    Consultancy Services for Digital Topographical Mapping and the preparation of integrated strategic urban

    development plans for cluster III towns: Machakos, Thika and Embu

    FORM TECH 4

    Study Approach, Methodology and Work Plan

    Stage I: Project Initiation

    Activity 1.1: Mobilization of Team

    Activity 1.2: Kick-off meeting with the stakeholders

    Activity 1.3: Preliminary Site Visit

    Activity 1.4: Inception Report Submission

    Stage II: Project Launch and Situational Analysis workshop

    Activity 2.1: Site Visit

    Activity 2.2: Collection and Review of secondary data, drawings and maps

    Activity 2.3: Review of Present Situation of each townsActivity 2.4: Workshop with Stakeholders for Situation Analysis

    Activity 2.5: Submission of Situation Analysis Report

    Stage III: Preparation of base maps

    Activity 3.1: Prepare base map and existing land-use map using recent high resolution satellite remote

    sensing data

    Activity 3.2: ReconnaissanceSurveys of the cities and the region conducted are such as

    i. Topographic survey

    ii. Land-use survey

    iii. Transportation survey

    Activity 3.3: Appreciation of demography, housing, socio-economy, industry, legal, regulatory and

    institutional development of the study areaActivity 3.4: Assessment of physical and social infrastructure, ecology and environment, hazard and

    vulnerability and cultural and heritage conservation assets

    Activity 3.5: Prepare an Integrated geo-spatial database collecting and collating appropriate data with

    various sectoral plans

    Activity 3.6: Submission of Base Maps

    Stage IV: Validation Workshops

    Activity 4.1: Validation Workshop with the Stakeholders

    Activity 4.2: Submission of Validation Workshop Reports and base map after modification (if any)

    Stage V: Interim Report on the proposals on Integrated Strategic Urban Development Plan

    (ISUDP) with Final MapsActivity 5.1: Undertake visioning exercise, formulate the objectives and evaluate and arrive at plans and

    recommendations at different scales through public participative consultation mode

    Activity 5.2: Generate scenarios and alternative features for set objectives

    Activity 5.3: Preparation of Final Maps after modification (if any) as per the comments received in the

    Validation Workshop

    Activity 5.4: Submission of Interim Report and thematic studies along with Final Maps

  • 7/31/2019 Email 6th July Approach and Methodology_Kenya Proposal

    2/2

    Stage VI: Draft Integrated Strategic Urban Development (ISUD) Plan

    Activity 6.1: Demand forecasting for Draft ISUD Plan on the following sectors

    i. Demographic, housing, socio-economic and enterprise forecasting

    ii. Integrated land-use, physical and social infrastructure and service demand forecasting

    iii. Legal, regulatory and institutional development option generationiv. Preparation of zoning regulation/ development control guidelines and appropriate

    recommendations of FAR normsActivity 6.2: Preparation of the urban area management plans such as Transportation Plan, Environment

    Management Plan, Disaster Management Plan and Cultural and Heritage Conservation Plan

    Activity 6.3: Preparation of criteria for phased development and implementation plan

    Activity 6.4: Preparation of Draft ISUD Proposals which will include

    i. Structure Plan

    ii. Action Area Plans and

    iii. Planning Policies and Regulations

    Activity 6.5: Submission of Draft ISUD Proposal

    Stage VII: Validation Workshop Report for the proposals on Integrated Strategic Urban

    Development (ISUD) with Final Maps

    Activity 7.1: Validation Workshop with the Stakeholders for ISUD proposals and Final MapsActivity 7.2: Submission of Validation Workshop Report for ISUD proposals

    Stage VIII: Draft Capital Investment Plan

    Activity 8.1: Preparation of Capital Investment Plan (CIP)Activity 8.2: Submission of Report on Capital Investment Plan (CIP)

    Stage IX: Submission of Final Maps (Hard Copy and Soft Copy) after modification (if any)

    Stage X: Workshop for final ISUD Plan and CIP

    Activity 10.1: Workshop on final Integrated Strategic Urban Development Plan (ISUDP) and Capital

    Investment Plan (CIP)

    Activity 10.2: Submission of Workshop Report on final ISUDP and CIP

    Stage XI: Submission of Final Integrated Strategic Urban Development Plan (ISUDP) and Capital

    Investment Plan (CIP) Report

    Stage XII: Skill and Knowledge Transfer

    Activity 12.1: Assessment of skill and knowledge transfer processActivity 12.2: Implementation of the process

    Stage XIII: Official Launch of approved ISUD plan and CIP