Eia coal convying at PIBT Port Qasim by NESPAK
-
Upload
zubeditufail -
Category
Environment
-
view
92 -
download
15
Transcript of Eia coal convying at PIBT Port Qasim by NESPAK
NATIONAL ENGINEERING SERVICES PAKISTAN (PVT.) LIMITEDConsulting Engineers
Draft
13th Floor, N.I.C.L Building, Abbasi Shaheed Road, Off: Shahra-e-Faisal, KARACHI-74400, Ph. No.+92-21-99090000, +92-21-99225277-84 Fax No. +92-21-35651994, +92-21-99225366, E-mail: [email protected] & [email protected] Website: www.nespak.com.pk
Table of Contents EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ToC - i July, 2016
Table of Contents
Description Page
Executive Summary
1.0 Introduction
1.1 Project Background …………………………………………………………………… 1-1
1.2 Scope of Study ………………………………………………………………………… 1-2
1.3 Study Objectives ………………………………………………………………............ 1-2
1.4 Need of EIA Study for the Proposed Project ……………………………………….. 1-3
1.5 The Proponent and Consultant ………………………………………………………. 1-4
1.6 Study Team ……………………………………………………………………………. 1-4
1.7 Study Approach & Methodology …………………………………………………….. 1-5
1.7.1 Study Approach ……………………………………………………………… 1-5
1.7.2 Methodology …………………………………………………………………. 1-5
1.8 Extent of the Study …………………………………………………………………… 1-8
1.9 Structure of the Report ………………………………………………………………. 1-9
2.0 Policy, Legal and Administrative Frameworks
2.0 General................................................................................................ 2-1
2.1 Legal Framework................................................................................................ 2-1
2.1.1 Pakistan Environmental Protection Agency Review of IEE/EIA
Regulations,2000............................................................................................... 2-1
2.1.2 Pakistan Environmental Assessment Procedure 1997......................... 2-1
2.1.3 Sindh Environmental Protection Act,2014............................................... 2-2
2.1.4 Sindh EPA Review of IEE/EIA Regulations,2014................................... 2-2
2.2 Sindh Environmental Quality Standards (SEQS), 2016.................................... 2-3
2.2.1 Air Quality Standards............................................................................ 2-4
2.2.2 Noise Quality Standards....................................................................... 2-4
2.2.3 Drinking Water and Wastewater Quality Standards............................. 2-5
2.3 Other Relevant Laws………………………………………...................................... 2-7
2.4 Policy Framework................................................................................................ 2-12
2.4.1 National Environment Policy, 2005........................................................ 2-12
2.4.2 National Resettlement Policy, 2002....................................................... 2-12
2.4.3 National Power Policy, 2013.................................................................. 2-12
2.5 Administrative Framework.................................................................................. 2-13
2.5.1 Port Qasim Authority GoP…………………………….…………………… 2-13
2.5.2 Environmental Protection Agency, Sindh..................................... 2-13
Table of Contents EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ToC - ii July, 2016
3.0 Description of the Project
3.1 Rationale of the Project ……………………………………………………………. 3-1
3.2 Coal Handling Facilities at Port Qasim ……………………………………………. 3-2
3.3 Transport of Coal from PIBT to Coal Fired Power Plants ……………………….. 3-3
3.4 Coal conveying System from PIBT to Existing Railway network ………………. 3-5
3.5 Site Selection for coal Conveyor from PIBT to New Stockyard ………………… 3-9
3.6 Route Selection for coal Conveyor from PIBT to New Stockyard ……………… 3-12
3.7 Location of the Project …………………………………………............................. 3-14
3.8 Project Administrative Jurisdiction ………………………………………………… 3-15
3.9 Project Implementation Schedule………………………….................................. 3-15
3.10 Cost of the Project………………………............................................................ 3-15
3.11 Financing of the Project……………………….................................................... 3-15
3.12 Construction Materials ………………………………………………………………… 3-15
3.13 Construction Camps …………………………………………………………………… 3-15
3.14 Manpower Requirements ……………………………………………………………… 3-15
3.15 Construction Equipment ……………………………………………………………….. 3-16
4.0 Environmental Baseline Profile
4.1 Physical Environment ………………………………………………………………….. 4-1
4.1.1 Topography and Geography ………………………………………………… 4-1
4.1.2 Geology and Soil ……………………………………………………………… 4-1
4.1.3 Climate and Meteorology……………………………………………………… 4-2
4.1.4 Seismicity ……………………………………………………………………… 4-7
4.1.5 Water Resources and Drainage……………………………………………... 4-8
4.1.6 Creek system Hydraulics…….. ……………………………………………… 4-10
4.1.7 Ambient Air Quality …………………………………………………………... 4-10
4.1.8 Air dispersion Modeling of Particulate Matter……………………………… 4-12
4.1.9 Noise Level ……………………………………………………………………. 4-12
4.1.10 Drinking Water Quality…………………………………………………………. 4-13
4.2 Ecological Resources …………………………………………………………………. 4-17
4.2.1 Flora ……………………………………………………………………........... 4-17
4.2.2 Fauna …………………………………………………………………………. 4-19
4.2.3 Wet Lands ……………………………………………………………………. 4-19
4.2.4 Endangered Species………………………………………………………… 4-20
4.2.5 Wild life Sanctuaries and Game reserves……………………………....... 4-20
4.2.6 Critical Habitats……………………………………………………………… 4-20
4.3 Social Economic Structure……………………………………………………………. 4-20
4.3.1 Malir District ………………………………………………………………….. 4-20
Table of Contents EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ToC - iii July, 2016
4.3.2 Study Area …………………………………………………………………… 4-21
4.3.3 Political and administrative Setup ………………..………………………… 4-21
4.3.4 Data Source/Methodology …………………………………………………… 4-22
4.3.5 Characteristics of the Project Area…………………………………………. 4-22
4.4 Economic Conditions…………………………………………………………………. 4-26
4.5 Transportations………………………………………………………………………… 4-28
4.6 Health facilities………………………………………………………………………… 4-29
4.7 Educations…………………………………………………………………………….. 4-30
4.8 Socioeconomic Baseline Survey……………………………………………………. 4-32
4.8.1 Field Survey …………………………………………………………………. 4-32
4.8.2 Survey Results ……………………………………………………………… 4-33
5.0 Public Consultation
5.0 General…………………………………………………………………………………. 5-1
5.1 Consultation and Participation Process ……………………………………………. 5-1
5.2 Methods of Public Consultation........................................................................... 5-2
5.3 Identification of Stakeholders............................................................................... 5-2
5.4 Categories of Stakeholders Contacted................................................................ 5-2
5.5 Major Stakeholders and their Apprehensions...................................................... 5-3
5.6 Consultation Meetings and Formal and Informal Group Discussions................... 5-5
5.7 Concerns / Suggestions of the Stakeholders........................................................ 5-7
5.8 Mitigation Measures proposed by EIA Consultants for Addressing the
Stakeholder’s Concerns.................................................................................... 5-8
5.9 Details of Meetings with the Stakeholders................................................... 5-9
6.0 Anticipated Environmental Impacts and Mitigation Measures
6.0 General……………………………………………………………………………….. 6-1
6.1 Environmental Impact Matrix ............................................................................ 6-1
6.2 Anticipated Impacts during Pre-Construction/Design Phase....................... 6-4
6.2.1 Design and Layout Planning................................................................... 6-4
6.2.2 Topography.& Geology.............................................................................. 6-4
6.2.3 Land Acquisition and Resettlement........................................................ 6-4
6.2.4 Transportation and access.......................................................................... 6-5
6.2.5 Ecological Impacts.................................................................................. 6-5
6.2.6 Flora.................................................................................................... 6-5
6.2.7 Fauna.................................................................................................... 6-6
6.2.8 Marine Fauna and Flora............................................................................. 6-6
6.2.9 Air Quality and Noise.............................................................................. 6-7
6.2.10 Public Utilities......................................................................................... 6-7
6.2.11 Archaeological and Heritage sites............................................................. 6-7
Table of Contents EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ToC - iv July, 2016
6.2.12 Impact on Traffic..................................................................................... 6-8
6.2.13 Seismic Hazard...................................................................................... 6-8
6.3 Anticipated Impacts during Construction Phase........................................... 6-9
6.3.1 Soil.......................................................................................................... 6-9
6.3.2 Construction Camps/Camp Sites........................................................... 6-10
6.3.3 Health and Safety................................................................................... 6-13
6.3.4 Air Quality............................................................................................... 6-16
6.3.5 Noise& Vibrations................................................................................... 6-18
6.3.6 Waste (Construction Waste and Hazardous Waste) ...................... 6-20
6.3.7 Surface and Groundwater ...................................................................... 6-21
6.3.8 Biodiversity Conservation and Natural Resources.................................. 6-22
6.3.9 Disposal of Mucking Material.................................................................. 6-23
6.3.10 Disruption of Existing Public Utilities/ Infrastructure ............................... 6-23
6.3.11 Traffic Management................................................................................. 6-24
6.3.12 Economic Activity.................................................................................... 6-24
6.3.13 Lifestyle and Culture ............................................................................... 6-25
6.3.14 Impacts and Sensitive Receptors.......................................................... 6-25
6.3.15 Impacts of heavy vehicles on the existing road Network...................... 6-26
6.3.16 Physical and Cultural Resources............................................................... 6-26
6.3.17 Storage of fuel on Site............................................................... 6-26
6.4 Anticipated Impacts during Operational Phase .............................................. 6-27
6.4.1 Ecology.................................................................................................... 6-27
6.4.2 Wastewater collection and Treatment at Depot...................................... 6-28
6.4.3 Coal Dust................................................................................................ 6-28
6.4.4 Noise....................................................................................................... 6-32
6.4.5 Solid Waste............................................................................................. 6-32
6.4.6 Socioeconomic....................................................................................... 6-33
6.4.7 Improvement of Infrastructure Facilities...................................... 6-33
6.4.8 Wider Economic Growth........................................................................ 6-33
6.4.9 Better Rail Transportation................................................................ 6-33
6.4.10 Reduced Health Risk and Accidental Hazards................................... 6-33
6.4.11 Fire Hazards..................................................................... 6-34
6.4.11 Emergency Management..................................................................... 6-34
7.0 Environmental Monitoring and Management Plan
7.1 Environmental Management................................................................................. 7-1
7.2 Worker’s Health and Safety................................................................................. 7-2
7.3 Anticipated Impacts During Construction Phase................................................ 7-3
7.4 Environmental Monitoring .................................................................................... 7-15
7.4.1 Construction Phase................................................................................ 7-15
Table of Contents EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ToC - v July, 2016
7.4.2 Operational Phase .................................................................................. 7-16
7.4.3 Responsibilities for Monitoring and Reporting ........................................ 7-17
7.5 Plantation ............................................................................................................. 7-19
7.6 Environmental Technical Assistance and Training Plan....................................... 7-19
7.7 Environmental Monitoring, Mitigation and Training Cost ..................................... 7-20
8.0 Conclusion and Recommendations
Annexure
Annexure-I Sind Environmental Quality Standards SEQS
Annexure-II Environmental Monitoring Results
Annexure-III Noise Modelling & Methodology
Annexure-IV Air dispersion Modeling of Particulate Matter
Annexure-V Emergency Response Plan
Annexure-VI Tree Plantation Plan
Annexure-VI Attendance Sheet of Scoping Meeting
Table of Contents EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ToC - vi July, 2016
Table
List of Tables
Description
2.1 Ambient Air Quality Standards
2.2 Drinking Water and Wastewater Quality Standards
2.3 SEQS for Drinking Water Quality
2.4 SEQS for municipal &Liquid Industrial Effluents (mg/l)
3.1 Machinery and Equipment Requirement for the Proposed Project
4.1 Meteorological Data (24-hr.) at NWIZ Water Pumping Station PQA
4.2 Meteorological Data (24-hr.) at Pharm Evo, PQA
4.3 Meteorological Data (24-hr.) at PIBT
4.4 Tide Levels at Port Qasim
4.5 Ambient Air Quality Test Results
4.6 Average values of noise levels
4.7 Groundwater Analysis of the Project Area
4.8 Area and Production Average Yield of Crops 1997-1998
4.9 Tree Species of the Project Area
4.10 Population and Intercensal Increase and Growth Rates since 1951
4.11 Percentage of Population by Religion
4.12 Percentage of Population by Mother Tongue and Rural/Urban Areas, 1998.
4.13 Life Time Migrants in the District by Rural/ Urban Areas, 1998
4.14 Percentage (%) of Population by Economic Categories, Gender and Rural/Urban
Areas, 1998
4.15 Number of Schools and Enrollment of Students, 1997-98
4.16 Literacy Ratios by Sex and Rural/Urban Areas, 1981 & 1998
4.17 Gender Ratio of the Respondents
4.18 Age Composition of the Respondents
4.19 Marital Status of the Respondents
4.20 Caste / Ethnic of the Respondents
4.21 Mother Tongue of the Respondents
4.22 Qualification of the Respondents
4.23 Professional Status of the Respondents
4.24 Average Monthly Income of the Respondents
4.25 Average Monthly Expenditures of the Respondents
4.26 Family System of the Respondents
4.27 Average Household Size of Respondents
Table of Contents EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ToC - vii July, 2016
4.28 Ownership Status of the Houses
4.29 Nature of Construction of Houses
4.30 Availability of Utilities
4.31 Source of Water for Domestic Use
4.32 Satisfaction Level with Water Quality
4.33 Satisfaction Level with Industrial Development
4.34 Impact of Proposed Project on Employment of Workers
4.35 Nature of Impact of Project on Employment of Workers
4.36 Location of Proposed Project in High Population Density
4.37 Acquisition of Private Land
4.38 Awareness about the Proposed Project
4.39 Implementation of the Proposed Project
4.40 Perceived Impacts (During construction)
4.41 Perceived Impacts (after Construction)
4.42 Protective Measures
4.43 Pressing Needs of the Project Area
5.1 Stakeholders Contacted in the Project Area
5.2 Major Stakeholders and their Apprehensions in the Project Area
5.3 Schedule of Meetings with Stakeholders and their Concerns / Apprehensions
6.1 Environmental Impact Matrix for the Construction Phase
6.2 Environmental Impact Matrix for the Operational Phase
6.3 Summary of Impact of Work Camp & Mitigation Measures
6.4 Maximum Limits of Noise Levels
6.5 Damage Risk Criteria for Hearing Loss
6.6 List of industries located on the either side of the Conveyor Belt
7.1 Environmental Management Plan
7.2 Budget Estimate for Environmental Monitoring During the Construction and Operation
Phases
7.3 Personnel Training Program/ Technical Assistance Services
7.4 Environmental Mitigation and monitoring Cost
7.5 Break-up for Health Safety & Environment cost
List of Figure
Figure Description
1.1 Study Area of the Proposed Project
3.1 Existing Coal handling Facility at Port Qasim
3.2 Material flow Diagram
Table of Contents EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ToC - viii July, 2016
3.3 Coal Stalk Yard near Railway Track/Sliding
3.4 Combine Stacker Reclaimer
3.5 Load out Station
3.6 Schematic Layout Plan
3.7 Convey System for Coal Stockyard to load out Station
3.8 Potential Sites for Coal Stockyard
3.9 Routes for Coal Conveying System
3.10 Location of the Project
4.1 Wind rose at NWIZ Water Pumping Station PQA
4.2 Wind rose at PharmEvo, PQA
4.3 Wind rose at PIBT
4.4 Seismic zoning map of Pakistan
4.5 Present Water Supply Zones of Karachi
4.6 Ambient Air Quality Monitoring in the Project Area
4.7 noise level measurement at the project site.
4.8 A General View of Water Sampling
4.9 Floral species present in the project area
4.10 The Map of Malir District
4.11 A view of Karachi International Airport
4.12 A view of Karachi Bin Qasim Port
4.13 A view of Malir City
4.14 A view of Pakistan Steel Mills
4.15 Age Composition of the Respondents
4.16 Marital Status of the Respondents
4.17 Caste/Ethnic Group of the Respondents
4.18 Mother Tongue of the Respondents
4.19 Qualification of the Respondents
4.20 Professional Status of the Respondents
4.21 Average Monthly Income of Respondents
4.22 Average Monthly Expenditures of Respondents
4.22 Family System of the Respondents
4.23 Average Household Size of Respondents
4.24 Ownership Status of the Houses
4.25 Nature of Construction of House
4.26 Availability of utilities for Respondents
4.27 Source of Water for Domestic Use
4.28 Satisfaction Level with Water Quality
Table of Contents EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ToC - ix July, 2016
4.29 Satisfaction Level with existing with Industrial Development
4.30 Impact of Proposed Project on Employment of Workers
4.31 Nature of the impacts proposed by the Respondents
4.32 Location of Proposed Project
4.33 Acquisition of Private Land
4.34 Awareness about the Proposed Project
4.35 Implementation of Proposed Project
4.36 Impacts Perceived by Respondents
4.37 Impacts Perceived by Respondents
4.38 Protective Measures Suggested by Respondents
4.39 Pressing Needs of the Project Area
5.1 Interviews and group discussions with stakeholders
Acronyms EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK 1 July, 2016
ACRONYMS
AASHTO : American Association of State Highway and Transportation Officials
BOD : Bio-chemical Oxygen Demand
BDL : Below Detection Limit
BWSR : Combine Bucket with Stake Reclaimer OC : Degree Centigrade
CCS : Coal Conveying System
CC : Construction Contractor
CO : Carbon Monoxide COD : Chemical Oxygen Demand
dBA : Decibel
DC : Design Consultant DNL : Day-night level EC : Environmental Committee
EIA : Environmental Impact Assessment EMMP : Environmental Monitoring & Management Plan
EMT : Emergency Response Group
EPA : Environmental Protection Agency
EPD : Environmental Protection Department
ERP : Emergency Response Plans
FGDs : Focused Group Discussions
GoP : Government of Pakistan
GoS : Government of Sindh
HSE : Health Safety and Environment
Km : Kilometer
KW&SB : Karachi Water & Sewage Board KESC : Karachi Electric Supply Corporation KMC : Karachi Metropolitan Corporation MGD : Million Gallons per Day
mg/L : Milligram per Liter
MSL : Mean Sea Level
NWIZ : North West Industrial Zone NCS : National Conservation Strategy NEQS : National Environmental Quality Standards
NEP : National Environmental Policy
NESPAK : National Engineering Services Pakistan (Pvt.) Limited NGO : Non-Government Organization NOC : No Objection Certificate
Acronyms EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK 2 July, 2016
NRP : National Resettlement Policy
ND : Not Defined
PEPA : Pakistan Environmental Protection Agency
PNCS : Pakistan National Conservation Strategy PM : Particulate Matter PPC : Pakistan Penal Code PHED : Public Health Engineering Department
PMU : Project Management Unit ppm : Parts per million
PIBT : Pakistan International Bulk Terminal PQA : Port Qasim Authority RAP : Resettlement Action Plan
ROW : Right of Way
RP : Resettlement Plan
SEPA : Sindh Environmental Protection Agency
SEL : SUPARCO Environmental Lab
SPT : Standard Penetration Test
STP : Sewage Treatment Plant
SOx : Sulfur Oxides
SC : Supervision Consultant
SUPARCO : Pakistan Space and Upper Atmosphere Research Commission SWM : Solid Waste Management
SBCA : Sindh Building Control Authority
SSGC : Sui Southern Gas Company SEQS : Sindh Environmental Quality Standards TA : Technical Assistance
TOR : Terms of Reference
TDS : Total Dissolved Solids
TSS : Total Suspended Solids USEPA : United States Environmental Protection Agency WHO : World Health Organization
Executive Summary EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-i July, 2016
EXECUTIVE SUMMARY
A) PROJECT BACKGROUND Electricity is considered to be most essential instrument for the socio-economic
development of a country. According to the “Annual Plan 2015-16” Pakistan
continues to suffer from the power crisis as nearly one-third of demand for
electricity, during the last year, could not be met due to the supply constraints. On
average, the supply deficit of around 5,000 Megawatt (MW) was experienced, while
it touched the peak of over 7,000 MW last July. And Pakistan’s existing primary
energy supplies are highly skewed towards more expensive fuels like oil and gas
instead of indigenous hydro and coal. Out of 67 Million Tons of Oil Equivalent
(MTOE) of total primary energy mix for 2013-14, 46.4 per cent share is of natural
gas, 35 per cent oil, 11.4 per cent hydro, 5.4 per cent coal and two per cent nuclear,
including imported energy. Disproportionate reliance on the imported oil, that is, 85
per cent of the total oil supply, is exerting a strain on the balance of payments
besides making the energy mix unfavorable.
To reduce the current deficit in the power supply in the country GoP has
implemented the “National Power Policy 2013” in the power sector.
Most of the upcoming coal fired power plants are being planned on imported coal
coming from South Africa, Indonesia or Australia.
Imported coal arriving at Port Qasim will be off loaded at Pakistan International Bulk
Terminal (PIBT) from where it will be transported to the coal fired power plants
situated in various parts of country.
The under construction PIBT, a private sector BOT project for handling coal, clinker
and cement is expected to start operations by December 2016. PIBT has been
planned for handling the import of coal and export of cement and clinker. The initial
handling capacity of PIBT is 8 million tonnes under its Phase-I and Phase-II. The
capacity will be enhanced to 12 million tones under Phase-III.
There are essentially two (02) modes of transport that are envisaged from PIBT to
the power plants.
a) By road, using trucks: This is seen to be practical mainly for local power plants situated closer to Port
Qasim as the large number of trucks required to transport coal to plants located in
Executive Summary EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-ii July, 2016
other parts of the country would significantly increase truck traffic in the port area as
well as the highway network adding to congestion on the roads, increasing the
chances of accidents and having an adverse impact on the environment.
b) By Rail, using wagons: This is considered to be a safe and efficient method of bulk coal transportation over
long distances and is suitable for supply to power plants in other parts of the
country.
The main railway tracks are located on northern side of Port Qasim in North-West
Industrial Zone (NWIZ). Two tracks links Karachi to other parts of the country. These
tracks are also being used for freight trains as reported by Pakistan Railways (PR).
A single track exists on west of NWIZ which connects Port Qasim Marginal Wharf
Berths to Pipri Marshalling Yard and is connected onward with the main railway
lines.
Pakistan Railways track in NWIZ of Port Qasim is 5.0 KM away from PIBT. A
transportation link is needed between PIBT and existing railway track in NWIZ of
Port Qasim. To meet this requirement the Government of Pakistan (GoP) decided to
connect PIBT with existing railway network at Port Qasim with a bulk conveyor. GoP
has directed PQA to develop the connectivity of PIBT with existing railway network
by laying a coal conveying system.
The project is to be undertaken on Engineering, Procurement and Construction
(EPC) basis and is required to be completed on priority basis to meet the demand of
coal at power plants.
The transport of coal through train shall initially reduce the gap between electric
power demand and supply, which will give boost to the economy by way of
employment and increase in the GDP growth.
Additional employment will be generated at the project and power plants and the
use of additional power will create employment in various industries.
The project is expected to be environmentally in conformity with national
environmental laws.
The alternative to the conveyor system would be transport of coal, from PIBT to
railway yard, by trucks. This mode of transportation would be inefficient, slow,
Executive Summary EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-iii July, 2016
unsafe, will cause pollution and road traffic congestion at port.
Presently, there is no connection between PIBT & existing railway network at
Port Qasim and hence, this link needs to be constructed.
Pakistan Railways has informed that the railway network cannot be extended to
PIBT due to the steep gradient and interface issues with the main line. Therefore;
connection between PIBT and existing railway network is required. GoP has
decided that this connectivity shall be through conveyor. The coal conveyor is to
be installed from PIBT to the existing Pakistan Railway Network measuring
approximately 4.5 km.
The Cabinet Committee in its meeting on 16th September, 2015 decided that Port
Qasim Authority (PQA) shall take up the installation of conveying system from
PIBT to existing Railway Network at Port Qasim
Working Mechanism: As per the conceived scheme, PIBT will unload the coal at its jetty and stock at its
backup area for the power plants and other consumers located in the vicinity of
Port Qasim. For the power plants and other consumers (if any) located upcountry
the PIBT will unload the vessel/ship at its jetty and load at PQA coal conveying
system for transportation of coal through Pakistan railway.
Transportation of coal from the coal loading area in Port Qasim to various power
plants in the country shall be performed by Pakistan Railways.
PQA’s coal conveyor will transport the coal to a coal stockyard near existing railway
track. The stockyard will be equipped with combined Bucket Wheel Stacker
Reclaimer (BWSR) coal stacking/reclaiming equipment. Coal will be stacked in
stock piles where approximately 440,000 tonnes of coal can be stored. Reclaiming
of coal from stockyard will be performed by the BWSR and coal will be loaded on a
coal conveyor for transportation to the load out station located at the railway track
for loading on railway wagons.
The arrangement for coal stacking, reclaiming and maintaining live and dead
storage at the power plant shall be made by the respective power plants.
Project Description
From PIBT to railway siding and loading of coal onto railway wagons for onward
transportation to the proposed coal fired power plants. The project is being taken
Executive Summary EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-iv July, 2016
up on the directive of the Prime Minister’s Office as per the decision of Cabinet
Committee on energy .
The Coal Conveying System from PIBT to existing Railway Network at Port Qasim
shall be carried out as per the approved development scheme and be executed in
a manner that will not obstruct the normal port activities. Scheme of coal conveying
and development is as follows:
Take up of coal outside PIBT Terminal’s premises onto the PQA coal conveyor
and transfer coal through conveyor to PQA’s coal stockyard located near the
existing railway track. Storage of coal in stockpiles by utilizing BWSR in PQA’s
stockyard and loading of coal from stockpiles to belt conveyor via BWSR for
onward transportation up to load out station at railway track.
• Provision of railway loop / siding for coal loading into railway wagons;
• Rapid loading of coal in railway wagons through a load-out station;
• Provision of infrastructure facilities i.e. road, drainage, water supply, storm water
firefighting and sewerage system;
• Provision of water sprinkling system to control coal dust at coal stockyard;
• Provision of wind breaker and coal dust suppression wall around the coal
stockpiles;
• Provision of security and surveillance systems including emergency power
backup;
• Provision of electric power supply (approx.4.5 MW) for the project during
construction and operation;
• Provision of telecommunication connection from existing network; and
• Acquisition of 200 acres of land adjacent to existing railway track on east of PQA
NWIZ in Pakistan Steel Mill Area and necessary ROW required for conveyor.
The coal dust suppression system will be designed during detail design stage. The
following is a general description of the system.
Coal dust from coal stockpile and coal conveyor belt is the major source of fugitive
emissions. Dust suppression using the covers over coal conveyor belt, inbuilt dust
control systems in transfer stations and rapid load-out station, wind breaker wall,
dust suppression wall and water sprinkler system at coal stockyard will be primarily
employed to control the coal dust from these areas.
Executive Summary EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-v July, 2016
PQA Coal Conveyor Belt and Coal Stockyard: Different potential routes for coal conveyor belt and sites for coal stockyard were
studied to develop a conveyor belt and coal stockyard.
PQA Coal Conveyor Belt Four (04) routes for the provision of Coal Conveyor Belt were studied by
considering the following factors to identify the most feasible route of coal
transportation from PIBT to PQA coal stockyard. The routes studied are shown in
figure 3.9 and described in detail in section 3.6.2 of this report.
a) Location of first coal transfer station near PIBT (starting point);
b) Location of PQA coal stockyard and load-out station (end point);
c) Minimum changes in the existing natural environment;
d) Relocation of existing utilities;
e) Topography of the area;
f) Geotechnical conditions;
g) Availability of R.O.W;
h) Physical features and impediments along the route;
i) Turning points along the route; and
j) Access roads for the inspection and maintenance of conveyor belt.
PQA Coal Stockyard Different four (04) potential sites as shown in figure 3.8 and discussed in detail in
section 3.5.2 have been studied by considering the following site selection criteria
for the development of PQA coal stockyard from where the coal can be conveyed
to a rapid load-out station for loading railway wagons.
a) Availability of adequate parcel of land along the existing railway track;
b) Minimum changes in the existing natural environment ;
c) Access to site;
d) Relocation of any existing utilities;
e) Proximity to rapid load-out station;
f) Suitability of land with respect to topographic and sub-soil conditions; and
g) Capital and O & M cost of conveying system.
B) NEED FOR EIA STUDY
An Environmental Impact Assessment (EIA) Study has been conducted for
construction of COAL CONVEYING SYSTEM as a mandatory requirement of
Executive Summary EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-vi July, 2016
Sindh Environmental Protection Act (SEPA), 2014, Environmental Examination
and Assessments Part VI 17. (1).
The Project Proponent, Port Qasim Authority, (PQA), Government of Pakistan
(GoP), entrusted National Engineering Services Pakistan Private Limited
(NESPAK) to fulfill this regulatory requirement of the project.
C) SCOPE OF STUDY The scope of EIA Study includes Environmental Assessment of the project
including collection of data related to physical, biological and socio-economic
environment, assessment of impacts which may be caused by the project activities
and mitigation measures for the abatement of potential environmental impacts
along with the estimated budgeted cost of mitigation.
This study has been conducted in accordance with the Sindh Environmental
Protection Agency (SEPA) and Government of Sindh (GoS) Guidelines. The study
is based on both primary and secondary data and information. Discussions were
held with stakeholders including, different government department, utility service
providers, community representatives and a wide range of road users and
roadside dwellers.
D) STUDY AREA Figure 1.1 shows the visual examination of Study Area and includes about 500 m buffer
area on either side from the centerline of the median of selected route for coal
conveyor belt and around the PQA coal stockyard.
E) RELEVENT LEGISLATIONS AND POLICIES The 18th amendment in the Constitution of Islamic Republic of Pakistan has
fundamentally altered the division of legislative powers between the National
Assembly and the Provincial Assemblies, resulting in a significant increase in the
extent of provincial autonomy. After this amendment, powers for the grant of No
Objection Certificate (NOC) have been delegated to the provincial EPAs. For this
project, Sindh EPA is the concerned authority.
In compliance with the regulatory requirement and commitment of Port Qasim
Authority (PQA) to sustainable development, this EIA Study has been conducted. The
EIA study has extensively considered all the relevant national and provincial
legislations, regulations and guidelines related to the project.
Executive Summary EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-vii July, 2016
F) PROJECT DESCRIPTION The estimated capital cost of the infrastructure development is approximately Rs. 16.0
billion.
G) DESCRIPTION OF THE ENVIRONMENT The baseline information was collected for the Study Area utilizing the checklists,
preforms, Satellite Imagery from Google Earth, and General Topographic (GT)
sheets. Meetings and scoping sessions with all the concerned project stakeholders
were carried out for the collection of primary information, disclosure of Project
interventions, information and to clear queries about the Project. The Study Area was
marked using the GT sheets and Google Earth Image during desk studies which was
later finalized during the field visit.
Physical Environment The physical environment includes topography, regional geology, soils, climate,
hydrology, drainage, seismology, surface water, groundwater, noise levels and
ambient air quality.
Port Qasim is located, adjacent to the Bin Qasim town, in the southern part of Malir
district, Karachi division, in Sindh. It is located in an old channel of the Indus River at
a distance of 35 kilometers east of Karachi city center.
The geographic position of the Port Qasim places it in close proximity to major
shipping routes. The approach to the port is along a 45-kilometre long Navigation
Channel which provides safe navigation for vessels up to 75,000 tones dead weight
(DWT).
The information, as per Geologic Survey of Pakistan, reveals that in the project area
and its adjoining areas only the middle and upper tertiary formations are present. The
formation found in the area is fresh and slightly weathered, recent and sub recent
shoreline deposits. These deposits are derived from Gaj / Manchhar formations of
lower Miocene to Middle Miocene / Upper Miocene to Pliocene age. Similar deposits
are found all along the coastal belt of Karachi and adjoining areas. The seabed is
predominantly sand and silt while the sediment of the delta is fine grained and
resembles the soil from the continental shelf at the mouth of the Indus delta.
Due to proximity to the sea, the city of Karachi has little variation in average maximum
and minimum temperatures. The average annual temperatures during summer are
26oC to 35oC (up to 42oC in May/June), whereas temperature ranges between 10oC
Executive Summary EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-viii July, 2016
to 27oC during winter. Day and night temperature also varies considerably as the sea
breeze in the afternoon rapidly decreases day time temperatures.
Seismicity
Sindh Building Control Authority (SBCA) has placed Karachi in Zone-2 B based on
the actual events, the past observations of fault movement and other geological
activities. Karachi is situated in a region where moderate earthquakes may occur of
magnitude 5.0 to 6.0 equivalents to intensity between VII and VIII on Modified
Mercallis Scale (M).
As per the building code of Pakistan, Seismic Provisions 2007, the project area falls in
Zone 2B Seismic Zoning Map of Pakistan (Figure 4.1). The project structures should
therefore be designed to cater for the ground acceleration of 0.16 g to 0.24 g.
Environmental Monitoring To establish the baseline of the project area, air, noise, drinking and ground water
monitoring was carried out near project site. The results of ambient air monitoring,
noise quality, drinking and ground water quality indicates that all parameters are well
within the permissible limits of NEQS.
Ecological Environment The climate of Malir District is arid and it is densely populated with wide variety of
vegetation in the form of natural foliage consisting diversity bushes, shrubs, trees
including agricultural products such as crops, vegetables and fruits.
Flora: The floral species located in the project area are very few mainly the xerophytic.
Shrubs/weeds were observed grown in the project area. The footings for coal
conveyor belt will be installed/erected in the existing green belt located in the median
of the road where about twelve (12) numbers of trees would be affected. These trees
are poplar, neem, molsary and kikar.
Fauna: In near past, Deer (Gazella benetti) Wolf (Canis lupus pellipes), Jackals (Canis
aureus) and Fox (Vulpes bengalenis) were found in abundance. Now days, these
wild animals can be seen only in the center of wild life development.
Among birds Indian Grey partridge, Chest-Nut-Bellied Sand Grouse, Rock Dove,
Indian Little Button Guail and Eurasian Roller are found in Malir District.
Executive Summary EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-ix July, 2016
Socio-economic Environment According to District Census Report (DCR) of Malir, 1998, the total area is 2268 Sq.
kilometer yielding a population density of 432.7 in 1998. The population of Malir
district was 981.41 thousand in 1998 as compared to 429.57 thousands in 1981. The
annual growth rate measured 4.98% during the 1981-1998.
A social survey was carried out in the project area to identify the impacts and their
magnitudes on the affected population. A sample of 100 respondents was taken on
the basis of random sampling technique, which included residents, Government
Officials and visitors etc.
SCREENING OF POTENTIAL ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES The project is linked with resolving the energy crisis by providing cheap base electric
power in quantum enough to let the various economic sectors to operate at optimum
capacity utilization and ability to make investment decisions with the knowledge that
cheaper base and reliable electric power shall be available.
Provision of power in adequate quantum will enhance capacity utilization, promote
higher employment, higher tax collection and a virtuous development cycle will be
started.
The potential impacts due to implementation of the proposed Project on physical,
ecological and socio-economic domains of the environment of the Project as well as
the Study Area have been identified.
The important and major impacts and respective mitigation measures are as follows:
Construction Stage During construction of Coal Conveying System, proper mitigation measures are
necessary. During the field survey, significant efforts were made to identify the main
social, cultural and environmental issues related to the project for which a cross
section of the society including residents of the project area, various government
departments and agencies were contacted for obtaining the information. Most of the
perceived impacts are during construction phase. Following is a list of main concerns
identified in the study:
• Disturbance to the public movement during construction;
• Air and noise pollution due to the different construction activities and operation
of construction machinery during construction phase of the project;
Executive Summary EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-x July, 2016
• Solid waste generation during construction;
• Accidental leaks/spills of hazardous chemicals from construction activities and
machinery;
• Health and safety issues of the workers;
• Contamination of water body by construction activities; and
• Disturbance in traffic movement during excavation and lying of utility pipe in
relocation of public utilities.
Operational Stage Recommended mitigation measures to contain potential adverse impacts are
described in the Environmental Monitoring and Management Plan (EMMP). EMMP
shall be strictly enforced during the operational phase of the proposed Project.
H) ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN The main objective of the Environmental Management and Monitoring Plan is to
ensure that all the necessary corrective actions are carried out to mitigate any
adverse environmental impacts, and that enhancement measures are used wherever
feasible and practical. This program includes Institutional Requirements;
Environmental Monitoring Program; Tree Plantation Plan; Training and Capacity
Building; Reporting Structure and Outcomes; Environmental Management and
Monitoring Cost.
To implement and monitor the mitigation measures, following organizations will be
involved:
• Port Qasim Authority (PQA) as the Proponent;
• NESPAK as the Consultant of the Project (Infrastructures Development only)
• Project Contractor, as the executor of the project;
• EPA-Sindh, as observer and top monitoring agency during the construction and
operations stage.
The Project Proponent will be responsible for ensuring the overall implementation of
EMMP during the construction and operation stages of the project.
Environmental Monitoring is recommended during the construction and operational
phases to ensure the effectiveness of the proposed mitigation measures.
Executive Summary EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-xi July, 2016
I) CONCLUSIONS AND RECOMMENDATIONS After the assessment of proposed project activities and investigation of the project
area, Screening of potential impacts reveals that the proposed CCS on adoption of
the suggested mitigation measures is an environmentally acceptable proposition.
It is suggested that in order to improve the disturbed ecology of the project site, a
landscape and plantation plan should be prepared and implemented by utilizing
available resources.
It is envisaged that the commitment of the PQA to maintain the quality of the
environment within and adjacent to project area through implementation of the
environmental management plan would mitigate any adverse impacts. For effective
environmental management, PQA should assign the necessary responsibilities to an
Environmental Committee (EC) which should be responsible for implementation of
the Environmental Monitoring of the proposed project.
It is concluded that the proposed project will not result in any significant negative
impact to the community or the environment during construction and subsequent
operation phase.
The mitigation measures are being proposed to control noise emission, wastes and
dust during construction and operation stage of the project. It will be ensured that the
project will comply with all the regulatory requirements, guidelines and safety
standards are followed and that the recommended environmental mitigation
measures as discussed in this report are adopted.
It is envisaged that the commitment of Port Qasim Authority (PQA) to maintain the
quality of environment within and adjacent to the project area through implementation
of the EMMP would mitigate any adverse impacts. For effective environmental
management, Port Qasim Authority (PQA) should assign the necessary
responsibilities to an Environmental Committee which should be responsible for
implementation of the Environmental Management and Monitoring of the proposed
project.
The implementation of Coal Conveying System (CCS) will provide;
• CCS includes features like inbuilt dust control in transfer stations, covered coal
conveyor, mechanized loading unloading features, dust suppression and
complete firefighting arrangements at coal stockyard, and rapid load-out station
for loading the train, all day service spans, and more frequent service than truck
Executive Summary EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-xii July, 2016
transport;
• The use of exclusive trains, flexibility and lower-cost of transportation by train
allows it to provide cost effective, environment friendly, safe, swift, and greater
reliability of fuel for power plants;
• Reliable supply of fuel ensures the reliable power generation and supply;
• Improved tax / fare collection;
• The total capacity of a single train is 2400 tonnes;
• The greater frequency and larger quantities of coal transport through train will
reduce traffic on highways;
• Contributes to reductions in traffic crashes;
• Reduced traffic load noise & air pollution; and
• Reduced maintenance of roads.
Some recommendations those need to be followed for the project to make the project
sustainable are:
• The Project impacts and their mitigation will be monitored as per the Monitoring
Plan;
• All mitigation, compensation and enhancement measures proposed in this EIA
report are implemented in full, as described in the document;
• To ensure that the environmental impacts of the project are successfully
mitigated;
• The Environmental Management and Monitoring Plan must be implemented;
and
• The Implementing Agency (PQA) shall ensure that the EMMP prepared by the
contractor includes construction methodologies and submit this to PQA for
review and approval.
At the implementation stage, PQA assisted by Supervision Consultants (SC) will
make arrangements to monitor the implementation of mitigation measures and
conduct environmental effects monitoring activities specified in the EMMP.
With these measures in place, environmental impacts of the Project should be
manageable and will not result in any residual impacts on the project.
Section–1 Introduction EIA of Coal Conveying System - Port Qasim, Karachi
____________________________________________________________________________________________________NESPAK Page 1-1 July, 2016
SECTION–1
INTRODUCTION
1.1 NEED OF THE PROJECT Pakistan continues to suffer from the power crisis as nearly one-third of demand for
electricity, during the last year, could not be met due to the supply constraints. On
average, the supply deficit of around 5,000 Megawatt (MW) was experienced, while it
touched the peak of over 7,000 MW last July1.
Pakistan’s existing primary energy supplies are highly skewed towards more
expensive fuels like oil and gas instead of indigenous hydro and coal. Out of 67
Million Tons of Oil Equivalent (MTOE) of total primary energy mix for 2013-14, 46.4
per cent share is of natural gas, 35 per cent oil, 11.4 per cent hydro, 5.4 per cent coal
and two per cent nuclear, including imported energy. Disproportionate reliance on the
imported oil, that is, 85 per cent of the total oil supply, is exerting a strain on the
balance of payments besides making the energy mix unfavorable1.
Highly expensive generation of electricity (~Rs 12 / unit) due to an increased
dependence on expensive thermal fuel sources (44% of total generation). RFO,
HSD, and mixed are the biggest sources of thermal electricity generation in Pakistan
and range in price from ~Rs 12 / unit for mixed, to ~Rs 17 / unit for RFO, and a
tremendously expensive ~Rs 23 / unit for HSD. Dependence on such expensive fuel
sources has forced Pakistan to create electricity at rates that are not affordable to the
nation and its populace2.
To reduce the current deficit in the power supply in the country GOP has
implemented the “National Power Policy 2013” in the power sector. The main feature
of the policy is to use coal as a lower cost energy source. As a result of policy the
number of coal fired power plant projects are being undertaken including Sahiwal,
Jamshoro and Lakhra.
1- Annual Plan 2015-16
2- National Power Policy 2013
Section–1 Introduction EIA of Coal Conveying System - Port Qasim, Karachi
____________________________________________________________________________________________________NESPAK Page 1-2 July, 2016
Coal, as a fuel for power generation, has very low usage in Pakistan and the
infrastructure required for the handling and transportation of bulk coal cargo does not
exist. However, with the new up-coming coal based power projects, the provision of
necessary infrastructure has become an urgent need.
Imported coal arriving at Port Qasim will be off loaded at Pakistan International Bulk
Terminal (PIBT) from where it will be transported to the coal fired power plants
situated in various parts of the country.
The under construction PIBT, a private sector BOT project for handling coal, clinker
and cement is expected to start operations by December 2016. PIBT has been
planned for the import of coal and export of cement and clinker. The initial handling
capacity of PIBT is 8 million tonnes under Phase I & II, which will be enhanced to 12
million tonnes under Phase III.
Transportation of coal from PIBT, Karachi to the coal power plants located in the
vicinity of Karachi / nearby areas will be by trucks but this mode of transport is
unsuitable for plants located in other parts of the country. Therefore, for plants
located at Jamshoro, Lakhra, Muzaffargarh, Sahiwal, etc., coal transport is foreseen
by railway.
Presently, there is no connection between PIBT & existing railway network at
Port Qasim and hence, this link needs to be constructed. The project is to become
part of the existing infrastructure at Port Qasim.
Pakistan Railways has informed that the railway network cannot be extended to PIBT
due to the steep gradient and interface issues with the main line hence; a coal
conveying system is to be installed from PIBT to the Pakistan Railways Network
measuring approximately 4.5km by Port Qasim Authority (PQA).
The proposed project "Coal Conveying System from PIBT to existing railway network
at Port Qasim” will provide an important link in the establishment of a coal
transportation infrastructure. The project derives its need from being an integral part
of imported coal based power projects.
Port Qasim Authority (PQA), GoP entrusted National Engineering Services Pakistan
(NESPAK) with the assignment of carrying out an Environmental Impact Assessment
(EIA) Study of Coal Conveying System from PIBT to existing railway network at Port
Qasim.
Section–1 Introduction EIA of Coal Conveying System - Port Qasim, Karachi
____________________________________________________________________________________________________NESPAK Page 1-3 July, 2016
1.2 SCOPE OF STUDY
The scope of EIA Study aims at collection and scrutiny of data related to biophysical
and socio-economic environment of the project area and to prepare the baseline
environmental profile. It also aims at the identification, prediction and evaluation of the
possible environmental impacts of the proposed project on its immediate surroundings
on both short and long-term basis. Based on the nature and levels of these impacts,
appropriate mitigation measures along with their cost have been incorporated in this EIA
Report.
1.3 STUDY OBJECTIVES The overall objective of EIA is to assess the environmental impacts arising from the
project. The specific objectives of the EIA Study for Coal Conveying System (CCS)
from PIBT to Railway Network at Port Qasim are:
Collection of data related to physical, biological and socio-economic
environments of the project area and to prepare baseline environmental profile;
Identification, prediction and evaluation of environmental impacts of the proposed
project;
Suggesting appropriate mitigation measures to minimize the adverse impacts;
and
Preparation of an Environmental Monitoring and Management Plan.
1.4 NEED FOR EIA STUDY OF THE PROPOSED PROJECT
EIA is mandatory according to Sindh Environmental Protection Act, (SEPA), 2014,
Environmental Examination and Assessments Part VI 17. (1), which states that:
“No proponent of a project shall commence construction or operation unless he has
filed with the Provincial Agency an initial environmental examination or, where the
project is likely to cause an adverse environmental effect, an environmental impact
assessment, and has obtained from the Provincial Agency approval in respect
thereof.”
According to the Sindh Environmental Protection Agency (Review of Initial
Environmental Examination and Environmental Impact Assessment) Regulations,
2014, the proposed project falls under category J (Other Projects) of Schedule II, which requires EIA before commencement of construction.
Section–1 Introduction EIA of Coal Conveying System - Port Qasim, Karachi
____________________________________________________________________________________________________NESPAK Page 1-4 July, 2016
1.5 THE PROPONENT AND CONSULTANT
The proponent of the project is Port Qasim Authority (PQA) while the Consultant is NESPAK. The details are given as under:
For the Proponent
Director General Port Qasim Authority
Bin Qasim, Karachi-75530, Pakistan Telephone : 021-99272111-30
Facsimile : 021-34730107
Email : [email protected]
For the Consultant
Project Manager National Engineering Services Pakistan Private Limited (NESPAK)
13th Floor, NICL Building, Abbasi Shaheed Road, Karachi
Telephone : 021-35657140
Facsimile : 021-35651994
Email : [email protected]
1.6 STUDY TEAM
A multidisciplinary team was formulated to conduct the study. The team comprises of
the following persons:
Syed Munawwar Abbas
Mukesk Kumar
Riazul Huda
Ainuddin
Syed Ali Sher Shah
Hammad Qamar
Saeed Hussain
Adeel Pervez
Sanober Zubair
Shariq Ullah Khan
Zahir uddin Khan
Project Manager
Project Coordinator/Senior Engineer
Project Adviser (Civil)
Project Adviser (Mechanical)
Team Leader / Environmental Engineer
Environmental Engineer
Sociologist
Environmentalist/Ecologist
Environmental Engineer
Sociologist
Senior Civil Surveyor
Section–1 Introduction EIA of Coal Conveying System - Port Qasim, Karachi
____________________________________________________________________________________________________NESPAK Page 1-5 July, 2016
1.7 STUDY APPROACH & METHODOLOGY
1.7.1 Study Approach This study has been conducted in accordance with Environmental Protection Agency
(EPA), Government of Pakistan (GoP) Guidelines, 2000. The study is based on both
primary and secondary data and information. Discussions were held with stakeholders
including government officials, nearest community representatives and -factory owners
and employees. The main purpose of this approach was to obtain a fair impression of
the people’s perceptions of the project and its environmental impacts.
