ENA Open Networks Project Workstream 1: Product 1 · The report consists of four sections,...
Transcript of ENA Open Networks Project Workstream 1: Product 1 · The report consists of four sections,...
The Voice of the Networks
ENA Open Networks Project
Workstream 1: Product 1
Mapping current SO, TO and DNO processes
12th June 2017
Energy Networks Association
Document Ref: TDWS1P1
Restriction: None
2 | P a g e
Executive Summary
Product 1 of ENA Open Networks Project (Workstream 1) seeks to capture the data
and processes underlying the DNOs and SO/TOs operational and investment
planning, including the role of ancillary services and customer connections. The
interface between DNOs and SO/TOs is critical for the effective development of these
plans and as such the Grid Code defines firm procedures to facilitate the
collaboration between the organisations.
The investment planning process involves an exchange of data between the SO and
DNOs. The SO submits an equivalent model of the transmission network to DNOs
(Week 42 model) which then feeds into the DNOs investment planning. DNOs merge
this with their model and produce a set of data to be submitted back to the SO (Week
24). Week 24 submissions contains information about past and forecasted demand
on agreed dates and times, as well as details on a reduced version of the distribution
network.
DNO investment planning makes use of historical demand data as well as information
related to economic growth within their area of operation. Customer connection
requests, network limitations and condition of assets are also taken into account.
Operation planning teams from SO, TOs and DNOs work closely together in order to
develop their operational plan. The Grid Code, again, defines strict processes with
the aim to coordinate the SO, TOs and DNOs outage planning and optimise whole
system operation without compromising its security.
DNO operational planning focuses on outages required by different parties including
the SO/TOs, customers and internal DNO teams. Outage planners consider a number
of factors before approving an outage and prioritize the security of supply.
Customers apply for connection to transmission or distribution network depending
on the size of their generation or demand. The TOs and DNOs run a set of studies and
check to accommodate customer’s request at least cost but without compromising
the system’s security. A process called SOW is in place to manage the interface
between the transmission and distribution networks where connections at the latter
are deemed to have the potential to impact the transmission system.
The SO utilises a range of services to support secure and economic system
operation. These services, traditionally supplied by transmission-connected
generators only, are increasingly being sourced from DER too.
3 | P a g e
Document Control
Version Issue Date Author Comments
1 19/05/2017 Draft reviewed by Working Group
2 12/06/2017 Comments incorporated
4 | P a g e
Contents
Executive Summary ............................................................................................................ 2
Document Control ............................................................................................................... 3
Contents .............................................................................................................................. 4
Acronyms ................................................................................. Error! Bookmark not defined.
1. Introduction ................................................................................................................ 8
2. Operational Planning ............................................................................................... 10
2.1 SO/DNO Interface Process ............................................................................... 10
2.1.1 Information provided by the SO to DNOs ................................................. 10
2.1.2 Information provided by DNOs to SO ....................................................... 11
2.1.3 Reviews ................................................................................................... 12
2.2 DNO Outage Planning ...................................................................................... 12
2.3 TO/SO Operational Planning ............................................................................ 14
3. Investment Planning ................................................................................................ 15
3.1 TO/SO/DNO Interface Process ......................................................................... 15
3.1.1 Week 24 submission (DNO to SO) .......................................................... 15
3.1.2 Week 42 submission (SO to DNO) .......................................................... 19
3.2 DNO investment planning ................................................................................. 20
3.2.1 Planning Assumptions/Information model ................................................ 20
3.2.2 Planning Load Estimates (PLE) ............................................................... 21
3.2.3 Planning .................................................................................................. 21
3.2.4 Long Term Development Statement (LTDS) ............................................ 23
3.3 TSO Investment Planning (National Grid) ......................................................... 24
3.3.1 Investment Process & Investment Types ................................................. 24
3.3.2 Planning Information and Assumptions .................................................... 25
3.3.3 Network Options Assessment .................................................................. 26
3.3.4 Main DNO and Whole System Interactions .............................................. 27
3.4 TOs/GBSO Interface Investment Planning ........................................................ 27
4. Customer connection process ................................................................................ 28
4.1 Transmission customers ................................................................................... 28
4.1.1 Generator Connections ............................................................................ 28
4.1.2 Demand connections ............................................................................... 31
4.1.3 Overlap of criteria between generation and demand connections ............ 32
4.1.4 Design variation ....................................................................................... 32
4.2 Distribution customers ...................................................................................... 32
5 | P a g e
4.3 Statement of Works Process (DNO/TSO Connections) ..................................... 34
5. The SO Process for Developing and Procuring Services ..................................... 36
Appendices ....................................................................................................................... 39
A Operational Planning maps .................................................................................... 40
A.1 Operational Planning SO/DNO Interface ........................................................... 40
A.2 DNO Operational Planning ................................................................................ 42
B Investment Planning maps ...................................................................................... 43
B.1 Week 24 submission ......................................................................................... 43
B.2 DNO Investment Planning ................................................................................ 44
B.3 TSO Investment Planning ................................................................................. 45
B.4 NOA Process .................................................................................................... 46
C Customer Connection Maps ......................................................................................... 51
C.1 Statement of Works process ............................................................................. 51
C.2 Appendix G process (England and Wales) ........................................................ 52
6 | P a g e
Glossary
ACS Average Cold Spell
AHS Average Hot Spell
ANM Active Network Management
BEGA Bilateral Embedded Generation Agreement
BELLA Bilateral Embedded Licence Exemptible Large Power Station Agreement
BM Balancing Mechanism
BSP Bulk Supply Point
CNAIM Common Network Asset Indices Methodology
CUSC Connection and Use of System Code
DER Distributed Energy Resources
DG Distributed Generator
DNO Distribution Network Operator
DSO Distribution System Operator
DSR Demand Side Response
DTU Demand Turn-up
EFR Enhanced Frequency Response
ENA Energy Network Association
ERPS Enhanced Reactive Power Services
EWAP Eight Week Ahead Programme
FCDM Frequency Control by Demand Management
FES Future Energy Scenarios
FFR Fast Frequency Response
FiT Feed in Tariff
FR Fast Reserve
GB Great Britain
GBSO Great Britain System Operator
GSP Grid Supply Point
HI Health Index
HV High Voltage
HVDC High Voltage Direct Current
JTPM Joint Technical Planning Meeting
LI Load Index
LRR Load Related Reinforcement
LTDS Long Term Development Statement
LV Low Voltage
MD Maximum Demand
MITS Main Interconnected Transmission System
NDP Network Development Process
NG National Grid
NGET National Grid Electricity Transmission
NOA Network Options Assessment
OC Operation Code
OFTO Offshore Transmission Owner
OP Outage Planning
7 | P a g e
ORPS Obligatory Reactive Services
OTSUA Offshore Transmission System User Assets
PLE Planning Load Estimate
POC Point of Connection
RO Renewable Obligation
SFTP SSH File Transfer Protocol
SHET Scottish Hydro Electric Transmission
SLD Single Line Diagram
SOW Statement of Works
SPT Scottish Power Transmission
SQSS Security and Quality of Supply Standard
SSE Scottish Hydro Electric
STC System Operator - Transmission Owner Code
STOR Short Term Operating Reserve
TEC Transmission Entry Capacity
TO Transmission Operator
TOGA Transmission Outage and Availability
(T)SO Transmission System Operator
8 | P a g e
1. Introduction
This report is the output of Product 1 from the ENA Open Networks Project working group / Workstream 1. It captures processes and data that underlie the DNO and SO/TO investment and operational planning as well as the interface between them. Process maps have been developed to improve the understanding of the given information.
The report consists of four sections, Investment Planning, Operational Planning, Customer Connections and Ancillary Services. Each section provides details on critical steps that individual organisations follow to plan the development and operation of their networks.
The interface between SO/TO and DNOs is key to the planning process and as such explicitly dictated by the Grid Code. The diagram below is a good representation of this interface and the Grid Code sections referring to it. The four areas represent Asset Management and Operations within a DNO and TO/SO while the arrows connecting the areas reflect the associated data and processes.
GR
ID
CO
DE
DA
TA E
XC
HA
NG
E IN
TER
FAC
E
Interfaces for Grid Code Standard Planning Data exchange
INV
ES
TM
EN
T P
LA
NN
ING
OP
ER
AT
ION
S
NETWORK OPERATOR (14)Investment Planning
TRANSMISSION
OWNERS
NGET
SPT
SHETL
NGET SYSTEM
OPERATORNETWORK OPERATOR (14)
Operations
DISTRIBUTION TRANSMISSION
Joint Technical Planning Liaison Meetings for further SPD planning data (PC.A.2.1.4)
Grid C
ode S
tanda
rd P
lannin
g D
ata
As
required for
Invest
ment P
lannin
g
SO
– T
Os
LIA
ISO
N
Indiv
idual D
NO
Lia
ison
and D
iscu
ssio
n
NB Grid Code does not
provide data from
National Grid to Network Operator
for asset investment planning
purposes (load f low infeeds)
Joaquin Jimenez Issue 14.0
April 2014
9 | P a g e
There are fourteen DNOs connected in the GB system who are responsible for developing and
maintaining the regional distribution networks:
DNO Area Company
1 East England UK Power Networks
2 East Midlands Western Power Distribution
3 London UK Power Networks
4 North Wales, Merseyside and Cheshire SP Energy Networks
5 West Midlands Western Power Distribution
6 North East England Northern Powergrid
7 North West England Electricity North West
8 North Scotland SSEN (Scottish Hydro Electric)
9 South Scotland SP Energy Networks
10 South East England UK Power Networks
11 Southern England SSEN (Southern Electric)
12 South Wales Western Power Distribution
13 South West England Western Power Distribution
14 Yorkshire Northern Powergrid
The GB onshore transmission system is owned by three regional transmission companies:
• National Grid Electricity Transmission plc (NGET) for England and Wales (above
132kV)
• Scottish Power Transmission Limited for southern Scotland (132kV and above)
• Scottish Hydro Electric Transmission plc for northern Scotland and the Scottish islands
groups (132kV and above)
These companies (TO - Transmission Owners) are permitted to develop, operate and maintain a high voltage system within their own distinct onshore transmission areas.
