EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

download EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

of 46

Transcript of EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    1/46

    Engineer In Society ( VAB 4042 ) Project Report

    1

    ENGINEER IN SOCIETY

    INSTALLATION OF METERING INTRUMENTS ON FLARE

    PIPELINE

    BY

    SitiHajarBintiJaafar( 9710 )

    Emi ZurimaBinti Ismail( 9136 )

    Nor WaniIdayuBintiAb Wahid ( 10266)

    NurulZahidahBintiMdHasidin( 10809 )

    Noor AzreenBintiMohdFaizol( 10902 )

    April 2011

    UniversitiTeknologiPetronas

    Bandar Seri Iskandar

    31750 Tronoh,

    Perak DarulRidzuan

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    2/46

    Engineer In Society ( VAB 4042 ) Project Report

    2

    EXECUTIVE SUMMARY

    We started the case study by choosing the hot tapping project that had been

    conducted at PETRONAS CarigaliSdnBhd, Peninsular Malaysia Operation (PCSB

    PMO). The main objective of hot tapping is to install new flare meter at Resak and

    Duyong flare header line at Onshore Gas Terminal (OGT) to calculate the amount of

    product being flared because the quality and performance of plant is based on the value

    being calculated.The few metering systems are installed at the flare pipelines without

    any hazards to determine quantity such as Mass, Volume and Energy and quality of

    material to be deliveredwithin specific uncertainty limits

    The project took about a month to be done for specific pipelines at the PCSB

    PMO. As the project being conducted, it must follow schedule which will be discussed

    in detail in Work Breakdown and it shows how important project management is in the

    every aspect of life especially in industrial world. Besides, precaution, safety aspects,

    operating conditions and instruments have to be followed which will be discussed in

    details in Health and Safety issues.

    The scope of study for the hot tapping project is basically on how to conduct hot

    tapping project in specific operating conditions at specific pipelines locations for the

    OGT at PCSB PMO with Trisystems Engineering SdnBhd as contractor and TMM

    Engineering SdnBhd as mechanical contractor

    At the end of the project, the objective which is to install new flare meter at

    Resak and Duyong flare header line at Onshore Gas Terminal (OGT) to calculate the

    amount of product being flared because the quality and performance of plant is based on

    the value being calculated,had been achieved successfully without any hazard occurred.

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    3/46

    Engineer In Society ( VAB 4042 ) Project Report

    3

    TABLE OF CONTENT

    Content Page

    Executive Summary 2

    Table of Content 3

    List of Figures and Tables 4

    Introduction & Background of The Project 5 - 6

    Organization Chart

    y PCSB PMOy Maintenance Engineering Departmenty Hot-Tapping Project

    7

    8

    9

    Environmental Impact 10Work Breakdown

    y Project Life Cycley Logical Sequence of Activitiesy Level of Work Breakdown Structure

    11

    11 12

    12 - 16

    Activities Estimation

    y Procedures

    y Close-up procedures

    17

    18 - 26Cost Estimation 27 - 35

    Scheduling 36

    Health & Safety Issues

    y Compliance to authority standards and guidelinesy Hazard Observation

    37 38

    38 - 40

    Discussions & Recommendations

    y Discussion of the outcomes

    y Recommendationsy Conclusions

    41 42

    43

    43

    Appendices

    References

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    4/46

    Engineer In Society ( VAB 4042 ) Project Report

    4

    LIST OF FIGURES

    Content Page

    Figure 1: Organization Chart of PCSB PMO 7

    Figure 2: Organizational Chart of Maintenance Eng. Dept. 8

    Figure 3: Organization Chart of Hot Tapping Project 9Figure 4: Project Life Cycles Stages 11

    Figure 5: Sequence of Activities vs Time 12

    Figure 6: Level of Work Breakdown Structure 12

    Figure 7: Fit-up Work 18

    Figure 8: Leak Test on Welding Joint 19

    Figure 9: Tightening and Untightening in cross sequence 20

    Figure 10: Gaskets 20

    Figure 11: Valve Installation 20Figure 12: Hot-Tapping Machine 21

    Figure 13: Leak Test on Hot tapping Machine / Gate Valve 22

    Figure 14: Fixing Pitot Drill and Boring Bit 23

    Figure 15: Tightening Hot-Tapping Machine 23

    Figure 16: Leak Test on Hot tapping Machine using Nitrogen gas 24

    Figure 17: Cutter pass check, cutting travel measurement,alignment using manually

    24

    Figure 18: Hot Tap Perforation 25

    Figure 19: Probe Installation 26

    Figure 20: Exhibit 5 and Exhibit 6 34

    Figure 21: Exhibit 7 and Exhibit 8 34

    Figure 22: Scheduling 36

    Figure 23: Fire Triangle 38

    Figure 24: Possible gas leak identified and covered 40

    Figure 25: Gas detector and Fire water 40

    LIST OF TABLES

    Content PageTable 1: Description on Project Managers Role 13

    Table 2: Method of Magnetic Particle Inspection (MPI) 19

    Table 3: Exhibit 3 29

    Table 4: Exhibit 4 32

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    5/46

    Engineer In Society ( VAB 4042 ) Project Report

    5

    INTRODUCTION& BACKGROUND OF PROJECT

    Hot Tapping is the method of making perforation on the online line without the

    interruption of emptying the section of pipe safely. This means the pipe can continue to

    be in operation while maintenance or modifications are being done to it. The hot tapping

    also used to drain off pressurized casing fluids. In this hot tapping, the heat must be

    distributed to the flow to minimize the risk of explosion.

    Hot tapping can be done to most any type of pipe, ranging from carbon steel to

    PVC that contain water, oil, gases, fuels, steam and other chemical substances with

    specific temperature and pressure condition.

