Environmental Compliance Monitoring Report Compliance Monitoring Report Semi-Annual Report No. 4 ......
-
Upload
nguyentuyen -
Category
Documents
-
view
217 -
download
2
Transcript of Environmental Compliance Monitoring Report Compliance Monitoring Report Semi-Annual Report No. 4 ......
Environmental Compliance Monitoring Report
Semi-Annual Report No. 4
Loan/Grant Number: L2851 NEP/G0284 NEP July-December, 2016
Nepal: Integrated Urban Development Project
Prepared by the Government of Nepal for the Asian Development Bank.
This environmental Monitoring Report is a document of the borrower. The views expressed herein do not
necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in
nature. Your attention is directed to the “terms of use” section of this website.
In preparing any country program or strategy, financing any project, or by making any designation of or
reference to a particular territory or geographic area in this document, the Asian Development Bank does
not intend to make any judgments as to the legal or other status of any territory or area.
Government of Nepal Asian Development Bank
Ministry of Urban Development
Department of Urban Development and Building Construction
IUDP, Project Coordination Office
INTEGRATED URBAN DEVELOPMENT PROJECT (IUDP)
Loan/Grant Number(s): L2851-NEP; G0284-NEP
SEMIANNUAL ENVIRONMENTAL SAFEGUARD REPORT
(July-December, 2016)
January, 2017
Integrated Urban Development Project (IUDP)Semi-annual Environmental Safeguard Report January, 2017
List of Acronyms and Abbreviations
ADB Asian Development BankBoQ Bill of QuantityCBR California Bearing RationDCP Dynamic Cone PenetrationDSC Design and Supervision ConsultantDUDBC Department of Urban Development and Building ConstructionDWSMB Dharan Water Supply Management BoardEA Executing AgencyEARF Environmental Assessment and Review FrameworkEIA Environmental Impact AssessmentEMP Environmental Management PlanGESI Gender Equality and Social InclusionGoN Government of NepalGRC Grievance Redress CommitteeGRM Grievance Redress MechanismIEE Initial Environmental ExaminationIUDP Integrated Urban Development ProjectMoSTE Ministry of Science, Technology and EnvironmentMoUD Ministry of Urban DevelopmentMPMC Municipal Project Management CommitteeNGO Non-Government OrganizationOHS Occupational Health and SafetyPCO Project Coordination OfficePAM Project Administration ManualPMSC Project Management Support ConsultantPIU Project Implementation UnitPPTA Project Preparation Technical AssistanceREA Rapid Environmental AssessmentRF Resettlement FrameworkRP Resettlement PlanSLF Sanitary LandfillSMC Sub-metropolitan CitySMR Safeguard Monitoring ReportSWM Solid Waste ManagementToR Terms of ReferenceVDC Village Development Committee
Integrated Urban Development Project (IUDP)Semi-annual Environmental Safeguard Report January, 2017
Table of Content1 Introduction............................................................................................................................... 1
2 Description of Sub-projects....................................................................................................... 1
3 Purpose of Report..................................................................................................................... 2
4 Environmental Category of the Project...................................................................................... 3
5 Environmental Safeguards Implementation Arrangements ....................................................... 4
6 Overall Project Progress Status ................................................................................................ 5
7 Environmental Safeguard Compliance Status........................................................................... 7
8 Compliance on Environmental Safeguards During Construction ............................................... 8
9 Monitoring and Reporting System on Environmental Safeguard ............................................... 9
10 Major Project Issues ................................................................................................................. 9
11 Conclusion and Recommendation ........................................................................................... 9
List of FigureFigure1: Project Municipalities
List of TablesTable 1: Compliance Status with Environmental Loan CovenantsTable 2: National Statutory Environmental RequirementsTable 3: Physical Progress Status of SubprojectsTable 4: Status of Environmental AssessmentTable 5: Municipality Wise Provisional Cost for Environmental MitigationTable 6: Remaining Input of Environmental Safeguard Expert of all DSC
AnnexesAnnex-I : PhotographsAnnex-II : Meeting MinutesAnnex-III : Status of Environmental Safeguards During Planning and Implementation StageAnnex-IV : Environmental Monitoring Format,
Integrated Urban Development Project (IUDP)Semi-annual Environmental Safeguard Report January, 2017
1
1 Introduction
Integrated Urban Development Project (IUDP) is funded by Asian Development Bank (ADB) andGovernment of Nepal in four Municipalities/SMC in order to develop the urban environmentalinfrastructures. These four municipalities/SMC are: Nepalgunj SMC, Siddharthanagar Municipality,Janakpur SMC and Dharan SMC. The project cost is $ 83.87 millions. The project started from July2012 and will end in June 2017.
The project provides the population in the municipalities/SMC of Nepalgunj, Siddharthanagar,Janakpur and Dharan with better access to municipal infrastructure and services in a sociallyinclusive manner. In accordance with the priorities of each municipality/SMC, integrated urbanenvironmental improvements, including drainage systems, solid waste management (SWM)facilities, and urban roads, will be implemented in Nepalgunj, Siddharthanagar and Janakpurmunicipalities/SMC. A water supply development subproject will be implemented in Dharan SMC.The project will also undertake community development programs (CDP), focusing primarily onpoverty pockets in the municipalities/SMC and communities that may not benefit directly from majorinfrastructure improvement subprojects. Gender equality and social inclusion (GESI) will bemainstreamed in all subprojects in the municipalities/SMC, and the capacity to address GESI in theMinistry of Urban Development (MoUD) strengthened by establishing an appropriate institutionalstructure and mechanisms for GESI mainstreaming.
