Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual...

110
Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405 July 2020 Nepal: Third Small Towns Water Supply and Sanitation Sector Project Prepared by the Government of Nepal for the Asian Development Bank This Environmental Compliance Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Transcript of Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual...

Page 1: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

Environmental Compliance Monitoring Report

Semi-Annual Report Project Number: 35173-013

Loan Numbers: 3157 and 8304, Grant Number:0405

July 2020

Nepal: Third Small Towns Water Supply and Sanitation Sector Project

Prepared by the Government of Nepal for the Asian Development Bank

This Environmental Compliance Monitoring Report is a document of the borrower. The views expressed

herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be

preliminary in nature. Your attention is directed to the “terms of use” section of this website.

In preparing any country program or strategy, financing any project, or by making any designation of or

reference to a particular territory or geographic area in this document, the Asian Development Bank does

not intend to make any judgments as to the legal or other status of any territory or area.

Page 2: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

Government of Nepal Asian Development Bank

Ministry of Water Supply

Semi-Annual Environmental Monitoring

Report-VII (January-June) 2020

Submitted in July 2020

PROJECT MANAGEMENT OFFICE (PMO)

Third Small Towns Water Supply and Sanitation Sector Project Loan

3157

Department of Water Supply and Sewerage Management

Ministry of Water Supply

Page 3: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

i

Executive Summary

Environmental Monitoring of Third Small Towns Water Supply and Sanitation Sector project has been

conducting as per Safeguard Policy of Asian Development Bank (ADB) and Environment legislation of the

Government to determine the degree of environmental impacts of the selected town projects during

project planning and implementation complying effectiveness of the mitigation measures. Project

Screening and Environment Categorization of ADB classification system to reflect the significance of a

project’s potential environmental impacts determining project category considering the mostly

environmentally sensitive component, including direct, indirect, cumulative, and induced impacts in the

project’s area of influence, all town projects are classified under Category B. Similarly, the prerequisite requirement of environmental legislation Environment Protection Act (EPA) 2019 and Environment

Protection Regulation (EPR 2020), Government of Nepal (GoN), selected town projects have to accompany

Initial Environmental Examination (IEE) studies.

The operational policies of the ADB include three safeguards Policies involve a structured process of

impact assessment, planning, and mitigation to address the adverse effects of projects throughout the

project cycle. The safeguard requirements of the policies involve impact identification and assessment

early in the project cycle, development and implementation of plans to avoid, minimize, mitigate, or

compensate for the potential adverse impacts and affected information dissemination and consultation

with the local people during project preparation and implementation.

The National Environmental Impact Assessment Guideline (1993) requires that monitoring types,

indicators, schedules, and responsibility to be identified in the IEE report and as per Rule 45 of the EPR

2020, the concerned agency – here the Ministry of Water Supply (MoWS), Department of Water Supply,

and Sewerage Management (DWSSM) is the legally responsible monitoring agency. This Rule also

empowers responsible agency to issue additional environmental control measures and directives for the

project to adopt mitigation measures if the actual impacts are higher than the ones specified in the

conditions prescribed at the time of approving the proposal for implementation. The sole of this

monitoring program has also been guided by ADB’s Safeguard Policy Statement (SPS) 2009 and its

requirements. The ADB-financed projects has required provisions of the policies to undertake social and

environmental assessments, carry out consultations with affected people and communities, prepare and

implement safeguard plans, monitor the implementation of these plans, prepare and submit monitoring

reports. Thus, this Semi-Annual Environmental Monitoring Report of January to June 2020 has prepared

covering Third Small Towns Water Supply and Sanitation Sector projects (TSTWSSSP).

Approach and Methodology: The approach and methods mainly focused on approved IEE reports and

Environmental Management Plan (EMP) of the selected Town projects. The main methods adopted to

prepare this monitoring reports covers; literature review, collection of primary data from field level

measurement and survey, inspection/observation, consultation and interaction with community,

stakeholders and local people covering physical, biological socio-economic & cultural environment during

planning and implementation stages of the town projects. The monthly progress reports submitted to

Project Management Office (PMO) through Regional PMO with support from Design, Supervision, and

Management Consultant (DSMC) duly reflected during preparation of this environmental monitoring

report.

Compliance with Environmental Covenants: The project has met all the compliance requirements of the

GoN and ADB, approving Terms of Reference (ToR) and IEEs of selected Town subprojects from MoWS

fulfilling legal and procedural requirements. Total 21 IEE reports of all TSTWSSSP have already approved.

Status of Project Implementation: Altogether 8 projects of Eastern Regional Design, Supervision and

Management Consultant (ERDSMC) entered in Operation and Maintenance (O & M) and Defect Liability

Period (DLP) phase and Charali, Jhapa and Mahendranagar, Sunsari is completed. Bidur Nuwakot and

Ramnagar-Mirchaiya Strom Draingae, Siraha are under construction phase. Among the 11 subprojects of

Page 4: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

ii

Western Regional Design, Supervision and Management Consultant (WRDSMC), Khalanga Sitalpati and

Tikapur subprojects have been crossed DLP phase and other 9 projects are DLP and O & M stages.

Institutions and Responsibilities: The concerned institutions and responsibilities for environmental

monitoring reveals as executing agency, the MOWS, GoN, working through the DWSSM, which has

established a PMO for the project headed by a Project Director. The PMO is responsible for overall project

planning, management, implementation, monitoring and reporting of the project. The DWSSM has

established two RPMOs. The Water User and Sanitation Committees (WUSC), on behalf of the Water Users

Association or the municipality is responsible for O & M of the water supply and sanitation facilities

constructed, operating under a management agreement with PMO/DWSSM.

Compliance Status with the Environment Management and Monitoring Plans: The EMP of individual

Town projects has included proposed mitigation measures of the project activities, environmental

monitoring and reporting requirements, emergency response procedures, related institutional or

organizational arrangements, capacity development and training measures, implementation schedule,

cost estimates, and performance indicators. Detailed project wise Compliance Status with EMP and

Monitoring Plans of the each subprojects of Eastern and Western Regions are presented in this report.

The contractor and workers were oriented/trained and made aware of their responsibility towards

Environmental Safeguard issues during construction works, such as:

• Adhering to the relevant adverse environmental impacts mitigation measures that are set out in

the EMP during carrying out construction activities of the sub-project;

• Assessing the conditions of surrounding environmental conditions, status of adjacent cleared area

and other infrastructure, prior to construction commencement and upon completion of

construction and thereby fully reinstating the environment to at least their pre-project conditions

and;

• EMP implementation throughout the project cycle

Monitoring of Environmental Impacts on Project surroundings: Regular monitoring carried out to comply

activities outlined in EMP of the proposed subprojects. Comprehensive environmental monitoring

parameters include monitoring of principle components like Greenery Promotion and Plantation, Pollution

Prevention and Abatement, Campsite Management, Solid Waste and Drainage Management, Health and

Safety, Physical Cultural Resources and Grievance Redress Mechanism (GRM) facility under the

supervision of the consultant’s Environmental Specialist. Detailed Compliance Status of the TSTWSSS

Project presented in each individual town projects included as per EMP implementation and monitoring

activities carried out during construction and O & M stages of the project.

Public Consultation: Consultation carried out in a manner commensurate with the impacts on affected

communities during the field visit. The contractor’s personnel and onsite staff from the Consultant were oriented/ trained and made aware of their responsibility towards Environmental Safeguard issues, during

construction works, such as:

• Adhering to the relevant adverse environmental impacts mitigation measures that are set out in

the EMP during carrying out construction activities; and

• Assessing the conditions of surrounding environmental conditions, status of adjacent cleared area

and other infrastructure, prior to construction commencement and upon completion of

construction and thereby fully reinstate the environment to at least their pre-project conditions.

GRM: A town project-specific GRM has been established in construction phase of each town projects to

receive record, evaluate, and facilitate the resolution of AP’s project related concerns, complaints, and grievances.

Overall Findings and Recommendations/Remedial Actions

Observations

Page 5: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

iii

• Air, water quality and noise level monitored periodically and continued up to project implementation

period

• Some town projects lies within community forest area within direct and indirect impact area, where

possible loss of forest and vegetation is an issue that can be highly considered to protect and

promoting plantation in project environment. The projects under DLP and O & M Stages, remaining

EMP activities, greenery promotion and plantation activities are ongoing

• More environmental awareness to the workers is required regarding health safety equipment (OSE)

as the contractors has provided OHSE equipment’s and first aids, which are not fully utilized

• Construction work has not carried out nearby streams or water bodies and contamination on surface

water not observed.

• Solid waste properly managed and no any complaint against construction activities reported by the

local people

• Employment opportunity given to the local communities, child labor not involved and not any conflict

with the local communities

• Most of the implementation activities in later stages hampered due to COVID-19 Pandemic.

Key environmental issues

• Implementation of EMP activities during project implementation like seasonal testing of water

quality, proper management of liquid and solid waste, plantation activities, efficient campsite

management, proper mitigation of air, nose and water pollution

Action Away forward

• Implementation of EMP activities till the project completion period

• Avail primary aid facility and OHS equipment to the workers including increment level of awareness

• Need erection of safety signs, awareness raising regarding plantation and biodiversity conservation

• Conduct training and awareness programs to the workers, user committee members and concerned

stakeholders as recommended in the EMP

• Need to prepare Site-specific EMP (SEMP) that includes the occupational health and safety (OHS)

plan and a Standard Operating Procedure (SOP) to manage COVID-19 risks in the work place

considering the prevailing pandemic situation and the guidance issued by GoN.

Conclusion

The subprojects scope towards civil works from design, construction to implementation that cause

impacts/issues and concerns addressed through adopting existing government legislation of Nepal, ADB

SPS, strategy, and guidelines. To ensure that the projects are environmentally sound, designed to operate

in compliance with applicable regulatory requirements and not likely to cause significant environmental,

health, or safety hazards, ADB’s SPS screening criteria resembles selected TSTWSS subprojects under

'Category B' and IEE of all projects approved from MoWS under prerequisite legislative requirement of

GoN.

Monitoring compliance with EMP implementation and safeguard measures are ongoing as per progress

status of the project. Among 21 TSTWSSP projects, Charali Jhapa, Mahendranagar Sunsari, Sitalpati Salyan

and Tikapur Kailali have been completed and remaining 16 projects are under implementation stage.

Bidur_Nuwakot, Ramnagar-Mirchaiya Storm Drainage and Beautification of Charali FSMTP are under

construction phase. Furthermore, IEE of 12 selected enhancement projects have been approved and

enhancement work is on progress. The two Regional DSMCs assisting the RPMOs with the overall planning,

implementation and monitoring of each subproject during all stages of implementation including

adherence to all environmental and social safeguards requirements working together with the WUSCs,

local bodies (LBs) and communities. Considering the nature of the project, only minor negative impacts

on the project sites observed. The overall implementation, supervision and monitoring of the EMP

activities concerning environmental safeguards status of the town projects is satisfactory. Proper

implementation of EMP as approved IEE reports, site specific EMPs of individual projects considering OHS)

plan and a SOP to manage COVID-19 risks in the work place and additional site-specific issues identified

need to be address and monitor during all stages from pre-construction, construction to O & M phases.

Page 6: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

i

Abbreviations

ADB Asian Development Bank

AP Affected Person

AM Accountability Mechanism

CRO Complaint Receiving Officer

DI Ductile Iron

DOWSSM Department of Water Supply and Sewerage Management

DRTAC Design Review and Technical Audit Consultant

DSMC Design, Supervision, and Management Consultant

EA Executive Agency

EARF Environmental Assessment and Review Framework

EIA Environmental Impact Assessment

EMP Environmental Management Plan

EMR Environmental Monitoring Report

EO Environmental Officer

EPA Environment Protection Act

EPR Environment Protection Regulations

ESA Environmental Safeguard Assistant

ESE Environmental Safeguard Expert

FSM Fecal Sludge Management

GI Galvanized Iron

GoN Government of Nepal

GRM Grievance Redress Mechanism

GRC Grievance Redress Committee

HHs Households

ICG Implementation Core Group

IPP Indigenous People Plan

IEE Initial Environmental Examination

MoWS Ministry of Water Supply

MoFE Ministry of Forests and Environment

NCB National Competitive Bidding

NEA Nepal Electricity Authority

NPR Nepalese Rupees

NOC No Objection Certificate

OHS Occupational Health and Safety

OBA Output Based Aid

O & M Operation and Maintenance

PMO Project Management Office

REA Rapid Environmental Assessment

RP Resettlement Plan

ROW Right of Way

RDSMCs Regional Design Supervision & Management Consultants

RPMO Regional Project Management Office

SPS Safeguard Policy Statement

TDF Town Development Fund

ToR Terms of Reference

TSTWSSSP Third Small Towns Water Supply and Sanitation Sector project

USD United States Dollar

UWSSSP Urban Water Supply and Sanitation Sector Project

WASH Water Sanitation and Hygiene

WHO World Health Organization

WSSDO Water Supply and Sanitation Divisional Office

Page 7: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

ii

WTP Water Treatment Plant

WUSC Water Users’ and Sanitation Committee

WEIGHTS AND MEASURES

C Celsius/centigrade

Dba decibel audible

Ha hectare/s

Km kilometer

Kph kilometer/s per hour

m meter

m3 cubic meter/s

Amsl Above mean sea level

mg/l

Mm

milligram/s per liter

millimeter/s

Page 8: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

iii

Contents Executive Summary ........................................................................................................................................ i

Abbreviations ................................................................................................................................................. i

List of Tables ................................................................................................................................................. v

List of Figures ................................................................................................................................................ vi

List of Pictures ............................................................................................................................................... vi

1. INTRODUCTION ..................................................................................................................................... 1

1.1. Background ........................................................................................................................................... 1

1.2. Status of Town Projects ........................................................................................................................ 2

1.3. Compliance with Environmental Covenants......................................................................................... 4

1.4. Institutional Arrangement and Responsibilities for Implementation of Environmental Safeguards . 13

2. APPROACH AND METHODOLOGY FOR ENVIRONMENTAL MONITORING .......................................... 15

2.1. Desk Study/Literature Review ............................................................................................................ 15

2.1.1. Collection and review of secondary sources .............................................................................. 15

2.1.2. Meeting, Interaction, and Review of Progress Activities ............................................................ 15

2.2. Field Work ........................................................................................................................................... 16

2.2.1. Interaction and consultation with the local community ............................................................ 16

2.3. GRM and Composition of GRC ............................................................................................................ 17

2.3.1. GRM Steps and Time Frame ....................................................................................................... 17

2.3.2. Establishment and Composition of GRC ..................................................................................... 18

2.4. Monitoring and Reporting .................................................................................................................. 19

3. COMPLIANCE STATUS WITH THE ENVIRONMENTAL MANAGEMENT AND MONITORING PLANS ..... 20

3.1. Compliance Status with Environmental Management and Monitoring Plans of Town Projects of

ERDSMC ...................................................................................................................................................... 20

3.1.1. Charali Jhapa Water Supply and Sanitation Project ................................................................... 21

3.1.2. Mahendranagar, Sunsari Water Supply and Sanitation Project ................................................. 21

3.1.3. Ramnager-Mirchaiya, Siraha Water Supply and Sanitation Sector Projects .............................. 22

3.1.4. Katari, Udayapur Water Supply and Sanitation Sector Projects ................................................. 26

3.1.5. Sakhuwa-Mahandranager, Dhanusa Water Supply and Sanitation Sector Projects .................. 30

3.1.6. Lalbandi, Sarlahi Water Supply and Sanitation Sector Project ................................................... 34

3.1.7. Katahariya, Rautahat Water Supply and Sanitation Sector Project ............................................ 39

3.1.8. Birendranager, Chitwan Water Supply and Sanitation Sector Project ....................................... 42

3.1.9. Bidur, Nuwakot Water Supply and Sanitation Sector Project .................................................... 46

3.1.10. Ramnagar Mirchaiya Storm Drainage Project, Siraha................................................................. 50

3.2. Compliance Status with Environmental Management and Monitoring Plans of Town Projects of

WRDSMCS ................................................................................................................................................... 51

Page 9: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

iv

3.2.1. Aabukaireni Tanahu Water Supply and Sanitation Project ........................................................ 52

3.2.2. Chhap Nahala Dumre Tanahun Water Supply and Sanitation Project ....................................... 55

3.2.3. Nirmalpokhari Kaski Water Supply and Sanitation Project ........................................................ 57

3.2.4. Tamsariya Nawalparasi Water Supply and Sanitation Project.................................................... 59

3.2.5. Chandrauta Kapilvastu Water Supply and Sanitation Project .................................................... 62

3.2.6. Rukum Musikot Water Supply and Sanitation Project ............................................................... 65

3.2.7. Babiyachaur Surkhet Water Supply and Sanitation Project ....................................................... 67

3.2.8. Suda Kanchanpur Water Supply and Sanitation Project ............................................................. 69

3.2.9. Amargadi Dadeldhura Water Supply and Sanitation Project ..................................................... 71

4. MONITORING OF ENVIRONMENTAL IMPACTS ON PROJECTS SURROUNDINGS ................................ 76

4.1. Training, Orientation and Community Awareness ............................................................................. 76

4.2. Pollution Prevention and Abatement ................................................................................................. 77

4.2.1. Ambient Air Quality ..................................................................................................................... 77

4.2.2. Water Quality .............................................................................................................................. 78

4.2.3. Noise Level .................................................................................................................................. 78

4.3. Solid Waste Management .................................................................................................................. 79

4.4. Occupational Health & Safety; and Community Health & Safety....................................................... 79

4.5. Camp Site Management ..................................................................................................................... 79

4.6. Public participation and Consultation ................................................................................................ 79

4.7. Community Awareness and Participation .......................................................................................... 80

4.8. Stakeholder Consultations and Participation ..................................................................................... 80

4.9. Protection Works, Bioengineering and Drainage Management......................................................... 81

4.10. Plantation and Greenery Promotion .................................................................................................. 82

4.11. Grievance Redress Committees .......................................................................................................... 82

5. OVERALL FINDINGS AND RECOMMENDATIONS/REMEDIAL ACTIONS ............................................... 84

5.1. Observations ....................................................................................................................................... 84

5.2. Key Environmental Issues ................................................................................................................... 84

5.3. Additional Actions Planned ................................................................................................................. 84

5.4. Operation & Maintenance Phase ....................................................................................................... 85

5.5. Risk from COVID-19 in the Project Area ............................................................................................. 85

5.6. Major Issues and Way Forward .......................................................................................................... 86

6. ACHIEVEMENT ON MAJOR ISSUES OF FOCUS ON PREVIOUS REPORT ............................................... 87

6.1 Major items of focus for next report .................................................................................................... 90

7. CONCLUSION AND RECOMMENDATION ............................................................................................ 93

References .................................................................................................................................................. 94

Page 10: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

v

ANNEXES ..................................................................................................................................................... 95

Annex I: Public Awareness and Grievances Records ................................................................................. 96

Annex II: Public Awareness and Community Participation ......................................................................... 98

Annex III: Photographs ................................................................................................................................ 99

List of Tables

Table 1: Status of IEE Studies ........................................................................................................................ 4

Table 2: Grant Covenants and Status of Compliance ................................................................................... 6

Table 3 : Summary of Projects and Status of ERDSMC ................................................................................. 7

Table 4 : Summary of Project and Status of WRDSMC ................................................................................. 8

Table 5 : Status of Environmental Safeguards during Planning Stage (June, 2020) ..................................... 9

Table 6 : Status of Environmental Safeguards during Planning Stage (January- June 2020) ...................... 11

Table 7 : Overall Compliance with EMP of Charali Water Supply and Sanitation Sector Project ............... 21

Table 8 : Overall Compliance with EMP ...................................................................................................... 22

Table 9 : Ramnagar-Mirchaiya Water Supply and Sanitation Sector Project .............................................. 23

Table 10 : Katari Water Supply and Sanitation Sector Project ................................................................... 27

Table 11 : Sakhuwa-Mahendranagar Water Supply and Sanitation Sector Project .................................... 31

Table 12 : Lalbandi, Sarlahi Water Supply and Sanitation Sector Project ................................................... 35

Table 13 : Katahariya, Rautahat Water Supply and Sanitation Sector Project ........................................... 39

Table 14: Birendranagar, Chitwan Water Supply and Sanitation Sector Project ........................................ 43

Table 15 : Bidur, Nuwakot Water Supply and Sanitation Sector Project .................................................... 47

Table 16 : Detailed Compliance Status with EMP and Monitoring Plans of Abukhaireni Subprojects....... 52

Table 17 : Detailed Compliance Status with EMP and Monitoring Plan of Dumre Subprojects ................. 55

Table 18: Detailed Compliance Status with EMP and Monitoring Plans of Nirmalpokhari Subprojects .... 57

Table 19 : Detailed Compliance Status with EMP and Monitoring Plans of Tamsariya Project ................. 60

Table 20 : Detailed Compliance Status of EMP and Monitoring of Chandrauta Subprojects..................... 62

Table 21 : Detailed Compliance Status with EMP and Monitoring Plans of Rukum Subprojects ............... 65

Table 22 ; Detailed Compliance Status of EMP and Monitoring of Babayachaur Subproject .................... 67

Table 23 ; Detailed Compliance Status of EMP and Monitoring of Suda Kanchanpur Subproject ............. 69

Table 24 : Detailed Compliance with EMP and Monitoring of Amargadi Subproject ................................ 71

Table 25 : Orientation Programs conducted in ERDSMC ............................................................................ 76

Table 26 : Training Programme on Leadership and Utility Management................................................... 77

Page 11: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

vi

Table 27 : School Wash Program conducted in ERDSMC Projects ............................................................. 77

Table 28 : Public Consultation Meeting & Orientations/trainings in Project Towns .................................. 81

Table 29 : Major Issues and Way Forward .................................................................................................. 86

Table 30 : Status on Items of focus of Previous Report .............................................................................. 87

Table 31 : Items of Focus in Next Report .................................................................................................... 91

List of Figures

Figure 1 : Location Map of TSTWSSSP .......................................................................................................... 3

Figure 2 : Institutional Framework for Implementation of Environmental Safeguards ............................. 14

Figure 3: Grievances Redress Mechanism .................................................................................................. 18

List of Pictures

Pic. 1 : Water Quality Monitoring at the Site .............................................................................................. 78

Pic. 2 : Placing Waste Segregation Beans at Tamsariya .............................................................................. 79

Pic. 3 : Waste Bin Placed at Abhukhereni TWSSP ....................................................................................... 79

Pic. 4 : Use of PPEs by Workers Amargadi Town ........................................................................................ 79

Pic. 5 : Consultation Meeting in Chandrauta Subproject ............................................................................ 80

Pic. 6 : Interaction with Local Elites/Groups at Amargadi Dadeldhura on March 2020 ............................. 81

Pic. 7 : Protection Works ............................................................................................................................. 81

Pic. 8 : Washout and River diversion works ................................................................................................ 82

Pic. 9: Plantation of Narkat (Arunod donax) in Sludge Drying Bed at Charali ............................................. 82

Page 12: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

1

1. INTRODUCTION

1.1. Background

1. The Government of Nepal (GoN) has been implementing small town's water supply and sanitation

projects to improve the health and the quality of life of people living in small and emerging towns by

constructing and extending water supply systems, drainage and sanitation facilities and providing health

and hygiene education programs. The Third Small Towns Water Supply and Sanitation Sector Project

(TSTWSSSP) is one of such projects proposed for improving water supply and sanitation facilities to

selected small towns in Nepal. This project has been developed in line with the Government's 15-year

development plan for water supply and sanitation in Small Towns, which was prepared and endorsed by

the Government in 2000 and updated in 2009. GoN initiated the 15-year Plan for Small Towns Water

Supply and Sanitation Development and requested Asian Development Bank (ADB) assistance in preparing

a sector investment project to support the plan1. In response to the government’s request, ADB approved technical assistance (TA)2 to prepare the Small Towns Water Supply and Sanitation Sector Project3. The

targeted outputs anticipated during appraisal were (i) the delivery of community health and hygiene

awareness and education programs, (ii) increased community participation and ownership of town

projects, (iii) water supply and public sanitation facilities constructed4, (iv) enhanced capacity in Water

User and Sanitation Committees (WUSCs) to manage the constructed Water Supply and Sanitation (WSS)

facilities; and (v) the establishment of regional technical support centers. The Asian Development Bank is

helping Nepal provide quality water and sanitation services in small towns. The project is benefiting over

1.2 million people in 69 towns with construction and upgrades of water pipes, treatment facilities and

household connections, as well as septic tanks, drainage and public awareness campaigns. The

Government of Nepal and Asian Development Bank are operational to provide WSS services in 21

TSTWSSPs of the country.

2. The Ministry of Water Supply (MOWS) is an Executing Agency (EA), working through the Department

Water Supply and Sewerage Management (DWSSM), which has established a PMO and two RPMOs

(eastern and western region) for the Project. Asian Development Bank (ADB) supports the TSTWSSP under

Ministry of Water Supply (MWS), Government of Nepal,5 to improve inclusive access to WSS services in

small towns and institutional strengthening and capacity building of local governments, service providers,

and the TDF. The major outcome of the Project are: (i) Improved Water Supply and Sanitation

infrastructure, (ii) Strengthened sector policy, regulatory and institutional capacity and service delivery

and (iii) Improved project implementation. The Ministry of Water Supply is working as an executing agency

of the project and the Project Management Office (PMO) is implementing 21 Water Supply and Sanitation

sub projects under TSTWSSSP engaging at both Eastern and Western Regions Design and Supervision

Management Consultants (DSMCs). Both the DSMCs supports two regional RPMOs of DWSSM in

conducting design, overall implementation management and construction supervision of the town

projects.

3. The subprojects scope towards civil works from design, construction to implementation that cause

impacts/issues and concerns, which can be addressed through adopting existing government legislation of

Nepal, ADB SPS, strategy and guidelines. The expected outputs of the project is to improve water supply

and sanitation infrastructure of concerned municipalities and strengthen institutional and community

1 The 15-year plan, approved by the government on 29 February 2000, has three phases: 2000–2004, 2005–2009, and 2010–2014. 2 ADB approved a loan of SDR26.7 Million ($35 million equivalent) for the Small Towns Water Supply and Sanitation Sector Project on 12 September

2000. 3 ADB. 1998. Technical Assistance to Nepal for Preparing Small Towns Water Supply and Sanitation Sector Project. Manila. 4 The DWSS reduced the number of town subprojects from 40–50 to 33 because of the excessive time required to mobilize communities’ contribution and increase in the number of beneficiaries. 5 The total project cost comprises $ 60 million (38.921 million SDR) from Asian Development Bank, $20 million loan from OPEC Fund for

International Development and $ 1.3 million Sanitation Financing Partnership Trust Fund under the Water Financing Partnership Facility (grant)

which was approved on 19 September 2016 and signed agreement on 15 November 2014 for construction and management of water supply &

sanitation facilities in the growing towns of the country.

Page 13: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

2

capacities. The GoN and ADB policies require to address environmental implications of the individual

development projects to reduce the adverse impacts into acceptable levels that can be taken into account

at the planning and decision-making process. Thus, an environmental assessment process is an integral

part of lending operations and project development and implementation.

4. Environmental assessment conducted for the subprojects based on screening criteria of

Environmental Protection Act (EPA) 2019 and Environmental Protection Regulation (EPR) 20206 and ADB’s Safeguard Policy Statement (SPS) 2009 to ensure the environmental soundness and sustainability of

projects and to support the integration of environmental considerations into the project decision-making

process. The existing environmental legislation and safeguard policies has been considered to meet legal

and procedural requirements for ongoing surface water and ground water-based water supply systems

and sanitation subprojects (including construction of toilets and wastewater treatment/septage

management systems and surface water drainage in some selected towns). To ensure that the projects

are environmentally sound, designed to operate in compliance with applicable regulatory requirements

and not likely to cause significant environmental, health, or safety hazards, ADB’s SPS screening criteria resembles selected subprojects under 'Category B7' where IEE studies are sufficient. Similarly, these

projects requires IEE study as per EPR 1997, Schedule (1-G), Drinking Water Sector. Thus, all selected town

projects has conducted IEE studies and approved from the Ministry of Water Supply (Table 3).

5. As TSTWSSP consists of many individual water supply town projects, storm water drainage projects

and DEWATS projects which will be implemented under ADB Loan 3711-NEP. Among them, Mirchaiya

Town Storm Water Drainage Project of Siraha district has been additionally selected as a potential projects

and updated IEE of 12 enhancement projects has been finalized. The IEE studies of the selected projects

have been conducted to ensure the environmental sustainability of the project, integrate environmental

considerations into the project preparation process, and manage environment during project

implementation.

6. The IEE reports of the subprojects are parts of the contract documents provided to the Contractors,

Regional Design Supervision & Management Consultants (RDSMCs) and the Water Supply and Sanitation

Division and Sub-division Offices. To implement safeguard measures and relevant safeguard plans extent

of monitoring activities, including their scope and periodicity and commensurate with the project’s risks and impacts, RDSMCs has placed Environmental Specialists for environmental monitoring. Based on the

progress of environmental compliance and monitoring8, this report has been prepared during the period

of January to June 2020.

1.2. Status of Town Projects

7. Third Small Towns Water Supply and Sanitation Sector Project (TSTWSSSP) has established Two

Regional Design Supervision and Monitoring Consultancies (RDSMC) to support two Regional Project

Management Offices (RPMOs), one in Eastern Region at Itahari and other in Mid- Western Region

Nepalgunj (Fig. 1). These Offices are implementing sub project supervision & monitoring activities by

conducting design, overall implementation management and construction supervision in their particular

regional' towns. The project has many stakeholders such as the Water User and Sanitation Committees

(WUSC), Project Management Office (PMO), Regional Project Management Office (RPMO), Town

Development Fund (TDF), Implementation Core Group (ICG), Design Supervision and Management

Consultants (DSMC) and Contractor. The status of Two Regional subprojects are given presented in the

Table 3 & 4.

6 The EPR 2020 has included Schedules on list of sector-specific projects that require brief environmental study, IEE or EIA. It has followed the

'threshold, 'sensitive area and 'investment' criteria as the previous EPR (1997) 7 As per ADB’s Safeguard Policy Statement 2009, Category B projects are classified for less potential adverse environmental impacts than those

of category 'A' projects. The likely impacts are site-specific, few if any of them are irreversible, and in most cases mitigation measures can be

designed more readily than for category 'A' projects, which require IEE study. 8 To ensure the environmental soundness and sustainability of projects and support the integration of environmental considerations into the

project decision-making process.

Page 14: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

3

Figure 1 : Location Map of TSTWSSSP

Eastern Regional Design, Supervision and Management Consultant (ERDSMC): The ERDSMC, joint

venture of TAEC Consult Pvt. Ltd and Integrated Consultants Nepal (P.) Ltd. has been assigned to the

existing contract with Department of Water Supply and Sewerage Management (DoWSSM) /GON to

provide services on engineering feasibility study, survey, and detailed design of various Town Projects to

meet the project criteria of the Third Small Towns Water Supply and Sanitation Sector Project. The

ERDSMC also assisting the RPMOs with the overall planning, implementation and monitoring of each

subproject during all stages of implementation including adherence to all environmental and social

safeguards’ requirements. Among 13 projects of ERDSMC, Bidur_Nuwakot, Ramnagar-Mirchaiya storm

drainage project and Beautification of Charali FSMTP are in construction phase. Charali, Jhapa and

Mahendranagar Sunsari sub-project has been completed. Sakhuwa-Mahendranagar, Ramnagar-

Mirchaiya, Birendranagar and Katahariya projects entered into defect liability period (DLP) effective from

June 15, 2019, June 12, 2019, April 13, 2020 and June 30, 2020 respectively. Similarly, Ramnagar-

Mirchaiya yet to be corrected and DLP has been extended up to November 2, 2020 and Katari, FSM project

and Lalbandi entered into 2nd stage Operation and Maintenance (O & M) phase effective form June 20,

2019, July 30, 2019 and Feb. 23, 2020 respectively. The Project summary and progress status of the

ERDSMC projects up to June 2020 are presented in the Table 3.

Western Regional Design, Supervision, and Management Consultant (WRDSMC): the WRDSMC, joint

venture of Building Design Authority Pvt. Ltd. and Plush Engineers and Architects (P) Ltd (BDA-PEA JV) has

been assigned for Feasibility Study, Detailed Design, preparation of Tender Documents and Construction

Supervision with Contract Management. The RDSMCs also assists the RPMOs with the overall planning,

implementation and monitoring of each subproject during all stages of implementation including

adherence to all environmental and social safeguards requirements working together with the WUSCs,

local bodies (LBs) and communities. Among the 11 subprojects of WRDSMC, Khalanga - Sitalpati and

Tikapur subprojects have crossed DLP phase and other 9 projects are in DLP and O & M stages.

Page 15: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

4

Babiyachaur, Chandrauta, Musikot-khalanga and Suda sub-projects have completed O&M phase and

running into DLP. Tansariya, Abukhaireni, Dumre, Nirmalpokhari and Amargadi sub-projects are running

operation and maintenance phase. The project summary and progress status of WRDSMC by June 2020

are presented in the Table 4.

Enhancement Town Projects: Enhancement towns comprises; (1) Waling Town, Syangya (2) Bijuwar Town,

Pyuthan (3) Khalanga Sitalpati Town, Salyan (4) Tikapur Town, Kailali (5) Adarshanagar Bhasi Town,

Kanchanpur (6) Mahendranagar Town, Kanchanpur (7) Baitadinagar Town, Baitadi. (8) Khandbari,

Sankuwasabha (9) Duhabi, Sunsari (10) Belbari, Morang (11) Birtamod Jhapa, and (12) Phidim Panchthar.

