ELK MEADOWS HOA Water Master Plan (Supply, Treatment, Distribution, and Storage) May 2005.
-
Upload
samuel-simmons -
Category
Documents
-
view
214 -
download
0
Transcript of ELK MEADOWS HOA Water Master Plan (Supply, Treatment, Distribution, and Storage) May 2005.
OBJECTIVES Evaluate Existing Water Supply and Water
Treatment Facilities
Hydraulic Modeling Recommend Improvements for a Buildout System
(Without Fireflow Protection )
Recommend Improvements for a Buildout System (With Fireflow Protection)
Recommend Improvements for Water Supply, Treatment and Distribution
Estimate Costs and Investigate Funding Alternatives for Recommended Improvements
PROJECT APPROACH
Collect Background Information
Review CDPHE and EPA Requirements
Conduct Site Investigations
Inventory and Photograph Existing Facilities
interview System Operator(s)
Hydraulic Analysis with WaterCAD® Software
Develop Water Demands
Evaluate Existing Facilities (Max Day, Peak Hour)
Model Short-Term and Long-Term Alternatives
WATER SUPPLY SOURCESGroff Spring
Classified as ‘Directly Under Influence of Surface Water’
Produces 28,000 gpd (20 gpm)
High Raw Water Turbidity (5 NTU up to 100 NTU)
No Hazardous Metals, Volatile Organics
Elk Meadows Well Completed in May 2003 as
Supplemental Source Produces 15,000 gpd (10
gpm) Acceptable Raw Water
Quality No Hazardous Metals,
Volatile Organics
Most recent boil-order in May of 2003.
Water rights allow a TOTAL of 53,800 gpd (37gpm) for combined well and spring source.
WATER DEMAND SUMMARYWATER DEMAND SUMMARY
*Estimated from Operations Data During for 2004 per Elk Meadows HOA. ** Assumes Average Annual Demand: Peak Hour Demand Factor = 4.00 (Mayes, 2000).
CONNECTION TYPENUMBER
OFCONNECTIONS
2004 SCENARIO (gpcd)
BUILDOUT SCENARIO
(gpcd)
Average Day Demand (gpcd) 80 72 80
Maximum Day Demand (gpcd) 126 129 143
2004 Average Annual Demand (gpd)
2004 Max Day Demand (gpd)
2004 Peak Hour Demand (gpd)
Max Day: Avg Day Factor
Peak Hour: Avg Day Factor 4.00**
11,520*
36,100*
46,080**
3.10
WATER TREATMENT PLANT
Building is 30 Years Old Upgraded in 2002 To Include Coagulation and Pressure
Filtration Hypochlorite Disinfection No Baffling in Clearwell to Provide Chlorine Contact Time Currently Backwashes with Raw Water (not allowed by CDPHE) Inappropriate for higher turbidity (>5 NTU) Raw Water per
(CDPHE) Backwash Wasted to Unlined Pond (not allowed by CDPHE) Need Additional Treatment Capacity No Redundancy or Expandability
WATER TREATMENT
Existing WTP
Capacity of 22,680 gpd
In-line Flocculation
• Coagulant Added to Raw Water
• Forms ‘Flocs’
Pressure Filtration
• Bag Filter Redundancy
• Effluent to Disinfection
WATER TREATMENT
Wet Well
Groff Spring
Well
Pressure Filter
Sodium Hypochlorite
Bag Filter Unbaffled
Clear Well
Raw Water Backwash
PAC Coagulant
(Alum)
To Distribution & Storage
FILTRATION
Vertical Pressure Filter
2-ft Diameter Yardney®
3.15 ft2 Filtration Area
Current Filtration Rate = 8 gpm/ft2
CDPHE Max. Filtration Rate = 5 gpm/ft2
Bag Filter
Strainrite®
Filters Down to 1.0 Micron
WATER TREATMENT OPTIONSWATER TREATMENT OPTIONSRETROFIT EXISTING WTP Add 2nd New Pressure Filters Additional Building Space Required Install larger capacity Backwash Pump That Draws from Clearwell Install Baffles in Clearwell May or May Not Fix Finished Water Turbidity
NEW WTP OPTION New Building with Package Plant or Membrane Plant Install Baffles in Clearwell More Expensive than Retrofitting Existing WTP Will Handle Peaks in Raw Water Turbidity Long-term Solution
