87 88 89 90 91 92 93 94 95 96 97 98 99 00 01 02 03 04 05 ...
@ENTRUSTY (88-95)
description
Transcript of @ENTRUSTY (88-95)
rticleA
1 s t Q u a r t e r 2 0 0 8
Must The Contractor Submit His Interim Payment Claims Before The Superintending Officer Certifies For Payment?
88
Your Contractual Questions Answered
By The Entrusty Group
Entrusty Group, a multi-displinary group of companies, of which, one of their specialisation is in project, commercial and contractual management, has been running a regular contractual questions and answers section for Master Builders members in the Master Builders Journal.
In this instalment of this series, Entrusty Group will provide the answer to another frequently asked question above.
Payments are of major concern to Contractors and Employers. As the duration of the construction
projects are usually long, contract sums involved are large and payments are only progressively paid rather then on delivery, thus the payments are lifeblood of the Construction Industry. In common law and in the absence of any provision in the contract for interim payments during the progress of work, the Contractor would not be entitled to such payment for his work done progressively unless he has fully or substantially completed his contracted work.
Nevertheless, in the present construction industry, almost all construction contracts have claims or payment application and certification provisions, which are usually applied and implemented on monthly or stage payment basis. Interim or progress payment claims are usually prepared by the Contractor and submitted to the Consulting Quantity Surveyor for valuation, which in turn is then submitted to the Architect/Engineer/Superintending Officer (SO)/Project Director (PD) for certification. The Employer is required to pay within a specified period after having received the said interim payment certificate
from the Architect/Engineer/SO/PD, who usually acts as the Contract Administrator of the project.
Before we go further to answering the above question, let us look into the standard form of contract provision for interim payment applications that is commonly used in the Malaysian Construction Industry.
Standard Forms of Construction Contract
Many standard forms of construction contract in Malaysia provide for payment application and certification clauses. The relevant payment clauses in respect of the various conditions of contract in use in Malaysia are: -
● PAM 1998 and PAM 2006 Clause 30 – Certificate and Payment (refer to Flow Chart 1 for PAM 1998 and Flow Chart 2 for PAM 2006)● IEM/JKR Clause 47 – Payment to Contractor and Interim Certificates (refer to Flow Chart 3 for IEM and Flow Chart 4 for JKR)● CIDB Clause 42 – Payment (refer to Flow Chart 5)● JKR PWD Form DB/T (2002 Edition) Clause 50 – Interim Payment (refer to Flow Chart 6)
PAM 1998 Sub-Clause 30.2 and PAM 2006 Sub-Clause 30.1 requires the Contractor to submit sufficient details/particulars to Architect for him to value and ascertain the works (including materials and goods on site) and issue interim certificate for Contractor’s entitlement to payment. The materials and goods on site shall be reasonably, properly and not prematurely delivered with adequate protection against weather or other casualties. PAM 1998 Sub-Clause 30.2 provides that the Architect shall have the discretion to make the interim valuation whenever he considers necessary for issuing the interim certificate.
The following Flow Chart 1 details the procedures of the interim payment process under PAM 1998 form of contract.
