Electrical Panels Method Statement

download Electrical Panels Method Statement

of 14

Transcript of Electrical Panels Method Statement

  • 7/23/2019 Electrical Panels Method Statement

    1/14

    METHOD STATEMENT FOR

    TESTING AND

    COMMISSIONING OF

    ELECTRICAL PANELS.

    (MDBs, MCCs, CAPACITOR

    BANKS, EMDBS, SMDBs,

    ESMDBs & VFD PANELS)

    CONTRACTOR:MACAIR /

    DOC.NO:MS-

    REV:

    DATE : 03/02/2011

    TABLE OF CONTENTS

    Item Description

    1.0 Scope.

    2.0 References.

    3.0 Access / Egress

    4.0 Health &Safety Hazards

    4.1 Safety Rules during Testing.

    4.2 Safety Lighting.

    4.3 Task Lighting

    4.4 Emergency Arrangements.

    4.5 Risk and Controls.

    5.0 Abbreviations and Definitions.

    6.0 Roles/Responsibilities/Competence.

    7.0 Testing and Commissioning Procedures.

    7.1 Attachment 1- Method of Commissioning:

    8.0 Training.

    9.0 Working Hours.

    10.0Manpower Requirement and Supervision.

    11.0Test Instruments Requirements.

    12.0Requirements.

    12.1General Requirements.13.0Personnel Equipment.

    14.0Supporting Information.

    15.0Distribution

    16.0Other information

    1

  • 7/23/2019 Electrical Panels Method Statement

    2/14

    METHOD STATEMENT FOR

    TESTING AND

    COMMISSIONING OF

    ELECTRICAL PANELS.

    (MDBs, MCCs, CAPACITOR

    BANKS, EMDBS, SMDBs,

    ESMDBs & VFD PANELS)

    CONTRACTOR:MACAIR /

    DOC.NO:MS-

    REV:

    DATE : 03/02/2011

    17.0Attachments

    17.1Method of Commissioning : MDBs, MCCs, EMDBs & Capacitor Banks

    17.2Method of Commissioning : SMDBs, ESMDBs &DBs.

    17.3Method of Commissioning: VFD Panels.17.4Calibration Certificates.

    17.5Risk Assessment.

    17.6Test Reports.

    2

  • 7/23/2019 Electrical Panels Method Statement

    3/14

    METHOD STATEMENT FOR

    TESTING AND

    COMMISSIONING OF

    ELECTRICAL PANELS.

    (MDBs, MCCs, CAPACITOR

    BANKS, EMDBS, SMDBs,

    ESMDBs & VFD PANELS)

    CONTRACTOR:MACAIR /

    DOC.NO:MS-

    REV:

    DATE : 03/02/2011

    1.0 SCOPE

    This Procedure Covers the Testing and Commissioning of Electrical Panels in the DUCAB HV & EHVFacility. The MDBs, EMDBs and Capacitor banks are installed at the LV rooms, while MCC Panels are atVCV Tower roof, CCV Tower roof, EHV Test lab electrical room , Chiller plant area and mechanical plantroom. EMCCs are located at VCV Tower roof, CCV Tower roof and Administration office first Floor.ESMDBs are installed at Factory area and VCV Tower electrical room (Ground floor). SMDBs and DBs areinstalled at all areas in the project as indicated on the service drawings. This procedure will also ensureproper workmanship and conforms to Contract documents, manufacturers instructions and standards.

    2.0 REFERENCES

    2.1 Approved MACAIR Shop Drawings for Power layout. (Ref: Ducab KB644/SD- 00107, 00108,00161-00170, 00174-00176, 00187-00199, 00203, 01027,01324,01325 & 01485).

    2.2 MACAIR Project Quality Plan.2.3 MACAIR Safety Manual2.4 Manufacturers recommendations.

    3.0 ACCESS /EGRESS

    The Commissioning of the System will commence only when Main Contractor clearance is given foraccess to conduct the Testing and Commissioning.

    4.0 HEALTH & SAFETY HAZARDS

    Health and Safety procedures by Main Contractor and MACAIR will be implemented for this job. A routinesafety check will be done by the Safety Officer In-charge as per MACAIR Safety Procedure.

