Engineering Economic Analysis Canadian Edition Chapter 2: Engineering Costs and Cost Estimating.
-
Upload
arline-doyle -
Category
Documents
-
view
222 -
download
5
Transcript of Engineering Economic Analysis Canadian Edition Chapter 2: Engineering Costs and Cost Estimating.
Engineering Economic AnalysisCanadian Edition
Chapter 2:
Engineering Costs and Cost Estimating
2-2EECE 450 — Engineering Economics
Chapter 2 … Defines cost concepts and engineering cost
estimating. Explains three types of engineering
estimates. Discusses the effect of the learning curve
on cost estimates. Covers models for estimating costs and
benefits. Presents cash flow diagrams to show costs
and benefits.
2-3EECE 450 — Engineering Economics
Engineering Costs Costs: the economic value of the resources
used in the production of goods and services.• Land, labour, capital, and entrepreneurial skills• Initial investment, wages and salaries, material
purchases, utilities
Profits indicate that scarce economic resources are being used properly.• The selling value of the goods and services
produced exceeds the cost of the resources used in their production.
Losses may reflect a waste of resources.
2-4EECE 450 — Engineering Economics
Classification of Costs Fixed: constant and unchanging
• Rent on a building is constant regardless of how much space is utilized.
Variable: depends on activity level• Linear (proportional) or non-linear
Amount of raw material used depends on how many units are made.
Total cost = Fixed cost + Variable cost Marginal cost: variable cost for the next unit. Average cost: total cost per unit =
units of #
MaterialsRent
2-5EECE 450 — Engineering Economics
Fixed, Variable, and Total Costs (Example 2-1)
Bus Rental 80.00$ Event Tickets 12.50$ Gas Expense 75.00$ Refreshments 7.50$ Other Fuels 20.00$ Bus Driver 50.00$ Total FC 225.00$ Total VC 20.00$
People Fixed cost Variable cost Total cost0 225.00$ -$ 225.00$ 5 225.00$ 100.00$ 325.00$
10 225.00$ 200.00$ 425.00$ 15 225.00$ 300.00$ 525.00$ 20 225.00$ 400.00$ 625.00$
Fixed Costs Variable Costs
Total costs
$-
$200
$400
$600
$800
0 5 10 15 20
Volume
Co
st
($)
Total cost
Fixed cost
2-6EECE 450 — Engineering Economics
Costs
OutputTotal Cost
Total Fixed Cost
Total Variable
Cost
Average Fixed Cost
Average Variable
CostAverage
CostMarginal
Cost
1.0 3.0 2.0 1.0 2.00 1.00 3.00 1.0
2.0 3.8 2.0 1.8 1.00 0.90 1.90 0.8
3.0 4.4 2.0 2.4 0.67 0.80 1.47 0.6
4.0 4.8 2.0 2.8 0.50 0.70 1.20 0.4
5.0 5.2 2.0 3.2 0.40 0.64 1.04 0.4
6.0 5.8 2.0 3.8 0.33 0.63 0.97 0.6
7.0 6.6 2.0 4.6 0.29 0.66 0.94 0.8
8.0 7.6 2.0 5.6 0.25 0.70 0.95 1.0
9.0 8.8 2.0 6.8 0.22 0.76 0.98 1.2
10.0 10.2 2.0 8.2 0.20 0.82 1.02 1.4
2-7EECE 450 — Engineering Economics
Total, Variable, and Fixed Costs
Total, Variable, and Fixed Costs
0.0
2.0
4.0
6.0
8.0
10.0
12.0
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0
Output (units)
$
TC
TVC
TFC
2-8EECE 450 — Engineering Economics
Average and Marginal Costs
Average and Marginal Costs
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0
Output (units)
$
ACAVCMCAFC
2-9EECE 450 — Engineering Economics
Profit and Loss Terms Total revenue = Unit price units sold Breakeven: total revenue = total costs
• Just getting by
Profit: total revenue > total costs• Putting money in the bank
Loss: total revenue < total costs• Going into debt
2-10EECE 450 — Engineering Economics
Profit and Loss(non-linear cost and revenue)
Total cost
Total revenue
Profit
OutputProfit Zone
2-11EECE 450 — Engineering Economics
Breakeven (Example 2-2)Ticket price
Bus Rental 80.00$ Event Tickets 12.50$ 35.00$ Gas Expense 75.00$ Refreshments 7.50$ Other Fuels 20.00$ Bus Driver 50.00$ Total FC 225.00$ Total VC 20.00$
People Fixed cost Variable cost Total cost Revenue Profit Region0 225.00$ -$ 225.00$ -$ (225.00)$ Loss5 225.00$ 100.00$ 325.00$ 175.00$ (150.00)$ Loss
10 225.00$ 200.00$ 425.00$ 350.00$ (75.00)$ Loss15 225.00$ 300.00$ 525.00$ 525.00$ -$ Breakeven20 225.00$ 400.00$ 625.00$ 700.00$ 75.00$ Profit25 225.00$ 500.00$ 725.00$ 875.00$ 150.00$ Profit30 225.00$ 600.00$ 825.00$ 1,050.00$ 225.00$ Profit35 225.00$ 700.00$ 925.00$ 1,225.00$ 300.00$ Profit40 225.00$ 800.00$ 1,025.00$ 1,400.00$ 375.00$ Profit
Fixed Costs Variable Costs
Profit-loss breakeven chart
$-
$500
$1,000
$1,500
0 5 10 15 20 25 30 35 40
Volume
Co
st
($)
Total cost
Fixed cost
Revenue
2-12EECE 450 — Engineering Economics
Past (Sunk) Costs Sunk cost: money spent due to a past
decision.• We cannot do anything about these costs.