The major works of enhancement towns have been started related to construction and rehabilitation of

sump well, reservoir tank, transmission and distribution pipelines, treatment plant- pressure filters, and

other associated works.

1.3. Compliance with Environmental Covenants

8. The TSTWSSSP has been striving to adhere and meet all the Environmental Covenants stipulated

in the Project Documents to increase water supply and sanitation coverage providing better water,

sanitation and wastewater management services to the residents of the growing towns. The

project has met all the compliance requirements of the Government of Nepal and ADB approving

Terms of Reference (ToR) and Initial Environmental Examinations (IEEs)9 of selected 21 Towns from

MoWS fulfilling legal and procedural requirements. Table 1 below represents the status of IEE up

to June 2020.

Table 1: Status of IEE Studies

S.N Project Name District ToR IEE Status Contract

1 Sitalpati Khalanga Salyan Approved Approved Awarded

2 Musikot Rukum Approved Approved Awarded

3 Chandrauta Kapilbastu Approved Approved Awarded

4 Chhap Nahala Dumre Tanahu Approved Approved Awarded

5 Mhendranagar, Sunsari Sunsari Approved Approved Awarded

6 Sakhuwa, Mahendranagar Danusa Approved Approved Awarded

7 Ramnagar Mirchaiya Siraha Approved Approved Awarded

8 Charali Jhapa Approved Approved Awarded

9 Tikapur Kailali Approved Approved Awarded

10 Bidur Nuwakot Approved Approved Awarded

11 Tamsariya Nabalparasi Approved Approved Awarded

12 Abukhairini Tanhu Approved Approved Awarded

13 Birenndranagar Citawan Approved Approved Awarded

14 Suda Kanchapur Approved Approved Awarded

15 Nirmal-pokhari Kaski Approved Approved Awarded

16 Babiyachour Surkhet Approved Approved Awarded

17 Katari Udayapur Approved Approved Awarded

18 Lalbandi Sarlahi Approved Approved Awarded

19 Kathariya Ratahat Approved Approved Awarded

20 Amargadhi Dadeldhura Approved Approved Awarded

21 Ramnagar Mirchaiya Storm

Drainage Project

Siraha Approved Approved Awarded

9 As per the ADB's Safeguard Policy Statement (SPS) 2009 and then EPR 1997, selected 21 subprojects screened under Category

B project for the study of Initial Environmental Examination (IEE).

Page 16: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

5

9. In addition, of updated IEE study of 12 enhancement town projects has been prepared. The

principle exists of safeguard policies for implementation of the provisions with the responsibility

of the borrower/client require to undertake social and environmental assessments, carry out

consultations with affected people and communities, prepare and implement safeguard plans,

monitor the implementation of these plans, and prepare and submit monitoring reports. Table 2

summarizes the status of the major project covenants and their compliances.

10. The progress status of safeguard of the subproject during planning and implementation stages is

outlined below in the Table 5 and 6, considering safeguard policy objectives to avoid adverse

impacts of projects on the environment and affected people, minimize, mitigate, and/or

compensate for adverse project impacts on the environment and affected people when avoidance

is not possible and help borrowers/clients to strengthen their safeguard systems and develop the

capacity to manage environmental and social risks.

Page 17: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

6

Table 2: Grant Covenants and Status of Compliance

SN Environmental Covenants (with reference to

Loan Agreements)

Responsibility Period/

Deadline

Current

Status

1. LA, Schedule 5, para. 3:

The Borrower shall ensure that the preparation, design,

construction, implementation, operation,

maintenance and decommissioning of each Sub-

project and all Project facilities comply with (a) all

applicable laws and regulations of the Borrower

relating to environment, health and safety; (b) the

Environmental Safeguards; (c) the EARF; and (d) all

measures and requirements set forth in the respective

IEE or EIA, EMP, and any corrective or preventative

actions set forth in a Safeguards Monitoring Report

Govt/EA

Before contract

is over during

implementation

IEE report of

the project

including the

EMP has been

approved by

GoN and ADB

Being

complied

with

2 LA, Schedule 5, para. 9:

The Borrower shall ensure that all bidding documents

and contracts for Works contain provisions that

require contractors to:

(a) comply with the measures relevant to the

contractor set forth in the IEE or EIA, the EMP,

(to the extent they concern impacts on affected

people during construction), and any corrective

or preventative actions set forth in a Safeguards

Monitoring Report;

(b) make available a budget for all such environmental

and social measures;

(c) provide the Borrower with a written notice of any

unanticipated environmental, resettlement or

indigenous peoples risks or impacts that arise

during construction, implementation or operation

of the Project that were not considered in the IEE

or EIA, the EMP, the RP or the IPP;

(d) adequately record the condition of roads,

agricultural land and other infrastructure prior to

starting to transport materials and construction;

and

(e) fully reinstate pathways, other local

infrastructure, and agricultural land to at least

their pre-project condition upon the completion of

construction

Govt/EA

During

implementation

During design

During

implementation

(c, d and e) and

before end of

construction)

Being complied

with

3 LA, Schedule 5, para. 10:

The Borrower shall do the following:

(a) submit semiannual Safeguards Monitoring

Reports to ADB and disclose relevant information

from such reports to affected persons promptly

upon submission;

(b) if any unanticipated environmental and/or social

risks and impacts arise during construction,

implementation or operation of the Project that

were not considered in the IEE or EIA, the EMP,

promptly inform ADB of the occurrence of such

risks or impacts, with detailed description of the

event and proposed corrective action plan; and

(c) report any actual or potential breach of

compliance with the measures and requirements

set forth in the EMP, promptly after becoming

aware of the breach.

Govt/EA

Govt/EA

Govt/EA

Every six

months after

field monitoring

As such cases

arise during

implementation

As such cases

arise during

implementation

Unanticipated

risks or

impacts have

not yet

occurred

Page 18: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

7

Table 3 : Summary of Projects and Status of ERDSMC

Name of the

Sub-Project

1. Bidur

Nuwakot

TSTWSSSP

2. Birendranagar

, Chitwan

TSTWSSSP

3. Charali

Jhapa

TSTWSSSP

4. Mhandranage

r Sunsari

TSTWSSSSP

5. Ramnagar-

Mirchaiya,

Siraha TSTWSSSP

6. Sakhuwa_

Mahendranagar_

Dhanusha TSTWSSSP

7. Katari_Udaypur

TSTWSSSP

8. Lalbandi_

Sarlahi

TSTWSSSP

9.

Kakarvitta

Town FSMP

10.

Charali

Town

FSMP

11.

Katahariya_

Rautahat

TSTWSSSP

12.

Ramnagar

Mirchaiya

SD, Siraha

Name of the

Contractor

M/S CICO-

KALIKA-

TUNDI JV

M/S Tundi-

Chandra &

Basant JV,

Tianjin-Kankai

JV

M/s Kankai

International

Builders Pvt.

Ltd.

M/S Kalika-

Raman-Kankai JV

M/S Raman Construction

(Pvt.)

M/S Kalika-

Raman-Sharma

JV

M/S Huashui-

Kankai JV

M/S Raman

Construction (Pvt.)

Ltd.

M/S Raman-

Ashish JV

M/s BKOI-

YOGI JV

Date of

Contract

Agreement

27th May

2016

11th Sept. 2016 June 08, 2015 6th July 2015 10th December

2015

8th June 2015 16th January

2017

2nd March

2017

26th November 2017 30th

November

2017

31st

December

2019

Commencemen

t Date

13th June

2016

22nd Sept.

2016

Completion

Dec. 14, 2016

Completion

12th Jan. 2017

13th December

2015

15th June 2015 17th January

2017

6th March

2017

30th November 2017 4th December

2017

1st January

2020

Completion

Date

Stage 1 :

11th June

2018 (total

730 days)

Stage 1 : 21st

March 2018

(total 548 days)

Commenceme

nt O& M June

21, 2017

Stage I: 8th Dec

2017

Stage 1 : 12th June

2017 (total 548

days)

Stage 1 : 14th December

2016 (total 548 days)

Stage 1 : 18th

July 2018 (total

548 days)

Stage 1 : 5th

March 2019

(total 730

days)

Stage 1 : 31st August

2018 (9 months)

Stage 1 : 4th

March 2019

(total 456

days)

NA

Stage 1 :

Revised

Completion

Date is May

7, 2020

Stage 1 :

Revised

Completion

Date is April 15,

2019

June 22, 2019

with DLP

Stage II: 8th

Dec 2017

Stage II (O &

M): up to 8th

Dec 2018

Stage 1 : Revised

Completion Date

is June 12, 2018

Stage 1 : Revised

Completion Date is June

15, 2018

Stage 1 : Revised

Intended

Completion Date

is May 14, 2019

Stage 1 :

Revised

Intended

Completion

Date is Sept.

16, 2019

Stage 1 : Revised

Intended Completion

Date is July 30, 2019

Stage 1 :

Revised

Intended

Completion

Date is June

30, 2019

Intended

Completion

Date is

December

31, 2020

Stage 2 :

May 7, 2021

Stage 2 : April

15, 2020

Stage 2: up to

June 22, 2018

Stage 2 : June 12,

2019 Stage 2 : June 15, 2019

Stage 2 : May

14, 2020

Stage 2 :

Sept. 16, 2020

Stage 2 : July 30,

2021

Stage 2 : June

30, 2020

Original

Contract

Amount with

VAT

NRs.810,820,

155.59

NRs.260,949,13

7.35

202.10 Million 216.58 Million NRs.486,848,922.

02

NRs.124,013,705.56 NRs.445,471,686

.04

NRs.689,590,0

71.17

NRs.127,744,061.76 NRs.141,853,7

36.40

NRs.363,361,

571.69

Revised Contract

Amount with VAT

NRs.859,204,

656.68

NRs.280,621,45

4.80

217.71 Million

(+ 7.72)

238.15 Million

(+ 9.81)

NRs.529,783,032.

20

NRs.129,239,148.26 NRs.445,471,686

.04

NRs.758,057,3

49.18

NRs.146,858,129.58 NRs.141,853,7

36.40

NRs.363,361,

571.69

PROGRESS SUMMARY – UP TO JUNE 2020

Physical

Progress

98.33% Entered in DLP

effective from

April 13, 2020

DLP

Completed

August 2019

Completed effective from

Dec. 8, 2019

Hand over to

WUSC

Entered in DLP

effective from

June 12, 2019 and

it has been

extended up to

Nov. 2, 2020

Entered in DLP effective

from June 15, 2019

Entered in O &

M Phase

effective from

June 20, 2019

and extended up

to Sep. 5, 2020

Entered in O

& M Phase

effective from

February 23,

2020

Entered in O & M

Phase effective from

July 30, 2019

Entered in O

& M Phase

effective from

June 30, 2019

0.00%

Physical Target

as per latest

Revision

100.00%

50.00%

Financial

Progress 92.85%

9.74%

Source: Progress reports of Subprojects (ERDSMC, June 2020)

Page 19: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

8

Table 4 : Summary of Project and Status of WRDSMC

Name of the

Project

1. Chandrauta

Kapilvastu

2. Musikot-

Khalanga

Rukum

5.Chhap

Nahala,

Dumre

Tanahun

3. Nirmalpo

khariKaski

4. Abukhaireni

Tanahun

5. Tamsariya

Nawalparasi

6. Babiyachaur

Surkhet

7. Suda

Kanchanpur

8. Amargadhi

Dadeldhura

Contractor M/s Chandra

& Basanta-

Nepal Adarsha

JV

Kankai

Internationa

l Builders

Pvt. Ltd,

Jhapa

M/s Prera

Nirman

Sewa Pvt.

Ltd

M/s Tundi –

Kankai - Mrit

Sanjiwoni

Joint

Venture

M/s Raman-

Gorkha-Prera

JV

M/s KALIKA –

SHARMA –

RAMAN JV

M/S Chandra &

Basant-Prera-JV

Kalika-Chandra

& Basant JV

M/s Kalika

Construction Pvt.

Ltd.

Commencem

ent Date

15 June 2015 15 June

2015

7 June 2015 8 Nov 2016 5 October 2016 20 Sept. 2016 15 June 2015 16 March 2017 31 Dec. 2017

Completion

Date as per

Contract

7 January

2017

August 12,

2016

8 Dec 2016 8 May 2018 19 April 2018 19 March,

2018

16 August 2018 15 April 2019 2 July2019

Actual Date

of

Completion

of Stage I

Works

3 November

2018

December 1,

2016

6 June 2019 15 May

2019

30 June 2019 29 July 2019 16August 2018 26 May 2019 12 May 2020

Date of

Commencem

ent of Stage II

Works

4 November

2018

January 31,

2017

7 June 2019 16 May

2019

12 July 2019 26 August

2019

17 August 2018 26 May 2019 9 June 2020

Intended

completion

period of O &

M (Stage II)

12 months

from the date

of

commenceme

nt of O & M

(up to 4

November

2019)

12 months

from the

date of

commence

ment of O &

M ( up to 7

April, 2020)

12 months

from the

date of

commence

ment of O &

M (up to 6

June 2020)

12 months

from the

date of

commence

ment of O &

M

12 months from

the date of

commencemen

t of O & M ( up

to 12 July 2020)

14 April 2021 12 months from

the date of

commencement

of O & M

26 May 2019 12 months from

the date of

commencement

of

O & M (up to 10

June 2021)

Progress

Status

DLP Period DLP Period

Stage II

Completed

on 4 Nov.

2019

Operation

and

maintenanc

e Phase

Operation and

maintenance

Phase

Operation and

maintenance

Phase

DLP Period DLP Period O & M Phase

from 13th May

2020

Source: Quarterly Progress report of WRDSMC June 2020

Page 20: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

9

Table 5 : Status of Environmental Safeguards during Planning Stage (June, 2020)

S.

No.

Name of Project or

Subproject

Environment

al screening

is carried

out? (Yes or

No)

Environment

category of

the project /

subproject

(A/B/C/FI)

EARF is

prepared (if

applicable)

(Yes/No)

EIA/IEE/D

DR with

EMP is

prepared

(Yes/No)

ADB approved

EIA/IEE with EMP

(Yes / Under Review

/ Not Yet Due /

Over Due)

Government

approved

EIA/IEE with

EMP (Yes / UR )

Safeguard

monitoring and

coordination

mechanism

established

(Yes/No)

GRC is

establis

hed

(Yes/No

)

Automated

safeguard

monitoring

system

customized

(Yes/No)

EMP cost in

approved

document is

included in BOQ

as an individual

item (Yes/No)

Re

mar

ks

1 Charali Y B Y Y Y

Approved

Y Y N Y

2 Mahendranagar Y B Y Y Y Y Y N Y

3 Ramnagar

Mirchaya Y B Y Y Y Y Y N Y

4 Sakhuwa

Mahendranagar Y B Y Y Y Y Y N Y

5 Chhapnahala

Dumre Y B Y Y Y Y Y N Y

6 Bidur Y B Y Y Y Y Y N Y

7 Abhukhaireni Y B Y Y Y Y Y N Y

8 Birendranagar Y B Y Y Y Y Y N Y

9 Tamasariya Y B Y Y Y Y Y N Y

10 Nirmal Pokhari Y B Y Y Y Y Y N Y

11 Musikot Y B Y Y Y Y Y N Y

12 Khalanga Sitalpati Y B Y Y Y Y Y N Y

13 Chandrauta Y B Y Y Y Y Y N Y

14 Tikapur Y B Y Y Y Y Y N Y

15 Suda Y B Y Y Y Y Y N Y

16 Babiyachaur Y B Y Y Y Y Y N Y

17 Katari Y B Y Y Y Y Y N Y

18 Lalbandi Y B Y Y Y Y Y N Y

19 Katahariya Y B Y Y Y Y Y N Y

20 Amargadi Y B Y Y Y Y Y N Y

21 Mirchaya Strom

Drainage Y B Y Y Y Y Y N Y

Note: EIA- Environmental Impact Assessment; IEE- Initial Environmental Examination; DDR- Due Diligence Report; EMP- Environmental Management Plan; GRC- Grievance Redress Committee;

BOQ- Bill of Quantity, Y = Yes, N = No, UR = Under Review, IP = In Progress

Page 21: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

10

S.

No

.

Name of Project or

Subproject

Environme

ntal

screening

is carried

out? (Yes

or No)

Environme

nt category

of the

project /

subproject

(A/B/C/FI)

EARF is prepared

(if applicable)

(Yes/No)

EIA/IEE/DD

R with EMP

is prepared

(Yes/No)

ADB

approved

EIA/IEE

with EMP

(Yes / Under

Review /

Not Yet Due

/ Over Due)

Govt.

approved

EIA/IEE with

EMP (Yes )

Safeguard

monitoring and

coordination

mechanism

established

(Yes/No)

GRC is

establis

hed

(Yes/No

)

Automated

safeguard

monitoring

system

customized

(Yes/No)

EMP cost in

approved

document is

included in BOQ

as an individual

item (Yes/No)

Remarks

FSM Projects

22 Kakarvitta & Charali

FSM Project Y B Y Y Y Y Y N Y N

Enhancement Towns

1

WalingTown,

Syangya Y B Y Y Y

Approved

N N N N

Wo

rk S

tart

ed

2

Bijuwar Town,

Pyuthan Y B Y Y Y

N N N N

3

Khalanga Sitalpati

Town, Y B Y Y Y

N N N N

4 Tikapur Town, Kailali Y B Y Y Y N N N N

5

Adarshanagar,

Kanchanpur Y B Y Y Y

N N N N

6 Mahendranagar

Town, Kanchanpur Y B Y Y Y

N N N N

7 Baitadinagar Town,

Baitadi Y B Y Y Y

N N N N

8 Phidim Town,

Panchthar Y B Y Y Y

N N N N

9 Birtamod Town,

Jhapa Y B Y Y Y

N N N N

10 Belbari Town,

Morang Y B Y Y Y

N N N N

11 Duhabi Town, Sunsari Y B Y Y Y N N N N

12 Khandbari Town,

Sankuwasabha Y B Y Y Y

N N N N

Page 22: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

11

Table 6 : Status of Environmental Safeguards during Planning Stage (January- June 2020)

S.

No.

Name of

Subproject

Compliance to Environmental Management Plan* Grievances

Physical Biological Socio-economic Corrective

Action Plans

are prepared

and

implemented

Env.

Compliance

reporting is

maintained

(Y/N)

Remarks

Spoil

Managem

ent

complianc

e in %)**

Landslide

protection

with Bio-

engg

(complianc

e)

Drainage

Manageme

nt

(complianc

e in %)**

Others as

per EMP

(specify)

EM Work

% of

Physical

Progress

till date

Compensat

ory

Plantation Firewoo

d is used

for

cooking

and

heating

Other

s as

per

EMP

(speci

fy)

Occupational Health and Safety

Community structures are

compensated / reconstructed

(progress in % of total

estimated work) Others

as per

EMP

(specify

)

Nos of

grievances

documente

d10

No of

Grievance

s resolv Un

solv

ed

Tar

get

(No

s.)

Repl

ante

d

(Nos

.)

Safety

Gears

are

sufficient

and used

(Y/N)

Labours

are

insured

(Y/N)

Labour and

work camps

are healthy

and have

sanitary

facilities

(Y/N)

Community

Structure 1

Community

Structure 2

1 Charali Y NA Y 100

No

lo

ss o

f tr

ee

s d

uri

ng

re

po

rtin

g p

eri

od

NA NA Y Y Y NA NA NA Y

2 Mahendranagar Y NA Y 100 NA NA Y Y Y NA NA NA Y Y

3 Ramnagar

Mirchaya Y NA Y 100 NA NA Y Y Y NA NA 1 1 0

Y Y

4 Sakhuwa

Mahendranagar Y NA Y 100 NA NA Y Y Y NA NA 1 1

Y Y

5 Birendranagar Y NA Y 100 NA NA Y Y Y NA NA NA Y

6 Bidur Y NA Y 98.33 NA NA Y Y Y NA NA NA Y

7 Katari Y NA Y 100 NA NA Y Y Y NA NA NA Y

8 Lalbandi Y NA Y 100 NA NA Y Y Y NA NA NA Y

9 Katahariya Y NA Y 100 NA NA Y Y Y NA NA NA Y

10 Mirchaya Stro

Draingae y NA y 0.00 NA NA Y y y NA NA 1 1 0

Y

11 Tamsariya Y Y Y 70 Y NA Y Y Y NA NA 3 3 0 Y

12 Anbhukhaireni Y Y Y 100 NA NA Y Y Y NA NA 0 0 0 Y

13 Nirmal Pokhari Y NA Y 75 NA LPG Y Y Y NA NA 3 3 0 Y

14 Chhapnala

Dumre Y NA Y 97.15 NA NA Y Y Y NA NA 0 0 0

Y

15 Musikot Y Y Y 100 NA NA Y Y Y NA NA 2 1 1 Y

16 Khalanga

Sitalpati Y NA Y 100 NA NA Y Y Y NA NA 0 0 0

Y

17 Chandrauta Y NA Y 81.5 NA NA Y Y Y NA NA 4 4 0 Y

18 Tikapur Y NA Y 100 NA Y Y Y Y NA NA 0 0 0 Y

19 Babiyachaur Y NA Y 81.5 Y NA Y Y Y NA NA 0 0 0 Y

20 Suda Y NA Y 75 NA Y Y Y Y NA NA 0 0 0 Y

21 Amargadi Y Y Y 75 NA NA Y Y Y NA NA 0 0 0 Y

22 Beautification

of Charali FSM Y NA Y 75 NA Y Y Y Y NA NA 0 0 0

NA

Page 23: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

12

S.

No

.

Name of

Subproject

Compliance to Environmental Management Plan* Grievances

Physical Biological Socio-economic

Spoil

Managem

ent

complianc

e in %)**

Landslide

protection

with Bio-

engg

(compliance

)

Drainage

Manageme

nt

(compliance

in %)**

Others as

per EMP

(specify)

EM Work

% of

Physical

Progress

till date

Compensatory

Plantation Firewood is

used for

cooking and

heating

Others

as per

EMP

(specify)

Occupational

Health and

Safety

Community structures are compensated / reconstructed

(progress in % of total estimated work)***

Others as

per EMP

(specify)

Nos of

grievances

documented1

No of

Grievance

s resolved un

solv

ed

Target

(Nos.)

Replan

ted

(Nos.)

Safety Gears

are sufficient

and used

(Y/N)

Labours

are

insured

(Y/N)

Labour and

work camps

are healthy and

have sanitary

facilities (Y/N)

Community

Structure 1

Community

Structure 2

Enhancement Towns

1

WalingTown,

Syangya NA NA NA NA NA NA NA

NA NA NA NA NA NA

2

Bijuwar Town,

Pyuthan NA NA NA NA NA NA NA

NA NA NA NA NA NA

3

Khalanga

Sitalpati Town, NA NA NA NA NA NA NA

NA NA NA NA NA NA

4

Tikapur Town,

Kailali NA NA NA NA NA NA NA

NA NA NA NA NA NA

5

Adarshanagar,

Kanchanpur NA NA NA NA NA NA NA

NA NA NA NA NA NA

6

Mahendranagar

Town,

Kanchanpur

NA NA NA NA NA NA NA

NA NA NA NA NA NA

7 Baitadinagar

Town, Baitadi NA NA NA NA NA NA NA

NA NA NA NA NA NA

8 Phidim Town,

Panchthar NA NA NA NA NA NA NA

NA NA NA NA NA NA

9 Birtamod Town,

Jhapa NA NA NA NA NA NA NA

NA NA NA NA NA NA

10 Belbari Town,

Morang NA NA NA NA NA NA NA

NA NA NA NA NA NA

11 Duhabi Town,

Sunsari NA NA NA NA NA NA NA

NA NA NA NA NA NA

12

Khandbari

Town,

Sankuwasabha

NA NA NA NA NA NA NA

NA NA NA NA NA NA

10 Number of Grievances updated as per latest progress report of Town Projects.

Page 24: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

13 | P a g e

1.4. Institutional Arrangement and Responsibilities for Implementation of Environmental Safeguards

10. The baseline scenario of physical, biological, socioeconomic, and cultural environment of the town

projects delivers an understanding of baseline scenario identifying, predicting, and evaluating likely

project impacts and propose mitigation measures forming the benchmark against the subproject

impacts. The approved IEE reports has detailed analysis of anticipated environmental impacts of

the project cycle during design and planning stage, construction, operations, decommissioning, and

post-closure activities. Considering the anticipated impacts and proposed mitigation measures, a

comprehensive environmental management and monitoring plan has been prepared. Based on the

approved IEEs, monitoring of the Town projects has been conducting as per framework of EMP a

part of bidding document.

11. The Ministry of Water Supply (MoWS) is an executing agency with the responsibility of project

execution delegated to the Department of Water Supply and Sewerage Management (DWSSM).

The Project Management Office (PMO) of Third Small Towns Water Supply & Sanitation Sector

Project (TSTWSSSP) is the implementing agency. The Water User’s and Sanitation Committees of participating towns are the implementing agencies. The DWSSM review the IEE ToR and IEE Report

prepared by the Design, Supervision, and Management Consultant Team prior to forwarding this

to MoWS through final reviewing through PMO and Environmental Safeguard Officer of Design

Review and Technical Audit Consultants (DRTAC).

12. The overall responsibilities of PMO for project planning, management, implementation, monitoring

and reporting of the selected project considering screening, the proposed subprojects from the

towns in accordance with the approved subproject selection criteria, PMO have engaged two DSM

Consultants under the project for the project design & supervision. The PMO time to time instructs

two regional DSMCs to conduct feasibility and detailed studies of the town projects and

disseminates the findings to concerning WUAs or local bodies to sign the management agreement

prior to the award of contract in each town. The DRTAC is working at the PMO office for project

management and monitoring consultants, providing support to the PMO and RPMOs with the main

aim of ensuring that the quality of the designs and construction of all water supply and sanitation

components implemented ensuring finest quality of required standards.

13. Regional Project Management Offices (Eastern and Western RPMOs): The regional DWSS

engineers, environment and social development officers of the RPMOs will receive support from;

(i) the PMO safeguards officers (environmental and social); and (ii) the safeguards specialists

(environmental and social), the social mobilizers and design, supervision and management

consultant (DSMC) teams as specified below:

• Prepare IEEs/EMPs in accordance with the EARF and government rules;

• Include EMPs in bidding documents and civil works contracts;

• Comply with all government rule and regulations;

• Take necessary action for obtaining rights of way;

• Oversee implementation of EMPs including environmental monitoring by contractors;

• Take corrective actions when necessary to ensure no environmental impacts;

• Submit monthly environmental monitoring reports to PMO, and;

• Address any grievances brought about through the Grievance Redress Mechanism in a timely

manner as per the IEEs.

14. Water Users and Sanitation Committees (WUSCs): WUSCs are facilitating EMP implementation with

water safety plan, water quality monitoring, public consultation, and participation, capacity

building activities-awareness raising, / training etc. The Institutional arrangement for the project

implementation presented below in the Figure 2.

Page 25: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

14 | P a g e

ADB = Asian Development Bank, EHS = Environmental, Health and Safety

PMO – project management office

RDSMC = regional design, supervision and management consultant

RPMO = regional project management office

WUSC = Water Users and Sanitation Committee

Third Small Towns Water Supply and Sanitation Sector Project

(TSTWSSSP)

Project Management Office

(PMO)

Ministry Of Water Supply Executive Agency

ADB

DRTAC

Environmentalist

Western RDSMC

Environment Specialist

Western RPMO Eastern RPMO

EMP Monitor

Eastern RDSMC

Environment Specialist

EMP Monitor WUSC or

Municipalities

Contractor

(EHS Supervisors)

Contractor

(EHS Supervisors)

WUSC or

Municipalities

Legend:

Coordinator

Supervision

Reporting

Environmental Officer

(Focal Person)

Department of Water Supply and Sewerage Management

(DWSSM)

Figure 2 : Institutional Framework for Implementation of Environmental Safeguards

Page 26: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

15 | P a g e

2. APPROACH AND METHODOLOGY FOR ENVIRONMENTAL MONITORING

15. The present Semi-Annual Environmental Monitoring Report covers progress of environmental

monitoring and safeguard implementation activities of the subprojects from January to June 2020.

The approach, methodology, and procedure have followed in according with EMP framework of

approved IEE reports, SPS 2009, EARF, environmental legislations, and monitoring guidelines. It

considers methodology suggested in the approved ToR, IEE Study (review of literature, sample

survey, site inspections/observations making simple measurements, discussion with communities

and other stakeholders, and expert’s team judgment), safeguard policy, EARF, and guidelines.

Following approach and methods considered during preparation of this Bi-annual Environmental

Monitoring report.

2.1. Desk Study/Literature Review

16. The detailed design report, feasibility study, IEE reports, Progress reports, EARF and Relevant

documents11 i.e. ADB SPS 2009, GON Act and Regulations12 -MOWS, DWSSM has reviewed. Relevant

policies and legal instruments, guideline and standards denoted. Matrix, Checklists, and

questionnaires was prepared to collect primary information’s in direct and indirect impact area of

the project. Similarly, formats for environmental monitoring prepared to cover status of the EMP

and monitoring methods adopted during project implementation stages. Specifically, desk review

includes the following activities:

• Review of the project related environmental monitoring documents and reports, including

the IEE, EMP, monthly, Quarterly and Semi-Annual Environment reports, Grievance

Registers, Measurements and Test Reports, DDR, Reports on conducted trainings for staff

and workers and community meetings; central level meetings/presentation- status and

progress of Town projects and site inspection reports of the consultants;

• Reporting and correspondences between the PMO/DWSSM, DSC Consultant, DSMCs,

Environmental Specialists of RPMOs and the Contractor on environmental compliance

issues;

• Analysis of information as per inspections/observations from the site visits, including camp

sites, local communities, observations of sources and structures and transmission lines and

other worksites;

• Meetings with the staff of the PMO, DRTAC Consultants, MOWS and the RPMOs as well as

discussions with the construction workers during the site visits; and

• Design of environmental compliance issued by photos taken during the site visits and final

audit.

2.1.1. Collection and review of secondary sources

17. Documents related to project site such as monthly progress reports submitted by DSMC, contractor

records, DSMCs technical documents, relevant information’s from WUSC, DSMC, Contractor, DWSS, and PMO were collected and reviewed.

2.1.2. Meeting, Interaction, and Review of Progress Activities

18. Regular meeting, interaction, consultative meeting, and progress review were conducted in

MoWS/PMO/RPMO/DSMCs and subproject sites for effective implementation of EMPs. As per the

activities and mitigation measures proposed in the EMP under approved IEE, environmental

monitoring activities conducted at the subproject level monitored and documented. Field level

support and facilitation for community mobilization and technical aspects documented as per report

submitted by DSMCS and Environmental Monitors. Similarly, support and facilitation to WUSC and

5 Small Towns Water Supply and Sanitation Sector Project (2000); Second Small Towns Water Supply and Sanitation Sector Project (2009); and Third Small

Towns Water Supply and Sanitation Sector Project (2014), and Urban Water Supply and Sanitation Policy 2009 12 Local Governance Operation Act, 2017-established municipalities as autonomous government institution with responsibility for WSS services, Water

Resource Act, 1992, Environment Protection Act (EPA) 1997 and Environment Protection Rules (EPR) 1997, as amended in 1999 and 2007

Page 27: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

16 | P a g e

relevant stakeholders of subprojects during implementation of environmental safeguard activities

were compiled to verify monitoring indications and activities.

2.2. Field Work

19. To collect primary data and understand implementation status of EMP of the Town projects,

detailed field investigation carried out from January to June 2020. However, lockdown disturbed

implementation activities of the project from 4th week of March 2020 due to COVID-19. Field visits

includes joint observation and inspections, supervision to DSMC field team with coordination of User

Committees and RMPO/ICG. The major components monitored during the period are:

➢ EMP Effectiveness

- Instrumental monitoring of air quality, water quality and noise level

- Non-Compliance Notices and Corrective Actions

- Training and Awareness Programs

- Grievances Redress Mechanism

- Plantation and uprooting activities

➢ Visual Monitoring during overall construction period

- Waste management (including storage and disposal)

- Health and safety management

- Storage, utilization and disposal of hazardous materials

- Traffic management (dust protection measures, weight; haulage, washing etc.)

- Water flow management

- Overall visual inspection of water and soil pollution due to the leakages

- Maintenance of equipment and machinery

20. During the field study, EMP of the projects were discussed with DSMC Environmentalists,

Environmental Monitors, and Contractors. The compliance monitoring of the environmental

monitors applying environmental monitoring checklists used for evaluating mitigation measures,

and implementation status of safeguards have conducted the projects. Similarly, Contractor and

DSMC are monitoring the works in the sub-projects and sending the monitoring and monthly

progress reports to the PMO. Topographical map and project design & drawings used to identify the

physical and environmental structures of the project and photographs taken to show the

implementation status of the EMP in the project area. The compilation of environmental monitoring

report submitted by monitors and records of Grievance Redress are included under Chapter 4.

21. Thus, monitoring of the construction activities in relation to EMP works and compliance of the

requirements of the EMP provisions carried out. Field level more information collected from the

team of DSMC and Environmental Specialist whose monitor project activities regularly in

coordination with the WUSC members. Monitoring reporting related to Air quality, noise levels,

water quality, solid waste management and occupational health & safety issues recorded. Field level

measurement, observation and inspections complying with environmental safeguards sought out

for effectiveness of EMP implementation and site-specific management plans.

