EIA India TamilNadu

download EIA India TamilNadu

of 370

Transcript of EIA India TamilNadu

  • 8/14/2019 EIA India TamilNadu

    1/369

    TAMIL NADU NEWSPRINT AND PAPERS LIMITEDKagithapuram, Karur District, Tamil Nadu

    MILL EXPANSION PLAN

    ENVIRONMENTAL IMPACT

    ASSESSMENT (EIA) REPORT

    March 2008

    Prepared by

    VIMTA LABS LTD SPB PROJECTS AND CONSULTANCY LTDHYDERABAD CHENNAI

  • 8/14/2019 EIA India TamilNadu

    2/369

    PROJECT AT A GLANCE

    Project Promoters : Tamil Nadu Newsprint and Papers Limited

    Kagithapuram 639 136

    Karur District, Tamil Nadu State

    Project : Mill Expansion Plan (MEP)

    Concept : Converting the surplus wet-lapped pulp into value-added

    products by installing a new paper machine #3 with

    power boiler by establishing more environment-friendly

    operations

    Paper Capacity Increase : From 245,000 tpa to 400,000 tpa.

    PROJECT HIGHLIGHTS

    Project Cost : Rs 725 Crores

    Cost for Environmental : Rs 10 Crores

    Management

    PROJECT OBJECTIVES

    To meet the growing demand for paper in the country and to maintain theleadership in the country and in export of newsprint and P&W papers/fine

    papers.

    To maintain the status of leading player in Indian Pulp and Paper Industry byachieving 1000 tpd paper production at a single location.

    To adopt energy efficient process and plant & machinery. To meet the growing demand for paper in the country. To facilitate the manufacture of more grades of environmentally friendly

    paper/products.

    To develop the existing green belt around the mill further.

  • 8/14/2019 EIA India TamilNadu

    3/369

    SALIENT FEATURES

    Installation of a new paper machine (PM #3) having an installed capacity of155,000 tpa, for the manufacture of surface sized printing and writing and on-

    machine light-weight coated papers

    Reduction in the overall specific energy consumption with energy-efficient designof PM #3 at the rated production capacity.

    Balancing of chemical bagasse fibre line for achieving a production capacity from500 tpd to 550 tpd has been planned by installing the following:

    One (1) continuous digester of capacity 225 BD tpd unbleached bagassepulp.

    One (1) brown stock washing street for 600 BD tpd unbleached bagassepulp.

    One (1) screening plant, consisting of combined pressure knotter andprimary screen, secondary, tertiary and quaternary screens with cleaning

    system, for 600 BD tpd unbleached bagasse pulp capacity.

    Balancing of hard wood fibre line for achieving a production capacity from300 tpd to 330 tpd by upgrading pumps and pipe lines, as considered necessary.

    Installation of new coal fired boiler of capacity 150 tph to supplement theadditional steam demand.

    Installation of high efficiency electrostatic precipitator for the new coal firedboiler.

    Adequate pollution control measures to minimise adverse impacts on theenvironment.

    Improvements in wastewater treatment system with one additional secondaryclarifier to take care of the ageing of existing secondary clarifiers.

    SOCIAL COMMITMENT

    On the social and community development front, TNPL has been committed to social

    responsibility in helping farmers and other inhabitants of the hamlets in and around

    the mill site as stated below.

  • 8/14/2019 EIA India TamilNadu

    4/369

    Drinking Water supply

    Provision of drinking water to all the five villages covered under TNPL EffluentWater Lift Irrigation Scheme (TEWLIS).

    TNPLs contribution in the construction of service reservoir of 2.5 lakh litrecapacity for distribution of drinking water to ten hamlets under Kagithapuram

    Town Panchayat.

    TNPLs contribution in the construction of service reservoir of one lakh litrecapacity and laying of new pipelines for the villages under Punjai Thottakurichi

    Town Panchayat.

    Provision of taps at Ponnia Goundanpudur and construction of 25000 litrecapacity ground level reservoir at Velliyampalayam and extension of pipelines to

    Kariampatti.

    Execution of pipeline work for drinking water supply to certain areas inVelayuthampalayam.

    Road Development Works

    Velayuthampalayam four road junction work including expansion. Construction of traffic island in Velayuthampalayam. Funding in two phases during the financial years 1999-2000 and 2000-2001 for

    improvement/formation of roads in various village panchayats nearby.

    Renewal of Black Topped (BT) road branching from Velayuthampalayam-Noyyalmain road upto Kattipalayam well.

    Construction of retaining wall portion on the road side near culverts at NaduNanaparappu intake village.

  • 8/14/2019 EIA India TamilNadu

    5/369

    Social Welfare

    TNPL has plans to institutionalise the Corporate Social Responsibility (CSR)activities so that the CSR transforms itself into personal Social Responsibility for

    the personnel manning the factory. With this in mind, the company has set apart

    an amount of Rs. 50 lakh for the year 2007-2008 for the following activities:

    TNPL Trauma Care Centre at a cost of Rs. 20 lakh is planned to be built andnecessary equipment will be provided to the Centre at a cost of Rs. 5 lakh

    Uplift the abutting villages through village adoption scheme. A sum ofRs. 5 lakh will be set apart for this purpose every year.

    Under the Women & Child Welfare Scheme, a sum of Rs. 5 lakh has beenearmarked.

    Financial assistance to economically weaker sections to pursue theireducation. A sum of Rs. 2 lakh will be provided for this purpose.

    Under CSR, it has become the primary responsibility of TNPL to ensure thatall the children in the rural areas are provided with education to avoid any

    dropouts. To encourage the parents and to supplement their needs, it is

    proposed to provide uniforms and footwear to the children studying in

    Elementary Schools in and around TNPL. Initially, it is proposed to provide

    such facilities at a cost of Rs. 1 lakh.

    Under Special Prize scheme to student belonging to SC/MBC/BC, a sum ofRs. 1 lakh will be set apart for this purpose

    Under sports promotion scheme, a sum of Rs. 2 lakh will be providedtowards purchase of sports materials and to meet the expenditure towards

    coaches etc.

    Under training of students to pursue competitive examination, a sum ofRs. 2 lakh will be provided

    Assistance to TEWLIS farmers (Visit of 5 formers to places to learn aboutinnovate farming and marketing), a sum of Rs. 1 lakh will be provided

    Under Womens Self Help Group (Hollow block manufacturing), a sum ofRs. 2 lakh will be provided

    For Apparel Training Centre for unemployed, a sum of Rs. 2 lakh will beprovided

  • 8/14/2019 EIA India TamilNadu

    6/369

    Career development Centre Library (one employee will be sent abroadevery year), a sum of Rs. 2 lakh will be provided

    Life enrichment skills (Promotions of Social Welfare), a sum of Rs. 1 lakhwill be provided

    Assistance to differently abled persons (prosthetics & supporting aids), asum of Rs. 1 lakh will be provided

    Under Promotion of Rural Arts & Crafts, a sum of Rs. 1 lakh will beprovided

    Under Establishment of Tamil Arts, Literature & Cultural DevelopmentCentre, a sum of Rs. 1 lakh will be provided

    Regular medical camps and eye-camps in the surrounding villages to providetreatment with free supply of medicines and highlight the aspects of hygiene and

    good health.

    Adoption/Maintenance of primary health centre, Punnam (each financial year). Provision of furniture and scientific equipment to nearby schools.

    Repair works to school buildings. Childrens park at Velliannai village, Samathuvapuram. Construction/Renovation of places of worship. Contribution to sports/cultural activities. Flood-relief fund to Thavittupalayam villagers who were affected by overflow of

    Cauvery water.

    Other Activities

    Construction of retaining wall and pipe culverts, earthen drains excavation etc.,in the TEWLIS area for a length of 22.5 km to solve the chronic drainage

    problems.

    Desilting the Pugalur canal near Thalavapalayam in Thottakuruchi TownPanchayat.

