EIA Railways

71
E507 Volume 4 ENVIRONMENTAL AUDIT OF DC TO AC CONVERSION PROJECT OF RAILWAYS (Submitted to Mumbal Mebopoitan Region Development Authorwity, GovL of Maharashtra) Serene Environm l Services 800, 'Devaviub', Plot No. 3, Sector 17, Vashi, mvi Mmbal 400705 Telefax -786926 E MIal: seaeneavsn1 com Web afth: www. screnenviro com JUNE 2002 FILE CnPY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Transcript of EIA Railways

E507Volume 4

ENVIRONMENTAL AUDIT OF DC TO ACCONVERSION PROJECT OF RAILWAYS

(Submitted to Mumbal Mebopoitan Region DevelopmentAuthorwity, GovL of Maharashtra)

Serene Environm l Services800, 'Devaviub', Plot No. 3,

Sector 17, Vashi, mvi Mmbal 400705Telefax -786926

E MIal: seaeneavsn1 comWeb afth: www. screnenviro com

JUNE 2002

FILE CnPY

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Environmental Audit of DC - AC Serene Environmental ServicesConversion Projects

TABLE OF CONTENTS

Sr. No. Description PageNumber

Executive Summary

1.0 Introduction 11.1 Background 11.2 Statement Of Purpose 1

2.0 Project Details 12.1 Project Need 12.2 Project Components and Implementation Status 2

3.0 Scope And Methodology 53.1 Scope and Methodology 53.2 Legal Requirements 6

4.0 Environmental Impacts 9

5.0 Assessment of Environmental Mitigation Measures 125.1 Introduction 125.2 EHS Mitigation Measures 12

6.0 Environmental Monitoring And Reporting 196.1 Environmental Monitoring Program 196.2 EMP Monitoring Program 19

6.2.1 EMP Monitoring and Reporting during 20Construction Phase

6.2.2 EMP Monitoring and Reporting during Operation 21Phase

6.3 Institutional Setup 226.4 Institutional Strengthening 236.5 Estimated Cost of EMP Implementation 24

Environmental Audit of DC - AC Serene Environmental ServicesConversion Projects

LIST OF TABLES

Table Description Page NumberNumber

1.0 Detailed Scope and Methodology 5

2 0 Approximate Weight and Quantity of Released material for DC - 10AC project

3.1 EHS Mitigation Measures (Pre-Construction / Design Stage) 133.2 EHS Mitigation Measures (Construction Stage) 143.3 EHS Mitigation Measures (Operation Stage) 174.0 Training Program for Institutional Strengthening 235.0 Cost of EMP Implementation 24

LIST OF FIGURES

Figure Number Descripton1.0 Existing Organization Framework

LIST OF ANNEXURES

Annex DescriptonNumber

1A.< Terms of Reference for carrying out Environmental Audit of Railway Projects1B. Legal Requirements2.0 Site Photographs2.1 Details of Public Consultations3. Vendors authorised by MOEF for disposal of Hazardous Wastes4. Environment/ Health/ Safety Inspection Sheet5. Documentation to be maintained by contractor or railway site engineer on site6. Survival reporting for tree plantation

Environmental Audit of DC- AC Serene Environmental ServicesConversion Pmject of Railways

LIST OF ABBREVIATIONS

AAQ: Ambient Air Quality

AC: Alternating current

CEMP: Community Environment Management Plans

DC: Direct Current

EA: Environmental Assessment

EMP: Environmental Management Plan

EHS Environment, Health and Safety

FOB: Foot over-bridges

GOM: Government of Maharashtra

MMR: Mumbai Metropolitan Region

MOEF: Ministry of Environment and Forests

MGGM: Municipal Corporation of Greater Mumbai

MMRDA: Mumbai Metropolitan Regional Development Authority

MRVC: Mumbai Rail Vikas Corporation

MSEB: Maharashtra State Electricity Board

MUTP: Mumbai Urban Transport Project

PIA: Project Implementation Agency

PUC Pollution Under Control

RAP: Rehabilitation Action Plan

ROW: Right of Way

R&R Resettlement and Rehabilitation

SES: Serene Environmental Services

WR: Western Railway

CR: Central Railway

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

EXECUTIVE SUMMARY

1.0 INTRODUCTION

The Mumbai Urban Transport Project (MUTP) has identified a number of sub-projects tostrengthen the suburban rail transport and road transport in Greater Mumbai and MumbaiMetropolitan Region (MMR) as a whole. MUTP places considerable emphasis on improvingpublic transport including the railway capacity.

Environmental Assessments (EA) was done for some of these sub-projects in the years 1996to 1998. Also, a consolidated EA was prepared for the entire MUTP project. EnvironmentalManagement Plans (EMP) was prepared as a part of these EAs, which included mitigationmeasures for minimising adverse environmental impacts. Currently, several of these sub-projects are in different stages of construction and MMRDA desires to carry out anassessment of the relevant EMPs.

This assignment pertains to the EMP assessment/audit for the project involving conversion ofthe current 1500 V DC traction system to 25000 V AC system. This system is beingimplemented at various routes of both Westem Railway (WR) and Central Railway (CR).

Mumbai Metropolitan Region Development Authority (MMRDA) has retained the services ofSerene Environmental Services (SES) to carry out Environmental Audit for railway projects ofMUTP.

2.0 OBJECTIVES OF THE STUDYThe Objectives of Environmental Audit are as follows:* Assess whether any activity of the project will have impacts on the environment such as

construction of sub-stations within coastal regulation zone.* Assess impacts of disposal of old DC transformers.* Suggest environmental management plan, if required, for mitigating environmental impact.

3.0 PROJECT COMPONENTS

The conversion is being done on various sections of both WR and CR. The broadcomponents of the project are as follows:

1. Modification to the existing overhead equipment (OHE) to suit the insulation level of 25kV.

2. Modification to the existing over line structures such as foot over bridges (FOB's), roadover bridges (ROB's).

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

3. Power supply arrangement for 25 kV system4. Modification to the existing low tension supplies5. Modification to the telecommunication installation6. Modification of the signaling installation with Audio frequency7. Modification to Electrical Multiple Units (EMU's)8. Modifications to Electrical Locomotives9 Miscellaneous. Civil Works. These include the following:

* Rebuilding/raising FOBs which are not having sufficient clearances to accommodateAC traction

. Freezing the rail level under ROBs having critical clearances for AC traction bybuilding ballast less track under them

. Construction of electrical and service buildings such as substations, relay rooms,cable huts etc.

. Construction of quarters, office accommodations, office rest houses and seniorsubordinates rest houses as per requirements.

At present 20 nos. of DC substations on Westem Railway and 49 nos. of DC substations onCentral Railway are feeding DC power supply for running the trains in Mumbai SuburbanNetwork. With switch over to 25 kV AC system, only 5 nos. of AC substations on WesternRailway and 13 nos. of AC substations on Central Railway will suffice.

The new substations will be provided at Mahalakshmi, Bandra, Jogeshwari, Borivali andVasai Road on Westem Railway and at Chinchpokali, Vidyavihar, Thane, Thakurdi, Vangani,Karjat, Titwala, Asangaon, Kasara, Raoli, Mankhurd, Sea wood and Panvel on CentralRailway.

lmplementation Status- Central RailwaYOn the Central Railway (CR) route, the conversion will be done in 4 phases:

Phase 1: Vasai - Panvel - Jasai (Non-suburban route)Titwala - Igatpur stations

Phase 2: Tilak-nagar - Panvel; Thane - Turbhe stations

Phase 3: Thane - Kalyan stationsPhase 4: Thane to CSTM stations

Phase 1 and 2 are in progress. Phase 3 will commence after completion of Phase 1 and 2Conversion in the suburban Phase 4 is expected to commence only after the year 2005.

Implementation Status- Western Railwav

On the Western Railway (WR) route, the conversion will be done in 3 phases:Phase 1: Borivali to Virar stationsPhase 2: Andheri to Borivali stationsPhase 3: Churchgate to Andheri stations

.

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

The OHE component in Phase 1 is about 90% complete. The expected date of completionfor Phase 1 is December 2002.

Phase 2 and Phase 3 implementation will begin after completion of Phase 1. The expecteddates of completion for Phase 1 and 2 are December 2004 and December 2006 respectively.

3.1 Applicable Legal Requirements

The applicable Indian environmental regulations, Wodd Bank policies/directives and GOMdirectives for all MUTP projects are given in detail in the Final Consolidated EnvironmentAssessment (EA) Report on MUTP, 2002 prepared by MMRDA. This EMP's for the DC to ACconversion project have been prepared within the Policy and Legal Framework outlined in theConsolidated EA (CEA), Report for MUTP, 2002. The legal requirements applicable to the DCto AC conversion project are as follows:

Indian Environmental and Other RegulationsO Environmental (Protection) Act, 1986, associated Rules and Notifications under the Act.O The Maharashtra (Urban Areas) Preservation of Trees Act, 1975O Land Acquisition Act 1894 (LA Act)O Maharashtra Regional and Town Planning Act, 1966 (MR&TP Act):O Development Control Regulations for Greater Mumbai 1991 (DCRs)

World Bank PoliciesO Environmental Assessment (OP 4.01)

4.0 ENVIRONMENTAL IMPACTS

Air Quality and Noise:Of all works in DC-AC project, only construction of AC sub-stations and laying of cables (fromMSEB to substations) has a potential'of causing minor negative impacts.

These impacts are typical to any minor civil construction. The magnitude of construction issmall and the associated impacts are not considered significant. Prior permissions for cablelaying will be taken from MCGM/Concerned Municipal Office.

Environmental impacts from waste disposalScrap DC electrical components such as insulators, cables, transformers etc. will be the mainwastes from this project. Good working components will be reused for maintenance of routeswith existing DC components. Generally the waste material generated will be the ones, whichcannot be serviced. These are sent to railway stores for auction. The amount of waste

ill

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

generated in the project till date in WR and CR (mainly for sections where work is in progress)and the current handling and disposal modes are given below in Table 2. Photo 4 showsthe scrap yard at Bhayandar. Discarded insulators and other material are stored here beforedisposal by sale.

One of the critical environmental issues in DC-AC project is disposal of scrap transformnersand switch gears that have oils. These oils could have Polychlorinated Biphenyls (PCBs)which is used as dielectric and heat exchange fluid. PCBs and their impurities are known torepresent a threat to human health and the environment. Thus managing PCB containingwastes is necessary.

As per a World Bank study, most transformers manufactured after 1985 do not have PCBs.The number of DC transformers likely to be replaced in WR and CR as a part of DC-ACconversion are given in Table 2. These transformers are unlikely to contain PCB's, sinceeven the transformers manufactured before 1985 have gone through several oil changes withnon-PCB containing transformer oils (Oil change required every 10 years). Oils manufacturedcurrently do not contain PCB's.

Ecological Impacts due to Construction Activities.Ecological impacts are possible if construction is done in ecologically fragile areas. None ofthe ecologically fragile areas in Greater Mumbai will be affected by the project. As mentionedeariier, in project component description, minor construction activities such as construction ofsub-stations, cable huts are involved.

Of particular significance here is the possibility of construction in Coastal Regulation Zone(CRZ) areas. Preliminary assessment has shown that none of the new AC sub-stations inChurchgate - Virar section and Thane-CST section (including one proposed at Mankhurd) willbe located in designated CRZ areas.

Some trees may require cutting in area designated for sub-stations. However, survey for thesame has not been done. As required by The Maharashtra Tree Felling Act, priorpermissions from tree officer of Municipal Corporation of Greater Mumbai (MCGM) orapplicable Forest officer will be taken before cutting down of any Tree (listed in the scheduleof the above Act)

Resettlement of Proiect Affected Households (PAH)Resettlement and rehabilitation (R&R) of any PAH will be done by MMRDA as per theRehabilitation Action Plan (RAP) of Govt. of Maharashtra.

Archaeological and Cultural Property

iv

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

Rehabilitation of Cultural Property such as archaeological and historical sites, religious(temples, mosques etc.) likely to be affected by the project is required by The World BankOperational Policy 4.11 on Cultural Property Preservation.

As per survey done by MMRDA, there are no such structure affected by this project.

5.0 Assessment of Environmental Mitigation Measures

Interviews and site visits have not indicated any significant adverse environmental impactcaused due the project activities. Any adverse impacts expected will be due to disposal ofhazardous waste material such as scrap transformers. No significant adverse impacts areexpected during the operation stage of the project.

Thus, as far as this project is concerned, recommendations for EMP implementation includethe following:

* EHS mitigation measures that could be included as a requirement for contractors for civilconstruction works and other related activities - Sub-stations, cable laying etc.

• EHS measures for waste handling, storage and disposal.* EMP monitoring and reporting mechanism including Institutional framework

5.1 Site Findings and Compliance For EHS Mitigation Measures

The EHS issues are addressed for the components given below for design, construction andoperation phases of the project.

* Ecological impacts such as tree cutting and destruction of mangroves.* Resettlement and rehabilitation* Utility relocation* Disposal of scrap hazardous material from DC-AC Project. Generation of Dust due to construction activity (Mainly applicable to Sub-Station

Construction)* Construction Vehicle /equipment exhaust emissions* Noise from vehicles, plants and equipment* Chocking of drains and other water bodies such as wells and lakes/ponds.* Soil erosion* Debris disposal* Soil contamination by construction wastes, fuel etc.* Land degradation in quarry area.e Health and hygiene at construction labour camps• Delays and congestion on tracks* Traffic Control and Safety

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

* Occupational Health and Safety* Hazardous material handling

Critical EHS recommendations for the project are given below, more details on audit findings andrecommendations are available in Tables 3.1 to 3.3 of this report.