However, PAM 2006 Sub-Clause 30.1, which has been revised from PAM 1998, states that the Interim Certificate is to be issued within 21 days from the Contractor’s submission of their interim payment application. In addition, PAM 2006 clearly provides that in the event the Contractor fails to submit the payment application, it shall be deemed to be a waiver
rticleA
1 s t Q u a r t e r 2 0 0 8
89
Flow Chart 1: PAM 1998 Form Of Building Contract Clause 30 - Interim Payment Process
Flow Chart 2: PAM 2006 Form Of Building Contract Clause 30 - Interim Payment Process
START
Contractor submits details and particulars to Architect during the Period of Interim
Certificate stated in the Appendix
Architect ascertains the amount due to the Contractor
Architect corrects or modifies previous certificate in next
certificate
Architect ascertains:(a) the total value of works
properly executed including those executed by sub-contractors
(b) the total value of materials and goods including:-(i) delivered to or
adjacent to the Works(ii) delivered up to and
not more than 7 days before the date of certificate
(iii) reasonably, properly and not prematurely brought to or adjacent to the Works
(iv) adequately protected against weather or other casualties
Architect issues Interim Certificate with a copy to the Employer
Contractor may serve default notice
Contractor proceeds with the Works
Notice of determination by contractor
Carry out provisions of Clause 26.2
END
No
Yes
No
Yes
Yes
No
Error or discrepancy in the previous certificate detected
Employer pays within the Period of Honouring Certificate stated in the
Appendix
Employer stops default in 7 days
START
Contractor submits details and particulars to Architect during the Period of Interim
Certificate stated in the Appendix
Architect ascertains the amount due to the Contractor
Error or discrepancy in the previous certificate detected
Architect corrects or modifies previous certificate in next
certificate
Architect ascertains:(a) the total value of works
properly executed including those executed by sub-contractors
(b) the total value of materials and goods including:-(i) delivered to or
adjacent to the Works(ii) delivered up to and
not more than 7 days before the date of certificate
(iii) reasonably, properly and not prematurely brought to or adjacent to the Works
(iv) adequately protected against weather or other casualties
Architect issues Interim Certificate with a copy to the Employer within 21 days from receipt Contractor’s Application
Employer pays within the Period of Honouring Certificate stated in the
Appendix
Contractor may serve default notice
Contractor proceeds with the Works
Notice of determination by contractor within 10 days
Carry out provisions of Clause 26.4 & 26.6
END
No
Yes
No
Yes
Yes
No
Employer stops default in 14 days
rticleA
1 s t Q u a r t e r 2 0 0 8
90
Flow Chart 3: IEM Form Of Building Contract Clause 47 - Interim Payment Process
of his contractual entitlement for that interim certificate, and the Architect may at his discretion, issue or not issue the interim certificate under the circumstances. After the issuance of the Certificate of Practical Completion, interim certificate shall be issued as and when further amounts are ascertained by the Architect as payable to the Contractor by the Employer.
Flow Chart 2 details the procedures of the interim payment process under PAM 2006 form of contract.
Similarly with PAM Form of Contract, IEM/JKR Clause 47 (a) to (d) deals with the interim payment claims, certifications and payments on a monthly basis. IEM/JKR Clause 47 (a) states that when the Contractor has executed the Works including the material on site has reached the minimum value requirement as stated in the Appendix for the First Interim Certificate, the SO shall make the first valuation of the Works, for which is the first claim can be less or more than a month. For subsequent claims, the amount must also exceed the minimum amount as stated in the Appendix, whereby the claims can be on monthly basis or more than a month (at the discretion of the SO). The Engineer/SO is required to make a fair valuation of works properly executed and 75% of the value of unfixed material and goods on-site and issue Interim Certificate to the Contractor for payment by Employer/Government. It is implied that the Engineer/SO is to value the executed works and issue an Interim Certificate on a monthly basis. IEM/JKR Sub-Clause 47 (b) requires the SO to issue an Interim Certificate within 14 days from the date of valuation.
The following Flow Chart 3 and Flow Chart 4 detail the procedures of the interim payment process under IEM and JKR respectively.
For CIDB Form of Contract, the Sub-Clause 42.1 requires the Contractor to submit a Statement of Work Done (SoWD), which would incorporate the work properly executed (subject to any agreement as to stage payment stipulated in the Appendix), any items priced in the contract including Construction Plant, Temporary Works, percentage (as stated in the appendix) of value of equipment, material or goods delivered for incorporation in the Works and any amount due to the Contractor under an Option Module.
