Electrical Snags Updated

7
Hi-LITE Mall -ELECTRICAL Incomplete Location Issue 1 Sub station 2 D.G room 3 4 Substation no back up supply for 6kva ups in substation 5 Substation floor epoxy painting need to do 6 Substation 8 9 D.G room no illumination provided 10 D.G room battery charger not yet provided for all d.g s 11 D.G room no fire standards provided inside d,g room 12 Diesel pump 13 Diesel 14 Basement 3 15 WTP electrical panel not commissioned 16 Basement -3 17 Basement -3 18 Basement -3 19 Basement -2 20 Basement -1 21 Ground floor entrance one ckt foot light ckt not working 22 wall fixed foot lights are not working 23 Ground floor UPS pm is pending Sl No. Earth Pit not yet commissioned and kept in an open condition floor epoxy painting work is not completed and air filters are getting choked HSD service tank area diesel transfer pump supply socket is kept in open condition with no enclosure.need to give proper covering . connected. Still Breakers are not working Properly. Diesel service tank need to fix a calibrated gauge scale for service tank diesel transfer pump kept above a disel barrel .need to fix on a permanent platform and permanet G.I line to be lined to tank no permanet platform for diesel unloading and barrel are getting damged fresh air,exhaust,gas fan cabling work not completed and not yet commissioned Emergency plant room progress and cables lying are not properly dressed there is no power socket(single and 3 phase) connection provided for any kind of maintanance work in future there is no water connection point given for maintanance in future there is no power socket(single and 3 phase) connection provided for any kind of maintanance work in future exterior focussing illumination light should be provided with a permanent power connection GF to base 1 Ramp(exterior)

description

YTFYF

Transcript of Electrical Snags Updated

Page 1: Electrical Snags Updated

Hi-LITE Mall -ELECTRICAL Incomplete Works.

Location Issue Remarks

1 Sub station

2 D.G room

34 Substation no back up supply for 6kva ups in substation Done5 Substation floor epoxy painting need to do

6 Substation

8 Diesel service tank need to fix a calibrated gauge scale for service tank 9 D.G room no illumination provided

10 D.G room battery charger not yet provided for all d.g s11 D.G room no fire standards provided inside d,g room

12 Diesel pump

13 Diesel

14 Basement 3

15 WTP electrical panel not commissioned

16 Basement -3

17 Basement -3 Done

18 Basement -3 Done

19 Basement -2 Done

20 Basement -1 Done21 Ground floor entrance one ckt foot light ckt not working

22 wall fixed foot lights are not working 23 Ground floor UPS pm is pending

Sl No.

Earth Pit not yet commissioned and kept in an open condition

floor epoxy painting work is not completed and air filters are getting choked

HSD service tank area

diesel transfer pump supply socket is kept in open condition with no enclosure.need to give proper covering .

all the ACB breakers UV RELAY not yet connected. Still Breakers are not working Properly.

diesel transfer pump kept above a disel barrel .need to fix on a permanent platform and permanet G.I line to be lined to tank

no permanet platform for diesel unloading and barrel are getting damged

fresh air,exhaust,gas fan cabling work not completed and not yet commissioned

Emergency plant room

still on temporary connection.work under progress and cables lying are not properly dressed

there is no power socket(single and 3 phase) connection provided for any kind of maintanance work in future

there is no water connection point given for maintanance in future

there is no power socket(single and 3 phase) connection provided for any kind of maintanance work in future

exterior focussing illumination light should be provided with a permanent power connection

GF to base 1 Ramp(exterior)

Page 2: Electrical Snags Updated

24 Ground floor

25 1st floor

26 2nd floor

27 3rd floor

28 Basement 1

29 Terrace no energy meter provided for chiller.

30Floor

31 Floor floor wise separate energy meter not fixed 32 Cooling tower area no illumination provided

33 Terrace area34 All AHU rooms no lighting yet provided35 Basement 1 IBS room debris not cleared. Done36 CCTV camera not yet connected in all mall area Done37 Electrical rooms ventillation work not yet completed 38 Service lift one lift near lifestyle not yet commissioned

39 Electrical rooms 40 Substation electrical total load balancing not completed . Under Progress.

41 D.G Air compresser need to order for cleaning the radiater

42 Electrical panel electrical mats need to be placed in all electrical panels 43 Stair Case No.2 There is no lighting supply given.

44 Exit Gate No.2 Lighting cables are provide but there is no light fixture.Done

45 Common Need to purchase hydraulic ladder to repalce fuse lights.

46 Common area Most of pillar focus LED lights are not working.

47Some panels CT's are not fixed.

48 ShopsDone

49 Basement -3

50 Substation All the ABB breakers need to do preventive maintenace.

sockets with no power supply:- near PUMA shop,near SPLASH,near DANIEL HETCHER ,near passenger lift

sockets with no power supply: near MAX,near OPTIC ZONE

sockets with no power supply: near MAX,near LEE FOOT ,near wash room

sockets with no power supply: near BARBIQUE. socket directly mounted on wall

no energy meter provided seperately for lift,escalator,fire system,WTP

Chiller#1, Chiller#2 & MCC Panel#2 is done. Need MCC Panel#1

all floor csu are connected from common area lighting panel MLT3B.

no illumintaionin in entire trerrace area and point also not given

MLT1 electrical cabling work under progress and smoke detecters are fixed

Cabling work completed. But Smoke detecter fixing still pending.

Substation, Electric Rooms

Major Anchor shops not fix in Energey Meter (Fbb,I am In, Baby Care, Malabar Fresh ) and other shops (Fazal Bag, Paont ball).

All the Sumps need to connect with submergible pump with starter panel to be connected to common Drain.

Page 3: Electrical Snags Updated

51 Pump Room WTP pumps need to be connected with level controls.52 Parking Area Fire Exits signag need to fix with battery Back-Up.

Page 4: Electrical Snags Updated

24 Ground floor 25 1st floor sockets with no power supply: near MAX,near OPTIC ZONE 26 2nd floor sockets with no power supply: near MAX,near LEE FOOT ,near wash room 27 3rd floor sockets with no power supply: near BARBIQUE. socket directly mounted on wall 28 Basement 1 no energy meter provided seperately for lift ,escalater,fire system,WTP

sockets with no power supply:near PUMA shop,near SPLASH,near DANIEL HETCHER ,near passenger lift