ehah167-136
-
Upload
bogdan-constantin-babii -
Category
Documents
-
view
213 -
download
0
Transcript of ehah167-136
-
7/23/2019 ehah167-136
1/11
The restoration of TynemouthRailway Station canopyJames Miller MA,CEng, FICE,FIStructEConservation Accredited Engineer and Technical Director, Ramboll, London,UK
Tynemouth railway station was built in 1882 and characterises the zenith of the railway age in Britain. The elegant
cast and wrought iron roof is a Grade II* listed structure, an important regional example of its type. It fell into
disrepair in the 1960s through lack of maintenance and by 2008 the larger part of the eastern canopy was in an
appalling state with widespread corrosion. This paper describes the restoration. Basic calculations of capacity were
undertaken prior to survey, to inform observations and the measurements of residual thickness. A comprehensive
survey of defects was carried out and a document outlining the conservation philosophy was compiled, which formed
the basis of the listed building consent. Almost all iron columns were found to have cracked near the top of the
casting. Replacement of columns was considered to be too great a loss of historic fabric and unnecessary; the reasons
for this are discussed. The paper concludes with an appraisal of the projects successes.
1. Introduction
Tynemouth Railway Station is located on the north-east coast
of England, east of Newcastle. When first built in the late
nineteenth century it was a major destination for passengers
travelling to the fine beaches on the Northumberland coastline,
but 100 years later, in the 1980s, it had become a through-
station for short, two-coach trains on the local Tyne and Wear
Metro line, and had deteriorated into an appalling condition.
The station is owned jointly by the private development
company Millhouse Developments Limited and local authority
North Tyneside Council.
Although many schemes for restoration had been proposed, it
was not until 2008 that the funding was assembled. Monies
were contributed by the local authority, central government,
other public bodies and the developer. This paper describes the
history of the project and the details of restoration, inparticular outlining the steps taken to follow good conserva-
tion philosophy in the execution of repairs.
2. History
Tynemouth lies on the north side of the river about 8 km east of
Newcastle. The first railway along the Tyne was opened in 1839,
but did not directly serve Tynemouth itself. The architects and
civil engineers for this early line were father and son, John and
Benjamin Green. The building of the railway was no small task,
and his effort, including the design of an earlier timber-structured
Ouseburn viaduct, earned Benjamin Green the Institution of
Civil Engineers Telford Silver Medal (Leyton, undated).
Tynemouth itself experienced four phases of rail development
over a relatively short period of time, serving both industry and
local community (Wells, 1989). This began in 1847 with an
extension of the Newcastle and Berwick Railway. In 1871 the
countrys Bank Holidays Act was passed, bringing to life the
concept of holidays for all and, in part spurred on by new-
found leisure, there was a wave of excursion development: the
sea piers and airy seaside stations to welcome holiday-makers
to the coasts of England. The current station at Tynemouth
was built in 1882 to designs by regional architect William Bell
and it characterises the zenith of the railway age in Britain.
Tynemouth Station itself was conceived as the jewel in the
necklace, as the rails from the north were linked to the line
arriving east from along the river in the last of the four phases,
the station lying on the curve in the alignment that connected the
two (see Figure 1). The broad, elegant cast and wrought iron
station canopy was built to welcome people from the area
around Newcastle as they discovered the beautiful beaches belowTynemouth Castle and around Whitley Bay. The passenger
station had through-lines to take trains further up the coast, but
two platforms were built for trains that terminated, shuttling to
Newcastle and back.