Offshore Transmission Owners (OFTOs) are not considered in this study.
National Grid Electricity Transmission plc (NGET) undertakes the role of the System Operator (SO) for the GB transmission system. The SO is responsible for ensuring the stable and secure operation of the whole transmission system.
10 | P a g e
2. Operational Planning
2.1 SO/DNO Interface Process
The following diagram illustrates the interaction between the SO and DNOs for exchanging operational data as required by the Grid Code. A more detailed diagram with associated timelines can be found in Appendix A.
Operational Planning SO/DNO Interface Point
Sho
rt T
erm
2-5
year
s ah
ead
1 Ye
ar a
hed
DNO develops outage schedule and sends to SO
SO develops proposed outage schedule and sends
to DNOs
DNO reviews and raises issues and concerns
Is DNO happy with proposed plan?
NO
SO delivers the Draft National Electricity
Transmission System outage plan covering period Years
2 to 5 ahead
YES
SO updates the draft outage plan and sends proposed
schedule to DNOs
DNO develops outage schedule and sends to
SO
SO revises proposed outage plan and sends
schedule to DNOs
DNO reviews and raises issues and
concerns
Is DNO happy with proposed plan?
NO
SO delivers the final National Electricity
Transmission System outage plan covering Year 1
YES
SO revises outage plan on a short term basis and
notifies DNO
DNO reviews and raises issues and concerns
Is DNO happy with proposed change?
NO
SO updates TOGA platform with most up-to-date
outage planYES
DNO prepares the Eight Weeks Ahead Programme (EWAP) and submits to NG
on a weekly basis
SO submits a Power Factory network model to DNO on a
weekly basis
DNO merges the model with their outage planning model
SO sends declared generation availability to DNO on a daily basis (for
few days ahead)
SO sends generation SYNC/DESYNC schedule for next
day to DNOs
FOR COMMENT
The following sections describe the information the SO submits to DNOs to feed into their operational planning and vice versa.
2.1.1 Information provided by the SO to DNOs
This section is a brief description of the information provided by the SO to the DNOs with regards to outage planning. Most of the requirements below are dictated by the OC2 section of the Grid Code.
Week 28
In week 28 (around July), the SO delivers a year ahead draft outage plan (April to March). It is usually an excel file sent via email and accompanied by a pdf with the following information:
a. Reference number
b. Plant
c. Time of isolation
d. Type of outage
e. Return to service emergency time
f. Details of the work to be carried out
g. Safety documentation
11 | P a g e
DNO outage planners (OP) have meetings with the SO before the formal issue of the plan in order to discuss concerns and negotiate alignment between distribution and transmission outage plans. After submission, OP confirm acceptance and review; a meeting may follow to discuss any potential issues and concerns. DNOs have up to week 36 to notify the SO if unhappy with proposed plan.
A similar process is conducted for the 2-5 year ahead time period, with data again being submitted in Week 28.
Week 49
In week 49, the SO submits the final outage plan as a revision of the week 28 one year ahead submission. The plan incorporates the discussions that take place before and after the Week 28 data submission.
TOGA (Transmission Outage and Generation Availability) platform
TOGA is a self-service data exchange platform, which contains the most up-to-date outages schedule. DNOs and other SO customers access it on a daily basis to inform their processes. The SO sends notifications before updating the outage schedule on TOGA in order for DNOs to raise any potential concerns. The format of the information provided is similar to week 28 data.
OC2 weekly model
The SO submits a network model (DigSILENT PowerFactory) to DNOs on a weekly basis. The model represents distribution networks with equivalents and it is up to each DNO to merge their models. The model is a snapshot of how the SO is planning to run the transmission network for the week ahead. The model is uploaded on an SFTP drive by the Customer Network Data – Network Access Planning team and includes forecasted peak transmission connected generation for the following week.
Availability of Generation
The SO updates DNOs about availability of generation as declared by generators (synchronous generator only, not HVDC and windfarms). The update is undertaken on a daily basis; it is looking a few days ahead and includes only generators that affect the respective DNO network. This information is provided by the SO control room via email from the Performance Review, Commercial optimisation team. The data is shown as maximum MW availability and corresponding time (e.g. 19/05/2015 1900 – 2200).
Synchronisation / De-synchronisation data
The SO submits data around expected synchronisation and de-synchronisation times of generators in the area (synchronous generator only, not HVDC and windfarms). The submission is completed on a daily basis; it is looking one day ahead and includes information for generators that affect the DNO network only. The data is provided in table format through a Fax from the SO control room. The table is populated with ON and OFF actions corresponding to each generator and the associated timestamp (e.g. ON at 19/05/2015 1900, OFF 29/06/2015 2200)
2.1.2 Information provided by DNOs to SO
The next section describes information that DNOs provide to the SO.
Eight Weeks Ahead Programme or EWAP
EWAP is a report submitted by the DNO to the SO and other interested parties (network rail, generators, critical customers etc.) via email on a weekly basis. It describes planned outage details for the following 8 weeks including:
a. Reference number for outage
12 | P a g e
b. Circuits to be taken out of service
c. Start and end date
d. Work description
e. Comments
f. Type of outage
Outage planning report (week 8)
In week 8, DNOs send a report with planned outages required for works to be carried out in the next 2-5 years. Its format is similar to the EWAP above and it is submitted to the SO short term planning team at Wokingham.
Outage planning report (week 32)
In week 32, DNOs send a report with planned outages required for works to be carried out during next year. Its format is similar to the EWAP above and it is submitted to the SO year-ahead planning team at Wokingham. Data include outages that may have impact on transmission network and/or Maximum Export/Import declared Capacity at the GSP.
2.1.3 Reviews
DNO Outage Planners sit in a number of meetings before or after the official submission dates. The objective of the meetings is to discuss proposed schedules, plans and practicalities around outages, raise awareness of future works and maintain a channel of communication between the planning teams.
1. JTPM (Joint Technical Planning Meeting). This meeting involves people from the DNO
outage planning and asset management teams as well as the TOs and SO. It takes place
2-3 times per year; there is no fixed period and it depends on availability and number of
issues identified. It is a forum where the SO/TO and DNOs present a high level list of works
to be carried out in the next few years. Participants discuss plan and raise concerns on
potential issues
2. Meeting with SO Year Ahead planners to discuss week 28 and 49 data. This is an ad-hoc
meeting
3. Formal meeting around Q1 of each year to discuss week 49 data with SO/TO Current Year
Planners. The meeting takes place after SO/TO internal handover from Year Ahead to
Current Planners.
4. Access meeting: Every three months with Current Year Planners to discuss network
configuration of the next 3 months
5. Operation Liaison Meetings - Meetings with TO Site responsible engineers to discuss site
issues and practicalities of required outages
2.2 DNO Outage Planning
The section below attempts to capture the steps followed by the DNOs outage planning teams for assessing and approving a requested outage. The following diagram is a brief overview of the process and it shows a sequence of specific checks and assessments that take place in the long and short term. A more detailed version of the diagram can be found in Appendix A.2.
13 | P a g e
DNO outage planningSh
ort
Ter
m (
~2-3
wee
ks)
Long
ter
m (
>6m
ont
hs)
Outage request
High level checks from Outage Planning
Is the outage feasible?
NOHigh Level Study of Available options
Is the outage feasible?
NODiscussions with requester and proposal of other options
YES
Record outage into the plan with high level details
YES
Review long term outage
plan
Detailed checks
Is the outage feasible?
Detailed Study of Available options
Is the outage feasible?
Discussions with requester and proposal of other options
Communicate proposed outage to all relevant parties
Are there any objections?
Proceed with outage and inform control engineers
NO NO
YES
Development of outage details
YES
NO
YES
Communicate proposed outage to all relevant parties
Are there any objections?
