    The purpose of this procedure is to define the guidelines

    for handling Site Queries.

    The scope of this procedure covers Site Queries raised by

    any MMG Department at all project sites.

    SITE QUERIES

    Are questions raised at a project site which are addressed to

    the Customer or Customer Representative for clarification.

    REFERENCES

    Project Field Change : Procedure No. END-3-004

    Change Request : Form No. END-4-004C

  • 7/30/2019 END 3 013 Site Querry

    3/10

    PROJECT MANAGER

    In overall charge of the project operation, reviews andapproves all Site Queries raised in the project site.

    FIELD ENGINEERING SUPPORT GROUP

    SUPERVISING ENGINEER

    Supervise the Field Engineering Support Group, raise SiteQueries and review those originating from other

    departments.

    FIELD ENGINEERS

    Raise Site Queries for identified field problems, changes indrawings & specifications, field re-routing problems and

    conduct site verification for recommendation of proposed

    resolution.

  • 7/30/2019 END 3 013 Site Querry

    4/10

    (continuation)

    DOCUMENT CONTROLLER

    Responsible for receiving, recording, distribution and

    updating all Site Queries passing through the office of the

    Field Engineering Support Group.

    PROJECT DEPARTMENT HEADS

    Responsible for raising Site Queries regarding their

    respective work discipline.

  • 7/30/2019 END 3 013 Site Querry

    5/10

    Field Engineering Support Group will review all incoming

    construction drawings, specifications and applicable standard

    references, conflicts between a drawings and specification for any

    applicable standard reference shall be addressed for the attentionof the Customer Representative, in writing, using Site Query Form

    No. END-3-013A.

    Field Engineers shall conduct a daily field inspection of work in

    progress, and take note of any field problem encountered by Project

    Team members, Such problems may involve the re-routing of lines(piping, electrical, cables, conduits, ductwork and etc..) obstruction

    due to existing facilities, grade elevations, dimensions and

    locations on drawings, differing from the actual site condition and

    such other field problems requiring clarifications by the Customer

    or Customer Representative. The Field Engineering addresses this

    in writing, using Site Query Form No. END-4-013A.

    The originating Discipline Project Department Heads/Manager and

    Field Engineering Support Group Supervising Engineer will review

    the Site Query raised in project site, to verify the technical aspects

    of the query , and recommend a Proposed Resolution.

  • 7/30/2019 END 3 013 Site Querry

    6/10

    (continuation)

    If the Site Query requires clarification from the Customer

    or Customer Representative, the Originating ProjectDepartment Heads/Manager and Field Engineering Support

    Group Supervising Engineer shall sign the site Query and

    forward for approval of the Project Manager.

    The approved Site Queries are recorded by the Document

    Controller in the Site Query Tracking Log (Form No. END-4-013B) and forward to the Customer or Customer

    Representative.

    Any response from the Customer Representative shall be

    reviewed by the Project Manager and the Field Engineering

    Support Group Supervising Engineer before it is forwarded

    to Construction Manager / Discipline Superintendent for

    implementation. The Document Controller shall complete

    the record on the Site Query Tracking Log, and file a copy

    of the Site Query.

  • 7/30/2019 END 3 013 Site Querry

    7/10

    PROJECT FIELD ENGINEERING

    TASK TITLE

    SITE QUERY

    (END-3-013)

    SUPERVISING / FIELD ENGINEER

    Raise Site Queries requiringclarification / decision by

    Customer

    (END-4-013A)

    Transmit Site Queries

    Response to the originatingEngineers

    Transmit Site Queries

    to Customer

    START

    A1 End

    CUSTOMEREvaluation /

    Responses

    PROJECT DOCUMENT CONTROLLER

    PROJECT DOCUMENT CONTROLLERPROJECT DOCUMENTCONTROLLER

    Records all Site Queries /Responses

    (END-4-013B)

  • 7/30/2019 END 3 013 Site Querry

    8/10

    PROCEDURE FOR SITE QUERY

    Site Queries are questions raised at a project site, address to Customer

    for clarification. Site Queries are raised by MMG at the project site.

    SITE QUERY RAISED BY FIELD ENGINEERING

    Field Engineering Support Section will review all incoming

    construction drawings, specification, applicable standards, references

    and other project documents, issued by the Customer at the project

    site. Conflicts between the drawings and specification or any applicable

    standard reference shall be addressed for the attention of the Customer

    or Customer Representative, in writing, using Site Query Form No. END-4-013A.

    Field Engineering shall raise Site Query on problem encountered

    during Field Operations, which need clarification / and/or decision by

    Customer or Customer Representative before the work can be

    performed or continued. Such problem may involve re-routing of lines

    (piping, electrical cables, conduits, duct works, and etc) obstructiondue to the existing facilities, grade elevations, and location on the

    drawing differing from the actual site conditions, and such other field

    problems. Site Query address in writing using the Site Query Form No.

    END-4-013A.

  • 7/30/2019 END 3 013 Site Querry

    9/10

    SITE QUERY RAISED BY FIELD ENGINEERING

    (continuation)

    The originating Discipline Project Department Heads / Managers

    and Field Engineering Manager or Supervising Engineer will reviewthe Site Query to verify the technical aspects of the query and

    recommend a Proposal Resolution.

    Site Query is then forwarded to the Project Manager for approval.

    Approved Site Queries are then transmitted to the Customer or

    Customer Representative. Site Query is recorded by MMG Document

    Controller using the Form END-4-013B (Site Query Tracking Log)

    Customer or Customer Representative will evaluate the Site Query.

    Customer may either decide to approve the recommended Proposed

    Resolution or make comments on the proposed resolution for

    implementation.

    The Site Query will be forwarded to Originator, Construction

    Manager / Discipline Superintendent for implementation. MMG

    Document Controller completes the record on the Site Query

    Tracking Log and file a copy of the Site Query.

    NOTE : In some cases, a Site Query may necessitate the raising of a Change

    Request Form END-4-004C shall be prepared by the Field Engineering inaccordance with Procedure END-3-004 Project Field Change?