annual Capital Cost(in Lakh)
Year-1
Year-2Year-
3Year-
4Year-
5Total
1 Educational Activities/Facilities 4.0 4.0 4.0 4.0 4.0 20.02 Public health (Annual health check up of
local people)3.0 3.0 3.0 3.0 3.0
15.03 Facility of Drinking water in nearby
villages3.5 3.5 3.5 3.5 3.5
17.54 Donation for Grampanchyat
Development3.0 3.0 3.0 3.0 3.0
15.05 Toilets Facility 3.0 3.0 3.0 3.0 3.0 15.06 Internal road development and repairing
of village roads2.0 2.0 2.0 2.0 2.0
10.07 Facility of solar light along the village
roads2.0 2.0 2.0 2.0 2.0
10.08 Woman Empowerment & children
Development Activities1.0 1.0 1.0 1.0 1.0
5.09 Miscellaneous as per the demand of
surrounding villages2.5 2.5 2.5 2.5 2.5
12.5Total 24.0 24.0 24.0 24.0 24.0 120.0
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 9:Environmental Cost
Benefit Analysis
Pollution and Ecology Control Services, Nagpur P a g e | 121
CHAPTER 9
ENVIRIONMENTAL COST BENEEFIT ANALYSIS
The chapter on “Environmental Cost Benefit Analysis” is applicable only, if the same is
recommended at the Scoping Stage (As per EIA Notification dated 14th September, 2006
as amended from time to time). However, as per the TORs issued by SEAC the
Environmental Cost Benefit Analysis is not asked for hence the same has not been
required.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 10:Environmental
Management Plan
Pollution and Ecology Control Services, Nagpur P a g e | 122
CHAPTER 10
ENVIRONMENTAL MANAGEMENT PLAN
10.0 INTRODUCTION
Any industrial development is associated with certain positive impacts as well as some
negative impacts on the environment. However, the negative or adverse impacts cannot
possibly rule out scientific development. At the same time adverse impacts cannot be
neglected. An Environmental Management Plan shall be formulated for mitigation of the
adverse impacts and is based on the present environmental conditions and the
environmental impact appraisal. This plan helps in formulation, implementationand
monitoring of the environmental parameters during and after commissioning of the
project. The Environmental Management Plan describes in brief, the management plan
for proper and adequate implementation of treatment and control system for air and liquid
pollutants and for maintaining the environment. It also includes the development of green
belts in and around the plant, proper safety of the workers, noise control, fire protection
systems and measures.
10.1 PURPOSE OF ENVIRONMENTAL MANAGEMENT PLAN
The environment management plan is prepared with a view to facilitate effective
environment management of the project, in general and implementation of the mitigation
measures in particular. The EMP provides a delivery mechanism to address potential
adverse impacts and to introduce standards of good practice to be adopted for all project
works. For each stage of the program, the EMP lists all the requirements to ensure
effective mitigation of every potential biophysical and socio-economic impact identified
in the EIA. For each operation, which could otherwise give rise to impact, the following
information is presented:
• To treat and dispose-off all the pollutants viz. liquid, gaseous and solid waste so
as to meet statutory requirements (Relevant Pollution Control Acts) with
appropriate technology.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 10:Environmental
Management Plan
Pollution and Ecology Control Services, Nagpur P a g e | 123
• To support and implement work to achieve environmental standards and to
improve the methods of environmental management.
• To promote green-belt development
• To encourage good working conditions for employees.
• To reduce fire and accident hazards.
• Budgeting and allocation of funds for environment management system.
• To adopt cleaner production technology and waste minimization program
10.2 OVERVIEW OF THE POLLUTION CONTROL MANAGEMENT
10.2.1 CONSTRUCTION PHASE
(a) Air Environment
The construction activities will result in the increase of PM10, PM2.5 due to fugitive
emissions of dust. Frequent water sprinkling in the vicinity of the construction sites will
be undertaken. It will be ensured that both gasoline and diesel powered vehicles are
properly maintained to comply with exhaust emission requirements.
(b) Noise Environment
There will be marginal increase in noise levels during construction phase, which is
temporary. To control the noise levels during construction phase, the silencer of the
vehicles will be maintained properly. Noise generating equipment’s with moving part
will be lubricated which will result in reduction of noise levels. Noise prone activities
will be restricted to the day time only. On site workers working in noise prone areas
would be provided with ear muffs & plugs. Noise prone activities will be restricted to day
time only.
(c) Water Environment
Provision for infrastructural services including water supply, sewage and drainage
facilities shall be made. Sewage from construction worker site will be collected in septic
tank followed by soak pit.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 10:Environmental
Management Plan
Pollution and Ecology Control Services, Nagpur P a g e | 124
(d) Land Environment
The tree plantation will be undertaken during the construction phase so as these plants
will grow in considerable height by the time the proposed activities are in operational
stage. Excavated top soil from site will be used for tree plantation.
