Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

34
Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

description

Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013. Background. Australian Treasury is interested in electricity modelling in an economy-wide framework It has used: detailed consultant’s electricity model and - PowerPoint PPT Presentation

Transcript of Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Page 1: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Electricity in the GTAP model

Tony WiskichNational CGE Workshop 2013

Page 2: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Background• Australian Treasury is interested in electricity

modelling in an economy-wide framework • It has used:

– detailed consultant’s electricity model and– embedded Constant Elasticity of Substitution (CET)

production nest between generation technologies.

• Interested in macroeconomic impacts of adjustment in electricity generation

Page 3: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Motivation• NOT to replace detailed bottom-up electricity

model• Provide some insight using an alternative

approach to a CET nest structure based on a competitive electricity market

• Provide some insight into costs of adjustment

Page 4: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Model basics• GTAP model made recursive through simple

capital/investment dynamic• Single region, 8 sectors including electricity

Page 5: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

-1

-0.9

-0.8

-0.7

-0.6

-0.5

-0.4

-0.3

-0.2

-0.1

0

Real GDP impact of a 1% decrease in Labour, Land & Nat Res efficiency

Temporary

Permanent

Page 6: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

-0.45

-0.4

-0.35

-0.3

-0.25

-0.2

-0.15

-0.1

-0.05

0

Real GDP impact of a 1% decrease in Capital stock

Page 7: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Electricity Structure Assumptions

• Profit + Fixed + Variable Costs• Profit = Capital Cost (28%)• Fixed = Labour Cost (13%)• Variable = Intermediate (59%) (+ TAX)• Generators operate in a competitive electricity

market similar to Australia

Page 8: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Base case assumptions• Baseload, Mid and Peak generation• Same rate of return on investment between

generation types & other sectors• Same Fixed Cost per MW (MegaWatt) Capacity• Same Variable costs structure• Small load shedding period (demand > supply)

– Approx 3 hours per year

Page 9: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

M

2M

1Duration

Load Load duration curve

Page 10: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

1

Capacity

Base

Mid

Peak

Duration

Page 11: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

1

Capacity

BaseMidPeakDuration

Page 12: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

1 Time

Price =Marginal Cost

BaseMidPeak

P_Base

P_Mid

P_Peak

Price CAP

Page 13: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

1 Time

Price =Marginal Cost

BaseMidPeak

Base Capital + Fixed (Labour) Costs

Base Variable (Intermediate) Costs

P_Base

P_Mid

P_Peak

Price CAP

Page 14: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Base case assumptions/numbers

Var Cost

Electricity Gen share

Capacity share

Utilisation rate

Rev Share

Marginal generator

time share

Cost to build

per MW

Baseload 1 84.9% 66% 96% 79.3% 33% 1

Mid 1.5 15% 31% 36% 20% 62% 0.33

Peak 2 0.1% 3% 3% 0.7% 5% 0.28

Page 15: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Policy shock

• Introduce electricity output tax on Baseload electricity generation

• Two rates, initial Baseload variable cost = 1– Fast: incremental tax increase of 0.05 per year

• Mobile capital (consider immobile later)

Page 16: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10111213141516171819 20212223242526272829

-100

-90

-80

-70

-60

-50

-40

-30

-20

-10

0

Baseload generation % change

CES (elas=10)ELY

Page 17: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

-100

0

100

200

300

400

500

600

700

Mid,Peak generation % change

Mid&Peak CESMid ELYPeak ELY

Page 18: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Back-of-envelope – ΔPrice• CES: Elasticity 10, approx 80% Base share• Price inc ~ 0.2*((1+0.8/0.2)10/9-1)-0.8 ~ 20%• ELY: Price inc ~ Base_varshare_as_marg_gen*

(Mid_varprice/Base_varprice-1)~14% * 0.5 ~ 7%

Page 19: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

0

2

4

6

8

10

12

14

16

18

20

Electricity price % change

CES (elas=10)ELY

Page 20: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Back-of-envelope - ΔGDP• CES: GDP impact ~

price_inc*ely_cost/GDP*dynamic_adj_factor ~ 20%* 2/56 * 1.5 ~ 1.1%• ELY: Price inc: (extra_var_cost –

cap_savings)/GDP*dynamic_adj_factor ~ (0.9*0.5 – 0.5*2/3)/GDP*dyn ~ 0.12/56*1.5 ~

0.3%

Page 21: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

-1.2

-1

-0.8

-0.6

-0.4

-0.2

0

Real GDP % change

CES (elas=10)ELY

Page 22: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

0

200

400

600

800

1000

1200

GDP cost per Baseload unit reduction

CES (elas=10) ELY

tax

Page 23: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Fixed capital in generation• Baseload Depreciation – 30 years to vanish• No limit on capital increase (build in single

period)• Capital is decommissioned if profits < 0

Slow tax introduction• From 0.05 to 0.02 increment per year

Page 24: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

-100

-90

-80

-70

-60

-50

-40

-30

-20

-10

0

Baseload: Fixed capital, Fast vs Slow tax introduction

fast Profit/MW

fast MW

fast GEN

Page 25: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

-100

-90

-80

-70

-60

-50

-40

-30

-20

-10

0

Fast vs Slow: Baseload MW, Profit/MW , Gen % change

slow profit/MWslow MWslow GENfast Profit/MWfast MWfast GEN

Page 26: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

0

200

400

600

800

1000

1200

GDP Cost: ELY slow vs fast tax

fast tax

slow tax

fast cost

slow cost

Page 27: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 10 20 30 40 50 60 70 80 90 1000

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

GDP cost vs Baseload reduction

Fast CET

Slow CET

% reduction in Baseload Generation

% re

ducti

on in

Rea

l GDP

Page 28: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 10 20 30 40 50 60 70 80 90 1000

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

GDP cost vs Baseload reduction

Fast CET

Slow CET

Fast MOBILECAP

Slow MOBILECAP

% reduction in Baseload Generation

% re

ducti

on in

Rea

l GDP

Page 29: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 10 20 30 40 50 60 70 80 90 1000

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

GDP cost vs Baseload reduction

Fast CET

Slow CET

Fast MOBILECAP

Slow MOBILECAP

Fast FIXCAP

Slow FIXCAP

% reduction in Baseload Generation

% re

ducti

on in

Rea

l GDP

Page 30: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Summing up• Competitive electricity market model can be

done and has different dynamics/costs to CET• Baseload-Mid substitution not Peak• Fixing capital: Adjustment cost depends on speed

of tax introduction– Inefficient capital allocation, merit order switching– Capital decommissioning

Page 31: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Possible further work• Simple international analysis

– based on projected capital/fixed/variable costs– Compare economic costs with CET

• Figure out way of adjusting CET implementation to approximate detailed model

• Intermittent generation

Page 32: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

Extra slides

Tony Wiskich2013 conference

Page 33: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 1112 13 1415 16 1718 1920 21 2223 24 2526 27 2829

0

200

400

600

800

1000

1200

GDP Cost: CES slow vs fast tax

fast CES

slow CES

fast tax

slow tax

Page 34: Electricity in the GTAP model Tony Wiskich National CGE Workshop 2013

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

0

200

400

600

800

1000

1200

GDP Cost: CES slow vs fast tax

fast CES

slow CES

fast ELY

slow ELY

fast tax

slow tax