El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits...
Transcript of El Compas Project Monthly Photo Update · Ball Mill 11 GROWTH WITH INTEGRITY The mill only awaits...
El Compas Project Monthly Photo Update
November 2017
Crushing
Fine Ore Bins
LaboratoryAdministration
Ball Mill Housing
Flotation Housing
Thickener
WarehouseConcentrate Storage & Filtering
November Project Highlights
GROWTH WITH INTEGRITY2
No lost time injury accidents
All mine services complete
Jumbo commenced lifting ramp production pace
Service entry ramp entrance 85% complete
100m mine development decline advance
Mine portal infrastructure at 95%
Plant construction at 75% completion
Production start-up on track for late Q1 2018
El Compas Timeline
GROWTH WITH INTEGRITY3
EL Compas3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27 3
9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52
Mine Explosives Magazine Permitting
Mine Access Road
Mine Powerline, Offices, Fencing
Mine Portal, Mine Laydown
Mine development using Pyroblast
Mine development
Mine Ore Supply
Plant powerline
Plant engineering and design
Plant procurement
Plant Construction
Plant Commissioning/Operation Sales Commence
Tailings Design
Tailings Construction
ACTIVITY
March April MaySeptember October November December January February
Mine Portal
GROWTH WITH INTEGRITY4
The portal showing the notice boards, ventilation
duct, fan, air and water lines in place. The final
power-lines are the last step.The final lengths of power cable are
about to be laid over the cable trays.
Blast monitoring
GROWTH WITH INTEGRITY5
Mine blasts are monitored in the neighborhood with results
officially registered. The vibrations from the Pyroblast-C
exploder agent are well below the recommended limit.
Ramp Advance
GROWTH WITH INTEGRITY6
The blasting cycle with Pyroblast-C
continued to improve. Shortfalls in
progress during the month were alleviated
when the jumbo arrived onsite.
The burn cut continues to be modified
as the ground conditions and
machinery available alter. Total ramp
advance was at 104m at month end.
Safety and Security
GROWTH WITH INTEGRITY7
Security fencing around the property
continued in November. The perimeter road
is also complete now separating the nearby
quarry traffic from the underground mine.
Safety inductions are well attended as new
contractors are constantly arriving.
Rehabilitation
GROWTH WITH INTEGRITY8
Pine trees are part of the rehabilitation
plan. These seedlings recently arrived and
will be tended in the greenhouse before
planting.
All programmed areas of disturbance are
surveyed for plant species and many species
are replanted including these Maguey Cacti.
Mine Service Entry
GROWTH WITH INTEGRITY9
Old mine ore stockpiles are being assessed
for grade and recoverability.
The old mine entrance was re-excavated.
Reinforcement will be added in December.
Crushing Circuit Foundation
GROWTH WITH INTEGRITY10
The conveyor to connect the crushing plant
to the fine ore bin arrived from El Cubo
Platforms for the mobile crushing plant are
complete, MCC and switchgear connected to
main power. Units are due for arrival in January.
Ball Mill
GROWTH WITH INTEGRITY11
The mill only awaits the arrival of the new
bronze bushings on December 5th before
final assembly.
Removal and reinforcement of the cyclone
and flash cell structure has commenced.
Ball Mill
GROWTH WITH INTEGRITY12
Checking the torque of the mill head and
shell bolts.
The mill bearing lubrication system is complete.
Conditioner Tank & Flash Cell
GROWTH WITH INTEGRITY13
The conditioner tank was raised to obtain
gravity feed to the flotation cells and avoid
another pump.
The flash cell at the fabricators.
Flotation Cells & MCC
GROWTH WITH INTEGRITY14
Commencing to install the motor starter
panels in the new motor control circuit.Two of the three main rougher flotation cells
have had the diffusion mechanisms
installed.
Flotation Cleaner Cells & Underdeck
GROWTH WITH INTEGRITY15
The transfer pump boxes are complete, piping
and electrical installation are in process.The cleaner cell repair is complete, only
awaiting motors to return from remanufacture.
Tailings & Concentrate Thickeners
GROWTH WITH INTEGRITY16
Tailings thickener is only pending the alignment
and leveling of rakes and transmission
installation.
Concentrate thicker is only pending the
alignment and leveling of rakes and
transmission installation.
Concentrate Filtering and Storage Area
GROWTH WITH INTEGRITY17
The concentrate security fence and other
such measures were completed.The concentrate storage building floor
was sealed.
Plant Security Measures
GROWTH WITH INTEGRITY18
Plant fencing and guard houses are complete.The front gate security measures are 95%
complete.
Tailings Deposit
GROWTH WITH INTEGRITY19
The engineers in field review of the tails facility
details.
Work commenced on borrow
material selection for the tailings
storage facility.
Key Deliverables for December
GROWTH WITH INTEGRITY20
• No lost time injury accidents
• Obtain explosives license
• Commence mine dewatering
• Obtain access to old mine workings
• Mine portal infrastructure complete
• Plant construction completion at 90%