EMIS 8373: Integer Programming “Easy” Integer Programming Problems: Network Flow Problems...
-
Upload
angel-merritt -
Category
Documents
-
view
222 -
download
0
Transcript of EMIS 8373: Integer Programming “Easy” Integer Programming Problems: Network Flow Problems...
EMIS 8373: Integer Programming
“Easy” Integer Programming Problems: Network Flow Problems
updated 11 February 2007
slide 2
The Minimum Cost Network Flow Problem (MCNFP)
• Extremely useful model in OR & EM• Important Special Cases of the MCNFP
– Transportation and Assignment Problems– Maximum Flow Problem– Minimum Cut Problem– Shortest Path Problem
• Network Structure– BFS’s for MCNFP LP’s have integer values !!!– Problems can be formulated graphically
slide 3
Elements of the MCNFP
• Defined on a network G = (N,A)
• N is a set of n nodes: {1, 2, …, n}– Each node i has an associated value b(i)
• b(i) < 0 => node i is a demand node with a demand for –b(i) units of some commodity
• b(i) = 0 => node i is a transshipment node
• b(i) > 0 => node i is a supply node with a supply of b(i) units
slide 4
Elements of the MNCFP
• A is a set of arcs that carry flow– Decision variable xij determines the units of
flow on arc (i,j)
– The arc (i,j) from node i to node j has• cost cij per unit of flow on arc (i,j)
• upper bound on flow of uij (capacity)
• lower bound on flow of ij (usually 0)
slide 5
Example MCNFP
• N = {1, 2, 3, 4}b(1) = 5, b(2) = -2, b(3) = 0, b(4) = -3
• A ={(1,2), (1,3), (2,3), (2,4), (3,4)}c12 = 3, c13 = 2, c23 =1, c24 = 4, c34 = 4
12 = 2, 13 = 0, 23 = 0, 24 = 1, 34 = 0
u12 = 5, u13 = 2, u23 = 2, u24 = 3, u34 = 3
slide 6
Graphical Network Flow Formulation
b(j)b(i)
i j(cij, ij, uij)
arc (i,j)
slide 7
Example MCNFP
5 1 4(1, 0,2)
3
2
0
-3
-2
(2, 0,2)
(4, 1,3)
(4, 0,3)
(3, 2,5)
slide 8
Requirements for a Feasible Flow
• Flow on all arcs is within the allowable bounds: ij xij uij for all arcs (i,j)
• Flow is balanced at all nodes:flow out of node i - flow into node i = b(i)
• MCNFP: find a minimum-cost feasible flow
slide 9
LP Formulation of MCNFP
Aji
Ni
uxbxx
xc
ijijij
iAijj
jiAjij
ij
Ajiijij
),(
st
min
),(:),(:
),(
slide 10
LP for Example MCNFP
Min 3X12 + 2 X13 + X23 + 4 X24 + 4 X34 s.t. X12 + X13 = 5 {Node 1} X23 + X24 – X12 = -2 {Node 2}
X34 – X13 - X23 = 0 {Node 3} – X24 - X34 = -3 {Node 4}
2 X12 5, 0 X13 2, 0 X23 2, 1 X24 3,
0 X34 3,
slide 11
Example Feasible Solution
5 1 4(1, 0,2)
3
2
0
-3
-2
(2, 0,2)
(4, 1,3)
(4, 0,3)
(3, 2,5)
5 3
000
Cost = 15 + 12 = 27
slide 12
Optimal Solution for Example
5 1 4(1, 0,2)
3
2
0
-3
-2
(2, 0,2)
(4, 1,3)
(4, 0,3)
(3, 2,5)
3 1
022
Cost = 25
Transportation Problems
slide 14
Graphical Network Flow Formulation
b(j)b(i)
i j(cij, uij)
arc (i,j)
ij=0
slide 15
C
W
+4
+1
+2
Supply Nodes
I
S
G
Demand Nodes
-1
-1
-1
-1
A
F
(13, 1)
(35, 1)
(9, 1)
(42, 1)
Dummy Node-3
(0,4)
(0,2)
(0,1)
D
slide 16Dummy Node -3
C
W
+4
+1
+2
Supply Nodes
I
S
G
Demand Nodes
-1
-1
-1
-1
A
F
slide 17
Shortest Path Problems
• Defined on a Network with two special nodes: s and t
• A path from s to t is an alternating sequence of nodes and arcs starting at s and ending at t:
s,(s,n1),n1,(n1,n2),…,(ni,nj),nj,(nj,t),t
• Find a minimum-cost path from s to t
slide 18
Shortest Path Example
1 2 3
4
5 10
7 71
s t
1,(1,2),2,(2,3),3 Length = 151,(1,2),2,(2,4),4,(4,3) Length = 131,(1,4),4,(4,3),3 Length = 14
slide 19
MCNFP Formulation of Shortest Path Problems
• Source node s has a supply of 1
• Sink node t has a demand of 1
• All other nodes are transshipment nodes
• Each arc has capacity 1
• Tracing the unit of flow from s to t gives a path from s to t
slide 20
Shortest Path as MCNFP
1 -11 2 3
4
(5,1,0) (10,0,1)
11 2 3
4
1 0
10
0
0
(7,0,1)(7,0,1)
(1,0,1)
slide 21
Shortest Path Example• In a rural area of Texas, there are six farms connected by
small roads. The distances in miles between the farms are given in the following table.