2 Description of Sub-projects
Nepalgunj SMC• 60.051 km new storm water drainage, 12.62 natural water course, 13.206 primary drain,
11.032 secondary drain, 7.038 tertiary drain, and 16.155 road side drain• 8.09 km urban road construction and Improvement• Integrated solid waste management with sanitary landfill site• Community development program and mainstreaming gender equality and social inclusion
Siddharthanagar Municipality
• 42.742 km new storm water drainage, 11.295 primary drain, 8.03 secondary drain, 2.159tertiary drain, and 20.628 road side drain
• 10.36 km urban road construction and improvement• Integrated solid waste management with sanitary landfill site• Community development program and mainstreaming gender equality and social inclusion
Janakpur SMC
• 31.08 km new storm water drainage• 9.29 km road construction and improvement• Integrated solid waste management with sanitary landfill site• Community development program and mainstreaming gender equality and social inclusion
Dharan SMC
• 375 km water supply construction, improvement and expansion• 7 new tube wells construction• Dharan water supply management board (DWSMB) formation for operation and
maintenance• Community development program and mainstreaming gender equality and social inclusion
Integrated Urban Development Project (IUDP)Semi-annual Environmental Safeguard Report January, 2017
2
Figure1: Project Municipalities/SMC (Nepalgunj, Siddharthanagar, Janakpur and Dharan)
3 Purpose of Report
As defined in the environmental requirements semiannual environmental safeguard reports have tobe prepared and submitted to ADB. The semiannual environmental safeguard report prepared forthe project covering the period from July to December 2016.
The following covenants to the financing agreement with ADB be complied with during design andimplementation stage.Table 1: Compliance Status with Environmental Loan Covenants
List scheduleand paragraphnumber ofLoanAgreement
Covenant Status ofCompliance
ActionRequired
Schedule 5,Para 3
The Beneficiary shall ensure or cause MOUD to ensure thatthe preparation, design, construction, implementation,operation and decommissioning of the Project, eachSubproject and all Project facilities comply with (a) allapplicable laws and regulations of the Beneficiary relating toenvironment, health and safety; (b) the EnvironmentalSafeguards; (c) the EARF, for Subproject under Part 2 of theProject; and (d) all measures and requirements set forth in therespective IEE, the EMP, and any corrective or preventativeactions set forth in a Safeguards Monitoring Report.
Complied with/Being compliedwith. These arethe part ofsubprojectappraisal report.
Schedule 5,Para 7
The Beneficiary shall make available or cause MOUD to makeavailable necessary budgetary and human resources to fullyimplement the EMP, the RP and any indigenous peoples’ plan.
Complied with.
Dharan
Janakpur
Siddharthanagar
Nepalgunj
Nepal
Integrated Urban Development Project (IUDP)Semi-annual Environmental Safeguard Report January, 2017
3
Schedule 5,Para 8a to 8e
The Beneficiary shall ensure or cause MOUD to ensure thatall bidding documents and contracts for Works containprovisions that require contractors to.(a) comply with the measures relevant to the contractor setforth in the IEE, the EMP, the RP and any indigenous peoples’plan (to the extent they concern impacts on affected peopleduring construction), and any corrective or preventativeactions set forth in a Safeguards Monitoring Report;
Complied/beingcomplied with.Provision ismade in biddingdocuments andcontracts forworks.
(b) make available a budget for all such environmental andsocial measures;
Complied/beingcomplied with.Provision ismade in biddingdocuments andcontracts forworks.
(c) provide the Beneficiary with a written notice of anyunanticipated environmental, resettlement or indigenouspeoples risks or impacts that arise during construction,implementation or operation of the Project that were notconsidered in the IEE, the EMP, the RP or any indigenouspeoples’ plan;
Complied/beingcomplied with.Will be followed.
Schedule 5,Para 9a to 9 c
The Beneficiary shall do the following or cause MOUD to dothe following:(a) submit semi-annual Safeguards Monitoring Reports toADB and disclose relevant information from such reports toaffected persons promptly upon submission;
Complied with/being compliedwith.
(b) if any unanticipated environmental and/or social risks andimpacts arise during construction, implementation or operationof the Project that were not considered in the IEE, the EMP,the RP or any indigenous peoples’ plan, promptly inform ADBof the occurrences of such risks or impacts, with detaileddescription of the event and proposed corrective action plan;and
Compliedwith/Beingcomplied with.Will be followed.
(c) report any actual or potential breach of compliancewith the measures and requirements set forth in theEMP, the RP or any indigenous peoples’ plan promptlyafter becoming aware of the breach.
Will befollowed.
