EMBA 5403 Costing Systems
-
Upload
ramakrishnarao -
Category
Documents
-
view
227 -
download
0
Transcript of EMBA 5403 Costing Systems
-
8/12/2019 EMBA 5403 Costing Systems
1/37
Costing Systems
EMBA 5403
Fall 2010
-
8/12/2019 EMBA 5403 Costing Systems
2/37
Fall 2010 Mugan 2/37
Available costing systems
Absorption costing
Actual Costing
Normal Costing
Standard Costing
Variable costing
Actual Costing
Normal Costing
Standard Costing
-
8/12/2019 EMBA 5403 Costing Systems
3/37
Fall 2010 Mugan 3/37
Costing systems
Costcomponent
Actual Normal Standard
material Actual Actual Standard
labor cost Actual Actual Standard
ManufacturingOverhead-
Variable
Actual Applied Standard
ManufacturingOverhead-Fixed
Actual Applied StandardApplied
-
8/12/2019 EMBA 5403 Costing Systems
4/37
Fall 2010 Mugan 4/37
Variance
Differences between the costsaccording to the costing system usedand actual amounts
Actual amounts are reflected in thefinancial statements
-
8/12/2019 EMBA 5403 Costing Systems
5/37
-
8/12/2019 EMBA 5403 Costing Systems
6/37
Fall 2010 Mugan 6/37
Product Costing Proceduresin Organizations
ProcessCosting
Job-orderCosting
Distinct jobs or batches of units.Costs accumulated separately by job.
Typical job order cost applications:Special-order printingBuilding construction
Also used in service industryHospitals
Law firms
-
8/12/2019 EMBA 5403 Costing Systems
7/37
Fall 2010 Mugan 7/37
Product Costing Proceduresin Organizations
ProcessCosting
Job-orderCosting
Typical process cost applications:
Petrochemical refinery
Paint manufacturer
Paper mill
-
8/12/2019 EMBA 5403 Costing Systems
8/37
Fall 2010 Mugan 8/37
Job-Order Costing
The
Job
Directlabor
Direct
materials
Manufacturing
overhead (MOVH)
Applied (added) to
eachjob using a
predeterminedrate
-
8/12/2019 EMBA 5403 Costing Systems
9/37
Fall 2010 Mugan 9/37
Job-Order Costing
Part of thejob cost
MaterialsRequisition and
Time tickets
Directmaterial
sand
labor
Indirectmaterialsand labor
ManufacturingOverheadControlAccount
Raw materialscould be used asdirect or indirect
product cost.
An employeestime may be eitherdirect or indirect.
-
8/12/2019 EMBA 5403 Costing Systems
10/37
Fall 2010 Mugan 10/37
Job-Order Costing
wages
Job-OrderCost
Sheets
Materialusage
OtherActual OHCharges
Indirect
Materials
Indirect
Labor
Applied
Overhead
ManufacturingOverheadControl
Account
-
8/12/2019 EMBA 5403 Costing Systems
11/37
Fall 2010 Mugan 11/37
Job-Order Cost Sheet
XYZ Job-Order Cost Sheet
Job Number A - 143 Date Initiated 17 September 2008
Date Completed
Department A4 Units Completed 2
Item Steel water tank
Direct Materials Direct Labor Manufacturing Overhead
Req. No. Amount Ticket Hours Amount Hours Rate Amount
MR 1041 TL 1200 20 8 TL 160 8 TL 6 TL 48
Cost Summary Units Shipped
Direct Materials TL 1200 Date Number Balance
Direct Labor TL 160
Manufacturing Overhead TL 48
Total Cost 1408
Unit Cost 704 11/17/08 1 1
17-Nov-08
-
8/12/2019 EMBA 5403 Costing Systems
12/37
Fall 2010 Mugan 12/37
Job-Order System Cost Flows
DirectLabor
Mfg. Overhead
Salaries andWages Payable
Work-in-Process(Job Cost Sheet)
DirectMaterials
OverheadApplied to
Work inProcess
IndirectLabor
DirectLabor
OverheadApplied
IndirectLabor
IndirectMaterials
Actual Appl ied If actual and appliedmanufacturing overheadare not equal, a year-endadjustment is required.
-
8/12/2019 EMBA 5403 Costing Systems
13/37
Fall 2010 Mugan 13/37
Job-Order System Cost Flows
Cost of
GoodsMfd.
Finished Goods
Cost ofGoods
Sold
Cost of
GoodsMfd.