2.2.1. Interaction and consultation with the local community

22. During the field visits, meetings were organized and discussion conducted regarding the work

progress, present status of project, EMP implementation and monitoring activities and GRM

registers with WUSC members, Consultants field level team members, and Contractor’s representatives (Pic.1). The regular interaction and discussion conducted by the environmental

team of DSMC/RMPOs with the concerned stakeholders at project site reported to understand

implementation status of environmental measures including potential challenges and existing

issues. The local people of the project impact areas interviewed regarding the impacts avoided,

corrected or compensated. Grievance Redress Committees formed at the site and registered public

Page 28: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

17 | P a g e

complaints also recorded. Regarding the use of forest products, health and safety issues, campsite

management and facility and other issues related to labors/workers (Unskilled, Semiskilled and

Skilled) were interviewed.

23. Similarly, consultation and interaction with relevant stakeholders, NGO/CBOs, DSMC, WUSC

members, contractors and different stakeholders carried out to understand project environment,

major issue and problems exists, compliance of mitigated and non-mitigated mitigation measures,

monitoring of project activities from responsible agencies to make effective implementation of EMP.

2.3. GRM and Composition of GRC

24. Grievance Redress Mechanism (GRM) has recorded in all subprojects to receive, evaluate, and

facilitate the resolution of affected people's concerns, complaints, and grievances about the social

and environmental performance of the project. This meant for persons seeking a satisfactory

resolution to their complaints about the social and environmental performance of the subprojects

under the TSTWSSP. The mechanism, developed in consultation with key stakeholders, will ensure

that: (i) the basic rights and interests of every person adversely affected by the social and

environmental performance of a Subproject are protected; and (ii) their concerns are effectively and

timely addressed.

2.3.1. GRM Steps and Time Frame

25. Informal Approach: Informally, APs can lodge complaints directly to the Contractor during

construction or Operator (WUSC) during operation. The contractor/operator will document and

screen the complaint immediately. If a screening reveals that the complaint as Project-related and

valid, the Contractor/Operator will act on the complaint within three days from receipt of the

complaint. Otherwise, the Contractor/Operator will direct the AP with a non-Project-related and

invalid complaint to the ICG. The Contractor/Operator will secure a confirmation of completion of

the action from the AP. For at least a week after confirmation of completion, the ICG will monitor

the effectiveness of the action/resolution taken. After which, ICG will secure a written confirmation

of satisfaction from the AP. The Contractor/Operator shall report to the ICG all complaints received,

eligible or ineligible, actions agreed on and taken and confirmation of completed action.

26. Formal Approach: If a complaint is eligible but is not acted on within three days from the receipt of

the complaint, or if AP is not satisfied with the resolution undertaken by the Contractor/Operator,

he/she can access the formal mechanism, as follows:

First Level: The access point will be the ICG. The steps are detailed below:

Step 1 - Lodging a Complaint (Day 1): AP lodges complaint with the ICG, verbally or in writing. ICG

documents/registers lodged a complaint, makes sure these are duly referenced and provides AP

with a copy of the referenced complaint.

Step 2 - Screening of Complaint (Day 1): ESA screens the complaint if it is Project-related and valid

and informs the AP immediately of the screening results. An AP with complaint screened as non-

Project-related and invalid will be advised that he/she may raise a complaint to the second level of

the GRM, and ICG will forward the complaint to the GRC.

Step 3 - Investigations, Discussion, and the Agreement (Day 1): ICG, together with the

Contractor/Operator and AP, will investigate and discuss the complaint at the site. Agreement on

actions and measures and time involved will be made with the AP. The agreement will be properly

documented and filed; ICG, AP, the contractor/operator will have copies.

Step 4 - Implementing the Agreed Action: If the required action is minor, i.e. not requiring further

investigation and would be quick and easy to implement, the Contractor/Operator will immediately

implement the agreed action. (Day 2/Day 3). If required action is major, i.e. requiring further

investigation and/or procurement of supplies/parts, the Contractor/Operator will: (i) immediately

provide the most suitable interim measure to reduce the magnitude of the impact (Day 2/Day 3);

Page 29: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

18 | P a g e

and (ii) start work on the major action within 5 days from the discussion (or not later than Day 8

since receipt of the complaint) and; The ICG will advise AP that his/her complaint may be raised to

the second level of the GRM, if he/she so prefers when: (i) minor action is not implemented within

2 days of discussion; (ii) interim measure prior to major action is not implemented within 2 days of

discussion; or (iii) major action is not started within 5 days of discussion.

Step 5 - Confirmation of Completed Action: Contractor/Operator will secure a written confirmation

of completed action from the AP and furnish the ICG a copy.

Step 6 - Confirmation of Satisfaction (1 week after confirmation of completed action): The ICG will

monitor the effectiveness of the resolution for at least a week after receipt of confirmation of

completed action from the Contractor/Operator. After which, ICG will secure a written

confirmation of satisfaction from the AP.

Second Level: The AP will be notified by the ICG when a complaint is forwarded to the GRC. The

GRC will call for a hearing, if necessary, where AP can present his or her concerns or issues. The

GRC will suggest corrective action/measure at the field level and assign clear responsibilities for

implementing its decision within seven days of receipt of the complaint by GRC. If GRC decision is

not acceptable to the AP, if the suggested corrective action/measure is not started within seven

days, the matter/AP will be referred to the third level.

Third Level: The ICG will refer AP and its unresolved complaint or major issues to the PMO EO who

will act within 15 days.

Fourth Level: For extremely major issues that will go beyond the third level, these will be referred

to the project steering committee (PSC), to be resolved within 30 days. Environmental complaints

(other than those that will involve the legal system) are expected to be mainly resolved at the

second level, and to a lesser extent on the third level.

27. Despite the GRM, an AP will have access to the country's legal system at any stage. Accessing the

country’s legal system can run parallel to accessing the GRM and is not dependent on the negative

Outcome of the GRM. If the established GRM is not in a position to resolve the issue, the affected

person also can use the

ADB Accountability

Mechanism (AM)

through directly

contacting (in writing)

the Complaint

Receiving Officer (CRO)

at ADB headquarters or

the ADB Nepal Resident

Mission. The complaint

can be submitted in the

country’s language. The ADB Accountability

Mechanism information

will be included in the

PID to be distributed to

the affected

communities, as part of

the GRM. The GRM

approach is presented

in the Figure 3.

2.3.2. Establishment and Composition of GRC

28. The MoWS, as the Project executing agency, will establish the GRM and its support system, including

setting up the Grievance Redress Committee (GRC) at the subproject level. The GRC will comprise of

the: (i) Chief of the WSSDO; (ii) members of the WUSC; (iii) two representatives of affected persons,

Figure 3: Grievances Redress Mechanism

Page 30: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

19 | P a g e

a male and a female; (iv) a member of IP community, preferably female; (v) a representative of a

non- government organization or community-based organization actively involved in IP

development/other backward communities in the area, if any; (vi) local government

representatives, i.e., RMs and DCC; (vii) DSMC social safeguard expert; and (viii) DSMC

Environmental Safeguard Expert (ESE). The Environmental Safeguard Assistant (ESA) of the ICG will

oversee the implementation/observance of the mechanism for environmental complaints at the

subproject level. He/she will be technically advised, supported and trained by DRTAC environmental

specialist and the DSMC ESE. PMO’s Environmental Officer will oversee the implementation/

observance of the GRM in all subprojects. Representatives of affected persons (APs), civil society,

and eminent citizens will be invited as observers during GRC meetings. Contractors and WUSCs (as

Operators) will be required to designate their respective counterpart GRM staff.

29. The GRM will accommodate both informally and formally lodged, but Project-related, valid

grievances. Informally-lodged grievances are those received by the Contractors during construction

or WUSCs during operation. Formally, lodged grievances are those received at the ICG office. The

ICG, GRC, and PMO maintain records of all grievances, informally- and formally lodged, valid and

invalid, and appealed. The ICG will immediately inform the PMO, as necessary, particularly when an

AP makes an appeal in court. The PMO will in turn immediately inform the ADB of the same. The

observance/implementation of the GRM will be reported by the: (i)ICG ESA in the subproject’s monthly progress reports, semi-annual subproject environmental monitoring report (EMR) during

construction and annual subproject EMR during operation; and (ii) PMO EO in the Project’s monthly progress report, semi-annual Project EMR during the construction and annual Project EMR during

operation.

30. The GRC has already been formed as per the ADB’s Project Administration Manual in all Town Projects. In most of the towns, two levels of GRC (Local level GRC & Town level GRC) has been

formulated and actively working at the project level. Reformation or replacement of some of the

GRC members has been fulfilled. It has been done due to the reformation of WUSCs of Sakhuwa-

Mahendranagar and Charali town projects.

2.4. Monitoring and Reporting

31. The implementation agency is monitoring and measuring the progress of implementation of the

EMP as stipulated in the approved IEE reports. The extent of monitoring activities are commensurate

with the project’s risks and impacts. In addition to record information and track performance, the

implementation has undertaken inspections to verify compliance with the EMP and progress toward

the expected outcomes. For selected Town projects likely to have significant adverse environmental

impacts, the PMO has retained qualified and experienced experts or qualified Consultants to verify

monitoring information. The Central, Regional and Local level monitoring team has documented

monitoring results in regular and periodic formats, identifying the necessary corrective actions, and

reflect them in a corrective action plan and those corrective actions are implementing by following

up to ensure Town Projects effectiveness. The periodic monitoring reports of EMP implementation

including compliance issues and corrective actions, feedbacks and outcomes from the Town project

sites covering all monitoring parameters has been prepared to address likely significant adverse

environmental impacts and enhance the beneficial impacts during design, construction and

operation stages of the project.

Page 31: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

20 | P a g e

3. COMPLIANCE STATUS WITH THE ENVIRONMENTAL MANAGEMENT AND MONITORING PLANS

32. The Environmental Management and Monitoring Plan of the subprojects has proposed in approved

IEE proposing appropriate mitigation measures for implementation including institutional

arrangement and responsibilities for monitoring to ensure compliance with environmental

regulations and proper implementation of the proposed mitigation measures. The selected

subprojects followed EMPs of IEEs ensuring continuous improvement of environmental protection

measures during design, construction, and operation stages in order to prevent, reduce, or mitigate

adverse impacts. The EMP of individual Town projects has included proposed mitigation measures

of the project activities, environmental monitoring and reporting requirements, emergency

response procedures, related institutional or organizational arrangements, capacity development

and training measures, implementation schedule, cost estimates, and performance indicators. The

Environmental Management and Monitoring Plans are under implementation based on guidelines

defined in the IEE Reports of Town Projects.

33. During the visit, the contractor’s personnel and site staff from the Consultant were oriented/trained

and made aware of their responsibility towards the Environmental Safeguarding issues during

construction works, such as:

• Adhering to the mitigation measures in the EMP during construction of the sub-project;

• Assessing environmental conditions, cleared areas, and other infrastructure, before and after

construction to reinstate the environment to pre-project conditions.

• Facilitate Town projects to construct, operate, and maintain the water distribution facility in

accordance with national requirements and internationally accepted standards meeting national

water quality standards or, in their absence, World Health Organization (WHO) Guidelines for

Drinking Water Quality13.

34. In line with the Third Small Towns Water Supply and Sanitation Sector Project (TSTWSSSP)

Operational Guideline-2071 and ADB Project Administration Manual of TSTWSSSP, GRC have been

formed in the town projects. All the town projects have been advised to expedite the tasks fully

adhering to the process mentioned in Grievance Redress Mechanism (GRM). Town projects in all

districts advised to keep proper report and record of grievances received if any. Appendix I provides

the information on submitted grievances and resolved status.

35. The compliance status with EMP and Monitoring Plans from January to June 2020 described in this

Biannual Environmental Safeguard Report is based on Status of completed Town Projects, DLP

stages, Construction and O& M stages of selected Third Small Towns Water Supply and Sanitation

Projects.

36. Detailed Compliance Status with EMP and Monitoring Plans of the each subprojects are presented

below:

3.1. Compliance Status with Environmental Management and Monitoring Plans of Town Projects of

ERDSMC

37. The project towns under ERDSMC are under construction supervision phase, O & M phase and DLP

stages and environmental monitoring has been conducting as per environmental management plan

of the respective towns. Trainings on OBA and Awareness & skill-development has been organized

in respective towns. The compliance status with Environmental Management and Monitoring Plans

of ERDSMCS Towns has been planned and implemented as per approved IEE reports and EMPs. The

Environmental Monitoring and activities of EMP implementation considered as per progress status

of projects both at construction and O & M stages.

13 National Drinking Water Quality Standards, 2006, WHO Guidelines for Drinking-Water Quality, 4th Edition, 2011

Page 32: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

21 | P a g e

38. Experts of DSMCS involved in design and Construction Supervision of different town sub-projects

and monitoring of EMPs with involvement of stakeholders such as the WUSC, Project Management

Office (PMO), Regional Project Management Office (RPMO), Town Development Fund (TDF), ICG,

Design Supervision and Management Consultants (DSMC) and Contractor.

39. EMPs of the Bidur and Lalbandi town sub-projects monitored by Environmental monitors. OBA and

Awareness & skill-development trainings have been organized in all implemented towns namely

Charali and Mahendranagar, Sunsari, Ramnagar Mirchaiya and Sakuwa Mahendranagar, Bidur

Nuwakot, Birendranagar Chitwan, Katahariya Rautahat, Katari Udaypur and Lalbandi Sarlahi.

Monthly environmental monitoring report prepared by the environmental monitors based on the

EMP implementation activities.

40. The detailed compliance status with EMP and monitoring from January to June 2020 of ERDSMC

Projects namely Charali Jhapa, Mahendranagar Sunsari, Ramnagar-Mirchaya, Sakuwa-

Mahendranagar, Bidur-Nuwakot, Birendranagar Chitwan, Katahariya_Rautahat, Katari_Udaypur,

Lalbandi Sarlahi and Ramnagar Mirchaya Strom Drainage TSTWSSSPs are presented below:

3.1.1. Charali Jhapa Water Supply and Sanitation Project

41. The Environmental Management and Monitoring Plans has been implemented as per approved

IEE of Charali Jhapa TSTWSSP. The project was completed on August 2019. During the visit, the

contractor’s personnel and site staff from the Consultant were oriented/trained and made aware

of their responsibility towards Environmental Safeguarding issues, during construction works,

such as:

• Adhering to the mitigation measures in the EMP during construction of the sub-project; and

• Assessing environmental conditions, cleared areas, and other infrastructure, before and after

construction to reinstate the environment to pre-project conditions.

42. Overall Compliance Status with EMP and Monitoring Plans of the Charali subproject are presented

in Table 7 below.

Table 7 : Overall Compliance with EMP of Charali Water Supply and Sanitation Sector Project

Sub-Project

Name

EMP Part of

Contract

Documents

(Y/N)

EMP Being

Implemente

d (Y/N)

Status of

implementation

(Excellent/Satisfactory /

Partially satisfactory /

Below Satisfactory)

Action Proposed and

Additional Measures

Required

TSTWSSSP/N

CB- 01(Lot 1)

/ Charali,

Jhapa

Y

Y

Satisfactory

Project completed,

Major issues on DLP

stages will be

addressed by WUSC

Public Consultation and Disclosure

43. The DSMC visited the project sites on a regular basis during O &M stages. As there were no major

environmental issues during the construction, O & M phase of the project no formal public

consultations conducted based on environmental issues. The informal public consultations have

solved the minor environmental issues that occurred during the DLP phase of the project.

3.1.2. Mahendranagar, Sunsari Water Supply and Sanitation Project

44. The Environmental Management and Monitoring Plans has been implemented as per approved

IEE of Mahandranagar Sunsari TSTWSSP. The project was completed on December 2019. During

the visit, the contractor’s personnel and site staff from the Consultant were oriented/trained and

Page 33: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

22 | P a g e

made aware of their responsibility towards Environmental Safeguarding issues, during

construction works, such as:

• Adhering to the mitigation measures in the EMP during construction of the sub-project; and

• Assessing environmental conditions, cleared areas, and other infrastructure, before and

after construction to reinstate the environment to pre-project conditions.

45. Overall Compliance Status with EMP and Monitoring Plans of the Mahandranagar Sunsari

subproject are presented in Table 8 below.

Table 8 : Overall Compliance with EMP

Sub-Project

Name

EMP Part of

Contract

Documents

(Y/N)

EMP Being

Implemente

d (Y/N)

Status of Implementation

(Excellent/Satisfactory/Partially

satisfactory /Below Satisfactory)

Action Proposed and

Additional Measures

Required

TSTWSSSP/NCB-01

(Lot 2)/

Mahendranagar,

Sunsari

Y

Y

Satisfactory

The project is Completed and

project is operating by WUSC.

Project is running well

Remaining EMP

activities will be

properly implemented

Public Consultation and Disclosure

46. The DSMC visited the project sites on a regular basis. During monitoring and project level

consultations, no major environmental issues were observed. Mitigation measures proposed in the

EMP and informal public consultations addressed environmental issues that raised during the

construction phase of the project.

3.1.3. Ramnagar-Mirchaiya, Siraha Water Supply and Sanitation Sector Projects

47. The IEE of Ramnagar Mirchaiya WSSSP of Siraha District approved from MOWS. As per defined

norms and parameters in the Environmental Monitoring and Management plan, field level

supervision and monitoring have been conducted with active involvement of monitoring team of

the DSC (including CSE, EMP) and Environmental Specialists. The contractor and workers were

oriented/trained and made aware of their responsibility towards Environmental Safeguarding issues

during construction works, such as:

• Adhering to the relevant adverse environmental impacts mitigation measures that are set out

in the EMP during carrying out construction activities of the sub-project; and

• Assessing the conditions of surrounding environmental conditions, status of adjacent cleared

area and other infrastructure, prior to construction commencement and upon completion of

construction and thereby fully reinstating the environment to at least their pre-project

conditions.

48. The progress summary of the projects up to June 2020 are presented below:

Progress of Work up to June 2020

Description of works as listed during transferring the project to

Stage II and any other outstanding works % Work completed (%)

Household connections 100% 97%

Valve chamber cover 100*% 99%

Water treatment (Installation of Treatment Plant completed) 100% Installation of Treatment

Plant completed

Page 34: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

23 | P a g e

49. The Compliance Status with EMP and Monitoring Plans of the Ramnagar Mirchaiya subproject are

presented in the Table 9 below.

Table 9 : Ramnagar-Mirchaiya Water Supply and Sanitation Sector Project

S.N. Major Environmental

Impacts

Proposed Mitigation Measures Status Remarks

Yes No A: Pre-Construction Phase

1.

Consents, permits,

clearances, no

objection certificate

(NOC), etc.

Obtain all of the necessary consents, permits, clearance √

Include in detailed design drawings and documents all

conditions and provisions if necessary

2.

Existing Utilities

(Spoil Disposal)

Collection & dumping of spoil materials at spoil disposal sites

Benching of ground slope √

Maintenance of Slope √

Construction of Toe Wall ×

Not

necessary

Construction of drainage ×

Bioengineering works ×

3.

Drinking Water

Water Quality Test ( Deep Tube well & Shallow well) √

Establishment o f Toilets at least 30 m downstream of the

drinking water source.

Sealed Septic tanks (water tight) √

Establishment of a test pit and regular water quality

monitoring

4

Sanitation (Toilets

and septage

disposal)

Establishment of Toilets at least 30 m downstream of the

drinking water source.

Separate Toilets for male and female √

Sealed Septic tanks (water tight) √

Location of disposal pits at least 300 m away from the

nearest residence

Proper septage management √

5. Construction work

camps, stockpile

areas, storage areas,

and disposal areas

Construction camp sites (Standard) √

Stockpiling Area ( Environmental friendly) √

Disposal Areas ( managed ) √

Storage Area (stockpiling material cover ) √

6.

Waste Generation

Differentiate of Solid wastes into Organic & Inorganic Solid

Wastes

Recycle of Solid Wastes √

Disposal of solid waste ( Mechanism) √

7.

Source of materials

Source materials ( sand, gravel, aggregates)

from approved quarry sites

Source materials ( sand, gravel, aggregates from approved

crusher sites

B: Construction Phase

a. Physical Environment

1.

Topography

landforms, geology,

and soils and river

morphology and

hydrology

Coordinate with MoFE, DCC, and local authorities regarding

restrictions in quarrying from rivers

Crusher Sites Approved from GoN √

Consultation with district development committee on

designated disposal areas for spoil disposal

Prevention of entering of waste water into streams,

watercourses, or irrigation system

Ensure storm water flow to divert (shall not lead to inundation

and other nuisances in low lying areas )

Conduct All earthworks related works during dry season √

Monitor water quality according to EMP √

2.

Air Quality

Arrest dust through frequent water spray √

Require trucks delivering aggregates and cement to have

tarpaulin cover

Page 35: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

24 | P a g e

S.N. Major Environmental

Impacts

Proposed Mitigation Measures Status Remarks

Yes No Limit speed of construction vehicles in access roads and

worksites to a maximum of 30 kph.

Use of vehicles complying with NVMES, 2069

enforcement, and green sticker standards and

Prohibition of open burning of solid waste. √

3.

Noise Pollution

Construct speed bumps at settlement areas √

Avoid use of pressure horn in the nearby settlement area

and construction sites

Erect no horn signs in settlement areas, health post,

schools and other public areas

Work during day time rather than night time √

Warning signs in construction sites √

Maintain sound levels not exceeding 80 decibels √

4.

Removal of

Aesthetics values

Preparation of debris disposal plan. √

Removal of all construction and demolition wastes on a daily

basis.

Coordination with District development office for beneficial

uses for excess excavated soils or immediately disposes to

designated areas

All vehicles delivering fine materials to the site and carrying

debris for disposal shall be covered to avoid spillage.

b. Biological Environment

1.

Biodiversity

Damage to Forest (Tree Cutting ) ×

Disturbance to wildlife ×

Disturbance to Aquatic life ×

Disturbance to Birds ×

c. Socio-economic Environment

1.

Local people hiring

& Local Market

development

Priority hiring of labor force from communities in the

vicinity of the site.

Purchasing of construction materials from local market √

2.

Community welfare

Consultation with local community/district development

committee/local administration to inform about the nature,

duration, likely effects of the construction work

Relocation of existing infrastructure (such as water distribution

pipes, electricity pylons, etc.) before construction starts at the

sub project sites.

Obtained permission from respective local authority for the use

of water for construction.

3.

Community health

and safety

Consult with district development committee on the designated

areas for stockpiling of soils, gravel, and other construction

materials

Construction of temporary latrines for workers with a proper pit

to avoid contamination of water sources.

Workers were made aware of the following general rules:

no alcohol/drugs on site;

prevent excessive noise;

no fires permitted on site expect if needed for the construction

works

Other than pre-approved security staff, no workers shall be

permitted to live on the construction site.

Grievance/ Compliant remedial action mechanism fully

applied

Workers are provided with personal protective equipment

(reflectors /cloths; footwear, gloves, goggles, and masks)

Availability of first aid ( Medical insurance coverage for

workers)

The hygienic manner in work camps. √

Page 36: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

25 | P a g e

S.N. Major Environmental

Impacts

Proposed Mitigation Measures Status Remarks

Yes No Ensure uncontaminated water for drinking, cooking, and

washing, clean eating areas where workers are not exposed to

hazardous or noxious substances; Sanitation facilities are

available at all times.

Provide H & S orientation training to all new workers. √

Mark and provide sign boards in chemical storage areas,

material storage areas & waste disposal areas.

d. Historical, Cultural, and Archaeological Characteristics

1. Physical and

cultural heritage

Stop work immediately to allow further investigation if

any finds are suspected.

No cultural heritage

areas found within

project area

e. Chemical Environment

1.

Mishandling of

chlorine

All disinfection chemicals require proper storage and handling practices: ii) providing safe

storage for chemicals; iii) ensure that the person is hired, with knowledge of chlorine use

for disinfection process during operation iv)Ensure use of PPE while using chemicals; v)

Use of chlorine guideline as per WHO

D. Operation and Maintenance Activity

Performance Target

Activity carried during

reporting months

(Yes/ No)

Quantity of treated water as set in the Performance Target meeting Nepal National

Drinking Water Quality Standard (NDWQS), 2005 is being delivered?

yes

Frequency of water quality monitoring (as per Table 1, frequency of monitoring for

urban water supply system, NDWQS) is being met?

Residual pressure of water at ground level should be at least 5m positive head in 90%

of the cases of at least 10 different domestic meter points of the distribution network

randomly chosen for verification. The pressure will be measured twice a week by

Contractor in the presence of Employer’s/WUSC’s representative/s. Is the above activity carried out by the Contractor?

yes

Is residual chlorine 0.1 mg/l minimum maintained? yes

Are pumps, motors and generators run on the basis of the characteristic curves

submitted by the Contractor along with the offer and the actual duty conditions for the

month?

yes

Take at least 2 samples each of raw water and treated water every day in the presence

of employer/co-employer or their designated representatives, analyse them and report

any deviation from Nepal standards and send weekly water quality test reports (with

summary of daily reports) to employer.

Are the above activities being done?

yes

The Contractor shall train WUSC’s technical staff run the whole system during whole O

& M period as ON-THE-JOB TRAINING (OJT).

Does the Contractor carry above activity during the reporting month?

yes

Does Contractor maintain Logbooks for operation and maintenance of all the equipment

and services in a mutually agreed format?

yes

Overall Compliance with EMP

Sub-Project

Name

EMP Part of

Contract

Documents (Y/N)

EMP Being

Implemented

(Y/N)

Status of Implementation

(Excellent/ Satisfactory/

Below Satisfactory)

Action Proposed and Additional

Measures Required

Ramnagar-

Mirchaiya,

Siraha

Y

Y

Satisfactory

Health and safety continuation

during completion of remaining

works i.e. Gate installation at

Chhagarya site, HH connections

etc. Local Level Redress Committee (Second Level) Ramnagar-Mirchaiya Town

S.N. Name/ Designation

1 Mr. Kusheshwar Sah, Chairman

2 Mr. Deep Narayan Sah, Secretary, Representative, Municipality

Page 37: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

26 | P a g e

3 Mr. Tatpta Bahadur Rawal, Member (Social Development Officer,RPMO)

4 Mr. HomJyoti Adhikari, Member(Environmental Safeguards Specialist, ERDSMC)

5 Mr. Roshan Subedi, Member( Gesi Specialist, ERDSMC representative)

6 Mr. Shyam Pd. Sah, Member

7 Mr. Raju Pd Sah, Member

8 Mr. Jageshwar Sah, Member

9 Mr. Bhawani Mahara, Member

Public Consultation and Disclosure

50. The DSMC visited the project sites on a regular basis. As there were no major environmental issues during

the construction phase of the project no formal public consultations were conducted based on

environmental issues. The informal public consultations have solved the minor environmental issues that

occurred during the construction phase of the project. Form June 12, 2019, project entered into DLP stage

and operating under WUSC and maintaining by the Contractor.

3.1.4. Katari, Udayapur Water Supply and Sanitation Sector Projects

51. The approved IEE of Katari WSSSP of Udayapur District has determined the monitoring parameter

schedule and responsibility under section EMP. As per defined norms and parameters in the

Environmental Monitoring and Management plan, field level supervision and monitoring have been

conducted with active involvement of monitoring team of the DSC (including CSE, EMP) and

Environmental Specialists. The contractor and workers were oriented/trained and made aware of their

responsibility towards Environmental Safeguarding issues during construction works, such as:

• Adhering to the relevant adverse environmental impacts mitigation measures that are set out in

the EMP during carrying out construction activities of the sub-project; and

• Assessing the conditions of surrounding environmental conditions, status of adjacent cleared

area and other infrastructure, prior to construction commencement and upon completion of

construction and thereby fully reinstating the environment to at least their pre-project

conditions.

• EMP breakdowns worked out; and in process of implementation

52. The progress summary and compliance status with EMP of the projects up to June 2020 are

presented below:

Component-Wise Physical Work Progress up to June 2020

Description of works as listed during

transferring the project to Stage II and any

other outstanding works

% Work completed and progress during

reporting month

Work

completed

(%)

i. Site Development of all sites (2 nos. of 25

cum RVT, 40cum RVT, 1000cum, WTP site,

Office Building Site etc.)

100% Partially completed of all sites 80%

ii. Remaining Meter Connection 100%

• Out of 2850 nos., 1565 nos. of water

meter connected – 54.91%;

• Out of 2022 nos., 1565 nos. of water

meter connected – 77.40%;

• Out of 2850 nos., household pipe

connected with water meter and end

cap 1945 nos. – 68.25%;

• Out of 2022 nos., household pipe

connected with water meter and end

cap 1945 nos. – 96.19%;

iii. Repair and Operation of Existing Water

Treatment Plant 100% Partially completed 95%

iv. Approach Road (Gravel and RCC) 100% Gravel road not yet started; and out of 300

m RCC road 125 m completed

0% and

42%

Page 38: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

27 | P a g e

v. Completion and handover of Public and

Institutional Toilet 100% Handed over 100%

vi. Protection structures at Tawa Khola near

Sump well and Collector wells 100%

100%

vii. Miscellaneous works ( Placing of Cover Slab

of Manholes, MS clamps in Tawa khola bridge,

GI crossing of Kholshi etc.

100%

Placing of Cover Slab of Manholes at almost

more of the places; Remaining MS clamps,

GI crossing not yet started

60%, 0%,

0%

viii. Repair and maintenance of all Leakage of

pipe line 100% On the progressive way 75%

ix. Gate on the RVT25 at East and West 100% Placed 100%

Table 10 : Katari Water Supply and Sanitation Sector Project

S.N. Major Environmental

Impacts

Proposed Mitigation Measures

Status

Remarks Yes No A: Pre-Construction Phase

1.

Consents, permits,

clearances, no

objection certificate

(NOC), etc.

Obtain all of the necessary consents, permits, clearance √

Include in detailed design drawings and documents all

conditions and provisions if necessary

2.

Existing Utilities

(Spoil Disposal)

Collection & dumping of spoil materials at spoil disposal sites √

Benching of ground slope √

Maintenance of Slope √

Construction of Toe Wall ×

Not

necessary

Construction of drainage ×

Bioengineering works ×

3.

Drinking Water

Water Quality Test ( Deep Tube well & Shallow well) √

Establishment o f T o i l e t s a t l e a s t 3 0 m downstream of

the drinking water source.

Sealed Septic tanks (water tight) √

Establishment of a test pit and regular water quality

monitoring

4

Sanitation (Toilets

and septage

disposal)

Establishment o f Toilets at least 30 m downstream of the

drinking water source

Separate Toilets for male and female √

Sealed Septic tanks (water tight) √

Location of disposal pits at least 300 m away from the

nearest residence

Proper septage management √

5. Construction work

camps, stockpile

areas, storage areas,

and disposal areas

Construction camp sites (Standard) √

Stockpiling Area ( Environmental friendly) √

Disposal Areas ( managed ) √

Storage Area (stockpiling material cover ) √

6.

Waste Generation

Differentiate of Solid wastes into Organic & Inorganic Solid

Wastes

Recycle of Solid Wastes √

Disposal of solid waste ( Mechanism) √

7.

Source of materials

Source materials ( sand, gravel, aggregates)

from approved quarry sites

Source materials ( sand, gravel, aggregates from approved

crusher sites

B: Construction Phase

a. Physical Environment

1.

Topography

landforms, geology,

and soils and river

morphology and

hydrology

Coordinate with MoEF, DCC, and local authorities regarding

restrictions in quarrying from rivers

Crusher Sites Approved from GoN √

Consultation with district development committee on

designated disposal areas for spoil disposal

Page 39: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

28 | P a g e

S.N. Major Environmental

Impacts

Proposed Mitigation Measures

Status

Remarks Yes No Prevention of entering of waste water into streams,

watercourses, or irrigation system

Ensure storm water flow to divert (shall not lead to inundation

and other nuisances in low lying areas )

Conduct All earthworks related works during dry season √

Monitor water quality according to EMP √

2.

Air Quality

Arrest dust through frequent water spray √

Require trucks delivering aggregates and cement to have

tarpaulin cover

Limit speed of construction vehicles in access roads and

worksites to a maximum of 30 kph.

Use of vehicles complying with NVMES, 2069

enforcement, and green sticker standards and

Prohibition of open burning of solid waste. √

3.

Noise Pollution

Construct speed bumps at settlement areas √

Avoid use of pressure horn in the nearby settlement area

and construction sites

Erect no horn signs in settlement areas, health post,

schools and other public areas

Work during day time rather than night time √

Warning signs in construction sites √

Maintain sound levels not exceeding 80 decibels √

4.

Removal of

Aesthetics values

Preparation of debris disposal plan. √

Removal of all construction and demolition wastes on a daily

basis.

Coordination with District development office for beneficial

uses for excess excavated soils or immediately disposes to

designated areas.

All vehicles delivering fine materials to the site and carrying

debris for disposal shall be covered to avoid spillage.

b. Biological Environment

1.

Biodiversity

Damage to Forest (Tree Cutting ) ×

Disturbance to wildlife ×

Disturbance to Aquatic life ×

Disturbance to Birds ×

c. Socio-economic Environment

1.

Local people hiring

& Local Market

development

Priority hiring of labor force from communities near

the site.

Purchasing of construction materials from local market. √

2.

