ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY...

164
1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services and Social Resilience Project (MSSRP) Date: May 2019 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Transcript of ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY...

Page 1: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

1

ENVIRONMENTAL AND SOCIAL IMPACT

ASSESMENT STUDY (ESIA)

Governmental Complex in Ramtha Municipality

Irbid Governorate

Municipal Services and Social Resilience Project

(MSSRP)

Date: May 2019

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

2

No.

Chapter 1: Executive Summary

1.1 Introduction 6

1.2 Project Objectives 6

1.3 ESIA Methodology 6

1.4 Legal and Institutional Framework 7

1.5 Baseline Data and Project Existing Environment 7

1.6 Environmental and Social Impacts 8

1.7 Analysis of Sub-Project Alternatives 9

1.8 Environmental and Social Management Plan –ESMP 9

1.9 Environmental and Social Mitigation Measures 10

1.10 Environmental and Social Monitoring Plan 27

1.11 Public Consultations 27

Chapter 2: Sub-project Description 2.1 Sub-project objectives 32

2.2 Location 32

2.3 Project Size & Land Requirements 33

2.4 Land Ownership & Current Land Use 33

2.5 Project Activities &Expected Equipment 35

2.6 Environmental & Social Assessment and Review Process 37

Chapter 3: Existing Environment and Baseline Data Geology & Soils 3.1 Water Resources & Hydrogeology 39

3.2 Air Quality & Noise level 39

3.3 Flora & Fauna 39

3.4 Wetlands & Protected Areas 40

3.5 Population 40

3.6 Services & Facilities 40

3.7 History, Heritage, and Touristic Sites 40

3.8 Climate & Topography 41

Chapter 4: Legal and Institutional Framework

4.1 Jordanian Environmental Regulations 43

4.2 Jordanian Environmental Impact Assessment Policy 43

4.3World Bank Environmental and Social Safeguards Policies 43

4.4 Gap analysis between Jordanian Legislations and the WB Policies 44

Chapter 5: Environmental and Social Impacts 5.1Scope of Impact Assessment and Methodology 47

5.2 Potential Impacts during Construction Stage 49

5.2.1 Removal of Existing Debris and Standing Trees 49

5.2.2 Impact of Site Leveling and Excavation Works 49

5.2.3 Impact of Constructing the Building Floors & Main Components 50

5.2.4 Potential Impact during Finishing & Indoor Works 50

5.2.5 Potential Impact on Social &Economic Conditions 51

5.2.6 Potential Social Impacts 51

5.3 Potential Impacts during Operation 52

5.3.1 Impact of Waste’s Generation& Poor Disposal Plan 52

5.3.2 Safety of Workers & Employees 52

5.3.3. Impact on Health Condition of Employees 53

5.3.4 Impact on Landscape &General View of Site 53

5.3.5Impact on Soil & Green Spaces 53

5.3.6 Potential Impact of Materials Handling& Storage 53

TABLE OFCONTENTS

LIST OF FIGURES, TABLES,, AND ABBREVIATIONS

Page 3: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

3

5.3.7 Impact on Socio-economic Condition 53

Chapter6: General Analysis of Project Alternatives 6.1 Sub-Project Location Alternatives 55

6.2 ‘No Project’ Alternative 55

Chapter 7: Environmental & Social Management Plan ESMP, and Mitigation Measures

7.1 General 58

7.2 Responsibilities & Procedures 58

7.3.1 Mitigation Measures During Preparation & Construction 80

7.3.2 Mitigation Measures During Operation Stage 89

Chapter 8: Environmental and Social Monitoring Plan

8.1 Monitoring Arrangement 107

8.2 Reporting 107

Chapter 9: Social Study 9.1 Social Consultation Program 114

9.2 Findings of Social Study & General Recommendations 115

Page 4: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

4

LIST OF FIGURES

Figure No.

Figure (1): the location of the proposed land using the Department of Land And Survey website 10

Figure (2): Front view of the expected sub-project 41

Figure (3): The locationof the proposed landusing the Department of Land And Survey website 42

Figure (4): View of sub-project construction area 44

Figure (5): Electrical convertor in the land of the sub-project 44

Figure (6): Bushes and existing species in the site 50

Figure (7): ESIA Community Consultations 136

Figure (8): Letter of Designation from Department of Land and Survey to Ramtha Municipality 154

Figure (9): Community Consultations for the Design of the sub-project 158

Page 5: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

5

LIST OF TABLES

Table No.

Table (1): ESMP Detailed Tables. 14

Table (2): Sub-Project’s Land Basic Information 43

Table (3):Sub-Project’sActivities and Equipment

46

Table (4): Environmental and Social Assessment and Review Process 47

Table (5): Safeguards Policies of the Bank 54

Table (6):E&S Impact Assessment Matrix for Constructing a New Governmental Complex in Ramtha

Municipality

59

Table (7): ESMP Detailed Tables 72

Table (8): Mitigation Measures Detailed Plan 107

Table (9): Detailed Monitoring Plan 129

Page 6: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

6

Abbreviations

MSSRP Municipal Services and Social Resilience Project

MOMA Ministry of Municipal Affairs

CVDB Cities and Village Development Bank

WB World Bank

PMU Project Management Unit

ESMF Environmental and Social Management Framework

ESIA Environmental and Social Impact Assessment

GRM Grievance Redress Mechanism

OP Operational Policy

PAPs Project Affected Persons

PMU Project Management Unit

RAP Resettlement Action Plan

RPF Resettlement Policy Framework

ARRAP Abbreviated Remedial Resettlement Action Plan

MoEnv Ministry of Environment

Page 7: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

7

Chapter 1

Executive Summary

Page 8: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

8

1.1 Introduction This Environmental and Social Impact Assessment ESIA is conducted for Ramtha municipality sub-project,

the construction of a governmental complex, under the Municipal and Social Resilience Project funded by

a number of donors and administered by the World Bank. More than five years of violent conflict in Syria

has resulted in massive movements of people within Syria, as well as into neighboring countries. The

displacement crisis has put enormous pressure on basic service delivery and social resilience in Jordan.

The latest Jordan census records of 2016 indicate that Jordan is currently hosting nearly 1.3 million Syrian

refugees, 80 percent of whom live in host communities. This number represents about 13 percent of

Jordan’s population. During the first two years of the Syrian refugee crisis, the international community’s

response focused almost exclusively on providing humanitarian assistance to the refugees, including to

those who fled to Jordan. As the numbers of Syrian refugees living in host communities in Jordan gradually

increased, the country’s systems and structures have been strained, adding pressure on basic service

delivery in water, sanitation, electricity, solid waste management, and overstretching health and education

systems. Relevant to this, through the large influx into cities and its effects on service delivery, social

tensions are increasingly common in many communities.

The Government’s response has shifted from an emergency framework to longer-term resilience and

economic stability. In response to the growing pressures, the GOJ committed the Jordan Compact in

February 2016 which put forward a more holistic framework for addressing the crisis, that:

(i) addresses the wellbeing of the Syrian refugees while responding to the immediate needs of the host communities; (ii) supports Jordan’s growth agenda and longer-term resilience and economic stability. To help translate the commitments under the Jordan Compact, the GOJ has requested the World Bank to extend and scale up its support and prepare the Jordan: Municipal Services and Social Resilience Project (MSSRP). The project is a continuation and scale-up of an earlier emergency program, and has the project development objective (PDO) to support Jordanian municipalities affected by the influx of Syrian refugees in delivering services and employment opportunities for Jordanians and Syrians. The project is aligned with the Government’s commitment under the Jordan Compact, and aims to (iii) strengthen resilience of local governance systems and communities to crisis with a particular focus on social cohesion, and to create short-term employment opportunities in host communities. Based on the construction plan of the proposed governmental complex - the sub-project - this building consists of seven floors; the ground floor is proposed to be used as a multi-purpose hall to be utilized by the municipality for public meetings, and to be also let for the community to organize events, social occasions, etc… Such a facility does not exist in the city. The other six floors are proposed to be used:(i) to host the Municipality offices, as the municipality is currently renting some offices in one mall,(ii) and to host other governmental agencies that will be renting the space inside the governmental complex. Renting this space to government offices will combine the objective of bringing critical government services in one place for the benefit of the community, and also providing a source of revenue for the municipality (from rental fees).

1.2 Sub-project Objectives The sub-project main objective is to construct a governmental complex in Ramtha municipality in order to minimize the time and effort on citizens in achieving their paper work when these government offices are grouped in one place. In addition to that, the Municipality would move its offices to one of the floors, hereby creating savings that replace the rental fees being paid now from rental of the Municipality offices. .Moreover, this sub-project will provide an extra source of revenue to the municipality from renting the complex spaces to the government offices. This sub-project was ranked as the top priority among the various groups representing Ramtha community in the community consultations held earlier in the municipality as part of the requirements under MSSRP.

Page 9: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

9

1.3 ESIA Methodology

The sub-project location and area physical systems are studied in detail within this document. Collection of data included gathering available information from the technical reports and drawings draft of the building. In addition, information like climate and geography were collected from different sources like the official relevant websites. Moreover, the ESIA included conducting field visits and making visual observation for the site and data on existing debris, economical activities, and project area facilities were gathered and included in this document. As stated before, the sub-project was selected through conducting several community consultation sessions and was ranked number one priority for the citizens of Ramtha municipality. Screening forms for the sub-project were filled, and they indicated that the sub-project would have some environmental and social impacts during construction. On September 13th, 2018, a field visit was conducted by the PMU Safeguards specialist and the Feasibility Study specialist, to observe the site and its surroundings. According to baseline studies and field visit, two major problems were identified in the site of the project: 1. An existing kiosk owned by a number of Project Affected Persons (PAPs), for which an Abbreviated Remedial Resettlement Action Plan ARRAP was prepared and approved. 2.An electrical convertor nearly on the edge of the land, for which the design of the building was slightly modified to avoid any contact with the convertor. On October 2nd, 2018, another field visit was conducted to the municipality, by the PMU Safeguards specialist and the supervision engineer, to make sure that the design was modified in order to deal with the problem of existing electrical convertor. The engineering design also took into consideration accessibility of people with special needs and appropriate waiting spaces. Preliminary scoping of the site, based on the field visits, indicated the potential occurrence of some impacts that are considered site-specific and could be mitigated through applying an Impact Assessment Matrix, which is part of the ESIA document. Potential impacts include: - Impacts on natural Environment: such as air quality, soil compaction, agricultural lands, noise and vibration. - Socio-Economic Impacts: such as resettlement, job creation, health and safety. Those impacts are detailed in the Assessment Matrix, according to the sub-project activities, and determine whether the impact is negatively low, medium, high, or is positive. An environmental and social management plan (ESMP) was prepared to present all possible impacts of the sub-project construction and the appropriate mitigation measures for those impacts. Consultation sessions were also held for the community to have their feedback on the sub-project selection and implementation, as well as on the proposed design of the complex with the latter having the objective of ensuring the community, more specifically females, youth, and other marginalized groups, such as disabled persons, are able to optimally benefit from the proposed complex spaces and services. .

1.4 Legal and Institutional Framework The legal and institutional framework of this assessment depends on investigating and including national regulations and the World Bank policies that relate to environment and social safeguards. Jordanian Law of Environmental Protection, No. 52 of 2006 that went into effect on Oct. 16, 2006and the Bank operational policies are the legal foundation of this work and formed the general framework of this study. Actually, this sub-project –is under category B for World Bank, which is equivalent to category 2 in the Jordanian Environmental Law. The World Bank Operational Policy OP 4.01 on “Environmental Assessment” is triggered for this project. The “Involuntary Resettlement Policy OP/4.12”is another policy that is triggered for his project taking into

Page 10: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

10

account the project’s potential unconformity with existing regulations and possible impact causing any resettlement due to sub-project implementation for which an ARRAP document was prepared. In addition, the ESIA refers to some clauses in the FIDIC for Works, that are considered relevant to regulations and articles arranging construction activities and identifying required documents and construction work permission and safeguards issues. Chapter II, General Conditions, Section 4, Contractor Responsibilities, and Chapter III, Particular Conditions, as well as the Supplementary Particular Conditions, contains specific clauses that are directly related to applying safety measures in the site.

1.5 Baseline Data and Sub-Project Existing Environment The sub-project land is almost located in the middle of Ramtha city with 80 m along the main street of Alsakhrat Almusharifa. The availability of public transportation raises the strategic importance of the proposed land, which was assessed as the most suitable land for constructing such a complex. The municipality owns other lands but those are far away from the center of the city and hence are not appropriate for the proposed scheme. This specific site had been designated since 2011 for this purpose, and citizens would only need one transportation to get there minimizing the cost and effort. The existing Governmental agencies are spread out in different locations around the city in which travel time for citizens, travel costs, as well as traffic jam could be a serious problem. The location of the proposed land is also near very important public buildings that include two schools, a healthcare center, and a Public Park. The coordinate of the land is (32.55905815, 36.00076154).The selected Governmental Complex lies on a land in Abu AlBasal AlSharqi area, and is surrounded by the following governmental buildings: 1.Comprehensive health center. 2.Musab bin Omair Secondary School for Boys. 3.Ramtha Health Directorate. 4.IbnHazm Elementary School. 5.Public Park.

Figure (1): the location of the proposed land using the Department of Land And Survey website

In the sub-project site, there are no protected areas or unique species to be included in this report. Whereas, pollution sources that may deteriorate air quality or disturb noise normal levels are not found. The only activity that might be mentioned here is the traffic movement at AlSakhra al Mosharafa Street the nearest road to the sub-project area. Actually, there are no measures for emissions level caused by traffic,

Page 11: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

11

but air and noise levels are estimated to be within acceptable limits. Moreover, current economic activities are simple and they are not expected to cause significant impact on air and noise levels. Groceries, commercial shops, and a number of public entities including two schools, Directorate of Education, Directorate of Public Health, a comprehensive health center and an amusement park, are the main activities in the surroundings of the sub-project area. In addition, there are no touristic, cultural heritage assets in the sub-project area that might be affected by the sub-project's activities. As an urban area, services and facilities like water and sanitation networks, telecommunications, health services, and electricity connectivity are available in this location. The new building will be owned and operated by Ramtha municipality.

1.6 Environmental and Social Impacts All potential impacts of sub-project preparation, construction, and operation stages are deeply investigated in this assessment. Both positive and negative environmental and social impacts are addressed as well. The analysis under this ESIA indicates that this sub-project will cause temporary and localized environmental impact especially during construction stage. Those were already explained to the communities in the community consultations mentioned earlier. Moreover, social and economic long-term benefits of the sub-project are high compared to the current situation for the municipality, while concerns like creation of conflicts, land acquisition, resources competition, and project failure arenot evident in this project.Small scale socio-economic impacts to operators of a small kiosk on the subject site were evaluated and compensated through an Abbreviated Remedial Resettlement Action Plan that is publicly disclosed.

Generally, the ESIA investigation indicates several potential impacts of this sub-project as the following:

During Construction Stage

1. Temporary deterioration of Air quality caused by increasing dust concentration and small emission produced from work place involved trucks; 2. Temporary increase in noise levels due to construction activities and noise of involved equipment; 3. Temporary accumulation & scatter of waste during construction activities; 4. Temporary obstruction of traffic & mobility pattern; and 5. Temporary exposure to work place hazards and accidents. 6. Temporary community exposure to hazards and accidents During Operation Period 1. Mismanagement of waste &poor disposal techniques; 2. Negative visual impact; 3. Normal wear and tear and deterioration of facilities, including wall paint, doors, toiled facilities, etc... 4. Lack of following up and implementing workplace safety measures; and 5. Poor storage of materials and equipment.

1.7 Analysis of Sub-Project Alternatives Sub-project alternatives’ investigation shows that the selected location, construction activities, construction materials, involved equipment, and social & economic aspects comport with the ESIA study considerations to construct this sub-project in this exact location. As it was stated before, Ramtha municipality offices are rented within a commercial mall, and this sub-project shall give the municipality a chance to have its own offices while using the rent paid in some other useful infrastructure sub-projects for better services of the citizens. Extra revenue will also be available for the municipality budget from renting other governmental entities in the complex, as well as using the multi-purpose hall which is intended to be built in the ground floor for different occasions. The social and economic benefits of the sub-project implementation are expected to be high.

Page 12: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

12

Alternatives were considered to use another piece of land owned by the municipality, but was rejected by the municipality, as the land of the sub-project was already designated for the construction of this governmental complex and is highly favored by Ramtha citizens due to its strategic location in the center of the city, which was clearly shown in the Community Consultations conducted earlier when prioritization of sub-projects was done. Hence, this document presents the current alternative as this site reflects high Socio-economic benefits and its temporary and localized environmental impact can be controlled through the implementation of mitigation measures included in this document. Other reasons for choosing the sub-project land include: - The municipality staff are currently renting a building on the main street that connects Amman with

Damascus, for a total amount of 39,000 JDs (almost US$56,000) per year. The intended governmental

complex project shall have offices owned by the municipality, so as to save the amount of rent when they

move there.

- The sub-project is supposed to generate revenue for the municipality and provide one location for the

citizens in Ramtha, hence minimizing the time and effort needed to accomplish any governmental paper

work for the citizens in Ramtha. Parking space is also planned to provide more convenience to citizens

and to employees working in this complex.

- Providing employment opportunities and providing better municipal services are core objectives of

MSSRP, which is the key purpose of building this governmental complex in Ramtha municipality.

The “No Project Alternative” means that all the above mentioned advantages would not be achieved.

Thus, the land alternative provided by the municipality is considered most suitable for the sub-project

construction.

1.8 Environmental and Social Management Plan –ESMP The ESMP is an effective means to manage and monitor the implementation of the mitigation measures for the potential negative impacts of the project. Generally, ESMP consists of five components;

• Potential impact of the project

• Mitigation measures

• Monitoring activities

• Institutional arrangements & responsibility

• Implementation cost & required budget. All those contents are detailed in the ESMP Table (1) below. These tables are prepared to cover construction and operation stage of the project and, therefore, to guide the contractor and responsible agency how to apply mentioned measures & treatment methods. The cost of implementing the construction ESMP will be borne by the contractor and will be incorporated into the construction budget. The cost of supervision of the contractor’s performance will be borne by the Municipality. The cost of implementing the measures during operations phase will be part of Ramtha municipality responsibilities to include it within its maintenance and monitoring plans over operations phase. During this period, short training for employees is recommended to follow measures and procedures included in this document.

Overall, implementation of the ESMP is the responsibility of the contractor and the subcontractors who

implement the work activities in accordance with their contractual obligations, along with the municipal

engineer who provides oversight against the contractual requirements. The contractor and municipal

engineer must have appropriate environmental and health & safety qualifications and will be supported by

the Safeguards specialist in the PMU. . Work’s methodology and monitoring procedures are explained in

detail within ESMP’s tables and will be defined in the contractor’s site-specific ESMP to be prepared by

the contractor and approved by the Municipal Engineer and PMU Safeguard Specialist.

Page 13: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

13

Regular Construction Progress Reports prepared by the Contractor and submitted to the Municipal Engineer for review, shall contain a section on Environmental, Social and Health and Safety. . An ESHS section of the Progress Report, as well as site monitoring reports will be prepared periodically by the PMU in every site visit conducted and will be revised by the safeguards specialist in the PMU, and submitted to the World Bank (WB) team who will follow up progress of the sub-project.

1.9 Environmental and Social Mitigation Measures Environmental and Social Mitigation Measures (ESMM) for the potential impacts of the proposed sub-project consist of short-term procedures and long-term precautions. For instance, preparation stage may require reviewing and making slight correction on the design in order to incorporate safety requirements for office buildings and public constructions. Actually, such additions may reflect on quantity tables, work contract, and maybe on the total cost of the project. This is just a case if such considerations have not been addressed on project designs. Concerning preparation and construction stage, it is the most expected phase to make adverse impact on surrounding environment despite its short implementation time in comparison with sub-project designed age. Therefore, ESIA focuses more on this critical period and suggests particular mitigation measures to minimize and control potential impacts. Potential impacts and mitigation measures are listed, but are not limited to those in the table below. The contractor is required to prepare a site-specific ESMP (includes health and safety) as well as Traffic Management Plan and these plans will be approved by the Municipal Engineer and the PMU Safeguard Specialist:

Page 14: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

14

Table (1): ESMP Detailed Tables

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

Preparation, Excavation,

and General Waste of

Work Site

1. The

contractor must

follow & implement

waste

management

measures included

within ESMP

documents

whenever needed.

2. Re-use of

construction waste

within the work

site, if possible.

3. Collection

of undesired

construction waste

and debris in

specific collection

points in the site

within special

receptacles.

Selection of waste

collection site

must be pre

agreed with the

site supervisor

engineer.

• There

must be a

previous list of

expected waste

during

construction

stage based on

used materials

and involved

equipment.

Decision must

be made about

the most critical

waste to be

monitored

• Waste

collection points

should be

clearly identified

before

launching the

construction

work

• Determin

e which waste

can be left and

The Municipal Engineer will monitor works on a regular basis and prepare weekly progress reports

The

environment

al specialist

in CVDB/ the

Municipal

engineer

- Cost of carrying out

Mitigation Measures by the

Contractor would be already

included in the Bill of

Quantities according to the

different items of

construction, and shall be

monitored by the municipal

engineer and the Safeguards

specialist in CVDB.

Page 15: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

15

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

4. Constructio

n work may be

avoided during

rainy periods in

order to avoid

transmitting of

waste and debris.

Whereas all work

materials must be

covered with

proper sheets.

5. Scatter of

waste should be

avoided. While

workers temporary

room in the site

should be supplied

with waste

garbage and

disposal of such

waste must be

done based on

waste type and

quantity, and in

cooperation with

municipal

engineer.

6. Disposal of

all waste must be

done in the landfill

and follow

re-used on site

and which must

be taken

• Monitorin

g form to

include date,

contractor

abidance by

Health and

Safety

measures, any

excavations

found in the site

and any

emerging

matters to be

filled regularly

by the site

engineer and

spot checks by

the

environmental

Safeguards

specialist in

CVDB.

• Monitor

and inspect the

contractor

Page 16: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

16

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

instruction of

construction

permission and

landfill

management

requirements.

7. Liquid

waste like water

needed during

construction

should be

collected on a

separate tank and

water should not

accumulate on

site. Besides,

drainage of water

to outside area is

forbidden.

compliance with

ESIA report

• Recordin

g all work sites,

activity location,

date, time, work

expected period

in each site

• Transpor

tation line and

times of waste

disposal must

be mentioned in

the report, in

collaboration

with the Traffic

Management if

necessary

• Review

all documents

relating to waste

management

and disposal

including

construction

permission

• All

hazardous

Page 17: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

17

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

waste and

disposal

methods should

be mentioned.

Whereas, time

to occur and

sites should be

explained

• Consider

climate

influence and

waste scattering

• Identifyin

g used

equipment,

construction

materials,

trucks, volume

of water

requirement,

and manual

work tools

• Decide

about PPEs

required within

each activity of

waste disposal

and handling.

Page 18: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

18

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

• Record

any spill,

accidents,

waste poor

management

during

supervision

visits

• Counting

of workers &

trucks number

and identify their

different waste.

Cost of disposal

must be

mentioned

• Make

photographic

documentation

Soil Compaction &

Contamination

1. Surface

soil can be kept

aside to be used

later within green

spaces

2. Trucks and

involved vehicles

should follow

specific &

identified truck

ways

• Make

sure that soil top

surface has

been removed

aside to be used

later on for

green spaces

purpose

• Identify

the most sites

The Municipal Engineer may follow up within 1-2 weeks

The

environment

al specialist

in CVDB/

Municipal

supervisor

engineer

Page 19: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

19

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

3. Spill

accidents must be

prohibited. If any

spill accidents

occurs, it should

be cleaned

immediately and

collected in

separate disposal

container.

subject to soil

compaction or

contamination.