4 Environmental Category of the Project
According the ADB safeguard policy statement the project is classified as category B with respect toenvironment. As per legislation of Nepal, Initial Environmental Examination (IEE) is required forwater supply, storm water drainage and road subprojects, Environmental Impact Assessment (EIA)is required for solid waste management.
Integrated Urban Development Project (IUDP)Semi-annual Environmental Safeguard Report January, 2017
4
Table 2: National Statutory Environmental RequirementsNo. Sub-Project Name Statutory Environmental
Requirements1 Nepalgunj SMC
Solid Waste Management EIAStorm water drainage and Road IEE
2 Siddharthanagar MunicipalitySolid Waste Management EIAStorm water drainage and Road IEE
3 Janakupur SMCSolid Waste Management EIAStorm water drainage and Road IEE
4 Dharan SMCWater Supply IEE
5 Environmental Safeguards Implementation Arrangements
The following are institutional roles and responsibilities to ensure IEE, EIA and EMPs areimplemented during design and implementation stages.
Project Coordination Office (PCO): The PCO, with assistance from the project management supportconsultant is to:
• confirm IEEs/EMPs are updated based on detailed designs• confirm EMPs are included in the bidding documents and civil works contracts;• ensure contractor EMPs are prepared by contractors prior to construction and endorsed by
PIUs;• establish a system to monitor environmental safeguards of the project including monitoring
the indicators set out in the monitoring plan of the EMP;• facilitate and confirm overall compliance with all Government rules and obtain all required
environmental clearances and any other environmental permits prior to contract award;• supervise and provide guidance to the PIUs to properly carry out environmental monitoring
and reporting;• review, monitor and evaluate the effectiveness with which the EMPs are implemented, and
recommend necessary corrective actions to be taken as necessary;• consolidate quarterly environmental monitoring reports from PIUs and submit semi-annual
environmental monitoring report to ADB;• ensure timely disclosure of final IEE/EMPs in locations and form accessible to the public,• address, record and report on any grievances brought about through the Grievance Redress
Mechanism in a timely manner as per the IEE/EIAs.
Project Implementation Units (PIUs): The four PIUs in Nepalgunj, Siddharthanagar, Janakpur andDharan, with the assistance of design supervision consultants, are to:
• ensure the draft IEE/EMP prepared during the feasibility study is updated during detaileddesign stage, where necessary;
• ensure EMPs are included in bidding documents and civil works contracts;
Integrated Urban Development Project (IUDP)Semi-annual Environmental Safeguard Report January, 2017
5
• ensure overall compliance with all Government rules and obtain all required environmentalclearances as well as any other environmental permits prior to contract award;
• oversee implementation of EMPs including environmental monitoring;• take corrective actions when necessary to ensure no major environmental impacts;• submit quarterly environmental monitoring reports to the PCO, and;• address any grievances brought about through the Grievance Redress Mechanism in a
timely manner as per the IEE/EIAs.
Regarding institutional arrangement, Grievance Redress Committees (GRCs) have been formed inall four municipalities to address overall safeguard related issues (environment, social andresettlement).
6 Overall Project Progress Status
Table 3: Physical Progress Status of SubprojectsNo.
Sub-Project Name Progress Status
1 Nepalgunj SMCStorm water drainageand Road
Contract awarded to CTCE - Kalika Construction JV on December17, 2014.Construction of about 59.391 km (60.051) of storm water drain ;12.62 km (12.62) natural water course, 13.206 km (13.206) primarydrain, 11.032 km(11.032) secondary drain, 6.718 km (7.038) tertiarydrain, 15.815 km (16.155) road side drain and 7.72 km (8.09) urbanroad (Asphalt) has been completed. Overall, about 99% ofconstruction work is completed.IEE report approved by MoUD on August 9, 2015 .and uploaded inproject’s website. Approved IEE report submitted to ADB.
Solid wastemanagement withsanitary landfill sitedevelopment
Land acquisition: 12.5 Bigha (8.47 ha) Private Land/ Ward -7,Hirminiya VDC procured on May 23, 2013.Contract agreement signed with RAMKY-NANC JV on June13,2016.Joint topographical survey of landfill site and its approach road iscompleted. Construction work commenced at Sanitary Landfill site.Revised EIA report submitted to MoUD for approval process.
2 Siddharthanagar MunicipalityStorm water drainageand Road
Contract awarded to M/S China Guangzhou-Sharma & Co. Pvt. LtdJV, Sitapaila, Kathmandu, Nepal on December 15, 2014.
About 33.113 km (43.07km); 9.568 km (11.295) primary drain, 5.348km (6.289) secondary drain, 0.467 km (4.858) tertiary drain and17.73 km (20.628) road side drain is completed. About 6.377 km(10.36km) of asphalt concrete work is completed under urban roadwork. About 81.24% of total construction works has been completed.
IEE report approved by MoUD on August 9, 2015, and uploaded inproject website Approved IEE report submitted to ADB
Solid wastemanagement withsanitary landfill sitedevelopment
Land acquisition: 6 Bigha (4.06ha) Private Land/ Ward -8, PatkhauliVDC. The municipality received the ownership of land on 29 June,2012.