YES
NO
DNO teams or customers have to submit a request for outage slots to the Outage Planning (OP) teams. This usually takes the form of an excel spreadsheet, which contains the following information:
a. Plant or Circuit to be taken out of service
b. Emergency Time Recovery
c. Date and time of outage
d. Details for the works to be carried out
The outage planners use this information to carry out a first set of checks that include:
a. Technical Limitation Records (TLRs) for the part of the network around the plant/circuit
b. Network abnormalities
c. Relevant Policies and Procedures
d. System Loads (historical demand and generation for the same period)
e. Fault Levels and Power Flows
f. Clashes with already scheduled outages (SO/TO and DNO)
g. Third party network reconfigurations (IDNOs, SO/TO, Network Rail, London
Underground etc.)
h. Line patrols
i. Site checks
j. Protection Settings
The above checks consist of a high-level analysis to assess whether the requested outage is feasible. The main objective of the outage planning team is to minimise the risk to customers (generation and demand) by making sure, where possible, that the next potential loss will not interrupt their supply and will not have any detrimental effect on the network.
14 | P a g e
If the request is not feasible, the outage planner will study a number of options that may help to accommodate the outage. The set of available options includes:
a. Load transfers
b. Generation Curtailment (MW)
c. Network reconfiguration
d. Stand-by generation
If the available options are not sufficient, the outage planner will examine other periods when the outage may be more feasible and discuss with the requester. It might also be the case that a number of works need to be completed first before the outage takes place.
The final agreed outage and its details are then recorded into the DNOs outage plan for informing all relevant parties (National Grid, IDNOs, customers with private networks, Network Rail etc.). The outage planning team reviews the outage if any of the relevant parties raise concerns.
A very similar process is followed in the short term, closer to the actual date of the requested outage. The analysis is carried out in greater detail including more up-to-date information with regards to system loads (generation and demand), network configuration and technical limitations. The planners also check alternative network running arrangements that minimise the risk to customers and maintain the network’s security.
At the end of the process, the outage planning team will develop a set of information that describes the outage and the works to be carried out. This consists of:
1. Visio file with proposed running arrangement
2. Date and time of outage
3. Works to be carried out
4. Emergency Return to Service time
5. Any other additional requirements (stand-by generator etc.)
The information is again submitted to relevant parties, including the DNO operation engineers, who review and comment on the proposed outage. If any concerns are raised, the outage planning team will review the plan and follow the same process until the outage is approved. The approved outage and associated details are forwarded to the control room for implementation.
2.3 TO/SO Operational Planning
TO/SO process mapping follows the requirements of STC Processes (STCP11.1 and 11.2) for Outage Planning and Outage Data Exchange between TO/SO. These documents can be found below:
STCP11-1 - Outage
Planning.pdf
STCP 11-2 Outage
Data Exchange.pdf
OFTOs have been considered only as a connecting party not impactful on overall process mapping.
15 | P a g e
3. Investment Planning
3.1 TO/SO/DNO Interface Process
This section describes the investment planning procedures with respect to the TO/SO/DNO Interface. The purpose of these processes is for the TO to establish whether the system is compliant with the National Electricity Transmission System Security and Quality of Supply Standard (commonly referred to as the NETS SQSS or SQSS) and trigger remedial works if not. As the following diagram demonstrates, TO/SO/DNO investment planning consists of a loop of exchanging data between the parties. Key dates of the process are:
• Week 17: The SO makes an official request to DNOs for data including SLDs, agreed
Access periods and times of Min/Max GB demand.
• Week 24: Described in section 3.1.1 (DNOs may delay this by week 28)
• Week 42: Described in section 3.1.2
• Week 6: TO confirms compliance with SQSS
The week 42 model provided to DNOs by the SO is used to produce the week 24 data submission for next year.
Week 17SO request data including SLDs,
agreed Access Periods & times of Max/Min demands.
Week 24 (28)DNOs compile data &
provide to SO
SO acknowledge receipt of data to
DNO.
SO inform NG users and TOs of data
availability
SO and TOs review. Any queries?
DNOs review and update YES
SO set up Year 1 winter peak model
TOs & DNO review compliance with SQSS / P2
Week 42SO calculate infeed and provide
data to DNOs
DNOs review. Further info?
YES
NO
DNOs merge with distribution network model
Week 6TOs release compliance report LTDS
3.1.1 Week 24 submission (DNO to SO)
Week 24 data (DNO may delay the submission up to week 28) is developed based on the following guidance notes and submitted to SO (Customer Network Data Team) using the Data Exchange Portal.
16 | P a g e
DNO Guidance
Notes v8.pdf
A brief summary of the information included in the week 24 (or 28) submission is as follows:
1. Total Network Operator Demand Profiles (Schedule 10)
Half-hour daily demand profiles in MW are submitted in Schedule 10. The data reflects the DNO's total demand and it is calculated by summing up the demand at primary substations (historical and forecast):
a. Table 10a - User’s Total System Demand Profile - Day of User’s Peak Demand (date
and time calculated by DNO)
b. Table 10b - User’s Total System Demand Profile - Day of GB Peak Demand (date and
time provided by SO in week 17)
c. Table 10c - User’s Total System Demand Profile - Day of GB Minimum Demand (date
and time provided by SO in week 17)
In addition, the tables include generation netted out (summated over all Grid Supply Points for the peak half hour of the day).
2. Demand Data per GSP for SQSS Compliance Assessments (Schedule 11 and 17)
Data is calculated by summing up the demand at primary substations (historical and forecast) and netting out generation. The calculations are carried out for the last and the next eight financial years (forecast).
a. Schedule 17: Access Period Data. Table with a visual indication of Access Periods
agreed between NG and DNOs by week 17
b. Demand data for Time of GB Transmission System Peak/Minimum Demand. Dates
and times given by SO. Forecast per primary site from Planning Load Estimates.
c. Demand data for Time of GSP Peak Demand. The date and time are calculated by the
DNO by summing up the demand at primary substations and netting out generation.
Forecast per primary site from Planning Load Estimates.
d. Demand data for Time of GSP Peak within Access Period. The date and time are
calculated by the DNO by summing up the demand at primary substations and netting
out generation. Forecast per primary site from Planning Load Estimates. In addition, a
table with available load transfer per Access Group is provided.
More specifically, the tables include the following information:
• Date and time
• Power Factor
• GSP Demand at time specified (MW and MVAR)
• Deduction made for Small Power Stations, Medium Power Stations and Customer
Generating Plant (MW)
• Reference to Single Line Diagram and to node and branch data spreadsheet
3. Table 11C: User’s Total System Active Energy Data
a. Energy for customers per class (LV, HV, EHV, Rail, Public Lighting)
b. System Losses
c. Energy from Embedded generating plant under 100MW
d. Forecast for next 8 financial years
17 | P a g e
4. Embedded Small Power Stations >1MW ( Schedule 11)
A list of embedded generators above 1MW with information such as:
a. Reference number
b. Connected node as named in the SLD
c. Fuel type
d. Registered capacity (MW)
e. Control Mode (power factor or voltage control)
f. Geographical location
g. Type of loss of mains protection
h. Loss of mains protection setting
5. Embedded Generation Data (Schedule 11)
A table for each GSP with the following information for the last and the following eight financial years (forecast)
a. For each GSP where there are Embedded Small Power Stations, Medium Power
Stations or Customer Generating Stations the following information is provided:
i. No. of Small Power Stations, Medium Power Stations or Customer Power
Stations
ii. Number of Generating Units within these stations
iii. Summated Capacity of all these Generating Units in MW
b. Where the DNO places a constraint on the capacity of an Embedded Large Power
Station
i. Station Name
ii. Generating Unit
iii. System constrained Capacity
iv. Reactive Dispatch Network Restriction
c. Where the DNO places a constraint on the capacity of an Offshore Transmission
System at an Interface Point
i. Offshore Transmission System Name
ii. Interface Point Name
iii. Maximum Export Capacity
iv. Maximum Import Capacity
6. Demand Control (Schedule 12)
a. Low Frequency Relay Settings (Table 12a)
This table provides information about automatic demand disconnection for different
frequency set points. The calculation is carried out per GSP and is based on a
preselected set of sites that are equipped with the necessary relays. Total demand to
be disconnected is calculated by summing up the demand at those primaries on GB
peak day.
b. Demand Control by Voltage Reduction and/or Demand Disconnection (Table 12b).
DNOs inform SO whether Demand Control is to be implemented either by
i. A combination of voltage reduction and Demand Disconnection
18 | P a g e
ii. Demand Disconnection alone,
Together with the magnitude of the voltage reduction stages (where applicable) and
for Demand Disconnection stages, the demand reduction anticipated.
c. Emergency Manual Disconnection (Table 12c)
The table lists the available cumulative demand disconnection 5/10/15/20/25 and 30
minutes after an SO instruction. It is shown per GSP and expressed in percentage of
GSP peak demand on GB peak day. It is calculated by summing up the demand of all
primary substations fed by the respective GSP. Demand disconnection is carried out
manually by DNO control room.