  • 8/14/2019 EIA India TamilNadu

    7/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited TOC-1

    TABLE OF CONTENTS

    CHAPTER # TITLE PAGE #

    1 EXECUTIVE SUMMARY..............................................................................................C1-1

    1.1 Project Profile................................................................................................C1-1

    1.2 Facilities under MEP........................................................................................C1-2

    1.3 Environmental Impact Assessment (EIA) and Environmental ...............................C1-4

    Management Plan (EMP)

    1.4 Conclusions ...................................................................................................C1-6

    2 BACKGROUND.........................................................................................................C2-1

    2.1 Project Promoters ..........................................................................................C2-2

    2.2 Need for MEP.................................................................................................C2-2

    2.3 Social Development Activities..........................................................................C2-5

    2.4 Project Site ...................................................................................................C2-6

    2.5 Environmental Setting of the Site.....................................................................C2-9

    2.6 Scope of the Present Study ........................................................................... C2-10

    2.7 Compliance to Terms of Reference (TOR) issued by MoEF.................................C2-10

    2.8 Methodology of the Study .............................................................................C2-11

    2.9 Environmental Impact Assessment (EIA) Report .............................................. C2-13

    3 Administrative and Legislative framework...................................................................C3-1

    3.1 Administrative and Legislative Background........................................................C3-1

    3.2 Environmental Regulations..............................................................................C3-3

    3.3 Regulations, Standards and Conditions followed by ............................................C3-7

    The Tamil Nadu Pollution Control Board (TNPCB)

    3.4 Hazardous Wastes (Management and Handling) Rules, 1989.............................C3-14

    with subsequent Amendments 2000, 2002 and 2003

    3.5 Charter on Corporate Responsibility for Environmental Protection (CREP) ........C3-15

    4 PROJECT DETAILS AND SOURCES OF POLLUTION........................................................C4-1

    4.1 Introduction ..................................................................................................C4-1

    4.2 Project Category ............................................................................................C4-14.3 Layout of the Proposed Project ........................................................................C4-1

    4.4 Land Requirement..........................................................................................C4-1

    4.5 Process Description ........................................................................................C4-1

    4.6 Details of Existing Process...............................................................................C4-2

    4.7 Details of Proposed Expansion....................................................................... C4-49

    4.8 Materials and Resources Requirement ............................................................C4-61

    4.9 Process Chemicals........................................................................................C4-67

    4.10 Proposed schedule for Implementation ...........................................................C4-70

    4.11 Capital Costs ...............................................................................................C4-70

    4.12 Sources of Pollution......................................................................................C4-71

    5 BASELINE ENVIRONMENTAL STATUS .........................................................................C5-1

    5.1 Introduction ..................................................................................................C5-1

    5.2 Geology and Hydro-Geology............................................................................C5-1

    5.3 Micro-Meteorology .........................................................................................C5-3

    5.4 Ambient Air Quality......................................................................................C5-17

    5.5 Water Quality ..............................................................................................C5-30

    5.6 Soil Characteristics.......................................................................................C5-39

    5.7 Noise Level Survey.......................................................................................C5-45

    5.8 Ecological Studies ........................................................................................C5-55

    5.9 Land Use Studies .........................................................................................C5-83

    5.10 Demography and Socio-Economics.................................................................C5-86

    5.11 Places of Historical and Tourist Importance .....................................................C5-89

  • 8/14/2019 EIA India TamilNadu

    8/369

    EIA Study Tamil Nadu Newsprint and Papers Limited

    TOC-2 Prepared by SPB-PC & Vimta Labs Limited

    CHAPTER # TITLE .......................................................................................................PAGE #

    6 IMPACT ASSESSMENT ..............................................................................................C6-1

    6.1 Introduction..................................................................................................C6-1

    6.2 Impact During Construction Phase ...................................................................C6-1

    6.3 Impacts during Operation ...............................................................................C6-4

    7 ENVIRONMENTAL MANAGEMENT PLAN .......................................................................C7-1

    7.1 Introduction..................................................................................................C7-1

    7.2 Anticipated Environmental Impacts & Mitigation Measures ..................................C7-2

    7.3 Environmental Management during Construction ...............................................C7-4

    7.4 Management during Operational Stage .............................................................C7-7

    8 ENVIRONMENTAL MONITORING ................................................................................C8-1

    8.1 Monitoring and Reporting Procedure.................................................................C8-2

    8.2 Infrastructure for Environmental Protection.......................................................C8-6

    9 Environment Management and Training......................................................................C9-1

    9.1 Introduction..................................................................................................C9-1

    9.2 Formation of an Environmental Management System .........................................C9-19.3 Implementation of an Environmental Management System .................................C9-2

    9.4 Implementation Schedule of Mitigation Measures...............................................C9-9

    9.5 Institutional Arrangements for Environment Management .................................C9-10

    9.6 Budgetary Cost Estimates for Environmental Management................................C9-11

    10 RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN ........................................... C10-1

    10.1 Introduction ................................................................................................C10-1

    10.2 Scope of the Study ...................................................................................... C10-2

    10.3 Approach to the Study.................................................................................. C10-3

    10.4 Hazard Identification.................................................................................... C10-5

    10.5 Visualisation of MCA Scenarios .................................................................... C10-10

    10.6 Hazard Assessment and Evaluation .............................................................. C10-12

    10.7 Disaster Management Plan.......................................................................... C10-31

    10.8 Emergencies.............................................................................................. C10-32

    10.9 Emergency Organisation............................................................................. C10-33

    10.10 Emergency Responsibilities ......................................................................... C10-34

    10.11 Emergency Facilities................................................................................... C10-38

    10.12 Emergency Actions..................................................................................... C10-41

    10.13 General .................................................................................................... C10-42

    10.14 Off-Site Emergency Preparedness Plan ......................................................... C10-43

    11 SOURCES OF DATA AND INFORMATION ...................................................................C11-1

    12 REFERENCES......................................................................................................... C12-1

    Annexes

    1 Ambient Air Quality Levels Winter 2008

    2 Ground Water and Surface Water Quality

    3 Soil Quality for Treated Wastewater Irrigated Area

    4 Ecological Details

    5 Village-wise Landuse Pattern

    6 Demographical Details

    7 Existing data on the total water consumption with AOX levels

    8 Note on the follow up of the CREP Guidelines with Odour Control

    9 Schematic flow diagram of wastewater treatment plant after MEP

  • 8/14/2019 EIA India TamilNadu

    9/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited TOC-3

    Appendix

    1 MoEF Notification 2006

    2 Mill layout

    3 Point-wise compliance details of conditions stipulated in Environmental Clearance

    accorded by MOEF

  • 8/14/2019 EIA India TamilNadu

    10/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited 1

    EXECUTIVE SUMMARY

    1 Project Profile

    Tamil Nadu Newsprint and Papers Limited (TNPL) owns and operates an

    integrated pulp and paper manufacturing facility at Kagithapuram in theState of Tamil Nadu. TNPL was promoted by the Government of Tamil Nadu

    for the manufacture of newsprint and printing and writing (P&W) papers,

    using bagasse as the principal fibre source. The mill, located at

    Kagithapuram in Karur District (about 400 km south west of Chennai), was

    commissioned in October 1985 with an installed capacity of 90,000 tpa of

    newsprint/P&W paper to meet the twin objectives of conserving the fast

    depleting forest resources and to promote use of annually renewable raw

    material.

    TNPL achieved commendable production performance/productivity levelsand posted impressive operating results within a short period of its

    inception.

    TNPL commissioned its second paper machine in 1996 to increase the

    installed capacity to 180,000 tpa, with a swing option to manufacture

    newsprint or fine papers, depending on the market conditions.

    During 2002, the paper machine#1 was retrofitted/ upgraded, resulting in

    a significant increase in the annual installed capacity, to 205,000 tpa.

    The mill has always strived to attain best possible standards of quality, by

    practising ISO 9001:2000 standards in the manufacturing operations. The

    mill has established an Environment Management System (EMS) complying

    with ISO 14001 standards and has been acknowledged by the Centre for

    Science and Environment (CSE) by awarding the THREE GREEN LEAVES

    under GREEN RATING PROJECT. The award of Excellence in Corporate

    Governance to TNPL stands as ample testimony to the overall operational

    efficiencies, transparency in mill functioning and social commitment of the

    mill. TNPL has been granted `Eco label licence for the plain copier paper as

    per IS 14490-97 by Bureau of Indian Standards.

    Consistent with its environment friendly and quality conscious development

    policy, TNPL had taken up its Mill Development Plan (MDP) to establish new

    ECF fibre lines (for both hardwood and chemical bagasse pulping streets)

    and chemical recovery island to make the operations more environment-

    friendly.

  • 8/14/2019 EIA India TamilNadu

    11/369

    EIA Study Tamil Nadu Newsprint and Papers Limited

    2 Prepared by SPB-PC & Vimta Labs Limited

    Installation of a new ECF fibreline for hardwood pulping, conversion of the

    existing chemical bagasse bleach plants to ECF bleaching sequence,

    establishment of related chemical preparation facilities to meet the

    requirements of the new ECF fibre lines, and augmentation/new facilities in

    chemical recovery island are being carried out. The mill has obtained the

    Environmental Clearance for the ongoing MDP which shall increase the

    production level to 245,000 tpa and wet-lapping of 45,000 tpa surplus pulp

    and market the same. The implementation of this MDP is nearing

    completion.

    Based on the performance in the current year and its anticipated

    performance in future years, TNPL now proposes to convert the surplus

    wet-lapped pulp into value-added products by installing a new paper

    machine (PM #3) of capacity 155,000 tpa along with its accessories and

    auxiliaries, and also balancing the back end, viz. bagasse and hardwood

    pulping streets and the utilities, under a Mill Expansion Plan (MEP). This

    MEP after implementation shall place TNPL as the only mill in India with

    paper production of 1000 tpd at single location.

    The additional steam requirement will be met by increased steam

    generation, with the installation of an energy-efficient coal fired boiler of

    capacity 150 tph. The existing power generation capacity is considered

    adequate for meeting the expansion requirements as well.

    The total fresh water requirement after implementation of the proposed

    MEP will increase to 53,970 m3 per day, from a post MDP level of 41,380m3/day, as per the Consent issued for ongoing expansion plan. The

    wastewater discharge will be 41,405 m3/day.