(e ) Socio-economic Environment
Management of M/s Sai Inductomelt Private Limited shall give preference to local people
through both direct and indirect employment.
(f) Occupational Health and Safety
Health hazards are due to dust generation, gas cutting, welding, noise and high
temperature and micro ambient conditions, which may be due to heat generated. The
precautionary measures which will be followed to reduce the risk due to dust to the
workers engaged in and around the material handling areas are:
Continuous water supply in the water spraying system will be maintained to
suppress the dust generated during construction activities.
Almost all material handling systems will be automatic thereby reducing the
manpower. The workers engaged in material handling area will be provided
with personal protective equipment like dust masks, respirators, helmets, face
shields etc.
All workers engaged in material handling system will be regularly examined
through PFT (Pulmonary Function Test) tests for lung diseases.
Any worker found positive symptoms of dust related disease will be given
medical treatment immediately.
Thermal insulation will be provided wherever necessary to minimize heat
radiation from the equipment, piping, etc. to ensure protection of workers.
Insulation thickness will be such that the covering jacket surface temperature
does not exceed the surrounding ambient temperature.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 10:Environmental
Management Plan
Pollution and Ecology Control Services, Nagpur P a g e | 125
The safety department will supervise the safe working of the contractor and their
employees. Work place will be maintained clean, with optimum lighting and
enough ventilation to eliminate dust/fumes.
Action plan for protecting the workers from the occurrence of hazardous will be
taken by safety department.
10.2.2 OPERATION PHASE
a) AIR MANAGEMENT
The major sources of pollutants are vehicular movement, material handling, crushing,
grinding and the emission from induction furnace operation. During the ambient air
quality monitoring, it is observed that the baseline concentration of air pollutants,
namely PM10, PM2.5, NO2, SO2, and CO is well below the National Ambient Air
Quality Standards (NAAQS), 2009. It is anticipated that the plant activity will not
cause any adverse effect on the existing baseline status. Fugitive emissions will be
controlled with the following recommended measures:
• Development of green belt in the plant area.
• Use of water sprinkling system in haulage roads for dust suppression.
• Over loading shall be avoided during crushing and grinding of Scrap.
• Proper maintenance of haulage roads, which are being used for transportation
of material
• Dust mask will be provided to all workers working in dust generating area.
• Spread of dust from grinding mill will be controlled with the help of
enclosures and dust collectors.
• Overloading of trucks will be avoided.
• Utmost care and regular inspection schedule will be carried out to prevent any
fugitive emission of dust during manufacturing process and transportation of
material from one place to another.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 10:Environmental
Management Plan
Pollution and Ecology Control Services, Nagpur P a g e | 126
Air Pollution Control Equipment
There will be two major source of air pollution in the plant, fugitive emissions from
various material handling and transfer points and flue gases generated from induction
furnace. Dust and fume extraction system will be provided for Induction Furnace.
Dust and fumes will be collected with the help of bag filter as air pollution control
system of specified size followed by 30 m stack. Flue gases generated will be cleaned
in the Bag Filters and discharged through stack, so that the dust concentration will be
well within the prescribed standard.
Height of the all the flue gas discharge facilities will be designed as per CPCB norms.
The various places where the flue gases will be discharge are shown in the Table.
AIR POLLUTION CONTROL SYSTEM
S.No Process Air Pollution Control System Stack
Height
1 Induction Furnace Bag filters air pollution control
system of specified size.
30 Mtrs.
b) WATER ENVIRONMENT
There will be no industrial wastewater generation and the domestic wastewater generated
will be treated in septic tank and soak pit system.
c) RAIN WATER HARVESTING SYSTEM
Rainwater harvesting is a mechanism involved in collecting, storing and putting rainwater to use
when it is most needed. A rainwater harvesting system comprises of various stages -
transporting rainwater through pipes or drains, filtration, and storage in tanks for reuse or
recharge.
Rain water harvesting can be done by three ways;
• Recharge through Roof Top
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 10:Environmental
Management Plan
Pollution and Ecology Control Services, Nagpur P a g e | 127
• Rain water storage Tank
• Recharge through surface run-off
There are five components in a rainwater harvesting system namely
catchment, conveyance, filtration, storage and recharge.
Advantages of Rain Water Harvesting
There are various advantages of Rain Water Harvesting from which some of them are
listed below:
• Outsourcing is reduced as it allows use of rainwater in case of scarcity.
• Solution to water problems.
• Effective rise in Ground Water levels.
• Inexpensive and simple technology.
• It’s economical & energy saving as it prevents extraction of water
from depleting Ground Water Table.
• Provides high quality water, having low mineral content.
• Easy operation & maintenance.
• Reduces soil erosion.
Design of Rain Water Harvesting
Quantity of Rain water collected depends upon:
• Average Rainfall Intensity.
Catchment area.