Pre-construction and design stage:

1. Trees to be removed before commencement of construction, with prior permission fromForest Officer as required by the Maharashtra Tree Felling Act.

2. Resettlement is currently being carried out by MMRDA as per RAP of GOM. SeparateTransit and penmanent accommodations for project affected households should be audited atleast 6 monthly.

3. Plans should be made showing the route of cable laying along with areas affected, trafficdiversions required, utilities affected etc.

4. Cable laying work to be done strictly after prior approval of concerned Municipal/CivicAuthority.

5. All utilities, such as electrical installations, telephone lines etc. to be shifted only after priorapproval of agencies.

Construction Phase

1. All scrap transformers to be stored in dedicated areas with adequate precautions in RailwayStores.

2 Transformers (including waste transformer oils) should be sold to only vendors authorised byMOEF

3. Stores Dept. to ensure that Authorisation is available for handling and disposal of waste oil(including Transformer oil) from State Pollution Control Board, as per requirement ofHazardous Waste (Handling and Management) Amendment Rules, 2000.

4. Road wetting at construction sites for minimising dust emissions.5. All contractors to make sure that all dumpers and other vehicles being used at site have been

checked for vehicle emissions and have a valid PUC certificate.6. A clear documented procedure to be made part of the tender documents, requiring

contractors to dispose debris in low-lying areas away from water bodies, as fill material only.7. Documentation such as quarry release receipt issued by the District Revenue officer at the

quarry site to be available at construction site.8. Safety and hazard posters and signs should be clearly displayed at locations such as plafformn

works, level crossings, Station building construction areas etc.9. All safety precautions as mentioned in tender documents to be taken. An engineering work

permit is made by Western Railway for each site, after inspection of safety conditions as pertender requirements. C.R. to assure that a similar procedure for work permit is followed at allconstruction sites

10. CR/WR to assure that all contractors make available safety shoes, face masks, earplugs etc.as applicable to the labourers. Such PPE's should be available on site and assessment

vi

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

should be made during scheduled inspections. This requirement to be made a part of tenderdocumentation.

11. First aid boxes to be made available at site.

ODeration Phase1. Regular maintenance of track side plantation.2. Regular audits of material handling and disposal (storage, disposal practice and records)

6.0 Environmental Monitoring and Reporting

Site visits and interviews have revealed the following facts related to environmentalmanagement organisation:

In the consolidated EA report for MUTP, MRVC was reported to be the ProjectImplementation Agency (PIA). However, Central Railway (CRANR) is the PIA for thisproject. MRVC is the coordinating agency to facilitate communication between MMRDAand CR.

* CRNWR has incorporated certain EHS elements in the tender documents. Additionalrequirements to be induded are pointed out in Table 3.2 of this report.

* Environmental monitoring is currently not required to be done by the contractors. Apartfrom periodic general inspections, currently there is no feedback mechanism for EHSelements of the project.

Environmental impacts for thq project are limited to those caused by handling and disposal oTwastes, particularly hazardous wastes such as transformers and transformer oils and cablelaying work, cutting of trees, minor civil construction work etc.

The objectives of monitoring will best be achieved for this project by a comprehensiveperiodic site inspection program for EHS elements for the on-going construction activities.This is covered in Section 6.2. Physical periodic monitoring of ambient air quality, noise,water etc. for the construction and operation stages of the project are not recommended forthis railway project.

The recommended EMP monitoring and reporting mechanism, inspection schedule - format -responsibilities, current institutional mechanism, training requirements etc. are given in detailin Sections 6.1 to 6.5 of this report. The estimated cost of EMP implementation for DC-ACconversion project will be Rs. 1250000 (Table 5).

vii

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

1.0 INTRODUCTION

1.1 Background

The Mumbai Urban Transport Project (MUTP) has identified a number of sub-projects tostrengthen the suburban rail transport and road transport In Greater Mumbal and MumbaiMetropolitan Region (MMR) as a whole. MUTP places considerable emphasis on improvingpublic transport induding the railway capacity.

As per requirement of The World Bank, Environmental Assessments (EA) was done for somethese sub-projects In the years 1996 to 1998. Also, a consolidated EA was prepared for theentire MUTP project. Environmental Management Plans (EMP) was prepared as a part ofthese EAs, which included mitigation measures for minimising adverse environmentalimpacts. Currently, several of these sub-projects are in different stages of construction andMMRDA desires to carry out an assessment of the relevant EMPs.

This assignment pertains to the EMP assessment/audit for the project involving conversion of

the current 1500 V DC traction system to 25000 V AC system. This system is being

implemented at various routes of both Westem Railway (WR) and Central Railway (CR).

1.2 Statement of purpose

Mumbai Metropolitan Region Development Authority (MMRDA) has retained the services ofSerene Environmental Services (SES) to carry out Environmental Audit for railway projectsof MUTP. The scope of work is as per TOR given in the RFP no. PD/MUTP/EA/701/2001dated October 16, 2001 (Annex 1). The work was awarded to SES on November 7, 2001,after final negotiations on November 6, 2001.

Objectives of the study:

* Assess whether any activity of the project will have impacts on the environment such asconstruction of sub-stations within coastal regulation zone.

* Assess impacts of disposal of old DC transformers.* Suggest environmental management plan, If required, for mitigating environmental Impact

2.0 PROJECT DETAILS

2.1 Project Need

The trains in Mumbai have been running on 1500V DC electric traction since 1930. Worldover the 25KV AC traction system has been accepted during 1950. The changeover has nottaken place here due to several technical and execution problems.

tnvironfrienrwal AU( or L)u-o- as 6erene tnvironmenrai servicesConversion Project of Railways

The several benefits that will be achieved by conversion from DC to AC traction system are:

• Future long-term traffic requirement of Mumbai area can be met with less number oftraction substations

* Haulage of longer and heavier trains with a single locomotive.* Increase train speeds* Less transmission losses with higher voltage* Saving of wagon detention hours.* Lower maintenance* Reduction in contact wire wear and tear* Higher reliability, due to fast acting precise relay in AC system with less number of cables.

2.2 Project Components and Implementation Status

The conversion is being done on various sections of both WR and CR. The broadcomponents of the project are as follows:

1. Modification to the existing overhead ecuicment (OHE) to suit the insulation level of 25kV.

The OHE will need to be modified to suit 25KV AC traction. This involves changing theinsulators and modifying suspension points, terminabon points, cross span point etc.Photo I shows a view of the insulators that need to be replaced.

2. Modification to the existing over line structures such as foot over bridges (FOB's), roadover bridqes (ROB's).

More clearance between the overhead bridge structure and electrical wires will berequired for 25KV system. Thus modificabon to existing over-line structures such asFOB's and ROB's will be required. To avoid huge investment in raising or rebuildingROB's, it is also proposed to provide changes in the tracks to freeze the rail level.

3. Power supply arrangement for 25 kV system

New AC substations will be set up. The old DC sub-stations will be phased out. Apartfrom the traction substations, smaller switching stations at different locations are beingprovided to create sections in the event of a fault and facilitate maintenance. All thesepower supply installations will be unmanned and controlled from a remote centre.Photo 2 in Annex 2 shows an area near Borivali station been identified for setting upone of the new AC sub-stations Photo 3 shows one of the DC sub-stations atBhayandar to be dismantled.

4. Modification to the existing low tension suopliesIn this work, the L.T. overhead lines of 2.2 KV are being changed over to under groundcables at stations and washing lines. Independent source of power supply fromMSEB/BSES etc. will be taken for feeding the stations Battery charging facilities onwashing sidings will also be modified.

2

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

5. Modification to the telecommunication installationIn this work, optic fiber cables (OFC) and associated equipments are being provided.Modifications are done in the telecommunication circuits of Passengers Announciationsystem, PF indicators and clocks.

6 Modification of the signaling installation with Audio freauencvIn this work, the point motors are replaced with AC motors and the AC track circuits arereplaced with Audio frequency track circuits. Modifications to block instruments will alsobe carded out.

7. Modification to Electrical Multiple Units (EMU's)During the period when the conversion work is being executed, the suburban trains haveto run with AC power on some converted sections and with DC power on other sectionswhere conversion in progress / awaited, Modifications will have to be carried out in theElectrical Multiple Units (EMU's) so that they can operate on dual voltage i.e. on 1500 VDC & 25 kV AC. For this purpose retro fitment work is in progress. Two of the convertedrakes are already in operation.

8. Modifications to Electrical LocomotivesAs explained above, the locomotives which haul Mail & Express / Passenger / Goodstrains will also be modified to work on both the systems.

9. Miscellaneous. Civil WorksThese include the following:* Rebuilding/raising FOBs which are not having sufficient clearances to accommodate

AC traction. Freezing the rail level under ROBs having critical clearances for AC traction by

building ballast less track under them. Construction of electrical and service buildings such as substations, relay rooms,

cable huts etc.* Construction of quarters, office accommodations, office rest houses and senior

subordinates rest houses as per requirements.

At present 20 nos. of DC substations on Westem Railway and 49 nos. of DC substations onCentral Railway are feeding DC power supply for running the trains in Mumbai SuburbanNetwork. With switch over to 25 kV AC system, only 5 nos. of AC substations on WestemRailway and 13 nos. of AC substations on Central Railway will suffice.

The new substations will be provided at Mahalakshmi, Bandra, Jogeshwar, Borvali andVasai Road on Westem Railway and at Chinchpokali, Vidyavihar, Thane, Thakurli, Vangani,Karjat, Titwala, Asangaon, Kasara, Raoli, Mankhurd, Sea wood and Panvel on CentralRailway.

Implementation Status- Central Reilwa.On the Central Railway (CR) route, the conversion will be done in 4 phases:

Phase 1 . Vasai - Panvel - Jasai (Non-suburban route)Titwala - lgatpuri stations

3

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

Phase 2: Tilak-nagar - Panvel ; Thane - Turbhe stationsPhase 3: Thane - Kalyan stationsPhase 4: Thane to CSTM stations

Phase 1 and 2 are in progress. Phase 3 will commence after completion of Phase 1 and 2.Conversion in the suburban Phase 4 is expected to commence only after the year 2005.

Implementatlon Status- Western Railwa,On the Westem Railway (WR) route, the conversion will be done in 3 phases:Phase 1: Borivali to Virar stationsPhase 2: Andher to Borivali stationsPhase 3: Churchgate to Andheri stations

The OHE component in Phase 1 is about 90% complete. The expected date of completionfor Phase I is December 2002.

Phase 2 and Phase 3 implementation will begin after completion of Phase 1. The expecteddates of completion for Phase 1 and 2 are December 2004 and December 2006 respectively.

Public consultation have also been conducted for MUTP and its various components. *Thedetails of which are given in Annex 2.1.

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

3.1 SCOPE AND METHODOLOGY

Oblectives of Environmental Audit

* Assess whether any activity of the project will have impacts on the environment such asconstruction of sub-stations within coastal regulation zone.

* Assess impacts of disposal of old DC transformers.* Suggest environmental management plan, if required, for mitigating environmental impact.

The various tasks and methodology followed for completing these objectives are given belowin Table 1.0. Methodology followed is as per the Inception Report of the project.

Table 1.0 Detailed Scope and Methodology

Scope Methodology

Task I All reports were procured and reviewed for understanding theReview of previous reports project background.such as engineering design,MUTP consolidated EAreport etc.

Task 2 Site visits to representative existing DC substations to be de-Determination of significant commissioned and proposed sites of AC sub-stations.impacts on the air, noise and The project impacts will be limited to following:ecological environment due * Disposal of dismantled DC electrical componentsto current construction works such as insulators, cables, transformers etc.and future planned activities. *' Minor air and noise impacts due to construction of

new AC sub-stations.* Impacts of laying of underground cables.* Ecological impacts due to sub-station construction in

CRZ or ecologically fragile areas.

Scrap electrical component quantities, current disposal modesetc. were compiled by discussion with Railway authorities.The impacts were assessed by conducting limited site visitsand interviews with contractors and railway authorities.

No environmental monitonng is envisaged for this project asenvironmental impacts are mainly from disposal of scrapitems

5

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of lRailways

Table 1.0 ContScope Methodology

TASK 3 *1 Detailed site visits along tracks, and other* Preparation of EMPs for adverse planned works to assess EMP

environmental impacts identified requirements.for the completed and planned *' Interviews with localworks. contractors/MRVC/Railways regarding EMP

* Preparation of EMP matrix which implementation.includes the environmental *' Review of the organization structure andimpacts, specific EMPs, chain of command between contractors,responsibilities and authorities for Railway and MRVC.implementation etc. * Review of documentation related to

environmental mitigation maintained by* Reporting formats for tracking of RiwyadCnrcos

EMPs. Railway and Contractors.. Assess*te adequcy ofcurent Bl Recommendations with costing/design for* Assess the adequacy of current .

institutional arrangements and any additional environmental enhancementmeasures proposed.

suggest measures for * Criteria for the assessment will be good

*Strgengtheningrthesmenif required. environmental practices in the electrncal /* Suggest improvements in construction industry, MOST guidelines etc.

implementation of mitigation * EMP implementation framework, reportingmeasures in future activities, requirements etc. will be firmed up after

discussions with MRVC, Railway andMMRDA.