Contract awarded to M/S UPLEEL-NANC JV on April 18, 2016.Contractor was mobilised from May 20, 2016. Work not yet
Integrated Urban Development Project (IUDP)Semi-annual Environmental Safeguard Report January, 2017
6
No Sub-Project Name Progress Status
commenced. Dialogue continued with local people who areobstructing contractor to start construction work of sanitary landfill.EIA report is submitted to MoPE through MoUD and is in the finalstage of approval.
3 Janakpur SMCStorm water drainageand Road
Contract awarded to ZIEC-Sharma JV on December 23, 2015.About 17 % of construction works completed.
• Laying of 6.565 km out of 11.362 km of NP3 RCC pipes of 500-
1200 mm dia is completed.
• Installation of machine for RCC pipe (NP2) at camp site office is
completed and commercial production started, about 685m (400-
600 mm dia) of RCC pipe casted.
IEE report submitted to MoUD for approval.
Solid wastemanagement withsanitary landfill sitedevelopment
Alternative site has been identified at Bhoyal, JSMC-18 owned byGuthi Trust. DSC has been instructed to prepare final detaileddesign report of integrated solid waste management includingsanitary landfill.
4 Dharan MunicipalityWater supply Contract agreement signed with Tianjian and Tundi JV on March 25,
2015. Contractor mobilized from July 15, 2015.Physical progress of water supply construction work is Physical
progress: 55.68%.
.IEE of rehabilitation, extension and development of Dharan watersupply sub-project is approved by MoUD on October 6, 2016Resettlement Plan submitted to ADB.• Production well: Drilling work of production well no. 4 at Udaya
community forest completed, development work and pressure test
ongoing.
• A total of 245.40 km of 375 km; 23.336 km DI (200-400 mm Φ )
transmission and distribution, 222.132 km of HDPE (63-225 mm
Φ ) distribution and 0.848 km of GI pipe laying work is completed.
• Railway distribution system RVT (500 cum): RCC work
completed, plaster and water proofing works completed.
• Phushre distribution system RVT (500 cum): RCC work
completed. Plaster work ongoing.
• Pindeswor distribution system RVT (900 cum): RCC work
completed.
• OHT (200 cum) for backwash of RSF: RCC work completed.
• Phushre operator house: Plaster work ongoing.
• Pindeswor guard house: Finishing work ongoing.
• Flocculation tank: Concreting work of baffle wall is ongoing.
• Sump well generator house (Udaya community forest): Booster
pump is installed and painting work ongoing.
Integrated Urban Development Project (IUDP)Semi-annual Environmental Safeguard Report January, 2017
7
No Sub-Project Name Progress Status
• House connection and interconnection works: Ongoing in both
Railway and Pindeswor distribution systems.
• Reinstatement of surface pavement work: Base, prime coating
and asphalt concreting ongoing.
7 Environmental Safeguard Compliance Status
Progress status of preparation of environmental assessment till December 30, 2016 for thesubprojects is presented in the following table.
Table 4: Status of Environmental AssessmentNo. Subproject
NameEnvironmental
screeningTOR/EIA/IEE Status GRC is
establishedRemarks
1 Nepalgunj SMC
Solid WasteManagement
Carried out Scoping and ToR for EIA studyapproved by MoSTE onDecember 11, 2014,EIA report submitted toMoPE through MoUD forapproval.
Yes Publichearing was
held on Poush2, 2072.
Storm waterdrainage, andRoad
Carried out IEE report approved by MoUDon August 9, 2015 .anduploaded in project’s website.Approved IEE report submittedto ADB.
2 Siddharthanagar Municipality
Solid WasteManagement
Carried out Scoping and ToR for EIA studyapproved by MoSTE onDecember 26, 2014,Revised EIA reportsubmitted to MoPE throughMoUD for approval.
Yes Public hearingwas held on
April 17,2015.
Storm waterdrainage, andRoad
Carried out IEE report approved by MoUDon August 9, 2015 .anduploaded in project’s website.Approved IEE report submittedto ADB.
3 Janakpur SMC
Solid WasteManagement
Carried out Alternative site for sanitarylandfill site identified and beingfinalized.
Yes
Storm waterdrainage andRoad
Carried out IEE report submitted to MoUDfor approval
4 Dharan SMC
Water Supply Carried out IEE report approved onOctober 6, 2016
Yes
Integrated Urban Development Project (IUDP)Semi-annual Environmental Safeguard Report January, 2017
8
8 Compliance on Environmental Safeguards during Construction
Construction works of Storm Water Drainage and Road almost completed in Nepalgunj, andconstruction work ongoing in Siddharthanagar and Janakpur. Water supply work at Dharan isongoing. Solid waste management and land fill site construction in Nepalgunj and Siddharthanagaris just started. Joint topographical survey of landfill site and its approach road is completed inNepalgunj. At Siddharthanagar yet to be started due to obstruction by local people of land fill site.
A meeting was held at PCO on November 11, 2016 on environmental safeguard status and relatedissues of ongoing sub-projects of IUDP. It was participated by PD/PCO, DPDs/PCO, Mr. PadamBahadur Chand/ADB staff consultant, TL/PMSC and Environmental expert/PMSC.
