Effects of Scheduling Practices on Project Sucess
Transcript of Effects of Scheduling Practices on Project Sucess
Effect of Scheduling Practices on Project Success
By Andrew Griffith, Ph.D., P.E., PMP Independent Project Analysis, Inc.
I. Presentation Objectives
A. Provide data that you can use to help justify the investment in project scheduling How?
B. Present the results of an Independent Project Analysis, Inc. research study
1. Demonstrates a measurable link between scheduling practices and project outcome success
2. Based on data from actual projects
METHODOLOGY
II. Independent Project Analysis, Inc. A. Project management research and consulting company based in Ashburn, Virginia
B. Capital project benchmarking
1. Project system benchmarking
2. Individual project evaluations
3. Project system monitoring
C. IPA approach is based on extensive, detailed, and robust databases
III. Characteristics of the IPA Process Plants Database
A. Over 7,000 capital projects from a wide range of industries
B. Over 200 companies worldwide
C. Quite detailed: up to 2,000 factors per project
D. Includes all phases of the project life-cycle, from R&D through operations
Effect of Scheduling Practices on Project Success By Andrew Griffith, Ph.D., P.E., PMP Independent Project Analysis, Inc.
PMI College of Scheduling Page 2
Topic of the Month – April 2005
E. All project types covered: greenfield to revamp
F. New projects added constantly
IV. Application of the IPA Methodology
Benchmarking
IPA
Databases
Project
Evaluations
Project System
Monitoring
Contingencies
Schedule
Histories
Cost
Histories
Project
Definition Technical
Characteri
i
Management
Strategies
Performances
Effect of Scheduling Practices on Project Success By Andrew Griffith, Ph.D., P.E., PMP Independent Project Analysis, Inc.
PMI College of Scheduling Page 3
Topic of the Month – April 2005
V. IPA Approach: Linking Inputs and Outputs
VI. Research Hypothesis
There is a positive and significant relationship between
scheduling practices used early in the project life-cycle and the
FEL Technical
Difficulty
Project
Management
Project
Practices
Cost Schedule Safety Operational
Performance
Inputs That Affect
ParametricStatistical
Techniques
Performance Outputs
Effect of Scheduling Practices on Project Success By Andrew Griffith, Ph.D., P.E., PMP Independent Project Analysis, Inc.
PMI College of Scheduling Page 4
Topic of the Month – April 2005
ultimate success of the project.
VII. Scheduling Practices Data A. Collected during every project interview
B. Measures characteristics of the project schedule
C. Anchored at the time of project authorization for all projects in the study
D. Validated with electronic schedule files and hard copy printouts
VIII. Project Outcome Performance Metrics A. Measure relative performance for a wide range of outcome metrics - not just one success measure
B. Based on data collected after mechanical completion and startup
C. Derived using parametric statistical techniques
D. Normalized based on project characteristics, location, currency, escalation, etc.
E. Includes both predictability and absolute metrics
IX. Predictability vs. Absolute Metrics
Predictability Metric Absolute Metric
Outcome performance relative to estimated performance
Outcome performance relative to industry average for comparable projects
Based on actual performance of project vs. the estimated performance
Based on performance vs. Industry average - derived using statistical models
Deviations are not normalized for project characteristics
Models normalize for project characteristics
Reported as a percent deviation from the estimated performance
Reported as an index with Industry average set to 1.0
Cost growth & schedule slip Cost index & schedule index
Effect of Scheduling Practices on Project Success By Andrew Griffith, Ph.D., P.E., PMP Independent Project Analysis, Inc.
PMI College of Scheduling Page 5
Topic of the Month – April 2005
X. Approach A. Developed sample database
1. Project scheduling practices
2. Outcome performance metrics
3. Other project practices and characteristics
B. Applied statistical tests
C. Controlled for other project characteristics
D. Interpreted the results and formed conclusions
XI. Sample Characteristics
Characteristic Study Sample
Number of Projects 494 completed projects
Number of companies represented 59 different owner organizations
Industries All industries covered by IPA database
Project locations Worldwide locations
Project types All project types: Greenfield to revamp
Project sizes Average estimated cost: $24MM ($100K to almost $1B)
Effect of Scheduling Practices on Project Success By Andrew Griffith, Ph.D., P.E., PMP Independent Project Analysis, Inc.