1.7.2 Methodology The following methodology was adopted for carrying out the EIA study of the proposed
Project:
a) Orientation Meetings and discussions were held among the members of the EIA Team. This activity
was aimed at achieving a common ground of understanding of various issues of the
study.
b) Planning for Data Collection Subsequent to the concept clarification and understanding obtained in the preceding
step, a detailed data acquisition plan was developed for the internal use of the EIA
Team. The plan included identification of specific data requirements and their sources;
determined time schedules and responsibilities for their collection; and indicated the
logistics and other supporting needs for the execution of the data acquisition plan.
c) Data Collection In this step, primary and secondary data were collected through field observations,
environmental monitoring in the field, concerned departments and published materials
to establish a baseline profile for physical, biological and socio-economic environmental
conditions.
Following steps were followed to collect the primary and secondary data related to this
study:
- Site Reconnaissance
- Analysis of Maps and Plans
- Literature Review
Section–1 Introduction EIA of Coal Conveying System - Port Qasim, Karachi
____________________________________________________________________________________________________NESPAK Page 1-6 July, 2016
- Desk Research
- Public Consultations
- Field Observations & Studies
- Environmental Monitoring and Laboratory Analysis
The data was collected for physical, biological and socio-economic conditions, the
details of which are given below:
i. Physical Environment
Information was gathered on the existing physical environment, particularly as related to
geology, topography, soils, hydrology, drainage, water quality, air quality and noise.
Geology, Topography, Soils
A review of relevant literature was performed on the geology, topography, sub-
soil conditions of the project area.
Hydrology and Drainage
A literature review was conducted to identify the components of the hydrological
cycle that are likely to impact on the project and the possible impacts that the
project could have on the hydrologic regime. Field assessment includes
assessment of drainage issues, interviews with local community members, and
round-table discussions with stakeholders.
Air Quality
Ambient air quality measurements are essential to provide a description of the
existing conditions, to provide a baseline against which changes can be measured
and to assist in the determination of potential impacts of the proposed construction
on air quality conditions. Ambient air quality was continuously monitored for Carbon
Monoxide (CO), Sulphur Dioxide (SO2), Nitrogen Dioxide (NO2), Particulate Matter
(PM10), for 24 hours. CO was analyzed by Test 317-3 CO Analyzer, while SO2
and NO2 were analyzed according to the Standard Operating Procedures (SOP)
based on recognized method ISO 6767 and method ISO 6768 of USEPA
respectively.
Noise
Noise level readings were monitored at 03 (three) sampling point for 24 hours with
the interval of one second and hourly average data was reported.
Section–1 Introduction EIA of Coal Conveying System - Port Qasim, Karachi
____________________________________________________________________________________________________NESPAK Page 1-7 July, 2016
Water Quality
The objective of water quality monitoring was to determine water quality condition
before construction. It has been observed that the water and air quality are the
most important environmental variables to be affected in a road project. The extent
of water contamination in the project area was assessed based on the test results
of chemical and microbiological parameters for water. Dissolved oxygen (DO), pH
and conductivity measurements were taken in situ at all sampling stations.
Laboratory analyses have been performed in SUPARCO laboratory.
ii. Biological Environment The status of the flora and fauna of the study area was determined by ecological
survey, a review of literature relevant to the area, and an assessment of terrestrial
environments.
Flora
The vegetative communities were identified and classified into community types.
Identification was carried out of dominant tree species.
Fauna
Information on fauna was gathered from existing literature on reported species as
well as observations in the field.
iii. Socio-Economic Environment The Consultants utilized a combination of desk research, field investigations,
census data, structured interviews, maps and reports to generate the data required
for description of the existing social environment and assessment of the potential
impacts of the construction of the proposed project. Data was gathered on the
following aspects of the social environment:
- Land use and Municipal Status
- Livelihoods
- Poverty
- Education
- Health
- Social Setup
- Community Facilities
- Solid Waste Management
- Proposed Developments
Section–1 Introduction EIA of Coal Conveying System - Port Qasim, Karachi
____________________________________________________________________________________________________NESPAK Page 1-8 July, 2016
- Recreational Activities
- Archaeological and Cultural Heritage
d) Identification and Evaluation of Environmental Impacts
The impacts of the proposed project on the physical, biological and socio-economic
environment prevalent in the project area were visualized at the Design, Construction
and Operational Phases.
e) Mitigation Measures and Implementation Arrangements
Adequate mitigation measures and implementation mechanisms were proposed so that
the Project Proponent could incorporate them beforehand in the design phase.
1.8 EXTENT OF THE STUDY
This document covers introduction of project, project description, analysis of
alternatives, baseline conditions, environmental impacts, mitigation measures,
institutional requirements and Environmental Management and Monitoring Plan
(EMMP) of the proposed coal conveyor route, in and around the Project Area covering
the physical, ecological and socio-economic aspects.
a) Study Area
Before proceeding to the environmental assessment of the Project, it is imperative to
delineate the area of project influence (referred to as the “Study Area”). While major
construction activities of the project are expected to remain confined within the project
area boundary, the environmental impact of these activities is expected to extend
beyond these boundaries to nearby residential and industrial areas.
Therefore, based on field visits and examination of the Study Area and surrounding
neighborhoods, the Study Area boundary was delineated. Figure 1.1 shows the visual
examination of Study Area and includes about 500 m buffer area on either side from
the centerline of the median and around the stockyard.
The description of the environment in this chapter pertains to the Study Area described
above as the potential environmental impacts are expected to remain within this
delineated boundary.
EIA OF COAL CONVEYING SYSTEM-PORT QASIM, KARACHI
FIGURE 1.1: STUDY AREA OF COAL CONVEYING SYSTEM
Section–1 Introduction EIA of Coal Conveying System - Port Qasim, Karachi
____________________________________________________________________________________________________NESPAK Page 1-9 July, 2016
1.9 STRUCTURE OF THE REPORT
The report has been structured as follows:
Section 1: Introduction briefly presents the project background, objectives,
methodology and need of the EIA study.
Section 2: Policy, Legal and Administrative Framework comprises policy guidelines,
statutory obligations and roles of institutions concerning EIA study of the proposed
project.
Section 3: Description of the Project furnishes information about the location of
proposed project, cost and size of the project, detailed description of project,
alternatives considered for the proposed project to select at the preferred alternative for
detailed environmental assessment.
Section 4: Environmental Baseline Profile establishes baseline conditions for
physical, biological and socio-economic conditions prevalent in the project area.
Section 5: Public Consultation identifies the main stakeholders and their concerns
raised through scoping sessions, stakeholder meetings and deals with the measures to
mitigate the social impacts.
Section 6: Anticipated Environmental Impacts and Mitigation Measures identifies,
predicts and evaluates impacts of the project activities during the Construction and
Operation stages and deals with the measures (including mitigation cost) proposed to
mitigate Potential Environmental Impacts of the project.
Section 7: Environmental Management and Monitoring Plan outlines institutional
arrangements for the implementation of the proposed mitigation measures, training
needs of the staff for implementation of the mitigation measures, monitoring
requirements, monitoring cost etc.
Section 8: Conclusions and Recommendations summarize findings of the study and
present its conclusions and recommendations.
Section–2 Policy, Legal and Administrative Framework EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-1 July, 2016
SECTION – 2
POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK
2.0 GENERAL
This chapter deals with the relevant policy, legal and administrative frameworks
instituted by the Government of Pakistan (GoP) and Government of Sindh (GoS) for
the protection of the environment. All the relevant provisions of these policies and
legal frameworks have been duly considered in this EIA study.
2.1 LEGAL FRAMEWORK
GoS has promulgated laws/acts, regulations and standards for the protection,
conservation, rehabilitation and improvement of the environment. In addition to this,
they have also developed environmental assessment procedures governing
developmental projects. Following are the excerpts of these laws and procedures
relevant to the proposed project.
2.1.1 Sindh Environmental Protection Agency (Review of IEE /EIA Regulations, 2014 The Sindh Environmental Protection Agency review of IEE)/EIA Regulations, 2014
provide the necessary details on the preparation, submission and review of the IEE
and the EIA. The regulation classifies projects on the basis of expected degree of
adverse environmental impacts and lists them in two separate schedules. Schedule-I
lists projects that may not have significant environmental impacts and therefore
require an IEE. Schedule-II lists projects of potentially significant environmental
impacts requiring preparation of an EIA.
2.1.2 Pakistan Environmental Assessment Procedures, 1997
Pakistan Environmental Assessment Procedures (1997) is in fact a package which
contains the following sets of information relevant to the proposed project:
a) Policy and Procedures for Filing, Review and Approval of Environmental
Assessment Reports.
Section–2 Policy, Legal and Administrative Framework EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-2 July, 2016
It describes environmental policy and administrative procedures to be followed for
filing of environmental examination/assessment reports by the proponents and their
review and approval by the concerned environmental protection agencies.
b) Guidelines for the Preparation and Review of Environmental Reports
These guidelines are developed to facilitate both the proponents and decision
makers to prepare reports (inclusive of all the information contained therein) and
carry out their review so as to take informed decisions.
c) National Environmental Quality Standards (NEQS), 2010
Pakistan Environmental Protection Council (PEPC) first approved these standards in
1993. They were later revised in 1995, 2000 and 2010. They furnish information on
the permissible limits for discharges of municipal and industrial effluent parameters
and industrial gaseous emissions in order to control environmental pollution.
2.1.3 Sindh Environmental Protection Act, 2014 Legislative assembly of Sindh province of Pakistan passed the bill on 24th February,
2014 to enact Sindh Environmental Protection Act 2014. The Act envisages
protection, improvement, conservation and rehabilitation of environment of Sindh
with the help of legal action against polluters. The Act is the basic legislative tool
that empowers the government to frame regulations to protect the environment. It
broadly applies to air, water, soil, and noise pollution.
Under this Act no project including construction activities or any change in the
existing physical environment can commence unless the fulfillment of prerequisite
to IEE or EIA has been conducted and its approval obtained from the Responsible
Authority, in the present case from Sindh EPA. It equally lays emphasis for the
preservation of the natural resources of Sindh and to adopt ways and means for
restoring the balance in its eco-system by avoiding all types of environmental
hazards.
2.1.4 Sindh EPA (Review of IEE/EIA) Regulations, 2014 The Sindh Environmental Protection Agency (Review of EIA/IEE) Regulations 2014
define Schedules (I & II) of projects falling under the requirement of IEE or EIA taken
account of the requirements of the Sindh Environmental Protection Agency (Review
of EIA/IEE) Regulations 2014 which define Schedules (I & II) as follows:
Schedule I: A project falls in Schedule (I) if it is likely to have adverse environmental
impacts, but of lesser degree or significance than those for category ‘A’ and all the
Section–2 Policy, Legal and Administrative Framework EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-3 July, 2016
mitigation measures to handle the impacts are manageable. Such types of projects
need IEE report including EMP.
Schedule II: Projects are categorized in Schedule (II) if they generate significant
adverse environmental impacts that require a comprehensive management plan or if
the project is located within or passes through: a) Areas declared by the Government
of Pakistan as environmentally sensitive (National Parks/Sanctuaries/Game
Reserve), b) Areas of International significance (e.g. protected wetland as designated
by the Ramsar Convention), or c) Areas designated by the United Nations
Educational, Scientific, and Cultural Organization (UNESCO) as cultural heritage
sites.
According to Sindh Environmental Protection Agency Regulation, 2014, a proponent
of a project falling in any category listed in Schedule II shall file an EIA with the Sindh
Environmental Protection Agency, since the listed projects are generally major
projects and have the potential to affect a large number of people.
The proposed project falls under category J (Other Projects) of Schedule II, which
requires EIA before commencement of construction.
2.2 SINDH ENVIRONMENTAL QUALITY STANDARDS (SEQS), 2016
Sindh Environmental Protection Council (SEPC) first approved the SEQS in 2014.
The standards were later revised in 2016 and furnish information on the permissible
limits for discharges of municipal and industrial effluent parameters and industrial
gaseous emissions in order to control environmental pollution.
2.2.1 Air Quality Standards In pursuance of the statutory requirement under Clause (g) of sub-section (1) of
section (6) of the Sindh Environmental Protection Act, 2014, the Sindh Environmental
Protection Agency with prior approval of the Sindh Environmental Protection Council,
has published the SEQS for Ambient Air (amended) 2016, which are given in Table
2.1.
Section–2 Policy, Legal and Administrative Framework EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-4 July, 2016
Table 2.1: Ambient Air Quality Standards
# Pollutant SEQS
Time-Weighted average Concentration standard
1 SO2 Annual average 80 µg/m3
24 hours 120 µg/m3
2 NO Annual average 40 µg/m3 24 hours 40 µg/m3
3 NO2 Annual average 40 µg/m3
24 hours 80 µg/m3
4 O3 1 hour 130 µg/m3
- -
5 Suspended Particulate
Matters (SPM)
Annual average 360µg/m3
24 hours 500 µg/m3
6 PM10 Annual average 120 µg/m3
24 hours 150 µg/m3
7 PM2.5 Annual average 15 µg/m3
24 hours 35 µg/m3 1 hour 15 µg/m3
8 Lead Annual average 1 µg/m3 24 hours 1.5 µg/m3
9 CO 8 hours 5 mg/m3 1 hour 10 mg/m3
SEQS= Sindh Environmental Quality Standards 2.2.2 Noise Quality Standards In pursuance of the statutory requirement under clause (g) of sub-section (1) of
section (6) of the Sindh Environmental Protection Act, 2014, the Sindh Environmental
Protection Agency with prior approval of the Sindh Environmental Protection Council,
has published the SEQS for Noise (2015). These standards are established for the
four different categories which include residential area, commercial area, industrial
area and silent zone. These standards vary according to the day and night timing;
day time hours are 6:00 am to 10:00 pm and night time hours are 10:00 pm to 6:00
am. Sindh Environmental Quality Standards for Noise effective from January, 2015
are used for bench marking purpose and given in Table 2.2.
Table 2.2: Noise Quality Standards
# Category of Area SEQS (dBA)
Day Time Night Time 1 Residential Area 65 50
2 Commercial Area 70 60
3 Industrial Area 80 75
4 Silence Zone 55 45
Section–2 Policy, Legal and Administrative Framework EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-5 July, 2016
2.2.3 Drinking Water and Wastewater Quality Standards In pursuance of the statutory requirement under clause (g) of sub-section (1) of
section (6) of the Sindh Environmental Protection Act, 2014 the Sindh Environmental
Protection Agency with prior approval of the Sindh Environmental Protection Council,
has published the National Standards for Drinking Water Quality, domestic Sewerage
and wastewater effluent.(2016).
Table 2.3: SEQS for Drinking Water Quality
Sr.No. Parameters Concentration Standards
SEQS (mg/L)
Chemical Parameters
1 Aluminum (Al) < 0.2
2 Ammonium (NH3) -
3 Antimony (Sb) < 0.005
4 Arsenic (As) < 0.05
5 Barium (Ba) 0.7
6 Boron (B) 0.3
7 Cadmium (Cd) 0.01
8 Chloride (Cl) < 250
9 Chromium (Cr) < 0.05
10 Copper (Cu) 2
11 Cyanide (CN) < 0.05
12 Fluoride (F) < 1.5
13 Iron (Fe) -
14 Lead (Pb) < 0.05
15 Manganese (Mn) < 0.5
16 Mercury (Hg) < 0.001
17 Molybdenum (Mo) -
18 Nickel (Ni) < 0.02
19 Nitrate (NO3) < 50
20 Nitrite (NO2) < 3
21 Selenium (Se) 0.01
22 Silver (Ag) -
23 Sodium (Na) -
24 Sulphate (So3) -
25 Residual Chlorine 0.2-0.5
26 Zinc (Zn) 5.0
Section–2 Policy, Legal and Administrative Framework EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-6 July, 2016
Sr.No. Parameters Concentration Standards
SEQS (mg/L)
Physical Parameters
27 Color < 15 TCU
28 Taste Non Objectionable/ Acceptable
29 Odour Non Objectionable/ Acceptable
30 Turbidity < 5 NTU
31 Total hardness < 500 mg/l
32 TDS < 1000
33 pH 6.5-8.5
Biological Parameters
34 E-Coli Must not be detectable in any 100 ml sample
35 Total Coliforms Must not be detectable in any 100 ml sample
Table 2.4: SEQS for municipal &Liquid Industrial Effluents (mg/l)
Sr. No.
Parameter Into Inland Waters
Into sewage
Treatment
Into Sea
1 Temperature 400C or Temperature increase*
≤3oC
≤3oC ≤3oC
2 pH value (H*) 6-9 6-9 6-9 3 Biochemical Oxygen Demand (BOD)5
at 20oC 80 250 80**
4 Chemical Oxygen Demand (COD) 150 400 400 5 Total Suspended Solids (TSS) 200 400 200 6 Total Dissolved Solids (TDS) 3500 3500 3500 7 Oil and Grease 10 10 10 8 Phenolic compounds (as phenol) 0.1 0.3 0.3 9 Chloride (as CT) 1000 1000 SC***
10 Fluoride (as F) 10 10 10 11 Cyanide (as CN) total 1.0 1.0 1.0 12 An-ionic detergents (as MBAS) 20 20 20 13 Sulphate (S04
2) 600 1000 SC*** 14 Sulphate (S2) 1.0 1.0 1.0 15 Ammonia 40 40 40 16 Pesticides 0.15 0.15 0.15 17 Cadmium 0.1 0.1 0.1 18 Chromium (trivalent and hexavalent) 1.0 1.0 1.0 19 Cooper 1.0 1.0 1.0 20 Lead 0.5 0.5 0.5 21 Mercury 0.01 0.01 0.01
Section–2 Policy, Legal and Administrative Framework EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-7 July, 2016
22 Selenium 0.5 0.5 0.5 23 Nickel 1.0 1.0 1.0 24 Silver 1.0 1.0 1.0 25 Total toxic metals 2.0 2.0 2.0 26 Zinc 5.0 5.0 5.0 27 Arsenic 1.0 1.0 1.0 28 Barium 1.5 1.5 1.5 29 Iron 8.0 8.0 8.0 30 Manganese 1.5 1.5 1.5 31 Boron 6.0 6.0 6.0 32 Chlorine 1.0 1.0 1.0
2.3 OTHER RELEVANT LAWS
2.3.1 Canal and Drainage Act, 1873 This Act entails provisions for the prevention of pollution of natural or man-made water
bodies.
2.3.2 The Forestry Act 1927 The Forestry Act 1927 provides rules and regulations for the protection of forests,
control of timber and other forest-produce transit, village forest and social forestry.
This act has been comprehensively formed and provides concerned agency the
power to declare protected and reserved forests by government notification, powers
entitled to forest settlement officers, power to acquire land over which right was
claimed, powers to stop ways and water-courses in reserved forests, healing of
claims relating to shifting cultivation, power to issue and publish notification to
reserve trees, power to make rules for protected forests, power to declare forest no
longer reserved, order on rights of pasture or transit forest-produce, record keeping
by the forest settlement officer, commutation of right to appeal, time limit for
resolution of claims and appeals, notification of acts prohibited in such forests
(unlawful cutting of trees) and awarding penalties on violations.
2.3.3 Provincial Wildlife (Protection, Preservation, Conservation and
Management) Acts, Ordinances and Rules (Act, 1972) The Act empowers provincial wildlife departments for the creation of three classes of
special protected areas: national parks, wildlife sanctuaries, and game reserves. It
classifies wildlife by degree of protection, i.e, animals that may be hunted on a permit
or special license, and species that are protected and cannot be hunted under any
circumstances.
Section–2 Policy, Legal and Administrative Framework EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-8 July, 2016
2.3.4 Sindh Wildlife Protection Act, 1974 Sindh Provincial Assembly passed the “Sindh Wildlife Protection Act” in 1974. The
Act provides protection, conservation, preservation and management of wildlife and
is applicable on entire areas of Sindh.
The Act regulates the issuance and validity of licenses and permits to public or
V.I.Ps, trapping or shooting near Game Reserves or Sanctuaries, empowering the
government officers to warranting, seizure or inspection of any person or hunting
equipment at any given time, prohibition of cooking of wild animals/birds meat in any
public place, as well as providing a set of fee structure for various permits including
hunting, trapping, possession or import and export of wild animals/birds.
2.3.5 Pakistan Penal Code, 1860 This defines the penalties for violations concerning pollution of air, water bodies and
land.
2.3.6 Pakistan Explosives Act, 1884 This Act provides regulations for the handling, transportation and use of explosives
during quarrying, blasting and other purposes.
2.3.7 Antiquities Act, 1975 The Antiquities Act of 1975 is designed to protect antiquities from destruction, theft,
negligence, unlawful excavation, trade, export and other cultural resources in
Pakistan. The act defines antiquities as ancient products of human activity, historical
sites, or sites of anthropological or cultural interest, national monuments, etc. The law
prohibits new developments in the proximity of a protected antiquity and empowers
the Government of Pakistan to prohibit excavation in any area that may contain such
articles of archaeological significance. Under the Act, the project proponents are
obligated to ensure that no activity is undertaken within 61 m (200 ft) of a protected
antiquity, and to report to the Department of Archaeology, Government of Pakistan
any archaeological discovery made during the course of the project.
2.3.8 Pakistan Clean Air Program
The Pakistan Clean Air Program (PCAP) is an initiative of the Pakistan
Environmental Protection Agency (Pak-EPA) to comprehensively address the air
quality issue in the country. Key elements of the PCAP include an Air Quality
Monitoring Program, Air Quality Indicators, Research Program, Air Quality Resource
Section–2 Policy, Legal and Administrative Framework EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-9 July, 2016
Centre, Regulatory Measures, Economic Instruments, Emissions Inventory, Air
Dispersion Models, and Air Quality Abatement Technology Clearing House.
The objectives of the program are to: Protect and enhance the quality of the country’s
air resources; Protect public health and welfare against any actual or potential
adverse effects that may reasonably be anticipated to accrue from air pollution;
Preserve, protect, and enhance the air quality in urban areas and the countryside
and in areas of natural, recreational, scenic, cultural, or historic value, in particular,
the protected areas of the country, i.e., national parks, wildlife sanctuaries, game
reserves, and national monuments.
Ensure that economic growth will occur in a manner consistent with the preservation
of existing clean air resources; Assure that emissions from any source in any
province do not interfere with pollution prevention programs in any other province;
and Assure that Pakistan’s international obligations regarding the trans-boundary
effects of air pollution are met.
2.3.9 Pakistan Guidelines for Public Consultation, (October 1997) These guidelines deal with possible approaches to public consultation and
techniques for designing an effective program of consultation that reaches out to all
major stakeholders and ensures the incorporation of their concerns in any impact
assessment study. These guidelines cover: Consultation, involvement and
participation of stakeholders; Effective public consultation (planning, stages of EIA
where consultation is appropriate); and Facilitation involvement (including the poor,
women and Non-Governmental Organizations (NGOs).
2.3.10 Cutting of Trees Act, 1975
This Act prohibits cutting or chopping of trees without permission of the Forest
Department. The act presents fine or imprisonment or both, for illegal cutting of tree
but has not mentioned any compensatory afforestation. However, it’s a common
practice to plant 7-10 trees for compensation of 1 tree to be rooted up.
2.3.11 Hazardous Substance Rules, 2003
These Rules make provisions for the granting of licences for the collection, treatment,
storage, importation, transportation, etc. of hazardous substances.
They consist of 22 Rules and 5 Schedules. Substances prescribed as hazardous
substances are listed in Schedule I. An Environmental Impact Assessment (EIA) of
Section–2 Policy, Legal and Administrative Framework EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-10 July, 2016
the project involving hazardous substances shall accompany the application to obtain
a licence (Rule 5).
Rules 7 and 8 deal with the issuance of licences, along with the conditions and
requirements of obtaining licensees. Packaging and labelling provisions are outlined
in Rule 9. General safety precautions and precautions for workers are covered in
Rules 11 and 12, respectively. Provisions on the validity, renewal and cancellation of
licences are set out in Rules 13-15, respectively. Authorized staff of the Federal
Agency/Provincial Agency is entitled to enter and inspect the premises in which
hazardous substances are generated, collected, treated, disposed of, stored etc.
(Rule 16).
Safety plans and waste management plans shall be submitted to the Provincial
Agency (Rules 17-19). Details to be provided for the application to licences for the
importation and transportation of hazardous substances are given in Rules 20 and
21, respectively.
2.3.12 Disaster Management Act, 2010 This act declares the establishment of Pakistan's multi-tiered system for disaster
management.
The act is divided into eleven sections:
- Section 01 defines the terms used in the act, such as 'disaster' and 'disaster
management';
- Section 02 declares the establishment of the National Disaster Management
Commission, and explains its structure and responsibilities;
- Section 03 declares the establishment of a Provincial Disaster Management
Commission for each province, and explains its structure and responsibilities;
- Section 04 declares the establishment of a District Disaster Management
Authority for each district, and explains its structure and responsibilities;
- Section 05 explains the various measures that the government is prepared to
take for the purpose of disaster management;
- Section 06 explains the functions of local authorities in terms of disaster
management;
- Section 07 declares the establishment of the National Institute of Disaster
Management, and explains the Institute's responsibilities in research and training;
- Section 08 declares the establishment of a National Disaster Response Force for
more specialized management of disaster events;
Section–2 Policy, Legal and Administrative Framework EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-11 July, 2016
- Section 09 explains how the sources of funding the government use to finance
the new disaster management projects;
- Section 10 warns of the punishments for those who abuse the disaster
management system; and
- Section 11 discusses other important factors of the disaster management
projects, such as a policy against discrimination and a plan for developing an
annual disaster management report.
2.3.13 Seismic Building Code of Pakistan, 2007 The objective of the provisions described in this code is to prescribe the minimum
requirements for the earthquake design and construction of buildings and building-
like structures and/or their components subjected to earthquake ground motions.
2.3.14 Land Acquisition Act, 1894 The Pakistani law governing land acquisition is the Land Acquisition Act (LAA) of
1894 and successive amendments. The LAA regulates the land acquisition process
and enables the provincial government to acquire private land for public purposes.
Land acquisition is a provincial responsibility and provinces have also their own
province specific implementation rules like Punjab and Sindh Land Acquisition Rules,
1983. The LAA and its Implementation Rules require that, following an impact
identification and valuation exercise, land and crops are compensated in cash at the
current market rate to titled landowners. The LAA mandates that land valuation is to
be based on the last 3 to 5 years average registered land-sale rates.
2.3.15 Occupational Health, Labor Laws (Amended) Ordinance, 1972 Construction and operational activities can affect the occupational health of the
workers. Quantitative national standards with respect to the above aspect are yet to
be developed in Pakistan. However, guidance in qualitative terms can be obtained
from the Labor Laws (Amended) Ordinance, 1972.
2.3.16 Toxic Or Hazardous Waste, Pakistan Penal Code (PPC), 1860. Environment Protection Agency, Sindh
Protection of the environment with regards to toxic and hazardous waste is covered
by the Pakistan Penal Code (PPC), 1860. Environment Protection Agency, Sindh, is
mandated to monitor the transportation of hazardous materials within the provincial
limits.
Section–2 Policy, Legal and Administrative Framework EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-12 July, 2016
2. 3.17 Preservation of Cultural Heritage, The Antiquities Act, 1975,
The Antiquities Act, 1975, administered by the Provincial Government, is aimed at
safeguarding the preservation of cultural heritage, destruction, damage or
defacement of antiquities is an offence under the Act.
2.4 POLICY FRAMEWORK
The Federal and Provincial Ministries dealing with the Environment are responsible
authorities for policy making on environmental protection in Pakistan and respective
provinces.
2.4.1 National Environment Policy, 2005 In March 2005, the GOP launched its National Environmental Policy, which provides
an overarching framework for addressing the environmental issues. Section 5 of the
policy commits for integration of environment into development planning as
instrument for achieving the objectives of National Environmental Policy. It further
states in clause (b) of subsection 5.1 that EIA related provisions of Environmental
Protection Act, 1997, shall be diligently enforced for all development projects. It also
provides broad guidelines to the federal government, provincial governments,
federally administered territories and local governments to address their
environmental concerns and to ensure effective management of their environmental
resources.
2.4.2 National Resettlement Policy, 2002 In March, 2002 Pakistan Environmental Protection Agency (PEPA), GoP issued its
National Resettlement Policy, which explains the basis for compensation,
rehabilitation and relocation of the affectees. It also explains the requirements and
implementation of Resettlement Action Plan (RAP). The Policy still is in the draft form
and has not yet passed Cabinet approval.
2.4.3 National Power Policy, 2013 The Ministry of Water and Power of the Government of Pakistan has developed an
ambitious power policy to support the current and future energy needs of the country.
This bold strategy has been developed to set Pakistan on a trajectory of rapid
economic growth and social development. Simultaneously, it addresses the key
challenges of the power sector in order to provide much needed relief to the citizens
of Pakistan. This policy has been designed to frame the broad contours of the energy
Section–2 Policy, Legal and Administrative Framework EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-13 July, 2016
policy articulating the vision for the power sector, highlighting its key challenges,
setting major goals, summarizing policy principles, and highlighting the strategy
devised to achieve Pakistan’s aspirations. The policy does not elaborate on issues
surrounding operational strategy, nor does it lay out detailed implementation plans.
The process of policy and strategy formulation is informed by the following organizing
principles:
a) Efficiency;
b) Competition; and
c) Sustainability.
2.5 ADMINISTRATIVE FRAMEWORK
2.5.1 Port Qasim Authority (PQA) The project falls under administration of Port Qasim Authority (PQA). The
management of PQA will ensure that all the proposed measures are effectively
implemented at the design and construction stages. PQA will be responsible for the
operation and maintenance.
2.5.2 Sindh Environmental Protection Agency (SEPA) Sindh Environmental Protection Council is the apex inter-ministerial and multi-
stakeholders decision-making body, which is headed by the Chief Minister. While
Sindh Environmental Protection Agency is meant for the enforcement of
environmental laws in Sindh, it has powers to review, approval and monitoring of
environmental examination/assessment projects. As regards the proposed Project,
Sindh EPA shall be responsible for reviewing the report, issuing No Objection
Certificate (NOC) and overall/broad-based monitoring of the proposed project
activities.
Section–3 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 3-1 July 2016
SECTION –3
DESCRIPTION OF THE PROJECT
3.1 RATIONALE OF THE PROJECT
The total power generation in the country, after completion of Chashma Hydro Power
Plant, stands at 15,746 MW as per information from National Transmission and
Dispatch Company Limited (NTDCL). Current deficit of power supply is around 7000
MW which results in load shedding throughout the country.
The future power demand for Pakistan is projected through National Power System
Expansion Plan which provides load forecast. The future demand, even with a low
growth scenario, in years 2019-20 and 2029-30 is estimated as 42,612 MW and
82,457 MW respectively. The situation is, therefore, alarming and needs an
immediate and efficient solution. The GoP is working to attract investment of
adequate quantum into the power generation platform.
Coal, being considered as an economical power generation source, is seen as a
major source for fuelling power generation plants. Coal fired power generation, based
on imported coal, at supercritical and pulverized coal is a viable option for meeting
future demand.
However, necessary infrastructure for efficient transportation of bulk coal cargoes
does not exist in Pakistan. The proposed project will provide an important link in the
establishment of coal transportation infrastructure. The project derives its need from
being an integral part of imported coal based power projects.
Port Qasim is Pakistan’s main deep sea port located on the coastline of the Arabian
Sea. Port Qasim is the second largest port of Pakistan that handles 45% of national
cargo.
Port Qasim Authority (PQA) does not have any dedicated coal handling facility at
present. However, limited quantity of coal is being handled at Marginal Wharf Berths.
Pakistan Steel is handling coal for its own use through Iron Ore and Coal Berth
(IOCB). A new facility is being developed at PIBT for handling coal, clinker & cement
Section–3 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 3-2 July 2016
up to 12.0 Million tonnes per annum (MTPA). The locations of the above mentioned
facilities are shown in Figure 3.1.
3.2 EXISTING COAL HANDLING FACILITIES AT PORT QASIM
3.2.1 Marginal Wharf Berth Facility Marginal Wharf berths 1 to 4 have shallow draft (up to 9m) and as such, only small
vessels of 25,000 to 35,000 DWT can be berthed. No facility is available to transport
the coal to existing railway siding located to the north of the Marginal Wharf Berths 1
to 4.
The coal from Marginal Wharf is transported to a temporary stock pile located in
Term Storage Area-A&B of Port Operation Zone. From the stock piles, the coal is
being transported to up-country through trucks and railway.
However, due to low draft and non-availability of requisite equipment, coal cargo
handling capacity at Marginal Wharf is constrained and bulk handling cannot take
place.
3.2.2 Iron Ore and Coal Berth (IOCB) Ships up to 50,000 DWT can be berthed at the Iron Ore and Coal Berth. This berth
can handle cargo of up to 3.03 MTPA with ship to shore un-loaders of 1,000 tonnes /
hr. The Coal from IOCB is transported to Steel Mill Plant through 3.9 km long belt
conveyor.
Bulk handling facility of IOCB can be made available after necessary repair and
maintenance for coal handling. However, IOCB cannot be considered for the coal
unloading terminal of this project because of the on-going privatization process of
Pakistan Steel Mills.
3.2.3 Pakistan International Bulk Terminal (PIBT) A dedicated terminal is being constructed at Port Qasim to handle coal, clinker and
cement by M/s. PIBT on BOT Basis. Under the present Implementation Agreement,
PIBT will handle cargo including coal, up to 8.0 MTPA. However, PIBT has plans to
expand its terminal for handling cargo up to 12.0 MTPA. In the backup area of the
terminal, 1.0 million tonnes of coal can be stacked.
pJIO.l!Cf'!
CONVEYING SYSTEM FROM PIBT COAL TERMINAL TO EXISTING RAILWAY NETMJRK
AT PORT QASIM
PORT QASIM AUTHORITY
CCINIUL.TANT:
••• NATIONAL ENGINEERING SERVICES
.... PAKISTAN (PVI) LIMITID
::..'7"��/n��
��,1� E-tMil:.....,......Rl.ftllfll
EXISTING COAL HANDLING
FACILITIES AT PORT QASIM
FIOURE No. 3.1
Section–3 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 3-3 July 2016
Two ships of up to 55,000 tonnes will be able to simultaneously berth at PIBT. The
facility will be capable of accommodating large ships up to 75,000 DWT after
widening and deepening of PQA Navigation Channel. At present, PIBT plans to
transport coal from its stockyard to power plants located in the vicinity of Port Qasim
by using trucks for which it is developing the requisite facility.
At the completion of PIBT terminal two ships of upto 55,000 tonnes will be able to
simultaneously berth at PIBT. The facility will be capable of accommodating large
ships up to 75,000 DWT after widening and deepening of PQA Navigation Channel.
The project is scheduled for completion in December 2016; PIBT at Port Qasim will
be first link in the supply chain of imported coal for the power plants.
3.3 TRANSPORT OF COAL FROM PIBT TO COAL FIRED POWER PLANTS
There are essentially two modes of transport those can be employed for the
transportation of coal from PIBT to the power plants.
3.3.1 Transport of coal by road:
This is seen to be practical mainly for local power plants situated closer to Port
Qasim as the large number of trucks required to transport coal to plants located in
other parts of the country would significantly increase truck traffic in the port area as
well as:
- Increased traffic & congestion on highways
- Increased pollution from large number of trucks
- Increased demand for diesel to run the trucks
- Possibility of greater number of accidents
- Increased pollution from the loading and unloading activities
- Increased pollution from coal transportation by road
- Massive wear and tear of road infrastructure due to movement of heavy
vehicles
- Increase in maintenance cost of the road network
3.3.2 Transport of coal by rail: This is considered to be a safe and efficient method of bulk coal transportation over
long distances and is suitable for supply to power plants in other parts of the country.
- Reduced pollution from mechanized loading and unloading activities
Section–3 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 3-4 July 2016
- Reduced pollution from coal transportation by train
- Reduced truck traffic due to bulk transport through trains
- Reduced traffic & congestion on highways thus reduced number of
accidents.
- Low demand for diesel to run the trains
- Less road wear and tear
Pakistan Railway has informed PIBT that railway link cannot be constructed up to
PIBT Terminal due to existing ground condition. Hence, a transportation link is
needed between PIBT and railway track in North West Industrial Zone (NWIZ) of Port
Qasim. To meet this requirement the Government of Pakistan (GoP) has decided to
connect the PIBT with existing railway network at Port Qasim with a belt conveyor.
GoP directed Port Qasim Authority to develop the connectivity of PIBT with existing
railway network by laying a coal conveying system upto existing railway tracks.
The main railway tracks are located on northern side of Port Qasim in NWIZ. Two
tracks link Karachi to other parts of the country. These tracks are also being used for
freight trains as reported by Pakistan Railways.
A single track exists on west of NWIZ which connects Port Qasim Marginal Wharf
Berths to Pipri Marshalling Yard and is connected onward with the main railway lines
Pakistan Railways has plans to lay one additional railway track along the existing
Pakistan railway track at Port Qasim to meet the demand for transport of coal and
other cargo from Port Qasim to up-country. Pakistan Railways track in the NWIZ of
Port Qasim is 4.5 km away from PIBT.
In view of operational and commercial aspects, PIBT has no dedicated facility to
stock the coal meant for transport through Pakistan Railways. PIBT can transport the
coal outside of its terminal by extending its conveying system, which can deliver coal
up to PQA transfer station to be located outside the PIBT back-up area. From
transfer station coal can be transported to coal stockyard, which shall be located near
existing railway track in the PQA.
Section–3 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 3-5 July 2016
3.4 COAL CONVEYING SYSTEM FROM PIBT TO EXISTING RAILWAY NETWORK
The absence of direct railway link to PIBT necessitates a material flow scheme for
coal transfer activity from ship to railway wagons.
As per the conceived project scheme for the transport of coal from PIBT to coal
stockyard to be constructed near existing railway track, coal will be unloaded from
the sea vessels at PIBT. PIBT will deliver coal at the PIBT boundary where coal will
be taken up by PQA’s coal conveyor via direct connectivity.
PQA’s coal conveyor will bring the coal to a coal stockyard near existing railway
track. The stockyard will be equipped with bucket wheel stacker and reclaimed, with
these machines coal will be stacked in stock piles. Reclaiming of coal from stockyard
will be performed by a re-claimer and coal will be loaded on a coal conveyor for
transportation to the load out station at the railway network for loading on railway
wagons.
Transportation of coal from the coal loading area in Port Qasim to various power
plants in the country shall be performed by Pakistan Railways.
Conceived working scheme for the coal conveying is shown in the Figure 3.2
The proposed Coal Conveying System from PIBT to Existing Railway Network
includes:
A) Covered Coal Belt Conveyor from PIBT to Coal Stockyard located existing
Railway Network
B) Stacking & Reclaiming Coal at Coal Stockyard
C) Transfer of Coal from Stockyard to Rapid Load-out Station
D) Loading of Coal from Rapid Load-out Station to railway wagons
3.4.1 Transfer of Coal from PIBT to Coal Stockyard
Direct connectivity will be provided from within PIBT to a transfer station just outside
PIBT from where a covered coal conveyor will take the coal to the new coal
stockyard near the existing railway track.
Capacity of the conveyor belt will be equal to the rate of unloading of coal from the
vessel at jetty using two (02) unloaders at a rate1,800 tonnes/hr each, i.e.,
Section–3 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 3-6 July 2016
simultaneous discharge rate of 3600 tonnes/hr. The belt will be around 5 Kms long
and 1800mm wide. It will run at a speed of 3.5 m/s with the help of electrically driven
motors.
Troughed belt conveyors will be as of ISO standards but designed generally in
accordance with B.S. 2890 (latest): Efficient and readily accessible means of
adjustment will be provided on the head and tail drum shafts for tracking the belt. The
belt conveyor structure will be designed to allow easy and simple access for
maintenance and replacement of idlers. Design will be such as to ensure correct
tensioning of the belt under all conditions. Removable protective screens or covers
will be provided around back weights and pulleys.
Transfer chutes at transfer stations will be provided which are necessary for the
effective transfer of coal from one conveyor belt to another. Chutes will be completely
enclosed and be supplied with a dustproof hinged inspection door for inspection and
cleaning. Transfer chute sides will be designed so that material will not build-up
inside the chute and cause an obstruction to material flow. The design will be such
that the commodity will not spill over moving parts. No apertures or ridges will be
present in order to prevent spillage or build-up of material.
All receiving hoppers that are necessary for the effective receipt of product will be
provided. Hoppers will be so designed and installed that no dust will escape when
commodity is received in the hopper. The opening at the bottom of hoppers will be
completely dust sealed on the receiving chute of the conveyor. The sides of hoppers
will be so designed that material will not build up in the hopper and cause an
obstruction to material flow.
R.C.C foundation and steel structure for the conveyor belt, transfer stations and load-
out station will be provided. Similarly, necessary rail tracks including foundation
structure for the equipment will be provided for the installation and operation of
stacker and reclaimer.
3.4.2 Coal Stockyard Various options were considered to transport the coal from PIBT to existing railway
network. Initially, it was considered that coal which is to be transported through
railway will be stacked in PIBT coal stockyard.
Section–3 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 3-7 July 2016
PIBT had informed that it cannot allocate dedicated coal stockyard for coal meant to
be transported through railway as it apprehended that in case of breakdown of PQA’s
conveying system / equipment or railway operations, PIBT’s stockyard operation may
be adversely impacted.
Considering the remote location of PIBT with respect to the existing railway track
where the proposed load-out station is to be established and also taking into account
efficient stock yard management, it was concluded that a separate coal stockyard,
near railway track, would offer a more practical solution.
The capacity of coal stockyard mainly depends on the rate of stacking and reclaiming
the coal from stock pile. The reclamation from stockyard to load out station / railway
sidings depends upon the handling capacity of Pakistan Railway. Pakistan Railway
has informed that it can handle 2400 tonnes of coal per train and that it can run
20freight trains a day on its main lines which include 5 trains per day for the Sahiwal
Power Plant.
For rapid loading of coal into railway wagon, a load-out station at railway loop
adjacent existing railway track is proposed. The capacity of the load-out station is
proposed to be 2400 tonnes/hr. considering a train speed of 0.5 to 0.8 km/hr under
the load-out station. Keeping in view the loading process of coal into the railway
wagons based on this proposal, the reclamation rate at stockyard will be 2400
tonnes/hr.
The stockyard will have eight (08) stockpiles each of 55,000 tonnes of coal. Each
stockpile will be 50 m wide and 115 m long. The height of the stockpile is proposed to
be 12.5 m. In first phase stacking area will be developed only for four (04) stockpiles
to handle coal up to 4.0 million and the remaining area for four (04) stockpiles will be
developed as demand arises. The conceptual layout of coal stockyard is shown in
Figure 3.3.
Keeping in view the operational requirements and capacity of train, two (02) bucket
wheel stacker/reclaimer machines having stacking capacity of 3600 tonnes/hr and
reclaiming capacity of 2400 tonnes/hr will be provided in the stockyard.
Coal stacking area will have two rows for piling of coal and coal stacker/reclaimer will
run on each side. Each row will be designed to accommodate 110,000 tonnes of coal
Section–3 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 3-8 July 2016
in two (02) equal numbers of stock piles. Two (02) rows of stock piles are kept for
future expansion.
In the coal stockyard Bucket wheel Stacker Reclaimer (BWSR) will be utilized to form
coal stockpiles. The BWSR will be rail mounted and of slewing & luffing type. The
machine will be operated by electric power which will be supplied through high
voltage power source via trailing cables or by machine mounted self-power electric
generator set(s). The coal will be fed through belt conveyor preferably mounted at-
grade (ground) level which will be routed through for stacking.
A tripper will be connected to the travelling stacker who serves to transfer material
from the longitudinal stockyard conveyor onto the boom conveyor. The luffing motion
is often done by hydraulic cylinder and counter weigh by concrete counterweight.
BWSR will be able to serve at various travel speeds and can be quickly relocated
from one end of the stockpile to another. BWSR has been envisaged to be used for
reclaiming the material from the stockpile. The reclaimed material from the stockpile
will be transferred onto the dispatch /feed conveyor belt for loading onto the waiting
train to be filled via coal load-out station located at the railway siding.
The operator's cabins location will be such so as to allow a clear and unobstructed
view of the operations of stacking, reclaiming and loading of coal. The cabins will be
air-conditioned and ergonomically designed for maximum comfort of the operator.
The information display screen would display details of all operations enabling the
operator to program according to the loading requirement.
3.4.3 Transfer of Coal from Stockyard to Rapid Load-out Station Bucket Wheel Stacker Reclaimer (Figure 3.4) will be used to reclaim coal from
stockpiles at the rate of 2400t/hr and transfer it to secondary belt conveyor. The belt
conveyor will transport coal from stockyard to rapid load-out station. The belt will be
1500mm wide. It will run at a speed of 3.5 m/s with the help of electrically driven
motors.
3.4.4 Loading of Coal from Rapid Load-out Station to railway wagons Rapid precision & intelligent train loading (Rapid Load-out Station) system is the
most advanced train loading system today. It can weigh and load material
continuously and automatically per the applicable weight restrictions. This large scale
system, which can be used at ports or wharfs as well, is suited for loading various
bulk materials such as coal, ore, cement and grains into the wagons.
Section–3 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 3-9 July 2016
The rapid load out station with the loading capacity of 2400 t/h and loading accuracy
of 0.01% per train, will consist of a storage silo (surge bin), a bin below the storage
silo (weighing bin) and a loading chute (Figure 3.5). The rapid load-outstation will be
mounted directly above the rail track. The rake (train of empty coal wagons) will be
moving below the loading chute with uniform speed while weighed material in the bin
will be discharged into the wagons at a controlled rate to ensure uniform loading of
the coal in the wagons.
The Control System will be an internationally renowned Digital Field bus technology
with complete alarming function. Three (3) control modes will be provided including
automatic, semi-automatic and manual modes with flexible statistic reporting
function. Digital signals will be transmitted with strong anti-interference capability.
