Mr. Liu Kwong Chi, Nelson Messrs. Clarence Wong, Cheung & Liu 29 September 2005
EFFECTIVENESS IN RELATIONAL CONTRACTING · 2005, organised by AIPM, Hilton on the Park, Australia,...
Transcript of EFFECTIVENESS IN RELATIONAL CONTRACTING · 2005, organised by AIPM, Hilton on the Park, Australia,...
A STUDY OF THE DETERMINANTS OF
EFFECTIVENESS IN RELATIONAL CONTRACTING
By
YAN KI FIONA CHEUNG
A thesis submitted in partial fulfilment of the requirements for the degree of
Master of Applied Science by Research
QUEENSLAND UNIVERSITY OF TECHNOLOGY
2006
Faculty of Built Environment and Engineering
To my dearest family
i
KEYWORDS
Australia, Case Study, Construction Industry, Culture, Interviews,
Organisation, Public Sector, Relational Contracting Survey.
ii
iii
ABSTRACT
The significance of a link between organisational culture and
organisational performance has long been recognised in both mainstream
management literature as well as in the construction management
literature. Within the construction research domain, the impact of culture
and organisation on project performance is becoming an increasingly
important topic for the establishment of sound partnering or alliancing, or
to what has been referred to increasingly in recent years as relational
contracting, in the overall approach to project management. However,
studies of the efficacy of alliancing or partnering have so far produced
mixed results.
The present study concerns two public sector organisations in Australia,
where the interrelationships between organisational culture and structure,
commitment and national culture were investigated. The methodology
was triangulated; with a detailed questionnaire survey undertaken with
both organisations, and with subsequent interviews and case studies
carried out for validation. Multivariate statistical techniques were utilised to
investigate complex relationships between variables.
The research reports the perceptions of professional personnel in the
public sector organisations, and some mismatches found between
organisational structuring and organisational culture. Key issues affecting
project performance, and the set of project team characteristics enhancing
the development of a collaborative project culture, were found to include
continuous commitment from all levels, right mix of people, formal and
informal communication, continuous facilitation, education and training in
the universities, institutions and industry. The combined outcomes of the
iv
research provided a framework of fundamental elements for successful
relational contracting.
v
CONTENTS
Keywords ............................................................................................................. i
Abstract.............................................................................................................. iii
List of Tables...................................................................................................... ix
List of Figures .................................................................................................... xi
List of Publications and Presentations ..............................................................xiii
Acknowledgements..........................................................................................xvii
Statement of Original Authorship ..................................................................... xix
CHAPTER 1 INTRODUCTION .......................................................................1
1.1 Background of Research ........................................................................1
1.2 Research Problems................................................................................2
1.3 Scope of the Research...........................................................................5
1.4 Research Methodology...........................................................................5
1.5 Structure of thesis ..................................................................................6
1.6 Conclusion..............................................................................................8
CHAPTER 2 PARTNERING, ALLIANCING AND RELATIONAL
CONTRACTING ........................................................................9
2.1 Introduction.............................................................................................9
2.2 Partnering...............................................................................................9
2.3 Alliancing ..............................................................................................16
2.4 Relationship Contracting ......................................................................21
2.5 Conclusion............................................................................................24
CHAPTER 3 CULTURE................................................................................29
3.1 Introduction...........................................................................................29
3.2 What is Culture?...................................................................................29
3.3 National and Organisational Culture.....................................................31
vi
3.4 Culture and Value ................................................................................ 36
3.5 Culture Dimensions.............................................................................. 38
3.5.1 Large or Small Power Distance............................................................................ 39
3.5.2 Masculinity vs. Femininity .................................................................................... 39
3.5.3 Individualism vs. Collectivism............................................................................... 40
3.5.4 Strong or Weak Uncertainty Avoidance ............................................................... 40
3.5.5 High and Low Confucian Dynamism .................................................................... 40
3.6 Commitment ........................................................................................ 41
3.7 Organisational Culture and Structure................................................... 44
3.8 Trust..................................................................................................... 45
3.8.1 Implications of Trust............................................................................................. 46
3.8.2 Nature of Trust ..................................................................................................... 47
3.9 Culture and Trust in the Construction Industry..................................... 49
3.10 Conclusion ........................................................................................... 52
CHAPTER 4 BACKGROUND OF QUEENSLAND DEPARTMENTS OF
MAIN ROADS AND PUBLIC WORKS ................................... 55
4.1 Introduction .......................................................................................... 55
4.2 Background of Queensland Department of Main Roads...................... 55
4.3 Project Delivery System....................................................................... 56
4.4 Partnering and Alliancing in QDMR ..................................................... 57
4.4.1 Relationship Management ................................................................................... 59
4.5 Background of Queensland Government Department of Public
Works............................................................................................................ 62
4.6 Project Delivery System....................................................................... 62
4.7 Partnering, Alliancing and Relational Contracting in QDPW ................ 64
4.7.1 C21 Construction Contract................................................................................... 65
4.8 Conclusion ........................................................................................... 68
CHAPTER 5 METHODOLOGY.................................................................... 71
5.1 Introduction .......................................................................................... 71
5.2 Research Background ......................................................................... 72
vii
5.2.1 Objectives.............................................................................................................73
5.2.2 Hypothesis............................................................................................................73
5.3 Research Methodology.........................................................................74
5.3.1 Organisational Culture and Structure....................................................................76
5.3.2 Levels of Commitment ..........................................................................................77
5.3.3 Organisational Structure .......................................................................................77
5.3.4 National Culture ....................................................................................................77
5.4 Scope of the Research.........................................................................78
5.5 Data Collection .....................................................................................79
5.6 Data Analysis .......................................................................................80
5.7 Summary ..............................................................................................80
CHAPTER 6 CULTURE SURVEY ................................................................83
6.1 Introduction...........................................................................................83
6.2 QDPW Survey Analysis........................................................................84
6.2.1 Organisational Culture ..........................................................................................84
6.2.2 Commitment .........................................................................................................86
6.2.3 Organisational Assessment ..................................................................................87
6.2.4 Culture ..................................................................................................................99
6.2.5 Overview of QDPW Data ....................................................................................103
6.3 QDMR Survey Analysis ......................................................................105
6.3.1 Organisational Culture ........................................................................................105
6.3.2 Commitment .......................................................................................................108
6.3.3 Organisational Assessment ................................................................................109
6.3.4 Culture ................................................................................................................119
6.3.5 Overview of QDMR Data ....................................................................................123
6.4 Discussion ..........................................................................................125
CHAPTER 7 CASE STUDIES ....................................................................129
7.1 Introduction.........................................................................................129
7.2 Findings..............................................................................................129
7.2.1 Case Study 1 ......................................................................................................130
viii
7.2.2 Case Study 2 ..................................................................................................... 132
7.2.3 Case Study 3 ..................................................................................................... 133
7.2.4 Case Study 4 ..................................................................................................... 135
7.2.5 Case Study 5 ..................................................................................................... 136
7.2.6 Case Study 6 ..................................................................................................... 137
7.2.7 Case Study 7 ..................................................................................................... 139
7.3 Discussion ......................................................................................... 141
7.3.1 Postscripts ......................................................................................................... 148
CHAPTER 8 CONCLUSION ...................................................................... 153
8.1 Introduction ........................................................................................ 153
8.2 Research Hypotheses........................................................................ 154
8.3 Conclusions ....................................................................................... 155
8.3 Limitations of the Research ............................................................... 158
8.4 Areas for Future Research................................................................. 158
APPENDICES .............................................................................................. 161
Appendix I Transactional & Relational Contracting ..................................161
Appendix II Definitions of Partnering, Alliancing & RC ..............................163
Appendix III Culture Questionnaire ............................................................171
Appendix IV Survey Results .......................................................................217
Appendix V Case Studies..........................................................................313
Appendix VI Relational Contracting Success and Failure Factors..............345
REFERENCES .............................................................................................. 349
ix
LIST OF TABLES
Table 2.1 Australian Partnering Types................................................................... 10
Table 2.2 Comparison of Identified Partnering Benefits......................................... 14
Table 2.3 Characterises of Services, Opportunistic and Stakeholder Alliances ..... 18
Table 2.4 Characteristics of Relational Contract and Construction Contract.......... 22
Table 3.1 Comparison between National Culture and Construction Culture .......... 35
Table 3.2 ‘Types’ of Commitment Identified by Meyer and Allen............................ 42
Table 4.1 Formal Relationship Management Process in QDMR Projects .............. 61
Table 4.2 Types of Contracts Used in QDPW........................................................ 67
Table 5.1 Organisation Culture and Structure Defined by Handy........................... 76
Table 6.1 Organisational Culture (QDPW)............................................................. 85
Table 6.2 Commitment Levels (QDPW)................................................................. 86
Table 6.3 Hypothesis Patterns of Systematized, Discretionary and Developmental Models of Structure in Complex Organisations.............. 88
Table 6.4 Hypothesised Patterns of Structure mode in QDPW.............................. 89
Table 6.10 Consensus and Conflict between QDPW and Other Units..................... 90
Table 6.14 Frequency of Use of Methods of Conflict Resolution (QDPW) ............... 91
Table 6.19 Correlation between Working Relationship Effectiveness and Methods of Communication (QDPW & Other Units)............................... 93
Table 6.43 Correlation between Perceived Effectiveness of Relationship and Relationship Indices (QDPW) ................................................................ 97
Table 6.44 Scores for Australian Professionals on Hofstede Indices .................99,119
Table 6.45 Importance of Criteria for an Ideal Job (QDPW)....................................100
Table 6.46 Levels of Agreement on Statements (QDPW).......................................101
Table 6.47 Agreements to Statements in Relation to Project Success or Achieving Objectives (QDPW)..............................................................102
Table 6.48 Organisational Culture (QDMR)............................................................106
Table 6.49 Commitment Levels (QDMR)................................................................108
Table 6.50 Hypothesised Patterns of Structure Mode in QDMR .............................110
Table 6.65 Correlation between Working Relationship Effectiveness and Methods of Communication (QDMR & Other Units)..............................114
Table 6.89 Correlation between Perceived Effectiveness of Relationship and Relationship Indices (QDMR) ...............................................................117
Table 6.90 Importance of Criteria for an Ideal Job (QDMR)....................................119
x
Table 6.91 Difference between the Means of QDPW and QDMR on the Importance of Criteria for an Ideal Job using t-test............................... 121
Table 6.92 Level of Agreement on Statements (QDMR)........................................ 121
Table 6.93 Agreement to Statements in Relation to Project Success or Achieving Objectives (QDMR) ............................................................. 122
xi
LIST OF FIGURES
Figure 1.1 Research Propositions............................................................................. 4
Figure 1.2 Thesis Map.............................................................................................. 6
Figure 2.1 Evolution of Partnering: from Project to Third Generation ...................... 12
Figure 3.1 Types of Culture as Illustrated Base on System Theory......................... 30
Figure 3.2 Components in an Organisational Culture ............................................. 32
Figure 5.1 Research Method .................................................................................. 74
Figure 7.1 Input-Process-Output Map based on Research Findings......................152
xii
xiii
LIST OF PUBLICATIONS AND PRESENTATIONS
The following publications were produced by or in conjunction with the
author, during her M.Sc. candidacy:
Refereed Journal Papers
Rowlinson, S., Cheung, F.Y.K., Simons, R. and Rafferty, A. (2006).
‘Alliancing in Australia – No Litigation Contracts; a Tautology?’,
Journal of Professional Issues in Engineering Education and Practice
(accepted for publication).
Refereed Conference Papers
Cheung, F.Y.K. and Rowlinson, S. (2005). ‘Relational Contracting: the
Way Forward or Just a Brand Name?’, Proceedings of 1st
International Conference on Construction Engineering and
Management, Seoul, Korea, October 16th-18th.
Cheung, F.Y.K., Rowlinson, S. and Jefferies, M.C. (2005). ‘A Critical
Review of the Organisational Structure, Culture and Commitment in
the Australian Construction Industry’, in (ed) Sullivan, K. and
Kashiwagi, D.T. Proceedings of the International Symposium of CIB
W92/TG23/W107 on the Impact of Cultural Differences and Systems
on Construction Performance, Las Vegas, Nevada, USA, February
8th-10th, 347-354.
Rowlinson, S. and Cheung, F.Y.K. (2004). ‘Relational Contracting,
Culture and Globalisation’, in (ed) Ogunlana, S., Charoenngam, C.,
Herabat, P. and Hadikusumo, B.H.W. Proceedings of the
International Symposium of CIB W107/TG23 Joint Symposium on
xiv
Globalisation and Construction, Bangkok, Thailand, November 17th-
19th, 239-247.
Rowlinson, S. and Cheung, F.Y.K. (2004). ‘A Review of the Concepts
and Definitions of the Various Forms of Relational Contracting’, in
(ed) Kalidindi, S.N. and Varghese, K. Proceedings of the
International Symposium of CIB W92 on Procurement Systems,
Chennai, India, January 7th-12th, 227-236.
Conference Papers
Cheung, F.Y.K. and Rowlinson, S. (2005). ‘The Interrelationships between
Organisational Structure, Culture and Commitment – an Australian
Case Study’, Proceedings of Australian Institute of Project
Management Conference 2005, Melbourne, Australia, October 9th-
11th.
Cheung, F.Y.K., Rowlinson, S., Spathonis, J., Sargent, R., Jones, T.,
Jefferies, M.C. and Foliente, G. (2004). ‘Organisational Structure,
Culture and Commitment: An Australia Public Sector Case Study’, in
(ed) McCarthy, J.V. and Hampson, K. Proceedings of the
International Conference of CRC for Construction Innovation on
Clients Driving Innovation, Surfers Paradise, Australia, October 25th-
27th.
Rowlinson, S. and Cheung, F.Y.K. (2004). ‘Relationship Management in
QDMR’, Road System and Engineering Technology Forum,
Brisbane, Queensland, Australia, August 4th-5th.
xv
The following presentations were given by the author, during her M.Sc.
candidacy:
Presentations
Cheung, F.Y.K. (2005), ‘The Interrelationships between Organisational
Structure, Culture and Commitment – an Australian Case Study’,
Australian Institute of Project Management National Conference
2005, organised by AIPM, Hilton on the Park, Australia, 9-11
October.
Cheung, F.Y.K. (2005), ‘A Critical Review of the Organisational Structure,
Culture and Commitment in the Australian Construction Industry’,
International Symposium of CIBW92/TG23/W107, organised by CIB,
UNLV, USA, 8-10 March.
Cheung, F.Y.K. (2004), ‘Relational Contracting, Culture and
Globalisation’, International Symposium of CIB W107/TG23,
organised by CIB, AIT, Thailand, 17-19 November.
Cheung, F.Y.K. (2004), ‘Organisational Structure, Culture and
Commitment: An Australia Public Sector Case Study’, International
Conference of CRC for Construction Innovation, organised by CRC
for Construction Innovation, Crown Plaza, Australia, 25-27 October.
Cheung, F.Y.K. (2004), ‘A Review of the Concepts and Definitions of the
Various Forms of Relational Contracting’, International Symposium
of CIB W92, organised by CIB, Indian Institute of Technology
Madras, India, 7-12 January.
xvi
xvii
ACKNOWLEDGEMENTS
A special acknowledgement goes to my supervisors Prof. Steve Rowlinson
and Prof. Tony Sidwell, who provided valuable advice and guidance for
the successful production of this thesis. Special thanks to Steve for his
patient and trust in me to be able to successfully complete the Master
degree. I have been given tremendous supports and opportunities from
Steve to attend workshops and conferences; as well as being encouraged
to publish and present during my candidature. Thanks Steve!
I would also like to express my sincere gratitude to staff members of the
Queensland Departments of Main Roads and Public Works, for their kind
participation on the questionnaire survey and interviews and providing me
with access to resources. Without their time and commitment to the
research, this thesis would hardly have been completed. Special thanks go
to John Spathonis.
I am grateful to the CRC for Construction Innovation and the Faculty of
Built Environment and Engineering, for funding me to attend conferences
during my candidature.
Finally, I would like to express my deepest gratitude to my Mom, Dad and
brother, for their unconditional love and support, and appreciation of my
work, which has motivated me to work harder. I would like to give my
special thanks to my dear friend Catherine Chen for keeping my spirits up
when I was at my lows during my M.Sc. journey.
xviii
xix
STATEMENT OF ORIGINAL AUTHORSHIP
“The work contained in this thesis has not been previously submitted to
meet requirements for an award at this or any other higher education
institution. To the best of my knowledge and belief, the thesis contains no
material previously published or written by another person except where
due reference is made.”
Signature CHEUNG, Yan Ki Fiona
Date
xx
xxi
Harvard referencing style has been employed in this thesis.
xxii
1
CHAPTER 1
INTRODUCTION
1.1 Background of Research
The implicit link between organisational culture and organisational
performance has long been recognised in both main-stream management
literature (Handy 1985; Hofstede 1980) as well as in the construction
management literature (Liu & Fellows 2001; Rowlinson 2001). Within the
construction research domain, the impact of culture and organisation on
project performance is becoming an increasingly important topic for the
establishment of a sound partnering or alliancing, or as referred to more
often in recent years, relational contracting, approach to projects. Many
reports have been produced in recent years, such as the Tang Report on
‘Construct for Excellence: Report of the Construction Industry Review
Committee’, the Hong Kong Housing Authority report on ‘Partnering for
Change’, ‘Building for Growth’ by Australia NatBACC and the Egan report
on ‘Rethinking Construction’; all indicate the way forward for the
construction industry and call for a culture change in the industry. These
reports advocate a move away from adversarial relationships and towards
the use of partnering and alliancing.
CHAPTER 1 INTRODUCTION
2
The impact of culture and organisation on project performance is
becoming recognised as an increasingly important research topic, as both
of these are important for the establishment of a sound relational
contracting approach to projects. The Queensland Departments of Main
Roads (QDMR) and Public Works (QDPW) have both identified the need
for further development in their own organisation culture and attitudes to
implementing the fundamental components of relationship contracts.
Alliancing, partnering and relational contracting projects aim to move the
project team away from adversarial relationships and towards collaborative
relationships. However, the efficacy of alliancing or partnering has thus far
not been proven and projects have produced mixed results. This research
aims to shed light on the practices and pre-requisites for relationship type
contracts to be successful (see for example Bresnen & Marshall
2000a,b,c) and to understand how the interrelationships between national
culture, organisational structure, organisation culture and levels of
commitment affect an organisation’s performance.
1.2 Research Problems
Organisational culture and organisation structure must be matched if
participants are to retain commitment to the organisation (Rowlinson
2001). This research takes Rowlinson’s work as a starting point and
develops it further into a study of the key determinants of effectiveness in
relational contracting. The aim of this research is to develop and test a
framework within which the determinants of performance in project teams
can be assessed. Therefore, the objectives of this research are:
• To investigate how a collaborative project culture is developed and
enhanced by considering the set of project team characteristics;
and
• To identify the ways in which collaboration can be transmitted
throughout the industry.
CHAPTER 1 INTRODUCTION
3
Based on the issues outlined in section 1.1 above, this research will
address the following questions:
• How is a collaborative project culture developed and enhanced by
considering the set of organisational characteristics, project team,
characteristics and national culture?
• What are the ways in which collaboration can be transmitted
throughout the organisation?
Based on issues identified in Chapters 2-4, the following hypotheses are
developed and will be tested in the study:
• Organisational culture and organisation structure must be matched
if participants are to retain commitment to the organisation
(Rowlinson 2001).
• Parent organisation culture affects temporary project culture.
• Encouragement by organisation to exhibit cooperative behaviour
amongst employees leads to greater cooperation between
individuals
The relationship between the literature review, research propositions and
instruments employed are presented in Figure 1.1 overleaf.
CHAPTER 1 INTRODUCTION
4
Figure 1.1 Research Propositions
LITERATURE REVIEW
RC Definitions � Long-term relationship � Culture � Trust � Legislations &
regulations
Culture & Value, Commitment, Organisational Culture & Structure • National culture • Organisational culture • Organisational structure • Commitment • Cooperation between individuals • Empowerment • Collaborative relationship & trust
Public Sector Organisations • Definition of relational
contracting • Current project delivery
systems • Relational contracting
in practice
INSTRUMENTS EMPLOYED • Organisational Culture and Structure (assessed using Handy’s instrument) • Commitment (assessed using Allen and Meyer’s instrument) • Organisation Assessment (assessed using Van de Ven and Ferry’s instrument) • National Culture (assessed using Hofstede’s VSM)
RESEARCH PROPOSITIONS
How is a collaborative project culture developed and enhanced by considering the set of organisational characteristics, project team, characteristics and national culture?
What are the ways in which collaboration can be transmitted throughout the organisation?
Hypothesis 1 Organisational culture and organisation structure must be matched if participants are to retain commitment to the organisation
Hypothesis 2 Parent organisation culture affects temporary project culture
Hypothesis 3 Encouragement by organisation to exhibit cooperative behaviour amongst employees leads to greater cooperation between individuals
CHAPTER 1 INTRODUCTION
5
1.3 Scope of the Research
Due to time and resource constraints, the research focused on the public
sector in Queensland. Believing the client is the driver of change
(Construction Clients' Forum 1998; Construction Industry Board 1997;
Construction Industry Institute 1991; Egan 1998), this research attempts to
provide an overall perspective of the industry’s achievements in effective
relational contracting by employing data collected from the public sector
organisations. A triangulated approach using questionnaire, interview and
case study was adopted and the research methodology is outlined in
section 1.4.