7. Equipment Data (Schedule 14)
a. LV Switchgear data (Table 14a). The table contains the information for all DNO circuit
breakers at each GSP:
i. Rated voltage (kV)
ii. Operating voltage (kV)
iii. Rated 3-phase rms short-circuit breaking current, (kA)
iv. Rated 1-phase rms short-circuit breaking current, (kA)
v. Rated 3-phase peak short-circuit making current, (kA)
vi. Rated 1-phase peak short-circuit making current, (kA)
vii. Rated rms continuous current (A)
viii. DC time constant applied at testing of asymmetrical breaking abilities (secs)
b. LV Substation Infrastructure Data (Table 14b). The table contains the information for
DNO Substation Infrastructure at each GSP. A single value for the entire substation
is supplied, provided it represents the most restrictive item of current carrying
apparatus.
i. Rated 3-phase rms short-circuit withstand current (kA)
ii. Rated 1-phase rms short-circuit withstand current (kA).
iii. Rated 3-phase short-circuit peak withstand current (kA)
iv. Rated 1- phase short-circuit peak withstand current (kA)
v. Rated duration of short circuit withstand (secs)
vi. Rated rms continuous current (A)
c. Reactive Compensation Plant Data (Table 14c). Table showing all independently
switched reactive compensation equipment not operated by the SO and connected to
the DNO’s system, other than power factor correction equipment associated directly
with Customers' Plant and Apparatus.
i. Type of equipment (e.g. fixed or variable);
ii. Capacitive and/or inductive rating or its operating range in MVAr;
iii. Details of any automatic control logic to enable operating characteristics to be
determined;
iv. The point of connection to the DNO System (including OTSUA) in terms of
electrical location and System voltage
8. Network Data (Schedules 5 and 13)
19 | P a g e
a. Single Line Diagram
DNOs submit a Single Line Diagram (SLD) to the SO. The SLD illustrates the normal
configuration of the distribution network. The network is reduced based on rules
defined in the Grid Code. It also shows node demand as calculated using the week 42
network model on GB peak day. Future works (reinforcements, replacements, new
connection etc.) are shown as mark-ups.
b. Network Data (Schedule 5)
This table contains the following information for the nodes and lines shown in the SLD:
Nodes data:
i. Voltage
ii. P, Q, S and power factor
iii. I’’,I’, X/R
iv. R0, X0 and B
Electrical parameters for lines:
i. Seasonal rating in MVA (winter, summer, spring, autumn)
ii. R1, X1 and B1
iii. R0,X0 and B0
iv. Rm, Xm and Bm
v. Info on couplings
Electrical parameters for transformers:
i. HV and LV vector group
ii. Grounding and earthing (type and Ohms)
iii. Tap range and step
iv. R1, X1, B1 and R0, X0, B0
v. Base rating in MVA
c. Fault Infeed data (Schedule 13)
The table contains fault infeed data for nodes in the SLD forecasted for the following 8
years
Demand and fault infeed data calculated using the week 42 network model for GB peak day.
By Week 6, the TO is required to provide the DNO’s with details of the week’s defining the proposed start and finish of each access period for each Transmission Interface Circuit and the connection points in each access group.
In addition to this, by week 6 the TO is required to issue to the DNO’s the results of any assessments undertaken to confirm whether the connection points are compliant against the SQSS
A diagram summarising the week 24 submission can be found in Appendix B.1
3.1.2 Week 42 submission (SO to DNO)
Week 42 model is submitted by SO (Customer Network Data, Network Access Planning) to DNOs. The SO is obliged to provide this Network Data under the Planning Code section of
20 | P a g e
the Grid Code to enable DNOs to model the National Electricity Transmission System in relationship to short circuit contribution.
The week 42 data is included in excel tables and submitted to DNOs for them to produce the equivalent transmission network in their modelling tools. The data comprise of fault infeeds from transmission network at the interface point, data for SGTs and lines interconnecting GSPs, and ratings for circuit breakers at the GSPs. Although not required by the Grid Code the SO also submits a network diagram showing the network configuration used to derive the week 42 data. The data is produced for GB peak winter demand. More information can be found in the guidance note below:
Guidance Note of
NG Network Data (Week42) Submission to DNOs- Revised.doc
3.2 DNO investment planning
This chapter captures the processes followed by DNOs during their investment planning. The outcome of these processes feed directly or indirectly to the interface data exchanged with TO/SO.
The first two sections give a brief overview of the general tools used by DNOs to forecast demand and assess their networks capacity. The diagram below is a high-level description of this process but not all steps are necessarily carried out by all DNOs
Planning Assumption / Information model
Planning Load Estimates (PLEs) Excel Tool
Data from external databases(FiT, Housing,
Commercial and Industrial activity, DNVL etc.)
Historical demand
Forecasted demand per Primary Substation
Load transfers
Infrastructure Development Plan
New Connections
Historical demand
Winter and Summer peak demand per site for last and future 8 years
(forecast)
Internal databases
3.2.1 Planning Assumptions/Information model
DNOs use a variety of models estimating future demand, to support their investment planning. To forecast effectively, these models, in addition to historic demand data and internal generation databases, may also take into account information available from government or other organisations. The information is directly connected to economic development and demand growth and may include, but not limited to:
• jobs,
• housing growth,
• commercial floor space,
• electric vehicle registrations,
• databases with FiT and RO information,
21 | P a g e
• planning applications
The outcome of the forecasting model is usually an anticipated demand growth per substation, which is used to inform the development of the Planning Load Estimates (see below).
3.2.2 Planning Load Estimates (PLE)
Planning Load Estimates (PLEs) or equivalents are developed once a year and are used by various parts of the DNO business as they contain critical substation information such as forecasted maximum demand (summer and winter), date and time of peak, firm capacity and power factors. PLEs are used predominantly by planners, to inform investment planning.
In order to obtain maximum demand per substation (value, date and time), DNOs look at historical data from past year and carry out a cleansing exercise to filter out any network or measurement abnormalities that result in non-representative values.
DNOs may also apply ACS (Average Cold Spell) and AHS (Average Hot Spell) to peak demand for winter and summer respectively. These factors are used to account for extreme conditions (e.g. very low temperatures) that occurred during the time of peak but are not representative for the respective time period. Average values are estimated using historical weather data from stations located around the country.
The substation maximum demand (MD) values for the current year are used as the starting point to forecast the MD for a number of years ahead. There are a number of aspects that must be considered during development of the PLEs. These include:
1. Relevant outcomes from regional infrastructure development plans (including new
substations, changes in substation firm capacity and load transfer actions)
2. Underlying load growth – incremental underlying load growth on individual substations is
added to each current year value to obtain a future forecast. The incremental additions
shall be obtained by the forecasting model described above.
3. New connections – impacts of new loads that are above the normal incremental demand
growth at a particular substation
Power Factors for each substation are usually obtained by measurements and are reviewed regularly.
3.2.3 Planning
The following section gives a high-level overview of the general processes being followed by DNOs to develop their investment plan. The diagram on the following page is a graphical representation of these processes and how they are interconnected. It is divided into four sections representing the different timeframes during which the plan is developed and implemented. A more detailed version of the diagram is in Appendix B.2.
22 | P a g e
DNO Investment PlanningD
eliv
ery
Fo
reca
stin
gA
nal
ysis
Op
tio
nee
rin
g
Design and Operation Limitations
Asset Health Indices
Planning teams analyse existing network (load flows, fault levels, P2 compliance, outage management, other regulatory requirements)
Connection Requests
Are there any constraints (current or future)?
Planning Load Estimates and Load Indices
Modelling of Constraint
YES
Analysis and Optioneering
Modelling of options
Select least cost technically acceptable solution
High Level Design
Detailed Design
Delivery of solution
START
END
NO
The first stage (forecasting) includes the following activities:
1. DNOs produce the Planning Load Estimates (PLEs) or equivalent which may contain,
among others, the following key information:
a. Summer and Winter firm capacity per substation for the last and the next 8 years
b. Summer and Winter peak demand per substation for the last and the next 8 years
c. Summer and Winter power factor per substation
PLEs show whether any substation is presently, or forecasted to be, out of firm capacity and drive the Load Related Reinforcements (LRR).
2. DNOs receive connection applications from demand and generation customers. These
applications are forwarded to the planning teams for assessment. This information drives
the customer-led reinforcements.
3. Asset Management is responsible for monitoring the condition of the DNO assets and
report any replacement requirements. They are using CNAIM (Common Network Asset
23 | P a g e
Indices Methodology) to produce Health and Criticality Indices that reflect the age and
likelihood of failure of assets as well as the impact of their failure in terms of number of
customers being affected. When a need for asset replacement is identified, the team
forwards a mandate to the planning team with details of the intervention required
(replacement, refurbishment etc.).
The second stage corresponds to the analysis carried out by the planning teams taking into account the information provided above as well as other operation and design requirements. The latter may include outage restrictions, fault levels, strategic investments and regulatory requirements such as P2 compliance and LI (Load Index) targets. The LI tables are produced based on PLEs and contain information about the previous year’s loading of the DNO substations.
Planners use the above information to identify current or future constraints in the network. A thorough analysis of the constraint and an investigation of a number of options to resolve it (optioneering) is then carried out. The analysis includes power flow and fault level studies, site specific issues, timescales, costs, safety and environmental concerns as well as security and quality of supply considerations. In addition, it takes into account other projects and the wider network state and limitations. It must be noted that constraints are not looked at in isolation but planners try to align solutions and projects (e.g. they may opt to bring a reinforcement (load-growth driven) scheme forward to harmonise it with an asset replacement (asset condition/health driven) scheme).