Community welfare

Consultation with local community/district development

committee/local administration to inform about the nature,

duration, likely effects of the construction work.

Relocation of existing infrastructure (such as water distribution

pipes, electricity pylons, etc.) before construction starts at the

sub project sites.

Obtained permission from respective local authority for the use

of water for construction.

3.

Community health

and safety

Consult with district development committee on the designated

areas for stockpiling of soils, gravel, and other construction

materials.

Only a

toilet for

about 40

workers. Construction of temporary latrines for workers with a proper pit

to avoid contamination of water sources.

Page 40: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

29 | P a g e

S.N. Major Environmental

Impacts

Proposed Mitigation Measures

Status

Remarks Yes No Workers were made aware of the following general rules:

no alcohol/drugs on site;

prevent excessive noise;

no fires permitted on site expect if needed for the

construction works

Contractor

was

instructed

to add

another

toilet. Other than pre-approved security staff, no workers shall be

permitted to live on the construction site.

Grievance/ Compliant remedial action mechanism fully

applied

Workers are provided with personal protective equipment

(reflectors /cloths; footwear, gloves, goggles, and masks)

Availability of first aid ( Medical insurance coverage for

workers)

The hygienic manner in work camps.

Ensure uncontaminated water for drinking, cooking, and

washing, clean eating areas where workers are not exposed to

hazardous or noxious substances; Sanitation facilities are

available at all times.

Provide H & S orientation training to all new workers.

Mark and provide sign boards in chemical storage areas,

material storage areas & waste disposal areas.

d. Historical, Cultural, and Archaeological Characteristics

1.

Physical and

cultural heritage

Stop work immediately to allow further investigation if

any finds are suspected.

No cultural heritage

areas found within

project area

e. Chemical Environment

1.

Mishandling of

chlorine

All disinfection chemicals require proper storage and handling

practices: ii) providing safe storage for chemicals; iii) ensure that

the person is hired, with knowledge of chlorine use for

disinfection process during operation iv)Ensure use of PPE while

using chemicals; v) Use of chlorine guideline as per WHO

(Annex 6 )

Not

Applicable

C: Operation and Maintenance Activity

S. N. Performance Target

Activity carried

during reporting

months

(Yes/ No)

If no, specify

reason Remarks

i Quantity of treated water as set in the Performance

Target meeting Nepal National Drinking Water

Quality Standard (NDWQS), 2005 is being delivered?

Yes Yes

ii Frequency of water quality monitoring (as per Table

1, frequency of monitoring for urban water supply

system, NDWQS) is being met?

Yes Yes But not reported

regularly

iii Residual pressure of water at ground level should be

at least 5m positive head in 90% of the cases of at

least 10 different domestic meter points of the

distribution network randomly chosen for

verification. The pressure will be measured twice a

week by Contractor in the presence of

Employer’s/WUSC’s representative/s.

Is the above activity carried out by the Contractor?

Yes Not Regularly

iv Is residual chlorine 0.1 mg/l minimum maintained? Yes

v Are pumps, motors and generators run on the basis

of the characteristic curves submitted by the

Contractor along with the offer and the actual duty

conditions for the month?

Yes characteristic curves

still not submitted

by the Contractor

Page 41: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

30 | P a g e

vi Take at least 2 samples each of raw water and treated

water every day in the presence of employer/co-

employer or their designated representatives,

analyse them and report any deviation from Nepal

standards and send weekly water quality test reports

(with summary of daily reports) to employer.

Are the above activities being done?

Yes

vii The Contractor shall train WUSC’s technical staff run the whole system during whole O & M period as ON-

THE-JOB TRAINING (OJT).

Does the Contractor carry above activity during the

reporting month?

Yes Not regular and

seen partially

viii Does Contractor maintain Logbooks for operation

and maintenance of all the equipment and services in

a mutually agreed format?

Yes

Overall Compliance with EMP

Sub-Project

Name

EMP Part of

Contract

Documents

EMP Being

Implemented

(Y/N)

Status of

Implementation

(Excellent/ Satisfactory/

Action Proposed and Additional

Measures Required

Katari,

WSSSP

Y

Y

Satisfactory

No, few sites only work has been

going on and still numbers of places

repair and maintenance work

remains Continuation of proper

management of health and

sanitation conditions

Local level grievance Redress Committee (First Level)

Name/ Designation

Mr. Dodaraj Poudel, Chairman, WUSC

Mr. Shiva Adhikari Social Safeguard Specialist, ERDSMC

Mr. Dhanraj Shah, Construction Engineer

Ms. Jyoti Kala Tamang, Social mobilizer

Mr.Durga Pokharel, Contractor Representative

Public Consultation and Disclosure

53. The DSMC visited the project sites on a regular basis. As there were no major environmental issues during

the construction phase of the project no formal public consultations were conducted based on

environmental issues. The informal public consultations have solved the minor environmental issues that

occurred during the construction phase of the project. Operation and maintenance works going on

simultaneously. Project entered into Operation and Maintenance Stage (Second Stage) effective from June

20, 2019 and decision made on 5 September 2019.

3.1.5. Sakhuwa-Mahandranagar, Dhanusa Water Supply and Sanitation Sector Projects

54. The approved IEE of Sakhuwa Mahendranagar Town project has determined the monitoring parameter,

schedule and responsibility. As per defined norms and parameters in the Environmental Monitoring and

Management plan, field level supervision and monitoring have been conducted. The contractor and

workers were oriented/trained and made aware of their responsibility towards Environmental

Safeguarding issues during construction works, such as:

• Adhering to the relevant adverse environmental impacts mitigation measures that are set out in the EMP

during carrying out construction activities of the sub-project; and

• Assessing the conditions of surrounding environmental conditions, status of adjacent cleared area and

other infrastructure, prior to construction commencement and upon completion of construction and

thereby fully reinstating the environment to at least their pre-project conditions.

• EMP breakdowns worked out; and in process of implementation

55. The progress summary and Compliance status of the projects up to June 2020 are presented below:

Page 42: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

31 | P a g e

Progress up to June 2020

Description of works as listed

during transferring the project to

Stage II and any other

outstanding works

% Work completed and progress during

reporting month

Work

completed

(%)

i. House connection work 100% Out of 2015 nos.1310 nos. completed 64%

ii. Washout connection 100% Site possession not given by WUSC.

iii. Well development BH-3 100% Not started yet.

iv. Level Indicator of OHT 100% Not started yet.

Table 11 : Sakhuwa-Mahendranagar Water Supply and Sanitation Sector Project

S.N. Major Environmental

Impacts

Proposed Mitigation Measures

Status

Remarks Yes No

A: Pre-Construction Phase

1.

Consents, permits,

clearances, no

objection certificate

(NOC), etc.

Obtain all of the necessary consents, permits, clearance,

etc.

Include in detailed design drawings and documents all

conditions and provisions if necessary √

2.

Existing Utilities

(Spoil Disposal)

Collection & dumping of spoil materials at spoil disposal sites

Benching of ground slope √

Maintenance of Slope √

Construction of Toe Wall ×

Not

necessary

Construction of drainage ×

Bioengineering works ×

3.

Drinking Water

Water Quality Test ( Deep Tube well & Shallow well) √

Establishment of Toilets at least 30 m downstream of the

drinking water source.

Sealed Septic tanks (water tight) √

Establishment of a test pit and regular water quality

monitoring

4

Sanitation (Toilets

and septage

disposal)

Establishment of Toilets at least 30 m downstream of the

drinking water source. √

Separate Toilets for male and female √

Sealed Septic tanks (water tight) √

Location of disposal pits at least 300 m away from the

nearest residence

Proper septage management √

5. Construction work

camps, stockpile

areas, storage areas,

and disposal areas

Construction camp sites (Standard) √ Not

necessary Stockpiling Area ( Environmental friendly) x

Disposal Areas ( managed ) √

Storage Area (stockpiling material cover ) √

6.

Waste Generation

Differentiate of Solid wastes into Organic & Inorganic Solid

Wastes

Recycle of Solid Wastes √

Disposal of solid waste ( Mechanism) √

7.

Source of materials

Source materials ( sand, gravel, aggregates)

from approved quarry sites

Source materials ( sand, gravel, aggregates from approved

crusher sites

B: Construction Phase

a. Physical Environment

1.

Topography

landforms, geology,

and soils and river

morphology and

hydrology

Coordinate with MoFE, DCC, and local authorities regarding

restrictions in quarrying from rivers

Crusher Sites Approved from GoN √

Consultation with district development committee on

designated disposal areas for spoil disposal

Page 43: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

32 | P a g e

S.N. Major Environmental

Impacts

Proposed Mitigation Measures

Status

Remarks Yes No

Prevention of entering of waste water into streams,

watercourses, or irrigation system

Ensure storm water flow to divert (shall not lead to inundation

and other nuisances in low lying areas )

Conduct All earthworks related works during dry season √

Monitor water quality according to EMP √

2.

Air Quality

Arrest dust through frequent water spray √

Require trucks delivering aggregates and cement to have

tarpaulin cover

Limit speed of construction vehicles in access roads and

worksites to a maximum of 30 kph.

Use of vehicles complying with NVMES, 2069

enforcement, and green sticker standards and

Prohibition of open burning of solid waste. √

3.

Noise Pollution

Construct speed bumps at settlement areas x Not

necessary Avoid use of pressure horn in the nearby settlement area

and construction sites

Erect no horn signs in settlement areas, health post,

schools and other public areas

Work during day time rather than night time √

Warning signs in construction sites √

Maintain sound levels not exceeding 80 decibels

4.

Removal of

Aesthetics values

Preparation of debris disposal plan.

Removal of all construction and demolition wastes on a daily

basis.

Coordination with District development office for beneficial

uses for excess excavated soils or immediately disposes to

designated areas.

All vehicles delivering fine materials to the site and carrying

debris for disposal shall be covered to avoid spillage.

b. Biological Environment

1.

Biodiversity

Damage to Forest (Tree Cutting ) ×

Disturbance to wildlife ×

Disturbance to Aquatic life ×

Disturbance to Birds ×

c. Socio-economic Environment

1. Local people hiring

& Local Market

development

Priority hiring of labor force from communities in the

vicinity of the site.

Purchasing of construction materials from local market. √

2.

Community welfare

Consultation with local community/district development

committee/local administration to inform about the nature,

duration, likely effects of the construction work.

Relocation of existing infrastructure (such as water distribution

pipes, electricity pylons, etc.) before construction starts at the

sub project sites.

Obtained permission from respective local authority for the use

of water for construction.

Page 44: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

33 | P a g e

S.N. Major Environmental

Impacts

Proposed Mitigation Measures

Status

Remarks Yes No

3.

Community health

and safety

Consult with district development committee on the designated

areas for stockpiling of soils, gravel, and other construction

materials.

Needs

improveme

Construction of temporary latrines for workers with a proper pit

to avoid contamination of water sources.

Workers were made aware of the following general rules:

no alcohol/drugs on site;

prevent excessive noise;

no fires permitted on site expect if needed for the

construction works

Other than pre-approved security staff, no workers shall be

permitted to live on the construction site.

Grievance/ Compliant remedial action mechanism fully

applied

Workers are provided with personal protective equipment

(reflectors /cloths; footwear, gloves, goggles, and masks)

Availability of first aid ( Medical insurance coverage for

workers)

The hygienic manner in work camps.

Ensure uncontaminated water for drinking, cooking, and

washing, clean eating areas where workers are not exposed to

Provide H & S orientation training to all new workers.

Mark and provide sign boards in chemical storage areas,

material storage areas & waste disposal areas.

d. Historical, Cultural, and Archaeological Characteristics

1. Physical and

cultural heritage

Stop work immediately to allow further investigation if

any finds are suspected.

No such problems

arise within the project

area

e. Chemical Environment

1. Mishandling of

chlorine

All disinfection chemicals require proper storage and handling

practices: ii) providing safe storage for chemicals; iii) ensure that

the person is hired, with knowledge of chlorine use for

disinfection process during operation iv)Ensure use of PPE while

using chemicals; v) Use of chlorine guideline as per WHO

(Annex 6 )

Not

Applicable

C: Operation and Maintenance Phase

Performance Target

Activity carried

during reporting

months (Yes/ No)

Quantity of treated water as set in the Performance Target meeting Nepal National Drinking

Water Quality Standard (NDWQS), 2005 is being delivered?

Yes

Frequency of water quality monitoring (as per Table 1, frequency of monitoring for urban

water supply system, NDWQS) is being met?

Yes

Residual pressure of water at ground level should be at least 5m positive head in 90% of the

cases of at least 10 different domestic meter points of the distribution network randomly

chosen for verification. The pressure will be measured twice a week by Contractor in the

presence of Employer’s/WUSC’s representative/s. Is the above activity carried out by the Contractor?

Yes

Is residual chlorine 0.1 mg/l minimum maintained? Yes

Are pumps, motors and generators run on the basis of the characteristic curves submitted by

the Contractor along with the offer and the actual duty conditions for the month?

Yes

Take at least 2 samples each of raw water and treated water every day in the presence of

employer/co-employer or their designated representatives, analyse them and report any

deviation from Nepal standards and send weekly water quality test reports (with summary of

daily reports) to employer.

Yes

Page 45: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

34 | P a g e

Are the above activities being done?

The Contractor shall train WUSC’s technical staff run the whole system during whole O & M period as ON-THE-JOB TRAINING (OJT).

Does the Contractor carry above activity during the reporting month?

Yes

Does Contractor maintain Logbooks for operation and maintenance of all the equipment and

services in a mutually agreed format?

Yes

Overall Compliance with EMP

Sub-Project

Name

EMP Part

of

Contract

Document

s

(Y/N)

EMP Being

Implement

ed (Y/N)

Status of

Implementation

(Excellent/Satisfactory

/ Partially satisfactory

/Below Satisfactory)

Action Proposed and Additional

Measures Required

TSTWSSSP/

NCB-01(Lot 3)

Sakhuwa-

Mahendranag

ar, Dhanusha

Y

Y

Satisfactory

As the main issue of the project is

damaged the pipeline both sides of the

Highway by the road construction.

Improve the condition of safety signs

and warning signals

Local Level Grievance Redress Committee (First Level)

Name/ Designation

Mr. Ramjulum Yadav, Chairman, WUSC

Member (Social Safeguards Specialist, ERDSMC)

Mr. Tapeshwar Jha,Member( CSE, ERDSMC)

Mr. Pramod Laugi, Member (Engineer, Contractor)

Mr. Ravi Shankar Sah, Member(Social Mobiliser, ERDSMC)

Public Consultation and Disclosure

56. Project entered into Defect Liability period (DLP) effective from June 15, 2019. The DSMC visited the project

sites on a regular basis. As there were no major environmental issues during the construction and O & M

phase of the project, no formal public consultations specific to environmental issues carried out. The

informal public consultations solved minor environmental issues during O & M phases of the project.

3.1.6. Lalbandi, Sarlahi Water Supply and Sanitation Sector Project

57. The monitoring parameter schedule and responsibility under section EMP of approved IEE of Lalbandi

Town projects, field level supervision and monitoring have been conducted with active involvement of

monitoring team of the DSC (including CSE, EMP) and Environmental Specialists. The contractor and

workers were oriented/trained and made aware of their responsibility towards Environmental

Safeguarding issues during construction works, such as:

• Adhering to the relevant adverse environmental impacts mitigation measures that are set out in the

EMP during carrying out construction activities of the sub-project; and

• Assessing the conditions of surrounding environmental conditions, status of adjacent cleared area and

other infrastructure, prior to construction commencement and upon completion of construction and

thereby fully reinstating the environment to at least their pre-project conditions.

• EMP breakdowns worked out; and in process of implementation

58. The progress summary and compliance status of the projects up to June 2020 are presented below:

Summary of Progress up to June 2020

Description of works as listed during transferring the

project to Stage II and any other outstanding works %

Work completed and

progress during

reporting month

Work

completed (%)

Provide and Install Water Meters & Taps (940 nos) 100% 280 nos. 29%

Providing Household Connections (650 nos) 100% 45 nos. 7%

Construction of Surface Drains (5 nos) 100% 0.80 no 16%

Page 46: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

35 | P a g e

Construction of GV Chambers (6 nos) 100% 1.50 nos. 25%

Construction of Surface Boxes over GVs (20 nos) 100% 0%

Surface Dressing, Walkway construction and block

pavements (5 nos) 100% 0%

Treatment of Leakage from overflow pipe inside OHT

dome, Hirapur (1 job) 100% completed 100%

Painting of Hirapur OHT (1500 sq m) 100% Approval of proposal

is awaited 0%

Treatment of Leakage from overflow pipe under bottom

dome of OHT at Hirapur ( 1 job) 100% 0%

Construction of Compound Wall gate of Hirapur Camp (1

job) 100% 0%

Installation of Fire Hydrants (9 nos) 100% Installed 1 out of 9

outstanding 11%

Outdoor Lighting Works(60 sets) 100% 0%

Repair of road cuts occurred during pipe line installation

and reconstruction works (3500 sqm) 100% 0%

Construction of Warehouse -1 job (subject to availability of

quantity) 100% 0%

Miscellaneous and casual works 100% Completed 0.02 job

out of 1 2%

Supply of tools and Equipment to WUSC for future

Operation and Maintenance (1 job) 100% 0%

Table 12 : Lalbandi, Sarlahi Water Supply and Sanitation Sector Project

S.N.

Major Environmental

Impacts

Proposed Mitigation Measures

Status

Remarks Yes No

A. Pre-Construction Phase

1 Consents, permits,

clearances, no

objection certificate

(NOC) etc.

Obtain all of the necessary consents, permits, clearance, etc. √

Include in detailed design drawings and documents all

conditions and provisions if necessary

2

Existing Utilities

(Spoil Disposal)

Collection & dumping of spoil materials at spoil disposal sites

Benching of ground slope √

Maintenance of Slope √

Construction of Toe Wall √

Construction of drainage √

Bioengineering works

3

Drinking Water

Water Quality Test ( Deep Tube well & Shallow well) √

Establishment of Toilets at least 30 m downstream of the

drinking water source.

Sealed Septic tanks (water tight) √

Establishment of a test pit and regular water quality

monitoring

4

Sanitation (Toilets

and septage

disposal)

Establishment of Toilets at least 30 m downstream of the

drinking water source

Separate Toilets for male and female √

Sealed Septic tanks (water tight) √

Location of disposal pits at least 300 m away from the

nearest residence

Proper septage management √

5

Construction work

camps, stockpile

areas, storage areas,

Construction camp sites (Standard) √

Stockpiling Area ( Environmental friendly √

Disposal Areas ( managed ) √

Page 47: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

36 | P a g e

S.N.

Major Environmental

Impacts

Proposed Mitigation Measures

Status

Remarks Yes No

and disposal areas Storage Area (stockpiling material cover ) √

6

Waste Generation

Differentiate of Solid wastes into Organic & Inorganic Solid

Wastes

Recycle of Solid Wastes √

Disposal of solid waste ( Mechanism) √

7

Source of materials Source materials ( sand, gravel, aggregates) from approved

quarry sites

Source materials ( sand, gravel, aggregates from approved

crusher sites

B. Construction Phase

1

Topography

landforms, geology,

and soils and river

morphology and

hydrology

Coordinate with MoFE, DDC, and local authorities regarding

restrictions in quarrying from rivers

Quarry Sites Approved from GoN

Crusher Sites Approved from GoN

Consultation with district development committee on

designated disposal areas for spoil disposal

Prevention of entering of waste water into streams,

watercourses, or irrigation system

Ensure storm water flow to divert (shall not lead to

inundation and other nuisances in low lying areas )

Conduct All earthworks related works during dry season √

Monitor water quality according to EMP √

2

Air Quality

Arrest dust through frequent water spray √

Require trucks delivering aggregates and cement to

have tarpaulin cover

Limit speed of construction vehicles in access roads and

worksites to a maximum of 30 kph.

Use of vehicles complying with NVMES, 2069 enforcement,

and green sticker standards and

Prohibition of open burning of solid waste. √

3

Noise Pollution

Construct speed bumps at settlement areas √

Avoid use of pressure horn in the nearby settlement

area and construction sites

Erect no horn signs in settlement areas, health post,

schools and other public areas

Work during day time rather than night time √

Warning signs in construction sites √

Maintain sound levels not exceeding 80 decibels √

4

Removal of

Aesthetics values

Preparation of debris disposal plan. √

Removal of all construction and demolition wastes on a

daily basis.

Coordination with District development office for beneficial

uses for excess excavated soils or immediately disposes to

designated areas.

All vehicles delivering fine materials to the site and carrying

debris for disposal covered to avoid spillage.

C. Biological Environment

1

Biodiversity

Damage to Forest (Tree Cutting ) ×

Disturbance to wildlife ×

Disturbance to Aquatic life ×

Disturbance to Birds ×

D. Socioeconomic Environment

Local people hiring &

Local Market

Priority hiring of labor force from communities in

the vicinity of the site

Page 48: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

37 | P a g e

S.N.

Major Environmental

Impacts

Proposed Mitigation Measures

Status

Remarks Yes No

1

development Purchasing of construction materials from the local

market

2

Community welfare

Consultation with local community/district development

committee/local administration to inform about the nature,

duration, likely effects of the construction work.

Relocation of existing infrastructure (such as water

distribution pipes, electricity pylons, etc.) before

construction starts at the subproject sites

Obtained permission from respective local authority for

the use of water for construction.

Consultation with local community/district development

committee/local administration to inform about the nature,

duration, likely effects of the construction work.

3

Health and Community

safety

Consultation with district development

Committee on the designated areas for stockpiling of

soils, gravel, and other construction materials.

Contractor

was

instructed to

provide PPE

to all workers

Construction of temporary latrines for workers with

a proper pit to avoid contamination of water

sources.

Workers were made aware of the following general rules:

➢ no alcohol/drugs on site;

➢ prevent excessive noise; √

➢ no fires permitted on site expect if needed for the

construction works

Other than pre-approved security staff, no workers shall

be permitted to live on the construction site.

Grievance/ Compliant remedial action mechanism

fully applied

Workers are provided with personal protective

equipment

× (reflectors /cloths; footwear, gloves, goggles, and masks)

Availability of first aid( Medical insurance coverage for

workers)

The hygienic manner in work camps. √

Ensure

- uncontaminated water for drinking, cooking, and washing;

- clean eating areas where workers are not exposed to

hazardous or noxious substances;

Sanitation facilities are available at all times.

Provide H & S orientation training to all new workers. √

Mark and provide sign boards in chemical storage areas,

material storage areas & waste disposal areas.

E. Histological, Cultural and Archeological Characteristics

1 Physical and

cultural heritage

Stop work immediately to allow further investigation

if any finds are suspected.

No cultural heritage areas found within project area

F. Chemical Environment

1

Mishandling of

chlorine

All disinfection chemicals require proper storage and

handling practices: ii) providing safe storage for chemicals;

iii) ensure that the person is hired, with knowledge of

chlorine use for disinfection process during operation

iv)Ensure use of PPE while using chemicals; v) Use of chlorine

guideline as per WHO (Annex 6 )

Not

Applicable

G. Operation and Maintenance Activity

S.

N. Performance Target

Activity carried during

reporting months Remarks

Page 49: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

38 | P a g e

(Yes/ No)

i Quantity of treated water as set in the Performance Target

meeting Nepal National Drinking Water Quality Standard

(NDWQS), 2005 is being delivered?

Yes

ii Frequency of water quality monitoring (as per Table 1,

frequency of monitoring for urban water supply system,

NDWQS) is being met?

Yes Record (hard Copy of

tests) being maintained

by lab.

iii Residual pressure of water at ground level should be at least

5m positive head in 90% of the cases of at least 10 different

domestic meter points of the distribution network randomly

chosen for verification. The pressure will be measured twice

a week by Contractor in the presence of Employer’s/WUSC’s representative/s.

Is the above activity carried out by the Contractor?

Yes Some users are filling

their 2 nd floor roof top

reserve tanks directly

from supply line i.e. > 5

m positive.

iv Is residual chlorine 0.1 mg/l minimum maintained? Yes

v Are pumps, motors and generators run on the basis of the

characteristic curves submitted by the Contractor along with

the offer and the actual duty conditions for the month?

Yes

vi Take at least 2 samples each of raw water and treated water

every day in the presence of employer/co-employer or their

designated representatives, analyse them and report any

deviation from Nepal standards and send weekly water

quality test reports (with summary of daily reports) to

employer.

Are the above activities being done?

Yes

vii The Contractor shall train WUSC’s technical staff run the

whole system during whole O & M period as ON-THE-JOB

TRAINING (OJT).

Does the Contractor carry above activity during the

reporting month?

Yes 7 operators and guards

are provided by WUSC

to operate the systems.

Others are also locals.

viii Does Contractor maintain Logbooks for operation and

maintenance of all the equipment and services in a mutually

agreed format?

Yes

Overall Compliance with EMP

Sub-Project

Name

EMP Part of Contract

Documents (Y/N)

EMP Being

Implemented

(Y/N)

Status of

implementation

Action Proposed and

Additional Measures Required

Lalbandi, Sarlahi

WSSSP

Y Y

Satisfactory

Improve sanitation conditions

in the camps; Provide PPE to

the workers; Improve debris

disposal system

GRM Local Level Grievance Redress Committee (First Level)

S.N

.

Name/ Designation

1 Mr. Basudev Adhikari, Chairman, WUSC

2 Mr. Shiva Adhikari Social Safeguard Specialist, ERDSMC

3 Mr. Harinandan Chaudhary, Construction Engineer

4 Mr. Saroj Sah, Social mobilizer

5 Mr. Ram lochan Tiwari, Contractor Representative

Public Consultation and Disclosure

59. The DSMC visited the project sites on a regular basis. As there were no major environmental issues during

the construction phase of the project no formal public consultations were conducted based on

environmental issues. The informal public consultations have solved the minor environmental issues that

occurred during the construction phase of the project. After detailed assessment of the then status of the

project, the meeting unanimously decided to enter into Stage-II effective from Feb 23, 2020. The decisions

are noted in WUSC’s Minute Book and copy circulated to the concerned authorities. Accordingly, the

contractor started Operation and Maintenance works (Stage-II) from Feb 23, 2020 and it is continue to

date.

Page 50: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

39 | P a g e

3.1.7. Katahariya, Rautahat Water Supply and Sanitation Sector Project

60. The approved IEE of Katahariya WSSSP of Rautahat District has determined the monitoring parameter

schedule and responsibility. As per defined norms and parameters in the Environmental Monitoring and

Management plan, field level supervision and monitoring have been conducted with active involvement of

monitoring team of the DSC (including CSE, EMP) and Environmental Specialists. The contractor and

workers were oriented/trained and made aware of their responsibility towards Environmental

Safeguarding issues during construction works, such as:

• Adhering to the relevant adverse environmental impacts mitigation measures that are set out in the

EMP during carrying out construction activities of the sub-project; and

• Assessing the conditions of surrounding environmental conditions, status of adjacent cleared area

and other infrastructure, prior to construction commencement and upon completion of construction

and thereby fully reinstating the environment to at least their pre-project conditions

61. The progress summary and compliance status of the projects up to June 2020 are presented below:

Summary of Progress

Outstanding works Work in progress

Description of works as listed

during transferring the project

to Stage II and any other

outstanding works

% Work completed and progress during

reporting month

Work

completed (%)

i. House connection work 100% Out of 1635 nos.1354 nos. completed 82.81%

ii. Level Indicator of OHT 100% Not started yet.

Table 13 : Katahariya, Rautahat Water Supply and Sanitation Sector Project

S.N.

Major Environmental

Impacts

Proposed Mitigation Measures

Status

Remarks

Yes No

A. Pre-Construction Phase

1. Consents, permits,

clearances, no

objection certificate

(NOC) etc.

Obtain all of the necessary consents, permits, clearance. √

Include in detailed design drawings and documents all conditions

and provisions if necessary

2.

Existing Utilities

(Spoil Disposal)

Collection & dumping of spoil materials at spoil disposal sites √

Benching of ground slope √

Maintenance of Slope √

Construction of Toe Wall √

Construction of drainage √

Bioengineering works

3.

Drinking Water Water Quality Test ( Deep Tube well & Shallow well) √

Establishment of Toilets at least 30 m downstream of the

drinking water source.

Sealed Septic tanks (water tight)

Establishment of a test pit and regular water quality

monitoring

4

Sanitation (Toilets

and septage

disposal)

Establishment of Toilets at least 30 m downstream of the

drinking water source.

Separate Toilets for male and female √

Sealed Septic tanks (water tight) √

Location of disposal pits at least 300 m away from the

nearest residence

Proper septage management √

5. Construction work

camps, stockpile

Storage areas

Construction camp sites (Standard) √

Stockpiling Area ( Environmental friendly √

Disposal Areas ( managed ) √

Page 51: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

40 | P a g e

S.N.

Major Environmental

Impacts

Proposed Mitigation Measures

Status

Remarks

Yes No

Storage Area (stockpiling material cover ) areas, and disposal

areas

6.

Waste

Generation

Differentiate of Solid wastes into Organic & Inorganic Solid

Wastes

Recycle of Solid Wastes √

Disposal of solid waste ( Mechanism) √

7.

Source of

materials

Source materials ( sand, gravel, aggregates)

from approved quarry sites

Source materials ( sand, gravel, aggregates from approved

crusher sites

B: Construction Phase

a. Physical Environment

1

Topography

landforms, geology,

and soils and river

morphology and

hydrology

Coordinate with MoFE, DDC, and local authorities regarding

restrictions in quarrying from rivers

Quarry Sites Approved from GoN Crusher Sites Approved from

GoN

Consultation with district development committee on designated

disposal areas for spoil disposal

Prevention of entering of waste water into streams,

watercourses, or irrigation system

Ensure storm water flow to divert (shall not lead to inundation and

other nuisances in low lying areas )

Conduct All earthworks related works during dry season √

Monitor water quality according to EMP √

2.

Air Quality Arrest dust through frequent water spray √

Require trucks delivering aggregates and cement to have

tarpaulin cover

Limit speed of construction vehicles in access roads and worksites

to a maximum of 30 kph.

Use of vehicles complying with NVMES,

2069 enforcement, and green sticker standards and

Prohibition of open burning of solid waste. √

3.

Noise

Pollution

Construct speed bumps at settlement areas

Avoid use of pressure horn in the nearby settlement area and

construction sites

Erect no horn signs in settlement areas, health post, schools

and other public areas

Work during day time rather than night time √

Warning signs in construction sites √

Maintain sound levels not exceeding 80 decibels √

4.

Removal of

Aesthetics values

Preparation of debris disposal plan. √

Removal of all construction and demolition wastes on

a daily basis.

× Needs

improve

ment Coordination with District development office for beneficial uses

for excess excavated soils or immediately disposes to

designated areas.

All vehicles delivering fine materials to the site and carrying

debris for disposal covered to avoid spillage.

b: Biological Environment

1.

Biodiversity Damage to Forest (Tree Cutting )

×

Disturbance to wildlife

× Disturbance to Aquatic life

× Disturbance to Birds

× c: Socioeconomic Environment

Page 52: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

41 | P a g e

S.N.

Major Environmental

Impacts

Proposed Mitigation Measures

Status

Remarks

Yes No

1. Local people

hiring & Local

Market development

Priority hiring of labor force from communities in the

vicinity of the site

Purchasing of construction materials from the local market.

2.

Community

welfare

Consultation with local community/district development

committee/local administration to inform about the nature,

duration, likely effects of the construction work.

Relocation of existing infrastructure (such as water distribution

pipes, electricity pylons, etc.) before construction starts at the

subproject sites.

Obtained permission from respective local authority for the use of

water for construction.

Consultation with local community/district development

committee/local administration to inform about the nature,

duration, likely effects of the construction work.

3.

Community health

and safety

Consultation with district development committee on the

designated areas for stockpiling of soils, gravel, and other

construction materials.

Construction of temporary latrines for workers with a proper pit

to avoid contamination of water sources.

Workers were made aware of the following general

rules:

➢ no alcohol/drugs on site;

➢ prevent excessive noise;

➢ no fires permitted on site expect if

needed for the construction works

Other than pre-approved security staff, no workers shall be

permitted to live on the construction site.

Grievance/ Compliant remedial action mechanism fully

applied

Workers are provided with personal protective equipment

(reflectors /cloths; footwear, gloves, goggles, and masks)

Availability of first aid ( Medical insurance coverage for workers) √

The hygienic manner in work camps. √

Ensure

- uncontaminated water for drinking, cooking, and washing,

- clean eating areas where workers are not exposed to

hazardous or noxious substances;

Sanitation facilities are available at all times.

Provide H & S orientation training to all new workers. √

Mark and provide sign boards in chemical storage areas, material

storage areas & waste disposal areas.

d: Historical, Cultural, and Archaeological Characteristics

1.

Physical and

cultural heritage

Stop work immediately to allow further investigation if any

finds suspected.

No cultural heritage

areas found within

project area

e: Chemical Environment

1.

Mishandling of

chlorine

All disinfection chemicals require proper storage and handling

practices: ii) providing safe storage for chemicals; iii) ensure that

the person is hired, with knowledge of chlorine use for disinfection

process during operation iv)Ensure use of PPE while using

chemicals; v) Use of chlorine guideline as per WHO (Annex 6 )

Not

Applicable

C: Operation and Maintenance Activity

Page 53: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

42 | P a g e

S.

N. Performance Target

Activity carried during

reporting months

(Yes/ No)

i Quantity of treated water as set in the Performance Target meeting Nepal National

Drinking Water Quality Standard (NDWQS), 2005 is being delivered?