Visual assessment and interviews with local contractors mre carried out during the site visit toBhayandar DC Traction sub-station, proposed AC sub-station at Borivali and scrap yard. Thefollowing are the brief findings:

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

3.2 Applicable Legal Requirements

The applicable Indian environmental regulations, World Bank policies/directives and GOMdirectives for all MUTP projects are given in detail in the Final Consolidated EnvironmentAssessment (EA) Report on MUTP, 2002 prepared by MMRDA. This EMP's for the DC to ACconversion project have been prepared within the Policy and Legal Framework outlined in theConsolidated EA (CEA), Report for MUTP, 2002. The brief details of the applicable Policyframework are presented in Annex lB. The legal requirements applicable to the DC to AC

conversion project are as follows:

Indian Environmental and Other Regulationsnl Environmental (Protection) Act, 1986, associated Rules and Notifications under the Act.0 The Maharashtra (Urban Areas) Preservation of Trees Act, 1975D Land Acquisition Act 1894 (LA Act)O Maharashtra Regional and Town Planning Act, 1966 (MR&TP Act):o Development Control Regulations for Greater Mumbai 1991 (DCRs)

World Bank Policies0 Environmental Assessment (OP 4.01)

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

4.0 Environmental Impacts

Air Quality and Noise:Of all works in DC-AC project, construction of AC sub-stations and laying of cables (fromMSEB to substations) has a potential of causing minor negative impacts on Ambient AirQuality and noise Photos Nos. 2 and 3 show the proposed site for new AC sub-station atBorivali and DC sub-station at Bhayandar respectively.

These impacts are typical to any minor civil construction. The magnitude of construction issmall and the associated impacts are not considered significant. Prior permissions for cablelaying will be taken from MCGM/Concemed Municipal Office.

Environmental Impacts from waste disposalScrap DC electrical components such as insulators, cables, transformers etc. will be the mainwastes from this project. Good working components will be reused for maintenance of routeswith existing DC components. Generally the waste material generated will be the ones, whichcannot be serviced. These are sent to railway stores for auction. The amount of wastegenerated in the project till date in WR and CR (mainly for sections where work is in progress)and the current handling and disposal modes are given below in Table 2. Photo 4 showsthe scrap yard at Bhayandar. Discarded insulators and other material are stored here beforedisposal by sale.

One of the critical environmental issues in DC-AC project is disposal of scrap transformersand switch gears that have oils. These oils could have Polychlorinated Biphenyls (PCBs)which is used as dielectric and heat exchange fluid. PCBs and their impurities are known torepresent a threat to human health and the environment. Thus managing PCB containingwastes is necessary.

As per a World Bank study, most transformers manufactured after 1985 do not Aave PCBs.The number of DC transformers likely to be replaced in WR and CR as a part of DC-ACconversion are given in Table 2. These transformers are unlikely to contain PCB's, sinceeven the transformers manufactured before 1985 have gone through several oil changes withnon-PCB containing transformer oils (Oil change required every 10 years). Oils manufacturedcurrently do not contain PCB's.

9

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

Table 2. Approximate Weight and Quantity of Released material for DC-AC project

Sr. Item Quantity Quantity Current handling Possible EnvironmentalNo. WR - CR -Entire and disposal Impacts

Dahisar to project)Virar

_ ____________ (Phase 1)I Non Ferrous 4.21 tons 120 tons This material is sent to No adverse direct impact

Material railway foundries from DC-AC project(Parel and other activites.

Catenary locations) for reuse.suspension Non-serviceable itemsclamps, Contact are sent to stores forwire swivel clips, onward sale throughcontact wires auction.etc.)

2. Ferrous 26.98 tons 300 tons This material is sent to Ferrous material ismaterial scrap yards-for sale recycled. No adverse directFittings, through auction. impacts from DC/AC projectassemblies, activities.brackets etc.

3. Porcelain 1290 nos. Not yet Good insulators will be Currently no procedure forInsulators estimated. used to maintain disposal. Could cause

(Only existing tracks with DC minor impacts such asdamaged traction. Damaged obstruction of drains etc. ifones will be ones will be sent to not disposed property.wastage) scrap yard. These are

normally used as fillmaterial

4. DC From About 70 to Oid good and * Normally transformnerTransformersl Phasel, 2, 3 80 Old DC serviceable parts are separated byswitchgears transformers transformers will be the parties and sold

About 43 Old will be reused in existing individually.DC generated sections with DC P*Adverse impacts ontransformers from traction. Transfomners ground/ surface waterwill be demolishing to be scraped will be bodies and land possiblegenerated DC sub- sent to Railway stores if transformer oils notfrom stations for disposal through disposed properly.demolishing auction. * Occupational healthDC sub- Transformer/switch- impacts possible due tostations gear oils are handling waste

separated and sold transformer oils. Properseparately. handling proceduresTransformer oils are necessarsold to vendorsauthorized byMOEF.(See Annex2)

10

Environmental Audit of DC- AC Serene Environmental SeMCeWConversion Project of Railways

Impacts on Natural Habitats and EcoloavEcological impacts are possible if construction is done in ecologically fragile areas. None ofthe ecologically fragile areas in Greater Mumbai will be affected by the project. As mentionedearlier, in project component description, minor construction activities such as construction ofsub-stations, cable huts are involved.

Of particular significance here is the possibility of construction in Coastal Regulation Zone(CRZ) areas. Preliminary assessment has shown that none of the new AC sub-stations inChurchgate - Virar section and Thane-CST section (including one proposed at Mankhurd) willbe located in designated CRZ areas.

Some trees may require culling in area designated for sub-stations. However, survey for thesame has not been done. As required by The Maharashtra Tree Felling Act, priorperrtissions from tree officer of Municipal Corporation of Greater Mumbai (MCGM) orapplicable Forest officer will be taken before cutting down of any Tree (listed in the scheduleof the above Act)

Resettlement of Proiect Affected Households (PAH)Resettlement and rehabilitation (R&R) of any PAH will be done by MMRDA as per theRehabilitation Action Plan (RAP) of Govt. of Maharashtra.

Archaeological and Cultural Property

Rehabilitation of Cultural Property such as archaeological and historical sites, religious(ternples, mosques etc.) likely to be affected by the project is required by The World BankOperational Policy 4.11 on Cultural Property Preservation.

As per survey done by MMRDA, there are no such structure affected by this project.

I I

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

5.0 Assessment of Environmental Mitigaffton Measures

5.1 Introduction

The previous sections described the possible ernironmental impacts from the DC-AC project.This section is dedicated to formulating Environmental Mitigation measures for the adverseenvironmental impacts identified for the project and drawing up of an EnvironmentalManagement Plan (EMP).

Interviews and site visits have not indicated any significant adverse environmental impactcaused due the project activities. Any adverse impacts expected will be due to disposal ofhazardous waste material such as scrap transformers. No significant adverse impacts areexpected during the operation stage of the project.

Thus, as far as this project is concemed, recommendations for EMP implementation includethe following:

* EHS mitigation measures that could be included as a requirement for contractors for civilconstruction works and other related activities - Sub-stations, cable laying etc.

* EHS measures for waste handling, storage and disposal.* EMP monitoring and reporting mechanism including Institutional framework

5.2 EHS Mitigation Measures

The mitigation measures identified in Tables 3.1 and 3.2 should be complied by WR andCR by assigning responsibilities for the same to various departments and making it a part ofcontractor requirements where relevant.

12

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

TABLE 3.1 EHS Mitigation Measures (PRE-CONSTRUCTION / DESIGN STAGE)Environmental EHS Mitigation Measures To be taken Responsibility **

Impact Implementation Supervision

Ecological impacts Trees to be removed before commencement of construction, withsuch as tree cutting prior permission from Forest Officer as required by The Maharashtra WR/CR - Site Engineer with WR/CR- Site Engineer &

(Urban Areas) Preservation of Trees Act, 1975 contractor Executive Engineer

Utility relocation Plans should be made showing the route of cable laying along withareas affected, traffic diversions required, utilities affected etc. WR/CR - Site Engineer with WR/CR- Site Engineer &

Cable laying work to be done strictly after prior approval of concerned contractor Executive Engineer

Municipal/Civic Authority.

All utilities, such as electrical installations, telephone lines etc. to beshifted only after prior approval of agencies.

13

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

TABLE 3.2 EHS Mitigation Measures (CONSTRUCTION STAGE)

Environmenta1 EHS Mitigation PIleasures To be taken Respon ibility **Impact Implementation SupervisionDisposal of scrap All scrap transformers to be stored in dedicated areas with adequatehazardous material precautions in Railway Stores. WR/CR - Site Engineer and WR/CR- Site Engineer &from DC-AC Project Transformers (including waste transformer oils) should be sold to Stores Department respective Executive Engineers

only vendors authorised by Ministry of Environment and Forests. Listof such vendors are given in Annex 3..Stores Dept. to obtain Authorisation for handling and disposal ofwaste oil (including Transformer oil) from State Pollution ControlBoard, as per requirement of Hazardous Waste (Handling andManagement) Amendment Rules, 2000. All waste handling, storageand disposal to be as per these Rules.

Generation of Dust Construction site to be watered periodically to minimise fugitive dust WR/CR- Site engineer anddue to construction generation. Site Contractor Executive Engineer,activity(Mainly applicable to Dumpers should be covered by tarpaulin to minimise dust generation WR/CR- Site engineer andSub-Station and spillage Site Contractor Executive Engineer,Construction) All Earthwork and construction material should be protected in such a Wi

manner so as to minimize Veneration of dust. Site Contractor Executive Engineer,Construction Vehicle Exhaust emissions from all construction vehicles shall adhere to/equipment exhaust vehicle emission norms. All contractors to make sure that all Site Contractor WR/CR- Site engineer and

dumpers and other vehicles being used at site have been checked for Executive Engineer,vehicle emissions and have a valid PUC certificate.

Noise from vehicles, All vehicle and construction equipment shall be fitted with exhaustplants and silencers. Damaged silencers to be promptly replaced by contractor. Site Contractor WR/CR- Site engineer andequipment Vehicles to be maintained and services regularly. Executive Engineer,Chocking of drains Construction material containing fine particles shall be stored in anand other water enclosure such that sediment-laden water does not drain into nearby Site Contractor WR/CR- Site engineer andbodies such as wells water courses.A documented procedure to be made by all Executive Engineer,and lakes/ponds contractors clearly prohibiting discharge/dumping of waste material

into any water body.In sections along water courses and close to cross drainagechannels, earth, stone or any other construction material shall be Site Contractor WR/CR- Site engineer and

Iproperly disposed so as not to block the flow of water. I_IExecutive Engineer,

** A follow-up mechanism for regular monitoring of mitigation measures to be followed as per EMP monitoring and reporting inSection 6 and the inspection sheet and formats in Annex 4, 5 and 6.

14

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

TABLE 3.2 Cont.

Environmental EHS Mitigation Measures To be taken ResponsibilityImpact Implementation Supervision

Ecological impacts All works shall be carried out in such a fashion that damage to flora issuch as tree cutting minimum Site Contractor WR/CR- Site engineer andand destruction of Executive Engineer,mangroves Plantation shall be done as per the Tree cufting permission from Tree

Officer WR/CR - Site Engineer with WR/CR- Site Engineer &contractor respeieExecutive Engineers

Soil erosion On road/track embankments, slopes shall be stabilized. The workshall consist of measures as per design, or as directed by the Site Contractor WR/CR- Site engineer andengineer to control soil erosion, sedimentation and water pollution, Executive Engineer,through use of berms, dikes, sediment basin, mulches, grasses andother devices

Debris disposal Debris generated due to dismantling of existing structures shall besuitably reused in proposed construction. Un-utilised debris shall be Site Contractor WR/CR- Site engineer andsuitably disposed either as fill material or at-pre-designated dump Executive Engineer,locations, approved by engineer. Care should be taken that thematerial does not block natural drainage or contaminate water bodies.

Slurry or similar debris generated from pile driving or otherconstruction activities shall be disposed such that it does not flow into Site Contractor WR/CR- Site engineer andsurface water bodies or form mud puddles In the area. Executive Engineer,

Soil contamination Oil and fuel spills from construction equipment shall be minimized byby construction good O&M practices. Soils contaminated by such spills shall be Site Contractor WR/CR- Site engineer andwastes, fuel etc. disposed as per MOEF requirements. Executive Engineer,Land degradation in Sand and stones shall be sourced from only and licensed quarries.quarry area. Documentation such as quarry release receipt Issued by the District ,ite Contractor WR/CR- Site engineer and

Revenue officer at the quarry site to be available at construction site. Executive Engineer,Health and hygiene Construction labour camps shall be located away from the nearestat construction habitation to avoid conflicts and stress over infrastructure facilities. Site Contractor WR1CR- Site engineer andlabour camps Executive Engineer,

** A follow-up mechanism for regular monitoring of mitigation measures to be followed as per EMP monitoring and reporting inSection 6 and the inspection sheet and formats In Annex 4, 5 and 6.

15

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

TABLE 3.2 Cont.

Environmental EHS Mitigation Measures To be taken Responsibility **Impact Implementation Supervision

Health and hygiene The contractor will provide, erect and maintain necessary (temporary)at construction living accommodation and ancillary facilities such as toilet blocks, Site Contractor WR/CR- Site engineer andlabour camps potable water supply etc. for labour as per the standards set by Executive Engineer,

various labour Act.These requirements are present in GeneralConditions (No. 59) of railways along with everyrelated tender.On completion of the works, all temporary structures shall be clearedaway along with all wastes. All excreta and other disposal pits should Site Contractor WRICR- Site engineer andbe filled in and effectively sealed. The site should be left clean and Executive Engineer,tidy to the satisfaction of the engineer.This is a requirement of the existing General TenderConditions (No. 40)

[_elays and The construction plan shall be discussed in advance with Centralcongestion on Railway Authorities to avoid delays in existing train schedules. Site Contractor WRICR- Site engineer andtracks Executive Engineer,Traffic Control and The contractor shall take all necessary measures for the safety ofSafety existing train traffic during construction and provide, erect and Site Contractor WR/CR- Site engineer and

maintain such barricades, including signs, markings, flags, lights and Executive Engineer,flagmen as may be required by the engineer for the information andprotection of traffic. All such measures should as per requirement ofWestern Railway. Special consideration shall be given in preparationof traffic control plan to the safety of pedestrians (at railwaycrossings) and workers at night.This is a requirement of tender conditions issued toall contractors.