• Run-off coefficient
Co-efficient and Factor Adopted:
Runoff Co-efficient
Surface Type Run off Co efficient
Roof top area of building/sheds 0.85
Road and Paved area 0.5
Green belt area 0.2
(Source: Concepts & Practices for Rain Water Harvesting CPCB)
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 10:Environmental
Management Plan
Pollution and Ecology Control Services, Nagpur P a g e | 128
Retention Time in Recharge Well
(10 - 15) min per hour
Volume of Harvesting Pit
Q * Retention Time
Where,
Q = Catchment Area x Harvesting Factor x Rainfall intensity (mm/ hour)
Rainwater harvesting Quantity
Factory roof, offices building, all remaining civil constructions rain water is collected in
underground water storage tank through pipeline. Collected water will be used for
gardening and domestic purpose. Total rain water harvesting in year is given a below.
S.N.
Type ofStructure/
Surface
Area [A]Sq. m
Run offCoefficient [C]
Filterefficienc
y
Averagerainfall
(m/year)
Discharge (Run off) [Q=CIAF] (m3/year)
TotalDischarge[Q](m3/y)
a)
Roof toparea of
building/sheds
23408.7 0.85 0.8 0.438 23408.7x0.85x0.8x0.438 6972.04
b)
Road andPaved areaand open
space
8468.140.5 0.8 0.438 8468.14x0.5x0.8x0.438 1483.61
c)
Green beltarea
17877.8 0.2 0.8 0.438 17877.8x0.2x0.8x0.438 1252.87
Total - - 9708.54
d) NOISE ABATEMENT
Noises from fans, centrifugal pumps, electrical motors etc. will be kept in control so that
the ambient noise level shall not exceed 75dBA during daytime and 70dBA during
nighttime. Noise pollution control measures will be provided in respective departments
by way of providing silencers soundproofs cubicles/ covers and proper selection of less
noise prone machinery and by development of green belt.Ear muffs, ear plugs, etc. will
be provided to workers when the noise levels exceed 85 dB (A). Regular maintenance
will be carried out for equipment and various machines.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 10:Environmental
Management Plan
Pollution and Ecology Control Services, Nagpur P a g e | 129
e) ENVIRONMENTAL MONITORING
Necessary provisions for routine monitoring of stack emissions, ambient air quality, noise
level, water quality as required by the regulations will also be provided.
f) SOLID WASTE MANAGEMENT/DISPOSAL
The solid waste generated will be in the form of slag. The total quantity of proposed slag
generation will be approx. 11,100 TPA. Slag crushers will be installed to recover iron
particles to be reused in Induction Furnace. Slag generated from Induction Furnace will
be used for hardening of working area, internal road, brick manufacturers and concreting.
The used machine oil of 0.1 TPA will be sell to registered oil vendors only.
g) GREENBELT DEVELOPMENT
Development of a greenbelt around the proposed facility mitigates to a certain extent the
potential negative impact on the environment due to dust, air emissions, fugitive emission
and noise. A green cover itself acts as containment for dust. Presence of a green belt, will
lead to micro-climate and soil quality balancing, by retaining soil moisture, recharge of
ground water as well as self-control of micro- climate of that area. It also improves the
aesthetic value of the area, later on it becomes the natural habitat of various bird species.
Development of a green belt around the proposed project site will also help to contain
noise generated during construction and operational phases.
In view of this, plantation and green belt development will be taken care in the plant and
the space reserved for plantation will be more than 33% of the total plant area. Plantation
will be made accordingly. For development of green belt Rs50,000 per Ha will be
allotted. The selection of plant species will be based on the local soil conditions. Post
plantation care like watering and protection from grazing will be done. The plant species
recommended for strengthening the existing plantation are presented in Table. However
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 10:Environmental
Management Plan
Pollution and Ecology Control Services, Nagpur P a g e | 130
the selection of the species will be finalized in consultation with the local Forest
Department.
PLANT SPECIES SUGGESTED FOR GREEN BELT DEVELOPMENT
Sr.No
Botanical name of theplant
Size of thegrown up tree
Type and suitable site, where the plants are to beplotted
1 acacia auriculiformis Medium Semi-evergreen fragrant white flowers suitablein green belts and on road sides
2 Adina corodifolia Large Deciduous, a light demander, suitable on open areas andnear flares
3 Aeglemarmelos Medium Deciduous, good for green belts.4 Anogeissuslatifolia Medium Deciduous, Suitable for green belts5 Artabotryshexapetalus Small Evergreen shrub with fragrant flowers good for gardens
and inside boundary wall and long canals7 Azadirachtaindica Large Evergreen, suitable in green belts along the boundary and
outside office & sensitive buildings like hospitals.8 Bauhinia variegate Medium Deciduous, good in green belts in garden and as a second
row avenue tree9 Borassusflabellifer Large A tall deciduous palm can be used as wind break when of
different age.10 Boswelliaserrata Medium Deciduous suitable on green belt on willow soils11 Caesalpiniapulcherrima Small A large shrub, suitable for gardens outside offices and
along channels12 Callistemon lanceolatus Medium Deciduous for some time, ornamental plant in garden
13 CareyaArborea Large Deciduous, good in green belts14 Cassia fistula Medium Deciduous, good ornamental tree in green belts.15 Cassia siamea Large Evergreen, good as an avenue tree.16 Ficusreligiosa Large Deciduous, widely spaced avenue tree also as a single tree
in isolated sites.17 Maducaindica Medium Deciduous, good in green belts.18 Peltophoruminerme Medium Semi evergreen, suitable on road sides, in gardens and