1.4 Research Methodology
The research was broken into two distinct phases and was carried out
using questionnaire survey, interview and case study approaches. Due to
the size and complexity of the questionnaire, both public sector
organisations, QDPW and QDMR, were asked to nominate professionals
with experience on partnering, alliancing or relationship contracting
projects for the questionnaire survey, to control the sample quality.
Twenty professionals were nominated to participate in the main
questionnaire survey and 16 questionnaires were returned. A sub-
questionnaire was then sent to 47 people identified in the main
questionnaire and 42 completed sub-questionnaires were returned. Upon
the collection of each main questionnaire, a 30 to 60 minute interview was
carried out with each professional. A total of seven case studies were
collected from both organisations. Observations of monthly site and
relationship management meetings were carried out in two case studies to
examine team dynamics and communication processes in the project
teams.
CHAPTER 1 INTRODUCTION
6
1.5 Structure of thesis
Three themes, the relational contracting form, cultural aspects and project
delivery systems in the public sector organisations, are treated in the
introductory chapters in order to provide the necessary background for the
presentation of the research model and methodology in Chapters 5, 6 and
7. The results of data analysis and subsequent discussions follow and the
thesis closes with an examination of the conclusions drawn from the
research. The thesis structure is shown in Figure 1.2.
Figure 1.2 Thesis Map
Chapter 2 RELATIONAL
CONTRACTING � Definitions � Perceptions � Project team
Chapter 3 CULTURE
� National culture � Organisational
culture � Organisational
structure � Commitment � Project team
Chapter 4 PUBLIC SECTOR
� Relational contracting process
� Current project delivery systems
Chapter 5 RESEARCH MODEL & METHODOLOGY
� Variables � Framework � Sample
Chapter 6&7 RESULTS
� Analysis � Discussion
Chapter 8 CONCLUSIONS
� Tested hypotheses � Research conclusions � Limitations of research � Further research
Chapter 1 INTRODUCTION
� Thesis structure � Research Scope � Introduction to thesis chapters
CHAPTER 1 INTRODUCTION
7
Chapter 1 is an introduction to the thesis, presenting its structure, its
primary assumptions and major findings. It introduces some key issues in
relation to relational contracting, organisational culture and performance,
in particular the scarcity of research into the practice and pre-requisites for
relationship type contracts to be successful in the construction industry.
Chapter 1 presents the overall thesis structure in a flowchart.
Chapter 2 is a review of the existing definitions of partnering, alliancing
and relational contracting in the construction domain. An overview of the
current state-of-the-art of the use and implementation of the procurement
systems presented. Attention is then turned to the construction industry
culture with relational contracting in practice. Chapter 3 discusses the
interrelationships between culture, structure and commitment in the parent
and project organisations. Factors affecting performance, as indicated
from a literature review of construction and general project management,
are presented. The chapter concludes with a presentation of the
construction industry characteristics and the drivers for culture change.
Chapter 4 presents the background of project delivery systems used by
the Queensland Departments of Main Roads and Public Works and the
reasons for change. It outlines how a relational contracting approach has
been adopted in both organisations, in theory and in practice, and the
inadequacies of the current system.
The review of previously published research, management literature and
theory, and opinions expressed publicly and privately, lays the foundation
for the presentation of the research model in Chapter 5. It outlines the
research questions addressed in this thesis and the hypotheses tested
during the study. The research was broken into 2 distinct phases: the
impact of the various cultural variables on project performance was
investigated using a questionnaire survey with follow-up interviews and the
CHAPTER 1 INTRODUCTION
8
results are presented in Chapter 6; and the variables influencing the
success of relational contracts were analysed through interviews and case
studies and are discussed in Chapter 7. Chapters 6 and 7 present and
discuss the research methodology adopted and cover the method of data
collection, the statistical analyses used and the properties of the sample
under consideration. The chapters discuss the research findings in detail.
More detailed case study information and data listings are included as
appendices.
Chapter 8 concludes with a summary of the contribution made to
knowledge by this thesis. It has examined the interrelationship between
national culture, organisational structure, culture and commitment in two
Australian public sector organisations with very diverse natures. The
chapter investigates the fundamental issues affecting project performance
and hence identifies the key determinants of effectiveness in relational
contracting in the construction industry. Chapter 8 outlines some
limitations to this research and the chapter concludes with proposed areas
of future research.
1.6 Conclusion
This chapter has laid the foundations for the thesis. It has introduced the
research problem that the thesis seeks to address and the research
hypotheses (see section 1.2). This chapter has provided an overview of
the research area and the research scope on relational contracting
effectiveness in the construction industry. The research methodology,
using questionnaire survey, case studies and interviews, has been briefly
described and the structure of the thesis has been outlined.
9
CHAPTER 2
PARTNERING, ALLIANCING AND RELATIONAL
CONTRACTING
2.1 Introduction
Partnering has been defined in many ways. It can be considered as an
individual project mechanism or as a long-term strategy. Alliancing is
normally assumed to be a long-term business strategy linking together
client, contractor and supply chain. Relational contracting goes further
than this and brings in the whole philosophy of the value chain and the
linking of the interdependent parts within the construction project as a key
business objective. This chapter aims to review existing definitions of
these three concepts and present an overview of the current state of-the-
art of the use and implementation of the procurement systems.
2.2 Partnering
Partnering is defined as a structured management approach to facilitate
team work across contractual boundaries. Its fundamental components
include mutual objectives, agreed problem resolution methods, and an
active search for continuous measurable improvements (CBP 1998). The
CHAPTER 2 PARTNERING, ALLIANCING & RELATIONAL CONTRACTING
10
Construction Industry Institute (CII) (1996) suggests a partnering charter is
developed to run in parallel with a traditional construction contract to
provide guidelines to the relationship between the organisations. CII
defines partnering as three types, namely experimental partnering,
packaged partnering and committed partnering, as illustrated in Table 2.1.
Type Description Outcome
Experimental partnering • Charter, workshop, small number of follow-up meetings
• Usually first partnering experience
• Minimally resourced • Often seen as a ‘toe-in-the-
water’ exercise
• Often unsuccessful, generally because of lack of clear understanding, commitment and structure
Packaged partnering • Offered as part of a contractor’s tender or imposed upon the contractor after the tender is accepted
• Often involves only the client and contractor
• This model is used very successfully as a marketing tool
• Problems may arise from lack of commitment and understanding of each stakeholder’s objective
• A client-contractor relationship perceived to be cooperative at the outside (outset) of a project may not necessarily last for the duration of the contract
Committed partnering • Often developed as a result of first, unsuccessful experience
• Incorporates as many stakeholders as possible in a tight, well facilitated dispute resolution mechanism
• Well resourced
• Problems may arise from lack of commitment and understanding of each stakeholder’s objective
• A client-contractor relationship perceived to be cooperative at the outside (outset) of a project may not necessarily last for the duration of the contract
Table 2.1 Australian Partnering Types (adapted from CII 1996 by Walker & Hampson 2003 – p. 48)
Partnering is also recognised as a method of improving communication
mechanisms and technologies, responding to innovative construction
projects, creating a less stressful working environment and reducing
transaction costs resulting from uncertainty, competition and information
CHAPTER 2 PARTNERING, ALLIANCING & RELATIONAL CONTRACTING
11
asymmetry (ECI 1997; Liu & Fellows 2001). One of the most commonly
used definitions for partnering was created by CII as follows (CII 1991):
‘…a long-term commitment between two or more organisations for the
purpose of achieving specific business objectives by maximising the
effectiveness of each participant’s resources. This requires changing
traditional relationships to a shared culture without regard to organisational
boundaries. The relationship is based on trust, dedication to common
goals, and an understanding of each other’s individual expectations and
values.’
Weston and Gibson (1993) find the three most important elements in the
definition given by CII are trust, shared vision and long-term commitments.
Peters et al. (2001) suggest partnering relies solely on the commitment of
individuals due to the fact that a partnering charter is not legally binding.
Green (1999) sees partnering as primarily concerned with ‘maximising
effectiveness’. The definition given by Bennett and Jayes (1995b) reflects
similar themes:
‘…partnering is a management approach used by two or more
organisations to achieve specific business objectives by maximising the
effectiveness of each participant’s resources. The approach is based on
mutual objectives, an agreed method of problem resolution, and an active
search for continuous measurable improvements.’
It is noted that improvement must not only be continuous but measurable
as well. The definition offered by the ‘Egan Report’ is similar (Egan 1998):
‘…partnering involves two or more organisations working together to
improve performance through agreeing mutual objectives, devising a way
for resolving disputes and committing themselves to continuous
improvement, measuring progress and sharing the gains.’
CHAPTER 2 PARTNERING, ALLIANCING & RELATIONAL CONTRACTING
12
The Department of the Environment, Transport and the Region further
consider partnering to be a ‘tool to tackle fragmentation’ which is
increasingly used by the best firms in place of traditional contract-based
procurement and project management (Green 1999). According to the
Construction Industry Board (1997), partnering has three essential
components:
• establishment of agreed and understood mutual objectives
• methodology for quick and cooperative problem resolution
• culture of continuous, measured improvement.
Partnering has also been discussed by many commentators and
categorised as project partnering and strategic partnering (RCF 1995a;
Gaedo 1995; Kumaraswamy & Matthews 2000; Matthews 1996; Matthews
& Rowlinson 1999). Project partnering is partnering undertaken on a
single project. At the end of the project, the partnering relationship is
terminated and another relationship is commenced on the next project.
Project partnering was pioneered in the USA construction industry during
the mid to late 1980s. Australia followed by adopting the partnering
philosophy in the early 1990s. Strategic partnering takes place when two
or more firms use partnering on a long-term basis to undertake more than
one construction project, or some continuing construction activity (RCF
1995a).
Kubal (1994) and more recently the Reading Construction Forum (RCF)
(1998) discuss partnering at an industry-wide level. Kubal (1994) notes
that although partnering is practiced on fragmented projects, it requires
national lobbying in order for partnering to be used across industry under
the correct circumstances. In the UK, the Reading Construction Forum
(1998) develop this point further by stating that new initiatives in partnering
have enabled ‘second and third generation partnering’ to evolve. Watson
CHAPTER 2 PARTNERING, ALLIANCING & RELATIONAL CONTRACTING
13
(1999) reported that second generation partnering was underpinned by the
‘seven pillars’ of partnering (RCF 1998) which are strategy, membership,
equity, integration, benchmarks, project processes, and feedback. In the
third generation of partnering, the construction firm should be building
virtual organisations with its supply chain to provide a complete service
that is efficient, creative, and innovative (Kumaraswamy & Matthews 2000;
Watson 1999). The industry should also become truly collaborative in
producing and marketing a range of services that clients are eager to
invest in (Matthews & Rowlinson 1999). Figure 2.1 shows the three
categories of partnering as described by RCF (1995a; 1998).
Figure 2.1 Evolution of Partnering: from Project to Third Generation (adapted from RCF 1995, 1998 by Matthews & Rowlinson 1999 – p.349)
Key Principles • Agreeing mutual objectives. • Making decisions jointly and
resolving problems. • Aiming at targets that provide
continuous measurement in performance from project to project.
(RCF, 1998: Chp. 1, Page 3)
Project and Strategic Partnering Partnering can be applied to one-off schemes (project partnering), or can be on going over a series of developments (strategic partnering). Typically, with project partnering, cost savings of 2-10% are achieved, with strategic partnering savings of 30% are realistic over time. (RCF, 1995:iii)
Key Principles (Seven Pillars) Strategy, Membership, Equity, Integration, Benchmarks, Project Process, Feedback. (RCF, 1998, Chp. 3, Page 12)
Second Generation A ‘Second Generation’ of partnering has now emerged that requires a strategic decision to cooperate in improving joint performance by a client and a group of consultants, contractors and specialists engaged in an ongoing series of projects… Second generation is tough but those firms who have the Seven Pillars in place find that cost savings of 40% are not uncommon, and time savings of more than 50% are achievable. (RCF, 1998:iii)
Third Generation …research also identifies the beginnings of a third generation of partnering in which the construction industry becomes a truly modern industry producing and marketing a range of products and services that clients are eager to invest in. The resulting Third Generation Partnering delivers even greater benefits, - cost savings of more than 50% or more, and where speed is crucial, construction time frames can be reduced by 50% or more. (RCF, 1998:ii)
CHAPTER 2 PARTNERING, ALLIANCING & RELATIONAL CONTRACTING
14
A comparison of identified partnering elements is as follows:
Associated General Contractors of America (1991) Sanders and Moore (1992)
Commitment Continuous evaluation Equity Mutual objectives Timely responsiveness Trust Implementation
Cooperative management team Cooperation Open communication Group working Common goals Problem solving
Matthews (1996) Reading Construction Forum (1995a)
Goals and objectives Trust Problem resolution Commitment Continuous evaluation Group working Win-win philosophy Shared risk Equity Cooperation
Free and open communication Open book costing Annual review of performance Workshops Continuous evaluation Mutual objectives Problem resolution
Table 2.2 Comparison of Identified Partnering Elements (Adapted from Matthews 1996 by Kumaraswamy & Matthews 2000 – p.5)
Green (1999) offers an opposing view on partnering. He argues that the
philosophy of continuous, measured improvement from the definition of
partnering presented by Construction Industry Board (1997) actually
demands that each project exceeds the performance of the previous one.
Despite the seductive discourse on ‘empowerment’, ‘working together’ and
‘relationships’, the ultimate measure of success seems to hinge on cost
improvement.
Green (1999) also suggests that the arguments in favour of partnering
would seem to owe more to the buying power of its advocates rather than
to any independent appraisal. It is advocated by the Construction Clients’
Forum (1998):
CHAPTER 2 PARTNERING, ALLIANCING & RELATIONAL CONTRACTING
15
‘…the message from the Construction Clients’ Forum is clear. If this Pact
is concluded, clients represented on the CCF will seek to place their £40bn
of business with companies that are seen to follow the approach described
in this document…’
The Construction Industry Board (1997) made their point equally
emphatically:
‘…if it becomes clear that anyone at the workshop is unable to adopt the
spirit of partnering, that person should be replaced in the team…’
Green (1999) has further pointed out that to propagate partnering in
construction is to exercise increased control over the construction supply
chain. Examples of some leading supermarkets in U.K. were used and
Green (1999) suggested that their innovations in supply-chain
management were directed towards earning super-normal profits, rather
than serving the interests of their customers. Investigation was carried out
by the Office of Fair Trading in 1998 according to a report in The Times on
31 July 1998. Further investigation of the supermarkets was carried out by
the Monopolies and Mergers Commission in late March 1999, with a
possible monopoly penalty.
It is difficult to separate partnering from the principles of Total Quality
Management (TQM) because they share a common goal – continuous
improvement - which originally came from TQM (Green 1999). TQM
encourages employees to identify themselves as parts of a supply chain
which comprises a sequence of relationships between suppliers and
customers (Tuchman 1995). Kerfoot and Knight (1995) suggest that this
provides employees with a sense of self-esteem from serving the next
person in the chain, rather than having to derive satisfaction from the task
itself. Metaphors such as ‘teamwork’ and ‘customer’ are therefore
intentionally used to mask the reality that most employees are required to
CHAPTER 2 PARTNERING, ALLIANCING & RELATIONAL CONTRACTING
16
act as mindless cogwheels in a remorseless machine (Green 1999). If this
critical interpretation is accepted, Green argues that the rhetoric of
customer responsiveness is primarily used as hollow propaganda to justify
management regimes that are increasingly based on domination and
control. The more that managers’ behaviour is governed by propaganda,
the less likely they are to engage in risk-taking and entrepreneurial
behaviour. Such behaviour might become a great barrier to change in an
organisation, for example, a move away from adversarial contractual
behaviour to more collaborative and proactive working behaviour. The
role culture described by Handy (1985) has similar characteristics; role
cultures are slow to perceive the need for change and slow to change
even if the need is seen.
Wood et al. (2002) and Wilson (1994) find the essence of partnering is
single-source, long-term relationships. Such relationships are business-
focused; directed at solving problems, rather than simply selling products.
Trust is a key component when a new relationship is developed, while the
industry moves from competitive, adversarial to cooperative relations
based on reciprocity and solidarity (Wood & McDermott 1999a). Trust-
based partnering encourages parties to adopt higher ethical standards.
2.3 Alliancing
Confusion about the differences between partnering and alliancing is
common in the construction industry. The most noticeable distinction
between partnering and alliancing is described by Walker and Hampson
(2003) as:
‘…with partnering, aims and goals are agreed upon and dispute resolution
and escalation plans are established, but partners still retain
independence and may individually suffer or gain from the relationship.
CHAPTER 2 PARTNERING, ALLIANCING & RELATIONAL CONTRACTING
17
With alliancing the alliance parties form a cohesive entity, that jointly
shares risks and rewards to an agreed formula…’
Alliancing is categorised into two main types by scholars, namely strategic
alliancing and project alliancing. The most common definition of strategic
alliances adopted is: to establish inter-organisational relations and to
engage in collaborative behaviour for a specific purpose (Love &
Gunasekaran 1999). The inter-organisational relationships can be
grouped into three broad classifications of services: cross-company
consortium (service), opportunistic, and stakeholder alliances (Howarth,
Gillin & Bailey 1995). The characteristics of the alliances are outlined in
Table 2.3. A strategic alliance is also seen as an inter-organisational
arrangement which usually exists between two companies, that extends
beyond a specific project and the parties would expect ongoing, mutually
beneficial business (Peters, Walker & Hampson 2001). According to
Bronder and Pritzl (1992), a strategic alliance exists when the value chains
between at least two organisations with compatible goal structures are
combined for the purpose of sustaining and achieving significant
competitive advantages.
A strategic alliance can provide access to resources such as capital,
information, technology, management expertise, markets, customers,
distribution channels, land and labour. Such resources may not be
available to an organisation acting alone. Greater access to resources
allows an organisation to reduce its level of uncertainty in a demanding
and turbulent environment. Strategic alliances also enable organisations
to speed up the market-entry process and increase their responsiveness
to consumer markets (Howarth, Gillin & Bailey 1995).
CHAPTER 2 PARTNERING, ALLIANCING & RELATIONAL CONTRACTING
18
Service Alliances • Requires the lowest level of interdependence between partners with the smallest amount of changes and the lowest level of joint commitment
• Provide economies of scale • Provide the ability for the partners to undertake
large-scale projects with a limited purpose • Difficulties arise due to the diversity of the
interests and goals of the partners • Result in a loss of commitment from members
Opportunistic Alliances e.g. Joint Ventures
• Provide access to the resources of the partner organizations
• Motivated by the existence and recognition of a market opportunity
• Partners might exploit one another’s resources and then move on to pursue the opportunity alone
Stakeholder Alliances e.g. Suppliers,
customers, employees.
• The closest link of all between member organizations
• Seek to build strong, long-term relationships • Assist in achieving the organizational goals by
(of) major stakeholders
Table 2.3 Characteristics of services, opportunistic and stakeholder alliances (Adapted from Howarth et al. 1995)
No successful strategic alliance can be developed without trust. Trust in a
strategic alliance also includes the concept of reciprocity, which implies a
long-term focus, the acceptance that obligations are mutual, and room for
adjustment if one partner is suddenly placed in a compromising position
(Howarth, Gillin & Bailey 1995). Like partnering and relational contracting,
trust between strategic alliance partners is important because it creates an
opportunity and willingness for further alignment, reduces the need for
partners to continually monitor one another’s behaviour, reduces the need
for formal controls, and reduces the tensions created by short-term
inequities. It allows the partners to focus on their long-term business
development as well as cutting down their costs and time. The
characteristics of successful strategic alliances as well as successful
business relationships proposed by Hampson and Kwok (1997) – trust,
CHAPTER 2 PARTNERING, ALLIANCING & RELATIONAL CONTRACTING
19
commitment, interdependence, cooperation, communication and joint
problem solving – reflect a similar theme.
A successful alliance also requires creativity. It has been shown in the
past that the alliances that fail are typically the second alliance that a
group of companies undertakes together. The problem arises when the
individual team members who were on the first alliance insist on using the
same practices since they worked on the previous alliance, despite the
fact that they might not be appropriate for the second. The new team
members do not understand why the practices are adopted and do not feel
any sense of ownership. Since both strategic and project alliances are
tailor-made mechanisms, such alliancing would fail due to the lack of
creativity by the team members from the first project team and the
avoidance of commitment to the work by the new team members.
The main difference between project alliances and strategic alliances is
that project alliances have a defined end, which is most commonly the
practical completion date of a project. The parties are brought together for
a specific project or outcome (Peters, Walker & Hampson 2001). A project
alliancing agreement is also legally enforceable.
A project alliance is described by Hutchinson and Gallagher (2003) as a
project delivery strategy. Several participants join together to share risks
and outcomes on a project (Manivong & Chaaya 2000), where sponsor
and commercial participants’ objectives (client’s objectives) are aligned to:
• maximise performance;
• proactively manage risk;
• reduce cost; and
• achieve outstanding results in the sponsor’s key project objective.
Hutchinson and Gallagher (2003) define a project alliance as:
CHAPTER 2 PARTNERING, ALLIANCING & RELATIONAL CONTRACTING
20
‘… an integrated high performance team selected on a best person for the
job basis; sharing all project risks with incentives to achieve game-
breaking performance in pre-aligned project objectives; within a framework
of no fault, no blame and no dispute; characterised by uncompromising
commitments to trust, collaboration, innovation and mutual support; all in
order to achieve outstanding results.’