    All the project facilities will be installed in the existing site. No additional

    land needs to be acquired.

    The ongoing MDP is nearing completion and the proposed MEP is intended

    to take off dovetailing the completion of MDP. The environmental scenario

    as achieved post MDP will continue to prevail unaltered post MEP too,

    without any adverse impact on the environment.

    2 Facilities under MEP

    TNPL proposes to install a new paper machine (PM #3), having an installed

    capacity of 155,000 tpa, for the manufacture of surface sized printing and

    writing and on-machine light-weight coated papers. The proposed paper

    machine will have facilities to produce different grades of coated and

    uncoated papers.

    The objectives of the installation of PM #3 are as follows:

  • 8/14/2019 EIA India TamilNadu

    12/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited 3

    Add coated paper production capability to meet increasing future

    demands expected for surface-sized printing and writing, copier and

    on-machine light weight coated papers.

    Designate PM #3 for SS printing and writing, copier and on-machine

    lightweight coated paper production.

    Design PM #3 for low water consumption to reduce the overall

    specific fresh water requirement.

    Reduce the overall specific energy consumption with energy-efficient

    design of PM #3 at the rated production capacity.

    Along with installation of PM #3, it is also proposed to balance the

    backend, viz. chemical bagasse and hardwood pulp mills and the utilities

    section, as described below

    Balancing of chemical bagasse fibre line for achieving a production

    capacity from 500 tpd to 550 tpd has been planned by installing the

    following:

    One (1) continuous digester of capacity 225 BD tpd unbleached

    bagasse pulp.

    One (1) brown stock washing street for 600 BD tpd unbleached

    bagasse pulp.

    One (1) screening plant, consisting of combined pressure

    knotter and primary screen, secondary, tertiary and quaternary

    screens with cleaning system, for 600 BD tpd unbleached

    bagasse pulp capacity.

    Balancing of hard wood fibre line for achieving a production capacity

    from 300 tpd to 330 tpd has been planned by upgrading pumps and

    pipe lines, as considered necessary

    Installation of new coal fired boiler of capacity 150 tph to supplementthe additional steam demand.

    Installation of high efficiency electrostatic precipitator for the new

    coal fired boiler.

    Adequate pollution control measures to minimise adverse impacts on

    the environment.

    Improvements in wastewater treatment system with one additional

    secondary clarifier to take care of the ageing of existing secondary

    clarifiers.

  • 8/14/2019 EIA India TamilNadu

    13/369

    EIA Study Tamil Nadu Newsprint and Papers Limited

    4 Prepared by SPB-PC & Vimta Labs Limited

    3 Environmental Impact Assessment (EIA) and Environmental

    Management Plan (EMP)

    Comprehensive Environmental Impact Assessment (CEIA) has been

    conducted during September 2004-September 2005. CEIA has been

    upgraded using baseline field data monitored again during January 2008.

    The January 2008 data has been monitored as per TOR conditions of MoEF.

    The existing baseline data as represented in upgraded CEIA including

    winter season 2008 data has been used for predicting the anticipated

    environmental impact on the surroundings.

    Construction Phase

    The construction activities of new installations will not necessitate any

    displacement of people, cutting of vegetation, etc., as the construction willbe carried out within the existing mill premises. This phase does not

    involve major changes in the terrain.

    Operation Phase

    Air Environment

    The major pollutants from the mill after MEP are suspended

    particulate matter (SPM) and sulphur dioxide (SO2) from the new

    power boiler

    The air dispersion modelling has been carried out for two scenarios using

    meteorological data monitored during the month of January 2008 at site,

    based on existing base line data.

    The maximum net incremental GLCs due to the MEP for SO2 and SPM are

    superimposed on the baseline SO2and SPM concentrations recorded during

    the study to arrive at the realistic baseline concentrations for the proposed

    MEP project.

    The details of the resultant concentration of SPM and SO2are furnished inthe table below, for industrial as well as residential zone.

    Pollutant Maximum AAQ

    Concentrations

    Recorded

    During Baseline

    Study (g/m3)

    Realistic

    baseline

    concentratio

    ns after MDP

    (g/m3)

    Net incremental

    concentrations

    due to Post -

    MEP (g/m3)

    Final Resultant

    Concentrations

    (g/m3)

    Industrial Zone

    SPM 190.8 189.9 0.9 190.8

    SO2

    26.8 30.8 11.0 41.8

  • 8/14/2019 EIA India TamilNadu

    14/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited 5

    Pollutant Maximum AAQ

    Concentrations

    Recorded

    During Baseline

    Study (g/m3)

    Realistic

    baseline

    concentratio

    ns after MDP

    (g/m3)

    Net incremental

    concentrations

    due to Post -

    MEP (g/m3)

    Final Resultant

    Concentrations

    (g/m3)

    Residential Zone

    SPM 180.1 179.2 0.3 179.5

    SO2 21.8 25.8 3.1 28.7

    A perusal of the above table clearly reveals that SPM and SO2are likely to

    be within the prescribed limits specified by CPCB for industrial zone and

    residential zone, thus showing insignificant impact due to the expansion.

    Water Environment

    In the plant, water is used mainly for paper machine, pulp mill apart from

    cooling water requirement and domestic purposes. The total water

    requirement of the mill and colony, at 53,970 m/day, will be met from

    river Cauvery. The additional water requirement for MEP will continue to be

    met from river Cauvery. The water drawal shall be within the Consented

    Quantity and hence, no permission for additional drawal of surface water is

    required.

    The existing wastewater treatment plant is proposed to be augmented with

    the installation of additional primary and secondary clarifiers. The mill shallalso consider installation of suitable filtration systems for recovery of fibre

    and to ensure effective recycling of water at paper machine itself.

    Wastewater will continue to be treated, to conform to the statutory

    standards of state pollution control board and MoEF before discharging on

    land for irrigation.

    The quality of water resources in the study area will not be adversely

    affected.

    Solid Waste

    The solid waste from the coal-fired boilers is mainly fly ash and bottom

    ash.

    The expected total fly ash generated from the coal-fired boilers is

    about 240 tonnes per day. Fly ash generated is being given to

    cement manufacturers. Part of the lime sludge, being disposed of as

    purge for non-process elements especially silica, is being given to

    cement manufacturers. The mill, as part of its commitment for

    Environmental upkeep, intends to install a mini-cement plant for

  • 8/14/2019 EIA India TamilNadu

    15/369

    EIA Study Tamil Nadu Newsprint and Papers Limited

    6 Prepared by SPB-PC & Vimta Labs Limited

    reusing the fly ash along with excess lime sludge generated which

    need disposal. In post MEP operations also it is proposed to re-burn

    the lime sludge in the lime mud reburning kilns. The pith and chipper

    dust generated are being used as fuel in boilers. The WWTP sludge

    will be thickened through dewatering machines and the cake will be

    given to small cardboard manufacturers

    The mill is installing a dedicated sludge dewatering machine for

    dewatering the sludge upto a dryness level of 50%. This sludge shall

    be fired in the boilers.

    Hence, no adverse impacts due to solid waste generation are

    envisaged

    Soil Environment

    An estimation of physico-chemical analysis of existing soil environment

    indicates no adverse impact on soil quality due to future activities of the

    mill.

    Noise Environment

    The baseline noise level (Leq) recorded is about 54.7 dB(A) and the

    predicted incremental noise level at the boundary due to the

    operation of MEP is likely to be

  • 8/14/2019 EIA India TamilNadu

    16/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited 7

    Socio-Economics

    The land required for the construction under the proposed project is

    already under the possession of TNPL. There will not be any resettlement

    and rehabilitation. Thus, there will not be any adverse socio-economic

    implications. The economic status of the area is likely to improve, as there

    will be direct/indirect employment generation during construction and

    operational phases.

    Risk Assessment & Disaster Management

    The preliminary risk assessment of the plant has identified no hazardous

    events, which would project damaging energies outside of the plant

    boundary. Events identified for offsite facilities are estimated to occur at

    extremely low incident frequencies and/or not to significant levels of

    consequence. Management of hazardous event scenarios and risks ingeneral can be adequately managed to acceptable levels.

    4 Conclusions

    Growth and development, in harmony with the environment, has always

    been the approach of TNPL.

    The conclusions of EIA are:

    The Mill Expansion Plan (MEP) is structured to be inline with the

    requirements of MoEF/CPCB/TNPCB.

    Community impacts will be beneficial, as the project will generate

    economic benefits for the locality.

    Continued improvement in wastewater treatment facilities coupled

    with high efficiency electrostatic precipitator results in minimising the

    impacts on environment.

    With the effective implementation of the Environment Management Plan

    (EMP) during the planning, design, construction and operation phases, theexpansion can proceed without any negative impact.