The heyday of the station was from the time of opening until
the outbreak of the First World War. The line to Tynemouth
Station was one of the first in Britain to be electrified when, in
1904, American-style electric multiple units were purchased to
make the shuttle journey, powered by the new Carville A
superheated steam turbines on the Tyne, which were the
worlds largest at the time. The increase in car ownership afterthe Second World War saw use of the branch line decline;
Tynemouth survived the cull in the 1960s, but the sprawling
station canopy was by now deteriorating rapidly and large
Engineering History and Heritage
Volume 167 Issue EH3
The restoration of Tynemouth Railway
Station canopy
Miller
Proceedings of the Institution of Civil Engineers
Engineering History and Heritage 167 August 2014 Issue EH3
Pages 136146 http://dx.doi.org/10.1680/ehah.14.00002
Paper 1400002
Received 09/01/2014 Accepted 06/05/2014
Published online 30/06/2014
Keywords: rail & bus stations/rehabilitation, reclamation &
renovation
ice | proceedings ICE Publishing: All rights reserved
136
-
7/23/2019 ehah167-136
2/11
parts of the glazing were stripped and replaced with corrugated
asbestos-cement sheeting.
When a new metro system was proposed in the 1970s to link
the wider Newcastle conurbation and outlying towns, the line
through Tynemouth was a natural choice to include as part ofthe network. However, the new two-car trains were a fraction
of the length of the original platforms and, although repairs,
redecoration and re-glazing were carried out to the smaller
western canopy and the centre section of the eastern canopy,
the north and south ends were fenced off from public access
and left to decay, exposed to the coastal weather. Many people
know of the station for the popular flea market that started in
1981, with hundreds browsing on the weekend stalls, but the
revenue from this activity was minimal. A number of planning
applications were put forward through the 1990s to permit
restoration and development, at a time when commercial
enabling development was often put forward as a solution forailing heritage fabric, in effect selling off part of an estate as a
solution to create capital for restoration, but this concept was
met with strong reaction from community and public bodies
alike. None of the solutions met with sufficient local support toproceed, and the canopy decayed further, with dwindling hope
of rescue (North East Civic Trust, 2001).
The station is listed Grade II* because of its significance as an
outstanding example of a regional excursion station, which in
terms of significance puts it in around the top 5% of UK
heritage assets.
Questions over the structural integrity of the bolted connec-
tions to the cantilever sections of the roof, which hang towards
the live railway and 1500 V DC (direct current) overhead lines,
led to erection of unsightly temporary scaffolding supports.This was a clear visual reflection of the very poor state of the
fabric, and in 1988 the structure was put on the English
Heritage at Risk register, emphasising the urgent need to
develop new uses for the site to create sustainable revenue. In
2008 it appeared on the front cover of the Heritage at Risk
review and efforts were redoubled to find a permanent
solution.
A many-stranded funding route became available in 2009,
when the third wave of government Sea Change funding for
coastal settlements and fabric was linked to monies from the
Heritage Lottery Fund, English Heritage and both local
authority and developer to build sufficient reserves to attempt
the restoration of the severely decayed sections of canopy;
these are shown as grids 19 and 1424 in Figure 2. An
essential part of this was also the granting of planning
permission for modest, single-storey, additional retail and
community buildings within the existing station complex, to
enhance revenue. These were required to be of exemplar design
to fit the historic setting. Architect for the new-build
application was Hodder Associates. With provisional funding
now in place, a programme of works to isolate the cost of
works and undertake the project was commissioned.
3. DescriptionTynemouth is an attractive station. Dating from the late
Victorian period, a decade before the introduction of early
steels, the use of cast and wrought material is seen at its best, in
a modest, regional scale. The ironwork is constructed to a
repeating design pattern of cast columns, cast decorated filigree
brackets and wrought lattice valley beams and longitudinal
arch trusses, in plan measuring approximately 150 m625 m.
However, being located on the gentle curve as the railway turns
from east to north and with the canopy varying in width, the
geometry changes quite subtly, creating an elegance in the
overall structure. It is not vast like the magnificent Grade I
listed, cathedral-like station roofs at York or Newcastle,having a free height of columns of just 4 m to the underside of
lattices, a longitudinal span of around 7 m and a roof pitch of
30 . It has the feel of a huge covered market, earning it the
Figure 1. Historic Ordnance Survey plan (1894)
Engineering History and Heritage
Volume 167 Issue EH3
The restoration of Tynemouth
Railway Station canopy
Miller
137
-
7/23/2019 ehah167-136
3/11
nick-name of the Covent Garden of the North, an illusion to
Londons famous Victorian covered flower market, and indeed
the proportions of the space are not unlike the London landmark.
