Engineering Quality common problems
Civil Work
-
7/21/2019 Engineering Quality Common Problem Series (1) - Civil Work
2/16
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Picture Case of Common Engineering Problem Civil Work
Page 2
The common problems of civil work
The type of problem The standards of Quality Check method
The strength of basement
1The base of tower falls intocrack
2The sustainable cement blockis cracked
3The base of the tower settles
1The strength of the concrete should meet thedesign requirements. The strength after 28-day
maintenance should not be less than C20.2Cement, water, sand, gravel and additives forthe concrete and mixing ration should meet the
design requirements
3The base backfill records are complete andcorrect
1Reboundinstrument2check the deliveryinspection report
3Check the recordsfor the concealed
project
The surface of base:1 concave, spongy surface2crack, defects of appearance
Check the appearance of the base: No concave,
spongy surface, crack (crack on the surface
1mm), defects of appearance, etc.
Visual measurement
Tape measurement
Design of civil work1The support of tower base does notmeet with the requirements
2The support of ladder does not meetwith the requirements
3The rabbet of feeder does not meetwith the requirements
All installation should meet the design
requirements
Visual measurement
Check against the
drawing
Fence1The spray paintcoatingdont meet with the requirements2No grounding
1The coating of the Fence componentcomplies with the design and specifications
requirements
2The spray paint of the Fence componentcomplies with the design and specifications
requirements
Visual measurement
Check the records for
the concealed project
-
7/21/2019 Engineering Quality Common Problem Series (1) - Civil Work
3/16
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Picture Case of Common Engineering Problem Civil Work
Page 3
Problem:The
cracked
concrete
probably
shows the
badstrength of
the base.
The strength of the concrete
Cracked surface of the base
Suggestion:1.Test the
strength of the
base;
2.If the strength
meets the
requirement,
repair the base,
otherwise
rework.
-
7/21/2019 Engineering Quality Common Problem Series (1) - Civil Work
4/16
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Picture Case of Common Engineering Problem Civil Work
Page 4
Problem:
The
sustainable
cement
block is
cracked
The strength of the concrete
The sustainable cement block is cracked
Suggestion:
1.Test the
strength of the
base;
2.If the strength
meets therequirement,
repair the base,
otherwise
rework.
-
7/21/2019 Engineering Quality Common Problem Series (1) - Civil Work
5/16
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Picture Case of Common Engineering Problem Civil Work
Page 5
Suggestion:
Repair the base
and make sure
the base is firm.
Problem:
The base of
the tower
are not
rammed
down with
soil and
sink
The strength of the concrete
The base of tower settles
-
7/21/2019 Engineering Quality Common Problem Series (1) - Civil Work
6/16
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Picture Case of Common Engineering Problem Civil Work
Page 6
Suggestion:Remove the scratch
and rework.
Problem:Separation of the top
layer from the base of
the slab by a thin layer
The surface of the base
The defects of appearanceProblem:The surface is uneven.
-
7/21/2019 Engineering Quality Common Problem Series (1) - Civil Work
7/16
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Picture Case of Common Engineering Problem Civil Work
Page 7
Suggestion:
1.Repair
2.Pay attention
to the curing
duration3. The step
should be under
the eave
according with
the design
Problem:
Surface
collapse
The surface of the base
Disintegration of the surface
-
7/21/2019 Engineering Quality Common Problem Series (1) - Civil Work
8/16
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Picture Case of Common Engineering Problem Civil Work
Page 8
Suggestion:
1.Test the
strength of the
base;
2.If the strength
meets the
requirement,
repair the base,
otherwise
rework.
Problem:
The surface
is spongy.
The surface of the base
Spongy surface
-
7/21/2019 Engineering Quality Common Problem Series (1) - Civil Work
9/16
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Picture Case of Common Engineering Problem Civil Work
Page 9
Suggestion:1.Test the
strength of the
base;
2.If the
strength
meets therequirement,
repair the
base,
otherwise
rework.
