ELECTRICITY OF VIETNAM
NORTHERN POWER CORPORATION
-----------------------------
DISTRIBUTION EFFICIENCY PROJECT
SUB - PROJECTS
LINE 110KV HAI DUONG – PHO NOI
(SUB - LINE ON HUNG YEN PROVINCE)
AND EXPANSION OF 110KV LINE AT 220KV PHO NOI SUBSTATION
ENVIRONMENTAL MANAGEMENT PLAN
Prepared by
PHU MINH JOINT STOCK COMPANY
Ha noi, 18 April 2012
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
1
ABBREVIATIONS
EIA Environmental Impact Assessment
EMP Environmental Management Plan
EMF Electromagnetic field
EVN Electricity of Vietnam
HW Hazardous waste
PAHs Project Affected Households
PMU Project Management Unit
PC Power Company
ROW Right of Ways
SIMC Safeguards Independent Monitoring Consultant
NPC Northern Power Corporation
WB The World Bank
CPC Commune People's Committee
2
TABLE OF CONTENTS
I. introduction ........................................................................................................................4
II. POLICY FRAMEWORKS, REGULATIONS ...............................................................4
2.1. Vietnam Government Regulations: .........................................................................4
2.2. World Bank safety Policies: .....................................................................................5
III. PROJECT DESCRIPTION AND WORK SCALE ........................................................5
3.1. Project Description: ..................................................................................................5
3.1.1. Line 110kV Hai Duong – Pho Noi (subline in Hung Yen Province) ...................5
3.1.2. Sub expansion 110kV at 220kV Pho Noi substation ............................................6
Table 3.1. Equipment expansion feeder ...............................................................................6
3.1.3. Amount main workload of project ........................................................................6
Table 3.2. Amount construction 110kV line Hai Duong – Pho Noi ....................................6
3.2. Work transportation .................................................................................................7
3.2.1. Materials and equipment supply: ..........................................................................7
3.2.2. Long distance transportation .................................................................................8
3.2.3. Intermediate transportation ...................................................................................8
3.2.4. Manual handling ...................................................................................................8
3.3. Arranging construction worker force and constructing site.................................8
3.4. Progress and total investment of project: ...............................................................9
3.4.1. Project progress:....................................................................................................9
3.4.2. Project total investment: .......................................................................................9
Table 3.3. Total investment of project .................................................................................9
IV. SUMMARY OF NATURAL AND ENVIRONMENTAL CONDITIONS
PROJECT’S AREA .........................................................................................................10
4.1. Geographical geological conditions .......................................................................10
4.1.1. Geographical location: ........................................................................................10
4.1.2. Topography and geomorphology ........................................................................10
4.1.3. Geological ...........................................................................................................10
4.2. Meteorological conditions ......................................................................................10
4.3. Traffic.......................................................................................................................10
4.4. Describe router: ......................................................................................................12
Table 4.1. Table describes line passing thought territory of administrative ĐDK-
110kV Hai Duong – Pho Noi ............................................................................12
V. IDENTIFICATION OF POTENTIAL IMPACTS OF THE PROJECT ...................16
Table 5.1. Rapid assessment of environmental impacts of the Project ..............................16
3
VI. ENVIRONMENTAL MANAGEMENT PLAN ............................................................20
6.1. Mitigation measures................................................................................................20
Table 6.1. Mitigation measures applied for the Project .....................................................20
6.2. Measures to minimize the specific impact of this project ...................................30
Table 6.2. Measures to minimize the specific impact of this project ................................30
6.3. Environmental monitoring plan ............................................................................30
Table 6.3. Environmental monitoring plan ........................................................................30
VII......... EMP IMPLEMENTATION ARRANGEMENT AND CAPACITY BUILDING 32
7.1. Responsibilities for Implementing the Environmental Management
Plan ...................................................................................................................32
To ensure effective implementation of the EMP, the following actions will be
carried out during the implementation of the subproject ..................................32
7.1.1 During Detailed Design and Preparation of Bidding Contract
Documents ........................................................................................................32
7.1.1. Construction phase: .............................................................................................33
Role and responsibilities of parties in implementing EMP are summarized in the
below table ........................................................................................................33
Table 7.1. Responsibility for EMP Implementation ..........................................................33
7.2. Building the EMP implementation capacity.........................................................35
Table 7.2.Estimates of capacity building for implementing EMP .....................................35
7.2 Reporting procedure .........................................................................................36
7.3. Estimated cost for implementing the EMP ...........................................................36
VIII. CONSULTATION AND DISCLOSURE OF INFORMATION ........................37
Table8.1 Summery consult public .....................................................................................37
ANNEX 1 ................................................................................................................................40
ANNEX 4 ................................................................................................................................45
ENVIRONMENTAL LICENCEANNEX 5 .........................................................................46
ANNEX 6 ................................................................................................................................47
ANNEX 7 ................................................................................................................................58
4
I. INTRODUCTION
The sub-project 110kV line Hai Duong – Pho Noi and expansion 110KV feeder at
220KV Pho Noi substation (hereinafter referred to as 110KV Hai Duong – Pho Noi Sub-
project) would be invested to ensure safe and reliable power supply for Hung Yen Province,
creating infrastructure for economic development and improving system stability in the
operating modes.
It is one of the sub-projects that will be implemented in Phase I of the Distribution
efficiency project (DEP) of the Electricity of Vietnam which will be financed by the World
Bank. The sub-project will be implemented in My Hao district, Hung Yen province.
The sub-project activities include: i) New construction of 9.427 km double circuit lines
110 kV, ii) Expansion of the 110kV at 220kV Pho Noi substation. These activities can cause
negative impacts on the environment and local communities in during the preconstruction,
construction, and operation phases of the subproject.
To ensure the potential negative impacts are identified and mitigated during the sub-
project implementation and in compliance with the policy on environmental assessment of
the World Bank (OP/BP 4.01), an environmental Management Plan (EMP) of the sub-project
has been prepared in accordance with the guidelines of the Environmental Management
Framework (EMF) of the DEP project. The EMP includes the following contents: sub-project
description, the main framework of policies, rules and technical regulations applicable
environment, the potential negative impacts, the mitigation measures proposed will be
conducted in the previous period building, construction and commissioning, implementation
arrangements. The EMP also includes Environmental Codes of Practice (ECOP) to apply for
the subproject, and to be incorporated into the bidding documents and construction contracts,
as well as a scope for environment quality monitoring.
According to the government EIA regulation the subproject need to prepare and
Environmental Impact Assessment report. An EIA has been prepared and approved by Hung
Yen People Committee on ……...
II. POLICY FRAMEWORKS, REGULATIONS
2.1. Vietnam Government Regulations:
The following laws and regulations are applied for subproject:
Law on Protection of the Environment No. 52/2005/QH11 passed by the National
Assembly on November, 29th
, 2005 regulates the obligations of individuals,
organizations in protecting environment.
Law on forest protection and forest development No. 29/2001/QH11.
Law on cultural heritage No. 28/2001/QH10.
Law on Water Resource No. 08/1998/QH10 dated 20 May, 1998
Decree of Government No. 80/2006/ND-CP dated 9 August, 2006 on guidance for
implementation of Law on Protection of the Environment.
Decree of Government No. 29/2011/ND-CP dated 18 April, 2006 regulating strategic
environmental assessment, environmental impact assessment and environment
protection commitment.
5
Circular No.26/2011/TT-BTNMT dated 18 July, 2011 on guidance for Decree
No.29/2011/ND-CP dated 18 April, 2011.
Decree of Government No.106/2005/ND-CP dated 17 August, 2005 on guidance for
Law on electricity relating to the protection of high-voltage networks.
Decree of Government No.81/2009/ND-CP dated 12 October, 2009 amending some
Article of Decree No.106/2005/ND-CP dated 17 August, 2005.
Circular No.12/2011/TT-BTNMT dated 14 April, 2011 relating to hazardous waste
management.
Vietnam National Standard: QCVN01: 2009/BYT- national technical regulation on
drinking water quality; QCVN02: 2009/BYT- national technical regulation on
domestic water quality; QCVN08: 2008/BTNMT - national technical regulation on
surface water quality; QCVN09: 2008/BTNMT - national technical regulation on
ground water quality; QCVN05: 2009/BTNMT – air quality – Standard for ambient
air quality; QCVN06: 2009/BTNMT – air quality –specified maximum allowable
concentrations of certain hazardous substances in ambient air.
Guidance of EVN No. 2623/CV-EVN - KHCN & MT dated 28 May, 2007 on
management and pollution prevention and exposure to PCBs.
2.2. World Bank safety Policies:
An environmental screening was undertaken in line with the guidelines provided in the
Environmental Management Framework (EMF) of the DEP project and it showed that the
World Bank’s policies on Environmental Assessment (OP 4.01) and Involuntary
Resettlement (OP 4.12) will be triggered for the subproject. In addition, the Bank’s
requirements on public consultation and information disclosure will need to be followed.
The implementation of policy on involuntary resettlement (OP 4.12) will be addressed in
a separate report
III. PROJECT DESCRIPTION AND WORK SCALE
3.1. Project Description:
3.1.1. Line 110kV Hai Duong – Pho Noi (subline in Hung Yen Province)
Sub line: “110kV line Hai Duong – Pho Noi (subline in Hung Yen province)” has below
main characteristics:
- First point: Pole No 55, 110kV line Hai Duong – Pho Noi
- End point: 110kV Pooctic 220kV Pho Noi Substation.
