Ensuring policies and strategies deliver€¦ · Simon Bunn –Cambridge City Council 2 Application...

15
Susdrain – Achieving multiple benefits from SuDs through planning 16/02/2016 Simon Bunn – Cambridge City Council 1 Ensuring policies and strategies deliver Simon Bunn Sustainable Drainage Engineer Cambridge City Council Application timeline - 1 Pre-preapp stage Early discussion detailing expectations, constraints, opportunities with local authority and other partners Local planning authority input from engineers, landscape architects, urban designers, ecologists and planners. (LPA technical team) Opportunity to influence scheme = high

Transcript of Ensuring policies and strategies deliver€¦ · Simon Bunn –Cambridge City Council 2 Application...

Page 1: Ensuring policies and strategies deliver€¦ · Simon Bunn –Cambridge City Council 2 Application timeline -2 Pre-app stage -outline Discuss proposals: Multiple pre-apps discussing:

Susdrain – Achieving multiple benefits

from SuDs through planning

16/02/2016

Simon Bunn – Cambridge City Council 1

Ensuring policies and

strategies deliver

Simon BunnSustainable Drainage Engineer

Cambridge City Council

Application timeline - 1

Pre-preapp stage

� Early discussion detailing expectations,

constraints, opportunities with local

authority and other partners

� Local planning authority input from engineers,

landscape architects, urban designers,

ecologists and planners. (LPA technical team)

� Opportunity to influence scheme = high

Page 2: Ensuring policies and strategies deliver€¦ · Simon Bunn –Cambridge City Council 2 Application timeline -2 Pre-app stage -outline Discuss proposals: Multiple pre-apps discussing:

Susdrain – Achieving multiple benefits

from SuDs through planning

16/02/2016

Simon Bunn – Cambridge City Council 2

Application timeline - 2

Pre-app stage - outline

� Discuss proposals:

� Multiple pre-apps discussing:

� Flow and volumetric run-off, controls, potable

water strategy, landscape, adoption strategy, flood

risk reduction scheme and future reserved matters.

� Opportunity to influence scheme = high

Application timeline - 3

Application stage - outline

� Assess submitted information:

� Provide comments and information re-

submitted

� Check re-submission

� Agree conditions

� Opportunity to influence scheme =

medium

Page 3: Ensuring policies and strategies deliver€¦ · Simon Bunn –Cambridge City Council 2 Application timeline -2 Pre-app stage -outline Discuss proposals: Multiple pre-apps discussing:

Susdrain – Achieving multiple benefits

from SuDs through planning

16/02/2016

Simon Bunn – Cambridge City Council 3

Application timeline - 4

Pre-app stage – reserved matters

� Early discussion detailing expectations,

and opportunities with local authority and

other partners. Discussions around detail.

� Local planning authority input from engineers,

landscape architects, urban designers,

ecologists and planners. (LPA technical team)

� Opportunity to influence scheme =

medium

Application timeline - 5

Ghost application stage – reserved matters

� Assessed as if an actual application.

� Checked against policy and best practice,

interrogation of calculations etc.

� Discuss application with colleagues

� Opportunity to influence scheme = low

Page 4: Ensuring policies and strategies deliver€¦ · Simon Bunn –Cambridge City Council 2 Application timeline -2 Pre-app stage -outline Discuss proposals: Multiple pre-apps discussing:

Susdrain – Achieving multiple benefits

from SuDs through planning

16/02/2016

Simon Bunn – Cambridge City Council 4

Application timeline - 6

Application stage – reserved matters

� Check submitted application has

addressed comments from ghost

application and provide feedback

� Fine grain details agreed through

conditions

� Opportunity to influence scheme = low

Application timeline - 7

Post applications stage – onsite monitoring

� Visit site to check what is being

constructed and how it is constructed in

accordance with submitted information.

� Opportunity to influence scheme = non-

existent!