The restoration was confined to the eastern canopy roof, which
is significantly broader than the western, as it was built to
cover the terminating platforms from Newcastle and further up
the coast. The station has four column grids on roughly
concentric curves, offset evenly from the tracks, and 24 grids
that fan perpendicular to the tracks.
By the time the station was built, engineers and architects had
long since come to appreciate the relative structural value of
cast and wrought iron and the economy of fixings. By the
1880s structural bolting had appeared as normal practice butthe cost of bolt fixings would continue to make it unreasonable
for them to be used at works for connecting parts. At
Tynemouth individual components have therefore been riveted
together into structural assemblies, such as lattice beams andarch trusses, and these were bolted together on site in the final
assembly, with structural bolting at all element interfaces, such
as angle purlin to arch truss, arch to valley lattice and lattice to
cast column.
The valley gutters are non-structural, sitting on the lattice
beam, and these are formed as substantial segmental iron
castings, with one standard unit and several specials for
corners, down-pipes and infills. Rainwater was discharged
from these down the unlined, hollow cast columns on two of
the four longitudinal grids: the one nearest the tracks and the
third one back. It is shot sideways from the base by way of acast spigot into the simple vitrified-clay drainage system.
The canopy is built into a single-storey red-brick station
building to the east, currently occupied by small retail shops, a
restaurant, a cafe and a private health clinic. It is these that the
planned building development will augment, to create a site
with a greater, more sustainable foot-fall and revenue.
4. Survey
In 2009 the client appointed Gifford LLP, now Ramboll, to
undertake an initial survey of defects with recommendations
for repair (seeFigures 3and4). This was used as the basis of a
listed building consent, to inform the cost plan and to provide
a basis for tendering the works. Ramboll was also instructed to
oversee structural works during implementation. Heritage
architect for the work was Lathams of Derby.
A brief initial walkover was sufficient to reveal that parts of the
station canopy were in an appalling state. The platforms
beneath the fenced-off areas of the canopy were strewn with
rivet heads from failed fixings and the bays at the southern end
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
23
22
21
20
19
18
17
16
24
Figure 2. Aerial view of station canopies
Figure 3. South end of canopy before restoration
Engineering History and Heritage
Volume 167 Issue EH3
The restoration of Tynemouth
Railway Station canopy
Miller
138
-
7/23/2019 ehah167-136
4/11
were in a particularly parlous condition; many of the diagonal
web flats in the lattice beams had been lost completely to
corrosion. The proximity of the railway and delicate condition
of the fabric meant that health and safety considerations were of
all the more concern. Following discussions with rail operator
Nexus, details of working methods and emergency procedures
were compiled into a report and this was distributed to all active
parties before any surveys were undertaken. A day-long on-site
review of the project was also undertaken prior to work, at
which all staff involved in the project were present, as well as a
director independent from the project team.
It was clear from initial site visits that detailed discussion
would need to be held during the survey with regard to the
extent of replacement of fabric, because of the extent of
corrosion. The conservation philosophy of minimum inter-
vention demands that the conservation engineer understands
what is and is not structurally acceptable: what is a necessary
intervention to restore structural performance and what isover-zealous and destructive to the listed fabric. In order to
establish this, prior to survey an assessment of the required
capacity of critical elements of the fabric was made, in
particular the wrought iron arches and the long-span lattice
trusses. This was done using hand calculation methods. It
provided a basis on which residual section thickness could be
measured for each element. For example, the critical section
thickness of back-to-back angles for end bays of arch trusses
was conservatively taken as a modest 4 mm, compared with
the J in (6.3 mm) original thickness. This meant that
elements with reasonable levels of section loss could be
accepted in certain locations.