- Level Voltage: 110kV.
- Line No: 2 lines.
- Length: 9,427km.
- Conductor: ACSR-300/39.
- Insulator: Insulator hanging by ceramic or glass, kind U70BS van U120B.
- Pole: Galvanized steel pole double circuit assembled by bolts.
- Foundation: Concrete pole foundation cast in situ
6
3.1.2. Sub expansion 110kV at 220kV Pho Noi substation
Project investment local:
To supply power for 110 kV two circuit lines Hai Duong – Pho Noi is distribution 110kV
station at 220kV Pho Noi substation must expansion an outgoing feeder for supply power to
the line.
Project investment scale:
- To fit full equipment for a 110kV outgoing feeder is expansion at 220kV Pho Noi
substation, as follows:
Table 3.1. Equipment expansion feeder
No Device’s name and characteristics Unit Quantity Note
1 Cut machine SF6 110kV 3 phase: 123kV-1250A-
25kA/1s
Set 1
2 Power line converter 110kV 1 phase: 123kV-(200-
400-600-800)/1/1/1/1A
Set 3
3 Voltage converter 110kV 1 phase: 123kV-
12000pF - 110:√3/ 0,1:√3/ 0,1:√3kV
Set 3
4 Disconnector 3 phase 110kV 2 earthing blades:
123kV-1250A-25kA/1s
Set 1
5 Disconnector 3 phase 110kV none earthing blade:
123kV-1250A-25kA/1s
Set 2
6 Disconnector 1 phase 110kV 1 earthing blade :
123kV-1250A-25kA/1s
Set 3
- To fit control, protect, information SCADA systems for device is new installed: to
fit a cabinet protect control 110kV line in house, an outdoor cabinet wiring to feeder
of 110kV, an outdoor cabinet wiring to variable voltage 110kV.
3.1.3. Amount main workload of project
Table 3.2. Amount construction 110kV line Hai Duong – Pho Noi
No Work content Unit Quantity Note
1 Pouring concrete rock 2x4, level
durability B15 m
3 1,492.79
Handmade +
Mechanical
2 Pouring concrete rock 4x6, level
durability B3,5 - 370.79 -
3 Processing steel foundation, steel plates Ton 147.96 -
4 Anchor bolts Ton 11.83 -
7
5 Processing to installation Earthing
systems Position 41 -
6 Processing, erection steel pole Ton 270.34 -
7 Pull the wire tension spread ACSR-
300/39 km 58.751 -
8 Pull the tension spread lightning TK-50 - 0.933 -
9 Pull the cable tension spread OPGW68 - 9.797 -
Pull the cable tension spread ADSS - 0.187
10 To fit the wire anchor serial types Serial 216 Handmade
11 To fit the wire serial types - 204 -
12 To fit the support chain, anchor rope
CS, CQ wire - 59 -
13 Amount digging foundation land +
Earthing systems m
3 11,394.82
Handmade +
Mechanical
14 Amount filling foundation land +
Earthing systems - 9,055.9 -
15 Crossing lower voltage information line Time 08 Handmade
16 Crossing medium voltage line - 11 -
17 Crossing lines 220kV - 03 -
18 Crossing roads ≤ 10m - 06 -
19 Number of steering angle Conner 12
20 Pile driving bamboo 2.5m Pile 332 Handmade
21 Wattle bamboo 1x2m Plate 112 -
22 Dikes m3 235 -
3.2. Work transportation
3.2.1. Materials and equipment supply:
Material and equipment supply will be determined in detail in later phase, depending on
the state budget disbursement and the subproject bidding method. Two sources are expected:
- Cement, steel, sand, stone, gravel, shuttering to get local through routes.
- Tubular steel, fiber, wireless accessories, ceramic take in Hanoi.
8
3.2.2. Long distance transportation
For material and equipment supplied by the project owner:
+ Long distance transportation of such material and equipment will be undertaken
using specialized trucks. Such trucks will be selected in accordance with the requirements
provided in the contract.
+ Long distance transportation from the subproject owner warehouse to the site
will be undertaken using 5-7.5 ton trucks and loading and unloading will be done using 5-
ton cranes.
For materials and equipment supplied by the contractor:
+ Electric poles will be transported using Kawaz trucks, using 5-ton cranes for
loading and unloading.
+ Supporting frames and accessories will be transported using 5-ton trucks with
manual loading and unloading.
+ Cement and steel will be transported using 5-ton trucks with manual loading and
unloading.
+ Stone and sand will be transported using 5-ton dump trucks.
3.2.3. Intermediate transportation
Materials are supplied by A as: steel poles, wires insulation, accessories …have hub
transports from Commander Board to rout (before handmade transport into the work).
Transport distance for average the entire route is 3km roads type third. Including some ways
(by local management) have to pay cost, local’s template into, following based on the actual
acceptance of payment.
3.2.4. Manual handling
All materials and equipment will be transported to the construction site manually. The
distance will be determined case by case.
3.3. Arranging construction worker force and constructing site
- Location of construction site in project’s communes: the specific locations are
selected by construction contractors and these must be approved by the local authorities.
- To ensure the maintenance of equipments, materials and housing for workers, the
temporary buildings include:
+ Indoor warehouse for preserving cement, equipments, electricity materials and
accessories: 1 warehouse/30m2 /per commune
+ Opening warehouse with protecting fence for transformer, medium voltage wires,
constructing tools, beams and anchor wires: 1 warehouse/40m2
/per commune.
+ Temporary house for workers: 1 house/20m2
/per commune
+ Indoor warehouse and temporary house are made of bamboo frame and surrounded
by bamboo mats, their roofs are covered by bamboo mats and oil papers. During constructing
process, domestic water, rain water and leftover water are gathered and released into local
drainage network through temporary drain system. All wastes are collected and disposed in
the right places to ensure the hygiene and the beauty of construction site.
9
- To streamline local construction apparatus, local workers will be hired to do manual
works that are not required technical.
- Construction labor force includes 1 construction team/commune. The construction
time: 4 months
One construction team includes:
- Instruction direct : 80 persons.
- Instruction indirect : 05 persons.
- Work Commander Board : 03 persons.
The other auxiliary units coordinate :
- Factory processing steel pole.
- Motor transportation workshop.
- Brand house processing galvanized steel, reinforcing steel and formwork.
3.4. Progress and total investment of project:
3.4.1. Project progress:
Base on demands power supply and ability of Investor force construction progress and
time for work into operation follows:
Preparing the investment : 3 months
Tendering equipment : 2 months
Preparing as-built drawing design : 4 months
Time for test and finish : 1 month
Time execution of the stages the above are arranged alternately with a total time of
project implementation and completion of construction and commissioning of 9 months.
Then 72 hours of commissioning new safety works are put into official operation.
3.4.2. Project total investment:
Table 3.3. Total investment of project
No. Capital Investment Capital
01 Construction cost 28,406,481,000
02 Equipment cost 3,052,574,000
03 Arrangement Site Clearance Cost 10,450,442,000
04 Project management cost 625,274,000
05 Project construction investment Consulting
cost 2,226,315,000
06 Other cost 3,151,377,000
07 Contingently cost 9,324,492,000
Total 157,478,000,000
10
IV. SUMMARY OF NATURAL AND ENVIRONMENTAL CONDITIONS
PROJECT’S AREA
4.1. Geographical geological conditions
4.1.1. Geographical location:
Hung Yen is located in the central the northern plain, in the northern key economic
sectors. The Northern is near Bac Ninh Province. The East side is near Hai Duong province.
The Southern is near Thai Binh Province. The West is near Hanoi city. The South west is
near Ha Nam Province. Have 10 districts with 161 communes, wards and townships.
My Hao district is a northern plain, the northern is near Venal district, the west is near
Yen Mỹ district, the southern is near An Thi district, all of Hung yen Province. East is near
districts of HaiDuong: Cam Giang (northern east) Binh Giang district (southern east). Natural
area of My Hao district is 79.1 km ². The district has 12 communes and 1 town. Ke Sat River
located on the border with Binh Giang district of Hai Duong province. Also in the district
also have Ban River, Bac Hung Hai River, and Cam Xa River through dowsing. 110 KV lines
Hai Duong – Pho Noi (sub line on Hung Yen province) mainly go on paddy land of 4
communes of Hoa Phong, Duong Quang, Cam Xa and Nhan Hoa commune, My Hao District.
4.1.2. Topography and geomorphology
Line 110kV Hai Duong - Pho (subline on Hung Yen province) to the low-lying terrain
plain belonging My Hao district, Hung Yen province. Land of the terrain types are mainly:
Lightning, Asian sand, clay ... derived accumulation Waterfront (amQ).
4.1.3. Geological
Hydro geological conditions
Based on the survey documents along geological sections. During the 2010 survey 04
months of stability of underground water at a depth of 0.6 ~ 1.5 m. Predicts the highest water
level stabilized at depths from 0.0 0.6 m. According to experimental data with calculated
groundwater intrusion weak (Ia) according to TCVN 3994-85.
