Energy Planning and Approval Strategies
description
Transcript of Energy Planning and Approval Strategies
Energy Planning and Approval Strategies
1
Overview
2
outline
Strategic – BC Hydro Long Term Planning
Project level Environmental Assessment
▪ Federal - Canadian▪ Comparative US + pipelines
Integration
3
BC Hydro – supply gap
4
BC Hydro - planning
Integrated electricity planning - the long-term planning of electricity generation, transmission, and demand-side resources to reliably meet forecast requirements.
2000s - long-term acquisition plan (LTAP) every 4 yrs Needs to be reviewed and approved by BCUC
2010 Clean Energy Act – IRP replaces LTAP Same problem for analysis and decision-
making but different consultation, review, and
approval
5
Utility planning
Planning context, objectivesGross (pre-DSM) demand forecastsResources (supply and DSM) – ID and
measurementDevelop resource portfoliosEvaluate and select resource
portfoliosDevelop action planConsultGet approval 6
2008 LTAP developments
Application submitted to BCUC June 2008 Evidentiary update December 08
Formal hearings in BCUCBCUC decision rejecting plan July
2009 Greenpolicyprof summary
7
BC government response
May 2010: Clean Energy Act passed. New IRP process Removed from BCUC scrutiny
8
9
Evaluation
What are the consequences of removing BC Hydro planning from BCUC review?
10
BC Hydro IRP presentationhttp://www.bchydro.com/etc/medialib
/internet/documents/planning_regulatory/iep_ltap/2011q2/bc_hydro_irp_-_webinar.Par.0001.File.BC-Hydro-IRP-Webinar-Presentation-April-2011.pdf
11
Change in Self-sufficiency Timing delayed by rate review Old: by 2016 enough B.C.-based energy to
meet customer demand even in critical water conditions; and by 2020, an extra 3,000 gigawatt hour per year of insurance energy
New: by 2016, enough B.C.-based energy to meet customer demand in an average water year
The Province will also propose changes to the Clean Energy Act to eliminate the insurance requirement 12
outline
Strategic – BC Hydro Long Term Planning
Project level Environmental Assessment
▪ Federal - Canadian▪ Comparative US + pipelines
Integration
13
Project level – Environmental Assessment – Case study oil sands pipelines
14
Environmental Assessment
Environmental Assessment as a policy tool – a “procedural policy instrument” Requires analysis and procedure but does not
specify outcome
15
Stages in EA
1. Proposal from proponent2. Screening – is EA required and if so
what kind?3. Scoping – what issues?4. Assessment of the proposal5. Report preparation, submission,
and review6. Decision: recommendation by EA
body, authoritative decision by political body
7. Monitoring and compliance follow-up
16
Environmental Assessment – Federal in CanadaCanadian Environmental Assessment Act
Came into force in 1995 Since 1972, governed by cabinet
guidelines applies to anything that requires federal
approval or permit Procedures managed by
Canadian Environmental Assessment Agency, within Environment Canada
Usually, if federal EA no provincial EA 17
CEAA Process
1. Determine if an environmental assessment is required
2. Identify responsible authority (RA)3. screening – initial assessment
If potentially significant adverse effects or significant public concern, requires mediation or panel review
4. Conduct the analysis and prepare the environmental assessment report
5. RA Reviews environmental assessment report6. Make environmental assessment decision7. Implement mitigation and follow-up program, as
appropriate 18
CEAA approval standards
(a) where, taking into account the implementation of any mitigation measures that the responsible authority considers appropriate,
(i) the project is not likely to cause significant adverse environmental effects, or
(ii) the project is likely to cause significant adverse environmental effects that can be justified in the circumstances
the responsible authority may exercise any power or perform any duty or function that would permit the project to be carried out in whole or in part
19
CEAA results
99% of projects approved
20
Pipeline Governance – Institutions
Within province, provincial government lead jurisdiction
Across provincial boundaries, federal lead jurisdiction
Across international boundaries, federal + US US State Department issues permits
increasing role for First NationsEnvironmental assessment critical
February 12, 2013 Sustainable Energy Policy 21
Pipeline Governance – ActorsFederal GovernmentNational Energy Board – lead
approval authorityEnvironment Canada –
environmental effects and assessment process
Transport Canada – terminal and tanker safety
Department of Fisheries and Oceans
February 12, 2013 Sustainable Energy Policy 22
Pipeline Policy
Interprovincial transport: National Energy Board NEB standard is “public interest” plan, assess, mitigate, approve Issues Certificates of Public Convenience
and Necessity – can attach conditions Hearings required for > 40 km
February 12, 2013 Sustainable Energy Policy 23
Enviro Checklist for EA
Sustainability as core objective
Strengthen public participation
Meaningfully engage Aboriginal governments as decision makers
Legal framework for strategic and regional EA
Require comprehensive, regional cumulative effects assessments
Coordinate multiple jurisdictions with highest standards
Transparency Fair, predictable,
accessible Rights over
efficiency
24
EA process criteria
Guided by sustainability principlesParticipatoryTransparent Well-informedCoordinated to avoid jurisdictional
conflicts and overlapsTimely
February 12, 2013 Sustainable Energy Policy 25
There are tradeoffs between these values. Fostering legitimacy while being timely requires adequately resourced processes
Harper’s “responsible resource development” – Spring 2012
Replace CEAA Definition of environmental effect narrowed Participants limited to are “directly affected” or
have, in the review panel’s judgment, “relevant information and expertise”
Time limits Transfer authority to provinces
NEB Act – final decision moved to cabinet Fisheries Act – reduce habitat protection
Bill C-38 and EA process
February 12, 2013 Sustainable Energy Policy 27
Should EA procedures allow for the approval of projects likely to cause significant adverse environmental effects?