Yes

ii Frequency of water quality monitoring (as per Table 1, frequency of monitoring for

urban water supply system, NDWQS) is being met?

Yes

iii Residual pressure of water at ground level should be at least 5m positive head in 90%

of the cases of at least 10 different domestic meter points of the distribution network

randomly chosen for verification. The pressure will be measured twice a week by

Contractor in the presence of Employer’s/WUSC’s representative/s.

Is the above activity carried out by the Contractor?

Yes

iv Is residual chlorine 0.1 mg/l minimum maintained? Yes

v Are pumps, motors and generators run on the basis of the characteristic curves

submitted by the Contractor along with the offer and the actual duty conditions for

the month?

Yes

vi Take at least 2 samples each of raw water and treated water every day in the

presence of employer/co-employer or their designated representatives, analyse

them and report any deviation from Nepal standards and send weekly water quality

test reports (with summary of daily reports) to employer.

Are the above activities being done?

Yes

vii The Contractor shall train WUSC’s technical staff run the whole system during whole O & M period as ON-THE-JOB TRAINING (OJT).

Does the Contractor carry above activity during the reporting month?

WUSC staff is not

available.

viii Does Contractor maintain Logbooks for operation and maintenance of all the

equipment and services in a mutually agreed format?

Yes

Overall Compliance with EMP

Sub-Project

Name

EMP Part of

Contract

Documents

(Y/N)

EMP Being

Implemented

(Y/N)

Status of

implementation

(Excellent/Satisfactory

/Partially satisfactory

/Below Satisfactory)

Action Proposed

and Additional

Measures Required

Kathariya

Rautahat Water

Supply, and

Sanitation Sector

Project

Y Y

Satisfactory

Project entered

into 2nd phase

effective from June

30, 2019. The O &

M stages

environmental

issues addressing

by the Contractor

Public Consultation and Disclosure

62. The DSMC visited the project sites on a regular basis. As there were no major environmental issues during

the construction and O & M phase of the project no formal public consultations conducted based on

environmental issues. The informal public consultations have solved the minor environmental issues that

occurred during the construction phase of the project.

3.1.8. Birendranagar, Chitwan Water Supply and Sanitation Sector Project

63. As per defined norms and parameters in the Environmental Monitoring and Management plan of the

approved IEE of Birendranagar WSSSP of Chitwan District, field level supervision and monitoring have been

conducted with active involvement of monitoring team of the DSC (including CSE, EMP) and Environmental

Specialists. The contractor and workers were oriented/trained and made aware of their responsibility

towards Environmental Safeguarding issues during construction works, such as:

Page 54: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

43 | P a g e

• Adhering to the relevant adverse environmental impacts mitigation measures that are set out in the

EMP during carrying out construction activities of the sub-project; and

• Assessing the conditions of surrounding environmental conditions, status of adjacent cleared area

and other infrastructure, prior to construction commencement and upon completion of construction

and thereby fully reinstating the environment to at least their pre-project conditions.

64. The progress and compliance status of the project up to June 2020 are given below:

Progress Summary

Component of the Project Designed Capacity/

Numbers/Length

Built Capacity/

Numbers/Length

Status (In % completion

or delivery)

Overhead Tank 450 cu.m.-1 no 450 Cu.m-1no 100% completed and in

operation.

Deep Tube well- 4

Nos(Test,No-1 , No- 2&

No-3)

20-25 lps-4nos(including

one additional)

4 nos 100% completed

(including one

additional),

WUSC Building 1 no 1 no 100% completed

Generator House 1 no 1 no 100% completed

Boundary Wall 175.00 m 223.2m 100% completed

Pressure Filters (20.00 to

30.00 lps)

2 Nos 2Nos 100% Completed

PE Pipes 63.308km (50 to 160mm ) 64.27km(50 to 160mm) 100% supplied

DI pipes 5.091 km(150 to 300mm) 5.091 Km(150

to300mmDia.)

100% supplied

Dosing Pump 1 set,50 liters per hour - 100% completed

Fire Hydrants 4 sets 4 sets 100% completed

HH connections 1922 Nos 1575 Nos 81.94% completed

Laying and jointing of PE

pipes

68.02km (50 to 160 mm dia.

)

61.2 km 89.97 % completed,(

Pakhribas area deleted

due to disputes)

Laying and jointing of DI

Pipes

5.42km (150 to 300 mm

dia.)

4.72km 87.08% completed,

(Pakhribas area deleted

due to disputes)

Table 14: Birendranagar, Chitwan Water Supply and Sanitation Sector Project

S.N.

Major Environmental

Impacts

Proposed Mitigation Measures Status Remarks

Yes No

A: Pre-Construction Phase

1. Consents, permits,

clearances, no

objection certificate

(NOC) etc.

Obtain all of the necessary consents, permits, clearance, etc. √

Include in detailed design drawings and documents all conditions

and provisions if necessary

2.

Existing Utilities

(Spoil Disposal)

Collection & dumping of spoil materials at spoil disposal sites

Benching of ground slope √

Maintenance of Slope √

Construction of Toe Wall √

Construction of drainage √

Bioengineering works

3.

Drinking Water

Water Quality Test ( Deep Tube well & Shallow well) √

Establishment of Toilets at least 30 m downstream of

the drinking water source.

Sealed Septic tanks (water tight) √

Establishment of a test pit and regular water quality

monitoring

4

Sanitation (Toilets

and septage disposal)

Establishment of Toilets at least 30 m downstream of

the drinking water source

Separate Toilets for male and female √

Page 55: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

44 | P a g e

S.N.

Major Environmental

Impacts

Proposed Mitigation Measures Status Remarks

Yes No

Sealed Septic tanks (water tight) √

Location of disposal pits at least 300 m away from the nearest

residence

Proper septage management √

5. Construction work

camps, stockpile

areas, storage areas,

and disposal areas

Construction camp sites (Standard) √

Stockpiling Area ( Environmental friendly √

Disposal Areas ( managed ) √

Storage Area (stockpiling material cover ) √

6.

Waste

Generation

Differentiate of Solid wastes into Organic & Inorganic Solid

Wastes

Recycle of Solid Wastes √

Disposal of solid waste ( Mechanism) √

7.

Source of

materials

Source materials ( sand, gravel, aggregates) from approved

quarry sites

Source materials ( sand, gravel, aggregates from approved

crusher sites

B: Construction Phase

a. Physical Environment

1. Topography landforms,

geology, and soils

and river morphology

and hydrology

Coordinate with MoFE, DDC, and local authorities regarding

restrictions in quarrying from rivers

Quarry Sites Approved from GoN, Crusher Sites Approved from

GoN

Consultation with district development committee on

designated disposal areas for spoil disposal

Prevention of entering of waste water into streams,

watercourses, or irrigation system

Ensure storm water flow to divert (shall not lead to inundation

and other nuisances in low lying areas )

Conduct All earthworks related works during dry season

Monitor water quality according to EMP √

2.

Air Quality

Arrest dust through frequent water spray √

Require trucks delivering aggregates and cement to have

tarpaulin cover

Limit speed of construction vehicles in access roads and

worksites to a maximum of 30 kph.

Use of vehicles complying with NVMES, 2069 enforcement,

and green sticker standards and

Prohibition of open burning of solid waste √

3.

Noise

Pollution

Construct speed bumps at settlement areas

Avoid use of pressure horn in the nearby settlement area

and construction sites

Erect no horn signs in settlement areas, health post, schools and

other public areas

Work during day time rather than night time √

Warning signs in construction sites √

Maintain sound levels not exceeding 80 decibels √

4.

Removal of

Aesthetics values

Preparation of debris disposal plan √

Removal of all construction and demolition wastes on a daily

basis.

×

Needs

improvem

Coordination with District development office for beneficial

uses for excess excavated soils or immediately disposes to

designated areas.

All vehicles delivering fine materials to the site and carrying

debris for disposal covered to avoid spillage.

b: Biological Environment

Damage to Forest (Tree Cutting ) ×

Page 56: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

45 | P a g e

S.N.

Major Environmental

Impacts

Proposed Mitigation Measures Status Remarks

Yes No

1. Biodiversity Disturbance to wildlife ×

Disturbance to Aquatic life ×

Disturbance to Birds ×

c: Socioeconomic Environment

1.

Local people hiring &

local Market

development

Priority hiring of labor force from communities in the vicinity of

the site

Purchasing of construction materials from the local market.

2.

Community

welfare

Consultation with local community/district development

committee/local administration to inform about the nature,

duration, likely effects of the construction work.

Relocation of existing infrastructure (such as water distribution

pipes, electricity pylons, etc.) before construction starts at the

subproject sites.

Obtained permission from respective local authority for the

use of water for construction.

Consultation with local community/district development

committee/local administration to inform about the nature,

duration, likely effects of the construction work.

3.

Community health

and safety

Consultation with district development committee on the

designated areas for stockpiling of soils, gravel, and other

construction materials.

Construction of temporary latrines for workers with a proper pit

to avoid contamination of water sources.

Workers were made aware of the following general rules:

➢ no alcohol/drugs on site;

➢ prevent excessive noise;

➢ no fires permitted on site expect if needed for the

construction works

Other than pre-approved security staff, no workers shall be

permitted to live on the construction site.

Grievance/ Compliant remedial action mechanism fully

applied

Workers are provided with personal protective equipment

(reflectors /cloths; footwear, gloves, goggles, and masks)

Availability of first aid ( Medical insurance coverage for

workers)

The hygienic manner in work camps √

Ensure

- uncontaminated water for drinking, cooking, and

washing,

- clean eating areas where workers are not

exposed to hazardous or noxious substances;

Sanitation facilities are available at all times.

Provide H & S orientation training to all new workers. √

Mark and provide sign boards in chemical storage areas, material

storage areas & waste disposal areas.

d: Historical, Cultural, and Archaeological Characteristics

1.

Physical and

cultural heritage

Stop work immediately to allow further investigation if

any finds are suspected.

No cultural heritage

areas found within

project area

e: Chemical Environment

1.

Mishandling of

chlorine

All disinfection chemicals require proper storage and handling

practices: ii) providing safe storage for chemicals; iii) ensure that

the person is hired, with knowledge of chlorine use for

disinfection process during operation iv)Ensure use of PPE while

using chemicals; v) Use of chlorine guideline as per WHO

Not

Applicable

Page 57: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

46 | P a g e

C. Operation and Maintenance Activity

S.

N. Performance Target

Activity reporting

months (Yes/ No)

I Quantity of treated water as set in the Performance Target meeting Nepal National

Drinking Water Quality Standard (NDWQS), 2005 is being delivered?

Yes

Ii Frequency of water quality monitoring (as per Table 1, frequency of monitoring for urban

water supply system, NDWQS) is being met?

Yes

Iii Residual pressure of water at ground level should be at least 5m positive head in 90% of

the cases of at least 10 different domestic meter points of the distribution network

randomly chosen for verification. The pressure will be measured twice a week by

Contractor in the presence of Employer’s/WUSC’s representative/s. Is the above activity carried out by the Contractor?

Yes

Iv Is residual chlorine 0.1 mg/l minimum maintained? Yes

V Are pumps, motors and generators run on the basis of the characteristic curves submitted

by the Contractor along with the offer and the actual duty conditions for the month? Yes

Vi Take at least 2 samples each of raw water and treated water every day in the presence of

employer/co-employer or their designated representatives, analyse them and report any

deviation from Nepal standards and send weekly water quality test reports (with summary

of daily reports) to employer.

Are the above activities being done?

Yes

vii The Contractor shall train WUSC’s technical staff run the whole system during whole O & M period as ON-THE-JOB TRAINING (OJT).

Does the Contractor carry above activity during the reporting month?

Yes

viii Does Contractor maintain Logbooks for operation and maintenance of all the equipment

and services in a mutually agreed format? Yes

Overall Compliance with EMP

Sub-Project

Name

EMP Part of

Contract

Documents

(Y/N)

EMP Being

Implemented

(Y/N)

Status of Implementation

(Excellent/Satisfactory/

/Below Satisfactory)

Action Proposed and Additional

Measures Required

Birendranagar

Water Supply,

and Sanitation

Sector Project

Y

Y

Satisfactory

Continuation of proper

management of health and

sanitation conditions in the

camps; Most of physical works

are completed

Public Consultation and Disclosure

65. The DSMC visited the project sites on a regular basis. As there were no major environmental issues during

the construction phase of the project no formal public consultations were conducted based on

environmental issues. The informal public consultations have solved the minor environmental issues that

occurred during the construction phase of the project.

3.1.9. Bidur, Nuwakot Water Supply and Sanitation Sector Project

66. The approved IEE of Bidur WSSSP of Nuwakot District has determined the monitoring parameter schedule

and responsibility under section EMP. As per defined norms and parameters in the Environmental

Monitoring and Management plan, field level supervision and monitoring have been conducted with active

involvement of monitoring team of the DSC (including CSE, EMP) and Environmental Specialists. The

contractor and workers were oriented/trained and made aware of their responsibility towards

Environmental Safeguarding issues during construction works, such as:

• Adhering to the relevant adverse environmental impacts mitigation measures that are set out in the

EMP during carrying out construction activities of the sub-project; and

• Assessing the conditions of surrounding environmental conditions, status of adjacent cleared area

and other infrastructure, prior to construction commencement and upon completion of

construction and thereby fully reinstating the environment to at least their pre-project conditions.

67. The progress and compliance status of the projects up to June 2020 are presented below:

Page 58: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

47 | P a g e

Progress Summary

Intake Structure: • Clearance of debris deposited by flood during monsoon

Transmission Main: Laying of DI pipes & fittings will be continued at Titung-Tirtirebhir, Bhainse, and

Betrawoti location

PE/GI Pipelines: • Installation of DI / PE pipes &fittings in Battar and colony along the highway will

be continued

Treatment Plants: • Manage Drainage system of RSF with laterals

• Fitting, Fixing air pipe system in RSF

• Filling of filter media in RSF

• Fixing of Complete set of Agitator including all necessary accessories in Mix Tank

• Manage chemical system for Rapid mix tank

Reservoir: • Installation of water level indicator will be completed.

• Fixing of chlorination system in all reservoir tanks

HHs Connection: 3500 Completed out of 5425

EMP Compliance and

Protection related

works

• Fencing with barbed wire at Colony RVT will be completed

• Fencing with barbed wire at Existing Tank Bidur will be completed

• Construction of Valve Chambers at different location will be continued

• Commissioning the pipeline of Nalagaun system is completed

• Valve Chamber Construction at Nalagaun system is in progress

• Boundary Wall ongoing at 4 places- Divakar danda & office Building & Bidur

Existing Tank

Table 15 : Bidur, Nuwakot Water Supply and Sanitation Sector Project

S.N.

Major

Environmental

Impacts

Proposed Mitigation Measures

Status Remarks

Yes No

A: Pre-Construction Phase

1. Consents, permits,

clearances, no

objection certificate

(NOC) etc.

Obtain all of the necessary consents, permits, clearance, etc. √

Include in detailed design drawings and documents all conditions

and provisions if necessary

2.

Existing

Utilities

(Spoil Disposal)

Collection & dumping of spoil materials at spoil disposal sites √

Benching of ground slope √

Maintenance of Slope √

Construction of Toe Wall √

Construction of drainage √

Bioengineering works

3.

Drinking Water

Water Quality Test ( Deep Tube well & Shallow well) √

Establishment of Toilets at least 30 m downstream of

the drinking water source.

Sealed Septic tanks (water tight) √

Establishment of a test pit and regular water quality monitoring √

4

Sanitation (Toilets

and septage

disposal)

Establishment of Toilets at least 30 m downstream of

the drinking water source.

Separate Toilets for male and female √

Sealed Septic tanks (water tight) √

Location of disposal pits at least 300 m away from the nearest

residence

Proper septage management √

5. Construction work

camps, stockpile

areas, storage

areas, and

disposal areas

Construction camp sites (Standard) √

Stockpiling Area ( Environmental friendly √

Disposal Areas ( managed ) √

Storage Area (stockpiling material cover ) √

6.

Waste

Generation

Differentiate of Solid wastes into Organic & Inorganic Solid

Wastes

Recycle of Solid Wastes √

Page 59: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

48 | P a g e

S.N.

Major

Environmental

Impacts

Proposed Mitigation Measures

Status Remarks

Yes No

Disposal of solid waste ( Mechanism) √

7.

Source of

materials

Source materials ( sand, gravel, aggregates)

from approved quarry sites

Source materials ( sand, gravel, aggregates from approved

crusher sites

B: Construction Phase

1. Topography

landforms, geology,

and soils and river

morphology and

hydrology

Coordinate with MoFE, DDC, and local authorities regarding

restrictions in quarrying from rivers

Quarry Sites Approved from GoN, Crusher Sites Approved from

GoN

Consultation with district development committee on designated

disposal areas for spoil disposal

Prevention of entering of waste water into streams,

watercourses, or irrigation system

Ensure storm water flow to divert (shall not lead to inundation

and other nuisances in low lying areas )

Conduct All earthworks related works during dry season √

Monitor water quality according to EMP √

2.

Air Quality

Arrest dust through frequent water spray √

Require trucks delivering aggregates and cement to have

tarpaulin cover

Limit speed of construction vehicles in access roads and

worksites to a maximum of 30 kph.

Use of vehicles complying with NVMES, 2069 enforcement,

and green sticker standards and

Prohibition of open burning of solid waste. √

3.

Noise Pollution

Construct speed bumps at settlement areas √

Avoid use of pressure horn in the nearby settlement area

and construction sites

Erect no horn signs in settlement areas, health post, schools

and other public areas

Work during day time rather than night time √

Warning signs in construction sites √

Maintain sound levels not exceeding 80 decibels √

4.

Removal of

Aesthetics values

Preparation of debris disposal plan. √

Removal of all construction and demolition wastes on a daily

basis.

Coordination with District development office for beneficial uses

for excess excavated soils or immediately disposes to designated

areas.

All vehicles delivering fine materials to the site and carrying

debris for disposal covered to avoid spillage.

C: Biological Environment

1.

Biodiversity

Damage to Forest (Tree Cutting ) ×

Disturbance to wildlife ×

Disturbance to Aquatic life ×

Disturbance to Birds ×

D: Socioeconomic Environment

1.

Local people

hiring & Local

Market

development

Priority hiring of labor force from communities in the vicinity of

the site

Purchasing of construction materials from the local market. √

Page 60: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

49 | P a g e

S.N.

Major

Environmental

Impacts

Proposed Mitigation Measures

Status Remarks

Yes No

2.

Community

welfare

Consultation with local community/district development

committee/local administration to inform about the nature,

duration, likely effects of the construction work.

Relocation of existing infrastructure (such as water distribution

pipes, electricity pylons, etc.) before construction starts at the

subproject sites.

Obtained permission from respective local authority for the

use of water for construction.

Consultation with local community/district development

committee/local administration to inform about the nature,

duration, likely effects of the construction work.

3.

Community health

and safety

Consultation with district development committee on the

designated areas for stockpiling of soils, gravel, and other

construction materials.

Construction of temporary latrines for workers with a proper pit

to avoid contamination of water sources.

Workers were made aware of the following general rules:

➢ no alcohol/drugs on site;

➢ prevent excessive noise;

➢ no fires permitted on site expect if

needed for the construction works

Other than pre-approved security staff, no workers shall be

permitted to live on the construction site.

Grievance/ Compliant remedial action mechanism

fully applied

Workers are provided with personal protective equipment

(reflectors /cloths; footwear, gloves, goggles, and masks)

Availability of first aid ( Medical insurance coverage for

workers)

The hygienic manner in work camps. √

Ensure

- uncontaminated water for drinking, cooking, and washing,

- clean eating areas where workers are not exposed to

hazardous or noxious substances;

Sanitation facilities are available at all times.

Provide H & S orientation training to all new workers. √

Mark and provide sign boards in chemical storage areas, material

storage areas & waste disposal areas.

E: Historical, Cultural, and Archaeological Characteristics

1.

Physical and

cultural heritage

Stop work immediately to allow further investigation if

any finds are suspected.

No cultural heritage

areas found within

project area

F: Chemical Environment

1.

Mishandling of

chlorine

All disinfection chemicals require proper storage and handling

practices: ii) providing safe storage for chemicals; iii) ensure that

the person is hired, with knowledge of chlorine use for disinfection

process during operation iv)Ensure use of PPE while using

chemicals; v) Use of chlorine guideline as per WHO

Not

Applicable

Local Level Grievance Redress Committee (First Level)

Name/ Designation

Mr. Narayan Bahadur Khanal Chairman, Sub-committee of WUSC

Member (Social Safeguards Specialist, ERDSMC)

Page 61: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

50 | P a g e

Mr. Hari Sharan Gyawali, Member( CSE, ERDSMC)

Mr. Sundar Panday, Member (Social Mobilizer, ERDSMC)

Member (Representative from Contractor Office ) Representatives from Civil Society Representatives from Local Parties Representatives from ICG

Representatives from District Drinking Water Division Office etc Public Consultation and Disclosure

68. The DSMC visited the project sites on a regular basis. As there were no major environmental issues during

the construction phase of the project no formal public consultations were conducted based on

environmental issues. The informal public consultations have solved the minor environmental issues that

occurred during the construction phase of the project.

3.1.10. Ramnagar Mirchaiya Storm Drainage Project, Siraha

69. The IEE of Ramnager Mirchaiya Strom Draingae Project of Siraha District has been approved from MOWS.

As per defined norms and parameters in the Environmental Monitoring and Management plan, ongoing

field level supervision and monitoring. The physical works of the project comprises establishment of

contractor’s camp, supply of pipes, pipefittings and appurtenances, and pipe laying works etc.

70. The progress status of the project up to June 2020 is given below:

Progress Summary

Work target up to reporting month 50.00%

Financial progress up to the reporting month (inclusive mobilization advance) 9.74%

Total work target for next month including lagging 55.00%

Page 62: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

51 | P a g e

3.2. Compliance Status with Environmental Management and Monitoring Plans of Town Projects of

WRDSMCS

71. The Third Small Towns Water Supply and Sanitation Sector project of the Western Region covers 11

small towns of western region of Nepal. The contract for Consultants’ Services with these Third Small Towns Water Supply and Sanitation Sector Project (TSTWSSSP) has assigned to the joint venture of

Building Design Authority Pvt. Ltd. and Plush Engineers and Architects (P) Ltd (BDA-PEA JV) as Design,

Supervision, and Management Consultants (DSMC). This section illustrates progress and compliance

status with Environmental Management and Monitoring Plans of WRDSMC Town Projects from

January to June 2020 comprises implementation of EMP including physical progress, GRM,

Training/awareness programme and community level consultations. Among the 11 subprojects of

WRDSMC, Khalanga Sitalpati and Tikapur subprojects have been crossed DLP phase. Babiyachaur,

Chandrauta, Musikot and Suda sub-projects have been completed the O&M and running in DLP.

Tansariya, Abukhaireni, Dumre, Nirmalpokhari and Amargadi sub-projects have been running in

operation and maintenance phase. The Stage III Defect Liability of Period (DLP) of Khallanga-Sitalpati,

Salyan, Chandrauta, Kapilbastu and Tikapur, Kailali Town Water Supply & Sanitation Project has been

completed on 30 Dec. 2018, 4 Nov. 2019 and 20 Nov. 2019 respectively.

72. The Environmental Management and Monitoring Plans are being implemented with respect to the

guidelines defined in the Initial Environmental Examination (IEE) Report of 11 Western Town Water

Supply and Sanitation Project namely Abhukhaireni Tanahun, Kalanga Sitalpati Salyan, Musikot

Khalanga Rukum, Chandrauta Kapilbastu, Nirmalpokhari Kaski, Dumre Tanahun, Tikapur Kailali, Suda

Kanchanpur, Amargadi Dadeldhura, Tamsariya Nawalparasi and Babiyachaur Surkhet. With the

involvements of field team of the DSC (including CSE, EMP staff) and Environmental Specialist - field

level supervision and monitoring have been conducted. The contractor and workers were

oriented/trained and made aware of their responsibility towards Environmental Safeguarding issues

during construction works, such as:

• Adhering to the relevant adverse environmental impacts mitigation measures that are set out

in the EMP during carrying out construction activities of the sub-project - especially along

access roads to Intake and Generator House/guard house, and near the Horizontal Roughing

Filter site;

• Assessing the conditions of surrounding environmental conditions, status of adjacent cleared

area and other infrastructure, prior to construction commencement and upon completion of

construction and thereby fully reinstating the environment to at least their pre-project

conditions and;

• EMP breakdowns approved by TL-DSC and it is in process of implementation by the

contractor.

73. During the visit, the contractor’s personnel and site staff from the Consultant, were oriented/trained

and made aware of their responsibility towards Environmental Safeguarding issues during

construction works, such as :

• Drag out possible problems at the sites are identified earlier or at the time of excavation and

take spot decision to address the problems related to the users concern such as damaging

existing pipeline, irrigation canal, boundary wall and other structures.

• To solve these concerns, since the WUSC is more familiar with users and local areas, they

coordinate with the users to response and address the problems as soon as possible.

74. The detailed compliance status with EMP and monitoring from January to June 2020 of Western Town

Water Supply and Sanitation Projects namely Abhukhaireni Tanahun, Kalanga Sitalpati Salyan,

Musikot Khalanga Rukum, Chandrauta Kapilbastu, Nirmalpokhari Kaski, Dumre Tanahun, Suda

Kanchanpur and Amargadi TWSSSP Town Projects are presented below:

Page 63: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

52 | P a g e

3.2.1. Aabukaireni Tanahu Water Supply and Sanitation Project

75. The Environmental Management and Monitoring Plans have been implemented as per determined

monitoring parameter schedule and responsibility described under EMP section of approved IEE

report. Field level supervision and monitoring have been conducted with active involvement of

monitoring team of the DSC (including CSE, EMP) and Environmental Specialists. The contractor and

workers were oriented/trained and made aware of their responsibility towards Environmental

Safeguarding issues during construction works, such as:

• Adhering to the relevant adverse environmental impacts mitigation measures that are set out

in the EMP during carrying out construction activities of the sub-project – and during the end

phase of the construction phase which is followed by the post-construction phase of the

project; and

• Assessing the conditions of surrounding environmental conditions, status of adjacent cleared

area and other infrastructure, prior to construction commencement and upon completion of

construction and thereby fully reinstating the environment to at least their pre-project

conditions.

76. The progress summary and detailed compliance status with EMP and Monitoring Plans of the project

up to June 2020 are presented in Table 16.

Project Summary

Description of works as listed during

transferring the project to Stage II and

any other outstanding works

% Work completed and progress

during reporting month

Work

completed

(%)

HRF fencing work 100 Fencing work completed 100

SSF fencing & drainage work 100 Drainage work remained 98

Submersible pump installation

100 Testing and commissioning work

of power line remained

95

Sump well construction 100 Completed 100

Sludge Drying bed 100 Site development work to be

done

98

Generator and guard House

fencing

100 Fencing work completed 100

Delivery of tractor & tanker 100 Advance payment is done 50

Gabion works under VO 100 Ongoing 25

Table 16 : Detailed Compliance Status with EMP and Monitoring Plans of Abukhaireni Subprojects

S.N

.

Major

Environmental

Impacts

Proposed Mitigation Measures Status

Remarks

Yes No

A. Post-Construction Phase

Bio-Physical Aspects

1. Topography

landforms, and

Aesthetic values

The temporary facilities have been

properly decommissioned

√ Coordinated with

local authority

The landscape temporarily used by

the contractor have been reinstated

to its original state or better state

The quality of natural surface water

bodies is not degraded by the project

activities

Prohibition of open burning of solid

waste from decommissioning.

1.

Greenery promotion Greenery promoted in project sites so

as to improve the micro-climatic

condition/s

Page 64: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

53 | P a g e

S.N

.

Major

Environmental

Impacts

Proposed Mitigation Measures Status

Remarks

Yes No

Socio-economic Environment

1. Job opportunity for

the locals

Priority hiring of labor force from

communities in the vicinity of the

site.

√ O&M training

provided

On-the-Job training

provided Capacity building of the locals √

Ensure any damage to properties and

utilities will be restored or

compensated to pre work conditions.

3. O&M aspects O&M Manual prepared √ The training has

been provided and

manual has been

prepared

O&M training provided √

WSP prepared √

B. Summary of Environmental Monitoring in Aabukhaireni Project

SN Activities Progress Remarks

1 Protection works

• RCC wall at the generator and guard house for

landslide protection

Completed

• Gabion wall at generator house and guard house Completed

2 Greenery Management

Plantation and greenery

promotion

• Work in progress

• Gardening at WUSC building premises has been

planned

To be

completed

in next

quarter

3 Campsite/workforce management

(a) Records or workers

and Gender rights

• Records of workers has been maintained

• Women employment has been encouraged

(b) Child labour Totally prohibited and monitored regularly

(c) Provisions in campsite

(drinking water,

electricity, toilets, etc)

• Segregation bins placed for managing solid waste (1

set with Green and Red bins set)

• Provisions of water and sanitation maintained in

campsites

• First aid kits made available at all campsites and all

work-fronts

• Code of Conduct placed in all the campsites

(d) Proper sign boards,

notice boards

• Construction sites are bounded by fencing and flex

banners placed at all active working site to restrict

entry of children, older, disabled and other

unauthorized movement.

• Community safety has been considered with priority

along with OHS aspects in the project sites.

4 Occupational Health and Safety

(a) Records of accidents Minor cuts and wounds treated with first aid kits and

medical services from local private clinics

(b) Use of PPEs (helmets,

masks, gloves, boots,

goggles, etc.)

Helmets, boots, safety jackets and gloves available at

each ongoing sites

(c) Medical insurance Yes

(d) First Aid facility Available at most of the active sites

5 Environmental Grievance Records (if any)

(a) Records of grievances None in this quarter

Page 65: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

54 | P a g e

(b) Support provided

6 Environmental

monitoring

(a) Noise levels

(associated with

operation of heavy

equipment's and

vehicles) Method: Use of

mobile-app

Regular noise level monitoring is conducted in active

project sites

(b) Air quality levels

(associated with dust

levels due to vehicular

movement, spoil disposal

and stockpiling of

construction materials)

Method: Visual

inspection and feedback

from the locals

Completed as per EMP

Dust pollution is seen in the market area (however, this

effect is related more to local vehicles plying on

earthen and gravel roads of the project area)

7 Awareness, capacity

building

Regular on-site visits to aware the workforce on safety,

environmental sensitivities, and social harmony

C. Summary of EMP Implementation in Aabukhaireni Project

SN EMP works Status

1 Stabilization/protection works

• Fencing work at Horizontal Roughing Filter (HRF) site,

Slow Sand Filter (SSF), and Generator & guard house

completed

2 Rehabilitation and

reinstatement works

Civil works carried out in the RVT site

3 Greenery Promotion In progress

4 WQ Monitoring

Water quality testing has been conducted (RVT, Treatment

Plant and HH connections) to ensure drinking water quality to

be supplied

5 AQ Monitoring/Noise levels This has been completed

6 Public awareness/Information

• Hoarding boards, message boards/sign boards, 1 set of

dustbins placed at market place

• Health and sanitation awareness campaign conducted

on 13th January 2020

(Male - 12, Female - 18; Total 30 participants)

• Health and sanitation awareness campaign conducted

on 17th February 2020

(Male - 12, Female - 19; Total 31 participants)

• Health and sanitation awareness campaign conducted

on 15th March 2020

• Project team and locals were instructed to practice

preventive health guidelines to stay safe from CovID-19

infection

7 Crop compensation Provided in coordination with the WUSC, and local authority

Plan Ahead

8 Supervision and Monitoring of

additional activities

The contractor’s activities need to be supervised and monitored to ensure that there is no deterioration of

environment due to post-construction activities described

above in the Table 16.

Page 66: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

55 | P a g e

3.2.2. Chhap Nahala Dumre Tanahun Water Supply and Sanitation Project

77. The Environmental Management and Monitoring Plans have been implemented with respect to the

details defined in the Initial Environmental Examination (IEE) Report of the project. Field level

monitoring have been conducted with the involvements of field team of the DSC (including CSE, EMP

staff) and Environmental Specialist. The contractor and workers were oriented/trained and made

aware of their responsibility towards Environmental Safeguarding issues during construction works,

such as:

• Adhering to the relevant adverse environmental impacts mitigation measures that are set out

in the EMP during carrying out construction activities of the sub-project – and during the end

phase of the construction phase which is followed by the post-construction phase of the

project; and

• Assessing the conditions of surrounding environmental conditions, status of adjacent cleared

area and other infrastructure, prior to construction commencement and upon completion of

construction and thereby fully reinstating the environment to at least their pre-project

conditions.

78. The progress summary and detailed compliance status with EMP and Monitoring Plans of the project

up to June 2020 are presented in Table 17.

Summary of Progress

Description of works as listed during transferring the

project to Stage II and any other outstanding works

Work completed and progress

during reporting month

Work

completed

(%)

Repairing of Damage/leakage of Distribution Pipeline In progress as per needed 100%

Re-Installation of Float valve at BPT

6 nos of 100mm Float valve

installed (but not working)

100%

Improvement works at Bhukbhuke intake. In progress

Remaining work at Public toilet finishing completed 100%

Placement of identification pillar along pipeline

alignment

In progress 95%

Finishing work at Fire Hydrant One remaining is not required 100%

Overflow Connection to Playground area Completed 100%

HHs Connection /WUSC shall provide due list within 2

weeks

HHs Connection (911Nos.)