  • 8/14/2019 EIA India TamilNadu

    17/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited C1-1

    1 EXECUTIVE SUMMARY

    1.1 Project Profile

    Tamil Nadu Newsprint and Papers Limited (TNPL) owns and operates an

    integrated pulp and paper manufacturing facility at Kagithapuram in theState of Tamil Nadu. TNPL was promoted by the Government of Tamil Nadu

    for the manufacture of newsprint and printing and writing (P&W) papers,

    using bagasse as the principal fibre source. The mill, located at

    Kagithapuram in Karur District (about 400 km south west of Chennai), was

    commissioned in October 1985 with an installed capacity of 90,000 tpa of

    newsprint/P&W paper to meet the twin objectives of conserving the fast

    depleting forest resources and to promote use of annually renewable raw

    material.

    TNPL achieved commendable production performance/productivity levelsand posted impressive operating results within a short period of its

    inception.

    TNPL commissioned its second paper machine in 1996 to increase the

    installed capacity to 180,000 tpa, with a swing option to manufacture

    newsprint or fine papers, depending on the market conditions.

    During 2002, the paper machine#1 was retrofitted/ upgraded, resulting in

    a significant increase in the annual installed capacity, to 205,000 tpa.

    The mill has always strived to attain best possible standards of quality, by

    practising ISO 9001:2000 standards in the manufacturing operations. The

    mill has established an Environment Management System (EMS) complying

    with ISO 14001 standards and has been acknowledged by the Centre for

    Science and Environment (CSE) by awarding the THREE GREEN LEAVES

    under GREEN RATING PROJECT. The award of Excellence in Corporate

    Governance to TNPL stands as ample testimony to the overall operational

    efficiencies, transparency in mill functioning and social commitment of the

    mill. TNPL has been granted `Eco label licence for the plain copier paper as

    per IS 14490-97 by Bureau of Indian Standards.

    Consistent with its environment friendly and quality conscious development

    policy, TNPL had taken up its Mill Development Plan (MDP) to establish new

    ECF fibre lines (for both hardwood and chemical bagasse pulping streets)

    and chemical recovery island to make the operations more environment-

    friendly.

  • 8/14/2019 EIA India TamilNadu

    18/369

    EIA Study Tamil Nadu Newsprint and Papers Limited

    C1-2 Prepared by SPB-PC & Vimta Labs Limited

    Installation of a new ECF fibreline for hardwood pulping, conversion of the

    existing chemical bagasse bleach plants to ECF bleaching sequence,

    establishment of related chemical preparation facilities to meet the

    requirements of the new ECF fibre lines, and augmentation/new facilities in

    chemical recovery island are being carried out. The mill has obtained the

    Environmental Clearance for the ongoing MDP which shall increase the

    production level to 245,000 tpa and wet-lapping of 45,000 tpa surplus pulp

    and market the same. The implementation of this MDP is in almost

    completion stage.

    Based on the performance in the current year and its anticipated

    performance in future years, TNPL now proposes to convert the surplus

    wet-lapped pulp into value-added products by installing a new paper

    machine (PM #3) of capacity 155,000 tpa along with its accessories and

    auxiliaries, and also balancing the back end, viz. bagasse and hardwood

    pulping streets and the utilities, under a Mill Expansion Plan (MEP). This

    MEP after implementation shall place TNPL as the only mill in India with

    paper production of 1000 tpd at single location.

    The additional steam requirement will be met by increased steam

    generation, with the installation of an energy-efficient coal fired boiler of

    capacity 150 tph. The existing power generation capacity is considered

    adequate for meeting the expansion requirements as well.

    The total fresh water requirement after implementation of the proposed

    MEP will increase to 53,970 m per day, from a post MDP level of41,380 m3/day, as per the Consent issued for ongoing expansion plan. The

    wastewater discharge will be 41,405 m3/day.

    All the project facilities will be installed in the existing site. No additional

    land needs to be acquired.

    The ongoing MDP is nearing completion and the proposed MEP is intended

    to take off dovetailing the completion of MDP. The environmental scenario

    as achieved post MDP will continue to prevail unaltered post MEP too,

    without any adverse impact on the environment.

    1.2 Facilities under MEP

    TNPL proposes to install a new paper machine (PM #3), having an installed

    capacity of 155,000 tpa, for the manufacture of surface sized printing and

    writing and on-machine light-weight coated papers. The proposed paper

    machine will have facilities to produce different grades of coated and

    uncoated papers.

    The objectives of the installation of PM #3 are as follows:

  • 8/14/2019 EIA India TamilNadu

    19/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited C1-3

    Add coated paper production capability to meet increasing futuredemands expected for surface-sized printing and writing, copier and

    on-machine light weight coated papers

    Designate PM #3 for SS printing and writing, copier and on-machinelightweight coated paper production

    Design PM #3 for low water consumption to reduce the overallspecific fresh water requirement

    Reduce the overall specific energy consumption with energy-efficientdesign of PM #3 at the rated production capacity

    Along with installation of PM #3, it is also proposed to balance the

    backend, viz. chemical bagasse and hardwood pulp mills and the utilities

    section, as described below

    Balancing of chemical bagasse fibre line for achieving a productioncapacity from 500 tpd to 550 tpd

    One (1) continuous digester of capacity 225 BD tpd unbleachedbagasse pulp

    One (1) brown stock washing street for 600 BD tpd unbleachedbagasse pulp

    One (1) screening plant, consisting of combined pressureknotter and primary screen, secondary, tertiary and quaternary

    screens with cleaning system, for 600 BD tpd unbleached

    bagasse pulp capacity.

    Balancing of hard wood fibre line for achieving a production capacityfrom 300 tpd to 330 tpd has been planned by upgrading pumps and

    pipe lines, as considered necessary

    Installation of new coal fired boiler of capacity 150 tph to supplementthe additional steam demand.

    Installation of high efficiency electrostatic precipitator for the newcoal fired boiler.

    Adequate pollution control measures to minimise adverse impacts onthe environment.

    Improvements in wastewater treatment system with one additionalsecondary clarifier to take care of the ageing of existing secondary

    clarifiers

  • 8/14/2019 EIA India TamilNadu

    20/369

    EIA Study Tamil Nadu Newsprint and Papers Limited

    C1-4 Prepared by SPB-PC & Vimta Labs Limited

    1.3 Environmental Impact Assessment (EIA) and Environmental

    Management Plan (EMP)

    Comprehensive Environmental Impact Assessment (CEIA) has been

    conducted during September 2004-September 2005. CEIA has been

    upgraded using baseline field data monitored again during January 2008.

    The January 2008 data has been monitored as per TOR conditions of MoEF.

    The existing baseline data as represented in upgraded CEIA including

    winter season 2008 data has been used for predicting the anticipated

    environmental impact on the surroundings.

    Construction Phase

    The construction activities of new installations will not necessitate any

    displacement of people, cutting of vegetation, etc., as the construction willbe carried out within the existing mill premises. This phase does not

    involve major changes in the terrain.

    Operation Phase

    Air Environment

    The major pollutants from the mill after the proposed expansion are

    suspended particulate matter (SPM) and sulphur dioxide (SO2) from the

    new power boiler. The air dispersion modelling has been carried out for

    using meteorological data monitored at site, based on existing base line

    data.

    The ambient air quality levels for SPM and SO2 are well below the

    permissible limits, thus showing insignificant impact due to the expansion.

    Water Environment

    The additional water requirement for MEP will continue to be met from river

    Cauvery. The water drawal shall be within the Consented Quantity and

    hence, no permission for additional drawal of surface water is required.

    The existing wastewater treatment plant is proposed to be augmented with

    the installation of additional primary and secondary clarifiers. The mill shall

    also consider installation of suitable filtration systems for recovery of fibre

    and to ensure effective recycling of water at paper machine itself.

    Wastewater will continue to be treated, to conform to the statutory

    standards of state pollution control board and MoEF before discharging on

    land for irrigation.

  • 8/14/2019 EIA India TamilNadu

    21/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited C1-5

    The quality of water resources in the study area will not be adversely

    affected.

    Solid Waste

    The solid waste from the coal-fired boilers is mainly fly ash and bottomash.

    The expected total fly ash generated from the coal-fired boilers is about

    240 tonnes per day. The mill, as part of its commitment for Environmental

    upkeep, intends to install a mini-cement plant for reusing the fly ash along

    with excess lime sludge generated which need disposal.

    The mill is installing a dedicated sludge dewatering machine for dewatering

    the sludge upto a dryness level of 50%. This sludge shall be fired in the

    boilers.

    Hence, no adverse impacts due to solid waste generation are envisaged.

    Soil Environment

    An estimation of physico-chemical analysis of existing soil environment

    indicates no adverse impact on soil quality due to future activities of the

    mill.

    Noise Environment

    The baseline noise level (Leq) recorded is about 54.7 dB(A) and the

    predicted incremental noise level at the boundary due to the operation of

    MEP is likely to be

  • 8/14/2019 EIA India TamilNadu

    22/369

    EIA Study Tamil Nadu Newsprint and Papers Limited

    C1-6 Prepared by SPB-PC & Vimta Labs Limited

    Socio-Economics

    The land required for the construction under the proposed project is

    already under the possession of TNPL. There will not be any resettlement

    and rehabilitation. Thus, there will not be any adverse socio-economic

    implications. The economic status of the area is likely to improve, as there

    will be direct/indirect employment generation during construction and

    operational phases.