Should EA’s have time limits
February 12, 2013 Sustainable Energy Policy 28
outline
Strategic – BC Hydro Long Term Planning
Project level Environmental Assessment
▪ Federal - Canadian▪ Comparative US + pipelines
Integration
29
Comparative Pipeline Politics:Oil Sands Pipeline Controversies in Canada and the United States
George Hoberg, Andrea Rivers, Geoff SalomonsUniversity of British ColumbiaInsert for CEEN 590 Feb 27, 2013
Shocking reversal of fortune for Alberta
February 12, 2013 32
The price gap crisis
February 12, 2013 Sustainable Energy Policy 33
WCS – Western Canadian Select – blend of heavy crude oil and bitumen
WTI – West Texas Intermediate (primarily US oil)
Brent – Combination of oil from 15 fields in North Sea – closer to world price
Actors/interests
KEYSTONE XL
TransCanada Pipeline Oil sands companies Rival pipelines Enviros – GHGs, spills,
aquifer Nebraska
NORTHERN GATEWAY PIPELINE Enbridge Oil sands companies Rival pipelines Enviros – tankers,
spills First Nations
Institutions
KEYSTONE XL
Divided government Presidential
government Adversarial legalism State control of
pipeline siting
NORTHERN GATEWAY PIPELINE Conservative Majority Leader-centred
parliamentary system Enabling legislation Federal paramountcy First Nations
Ideas
KEYSTONE XL
Jobs Economic growth American energy
security Risks to water Risks to climate
NORTHERN GATEWAY
Jobs Economic growth Future prosperity Foreign-funded
radicals Oils spills from
tankers Pipeline accidents Aboriginal rights China
Environmental AssessmentScreening – is EA required, if so what
kind? Both processes most intensive
Scoping – what issues should it consider? US included GHGs, Canada excluded
GHGsAssessment
Canada done by gov, US by contractorDecision – both processes require
assessment but do not alter the balance of decision values
Approval process
KEYSTONE XL International pipeline –
State Department “national interest” determination
NEPA environmental impact statement required
Extensive hearings, analysis
Presidential determination Obama postponed,
rerouted proposal under consideration
NORTHERN GATEWAY PIPELINE National Energy Board CEAA environmental
assessment required Joint Review Panel = CEAA
+NEB Extensive hearings,
analysis Current status
Draft report sent to cabinet; cabinet comments
NEB makes final decision*
Keystone Protests
39
Backlash – discredit environmentalists
40
environmental and other radical groups
funding from foreign special interest groups
threaten to hijack our regulatory system to achieve their radical ideological agenda
The regulatory system is broken
Backlash – revamp environmental law Replace CEAA
Definition of environmental effect narrowed Participants limited to are “directly affected” or
have, in the review panel’s judgment, “relevant information and expertise”
Time limits Transfer authority to provinces
NEB Act – final decision moved to cabinet Fisheries Act – reduce habitat protection
interactions
Binational network of interest groups Enviros, foundations Multinational energy companies
Canadian government lobbying Impact on Obama decision: Dramatic
intensification of Harper gov urgency to see pipeline approved
Conclusions - general Similar structure of interests
different types of place-based opposition: First Nations and tankers in BC, aquifer in US
Enabled by institutions in different ways Different salience of issues
Tankers in Canada; Climate in US Similar reliance on EA, with limits
Big difference in scope, driven by legalism Political control of regulatory process
shaped by institutional and partisan differences
Final thoughts
Can diffuse issues like climate change ever motivate political action, or are placed-based essential to motivation
Environmental Assessment - conclusion
requires elaborate assessment demonstration of awareness of concerns consideration of environmental impacts
and mitigation measures but project can still be approved if
justified By forcing agencies to consider
environmental consequences, environmental assessment is a critical tool, but it does not affect the balance of values decision-makers ultimately apply.
February 12, 2013 Sustainable Energy Policy 45
Cumulative effects?
“effects that are additive or interactive and result from the recurrence of actions over time. Cumulative impacts are incremental and result when undertakings build on or add to the impacts of previous impacts.”
Consideration required in federal rules, permitted but not required in BC
What is the best way to deal with cumulative effects in project level assessments?
46
Institutions for renewable energy expansion – criteria (Jaccard et al)
47
Alternatives, consequencesJaccard et alIRP + PROJECT SPECIFIC ASSESSMENT/APPROVALS risks larger than
necessary local environmental effects
Risks less satisfied public
STRATEGIC ASSESSMENT Risks delay in
renewable development (and climate change mitigation)
48
An important tradeoff that needs to be considered in process design