Sub-Clause 42.2 (a) requires that the S.O. shall subject to sub-clause 42.2 (c) and (d) issue an Interim Certificate within 21 days from receiving SoWD. As provided under sub-clause 42.2 (c), the Interim Certificate must be issued at regular interval (as stated in the Appendix). After the Practical Completion of the Works, the SO may issue Interim Certificate as and when he ascertains further amounts due to the Contractor. Sub-Clause 42.2 (d) provides that the SO is not required to issue an Interim
START
Contractor submits claims to Engineer when the value of executed work including delivery of materials had reached
the sum referred to in the Appendix
Engineer makes the first* valuation of the Works
Engineer makes fair valuation of the Works and materials delivered each succeeding month, provided the total value is not less
than the sum referred to in the Appendix
Within 14 days from the valuation, Engineer issues Interim Certificate stating the amount die to the Contractor
Contractor proceeds with the Works
Within the Period of Honouring Interim Certificate stated in the Appendix / Within 30 days if the issues of Interim Certificate, Employer makes
payment to the Contractor
Amount of Interim Certificate includes:-(i) Estimated total value of work done(ii) 75% of value of unfixed materials up to
and including date of valuation
Less(iii) Installment previously paid(iv) Retention Fund
Contractor gives notice of default under Clause 52 (a)
Contractor terminates the Contract under Clause 52
Recover monies outstandingusing Clause 55
END
YES
NO
rticleA
1 s t Q u a r t e r 2 0 0 8
91
Flow Chart 4: JKR Form Of Building Contract Clause 47 – Interim Payment Process
Certificate if the amount claimed or the amount certified is less than the minimum amount stated in the Appendix.
The following Flow Chart 5 details the procedures of the interim
payment process under CIDB form of contract.
JKR D&B/T Clause 50 deals with interim payment. The Interim Payment shall be made as set out in the Appendix 2 drawn up by
mutual agreement of the contracting parties. However, the PD reserves the right to make payment according to the value of work done or Payment Schedule. Sub-Clause 50.2 requires the Contractor to submit to the PD written application for Interim
Contractor returns Letter of Acceptance of Tender
START
Contractor deposits relevant insurance policies
Contractor deposits the Performance Bond
Total value more than the sum referred to in Appendix
Within 14 days from the valuation, S.O. issues Interim Certificate stating the amount due to the
Contractor
No Interim Certificate shall be issued
Contractor executed works including delivery of materials
S.O. makes valuation of the Works executed and materials delivered every month
Amount of Interim Certificate includes:-(i) Estimated total value of work done(ii) 75% of value of unfixed materials up to and including date of valuationLess(iii) Installment previously paid
Within the Period of Honouring Interim Certificate stated in the
Appendix / Within 30 days of the issue of Interim Certificate, Government
makes payment to the Contractor
Contractor proceeds with the Works
END
Dispute or differences arise
Refer Settlement of Dispute Clause 54.0
No
No
Yes
No
No
Yes
Yes
No
Yes
rticleA
1 s t Q u a r t e r 2 0 0 8
92
STA
RT
Cont
ract
or s
ubm
its to
th
e S.
O. a
t the
inte
rval
s sp
ecifi
ed in
App
endi
x as
“Sta
tem
ent o
f Wor
k D
one”
“Sta
tem
ent o
f Wor
k D
one”
sh
all c
onta
in:
(i)
valu
e of
wor
ks p
rope
rly
exec
uted
(ii)
item
s se
para
tely
pric
ed in
th
e Co
ntra
ct(ii
i) pe
rcen
tage
of v
alue
of
equi
pmen
t, m
ater
ials
de
liver
ed to
Site
(iv) a
mou
nt e
ntitl
ed(v
) am
ount
due
und
er O
ptio
n M
odul
e
S.O
. Sha
ll no
tify
the
Cont
ract
or in
writ
ing
with
in
21 d
ays
of re
ceiv
ing
“Sta
tem
ent o
f Wor
k D
one”
S.O
. at h
is d
iscr
etio
n de
cide
s no
t to
issu
e In
terim
Cer
tifica
te
Tota
l am
ount
Co
ntra
ctor
sta
ted
in
“Sta
tem
ent o
f Wor
k D
one”
gre
ater
than
th
e m
inim
um a
mou
nt
spec
ified
in th
e A
ppen
dix
Tota
l am
ount
w
hich
the
S.O
. co
nsid
ers
Cont
ract
or
to b
e en
title
d to
gr
eate
r tha
n th
e m
inim
um a
mou
nt
spec
ified
in th
e A
ppen
dix
Cont
ract
or is
en
title
d to
som
e re
med
y w
here
the
Empl
oyer
is li
able
. Cl
ause
42.
