1 NTPC Electrical & NTPC Electrical & Mechanical Safety Mechanical Safety Rules Rules 1. 1. Introduction Introduction 2. 2. Philosophy & Principles Philosophy & Principles 3. 3. Definitions Definitions 4. 4. Provisions’s Generals Provisions’s Generals 5. 5. Basic Safety Rules Basic Safety Rules 6. 6. Procedure for Safety Procedure for Safety Documents & Keys Documents & Keys

Transcript of Ele.& Mech Safety&rules NTPC.ppt

  • NTPC Electrical & Mechanical Safety RulesIntroductionPhilosophy & PrinciplesDefinitionsProvisionss GeneralsBasic Safety RulesProcedure for Safety Documents & Keys

  • Forms of SAFETY DOCUMENTSSelected Persons ReportPermit To WorkLimited Work CertificateSelection for TestPermit to Work with restoration of Motive PowerResponsibilities of PersonsCodes of practice

  • SAFETY IN P.T.W. SYSTEM(INTRODUCTION & PHILOSOPHY)AA.SAFETY Rules & Code of Practice are approved by NTPC BOARD.(Mandatory&Complied)BB.SAFETY RULES -that each location shall produce written management Instruction (LMIs)CC.SAFETY RULES- shall be issued individually to persons appropriate to enable them to fulfill obligationsDD.-These rules are based on STATUATORY LEGISLATIONSEE.SAFETY RULES shall be applied where reasonably practicable eg.earthing device, locking of vales etc.FF.OBJECTIVE OF SAFETY RULES : A programmed of work to MODIFY points of isolations to simplify LOCKABILITY should be developed at each point

  • SAFETY IN P.T.W. SYSTEM(INTRODUCTION & PHILOSOPHY

    GG.-NTPC-Power Generating OrganisationInherent danger of Electro-Mechanical SystemsDANGER Arising from environment not directly associated with the system such as, a method of work or means of access.Safety Precautions shall be taken professionally against Inherent dangers.Execution of required

    DD.-PRINCIPLESThese rules concern only safety of persons.During work on high voltage apparatus Safety is achived mainly by Isolation from the system. HOT LINE GANGS)LIVE apparatus of SAFETY shall be achieved by application of specialized procedures.

  • SAFETY IN P.T.W. SYSTEM(INTRODUCTION & PHILOSOPHYII. CONTROL Instructions, Actions, Precautions, Consent, Issuance of Safety Documents before actual work starts.After Completion of work-Consulting to Cancellation.

    JJ. WORK. It includes-Receipt of safety DocumentsExecution of WorkAfter Completion or termination of work & clearance of work area, clearance of documents

  • SAFETY DOCUMENTS & KEYSKK. LIMITED WORK CERTIFICATEPermit to WorkPermit to Work-ROMP (Restoration of Motive Power)SANCTION FOR TEST

    XX. PREPARED-ISSUED-CANCELLEDBYSENIOR AUTHORISED PERSON INVOLVING PERSONAL SUPERVISION totransfer & Suspension of all Safety Documents exceptSANCTION FOR TEST cannot be suspended under any circumstances

  • SANCTION FOR TEST: is in force on PLANT/HIGH VLAGE apparatus-No other SAFETY DOCUMENT shall be in force on the same item of plant/apparatus.LL. SENIOR AUTHORISED PERSON(SAP): Competent Person nominated in writing by the location General Manager/Add/Deputy to carry out these dutiesMM. Wherever reasonably practicable safety documents should be issued to the PERSONS doing the work provided he has adequate knowledge from safety point of view (VSTPP-e.g.. CMP ,Labour etc.) (GAS Plant-foreign expert)NN. If several groups are working SAFETY DOCUMENTS shall be isued directly (face to face) to recipient who shall responsible for the working party.

  • OO. PERMIT TO WORK (Preparation)SAP cannot physically check because of remoteness but safety precautions can be recorded in detail in SAP.PTW original to be retained by applicant & recorded in tune with LMI with precautions in record.SAP can check physically check location-Satisfactory/DoubtableAppropriate KEYS-FUSES or other means of securing isolations shall be placed in KEY-SAFELMI must specify what is safe custodySAP shall secure the local KEY SAFE by operating his CONTROL-KEY to lock the KEY-SAFE under his control.SAP when considered necessary can add/delete safety precautions to avoid danger.It basically concerned with SAFETY FROM SYSTEM &not general safety.

  • PP -ISSUE & RECEIPThaving recorded the items to be issued the SAP shall sign & issue the permit with a key safe together with item noted.QQ- TRANSFERWork not completed-Necessary to TransferRecord on reverse side of PTW-by recipient & Newcomer with all relevant instructions & briefing.RR- SUSPENSIONWhen it becomes necessary to temporarily discontinue work with & withdraw for limited period of time from Plant/APP without changing the safety precautions then suspension is used. eg Boiler Case for RadiographySS-CLEARANCE & CANCELLATION SAP-ensures withdrawal of working persons, earthen, T&P systems, work area clearance, Guards & access doors refitted.