• What is the minimum distance to get from Farm 1 to Farm 6?
From Farm To Farm Distance 1 2 81 3 102 3 42 4 92 5 53 4 63 5 24 5 34 6 65 6 5
slide 22
Graphical Network Flow Formulation
b(j)b(i)
i j
ij= 0, uij=1
arc (i,j)
(cij)
slide 23
Formulation as Shortest Path
s t
1
2 4
3
9
10
56
6
8 45
5
4
2
3
1 -1
0 0
00
slide 24
LP Formulation
10
1
0
0
0
0
1st
min
5646
45352556
34244546
23133534
12252423
1312
5646453534
2524231312
54326594108
xxx
xxxxxxxxxxxxxxxx
xxxxxxxxxxxx
ij
slide 25
Maximum Flow Problems
• Defined on a network– Source Node s– Sink node t– All other nodes are transshipment Nodes– Arcs have capacities, but no costs
• Maximize the total flow from s to t
slide 26
Example: Rerouting Airline Passengers
Due to a mechanical problem, Fly-By-Night Airlines had to cancel flight 162 - its only non-stop flight from San Francisco to New York.
Formulate a maximum flow problem to reroute as many passengers as possible from San Francisco to New York.
slide 27
Data for Fly-by-Night Example
Flight From To Number of seats 160 San Francisco Denver 5 115 San Francisco Houston 6 153 Denver Atlanta 4 102 Denver Chicago 2 170 Houston Atlanta 5 150 Atlanta New York 7 180 Chicago New York 4
slide 28
Network Representation
s t
SF
D C
H
2
6
A5
NY
5 4
4
7
slide 29
Graphical Network Flow Formulation
b(j)b(i)
i j(uij)
arc (i,j)
ij =0cij =0
slide 30
MCNF Formulation of Maximum Flow Problems
1. Let arc cost = 0 for all arcs
2. Add an arc from t to s– Give this arc a cost of –1 and infinite
capacity
3. All nodes are transshipment nodes
4. Circulation Problem
slide 31
Formulation as MCNFP
SF
D C
H
(0,0,2)
(0,0,6)
A(0,0,5)
NY
(0,0,5) (0,0,4)
(0,0,4)
(0,0,7)
(-1,0,)
slide 32
MCNFP Solution
SF
D C
H
(0,0,2)
(0,0,6)
A(0,0,5)
NY
(0,0,5) (0,0,4)
(0,0,4)
(0,0,7)
9
4
22
5 75
2
(-1,0,)
slide 33
LP Formulation
xxxxxxxx
xxxxxx
xxxxx
xxxxx
x
SFNYNYC
NYAAHAD
CDHSFDSF
NYASFNY NYC
ADAHNYA
CDNYC
DSFADCD
HSFAH
SFNYHSFDSF
SFNY
,.
.,,
,..
,, ,
,,,
,,
,,,
,,
,,,
,
040
70,50,40
20,60,50
0
0
0
0
0
0st
min
slide 34
NSC Example
Month Demand Production Cost1 2,400 $7,4002 2,200 $7,5003 2,700 $7,6004 2,500 $7,800
• Max production per month = 4,000 tons• Inventory holding cost = $120/ton/month• Initial inventory = 1,000 tons• Final inventory = 1,500 tons
slide 35
Network Flow Formulation
d1
d2
d3
d4
p1
p2
p3
p4
4000
4000
4000
4000
-2400
-2200
-2700
-2500
I4 -1500
I0 1000
d0 -5700
I1
I2
I3
slide 36
Arc Parameters
• All arcs have ij = 0 and uij =
• Arcs (pi, d0) have cost 0.
• Arcs (Ii, di+1) and (Ii,Ii+1) have cost 120.Arc Cost(p1,d1) 7400(p2,d2) 7500(p3,d3) 7600(p4,d4) 7800
slide 37
Backorder Cost of $200/unit/month
d1
d2
d3
d4
p1
p2
p3
p4
4000
4000
4000
4000
-2400
-2200
-2700
-2500
I4 -1500
I0 1000
d0 -5700
I1
I2
I3
slide 38
Parameters for Backorder Arcs
• All arcs have ij = 0 and uij =
Arc Cost(p2,d1) 7700(p3,d2) 7800(p3,d1) 8000(p4,d3) 8000(p4,d2) 8200(p4,d1) 8400