Environmental and Social Monitoring Report Samoa: Power ... · EPC agreed and redesign system to...
Transcript of Environmental and Social Monitoring Report Samoa: Power ... · EPC agreed and redesign system to...
Environmental and Social Monitoring Report
Number 1: Semestral Report July, 2015
Samoa: Power Sector Expansion Project
Prepared by Electric Power Corporation for the Government of Samoa and the Asian Development
Bank
This environmental and social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of
or reference to a particular territory or geographic area in this document, the Asian Development
Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Telephone: (685) 65400
Facsimile: (685) 23748
E-mail: [email protected]
Website: www.epc.ws
PO Box: 2011
Electric Power Corporation
Semi Annual Safeguard Monitoring Report
Period: January - June 2015 ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Samoa: Power Sector Expansion Project
July 2015
Page 2
Telephone: (685) 65400
Facsimile: (685) 23748
E-mail: [email protected]
Website: www.epc.ws
PO Box: 2011
Electric Power Corporation
This continual six months safeguard report is prepared by the Electric Power
Corporation for the Government of Samoa and the Asian Development bank.
This report is a document of the borrower. The views expressed herein do not
necessarily represent those of ADB's Board of Directors, Management, or staff, and may
be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document,
the Asian Development Bank does not intend to make any judgments as to the legal or
other status of any territory or area.
Page 3
Telephone: (685) 65400
Facsimile: (685) 23748
E-mail: [email protected]
Website: www.epc.ws
PO Box: 2011
Electric Power Corporation
Table of Contents
ACRONYMS ......................................................................................................................................... 4
EXECUTIVE SUMMARY ................................................................................................................... 5
INTRODUCTION ................................................................................................................................ 6
SITES DESCRIPTIONS...................................................................................................................... 7
Afulilo Micro Bubble Technology…………………………………………………………………7
PROJECT DESCRIPTION…………………………………………………………………………………………7
Afulilo Micro Bubble Technology…………………………………………………………..…7-8
OTHER TASKS…………………………………………………………………………………………………….…8
Afulilo and Taelefaga……………………..…………………………………………………………8-9
Storage………………………………………………………………………………………………..………9
SAFETY, SOCIAL and RE-SETTLEMENT .................................................................................... 9
SITE ISSUES and GRIEVANCES……………………………………………………………………………..
Fiaga Water Booster Pumping System………………………………………………………..
kv Fuluasou to Apia wharf Underground Power Cable Works……….………
SCADA………………………………………………………………………………………………………..
Hospital Feeder Stage …………………………………………………………………………..…
GRIEVANCE REDNESS MECHANISM……………………………………………………………….. -12
CONCLUSIONS ................................................................................................................................. 12
Page 4
Telephone: (685) 65400
Facsimile: (685) 23748
E-mail: [email protected]
Website: www.epc.ws
PO Box: 2011
Electric Power Corporation
ACRONYMS
ADB - Asian Development Bank
ADF - Asian Development Fund EMMP - Environmental Management and Monitoring Plan
EPC - Electric Power Corporation
ESU - Environment and Social Unit
H2S - Hydrogen sulfide gas IEE - Initial Environmental Examination
JICA - Japan International Cooperation Agency
JBIC - Japan Bank for International Cooperation
PMU - Project Management Unit
PSEP - Power Sector Expansion Project
SCADA - Supervisory Control and Data Acquisition
Page 5
Telephone: (685) 65400
Facsimile: (685) 23748
E-mail: [email protected]
Website: www.epc.ws
PO Box: 2011
Electric Power Corporation
EXECUTIVE SUMMARY
Project Management Unit (PMU) during this period, advertised for interest Bidders who
can install a Micro bubble technology to be applied at Afulilo reservoir; finalized the
Environmental Management and Monitoring Plan (EMMP) and Initial Environmental
Examination (IEE) for the Upgrading of Afulilo Reservoir and Taelefaga Hydro Station ; finalized the EMMP and IEE for the Energy Storage System ; and investigated and
addressed all complaints received by the Corporation in relations to PSEP projects and
subprojects.