    Risk Assessment & Disaster Management

    The preliminary risk assessment of the plant has identified no hazardous

    events, which would project damaging energies outside of the plant

    boundary. Events identified for offsite facilities are estimated to occur at

    extremely low incident frequencies and/or not to significant levels of

    consequence. Management of hazardous event scenarios and risks ingeneral can be adequately managed to acceptable levels.

    1.4 Conclusions

    Growth and development, in harmony with the environment, has always

    been the approach of TNPL.

    The conclusions of EIA are:

    The Mill Expansion Plan (MEP) is structured to be inline with therequirements of MoEF/CPCB/TNPCB.

    Community impacts will be beneficial, as the project will generateeconomic benefits for the locality.

    Continued improvement in wastewater treatment facilities coupledwith high efficiency electrostatic precipitator results in minimising the

    impacts on environment.

    With the effective implementation of the Environment Management Plan

    (EMP) during the planning, design, construction and operation phases, theexpansion can proceed without any negative impact.

  • 8/14/2019 EIA India TamilNadu

    23/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited C2-1

    2 BACKGROUND

    Tamil Nadu Newsprint and Papers Limited (TNPL) was promoted by the

    Government of Tamil Nadu for the manufacture of newsprint and printing

    and writing (P&W) papers, using bagasse as the principal fibre source.About 20% of its P&W paper production is exported. Over the years, the

    mill has been improving its environmental performance by adopting various

    measures. Apart from its sound technical and financial performance, TNPL

    has always strived to attain best possible standards of quality, by

    practising ISO 9001:2000 standards in the manufacturing operations. The

    mill operations are environment friendly and conform to pollution

    abatement norms that are superior to the state and national standards.

    The mill has established an Environment Management System (EMS)

    complying with ISO 14001 standards. As a testimony of TNPLs

    commitment to the protection of the environment, World Wide Fund for

    Nature India has accorded permission to TNPL to use it Panda logo in

    TNPLs branded products. TNPLs environmental compliance has been

    acknowledged by the Centre for Science and Environment (CSE) by

    awarding the THREE GREEN LEAVES under GREEN RATING PROJECT.

    The award of Excellence in Corporate Governance to TNPL stands as ample

    testimony to the overall operational efficiencies, transparency in mill

    functioning and social commitment of the mill. TNPL has been granted

    `Eco label licence for the plain copier paper as per IS 14490-97 by Bureau

    of Indian Standards.

    The mill is implementing a comprehensive Mill Development Plan (MDP) to

    meet the requirements of the Ministry of Environment and Forests (MoEF)

    as part of the mills compliance to the Charter on Corporate Responsibility

    for Environmental Protection (CREP) as applicable to pulp and paper

    industries. The ongoing expansion is to achieve the target set by the

    CREP.

    Under the ongoing MDP, TNPL has installed 300 tpd Elemental Chlorine

    Free (ECF) chemical hardwood pulp line and a 500 tpd Elemental Chlorine

    Free (ECF) chemical bagasse bleach plant to replace the existing chlorine

    based bleach plants.

    However, to be a leading player in the Indian Pulp and Paper Industry, the

    mill intends to install a new paper machine of capacity 155,000 tpa along

    with the balancing of bagasse pulp mill for a capacity of 550 tpd of

    bleached pulp. The hardwood pulp mill shall have balancing facilities for a

    production of 330 tpd bleached pulp production. The total finished paper

    production will increase from 245,000 tpa to 400,000 tpa. In conformity

    with the guidelines of Ministry of Environment and Forests (MoEF), TNPL

    has embarked on Environmental Impact Assessment (EIA) for the proposed

    Mill Expansion Plan (MEP).

    SPB Projects and Consultancy Limited (SPB-PC), Chennai, association with

  • 8/14/2019 EIA India TamilNadu

    24/369

  • 8/14/2019 EIA India TamilNadu

    25/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited C2-3

    new units with better quality products apart from the threat of dumping

    from overseas manufacturers, the mill has to find ways and means to meet

    these challenges and for its continued economically viable operation for

    sustenance.

    TNPL proposes to install a new paper machine (PM #3), having an installed

    capacity of 155,000 tpa, for the manufacture of surface sized printing and

    writing and on-machine light-weight coated papers. The proposed paper

    machine will have facilities to produce different grades of coated and

    uncoated papers.

    The objectives of the installation of PM #3 are as follows:

    Add coated paper production capability to meet increasing future

    demands expected for surface-sized printing and writing, copier andon-machine light weight coated papers

    Designate PM #3 for SS printing and writing, copier and on-machine

    light weight coated paper production.

    In the process of achieving the above objection, TNPL will

    Design PM #3 for low water consumption to reduce the overall

    specific fresh water requirement

    Reduce the specific energy consumption with energy-efficient designof PM #3 at the rated production capacity.

    Along with installation of PM #3, it is also proposed to balance the

    backend, viz. chemical bagasse and hardwood pulp mills and the utilities

    section, as described below

    Balancing of chemical bagasse fibre line for achieving a production

    capacity from 500 tpd to 550 tpd

    One (1) continuous digester of capacity 225 BD tpd unbleached

    bagasse pulp

    One (1) brown stock washing street for 600 BD tpd unbleached

    bagasse pulp

    One (1) screening plant, consisting of combined pressure

    knotter and primary screen, secondary, tertiary and quaternary

    screens with cleaning system, for 600 BD tpd unbleached

    bagasse pulp capacity.

  • 8/14/2019 EIA India TamilNadu

    26/369

    EIA Study Tamil Nadu Newsprint and Papers Limited

    C2-4 Prepared by SPB-PC & Vimta Labs Limited

    Balancing of hard wood fibre line for achieving a production capacity

    from 300 tpd to 330 tpd has been planned by upgrading pumps and

    pipe lines, as considered necessary

    Installation of new coal fired boiler of capacity 150 tph to supplementthe additional steam demand.

    Installation of high efficiency electrostatic precipitator for the new

    coal fired boiler.

    Adequate pollution control measures to minimise adverse impacts on

    the environment.

    Improvements in wastewater treatment system with one additional

    secondary clarifier to take care of the ageing of existing secondary

    clarifiers.

    The estimated capital outlay for the proposed MEP is about Rs 725 crores,

    whichwill be spent on plant and machinery including the pollution control

    systems and environmental management.

    2.2.2 Environmental Considerations

    2.2.2.1 Environmentally Friendly Processes

    Adoption of more environmentally friendly processes has been given a highpriority. The project shall ensure improving the performance levels of the

    production units. The aim is to achieve the ultimate target of the

    environmental standards set by MoEF, CPCB and TNPCB.

    The mill is already implementing an expansion plan for compliance to

    CREP. Major process modification involving substantial capital investment is

    being carried out, as per MOEF's Environmental Clearance.

    The proposed expansion plan of the mill shall ensure continued compliance

    with all applicable environmental laws and regulations.

    To minimise the solid waste disposal, the mill as a separate project intends

    to install a cement mill for reusing the fly ash and excess lime sludge, thus

    avoiding the disposal requirements.

    2.2.2.2 Green Belt

    With a view to mitigate the adverse environmental effect on surroundings

    and to provide an environmental cover from emissions, green belts are

    developed in and around the mill.

  • 8/14/2019 EIA India TamilNadu

    27/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited C2-5

    The plantation and green belt development in an industrial area not only

    serves as foreground and background landscape features resulting in

    harmonising and amalgamating the physical structures of a pulp and paper

    mill with the surrounding environment but also acts as a pollutant sink.

    Plantation also contributes towards environmental improvement, by:

    Acting as a pollution sink and preventing the particulate and other

    atmospheric pollutants from spreading to the nearby areas

    Providing vegetative cover

    Increasing the aesthetics of the surroundings, and

    Providing resting, feeding and breeding site for fauna.

    Extensive plantation has been done under green belt development for the

    existing plant. Green belt has been developed and well maintained along

    the internal roads and mill area. The mill has made elaborate arrangement

    in developing green belt inside the mill. Plantation has been developed in

    an area of 66 acres and the total number of trees in this area is 58385 in

    side the mill. Colony area has 55137 trees in an area spread over 98 acres

    for this purpose. Additionally, green belt in an area of 109 acres has been

    developed in the Moolimangalam area and 98100 trees are planted. TNPL

    is committed to greening of dry barren wasteland. Around 300 various

    flowering trees are planted as avenue trees on local roads involving local

    population to create awareness among the public.

    2.2.3 Energy Efficiency

    The steep increase in the administered prices of fuel and power has made

    it absolutely necessary that any fuel and power intensive industrial

    operation shall have to perform at the most energy-efficient levels. Steam

    generation at higher pressure will provide the mill with very attractive

    economics in steam and power generation.

    2.3 Social Development Activities

    On the social and community development front, TNPL has been committed

    to social responsibility in helping farmers and other inhabitants of the

    hamlets in and around the mill. TNPL has spent about Rs 5.73 crores for

    the community development activities including the amount of Rs 50 lakhs

    spent during the year 2007-08.