Road Traffic delays The construction plan shall be discussed in advance with concerneddue to cable laying civic authorities to minimise traffic congestbn. Site Contractor WRICR- Site engineer andwork. Executive Engineer,

** A follow-up mechanism for regular monitoring of mitigation measures to, be followed as per EMP monitoring and reporting inSection 6 and the inspection sheet and formats in Annex 4, 5 and 6.

16

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

TABLE 3.2 Cont

Environmental EHS Mitigation Measures To be taken Responsibility **Impact Implementation Supervision

Traffic Control and The contractor shall take all necessary measures for the safety ofSafety existing road traffic during cable laying work and provide, erect and Site Contractor WR/CR- Site engineer and

maintain barricades, including signs, markings, lights as may be Executive Engineer,required by the engineer for the information and protection of traffic.Special consideration shall be given in preparation of traffic controlplan for safety of pedestrians, vehicles and workers at night.

Occupational The contractor is required to comply with all the precautionsHealth and Safety as required for the safety of workmen. Site Contractor WR/CR- Site engineer and

Safety requirements are specified in Tender Executive Engineer,conditions issued to all contractorsAdequate precautions shall be taken to prevent danger fromelectrical equipment. All machines/equipment used shall Site Contractor WR/CR- Site engineer andconfirm to the relevant Indian Standards (IS) codes and shall Executive Engineer,be regularly inspected by the engineer.A readily available first aid unit includirf an adequate supplyof sterilized dressing material and appliances shall be Site Contractor WR/CR- Site engineer andprovided as per the requirements under the Factory Act. Executive Engineer,This is a requirement of tender conditions issued toall contractors.All anti-malarial measures as prescribed by the engineer shallbe complied with, including filling up of burrow pits. Site Contractor WR/CR- Site engineer andProvision of medical facilities on site (with respect Executive Engineer,to worker strength) is a requirement of GeneralConditions of Contract (Condition No. 59).

** A follow-up mechanism for regular monitoring of mitigation measures to be followed as per EMP monitoring and reporting inSection 6 and the inspection sheet and formats in Annex 4, 5 and 6.

17

E:nvironmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

TABLE 3.3 EHS MITIGATION MEASURES (OPERATION STAGE)

Environmental EHS Mitigation Measures To be taken Responsibility **Impact Implementation Supervision

Hazardous Regular audits of material handling and disposal (storage,material handling disposal practice and records) as per inspection sheet. WR/CR site engineer, Stores WR/CR- Site engineer and

Personnel. Executive Engineer,

Handling of material related to batteries as per BatteryManagement and Handling Rules, 2001 under EnvironmentProtection Act, 1986

Loss of Trees Regular maintenance of track-side and other plantationshould be done. Monitoring to be done as per format in Site Engineer with Contractor WR/CR- Site engineer and

____ Annex 6. Executive Engineer,

** A follow-up mechanism for regular monitoring of mitigation measures to be followed as per EMP monitoring and reporting inSection 6 and the inspection sheet and formats in Annex 4, 5 and 6.

18

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

6.0 Environmental Monitoring and Reporting

Ste visits and interviews have revealed the following facts related to environmentalmanagement organisation:

* In the consolidated EA report for. MUTP, MRVC was reported to be the ProjectImplementation Agency (PIA). However, CR/WR is the PIA for this project. MRVC is thecoordinating agency to facilitate communication between MMRDA and CR\NR.

* Environmental monitoring is currently not required to be done by the contractors. Apartfrom periodic general inspections, currently there is no feedback mechanism for EHSelements of the project.

6.1 Environmental Monitoring Program

The main objectives of a monitoring program are:

• To evaluate the effectiveness of the mitigation measures during the construction andoperation phases.

* To satisfy the legal and community obligations• To respond to the unanticipated environmental issues at an early stage and to verify the

accuracy of environmental impact prediction.

Environmental impacts for the project are limited to those caused by handling and disposal ofwastes, particularly hazardous wastes such as Transformers and transformer oils and cablelaying work, cutting of trees, minor civil construction work etc.

The objectives of monitoring described above will best be achieved for this project bya comprehensive periodic site inspection program for EHS elements for the on-goingconstruction activities.. The significant environmental impacts of this project is related tohazardous waste handling and disposal and monitoring of ambient air quality, noise, wateretc. for the construction and operation stages of the project are not recommended for thisrailway project.

6.2 EMP Monitoring and ReportingAs described in Section 6.1 above, an effective inspection program will go a long way toassure implementation of various EHS mitigation measures for this project. The inspectionprogram needs to be dove-tailed into existing programs followed by CRNVR and theparameters for inspection, inspection schedules etc. need to be clearly defined. The existinginstitutional arrangement mentioned in Section 6.4 ahead is adequate.

19

Environmental AOdit of DC- AC Serene Environmental ServicesConversion Project of Railways

6.2.1 EMP Monitoring and Reportina durina Construction Phase

The project implementation work for Greater Mumbai is yet to take off. Currently there is noprocedure for site EHS inspections, which could be followed for on-going constructionactivities.

Based on the site observations, level of awareness of staff (as found during site assessment,interview of CR staff and during audit of BVQR/Santacruz-Borivali project), the followingprogram and procedure is suggested for effective monitoring of EHS implementation at theupcoming construction sites:

a. Monthly inspection program by CR/WR for all on-going and up-coming projectconstruction sites. The inspection will be carried out by the Engineer in-charge ofthe construction site, or his representative. The format for inspection will be as perAnnex 4. The inspection will be carried out during the entire period ofconstruction activity including before start of construction and immediately afterconstruction is complete.

The completed inspection checklist shall be submitted by the concemed engineerto the Chief Engineer (WR/CR). Corrective action plan with time frame forimplementation for any non-compliance to be also-submitted.

(Separate checklists need to be filled in for separate works such as sub-stationconstruction site, scrap yard, cable laying site etc. However, a group of similaractivitfes could be inspected using the same checklist.

b. All site contractors to maintain log books and other documentation specffied inAnnef 5.

c. A copy of the completed monthly inspection checklist should be sent by the ChiefEngineer (CR/WR) to MMRDA every month for review. The inspection checklist fora month along with the corrective acton plan, ff any, shall reach MMRDA no laterthan the 15th day of the next month (This will be applicable mainly for MUTPProjects with Worid Bank Aid Component)

d. MMRDA to carry out independent f'- party inspection of various construction sitesevery quarter during the construction activity and also after construction iscompleted to assess any residual environmental impact. A Project ManagementConsultant (PMC) could be appointed for this purpose by MMRDA. Reviewchecklist given in Annex 4 could be used for this purpose. (This will be applicablemainly for MUTP Projects with World Bank Aid Component)

20

Environmental Audit of DC- AC Serene Environmental SenvicesConversion Project of Railways

6.2.2 EMP Monitoring and Reportina during Operation Phase

There are no significant adverse environmental impacts during the operation phase of this railproject, except for. Thus operation phase monitoring for this project is required mainly for thefollowing:

* Health and survival rates of the compensatory and other plantation done by CRNWR.* Monitoring of Rehabilitation and Resettlement (R&R) sites for the people displaced due to

the project (If Any). This will be done as a separate exercise not covered in this auditreport.

The monitoring program and procedure suggested is as follows:a. CRIWR to carry out survey of plantation done as per the approved Plantation Plan.

Checklist given in Annex 6 could be used for this purpose. Survey to be done 6-monthlyfor 3 years and to be submitted to MMRDA for review by MMRDA and World Bank.

b. Regular inspections of stores and scrap yards to assess adequacy of safe handling ofhazardous waste material and other wastes.

21

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

6.3 INSTITUTIONAL SETUP

The construction activities of the project are being implemented by CR and WR. The existingorganisational structure of Westem Railways for DC-AC conversion activity is given below inFigure 1. This structure is for the construction phase. In the operation phase thecontractors and site-incharge function will not be present. Similar structure exists for CentralRailway

FIGURE 1.0 EXISTING ORGANISATION FRAMEWORK

MMRDA - Apex AgencyMRVC - Coordinating Agency

4FChief Engineer (WR)

4FChief Chief Electrical Chief Signal andAdministrative Engineer TelecommunicationOffice Engineer (Works)

CEE Chief Project Site In-charge(Construction) lMAnon=rBVQR Project

Site In-Charge Contractors

Site In-Charge

Contractors

Contractors l

In the consolidated EA report, it was envisaged that the monitoring and reporting process formitigation measures during construction should initiate from the contractor at the lowest rungwho will report to the Project Implementation Agency (PIA) through the Project ManagementConsultant (PMC).

EMP monitoring etc. during construction and operation stages can be taken up by the WR/CRstaff. PMC can be appointed by MMRDA for 3r party verification of EMP implementation.

22

Environmental AUdit of DC- AC Serene Environmental ServicesConversion Project of Railways

6.4 Institutional Strengthening

For carrying out regular inspection for the EHS elements, the CRNVR staff needs training forappreciation of various EHS elements. The training program proposed is given in Table 4below.

Table 4. Training Program for Institutional Strengthening

Module Topic and Contents Duration1 Environmental Awareness Class Room

Appreciation of Environment, Health and Safety Training of 1issues - Fundamentals of Air Pollution, Noise, dayWater Pollution, Solid and Hazardous Wastesgeneration and handling etc.

2 Environmental Impact Assessment Class RoomEIA fundamentals. Consequences of adverse Training of 1environmental impacts on various ecosystems. dayTypical environmental impacts of railway projects

3 Environmental Legislation Class RoomIndian Environmental Laws and their application to Training of 1/2Railway Projects. day

4 EHS Management System Class RoomComponents of EHS Management System in Training of 1Ageneral and as applicable to Railway projects. dayMethodology of environmental monitoring for airquality, noise etc. Site visit to any

one railwayEnvironmental management of hazardous wastes construction(including waste oils) including waste handling, site forstorage and disposal mechanisms. appreciation of

variousEnvironmental monitoring and inspection programs environmentalas suggested in'this report should be discussed. components.

(1/2 day)Review of - existing tender conditions and itsmodification to include EHS elements for better EHSmanagement.

The training should be provided at a minimum to the following personnel:* Deputy Chief Engineers (Construction)* Central Railway Site In-charge of various construction sites* Contractor Site In-charge of various construction sites.

1 training program of 4 days as given above should be conducted every quarter to cover allconcerned WR/CR staff. The training program can also be integrated into the WR induction-training program.

Visits to country's having similar railway projects and with established and demonstrated EHSManagement System, including demonstrated measures for noise attenuation could be visitedby concerned officials of CRNVR. This will help tremendously in increasing awareness withWR and improve technical skills for EHS management.

23

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

6.5 Estimated Cost of EMP ImplementaffonAs seen in the Tables 3.1 to 3.3, several EHS elements are already included in the currentconstruction operation. Costs for these measures are already included in the project cost.These components include provision of safety barriers and other safety measures, utilityrelocation, dust suppression by road watering, 2m boundary walls along tracks, compensatoryplantation of trees etc. Costs for additional EMPs not induded in the project costs are givenbelow in Table 5.

Table 5 Cost of EMP Implementation

Component Unit cost (Rs) Units Total Cost (Rs)

EnvironmentalMonitoring(Operation Phase)Tree survival rates. 15000 per survey 1 survey every 6 months 90000

for 3 years = 6 surveys

Training Program 40000 per program 4 programs per year 160000of 4 days each.

Visit abroad to 200000 per person 5 persons 1000000*Railway Project site -with demonstratedMeasures forEnvironmentalProtection - andestablished EHSManagement Systemincluding noiseattenuation.Total Cost 1250000

* Cost of visits to similar international project sites have already been included as a part ofBVQR and kurla Thane project, Thus the actual cost of EMP implementation for DC-ACconversion project will be Rs. 250000.

24

Environmental Audit of DC - AC Serene Environmental ServicesConversion Projects

ANNEX-1A

TERMS OF REFERENCE

MUMBAI URBAN TRANSPORT PROJECT

TERMS OF REFERENCE FOR CARRYING OUT ENVORONMENTALASSESSMENT/ AUDITING OF RAILWAY PROJECTS

1 ASSIGNMENT:

The purpose of this assignment is to assist Mumbai Metropolitan RegionDevelopiment Authiority (MMRDA) in carrying out an environmilenital audit ofvarious ongoing railways projects to determine how environmental issues, if any,can be addressed at this stage of prolect implementation.

2 BACKGROUND:

2.1 MMRDA had appointed Montgomiiery-Watson Consultants (India) Pvt Ltd toundertake thie preparation of the Environrimental Assessment (EA) for the MUTP.This EA process resulted in the preparation of Sectoral-Level EnvironmentalAssessment (SLEA), Programmatic Level Environmental Assessment (PLEA)and Micro-Level Environmental Assessment (MLEA) Thie SLEA was a strategicdocument, the PLEAs were prepared for small generic sub-projects like flyovers.RO(Bs and RUBs while MLEAs were prepared for larger sub-projects like roadwidening and extensions. This study was undertaken between 1996 and 1998and oestilted in several outputs including a synthesized final Iepolt

2 2 Consequently, almost all of these railway projects except DC to AC conversionhave been started and are in varying stages of implementation As theco'lstiuction work of the project is already underway, consultarits should assessthe current anid residual requirenments of environmilental management practiceEnvironimental studies, which have been carried out for railway projects, are asuIniide r

a) Report of MLEA of Borivali-Virar Quadrupling prepared by Montgomery-Watson Consultants (India) Pvt Ltd in 1998.

b) Report of Initial Environmental Examination for Thane- Kurla 5th and 6th linesprepared by MMRDA in 2000-01.