Dynamic geological conditions – earthquakes
According to the earthquake zone map on the territory of Vietnam, by the Center for
Natural Science and the National Technology established in 1995, the area of control sections
located in the earthquake may occur at level 7 8 .
4.2. Meteorological conditions
110kV Hai Duong – Pho Noi line, sub line VT55 - DC pass through the flat plains of My
Hao district, Hung Yen province
Lines lie completely within the influence of climate, hydrology northern plain. Basically
tropical monsoon, winter cold, summer is hot and humid and rainy.
Through the Hydro meteorological monitoring data with frequency 2% years showed:
Average air temperature in a year, about 23.50 C. Maximum temperature can reach up to
41.50 C, the lowest possible temperature drops below 30C. The average humidity in about
84%.
4.3. Traffic
The district has very favorable position, on many important traffic hub of the area:
Highway No. 5 from Hanoi, pass Ban Yen Nhan town, passes through district to Hai
Duong province. Highway No 39 from junction with Highway No 5 at Ban Yen Nhan town
11
of Hung Yen town, then to ThaiBinh province. The East has highway No 38, cut with
Highway No 5 with the province of Hai Duong Cam Giang district.
The project area is traffic conditions relatively favorable position of the road 5 to about 0.2
km; it is very convenient for the transportation of materials and equipment.
12
4.4. Describe router:
Table 4.1. Table describes line passing thought territory of administrative ĐDK-110kV Hai
Duong – Pho Noi
Sub line/
length Describe router Present use land Location
Position 55 - G1
length 953.8 m
Beginning from No. 55 has value left
steering angle 06015’ take the field
lines cut through some paddy ditches,
cutting through the plastic inter-
district, Garden wall built Mr Nguyễn
Văn Tranh, Phuc Mieu village, Hoa
Phong commune is 7.5m and passing
through rice fields Mr Dang Dinh Khu
next the plastic inter - district. Route
cut through a 0.4-kV power line, a 35
kV power line and a cable
communication lines. G1 is placed on
the rice fields, at the G1 line drive left
at = 090 16 '20"
Rural land, land
transport,
agricultural land
Phuc Mieu
village, Hoa
Phong
commune, My
Hao district,
Hung Yen
province.
G1 – G2
lenght 1,237.3m
Mainly router passing rice fields,
ditches cut through some thin, cut
through a power line was 10 kV. G2 is
placed on the rice fields of the
outermost lines Pha Lai-Pho Noi 220
kV is 15.2m, in line G2 drivers must
tiles = 450 52 '25 "
Rural land, land
transport,
agricultural land
Phuc Mieu
village, Hoa
Phong
commune, My
Hao district,
Hung Yen
province.
G2 – G3
length 52.6m
Route to the rice fields, pass through
220 kV power lines Pha Lai – Pho Noi
existing, G3 is placed on the rice
fields of the outermost 220 kV power
line-Pha Lai – Pho Noi is a 11m , in
the G3 line left drive = 420 48 '15 "
farm soil, paddy
land
Hoa Phong
commune, My
Hao district,
Hung Yen
province.
G3 – G4
length 1,428.4m
Mainly router passing rice fields,
parallel and the outermost of the 220
kV power line-Pho Noi - Pha Lai is
11m, cut through the banana growing
garden land and ponds Mr Trần Văn
Tranh Duong Xa village, Duong
Quang Commune distance houses
abandoned is 0.5m. Cutting through
the plastic inter-district, An
underground cable, a cable
communication lines, a power line 0.4
kV. G4 is located on the rice fields of
the outermost 220 kV power lines Pho
Noi- Pha Lai is 11m, at the G4 line
Rural land, land
transport,
agricultural land
Hoa Phong
commune, My
Hao district,
Hung Yen
province.
13
Sub line/
length Describe router Present use land Location
right drive is OP = 050 34 '20 "
G4 – G5
length 259.0m
Route to the rice fields, avoid the
pagoda Duong Xa village, Duong
Quang commune, should not go in
parallel with now power lines 220 kV
Pha Lai-Phố Nối, cut through a line 30
meters wide ditch and a small ditch,
cut through a 35 kV power line. G5 is
placed on the rice fields, At the G5
line left drive is = 080 15 '20”
Rural land, land
transport,
agricultural land
Duong Quang
commune, My
Hao district,
Hung Yen
province.
G5 – G6
length 611.3m
Line passing rice fields cut through
some smaller canals, ditches G6 is
placed inside the outermost of the 220
kV power line-Pho Noi - Pha Lai is >
11m, G6 line right drive at OP = 090
30' 15 "
Rural land, land
transport, canals
and paddy land.
Duong Quang
commune, My
Hao district,
Hung Yen
province.
G6 – G7
length 250m
Cross section through the drain line
20m cross cut about 150 m, go left to
the kitchen wall Mr Đặng Văn Hiệu
7.2m, go right to the kitchen wall Mr g
Phan Minh Công, Hieu Duong village,
Duong Quang commune 7.2m, cut
thought plastic inter-district, cut
thought 2 times power line 0.4 kV, cut
thought 2 eucalyptus tree sides of
ditches height 15m, G7 is placed
inside the trench. At G7 left drive
=330 03’ 42”
Rural land, land
transport,
agricultural land,
canals and paddy
land.
Duong Quang
commune, My
Hao district,
Hung Yen
province.
G7 – G8
length 165.6m
Route to the rice fields, G8 is placed
on the rice fields of the outermost 220
kV now power lines Pha Lai-Pho
Noiis 11m, At G8 right drive opr =180
52’ 30”
Rural land, land
transport,
agricultural land,
canals and paddy
land.
Duong Quang
commune, My
Hao district,
Hung Yen
province.
G8 – G9
length 1,084.2m
Rout go parallel and the outermost of
the 220 kV power line-Pho Noi - Pha
Lai is 11m, cutting through some
small ditches, cut thought a power line
0.4 kV. G9 is placed on the rice fields
outside of the phase 220 kV now
power lines Pha Lai-Pho Noiis 11m,
At G9 left drive ỏt =230 22’ 35”
Rural land, land
transport,
agricultural land,
canals and paddy
land.
Duong Quang
commune, My
Hao district,
Hung Yen
province.
G9 – G10 length
86.0m
Routes pass through 220 kV now
power lines Pha Lai-Phố Nối, cut
Rural land, land
transport,
Cam Xa
commune, My
14
Sub line/
length Describe router Present use land Location
through the graveyard, G10 is placed
on the rice fields, at G10 right drive
opr =230 35’ 55”
agricultural land,
canals and paddy
land.
Hao district,
Hung Yen
province.
G10 – G11
length 2,464.5m
Route cuts through paddy fields, go
left and outermost of the 220 kV now
power lines Pha Lai-Pho Noi is 11m,
cut thought 3 times power line 10kV,
an information line cable , a time
plastic inter - district. G11 is placed on
the rice fields outside of the phase 220
kV now power lines Pha Lai-Pho Noi
is 11m, at G11 right drive opr =300
39’ 55”
Rural land, land
transport,
agricultural land,
canals and paddy
land.
Cam Xa
commune, My
Hao district,
Hung Yen
province.
G11–G12
length 46.56m
Routes pass through 220 kV now
power lines Pho Noi – Pha Lai, G12 is
placed on the rice fields, at G12 left
drive ỏt =300 42’ 40”
Paddy land Nhan Hoa
commune, My
Hao district,
Hung Yen
province.
G12 – G13
length 350.3m
Go to the right line, parallel and
outermost of the 220 kV now power
lines Pha Lai-Pho Noi is 11m, cut
across a number of small ditches,
cutting through gardens and ponds
raising chickens, ducks of Ms Nguyễn
Thị Xuân, cut thought 2 power line 35
kV. G13 is placed on the rice fields
outside of the phase 220 kV now
power lines Pha Lai-Pho Noi is 11m,
at G13 right drive opr =200 36’ 40”
Rural land, land
transport,
agricultural land.
Nhan Hoa
commune, My
Hao district,
Hung Yen
province.
G13 – G14
length 159.7m
Rout cut thought 3 power line 35 kV,
Cutting through the overpass Pho Noi
to lạc Đạo, and connected to pole No 3
of now power line 110 kV Kim
Dong(It is G14). At G14 right drive
opr =650 18’ 30”
Rural land, land
transport,
agricultural land.
Nhan Hoa
commune, My
Hao district,
Hung Yen
province.
G14 – G15
lenght 74m
Routes to coincide with 110 kV power
lines Kim Dong and connected to pole
No 2 of now power line 110 kV Kim
Dong(it is G15). At G15 left drive ỏt
=90000’ 00”
Rural land, land
transport,
agricultural land.
Nhan Hoa
commune, My
Hao district,
Hung Yen
province.
G15 –G16-PT
length 70.3m
From G15 to G16 line break angle,
from the G16 line is connected to
110kV the bus bar of 220kV
Rural land, land
transport,
agricultural land,
Nhan Hoa
commune, My
Hao district,
15
Sub line/
length Describe router Present use land Location
substation Pho Noi currently operates.
Vegetation cover and which lines are
mainly rice, the rest is the fruit of
people in the region.
canals and paddy
land, fruit tree
Hung Yen
province.
16
V. IDENTIFICATION OF POTENTIAL IMPACTS OF THE PROJECT
The potential impacts of the project is paid model in the table below:
Table 5.1. Rapid assessment of environmental impacts of the Project
Screening questions Yes No Describe the impact
1.Location of Project:
Project location is near or within
the areas of environmental
sensitivity as well?