outside office buildings.19 Saracaindica Medium
Evergreen tree good on road sides within campus
20 Tamarindusindica LargeEvergreen tree good along boundary and road sides.
21 Terminaliacatappa Large Deciduous tree
22 Terminaliaarjuna LargeEvergreen tree for road sides and in green belts
23 Zanthoxylumalatum Medium Deciduous in green belts
h) OCCUPATIONAL HEALTH AND SAFETY
Project proponent will provide all necessary provisions under Factory Act. In addition a
Safety committee will be formed and manned by equal participants from Management
and Workers.Besides the above, the operating and maintenance personnel will be
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 10:Environmental
Management Plan
Pollution and Ecology Control Services, Nagpur P a g e | 131
provided with all the necessary safety equipment such as hand gloves, gum boots, aprons,
helmets, protective glasses, ear muffs etc.
Workers training will focus on reduction of wastes, utilization of wastes and generally
maintaining a clean and healthy environment.Company under its safety policy issues
Helmets, safety shoes, Safety goggles and location specific personal protective equipment
twice a year and has the policy to penalize the person not using the PPE in work area. All
the Internal roads are concrete trimix with speed breakers where ever required. Company
conduct annual medical health checkup for all employees and keep the record for future.
Pre-employment medical checkup is carried out by authorized medical officer
10.3 ENVIRONMENT MANAGEMENT POLICY & ENVIRONMENT COMMITTEE
The Company is very much oblivious of its responsibility in protecting the Environment.
Thus various mitigation measures as given in the report shall be taken-up and effort will
be made to nullify the effect of the Project, on the Environment, if any. Any action or
effort remains incomplete, if it is not monitored properly at regular intervals and
corrective measures taken, wherever necessary. Regular monitoring has thus, been
provided. The Company has a well-defined policy to keep the Environment clean. The
management has decided that all effective steps shall be taken to prevent deterioration of
the existing Environment. They have formed an Environment Committee committed for
this cause. The Committee will consist of following persons as given in Figure 10.1
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 10:Environmental
Management Plan
Pollution and Ecology Control Services, Nagpur P a g e | 132
Figure 10.1 Organizational Set-up for Environmental Committee
SOP in case of any Violation is observed
• The cases of violations/non-compliances of Environment or Forest Laws, if any,
shall be reported to the Board of Directors through EHS Manager and shall
identify designate responsible person for ensuring compliance with the
Environmental Laws and Regulations.
• Comply with all relevant environmental laws and regulations to minimize risks to
health, safety and the environment.
DIRECTOR (OPERATIONS)
General Manager(Environment)
Head (EHS)
Staff
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 10:Environmental
Management Plan
Pollution and Ecology Control Services, Nagpur P a g e | 133
• Work with local government, regulatory authorities and communities to ensure
safe handling, use and disposal of all materials, resources and products.
The main aims under the said Policy are to:
• Effectively manage, monitor, improve and communicate the environmental
performance.
• Take all reasonable steps to prevent pollution.
• Set realistic and measurable objectives and targets for continual improvement of
the environmental performance.
• Ensure that all employees and contractors are trained to understand their
environmental responsibilities and create an environment that adheres to the
Company’s Policies, procedures and applicable regulations.
• Hold leadership accountable for good environment performance of our operations
and projects. Inherent in that accountability will be the commitment of
management to provide resources and successfully create an appropriate
environment
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 11:Summary & Conclusion
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 134
CHAPTER 11: SUMMARY & CONCLUSION
11.1 PROJECT DESCRIPTION
11.1.1 Introduction
Sai Inductomelt Pvt. Ltd is a Private Company incorporated in 2004. It is classified as
Indian Non-Government Company and is registered at Registrar of Companies,
Ahmedabad. Sai Inductomelt Pvt. Limited Corporate Identification Number is (CIN)
U35117GJ2004PTC044607 and its registration number is 044607. Its registered address
is plot no. 1497/B, Theosophical Lodge, Rupani Circle, Bhavnagar - 364001, Gujarat,
India.