WATER DISTRIBUTION SYSTEM
Serves 80 Unmetered Connections
Most Piping is 30 Years Old
Comprised largely of 2-inch Diameter Piping
Materials Vary from PVC to HDPE
Problems with Pipe Leaks and Freezing
HOA Incurs Significant Costs for Repairs and Replacement ($150,000 from 2000 to 2004)
No Fireflow Protection
No Hydrants
EXISTING HYDRAULIC PROFILEEXISTING HYDRAULIC PROFILE
Single 5-HP Transmission Pump Located at WTP
12,000-gal Tank Serves Zones Through PRVs
CDPHE Pressure Criteria
• Maximum = 100 psig
• Minimum = 35 psig
Pressure Zone Boundaries
• Zone 1 = 8,500 to 8,580 ft
• Zone 2 = 8,581 to 8,719 ft
• Zone 3 = 8,720 to 8,864 ft
WATER STORAGE NEEDSWATER STORAGE NEEDS
STORAGE COMPONENT
CDPHE REQUIREMENT with
FIRE
(GALLONS)
CDPHE REQUIREMENT
without FIRE
(GALLONS)
Fireflow 120,000 0
2004 Domestic
Buildout Domestic
60,000*
100,000
60,000*
100,000
Emergency 0 0
Operational 0 0
TOTAL AT BUILDOUT 220,000 120,000
*CDPHE requires 300 gallons per capita; Assumes 80 homes with 2.5 persons per home.
HYDRAULIC ANALYSISHYDRAULIC ANALYSIS Haestad Methods
WaterCAD®
Steady-State Analysis
Multiple Scenarios
• 2004 Max Day
• 2004 Peak Hour
• Buildout Max Day
• Buildout Max Day + Fireflow
Identify Problems
Two Buildout Scenarios
• Option I – No Fireflow Protection
• Option II – Provide Fireflow Protection
HYDRAULIC ANALYSIS RESULTSHYDRAULIC ANALYSIS RESULTS
Reservoir Drains During Max Day Demand
Low Pressures in Zone 3 at Peak Hour (<20 psig)
Max Day Demand Approaching Available Water Supply
Max Day + Fire Demand Indicates Significant Piping and Storage Improvements Needed
Modeled Buildout System Without Fire Protection
Modeled Buildout System With Fire Protection
SHORT-TERM IMPROVEMENTSSHORT-TERM IMPROVEMENTS
ID, DESCRIPTIONUNITS QUANTITY COST
ST 1A, Add 2” PRV Zone 3 to Zone 2 EA 1 $ 9,000
ST 1B, New Zone 3 Piping (3” DIA) LF 850 $ 13,000
ST 2, Zone 2 Looping (3” DIA) LF 240 $ 3,600
ST 3, Zone 3 Looping (3” DIA) LF 460 $ 6,900
ST 4, New Pipe from WTP to Zone 3 (3” DIA) LF 2,670 $ 40,000
ST 5, Line Replacement (Replace w. 3” DIA) LF 5,000 $ 75,000
Existing Well Enlargement LS 1 $ 7,500
Remedial Work @ Treatment Plant LS 1 $ 6,000
SUBTOTAL $ 161,000
ENGINEERING AND ADMINISTRATION (20%) $ 32,200
TOTAL PROJECT COST $193,200
BUILDOUT SYSTEM SCENARIOSBUILDOUT SYSTEM SCENARIOS
Option I – Maximum Day Demand Only (No Fire)
• Implement all Short-Term Improvements
• Recommend All New Piping be 3-inch Diameter or larger
Option 2 – Maximum Day Demand (+ Fire)
Implement all Short-Term Improvements All New Piping 6-inch Diameter Require 6-inch Fire Hydrants Use 1997 UFC Requirement of 1,000 gpm at 2-hour
Duration with Residual Pressure of 20 psig = 120,000-gal Storage
OPTION 1 SYSTEM COSTSOPTION 1 SYSTEM COSTS
ID, DESCRIPTIONUNIT
SQUANTIT
YINSTALLED COST
O1-1, West Zone 3 Piping (3” DIA)
LF 1,000 $15,000
O1-2, East Zone 3 Piping (3” DIA)
LF 620 $9,300
O1-3, Central Zone 3 Piping (3” DIA)
LF 1,460 $21,900
O1-4, Zone 2 Loop Piping (3” DIA)
LF 940 $14,100
New Coated Steel Storage Reservoir
MG 0.100 $70,000
SUBTOTAL $130,300
ENGINEERING & ADMIN. (20%)
$26,000
TOTAL PROJECT COST $156,300The costs in do not include new water meters, improvements to the WTP or maintenance costs for existing piping, which are included in the short-term improvements and should also be budgeted in the HOA’s capital improvements plan. Also, the storage volume is the minimum domestic storage required by the CDPHE and doesn’t include an emergency storage component.