    Typical Hot Tap installation consists of a tapping saddle, gate valve, and Hot

    Taping Machine. The installation is tested, the valve is opened, and the cutter and pilot

    drill advanced. When the cut is completed, the cutter and pilot drill are retracted, the

    valve is closed and the Hot Tap Machine is removed.[ i ]

    There are three types of hot tapping which is tapping on tangential of pipeline,

    tapping not on tangential (offset tapping), twisted and not on tangential of pipeline. At

    OGT, there are two types of pipelines used which is High Pressure (HP) and Low

    Pressure (LP) pipeline. For HP pipeline, the tapping types are flow transducers: offset

    tapping, pressure transmitter: tangential tapping and temperature transmitter: tangential

    tapping where for LP pipeline, the tapping types are flow transducers: twisted and offset

    tapping, pressure transmitter: tangential tapping, temperature transmitter: tangential

    tapping.

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    6/46

    Engineer In Society ( VAB 4042 ) Project Report

    6

    In this report, basically we discuss on Hot Tapping and perforation (making

    holes) that were done to the existing pipelines at Onshore Gas Terminal (OGT) in

    PETRONAS CarigaliSdnBhd, Peninsular Malaysia Operation (PCSB PMO) to tie-in the

    new nozzle installation. A few metering instruments such as flow transducers,

    temperature transmitters and pressure transmitters are installed on the flare pipelines to

    measure the flared gas to keep track on where the product goes and the percentage. The

    operating condition during the entire hot tapping process must be monitored crucially as

    the pipelines pressure must not exceed maximum gas pressure that will absolutely

    contributed to hazard such as explosion and fire.

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    7/46

    Project Report

    7

    ORGANIZATION CHART

    Figure 1: Organization Chartof PETRONAS CARIGALI SDN BHD, PENINSULAR MALAYSIA O

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    8/46

    Project Report

    8

    Figure 2: Organization Chart ofMAINTENANCE ENGINEERING DEPARTMENT

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    9/46

    Project Report

    9

    Figure 3: Organization Chart of HOT TAPPING PROJECT

    PROJECT MANAGER

    Mr M Fallah bin Mohamedy To lead the project

    and supervise thecontractor involved.

    MAIN CONTRACTOR

    TRISYSTEMSENGINEERING SDN. BHD(TRI)

    y In charge on electricaland instrument part.

    y Responsible to doinstallation of metering instrumentsand electrical.

    MECHANICAL

    CONTRACTOR

    TMM ENGINEERINGy In charge on mechanical

    part.y In charge on equipment.y Responsible to do welding

    and perforation process.

    C

    PETRONASSDN. BHD (

    y To pthe p

    y To ley To o

    appr proje

    y To pof th

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    10/46

    Engineer In Society ( VAB 4042 ) Project Report

    10

    ENVIRONMENTAL IMPACT

    By performing a shutdown interconnect with low or high pressure system will

    give an impact on environmental. Gas vented from the pipeline segment represents a

    loss of product and an increase in methane emission. From the record, up to 6000 cubic

    feet natural gas vented to make a new connection or non-leaking repairs.[ ii ]The

    quantity is depends on pipe diameter, length between isolation valves and operation

    pressure. For example, a shutdown connection on a steel can require one to three or

    more days if pipeline outage and possible interruption of natural gas shipments in

    addition to the release of methane to the atmosphere.

    Methane is difficult to transport from its source. Generally it will be transported

    in bulk by pipeline in its natural gas form. It is a relatively potent a greenhouse gas.

    Compared with carbon dioxide, it has a high global warming potential of 72 (calculated

    over a period of 20 years) or 25 (for a time period of 100 years). It is also affects the

    degradation of the ozone layer. Large amount of methane are produced anaerobically by

    methanogenesis. [ iii ]

    So, hot tapping is an alternative technique that allows the connection to be made

    without shutting down the system and venting gas to the atmosphere. With that, the

    quantity of methane gas at atmosphere will be reducing. Hot tapping will avoided

    cutting, realignment and re-welding of pipeline sections. It will also avoid inserting or

    gas-freeing pipeline section for hot work. In other side, hot tapping also can reduce

    planning and coordination costs.

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    11/46

    Engineer In Society ( VAB 4042 ) Project Report

    11

    W ORK BREAKDO W N

    Project Life Cycle

    By general definition, project is taken to create a unique product or services where we

    have to invest our time, money and resources in hope of a return. In the Hit Tapping

    Project, four stages in sequence are done to follow the timeline. The four stages are:

    Figure 4: Project Life Cycle Stages

    Logical Sequence of Activities

    In Hot Tap Project, each stage of life cycles is done by different types of team

    according to their area of works. In defining stage, there are 3 minor stage will be done

    which is inception, definition of project and proposal preparation which done by the

    project manager. Organization chart of the project is created which included the main

    contractor, mechanical contractor and the client. The job scope has been defined to all

    members.

    During planning stage, the Planning, Organizing, Leading and Controlling

    (POLC) level is being used. The planning is satisfied by top management and completes

    the strategies using the resources of time, money, team members, material of the

    pipeline, installed instrument, drilling equipment, welding, and perforation process.

    Leading is by directing each team to complete their jobs within time using motivating

    2.PLANNING

    4.DELIVERING

    1.DEFINING

    3.EXECUTION

    ProjectLife Cycle

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    12/46

    Engineer In Society ( VAB 4042 ) Project Report

    12

    methods and good communication skills. Finally, manager has to control the project

    flow with respect to time, cost, and quality of the flared gas.

    Execution stage is important because this is where the construction begins. The

    metering instrument is installed regarding to the sequence and the drilling, welding, and

    perforation process is done in safe environment by following the HSE standard. After

    construction is done, we reach the final stage, delivering. This is where we handing over

    the process of plant. The project life cycle is simplified in the diagram below:

    Figure 5: Sequence of Activities vs Time

    Levels of Work Breakdown Structure

    Work breakdown is the schedule which guides all the teams to develop the project

    according to the timeline. Work breakdown structure is divided into three main phases

    which is Initiation Phase, Development Phase, and Procurement Phase.