    4.1 Safety Rules During Commissioning

    In order to ensure safe conditions during testing the following rules have to be followed:

    4.1.1 Persons engaged with this commissioning are experienced and have received proper and

    adequate training related to procedures and test equipment utilized for the particular

    testing activity.

    4.1.2 Test instruments and test leads should be maintained in a safe condition and the test

    methods not to create danger either for the operator or for other persons.

    4.2 Safety Lighting

    Safety Lights will be used in case of power failure ensuring good illumination at the working area to

    aid evacuation if necessary.

    3

  • 7/23/2019 Electrical Panels Method Statement

    4/14

    METHOD STATEMENT FOR

    TESTING AND

    COMMISSIONING OF

    ELECTRICAL PANELS.

    (MDBs, MCCs, CAPACITOR

    BANKS, EMDBS, SMDBs,

    ESMDBs & VFD PANELS)

    CONTRACTOR:MACAIR /

    DOC.NO:MS-

    REV:

    DATE : 03/02/2011

    4.3 Task Lighting

    Adequate lighting shall be provided to ensure good illumination at the working area.

    4.4 Emergency Arrangements

    4.4.1 General: Site Safety procedures will be followed and in case of any emergency, Safety

    Officer will administer the emergency arrangements as per the system, stop work and

    report to nearest Assembly Point, etc.Safety Officer Name : Mr. Reghupathy, (Con # 0559262923)

    4.4.2 Fire Precautions: No significant fire risks associated with this activity but general fire

    precaution measures will be taken.

    4.4.3 Communication: Via mobile phones issued to all engineers.

    4.5 Risk and Controls

    4.5.1 Please refer to the Risk Assessment attached in Section 17.6

    4.5.2 Environmental considerations: There are no waste materials associated with this activity.

    5.0 ABBREVIATIONS & DEFINITIONS

    MC - Main Contractor (MACAIR)PM - Project Manager (MACAIR)PE - Project Engineer (MACAIR)PE - Project Engineer (Prime Electrical)SO - Safety Officer (MACAIR)QA/QC - Quality Assurance/Quality Control (MACAIR)

    6.0 ROLES/RESPONSIBILTY /COMPETENCE

    6.1 PM - will have the overall responsibility of the Project for execution, quality and safety, maintainthe planning and progress and coordination with Main Contractor.

    6.2 PE -will be responsible for day to day activities in the Site for System Testing and Commissioning,report preparation and demonstration of System Commissioning.

    6.3 PE (Prime Electrical) -will be directly responsible for the System commissioning.

    6.4 SO - will be responsible for Health and Safety aspects in the Site in line with Main ContractorSafety requirements.

    4

  • 7/23/2019 Electrical Panels Method Statement

    5/14

    METHOD STATEMENT FOR

    TESTING AND

    COMMISSIONING OF

    ELECTRICAL PANELS.

    (MDBs, MCCs, CAPACITOR

    BANKS, EMDBS, SMDBs,

    ESMDBs & VFD PANELS)

    CONTRACTOR:MACAIR /

    DOC.NO:MS-

    REV:

    DATE : 03/02/2011

    6.5 QA/QC -willoversee the quality requirements and quality control measures for the Project.

    7.0 TESTING AND COMMISSIONING PROCEDURES

    Please refer to the attachments as follows;

    7.1 Method of Commissioning : MDBs, MCCs & EMDBs.

    7.2 Method of Commissioning : Capacitor Banks

    7.3 Method of Commissioning : SMDBs, ESMDBs &DBs.

    7.4 Method of Commissioning: VFD Panels.

    7.5 Calibration Certificates.

    7.6 Risk Assessment.

    7.7 Test Reports.

    8.0 TRAINING

    8.1 Engineers who will conduct the Commissioning shall have the experience in SystemCommissioning.

    8.2 Tool Box talks will provide general training and awareness for each activity and also undergofurther training by the Quality Assurance Department.

    9.0 WORKING HOURS

    Site Normal Working Hours.