Cultural Heritage X The transmission line and substation
will not pass through areas with
cultural and historic value.
The conservation area X
Wetlands X
Forests X
Estuaries X
Buffer zones of protected
areas
X
The nature: bird sanctuary,
mangroves, etc.
X
Rivers and reservoirs X
Canal and Irrigation System X
2. Potential environmental
impacts
Is the project would cause:
- Invasive areas historic / cultural X
- Damaging the ecosystem (eg
sensitive areas or conservation,
national parks, nature reserves, etc.)
X
- Morph landscape waste and
increase
X - Due to clearing a corridor should
be small changes in the landscape
and increase waste but is rated at
low levels and will take the
appropriate measures to limit
- Cutting up trees and vegetation, or
to clean surfaces and stations along
X - Corridor routes only felling the
trees also affect the vegetation line
17
Screening questions Yes No Describe the impact
the corridor? and low trees retained (vegetation
only affected at position to the
foundations, but the area affected is
negligible).
- Change of surface water quality or
flow
X
* Increased water turbidity due to
surface runoff or erosion
X - In the course of construction if the
rainy season without safeguards for
the pole to the foundations, the
erosion can occur and affect the
local flow.
* Waste water from area camps
dumped onto the surface water or
not?
X - Units constructed primarily to lease
houses in so wastewater will be
collected into the general sewage
system.
* Waste water is poured into the
construction of surface water or
not?
X
- It increases the level of dust or
not?
X - Due to the transport of sand, rocks
using transport vehicles should have
caused dust. But is considered
negligible.
- It increases the noise and / or
vibration or not?
X - Due to the transportation of sand
stone materials using transport
vehicles should be making noise. But
is considered negligible.
- Permanent Land Acquisition X -Nhan Hoa Conmmune: 1,046.4m2
Including agricultural land and
wasteland.
-Duong Quang Commune: 1,269.
4m2 Including agricultural land and
wasteland.
- Cam Xa Commune: 433.9m2
Including agricultural land and
wasteland...
- Hoa Phong Commune: 444.7m2
Including agricultural land and
wasteland.
- Temporary Land Acquisition X The area of land occupied
temporarily: 69,525m2. Land used
for the corridor is agricultural land,
wasteland and plantation production
18
Screening questions Yes No Describe the impact
is not land acquisition.
- Are families moving or not? If
yes, how many households?
X
- Resettlement Area Is the area of
environmental sensitivity and / or
culture?
X
- Is there any risk to the spread of
disease from construction workers
to the local population (and vice
versa) does not?
X - All the work will be divided into 02
crews in 04 communes, each team
about 40 people. The total number of
workers on site at the highest point is
about 80 people scattered on the
route but not focused in one place.
Therefore, the spread of disease will
also be limited.
- There are potential conflicts
between construction workers and
local people do not?
X - Construction workers and local
people have different incomes,
lifestyles, and customs, so minor
inconsistencies may have occurred
but will be limited.
- There explosives or chemicals
used in the project?
X
- Previously, there were no
accidents caused by mines or
explosive remnants of war?
X
- Construction projects for
disrupting traffic in the area?
X Because rural roads sparse capital,
time and materials handling
equipment is short (about 1 hour), in
addition to construction materials
(sand, earth, stone ...) used dump
truck should cause the level of the
yoke traffic is not large.
- Construction projects can cause
damage to existing road system
does not?
X - All materials and equipment are
classified for transportation in
accordance with the load of the road,
traffic here is an asphalt road
(Highway 5, provincial roads and
village roads, other inter-communal)
should no effect
- Training of land during
construction does not cause
erosion?
X - Pot round-foundation at each
position normally does not last long
(up to about 1 week), construction
finish each item, but there are two
19
Screening questions Yes No Describe the impact
pole foundation position near the
water canals and the construction
plan will take part in the rainy
season so the erosion is likely to
occur if no preventive measures for
good.
- The project should pave the way
public service is new?
X - The lines along roads so the
existing roads are used.
- The project has caused the fault of
the habitat of flora and fauna not?
X
- The project affects air quality? X - The environmental impact level will
be insignificant because the
transportation will be cover by
canvas
- The project has caused the
accident risks for workers and
communities in the construction
phase do not?
X - Minor impact
- The project has generated
hazardous wastes including PCBs
due to replace the transformer?
X
- The project has caused any risk to
safety and health
(electromagnetism, electric shock,
etc.)?
X - The line and transformer station
are designed and built basing on
current regulation of the electricity
sector, in which the calculations on
the harmful effects of
electromagnetic fields and standards
to ensure electrical safety, operation
safety are done to avoid harm to
human health.
- Sub-projects not related to work
off, oil change equipment, so there is
no risk of intrusion of big oil
environment;
- Electric shock and other electrical
accidents can occur if safety
measures are not sufficient attention.
- The negative impact on other
(specify, if any) X
20
VI. ENVIRONMENTAL MANAGEMENT PLAN
6.1. Mitigation measures
Table 6.1. Mitigation measures applied for the Project
Environmental-
social issues Mitigation measures applied
Responsible
bodies
A. Preparation phase
1. Permanent and
temporary land
acquisition will
impact affected
households and
agriculture
production
- To plan for construction activities after harvesting
season and try to shorten the progress.
- Inform the affected HHs about permanent and
temporary land acquisition.
- Properly compensate for land acquisition and tree
compensation in accordance with the Resettlement
Policy Framework of the DEP project and
Resettlement Plan of the Subproject.
- PMU
- Contractor
2. Impacts on
vegetation cover
as a result of site
clearance (ROW)
- Minimize land clearing by planning for
installation of transmission/distribution lines
above existing vegetation.
- Utilize hand clearing of vegetation if possible.
Save as much vegetation as possible. Careful
manage cutting trees. Cut only tree above 4m
within the ROW.
- Do not burn cleared trees and branches;
- Carry out the safety procedures to prevent hazard
of downing trees.
- Dispose at established dump site.
- During clearing, contact with the affected HHs in
order to mitigate impacts and carry out
compensation.
- PMU
- Contractor
3. Explosive
materials left
from war
- Contract with related army unit to clear the site
from unexploded ordnances left from war.
- Return the ground after the clearance.
- PMU
- Army
- Local
authorities
B. Construction
phase
21
Environmental-
social issues Mitigation measures applied
Responsible
bodies
1. Dust pollution - The contractor is responsible for implementing
the state applicable regulations related to air
quality.
- The contractor will ensure minum dust generation
and no impact on local residents and take proper
measures to control dust generation (for example,
praying water, covering the trucks when carrying
material).
- Material will be covered up during. transportation
to prevent scattering of material along the way.
- Material dump site and storage yards will be
covered up and isolated from winds and located
away from schools and residential areas.
- Workers will be provided with masks when
working in high risk areas.
- Contractor
- CSC
2. Air pollution - All transportation vehicles must comply with
applicable regulations of Vietnam with regards to
exhaust gases.
- Transportation vehicles in must be tested
frequently on the waste gases and have to show
certificate of quality, technical safety and
environmental friendliness according to Decision
No.35/2005/QD-BGTVT.
- Do not burn waste or construction materials at the
site.
- Contractor
- CSC
3. Noise and
vibration level
- The contractor will be responsible for complying
with applicable regulations related to permitted
noise and vibration levels.
- All transportation vehicles need to show
certificate of quality, technical safety and
environmental friendliness according to the
Decision No.35/2005/QD-BGTVT; to prevent
excessive noise level from machinery that is not
properly maintained, proper noise reduction
measures are taken, including noise reducers or
arrangement of noisy machinery in a specific
noise proof area.
- To prevent or reduce traffic in residential area as
well as processing of material in residential areas
(concrete mixing)
- Contractor
- CSC
22
Environmental-
social issues Mitigation measures applied
Responsible
bodies
4. Waste water
pollution
- The contractor will be responsible for complying
with applicable regulations related to waste water
treatment and discharge.
- To provide mobile toilets or construct proper
toilets for workers at the site. Toilet waste water
and restaurants will be treated before discharging
into the outside environment.
- When construction is completed, toilets have to
be properly destroyed and/or removed.
- Contractor
- CSC
5. Water drainage
and
sedimentation
control
- The contractor will comply with the water
drainage system design to prevent rain drop from
causing local inundation, soil erosion in high risk
areas.
- To ensure proper operation of the drainage
system.
- To sustain those areas not impacted by
construction activities.
- The excavation work needs to be done in
compliance with applicable technical construction
regulations.
- To prevent the spreading of mud into surrounding
environment, take proper measures to control
sedimentation in high risk areas.
- When there is a need to dry construction site
(foundation concrete pouring), the pumped water
containing sand will be controlled with regards to
sedimentation before discharging it into outside
water bodies.
- Use diversion techniques at construction to
prevent deposit from being stirred up in water
bodies.
- Contractor
- CSC
6. Material
warehouse and
material quarry
management
- Material storage yards will be predetermined in
the approved engineering design.
- Material supplied by local suppliers need to have
operation licenses for particular material type.
- To rehabilitate material storage yard after
construction is completed.