12
S.O
. iss
ues
Inte
rim
Cert
ifica
te to
the
Empl
oyer
(c.c
to th
e Co
ntra
ctor
) sta
ting
amou
nt a
scer
tain
ed
with
in 2
1 da
ys o
f re
ceiv
ing
“Sta
tem
ent
of W
ork
Don
e”
Inte
rim C
ertifi
cate
sha
ll in
clud
e:(i)
Th
e am
ount
Con
trac
tor i
s en
title
d to
Less
(ii)
Rete
ntio
n M
onie
s(ii
i) A
ny a
mou
nt p
revi
ousl
y st
ated
(iv) A
ny a
mou
nt p
revi
ousl
y ce
rtifi
ed to
be
dedu
cted
S.O
. may
mak
e an
y co
rrec
tion
or
mod
ifica
tion
on e
rror
in
prev
ious
cer
tifica
tes
Aft
er is
suan
ce o
f Ce
rtifi
cate
of P
ract
ical
Co
mpl
etio
n, In
terim
Ce
rtifi
cate
sha
ll be
is
sued
as
and
whe
n fu
rthe
r am
ount
s ar
e as
cert
aine
d by
the
S.O
Empl
oyer
pay
s th
e Co
ntra
ctor
with
in 2
1 da
ys/t
he P
erio
d of
H
onou
ring
Cert
ifica
te
stip
ulat
ed in
the
App
endi
x
Opt
ion
Mod
ule
E / P
aym
ent B
ond
appl
icab
le
Inte
rest
in
resp
ect o
f the
un
paid
am
ount
ac
crue
d
Empl
oyer
s pa
ys c
ertifi
cate
an
d in
tere
st
Empl
oyer
’s fa
ilure
to
pay
for f
urth
er
14 d
ays
Cont
ract
or
give
s no
tice
of h
is
inte
ntio
n to
su
spen
d w
ork
Empl
oyer
’s fa
ilure
to m
ake
paym
ent a
fter
fu
rthe
r 14
days
Cont
ract
or s
uspe
nds
who
lly /
part
ly /
redu
ces
the
fate
of t
he W
ork
prog
ress
Cont
ract
or
prot
ect a
nd
secu
re th
e W
orks
dur
ing
susp
ensi
on
Cont
ract
or
entit
led
to
Exte
nsio
n of
Ti
me
Cont
ract
or
entit
led
to L
oss
and
Expe
nse
Cont
ract
or
subm
its L
oss
and
Expe
nse/
EoT
clai
ms
S.O
. eva
luat
es
clai
ms
Add
to C
ontr
act
sum
Empl
oyer
’s fa
ilure
to p
ay
subs
eque
ntly
Cont
ract
or li
fts
susp
ensi
on
Refe
r Set
tlem
ent o
f D
ispu
tes
Clau
se 4
7D
eter
min
atio
n su
bjec
t to
Clau
se 4
5.1
(b)
Refe
r Not
ice
of
defa
ult C
laus
e 45
.1 (a
)Co
ntra
ctor
reco
vers
th
e un
paid
am
ount
fr
om th
e Bo
nd
Cont
ract
or p
roce
eds
the
Wor
ks
END
YES
NO
NO
YES
YES
YES
YES
YES
YES
YES
YES
NO
NO
NO
NO
Flo
w C
hart
5: C
IDB
Form
Of B
uild
ing
Cont
ract
Cla
use
42 –
Inte
rim P
aym
ent
Proc
ess
rticleA
1 s t Q u a r t e r 2 0 0 8
Brief Description of Relevant Contract Clauses
Contract Clauses
PAM 2006
PAM 1998 JKR 203A
IEM1989
CIDB 2000
FIDIC 4th Edition
The Contractor shall submit a payment application at the Interim Claim Interval stated in the Appendix. 30.1 30.2 47 (a) 42.1 50.2
The Architect / Engineer / Superintending Officer shall within the stipulated period after the Contractor submitted Interim Payment Claims issues the Interim Certificate.