During field visit on November in Siddharthanagar, it is found inadequate supply of OHS. Thecontractor has been suggested to supply sufficient number of the safety gears and first aid withrequired medicines in all work sites. The Contractor was strongly advised to compel the workers touse protective clothing during work hours for their safety. Relocation and reinstatement of drinkingwater pipeline, shifting of electric poles etc are provisioned in BoQ and being done along thecorridor.
Dharan SMC has followed good practice of OHS, but OHS to be improved by Janakpur,Siddharthanagar and Nepalgunj municipality/SMC due to inadequate supply of safety tools (Helmet,Boots, Globes, Jacket, First aid tool kits).Implementation of EMP is not found fully followed.Contractors have submitted environmental monitoring report by checklist, attached in Annex-IV.
EMPs are incorporated into the bidding and contract documents. Contract Clauses onEnvironmental protection are included in contract document as well. Environmental mitigation andenhancement measures are incorporated in bill of quantities. Municipality/sub-project wiseprovisional cost for environmental mitigation is presented in the following table.
Table 5: Municipality Wise Provisional Cost for Environmental MitigationNo. Sub-project Name Provisional cost for
environmentalmitigation(NRs.)
Remarks
1 Nepalgunj SMC
Storm water drainage and Road 3,298,500 (Include plantation work, Trafficmanagement, drainage outletmanagement, OHS, and Airwater quality test.)
Solid Waste Management 3,427,075
2 Siddharthanagar Municipality
Storm water drainage and Road 2,630,585 (Include plantation work, Trafficmanagement, drainage outletmanagement, OHS, and Airwater quality test.)
Solid Waste Management 7,441,939
3 Janakpur SMC
Storm water drainage and Road 1,250,000
Solid Waste Management4 Dharan SMC 17,995,000 With compensatory tree
plantation.
Source: Contract document of relevant municipalities.
Integrated Urban Development Project (IUDP)Semi-annual Environmental Safeguard Report January, 2017
9
9 Monitoring and Reporting System on Environmental Safeguard
Regular compliance monitoring has been not done by DSC safeguard Expert due to completion ofinput of Experts. The remaining input of DSC environmental Safeguard expert has been given inTable 6. Semiannual report is submitted to ADB regularly, but municipality yet to be submittedquarterly environmental monitoring reports to the PCO. Due to the lack of regular quarterlyenvironmental monitoring report from municipalities, semiannual report could not address allinformation.Table 6: Remaining Input of Environmental Safeguard Expert of all DSCNo. Sub-project Name Responsible personnel
for Environmentalsafeguard
ContractManmonth
ConsumedInput uptoNovember,2016
Remark
1 Nepalgunj SMC S.K Pandit 18.5 16 Replacementprocess
2 SiddharthanagarMunicipality
R.K. Sah 18 18
3 Janakupur SMC Mahesh Bhattarai 18 13.644 Dharan SMC Subodh Sharma 6 5.85
Source: Monthly progress report of December, 2016, IUDP.
10 Major Project Issues
The input of Environmental Safeguard Expert of all DSC has been almost completed. IEE report ondrainage and road construction of Janakpur and EIA report of solid waste management ofNepalgunj,Siddharthanagar and Janakpur yet to be approved.
At Siddharthanagar, construction work of landfill site is obstructed by local people. Close monitoringand additional enhancement program are needed to be launched for local residence in the land fillsite. At Nepalgunj also close monitoring is required during construction of landfill site.
Occupational health and safety measures have been found good at Dharan SMC, but partiallysatisfactory in Janakpur, Siddharthanagar and Nepalgunj municipality/SMC. To bring positivechange in this regard, corrective action plan is required.
The Contractor has stockpiled materials such as aggregates, sand, cement, steel and bricks atvarious work sites. However, the stockpiling of materials needs good planning to avoid obstructionto construction works and provide ease for traffic flow. Recommendation was made on properplanning of stockyard and piling of construction material with proper coverage to avoid surfacerunoffs.
11 Conclusion and Recommendation
The Contractor’s compliance towards environmental management has been rated good in DharanSMC other are fair. No accident and incident were registered. All concern stakeholders shall betrained on environmental issues to reduce adverse impacts related with the construction activities.
Integrated Urban Development Project (IUDP)Semi-annual Environmental Safeguard Report January, 2017
10
The followings are recommendations made based on progress status:
• Further work to be taken up in the next reporting period will focus on approval of IEE report ofJanakpur Storm water drainage and road and approval of EIA report of Solid wastemanagement and land fill site construction in Nepalgunj and Siddharthanagar.
• The input of Environmental Safeguard Expert of all DSC has been almost completed it need toincrease in Nepalgunj, Siddharthnagar, Dharan.
• Occupational health and safety measures have been found good at Dharan SMC, but partiallysatisfactory in Janakpur, Siddharthanagar and Nepalgunj municipality/SMC.
• Close monitoring and additional enhancement program to be launched for local residence inthe land fill site of Siddharthanagr municipality.
• Quarterly environmental monitoring report to be submitted regularly to PCO.
