ENGINEERING & CONSTRUCTION DIVISION
GERALD N. BRINTON, P.E. COUNTY ENGINEER / DIRECTOR OF ENGINEERING &
CONSTRUCTION
VOLUSIA COUNTY
PUBLIC WORKS DEPARTMENT
![Page 2: ENGINEERING & CONSTRUCTION DIVISION GERALD N. BRINTON, P.E. COUNTY ENGINEER / DIRECTOR OF ENGINEERING & CONSTRUCTION VOLUSIA COUNTY PUBLIC WORKS DEPARTMENT.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649ec85503460f94bd46f9/html5/thumbnails/2.jpg)
Engineering & Construction Division
• 5-Year Road Program
• 5-Year Multi-Use Trails Program
• New Facilities Construction Program
• Development Engineering Review
• Right of Way Use Permits
![Page 3: ENGINEERING & CONSTRUCTION DIVISION GERALD N. BRINTON, P.E. COUNTY ENGINEER / DIRECTOR OF ENGINEERING & CONSTRUCTION VOLUSIA COUNTY PUBLIC WORKS DEPARTMENT.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649ec85503460f94bd46f9/html5/thumbnails/3.jpg)
Engineering & ConstructionOrganizational Chart
![Page 4: ENGINEERING & CONSTRUCTION DIVISION GERALD N. BRINTON, P.E. COUNTY ENGINEER / DIRECTOR OF ENGINEERING & CONSTRUCTION VOLUSIA COUNTY PUBLIC WORKS DEPARTMENT.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649ec85503460f94bd46f9/html5/thumbnails/4.jpg)
4
Geographic Zones
Geographic Zones
Five YearFive YearRoad ProgramRoad Program
![Page 5: ENGINEERING & CONSTRUCTION DIVISION GERALD N. BRINTON, P.E. COUNTY ENGINEER / DIRECTOR OF ENGINEERING & CONSTRUCTION VOLUSIA COUNTY PUBLIC WORKS DEPARTMENT.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649ec85503460f94bd46f9/html5/thumbnails/5.jpg)
Five Year Road Program
![Page 6: ENGINEERING & CONSTRUCTION DIVISION GERALD N. BRINTON, P.E. COUNTY ENGINEER / DIRECTOR OF ENGINEERING & CONSTRUCTION VOLUSIA COUNTY PUBLIC WORKS DEPARTMENT.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649ec85503460f94bd46f9/html5/thumbnails/6.jpg)
Five Year Road Program
![Page 7: ENGINEERING & CONSTRUCTION DIVISION GERALD N. BRINTON, P.E. COUNTY ENGINEER / DIRECTOR OF ENGINEERING & CONSTRUCTION VOLUSIA COUNTY PUBLIC WORKS DEPARTMENT.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649ec85503460f94bd46f9/html5/thumbnails/7.jpg)
Road Program…Road Program…Road Program…Road Program
“The Last Hurrah”Volusia County Road Program Capital Investments
13/14 14/15 15/16 16/17 17/18
Zone 1 $12.52M $17.56M $47.95M* 0 0
Zone 2 0 $5.18M $7.8M $3.0M 0
Zone 3 $4.39M $11.44M 0 0 0
Zone 4 0 0 $6.91M 0 0
Total $16.91M $34.18M $62.66M $3.0M 0
* Federal Grant for Veterans Memorial Bridge Replacement
• When Bond money is gone, limited revenues will be focused on safety and intersection upgrades.
• Significant issues continue with funding long term maintenance of the two remaining bascule bridges.
Excludes sidewalk & resurfacing improvements
![Page 8: ENGINEERING & CONSTRUCTION DIVISION GERALD N. BRINTON, P.E. COUNTY ENGINEER / DIRECTOR OF ENGINEERING & CONSTRUCTION VOLUSIA COUNTY PUBLIC WORKS DEPARTMENT.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649ec85503460f94bd46f9/html5/thumbnails/8.jpg)
Funded Construction ProjectsFunded Construction Projects
Ormond Beach• Tymber Cr Rd 4 Laning - SR40 to Peruvian Ln $6,133,000
(County)(Recently Completed)
Orange City• Saxon Blvd 6 Laning - I-4 to Enterprise Rd $2,950,000
(County) (Recently Completed) $1,443,000 (State Grant)
Daytona Beach• Orange Av Reconstruction - Nova Rd to Beach St $1,660,000 (County)
(Under Construction) $4,679,000 (State Grant)
• Dunn Av Paved Shldrs - Clyde Morris to Bill France $140,000 (County) (Under Construction) $1,404,000 (State Grant)
FY 2014/2015
![Page 9: ENGINEERING & CONSTRUCTION DIVISION GERALD N. BRINTON, P.E. COUNTY ENGINEER / DIRECTOR OF ENGINEERING & CONSTRUCTION VOLUSIA COUNTY PUBLIC WORKS DEPARTMENT.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649ec85503460f94bd46f9/html5/thumbnails/9.jpg)
Funded Construction ProjectsFunded Construction Projects
Deltona• Doyle Rd Paved Shldrs - Courtland Blvd to SR415 $1,150,000 (Fed