The optioneering study carried out draws from a pool of available solutions ranging from conventional asset replacement to more innovative approaches such as Demand Side Response and Active Network Management. The optimal solution is then selected to proceed to the next stage.
After approval, the document is forwarded to delivery teams, responsible for producing a more detailed design which describes the development of the proposed solution looking into the design, procurement, commission, test and commission of the project.
3.2.4 Long Term Development Statement (LTDS)
Every DNO produces a Long Term Development Statement (LTDS) that provides developers with sufficient network data, forecasts and commentary to carry out initial assessments of project feasibility. The statement also informs existing users of the distribution network about development proposals.
The LTDS contains the following information:
1. Circuit data
2. Transformer data
3. Load Information (past and forecast for next 5 years)
4. Fault Level Information
5. Generation
6. New connections interest (both demand and generation)
The development process is similar to week 24 data but it includes much more details about the distribution network (e.g. 33kV assets, geographical arrangements etc.). The week 42 network model submitted by the SO feeds into the LTDS preparation as well.
24 | P a g e
3.3 TSO Investment Planning (National Grid)
This chapter captures the process followed by National Grid in the development and delivery of transmission investments. Transmission network investments are developed and delivered through the National Grid TO function. The National Grid SO (GBSO) inputs to this process on system access and operability aspects. Further details of National Grid TO investment process are included below.
Recently, the Network Options Assessment process has been introduced to determine transmission boundary capacity requirements and preferred reinforcements. This process is operated by the GBSO and is also detailed in this section.
3.3.1 Investment Process & Investment Types
The key internal National Grid TO investment process is referred to as the Network Development Process (NDP). This comprises a number of stages with “gates” to manage the transition of investments between stages. This is illustrated in the diagram below.
High Level Network Development Process
The stages of the Network Development Process operate as follows:
Establish Drivers – Investment projects broadly comprise i) customer driven works (eg
local and enabling works for new generation connections), ii) other load related work to
meet system security standards, and iii) non-load related work to replace equipment on
the basis of condition and criticality. (A recommendation to proceed with a transmission
boundary investment through the NOA process is also, in effect, an investment driver.)
Initial Business Plan Entry – A project is included in the investment plan if it is needed to
meet an investment driver. A portfolio of the works required (investment plan) to meet
our current understanding of all investment drivers is maintained with provisional costs
and milestones. A Needs Case document is created for each project to record the need,
a high-level assessment is undertaken and a standard solution is used to provide a cost
forecast and milestones for business planning. When the milestones indicate that it is
necessary to begin pre-construction works, the project is further progressed. For
customer connections, there are additional works to provide a customer offer. An
Investment Team is formed to develop the works to offer a contracted date against a
reasonable scope. The customer project is progressed if the customer agrees the offer.
Select Options - The driver for work is reviewed before optioneering is undertaken to
identify with more certainty the scope, programme, forecast cost and risks. Sufficient
work is undertaken to assess options and identify the preferred option; this will be
selected based on a financial (Net Present Value) and whole life value approach. This
25 | P a g e
stage will typically span two to six months. Forecast costs will be updated and the project
will move to the next stage for full development and sanction.
Develop & Sanction - Further work is undertaken to develop the preferred option to the
level of accuracy required to achieve financial sanction and move into the delivery
phase; this stage will typically span five to fourteen months. The purposes of this stage
are to confirm commitment to the preferred option, refine the design to identify
efficiencies and address outstanding risks and opportunities, and provide baseline
scope, outputs, programme and forecast costs for future tracking. A financial (Net
Present Value) and whole life value approach will be used to identify the option to be
taken forward for sanction. A specification for procurement and delivery activities will
also form part of the Project Execution Plan.
Execute Project - This stage encompasses the delivery phase, from tendering and
contract award through physical works on site to commissioning and completion of asset
data drawings. Once physical works have been completed, a Project Manager’s report
will be finalised to confirm that the outputs identified in the Needs Case have been
physically delivered and recorded in the appropriate business systems.
Review & Close Project - A Closure Paper is presented to the appropriate governance
body. Checks are carried out to confirm that the scheme elements have been closed in
all business systems, and that all reported costs are final and complete.
The Network Development Process is further represented in Appendix B3 on TSO Investment Planning. This shows the 3 main investment drivers being customer connecton requests, the need to provide transmission infrastructure capacity to meet NETS SQSS requirements and the need to replace existing assets due to their deteriorating condition. From the National Grid TO’s perspective, the NOA process also provides an investment driver for a sub-set of transmission infrastructure capacity.
3.3.2 Planning Information and Assumptions
The key planning information that is used to determine investment projects include:
For customer driven connections, in its connection application, the customer provides
data on the size, location, timing and technical parameters of the generation or demand
development. This includes standard planning data as per the Grid Code provisions.
DNO demand estimates (see section 3.1.1) are used to assess the requirement for local
supply point reinforcement.
Asset health information and condition reports are used to help determine requirements
for non-load related asset replacement work. These will be used with system criticality
information and regulatory outputs to prioritise the investments that are taken forward.
Each year, the National Grid SO produces a set of holistic energy scenarios that are used by National Grid and others for planning. The Future Energy Scenarios (FES) are produced annually through a process of industry analysis and consultation. They normally cover 3 to 4 holistic scenarios covering a 20 to 25 year period. From the investment persective, the FES are used to inform the need for load related works.
26 | P a g e
FES Scenarios for Electricty & Gas
3.3.3 Network Options Assessment
To identify the need and preferred options for wider load related work to increase transmission boundary capabilities, the Network Options Assessment (NOA) process is used. This process is further described in STC Procedure STCP 21-1 and in the NOA Report Methodology (Draft 3, 12th May 2017).
This process is developing year to year. The latest high level process is illustrated below. The more detailed elements of the process are shown in Appendix B4.
Overall, the GBSO co-ordinates the NOA process and carries out the cost benetit analysis to recommend preferred reinforcement options. In broad terms, where there is a need to increase boundary capabilities to meet future boundary transfers, options for reinforcements are worked up and evaluated. These options include TO network reinforcement options and any non-network reinforcement options based on “smart” use of the existing network or on commercial arrangements with transmission service providers.
27 | P a g e
Where the GBSO recommends through the NOA process that a particular transmission reinforcement is taken forward, the TO will account of this recommedation in its investment planning.
3.3.4 Main DNO and Whole System Interactions
The 2 main areas where the SO, TOs and DNO’s interface on investment are:
Grid supply point security & investment requirements.
Distributed generation connection impacting the transmission network.
3.4 TOs/GBSO Interface Investment Planning
Coordination of TO investment plans with the GBSO is defined in the STC. The three main processes associated with this are detailed in the following documents:
1. STCP18-1 Connection and Modification Application, this document details the
process and timelines with which the Scottish TOs exchange information with the SO
to provide connection offers to developers requesting connection (Section 4.1). Link:
http://www2.nationalgrid.com/WorkArea/DownloadAsset.aspx?id=8589935636
2. STCP16-1 - Investment Planning, this document details the process and timelines
with which the Scottish TOs exchange information with the SO to develop investment
plans for the GB transmission system. Link:
http://www2.nationalgrid.com/WorkArea/DownloadAsset.aspx?id=8589936017
3. STCP21-1 - Network Options Assessment (NOA), this document details the process
and timelines with which all the TOs exchange information with the SO to develop
reinforcement options for the main MITS (Main Interconnected Transmission System)
boundaries. Link:
http://www2.nationalgrid.com/WorkArea/DownloadAsset.aspx?id=8589936305
Any wider TO MITS reinforcement investment will follow a similar process to the NDP plan
described in Section 3.3.1 and the information exchange between the TO and GBSO is
governed by item 2.
The NOA process in item 3 describes the process for wider system reinforcements on the
main MITS boundaries. The NOA methodology is under review with the latest draft in:
http://www2.nationalgrid.com/WorkArea/DownloadAsset.aspx?id=8589940300
28 | P a g e
4. Customer connection process
4.1 Transmission customers
This section discusses the analysis carried out by the TOs in assessing generation and
demand connections. Generation and demand connection applications are received from
current and prospective users of the transmission system. Upon receipt of a connection
application, the TO undertakes the relevant connection studies using the planning data
provided by the applicant to determine the appropriate connection works required to
accommodate the connection in accordance with the SQSS.
Affected TOs and Applications Steering Groups
For connections to the NGET transmission network that might impact the Scottish Transmission companies (and vice-versa), the System Operator and Transmission Owner Code (STC) requires that all of the affected Transmission Owners and the System Operator input to the application process through an Application Steering Group. This group will meet through the application to ensure that potential impacts on other transmission networks are considered.
Connect and Manage
In some cases it may not be feasible to meet the customers requested connection data and complete all of the transmission reinforcement works that may be required. Where the customer can connect and operate ahead of the wider works being completed, a “Connect and Manage” arrangement can be put in place.