Completed according to the list of

WUSC

100%

Table 17 : Detailed Compliance Status with EMP and Monitoring Plan of Dumre Subprojects

S.N. Major Environmental

Impacts

Proposed Mitigation Measures Status

Remarks Yes No

A. Post-Construction Phase

Bio-Physical Aspects

1. Topography landforms,

and Aesthetic values

The temporary facilities have been

properly decommissioned

√ Coordinated

with local

authority The landscape temporarily used by the

contractor have been reinstated to its

original state or better state

The quality of natural surface water

bodies is not degraded by the project

activities

Prohibition of open burning of solid

waste from decommissioning.

Page 67: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

56 | P a g e

S.N. Major Environmental

Impacts

Proposed Mitigation Measures Status

Remarks Yes No

1.

Greenery promotion Greenery promoted in project sites so

as to improve the micro-climatic

condition/s

Socio-economic Environment

1. Job opportunity for the

locals

Priority hiring of labor force from

communities in the vicinity of the site

√ O&M training

provided

On-the-Job

training

provided

Capacity building of the locals √

2. Occupational Health and

Safety; community health

and safety

All disinfection chemicals require

proper storage and handling practices:

ii) providing safe storage for chemicals;

iii) ensure that the person is hired, with

knowledge of chlorine use for

disinfection process during operation

iv)Ensure use of PPE while using

chemicals; v) Use of chlorine guideline

as per WHO

√ Complied

Community

safety has been

considered

with priority

along with OHS

aspects in the

project sites

Ensure any damage to properties and

utilities will be restored or

compensated to pre work conditions

3. O&M aspects O&M Manual prepared √ The training

has been

provided and

manual has

been prepared

O&M training provided √

WSP prepared √

B. Major Safeguard Activities

Major Environmental Safeguard Activities Plan ahead

• Water quality tests have been regularly

carried out

• Project team and locals were instructed to

practice preventive health guidelines to stay

safe from CovID-19

• Semi formal public events conducted and

waste bins were provided to the locals, and

awareness activities conducted

The contractor’s activities need to be supervised and

monitored to ensure that there is no deterioration of

environment due to post-construction activities

C. Summary of EMP Implementation14

EMP works Status

Protection works Intake protection works conducted

Occupational Health & Safety PPEs provided, orientations and monitoring carried out

Waste management Awareness activities carried out, and Waste bins provided

Greenery Promotion Completed

WQ Monitoring Carried out

14 Most of the EMP works have been completed and the EMP budget utilized in 97.15%

Page 68: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

57 | P a g e

3.2.3. Nirmalpokhari Kaski Water Supply and Sanitation Project

79. The Environmental Management and Monitoring Plans have been implemented with respect to the

details defined in the Initial Environmental Examination (IEE) Report of the project. Field level

monitoring have been conducted with the involvements of field team of the DSC (including CSE, EMP

staff) and Environmental Specialist. The contractor and workers were oriented/trained and made

aware of their responsibility towards Environmental Safeguarding issues during construction works,

such as:

• Adhering to the relevant adverse environmental impacts mitigation measures that are set out

in the EMP during carrying out construction activities of the sub-project – and during the end

phase of the construction phase which is followed by the post-construction phase of the

project; and

• Assessing the conditions of surrounding environmental conditions, status of adjacent cleared

area and other infrastructure, prior to construction commencement and upon completion of

construction and thereby fully reinstating the environment to at least their pre-project

conditions.

80. The progress summary and detailed compliance status with EMP and Monitoring Plans of the project

up to June 2020 are presented in Table 18.

Physical Progress up to June 2020

SN

Description of works as listed during transferring the project to Stage II and

any other outstanding works %

Work completed

(%)

i House Connection Work 2% 98%

ii Fencing and access road on progress in Chisapani RVT 1% 99%

iii Supply of Pipe and Fittings continues 2% 98%

iv Remaining New Pipeline work continues 2% 98%

v Installation of Dosing Unit in Treatment Plant - 100%

vii. Operation and maintenance of transmission and distribution line and also

resolve the problem in House connection

- 100%

vii. Distribution Line Updated by addition of Valve chamber in different location

as per instruction

- 100%

vii. Supply and distribution of adequate quantity of potable water to the

required location

- 100%

Table 18: Detailed Compliance Status with EMP and Monitoring Plans of Nirmalpokhari Subprojects

S.N. Major

Environmental

Impacts

Proposed Mitigation Measures Status Remarks

Yes No

A. Post-Construction Phase

Bio-Physical Aspects

1. Topography

landforms, and

Aesthetic values

The temporary facilities have been properly

decommissioned

√ Coordinated

with local

authority The landscape temporarily used by the

contractor have been reinstated to its original

state or better state

The quality of natural surface water bodies is

not degraded by the project activities

Prohibition of open burning of solid waste

from decommissioning.

2.

Greenery promotion Greenery promoted in project sites so as to

improve the micro-climatic condition/s

Page 69: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

58 | P a g e

S.N. Major

Environmental

Impacts

Proposed Mitigation Measures Status Remarks

Yes No

Socio-economic Environment

1. Job opportunity for

the locals

Priority hiring of labor force from communities

in the vicinity of the site.

√ O&M

training

provided

On-the-Job

training

provided

Capacity building of the locals √

2. Occupational Health

and Safety;

community health

and safety

All disinfection chemicals require proper

storage and handling practices: ii) providing

safe storage for chemicals; iii) ensure that the

person is hired, with knowledge of chlorine

use for disinfection process during operation

iv)Ensure use of PPE while using chemicals; v)

Use of chlorine guideline as per WHO

√ Complied

Community

safety has

been

considered

with priority

along with

OHS aspects

in the project

sites.

Ensure any damage to properties and utilities

will be restored or compensated to pre work

conditions.

3. O&M aspects O&M Manual prepared √ The training

has been

provided and

manual has

been

prepared

O&M training provided √

WSP prepared √

B. EMP Implementation in Nirmalpokhari Project

1 Protection/Stabilizati

on works

Completed

2 Greenery Promotion Completed

3 Public awareness/

Information

Dissemination

This has been completed with wide range of activities like hygiene

promotion, and sanitation promotion in the community level and school

level WASH campaigning

C. Major Environmental Safeguards Activities

• Regular water quality monitoring has been carried out

• Project team and locals were instructed to practice preventive health guidelines to stay

safe from CovID-19 infection

• Semi formal public events conducted and waste bins were provided to the locals, and

awareness activities conducted

D Action Forwarded

• The contractor’s activities need to be supervised and monitored to ensure that there is no deterioration of environment due to post-construction activities

• O&M Plan will be prepared for the project

Meeting Interaction

Date of

Meeting

Organization/

Firm/ Person

Agenda Remarks

2020/05/30 WUSC/CSE/IC

G/ Contractor

Regular Progress

Meeting

Minutes of meetings are included in the

monthly progress reports of respective

months

Page 70: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

59 | P a g e

3.2.4. Tamsariya Nawalparasi Water Supply and Sanitation Project

81. The Environmental Management and Monitoring Plans have been implemented with respect to the

details defined in the Initial Environmental Examination (IEE) Report of the project. Field level

monitoring have been conducted with the involvements of field team of the DSC (including CSE, EMP

staff) and Environmental Specialist. The contractor and workers were oriented/trained and made

aware of their responsibility towards Environmental Safeguarding issues during construction works,

such as:

• Adhering to the relevant adverse environmental impacts mitigation measures that are set out

in the EMP during carrying out construction activities of the sub-project – and during the end

phase of the construction phase which is followed by the post-construction phase of the

project; and

• Assessing the conditions of surrounding environmental conditions, status of adjacent cleared

area and other infrastructure, prior to construction commencement and upon completion of

construction and thereby fully reinstating the environment to at least their pre-project

conditions.

82. The progress summary and detailed compliance status with EMP and Monitoring Plans of the project

up to June 2020 are presented in Table 19.

Physical Progress up to June 2020

SN Description of works as listed during transferring the

project to Stage II and any other outstanding works %

Work completed

and progress

Work

completed

(%)

i Remaining HHs connection (553 nos.) 100.00 On progress 55%

ii Repairing of Damage/Breakage/Leakage of Pipe Line 100.00 On progress 80%

iii Supply of remaining (a few) Lab. Equipment's /Tools

& Plants

100.00 On progress 75%

iv Supply and installation of Ladder from the top of

OHTs to inside of the tank including the gates at the

beginning point of all the staircases.

100.00 On progress 95%

v Remaining part of compound wall work at

Basantapur and Simreni sites (Site development

/Protection work).

100.00 On Progress 80%

vi Barbed wire fencing work at Public Toilet.

and Sludge Drying Bed.

100.00 On Progress 95%

vii Remaining part of EMP works and rectification on

painting works

100.00 On Progress 10%

viii Supply and installation of GSM based remote

operating system

100.00 Completed 100%

ix Any other works as per the mutual understanding 100.00 On Progress 70%

Page 71: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

60 | P a g e

Table 19 : Detailed Compliance Status with EMP and Monitoring Plans of Tamsariya Project

S.N. Major Environmental

Impacts

Proposed Mitigation Measures Status Remarks

Yes No

A. Post-Construction Phase

Bio-Physical Aspects

1. Topography landforms,

and Aesthetic values

The temporary facilities have been

properly decommissioned

√ Coordinated

with local

authority The landscape temporarily used by

the contractor have been reinstated

to its original state or better state

The quality of natural surface water

bodies is not degraded by the project

activities

Prohibition of open burning of solid

waste from decommissioning.

1.

Greenery promotion Greenery promoted in project sites

so as to improve the micro-climatic

condition/s

Socio-economic Environment

1. Job opportunity for the

locals

Priority hiring of labor force from

communities in the vicinity of the

site.

√ O&M training

provided

On-the-Job

training

provided Capacity building of the locals √

2. Occupational Health and

Safety; community health

and safety

All disinfection chemicals require

proper storage and handling

practices: ii) providing safe storage

for chemicals; iii) ensure that the

person is hired, with knowledge of

chlorine use for disinfection process

during operation iv)Ensure use of

PPE while using chemicals; v) Use of

chlorine guideline as per WHO

√ Complied

Community

safety has

been

considered

with priority

along with

OHS aspects in

the project

sites.

Ensure any damage to properties and

utilities will be restored or

compensated to pre work conditions.

3. O&M aspects O&M Manual prepared √ Training has

been provided

and manual has

been prepared

O&M training provided √

WSP prepared √

B. Major Safeguard Activities Actions Way Forward

• Environmental awareness and sanitation campaign is carried out in the

project area in coordination with the local stakeholders, primarily WUSC

• Protection work at Girbari khola for the safety was carried out at OHT at

Chulesi site

• Segregation bins placed for managing solid waste (3 sets with Green and

Red bins sets)

• Project team and locals were instructed to practice preventive health

guidelines to stay safe from CovID-19 infection

• Regular water quality monitoring has been carried out

The contractor’s activities need to be

supervised and

monitored to ensure

that there is no

deterioration of

environment due to

post-construction

activities

O&M Plan will be

prepared for the

project.

Page 72: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

61 | P a g e

Summary of Environmental EMP Implementation in Tamsariya Project

SN EMP works Status

1 Stabilization/protection works Retaining wall at Basantapur site has been completed

2 Greenery Promotion 500 saplings of Neem are planted including some Mango and

Dhupi plants

3 WQ Monitoring In progress

4 AQ Monitoring/Noise levels This has been completed

5 Public awareness/Information Hoarding boards, message boards/sign boards, 3 sets of

dustbins placed at market places

6 Social safeguards Combined events with GESI activities

Summary of Meeting and Interaction

Date of

Meeting

Organization/

Firm/ Person

Agenda Decision (in brief) Remarks

9

Chaitra,

2076

WUSC and

DSMC

Re-evaluation of

Water Tariff after

collecting the list of

new water users.

Request to TDF for the

Reevaluation of water tariff

including the list of additional

members of water user's

committee.

Minutes of

meetings are

included in the

monthly

progress

reports of

respective

months

9

Chaitra,

2076

WUSC and DSMC Request to

Contractor for the

repair of third party

damaged Pipe line

including Household

connections.

WUSC will pay the cost of

repairment after obtaining the

evaluation of such works by a

sub-committee consisting of

the technical representatives of

DSMC, Contractor and WUSC.

9

Chaitra,

2076

WUSC and DSMC Software

installation for

maintaining the

financial records

properly.

Whole sole authority was

delegated to the WUSC

Chairperson for the installation

of such software as per the

prevailing financial rules and

regulations of GON.

10 June,

2020

WUSC and WUSC

Staffs.

Start of collecting

the Water Tariff @

Rs. 150.00 per

month.

Agreed to collect the water

Tariff effective from 1st

Ashadh-2077 @ Rs. 150.00 per

household per month.

10 June,

2020

WUSC and WUSC

Staffs.

To install the

Software for the

effective running of

the project works.

Agreed to procure the Software

on the leadership of WUSC

chair person.

Page 73: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

62 | P a g e

3.2.5. Chandrauta Kapilvastu Water Supply and Sanitation Project

83. The Environmental Management and Monitoring Plans have been implemented with respect

to the details defined in the Initial Environmental Examination (IEE) Report of the project. Field

level monitoring have been conducted with the involvements of field team of the DSC (including

CSE, EMP staff) and Environmental Specialist. The contractor and workers were

oriented/trained and made aware of their responsibility towards Environmental Safeguarding

issues during construction works, such as:

• Adhering to the relevant adverse environmental impacts mitigation measures that are

set out in the EMP during carrying out construction activities of the sub-project – and

during the end phase of the construction phase which is followed by the post-

construction phase of the project; and

• Assessing the conditions of surrounding environmental conditions, status of adjacent

cleared area and other infrastructure, prior to construction commencement and upon

completion of construction and thereby fully reinstating the environment to at least

their pre-project conditions.

84. The progress summary and detailed compliance status with EMP and Monitoring Plans of the

project up to June 2020 are presented in Table 20.

Progress Summary

SN

Description of works as listed during

transferring the project to Stage II and any

other outstanding works

% Work completed and progress

during reporting month

Work

completed

(%)

i HHs Connection 100 1463 nos. of name list provided by

WUSC, out of 1500 and 1312 nos.

connection is done.

88.51%

ii Supply of Lab Equipment/ breakage 100 None 100%

iii Water Level Measuring Rod 100 None 0

iv Repairing of Road Crossing 100 Repaired 100%

Table 20 : Detailed Compliance Status of EMP and Monitoring of Chandrauta Subprojects

S.N

.

Major Environmental

Impacts

Proposed Mitigation Measures Status Remarks

Yes No

Post-Construction Phase

1. Topography landforms,

geology and soils and/or

river morphology and

hydrology

The decommissioning is carried out

maintaining the natural landscape

Any possible land reclamation is well carried

out under coordination with the

locals/WUSC

2. Environmental Pollution Regular monitoring of drinking water sources √ Settling

units are

placed to

trap

effluents

from water

treatment

units

Regular

monitoring

of sites is

being

carried out

Ensure no discharge of waste water or

effluents from WTP units directly into land or

water bodies

Standard DGs with low emissions are used √

Fuel quality is assured of standard quality

Prohibition of open burning of solid waste or

any residue.

Avoid use of pressure horn in the nearby

settlement area and construction sites

Warning signs placed in construction sites to

prohibit action causing pollution

Page 74: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

63 | P a g e

S.N

.

Major Environmental

Impacts

Proposed Mitigation Measures Status Remarks

Yes No

3. Community health and

safety

Safety signs and messages are placed to

aware people on safety aspects, and

possibility of pollution of water sources

√ Signboards

have been

placed with

messages on

safety, total

sanitation and

environmental

awareness

Unauthorized entry of people, especially

children, into the WSSP sites is regulated

4. Mishandling of chlorine All disinfection chemicals require proper

storage and handling practices: ii) providing

safe storage for chemicals; iii) ensure that

the person is hired, with knowledge of

chlorine use for disinfection process during

operation iv)Ensure use of PPE while using

chemicals; v) Chlorine Use Guideline

NA Being

complied

Summary of Environmental Status Monitoring in Chandrauta Project

SN Activities Progress Remarks

1 Protection works

Mixed Gravel laying on the Sub-base road

at New OHT and Existing OHT

Completed

Brick Work at New OHT Site Completed

2 Greenery Management

Plantation and greenery

promotion

Plantation of Endogenous tree, Teak wood,

around the boundary wall at New OHT

Ornamental, Seasonal Flower planted at

New OHT

To be

completed in

next quarter

3 Campsite/workforce management

(a) Records or workers and

Gender rights

Records of workers has been maintained

Women employment has been encouraged

(b) Child labour Totally prohibited and monitored regularly

(c) Provisions in campsite

(drinking water, electricity, toilets,

etc)

Provisions of water and sanitation

maintained in campsites

First aid kits made available at all campsites

and all work-fronts

(d) Proper sign boards, notice

boards

Construction sites are bounded by fencing

and flex banners are placed at all active

working site to restrict entry of children,

older, disabled and other unauthorized

movement.

Community safety has been considered

with priority along with OHS aspects in the

project sites.

4 Occupational Health and Safety

(a) Records of accidents Minor cuts and wounds treated with first

aid kits and medical services from local

private clinics

(b) Use of PPEs (helmets, masks,

gloves, boots, goggles, etc.)

Helmets, boots, safety jackets and gloves

available at each ongoing sites.

(c) Medical insurance Yes

(d) First Aid facility Available at most of the active sites

5 Environmental Grievance Records

(if any)

(a) Records of grievances None in this quarter

Page 75: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

64 | P a g e

(b) Support provided

6 Environmental monitoring

(a) Noise levels

(associated with operation of

heavy equipment's and vehicles)

Method: Use of mobile-app

Regular noise level monitoring is conducted

in active project sites

(b) Air quality levels

Not planned

by the field

team

7 Awareness, capacity building

Regular on-site visits to aware the

workforce on safety, environmental

sensitivities, and social harmony

SWM campaigns conducted

Hand Washing promoted

School WASH campaign has been supported

by the project

Major Environmental Safeguards Activities and Plan ahead

• Awareness and orientation works are being carried out

• OHS and community health & safety is being monitored

• Project team and locals were instructed to practice preventive health guidelines to stay safe from

CovID-19 infection

• Water quality tests are being carried out

• Water quality test/monitoring works carried out continuously

Plan Ahead

• The contractor’s activities need to be supervised and monitored to ensure that there is no deterioration of environment due to post-construction activities

• O&M Plan will be prepared for the project

EMP Compliance with Operation and Maintenance Activity

SN EMP works Status Remarks

1 Stabilization works

Stabilization works have been carried

out in the OHT sites (new OHT and

existing OHT)

2 Rehabilitation and reinstatement

works

Brick work at new OHT site has been

completed

3 Greenery Promotion Completed

4 WQ Monitoring This has been partially completed, and is

ongoing

5 AQ Monitoring/Noise levels

This has not been completed This sum could

be utilized in

other activities

as per demand of

the WUSC

6 Public awareness/Information

Completed with wide range of activities

like hygiene promotion, and sanitation

promotion in the community level along

with SWM campaigning

Page 76: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

65 | P a g e

3.2.6. Rukum Musikot Water Supply and Sanitation Project

85. The Environmental Management and Monitoring Plans have been implemented with respect

to the details defined in the Initial Environmental Examination (IEE) Report of the project. Field

level monitoring have been conducted with the involvements of field team of the DSC (including

CSE, EMP staff) and Environmental Specialist. The contractor and workers were

oriented/trained and made aware of their responsibility towards Environmental Safeguarding

issues during construction works, such as:

• Adhering to the relevant adverse environmental impacts mitigation measures that are

set out in the EMP during carrying out construction activities of the sub-project – and

during the end phase of the construction phase which is followed by the post-

construction phase of the project; and

• Assessing the conditions of surrounding environmental conditions, status of adjacent

cleared area and other infrastructure, prior to construction commencement and upon

completion of construction and thereby fully reinstating the environment to at least

their pre-project conditions.

86. The progress summary and detailed compliance status with EMP and Monitoring Plans of the

project up to June 2020 are presented in Table 21.

Progress during reporting month

Description of works as listed during transferring the project to

Stage II and any other outstanding works

Work completed and

progress during

reporting month

Work

completed

(%)

i Connection of Water meters-22 nos remained out of 1057 no 1057 Completed 98%

ii Environment Mitigation works at Office Building Compound Work on Progress

iii Finishing works of SSF-II, RVT-3 compound area and Public

Toilet at Serigaon.

100%

iv Construction of anchor blocks at various sites of Transmission

and Distribution line

100%

v Miscellaneous works ( Water level Indicator, PCC work for

pipeline)

Work on Progress

Table 21 : Detailed Compliance Status with EMP and Monitoring Plans of Rukum Subprojects

S.N

.

Major

Environmental

Impacts

Proposed Mitigation Measures Status Remarks

Yes No

Post-Construction Phase

1. Topography

landforms, geology

and soils and/or

river morphology

and hydrology

The decommissioning is carried out maintaining

the natural landscape

Any possible land reclamation is well carried out

under coordination with the locals/WUSC

2. Environmental

Pollution

Regular monitoring of drinking water sources √ Settling units

are placed to

trap effluents

from water

treatment

units

Regular

monitoring of

sites is being

carried out

Ensure no discharge of waste water or effluents

from WTP units directly into land or water bodies

Standard DGs with low emissions are used √

Fuel quality is assured of standard quality

Prohibition of open burning of solid waste or any

residue.

Avoid use of pressure horn in the nearby

settlement area and construction sites

Warning signs placed in construction sites to

prohibit action causing pollution

Page 77: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

66 | P a g e

S.N

.

Major

Environmental

Impacts

Proposed Mitigation Measures Status Remarks

Yes No

3. Community health

and safety

Safety signs and messages are placed to aware

people on safety aspects, and possibility of

pollution of water sources

√ Signboard's have

been placed with

messages on

safety, total

sanitation and

environmental

awareness

Unauthorized entry of people, especially children,

into the WSSP sites is regulated

4. Mishandling of

chlorine

All disinfection chemicals require proper storage

and handling practices: ii) providing safe storage

for chemicals; iii) ensure that the person is hired,

with knowledge of chlorine use for disinfection

process during operation iv)Ensure use of PPE

while using chemicals; v) Chlorine Use Guideline

NA

for

no

w

Being complied

EMP Compliance with Operation and Maintenance Activity

S N Performance Target

Activity carried

during reporting

months (Yes/ No)

i Quantity of treated water as set in the Performance Target meeting Nepal

National Drinking Water Quality Standard (NDWQS), 2005 is being delivered?

Yes

ii Frequency of water quality monitoring (as per Table 1, frequency of monitoring

for urban water supply system, NDWQS) is being met?

Yes

iii Residual pressure of water at ground level should be at least 5m positive head in

90% of the cases of at least 10 different domestic meter points of the distribution

network randomly chosen for verification. The pressure will be measured twice a

week by Contractor in the presence of Employer’s/WUSC’s representative/s. Is the above activity carried out by the Contractor?

Yes

iv Is residual chlorine 0.1 mg/l minimum maintained? Yes

v Are pumps, motors and generators run on the basis of the characteristic curves

submitted by the Contractor along with the offer and the actual duty conditions

for the month?

vi Take at least 2 samples each of raw water and treated water every day in the

presence of employer/co-employer or their designated representatives

Yes

analyse them and report any deviation from Nepal standards and send weekly

water quality test reports (with summary of daily reports) to employer.

Are the above activities being done?

vii The Contractor shall train WUSC’s technical staff run the whole system during whole O & M period as ON-THEJOB TRAINING (OJT).

Does the Contractor carry above activity during the reporting month?

No

viii Does Contractor maintain Logbooks for operation and maintenance of all the

equipment and services in a mutually agreed format?

Yes

Page 78: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

67 | P a g e

3.2.7. Babiyachaur Surkhet Water Supply and Sanitation Project

87. The Environmental Management and Monitoring Plans have been implemented with respect

to the details defined in the Initial Environmental Examination (IEE) Report of the project. Field

level monitoring have been conducted with the involvements of field team of the DSC (including

CSE, EMP staff) and Environmental Specialist. The contractor and workers were

oriented/trained and made aware of their responsibility towards Environmental Safeguarding

issues during construction works, such as:

• Adhering to the relevant adverse environmental impacts mitigation measures that are

set out in the EMP during carrying out construction activities of the sub-project – and

during the end phase of the construction phase which is followed by the post-

construction phase of the project; and

• Assessing the conditions of surrounding environmental conditions, status of adjacent

cleared area and other infrastructure, prior to construction commencement and upon

completion of construction and thereby fully reinstating the environment to at least

their pre-project conditions.

88. The progress summary and detailed compliance status with EMP and Monitoring Plans of the

project up to June 2020 are presented in Table 22.

Progress during reporting month

Description of works as listed during transferring the project to Stage II and any other

outstanding works

Work

Completed

(%)

House hold Connections and Water meters- 120 nos (Included in VO-01/ out of 170 no) 100

Office Building 1st Floor Door/window work, Electrical work, Painting, Finishing work etc 100

Permanently Establishment of laboratory in 1st Floor of Office Building 100

700m barbed weir fencing from RVT 200 cum to 100 cum Existing RVT (Requested by

WUSC and Included in VO-1).

100

Installation of control Gate in Sludge drying Bed. 100

Cover the Sedimentation tank at Road side by Transparent Corrugated Sheet 20 m. 100

Finishing works ,Sanitation work in Guard House 100

Minor works at Intake III( Ghattakhola) 100

Table 22 ; Detailed Compliance Status of EMP and Monitoring of Babayachaur Subproject

S.N. Major Environmental

Impacts

Proposed Mitigation Measures Status

Remarks Yes No

Post-Construction Phase

1. Topography landforms,

geology and soils and/or

river morphology and

hydrology

The decommissioning is carried out maintaining

the natural landscape

Any possible land reclamation is well carried

out under coordination with the locals/WUSC

2. Environmental Pollution Regular monitoring of drinking water sources √ Settling

units are

placed to

trap

effluents

from water

treatment

units

Regular

monitoring

of sites is

Ensure no discharge of waste water or effluents

from WTP units directly into land or water

bodies

Standard DGs with low emissions are used √

Fuel quality is assured of standard quality

Prohibition of open burning of solid waste or

any residue.

Avoid use of pressure horn in the nearby

settlement area and construction sites

Warning signs placed in construction sites to

prohibit action causing pollution

Page 79: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

68 | P a g e

S.N. Major Environmental

Impacts

Proposed Mitigation Measures Status

Remarks Yes No

being

carried out

3. Community health and

safety

Safety signs and messages are placed to aware

people on safety aspects, and possibility of

pollution of water sources

√ Signboards

have been

placed with

messages on

safety, total

sanitation

and

environment

al awareness

Unauthorized entry of people, especially

children, into the WSSP sites is regulated

4. Mishandling of chlorine All disinfection chemicals require proper

storage and handling practices: ii) providing

safe storage for chemicals; iii) ensure that the

person is hired, with knowledge of chlorine use

for disinfection process during operation

iv)Ensure use of PPE while using chemicals; v)

Chlorine Use Guideline

NA Being

complied

Environmental Monitoring in Babiyachour Project

SN Activities Progress Remarks

1 Water quality testing It is being carried out daily/monthly basis, and

the water quality is potable

3 Campsite/workforce management

Decommissioning of campsites

The campsites have been dismantled, and the

sites have been restored to the original site,

and landscape maintained

Coordinated

with WUSC

Sign boards, notice boards The previously placed message boards, and

messages on environmental awareness and

sanitation aspects are still in-place

Coordinated

with WUSC

4 Occupational Health and Safety

Storage of chlorine This has been safely placed in the guard house

Unauthorized entry has been controlled

Trainings to the operators 2 operators are working since mid-August 2018

They have been trained DSMC team

OHS aspects been made well aware to them

5 Other aspects

Water Safety Plan (WSP) Preliminary WSP training has been conducted

Summary of EMP Implementation in Babiyachaur Project

SN EMP works Status

1 Stabilization/protection works Protection works completed at Intake/existing intake

protection, sedimentation tank sites

2 Rehabilitation and reinstatement

works

Reinstatement of access roads

3 Greenery Promotion Plantation carried out in the intake site, Greenery

promotion conducted in the Water Treatment site as well

4 WQ Monitoring Completed

5 AQ Monitoring/Noise levels Completed

6 Public awareness/Information Hoarding boards, message boards/sign boards, 2 sets of

dustbins placed at market places

7 Crop compensation Provided in coordination with the WUSC, and local

authority

8 Social safeguards completed

Page 80: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

69 | P a g e

3.2.8. Suda Kanchanpur Water Supply and Sanitation Project

89. The Environmental Management and Monitoring Plans have been implemented with respect

to the details defined in the Initial Environmental Examination (IEE) Report of the project. Field

level monitoring have been conducted with the involvements of field team of the DSC (including

CSE, EMP staff) and Environmental Specialist. The contractor and workers were

oriented/trained and made aware of their responsibility towards Environmental Safeguarding

issues during construction works, such as:

• Adhering to the relevant adverse environmental impacts mitigation measures that are

set out in the EMP during carrying out construction activities of the sub-project – and

during the end phase of the construction phase which is followed by the post-

construction phase of the project; and

• Assessing the conditions of surrounding environmental conditions, status of adjacent

cleared area and other infrastructure, prior to construction commencement and upon

completion of construction and thereby fully reinstating the environment to at least

their pre-project conditions.

90. The progress summary and detailed compliance status with EMP and Monitoring Plans of the

project up to June 2020 are presented in Table 23.

Physical Progress up to June 2020

SN Description of works as listed

during transferring the project to

Stage II and any other outstanding

works

% Work completed and progress during

reporting month

Work

completed

(%)

1. Construction work of public toilet

as per specification is completed

100% Handover to municipality

(Betkot)

2

2. Remaining Household

Connection and Earth works

99.47% 1842 completed out of 1895 house hold

list provided by WUSC further

connection work

is still running

99.47%

3. Brass tap and GI stand connection

work

89.70% 1570 HH connection work completed

further connection work is still running

89.70%

4. Sludge drying bed 0% Area not provided by WUSC but we are

in Discussion

0%

5. Environmental

work

mitigation 75% Carpet grass placement work

completed further work as per break

down are still running

75%

Table 23 ; Detailed Compliance Status of EMP and Monitoring of Suda Kanchanpur Subproject

S.N. Major Environmental

Impacts

Proposed Mitigation Measures Status

Remarks Yes No

A. Post-Construction Phase

Bio-Physical Aspects

1. Topography

landforms, and

Aesthetic values

The temporary facilities have been

properly decommissioned

√ Coordinated

with local

authority The landscape temporarily used by the

contractor have been reinstated to its

original state or better state

The quality of natural surface water

bodies is not degraded by the project

activities

Prohibition of open burning of solid

waste from decommissioning.

Page 81: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

70 | P a g e

S.N. Major Environmental

Impacts

Proposed Mitigation Measures Status

Remarks Yes No

1.

Greenery promotion Greenery promoted in project sites so as

to improve the micro-climatic condition/s

Socio-economic Environment

1. Job opportunity for

the locals

Priority hiring of labor force from

communities in the vicinity of the site.

√ O&M training

provided

On-the-Job

training

provided

Capacity building of the locals √

2. Occupational Health

and Safety;

community health

and safety

All disinfection chemicals require proper

storage and handling practices: ii)

providing safe storage for chemicals; iii)

ensure that the person is hired, with

knowledge of chlorine use for

disinfection process during operation

iv)Ensure use of PPE while using

chemicals; v) Use of chlorine guideline as

per WHO

√ Complied

Community

safety has been

considered with

priority along

with OHS

aspects in the

project sites.

Ensure any damage to properties and

utilities will be restored or compensated

to pre work conditions.

3. O&M aspects O&M Manual prepared √ The training has

been provided

and manual has

been prepared

O&M training provided √

WSP prepared √

Major Environmental Safeguard Activities and Action Way Forward

• Awareness and orientation works are being carried out

• Monitoring of worksite safety is being carried out regularly

• Project team and locals were instructed to practice preventive health guidelines to stay safe from

CovID-19 infection

• Water quality test/monitoring works carried out continuously

Action Way Forward

• The contractor’s activities need to be supervised and monitored to ensure that there is no

deterioration of environment due to post-construction activities

• O&M Plan will be prepared for the project.

EMP Implementation

Environmental mitigation and protection works implemented up to the reporting months as presented

below:

SN EMP works Status

1 Stabilization/protection works Protection works have been completed

2 Rehabilitation and reinstatement

works

Civil works carried out

3 Greenery Promotion Completed

4 WQ Monitoring This has been partially completed, and is ongoing

5 AQ Monitoring/Noise levels This has been completed

6 Public awareness/Information Hoarding boards, message boards/sign boards placed

7 Crop compensation Provided in coordination with the WUSC, and local

authority

8 Social safeguards This is under progress

Page 82: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

71 | P a g e

3.2.9. Amargadi Dadeldhura Water Supply and Sanitation Project

91. The Environmental Management and Monitoring Plans have been implemented with respect

to the details defined in the Initial Environmental Examination (IEE) Report of the project. Field

level monitoring have been conducted with the involvements of field team of the DSC (including

CSE, EMP staff) and Environmental Specialist. The contractor and workers were

oriented/trained and made aware of their responsibility towards Environmental Safeguarding

issues during construction works, such as:

• Adhering to the relevant adverse environmental impacts mitigation measures that are

set out in the EMP during carrying out construction activities of the sub-project – and

during the end phase of the construction phase which is followed by the post-

construction phase of the project; and

• Assessing the conditions of surrounding environmental conditions, status of adjacent

cleared area and other infrastructure, prior to construction commencement and upon

completion of construction and thereby fully reinstating the environment to at least

their pre-project conditions.