The Consultant should use these reports as the' basis'to' carry out tlie proposedenvironmental audit.

2.3 Sonme of the projects may also involve construction in areas, whichi are classifiedas restncted areas under Coastal Regulation Zone (CRZ) Rules Hence,peiiiissioni needs to be obtained- under CRZ Rules from the Ministry ofEniw'ronmnent and Forests, Goverr1rnent of In1dia for suchI projects

3 SCOPE OF WORK:

The Consultant should closely work with the staff of MMRDA and Mumbai0RailVikas Corporation (MRVC) in the conduct of this assignimet. The specific tasksfor the four Railway projects are outlined below:

3.1 To perforni environimenmt audit for Borivali - Virar Quadruplinig ofrailway liic (26.0 kin)

3 I 1 Micro Level E,ivironlieiital Assessment (MLEA) has been carriecl out for B3nrivnli-Virar Quadrupllllng of Railway linie as part of Ilte Environmental Assessimetit ofMUTP. The project hias now been commeniced and land acquisition completedfor 4 ha out of 38 ha of the land required to be acquired The earthwork of upto45/o hlas already been comilpleled The work on two imiajor b idges onl Vasnlcieek has staited and work on 3 otlher major bridges is also in piO(iJCSS liheminlor bridges lhave beenl comiipleted. Plhysical progress to the tuLle of 16% hlasbeen achieved in respect of the potect.

3 1 2 1 ie aim) of the audit will be to.

- verify the imiplemiientation of EMP delineated in the MLEA Thie mitigationmeasures for milliniizing the adverse impacts due to tree felling, waterpollution, erosion arid dust generation, flora and fauna, conistrticion in drainsand waterways, alterinatiori in drainage pattern, and provision of adequatecross-drainage stILuctures, etc need to be documnlted(

- recomimiienld the watys for retiofitting tihe miitigatici nieasuies into onlgoingcolstrLIctIoll activities so tilat the EMP could be miade operational durinlgCOnStruCtilo actIVities

- assess whiether anly (urthier environmental mTitigatioll mieasuLies are required.based on comipleted arid planned works, if any

- siggest imoptrovenimeits in IIle imi1plemeinitation of Lnvitonneontal Maanagelenitplan in future activities, if requlred.

: 1.3 Detailed scope of work will be as follows:

Task I : Previous outputs and studies

The! consultant should familiarize himself with the following studies

- MLEA repor-t of Bonivali-Virar Quadrupling project prepared by MontinotneryvVatsonl Goinsultanits, Mumbai;

- Final report on Environmiienital Assessmcnit for the MUTP project prepared byMoI)tgoml' y Watson Consultants, Muinbai,

- Project Design Report prepared by MRVC;

- Engiineerinig Designi Report and Techno-econioiniic Feasibility Report

Assessnienit has not been carried out for this project as under the screening ofMIJTP carried out by Montgomilery Watson, it was placed in tlhe category ofsutjbpoject witlh possibly negligible iiiipacts on the environment

T1he puI pose of the Audit will be to

- assess the status of enviroririieital imlpacts durinig ongoing cotnstructioll .and(opelation

assess whether any environmzental mitigation mleasures are re(lqtired basedon the on- going and completed works

- Outline environmienital mitigation measures for planned works, if required

- docLireIlt lessons thlat can bc useful for future projects

- Suggest mitigatioll measures for environmilental inmpacts on the marille watelduallty, water flow due to construction of bridges, and otlier possible impactsas identified in the MLEA reponl of Borivali-Virar Quadrupling projectprepared by Montgomery Watson Consultants, Mumbar

The dietailecl scope of work will be as follows

T-.sk 1. Previotis outptit anld sttI(lies

'I i e cCIIsulltait sIhouldl familiarize himiself with

- MlEEA report of Borivaii-Virar Quadrupling project prepared by MontgomeryWatson Consultants, Munmbal

- Final repoit on Environimlental Assessrmerot for the MUTP project prepared byMonlgomirely Watson1 Consullants, Mumbar

- Project Design/Engineering and Techno-econonnic Feasibility Reportsprepared by MRVC

Task 2: Assessment of Impacts

Consultant should ulidertake site visits to Constructioni and Operationsites to check whether any significant impacts on the air, noise andecological environrmrent. have occurred, if any due to the alreadycoimpieted works

Cons-Iltant should identify significant environmental imipacts dLie to oni-cgoirnl and proposed activities, if any

C onsultant should develop a matrix of possible environmiiiental gilmpacts

and ssues for assessmient of the cumulative imnpacts due to ongoigngconstictioti and operation activities

Task 2: Review Environimiental Monitoring Data

Consultant must visit the project site and observe any significant changes,if any since 1998 in environmental data to capture possible changes inthe ground and corroborate the changes from available secondary datawitli possible imnplications on environmental management plans

Task 3 : EMP Implementation

Consultant should undertake site visits to Construction sites to checkstatus of implementation of environmental mitigation measures, asproposed in the Environmental Management Plan of MLEA report for thealleady coimpleted and planned works

Consultant sh,ould outline in a tabulated format the EMP proposed and itsstatus of implemnentation

Consultants should suggest imnprovements in the implementation ofEnvironmental Management Plan for completed and planned activities, ifany based on the signrificant changes observed in the environmentalbaseline data

The EMPs and their implementation plans stiould be prepared inconsultationi and a9)rement with the MRVC and other concerneda-gciiciCs

Task 4: CRZ Regulation

The consultant should assist the MRVC in preparation of Application Format&inder- CRZ Rules based on the available secondary information fronm MLEAand Project Designi report and other background studies Consultant shiouldassist MRVC in obtaining CRZ clearance from Ministry of Environmrilent andForests, Governmnent of India for the proposed project

Task 5: Environimental Audit Report

- Prepare Environmental Audit report based on the above tasks, incorporatingupdated Environmiiental Management Plan. in case any significant imnpactsfor various environmental parameters are cbserved.

3.2 To l)crforim] Enviroiw .ental Aud t for laying of Santacruz and Borivali5thi line (17.80 Kn)

3 2 1 Thie piojoct at Santaciuz-Bori;alr 5th line has achlieved 90% overall progress anda 4 92 Km] long section between Santacruz-Andlieri has been already opened torail passenger traffic Land acquisition tas been completed Other civilengiiiemiing works hai e a oost been comipleted, except one malor bridge andlinkinig of 2Kiii of tiarl r . ain ifiO and 5 60 Kml of loop line Enviionmnental

Lsuggest environnrllCntal niill(gatori mieastires for planned wolrks. if any asdelineated in the IF:S rel)oit as well as based on the MLEA repout of lloivalirVi01.11 Ol I.j illrri f)iOJt Ct lp)al)are(d t)y MorltJorflQely W;1Vt'rr Cmi .u1rt1ii t.MuM 1bar

TIlire detailedl scope of work will h)e as follows

Task I: Previous output arid studies

T'lie consultant should famiiliarize hIimiself witlh

- Initial Environimiental Assessmenit Report prepared bv MMRDA inid MRVC

- MLEA Irpolt of Bonvali-Viiar QuadcrupIling project prepared by MontgoiHcryWatson Consultants, MLrr1I)a

- Final report on Envirorliilerntal Assessmicnit for the MU IT) project prepar re(d hyMontgoiner-y Watson Consultants, Mumiibar

- Project Design/Engineerinlg ancl Tecthno-economiiic Feasibil,ty Repoitsprepared by MRVC

Task 2: Assessmiicnt of Impacts

Consultanit shioulcd undertake site visits to Constructiorn and Operationsites to chieck whethier any significant impacts on the air, noise andecological enviionimiierit. [lave occurred, if any due to the alrealdycomupleted wo'aks

Consultalrt sIhould identify significant environmental inipncts duL to on-going aid pirl)osed activities, if any

CConsultanit sh.ould develop a miatrix of possible environimilerital impactsand ISSueS for assessmienit the cunIL.lative impacts dLue to or'goingconstr-uctioni and operation activities

Task 3: Environimllenital Mitigation Measures

Consultanit should undertake visits to Construction and Operation sites toidentify if any environimienital mitigation measures are required based oncomipletecd arci planned works and delineate environmiilenital mnanaernlentplan for this purpose An EMP matrix giving the erivironmenV alimpacts/issuLes. tihe milt;gation measures, the implenventation a'id

supeivisiun aiLtho0ity for the EMP (.vhilch ma'y be two different ac3elicles),ancl the cost imll)licationls for each miltigation nreasure slroul.; be prCvicYCd

Il1e EMl's and tileir implemientation plans shIould be porepared in(:o istRlt;atinii Miid aciWrHonfit w:ith tthe MPVC arid ntdier Wiwi - 'i,,(-)(j (I icilo';

Task 3: Environmental Mitigation Measures

Consultant shiould undertake visits to Construction and Operationi sites toidcentify if any environmental mlitigationi measures are required based onicomipleted and planned works and delineate environmental mianagemilentplan for this purpose An EMP mzatrix giving the enviroritnenitalini pactsfissues, tile iiitigation m1easures t(e implementation andsupervision authiority for thie EMP (which may be two different agencies),and the cost iiiplications for each mitigation measure should be provided

The EMPs and their implementation plans should be prepared inconsultation and agreement with the MRVC and other concernedagencies

Task 4: Envirornmiiental Audit Report

Prepare Environmiiental Audit report for the present exercise based on theabove tasks.

I o periorim Enivironmiienital audit for laying of 5t1i andf 6ti line betweenThianie and Kurla (17.0 kin

3 3 1 The pioject at Kurla-Thanie 5th1 and 6thi lines has achbeved 52 % progress. Landacquisition for 30% of land has been completed Earth works, and works onminor and major bridges are in progress The detailed EnvironmentalAssessmienit was not prepared as under the screening of MUI P carried out byMontgomiiery Watson, it was identified to have nealggible impacts on theenvironmiiienit However, MMRDA and MRVC carried out Initial EnvironimiierntalScreeninig (IES) of this project in 2000

3 3 2 The purpose of the Audit will be to

- verify the implemiientation of EMP delineated in the IES report as well asbased on the MLEA report of Borivali-Virar Quadrupling project prepared byMontgomery Watson Consultants, Mumbai

- assess the status of environmental imnpacts during ongoing construction andoperation

- assess wlhetlher any envirorinmierntal mitigation measures are requirecd basedon1 tie ongoinig and completed works, if any

- doculieit lessons thiat can be useful for fu-ure projects

- mitigate environmiiental im1pacts on the marine %..ater qLuiality. w:ater flow dueto construction of bridges

Task 2 : Asscssrinenit of lriipacts

- Consultant should uLideiltake visits to the proposed sub-station sites to chieckwhietlher any significanit impacts during constructioni and opeiation especiallyon ecological environimient, would occur, if any due to the proposed activitiesSomqe of the impacts likely to occur relate to construction works. accessroads, i1il)act on suLroundiling flora and fauna, and imiipact on tile coastalecology (CRZ violation)

- Consultanit should identify impacts during construction dLue to laylng ofundeiground cables for replacement of L T. overlhead lines

- Consultants should identify whether the DC transformers to be replacedcoitain l'oly Clhlomiriated Bi-phllenryls (PCI3s) arnd Iriql iligit IIhie niripncts ofdisposal of old DC tiansfoiniers,

- Consultants shIould review the Project Design Report and EnviolninllintalAssessiiieiit [Report prepared by M/s Rl-IES and identify impacts oni air,noise and ecological enivironimenit due to various othier activities of thleproject.

Task 3: Environilmenital Mitigation Measures

- Consultant should idenitify nileasLires Cduring constructio-L arrid oprratioll. ifaiiy reqlted to mii tigate enivironimiierntal iimipacts ard delinc?at(ee ri vironinci ibi'mianiagemlent plan for this purpose

- Consultalnt sihould identify mitigation mieasures for minimizilig tlle imlipacts ofold DC transforrimers and delineate EMP incorporating thie mieasures for safedisposal of old tianisforimers, and prepare a PCB nianagemient plan in casePCBs are likely to be found in old transforimiers

- The EMIVs arid their inipen0emitation plans stiould be prepr.ed iii cori'ultatioi Iand agreemilent withi the MRVC and other concerned agenc es

Task 4: Environmenltal Assessment Report

- Prepare an Environmental Assessment report based on the above tasks.

DOCUMENTS:

lie consUltants should review the following documents

I Final report on Eniviroiinietital Assessmlenit for thie MUTP project prepared hb"

Moiitgoriiciy Watso n Conisultarits. Munrbai

ii Project Design Report for Borivali-Virar Quadrupling. Santacruz-Borivali 5t.-lilne Kurla-Tlharie 5tl arid 6ti lines and DC to AC cotversion )project.piepaiccl by MRVC

Task 4: Environiotrental Assessiient Report

Prepare Environmental Audit report for the present exercise based on tileabove tasks

3 4 To perform Environimenital Assessmnctit of DC to AC Traction ConversionProject (1500 V DC to 25000 V AC)

3 4 1 The MRVC has proposed to undertake the conversion of DC to AC Traction sothat the sub-urban trains in Murnbai would be converted to traction of 25000 VAC froin the present 1500 V DC The pr6ject would involve the provision of 18DC sub-stations (5 substations on Western Railway and 13 sub-stations onCcintal Railway) in place of existinrg 69 DC subsInrdrs II rldraile.