There were no environment issues raised by members of the public and other
stakeholders.
There were also no safety issues or reports of any injuries or near miss during this
period.
Page 6
Telephone: (685) 65400
Facsimile: (685) 23748
E-mail: [email protected]
Website: www.epc.ws
PO Box: 2011
Electric Power Corporation
INTRODUCTION
The Power Sector Expansion Project (PSEP) is an 8 year commitment, from 2008 to
2016 for the implementation of various improvements to the power sector to improve
the supply of electricity in Samoa and Electric Power Corporation (EPC) financial
capacity.
System improvements include: construction of new power station to increase
generating capacity to meet current growing demands and future, increasing capacity of
transmission and distribution power lines, reduce line loss, improve efficiency of
operation, new Supervisory Control and Data Acquisition (SCADA) system to closely
monitor and remotely control generators and other equipment, substations and
National Control Center, underground of backbone transmission and distribution lines,
conversion to prepayment meters from current induction/readable meters, etc.
EPC is in need of improving its collection performance; remove transmission obstacles
to improve reliability and quality of electricity supply; and capacity requirements to
meet growing peak demands. The long term objective is to reduce Samoa s reliance on imported fuel by promoting clean and renewable energy using hydro, sun, wind, biogas
and waste to energy generation.
Project is funded by the Asian Development Fund (ADF), Asian Development Bank
(ADB) loan, Japan Bank for International Cooperation (JBIC) loan, Government of
Australia grant, Samoa Government and EPC.
The Project Management Unit was established for the management and implementation
of the Power Sector Expansion Project. This includes project planning, design,
construction, project and construction management, monitoring, reporting,
procurement, evaluation, cost and quality control. The Environment and Social Unit
(ESU) under the PMU is responsible for managing land acquisition, resettlement, social
and environmental impacts.
Page 7
Telephone: (685) 65400
Facsimile: (685) 23748
E-mail: [email protected]
Website: www.epc.ws
PO Box: 2011
Electric Power Corporation
Afulilo
Reservoir
Afulilo
Dam
Taelefaga
Hydro Station
SITES DESCRIPTIONS
Afulilo - Micro Bubble Technology
Afulilo Dam and Reservoir is located on the North East of Upolu Island, approximately
317meters above sea level in full capacity. The hydro station is situated 200meters
from the Fagaloa Bay, 35meters from the Primary school and 22meters from the nearest
residence.
PROJECT DESCRIPTION
Below are some of the subprojects that ESU is closely involved with to identify all social
and environment impacts and address them, so as to ensure no delays are encountered
during implementation phase.
Afulilo - Micro Bubble Technology
Afulilo Dam was constructed in 1990 and Taelefaga station is Samoa s only storage
hydro-power station that is fed by the Afulilo reservoir. Over the years, the people of
Taelefaga (where the powerhouse is located, near the North East coast) complained regarding foul smell from EPC s hydro station at their village. They threatened the
Corporation that they will shut down the operation of this hydro station if foul smell
continues and no resolution is implemented.
EPC is presently using a compressor to pump oxygen into deep part of the dam
(Aeration system) to mitigate generating of Hydrogen sulfide gas (H2S) which causes
smell when discharge from power station at Taelefaga. H2S often results from the
Map source: SMEC report 2011 – Afulilo Environmental Enhancement Project.
Page 8
Telephone: (685) 65400
Facsimile: (685) 23748
E-mail: [email protected]
Website: www.epc.ws
PO Box: 2011
Electric Power Corporation
bacterial breakdown of organic matter in the absence of oxygen, mainly at the Reservoir.
PMU with the assistance of Dr. Seiichi Tanaka (a Japan International Cooperation Agency
- JICA volunteer) are investigating mitigation measures to solve the offensive smell; and
currently we are looking into the use of a micro bubble technology.
This technology has been successfully implemented in Japan and the United States of
America. The aim of this technology is to clear the color and the odor of the water
discharged from the reservoir. Micro bubbles are created from pressuring water into a
nozzle where air is sucked in, and the outlet flow is twisted so that air bubbles become
really small.