  • 8/14/2019 EIA India TamilNadu

    28/369

    EIA Study Tamil Nadu Newsprint and Papers Limited

    C2-6 Prepared by SPB-PC & Vimta Labs Limited

    2.4 Project Site

    Adequate land with basic infrastructure is available within the existing plant

    for implementation of the Mill Expansion Plan. The proposed mill expansion

    area is located within the existing plant premises at Pugalur-Kagithapuramin the district of Karur, Tamil Nadu State. The site is located at the

    intersection of longitude 77o4925E and latitude 11o310 N and falls under

    Survey of India Top sheet No 58E/16, F13, I/4 and J/1.

    The site is about 400 km (aerial) from Chennai, the State Capital and it is

    about 15 km from Karur, the District Headquarters. The National Highway

    NH-7, which connects Salem with Karur, is at 3 km in northeast direction

    from the plant site. The index map of the project area is shown in

    Figure 2.1 and the study area map of 10 km radius around TNPL is

    depicted in Figure 2.2.

  • 8/14/2019 EIA India TamilNadu

    29/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited C2-7

    FIGURE 2.1

    INDEX MAP OF THE PROJECT AREA

  • 8/14/2019 EIA India TamilNadu

    30/369

    EIA Study Tamil Nadu Newsprint and Papers Limited

    C2-8 Prepared by SPB-PC & Vimta Labs Limited

    FIGURE 2.2

    STUDY AREA MAP 10 KM RADIUS

  • 8/14/2019 EIA India TamilNadu

    31/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited C2-9

    2.5 Environmental Setting of the Site

    The details of environmental setting around the proposed MEP site are

    given in the following table.

    ENVIRONMENTAL SETTING OF THE SITE

    Sl. No. Particulars Details

    1 Location

    Town/Village Pugalur

    District Karur

    State Tamil Nadu

    2 Latitude 11o3 10 N

    3 Longitude 77o49 25 E

    4 Elevation above mean sea level (MSL) 150m

    5 Climatic conditions as per IMD Salem Predominant Annual Wind Direction :East, Southwest, and West

    Annual mean Max Temp: 33.5oc

    Annual mean Min Temp : 22.6oC

    6 Present land use at the proposed site Industrial

    7 Nearest Highway/Road NH-7 connecting Salem to Karur(3 km NE)

    8 Defence Installations None within 10 km radius

    9 Nearest railway station Pugalur R.S10 Nearest airport/air strip Thiruchirapalli

    11 Nearest village Pugalur

    12 Nearest town Karur

    13 Nearest river Cauvery River

    14 Hills/valleys Some hillocks are present nearby

    15 Archaeologically important places Nil in 10 km radius

    16 Nearest place of tourist/ Religiousimportance

    Kalyana Venkatasami Temple,Thanthonimalai.

    Pasupatheswarar Temple Karur

    17 Ecologically sensitive areas (NationalParks/Wildlife sanctuaries/bio-spherereserves)

    No sensitive areas within 10km radius

    18 Reserved/Protected forests within 10 kmradius

    None within 10km radius

    19 List of Industries EID Parry, some small scaleindustries

    20 Topography of the plant site Plain

    21 Nature of soil Silty

    22 Major crops in the study area Sugarcane, Paddy

  • 8/14/2019 EIA India TamilNadu

    32/369

    EIA Study Tamil Nadu Newsprint and Papers Limited

    C2-10 Prepared by SPB-PC & Vimta Labs Limited

    2.6 Scope of the Present Study

    The study covers the core area of 10 km radius with the proposed project

    site as the centre. The scope of the study broadly includes:

    Literature review to collect data relevant to the study area

    Environmental monitoring so as to establish the baseline

    environmental status of the study area (reference CEIA data from

    September 2004 to September 2005 and January 2008)

    Identification of various existing pollution loads due to industrial and

    domestic activities in the ambient levels

    Prediction of incremental levels of pollutants in the study area due to

    implementation of the proposed expansion using CEIA data.

    Evaluation of the predicted impacts on the various environmental

    attributes in the study area by using scientifically developed and

    widely accepted Environmental Impact Assessment Methodologies

    using CEIA data

    Preparation of an Environmental Management Plan (EMP) outlining

    the measures for improving the environmental quality and

    environmentally sustainable development

    Identification critical environmental attributes required to be

    monitored.

    The literature review includes identification of relevant articles from various

    publications, collection of data from various government agencies and

    other sources.

    2.7 Compliance to Terms of Reference (TOR) issued by MoEF

    The EIA report is prepared in accordance with the additional TOR conditions

    issued by MoEF. The compliance statement to TOR conditions is given in

    following table.

  • 8/14/2019 EIA India TamilNadu

    33/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited C2-11

    TABLE

    COMPLIANCE TO TOR ISSUED BY MOEF FOR PREPARATION OF EIA

    S.

    No.

    Terms of Reference Compliance

    1 One month data for ambient air, stackemissions from all the stacks.

    The ambient air quality of the areaincluding meteorological conditions,stack emission details is monitoredduring January 2008. The details of themonitoring are given in Section-5.4,Chapter-5, Page: C5-23 to C5-29

    2 Existing data on the total waterconsumption, per t of paper producedincluding AOX levels.

    Enclosed as Annex 7

    3 Ground water study should be carriedout where the effluent is discharged.

    The details of groundwater quality in andaround plant premises including theeffluent discharge points is given in

    Section-5.5, Chapter-5, Page: C5-31 toC5-36

    4 A note on the follow up of the CREPguidelines.

    Enclosed as Annex 8

    5 A note on the odour control.

    6 Action Plan for colour removal from theeffluent.

    Enclosed as Annex 8

    7 Point-wise compliance to the stipulated

    environmental conditions for the existing

    plant.

    Enclosed as Appendix 3

    2.8 Methodology of the Study

    Reconnaissance survey was conducted by SPB-PC and Vimta Labs Limited,

    in consultation with the officials of TNPL, and sampling locations were

    identified on the basis of:

    Dispersion modelling exercise using the predominant wind directions

    in the study area as recorded by Indian Meteorological Department

    (IMD)

    Topography, location of surface water bodies like ponds, canals and

    rivers

    Location of villages/towns/sensitive areas

    Accessibility, power availability and security of monitoring equipment,

    pollution pockets in the area

    Areas which represent baseline conditions

  • 8/14/2019 EIA India TamilNadu

    34/369

    EIA Study Tamil Nadu Newsprint and Papers Limited

    C2-12 Prepared by SPB-PC & Vimta Labs Limited

    Collection, collation and analysis of baseline data for various

    environmental attributes.

    The field observations are used to:

    Set up air quality models

    Identify extent of negative impacts on community/natural resources

    Identify mitigation measures and monitoring requirements.

    The study also provides framework and institutional strengthening for

    implementing the mitigation measures. Field studies have been conducted

    during September 2004 to September 2005 and during January 2008 to

    determine variations and also to determine existing conditions of various

    environmental attributes as outlined in the following table.

    ENVIRONMENTAL ATTRIBUTES & FREQUENCY OF MONITORING ADOPTED

    SlNo.

    Attribute Parameters Frequency of Monitoring

    1 Ambient airquality

    SPM, RPM, SO2, NOX, and CO Twice a week during the studyperiod at six locations, 24hourly samples for SPM, RPM,SO2, NOX and 8 hourlysamples for CO.

    2 Meteorology Wind Speed and Direction,Temperature, Rainfall,Atmospheric Pressure, andother non instrumentalobservations like visibility

    Continuous monitoring duringSept 2004 to Sept 05 andJanuary 2008 with hourlyrecording and data collectedfrom secondary sources likeIMD station at Salem

    3 Water quality Physical, Chemical andBacteriological Parameters.

    Sampling once in a monthduring study period

    4 Ecology Existing terrestrial and aquaticflora and fauna

    Through field visits

    5 Noise levels Noise levels in dB (A) Continuous recording for 24hours per location once in eachseason during the study periodat ten locations

    6 Soilcharacteristics

    Soil profile, characteristics, typeof soils in and around the plant

    Soil sampling at ten locationsonce in each season during thestudy period.

  • 8/14/2019 EIA India TamilNadu

    35/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited C2-13

    SlNo.

    Attribute Parameters Frequency of Monitoring

    7 Land use Land use of different categoriesaround the plant site

    Based on data published indistrict census handbooks anddata collected from othersources such as Districtinformation Centre

    8 Socio-economicaspects

    Socio-economic characteristics,labour force characteristics,trend since inception ofindustrialisation

    -do-

    9 Geology Geological history Based on data collected fromsecondary sources

    10 Hydrology(Surface andGround)

    Drainage area and pattern,nature of streams, aquifercharacteristics

    -do-

    11 Riskassessment

    Identify areas where disastercan occur by fires, explosionsand release of toxic substances

    Risk assessment throughModelling

    2.9 Environmental Impact Assessment (EIA) Report

    2.9.1 Format of the Report

    The proposed MEP would naturally have implications on the neighbourhood

    with reference to environmental attributes such as land, water, air,

    aesthetics, flora and fauna. In assessing the environmental impact,

    collection, collation and interpretation of baseline data are of prime

    importance. Environmental impact analysis and assessment, which are

    required for every industrial project, should preferably be carried out at the

    planning stage itself, well before the implementation of the MEP, and hence

    this study.