And follow

mitigation

measures to

maintain such

impact

• Record

soil collection

containers and

available

garbage in work

site

• Monitorin

g identified

working paths

and workers

compliance to

avoid soil

compaction

• Refer to

ESIA and make

photos

documentation

of soil condition,

as soil tests

must be done

by the

Page 20: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

20

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

contractor in the

design phase.

Air Quality & Noise

Levels

1. Spraying

water on

foundations before

excavation work

takes place. Water

must be used

when there is raise

up of dust like

sand lifting and

handling

2. Spraying of

water may take

place every day to

prevent dust

concentration.

This action might

be required in

many places in

work site

3. Dust and

fine particles

should be always

• Define

air pollution

sources, type,

locations,

remaining time,

weather main

drivers

• Ensure

water is used to

maintain dust

concentration

and scattering

of fine articles

• Ensure

all equipment

and trucks are

in a good

condition and

emission does

not exist

The Municipal Engineer will monitor works ion a regular basis

The

environment

al specialist

in CVDB/

Municipal

supervisor

engineer

Included above

Page 21: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

21

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

within low level

during all

construction

activities

4. Transportat

ion trucks are

preferably

selected based on

motor

performance and

low emission or

filtered exhaust

presence. Old

vehicles & trucks

with high

emissions

shouldnot allowed

to be used

5. Truck

engine must be

switched off when

on site.

6. Noise

barrier should be

constructed

around work area

and should be

high to prevent

noise transmission

and taking

neighboring

• Identify

noise

disturbance

sources,

duration, time,

most affected

group, number

of affected

workers,

mitigation

requirement

(supply workers

with earplugs

when

necessary)

• Make

sure that noise

prevention

measures are

applied. For

instance, noise

barrier and

noise protective

equipment, and

to abide by

allowed time to

work in during

the day.

Page 22: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

22

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

facilities attention,

in particular

nearby school

students.

7. Noise

within work site

can be minimized

by providing

workers with

special equipment

like ears protective

equipment and

masks. Workers in

stone quarry

location must be

provided with

PPEs as well.

8. Transportat

ion of materials

and waste might

be scheduled

during the

afternoon period in

order to avoid

disturbing

neighboring

facilities’ users, as

working hours are

restricted between

6:00 p.m. and 9:00

a.m., and noise

Page 23: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

23

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

levels are NOT to

exceed 55

decibels during the

day and 45

decibels at night.

Transportation of Materials & Storage

1. Materials transferred to the site must be tight well to the truck and covered by an appropriate sheet. 2. Sand is liable to scatter during truck movement. So, water must be sprayed on it and it should be covered by appropriately. 3. Truck back door must be closed during transportation. 4. Materials and equipment storage location must be agreed previously with site engineer. It must not be far from work site location. 5. Separation of materials based

• Identify materials temporary storage locations and make sure such locations are not disturbing construction activities. Also, they must be away of truck & vehicles ways

• All transported materials & waste should be covered with proper sheet. And scattering of waste must be avoided

• Drivers should follow safety procedures when making this task. While all materials

The Municipal Engineerwill monitor activities on a regular basis and as needed.

The environmental specialist in CVDB/ Municipal supervisor engineer

Included above

Page 24: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

24

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

on their nature and type. 6. Flammable or oil components materials and machinery equipment should not be aggregated with construction or organic materials. Materials on storage location must be covered with suitable plastic wrap and surrounded by short stones wall to prevent weathering and rainfall effects

should be tight well to the truck

• Water might be used to prevent scattering of sand during transportation

• Identify truck routes, truck condition, materials type, applied safety procedures.

• Temporary storage location must address protection against rain & weather conditions. Materials should be covered and surrounded by short traditional wall and drainage channels

• Materials should be stored in compatible group. Flammable materials should

Page 25: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

25

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

be separate from other construction materials Smoking is not allowed in storage locations

Health and Safety Impacts

. Contractor

Prepares a site-

specific ESMP

(includes H&S) to

fulfill contractual

obligations to

protect workers

and the public and

to comply with

Jordanian Laws

2. The contractor is required to have a code of conduct covering worker interactions with the community, including children. The Code of Conduct is applicable to all of its workers as well as subcontractors. 3. All workers

including

subcontractors,

are required to

• Monitor implementation of the contractor’s plan that defines& anticipates work potential hazards, health hazards, and work place safety measures.

• Make sure all required PPEs are available and workers are assigned based on physical condition capacity

• Work site must provide protection against any risk and work hazards. Any

The Municipal Engineer will follow up on a daily basis

The environmental specialist in CVDB/ Municipal supervisor engineer

Included above

Page 26: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

26

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

acknowledge that

training in the

code of conduct

has been

received.

1. 2. The location of electrical power line and cables must be determined before digging and excavation work takes place (in our case, the Electric Convertor in the site should by isolated by a wall to avoid any accidents) 3. Work sites must be clean and orderly. While all site surface must be kept dry. Otherwise, proper means might be taken to assure the surface is slip-resistant. 4. Items and materials that are not required during work hours must

indicator of potential injury exposure must be recorded

• Check out scaffolds, ladders, floors, openings, and machinery used in this construction

• Inspect any potential threat of involved equipment on project’s components. In addition , equipment must be checked up to make sure they are in a good condition and they are safe to be used

• Inspect the existence of firefighting agents and workers ability to handle fire extinguishers. Make sure First Aid Box is on site

Page 27: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

27

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

be removed from the work site 5. PPEs are necessary during all times of work. Hardhats, proper safety shoes, inspiration masks, and ear protective tools should be worn by workers. Moreover, safety devices during indoor work like electrical connection, painting, and plastering work are all required. 6. Storing debris and waste safely and removing them immediately from the construction site. 7. All construction safety requirements must be addressed in this project. Workplace injury must be avoided and the contractor is responsible to follow up safety

• Ensure the availability of PPEs for handling chemical & painting substances. While such materials should be labeled with explanation about its contents and use requirements

• All electrical connections and involved devices must be evaluated and protective measures of applying those devices must be attached to product boxes

Page 28: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

28

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

procedures, as well as providing basic medical services and supplies to workers 8. Workers must be careful when working near floor and ground openings. While, openings should be marked and easily identified by all workers and drivers. 9. Bending & forming of construction steel must be done with care and high safety measures application. Suitable manual tools and safety protective agents must be applied during this work 10. All aisles and passageways must be identified and marked. 11. Lifting and moving of heavy objects should be done by

Page 29: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

29

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

mechanical devices. 12. Ladders & scaffolds must be checked out each time before climbing. Damaged ladders & scaffolds should never be used. 13. If metal ladders & scaffolds are to be used, they must be checked up on corrosion and they must be isolated from communication with any electrical connections 14. There must be rain clear paths and proper drainage system to avoid accumulation of rain water on site. 15. All electrical power supplies and connections must be grounded while dangerous voltage and current must be isolated by

Page 30: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

30

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

covers & enclosures. 16. All painting and chemical containers must be labeled and workers must be aware how to handle those materials. Leaking containers should not be accepted while workers should not pour paint remaining onto ground. There must be sealed containers to collect and dispose such substances. 17. There must be a washing tank on site to wash manual and work tools at the end of each working day. 18. Firefighting equipment and fire extinguishers should be available while workers must be trained to handle fire prevention cylinders.

Page 31: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

31

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

19. Smoking is not allowed at site. Disposal of cigarettes may lead to break out of fire. 20. All drivers and workers must be trained about environment and safety measures

Safety of Transportation 1. All drivers

should drive safely

2. Transportat

ion’s instruction

and signs must be

posted on site,

and the contractor

shall ensure that

roads remain open

to traffic during

construction

activities.

3. Drivers

must follow a limit

speed. 30-45 km/

h might be a good

acceptable limit.

4. Drivers

must avoid driving

and transporting

materials & waste

during rush time.

• Make

sure drivers are

driving safely

and following

traffic safety

measures

• Ensuring

their compliance

towards

preventing

waste scattering

• Check

out trucks and

vehicles applied

speed based on

mitigation

measures

recommendatio

n and record

any violation on

this regard

The Municipal engineer will monitor works on a regular basis.

The environmental specialist in CVDB/ Municipal supervisor engineer

Contractor shall submit a Traffic Management Plan to be approved by the municipal engineer and the Safeguards specialist in CVDB,

Page 32: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

32

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

5. Vehicles

must follow

specific routes and

avoid obstructing

traffic

6. During

transportation all

transported

materials and

equipment must

be tight well to the

truck and waste

scattering is not

accepted

7. Trucks &

vehicle must be

switched off when

on site

8. Drivers

should avoid

passing near to

flammable source

and smoking is not

recommended

when driving

9. All

materials should

be covered and

sand may require

spraying water

• Ensure

all requirements

mentioned on

mitigation

measures table

are followed

accordingly.

Page 33: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

33

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

before covering

with a sheet.

Management of Workers temporary room in the site

1. Management of workers room and all potential waste must be maintained through direct supervision of site engineer and the Environmental specialist in CVDB. 2. Room must be established on free space area and should be near project’s location 3. It must be supplied with solid waste storage tank that must be connected to the local network or to separate sink. Design of this system and disposal process should be discussed & agreed with municipal supervisor engineer.

• Ensure the room is equipped with suitable wastewater system and connected to local network or waste is disposed regularly through a special tank

• Identify waste produced from the room and number of residents

• Ensure hygienic condition of the room and the supply of adequate water sources for cooking and washing purposes

• Make sure workers are not using facilities of surrounding

The Municipal Engineerwill follow up on a regular basis.

The environmental specialist in CVDB/ Municipal supervisor engineer

Included above

Page 34: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

34

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

4. If kitchen to be included in this container, there must be gray tank to collect water of kitchen activities considering use of water for existing trees and nearby green spaces. While organic waste should be collected and disposed of outside the site in designated garbage containers. 5. There should be a temporary tank within the room area to be used for washing purpose.

6. All safety procedures of temporary establishment must be taken into account when constructing this room, such as adequate signage, lighting devices, barriers

employees and guards

• Identify waste disposal methods

• Identify garbage and containers used to collect waste.

Page 35: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

35

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

and safe drinking water.

Public Health of Workers 1. Work assignment is preferably given based on physical condition and worker’s capability 2. The contractor must cover health insurance of workers during work 3. Temporary room in the site must be comfortable and hygienic conditions should be monitored by site engineer 4. Workers are prohibited to directly communicate with chemical substance like painting materials. Therefore, workers with allergy should not handle cement and concrete materials.

• Make sure worker is assigned based on physical condition and qualification

• First aid box availability

• Medical checkup is recommended

• Workers with allergy to any of materials of construction should not be working and if there is simple allergy to concrete or cement materials then worker must not communicate with such substances

• Make sure all workers are health ensured by the contractor.

The Municipal Engineerwill follow up on a regular basis.

The environmental specialist in CVDB/ Municipal supervisor engineer

Included above

Page 36: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

36

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

5. Smoking must be avoided when on work 6. First Aid Box should be available during all construction phases.

Socio-Economic Development

1. Nearby residents and work site near houses must be given priority when selecting local labors, within the labor intensive arrangements to be implemented under MSSRP project. This activity shall be monitored by the ILO specialist in the MSSRP project regularly. 2. Workers should not disturb employees of nearby agencies. 3. The contractor must follow engineering design of the project and use entrances pointed by the site engineer.

• Ensure the involvement of local labors in this project and nearby residents and workers should be given priority when handling this work

• Workers must not disturb nearby residents and employees

• Purchasing materials required during construction from nearby markets and shops.

The Municipal Site Engineer will follow up on a regular basis

The environmental specialist in CVDB/ Municipal supervisor engineer

Included above

Page 37: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

37

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

4. Materials required for work activities can be purchased from near shops and markets unless such materials are not available in this area or their prices are not reasonable.

Workplace Hazards &

Health

1. All electrical and

electronic cables,

and equipment

must be designed

to provide

personal

protection while

cables must be

covered and

prove high

resistance to

electricity

fluctuation and

voltage variations

2. Parking area

should be

identified with

marked lines and

blocks

• There must be

always an

inspection of

the following;

• Storage room

and storage

materials

condition

• Fire

extinguishers

and validation

of hydrants

• All electrical

cable and

uncovered

connections

• Stability of

involved

supplies and

materials

Over project designed age

Municipality No Cost. Measures should be applied only

Page 38: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

38

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

3. Municipalit

y should make

regular inspection

of firefighting

extinguishers.

This action might

be conducted

twice a year to

ensure validation

of fire

extinguishers

4. Handling and

storing of

chemical

substances &

cleaning

materials should

follow official

safety & health

precautions

5. It is always

recommended to

equip

constructions and

office building with

First Aid Box

Corridors and

aisles must not be

• First aid box

availability

• Following

other

procedures

mentioned in

ESIA.

Page 39: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

39

IMPACT MITIGATION

MEASURES

MONITORING

ACTIVITY FREQUENCY

RESPONSIB

ILITY ESTIMATED COST

used for storage

purposes

Page 40: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

40

Implementation of mitigation measures during the construction phase is the responsibility of the contractor and cost of these interventions should be part of the Bill of Quantities tables and highlighted clearly in the special conditions of the contract prior to announcing project tender. Whereas, Ramtha municipality is fully responsible to carry out mitigation measures during the operation phase. In fact, these actions will not require a significant budget and such expenditures might be incorporated within the annual budget of the municipality. 1.10 Environmental and Social Monitoring Plan Ensuring and monitoring the application of mitigation measures during preparation, construction, and operation phase is the responsibility of Ramtha municipality. Direct supervision of construction activities will be carried out by the municipal engineer, under the direct supervision of the safeguards specialist in the PMU who will be in charge to monitor and record work activities by following monitoring activities included in ESMP. The safeguards specialist will monitor the application of environmental and social mitigation measures and result of monitoring activities should be reflected in quarterly reports according to contract conditions and site works performance. In case monitoring report indicates neglect or careless behavior from the contractor side, direct suggestions and correction actions should be delivered to the contractor and labors as well. Such recommendations should follow ESIA and ESMP suggested measures included already in these documents.

Entity Responsibility Frequency

MoMA PMU overall supervision on sub-project implementation

Monthly

CVDB / Safeguards specialist and supervision engineers

monitoring of environmental, social and health and safety performance of contractor and municipal engineer including implementation of site-specific ESMP application in the site

Weekly

Ramtha Municipality / Engineers Oversight of contractor Environmental, Social Health and Safety Performance in accordance with contractual obligations and site-specific ESMPand preparation of progress reports

Daily

Contractor Implementation of sub-project in accordance with contractual obligations and site specific ESMP (includes HS) Plan

Daily

1.11 Public Consultations

Public consultations for the proposed sub-project could be categorized in three parts: (i) community

consultations with the purpose of achieving/confirming the top prioritized sub-projects for proposal to

receive funding for implementation under MSSRP Municipal Grants allocation; (ii) community consultations

to discuss potential social and environmental impacts during the construction phase and proposed

mitigation measures; and (iii) a consultation meeting to discuss with the community, especially

marginalized groups including females, youth, disabled, Syrians, and others, the proposed design scheme

of the government complex. The latter was organized to ensure such community groups have the

opportunity to influence the final design of the proposed sub-project in a manner that provides them with

a more effective use and accessibility, and to take into consideration their specific concerns, if any.

• Community prioritization consultations:

Page 41: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

41

Sub-project selection included conducting consultations with several groups and potential direct

beneficiaries and end users of the sub-project. During the sub-projects prioritization process, seven

community consultation sessions were conducted in Ramtha municipality, which included youth, both

Jordanian and Syrian, women, people with disabilities, local council female members, and of course men,

with a total number of 333 participants in all the sessions. Afinal comprehensive public consultation session

was conducted in May, 2018 in which most of the participants voted for the Governmental Complex project

as their top ranked priority. Those detailed Community Consultation sessions can be found in the ARRAP

document which was prepared for the purpose of economic displacement of five identified PAPs, and in

Annex 1, as well.

• Consultations to discuss Impacts and Mitigation Measures:

On January13th, 2019 a specific environmental and social consultation session was conducted in Ramtha

municipality in which attendants from the private sector, government sector, NGOs, women and charity

associations were given a rapid and short explanation about general activities of this sub-project, its social

and economic benefits, the environmental and social impacts it may have and the suggested mitigation

measures to minimize those impacts.

Attendants expressed their enthusiasm and full support for the construction of the Governmental Complex.

No concerns were raised except for the quality of the engineering work to be done, which shall be closely

monitored by the supervising engineers whether from the PMU or municipality to get the best performance

and abidance to laws and regulations by the contractor. Attendants of the January 13, 2019 consultation

meeting included:

1. Ramtha mayor and municipal staff 2. Deputy Director of MSSRP 3. Safeguards specialist in PMU 4. Community Outreach specialist in PMU 5. Procurement and supervisor engineer in PMU

Summary Report and Attendance sheet is found in Annex 3.

The ESIA also included carrying out a visual observation for existing natural resources and economical

elements within the area of the proposed sub-project. Moreover, consultation contained documenting

positive feedback from the attendants and including their suggestions, comments, and concerns about this

sub-project. One of the main concerns indicated by the consultation participants was related to the

temporary potential environmental impacts during construction stage with some comments regarding the

traffic congestion that the sub-project may cause. The attendants suggested increasing the number of

parking spaces in the intended sub-project or making an agreement with the Ministry of Transport to

provide more buses for Ramtha municipality to minimize the usage of cars. Both of these

recommendations are under consideration by the Municipality. Mitigation measures to minimize potential

environmental impacts were explained in this consultation meeting, as well as a follow up dedicated

meeting which was organized on April 15, 2019, to discuss with the community members the design

aspects of the proposed governmental complex.

• Community Consultation to Discuss the Design aspects of the proposed sub-project

As mentioned earlier, a dedicated consultation meeting which was organized on April 15, 2019, to

discuss with the community members the proposed design aspects of the governmental complex. The

meeting focused on representatives of women organizations, youth representatives, and representatives

of disabled Societies and other community representatives, including elders. During this meeting, the

governmental complex design engineer provided an overview of the layout and objective of each of the

planned complex floors. The Project Management Unit also reiterated the potential social and

Page 42: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

42

environmental impacts described in the ESIA and proposed mitigation measures, to confirm awareness of

the community. Attendees renewed their overwhelming support to see this sub-project being implemented.

They also provided a set of recommendations under discussion by the Municipality and the design

engineer. Some of these recommendations included: (i) creating space for day-care services which would

benefit female staff in the building who are parents of children in the pre-school stage; (ii) providing a

separate entrance to the section hosting the public court (one of the government agencies that will move

into this complex), to protect the privacy of court users; (iii) provision of multiple staircases and multiple

elevators in different sections of the building, a recommendation which has already been considered in

the design; (iv) ensuring proper lighting exposure in the building, leaving no dark, or badly-lit areas; (v)

provision of facilitates for public use during waiting hours, including prayer rooms for males and females,

restaurant and food catering services. In addition, the meeting recommended reaching an agreement with

the construction contractor to include, as much as practically possible, unemployed engineers/graduates

from Ramtha to provide site supervision support. The meeting attendees and summary as well as the

answers and recommendations from both the municipal staff and the engineering design office are

provided in Annex 4.Those recommendations shall be taken into account, alongside technical and

financial considerations, through conducting documented meetings with the design office to modify any

potential changes in the final detailed design phase before tendering, and revising the tendering

documents thoroughly by a technical committee that has members of the Safeguards Specialist,

Procurement Specialist and ILO representative, to guarantee that all safeguards aspects mentioned in the

ESMP are taken into consideration, including the costing of all mitigation measures that need to be clear

for the contractor. This will be reflected in the Progress Reports provided to the Bank and donors, and

upon any request at any time.

Conclusion:

The construction of the Governmental Complex in Ramtha municipality will definitely lead to temporary

(but not adverse) impact on local environment especially during construction stage. Whereas, construction

of this project is not expected to contribute in creating adverse impact on social side. In fact, Social and

Economic returns of this project are high and beneficial compared to current situation. Such benefits can

be summarized as below:

1. Providing Ramtha municipality with an appropriate place to practice daily work without paying any rent that can be used in providing other services for the benefit of the people. 2. Providing a space for the community through the construction of the multipurpose hall to host its social (and others) events 3. Facilitating dealings and transactions between Ramtha municipality and other nearby authorities; 4. Gathering & increasing number of employees in one place which is expected to improve the sale rate of surrounding markets and shops. 5. Decrease the time and effort on people in doing their routines and governmental paper work. On the other hand, potential environmental impact of the project is localized, temporary, and can be

mitigated through implementing mitigation measures and procedures included in ESMP.

Therefore, this sub-project can be implemented BUT with application of mitigation measures mentioned

in this document, and application of ARRAP document that includes compensation packages for the 5

Project Affected People (PAPs) identified, as a result of the economic displacement that occurred during

the preparation phase of the sub-project. The ESIA/ESMP will be included as an integral part of the tender

documents. Also, the contractor shall be requested, through the Contract Particular Conditions, to submit

a site specific Environmental and Social Health and Safety Plan. This Plan will be reviewed and approved

by the Municipal Site Engineer and PMU Safeguards specialist after having also received the World Bank

approval, and as an indicative measure for the sub-project.

Page 43: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

43

Chapter 2

Sub-project Description

Page 44: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

44

Figure (2): Front view of the expected sub-project

The sub-project is a construction of a governmental complex in Ramtha municipality that will have a multi-

purpose hall, offices for the municipality and offices of other governmental entities that will pay rent for the

municipality. This building

The project is located in Abu Basal Sharqi area, within Ramtha municipality which is located in the Northern

part of Jordan in Irbid governorate, and in direct contact with the Syrian border.

The project is a governmental complex that shall consist of 7 (seven) floors in its final stage: a Basement

that shall be used as a multi-purpose hall for the municipality in conducting its meetings and official use,

with an area of 1250 m2. A Ground floor that contains the offices of the municipality, with an area of 1250

m2, as well. The other 5 (five) floors shall be offices rented by the governmental entities, according to

certain legal contracts with the municipality, with an average wage of 30 (thirty) JDs per m2 a year.

The design of the building, checked by the Safeguards specialist includes also several entrances, along

with passages and bathroomsfor people with special needs, as well as some green areas in different parts

of the building.

In general, launching construction stage of this sub-project depends upon delivering project technical

documents including Environmental & Social Impact Assessment study (ESIA) that must address project

potential impacts on environment and local residents. In addition, this study should include required

measures and recommend practical methods to avoid and minimize that impact. Also, an ARAP document

was prepared as a result of an economic displacement action that was caused by the sub-project

preparation phase.

General components of the sub-project can be summarized as the following;

Page 45: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

45

1. Construction of the main building of the Complex

2. Gates and fences construction and people with special needs entrances,

3. Construction of free and parking areas,

4. Green spaces,

5. Water and sanitation network,

6. Facilities and services connections,

7. Safety and traffic signboards installation,

8. Indoors and finishing works,

9. Generator and power supply room to be connected with the electrical generator which is already present

in the land,

10. Security room,

11. Sidewalk and onsite pavement works, and

12. Others

2.1 Sub-project objectives The main objective of constructing this governmental complex is to have the municipality offices and other

governmental entities’ offices gathered in one building, so as to minimize time and effort needed by citizens

in achieving their paper work. Extra income for the municipality will be available due to rent amounts paid

by the different governmental entities for the municipality. A multi-purpose hall is another benefit that the

sub-project is intended to have as well.