M/s Sai Inductomelt Pvt. Ltd has proposed a project for manufacturing of Billets/Ingots
@ 2, 22,000TPA by installation of new induction furnace of capacity 2 x 25TPH and 2 x
12TPH The proposed project to be sited atSurvey no: 1020& 1021/1,Bhavnagar -
Vallabhipur Highway, Village:Chamardi, Taluka: Vallabhipur,District:Bhavnagar
(Gujarat). The total 13.29 Acreland has acquired for the proposed project.
11.1.2 Project Location & Environment Sensitivity
Sr No Particulars Details
1 Project Site Survey no: 1020 & 1021/1,Bhavnagar - VallabhipurHighwayVillage:Chamardi, Talluka :Vallabhipur,District:Bhavnagar
2 Latitude Latitude : 210 48’ 30.29” N
3 Longitude Longitude : 710 54’ 07.37 E
4 Elevation above MSL 12 m
5 Topo sheet NF 42 - 12
6 Present landuse Vaccant land, NA is obtain
7 Nearest NationalHighway/State Highway
SH 36:1.3 km in East Direction
8 Nearest Airport/ Air Strip Bhavnagar 30.Km (ESE)
9 Nearest Village/Habitates Chamardi 2.5 kms South direction
10 Forest Blackbuck National Park 30 km in NE direction
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 11:Summary & Conclusion
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 135
11.1.3 Size or Magnitude of Operation
The proposed project will installed four induction furnace having capacity of 2 x 25 TPH
and 2 x 12 TPH. The total production capacity of M.S.Billtes /Ingots will be 2,
22,000TPA.
Sr. No Name of Product Quantity (TPA)
1 M.S.Billets/Ingots 2, 22,000
11.2 DESCRIPTION OF ENVIRONMENT
Air Environment
The baseline environmental quality for the October to December – 2018 was assessed in
an area of 10 km radius around the proposed project site.
During the study period, average wind speed measured on site is 1.45 m/s. The
wind rose diagram indicates predominant wind direction is from NE with 7.25 % calm
condition
The ambient air quality monitored at 8 locations selected based on predominant wind
direction, indicated the following ranges;
PM10 - 47-84 µg/m3.
PM2.5 - 18-39 µg/m3
SO2 - 9-23 μg/m3
NO2 - 11-26 μg/m3
CO - 0.2-0.91 mg/m3
11Ecologically SensitiveZones like wild lifesanctuaries, national parksand biospheres
Archaeological structures, Historical places, Sanctuariesand Biosphere are not present within 10 km
12 Water Bodies Rangholi River 0.6Km South directionKalubar River 1.5Km NE directionGautameshwar Dam 13 Km SE DirectionGulf of Khambhat 36.0Km in East DirectionGhelo River 7.8 Km in North Direction
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 11:Summary & Conclusion
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 136
NATIONAL AMBIENT AIR QUALITY STANDARDS
PollutantTime weighted
Average
Concentration in air
IndustrialAreas, residential rural &
other areas
PM10 24 hours 100.0 µg/m3
PM2.5 24 hours 60.0 µg/m3
Nitrogen Dioxide (NOx) 24 hours 80.0 µg/m3
Sulphur dioxide (SO2) 24 hours 80.0 µg/m3
Carbon Monoxide (CO0 8 hours 2.0 mg/m3
The concentrations of PM10, PM2.5, SO2 NO2 and CO were found within the National
Ambient Air Quality Standards (NAAQ).
Water Environment
A total 10 samples including four surface & six ground water samples were collected and
analyzed. The water samples were analyzed as per Standard Methods for Analysis of
Water and Wastewater, American Public Health Association (APHA) Publication.
The data indicates that the ground water as well as the surface water quality is below the
stipulated standard for drinking water (IS 10500 of 2012).
Noise Environment
Noise levels measured at eight stations. Noise level is quietly exceed than prescribed
limit of 55.0 dB (A) for Residential Area. However noise level in industrial area is within
limit of 75.0 dB (A) for Industrial Area as given in MoEF Gazette notification for
National Ambient Noise Level Standard.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 11:Summary & Conclusion
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 137
Area Code Category of AreaLimits in dB(A) Leq
Day time Night time
A Industrial Area 75 70
B Commercial Area 65 55
C Residential Area 55 45
D Silence Zone** 50 40
**Silence zone is defined as area up to 100 meters around premises of hospitals, educational institutions and courts. Use of
vehicle horns, loud speakers and bursting of crackers are banned in these zones
11.3 ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATIONMEASURES
Air Environment
The impacts on air quality due to source of the air pollutant in the proposed facilities have
been identified.
Sources of Emissions
Emissions released from the stack during operation phase will get dispersed in the
atmosphere and finally reach the ground at a specified distance from the sources. From
the proposed activities the possible environmental impact on air quality has been
envisaged due to the following sources.
Raw Material Handling / Transport System
The possible pollutants are fugitive dust emissions from raw materials handling areas viz.
loading / unloading, etc.