Each coal train (Rake) will consist of 40 wagons (15 meter length each) of ZBKC type
(with side discharge) having a capacity of 70 tonnes taking a payload of 60 tonnes.
The desired loading capacity from rapid load out station is 2400 tonnes per rake with
loading time of 40~60 seconds per wagon. The scheme is shown on Figure 3.3, 3.6
& 3.7.
3.5 SITE SELECTION FOR NEW COAL STOCKYARD FOR COAL CONVEYING UPTO RAILWAY NETWORK Different potential sites have been studied to develop a coal stockyard from where
coal can be conveyed to a rapid load-out station for loading railway wagons.
3.5.1 Site Selection Criteria for New Coal Stockyard Following factors were considered for site selection and development of coal
stockyard.
a) Availability of adequate parcel of land along the existing railway track
b) Access to site
c) Minimum changes in the existing natural environment
d) Relocation of any existing utilities
e) Proximity to rapid load-out station
f) Suitability of land with respect to topographic and sub-soil conditions
g) Capital and O & M cost of conveying system.
·-.....
·----
18.1
·-1GHAROC REEK
Mt.JD
LAYOUT PLAN
FROM PIBT JETTY
Plll>,/&Gll
CONVEYING SYSTEM FROM PIBT COAL
Tl:RIIINAL TO EXISTING RAILWAY NETWORK AT PORT QASIII
PORT QASIM AUTHORITY
CONVEYING SYSTEM
FOR COAL STOCK YARD
TO LOAD OUT STATION
FIGURE No. 3.7
Section–3 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 3-10 July 2016
3.5.2 Studied Sites for New Coal Stockyard Following four (04) sites with respect to above site selection criteria were studied for
coal stockyard (Figure 3.8).
Site-1: This site is located in the east of PQA North-West Industrial Zone (NWIZ) and
existing railway track. The land is owned by Pakistan Steel Mills (PSM) and as such
acquisition of land for development of stockyard by PQA will be required. A large
natural drain (nallah) traverses through the site. To access the site from the western
side a crossing over the railway tracks and construction of two (02) bridges over the
existing nallah will be required. At this site, a railway loop having radius of 250m can
be developed for movement of coal trains (Figure 3.8).The available land is plain and
even. Currently the land is being used as open yard for the storage of old materials
by PSM. Keeping in view the current and future requirements for development of coal
stockyard and railway loop the land available at this site is sufficient.
Site-2: This site is located near PQA South-West Industrial Zone (SWIZ). To the east
of this site, Pakistan Railways track exists, whereas on the west PQA Main Access
Road is located (Figure 3.8). The land is reserved for a flyover which is planned to be
constructed at Main Access Road to connect the Main Access with the road network
of North-West Industrial Zone (NWIZ). The topography of the land comprises of
uneven terrain and ground levels vary from 7m to 22m. One high tension line also
crosses this area. Due to the un-even topography of the area, construction of coal
stockyard and required railway track, load-out station will involve relocation of high
tension line and also considerable earth work. Furthermore, conveyor route from
PIBT to the stockyard at this site will require crossing of existing trestles of FOTCO &
SSGC Terminals and the conveyor supporting structure and access road would need
to be built in tidal zone. The site is spread on an area of 75 acres only area required
for the future development is not available at site. Site-3:An area of 53 acres of land, without any permanent construction, is located in
North-Western Industrial Zone (NWIZ) on west side of existing railway track (Figure
3.8).The site is fairly leveled and graded no significant earth work will be required.
The site is also easily accessible from existing road network and very close to the
railway line. The conveyor and load-out station can be easily connected with the
stockyard developed at this site. But the land is owned by a private party and is
spread over only 54 acres of land which is insufficient for future development.
Section–3 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 3-11 July 2016
Site-4: An area of 78 acres of land is available to the north of PIBT terminal back-up
area. It has been informed by PQA that 36 acres of land will be made available by
PQA for the coal stockyard (Figure 3.8). This site is fairly levelled and graded and as
such no major earth work is expected to be required. Sub-soil conditions at this site
are, however, relatively poor and will require improvement. The site is accessible
from the existing road network in PQA area.Site-4 is located to the north of PIBT but
is far away (approx. 4.5 km) from the existing railway track. It can be connected with
PIBT conveyor system directly and a short conveyor of 2700 tonnes/hr will be
required for coal transportation from PIBT to new coal stockyard. The onward
conveying system from new coal stockyard to rapid load-out station will require a
conveyor of smaller capacity and hence, will reduce overall capital costs. However,
the long length of conveyor, as well as its continuous operation, to feed the rapid
load-out station will increase O & M costs.
Keeping in view the operation strategy for handling different types of coal for various
power plants, it is advantageous to have the coal stockyard located near the rapid
load-out station for the following reasons:
i) Easy management of coal loading and dispatch as different types of coal can
be stocked close to the rapid load-out station and allow quick change over
from one stockpile to other as coal requirement for each power plant may be
different.
ii) There will be a short feeding conveyor from stockyard to rapid load-out station
and it will be easy to empty the conveyor quickly after one train load has been
dispatched.
iii) The main belt conveyor from PIBT to the stockyard will only be operational
when ships are being unloaded at PIBT. The belt conveyor can then be shut-
down till unloading of next ship at PIBT. This will reduce the environmental
problems and cost of operation and maintenance.
iv) Operation and maintenance staff will be able to monitor / control the
stockyard and load-out station with ease as both facilities will be located near
each other. Site 1 and 3 are both suitable sites for development of the
stockyard with respect to the connections with existing railway and road
network. Site 1 also offers the opportunity to have a loop arrangement for
railway tracks which will facilitate train movement and future development.
Site 2 is considered unsuitable due to reasons discussed above. Site 4 is
located away from the proposed load-out station and is not suitable due to the
reasons discussed above.
Section–3 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 3-12 July 2016
Keeping in view the site selection criteria, merits and demerits of studied sites
discussed above, Site 1 is most suitable site for the construction of new coal
stockyard.
3.6 ROUTE SELECTION FOR COAL CONVEYOR FROM PIBT TO NEW STOCKYARD
Different routes for the coal conveyor from PIBT to proposed new coal stockyard
have been studied.
3.6.1 Route Selection Criteria for Coal Conveyor Following factors were considered for route selection and development of coal
conveyor.
a) Location of first coal transfer station near PIBT (starting point)
b) Location of new coal stockyard and load-out station (end point)
c) Minimum changes in the existing natural environment
d) Relocation of existing utilities
e) Topography of the area
f) Geotechnical conditions
g) Availability of R.O.W
h) Physical features and impediments along the route
i) Turning points along the route
j) Access roads for the inspection and maintenance of conveyor belt
3.6.2 Studied Routes Various routes were studied to identify the most feasible route of coal transportation
from PIBT to new coal stockyard. The routes studied are shown in figure 3.9 and
described below;
Route-1: This route starts from the first coal transfer station near PIBT and runs
along the existing Road-A located on western boundary of Port Qasim’s North- West
Industrial Zone (NWIZ) area then turns toward east along Road-B located on north
side of PAPCO and FOTCO installations and then goes straight to the proposed
stockyard (site 1) near existing railway track. The conveyor belt under this route will
run under the HT line &cross the railway track. H.T lines are high and will not
interfere with the belt structure.
I
.:-1I
. \� •? [_ -.. -
ROUTE-4 (LENGTH = 4.9km)
REEK
PLAN
FROM PIBT JETTY
Plll>,/&Gll
CONVEYING SYSTEM FROM PIBT COAL
TERMINAL TO EXISTING RAILWAY NETWORK AT PORT QASIM
PORT QASIM AUTHORITY
t:a'l!ULTAIIT!
ROUTES FOR
COAL CONVEYING SYSTEM
FIGURE No. 3.9
Section–3 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 3-13 July 2016
There is only one turn along this route, therefore; only one (01) intermediate transfer
station will be required. The length of this route is around 4.5 km. The topography of
this route is fairly leveled & graded except the first 700m where the gradient varies
from 5% to 7%. Availability of land is not expected to be an issue as sufficient space
is available along either side and also within the median of the existing roads. The
sub-soil conditions along this route are known to be fairly good, except in the area
near PIBT, and as such shallow foundations can be provided for the supporting
structure. Keeping in view the above, the route is considered suitable for laying the
conveyor belt.
Route-2: Along this route, the conveyor may be laid on western boundary along
Road-A after which it will turn to Road-C located on north of SSGC backup area. The
route then goes straight to proposed coal stockyard (site 1) near existing railway
track. Since load-out station can only be located in middle of straight portion of
existing track, the route, therefore, runs parallel to railway track up to proposed load
out station (Figure 3.9). The length of this route is around 4.85 km. There are three
(03) turnings on this route and hence, three (03) intermediate transfer stations will be
required. The conveyor structure will cross under the high tension power lines and
FOTCO road. Re-location of high tension power lines and construction of bridge over
FOTCO road will be required. The part of route which is located between PQA Main
Access Road and proposed stockyard (site 1) consists of hilly/broken ground and will
require extensive earthwork for constructing road/track to enable access during
operation and maintenance of conveyor. Availability of ROW along the railway track
is another issue because a number of underground utilities are located along existing
track. The construction of supporting structure for the conveyor will take considerable
time along this route due to the poor sub-soil condition in the initial portion, uneven
terrain, relocation of high tension power lines, other utilities along the railway track
and construction of bridge crossing over FOTCO access road.
Route-3: The route starts from first coal transfer station near PIBT and runs along
Road-D located just north of PIBT backup area. It then turns towards north along
Road-E located adjacent to SSGC trestle and west on Road-F located north of SSGC
backup area. The route then goes straight to proposed stockyard after which it runs
along the existing railway track up to load out station. The length of this route will be
around 5.3 km. There are three (03) turnings on this route, therefore; three (03)
intermediate transfer stations will be required. The conveyor on this route will cross
Section–3 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 3-14 July 2016
under H.T lines at two locations and it will also cross the existing FOTCO road where
bridge structure will be required.
The ROW along the existing road is available but ROW beyond PQA Main Access
Road up to existing railway track is to be acquired. The topography up to existing
road is generally leveled and graded except the portion between PQA Main Access
Road and proposed stockyard site which is hilly and will require considerable earth
work to access the conveyor during operation and maintenance. The geological
condition will be same as mentioned for Route-1.
Route-4: The conveyor can be laid straight from the first coal transfer station near
PIBT in an eastward direction to proposed stockyard (site 1) near existing railway
track. The length of this route will be around 4.9 km. The route runs along the
existing road on north of PIBT backup area and goes straight to railway track then
turns toward north along the railway track up to proposed location stockyard. There
are two turnings on this route; therefore, two (02) intermediate transfer stations will
be required. The conveyor will need to cross existing trestles of SSGCLPG Terminal,
FOTCO Oil Terminal, PQA Main Access Road and high tension power lines.
The topography of this route is not favorable as it is located in the tidal zone the
access to the conveyor during maintenance and operation will be required. Time
required for the relocation of the existing H.T line and construction of supporting
structure along with the access road in tidal zone will be significantly more than other
three routes.
Based on the above comparison and selection criteria, Route-1 seems to be most
feasible route for the conveyor from PIBT to proposed coal stockyard and load-out
station near railway track.
3.7 LOCATION OF THE PROJECT
Project is located in the North West Industrial Zone (NWIZ) of Port Qasim Industrial
Estate and in the west side of PSM adjacent to the existing railway track which is 4.5
km away from PIBT. (Figure 3.10)
Section–3 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 3-15 July 2016
3.8 PROJECT ADMINISTRATIVE JURISDICTION
Project is located in the Port Qasim Area and Port Qasim Authority (PQA) will
execute the project. A Project Director will head the Project Management Unit (PMU)
from PQA. The team of PMU will consist of technical and professional staff.
3.9 PROJECT IMPLEMENTATION SCHEDULE
Construction work of the proposed project is scheduled to be completed within Nine
(09) calendar months from the Date of Commencement of Construction work at Site.
3.10 COST OF THE PROJECT
The estimated construction cost of the infrastructure development works for coal
conveying system is approximately Rs.16 billion.
3.11 CONSTRUCTION MATERIALS
The construction materials used in the construction of coal conveying infrastructure
construction project would include coarse/fine aggregates, steel, water, asphalt,
Portland and sulphate resistant cements etc. Aggregates and soil shall be
transported outside the project area, while the cement and steel will be procured from
other sources in Karachi. The other construction material suitable for construction of
coal conveyer infrastructure will be obtained from the nearby local quarry.
3.12 CONSTRUCTION CAMPS
Construction camp(s) will be selected keeping in view the availability of adequate
area for establishing camp site, including parking areas for machinery, stores and
workshops, access to communication and local markets, an appropriate distance
from sensitive areas in the vicinity. Final locations will be selected by the contractor
with in consultation with PQA
3.13 MANPOWER REQUIREMENTS
The manpower requirement during construction and operation of the project will be
about 150 personnel including managerial staff, skilled and unskilled labour and
manpower requirement of about 30 people for Design Phase.
Section–3 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 3-16 July 2016
3.14 CONSTRUCTION EQUIPMENT
The following are the machinery and equipment required for the proposed project is
provided in Table 3.1.
Table 3.1: Machinery and Equipment Requirement for the Proposed Project S. No. Type of Machinery and Equipment
1 Dump Trucks 2 Front End Loaders 3 Dozers 4 Graders 5 Vibratory Rollers 6 Pneumatic Tyre Rollers 7 Sheep Foot Rollers 8 Three Wheel Rollers 9 Tandem Rollers
10 Water Tankers 11 Concrete Batching Plant 12 Concrete Transit Mixers 13 Concrete Pumps 14 Excavators 15 Water Pumps 16 Cranes 17 Generators 18 Asphalt Distributors 19 Welding plants 20 Air compressors 21 Steel cutters 22 Tailors
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-1 July 2016
SECTION – 4 ENVIRONMENTAL BASELINE PROFILE
The baseline for project area was established considering physical, biological and
socio-economic aspects along the project area. The information of environmental
parameters was gathered from government departments, through review of literature,
and site visits. In addition to this, consultations were held with the general public and
major stakeholders of the project area in order to seek the public opinion on the
implementation of the proposed project. Designed questionnaires and focus group
discussions were used to interview stakeholders for their concerns and suggestions
about the proposed project.
4.1 PHYSICAL ENVIRONMENT
The physical environment includes topography, regional geology, soils, climate,
hydrology, drainage, seismology, surface water, groundwater, ambient air quality,
dust monitoring and noise levels.
4.1.1 Topography & Geography Port Qasim is located, adjacent to the Bin Qasim town, in the southern part of Malir
district, Karachi division, in Sindh. It is located in an old channel of the Indus River at
a distance of 35 kilometres east of Karachi city center.
The geographic position of the Port Qasim places it in close proximity to major
shipping routes. The approach to the port is along a 45-kilometre long Navigation
Channel which provides safe navigation for vessels up to 75,000 tones dead weight
(DWT).
The existing site is fairly leveled and already developed. Furthermore, the future
development is planned according to the international standards for the design of
coal conveyor, stockyard and load-out station and allied structures.
4.1.2 Geology and Soil Karachi lies approximately 150 km east of the triple junction between the Arabian,
Indian and Asian plates. The rocks found in the area sedimentary in origin and were
laid down in shallow marine conditions. They range in age from Eocene to recent.
Inter bedded sandstone and sandy shale have been found in the area. The rocks are
overlain by unconsolidated mixture of gravels, sand, silt and clay.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-2 July 2016
A total of thirteen (13) boreholes were of varying depths were drilled at different
areas of the site in order to evaluate the foundation conditions for the proposed
project.
The locations of these boreholes were fixed in such a manner as to cover all the
major structure locations as per the available layout at the time of field investigations.
(a) Stratum of brown silty fine to coarse sand with trace gravels is found mostly as
first soil unit having maximum depth of 10 m. In some of the boreholes clayey silt /
silty clay forms the upper stratum.
(b) Light brown poorly graded fine / coarse sand with silt is present in medium dense
to very dense state at various depths.
(c) Below the alluvial soils, grayish brown mostly loose sandstone intermixed with
shale and mudstone is found starting from various depths to maximum
Investigated depth of 30 m. The shallowest depth encountered is 6 m.
(d) It is expected that groundwater will not affect the foundation preparations for the
proposed track.
(e) For the placement and compaction of the embankment and engineered fill,
granular material should be used.
(f) It is recommended that the subgrade should be properly prepared to meet the
deign CBR.
(g) An experienced geotechnical engineer / engineering geologist should thoroughly
inspect the area and should remain involve in fill placement and compaction for
subgrade and other foundations.
(h) All the areas that will support the track, should be properly cleared, grubbed by
removing any topsoil / fill and wet, soft or loose soils.
(i) It is recommended to adopt peak ground acceleration (PGA) of 0.16g to 0.24g for
the design of the structures.
(j) It is recommended to use Sulphate Resisting Cement (SRC) or other suitable type
in concrete construction works according to requirement.
4.1.3 Climate and Meteorology Temperature
Due to proximity to the sea, the city of Karachi has little variation in average
maximum and minimum temperatures. The average annual temperatures during
summer are 26oC to 35oC (up to 42oC in May/June), whereas temperature ranges
between 10oC to 27oC during winter. Day and night temperature also varies
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-3 July 2016
considerably as the sea breeze in the afternoon rapidly decreases day time
temperatures.
Humidity and Rainfall Humidity levels experience a drop usually in the month of October while the lowest
levels occur in March or April. The highest humidity levels generally occur during the
month of August.
The meteorological station at Karachi Airport collects climatic data. Rainfall near the
Karachi coast is extremely low and erratic and this region falls in the semi-arid
climatic zone. Heavy rains exceeding 50mm (sometimes 100mm) in a day are
common in north-eastern humid and sub-humid parts of Pakistan and Kashmir which
is known as the gateway of the monsoon for the country. However, such events only
occasionally occur in the south where the climate is mainly arid.
Table 4.1 to 4.3 shows the temperature, humidity, wind speed and wind direction
monitored at Site-1 NWIZ water pumping station PQA, Site-2 Pharm Evo and Site-3
PIBT Stockyard from June 27, 2016 to June 28, 2016 by SUPARCO Laboratory
respectively. The temperature was found in the range of 30 – 37 0C at Site-1, 27 – 37 0C at Site-2 and 25 – 34 0C at Site-3. The maximum value of humidity recorded at
Site-1 is 79 0C and 94 0C at Site-2 & Site-3. The predominant directions are North-
East at average speed of 3.1 m/s, North-West at average speed of 3.9 m/s and
North-West at average speed of 3.3 m/s at Site-1, Site-2 and Site 3 respectively. The
Calm wind was observed most of the time at Site-3. Figure 4.1 to 4.3 are the
graphical representation of the wind direction at Site-1, Site-2 and Site-3.
Table 4.1: Meteorological Data (24-hr.) at NWIZ Water Pumping Station PQA
Time Ambient Temperature
Co
Wind Direction (Degree)
Wind Speed
m/s
Humidity %
12:00 36 90 5.1 44 13:00 37 90 3.6 39 14:00 36 200 4.1 47 15:00 35 135 4.1 53 16:00 35 135 4.1 53 17:00 33 180 5.1 55 18:00 33 135 4.6 55 19:00 31 160 4.6 66 20:00 31 180 3.6 66 21:00 31 200 4.1 66 22:00 30 200 2.1 74 23:00 30 200 2.1 74
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-4 July 2016
Time Ambient Temperature
Co
Wind Direction (Degree)
Wind Speed
m/s
Humidity %
00:00 30 115 1.5 74 01:00 30 70 1.0 74 02:00 30 70 1.5 74 03:00 30 23 2.1 74 04:00 29 23 2.1 74 05:00 29 359 2.6 79 06:00 30 23 3.1 70 07:00 31 70 1.5 66 08:00 32 70 2.1 59 09:00 33 45 2.1 55 10:00 36 90 3.6 41 11:00 36 90 5.1 41
Figure 4.1: Wind rose at NWIZ Water Pumping Station PQA
Table 4.2: Meteorological Data (24-hr.) at Pharm Evo, PQA
Time Ambient Temperature
Co
Wind Direction (Degree)
Wind Speed
m/s
Humidity %
13:00 36 180 6.2 44 14:00 37 225 6.2 39 15:00 35 180 3.6 53 16:00 34 180 5.1 56 17:00 33 315 7.2 59 18:00 30 330 2.6 79 19:00 31 340 2.6 75
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-5 July 2016
Time Ambient Temperature
Co
Wind Direction (Degree)
Wind Speed
m/s
Humidity %
20:00 27 23 17 94 21:00 25 330 3.1 94 22:00 27 315 2.6 84 23:00 28 340 3.1 84 00:00 28 340 2.1 84 01:00 28 330 2.6 84 02:00 29 330 4.6 84 03:00 29 45 1.0 79 04:00 28 45 1.5 84 05:00 28 70 2.1 89 06:00 28 45 2.6 89 07:00 29 70 2.1 84 08:00 31 70 4.6 75 09:00 31 90 2.6 75 10:00 33 115 2.6 66 11:00 33 180 2.6 75 12:00 34 180 3.6 59
Figure 4.2: Wind rose at PharmEvo, PQA
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-6 July 2016
Table 4.3: Meteorological Data (24-hr.) at PIBT
Time Ambient Temperature
Co
Wind Direction (Degree)
Wind Speed
m/s
Humidity %
14:00 33 330 9.3 66 15:00 25 45 3.1 94 16:00 28 359 3.6 84 17:00 28 45 1.5 84 18:00 29 330 1.0 79 19:00 29 315 2.1 79 20:00 29 315 3.6 74 21:00 30 Calm 74 22:00 29 45 2.6 78 23:00 29 Calm 84 00:00 28 340 2.6 89 01:00 28 Calm 89 02:00 28 Calm 89 03:00 28 Calm 89 04:00 28 270 2.6 89 05:00 28 Calm 89 06:00 28 Calm 94 07:00 29 315 4.6 89 08:00 30 359 4.6 84 09:00 31 Calm 79 10:00 33 250 3.1 66 11:00 34 Calm 63 12:00 34 270 1.5 63 13:00 34 180 4.1 52
Figure 4.3: Wind rose at PIBT
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-7 July 2016
4.1.4 Seismicity Karachi has been established in a moderate earthquake zone. Pakistan was divided
into five seismic zones in line with UBC97. The boundaries of these zones are
defined on the following basis:
Zone 1 0.05 to 0.08g
Zone 2A 0.08 to 0.16g
Zone 2B 0.16 to 0.24g
Zone 3 0.24 to 0.32g
Zone 4 > 0.32g
Where g is the ground acceleration and its unit is in Gal. Figure 4.4 shows the
seismic zoning Map of Pakistan.
Sindh Building Control Authority (SBCA) has placed Karachi in Zone-2 B based on
the actual events, the past observations of fault movement and other geological
activities. Karachi is situated in a region where moderate earthquakes may occur of
magnitude 5.0 to 6.0 equivalents to intensity between VII and VIII on Modified
Mercallis Scale (M).
As per building code of Pakistan, Seismic Provisions 2007, the project area falls in
Zone 2B of the Seismic Zoning Map of Pakistan. The project structures should
therefore be designed to cater for the ground acceleration of 0.16 g to 0.24 g.
Figure 4.4: Seismic zoning map of Pakistan
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-8 July 2016
4.1.5 Water Resources and Drainage The existing bulk water supply system conveys water to Karachi from two main
sources, namely, Indus River through Kalri Baghar Feeder and Hub Dam across Hub
River.
Karachi has been receiving its water supply from the Indus River since 1957 when
the quota for urban supplies in Karachi from the River Indus was sanctioned. This
allowed Karachi to take 450 cusecs (242 mgd or 1,100,000 m3/d) from 16 October to
15 April (Rabbi) and 520 cusecs (280 mgd or 1,270,000 m3/d) from 16 April to 15
October (Kharif) from the tail of the system at Kotri, through storage in Kinjhar Lake.
Later, a presidential decree in 1988 increased this quota to 1,200 cusecs (645 mgd
or 2, 940, 000 m3/d).
Urban and industrial water for Karachi is taken from the Kotri Barrage and discharged
through the Kalri Baghar Feeder Upper (KB Feeder Upper) to Kinjhar Lake. The right
(west) bank command of 310,000 ha (3,100 km2) gross is supplied by a single canal:
the KB Feeder which also supplies Karachi 150 km west southwest of the off‑take.
The KB Feeder Upper has a design capacity at its head of 9,075 cusecs (22, 300,000
m3/d) and terminates at the head of Kinjhar Lake. This is also the off take for the
Right Bank Link Canal which, since it was opened in 1982, has enabled water from
the KB Feeder Upper to be supplied directly to the KB Feeder Lower without passing
through the lake. This allows unsettled silty water to be supplied to downstream
irrigators and also serves to reduce sedimentation of the lake.
The Hub Dam is a multi‑purpose dam (municipal, industrial and irrigation purposes)
constructed on the Hub River approximately 50 km to the northwest of Karachi City.
The construction of the dam started in September 1963 and completed after 18 years
in September 1981. The construction of the Lasbela Canal and Hub Main Canal was
completed in September 1981 and September 1982 respectively. The catchment
area of the dam extends across two provinces namely Sindh and Baluchistan
covering a total area of 3,410 sq miles (8,730 km2). The water distribution network in
Karachi covers 18 towns, 6 Cantonments and the Defense Housing Authority (DHA)
Area. These 18 towns are included in 5 administrative water supply zones classified
by KW&SB, as shown in Figure 4.5. Water is supplied through water trunk mains
from water filtration plants, reservoirs, pumping stations or Dumlottee Wells in the city
of Karachi. Bin Qasim is included in Zone‑I and it receives its supply from a canal
that takes off from Gujjo Headworks.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-9 July 2016
Figure 4.5: Present Water Supply Zones of Karachi
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-10 July 2016
4.1.6 Creek System Hydraulics Port Qasim Entrance and Navigation Channels
The Port Qasim provides the second port facility for the country. The access to Port
Qasim / Phitti Creek is provided through Ahsan Channel, being maintained at 12.4 m
depth. Its maintained width increases in-shore from 185 m to 225 m. The 225 m wide
inner channel of Phitti Creek from Zulfiqar Bank to Hasan Point and of Kadiro Creek
from Hasan Point to the Iron Ore and Coal Berth is maintained at 11.3 m Berth.
Vessels of up to 25,000 tones can operate to Marginal Wharf where a depth of 10.0m
is maintained.
Tides and Currents The tides at Port Qasim are predominantly semidiurnal with a substantial diurnal
component. The Mean Higher High Water (MHHW) to Mean Lower Low Water
(MLLW) range is about 2.4 m at the port complex while the peak tide over diurnal
range is about 3.5 m. The tide levels at Port Qasim are presented in Table 4.4 below.
The flow pattern within this large, relatively deep and generally stable creek system
around Port Qasim is strongly influenced by tides and the presence of extensive
inter-tidal flats.
Tide levels at Port Qasim apply to Gharo Creek from Iron Ore and Coal Berth to
Marginal Wharf. The currents in Gharo Creek show a well-defined ebb bias. In the
channel, Ebb currents of up to 2m/s have been measured with corresponding flood
currents of up to 1m/s. The strong current corresponds to the large volume of tidal
flows.
Table 4.4: Tide Levels at Port Qasim
Sr. No.
Location MLLW MHLW MLHW MHH HAT LAT
1. Bundal Island +0.6 +1.2 +2.3 +2.9 N/A N/A
2. Hasan Point +0.6 +1.3 +2.8 +2.9 +3.4 +0.6
3. Phitti Creek 01.6 +1.4 +2.1 +3.4 +4.00 -0.6
4.1.7 Ambient Air Quality The ambient air quality for priority pollutants such as NO, NO2, SO2, CO, O3, PM10,
PM2.5 Total Suspended Particles (TSP) and lead was carried out at Site-1 NWIZ
water pumping station PQA, Site-2 Pharm Evo and Site-3 PIBT Stockyard from June
27, 2016 to June 30, 2016 by SUPARCO Laboratory. The monitoring period was
24 hours. Figure 4.6 shows a view of ambient air quality monitoring in the project.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-11 July 2016
area. The results obtained are tabulated under Table 4.5. The detailed monitored
results for air quality are attached as Annex –II respectively.
Figure 4.6: Ambient Air Quality Monitoring in the Project Area
Site-1 NWIZ water pumping
station PQA Site-2 PharmEvo Site-3 Start Point at PIBT
Table 4.5 Ambient Air Quality Test Results
Parameter Unit Monitoring Duration M
in.
Con
cent
ratio
n Li
mits
Average Obtained Concentration
Limits As Per SEQS
NWIZ water pumping station,
PQA
Pharm Evo, PQA
PIBT Stockyard
Nitrogen Dioxide (NO2)
µg/m3 24 Hours 1 10.1 11.8 10.5 120
(µg/m3) For 24 Hrs
Nitrogen Oxide (NO)
µg/m3 24 Hours - 3.9 5.6 4.4 40 (µg/m3)
Sulfur Dioxide (SO2)
µg/m3 24 Hours 1 5.3 10.5 9.7 120
(µg/m3) For 24 Hrs
Carbon Monoxide (CO)
mg/m3 24 Hours <0.5 0.4 1.8 0.9 5 (µg/m3) For 8 Hrs
Ozone (O3) µg/m3 24 Hours 1 7.2 8.6 10.3 130
(µg/m3)
Particulate Matter (PM10)
µg/m3 24 Hours 5 90 101.1 91.9 150
(µg/m3) For 24 Hrs
Particulate Matter (PM2.5)
µg/m3 24 Hours - 22 25.8 32 75 (µg/m3) For 24 Hrs
Total Suspended Particles (TSP)
µg/m3 24 Hours - 247 288 259 500
(µg/m3) For 24 Hrs
Lead µg/m3 24 Hours - ND 0.6 0.4 1.5
(µg/m3) For 24 Hrs
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-12 July 2016
µg/m3 : microgram per cubic meter mg/m3 : milligram per cubic meter ND : Not Detectable SEQS : Sindh Environmental Quality Standards
The above table indicates that the concentrations of all the parameters are well within
permissible limits of SEQS.
4.1.8 Air Dispersion Modeling of Particulate Matter Air dispersion modeling was conducted to find out the baseline air quality conditions
and to calculate the future projections. The major objectives for the Air Dispersion
Modeling are (i) to estimates the impact of emissions due to transportation, transfer
and storage of coal from PIBT to Coal storage yard and (ii) its compliance to Sindh
Environmental Quality Standards (SEQS) for PM10. USEPA developed an air dispersion regulatory model “AERMOD” (American
Meteorological Society/Environmental Protection Agency Regulatory Model) is a
steady state plume model which was used to estimate the impact.
The details of the modeling depict that the PM10 values will be within the permissible
limits of SEQS if proper mitigation measures will be adopted. The detail study is
attached as Annexure-IV.
4.1.9 Noise Level Noise level monitoring was carried out at the same locations where ambient air
quality was monitored. The Noise levels were found in the range of 42.1 – 57.7 dB
(A) at Site-1, 60.4 - 73.9dB (A) at Site-2 and 40.9 – 62.5 dB (A) at Site-3. Noise
levels were monitored with the help of a potable digital sound meter at the project site
for 24 (twenty four) hours. The detailed noise level monitored results are attached as
Annex–II respectively. Average values of noise levels are given in Table 4.6.
Table 4.6: Average values of noise levels
Site No. Sampling Locations
Maximum Concentration
Minimum Concentration
Average Concentration SEQS (dB)
(dB)
1 NWIZ water pumping station, PQA
57.7 42.1 47.7
80 2 PharmEvo, PQA 73.9 60.4 67.6
3 PIBT Stockyard 62.5 40.9 54.7
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-13 July 2016
It is evident from the results given in above table that the noise levels at the project
area are within the permissible limits of SEQS.
4.1.10 Drinking Water Quality Drinking water samples were collected from Site-1 Water Pumping Station, Site-2
Shrine of Baba Kamal and Site-3 China Camp located in the proposed site on June
27, 2016 by SUPARCO Laboratory (See Plate 4.3) and was analyzed for chemical
and microbiological parameters. The analysis results of groundwater samples are
compared with NSDWQ. The detailed monitored results for drinking water quality are
attached as Annex-II respectively. Table 4.7 shows the results of groundwater
analysis.
Figure 4.8: A General View of Water Sampling
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-14 July 2016
Table 4.7: Groundwater Analysis of the Project Area
Sr. No. Parameters Unit
Test Result
NSDWQ Sample-1 ( Water Pumping
Station)
Sample-2 (Shrine of Baba
Kamal) Sample-3
(China Camp)
Chemical Parameters 1 Turbidity (NTU) NTU 2.63 1.94 1.65 <5
2 pH pH unit 7.6 7.4 7.7 6.5 - 8.5
3 Color TCU 2 2 1 ≤15 4
Odor - Acceptable Acceptable Acceptable Acceptable
5 Taste - Acceptable Acceptable Acceptable Acceptable
6 Total Dissolved Solids mg/l 131 514 116 <1000
7 Total Hardness as CaCO3 mg/l 180 420 290 <500
8 Nitrate, Nitrogen (NO3) mg/l 0.025 0.037 0.018 ≤50
9 Nitrite, Nitrogen (NO2) mg/l *ND 0.010 *ND ≤3
10 Cyanide mg/l *ND *ND *ND ≤0.05
11 Chloride mg/l 37 103 28 <250
12 Chlorine Macro(Residual) mg/l 0.26 0.24 0.09 0.2-0.5
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-15 July 2016
Sr. No. Parameters Unit
Test Result
NSDWQ Sample-1 ( Water Pumping
Station)
Sample-2 (Shrine of Baba
Kamal) Sample-3
(China Camp)
13 Fluoride mg/l *ND 0.017 *ND ≤1.5
14 Arsenic (As) mg/l *ND 0.009 0.006 ≤0.05
15 Antimony (Sb) mg/l *ND *ND *ND ≤0.005
16 Aluminum (Al) mg/l 0.015 0.013 0.044 ≤0.02
17 Barium (Ba) mg/l 0.056 0.121 0.043 0.7
18 Boron mg/l 0.028 0.071 0.019 0.3
19 Cadmium (Cd) mg/l *ND *ND *ND 0.01
20 Chromium (Cr) mg/l 0.003 0.009 0.013 ≤0.05
21 Copper (Cu) mg/l *ND 0.035 0.021 2
22 Lead (Pb) mg/l *ND *ND *ND ≤0.05
23 Manganese (Mn) mg/l 0.014 0.029 0.012 ≤0.5
24 Nickel (Ni) mg/l 0.008 0.011 0.003 ≤0.02
25 Selenium (Si) mg/l 0.008 0.011 0.003 ≤0.01
26 Zinc (Zn) mg/l 0.089 0.161 0.124 5
27 Mercury (Hg) mg/l *ND *ND *ND ≤0.001
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-16 July 2016
Sr. No. Parameters Unit
Test Result
NSDWQ Sample-1 ( Water Pumping
Station)
Sample-2 (Shrine of Baba
Kamal) Sample-3
(China Camp)
Microbiological Parameters
28 Total Coliform Bacteria MPN 8 12 6 0 MPN
29 Fecal Coliform MPN 1 2 1 0 MPN
30 E.Coli Form MPN 7 10 5 0 MPN
31 Phenols, Total (Phenolic compounds) mg/l *ND *ND *ND -
The above table shows that concentration of Total Coliform Bacteria and Fecal Coliform are higher than the permissible limits of NEQS while all other parameters are within the prescribed limits of NEQS.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-17 July 2016
4.2 ECOLOGICAL ENVIRONMENT
The climate of Malir District is arid and it is densely populated with wide variety of
vegetation in the form of natural foliage consisting diversity bushes, shrubs, trees
including agricultural products such as crops, vegetables and fruits. According to
geographical study, the Malir district is also composed of open communities of
deciduous, xerophytic trees and shrubs. In the alluvial plains and calcareous hilly
area of the district 25 species of plains are found. Most of the species are of minor
importance and only few of them are dominant and wide spread. These are Prosopis
Juliflora, Prosopis Cineraia, Acacia Nelotica and Euphorbia Triucalli. The rapid
increases in the population of the city and to cater for its housing and commercial
requirements, some of the agricultural lands were also converted into business
centers, multi storey plazas and housing colonies.
The flora and fauna present in and around the proposed project site is described as follows:
4.2.1 Flora
a) Crops
The predominant crops of Malir green belt are Lucerne (Forage crop), vegetables
and fruits. Cultivation of food grains is very limited and is periodically, substituted by
most favoured crops, vegetables and fodder. Generally the best lands are cultivated
under vegetables and the next best are cultivated under fodder and orchards.
Multiple cropping is common on most lands. A statement showing area and
production of some crops is given below which pertains to Karachi division
Table 4.8: Area and Production Average Yield of Crops 1997-1998
Sr. No.
Crop Area
(Hectares) Production
(Tons) Yield per
Hectares (Kg)
1. Jowar (Sorghum Vulgare) 629 261 415
2. Wheat (Triticum sativum) 119 132 1109
3. Maize (Zea mays) 217 99 456
4. Sesame (Sesamum indicum) 48 14 292
5. Other pulses 52 21 404
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-18 July 2016
b) Trees The District Malir has a variety of trees parallel to the study area. Table 4.9 shows
the tree species found in and around the area including their Local and Botanical
names.
Table 4.9: Tree Species of the Project Area
Sr. No. Common Name Scientific Name
1 Neem Azadiraccta indica 2 Peepal Ficus religiosa 3 Kaner Thevetia nereifolia 4 Amaltas Laburnum anagyroides 5 Gul mohar Delonix regia 6 Sultana champa Calophyllum incophyllum 7 Algaroba Prosopis juliflora 8 khejri Prosopis cineraria 9 Kikar Acacia nilotica 10 aveloz Euphorbia triucalli 11 Peelu Salvadora persica 12 Rohida Tecomella undulata 13 Kapok bush Avervea javavica 14 Neutral Henna Senna obovata
The floral species located in the project area are very few mainly the xerophytic
shrubs/weeds were observed grown in the project area. The pylons for coal conveyor
belt will be installed/erected in the existing green belt located in the median of the
road where about 12 number of trees would be affected. These trees are poplar,
neem, molsary and kikar. Figure 4.9 is showing the floral species located in the
project area.
Figure 4.9: Floral species present in the project area
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-19 July 2016
c) Mangrove Forest Mangroves play an important role in the swampy ecosystems of the environment.
They accumulate silt, stabilize shoreline and prevent erosion of the coastline and
beaches. The Avicenna marina is the dominant species of the mangroves in the Indus
delta. The density of mangrove trees was estimated between 50-60/100m2. The
height of the individual tree within the established Avicenna marina habitat was
greater than 3m. This species grows by natural means of regression quite profusely
and does not require any artificial means.
Sediment erosion was observed at the site. Well established mangrove plantation
(mangrove trees of medium height i.e. > 2-3 m) were found under stress due to
eroding sediments in the channel.
4.2.2 Fauna In near past, Deer (Gazella benetti) Wolf (Canis lupus pellipes), Jackals (Canis
aureus) and Fox (Vulpes bengalenis) were found in abundance. Now days, these
wild animals can be seen only in the center of wild life development.
Among birds Indian Grey partridge, Chest-Nut-Bellied Sand Grouse, Rock Dove,
Indian Little Button Guail and Eurasian Roller are found in Malir District.
a) Marine and Benthic Fauna Being close the shoreline, Brittle star (Amphiurid), Annelida (Polychaeta), Mollusca
(Gastropods), Ostracods, Crabs (pinnotherid), False crabs, Hydrozoan, Sea
anemone, Amphipods, Nematoda, Tanaidacean and Shrim (Alpheus) are the benthic
species found in the project area.
b) Fish Predaceous, Croakers, Sharks, Carangids Breams, Perches, Sea Snakes, Dolphin
and Seagulls are some fishes that were observed in the project area.
c) Birds Grey Plovers (Pluvialis squatarola), Golden Plover (Pluvialis apricaria apricaria),
Lesser Sand Plover (Charadrius mongolus atriforns), Curlew (Numenius arquata
arquata), Bar Tailed Godwit (Limosa limosa limosa) and Terek Sandpiper (Xenus
cinerus) are the most common sight in the area.
4.2.3 Wetlands There are no significant wetlands in the study area.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-20 July 2016
4.2.4 Endangered Species There are no endangered species of flora and fauna in the Study Area.
4.2.5 Wildlife Sanctuaries and Game Reserves No wildlife sanctuary or game reserve is located in the vicinity of the study area.
4.2.6 Critical Habitats
No wild life sanctuary or game reserve (Critical Habitats) exists near the project area
or the study area and therefore it can be quantified that this project does not affect
any critical habitat as no critical habitat is located close to the project area.
4.3 SOCIO-ECONOMIC STRUCTURE
This section deals with the existing social conditions of the proposed project area.
During the desk/ office study, available reports/ documents were comprehensively
reviewed. A detailed site visit was conducted by the Consultants’ EIA team
(Sociologist and Environmentalist) to appraise the prevailing socio economic
conditions of the proposed project area and to assess the impacts (positive or
negative) on the local settlements and to achieve the project objectives, it is
imperative to study the prevailing socio-economic and socio cultural aspects of their
livelihood. During the field survey, interviews were conducted with the local residents
of the project area, pedestrians, shop keepers and fishermen at different places (Bin
Qasim Town, Bhains Colony, Korangi, Landhi Industrial Area, Rerhi Ghoth, Steel
Town and surrounding areas). Observations were made after giving consideration to
the desk/ office study results.
4.3.1 Malir District The proposed project area falls in the Malir District of Karachi division. The district
lies between 24°-45’ to 25°-37’ North latitude and 67°-06’ to 67°-34’ East longitudes
and it is bounded on the north by Dadu district, on the west by Karachi South,
Karachi Central, Karachi east Karachi west and Lasbeela district of Baluchistan
province, on the south by Thatha district and Arabian sea and on the east by Dadu
and Thatha districts. The map of the Malir District is shown below in the Figure 4.10.
Total area of district is 2268 square kilometers. Pakistan Steel mills, Chowkandi
Tombs and Karachi air Port are the places of interest of the Malir District.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-21 July 2016
Figure 4.10: The Map of Malir District
4.3.2 Study Area The study area falls in Malir Taluka of Malir District. Prominence of Malir came into
existence in 1856 when scheme for supplying of water to Karachi was developed and
Capitan D. Leezay discovered the source of water in dry belt of Malir River at
Dumlotee.
The area of the district is 2268 Sq. kilometre yielding a population density of 432.7 in
1998. The population of Malir district was 981.41 thousand in 1998 as compared to
429.57 thousands in 1981. The annual growth rate measured 4.98% during the 1981-
1998.
4.3.3 Political and Administrative Setup The project area falls in Malir District. Malir was an administrative district of Karachi
Division in Sindh, Pakistan. Malir District was abolished in 2000 and divided into
three towns namely Malir Town, Bin Qasim Town and Gadap Town. On 11 July 2011
Sindh Government restored again Malir District.
District Coordination Officer (DCO) is the highest ranked administrator of the district.
For the collection of revenue and administration, the districts are subdivided into six
Talukas, one of which i.e. Malir is Sub Division under a Sub Divisional Magistrate.
The other talukas are Bin Qasim Town, Ibraheem Haidri, Shah Mureed, Gadap,
Murad Mamon, Airport and Malir Cantonment.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-22 July 2016
4.3.4 Data Source/Methodology Data collection for socioeconomic study of the proposed project involved socio-
economic baseline survey of the proposed project area.
i) Primary Data Primary data was collected through socio-economic baseline survey. For the
selection of respondents simple random sampling technique was adopted and 100
households residing within the project area and in the vicinity of proposed project
were selected. After determining sample size, an interview schedule was developed
for the collection of baseline data. This interview schedule included the baseline data/
information (i.e. demographic characteristics, livelihoods, economic conditions,
quality of life and land acquisition) that is required for establishing the baseline study
and was collected during the socio economic baseline survey.
The socioeconomic baseline data was analysed by a software “Statistical Package
for Social Sciences” (SPSS), because it has an easier and quicker access to basic
functions and also useful to get the actual and accurate results of baseline data.
Spread sheet for baseline data of EIA was created in SPSS in the form of
quantitative data. After entering, checking, sorting, and transforming the data, the
basic operation, data analysis was taken place through descriptive analysis by
finding out the percentages and the frequencies of the respondent’s views in the form
of tables and charts/graphs. These percentages, frequencies and charts/graphs of
baseline data were automatically generated by this software.
ii) Secondary Data Secondary data was collected from following sources for socio economic baseline
survey
• District Census Report, 1998; and
• Provincial Population Census Report of Sindh 1998.
4.3.5 Demographic Characteristics of the Project Area The total population of Malir District was 981.47 thousand in 1998 as compared to
429.57 thousands in 1981recording an increase of 128.46 percent over the last
seven years i.e., during 1981-98.
The average annual growth rate of population in the district during 1981-1998 was
4.9 percent. If the population continues to grow at its percent rate i.e. 4.98 percent
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-23 July 2016
per annum, it will double in about every 14 years. The total area of the district is 2268
square kilometers, which gives population density of 432.7 persons per square
kilometer in 1998. Table 4.10 gives population, its intercensal increase and average
annual growth rate since 1981.
Table 4.10: Population and Intercensal Increase and Growth Rates since 1951
Description 1981 1998
Population (in thousands) 429.57 981.41
Intercensal Increase (Percent) - 128.46
Average Annual Growth Rate (percent) - 4.98 Source: DCR of Malir District, 1998
A) Household size Average household size of the district is 6.2 in 1998. if we compare rural / urban
areas the household size is 5.6 in rural and 6.8 in urban areas
B) Rural and Urban Distributions The rural population of the district is 321.00 thousands constituting 32.70 percent of
the total population in the district. The average annual growth rate of rural population
during 1981-1998 was 3.80 percent.
The urban population of the district was 660.00 thousand which constitutes 67.30
percent of its total district population. There are four urban localities in the district of
which District Municipal Corporation, Malir has a population of 447.00 thousands
followed by Gujro Town Committee with 134.54 thousands.
C) Religion The population of district is predominantly Muslims who constitutes 96.57 percent of
the total population; 96.51 percent in rural area and 96.60 percent in urban area. The
next higher percentage is of Christians with 2.08 percent followed by Hindu (Jati)
1.10 percent. While other minorities like Ahmadi, Scheduled Castes etc. are very
small in number. The following Table 4.11 shows percentage distribution of the total
population by religion.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-24 July 2016
Table 4.11: Percentage of Population by Religion
Religion All Areas Rural Urban Muslim 96.57 96.51 96.60
Christians 2.08 0.71 2.75 Hindu (Jati) 1.10 2.53 0.41
Ahmadi 0.18 0.15 0.19 Schedule Caste 0.03 0.07 0.01
Others 0.04 0.04 0.04 Source: DCR Malir District, 1998
D) Ethnic Structure Different tribes are settled in the district, majority of who are Muslim. Among Sindhis
the tribes settled here are Syed, Jokhia, Khaskheli, Palri, Bareja, Bhabra, Dhars,
Sirhindi Jamot and Mohannas. These tribes are landowners keep herds and do
fishing.