grant)(Construction Contract Awarded) $176,000
(County)
• Howland Blvd 4 Laning - Courtland Blvd to SR415 $4,236,000 (County)(Under Construction) $5,879,000
(State Grant)
N Smyrna Beach• Pioneer Trl at Turnbull Bay Rd $376,000 (County)
(Under Construction) $1,053,000 (State Grant)
• Turnbull Bay Bridge Replacement $3,789,000 (Fed Grant)
FY 2014/2015
![Page 10: ENGINEERING & CONSTRUCTION DIVISION GERALD N. BRINTON, P.E. COUNTY ENGINEER / DIRECTOR OF ENGINEERING & CONSTRUCTION VOLUSIA COUNTY PUBLIC WORKS DEPARTMENT.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649ec85503460f94bd46f9/html5/thumbnails/10.jpg)
Funded Construction ProjectsFunded Construction Projects
Holly Hill• LPGA Blvd 4 Laning - Jimmy Ann to Derbyshire $1,300,000 (County)
$965,000 (State Grant)
Port Orange• S Williamson Ext - Airport Rd to Pioneer Trl $9,800,000 (County)
Partnership with Pioneer CDD $5,500,000 (State Grant)
(Construction Contract Awarded)
FY 2014/2015 (continued)
![Page 11: ENGINEERING & CONSTRUCTION DIVISION GERALD N. BRINTON, P.E. COUNTY ENGINEER / DIRECTOR OF ENGINEERING & CONSTRUCTION VOLUSIA COUNTY PUBLIC WORKS DEPARTMENT.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649ec85503460f94bd46f9/html5/thumbnails/11.jpg)
Funded Construction ProjectsFunded Construction Projects
DeLand• Kepler Rd at SR44 Intersection
$1,400,000 (County) $821,000 (State Grant)
• Orange Camp Rd 4 Laning - MLK Blvd to I-4 $4,690,000 (County)
Edgewater/N Smyrna Beach• Tenth St 4 Laning - Myrtle Av to US 1 $5,000,000
(County)
$2,800,000 (State Grant)
Daytona Beach• Veterans Memorial Bridge Replacement $47,950,000 (Fed
Grant)
FY 2015/2016
![Page 12: ENGINEERING & CONSTRUCTION DIVISION GERALD N. BRINTON, P.E. COUNTY ENGINEER / DIRECTOR OF ENGINEERING & CONSTRUCTION VOLUSIA COUNTY PUBLIC WORKS DEPARTMENT.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649ec85503460f94bd46f9/html5/thumbnails/12.jpg)
Funded Construction ProjectsFunded Construction ProjectsFY 2016/2017
![Page 13: ENGINEERING & CONSTRUCTION DIVISION GERALD N. BRINTON, P.E. COUNTY ENGINEER / DIRECTOR OF ENGINEERING & CONSTRUCTION VOLUSIA COUNTY PUBLIC WORKS DEPARTMENT.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649ec85503460f94bd46f9/html5/thumbnails/13.jpg)
Funded Construction ProjectsFunded Construction ProjectsSuccess in Leveraging Grant Funding
1.8 to 1 Ratio(in just 4 fiscal years)
Grant Funds $77,433,000County Funds $44,019,000
“Takes Money to Leverage Money”
![Page 14: ENGINEERING & CONSTRUCTION DIVISION GERALD N. BRINTON, P.E. COUNTY ENGINEER / DIRECTOR OF ENGINEERING & CONSTRUCTION VOLUSIA COUNTY PUBLIC WORKS DEPARTMENT.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649ec85503460f94bd46f9/html5/thumbnails/14.jpg)
Status of Regional Trails System
Showcase Trails Showcase Trails SystemSystem
• 33.4 miles constructed
• 27.6 miles construction funded next three years
• 9.5 miles construction unfunded
2005 – 2015
![Page 15: ENGINEERING & CONSTRUCTION DIVISION GERALD N. BRINTON, P.E. COUNTY ENGINEER / DIRECTOR OF ENGINEERING & CONSTRUCTION VOLUSIA COUNTY PUBLIC WORKS DEPARTMENT.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649ec85503460f94bd46f9/html5/thumbnails/15.jpg)
Regional Trails System when finished
70.5 miles
![Page 16: ENGINEERING & CONSTRUCTION DIVISION GERALD N. BRINTON, P.E. COUNTY ENGINEER / DIRECTOR OF ENGINEERING & CONSTRUCTION VOLUSIA COUNTY PUBLIC WORKS DEPARTMENT.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649ec85503460f94bd46f9/html5/thumbnails/16.jpg)
Status of Regional Trails SystemStatus of Regional Trails System
33.4 miles completed27.6 miles funded
9.5 miles unfunded70.5 miles total system
![Page 17: ENGINEERING & CONSTRUCTION DIVISION GERALD N. BRINTON, P.E. COUNTY ENGINEER / DIRECTOR OF ENGINEERING & CONSTRUCTION VOLUSIA COUNTY PUBLIC WORKS DEPARTMENT.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649ec85503460f94bd46f9/html5/thumbnails/17.jpg)
Status of Regional Trails System