2.2Location The subproject land is almost located in the middle of Ramtha city with 80 m along the main street of

Alsakhrat Almusharifa as shown in Figure 1. The availability of public transportation raises the strategic

importance of the proposed land, which is the most appropriate land for constructing such a complex. The

municipality owns other lands but is far away from the center of the city. This specific site was chosen

years ago, since 2011, and People would only need one transportation to get there minimizing the cost

and effort. The existing Governmental agencies are spread in different locations around the city in which

traffic jam could be a serious problem. In addition, most of the city population works in public sector

agencies. Gathering such population in one place could achieve the social feasibility of the proposed

subproject. The location of the proposed land is also near very important governmental buildings such as

schools, healthcare center and Public Park. The coordinate of the land (32.55905815, 36.00076154) could

be used to observe clearer information about neighboring land properties. Such importance makes the

subproject socially feasible.

Page 46: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

46

Figure (3): the locationof the proposed landusing the Department of Land And Survey website

Table (2): Sub-Project Land Basic Information

Parameter Value

Governorate Irbid governorate

City Al Ramtha

Land number 161

Neighborhood 29

Total Area(m2) 6,186.00

Near the Location 1. Comprehensive health center. 2. Musab bin Omair Secondary School for Boys. 3. Ramtha Health Directorate. 4. IbnHazm Elementary School. 5. Public Park.

On Main Street Yes, AlSakhrat Almusharifa St.

2.3 Project Size & Land Requirements

The size area of this project is around 6,000 m2. This size contains land required to construct the main

building of Ramtha Governmental Complex. It is expectedthat,this sub-project will be constructed over 12

months since signing the contract.

Page 47: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

47

2.4 Land Ownership & Current Land Use

Land Ownership: The land is owned by Jordanian Treasury/MoMA, and re-assigned for the purpose of

building a governmental complex in Ramtha municipality and under the Public Building Regulation of

Ministry of Municipal Affairs, with a total area of 6134 m2. A formal letter was issued by MoMA to the Land

and Survey Department to speed the designation process. The approval is provided in the letter from the

Land and Survey Department.

As for the land use of project site, this location is currently free from any activities. A kiosk was evicted

from the land of the sub-project which resulted in triggering WB Resettlement Policy 4.12 and an ARAP

was conducted for this case of economic displacement.

Figure (4): View of sub-project construction area

Page 48: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

48

Figure (5): Electrical convertor in the land of the sub-project

2.5 Project Activities &Expected Equipment

Establishment of this sub-project will require conducting many activities during the different stages of

implementation. Interventions during each proposed phase is detailed in the following tables;

No Phase Details Equipment& Expected Materials

01 Site preparation

This phase will include (but not limited to) making the following;

• Making studies and site investigations

• Drawing site’s maps, designs, and related documents

• Reviewing and correction of designs to include safety measures

• Identification of site possible materials to be kept in site during construction

• Making list of materials & involved equipment

• Preparation of time framework & work plan

• Site delivery

• Papers & administrative work requirements

• PC & office programs application

• Survey, field visit, and making rapid inventory work

• Plastic collection bags, boxes, wood cutting machines, and PPEs.

• Manual construction tools, heavy truck for site leveling, and digging work equipment.

Page 49: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

49

No Phase Details Equipment& Expected Materials

• Identify waste collection points, construction work route, and site exits.

• Removal of exist waste, trees, and undesired debris

• Site leveling works

02 Construction phase

This stage includes the following activities;

• Excavation & fill up activities

• Concrete works

• Construction & buildings works

• Plastering works

• Flooring & slab works

• Rain water drainage works

• Carpentry work

• Painting

• Water & sanitation works

• Electricity works

• Decoration

• Furniture & building supplies installation

Out& Indoor activities;

• Fences & gates work

• Free spaces work

• Garden & site pavement work

• Water supply & sanitation activities

• Electricity & external lamps work

• Instruction boards & traffic signs

• Construction of gray water tank

• Solar energy installation

• Ventilators designs

• Line phone & internal communication network

• All electrical works

• Safety applications work

• Installation of firefighting systems & equipment

This intensive phase will involve using different kind of materials and equipment like the following;

• Establishment of temporary noise barrier and fences around work area

• Applying heavy trucks &machines such as bulldozer, excavation axe tools forklift, concrete mixer machine, cranes, and Transportation means

• Construction materials &manual construction tools.

• Materials and equipment like cement, stones, construction’s steel, water, sand, breaks, water plastic tubes, ladders, scaffolds, ropes, and wood are involved when making this part

• Local and intensive labor is required in collaboration with the ILO

• Establishing worker’s room and its supplies including waste disposal receptacles

• Supplying the site with washing water temporary tank & waste collection bags,

• Construction the site with water designs & irrigation equipment

• Sanitation connections &storage tank of solid waste

• Place room for the site engineer

• Plantation& garden work

Page 50: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

50

No Phase Details Equipment& Expected Materials

• Painting materials and involved chemical substances

• Electricity & electronic work devices

• Installation of safety supplies

• Materials & equipment related to plastering works

• Cables and site gates installation

• Others

03 Operation phase

Activities of this stage can be summarized as below ;

• Authority Daily work

• Holding meetings & related workshops

• Documentation & archiving authority documents

• Preparation of studies

• Correspondence & coordination works

• Storage of authority supplies &equipment

• Printing, copying, and administrative office works

• Traffic & parking of the municipality’s vehicles

• Maintaining &preparation of out spaces

• Frequent operation of electricity generator

• Activities related to maintenance & operation

• kiosks for different services

• Communication & training

• Security & secretary works

• Toilette & water cycle uses

• Oil & lubricant frequent change

• Cleaning and building arrangement

During this period, materials & work requirements may include the following;

• Materials related to administrative work & offices activities

• Cleaning substances & furniture purification Using equipment like;

• copy machines& scanners

• PC s & printers

• Internet & communication network

• Faxes, phones, and servers

• Equipment related to municipality main duties

Table (3): Sub-project’s Activities and Equipment

2.6 Environmental & Social Assessment and Review Process

In order to prepare and review the environmental and social investigations required for this sub-project,

Ramtha municipality and the PMU follow and adopt the below activities and policies;

Phase Activities Condition Responsibility

Screening & preparation of ESIA’s outlines

- Investigation of ESIA study scope - Meeting related stakeholders and involved agencies - Making an initial site visit &gathering available

documents

Done PMU / Municipality

Page 51: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

51

Phase Activities Condition Responsibility

- Identification of issues and applicable safeguard policies in regards to kiosk issue and preparation of ARAP document

- Investigating related studies and project’s documents

- Categorization - Making study action plan

Conducting ESIA/ESMP

- Conducting field visit and project site investigation - Conduct consultations with affected groups&

beneficiaries - Outline findings of meetings &site documentation - Making ESIA/ ESMP draft

Done PMU

Review of ESIA draft

- Review of ESIA draft - Review of ESMP tables - Discuss comments with municipality

Done Municipality / Safeguards specialist in PMU

Comments incorporation and final pre review of final document

- Integration of municipality comments and discussion of all critical points related to ESIA’s study

- Improving ESIA draft and revising its contents - Reviewing of ESIA & ESMP all chapters

Done Safeguards specialist in PMU

Preparation of final study of ESIA/ ESMP

- Making the final ESIA and ESMP report - Review of ESIA, ESMP final document - Incorporation of PMU final comments and

suggestions

Done Safeguards specialist in PMU

Approval of ESIA & ESMP final report

- Consent of ESIA & ESMP study - Submission of the final document of ESIA/EMP to

the WB - Formal acceptance of the study by the World Bank

team - Printing out the document and providing the client

with required copies

Upcoming /The WB team/ PMU

Disclosure of ESIA & ESMP

- Disclosure of ESIA on project Website - Making information letter to related agencies&

involved parties

Upcoming PMU / Municipality

Procurement of work contract and incorporation of ESIA measures

- Incorporation of ESIA/ ESMP measures in the work contract documents

- Announcing project tender documents and bids qualifications

- Signing with the contractor

Upcoming CVDB / Municipality

Implementation & Monitoring

- Construction of the project with mitigation measures included in ESIA/ESMP document

- Monitoring & reporting applications of work mitigation measures

- Reviewing field monitoring reports - Submission of final reports to the WB

Upcoming PMU / Municipality

Table (4): Environmental and Social Assessment and Review Process

Page 52: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

52

Chapter 3

Existing Environment and Baseline Data

Page 53: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

53

3.1 Geology & Soils

Irbid governorate, in which Ramtha municipality lies, is situated the Yarmouk River Basin that covers an area of about 1160 km2. The headwaters of the basin fall in the Ajloun highlands south of Irbid, but the Yarmouk River itself begins permanent flow at WadiShallaleh near the Syrian border. The geology is dominated by Upper Cretaceous limestone with sinkholes mixed with marl in the lower formation sand chert in the upper formations. Finally, early in the rifting and uplift process, volcanism led to basalt flow along much of the northern part of that area. However, project location has no indication of soil contamination or soil erosion to be mentioned in this study, while top soil might be removed aside to be used later within green spaces and may be for garden purposes, as it has significant agricultural values.

3.2 Water Resources & Hydrogeology

Generally, Jordan’s primary sources of water are aquifers and basins fed and recharged through annual rainfall. The groundwater resources are subdivided into groundwater basins on the bases of natural boundaries and administrative boundaries. The Yarmouk Basin in which Ramtha municipality lies, is considered the largest as it covers an area of about 1,500 km2. This area has a semiarid climate of the Mediterranean Sea region with a limited amount of rainfall and high temperatures. Meteorological records collected by the Jordan Meteorological Department at Irbid station in the North, gave the mean annual rainfall and temperatures as 410mm and 18degrees C. Depletion of this valuable and scarce resource may be inevitable due to the increase in population, especially after the Syrian crisis, and the misuse and mismanagement of water resources.

3.3 Air Quality & Noise level In general, current activities in the sub-project area are not considered to make adverse impacts on air quality or contribute in disturbance of noise levels since existing investments are simple and involvement of industrial complicated processes and large equipment are not accounted. However, this sub-project is expected to temporarily increase dust concentration and disturb noise level during construction stage, especially for the students in the nearby schools and the visitors of the health center near the site, IF mitigation measures that are explained in details and included in this document are not taken into consideration.

3.4 Flora & Fauna

Based on site investigation and field visit for sub-project area, the site is clear from perceptible diversity

while unique and endangered species are not known to exist in the area and were not observed during

the field visit, even no trees exist in the site except for a few bushes -of species which are common in the

project’s area- that were removed when the kiosk was demolished, these bushes are common in the area

and have no special biological significance.

Page 54: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

54

Figure (6): Bushes and existing species in the site

3.5 Wetlands & Protected Areas There are no wetlands or protected areas recorded in the sub-project area.

3.6 Population With a population of approximately 165,000, Ramtha city is the second largest city in Irbid Governorate.

However, the total population in the project area is estimated to be around 5,000 people as a maximum

and most of them are not living permanently in this place. This number is of students and school staff in

the nearby schools, employees of the comprehensive health center and health directorate near the site,

as well as the local people and citizens who live in the adjacent area and may use the amusement park

which is located near the site as well. In addition, small number of surrounding residents is included to

figure out the total number of area population and to identify the most affected groups of project

construction and operation activities.

3.7 Services & Facilities Since this sub-project is located in an urban city, services such as public water networks,

telecommunication, electricity, roads network, sanitation services, and education and health centers are

all available in the sub-project’s area. In addition, facilities like transportation means and private business

are available in this area.

Page 55: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

55

3.8 History, Heritage, and Touristic Sites

Field visits and site investigation indicate the absence of historical and heritage culture elements in this

site while touristic sites are not recorded. Therefore, the proposed sub-project has no impact on this

domain.

3.9 Climate & Topography There is no weather station to give accurate data about climate parameters on sub-project’s location.

Generally, Ramtha climate is characterized by its moderate temperature and moderate rainfall patterns.

Topography of sub-project’s site is part of Ramtha city that is located in the far northwest of Jordan, with

a population of approximately 165,000, making it the second largest city in Irbid Governorate. The city

experiences a Mediterranean climate with relatively hot summers and cold winters. Sub-project location is

a flat and urban open area with no adjacent hills and height features.

Page 56: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

56

Chapter 4

Legal and Institutional Framework

Page 57: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

57

4.1 Jordanian Environmental Regulations

The Ministry of Environment (MoEnv) was established in 2003 as Jordan’s lead institution for

environmental management, with one of its responsibilities to coordinate national efforts to protect the

environment. Jordan has an extensive web of laws and regulations pertaining to environmental protection

and management. The following regulations have been initially identified to discuss within the framework

of the legal requirements for the project and accordingly the ESIA study.

Law of Environmental Protection, No. 52 of 2006, went into effect in the Official Local

Newspaper on Oct. 16, 2006:

The provisions under this Law include the requirement to protect the environment and all of its elements;

the requirement to set policies for the protection of the environment and the preparation of plans for such

policies; the requirement to monitor elements of the environment; the requirement to set principles for the

handling of harmful substances; approval for the establishment of natural reserves, national parks, and

their management and supervision; the requirement to issue environmental emergency plans; and the

monitoring and inspection of projects and facilities to ensure that they are in compliance with Jordanian

standard specifications. As per the law, MoEnv is responsible for setting Jordan’s environmental protection

policy, monitoring activities, coordinating national efforts for environmental protection, and preparing

environmental contingency plans.

• Article 7 of the law assigns the MoEnv with the environmental monitoring and inspection

responsibilities, and grants its employees the right to enter any facility for inspection needs;

• Article 13 sets the requirements for conducting Environmental Impact Assessment for projects;

• An Environmental Protection Fund was established under articles 16 and 17 and sets fees for

violation of its provision, terms for delegation of authority, and the operation of environmental non-

governmental organizations in Jordan. Finally, it lists the regulations that should be issued in accordance

to the law .

Of the required 12 regulations set by law; the following regulations have already been issued: marine

and coastal environment; environment protection from pollution in emergency cases; air protection;

nature reserves and national parks; management, transport and handling of harmful and hazardous

substances; management of solid wastes; environmental impact assessment; and soil protection.

Many other agencies retain their environmental responsibilities and structures. Environmental sections

and departments are present in a number of institutions such as the Ministry of Water and Irrigation,

Water Authority of Jordan, and Ministry of Health, among others .Institutions that do not have dedicated

environmental departments often resort to naming environmental focal points whose responsibilities

often include liaising with institutions on issues that pertain to both their respective agencies’ mandate

and the environment .

Furthermore, Article 23 mandates MoEnv to issue a number of bylaws which include natural reserves

and national parks. To date, the following by-laws have been issued :

• EIA regulation No. 37 for the year 2005 ;

• Noise Level Control Regulation for the year 2003;

• Hazardous Waste Management and Handling Regulation for the year 2003;

• Regulation for the Control of the Use of Ozone Depleting Materials for the year 2003 ;

• Regulation for the Management, Transport and Handling of dangerous and Hazardous Materials

number 24 for the year 2005 ;

• Public Heath Law (No. 54, 2002);

• Water Authority Law (No. 18, 1988) and related standards;

• Regulations for protection of birds and wildlife and roles covering their hunting (No. 113, 1973);

• The Antiquities Law (No. 21, 1988);

• Civil Defense Law (No. 18, 1999);

• Traffic Law No. 47, 2001;

• Labor Law;

Page 58: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

58

• Penalty Law (No. 16, 1960);

• Ministry of Agriculture Law (No. 44, 2002);

• Natural Resources Authority Laws 2002;

• Jordanian Standards for Air Pollution (JS 1189/2006);

• Handling and discharge of used oil by-law of 2003;

• Natural Reserves and national parks by-law (No, 29, 2005); and

• Soil protection by-law (No.25, 2005)

4.2 Jordanian Environmental Impact Assessment Policy

Environmental Impact Assessment (EIA) is a key tool to ensure that decisions taken at the legislative and

regulatory level are actually executed and built into the design and implementation of development

projects.

All development projects (including this project), regardless of EIA classification, must adhere to the

Jordanian Standards in regards to air, emission, water, wastewater reuse; industrial and municipal

discharge, in case triggered by the project. Requirements in the General Conditions of the FIDIC are

applied.

The Municipality as local executing agency must consult and refer to several Jordanian governmental

institutions, regulatory authorities as well as other stakeholders from public & private sector several times

during the clearance process to ensure environmental compliance; others must be approached prior to

construction to take permissions.

4.3World Bank Environmental and Social Safeguards Policies

The World Bank (WB) has ten operational safeguard policies that apply to various development projects

that the Bank is either implementing or funding. The purpose of these policies is to prevent and mitigate

negative social and environmental impacts of development projects. At the same time, these policies aim

to increase socio-eco returns of constructed project on people and local environment through investigating

and ensuring effectiveness and efficiency of development project and implementing proper mitigation

measures to leave no adverse impact of the project.

The table below liststheWorldBank10 safeguard policies which shall be considered when conducting ESIA

study for development projects;

No. Policy Reference Applicable to Ramtha sub-project

1 Environmental Assessment OP / BP / 4.01 Yes

2 Involuntary Resettlement OP / BP/ 4.12 Yes

3 Natural Habitats OP / BP 4.04 No

4 Cultural Property OP 4.11 No

5 Pest Management OP 4.09 No

6 Indigenous Peoples OP 4.10 No

7 Forestry OP / BP 4.36 No

8 Safety of Dams OP / BP 4.37 No

9 Projects in Disputed Areas OP / BP / 7.60 No

10 Projects on International Waterways OP / BP / 7.50 No

Table (5):Safeguards Policies of the Bank

Page 59: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

59

MSSRP would include small-scale investments in eligible municipalities selected based on the positive list

and pre-approved selection criteria. During the implementation process, some negative environmental

impacts which are easily mitigated may occur due to construction, rehabilitation and maintenance of sub-

projects. As a result, MSSRP is rated a category “B” in accordance with World Bank Operational Policy

4.01 (January 1998).

It is, anticipated that subprojects activities will have some negative environmental impacts which will need

to be managed. The ESMF is therefore a precautionary measure and details steps to be undertaken for

each specific category of investment through preparation of subproject specific environmental and social

management plans.

In the case of Ramtha municipality sub-project; the Governmental Complex, it is a category B, which needs

ESIA including site-specific ESMP as the appropriate tool to implement this project, so that any significant

environmental or social impacts can be mitigated properly.

4.4Gap analysis between Jordanian Legislations and the World Bank Policies

In Jordan, the national regulations define a list of projects that must conduct a comprehensive Environment

and Social Impact Assessment (ESIA). In addition, through the screening processes, unlisted projects

could be required to conduct an ESIA if they prove to have significant negative environmental impacts.

Further, the Jordanian regulations divide the projects into three categoriesthat correspond roughly to the

three categories of the World Bank (i.e. A,B,C) .

It should be noted that an ESIA was not required for this sub-project under Jordanian national regulations.

In accordance with the Project’s Environmental and Social Management Framework, the sub-project was

screened and was considered Category B as the potential for impacts on the environment and human

populations are considered less adverse than for a Category A project. The impacts are considered site-

specific, and mitigation measures can be designed to address them. Accordingly, this ESIA was prepared,

with emphasis on the ESMP.

Many features of the Jordanian EA system are compatible with the World Bank EA Policy (OP 4.01). These

features are: (i) screening; (ii) scoping; (iii) ESIA report content; (iv) content of the Environment and Social

Management Plan; (v) provisions for appeal; and (vi) requirements for monitoring and evaluation.

As for the World Bank Resettlement Policy 4.12, which implies that affected persons by any project

implementation must be compensated based on a socio-economic study conducted by a third party or

consultant. According to Jordanian Laws and regulations of land acquisition, the government has the right

to use up to 25% of any citizen’s property, in case a project is intended to use this property and has an

added value to the whole area, such as opening new roads that can add extra value to the land as the

services shall be provided through this road to the area.

While the Bank’s policy for involuntary resettlement distinguishes between compensation for expropriated

assets and rehabilitation measures to help improve, or at least restore, incomes or standards of living of

PAPs and their communities, the Jordanian LAL pays little or no attention to the difference between simple

compensation and resettlement for productive purpose. The LAL allows for cash compensation to be paid

for the expropriated land but does not require development of alternative livelihood restoration strategies

to address PAPs’ social and economic well-being and to build their productive capacity.

In the case of Ramtha municipality governmental complex project, the owner of the kiosk which was

removed is considered an affected person and has to be compensated in the appropriate amount his

livelihood was affected, which is not the case according to Jordanian laws.

Page 60: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

60

As previously mentioned, an A-RRAP was conducted by the PMU, in which 5 PAPs were identified that

were directly affected by the removal of the kiosk within the land designated to build the Governmental

Complex. Socioeconomic surveys were conducted for all PAPs, and a compensation arrangement that

includes both monetary and in-kind compensation was suggested and accepted. A Grievance Committee

will be formed to receive complaints from the PAPs, during the whole process of sub-project

implementation and shall be monitored closely by the PMU.

Involved Authorities include:

- Ministry of Municipal Affairs

Being the implementing agency of the MSSRP project, under which the Governmental Complex in

Ramtha Municipality lies. According to the Project Operations Manual, all Project agencies and entities

are committed to implement the Project following the Grant Agreement, the Project Environmental and

Social Safeguards Framework (ESMF), the Project Resettlement Policy Framework (RPF), and other

relevant rules, regulations and guidelines of the World Bank and the Government of Jordan (GOJ), as

applicable.

- Cities and Villages Development Bank

Being the Technical implementing agency in the MSSRP projectand responsible for overseeing

technical, fiduciary and safeguards compliance. CVDB will also be responsible for the procurement of

the sub-project which includes preparing the bidding documents with the municipality, advertising,

tendering, evaluation of submitted proposals and follow up on the sub-project while implementation to

ensure abidance of the contractor with all specifications before approving his payments, through

conducting continuous supervising field visits in collaboration with CVDB branch in Irbid, which is closer

to Ramtha municipality that is located in Irbid Governorate.

- Ramtha Municipality

The municipality shall bear overall responsibility for implementation of Municipal Grants in compliance

with the Grant Agreement, the Project OM, the ESMF and the RPF, and will have direct supervision on

the sub-project implementation and the contractor’s performance through all the phases. Qualified

Municipal engineers will be responsible for reporting to the PMU in CVDB and MoMA on any issue

raised during implementation, and to follow up with the contractor on applying the ESMP contained in

this document, after explaining the document to relevant staff by CVDB Safeguards specialist.

- Land and Survey Department (LSD)

The role of LSD was completed once the final designation letter was issued by their side to MoMA, in

order to start implementing the sub-project.

Page 61: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

61

Chapter 5

Environmental and Social Impacts

5.1 Scope of Impact Assessment and Methodology

Page 62: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

62

Impact assessment is the corner stone of this study. Usually, impact assessment requires investigating all

relative documents and conducting comprehensive field study for sub-project area. In this study,

assessment studied the project components and expected materials required during construction. These

details were obtained from tables of quantities and project designs included in technical studies made by

a private engineering office, under the supervision of Ramtha municipality.. Additionally, assessment methodology depended on gathering information and data about the sub-project

area and Ramtha city in general. Actually, collection of data included going through site investigation

reports and investigating operational policies related to ESIA topics.

In this sub-project, ESIA assessment focused more on construction stage since this period appears to be

the critical stage that may lead to degradation of local environment and may make an adverse impact on

Social and Economic condition of surrounding residents and entities.

However, this chapter starts with brief and simple matrix table that gives an overview of sub-project

different stages and impact levels. This table aims to facilitate understanding and making quick analysis

of potential impacts of the sub-project. At the same time, it enables reader to realize type and quantity of

the impact and to have a complete picture about the critical stage of this sub-project. The table includes a

matrix of potential impacts likely to occur during construction & operation stage and it shows the most

group subject to this impact.