Example: the amount paid to purchase a car two years ago.
2-13EECE 450 — Engineering Economics
Future (Opportunity) Costs Opportunity cost: a benefit that is not realized
when a resource is engaged in one activity instead of engaging that same resource in another foregone activity.• We make a choice or decision.
Example: Buying lunch instead of gas.
Examine each cost and determine what type it is (Example 2-3).
Price when purchased 7,000.00$ Sunk cost Past decisionsStorage costs 1,000.00$ Sunk cost Past decisionsList price when purchased 9,500.00$ Old list Past decisionsCurrent list price of new pumps 12,000.00$ New list different features Past decisionsAmount offered for pumps 2 years ago 5,000.00$ Foregone opportunity Past decisionsCurrent price that the pumps could be sold for 3,000.00$ Market value Present opportunity
2-14EECE 450 — Engineering Economics
Expense Types Recurring expense: anticipated and occurs at
regular intervals.• Purchasing food, paying rent.
Non-recurring expense: one-of-a-kind event that occurs at an irregular interval.• Illness, accident, death.
Sometimes we attempt to plan for large non-recurring costs by buying insurance. Paying the periodic insurance premium turns this expense into a recurring cost.
2-15EECE 450 — Engineering Economics
Incremental Costs Incremental cost: the difference between the
costs of two alternatives (Example 2-4).
Cost Items A BPurchase price 10,000.00$ 17,500.00$ 7,500.00$ Installation costs 3,500.00$ 5,000.00$ 1,500.00$ Annual maintenance costs 2,500.00$ 750.00$ (1,750.00)$ Annual utility expenses 1,200.00$ 2,000.00$ 800.00$ Disposal costs after useful life 700.00$ 500.00$ (200.00)$
Model Costs
Incremental
2-16EECE 450 — Engineering Economics
Cash versus Book Costs Cash costs: movement of money from one
owner to another.• Also known as a ‘cash flow’.
Payment this month on an auto loan.
Book costs: cost of a past transaction that is recorded in a book.• Down payment recorded in your cheque book from
last year’s automobile purchase.
2-17EECE 450 — Engineering Economics
Life-cycle Costs Life-cycle: all the time from the conception to
the death of a product or process. Life-cycle costs: the sum total of all the costs
incurred during the life-cycle. Life-cycle costing: designing with an
understanding of all the costs associated with a product during its life-cycle.
2-18EECE 450 — Engineering Economics
Phases of Life-cycle Costs
1. Needs assessment and justification
2. Conceptual or preliminary design
3. Detailed design
4. Production or construction
5. Operational use
6. Decline and retirement
2-19EECE 450 — Engineering Economics
Life-cycle Costing In general, the later a product design change
is made, the higher the cost.• Earlier changes are easier and less costly. • Decisions made early in the life-cycle tend to ‘lock-
in’ cost that will be incurred. About 70% to 90% of all costs are committed
during the design phases. Only 10% to 30% of cumulative life-cycle
costs have been spent by the end of the design phase.
2-20EECE 450 — Engineering Economics
Cost Estimating Engineering economic analysis is future
based.• Future consequences (costs and benefits) of
current decisions are analyzed.• Requires estimating.
Estimated costs and benefits are not known with certainty.• The more accurate the estimate, the more reliable
the decision.
2-21EECE 450 — Engineering Economics
Types of Estimates Rough: gut level
• Inaccurate. 30% to +60%.
Semi-detailed: based on historical records• Reasonably sophisticated and accurate. 15% to +20%.
Detailed: based on specifications and cost models• Very accurate. 3% to +5%.
Difficulties arise when the future is uncertain.
2-22EECE 450 — Engineering Economics
Types of Estimates … One-of-a-kind or first time projects
• There are few such projects in engineering economic analysis.Example: First NASA mission.
Resource constraints• Time and human resources.• Quality and accuracy of estimates adversely
affected.
