WCCUSD Bond Program
Construction UpdateEl Cerrito High School Stadium
07/15/2014
El Cerrito High SchoolStadium
Conceptual Design
General Contractor Wright
Contracting
Architect of Record WLC Architects
Construction Manager Hector De Leon
Project Engineer Maria Zupo
Inspector of Record Kris Gilbert
El Cerrito High SchoolStadium
Project Team
El Cerrito High SchoolStadium
Site Plan
Contract Amount $13,438,000
Notice of Award 11/21/13
Notice to Proceed 01/27/14
Duration 608 days
Completion Date 09/27/15
Change Order $10,285.00
(0.07%)
El Cerrito High SchoolStadium
General Information
Site retaining walls at Ashbury and
Colusa
Fence piers at Colusa
Building retaining walls and foundations
Site grading and compaction
Underground utilities
El Cerrito High SchoolStadium
Progress Update
Backfilling at Ashbury
Site Walls and Foundation
Building Footings
Retaining Wall Construction at Colusa
Retaining Wall Construction at Ashbury
Retaining Wall Construction at Ashbury
Tree Planting
El Cerrito High SchoolStadium
Ashbury Avenue Elevation