OPTION 2 SYSTEM COSTSOPTION 2 SYSTEM COSTS
ID, DESCRIPTIONUNITS QUANTITY
INSTALLED COST
O2-1, Zone 3 Piping (8” DIA) LF 4,250 $170,000
O2-2A, Zone 3 Piping (6” DIA) LF 10,430 $313,000
O2-2B, Zone 3 Fire Hydrants EA 12 $12,000
O2-3A, Zone 2 Piping (6” DIA) LF 6,340 $190,200
O2-3B, Zone 2 Fire Hydrants EA 4 $4,000
O2-4, New PRVs with Vaults EA 1 $40,000
O2-5A, Zone 1 Piping (6” DIA) LF 320 $9,600
O2-5B, Zone 1 Fire Hydrants EA 1 $1,000
New Storage Reservoir MG 0.220 $110,000
SUBTOTAL $849,800
ENGINEERING & ADMIN. (20%)
$170,000
TOTALPROJECT COST $1,020,000
The costs in do not include water meters or improvements to the WTP present an economic challenge for the Elk Meadows HOA and residents. Funding options available for financing these improvements are discussed in Section 6.3. Also, the improvements could be phased over a long period with the storage reservoir and Zone 3 piping improvements taking priority over improvements in Zones 1 and 2. This is due to the fact that Zone 3 piping and PRVs provide storage and distribution to Zones 1 and 2 and any restrictive piping in Zone 3 would be apparent in the downstream Zones.
SUMMARY OF RECOMMENDED SUMMARY OF RECOMMENDED SYSTEM IMPROVMENTSSYSTEM IMPROVMENTS
Project Description Project Cost
Short-Term Improvements $ 193,000
Option 2 (Build-out with Fire) $ 958,000
Additional Source Development $ 100,000
Treatment Plant Replacement $ 500,000
Meters $ 70,000
Total $ 1,821,000
ALTERNATIVE ALTERNATIVE SYSTEM IMPROVMENTSSYSTEM IMPROVMENTS
Project Description Project Cost
Short-Term Improvements $ 177,000
Option 1 (Build-out with Fire) $ 199,000
Additional Source Development $ 100,000
Treatment Plant Upgrades (if permittable) $ 75,000
Meters $ 50,000
Total $ 601,000
FUNDING OPTIONSFUNDING OPTIONS Colorado Rural Water Association - Loans Colorado Water Conservation Board - Grants Up to 75% of
Project Cost Department of Agriculture - Grants and Loans
• Objective to Improve Rural Areas
• Priory Given for Public Safety Projects
Department of Local Affairs (DOLA)• Offers Grants and Loans
Other (595, Special Legislative Grants, etc.)
In general, Government Grants require formation of a legal Governmental Entity (i.e. District)
Low to Moderate Income Eligibility (Income Survey)