- Contractor
- CSC
7. Waste and
hazardous waste
- Prior to construction, the contractor needs to
prepare a procedure for controlling waste
(storage, use of recycle bins, site
- Contractor
- CSC
23
Environmental-
social issues Mitigation measures applied
Responsible
bodies
decommissioning, etc.) and strictly complying
during construction phase.
- Prior to construction, all necessary licenses have
to be obtained related to waste management.
- Proper measures are taken to ensure good
practices in waste management and treatment.
The contractor will provide recycle bins,
containers and other means to collect waste from
necessary areas.
- Waste can be stored temporarily at the site when
it is approved by the Construction Monitoring
Consultant, local authorities before collection and
treatment. If in the absence of such authorities,
normal domestic waste can be land filled.
- Recycle bins or containers storing waste have to
be covered up from weather impacts and intrusion
by scavengers. Do not burn waste.
- Recyclable waste such as wood form, waste steel
and packing material will be collected and
separated at the site from other waste sources for
reuse, refilling or sale to an external company.
- If it is impossible to carry away from the site,
solid waste can be land filled at a certain place
approved by the construction supervising
consultant provide in the waste management plan.
Under any circumstance, the contractor has to
treat all construction waste within the site.
- Waste lubricants will be taken out from the site
by an authorized recycling company.
- Waste lubricants and cleaning solutions will be
collected into covered containers and carried
away by a contracted external company that is
permitted to treat hazardous waste
8. Site clearance - The contractor will prepare a plan on site
clearance and vegetation recovery according to
applicable regulations for the construction
supervising consultant to approve. The contractor
will strictly comply with this plan.
- Do not use chemicals in clearing vegetation.
- Do not cut down any trees when it is not provided
in the vegetation clearance plan.
- Contractor
- CSC
24
Environmental-
social issues Mitigation measures applied
Responsible
bodies
- If necessary, set up temporary fence to protect
valuable trees prior to starting any construction
activities.
9. Traffic
management
- Prior to construction, conduct consultation with
local authorities and traffic police.
- Impacts on traffic flow needs to be considered in
the construction plan before approval. Traffic
routes, particularly those with heavy duty vehicles
need to consider high risk area such as schools,
hospitals or markets.
- It is necessary to provide sufficient lighting
system for night time to ensure proper traffic
conditions.
- Arrange indication signs at the construction site to
inform public people, provide instructions to
different components and instructions and safety
directions.
- Take proper traffic safety measures including sign
posts and flags to indicate danger
- Do not transport material during peak house.
- Space spared for walkers and vehicles at the site
need to be separate from the site and can be easily
accessible. Provide proper sing posts where
necessary.
- Contractor
- CSC
10. Interruption of
utility and
business services
- Planned or unplanned interruptions to services
such as water, gas power supply and internet
access: The contractor will be prepared for
emergency scenarios and any potential failures.
- Cooperate with services suppliers (water,
telecommunications, etc.) to work out a proper
construction schedule.
- During the laying out of cables crossing over
telecommunications cable, mitigation measures
have to be taken (What are the measures?)
- Notify affected households of construction
schedule as well as expected interruptions (at
least 5 days in advance)
- Interruptions to water supply for agriculture
production need to be avoided.
- The contractor will ensure alternative water
supply for affected residents in case it is more
- Contractor
- CSC
- PMU
25
Environmental-
social issues Mitigation measures applied
Responsible
bodies
than one day.
- Any damage to the existing service cables will be
notified to the local authorities for timely repair.
11. Rehabilitation of
affected areas
- Clearance areas such as soil or rock quarries,
waste treatment areas, worker houses, warehouse
and wood forms and any other temporary areas
during construction phase will be rehabilitated
with regards to the landscape and vegetation
cover.
- Compensate the vegetation cover at the soonest.
Use proper vegetation for such rehabilitation.
- Do not use exotic or banned vegetation for such
rehabilitation
- Excavated hillsides and waste yard need to be
planted with grass to prevent soil erosion and
landslide;
- All the affected areas will be compensated with
proper landscape and there should be no delay in
doing so, including any necessary repair or
construction of green space and other affected
areas.
- Soil contaminated with chemicals or hazardous
waste will be carried away and land filled in a
proper hazardous dump site
- Rehabilitate all affected roads and bridges due to
the project construction
- Contractor
- CSC
12. Labor and public
safety
- The contractor will comply with all applicable
regulations related to labor safety.
- Prepare and implement action plan in response to
risk and emergency cases.
- Prepare emergency services right at the site.
- Provide training for workers on labor safety
requirements.
- Ensure to provide protective devices for workers,
including noise protection at high risk places
- In destroying existing structures, workers and
community need to be protected from falling
objects by taking proper protection measures
- Provide protective fences and warnings of danger
at the construction site to indicate danger to local
- Contractor
- CSC
26
Environmental-
social issues Mitigation measures applied
Responsible
bodies
resident.
- The contractor will provide safety measures such
as installation of fences, provision of warning
signs at high risk areas, including pole foundation
under construction to prevent traffic accidents as
well as other risk to local residents.
- Only allow trained workers to install, maintain or
repair electrical equipment.
- Cut off and do correct earthling for the existing
power line prior to construction work.
- Comply with labor safety procedures when
working at height and with electrical equipment
13. Communications
to local
community
- Sustain communications to local authorities and
community; the contractor will work with local
authorities to agree on construction schedule for
sites near sensitive areas or at sensitive time
(regional festivals).
- Enhance relationship with local community in
order to obtain necessary information about the
project activities in the region, progress and
performance;
- Keep track of the community concerns and
information required such as project progress;
- Respond to community concerns via telephones
and documents in a timely manner;
- Notify local residents of construction schedule,
work schedule, potential interruptions to services
and detour roads and temporary buses, any
destruction or mine explosion schedule;
- Provide technical data and drawings for
community, particularly a scheme on construction
sites and EMP;
- Provide notice boards at all sites to provide
information about the site manager,
environmental officer, medical and safety officer,
with concrete contact details and other
information so that affected people will be able to
raise their voice and concerns.
- Contractor
- CSC
- PMU
14. Chance find
procedures
During construction phase if the contractor finds any
cultural and historical sites, including commentary or
tombs, the contractor will:
- Contractor
- CSC
27
Environmental-
social issues Mitigation measures applied
Responsible
bodies
- Stop construction activities in the particular area;
- Protect the area from any damage or loss to the
sites. In case the historical objects can be
removed or sensitive objects assign a person to
protect it until local authorities come to confirm
and take over the issue;
- Notify the construction supervising consultant,
who will be responsible for informing local
authorities or the state agencies of such cultural or
historical sites (within 24 hours or less);
- Local authorities or state agencies will be
responsible for protecting and isolating such area
before any further processing.
- Decide how to process such issues is the
responsibility of the local authorities, including
change, (in case a cultural or historical site is
found and cannot be removed), reservation,
isolation, rehabilitation and rescue;
- If the cultural or historical site are of high value
and the reservation is recommended by relevant
agencies the project owner will have to change
project design accordingly for the component in
that particular area;
- Decisions related to the management of found
sites will be notified in writing to relevant
authorities;
- Construction work will continue only after
relevant authorities come and take responsibility
of potential sites.
- PMU
C.Operation phase
1. Health and safety
for workers and local
residents
- Disseminate the information on electricity safety
regulations to the users.
- Comply Decree No. 106/2005/ND-CP dated 17
August 2005 of Goverment on protecting grid;
Decree No. 81/2009/ND-CP dated 12 October
2009 of Goverment on protecting hight voltage
grid
- Regular training for local technicians and people
on safety issues.
- Use warning signs, barriers (locks, gates, iron
barriers...) around substation or tower to prevent
- NPC
28
Environmental-
social issues Mitigation measures applied
Responsible
bodies
people reach danger equipment;
- Putting warning signs, barriers on the ground
close to electricity wire to prevent electric shock
- 2. Fire and
explosion
- Periodically inspect fire prevention and fighting
facilities.
- Organize training on fire prevention and fighting
for operation workers.
- NPC
3.Transmisison line -
Mitigation measures
related to
transmission lines
- Only allow workers who have been trained and
obtained certificates on installation, maintenance
and repair of electrical equipment
- Cut off power and provide safe earthling before
construction on the power line or where it is near
power line
- Ensure operations related to power line will be
undertaken by trained workers with strict
compliance with safety regulations. Qualified or
trained workers to operate power lines need to able
to:
- Distinguish between online and offline power lines
from other parts of the distribution system
- Determine voltage of online power lines
- Understand safety distance for each cable types
- Ensure correct and sufficient use of safety devices
and other safety procedures or other online parts of
the distribution system
- Even when being trained, workers will not contact
any online parts unless:
- Workers have been safely isolated from online
parts via gloves or other insulation devices
- Online parts have been safely isolated from
workers and other parts or
- Workers have been isolated and safely insulated
from online objects
- When operations and maintenance request
minimum distance, provide trainings on safety
measures and safety devices for individuals and
other preventive measures identified in the health
and safety compliance plan. (Below is the
recommended safety distance for workers:
- NPC
29
Environmental-
social issues Mitigation measures applied
Responsible
bodies
o 2-15 kV: 0.6 m
o 15.1-35kV: 0.71 m
o 72.6-121 kV: 1.01 m
4.Safety measures
when working at
height
Preventive and control measures include:
- Check the firmness of structures before starting
work
- Take anti-fall measures including climbing skills,
use of supporting devices and first aid toolkit
- Install supporting and anti-fall devices
- Safety bands will not be smaller than 16 mm, two
layers, and durable strength. Safety bands will be
replaced before any defect or crack is detected or if
is too old
- When working with tools at height, workers will
need an additional safely band (backup).