4.1.1 Generator Connections
Section 2 of the SQSS covers the onshore generation connection design criteria to be applied
by the TO in the analysis of generator connections. The criteria focus on two main areas; i.e.
loss of power infeed and connection capacity requirements. In addition to the generation
connection criteria of the SQSS section2, the MITS design criteria of section 4 should also be
maintained considering the new generator. For defined relevant secured events in the SQSS,
29 | P a g e
the connection design should not result in generation disconnection beyond the specified loss
of power infeed. This is important for the system wide security. Equally, for defined relevant
secured events in the SQSS, the remaining assets should not be overloaded and the voltage
level at user sites should remain within the relevant planning limits. Additionally, the system
should remain stable.
When all the works required to comply with the SQSS sections 2 and 4 have been identified,
the Connect and Manage1 criteria are applied to determine those works which are enabling
for the connection and those that can be categorised as wider works. Enabling works are those
works required between the connection point and the nearest MITS substation, where the
‘MITS substation’ for the purposes of Connect and Manage is defined as a transmission
substation with connections to more than four transmission circuits excluding Grid Supply
Point (GSP) transformer circuits. Enabling works are the minimum transmission reinforcement
works that need to be completed before a generator can be connected and given firm access
to the transmission network. Wider works on the other hand on the other hand are the other
transmission reinforcement works (i.e. not Enabling Works) associated with reinforcing the
network to accommodate the new generator and ensure compliance with the SQSS. In
exceptional circumstances, the boundary between enabling works and wider works will extend
beyond the nearest MITS substation, such as in long radial parts of the network.
Generator connection categories:
Directly connected: These are generators that are directly connected to the
transmission system. They are modelled explicitly within connection studies.
Embedded: These generators are connected to the distribution systems and can
be large, medium or small in size:
Large embedded generators are explicitly modelled when carrying out
connection studies
Small embedded generators are represented by their equivalents at the
GSP for the purposes of determining loss of power infeed and
transmission capacity requirements.
Key assumptions:
The key modelling assumptions for the local transmission network relate to the
need to ensure that there is sufficient capacity to minimise constraints within a
local generation group in order to facilitate efficient market operation. Therefore, it
is necessary to model generation operating regimes representing credible
conditions which result in the transmission system being placed under greatest
stress, typically,, the following conditions are chosen to represent this condition:
Winter Peak conditions, here the plant dispatch will be greatest, resulting in
highest flows on the transmission circuits, however during winter conditions
the seasonal ratings will also be the highest, this can result in off peak
conditions being more onerous.
1Connect and Manage guidance document available online: http://www2.nationalgrid.com/WorkArea/DownloadAsset.aspx?id=5639
30 | P a g e
Summer minimum conditions, here the local and or total system demand
maybe at its lowest, whilst the generation dispatched on the GB system would
be less than that of a peak dispatch, at a local level, dependant on the plant
types the generation dispatch could be quite similar to that the lower demand
results in less demand being netted off thus resulting in higher loadings on
transmission assets, in addition during summer periods the transmission plant
seasonal ratings will also be at their lowest .
Alternative scenarios reflecting different loading conditions and seasonal
ratings may also be considered such as Spring/Autumn
Generation dispatch in the local area is set to represent credible operating
regimes of the generator types e.g. it is credible that thermal power stations
could all be running at full output in the same local generation group. It is also
possible that some or all of them could be off the grid. For loss of power
infeed calculations the generators that would be disconnected from the
system as a result of the secured event are set to their registered capacity
values.
The boundary of the local area is fluid as it depends on a number of factors such
as the topology of the network and the number, size and types of generators
involved within the area. The guiding principle is that the local network capacity
should not unduly restrict efficient market operation.
For the wider system, the MITS capacity requirements should be maintained as
per SQSS section 4 following the connection of the new generator. The capability
of the transmission network will be determined by considering a boundary or a
number of boundaries relevant to the generator under study. This assessment is
based on winter peak conditions as set out in SQSS section 4:
Winter circuit ratings applied to all transmission plant
Demand is set to Average Cold Spell (ACS) peak demand
Generation is dispatched according to technology specific scaling factors
specified in the SQSS.
Study input data:
Location of generator /connection point
Capacity of the generator in MW – Transmission Entry Capacity (TEC)
Technology, e.g. Thermal (nuclear, gas, etc.), Hydro, Wind, Marine, Pumped
storage, etc.
Machine and generator transformer parameters and associated circuit data
Connection date
Study model preparation:
For the local transmission capacity study, the GB network model for the relevant
year is prepared by representing all contracted generation in the area local to the
connection point for the current assessment. Where there are other generators
contracted to connect in the same area in later years, it may also be necessary to
prepare the network model a later year to ensure that other works already
31 | P a g e
identified for other generators are taken into account in determining the
transmission works required for the current connection assessment.
In order to ensure that the thermal requirements can be met, the network is set
up to represent conditions that ought to reasonably be foreseen during when the
asset ratings are lowest. Demand is set to its minimum value to allow the
identification and evaluation of any thermal capacity limitation on the local
transmission network assets under credible operating regimes for the generators
in the local area, including the one being studied.
For the MITS study, the network model is set according to criteria specified in
SQSS section4. This based around winter peak system conditions.
When generation and demand has been dispatched, the system model is
conditioned to ensure that it represents a credible operating point, i.e. voltages
are well within limits and generators are operating within their active and reactive
power ranges and with sufficient reactive margin on the network. Where stability
studies are to be performed, the dynamic models of all active plant will also need
to be setup and initialised.
Generation connection study
The following studies are performed for generator connections:
Loss of infeed: SQSS section 2.5 details the calculation method for loss of
infeed while section 2.6 specifies the relevant contingency criteria and limits
for assessment. If the loss of infeed limit is exceeded as a result of the
generator being assessed, works will be required to be specified to address
the issue.
Voltage, thermal, and stability: SQSS sections 2.8 - 2.14 specifies the
connection capacity requirements. SQSS section 4 specifies criteria for MITS
capacity requirements. The criteria cover the secured events and the voltage
and thermal requirements to be considered. They also require that there
should not be system instability as a result of any of the relevant secured
events. Where voltage, thermal or stability performance is determined to be
outside the SQSS limits, works will need to be identified to rectify any issues
identified.
Fault level: For all generator connections, fault level studies are carried out to
determine the correct switchgear short circuit rating and ensure that the
existing assets are adequately rated for the prospective fault level taking into
account the new generator. If fault level constraints are identified, works will
need to be identified to rectify any limitations.
4.1.2 Demand connections
Demand connection criteria are covered in SQSS section 3. In practice, there two main types
of demand connections from a transmission perspective. These are:
Directly connected demand user
Grid Supply Point
The connection analysis approach for these two from a transmission perspective is the same.
SQSS section3 is mainly concerned with the security of demand, considering both an
32 | P a g e
individual point (directly connected or GSP) and a group of demand points to form a demand
group.
Key assumptions:
The transmission network capacity is planned to meet the ACS peak demand
subject to loss of supply criteria in SQSS Section 3 Table 3.1.
Maintenance period demand security also considered.
Large embedded generation is expected to contribute to demand security subject
to criteria in SQSS Section 3 Table 3.2.
The study input data and network model setup are broadly the same. Specific contingencies
and performance limits are specified in SQSS Section3. Equally, criteria of SQSS Section 4
should continue to be met following a new demand connection and it may be necessary to
identify remedial works to restore compliance with SQSS section 4.
4.1.3 Overlap of criteria between generation and demand connections
It is common to have both generation and demand served by the same transmission network.
When assessing a generator or demand connection within such a composite group, both
SQSS section 2 and SQSS section 3 are applied such that the more onerous of the two will
dictate any works necessary to meet SQSS compliance.
4.1.4 Design variation
The deterministic criteria in the SQSS set the minimum requirements for transmission system
design. Design variations are however permitted subject to conditions specified in each of the
main sections of the SQSS. For example, a design variation for a generator connection can
be adopted to facilitate a customer choice connection design that is lower than the standard
planning level subject to meeting the conditions set out in SQSS sections 2.16 – 2.17. Equally,
for a design over the minimum deterministic standard specified in the SQSS, an economic
justification has to be provided in accordance with SQSS Appendix G.
4.2 Distribution customers
The following section gives a high-level description of the process followed when a customer raises a request for connection at the distribution network.
33 | P a g e
DNO Connections quotation process for High voltage and above.
Cus
tom
erC
onn
ecti
ons
Team
Plan
ner
(Ass
et
Man
agem
ent)
Des
ign
Rev
iew
/
Fina
nci
al s
ign
off
Net
wo
rk
Con
nec
tion
s D
esig
ner
Connection application made
Application processed and checked for minimum required
information
Technically assess the proposed connection e.g. P2/6 compliance,
Thermal, Voltage, and fault level studied
Design review and financial sign off
Quotation pack created and sent to customer
Quotation for connection received
High level connection designed
Customers submit connection applications to DNO Connection teams who are responsible for managing the communication with the customers. An application shall provide the DNO with at least the following information:
a. Location (address, OS grid reference etc.)
b. Size of generation or demand
c. Type of technology (or type of demand)
After receiving the application, the Networks Connections design team produces a high-level design of the customer’s connection and forwards to the planning team for a detailed assessment.