Among the Baloch, the tribes resides in the district are Kulmati, Jadgal, Gorgej, Hoot,
Vadela, Vashki, Zarzedagh, Tumpi, Lashari, Laghri, Khosa, Rindh, Brohi, Harani.
Characteristically, these people are hardworking and hospitable. The previously
mentioned tribes are engaged in land, service and business.
Among the Memons are Modaani, Chitrani, Bolani and Hamlani. The new settlers are
from India and have settled in this district after 1947. After the downfall of Dhaka, the
inhabitants from former East Pakistan migrated to this district.
Business and Industry allured a large number of persons from the rest of the country.
The majority among them are the Punjabis and the Pathans. A small proportion of
the Bengalis, the Burmese and the Meghwars are also settled in this district.
A small minority, which consists of Christians and Hindus, resides in Malir District.
E) Mother Tongue The mother tongue refers to the language used for communication between parents
and their children in any household. Sindhi as the mother tongue is spoken by 25.08
percent of the total population followed by Pushto and Punjabi sharing 20.67 and
17.46 percent respectively. Urdu, Baloachi and Saraiki are spoken by only 15.87,
8.51 and 2.36 percent of the population. While remaining people speak other
languages for communication. The following Table 4.12 gives detail on percentage of
population by mother tongue being spoken in rural and urban areas in 1998.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-25 July 2016
Table 4.12: Percentage of Population by Mother Tongue and Rural/Urban Areas, 1998.
Area Urdu Punjabi Sindhi Pashto Balochi Siraiki Others All Areas 15.87 17.46 25.08 20.67 8.51 2.36 10.06
Rural 6.21 10.56 58.44 4.09 15.25 0.00 5.45 Urban 20.57 20.81 8.87 28.72 5.23 3.50 12.31
Source: DCR Malir District, 1998
F) Gender Ratio Number of males for every 100 females was 126.80 percent recorded in 1998
Census in the district. The ratio was 114.60 percent in rural areas and it was 133.21
in urban areas.
G) Marital Status The population of 15 years and above was classified into never married, married,
widowed and divorced. Out of them 35.15 percent of the total population were never
married, 60.98 percent married 3.66 percent widowed and 0.21 percent divorced.
The percentage share of never married male was much higher than that of females,
being 41.31 percent and 26.47 percent respectively.
H) Migration The total number of life time in-migrants in Malir district was 354516 or 36.12 percent
of the total population in the district. They are 16.65 percent in rural and 45.59
percent in urban areas. The male and female in-migrants are 38.45 and 33.29
percent respectively. The persons, who have migrated into the district after March,
1993 are 33.16 percent, while 24.49 percent had migrated before 1993 but after
1988.
Out of total in-migrants, 4.22 percent migrated into the district as a result of
marriages, 53.86 percent moved with head, 16.57 percent due to business and 13.05
percent as a result of employment / transfer. Table 4.13 throws light on life time in-
migrants with their decomposition by place of origin and settlement in rural and urban
areas of the district.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-26 July 2016
Table 4.13: Life Time Migrants in the District by Rural/ Urban Areas, 1998
Place of Previous Residence
All Areas Rural Urban
All Areas 357,516 (100)
53,431 (100)
301,085 (100)
Sindh 31.43 42.63 29.44 KPK 9.45 5.78 10.11 Punjab 22.05 26.69 21.22 Baluchistan 4.98 0.67 5.74 Islamabad 0.02 0.00 0.02 FATA 1.16 0.13 1.34 AJK/NA 1.03 1.75 0.90 Other Countries 5.27 3.78 5.53 Not Reported 24.62 18.56 25.70
Source: DCR of Malir District, 1998
Size of immigrants with the province i.e., 31.43 percent belongs to Sindh while 22.05
percent migrated from Punjab, 9.45 percent from KPK and 4.98 percent from
Baluchistan as well as a significant proportion i.e. 5.27 percent had repatriated from
other countries. However, 24.62 percent had not reported their previous place of
residence.
4.4 ECONOMIC CONDITIONS
a) Economically Active Population of the Malir District The economically active population comprises the persons of either sex who are
engaged in some kind of work for pay or profit including unpaid family helpers as well
as the un-paid persons who are not working but looking for work as well as laid off,
during the reference period. The economically active population of the district as
enumerated in the last census was 23.73 percent of the total population or 33.22
percent of the population aged 10 years and above. The percentage of children
below 10 years was 28.59 while 8.28 percent were students. Further details can be
seen in Table 4.14.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-27 July 2016
Table 4.14: Percentage (%) of Population by Economic Categories, Gender and Rural/Urban Areas, 1998
Economic Category
All Areas Rural Urban Both
gender
Male Female Both Sexes Male Female Both
Sexes Male Female
Labour Force 23.73 40.90 1.95 22.53 40.35 2.10 24.31 41.16 1.86 Not in Labour Force 76.27 59.10 98.05 77.47 59.65 97.90 75.69 58.84 98.14
Children below 10 Years 28.59 26.54 31.30 29.81 28.80 30.98 28.00 25.39 31.47
Domestic Workers 30.52 2.42 66.13 32.26 2.65 66.18 29.67 2.31 66.11
Students 8.28 14.48 0.41 8.93 16.30 0.47 7.96 13.66 0.38 All Others 8.89 15.74 0.21 6.48 11.90 0.27 10.06 17.48 0.17 Un-Employment Rate
18.99 19.55 4.01 22.32 23.27 1.24 17.49 17.89 5.66
Labour Force Participation Rate
33.22 55.62 2.83 32.09 56.67 3.04 33.76 55.16 2.72
Source: DCR of Maliri District, 1998
b) Unemployment Unemployment rate is the percentage un-employed persons including those not
looking for work and laid off to the total economically active population in the district.
The unemployment rate is 18.99 percent, which was mainly due to unemployment
amongst males representing 19.55 percent, while female unemployment rate was
just 4.01 percent. This is because of their small proportion in total economically
active population. The unemployment rate in urban areas is 17.49 percent and 22.32
percent in rural areas.
c) Employed Population by Occupation Of the total employed population in the district 56.12 percent is in the major
occupation Group-9 “Elementary Occupations”. The next higher occupation group
comprising 15.63 percent is of Skilled Agriculture and Fishery Workers followed by
“Professionals” constituting 10.07 percent and then “Plant and Machine Operators
and Assemblers” sharing 4.37 percent.
In rural areas most of the employed persons i.e. 51.77 percent are associated with
Group-9 “Elementary Occupations, followed by “Service Workers, Shop and Market
Sale Workers” at 19.47 percent. In urban areas, as high as 57.96 percent is engaging
in “Elementary Occupations”, followed by Service Workers and Shop and Market
Sales Workers at 13.88 percent and Professionals at 12.82 percent.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-28 July 2016
d) Industry, Trade and Trade Centers The district is prominent from industrial point of view. The large industries established
here which is about 15.3 percent of the entire Karachi is. These manufacturing
industries are of textiles, food, pharmaceuticals, iron and ceramics. The famous are
Daud Mills, Firdous Mills, Nagerya Mills, Gul Ahmed Mills, Metropolitan Steel Mills,
General Tyre and Trust Ceramics.
Pakistan Steel, the largest steel mill of the country is situated in this district. The mill
has a capacity of producing 1.1 million tonnes of steel.
Malir is also the most important Centre of handicrafts and cottage industries.
Amongst others the main cottage industries are carpet, zari (gold/silver), embroidery
etc.
There is no major trade Centre in the district, however Quaid Abad is to be
considered as local market. In this market besides food items basic commodities of
life are available.
4.5 TRANSPORTATION Roads The district has an adequate communication network. Besides numerous roads
connecting the district with other parts of the district two major Highways passes
through this district: Super Highway and National Highway. Lengths of Super
Highway and National Highway passing through the district are about 50 and 35
kilometers respectively.
Railways The district is also connected with Railways. Main Railway Lines connecting Karachi
with up country passes through this district and its distance within the district is about
50 kilometers.
International Airport Karachi International Airport is situated in this district which is the biggest in the
country in terms of size and passengers handled. The National and International
Airlines connects Karachi with rest of the country and with the others countries.
A view of Karachi International Airport has been shown in the following Figure 4.11.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-29 July 2016
Figure 4.11: A view of Karachi International Airport
Port Bin Qasim In order to ease the burden of Karachi harbor, a new port at Bin Qasim (in Malir
District) has been built. This port in mainly used for bulk cargo and particularly
serving for shipment of Steel Mills. A view of Karachi Bin Qasim Port has been
shown in the following Figure 4.12.
Figure 4.12: A view of Karachi Bin Qasim Port
4.6 HEALTH FACILITIES
There are only 5 dispensaries and 3 maternity homes in the district; whereas on
private sector there are numerous hospitals and dispensaries well-equipped with
modern technological equipment needed for treatment of diseases.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-30 July 2016
4.7 EDUCATION
The district being a part of Karachi metropolis, as such all type of education facilities
are available. Though the district has one medical university in private sector,
however, the remaining districts of Karachi division fulfill this shortage providing the
facility of higher studies in Government universities like the Karachi University. The
NED University of Engineering and Technology, Sindh Medical College and Dow
Medical College of Sindh Government as well as Agha Khan Medical College and Sir
Syed University of Engineering and Technology in private sector.
Institute of Computer Science (FAST), Pakistan Swedish Institute of Technology and
Cadet College in Gulshan-e-Hadeed are the institutions of national repute which are
located in the district.
A statement showing number of educational institutions and enrollment of students in
the district during 1997-98 is given below in Table 4.15.
Table 4.15: Number of Schools and Enrollment of Students, 1997-98
Primary Secondary High Degree Others
Institute/Enrolments 120 24 05 12 35
No of Students 15746 8306 2960 15458 1748 Source: Deputy Commissioner Office, Malir.
Literacy The literacy in the 1998 census is defined as the “ability of a person to read a
newspaper or write a simple letter in any language”, the literacy is measured in terms
of literacy ratio and computed as percentage of literate persons among the
population aged 10 years and above.
The literacy ratio of the district is 53.56 percent. The male literacy ratio is higher at
61.44 percent as compared to 42.87 percent for females. There are sharp differences
in the literacy ratios by sex and area. The ratio in urban areas is 55.65 as compared
to 49.16 percent in rural areas. In rural areas male literacy is 58.57 percent as
compared to female literacy ratio which is at 38.05 percent. In urban areas, it is 62.69
for males in comparison to females at 45.43. Table 4.16 shows literacy ratio by sex
and rural/urban areas for the year 1998.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-31 July 2016
Table 4.16: Literacy Ratios by Sex and Rural/Urban Areas, 1981 & 1998
Area 1998
Both Sexes Male Female
All Areas 53.56 61.44 42.88
Rural 49.16 58.57 38.05
Urban 55.65 62.69 45.43 Source: DCR of Malir District, 1998
Important Places including in project area The three important places are included in our project area; these places are as
follows;
a) Malir City Malir, the district headquarters, is situated twenty kilometers from the heart of
Karachi City. It is famous for its vegetables gardens and fruit orchards. With the
increase industrial growth, Malir has developed into a commercial and industrial
centre. A view of Malir City has been shown in the Figure 4.13.
Figure 4.13: A view of Malir City
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-32 July 2016
b) Pakistan Steel Mills Pakistan Steel Mills is the country’s largest industrial unit having production capacity
of 1.1 million tonnes of steel. A view of Pakistan Steel Mills has been shown in the
Figure 4.14.
Figure 4.14: A view of Pakistan Steel Mills
c) Karachi Airport Karachi airport is the gateway to the east. It was built in 1924 when aviation was in its
infancy. During the last 26 years it has grown to be one of the best in Asia in air
traffic control and communication facilities.
4.8 SOCIOECONOMIC BASELINE SURVEY The information regarding socioeconomic baseline is derived from primary data
collection. Baseline survey was carried out in the project area to study and to
establish the baseline socioeconomic conditions around the project area. For this
purpose, a sample of 100 respondents was taken on the basis of simple random
sampling technique, which included shop keepers, factory workers, local residents,
PharmEvo representatives, EPA Officials and pedestrians, etc. Only males were
included during the survey.
Efforts were made to include the majority of the population in the sample and contact
the households residing around the project site. A study specifically for the purpose
has been carried out for proposed project which undertook the demographic and
socioeconomic investigation / survey by carrying out field visit and performing
subsequent analysis.
4.8.1 Field Survey A site visit to the proposed project area was conducted in May 2016 and June 2016.
Data collection was subsequently undertaken during May 30, 2016 to June 03, 2016.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-33 July 2016
This included the collection of demographic and socio-economic baseline information
through a standardized survey tool focusing on household composition, education
levels, general health status, livelihood strategies, employment, income and
expenditure and the availability of utilities, their pressing needs and most importantly
land acquisition and resettlement issues. A sample survey was carried out in the Bin
Qasim Town, Bhains Colony, Korangi, Landhi Industrial Area, Rehri Goth and Steel
Town located in the proposed project site.
4.8.2 Survey Results
a) Demographic Characteristics of the Respondents Demography is defined as statistical analysis of data about the characteristics of a
population, such as the age, sex / gender, income, religion, ethnic structures, mother
tongue, marital status of the people within the population. According to proposed
project, some specific demographic characteristics of sampled population are
described hereunder;
i. Gender Ratio of the Respondents The gender ratio is actually the proportional distribution of the gender in a population
aggregate, expressed as the number of females per 100 males. According to
baseline survey, 100 respondents were interviewed and all of them were males.
Table 4.17 shows gender ratio of the respondents contacted.
Table 4.17: Gender Ratio of the Respondents
Gender Ratio of the Respondents
Sr. No.
Gender Frequency Percentage (%)
1 Male 100 100 Total 100 100
ii. Age Composition of the Respondents The demographic characteristics of the sample survey in (Table 4.18) showing that
06% of the respondents were up to 25 years of age, 44% of the respondents were
aged between 26 – 35 years while 34% were 36 – 45 years and 16% were more than
45 years of age. These figures show that sampled respondents were mature enough
to give their opinion about the proposed project and envisioned of its impacts.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-34 July 2016
Table 4.18: Age Composition of the Respondents
Age Composition of the Respondents
Sr. No. Age Group
Frequency Percentage (%)
1 15-25 06 06 2 26-35 44 44 3 36-45 34 34 4 Above 45 16 16
Total 100 100
The bar chart (Figure 4.15), given below shows the age composition of the
respondents.
Figure 4.15: Age Composition of the Respondents
iii. Marital Status One's situation with regard to whether one is single, married, separated, divorced, or
widowed is basically a marital status. In all 100 sampled respondents, the percentage
share of the married respondents were higher than that of the unmarried. Majority of
the respondents i.e. 77% were married and remaining 23% were unmarried during
socioeconomic baseline survey as shown in Table 4.19.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-35 July 2016
Table 4.19: Marital Status of the Respondents
Marital Status of the Respondents
Sr. No. Marital Status Frequency
Percentage (%)
1 Married 77 77 2 Unmarried 23 23
Total 100 100
The bar chart (Figure 4.16), given below shows the marital status of the
respondents.
Figure 4.16: Marital Status of the Respondents
iv. Caste / Ethnic Group According to baseline survey, it was found that largest part of the respondents i.e.
30% was Syeds. While 19% were Pashton, 03% were Rajpoot, 15% were Rajpoat,
12% Muhajir and 18% were those who did not show any response regarding this
question. Only 05% respondents belong to some other castes. The total sampled
castes of the respondents are given in Table 4.20.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-36 July 2016
Table 4.20: Caste / Ethnic of the Respondents
Caste / Ethnic Group of the Respondents
Sr. No. Caste Number Percentage (%)
1 Abbasi 06 06 2 Baloch 15 15 3 Muhajir 12 12
4 No Response
10 10
5 Others 05 05 6 Pashtoan 19 19 7 Rajpoot 3 03 8 Syed 30 30
Total 100 100
The bar chart below (Figure 4.17) shows the caste distribution of the respondents.
Figure 4.17: Caste/Ethnic Group of the Respondents
v. Mother Tongue When respondents were asked about their mother tongue then it was observed
during survey that Urdu language was the preponderant language being spoken by
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-37 July 2016
majority of the respondents i.e. 34%. While 12% respondents use Pashto Language
for communication and 10% respondents use Punjabi language as mother tounge.
Hindi language is spoken by 06%, Sindhi by 19%, Bangali language by 03% and
07% respondents are using Saraiki Language for communication. Table 4.21 shows
the language spoken by the respondents.
Table 4.21: Mother Tongue of the Respondents
Mother Tongue of the Respondents Sr. No.
Mother Tongue Number Percentage
(%) 1 Balochi 10 10 2 Bengali 3 03 3 Hindi 6 06 4 Pashto 12 12 5 Punjabi 9 09 6 Sindhi 19 19 7 Siraiki 7 07 8 Urdu 34 34
Total 100 100
The language spoken by the respondents is illustrated in the following bar chart
(Figure 4.18).
Figure 4.18: Mother Tongue of the Respondents
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-38 July 2016
vi. Qualification of the Respondents From survey results (Table 4.22) it was found that educational attainment for
sampled population of project area is not very low. Out of 100 respondents, 23% of
were illiterate. Primary and middle school respondents were 18% each. While 13%
got education up to metric level, 14% passed the intermediate and above inter
respectively of the total respondents.
Table 4.22: Qualification of the Respondents
Qualification of the Respondents Sr. No. Education Number Percentage
(%) 1 Illiterate 23 23 2 Primary 18 18 3 Middle 18 18 4 Metric 13 13 5 Intermediate 14 14 6 Above inter 14 14
Total 100 100
The bar chart given below in (Figure 4.19) shows the educational status of the
respondents.
Figure 4.19: Qualification of the Respondents
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-39 July 2016
vii. Professional Status of the Respondents According to socioeconomic survey findings, it was witnessed that out of 100
respondents, majority of the respondents i.e. 40% are working as labor, 12% are
involved in government jobs. While 29% are doing their own business and 29% of the
respondents are doing private jobs. During survey, efforts were made to interact with
people from all walks of life. The detailed statistics based on sample survey,
regarding occupational status of the respondents are shown in Table 4.23.
Table 4.23: Professional Status of the Respondents
Professional Status of the Respondents Sr. No.
Professional Status Number Percentage
(%) 1 Business 19 19 2 Labor 40 40 3 Private job 29 29 4 Govt. Job 12 12
Total 100 100
The bar chart (Figure 4.20) shows the professional status of the respondents is
given below.
Figure 4.20: Professional Status of the Respondents
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-40 July 2016
b) Economic Conditions Average monthly income and average monthly expenditures are the economic
indicators to determine the economic conditions of any individual.
i) Average Monthly Income The income status of the respondents was evaluated by dividing the respondents into
different income categories. During field survey, it was observed that out of 100
respondents, 01% respondents are earning less than 5000 per month, 05%
respondents fall in income range between 5,001 to 10,000, 19% respondents plunge
within the income range of 10,001 to 15,000 and 75% respondents are earning
above 15,000. Table 4.24 shows income status of the respondents.
Table 4.24: Average Monthly Income of the Respondents
Average Monthly Income of the Respondents
Sr. No. Distribution Number Percentage (%)
1 Less than 5000
01 01
2 5001-10000 05 05 3 10001-15000 19 19 4 Above 15000 75 75
Total 100 100
In the pie chart (Figure 4.21), the income groups of various respondents are shown below.
Figure 4.21: Average Monthly Income of Respondents
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-41 July 2016
ii) Average Monthly Expenditures Table 4.25 shows expenditure status of the respondents. Out of 100 respondents,
03% respondent’s falls in average monthly expenditure range of 5,000-10,000, 08%
respondents plunge within the expenditure range of 10,001 to 15,000 and majority of
the respondents i.e 89% respondents have the expenditure range of above 15,000
and No respondent is falling within the income group of less than 5000.
Table 4.25: Average Monthly Expenditures of the Respondents
Average Monthly Expenditure of the Respondents
Sr. No. Distribution Number Percentage (%)
1 5001-10000 03 03 2 10001-15000 08 08 3 Above 15000 89 89
Total 100 100
In bar chart (Figure 4.22), the average monthly expenditures of various respondents
are shown below.
Figure 4.22: Average Monthly Expenditures of Respondents
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-42 July 2016
c) Family System Survey results clearly show that majority of the respondents i.e. 55% are living in the
nuclear family system. Remaining 45% are living in the nuclear family system which is
shown in the Table 4.26.
Table 4.26: Family System of the Respondents
Family System Sr. No Type Number Percentage (%)
1 Joint 45 45 2 Nuclear 55 55
Total 100 100
Bar chart given below (Figure 4.22) shows the Family System of the respondents.
Figure 4.22: Family System of the Respondents
d) Average Household Size It is clear from data presented in the Table 4.27 that the majority of the respondents
42% reported their household size ranging from 6 to 8 persons, 27% respondents were
reported holding family members between 3-5 and 17% families have the average
household size above 8. While 03% of the respondents reported their household size
0-2 and 11% respondents did not give any response regarding their family size.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-43 July 2016
Table 4.27: Average Household Size of Respondents
Average Household Size Sr. No. Distribution Number Percentage (%)
1 0-2 03 03 2 3-5 27 27 3 6-8 42 42 4 Above 8 17 17
5 No Response 11 11
Total 100 100
The bar chart given (Figure 4.23) shows the average household size of the
respondents.
Figure 4.23: Average Household Size of Respondents
e) Ownership Status of the Houses Ownership status of the house depict that how much respondents blong to self
owned, rented and encroached structures (houses and shops). During the field
survey it was observed that out of 100 respondents majority i.e. 58% of the
respondents are the renters, 34% have self owned houses and only 08% of the
respondents are enchroachers. Table 4.28 shows the ownership status of the
houses of the respondents.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-44 July 2016
Table 4.28: Ownership Status of the Houses
Ownership of Houses Sr. No Status Number Percentage
(%) 1 Self-Owned 34 34 2 Rented 58 58 3 Encroached/Squatted 08 08
Total 100 100
The bar chart given below (Figure 4.24) shows the ownership of the houses of the
respondents.
Figure 4.24: Ownership Status of the Houses
f) Nature of Construction of Houses Housing structures within the proposed project area reflect a dependence on natural,
local resources and the lack of access to or ability to purchase external, more durable,
man-made construction materials. Out of 100 respondents, majority i.e. 47% of them
live in the in the semi-pacca houses made by the mixture of concrete, bricks and mud,
37% in pacca houses made up of bricks and concrete and 15% of the respondents
are living in Katcha houses made of mud. While 01% of the respondents are running
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-45 July 2016
their business in the type of kiosk (an open summer house or pavilion). Table 4.29
shows the nature of the construction of the houses.
Table 4.29: Nature of Construction of Houses
Nature of Construction of Houses
Sr. No. Type Number Percentage (%)
1 Semi-Pacca 47 47
2 Pacca 37 37 3 Kaccha 15 15 4 Kiosk 01 01
Total 100 100
The bar chart below (Figure 4.25) shows the nature of construction of houses.
Figure 4.25: Nature of Construction of House
g) Availability of Utilities The availability of utilities and development of this community is noticed by visiting
this proposed project area. Table 4.30 shows that bulk of the respondents i.e. 55%
had access to electricity, water supply and gas while 12% of the respondents had
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-46 July 2016
both water supply system and gas and 26% are those who had access to all facilities.
While 07% of the respondents had no access to these facilities.
Table 4.30: Availability of Utilities
Availability of Utilities
Sr. No. Facility Number Percentage (%)
1 Electricity, Water supply, Gas 55 55 2 Water supply, Gas 12 12 3 All 26 26 4 None 07 07
Total 100 100
In the bar chart (Figure 4.26), the availability of utilities of various respondents is
shown below.
Figure 4.26: Availability of utilities for Respondents
h) Source of Water for Domestic Use Sampled respondents are depending upon multiple sources of water for domestic
use which is shown in Table 4.31. Water supply is the main source of drinking water
in the proposed project area so majority of the respondents i.e. 29% use this source,
12% use hand pumps / electric motor as a source of water for domestic use, while
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-47 July 2016
25% use public water supply, hand pump / electric motor as source of water. 12%
respondents are using other sources of water for domestic use and 22% respondents
are using all sources of water.
Table 4.31: Source of Water for Domestic Use
Source of Household Water in Project Area Sr. No. Sources of Water Number Percentage (%)
1 Public water supply 29 29 2 Hand pumps/Electric motor and Bore hole 12 12
3 Public water supply & Hand pumps, Borehole
25 25
4 Any Other 12 12 5 All 22 22
Total 100 100
In the bar chart (Figure 4.27), Source of household water for domestic use is shown
below.
Figure 4.27: Source of Water for Domestic Use
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-48 July 2016
i) Satisfaction level with Water Quality The quality of water is directly linked to the quality of health. Table 4.32 depicts the
perception of people about water quality in the proposed project area. It was noticed
during the baseline survey that the quality of water is satisfactory and acceptable.
Majority of the respondents i.e. 75% are satisfied with the water quality. But
according to 25% respondents, the water quality is not satisfactory due to the poor
quality of water. They also reported that water supply lines are mixed with the waste
water which makes the water unhealthy for drinking purpose.
Table 4.32: Satisfaction Level with Water Quality
Satisfaction Level with Water Quality
Sr. No. Opinion Number Percentage (%)
1 Yes 75 75 2 No 25 25
Total 100 100
In the bar chart (Figure 4.28), satisfaction level with quality of water is shown below.
Figure 4.28: Satisfaction Level with Water Quality
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-49 July 2016
j) Satisfaction level with Industrial Development Table 4.33 depicts the perception of people about the industrial development in the
project area. It was noticed during the baseline survey that majority of the
respondents i.e. 73% are satisfied with this industrial development. But according to
27% respondents these developments are not satisfactory due to some reasons.
Table 4.33: Satisfaction Level with Industrial Development
Satisfaction Level with existing with Industrial Development
Sr. No. Opinion Number Percentage (%)
1 Yes 73 73 2 No 27 27
Total 100 100
In the bar chart (Figure 4.29), satisfaction level with Industrial Development is shown below
Figure 4.29: Satisfaction Level with existing with Industrial Development
k) Impact of Proposed Project on Employment of Workers When respondents were asked about the impacts of the proposed project on
employment of workers then majority of respondents i.e. 73% respondents were
those who responded that proposed project will impact on the employment while 27%
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-50 July 2016
believed that this proposed project will not impact on employment of workers as
shown in Table 4.34.
Table 4.34: Impact of Proposed Project on Employment of Workers
Impact of Proposed Project on Employment of Workers
Sr. No. Impact Number Percentage (%)
1 Yes 73 73
2 No 27 27
Total 100 100
In the following bar chart (Figure 4.30), responses are shown below
Figure 4.30: Impact of Proposed Project on Employment of Workers
l) Nature of Impact of Proposed Project on Employment of Workers In the response of this question majority of the respondents i.e. 52% hope that the
proposed project will create job opportunities for the locals. According to 07% and
09% respondents, this project will prove a good source of revenue generation and
good for economic growth respectively. While 27% respondents did not show any
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-51 July 2016
response regarding this question. Table 4.35 depicts the details of nature of the
impacts.
Table 4.35: Nature of Impact of Project on Employment of Workers
Nature of Impact of Project on Employment of Workers
Sr. No. Issues Number Percentage (%)
1 A good source of revenue generation 07 07
2 Employment Opportunities 52 52
3 Good for economic growth 09 09 4 Logistic Increase 05 05 5 No 27 27
Total 100 100
In the following bar chart (Figure 4.31), nature of the impacts are shown below
Figure 4.31: Nature of the impacts proposed by the Respondents
m) Location of Proposed Project in High Population Density
Survey results (Table 4.36) show that out of 100 respondents, majority i.e. 91%
respondents appreciated that project is not falling within the populated area only 09%
respondents said that this project is falling in the populated area.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-52 July 2016
Table 4.36: Location of Proposed Project in High Population Density
Location of Proposed Project
Sr. No. Opinion Number Percentage (%)
1 Yes 09 09 2 No 91 91
Total 100 100
The views of various respondents about location of proposed project in high
population Density is shown in below bar chart (Figure 4.32).
Figure 4.32: Location of Proposed Project
n) Acquisition of Private Land Survey results (Table 4.37) show that out of 100 respondents, majority i.e. 96%
respondents appreciated that no private land acquisition is involved. Only 04%
respondents said that they will face land acquisition regarding this project.
Table 4.37: Acquisition of Private Land
Acquisition of Private Land Sr. No. Opinion Number Percentage (%)
1 Yes 04 04 2 No 96 96
Total 100 100
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-53 July 2016
The acquisition of private land of various respondents is shown in below bar chart
(Figure 4.33).
Figure 4.33: Acquisition of Private Land
o) Awareness about the Project The analysis of the socio economic baseline survey shows the awareness level
about the proposed Project in Table 4.38. A vast majority of respondents i.e. 94%
had cognizance about the proposed project and remaining 06% of the respondents
had no knowingness about the proposed project.
Table 4.38: Awareness about the Proposed Project
Awareness about the Proposed Project Sr. No.
Response Number Percentage
(%) 1 Yes 06 06 2 No 94 94
Total 100 100
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-54 July 2016
In the bar chart (Figure 4.34), information regarding proposed project are shown
below.
Figure 4.34: Awareness about the Proposed Project
p) Implementation of the Proposed Project Table 4.39 shows the willingness of the respondents about implementation of the
proposed project. The greater volume of the respondents i.e. 70% were in favor of
the construction of proposed project. Only 30% did not show any avidness about the
project implementation.
Table 4.39: Implementation of the Proposed Project
Project Implementation
Sr. No Opinion Number Percentage (%)
1 Yes 70 70 2 No 30 30
Total 100 100
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-55 July 2016
In the bar chart (Figure 4.35), the perception of various respondents about the proposed
project is shown below.
Figure 4.35: Implementation of Proposed Project
q) Perceived Impacts Table 4.40 & Table 4.41 provide us the various impacts perceived by the respondents
during construction and operation of provision of coal conveying system.
i) Perceived Impacts of the Project during construction
The big trepidation of the respondents i.e. 37% was about traffic issues due to the
movement of heavy machinery during the construction phase of the proposed
project. 08% of respondents think that safety hazards might be produce due to
construction/spillage of the proposed project. In 07% cases, the respondents showed
their serious concern about mobility problem for factory workers in the vicinity of the
proposed project.
While 15% and 09% of the respondents expressed that there will be dust & noise and
tree cutting issue during the construction phase respectively, 06% respondents said
that due to the construction phase of this project local residents will suffer from all the
aspects and 18% of the total respondents responded that they have no issue due to
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-56 July 2016
the proposed project. Table 4.40 shows the impacts perceived by the respondents
during construction.
Table 4.40: Perceived Impacts (During construction)
Perceived Impacts of the Project (During Construction)
Sr. No. Impacts Number Percentage (%)
1 Dust & air pollution 15 15
2 Local residents will suffer from all aspects 06 06
3 Mobility problems for factory workers 07 07
4 Road blockage issues due to heavy traffic 37 37
5 Safety hazards due to construction/spillage 08 08
6 Tree cutting 09 09
7 No Response 18 18 Total 100 100
The perceived impacts of the respondents during construction are shown below in
graphical form (Figure 4.36).
Figure 4.36: Impacts Perceived by Respondents
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-57 July 2016
ii) Perceived Impacts of the Project after Construction When respondents were asked about perceived impacts after construction phase, 10%
respondents responded that as income generating activities will increase so more
income will be generated through this project, while bulk of respondents i.e. 37%
believed that pollution will increase due to the coal dust which will have negative
impacts on the health of local settlements. According to survey finding, 12%
respondents also responded that proposed project would have positive impacts on the
local residents in terms of employment opportunities, 09% respondents expressed that
environmental hazards might be arise due to gas leakage/spillage in the project area.
In 08%, respondents believe that proposed project will be beneficial for local residents
in all aspects, while 24% respondents did not give ant response. Table 4.41 shows the
impacts perceived by the respondents after construction.
Table 4.41: Perceived Impacts (after Construction)
Perceived Impacts of the Project (After Construction) Sr. No Impacts Number Percentage (%)
1 Beneficial for people from all aspects 08 08
2 Employment Opportunities 12 12
3 Environmental hazards due to Gas leakage/Spillage 09 09
4 Income generation 10 10 5 Pollution due to coal dust 37 37 6 No Response 24 24
Total 100 100
The perceived impacts of the respondents during operation are shown below in
graphical form (Figure 4.37).
Figure 4.37: Impacts Perceived by Respondents
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-58 July 2016
r) Protective Measures From the data given in Table 4.42, in 09% cases, respondents suggested that
harmful effects of coal on local residents should be minimize, 08% respondents
highlighted that there should be a proper maintenance of roads and other
infrastructure so that the heavy load of traffic can be managed easily. While 05%
suggested that fire protection systems should be installed for a safe & healthy
environment, 14% accentuated that fishing sector should improve more rather any
disturbance, 03% respondents said that more development projects should be
constructed in this project area, 13% respondents want that project must shift
somewhere else because it is not suitable place for this project and 48% respondents
did not give any response.
Table 4.42 Protective Measures Protective Measures
Sr. No. Protective Measures Number Percentage (%)
1 Fire protection system should be installed 05 05
2 Fishing Sector should be improve rather any disturbance 14 14
3 Harmful effects of coal on local residents should minimize 09 09
4 Maintenance of road & traffic management 08 08
5 More development projects should be constructed here 03 03
6 Project must shift somewhere else 13 13
7 No Response 48 48
Total 100 100
In the pie chart below (Figure 4.38) the protective measures suggested by the
respondents are shown.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-59 July 2016
Figure 4.38: Protective Measures Suggested by Respondents
a) Pressing Needs of the Project Area Survey Results are shown in Table 4.43, which further depict that out of 100
respondents, majority i.e. 22% said that the proper medical and educational institutions
should be provided to the local residents and these institutions should also be
upgraded with the passage of time, again in majority i.e. 22% respondents showed that
the maintenance of roads and proper provision of infrastructure should be in this
proposed project area, while remaining 20% respondents assumed that there should
be a provision of clean drinking water in this project area and 11 % respondents think
that the provision of electricity is a basic need of the local residents so it should be prior
in the provision of all needs. 09% respondents thought that a proper waste
management system should be provided to the local residents of the proposed project
area. Remaining 16% respondents did not show any response regarding the pressing
needs of that project area.
Section-4 Environmental Baseline Profile EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 4-60 July 2016
Table 4.43 Pressing Needs of the Project Area
Pressing Needs of the Project Area Sr. No. Pressing Needs Number Percentage (%)
1 Establishment of roads and infrastructure 22 22
2 Proper waste management 09 09 3 Provision of drinking water 20 20 4 Provision of electricity 11 11
5 Provision of medical and educational institutions 22 22
6 No Response 16 16 Total 100 100
In the pie chart below (Figure 4.39) the pressing needs suggested by the
respondents are shown.
Figure 4.39: Pressing Needs of the Project Area
Section – 5 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 5-1 July 2016
SECTION - 5 PUBLIC CONSULTATION
5.0 GENERAL This section describes the outcome of the public consultation sessions held with
different stakeholders that may be affected by the proposed project. Public
Consultation is a mandatory part of the EA process for development projects. The
adequacy of the public consultation and information disclosure is one of the basic
criteria used to determine the project compliance with the national / international
safeguard policies.
The consultation process was carried out in accordance with the requirements of
Pakistan Environmental Procedures. The objectives of this process were to:
a) Identify and involve all stakeholders, especially local residents, in the
consultative and participation process;
b) Share information with stakeholders on the design and construction of the
proposed project and anticipated impacts on the physical, biological and
socio-economic environment of the project area;
c) Understand stakeholders' concerns regarding various aspects of the project,
including the existing available facilities and problems, construction of the
project and the likely impacts of construction and operation related activities;
d) Understand the perceptions, assessment of social impacts and concerns of
the communities in the vicinity of the proposed project;
e) Provide an opportunity to the public in the public consultation session to
provide valuable suggestions for the project design in a positive manner; and
f) Reduce the chances of conflict through the identification of controversial
issues, and consult them to find up to standard solutions.
5.1 CONSULTATION AND PARTICIPATION PROCESS
For ascertaining the perceptions of different stakeholders about the project (during
construction/operation) consultation meetings were held with them. These meetings
Section – 5 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 5-2 July 2016
were conducted in an open atmosphere at different places (Bin Qasim Town, Bhains
Colony, Korangi, Landhi Industrial Area, Rerhi Ghoth, Steel Town and surrounding
areas). in which participants expressed their views freely. The consultation meetings
were carried out from May 30, 2016 to June 03, 2016.
5.2 METHODS OF PUBLIC CONSULTATION
Public Consultation was carried out in order to establish stakeholder’s opinion
regarding project implementation. The following methods were used for public
consultation with project stakeholders
• Scoping Sessions
• Formal Meetings
• Informal Group Meetings
5.3 IDENTIFICATION OF STAKEHOLDERS
Stakeholders are those who have a direct or indirect interest in project development,
and who will be involved in the consultation process. During the field survey,
significant efforts were made to identify the possible categories of stakeholders and
their stakes. The stakeholders identified during field survey were the local residents,
shop keepers, pedestrian, factory workers, Pharm Evo and EPA officials. All the
stakeholders had different type of stakes according to their professions which are
listed down along with their apprehensions.
5.4 CATEGORIES OF STAKEHOLDERS CONTACTED The stakeholders contacted, are given in the Table 5.1.
Table 5.1: Stakeholders Contacted in the Project Area
Sr. No. Stakeholder Category 1 EPA Officials 2 Bin Qasim Association of Trade and
Industry 3 Industries Located in the Project Area 4 Local residents 5 Shop keepers 6 Pedestrians 7 Factory workers
Section – 5 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 5-3 July 2016
5.5 MAJOR STAKEHOLDERS AND THEIR APPREHENSIONS
Among all stakeholders some major stakeholders were identified in the proposed
project area. Plate 5.1 shows the pictorial view of Interviews, consultation meetings
and focused group discussions (FGDs) held with the stakeholders. The following Table 5.2 contains the list of major stakeholders and their apprehensions.
Table 5.2: Major Stakeholders and their Apprehensions in the Project Area
Sr. No.
Stakeholders Apprehensions
4 Industries Dust and noise pollution, safety issues, disturbance of utilities, traffic associated with construction activities.
1. Local Residents Movement problem for local residents and labor, dust and noise problem, privacy / safety issues, disturbance of public utilities
2. Shop Owners Increase in business, noise, air pollution
3 Pedestrians During construction period pedestrians will face difficulties while walking to nearby places existing in the vicinity of proposed project area
4 Factory workers Dust and noise pollution, privacy / safety issues, disturbance of utilities, traffic and lightening associated with construction activities on the residents living near the project area that can cause disturbances and stress.
5 Pharm Evo Representatives
Coal dust and noise pollution, Health & safety issues, Coal fire hazard
Section – 5 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 5-4 July 2016
Plate 5.1: Interviews and group discussions with stakeholders
Section – 5 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 5-5 July 2016
5.6 CONSULTATION MEETINGS AND FORMAL AND INFORMAL GROUP DISCUSSIONS
Consultation Meetings, Focus Group Discussions (FGDs) and Scoping Meetings
regarding project impacts, their magnitude and mitigation measures were held with
the representatives of Bin Qasim Association of Trade and Industry (BQATI) and
different industries, local residents, shop keepers, pedestrian, factory workers and
EPA officials to know their concerns regarding proposed project.
Scoping sessions were conducted with the local residents, shop keepers,
pedestrians and factory workers. These sessions were held at Bin Qasim Town,
Bhains Colony, Korangi, Landhi Industrial Area, Rerhi Ghat, Steel Town and
surrounding areas.
Generally, it was found that people were already aware of the proposed project. After
the meetings with the local residents and other stakeholders, majority of the
respondents (70%) during sample survey showed their support for the proposed
project. This project will be beneficial not only for the local residents but also good for
the development of the country as this project will increase power generation.
Scoping Meeting
An EIA scoping meeting was organized by PQA, on April 12, 2016 at the Conference
Room of Port Qasim Authority Karachi with the objective to provide a joint platform to
the project relevant stakeholders to discuss and highlight, the important issues, and
aspects pertaining to the project which need to be considered during the ongoing EIA
study for Coal Conveying System.
Scoping at the outset of the EIA study enables the EIA study team to identify and
earmark the important aspects/ issues to be subsequently covered in the EIA.
All the relevant stakeholders as identified by PQA and NESPAK as per
recommendations and Public Consultation Guidelines by Pakistan Environmental
Protection Agency (1997) were invited to attend the Scoping Meeting. The meeting
was attended by many important stakeholders representing the proponent,
governmental and non-governmental organizations, industrial and special interest
groups. (Attendance Sheet of Participants is also attached as annexure vii).
Section – 5 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 5-6 July 2016
The meeting started with the recitation of Holy Quran at 10:00 hrs with opening
remarks from Director General (Technical), PQA. The Director General, welcomed
the participants to the meeting. The meeting proceeded with a presentation by
Consultants on the proposed project. The presentation illustrated different project
components, route alignments along the entire project length, strategies that will be
adopted at sensitive locations, alternatives considered for different sections of the
alignment and other relevant aspects.
At the end of the presentation, participants were invited to ask questions and give
suggestions/observations.
Scoping Meeting at Conference Room of Port Qasim Authority, Karachi
Section – 5 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 5-7 July 2016
5.7 CONCERNS / SUGGESTIONS OF THE STAKEHOLDERS
The most commonly raised concerns during the meetings are listed below:
Exposure of noise and dust pollution will deteriorate the air quality and cause
health & safety issues to the local residents and factory workers throughout
the construction and operation stages due to the movement of construction
machinery and transportation of construction materials and coal. The effects
of noise and dust pollution on the local residents should be minimized by
making necessary arrangements. Dust pollution should be controlled by water
sprinkling on daily basis and the conveyor belt shall be covered;
Due to the movement of loaded trucks in the construction period of proposed
project, congestion on the access road will create. Proper diversion route
rather than access road should be clearly defined to avoid blockage of access
road during the entire construction period;
Loading and unloading of coal can cause fire hazard.
During construction period local residents and pedestrians will face difficulties
while walking to nearby places in the vicinity of proposed project area.
Appropriate diversion plan should be develop to avoid the disruption of all the
people due to use of heavy machinery in day timings and should avoid
disturbance for the local residents living in the project vicinity;
Local residents should be given priority for jobs during the construction
phase;
Due to the construction of the proposed project, public utilities will be
disturbed. Arrangements should be made to minimize the disruption of public
utilities or they may be rehabilitated on priority basis to reduce the impacts;
Tree cutting should be avoided in this area as much as possible; and
Increase in traffic and safety hazards will create problems to local population
and surrounding communities. Accordingly, a detailed health and safety plan
must be developed to mitigate the construction and operation risks of the
proposed project on the local residents and surrounding communities.
Section – 5 Description of the Project EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 5-8 July 2016
5.8 MITIGATION MEASURES PROPOSED BY EIA CONSULTANTS FOR ADDRESSING THE STAKEHOLDER’S CONCERNS
The contractors and design consultants may include the following environmental and safety
provisions in the project design in order to protect the surrounding communities from
the anticipated impacts of pre and post construction activities:
Local residents should be given jobs on priority basis during construction and
operation phase of the proposed project;
All efforts should be espoused to save existing plantation;
Construction machinery should be placed at adequate locations away from
the sensitive areas to minimize the impacts related to the noise;
Project facilities should be located outside the existing residential areas. In
order to avoid restricting the daily movement of the local stakeholders,
construction vehicles should remain confined within their designated areas of
movement;
The utilities to be shifted due to the implementation of the proposed project
should be rehabilitated on priority basis to minimize the impacts on the
stakeholders;
Solid waste generated during construction at site should be disposed of safely
at the waste disposal sites approved by the City District Government, Karachi;
and
All necessary measures should be taken to ensure the safety of traffic during
construction, including barricades (including signs boards, pavement
markings, flags, and lights). All such barricades will be set up to facilitate the
local traffic.
5.9 DETAILS OF MEETINGS WITH THE STAKEHOLDERS
In addition to the previously discussed commonly raised concerns, there were certain
issues at the project site which were raised by the respondents. The detailed
schedule of meetings at site with the stakeholders and the issues raised by the
respondents are given below in Table 5.3.
Section – 5 Public Consultation EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 5-9 July 2016
Table 5.3: Schedule of Meetings with Stakeholders and their Concerns / Apprehensions
Sr. No. Date Time Venue No. of
Participants Apprehensions
Raised
Suggestions
1.
30/5/2016
10.30 AM Bhains Colony 17 No Apprehensions. Government should launch projects for power generation.
Local residents should give preference for jobs during construction and operation phase.
Solid waste generated during construction at site should be disposed of safely at the waste disposal sites.
Arrangements should be made to minimize the disruption of public utilities, or they may be rehabilitated on priority basis to reduce the impact.
Efforts should be made to complete the construction work within the time period.
Accordingly a detailed health and safety plan must be developed and implement to mitigate the construction and operation risks of the proposed project on the local residents and surrounding communities.
2. 30/5/2016
12.30 PM Landhi road side 9 Unavailability of electricity, water and gas, poor infrastructure, health sewerage problems
Government should provide basic facilities to the public like safe drinking water, proper medical and educational facilities.
3 31/5/2016
9.30 AM Port Qasim 8 Daily movement problem will occur for labor; No proper medical facility available in the area.
To avoid the mobility problem, an appropriate diversion plan should be develop; Government should provide good medical facilities to the local people.
Section – 5 Public Consultation EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 5-10 July 2016
Sr. No. Date Time Venue No. of
Participants Apprehensions
Raised
Suggestions
4 1/6/2016 10.00 AM PQA Bin Qasim 13 Coal dust can cause health issues and fire hazard. Mobility issues during construction phase.
A detailed health & safety plan should be adopted to avoid these issues. To avoid the mobility problem, an appropriate diversion plan should be develop
5 3/6/2016 10.AM Ibrahim Hyderi (Fish Harbour)
7 Harmful effects of coal dust on fishermen colony, natural habitat and marine ecology
Renewable energy should be used in the coal conveying belt, it should not executed here because of harmful effects on marine life
6 3/6/2016 10.AM PharmEvo at PQA
15 Harmful effects of coal dust on pharmaceutical industry. Issues about coal dust and greenhouse gas emissions and fire hazard.
Alternate resources like wind turbines, solar power generation plants and biogas plants should be used instead of coal. A detailed health & safety plan should be adopted to avoid these issues. In order to ensure effective and efficient implementation measures throughout the operational life of the project, an Environmental Monitoring and Management Plan should be implemented.
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-1 July, 2016
SECTION – 6 ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
6.0 GENERAL
This section identifies the overall impacts of design, construction and operational
phase of the proposed project on physical, biological and socio-economic
environment. In addition to that, it also narrates the measures that will mitigate or at
least minimize the project’s adverse environmental impacts.