PMI College of Scheduling Page 6
Topic of the Month – April 2005
ANALYSIS
XII. Scheduling Practices That Drive Better Project Outcome Performance A. Integration of all project phases into a single schedule
B. Application of CPM techniques
C. Resource-loading
D. Review by core project team
XIII. Integrated Schedules A. Integrates all project phases into a single master schedule
1. Definition, detailed engineering, procurement, construction, shutdown/turnaround, and commissioning and startup
B. Only 33% include all applicable project phases
1. Many missing FEL, shutdown/turnaround, and/or commissioning and startup
XIV. Integrated Schedules - Correlated With Better Cost Performance
0.7
0.8
0.9
1.0
1.1
1.2
1.3Integrated Schedule Not Integrated
Cos
t Ind
ex(A
ctua
l / In
dust
ry B
ench
mar
k)
pr < 0.02 +1 Std.
-1 Std.Mean
Effect of Scheduling Practices on Project Success By Andrew Griffith, Ph.D., P.E., PMP Independent Project Analysis, Inc.
PMI College of Scheduling Page 7
Topic of the Month – April 2005
XV. Integrated Schedules - Also Correlated With Less Schedule Slip
XVI. Based on CPM A. Is the project schedule based on the Critical Path Method (CPM)?
1. Activities networked together
2. Activity start and finish dates based on network calculations
3. Critical path and activity float defined
B. Less than 50% of schedules in the sample were based on CPM
XVII. Use of CPM Correlated with Less Cost Growth
XVIII. Use of CPM Also Correlated with Less Schedule Slip
-40%
-20%
0%
20%
40%
60%
80%
100%Integrated Schedule Not Integrated
Perc
ent S
ched
ule
Slip
(Act
ual /
Pla
nned
Dur
atio
n)
-30%
-20%
-10%
0%
10%
20%
30%
40%Applied CPM Did not Apply CPM
Perc
ent C
ost G
row
th(A
ctua
l / E
stia
mte
d C
ost)
+1 Std.
-1 Std.Mean
pr < 0.00
pr < 0.00 +1 Std.
-1 Std.Mean
Effect of Scheduling Practices on Project Success By Andrew Griffith, Ph.D., P.E., PMP Independent Project Analysis, Inc.
PMI College of Scheduling Page 8
Topic of the Month – April 2005
XIX. Use of CPM Also Correlated With Better Cost Performance
XX. Resource-Loaded
A. Critical project resources loaded into the schedule using appropriate units of measure
B. Only 24% were resource-loaded
C. Mix of resource categories for projects with resource-loading
D. Construction labor 73%
E. Engineering labor 58%
F. Construction Equip. 24%
0%
10%
20%
30%
Applied CPM Did Not Apply CPM
Perc
ent S
ched
ule
Slip
(Act
ual /
Pla
nned
Dur
atio
n)
0.7
0.8
0.9
1.0
1.1
1.2
1.3Applied CPM Did Not Apply CPM
Cos
t Ind
ex(A
ctua
l / In
dust
ry B
ench
mar
k)
pr < 0.03 +1 Std.
-1 Std.Mean
pr < 0.03
Effect of Scheduling Practices on Project Success By Andrew Griffith, Ph.D., P.E., PMP Independent Project Analysis, Inc.
PMI College of Scheduling Page 9
Topic of the Month – April 2005
G. Estimated cost 21%
H. Other 10%
XXI. Resource-Loading Correlated with Better Cost Performance
XXII. Resource-Loading Also Correlated with Less Schedule Slip
XXIII. Project Team Review
A. Review by the core project team
1. Supports buy-in to plan
2. Provides a check for accuracy and feasibility
0.7
0.8
0.9
1.0
1.1
1.2
1.3Resource-Loaded Not Resource-Loaded
Cos
t Ind
ex(A
ctua
l / In
dust
ry B
ench
mar
k)
+1 Std.