92. The progress summary and detailed compliance status with EMP and Monitoring Plans of the

project up to June 2020 are presented in Table 24.

Physical Progress up to June 2020

Description of works as listed during transferring the

project to Stage II and any other

outstanding works

%

Work completed and

progress

Work completed

(%)

143 Nos Household Connections (Included in upcoming

VO-02/ Out of 1500 Nos.

100% 9 Nos of house connected

at this month.

6.29%

Boundary(chain link) Works: Office Building and

Reservoir Tank Area, Sedimentation Tank and Brick

Mosaic Tile laying in Office Building Terrace

100% None this month 0%

Permanently Establishment of Laboratory in Office

Building.

100% Completely Establish

Laboratory.

100%

Finishing Works ,Door and Window

Installation, Sanitation Work in Guard House

100% Sanitation Work

Completed

4.25%

Air Valve and Washouts Valve , Chamber, in Lamasinge

(2 AV) ,Matare (1 WO) And Anarbe Site (3 WO) and

Thrust Block Works in Transmission Line

100% None this month 0%

8 Nos. of Fire Hydrant Installation

100% 1 one of fire hydrant

installation completed.

12.5%

Barbed Fencing Work and Painting in Public Toilet 100% Painting work completed 99%

Black Top Work in Road Crossing 0% None this month 0%

Table 24 : Detailed Compliance with EMP and Monitoring of Amargadi Subproject

SN Major Environmental

Impacts

Proposed Mitigation Measures Status

Remarks Yes No

A. Pre-Construction Phase

1. Consents, permits,

clearances, no

objection certificate

(NOC), etc.

Obtain all of the necessary consents, permits, clearance

etc.

Include in detailed design drawings and documents all

conditions and provisions if necessary

2. Existing Utilities

(Spoil Disposal)

Collection & dumping of spoil materials at spoil disposal

sites

Benching of ground slope √

Maintenance of Slope √

Construction of Toe Wall ×

Construction of drainage √

Page 83: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

72 | P a g e

SN Major Environmental

Impacts

Proposed Mitigation Measures Status

Remarks Yes No

Bioengineering works ×

3. Drinking Water Water Quality Test

(Deep Tube well & Shallow well)

Establishment of Toilets at least 30 m downstream of the

drinking water source.

Sealed Septic tanks (water tight) √

Establishment of a test pit and regular water quality

monitoring

4. Sanitation (Toilets and

septage disposal)

Establishment of Toilets at least 30 m downstream of the

drinking water source.

Separate Toilets for male and female √

Sealed Septic tanks (water tight) √

Location of disposal pits at least 300 m away from the

nearest residence

Proper septage management √

5. Construction work

camps, stockpile areas,

storage areas, and

disposal areas

Construction camp sites (Standard) √

Stockpiling Area

( Environmental friendly)

Disposal Areas ( managed ) √

Storage Area (stockpiling material cover ) √

6. Waste Generation Differentiate of Solid wastes into Organic & Inorganic Solid

Wastes

Recycle of Solid wastes ×

Disposal of solid waste ( Mechanism) ×

7. Source of materials Source materials ( sand, gravel, aggregates) from approved

quarry sites

Source materials ( sand, gravel, aggregates from approved

crusher sites

B. Construction Phase

a. Physical Environment

1. Topography landforms,

geology and soils

and/or river

morphology and

hydrology

Coordinate with MoPE, DCC, and local authorities

regarding restrictions in quarrying from rivers

Quarry Sites Approved from GoN

Crusher Sites Approved from GoN

Consultation with district development committee on

designated disposal areas for spoil disposal

Prevention of entering of waste water into streams,

watercourses, or irrigation system

Ensure storm water flow to divert (shall not lead to

inundation and other nuisances in low lying areas )

Conduct All earthworks related works during dry season √

Monitor water quality according to EMP √

2. Air Quality Arrest dust through frequent water spray √

Require trucks delivering aggregates and cement to have

tarpaulin cover

Limit speed of construction vehicles in access roads and

worksites to maximum of 30 kph.

Use of vehicles complying with NVMES, 2069 enforcement

and green sticker standards and

Prohibition of open burning of solid waste. √

3. Noise Pollution Construct speed bumps at settlement areas × Placed sign

boards with

instruction

of no horn

in sensitive

places

Avoid use of pressure horn in the nearby settlement area

and construction sites

Erect no horn signs in settlement areas, health post,

schools and other public areas

Work during day time rather than right time √

Warning signs in construction sites √

Maintain sound levels not exceeding 80 decibels √

Page 84: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

73 | P a g e

SN Major Environmental

Impacts

Proposed Mitigation Measures Status

Remarks Yes No

4

.

Removal of Aesthetics

values

Preparation of debris disposal plan. √

Removal of all construction and demolition wastes on a

daily basis.

Coordination with district development office for

beneficial uses for excess excavated soils or immediately

disposes to designated areas.

All vehicles delivering fine materials to the site and

carrying debris for disposal shall be covered to avoid

spillage.

b. Biological Environment

1.

Biodiversity Damage to forest (Tree Cutting ) ×

Disturbance to wild life ×

Disturbance to Aquatic life ×

Disturbance to Birds ×

c. Socio-economic Environment

1. Local people hiring &

Local Market

development

Priority hiring of labor force from communities in the

vicinity of the site.

Purchasing of construction materials from local market. √

2. Community welfare Consult with local community/district development

committee/local administration to inform about the

nature, duration, likely effects of the construction work.

Existing infrastructure (such as water distribution pipes,

electricity pylons, etc.) shall be relocated before

construction starts at the sub project sites.

Prior permission shall be obtained from respective local

authority for use of water for construction. Use of water

for construction works shall not disturb local water users.

Ensure any damage to properties and utilities will be

restored or compensated to pre work conditions.

NA

3. Community health and

safety

& Occupational Health

and Safety

Consult with district development committee on the

designated areas for stockpiling of soils, gravel, and other

construction materials.

Signboards

have been

placed with

messages/c

ode of

conduct to

be followed

by the

workforce

PPEs were

provided

and

monitoring

was

focused at

Matare

WTP sites

and Anarbe

WTP sites

Construction of temporary latrines for workers with proper

pit to avoid contamination of water sources.

Workers need to be made aware of the following general

rules:

• no alcohol/drugs on site;

• prevent excessive noise;

• no fires permitted on site expect if needed for the

construction works

Encroaching/violating on private/commercial properties

adjoining the site is forbidden

Other than pre-approved security staff, no workers shall be

permitted to live on the construction site.

The contractor shall immediately take the necessary

remedial action on any complaint/grievance received by

him and forward the details of the grievance along with

the action taken to the PIU within 48 hours of receipt of

such complaint/grievance.

Workers are provided with personal protective equipment

(reflectors /cloths; footwear, gloves, goggles and masks)

Availability of first aid

( Medical insurance coverage for workers)

Hygienic manner in work camps. √

Ensure

- uncontaminated water for drinking, cooking and

washing,

Page 85: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

74 | P a g e

SN Major Environmental

Impacts

Proposed Mitigation Measures Status

Remarks Yes No

- clean eating areas where workers are not exposed to

hazardous or noxious substances;

Sanitation facilities are available at all times.

Provide H&S orientation training to all new workers. √

Mark and provide sign boards in chemical storage areas,

material storage areas & waste disposal areas.

Disallow worker exposure to noise level greater than 85

dBA for duration of more than 8 hours per day without

hearing protection. The use of hearing protection shall be

enforced actively.

d. Historical, Cultural, and Archaeological Characteristics

1. Physical and cultural

heritage

Stop work immediately to allow further investigation if any

finds are suspected.

NA

e. Chemical Environment

1. Mishandling of chlorine All disinfection chemicals require proper storage and

handling practices: ii) providing safe storage for chemicals;

iii) ensure that the person is hired, with knowledge of

chlorine use for disinfection process during operation

iv)Ensure use of PPE while using chemicals; v) Use of

chlorine guideline as per WHO

F. Status of EMP Implementation

S

N EMP works

Status

1 Stabilization/protection works All works have been completed. Gabion wall protection

placed against landslide at WUSC office building site.

2 Rehabilitation and reinstatement works Not yet utilized

3 Greenery Promotion The plantation works have been started; around 15%

completed

4 WQ Monitoring It is yet to be conducted

5 AQ Monitoring/Noise levels Completed

6 Public awareness/Information Hoarding boards, message boards/sign boards, 2 sets of

dustbins placed at public places in Amargadhi

7 Compensation of crops Not yet utilized

8 Social safeguards Under preparation

The DSMC team will coordinate and facilitate for process of WSP and preparation of Operation &

Maintenance Manual for the sub-project. Required trainings will also be provided for the WUSC members

and concerned locals.

Major Environmental Concerns, their Remedial Actions, and Plan Ahead

• Revetment wall for slope stability and protection in the WUSC building site has been completed

• Interaction with the labors of office building protection wall site was conducted regarding the social

and the use of PPEs.

• Interaction with the local people at Buspark area and discuss about the social and environmental

issues they have faced during the construction phase of the project.

• Active site of WTP sites, Office building protection wall construction site, khatal khola area and PE

pipe laying sites were regularly monitored during this period.

• In average around 10 skilled workers, 25 unskilled workers and 40 mules were used each month in

the construction sites till April 2020.

• Fencing works completed in WTP sites

• Occupational Health and Safety aspects were given priority. Personal Protective Equipment's (PPEs)

were provided by contractor to the labourers. Regular monitoring carried out to encourage the use

of PPEs. It was observed that around 80% of the workers used the PPEs provided to them.

• Local people have been employed and no child labour was employed.

• Code of Conduct implemented for the workers at the campsites and work-fronts.

Page 86: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

75 | P a g e

• Project team and locals were instructed to practice preventive health guidelines to stay safe from

CovID-19 infection. A formal meeting on this was held on 18th May 2020.

• Overall no major conflict with the community has been observed. A cordial relation has been

maintained with the local community.

Additional Actions Planned

• Continuation of more of awareness programs will be conducted in the communities

• High caution regarding practicing of preventive health measures will be taken during O&M phase as

well so as to avoid any viral infections, specially under the context of present CovID-19 disease

• A joint monitoring for ensuring that the project works are complete, and monitoring of any

safeguards concerns have been planned for next quarter

Meeting and Interaction

Date of

Meeting

Organization/ Firm/

Person

Agenda Decision (in brief) Remarks

12-May-

2020

WUSC committee,

Consultant and

contractor

• First phase

completion

meeting.

• Vo-2.

• Recommendation second

phase.

• Recommendation vo-2.

Minutes of

meetings are

included in the

monthly

progress reports

of

respective

months

2020-06-

09

PMO Representative,

RPMO, consultant

Team, Contractor

Team, WUSC Team,

TDF Team

Stage transfer

for Stage 1st

to stage 2nd

All the parties agree under taken

the stage ii, O&M

responsibilities as per contract

document, and recommend the

same to PMO/

RPMO /DSMC.

2020 -05-

12

WUSC, Consultant and

Contractor

Transfer to

Stage 2nd

Recommend to RPMO for

Transferring project to second

stage

Grievance Redress Mechanism

Grievance Redress Committee (GRC) formation date: August 13, 2017

Composition of GRC

I I. Chairperson : Bisweswar Prasad Ojha (Chief of Amargadhi Municipality)

II. Secretary : Rabindra K. C. (President, WUSC)

III. Member : Preeti Ojha (RPMO)

IV. Member : Madhav Prasad Joshi (BDA-PEAJV)

V. Member : Hira Bhandari (Kalika Construction Company)

VI. Member : Ramesh Prasad Joshi (coordinator, public society)

Page 87: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

76 | P a g e

4. MONITORING OF ENVIRONMENTAL IMPACTS ON PROJECTS SURROUNDINGS

93. Monitoring of environmental impacts and mitigation measures has been carried out concerning the

magnitude, extent, and duration of the impacts and effectiveness of implemented mitigation

measures. Comprehensive environmental monitoring parameters includes ambient air quality

monitoring, water quality & noise monitoring of operating machinery, campsite drinking water

facility, waste disposal and discharge management, health and safety issue, conservation of physical

cultural resources, consultation and community participation under the supervision of the

consultant’s Environmental Specialist. Environmental monitors of respective towns of Bidur,

Amargadi and Lalbandi town sub-project are monitoring EMPs. The detailed EMP15 compliance and

monitoring of environmental impacts are presented below:

4.1. Training, Orientation and Community Awareness

94. Environmental Monitors are working in their respective town project for monitoring of EMPs. OBA

and Awareness & Skill-development trainings organized in all implemented towns. Orientation on

WASH program organized in different town projects. Similarly, Social Mobilizers are working in Bidur

and Lalbandi town sub-project. Gender Equity and Social Inclusion (GESI) and OBA training has been

organized in all implemented towns namely Charali_Jhapa, Mahendranagar_Sunsari, Ramnagar-

Mirchaiya, Sakhuwa-Mahendranagar, Birendranagar, Bidur, Lalbandi, Katari and Katahariya.

Livelihood Enhancement Orientation Program has been organized in Charali_Jhapa,

Mahendranagar_Sunsari, Ramnagar-Mirchaiya, Katari, Lalbandi, Shakhuwa-Mahendranagar, Bidur

and Birendranagar. Similarly, School WASH programs are also campaigned at Bidur_Nuwakot,

Birendranagar_Chitwan, Katahariya_Rautahat, Sakhuwa-Mahendranagar_Dhanusha, Ramnagar-

Mirchaiya_Siraha and Katari_Udaypur town sub-project and continued in other towns. The

Orientation workshop for contractors/ laborers, Project orientation seminar in each town in the first

year of implementation for community members with participation of affected persons has

organized in every town of WRDSMC. Similarly, Total 61 participants were involved in Health and

sanitation awareness campaign conducted at Abukhaireni and Consultation meeting held at

Amargadi, Suda and Tamsariya project sites of Western Region. Further continuation of proposed

awareness and training programmes from April to June 2020 like skill training to the OBA

beneficiaries are cancelled due to covid-19 pandemic. The details of awareness and training

programs conducted in subprojects in the first quarter of the reporting period are presented below:

Orientation Programs: Orientation was conducted to all contractors including laborers on labor standards,

gender equality in wages, safety, and hygiene in work sit of 9 subprojects of ERDSMC encompassing 72

participants (Table 25).

Table 25 : Orientation Programs conducted in ERDSMC

SN Name of Town Project District Total Participants by Sex Total

Male Female

1 Charali Jhapa 7 1 8

2 Bidur Nuwakot 5 2 7

3 Katahariya Rautahat 5 2 7

4 Mahendranagar Sunsari 6 2 8

5 Ramnagar-Mirchaiya Siraha 6 1 7

6 Mahendranagar-Sakhuwa Dhanusha 5 1 6

7 Katari Udayapur 7 2 9

8 Lalbandhi Sarlahi 11 1 12

9 Birendranagar Chitwan 6 2 8

Total 58 14 72

Source: QPR ERDSMC June 2020

15 Mitigation measures, monitoring programs, cost estimates, budgets, and institutional arrangements for implementation are the key

elements of EMPs.

Page 88: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

77 | P a g e

Training Programs: Training Programme on Leadership and Utility Management was conducted

participating 24 women executives of WUSCs in 6 Town projects of ERDSMC (Table 26).

Table 26 : Training Programme on Leadership and Utility Management

SN Name of Town Project Total

1 Charali Jhapa 2

4 Ram Nagar Mirchaiya Siraha 3

5 Bidur Nuwakot 4

6 Lalbandi Sarlahi 7

7 Birendranagar Chitwan 2

8 Katari Udaypur 6

Total Eastern Region 24

Source: QPR ERDSMC June 2020

School Wash Program: School Wash Program with 3 events in each 3 schools of 9 projects was conducted

in ERDSMC involving 1061 Participants (531 boys and 530 girls) Table 27.

Table 27 : School Wash Program conducted in ERDSMC Projects

SN Name of Town Project District Participants Number of Events

conducted and no.

of Schools Boy Girl Total

1 Charali Jhapa 53 63 116 3 events in 3 Schools

2 Mahendranagar Sunsari 49 64 113 3 events in 3 Schools

3 Sakhuwa Mahendranagar Danusha 70 54 124 3 events in 3 Schools

4 Ram Nagar Mirchaiya Siraha 60 59 119 3 events in 3 Schools

5 Bidur Nuwakot 45 60 105 3 events in 3 Schools

6 Lalbandi Sarlahi 65 55 120 3 events in 3 Schools

7 Birendranagar Chitwan 45 60 105 3 events in 3 Schools

8 Katari Udaypur 77 57 134 3 events in 3 Schools

9 Katahariya Rautahat 67 58 125 3 events in 3 Schools

Total 531 530 1061

Source: QPR ERDSMC June 2020

4.2. Pollution Prevention and Abatement

95. During the design, construction, and operation stages of the Town projects, implementation of EMP

activities have focused pollution prevention and control technologies and practices as per approved

IEE16 and guidelines in practice17. The nature of the Town projects activities has not experienced

severity by air pollution however, contractors aware to avoid, or where avoidance is impossible,

minimizing or control the intensity or load of pollutant emission especially dust pollution. Most of

the cases established provision of onsite mitigation with use of Personal Protective Equipment (PPE)

(e.g. ear protection gears, masks, goggles etc.). The following activities are placed for pollution

prevention and abatement during the monitoring period.

4.2.1. Ambient Air Quality

96. Ambient air quality at the direct impact area of the town projects observed through visual siting and

interviewed with the project workers and contractors. The construction sites and construction

material and pipe laying area and work transported areas were focused more to experience the air

quality impact. As the instrumental monitoring as per Nepal’s Standard18 was not used to check the

ambient air quality during reporting period as per nature of the project activity and most of the cases

16 Safeguard Policy Statement, 2009 of ADB also suggest the appropriate practical & site specific mitigation and enhancement measures

to address the environmental impact of the proposal and the sub project falls ADB’s SPS Category B projects. 17 World Bank Group, 2007. Environmental, Health, and Safety General Guidelines. Washington, DC. 18 Nepal’s Ambient Air Quality Standard, 2003 (μg/m3)

Page 89: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

78 | P a g e

observed level of dust pollution has used water sprinkling. Dust during pipe laying work was

relatively higher which was mitigated by sprinkling water and prompt refilling of the excavated soils.

Mandatory use of air mask and regular sprinkling of water during construction in the dusty

environment was suggested to the workers. To minimize such possible impacts, aware contractor to

follow mitigation measures i.e. wearing masks as mitigation measures proposed in contract

documents and update EMPs. Moreover, aware to contractor and the local communities, applied

the following mitigation measures:

• Wearing masks while working in dusty sites;

• Regular sprinkling of water to reduce dust pollution at the severe project sites;

• Controlled vehicular movement and safe transportation during upload/unload construction

materials;

• Regular maintenance of vehicles/equipment’s and use of good quality fuel; • Awareness regarding construction activities, and use of masks to the schoolchildren, teachers and

communities.

4.2.2. Water Quality

97. The field level monitoring team has made regular visits and observations to identify possible risk of

drinking water in project impacts area. As reported by the field level monitoring team no risk or

impact on human health found in the project area especially work sites, campsites and adjacent to

construction sites. The contractor has provided the drinking water in the camps, which is from the

drinking water supply taps. There are no records of diseases found in workers due to consumption

of existing tap water. In addition, the wastewater generated from the camp has not been discharged

into the stream but has been discharged into a soak-pit. Wastewater generated from camp toilet

collected in the soak pit. Instructed workers of each camps regarding safe health and sanitation

practices and requirements. On the other hand, the contractor has been instructed to conduct

regular water quality monitoring of the water sources. Monitor considering the transmission

sections of distribution pipeline, which cross water bodies, exposing them to risks of pollution i.e.

poorly managed construction sediments, and waste materials; and poor sanitation practices of

construction workers, mitigation measures stipulated in EMPs. All projects has delivered quantity

of treated water as set in the Performance Target meeting Nepal, National Drinking Water Quality

Standard (NDWQS)19, 2005 (Pic. 1).

Regular Water Quality Test Kathariya Rautahat

Lab Establishment at Amargadi Dadeldhura

Pic. 1 : Water Quality Monitoring at the Site

4.2.3. Noise Level

98. The major source of the noise pollution experienced in the selected Town projects are material

transportation vehicles and operating of generators. Noise in the construction areas was

experienced insignificant except minimal noise disturbance due to generator operation. Established

campsites away from the residential areas/urban vicinities. The noise intensity during reporting period

was not tested. The contractor has strictly instructed to keep their excavators, vehicles, generators

and other machinery in good condition & they have shown compliance in this context. The

19 To ensure that the quality of the delivered water is safe the concerned parties must use and abide by the provisions of the NDWQS, Government of

Nepal has prepared National Drinking Water Quality Standards for implementation of Guidelines for National Drinking Water Quality Standard, 2062.

Page 90: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

79 | P a g e

contractor workforce has also been instructed to use personal protective equipment (PPE) like

earplugs at noise generating sites to abolish the effects from noise. Use of heavy equipment’s is

restricted before 6 am in the morning and after 7 pm in the evening. No grievance recorded from

the workforce and communities in the project areas regarding noise generation during execution of

construction activities. As reported field level monitoring team, mobile applications have been used

to record the indicative noise levels in the project area in regular frequencies.

4.3. Solid Waste Management

99. Aware workers occupational health and sanitation, environmental hazards due to solid waste. Most

of the solid wastes generated in the campsite found collected in pits and bins. Littering of waste

found some sites of the project and workforce and contractors were instructed regarding the

ways of managing solid wastes avoiding burning of waste. In Aabukheireni and Tamsariya Town

Water Supply and Sanitation Project has placed dustbins for degradable and non-degradable wastes

at the project site (Pic. 2 & 3).

Pic. 2 : Placing Waste Segregation Beans at

Tamsariya

Pic. 3 : Waste Bin Placed at Abhukhereni

TWSSP

4.4. Occupational Health & Safety; and Community Health & Safety

100. Occupational health and safety measures are instructed to be implemented as per EMP. The workers

partially provided safety gears like helmet, facemasks, goggles etc. in all town projects. Level of

knowledge of using safety gear in workers found very low due to ignorance. Primary first aids kits

has provided by the contractor at campsites; contractor’s offices and at the work fronts as well (Pic.

4). The contractor has been regularly instructed to make the first aid boxes available at sites

accessible to the workforce. Similarly, monitoring

on health and safety issues to the local communities

has not observed any risk due to implementation of

project activities. Among priority works to prepare

waste management master plans for seven small

towns and storm-water drainage master plans of

ERDSMC projects, Sanitation Master of

Birendranagar, Lalbandi, Katari, Kathariya have

been prepared.

Pic. 4 : Use of PPEs by Workers Amargadi Town

4.5. Camp Site Management

101. Drinking water and sanitary facilities (toilets) found available in the camps for each contract

packages. Each camps, workers were using LPG in most of the cases and firewood (rare case) for

cooking purpose sold by the local people. Code of conduct for workforce found placed in some

campsites of the Project. Similarly, at the campsite occupational health and safety measures

provided with safety gears like helmet, facemasks, globes etc. in most of the Town Projects.

4.6. Public participation and Consultation

102. Public participation and consultation regarding implementation of project activities has been

conducted in each Towns with active involvement of local elites. The orientation workshop for

Page 91: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

80 | P a g e

contractors/ laborers, Project orientation seminar in each town in the first year of implementation

for community members with participation of affected persons has organized in every town.

Orientation seminars on livelihood enhancement for women only have been conducted in towns.

The activities as a Public meetings with affected persons and beneficiaries on resettlement,

entitlement, compensation, special protection measures for vulnerable, mitigation and

management measures, subsidies for poor and vulnerable, other benefits under the project has

been performed in timely in every town. consultation workshop with low income/IP/Dalit

communities from project areas in each town with community members including school/college

students, teachers, academicians, on the plans, design, location, management of water supply

infrastructure, environmental and social mitigation measures are also included in consultation and

participation activities. Participatory Review Meetings in every project towns have conducted.

4.7. Community Awareness and Participation

103. Environmental Management Plan (EMP) has implemented with mitigation works, monitoring works,

awareness raising, and social safeguards as well - through involvement of the contractor and WUSC.

The project team has regularly conducted interactions and consultations in communities to enhance

public awareness on environmental conservation and sanitation aspects. This has made the project

more effective in terms of service delivery through water supply and, sanitation systems and the

overall improvement in the environmental sanitation aspects if the beneficiary communities.

Mitigation & monitoring works as per EMP have implemented regarding awareness raising, and

social safeguards through involvement of the contractor and WUSC (Pic. 5). The user committee

members and concerned stakeholders are well aware

on environmental risks and potential measures.

According to the progress, reports of TSTWSSP

different awareness and community participation

activities such as WASH messages, safety signs, traffic

signs and orientations/trainings delivered to the

workforce, local women and schoolchildren. Table 28

below reflects awareness and community

participation on environmental awareness and

environmental sanitation activities in the Town

projects during the reporting period.

Pic. 5 : Consultation Meeting in Chandrauta Subproject

4.8. Stakeholder Consultations and Participation

104. Stakeholder's consultations conducted at various locations of the town projects and discussed on

magnitude of anticipated environmental impacts that may result from the construction of the

proposed project, the progress of the subprojects, adverse impacts, mitigation measures and

environmental monitoring and grievances. The key stakeholders consulted were Local, regional

and central level organizations, beneficiaries' households, WUCS, TDF, PMO, RPMO & DRTAC in

line with ADB’s requirements pertaining to environment and social considerations. The key

concerns of the people related to the project that includes Implementation of the EMP in field

level, delivering the information regarding safeguard activities to local level, willingness to pay,

upfront cash collection and people’s participation in project implementation. The stakeholder's

consultation also involved user committee members and their participation on awareness program

and capacity building activities with active involvement of Construction Supervision Engineers

(CSEs), Environmental Monitoring Persons, Social Mobilizers, and Environmental Specialist of the

Consultant, the Contractor’s teams, and the WUSCs. The main activities stipulated in EMP has

discussed and introduced responsibility of implementation focusing activities of the contractors

/workforce. The main agenda for consultation were:

• Consideration of solid/liquid waste management issues, campsite management, spoil

management & disposal, disposal of dismantled debris and management of construction

wastes & solid wastes during construction period;

Page 92: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

81 | P a g e

• The socioeconomic problems that may be observed and addressed during the construction

period at the subproject sites like Traffic Congestion, Disruption to Local Vendors,

Discomfort to the passerby, Interruption to the traffic flow, Noise Pollution, Air Pollution,

Damage to the existing facilities etc.;

• Environmental awareness among the local communities and school level program;

• Process of grievance redress regarding any social or environmental aspects of the project

activities;

• Timely coordination and information

sharing regarding pipe-laying works and

other construction activities so as to

minimize any conflict during working;

• Support in compliance monitoring of

the contractor’s activities by providing suggestions and information Promotion of

environmental sanitation in the project

area;

• Interaction with local community

regarding social and environmental issues

(Pic.6).

Table 28 : Public Consultation Meeting & Orientations/trainings in Project Towns

Town Projects Date & Location Public Awareness programs/Interactions No. of Participants

Aabukhaireni 13th January 2020 Health and sanitation awareness campaign 30 (m - 12, f – 18)

17th February 2020 Health and sanitation awareness campaign 31 (m - 12, f – 19)

Amargadhi 8th January,2020 at

Tufandanda

Discussion with locals on environmental

sanitation and HH sanitation

22 (m-12,f-10)

23rd January,2020

at Dalit tole

Discussion with locals on environmental

sanitation and HH sanitation

17 (m-9,f-8)

18th May 2020 Discussion on project progress and caution

to be taken due to CovID-19

12 (m-12, f-0)

Suda 12th January 2020 Consultation meeting at Musepani 19 (m-11,f-8)

29th February 2020 Consultation meeting at WUSC office 13 (m-8, f - 5)

Tamsariya 12th January 2020 Consultation meeting at WUSC Office 13 (m-8,f-5)

18th Feb. 2020 Consultation meeting at WUSC office 17 (m-11, f - 6)

4.9. Protection Works, Bioengineering and Drainage Management

105. Slope protection works, bioengineering and drainage management activities suggested in detail

design and EMP have been considered in the Town projects. Drainage management in the project

area is satisfactory. Some monitoring activities and protection measures adopted among the

selected projects shown in the Pic. 5.

Gabion wall construction ongoing

below RVT at Abukhairini WSSP

Protection Works at Ghatalkhola

in Amargadi WSSP

Protection work at Girbari Khola

Tamsariya Nawalparasi Town

Pic. 7 : Protection Works

106. The major protection and drainage management works carried out during reporting period are:

Pic. 6 : Interaction with Local Elites/Groups at

Amargadi Dadeldhura on March 2020

Page 93: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

82 | P a g e

• Lunching apron at ghatal khola, River crossing Concreting Anarbe Site and Fencing work at

Amargadi Town

• Fencing work of public toilet on progress Protection work at Girbari Khola for the safety of OHT at

Chulesi & Public Toilet at Tamsariya Town

• Gabion wall construction ongoing below RVT at Abukhairaini Town

• Wash out work at Southern Scheme Treatment plant installed site at Suda Kanchanpur

Wash out work at Southern Scheme at Suda

Kanchanpur Town

Anarbe Khola Diversion at Ghatal Khola at

Amargadi Town

Pic. 8 : Washout and River diversion works

4.10. Plantation and Greenery Promotion

107. Plantation and greenery promotion activities observed in Town projects during reporting period.

Plantation carried out in the intake site and greenery promotion activities carried out in the WTP at

Babiyachaur, Tamsariya and Charali FSM subprojects (Pic. 9). Private tree loss due to construction

activities in construction phase of town projects has not been reported till the reporting period.

Pic. 9: Plantation of Narkat (Arunod donax) in Sludge Drying Bed at Charali

4.11. Grievance Redress Committees

108. A town project-specific grievance redress mechanism (GRM) has been established in each

construction phase town projects to receive record, evaluate, and facilitate the resolution of AP’s project related concerns, complaints, and grievances. The GRM is responsible for the social and

environmental performance at the sub project level. The GRM will aim to provide a time-bound and

transparent mechanism to voice and resolve social and environmental concerns related to the town

project. In line with the Third Small Towns Water Supply and Sanitation Sector Project (TSTWSSSP)

Operational Guideline-2071 and ADB Project Administration Manual of TSTWSSSP, Grievance

Redress Committees have been formed in the selected town projects. All the town projects have

been advised to expedite the tasks fully adhering to the process mentioned in Grievance Redress

Mechanism (GRM). Following are the GRM established among the town projects and proper report

Page 94: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

83 | P a g e

and record of grievances received during the reporting period January to June 2020.

- Second level of Grievances Redress Committees (GRC) has been formed in town projects (Charali,

Chakraghatti Sunsari, Mirchaiya, Mahendranagar Sakhuwa, Katari Udayapur, Birendranagar Chitwan,

Katahariya Rautahat, Bidur Nuwakot,). Similarly, local level GRC has been formed in all ongoing construction

towns. Regular follow up, meeting, review, and facilitation have been done in all towns for solving safeguards

issues. Similarly, regular documentation of grievances and solution has been documented in each town

projects. In line with the TSTWSSSP Operational Guideline-2071 and ADB Project Administration Manual of

TSTWSSSP Grievance Redress Committees have been formed in 11 town projects (Tikapur, Chaundrauta,

Salyan, Rukum, Babiyachour, Suda, Tamsariya, Dumre, Abukhaireni, Nirmalpokhari and Amargadhi). All the

town projects have been advised to expedite the tasks fully adhering to the process mentioned in Grievance

Redress Mechanism (GRM). Town projects in all districts have also been advised to keep proper report and

record of grievances received if any.

- Among the 15 GRM recorded during the reporting period, 11 cases have been solved and remaining 4 cases

are in resolving process. Meeting / interactions were held among WRPMO, elected Local body, WUSC and

representatives of local community as per GRM types. WUSC, DSMC and contractor interacted and discussed

with local people to settle disputes of intake construction, damage of community utility, Pipe lying and tap

connection, drainage within RoW etc.at Khalanga Musikot, Nirmal Pokhari Kaski, Tamsariya, Sakuwa

Mahandranagar, Ramnager Mirchaya, Ramnager Mirchaya Strom Drainage, and Chandrauta subprojects.

Most of the grievances were recorded as informal ones in WRDSMC projects related to pipe lying, pipe

leakage, meter function and water supply. All the grievances have been addressed on time by the contractor

under coordination of the WUSCs and the DSMC team.

109. The detailed status of grievances and resolved status of Khalanga Rukum, Nirmal Pokhari Kaski,

Tamsariya Nawalparasi, Skauwa Mahandranager, Ramnagar Mirchiya, Chandrauta, Ramnagar

Mirchiya strom drainage projects recorded during report period are presented in the Annex I.