- Sign posts and other obstacles need to be removed
before starting work
- Use standard tool bag to carry tools and materials
to the height when working on pillars
- NPC
5. EMF impacts - Prevent or minimize exposure to EMF in the
working environment by developing and
implementing a EMF safety program with the
following components:
- Determination of potential exposure level
- Trainings for workers on how to identify their
exposure to EMF and its impacts
- Determination of safe areas in order to
differentiate those areas with higher EMF impacts
than the others where EMF impacts are small
enough not to be provided with mitigations and
minimize exposure to high EMF impact areas
- The exposure detector for individuals will be
installed to give warning when exposure is below
the safety limit (for example, 50%). Action plans
for mitigating impacts includes taking turn to work
in high risk areas, and if necessary being provided
with protective devices.
- NPC
30
6.2. Measures to minimize the specific impact of this project
Table 6.2. Measures to minimize the site specific impact of this project
Environmental-social issues Mitigation measures applied
- Location of transformer and medium-
voltage lines passing through rice
fields, forested hills and some canals
will affect the public drainage,
irrigation system if no any mitigation
measures are provided during
construction
- Before construction, workers will
be reminded not to leave rock and
soil fill up the canals drainage
systems, and field irrigation system.
- Safety construction measures shall
be carefully studied in order to not
impact to the existing irrigation
system.
- Materials and refuses must be
removed to reinstate the landscape
and environment after completion
of construction.
6.3. Environmental monitoring plan
Table 6.3. Environmental monitoring plan
Impact Monitored
parameter
Monitored
point
Monitoring
equipment
/method
Timing/
frequency of
monitoring
Responsibility
Construction phase
I.
Vegetation
cover
clearance or
cutting
down trees
-Clearance
technique
- Disposal of
cut-down trees.
- Along the
transmission
line
- In a
centralized
place for
processing.
Observation -From
beginning to
the last
moment.
-Contractor
-Construction
supervising
consultant
I I. Rural
roads in the
project
region
- All heavy
tonnage
vehicles on the
local roads
- Along the
roads
Observation
and
consultation
with local
residents.
-Weekly basis
when material
is transported
to the region.
- Four months.
- Contractor,
-Construction
supervising
consultant
III. Surface
water
quality,
- Not excavate
while it is
raining
- Surface
water near
the site.
Observation -During and
after heavy
rain
-Contractor,
-Construction
supervising
31
Impact Monitored
parameter
Monitored
point
Monitoring
equipment
/method
Timing/
frequency of
monitoring
Responsibility
sedimentati
on and
erosion
- Not clear
plants
completely
consultant
IV. Dust
and air
pollution
- Dust
concentration
in material
storage area
- Cover for
material during
transportation
process
- Areas with
excavation
foils and
material
storage
Observation -In presence of
strong winds
-Contractor,
-Construction
supervising
consultant
V. Noise
level
- Noise by
machinery
- Local
resident
response to
noise from the
construction
process
- The line
section
running over
residental
area
Consultatio
n with local
residents
-During
activities that
may result in
high noise
level;
Complaints by
local residents
-Contractor,
-Construction
supervising
consultant
VI. The
culture and
history
monuments
- The effects of
noise
-At the
construction
places close
to culture and
history
monuments
Observing
the local
residents
-During
construction,
the activities
emanate noise
-Contractors
-Construction
monitoring
consultant
VII.
Sanitation
situation at
the
construction
site,
including
the hygiene
of workers’
camps
-Garbage,
waste water at
the
construction
site and
workers’ tents
- If he tents
have been
supplied clean
water and had
sanitary
latrines
-At the tents Observing -Every week,
when official
acceptance of
work
-Contractors
-Construction
monitoring
consultant
VII. Safety
of workers
and local
- Accidents
happen
- At the sites,
local areas
- Consult,
Record the
constructio
-Contractors
-Construction
32
Impact Monitored
parameter
Monitored
point
Monitoring
equipment
/method
Timing/
frequency of
monitoring
Responsibility
presidents n log of the
contractor
monitoring
consultant
Operation phase
I. Maintain
and protect
the ROW
The height of
plants along
the ROW
Along the
ROW, houses
and trees
Prune trees
and ensure a
safe
distance for
the ROW
One month/
time
North High
Voltage grid
Company
II. Danger
due to
danger
-The intact
situation of
poles,
insulators,
protecting
devices of the
station
- At the pole
of the line
route, the
position of
the station
- Observing
and
assessing
3months/
time
-North high
voltage grid
Company
VII. EMP IMPLEMENTATION ARRANGEMENT AND CAPACITY BUILDING
7.1. Responsibilities for Implementing the Environmental Management Plan
Non-compliance by the contractor could result in suspension of works, financial
penalties, or other penalties, as must be clearly spelled out in the EMP and in the contract.
Contractors are responsible for implementation of EMP. The responsibilities for
monitoring EMP implementation are typically shared between the contractor, the PMU, and
the Construction Supervision Consultant (CSC). The Contractor’s Work Plan should
incorporate the guidelines provided in the EMP created for the subproject. The designated
Technical Officer(s) and Safeguards Officer(s) of the PMU are responsible for supervising
the adherence to the agreed EMP by the selected contractor(s). The World Bank may
periodically supervise implementation activities of the subproject.
At a minimum, the contractor should prepare a monthly report on adherence to EMP
which should be submitted to the CSC and to the PMU. Subproject-specific or contract-
specific reporting requirements are described in the EMP. CSC is responsible for monitoring
overall environmental performance of the project and submit to PMUs quarterly monitoring
reports.
To ensure effective implementation of the EMP, the following actions will be carried out
during the implementation of the subproject
7.1.1 During Detailed Design and Preparation of Bidding Contract Documents
During the detailed design and bidding invitation preparation, the project management
unit will be responsible for incorporate the EMP (mitigation measures, responsibilities of the
contractor) into the attached annexes in the bidding invitation and contract signed with the
33
contractor. Engineers taking charge of the detailed design will also refer to findings in the
EIA and EMP to ensure environmental issues will be looked at in the final design.
During the bidding invitation preparation and the contract, it is necessary to ensure the
contractor is fully informed of its responsibilities in implementing environmental mitigation
measures and its commitment to compliance.
7.1.1. Construction phase:
PMU will assign the Construction Supervising Consultant (CSC) and/or field engineer
to be responsible for supervision of safeguard performance of contractor on a daily basis. A
generic Terms of Reference (TOR) is provided in Annex 1. CSC and/or field engineers will
carry out, but not limited to, the following tasks:
- Before the commencement of the construction, confirm that all compensation for land
and facilities are provided and relocation and/or land acquisition/donation has been
completed.
- Closely supervise the implementation of safeguard measures throughout the
construction period.
- Confirm the compliance with the EMP and inspect for any damages caused by the
contractor. If necessary, prepare a minutes to ask the contractor to compensate or
rehabilitate as provisions of the contract. Contractor safeguard performance will be
included in the subproject progress report.
Role and responsibilities of parties in implementing EMP are summarized in the below table
Table 7.1. Responsibility for EMP Implementation
Role Responsibility Organization
- Project
owner
- Take final responsibility with regards to the
management and implementation of project including
environmental compliance environmental
performance.
-North
Electricity
Corporation
- Environme
ntal officer
- Indicate specific responsibility and provide contact
details.
Environmental
officer of
project
34
Role Responsibility Organization
- Project
manageme
nt and
implement
ation entity
Responsible for cooperating and managing the
implementation of project including providing guidance
and implementing the EMP:
- Develop plan and implement EMP activities during
construction.
- Cooperate with relevant stakeholders with regards to
environmental performance.
- Conduct internal supervision and independent audit.
- Supervise and provide budget for monitoring
activities.
- Report environmental information to relevant
stakeholders.
PMU
- Project
operation
entity
- Operating the project including environmental
management and supervision during operation phase.
North High
Voltage Grid
Company
- Contractor
supervisor
- Support the PMU in supervising project operations
with regards to environmental impacts mitigation
according to measures described in the EMP and keep
in touch with local residents.
Construction
supervising
consultant
hired by the
PMU
- Contractor Constructing and complying with technical requirements of
the EMP, including:
- Taking mitigation measures to minimize negative
impacts as described in the EMP.
- Communicating with local residents and taking action
to prevent environmental and social interruptions in
the project region during construction.
- Ensuring at least one officer supervises compliance to
EMP during construction.
- Ensuring all construction activities are given
necessary approvals from relevant authorities.
- Ensuring workers and officers understand their
responsibilities and procedures in environmental
management.
- Reporting to the construction supervising consultant
on difficulties and solutions.
- Reporting to local authorities and PMU and
cooperating with relevant agencies to address any
issues.
Construction
supervising
consultant
hired by the
PMU
35
7.2. Building the EMP implementation capacity
Training plan in the coming time includes:
EVN’s training program: Internal training courses on the implementation of
environmental management work at site, the preparation of reports on the Project
environmental issues as a part of half-yearly and annual reports. The program will
also provide training on environmental impact mitigation measures which
unexpectedly occur and differ with forecasts stated in the EMP report.