In this table, type and magnitude of impact are represented in literal ranks and levels based on its severity

and time of occurrence. Actually, this technique depends upon giving each impact a rank starting from the

less impact (L) to the highest impact ones (H).Moreover, several social and environmental benefits of the

sub-project are included within this matrix even though ESIA expects further advantages on this side.

From this exercise one may realize that, the most and expected environmental impacts of this sub-project

are summarized as the following;

1. Waste of construction & general waste of the site

2. Workplace and community hazards (particularly during construction)

3. Dust concentration and deterioration of Air quality

4. Increase of noise levels,

5. Waste of workers &General Waste of their room

6. Traffic & violation of road safety

7. Mismanagement of waste especially during operation stage

8. Misapplication of safety measures &proper storage of materials

9. Potential absence of Instantaneous Maintenance for ruinous parts of the building

On the other side, this sub-project will have many advantages that include the following points:

- Once the project is completed, the parking area of the proposed project shall be used by citizens in

case they wanted to visit the amusement park in the afternoon, with some kind of minimal fee that can

create an extra income for the municipality.

Overall, ESIA sees potential environmental impact of this sub-project to be Site Specific Impact and it can be controlled through applying mitigation measures mentioned in this document. Whereas, social investigation resulted in one economic displacement incident in which OP 4.12 was triggered. Therefore, a Remedial Abbreviated Resettlement Action Plan (ARRAP) was prepared and submitted to the World Bank for approval before tendering any documents of this sub-project.

Page 63: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

63

Table (6):E&S Impact Assessment Matrix for Constructing a New Governmental Complex in Ramtha Municipality

IMPACT CATEGORY NATURAL ENVIRONMENT ECOSYSTEMS & BIODIVERSITY

SOCIO-ECONOMIC SIDES

PROJECT ACTIVITIES

AIR

QU

ALIT

Y

SO

IL C

OM

PA

CT

ION

SO

IL C

ON

TE

MIN

AT

ION

RU

NO

FF

ALT

ER

AT

ION

GR

OU

ND

WA

TE

R

AG

RIC

ULT

RA

L L

AN

DS

SU

RF

AC

E W

AT

ER

NO

ISE

& V

IBR

AT

ION

SLO

PE

ST

AB

ILIT

Y

RE

SO

UR

CE

S &

EN

ER

GY

PR

OT

EC

TE

D A

RE

AS

HA

BIT

AT

S C

HA

NG

E

DIV

ER

SIT

Y

DE

GR

AD

AT

ION

WIL

DLIF

E M

OV

EM

EN

T

WE

TLA

ND

S

LA

ND

SC

AP

E

RE

ST

TLE

ME

NT

HE

ALT

H &

SA

FE

TY

CO

NF

LIC

TS

JO

B C

RE

AT

ION

EC

ON

OM

ICA

L

DE

VE

LO

PM

EN

&

SO

CIA

L B

EN

EF

ITS

Construction Activities& Site Excavation Works

H H L H 0 0 0 H 0 0 0 0 0 0 0 L 0 H 0 B B

Transportation of Materials and Storage Process

H H M L 0 0 0 H 0 L 0 0 0 0 0 M 0 H 0 B B

Waste of Workers & General Waste of the Site

L L L 0 0 0 0 L 0 0 0 0 0 0 0 H 0 M 0 0 0

Operation of Vehicles& Involved Equipment

H 0 L 0 0 0 0 L 0 0 0 0 0 0 0 H 0 H 0 0 0

Vibration &Disturbance of Soil 0 0 0 0 0 0 0 M 0 0 0 0 0 0 0 0 0 H 0 0 0

Traffic Mobility & Violation of Road Safety

H L 0 0 0 0 0 M 0 L 0 0 0 0 0 0 0 H M 0 0

Poor Disposal of Waste during Operation

L L H 0 L L 0 0 0 0 0 0 0 0 0 H 0 H M 0 0

Lack of Safety Measures Application &Poor Storage of Materials & Equipment

0 0 0 0 0 0 0 0 0 M 0 0 0 0 0 0 0 H 0 0 0

Removal of existing debris and Standing Trees

L L L 0 0 L 0 0 0 0 L L L 0 0 L 0 M 0 M 0

Economic Displacement of 5 identified PAPs

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 H 0 0 B B

Page 64: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

64

Legend: L= Low impact; M= Medium impact; H= High adverse impact; B= Beneficial Impact 0= No Impact Positive impact of the project Negative impact of the project NOTE; above table does not include ALL direct & indirect benefits of the project. Such gains

are detailed within the study’s context. For instance, building’s operation is the highest

beneficial stage.

5.2 Potential Impacts during Construction Stage

Within the sub-project different stages, construction is considered to be the most critical period

to produce adverse impact onto local environment and to make significant influences on

surrounding residents. Usually, construction activities are carried out within an environment

full of hazard and risks while magnitude of hazards varies from project to another. In this

document, ESIA have investigated all effects of the project including both positive and

negative sides. Result of this investigation divides impacts during this period into two main

categories:

• Impacts related to Local Environment and Workplace Safety, and

• Impact on Socio-economic Condition

5.2.1 Removal of Existing Debris and Standing Trees

The proposed location to construct this building does not contain any kind of waste or unused

debris. The main obstacle found in the site was the Electrical Convertor that is located on the

edge of the land. It was recommended by the PMU to modify the design of the building so as

to stay away from the convertor, which was done by the private engineering office who

conducted the first design. The Electrical Convertor will be isolated using a fence, as it will be

used to generate electricity for the new complex.

5.2.2 Impact of Site Leveling and Excavation Works

Establishment of this sub-project requires conducting activities like site leveling and

excavation works. This activity will involve using heavy equipment like bulldozer and applying

several types of manual and modern pavement and excavation tools. In addition, an intensive

labor approach is needed to accomplish this work on time, which will be done in collaboration

with the ILO.

During this period, work activities may generate the following impacts:

• Raising up of dust and fine particles of sand

• Production of small amount of emission from used equipment and trucks

• Disturbance of noise levels

• Increasing of vibration caused by used heavy trucks& machines

• Alteration of site landscape &area’s general sight

• Generation of water spots due to using water for excavation activity

• Removing rich & top soil layer

• Accumulation of waste & work general debris

• Impacts related to spill accidents & oil fueling process

• Disturbance of traffic & current mobility pattern

Page 65: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

65

• Scatter of transported materials &work requirements

• Workers and drivers are subject to workplace different hazards. Risks of over tension,

carrying heavy materials, exposure to dust and emission, equipment handling, and traffic

accidents may associate this work.

• General waste of workers room and residence place of the supervisor engineer

5.2.3 Impact of Constructing the Building Floors & Main Components

Construction of the building and its main elements requires establishing sub-project’s

foundations, building the main walls, and carrying out all other works related to the

construction of the building body and its supplements. Materials like cement, breaks, stones,

sand, water, and construction’s steel will be transported and used during this stage.

Whereas, an intensive labor & special equipment like cement mixture truck, concrete cartridge,

and forklifts truck will be employed to contribute in performing this work. In addition, manual

construction tools, scaffolds, ladders, ropes, stone embellishment machine, and mechanical

devices will be used during this work.

Potential impacts of this stage can be summarized as the following;

• Disturbance of noise levels

• Deterioration of air quality

• Accumulation of waste and contaminated water of the work site

• Scatter of debris & carton waste

• Contamination &soil compaction impact

• Impact related to spill accidents

• Occupational hazards & potential risks on workers and truck drivers

• Vibration impact due to applying heavy equipment

• Workers waste & solid waste of their residence

• Impact on traffic

• Impact of material’s transportation

• Health impact of workers and site supervisor engineer

5.2.4 Potential Impact during Finishing & Indoor Works

After finishing the construction of the building’s main body and internal walls, the contractor is

supposed to continue working indoor and some other outdoor works. Generally, this part of

works contains several activities as the following:

1. Electrical connections &light supplies activities

2. Plastering works

3. Painting activity

4. Flooring &slab work

5. Decoration

6. Furniture & building supplies installation

7. Free spaces work

Page 66: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

66

8. Garden & site pavement work

9. Installation of instruction boards & traffic signs

10. Solar energy designs

11. Ventilators designs

12. Installation of communication network

13. Installation of firefighting systems

Therefore, all the above activities may result in different environmental and some workplace

hazards as the following:

• Potential impact of electricity’s misconnection and mishandling of relative tools

• Accumulation of electrical and carton debris

• Falling down and impact related to workplace safety

• Impact of handling paint materials &painting chemical substances

• Mismanagement of chemical substance & paint materials disposal

• Lack of ventilation & potential impact of short light environment

• Smoking serious health impact particularly in confined work environment

• Breaking out of fire due to careless behavior of workers and cigarette improper

disposal

• Slip down and enrichment of unresisting floor and surfaces

• Disposal of waste through windows and building openings

• Potential impact of noise level disturbance

• Potential impact owing to absence of safety’s application.

• General health impacts on workers &involved parties

5.2.5 Potential Impact on Social &Economic Conditions

Concerning socio-economic condition of sub-project’s area, ESIA believes that, construction

stage will offer short work opportunities for local labor and drivers. Also, construction activity

will improve sales rate of surrounding shops due to purchasing dealings of workers and selling

different requirements of construction work.

In general, this location will be improved through the infrastructure facilities and service

networks that are going to be established on this location. Whereas, involvement of local

residents and adjacent users of entities in a social consultation process is another indirect

profit of this project as it provides a good opportunity for this group to rise up their voices and

to participate in improving sub-project’s construction activities. This consultation session was

conducted on January 13th, 2019 in one of the schools in Ramtha municipality, where

attendants expressed their full support for constructing such a facility in order to minimize the

time and effort in doing governmental paper work.

Nevertheless, environmental potential impact of the sub-project and traffic congestions during

construction phase as well as road safety may lead to social conflicts if mitigation measures

included in this document are not applied.

Page 67: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

67

5.2.6 Potential Social Impacts

- Impact of noise and dust emissions; which can be reduced through spraying water to

minimize the dust emissions. The noise can be minimized through working for limited hours

during the day, when students are in their schools. These procedures can be applied in

reference with the ESMP, and monitored by the municipal site engineer.

- Safety of public including children near the site from trip/fall/hazards, moving vehicles,

etc. The contractor is required to prepare a site-specific ESMP plan outlining the mitigation

measures necessary to meet the contractual obligations to protect the public, workers and the

environment, as well as a Traffic Management Plan. The implementation of the plans will l be

monitored closely by the supervising engineer and.

- Negative Interactions of workers with the public including children;

- Accessibility of the building to people with disabilities.

5.3 Potential Impacts during Operation

Operation of this building includes occupational daily work and employment regular activities

of management and departments of the governmental entities in the building. In fact, operation

of this building will not lead to adverse impact on local environment like the ones mentioned

in construction stage. Generally, this phase does not involve massive works or require

complicated production processes that may lead to consumption of natural resources or

contribute to degradation of local environment.

Therefore, ESIA expects a few number of potential impacts to come up during this period

especially if practical & mitigation measures of this study are not considered.

5.3.1 Impact of Waste’s Generation& Poor Disposal Plan

Daily work involves using supplies and materials related to administrative works and fieldwork

measurements. This activity is performed through using office equipment and machines such

as Copy Machines, Scanners, Printers, PCs supplies, Fax machines, Phones, Papers, Box

Files, and other office work requirements. Moreover, the building may include a place for the

cafeteria and snack bar whose waste and outputs require special management.

Therefore, when operating this building, using such equipment & materials will generate

several kinds of waste like:

• Paper & carton waste

• Inks & band colored papers

• Food and drinking waste

• Woody & desk debris

• Cables & electrical loose parts

• Waste of PCs & external supplies

• Organic garden waste

• Plastic waste

• Ink empty cans & cleaning materials bottles

Page 68: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

68

• Glass waste

• Others

5.3.2Safety of Workers & Employees

Employers and supervisors are obliged to implement all reasonable precautions to protect the

health and safety of workers. Municipality should hire a contractor that have the technical

capability to manage the occupational health and safety issues of their employees, extending

the application of the hazard management activities through formal procurement agreements.

During working hours, governmental staff might be exposed to different workplace hazards

such as electrical contact hazard, misuse of office machines, falling and slip down risk, failure

of materials handling, fire potential hazard, low light risks, lack of ventilation, sun strike hazard,

storage and parking risks, and potential of natural hazards. Actually, occupational hazards

vary based on work nature and used materials. In this project, associated hazards might be

maintained through following and integrating measures included in this document.

5.3.3 Impact on Health Condition of Employees

Health condition of employees might be affected because of long duration and frequent

exposure to a certain workplace hazard. For instance, radiation of copy machine has a

negative and accumulative health impact. In addition, direct contact with printer inks and color

cans has a serious health effect as these substances have an ability to penetrate the skin and

observed through blood circulation system. Smoking is another health concern while long time

working hours and handling cleaning materials are considered to make harmful and

accumulative health effects on cleaners& building occupants as well.

5.3.4 Impact on Landscape &General View of Site

Waste scattering & carelessness of cleaning process will deteriorate site view and make area

landscape looks unsightly. In addition, such neglect will lead to raising dust up and disturb

work environment which indirectly depress employees willingness to work under this condition.

Small debris, plastic bags, garden’s lefts, and cigarettes are part of these wastes while

discolored walls and destroyed parts of the building body and project’s supplements can

disfigure project general view.

5.3.5Impact on Soil & Green Spaces

During operation stage especially when employees move around, vacant spaces, surface soil,

and green areas are subject to deterioration and compaction effects. Usually, leaves and trees’

stem are the most affected parts whereas compaction of soil prevents trees from irrigation

requirements because of sever compaction influence and decrease of porosity ratio in the soil.

Absorption property will reduce and irrigation water will accumulate on the surface for quite

some time and that may attract insects like Mosquito and squalors.

Page 69: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

69

5.3.6 Potential Impact of Materials Handling& Storage

Insufficient handling of materials and bad storage of supplies may create a habitat of undesired

rodents and encourage fire to break out. Usually, storage of combustible materials and scrap

in a small room deteriorate the air, create odor, and leave debris on storage floor.

In addition, paint and exist electrical connections may get corroded and make electrical shock

as a reason of materials mismanagement and poor application of storage procedures.

5.3.7 Impact on Socio-economic Condition

It is believed that construction of this building will surely improve social and economic condition

of local residents. Since the main residents and beneficiaries are employees of the

municipality and other governmental employees, this building provides an appropriate place

for this group to carry out their employment requirements.

At the same time, ESIA does not expect a concern or significant negative impact to rise up

when operating this building.

Page 70: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

70

Chapter 6

General Analysis of Project Alternatives

Forward The aim of making this analysis is to identify project different alternatives and to choose the

best option with highest visible and invisible returns on the sub-project’s area. Comparison of

project alternatives considers aspects like social benefits, economical returns, and

environmental sounds associated with the establishment of this sub project.

Page 71: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

71

6.1 Sub-Project Location Alternatives

The sub-project site was selected years ago, to build this governmental complex on a land

designated for this particular purpose. The sub-project land is almost located in the middle of

Ramtha city with 80 m along the main street of Alsakhrat Almusharifa. The availability of public

transportation raises the strategic importance of the proposed land, which is the most

appropriate land for constructing such a complex. The municipality owns other lands but is far

away from the center of the city. People would only need one transportation to get there

minimizing the cost and effort. The existing Governmental agencies are spread out in different

locations around the city in which traffic jam could be a serious problem. The location of the

proposed land is also near very important governmental buildings that include two schools,

healthcare center and Public Park. Other sites are not considered as they are far away from

the center of Ramtha city, which is another advantage of selecting this site in specific.

Also, the municipality will be able to save the rent currently paid for its offices, to be used in

other useful projects and services for the citizens.

Therefore, ESIA sees this location to be the proper place to construct this building.

6.2 “No Project” Alternative The ESIA does not give preference to a “No Project Alternative”, and presents the current land

alternative as this site reflects high Socio-economic benefits and its temporary and localized

environmental impact can be controlled through the implementation of mitigation measures

included in this document. Other reasons for choosing this alternative include:

- The municipality staff is currently renting a building on the main street that connects

Amman with Damascus, for a total amount of 39,000 JDs (almost 56,000$) per year. The

intended governmental complex project shall have offices owned by the municipality, so as

to save the amount of rent when they move there.

- The project is supposed to generate income for the municipality and provide one stop shop

for the citizens in Ramtha that will help in providing a parking place, as well as minimizing

the time and effort needed to accomplish any governmental paper work for the citizens in

Ramtha.

- Raising the employment rate and providing better municipal services through local

economic development, is the core objective of MSSRP, which is the key purpose of building

this governmental complex in Ramtha municipality.

- The residual negative economic impacts for five PAPs as a result of this sub-project were

offset with compensation. The removal of the kiosk which affected the livelihood of the above

mentioned PAPs, resulted in preparing compensation packages for them, and obtaining their

approval on the whole process.

The “No Project Alternative” means that all the above-mentioned advantages would not be

achieved. Thus, constructing the complex in the selected land provided by the municipality is

considered most suitable alternative.

Page 72: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

72

Page 73: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

73

Chapter 7

Environmental& Social Management Plan

ESMP and Mitigation Measures

7.1 General The main objectives of Environmental and Social Management Plan (ESMP) Table (7) are to

establish a mechanism to carry out mitigation measures for the potential environmental and

social negative impacts of the proposed sub-project and to monitor implementation of these

mitigation measures during all stages of the sub-project. The ESMP Table (7) contains all

mitigation measures mentioned in ESIA study. Moreover, this document identifies responsible

agencies/ persons who must be in charge to follow up and to carry out ESMP while it includes

Page 74: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

74

details on durations and suggested times to conduct monitoring activity. This plan was

prepared with full consideration to comply with the OP 4.01 Environmental Assessment

Safeguards Policy of the World Bank and to follow national regulations on social &

environmental sides. In fact, the Bank will review ESIA and ESMP according to above

mentioned policy as well as the operational policy OP(4.12) which considers involuntary

resettlements and potential social impact of the sub-project, described earlier. In case the

ESIA and ESMP are not addressing complete treatment of potential impacts of the sub-project,

the Bank will forward its comments and remarks to PMU as the sub-project cannot be

processed with unsatisfactory ESIA & ESMP.

The budget of applying the ESMP, which shall be reflected on certain items in the Bill of

Quantity, and monitoring shall be stressed upon on the Special Conditions of the Contract,

should cover the cost of mitigation measures and monitoring activities during preparation,

construction, and operation stage of the project. Workers and drivers will use very small

portion of this budget towards the application of safety procedures on work site especially

PPEs and safety devices required for machineries. Whereas, the majority of this budget will

cover incorporation of mitigation measures within construction activities of this building. A short

training can be held for workers and employees about the application of proper methods and

measures to ensure safety compliancy of workplace and to preserve local environment. In

fact, all employees must work towards achieving safe and clean workplace and Ramtha

municipality management must point out the role of its employees especially during working

hours and emergency.

ESMP is an official and mandatory document when contract is signed. The contractor must

commit to fulfill all required measures mentioned in this report, as it will be part of the tendering

documents for Ramtha Municipality sub-project.

7.2 Responsibilities & Procedures

Overall, implementation of the ESMP is the responsibility of the contractor and the

subcontractors who implement the work activities in accordance with their contractual

obligations, along with the municipal engineer who provides oversight against the contractual

requirements. The contractor and municipal engineer must have appropriate environmental

and health & safety qualifications and will be supported by the Safeguards specialist in the

PMU. . Work’s methodology and monitoring procedures are explained in detail within ESMP’s

tables and will be defined in the contractor’s site-specific ESMP to be prepared by the

contractor and approved by the Municipal Engineer. The plan addresses each potential

impact during project working phases and designs applicable measures to control such impact

or at least to maintain it at lowest level of influence.

MoMA and CVDB are considered the implementing agency in the MSSRP, and therefore are

responsible for ensuring and monitoring the application of mitigation measures during

preparation, construction and operation phase. Direct supervision of construction activities will

be carried out by CVDB Engineers in Irbid Branch and the Municipal Engineer, who will be in

charge to monitor and record work activities included in the ESMP, and report directly to the

Safeguards specialist in CVDB.

The safeguards specialist, shall monitor the performance of the contractor and the municipal

engineer implementation of environmental, health and safety, and social mitigation

Page 75: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

75

measures and findings of monitoring activities should be reflected in quarterly reports

according to contractor on-site compliance with the ESMP and performance. In case

monitoring report indicates neglect or careless actions from the contractor side, direct

suggestions and correction measures should be delivered to the contractor. Such

recommendations should follow ESIA and ESMP suggested measures, and appropriate

measures shall be taken to make sure that the contractor performs against his contractual

obligations which includes conformance with the ESMP in this ESIA, the contractor’s own

site-specific ESMP, and the General and Special conditions that are included in the

contract.

Page 76: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

76

Table (7): ESMP Detailed Tables

IMPACT MITIGATION MEASURES

MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY

ESTIMATED COST

Preparation, Excavation, and General Waste of Work Site

1. The contractor

must follow &

implement waste

management

measures included

within ESMP

document whenever

needed.

2. Re-use of

construction waste

within the work site,

if possible.

3. Collection of

undesired

construction waste

and debris in specific

collection points in

the site within special

receptacles.

Selection of waste

collection site must

be pre agreed with

the site supervisor

engineer.

4. Construction work

may be avoided

during rainy periods

• There must

be a previous list

of expected

waste during

construction

stage based on

used materials

and involved

equipment.

Decision must be

made about the

most critical

waste to be

monitored

• Waste

collection points

should be clearly

identified before

launching the

construction work

• Determine

which waste can be

left and re-used on

The Municipal Engineer may follow up within 1-2 weeks, and prepare weekly progress reports

The environmental specialist in CVDB/ the Municipal supervisor engineer

- Cost of carrying out Mitigation Measures by the Contractor would be already included in the Bill of Quantities according to the different items of construction, and shall be monitored by the municipal engineer and the Safeguards specialist in CVDB.

Page 77: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

77

IMPACT MITIGATION MEASURES

MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY

ESTIMATED COST

in order to avoid

transmitting of waste

and debris. Whereas

all work materials

must be covered with

proper sheets.

5. Scatter of waste

should be avoided.

While workers

temporary room in

the site should be

supplied with waste

garbage and

disposal of such

waste must be done

based on waste type

and quantity and in

cooperation of

municipal engineer.

6. Disposal of all

waste must be done

in the landfill and

follow instruction of

construction

permission and

landfill management

requirements.

site and which must

be taken

• Monitoring

form to include

date, contractor

abidance by Health

and Safety

measures, any

excavations found

in the site and any

emerging matters

to be filled regularly

by the site engineer

and spot checks by

the environmental

Safeguards

specialist in CVDB.

• Monitor and

inspect the

contractor

compliance with

ESIA report

• Recording

all work sites,

activity location,

date, time, work

Page 78: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

78

IMPACT MITIGATION MEASURES

MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY

ESTIMATED COST

7. Liquid waste like

water needed during

construction should

be collected on a

separate tank and

water should not

accumulate on site.

Besides, drainage of

water to outside area

is forbidden.

expected period in

each site

• Transportati

on line and times of

waste disposal

must be mentioned

in the report, in

collaboration with

the Traffic

Management if

necessary

• Review all

documents relating

to waste

management and

disposal including

construction

permission

• All

hazardous waste

and disposal

methods should be

mentioned.

Whereas, time to

occur and sites

Page 79: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

79

IMPACT MITIGATION MEASURES

MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY

ESTIMATED COST

should be

explained

• Consider

climate influence

and waste

scattering

• Identifying

used equipment,

construction

materials, trucks,

volume of water

requirement, and

manual work tools

• Decide

about PPEs

required within

each activity of

waste disposal and

handling.