Mitigation Measures
M/s. Sai Inductomelt Pvt.Ltd. will provide dust suction system which will control
fugitive emission due to material handling. Dust suppression system will be provided in
the form of water sprinklers. The entire length of conveyors is covered to prevent dust
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 11:Summary & Conclusion
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 138
pollution. All bins are totally packed and covered so that there is no chance of dust
leakage. All material transfer points are connected with dust suppression water nozzles to
avoid air pollution.
Manufacturing of M.S billets/Ingots
Bag filter will be provided for the extraction of dust particles. The continuous casting
operation is selected for the production of billets/Ingots in induction furnace, where there
is less attack on refractory lining, the changing need drastically comes down by 87%.
This process results in the low gases emission.
Mitigation Measures
Installation of Bag filter followed by Stack height as per GPCB norms.
The particulate matters and air borne metallic particles are generated from the
transfer of molten steel to the mold and from the cutting of the product by oxy-
fuel torches during continuous casting.
Exhaust should be fitted to filters and other relevant abatement equipment,
especially in the casting and finishing shops, wherever it is applicable.
11.4 ENVIRONMENT MONITORING PROGRAMME
The environmental monitoring is important to assess performance of pollution control
equipment installed in the expansion project of M/s Sai Inductomelt Pvt Ltd. The
sampling and analysis of environmental attributes including monitoring locations will be
as per the guidelines of the Central Pollution Control Board/ State Pollution Control
Board.
Environmental monitoring will be conducted on regular basis by M/s Sai Inductomelt
Pvt Ltd. to assess the pollution level in the proposed plant as well in the surrounding area.
Therefore, regular monitoring program of the environmental parameters is essential to
take into account the environmental pollutant of the study area. The objective of
monitoring is:
To verify the result of the impact assessment study in particular with regards to
new developments;
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 11:Summary & Conclusion
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 139
To follow the trend of parameters which have been identified as critical;
To check or assess the efficiency of the controlling measures;
To ensure that new parameters, other than those identified in the impact
assessment study, do not become critical due to the commissioning of proposed
facilities;
To check assumptions made with regard to the development and to detect
deviations in order to initiate necessary measures;
To establish a database for future Impact Assessment Studies for new projects.
The attributes, which needs regular monitoring, are specified below:
Air quality
Water and wastewater quality;
Noise levels;
Soil quality;
Ecological preservation and afforestation
Socio Economic aspects and community development
11.5 ENVIRONMENT MANAGEMENT PLAN
Overview of Pollution Control Management during Operational Phase
SOURCE POLLUTANTS CONTROL MEASURES
Air pollution from inductionfurnace due to melting of hotmetal
PM Dust and fumes will be collected withthe help of bag filter with fume hoodfollowed by 30 m stack
Solid waste Slag frominduction 11,100
TPA
Slag Crushers will be installed torecover iron particles to be reused inInduction Furnace. Slag generatedfrom Induction Furnace will be usedfor hardening of working area, internalroad, brick manufacturers, concreting.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 11:Summary & Conclusion
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 140
Air Environment
The sources of air pollution are raw material handling system, materials transportation,
raw materials feeding to the operating equipments. The automatic process equipments
will be employed for the raw material feeding system. Stacks height as per GPCB norms
is proposed for proper dispersion of flue gases.
Action Plan to Control and Monitor Secondary Fugitive Emissions from all the
Sources.
The primary fume pick up from Induction Furnace will be by a canopy hood placed over
the furnace and to convey the same single walled MS ducting will be employed.
Bag filter followed by a stack will be installed.
Fugitive emission from material unloading operations, material transfer points
will be controlled fully with total enclosure.
Fugitive as well ambient air quality monitoring shall be carried out on regular
basis to ensure the compliance with National Ambient Air Quality Standards
(NAAQS). The ambient air quality within the factory premises shall not exceed
the standards (PM10 100µg/m3, PM2.5 60µg/m3 SO2 80µg/m3, NO2 80µg/m3 and
CO 04µg/m3) prescribed by CPCB.
The monitoring frequency of air quality shall be as per the consent issued by State
Pollution Control Board and reports shall be submitted as part of compliance. The
records will be maintained.
Regular Stack Monitoring will be done. All the emissions from the plant will be
controlled to meet the relevant standard set by CPCB/State Pollution Control
Board.
Details regarding volumetric flow, temperature and emission rate of pollutants
from different stacks shall be collected and compiled regularly.
Effective steps shall be taken to control fugitive emission inside the plant. All
internal roads will be Tar Roads. Efficient arrangements will be provided to
control fugitive dust emission during handling/transportation of Raw materials /
finished product etc.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 11:Summary & Conclusion
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 141
The emission from induction furnace area will be extracted and treated in a fume
extraction system.
Fumes will be evacuated directly from induction furnaces through hoods with
swirling mechanism and ducting.