Love and Gunasekaran (1999) state that alliances can be either
collaborative or cooperative (Bronder & Pritzl 1992; Hamel 1989;
Hutchinson & Gallagher 2003), based on core competences. Kwok and
Hampson (1996) describe project alliances as a cooperative arrangement
between two or more organisations that forms part of their overall strategy,
and contributes to achieving their major goals and objectives for a
particular project. Hamel (1989) suggests that organisations that enter
into collaborative alliances (short-term) are aware that their partners are
capable of disarming them. Parties to these alliances have clear
objectives and understand that their partner’s objectives will affect their
success. Yet, collaboration does not always provide an opportunity to
internalise a partner’s skills. Love and Gunasekaran (1999) suggest that a
‘psychological barrier’ may exist between alliance partners caused by the
fear that their partner(s) may out-learn or deskill them. Wood and Gray
(1991) state that organisations typically enter collaborative relations to
reduce the complexity of their environment and to gain more control over
environmental factors. Such collaboration may cause new dependencies
to be created, which may increase environmental complexity and
turbulence. They argue that increases in complexity may increase
transaction costs, the need to manage bilateral and multilateral relations
and the need to develop new skills.
Cooperative alliances (long-term) encourage alliance partners to commit
their resources to the relationship to gain mutual learning (Love &
CHAPTER 2 PARTNERING, ALLIANCING & RELATIONAL CONTRACTING
21
Gunasekaran 1999). There is a lower level of competition and as a result,
partners may feel more committed to work together and exchange their
knowledge and resources. Ketelholm (1993) suggests that cooperative
strategic alliances can create a competitive advantage. Organisations that
rely on cooperation have been found to obtain lower costs for as long as
they maintain trust internally and externally – among employees and
members of their network.
2.4 Relationship Contracting
Relationship (or relational) contracting is based on a recognition of mutual
benefits and win-win scenarios through more cooperative relationships
between the parties. Relationship contracting embraces and underpins
various approaches, such as partnering, alliancing, joint venturing, and
other collaborative working arrangements and better risk sharing
mechanisms (Alsagoff & McDermott 1994; Jones 2000; Rahman &
Kumaraswamy 2002). Relational contracts are usually long-term, develop
and change over time, and involve substantial relations between the
parties. Relational contracts are the norm for complex transactions to be
conducted in environments of high complexity, where complete
contingency arrangements are impossible. Successful completion of the
transaction relies on cooperation and the desire to effectuate the contract.
In addiction, the contract must allow a certain flexibility so as to enable
necessary adjustments as appropriate (Cheung 2001). The characteristics
of relational contracts and construction contracts are summarised in Table
2.4.
CHAPTER 2 PARTNERING, ALLIANCING & RELATIONAL CONTRACTING
22
Relational Contracts Construction Contracts
Contracting Environment
• Cooperative instead of defensive
• Proactive instead of reactive
• Cooperative, mutual trust is the desired static of contracting
Effectuation • Flexibility and Adjustments provisions to cater for unanticipated contingencies
• Power to issue variations with associated time and cost adjustments
Dispute Resolution
• Relational Dispute Resolution
• Alternative Dispute Resolution
Table 2.4 Characteristics of Relational Contract and Construction Contract (adapted from Cheung 2001 – p.43)
Various authors have suggested that a relational approach to contractual
governance entails long-term social exchange between parties, mutual
trust, interpersonal attachment, commitment to specific partners, altruism
and cooperative problem solving (Blau 1963; Darwin 1994; Darwin,
Duberley & Johnson 2000; MacNeil 1978; 1985; Rousseau & Parks 1993).
Darwin and numerous other authors suggest that a relational approach is
closely associated with partnerships and strategic alliances (Jorde &
Teece 1989; Kanter 1989; 1994; Lynch 1993), with contractors who avoid
adversarial approaches to contract management (e.g. Lorenz 1991;
Stinchcombe 1986; Teubner 1991) by emphasising the ‘stable bonding
mechanisms’ (Bolton, Malmrose & Ouchi 1994) which entail long-term
collaborative arrangements based on informality, shared problem solving,
reciprocity and high trust. MacNeil (1985) suggests that construction
contracts are typical relational contracts as they often involve numerous
parties and subcontracts with heavy informational exchange in the
construction activities. The parties involved are mutually dependent. The
extent of mutuality and interdependence and the need for trust and
cooperation are greatly heightened (Cheung 2001).
CHAPTER 2 PARTNERING, ALLIANCING & RELATIONAL CONTRACTING
23
According to Rahman and Kumaraswamy (2002), relational contracting
considers contracts as the ‘ongoing dynamic state’ of relations among the
contracting parties and promises to do something in the future (MacNeil
1974), in the process of projecting ‘exchange’ into the future (MacNeil
1980). Rahman and Kumaraswamy (2002) point out that no real life
human cooperation will be entirely transactional - personal relations,
diffuse communication and some non-economic personal satisfaction will
be involved. Equally, contractual relations will not be entirely lacking in
transactional discreteness. Accordingly, MacNeil (1978) classified
contracts into three types: classical, neoclassical, and relational. Classical
contracting covers all future contingencies, and transactions tend to be
self-liquidating. Neoclassical contracting involves trilateral governance,
where third-party ‘assistance’ is employed in resolving disputes and
evaluating performance. Relational contracting provides the means to
sustain ongoing relations in long and complex contracts by adjustment
processes of a more thoroughly transaction-specific, ongoing
administrative kind.
Industry-wide studies have pointed out that a more efficient construction
industry would be achieved if a cooperative style of contracting were used.
Two major studies in quality and efficiency of the construction industry
commissioned by the government were carried out in the UK. The Latham
Report (1994) highlighted 30% reduction in construction costs as an
attainable goal while the Egan Report (1998) forecast annual reductions of
10% in both construction costs and time. The common theme in their
recommendations is replacement of competitive tendering with long-term
relationships.
Partnering is a good example of practicing relational contracting principles
(Rahman & Kumaraswamy 2002). Thompson and Sander (1998)
observed that benefits from partnering (i.e. relational contracting) increase
with a migration of teamwork attitude from competition to cooperation,
CHAPTER 2 PARTNERING, ALLIANCING & RELATIONAL CONTRACTING
24
through to collaboration and finally to coalescence. Rahman et al. (2001)
argued that more relational and performance oriented contractor selection
would encourage an amicable relational contracting environment and
more collaborative teamwork. Rahman and Kumaraswamy (2002)
suggest relational contracting approaches should work in almost any
environment if applied properly. However, this requires transforming
traditional relationships towards a shared culture that transcends
organisational boundaries (CII 1996), where the motivation and attitude of
the project participants are also critical.
2.5 Conclusion
Alliancing, partnering and relational contracting all have a common theme,
which is to move away from adversarial relationships, to develop a team,
perhaps a long-term relationship (e.g. long-term work relationship). From
the previous literature review, it is not difficult to see that both alliancing
and partnering are heading toward the concept of relational contracting. A
long-term relationship has always been a main element in relational
contracting. In order to build up a long-term relationship between two
parties, trust is essential.
Unlike traditional contracting, relational contracting allows a much higher
flexibility, which is suitable for the construction industry where there are
many uncertainties as well as many unforeseeable events. Also with
relational contracting, a lower construction cost may be obtained. With
traditional contracts, if contractors are not able to get their work done on
time according to the contract, they will suffer liquidated damages and in
most cases, arbitration or litigation will also be involved. Because of the
involvement of legal practitioners, works may be delayed and the
construction time extended since work will be postponed until proceedings
are completed and results known. For example, it is not uncommon for an
arbitration to take at least one year before the decision is made.
CHAPTER 2 PARTNERING, ALLIANCING & RELATIONAL CONTRACTING
25
With the high flexibility in relational contracting, construction time will be
shortened, as less documentation passes between parties when an
unexpected event occurs during construction; and solutions are negotiated
around a table. Also, it might minimise the necessity for extensions of time
for works since the contractor has more flexibility in re-scheduling the
work.
Without the aggravation of hearings, claims and damages, a better
relationship is built up between the client and the contractor. The trust in
each other becomes stronger and the contractor is willing to work for the
client in a better and more efficient way, while the client is willing to give
the contractor more work in the future. A mechanism for dealing with this
in Hong Kong government contracts is the appointment of an alternative
dispute resolution adviser. The role is one of arbiter between the two
parties but this is still, essentially, an adversarial approach – although a
skilled advisor can draw the parties together into an informal, relational
approach. Such a role could be fitted ‘on top’ of a relational contract to
help steer it after the project workshop has been completed.
However, a recent case study carried out by Darwin et al. (2000) on ten
clients from the public sector and contractors in the U.K., shows that it is
not desirable to have a pure long-term relationship from both clients’ and
contractors’ point of view. It is also necessary to have contracts drawn up
in black and white .
Due to human nature, while parties may be moving along with the main
purpose of relational contracting, legally binding documents are also
necessary for both parties to feel secure and to ensure work is
‘guaranteed’. Also, for the public sector, a transparent system is required
as the government needs to report to the public. For questions such as
‘what if that does not happen…’, some contracted terms are needed to
CHAPTER 2 PARTNERING, ALLIANCING & RELATIONAL CONTRACTING
26
reassure the public. Research has demonstrated the importance of
legislative constraints upon the application of partnering in the public
sector (Loraine 1993).
Pure ‘buddy buddy’ relationships do not exist in the commercial world.
There is never complete trust. A structured legal framework where roles
and protocols are defined can provide a level playing field for all parties,
as well as the initial bonding of the relationship between parties.
Culture is another issue. Without knowing much about or having much
experience with the contractor, the client may have doubts about the
trustworthiness of the contractor. One may argue that pre-qualification
addresses this issue, however, further research may need to be carried
out on the effectiveness of pre-qualification in respect of relational
contracts.
Contractors have traditionally taken every chance to increase their income
during work, and this has been part of the culture in the construction
industry – see, for example, the CIRIA report on management contracting
(1983). However, if once the contractor knows there will be more work
with the client in the future, it is highly likely that he would look at the
relationship from a long-term perspective rather than concentrating on
seeking more money during work as a short-term response.
It is comment believe that in the past everything was simple and people
had a much stronger sense of trusting one another, whereas now, every
party tries to get the most out of the other. Because of such human
behaviour, workshops evolve with the aim of trying to build up the team
spirit as well as trust in each other. Yet, the objectives of the workshops
need to be implemented continuously or the results will fade and the whole
program will become a failure. In this case, it depends very much on the
approach to future development and implementation.
CHAPTER 2 PARTNERING, ALLIANCING & RELATIONAL CONTRACTING
27
After all, ‘Business is business’, which also describes the current industry
culture as a whole.
29
CHAPTER 3
CULTURE
3.1 Introduction
Culture is a difficult and complex concept. It is socially transmitted
behaviour patterns, beliefs, thoughts and values. It is learnt and built over
time, and passes on from generation to generation.
Culture is predominating attitudes and behaviours that characterise the
functioning of a group or organisation. National and organisational culture
cannot be studied in isolation. National culture has an effect on
organisational culture. National culture defines boundaries of behaviour,
based on characteristics of interrelations and assumptions. Organisation
culture is an interconnected web of relationships. This chapter aims to
break down the concept of culture, also to identify the elements that have
an influence on culture.
3.2 What is Culture?
It is recognised world wide that culture is a difficult and complex concept.
In the broadest sense culture refers to the way of life of a group of people:
CHAPTER 3 CULTURE
30
patterns of behaviour that are seen to be useful and valuable to the people
concerned and worthy of being passed on from one generation to another.
Figure 3.1 presents a general idea on types of culture.
Figure 3.1 Types of Culture, based on Systems Theory
Culture takes time to evolve. It also takes time to change, or to evolve a
‘new’ culture. It is very difficult to define each type of culture on its own.
No matter which type of culture we look at, they all overlap with each other
and cannot be separated from one another. Culture needs to be looked at
as a WHOLE.
American anthropologists, Kroeber and Kluckhohn (1952), presented 160
different definitions of culture. Bodley (1994) drew out a simple version by
stating that culture involves what people think, what they do, and what
they produce. The concept of culture has also been identified in literary
traditions and philosophy (Jenks 1993; Williams 1988). Jenks (1993)
argues the term ‘culture’ became widely accepted due to the changes to
the structure of social life during the industrial revolution.
World
Nations
Professions
Organisations
Project Teams/Groups
Individuals
CHAPTER 3 CULTURE
31
3.3 National and Organisational Culture
Culture can be broadly defined as the dominant set of learnt, shared and
interrelated behaviour within a society (Vecchio, Hearn & Southey 1992).
Terpstra and David (1985) also see culture as a compelling set of
symbols, which provides a set of orientations for members of a society.
When taking these orientations together, solutions are provided to
problems that all societies must solve if they are to remain viable. As
suggested by Punnett (1998), culture is interrelated and provides
orientation to people.
Owens (1987) and Schein (1990) examine organisation culture as patterns
of shared beliefs and values that evolve into norms of behaviours, which
are adopted in solving problems. Rousseau (1993) sees culture as layers
of elements, which all lie along a continuum of subjectivity and
accessibility. These layers range from physical manifestations of culture
to fundamental assumptions, which are hidden deeply in the centre of
culture and are most difficult to uncover (Thorsdottir 2001). Trompenaars
(1994) describes culture using an onion, which has many layers. The
products of the basic values are on the outer layer and assumptions are
deep inside the onion, which coheres with Rousseau’s view on culture.
Schein (1990) proposes three levels in organisation culture – surface (by
means of structure and rules of conduct), organisation values and
underpinning assumptions, as also suggested by Wool et al. (2001).
CHAPTER 3 CULTURE
32
Figure 3.2 Components in an Organisational Culture (adapted from Organisational Behaviour: A Global Perspective by Wood et al. 2001 – p.293)
Culture is knowledge, behaviour and value, and is evolved over time.
Culture is built over time (Handy 1985). National culture has an effect on
organisational behaviour. It creates divergent mindsets regarding
characteristics of interaction and assumptions defining the boundaries of
behaviour (Vecchio, Hearn & Southey 1992). Assumptions amongst the
subordinates are also made. For example, Australians would expect open
and honest communication, and are not afraid of confrontation; for Asian
people, there should be no direct confrontation with superiors, relationship
and job security are placed in a very high position; whereas the English
have a strong sense of pride and would show their politeness to others,
despite a strong sense of distrust. In essence, national culture influences
the attributional basis for evaluating behaviour and the consequences of
behaviour (Vecchio, Hearn & Southey 1992).
As shown in Figure 3.2, the surface aspects of organisational culture relate
to observable culture. These are the methods that the group has
developed and are learnt by new members (Wood, Wallace & Zeffane
2001), where the behaviours are visible and can be clearly seen. The
observable aspects of the culture emerge from the collective experience of
OBSERVABLE CULTURE
SHARED VALUES
COMMON ASSUMPTIONS
Deeper/hidden Aspects
Surface aspects
CHAPTER 3 CULTURE
33
its members. Some of these aspects may be observed from day-to-day
practice; others may have to be discovered by asking subordinates about
past events and the history of the culture. Going further down, the next
level in culture is shared values between members in an organisation.
Shared values play a critical part in linking people together. They also
provide a set of orientations for members of a society. These orientations,
when taken together, provide solutions to problems that all societies must
solve if they are to remain viable. As suggested by Punnett (1998), culture
is interrelated and provides orientation to people. However, the shared
values may not be agreed by every member in the organisation, but they
have all been exposed to the values and have often been reminded that
they are important (Wood, Wallace & Zeffane 2001). While at the deepest
level of culture analysis, there are common assumptions or truths
developed and shared by members through their joint experience in the
organisation. Culture is learnt, shared and interrelated.
Organisational culture is an interconnected web of relationships (Tierney
1988). Based on Roger Harrison’s work, Handy (1985) identifies four
primary forms of organisational culture.
CHAPTER 3 CULTURE
34
• Power Culture – which is configured as a
web with the primary power at the centre,
and is frequently found in entrepreneurs;
• Role culture – in which functions and
professions provide the structural pillars to
support the overarching top management,
and is typical of public service
organisations;
• Task culture – in which the structure can be
represented as a net and is job or project
orientated, such culture can usually be
found in a matrix organisation; and
• Person culture – in which people interact
and cluster relatively freely.
Although national culture and organisational culture cannot be studied in
isolation from each other, there is a clear distinction between the two types
of culture. It is important to understand the connections between
organisational culture and national culture because organisational culture
frequently derives from national culture. Many of the shared beliefs and
values that develop in organisations can be traced to commonly held
assumptions in society (Wood, Wallace & Zeffane 2001). Organisations
seek commonality of beliefs and values amongst personnel which accord
with the beliefs of the organisation, while people retain levels of
individuality which impact on organisational performance (Liu & Fellows
1996). National culture is where people in the same nation share the
same beliefs, values and practices. It creates divergent mindsets
regarding characteristics of interaction and assumptions defining the
boundaries of behaviour (Vecchio, Hearn & Southey 1992). National
culture is learnt early in life without awareness. It is reflected in the
�
CHAPTER 3 CULTURE
35
behaviour and reinforced by rules and procedures. For example, in
Germany, business plans would be for twenty or even fifty years in the
future, whereas in America, the business planning intervals are often much
shorter.
Organisational culture is where beliefs, values and practices are shared by
most members of an organisation. Like national culture, each organisation
has its own unique culture. Members of an organisation need to learn
their own culture. When one moves to a new organisation, one needs to
learn the new rules of the new culture. Compared with national culture,
organisational culture is acquired at a later stage in life at a conscious
level. Also, values change when the top management introduces new
beliefs and attitudes to the subordinates. National culture is originated
from the root and is more difficult to change than organisational culture.
National Culture Organisational Culture
• Share same beliefs, values and practices
• Share same beliefs, values and practices
• Nation • Organisation
• Learnt early in life • Learnt at a later stage in life
• Learnt subconsciously • Learnt at conscious level
• Difficult to change • Changes when moving to a new organisation or when new beliefs or attitudes are introduced by top management
Table 3.1 Comparison between National Culture and Organisational Culture
National culture is reflected in organisational culture. Members of an
organisation would resist plans to impose a culture which does not reflect,
or which goes against their national values (Laurent 1986). Although
organisational culture values are learnt later in life at the workplace, they
also have an influence on behaviour, just as national culture does. The
extent to which the individual is influenced by the organisational culture
CHAPTER 3 CULTURE
36
depends very much on how long he/she has stayed with the organisation
(Mead 1998). The organisational culture would have a much stronger
influence on a long-term employee than a ‘job-hopper’, who moves rapidly
between companies. After all, culture takes time to ‘root’.
3.4 Culture and Value
To many scholars, sharing common values lie at the very heart of culture.
Hofstede defines culture as including systems of values. Indeed, if culture
is viewed as an emergent social process, values are very important
because the values of the collective form the foundations of an emerging
culture (Root 2000). However, as with culture, values are very
complicated and cannot be easily defined. In human society, the removal
of value means no value judgments and so, no quality (Pirsig 1974; Root
2000). All that remains in an imaginary world of no art, variety or trade, is
pure science, mathematics, philosophy and logic. Of course, there are
certain concepts within the mind that are not affected by the removal of the
‘value’ concept because they are not part of the physical perceived reality;
yet other concepts such as love, which has a strong relationship to objects
in the world, are greatly affected (Root 2000).
Value is a set of relationships between the mind (self) and the world
(Morrill 1980; Pirsig 1974; Robinson 1964). If values are purely subjective,
they can then be equated with the satisfaction of a felt need or an object
being of interest (Perry 1954). It was argued by Pirsig (1974) and
Robinson (1964) that value then just becomes a term for anything the
individual likes, and is meaningless within a social group. On the other
hand, if values are objective, they can be described as self existent
essences whose reality is independent of the feelings of the observer
(Morrill 1980). Again, Pirsig (1974) argues that the world can be split into
subjects and objects; quality and values cannot be measured objectively
due to their subjective nature and cannot be subjective because they are
CHAPTER 3 CULTURE
37
linked to the object. Morrill (1980) attempts to overcome this paradox by
quoting Niebuhr (1960):
‘That value is present wherever an existent being with capacities and
potentialities confronts another existent that limits or completes or
complements it. Thus, first of the fittingness or unfittingness of being a
being’
Morrill continues:
‘this relational perspective suggests that value is neither an exclusively
subjective or objective reality. Elements from each of these views need to
be incorporated into an adequate theory. Value is understood best as
arising in a relation among beings. As such, value is not simply a function
of preference or desire. … it is difficult to conceive of worth or value as
independent of the potential or structure of some particular being. Value,
then, is always for someone or something and is not a self-sufficient reality
or ideal’.
As pointed out by Morrill (1980), value is something neither subjective nor
objective. Root (2000) suggests existentialism provides a way out of the
paradox by quoting Magee (1988) that ‘the objects of our consciousness
do exist as objects of consciousness for us’. By accepting the said
proposition, no further assumptions on existence of values need to be
made. Culture may be viewed as an object as long as it is treated as our
consciousness and is real in its effects (Root 2000).
In sociological terms, an individual is ‘cultured’ when the valuing process is
conscious. Taking a child as an example, the valuing process of a child is
flexible and depends highly on context; food is valued highly when hungry
but once fed is negatively valued (Rogers & Stevens 1967). At the early
stage, values are driven by organism, representing a clear approach to
CHAPTER 3 CULTURE
38
values. As the child develops, the valuing process becomes dependent
on the external environment. The child learns the good and the bad from
others and absorbs them as his/her own values. The valuing process
changes from organism-driven to being dependent on the norms of
behaviours/values expected by - others (Rogers & Stevens 1967; Root
2000). Such ideas align with Terpstra and David’s (1985) belief – culture
is learnt.