Annex-I Photographs
Temporary crossing for pedestrian place byContractor, Dharan SMC
Sumpwell,Uday Community Forest Area
Brick Masonry manhole, Janakpur SMC Box Culvert at Gallamandi Road of LGDN NalaAlignment, Siddharthanagar
Laying of RCC NP3 Hume pipes, JanakpurSMC
Phusre RVT Concrete work, Dharan SMC
Cleaning Road after pipe laying work , Dharan Joint Survey for demarcation of fence boundary lineof SLF site, Nepalgunj
JBKN Nala, Rectangular Brick Masonry Workat CH 0+120, Siddharthanagar
Transmission main pipe laying, Dharan
SLF Site: Discussion and Meeting with locals and start of joint survey work, Siddharthanagar
Annex 3
page 1of 2
Name of the Project: Integrated Urban Development Project Reporting period: Dec-16
S. No. Name of Project or Subproject
Environmental
screening is carried
out? (Yes or No)
Environment
category of
the project /
subproject
(A/B/C/FI)
EARF is
prepared (if
applicable)
(Yes/No)
EIA/IEE/DDR
with EMP is
prepared
(Yes/No)
ADB approved
EIA/IEE with
EMP
(Yes / Under
Review / Not
Yet Due/Over
Due)
Government
approved EIA/IEE
with EMP
(Yes / Under Review
/ Not Yet Submitted)
Safeguard
monitoring and
coordination
mechanism
established
(Yes/No)
GRC is
established
(Yes/No)
Automated
safeguard
monitoring
system
customized
(Yes/No)
EMP cost in
approved
document is
included in BOQ
as an individual
item (Yes/No)
Remarks
1 Nepalgunj SMC
Solid Waste Management Yes B/C Yes Scoping andToR approved
and EIAprepared andsubmitted to
MoPE
Yes Submitted forapproval
No Yes Yes Yes
Stormwater Drainage and Road Yes B/C Yes Yes Yes Approved No Yes Yes Yes
2 Siddharthanagar Municipality
Solid Waste Management Yes B/C Yes Scoping andToR approved
and EIAprepared andsubmitted to
Yes Submitted forapproval
No Yes Yes Yes
Status of Environmental Safeguards During Planning Stage
submitted toMoPE
Stormwater Drainage and Road Yes B/C Yes Yes Yes Approved No Yes Yes Yes
3 JanakpurSMC
Solid Waste Management Yes B/C Yes Scoping andToR in
progress
Not Yet Due Not Yet Submitted No Yes Yes Not Yet Due
Stormwater Drainage and Road Yes B/C Yes IEE submittedto MoUD for
approval
Submitted Submitted forapproval
No Yes Yes Yes
4 Dharan SMC
Water Supply Yes B/C Yes Yes Submitted Approved No Yes Yes Yes
Note: EIA- Environmental Impact Assessment; IEE- Initial Environmental Examination; DDR- Due Diligence Report; EMP- Environmental Management Plan;
GRC- Grievance Redress Committee; BOQ- Bill of Quantity
Annex 3
Page 2 of 2
Name of Project: Integrated Urban Development Project Reporting period: Dec-16
Quarry Operation
and restoration
Target
(Nos.)
Replanted
(Nos.)
Safety Gears
are sufficient
and used (Y/N)
Labors
are
insured
(Y/N)
Labor and work
camps are healthy
and have sanitary
facilities (Y/N)
Community
Structure 1
Community
Structure 2
1 Nepalgunj SMC
Solid Waste Management Contract awarded on 13 June 2016, work yet to be started
Stormwater Drainage and Road
95% 0 90% NA N NA NA N
Not
adequate Y
Not
adequate
Electric
pole to be
reinstated Y Y/not regular
2 Siddharthanagar Municipality
Solid Waste Management Contract awarded on 18 April 2016, Survey work started
Stormwater Drainage and Road
90% 0 70% NA N N
Not
adequate Y
Not
adequate
Electric
pole to be
reinstated Y Y/not regular
3 Janakpur SMC
Solid Waste Management Alternative site has been identified at Bhoyal, JSMC-18 owned by Guthi Trust
Stormwater Drainage and Road 60% 0 45.00 NA N NA NA N Y Y Y Y N
4 Dharan SMC
Water Supply 95% 0 NA NA N N Y Y Y Y Y/not regular
Progress status and issues in brief:
Others as
per EMP
(specify)(Air
/water
pollution)
Compensatory
Plantation
Others as
per EMP
(specify)
Env
compliance
reporting is
maintained
(Y/N)
Remarks
Nos of
grievances
documented
No of
grievances
resolved
Community structures are
compensated / reconstructed
(progress in % of total estimated
Status of Environmental Safeguards During Implementation Stage
Compliance to Environmental Management Plan*
Physical Socio-economic
S.