• Record any

spill, accidents,

waste poor

management

during supervision

visits

Page 80: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

80

IMPACT MITIGATION MEASURES

MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY

ESTIMATED COST

• Counting of

workers & trucks

number and identify

their different

waste. Cost of

disposal must be

mentioned

• Make

photographic

documentation

Soil Compaction & Contamination

1. Surface soil can

be kept aside to be

used later within

green spaces

2. Trucks and

involved vehicles

should follow specific

& identified truck

ways

3. Spill accidents

must be prohibited. If

any spill accidents

occurs, it should be

cleaned immediately

and collected in

separate disposal

container.

• Make sure

that soil top surface

has been removed

aside to be used

later on for green

spaces purpose

• Identify the

most sites subject

to soil compaction

or contamination.

And follow

mitigation

measures to

maintain such

impact

Five times during construction stage / Municipal Engineer may follow up within 1-2 weeks

The Municipal Engineer may follow up within 1-2 weeks

Page 81: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

81

IMPACT MITIGATION MEASURES

MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY

ESTIMATED COST

• Record soil

collection

containers and

available garbage

in work site

• Monitoring

identified working

paths and workers

compliance to

avoid soil

compaction

• Refer to

ESIA and make

photos

documentation of

soil condition, as

soil tests must be

done by the

contractor in the

design phase.

Air Quality & Noise Levels

1. Spraying water on

foundations before

excavation work

takes place. Water

must be used when

there is raise up of

• Define air

pollution sources,

type, locations,

remaining time,

weather main

drivers

The Municipal Engineer may follow up on a daily basis

The environmental specialist in CVDB/ Municipal supervisor engineer

Included above

Page 82: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

82

IMPACT MITIGATION MEASURES

MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY

ESTIMATED COST

dust like sand lifting

and handling

2. Spraying of water

may take place every

day to prevent dust

concentration. This

action might be

required in many

places in work site

3. Dust and fine

particles should be

always within low

level during all

construction

activities

4. Transportation

trucks are preferably

selected based on

motor performance

and low emission or

filtered exhaust

presence. Old

vehicles & trucks

with high emissions

should not be

allowed to be used

• Ensure

water is used to

maintain dust

concentration and

scattering of fine

articles

• Ensure all

equipment and

trucks are in a good

condition and

emission does not

exist

• Identify

noise disturbance

sources, duration,

time, most affected

group, number of

affected workers,

mitigation

requirement

(supply workers

with earplugs when

necessary)

• Make sure

that noise

prevention

measures are

applied. For

Page 83: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

83

IMPACT MITIGATION MEASURES

MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY

ESTIMATED COST

5. Truck engine must

be switch off when

on site.

6. Noise barrier

should be

constructed around

work area and

should be high to

prevent noise

transmission and

taking neighboring

facilities attention, in

particular nearby

school students.

7. Noise within work

site can be

minimized by

providing workers

with special

equipment like ears

protective equipment

and masks. Workers

in stone quarry

location must be

provided with PPEs

as well.

8. Transportation of

materials and waste

instance, noise

barrier and noise

protective

equipment, and to

abide by allowed

time to work in

during the day.

Page 84: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

84

IMPACT MITIGATION MEASURES

MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY

ESTIMATED COST

might be scheduled

during the afternoon

period in order to

avoid disturbing

neighboring facilities’

users, as working

hours are restricted

between 6:00 p.m.

and 9:00 a.m. and

noise levels NOT to

exceed 55 decibels

during the day and

45 decibels at night.

Transportation of Materials & Storage

1. Materials

transferred to the site

must be tight well to

the truck and covered

by an appropriate

sheet.

2. Sand is liable to

scatter during truck

movement. So, water

must be sprayed on it

and it should be

covered

appropriately.

• Identify

materials temporary

storage locations

and make sure

such locations are

not disturbing

construction

activities. Also, they

must be away of

truck & vehicles

ways

• All

transported

materials & waste

should be covered

The Municipal Engineer may follow up

on a daily basis

The environmental specialist in CVDB/ Municipal supervisor engineer

Included above

Page 85: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

85

IMPACT MITIGATION MEASURES

MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY

ESTIMATED COST

3. Truck back door

must be closed

during transportation.

4. Materials and

equipment storage

location must be

agreed previously

with site engineer. It

must not be far from

work site location.

5. Separation of

materials based on

their nature and type.

6. Flammable or oil

components

materials and

machinery equipment

should not be

aggregated with

construction or

organic materials.

7. Materials on

storage location must

be covered with

suitable plastic wrap

and surrounded by

short stones wall to

with proper sheet.

And scattering of

waste must be

avoided

• Drivers

should follow safety

procedures when

making this task.

While all materials

should be tight well

to the truck

• Water might

be used to prevent

scattering of sand

during

transportation

• Identify

truck routes, truck

condition, materials

type, applied safety

procedures.

• Temporary

storage location

must address

protection against

rain & weather

conditions.

Materials should be

Page 86: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

86

IMPACT MITIGATION MEASURES

MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY

ESTIMATED COST

prevent weathering

and rainfall effects.

covered and

surrounded by

short traditional

wall and drainage

channels

• Materials

should be stored in

compatible group.

Flammable

materials should be

separate from other

construction

materials

• Smoking is

not allowed in

storage locations

Health and Safety Impacts

1. Contractor

Prepares a site-

specific ESMP

(includes H&S) to

fulfill contractual

obligations to protect

workers and the

public and to comply

with Jordanian Laws

2. The contractor is required to have a code of conduct covering worker

• Monitor

implementation of

the contractor’s

plan that defines&

anticipate work

potential hazards,

health hazards, and

work place and

community safety

measures.

• Make sure

all required PPEs

The Municipal Engineer may follow up on a daily basis

The environmental specialist in CVDB/ Municipal supervisor engineer

Included above

Page 87: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

87

IMPACT MITIGATION MEASURES

MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY

ESTIMATED COST

interactions with the community, including children. The Code of Conduct is applicable to all of its workers as well as subcontractors. 3. All workers

including

subcontractors, are

required to

acknowledge that

training in the code of

conduct has been

received.

4.. The location of

electrical power line

and cables must be

determined before

digging and

excavation work

takes place (in our

case, the Electric

Convertor in the site

should by isolated by

a wall to avoid any

accidents)

2. Work sites must be

clean and orderly.

are available and

workers are

assigned based on

physical condition

capacity

• Work site

must provide

protection against

any risk and work

hazards.

• All

accident/incidents

must be recorded

and serious

incidents should be

reported

immediately to the

Municipal Engineer

and authorities as

required. Inspect

accident/incident

logs. Check out

scaffolds, ladders,

floors, openings,

and machinery

used in this

construction

Page 88: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

88

IMPACT MITIGATION MEASURES

MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY

ESTIMATED COST

While all site surface

must be kept dry.

Otherwise, proper

means might be

taken to assure the

surface is slip-

resistant.

3. Items and

materials that are not

required during work

hours must be

removed from the

work site

4. PPEs are

necessary during all

times of work.

Hardhats, proper

safety shoes,

inspiration masks,

and ear protective

tools should be worn

by workers whenever

necessary. Moreover,

safety devices during

indoor work like

electrical connection,

painting, and

• Inspect any

potential threat of

involved equipment

on project’s

components. In

addition ,

equipment must be

checked up to

make sure they are

in a good condition

and they are safe

to be used

• Inspect the

existence of

firefighting agents

and workers ability

to handle fire

extinguishers.

Make sure First Aid

Box is on site

• Ensure the

availability of PPEs

for handling

chemical & painting

substances. While

such materials

should be labeled

with explanation

Page 89: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

89

IMPACT MITIGATION MEASURES

MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY

ESTIMATED COST

plastering work are

all required.

5. Storing debris and

waste safely and

removing them

immediately from the

construction site.

6. All construction

safety requirements

must be addressed in

this project.

Workplace injury

must be avoided and

the contractor is

responsible to follow

up safety procedures,

as well as providing

basic medical

services and supplies

to workers

7. Workers must be

careful when working

near floor and ground

openings. While,

openings should be

marked and easily

identified by all

workers and drivers.

about its contents

and use

requirements

• All electrical

connections and

involved devices

must be evaluated

and protective

measures of

applying those

devices must be

attached to product

boxes

• The

Contractor should

prepare and submit

an ESMP including

emergency

response

procedure

• Provide

OHS training to

supervisors and

workers, including

daily toolbox

meeting for workers

• Provide first

aid kits

Page 90: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

90

IMPACT MITIGATION MEASURES

MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY

ESTIMATED COST

8. Bending & forming

of construction steel

must be done with

care and high safety

measures

application. Suitable

manual tools and

safety protective

agents must be

applied during this

work

9. All aisles and

passageways must

be identified and

marked.

10. Lifting and

moving of heavy

objects should be

done by mechanical

devices.

11.Ladders &

scaffolds must be

checked out each

time before climbing.

Damaged ladders &

scaffolds should

never be used.

Page 91: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

91

IMPACT MITIGATION MEASURES

MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY

ESTIMATED COST

12. If metal ladders &

scaffolds are to be

used, they must be

checked up on

corrosion and they

must be isolated from

communication with

any electrical

connections

13.There must be

rain clear paths and

proper drainage

system to avoid

accumulation of rain

water on site.

14. All electrical

power supplies and

connections must be

grounded while

dangerous voltage

and current must be

isolated by covers &

enclosures.

15. All painting and

chemical containers

must be labeled and

workers must be

aware how to handle

Page 92: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

92

IMPACT MITIGATION MEASURES

MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY

ESTIMATED COST

those materials.

Leaking containers

should not be

accepted while

workers should not

pour paint remaining

onto ground. There

must be sealed

containers to collect

and dispose such

substances.

16. There must be a

washing tank on site

to wash manual and

work tools at the end

of each working day.

17. Firefighting

equipment and fire

extinguishers should

be available while

workers must be

trained to handle fire

prevention cylinders.

18. Smoking is not

allowed at site.

Disposal of cigarette

may lead to break

out the fire.

Page 93: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

93

IMPACT MITIGATION MEASURES

MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY

ESTIMATED COST

19. All drivers and

workers must be

trained about

environment and

safety measures

IMPACT MITIGATION MEASURES

• MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY ESTIMATED COST

Management of Workers temporary room in the site

1. Management of

workers room and

all potential waste

must be maintained

through direct

supervision of site

engineer and the

Environmental

specialist in CVDB.

2. Room must be

established on free

space area and

should be near

project’s location

3. It must be

supplied with solid

waste storage tank

that must be

connected to the

local network or to

• Ensure the

room is equipped with

suitable wastewater

system and connected

to local network or

waste is disposed

regularly through a

special tank

• Identify waste

produced from the

room and number of

residents

• Ensure

hygienic condition of

the room and the

supply of adequate

water sources for

cooking and washing

purposes

The Municipal Engineer may follow up weekly

The environmental specialist in CVDB/ Municipal supervisor engineer

Included above

Page 94: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

94

IMPACT MITIGATION MEASURES

• MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY ESTIMATED COST

separate sink.

Design of this

system and disposal

process should be

discussed & agreed

with municipal

supervisor engineer.

4. If kitchen to be

included in this

container, there

must be gray tank to

collect water of

kitchen activities

considering use of

water for existing

trees and nearby

green spaces. While

organic waste

should be collected

and disposed of

outside the site in

designated garbage

containers.

5. There should be a

temporary tank

within the room area

to be used for

washing purpose.

• Make sure

workers are not using

facilities of

surrounding

employees and

guards

• Identify waste

disposal methods

• Identify

garbage and

containers used to

collect waste.

Page 95: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

95

IMPACT MITIGATION MEASURES

• MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY ESTIMATED COST

6. All safety

procedures of

temporary

establishment must

be taken into

account when

constructing this

room, such as

adequate signage,

lighting devices,

barriers and safe

drinking water.

Public Health of Workers

1. Work assignment

is preferably given

based on physical

condition and

worker’s capability

2. The contractor

must cover health

insurance of workers

during work

3.Temporary room

in the site must be

comfortable and

hygienic conditions

should be monitored

by site engineer

4. Workers are

prohibited to directly

• Make sure

worker is assigned

based on physical

condition and

qualification

• First aid box

availability

• Medical

checkup is

recommended

• Workers with

allergy to any of

materials of

construction should

not be working and if

there is simple allergy

The Municipal Engineer may follow up within 1-2 weeks

The environmental specialist in CVDB/ Municipal supervisor engineer

Included above

Page 96: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

96

IMPACT MITIGATION MEASURES

• MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY ESTIMATED COST

communicate with

chemical substance

like painting

materials. Therefore,

workers with allergy

should not handle

cement and

concrete materials.

5. Smoking must be

avoided when on

work

6. First Aid Box

should be available

during all

construction phases.

to concrete or cement

materials then worker

must not communicate

with such substances

• Make sure all

workers are health

ensured by the

contractor.

Socio-Economic Development

1. Nearby residents

and work site near

houses must be

given priority when

selecting local

labors, within the

labor intensive

arrangements to be

implemented under

MSSRP project.

This activity shall be

monitored by the

ILO specialist in the

• Ensure the

involvement of local

labors in this project

and nearby residents

and workers should be

given priority when

handling this work

• Workers must

not disturb nearby

residents and

employees

• Purchasing

materials required

The Municipal Engineer may

follow up within 1-2 weeks

The environmental specialist in CVDB/ Municipal supervisor engineer

Included above

Page 97: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

97

IMPACT MITIGATION MEASURES

• MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY ESTIMATED COST

MSSRP project

regularly.

2. Workers should

not disturb

employees of

nearby agencies.

3. The contractor

must follow

engineering design

of the project and

use

entrancespointed by

the site engineer.

4. Materials required

for work activities

can be purchased

from near shops and

markets unless such

materials are not

available in this area

or their prices are

not reasonable.

during construction

from nearby markets

and shops.

Workplace Hazards & Health

1. All electrical and

electronic cables,

and equipment must

be designed to

provide personal

protection while

• There must be

always an inspection

of the following;

Over project designed age

Municipality No Cost. Measures should be applied only

Page 98: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

98

IMPACT MITIGATION MEASURES

• MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY ESTIMATED COST

cables must be

covered and prove

high resistance to

electricity fluctuation

and voltage

variations

2. Parking area

should be identified

with marked lines

and blocks

3.Municipality

should make regular

inspection of

firefighting

extinguishers. This

action might be

conducted twice a

year to ensure

validation of fire

extinguishers

4. Handling and

storing of chemical

substances &

cleaning materials

should follow official

• Storage room

and storage materials

condition

• Fire

extinguishers and

validation of hydrants

• All electrical

cable and uncovered

connections

• Stability of

involved supplies and

materials

• First aid box

availability

• Following other

procedures mentioned

in ESIA.

Page 99: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

99

IMPACT MITIGATION MEASURES

• MONITORING ACTIVITY

FREQUENCY RESPONSIBILITY ESTIMATED COST

safety & health

precautions

5. It is always

recommended to

equip constructions

and office building

with First Aid Box

6. Corridors and

aisles must not be

used for storage

purposes.

Page 100: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

100

Page 101: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

101

7.3 Environmental & Social Mitigation Measures

Mitigation measures plan addresses potential environmental and social impact of proposed sub-project on

the targeted area and beneficiaries. This plan includes required mitigation measures and treatment

methods to control and minimize potential impacts over sub-project different stages. Actually, mitigation

measures plan aims to minimize and control negative impact of the project at low level while it considers

increasing project profits on local people and environment.

Moreover, mitigation measures plan identifies agencies and stakeholders involved in carrying out its

measures while implementation activities are detailed within the following tables.

7.3.1 Mitigation Measures during Preparation & Construction

Preparation Stage

Before going through construction activities, project documents and engineering studies may require

making short and rapid revising. Therefore, review and correction of building drawings and designs may

be required to ensure application of environmental and safety considerations in this building. This is just if

such measures are not included. However, reviewing may focus on the inclusion of following aspects:

1. Fire & Emergency Exits 2. Ventilation openings especially in stores and power supply room, 3. Ventilation & wash up outlets within supposed water tank, 4. Women separated toilet and an independent storage room.

Mitigation Measures during Site Leveling & Removal of Existing Debris

Potential environmental impacts during site leveling and removal of existing debris can be avoided through

identifying waste type and existing debris before collection and removing process takes place. Generally,

mitigation of potential impact during this phase can be done through applying the following measures;

• Work boundaries should be identified and fences must be established before making any

intervention on work site.

• Making rapid inventory of existing debris and waste

• Identifying waste collection tools, equipment, and waste collection points

• Anticipating potential personal injury, property damage, and workplace accidents before launching

this work. Based on the contractor's experience, the contractor has to anticipate workplace hazards and

draw specific plan to control and treat any accidents that may occur during construction activities. For

instance, PPEs and other safety measures to protect workers and property will be applied based on work

nature. While, capacity of nearby health centers and emergency responses of hospitals should be

considered within the safety plan prepared by the contractor. Luckily, there is one comprehensive health

center very close to the sub-project’s site.

• Identifying traffic and transportation line while instruction signs and traffic boards must be posted

and installed within the sub-project’s area.

• Construction of this building must be announced prior to launching any physical work on sub-

project’s site.

• Safety transportation measures must be applied while contractor should compel drivers to follow

transportation safety procedures.

Page 102: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

102

• Soil top surface (15-30 cm) might be kept aside to be used later for garden and green spaces

purposes.

• Inspect the load to be lifted for sharp edges, slivers, and wet or greasy spots.

• Recommendation on personal protective clothing and equipment (PPEs) should be identified

previously. And workers should wear proper gloves, masks, eye protective glasses, and safety shoes when

working.

• Wear gloves when lifting or handling objects with sharp or splintered edges. These gloves must

be free of oil, grease, or other agents that may cause a poor grip.

• Work assignment should be given based on work type, worker experience, and worker physical

qualification. Workers should be trained and guided before using any lifting or cutting machines. Health

examination might be a good option for the contractor before selecting workers.

• Waste collection points should be designed to be easy accessible by vehicles and transportation

means. Segregation of waste must be considered based on waste type and quantity.

• The contractor and involved workers should make sure all walkways are identified, clean, and

promote slip-resistant surface.

• Spraying water JUST when it is needed. This action may be applied when work leads to raising

dust or other fine substances. In this case, sprayed water must not accumulate on site.

• Work and site general activities can be scheduled based on noise leveling disturbance and air

quality deterioration. For instance, using noisy and vibration machine, transportation means, and removing

of waste with ability to raise dust up, can be done on the afternoon period to minimize potential effects on

workers and passengers in the area.

• Manual lifting and handling of material must be done by methods that ensure the safety of both the

worker and the material.

• Any spill accidents or soil contamination, should be cleaned immediately and disposal must

consider segregation of waste and taking out collected waste to nearby landfill.

• Safety procedures must be taken to ensure all electrical exist supplies and connections are out of

electricity before working.

• Consideration might be given to reuses and recycling of debris like electricity cables and metal

substances through reuse and recycling agencies.

• Under no reasons, waste scattering must be avoided. In addition, smoking should be prohibited

during collection of waste and debris.

Mitigation Measures During Construction of Building Main Components

Construction of the Governmental Complex will involve carrying out many activities and integration of very

detailed engineering designs and structures. For instance, intensive labor, construction materials, and

heavy equipment and manual tools are required to accomplish this work. Based on the potential impacts

mentioned in this document, ESIA suggests the following mitigation measures to avoid adverse impacts

of this stage, in which most of the activities related to Health & Safety and decent working conditions will

be monitored closely through ILO supervision, according to their contract with the PMU under MSSRP

Project, which includes the development of guidelines and specifications on labor based methodologies

for different categories of works, which indicates amendment of FIDIC Special Conditions of Contract to

cover labor-intensity provisions, decent work provisions and safeguards such as welfare and safety. Also,

propose social safeguards and mitigation measures for social impact on local communities possibly

resulting from labor-based works.

1. ENVIRONMENTAL GENERAL CONSIDERATIONS

Page 103: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

103

▪ Construction of the building must be designed according to quantity tables and engineering

drawings.

▪ Construction might be scheduled to avoid working during rainy periods while framework plan may

contain details of construction activities including waste disposal plan and waste treatment methods. In

addition, construction work should be prohibited in the evening.

▪ Identify all construction’s requirements including mechanical and manual equipment.

▪ Identification of waste collection points and safety procedures during this stage. For example,

Personal Protective Equipment (PPEs) should be worn over construction period while construction

safety precautions like shoring and covering floor openings must be considered.

▪ The location of electrical power lines and cables (overhead, underground, under floor, other side

of walls) must be determined before digging, drilling or similar work is undertaken.

▪ Hardhats are required at all times especially when carrying out falling work or dealing with flaying

objects. Whereas, workers must be supplied with proper safety shoes, respiration masks, and maybe ear

protective tools.

▪ Identify waste collection baskets and bags (plastic, metal, woody boxes).

▪ Construction of Noise prevention barrier around project site. Barrier with 4 m high might be enough

to make this part. Besides, workers should be provided with Ear muffle and work equipment must be

maintained and repaired to prevent production of nuisance noises.

▪ Work sites must be clean and orderly. While all site surfaces must be kept dry or appropriate means

might be taken to assure the surfaces are slip-resistant.

▪ Workers room must be constructed with a sanitation system that contains primary storage tank.

The tank should be connected to local main sanitation network. Besides, the contractor must provide the

room with waste garbage and temporary water tank.

▪ Before conducting excavation work, water should be sprayed over foundations site in order to

minimize Dust Concentration and to facilitate excavation works.

▪ All dust concentrations must be mitigated through spraying water over proposed work sites On

Condition that, water not to accumulate in work site or drain to outside areas. However, water might be

used every day. So this issue must be handled properly.

▪ Using equipment and trucks with low emission exhaust.

▪ Any spills must be cleaned up immediately.

▪ All combustible scrap, debris and waste must be stored safely and removed promptly.

▪ Smoking is not allowed when on site while fire extinguishers should be made available and remains

accessible at all times.

▪ All workers and drivers must be trained about environment protection measures and safety

procedures application included in this document. This action can be implemented prior to carrying out

any activities at work site.

▪ As much as possible, reuse of work-produced waste within the work site.

2. FLOOR & GROUND OPENINGS

• Workers must be careful when working near floor and ground openings.

• Such openings should be marked and easily identified by all involved workers.

• All floor’s openings (holes) should be guarded by a cover or equivalent barrier on all sides except

at the entrance to stairways and ladders.

• Toe boards might be installed around the edges of a permanent floor opening.

• If ground openings to be constructed on roadways and driveways, covers with capacity to carry a

truck rear axle load must protect all openings and trenches.

• Excavation and trenches shoring must be considered when conducting foundations and concrete

work. While, applied walls within site openings must address erosion resistant surface.

Page 104: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

104

• As it mentioned before, water might be sprayed out on foundations site before launching

excavation work in order to mitigate dust impact and to facilitate excavation work as well.

• Considering a distance of 30 cm between excavation produced waste and proposed trench or

floor openings to prevent filling up of produced waste and to prevent work accidents.

3. CONCRETE & WORK PLATFORMS

• Bending & forming of construction steel must be done with care and high safety measures

application. For instance, sunhats, eye protective glass, and proper gloves must be worn when making

this assignment. Suitable manual tools with plastic end edge should be provided especially when welting

work is involved.

• Workers with skin allergy diseases should not make direct contact with cement and construction

concrete materials.

• Work distance of90 cm (at least) from cement mixing machinery must be recognized.

• All work sites must be clean and orderly.

• All work surfaces must be kept dry or appropriate means taken to assure that surfaces are slip-

resistant.

• Suitable safety (PPEs) such as suitable safety shoes, gloves, strong pants , and head protection

hats must be worn all times during this stage

• Water shouldn’t accumulate on surface and simple drainage system might be designed to take

used water into water collection point or tank. Instead, involved worker may adjust water pipe and install

valve to provide work site with proper requirements of water.