30.2 within 21
days
Architect discretion
14 days after Valuation
42.2(a) within
21 days
50.3 (a)14 days after application
The Employer has to make the payment to the Contractor within stipulated period after the Architect / Engineer / Superintending Officer issued the Interim Payment Certificate.
30.2 30.3 47 (d) 42.9 (a) 50.3 (c)
Interest imposed on Employer for late payment. 30.17 - - 42.9 (b) -
Flow Chart 6: JKR PWD DB/T Form Of Building Contract Clause 50 – Interim Payment Process
Payments showing the amounts due under the contract, variations, expenditure of provisional sums and material on site for use in the Works.
Where Payment Schedule is included in the Contract, PD shall issue the Interim Certificate within 14 days upon receipt of Contractor’s application for Interim Payment. Where no Payment Schedule is included in the Contract, the Interim Payment shall be made by the Government based on PD’s monthly valuation of the Works properly executed and any goods or unfixed materials delivered to Site intended for use in the Works.
Flow Chart 6 details the procedures of the interim payment process under JKR D&B/T form of contract.
Table 1 shows the relevant payment clauses in the standard forms of construction contract.
Whilst most of the above stipulated forms of contract provided for similar words ‘...... shall on submission of payment application ........’, which make it a mandatory obligation on the Contractor to submit his payment application for the Architect/Engineer/SO/PD consideration and certification. Whether such obligation
START
Contractor executed works including delivery of materials
Contractor submitpayment application
PD shall issue a notice to Contractor with reasons to the effect
Payment Schedule included in Appendix 2 of the Contract
Contractor executed works and payment application in accordance with Contract
PD do valuation of the executed Works (including
materials delivered) on monthly basis and the total value shall be more than
the sum referred to in Appendix 1
PD shall issue interim certificate within 14 days upon received
Contractor payment application
PD shall issue Interim Certificate within 28 days from the Contractor’s payment application stating the amount due to the Contractor
Within the Period of Honouring Interim Certificate
stated in the Appendix / Within 30 days of the issue of Interim Certificate Government makes
payment to the Contractor
Dispute or differences arise
Contractor proceeds with the Works
Refer Settlement of Disputes Clause 56.0
END
No
No
Yes
Yes
No
Yes
No
Yes
Table 1
93
rticleA
1 s t Q u a r t e r 2 0 0 8
1 Ir. Harbans Singh K.S., Engineering and Construction Contracts Management – Post-Commencement Practice, Chapter 3 – Payments, LexisNexis (Singapore) Pte. Ltd., 2003.
Kuala Lumpur high rise offices
is indeed a mandatory requirement is debatable, except when it is expressly provided for as condition precedent, as in the case of PAM 2006 Clause 30.1.
According to Ir. Harbans Singh K.S.1, ‘...... non-compliance to such requirements is not fatal to the contractor’s entitlement, since the employer is obliged, in the absence of such breaches anyway to proceed with the discharge of his side of the bargain.’
CONCLUSION
In normal practice, the Architect/Engineer/SO/PD usually prepares the Interim Certificate only after the Contractor has submitted their payment application. Whether the
Contractor has to submit their payment application prior to the Architect/Engineer/SO/PD issuance of the interim certificate at the interval period as prescribed in the Appendix of the Conditions of Contracts depends on different forms of Conditions of Contract.
PAM 2006 Form of Contract make it a condition precedent in that the Contractor must submit their payment application to the Architect/SO, otherwise it is deemed a waiver of his contractual entitlement for that interim certificate. Nevertheless, the Architect may issue the interim certificate at his discretion, depending on the circumstances.
