energy made Transmission Limited (SHETL) better...(1 x 3c 132kV cable per circuit, a total of 3...
Transcript of energy made Transmission Limited (SHETL) better...(1 x 3c 132kV cable per circuit, a total of 3...
-
Scottish Hydro Electric Transmission Limited (SHETL)
energymadebetter
Presentation to the Argyll and Bute
Renewable Energy Alliance (ABRA)
“A Wires Overview”Wednesday 22nd June 2011
Alec Morrison – Transmission Commercial Policy Manager
-
Transmission and Distribution
Transmission system - the ‘motorways’
Distribution systems – the ‘A’ and ‘B’ roads
The grid functions as a single ‘meshed’ network
-
PORT ANN BSP
InverarayClachan
Nant
TAYNUILT BSPCruachan
Dalmally
Sloy
Windyhill SP
Argyll & Kintyre
DUNOON BSP
CARRADALE BSP
Hunterston
Inverarnan
132 kV275 kV
ARRAN
MULL
BUTE
COWALJURA
-
ColonsayJura
SouthKintyre
Cowal
Arran
Islay DunoonGrid
CarradaleGrid
Port AnnGrid
-
Tiree
Mull
Ardnamurchan(mainland)
Coll
Inveraray
Fort WilliamGrid
TaynuiltGrid
-
Connection Summary – 12.7GW (Excludes Pre-1990 Hydro)
Connected, 1.1
Contracted O nshore, 4.8
Contracted O ffshore, 4.6
Future O ffshore & Marine, 2.2
0
2
4
6
8
10
12
14
GW
Existing system can accommodate 1.5GW.
Transmission works have been identified to accommodate additional contracted schemes. A number are under construction.
Future position kept under review. Additional transmission works may be required, but will depend on utilisation of existing works.
-
South West Generation Statistics
• Connected– Small DG: 56MW– Large: 161MW
• Contracted– Small DG: 63MW – Large Onshore: 256MW– Large Offshore: 400MW
• Future– Onshore:
-
Transmission Development Proposals (1)
Balance between “make best use of what we’ve got” and “creating additional transmission capacity”
• Completed– Greater Grid Supply Point capacity at Taynuilt, Port Ann and Carradale– 3rd 132kV Circuit between Sloy and Inveraray– Inverarnan 275 / 132kV substation
• Short-Term Proposals– Connect & Manage
• Medium-Term Reinforcements– Hunterston – Crossaig– Crossaig - Carradale
-
Transmission Development Proposals (2)
Balance between “make best use of what we’ve got” and “creating additional transmission capacity”
• Longer-Term Reinforcements– 132kV Rebuild between Inveraray and Crossaig, forecast October 2017– 132kV Rebuild between Inveraray and Taynuilt, forecast October 2015
– HVDC link across South Kintyre (via underground cable) to Hunterston - WITHDRAWN
– Potential for HVDC Converter Station on Islay and an HVDC link to the Ayrshire coast
-
PORT ANN BSP
InverarayClachan
Nant
TAYNUILT BSPCruachan
Dalmally
Sloy
Windyhill SP
Argyll & Kintyre
DUNOON BSP
CARRADALE BSP
Hunterston
Inverarnan
132 kV275 kV
ARRAN
MULL
BUTE
COWALJURA
-
Hunterston – Crossaig Update
• Delayed from 2013 to 2015
– Route constraints (limited seabed routes for subsea crossing to the north of Arran); unable to lay 2 circuits (3 x 1c 132kV cables per circuit, a total of 6 cables); alternative is 3 circuits (1 x 3c 132kV cable per circuit, a total of 3 cables). This has required additional seabed survey.
– Alternative is too heavy for traditional subsea laying techniques given the water depth of up to 170m.
– Considering alternative 220kV technology, 2 circuits (1 x 3c 220kV cable per circuit, 2 cables), but requires additional development, testing and quality assurance for asset integrity and life.
– Availability of cable manufacturing and installation capacity is constrained due to high demand from offshore wind installations.
-
Example 132kV Substation with woodpole ‘Trident’ overhead line Example 132kV Substation
Typical AC 132kV Wood Pole Overhead Lines
-
13
HVDC Infrastructure
• Converter station
• Onshore HVDC cable(s)
• Switching station
• Offshore HVDC cable(s)
• Offshore HVDC connection hub
-
HVDC Converter Stations
• Large buildings with outside sub station infrastructure
• Likely dimensions for shed 120 m x 60 m x 15 m
• Overall footprint 400 m by 400 m
ABB technology
Siemens technology
Estlink converter station shedsEstlink converter station site
-
Transportation
• Converter and substation will require delivery of heavy loads
• A few may exceed 200 tonnes
• Special vehicles will spread load across many axles
• Sharp turns and hump-backs may create issues
• Potential to use local harbours as delivery points
Typical vehicle for transformer transport
-
Thank you for listening
Do you have any Questions?
Alec MorrisonSHETL, Transmission Commercial Policy Manager
Tel: 01738 456770 email: [email protected]
Slide Number 1Transmission and DistributionSlide Number 3Slide Number 4Slide Number 5Slide Number 6Slide Number 7Slide Number 8Slide Number 9Slide Number 10Slide Number 11Example 132kV Substation with woodpole ‘Trident’ overhead lineSlide Number 13Slide Number 14Slide Number 15Slide Number 16