    Figure 6: Level of Work Breakdown Structure

    WORKBREAKDOWN

    Oganization

    INITIATIVE PHASEProject Manager

    DEVELOPMENT PHASEEngineer/Constructor

    Electrical Mechanical

    PROCUREMENTPHASE

    Closure Phase

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    13/46

    Engineer In Society ( VAB 4042 ) Project Report

    13

    To make sure that the yield flared gas, installation and perforation process of Hot tap

    Project is follows the requirement and standard given, several task need to be completed

    in sequence so that the project will complete before or on time.

    1) Initiative Phase

    This task is done by the project manager where he has to make sure that the

    strategy chosen will be manage in sequence according to plan. The task of

    project manager in initiative phase is described in the following table:

    TASK DESCRIPTIONProject Initiation Initiation of project that fulfill clients need andstandard requirement.The client, PETRONASCarigaliSdnBhd want the project is done withoutshutting down the process of plant and the heat can bemeasured from digital meter installed on the pipeline.

    Project Directive Basic direction of the project flow which includes thescope and procedure on how to complete the task.Thedirection is given including the duration of thedrilling, welding, installation and perforation process.

    Project RequirementSpecification

    Follow the standard and requirement highlighted byclient or project director to be completed bymanagement, design, engineering and constructionteams.Project manager will manage the flow of

    project, electrical and mechanical engineering teamswill do the installation of metering instrument andconstruct the related equipment to the flare pipeline.

    Project Management Plan Defines the objectives, scope for implementation,installation and the task responsible for each team.

    Construction ManagementPlan

    Build and develop the project according to therequirements in a manner rules for electrical andmechanical area.

    Work Breakdown Structure Develop a structure for completing project accordingeach subordinate and working area.

    Table 1: Description on Project Managers Role

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    14/46

    Engineer In Society ( VAB 4042 ) Project Report

    14

    2) Development Phase

    There are four main responsibility which is electrical and mechanical

    engineering, inspection group, execution foreman and operations.

    a) Engineering

    Engineering responsibility includes design of nozzle and its support, type of

    inspection of the parent wall for example, the radio graph and/or ultra-sonic

    inspection, welding method and procedure, valve selection and specification

    of test pressures, method of testing and the test media, appropriate drawingsand files up-dated. Special consideration must be given to testing media due

    to parent wall temperature and thickness. The engineer or tapping technician

    will assist other involved groups in the evaluation, planning, and execution.

    The parent metal, at the immediate location of the hot tap, shall be inspected

    prior to the welding of the nozzle onto the line, and vessel. The type, design

    and temperature of the parent metal will determine the type of wall

    inspection.The engineer will determine if Corporate Engineering Team

    should be contacted. Typically, but not limited to, Corporate Engineering is

    contacted prior to performing a high risk tap and/ or line plug for example,

    lethal services, pressures greater than 1000 psig and/or temperatures greater

    than 600o

    F.

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    15/46

    Engineer In Society ( VAB 4042 ) Project Report

    15

    b) Inspection Group

    The Inspection Group which consists of the project manager and supervisors

    representative will review and determine materials of construction, hot tap

    location wall thickness. Inspection Group representative will also recommend

    the welding method and procedure to the engineer. The Engineer will make a

    decision concerning x-raying of the hot tap valve and any other special

    testing or inspection requirements or procedures.

    c)

    Execution Foreman / Mechanical Planner The Execution Foreman / Mechanical Planneris responsible for all phases of

    the planning, ordering, and execution of the job. In conjunction with the

    Inspection Group the Execution Foreman / Mechanical Planner is responsible

    for the proper inspection of the tapping and/or plugging machine, and

    witnessing of all tests specified by Engineering.

    d) Operations

    The Operations Engineer/Planner are responsible for the initiation and

    completion of the hot tapping data list used for preplanning and submitting

    these sheets with the permit request. With assistance from other groups, as

    required, the specification of department number, line or equipment number,

    process conditions, justification and the safety review for a hot tap or plug is

    also included in the client's responsibility. At the completion of the job, the

    planner will send one copy of the completed data sheets to the responsible

    mechanical engineer; including the recovered coupon.

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    16/46

    Engineer In Society ( VAB 4042 ) Project Report

    16

    3) Procurement Phase

    The Procurement phase is where the Hot Tap is installed based on the request

    from the client after the Development phase completed. The quality of Hot Tap

    on flare pipeline is monitored by the procurement team and construction

    engineering team. Before Hot Tap is installed in real plant process pipeline, there

    are several samples of Hot Tap being tested by the quality team during

    experimentation. This is to ensure that the product does not have any issue in

    terms of operations and functionality. The installation and perforation process

    must be within the estimated cost and time given before the deadline to avoidany additional in cost and delay time to the client and plant process. If the

    products are not settled at the agreed time between the company and the client,

    there will be a penalty and bad reputation to the company. After the Procurement

    phase and delivery of the products to the customer, the project comes to the

    closure.Finally, in the Closure Phase under Procurement Phase, the Project

    Manager issues the Project Closure report to the Corporate Engineering Team.

    The details of the project are attached such as the documents related to the

    project including the planning, designs, development and procurement. The list

    of the items is mentioned in the handover checklist documents.

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    17/46

    Engineer In Society ( VAB 4042 ) Project Report

    17

    ACTIVITIES ESTIMATION

    This project can be generally classified to two major parts, Hot Tapping (welding,

    installation of isolation valve and perforation of pipeline) and Installation of metering

    instruments (Flow transducers, temperature transmitters and pressure transmitters.)

    Procedures:

    1. Pre-works

    2. Hot tapping works

    3. Leak test on welding joint

    4. Valve installation

    5. Preparation of hot tap equipment

    6. Fittings of hot tap equipment on the valve

    7. Leak test of hot tap machine set up using Nitrogen gas.

    8. Cutter pass check and cutting travel measurement, alignment using manually.

    9. Connecting high pressure air hoses between hot tap machine and power unit/air

    compressor.