    The basic objective of identification of impacts is to aid the proponents of

    the project to rationalise the procedure for an effective environmental

    management plan by adopting the following procedures:

    Collection, collation and analysis of baseline data for various

    environmental attributes

    Identification of impacts

    Impact assessment through modelling

    Evaluation of impacts leading to preparation of environmental

    management plan

  • 8/14/2019 EIA India TamilNadu

    36/369

    EIA Study Tamil Nadu Newsprint and Papers Limited

    C2-14 Prepared by SPB-PC & Vimta Labs Limited

    Outlining post project monitoring methodology.

    2.9.2 Contents of the EIA Report

    This EIA Report is based on field data generated at site during the studyperiod [September 2004 to September 2005 and January 2008] and data

    collected from secondary sources. The report has been divided into 12

    chapters and presented as follows:

    Chapter 1 Executive Summary

    Chapter 2 Background

    This chapter provides a general scenario of the Industry, background

    information of the project, brief description and objectives of the project,

    description of the area, scope and organisation of the study. It also

    provides information on climate and environment in the region.

    Chapter 3 Legal and Administrative Framework

    This chapter deals with

    The guidelines on EIA issued by Ministry of Environment & Forests

    Indian laws

    Acts and regulations on the environment for

    Air

    Water

    Workers

    Health and safety

    Hazardous materials handling

    Regulations, standards and conditions laid down by the Tamil Nadu

    Pollution Control Board.

    Chapter 4 Project Details and Sources of Pollution

    This chapter deals with the process technology and details of the project.

    This also deals with the sources of pollution from the proposed plant and

    required control measures.

  • 8/14/2019 EIA India TamilNadu

    37/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited C2-15

    Chapter 5 Baseline Environmental Status

    This chapter presents the methodology and findings of field studies

    undertaken with respect to ambient air, water, soil, noise levels and

    ecology to define the various existing environmental status in the area. Italso presents the meteorological conditions, which govern the air quality

    impacts, a major concern during the operation of the pulp and paper mill.

    Details are included on land use, socio-economics, geology, and hydrology

    from published secondary data.

    Chapter 6 Impact Assessment

    This chapter details the inferences drawn from the environmental impact

    assessment of the project during construction and operational phase. It

    describes the overall impacts of the proposed project and underscores theareas, which may require implementation of some mitigation measures in

    the event of the applicable environmental standards not being met.

    Chapter 7 Environmental Management Plan (EMP) Including Mitigation

    Measures

    This chapter proposes an environmental management plan aimed at

    environmental impacts of the project. Environmental monitoring

    requirements for effective implementation of mitigatory measures during

    construction as well as operation of the project have also been delineated

    along with requisite institutional arrangements for their implementation.

    This chapter also deals with possible hazards and hazard identification and

    risk analysis from the proposed MEP.

    Chapter 8 Monitoring Programme

    This chapter deals with monitoring programmes for wastewater, ground

    water, surface water, air quality and noise levels.

    Chapter 9 Environmental Management and Training

    This chapter details recommended environmental management and training

    procedures.

  • 8/14/2019 EIA India TamilNadu

    38/369

    EIA Study Tamil Nadu Newsprint and Papers Limited

    C2-16 Prepared by SPB-PC & Vimta Labs Limited

    Chapter 10 Risk Assessment and Disaster Management Plan

    This chapter deals with possible hazards and hazard identification and risk

    analysis from the proposed MEP. Based on these, the risk assessment and

    disaster management plan, including on-site and off-site management, hasbeen prepared.

    Chapter 11 Sources of Data and Information

    This chapter provides the details about the sources of data, field data

    collection programmes, and public participation.

    Chapter 12 References

    Annex #

    1 Ambient Air Quality Levels Winter 2008

    2 Ground Water and Surface Water Quality

    3 Soil Quality for Treated Wastewater Irrigated Area

    4 Ecological Details

    5 Village-wise Landuse Pattern

    6 Demographical Details

    7 Existing data on the total water consumption with AOX levels

    8 Note on the follow up of the CREP Guidelines with Odour Control

    9 Schematic flow diagram of wastewater treatment plant after MEP

    Appendix #

    1 MoEF Notification 2006

    2 Mill layout

    3 Point-wise compliance details of conditions stipulated in

    Environmental Clearance accorded by MOEF

  • 8/14/2019 EIA India TamilNadu

    39/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited C2-1

    2 BACKGROUND

    Tamil Nadu Newsprint and Papers Limited (TNPL) was promoted by the

    Government of Tamil Nadu for the manufacture of newsprint and printing

    and writing (P&W) papers, using bagasse as the principal fibre source.About 20% of its P&W paper production is exported. Over the years, the

    mill has been improving its environmental performance by adopting various

    measures. Apart from its sound technical and financial performance, TNPL

    has always strived to attain best possible standards of quality, by

    practising ISO 9001:2000 standards in the manufacturing operations. The

    mill operations are environment friendly and conform to pollution

    abatement norms that are superior to the state and national standards.

    The mill has established an Environment Management System (EMS)

    complying with ISO 14001 standards. As a testimony of TNPLs

    commitment to the protection of the environment, World Wide Fund for

    Nature India has accorded permission to TNPL to use it Panda logo in

    TNPLs branded products. TNPLs environmental compliance has been

    acknowledged by the Centre for Science and Environment (CSE) by

    awarding the THREE GREEN LEAVES under GREEN RATING PROJECT.

    The award of Excellence in Corporate Governance to TNPL stands as ample

    testimony to the overall operational efficiencies, transparency in mill

    functioning and social commitment of the mill. TNPL has been granted

    `Eco label licence for the plain copier paper as per IS 14490-97 by Bureau

    of Indian Standards.

    The mill is implementing a comprehensive Mill Development Plan (MDP) to

    meet the requirements of the Ministry of Environment and Forests (MoEF)

    as part of the mills compliance to the Charter on Corporate Responsibility

    for Environmental Protection (CREP) as applicable to pulp and paper

    industries. The ongoing expansion is to achieve the target set by the

    CREP.

    Under the ongoing MDP, TNPL has installed 300 tpd Elemental Chlorine

    Free (ECF) chemical hardwood pulp line and a 500 tpd Elemental Chlorine

    Free (ECF) chemical bagasse bleach plant to replace the existing chlorine

    based bleach plants.

    However, to be a leading player in the Indian Pulp and Paper Industry, the

    mill intends to install a new paper machine of capacity 155,000 tpa along

    with the balancing of bagasse pulp mill for a capacity of 550 tpd of

    bleached pulp. The hardwood pulp mill shall have balancing facilities for a

    production of 330 tpd bleached pulp production. The total finished paper

    production will increase from 245,000 tpa to 400,000 tpa. In conformity

    with the guidelines of Ministry of Environment and Forests (MoEF), TNPL

    has embarked on Environmental Impact Assessment (EIA) for the proposed

    Mill Expansion Plan (MEP).

    SPB Projects and Consultancy Limited (SPB-PC), Chennai, association with

  • 8/14/2019 EIA India TamilNadu

    40/369

    EIA Study Tamil Nadu Newsprint and Papers Limited

    C2-2 Prepared by SPB-PC & Vimta Labs Limited

    Vimta Labs, Hyderabad, has been retained to undertake in, a study of the

    Environmental Impact Assessment (EIA) and prepare an Environmental

    Management Plan for various environmental components which may be

    affected due to the impacts arising out of the proposed MEP.

    2.1 Project Promoters

    The Tamil Nadu Newsprint and Papers Limited (TNPL) have its

    manufacturing facilities at Kagithapuram, near Pugalur of Karur Taluk,

    Karur District, Tamil Nadu State. Its Corporate Office is located at Chennai.

    TNPL proposes to modernise and expand the operations of the unit located

    at Kagithapuram with a view to improve technology, energy efficiency,

    marketability, and long-term environmental compliance. TNPL has

    ISO 9001-2000 and ISO 14001-2004 certification.

    From the inception, TNPL has always been a responsible player in the

    paper industry, by

    Adopting environment-friendly processes as far as practicable

    Being quality conscious - in products, processes, service & people

    Continuously enhancing the value for all stakeholders, and

    Upholding societal values and expectations.

    The driving force for the Mill Expansion Plan (MEP) is a combination of

    quest for improved environmental performance and sustained mill

    operations with improved productivity.

    2.2 Need for MEP

    2.2.1 Project Rationale

    The objectives of the proposed expansion are

    To maintain the status of leading player in Indian Pulp and Paper

    Industry by achieving 1000 tpd paper production at a single location.

    To adopt energy efficient process and plant & machinery.

    To meet the growing demand for paper in the country.

    To facilitate the manufacture of more grades of environmentally

    friendly paper/products.