However, the mechanism for acquiring values is dependent on the
collective level of mental programming (Hofstede 1980), which
distinguishes people from one group to another, by classifying groups. It
does not only focus on an individual, but individuals with similar cultures
would cluster together and form groups of different cultures. Some
successful organisations share some common cultural characteristics.
Organisations with strong cultures possess a broadly and deeply shared
value system (Mead 1998; Wood, Wallace & Zeffane 2001).
3.5 Culture Dimensions
Cultures vary in their underlying values and attitudes (Wood, Wallace &
Zeffane 2001). The way people think about such matters as achievement
and work, wealth and material gain, risk and change may influence how
they view work and their experiences in organisations. Using an example
of Western and Asian culture, a Western manager may value autonomy
and therefore not provide detailed operational directions to his Asian
subordinates. Using the findings from a study conducted by Hofstede in
early 80’s, Koreans are found to be collectivists, whereas Americans are
individualists. In this case, the subordinates may look up to the manager
for his directions with total respect. Because of the culture differences,
when the subordinates do not perform appropriately, the manager may
attribute this to their incompetence, and the subordinates may come to
believe the manager cannot be trusted. These consequences then act to
CHAPTER 3 CULTURE
39
reinforce cultural stereotypes and in turn lead to more divergence between
cultures and increase misunderstanding (Vecchio, Hearn & Southey
1992).
As mentioned earlier, one of the most ambitious studies of how cultural
differences relate to organisational issues was undertaken by Hofstede in
forty different countries. He developed a framework that offers an
approach for understanding value difference across national cultures.
Based on his findings and evidence in the field of cultural differences,
Hofstede (1980) identifies four cultural dimensions. The four dimensions
used to differentiate between cultures are:
3.5.1 Large or Small Power Distance
Power distance reflects the degree to which a society accepts a
hierarchical system and unequal distribution of power. Large power
distance indicates larger inequalities between the members in these
societies with power and those without. People in these societies also find
it normal that usually a small number of people have much power while
most of the people have less power. In countries with small power
distance, the basic idea is that in principle, everybody is born equal.
3.5.2 Masculinity vs. Femininity
Masculinity reflects the degree to which a society defines achievement in
terms of success and the acquisition of money or material possessions.
Some societies with sharp and strict divisions turn masculine; others when
the divisions are loose and blurred turn feminine. In masculine societies,
people admire the ones who have success. In feminine societies, people
pursue a different set of values such as relationship orientation, concern
for quality of life, modesty and caring.
CHAPTER 3 CULTURE
40
3.5.3 Individualism vs. Collectivism
Individualism reflects the degree to which a society values independence
from group membership. It is concerned with the form and manner of the
relationship between an individual and others in the society. In
individualist cultures, people are supposed to look after themselves and
their direct families only, people are expected to conform; while in
collectivist cultures, people belong to larger group (e.g. in-group, extended
family, etc.) which takes care of their interests in exchange for loyalty, and
relationships are more tightly structured.
3.5.4 Strong or Weak Uncertainty Avoidance
Uncertainty avoidance reflects the degree to which a society tolerates
ambiguous situations and the extent to which it has created institutions
and beliefs to minimise or avoid these situations. In some societies,
people are socialised to accept ambiguity and uncertainty and do not feel
threatened. In others, uncertainty is seen as disruptive, and makes people
psychologically uncomfortable. Strong uncertainty avoidance societies
reduce uncertainty and limit risk by ordering and structuring things,
imposing rules and systems.
Hofstede’s later work with Bond (Hofstede & Bond 1988) produced a fifth
cultural dimension.
3.5.5 High and Low Confucian Dynamism
Confucian dynamism is associated with the teaching of Confucius. This
dimension is the degree to which people in a country emphasise values
associated with the future over values that focus on the past or present. In
societies with high scores on Confucian dynamism, people tend to be
pragmatic, future-oriented, and focusing on obligations and tradition;
whereas in those with low scores, people tend to be normative and short
CHAPTER 3 CULTURE
41
term oriented, quick results are expected and people are more concerned
for stability.
3.6 Commitment
Some successful organisations share some common cultural
characteristics. Organisations with strong cultures often also have a
deeply shared value system (Deal & Kennedy 1982; Wood, Wallace &
Zeffane 2001). According to Wood et al. (2001), unique, shared values
have the following benefits:
• provide a strong corporate identity;
• enhance collective commitment;
• provide a stable social system; and
• reduce the need for formal and bureaucratic controls.
Culture is a system of shared values that distinguish one group of people
from another (Fang 2001) and value can be explicitly or implicitly desirable
to individuals or groups, which also influences their selections of various
modes, means and ends of actions (Adler 2002). Value also provides a
guide for desired patterns of behaviour and explains why people
selectively attend to certain goals while subordinate others. A high level of
commitment by members also implies a strong value system within the
organisation. Individuals express culture and its normative qualities
through the values that they hold about life and the world around them
(Adler 2002). Meyer and Allen (1991) developed three measurements for
the levels of commitment in an organisation.
CHAPTER 3 CULTURE
42
Affective Commitment
It refers to the employee’s emotional attachment to the organisation. Employees with strong affective commitment continue employment with the organisation because they want to.
Continuance Commitment
It is based on the idea that the costs of leaving the organisation outweigh the opportunity costs of staying. Employees whose primary link to the organisation is based on continuance commitment remain because they need to do so.
Normative Commitment
It is based on the acceptance of the organisation’s set of values. Employees with a high level of normative commitment feel that they ought to remain with the organisation.
Table 3.2 ‘Types’ of Commitment Identified by Meyer and Allen
Affective, continuance and normative commitment should be considered
as components, rather than types of commitment because an employee’s
relationship with an organisation might reflect varying degrees of all three
(Allen & Meyer 1990). The identification of culture given by Liu and
Fellows (1996) reflects a similar theme. They find culture comprises a
shared understanding of what is correct, proper and normal for the
conduct of relationships and has both normative and behavioural
components. As commonly accepted by scholars, culture defines people’s
behaviour. A strong commitment to the organisation by an employee
results in behaviour such as getting to work on time, more flexible at work
hours to the organisation’s benefit, willing to take up tasks outside his/her
job specification, he/she is more self motivated, a good team player and
has good relationships with his/her subordinates. Although strong
commitment to the organisation by employees influences their
performance, Meyer and Allen (1997) argue continuous commitment to the
organisation is negatively related to job performance. The suggested
relation was observed in many studies for (for example, Konovsky &
CHAPTER 3 CULTURE
43
Cropanzano 1991; Meyer et al. 1989), but was also refuted by some
(Angle & Lawson 1994; Bycio, Hyackett & Allen 1995; Moorman, Niehoff &
Organ 1993). A strong positive relationship was found between affective
commitment and job performance (for example, Bycio, Hyackett & Allen
1995; Ingram, Lee & Skinner 1989; Konovsky & Cropanzano 1991; Leong,
Randall & Cote 1994; Meyer et al. 1989; Moorman, Niehoff & Organ
1993); similar results were found between normative commitment and job
performance (for example Ashforth & Saks 1996; Randall, Fedor &
Longenecker 1990), although the results were weaker than for affective
commitment. Rowlinson (2001) points out that organisational culture and
structure must be matched if employees are to retain commitment to the
organisation.
Clearly, a strong culture and value system can reinforce a remarkably
positive view of the organisation and its environment. However, a strong
culture can also be a double-edged sword, creating great resistance to
dramatic changes in an organisation (Wood, Wallace & Zeffane 2001).
Organisations with strong power dynamics and role prescriptions impeded
promotion of staff empowerment (Cunningham & Hyman 1999; Foster-
Fishman & Keys 1997; Goodstein & Boyer 1972; Gruber & Trickett 1987;
Serrano-Garcia 1984). Implementing changes to an organisation
effectively requires strong commitment from top management (Bresnen &
Marshall 2000c; Oakland 1993; Prabhu & Robson 2000; Zairi 1999).
Empowerment refers to ‘the process of gaining influence over events and
outcomes of importance to an individual or group’ (Fawcett et al. 1994).
Staff empowerment was cited as a powerful means to engendering
commitment (Walton 1985). Staff at lower levels feel they are given
greater responsibilities in decision making, which leads to more
commitment to the project and to achievement of its missions (McDonough
III 2000), leading to greater job satisfaction and sense of ownership. The
decision-making process in projects is shorter since local (hands on)
CHAPTER 3 CULTURE
44
knowledge is acquired (Griffin & Hauser 1996). Project staff work in a
more cooperative manner as a team and in so doing enhance project
process (Jassawall & Sashittal 1998; Moenaert et al. 1994) and project
performance such as timely completion (McDonough III & Barczak 1991).
3.7 Organisational Culture and Structure
In layman’s terms, culture is ‘how we do things here’, which has a huge
effect on a project’s success. Successful project delivery is greatly
influenced by organisational culture and structure.
In an unsuccessful project, it is often found that people in the project or the
organisation do not understand the organisational culture and the existing
culture is not supportive. Also, having a good procedure in place is the
first challenge; getting staff in the organisation or the project team to follow
it is another issue. We will take contract administration in the construction
industry as an example. Traditional contracting has an adversarial effect
on the project team, people tend to work in opposition to each other rather
than cooperatively as a team. However, like national culture, the
organisational culture also has an effect on the project team, the project
culture. Experience shows that project performance is largely hindered by
the parent organisation. It is commonly seen in a construction project with
a high staff turnover, when the parent company removes staff from the
project, especially when a new job arises. The new project member(s)
would need to learn about the project including the problems facing it and
its history, as well as building up their relationships with the project team.
If the parent organisation has a culture of communicating in black and
white, with everything being referred to the contract document; staff
working on the project will do the same. Rather than concentrating on
working efficiently and effectively on the project work, staff spend a large
portion of their time on correspondence, ‘fighting the paper war’, with
letters back and forth between the contractor and the client representative.
CHAPTER 3 CULTURE
45
Organisational structure also plays a major role in project success. It is
the way in which the interrelated groups of an organisation are
constructed. Yet to develop or to change an organisational structure takes
much less time when compared with organisational culture. Changes in
organisational structure can also be carried out more frequently e.g. by
changing the organisation chart.
Organisational structure can be based on organisation size, number of
supervisory levels, number of sections and job titles, number of operating
sites, administrative intensity (based on the supervisor-staff ratio, spans of
control by top manager and the percentage of supervisors above the
bottom level supervisors), number of divisions and the form of department
(e.g. functional, project, product, or matrix forms) (Blau & Schoenherr
1971; Galbraith 1977; Galbraith & Nathanson 1978; Van de Ven & Ferry
1980).
3.8 Trust
Earlier in this chapter, the relationship between trust and culture was
briefly introduced. Trust is defined as the willingness to rely upon the
actions of others, to be dependent upon them and thus be vulnerable to
their actions (Wood & McDermott 1999b). Trust is also perceived as a
result of effective collaborative relationship and higher level of
partner/customer satisfaction (Mohamed 2003; Zineldin & Jonsson 2000).
Trust is seen as representing a ‘diffuse loyalty to the organisation’ which
prompts the individual to ‘accept, as the occasion demands,
responsibilities beyond any specific contracted function’ (Parson &
Smelser 1984). Moorman, Deshandè and Zaltman (1993) believe that
trust is built up over a series of interpersonal encounters, in which the
parties establish reciprocal obligations. However, Gambetta (1998) and
CHAPTER 3 CULTURE
46
his contributors see trust as a precondition of cooperation because
partners need some assurance that the other parties will not defect.
The traditional Chinese way of doing business exhibits a high level of trust
at interpersonal level. Trust has a very strong moral content when seen in
the Chinese way (see Confucius [Lun Yu], 1979). Trust has the meaning
of integrity, as well as the meaning of trustworthiness and compliance. In
the Records of Historian, it states in a similar way ‘by commending the
soldier, the empire should trust him (in the sense of trustworthiness and
ability) with all his heart once he is recruited’ (Lau, 1999).
3.8.1 Implications of Trust
The implication of high trust is that one would be confident and
psychologically secure. One is more relaxed, less suspicious and
defensive towards the organisation one is entrusted to (Westwood 1993).
High trust between parties not only reduces the transaction costs, it makes
possible the sharing of sensitive information, permits joint projects of
various kinds, and also provides a basis for expanded moral relations in
business (Brenkert 1998).
Trust is said to have a direct effect on work group process and
performance, and in Dirks’ findings (1999), it is shown that better
coordination and greater efficiency are found in a high-trust group and
hence better performance. Barney and Hansen (1994) believe that a firm
characterised by a culture of trustworthy values and beliefs will often
behave with a strong form of ‘trust in exchange’ relationship.
Wood and McDermott (1999b) define trust from a social perspective with
the following statement:
CHAPTER 3 CULTURE
47
‘Trust is a multidimensional (Ganesan 1994; McAllister 1995; Sako 1992),
multifaceted social phenomenon (Fukuyama 1995; Misztal 1996), which is
regarded by some as an attitude (Flores & Solomon 1998; Luhmann
1979), by others as a personality trait (Wolfe 1976) and as a vital social
lubricant (Flores & Solomon 1998; Gambetta 1998; Luhmann 1979)’
3.8.2 The Nature of Trust
Ganesan (1994) and McAllister (1995) identified two dimensions of trust,
whereas Sako (1992) and Mittal (1996) have argued for three dimensions
of trust, namely competence (behaviour), motives (feelings) and
commitment (beliefs) (Wood & McDermott 1999a). Das and Teng (1998)
refer to trust as the expectation of positive motives (behaviour) of the
trustee, while Lewicki, Saunders and Minton (1999) see trust as positive
conduct, where morality comes from the individual. Trust also has a social
meaning concerning both individual and organisation. Social trust
described by Earle and Cvetkovich (1995) is a bridge from State A
(disequilibrium or non-normal) to State B (equilibrium or normal). It
constitutes the in-group and out-group theory where people will behave
differently in groups, and is culture-specific (Earle & Cvetkovich 1995;
Fukuyama 1995). Nevis’s model of hierarchy of needs shows that social
need is higher in Chinese culture than in western culture.
Trust is also seen to have different levels, which is an essential
precondition for a successful negotiation (Fisher & Ury 1981). It is
interesting to see how and where trust is implied in different cultures.
French negotiators may come to the table mistrusting the other party until
they can establish an element of trust, while American negotiators may
come fully trusting the other unless led to believe that the other person is
untrustworthy (Jackson 1993). Japanese tend to have a tolerance of
ambiguity and rely on mutual trust while facing internationalisation of
business. Westwood (1993) finds this is a way of avoiding making
CHAPTER 3 CULTURE
48
offensive statements. Many managers in Asian countries negotiate in a
subtle and indirect manner to avoid confrontation. The Chinese
negotiation process is in an order of preference compromising: avoiding,
accommodating, collaborating and competing (Westwood 1993), with
competing being the last resort (Lau 1999).
Trust is described as calculative, with constitute of self-interest and vest
benefits in the economic dimension (Williamson 1975; Williamson 1985).
Williamson (1993) further suggests two other kinds of trust, namely
personal and institutional. Personal trust is suggested to be non-
calculative and is irrelevant to commercial exchange; institutional trust
refers to the social and organisational context on a contractual basis (Sako
1992; Williamson 1993). In management, Deming (1994) states that trust
is mandatory for optimisation of a system where a network of
interdependent components works together to try to accomplish the aim of
the system. In organisational management, trust is shown in the form of
achieving results, demonstrating concern and possessing integrity (Shaw
1997), and in an employee’s perception of trust in performance appraisal,
trust is measured by ability, benevolence and integrity (Mayer & Davis
1999). These items are measured as antecedent factors (Wong, Then &
Skitmore 2000) for trust relationships in order to evaluate trustworthiness
between trustor and trustee.
Trust is particularly important when a relationship contains the following
elements:
• entering into any form of contract;
• exchange of information;
• uncertainty arising from unforeseeable future contingencies;
• risk sharing;
• a degree of interdependence between agents;
• the threat of missing opportunities;
CHAPTER 3 CULTURE
49
• acting as a means of enhancing the effectiveness of a relationship
that depends upon extensive cooperation at both inter-
organisational and intra-organisational levels;
• developing the business relationship to a higher level;
• reaching alternative goals by group members;
• negotiating to avoid confrontation.
3.9 Culture and Trust in the Construction Industry
Construction project teams are unique entities, created through a complex
integration of factors, with inter-disciplinary players, and varying roles,
responsibilities, goals and objectives (Goodman & Chinowsky 1996).
Collaboration and teamwork are therefore crucial since sharing up-to-date
information between participants leads to minimising errors, reduction of
time delays and breaking the widespread rework cycle. Benefits of
collaborative, rather than adversarial, working relationships within
construction organisations are well documented (Walker & Hampson
2003).
Successful collaborative relationships rely on relational forms of exchange
characterised by high levels of trust. Higher levels of trust encourage
more open communication between individuals (Argyris 1973; Ruppel &
Harrington 2000), which subsequently increases understanding of other
parties’ perspectives (Johnson & Johnson 1989). Hosmer (1994a,b)
suggests trust leads to commitment, which in turn leads to enthusiastic
cooperative and innovative effort in people. However, it has been shown
in the past that the construction industry has a stronger preference for
distrust rather than the full benefits of cooperation (Wood & McDermott
1999a). There is a need for culture change to bring about increased
cooperation between parties on a long-term basis. With relational
contracting, based on the long-term relationship and trust, a win-win
situation can be created for both the client and contractor. The
CHAPTER 3 CULTURE
50
development of trust between organisations is seen as a function of the
length of the relationship between them (Bresnen & Marshall 2000c). It is
also believed that the construction industry is one that requires more trust
between parties due to the high uncertainty in the industry.
Partnering has been criticised as benefiting the clients’ side only (Green
1999). Bresnen and Marshall’s work (2000c) shows that contractors would
absorb extra costs in the interest of maintaining good relationships with the
client and increasing chances of gaining future work. Yet, one may ask
why contractors are still involved if they would not gain any benefits. The
reason behind this may be the global pressure for change. Partnering is
seen to be a pre-qualification requirement in recent years.
In reality, the client would try to spend as little money as possible to get
the work done; whereas the contractor would want to earn as much as
possible from the project – reflecting a part of human behaviour from an
economic point of view, that all human beings are selfish. In order for the
client to maximise its benefits, a choosing mechanism is required where
the contractors compete for the project. Tendering is the most common
approach used in the construction industry. The norm behind the
tendering process is that the lowest bid wins the contract. The downside
of this mechanism is the lower the proposed project cost, the higher risk
for work to result in low quality with extra costs incurred during and/or after
work. After all, the contractor also runs a business, and would not carry
out work which would result in a loss. Rather, a minimum amount of profit
to be made is set. With a low bidding price on the tender, what is most
likely to happen is cost cutting on items such as labour cost, affecting the
quality of labour (something which is difficult to state in the contract) with
extensive sub-contracting, which makes work difficult to supervise and has
a great impact on the quality control of work done. Also, the suppliers of
materials chosen might be of poor work performance with no guarantee of
CHAPTER 3 CULTURE
51
prompt delivery of materials. Such problems have been solved by
implementing a pre-qualification system – ISO certification.
The quality certification system, ISO 9000, is widely used as a pre-
qualification before selection of tenderers in Hong Kong. In the Hong
Kong public housing sector, ISO certification is a requirement for all
contractors and suppliers before they apply to be included on the ‘Control
List’.
The fact is that ISO certification does not really help the company to
achieve a higher standard of quality, but is rather a mechanism for
generating more paper and consuming time, however they still fight to get
a certificate in order to promote greater job opportunities. Indeed, results
have proved this strategy on pre-qualification for high quality and
productivity has not been very successful. Partnering seems to follow the
same track. Even though contractors suspect they will not get much
benefit from partnering, they still enter into partnering arrangements
because many job opportunities will be missed if they do not. Partnering
has even been called a ‘brand label’ (Liu & Fellows 2001).
However, with relational contracting, it benefits not just the clients but also
the contractors because of high chances of future work. Maintaining a
good relationship to sustain a long-term relationship is believed to lead to
reduced tendering cost, by means of lower transaction costs, which
benefits both the client and the contractor. A cynical view might be
expressed: first generation partnering suits the public sector as it provides
no guarantees of future work but commits the contractor to a non-
contractual relationship; alliancing suits the private sector as long term
business relationships and mutual benefits can accrue – in both cases
probity issues can be managed.
CHAPTER 3 CULTURE
52
Characteristics and benefits of relational contracting have been discussed
in Chapter 2 and they include long-term relationship, trust, commitment,
interpersonal attachment and cooperative and collaborative attitudes
towards problem-solving. Partnering, alliancing, Private-Public-
Partnership and joint-ventures are examples of relational contracting
approaches and were introduced to the Australian construction industry
during the 20th Century.
Studies show that role cultures are barriers to change (see Cunningham &
Hyman 1999; Foster-Fishman & Keys 1997 for examples). They are slow
to perceive the need for change and slow to change even if the need is
seen (Handy 1985). They are particularly unsuitable for a continuously
changing and competitive environment. Interactions in the organisation
between function groups and individuals are controlled by rules and
procedures, restricting staff empowerment, especially at the lower or team
levels. Role culture is often stereotyped as bureaucracy. On the other
hand, task culture is job or project orientated. This culture is extremely
adaptable; it reacts quickly to changes and is most appropriate where
flexibility and sensitivity to the environment are important (Handy 1985).