The planning team then conducts a number of checks and network studies to identify technically feasible points of connection (POCs) that satisfy the customer’s request. These may include:
• Network Assessment - Running Arrangements - Circuit complexity - P2/6 compliance - PLE (or equivalent) Analysis - Historical data - Line/cable and transformer ratings - Fault levels and switchgear rating - Automation - Protection settings
• Network studies (DigSilent, PSSE, IPSA etc.) - Voltage rise - Voltage step change - Load Flows (MW/MVAr) - Fault levels (three phase/single phase)
34 | P a g e
The aforementioned assessment/studies produce a number of options with associated costs and requirements, which are then provided back to the connections team. The options are described in detail, including the requirement for any additional equipment and/or potential network reinforcements. Some of the options studied may be rejected due to unreasonably high costs or technical limitations.
The customer will be presented with the most cost efficient POC only. The customer receives the offer and has a specific timeframe in which to accept or reject it.
4.3 Statement of Works Process (DNO/TSO Connections)
Customer Applies to DNO
DNO Connection
offer inc. req. for SoW
Customer Accepts Offer. DNO initiates SoW with SO
Revised BCA SO to DNO. Customer informed of
outcome
SoW Process SO/TO
Small and Medium embedded generators connecting to the distribution network do not require a direct agreement with National Grid as SO; instead they will have a connection agreement with the DNO. However, medium power stations can choose to have a BEGA or BELLA (direct agreement with NG). The definition of a Small generator varies between different parts of the network, as a consequence of differing transmission network topologies. The table below shows these differences:
Transmission Area
Size of Power
Station
SHE Transmission SP Transmission NGET
Small <10MW <30MW <50MW
Medium - - 50MW to <100MW
Large ≥10MW ≥30MW ≥100MW
When an embedded generator wishes to connect to the distribution network they will apply to the DNO, who must then determine whether they reasonably believe the new generator may have a significant system effect on the transmission system, and therefore be deemed Relevant. Where the generator is Relevant, the DNO will request that the SO conduct an assessment to determine the extent of the impact. This process is the Statement of Works (SoW) process as defined in CUSC Section 6.5.5.
Where the TO’s SoW studies indicate that there is an impact to the transmission system or works may be required, and the DG applicant wishes to proceed, the project moves to Project Progression and the DNO submits either a Confirmation of Project Progression or a Modification Application.
The SOW submission consists of the following data for each relevant generator:
Site name
Registered capacity
Voltage
Location (e.g. postcode)
Connection substation
Technology type
Connection status (connected, contracted or offered)
Control mode (voltage or power factor)
Fault infeed at BSP (I”, I’ and X/R)
Impedance between generator terminals and DNO network (R,X and C)
35 | P a g e
Minimum morning and afternoon load at BSP
A detailed map of the SOW process is included in Appendix C.1.
Work is currently underway to develop a revised version of the Statement of Works process.
Reference should be made to ENA Open Networks Project: WS1: Product 7 for further details.
The diagram in Appendix C.2 describes the Appendix G process, which was developed as
part of the ongoing work now covered under Product 7. Since this methodology is now
business as usual across a number of DNOs, it has been included in this report for
completeness.
36 | P a g e
5. The SO Process for Developing and Procuring Services
The SO utilises a range of services to support secure and economic system operation. Around 30 different types of service are currently used to provide reserve, frequency management, voltage management and other capability. These services are summarised in the table below.
Increasingly these services are being sourced from Distributed Energy Resources (DER) as well as from providers connected at transmission voltages. Engagement with DER providers and aggregators around service provision is being coordinated through the Power Responsive initiative. The Power Responsive column in the table indicates those services where DER participate.
At present, whole system network industry processes to develop and put in place services are not available. The current suite of SO services have either followed from mandatory requirements placed on generators or have been developed with providers to address system need as these have arisen.
Type of Service
Service
Power Responsive
2016 Report
Details on NG
Website Notes
Instructed Bids and Offers Balancing market
Frequency Mandatory Frequency Response Yes
Voltage Obligatory Reactive Power Services (ORPS)
Yes
Reserve
Short Term Operating Reserve (STOR) Included Yes
STOR Runway Included Yes
Enhanced Optional STOR Yes No longer used.
Fast Reserve (FR) Included Yes
Demand Turn-up (DTU) Included Yes
Low SEL / Super SEL Summary
BM Start-up Yes
Hot Standby Yes Bundled with BM start-
up.
Fast Start Large generators
Frequency
Firm Frequency Response (FFR) Included Yes
FFR Bridging Included Yes
Enhanced Frequency Response (EFR) Included Yes
Frequency Control by Dem M’ment (FCDM)
Included Yes
Voltage Enhanced Reactive Power Services (ERPS)
Yes
Pumped Storage
Spin Gen
Optional fast reserve services
Spin Gen LF
Pump Deload
Pump Deload LF
Spin Pump
Rapid Start
Synchronous Compensation
Security
Black Start Yes
Maximum Generation Yes
Intertrips Summary
Trip to House Load Large generators
37 | P a g e
Demand Side Balancing Reserve (DSBR)
Yes No longer used.
Supplemental Balancing Reserve (SBR) Yes No longer used.
Other Services
Other Services
Capacity Market / Warning
Market Trades
Cross-Border Trades Summary
Constraint contracts Summary
A high level process illustrating the typical approach to developing and procuring services is shown on the following figure. This process is indicative of how the Enhanced Frequency Response (EFR) service and other new services have been developed recently and involves a number of stages through to utilisation of the service:
• Steps 1 & 2 - Identifying the need and high level service characteristics.
• Steps 3 & 4 – Engaging with potential providers and establishing interest in the service.
• Steps 5 & 6 – Refining the service specification and carrying out pre-qualification.
• Steps 7 & 8 – Running the procurement process and assessing returns.
• Step 9 – Putting in place any contract requirements with providers.
• Step 10 – Providers putting in place the equipment to provide and control the service.
• Steps 11 & 12 - Setting up the systems to enable the service to be utilised together with
any aggregation or optimisation of service providers.
• Step 13 – Dispatch of the service to meet system needs.
• Steps 14 & 15 – Metering and settlement for the services provided.
• Step 16 – Any reporting association with the ongoing use of the service.
Alongside this process an Account Management team in SO will work with potential service providers and other stakeholders in developing and implementing the service.
Going forward, as part of its Future Role of System Operator programme, National Grid is assessing how it can simplify the range of services required in the areas of reserve, frequency management etc. It is consulting with service providers on how services might be best procured.
38 | P a g e
39 | P a g e
Appendices
40 | P a g e
A Operational Planning maps
A.1 Operational Planning SO/DNO Interface
Week 28SO provides draft outage plan in excel and pdf format via email
Week 30DNOs confirm receipt and inform
SO if unhappy with proposed outages
Week 8DNOs proposed outage plan to
SO in excel and pdf via email
Request for outages from DNO departments
DNO outage planning team processes requests and develops
a plan for the next 2-5 years
Long term planning team receives and processes
information
Week 13SO provides to DNOs a copy of
the week 8 information submitted by all DNOs
DNO outage planning team reviews
Week 28Proposed Year Ahead outage
plan in excel and pdf via email to DNOs
Year ahead planning team in Wokingham prepares outage
plan for year ahead
DNO outage planning team processes requests and develops
a plan for one year ahead.
Revision of outage plan based on DNOs comments
Week 34Draft National Electricity Transmission System outage plan covering period
Years 2 to 5 ahead. Excel and Pdf format via email
Week 32DNOs submit proposed outage plan to SO. Excel
and pdf format via email
Week 34SO notifies DNO of aspects that might affect
their network. SO provides a copy of the week 32 information to all other DNOs
Week 36DNO confirms and comments
Week 49 Final SO outage plan submitted via email in Excel
and pdf format
Request for outages from DNO departments
Long term planning team prepares outage plan for next 2-
5 years
Year ahead planning team draws up a revised year ahead outage
plan
DNO outage planning team reviews, comments and raises
concerns or issues
SO draws up final National Electricity Transmission System
outage plan covering Year 1
DNO outage planning team
41 | P a g e
Most up-to-date SO outage schedule uploaded on TOGA
SO notifies DNOs for any proposed changes to the latest
outage schedule
Notification to DNO via email DNOs review notification and raise any concerns
Potential concerns discussedShort term planning team
develops latest plan and updates TOGA
DNOs Outage Planning team advises TOGA regularly for the
most up-to-date SO outage schedule
Customer Network Data team submits the NG Power Factory
model to DNOs
SO model uploaded on an SFTP drive. PFD format
DNOs receive the model and merge it with their system
Outage Planning team prepares the Eight Weeks Ahead
Programme
EWAP submitted via email in excel and pdf format
Short Term Planning team
Commercial Optimisation Team sends declared generation
availability to DNOs for a few days ahead
Days ahead generation availability via email
Outage Planning
SO control room sends generation SYNC/DESYNC
schedule for next day to DNOs
Generation SYNC/DESYNC scehduled via fax
Outage Planning team
FOR COMMENT
42 | P a g e
A.2 DNO Operational Planning
DNO outage planning
Sho
rt T
erm
(~
2-3
we
ek
s)Lo
ng
term
(>
6m
on
ths)
Outage request
with:
ETR
Plant/Circuit
Date and time
Works
High level checks
Technical limitations
Load flows and plant
ratings
Fault levels
Outage plan clashes (NG
and DNO)
Network security
Is the outage feasible?