6.1 ENIRONMENTAL IMPACT MATRIX
Methodology adopted for the identification and evaluation of environmental impacts
of the proposed project is “Matrix Method”. The environmental impacts matrices have
been developed to evaluate magnitude of the impacts of different project activities on
different environmental settings for both construction and operational phases. These
matrices are presented in Tables 6.1 and 6.2. The following scale has been used for
the evaluation of impacts:
LA = Low Adverse (low/short-term damage to the environment)
MA = Medium Adverse (moderate damage to the environment)
HA = High Adverse (severe damage to the environment)
LB = Low Beneficial (less beneficial to the environment)
MB = Medium Beneficial (moderate beneficial to the environment)
HB = High Beneficial (highly beneficial to the environment)
N/A = Not Applicable
O = Insignificant / No Impact
Section–6 Anticipated Environmental Impacts and Mitigation Measures EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-2 July, 2016
Table 6.1 Environmental Impacts Matrix for the Construction Phase of Coal Conveying System at Port Qasim Karachi
Sr. No. Physical Environment Biological Environment Socioeconomic Environment
Environmental Components
Topo
grap
hy
Soil
Eros
ion/
Con
tam
inat
ion
Land
scap
e
Air
Qua
lity
Hyd
rolo
gy a
nd D
rain
age
Noi
se &
Vib
ratio
n
Hab
itat C
hang
e
Vege
tatio
n
Ani
mal
Mov
emen
t
Hea
lth &
Saf
ety
for P
ublic
and
W
orke
r
Dis
rupt
ion
of P
ublic
Util
ities
Empl
oym
ent
Popu
latio
n D
istu
rban
ce
Cul
tura
l / R
elig
ious
Val
ues
Loca
l Eco
nom
y / B
enef
its to
C
omm
unity
Traf
fic M
anag
emen
t
1 Establishment & functioning of Construction camps, workshops etc. O LA LA LA O LA O O O LA LA MB O O LB LA
2 Excavation/drilling operations LA LA LA MA LA MA LA LA LA LA LA MB O O LB LA
3 Transportation of construction materials O LA O LA LA MA O O LA LA O LB O O LB LA
4 Open storage of construction material and fuel etc. O LA O LA O LA O O O LA O O O O LB LA
5 Earthwork / concrete work operations LA LA LA LA O MA LA O LA LA LA MB O O MB LA
6 Operation of concrete batching plants O LA LA HA O MA O O O MA O MB O O MB O
7 Disposal of Wastewater O MA LA MA LA O O O O LA O MB O O O O
8 Solid Waste Management (segregation, collection, handling, storage and disposal of Excavated Material) O LA LA LA LA O O O O LA O LB O O O O
9 Storage of oils/diesel O LA O LA O O O O O LA O LB O O O O
10 Shifting of utilities O LA O LA O MA O O O LA MA MB MA O LA O
Legend
O - Insignificant / no impact LA - Low Adverse
MA - Medium Adverse
HA - High Adverse NA - Not Applicable
LB - Low Beneficial
MB - Medium Beneficial
B - High Beneficial
Project Activities
Section–6 Anticipated Environmental Impacts and Mitigation Measures EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-3 July, 2016
Table 6.2 Environmental Impacts Matrix for the Operation Phase
of Coal Conveying System at Port Qasim Karachi
Sr.
Physical Environment Biological
Environment Socioeconomic Environment
Project Environmental Activities Components
Soil
Eros
ion/
Qua
lity
Surf
ace
Run
off
Air
Qua
lity
Gro
undw
ater
Qua
lity
Flor
a
Ani
mal
Har
assm
ent
Tran
spor
t
Empl
oym
ent
Com
mun
ity D
evel
opm
ent
Hea
lth a
nd S
afet
y Is
sues
1 Movement of Trains O O LA O LA O HB MB MB HB
2 Movement of Vehicles O O HB O O O HB MB MB HB
3 Transport of Coal through conveyor Belt O O LA O LA LA HB MB MB LA
4 Coal Stacking O MA HA O LA LA O MA MB MA
5 Coal Reclaiming O MA MA O LA LA O MA MB MA
6 Maintenance Work O LA LA O LA O LA MB MB LA
7 Disposal of storm water drainage LA LA O O O O LA MB MB LA
Legend
O - Insignificant / no impact LA - Low Adverse
MA - Medium Adverse NA - Not Applicable LB - Low Beneficial
MB - Medium Beneficial
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-4 July, 2016
6.2 ANTICIPATED IMPACTS DURING PRE-CONSTRUCTION/DESIGN PHASE
Following is the description of impacts envisaged and recommended mitigation measures
during Pre-construction/Design Phase:
6.2.1 Design & Layout Planning Incompatible layout plan and engineering design of the project’s structures can
undermine the overall aesthetic beauty and ambience of the project area. Further low
utilization of the available spaces and not designing the structures taking into account the
prospective and futuristic needs, can result in structures with low social acceptability and
functionality. This impact will be temporary in nature.
Mitigation:
All structural layout and engineering designing of proposed Coal Conveying System
should be in strict accordance with the applicable by-laws and engineering parameters.
6.2.2 Topography & Geology During the construction phase the chances of severe impacts are less because the
existing site is fairly leveled and already developed. Furthermore, the future development
is planned according to the international standards for the design of coal conveyor,
stockyard and load-out station and allied structures. Hence the impacts will be minor and
not noteworthy.
Mitigation:
Mitigation measures will involve careful planning, design, alignment and route selection
by the designer.
6.2.3 Land Acquisition and Resettlement The proposed structure for the conveyor belt is being developed in the median of the
existing road so no land acquisition and resettlement is involved for the proposed coal
conveyor. However, the proposed coal stockyard and load-out stations are being
developed on the land of Pakistan steel mills. The area is currently being used for the
storage of old materials by Pakistan Steel. The land from the Pakistan steel will be
transferred to PQA (from one department to another department of Government of
Pakistan). No private land acquisition and any resettlement are involved in the project.
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-5 July, 2016
6.2.4 Transportation and Access The project is located in the North West Industrial Zone (NWIZ) of Port Qasim industrial
estate which is a high density industrial area.
During the construction phase of the infrastructure of coal conveyor, it might be difficult
for road users to get access to their industries and transport the raw materials/finished
products to and from the market which will result in affecting their daily working activities.
This impact is temporary in nature and for short period of time.
Mitigation:
Mitigation measures will include provisions in the design and construction such as:
• Proper traffic diversion plans;
• Careful planning of construction activities;
• Appropriate sign boards;
• Public awareness through media; and
• Timely completion of the project.
6.2.5 Ecological Impacts The existing ecological environment will not be changed after the establishment of Coal
Conveying System from its present state. Clearing of the project areas will not cause the
elimination of any remains of semi-natural habitats. There exists no any significant
vegetation cover, ecological disturbance does not seem to be significant vis-à-vis the long
term benefits derived from the construction of the CCS, as long as environmentally sound
construction practices are followed and necessary mitigation measures are put in place
during and after construction.
Mitigating Measures
It is recommended that in order to improve the disturbed ecology of the project site,
landscape development plan along the Coal Conveyor corridor and in the area of Coal
Stockyard should be prepared and implemented by utilizing available resources.
6.2.6 Flora Trees are present in the median of existing road only. There is no significant vegetation
cover in the proposed area of Coal Stockyard. The species present are Pipal, Neem,
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-6 July, 2016
Conocarpus and Lignum in the median of road and mesquites in the area of stockyard.
The total number of trees in the median of existing road is 12.
During construction of proposed project, the efforts will be made to retain or save the
trees present in the median. A total of about 12 trees may be removed or disturbed for
the construction of footings of the conveyor belt.
Mitigating Measures
• Mitigation will be required in the form of reinstatement and compensatory planting.
• Soft landscaping should be installed under the elevated sections and along the
route of conveyor belt to improve the appearance of the completed works.
• Replacement at a minimum rate of 10:1 for trees that will be 120 trees but we
recommend 240 trees should be planted and that would be appropriate given
possible difficulties with establishing trees and low survival rate of young trees.
This would probably be affordable. Therefore it is important to recognize that
some significant part of their placement ratio should allow for a high mortality rate
among the newly planted trees based on observation and international
expectations. A detailed tree plantation plan is given as Annexure-IV
6.2.7. Fauna As the project area is modified as urban area, there are no significant faunal species
present in the project area. There will be no significant adverse impact of fauna by the
execution of the project. However, mammals, such as dogs, cats, etc will avoid these
areas for fear of being persecuted. Same will be the case with reptiles. Similarly, the birds
will try to find shelter and food elsewhere and will tend to move away from the project
area due to construction activities. Overall, the impact on fauna of the area is insignificant
in nature.
6.2.8 Marine Fauna and Flora As the project area includes about 500 m buffer area on either side from the centerline of
the median and around the stockyard as shown in fig 1.1 which shows that the site is far
away to affect marine ecology hence no any direct impact of construction and operation
of Coal Conveying System on the marine fauna and flora are anticipated.
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-7 July, 2016
6.2.9 Air Quality and Noise With the implementation of proposed project, air pollution, noise and associated health
risks may decrease as the project will enable continuous transport of coal through a
covered coal conveyor. This impact is permanent and moderately positive in nature.
However, the emission of dust from the construction activities and coal dust from the coal
stockyard operations may cause the deterioration of air quality in the project area.
Mitigating Measures
• Special care for air emission and noise generated during the construction and
operation stage of Coal Conveying System (CCS) should be taken during design
phase; and
• Provision of covers and noise barriers must be considered in design of the coal
conveyor and dust control measures e.g. height of coal stacks, water sprinkling
system, wind breaking and dust suppression walls must be provided to control the
dust generated from the coal handling activities.
6.2.10 Public Utilities Due to the proposed project, public utilities affected may create disruption of public
services and economics including water supply, electric transmission lines, telephone line
and gas facilities etc. This impact is however temporary and moderate adverse in nature.
Mitigation measures will include:
• Incorporate technical design features to minimize impacts on public utilities; and
• All public utilities likely to be affected by the proposed project need to be
relocated/rehabilitated well ahead of the commencement of construction work.
6.2.11 Archaeological and Heritage Sites There is Mazar of Kamal Shah which is a significant site of archaeological and heritage
value in the project area and during the construction phase there is some exposure to be
experienced with this site which needs attention and should be carefully handled to
minimize the physical impacts.
Mitigation measures will include:
• The socio-economic and cultural considerations of this site is to be given due
regards under respective domains.
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-8 July, 2016
6.2.12 Impact on Traffic The proposed Coal Conveyor will be constructed in the median of existing road and Coal
Stockyard will be constructed in the land located within the boundaries of Pakistan Steel
Mills.
As stated earlier in section 6.2.4 the existing road is being used by the traffic generated
from the industries. Construction activities along the existing road are likely to cause
hindrance in traffic flow if not mitigated properly.
Mitigation Measures
• A temporary traffic management plan will be developed and submitted by the
contractor at least two weeks before commencement of construction and the
same will be shared with the security agencies of Port Qasim.
The main objectives of the plan shall be to maximize the safety of road users and also to
keep traffic flowing as freely as possible.
The temporary transport management plan will include consideration of the following:
• Lane availability and minimization of traffic flows past the works site;
• Agreement on time scale for the works and establishment of traffic flow/delay
requirements;
• Availability of diversion routes where necessary;
• Need for road closures and the necessary orders;
• Co-ordination with other planned road and street work; and
• Co-ordination with the agencies of Port Qasim.
6.2.13 Seismic Hazard The project area is located in Seismic Zone 2B, where 2B represents peak horizontal
ground acceleration from 0.16 to 0.24g. In this zone, designing of various types of
structures should be done on the basis of Peak Ground Acceleration (PGA). The
moderate intensity earthquake can adversely impact the development. This will be a
major negative impact.
Mitigation:
• The infrastructure for the operation of proposed project shall be designed and
constructed to withstand low to moderate earthquakes.
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-9 July, 2016
6.3 ANTICIPATED IMPACTS DURING CONSTRUCTION PHASE
Following is a brief description of impacts and their mitigation envisaged during the
construction phase:
6.3.1 Soil Soil erosion and contamination may occur on roadside and contractor’s camp due to the
following activities:
• Earth filling operations, clearing of vegetation and leveling activities can impact
the surrounding land surface;
• The unspent materials and debris produced from consumed up materials, if left as
such and allowed to mix with soil underneath, can degrade the quality of receiving
soils and may render them unfit for plantation later on;
• Leakages of oils, lubricants, chemicals, and other similar substances from their
storage area and from engines of the generators, machines, equipments and
vehicles can spoil the receiving soils and may undermine the ability of soils to
support growth of vegetation and plants;
• Non-provision of septic tanks with the temporary worksite toilets, constructed for
the labour and others, can contaminate the effluent receiving soils because of raw
nature of the effluents;
• Washing of the gadgets, machinery and equipment without proper drainage of the
washout water can adversely affect the soil quality;
• Onsite storage of the construction materials such as sand, aggregate, crushed
stone, cement, blocks, lubricants, fuels and iron bars on the land without an
intervening barrier, can degrade soil quality and may spread them with fine
particulates of the dumped materials; and
• Improper onsite storage of equipment and machinery such as wheel barrows,
mixers ,compactors and disorderly parking of machinery and equipment may
cause soil contamination from trickling or accidental leakages of oils and
lubricants there from.
Mitigation:
• All spoils will be disposed off as desired and the site will be restored back to its
original conditions;
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-10 July, 2016
• Non-bituminous wastes from construction activities will be dumped in approved
sites, in line with the legal prescriptions for dump sites, and covered;
• As applicable and needed, plantation of grasses and shrubs will be done at
appropriate place where required;
• Excavations would be kept confined to the specified foundation spots as per the
approved engineering drawings. Unnecessary excavations shall be avoided;
• Site camps for the resident labour shall not be setup on the land earmarked for
developing green belts and lawns;
• Oils, lubricants, chemicals, and other listed hazardous materials shall be stored
safely at their designated spots, enclosures or store rooms, which should be safe
from rainfall and away from any potential source of fire;
• Septic tanks of adequate capacities shall be constructed for receiving and treating
wastewater from all temporary worksite toilets and at the temporary container
offices, if any. The toilet wastewater should not be discharged untreated onto the
adjacent lands;
• All machineries and materials should be stored at the designated areas and
compounds;
• All the unspent and left over materials be completely removed offsite upon
completion of construction and the site be restored to original or near to original
condition; and
• Washout from washing of equipment and gadgets should be drained into either a
septic tank or a sand-gravel bed for removal of the grit and contaminants.
6.3.2 Construction Camp/Camp Site Due to the proposed camp sites, loss of vegetation and assets on the selected land and
dissatisfaction of rehabilitation measures during and after completion of construction
phase may occur. However, it will be a temporary and minor negative impact. For these
impacts, mitigation measures have been developed to minimize the likelihood, extent or
duration of their occurrence, and any associated adverse effects. Table 6.3 summarizes
potential impacts and proposed avoidance and mitigation measures associated with
construction camps.
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-11 July, 2016
Table 6.3: Summary of Impacts of Worker Camp & Mitigation Measures
Potential Impact Proposed Avoidance and Mitigation Measures
Environmental • Temporary habitat loss or
disturbance
• Temporary visual intrusion • Noise emissions at a single location • Waste generation • Discharge of sanitary effluent and
rainwater run-off to water courses
• Reinstate any temporary facilities to pre-existing conditions in ecologically sensitive areas.
• Implement landscaping plan for all facilities in areas where high landscape value and visual vulnerability to the proposed activities warrants site-specific landscape restoration measures.
• Operate equipment in a manner sympathetic to the ambient noise environment. Do not leave equipment idling unnecessary.
• Eliminate tonal, impulsive or low frequency noise through noise control engineering techniques where practical (fitting of mufflers, damping, etc.), and substitute for a different method if necessary (e.g., instead of hammering actions, use hydraulics).
• Provide adequate warnings of impeding works to all potential receptors within 0.5 to 1 km corridor surrounding the right-of-way via public notices and local news.
• Implement Waste Management Plan to include procedures for the classification, storage and disposal of all construction wastes and the training of employees who handle hazardous materials.
• Ensure that discharge of sewage from temporary construction facilities to surface courses does not impact soil, surface water ecology. This will be achieved through the provision of treatment facilities and by enforcing the discharge standards.
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-12 July, 2016
Potential Impact Proposed Avoidance and Mitigation Measures
Social • Worker camp sitting: consultation
surrounding potential construction camp did not reveal concerns regarding the location of proposed sites for Worker Camps.
• Tension between Communities and
Workers: cultural differences, behavior of construction workers, potential disregard for local cultural norms could lead to increased tension between local communities and the workers and camps. The scale of this impact will depend on successful implementation of mitigation measures and in part on the origin of the workforce staying in construction camps.
• Government land / PQA land will be the first preference for worker camp location, followed by land where there is a willing lessee.
• The project will seek to avoid sitting camps where their presence might contribute to any conflicts between residents.
• Employment policies which aim to
maximize job opportunities for local people will help to minimize tensions caused by different socio-cultural values.
• Training will be provided to all staff
on camp management rules and overall discipline and cultural awareness. This will include, in appropriate languages:
• A briefing on Camp Rules • A community relations orientation to
increase awareness about the local area, cultural sensitivities and the project Code of Conduct
• Awareness-raising on health
considerations, including STDs. • The construction contractor is
required to develop a Construction Camp Management Plan to address:
• Discipline • Community liaison • Ethnic tensions • Market distortion and • Communicable diseases. • A Code of Conduct and Camp Rules
will be required within the Construction Camp Management Plan, which provides policies and a disciplinary framework with respect to worker behavior.
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-13 July, 2016
Potential Impact Proposed Avoidance and Mitigation Measures
Camp Location The final location of camp site will be determined by the construction contractors and agreed by the PQA.
The construction contractor will be required to assess the environmental/social sensitivity of any additional or alternative sites prior to their approval for adoption.
Some additional mitigation measures will include:
• All efforts during the design stage shall be made to minimize the removal of
existing macro-plants at camp sites;
• The contractor(s) will provide plan for removal & rehabilitation of site upon
completion;
• Photographical and botanical inventory of vegetation before clearing the site; and
• Compensatory plantation to be scheduled when construction works are near
completion.
6.3.3 Health and Safety
a) Occupational Health and Safety
Health risks and work safety problems may result at the workplace if working
conditions provide unsafe and/or unfavorable working environment and due to
storage, handling and transport of hazardous construction material. Workers
should be provided with safe and healthy working environment taking into account
risks inherent to the particular sector and specific classes of hazards in project
area.
Mitigation measures will include:
• Insurance for labourers /workers;
• Providing basic medical training to specified work staff and basic medical
service and supplies to workers;
• Layout plan for camp site, indicating safety measures taken by the
contractor, e.g. firefighting equipment, safe storage of hazardous material,
first aid, security, fencing, and contingency measures in case of accidents;
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-14 July, 2016
• Work safety measures and good workmanship practices are to be followed
by the contractor to ensure no health risks for labourers;
• Protection devices (ear muffs) should be provided to the workers doing job
in the vicinity of high noise generating machines;
• Provision of adequate sanitation, washing, cooking and dormitory facilities
including light up to satisfaction;
• Proper maintenance of facilities for workers will be monitored;
• Provision of protective clothing for labourers handling hazardous materials,
e.g. helmet, adequate footwear for bituminous pavement works, protective
goggles, gloves etc;
• Ensure strict use of wearing these protective clothing during work
activities;
• Elaboration of a contingency planning in case of major accidents;
• Instruct foremen to strictly enforce the keeping out of non-working persons,
particularly children, off work sites; and
• Adequate signage, lightning devices, barriers, yellow tape and persons
with flags during construction to manage traffic at construction sites,
haulage and access roads.
b) Community Health and Safety
The construction activities and vehicular movement at construction sites and
access service roads may also result in road side accidents particularly inflicting
local communities who are not familiar with presence of heavy equipment and
machinery. This is a temporary and minor negative impact. Quality of ground and
surface water resources (if any) available in the nearby local communities may get
contaminate due to the construction activities, oil spillage and leakage, roadside
accidents etc. The labourers work with different transmittable diseases may cause
spread out of those diseases in the local residents.
Mitigation measures will include:
• There should be proper control on construction activities and oil spillage
leakage of vehicles;
• The labour works with different transmittable diseases should be restricted
within the construction site;
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-15 July, 2016
• Efforts will be made to create awareness about road safety among the
drivers operating construction vehicles;
• Timely public notification of planned construction works;
• Close consultation with local communities to identify optimal solutions for
diversions to maintain community integrity & social links;
• Seeking cooperation with local educational facilities (school teachers) for
road safety campaigns;
• Provision of proper safety and diversion signage, particularly at
sensitive/accident-prone spots;
• Setting up speed limits in close consultation with the local stakeholders;
• If identified, consider additional guard rails at accident-prone stretches and
sensitive locations;
• The communicable disease of most concern during construction phase
should be prevented by successful initiative typically involving health
awareness; education initiatives; training heath workers in disease
treatment; immunization program and providing health service;
• Reducing the impacts of vector borne diseases on long-term health effect
of workers should be accomplished through implementation of diverse
interventions aimed at eliminating the factors that lead to disease, which
includes: Prevention of larval and adult propagation of vectors through
sanitary improvements and elimination of breeding habitat close to human
settlements and by eliminating any unusable impounding of water;
• During construction work pedestrian and vehicular passages should be
provided for crossing near settlement;
• Fencing around the camps should be strong enough so that it can not be
broken easily by local people for making passages; and
• Use of water should not disturb public water availability and source of
water should be selected carefully.
c) Emergency Response
Disasters such as earthquake, flooding, fire and etc, may occur and they must be
considered for minimizing their impacts.
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-16 July, 2016
Mitigation measures will include:
An Emergency Response Plan for earthquakes and manmade disasters will be
implemented by the PQA during Project Execution. Emergency Response Plan
will be implemented in close consultation with the disaster management
authorities, fire fighting department, bomb disposal squad, hospitals and
paramedics. In addition, training of the staff/employees regarding the emergency
procedures/plans will be regularly conducted. In this regard an Emergency
Response Plan prepared and is attached as Annexure-V
6.3.4 Air Quality Air quality will be affected by fugitive dust emissions from construction machinery,
unpaved surfaces and construction vehicles. Emissions may be carried over longer
distances depending upon the wind speed, direction, temperature of surrounding air and
atmospheric stability. Besides, multifarious construction activities and increased vehicular
traffic (construction vehicles) would also contribute to the localized airborne dust. Once in
the air, the larger size particles, under influence of gravity, tend to settle down in the
immediate vicinity of the source. The Suspended Particulate Matter (SPM) of the size
smaller than 10 micrometer (PM10) tends to remain suspended in the environment for
much longer and persistent time and is an environmental hazard. The objectionable
impacts of settling of the suspended dust would be its dry deposition on vegetation, glass
windows, motor vehicles, buildings, and other exposed surfaces. Exhausts from fossil fuel
burning in the construction machinery will also deteriorate local air quality. Similarly,
exhausts from generators can also have impacts on air quality in the vicinity.
The critical sources of dust pollution during the construction phase will be:
• Unpaved road surface; and
• Transportation of materials and other construction activities.
The overall impact on the quality of air during the construction phase will, however, be
temporary and limited to the project’s implementation phase only.
Mitigation measures will include:
• All vehicles, machinery, equipment and generators used during
construction activities should be kept in good working condition and be
properly tuned and maintained in order to minimize the exhaust emissions;
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-17 July, 2016
• Blowing of dust from potential sources at the worksite should be avoided
by shielding them from the exterior, for example using polythene curtains
or raising a fence of corrugated sheets around areas of active
construction;
• Blowing of dust and particulate matter from stockpiled loose materials (e.g.
sand, soil) should be avoided either by sheeting them with tarpaulin or
plastic sheets or by sprinkling them with light shower of water;
• Open burning of solid waste from the contractor’s camps should be strictly
banned;
• Preventive measures against dust should be adopted for on-site mixing
and unloading operations. Regular water sprinkling of the site should be
carried out to suppress excessive dust emission(s);
• Only good quality oils, petroleum products, additives and spares should be
used in the machinery, generators, and the construction vehicles. Usage of
used oil should be strictly prohibited;
• Emissions from power generators and construction machinery are
important point sources at the construction sites. Proper maintenance and
repair is needed to minimize the hazardous emissions; and
• SEQS applicable to gaseous emissions generated by construction
vehicles, equipment and machinery should be enforced during
construction works.
As the existing road have two broad lanes in each direction. It is planed that only one half
of the lane on each side will be occupied for construction activities and rest of the lanes
will be present for the movement of traffic. As the lanes of existing road are paved/metal
roads, therefore, dust pollution or particulate matter will not present. However, some of
dust problems caused during the construction phase of the Project can be effectively
mitigated by the implementation of simple procedures by the Contractor including, but not
limited to, the following:
• Unpaved roads (used for earthmoving equipment and general transport)
should be regularly sprayed with water during dry weather;
• All excavation work should be sprinkled with water;
• Construction workers should be provided with masks for protection against
the inhalation of dust;
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-18 July, 2016
• Vehicle speed in the project area should be prescribed not more than 20
km/ hr and controlled accordingly;
• Vehicles used for construction should be cleaned, tuned properly and
regularly to control fugitive dust and exhaust gases emission; and
• Road marking and safety signs should be provided at work site.
6.3.5 Noise and Vibrations Noise is a by-product of human activity, and area of exposure increases as function of
mobility and construction activities. Sources of noise during construction are heavy
machinery such as bulldozers, excavators, stabilizers, concrete mixing plant, pneumatic
drills and other equipment. The above machinery is expected to generate noise levels
that would be severe in the areas whereas previously no construction is done but the
condition is not applicable in the proposed project. Noise modeling for construction
equipment proposed for the CCS project has been carried out and modeling results
along with modeling methodology is attached as annexure III. Noise generated by
construction machinery can likely to affect sensitive receptors located within 50 meters
of the proposed project. This impact is temporary and moderate adverse in nature.
Table 6.4 illustrates maximum permissible noise levels for different situations and is
given below:
Table 6.4: Maximum Limits of Noise Levels
Noise Level dB (A) Situation
194 Lung damage
180 Ear drum rupture
150 Absolute limit with ears protected
150 Maximum of instantaneous noise
135 Absolute maximum with ears unprotected
100 Prolonged noise causing permanent damage
90 Factory work for an 8-hour day, 5 days a week
*85 Ear protection should be worn
80 Noise on building or construction sites
70 Normal road traffic near residential areas Source: “Environmental Degradation” by Engr. Col. Mumtaz Hussain *Above 85 dB (A) ear protection devices should be worn.
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-19 July, 2016
According to Table 6.5 given below, which presents the damage risk criteria for
hearing loss, noise level above 110 dB(A) can be tolerated for half an hour only.
Table 6.5: Damage Risk Criteria for Hearing Loss
Sr. No. Maximum Allowable Duration per day (Hours) Noise-Level in dB (A)
1 8 90
2 6 92
3 4 95
4 3 97
5 2 100
6 1 ½ 102
7 1 105
8 ½ 110
9 ¼ or less 115 (Max.) Source: Occupational Safety and Health Administration, OSHA, USA
The likely impacts due to noise are:
• Persistently higher noise levels can produce psychological effects of distraction of
attention, irritation and short temperedness in the exposed persons;
• Noisy settings and higher background levels can cause temporary threshold shift
and the consequent habit of speaking loud, which may cause damage to vocal
cords in the persons exposed;
• Noise produced from moving construction vehicles and blowing of pressure horns,
at times, could be intolerable particularly during quiet hours of night; and
• Vibrations from machinery and equipment such as hand held compactors and
concrete vibrators can produce easy fatigability and generalized aches in the
persons operating these machines.
All mitigation measures mentioned below should be taken in order to minimize the
impacts of noise in the project area. These measures include, but are not limited to
the following:
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-20 July, 2016
• Selection of up-to-date and well maintained plant or equipment with reduced noise
levels ensured by suitable in-built damping techniques or appropriate muffling
devices;
• Confining excessively noisy work to normal working hours in the day, as far as
possible;
• Providing the construction workers with suitable hearing protection like ear cap, or
earmuffs and training them in their use;
• Preferably, restricting construction vehicles movement during night time;
• Heavy machinery like percussion hammers and pneumatic drills should not be
used during the night without prior approval of the client;
• Vehicles and equipment used should be fitted, as applicable, with silencers and
properly maintained;
• Use of low noise machinery, or machinery with noise shielding and absorption;
• Contractors should comply with submitted work schedule, implement regular
maintenance and repairs; and employ strict implementation of operation
procedures; and
• Public hearings to discuss appropriate solutions and materials to control noise.
6.3.6 Waste (Construction and Hazardous Waste) Due to construction activities, waste will be generated at construction and contractors
camp site. The construction waste will include wastewater, oil spillage from machinery,
domestic waste and solid waste etc. The handling and storage of oil, asphalt/bitumen
may be a source of environmental pollution as a hazardous waste. This will result in
unhygienic conditions, health risk to work force and public at the camp site. The likely
impacts of solid waste are:
• Insecure and unhygienic disposal of the solid wastes generated at the worksite,
particularly garbage and trash may cause degradation of soil and land;
• Insecurely disposed off heaps of wastes containing kitchen garbage and food
waste can serve as breeding grounds for the disease spreading vectors and
rodents; and
• Throwing away of solid wastes into water channels and the wastewater network
can result into choking of the latter.
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-21 July, 2016
These impacts are temporary and minor adverse in nature.
Mitigation measures will include:
• Wastewater from contractor’s workshop and equipment washing yards would be
passed through oil/grease separator to remove oil/ grease contaminants before
discharging it into the existing natural drains;
• An efficient and responsive solid waste management system should be devised
for the entire duration of the construction phase. Such a system should provide for
separate collection of different categories of construction wastes. The wastes
which will be reusable/recyclable (iron bars, aluminum, etc) should be sold to
waste vendors and those which cannot be sold out (block pieces) may be used
as a filling material for leveling the depressions, subject to technical feasibility;
• Solid waste generated during construction and camp sites will be safely disposed
in demarcated waste disposal sites and the contractor will provide a proper waste
management plan;
• Proper labelling of containers, including the identification and quantity of the
contents, hazard contact information etc.;
• Training of work force in the storage and handling of materials and chemicals that
can potentially cause soil contamination;
• Training of employees involved in the transportation of hazardous material
regarding emergency procedures;
• Providing the necessary means for emergency response on call 24 hours/day;
• The sewage system for camps will be properly designed (pit latrines or, as
required, septic tanks) to receive all sanitary wastewaters;
• Lined wash areas will be constructed within the camp site or at site, for the receipt
of wash waters from construction machinery;
• Construction workers and supervisory staff should be encouraged and educated
to practice waste minimization reduce, reuse and recycling the waste for disposal;
and
• Prohibit open burning of solid waste.
6.3.7 Surface and Groundwater There is a possibility that various materials like fuel, lubricant oil and other oily products,
which are used during the construction phase may contaminate groundwater (if any), if
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-22 July, 2016
they are not handled properly. During the construction phase, the sanitary wastewater will
be generated at the workers’ camp(s). If this wastewater is allowed to stagnate in water
ponds on the site, it can percolate into the soil, thereby, contaminating groundwater,
these impacts are temporary and minor negative in nature.
Mitigation measures will include;
• Protection of groundwater reserves from any source of contamination such as the
construction and oily waste that will degrade its potable quality;
• The solid waste will be disposed off in designated landfill sites to sustain the water
quality for domestic requirements;
• Water required for construction is obtained in such a way that the water availability
and supply to nearby communities remain unaffected;
• Regular water quality monitoring according to determined sampling schedule;
• Take precautions construct temporary or permanent devices to prevent water
pollution due to increased siltation; and
• Wastes must be collected, stored and taken to approve disposal site.
6.3.8 Biodiversity Conservation and Natural Resources Flora
Trees are vital ecosystem, which perform variety of functions for the improvement of
environment such as reduction in air pollution, noise abatement, cooling effect on earth,
supply of oxygen etc. Conocarpus, Eucalyptus, Lignum, Neem and Pipal are the common
trees found in project area.
Exhaust of noxious gases from movement of heavy machinery will further pollute air
which will adversely affect health and vigor of plants located in nearby project area
To minimize the impacts on flora, following measures will be adopted during construction
stages:
• Only plants coming in the alignment of the conveyor, shall be removed;
• Camp sites will be established on waste/barren land rather than social and
commercial land. However, if such type of land is not available, it will be ensured
that minimum clearing of the vegetation is carried out and minimum damage is
caused to the plants;
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-23 July, 2016
• Construction vehicles, machinery and equipment will remain confined within their
designated areas of movement;
• The Contractor’s staff and labour will be strictly directed not to damage any
vegetation;
• Contractor will provide gas cylinders at the camps for cooking purposes and
cutting of trees/bushes for fuel will not be allowed; and
• A tree plantation program will be formulated by the PQA.
Fauna As the project area is modified industrial area, there are no significant faunal species
present in the project area. There will be no significant negative impact of fauna by the
execution of the project. However, mammals, such as dogs, cats, etc will avoid these
areas for fear of being persecuted. Same will be the case with reptiles. Similarly, birds will
try to find shelter and food elsewhere and will tend to move away from the project area
due to construction activities. Overall, the impact on fauna of the area is insignificant in
nature.
6.3.9 Disposal of Mucking Material Earthwork operations during project construction will not open up any scars on the land
around the project area. The impacts of earthwork are temporary and minor adverse
negative in nature.
Mitigation measure will include:
• Proper landscaping, which should be given due consideration along with re-
establishment of the indigenous vegetation (if any); and
• The excavated materials that are unsuitable for use will need to be stored,
transported and disposed off appropriately at designated sites.
6.3.10 Disruption of Existing Public Utilities/ Infrastructure There may be some disruption to the already existing utilities like electricity poles,
underground telephone, water supply, natural gas supply, power transmission lines etc. in
the project area during the construction phase. These impacts are, however, temporary
and minor adverse in nature.
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-24 July, 2016
Mitigation measures will include:
• Marking and rehabilitation of existing utilities before construction to avoid any
inconvenience to the residents of the project area or provide them with alternate
arrangement during the construction period.
6.3.11 Traffic Management Due to the construction activities, proper traffic management may pose a challenge in the
project area. This may result in traffic jams and cause inconvenience to the people
passing through the project area due to movement of vehicles carrying construction
materials. It will also increase the traffic load on the existing road network, thus
deteriorating the existing condition of the road. Also, the movement of vehicles along the
haulage routes may cause soil compaction and alteration of percolation, and damage to
properties and utilities. This impact is temporary and minor negative in nature.
Mitigation measures will include:
• Proper traffic management plan will be needed to avoid traffic jams/public
inconvenience;
• Coordinated planning of traffic diversions by the Contractor and PQA in
accordance with the construction program with advance warnings to the affected
road users;
• Construction vehicles, machinery and equipment will move or be stationed in the
designated ROW to avoid un-necessary compaction of soil.
• Availability of continuous services of the trained persons in the diversion and
control of traffic; and
• The executing agency is required to maintain liaison between the Contractors
representatives and local travelers to facilitate traffic movement during
construction stage.
6.3.12 Economic Activity Due to the construction of the proposed project, economic activity will be generated in the
project area as the labourers and semi-skilled staff will have an opportunity to work for
the construction of the proposed project. This will help in developing their skills and
capacities. This is a moderate beneficial impact.
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-25 July, 2016
6.3.13 Lifestyle and Culture There are chances of arising the issues related to cultural differences/conflict between
the contractor’s workforce and the local inhabitants, conflicts arising due to the mix of
local and migratory job seekers as the use of local resources and products will be
increased. In this situation, local residents may resist contractor’s workforce attitudes,
cultural clashes particularly when local/international contractors are engaged, social
disturbance and dissatisfaction with employing outsiders may arise. This impact is
temporary and minor adverse in nature.
This impact can be mitigated by adopting the following mitigation measures:
• Timely public notification and announcement of mobilizing equipment;
• Local labour should be employed for construction works; and
• Water supply and sanitation facilities, Contractor’s workforces could exacerbate
the existing shortages and environmental hazards; contractor should primarily
seek their own sources of water.
6.3.14 Impacts on Sensitive Receptors As the project area surrounded by different kind of industries, which might be considered
as sensitive receptors as the different gas and pharmaceutical industries are located on
either side o f the coal conveyor belt. These industries are highly sensitive as the coal fire
might be a major impact on these industries. Also, the workers working in the industry
might be affected in case of noise and dust emission. Following is the list of industries
located on either sides of the conveyor belt;
Table: List of industries located on the either side of the Conveyor Belt
Sr. No.
Right Hand Side Left Hand side
1 PARCO Pearl Gas Garib Sons pvt. Ltd.
2 Pharm Evo Pvt. Ltd. Pak Shaheen Container
3 Wak Gas Limited MTO CFS
4 SSGC Indus
5 KE FATCO
6 PAPCO
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-26 July, 2016
A mosque Masjid Ameer Hamza is also located on the left side of the
proposed conveyor belt. During construction phase of the proposed project,
the persons will face inconvenience to approach the mosque to offer their
prayers. This impact is temporary and low adverse in nature.
Mitigation Measures:
• A covered conveyor belt will be installed to stop the dispersion of the coal dust.
• Automatic water sprinklers will be installed in the conveyor belt to sprinkle water in
case of fire hazard.
• Fire alarms will be installed wherever required to handle the fire hazard.
• Immediate actions will be taken to avoid the fire hazard as emergency response
team will be timely mobilized to take actions.
6.3.15 Impacts of Heavy Vehicles on the Existing Road Network
The plying of heavy vehicles on the existing road network may result in air and noise
pollution due to tire-road friction and damage to roads and traffic congestion. However,
the impacts would be temporary and moderate negative in nature for which the following
mitigation measures are proposed:
• Any vehicle with an open load carrying area used for transport of potentially dust
producing materials shall have properly fitted side and tailboards. Materials having
potential to produce dust shall not be loaded to a level higher than the side and
tail boards and shall be covered with clean tarpaulin in good condition. The
tarpaulin shall be properly secured and extended to at least 300 mm over the
edges of the sideboard and tailboard;
• The Contractor shall not use any vehicles either on or off road with grossly
excessive noise pollution. Noise mufflers shall be installed and maintained in good
condition on all motorized equipment under the control of the contractor;
• Timely maintenance of affected roads to avoid any inconvenience to the road
commuters.
6.3.16 Physical and Cultural Resources As discussed earlier there is a Mazar of Kamal Shah and no any other physical/cultural
resources in the project area were observed. During construction, there is no chance of
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-27 July, 2016
finding archeological remains as the route is passing through already allocated median. If
in case, chance of finding archeological remains during construction, the contractor shall
immediately report through Supervision Consultant to Project Management Unit (PMU) of
Port Qasim to take further suitable action to preserve those antiques or sensitive remains.
6.3.17 Storage of fuel on Site Storing diesel fuel on site offers many advantages for a heavy-equipment fleet. One can
get price break for buying fuel in bulk and don’t have to wait on fuel delivery services to
top up trucks and machines.
For construction fleets, above ground storage tanks (ASTs) are almost always the best
choice, ASTs are vulnerable to high winds, flooding, theft and vandalism.
There is also the possibility for soil and groundwater pollution from leaks. Even one drop
per second can release of 400 gallons of fuel into the groundwater over the period of one
year if there is no secondary containment.
Care should be taken for keeping it free from water and contamination.
6.4 ANTICIPATED IMPACTS DURING OPERATIONAL PHASE
The anticipated potential environmental impacts related to the proposed project have
been studied for the operational stage of the project and are discussed as under.
6.4.1 Ecology
During the operation phase there is fewer chance of habitat disturbance. Hence no major
impacts are envisaged. Following remedial measures should be taken to reduce the
impacts:
Flora During the operation stage, raising of new plants/trees at available spaces will have a
positive and permanent impact. Minor negative impacts are envisaged on the flora during
the operational phase of project. Landscaping will be done along the corridor of conveyor
belt and stock yard at available spaces. The presence of adequate flora, along the route
of conveyor belt and at stockyard, will absorb flue gases, emitted from the already
existing industrial units, standby diesel generators, other machines and vehicles, which
shall in turn improve air quality.
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-28 July, 2016
Fauna In many ways, fauna of the project area is dependent upon flora for its resting, nesting
and roosting activities. With the improved flora of the project area, due to rising of trees,
the fauna and especially the avi-fauna shall be attracted to the area. The birds, which
were scared away due to noise and degradation of their habitat, shall return to the area.
Plantation on road side and stockyard shall not only reduce the noise and air pollution but
will also be a source of attraction for the birds.
6.4.2 Wastewater collection and Treatment at Stockyard Wastewater collection, conveyance and disposal system shall be installed at stockyard
where toilets for the employees and workers are planned. Proper treatment for oil and
grease removal shall be carried out prior to the disposal into the septic tank and soak pit.
Monitoring shall be carried out at specified locations for any possible incident of
contamination and non-compliance to SEQS.
Wastewater will be collected in underground Septic tank and soakpit next to
administration building inside stockyard.
In areas where detergents are handled (washing and cleaning area) a coalescence
separator with integrated mud separator and a subsequent control and sampling manhole
is proposed before connected to the sewage system.
6.4.3 COAL DUST The major sources of air pollution in this project are coal dust, the concentration of coal
dust pollution (SPM) in the air varies with the size, moisture content of coal to be stored
and transported through this project.
On the macro-environment the impact would be reduction in the air emissions due to
expected switchover to a more environment friendly mode of transport which would curtail
the manual loading and unloading activities from PIBT, reduction in truck traffic from port
roads as well as from the national highways, motorways, increased vehicular traffic and
delays in traffic results in excessive vehicular emissions specially in the events of road
jams.
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-29 July, 2016
The major sources of coal dust (SPM) in this project are:
a) Transfer Stations
b) Coal conveyor belts
c) Stacking and Reclamation of Coal in stockyard
Mitigation Measures
Following mitigating measures are suggested:
All the coal handling units need effective dust control system. To prevent the dust
emissions there is no one single way. The dust control system must be based on total
concept approach. The approach for dust control should be based on to keep the dust
emissions confined, sealed and suppressed, with the combination of these three the
maximum dust control be attained.
Confine dust For maximum efficiency of dust control at transfer points and conveyor belts the source of
coal dust should be enclosed to provide protection from ambient conditions, especially
wind. To properly confine dust, enclosures will be created using wind screens and chute
baffles etc as defined in the applicable design codes.
Sealing During the design, construction and operation the sag of conveyor belt must be
controlled. The sag of belt between idlers will be controlled by using impact or slider
beds, along with skirting. Without the use of the impact or slider beds, the belt may sag
between idlers, allowing material and dust to easily escape. Skirt seals are designed to
take the conveyor dynamics into account. And they prevent material from escaping
through the gaps caused by belt sag. The most effective skirt seals have flexibility. This
allows the seal to conform to the ever changing belt surface. These seals will provide
optimal seal with low maintenance and little belt wear.
Suppress The moisture content of the coal can have an effect on dust emissions. However, as
crushing/friction between coal particles during the transportation, loading and unloading
creates new fine particles and the moisture content is reduced by evaporation during the
activities. This, in turn, diminishes the suppressive effect, requiring a mechanical need for
moisture enhancement. This is where a dust control system is necessary. Wet
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-30 July, 2016
suppression systems control dust emissions and maintain relatively high material
moisture content.
The fogger system is recommended for this project to control the coal dust emissions at
coal stockyard. The fogger systems can agglomerate the dust particles. This increases
the density and forces the particles to settle at a faster rate. When water droplets
produced from fogger systems and dust particles collide, they agglomerate. This action is
achieved by fogging the water, thus forming a droplet size that is close to the size of a
dust particle. Another benefit of a fogger system is the low volume of water required to
achieve effective dust control. The most effective and maintenance free fogger systems
use water only, with no air or chemical injectors required.
Belt cleaners also have a positive effect on dust control. These additional controls reduce
carry-back that produces piles under the conveyor belt and fugitive dust created by the
return rolls “beating” the dust and dirt from the belt cover. This eliminates dangerous
cleanup around conveyors and reduces downtime due to the cleaning. An efficient belt
cleaner also prevents unnecessary wear on the conveyor belt and conveyor components.
Most importantly, this will also reduce dust emissions produced from weathered piles
escaping in to the air.
Provisions for Dust Emission Control at Transfer Stations and Load-out Stations The load-out station will have in-built dust suppression system to suppress the coal dust.
Regular maintenance of the parts of the transfer stations should be mandatory.
Controlled speed of conveyor belt is also helpful in reducing the emission rate.
As discussed in the section 3.4.1 of this report the transfer chutes at transfer stations will
be provided which are necessary for the effective transfer of coal from one conveyor belt
to another. Chutes will be completely enclosed and be supplied with a dustproof hinged
inspection door for inspection and cleaning. Transfer chute sides will be designed so that
material will not buildup inside the chute and cause an obstruction to material flow. The
design will be such that the commodity will not spill over moving parts. No apertures or
ridges will be present in order to prevent spillage or build-up of material.
All receiving hoppers that are necessary for the effective receipt of product will be
provided. Hoppers will be so designed and installed that no dust will escape when
commodity is received in the hopper. The opening at the bottom of hoppers will be
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-31 July, 2016
completely dust sealed on the receiving chute of the conveyor. The sides of hoppers will
be so designed that material will not build up in the hopper and cause an obstruction to
material flow.
Dust Emission Control measures at Conveyor Belts Proper design, operation and maintenance of the conveyor belts and allied parts of the
conveyor belts, controlled speed of conveyor belt and covers over the conveyor belts can
reduce the coal dust emissions from the conveyor belts.
As discussed in section 3.4.1 the troughed belt conveyors will be as of ISO standards but
designed generally in accordance with B.S. 2890 (latest): Efficient and readily accessible
means of adjustment will be provided on the head and tail drum shafts for tracking the
belt. The belt conveyor structure will be designed to allow easy and simple access for
maintenance and replacement of idlers. Design will be such as to ensure correct
tensioning of the belt under all conditions. Removable protective screens or covers will be
provided around back weights and pulleys.
Dust Emission Control measures at Coal Stockyard For dust suppression of coal stockpile sprinkler system will be provided. For sprinkling of
the water to stockpile; fogging arrangement and impact water gun will be installed. The
dust suppression arrangements will be made all around the coal stockyards to suppress
the coal dust; generated during stacking and reclaiming. For dust suppression at coal
stockyard wind breaker and dust suppression wall will be provided in addition to the
sprinkler system.
Rain water may also be used for sprinkler purpose after its treatment; for which rain water
sedimentation basin will be provided.
Greenbelt Development Increasing vegetation in the form of greenbelt is one of the preferred methods to mitigate
air and noise pollution. Plants generate oxygen, serve as a sink for pollutants, reduce the
flow of dust and reduce the noise too.