This culture suits the construction project team environment very well;
after all the whole emphasis of the culture is on getting the job done.
Project teams are formed for specific purposes and can be reformed,
abandoned or continued. Individuals in task cultures are found to have a
high degree of control over their work, can be judged by results, and have
easy working relationships within the project team with mutual respect
based upon capacity rather than status.
3.10 Conclusion
This chapter has explored prior research and theory into culture and has
discussed culture and trust in the construction industry. This chapter has
commented that national culture has an effect on organisational culture,
CHAPTER 3 CULTURE
53
which also has an effect on project culture. The industry has a stronger
preference for distrust rather than the benefits of cooperation. The need
for culture change to bring about increased cooperation between parties
on a long-term basis is identified. Benefits of relational contracting
approaches such as long-term relationships, cooperative and collaborative
attitudes towards problem-solving have been well documented. However,
tests of the efficacy of alliancing or partnering have so far produced mixed
results, and there is a scarcity of prior studies that have significantly
addressed the determinants of effectiveness in relational contracting in the
public sector. The following chapter presents the background of the
Queensland Departments of Public Works and Main Roads and the
historical background of project delivery systems in both organisations.
55
CHAPTER 4
BACKGROUND OF QUEENSLAND DEPARTMENTS
OF MAIN ROADS AND PUBLIC WORKS
4.1 Introduction
The Queensland Departments of Main Roads and Public Works have
identified the need to move towards more relational type of contracts.
Both organisations have their own definitions on relational contracting and
have experiences of partnering projects. This chapter presents the
historical background of both organisations’ project delivery systems and
the changes that have taken place.
4.2 Background of Queensland Department of Main
Roads
The Queensland Department of Main Roads (QDMR) is responsible for
the management of the 34,000 kilometre state-controlled road network,
including highways and other connecting roads in Queensland. This
involves planning, designing, building and maintaining the roads and
associated infrastructure (such as bridges). The road network is managed
to ensure it contributes to the State’s development and progress. QDMR
CHAPTER 4 QDMR & QDPW
56
is a technically oriented public organisation. The many roles played by
QDMR include (Manley & Hampson 2000):
• manager of the State-controlled road network;
• a leading industry client;
• a significant research provider;
• a designer, contractor, sub-contractor, trade-services provider,
consultant and technology provider1.
4.3 Project Delivery Systems
Competitive tenders are generally called for construction projects
managed by QDMR. A number of projects are delivered under sole invitee
contracts with local governments’ and QDMR’s own Road Transport
Construction Services (RoadTek) commercialised units.
QDMR has developed a manual for determining project delivery options
for major works and projects. Main Roads Project Delivery System
(MRPDS) consists of three volumes:
• Volume 1 – Selection of Appropriate Project Delivery Options
• Volume 2 – Tendering for Major Works
• Volume 3 – Major Works Prequalification System
MRPDS is used by those who are responsible for ensuring value for
money is obtained in the delivery of a project. The aim of MRPDS is to
provide guidance for the procurement of major works including:
• developing the best delivery strategy;
• how tenders should be called, compiled and assessed; and
• who should be eligible to tender.
1 Commercial arms within QDMR (RoadTek) operate in a competitive environment within the private sector and local governments.
CHAPTER 4 QDMR & QDPW
57
The manual provides guidance in developing an appropriate delivery
strategy for the implementation of road infrastructure projects. It provides
thorough guidance in the relational contracting process. A clear message
has been sent out to the construction industry that a culture change is
needed in the industry, where parties from the client to the supply chain
should be working in a cooperative and collaborative manner. QDMR also
believes that the client is the driving force for change and therefore QDMR
should take up a leadership role.
4.4 Partnering and Alliancing in QDMR
During the 60s and 70s, the design and construction of road works was a
well-defined process with engineering solutions and risks were exposed.
The works were either undertaken by day labourers or contracted out
under lump-sum or schedule of rates contracts. In the early 80s, there
was a downturn in road construction activity, with new players entering the
game. This caused an increase in the level of competition in the small
market, where the contractors bid low for the projects and recovered cost
by any means. The most common approach (as is still used widely in the
construction industry) is through claims and adjustment of the quality of
work. The consequence was that QDMR drafted tighter contracts with a
subsequent risk transfer. The relationship between parties turned
adversarial.
In the early 90s, partnering was introduced to Australia. QDMR has been
applying partnering in some road projects since the mid 90s. The
Australian Construction Association conducted an industry survey in 1998,
which found that relationship contracting is believed to be the way forward
in the Australian construction industry, echoing with the messages
identified in both the Egan Report and the Tang Report.
CHAPTER 4 QDMR & QDPW
58
QDMR defines partnering as a process applied outside the contract to
align the goals and objectives of the parties to the contract, to facilitate
good communication, teamwork and joint problem solving (QDMR 2003).
As stated clearly in MRPDS, partnering is not a form of contract, but a way
of conducting business. Partnering is a business strategy, not a contract
strategy.
When partnering was first adopted in QDMR’s projects in the mid 90s, it
was found unsuccessful in most of the projects. Continuous amendments
were carried out and the partnering process was reviewed. Realising a
more cooperative and honest environment is needed between the project
parties in order for the project to be successful and have a cost effective
outcome, QDMR has started to adopt a new approach to project delivery,
relationship contracting.
Project alliancing, a particular form of relationship contract, has been tried
and tested as a road infrastructure delivery system by QDMR since 1999.
As discussed in Chapter 2, unlike partnering, project alliancing is a type of
contract. One distinct clause in an alliance contract is a No Dispute
clause, where neither arbitration nor litigation may be used for dispute
resolution. All problems or issues must be solved at the broad level. The
No Dispute document was produced by NWPC in 1990 and was
recognised as a watershed report by the construction industry in Australia
(Skinner 2001). Key features such as more cooperation and better
relationships between parties and fairer risk allocation were highlighted in
the report, pushing forward the message on the urgency of change.
The current tender system for government projects mainly relies on the
lowest bid win. As identified earlier in this chapter, contractors have
become very competitive and have been offering unsustainably low tender
prices. Projects have often suffered from numerous unreasonable claims
and poor workmanship, followed by ‘paper wars’ between the contractor
CHAPTER 4 QDMR & QDPW
59
and the client, which escalated the development of an adversarial
environment in the project.
This happened until recently, when QDMR reviewed the tender process,
particularly the selection criteria. The weighting of non-price criteria on the
overall score has greatly increased. Non-price criteria include the claim
history in previous projects; project team relationship; and sub-contractors
relationship. A low-bid clause has also been implemented, where QDMR
has the right to reject any unreasonably low bid2. The revised tender
documents and tender evaluation system aim to trigger a change of
attitude in the contractors, before the project begins, also sending a clear
message to the industry. It voices the significance of relationship
management as seen by QDMR, and the urgency of a change of attitude
and culture.
4.4.1 Relationship Management
QDMR has a policy of including the supplementary specification for
‘Relationship Management’ in contracts with a value of $10M or greater
and a period of construction of 12 months or more. Some districts adopt a
partnering arrangement by agreement after contract award for projects of
lesser value and shorter construction periods. South East Region –
Metropolitan District has a section on Relationship Management in the
‘Infrastructure Delivery: Metropolitan District Supplementary
Specifications’.
The specification is intended to establish and maintain good relationships
between the parties within the contract. However, it does not replace
requirements detailed elsewhere within the contract such as the provision
2 10% or more below the median value. However, not all unreasonable low-bids are rejected. There is a clause of taking innovative advantage and process advantage into account during tender evaluation.
CHAPTER 4 QDMR & QDPW
60
of notices, information exchange and dispute resolution. The specification
details work operations including:
• Relationship Management Workshop – which is preferably held at
the beginning of the project, with duration of 1.5 days maximum.
Representatives of the Principal, the Superintendent and the
Contractor (the Team) attend a facilitated workshop where the
facilitator introduces the concepts of relationship management to
the workshop participants. The Team develops matrix resolution
and a relationship charter that sets the relationship goals and
objectives, core values and guiding principles.
• Team and Relationship Skill Building Activities – are carried out
during the Relationship Management Workshop, expertise and
skills are shared during operational and Relationship Management
meetings. Dinners and/or barbeques are held for informal
communication channels, which also help build up relationships in
the Team.
• Relationship Management Meetings – relationship objectives are
rated individually using a score sheet prior to the monthly
Relationship Management meeting. Scores are discussed during
each meeting, which also give participants a chance to raise any
comments or issues, including personality related issues.
Under the current system, Relationship Management is tendered on a
Lump Sum basis and payment for this item is made progressively, on a
monthly pro-rata basis. However, all facilitator fees are paid directly by the
Principal and are therefore not included in the Contractor’s Lump Sum.
CHAPTER 4 QDMR & QDPW
61
Type Description
Extended Partnering • Long project duration • Provision for Relationship
Management process in tender invitations/contract documents
• Foundation workshop (1.5 days with dinner)
• Monthly Relationship Management Meetings
• Skilling Workshop later in the project (1.5 days with dinner)
• Mid project review (to review project goals) for larger projects
• Project completion workshop (may or may not be incorporated)
Partnering Plus • Short project duration • Expanded Foundation workshop
(combining Skilling workshop) • Monthly Relationship Management
Meetings
Table 4.1 Formal Relationship Management Process in QDMR Projects
Standard forms of contract such as AS2124, AS4300, AS4000 or other
special forms such as Managing Contractor and Cost Reimbursable
Performance Incentive often have a degree of complexity and some
unknowns. As the degree of unknowns increases, the need for
collaboration and good relationships also increases. Adopting the formal
Relationship Management process in the project encourages positive
collaboration in the project team and development of good relationships.
The Queensland Department of Public Works also recognises the
necessity of culture change, both in the industry and in the organisation.
QDPW too believes the client should be the driving force for change and is
moving in a similar direction to QDMR. The following gives a brief
background of QDPW.
CHAPTER 4 QDMR & QDPW
62
4.5 Background of the Queensland Department of Public
Works
The Queensland Department of Public Works (QDPW) plays a major role
in the Queensland Government’s capital works building program. This
involves planning, designing, constructing and maintaining government-
owned facilities. QDPW is also responsible for information and
communication technologies in both private and public sector operations,
and Queensland’s cultural and historical records. QDPW is a managerially
oriented public organisation. The many roles played by QDPW include:
• manager of State-owned facilities;
• a leading industry client;
• a significant research provider;
• a designer, contractor, sub-contractor, trade-services provider,
consultant and technology provider3.
4.6 Project Delivery Systems
QDPW has produced some guidelines for determining project delivery
options on all building capital works projects and they include:
• Procurement Selection and Generic Contracts
• Building Industry Contractor Tendering and Selection Process.
Like most Queensland Government departments, publicly invited (open) or
select methods of tendering are generally used for building projects. The
choice on the methods of tendering depends on the project requirements,
and the assessed PQC (Prequalification System for contractors and
consultants) Service Risk Rating. 3 QDPW has five divisions (Building Division, Infrastructure and Major Projects, Queensland Purchasing and Queensland State Archives and Information Economy), six commercialised business units (Project Services, QBuild, QFleet, Goprint, SDS and CITEC) and six corporate and executive services units (Planning and Human Resources, Executive Services, Internal Audit, Legal and Contractual, External Relations and Finance and Information Technology).
CHAPTER 4 QDMR & QDPW
63
The project delivery systems used in QDPW can be classified as two main
types:
• Traditional – where the agency has full responsibility for the design
and documentation process and the contractor constructs for a
lump sum amount. An example is the Traditional Lump Sum
Contract, where the Principal provides detailed and comprehensive
construction documentation.
• Non-Traditional – where the contractor has varying degrees of
responsibility for the design and documentation process. Examples
include Design and Construction Lump Sum Contract, Design and
Construction Management Contract, Design and Construction
Management (2-stage tender) Contract, and Document and
Construction Management Contract, where the contractor or
managing contractor has total responsibility for design and
construction; Construction Management Contract, where the
construction manager is engaged to manage construction of the
project as well as providing advice during the project design.
The selection of project delivery system in QDPW is usually a four-step
process:
1. Determine project risk – whether the project is categorised as a low
risk or high risk/significant (HRS) building project;
2. Determine project time – by considering time allocation for design,
tender, construction and contingency such as wet weather,
disputes, variations etc.;
3. Evaluate project constraints and determine if traditional or non-
traditional project delivery system should be used – by evaluating
the project constraints, it will then be possible to determine the
importance of time, cost and quality and the potential risks
associated with adjusting these parameters; and lastly
CHAPTER 4 QDMR & QDPW
64
4. Determine type of non-traditional project delivery system – after
step 3, if the project is determined as a non-traditional project
delivery system, the Procurement System Matrix is used as a guide
to choose the type of project delivery system.
QDPW does not have a manual to determine the type of project delivery
system for each project. The choice of project delivery system relies
mainly on the risk assessment, rule of thumb from staff expertise, and
further consideration of the client basis (e.g. different government client
agencies), risk profile and scale of project. Major projects would normally
be carried out with non-traditional contracts, and traditional lump sum
contracts for minor projects.
4.7 Partnering, Alliancing and Relational Contracting in
QDPW
In July 2002, QDPW issued a policy statement on the tendering and
selection process for all Capital Works. It is clearly stated in the policy that
QDPW looks for an effective relationship with the construction industry.
QDPW believes that, to have a sustainable industry and an improved
service outcome for the Government, open, cooperative and non-
adversarial relationships are needed in building project. Project teams
with good relationships often achieve high performance.
From the statistics, traditional project delivery systems (e.g. traditional
lump sum contract, design and construct lump sum contract) often lead to
time and cost over-runs upon project completion, as well as creating an
adversarial environment for the project team. Knowing relationship
elements should be injected into the project documents, QDPW is heading
to more use of relationship-based contracts and less use of adversarial
contracts. The most commonly used relationship-based procurement
methods are partnering, relationship contracting and alliancing.
CHAPTER 4 QDMR & QDPW
65
In QDPW, partnering is understood as a tag on some forms of contract, a
third document. It is a business strategy, not a procurement strategy;
relational contracting is an agreement and obligation which binds the
contract, making sure the parties in the project team are working closely
together; alliancing is having an alliance with a company, without a fixed
price or a maximum price, but a target cost which usually also includes a
profit margin.
QDPW has carried out a large number of projects using the managing
contractor approach and good results have been achieved. Project teams
were found to work closer together in a more friendly environment and
better relationships were developed, compared with projects carried out
using traditional procurement methods. QDPW is aiming to put out more
contracts that approach alliancing. Most projects have been carried out
using traditional type of contract, based on AS 2124. Under AS 2124, the
Superintendent is not a party to the contract but a person named in the
contract by the two parties to the contract (the Principal and the
Contractor), although in reality, the Superintendent is nominated by the
Principal or client organisation. The major role of Superintendent is
carrying out administrative work and ensuring justice. Many have found
the Superintendent uncooperative, even rather obstructive, causing delays
in work and information transfer, due to the nature of this role.
4.7.1 C21 Construction Contract
Under a C21 Construction Contract, it clearly states that:
‘The parties must do all they reasonably can to cooperate in all maters
relating to the Contract, but their rights and responsibilities under the
Contract (or otherwise) remain unchanged unless the parties agree in
writing to change them.’
CHAPTER 4 QDMR & QDPW
66
Also,
‘Each party must do all it reasonably can to avoid hindering the
performance of the other under the Contract.’
C21 has a strong emphasis on cooperative contracting and has proven to
be highly effective (Department of Commerce 2003). Under C21, the
contractor carries out both design and construction works. Parties in the
contract must cooperate yet rights and responsibilities in the contract
remain unchanged. C21 offers a greater flexibility, the allocation of risk is
also much more clearly stated since the risks allocated to the contractor
are included in the obligations. The importance of good relationships
between contractor and subcontractors is also highlighted in the contract.
QDPW is moving in a direction very similar to C21, using C21-based
contracts as a driver for change of culture in the project team.
Like QDMR, most building projects with QDPW are awarded through the
competitive tendering system, where the lowest bid tender would win.
QDPW began implementing a 3-stage tendering system in late 2003.
Potential contractors are invited to a round table meeting, where two
contractors would be selected to attend a one-day workshop separately,
followed with an individual interview for the final decision.
CHAPTER 4 QDMR & QDPW
67
CONTRACT TYPE DESCRIPTION TENDER
PROCESS RELATIONSHIPS WORKSHOP
AS 2124 Principal's Consultant provides:
Competitive tenders
Adversarial None
(Traditional Lump Sum)
Project Brief, Schematic Design, Design Development, and Construction Documentation
Lump Sum - evaluation criteria (90% - 100% price; 0% - 10% non-price)
AS 4300 Principal's Consultant provides:
Competitive tenders
Adversarial None
(Design and Construct)
Project Brief, Schematic Design, Design Development, and Construction Documentation
Lump Sum
Managing Contractor
2-Stages Non-Adversarial Relationship team building workshops
(Design and Construction Management)
Stage I Competitive tenders (lump sum) for Design Fee, Documentation Fee and Construction Fee
Principal's Consultant provides:
Principal provides a Target Guaranteed Construction Sum
Project Brief and Schematic Design
Evaluation criteria (25% - 35% price; 65% - 75% non-price)
Stage II
Contractor's option on carrying out work on additional work list
Bonus sharing for actual costs of construction under Guaranteed Construction Sum
Alliance Schematic Design by Principal's consultants
Submissions called from alliance consortiums
Non-Adversarial Relationship / Team building workshops
Three levels of management: Alliance Board, Alliance Leadership Team and On-Site Project Team
Evaluation criteria (100% non-price)
No blame/No disputes clause
Ongoing facilitation by alliance facilitator / coach
Two consortiums are chosen
Workshops with Preferred consortium
Partnering Bolt-on to conventional conditions of contract
Non-Adversarial Partnering workshops
(NOT a contract) An agreement between parties to act in good faith
Not necessarily applied at the beginning of the project
Table 4.2 Types of Contracts Used in QDPW
CHAPTER 4 QDMR & QDPW
68
4.8 Conclusion
Both QDMR and QDPW have established methodologies for determining
when to use alternative project delivery systems and how to determine
which delivery system to use. QDMR’s approach is very structured
whereas QDPW’s is based on expertise. QDMR has established a
MRPDS manual, where the first volume of the manual deals with the
choice of project delivery system. Both departments have their own
definitions of partnering, alliancing and relational contracting (please refer
to Chapter 2 for details).
Traditional contracts operating under AS2124, AS4300, AS4000 or similar
were found to be adversarial. Contractors were selected mainly on the
basis of lowest price in a competitive bid and the Superintendents saw
their role as gatekeepers, safeguarding the client’s interest.
Partnering was implemented by putting a partnering agreement on top of
the traditional contract and encouraging contractor, consultant and client
to proactively address project risks, identify them before they affect the
project and take action, jointly agreed to manage the risk. It is seen as a
‘bolt-on’ to conventional conditions of contract. The problem with this
approach is the Superintendents have continued to see themselves as
gatekeepers rather than as team members, and the contractors have kept
one eye on the conditions of contract and claims, whilst going through the
partnering process.
Relationship management/contracting has been implemented by inserting
a provision in tender invitations and/or contract documents. Contractor
and Superintendent working as a team is a goal of Relationship
Contracting, with more open and cooperative relationships. Relationship
Management workshops and monthly Relationship Meetings are held
during the project, with project team including the Client Representative,
CHAPTER 4 QDMR & QDPW
69
the Principal, Superintendent, Superintendent Representative, Inspectors,
Contractor Project Manager and foremen. The project team is formed
after the contract award. An external partnering facilitator is employed to
facilitate the Relationship Management workshop held at the beginning of
the project; while monthly workshops are mostly led by the Principal or
alternated between the Principal and the Contractor Project Manager. No
further workshops or external facilitation would be held unless problems
are shown on the project team relationship. Although it is not stated in the
provisions, the Contractor is welcome to bring any major sub-contractors
to the RM workshop and monthly RM meetings. However, bringing sub-
contractors or consultants into RM workshops or monthly RM meetings is
still not a common practice in the construction industry. Some Contractors
believe that sub-contractors would feel uncomfortable being in an office
environment. Research shows that partnering should be moved down the
value chain to be truly successful. Innovative ideas and professional
advice are often received from the specialists, the sub-contractors. The
person who works 365 days on asphalt has to know more about asphalt
than those who do not work directly with it. Technical issues as well as
challenges ahead, which are often overlooked at the beginning, can be
picked up quickly by sub-contractors.
Consultants/Designers are often not brought into any of the meetings.
The quality of designs has raised concern in the industry. A similar tender
system is used for the consultants – the lowest bid wins. Designs are
often carried out by junior engineers, who have little experience. During
construction, design problems which should be addressed or noted during
the design stage or the refinement stage arise. Rather than getting it right
in the first place, resources are spent on rectifying the problems during
project construction, with huge amounts of time wasted on communication.
These are important issues which should be addressed, for the sub-
contractors have the insights on specific problems as well as offering
CHAPTER 4 QDMR & QDPW
70
innovative ideas; whereas rapid feedback and clarifications from
consultants are often major issues in all construction projects.
QDMR has no experience in alliancing contracts. However, both QDMR
and QDPW share the same definition of alliancing. Alliancing refers to
either a win-win or lose-lose situation with both client and contractor – risk
is shared and managed. There are three levels in an alliance project:
Project Alliance Board, Alliance Management Team and Project Team. All
three levels are formed before the actual construction begins. Project
Team members are chosen before the project begins. The Project Team
often involves Contractor, key Subcontractors, key Consultants, Principal
and Client. Also, during the course of the project, there is continuous
facilitation by an alliance facilitator/coach. Alliance contracting has only
been applied in large scale projects with high complexity, for a full-blown
alliance contract is a complicated contract which involves a high level of
commitment from all project members, and of resources. Various
professionals comment that alliance contracts should only be applied in
large-scale projects in order to balance the costs and benefits.