Latest progress: January - June 2015
EPC advertised the installation of Aeration and Micro-bubble systems for responsible
bidders. 2 companies applied (see figure 4 for pre-bid meeting);
Technical Evaluation Committee consists of Attorney General s Office, Ministry of Finance and EPC will review bids and provide report.
OTHER TASKS
Afulilo & Taelefaga EMMP and IEE for the Upgrading of Afulilo Reservoir and Taelefaga Hydro Station were finalized; The Taelefaga power station is located near the coast and discharges water
from Afulilo reservoir to the Fagaloa bay. These projects were commissioned in 1993,
space, tailrace and penstock for a third generator is already there, now EPC is proposing
to install a 2MW generator. EPC will also soundproof the powerhouse door to avoid
noise impacts on neighbouring properties. Construction of a pipe to divert water from
the powerhouse to the bay, upgrading of the aeration system, installing of a micro
Figure 4: (L-R) Fonoti Perelini (EPC Project
Manager), Dr. Seiichi Tanaka (JICA
Volunteer), Moetuasivi Asiono (EPC Public
Relations and Community Officer), and
Aoyama Hideo (RINKAI Construction Co Ltd -
Tokyo Japan). Photo on Monday 13 April
2015. 10:20am.
Page 9
Telephone: (685) 65400
Facsimile: (685) 23748
E-mail: [email protected]
Website: www.epc.ws
PO Box: 2011
Electric Power Corporation
bubble system and installing of a floating intake at Afulilo reservoir will help solve the
effects of H2S to Taelefaga community.
Areas surrounding the site have been mainly used for plantations and cattle farms.
There is no settlement in the vicinity of the Afulilo reservoir and no households will
need to be resettled. Areas near the Taelefaga hydro station are mixed use (plantations,
residential buildings, cattle farm and a Primary school). Minimum compensation will be
required for only land and crops that will be occupied by the pipeline. There are no
other significant cultural sites or conservation areas that will be affected by the
developments.
Other mitigation measures have been proposed to avoid any interference with
neighbouring properties, pollution of the bay and stream, and to ensure that all
constructions are carried out using best practices.
Storage EMMP and IEE for the Energy Storage System were finalized. The proposed
development includes the construction of a storage system building and its accessories.
The installation of this Energy storage system will be able to provides grid operational
support, maintain good power quality and reliability and allow higher percentage of
integration from intermittent renewable energy sources.
Areas surrounding the proposed site have been mainly used for plantations and cattle
farms. There is no settlement in the vicinity of the 97 acres and no households will need
to be resettled. No compensation will be required for this project. There are no other
significant cultural sites or conservation areas that will be affected by the development.
Mitigation measures have been proposed to address and avoid any interference with
neighbouring properties, environmental pollutions, and to ensure that all constructions
are carried out using best practices.
SAFETY, SOCIAL and RE-SETTLEMENT
There were no issues on the Environment. Minor land grievances were addressed by
EPC and compensation of affected crops were made during this period.
Page 10
Telephone: (685) 65400
Facsimile: (685) 23748
E-mail: [email protected]
Website: www.epc.ws
PO Box: 2011
Electric Power Corporation
SITE ISSUES and GRIEVANCES
Below were the 4 minor issues with the following subprojects.
1. Fiaga Water Booster Pumping System.
This subproject involves building 4 booster pumping stations to pump water from
Samoa Water Authority water system at a lower elevation to Fiaga Power Station. In
January 2015, Mr. Ututaaloga Charlie Ulia, a tenant in Aleisa, requested if the first booster pump station could be relocated from the EPC s proposed location so that his concrete blocks and drain pipes business would not be affected.
Addressing Grievances
EPC agreed and redesign system to relocate first booster pump station in question
100 meters up the road, away from the area tenant had requested to leave for his
concrete business.
2. 22kv Fuluasou to Apia wharf Underground Power Cable Works.