Green House Gases and Local Air Pollutant Emissions Reductions Coal Conveying System reduces the overall amount of vehicle kilometers traveled (VKT)
in the port area and highways by shifting the coal to high-capacity trains that can carry up
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-32 July, 2016
to 2400 tonnes of coal at a time. Fewer trains transporting the same amount of coal
reduces traffic congestion, and presents the opportunity to replace more polluting
vehicles.
6.4.4 Noise Noise is generally accepted from local traffic and industries in the industrial estates as a
consequence of industrialization.
Depending on the eventual traffic flows most road sections near the coal conveyor route
are expected to carry less traffic as compared to the transport of coal by road. The noise
in the vicinity will not increase from the SEQS Limits for the industrial areas.
6.4.5 Solid Waste Due to operational activities of Coal Conveying System waste will be generated. Handling
and storage of wastes may be a source of environmental pollution. This will result in
unhygienic conditions, health risk to CCS operators. No hazardous waste is expected to
be generated in operation phase except during the maintenance works and
miscellaneous municipal wastes generated. Putrefaction of the organic component of the
uncollected wastes may give rise to foul smells and will affect the aesthetics of the project
area.
Mitigation measures will include:
• Installation of sign boards for keeping clean the area and solid waste
management at suitable locations.
• Proper solid waste management arrangements shall be made at stockyard.
• Management of hazardous waste during maintenance works will be given due
consideration.
An efficient and responsive solid waste management system should be devised, and
maintained during operation phase.
6.4.6 Socioeconomic
Economic Benefits
The transport of coal through train shall initially reduce the gap between electric power
demand and supply, which will give a boost to the economy by way of employment and
increase in the GDP growth.
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-33 July, 2016
Social Benefits
Additional employment will be generated at the project and power plants and the use of
additional power will create employment in various industries
Activities during the operations would contribute to local economy by providing job
opportunities. These benefits will definitely increase the socio-economic status of the
area. Hence the overall impact will bring the positive change.
6.4.7 Improvement of Infrastructure Facilities The development of project will also create or improve the amenities / services like
power, railway, communication, health, education, etc. thereby improving the life of
overall populace of the country.
6.4.8 Wider Economic Growth The proposed project will increase the economic activities all around the country and
area, creating avenues for direct/indirect employment in the post project period.
Implementation of the project will enhance the use of coal for power generation, thus
increasing the chances mining activities of coal in country specially the Thar coal.
There would be a wider economic impact in terms of power generating and reducing the
shortage of electricity in the country.
6.4.9 Better Rail Transportation During the operation phase the project the tracks and other infrastructure related to the
rail transport will likely to be improved without any obstruction. As more cargo will be
diverted to rail traffic conditions will improve due to reduction in traffic flow which further
suggests improved air quality and general environmental conditions associated with
vehicular traffic along road side. Hence the project will bring the positive change.
6.4.10 Reduced Health Risk and Accidental Hazards The same applies while ensuring maximum operational safety it suggests that accidental
hazards are minimized. As well as diversion of cargo traffic from road to railway will
greatly reduce the accidents associated with movements across the roads. Health /
accidental risks due to vehicular traffic/exhaust emissions experienced in congested
traffic conditions is likely to be avoided by the commuters travelling on roads thereby
giving them a free or no exposure environment.
Section–6 Anticipated Environmental Impacts and Mitigation Measures
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 6-34 July, 2016
6.4.11 Fire Hazard The ignition source involves frictional heat generated by the conveyance process itself.
Rollers that support the conveyor belt can occasionally jam or lock due to lack of
lubricant, accumulation of dirt or mechanical breakdown.
Once locked, the idler bearings can overheat to a point where they can ignite any coal
that has accumulated around the roller bearing support structure. This kind of fire can
then quickly spread into the coal on the conveyor.
Mitigation measures will include:
• Automatic water sprinklers will be installed in the conveyor belt to sprinkle water in
case of fire hazard.
• Fire alarms will be installed wherever required to handle the fire hazard.
• Install firefighting equipment and provide first aid, security, fencing, and
contingency measures in case of accidents;
• An Emergency Response Plan for earthquakes and manmade disasters will be
implemented by the PQA during Project Execution. Emergency Response Plan
will be implemented in close consultation with the fire fighting department. In
addition, training of the staff/employees regarding the emergency
procedures/plans will be regularly conducted.
6.4.12 Emergency Management Disasters such as earthquakes, flooding and other disasters such as local flooding of
storm water channels, fires may occur, and that must be considered for minimizing their
impacts.
Mitigation measures will include:
An Emergency Response Plan for earthquakes and manmade disasters including
violence and terror activities will be developed by the PQA. Emergency Response Plan
will be implemented in close consultation with the Rescue Service, Fire Fighting
Department, bomb disposal squad and paramedics. In addition, training of the
staff/employees regarding the emergency procedures/plans will be regularly conducted.
The Emergency Response Plan is attached as Annex V.
Section–7 Environmental Monitoring and Management Plan EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-1 July, 2016
SECTION –7 ENVIRONMENTAL MONITORING AND MANAGEMENT PLAN
7.1 ENVIRONMENTAL MANAGEMENT
Proper Environmental Management includes allocation of resources for mitigation of
any potential environmental impact that may be caused due to the implementation of
the project. For effective management of the environmental impacts identified in
Section–6 of this EIA Report, a comprehensive Environmental Management and
Monitoring Plan (EMMP) has been prepared and will be followed during design,
construction and operation phases of project.
The objective of the EMMP is to provide framework for the implementation of the
proposed mitigation measures during all three phases of the proposed project. The
proper implementation of the EMMP will ensure that all adverse environmental
impacts identified in the EIA are adequately mitigated, either totally prevented or
minimized to an acceptable level and required actions to achieve those objectives
are successfully taken by the concerned institutions or regulatory agencies. The
implementation of EMMP should be carefully coordinated with the design and
construction program of the project to ensure that relevant mitigation measures are
implemented at the appropriate stage and adequate resources are allocated to
achieve the desired results.
For effective environmental management, the Client should assign the necessary
responsibilities to an Environmental Committee (EC) through EPC Contractor
(EPCC), who should be responsible for implementation of the EMMP of the proposed
project. The EPC will be assisted by an Environmental Expert and a Social Expert in
implementing the mitigation measures proposed in EMMP.
The EPC Contractor shall be responsible for the implementation of the proposed
project under the supervision of PD Coal Conveying System, PQA. The Contractor
should be bound to follow the provisions of the contract documents especially about
environmental protection and apply good construction techniques and methodology
without damaging the environment. Obligation of the contractor, to safeguard,
mitigate adverse impacts and rehabilitate the environment should be addressed
through environmental provisions in the contract document.
Section–7 Environmental Monitoring and Management Plan EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-2 July, 2016
7.1.1 Environmental Committee and its Responsibilities PQA will form up an Environmental Committee (EC), which will be responsible for the
environmental management and supervisory affairs during the construction phase of
the proposed project.
The responsibilities of the Environmental Committee (EC) are as follows:
To ensure implementation of all the proposed mitigation measures proposed
in EMMP during the construction of the project;
To organize routine monitoring of motor vehicle emissions, air quality, traffic,
noise and vibration; etc. In case, the noise and emission levels exceed the
acceptable levels; a penalty or ban must be enforced;
To develop operational guidelines and implementation schedule;
Receiving complaints from industries, institutions and assisting the local
environmental authority including liaison with EPA Sindh; and
To ensure that the proposed project is implemented in an environment
friendly manner, causing least harm to the existing environment including
public health, flora, fauna, sites of religious and cultural significance etc.
7.1.2 Equipment and Instruments Environmental monitoring during different stages of project will be carried out by the
EPA certified laboratory hired by PQA during construction and operational stages of
the proposed project.
7.2 WORKER’S HEALTH AND SAFETY
During the period of construction at site, EHS Officer will ensure that the contractor
bears the responsibility for worker’s safety, safe working practices and for providing
adequate and appropriate facilities for safety, fire protection, medical aid, potable
water supply and sanitation. Emphasis would be on health and safety training of the
personnel. Safety instructions, handbooks, charts, diagrams etc. will be printed in
English as well as Urdu. The workers would be given appropriate training for
handling hazardous materials and goods. World Bank guidelines relating to worker’s
health and safety would be incorporated into the PMU’s Health and Safety
Procedures. For eye and face protection it will be mandatory on the Construction
workers and other personnel in emergency situations to wear safety glasses, for skin
protection to wear protective gloves, and for respiratory protection, positive pressure
Section–7 Environmental Monitoring and Management Plan EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-3 July, 2016
air line with full-face mask and escape bottle or self-contained breathing apparatus
will be made available for emergency use. For general protection, wearing of
overalls, helmets and safety shoes will be made obligatory, and provision will be
made for safety shower and eye wash. Restoration of site: It will be contractor’s
responsibility to restore the sites of excavation for the supporting structures by
removing the debris and construction equipment and materials No attempt will be
made to dispose of residual waste or unused materials on the Corridors. Health,
Safety & Security Commitment of the project will have the following components:
• Monitoring implementation of Health and Safety Plan to prevent and reduce
accidents and occupational diseases among workers of the project as well as
facilities affiliated with operations within its jurisdiction.
• Periodic programme for fire, safety and accident prevention
• Good housekeeping practices
• Regular and periodic course on general safety health and hygiene.
• Providing appropriate signage throughout the corridors
• Providing a site safety handbook.
• Providing on site publicity on safety instructions through conventional notice
boards.
7.3 ANTICIPATED IMPACTS DURING CONSTRUCTION PHASE
The Environmental Management and Monitoring Plan (EMMP) provides the
framework for implementation of mitigating measures, environmental management
and monitoring during the construction and operation phases of the proposed project.
Table 7.1 Portray impacts, targets, mitigations and the responsible organizations for
the implementation of the mitigation measures during the design, construction and
operation phases respectively.
Section–7 Environmental Monitoring and Management Plan EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-4 July, 2016
Table 7.1: Environmental Management Plan
Sr. No. Parameters Target Mitigation Responsibility
Design Phase 1 Air Quality To control the dust emissions
from coal handling activities All machinery, equipment, vehicles, and generators used
during construction and operation activities should be selected of latest technology keeping in view the dust emissions from the coal handling activities.
The selected equipment for coal handling should have the inbuilt features of dust control and should be kept in good working condition, be properly tuned and maintained in order to minimize the emissions;
Blowing of dust from potential sources at the project site should be avoided by shielding them from the exterior, for example using the covers over potential sources of dust, wind breaker walls, dust suppression walls and provide water sprinkling arrangements at site.
Preventive measures against dust should be adopted for on-site loading and unloading operations. Regular water sprinkling of the coal stock piles should be carried out to suppress excessive dust emission(s);
Emissions from power generators and other machines are important point sources at the project. Proper selection operation and maintenance manuals are needed to minimize the hazardous emissions.
EPCC, SC and PQA
2 Noise and vibration To control Noise and vibration Selection of new generation equipment having environment friendly technology for coal handling with reduced noise levels of noise ensured by suitable in-built damping techniques or appropriate muffling devices;
Foundations of the equipment should be designed and constructed as per the recommendations of manufacturer to avoid the unnecessary vibration and noise; and
Construction schedule should confine excessively noisy work to normal working hours in the day, as far as possible
EPCC, SC and PQA
3 Fire To control fire hazard Firefighting arrangements should be planned and designed for the project as required by the international
EPCC, SC and PQA
Section–7 Environmental Monitoring and Management Plan EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-5 July, 2016
Sr. No. Parameters Target Mitigation Responsibility
design codes and operational standards for coal handling facilities.
Proper cleaning mechanism and solid waste management system including hazardous waste should be devised to avoid fire hazard.
4 Wastewater Avoid downstream water pollution
Proper wastewater management plan should be planned and designed for the project.
Suitable wastewater treatment and disposal technology for the treatment and disposal of wastewater should be recommended.
Contaminated water from the sprinkling and firefighting activities laden with coal particles should be collected treated and reused.
EPCC, SC and PQA
5 Storm water Avoid downstream water pollution
Storm water management system (collection treatment and disposal) for stockyard keeping in view the natural drainage pattern of site should be designed and implemented.
EPCC, SC and PQA
6 Social Issues To minimize inconvenience for the public
Mitigation measures will include provisions in the design such as public awareness through different means, proper traffic diversion plans, appropriate sign boards, and timely completion of the project.
EPCC, SC and PQA
7 Flora To avoid the cutting of trees as far as possible.
Avoid the unnecessary cutting of trees Plan for compensatory planting for ten trees against each
fallen tree of similar floral function; Transplantation plan of maximum trees/plants to be
affected; and Disallow introduction of exotic species with known
environmental setbacks (Eucalyptus, etc.).
EPCC, SC and PQA
8 Public Utilities To avoid disturbance to the public utilities.
Incorporate technical design features to minimize impact on public utilities; and
All public utilities likely to be affected by the proposed project need to be relocated/rehabilitated well ahead of the commencement of construction work.
EPCC, SC and PQA
Section–7 Environmental Monitoring and Management Plan EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-6 July, 2016
Sr. No. Parameters Target Mitigation Responsibility
9 Seismic Hazard To minimize the structural damage
The proposed project will be designed and constructed to withstand low to moderate earthquakes. For seismic hazard analysis, updated structural and seismic evaluations will be consulted.
EPCC, SC and PQA
Construction Phase
1 Soil To minimize soil erosion and contamination.
All spoils will be disposed off as desired and the site will be restored back to its original conditions;
Non-bituminous wastes from construction activities will be dumped in approved sites, in line with the legal prescriptions for dump sites, and covered
Excavations would be kept confined to the specified foundation spots as per the approved engineering drawings. Unnecessary excavations should be avoided;
Site camps for the resident labour should not be setup on the land earmarked for developing green belts and lawns;
Oils, lubricants, chemicals, and other listed hazardous materials should be stored safely at their designated spots, enclosures or store rooms, which should be safe from rainfall and away from any potential source of fire;
Septic tanks of adequate capacities should be constructed for receiving and treating wastewater from all temporary worksite toilets and at the temporary container offices, if any. The toilet wastewater should not be discharged untreated onto the adjacent lands;
All machineries and materials should be stored at the designated areas and compounds;
All the unspent and left over materials be completely removed offsite upon completion of construction and the site be restored to original or near to original condition; and
Washout from washing of equipment and gadgets should be drained into either a septic tank or a sand-gravel bed for removal of the grit and contaminants.
EPCC , SC and EC
Section–7 Environmental Monitoring and Management Plan EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-7 July, 2016
Sr. No. Parameters Target Mitigation Responsibility
2 Camp Site To minimize loss of assets and vegetation/forests due to labor movement.
All efforts during the design stage should be made to minimize the removal of existing macro-plants (if any) at camp sites;
The contractor(s) will provide plan for removal & rehabilitation of site upon completion;
Photographical and botanical inventory of vegetation (if any) before clearing the site; and
Compensatory plantation (if any) to be scheduled when construction works near end.
CC, SC, PQA and EC
3 Health and safety of workers and associated communities
To minimize health risks Obligatory insurance against accidents for labourers/workers;
Providing basic medical training to specified work staff and basic medical service and supplies to workers;
Layout plan for camp site, indicating safety measures taken by the contractor, e.g. firefighting equipment, safe storage of hazardous material, first aid, security, fencing, and contingency measures in case of accidents;
Work safety measures and good workmanship practices are to be followed by the contractor to ensure no health risks for labourers;
Protection devices (ear muffs) should be provided to the workers doing job in the vicinity of high noise generating machines;
Provision of adequate sanitation, washing, cooking and dormitory facilities including light up to satisfaction;
Proper maintenance of facilities for workers will be monitored;
Provision of protective clothing for labourers handling hazardous materials, e.g. helmet, adequate footwear for bituminous pavement works, protective goggles, gloves etc;
Ensure strict use of wearing these protective clothing during work activities;
Elaboration of a contingency planning in case of major accidents;
Instruct foremen to strictly enforce the keeping out of non-working persons, particularly children, off work sites; and
EPCC, SC, EC
Section–7 Environmental Monitoring and Management Plan EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-8 July, 2016
Sr. No. Parameters Target Mitigation Responsibility
Adequate signage, lightning devices, barriers, yellow tape and persons with flags during construction to manage traffic at construction sites, haulage and access roads.
There should be proper control on construction activities and oil spillage leakage of vehicles.
The labour works with different transmittable diseases should be restricted within the construction site.
Efforts will be made to create awareness about road safety among the drivers operating construction vehicles;
Timely public notification of planned construction works; Close consultation with local communities to identify
optimal solutions for diversions to maintain community integrity & social links;
Seeking cooperation with local educational facilities for road safety campaigns;
Provision of proper safety and diversion signage, particularly at sensitive/accident-prone spots;
Setting up speed limits in close consultation with the local stakeholders;
If identified, consider additional guard rails at accident-prone stretches and sensitive locations (schools & hospitals);
Reducing the impacts of vector borne diseases on long-term health effect of workers should be accomplished through implementation of diverse interventions aimed at eliminating the factors that lead to disease, which includes: Prevention of larval and adult propagation of vectors through sanitary improvements and elimination of breeding habitat close to human settlements and by eliminating any unusable impounding of water;
During construction work vehicular passages should be provided for crossing;
Fencing around the camps should be strong enough so that it cannot be broken easily by local people for making passages; and
Use of water should not disturb public water availability and source of water should be selected carefully.
Section–7 Environmental Monitoring and Management Plan EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-9 July, 2016
Sr. No. Parameters Target Mitigation Responsibility
4 Emergency Response
To be prepared for emergency
An Emergency Response Plan for earthquakes and manmade disasters will be developed by the PQA. Emergency Response Plan will be implemented in close consultation with the, firefighting department, bomb disposal squad and paramedics. In addition, training of the staff / employees regarding the emergency procedures / plans will be regularly conducted.
PQA & EPCC
5 Air Quality To minimize air pollution All vehicles, machinery, equipment and generators used during construction activities should be kept in good working condition and be properly tuned and maintained in order to minimize the exhaust emissions;
Blowing of dust from potential sources at the worksite should be avoided by shielding them from the exterior, for example using polythene curtains or raising a fence of corrugated sheets around areas of active constructions;
Blowing of dust and particulate matter from stockpiled loose materials (e.g. sand, soil) should be avoided either by sheeting them with tarpaulin or plastic sheets or by sprinkling them with light shower of water;
Open burning of solid waste from the Contractor’s camps should be strictly banned;
Preventive measures against dust should be adopted for on-site mixing and unloading operations. Regular water sprinkling of the site should be carried out to suppress excessive dust emission(s);
Only good quality oils, petroleum products, additives and spares should be used in the machinery, generators, and the construction vehicles. Usage of used oil should be strictly prohibited;
Emissions from power generators and construction machinery are important point sources at the construction sites. Proper maintenance and repair is needed to minimize the hazardous emissions.
EPCC, SC and EC
6 Noise To minimize noise pollution Selection of up-to-date and well maintained plant or equipment with reduced noise levels ensured by suitable in-built damping techniques or appropriate muffling
EPCC, SC and EC
Section–7 Environmental Monitoring and Management Plan EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-10 July, 2016
Sr. No. Parameters Target Mitigation Responsibility
devices; Confining excessively noisy work to normal working hours
in the day, as far as possible; Providing the construction workers with suitable hearing
protection like ear cap, or earmuffs and training them in their use;
Preferably, restricting construction vehicles movement during night time;
Heavy machinery like percussion hammers and pneumatic drills should not be used during the night without prior approval of the client;
Vehicles and equipment used should be fitted, as applicable, with silencers and properly maintained;
Use of low noise machinery, or machinery with noise shielding and absorption;
Contractors should comply with submitted work schedule, keeping noisy operations away from sensitive points; implement regular maintenance and repairs; and employ strict implementation of operation procedures.
7 Waste To minimize the Wastes Wastewater effluent from contractor’s workshop and equipment washing yards would be passed through oil and grease separator to remove oil/ grease contaminants before discharging it into natural streams;
An efficient and responsive solid waste management system should be devised for the entire duration of the construction phase. Such a system should provide for separate collection of different categories of constructional wastes. The wastes which will be reusable/recyclable (iron bars, aluminum) should be sold to waste vendors and those which cannot be sold out (Block pieces) may be used as a filling material for leveling the depressions, subject to technical feasibility;
Solid waste should not be disposed off into natural drain; Training of working force in the storage and handling of
materials and chemicals that can potentially cause soil contamination;
Solid waste generated during construction and camp sites
EPCC and EC
Section–7 Environmental Monitoring and Management Plan EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-11 July, 2016
Sr. No. Parameters Target Mitigation Responsibility
will be safely disposed in demarcated waste disposal sites and the contractor will provide a proper waste management plan;
Proper labeling of containers, including the identification and quantity of the contents, hazard contact information etc.;
Training of employees involved in the transportation of hazardous material regarding emergency procedures;
Providing the necessary means for emergency response on call 24 hours/day;
The sewage system for camps will be properly designed (pit latrines or, as required, septic tanks) to receive all sanitary wastewaters;
Lined wash areas will be constructed within the camp site or at site, for the receipt of wash waters from construction machinery;
Insecticides that are less toxic to human health should be used;
Construction workers and supervisory staff should be encouraged and educated to practice waste minimization, reuse and recycling to reduce quantity of the waste for disposal; and
Prohibit open burning of solid waste. 8 Surface and Ground
water To avoid contamination of water bodies and ground water
Protection of groundwater reserves (if any) from any source of contamination such as the construction and oily waste that will degrade its quality;
The solid waste will be disposed off in designated landfill sites;
Water required for construction is obtained in such a way that the water availability and supply to nearby communities remain unaffected; and
Prohibit washing of machinery and vehicles in open areas, provide sealed washing basins and collect wastewater in sedimentation/retention pond.
EPCC, SC and EC
9 Flora To minimize the impact on flora
There are about 12 trees in the median of existing road; efforts shall be made to save the trees as much as
EPCC, SC and PQA
Section–7 Environmental Monitoring and Management Plan EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-12 July, 2016
Sr. No. Parameters Target Mitigation Responsibility
possible. Compensatory plantation of trees at the rate of 1:10 is recommended. The plantation will start as soon as the construction of proposed project is nearing completion;
Camp sites will be established on waste/barren land rather than social and commercial land. However, if such type of land is not available, it will be ensured that minimum clearing of the vegetation is carried out and minimum damage is caused to flora;
Construction vehicles, machinery and equipment will remain confined within their designated areas of movement;
The Contractor’s staff and labour will be strictly directed not to damage any vegetation;
Contractor will provide gas cylinders at the camps for cooking purposes and cutting of trees/bushes for fuel will not be allowed; and
A tree plantation program will be formulated by the PQA along the Road and stockyard at available spaces.
10 Disposal of Mucking Material
To minimize the scars on the land in the project area
Mitigation measure will include proper landscaping, which should be given due consideration along with re-establishment of the local/indigenous vegetation. The excavated materials that are unsuitable for use will need to be stored, transported and disposed of appropriately at designated sites.
CC, SC and EC
11 Public Utilities and Infrastructure
To minimize the disturbance to public utilities and infrastructure
Mitigation measures will include rehabilitation of existing utilities before construction to avoid any inconvenience to the residents of the project area or provide them with alternate arrangement during the construction period.
EPCC, SC and EC
12 Traffic Management To minimize traffic problems in the project area
Proper traffic management plan will be needed to avoid traffic jams/public inconvenience;
Coordinated planning of traffic diversions by the traffic control agency of PQA in accordance with the construction program with advance warnings to the affected road users;
Construction vehicles, machinery and equipment will
Traffic Police, EPCC and EC
Section–7 Environmental Monitoring and Management Plan EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-13 July, 2016
Sr. No. Parameters Target Mitigation Responsibility
move or be stationed in the designated ROW to avoid un-necessary compaction of soil.
Availability of continuous services of the traffic control personnel in the diversion and control of traffic; and
The executing agency is required to maintain liaison between the traffic control agency, local travelers and the contractor to facilitate traffic movement during construction stage.
13 Lifestyle and Culture To minimize cultural conflicts Timely public notification and announcement of mobilizing equipment;
Local labour should be employed for construction works Water supply and sanitation facilities, Contractor’s
workforces should exacerbate the existing shortages and environmental hazards; contractor should primarily seek their own sources of water in due distance.
EPCC, SC and EC
14 Heavy Vehicles on the Existing Road Network & Sensitive Receptors
To minimize negative impacts on existing road and surroundings.
Any vehicle with an open load carrying area used for transport of potentially dust producing materials shall have properly fitted side and tailboards. Materials having potential to produce dust shall not be loaded to a level higher than the side and tail boards and shall be covered with clean tarpaulin in good condition. The tarpaulin shall be properly secured and extended to at least 300 mm over the edges of the sideboard and tailboard;
The Contractor shall not use any vehicles either on or off road with grossly excessive noise pollution. Noise mufflers shall be installed and maintained in good condition on all motorized equipment under the control of the Contractor;
Timely maintenance of affected roads to avoid any inconvenience to the road commuters.
EPCC, SC, Traffic Control agency of PQA and EC
Operational Phase
1 Air Quality To Minimize the dust emissions from coal handling activities
All machinery, equipment, vehicles, and generators used during operation activities should be kept in good working condition, be properly tuned and maintained in order to control the emissions;
Sindh EPA and PQA
Section–7 Environmental Monitoring and Management Plan EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-14 July, 2016
Sr. No. Parameters Target Mitigation Responsibility
All the coal dust control measures provided by the planner and designer of the project including inbuilt dust control units of equipment, covers over potential sources of dust, wind breaker walls, dust suppression walls and water sprinkling arrangements should be well maintained and regularly operated at site.
Preventive measures against dust should be adopted for on-site loading and unloading operations. Regular water sprinkling of the coal stock piles should be carried out to suppress excessive dust emission(s);
Emissions from power generators and other machines are important point sources at the project. Proper operation and maintenance schedules should be prepared by the operator of the facility is required to minimize the hazardous emissions.
2 Noise and vibration To minimize noise pollution Keep the plant and equipment well maintained to control the noise and vibration levels within the specified limits.
Use of low noise machinery, or machinery with noise shielding and absorption;
Foundation of equipment should be well maintained to avoid vibration and noise from the equipment;
Vehicles and equipment used should be fitted, as applicable, with silencers and properly maintained; and
Providing the operating workers of the facility with suitable hearing protection like ear cap, or earmuffs and training them in their use;
Sindh EPA and PQA
3 Fire To control fires Firefighting arrangements should be properly maintained as required by the international operational codes and standards;
Operating staff must be trained for firefighting; Fire drills with the recommended frequency should be
arranged at site; Proper cleaning mechanism and solid waste management
system including hazardous waste should be followed to avoid fire hazard.
Sindh EPA and PQA
Section–7 Environmental Monitoring and Management Plan EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-15 July, 2016
Sr. No. Parameters Target Mitigation Responsibility
4 Flora Raising of compensatory plantation
Plants will be raised in and around the project area at available spaces. The presence of adequate flora, along the route of coal conveyor and stockyard will control the dust emission and absorb flue gases, emitted from coal handling activities, which shall in turn improve air quality.
Organic farming will be encouraged to minimize the use of chemical fertilizers and pesticides.
PQA
5 Air Quality To minimize air pollution Setting up of a system to monitor air quality along project area in accordance with the applicable standards/limits;
Tree plantations as applicable and feasible under harsh climatic conditions; plants should be selected in accordance to their ability to absorb emissions;
Regular road maintenance to ensure good surface condition;
Sindh EPA and PQA
6 Wastewater To control downstream water pollution
Proper wastewater management practices should be employed at project site;
Wastewater treatment and disposal system should be maintained and monitored for the proper treatment and disposal of wastewater; and
Contaminated water from the sprinkling and firefighting activities laden with coal particles should be collected in the sedimentation basin and reused for the same purposes (if possible).
PQA
7 Storm water To control downstream water pollution
Storm water management system (collection treatment and disposal) for stockyard should be operated to avoid contamination of sea water.
Sindh EPA and PQA
KEY DESCRIPTION EPCC Engineering Procurement Construction Contractor
EC Environmental Committee
SC Supervision Consultant
SEPA Sindh Environment Protection Agency
PQA Port Qasim Authority
Section–7 Environmental Monitoring and Management Plan EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-16 July, 2016
7.4 ENVIRONMENTAL MONITORING
Environmental Monitoring is undertaken during both the construction and operational
phases to ensure the effectiveness of the proposed mitigation measures. Certain
environmental parameters are selected and quantitative analysis is carried out. The
results of analysis are compared with the guidelines; standards and pre-project
conditions to investigate whether the EMMP and its implementation are effective for
the mitigation of impacts or not. Parameters to be analyzed during construction and
operation of the project and responsibilities for monitoring and reporting have been
discussed below.
A cost estimate for this measurement of parameters is given in Table 7.2.
7.4.1 Construction Phase
a) Air Quality Air quality monitoring will be carried out once during the construction phase at
the project site. All SEQS parameters will be monitored.
b) Water Quality Water quality monitoring will be done once during the construction phase at
the representative location. All SEQS parameters will be monitored.
c) Wastewater Quality Wastewater quality monitoring will be done once during the construction
phase at the representative locations. All SEQS parameters will be monitored.
d) Noise Levels
The noise level monitoring will be carried out once during the whole
construction period as per monitoring plan at representative location in the
project area.
7.4.2 Operation Phase
a) Air Quality Air quality monitoring will be done monthly during the operational phase at the
representative locations. The following parameters will be monitored:
Section–7 Environmental Monitoring and Management Plan EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-17 July, 2016
CO
NOX
SO2
PM10
b) Noise Levels
The noise level monitoring will be carried out monthly at representative
locations in the project area.
7.4.3 Responsibilities for Monitoring and Reporting The EC will be responsible for environmental monitoring and reporting throughout the
construction and operation phases. A monitoring report will be prepared on monthly
basis and one comprehensive report will be prepared after every three months.
Contents of the report will include results of environmental monitoring in comparison
to the SEQS/NEQS for the various parameters, location and sampling time along
with recommendations. Reports will be submitted during the construction phase to
each of the following authorities and institutions:
(i) PQA and
(ii) Sindh EPA whereas, during the operational phase, one report will be
submitted to EPA-Sindh
Section–7 Environmental Monitoring and Management Plan EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-18 July, 2016
Table 7.2: Budget Estimate for Environmental Monitoring During the Construction and Operation Phases
Components Parameters No. of Samples
(No. of Samples x No. of locations x Frequency)
Frequency Responsibility Duration Cost (Rs.)
Construction Phase (9 Months)
Air Quality CO, NOx, SOx, SPM, PM 2.5, PM10 1x1x9 = 9 Monthly EPCC/ EC 24 hours 315,000/-
Water Quality Total Coliforms, Fecal E. Coli, Total Colonial Count, Turbidity, pH, TDS, Total Hardness, Nitrate, Chloride, Sodium
1x1x9 = 9 Monthly EPCC/ EC - 225,000/-
Wastewater Quality pH, DO, TSS, TDS, Alkalinity, BOD5, COD, Turbidity 1x1x9 = 9 Monthly EPCC/EC - 225,000/-
Noise Level - 1x1x9 = 9 Monthly EPCC/EC 24 hours 22,500/-
TOTAL 787,500/-
Operation Phase (1 year)
Air Quality CO, NOx, SOx, SPM, PM 2.5, PM10 1x1x12 = 12 Monthly EC/Sindh -EPA 24 hours 420,000/-
Noise Level - 1x1x12 = 12 Monthly EC/Sindh -EPA 24 hours 30,000/-
TOTAL 450,000/-
GRAND TOTAL 1,237,500/-
KEY EC – Environmental Committee
EPCC- Engineering Procurement Construction Contractor
SEPA – Sindh Environmental Protection Agency
Section–7 Anticipated Environmental Impacts and Mitigation Measures EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-19 July, 2016
7.5 PLANTATION To minimize the negative impacts arising due to the operations of Coal Conveying
System and to enhance the landscape of the project area, plantation at available
spaces will be carried out. Total cost for the plantation of recommended trees is
about Rs. 349,310/-.
Plantation Plan A Plantation Plan is prepared for Coal Conveying System at Port Qasim, Karachi.
The plantation in the project area was considered as an essential component of
Environmental Impact Assessment (EIA) of the project.
The plants/trees exist in the project area are being looked after by Port Qasim
Authority.
If any plant/tree cut down/uprooted, saplings have to be planted against any uprooted
plant/tree as replacement. The execution of the project will involve the
cutting/uprooting of only 12 trees owned by the PQA, inside median of proposed Coal
Conveyor route. The contractor will plant 240 plants at available spaces of specified
species as directed by the Program Monitoring Unit of PQA.
The following plan is proposed for Port Qasim Authority:
i. The plants/tree inventory prepared by the consultants may be shared with the
PQA.
ii. The cut/uprooted plants/trees will remain the property of PQA.
iii. The replenish cost will be paid to Contractor.
iv. The Contractor will plant 20 sapling for every cut/uprooted plants/tree and
take care of the plantation including the replacement of dead plants up to the
defect liability period.
7.6 ENVIRONMENTAL TECHNICAL ASSISTANCE AND TRAINING PLAN
In order to raise the level of professional and managerial staff, there is a need to
upgrade their knowledge in the related areas. The EC should play a key role in this
respect and arrange the trainings.
Section–7 Anticipated Environmental Impacts and Mitigation Measures EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-20 July, 2016
An environmental and social training and Technical Assistance (TA) program is to be
carried out before the implementation of the project. Contractor’s environmental
awareness and appropriate knowledge of environmental protection is critical to the
successful implementation of the EMMP because without appropriate environmental
awareness, knowledge and skills required for the implementation of the mitigation
measures, it would be difficult for the Contractor’s workforce to implement effective
environmental protection measures. A suitable training program is proposed to train
the Contractor(s) staff who will be involved in the construction phase and the
professional staff from the client involved at the operational stage of the project.
The PQA will engage a consultant to manage the environmental training program.
The objective of the TA will be, to help in establishment of appropriate systems, and
to train senior PQA staff and EC responsible for managing environment, operations,
and planning, who can then impart training at a broader level within and outside the
PQA (i.e. the training of trainers). The TA consultant will organize training courses for
PQA and contractor staff to train them in specialized areas such as air and noise
pollution monitoring; develop environment operation manuals in consultation with the
Sindh EPA. The details of this training program are presented in Table 7.3
Table 7.3: Personnel Training Program/ TA Services
Provided by Contents Trainees/Events Duration TA consultants/ organizations specializing in environmental management and monitoring
Short seminars and courses on: Environmental laws and regulations, daily monitoring and supervision
Two seminars for PQA and Contractor project staff
2 days
TA consultants/ organizations specializing in social management and monitoring
Short seminars and courses on: Social awareness
Two seminars for project staff dealing in Social matters
2 days
TA consultants/ organizations specializing in Occupational, health and safety issues
Short lectures relating to Occupational Safety and Health
Two seminars for contractor’s staff
2 days
7.7 ENVIRONMENTAL MONITORING, MITIGATION AND TRAINING COST
The cost required to effectively implement the mitigation measures is important for
the sustainability of the project both in the construction and operation phases of the
Project.
Section–7 Anticipated Environmental Impacts and Mitigation Measures EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-21 July, 2016
These costs are summarized in Table 7.4 and the break-up for Health Safety &
Environment cost is given in Table 7.5.
Table 7.4: Environmental Mitigation and Monitoring Cost
Sr. No. Activity Basis Cost (Rs.)
1 Medical screening for workers Rs. 1200 for 150 employees 180,000
2 Drinking water analysis
Rs. 25,000 for microbiological and chemical analysis for one sample collected twice for 9 months from one (01) camp site
50,000
3 Material Storage, handling and use Five (05) No. of tarpaulins of Rs. 20,000 each 100,000
4 Handling/ transportation of hazardous material
Rs. 12,000/month for a period of 9 months will be required for transportation of material
108,000
5 Handling of solid waste
Rs.10,000 per month (two trips per month) for a period of 9 months, which includes the cost of collection, transportation and disposal to the designated site
90,000
6 Health & Safety of Workers
For 100 employees for the provision of dust masks, safety shoes, gloves, first aid box, ear plugs, safety helmets and safety jackets (Hi Vis) And Provision of dust bins, warning tap, safety cones, safety sign boards and water sprinkling
2,256,000
7 Environmental Monitoring Cost Air, water, noise 1,237,500
8 Cost for hiring of staff (Environment Health & Safety Specialist)
Rs. 150,000 / month for 9 months 1,350,000
9 Cost of environmental training For the whole construction period 600,000
10 Tree Plantation and maintenance for five (05) years 349,310
Grand Total 6,320,810
Section–7 Anticipated Environmental Impacts and Mitigation Measures EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-22 July, 2016
Table 7.5: Break-up for Health Safety & Environment cost (Serial No. 6 of Table 7.4)
Items Quantity Cost / Item (Rs.) Total Cost (Rs.)
(A) Personal Protective Equipments PPEs
Dust masks 3600 20 72,000
Safety Shoes 200 1200 240,000
Gloves 1800 200 360,000
First Aid Box 2 2000 4,000
Ear Plugs 900 30 27,000
Safety Helmets 100 800 80,000 Safety Jackets (Hi Vis) 200 400
80,000
Sub-Total (A) 863,000
(B) Others Provision of Dust Bins 4 1000
4,000
Warning Tape 50 500 25,000
Safety Cones 40 1000 40,000
Safety Sign Boards 20 1200 24,000
Water Sprinkling 2 times/day 15000
900,000
Rain Coat 200 2000 400,000
Gum Boots 200 1000 200,000
Sub-Total (B) 1,393,000
Total (A) + (B) 2,256,000
Time required for Construction = 9 months No. of labour required during construction = 100
(A) Personal Protective Equipments PPEs
Dust mask 1 dust mask to be used in a week by each labourer Safety Shoes 1 safety shoe for six months for each labourer Gloves 2 pair of gloves for each labourer for a month
First Aid Box 1 first aid box for every 50 labourers Ear Plug 1 set of ear plug to be used for 1 month for each labourer
Safety Helmet 1 safety helmet for each labourer for 9 months
Section–7 Anticipated Environmental Impacts and Mitigation Measures EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 7-23 July, 2016
Safety Jackets (Hi Vis) 2 safety Jackets (Hi Vis) for each labourer for 9 months
(B) Others Water Sprinkling only considered for road manufacturing for the period of 1 month (30
days) Rain Coat 2 rain coat for each labourer for 9 months
Gum Boots 2 gum boot for each labourer for 9 months
The Environmental Mitigation and Monitoring cost will be Rs. 6,320,810 or Rs. 6.320 Million.
Section – 8 Conclusion and Recommendation EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 8-1 July 2016
SECTION - 8 CONCLUSION AND RECOMMENDATIONS
8.0 GENERAL This section presents conclusion of the EIA Study of Coal Conveying System at Port
Qasim, Karachi. The overall objective of this EIA is to carry out a detailed
environmental assessment of the proposed project to assess impacts caused by the
different activities and to address measures to mitigate adverse environmental
impacts arising from the execution of the project.
The conclusions mentioned below are based on the findings of detailed
environmental assessment, which has been carried out as per requirement of Sindh-
EPA.
8.1 MAIN ISSUES AND CONCERNS
During the field surveys, significant efforts were made to identify the main
environmental, ecological and social issues related to the implementation of the
proposed project. Various Government Departments and Agencies were also
contacted for obtaining salient information along with area residents / stakeholders.
Following is the list of main issues and concerns identified:
• Disturbance to the public movement during construction;
• Air and noise pollution due to the different construction activities and operation of
construction machinery during construction phase of the project;
• Coal dust generation might occur during the operation phase of the project;
• The disposal of water containing coal dust is another major environmental impact
at the stockyard during the operation phase of the project;
• Coal fire hazard might be an adverse impact for the adjoining industries along
either side of the conveyor belt;
• Solid waste generation during construction;
• Accidental leaks/spills of hazardous chemicals from construction activities and
machinery;
• Health and safety issues of the workers;
• Contamination of water body by construction activities; and
Section – 8 Conclusion and Recommendation EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 8-2 July 2016
• Disturbance in traffic movement during excavation and lying of utility pipe in
relocation of public utilities.
All the adverse impacts have properly been mitigated and a comprehensive EMP
has been formulated. The implementation of EMP will help to reduce the adverse
impacts of execution of coal conveyor system.
8.2 MITIGATION MEASURES
It is envisaged that the commitment of Port Qasim Authority (PQA) to maintain the
quality of environment within and adjacent to the project area through
implementation of the EMP would mitigate any adverse impacts. For effective
environmental management, Port Qasim Authority (PQA) should assign the
necessary responsibilities to an Environmental Committee which should be
responsible for implementation of the Environmental Management and Monitoring of
the proposed project.
The implementation of Coal Conveying System (CCS) will provide;
• CCS includes features like inbuilt dust control in transfer stations, covered coal
conveyor, mechanized loading unloading features, dust suppression and
complete firefighting arrangements at coal stockyard, and rapid load-out station
for loading the train, all day service spans, and more frequent service than truck
transport;
• The use of exclusive trains, flexibility and lower-cost of transportation by train
allows it to provide cost effective, environment friendly, safe, swift, and greater
reliability of fuel for power plants;
• Reliable supply of fuel ensures the reliable power generation and supply;
• Improved tax / fare collection;
• The total capacity of a single train is 2400 tonnes;
• The greater frequency and larger quantities of coal transport through train will
reduce traffic on highways;
• Contributes to reductions in traffic crashes;
• Reduced traffic load noise & air pollution; and
• Reduced maintenance of roads.
The EIA study concluded that there could be some areas of concern, provided the
mitigation measures identified are not addressed to the satisfaction of all
Section – 8 Conclusion and Recommendation EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 8-3 July 2016
stakeholders. Probably the main area of concern which would require special
attention are; Coal dust generation, coal fire hazard, health and safety of workers,
etc.
Overall, the impacts related to construction phase of the project could be minimized
by the implementation of the proper mitigation measures.
8.3 RECOMMENDATIONS
Some recommendations those need to be followed for the project to make the
project sustainable are:
• The Project impacts and their mitigation will be monitored as per the Monitoring
Plan;
• All mitigation, compensation and enhancement measures proposed in this EIA
report are implemented in full, as described in the document;
• To ensure that the environmental impacts of the project are successfully
mitigated;
• The Environmental Management and Monitoring Plan must be implemented; and
• The Implementing Agency (PQA) shall ensure that the EMP prepared by the
contractor includes construction methodologies and submit this to PQA for review
and approval.
At the implementation stage, PQA assisted by Supervision Consultants (SC) will
make arrangements to monitor the implementation of mitigation measures and
conduct environmental effects monitoring activities specified in the EMP.
With these measures in place, environmental impacts of the Project should be
manageable and will not result in any residual impacts on the project.
ANNEXURE
EIA of Coal Conveying System at Port Qasim, Karachi
NESPAK July, 2016
Annexure-I:
SIND ENVIRONMENTAL QUALITY STANDARDS, 2016
ANNEXURE
EIA of Coal Conveying System at Port Qasim, Karachi
NESPAK July, 2016
Annexure-II:
ENVIRONMENTAL MONITORING REPORT
S
PAK
ENVIRON
COAL C
Sector 28Phon
KISTAN
MENTAL MO
E
CONVEYIN
, Gulzar-ne: (92-2
N SPACE
ONITORING O
ENVIRO
NG SYSTE
e-Hijri O21) 34650
E & UPPE
OF COAL CONPO
ONMENT
EM FROM
PORT QA
ff .Unive0765-743
ER ATM(SUP
NVEYING SYORT QASIM
TAL MOFOR
PIBT TO
ASIM, KAR
rsity Roa3469494
MOSPHEPARCO)
YSTEM FROM
ONITOR
EXISTINGRACHI
ad, P.O.Bo41, Fax:
RE RES)
M PIBT TO RA
RING
G RAIWAY
ox 8402, (92-21)
SEARCH
AILWAY NET
Y TRACK A
, Karachi- 3464492
H COMM
TWOK
AT
-75270 28
MISSION
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
ENVIROMENTAL MONITORING AND MODELING DIVISION Page ii
DISCLAIMER
This report containing 38 pages is produced in compliance with the request of
M/s NESPAK, Karachi. for ascertaining ambient air quality, Noise and Vibration
Monitoring at three (03) sites for 24 hour for coal conveying system from PIBT
to railway Network at Port Qasim and drinking water quality at three (03)
locations. The information contained in this report has been verified by
SUPARCO experts and any changes made hereafter would not be the
SUPARCO’s responsibility.