71
CHAPTER 5
RESEARCH MODEL AND METHODOLOGY
5.1 Introduction
This chapter details the research design and method developed to study
the determinants of effectiveness in relational contracting.
This research was carried out by investigating the national culture,
organisational structure, culture and commitment in two large public sector
organisations in Queensland, Australia, and to identify the key issues
affecting project performance. This research has adopted a triangulated
approach where questionnaires, interviews and case studies were
conducted in order to validate the results. Various scholars have been
critical of an often misplaced emphasis on quantitative elements of
research (Easterby-Smith, Thorpe & Lowe 1991). By employing both
qualitative and quantitative approaches, it helps to eliminate the
disadvantages of each, whilst gaining the advantages of each (Fellows &
Liu 1997).
CHAPTER 5 RESEARCH MODEL AND METHODOLOGY
72
5.2 Research Background
The implicated link between organisational culture and organisational
performance has long been recognised in both main-stream management
literature (Handy 1985; Hofstede 1980) as well as in the construction
management literature (Liu & Fellows 2001; Rowlinson 2001). Within the
construction research domain, the impact of culture and organisation on
project performance is becoming an increasingly important topic for the
establishment of a sound partnering or alliancing, or as referred to more
often in recent years, relational contracting, approach to projects.
However, the efficacy of alliancing or partnering has so far produced
mixed results (see for example Bresnen & Marshall 2000a,b,c) and this
research aims to shed light on the practice or pre-requisites for relational
contracting to be successful.
A number of characteristics for successful alliancing have been identified
in recent studies e.g. (Rowlinson 2001; Winch 2000; Winch, Millar &
Clifton 1997). These studies addressed change in the context of the
working relations in project organisations. The main parameters identified
as being significant in shaping how an organisation performed and the
spirit within the organisation were:
• Organisational Culture and Structure (assessed using Handy’s
instrument);
• Commitment (assessed using Allen & Meyer’s instrument);
• Organisation Assessment (assessed using Van de Ven & Ferry’s
instrument); and
• National Culture (assessed using Hofstede’s VSM).
Each of these four variables already has well developed measurement
instruments that could readily be adapted to the Queensland construction
industry to study the collaboration process. By investigating the impact of
CHAPTER 5 RESEARCH MODEL AND METHODOLOGY
73
the various cultural variables on project performance, it would be possible
to define patterns in which relational contracting works most effectively.
Organisational culture and organisation structure must be matched if
participants are to retain commitment to the organisation (Rowlinson
2001). This research takes Rowlinson’s work as a starting point and
develops it further into a study of the key determinants of effectiveness in
relational contracting.
The following research objectives and hypothesis were identified during
the literature review.
5.2.1 Objectives
The objectives of this research are:
• To investigate how a collaborative project culture is developed and
enhanced by considering the set of project team characteristics;
and
• To identify the ways in which collaboration can be transmitted
throughout the industry.
5.2.2 Hypothesis
The problems to be addressed in this research are:
• How is a collaborative project culture developed and enhanced by
considering the set of organisational characteristics, project team,
characteristics and national culture?
• What are the ways in which collaboration can be transmitted
throughout the organisation?
The hypotheses to be tested in this research are:
CHAPTER 5 RESEARCH MODEL AND METHODOLOGY
74
• Organisational culture and organisation structure must be matched
if participants are to retain commitment to the organisation
(Rowlinson 2001).
• Parent organisation culture affects temporary project culture.
• Encouragement by organisation to exhibit cooperative behaviour
amongst employees leads to greater cooperation between
individuals
5.3 Research Methodology
The following research model was developed after a review of the
literature as detailed in Chapters 2-4.
Figure 5.1 Research Method
Questionnaire Interviews
Analysis & Testing Chi-square test and
Correlation Analysis
Results Relationships between
commitment, organisational culture, national culture and
organisational structure
Results Patterns on good and
bad practice
Theory and Literature Rowlinson’s Work in
2001
Mapping of Research Findings
Research Outcome Enhance the understanding of the team working process
Understand the dynamics of the team and a profile of projects, participants and procurement systems Identify commonly recurring themes and situations that reflect good and bad practice
Distinguish the determinants of effectiveness in relational contracting
Case Studies
Qualitative Data Quantitative Dat a
CHAPTER 5 RESEARCH MODEL AND METHODOLOGY
75
The research was broken down into two distinct phases:
• Investigation of the impact of the various cultural variables on
project performance (Culture Questionnaire and follow up
interviews);
• Analysis of the variables influencing the success of relational
contracts (interviews and case studies).
Questionnaires, interviews and case studies were conducted in this
research in order to validate the results. Both qualitative and quantitative
approaches have different strengths and logics, and are best used to
address different questions and purposes (Maxwell 1996). The qualitative
approach derives primarily from its inductive approach and its emphasis
on words rather than numbers. It focuses on specific situations or people.
By involving inductive, theory-generating, subjective and non-positivist
processes (Lee 1999), the qualitative approach seeks to gain insights and
to understand people’s perceptions of ‘the world’, as individuals and as
groups (Fellows & Liu 1997). Qualitative methods allow selected issues to
be studied in depth and detail. Approaching fieldwork without being
constrained by predetermined categories of analysis contributes to the
depth, openness and detail of qualitative inquiry (Patton 1990). On the
other hand, the quantitative approach tends to relate to positivism and to
gather factual data, then studying the relationships between facts and how
such facts and relationships accord with theories and any previous
research findings (Fellows & Liu 1997).
A grounded theory is one which is inductively derived from the study of the
phenomenon it represents. That is, it is discovered, developed and
provisionally verified through statistical data collection and analysis of data
pertaining to that phenomenon. Therefore, data collection analysis and theory
stand in reciprocal relationships with each other. One does not begin with a
theory, then prove it, rather one begins with an area of study and what is
relevant to that is allowed to emerge (Strauss & Corbin 1990).
CHAPTER 5 RESEARCH MODEL AND METHODOLOGY
76
The research methodology is a grounded, triangulated approach. By
using independently collected data, it was possible to verify the thinking of
key individuals in the organisations as to the strengths and weaknesses of
the systems currently in place. The basic concepts and variables relating
to cooperation, collaboration, organisational issues and performance were
investigated through the interview process with QDPW and QDMR. Data
collection was then conducted through case studies via in-depth interviews
and a questionnaire4 survey. The questionnaire survey was designed by
combining four well-developed instruments which measure variables on
organisational culture, commitment, organisational structuring and national
culture. By investigating the impact of the various cultural variables on
project performance, it would be possible to define patterns in which
relational contracting works or does not work. The four measurement
instruments used in the questionnaire survey are:
5.3.1 Organisational Culture and Structure
Handy (1985) defines four types of organisation culture and structure and
measures these based on an adaptation from a questionnaire compiled by
Dr. Roger Harrison:
Cultures Structures
power web
role temple
task net
person cluster
Table 5.1 Organisation Culture and Structure defined by Handy
4 See Appendix III
CHAPTER 5 RESEARCH MODEL AND METHODOLOGY
77
He further indicates that the choice of an appropriate culture is dependent
on history and ownership; size; technology; goals and objectives; the
environment; and the people.
5.3.2 Levels of Commitment
Allen and Meyer (1990) define the focus of commitment and suggest three
dimensions of commitment:
• Affective commitment is an emotional attachment to the
organisation
• Normative commitment is based on acceptance of the
organisation’s set of values
• Continuance commitment is based on the idea that the costs of
leaving the organisation outweigh the opportunity costs of staying.
In this context, the latter view of commitment can be seen as a negative
concept in project performance.
5.3.3 Organisational Structure
Van de Ven and Ferry (1980) measure a whole series of organisational
parameters including individual motivation, work processes and
organisational structure. Winch et al. (1997) found autonomy at work,
work coordination and work control along with job satisfaction,
instrumental motivation and feedback as essential for enabling teamwork
and individual motivation in construction projects.
5.3.4 National Culture
Hofstede (1980) defined four dimensions in national culture:
� The Individualism dimension is concerned with the form and
manner of the relationship between an individual and others in
CHAPTER 5 RESEARCH MODEL AND METHODOLOGY
78
society. In countries with high individualism scores relationships
are loosely structured.
� Power distance refers to the distribution of power within a society.
Large power distances indicate large inequalities between those
with power and those without. Empowerment is often seen as an
alliancing objective and so is perhaps at odds with high power
distance.
� Uncertainty avoidance is to do with how a society reacts to and
manages uncertainty inherent in human situations. In some
societies people are socialised to accept ambiguity and uncertainty
and are not threatened. In others uncertainty is disruptive and
psychologically uncomfortable. This dimension has to be balanced
in alliancing, with an appropriate mix of structuring and innovative
behaviour.
� Masculinity concerns the way society handles basic divisions in
society. Some societies with sharp and strict divisions are termed
masculine; others, where the divisions are loose and blurred are
termed feminine.
5.4 Scope of the Research
Due to time and resource constraints, the research focused on the public
sector in Queensland. Believing the client is the driver of change
(Construction Clients' Forum 1998; Construction Industry Board 1997;
Construction Industry Institute 1991; Egan 1998), both public
organisations, QDPW and QDMR, were asked to nominate professionals
for the questionnaire survey who have had experience on partnering,
alliancing or relationship contracting projects, to control the sample quality.
In order to obtain a fairer view, interviews were conducted with project
team members from both the client and contractor organisations in some
of the case studies.
CHAPTER 5 RESEARCH MODEL AND METHODOLOGY
79
5.5 Data Collection
Methods of data collection used in this research are questionnaires,
interviews, direct observation and documentation analysis.
Questionnaires were sent to professionals nominated by QDPW and
QDMR. The nominees had had experience on partnering, alliancing or
relationship contracting projects. A total of 67 questionnaires were sent
out for this research. Questionnaires were sent to eight professionals
nominated by QDPW. Six completed questionnaires (75%) were returned
and an interview was conducted whist collecting each questionnaire. The
professionals then nominated for further study other project participants
who were connected with them. A follow-up survey was conducted by
sending out a sub-questionnaire 5 to 27 people identified in the main
questionnaire6, with a response rate of 77% (twenty questionnaires). The
same process was followed with QDMR. Questionnaires were sent to 12
professionals nominated by QDMR. Ten questionnaires (83%) were
returned and an interview was conducted whist collecting each
questionnaire. Again, the professionals nominated other project
participants who had work relationships with them. The sub-questionnaire
was sent out to 40 people identified in the main questionnaire. A total of
22 questionnaires were returned with a response rate of 55%. To ensure
consistency in the data collected, the author administered each
questionnaire individually. Each respondent was contacted by phone prior
to the collection of the questionnaire to avoid misinterpretation of any
terms and concepts. The completed questionnaire was again gone
through with each respondent face-to-face upon collection.
A total of a 34 thirty to sixty minute interviews were conducted in this
research. Data from seven case studies were collected from QDMR and
QDPW. Interviews were conducted with key project team members
5 Pages 184-196 in Culture Questionnaire – see Appendix III 6 Pages 197-202 in Culture Questionnaire – see Appendix III
CHAPTER 5 RESEARCH MODEL AND METHODOLOGY
80
including project manager, project director, client’s principal, consultant,
superintendent, superintendent representative, engineer, foreman and site
inspector.
In all cases, the researcher was in the role of a neutral observer. Specific
observational data was collected from participation in monthly project
meetings. Interviews were also used for other participants’ experiences
and observations of meetings or events relevant to relationship
contracting. Records collected including meeting minutes and memos,
various forms of partnering assessment sheets and contracting
documents. Observation of a number of monthly site and relationship
meetings was carried out in two case studies in order to examine team
dynamics and communication processes in the project team.
5.6 Data Analysis
The questionnaire survey (Culture Questionnaire) used for this research is
presented in Appendix III. SPSS was used to carry out statistical analysis
in this research. In order to determine relationships between variables and
to measure tests of correlation have been used, Pearson’s product-
moment correlation coefficient was used for interval data measures and
Spearman’s rho for ordinal data measures (Wikipedia 2004). A chi-square
test was used in some relationships to test the linkage between the
attributes of variables and ordinal measures in the sample.
5.7 Summary
The objectives of this research are to investigate how a collaborative
project culture is developed and enhanced; and to identify the ways in
which collaboration can be transmitted throughout the industry. This
research was carried out by investigating the national culture,
organisational structure, culture and commitment in two large public sector
CHAPTER 5 RESEARCH MODEL AND METHODOLOGY
81
organisations in Australia. The research methodology is a grounded,
triangulated approach. The impacts of various cultural variables on project
performance were investigated initially through a questionnaire survey.
The outcome of this process was validated through follow-up interviews
with survey participants; the concepts and instruments used on seven
case studies were identified during the course of the research, where data
collected was used to explain and understand the outcomes of these real
life projects. The results and analysis of the questionnaire survey are
presented in Chapter 6; and Chapter 7 presents the case studies findings
and analysis.
83
CHAPTER 6
CULTURE SURVEY
6.1 Introduction
This chapter reports the impact of the various cultural variables on project
performance in two government departments in Australia, QDPW and
QDMR. The variables focused on are organisation culture, commitment
level, organisation structure and national culture. This questionnaire
survey was carried out as a pilot study. Questionnaires were sent to eight
professionals nominated by QDPW and to 12 professionals nominated by
QDMR, and a sub-questionnaire was sent to 47 people identified in the
main questionnaire. A total of 67 questionnaires were sent out for this
research. Upon questionnaire collection from QDPW and QDMR
professionals, a thirty to sixty minute interview was conducted with each
professional. QDPW and QDMR survey findings were analysed as two
different groups for a detailed comparison between the building work
project and civil work project environments. As was discussed in chapter
4, QDPW and QDMR have very different procedures on the choice of
project delivery system. Both departments have different strategies on the
application of relational contracting. By analysing the data sample
CHAPTER 6 CULTURE SURVEY
84
separately, the relationships between the results are expected to be more
accurate and meaningful.
All figures and tables generated from the survey are detailed in Appendix
IV.
6.2 QDPW Survey Analysis
Questionnaires were sent to professionals nominated by QDPW. The
nominees had had experience on partnering, alliancing or relationship
contracting projects. Questionnaires were sent to eight professionals
nominated by QDPW. Six completed questionnaires (75%) were returned
and an interview was conducted whist collecting each questionnaire. The
professionals then nominated other project participants who were
connected with them for further study. A follow-up survey was conducted
by sending out a sub-questionnaire7 to 27 people identified in the main
questionnaire8, with a response rate of 77% (20 questionnaires). While
this survey was taking place, QDPW was undergoing organisation
restructuring.
6.2.1 Organisational Culture
The results of the organisation culture survey are shown in Table 6.1. It is
clear that a task culture is preferred by those in the organisation. Handy
(1985) describes task culture as being best suited to groups, project teams
or task forces which are formed for a specific purpose, which very much
describes the job nature in QDPW. Individuals in QDPW form his/her own
project team for each project and are highly likely to work with a different
team of people in each project.
7 Pages 197-202 in Culture Questionnaire – see Appendix III 8 Pages 184-196 in Culture Questionnaire – see Appendix III
CHAPTER 6 CULTURE SURVEY
85
Preferred Culture:
Task – this culture can be found where the market is competitive, the
product life is short, and speed of reaction is important. In this instance this
fits well with the organisation as QDPW generally:
• works as a team, particularly a project team;
• forms a team for a specific purpose – projects;
• is judged by results – the success of the project;
• emphasises work relationships within team.
However, when the results were analysed further it was found that the
culture that was perceived to exist within QDPW was a role culture.
Perceived Culture:
Role culture is often found where economies of scale are more important
than flexibility or where technical expertise and depth of specialisation are
more important than product innovation or product cost. In this context it is
apparent in:
• bureaucracy;
• heavy reliance on procedures and formal authority;
• long product life – QDPW still exists when projects (e.g. schools,
residential blocks, hospitals) have finished. Staff members in
QDPW would not expect to be abandoned after each project is
complete.
Organisational Culture Preferred Culture Perceived Culture Power 0 0.5* Role 0 4 Task 6 1.5* Person 0 0
(n=6) * Same score for Power and Task Culture was calculated from one of the returned
questionnaires.
Table 6.1: Organisational Culture (QDPW)
CHAPTER 6 CULTURE SURVEY
86
It is interesting to note that similar mismatches between preferred and
perceived cultures were identified in a government department that was
going through an organisational change in Hong Kong (Rowlinson, 2001).
6.2.2 Commitment
The results on levels of commitment, using Allen and Meyer’s (1997)
Affective, Continuance and Normative Commitment Scales, are reported in
Table 6.2. Both affective commitment (emotional attachment to the
organisation) and normative commitment (acceptance of the organisation’s
set of values) were found to be a little stronger than continuance
commitment (costs of leaving the organisation outweigh the opportunity
costs of staying). However, all scores are rather ‘middling’, indicating a
‘non-committal’ level of commitment. It is interesting to note that these
scores are still substantially higher than those reported by Rowlinson in his
study of the Architectural Services Department in Hong Kong. The QDPW
questionnaire responses did not explain how this situation has arisen. It
might be the department was undergoing restructuring and the
professionals were unsure with the organisation values and future
directions. Further research is required on this proposition.
Type of Commitment Mean Median Standard Deviation
Affective 23.2 23.5 4.4 Normative 22.0 22.5 1.5 Continuance 19.0 19.0 1.9
(n=6) * Concepts are measured on a scale of 1 to 7, with 1 indicating low levels of commitment
and 7 indicating high levels, for six variables giving, for each scale, maximum scores of 42 and minimum scores of 6.
Table 6.2: Commitment Levels (QDPW)
CHAPTER 6 CULTURE SURVEY
87
6.2.3 Organisational Assessment
The objective of this part of the questionnaire was to explore the type of
structure prevalent in QDPW and relate this to the nature of the tasks
being undertaken by the organisation, with a view to identifying
mismatches. From the six returned questionnaires, a follow-up survey was
conducted by sending out a sub-questionnaire (Ref.: Pages 29-35 in
Culture Questionnaire) to 27 people identified in the main questionnaire
(Ref.: Pages 13-28 in Culture Questionnaire). Twenty sub-questionnaires
(77%) were returned and the results on organisational assessment are
shown below.
Van de Ven and Ferry (1980) suggested that organisational units that
undertake work at high levels of difficulty and variability adopt what they
termed a developmental group mode of structure. Table 6.3 presents the
hypothesised patterns of their three design modes in complex
organisations. A developmental group mode is aimed at creating a
programme for handling tasks, problems or issues that have not been
encountered before, and/or are sufficiently difficult or complex, which
require further work for solutions. It is also suggested that a
developmental programme/mode of structure consists of (1) general goals
or ends to be achieved in a specified amount of time, leaving unspecified
the precise means to achieve them, and (2) a set of norms and
expectations regarding the nature of behaviour and interactions among
group members. The characteristics mentioned above seem to fit in with
QDPW’s mission very well. One of the major roles of QDPW is to be part
of the project team in a construction project, including being able to react
to unforeseeable events that occur during the project, whether these
events have natural or man-made causes. It is also common not to have
the project thoroughly strategically planned and specified at the outset,
particularly when dealing with complex ‘multi-clients’, as often happens
with QDPW. Based on the facts and characteristics described above, a
CHAPTER 6 CULTURE SURVEY
88
developmental group mode of structure is seen as being the most
appropriate structure mode9 for QDPW.
Systematized Impersonal
Mode
Discretionary Personal Mode
Developmental Group Mode
Difficulty & Variability of Tasks, Problems, Issues Encountered by subsystem –
Low Medium High
Salient Dimensions of Managerial Subsystem
1. Organizational Referent Central information
systems Hierarchy & staff Coordination
committees
2. Coordination and Control by: Rules, plans, schedules
Exceptions to hierarchy
Mutual group adjustments
3. Resource & Information Flows among Organizational Levels, Units, & Positions:
a. Direction Diffuse Vertical Horizontal b. Amount High Medium Low c. Standardization &
Codification High Medium Low
4. Perceived Interdependence among Components Low Medium High
5. Frequency of conflict among Components Low Medium High
Table 6.3: Hypothesised Patterns of Systematized, Discretionary and Developmental Modes of Structure in Complex Organisations (extracted from Van de Ven and Ferry, 1980, p. 368-369)
Using the results generated from the survey, Table 6.4 was developed to
test the hypothesised patterns suggested by Van de Ven and Ferry. It is
noted that although QDPW was initially expected to follow the logic of
developmental group mode of structure, the logic of systematised mode is
more closely followed (although it is apparent from Table 6.4 that the
mode displayed is to some extent a hybrid). This again reflects the results
from Handy’s instrument but, as Van de Ven has written extensively on
organisational change, he does provide us with a useful set of tried and
tested methods (tools) to bring about an appropriate organisational
change and to measure the degree of change over time.
9 Note: There is a strong link here to Handy and his task culture – similar concepts operate in task culture and developmental group mode of structure. There should be a strong correlation between these two concepts.
CHAPTER 6 CULTURE SURVEY
89
Systematized Impersonal
Mode
Discretionary Personal Mode
Developmental Group Mode
Salient Dimensions of Managerial Subsystem
1. Organizational Referent Central information systems?
Hierarchy & Staff?