    10. Hot tap perforation.

    11. Bleeding off gas after first penetration and after perforation completion.

    12. Releasing pressure from hot tap machine after completion.

    13. Unbolting hot tap machine from tapping valve.

    14. Probe installation

    15. Housekeeping.

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    18/46

    Engineer In Society ( VAB 4042 ) Project Report

    18

    Close-Up Procedures:

    1. Pre-works

    The pre-works are mobilization or demobilization of equipment, machinery and

    manpower to site including loading and unloading, equipment inspection, refueling

    diesels for gen sets and lifting activities using cranes.

    2 . Hot Tapping W orks:

    i. Fit-up: Fittings are measured and cut accurately to fitthe pipeline before

    perforation. Pipeline is measured and marked to make sure the fittings areaccurately aligned to the pipeline.

    Figure 7: Fit-up work

    ii. Grinding: Pipeline is grinded before welding to remove paint and coating on

    the welding spot.

    iii. Welding: There are four phases of welding: Tark (welding points on the

    pipeline just as markings of where should the nozzles will be welded), Root

    Pass (welding around the nozzle circumference.), Hot Pass (several layers of

    welding) and Buffering (final layer of welding)

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    19/46

    Engineer In Society ( VAB 4042 ) Project Report

    19

    3 . Leak Test On W elding Joint

    Welds are tested to make sure its robustness. One of weld tests is by using the

    Magnetic Particle Inspection (MPI) technique to test the continuity of the

    welding. There are two methods of MPI:

    Using dry powder Using wet solutionCan be used directly even when thesurface is still hot.

    Can be used to cold surfaces only (waituntil surface is cold).

    Table 2: Method of MPI

    Principle of MPI:

    Figure 8: (a) no cracks/discontinuity (b) cracks/discontinuity on the welding

    If there is no crack or discontinuity of the welding, the iron particles will be

    attracted to the U-magnet. If there is discontinuity on the welding, the metal became lots

    of magnets (poles formed magnets). The iron particles will not attracted to the U-magnet

    but it will be attracted to the cracks. The tubing and fitting have to be check to make sure

    they are properly fitted, control valve operational, ball valves and other venting outlets

    are in close position and all bolts and nuts are in tight condition.

    N S

    N S N S

    Iron particles Iron particles

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    20/46

    Engineer In Society ( VAB 4042 ) Project Report

    20

    4 . Valve Installation

    i. Tightening and untightening bolts in cross sequence.

    Valve is installed on the branch fitting Nuts and bolts are put randomly.

    Spherelwound gasket is inserted The bolts are tightened cross sequence.Figure 9: Tightening and untightening bolts in cross sequence

    ii. Gasket

    Gasket is chosen according to the pipeline size and type. In this project, we

    use sphere wound andshould not have scratch to ensure no leakage

    Teflon sphere wound gasket Graphite sphere wound gasketFigure 10: Gaskets

    iii. Valve installed as isolation valve : Ball valve class VI is used

    Figure 11: Valve Installation

    HP pipeline

    LP

    Ultrasonic Flowtransducers point

    Pressuretransmitter

    point Temperaturetransmitter

    point

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    21/46

    Engineer In Society ( VAB 4042 ) Project Report

    21

    5 . Preparation of Hot Tap Equipment

    Visit TMM Engineering Sdn. Bhd. to check the operation of the hot-tap equipment.

    Tests conducted during the inspection.

    Equipments used:

    i. Hot tapping machine

    Hot tapping machine

    The pilot drill for the hottap machine T-101

    Coupon cutter 1 drilling bit

    2 drilling bit drilling bitFigure 12: Hot Tapping machine

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    22/46

    Engineer In Society ( VAB 4042 ) Project Report

    22

    Tests conducted:

    i. Leak Test of Hot Tap Machine/Gate Valve

    1.

    Hot tap machine T-101 is the smallest hottap machine. The drilling machine ismounted to the metal disc as a replacementto the hot tap valve.

    2. Hot tap machine T-101 assembly isconnected to the nitrogen gas tank for leak test.Nitrogen gas is used because it is nothydrocarbon gas and cannot produce fire.

    3. Pressure supplied is for testing is about 5 bars. This pressure must maintain for about5 minutes to show that there is no leak onthe machine.

    4. Snoop liquid which is a soap based liquid isapplied at the mounting point to test if thereis leak

    5. Snoop is applied to the marking area tocheck whether there is leakage.

    6. Snoop liquid: leak detector

    Figure 13: Leak Test of Hot Tap Machine/Gate Valve

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    23/46

    Engineer In Society ( VAB 4042 ) Project Report

    23

    ii. Fixing of pitot drill and boring bit

    Drilling bits are attached to the hot-tapping machine. We run the hot tap

    machine and observe the movement of the drilling bit. The drilling bit

    will be adjusted until it rotates straight on the exact point to ensure

    accurate drilling point.

    Figure 14: Fixing pitot drill and boring bit.

    6 . Fittings Of Hot Tap Equipment On The Valve

    Hot tap machines are tightened to the valves before any perforation done on the

    pipeline.

    The hot tapping machine ismounted in the valve.

    Tightening the hot tap machine by cross sequence.

    Figure 15: Tightening Hot Tapping machine

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    24/46

    Engineer In Society ( VAB 4042 ) Project Report

    24

    7 . Leak Test of Hot Tap Machine Set Up Using Nitrogen Gas.

    Nitrogen gas is injected for leak test and to vent out oxygen gas.

    Hot tapping machine is powered by pneumatic. Genset supplies = 7bar

    Masking tape is wrapped aroundthe mounting between the hottapping machine and the valve.

    Nitrogen gas injected 2.5 bars. Pressureinjected must be higher than operating

    pressure in the pipeline. . Pressure of thegauge drop indicates leak of the hot tappingmachine.

    Figure 16: Leak Test of Hot Tap Machine Set Up Using Nitrogen Gas.