Northern Power Corporation’s training program: NPC’s training program
provided to the local power company’s staff and some local people is about:
Training on safety work: Periodically training on the safety work and power
network maintenance;
Supervision method and report EMP implementation to stakeholders in the
province and the districts where the Project is located. The training work will also
provide guidance’s on the coordination with the people in the environmental
management work;
Table 7.2.Estimates of capacity building for implementing EMP
No. Training contents Participants Unit Amount
1 Annual training of EVN
for all of its subsidiaries
3 persons from the PMU of
NPC, participating in 2days
5,000,000 đ 30,000,000 đ
2 Training and exchanging
experience in
implementing
environment
management plan and the
Environmental
Management Plan
2 persons from the PMU of
NPC, participating in 2days
5,000,000 đ 20,000,000 đ
3 Training on the EMP
implementation
2 persons from NHPNC,
participating in 2 days
5,000,000 đ 20,000,000 đ
4 Training on the EMP
enforcement for local
officers
1 person/commune x 4
communes
1 person/district x 1 districts,
participating in a day
500,000 đ 2,500,000 đ
5 Training for site
commanders
80 persons participating in a
day
300,000 đ 24,000,000 đ
Total 96,500,000 đ
36
7.2 Reporting procedure
Responsibility and frequency of reporting on EMP implementation are shown
the below table.
N
o.
Report by Submitted to Frequency of reporting
1 By contractor to project owner PMU Once prior to starting
construction afterwards
every one month.
2 Construction supervisor (cum
environmental monitor)
PMU Monthly
3 Community supervisor (if any) MPU If any complaint
4 PMU EVN Quarterly
5 EVN WB Biannually
7.3. Estimated cost for implementing the EMP
Estimated cost for (i) implementing main mitigation measures (ii) and trainings:
No. Description Construction phase Operation phase
01 Mitigation measures. Under the contract with the
contractor
Under the production
cost of province
electricity
02 Environmental monitoring during
construction phase (incorporated
into the cost of construction
supervising consultant).
Under the cost for PMU
operation (Supervising
consultant will exercise
independent monitoring)
Under the cost of the
project owner operation
03 Training on environmental
management by project investor
for local officers, contractor and
supervising consultant.
96,000,000 VND Capacity building need
assessment (trainings,
workshops and study
tours)
TOTAL COST: 96,000,000 VND
* The cost for mitigation measures during the construction phase and
environmental monitoring by the supervising consultant will be included in the
construction supervising contract.
37
VIII. CONSULTATION AND DISCLOSURE OF INFORMATION
In the subproject preparation phase (the year of 2011), the following five activities
were carried out:
Activity 1: Surveying the site, working with the local authorities to discuss the route
and the substation locations.
Activity 2: Surveying the site and preparing the EPC and the EMP reports.
Activity 3: Conducting public consultation on the subproject.
From May 16th
, 2011 to May 19th
, 2011, a meeting with local residents in 04
communes was organized in order to consult with the public on the EMP, the representatives
of the Subproject Owner were also involved the following contents:
- Describing the subproject, the route, thesubstation locations, and the necessity for
the subproject;
- The potential impacts on the environment and communities;
-The measures to mitigate environmental impacts.
Participants: Participants of the Commune People Committee, Farmer Association, Women
Association , and other public organizations, hamlet chiefs, representatives of project’s
affected households, and consulting agency.
Table8.1 Summery consult public
No District/ Commune Time People
I My Hao District
1 Hoa Phong Commune 16/05/2011 18
2 Cam Xa Commune 17/05/2011 18
3 Nhan Hoa Commune 18/05/2011 18
4 Duong Quang Commune 19/05/2011 18
Summary of comments from the participants:
- All local people agreed to implement the Project. However, they required quick
construction, limited delay, prolong extension and cleaniness for environment and
work quality.
- The ROW which has been chosen suitable is proper and convenient for construction
work. The line route was chosen to minimize the negative impacts;
- The land occupation and pruning of trees are considered and reduced to a
minimum. Therefore, the long term adverse effects on the environment will not occur;
- Local people have three main concerns to the project’s environment issue. The first
one is that the damages which are due to tree felling, land acquisition are
compensated or not. The second one is that who will be responsible for monitoring
the implementation of mitigation measures, in some previous projects, the Contractor
had promised to implement mitigation measures, but in fact they did not do. The last
38
one is the role of local communities in the implementation of mitigation measures,
especially in monitoring the implementation of mitigation measures. About the
potential impact of sub-project on the environment, local people emphasized the
impact which involves felling trees, occupied land and village roads.
- The Consultant and the Contractor must select the appropriate time for construction
phase to minimize the crop affect, to avoid damage or degradation on the roads, to
avoid traffic jams. The construction space should be allocated appropriately to
minimize the impact on daily life impact of local people;
- Once the construction is completed, the contractor shall rehabilitate the site and return
the original landscape.
- The local government always volunteers to cooperation with the Project owner and
the Contractor in environmental supervision and management activities;
- The citizens and local governments expect that sub-project is constructed and
operated as soon as possible.
The summary of meeting with local residents, minute of stakeholder consultation
meeting and some photos about the meeting attached in Annex 6.
All relevant issues as well as comments by the local residents have been taken into
account by the supervising consultant and the project owner and shall include them in the
design of the project and EMP implementation.
Activity 4: Review and correct the EMP in accordance with the
comments. Continuing to receive feedback from the affected households. To collect opinions
of the people to complete the environmental impact mitigation measures in the EPC and
EMP.
Activity 5:Disclosure of the EMP
The EMP will be translated into Vietnamese and disclosed in the country at PMU, as
well as in Hung Yen province, and the subproject areas.
The EMP copies in Vietnamese and English will be sent to the Vietnam Development
Information Center at 63 Ly Thai To street, Hanoi City for disclosure of information.The
EMP copies in English will also be disclosed in the Infoshop of the World Bank.
39
REFERIENCES
1 Compensation Plan of the Project
2 World Bank Environmental Assessment Source Book
3 Statistical Yearbook 2010 - Statistical Publisher
4 Project investment report
5 Framework for Applying Environment Safeguards to RD Project- WB.
40
ANNEX 1
TERMS OF REFERENCES FOR MONITORING OF EMP IMPLEMENTATION
FOR CONSTRUCTION SUPERVISING CONSULTANT
Background
The construction supervising consultant will deliver technical services (“Services”) to ensure
efficient implementation of the EMP for the project.
Scope of services:
Services provided by the supervising consultant will include reviewing and monitoring of
construction activities to ensure mitigation measures described in the EMP for the project are
correctly complied with and negative environmental impacts are minimized.
On behalf of the PMU, supervising consultant undertakes the following duties:
- Conduct frequent field inspection;
- Review the implementation of environmental protection measures described in the EMP
and contract documentation;
- Review the effectiveness of the mitigation measures and environmental performance of
the project;
- If necessary, validate the acceptability of construction methods with regards to
environmental compliance (for temporary and permanent items), relevant design plans
and other submitted documents. If necessary, the supervising consultant will seek for and
recommend methods with less environmental impacts with consultation with the design
consultant and the PMU;
- Validate inspection results with regards to any non-conformance to environmental
performance and effectiveness of any countermeasures;
- Provide audit results for the leading engineer of the contractor in accordance with non-
conformance handling procedure described in the EMP;
- Direct the contractor to take corrective actions within a specific time period and exercise
additional monitoring if necessary, as per the requirements of the contract in case of non-
conformance and complaints;
- Direct the contractor to take actions to mitigate impacts and comply with the EMP in case
non-conformance is found;
- Direct the contractor to stop any activity resulting negative impacts and/or in case the
contractor does not fulfill requirements of the EMP, to take corrective actions.
- For contracts that need Site Environmental Management Plan (SEMP), the
supervising consultant will conduct a final review and approve all environmental plans at
the site that may affect environment. This work includes but not limited to: dredging
areas, material quarries and dumping areas and worker houses. The supervising
consultant will review and approve such SEMP submitted by the contractor. If such plans
are found non-compliant to the EMP, EPC or RAP, the supervising consultant will work
with the PMU and contractor for a proper solution.
- Complaint handling: Complaints from local residents will be collected by site officer of
the contractor, which may include violations to noise level, dust concentration and traffic
41
safety requirements. The lead consultant of the contractor and the supervising consultant
will address and work out a final solution organizes all such complaints. The supervising
consultant will provide a list of these complaints and confirm they have been properly
handled by the contractor in the same way with issued identified during site inspection.
- Confirmation of monthly payment: The supervising consultant will confirm monthly
payment for environment related activities undertaken by the contractor.
- Report: The supervising consultant will make the following reports in English:
o Report twice a week on non-conformances
o Monthly summary report will include issues and findings from the reviewing
and monitoring of construction activities
o At the end of project, the supervising consultant will make a final summary
report on findings from their work, number of violations, and solutions, etc. as
well as provide consultancy and guidance on how to implement such duties in
future.