2. Coordination and Control by: Rules, plans, schedules
3. Resource & Information Flows among Organizational Levels, Units, & Positions:
a. Direction Diffuse? b. Amount Low c. Standardization &
Codification High Medium
4. Perceived Interdependence among Components
High
5. Frequency of conflict among Components Low
Table 6.4: Hypothesised Patterns of Structure Mode in QDPW
Reasons for Relationship
Figures 6.1-6.4 in Appendix IV show that the relationship between QDPW
and Other Units exists not for receiving/sending work or resources, but for
receiving/sending technical assistance and information. It is also noted in
Figure 6.4 that the units with which QDPW has relationships give a higher
rating (or expectation) for information transfer between parties than QDPW
does. It is interesting to see both QDPW and the other units have similar
ratings of each other. Also, both groups find their working relationship
highly effective.
Resource Dependence
In the main, both QDPW and Other Units indicate their relationship is
highly dependent on the other party’s resources. Both QDPW and Other
Units agree there is some dependence on the other party to attain their
own goals.
CHAPTER 6 CULTURE SURVEY
90
Awareness of Relationship
Figure 6.9 shows the relationship between QDPW and Other Units has
existed for over ten years in most cases. This may imply there is a mutual
understanding on Government policy and organisational direction; perhaps
suggesting a reason for both parties finding their working relationship to be
highly effective. Both QDPW and Other Units believe the other party is
quite familiar with each other’s services and goals. A high degree of
personal acquaintance is reported by Other Units, where a low-medium
degree is reported by QDPW.
Consensus/Conflict
The consensus between parties rated by QDPW was found to be low
because many respondents do not know if the other party agrees on the
goal priorities/way of work provided/terms of relationship. Otherwise, both
parties have a medium-high agreement on their operating goals and the
special ways for their works to be carried out, and a high agreement on the
terms of their relationship.
Mean Median Standard Deviation
Goal Priorities QDPW 2.40 3.00 1.86 Other Units 4.35 4.00 0.49
Way of Work/Services are Provided
QDPW 2.90 3.50 1.62 Other Units 4.05 4.00 0.61
Terms of Relationship QDPW 3.10 4.00 1.65 Other Units 4.45 5.00 0.69
(n=20) * Concepts are measured on a scale of 0 to 5, with 0 indicating not knowing if the other
party agrees on goal priorities/way of work or services provided/terms of relationship, and 5 indicating knowing the other party agrees very much on items.
Table 6.10: Consensus and Conflict between QDPW and Other Units
CHAPTER 6 CULTURE SURVEY
91
Yet, it is interesting to see from the returned questionnaires from QDPW, a
total of seven stated they do not know if the other party agreed on their
goal priority; four do not know if the other party agreed on the ways of
work/services provided and four do not know if the other party agreed on
the terms of relationship.
This finding suggests an issue that needs further investigation with QDPW
– if roles/relationships cannot be clearly stated or specifically laid down,
how should this be addressed by client departments?
The average frequency of conflict for both QDPW and Other Units is found
to be low. There is no correlation between degree of personal
acquaintance and frequency of conflict, suggesting no matter how well
each other is known on a personal basis, the frequency of conflict is
neither positively or negatively affected.
Methods of Conflict Resolution
Mean Median Standard Deviation
Avoiding Issues 0.70 1.00 0.57 Smoothing Over Issues 0.80 1.00 0.77 Confronting Issues 3.40 5.00 2.30 Hierarchy 0.75 0.50 1.16
(n=20) * Concepts are measured on a scale of 1 to 5, with 1 indicating the conflict resolution was
almost never and 5 indicating it was used almost always
Table 6.14: Frequency of Use of Methods of Conflict Resolution (QDPW)
When disagreements arise, the most frequently used resolution method
was by an open exchange of information about the conflict or problem and
a working through of differences to reach a mutually agreeable solution. A
significant correlation is found between effectiveness of working
relationship and frequency of conflict from QDPW, suggesting the lower
CHAPTER 6 CULTURE SURVEY
92
the effectiveness of working relationship, the higher frequency of conflict.
However, there was no significant correlation from Other Units on the
tested variables. The resolution of disagreements reflects an intra-
organisational partnering/alliancing approach within QDPW.
Domain Similarity
Domain similarity refers to the extent to which QDPW and Other Units in a
relationship obtain their money from the same source; have the same
goals, work, technology and professional skills; and provide the same
kinds of products and services to the same client/customers.
A medium degree of domain similarity is found on funding source,
clients/customers, employee skills and technology. Most of the items are
found to be significantly correlated with the others. It is noted that
Operating Goals is highly correlated with all the items. This is expected
because the project team should have the same goals during work, and
one of the fundamental philosophies in alliancing is to have common goals
in the project team. Also, it is realised that the higher the domain similarity
of funding source is between both parties, is the more likely that a high
domain similarity of operating goals and technology exists; and the higher
the domain similarity of employee skills, the higher the domain similarity of
technology. Such is often observed from units in the same organisation.
An example would be the contract administration unit and the legal and
contractual unit in QDPW. It is suggested by Van de Ven and Ferry (1980)
that the best situation for units with high domain similarity is to have a
satisfaction relationship with other parties.
CHAPTER 6 CULTURE SURVEY
93
Communications
Working Relationship Effectiveness
(QDPW)
Working Relationship Effectiveness (Other Units)
Written Reports
Face-to-Face Talks
Telephone Calls
Group Meetings
Working Relationship Effectiveness (QDPW)
Sig. 1 -
0.537* 0.015
0.301 0.198
0.574** 0.008
0.315 0.176
0.227 0.335
Working Relationship Effectiveness (Other Units)
Sig. 0.537* 0.015
1 -
0.015 0.951
0.232 0.324
0.135 0.570
0.168 0.478
Written Reports
Sig. 0.301 0.198
0.015 0.951
1 -
0.366 0.113
0.665** 0.001
0.395 0.084
Face-to-Face Talks
Sig. 0.574** 0.008
0.232 0.324
0.366 0.113
1 -
0.467* 0.038
0.336 0.147
Telephone Calls
Sig. 0.315 0.176
0.135 0.570
0.665** 0.001
0.467* 0.038
1 -
0.536* 0.015
Group Meetings
Sig. 0.227 0.335
0.168 0.478
0.395 0.084
0.336 0.147
0.536* 0.015
1 -
** Correlation is significant at the 0.01 level (2-tailed) * Correlation is significant at the 0.05 level (2-tailed) (n=20)
Table 6.19: Correlation between Working Relationship Effectiveness and Methods of Communication (QDPW & Other Units)
Amongst the four types of communication, group meetings are carried out
less frequently. Face-to-face talks are found to have a high correlation
with the effectiveness of QDPW’s working relationship with other parties.
One common behaviour observed from successful alliancing projects or
projects using relationship contracting is frequent face-to-face talks
between parties. Issues or foreseeable problems are often resolved
before conflicts arise, allowing relationships between parties to be nurtured
and sustained. During one of the follow up-interviews, one interviewee
pointed out face-to-face talks or meetings were an issue between project
teams - due to the distance between parties, physical meetings were not
feasible and telephone conferences were used instead. With today’s
technology, one suggestion to achieve some of the benefits of face-to-face
CHAPTER 6 CULTURE SURVEY
94
talks or meetings is to use video conferencing or Netmeeting© via the
internet. Although physical presence is still not possible, these
technologies do allow behaviour or body language of the other party to be
observed.
A very strong correlation is found between consensus and quality of
communication, indicating there is a higher degree of agreement in
situations when it is easier to get ideas across, whereas there is no
significant correlation between consensus and difficulty in getting in touch.
One suggestion given is most of the participants in this survey are not
based on site, and participate in more than one project at one time.
He/She might not be as easy to locate as someone working regularly in
the office.
A positive correlation is found between difficulty getting in touch and
hindered performance in Other Units. This suggests the more difficult it is
to get in touch with QDPW, the more the performance of QDPW is
hindered by Other Units. This is purely a consequence of the nature of
construction in that all works are inter-related. For example, if there is a
problem on the quality of concrete, consent from QDPW is required for the
person-in-charge. Should the person not be contactable on a day, work
will then be delayed for one day and so on. Quality of information flow has
always been crucial in the project team. This is again confirmed by the
positive correlation between difficulty in getting ideas across and
frequency of dispute, suggesting a poor quality of communication often
leads to a higher frequency of dispute. All of these issues have surfaced
as anecdotal evidence in case studies.
Resource Flows
Three sets of data have missing values.
CHAPTER 6 CULTURE SURVEY
95
Significant correlations are found between variability of resource flow and
standardisation of relationship, suggesting that a higher degree of official
communication channels and standard operating procedures, rule and
policies, and a higher uniformity of resource flows may well in fact lead to
a higher frequency of interruptions and problems encountered in
transferring work objects and materials between parties. A more formal
and standardised relationship does not necessarily lead to a more uniform
resource flow. More problems or interruptions might well be encountered.
(The view was expressed that not everything can be ‘solved’ or ‘clarified’
or ‘problems reduced’ by having everything down in black and white. The
number of rules and procedures does not run in parallel with improved
relationships). Thus, these findings back up the observations on
organisation culture and organisation mode – a task culture and
developmental group mode fit the needs of a project-based organisation,
albeit a temporary multi-intra-organisation, rather than the role culture and
systematised mode which appear to be evident as the predominant
cultures in QDPW. A theme that has emerged in this survey research and
in the case studies is that QDPW’s management of its own clients, the
temporary multi intra-organisation that is imposed on it during projects, is a
key issue in the project delivery process.
Perceived Effectiveness of Relationship
Results indicate that both QDPW and Other Units have a medium-low
level of influence on each other.
A positive correlation is found between the extents of commitment by
QDPW and Other Units, suggesting that there is the potential to increase
the extent of commitment by other parties if more evidence of commitment
is made apparent by either QDPW or Other Units. A positive correlation is
also noted between the extent of commitment and the degree of
CHAPTER 6 CULTURE SURVEY
96
relationship productiveness, suggesting the level of commitment by each
party has a significant impact on the level of productive relationship.
The power of informal relations, intra-organisational alliancing even, is
apparent from Table 6.43 in that the level of standardised relationship has
a negative correlation with the equality of transactions, meaning the more
formalised the relationship is, i.e. the more the agreement between parties
is written down or contracted, the less acceptable are ‘payoffs’ from the
other party, which actually move the project forward.
97
CHAPTER 6 CULTURE SURVEY
Table 6.43: Correlation between Perceived Effectiveness of Relationship and Relationship Indices (QDPW)
Commitments (OU)
Commitments (QDPW)
Productive Relationship Time & Effort
Relationship Satisfaction
Equality of Transactions
Relationship Clearly
Specified Standardised Relationship
Resource Flow to QDPW
Resource Flow from QDPW
Poor Communi-
cation Quality
Freq. of Communi-
cation Domain
Similarity Resource
Dependence Awareness Personal
Acquaintance Consensus
Commitments (OU)
Sig.N
1 -
20
0.466(*) 0.038
20 0.419 0.066
0.371 0.108
20
0.223 0.344
20
-0.106 0.657
20
-0.316 0.175
20
0.032 0.893
20
-0.054 0.831
18
-0.284 0.268
17
-0.456(*) 0.043
20
-0.331 0.153
20
0.141 0.552
20
-0.222 0.361
19
-0.097 0.683
20
0.183 0.440
20
0.282 0.228
20 Commitments (QDPW)
Sig.N
0.466(*) 0.038
20
1 -
20
0.866(**) 0.000
20
0.313 0.179
20
0.533(*) 0.016
20
0.236 0.316
20
0.222 0.346
20
-0.179 0.451
20
0.002 0.994
18
0.104 0.691
17
-0.661(**) 0.002
20
-0.059 0.804
20
0.055 0.817
20
0.354 0.137
19
-0.038 0.874
20
0.444(*) 0.050
20
0.397 0.083
20 Productive Relationship
Sig.N
0.419 0.066
20
0.866(**) 0.000
20
1 -
20
0.475(*) 0.035
20
0.769(**) 0.000
20
0.128 0.591
20
0.263 0.263
20
-0.215 0.363
20
0.246 0.325
18
0.294 0.252
17
-0.625(**) 0.003
20
0.138 0.563
20
0.046 0.848
20
0.462(*) 0.046
19
0.253 0.281
20
0.650(**) 0.002
20
0.562(**) 0.010
20 Time & Effort
Sig.N
0.371 0.108
20
0.313 0.179
20
0.475(*) 0.035
20
1 -
20
0.612(**) 0.004
20
-0.185 0.435
20
0.209 0.377
20
0.093 0.696
20
0.335 0.174
18
0.415 0.098
17
-0.198 0.404
20
0.225 0.340
20
-0.198 0.402
20
0.351 0.140
19
0.248 0.291
20
0.418 0.067
20
0.234 0.321
20 Relationship Satisfaction
Sig.N
0.223 0.344
20
0.533(*) 0.016
20
0.769(**) 0.000
20
0.612(**) 0.004
20
1 -
20
0.000 1.000
20
0.180 0.448
20
-0.124 0.604
20
0.172 0.495
19
0.199 0.443
17
-0.507(*) 0.022
20
0.211 0.373
20
-0.065 0.784
20
0.357 0.134
19
0.268 0.253
20
0.558(*) 0.011
20
0.381 0.097
20 Equality of Transactions
Sig.N
-0.106 0.657
20
0.236 0.316
20
0.128 0.591
20
-0.185 0.435
20
0.000 1.000
20
1 -
20
0.131 0.581
20
-0.457(*) 0.043
20
-0.039 0.878
18
0.277 0.282
17
0.036 0.882
20
0.352 0.127
20
0.255 0.278
20
0.109 0.655
19
0.223 0.345
20
0.045 0.850
20
-0.097 0.684
20 Relationship Clearly Specified
Sig.N
-0.316 0.175
20
0.222 0.346
20
0.263 0.263
20
0.209 0.377
20
0.180 0.448
20
0.131 0.581
20
1 -
20
0.084 0.724
20
0.195 0.439
18
0.489(*) 0.046
17
-0.255 0.277
20
0.517(*) 0.020
20
0.000 1.000
20
0.502(*) 0.029
19
0.366 0.112
20
0.497(*) 0.026
20
0.352 0.128
20 Standardised Relationship
Sig.N
0.032 0.893
20
-0.179 0.451
20
-0.215 0.363
20
0.093 0.696
20
-0.124 0.604
20
-0.457(*) 0.043
20
0.084 0.724
20
1 -
20
-0.315 0.203
18
-0.406 0.106
17
-0.009 0.970
20
-0.235 0.319
20
-0.145 0.542
20
0.000 0.999
19
-0.169 0.477
20
-0.251 0.286
20
-0.011 0.963
20 Resource Flow to QDPW
Sig.N
-0.054 0.831 18
0.002 0.994
18
0.246 0.325
18
0.335 0.174
18
0.172 0.495
18
-0.039 0.878
18
0.195 0.439
18
-0.315 0.203
18 1 -
0.623(**) 0.008
17
0.254 0.309
18
0.510(*) 0.031
18
0.357 0.146
18
0.400 0.111
18
0.568(*) 0.014
18
0.488(*) 0.040
18
0.590(*) 0.010
18 Resource Flow from QDPW
Sig.N
-0.284 0.268
17
0.104 0.691
17
0.294 0.252
17
0.415 0.098
17
0.199 0.443
17
0.277 0.282
17
0.489(*) 0.046
17
-0.406 0.106
17
0.623(**) 0.008
17 1 -
0.016 0.952
17
0.549(*) 0.023
17
-0.107 0.683
17
0.432 0.095
17
0.219 0.398
17
0.468 0.058
17
0.081 0.758
17 Communication Quality
Sig.N
-0.456(*) 0.043
20
-0.661(**) 0.002
20
-0.625(**) 0.003
20
-0.198 0.404
20
-0.507(*) 0.022
20
0.036 0.882
20
-0.255 0.277
20
-0.009 0.970
20
0.254 0.309
18
0.016 0.952
17
1 -
20
0.210 0.374
20
-0.064 0.789
20
0.015 0.951
19
0.225 0.341
20
-0.510(*) 0.022
20
-0.442 0.051
20 Freq. of Communication
Sig.N
-0.331 0.153
20
-0.059 0.804
20
0.138 0.563
20
0.225 0.340
20
0.211 0.373
20
0.352 0.127
20
0.517(*) 0.020
20
-0.235 0.319
20
0.510(*) 0.031
18
0.549(*) 0.023
17
0.210 0.374
20
1 -
20
0.281 0.231
20
0.454 0.051
19
0.533(*) 0.016
20
0.453(*) 0.045
20
0.143 0.546
20 Domain Similarity
Sig.N
0.141 0.552
20
0.055 0.817
20
0.046 0.848
20
-0.198 0.402
20
-0.065 0.784
20
0.255 0.278
20
0.000 1.000
20
-0.145 0.542
20
0.357 0.146
18
-0.107 0.683
17
-0.064 0.789
20
0.281 0.231
20
1 -
20
-0.054 0.825
19
0.387 0.092
20
0.223 0.346
20
0.483(*) 0.031
20 Resource Dependence
Sig.N
-0.222 0.361
19
0.354 0.137
19
0.462(*) 0.046
19
0.351 0.140
19
0.357 0.134
19
0.109 0.655
19
0.502(*) 0.029
19
0.000 0.999
19
0.400 0.111
18
0.432 0.095
17
0.015 0.951
19
0.454 0.051
19
-0.054 0.825
19
1 -
19
0.695(**) 0.001
19
0.354 0.137
19
0.194 0.426
19 Awareness
Sig.N
-0.097 0.683
20
-0.038 0.874
20
0.253 0.281
20
0.248 0.291
20
0.268 0.253
20
0.223 0.345
20
0.366 0.112
20
-0.169 0.477
20
0.568(*) 0.01 18
0.219 0.398
17
0.225 0.341
20
0.533(*) 0.016
20
0.387 0.092
20
0.695(**) 0.001
19
1 -
20
0.406 0.076
20
0.486(*) 0.030
20 Personal Acquaintance
Sig.N
0.183 0.440
20
0.444(*) 0.050
20
0.650(**) 0.002
20
0.418 0.067
20
0.558(*) 0.011
20
0.045 0.850
20
0.497(*) 0.026
20
-0.251 0.286
20
0.488(*) 0.040
18
0.468 0.058
17
-0.510(*) 0.022
20
0.453(*) 0.045
20
0.223 0.346
20
0.354 0.137
19
0.406 0.076
20
1 -
20
0.730(**) 0.000
20 Consensus
Sig. N
0.282 0.228
20
0.397 0.083
20
0.562(**) 0.010
20
0.234 0.321
20
0.381 0.097
20
-0.097 0.684
20
0.352 0.128
20
-0.011 0.963
20
0.590(*) 0.010
18
0.081 0.758
17
-0.442 0.051
20
0.143 0.546
20
0.483(*) 0.031
20
0.194 0.426
19
0.486(*) 0.030
20
0.730(**) 0.000
20
1 -
20
** Correlation is significant at the 0.01 level (2-tailed) * Correlation is significant at the 0.05 level (2-tailed)
CHAPTER 6 CULTURE SURVEY
99
6.2.4 Culture
The results of the calculations following Hofstede’s method for the Value
Survey Model are presented in Table 6.44. Australian professionals
scored low on Hofstede’s power distance index, indicating the low
acceptance of a hierarchical or unequal distribution of power in
organisations. A medium score is perceived in Hofstede’s uncertainty
avoidance index, suggesting Australian professionals are semi-
comfortable with uncertain or unknown circumstances, and would create
formal rules and procedures to deal with those situations. The degree of
individualism was found high in the same sample, suggesting people
would look after themselves and their direct family in preference to seeing
themselves belonging to the larger group (organisation), which takes care
of their interests in exchange for loyalty. Finally, Australian professionals
scored low on Hofstede’s masculinity index, implying people tend to
sympathise with the underdog, rather than admire the achiever;
interpersonal relations, gender equality and interdependence are
emphasised.
PDI UAI IDV MAS
Hofstede 36 51 90 61
Survey Findings 16 42 90 33
Keys: PDI – Power Distance Index UAI – Uncertainty Avoidance Index IDV – Individualism Index MAS – Masculinity Index
(n=16)
Table 6.44: Scores for Australian Professionals on Hofstede Indices
Table 6.45 shows that employees in QDPW rate personal time, challenges
at work and freedom to adopt their own approach at work as very
important for their ideal job. However, working in a successful company
and the size of the organisation is considered to be not so important or
CHAPTER 6 CULTURE SURVEY
100
desirable. The findings reflect characteristics found in low power distance
countries with individualism culture. The respondents agree that it is very
important to have a good working relationship with their direct superior.
Being consulted by their superiors is important, as it is expected in a
country with high femininity culture, yet it is found less important than the
immediate work place relationships. It is suggested that although
respondents at QDPW work together in the organisation, each of them is
engaged in various project teams. One of the main philosophies in
relational contracting is to have a good working relationship with the
project team.
Mean Median Standard Deviation Personal Time 1.83 2.00 0.41 Challenge 2.17 2.00 0.41 Stress 2.67 2.50 0.82 Physical Condition 2.33 2.00 1.03 Relationship with Superior 1.67 2.00 0.52 Employment Security 2.50 2.50 0.55 Freedom 2.50 2.50 0.55 Cooperation 2.00 2.00 0.63 Consult by Superior 2.17 2.00 0.75 Contribution to Company 2.17 2.00 0.41 High Earning 2.17 2.00 0.41 Serve the Country 3.67 4.00 0.52 Desirable Living Area 2.00 2.00 0.00 Opportunity for Advancement 2.33 2.00 0.52 Job Adventure 2.17 2.00 0.41 Successful Company 3.00 3.00 0.63 Help the Others 2.67 2.50 0.82 Job Definition 2.67 2.50 0.82
(n=6)
* Concepts are measured on a scale of 1 to 5, with 1 indicating utmost importance and 5 indicating little to no importance on the said criteria for an ideal job.