PAM 1998, CIDB and JKR PWD Form DB/T Forms of Contract require the Contractor to submit their payment application to the Architect/PD. However, there is no provision stating that the failure of the Contractor to do so will cause the Contractor to waive his contractual entitlement for that interim certificate. Thus, it is still depends on the Architect/SO/PD’s discretion to make an interim valuation whenever he considers necessary for ascertaining the amount due in an interim certificate.
IEM/JKR Forms of Contract do not have any provisions that the Contractor must submit his payment application for the Engineer/SO to
94
rticleA
1 s t Q u a r t e r 2 0 0 8
The Entrusty Group includes Entrusty Consultancy Sdn Bhd (formerly known as J.D. Kingsfield (M) Sdn Bhd), BK
Burns & Ong Sdn Bhd (a member of the Asia wide group BK Asia Pacific) , Pro-Value Management, Proforce Management Services Sdn Bhd / Agensi Pekerjaan Proforce Sdn Bhd and International Master Trainers Sdn Bhd. providing project, commercial and contractual management services, risk, resources, quality and value management, recruitment consultancy services and corporate training programmes to various industries, particularly in construction and petrochemical, both locally and internationally.
For further details, please visit website: www.entrusty.com. or contact HT Ong at 22-1& 2 Jalan 2/109E, Desa Business Park, Taman Desa, 58100 Kuala Lumpur, Malaysia. Tel: 6(03)-7982 2123 Fax: 6(03)-7982 3122 Email: [email protected].
Entrusty Group provides 30 minutes of free consultancy (with prior appointment) to MBAM members on their contractual questions. The Group also provides both in-house and public seminars/workshops in its various areas of expertise.
In the next issue of the MBAM journal the article will answer the question on ‘Is determination of employment and termination of contract the same in meaning and implications?’
REFERENCE/BIBLIOGRAPHY
1. Malaysian standard forms of contract: -i. PAM Form of Building Contract (1998 & 2006) ii. JKR/PWD Form of Contract (203A - Rev 10/83)iii. IEM Conditions of Contract for Works Mainly of Civil Engineering
Construction (1st Edition – 1989) iv. CIDB Form of Contract for Building Works (2000 Edition)v. JKR PWD/ Standard Form of Design & Build/Turnkey Contract (PWD
Form DB/T) (2002 Edition)2. Sr. Ong Hock Tek, Payment Claims, Valuations, Certification and Final
Account, one day seminar organised by Entrusty Management Sdn. Bhd. and B.K. Burns & Ong Sdn. Bhd., 2 November 2004.
3. Ir. Harbans Singh K.S., Engineering and Construction Contracts Management – Post-Commencement Practice, Chapter 3 – Payments, LexisNexis (Singapore) Pte. Ltd., 2003.
4. Vincent Powell Smith, The Malaysian Standard Form of Building Contract, Clause 30 – Interim Certificate and Valuation, Malaysia Law Journal Sdn. Bhd., 1990.
5. Ling Tek Lee, Natural Justice in Adjudication, Chapter 2 – The Dilemma in the Construction Industry, University Technology Malaysia, March 2006.
do the valuation and then issue the interim certificate. However, the Engineer/SO is required to make the first valuation when the Contractor has executed the Works (including material on-site) have reached the minimum value as stated in the Appendix of the said form of contract. Subsequently, the Engineer/SO is also required to do the valuation and issue an Interim Certificate when the Works (including materials on site) have exceeded the minimum amount stated in the Appendix either monthly or more than a month. Failure of the Engineer/SO to issue the Interim Certificate is a breach of conduct for which the Employer/Government can be liable under the Contract.
Although certain standard forms of contract do not expressly require the Contractor to submit their payment application, they impose such duty on the Contract Administrator (Architect/Engineer/SO/PD) to initiate the payment process. It is therefore pertinent that the Contractor is proactive and in his interest, to make the necessary payment application regularly and timely, as it will definitely assist the Contract Administrator to expedite the payment process and in turn for the Employer to fulfil his payment obligation, accordingly.
95
Payment calculations