Page 5: Ensuring policies and strategies deliver€¦ · Simon Bunn –Cambridge City Council 2 Application timeline -2 Pre-app stage -outline Discuss proposals: Multiple pre-apps discussing:

Susdrain – Achieving multiple benefits

from SuDs through planning

16/02/2016

Simon Bunn – Cambridge City Council 5

Residential Lot M2 M2

� 240 Dwellings

� 64 dwellings per hectare

� 4 discharge locations into strategic system

at 5 l/s each

� All images copyright University of Cambridge, Hill Residential,

Alison Brooks Architects, Pollard Thomas Edwards, Robert Myers

Associates and WSP Group

Page 6: Ensuring policies and strategies deliver€¦ · Simon Bunn –Cambridge City Council 2 Application timeline -2 Pre-app stage -outline Discuss proposals: Multiple pre-apps discussing:

Susdrain – Achieving multiple benefits

from SuDs through planning

16/02/2016

Simon Bunn – Cambridge City Council 6

Page 7: Ensuring policies and strategies deliver€¦ · Simon Bunn –Cambridge City Council 2 Application timeline -2 Pre-app stage -outline Discuss proposals: Multiple pre-apps discussing:

Susdrain – Achieving multiple benefits

from SuDs through planning

16/02/2016

Simon Bunn – Cambridge City Council 7

Page 8: Ensuring policies and strategies deliver€¦ · Simon Bunn –Cambridge City Council 2 Application timeline -2 Pre-app stage -outline Discuss proposals: Multiple pre-apps discussing:

Susdrain – Achieving multiple benefits

from SuDs through planning

16/02/2016

Simon Bunn – Cambridge City Council 8

Page 9: Ensuring policies and strategies deliver€¦ · Simon Bunn –Cambridge City Council 2 Application timeline -2 Pre-app stage -outline Discuss proposals: Multiple pre-apps discussing:

Susdrain – Achieving multiple benefits

from SuDs through planning

16/02/2016

Simon Bunn – Cambridge City Council 9

Page 10: Ensuring policies and strategies deliver€¦ · Simon Bunn –Cambridge City Council 2 Application timeline -2 Pre-app stage -outline Discuss proposals: Multiple pre-apps discussing:

Susdrain – Achieving multiple benefits

from SuDs through planning

16/02/2016

Simon Bunn – Cambridge City Council 10

Lot 2 Residential and

commercial

� 264 dwellings (key worker)

� 1983 sqm commercial use

� 8.81 l/s discharge into strategic network

� All images copyright University of Cambridge, Aecom, Stanton

Williams and Townshend Landscape Architects

Page 11: Ensuring policies and strategies deliver€¦ · Simon Bunn –Cambridge City Council 2 Application timeline -2 Pre-app stage -outline Discuss proposals: Multiple pre-apps discussing:

Susdrain – Achieving multiple benefits

from SuDs through planning

16/02/2016

Simon Bunn – Cambridge City Council 11

Page 12: Ensuring policies and strategies deliver€¦ · Simon Bunn –Cambridge City Council 2 Application timeline -2 Pre-app stage -outline Discuss proposals: Multiple pre-apps discussing:

Susdrain – Achieving multiple benefits

from SuDs through planning

16/02/2016

Simon Bunn – Cambridge City Council 12

Page 13: Ensuring policies and strategies deliver€¦ · Simon Bunn –Cambridge City Council 2 Application timeline -2 Pre-app stage -outline Discuss proposals: Multiple pre-apps discussing:

Susdrain – Achieving multiple benefits

from SuDs through planning

16/02/2016

Simon Bunn – Cambridge City Council 13

Page 14: Ensuring policies and strategies deliver€¦ · Simon Bunn –Cambridge City Council 2 Application timeline -2 Pre-app stage -outline Discuss proposals: Multiple pre-apps discussing:

Susdrain – Achieving multiple benefits

from SuDs through planning

16/02/2016

Simon Bunn – Cambridge City Council 14

Page 15: Ensuring policies and strategies deliver€¦ · Simon Bunn –Cambridge City Council 2 Application timeline -2 Pre-app stage -outline Discuss proposals: Multiple pre-apps discussing:

Susdrain – Achieving multiple benefits

from SuDs through planning

16/02/2016

Simon Bunn – Cambridge City Council 15

Conclusion

� Early consideration = better SuDS

� Maximise pre-app

� Attention to detail

� Don’t worry about the calcs

� Follow through to construction