Avenue plantation will be strengthening further to control fugitive emissions &
gaseous pollutants to keep clean and healthy environment.
During induction melting of steel scrap, lot of sparks gets generated. For the
purpose of arresting sparks & flame, it is necessary to have an arrestor which
arrests sparks. The device provided will be a centrifugal cyclone, which removes
sparks and also collects coarser particles. The collected dust in the cyclone hopper
can be drained periodically into a drum when the system is shut or a continuous
motorized rotary air lock valve can be provided.
Impact on Transportation
The road (State Highway) connected with our project is SH 36 (Bhavnagar
Ahmadabad Road) Traffic intensity due to existing and proposed expansion is
worked out as below.
Sr. No. Name of Material(RM and Product)
Mode of Transportation No. of trucks/day
1 MS Scrap By Road 23
2 Sponge Iron By Road 02Total No. of Trucks/Day 25 Trucks/Day
All raw material and finished good shall be transported by road. The finished
product i.e. M.S. Billets/Ingots will be transported by the truck carrying raw
material. The plant is having good road connectivity and can be approached from
both Bhavnagar and Ahmadabad is strong to handle the traffic due to proposed
project. National highway 8E is also 6.5 km at south direction of plant site.
The additional transportation will have negligible impact on surroundings. There
is no habitation on approach road to the project site. The parking of the vehicles
will be in the project area.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 11:Summary & Conclusion
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 142
Water Environment
During plant operation no waste water will be generated from M.S. Billets/Ingots as the
water is being used for cooling the products which will be evaporated and condensed,
water if generated will be recycled. Provision for oil/grease separators will be made to
skim oil / grease, if any in the waste water. After skimming of the oil water will be stored
in guard pond. Domestic waste will be disposed through Septic Tanks along with soak
pits.
Noise Environment:
The industry will take care while procuring major noise generating
machines/equipment to ensure that the manufactures have taken adequate
measures to minimize generation of noise.
The areas where noise levels are high will be partitioned off, noise levels will be
minimized at the source, and noise reflection and transmission will be minimized.
The workers working in the high noise areas will be provided with ear muffs/ear
plugs.
Acoustic laggings and silencers will be provided in equipment wherever
necessary. Ventilation fans shall be installed in enclosed premises.
Supply ducts and grills on the ventilation and air conditioning system will be
suitably sized for minimum noise level.
The silencers and mufflers of the individual machines shall be regularly checked
The noise level shall not exceed the limit 75 dB (A) during the day time 70 dB
(A) night time within the plant premises.
Provision of insulating caps and lids at the exit of noise source and providing
polystyrene, etc. as noise insulation material will be adopted. All the openings
will be covered and partitions will be acoustically sealed.
Avenue plantation around the plant area will reduce the noise level further.
Training of personnel is recommended to generate awareness about damaging
effects of high noise levels.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 11:Summary & Conclusion
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 143
Land Environment
The main objective of the green belt is to provide a buffer between the sources of pollution
and the surrounding areas. More than 33 % of the plot area will be developed as green belt
of mixed tree species (local varieties).
The green belt helps to capture the fugitive emissions and attenuate the noise apart from
improving the aesthetics quality of the region. Dense greenbelt will be developed along the
periphery of the plant. Avenue plantation will also be developed as per the standard norms.
The general guidelines for development of greenbelt will be as follows:
Trees growing up to 5 m or more will be planted along the plant premises and
along the road sides.
Planting of trees will be undertaken in rows.
Open areas inside the plant boundary will be covered with grass lawns.
Planting of trees in each row will be in staggered orientation.
Shrubs and trees will be planted in encircling rows around the project site.
The short trees (<10 m height) will be planted in the first two rows (towards plant
side) of the green belt. The tall trees (>10 m height) will be planted in the outer
three rows (away from plant side).
Management Plan of Solid waste
Process needs refractory lining and is being changed every month.
Total Solid waste of slag generation will be about 11100 TPA after Expansion
project.
Solid waste is nonhazardous and non-toxic in nature.
Solid waste will be used for land filled, in own premises, concreting /hardening of
work area.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 11:Summary & Conclusion
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 144
SOCIO-ECONOMIC ENVIRONMENT
The project proponent would aid in the overall social and economic development of the
region. The manpower requirements for the operational phase of the proposed project
will be about 325 people. In addition, there will be an indirect employment for skilled/
semi-skilled people during project life. All attempts will be made to employ suitable,
locally available, skilled personnel from the nearby area. In order to mitigate the adverse
impacts likely to arise in the proposed project activities and also to minimize the
apprehensions to the local people, it is necessary to formulate an affective EMP for
smooth initiation and functioning of the project. The suggestions are given below:
Communication with the local people will be established regular basis by project
authority to provide an opportunity for local youth.
Project authorities will undertake regular environmental awareness program on
environmental management.