    8 . Cutter Pass check and Cutting Travel Measurement, Alignment using

    manually.

    Height of the valve and branch fitting ismeasured. Travel length is the length for the drilling bit being screwed up/downduring and after perforation.

    Alignment of the boring bit isadjusted according to the travellengthto make sure that drilling bit istaken out without being stuck whenthe isolation valve is closed after

    perforation is done.Figure 17: Cutter Pass check and Cutting Travel Measurement, Alignment

    Nitrogen gas injected=1.1 x operating pressure

    Cuttingtravel length

    Marking line forboring bit.

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    25/46

    Engineer In Society ( VAB 4042 ) Project Report

    25

    9 . Connecting high pressure air hoses between hot tap machine and power

    unit/air compressor.

    10. Hot tap perforation.

    A non-hydrocarbon gas, Nitrogen gasis injected to suppress oxygen in the air to

    eliminate one element of the fire triangle.

    Before perforation:

    Valve is in open position. Then, Nitrogen gas is injected to the hot tapping

    machine after it is mounted to the isolation valve.The bleed valve is opened;

    Nitrogen gas is injected again for about 2 seconds to purge out the natural gas

    inside the valve chamber that may contain oxygen which can cause explosion.

    Bleed valve is closed, nitrogen gas supply stopped. Nitrogen gas inside the

    chamber is 2.5bar.Perforation is done.

    After perforation:

    Perforation is confirmed when pressure on the gauge drops to atmospheric

    pressure.Drilling is complete when the hot tapping machine reached marked link.

    Pipeline is tapped. Tapping is confirmed when pressuredrops. From 2.5 bars on the hottapping machine gauge. The pressureafter tap is the pipeline pressure

    Figure 18: Hot Tap Perforation

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    26/46

    Engineer In Society ( VAB 4042 ) Project Report

    26

    11. Bleeding Off Gas AfterFirst Penetration and After Perforation Completion.

    12 . Releasing Pressure from Hot Tap Machine After Completion.

    13 . Unbolting Hot Tap Machine From Tapping Valve.

    14 . Probe Installation

    Temperature transmitter Flow transducer (horizontal) Sensor element (horizontal)

    Flow transducer (vertical ) Sensor element (vertical) Pressure transmitter

    Flow computer Flow computer Figure 19: Probe Installation

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    27/46

    Engineer In Society ( VAB 4042 ) Project Report

    27

    15 . Housekeeping.

    COST ESTIMATION

    Operators can assess the economics of performing a hot tap as an alternative to a

    shutdown connection by following the five steps below:

    Five Steps for Assessing Hot Tap Economics:

    i. Determine physical conditions of existing line.

    ii. Calculate cost of performing a shutdown interconnects.

    iii. Calculate the cost of a hot tap procedure.

    iv. Evaluate the gas savings benefits of hot tapping.

    v. Compare the options and determine the economics of hot tapping.

    Step 1: Determine physical conditions of the existing line.

    To ensure safety and as a preparation of hot-tapping project, operators need to

    determine the maximum operating pressure (during the hot tap), type of pipe material

    (steel, cast iron, plastic), condition of the parent pipeline (internal/external conditions

    to evaluate include the location of nearby valves for emergency and corrosion, wall

    thickness) to assure a safe project, location of nearby valves for emergency isolation in

    the event of an accident, desired tap diameter depends on size of pipeline involve,

    working space around the connection, location of other pipeline welds and

    imperfections or obstructions. Operators should also determine if the line is looped,

    as many gas transmission companies avoid operational disruptions by shifting the load

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    28/46

    Engineer In Society ( VAB 4042 ) Project Report

    28

    to a parallel line. It is advisable to develop and follow a written plan to assure full and

    proper evaluation of a future connection.

    Step 2 : Calculate cost of performing a shutdown interconnect.

    To tap a new point on a pipeline, there are two options, either to shutdown

    interconnects or keep the pipeline online while hot-tapping is done.Thus, it will be

    important to calculate the cost of both options. The cost of an actual project would

    include Direct costs ( Material and equipment, welding requirements, quality control,

    blow down and purge costs, labor, and scheduling expenses) and H idden costs ( Costof shut-off valves, advertising if service is to be interrupted, relighting of customer

    services, and excavating for stopples and purge connections). Operators would be

    advised to reference historical data to determine these costs. For the purposes of this

    scoping analysis, material and labor costs for cutting out the line section and welding

    in a tee connection in the shutdown method are assumed to be comparable to the cost

    of welding on the fitting and performing the hot tap when the branch connection is the

    same size as the pipeline. However, the costs of the gas lost through venting and inert

    gas purging are unique to the shutdown interconnect.The formulas used to determine

    the cost of a shutdown interconnects are shown in Exhibit 3. For these calculations,

    low pressure is defined as less than 2 psig.For comparative purposes, calculating the

    cost of a shutdown interconnects should take into consideration a multiple-project

    scenario. This multiple-project perspective allows for a more complete comparative

    cost analysis given the up-front capital costs of owning and operating a hot tap

    machine and the need to perform several interconnections throughout a given year.

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    29/46

    Engineer In Society ( VAB 4042 ) Project Report

    29

    Exhibit 4 illustrates how the cost calculations in Exhibit 3 can be applied in a

    multiple connection scenario. The hypothetical situation presented includes several

    projects on pipelines of various sizes and pressures. Cost calculations, however, are

    only provided for the 4-inch pipeline scenario and only cover direct costs.

    Exhibit 3 : Calculating the Cost of Shutdown Interconnect

    Given:D = diameter of pipeline (inches)T = taphole diameter (inches) - for low pressure shutdown with tapholes for stoppersL = length of pipeline between tapholes (feet) - for high pressure shutdownP = line pressure (psia for low pressure, psig for high pressure)

    Ppgas = current purge gas market price ($/Mcf) - assumed $4/Mcf Pg = current gas market price ($/Mcf) - assumed $3/Mcf Ce = cost of extra excavation, use company records ($)Cp = cost of purge connections and excavationCs = cost of hidden shutdown expenditures, see Appendix ($)Cf = cost of fittings, see Appendix ($) Time Taphole is open = from prior experience (minutes)

    Calculate Direct Costs:

    1. 2 . 3 . 4 . 5 . 6 .