    With steady increase in input costs and a continuous competition from the

  • 8/14/2019 EIA India TamilNadu

    41/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited C2-3

    new units with better quality products apart from the threat of dumping

    from overseas manufacturers, the mill has to find ways and means to meet

    these challenges and for its continued economically viable operation for

    sustenance.

    TNPL proposes to install a new paper machine (PM #3), having an installed

    capacity of 155,000 tpa, for the manufacture of surface sized printing and

    writing and on-machine light-weight coated papers. The proposed paper

    machine will have facilities to produce different grades of coated and

    uncoated papers.

    The objectives of the installation of PM #3 are as follows:

    Add coated paper production capability to meet increasing future

    demands expected for surface-sized printing and writing, copier andon-machine light weight coated papers

    Designate PM #3 for SS printing and writing, copier and on-machine

    light weight coated paper production.

    In the process of achieving the above objection, TNPL will

    Design PM #3 for low water consumption to reduce the overall

    specific fresh water requirement

    Reduce the specific energy consumption with energy-efficient designof PM #3 at the rated production capacity.

    Along with installation of PM #3, it is also proposed to balance the

    backend, viz. chemical bagasse and hardwood pulp mills and the utilities

    section, as described below

    Balancing of chemical bagasse fibre line for achieving a production

    capacity from 500 tpd to 550 tpd

    One (1) continuous digester of capacity 225 BD tpd unbleached

    bagasse pulp

    One (1) brown stock washing street for 600 BD tpd unbleached

    bagasse pulp

    One (1) screening plant, consisting of combined pressure

    knotter and primary screen, secondary, tertiary and quaternary

    screens with cleaning system, for 600 BD tpd unbleached

    bagasse pulp capacity.

  • 8/14/2019 EIA India TamilNadu

    42/369

    EIA Study Tamil Nadu Newsprint and Papers Limited

    C2-4 Prepared by SPB-PC & Vimta Labs Limited

    Balancing of hard wood fibre line for achieving a production capacity

    from 300 tpd to 330 tpd has been planned by upgrading pumps and

    pipe lines, as considered necessary

    Installation of new coal fired boiler of capacity 150 tph to supplementthe additional steam demand.

    Installation of high efficiency electrostatic precipitator for the new

    coal fired boiler.

    Adequate pollution control measures to minimise adverse impacts on

    the environment.

    Improvements in wastewater treatment system with one additional

    secondary clarifier to take care of the ageing of existing secondary

    clarifiers.

    The estimated capital outlay for the proposed MEP is about Rs 725 crores,

    whichwill be spent on plant and machinery including the pollution control

    systems and environmental management.

    2.2.2 Environmental Considerations

    2.2.2.1 Environmentally Friendly Processes

    Adoption of more environmentally friendly processes has been given a highpriority. The project shall ensure improving the performance levels of the

    production units. The aim is to achieve the ultimate target of the

    environmental standards set by MoEF, CPCB and TNPCB.

    The mill is already implementing an expansion plan for compliance to

    CREP. Major process modification involving substantial capital investment is

    being carried out, as per MOEF's Environmental Clearance.

    The proposed expansion plan of the mill shall ensure continued compliance

    with all applicable environmental laws and regulations.

    To minimise the solid waste disposal, the mill as a separate project intends

    to install a cement mill for reusing the fly ash and excess lime sludge, thus

    avoiding the disposal requirements.

    2.2.2.2 Green Belt

    With a view to mitigate the adverse environmental effect on surroundings

    and to provide an environmental cover from emissions, green belts are

    developed in and around the mill.

  • 8/14/2019 EIA India TamilNadu

    43/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited C2-5

    The plantation and green belt development in an industrial area not only

    serves as foreground and background landscape features resulting in

    harmonising and amalgamating the physical structures of a pulp and paper

    mill with the surrounding environment but also acts as a pollutant sink.

    Plantation also contributes towards environmental improvement, by:

    Acting as a pollution sink and preventing the particulate and other

    atmospheric pollutants from spreading to the nearby areas

    Providing vegetative cover

    Increasing the aesthetics of the surroundings, and

    Providing resting, feeding and breeding site for fauna.

    Extensive plantation has been done under green belt development for the

    existing plant. Green belt has been developed and well maintained along

    the internal roads and mill area. The mill has made elaborate arrangement

    in developing green belt inside the mill. Plantation has been developed in

    an area of 66 acres and the total number of trees in this area is 58385 in

    side the mill. Colony area has 55137 trees in an area spread over 98 acres

    for this purpose. Additionally, green belt in an area of 109 acres has been

    developed in the Moolimangalam area and 98100 trees are planted. TNPL

    is committed to greening of dry barren wasteland. Around 300 various

    flowering trees are planted as avenue trees on local roads involving local

    population to create awareness among the public.

    2.2.3 Energy Efficiency

    The steep increase in the administered prices of fuel and power has made

    it absolutely necessary that any fuel and power intensive industrial

    operation shall have to perform at the most energy-efficient levels. Steam

    generation at higher pressure will provide the mill with very attractive

    economics in steam and power generation.

    2.3 Social Development Activities

    On the social and community development front, TNPL has been committed

    to social responsibility in helping farmers and other inhabitants of the

    hamlets in and around the mill. TNPL has spent about Rs 5.73 crores for

    the community development activities including the amount of Rs 50 lakhs

    spent during the year 2007-08.

  • 8/14/2019 EIA India TamilNadu

    44/369

    EIA Study Tamil Nadu Newsprint and Papers Limited

    C2-6 Prepared by SPB-PC & Vimta Labs Limited

    2.4 Project Site

    Adequate land with basic infrastructure is available within the existing plant

    for implementation of the Mill Expansion Plan. The proposed mill expansion

    area is located within the existing plant premises at Pugalur-Kagithapuramin the district of Karur, Tamil Nadu State. The site is located at the

    intersection of longitude 77o4925E and latitude 11o310 N and falls under

    Survey of India Top sheet No 58E/16, F13, I/4 and J/1.

    The site is about 400 km (aerial) from Chennai, the State Capital and it is

    about 15 km from Karur, the District Headquarters. The National Highway

    NH-7, which connects Salem with Karur, is at 3 km in northeast direction

    from the plant site. The index map of the project area is shown in

    Figure 2.1 and the study area map of 10 km radius around TNPL is

    depicted in Figure 2.2.

  • 8/14/2019 EIA India TamilNadu

    45/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited C2-7

    FIGURE 2.1

    INDEX MAP OF THE PROJECT AREA

  • 8/14/2019 EIA India TamilNadu

    46/369

    EIA Study Tamil Nadu Newsprint and Papers Limited

    C2-8 Prepared by SPB-PC & Vimta Labs Limited

    FIGURE 2.2

    STUDY AREA MAP 10 KM RADIUS

  • 8/14/2019 EIA India TamilNadu

    47/369

    Tamil Nadu Newsprint and Papers Limited EIA Study

    Prepared by SPB-PC & Vimta Labs Limited C2-9

    2.5 Environmental Setting of the Site

    The details of environmental setting around the proposed MEP site are

    given in the following table.

    ENVIRONMENTAL SETTING OF THE SITE

    Sl. No. Particulars Details

    1 Location

    Town/Village Pugalur

    District Karur

    State Tamil Nadu

    2 Latitude 11o3 10 N

    3 Longitude 77o49 25 E

    4 Elevation above mean sea level (MSL) 150m

    5 Climatic conditions as per IMD Salem Predominant Annual Wind Direction :East, Southwest, and West

    Annual mean Max Temp: 33.5oc

    Annual mean Min Temp : 22.6oC

    6 Present land use at the proposed site Industrial

    7 Nearest Highway/Road NH-7 connecting Salem to Karur(3 km NE)

    8 Defence Installations None within 10 km radius

    9 Nearest railway station Pugalur R.S10 Nearest airport/air strip Thiruchirapalli

    11 Nearest village Pugalur

    12 Nearest town Karur

    13 Nearest river Cauvery River

    14 Hills/valleys Some hillocks are present nearby

    15 Archaeologically important places Nil in 10 km radius

    16 Nearest place of tourist/ Religiousimportance

    Kalyana Venkatasami Temple,Thanthonimalai.

    Pasupatheswarar Temple Karur

    17 Ecologically sensitive areas (NationalParks/Wildlife sanctuaries/bio-spherereserves)

    No sensitive areas within 10km radius

    18 Reserved/Protected forests within 10 kmradius

    None within 10km radius

    19 List of Industries EID Parry, some small scaleindustries

    20 Topography of the plant site Plain

    21 Nature of soil Silty

    22 Major crops in the study area Sugarcane, Paddy

  • 8/14/2019 EIA India TamilNadu

    48/369

    EIA Study Tamil Nadu Newsprint and Papers Limited

    C2-10 Prepared by SPB-PC & Vimta Labs Limited

    2.6 Scope of the Present Study

    The study covers the core area of 10 km radius with the proposed project

    site as the centre. The scope of the study broadly includes:

    Literature review to collect data relevant to the study area

    Environmental monitoring so as to establish the baseline

    environmental status of the study area (reference CEIA data from

    September 2004 to September 2005 and January 2008)

    Identification of various existing pollution loa