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
ENVIROMENTAL MONITORING AND MODELING DIVISION Page iii
PREPARED BY: Name: M. Khalid
Designation: Research Associate, SUPARCO
Signature---------
CHECKED BY: Name: Dr. M. Mansha
Designation: General Manager, SUPARCO
Signature---------
SUBMITTED TO: M/s NESPAK, KARACHI
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
ENVIROMENTAL MONITORING AND MODELING DIVISION Page iv
LIST OF ABBREVIATIONS
SUPARCO Pakistan Space & Upper Atmosphere Research Commission
NOx Oxides of Nitrogen
CO Carbon Monoxide
PM10 Particulate Matter Less than 10 micron
PM2.5, Particulate Monitor less than 2.5 micron
µg/m3 Microgram per cubic meter
SEQS Sindh Environmental Quality Standard
US EPA Environmental Protection Agency of USA
NEQS National Ambient Air Quality Standards
ND Not Detected
NESPAK National Engineering Services Pakistan
PIBT Pakistan International Bulk Terminal
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
ENVIROMENTAL MONITORING AND MODELING DIVISION Page v
TABLE OF CONTENTS 1. INTRODUCTION ..................................................................................... 1
1.1 Objectives ......................................................................................... 2
2. AMBIENT AIR QUALITY MONITORING ................................................ 3
2.1 Methodology .......................................................................................... 3
2.2 Data Acquisition Criteria ................................................................. 3
2.3 Ambient Air Quality Monitoring Methods and Ambient Air Quality Standards ..................................................................................... 4
2.4 Work Plan ......................................................................................... 5
2.5 Air Quality Data Acquisition Plan ................................................... 5
3. GENERAL DISCUSSION AND RESULTS ............................................. 6
3.1 Oxides of Nitrogen (NOx) ................................................................ 6
3.1.1 Monitoring Results of NOx .............................................................. 6
3.2 Sulfur Dioxide (SO2) ......................................................................... 7
3.2.1 Monitoring Results of SO2 ............................................................... 7
3.3 Carbon Monoxide (CO) .................................................................... 8
3.3.1 Monitoring Results of CO ................................................................ 8
3.4 Ozone (O3) ........................................................................................ 9
3.4.1 Monitoring Results of Ozone .......................................................... 9
3.5 Particulate Matter (PM10,PM2.5 and SPM) ................................... 10
3.5.1 Monitoring Results of PM 2.5 ......................................................... 11
3.5.2 Monitoring Results of PM 10 .......................................................... 11
3.5.3 Monitoring Results of SPM ........................................................... 12
3.6 Noise Level Measurement ............................................................. 13
3.6.1 Monitoring Results of Noise Level ............................................... 13
3.7 Vibration ......................................................................................... 14
3.7.1 Monitoring Results of Vibration ................................................... 14
3.8 Lead in Ambient Air ....................................................................... 14
3.8.1 Testing Results of Lead ................................................................ 14
3.9 Meteorological Data ....................................................................... 15
3.9.1 Monitoring Results of Meteorological Data .............................. 15
4. WATER TESTING ................................................................................. 18
4.1 Methodology ................................................................................... 18
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
ENVIROMENTAL MONITORING AND MODELING DIVISION Page vi
4.2 Data Acquisition Criteria ............................................................... 18
a. Drinking Water Quality Testing Methods and Standards ........... 19
4.3 Work Plan ....................................................................................... 20
4.4 Water Quality Sampling Plan ........................................................ 21
4.5 Water Quality Results .................................................................... 24
4.6 Conclusion ..................................................................................... 25
Annexure-I 26
(Detailed Monitoring Data) ........................................................................ 26
Annexure-II ................................................................................................ 33
(MONITORING SURVEY PICTURES) ........................................................ 33
i: End Point Pictures (NWIZ/ Pumping Station PQA) ............................ 34
ii: Pharm-Evo Pictures ............................................................................. 35
iii: Start Point (PIBT) Pictures ................................................................. 36
iv: Water Sampling Pictures .................................................................... 37
v: Noise and Vibration Monitoring .......................................................... 38
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
ENVIROMENTAL MONITORING AND MODELING DIVISION Page vii
List of Figure
Figure # Title Page #
Figure A Satellite View of Locations of Ambient Air Monitoring Sites 1
Figure 2 (a) Minimum, Maximum and Average (24hrs) Concentration of NO 6
Figure 2 (b) Minimum, Maximum and Average (24hrs) Concentration of NO2 7
Figure 3) Minimum, Maximum and Average (24hrs) Concentration of SOX 8
Figure 4 Minimum, Maximum and Average (24hrs) Concentration of CO 9
Figure 5 Minimum, Maximum and Average (24hrs) Concentration of O3 10
Figure 6 Minimum, Maximum and Average (24hrs) Concentration of PM 2.5 11
Figure 7 Average (24hrs) Concentration of PM10 12
Figure 8 Average (24hrs) Concentration of SPM 12
Figure 9 Minimum, Maximum and Average (24hrs) Noise level at different sites 13
Figure 10 Average (24hrs) values of Temperature at different sites 15
Figure 11 Average (24hrs) values of Humidity at different sites 16
Figure 12 Average (24hrs) values of Wind Speed at different sites 16
Figure 13 Wind rose Plot Showing Wind Speed and Wind Direction (Blowing from) of End Point of the Project
17
Figure 14 Windrose Plot Showing Wind Speed and Wind Direction (Blowing from) of Pharm Evo 17
Figure 15 Windrose Plot Showing Wind Speed and Wind Direction (Blowing from) of Start Point 18
Figure 16 Satellite View of Locations of Water Sampling Sites 22
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
ENVIROMENTAL MONITORING AND MODELING DIVISION Page viii
List of Tables
Table # Title Page #
Table 1 Ambient Air Quality and Noise Level Monitoring Point 2
Table 2 Concentration limits of Equipment 3
Table 3 Ambient Air Quality Monitoring Methods 4
Table 4 Ambient Air Quality Standards of Pak. EPA, USEPA, WHO and World Bank 4
Table 5 Testing Methods and National Standards for Drinking Water Quality 19
Table 6 Drinking Water Quality Results 24
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
ENVIROMENTAL MONITORING AND MODELING DIVISION Page 1
1. INTRODUCTION
NESPAK is in process of conducting Environmental Impact Assessment (EIA) of
Coal Conveying System from PIBT to Railway Network at Port Qasim, Karachi. We,
therefore intend to conduct sampling and testing of Air, Water, Noise and Monitoring of
Vibration at site.
For the monitoring of Ambient Air, Noise and Vibration, three points have been
selected along the route of conveyor belt to coal stockyard; sampling of water has been
carried out from project area. In addition, the Air Dispersion Modeling is required to
simulate the physical process of dust dispersion from the source and identify potential
hazard areas surrounding the source with respect to health and safety.
Figure A: Satellite View of Locations of Ambient Air, Noise, and Vibration Monitoring Points
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
ENVIROMENTAL MONITORING AND MODELING DIVISION Page 2
Table 1: Ambient Air Quality and Noise Level Monitoring Point
Equipment Min. Concentration Limits
Ambient Air Quality Monitoring at PIBT
(Start Point)
N 24048’46.0”
E 67017’18.5”
Ambient Air Quality Monitoring at
Pharm Evo
N 24049’40.4”
E 067017’37.4”
Ambient Air Quality Monitoring at
Water Pumping Station (End Point)
N 24049’41.3”
E 67018’54.9”
1.1 Objectives
The main objective of the proposed study was to collect the baseline ambient air
quality data (NOx, SO2, CO, Noise, PM10, PM2.5, Noise, Vibration and Meteorological
Parameters) at three sites along the selected route of Coal Conveyor and Coal Stockyard
for Coal Conveying System at Port Qasim, Karachi.
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
ENVIROMENTAL MONITORING AND MODELING DIVISION Page 3
2. AMBIENT AIR QUALITY MONITORING
2.1 Methodology
SUPARCO collected the ambient air data using its USEPA recommended
monitoring equipment at three sites along the Coal Conveying System at Port Qasim,
Karachi.
2.2 Data Acquisition Criteria a. Air Quality data (concentration) of criteria pollutants such as NOx (as sum of
NO & NO2), SO2, CO, PM10 and PM2.5, Vibration along with additional Noise
Level Monitoring was also performed at each site
b. The meteorological parameters (Wind Speed, Wind Direction, Temperature
and Relative Humidity) were also measured on site
c. The data (air quality and meteorological parameters) was collected with
interval of 01 hour for 24 hours at each site
d. The analyzer concentration limits are given in Table 2 for monitoring the air
quality
e. The data was analyzed under SEQS guidelines for ambient air quality given in
Table 3
Table 2: Concentration limits of Equipment
Equipment Min. Concentration Limits
SO2 Analyzer ~1 µg/m3
O3 Analyzer ~1 µg/m3
CO Analyzer < 0.5 mg/m3
NOx (NO+NO2) Analyzer ~ 1 µg/m3
PM2.5/PM10 Sampler ~ 5 µg/m3
Vibration Meter ~ 0.005 mm
Noise Meter ~ 0.1 dB
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
ENVIROMENTAL MONITORING AND MODELING DIVISION Page 4
2.3 Ambient Air Quality Monitoring Methods and Ambient Air Quality Standards
The air quality parameters were measured using the state of the art instruments
based upon the USEPA and ASTM methods. The ambient air quality
standards/guidelines of Pak EPA, USEPA, WHO and World Bank for data analysis and
comparison are given in Table 4.
Table 3: Ambient Air Quality Monitoring Methods
Pollutants Title of US EPA 40 CFR Methods
NOx Reference Method in Appendix F of 40 CFR Part 50 Chemiluminescence
SO2 Ambient Monitoring Reference & Equivalent Method of 40 CFR Part 52 Fluorescence Method
O3 Reference Method in Appendix D of 40 CFR Part 50 UV absorption
CO Method in Appendix C of 40 CFR Part 50 IR Gas Filter Correlation PM10 Reference Method in Appendix J of 40 CFR Part 50 Beta Source PM2.5 Reference Method of 40 CFR Appendix L of Part 50 Beta Source
Table 4: Ambient Air Quality Standards of Sindh EPA, USEPA, WHO and World Bank
Pollutants USEPA WHO World Bank SEQS
Avg. Time Standard Avg. Time Standard Avg. Time Standard Avg. Time Standard
SO2 24 HRS
365 ug/m3 (140 ppb)
24 HRS 10 min.
20 ug/m3
500 ug/m3
ANNUAL MEAN
24 HRS
100 ug/m3 (38 ppb)
500 ug/m3
ANNUAL MEAN
24 HRS
80 ug/m3
120 ug/m3
CO
8 HRS
1 HR
10 mg/m3 (9 ppm)
40 mg/m3
8 HRS
1 HR
10 mg/m3 (9 ppm)
40 mg/m3
- - 8 HRS
1 HR
5 mg/m3
10 mg/m3
NO2 Annual Mean
100 ug/m3 (53 ppb)
Annual Mean
1 Hr
40 ug/m3
200 ug/m3
ANNUAL MEAN
100 ug/m3 (50 ppb)
ANNUAL MEAN
24 HRS
80 ug/m3 -
120 ug/m3
O3 1 HRS 235ug/m3 8 HRS 100 ug/m3 - - - 130 ug/m3
TSP 24 HRS 260 ug/m3 - - A.MEAN
24 HRS
100 ug/m3
500 ug/m3
A.MEAN
24 HRS
360 ug/m3
500 ug/m3
PM10 24 HRS 150 ug/m3
Annual Mean
24 HRS
20 ug/m3
50 ug/m3 - -
A.MEAN
24 HRS
120 ug/m3
150 ug/m3
PM2.5 - - Annual Mean
24 HRS
10 ug/m3
25 ug/m3 - - 24 HRS 75 ug/m3
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
ENVIROMENTAL MONITORING AND MODELING DIVISION Page 5
2.4 Work Plan
The work plan followed for data acquisition was as under;
Commencing Date : 27-06-2016
Completion Date : 30-06-2016
Duration : 04 day
Supervisor and Field Monitoring Officials: 1. Dr. M. Mansha (General Manager)
2. Mr. Muhammad Khalid (Research Associate)
3. Mr. Zahid Hussain (Sub Engineer-II)
2.5 Air Quality Data Acquisition Plan 2.4.1 Plan
Site No –I Start Point (NWIZ Water Pumping Station) PQA
Starting Date: 27-06-2016
Starting Time: 1200
Completion Date: 28-06-2016
Completion Time: 1100
Sampling Duration: 24 Hrs Site No –II Pharm Evo
Starting Date: 28-06-2016
Starting Time: 1300
Completion Date: 29-06-2016
Completion Time: 1200
Sampling Duration: 24 Hrs
Site No –III End Point, PIBT Site
Starting Date: 29-06-2016
Starting Time: 1400
Completion Date: 30-06-2016
Completion Time: 1300
Sampling Duration: 24 Hrs
ENVIRON
3. G
3.1 Ox
Ni
are prod
processe
NO2 is a
environm
yellowish
3.1.1
observed
also obse
and Site
Figure 2 (a
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
Concen
tration (ug/m3)
MENTAL MO
ENERAL
xides of N
trogen oxid
duced from
es. NO is co
an odorous
ment. NOx a
h-brown col
Monit
The m
d at site 1,
erved at Si
3 was 3.9,
a): Minimum,
0
0
0
0
0
0
0
0
0
ONITORING O
DISCUS
Nitrogen (N
des (NOx),
m natural
olorless and
, brown, a
are critical
or of the sm
toring Res
measured m
which was
ite 2 was 7
5.6 and 4.4
Maximum an
End Point
C
OF COAL CONPO
SION AN
NOx)
a mixture o
sources,
d odorless
cidic, highl
componen
mog.
sults of N
minimum co
s 3.4. Simila
7.0. Averag
4 respective
nd Average (2
Concent
NVEYING SYORT QASIM
ND RESUL
of Nitric oxi
motor ve
and is oxid
y-corrosive
nts of phot
Ox
oncentratio
arly, the ma
ge concentr
ely.
24hrs) Conce
Pharm
tration o
YSTEM FROM
LTS
ide (NO) an
hicles and
dized in the
e gas that
tochemical
n of NO (µ
aximum co
ration of NO
ntration of NO
Evo
of NO
M PIBT TO RA
nd Nitrogen
d other fu
e atmosphe
can affect
smog, NO
µg/m3) at P
oncentration
O (µg/m3) a
O
Star
Mi
Av
Ma
SEQ
AILWAY NET
n dioxide (N
uel combu
ere to form
our health
O2 produces
Port Qasim
n of NO (µg
at Site 1, S
rt Point
n
erage
ax
QS
TWOK
NO2),
ustion
NO2.
h and
s the
was
g/m3)
Site 2
ENVIRON
Th
observed
also obse
and Site
Figure 2 (b
Th
internatio
Figures 2
3.2 Su
SO
way it re
children,
asthma p
3.2.1
observed
was obse
and Site
.
0
20
40
60
80
Concen
tration (ug/m3)
MENTAL MO
he measur
d at site 1, w
erved at Sit
3 was 10.1
b): Minimum,
he average
onal and SE
2(a) and 2(b
ulfur Diox
O2 causes
eacts with
the elderl
patients are
Monit
The m
d at site 1, w
erved at Sit
3 was 5.3,
0.0
0.0
0.0
0.0
0.0
ONITORING O
red minimu
which was
te 2 was 17
, 11.8 and
Maximum an
levels of N
EQS (see T
b).
xide (SO2)
a wide var
other subs
y people,
e more vuln
toring Res
measured m
which were
te 2 was 15
10.5 and 9
End Poin
C
OF COAL CONPO
um concen
0.8. Simila
7.2. Averag
10.6 respe
nd Average (2
NO and NO
Table 4 for
riety of hea
stances in
and peopl
erable.
sults of S
minimum co
e 3.8. Simila
5.3.Average
9.7 respectiv
nt
Concent
NVEYING SYORT QASIM
ntration of
arly, the ma
ge concentr
ctively.
24hrs) Conce
O2 were we
r reference
alth and en
the air. P
e with hea
O2
oncentration
arly, the ma
e concentra
vely.
Pharm
tration o
YSTEM FROM
NO2 (µg/
aximum con
ration of NO
ntration of NO
ell also with
) for ambie
nvironmenta
Particularly
art or lung
n of SO2 (µ
aximum co
ations of SO
m Evo
of NO2
M PIBT TO RA
/m3) at Po
ncentration
O2 (µg/m3)
O2
hin the pres
ent air qual
al impacts
y sensitive
diseases
µg/m3) at P
ncentration
O2 (µg/m3)
Sta
M
A
M
S
AILWAY NET
ort Qasim
of NO2 (µg
at Site 1, S
scribed lim
lity as show
because o
groups inc
specifically
Port Qasim
n of SO2 (µg
at Site 1, S
art Point
Min
Average
Max
SEQS
TWOK
was
g/m3)
Site 2
its of
wn in
of the
clude
y the
was
g/m3)
Site 2
ENVIRON
Figure 3 :
T
and natio
Figure 3.
3.3 Ca
Ca
one Carb
preferenc
Oxygen
value, bu
its seriou
to myriad
3.3.1 MT
observed
was obse
and Site
0.
20.
40.
60.
80.
100.
120.Co
ncen
tration (ug/m3)
MENTAL MO
Minimum, Ma
The averag
onal standa
arbon Mo
arbon Mono
bon atom c
ce to the m
present du
urning in ai
us toxicity, C
d products.
MonitorinThe measu
d at site 1, w
erved at Sit
3 were 0.4
.0
.0
.0
.0
.0
.0
.0
ONITORING O
aximum and A
ge levels of
ards (see T
noxide (C
oxide (CO)
covalently b
more usua
uring the co
r with a ch
CO plays a
g Resultsured minim
which were
te 2 were 1
, 1.8 and 0
End Point
C
OF COAL CONPO
Average (24h
f SO2 were
Table 3 for
CO)
) is a color
bonded to
l Carbon d
ombustion
aracteristic
highly use
s of CO mum conce
e 0.2. Simila
.5. Average
.9 respectiv
Concentr
NVEYING SYORT QASIM
hrs) Concentra
well within
r reference)
less, odorle
one Oxyge
dioxide whe
process. C
c blue flame
ful role in m
entration o
arly, the ma
e concentra
vely.
Pharm E
ration o
YSTEM FROM
ation of SOX
n the presc
) for ambie
ess, and ta
en atom. C
en there is
Carbon mon
e, producin
modern tech
of CO (mg
aximum co
ations of CO
Evo
f SO2
M PIBT TO RA
ribed limits
ent air qual
asteless ga
Carbon mon
s a reduce
noxide has
g Carbon d
hnology, be
g/m3) at Po
ncentration
O (mg/m3)
Start
Mi
Ave
Ma
SEQ
AILWAY NET
of internat
ity as show
as. It consis
noxide form
d availabili
s significant
dioxide. De
eing a prec
ort Qasim
n of CO (mg
at Site 1, S
Point
n
erage
ax
QS
TWOK
tional
wn in
sts of
ms in
ity of
t fuel
espite
ursor
was
g/m3)
Site 2
ENVIRON
Figure 4: M
T
internatio
shown in
3.4 OzOz
when ozo
health ef
active ou
Oz
environm
distances
In some
region.
3.4.1 MT
observed
Concen
tration (m
g/m3)
MENTAL MO
Minimum, Ma
The averag
onal and na
Figure 4.
zone (O3)zone in the
one can re
ffects. Chi
utdoors, inc
zone is par
ments. It is
s by wind.
cases, ozo
MonitorinThe measu
d at site 2
0.0
1.0
2.0
3.0
4.0
5.0
ONITORING O
aximum and A
ge levels of
ational stan
) e air we br
each unhea
ldren, peop
luding outd
rticularly lik
a major p
For this re
one can oc
g Resultsured minim
, which we
End Poin
C
OF COAL CONPO
Average (24hr
f Carbon M
dards (see
reathe can
althy levels.
ple with lu
oor worker
kely to reac
art of urba
eason, even
ccur throug
s of Ozonemum conce
ere 5.1. Si
nt
Concent
NVEYING SYORT QASIM
rs) Concentra
onoxide we
Table 3 fo
harm our
. Even rela
ng disease
rs, may be p
ch unhealth
an smog. O
n rural area
ghout the y
e ntration of
milarly, the
Pharm
tration o
YSTEM FROM
ation of CO
ere well wit
r reference
health—typ
atively low l
e, older ad
particularly
hy levels on
Ozone can
as can expe
year in som
Ozone (µ
e maximum
m Evo
of CO
M PIBT TO RA
hin the pre
e) for ambie
pically on h
evels of oz
ults, and p
sensitive to
n hot sunny
also be tr
erience high
me southern
g/m3) at P
m concentr
Star
Mi
Ave
Ma
SEQ
AILWAY NET
scribed lim
ent air quali
hot, sunny
zone can c
people who
o ozone.
y days in u
ransported
h ozone lev
n and mou
Port Qasim
ration of O
rt Point
n
erage
ax
QS
TWOK
mits of
ity as
days
cause
o are
urban
long
vels.
ntain
was
Ozone
ENVIRON
(µg/m3) w
Site 1, Si
Figure 5: M
T
internatio
shown in 3.5 Pa Pa
dry solid
tiny partic
of differe
particles.
one-millio
10 micro
as TSP.
2
4
6
8
10
12
14
Concen
tration (ug/m3)
MENTAL MO
was observ
ite 2 and Si
Minimum, Ma
The avera
onal and na
Figures 5.
articulate
articulate m
fragments
cles vary g
ent material
. PM may b
onth of a m
ns (PM10),
PM2.5 parti
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
ONITORING O
ved at Site
ite 3 was 7
aximum and A
age levels
ational stan
Matter (P
matter (PM)
, solid core
reatly in sh
ls such as
be divided i
meter).Sindh
particles u
icles are a s
End Poin
C
OF COAL CONPO
2 was 14.
.2, 8.6 and
Average (24hr
of Ozone
dards (see
M10,PM2.
is a comple
es with liqu
hape, size a
metals, so
into many s
h EPA regu
up to 2.5 m
subset of P
nt
Concent
NVEYING SYORT QASIM
3. Average
10.3 respe
rs) Concentra
e were we
Table 3 fo
.5 and SP
ex mixture
uid coatings
and chemic
oot, soil an
size fraction
ulates three
icrons (PM
PM10 where
Pharm
tration o
YSTEM FROM
e concentra
ectively.
ation of O3
ell within
r reference
M)
consisting
s and smal
cal compos
d dust. PM
ns, measur
e classes o
M2.5) and To
e as PM10 p
m Evo
of O3
M PIBT TO RA
ations of Oz
the presc
e) for ambie
of varying
ll droplets o
sition, and c
M may also
red in micro
of particles
otal Suspen
articles are
Star
Mi
Ave
Ma
SEQ
AILWAY NET
zone (µg/m
cribed limit
ent air quali
combinatio
of liquid. T
can be mad
contain su
ons (a micr
- particles
nded Partic
e subset of T
rt Point
n
erage
ax
QS
TWOK
m3) at
ts of
ity as
ons of
These
de up
ulfate
ron is
up to
culate
TSP.
ENVIRON
3.5.1 M
T
observed
(µg/m3) w
Site 1, Si
Figure 6:
T
and natio
Figures 6
3.5.2 MThe mea
site 1, w
observed
and Site
0
10
20
30
40
50
60
70
80
Concen
tration (ug/m3)
MENTAL MO
Monitorin
The measu
d at site 1
was observ
ite 2 and Si
Minimum, Ma
The averag
onal standa
6.
Monitorinasured mini
which were
d at Site 2 w
3 were 90,
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
ONITORING O
g Results
ured minim
, which we
ved at Site
ite 3 were 2
aximum and A
ge levels of
ards (see T
g Resultsimum conc
e 72. Simi
were 120.3
101 and 9
End Point
Co
OF COAL CONPO
s of PM 2.5
mum conce
ere 19.2. S
3 were 35
22, 25.8 an
Average (24h
PM2.5 were
Table 3 for
s of PM 10
centration o
larly, the m
3. Average
1.9 respect
t
oncentra
NVEYING SYORT QASIM
entration of
Similarly, th
5.3. Averag
d 31.9 resp
rs) Concentra
e well within
r reference)
of PM10 (µg
maximum
concentrat
tively.
Pharm
ation of P
YSTEM FROM
f PM2.5 (µg
he maximu
ge concentr
pectively.
ation of PM 2.
n the presc
) for ambie
g/m3) at Po
concentrati
ions of PM
Evo
PM 2.5
M PIBT TO RA
g/m3) at P
um concent
rations of P
5
cribed limits
ent air qual
rt Qasim w
ion of PM
10 (µg/m3)
Star
AILWAY NET
ort Qasim
tration of P
PM2.5 (µg/m
s of internat
ity as show
was observe
10 (µg/m3)
at Site 1, S
rt Point
Average
SEQS
Min
Max
TWOK
was
PM2.5
m3) at
tional
wn in
ed at
was
Site 2
e
ENVIRON
Figure 7: A
T
and natio
Figures 7 3.5.3 M
A
288 and
Figure 8: A
0
50
100
150Co
ncen
tration (m
g/m3)
050
100150200250300350400450500
Concen
tration (µg/m3)
MENTAL MO
Average (24h
The averag
onal standa
7.
MonitorinAverage co
259 respec
Average (24h
0.0
0.0
0.0
0.0
0.00.00.00.00.00.00.00.00.00.00.0
ONITORING O
hrs) Concentra
ge levels of
ards (see T
g Resultsoncentration
ctively.
hrs) Concentra
End Poin
Co
End Point
Con
OF COAL CONPO
ation of PM10
f PM10 were
Table 3 for
s of SPM ns of SPM
ation of SPM
t
oncentra
t
centrati
NVEYING SYORT QASIM
e well within
r reference)
(µg/m3) at
Pharm
ation of
Pharm
ion of SP
YSTEM FROM
n the presc
) for ambie
Site 1, Sit
Evo
PM 10
Evo
PM Leve
M PIBT TO RA
cribed limits
ent air qual
te 2 and S
Star
Star
elAvg
SEQS
AILWAY NET
s of internat
ity as show
ite 3 were
rt Point
Average
SEQS
Min
Max
rt Point
TWOK
tional
wn in
247,
e
ENVIRON
T
prescribe
ambient a
3.6 No
En
activities
- and fro
the enviro
3.6.1 MTh
observed
(dBA) wa
Site 1, Si
Figure 9: M
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
Concen
tration (dB)
MENTAL MO
The meas
ed limits of
air quality a
oise Leve
nvironmenta
, including
m sites of
onment, inc
onitoring he measure
d at site 3, w
as observed
ite 2 and Si
Minimum, Ma
E
ONITORING O
ured conc
internation
as shown in
el Measure
al noise is
noise emitt
industrial a
cluding hum
Results oed minimum
which were
d at Site 2
ite 3 were 4
aximum and A
nd Point
Conc
OF COAL CONPO
centrations
nal and nat
n Figures 8
ement
s unwanted
ted by mea
activity. It is
man health.
of Noise Lm concentr
e 40.9. Sim
were 73.9.
47.7, 67.6 a
Average (24hr
centratio
NVEYING SYORT QASIM
of SPM
tional stand
.
d or harmfu
ans of trans
s monitored
.
Level ration of no
ilarly, the m
Average c
and 54.7 re
rs) Noise leve
Pharm E
on of No
YSTEM FROM
(µg/m3) we
dards (see
ul outdoor
port - road
d to prevent
oise level
maximum c
concentratio
spectively
el
Evo
oise Leve
M PIBT TO RA
ere well a
Table 3 fo
sound cre
traffic, rail
t and reduc
(dBA) at P
concentratio
ons of nois
Star
elMin
Aver
Max
SEQS
AILWAY NET
also within
or reference
ated by hu
traffic, air t
ce its impa
Port Qasim
on of noise
e level (dB
t Point
rage
x
S
TWOK
n the
e) for
uman
traffic
ct on
was
level
BA) at
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
ENVIROMENTAL MONITORING AND MODELING DIVISION Page 14
3.7 Vibration
Vibration is a mechanical phenomenon whereby oscillations occur about an
equilibrium point. The word comes from Latin vibrationem ("shaking, brandishing"). The
oscillations may be periodic, such as the motion of a pendulum—or random, such as the
movement of a tire on a gravel road.]
There are currently no statutory limits for vibration. However, the Environment
Protection Act 1993 includes vibration in the definition of ‘noise’, and as such, the general
duty of care applies as above. Also, under common law, the Department or its
Contractors can be held liable if construction activities result in vibration-induced damage
to property.
3.7.1 Monitoring Results of Vibration
The measured minimum concentration of vibration (mm) at Port Qasim was
observed at site 1, which were 0.001. Similarly, the maximum concentration of vibration
(mm) was observed at Site 3 were 0.395. Average concentrations of vibration (mm) at
Site 1, Site 2 and Site 3 were 0.005, 0.151 and 0.151 respectively
3.8 Lead in Ambient Air
Lead (Pb) is a metal found naturally in the environment as well as in manufactured
products. The major sources of lead emissions have historically been from fuels in on-
road motor vehicles (such as cars and trucks) and industrial sources. The highest levels
of lead in air are usually found near lead smelters. The major sources of lead emissions
to the air today are ore and metals processing and piston-engine aircraft operating on
leaded aviation gasoline.
3.8.1 Testing Results of Lead
Average concentrations of Lead (µg/m3) at Site 1, Site 2 and Site 3 were ND, 0.6
and 0.4 respectively
The measured concentrations of lead (µg/m3) were well also within the prescribed
limits of international and national standards (see Table 3 for reference) for ambient air
ENVIRON
quality T
national s
3.9 M
In
ambient
meteorol
speed an
3.9.1 M
Th
site 2 an
observed
2 and Sit
Th
1 and S
observed
and Site
Th
at site 2,
at Site 2
3.1, 3.9 a
Figure 10:
1
1
2
2
3
3
MENTAL MO
The concen
standards f
eteorolog
this study
temperatu
ogical data
nd wind dire
Monitoring
he measure
d Site 3, w
d at Site 1 a
te 3 were 32
he measure
Site 2, whic
d at Site 2
3 were 61,
he measure
which was
was 17. A
and 3.3 res
Average (24
0
5
10
15
20
25
30
35
St
ONITORING O
ntration of
for ambient
gical Data
y, meteorol
re, relative
a of these p
ection at ea
g Results
ed minimum
which were
and Site 2 w
2, 30.5 and
ed minimum
ch were 3
and Site 3
74.5 and 8
ed minimum
s 1. Similarl
verage valu
pectively
4hrs) values o
tart Point
Ave
OF COAL CONPO
Lead (µg/
t air quality
logical para
e humidity
arameters
ach site is p
of Meteor
m value of t
25. Similar
was 37. Av
d 29.6 respe
m value of H
9. Similarly
was 94. A
80.1 respec
m value of W
ly, the max
ues of Win
of Temperatur
P
erage Air Tem
NVEYING SYORT QASIM
/m3) was
all three sit
ameters in
were me
are given i
produced as
rological D
temperature
rly, the max
verage valu
ectively
Humidity (%
y, the max
Average val
ctively
Wind Spee
ximum value
d Speed (m
re
harm Evo
mperature (⁰
YSTEM FROM
also within
tes.
ncluding wi
easured at
n Annexure
s wind rose
Data
e (°C) at Po
ximum valu
ues of temp
%) at Port Q
ximum valu
ues of Hum
ed (m/s) at
e of Wind S
m/s) at Site
E
⁰C)
M PIBT TO RA
n the pres
nd speed,
each site
e, while the
es.
ort Qasim w
e of tempe
perature (°C
Qasim was o
ue of Hum
midity (%) a
Port Qasim
Speed (m/s
e 1, Site 2 a
End Point
AILWAY NET
cribed limi
wind direc
e. The det
e prevailing
was observ
erature (°C)
C) at Site 1,
observed a
midity (%)
at Site 1, S
m was obse
s) was obse
and Site 3
TWOK
ts of
ction,
tailed
wind
ed at
) was
, Site
at site
was
Site 2
erved
erved
were
ENVIRON
Figure 11:
Figure 12:
1
2
3
4
5
6
7
8
9
Hum
idity(%
)
0
1
2
3
4
Wind Spe
d (m
/s)
MENTAL MO
Average (24
Average (24
0
10
20
30
40
50
60
70
80
90
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
ONITORING O
4hrs) values o
4hrs) values o
Start Point
Start Point
OF COAL CONPO
of Humidity
of Wind Speed
Average
Averag
NVEYING SYORT QASIM
d
Pharm Ev
e Humidity (%
Pharm Evo
ge Wind Sped
YSTEM FROM
vo
%)
d (m/s)
M PIBT TO RA
End
End Poin
AILWAY NET
Point
nt
TWOK
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
ENVIROMENTAL MONITORING AND MODELING DIVISION Page 17
Figure 13: Wind rose Plot Showing Wind Speed and Wind Direction (Blowing from) of water Pumping
Station (site-1) of the Project
Figure 14: Windrose Plot Showing Wind Speed and Wind Direction (Blowing from) of Pharm Evo (site-2)
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
ENVIROMENTAL MONITORING AND MODELING DIVISION Page 18
Figure 15: Windrose Plot Showing Wind Speed and Wind Direction (Blowing from) of Near PIBT (site-3)
4. WATER TESTING 4.1 Methodology
To assess the status of drinking water quality identified locations by the client.
SUPARCO collected the one (01) drinking water sample (Tap Water) from the End
point (NWIZ Water Pumping Station of Port Qasim) 2nd is ground water from the Shrine
Baba Kamal and 3rd from China Camp at PIBT, according to criteria specified by USEPA
and standard methods. The samples were tested in SUPARCO Environmental Lab
(SEL).
4.2 Data Acquisition Criteria
Three (03) drinking water samples were collected. The samples were analyzed in
SEL.
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
ENVIROMENTAL MONITORING AND MODELING DIVISION Page 19
a. Drinking Water Quality Testing Methods and Standards The drinking water quality parameters were measured using the state of the art
instruments based upon the USEPA and HACH methods. The national drinking water
quality standards for verifying compliance status are used for this report. The details of
methods and standards are given in Table 5.
Table 5: Testing Methods and National Standards for Drinking Water Quality
S. No. Parameters
Unit
*NSDWQ Method
1 E. Coliform MPN Must not be detected in any 100ml sample HACH 10029
2 Fecal Coliform MPN Must not be detected in any 100ml sample HACH 10029
3 Total Coliform MPN Must not be detected in any 100ml sample HACH 10029
4 Color TCU ≤ 15 HACH 8025
5 Taste - Non Objectionable / Acceptable
Sensory Test
6 Odor - Non Objectionable / Acceptable
Sensory Test
7 Turbidity NTU < 5 US-EPA 180.1
8 Total Hardness mg/l < 500 HACH 8213
9 TDS mg/l < 1000 US-EPA 160.1
10 pH - 6.5 – 8.5 ASTM D 1293 / US-EPA
150.2
11 Aluminium mg/l ≤ 0.2 US-EPA 200.8
12 Antimony mg/l ≤ 0.005 US-EPA 200.8
13 Arsenic mg/l ≤ 0.05 US-EPA 200.8
14 Barium mg/l 0.7 US-EPA 200.8
15 Boron mg/l 0.3 US-EPA 200.8
16 Cadmium mg/l 0.01 US-EPA 200.8
17 Chloride mg/l < 250 US-EPA 300.1 / HACH 8206
18 Chromium mg/l ≤ 0.05 US-EPA 200.8
19 Copper mg/l 2 US-EPA 200.8
20 Cyanide mg/l ≤ 0.05 HACH 8027
21 Fluoride mg/l ≤ 1.5 US-EPA 300.1 / HACH 8029
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
ENVIROMENTAL MONITORING AND MODELING DIVISION Page 20
4.3 Work Plan
The work plan followed for data acquisition was as under;
Sampling Date : 28-06-2016
Sample Receipt Date (SEL) : 28-06-2016
Analysis Completion Date : 04-07-2016
Supervisor and Field Monitoring Officials: 1. Dr. M. Mansha
(General Manager)
2. Mr. Muhammad Khalid
(Research Associate)
3. Mr. Zahid Husain Memon
(Sub Engineer)
22 Lead mg/l ≤ 0.05 US-EPA 200.8
23 Manganese mg/l ≤ 0.5 US-EPA 200.8
24 Mercury mg/l ≤ 0.001 US-EPA 200.8
25 Nickel mg/l ≤ 0.02 US-EPA 200.8
26 Nitrate mg/l ≤ 50 US-EPA 300.1 / HACH 8171
27 Nitrite mg/l ≤ 3 HACH 8507
28 Selenium mg/l 0.01 US-EPA 200.8
29 Residual Chlorine mg/l 0.2 - 0.5 HACH 8210
30 Zinc mg/l 5.0 US-EPA 200.8
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
ENVIROMENTAL MONITORING AND MODELING DIVISION Page 21
Figure 16: Satellite View of Locations of Water Sampling Sites 4.4 Water Quality Sampling Plan
Site 1 – End Point NWIZ Water Pumping Station (Tap Water)
Sampling Date: 28-06-2016
Site 2 – Shrine Baba Kamal (Ground Water) Sampling Date: 28-06-2016
Site 3 – Start Point (Tanker Water) Sampling Date: 28-06-2016
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
Environmental Monitoring & Modeling Division Page 24
4.5 Water Quality Results
Drinking Water: One (01) drinking water sample was collected from the Tap near
End Point (Water Pumping Station of Port Qasim) 2nd Drinking Water sample was
collected from the Shrine of Baba Kamal and 3rd sample was collected from the Water
Tanker at PIBT was analyzed in SEL. The sample was tested for biological, chemical,
and physical parameters to check their compliance with National Standards for Drinking
Water Quality (NSDWQ).
The results showed that the chemical and physical parameters were compliant
with the NSDWQ. However, E.Coli and Total Coliform were present in all the samples,
hence rendering the water unsuitable for drinking purposes. Table 6 shows the results of
drinking water sample.
Table 6: Drinking Water Quality Results
S. No. Parameters
Unit
Sample #1 (Water
Pumping Station)
Sample #2 (Shrine of
Baba Kamal)
Sample #3 (China Camp)
Method
1 E. Coliform MPN 7 10 5 HACH 10029
2 Fecal Coliform MPN 1 2 1 HACH 10029
3 Total Coliform MPN 8 12 6 HACH 10029
4 Color TCU 2 2 1 HACH 8025
5 Taste - Acceptable Acceptable Acceptable Sensory Test
6 Odor - Acceptable Acceptable Acceptable Sensory Test
7 Turbidity NTU 2.63 1.94 1.65 US-EPA 180.1
8 Total
Hardness mg/l 180 820 290 HACH 8213
9 TDS mg/l 131 514 116 US-EPA 160.1
10 pH - 7.6 7.4 7.7 ASTM D 1293 / US-EPA 150.2
11 Aluminium mg/l 0.015 0.013 0.044 US-EPA 200.8
12 Antimony mg/l *ND *ND *ND US-EPA 200.8
13 Arsenic mg/l *ND 0.009 0.006 US-EPA 200.8
14 Barium mg/l 0.056 0.121 0.043 US-EPA 200.8
15 Boron mg/l 0.028 0.071 0.019 US-EPA 200.8
16 Cadmium mg/l *ND *ND *ND US-EPA 200.8
17 Chloride mg/l 37 103 28 US-EPA 300.1 / HACH 8206
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
Environmental Monitoring & Modeling Division Page 25
S. No. Parameters
Unit
Sample #1 (Water
Pumping Station)
Sample #2 (Shrine of
Baba Kamal)
Sample #3 (China Camp)
Method
18 Chromium mg/l 0.003 0.009 0.013 US-EPA 200.8
19 Copper mg/l *ND 0.035 0.021 US-EPA 200.8
20 Cyanide mg/l *ND *ND *ND HACH 8027
21 Fluoride mg/l *ND 0.017 *ND US-EPA 300.1 / HACH 8029
22 Lead mg/l *ND *ND *ND US-EPA 200.8
23 Manganese mg/l 0.014 0.029 0.012 US-EPA 200.8
24 Mercury mg/l *ND *ND *ND US-EPA 200.8
25 Nickel mg/l 0.008 0.011 0.003 US-EPA 200.8
26 Nitrate mg/l 0.025 0.037 0.018 US-EPA 300.1 / HACH 8171
27 Nitrite mg/l *ND 0.010 *ND HACH 8507
28 Selenium mg/l *ND *ND *ND US-EPA 200.8
29 Residual Chlorine mg/l 0.26 0.24 0.09 HACH 8210
30 Zinc mg/l 0.089 0.161 0.124 US-EPA 200.8
31 Phenolic Compounds (as phenol)
mg/l *ND *ND *ND HACH 8047
* ND = Not Detected 4.6 Conclusion
The average levels of Oxides of Nitrogen, Sulphur Dioxide, Carbon Monoxide,
Ozone, Particulate Matter (PM2.5, PM10 and SPM), were well within the prescribed limits
of international and national environmental standards (see Table 3 for reference).
Similarly, most of the parameters were compliant with the NSDWQ for drinking water
sample, except Biological parameters.
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
Environmental Monitoring & Modeling Division Page 26
Annexure-I (Detailed Monitoring Data)
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
Environmental Monitoring & Modeling Division Page 27
S. No Date Time SO2
(µg/m3) NO
(µg/m3) NO2
(µg/m3) CO
(mg/m3) O3
(µg/m3) Noise (dB)
Vibration (mm)
PM 2.5 (µg/m3)
PM 10 (µg/m3)
PM total (µg/m3)
Lead (µg/m3)
Air Temperature
(°C) Humidity
(%) Wind
Speed (m/s)
Wind Direction
(Deg)
1 27-06-2016 1200 4.7 4.7 10.3 0.5 6.2 48.1 0.008 20.2 92
247.0
ND
36.0 44 5.1 90 2 27-06-2016 1300 7.7 3.5 10.3 0.8 9.5 53.3 0.005 20.8 107 37.0 39 3.6 90 3 27-06-2016 1400 6.9 4.2 10.8 0.6 9.8 55.4 0.006 20.9 97 36.0 47 4.1 200 4 27-06-2016 1500 7.1 4.5 11.1 0.5 9.5 51.2 0.004 22.0 88 35.0 53 4.1 135 5 27-06-2016 1600 6.5 4.2 11.3 0.4 9.5 46.8 0.005 22.5 78 35.0 53 4.1 135 6 27-06-2016 1700 6.3 4.5 10.5 0.4 8.8 44.0 0.009 23.5 72 33.0 55 5.1 180 7 27-06-2016 1800 5.9 4.2 10.1 0.4 6.5 57.2 0.004 23.7 91 33.0 55 4.6 135 8 27-06-2016 1900 6.1 3.8 11.0 0.3 7.6 57.7 0.003 23.8 87 31.0 66 4.6 160 9 27-06-2016 2000 4.1 3.7 8.8 0.5 6.2 45.7 0.002 22.1 82 31.0 66 3.6 180
10 27-06-2016 2100 4.3 3.7 8.8 0.5 6.3 50.2 0.001 20.7 88 31.0 66 4.1 200 11 27-06-2016 2200 4.4 3.8 9.2 0.4 6.5 47.5 0.002 22.1 101 30.0 74 2.1 200 12 27-06-2016 2300 5.3 3.8 9.3 0.5 6.2 44.2 0.002 20.9 102 30.0 74 2.1 200 13 28-06-2016 0000 5.3 3.7 9.5 0.5 6.1 45.7 0.002 22.4 97 30.0 74 1.5 115 14 28-06-2016 0100 5.0 3.7 9.5 0.5 6.2 45.7 0.001 21.7 101 30.0 74 1.0 70 15 28-06-2016 0200 5.2 4.0 10.0 0.5 6.3 50.2 0.004 21.3 88 30.0 74 1.5 70 16 28-06-2016 0300 5.3 4.2 10.1 0.6 6.1 47.5 0.006 22.1 97 30.0 74 2.1 23 17 28-06-2016 0400 5.9 4.0 11.1 0.2 7.6 44.8 0.006 24.3 97 29.0 74 2.1 23 18 28-06-2016 0500 5.3 4.2 11.3 0.2 7.7 42.1 0.007 23.8 78 29.0 79 2.6 359
PROJECT Environmental Monitoring at Port Qasim, Karachi; June 2016 CLIENT M/s NESPAK
SITE ID Site 1:- Start Point PQA (Pumping Station) COORDINATES N 240 49' 46"
E 670 17' 18.5"
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
Environmental Monitoring & Modeling Division Page 28
19 28-06-2016 0600 5.2 4.0 11.0 0.3 6.9 44.0 0.005 23.0 88 30.0 70 3.1 23 20 28-06-2016 0700 5.0 3.8 11.1 0.3 6.6 44.2 0.005 23.2 97 31.0 66 1.5 70 21 28-06-2016 0800 4.3 3.4 9.0 0.3 6.5 45.7 0.008 22.3 78 32.0 59 2.1 70 22 28-06-2016 0900 4.3 3.5 9.5 0.5 6.6 44.0 0.007 20.9 90 33.0 55 2.1 45 23 28-06-2016 1000 3.8 3.7 9.2 0.4 6.4 44.2 0.006 21.4 85 36.0 41 3.6 90 24 28-06-2016 1100 4.1 3.7 9.3 0.6 6.5 45.7 0.004 19.2 78 36.0 41 5.1 90
Maximum 7.7 4.7 11.3 0.8 9.8 57.7 0.009 24.3 107.1
247.0
ND
- - - -
Minimum 3.8 3.4 8.8 0.2 6.1 42.1 0.001 19.2 72.0 - - - -
Average 5.3 3.9 10.1 0.4 7.2 47.7 0.005 22.0 90.0 - - - -
SEQS 120 40 80 5 120 85 - 75 150 500 1.5 - - - -
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
Environmental Monitoring & Modeling Division Page 29
S. No Date Time SO2
(µg/m3) NO
(µg/m3) NO2
(µg/m3) CO
(mg/m3) O3
(µg/m3) Noise (dB)
Vibration (mm)
PM 2.5 (µg/m3)
PM 10 (µg/m3)
PM total (µg/m3)
Lead (µg/m3)
Air Temperature
(°C) Humidity
(%) Wind
Speed (m/s)
Wind Direction
(Deg)
1 28-06-2016 1300 7.5 4.2 8.4 1.8 5.3 65.1 0.345 25.7 103
288.0
0.6
36.0 44 6.2 180 2 28-06-2016 1400 6.7 4.4 7.5 1.6 8.0 69.9 0.251 24.2 120 37.0 39 6.2 225 3 28-06-2016 1500 7.9 4.6 8.8 1.7 9.6 67.4 0.252 25.8 109 35.0 53 3.6 180 4 28-06-2016 1600 9.4 4.7 13.2 1.7 9.8 72.7 0.182 24.4 98 34.0 56 5.1 180 5 28-06-2016 1700 11.9 4.6 13.4 1.5 11.3 73.4 0.193 26.1 88 33.0 59 7.2 315 6 28-06-2016 1800 10.8 6.9 13.4 1.6 14.4 69.9 0.206 25.4 81 30.0 79 2.6 330 7 28-06-2016 1900 9.3 5.8 8.9 1.8 5.4 60.4 0.315 26.8 102 31.0 75 2.6 340 8 28-06-2016 2000 7.9 5.1 8.9 2.0 5.1 64.5 0.326 27.1 98 27.0 94 17. 23 9 28-06-2016 2100 7.4 5.1 8.3 1.9 5.5 61.9 0.195 26.0 92 25.0 94 3.1 330 10 28-06-2016 2200 7.2 5.1 8.0 1.9 5.1 64.5 0.123 24.4 98 27.0 84 2.6 315 11 28-06-2016 2300 7.2 5.1 8.0 1.7 5.2 65.7 0.059 25.0 113 28.0 84 3.1 340 12 29-06-2016 0000 6.9 5.1 7.8 1.8 5.2 67.6 0.069 22.4 115 28.0 84 2.1 340 13 29-06-2016 0100 13.7 6.1 15.4 1.5 13.7 67.0 0.084 24.8 109 28.0 84 2.6 330 14 29-06-2016 0200 13.1 7.0 14.7 1.5 14.1 65.8 0.104 25.7 113 29.0 84 4.6 330 15 29-06-2016 0300 14.1 6.0 15.8 1.9 11.4 67.4 0.088 23.6 98 29.0 79 1.0 45 16 29-06-2016 0400 13.7 6.5 15.4 1.9 10.4 70.6 0.141 24.4 109 28.0 84 1.5 45 17 29-06-2016 0500 12.8 6.4 14.3 1.8 11.3 71.5 0.126 24.3 109 28.0 89 2.1 70 18 29-06-2016 0600 15.3 5.7 17.2 1.9 11.8 73.9 0.154 25.6 88 28.0 89 2.6 45
PROJECT Environmental Monitoring at Port Qasim, Karachi; June 2016 CLIENT M/s NESPAK
SITE ID Site 2:- Pharm Evo, PQA COORDINATES N 240 49' 40.4" E 670 17' 37.4"
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
Environmental Monitoring & Modeling Division Page 30
19 29-06-2016 0700 13.0 6.6 14.5 1.8 9.6 72.0 0.132 26.3 98 29.0 84 2.1 70 20 29-06-2016 0800 12.9 5.9 14.5 1.9 8.6 65.2 0.348 27.4 109 31.0 75 4.6 70 21 29-06-2016 0900 12.8 5.7 14.3 1.9 6.7 63.6 0.229 27.6 88 31.0 75 2.6 90 22 29-06-2016 1000 10.8 5.7 12.1 1.9 6.1 68.4 0.147 27.8 101 33.0 66 2.6 115 23 29-06-2016 1100 9.7 5.9 10.8 1.8 6.1 65.7 0.121 28.4 95 33.0 75 2.6 180 24 29-06-2016 1200 10.6 6.6 10.1 2.1 6.2 68.9 0.135 30.6 88 34.0 59 3.6 180
Maximum 15.3 7.0 17.2 2.1 14.4 73.9 0.348 30.6 120.4
288.0
0.6
- - - -
Minimum 6.7 4.2 7.5 1.5 5.1 60.4 0.059 22.4 80.9 - - - -
Average 10.5 5.6 11.8 1.8 8.6 67.6 0.180 25.8 101.1 - - - -
SEQS 120 40 80 5 120 85 - 75 150 500 1.5 - - - -
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
Environmental Monitoring & Modeling Division Page 31
S. No Date Time SO2
(µg/m3) NO
(µg/m3) NO2
(µg/m3) CO
(mg/m3) O3
(µg/m3) Noise (dB)
Vibration (mm)
PM 2.5 (µg/m3)
PM 10 (µg/m3)
PM total (µg/m3)
Lead (µg/m3)
Air Temperature
(°C) Humidity
(%) Wind Speed (m/s)
Wind Direction
(Deg)
1 29-06-2016 1400 10.8 3.8 11.6 0.6 6.5 60.4 0.363 34.3 97.2
259.0
0.4
33.0 66 9.3 330 2 29-06-2016 1500 7.9 3.6 12.4 0.6 8.0 59.3 0.395 34.8 95.6 25.0 94 3.1 45 3 29-06-2016 1600 8.4 5.1 9.8 0.7 8.2 60.0 0.352 34.3 89.8 28.0 84 3.6 359 4 29-06-2016 1700 11.2 5.1 11.6 0.7 9.9 61.0 0.196 33.5 101.7 28.0 84 1.5 45 5 29-06-2016 1800 9.0 5.0 11.2 0.7 10.7 62.5 0.192 32.1 101.9 29.0 79 1.0 330 6 29-06-2016 1900 9.2 3.9 12.0 0.7 11.6 59.9 0.098 29.5 93.7 29.0 79 2.1 315 7 29-06-2016 2000 9.9 4.4 11.9 0.6 11.9 52.3 0.104 31.0 85.3 29.0 74 3.6 315 8 29-06-2016 2100 11.3 3.9 12.1 0.6 11.2 53.4 0.106 28.6 93.8 30.0 74 Calm 9 29-06-2016 2200 11.2 3.8 12.2 0.5 11.3 50.7 0.108 31.0 85.4 29.0 78 2.6 45 10 29-06-2016 2300 10.2 3.6 12.5 0.7 11.3 46.1 0.094 33.5 79.6 29.0 84 Calm 11 30-06-2016 0000 9.2 3.8 12.7 0.7 11.0 40.9 0.087 33.5 82.6 28.0 89 2.6 340 12 30-06-2016 0100 8.8 3.5 10.2 0.8 11.2 51.7 0.104 31.9 91.4 28.0 89 Calm 13 30-06-2016 0200 9.3 4.2 9.2 0.7 11.2 52.9 0.085 31.6 92.5 28.0 89 Calm 14 30-06-2016 0300 8.7 4.4 9.0 0.7 10.7 42.7 0.096 30.8 88.6 28.0 89 Calm 15 30-06-2016 0400 9.5 4.4 9.2 1.0 10.4 45.9 0.079 32.2 97.0 28.0 89 2.6 270 16 30-06-2016 0500 9.6 4.2 9.0 1.0 10.4 49.4 0.066 32.0 97.0 28.0 89 Calm 17 30-06-2016 0600 9.8 4.2 8.8 1.1 10.2 50.2 0.063 31.9 102.8 28.0 94 Calm
PROJECT Environmental Monitoring at Port Qasim, Karachi; June 2016 CLIENT M/s NESPAK
SITE ID Site 3:- End Point (Stock Yard) COORDINATES N 240 49' 41.3" E 670 18' 54.9"
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
Environmental Monitoring & Modeling Division Page 32
18 30-06-2016 0700 9.7 4.4 9.0 1.2 10.5 55.3 0.047 31.9 93.9 29.0 89 4.6 315 19 30-06-2016 0800 9.8 4.8 9.6 1.2 10.7 56.2 0.099 35.6 85.7 30.0 84 4.6 359 20 30-06-2016 0900 9.9 5.3 9.5 1.3 8.0 58.8 0.084 34.1 91.6 31.0 79 Calm 21 30-06-2016 1000 10.1 5.3 9.9 1.3 8.7 59.5 0.082 30.8 86.8 33.0 66 3.1 250 22 30-06-2016 1100 10.1 5.1 10.1 1.1 8.4 61.4 0.141 27.4 91.4 34.0 63 Calm 23 30-06-2016 1200 10.1 5.2 10.7 1.1 12.4 61.7 0.285 29.8 92.5 34.0 63 1.5 270 24 30-06-2016 1300 9.8 5.2 10.8 1.0 12.2 61.2 0.296 31.0 88.6 34.0 52 4.1 180
Maximum 11.3 5.3 12.7 1.3 12.4 62.5 0.395 35.6 102.8
259.0
0.4
- - - -
Minimum 7.9 3.5 8.8 0.5 6.5 40.9 0.047 27.4 79.6 - - - -
Average 9.7 4.4 10.6 0.9 10.3 54.7 0.151 32.0 91.9 - - - -
SEQS 120 40 80 5 120 85 - 75 150 500 1.5 - - - -
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
Environmental Monitoring & Modeling Division Page 33
Annexure-II (MONITORING SURVEY PICTURES)
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
Environmental Monitoring & Modeling Division Page 34
i: End Point Pictures (NWIZ/ Pumping Station PQA)
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
Environmental Monitoring & Modeling Division Page 35
ii: Pharm-Evo Pictures
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
Environmental Monitoring & Modeling Division Page 36
iii: Start Point (PIBT) Pictures
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
Environmental Monitoring & Modeling Division Page 37
iv: Water Sampling Pictures
Water sampling at NWIZ/ PQA Pumping Station
Water sampling at Shrine of Baba Kamal Shah
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
Environmental Monitoring & Modeling Division Page 38
v: Noise and Vibration Monitoring
Noise Monitoring at PIBT
Vibration testing at PIBT
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
Environmental Monitoring & Modeling Division Page 39
Vibration Monitoring at Pharm Evo Noise Monitoring at Pharm Evo
ENVIRONMENTAL MONITORING OF COAL CONVEYING SYSTEM FROM PIBT TO RAILWAY NETWOK PORT QASIM
Environmental Monitoring & Modeling Division Page 40
Vibration Monitoring near Water Pumping Station Noise Monitoring near Water Pumping Station
ANNEXURE
EIA of Coal Conveying System at Port Qasim, Karachi
NESPAK July, 2016
Annexure-III: ENVIRONMENTAL NOISE MODELING
Annexure-III Environmental noise Modeling EIA of Coal Conveying System - Port Qasim, Karachi
____________________________________________________________________________________________________ NESPAK Page III-1 July, 2016
ENVIRONMENTAL NOISE MODELING Environmental noise modelling describes the process levels within a region of interest under a specific set of conditions. The specific set of conditions for which the noise is being estimated representation or 'snapshot' of a physical environment of interest. However, in practice the physical environment will usually not be fixed, but will be characterized by constantly varying conditions. These variations in real world conditions will subsequently cause the actual sound field to vary in time and space. Thus it is important to recognize that the output of an environmental noise model will only represent an estimate for a ‘snapshot’ of the range of actual environmental noise levels that could occur in time and space.
