description

RANDOLPH COUNTY CONSERVATION DISTRICT. ELEVEN POINT WATERSHED COST SHARE PROJECT ANRC, EPA, RCCD, NRCS. The Problem:. Listed on 303(d) list Organic enrichment causing depleted oxygen levels. Not sustaining the designated use for aquatic life because of low dissolved oxygen. - PowerPoint PPT Presentation

Transcript of ELEVEN POINT WATERSHED COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

Page 1: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

ELEVEN POINT WATERSHED COST SHARE PROJECT

ANRC, EPA, RCCD, NRCS

RANDOLPH COUNTY CONSERVATION DISTRICT

Page 2: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

Listed on 303(d) listOrganic enrichment causing depleted oxygen

levels.Not sustaining the designated use for aquatic

life because of low dissolved oxygen.Agriculture activities within the watershed are

thought to be the major source of nutrient runoff.

The Problem:

Page 3: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

Eleven Point River Watershed

2006 Land UseArkansaswater.org

Forest: 61.7%Grassland:

33.4%Transitional:

4.0%Water: 0.6%Cropland: 0.5%Suburban: 0.2%Urban: 0.1%

Page 4: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

Project Management:Randolph County Conservation

District

Project Cost: Total ($328,460)Federal ($169,500) State/Local($158,960)

$75,000 federal dollars made available to landowners for up to 40% cost share

Eleven Point River 319(h) Project

Page 5: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

Goal: Improve water quality and land productivity in an effort to remove this stream from ADEQ’s 303(d) list.

Objective: Write 132 Conservation plans and provide cost-share on approved conservation practices.

Eleven Point River 319(h) Project

Page 6: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

Project Tasks1. Utilize Conservation District Board2. Provide Technical Assistance3. Provide Cost Share for BMP

Implementation4. Technology Transfer5. Equipment Purchase6. Reporting

Eleven Point River 319(h) Project

Page 7: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

Steering Committee ResponsibilitiesR.C.C.D. will meet monthly for 3 yearsReview all inventories and

assessments done in the Watershed; set priorities for cost-share in the project area; and coordinate all activities of the project components

Review and approve all deliverables

Task 1

Page 8: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

Technical AssistanceThe District Technician will write

132 conservation plans over a 2 year period.

R.C.C.D. will make return visits as needed to the 132 farms planned to assist with conservation planning and BMP implementation.

Task 2

Page 9: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

Cost Share 40%:Based on 2009 EQIP Cost List

Task 3

Page 10: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

PondFenceWatering FacilityPipelineHeavy Use AreaPasture And Hay PlantingBrush ManagementTree/Shrub Establishment

Task 3 (cont.)

Page 11: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

Technology Transfer:Develop and publish a

quarterly newsletter (8 Completed)

Distribute the newsletter to landowners who own 15 acres or more within the Eleven Point Watershed

Plan and hold yearly outreach meetings to inform landowners within the Eleven Point Watershed

Task 4

Page 12: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

Equipment Purchase

Purchased Fence Dawg fencing tool

Held Field day to show producers how this equipment works

Task 5

Page 13: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

Fence Dawg Field Day

Page 14: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

Reporting:Provide quarterly reports that include

implementation documentation (7 Quarterly Reports Completed)

Provide Annual Reports (1 Annual Report Completed)

Complete Final Report

Task 6

Page 15: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

Accomplishments to date:Held monthly Conservation District Board

MeetingsPublished 8 NewslettersCompleted 132 conservation plans Purchased Fence Dawg Fencing EquipmentHeld Fence Dawg Field Day Demonstration$46,089.42 has been paid to landowners

($90,774.99 landowner match)

Eleven Point River 319(h) Project

Page 16: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

Ponds:4 Completed

Critical Area Planting:2 acres completed

Pipeline:1310 ft. installed

Pest Management:349 acres completed

Best Management Practices:

Page 17: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

2 Completed

Best Management Practices:Waste Storage Facilities

Page 18: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

306 acres completed

Best Management Practices: Pasture and Hay Planting

Page 19: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

29,702 ft. completed

Best Management Practices: Fence

Page 20: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

5 Completed

Best Management Practices: Watering Facilities

Page 21: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

5,375 square ft. Installed

Best Management Practices: Heavy Use Areas

Page 22: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

10 acres of Brush Management completed

Best Management Practices:Pest Management & Brush Management

Page 23: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS
Page 24: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

R.C.C.D. EquipmentHaybuster 107 No-till Drill

Page 25: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

R.C.C.D. Equipment300 gallon Trailer

Sprayer

Page 26: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

R.C.C.D. EquipmentBermuda Sprigger

Page 27: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

R.C.C.D. EquipmentRoto Wiper & Vicon Seeder

Page 28: ELEVEN POINT WATERSHED  COST SHARE PROJECT ANRC, EPA, RCCD, NRCS

QUESTIONS???