    7 . =

    8 . Calculate Indirect Costs:1. Calculate Ce = cost of extra excavation for tie-in ($)2. Calculate Cp = cost of purge connections ($)3. Calculate Cs = cost of hidden shutdown expenditures ($)4. Calculate Cf = cost of fittings ($)

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    30/46

    Engineer In Society ( VAB 4042 ) Project Report

    30

    Table 3: Exhibit 3Additional factors that are company specific include gas leakage past the pipeline

    valves on both ends of the shutdown, number of stoppers, tap holes for venting and

    purging, and type of purge gas. Leakage is particularly important as large pipeline block

    valves can leak significant volumes of gas because they are used infrequently and the

    valve seat can accumulate debris that inhibits a tight seal. The volume of leakage is

    highly variable, dependent on valve type, age, pipeline pressure and service (dry gas

    causes much less corrosion and accumulation of debris than wet gas). If a partners

    individual evaluation following this lesson learned results in marginal economic

    justification, then company experience on pipeline valve leakage 9 should be factored in

    to improve the economics.

    Step 3 : Calculate the cost of a hot tap procedure.

    When comparing the up-front costs of hot tapping with shutdown interconnects

    the only significant difference is the cost of the hot tap equipment. The tee fitting or full

    encirclement sleeve and the valve have nearly the same cost for either method when the

    branch is essentially the same size as the pipeline. The cost of welding a full

    encirclement sleeve is nearly the same as the cost of welding a tee fitting in a line.

    Labor cost for cold cutting the pipeline and hot tap cutting out a coupon are

    sufficiently close for this type of feasibility evaluation. Maintenance costs apply only to

    hot tap equipment, such as drill sharpening and other equipment care and replacement.

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    31/46

    Engineer In Society ( VAB 4042 ) Project Report

    31

    Tapping machines come in several sizes, and a single machine can perform hot taps

    from 3 to 12 inches. Less expensive machines can be purchased to perform small taps. In

    general, capital costs for purchasing the hot tap machines typically used by gas

    companies for the most common sized connections range from $13,200 to $23,000.

    Equipment cost is normally a one-time capital expenditure and can be

    depreciated over the life of the equipment, typically 15 to 20 years. Each company,

    however, should calculate the depreciation in the same manner used for other equipment

    purchases. This should be considered in conjunction with how often the machine will be

    used in the future. To make this determination, operators should look at companyrecords to determine the number of times similar connections have been performed.

    Typically, a company that performs several hot taps a year will find it economical to

    own the equipment, especially in sizes up to 12 inches, and to maintain trained personnel

    to perform the service. These jobs are usually simpler and require less specialized

    training than larger hot tap jobs. For larger and less frequent hot taps a company might

    consider it more cost effective to hire a contractor who will supply the equipment and

    trained personnel. Most hot tap vendors will supply all necessary tapping equipment,

    including the drilling machine, fittings, valves, cutters, and repair services. The majority

    of vendors also offer contract services for larger or infrequent jobs, or will rent out the

    tapping equipment. Supplying support services, such as excavation, welding, and cranes,

    can reduce the costs of using an outside contractor.

    Other factors, such as the line material and thickness, system pressure, and

    temperature, should also be considered when determining the alternatives of purchasing

    hot tapping equipment or hiring contractors. A company should evaluate how often the

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    32/46

    Engineer In Society ( VAB 4042 ) Project Report

    32

    tapping equipment would be used and if they would realize savings by owning and

    maintaining the equipment and training operators.

    Exhibit 4 : Hypothetical Scenario and Example Calculation of Lost Gas andPurge Gas Costs for a Shutdown Interconnect

    Given: A pipeline company requires numerous shutdown or hot tap connections asfollows: Pipeline Diameters, Inches 4 8 10 18 Pipeline Pressures, psig 350 100 1,000200 Pipeline Lengths1, miles2 2 1 3 2 Annual Taps3, number 250 30 25 15

    (2 ) Calculate: Vpgas = Volume of Purge Gas 4

    (3 ) Calculate: Value of Gas Lost by Shutdown Interconnects (Including PurgeGas)Calculate: Value of Gas Lost by Shutdown Interconnects (Including Purge Gas)

    Cost = $74 for each of the 4 inch pipeline shutdown interconnects

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    33/46

    Engineer In Society ( VAB 4042 ) Project Report

    33

    Table 4:Exhibit 4

    The procedures described above are general guidelines for preliminary economic

    assessment and can differ from company to company. Additional factors that are

    company specific include gas leakage past the pipeline valves on both ends of the

    shutdown, number of stoppers, tap holes for venting and purging, and type of purge gas.

    Leakage is particularly important as large pipeline block valves can leak significant volumes of gas because they are used infrequently and the valve seat can

    accumulate debris that inhibits a tight seal. The volume of leakage is highly variable,

    dependent on valve type, age, pipeline pressure and service (dry gas causes much less

    corrosion and accumulation of debris than wet gas). If a partners individual evaluation

    following this lesson learned results in marginal economic justification, then company

    experience on pipeline valve leakage 9 should be factored in to improve the economics.

    Exhibit 5 presents ranges of hot tapping costs for both equipment purchase and

    contracted services. The cost ranges shown include all materials; additional expenses

    will result from labor and maintenance expenditures, as discussed above. Vendors state

    that the operations and maintenance (O&M) costs can vary greatly, depending on the

    number of taps performed and equipment and procedural care.