Page 95: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

84 | P a g e

5. OVERALL FINDINGS AND RECOMMENDATIONS/REMEDIAL ACTIONS

110. Following are the overall findings and recommendation and remedial actions:

5.1. Observations

• Training, orientation and community awareness programmes have been conducted

• Wearing masks at working in dusty sites and observed sprinkling of water to reduce dust

pollution at the severe project sites

• No grievance recorded from the workforce and communities in the project areas regarding noise

generation

• Considered possible risk of drinking water in project impacts area of the project and provided

safe drinking water at the workers camp

• Regular water quality monitoring is ongoing

• Littering of waste found some sites of the project and workforce and contractors were

instructed for management of solid and liquid waste . Solid waste found managed in

most of the construction sites

• Avoided possible loss of forest vegetation during construction works of additional towns and

promoted plantation activities

• Contractors provided OSE and first aids aware workers for their proper use and utilization considering

Covid-19 Pandemic

• Awareness and community participation activities such as WASH messages, safety signs, traffic

signs and orientations/trainings delivered to the workforce

• The water bodies nearby the project are not contaminated and further prohibit discharges from

construction sites

• Equal employment opportunity to the local and prohibit child labor

• Ongoing protection works at the construction and rehabilitation sites of the projects

• Counselled to keep proper report and record of grievances received if any.

5.2. Key Environmental Issues

111. Considering the nature of the project, following are the key issues/impacts on the project sites.

• Health and Safety issues to continuation of works due to COVID -19 pandemic

• Damaged pipelines in Sakhuwa Mahandranagar, Ramnager Mirchaya Lalbandi, Katari and

Bidur subprojects

• Implementation of awareness and training programs

• Satisfactory but not complete proper management of the solid waste and wastewater in the

construction area, which may have negative impacts on the site environment.

• Delay in campsite management also observed, timely management of campsite is

suggested.

• Recommended implementation of EMP activities both construction and O and M stages

• Proper implementation of EMP and monitoring works and preparation of site specific plans

5.3. Additional Actions Planned

• Increase facility of Personal Protective Equipment (PPE) (e.g. ear protection gears, masks, goggles,

safety shoes etc.) at all work fronts and aware workers to use of safety equipment’s

• Pre-medical screening and regular medical screening have been proposed for the workforce

• Planned to place some WASH messages, safety signs, traffic signs, and other environmental and

social safeguards messages around the construction site.

• Trained more workers, user committee members, and concerned stakeholders on EMP to make

them aware on environmental risks and potential measures.

Page 96: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

85 | P a g e

• Coordination and consultation with concerned authority regarding disturbance on pipe lying

works

• Implement sites specific issues adopting proper mitigation and monitoring works, conducting

awareness raising, and social safeguards trainings involving local communities, workers,

contractor, concerned stakeholders and WUSCs.

• Prepare and implement occupational health and safety (OHS) plan and a Standard Operating

Procedure (SOP) to manage COVID-19 risks in the work place

• Promote greenery and implement EMP during construction, O and M phases of the project

5.4. Operation & Maintenance Phase

112. As most of the projects running in the O & M phases, following key safeguard measures are

recommended for implementation.

Risks from exposure to chemicals

To address storage procedures, in-plant handling and dosages of chlorine (bleaching powder), procedures

and guidelines shall be developed and approved by the Consultant after completion of the construction. For

this cost shall be included in the contract document itself. First aid measures shall be introduced for

emergencies and training on the handling and on dosage of the chemicals shall be given to the staff.

Impact on water bodies and aquatic life

The measures that shall be taken to mitigate the impacts are as follows;

- The effluent produced from the periodic backwashing of the filter plant, if discharged directly to the

river course may cause harm to the water bodies and aquatic life especially during the dry season

when the flow will be less.

- As the backwash water mainly contains suspended solids, a small pond of 20,000 litter's capacity

shall be constructed for decantation and draining to the river/ stream course after decantation.

- To avoid the impact to aquatic life, the effluent and sludge shall be disposed only in designated

areas and regular monitoring of the river or stream water quality shall be done.

- Septic tanks shall be built as per standard designs for public toilets and household latrines.

- Public toilet constructed under this project shall be managed through WUSC initiation and

coordination of the municipality. The local youth clubs shall be mobilized.

- Septage disposal pits similar to sludge drying bed shall be used for disposal of slurry and septic

sludge.

- Operation and Maintenance (O&M) Manual shall be prepared along with provision of O&M training

to the WUSC and its team.

- Water Safety Plan (WSP) shall be prepared for the project and the WUSC and its team shall be

trained on the WSP and total sanitation aspects.

- Rehabilitation of post construction works including landscape maintaining/reclaiming especially at

sites where the temporary facilities are to be demolished or removed

5.5. Risk from COVID-19 in the Project Area

113. The outbreak of endemic COVID-19 has been controlled movement of people and disturbed on

project implementation activities of the projects. Taking into account the prevailing pandemic

situation and the guidance issued by GoN, the contractor will have to prepare Site-specific EMP

(SEMP) that includes the occupational health and safety (OHS) plan and a Standard Operating

Procedure (SOP) to manage COVID-19 risks in the work place. The SEMP and OHS Plan will comply

with the EMP measures and the government instruction/guidelines for implementing construction

work during the pandemic. The EA will guide the contractor in preparing site-specific EMP and OHS

plans with SOP giving a priority to the measures for responding to the COVID-19 risks during

construction. The proposed plan will be costed and a robust monitoring and reporting mechanism

Page 97: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

86 | P a g e

will be detailed out to ensure full compliance with the plan. The OHS plan and SOP, as a minimum,

may look at the aspects of:

- record keeping and health screening of workers, and the note all required details for contact tracing

in case needed,

- disinfecting/cleaning offices, yards, stores and labor camps,

- daily temperature checks and other health checks of staff and workers on site,

- social distancing measures in work areas and labor camps,

- mandatory use of personal protective equipment including facemasks and gloves,

- provision of handwashing stations with soap and supply hand sanitizer at camps, kitchen, dining

and work areas,

- keep a medical bay serviced by a fulltime assistant health worker oriented by an expert on

communicable disease,

- information and education campaign for workers (and as required communities); and

- procedures to be adopted in the event any worker has COVID-19 symptoms.

5.6. Major Issues and Way Forward

114. The major issues assessed and way forward for implementation of EMP and Monitoring are

presented in the Table 29.

Table 29 : Major Issues and Way Forward

S.N Issues Way forward

1 Water quality - Water quality testing and regular monitoring of water

quality

2 Waste disposal - Waste minimization and waste segregation

- Awareness programs

3 Occupational Health & Safety - Mandatory use of safety measures (PPEs) such as mask,

helmet, hand gloves and rubber boots, etc

- Provide safe drinking water for labours

- First aid box will be kept at a proper and easily accessible

place

4 Loss of Vegetation cover

during new construction works

- Greenery promotion around the construction sites

- Promote plantation activities at new construction sites

5 Awareness and training

Programs

- Continuation of more of awareness and training programs

to be conducted in the communities

7 Implementation of O & M

activities

- Joint monitoring to be mobilized to ensure that the

project works are completed and monitoring of any

safeguards concerns have been planned for next quarter

- The contractor’s activities need to be supervised and monitored to ensure that there is no deterioration of

environment due to post-construction activities

- O& M Plan will be prepared for the project

- Rehabilitation of post construction works

8. Risk from COVID-19 - Implementation of Standard Operating Procedure (SOP)

to manage COVID-19 risks in the work place

- Inform and aware local communities about the work plan

and precautions the project has taken to mitigate the

health and safety risks

9. GRM Settle disputes of existing pipeliying distrubances with

consultation and keep proper report and record of

grievances received if any.

Page 98: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

87 | P a g e

6. ACHIEVEMENT ON MAJOR ISSUES OF FOCUS ON PREVIOUS REPORT

115. This section describes major issues addressed in EMP implementation and monitoring as per

recommended actions on the previous report with details of achievement undertaken. The

detailed achievements on major issues focused on previous report and suggested corrective

actions are presented in Table 27 below:

Table 30 : Status on Items of focus of Previous Report

S.N Item of Focus Status Description Corrective action

plan, if any

1 Stabilization/

protection

works

Ongoing - Fencing work at Horizontal Roughing

Filter (HRF) site, Slow Sand Filter (SSF),

and Generator & guard house

- Reuse of excavated soil was done

properly, and the excavated soil was

used completely for backfilling. Where

soil needs temporary storage, it was

placed safely to avoid pollution and

erosion, and no erosion was observed in

subprojects.

- Minimizing soil loss, slope stabilization

were duly completed i.e Matiarwa site,

landscaping & gardening works done at

each site.

- Safely placed

excavated soil and

safely disposed

excavated soil

against erosion

- Reused excavated

soil and backfilling

of trenches

-

2 Rehabilitation

and

reinstatement

works

Partially

achieved

- Civil works carried out in the RVT site

- Continued Pipe lying and repairing

works

Prompt actions for

any damage to

properties and

utilities to be

restored or

compensated to

pre-work conditions

3 Plantation and

Greenery

Promotion

activities

Ongoing In progress, Charali FSM, Babiyachaur and

Tamsariya Projects has planted tree and

grass species for greenery promotion

N/A

4 WQ Monitoring Ongoing - Water quality testing has been

conducted (RVT, Treatment Plant and

HH connections) to ensure drinking

water quality to be supplied

- Safe potable water is being served to

the consumers in the O & M phase and

DLP by the contractor and WUSC

respectively. (Effectiveness e.g.

reduction in hardness parameter, of

water treatment test results of

Ramnagar Mirchaiya Subproject).

Water quality test

Page 99: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

88 | P a g e

S.N Item of Focus Status Description Corrective action

plan, if any

5. AQ Monitoring/

Noise levels

Achieved - Instrumental monitoring was not carried

during reporting period.

- Observed water sprinkling at the

construction sites to minimize dust

pollution.

- Drilling work was carried out carefully

with minimal vibration and disturbances

Water sprinkling at

dry exposed

surfaces and

stockpiles of

aggregates at least

twice daily, or as

necessary

6. Public

awareness/

Information

Achieved - Hoarding boards, message boards/sign

boards, and dustbins placed at market

place

- Consulted and informed local people

about the work schedule and possible

disturbances in advance.

- Temporary diversions and signboards

has provided for the pedestrians.

- Trained more

workers, user

committee

members, and

concerned

stakeholders on

EMP to make them

aware on

environmental risks

and potential

measures

7. Camp

management

Achieved The site has sanitary facilities with latrines

and drinking water

Instructed workers about solid and liquid

waste management at the site

Avail sanitary

facilities to the

workers camp ,

management of

solid and liquid

waste

8. OHS and

community

health & safety

Partially

achieved

In case of minor injuries, first aid is available

onsite, and in the case of major accidents,

the contractor pays for medical treatment

Provide first aid

facility at the site

and increase

awareness

9. Timely taken

into account of

EMP activities,

systematic

record of joint

monitoring,

boosting the

workers to use

PPEs and more

effective

grievance

mechanisms

Partially

achieved

- Response for minimizing the impact was

assessed and discussed. Feedbacks and

suggestions were provided to follow the

agreed EMP of the Ramnagar Mirchaiya

town project properly and strictly.

- The WUSC were suggested to keep

hygienic & aesthetic value of OHT site at

Chhagariya in coordination with the

land owner and also separately manage

the segregated areas of land by

bisecting road in consultation with the

Municipality.

- Systematic record of joint monitoring

observed

- Overall, no major conflict with the

communities is observed.

- Jointly site visited at the project sites i.e.

Phalakhu Intake Bidur Nuwakot

Regular supervision

and monitoring

Mobilization of

environment and

social monitors at

the construction site

Stakeholders

consultation

Continuation of

systematic record of

joint monitoring

Page 100: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

89 | P a g e

S.N Item of Focus Status Description Corrective action

plan, if any

10. Continuation of

capacity building

and awareness

Ongoing - Training and capacity building and

awareness activities were conducted

before lockdown due to COVID-19

- Training Programme on Leadership and

Utility Management was conducted at 6

towns of ERDSMC.

- 24 participants24 participants of 6 Town

project of ERDSMC has benefited by the

Training Programme on Leadership and

Utility Management

- School Wash Program with 3 events in

each 3 schools of 9 projects was

conducted in ERDSMC involving 1061

Participants (531 boys and 530 girls)

- Total 72 participants of 9 subprojects of

ERDSMC are benefited from orientation

regarding labor standards, gender

equality in wages, safety and hygiene in

work site

- Total 61 participants were involved in

Health and sanitation awareness

campaign conducted at abukhareni

- Consultation meeting held at Amargadi,

Suda and Tamsariya project sites

Awareness and

implementation of

OHS guideline

considering COVID-19

pandemic

Implementation of

orientation, training

and awareness

programs as

scheduled

11. Regular joint

monitoring of

the project sites

(UCs, contractor

and

stakeholder)

Partially

achieved

Meeting / interactions were held among

RPMO, elected Local body, WUSC and

representatives of local community as per

GRM types. WUSC, DSMC and contractor

interacted and discussed with local people

several times to settle the issues at

Khalanga Musikot, Nirmal Pokhari Kaski,

Tamsariya, Sakuwa Mahandranagar,

Ramnager Mirchaya, Ramnager Mirchaya

Strom Drainage, and Chandrauta.

Continued joint

monitoring to

implement EMP

activities and

resolve the

emerging issues at

the site

12. Continue the

environmental

management

works by the

contractors

Compliance and

noncompliance

actions

construction

and O & M

stages

Ongoing - No construction work was being carried

out nearby any streams or water bodies.

- No surface water contamination is

reported due to oil spillages from

construction equipment.

- Proper protection has been done at the

deep borehole sites with compound

walls and concreted at the upper

portion of boreholes to control

contamination of ground water.

- Campsites were in good condition for

working. No complaints regarding the

transmission of communicable diseases

have been reported.

Solid waste

management in the

campsite needs

improvement in

some subprojects

COVID-19 pandemic

has caused adverse

effect implementing

town projects in

various stages of

works related and its

Page 101: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

90 | P a g e

S.N Item of Focus Status Description Corrective action

plan, if any

- No damage to agricultural land due to

borrow pits or top soil erosion has been

reported.

- Construction materials were

transported from quarries without

degrading the natural environment and

downstream water bodies.

- Occupational safety equipment (OSE)

was provided by contractors for

construction works to labor.

- Wastes produced from construction

areas (like excavated and discarded

materials, etc.) need to be managed

more efficiently.

- Construction materials were covered

with tarpaulins while being transported.

- Sprinkling water has controlled air

pollution resulting from dust produced

from construction area.

effective monitoring

works

Storm Water

Drainage Project,

Ramnagar Mirchaiya

has not been

mobilized effectively

before the pandemic

13 Review and

implement EMP

through wider

consultation at a

Staff Review

Committee and

WUSC meeting

Ongoing - Consultation meetings was conducted

- Local people have been employed, and

no child labor was employed.

Update and review

of EMP and SEMP

for implementation

14 Damage and

disturbance of

pipe lines in the

Sakhuwa-

Mahendranagar,

Ramnagar-

Mirchaiya,

Lalbandi, Katari,

Bidur and

Katahariya town

sub-projects

Partially

achieved

Meeting held among WUSC, DSMC and

Contractor and Decision to resolved the

problem, the name list of remaining

households has provided to contractor for

Tap connection

To be addressed

through wider

consultation with

concerned authority,

WUSC, Contractor

and stakeholder

15 Minimize forest

and vegetation

clearance and

promote

compensatory

plantation

Partially

achieved

No potential loss of trees or vegetation in

the subproject area was observed.

Aesthetics in the project area was

maintained well

NA

6.1 Major items of focus for next report

116. The major issues and remedial actions to be addressed for next report are presented in Table 28

considering ongoing TSTWSSP, FSM projects and 12 enhancement town projects.

Page 102: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

91 | P a g e

Table 31 : Items of Focus in Next Report

SN Item of Focus Remedial actions

1. Surface cutting and excavation works may

cause erosions and impact on the local

water bodies

Soil erosion will be minimized by taking

precautionary measures such as: (i) reuse of

excavated soil, (ii) immediate and proper

backfilling of the trenches, and (iii) the excavated

soil temporarily stored properly against erosion

by using barriers or silt traps.

2. Damage to existing facilities like drains,

road, compound walls and pavements

Ensure any damage to properties and utilities

will be restored or compensated to pre-work

conditions

3. Pollution of water bodies, contamination

of water sources due to waste disposal,

transport of sediments from worksites

and/or construction camps (if any)

Take all precautions to prevent entering of

wastewater into streams, watercourses, or

irrigation system.

4. Solid Waste disposal - Waste minimization and waste segregation will

be prioritized

- Practices of composting will be promoted

- Containment of hazardous waste will be carried

out

5. Disposal of waste on or nearby water

bodies, sediment transport and

leakage/disposal of hazardous waste may

harm the aquatic lives in the

rivers/steams of project area

- Washing of vehicles on rivers will be restricted

- Disposal of waste of any kind on water bodies

will be strictly prohibited

- Fishing in rivers will be prohibited for workforce

6. Loss of vegetation cover during

construction works and laying of the

pipelines, especially treatment and

reserviour sites of Enhancement town

projects

- Greenery promotion around the construction

sites and road alignments where possible

- Promote plantation activities at new

construction sites of enhancement projects

7. Occupational and Community Health and

Safety

- A site health and safety plan including safety

measures such as provision of mask, helmet,

hand globes and rubber boots to workers will be

prepared and implemented

- First aid will be kept at hand in working area

- General public will be excluded from all the

construction sites

8. Overall, communities will be exposed to

cross-cutting threats from construction’s impacts on air and water quality, ambient

noise level; Chances of accidents,

Communicable and transmittable diseases

may potentially be brought into the

community by construction workers

- Contractor’s will maintain adequate space and adequate lighting, temporary fence, barriers

and signage at worksites;

- Children will be prohibited from active

construction sites

- Proper fencing of stockpile areas

- Awareness programs on communicable

diseases and hygiene practices will be carried

out

- Disseminate the GRM to communities and

affected stakeholders during consultations

Page 103: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

92 | P a g e

9. Review and implement EMP through

wider consultation at a Staff Review

Committee and WUSC meeting

- Meeting / interactions among RPMO, elected

Local body, WUSC and representatives of local

community as per monitoring activities and

GRM types

10. Training and Awareness - Continuation of more of orientation, awareness

and training programs to be conducted in the

communities

12. Continue the environmental management

works by the contractors Compliance and

noncompliance actions construction and O

& M stages

- Follow and implement EMP activities in IEE

SSMP and BoQ

- Conduct regular monitoring and supervision

works in coordination with DSMC, WUSC and

other stakeholders

13. Excessive exposure to chlorine,

hypochlorous acid, and hypochlorite ion

generally results in irritation of the

esophagus, a burning sensation in the

mouth and throat, and spontaneous

vomiting

- All disinfection chemicals require proper

storage and handling practices

- Provide safe storage for chemicals

- Ensure that the person is hired, with knowledge

of chlorine use for disinfection process during

operation

- Ensure use of PPE while using chemicals

- Use of chlorine guideline as per WHO

14. Risk of contamination of water in

distribution system

• Regular testing and maintenance of the

water softening, pressure filter and

chlorinator and testing of residual chlorine

will be done on a routine basis and recorded

• Regular water quality monitoring of water of

the distribution system

• System staff will be trained and supervised

15. Delivery of unsafe water due to source

contamination, leakage in pipes

- The operations and maintenance plan and

training for staff will cover; (i)

competent/cautions handling and storage of

calcium Hypochlorite and qualified persons to

implement/oversee disinfection and treatment;

(ii) providing safe storage for chemicals; (iii)

ensure capacity of WUSC to implement quick

response to hazardous substance/waste spills;

(iv) implement SPS-complaint EMP and a water

safety plan; and (v) monitor water quality

16. Implementation of Standard Operating

Procedure (SOP) to manage COVID-19

risks in the work place

Inform and aware local communities about the

work plan and precautions the project has taken

to mitigate the health and safety risks

Page 104: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

93 | P a g e

7. CONCLUSION AND RECOMMENDATION

117. As per the GoN and ADB policies, environmental implications of individual development activities must

account in the planning and decision-making process comprehending a structured process of impact

assessment, planning, and mitigation to address the adverse effects of projects throughout the project

cycle. In TSTWSSSP, project activities addressed through the environmental assessment process,

approving 21 IEEs/EMPs of Town Projects as an integral part of lending operations and Project

development and implementation. Among 21 TSTWSSSP, construction of 11 Town projects of

WRDSMC are completed and monitoring of EMP activities and implementation of safeguard measures

in O& M and DLP stages of the projects are ongoing. Whereas, environmental implications of

completed Town projects has provisioned to be addressed by the respective WUSCs. Similarly, EMP

implementation and monitoring of environmental safeguards on ERDSMC Towns under construction,

O & M phase and DLP stages are ongoing.

118. The Semi-Annual report from January to June 2020 has been prepared based on desk studies and field

level monitoring. During monitoring, it was observed that the contractors has followed most of the

environmental mitigation measures prescribed in the EMP besides some non-compliance issues for

the PPE, erection of information boards/road signs and maintained sanitary situations in worker

camps. However, outbreak of Covid-19 hampered the ongoing project activities in later period. The

overall implementation, supervision and monitoring of the EMP activities concerning environmental

safeguards status of the town projects is satisfactory. The overall implementation, supervision and

monitoring of the EMP activities in the small town projects show that the coordination among the

users, contractor, consultant and the authorities has improved and become efficient in terms of

environmental safeguards aspects in the project sites and offices. Timely addressing of environmental

concerns; systematic recording of the joint monitoring visits; encouraging the workers to use PPEs and

more effective grievance mechanisms are the areas that need to be improved in the small town

projects

119. The contractors instructed and warned to undertake appropriate measures to ensure complete

implementation of EMP including the compulsory use of personal protective equipment and

improvement of sanitary situation in workers camp. No serious omissions or violations of

Environmental standards and norms identified. Proper implementation of EMP as approved IEE

reports and identified additional site-specific issues need to be addressed and monitored during all

stages from pre-construction, construction to O & M phases. Following recommended actions way

forwarded for action:

• Timely taken into account of EMP activities, systematic record of joint monitoring, boosting the

workers to use PPEs and more effective grievance mechanisms;

• Continuation of capacity building and awareness, plantation and greenery promotion activities in

all work fronts of the small town projects;

• Need of the User Committees to be proactive in regular joint monitoring of the project sites to

ensure the compliance of environmental safeguards requirements by the contractor, and all the

stakeholders as well;

• The contractor should be encouraged to continue the environmental management works even

during the operation and maintenance works, Compliance and noncompliance actions are

recommended for review and implement through wider consultation at a Staff Review Committee

and WUSC meeting;

• The key issues regarding damage and disturbance of pipelines in sub-projects to be addressed

through wider consultation with concerned authority, WUSC, Contractor and stakeholder. The

apprehensive environmental implications adhered by such issues should monitored and

implement corrective actions for sustainability of the project;

• Promote greenery and plantation activities in the project area;

• Increased coordination among the stakeholders for completion of EMP works

• Prepare and implement occupational health and safety (OHS) plan and a Standard Operating

Procedure (SOP) to manage COVID-19 risks in the work place.

Page 105: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

94 | P a g e

References

• ADB, 2003.Environmental Assessment Guidelines. Manila

• ADB, 2009. Safeguard Policy Statement. Asian Development Bank.

• ADB. 2008. Strategy 2020: The Long-Term Strategic Framework of the Asian Development Bank 2008–2020.

Manila.

• ADB. 2006. Operations Manual. Section F1: Environmental Considerations in ADB Operations. Manila.

• ADB. 2006. Operations Manual. Section F2: Involuntary Resettlement. Manila.

• ADB. 2006. Operations Manual. Section F3: Indigenous Peoples. Manila.

• ADB, 2010.Handbook of Style and Usage. Manila

• ADB 2014. Environmental Assessment and Review Framework, Third Small Towns Water Supply and Sanitation

Sector Project, 2014, Asian Development Bank

• ADB 2018. Environmental Assessment and Review Framework, NEP: Urban Water Supply and Sanitation

(Sector), Project, July 2018.

• ADB 2019. Project Administration Manual, Nepal: Third Small Towns Water Supply and Sanitation Sector

Project, Project Number: 35173-013, Loan Number: L3157, November 2019.

• CBS 2011.Central Bureau of Statistics, Government of Nepal, Thapathali, Kathmandu

• GoN 1993; Nepal Environmental Policy and Action Plan, Government of Nepal and IUCN Kathmandu.

• GoN/MoLJPA, 2015. Constitution of Nepal 2015. Ministry of Law, Justice and Parliamentary Affairs, Law Books

Management Board, Kathmandu, Nepal

• GoN, 1993. National Environmental Assessment Guidelines. Nepal Gazette (Rajpatra), Volume 43, Number 5,

Kathmandu, 19 July 1993.

• GoN/MoLJPA 1997, Environmental Protection Act 1997 and Environmental Protection Regulation 1997, GoN/N

(Ministry of Law, Justice, and Parliamentary Affairs), Law Books Management Board, Kathmandu, Nepal.

• GoN/MoLJPA 2019. Environment Protection Act 2019 (EPA 2019). Ministry of Law, Justice and Parliamentary

Affairs (MoLJPA), Law Books Management Board, Kathmandu, Nepal.

• GoN/MoLJPA 2020. Environment Protection Regulation 2020 (EPR 2020). Ministry of Law, Justice and

Parliamentary Affairs (MoLJPA), Law Books Management Board, Kathmandu, Nepal

• MoWSS/DWSSP 2015. Final Feasibility Study of Katahariya Water Supply and Sanitation Project

• MoWSS/DWSSP 2016. Detailed Engineering Design Report of Katahariya Water Supply Sub-Project.

• Labor Act (1991), Ministry of Law, Justice and Parliamentary Affairs, Law Books Management Board, Kathmandu

• National Urban Policy (2007). Ministry of Law, Justice and Parliamentary Affairs, Law Books Management Board,

Kathmandu

• Shrestha K 1998. Dictionary of Nepalese Plant Names. Mandala Book Point, Kathmandu, Nepal.

• MoSTE 2011. Solid Waste Management Act (2011). Ministry of Science and Technology and Environment,

Kathmandu

• MoWSS/DWSSP 2009. The Updated Fifteen-Year Development Plan for Small Towns Water Supply and

Sanitation Sector, 2009

• Water Resource Act (1992). Ministry of Law, Justice and Parliamentary Affairs, Law Books Management Board,

Kathmandu

Page 106: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

95 | P a g e

ANNEXES

Page 107: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

96 | P a g e

Annex I: Public Awareness and Grievances Records

SN Issues Site /

Location

Affected

Person /

Community

Action Taken to solve the issue Current

status

Remarks

Khalanga Rukum Musikot

1 Includes 19 points

demands of source

area of Panakhola

Panakhola Community

people of

Pana khola

(Ward no 6

Musikot

Municipality)

Meeting / interactions were held

among WRPMO, elected Local body,

WUSC and representatives of local

community. WUSC, DSMC and

contractor interacted and discussed

with local people several times to

settle the issues

Solved Permanent

Intake has been

developed

at Panakhola

source

2 Issues were recorded

as a formal in earlier

month related to the

dispute of intake

construction in

Timure Source

Timure Community

people of

Timure

Source

Meeting / interactions were held

among WRPMO, elected Local body,

WUSC and representatives of local

community. WUSC, DSMC and

contractor interacted and discussed

with local people several times to

settle the issues

unsolved Temporary

use of

source for

system

operation

Nirmal Pokhari Kaski

3 Delay of pipe laying

work due to the Road

expansion

Ambote Area Community of

Ambote

WUSC, DMSC had been requested to

Municipality to solve the problem and

Municipality had taken action for this

work.

Solved

4 Existing Pipe line

damage during

pipeline excavation

during pipeline

excavation

Bhatechautara

tole ,Lamgadi

tole ,Mahakali

chowk shanti

tole chowk

Shanti tole

Community Contractor immediately to take action

to maintenance the damaged pipeline

Solved

5 Grievances were

recorded as an

informal related to tap

connection in wrong

place in some houses

Lamgadi,Sisne, Bishnu maya

Adhikari,

Sita

Bhandari

Contractor has reconnected in right

place

Solved

Tamsariya Nawalparasi

6 Grievances were

recorded as an

informal related to

damage the masonry

wall

Baireni tole Community 5 Bag Cement and Rs. 5000 provided

by Contractor to maintenance the wall

Solved

7 Grievances were

recorded as an

informal related to

the pipe of Drainage

has cutting down

during Construction

Chormara Community Contractor has immediately taken an

action to maintenance the damage

pipe

Solved

Page 108: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

97 | P a g e

8 Grievances were

recorded as an

informal related to

the irrigation pipe

has damage during

Construction

Basantapur Community Contractor has immediately taken an

action to maintenance the damaged

pipe as per community demand

Solved

Sakuwa Mahandranagar

9 Pipeline damaged in

Highway by six lane

Road construction

Janakpur-

Dhalkebar

trade Road

Project

Letter has been written to Road

Project and requested to repair the

damaged pipe lines.

In

Process

WUSC, Road

Project

Ramnagar-Mirchaiya, Lalbandi, Katari and Bidur

10 Respective

Municipality damaging

the laid pipeline and it

makes uncertainty of

completion of Project

High level decisions were provided to

the respective municipality, which

are made in ministry level as well as

project level. Outcome is yet to come

In

Process

WUSC, RPMO

and PMO

Ramnagar-Mirchaiya Storm Drainage,

11 Department of Road

has not given the

permission to

construct the storm

drainage within it’s right of way (RoW)

It has been informed to the PMO as

well as RPMO

In

Process

PMO/RPMO

Chandrauta

12 Grievances were

recorded as an

informal in earlier

month related to

damage pipe line

(1375M) due to road

construction by

Local Government

Different Site Users

Community

Municipality taken action to maintain

the damaged pipe on the request of

WUSC, DSMC

Solved

13 Grievances were

recorded as an

informal related to

damage pipe line

(850 m.) due to road

construction by

Local Government

Different Site Users

Community

Municipality taken action to maintain

the damaged pipe on the request of

WUSC, DSMC

Solved

14 Grievances were

recorded as an

informal related to

Less quality of water

Different Site User

Community

WUSC established a lab for water test

and ensure the quality of water

Solved

15 Grievances were

recorded as an

informal related to

Pipe lying and tap

connection

Krishnagar

road, Samitee

chock, sunrise

tole, diduwa

tole

User

Community

Meeting held among WUSC, DSMC and

Contractor and Decision to resolved the

problem, the name list of remaining

households has provided to contractor

for Tap connection

Solved

Source: QPR RDSMCS June 2020

Page 109: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

98 | P a g e

Annex II: Public Awareness and Community Participation

Date of

Meeting

Organization/

Firm/ Person

Agenda Decision (in brief) Remarks

Tamsariya_Nawalparasi Town Water Supply & Sanitation Project

22 March,

2020

WUSC and

DSMC

Re-evaluation of Water

Tariff after collecting the

list of new water users.

Request to TDF for the Reevaluation

of water tariff including the list of

additional members of water user's

committee.

Minutes of

meetings are

included in the

monthly progress

reports of

respective months 22 March,

2020

WUSC and DSMC Request to

Contractor for the repair

of third party damaged

Pipe line including

Household connections

WUSC will pay the cost of repair

after obtaining the evaluation of

such works by a sub-committee

consisting of the technical

representatives of DSMC, Contractor

and WUSC

22 March,

2020

WUSC and DSMC Software installation for

maintaining the financial

records properly.

Whole sole authority was delegated

to the WUSC

Chairperson for the installation of

such software as per the prevailing

financial rules and regulations of

GON.

10 June,

2020

WUSC and WUSC

Staffs.

Start of collecting the

Water Tariff @ Rs.

150.00 per month.

Agreed to collect the water Tariff

effective from 1st Ashadh-2077 @

Rs. 150.00 per household per month.

10 June,

2020

WUSC and WUSC

Staffs.

To install the Software

for the effective running

of the project works

Agreed to procure the Software on

the leadership of WUSC chair person

Nirmal Pokhari Kaski

30 May,

2020

WUSC/CSE/IC

G/ Contractor

Regular Progress

Meeting

Amargadi Dadeldhura

12 May,

2020

WUSC

committee,

Consultant and

contractor.

• First phase

completion

meeting.

• Vo-2.

• Recommendation second phase.

• Recommendation vo-2.

Minutes of

meetings are

included in the

monthly progress

reports of

respective months

09 June,

2020

PMO

Representative,

RPMO, consultant

Team, Contractor

Team, WUSC

Team, TDF Team

Stage transfer for

Stage 1st to stage

2nd

All the parties agree under taken the

stage ii, O&M responsibilities as per

contract document, and recommend

the same to PMO/RPMO/DSMC.

12 May,

2020

WUSC,

Consultant and

Contractor

Transfer to Stage 2nd Recommend to RPMO for

Transferring project to second stage

Source: RDSMC June 2020

Page 110: Environmental Compliance Monitoring Report...Environmental Compliance Monitoring Report Semi-Annual Report Project Number: 35173-013 Loan Numbers: 3157 and 8304, Grant Number:0405

99 | P a g e

Annex III: Photographs

Regular Maintanance NirmalPokhari Town

Kaski

Public Toilet Kalikasthan Nirmalpokhari, Kaski

Lab building at ChhapNahala Dumre Town

Tanahun

Hardness of water checked by taking sample

from Eastern Scheme Source Suda Kanchanpur

Fencing work of public toilet on progress

Tamsariya Town Nawalparasi

Anarbe Site Fencing work Amargadhi Town

Dadeldhura

Plantation of (Narkat) Sludge Drying Bed of

Charali Town

WQ test being conducted in laboratory

of Tamsariya WSS Sub-Project