The survey was undertaken over a continuous 2-week period
in April 2009. Two members of staff were engaged on site,
lodging locally, with two mobile access platforms and machineoperators at their disposal to provide fingertip access to all
areas. Site visits from the project director and the company
materials specialist helped to calibrate the findings of the work
by comparing the notes being made by each surveyor and
providing independent review.
5. DefectsThe station is located about 800 m from the North Sea and, as
the roof had failed in many places and the ironwork paint
system was almost non-existent in places through failure, it was
inevitable that very high levels of corrosion were found
throughout the structure. This was far more serious at theexposed northern and southern ends, where the ironwork was
unprotected by asbestos-cement sheeting or glazing. The
defects were categorised and listed in the final report using,
as an appendix, a photographic gazetteer. The following
subsections describe the most common types of defect (also
seeFigures 58).
5.1 Lattice trusses
& Heavy corrosion and reduced section of top and bottom
chords to lattice trusses. Corrosion in the bottom chord
with very serious delamination of the wrought plates was
common, because the double angles, facing upwards,
trapped the rain in pockets.
& Heavy corrosion and reduced section or failure of lattice
truss web members. Complete loss of section at the point at
which they met the bottom chord was common at the south
end of the canopy, the iron flat necking to failure.
& Dimensional expansion of lattice truss bottom chords,
sufficient to result in the splitting of plates from angles and
a consequent failure of rivets.
Figure 4. Survey inspection in April 2009
Figure 5. Typical column fracture
Engineering History and Heritage
Volume 167 Issue EH3
The restoration of Tynemouth
Railway Station canopy
Miller
139
-
7/23/2019 ehah167-136
5/11
& Cracking through the section of the filigree cast-iron
brackets below the ends of the lattice trusses, both in
purely decorative parts and the thicker, structural angles,
circles and swags, generally as a result of expansion of
adjacent corroding components.
5.2 Arch trusses
& Heavy corrosion and reduced angle sections in the arch
trusses, in particular on the top chord.
& Delamination of the drilled cheese plate packer at the
connection to lattice trusses, which was drilled to sit over
the top of the rivet heads.
& Delamination of the various gussets and plates sandwiched
between the chord angles.
5.3 Columns
& Horizontal cracking through the columns immediately
above the level of the square impost (plinth or simple
capital) of the casting, in many cases completely splitting
the top from the bottom (see Figure 5). The extent of thiscracking was not immediately apparent from the early
ground-level walkover inspections, but it quickly became
clear from fingertip work that this defect extended to almost
all columns in the canopy. It was a very serious defect to
overcome in order to complete a structurally acceptable
solution in the restoration.
& Cracking through the root of the seating corbel to the arch
trusses, in which the corbels had been jacked away by
corrosion.
& Cracking at lower levels in the columns, for example a
circumferential crack, or one clearly due to impact, of which
there were only a few cases.
The diagnosis of the cause of the column cracking was almost
certainly the jacking of the very heavy corrosion deposits on
the underside of the arch trusses where they rested on the cast
corbel beside the impost, forcing the upper section away from
the lower through the bolted connections between assemblies.
This may well have been exacerbated towards the ends of
the canopy by longitudinal thermal movement, racking the
columns back and forth over successive seasons.
The cracks in the columns at impost level were widespread,
present in almost every column inspected. They posed a
considerable threat to the fabric, as total replacement wouldresult in huge trauma to the listed structure. They also
threatened the viability of the project itself, as the cost of total
replacement would have been prohibitive, as it was unfunded.
Figure 6. Trial works in progress
Figure 7. Disintegration of the cast-iron brackets
Figure 8. Delamination of the flanges of the lattice trusses
Engineering History and Heritage
Volume 167 Issue EH3
The restoration of Tynemouth
Railway Station canopy
Miller
140
-
7/23/2019 ehah167-136
6/11
A risk-based approach was adopted for the inspection offixings. There are no conclusive, reliable methods for assessing
the integrity of bolts and rivets in a structure that exhibits such
extreme levels of corrosion. Therefore the function of each set
of fixings, their location and type were all taken into account in
examining the need for replacement.
