6th July, 2012 (3:00 pm)
Consultancy Services for Digital Topographical Mapping and the preparation of integrated strategic urban
development plans for cluster III towns: Machakos, Thika and Embu
FORM TECH 4
Study Approach, Methodology and Work Plan
Stage I: Project Initiation
Activity 1.1: Mobilization of Team
Activity 1.2: Kick-off meeting with the stakeholders
Activity 1.3: Preliminary Site Visit
Activity 1.4: Inception Report Submission
Stage II: Project Launch and Situational Analysis workshop
Activity 2.1: Site Visit
Activity 2.2: Collection and Review of secondary data, drawings and maps
Activity 2.3: Review of Present Situation of each townsActivity 2.4: Workshop with Stakeholders for Situation Analysis
Activity 2.5: Submission of Situation Analysis Report
Stage III: Preparation of base maps
Activity 3.1: Prepare base map and existing land-use map using recent high resolution satellite remote
sensing data
Activity 3.2: ReconnaissanceSurveys of the cities and the region conducted are such as
i. Topographic survey
ii. Land-use survey
iii. Transportation survey
Activity 3.3: Appreciation of demography, housing, socio-economy, industry, legal, regulatory and
institutional development of the study areaActivity 3.4: Assessment of physical and social infrastructure, ecology and environment, hazard and
vulnerability and cultural and heritage conservation assets
Activity 3.5: Prepare an Integrated geo-spatial database collecting and collating appropriate data with
various sectoral plans
Activity 3.6: Submission of Base Maps
Stage IV: Validation Workshops
Activity 4.1: Validation Workshop with the Stakeholders
Activity 4.2: Submission of Validation Workshop Reports and base map after modification (if any)
Stage V: Interim Report on the proposals on Integrated Strategic Urban Development Plan
(ISUDP) with Final MapsActivity 5.1: Undertake visioning exercise, formulate the objectives and evaluate and arrive at plans and
recommendations at different scales through public participative consultation mode
Activity 5.2: Generate scenarios and alternative features for set objectives
Activity 5.3: Preparation of Final Maps after modification (if any) as per the comments received in the
Validation Workshop
Activity 5.4: Submission of Interim Report and thematic studies along with Final Maps
-
7/31/2019 Email 6th July Approach and Methodology_Kenya Proposal
2/2
Stage VI: Draft Integrated Strategic Urban Development (ISUD) Plan
Activity 6.1: Demand forecasting for Draft ISUD Plan on the following sectors
i. Demographic, housing, socio-economic and enterprise forecasting
ii. Integrated land-use, physical and social infrastructure and service demand forecasting
iii. Legal, regulatory and institutional development option generationiv. Preparation of zoning regulation/ development control guidelines and appropriate
recommendations of FAR normsActivity 6.2: Preparation of the urban area management plans such as Transportation Plan, Environment
Management Plan, Disaster Management Plan and Cultural and Heritage Conservation Plan
Activity 6.3: Preparation of criteria for phased development and implementation plan
Activity 6.4: Preparation of Draft ISUD Proposals which will include
i. Structure Plan
ii. Action Area Plans and
iii. Planning Policies and Regulations
Activity 6.5: Submission of Draft ISUD Proposal
Stage VII: Validation Workshop Report for the proposals on Integrated Strategic Urban
Development (ISUD) with Final Maps
Activity 7.1: Validation Workshop with the Stakeholders for ISUD proposals and Final MapsActivity 7.2: Submission of Validation Workshop Report for ISUD proposals
Stage VIII: Draft Capital Investment Plan
Activity 8.1: Preparation of Capital Investment Plan (CIP)Activity 8.2: Submission of Report on Capital Investment Plan (CIP)
Stage IX: Submission of Final Maps (Hard Copy and Soft Copy) after modification (if any)
Stage X: Workshop for final ISUD Plan and CIP
Activity 10.1: Workshop on final Integrated Strategic Urban Development Plan (ISUDP) and Capital
Investment Plan (CIP)
Activity 10.2: Submission of Workshop Report on final ISUDP and CIP
Stage XI: Submission of Final Integrated Strategic Urban Development Plan (ISUDP) and Capital
Investment Plan (CIP) Report
Stage XII: Skill and Knowledge Transfer
Activity 12.1: Assessment of skill and knowledge transfer processActivity 12.2: Implementation of the process
Stage XIII: Official Launch of approved ISUD plan and CIP