Envelope Commissioning Presentation 5 25 09
Transcript of Envelope Commissioning Presentation 5 25 09
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
1/45
Building EnvelopeCommissioning
Arlene Lanman, P.E., R.ADirector
OSU Architectural & Engineering Services
www.pp.okstate.edu/arch
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
2/45
and installed envelope systems
Understand how commissioning
addresses these problems
process to the building envelope
Case study
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
3/45
=
paid for and are getting quality are
engaging in denial. In far too many
projects, cutting out quality has been
, .
- . ,Costs, HPAC(April, 1998), p. 52.
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
4/45
Water intrusion
Mold / mildew
Decreased worker productivity
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
5/45
A recent studyreported that 20-30%of commercial
buildings suffer fromindoor air qualityproblems.
- Ibid., p. 5.
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
6/45
operating costs for commissioned
buildings are reported at 8-20% lowerthan those of a comparable non-commissioned building.
Building Commissioning, (Washington, D.C.: U.S. General
erv ces m n s ra on , p. . va a e awww.betterbricks.org.
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
7/45
Responsibility
Quality Assurance
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
8/45
Review Owners Project Requirements (OPR)
ev ew as s o es gn
Peer Review Design Documents
Commissioning Specifications
Develo Pre-functional Checksheets
Review Contractor Submittals
Functional / Performance Testing
Develop Envelope Materials Manual Verify Training Requirements
-
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
9/45
Provide Direction toProject Team
Coordinate Scheduling
Updated Throughout
Project
Establish CommissioningPlan
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
10/45
Commissioning Components
Exterior Below Grade Walls
- -
Exterior Walls
,
Storefronts
Sealants, Control Joints & Flashings
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
11/45
Commissioning Components
Plaza Decks
Roofs / Garden Roofs
Atria
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
12/45
Commissioning
Develop Owners Performance
Review Basis of Design (BOD)
Specifications
en y o es espons es Drawing Reviews
on rac or u m a ev ews
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
13/45
Commissioning
Pre-functional Checklists
Construction Functional Testing Final Report
Can all of these steps be applied to thebuilding envelope?
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
14/45
Requirements
Many formats including nominal
group technique workshop
Define success criteria for ro ect
Often overlooks envelope
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
15/45
Requirements (OPR)
Occupant Requirements
Thermal Comfort
Visual Comfort
Acoustics
Requirements
Level of Occupant Control
(Operable Windows, Etc)
Life Safety
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
16/45
Reduced Energy Costs
Chiller Efficiency
Increased Equipment Life
-
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
17/45
Durability
Maintainability
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
18/45
Heat Flow Control
Water Vapor Flow Control
Light, Infrared, Ultraviolet, and Other
Noise and Vibration Control
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
19/45
Snow
Seismic
Ballistic
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
20/45
Site Information
Restrictions and Limitations Training Requirements
Warranty Requirements
Quality Requirements Systems
Materials
Construction
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
21/45
Statistical and Quality Tools
Benchmarking Requirements Operation and Maintenance
Allowable Range of Operation
Applicable Codes and Standards Insurance Requirements
Owner Safety Requirements
Constructability
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
22/45
MEP basis of design
CxAs first chance to review designers
vision for envelope
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
23/45
Owners Preference For Materials Or S stems
Initial Cost Im act On Schedule
Acoustical Performance
Thermal Performance Air Leakage
Water Leaka e
Fire Resistance Structural Criteria
Reliability
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
24/45
Sustainable Desi n
Life Cycle Cost Securit
Acoustical Performance
Warrant Glare Control
Condensation Control
Insulation Methods Glazin Methods
Durability
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
25/45
Look for ambi uities
Compare design to OPR and BoD
Remember chan e orders and RFIsadd cost to the project!
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
26/45
Structurally-related failures of building
Major Design Errors
- Drainage planes- Air barriers- Vapor barriers-- Roof
Incompatibility between structure & wall Absence or lack of coordination Material deficiencies
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
27/45
Hydrothermal Map of North America
Location, Location, Location!
Understanding Vapor
Barriers b LstiburekJ. ASHRAE Journal,2004.
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
28/45
Review roduct data
Review shop drawings
Compare to OPR and BoD
Must occur in parallel withdesigner review
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
29/45
-
Checklists su lement the desi n
they do NOT replace the design
Refer to Building Design Standard (BDS)
15995, Commissioning, for pre-functional
checklists
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
30/45
- Use the desi n drawin s
specs, OPR, and BoD tocreate checklists
Get information to the
contractor in sim le tounderstand language
Convey quality expectations
to contractor Helps the Owner track
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
31/45
-
Yes or No questions
Yes is always the
correct answer No indicates a
deficienc Keep it simple
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
32/45
-
Is the vapor barrier polyethylene with a
Are vapor barrier layers installed with 6 of
Are edges sealed with tape along the entirelength of lap?
Are edges turned up to within of top ofslab?
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
33/45
Site Observation Visits
Periodic site visit to verify installation
Document deficiencies
Be specific, take photos
Meet with contractor to discuss
findings
minimize schedule impact
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
34/45
Existin test rocedures ASTM
Thermal imaging Develop new test procedures
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
35/45
Pro ect did not
included envelopecommissionin
Lack of vapor
barrier wasdetected afterwalls were finished
Major cost andschedule im act torepair
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
36/45
Document deficiencies
If Cx process is successful, no
deficiencies found Should not be used strictly as a punch-
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
37/45
Document deficiencies
If Cx process is successful, no
deficiencies found Should not be used strictly as a punch-
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
38/45
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
39/45
Operations and MaintenanceManual Verification
Commissioning Forms
Templates Record Drawings (include Cx)
eg n rans er ay O&M Following Submittal Involve Operations
ersonne ar y
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
40/45
Responsibilities during first year of
warranty include:
Perform seasonal and/or deferred
Conduct lessons learned workshop
ev ew warran y ems w ac yoperations staff
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
41/45
Southeast
High containment Laboratory space
exterior of building
Envelope commissioning not included
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
42/45
Re airs set ro ect back 6 weeks
Several BSL-3 suites were torn downand reconstructed
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
43/45
Estimated cost of envelo e
commissioning $17k
envelope $50k + 6 weeks lost
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
44/45
quality assurance process
Can be applied to ANY building
Goal is to catch issues earl and
provide a building that meets the
-
8/3/2019 Envelope Commissioning Presentation 5 25 09
45/45
.
Building Commissioning Association (BCA).
2. Owners Representative and OSU Architectural &
Engineering Services Coordinator should take advantage of
BCA trainin .
3. Envelope commissioning shall be in accordance with the
Envelope Design Guide
Questions?