Cost of Goods Sold
Cost of
GoodsSold
Work-in-Process(Job Cost Sheet)
DirectMaterials
DirectLabor
OverheadApplied
-
8/12/2019 EMBA 5403 Costing Systems
14/37
Fall 2010 Mugan 14/37
Allocation Process
Define the cost objects.
Accumulate indirect costs in cost pools.
Choose an allocation base.Estimate an application rate.
Allocate indirect costs based on use of
the allocation base
-
8/12/2019 EMBA 5403 Costing Systems
15/37
Fall 2010 Mugan 15/37
Over- and UnderabsorbedOverhead
Overabsorbed overhead
Underabsorbed overhead
Applied
Overhead
Costs
Actual
Overhead
Costs
-
8/12/2019 EMBA 5403 Costing Systems
16/37
Fall 2010 Mugan 16/37
Over- and UnderabsorbedOverhead
SOLUTIONApplied Overhead = POHR Actual Direct Labor Hours
Applied Overhead = TL 6.00 per DLH 100,000 DLH = TL 600,000
XYZsactualoverhead for the year was TL650,000and a total of 100,000 direct labor hours were
worked.
Using XYZs predetermined overhead rate ofTL 6.00 per direct labor hour, how much overhead
was appliedto XYZs jobs during the year?
-
8/12/2019 EMBA 5403 Costing Systems
17/37
Fall 2010 Mugan 17/37
Accounting for Over- andUnderabsorbed Overhead
Three basic approaches
Prorate among work-in-process,finished goods, and cost of goods
sold.
Adjust cost of goods sold.
Recalculate the application rate and
apply to all the jobs during theperiod.
-
8/12/2019 EMBA 5403 Costing Systems
18/37
Fall 2010 Mugan 18/37
Accounting for Over- andUnderabsorbed Overhead
Alternative 1 Alternative 2
If Manufacturing Close to Cost
Overhead is . . . of Goods Sold Allocation
UNDERABSORBED INCREASE INCREASE
Cost of Goods Sold Work-in-Process
(Applied OH is less Finished Goods
than actual OH) Cost of Goods Sold
OVERABSORBED DECREASE DECREASE
Cost of Goods Sold Work-in-Process
(Applied OH is greater Finished Goods
than actual OH) Cost of Goods Sold
-
8/12/2019 EMBA 5403 Costing Systems
19/37
Fall 2010 Mugan 19/37
Allocation Base
Products
ApplicationRate
If overheadcosts are
accumulated ina single costpool and
allocated usinga single
allocation base.
Single OverheadCost Pool
-
8/12/2019 EMBA 5403 Costing Systems
20/37
Fall 2010 Mugan 20/37
Many companies use Activity Based Costing where multiple costpools and a different allocation base for each cost pool.
Products
Application
Rate A
OverheadCost Pool
A
OverheadCost Pool
B
OverheadCost Pool
C
Application
Rate B
Application
Rate C
Multiple Allocation Bases
-
8/12/2019 EMBA 5403 Costing Systems
21/37
Fall 2010 Mugan 21/37
Improves planning and control.
Activity Based Costing (ABC)is onemethod of using multiple allocationbases.
ABC and Multiple AllocationBases
-
8/12/2019 EMBA 5403 Costing Systems
22/37
Fall 2010 Mugan 22/37
Multistage Allocation Processes
OverheadCost Pool 1
OverheadCost Pool 2
OverheadCost Pool 3
OverheadCost Pool 4
Separate
Application Rates
Department A Department CDepartment B
Products
Dept. ApplicationRates
Dept. ApplicationRates
-
8/12/2019 EMBA 5403 Costing Systems
23/37
Fall 2010 Mugan 23/37
Process Costing
Identical units of product areproduced
in a continuous flow through a seriesof manufacturing steps orprocesses.
Costs are assigned to completed units
transferred out of the process and toincompleteunits remaining in the
process.
-
8/12/2019 EMBA 5403 Costing Systems
24/37
Fall 2010 Mugan 24/37
Costs are accumulated for a period oftimefor products in work-in-process
inventory.
Equivalent unitsis a conceptexpressing these partially completed
products as a smaller number of
fully completed products.
Process Costing
-
8/12/2019 EMBA 5403 Costing Systems
25/37
Fall 2010 Mugan 25/37
Two one-half completed products areequivalent to one completed product.
+ =
So, 8,000 units 70 percent completeare equivalentto 5,600 complete units.