42
ANNEX 2
------------
Report template for monitoring of EMP implementation
(Used for report by supervising consultant to PMU)
Project name:
Project location: Province: District:
Commune/Town:
Supervising consultant:......Full name Date of report:……………………
No. Parameter
Assessment of
comments by
supervising
consultant and
community
Comment/
Recommenda
tion
Construction phase
1 Water turbidity and soil erosion
2 Noise level at the site and nearby
residential area
3 Dust concentration
4 Solid waste and site cleaning after
construction
5 Conflict between workers and local
residents
6 Disease spreading
7 Hygiene condition and safety for workers
8 Local traffic interruption
9 Road damage
10 Safety measure application
11 Material management
12 Remained soil and rock management
13 Evidences about loss to biodiversity (if
any)
14 Evidences about loss to cultural and
43
No. Parameter
Assessment of
comments by
supervising
consultant and
community
Comment/
Recommenda
tion
historical sites
15 Other environmental issues (if any)
….
Operation phase
16 Transmission line lobby maintenance
17 1. Health and safety for operation
workers and local residents
44
ANNEX 3: Report template for monitoring of EMP implementation
(Used for reports by contractor)
Project name:
Project location:
Contractor name:
Initial or monthly report:
Date of report:
No. Impact Mitigation
measure taken Comment
Construction phase
1 Surface water pollution
2 Noise and vibration level
3 Soil erosion
4 Air pollution
5 Impacts on agriculture land due to
temporary land acquisition
6 Local traffic interruptions
7 Existing road damage
8 Solid waste from excavation
9 Remained soil management
10 Environmental impacts by workers
11 Conflict between workers and local
residents
12 Disease spreading between workers
and local residents
13 Health and safety
14 …..
Reported by :
Title :
Address :
Telephone
47
ANNEX 6
--------------------
SUMMERY OF MEETING PEOPLE
No Location Time Women/
People
Summery of idea’s
people
Summery of idea’s
contractor
1 Venue of Hoa
Phongcommune
people’s
committee, My
Hao district
16/05/2011 3/18 - Supporting the
construction of
common purpose of
social
- Concerned about
the time of
construction and
method of
compensation for
crops to farmers.
- There wants to be
construction
contractors and
investors
employers at the
local school to
create additional
income for people
in the construction
process.
- Thanks for the
support of the local
population relative
to the project.
- The compensation
of crops affected
people will be
calculated with
love and
rationality.
- Will encourage
construction
contractors use
unskilled workers
locally.
2 Venue of Cam
Xa commune
people’s
committee, My
Hao district My
Hao
17/05/2011 5/18 - Agree with the
construction of 110
kV lines.
- Have a little doubt to
the influence of
electromagnetic
field lines to
people's health.
- Construction
contractors,
regardless of local
practices in the
construction process
to avoid conflicts
between workers
with local people
easy to lead to
unfortunate
- Thanks for the
support of the local
population relative
to the project.
- Design of 110 kV
transmission line
route followed the
standards of the
state power grid
safety standards
including, but
allows the
magnetic field.
Thus the effects of
electromagnetic
fields to citizens is
very small, no
harm to health.
48
No Location Time Women/
People
Summery of idea’s
people
Summery of idea’s
contractor
consequences. - It will be noted
contractor
relationship in
communicating
with local people.
Respect the
customs and
practices of local
people as well as
compliance with
law.
3 Venue of Nhan
Hoa commune
people’s
committee, My
Hao district
18/05/2011 2/18 - Supporting the
construction.
- After the work is
completed and put
into use, the rice
and subsidiary
crops in the area
near the poles are
dangerous to the life
of the people do
not?
- In each village
commune has a
garbage collection
site, the proposal is
waste arising from
the need put to
work right where it
was prescribed.
- During construction,
if damaged roads,
ditches, culverts
must refund to the
original local
- Thanks for the
support of the local
population relative
to the project.
- Apart from the land
for planting
permanent
recovery pole,
people can still
pick normally
implanted in the
soil around the
pole, there is no
danger threatening
the lives of the
people.
- It prompted the
construction units
to the correct
collection places of
local regulations.
In the course of
construction if
damage to the
transportation
works as well as
irrigation repairs
will commit
according to the
original state.
4 Venue of
Duong Quang
commune
19/05/2011 3/18 Supporting the
construction.
- Thanks for the
support of the local
population relative
49
No Location Time Women/
People
Summery of idea’s
people
Summery of idea’s
contractor
people’s
committee, My
Hao district My
Hao
- Very welcome
design unit was
designed to avoid
lines of the village
temple.
- Need to perform
design and
construction lines in
accordance with
safety standard grid.
Ensure network for
people.
- Need a plan to
minimize
construction impact
crop most of her
children primarily
because lines go on
the field?
to the project.
- The design lines are
the investors in
accordance with
approved technical
standards and
safety standards of
the grid.
Construction
process the
investor will be
closely monitored
to ensure
construction
according to the
approved design.
- Time of
construction as
well as
construction
methods will be
calculated to
minimize the
impact on people's
crops. If you have
calculated the
impact will be
compensated for
reasonable people.
51
LIST OF PARTICIPATING COMMUNITY CONSULTATION SESSIONS
(Cam Xa Commune)
Full name Address Signature
1. Pham Thi The– Vice Chairman Ward
2. Dinh Van Phuong – Personnel land
3. Le Thi Thai – Vice Chairman women
4. Ngo Duy Hoang – Chairman of the elderly
5. Dang Thanh Nghe- Chairman of the Veterans
6. Nguyen Thanh Tam– Fatherland Front Chairman
7. Dao Manh Hung– Chairman of the People’s Council
8. Le Thi Minh Khanh– Youth Secretary
9. Dinh Xuan Thuy – Chairman of the farmers...
10. Nguyen Hong Quan– Personnel land
11. Hoang Van Thuy– Vice Youth Secretary
12. Chu Sy Binh– Deputy director of consulting unit
13. Le Thanh Son– Chairman of the project design.
14. Nguyen Xuan Huan– Household is affected
15. Tran Thi Ngung – Household is affected
16. Do Thi Tan – Household is affected
17. Dang Van Quy – Household is affected
18. Nguyen Van Luong – Household is affected
53
LIST OF PARTICIPATING COMMUNITY CONSULTATION SESSIONS
(Hoa Phong Commune)
Full name Address Signature
1. Vu Van Hoa- Vice Chairman of the CPC
2. Tran Quy Huyen – Personnel land
3. Pham Thi Dung– Chairman of the commune Women
4. Hoang Van An – Chairman of the elderly
5. Bui Van Nghiep - Chairman of the Veterans
6. Nguyen Xuan Huan – Fatherland Front Chairman
7. Do Thi Tan– Chairman of the People’s Council
8. Tran Thi Nhung– Youth Secretary
9. Vu Van Thuan– Chairman of the farmers..
10. Nguyen Hong Quang– Personnel land
11. Nguyen Van Thuy– Vice Youth Secretary
12. Chu Sy Binh– Deputy director of consulting unit
13. Le Thanh Son– Chairman of the project design.
14. Dang Dinh Khu– Household is affected
15. Dinh Van Phuong – Household is affected
16. Dang Dinh Vinh – Household is affected
17. Nguyen Hong Vi– Household is affected
18. Trần Văn Nhan– Household is affected
55
LIST OF PARTICIPATING COMMUNITY CONSULTATION SESSIONS
(Nhan Hoa Commune)
Full name Address Signature
1. Nguyen Ba Nam- Chairman of the CPC
2. Nguyen Thanh Trung – Personnel land
3. Le Xuan Thuy – Vice Chairman women
4. Ngo Duy Hoang – Chairman of the elderly
5. Bui Xuan Trung - Chairman of the Veterans
6. Trinh Van Bao – Fatherland Front Chairman
7. Nguyen Trung Kien – Chairman of the People's Council
8. Le Thi Anh – Youth Secretary
9. Dinh Xuan Chung – Chairman of the farmers...
10. Nguyen Ba Hung – Personnel land
11. Hoang Trung Kien – Vice Youth Secretary
12. Chu Sy Binh– Deputy director of consulting unit
13. Le Thanh Son– Chairman of the project design.
14. Vu Van Thuan – Household is affected
15. Bui Van Nghiep – Household is affected
16. Cao Van Khoi – Household is affected
17. Dinh Van Toi – Household is affected
18. Hoàng Văn Ân– Household is affected
57
ST OF PARTICIPATING COMMUNITY CONSULTATION SESSIONS
(Duong Quang Commune)
Full name Address Signature
1. Vu Dinh Huan - Chairman of the CPC
2. Nguyen Huu Phuoc – Personnel land
3. Le Thi Nhien – Vice Chairman women
4. Ngo Van Dinh – Chairman of the elderly
5. Bui Cong Son - Chairman of the Veterans
6. Nguyen Van Than – Fatherland Front Chairman
7. Dao Manh Thang – Chairman of the People's Council
8. Le Thi Thuong – Youth Secretary
9. Dao Le Ngoc – Chairman of the farmers...
10. Nguyen Ba Quang – Personnel land.
11. Hoang Xuan Thuy – Vice Youth Secretary
12. Chu Sy Binh– Deputy director of consulting unit
13. Le Thanh Son– Chairman of the project design.
14. Trieu Van Uy – Household is affected
15. Bui Thi Lai – Household is affected
16. Tran Quy Huyen – Household is affected
17. Nguyen Huu Huynh – Household is affected
18. Nguyen Dang Phuc – Household is affected