    Exhibit 6 shows the equipment, O&M, and contractor services cost to per-form

    the 320 taps per year in the hypothetical scenario first described in Exhibit 4. The

    assumption is made that the 4, 8, and 10 taps (a total of 305 taps) would be

    performed by the company. Because few taps equal to or larger than 18 inches are

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    34/46

    Engineer In Society ( VAB 4042 ) Project Report

    34

    performed each year, these taps (a total of 15 taps) would be contracted to vendors. The

    equipment cost includes the purchase cost of two small (

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    35/46

    Engineer In Society ( VAB 4042 ) Project Report

    35

    Figure 21: Exhibit 7 and Exhibit 8

    Step 5 : Compare the options and determine the economics of hot tap-ping.

    The economic analysis shown in Exhibit 8 compares the significant cost and

    benefit differences between hot tapping and shutdown interconnections for the

    hypothetical scenario of 320 taps per year. The significant costs are the purchase,

    operation and maintenance of hot tapping equipment and/or contracting for hot tapping

    services. Here, both costs are included: the purchase of two hot tapping machines for

    $36,200 for the smaller sizes and contracting the 15 large taps at $37,500 per year. The

    purchased hot tap machines are operated and maintained at $5,500 per year. All these

    costs are calculated in Exhibit 6. Many expenses, including the cost of fittings, valves

    and basic labor, are assumed to be similar in both hot tap and shutdown procedures, and

    can be excluded in the comparative analysis. A more complete analysis can be done by

    evaluating and including the company specific hidden costs per Exhibit 3.The

    significant benefit differences are the reduction in natural gas loss by eliminating

    venting and the inert purge gas used in the shutdown interconnect procedure. As

    summarized in Exhibit 7, annual natural gas savings total 24,440 Mcf for the

    hypothetical hot tapping scenario, worth $73,320 per year at $3 per Mcf gas price. The

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    36/46

    Engineer In Society ( VAB 4042 ) Project Report

    36

    annual inert gas savings of 1,710 Mcf is worth $6,840 per year at $4 per Mcf of

    nitrogen, for a total annual benefit of $80,160.

    In conclusion, hot tapping has been found to be more cost effective than

    shutdown interconnects. Even when the system must be taken out of service, hot tapping

    presents opportunities for both time and cost savings. While hot tapping is a by

    companies for reasons other than the gas savings, consideration of the methane reduction

    benefits can often serve to justify hot tapping over the shutdown inter-connect procedure

    in a variety of circumstances.

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    37/46

    Project Report

    37

    SCHEDULING

    Figure 22: Scheduling

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    38/46

    Engineer In Society ( VAB 4042 ) Project Report

    38

    HEALTH & SAFETY ISSUES

    Hot taps are permissible only as a last resort, i.e. when safety, the time required

    and/or expense of isolation and decontamination is unreasonable or either of the

    preceding are less safe. If the facility is a covered process as defined by OSHA

    1910.119, then the sites Management of Change (MOC) Procedure must be

    followed. If a facility is not a covered process then an appropriate safety

    review/audit should be performed prior to the execution of the hot tapping/plugging.

    A special permit is required for all hot taps according to Safety Procedures, Fire

    Permits and Vessel Entry/Fire Permits.

    Compliance to Authority Standards and Guidelines

    There are several authority standard and guidelines to follow in completing this

    project. A lot of safety precautions to be take into account. The standard and

    guidelines are;

    A. Contact Safety for Sniff Test

    B. Permits required are Special Permit, Entry Permit (Vehicle),Welding

    Machine, Hot Tap Machine and Other machines or power equipment.

    C. Special Safety Requirements are Two (2) points of egression, Sewers in the

    area covered, Trapping required to retain welding sparks, Two (2) fire

    extinguishers at the Hot Tap site, Periodic Sniff Test, Area enclosed with

    barricade tape and Scaffolding if required

    Please note that providers must be accredited by the Qualifications Authority, or an

    inter-institutional body with delegated authority for quality assurance, before they

    can report credits from assessment against unit standards or deliver courses of study

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    39/46

    Engineer In Society ( VAB 4042 ) Project Report

    39

    leading to that assessment.[ iv]. All hot taps should be designed, fabricated, inspected

    and tested in accordance with the applicable Codes and Standards. The applicable

    standard for pressure vessels is usually the National Board Inspection Code (NBIC)

    or API Standard 510, Inspection, Repair, Alteration and Re-rating of Pressure

    Vessels. These Codes or Standards require that the design of the hot tap should also

    be in accordance with the original code of construction. In most cases in the US, this

    is typically the ASME Code Section VIII Division 1. In addition, API Recommended

    Practice RP 2201, Procedures for Welding or Hot Tapping on Equipmen t in

    Service, should also be followed [ v]

    Hazard Observation

    Hot tapping have an explosion hazard. Gas can ignite, causing explosion, death or

    serious injury. Tapping into pipe under pressure can cause severe injury if safety

    procedures are not followed. No person should make a hot tap unless that person has

    been trained and qualified in the use of equipment. Welding is one of element in this

    project, but it is the most crucial part of the project. This is because welding involves

    heat, hydrocarbon element in the pipeline and also oxygen gas available in the

    pipeline. Any carelessness may cause flame/explosion as all the elements in the fire

    triangle are available.

    Figure 23: Fire Triangle

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    40/46

    Engineer In Society ( VAB 4042 ) Project Report

    40

    To prevent explosion happen, consider the fire triangle. We must eliminate at least

    one of the factors to prevent fire which are flammable materials in the equipment,

    combustible materials in the equipment and flammable gas in the atmosphere.

    Fire Triangle elements;

    i. Oxygen

    a. Atmospheric air contains 20.9% oxygen

    b. Maintain physical separation between air and fuel as far as

    possible

    c. Use line packing concept whenever there is a breach of the

    physical barrier

    i. Pressurize containers such that oxygen cannot step in

    ii. Blanketing

    ii. Fuel

    a. Always present in hydrocarbon and petrochemical facilities

    b. Detection methods used to monitor leakages of fuel

    iii. Ignition Source

    a. Energy is used to operate equipment in the plant

    b. Contained based on standards used to define the hazards of

    ignition in the plant

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    41/46

    Eng ineer In Soc iet ( VAB 4042 ) Pro ject Repor t

    41

    Fi 24: poss i l gas l ak i ti i and covered

    Figure 25 : (a)Surround ing LEL iden ti ied us ing gas de tector

    (b) F ire wa ter is ready in case of emergency.