4. WALKWAYS

• All aisles and passageways must be marked and kept clear.

• Wet surfaces must be covered with non-slip material and all holes should be marked with warning

guards.

• In cases of passageways used by forklifts, cranes, trucks or other machinery, use a separate aisle

for walking, if available. If no separately marked aisle is available, use extreme caution.

5. LIFTING & MOVING

Lifting and moving objects must be done by mechanical devices rather than manual efforts whenever this

is practical. Used equipment must be appropriate for lifting or moving task. Lifting and moving devices

must be operated only by authorized and trained person. Workers must not be required to lift heavy or

bulky objects that overtax their physical condition or capability.

6. LADDERS &SCAFFOLDS

• Check ladders &scaffolds each and every time before climbing.

• Damaged ladders & scaffolds must never be used; they should be repaired or destroyed.

Ladders used near electrical equipment must be made of a non-conducting material like wood.

• Installation of scaffolds should be designed to provide safe work site and to prevent any work

accidents among workers. They must be tight well and address free and flexible work environment.

• If metal scaffold to be used, check out of corrosion and connections damage must be

undertaken before installation. In addition, it must be isolated from touching or communicating any

electricity connection and supplies.

Page 105: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

105

• Ladders & scaffolds should be maintained in a good condition: joints between steps and side

rails should be tight; hardware and fittings securely attached; and movable parts operating freely without

binding or undue play.

• Non-slip safety feet must be provided on each ladder & scaffolds.

• Ladder rungs and steps should be free of grease and oil. While workers hands should be free to

grasp the larder when ascended or descended.

• Workers are prohibited from using ladders that are broken, missing steps, rungs, or cleats, or that

have broken side rails or other faulty equipment.

• It is prohibited to place ladders on boxes, barrels, or other unstable bases to obtain additional

height. Face the ladder when ascending or descending. Whereas, unstable objects such as barrels,

boxes, loose brick, or concrete blocks must not be used to support scaffolds or planks

• It is required that when portable rung or cleat type ladders are used, the base must be so placed

that slipping will not occur, unless it is lashed or otherwise held in place.

• All portable metal ladders must be legibly marked with signs reading “CAUTION”

• Metal ladders should be inspected for tears and signs of corrosion. Rungs of ladders should be

uniformly spaced at 12 inches, center-to-center.

7. DRIVING & MATERILAS TRANSPORTAION

• Drive safely.

• Transportation’s instructions and signs must be posted and attached alongside the main road to

project area. Also, signs must be attached to all exits& entrances of work site.

• Drivers must wear seat belts at all times during the work day.

• Drivers must not exceed the speed limit. For instance, 30-45 km /h is accepted limit speeds when

transportation of materials takes place.

• Vehicles must follow specific route and avoid obstructing exist traffic.

• Transported materials must be well tightly to the truck and scattering of waste must be avoided.

• Materials can be covered by a proper plastic sheet to avoid scattering waste along transportation

side

• Water might be used additionally to avoid scattering of transported materials. For example,

spraying water on Sand before putting the cover and prior to transportation process is a good mitigation

option.

• Posting work site & transportation caution signs within the work area and transportation proposed

line.

• Emission of transportation means must be mitigated through using trucks with improved exhaust

system or less emission motors.

• Trucks and vehicles must be switch off when on site.

• Drivers should comply with all safety procedures including wear of safety protective agents,

considering materials safety, and safety of traffic in general.

• However, identifying transportation line and time should be applied based on permission of traffic

department and local state. Whereas, transportation of materials and site waste might be carried out

during the afternoon period in order to minimize taking attention of MWE employees and to reduce

making any disturbance on traffic.

• Any accident must be reported in accordance with legal requirements and quick action must be

taken to manage the accident. Serious incidents and accidents must be reported immediately to CVDB

and the World Bank.

Page 106: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

106

8. CARRYING & HANDLING CONSTRUCTION MATERIALS

• Evaluation of material-handling and storage facilities, such as manual and mechanical handling

devices, slings, ropes, chains, and hooks.

• Manual lifting and handling of material must be done by methods that ensure the safety of both the

workers and the material.

• Good footing that set feet about 10 to 15 inches apart will help to set one foot forward of the other.

• Additionally, workers should assure knees to be bend and to keep back straight and upright position

especially when carrying heavy object. For example, lifting the object by straightening knees - not the

back. In addition, carrying the load close to the body (not on extended arms).

• Mechanical devices must be used for lifting and moving objects that are too heavy or bulky for safe

manual handling by workers.

• Workers who have not been trained must not operate power-driven mechanical devices to lift or

move objects of any weight.

• Heavy objects that require special handling or rigging must be moved only by riggers or under the

guidance of workers specifically trained and certified to move heavy objects.

Mitigation Measures during Finishing & Indoor Works Finishing activities are accounted to be the longest stage throughout the sub-project construction period.

Because of very detailed requirements and installation& equipping of many supplies and equipment inside

the building, this phase takes around 65% of construction’s allocated time and maybe from the total cost

of building establishment.

In this stage, ESIA contains safety and health requirements of indoor works and discusses mitigation

measures of potential environmental impacts of outside associated activities like preparation of green

spaces and parking area. However, suggested mitigation measures cover the potential impact of the

following activities:

• Electrical connections & light supplies installation,

• Plastering works,

• Painting activity,

• Flooring & slab work,

• Decoration,

• Furniture &Building’s supplies installation,

• Free Spaces work& site instruction signs,

• Garden &Site preparation work,

• Ventilators designs, and

• Installation of firefighting systems

1. Mitigation Measures Related to Electricity Works

The following rules are the minimum, but not limited to, measures to be applied when making electrical

work in this building;

• Power: All ac and dc power cabling to equipment not having a separate external ground but having

wire-to-wire or wire-to-ground voltage of 50 volts or more must carry a ground conductor unless cabling is

inside an interlocked enclosure, rack, grounded wire way, or conduit, or feeds a commercial double-

insulated or UL-approved device. This requirement will ensure that loads such as portable test equipment,

temporary or experimental, is grounded. UL-approved devices such as coffeepots, timers, etc., used per

the manufacturer’s original intent are permissible.

Page 107: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

107

• Isolation: All sources of dangerous voltage and current must be isolated by covers and enclosures.

Access to lethal circuits must be either via screw-on panels, each containing no less than four screws or

bolts, or by interlocked doors. The frame or chassis of the enclosure must be connected to a good

electrical ground with a conductor capable of handling any potential fault current.

• Cable Clamping: A suitable mechanical-strain-relief device such as a cord grip, cable clamp, or

plug must be used for any wire or cable penetrating an enclosure where external movement or force can

exert stress on the internal connection. Grommets, ad lets, or similar devices must not be used as strain

relief.

• Lighting: Adequate lighting must be provided for easy visual inspection.

• Labels: All disconnects and breakers should be clearly labeled as to which loads they control.

• Overload Protection: Overload protection and well-marked disconnects must be provided. Local

“off” controls must be provided on remote-controlled equipment.

• Safety Grounding: Automatic discharge devices must be used on equipment with stored energy

of 5 joules or more. Suitable and visible manual grounding devices must also be provided to short-to-

ground all dangerous equipment while work is being performed. However, all electrical system of the

building must be grounded.

• Emergency: There must be an emergency lighting system that activates when normal power fails.

• Either safety glasses or a face shield must be worn when working on electrical equipment.

Moreover, Personal Protective Devices such as face shields, blast jackets, gloves, and insulated floor

mats are required.

• All covering, clothing, and metal items that might cause hazardous involvement must be removed.

• Adequate and workable lock-out/tag-out procedures must be employed.

• Automatic safety interlocks must be provided for all access to high-hazard equipment. Any bypass

of such an interlock should have an automatic reset, display conspicuously the condition of the interlocks,

and ensure that barriers cannot be closed without enabling the interlock.

• All electrical equipment should have convenient, comfortable, and dry access.

• Equipment must be designed and constructed to provide personnel protection. First-line and

backup safeguards should be provided to prevent personnel access to energized circuits.

2. Mitigation Measures during Plastering & Painting Work

• All produced waste must be collected in temporarily collection points inside the building.

Segregation of waste must be considered before disposal and removal of waste takes place.

• Personal Protective Equipment should be worn, while workers with allergy to any materials of

plastering and painting works should not be allowed to communicating with such agents.

• All electrical connections and cables must be identified and clearly marked before going through

this activity.

• As much as possible, burying & filling up work waste within building floor especially remaining

waste of plastering. While grounds and work surfaces must be dry during all activities inside the building

• Painting involves using chemical and hazardous chemical substance. Therefore, handling and

storage of such agents must be done under direct supervision of site supervisor and the contractors well.

Sealed containers to keep such components and used liquids are required, whereas, containers must be

covered and closed all times.

• Mixing tools, proper equipment, and protective instructions should be available prior to make

painting work.

• Direct contact with painting materials is not allowed while workers must be provided with eye

protection devices, protective masks, gloves, shoes, and head protection devices when working on both

plastering and painting.

• All painting and chemical containers must be labeled to identify their contents while workers must

be aware about posted information and use requirements.

• All ladders and scaffolds required during this work must be convenient and provide protection

against potential work hazards.

Page 108: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

108

• Leaking containers of any sort must not be accepted on any account.

• Washing tank should be provided to wash work tools and devices at the end of each day.

• All chemical and painting substances must not be placed in salvage or garbage receptacles.

Whereas, pouring onto ground is not recommended.

• There must be enough ventilation in building when performing this task. Painting materials may

cause serious health effect especially if it is swallowed or enter inspiration system. Thus, safety

precautions should be applied and considered by all workers.

• Spill accidents is prohibited. Any spill must be cleaned up immediately.

• Smoking is not allowed and any flammable action may lead to breaking out of fire inside the

building.

• Disposal of painting substance should follow instructions and methods of landfill management rules

otherwise Re-use &Re-cycling may be recognized.

• During transportation, scattering is prohibited and containers should be well tight and close all

during transportation.

• Caution & danger signs might be posted on trucks and label might be attached to disposal

materials.

3. Flooring & Decoration Work Mitigation Measures

• Using of available & construction debris to filling up and leveling ground before lunching flooring

work.

• All flooring & decoration equipment and manual devices should be available.

• Personal safety devices and suitable manual tools should be provided.

• Workplace safety & health procedures must be considered by all involved workers.

• There must a short break over flooring periods to avoid adverse health impact owing to long time

sitting and standing.

• Workers must be aware of handling sharp devices and tools with incisive ends and edges.

• Small amount of chemical substance and coloration materials must be handled with care and based

on handling requirements attached to the products.

• All waste must be collected in special garbage boxes. Whereas, workers should segregate waste

before disposal is lunched.

• Workplace must address enough ventilation and suitable illumination environment.

4. Installation of Furniture &Building’s Supplies

• All safety measures related to materials handling must be recognized

• Furniture and offices supplies should be wood made or plastic resistive materials including doors,

chairs, and desks.

• Metal supplies are not preferred. Care must be given to avoid electrical connection with metal

materials and supplies.

• Floor of power supply room must be cemented well to prevent any penetration of spills and

contamination into underground layers.

• Generator must be selected based on low emission exhaust. Motor may supplied with filter and

long pipe outlet. In addition, it is recommended the generator to be equipped with suitable type of barrier

to avoid personnel injury or property damage.

• All equipment and supplies must be designed and constructed to provide personnel protection.

• As much as possible, including environment-friendly products and environmentally sound

equipment within all work supplies.

• Glass used in windows, doors, and walls (including glass block) must be able to withstand a human

impact, and if required by code, be shatterproof “safety glass.”

Page 109: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

109

• The building might be equipped with self-closing features that break fire through proper closures

installed on doors and hallway closures.

• Building must be supplied with fire hydrants and proper fire extinguishers. Instructions and labels

must be provided on all fire cylinders.

• All disconnecting switches and circuit breakers must be labeled to indicate their use or equipment

served.

• All electrical cables, breaks, switches, and connections must be covered to prevent direct contact.

Whereas, installation of electronic equipment and devices should comply with safety procedures of office

constructions.

• All interior wiring systems must include provisions for grounding metal parts or electrical raceways,

equipment and enclosures.

• All electrical raceways and enclosures must be fastened securely in place.

• All unused openings (including conduit knockouts) in electrical enclosures and fittings must be

closed with appropriate covers, plugs or plates.

• First Aid Box is recommended during construction and operation stage

5. Mitigation Measures of Free & Green Spaces

• Free space including parking area, passageways, and green spaces must be identified and marked

• Preparation of land must avoid creating dust concentrations through spraying water before and

during land preparation.

• All safety measures have to be implemented while noise levels must be minimized through using

equipment with low nuisance noise and implementing mitigation measures discussed in this document.

• Parking area must not be very close to employees’ offices but it must not be far from the building.

• There must be enough space between cars and parking lines.

• This area might be equipped with flexible sunshade to prevent potential damage caused by direct

sunshine.

• When preparing green space, one may consider using allocated Top Soil for planting purposes.

• Plants and flowers should be selected based on plant low water requirements and dry resistant

capacity.

• Additionally, there are different kind of flowers and plants that prove its ability to absorb pollution

through its stomata and pores. Thus, this consideration might be taken into account when making this

work.

• The contractor should consider leaving and incorporating exist standing and ligneous trees within

these spaces.

• Garden should be supplied with modern irrigation techniques whereas asphalt spaces are required

in parking area.

6. Installation of Fire Extinguishers & Ventilators

• During all construction activities, fire extinguishers must be provided to fight unexpected fire caused

by work mistakes or equipment’s’ failure. Whereas, workers must be trained previously to use and handle

fire cylinders.

• The building should be equipped with at least three fire extinguishers in each floor. Additional

extinguisher is required in the power supply room which might be used during emergency to fight fire in

parking and garden area too.

• The building is recommended to contain one to two fire hydrants. They can be installed near to the

building’s main entrance and storage room. Charge source of water must be designed close to the

hydrants in order to supply water during emergency.

• Use instructions and safety handling of hydrants & extinguishers must be made available by the

contractor or dealer.

• It is recommended to allocate place for body and hands washing purposes especially after handling

chemical materials.

Page 110: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

110

• Artificial ventilators are required particularly in offices that include heat- very- sensitive- equipment and materials while work environment must be cool to practice daily work. Therefore, building should include adequate ventilation & lighting openings based on project’s construction details.

Page 111: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

111

7.3.2 Mitigation Measures during Operation Stage

Mitigation Measures of Waste & Site General View

During operation, waste management & maintenance of building’s general view can be achieved through

applying the applicable techniques mentioned below:

• There must be a clear and detailed waste management plan for the building over this period.

Disposal methods and schedule times must be mentioned in the plan.

• Identification of responsibilities and nominated employees to follow up implementation of waste

management. However, the municipality management must allocate budget to handle this activity.

• There must be an inventory list of regular used materials, supplies, equipment, and all work

requirements. Nominated department must be aware of all requirements.

• Waste management must be shared by all employees. All involved workers and building should be

given a short training about their role in managing work environment and following safety procedures.

• All offices and rooms should be equipped with proper garbage and waste collection receptacles

based on generated waste within each room.

• Potential liquid waste like ink, cleaning chemical substance must be collected in proper sealed

containers

• Safety measures and personal protective equipment must be available when making this task.

• Waste should be segregated based on its nature and type. Employees should take part on this

side by helping segregation of waste at their offices.

• Disposal plan should give preference for Re-use, Re-cycling of waste before another decision is

taken.

• Waste scattering is totally prohibited by all workers and employees.

• Smoking area must be identified and special collection receptacles must be provided.

• It is recommended to enclose Green spaces with short fences and garden internal routes can be

identified to minimize walk and moving around impacts.

• Planting green space with plants capable to absorb major pollution of surrounding air.

• Waste must be disposed off on time while green and free spaces must be maintained regularly.

• Operation of electrical generator and handling of motor materials must be undertaken with high

considerations to follow safety measures attached to the motor and requirements of waste management

of lubricant & oil.

• Spill accidents in power supply room are prohibited while liquid waste must be collected in plastic

and special metal containers. Liquid collected waste might be reused or recycled by workshops & waste

recycling agencies

• Minor impact of motor emissions can be mitigated through making regular maintenance of the

motor and avoid using second hand oils. Moreover, motor may include outlet with filter or low emission

performance exhaust. Whereas, motor’s noise is not expected to make adverse impacts especially with

designed barrier on the motor and the quite far distance of power supply room from offices.

• The building must be equipped with waste collection containers. Those containers may contain

separated compartments to facilitate waste collection and segregation process.

Page 112: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

112

• Using of second hand lubricants and oils are not permitted.

• Spill accidents should be handled promptly.

• Liquid waste must be collected in sealed and proper plastic containers.

• Disposal of liquid waste into sanitation network is totally prohibited.

• Recycling and transporting of such waste to recycling agencies or near workshops should be

considered.

8.2.6 Emergency Plan & Natural hazards Prevention Program

Generally, emergency plan is not considered by many agencies and governmental authorities. Usually,

this plan is designed to protect personnel from further injury and to minimize property damage. Natural

hazards are unavoidable events especially with rapid change of climate whose impacts become obvious

and indicate serious challenges before development projects.

Moreover, climate change impact is thought to expand throughout long- term- time with uncertainty about

impact magnitude on regional & local level.

However, ESIA does not focus on direct impact and unknown impacts of climate rather than suggest some

practical mitigation measures towards any natural & man-made hazards that might occur during operation

period:

• There must be annual allocated budget to meet emergency plan requirements. This budget can be

incorporated within the authority total budget of renovation and maintenance.

• The authority may design own preparedness & response program and include it within its

ongoing strategy. What to do during emergency? Is the best explanation statement to make program

contents. Emergency during fire, potential earthquake, electricity accidents, and failure of work's

equipment are some examples that can be addressed.

• Short training course on safety measures and emergency response is recommended for all staff

and employees.

• During emergency, documents and equipment are subject to damage, loss, and robbing crime.

Therefore, securing authority’s information may require back up or other methods to save files and

documents.

• Using & purchasing equipment with acceptable resistant capacities.

• Any damage of building materials, body, equipment must be maintained on time and renovation

work should be carried out whenever it is required.

• Reparation of equipment and work supplies on time.

• As much as possible, the authority may take into account having back up place to practice its

work during emergency.

• From time to time, checkout of emergency & fire exits and maintenance work should be taken if

inspection indicates needs to do such work.

• Free spaces might be used for temporary evacuation during emergency. Thus, they must be

considered to be free from any obstacles.

• Safety instructions & warnings can be posted on the most hazardous places and attached to the

information board of the authority.

• Municipality should have an inventory list and details about daily work requirements and used

materials.

• All equipment, hardware, and objects inside and outside of buildings must be adequately restrained

and/or anchored to ensure that they do not block escape routes during emergency.

• The building might be supplied with emergency & evacuation alarm system. It is available as

manual & automatic devices.

Page 113: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

113

Table (8): Mitigation Measures Detailed plan

Preparation & Construction Stage

IMPACT MITIGATION MEASURES RESPONSIBILITY ESTIMATED COST

Preparation, Excavation,

and General Waste of

Work Site

1. The contractor, must follow &implement waste

management measures included in

ESMP document.

2. Re-use of construction waste within the work site.

3. The contractor commits to make segregation of worksite

waste. Whereas, the site should be supplied with different

type of garbage containers. Colored plastic garbage and

labeled boxes can be used

4. Collection of undesired construction waste and debris in

specific collection points in the site within special

receptacles. Selection of waste collection site must be pre

agreed with the municipal site supervisor engineer.

5. Construction work may be avoided during rainy periods in

order to avoid transmitting of waste and debris. Whereas all

work materials must be covered with proper sheets.

6. Scatter of waste should be avoided. While workers room

should be supplied with waste garbage and disposal of such

waste must be done based on waste type and quantity.

7. There must be solid waste storage tank in the room and

must be connected to local network.

8. Disposal of all waste should be done in the landfill and

follow instruction of construction permission and landfill

management requirements.

9. Liquid waste like water needed during construction should

be collected on separate tank and water should not

The Contractor

To be part of the

Contract.

Page 114: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

114

Preparation & Construction Stage

IMPACT MITIGATION MEASURES RESPONSIBILITY ESTIMATED COST

accumulate on site. Besides, drainage of water to outside

area is forbidden.

Soil Compaction &

Contamination

1. Surface soil must be kept aside to be used later within

green spaces, if possible.

2. Trucks and involved vehicles should follow specific &

identified traffic routes.

3. Spill accidents must be prohibited. If any spill accidents

occur, it should be cleaned immediately and collected in s

separate disposal container.

4. In case soil is compacted in some unavoidable places,

plowing is urgently needed particularly for green spaces

allocated area.

The Contractor Part of the Contract.

Page 115: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

115

IMPACT MITIGATION MEASURES RESPONSIBILITY Est. COST

Air Quality & Noise

Levels

1. Spraying water on foundations before

excavation work takes place. Water must be used

when there is raise up of dust like sand lifting and

handling.

2. Spraying of water may take place every day to

prevent dust concentration. This action might be

required in many places in work site.

3. Dust and fine particles should be always within

low level during all construction activities.

4. Transportation trucks are preferably selected

based on motor performance and low emission or

filtered exhaust presence. Old vehicles & trucks

with high emissions are not allowed to be used.

5. Truck engine must be switched off when on site.

6. Noise barrier should be constructed around work

area and should be high enough to prevent noise

transmission and taking neighboring residents’

attention.

7. Noise within work site can be minimized by

providing workers with special equipment like ears

protective equipment and masks. Workers in stone

quarry location must be provided with PPEs as

well.

8. Transportation of materials and waste might be

scheduled during the afternoon period to avoid

making any disturbances

The Contractor

Page 116: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

116

IMPACT MITIGATION MEASURES RESPONSIBILITY Est. COST

Materials Transportation

& Storage

1. Materials transferred to the site must be tight

well to the truck and covered by an appropriate

sheet.

2. Sand is liable to scatter during truck movement.

So, water must be sprayed on it and it should be

covered appropriately.

3. Truck back door must be closed during

transportation.

4. Materials and equipment storage location must

be agreed previously with site engineer. It must not

be far from work site location.

5. Separation of materials based on their nature

and type, is preferable.

6. Flammable or oil components materials and

machinery equipment should not be aggregated

with construction or organic materials.

7. Materials on storage location must be covered

with suitable plastic wrap and surrounded by short

stones wall to prevent weathering and rainfall

effects.

The Contractor Be part of the Contract

Transportation Safety 1. All drivers should drive safely

2. Transportation’s instruction and signs must be

posted on site and along transportation way

3. Drivers should commit to wear PPEs when

driving. For example, seat belt must be fastened all

times during transportation.

4. Drivers should follow a limit speed of 30-45 km/

h which might be a good acceptable limit.

5. Drivers must avoid driving and transporting

materials & waste during rush time.

The Contractor To be part of the

Contract.

Page 117: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

117

IMPACT MITIGATION MEASURES RESPONSIBILITY Est. COST

6. Vehicles must follow specific routes and avoid

obstructing traffic.

7. During transportation all transported materials

and equipment must be tight well to the truck and

waste scattering is not accepted.

8. Trucks & vehicle must be switched off when on

site.

9. Drivers should avoid passing near to flammable

source and smoking is not recommended when

driving.

10. All materials should be covered and sand may

require spraying with water before covering with a

sheet

Page 118: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

118

IMPACT MITIGATION MEASURES RESPONSIBILITY Est. COST

Work Site & Workers

Safety

1. The contractor must comply with all Jordanian requirements regarding health and safety.

The location of electrical power line and cables

must be determined before digging and excavation

work takes place.