Corrosion of bolt fixings was clearly very advanced in places.
Where these passed through the columns it was sometimes
possible to see the shank by looking down from above the
guttering; these had in many places wasted away to a fraction
of original thickness, or to nothing. It was therefore planned to
replace all key bolted connections into or through the columnsregardless of whether the elements would be dismantled or not.
The exception was the connection between arch and lattice
trusses, which having a six-bolt connection had a high
degree of redundancy and in general showed relatively little
sign of corrosion.
Rivets had been falling from the underside of the lattice trusses
over a large area of the canopy, and rivet-heads littered the
platform. As ironwork in the end bays of the station had to be
disassembled and reconstructed, these would be replaced in
entirety. Towards the centre, where rivets were found to have
greater integrity, it was necessary to find a philosophy that
respected the original fabric while ensuring structural capacity,
and one in every three was replaced using bolt equivalents.
The survey report and accompanying drawings (see Figures 9
and10) were accompanied by a report outlining the philosophy
of repair. Together, these documents were submitted for listed
building consent, and their approval was part of the deliberate
effort to achieve as great a body of approved works as possible
before starting works on site.
6. Conservation philosophy
6.1 Trial worksModern conservation philosophy in Britain goes back to the
origin of the UKs Society for the Protection of Ancient Buildings
in 1877 and is based on an assumption of minimum intervention.
This is widely accepted across the world, as conservation thought
has developed through the Treaties of Athens and Venice and,
later in the twentieth century, the Burra Charter (ICOMOS,
1979). In an overseas setting this can still mean the environmental
threats such as seismic activity and extreme storms can demand
structural intervention to offset the risk to fabric. However, the
UK does not suffer from significant seismic activity and so this
threat does not impose an obligation on the conservation engineer
to intervene to enhance seismic resistance.
The temptation for the engineering professional in handling
corroded ironwork is to adopt high levels of replacement for
what are thought to be practical reasons, for example
substituting a complete angle section when only a relatively
small length is seriously corroded. This was indeed the
approach presumed in a document written just before the
project received funding, where it was said that the system (of
ironwork construction) does not favour selective repair as inmasonry or timber construction (North of England Civic
Trust, 2007); in other words, a more extensive reconstruction
would be necessary. However, at Tynemouth this approach
would have resulted in very significant loss of original fabric.
In many places, such as on the corners of arch trusses touching
the gutters, significant corrosion had occurred, but only to
quite limited lengths of each angle component. The suitability
of conducting local, limited repairs needed to be examined and
proved.
A trial project was undertaken at the same time as the survey
work, funded by English Heritage. This was undertaken on acorner bay on the south end and was intended to address the
philosophy of repair. It used a number of alternative solutions
and techniques, as follows.
Figure 9. Structural actions on columns
Engineering History and Heritage
Volume 167 Issue EH3
The restoration of Tynemouth
Railway Station canopy
Miller
141
-
7/23/2019 ehah167-136
7/11
& The badly corroded web flats were cut back and repaired by
both fire-welding wrought iron flats and electric fusion-
welding mild steel flats.
& The rivets were replaced by both hot-riveted mild steel
equivalents and dome-headed, hexagonal, slotted bolts.
& Equivalent modern, metric, mild steel angle sections were
used to substitute for original nineteenth century imperial
wrought iron sizes.
& A repair of the cracked column section was trialled, using
an internal sleeve bonded in place with low-viscosity resin.
The works were inspected by the project team and English
Heritage on completion. The trial project was completed at
a cost of around 30 000. It was a very valuable exercise,
enabling techniques to be proposed, trialled and approved in
advance of the project, providing cost indicators, reducing cost
risk and assisting specification. The conclusions of the trial
works were taken forward in a report that proposed the forms
of repair (Jacques and Miller, 2009). This sought to adhere
closely to established UK conservation practice (BSI, 1998,
2014;English Heritage, 2008).