Cinviioni ue iital Asscssmcnt was rot c1(led otit as iiid(los 1e1 Sd Ih isr, '( o Mt I1 Pcarried OLlt by Montgomiiery Watson, it was identified to hiave least impacts on tlheenvironimienit M/s RITES as a part of feasibility study have identified variousenviionmental benefits of the project The project will hiave 10 to 15 'Y,/ lowerconsumptioni of energy-and lesser use of insulation materials such as copper andAluminuni which would have least impact on environment as comipared to DCtraction/ disposal of old DC transformers

3 4 2 The objectives of the enviroimential assessmient will be to

-assess wlietlier any activity of the project will have impacts on tileenivironimient such as construction of sub-stations withinl coastal regulationzone

propose piopei disposal ineasures for the old DC tiansfoinrers

sLiggest envirornilental mianiagemilent plans if requirecd for nitigatingeiivironinicnital iniipact

3 4 3 The detailed scope of work will be as follows

Task I: Previous output and studies

The consultant should familiarize himself with the

- Components of the Project

- Final i eport onl Environmental Assessment for th e MUl P pro!eel p a e ;d hyMoinlgomlery Watson Consultanits, Munmbai

- Project Design Reports prepared by M/s RITES and MRVC

iii. MLEA report of Borivali-Virar Quadrupling project prepared by MontgomeryWatson Consultants, Mumbai.

iv. Initial Environmienital Report prepared by MMRDA anid MRVC

v. Environiiiicntal Statlus Repoits prepared by MCGB3 for tlhe yeais 199(3-2001

vi. Guidelines available (from the World Bank and elsewhere) on environmentalissues related to electrical substation / transformers.

5 REPORTING REQUIREMENTS

The Consultant will report to MMRDA and the following is the output schedule foreach of the four projects. The draft reports submitted by the Consultant will bereviewed and monitored by a Technical Working Group (TWG) constituted byMMRDA comprising of the representatives of MMRDA, MRVC, MCGM, andNGO

i. Inception Report 1st weekii Interimi Report I 4th weekiii Draft final Report 7th weekiv Final Report 8th week

6 DURATION:

-he study should be completed within a period of 8 weeks. The total Consullant inputsfor the above assignment is expected to be 6 person weeks.

7 CCYNSULTANT'S QUALIFICATIONS:

The Consultant for the assignment shall have acquired a post graduate degree inEnvironimental Engineering with at least 7 to 10 years experience in preparingEnvironmental Assessment reports, conducting Environmental Audits and good workingknowledge of environmental management in related projects.

Environmental Audit of DC - AC Serene Environmental ServicesConversion Projects

ANNEX-1B

LEGAL REQUIREMENTS

LEGAL AND POLICY FRAMEWORK

1. The project will be implemented within the Indian legal framework and will also comply withthe safeguard policies of the World Bank. The applicable legal and policy framework isdescribed below.

Applicable Indian Legal Requirements2. The applicable Indian legal provisions are described in two groups one related to

environment and the other related to resettlement.

Legislation related to Environment

3. There are various Acts, Rules and Notifications applicable for different environmentalcomponents such as Air Pollution, Water Pollution, Noise Pollution, Coastal Areas,Hazardous Materials Handling and Transport, Forest and Wildlife. In addition, regulatoryprovisions by way of environmental clearance also exist. The applicable acts andregulations are listed below.

Environmental (Protection) Act, 19864. This is an umbrella act for environmental protection. Various rules and notifications are

issued from time to time under the provisions of this Act. Environmental Protection Rules(2000) specify standards for ambient air quality whereas Noise Pollution (Requlation andControl) Rules, 2000 provide for the ambient noise standards in public places Howeverlegal mechanism to achieve these are not explicit in terms of emission at source intransport sector except for the vehicle emission norms like Euro II or Bharat II that havebeen prescribed. The Environmental ImpactAssessment Notification. 1994 (asamended inMay 1997) make environmental clearance mandatory for 29 categories of developmentalprojects listed in Schedule 1 of the notification. Railways are not listed in schedule 1 andhence do not need environmental clearance. For other components under MUTP, MoEFhas confirmed that environmental clearance EIA notification is not required.

Coastal ReQulation Zone Notification, 19915. The notification provides for determining certain areas between the Low Tide Line

(LTL) and High Tide Line (HTL) and adjacent land ward area as the CoastalRegulation Zone and its classification into CRZ I -ecologically sensitive and coastalwetland between HTL and LTL, CRZ II - where development has already occurredand CRZ IlIl - the residual area largely rural in character. The notification alsoprescribes prohibited activities in CRZ and activities that can be taken up with theapproval of MoEF. Reclamation being a prohibited activity cannot be undertaken inCRZ

The Maharashtra (Urban Areas) Preservation of Trees Act. 19756 GOM legislation requires every local authority to constitute a Tree Authority. No tree can be

felled withoutthe permission of this authority. The Road development agencieswill havetoobtain the permission of the Tree Authority for felling of trees in the right of way and followthe Tree Authorities stipulations in respect of transplanting or compensatory plantation.

Legislation related to R & R.

Land Acquisition Act 1894 (LA Act):7. This act provides for compulsory acquisition of land for public purposes by paying

compensation at the market rate with 30% solatium for the compulsory nature of acquisitonand interest at 12 percent per annum from the date of notification of land for acquisition.

Maharashtra Regional and Town Planninq Act. 1966 (MR&TP Act):8. The act provides for preparation of Regional Plan for the MMR as a whole and preparation

of Development Plans (Master Plans) for the local jurisdiction of individual municipalauthority like MCGM. The Regional Plan of MMR has been sanctioned in 1999 whereas theDevelopment Plan of Greater Mumbai was sanctioned in 1991. The Regional Plan is policyoriented and strategic in nature whereas Development Plan is more specific and prescribesdetailed land use zoning including designation of land required for public purposes, which.can then be acquired in conjunction with the provisions of Land Acquisition Act. The actalso provides a statutory framework for formulation and enforcement of DevelopmentControl Regulations. The sub-projects are required to be consistent with the Regional Planand the Development Plan.

Development Control Regulations for Greater Munibai 1991 (DCRs):9. The DCRs set out the standards for building design and construction, provision of services

like water supply, sewerage, site drainage, access roads, elevators, fire fighting etc. Aseparate stt of regulations is included for the redevelopment or resettlefnent of slums,which are administered by the Slum Rehabilitation Authority (SRA). Buildings procured forR & R have to conform to these DCRs. Up-front clearance of the entire project is howevernot required under the DCR. Approvals are to be obtained for individual scheme, as it getsprepared.

10. These regulations prepared under the MR & TP Act offer an alternative to acquisition underLA Act by way of Transfer of Development Rights (TDR). The permissible Floor SpaceIndex (FSI) defines the development rights of every parcel of land in Mumbai. If a particularparcel of land is designated for a public purpose the landowner has an option of acceptingmonetary compensation under the LA Act 1894 or accept TDR (equivalent to the plot areatimes the permissible FSI), which can be sold in the market for use elsewhere in Mumbai.The DC Regulations have been amended to provide incentives for rehabilitation (includingresettlement of slum dwellers) in 1997. For landowners prepared to provide 225 sq.ft.dwelling units free of cost to slum dwellers, the incentive is in the form of right to build andsell floor space equivalent to that required for slum rehabilitation subject to the maximumin-situ utilization of FSI of 2.5. The remainder of the total development rights can be usedas TDR. In case of land designated for resettlement of slum dwellers affected byinfrastructure projects, the land owner has an option of offering dwelling units to the projectimplementing agency free of cost and getting the benefit of maximum of TDR equivalenttofloor area calculated at FSI of 3.5 (1 for land and 2.5 for the built-up area)

The Maharashtra Co-operative Societies Act 1960:11. This act provides for establishing, registering and administering the co-operative societies.

Housing co-operative is a special form of co-operative society, where the land and building

is owned by the co-operative and its members have occupancy rights of apartmentoccupied by them. Sale and purchase of such units can take place only with the consent ofthe society. This is a common form of tenure in Mumbai's apartment buildings and is widelyunderstood.

Applicable World Bank Policies12. Given that MUTP has been developed with the intention of mobilizing financial resources

from the World Bank, project preparation has included a number of studies andassessments which have sought to address and meet the requirements of the WorldBank's environmental and social policies, often referred as the 'safeguard' policies. Thenext paragraphs provide a summary overview of how these guidelines have beenconsidered.

Environmental Assessment (OP 4.01)13. In the context of the Bank's Operational Policy (OP) 4.01 on Environmental Assessment,

MUTP has been classified as category "A" project, largely on the basis of the large numberof people requiring resettlement and rehabilitation. Because of the large-scale resettlementand the triggering of more than one safeguard policy the project is also classified as "S1 " interms of safeguard issues. A consolidated EA including SEA has been prepared thatprovides the framework for preparing sub-project specific EA and EMPs in compliance withthe World Bank policy.

Cultural Propertv (OP 4.11):14. The United Nations term "cultural property" includes sites having archeological

(prehistoric), paleontological, historical, religious, and unique natural values. Culturalproperty, therefore, encompasses both remains left by previous human inhabitants (forexample, middens, shrines, and battlegrounds) and unique natural environmental featuressuch as canyons and waterfalls. The World Bank's general policy regarding culturalproperties is to assist in their preservation, and to seek to avoid their elimination.

15. Mumbai with its history of nearly three hundred years is rich in cultural propertyparticularly in the form of built heritage. GOM and MCGM are acutely aware of the need toconserve such heritage. GOM in 1995 with the involvement of NGOs listed over 600buildings and precincts as of heritage significance. DCR 67 governs the development ofthese listed buildings and precincts. GOM has also constituted a Heritage ConservationCommittee in 1995 to advise the Municipal Commissioner regarding developmentpermission to be granted in case of listed buildings and precincts. No developmentpermission can be granted of the listed buildings or within the precincts without the consentof the Heritage Committee.

16. During the execution of works, if a 'chance find a of archaeological significance occurs, thecontract requires the contractor to immediately inform the employer and stop further work.Employer will in turn inform the state Archaeology Department for further investigation.

17. The only cultural properties that are directly affected by the sub projects are smallplaces of worship established by the community of squatters within the right ofway. These have been created by the affected communities for their own use.Such places of worship do not possess any histoncal or architectural significancee,nd may not therefore strictly qualify to be treated as cultural property.Nevertheless they are treated as an integral part of preparation of RIPs Theplaces of worship and other community assets are identified dunng the BSES.Their rehabilitation is being implemented as a part of the R & R process inconsultation with the community. The impact on these properties and the manner.inwhich such impacts can be identified can be classified in three categones. Firstly the

buildings that are only partially affected can be helped to add equivalent area elsewhereadjacent to the building. Secondly structures that are fully affected by the right of way butare patronized by the community that is not affected by the project could be rebuilt outsidethe right of way in consultation wth the community and with assistance of the NGO. Insome cases the entrance to the structure could be reoriented to ensure safety of thedevotees visiting the place. Thirdly the affected structuresthat patronized by the communitybeing resettled could be relocated in consultation with the community. In addition, thecommunity may agree to forego some places without insisting upon their resettlement.

Natural Habitat (OP 4.04):

18. Natural habitats are defined as land and water areas where (i) the ecosystems' biologicalcommunities are formed largely by native plant and animal species, and (ii) human activityhas not essentially modified the area's primary ecological functions. All natural habitatshave important biological, social, economic, and existence value. Important natural habitatsmay occur in tropical humid, dry, and cloud forests; temperate and boreal forests;Mediterranean-type shrub lands; natural arid and semi-arid lands; mangrove swamps,coastal marshes, and other wetlands; estuaries; sea grass beds; coral reefs; freshwaterlakes and rivers; alpine and sub alpine environments, including herb fields, grasslands, andparamos; and tropical and temperate grasslands. Critical natural habitats include existingprotected areas and areas officially proposed by governments as protected areas (e.g,reserves that meet the cnteria of the World Conservation Union [IUCN] classifications i.e.Strict Nature Reserve/Wilderness Area: protected area managed for science or wildernessprotection; Il-National Park: protected area managed mainly for ecosystem protection andrecr.eation; Ill-Natural Monument: protected area managed mainly for conservation ofspecific natural features; IV-Habitat/Species Management Area: protected area managedmainly for conservation through management intervention; V-ProtectedLandscape/Seascape: protected area managed mainly for landscape/seascapeconservation and recreation; and VI-Managed Resource Protected Area: protected areamanaged mainly for the sustainable use of natural ecosystems. The conservation of naturalhabitats, like other measures that protect and enhance the environment, is essential forlong-term sustainable development. The Bank therefore supports the protection,maintenance, and rehabilitation of natural habitats and their functions in its economic andsector work, project financing, and policy dialogue. The Bank supports, and expectsborrowers to apply, a precautionary approach to natural resource management to ensureopportunities for environmentally sustainable development.

19. From this perspective one of Mumbai's notable natural habitat is limited to the 103 sq.km.National Park at Borivali, which is located in the northern part of the peninsula between thetwo rail corridors. The National Park is protected under the Indian Forest Act. None of thesub-projects passes through the National Park. The other important Natural Habitat is thecoastal wetlands in the eastern and western suburbs and along the Vasai creek. These areprotected by the Coastal Regulation Zone (CRZ) Notification of 19 February 1991.

Involuntary Resettlement (OD 4 30)

20. The Operational Directive 4.30 describes Bank policy and procedures oninvoluntary resettlement, as well as the conditions that borrowers are expected tomeet in operations involving involuntary resettlement. Planning and financingresettlement of projects are an integral part of preparation for projects that causeinvoluntary displacement MUTP will require resettlement of about 19000households (68000 persons). The World Bank Policy on Involuntary Resettlement

is therefore applicable to the project. In compliance with to this policy an R & RPolicy has been prepared and adopted by GOM for MUTP. RAP providing theoverall framework of policy, entitlements, consultative processes, grievanceredressal mechanism, component costs and monitoring and evaluation mechanismhas already been prepared. Sub-project specific RIPs are being prepared.

