El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits...

20
El Compas Project Monthly Photo Update November 2017 Crushing Fine Ore Bins Laboratory Administration Ball Mill Housing Flotation Housing Thickener Warehouse Concentrate Storage & Filtering

Transcript of El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits...

Page 1: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

El Compas Project Monthly Photo Update

November 2017

Crushing

Fine Ore Bins

LaboratoryAdministration

Ball Mill Housing

Flotation Housing

Thickener

WarehouseConcentrate Storage & Filtering

Page 2: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

November Project Highlights

GROWTH WITH INTEGRITY2

No lost time injury accidents

All mine services complete

Jumbo commenced lifting ramp production pace

Service entry ramp entrance 85% complete

100m mine development decline advance

Mine portal infrastructure at 95%

Plant construction at 75% completion

Production start-up on track for late Q1 2018

Page 3: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

El Compas Timeline

GROWTH WITH INTEGRITY3

EL Compas3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27 3

9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9

14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52

Mine Explosives Magazine Permitting

Mine Access Road

Mine Powerline, Offices, Fencing

Mine Portal, Mine Laydown

Mine development using Pyroblast

Mine development

Mine Ore Supply

Plant powerline

Plant engineering and design

Plant procurement

Plant Construction

Plant Commissioning/Operation Sales Commence

Tailings Design

Tailings Construction

ACTIVITY

March April MaySeptember October November December January February

Page 4: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

Mine Portal

GROWTH WITH INTEGRITY4

The portal showing the notice boards, ventilation

duct, fan, air and water lines in place. The final

power-lines are the last step.The final lengths of power cable are

about to be laid over the cable trays.

Page 5: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

Blast monitoring

GROWTH WITH INTEGRITY5

Mine blasts are monitored in the neighborhood with results

officially registered. The vibrations from the Pyroblast-C

exploder agent are well below the recommended limit.

Page 6: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

Ramp Advance

GROWTH WITH INTEGRITY6

The blasting cycle with Pyroblast-C

continued to improve. Shortfalls in

progress during the month were alleviated

when the jumbo arrived onsite.

The burn cut continues to be modified

as the ground conditions and

machinery available alter. Total ramp

advance was at 104m at month end.

Page 7: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

Safety and Security

GROWTH WITH INTEGRITY7

Security fencing around the property

continued in November. The perimeter road

is also complete now separating the nearby

quarry traffic from the underground mine.

Safety inductions are well attended as new

contractors are constantly arriving.

Page 8: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

Rehabilitation

GROWTH WITH INTEGRITY8

Pine trees are part of the rehabilitation

plan. These seedlings recently arrived and

will be tended in the greenhouse before

planting.

All programmed areas of disturbance are

surveyed for plant species and many species

are replanted including these Maguey Cacti.

Page 9: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

Mine Service Entry

GROWTH WITH INTEGRITY9

Old mine ore stockpiles are being assessed

for grade and recoverability.

The old mine entrance was re-excavated.

Reinforcement will be added in December.

Page 10: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

Crushing Circuit Foundation

GROWTH WITH INTEGRITY10

The conveyor to connect the crushing plant

to the fine ore bin arrived from El Cubo

Platforms for the mobile crushing plant are

complete, MCC and switchgear connected to

main power. Units are due for arrival in January.

Page 11: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

Ball Mill

GROWTH WITH INTEGRITY11

The mill only awaits the arrival of the new

bronze bushings on December 5th before

final assembly.

Removal and reinforcement of the cyclone

and flash cell structure has commenced.

Page 12: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

Ball Mill

GROWTH WITH INTEGRITY12

Checking the torque of the mill head and

shell bolts.

The mill bearing lubrication system is complete.

Page 13: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

Conditioner Tank & Flash Cell

GROWTH WITH INTEGRITY13

The conditioner tank was raised to obtain

gravity feed to the flotation cells and avoid

another pump.

The flash cell at the fabricators.

Page 14: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

Flotation Cells & MCC

GROWTH WITH INTEGRITY14

Commencing to install the motor starter

panels in the new motor control circuit.Two of the three main rougher flotation cells

have had the diffusion mechanisms

installed.

Page 15: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

Flotation Cleaner Cells & Underdeck

GROWTH WITH INTEGRITY15

The transfer pump boxes are complete, piping

and electrical installation are in process.The cleaner cell repair is complete, only

awaiting motors to return from remanufacture.

Page 16: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

Tailings & Concentrate Thickeners

GROWTH WITH INTEGRITY16

Tailings thickener is only pending the alignment

and leveling of rakes and transmission

installation.

Concentrate thicker is only pending the

alignment and leveling of rakes and

transmission installation.

Page 17: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

Concentrate Filtering and Storage Area

GROWTH WITH INTEGRITY17

The concentrate security fence and other

such measures were completed.The concentrate storage building floor

was sealed.

Page 18: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

Plant Security Measures

GROWTH WITH INTEGRITY18

Plant fencing and guard houses are complete.The front gate security measures are 95%

complete.

Page 19: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

Tailings Deposit

GROWTH WITH INTEGRITY19

The engineers in field review of the tails facility

details.

Work commenced on borrow

material selection for the tailings

storage facility.

Page 20: El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits the arrival of the new bronze bushings on December 5th ... Checking the torque of

Key Deliverables for December

GROWTH WITH INTEGRITY20

• No lost time injury accidents

• Obtain explosives license

• Commence mine dewatering

• Obtain access to old mine workings

• Mine portal infrastructure complete

• Plant construction completion at 90%