Work has been completed for a while, but there were two late grievances received by
EPC related to construction of this subproject which affected their properties:
a. Mr. Raymond Voigt, a resident of Lepea village, complained that EPC s hired contractor excavating trench to lay underground cables accidently damaged
and lost a corner survey peg to his family property adjacent to the road. Voigt
wants the survey peg restored. This requires a certain amount of resurveying of Voigt s property which EPC agreed to do.
b. Mr. Si utaulalovasa Galumalemana of Vailoa Faleata requested compensation
for his crops and ornamental plants that were affected and removed resulting
from underground of 22kv and 33kv cable works along Tulaele Road adjacent
to Fuluasou Substation.
Addressing Grievances
Regarding Voigts complaint, EPC agreed to hire a surveyor to resurvey property in order to locate and build a new survey peg on Voigt s property. All expenses
will be covered by EPC. PMU is calling bids for this survey work.
EPC already settled and paid compensation for crop damages to Galumalemana.
Full amount for crop damage was paid in January 2015.
Page 11
Telephone: (685) 65400
Facsimile: (685) 23748
E-mail: [email protected]
Website: www.epc.ws
PO Box: 2011
Electric Power Corporation
3. Supervisory Control and Data Acquisition.
No complaints received but only an issue related to a family in Vaigaga village cutting
a tree on their property and fell on EPC overhead fiber optic cable to EPC s Vaitele Power Distribution and Store breaking the cable attachment and cable fell to the
ground. Fortunately the fiber cable was not damaged. EPC reattached cable to the
pole. EPC s telecommunication system using this cable was not affected. Eventually,
EPC will underground this fiber ones road extension is completed. Fiber conduits
are laid as part of road extension work. Furthermore, families are asked to contact
EPC if they have any trees close to power lines and fiber cable to be cut down. EPC
offers to cut them down at no cost to families.
4. Hospital Feeder Stage 2
There are more and more developments for township improvements in Apia. vEPC
was consulted by Samoa Land Transport Authority (LTA) of their plan to build new
road drainage along section of road where EPC already laid power and fiber optic
cables. This is area in Savalalo and Fugalei. There were some of underground fiber
and power cables affected from these road improvements.
Addressing Grievances
The contractors for these new developments in Apia township had being informed
that before they execute any civil works, it is priority that their working environment
is safe, electricity cables have no second option for anyone, and so they must first
request EPC for a representative to identify EPC services that maybe available in
their vicinity of work. EPC will also make sure to lay future cables at right depth
below road, which is 2.5 meters, to minimize being affected in future road
improvement work.
GRIEVANCE REDNESS MECHANISM
EPC have enquiry boxes at each office centre and outlet where the public can submit
complains or suggestions. There is also the assistance from the customer complaint
center which opens 24 hours whereby the public is advised to contact if ever complaints
arising regarding any aspect of electricity services and projects especially during
afterhours and busy business hours. The call center numbers 65500 and 65502 have
also been advertised on media and EPC website for public awareness.
PMU has a Grievance Redress Mechanism to address complaints regarding PSEP
projects as well as EPC Projects. All records of complaints and responses are kept and
Page 12
Telephone: (685) 65400
Facsimile: (685) 23748
E-mail: [email protected]
Website: www.epc.ws
PO Box: 2011
Electric Power Corporation
will be documented continually for future reference especially with regards to lawsuit
cases. The mechanism is equipped with a step-by-step procedure to receive, register
and track all grievances concerning environment and social issues. A grievance form
has been created and will be used to address complaints for each PMU projects.
Complaints can be filed in person, via email or via a letter to EPC.
The public communication officer is responsible for receiving complaints, facilitating,
tracking and reporting on grievances and their resolutions.
CONCLUSIONS
PMU/ESU concludes that no health, social, safety or environmental issue has been
witnessed or occurred during this period.
All the necessary mitigation measures were followed by in addressing safeguard issues
and are compiled for references with the exception of the issue with the family peg lost
from works related to underground, which ESU had issued to contractors persuading
them that EPC will be paying for this task upon completion.
PMU continue to oversee and highly prioritize concerns from the public in relations to
PSEP projects, and act as soon as practical to address, minimize and solve the nuisances.
Prepared by Environment and Social Unit
Reviewed and endorsed by:
Fonoti Perelini S. Perelini
Project Manager
Project Management Unit