Indigenous People (OD 4.20)

21 This operational directive describes Bank policies and processing procedures for projectsthat affect indigenous peoples. It sets out basic definitons, policy objectives, and guidelinesfor the design and implementation of project provisions or components for indigenouspeoples. The terms "indigenous peoples," "indigenous ethnic minorities," "tibal groups,"and "scheduled tribes" describe social groups with a social and cultural identty distnctfromthe dominant society that makes them vulnerable to being disadvantaged in thedevelopment process. For the purposes of this directive, "indigenous peoples" is the termthat will be used to refer to these groups. Indigenous peoples can be identified in particulargeographical areas by the presence in varying degrees of the following characteristics: (a)a close attachment to ancestral territories and to the natural resources in these areas; (b)self-identification and identification by others as members of a distinct cultural group; (c) anindigenous language, often different from the national language;(d) presence of customarysocial and political institutions; and (e) primarily subsistence-oriented production.

22. About 1% of the PAHs of-MU-TP belong to the Scheduled Tnbes. A field-based reviewwasundertaken to determine if these PAHs were subject to application of this Policy since theymight have originally belonged to tribal communities in the distant past. As of now they areintegrated with the city life and do not have their traditional habitat or follow tradibonal waysof life. More particularly, (a) they no longer have close attachment to ancestral territories;(b) they do not identify themselves or are identified by others as distinct cultural group; (c)they do not speak an indigenous language; and (d) they no longer belong to customarysocial and politcal institutions. There is also a general reluctance to reveal the caste ortnbe particularly pronounced when data is to be kept in public domain. Itwasdeterminedbythe review thatthe soctal impact of the project on such people is therefore similar to that onother PAHs and thus the policy does not apply. No separate Indigenous PeoplesDevelopment Plan (IPDP) has therefore been prepared.

Other Safeguard Policies

23. World Bank has other safeguard policies dealing with Pest Management, Forestry, Safetyof Dams and Projects in International Waterways or in Disputed Areas. These are howevernot applicable to MUTP.

Envirnmental Audit of DC - AC Serene Environmental ServicesConversion Projects

ANNEX-2

SITE PHOTOGRAPHS

:nvirmnmental Audit of DC - AC Serene Environmental Services,onversion Projects

1. View Of The Insulators That Needs To Be Replaced

, S *~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~I

2. Area Near Borivali Station Been Identified For Setting Up One Of The NewAC Sub-Stations.

Environmental Audit of DC - AC Serene Environmental ServicesConversion Projects

,ow 4~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

W'

3. The DC Sub-Station At Bhayandar

4. Scrap Yard at Bhayandar- Waste insulators..

Environmental Audit of DC - AC Serene Environmental ServicesConversion Projects

ANNEX - 2.1

DETAILS OF PUBLIC CONSULTATIONS

SUMMARY OF PUBLIC CONSULTATIONS

DATE VENUE TARGET AUDIENCE - MEANS OF RECORDSCOMMUNICATION MAINTAINED

During CTS _1993 Conference Representatives of the Letters of Invitations List of

Room, government along with Executive participants,MMRDA departments, local Summary of draft CTS Minutes of the

authonties, project report. Meetingimplementationagencies, consultants inthe transport.

DuringSectoral EAJune 2, 1997 Yashwantrao Representatives of the Letters of Invitations List of

Chavan government along with Executive participants,Centre departments, local Summary of EA report Minutes of the

authorities, project were sent to individuals. Meetingimplementation Telephonic Confirmationsagencies, academia and about individualsthe consultants in the participationtransport andenvironment field.

During R&R ___1996 to 2002 All Sub-Project Project Affected Personal visits, List of

Sites, Households, Local discussions, Meetings in participants,MMRDA Leaders, etc. MMRDA Photographs,

. etc.DuringUpdated EANovember 20, Conference Environmental experts, Letters of Invitations List of2000 Room, Consultants, Academia, along with Executive participants,

MMRDA representatives of Summary of EA report Minutes of thegovemment were sent to individuals. Meetingdepartments, NGOs Telephonic Confirmationsand of project about individualsimplementing agencies participationand the World Bank

December 13, Office of Project Affected Public Notices to leading Public Notices,2000 Divisional Households (PAHs), English and Marathi List of

Engineer, NGOs newspapers, Draft participants,Mankhurd Updated EA report, Minutes of the

Executive Summary made Meeting,available at Public Photographs,Information Centres (PIC), Pamphlets,Pamphlets, Non technical Updated EASummary of EA report in reports,English and Marathi were Executivedistributed to PAHs Summary, Nonthrough NGOs well in Technicaladvance. Summary at PIC

DATE VENUE TARGET AUDIENCE MEANS OF RECORDSCOMMUNICATION MAINTAINED

December 14, Yashwantrao The Cross section of Public Notices to leading List of2000 Chavan Society, NGOs, English and Marathi participants,

Centre Journalists newspapers, Draft Minutes of theUpdated EA report, Meeting,Executive Summary made Photographs,available at Public Pamphlets,Information Centres (PIC), Updated EAPamphlets, Non technical reports,Summary of EA report in ExecutiveEnglish and Marathi were Summary, Nondistributed to participants Technical

Summary at PICDuringConsolidatedEANovember 23, Mumbai Cross section of Public Notices in English, List of2001 Marathi Society, NGOs, Marathi and Hindi to participants,

Patrakar Representatives of the leading English and Minutes of theSangh, CST government Marathi newspapers, Meeting,Mumbai departments, local Draft Consolidated EA Photographs,

authorities, project report, Executive Pamphlets,implementation Summary in English and Consolidatedagencies, World Bank Marathi made available at EA reports,academia and the PICs at MMRDA and Executiveconsultants in the Mankhurd well in -Summary, Nontransport and advance. Pamphlets each Technicalenvironment field, in English, Hindi and Summary atJournalists Marathi were distributed PIC. Records of

amongst the general writtenpublic and in the project comments,affected areas through e 'mailenvironmental and social .NGOs. Public Notice and messages, etcExecutive Summary kept maintainedon MMRDA's web sitewell in advance.

November 24, Goregaonkar Project Affected Public Notices in English, List of2001 English Households (PAHs), Marathi and Hindi to participants,

School, NGOs, Representatives leading English and Minutes of theGoregaon of the project Marathi newspapers, Meeting,0/Vest) implementation Draft Consolidated EA Photographs,Mumbai agencies, World Bank, report, Executive Pamphlets,

Journalists, etc. Summary and Non ConsolidatedTechnical Summary in EA reports,English and Marathi made Executiveavailable at PICs at Summary, NonMMRDA and Mankhurd Technicalwell in advance. Summary atPamphlets each in PIC. Records ofEnglish, Hindi and Marathi writtenwere distributed amongst comments,the general public and in e.mallthe project affected areas messages, etc

through environmental maintainedand social NGOs. PublicNotice and ExecutiveSummary kept onMMRDA's web site well inadvance.

Environmental Audit of DC - AC Serene Environmental ServicesConversion Projects

ANNEX-3

VENDORS AUTHORISED BY MOEF FORDISPOSAL OF HAZARDOUS WASTES

04!2002 10:42 2073829 WESTERN RAILWAY PAGE 01~fr

rs.~~~~~~~~~~~~~~~~~~~~~L r lllll

14M~~~~~t .Rttil

RniIw.,~~' Storcs ~~~S~ce1) J'AnYfwAfV1"~III Iti WA[fl.C.:O Cfl4

fniinvtLry of Rail m-s LQUI:F4OAD, ;1EWV DEL1- I I Ut 3Rail I3hawwll, Niew LDclli- I 10 001

F.No. 23-1 I-1-i l-SMI.)(Pn.t -(II) I:.:c I,.1 l.I'99Q

StibjecCL, L)isplt O r 'letl SOfIUO , \\.'%!t oil aiild utsecd leAtl i\i'ddl3aLLciC'

Your Rufl ci euce No. 8'.5/ISS)!709/2/oij dated 29 LU. 1 999 (o Sli i V. 1):ai:mionloblt, ;uii.t Scietaiy,1)

Picasc fhl li clicluo5edJ n list oF ui i.' ':viil; Ii:lve !1c0 i "isiicdl bI, klis bliisikt1 :1 V li- I haveroiudi(I to be ilic Aduetl;i Ulss li;uvingr rcqluisite Uncilities it) plioc6s 1II :s I), S;. /.iitc A.Ji mlCuppel Di0 &!-. 1 livy have :Iko hcecii appi pved by tiwi 1111iw ir lE~jihi ts :Cumilitt. I Usiderthese. ;1})y taiIit 1i!ssussill!j (le l'olltu%viiig is cligiblu 16i )altizia:ltiillg ill ;atuv,l1-

(i) V'alid Liccaico IC)to )cess J,1 d;.c, W10

(ii) Valid comeoi(s tiiitlei Aii jl iid Vattei Act.(iii) Vulidl ani'lOio is;ltioll tmier I la.1zL clolls \V'.i 1e iit'les.

(iv) 1E iviaoniutent, f-riend(lly lechinology Iur l)rptucessmil; adt1 sciusc,ific limpos:al Ih.cilily :uapjl uved

loI -. W!_0

*' , ,- ;,,-.,,,,,,.

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~t!l jl|)\(,.I(j

ILIST OF T HE UNIl'S REGISTEIRED \VIT MOEF AS RECYCLERS/REPROCIF SSo RZSHAVING ENVIRONMENTALLY SOUND MANlGNAGEMINT INACCI,llllT:S

TILL 30tih NOVEMIBER 2000

N a me of thie Ullit Waste permitted an1d Q1ia atity I'ate ofS.No allowed/Y (MT /KL) Issuic

Ameet Lubl ricanlts & Cliciieal Zinc Ash/Skir-ninings- 1 ,500 21 1 1 2000<

A-9 SIl\ sga-m APTS, Unvels;lyRoad, PLine- 411 016MaharasTitra 1 i

At-ya Alloys (P) Ltd B-S24, Used Lead Acicd Batte-y Scr-ap, i 06 2000Phase-l1. Industrial Area, 9,630 V2Blhiwadi, Distt. Alwar,

Rajastihanl- 301 019

| 3 1 Asawa Industries, F 34 Used Lead Acid Battery Scrap, 300 i 2.UOIndustrial Area, Gegal, Distt.

-|____ ] Ajmer, Rajasthaln_i

4 | Ashish -Pigments & Allovs P. Used Lead Acied Battery Scrap, 12 06 2000Ltd, G-1, Phase-Il, RIICO 4,500Industrial Area, Bhiwadi, Distt.Alwar, Rajasthan

5 B.M.A. Zinc (P) Itcl , F-449, lJsed Lead Acid Battery 13 H3 2000Industilal Area. Bliwadl Dist. Scrap,4,500Alwar, Rajasthan.

ZinIc Asl and Skimmings -1,350

6 Blhoomi Suldllar ClhemillcalIndustries 7-A Focal lPoint,

| Industrial Area, Sangmr- Zinlc Ash/Skiiiminigs 4,000 08 OS 2000148001 PuIn1jab

7 Contietictal Petroleum Ltd.. W|\1aste/Used Oil- 5,200 29 0' 2000

A-166 & F-162-165, RIICOlIdustrial Area, Blheror-30 I701, R.ijasathlnia

' _J

Pa-e 2 o0 6

s Deepak & Company, Ploi No. Waste/Used Oil- 5,200 26.09.2000B-20, Rd No. 16. \,aleIndusti-ial Area, Thanle- 4)0 604Maharaslhitra

Ferticliemil (India), 1','11, Ziic AsIhSkiiiminigs 5,000 04 10.1000Indlustrial Area-I, Chanditi2arh-160 002

I () Ganeshi Agro, B-7, Focal Point Zinc Ash/Skininrings 2,000 08.09.2000

SirSangmrr, PuLnjab-148 001

I I Golkonda Enter-prise Ltd., Telephone Jclly Filled and other 12 06.2000type of Copper Cabic Scrap, 3,000

711t Floor-, Sul-ya Towers, SarclarPatel Road, Secunderanaid

-- j 500003, A P __ |

12 Gupta Agro Industries, B-13-14, 08.09 2000Industrial Focal Point, Sangrur,PIPunjab-148 001 Zinc Ash and Skimmings 1,500

|| 13 ||Hans Enterprises, 1, ;\Ieera, Used Lead Acid Battery Scrap, 600 03.08.2000Golani Complex, Opp SynidicateBank, Off Vasai VajreshiwariRoad, Waliv, Vasai (East. Distt.Thane- 401 208 Maharashtra |.

14 Hiiigiri Metals Private Ltd Zinc Ash/Skimrning,1,800 23.11.2000

E-I, Industrial Area, Begrajpur

Dist. .NMuzaffarnagar- 251 203Uttar Pradeshl

I| 15liHydromet (Inidia) -Ltd. 5ii' Brass Dross 4,800 14.10 1999*Floor , 241, Mint Street ParkTowil, Chennai- 600 003 Copper Dross 6300

Tamil lNadL.