2. Work sites must be clean and orderly. While all

site surface must be kept dry. Otherwise, proper

means might be taken to assure the surface is slip-

resistant.

3. Items and materials that are not required during

work hours must be removed from the work site.

4. PPEs are necessary during all times of work.

Hardhats, proper safety shoes, inspiration masks,

and ear protective tools should be worn by workers

whenever necessary. Moreover, safety devices

during indoor work like electrical connection,

painting, and plastering work are all required.

5. Storing debris and waste safely and removing

them immediately from the construction site.

6. All construction safety requirements must be

addressed in this project. Workplace injury must be

avoided and the contractor is responsible to follow

up safety procedures.

7. Workers must be careful when working near floor

and ground openings. While, openings should be

marked and easily identified by all workers and

drivers.

8. Floor openings and trenches must be shored

and distance of 30 cm between excavation

produces waste and proposed hole should be

The Contractor

Will be part of the

Contract.

Page 119: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

119

IMPACT MITIGATION MEASURES RESPONSIBILITY Est. COST

considered to avoid filling up of waste and to

prevent work accidents.

9. Bending & forming of construction steel must be

done with care and high safety measures

application. Suitable manual tools and safety

protective agents must be applied during this work.

10. All aisles and passageways must be identified

and marked.

11. Lifting and moving of heavy objects should be

done by mechanical devices.

12. Ladders & scaffolds must be checked up each

time before climbing. Damaged ladders & scaffolds

should never be used.

13. If metal ladders & scaffolds to be used, they

must be checked up on corrosion and they must be

isolated from communication with any electrical

connections.

14. Manual lifting and handling materials must be

evaluated before undertaking relative work.

15. There must be rain clear paths and proper

drainage system to avoid accumulation of rain

water on site.

16. All electrical power supplies and connections

must be grounded while dangerous voltage and

current must be isolated by covers & enclosures.

17. All painting and chemical containers must be

labeled and workers must be aware how to handle

those materials. Leaking containers should not be

accepted while workers should not pour paint

remaining onto ground. There must be sealed

containers to collect and dispose such substances.

Page 120: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

120

IMPACT MITIGATION MEASURES RESPONSIBILITY Est. COST

18. There must be a washing tank on site to wash

manual and work tools at the end of each working

day.

19. Firefighting equipment and fire extinguishers

should be available while workers must be trained

to handle fire prevention cylinders.

20. Smoking is not allowed at site. Disposal of

cigarettes may lead to break out of fire.

21. All drivers and workers must be trained about

environment and safety measures.

Page 121: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

121

IMPACT MITIGATION MEASURES RESPONSIBILITY Est. COST

Management of

Workers Residence

1. Management of workers residence or room and

all potential waste must be maintained through

direct supervision of site engineer.

2. Residence must be established on free space

area and should be near to sub-project’s location

3. It must be supplied with solid waste storage

tank that must be connected to the local network

or to separate sink. Design of this system and

disposal process should be discussed & agreed

with municipal site supervisor engineer.

4. If kitchen to be included in this room, there must

be gray tank to collect water of kitchen activities

considering use of water for existing trees and

nearby green spaces. While organic waste should

be collected and disposed off outside the site in

designated garbage containers.

5. There must be temporary tank within the area

to be used for washing purpose.

6. There should be enough garbage bins for waste

disposal.

The Contractor

Public Health of

Workers

The contractor must comply with all Jordanian regulations regarding health and safety.

Work assignment should be given based on

physical condition and worker’s capability.

2. The contractor must cover health insurance of

workers during work.

3. Worker’s residence must be comfortable and

hygienic condition should be monitored by site

engineer.

The Contractor Must be included in the

contract

Page 122: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

122

IMPACT MITIGATION MEASURES RESPONSIBILITY Est. COST

4. Workers are prohibited to directly communicate

with chemical substance like painting materials.

Therefore, workers with allergy should not handle

cement and concrete materials.

5. Smoking must be avoided when on work.

6. First Aid Box should be available during

construction.

Designs of the

Building & its

Supplements

1. The building should have at least two

emergency exits and one fire door.

2. There must be a separate toilet for women. Its

location must not be close to men toilet.

3. Additionally, there must be small prayer area

and rest place for women. It can be near to toilet

location.

4. Cafeteria room and rest place is required.

5. Small smoking area might be included.

6. Free & green spaces area should be designed

with separate water source. Construction should

follow project’s quantity tables that include

installation of modern irrigation technique within

green spaces area.

7. Installation of water rational automatic taps is

preferred.

8. Power supply room should be designed to

include enough ventilation and light openings.

Also, it has to be cemented well to prevent any

soil contamination.

9. Using the top soil for green spaces and garden

purposes.

Ramtha

municipality/

Engineering firm/

the Contractor

Designs to be reviewed

/ Contractor should

follow final design of

the project

Page 123: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

123

IMPACT MITIGATION MEASURES RESPONSIBILITY Est. COST

Socio economic

Development

1. Nearby residents of work site and near houses

must be given priority when selecting local labors.

2. Workers should not disturb employees of

nearby agencies.

3. The contractor must follow engineering design

of the project and use entrance pointed by the site

engineer. Preferably, purchasing materials

required for work activities from near shops and

markets, unless such materials are not available

in this area or its price is not reasonable.

The Contractor Must be included in the

work Contract

Community Health and Safety

The contractor is required to have a code of conduct covering worker interactions with the community, including children. The Code of Conduct is applicable to all of its workers as well as subcontractors. All workers including subcontractors, are required to acknowledge that training in the code of conduct has been received.

The contractor Must be included in the contract

Page 124: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

124

During Operation Phase

IMPACT MITIGATION MEASURES RESPONSIBILITY ESTIMATED COST

Waste

Management

1. All involved workers should be

given a short training about their role

in managing work environment and

following safety procedures.

2. All offices and rooms should be

equipped with proper garbage and

waste collection receptacles.

3. Potential liquid waste like ink,

cleaning chemical substance must be

collected in proper sealed containers.

4. Waste should be segregated

based on its nature and type.

5. Disposal plan should give

preference for Re-use, Re-cycling of

waste before another decision is

taken.

6. Waste scattering is totally

prohibited by all workers and

employees.

7. Smoking area must be identified

and special collection receptacles

must be provided.

8. Waste must be disposed off on

time while green and free spaces

must be maintained regularly.

Ramtha Municipality

To be included within the

monitoring & maintenance

budget of Municipality

Page 125: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

125

During Operation Phase

IMPACT MITIGATION MEASURES RESPONSIBILITY ESTIMATED COST

Workplace

Hazards & Health

1. All electrical and electronic cables,

and equipment must be designed to

provide personal protection while

cables must be covered and prove

high resistance to electricity

fluctuation and voltage variations.

2. Parking area should be identified

with marked lines and blocks.

3. Municipality should make regular

inspection of firefighting

extinguishers. This action might be

conducted twice a year to ensure

validation of fire extinguishers.

4. Handling and storing of chemical

substances & cleaning materials

should follow official safety & health

precautions.

5. It is always recommended to equip

constructions and office building with

First Aid Box.

6. Corridors and aisles must not be

used for storage purposes.

Ramtha Municipality To be included within the

Monitoring Plan Budget

Page 126: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

126

IMPACT MITIGATION MEASURES RESPONSIBILI

TY

Est. COST

Soil Compaction & Green

Space Deterioration

1. There must be paved routes

across and surrounding the green

areas.

2. It is recommended for green

spaces to have instructions and

warning signs about proper use of

the garden.

3. Workers and employees should

be aware about the necessity to

avoid making soil compaction and

deteriorating of grass and existing

plants.

4. There must be enough garbage

and constant metal baskets to

collect potential waste.

5. Scatter of waste is not allowed

within this space.

6. Safety equipment and plantation

manual tools must be available and

cleaned all the time.

7. Smoking is prohibited in green

spaces.

8. Mixing of long live trees, salinity

resistant flowers, and plantation

diversity is a good option to avoid

applying pesticides. While this

technique is considered to be a

natural treatment method should be

improved and encouraged.

Ramtha

municipality

To be included within maintenance

budget of the Authority

Page 127: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

127

IMPACT MITIGATION MEASURES RESPONSIBILI

TY

Est. COST

9. In order to avoid accumulated

impact of salinity, green spaces

might be constructed with surface

or underground channels

connected to rainwater existing

streams. Direct rain water is

enough to minimize salinity

concentration but this technique

helps to wash up salinity within the

soil.

10. Vehicles are forbidden from

entering this area.

11. In case compaction occurs,

plowing with spraying water is an

appropriate method to recover

compacted soil. However, water

should not accumulate on surface

to avoid attracting pests and dirt.

12. Modern irrigation techniques

like drip irrigation and sprinkler can

be used.

13. It is recommended to enclose

green spaces with short fences.

Page 128: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

128

IMPACT MITIGATION MEASURES RESPONSIBILITY Est. COST

Handling & Storage of

Materials

1. Materials and equipment must

be separated into compatible

groups. Storage is based on

nature and type of stored

materials and equipment.

2. Storage room must be

equipped with adequate

ventilation openings and lighting

sources.

3. Storage room must be clean

all times and well arranged.

Whereas, materials should be

kept in separate shelves and

labels must be posted on each

shelf explaining contents and

safe handling instructions.

4. Special handling of chemicals

must be considered. For

instance, cleaning materials and

ink used for copy machines and

printers must be handled with

care. Direct contact with such

substance should not happen.

5. Personal safety equipment

must be provided when handling

such materials.

6. Recycling and reuse policy

should be in account when

disposal of waste.

Ramtha

municipality

To be included with Municipality

ongoing plan

Page 129: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

129

IMPACT MITIGATION MEASURES RESPONSIBILITY Est. COST

7. Storage room might be

supplied with fire detector and

fire alarm system. While

firefighting cylinders should be

always available.

8. Application of chemicals must

follow instructions attached to

the product.

9. There must be regular follow

up of materials storage and room

condition. Dust concentration

should be cleaned while spills

must be removed immediately.

10. Water taps and accessible

water source must be

constructed near to storage

room.

Emergency Plan &

Hazards Prevention

Program

1. There must be annual

allocated budget to meet

emergency plan requirements.

This budget can be incorporated

within the authority total budget

of renovation and maintenance.

2. The authority may design own

preparedness & response

program and to include it on its

ongoing strategy. What to do

during emergency? Is the best

explanation statement to make

program contents.

Ramtha

municipality

To be included with municipality

ongoing plan

Page 130: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

130

IMPACT MITIGATION MEASURES RESPONSIBILITY Est. COST

3. Short training course on safety

measures and emergency

response is recommended for all

staff and employees.

4. During emergency,

documents and equipment are

subject to damage or loss.

Therefore, securing authority’s

information may require back up

or other methods to save files

and documents.

5. Any damage of building

materials, body, equipment must

be maintained on time and

renovation work should be

carried out whenever it is

required.

6. As much as possible, the

authority may take into account

having back up place to practice

its work during emergency.

7. From time to time, checkup of

emergency & fire exits and

maintenance work should be

taken into consideration.

8. Free spaces might be used for

temporary evacuation during

emergency. Thus, they must be

considered to be free from any

obstacles.

Page 131: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

131

IMPACT MITIGATION MEASURES RESPONSIBILITY Est. COST

9. Safety instructions & warnings

can be posted on the most

hazardous places and attached

to the information board of the

authority.

10. Municipality should have an

inventory list and details about

daily work requirements and

used equipment.

11. All equipment, hardware, and

objects inside and outside of

buildings must be adequately

restrained and/or anchored to

ensure that they do not block

escape routes during

emergency.

12. The building might be

supplied with emergency &

evacuation alarm system. It is

available as manual & automatic

devices.

Page 132: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

132

Chapter 8

Environmental and Social Monitoring Plan

Page 133: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

133

8.1 Monitoring Arrangement

During sub-project construction phase, Periodic Monitoring Report should be prepared by the site

engineer and revised by the Safeguards specialist in the PMU. It is the Municipal site supervisor engineer’s

task is to observe work site activities and to ensure the contractor’s compliance with the contract

requirements, the ESMP for all potential environmental and social impacts mentioned in the ESIA study.

The ESMP and ESIA will be included in the tender documents for the project.

Preparing monitoring reports requires conducting field visits to sub-project site and in some exceptional

cases, the supervisor may require taking sample tests from different places of the sub-project to compare

it with former tests of the site. However, results of site observations should be mentioned clearly in this

report while time and duration of monitoring activity must be stated. Suggestions of each report and any

recommendations should be discussed and considered by the municipality.

Monitoring activity may also include meeting surrounding residents and nearby affected groups

considering any emerging issue from social and health side. Such aspects should be handled on time and

reported to the municipality as to involve the Community Outreach specialist in the PMU in any case of

grievances regarding this sub-project, within the monitoring report. Shall mitigation measures are not

applied or monitoring field reports indicate incomplete management of environment and safety; then, the

supervising municipal engineer should report to the management in the municipality and the Safeguards

specialist in PMU.

Generally, the World Bank (WB) is responsible to review and approve findings & recommendations of

ESIA to determine whether they provide an adequate basis for processing the sub-project. If the ESIA and

the ESMP satisfy WB safeguard policies, then the document will be approved and the project can proceed.

In fact, the WB would not continue funding any sub-project that might lead to environment degradation or

social conflicts. Therefore, monitoring report should follow procedures and recommendations included on

those two documents.

8.2 Reporting

Reporting on the implementation of ESIA especially during construction period is the responsibility of the

supervising municipal engineer, in collaboration with the Safeguards specialist in the PMU. Once, the WB

approves to fund this sub-project, Ramtha municipality in collaboration with CVDB will be in charge to

complete contracting procedures and to directly follow up progress of project construction including

following up the implementation of ESMP. When field report is made, the municipality must review its

contents and send a copy of each monitoring report to PMU and then to the WB. Report must follow

monitoring activities and procedures mentioned within ESMP. Based on suggested measures, the

municipality and the site engineer may design a specific format or short pointed report to be used during

field monitoring process. It is expected that, the site engineer will prepare several monitoring reports over

construction period while time to make this work depends on construction work performance and

construction stages. In addition, the municipality and the site engineer have to determine when to make

this report on this basis, in collaboration with the Safeguards specialist in the PMU.

During each inspection, the site engineer should inform the contractor and the workers about any neglect

concerning environment, social, and safety sides. Findings of this discussion must be included with the

monitoring report even though problem under discussion is over. Afterward, the site engineer may conduct

quick and sudden visits to ensure undertaking matter is not reoccurring.

Page 134: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

134

Reviewers of the monitoring reports should not exclude any details or shortcomings mentioned in field

report and transparency must be in account when reporting to the Bank. The field report may indicate

undertaken treatment methods or ongoing actions made by the municipality to handle such failure of

project activities. In fact, this action will not affect progress of the sub-project rather than making all efforts

to maintain sub-project’s activities and to avoid any impact on local environment and residents.

In case, the contractor or site supervisor does not comply with ESMP & ESIA mitigation measures at all,

corrective actions should be taken by Ramtha municipality and information on this regard should be

delivered to responsible team in the PMU. The corrective actions may include certain fine that has to be

taken from the contract's budget as a reason of not implementing ESMP. In addition, CVDB may stop

delivering financial allowances of the contractor. If mentioned actions do not work, the municipality has the

option of going to the court and the contractor must be included within the black list. However, the

municipality must decide which action should be taken to manage this issue, and ALWAYS report to the

PMU.

Page 135: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

135

Table (9): Detailed Monitoring Plan

IMPACT MONITORING ACTIVITY FREQUENCY RESPONSIBILITY

Preparation, Excavation, and General Waste of Work Site

• There should be a list of expected waste during construction stage based on used materials and involved equipment. Decision must be made about the most critical waste to be monitored

• Waste collection points should be clearly identified before launching the construction work

• Determine which waste can be left and re-used on site and which must be taken

• Monitoring form to include date, contractor abidance by Health and Safety measures, any excavations found in the site and any emerging matters to be filled regularly by the site engineer and spot checks by the environmental Safeguards specialist in CVDB.

• Monitor and inspect the contractor compliance with ESIA report

• Recording all work in the site, activity location, date, time and work expected period.

• Transportation line and times of waste disposal must be mentioned in the report, in collaboration with the Traffic Management if necessary

• Review all documents relating to waste management and disposal including construction permission

• All hazardous waste and disposal methods should be mentioned. Whereas, time to occur and sites should be identified.

The Municipal Engineer may follow up within 1-2 weeks, and prepare weekly progress reports

The environmental specialist in CVDB/ the Municipal Site supervisor engineer, through Site inspection, Visual observation and photographic documentation.

Page 136: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

136

IMPACT MONITORING ACTIVITY FREQUENCY RESPONSIBILITY

• Consider climate influence and waste scattering

• Monitor used equipment, construction materials, trucks, volume of water requirement, and manual work tools

• Monitor PPEs used for each activity of waste disposal and handling.

• Record any spill, accidents, waste poor management during supervision visits

• Counting of workers & trucks number and identify their different waste.

• Make photographic documentation

Soil Compaction & Contamination

• Make sure that top soil has been removed aside to be used later on for garden purpose;

• Identify the most sites subject to soil compaction or contamination. And follow mitigation measures to maintain such impact;

• Identify soil potential source of pollution, pollution type, treatment methods;

• Deal withany spill accidents or soil contaminated by handling oil & liquid substance on worksite;

• Record soil collection containers and available garbage in work site; Monitoring identified working paths and workers compliance to avoid soil compaction.

The Municipal Engineer may follow up within 1-2 weeks

The environmental specialist in CVDB/ Municipal Site supervisor engineer through Site inspection & Visual observation and photographic documentation

Air Quality & Noise Levels

• Define air pollution sources, type, locations, remaining time and weather main drivers.

• Ensure water is used to maintain dust concentration and scattering of fine articles.

• Ensure all equipment and trucks are in a good condition and emission does not exist.

The Municipal Engineer may follow up on a daily basis

The environmental specialist in CVDB/ Municipal Site supervisor engineer through Site inspection & Visual observation.

Page 137: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

137

IMPACT MONITORING ACTIVITY FREQUENCY RESPONSIBILITY

• Identify noise disturbance sources, duration, time, most affected group, number of affected workers, mitigation requirement and cost of application.

• Make sure that noise prevention measures are applied. For instance, noise barrier and noise protective equipment.

Transportation of Materials & Storage

• Identify materials temporary storage locations and make sure such locations are not disturbing construction activities. Also, they must be away of truck & vehicles routes.

• All transported materials & waste should be covered with proper sheet. And scattering of waste must be avoided

• Drivers should follow safety procedures when making this task. While all materials should be tight well to the truck

• Water might be used to prevent scattering of sand during transportation

• Identify truck routes, truck condition, materials type, applied safety procedures, and estimated cost of application

• Temporary storage location must address protection against rain & weather conditions. Materials should be covered and surrounded by short traditional wall and drainage channels

• Materials should be stored in compatible group. Flammable materials should be separate from other construction materials

• Smoking is not allowed in storage locations

The Municipal Engineer may follow upon a daily basis

The environmental specialist in CVDB/ Municipal Site supervisor engineer through Site inspection & Visual observation and photographic documentation

Page 138: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

138

IMPACT MONITORING ACTIVITY FREQUENCY RESPONSIBILITY

Health and Safety Impacts

• Ensure the Contractor performs against his contractual obligations and the site-specific ESMP to mitigate work hazards, health hazards, and protect the public.

• Make sure all required PPEs are available and workers are assigned based on physical condition capacity

• Work site must provide protection against any risk and work hazards.

• All accidents and incidents should be recorded. Serious injuries should be reported to the Municipal Engineer immediately. Municipal Engineer checks accident/incident logs

• Check out scaffolds, ladders, floors, openings, and machinery used in this construction

• Inspect any potential threat of involved equipment on project’s components. In addition , equipment must be checked up to make sure they are in a good condition and they are safe to be used

• Inspect the existence of firefighting agents and workers ability to handle fire extinguishers. Make sure First Aid Box is on site

• Ensure the availability of PPEs for handling chemical & painting substances. While such materials should be labeled with explanation about its contents and use requirements

• All electrical connections and involved devices must be evaluated and protective measures of applying those devices must be attached to product boxes

The Municipal Site Engineer may follow up on a daily basis

The environmental specialist in CVDB/ Municipal Site supervisor engineer through Site inspection & Visual observation and photographic documentation

Page 139: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

139

IMPACT MONITORING ACTIVITY FREQUENCY RESPONSIBILITY

Safety of Transportation

• Make sure drivers are driving safely and following traffic safety measures

• Ensuring their compliance towards preventing waste scattering

• Check out trucks and vehicles applied speed based on mitigation measures recommendation and record any violation on this regard

• Ensure all requirements mentioned on mitigation measures table are followed accordingly.

The Municipal site engineer may follow up on a daily basis

The environmental specialist in CVDB/ Municipal Site supervisor engineer through Site inspection & Visual observation

Management of Workers temporary room in the site

• Ensure the room is equipped with suitable wastewater system and connected to local network or waste is disposed regularly through special tanker

• Identify waste produced from the room and number of residents

• Ensure hygienic condition of the room and the supply of adequate water sources for cooking and washing purposes

• Make sure workers are not using facilities of surrounding employees and guards

• Identify waste disposal methods

• Identify garbage and containers used to collect waste, with consideration to segregation, if necessary

The Municipal Site Engineer may follow up weekly

The environmental specialist in CVDB/ Municipal Site supervisor engineer through Site inspection & Visual observation and photographic documentation

Occupational Health of Workers

• Make sure worker is assigned based on physical condition and qualification

• First aid box availability

• Medical checkup is recommended, when necessary.

• Workers with allergy to any of materials of construction should not be working and if there is simple allergy to concrete or cement

The Municipal Site Engineer may follow up within 1-2 weeks

The environmental specialist in CVDB/ Municipal Site supervisor engineer through Site inspection & Visual observation

Page 140: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

140

IMPACT MONITORING ACTIVITY FREQUENCY RESPONSIBILITY

materials then worker must not communicate with such substances

• Make sure all workers are health ensured by the contractor.

Socio-Economic Development

• Ensure the involvement of local labors in this project and nearby residents and workers should be given priority when handling this work

• Just when it is required to have qualified and skilled labor , it can be brought from outside this area

• Workers must not disturb nearby residents and employees

• Purchasing materials required during construction from nearby markets and shops.

The Municipal Site Engineer may follow up within 1-2 weeks

The environmental specialist in CVDB/ Municipal Site supervisor engineer

Workplace Hazards & Health

• There must be always an inspection of the following;

• Storage room and storage materials condition

• Fire extinguishers and validation of hydrants

• All electrical cable and uncovered connections

• Copy machines and printers

• Medical checkup of employees

• Stability of involved supplies and materials

• Furniture and equipment validation

• First aid box availability

• Following other procedures mentioned in ESIA.

Over project designed age

Municipal Engineer through Site inspection & Visual observation and photographic documentation that are reflected in progress reports provided for the PMU

Page 141: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

141

Chapter 9

Social Study

Page 142: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

142

9.1 Social Consultation Program

Social study and consultations program started by conducting the following steps;

• Gathering documents and official letters of land ownership and land use permissions from

Ramtha municipality and MoMA.

• Conducting field visits and making rapid survey for social and economic activities within

surrounding area of the sub-project.

• Preparation of several social meetings with community members and social consultation

program, in which the prioritization of the sub-project was concluded, and is found in Annex 1.

• Documentation and taking photos of sub-project site and surrounding area.

• Meeting employees and direct beneficiaries of the project.

• Making interviews with local residents and nearby shopkeepers.

• Making list of meeting participants and interviewees.

• Incorporating consultation findings and comments in ESIA & ESMP document.

Seven community consultations took place during sub-project selection, a brief of those

consultations and the Community Consultations Methodology steps can be found in Annex 1.