6.2 Philosophy of column repairs
The issue of column fracture was a great concern. Almost all
the columns exhibited this defect. In effect the tops which
connected to the lattice and arch trusses were separate from
the main shafts below. Regrettably, also, the column repair
that had been undertaken during the trial works could not be
used for columns that acted as rainwater down-pipes, as the
internal sleeve would block the flow of water. So even at the
end of the survey and trial works there was still no universal
solution for repair of the fractured columns.
Both the structural behaviour and the conservation philosophy
for repair of these elements were examined in detail.Engineering practice might have been to dictate total replace-
ment of all such highly fractured column components, where
the defect runs right through the stressed section. However,
there was a strong argument not to replace the columns: the
loss of original fabric would be considerable and dismantling
of the whole structure would cause considerable trauma to the
frame and risk of geometric misfit on reassembly.
The key to solving this conflict was a careful consideration of
the structural actions and load paths. The various actions on
the roof structure were examined and are shown diagrammi-
cally inFigure 9. The possibility of separation of the columnand the way in which tying action and integrity might be
maintained were considered. The problem was resolved by
careful consideration of the tying, ensuring also that the parts
Gridline A Gridline B
1in 3 rivets replaced in top chord
Gridline B-1
Gridline B-2
Gridline B-3
West elevation
West elevation
West elevation
West elevation
West elevation1211
10
10 10
10
1112
13 13
West elevation
Gridline 3 south elevation
Live railway
To be reconstructedA B C D
7 7
5
5
4
7
4
7 7
55
4
55
4
7 7
B-1 B-2 B-3
3 4
1500
1500
1211
10
10 10
10
1112
13 13
3 4
1500
1500
1211
10
10 10
10
1112
13 13
1500
12
10
10 10
12
13 13
3 4
150
0
12
10
10 10
12
13 13
3 4
12
10 10
12
13 13
3 4
Figure 10. Truss elevation showing extent of repairs
Engineering History and Heritage
Volume 167 Issue EH3
The restoration of Tynemouth
Railway Station canopy
Miller
142
-
7/23/2019 ehah167-136
8/11
could be positively located; this placed a greater emphasis onthe integrity of the cast-iron filigree brackets, which provided a
load path for tying action, bolted to both the ironwork above
and the column shaft below.
The issues relating to the columns were considered such an
important matter that a separate report was issued to English
Heritage, outlining the concerns and solution.
6.3 Ironwork materials
The conservation philosophy discussed material choice.
Wrought iron is no longer manufactured in structural
quantities anywhere in the world, and the use of recycled
material would have been inappropriate for the project. The
precedent for mild steel replacement was examined and this
was specified for repairs, either in full replacement or, as in
many areas, where wrought iron was cut out locally and new
material fusion-welded in place.
It was clear that the cast-iron filigree brackets supporting the
lattice trusses had fractured in various tensile failures. This was
particularly important when considering their role in main-
taining continuity around the column fractures. A higher
tensile capacity was required in new elements and spheroidal
graphite iron (SGI) was chosen as a substitute for grey castiron.
After many years of abortive schemes, the project itself was
finally kick-started by the risks posed by bolt failure, which
would have caused catastrophic failure of ironwork over-
hanging the railway. The bolt specification was critical. There
was little debate over the proposed use of stainless steel
replacement bolts. Hard nylon electrical isolation inserts were
used to prevent bi-metallic corrosion. This meant that bolt
sizes were 2 mm smaller than original, to fit inside the inserts,
which was compensated for by use of a higher bolt grade. Rivet
replacements were dome-headed bolts, not hot-riveted mildsteel studs.
7. Specification
The standard materials and workmanship specification used
on building works in the UK is in the National Building
Specification (NBS). In the case of the ironwork restoration,
virtually no part of the NBS was relevant and a new
specification section was written for the ironworks.