Problem:
Separation
of the top
layer of
the slab
from the
base ofthe slab by
a thin
layer
The surface of the base
Delamination
-
7/21/2019 Engineering Quality Common Problem Series (1) - Civil Work
10/16
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Picture Case of Common Engineering Problem Civil Work
Page 10
Problem:
The base is
unstable.
Design of civil work
The support of ladder dont meet with requirementsSuggestion:Make a concrete
base.
Pi t C f C E i i P bl Ci il W k
-
7/21/2019 Engineering Quality Common Problem Series (1) - Civil Work
11/16
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Picture Case of Common Engineering Problem Civil Work
Page 11
Design of civil work
The cable trough dont meet with requirementsProblem:
The
support of
the trough
is unstable.
Suggestion:
Make a
concrete
base to
support the
trough.
Pi t C f C E i i P bl Ci il W k
-
7/21/2019 Engineering Quality Common Problem Series (1) - Civil Work
12/16
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Picture Case of Common Engineering Problem Civil Work
Page 12
Fence installation
The spray paint of the Fence component dont meetwith the requirements
Problem:
The paint
comes
unglued.
Suggestion:
Clean the
bar and
repaint.
Picture Case of Common Engineering Problem Civil Work
-
7/21/2019 Engineering Quality Common Problem Series (1) - Civil Work
13/16
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Picture Case of Common Engineering Problem Civil Work
Page 13
Appendix1 Tower-Civil Work Checklist
Problem type Check Item
A
The examination records for the concealed project are complete and correctinclude1The pit (ditch) examination records for the groundwork are complete and correct 2The examination records of steel bars are complete and correct3The template records are complete and correct 4The concrete records are complete and correct5The base backfill records are complete and correct
A The dimensions of tower base section should meet the design requirements, and thetolerance should be +15/-10mm
B Check the smoothness of the towerbase surface. The deviation should be 5mm
B Check the appearance of the base: No concave, spongy surface, crack (crack on the surface1mm), defects of appearance, etc.
B The intensity of the concrete should meet the design requirements. The intensity after 28-day maintenance should not be less than C20.
Picture Case of Common Engineering Problem Civil Work
-
7/21/2019 Engineering Quality Common Problem Series (1) - Civil Work
14/16
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Picture Case of Common Engineering Problem Civil Work
Page 14
Appendix2 Shelter-Civil Work Checklist
Problem type Check Item
AThe examination records for the concealed project are completeincludeThe pit (ditch) examination records for the groundwork are complete
The concrete records are complete
ACheck the appearance of the base of the equipment room: No concave, spongy surface,
crack (crack on the surface 1mm), defects of appearance, etc.
BThe dimensions of base section of the equipment room should meet the design
requirements, and the tolerance should be +15/-10mm
BCheck the smoothness of the base surface of the equipment room. The deviation should be
5mm
Picture Case of Common Engineering Problem Civil Work
-
7/21/2019 Engineering Quality Common Problem Series (1) - Civil Work
15/16
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Picture Case of Common Engineering Problem Civil Work
Page 15
Appendix3 Transmission Room-Civil Work Checklist
Problem type Check Item
A Brick laying records are complete
ACheck that the dimensions and azimuth of the equipment room meet the design
requirements
A Check the verticality of each wall. The allowable deviation is 10mm
B
Smoothness of the surface (the allowable deviation for the cement mortar is 4mm; the
allowable deviation for the terrazzo is 3mm; and the allowable deviation for the ground tile
is 2mm)
Picture Case of Common Engineering Problem Civil Work
-
7/21/2019 Engineering Quality Common Problem Series (1) - Civil Work
16/16
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Picture Case of Common Engineering Problem Civil Work
Page 16
Appendix4 Solar energy-Civil Work Checklist
Problem type Check Item
A The concrete records are complete and correct
B
For the cement base on the floor: The distance to the floor, the intensity of the base and the
level deviation should conform to the design requirements. The level deviation of the base
should be no more than 3mm/m; For the overhead cement base:Check whether the
installation holes match the equipment against the construction drawings. The level
deviation of the platform should be no more than 3mm/m
BThe coating of the Fence component complies with the design and specifications
requirements
The spray paint of the Fence component complies with the design and specifications
requirements