NO
High Level Study of
Available options
Load transfers
Generation Curtailment
(MW)
Network reconfiguration
Stand-by generation
Is the outage feasible?
NO
Discussions with requester
and proposal of other
options:
Alternative outage times
Works to be completed
YES
Record outage into the plan with high level details
YES
Review long term outage
plan
Detailed checks
Technical limitations
Load flows and plant ratings
Fault levels
Outage plan clashes (NG and
DNO)
Running arrangement
Network security
Is the outage feasible?
Detailed Study of Available
options
Load transfers
Generation Curtailment (MW)
Network reconfiguration
Stand-by generation
Alternative running
arrangement
Is the outage feasible?
Discussions with requester
and proposal of other
options:
Alternative outage times
Works to be completed
Communicate proposed
outage to all relevant
parties (internal, site
engineers, NG,
generators, customers)
Are there any objections?
Proceed with outage and
inform control engineers
NO NO
YES
Development of outage
details
Running arrangement
Load transfers
Generation curtailment
YES
NO
YES
Communicate proposed
outage to all relevant
parties (internal, site
engineers, NG,
generators, customers)
Are there any objections?
YES
NO
43 | P a g e
B Investment Planning maps
B.1 Week 24 submission
Historical data and forecasted data from PLEs
DNO Team prepares week 24 data submission
Week 6Proposals for Access Periods put forward by SO to
DNOs for discussion
Week 6-17Discussions between SO and DNOs to agree
Access Periods
Week 17Send details of agreed Access Periods, GB Max &
Min demand dates (past and forecast)
Week 42 SO sends transmission network to DNO
(equivalent)
DNO merges with distribution network model
Fault level and load flow studies
Schedule 5 Single Line Drawing Fault Infeeds Demand at GB max date Network alterations and
reconfigurations
Regional Development Plan and Load transfers
New connections (demand and generaration)
Schedule 10Total DNO daily demand (MW) profiles for: GB max GB min DNO max
Schedule 11GSP Demand Data (MW and MVAr) for: GB max GB min GSP peak Access Period peak
Schedule 12Demand Control Low Frequency Relay Settings Demand control by Voltage
reduction and/or demand disconnection
Emergency manual disconnection
Schedule 14Equipment data LV switchgear data LV substation infrastructure data Reactive compensation plant
Summing up demand at primaries and netting out generation
Schedule 11Small Embedded Power Station data per GSP: Registered capacity Type of generation Control mode Loss of mains protection
Table 11CTotal DNO:
Customers energy per class System Losses Embedded Generation
44 | P a g e
B.2 DNO Investment Planning
DNO Investment Planning
Del
iver
yFo
reca
stin
gA
nal
ysis
Op
tio
ne
eri
ng
Design and Operation Limitations Outages Fault Levels Security of Supply Strategic developments
Asset Health: Health Indices End of Life Mandate for
replacement/retrofit
Planning teams analyse existing network: Load flow and fault level studies using PowerFactorty, PSSE or equivalent software Security of Supply (P2 standard) Outage management Contingency Analysis Business Plan targets Other regulatory requirements
Connection Requests: Point of Connection Technology Size
Are there any constraints (current
or future)?
Planning Load Estimates: Maximum Demand Firm Capacity Load Indices Load transfers
Modelling of Constraint
YES
Analysis and Optioneering: Network reconfiguration Reinforcement/Retrofit Load Transfer ANM DSR
Modelling of options: Costs High Level works Wider benefits
Select least regrets and most cost efficient solution
Design and Development of
the solution
Delivery of solution: Procurement Commissioning Tests Hand over to Operations
START
END
NO
45 | P a g e
B.3 TSO Investment Planning
TSO Investment Planning
De
live
ry
Exe
cute
& C
lose
NO
A P
roce
ssO
pti
on
ee
rin
g,
De
sign
& A
pp
rova
lA
nal
yse
Re
qu
ire
me
nts
& I
de
nti
fy O
pti
on
sIn
vest
me
nt
Dri
vers
,
Bu
sin
ess
Pla
n E
ntr
y
Review Investment Drivers
Infrastructure Requirements(Other thermal, vol tage work)- Grid Code Data- Future Energy Scenarios- ETYS Boundary Req'ts- Bus iness Plan entry
Connection Request(eg Generation Development)- Customer data- Size, technology, timescales- Location- Bus iness Plan entry
Asset Replacement
(eg Primary Equipment)- Condition information- Cri tica lity- Customer impacts- Bus iness Plan entry
Analysis & Option Identification- SO & TO Development Teams- Power System Analysis(thermal, voltage, s tability etc)
- PowerFactory & Economic Tools- Securi ty (NETS SQSS, P2)- Outage management- Regulatory constraints
Analysis & Option Identification- SO & TO Development Teams- Power System Analysis(thermal, voltage, s tability etc)
- Securi ty (NETS SQSS, P2)- Programme, Outages - Indicative Charges- Interactivi ty
Analysis & Option Identification- Largely TO Development- Condition Information- Cri tica lity- Ongoing requirements - Customer, wider impacts- Overlaps with other work
Is investment to be taken
forward?
No Yes
Assess Options- Cost
- Risks- Programme
Select Preferred Option & Confirm Requirements
Infrastructure Reqts(Boundary Capacity)Networks Options Assessment (NOA)- GB Models- SO confi rms need for boundary capability
Des ign & Develop Solution.- Fi rm Up Scheme Req'ts
(SRD for Resources & Outages)- Execution Plan- Value checks & affordability
Approval of Investment
Issue
Req'ts
Proposed Options- TO Tx options- Other options (non-build)- Costs
Boundary Capability Assessment for Options
Cost Benefit Analysis of Options- BID3 Model
Select Preferred Options
Assess Sui tability for Competition
Del ivery Vehicle- Issue enquiry- Evaluate proposals
- Place contract
Deta iled Design& Assurance
Bui ld AssetsCommission Assets
Accept Assets- Data- Outstanding
Works
Closure- Data- Costs
Del ivery
Determine how to take forward NOA recommendation.
Non-investment option i f appropriate (eg customer offer without works).
Mapping current SO, TO, DNO Processes
46 | P a g e
B.4 NOA Process
Taken from NOA Report Methodology, Draft 3, 12th May 2017
NOA High Level Process (Draft)
Mapping current SO, TO, DNO Processes
47 | P a g e
NOA Capability Requirements & Transmission Options (Draft)
Mapping current SO, TO, DNO Processes
48 | P a g e
NOA Boundary Capability Assessment (Draft)
Mapping current SO, TO, DNO Processes
49 | P a g e
NOA Cost Benefit Assessment & Preferred Option Selection (Draft)
Mapping current SO, TO, DNO Processes
50 | P a g e
NOA Report Drafting and Publication
Mapping current SO, TO, DNO Processes
51 | P a g e
C Customer Connection Maps
C.1 Statement of Works process
DG CUSTOMER APPLIES TO DNO
FOR CONNECTION
DNO REQUIRED TO MAKE OFFER WITHIN
70 DAYS
DOES THE CONNECTION BREACH 50MW* CUMULATIVE
OR IS IT 50MW
NONOT SUBJECT TO
SOW MAKE OFFER
MAKE OFFER SUBJECT TO SOW
SINGLE OR BULK SOW SUBMISSION
MADE TO SO
SO PROVIDES TO WITH DATA
TO FEEDS BACK TO SO
IS THERE AN IMPACT ON THE
NETS
SO FEEDS BACK TO DNO
INFORM CUSTOMER NO IMPACT ON THE
NETS
PROJECT PROGRESSION
REQUIRED
INFORM CUSTOMER OF NETS IMPACT
CUSTOMER DECIDES WHETHER TO MOVE
FORWARD
CUSTOMER DECIDES WHETHER TO MOVE
FORWARD
TO UNDERTAKE DETAILED STUDIES
AND PROVIDES DETAILS OF WORKS, TIMESCALES, COSTS,
ETC.
DNO PROVIDES INFORMATION TO
DG CUSTOMER
CUSTOMER DECIDES WHETHER TO MOVE
FORWARD
IS THERE SUFFICIENT DETAILEDSO/TO INFORMATION
AVAILABLE
NO
YES
YES
NO YES NO
*DNO DEPENDENT
CUSTOMER ACCEPTS OFFER (OR
PAYS FOR SOW)
**CUSTOMER DRIVEN
YES**
Mapping current SO, TO, DNO Processes
52 | P a g e
C.2 Appendix G process (England and Wales)
Customer applies
Offer made against Materiality Headroom
TSO approves changes and contractualises DER
NG provides revised BCA inc. Appendix G & Materiality Headroom
DNO National Grid
Customer accepts & pays
Appendix G updated/monthly process
Appendix G re-issued
Materiality Limit updated
Identifies changes to technical reqs (if required)
Appendix G re-issued
Is materiality headroom
reachedNo
TO runs studies
DNO raises SoW/Mod AppYes
Records updated
DNO provides GSP technical data via SoW/Mod App
DER contracted