Elevation drawings for the repairs on each grid line were
produced from the survey, on which competitive tenders were
based. The value of a good written specification is that it can beused to control both work that appears on the drawings and
other unforeseen repairs, and this is particularly important on
an historic restoration.
Key features of the works specification are
& the requirement for a photographic record prior to works
& a clause defining the experience of the ironwork subcon-
tractors on historic fabric
& a clause requiring the names and brief experience of all
operatives working on the project to be submitted
& details of how the careful dismantling of the canopy should
be undertaken
& requirements for a full dimensional survey of the structure
prior to dismantling
& a diagram defining which areas may be dismantled and
which may not, which had been previously agreed withEnglish Heritage through listed building consent
& requirements for marking and recording dismantled com-
ponents
& precise details of bolt substitutions and grades
& precise details of mild steel section sizes for substitution of
imperial with metric sizes, which, again, had previously
been agreed through listed building consent
& a clause defining which direction rivet substitutes should
face.
The areas that could or should be dismantled were carefully
defined, as the greater the area of canopy taken down, the
greater would be the trauma on the fabric and potential loss of
the original. A diagram binding the contractor to certain limits
and areas was included in documentation. The bills of
quantities required the contractor to establish rates for most
types of repair, including the re-casting of iron elements,
showing the mould and unit prices separately. In addition to
other contractual matters, there were clauses describing the
risk of working close to the live overhead lines of the railway
and the interface with rail authorities.
The corrosion protection comprised a zinc-rich epoxy primer
designed for use after wet blasting, zinc-rich epoxy undercoats
and an acrylic urethane top coat.
8. Site works
The project was advertised through the OJEU (Official Journal
of the European Union) process. Works started in March 2011
and were completed in April 2012 (see Figures 1114). The
final contract valuation was 3.9 million. Main contractor for
the works was Mansell Construction Services Limited from
Gateshead and their chosen ironwork repair subcontractor was
Eura Conservation Limited from Telford.
The dismantling proceeded well. Components were marked
with two tags, so that if one marker was lost, another wouldremain attached. The contractor opted to dismantle to the full
extent of permitted areas, and two additional grids were also
agreed in conjunction with English Heritage.
Engineering History and Heritage
Volume 167 Issue EH3
The restoration of Tynemouth
Railway Station canopy
Miller
143
-
7/23/2019 ehah167-136
9/11
The cast-iron filigree brackets had been carefully inspected
twice to specify the number of replacements. However, as
disassembly proceeded, many others simply fell to pieces as
either the rapid change of stress caused fracture or the release
of load revealed pre-existing defects. This led to a higher level
of replacement, with 49 new brackets out of a total of 86 within
the works area.
The cleaning of paint from ironwork was achieved using a ultra-
high-pressure system, with water jetted at about 32 000 psi
(220.6 N/mm2
) through a spinning head. No blast mediumwas used. Water usage was relatively low, about 1015 l/min
depending on the nozzle size.
The contractor reported that one column visibly moved on
removal of the interconnecting ironwork as the foundation
settled sideways, and this led to a concern that the latticework
would no longer fit onto the columns on re-erection.
Thankfully this proved unfounded and reassembly proceeded
remarkably smoothly.
It had not been possible to inspect the cast-iron gutters in detail
during the survey phase. These were deep channels laid flatbetween the down-pipe columns, and a fall for rainwater
appeared to have been created by compacting burnt coal ash in
the bottom of the units. This sulfurous material had both
Figure 11. Reconstruction of lattice truss in works
Figure 12. Fettling of new SGI filigree brackets
Figure 13. Corrosion of the gutter resulting from sulfurous
deposits
Engineering History and Heritage
Volume 167 Issue EH3
The restoration of Tynemouth
Railway Station canopy
Miller
144
-
7/23/2019 ehah167-136
10/11
caused and masked the extent of corrosion in the base
(Figure 13), and a significant number of sections had to be
either re-cast or repairs made when they were dismantled and
inspected in the workshop.