No.Name of Subproject
Spoil Management
compliance in %)**
Landslide
protection with
Bio-engg
(compliance in %)**
Drainage
Management
(compliance in
%)**
Others as per EMP
(specify)/ Safety sign
Occupational Health and SafetyFirewood
is used for
cooking
and
heating
(Y/N)
No of
grievances
under
processing
Corrective
Action
Plans are
prepared
and
implement
ed (Y/N)
Biological
Grievances
Progress status and issues in brief:
Annex- IV
Monitoring ChecklistName contractor:- TIANJIN TINDI JV Contract No:- IUDP/W/DHN/ICB-01 FOR THE MONTH OF :- October,2016Name of DSC:- Building Design Authority Pvt. Ltd.(insert sign , or scale where applicable)Projectstage
Project ActivityPotential Environmental
ImpactsProposed mitigation measures
MitigationCompliance
MitigationEffectiveness DSC Remarks
Preparation forconstruction
Indicate in1-5 scale(1=Low)
Indicate in1-5 scale(1=Low)
Compliance(C);NonCompliance(NC)Not applicable(NA)
C NC NA
Identify the temporary areasrequired by the project andlocate them with propermarking
May result social tensions Prepare the details of temporary land
acquisition and other private properties
3 4
Submit to Supervising Engineer 3 4
Follow RAP for temporary acquisition 3 4
Submit applications to get anapproval
Submit such agreement andpermits to SupervisingEngineers for officialinformation
May result social conflict and legalobstructions resulting in delay of work
Obtain Letters of Approval and Agreement
for (i) temporary acquisition of land and
properties (ii) relocation of religious site,
foot trails, (iii) disruption of water supply,
and others
2 3
Delineate and peg the areasrequired
May result social conflict and legalobstructions resulting in delay of workPegging of project area
Pegging of all constructions site and labor
camp 4
3
Maintain records of trees and other
properties likely to be affected
3 2
Construct workforce camp Haphazard camps resulting in socialstress and degradation of localenvironment
Establish workforce camp at designatedsite only
5 5
Make employment policy forlocal and affected people asper EMP
Local people may be deprived ofopportunities, Minors may beemployed
Employ local people (not under age 14)
especially SPAF, and PAF in jobs
3 2
Settle wage rate based on DWEC andprovide the list of employees to SupervisingEngineer
3 3
Annex- IV
Projectstage
Project ActivityPotential Environmental
ImpactsProposed mitigation measures
MitigationCompliance
MitigationEffectiveness DSC Remarks
Indicate in1-5 scale
Indicate in1-5 scale
Compliance(C);NonCompliance(NC)Not applicable(NA)
C NC NA
ConstructionPhase: PhysicalEnvironment
Construction Activity
Adopt cut and fill principleduring earthworksDisposal of excess materialsin designated areaApply Bio-engineering forcontrolling of erosion andGully
Soil Erosion sedimentation and slopeinstability
Adopt ‘cut and fill’ approach, wherever
possible
4 3
Avoid works during monsoon 5 5
Provide proper drainage facilities 2 2
Stockpile top soil for reuse 4 4
Adopt gully control and bioengineering 2 3
Procure aggregates from already existing
sites
5 5
Dispose spoil in designated area 4 5
Quarrying from river bed Change in River Hydrology and RiverMorphology Avoid Quarrying/Mining activity in
river/streams for extraction of materials
required for project shall not be done so
that change the river cross sections and
longitudinal profile do not occur
3 4
Ensure care so that irrigation canal/channel
are not adversely affected by the project
construction
3 4
Ensure care of stone spout in order not todisturb the existing flow.
3 4
Annex- IV
Projectstage
Project ActivityPotential Environmental
ImpactsProposed mitigation measures
MitigationCompliance
MitigationEffectiveness DSC
Remarks
Indicate in1-5 scale
Indicate in1-5 scale
Compliance(C);NonCompliance(NC)Notapplicable(NA)
C NC NA
Disturbance of drainage
Dumping of waste in the river
Construct of toilets in thecamps
Storing of materials in theproject area
Handling of toxic materials
Dumping of excess materials
Quarry operation
Water PollutionAvoid camping facility within drainage
4 4
Prohibition on dumping of wastes in the
water source
4 4
Provision of sanitary facility and prohibitionon defecation in open areas
3 4
Proper storage of construction aggregates,hazardous, and toxic materials and properdisposal of chemical containers, packagingmaterials, plastic bags provide training toworkforce on safe handling of toxic materials
3 4
Disposal of waste in the designated area4 5
provide dumping site and waste treatment
facility
2 2
Avoid excessive mining from riverbed.3 4
Movement of vehicles
Operation of crusher
Earthworks
Stockpiling of constructionwaste and constructionmaterials
Air Quality deteriorationSpraying of water in dry season at
construction site and disposal site (Three
time a day)
4 5
Annex- IV
Projectstage
Project ActivityPotential Environmental
ImpactsProposed mitigation measures
MitigationCompliance
MitigationEffectiveness DSC Remarks
Indicate in1-5 scale
Indicate in1-5 scale
Compliance(C);NonCompliance(NC)Not applicable(NA)
C NC NA
Limit speed of construction vehicle4 4
Safe place3 4
Regularly maintain equipment and cover the
stockpile
4 4
Compliance of vehicles with National Vehicle
Mass Emission Standards, 2056 BS
4 4
Arrange proper ventilation in confined
working areas
4 4
Movement of vehicles
Operation of crusher
Operation of constructionmachineries and equipment
Horn honking
Noise and vibrationFit mufflers to control noise
2 3
speed limit of construction vehicle5 5
Use light horn in vehicles5 5
Maintenance of equipment5 5
Prohibit the operation of crushing plant
between 7 PM to 6 AM
5 5
Compensate the damages caused by
vibration
3 3
Annex- IV
Projectstage
Project ActivityPotential Environmental
ImpactsProposed mitigation measures
MitigationCompliance
MitigationEffectiveness DSC
Remarks
Indicate in1-5 scale
Indicate in1-5 scale
Compliance(C);NonCompliance(NC)Notapplicable(NA)
C NC NA
Scrapping of top spoil Effect on Soil quality Stockpile reusable top soil properly in safeyard
3 4
Storage of fuel, lubricating
oil, chemicals etc.