-1 Std.Meanpr < 0.01
0%
10%
20%
30%
Resource-Loaded Not Resource-Loaded
Perc
ent S
ched
ule
Slip
(Act
ual /
Pla
nned
Dur
atio
n)
Effect of Scheduling Practices on Project Success By Andrew Griffith, Ph.D., P.E., PMP Independent Project Analysis, Inc.
PMI College of Scheduling Page 10
Topic of the Month – April 2005
B. 76% of the project schedules were reviewed by the team
XXIV. Team Review Correlated with Less Cost Growth
Conclusions and Recommendations
XXV. Single Schedule Definition Rating
A. Definitive - Resource-loaded CPM schedule that covers all major project phases
B. Preliminary - CPM schedule that covers all major project phases, but not resource-loaded
C. Factored - Milestone schedule showing the timing required for major project milestones and phases
D. No Schedule - No project schedule developed other than possibly a target completion date
-30%
-20%
-10%
0%
10%
20%
30%
40%
50%Reviewed by Core Team Not Reviewed by Core Team
Perc
ent C
ost G
row
th(A
ctua
l / E
stim
ated
Cos
t)
+1 Std.
-1 Std.Mean
pr < 0.00
Effect of Scheduling Practices on Project Success By Andrew Griffith, Ph.D., P.E., PMP Independent Project Analysis, Inc.
PMI College of Scheduling Page 11
Topic of the Month – April 2005
XXVI. Sample Distribution
XXVII. Schedule Definition Drives Better Cost Performance
Definition Rating Percent of Sample
Definitive 13%
Preliminary 29%
Factored 55%
No Schedule 3%
0.90 0.95 1.00 1.05
Milestone
CPM Schedule
Resource-Loaded
Average Cost Index(Actual / Industry Benchmark)
pr < 0.00
Effect of Scheduling Practices on Project Success By Andrew Griffith, Ph.D., P.E., PMP Independent Project Analysis, Inc.
PMI College of Scheduling Page 12
Topic of the Month – April 2005
XXVIII. Schedule Definition Also Correlated with Better Schedule Performance
XXIX. Schedule Definition Also Drives Lower Schedule Slip
0.4
0.6
0.8
1.0
1.2
1.4
1.6Definitive Preliminary Factored
Exec
utio
n Sc
hedu
le In
dex
(Act
ual /
Indu
stry
Ben
chm
ark)
+1 Std.
-1 Std.Meanpr < 0.02
0% 5% 10% 15% 20% 25% 30%
Milestone
CPM Schedule
Resource-Loaded
Average Percent Schedule Slip(Actual / Planned Duration)
Effect of Scheduling Practices on Project Success By Andrew Griffith, Ph.D., P.E., PMP Independent Project Analysis, Inc.
PMI College of Scheduling Page 13
Topic of the Month – April 2005
XXX. Schedule Definition Also Correlated with Less Cost Growth
XXXI. Conclusions
A. Sound scheduling practices drive better project outcomes
B. Significant benefits of good scheduling practices
1. 7% better cost
2. 12% better schedule
3. 6% less cost growth
4. 23% less schedule slip
XXXII. Transferability of Findings
A. Sample is limited to capital projects in the heavy industrial sector
B. Measure of scheduling practices anchored at the time of project authorization - not at the start of construction
However
C. Relationship between practices and outcomes is consistent across project types and industries
D. General findings are applicable to all project types
pr < 0.00 -30%
-20%
-10%
0%
10%
20%
30%
40%Definitive Preliminary Factored
Per
cent
Cos
t Gro
wth
(Act
ual /
Est
imat
ed C
ost)
+1 Std.
-1 Std.Mean
Effect of Scheduling Practices on Project Success By Andrew Griffith, Ph.D., P.E., PMP Independent Project Analysis, Inc.
PMI College of Scheduling Page 14
Topic of the Month – April 2005
XXXIII. Recommendations
A. Use the results of this study to help justify the investment in sound scheduling practices
B. Benchmark schedule development
1. Design an applicable metric for schedule definition
2. Systematically measure schedule definition at authorization for all projects
3. Measure trends and strive to improve
Contact Information
Andrew F. Griffith
Independent Project Analysis, Inc.
44426 Atwater Drive, Suite 100
Ashburn, Virginia 20147
Phone: 703-729-8300
E-Mail: [email protected]