PURPOSE
2
Establish the next “pipeline” of Regional Priority Projects
iiiiiiiii
Round 1 Projects
3
HRTPO Actions
• Direct HRTPO staff to work with TTAC to review and identify projects in the 2040 LRTP that could be considered as Round 2 Hampton Roads Regional Priority Projects. Round 1 projects will not be impacted in terms of priority or funding by the work done in Round 2.
HRTPO Board Action from May 18, 2017 Meeting:
• Review the 2040 LRTP projects and submit candidates for Round 2 Hampton Roads Regional Priority Projects.
• HRTPO staff will work with the LRTP Subcommittee to review Round 2 candidate projects and develop a list of project recommendations for consideration by TTAC and the HRTPO Board.
TTAC Action from June 7, 2017 Meeting:
4
LRTP Actions
Directed HRTPO staff to compile a list of candidate projects for Round 2 of the Regional Priority Projects to include:
• Projects collected to date (submitted from regional stakeholders)
• 2040 LRTP projects including the vision plan
• Additional projects submitted by localities
Initial multi-tier project screening process based on:
• Guiding Principles from Round 1
• Submitted 2040 prioritization data
• Regional Travel Demand Model
36 Candidate Projects collected and analyzed
• Additional request from 12/19/17 LRTP Meeting: evaluate Air Terminal Interchange (ATI) with updated project cost estimate
5
LRTP Subcommittee Actions Meetings: 7/12/17, 9/6/17, 12/19/17
Round 1 Projects
Regional Priority Projects should meet the following:
Consistent with HB2313 Legislation
Meet Regional Project Cost Threshold of $100 Million
Included in the HRTPO Board Approved Long-Range Transportation Plan OR
Supported by HRTPO Resolutions
Guiding Principles for selection of Regional Priority Projects Round 1 (October 2013):
6
Project Screening
Screen #1
• Screening based on 2040 LRTP and other relevant factors
Screen #2
• Estimated project cost > $100 Million
Screen #3
• Regional congestion
• “HRTAC shall give priority to those projects that are expected to provide the greatest impact on reducing congestion for the greatest number of citizens” and “shall ensure that the moneys “shall be used for such construction projects.”
7
Project Screening
8
Assumptions for Screen #3
• Screen #3A: Applied congestion analysis from Project Utility component of HRTPO Project Prioritization Tool
• Screening Threshold: 20 pts (out of 30 pts)
• ‘Study’ indicated for those projects without sufficient data to score and currently being analyzed as part of a regional study
• Screen #3B: Used Regional Travel Demand Model to develop Origin-Destination Demand Maps (to evaluate regional congestion impact of project)
Other Assumptions
• Candidate Projects currently under regional study automatically retained (will be further analyzed once study is completed)
Project Screening
9
Highway/ Bridge/Tunnel
Interchanges
% Reduction between Existing and Future Volume/Capacity Ratios
Existing Queue Conditions
Existing Peak Period Congestion (projects with TTI data)
Queue Improvements
Existing Peak Period Level of Service (projects with no INRIX Data)
Number of Movements Added or Improved
Impact to Nearby Roadway
Project Utility: Scoring Criteria for Congestion
Project Screening
10
Candidate Project Name From To Jurisdiction (Primary)
CONGESTION LEVEL TOTAL
I-64/I-264 Interchange - Phase 3 (RPP Round 1) N/A N/A Multi-jurisdictional N/A
I-64 Peninsula Widening Bland Blvd New Kent County Line Multi-jurisdictional 26.89
I-64 Peninsula - Segment 4 Route 199 West of Williamsburg New Kent County Line Multi-jurisdictional
I-64 Peninsula (8-Lane Option, Segment 1) Jefferson Ave Exit 247 (Yorktown) Multi-jurisdictional
I-264/Independence Blvd Interchange Improvements N/A N/A Virginia Beach 26.00
I-664/MMMBT Bowers Hill Hampton Coliseum Multi-jurisdictional 23.11
I-64 at Denbigh Blvd (Rte 173) N/A N/A Newport News 21.00
I-264/Rosemont Rd Interchange Improvements N/A N/A Virginia Beach 21.00