Project activities producing
wastes such as used tyres,
lubricating oil, exhausted
battery etc
Solid waste problems, health risk Store all materials, toxic, non-toxic andhazardous materials in safe place(warehouse)
3 4
Collect, segregate and dispose waste at
designated area
3 4
ConstructionPhase:BiologicalEnvironment
Construction Activity
vegetation clearance forconstruction of projectstructures
Vegetation clearance Cut only marked trees 4 5
Fuel wood and NTFPscollection by workforce
vegetation clearance forconstruction of projectstructures and compensationto them
Loss of vegetation species Prohibit fuel wood and timber collection 3 4
Prohibit illegal NTFPs collection and Trade 3 4
Provide LPG/kerosene to workforce 3 4
Stockpile the felled trees and take
permission from concerned authority for its
use
3 4
Plant trees @ 5 times of each felled trees 3 4
Compensate for affected trees from private
and community forests
3 4
Annex- IV
Project stage Project ActivityPotential Environmental
ImpactsProposed mitigation measures
MitigationCompliance
MitigationEffectiveness DSC
Remarks
Indicate in1-5 scale
Indicate in1-5 scale
Compliance(C);NonCompliance(NC)Notapplicable(NA)
C NC NA
ConstructionPhase: Socio-EconomicEnvironment
compensation andRehabilitation as per RAP
Land Intake and compensation toaffected people
Avoid involuntary displacement 3 4
Compensation, Rehabilitation and
employment opportunity to the affected
people
3 4
Provide all possible assistance to the
displaced people until the displaced people
are settled
3 4
Provide disturbance and rehabilitation cost 4 5
Protect traditional rights of locals 2 3
Compensate for any loss of 3 4
crops, trees and other natural resources 3 4
Establish technical committee to assess
damage caused by vibration for
compensation
3 4
Reinstatement ofdamaged communityservices andinfrastructures
Reinstatement of community servicesand infrastructures
Compensate or reinstate community assetssuch as temples, bridges and irrigationcanals, electricity poles, telephone lines,drinking water pipes, sewerage lines, roads,trails, cremation sites etc
3 4
Annex- IV
Projectstage
Project ActivityPotential Environmental
ImpactsProposed mitigation measures
MitigationCompliance
MitigationEffectiveness DSC
Remarks
Indicate in1-5 scale
Indicate in1-5 scale
Compliance(C);NonCompliance(NC)Notapplicable(NA)
C NC NAInflux of outside workforce,money and disharmonyactivity
Increase in crime and communitystress
Instruct Workforce for not to indulge in
Gambling and drinking alcohol
3 4
Prohibit Visiting of workers to nearby village
after 7 pm and living outside
3 4
Instruct workforce to respect local culture,
tradition, rights etc.
3 4
Request police to patrol in the camp site and
adjoining villages
3 4
Launch awareness programs concerning the
human trafficking and possibility of spread of
STDs and HIV/AIDS
3 4
Project Activities relating tohealth and safety issues atwork areas
Health and hygiene(unsafe working conditions, accidents,fire hazard, transmission ofcommunicable disease)
Provide facilities of health check, proper
sanitation and hygiene, health care, control
of epidemic diseases to workforce
4 5
Provide awareness on STD, HIV/AIDS 4 5
Place adequate warning system, signboard,
hoarding post and prohibit visiting risky area
as necessary
3 4
Make available first aid kits ambulance and
fire fighting gears
4 5
Make available protection gears to all
construction workers and compensate for
the loss of life or any type of injuries
4 5
Dislocation of archaeologicalartifacts, if any
Loss of Archaeological and culturalsites
Protect archaeological and cultural sites
In case of relocation, consult localcommunity
3 4
Annex- IV
Projectstage
Project ActivityPotential Environmental
ImpactsProposed mitigation measures
MitigationCompliance
MitigationEffectiveness DSC
RemarksPreparation forconstruction
Indicate in1-5 scale
Indicate in1-5 scale
Compliance(C);NonCompliance(NC)Notapplicable(NA)
C NC NA
Traffic Congestion For Dharan schedule working hour at night
Provide information about constructionschedule to the local people
2 3
Demolition of unnecessarystructures
Decline in aesthetics andinconvenience to people
Remove all unnecessary structures andreinstall the facilities and others to theoriginal condition
3 5
Traffic management atconstruction sites
Traffic Congestion For Dharan Valley schedule working hour atnight
Provide information about constructionschedule to the local people
2 3
Prepared by: Ashok Raj Adhikari Submitted to: Team Leader, IUDP,
DSC Contract Manager Date of