    10.0 MANPOWER REQUIREMENT & SUPERVISION

    PM - Project Manager (MACAIR)

    PE - Project Engineer (MACAIR)PE - Project Engineer (Prime Electricals)SO - Safety Officer (MACAIR)QA/QC - Quality Assurance/Quality Control (MACAIR)

    11.0 TEST INSTRUMENT REQUIREMENT

    The following Test Instruments will be used for the Commissioning of the Electrical Panels. They will beselected as having the maximum field measuring accuracy and being the best suited to the function beingmeasured and will be applied as recommended by the manufacturer.

    5

  • 7/23/2019 Electrical Panels Method Statement

    6/14

  • 7/23/2019 Electrical Panels Method Statement

    7/14

  • 7/23/2019 Electrical Panels Method Statement

    8/14

    METHOD STATEMENT FOR

    TESTING AND

    COMMISSIONING OF

    ELECTRICAL PANELS.

    (MDBs, MCCs, CAPACITOR

    BANKS, EMDBS, SMDBs,

    ESMDBs & VFD PANELS)

    CONTRACTOR:MACAIR /

    DOC.NO:MS-

    REV:

    DATE : 03/02/2011

    ATTACHMENT 17.1

    Method of Commissioning: MDBs, MCCs, EMDBs

    8

  • 7/23/2019 Electrical Panels Method Statement

    9/14

    METHOD STATEMENT FOR

    TESTING AND

    COMMISSIONING OF

    ELECTRICAL PANELS.

    (MDBs, MCCs, CAPACITOR

    BANKS, EMDBS, SMDBs,

    ESMDBs & VFD PANELS)

    CONTRACTOR:MACAIR /

    DOC.NO:MS-

    REV:

    DATE : 03/02/2011

    ATTACHMENT 17.2

    Method of Commissioning: Capacitor Banks

    9

  • 7/23/2019 Electrical Panels Method Statement

    10/14

    METHOD STATEMENT FOR

    TESTING AND

    COMMISSIONING OF

    ELECTRICAL PANELS.

    (MDBs, MCCs, CAPACITOR

    BANKS, EMDBS, SMDBs,

    ESMDBs & VFD PANELS)

    CONTRACTOR:MACAIR /

    DOC.NO:MS-

    REV:

    DATE : 03/02/2011

    ATTACHMENT 17.3

    Method of Commissioning: SMDBs, ESMDBs &DBs.

    10

  • 7/23/2019 Electrical Panels Method Statement

    11/14

    METHOD STATEMENT FOR

    TESTING AND

    COMMISSIONING OF

    ELECTRICAL PANELS.

    (MDBs, MCCs, CAPACITOR

    BANKS, EMDBS, SMDBs,

    ESMDBs & VFD PANELS)

    CONTRACTOR:MACAIR /

    DOC.NO:MS-

    REV:

    DATE : 03/02/2011

    ATTACHMENT 17.4

    Method of Commissioning: VFD Panels

    11

  • 7/23/2019 Electrical Panels Method Statement

    12/14

    METHOD STATEMENT FOR

    TESTING AND

    COMMISSIONING OF

    ELECTRICAL PANELS.

    (MDBs, MCCs, CAPACITOR

    BANKS, EMDBS, SMDBs,

    ESMDBs & VFD PANELS)

    CONTRACTOR:MACAIR /

    DOC.NO:MS-

    REV:

    DATE : 03/02/2011

    ATTACHMENT 17.5

    Calibration Certificate

    12

  • 7/23/2019 Electrical Panels Method Statement

    13/14

    METHOD STATEMENT FOR

    TESTING AND

    COMMISSIONING OF

    ELECTRICAL PANELS.

    (MDBs, MCCs, CAPACITOR

    BANKS, EMDBS, SMDBs,

    ESMDBs & VFD PANELS)

    CONTRACTOR:MACAIR /

    DOC.NO:MS-

    REV:

    DATE : 03/02/2011

    ATTACHMENT 17.6

    Risk Assessment

    13

  • 7/23/2019 Electrical Panels Method Statement

    14/14

    METHOD STATEMENT FOR

    TESTING AND

    COMMISSIONING OF

    ELECTRICAL PANELS.

    (MDBs, MCCs, CAPACITOR

    BANKS, EMDBS, SMDBs,

    ESMDBs & VFD PANELS)

    CONTRACTOR:MACAIR /

    DOC.NO:MS-

    REV:

    DATE : 03/02/2011

    ATTACHMENT 17.7

    Test Reports