I-564/I-664 Connector (Patriots Crossing) I-664 I-564 Multi-jurisdictional 20.18
I-264 (entire corridor with recommended interchange improvements) I-264 at Military Hwy Rosemont Rd Multi-jurisdictional 20.00
I-264 Preferred Alternative Independence Blvd Rosemont Rd Virginia Beach
I-264/Military Rd Interchange Improvements N/A N/A Norfolk
Brambleton Ave Midtown Tunnel I-264 Norfolk 20.00
G.W. Mem Hwy (US 17) Dare Rd Denbigh Blvd (Rte 173) York County 20.00
G.W. Mem Hwy (US 17) Denbigh Blvd (Rte 173) Fort Eustis Blvd (Rte 105) York County
G.W. Mem Hwy (US 17) Fort Eustis Blvd (Rte 105) Coleman Bridge York County
I-64/I-464 Interchange Improvements N/A N/A Chesapeake N/A
US 460/58/13 (8-Lane Option) Bowers Hill Suffolk Bypass Multi-jurisdictional N/A
Route 164 I-664 Midtown Tunnel Multi-jurisdictional N/A
US Route 58 Corridor US 460/58/13 Connector Greensville CL Multi-jurisdictional N/A
I-64 at N. King St N/A N/A Hampton 18.50
Holland Rd Rosemont Rd Independence Blvd Virginia Beach 17.21
Warwick Blvd Nettles Dr Fort Eustis Blvd Newport News 16.10
Route 17 Corridor (total) Whippingham Pkwy/ / Harbor Point Ln Chesapeake CL Multi-jurisdictional 10.00
Bridge Rd (US 17) Mills Godwin Bridge Chesapeake CL Suffolk 10.00
Mills Godwin Bridge Quail Hollow Waterview Rd Suffolk 10.00
Bridge Rd (US 17) Mills Godwin Bridge Isle of Wight CL Suffolk 7.49
US 17/Carrollton Blvd (part of Route 17 corridor) End of Chuckatuck Creek Bridge Whippingham Pkwy/ / Harbor Point Ln Isle of Wight 5.43
J. Clyde Morris Blvd / G.W. Hwy (US 17) Newport News CL 1.27 mi South of Rte 620 (Lakeside Dr/ Oriana Rd)
York County 14.78
Suffolk/US 58 Bypass Terminus west of SPSA landfill/ HR Executive Airport
US 460 Interchange Suffolk 10.00
G.W. Mem Hwy (US 17) 1 mi North of Coleman Bridge Main St (@ Walmart) Gloucester 10.00
I-64 at Lasalle Ave I-64 WB Lasalle Ave Hampton 9.75
Craney Island Rd VA 164 and Median Rail Craney Island Marine Terminal Portsmouth 7.20
Congestion Screening Threshold: 20 Points
Project Screening
11
Screen #3B: Origin-Destination Maps
Project Screening
12
Screen #3B: Origin-Destination Maps
Project Screening
13
Screen #3B: Origin-Destination Maps
Project Screening
14
Screen #3B: Origin-Destination Maps
Project Screening
15
Screen #3B: Origin-Destination Maps
Project Screening
16
Candidate Round 2 Regional Priority Project
Screen 1 (2040 LRTP
Prioritization Factors/
Regionalism)
Screen 2 (Project Cost >
$100M)
Screen 3A (Congestion Threshold)
Screen 3B (Regional
Congestion) Comments
I-64/I-464 Interchange Improvements Yes Yes Yes Associated with I-64 Southside/High-Rise Bridge Design-Build Project
I-564/I-664 Connector (Patriots Crossing) Yes Yes Yes Yes Regional Connectors Study
I-64/I-264 Phase 3 - Round 1 Regional Priority Project (construction recommendations from ongoing study of remaining movements from Round 1)
N/A N/A N/A N/A RPP Round 1 project
I-264/Military Highway Interchange Improvements Yes Yes Yes Yes I-264 Corridor Project
Route 164 Widening (I-664 to Midtown Tunnel) Yes Yes Study Yes Regional Connectors Study
US Route 58 Corridor Yes Study Yes US 58 Study
I-64/Denbigh Interchange Yes Yes Yes N/A Need IJR
I-664 Widening/MMMBT (Bowers Hill to Hampton Coliseum) Yes Yes Yes Yes Regional Connectors Study
I-64 Peninsula Widening to 8 Lanes - Segment 1 (Jefferson Ave to Exit 247/Yorktown)
Yes Yes Yes Yes
I-64 Peninsula Widening - Segment 4 (Rt 199 to James City/New Kent County line)
Yes Yes Yes Yes
Entire I-264 Corridor from Military Hwy to Rosemont Rd (including adding capacity between Independence Blvd and Rosemont Rd and interchanges along corridor)
Yes Yes Yes Yes I-264 Corridor Project
I-264 Widening from Independence Blvd to Rosemont Rd Yes Yes Yes Yes
I-264/Independence Interchange Yes Yes Yes Yes I-264 Corridor Project
I-264 at Rosemont Rd Interchange Yes Yes Yes Yes I-264 Corridor Project
US 460/58/13 Connector 8-Lane Option (Bowers Hill to US 58 Bypass) Yes Yes Study Yes US 460/58/13 Connector Study