    Safe ty Precau tions before we lding works are ;

    i. Close / cover a ll poss i b le gas leakage /source

    ii. Make sure tapp ing po int is far enough from poss i b le leakage source

    iii. Iden tify w ind d irec tion by observ ing w ind sock. W ind may br ing gas

    leakage to the we ld ing area and cause f lame

    iv. Always measure lower exp los ion limit LEL leve l us ing gas de tec tor

    v. Always make sure that f ire wa ter is ava ilab le when needed in case of

    emergency

    W ind sock

    Poss i blegas leak

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    42/46

    Engineer In Society ( VAB 4042 ) Project Report

    42

    DISCUSSIONS& RECOMMENDATIONS

    This last chapter will give the big picture for the hot tapping projects outcomes,

    necessary recommendation and conclusion.

    Discussion of the Outcomes

    Each year pipelines typically undergo several transformations. Performing hot taps to

    make these connections and installations can reduce methane emissions from

    pipelines and increase savings and efficiency. The following are several lessons

    learned offered by partners and hot tap vendors:

    1) Hot tapping has been performed by transmission and distribution companies

    for decades. By evaluating the gas savings associated with this practice, hot

    tapping can be used in many situations where it would not ordinarily have

    been used

    2) The site for the branch weld must be free of general corrosion, stress

    corrosion cracking, and laminations.

    3) Hot tap should not be performed immediately upstream of rotating equipment

    or automatic control valves, unless such equipment is protected from the

    cuttings by filters or traps.

    4) For tapping on steel pipes, fitting generally consist of a welded branch

    connection. However, when tapping into cast iron, asbestos cement, or

    concrete, the fitting cannot be welded onto the existing header. Alternative

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    43/46

    Engineer In Society ( VAB 4042 ) Project Report

    43

    fitting attachment techniques, such as a split cast iron compression sleeve or a

    mechanical joint saddle, must be employed

    5) For plastic systems, the operator should ensure that the hot tapping fittings

    are compatible with the type of plastic pipe in the system and appropriate

    joining methods are used. Vendors can supply suitable fittings and tools for

    almost every kind of plastic system

    6) If hot tapping has not been performed in the past, hot tapping procedures

    should be developed and personnel trained. Be sure to include instructions

    concerning possible burn through or hydrogen cracking during welding

    7) All equipment must meet minimum industry and federal standards for

    pressure, temperature, and operating requirements

    8) If conditions of temperature, pressure, pipe composition, or tap diameter are

    encountered that are unusual for your system, be sure to consult the

    manufacturer of the tapping equipment or fittings

    9) Industry and federal codes and standards should be consulted for more

    specific specifications

    10) Record emissions reductions associated with using hot taps and submit them

    with your Natural Gas STAR Annual Report

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    44/46

    Engineer In Society ( VAB 4042 ) Project Report

    44

    Recommendations

    A decision on whether hot tapping is to be applied shall be based on careful

    considerations including at least the following aspect which are;

    Safety

    Condition of the pipe/equipment under consideration

    Configuration of the connection

    Code/statutory requirements

    Operating conditions

    Technical capabilities of the drilling equipment under the operating

    conditions (pressure, temperature, nature of product)

    Related welding problems

    Economic aspects

    Environmental/pollution aspects

    If hot tapping is to be applied under conditions approaching the technica l or

    operational limits, specialist advice should be sought

    Conclusion

    Hot tapping is potentially hazardous and therefore should only be undertaken when

    continuity of service is essential or shutdown of the system is impractical and when it

    is shown to be technically feasible and to offer a clear advantage over alternatives.

    The advantage may be economic and, in some situations, the safety and

    environmental risk may be less than those associated with more conventional

    methods.

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    45/46

    Project Report

    45

    APPENDICES

    Appendix i: Hot Tap Metering Installation Work Breakdown Structure

    Hot Tap Metering Installation W ork Breakdown Structure

    1.1.1Product Requirement

    Specification

    1.2.1Project Management PlanChecklist 1.2.2Project Estimation

    1.1Project Directive1.2Project Management Plan 1.2.3Issue Management Plan 1.

    1.2.4Risk Management Plan 1. Initiation 1.3Configuration Management 1.3.1Document Master Checklist 1.3Phase Plan

    1.4Project Timeline 1.4.1Work Breakdown Structure 1.

    2.1.1Schematic Block Diagram2.1.2Bill of Material

    2. Development 2.1Electrical 2.2.1Industrial DesignPhase 2.2Mechanical 2.2.2Drilling and Welding 2

    Hot TapMeteringInstallation 3.Procurement 3.1Supplier Management Plan 3.1.1Scope of Work

    Phase 3.2Procurement 3.1.2Requisition of Order 3.1.3Puchase of Order 3.1.4Quotation3.1.5Delivery of Order 3.2.1Samples Prototype

    4. Closure 4.1Project Closure Report 4.1.1Compile All Related Document 4.1Phase

  • 8/7/2019 EIS_INSTALLATION OF METERING INSTRUMNETS ON FLARE PIPELINE

    46/46

    Engineer In Society ( VAB 4042 ) Project Report

    REFERENCES

    iwww. koppl .com/pdfs/ Hot tap.pdf

    iihttp://www.globalmethane.org/documents/events_oilgas_20090127_techtrans_day2 _robinson3_en.pdf

    iiihttp://en.wikipedia.org/wiki/Methane

    ivhttp://www.nzqa.govt.nz/nqfdocs/units/pdf/10983.pdf

    vhttp://www.carmagen.com/news/engineering_articles/news38.htm