The noise model for machinery during the construction phase is attached as an annexure III which shows that the noise levels will be high at a distance of 10 meter from the source machinery. This modelling result is applicable when all the mentioned construction machinery is working at the same time. However, ideally this will not occur (all machinery functioning at the same time), so the noise level will be reduced as per the number of machinery working.
ANNEXURE-III Environmental noise ModelingEIA of Coal Conveying System - Port Qasim, Karachi
Dump trucks 70 70 0 1 0 70 10 0.4 70Dozer 55 55 0 1 0 55 10 0.4 55Pneiumatic tyre rollers 71 71 0 1 0 71 10 0.4 71Sheep foot rollers 75 75 0 1 0 75 10 0.4 75Three wheel rollers 65 65 0 1 0 65 10 0.4 65Grader 85 85 0 1 0 85 10 0.6 86Excavator (Tyre) 75 75 0 1 0 75 10 0.5 76Crane 60 60 0 1 0 60 10 0.3 58Dump trucks 70 70 0 1 0 70 10 0.4 70Tendem rollers 62 62 0 1 0 62 10 0.2 59Water tankers 65 65 0 1 0 65 10 0.2 62Plate Compactor 80 80 0 1 0 80 10 0.5 81Vibratory Roller 85 85 0 1 0 85 10 0.2 82Concrete batching plant 80 80 0 1 0 80 10 0.4 80Tractor 70 70 0 1 0 70 10 0.4 70Tractor Troller 70 70 0 1 0 70 10 0.4 70Tractor Trolley-J 70 70 0 1 0 70 10 0.4 70Air Compressor (Diesel & Electrical) 55 55 0 1 0 55 10 0.4 55Electric Vibrator / Petrol 60 60 0 1 0 60 10 0.3 58Steel Cutting Machine 85 85 0 1 0 85 10 0.4 85Steel Bending Machine 80 80 0 1 0 80 10 0.5 81Water Bowzer 60 60 0 1 0 60 10 0.2 57Water Pump 82 82 0 1 0 82 10 0.4 82Power Generator 82 82 0 1 0 82 10 0.4 82Welding plant (Diesel) 72 72 0 1 0 72 10 0.4 72Dewatering Pump (Diesel) 77 77 0 1 0 77 10 0.5 78Asphalt distributor 77 77 0 1 0 77 10 0.5 78Trailer 68 68 0 1 0 68 10 0.6 69
Environmental Noise ModelingCoal Conveying System - Port Qasim, Karachi
Usage Factor (UF)
Equipment Leq(h) at
Receptor (dbA) Leq (h)
Leq(h) Site at Receptor db(A)
Noise level emissions Leq (h)=E.L =Lj+EF
Estimated Distance from Equipment to
Observer (D) E
92
Clearing,earthwork,
foundation, piling, super structure etc.
Predicted Noise Level for Coal Conveying System (Receptor Distance 10 meter)
Activity Source
Typical Peak Sound Level in
Work Cycle (Lm)
Typical MInimum
Sound Level in Work Cycle
(Lb)
Lm-Lb
Fraction of time spent at peak in work Cycle (Ta/T)
Equivalency Factor (E.f)
ANNEXURE
EIA of Coal Conveying System at Port Qasim, Karachi
NESPAK July, 2016
Annexure-IV: AIR DISPERSION MODELING
1Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
AIR DISPERSION MODELING OF PARTICULATEMATTER EMISSIONS FROM COAL STOCKPILES ANDCONVEYING BELT SYSTEM
PAKISTAN SPACE & UPPER ATMOSPHERE RESEARCH COMMISSION(SUPARCO)
Sector 2 8, Gulzar-e-Hijri Off .University Road, P.O.Box 8402, Karachi-75270Phone: (92-21) 34650765-7434694941, Fax: (92-21) 34644928
1Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
AIR DISPERSION MODELING OF PARTICULATEMATTER EMISSIONS FROM COAL STOCKPILES ANDCONVEYING BELT SYSTEM
PAKISTAN SPACE & UPPER ATMOSPHERE RESEARCH COMMISSION(SUPARCO)
Sector 2 8, Gulzar-e-Hijri Off .University Road, P.O.Box 8402, Karachi-75270Phone: (92-21) 34650765-7434694941, Fax: (92-21) 34644928
1Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
AIR DISPERSION MODELING OF PARTICULATEMATTER EMISSIONS FROM COAL STOCKPILES ANDCONVEYING BELT SYSTEM
PAKISTAN SPACE & UPPER ATMOSPHERE RESEARCH COMMISSION(SUPARCO)
Sector 2 8, Gulzar-e-Hijri Off .University Road, P.O.Box 8402, Karachi-75270Phone: (92-21) 34650765-7434694941, Fax: (92-21) 34644928
2Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
DISCLAIMER
This report containing 16 pages is produced in compliance with the request of M/s
NESPAK, Karachi for “Air Dispersion Modeling of Emissions from Transportation,
Transferring and Storage of Coal” activities to ascertaining impact on ambient air
quality for coal conveying system from PIBT to railway Network at Port Qasim. The
information is based upon the modeling results using USEPA regulatory “AERMOD”
modeling system. UPARCO expert has verified the information contained in this report
and any changes made hereafter would not be the SUPARCO’s responsibility.
3Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
PREPARED BY: Name: Dr. M. Mansha
Designation: General Manager, SUPARCO
Signature---------
SUBMITTED TO: M/s NESPAK, KARACHI
4Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
AIR DISPERSION MODELING OF PARTICULATEMATTER EMISSIONS FROM COAL STOCKPILES ANDCONVEYING BELT SYSTEM
1. INTRODUCTION:
Fugitive emissions are emitted gaseous or aerosol materials that do not pass
through vents, stacks or other openings. These emissions can affect air quality
near a source and are regulated by federal and state agencies. By their nature,
fugitive emissions are difficult to quantify. Indirect techniques have been used to
estimate emissions and relate them to some kind of human activity or physical
process (e.g., wind erosion of soils)
2 AN OVERVIEW OF AERMOD:
USEPA developed an air dispersion regulatory model “AERMOD” (American
Meteorological Society/Environmental Protection Agency Regulatory MOdel) is a
steady state plume model. It assumes the concentrations at all distances during a
modeled hour which are governed by the temporally averaged meteorology of the
hour.
The AERMOD modeling system consists of two pre-processors and the
dispersion model (i) AERMET-meteorological preprocessor and (ii) AERMAP for
characterizing the terrain and generates receptor grids for the dispersion model.
The data information flow is shown in Figure 1.
5Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
Figure 1: Data flow in the AERMOD modeling system
2. MODELING OBJECTIVE AND METHODOLOGY:
The major objectives the modeling study are (i) to estimates the impact of
emissions due to transportation, transfer and storage of coal from PIBT to Coal
storage yard at Port Qasim, Karachi and (ii) its compliance to Sindh Environmental
Quality Standards (SEQS) for PM10. Following approach is adapted to during the
modeling of the emissions to achieve the above objectives;
(i) Identification of sources of dust emissions due to the project
activities.
(ii) Estimation of rates from the coal transportation, transferring and
storage using the empirical formulas from the published literature
(iii) Pre-Processing of Meteorological data (both surface and upper
profile) using AERMET tool along with basic terrain characteristics
(iv) Incorporating building downwash using BPIP-PRIME (requires source
and building information)
(v) Characterizing site – complete source and receptor information.
(vi) Performing terrain data pre-processing (if required) for AERMOD
dispersion model using AERMAP.
6Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
(vii) Running the model for the following two scenarios: Scenario 1
represents uncontrolled dust emissions. Scenario 2 represents the
dust emissions with controls on emissions from coal stockyard,
Conveyor Belt System and Mobile Hoppers at the Transfer Towers.
(viii) Visualizing and analyzing results using 3-D Analysis (a post
processing tool in AERMOD Suit) as shown in Figure 2 for each of
the said scenarios.
In current study, it is also assumed that Particulate Matter (PM as PM10)
emission is contributed due to both natural means due to wind erosion and
anthropogenic activity of coal transportation at the proposed stockpile piles and
transportation system consisting Conveyor Belts System and Transfer Towers in the
project site located at Port Qasim. The size of stockpile is 115m long, 50m wide and
12.5m high within dimensions of site. In the project site, there eight piles (08) with
each of capacity of 55,000 tons are located in the proposed project sites. It is also
assumed that particles size of coals of each of stockpile is uniform and have same
emission rates as estimated.
Figure 2. An Output Overview Diagram1
1 User Operational Manual of AERMOD, Trinity Consultants, USA
7Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
3. IDENTIFICATION OF EMISSION SOURCES FROM THE PROJECT
ACTIVITIES:
The coals is transported from PIBT to Coal Stock Pile Yard consisting of eight stock
pile (each having size s mentioned above). In this transportation rout, there are three
Transfer Towers (TTs) and four section of Conveyor Belt (CBs) and finally Stock Pile
Yard as shown in Figure 3. This whole process will result in coal dust emissions
(particulate matter). This routs and process can be described as;
i. Loading of Coal from PIBT to Conveyor Belt System (CB-1)
ii. Transfer of Coal to 2nd Conveyor Belt (CB-2) through Transfer Tower-1
(PQA-TT-1)
iii. Loading of Coal from Conveyor Belt (CB-2) to Transfer Tower-2 (PQA-TT-2)
iv. Transfer of Coal from Transfer Tower-2 (PQA-TT-2) to Conveyor Belt (CB-3)
and L3
v. Transfer of Coal from Conveyor Belt (CB-3) to Transfer Tower-3 (PQA-TT-3)
vi. Transfer of Coal from Transfer Tower-3 (PQA-TT-3) to Stock Pile Yard
The major source of emissions is the Stock Pile Yard due to wind Erosion process and
loading of coal from pile to Rapid Load- out Station. Each of the section of the
Conveyor Belts has design capacity of 3,600 Ton per day and each
8Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
Figure 3: Rout Plan of Transportation and Storage of Coal from PIBT
3. EMISSIONS RATE ESTIMATION:
Empirical formulas are used to estimates the emission rates from each of the
major source indentified as;
a. Emissions due to Wind Erosion in Coal Storage Stock Piles2
b. Fugitive Emissions from Transportation Processes using Conveyor Belt
System
c. Fugitive Emissions due to loading of coal from Belts to Mobile Hoppers and
Unloading to Conveyor Belts at Transfer Towers.
The emissions are calculated considering the worst-case quantity (maximum) of coal
is stored has been used. The fugitive emissions factor are adopted from published
2 https://www3.epa.gov/ttn/chief/ap42/ch13/final/c13s0204.pdf
8Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
Figure 3: Rout Plan of Transportation and Storage of Coal from PIBT
3. EMISSIONS RATE ESTIMATION:
Empirical formulas are used to estimates the emission rates from each of the
major source indentified as;
a. Emissions due to Wind Erosion in Coal Storage Stock Piles2
b. Fugitive Emissions from Transportation Processes using Conveyor Belt
System
c. Fugitive Emissions due to loading of coal from Belts to Mobile Hoppers and
Unloading to Conveyor Belts at Transfer Towers.
The emissions are calculated considering the worst-case quantity (maximum) of coal
is stored has been used. The fugitive emissions factor are adopted from published
2 https://www3.epa.gov/ttn/chief/ap42/ch13/final/c13s0204.pdf
8Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
Figure 3: Rout Plan of Transportation and Storage of Coal from PIBT
3. EMISSIONS RATE ESTIMATION:
Empirical formulas are used to estimates the emission rates from each of the
major source indentified as;
a. Emissions due to Wind Erosion in Coal Storage Stock Piles2
b. Fugitive Emissions from Transportation Processes using Conveyor Belt
System
c. Fugitive Emissions due to loading of coal from Belts to Mobile Hoppers and
Unloading to Conveyor Belts at Transfer Towers.
The emissions are calculated considering the worst-case quantity (maximum) of coal
is stored has been used. The fugitive emissions factor are adopted from published
2 https://www3.epa.gov/ttn/chief/ap42/ch13/final/c13s0204.pdf
9Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
literature3. However, the real/actual emissions could be calculated based on the
average amount of coal usually maintained in the storage pile. The annual emission
from wind erosion of coal piles was calculated based on the following equation:
AEi (lb/yr) = Q x EFPM x Ci-------------------------------A
Where,
AEi = Annual emissions of chemical I, lb/yr
Q = Maximum potential
EFPM = Particulate Matter emission factor, lbPM/ton coal stored;
Ci =Chemical mass speciation (equal to 1.0 for PM), fraction
While the formulas for emission rates calculation from other sources are given in
Table 1.
Table 1: Emission Rate Calculations due to Wind Erosion
Sr. No Source Length(m)
Width(m)
Area(m2)
Emission FactorCalculation
Emission Rate (g/s-m2)
without ControlMeasures
Emission Rate(g/s-m2)
with ControlMeasures
1 Stock Pile 115 50 5750 AEi (lb/yr) = Q xEFPM x Ci as above
0.21818 0.022
2 Conveyor Belt 1 (CB-1)from PIBT to TT-1 70 1.8 126
k(0.0032*(U/5)1.3)/(M/2)1.4)*(length of conveyor
belt/1000ft)
8.78 E-06 8.78E-07
3 Conveyor Belt (CB-2)from TT-1 to TT-2 1692 1.8 3045.6 3.63 E-06 3.63E-07
4 Conveyor Belt (CB-3)from TT-2 to TT-3 2850 1.8 5130 2.15 E-07 2.15E-08
5 Conveyor Belt (CB-4)from TT-3 to CoalYard
646 1.8 1162.8 9.51 E-07 9.51E-08
Mobile Hoppers (TT-1,TT-2, TT-3 ) 3.5 3 10.5 k*0.0032*((U/5)1.3)/(M/2
)1.4 1.054 E-4 0.17455
U is mean Wind Speed =3.9 mile/hr; M is Moisture Content (%)= 3.5, Active days are310 (85% of the year).
Background Concentration (Annual Avrg) of 110 ug/m3 was used in the model which is
added in the modeled concentrations which was determined from field survey of the
project site using UEPA designated method based upon Beta Attenuation Method
(BAM) were used as Back Ground Concentration.
3 How to Control Fugitive Emissions from coal-fired plants” (Power Magazime, June 1987)
10Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
4 MODELING SCENARIOS:
The modeling was carried out for the following scenarios: Scenario 1; Scenario 1
represents uncontrolled dust emissions. Scenario 2; Scenario 2 represents the dust
emissions with controls on emissions from coal stockyard, Conveyor Belt System and
Mobile Hoppers at the Transfer Towers. The proposed control measures include (i) the
continuous water spraying in coal stockyard and Covering of Conveyor Belts and
Transfer Tower one control. The expected reduction is 90%. There will be another
control around stockyard in the form of boundary walls. These walls reduce the wind
speed and hence results in less dispersion of dust. The expected reduction is 90%.
5 RESULTS AND DISCUSSION:
The concentrations of dust emissions from each type of sources emissions (24-hrs and
annual averaged) from the project sites are given in Table 2 for each of model
scenario. The results indicate that major contribution to the dust emissions are from
the Coal Stock Piles.
Table 2: Incremental Dust Emissions from each Scenario and Modeled Source (µg/m3)
Scenario 1 Scenario 2
Source of Emission 24-Hrs Annual 24-Hrs Annual
Stockyard 1466.19 648.2064 147.8421 65.36139
Transfer Tower and Conveyor Belt (BC1) Mobile Hoppers 0.01595552 0.005389319 0.001595533 0.0005387983
While the commutative impact (concentrations) of the emission from each type of
modeled source for 24-hr averaged and annual averaged emission are give in Table 3
and Table 5 respectively.
Table 3: Cumulative Predicated Incremental Concentrations of PM10 (24 Hrs Avrg,), µg/m3
Scenario-1 (Without Control Measures) Scenario-2 (With Control Measures)
Maximum 35645.18 (14658.17, 13658.42) 1460.053 (14658.17, 13658.42)
Minimum 0.00651 (14266.95, 15374.75) 0.00026 (18179.2, 10225.75)
Avrg 1466.194 147.8425
11Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
Table 4: Cumulative Predicated Incremental Concentrations of PM10 (Annual Avrg, g/m3
Scenario-1 (Without Control Measures) Scenario-2 (With Control Measures)
Maximum 36561.9 (14658.17, 13658.42) 2004.598 (14658.17, 13658.42)
Minimum 0.00023 (13093.28, 15660.8) 1E-05 (12702.05, 15660.8)
Avrg 648.2112 65.36192
Table 4: Particulate Matter Emission from each Scenario Modeled (µg/m 3)
Pollutant Averaging Period Baseline ConcentrationRange
Scenario 1 Scenario 2 SEQS
PM10 24-hour 90-101.1 1466.194 147.8425 150
Annual -- 648.2112 65.36192 120
The spatial distribution of dust emissions and impact areas has been modeled in both
of the scenarios which indicated the 24 hr averaged and annual averaged increment
to the PM10 (dust) levels in the ambient air around the project site. The spatial
distribution contour plots of 24-hrs and Annual averaged for Scenario-1 are shown in
Figure 4 to 5 respectively. Similarly, the contour plots for 24 and Annual averaged for
Scenario-2 are shown in Figure 6 to 7 respectively
6. CONCLUSION:
The study concluded that the proposed control measures effectively decreased
the emissions and the concentrations were predicted well within the limits of SEQS for
24-hrs averaged (150 µg/m3) and annual averaged (120 µg/m3) when the height of
Dust Suppression Boundary Wall and Wind Breaker Shields are of minimum of 15 m..
12Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
Figure 4: Scenario-1; Modeled Spatial Distribution of PM Concentration(Cumulative, 24 Hrs Avrg, )
12Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
Figure 4: Scenario-1; Modeled Spatial Distribution of PM Concentration(Cumulative, 24 Hrs Avrg, )
12Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
Figure 4: Scenario-1; Modeled Spatial Distribution of PM Concentration(Cumulative, 24 Hrs Avrg, )
13Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
Figure 5: Scenario-1: Modeled Spatial Distribution of PM Concentration(Cumulative, Annual Avrg)
13Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
Figure 5: Scenario-1: Modeled Spatial Distribution of PM Concentration(Cumulative, Annual Avrg)
13Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
Figure 5: Scenario-1: Modeled Spatial Distribution of PM Concentration(Cumulative, Annual Avrg)
14Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
Figure 6: Scenario-2: Modeled Spatial Distribution of PM Concentration (24Hrs Avrg)
14Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
Figure 6: Scenario-2: Modeled Spatial Distribution of PM Concentration (24Hrs Avrg)
14Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
Figure 6: Scenario-2: Modeled Spatial Distribution of PM Concentration (24Hrs Avrg)
15Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
Figure 7: Scenario-2; Modeled Spatial Distribution of PM Concentration(Annual Avrg)
15Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
Figure 7: Scenario-2; Modeled Spatial Distribution of PM Concentration(Annual Avrg)
15Pakistan Space Upper Atmosphere Research Commission (SUPARCO)
Figure 7: Scenario-2; Modeled Spatial Distribution of PM Concentration(Annual Avrg)
Annexure–VI Plantation Plan
EIA of Coal Conveying System – Port Qasim, Karachi
NESPAK Page VI-1 July, 2016
Plantation Plan for Coal Conveying System - Port Qasim, Karachi About Two Hundred and Forty (240) plants are to be raised in lieu of twelve (12) in vacant
places most preferably near the proposed project area and ornamental plants are to be planted
in the median where pylon will be installed for coal conveying system. Plants are to be grown,
keeping the distance from plant to plant as 4 meters and also 4 meters between 2 rows of
plants. Enough space or open places are available around the industrial area that is present
near the project site for raising these plants.
It is recommended that 4 to 5 years old plants, grown in the nursery, should be procured for the
purpose. Table 1 Shows the types of trees to be planted in the project area.
Table 1: Types of Trees to be Planted
Sr. No. Local Name Scientific Name
1. Neem Azadiraccta indica
2. Peepal Ficus religiosa
3 Kaner Thevetia nereifolia
4 Amaltas Laburnum anagyroides
5. Gul Mohar Delonix regia
Plant Requirements Number of large sized 4 to 5 years old Plants = 240
Cost The cost of raising 240 plants at length of 4.5 Km has been estimated as Rs. 349,310/-
including price of plants, earthwork, procurement of manures, continued supply of water to
young plants throughout the year and its maintenance for five (5) years.
Break-up of expenditure of 240 plants @ Rs. 500/- per diem is as follows:
Annexure–VI Plantation Plan
EIA of Coal Conveying System – Port Qasim, Karachi
NESPAK Page VI-2 July, 2016
Table 1: Estimated Cost of Plantation of 240 Plants for First Year
Sr. No. Item Quantity Rate Amount (Rs.)
1. Layout 240 plants 2 MD/Av.km 1,000
2. Digging of Pits 2.5 ft. each 2.5x240 =600 cft. 600 cft. 5
MD/Av.km 2,500
3. Cost of plants including 240 No. Rs.450/- plant 1,08,000
4. Cost of planting of plants 240 No. Rs. 10/- plant 2,400
5. Carriage of plants from private nursery to site including loading/unloading
240 No. Rs. 5/- plant 1,200
6. Cost of Manure and Bhall (silt) including carriage 240 plants Lump Sum 2,500.00
8. Hand watering 200 times x 240 = 48,000 plants
48,000 plants (120 MD)
500/MD 60,000
8. Weeding twice 240 x 2 480 no. 2 MD 1,000
9. Reopening of Pits twice (240x2)/cft/pit 480 cft. 2 MD 1,000
10. Unforeseen --- --- 500
Total 180,100
Table 2: Estimated Cost of Plantation of 20% (50) Plants and maintenance for Second Year
Sr. No. Item Quantity Rate Amount (Rs.)
1. Cost of Plants 20% Restocking 48 No. Rs.750/- plant
36,000
2. Cost of planting 48 No. Rs. 10/- plant
480
3. Carriage of plants 48 No. Rs. 5/- plant 240
4. H/watering 50 times with water bowser, one driver and one coolie (240x 50)
12,000 plants (30 MD)
500/MD 15,000
5. Reopening of Pits twice (240x2) 480 cft. 2 MD 1,000
6. Weeding twice 240x2 480 no. 2 MD 1,000
7. Unforeseen --- --- 500
Total 54,220
Annexure–VI Plantation Plan
EIA of Coal Conveying System – Port Qasim, Karachi
NESPAK Page VI-3 July, 2016
Table 3: Estimated Cost of Plantation of 20% (50) Plants and maintenance for Third Year
Sr. No.
Particulars of Work Quantity Rate (Rupees)
Amount (Rs).
1. Restocking of 20% plants
48 No. 50.00 each
2,400
2. Carrying of plants from Nursery to site including loading/ unloading
48 No. Rs. 5/- per plant
240
3. Re-Digging of Pits 20% - 48 No.
48 No. (2 MD)
500/MD 1,000
4. Planting of plants with ball of earth – 48 No.
48 No. (1 MD)
500/MD 500
5. Hand watering 150 times of 240 plants
36000 plants (80 MD)
500/MD 40,000
6. Reopening of pits twice 1 cft per pit
150 cft. (3 MD)
500/MD 1,500
7. Weeding twice 240x2 480 plants (2 MD)
500/MD 1,000
8. Miscellaneous 350 Sub-Total 46,990
Table 4: Estimated Cost of maintaining for Fourth Year
Sr. No.
Particulars of Work Quantity Rate (Rupees)
Amount (Rs).
1. Hand watering 150 times 150x 240
36000 plants (60 MD)
500/MD 30,000
2. Weeding twice 240x2 480 plants (2 MD)
500/MD 1,000
3. Trimming/pruning of plants
240 No. (5 MD)
500/MD 2,500
4. Miscellaneous 500 Sub-Total 34,000
Annexure–VI Plantation Plan
EIA of Coal Conveying System – Port Qasim, Karachi
NESPAK Page VI-4 July, 2016
Table 5: Estimated Cost of maintaining for Fifth Year
Sr. No.
Particulars of Work Quantity Rate (Rupees)
Amount (Rs).
1. Hand watering 150 times 150x 240
36000 plants (60 MD)
500/MD 30,000
2. Weeding twice 240x2 480 plants (2 MD)
500/MD 1,000
3. Trimming/pruning of plants
240 No. (5 MD)
500/MD 2,500
4. Miscellaneous 500 Sub-Total 34,000
Grand Total: 349,310
Cost for raising 240 plants and their
Maintenance for five years = Rs. 349,310/-
Cost for raising one plant and its
Maintenance for five years = Rs.1455/-
ANNEXURE
EIA of Coal Conveying System at Port Qasim, Karachi
NESPAK July, 2016
Annexure-V: EMERGENCY RESPONSE PLAN
Annexure–V Emergency Response Plan EIA of Coal Conveying System – Port Qasim, Karachi
NESPAK Page V-1 July, 2016
EMERGENCY RESPONSE PLAN
1. Introduction
Emergency management can be defined as the organization, coordination and
implementation of a range of measures to prevent, mitigate, respond to, overcome and
recover from the consequences of emergency events affecting the community, its assets
and the environment.
2. Purpose of Plan
This plan intends to provide a framework for safety and security to infrastructure, people and
vehicles. It assigns responsibility to organizations and individuals for carrying out specific
actions at projected times and places in an emergency situation that exceeds the capability
or routine responsibility of any one agency.
The emergency response plan provides guidance to;
Prevent any potential sources causing hazard to the resources during all stages of the
project;
Coordinate between various organizations to take actions in case of emergencies;
Protect people and property in emergencies and disasters;
Develop procedures to respond to the emergencies efficiently;
Identify and ensure availability of personnel, equipment, facilities, supplies, and other
resources for use in order to provide timely and efficient response and recovery
operations; and
Confirm that measures taken in an incident are adequate to recover the affected
resources or further improvements are needed.
3. Planning i. Emergency Response Team A group/team shall be dedicated to identify and control potential emergencies during the
construction and operation of the project. The roles and responsibilities of the group
members shall be clearly defined.
The primary responsibilities of the group are described below:
Annexure–V Emergency Response Plan EIA of Coal Conveying System – Port Qasim, Karachi
NESPAK Page V-2 July, 2016
Identify the potential hazard or risk sources that can lead to emergency situations;
Ensure availability of adequate resources, procedures and communication system to
deal with the identified emergency situations;
Ensure awareness and training of the staff to facilitate implementation of the
emergency response plan;
Maintaining the records of any previous incidents; and
Post-event analysis to bridge the gaps of the existing risk prevention procedures.
The emergency response team shall include but not limited to the following;
1. Team Leader
2. Safety Engineer
3. Reporting officer/Inspector
Team Leader Approve/ modify devised measures to prevent or mitigate the risks associated with
the identified risk sources
Arrange resources for dealing with potential emergencies including, financial,
equipments and personnel required to deal with emergencies.
Assure that the Emergency Response plan is adequate, effective and can be
implemented practically.
Safety Engineer Analyze the Identified risk sources and devise measures to prevent or mitigate the
risks in close consultation with the Team Leader;
Develop and implement the Emergency Response Procedures, in case of the
possible emergencies arise;
Ensure effective internal and external communication; and
Provide regular trainings and arrange drills to make people aware of dealing with
emergencies.
Reporting officer/Inspector Regular inspections of the site, to identify potential risks associated with equipments,
materials and work practices;
Anybody from the site can notify the reporting officer about potential risk and/or near
misses on the site;
Record any identified risks and mitigation measures to control the identified risk; and
Notify the issue and control measures taken thereby to the safety engineer.
Annexure–V Emergency Response Plan EIA of Coal Conveying System – Port Qasim, Karachi
NESPAK Page V-3 July, 2016
The designation, roles and responsibilities of each member shall be clearly defined and
communicated to the employees. An outline of the framework of responsibilities is
presented in the following organizational chart:
ii. Hazard Identification A comprehensive identification and evaluation of the hazards/risks likely to cause an
emergency shall be done by Emergency Response Team (ERT). Major potential
emergencies identified in road projects are as follows:
Structural failure
Disruption of Utility (Power, Water, Telecommunications, Gas, etc)
Accidents
Vehicle accident
Fog
Approvals and Quality Control
Team Leader
Safety Engineer
Reporting officer/Inspector
Identify and minimize risk
sources
• Site inspections • Reported risks/near
miss
Develop Emergency Response
Procedures
Ensure effective communication and trainings
Annexure–V Emergency Response Plan EIA of Coal Conveying System – Port Qasim, Karachi
NESPAK Page V-4 July, 2016
Smoke
Power/equipment failure or Vandalism
Fire
Earthquake
Terrorism including bombing
Disease Outbreak
iii. Prevention and Mitigation
The ERT shall work to eliminate or reduce the impact of identified emergencies and
increasing the resilience of an affected community to recover from the consequences of
such events. These activities include:
Design considerations to control flooding, earthquakes and adequate lightening for
fog etc.;
Regular inspection and maintenance of construction machinery and the structural
integrity;
Review of work schedules based on weather updates; and
Security controls based on political situations.
4. Emergency Preparedness
The ERT shall be prepared with all necessary resources and the personnel’s shall be
trained regularly.
i. Resources
Finance and administration
The financial resources shall be reserved for dealing with any emergencies arising on
site during construction and operation. Responsibilities of the person managing the
resources in case of emergencies shall be clearly defined and the required resources
shall be adequate and updated regularly.
Equipment
All the necessary equipments needed in an event of emergencies shall be made
available, as a minimum, the equipments needed include;
Personal Protective Equipments
Alarms/ Warnings
Annexure–V Emergency Response Plan EIA of Coal Conveying System – Port Qasim, Karachi
NESPAK Page V-5 July, 2016
Fire extinguishers
Crowd control, flashlights, signs, barricades
First Aid Facility
Detection instruments, e.g; personal alarm kits; smoke detection instruments
Tools to fix minor vandalism
Communication
All external and internal communication systems shall be made available. Local
emergency numbers shall be clearly posted and communicated to the personnel
involved in construction and during operation.
The local emergency numbers are given below, which shall be regularly updated.
Emergency Numbers
Service Karachi (021)
1 Ehdi Ambulance (115)- 32413232
2 Emergency Police 15
3 Bomb Disposal 99212646
4 Civil Hospital (casualties) 99215960
5 Fire Brigade 16
Trainings
Personnel shall be made aware of the importance of safety, potential emergencies
and how to respond in case of emergencies. One day training and mock exercise
shall be done to prepare, the personnel to deal with emergencies.
5. Emergency Response
Response includes actions taken to reduce the impacts of an emergency event, and to
limit the threat to life, property and the environment.
The emergencies can be dealt with:
On-Site Management of the situation
Off-site coordination to arrange necessary resources to support the on-site
management
Providing advice and reports of the situation to stakeholders
Annexure–V Emergency Response Plan EIA of Coal Conveying System – Port Qasim, Karachi
NESPAK Page V-6 July, 2016
i. Emergency Response Procedure: Any person can report about an emergency, an on-site worker, an outside agency, or
the public. Circumstances change during the course of an emergency in different
events, thus, the procedure will vary as per the specific situation on ground.
However, a basic action plan to be followed in an emergency is discussed below.
This order of response is applicable to almost any emergency and should be followed
in sequence.
Assess the situation: The most important thing to do in case of emergency is to stay calm and avoid panic.
Assess the situation, the cause and most immediate requirement to control, limit
and/or manage the immediate, ongoing, or further damage.
Immediate control: The most senior person on the scene should take control and contact, or delegate
someone to contact emergency services as posted and communicated by ERT and
inform the reporting officer of ERT and explain the situation. The area of emergency
shall be restricted by barricades, tapes and adequate signage, if and as required.
Protection from further losses: 1. Once the site is restricted, to provide protection and reduce further losses, the
source causing the emergency shall be controlled including equipments,
materials, environment and accident scene from continuing damage or further
hazards to the area and people. e.g: suppress fire, prevent objects from falling,
shut down equipment or utilities, and take other necessary measures as required
depending upon the type of emergency
2. Provide first aid if required or in doing so.
3. Designate people to emergency duties. e.g: assign personnel to guide
emergency services on arrival.
4. Headcount People/personnel to identify any missing persons.
5. People/ personnel shall be directed to safe location.
6. Arrange diversions for the traffic to reduce disturbance to the flow of traffic, if and
as far as possible.
7. Preserve the accident scene until experts mark it safe; only disturb what is
essential to maintain life or relieve human suffering and prevent immediate or
further losses.
Annexure–V Emergency Response Plan EIA of Coal Conveying System – Port Qasim, Karachi
NESPAK Page V-7 July, 2016
ii. Communication: Emergency service providers: The emergency service providers’ needs to be kept informed of the situation. On site,
personnel from the emergency services shall be guided towards the emergency
scene, brief about the event, ongoing and potential hazards and cause(s), if known.
Emergency Response Team and Management: Members of ERT shall be immediately informed and the management shall also be
kept informed.
Public: Timely notifications to public shall be disseminated through electronic and print
media depending upon the requirement and urgency of the emergency so that they
can adopt alternate routes and avoid the hazards associated with the emergency
encountered.
Utilities:
In case of disruption of utilities, the utility control authorities shall be immediately
contacted to control the situation.
6. Recovery:
Emergency affected individuals, communities and infrastructure shall be restored in
terms of emotional, economic, and physical well being including the following as a
minimum:
A detailed analysis and assessment of causes of emergency , extent of damage and
gaps if any, in managing the emergency;
Recovery/replacement of the assets and infrastructure;
Reinstatement of disrupted services;
Road and bridge repairs;
Updation of safety arrangements and Emergency response procedures to ensure
better safety and security in any other arising emergencies.
ANNEXURE
EIA of Coal Conveying System at Port Qasim, Karachi
NESPAK July, 2016
Annexure-VI: PLANTATION PLAN
Annexure–VI Plantation Plan
EIA of Coal Conveying System – Port Qasim, Karachi
NESPAK Page VI-1 July, 2016
Plantation Plan for Coal Conveying System - Port Qasim, Karachi About Two Hundred and Forty (240) plants are to be raised in lieu of twelve (12) in vacant
places most preferably near the proposed project area and ornamental plants are to be planted
in the median where pylon will be installed for coal conveying system. Plants are to be grown,
keeping the distance from plant to plant as 4 meters and also 4 meters between 2 rows of
plants. Enough space or open places are available around the industrial area that is present
near the project site for raising these plants.
It is recommended that 4 to 5 years old plants, grown in the nursery, should be procured for the
purpose. Table 1 Shows the types of trees to be planted in the project area.
Table 1: Types of Trees to be Planted
Sr. No. Local Name Scientific Name
1. Neem Azadiraccta indica
2. Peepal Ficus religiosa
3 Kaner Thevetia nereifolia
4 Amaltas Laburnum anagyroides
5. Gul Mohar Delonix regia
Plant Requirements Number of large sized 4 to 5 years old Plants = 240
Cost The cost of raising 240 plants at length of 4.5 Km has been estimated as Rs. 349,310/-
including price of plants, earthwork, procurement of manures, continued supply of water to
young plants throughout the year and its maintenance for five (5) years.
Break-up of expenditure of 240 plants @ Rs. 500/- per diem is as follows:
Annexure–VI Plantation Plan
EIA of Coal Conveying System – Port Qasim, Karachi
NESPAK Page VI-2 July, 2016
Table 1: Estimated Cost of Plantation of 240 Plants for First Year
Sr. No. Item Quantity Rate Amount (Rs.)
1. Layout 240 plants 2 MD/Av.km 1,000
2. Digging of Pits 2.5 ft. each 2.5x240 =600 cft. 600 cft. 5
MD/Av.km 2,500
3. Cost of plants including 240 No. Rs.450/- plant 1,08,000
4. Cost of planting of plants 240 No. Rs. 10/- plant 2,400
5. Carriage of plants from private nursery to site including loading/unloading
240 No. Rs. 5/- plant 1,200
6. Cost of Manure and Bhall (silt) including carriage 240 plants Lump Sum 2,500.00
8. Hand watering 200 times x 240 = 48,000 plants
48,000 plants (120 MD)
500/MD 60,000
8. Weeding twice 240 x 2 480 no. 2 MD 1,000
9. Reopening of Pits twice (240x2)/cft/pit 480 cft. 2 MD 1,000
10. Unforeseen --- --- 500
Total 180,100
Table 2: Estimated Cost of Plantation of 20% (50) Plants and maintenance for Second Year
Sr. No. Item Quantity Rate Amount (Rs.)
1. Cost of Plants 20% Restocking 48 No. Rs.750/- plant
36,000
2. Cost of planting 48 No. Rs. 10/- plant
480
3. Carriage of plants 48 No. Rs. 5/- plant 240
4. H/watering 50 times with water bowser, one driver and one coolie (240x 50)
12,000 plants (30 MD)
500/MD 15,000
5. Reopening of Pits twice (240x2) 480 cft. 2 MD 1,000
6. Weeding twice 240x2 480 no. 2 MD 1,000
7. Unforeseen --- --- 500
Total 54,220
Annexure–VI Plantation Plan
EIA of Coal Conveying System – Port Qasim, Karachi
NESPAK Page VI-3 July, 2016
Table 3: Estimated Cost of Plantation of 20% (50) Plants and maintenance for Third Year
Sr. No.
Particulars of Work Quantity Rate (Rupees)
Amount (Rs).
1. Restocking of 20% plants
48 No. 50.00 each
2,400
2. Carrying of plants from Nursery to site including loading/ unloading
48 No. Rs. 5/- per plant
240
3. Re-Digging of Pits 20% - 48 No.
48 No. (2 MD)
500/MD 1,000
4. Planting of plants with ball of earth – 48 No.
48 No. (1 MD)
500/MD 500
5. Hand watering 150 times of 240 plants
36000 plants (80 MD)
500/MD 40,000
6. Reopening of pits twice 1 cft per pit
150 cft. (3 MD)
500/MD 1,500
7. Weeding twice 240x2 480 plants (2 MD)
500/MD 1,000
8. Miscellaneous 350 Sub-Total 46,990
Table 4: Estimated Cost of maintaining for Fourth Year
Sr. No.
Particulars of Work Quantity Rate (Rupees)
Amount (Rs).
1. Hand watering 150 times 150x 240
36000 plants (60 MD)
500/MD 30,000
2. Weeding twice 240x2 480 plants (2 MD)
500/MD 1,000
3. Trimming/pruning of plants
240 No. (5 MD)
500/MD 2,500
4. Miscellaneous 500 Sub-Total 34,000
Annexure–VI Plantation Plan
EIA of Coal Conveying System – Port Qasim, Karachi
NESPAK Page VI-4 July, 2016
Table 5: Estimated Cost of maintaining for Fifth Year
Sr. No.
Particulars of Work Quantity Rate (Rupees)
Amount (Rs).
1. Hand watering 150 times 150x 240
36000 plants (60 MD)
500/MD 30,000
2. Weeding twice 240x2 480 plants (2 MD)
500/MD 1,000
3. Trimming/pruning of plants
240 No. (5 MD)
500/MD 2,500
4. Miscellaneous 500 Sub-Total 34,000
Grand Total: 349,310
Cost for raising 240 plants and their
Maintenance for five years = Rs. 349,310/-
Cost for raising one plant and its
Maintenance for five years = Rs.1455/-
ANNEXURE
EIA of Coal Conveying System at Port Qasim, Karachi
NESPAK July, 2016
Annexure-VII: ATTENDANCE SHEET OF SCOPING MEETING