EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

21
EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT Manley Higgins Project Manager System Operations Pepco Holdings Inc. September 8, 2008

description

EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT. Manley Higgins Project Manager System Operations Pepco Holdings Inc. September 8, 2008. Project Goals. Implement state of the art technology EMS for all of PHI operating regions - PowerPoint PPT Presentation

Transcript of EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

Page 1: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

EMS User Group Conference – 2008

PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

Manley Higgins Project ManagerSystem OperationsPepco Holdings Inc.

September 8, 2008

Page 2: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

Project Goals

Implement state of the art technology EMS for all of PHI operating regions

Maintain reliability of the PHI power system and meet current and future regulatory requirements

Minimize System Customs and procure a baseline system to make it easier to support

Page 3: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

Project Justification

NERC CIP Compliance for Pepco by December 2009– Existing Pepco system was older vintage EMS and would

have been difficult and expensive to make compliant Common EMS platform at Pepco, Atlantic City Electric and

Delmarva Power will better support PHI Blueprint for the Future initiatives

Provide the opportunity to leverage PHI’s collective EMS knowledge and experience across the company, and allow improved decision making.

Improved allocation of support and training resources across all regions of PHI

Need to upgrade or replace Pepco’s EMS to provide long term maintenance and reliability

– Existing system was highly customized and expensive to maintain due to it’s age

Page 4: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

Project Core Team

Established a cross regional team representative of all of PHIPEPCO ACE/DPL KEMA

Manley Higgins Linda Stevens Mark Bruen

Brian Chabot Phil Vavala Joe Moran

Bob Krug Ken West

Bill Disney Donna Hare

Chris Koch Ray Cichocki

George Menefee Diane Burns

Pam King Monte Bellon

Sunil Pancholi - Liaison to Business Transformation Team

Karen Lefkowitz – Executive Sponsor

Michael O’Grady and Vic Davis – Sponsors and Support Managers

Page 5: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

Project Began Early Spring 2007

PHI Team formed Solicited bids from two vendors

– Decided to request bids from incumbent vendors only Technical, Business and Commercial evaluations

performed Site visits conducted by PHI Team Team Performed Qualitative Risk Analysis of all

offerings Vendor Selected in December 2007

Page 6: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

Process

Statement of Work completed December 2007

Purchase Order issued February 2008 Project Implementation Work began

immediately Contract consisted of two purchase orders

due to Pepco lease constraints

Page 7: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

Overall Project Plan

Phased Project Approach – Phase 1 for Pepco– Phase 2 for ACE/DPL

Common Software Platform for both System Common System Design and Requirements

– Ensures that both systems have the same version software and hardware

Utilize PHI Expertise with the incumbent system during the design and implementation process

Page 8: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

Major System Capability

The EMS– Consists of redundant systems

The BCS– Includes redundant systems

QAS – NERC requirement for separate system for test board

PDS DTS

Page 9: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

System Functionality

Basic EMS capability including SCADA, power applications, DTS, and custom applications such as DVD & RLBVC

Interface with PHI’s ISO (i.e. PJM) Interface with the OMS Support future DA programs

Page 10: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

EMS Implementation Project Status

The PDS hardware for Pepco’s EMS was received the week of May 28th. The software was installed on the system prior to shipment.

Vendor resolved performance issues with the PDS affecting the PHI Database, Display, and Standards work.

The PDS has been installed and operational. The initial Pepco database build has been completed and was

loaded on the PDS in June. The prototype display building effort has begun on the Pepco

PDS with assistance from ACE/DPL. Vendor is assisting with display design and build.

The ACE/DPL PDS has been staged at the vendor this month and is scheduled for delivery in October.

Page 11: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

PHI/Pepco Project Status – September 2008

Hardware Staging complete for Pepco EMS, BCS, QAS and DTS.

ACE/DPL PDS is being configured and tested. Building initial PHI Power Systems Applications database. PHI validating converted SCADA database at site. PHI reviewing Power Systems Custom Designs and

SCADA Custom Requirements. Design review nearing completion.

On-site Database and Display training has been conducted.

Page 12: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

Upcoming Activities

Complete Pepco PSA database build. Pepco detailed database verification. Load ACE/DPL converted database and

checkout PDS. Coding of Power Systems customs. Implement Custom Designs. Evaluating and selecting security

configuration.

Page 13: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

Project Milestones - PEPCO

Milestones Contract Completion Date

Current Completion Date

1 Contract Executed 01 Feb 2008 01 Feb 2008

2 Delivery & Installation of PDS 13 May 2008 20 May 2008

3 Submittal of Requirements Specifications

04 Apr 2008 28 Jul 2008

4 System Hardware Staged. Design Approvals.

18 Apr 2008 29 Aug 2008

5 Approval of Test Plans 24 Oct 2008 05 Dec 2008

6 Completion of FAT 05 May 2009 11 Jun 2009

7 System Shipment 30 Jun 2009 30 Jul 2009

8 Completion of SAT 30 Jul 2009 27 Aug 2009

9 System Cutover/Acceptance 16 Dec 09 22 Jan 10

Page 14: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

Project Milestones – ACE/DPL

Milestones ContractCompletion

Date

CurrentCompletion

Date

1Delivery & Installation of PDS 15 Jul 2008 15 Jul 2008

2 System Hardware Staged 15 Sep 2009 08 Oct 2009

3Completion of Integration Testing 24 Nov 2009 21 Dec 2009

4 Approval of Test Plans 25 Nov 2009 22 Dec 2009

5 Completion of FAT 12 Mar 2010 06 Apr 2010

6 System Shipment 03 Jun 2010 28 Jun 2010

7 Completion of SAT 01 Jul 2010 26 Jul 2010

8 System Acceptance 16 Dec 2010 10 Jan 2011

Page 15: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

In-Service Dates

Pepco In-Service Date is– January 2009

ACE/DPL In-Service Date is– January 2011

Page 16: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

Challenges Remain

Database checkout and point - to - point testing to minimize schedule and maintain safety and security

Display Building – Lots of work

Operator Training on Change Management Complete System Testing

– More work to be done

Page 17: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

ON-Going EMS Integration Program Initiatives

Risk Mitigation Resource Acquisition for PHI tasks PHI Team Building with Pepco and ACE/DPL

– Integration of PHI support and operations organizations

Page 18: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

One System – One Process

Complete Standards for System Displays and Symbologies for PHI EMS by December 2008

Other Efforts from EMS Project Investigate further integration of regional support teams Assess operational/business processes for additional

areas of commonality and potential effectiveness Develop change management program to ensure

success of common platform initiative

Page 19: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

Display Standards and Conventions Effort

The effort to determine display standards and conventions (symbols, colors, layout, etc.) for all of PHI EMS’s is progressing.

The initial draft agreement that is going to be prototyped for display types, display guidelines, substation one lines and symbology has been completed.

Initial development of the prototype displays and screens is in progress.

A draft summary of the Display Symbology and Standards Workshops has been completed and is being reviewed by the team.

Finalization of the agreements and prototypes should occur after review of the results of the prototyping effort.

Resource availability and stability issues with the PDS has affected progress on the display prototyping and symbology effort.

Page 20: EMS User Group Conference – 2008 PHI EMS MIGRATION TO COMMON PLATFORM PROJECT

Lessons Learned (so far!!)

Advanced work with Procurement Group to Ensure quick transition to contract

Never trust the EMS salesman for schedule related issues

Database Build and Conversion is never as simple as the vendor states

– Be prepared to do it in house Display Building is a Major Effort when changing

vendors Dedicated Resources are a must for both Vendor

and Customer