DRAFT Scores
17
Assumptions for Project Prioritization Scores
• Used Current Year dollar estimate (as opposed to Year of Expenditure)
• Updated information where applicable for previously scored projects
• Regional studies
DRAFT Scores
18
DRAFT scores – not in priority order Candidate Round 2 Regional Priority Project
Estimated
Planning Level
Project Cost,
Current Year $ (in
Millions)
Screen 1
(2040 LRTP
Prioritization
Factors/
Regionalism)
Screen 2
(Project Cost
> $100M)
Screen 3A
(Congestion
Threshold:
20pts)
Screen 3B
(Regional
Congestion)
DRAFT Project
Utility Score
(100 pts)
DRAFT
Economic
Vitality Score
(100 pts)
DRAFT Project
Viability Score
(100 pts)
DRAFT Round
2 RPP Score
(Max 300 pts)
Comments
I-64/I-264 Phase 3 - Round 1 Regional Priority Project
(construction recommendations from ongoing study of remaining movements from Round 1)N/A N/A N/A N/A N/A N/A N/A N/A N/A
- Round 1 Regional Priority Project
- Ongoing HRTAC Funded Study
I-64 Peninsula Widening
I-64 Peninsula Widening - Segment 4 (Rt 199 to James City/New Kent County line) $300 Yes Yes Yes Yes 82 85 25 192
- congestion stats updated
- project cost updated
- updated viability (in LRTP as study, project design, env. Decision)
I-64 Peninsula Widening to 8 Lanes - Segment 1 (Jefferson Ave to Exit 247/Yorktown) $500 Yes Yes Yes 80 85 25 190
- congestion stats updated
- project cost updated
- updated viability (in LRTP as study, project design, env. Decision)
I-664 Widening/MMMBT (Bowers Hill to Hampton Coliseum) $4,000 Yes Yes Yes 79 95 15 189- Regional Connectors Study (ongoing HRTAC Funded Study)
- project cost estimate HRCS SEIS
I-264 Corridor Widening and Interchange Improvements
I-264/Independence Blvd Interchange $466 Yes Yes Yes Yes 79 90 10 179
- project cost updated (I-264 Corridor Study, 2016)
- Economic Vitality updated (increased opportunity)
- Project Viability updated (LRTP study)
Entire I-264 Corridor from Military Hwy to Rosemont Rd (including adding capacity between
Independence Blvd and Rosemont Rd and interchanges along corridor)$2,400 76 85 3 164
- I-264 Corridor Project (all segment widening and interchange
improvements)
- cost estimate I-264 Corridor Study, 2016
I-264/Military Highway Interchange $100 Yes Yes Yes Yes 80 63 8 151- I-264 Corridor Project
- cost estimate I-264 Corridor Study, 2016
I-264 at Rosemont Rd Interchange $460 Yes Yes Yes Yes 69 68 10 147
- project cost updated (I-264 Corridor Study, 2016)
- Economic Vitality updated (increased opportunity)
- Project Viability updated (LRTP study)
I-264 Widening from Independence Blvd to Rosemont Rd $277 Yes Yes Yes 71 72 3 146- I-264 Corridor Project (Preferred Alternative from I-264 Corridor Study)
- cost estimate I-264 Corridor Study, 2016
I-64/Denbigh Interchange $350 Yes Yes Yes N/A 76 95 5 176- project cost updated
- project Viability updated (LRTP study, need IJR)
I-564/I-664 Connector (Patriots Crossing) $4,200 Yes Yes Yes 58 100 15 173- Regional Connectors Study (on going HRTAC Funded Study)
- project cost estimate HRCS SEIS
I-64/I-464 Interchange Improvements $347 Yes Yes Yes 71 92 0 163 - Associated with I-64 Southside/High-Rise Bridge Design-Build Project
US 460/58/13 Connector 8-Lane Option (Bowers Hill to US 58 Bypass) $590 Yes Yes Study Yes 62 35 13 110
- ongoing HRTAC Funded Study
- project cost updated
- Project Viability updated (LRTP study, env process underway)
Route 164 Widening (I-664 to Midtown Tunnel) $195 Yes Yes Study Yes 67 29 8 104- Regional Connectors Study (ongoing HRTAC Funded Study)
- project cost estimate HRCS SEIS
US Route 58 Corridor Unknown Yes Study Yes N/A - US 58 Study
Recommended Action
• Recommend HRTPO Board consideration of the recommended list of potential Round 2 Regional Priority Projects
19
Next Steps
LRTP Subcommittee Request
• Evaluate Air Terminal Interchange (ATI) as Candidate Project (with updated project cost estimate)
January HRTPO Board
• Further direction from Board
20