EGLINTON CROSSTOWNEglinton-Mount Pleasant Construction Liaison CommitteeOctober 10, 2017
![Page 2: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/2.jpg)
2
Agenda
• Eglinton Station Update
• Mount Pleasant Station Update
![Page 3: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/3.jpg)
3
Eglinton Station Update
![Page 4: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/4.jpg)
4
Eglinton Station Updates
Complete
Demolition of the Salvation Army Community Church
Demolition of the abandoned TTC bus depot
Wet utilities stages 1-4
THESL 1a, 1b
North and east pedestrian tunnels closure
Shoring at Salvation Army site
Underground pedestrian tunnel closure from TTC subway to Riocan Centre
Fall/Winter 2017
• Shoring along the south side of Eglinton (three rigs now in operation)
• Toronto Hydro relocation 2b (Hillsdale Ave, Yonge St)
• Shoring along the north side of Eglinton
• Toronto Hydro relocation 2a (Eglinton Ave East)
![Page 5: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/5.jpg)
5
Eglinton Station Shoring Phase 1 – Ongoing
![Page 6: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/6.jpg)
6
Eglinton Station – West Tunnel Closure – September
![Page 7: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/7.jpg)
7
Eglinton Station Shoring Phase 2 – October/November
![Page 8: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/8.jpg)
8
Eglinton Station Shoring Phase 3
![Page 9: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/9.jpg)
9
Eglinton Station Shoring Phase 4
![Page 10: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/10.jpg)
10
Construction Progress Picture
JET GROUTING BEGAN AT YONGE-EGLINTON
![Page 11: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/11.jpg)
11
Mount Pleasant Station Update
![Page 12: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/12.jpg)
12
Mount Pleasant Station Construction Update
Fall 2017
• Continue hydro utilities relocation
• Continue piling at the north side of Eglinton Ave E
• Storm sewer installation on the south side of Eglinton Ave E
• Watermain and sanitary sewer realignment work for piling
• Sewer relocation at the Secondary Entrance/801 Mt Pleasant Rd
![Page 13: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/13.jpg)
13
Current Construction Staging
NO TURNS IN ALL DIRECTIONSMT PLEASANT &
EGLINTON
![Page 14: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/14.jpg)
Storm Sewer Installation
• Installation of new storm sewer infrastructure is required to accommodate
construction of Mount Pleasant Station
• To accommodate the on-going piling operation and minimize the disruption to
traffic, the work will be performed using a micro-tunneling methodology
• One launch shaft is required to send the tunnel boring machine (TBM) and pipes,
and one receiving shaft is required to extract the TBM
• The TBM will operate 24/7 during the tunneling operation – approx. 2 weeks
• Lane closures and pedestrian rerouting will be in effect
• Taunton Road will be closed at Eglinton Ave E for eight (8) weeks while the
launch shaft is in place
![Page 15: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/15.jpg)
Schedule – Storm Sewer Installation
• Launch Shaft (at Taunton Road):
Beginning as early as October 11 for approximately eight (8) weeks
• Receiving Shaft (east of Brownlow Avenue):
Beginning as early as early November 15 for approximately four (4) weeks
• Work Sequence:
– Implement traffic staging for launch shaft
– Construction of the launch shaft and mobilize TBM
– Tunneling/pipe installation - 24 hours for approximately two (2) weeks
– Implement traffic staging for receiving shaft
– Construction of receiving shaft
– Extraction of the TBM
![Page 16: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/16.jpg)
Storm Sewer Installation Map
Part 1 - Beginning as early as October (8 weeks)Part 2 – Beginning as early as November 15 (4 weeks)
PART 1
PART 2
![Page 17: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/17.jpg)
17
Mount Pleasant Station Concept Aerial View
Main Entrance
Secondary Entrance
*60% rendering
![Page 18: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/18.jpg)
18
Mount Pleasant Station Main Entrance
*60% rendering
![Page 19: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/19.jpg)
19
Mount Pleasant Station Secondary Entrance
*60% rendering
![Page 20: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/20.jpg)
Mount Pleasant Station Construction Progress
20
DRILLINGSTREET
SWEEPING
![Page 21: Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October 2017](https://reader033.fdocuments.in/reader033/viewer/2022052117/5a64e5747f8b9ac21c8b78a5/html5/thumbnails/21.jpg)
Mount Pleasant Station Construction Progress
21
DRILL MOVE AERIAL VIEW