Equivalent Units
-
8/12/2019 EMBA 5403 Costing Systems
26/37
Fall 2010 Mugan 26/37
For the current period, Ames started 15,000units and completed 10,000 units, leaving
5,000 units in process 30 percent complete.How many equivalent units of production did
Ames have for the period?
a. 10,000
b. 11,500
c. 13,500
d. 15,000
Equivalent Units Question
-
8/12/2019 EMBA 5403 Costing Systems
27/37
Fall 2010 Mugan 27/37
For the current period, Ames started 15,000units and completed 10,000 units, leaving
5,000 units in process 30 percent complete.How many equivalent units of production did
Ames have for the period?
a. 10,000
b. 11,500
c. 13,500
d. 15,000
10,000 units + (5,000 units .30)= 11,500 equivalent units
Equivalent Units Question
-
8/12/2019 EMBA 5403 Costing Systems
28/37
Fall 2010 Mugan 28/37
Calculating and UsingEquivalent Units of Production
To calculate the cost perequivalent unit for the period:
Cost perequivalent
unit
=Costs for the period
Equivalent units for the period
-
8/12/2019 EMBA 5403 Costing Systems
29/37
Fall 2010 Mugan 29/37
Now assume that Ames incurred $27,600 inproduction costs for the 11,500 equivalent
units. What was Ames average cost perequivalent unit for the period?
a. $1.84
b. $2.40c. $2.76
d. $2.90
Equivalent Units Question
-
8/12/2019 EMBA 5403 Costing Systems
30/37
Fall 2010 Mugan 30/37
Now assume that Ames incurred $27,600 inproduction costs for the 11,500 equivalent
units. What was Ames average cost perequivalent unit for the period?
a. $1.84
b. $2.40c. $2.76
d. $2.90
$27,600 11,500 equivalent units
= $2.40 per equivalent unit
Equivalent Units Question
-
8/12/2019 EMBA 5403 Costing Systems
31/37
Fall 2010 Mugan 31/37
What portion of the $27,600 in productioncosts was assigned to work-in-process
inventory and what amount was assignedto completed units for the period?
a. $0 and $27,600
b. $7,600 and $20,000c. $3,600 and $24,000
d. $12,000 and $15,600
Equivalent Units Question
-
8/12/2019 EMBA 5403 Costing Systems
32/37
Fall 2010 Mugan 32/37
What portion of the $27,600 in productioncosts was assigned to work-in-process
inventory and what amount was assignedto completed units for the period?
a. $0 and $27,600
b. $7,600 and $20,000c. $3,600 and $24,000
d. $12,000 and $15,600
Work-in-process:
1,500 equivalent units @ $2.40 = $3,600
Completed units:10,000 equivalent units @ $2.40 = $24,000
Equivalent Units Question
-
8/12/2019 EMBA 5403 Costing Systems
33/37
Fall 2010 Mugan 33/37
Equivalent Units
When there are partially completed unitsin beginning inventory, work efforts
during the period can be categorized asfollows:
Work to complete beginning work-in-process
Work on units started and completed duringthe period
Work on units in ending work-in-process
-
8/12/2019 EMBA 5403 Costing Systems
34/37
Fall 2010 Mugan 34/37
Equivalent Units - Example
ACE started June with 250 partially completedunits in work-in-process (30% complete).
During June, ACE completed the units in work-
in-process and started an additional 1,200units.
There were 300 units in ending work-in-processon June 30. They were 40% complete.
How many total equivalent unitsdid ACE produce during June?
Continue
-
8/12/2019 EMBA 5403 Costing Systems
35/37
Fall 2010 Mugan 35/37
units
% of work
done this
period
Equivalent
units
Work to complete
beginning work-in-process250 70% 175
Equivalent Units - Example
Since 30% of the work was done onthese units in May, the remaining 70% of
the work is done in June.
-
8/12/2019 EMBA 5403 Costing Systems
36/37
Fall 2010 Mugan 36/37
units
% of work
done this
period
Equivalent
units
Work to complete
beginning work-in-process250 70% 175
Work on units started and
completed900 100% 900
Equivalent Units - Example
Since 1,200 units were started during June, and 300 ofthose units are still in work-in-process on June 30,900 units were started and completed during June.
-
8/12/2019 EMBA 5403 Costing Systems
37/37
Fall 2010 Mugan 37/37
Equivalent Units - Example
units
% of work
done this
period
Equivalent
units
Work to complete
beginning work-in-process250 70% 175
Work on units started and
completed900 100% 900
Work on ending work-in-process 300 40% 120
Total equivalent units 1,195
40% of the work was done on these units in June.