9. Conclusions
This was a successful project, delivered on time, to budget, with
good working arrangements between parties and above all
with appropriate levels of historic intervention.
Key to the success of the project were the following factors.
& The processes gave time for the effect of each causal activity
to be examined: for example, the detailed survey allowed a
suite of repairs to be proposed and critiqued, rather than
trying to work details out on site without prior approval.
& The trial works allowed experimentation in types of repairin advance of the works, agreement between parties and
better establishing of costs for the works.
& The survey was undertaken in sufficient detail to allow
every ironwork repair to be scheduled, even if some changes
were made during the site works.
& A clear conservation philosophy was put forward at the time
of the application under UK heritage protection legislation.
& A thorough engineering review was undertaken on site,
involving staff with the highest levels of historic and
materials experience, at an early stage in the project.
& A pro-active contractor was chosen for the project, and the
client and contractor were willing to talk openly about costconcerns and programme issues.
& The contractor chose an ironwork subcontractor with good
experience in historic repair; this was due in part to the
wording of the specification and emphasis on quality at
tender interview.
The result is a significant ironwork restoration project where
the repairs are distinct to the trained eye, while the canopy
retains a unity as a whole (Figure 15). Defects are still visible,
for example, some brackets remain cracked and many
wrought iron sections are thinned by corrosion. However,the overall level of intervention is commensurate with the
structural performance of the fabric: a balance has been
achieved.
Throughout the site phase, the team was mindful of the
preceding many decades of project failure, through lack of
community agreement and lack of funding. There was a very
strong will to conclude the work successfully. The result is an
ironwork restoration that follows contemporary conservation
philosophy and in which everyone involved has taken
considerable pride.
REFERENCES
BSI (1998) BS 7913:1998: Guide to the principles of the
conservation of historic buildings. BSI, London, UK.
BSI (2014) BS 7913:2013: Guide to the conservation of historic
buildings. BSI, London, UK.
English Heritage (2008) Conservation Principles, Policies and
Guidance. English Heritage, London, UK.
ICOMOS (International Council on Monuments and Sites) (1979)
The Burra Charter, 1979 edition and subsequent revisions.
ICOMOS, Burwood, Victoria, Australia.
Jacques S and Miller JD (2009) Tynemouth Station Newcastle,
Conservation Philosophy for Structural Repairs. Gifford,now Ramboll UK Ltd, London, UK.
Leyton A(undated)The Opening of the First Newcastle to North
Shields Railway. Archive of the Friends of Tynemouth
Figure 14. Reassembly in progress in September 2011
Figure 15. South end of the restored canopy
Engineering History and Heritage
Volume 167 Issue EH3
The restoration of Tynemouth
Railway Station canopy
Miller
145
-
7/23/2019 ehah167-136
11/11
Station, by kind permission of Ylana First (unpublishedarticle).
North East Civic Trust (2001) Tynemouth Station Conservation
Strategy. North East Civic Trust, Newcastle upon Tyne,
UK.
North of England Civic Trust (2007) Tynemouth Station OptionsAppraisal, Final Report. North of England Civic Trust,
Newcastle upon Tyne, UK.
Wells JA (1989) The Blyth and Tyne Branch Volume II 1874
1989. Northumberland County Library, UK.
WHAT DO YOU THINK?
To discuss this paper, please email up to 500 words to the
editor at [email protected]. Your contribution will be
forwarded to the author(s) for a reply and, if considered
appropriate by the editorial panel, will be published as
discussion in a future issue of the journal.
Proceedingsjournals rely entirely on contributions sent in
by civil engineering professionals, academics and stu-
dents. Papers should be 20005000 words long (briefing
papers should be 10002000 words long), with adequateillustrations and references. You can submit your paper
online via www.icevirtuallibrary.com/content/journals,
where you will also find detailed author guidelines.
Engineering History and Heritage
Volume 167 Issue EH3
The restoration of Tynemouth
Railway Station canopy
Miller
146