A consultation session was conducted on January 13th, 2019 in one of the schools in Ramtha

municipality, as an invitation letter was prepared and sent to different governmental agencies, private

sector, NGOs, Women’s associations, direct PAPs of the sub-project and of course the mayor and

his staff. The PMU team made a brief presentation on the characteristics of the sub-project, World

Bank Policies on Environmental issues and Resettlement, how it was selected through community

consultations, and its expected impacts and mitigation measures of those impacts. The audience

showed clear support for the application of the sub-project, as it will minimize their time and effort in

doing their governmental paper work. Attendants included (46) persons, out of which were (19)

women representing different entities.

Page 143: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

143

Figure (7): ESIA Community Consultations

9.2 Findings of Social Study & General Recommendations

The construction of a new Governmental Complex for Ramtha municipality shall definitely lead to

temporary (but not irreversible) impact on local environment especially during construction stage.

Whereas, construction of this project is not expected to contribute in creating adverse impact on

social side.

In fact, social and economic returns of this project are high and beneficial compared to current

situation. Such benefits can be summarized as follows:

- Provide Ramtha municipality and the other governmental entities with an appropriate place to

practice daily work and service of the community.

- Reducing expected cost to lease another building.

- Facilitating dealings and transactions between the municipality and other nearby authorities and

citizens, as it will present a one stop shop for them.

Other benefits include:

Page 144: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

144

- The municipality staff is currently renting a building on the main street that connects Amman with

Damascus, for a total amount of 39,000 JDs (almost 56,000$) per year. The intended

governmental complex project shall have offices owned by the municipality, so as to save the

amount of rent when they move there.

- The project is supposed to generate income for the municipality and provide one stop shop for

the citizens in Ramtha that will help in providing a parking place, as well as minimizing the time and

effort needed to accomplish any governmental paper work for the citizens in Ramtha.

- Raising the employment rate and providing better municipal services through local economic

development, is the core objective of MSSRP, which is the key purpose of building this

governmental complex in Ramtha municipality.

On the other hand, potential environmental impact of the project is localized temporary, and can be

mitigated through implementing mitigation measures and procedures included in ESMP, as the

contractor shall have to submit an environmental and social health and safety plan that includes the

appropriate requirements to be reflected in the Special Conditions of the contract before signature.

In this study, the total expected cost of applying the ESMP shall be reflected in the tendering

documents of the Governmental Complex in Ramtha municipality, through the General and Special

conditions of the contract that the contractor must sign and abide by, according to FIDIC Regulations,

and the Labor Intensive Methods that the ILO shall apply in the MSSRP project, as part of their tasks

in training the PMU and municipal engineers, as well as the contractors, on Health & Safety issues

and decent work conditions that must be applied in the construction site. Also, ILO will be the

monitoring agency to insure that the percentage of Syrian workers is met, which was approved to be

30% The majority of this budget will be used to maintain mitigation measures during construction

while applying mitigation measures during operation will be the responsibility of Ramtha municipality

and throughout the project designed age.

It is also recommended that a session is held by the municipality, for the municipal staff and the

contractor, in cooperation with the Safeguards specialist in CVDB, in order to explain the ESIA

document and inform them on the procedure of implementing the ESMP, their responsibilities and

the way of monitoring the whole project.

A Remedial Abbreviated Resettlement Action Plan (ARRAP) was also prepared for 5 identified

PAPs, who were operating one kiosk in the land of the sub-project. Socioeconomic surveys were

prepared for each PAP, the purpose of conducting this study was explained and compensation

packages that include cash and in-kind compensations were discussed with them and approved.

The ARRAP has already been submitted to the WB specialists for approval.

Therefore, this project can be implemented BUT with application of mitigation measures mentioned

in this document, under the direct supervision of the site engineer, municipal staff and Environmental

specialist in CVDB.

Page 145: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

145

Annexes and References

- Environmental and Social Managenet Framewok - Field Visits and direct contact with Ramtha Mayor and Municipal Engineers - PMU Consultants - Different Project Documents.

Annex 1: First Round of Community Consultations (Sub-project’s selection)

- Community Outreach and Citizen Engagement process methodology for MSSRP:

STEP 1: Identifying the participating municipalities and the allocated funds.

STEP 2: Conducting preliminary meetings with the mayors and members of the

participating municipalities to:

- Meet with them and identify the general conditions of the municipality

- Gather statistical information about the local community such as: percentage of the local

population, percentage of refugees…

Page 146: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

146

- Setting an outline for the next phase of the project in terms of meetings and consultation

workshops, to ensure optimal citizen engagement.

STEP 3: Selecting the most appropriate means and tools for community engagement and

consultation

- Facilitating discussion groups or workshops, in which participants are selected randomly and

according to the demographic composition of a community.

- Preparing a plan that specifies the dates, venues and duration of the meetings with the

community members.

STEP 4: Setting up several meetings with community members and stakeholders to:

- Identify the views and needs of the local community

- Prioritize and arrange the issues and needs of the community

- Identify a preliminary list of the social and economic projects that address the community

needs identified previously.

STEP 5: Assisting in the identification of the project selection criteria that may include the

following:

- The project set by the local community

- Benefiting the largest possible portion of the community

- Number of jobs to be created

- Meeting the needs of women, youth, children and the most vulnerable groups

- Sustainability of the project

- Improving the quality of municipal services

- Enhancing community cohesion

- Boosting local economic activity

STEP 6: Mapping of the Stakeholders

Identifying the target groups for community participation which include (but are not limited to):

NGOs, community organizations (CBO), women, community leaders, community activists, Syrian

refugees, people with special needs, youth and unemployed citizens.

Page 147: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

147

STEP 7: Publicly announcing and calling for community engagement meeting through:

- Informing the local communities of such meetings

- Inviting the local communities with the assistance of local NGOS, mosques, municipal

advertisement…

STEP 8: Setting up the community engagement meetings to openly discuss and perform the

following:

- Setting the long list of projects

- Presenting the selection criteria of projects and the weighs of each criteria

- Narrowing down the long list based on the priorities and project criteria

- Coming up with the short list (top five projects)

Step 9: Assisting the Municipal committee in reviewing and analyzing the short list of

projects to determine the most feasible project to implement, in terms of:

- Technical review

- Operational review

- Financial review

- Safeguards screening

- Preparing the procurement plan

- Conducting the initial feasibility studies

Step 10: Inform the local community through various media outlets

- The eligible project will be announced to the public through different media platforms

The local community will be granted 5 days to submit any objections through the established

grievance mechanism in the municipality

Throughout Steps 2 and 3, a preliminary assessment meeting was conducted in the municipality in

order to have a clear idea about the local development unit tasks, establish the local community

committee, the grievance and social engagement mechanisms and the strategic plan for the local

community.

Step 4 and the rest of the steps included conducting seven community consultation sessions in

Ramtha municipality for the youth, both Jordanian and Syrian, women, people with disabilities, local

Page 148: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

148

council female members, and of course men, with a total number of 333 participants in all the

sessions. The final comprehensive session was conducted in May, 2018 in which most of the

participants voted for the Governmental Complex project as their priority.

- Beneficiaries: Number of beneficiaries is expected to be as follows:

(A) Jordanians: 155,693 which is divided into 81,231 males and 744, 62 females.

(B) Syrians: 80,000 which is divided into 488, 31 males and 311, 69 females.

Those (7) focus group sessions with different stakeholders were as follows:

- Session (1): on 22/4/2018 (morning), target group was (38) women, with ages that range between

(18-60) years old. Attendants included the Mayor, CVDB branch manager in Irbid, employees from

the municipality and CVDB branch, as well as the Community Outreach specialist in the PMU.

Priorities included:

* Nursery for the children of the female workers in the municipality.

* Market place for fruits and vegetables.

* Governmental Complex.

* Gym for the ladies in Ramtha municipality.

- Session (2): on 22/4/2018 (afternoon), the target group was (30) men, with ages that range

between (19-76) years old. Attendants included the Mayor, CVDB branch manager in Irbid,

employees from the municipality and CVDB branch, as well as the Community Outreach specialist

in the PMU. Priorities included:

* Comprehensive plan for Ramtha and Bwayda areas.

*Pedestrian bridge in Al-Kokh area.

*Stray dogs alleviation.

* Opening new roads.

* Construction of Gabion walls on the sides of the valleys in Ramtha municipality.

- Session (3): on 2/5/2018, the target group was (69) male and female Syrians, with ages that

range between (18-65) years old. Attendants included some employees from the municipality, as

well as the Community Outreach specialist in the PMU. Priorities included:

* Training and employment for handmade crafts.

* Better transportation in the area.

* Parks and playgrounds.

- Session (4): on 6/5/2018, the target group was (20) male young people, with ages that range

between (14-18) years old. Attendants included some employees from the municipality, as well as

the Community Outreach specialist in the PMU. Priorities included:

Page 149: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

149

* Support of folklore activities.

* Rehabilitation of an existing meeting hall.

* Swimming pool.

* Productivity projects.

* Paper recycling.

- Session (5): on 12/5/2018, the target group was (62) male and female, representatives of the

local NGOs, people with special needs, with ages that range between (14-70) years old.

Attendants included the Mayor, some employees from the municipality, municipal council

members, as well as the Community Outreach specialist in the PMU. Priorities included:

* Box culverts.

* Paving.

* Governmental Complex.

* Central market for fruits and vegetables.

* Sidewalks and curbs.

- Session (6): on 14/5/2018, the target group was (31) male and female Jordanian and Syrian

young people, and some NGO representatives, with ages that range between (18-40) years old.

Attendants included some Local Development Unit employees from the municipality. Priorities

included:

* Governmental Complex.

* Box culverts.

* Opening new roads.

- Session (7): on 20/5/2018, a comprehensive meeting with all target groups of (72) participants

including (30) males and (42)females from the local community with ages that range between (15-

60) years old. Attendants included the Mayor, some employees from the municipality, municipal

council members, as well as the Community Outreach specialist in the PMU and supervising

engineers from CVDB branch in Irbid. Priorities included:

* Governmental Complex (almost 63%).

*Opening new roads.

* Sidewalks and curbs.

* Box culverts.

* Paving.

Page 150: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

150

Annex 2: Feasibility Study Summary The project was listed as top priority in the community consultations conducted earlier in the

municipality. The design of the project was awarded on a private consulting company with a total

amount of 12,500 JDs (almost 18,000$). The project is expected to start by the end of 2018, and

end in August 2019 as the first stage, while the second stage is expected to start in September 2019

and end in April 2020. The municipality provided documents to show its financial capability to fund

the project, besides its allocation from MSSRP.

The table below shows the sub-project budget for the entire period of implementation:

Sub-Project Budget

Funding source Amount (JOD) Number

MSSRP FY2018 668,000 1

PM Budget FY2018 325,750 2

PM Budget FY2019 662,500 3

PM Budget FY2020 662,500 4

2,318,750 Total

Page 151: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

151

As the municipality is located directly on the Syrian border, a noticeable increase in the population

as well as increase in most economical sectors in the municipality, thus an increase in the demand

for the basic infrastructure services with a slight increase in the unemployment ratio in the

municipality that reached almost 18.4% for year 2017.

According to the feasibility study, there are 8 governmental entities that are willing to rent offices in

the governmental complex with a total amount of income that will reach 251,650 JDs (almost

366,000$) per year. Those entities include:

1- Directorate of Municipal Affairs

2- Health Directorate of Ramtha

3- Department of Land And Survey

4- Civil Status And passport Department

5- Directorate of Social Development

6- Directorate of Antiquities

7- Directorate of Public Works and Housing

8- Directorate of Labor

The municipality shall prepare the site for construction using its equipment, after conducting a soil

test for the site with a total amount of 6,000 JDs (almost 8,500$). The electrical convertor, which is

located at the edge of the land, shall be used to provide electricity for the building, in coordination

with the Jordanian Electricity Company.

As for the maintenance plan provided by the municipality, a qualified municipal staff shall operate

the building and shall be paid from the budget of the municipality for this purpose, with an estimated

amount of 18,350 JDs (almost 26,000$).

Annex 3: Summary Report and Attendance sheet of ESIA Consultations

Report Summary:

, 2019thDate: January 13 Venue: Om Kalthoum Intermediate School, Ramtha Municipality Time: 10:00 a.m.

MSSRP Project Deputy and PMU members including the Safeguards specialist, Site engineer and Community Consultation specialist, gave a brief presentation to the audience, that included the mayor, municipal staff and community members from different backgrounds and representatives of some active NGOs in the community.

The presentation included brief description of the sub-project’s main components, the selection method, possible impacts that the sub-project would have on the environment, the mitigation measures that will be taken in coordination with the municipal staff and the contractor, monitoring procedures and some social impacts that might accompany the sub-project implementation.

The audience were very supportive of the idea of constructing such a governmental complex and that they have been waiting for this sub-project for years. Some expressed their concerns regarding the quality of work that needs to be monitored well, and the PMU assured them that this will be done closely with the municipal staff through submitting periodic progress reports and the reinforcement of grivance redress mechanisms applied in the MSSRP project as a whole, and in specific for Ramtha municipality, as an Environmental and Social Management Plan was prepared for this purpose.

Page 152: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

152

Attendance: Provided in sheets below

Page 153: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

153

Page 154: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

154

Page 155: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

155

Page 156: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

156

Page 157: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

157

Figure (8): Letter of Designation from Department of Land and Survey to Ramtha Municipality

Annex 4: Community Consultations for the Design of the sub-project and Attendance

Sheet

محضر اجتماع

مشروع تحسين الخدمات والتكيف الاجتماعي للبلديات المستضيفة للاجئين السوريين

مجمع الدوائر الحكومية / بلدية الرمثا الكبرى

Page 158: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

158

مكان الاجتماع : حديقة الشياح

15/4/2019 الاثنين التاريخ :

الواحدة مساء –العاشرة صباحا الساعةالوقت :

الحضور :

وحدة ادارة المشروع: سهى قول / ريم حلوش/ اسماء العبدالله/ خولة الحسن / ثائر زيادنة

لجهات المانحة: البنك الدولي )لينا عبدالله، غادة شقور( / ممثل عن السفارة الكندية ا

مدير وحدة التنمية المحلية/ –لدية الرمثا الكبرى: نائب رئيس البلدية حسين الجراورة/ رقية العكور ب

مسؤول الاعلام -عبدالغفار الزعبي

لحضور من المجتمع المحلي: اعضاء المجلس البلدي/ المؤسسات المحلية والجمعيات: جمعية الرمثا ا

للمعاقين/ جمعية العدالة/ مركز الأمل للحالات الخاصة/ جمعية البويضة للمتقاعدين/ فريق التطوير

المجتمع.

لاجتماع : موضوع ا

والبنك الدولي وبنك تنمية المدن والقرى والمكتب الهندسي المصمم لمخططات المشروع ومندوب من المانحةلقاء بين الجهات

المبنى وعدد من الجمعيات الحكومية التي تنوي الاستئجار في المجتمع المحلي والدوائر أفراد السفارة الكندية مع عدد من

المشروع .تنفيذ لمشروع امام الحضور وتوضيح الاثار المتوقعة من التصميم الداخلي ل الخيرية لعرض

وقائع الاجتماع :

ترحيب بالالسيد حسين الجراورة رئيس بلدية الرمثا نائب ح الاجتماعبتجهيز القاعة للاجتماع وقد افتتقامت بلدية الرمثا

توضيح لهم عن طريقة اختيار المشروع .بالحضور وال

همية المشروع واهدافه ومدى بالحضور وتوضيح أبالترحيب (وحدة التنميةعكور )بلدية الرمثا / مديرية قامت المهندسة رقية

الحاجة له.

للمشروع امام الحضور وتوضيح الاثار المتوقعة خلال توضيحي( بعرض ريم حلوش )وحدة ادارة المشروعقامت المهندسة

مدة التنفيذ للمشروع .

لمشروع :تمويل ا

الف (دينار اردني 668) مشروع تحسين الخدمات والتكيف الاجتماعي للبلديات المستضيفة للاجئين السورينمنحة من -1

.

( دينار اردني.1650750بقيمة ) سيتم تمويل باقي تكاليف المشروع من موازنة البلدية -2

( بتوضيح ما يلي :/ دارة عمان )المكتب الهندسي المصمم للمشروع الجنيدي قام المهندس احمدوقد

.(طوابق 7عدد طوابق المبنى وهي ) -1

(. 2م1200مساحة كل طابق وهي ) -2

Page 159: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

159

(. 2م450مساحة كل جناح وهي ) -3

الداخلي حسب بحيث تستطيع كل دائرة بالتقسيمبان التصميم الداخلي لبعض الدوائر سيكون بدون حواجز التوضيح للحضور تم

لتصميم بحيث تراعي وجود رمبات وحمامات لذوي الاحتياجات الخاصة.حاجتها. كما تم عرض صور من ا

مسبقا على الاستئجار من المبنى المقرر ائر التي تم اخذ الموافقة وذكر اسماء الدب( وقامت المهندسة رقية )بلدية الرمثا

انشاؤه.

ماعية والبيئية للمشروع مثل:عن الفوائد الاجتدسة ريم )وحدة ادارة المشروع(بالتوضيح للحضور المهنكما قامت

.مصدر دخل للبلديةكونه -1

ين خلال فترة تنفيذ المشروع.خلق فرص عمل للمواطنين الاردنيين والسوري -2

اطنين متلقي الخدمة.تقليل الوقت والجهد على المو -3

.توفير مواقف سيارات للموظفين والمراجعين خلال اوقات الدوام الرسمي -4

متلقي الخدمات حيث يتم جمع مجموعة الدوائر الحكومية في مبنى واحد. توفير مصاريف المواصلات على -5

الزيادنة )وحدة ادارة المشروع( مراحل انشاء المشروع والتي تشمل:المهندس ثائر وعرض

.المدنيةالاعمال -1

تحضير الموقع وحفر الاساسات مما يسبب الازعاج – 1الاعمال الانشائية والاضرار الناتجة في هذه المرحلة مثل -2

– 4ازدحام مروري لفترة معينة – 3تلوث البيئية لفترة معينة - 2للمواطنين بسبب وجود الاليات لفترة معينة

المدارس المجاورة للمشروع لفترة معينة. ازعاج – 2بقايا المشروع وتراكم بعض النفايات من اعمال التشطيب

سة ريم )وحدة ادارة المشروع( بعض الاجراءات لتخفيف الاثار الناتجة عن أعمال المشروع المدنية المهندرحت وقد اقت

مثل الاسراع في هذه الأعمال بدون التأثير على نوعية العمل بالطبع ومراعاة عدم العمل في ساعات النهار المتأخرة.

روع من قبل مختص الضمانات البيئية و الاجتماعية و موافق وأوضحت بانه قد تم تطوير خطة ادارة بيئية كاملة للمش

عليها من البنك الدولي.

وعرضت أخصائية الوصول المجتمعي وإشراك المواطنين لدي المشروع د. اسماء العبدالله عن المشاورات المجتمعية التي تم

شاورات مجتمعية شملت كافة فئات المجتمع من جلسات م 7تنفيذها خلال فترة اختيار المشاريع حيث أفادت بأنه قد تم تنفيذ

شخص من المجتمع 333شباب ، نساء ، وذوي احتياجات خاصة وسوريين، وبلغ عدد الحضور لهذه الجلسات ما يقارب

.مجتمعيةالمحلي والتي كان من اهم مخرجاتها هو اختيار مشروع مجمع الدوائر الحكومية كاولوية

د.خولة الحسن على اهمية النوع الاجتماعي في هذا المشروع وتكافؤ الفرص من خلال واكدت أخصائية الجندر والادماج

....اجات الخاصة والاناث وغيرهميالتصميم الداخلي والخارجي عن طريق مراعاة احتياجات كبار السن وذوي الاحت

الرمثا وسينهي معاناة المواطنين وساهم الحضور من المجتمع المحلي بتقديم ملاحظاتهم حول هذا المشروع الذي سيخدم لواء

. الذين كانو يواجهون صعوبات في انهاء معاملاتهم بحكم التوزيع الجغرافي للدوائر وصعوبات التنقل

اقتراحات و توصيات الحضور:

شخص. 350 بحيث تتسع لاكثر من الاجتماعات في المبنى سعةقاعةزيادة -1

من ضمن المجتمع المحلي لأهالي الرمثا وعلى ضرورة تلبية أكد الحضور على ضرورة تشغيل العمالة المحلية -2

احتياجات المجتمع بكافة فئاته.

توزيع المداخل في المبنى وتخصيص مدخل خاص ومستقل للمحكمة الشرعية. -3

تقسيم الكراجات الى جزئين جزء للموظفين وجزء للمواطنين مع تأمين مواقف اصطفاف مناسبة. -4

هور في المبنى.ة الجممراعاة وجود مكتب خدم -5

ة المشروع.الاستفسار عن الفترة الزمنية للانتهاء من اقام -6

دد الاكشاك الموجودة في المبنى.ع -7

مراعاة وجود مصلى في التصميم, اضافة الى تزويد المبنى بجلسات ومطعم او كافتيريا. -8

Page 160: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

160

الخدمة من الدوائر المتناثرة في الاسراع في تنفيذ المبنى بسبب ما يتحمل المواطن من وقت وجهد ومال في تلقي -9

ة.المنطق

اعاة وجود حضانة اطفال في المبنى.مر -10

في اقامة المشروع حتى هذا الوقت.اسباب التأخير -11

تشغيل العمالة المحلية من ابناء المنطقة العاطلين عن العمل وخاصة المهندسين الخريجين الجدد لاكتساب الخبرة في -12

العمل.

لواء الرمثا بحيث يكون هذا شرط من شروط العقد. ان يكون المقاول من نفس -13

تم اقتراح انشاء عيادة صغيرة او غرفة اسعافات طبية بسيطة داخل المبنى. -14

وقد تم الرد على جميع استفسارات المواطنين بالشكل المناسب من قبل المهندسة رقية ومندوب البنك الدولي وادارة المشروع

للمشروع.لمهندس من المكتب المصمم وا

طنين :ابعض الردود على اقتراحات المو

% سوري.30% اردني و70مثا بنسبة سيتم تشغيل الايدي العاملة في المشروع من ابناء الر -1

الخدمة من جميع الدوائر بسهولة. تم تصميم عدة مداخل للبناء مما يسهل عملية تلقي -2

د مكتب خدمة الجمهور في التصميم.وجو -3

باذن الله. 2020لمشروع في نهاية انشاء افترة الانتهاء من -4

تصميم وقابل للزيادة حسب الحاجة.وجود عشرة اكشاك في ال -5

.لإقامة حضانة في المبنىوجود مساحة كافية -6

يف الازمة العمل على خلق خط سرفيس داخلي للوصول الى مجمع الدوائر لتخفباقتراح من مندوب البنك الدولي كما كان هناك

وجود خط باصات اللواء التي يتم الوصول الى المبنى (ببلدية الرمثاالمجمع, حيث كان الرد من المهندسة رقية) المرورية امام

من امام المبنى وعلى مدار لواء كونه خط السير الرئيسي لهذه الباصات لمن جميع مناطق الرمثا وا سهولةبواسطتها بكل

اليوم.

لمشروع ذي القيمة العالية و مشاركتهم للبلدية في اختيار اتقديم الشكر للحضور على ب رئيس البلديةنائب قاء قام لوفي نهاية ال

الأثر البناء على منطقة الرمثا واللواء بأكمله.

Page 161: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

161

Figure (9): Community Consultations for the Design of the sub-project

Page 162: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

162

Page 163: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

163

Page 164: ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT ......1 ENVIRONMENTAL AND SOCIAL IMPACT ASSESMENT STUDY (ESIA) Governmental Complex in Ramtha Municipality Irbid Governorate Municipal Services

164