Estimator expertise• Experience and knowledge better quality (and
more reliable) estimates.
2-23EECE 450 — Engineering Economics
Estimating Models
Model Explanation
Per unit Uses a ‘per unit’ factor$/sq ft, Benefits/employee
Segmenting Divide problem into items, estimate each and sum
Cost indexes Index number based on history
Power sizing Scaling previous known costs up or down
Triangulation Looking at costs from several perspectives
Learning curve Tracking cost improvements
Examples
Microsoft Excel
Worksheet
Click the Excel® icon to open a spreadsheet of examples.
2-24EECE 450 — Engineering Economics
In general, as the output doubles, the unit production time will be reduced by a fixed percentage or learning curve rate.• If the 3rd unit took 200 minutes to produce in a
production run with a 90% learning time curve, then the 6th unit will take 200(0.90) = 180 minutes.
Estimating time in repetitive tasks:TN = TInitial Nb
where TN = time required for the Nth unitTInitial = time required for the 1st unit
N = number of completed unitsb = learning curve exponent
Learning Curves
2-25EECE 450 — Engineering Economics
Learning Curve (Example 2-10) A company has a learning curve rate of 85% and a
production run of 20 units. Unit production time is 5.0 minutes when 16 units have been produced. Total production time is 118.8 minutes.
Learning Curve
0.0
2.0
4.0
6.0
8.0
10.0
12.0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Units
Pro
du
ctio
n T
ime
(m
inu
tes)
2-26EECE 450 — Engineering Economics
Cash Flow Diagrams Arrows: the usual interpretation is positive for
cash inflows (revenues) and negative for cash outflows (expenses).• The length of the arrow represents the magnitude
($) of the cash flow.
Time dimension: points in time when the positive and negative cash flows occur
Discount factor
2-27EECE 450 — Engineering Economics
Categories of Cash Flows1. First cost ≡ construction, purchase, or
installation expense.2. Operations and maintenance ≡ annual
expense.3. Salvage value ≡ receipt at project
termination.4. Revenues ≡ annual receipts due to sale of
products.5. Overhaul ≡ major capital expenditure
occurring during life of asset.
2-28EECE 450 — Engineering Economics
Cash Flow Diagrams … Cash flow diagrams summarize the flow of
money over time. They can be represented using a spreadsheet.
Year Capital costs O&M Overhaul Total0 (80,000.00)$ (80,000.00)$ 1 (12,000.00)$ (12,000.00)$ 2 (12,000.00)$ (12,000.00)$ 3 (12,000.00)$ (25,000.00)$ (37,000.00)$ 4 (12,000.00)$ (12,000.00)$ 5 (12,000.00)$ (12,000.00)$ 6 10,000.00$ (12,000.00)$ (2,000.00)$
Cash flow
$(100,000.00)
$(80,000.00)
$(60,000.00)
$(40,000.00)
$(20,000.00)
$-
$20,000.00
0 1 2 3 4 5 6
Year
Cas
h f
low Overhaul
O&M
Capital costs
2-29EECE 450 — Engineering Economics
Cash Flow: Annuity
Project Cash Flows
-$12,000
-$10,000
-$8,000
-$6,000
-$4,000
-$2,000
$0
$2,000
$4,000
$6,000
0 1 2 3 4 5 6 7 8 9 10
End-of-year
$
End of Year
Cash Flow
0 $10,000
1 $5,000
2 $5,000
3 $5,000
4 $5,000
5 $5,000
6 $5,000
7 $5,000
8 $5,000
9 $5,000
10 $5,000
2-30EECE 450 — Engineering Economics
Irregular Cash Flow
Project Cash Flows
-$15,000
-$10,000
-$5,000
$0
$5,000
$10,000
0 1 2 3 4 5 6 7 8 9 10
End-of-year
$End of Year
Cash Flow
0 $10,000
1 $3,000
2 $2,000
3 $1,000
4 $5,000
5 $6,000
6 $2,000
7 $6,000
8 $3,000
9 $4,000
10 $8,000
2-31EECE 450 — Engineering Economics
Cash Flow: Geometric Series
Project Cash Flows
-$15,000
-$10,000
-$5,000
$0
$5,000
$10,000
$15,000
$20,000
0 1 2 3 4 5 6 7 8 9 10
End-of-year
$
End of Year
Cash Flow
0 $10,000
1 $3,000
2 $3,600
3 $4,320
4 $5,184
5 $6,221
6 $7,465
7 $8,958
8 $10,750
9 $12,899
10 $15,479
2-32EECE 450 — Engineering Economics
Suggested Problems 2-3, 2-7, 2-10, 2-11, 2-20, 2-21, 2-23, 2-24, 2-
26, 2-27, 2-28, 2-31, 2-32, 2-34, 2-35, 2-36, 2-37