Job opportunities are the most demanding factor, the local people as per their
education will be employed.
For social welfare activities to be undertaken by the project authorities,
collaboration should be sought with the local administration, gram panchayat,
block development office etc for better coordination.
Occupational Safety & Health Management
Project proponent will provide all necessary provisions under Factory Act. In addition a
Safety committee will be formed and manned by equal participants from Management
and Workers. All personal protect equipments like Safety shoes, helmet & uniform will
be issued to each employee based on the nature of job involved. In case a person inhales
CO, he should be removed to fresh air and given mediated oxygen through a mask for 30
minutes and if required cardiopulmonary resuscitation should be performed.
EIA on Proposed project for manufacturing of Billets/Ingots @ 2, 22, 000TPA
Project Proponent: M/s SAI INDUCTOMELT PRIVATE LIMITED
Chapter 11:Summary & Conclusion
Pollution and Ecology Control Services(PECS), Nagpur P a g e | 145
11.6 CONCLUSION
Based on the study it is concluded that-
• There will be no major impact on water environment as generated
• Domestic wastewater will be disposed in the septic tank followed by soak pit.
• Electrically operated induction furnace is used and it will be equipped with
suction hood, followed by bag filter.
• To prevent fugitive emission, from material unloading operations regular
sprinkling of water will be done.
• For noise control, unit will provide necessary PPEs like earplugs or earmuffs to
all workers
• Entire quantity of hazardous waste will be handled and disposed as per Hazardous
& Other Waste (Management & Trans-boundary Movement) Rules, 2016.
• Direct and indirect employment opportunities will have positive impact
EIA/EMP OF SARDA ENERGY AND MINERALS LIMITEDDISCLOSURE OF CONSULTANTS ENGAGED
PECS, Nagpur 146
CHAPTER 12
DISCLOSURE OF CONSULTANTS ENGAGED
12.0 INTRODUCTION
The EIA/EMP report for “Sai Inductomelt Pvt.Ltd” at Village Mandhar, Raipur
Chhattisgarh”, has been prepared by Pollution and Ecology Control services (PECS),
Nagpur accredited by QCI/NABET for preparing EIA/EMP reports in 10 major sectors,
including “Metallurgical industries (ferrous & non-ferrous) – both primary and
secondary” vide certificate no. NABET/EIA/1720/RA 0101 dated 07.09.2018. This
certificate is valid up to 15.11.2020. The details of sectors accorded to PECS under the
QCI-NABET scheme for accreditation of EIA consultant organization is given below:
Table 12.1 Details of sectors accorded to PECS under the QCI-NABET scheme for
accreditation of EIA consultant organization
EIA/EMP OF SARDA ENERGY AND MINERALS LIMITEDDISCLOSURE OF CONSULTANTS ENGAGED
PECS, Nagpur 147
12.1 PROFILE OF EIA/EMP CONSULTANT
PECS established and NABET accredited Environmental Consultant and Engineers based
in Nagpur and working since last 28 years. We are having tie up with well-equipped
laboratory for field studies as well as for testing and monitoring of Air, Water, Noise,
Soil and other related activities of Environment of Mines and Industries.
PECS is having a qualified and experience staff comprising of trained professionals in
their respective fields. PECS is backed by the services of retired scientists form National
Environmental Engineering Research Institute (NEERI) and retired Engineers of Thermal
Power Stations and Coal India Ltd. A team of experience Geologists is with us for
various surveys. PECS is also having a computers and software facility for modeling
purposes.
PECS is specialized in Environmental Services as mentioned below:-
o Environmental Impact Assessment (EIA)
o Environmental Risk Analysis and Assessment.
o Monitoring of Air, Water, Noise and Soil.
o Preparation of Documents for Clearance of Forest Land.
o Environmental Management Plan.
o Environment Audit Statement.
o Disaster Management Plan.
o Study and Treatment of Industrial Effluents.
o Design, Engineering and Commissioning of Effluent Treatment Plant, SewageTreatment Plant and Water Treatment Plant.
o Designing, Engineering and Commissioning of Air Pollution Control Devices.
o Dust Suppression.
o Dealing with Solid Waste Management.
EIA/EMP OF SARDA ENERGY AND MINERALS LIMITEDDISCLOSURE OF CONSULTANTS ENGAGED
PECS, Nagpur 148
o Planning on Waste Recycle, Reuse and Control
o Follow up with Explosive Department and IBM, HQ, Nagpur.
o Preparation of “ON SITE” and “OFF SITE” emergency plans and health survey.
o Geo Hydrological, Ground and Surface Water Survey and Transit Survey.
o Rain water harvesting including design and execution.
o Clearing of Project form Ministry of Environment and Forest, New Delhi(MOEF),) and State Pollution Control Board (SPCB)/SEIAA.
PECS has completed more than 50 projects in EIA sector successfully since its
incorporation.