16 ICMC Coporation Ltd, 1/3| Zinc Asli/Skimmings,850 05.09.200(IIndustrial Estate,Aryarv ngalnan

Tricily- 620 010 , Tani1 M.!du

P,)c 3 uof(

1 7 ICMC Coporaitioln Ltd., Mailarn Zinc Ashi/Skimminiigs, 850 05 09.2000Village. Tinclivaniamii, TamilNaduL

IS In(liani Lead Limited, L.B.S. Usecd Lead Acid Battery and otherMarg, Majiwada, Tliane 400 Icad bearing Scrap-25,920601 31 10 2000

Maliarasliti-a iL -=I9 Indiani Phosphates and ilmc Ashi and Skimmni ngs 2,0(X) 2109.2000

Carbonates Ml',,. Co ,jlawamaRoad, Moonak,

Distt. Sangr-ul-, Punljab

20 Jarson Metal, IS, Ganesh Used Lead Acid Battery Scrap,600 03.08 2000Industrial Estate, NationalHighway, Valive, TalukaBassein,

Distt. Thiane- 401 202Maharaslhtra

21 Jyoti Clhemicals and Fertilisers Ziinc Ash and Skimminiigs- 3,000 29.09.2000

P.O No. 15, Patiahi Road,Samana,- 147101, PatialaPunjab'

i2 '7 1Malheshi Clhemicals and Allied-1I|Industries, 24 Industrial Area- |111, Sirsa, Haryana Zinc Aslh/skliminiiigs- 500 ] 08 09.2000

2| 93 ||Malwa Fertilisers, Pawara Road, Zinc Asil/Sk}immliinos 2,000 1S 09.2000]Moonak, Distt. Sangrur, Punj'ab

2 24 [Nayan Metals Pvt. Ltd., Used Lead Acid Battery Scrap- 03.08 2000960

D-6, MIDC. Lote Parshuraim,

TaKhed, Dist- RatiagiriMaliaraslhtirai

25 Newv Metal Refinery, Arvi1d Uscd Lcid Acid Battery Scrap- 04 OS 2((0Brotiler-s CompouLnd, Old 3,000Belapur Road, Ganapathii Pada,Dighe. Navi Mumbai- 4(i(i 605IMall;alr;'Ieslitr-;

-7,1 - M . ( Of

l'1a,-c 4 oF(n

20 Nikhil Mctal Works, Plot No. Use(d Lead Acid Battery Scrap, 240 04.0S.200()313, Near Shli Hari Fabrics.Boisar Road, Village LUli,roli,Taluoka Palghar, Dist. rhania-401 404 . Malhaslitra

27 Northern India Chemical Zinc Ash/Skinminings 5,000 04 10. I 0O0(j Industries. 665, Industrial Area,Pliasc-1, Chandliarhi- 160 002 _r -~~~__ .==__ -

284 Oiii Enterprises , B-9, Pr-cmii Usc(d 1ca(l edAc(i Battcr-y Scrap, 18.07.2000Colony, Kulidli, Dist. Sonlepat 3,000

_ Har yanaIJ29 Prablhat Fertilizer and Chemlical

Works , Mangalpur, KunipuraRoad, Kamial-132 001, Haryana Zinc Ash/Skimiiiiigs 4,000 25 07 .2 0 0 0 j

3 0 Puran Sons Alloys Pvt. Lid, F- Used Lead Acid Battery Scrap, 03.08.2000 |934, RIICO Indl Area, Bhiwvadi, 9,000

Alwar , Rajasthai

I1 Rahul Metal Industries, .1512- Used Lead Acid Battcry Scrap, 12.06.2000| 513-514, Matsya Industrial 6,000Area, Alwar, Rajsathan

32 Rohan Metals Pvt. Ltd, G-733, Used Lead Acid Battery Scrap, 03.08.2000Phase-ll, RIICO Industrial. 4,500Area, Bhiwari, Rajasthan - .

33 ' |Rose Zinc Limited Zinc Ashi Skimmings- 15,920 30.10 2000

505-508, S.M. Lodha Complex Brass Dross- 5,280

O|p-1 Slhastri Circle Post Office

Udaipur- 313 001 Rajasthanl

34 Sa4u11 Clhemlicals Pvt. Ltd., Ziinc Ashl/Skinimings -3,000 10.08.2000Rajdeopur. Rauza, Glhazipur

U. P.

35 || Slhailti Metal Refinery, 13Behind |Uscd Lcad Acid Battcry Scrap- 04 08 2000Slhalh Steel, Kamnan Road, 480Sativali. Vasai (East) D)istTlhanie- 401202 Maharashir.i

,I 2 1 000

Pa-e , of 6

I36 Shree Balaji Metal \W orks, Used Lcad Battcry Scrap- 900 13.10() 2000Parbatpura Kishaangarh By PassRoad. Sedaria Road. Villa,c-Sedaria, Ajmlc , Rajastilaii -

37 Simplex India. Plot No. 4, Uscd Lcad Acid Batter-' Scrap- 03.0).2000Sativali Nagar, Khok-han 600Industrial Complex, Vasai(East), Disir Tlhana- 401 208,Maha rasht ra

38 Sirosimielt Indlia Ltd. A-197, Brass Dross- 1 1,425 0608.6 Os.Road No I (F) Mev.WarIndustrial Area, UdaipuLr- 313001 Inidia

RajasthanJ

|| 39 ||Siyarco Industries, F-540/B;, Used Lead Acid Battcry Scrap, 03 03.2000Marudliar Industrial Area, Basni 1,20011II Phase, Jodhpur , Rajasthan

Zinc Ash and Skimiinings -3,600

40 Sonia Overseas (P) Ltd., 34, 06.07.2000Industrial Area, PhaseI ,Panchkula, Haryana Zinc Ashi /Skimmning, 3,600

41 Soutlhen Refineries Ltd. Used /Waste Oil- I 8,00() 31.10 2Q0()

K|Kuzhlinjaavila, Parassala P.O.

Trivandrumi -695 502 , Kerala ||

42 Surnetco Alloys Pvt. Ltd., G- Uscd Lead Acid Battcry Scrap- 31.08.2000740, Phase-11, RIICO Induistrial 9,000 1Area, Bhivadi, Distt. AlwarRajasthan Ji 11 _11

43 Sunlrise Zinc Ltd., L 2&3|Industr-ial Estate, Cunicolini

Zinc Ash! Skimminig, 11,500 12.06.2000Goa- 403 703

44 Taxoil Lubricants Pvt. Ltd.. Used /Waste Oil- 7,200 3)31. 10.2000

R-5991, MIDC Industri-al Aica

R. h,lc.lim'IclM O I M l11 i- ()b 0 70! 1 , - - - I

: 2'.2! ( i

I';,c 6 orf6

45 T11 r-Lpau iI Clcillcals Lid Zilc Ash1 /Ski mm ings- 3,60() 06.08 1I99S*Mi\alcrko a. LuLdliani.a RoadMaleikotl I. Pullni bI

40 Un1ivclrs.ll Lubricants & Wasic Oil /Used- 1 ,200 26.09 200()Speciality Producis, VillageDaniallptur. Kunjll)Ura Road.

I K ar nal . I L ary ana1; I ____ ___I _________

47 VI scolILh c Corporation .53lPalghar Tal ' C o-Op Indl ust rialEstate Lt-d. Pal,har ,Dist' Thane Wasi.c/Used OiI-5,40u KL 01.09.200( l401 404, I`\laharashtra _. ______

Registration valid ior only one year

Lznvironmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

ANNEX 4.0 ENVIRONMENT I HEALTH I SAFETY INSPECTIONSHEET

Nature of Work: Earth working operations / Civil construction (plafform extension, bridgeconstruction etc.) / Subways I FBO/ other(Tick as applicable)

Location:

Contractor Name: Sign

Name of Central Railway - Site incharge: Sign

Inspected by - Sign

Reviewed by Exec. Engineer: SignReviewed by Chief Engineer (WR/CR): . Sign

Report to JPD (Env.) - MUTP (MMRDA): Sign

Environment / Health I Safety Elements Compliance Status Comments I Remarksfor improvement

Stores/Scrap yard Management

1. All transformers in stores handled as per Yes No_requirements of Hazardous Waste Handling NA_and Management rules.

Yes No_2 Transformers and switch-gears with waste NA_

transformer oils sold to vendors authorisedby Pollution Control Board.

Yes _ No3 Logs of waste received and disposed NA_

maintained at Stores.

Yes _ No-4 Atore personnel are adequately trained for NA-

handling hazardous material (Transformeroils with PCB etc.)

Yes No5 Housekeeping in Stores/ Scrap Yard NA_

Satisfactory? Any oil leaks from scraptransformers observed?

Yes No6 Authorisation for handling Waste NA_

Transformer and other oils obtained fromState Pollution Control Board.

AIR POLLUTION -7. Watering of Sub-station construction site. No. of times/ day:

Source of water:8. PUC certificate for all construction vehicles

used, avail with contractor Yes No_NA

NOISE -9. All vehicles / DG sets have working

silences Yes No_NA

10. High noise generating operations inresidential areas limited to daytime only. Yes No_(eg. DG sets, drilling, fabrication etc.) NA

Environmental Audit of DC- AC Serene Environmental ServicesConversion Pioject of Railways

ANNEX 4.0 Cont.

Environment / Health I Safety Elements Compliance Status Comments / Remarksfor improvement

WATER POLLUTION -11. Log book of construction waste generated

& disposed available Yes No_NA

12. Any signs of contamination of nearby waterbodies due to construction operation. Yes No_If yes, method employed by contractor for NAits control - dyke / embankment etc.

13. Any construction material stored nearwater bodies with a possibility of water Yes No_contamination NA

ECOLOGICAL ISSUES14. Have any tree > 10m girth or sensitive

vegetation such as mangroves cut at Yes No_construction site and stretch NA

15. Copy of NOC from forest Dept. or relevantauthority available at sie for the trees to be Yes No_cut. NA

LAND POLLUTION / DEGRADATION -

16. Waste Logbook of waste generated on Yes No_site- Insulators, Ferrous/Non-ferrous NAmaterial, Old Transformers etc.

Yes_ No_17. Any indication of land contamination by oil NA

spills, dumping of garbage etc. onconstruction site.

Yes No_18. Log book of quarry material brought to site, NA

quarry location and related receipts ofDistrict Collector available on site

Yes_ No_19. Temporary structures, wastes dumps, NA

material etc. been cleared adequately aftercompletion of construction activity

LABOUR CAMP HEALTH AND HYGIENE -

20. Adequate drinking water and toilet facilities Yes No_in labour camps NA

Are general sanitation conditions Yes No_adequate9 NA .-

Environmental.Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

TRAFFIC CONTROL & SAFETY

21. Have all safety precautions been taken as Yes Noper requirement of Central Railway NA

22. Copy of endorsed work permit for theamount penod available at site. Yes No_

NA23. Safety and hazard sign boards at critical

locations such as cable laying works, sub- Yes No_station construction sites been installed NA

OCCUPATIONAL HEALTH AND SAFETY -

24 Are Personal protection equipments Yes_ No_(PPEs) such as Gloves for handling NAhazardous wastes, safety helmets, safetyshoes, safety belts, safety goggles etc.available for all workers?

Yes No25. Are law related to safe scaffolding, ladder NA

working, working on platforms etc.complied with. (IS codes for safety forvarious equipment/operations given inAttachment A)

Yes No_26. Any unsafe condition observed during NA_

inspection?27 Is adequate First Aid available at site? First Yes_ No_

Aid to consist of antiseptic solution. Aspirin, NA _sterilized gauze, bum ointment etc.

(ATTACHMENT A for ANNEX 4)IS CODES FOR SAFETY

1. Code of practice for pre-stressed concrete IS 1343:19802. Wire Ropes Slings & Sling legs IS 2762:19863. Safety Code of scaffold and ladders IS 3696 :19914. Excavation Work - code of safety IS 3764: 19925. Safety code for blasting and related drilling operations IS 4081 :19866. Stacking and storage of construction materials and components IS 4082: 1996

at site7. Safety code for use of hot bituminous material s IS 5916:19708. Safety code for working in compressed air IS 4138: 19779 Safety code for tunnelling work IS 4756: 197710. Concrete batching and mixing plant IS 4925: 196811. Ready / Mixed concrete IS 4926 :197612. Safety code for piling and other deep foundations IS 5121 :196913. Safety code for erection of structural steel work IS 7205: 197414 Safety code for working with construction machinery IS 7293: 197415. Wire rope slings - safety criteria and inspection procedure IS 12735:199416. Code of safety for protective barriers in and around buildings IS 13415: 199217 Industrial safety gloves IS 6994: 197318. Safety helmets IS 2925 :198419 Safety in electric and gas welding IS 818: 196320 Safety procedure in hand operated tools IS 8235: 1976

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

ANNEX 5DOCUMENTATION TO BE MAINTAINED BY CONTRACTOR

OR RAILWAY SITE ENGINEER ON SITE

1) Log book of waste stored and disposed in the WR and CR Stores (For DC/ACProject)

Type of Material Quantity Date Received Sold to- VendorScrap Stored Vendor Authorisation/Transformers/ Name Consent Numberswitch gears (From Pollution

Control Board)

2) Road watering daily schedule and source of water in the following format:

Date of Location No. of times Source of waterroad watering waswatering done

3) Daily records of Nature and quantity of construction waste generated

Type of Waste Date Quantity Disposal Method /(VVaste oil, debris, generated (in Kg, Number, Locationmetal/electric scrap and Truck Loadetc.) etc.)

4) List of trees to be cut or planned for cutting.

Tree Type Number Location

5) Copy of permission for tree felling from Tree officer / Forest Dept.

6) Amount of material taken from quarry, quarry location, copy of permit by Districtcollector etc.

Type of Quantity Date Quarry Name Copy ofMaterial and Address OfficialBought Royalty paid

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ R e c e ip t

Environmental Audit ot UG- AC .Serene Lnwronmental .>ervicesConversion Project of Raihvays

7) Number of personnel protective equipment (PPE) avail at site (safety helmets,safety belts, shoes, belts etc.)

8) List of First Aid available at site

9) Log book of fatal accidents on site

Environmental Audit of DC- AC Serene Environmental ServicesConversion Project of Railways

ANNEX 6 SURVIVAL REPORTING FOR TREE PLANTATION

Date of Survey:Name of Surveyor

Sr. Location of Plantation Planted TreesNo. Total trees Total surviving % survival

Planted (numbers)(Species /number)