Table 6.45: Importance of Criteria for an Ideal Job (QDPW)
It is interesting to note that Hong Kong professionals also scored highly on
Hofstede’s power distance index (Rowlinson and Root, 1996), yet
relatively low on individualism index. Rowlinson and Root suggested
Hong Kong professionals are more ‘situation accepting’ and are afraid to
CHAPTER 6 CULTURE SURVEY
101
express disagreements with superiors. Whereas with QDPW, findings
indicate professionals accept the inequalities, yet they are not afraid to
disagree with their superiors. Open communications in project
environments are crucial for successful implementation of relational
contracting.
Mean Median Standard Deviation Organisation’s rule should not be broken under any circumstances
3.17
3.00
0.75
Trust 2.00 2.00 0.00 Dislike of work 4.00 4.00 0.00 More desirable to work in a large corporation
3.33
3.00
0.82
(n=6) * Concepts are measured on a scale of 1 to 5, with 1 indicating strongly agree with the
statement and 5 strongly disagree.
Table 6.46: Levels of Agreement on Statements (QDPW)
Respondents find they do not often feel stress at work. Also, the majority
disagree that a large corporation is a more desirable place to work than a
small company, and theory X (see McGregor 1960 for more information) is
strongly rejected – these all match nicely with what Hofstede suggested
would be found in an organisation with a low masculinity index. The
survey results show that relationship and cooperation with co-workers are
rated of high importance, yet the importance of having sufficient time left
for one’s personal life is rated the highest, suggesting work is less central
in people’s lives, which again goes with an organisation with a low
masculinity index as suggested by Hofstede. It is also agreed by the
majority that formal procedures should be retained in order to ensure both
personal and the firm’s objectives are met. QDPW professionals were
found operating in role culture and systematised structure mode. This
study also revealed that Australian professionals are weaker in uncertainty
avoidance (compared with other countries in Hofstede’s indices);
suggesting ineffective rules were imposed to satisfy people’s emotional
need for formal structure (Hofstede, 1991). It was observed during follow-
CHAPTER 6 CULTURE SURVEY
102
up interviews that decision-making processes were often prolonged due to
layers of procedures followed with extensive amount of meetings.
Mean Median Standard Deviation Personal relationship are important in managing project/contract
1.67
2.00
0.52
Formal procedures are necessary for the successful management of a project
2.00
2.00
0.63
Informal arrangements are necessary for the successful management of a project
2.67
2.50
0.82
Personal relationships amongst the project members are more important than those in your employer’s organization
2.33
2.50
0.82
One must be willing to sacrifice personal relationships with members of the project team to ensure the successful completion of the project
2.67
2.50
0.82
One must be willing to sacrifice personal relationships with members of the project team to ensure their firm’s objectives are met
2.83
2.50
0.98
One must be willing to sacrifice personal relationships with members of the project team to ensure one’s personal objectives are met
3.50
4.00
0.84
One must be prepared to disregard formal procedures in order to ensure the successful completion of the project
2.67
2.00
1.03
One must be prepared to disregard formal procedures in order to ensure one’s firm’s objectives met
3.17
3.00
0.75
One must be prepared to disregard formal procedures in order to ensure one’s own objectives are met
3.50
4.00
0.84
(n=6) * Concepts are measured on a scale of 1 to 5, with 1 indicating strongly agree with the
statement and 5 strongly disagree.
Table 6.47: Agreement to Statements in Relation to Project Success or Achieving Objectives (QDPW)
Survey results shown in Table 6.47 and follow-up interviews with
respondents found that QDPW professionals view personal relationships
as an important aspect in managing projects. One common statement
obtained from the interviewees was they find having a good personal
relationship with their project team members helps to minimise the chance
of conflicts during work. This observation is reinforced by the
disagreement with the statement that ‘one must be willing to sacrifice
personal relationships with members of the project team to ensure one’s
CHAPTER 6 CULTURE SURVEY
103
personal objectives are met’. However, with reference to the survey
results presented earlier (please refer to Table 6.9), the degree of personal
acquaintance is found to be low. Also, the majority agree that personal
relationships need to be sacrificed to ensure a successful project
completion and to meet the firm’s objectives. This suggests that, after all,
work is work, and with reference to earlier survey results (please refer to
Table 6.1), task culture is preferred by those in the organisation. It is also
interesting to note that although QDPW professionals find formal
procedures are necessary for project management success, at the same
time, they also agree formal procedures may need to be disregarded to
ensure successful project completion. This again verifies the mismatch
between the perceived role culture and the preferred task culture, where
QDPW professionals are restrained by rules and procedures, with a lack of
flexibility.
6.2.5 Overview of QDPW Data
Levels of commitment were found to be average in QDPW. A relational
contracting approach cannot succeed if the collaborating organisations do
not accept its ethos. Hence, commitment to the goals and objectives of
the organisation is crucial in implementing new approaches to contract
strategy. Also, QDPW personnel should be following a developmental
group mode and do prefer working in a task culture but are actually in a
role culture and follow the systematised mode. Hence, the results support
one another. It appeared that there is a mismatch between how the
organisation in general operates – the role model, and what the
professionals working in the project side of the organisation actually want
to be and to achieve – the task model. Interestingly, out of the twenty-five
problems indicated by participants in the questionnaire survey, over 50%
have a direct relationship with communication, such as timely response,
continued and open communication, quality response and respect of
CHAPTER 6 CULTURE SURVEY
104
different views. One of the recurring suggestions to overcome the
problems is more face-to-face meetings.
The level of awareness between QDPW and Other Units increases as the
frequency of communication increases. It is also noted that when there is
a high domain similarity, there is a lower amount of conflict between
parties. Also, high productive relationships actually occur when there is
higher quality of communication, reinforcing the importance of
communication quality and frequency. Though it is often the case for a
person to be involved in more than one project at the same time, one
common issue pointed out by the participants from QDPW in this survey is
more face-to-face and continuing open communication is needed. To find
time to get around the table for discussions is often a challenge, and this
inability leads to problems such as late provisions or approvals, late
response to queries, poor quality of response, cost and programme
problems, opinions on design elements, etc, which mostly relate to
information flow issues. ‘Finding time’ for communication seems to be a
major issue in QDPW.
It was expected that there would be a correlation between resource
dependence and frequency of communication. However, no significant
correlation was found. It may well be that the frequency of communication
remains at a high level, not necessarily of high quality, due to the nature of
the construction industry. Site inspections will be carried out whether work
is carried out by in-house personnel or contracted out; project meetings
will still be held periodically e.g. partnering meetings and regular site
meetings. A significant issue is that site meetings and project meetings
are held separately from partnering meetings/workshops, suggesting
project teams in relationship contracting projects have more set meetings
(higher frequency of communication) than traditional types of contract,
allowing each party to become more familiar with other parties’ goals and
services and, perhaps significantly, for the communication to take place at
CHAPTER 6 CULTURE SURVEY
105
all levels within the organisation. The organisational cross-sectional
nature of the participants taking part in meetings in relationship contracting
projects perhaps has a positive impact on the quality of communication
and information flow and is a stimulus to timely and appropriate action.
Weaker uncertainty avoidance was found in the Australian professional;
ineffective rules and procedures might be imposed to satisfy people’s
emotional need for formal structure. However, findings suggested that the
number of rules and procedures does not run in parallel with improved
relationships, as more problems or interruptions might be encountered.
Similarly with relationship contracting, transferring maximum amount of
risk to the contractor for a greater control over the project does not
necessarily lead to project success or better relationships in the project
team.
6.3 QDMR Survey Analysis
Questionnaires were sent to twelve professionals nominated by QDMR.
The nominees had had experience on partnering, alliancing or relationship
contracting projects. Ten completed questionnaires (83%) were returned
and an interview was conducted whilst collecting each questionnaire. The
professionals then nominated for further study other project participants
who were connected with them. A follow-up survey was conducted by
sending out a sub-questionnaire to forty people identified in the main
questionnaire, with a response rate of 55% (22 questionnaires).
6.3.1 Organisational Culture
The results of the organisational culture survey are shown in Table 6.48. It
is clear that a task culture is preferred by QDMR staff. Handy (1985)
describes task culture as being best suited to groups, project teams or
task forces which are formed for a specific purpose, which very much
CHAPTER 6 CULTURE SURVEY
106
describes the job nature in QDMR. Similar to QDPW, individuals in QDMR
form his/her own project team for each project and are highly likely to work
with a different team of people in each project.
Preferred Culture:
Task – this culture can be found where the market is competitive, the
project life is short, and speed of reaction is important. In this instance this
fits well with the organisation as QDMR generally:
• works as a team, a project team;
• forms as a team for a specific purpose – projects;
• is judged by results – success of the project;
• emphasises work relationships within teams.
However, when the results were analysed further, it was found that the
culture that was perceived to exist in QDMR was a mix between power,
role and task culture.
Organisational Culture Preferred Culture Perceived Culture Power 0 2.5b Role 0.5a 4b,c Task 8.5a 3.5c Person 1 0
(n=10) a Same score for Role and Task Culture was calculated from one of the returned
questionnaires. b Same score for Power and Role Culture was calculated from one of the returned
questionnaires. c Same score for Role and Task Culture was calculated from one of the returned
questionnaires.
Table 6.48 Organisational Culture (QDMR)
CHAPTER 6 CULTURE SURVEY
107
Perceived Culture:
Power culture is frequently found in small entrepreneurial organisations,
and it relies on a central power source. The organisation depends on trust
and empathy for its effectiveness and on telepathy telephone and personal
conversation for communication. In QDMR it is apparent in:
• power-orientated;
• politically minded – (relationship management) decisions made are
hindered by politicians;
• risk-taking – sharing risk with the Contractor and open
communication by adopting relationship management;
• organisation with maximum independence from heads of
departments – principals have great control over his/her project
teams and projects.
Role culture is often found where economies of scale are more important
than flexibility or where technical expertise and depth of specialisation are
more important than product innovation or product cost. In this context it is
apparent in:
• bureaucracy;
• heavy reliance on procedures and formal authority;
• long product life – QDMR still exists when projects (e.g. highway
up-grade, road and bridge construction) have finished. Staff
members in QDMR would not expect to be abandoned after each
project is completed.
A reason suggested for this mix of perceived culture is that there is a
different culture between different districts e.g. metropolitan and outer
districts. Such culture differences may be due to resources availability
(e.g. metropolitan district has closer access to resources), communication
and information flow. For example, departments in metropolitan districts
have a higher information flow and there is a higher frequency of
CHAPTER 6 CULTURE SURVEY
108
communication between staff. There is a higher chance of more
interaction with each other by working in the same area. Also, directors in
the organisation are based in the metropolitan district, where most
decisions and policies are made. It is interesting to note that similar
findings on the mismatches between preferred and perceived cultures
were also reflected in the QDPW results and in Rowlinson’s study of the
Architectural Services Department in Hong Kong. Professionals in the
departments prefer working in a task culture, but are observed to be
working in a role culture.
6.3.2 Commitment
The results on levels of commitment, using Meyer and Allen’s (1997)
Affective, Continuance and Normative Commitment Scales, are reported in
Table 6.49. Affective commitment (emotional attachment to the
organisation) was the strongest amongst the three types of commitment,
where there was little variance from the responses, whereas the scores for
both normative (acceptance of the organisation’s set of values) and
continuance commitment (costs of leaving the organisation outweigh the
opportunity costs of staying) were more ‘middling’.
Type of Commitment Mean Median Standard Deviation
Affective 48.7 48.0 2.5 Normative 36.0 35.5 8.5 Continuance 35.0 37.5 6.2
(n=10) * Concepts are measured on a scale of 1 to 7, with 1 indicating low levels of commitment and
7 indicating high levels, for six variables giving, for each scale, maximum scores of 56 and minimum scores of 9.
Table 6.49: Commitment Levels (QDMR)
It is interesting to find that the scores on all three commitment dimensions
are higher than those reported in QDPW, and than those reported in
Rowlinson’s study in Hong Kong (other than scores on the continuance
CHAPTER 6 CULTURE SURVEY
109
commitment dimension). For the implementation of relational contracting
to be successful, there needs to be a high degree of support and
commitment to the organisation’s values, with the benefits and philosophy
of relational contracting filtered to all levels.
6.3.3 Organisational Assessment
Van de Ven and Ferry (1980) suggested that organisational units which
undertake work at high levels of difficulty and variability adopt what they
termed a developmental group mode. As with QDPW, Van de Ven and
Ferry’s characteristics of an organisation with a developmental group
mode of structure also fit in very well with QDMR’s mission. A major role
in QDMR is to be part of the project team in a construction project,
including being able to react to unforeseeable events that occur during the
project, whether these events have natural or man-made causes. It is
common not to have the project strategically planned and specified at the
outset, complex problems (e.g. political, environmental) often come up
during construction such as interferences from the local council or an
indigenous community. Based on the facts and characteristics described
above, as with QDPW, a developmental group mode is seen as being the
most appropriate structure mode for QDMR.
Using the results generated from the survey, Table 6.50 is developed to
test the hypothesised patterns suggested by Van de Ven and Ferry. Like
QDPW, although QDMR was initially expected to follow the logic of
developmental group mode, in reality, the logic of a cross between
systematised impersonal mode and discretionary personal mode is more
closely followed. This again reflects the results from Handy’s instrument.
The mismatches between the organisation culture as perceived by the
professionals and the organisational structure in both departments are
apparent.
CHAPTER 6 CULTURE SURVEY
110
Systematized Impersonal
Mode
Discretionary Personal Mode
Developmental Group Mode
Salient Dimensions of Managerial Subsystem
1. Organizational Referent Hierarchy & staff 2. Coordination and Control by: Rules, plans,
schedules
3. Resource & Information Flows among Organizational Levels, Units, & Positions:
a. Direction Diffuse b. Amount Medium c. Standardization &
Codification Medium
4. Perceived Interdependence among Components
High
5. Frequency of conflict among Components Low Medium
Table 6.50: Hypothesised Patterns of Structure Mode in QDMR
Reasons for Relationship
Figures 6.61-6.64 show the relationships between QDMR and Other Units
exist mostly for receiving/sending information. It is also noted in Figure
6.62 that receiving/sending resources has only a minor value for the
reason for relationship with both QDMR and Other Units. It is interesting
to see both groups have similar ratings of each other except Other Units
has higher ratings on resources than QDMR in general. Also, both groups
find their working relationships highly effective.
Resource Dependence
In the main, both QDMR and Other Units indicate their relationship is of
median to high dependence on the other party’s resources. Also, both
groups agree that QDMR has a higher dependence on Other Units in
order to attain its goals, but not the reverse. However, in the follow-up
interviews, QDMR staff commented Contractor not ‘fully utilising’ QDMR
resources, such as professional knowledge/expertise on environmental
issues.
CHAPTER 6 CULTURE SURVEY
111
Awareness of Relationship
Figure 6.69 shows the relationship between QDMR and Other Units has
existed for over ten years or six to ten years in most cases. This may
imply there is a mutual understanding of Government policy and
organisational direction in general; perhaps suggesting a reason for both
parties finding their working relationship to be medium to highly effective.
Both QDMR and Other Units believe the other party is quite familiar with
each other’s services and goals. Both groups indicate the personal
acquaintance with the other party is good, where a higher degree of
personal acquaintance is reported by Other Units than QDMR.
Similar findings are recorded in QDPW. Both QDMR and QDPW have
had long relationships with the other parties. The fact that the degree of
relationship awareness was rated higher by both groups of Other Units
than the departments might suggest QDMR and QDPW have overlooked
the other parties’ knowledge or understanding of the departments’ goals;
or perhaps QDMR and QDPW find the other parties do not truly
understand the departments’ objectives and goals. Either way, QDMR
and QDPW should look into their client/contractor management for better
understanding of each party’s business and goals. Relational contracting
is about opening up communication and working with goals aligned.
There will not be common goals and objectives in a project if members do
not openly communicate and discuss each other’s objectives for
consensus.
Consensus/Conflict
The consensus between QDMR and Other Units is rated medium-high by
both parties. Both parties also find their performances are hindered by
each other at a relatively low degree.
CHAPTER 6 CULTURE SURVEY
112
The average frequency of conflict for both QDMR and Other Units is found
to be low. Again, similar to QDPW, there is no correlation between degree
of personal acquaintance and frequency of conflict between QDMR and
Other Units. This reinforces the suggestion that no matter how well people
know each other on a personal basis, the frequency of conflict is neither
positively nor negatively affected.
Methods of Conflict Resolution
When disagreements arise, the most frequently used resolution method
was an open exchange of information about the conflict or problem and a
working through of differences to reach a mutually agreeable solution.
Table 6.61 shows a significant negative correlation is found between
effectiveness of working relationship and conflict resolution by avoiding
issues and smoothing over issues, suggesting the less frequent use of
conflict resolution by avoiding/smoothing over issues, the more effective
the working relationship is. However, there is no significant correlation
from Other Units on the tested variables.
Similar findings are recorded in QDPW’s survey. Follow-up interviews with
respondents confirmed Australian professionals prefer confronting issues
when disagreements arise. A conclusion can be drawn from the findings
so far – the Australian culture is very well suited to relational contracting.
Professionals are not afraid of confronting issues. Instead, this open
exchange of information is accepted and very welcome in the construction
industry. Open communication is a crucial element in relational
contracting.
Domain Similarity
Domain similarity refers to the extent to which QDMR and Other Units in a
relationship obtain their money from the same source; have the same
CHAPTER 6 CULTURE SURVEY
113
goals, work, technology and professional skills; and provide the same
kinds of products and services to the same clients/customers.
A high degree of domain similarity is found on funding source, whereas a
low degree of domain similarity is found on work kind. Significant
correlations are found between Work Kind and Clients/Customers,
Operating Goals and Technology. QDMR is often the client itself in most
projects. When QDMR and Other Units are carrying out the same work,
they should also be working towards common goals, which is one of the
fundamental philosophies in relational contracting. Similar results are
noted in QDPW. This is expected because respondents in both
organisations were working in project teams. A project team would not
work as effectively if team members do not reach common goals. It is
also realised that the higher the domain similarity of work kind is between
both parties, is the more likely that a high domain similarity of technology
exists. Sharing of knowledge and exchange of ideas are the themes of
relational contracting.
CHAPTER 6 CULTURE SURVEY
114
Communication
Working Relationship Effectiveness
(Project Services)
Working Relationship Effectiveness (Other Units)
Written Reports
Face-to-Face Talks
Telephone Calls
Group Meetings
Working Relationship Effectiveness (Project Services)
Sig. 1 -
-0.181 0.421
0.143 0.524
-0.260 0.242
-0.106 0.638
-0.226 0.312
Working Relationship Effectiveness (Other Units)
Sig. -0.181 0.421
1 -
0.171 0.447
0.298 0.179
0.247 0.268
0.206 0.358
Written Reports
Sig. 0.143 0.514
0.171 0.447
1 -
0.427* 0.047
0.720** 0.000
0.457* 0.033
Face-to-Face Talks
Sig. -0.260 0.242
0.298 0.179
0.427* 0.047
1 -
0.568** 0.006
0.633** 0.002
Telephone Calls
Sig. -0.106 0.638
0.247 0.268
0.720** 0.000
0.568** 0.006
1 -
0.479* 0.024
Group Meetings
Sig. -0.226 0.312
0.206 0.358
0.457* 0.033
0.633** 0.002
0.479* 0.024
1 -
* Correlation is significant at the 0.05 level (2-tailed) ** Correlation is significant at the 0.01 level (2-tailed) (n=22)
Table 6.65: Correlation between Working Relationship Effectiveness and Methods of Communication (QDMR & Other Units)
Table 6.64 in Appendix IV shows the most frequently used communication
method is telephone calls, followed by face-to-face talks. However, there
is no significant correlation between the frequency of communication and
working relationship effectiveness. Also, although there is a high
frequency of contact between the parties, the amount of time they spend
for each other is relatively low. The quality of communication is found to
be average (based on the degree of difficulty of getting in touch and
getting ideas across to other party). It is interesting to note from Table
6.69 that although both QDMR and Other Units find it relatively easy to get
in touch with the other party, the degree of difficulty in getting in touch and
getting ideas across is rated higher by Other Units. It is also noted from
the survey findings that Other Units finds the existing quality of
CHAPTER 6 CULTURE SURVEY
115
communication low when comparing with QDMR. The higher the degree
of difficulty in getting ideas across to Other Units, the more the
performance of QDMR is hindered by Other Units and visa versa. Positive
correlation is also found between difficulty in getting ideas across and
frequency of disputes (see Table 6.70). Similar findings are reflected in
the QDPW results; the more difficulty in getting in touch with QDPW, the
more QDPW performance is hindered by Other Units. This reinforces the
relationship between quality of communication and work performance.
However, the quality of communication in both departments is average
only.
Perceived Effectiveness of Relationship
Tables 6.79-6.82 show both QDMR and Other Units have a medium-low
level of influence on operations and goals/services on each other.
Survey results show that both QDMR and Other Units found there to be a
high extent of commitments by each party. Also, both parties found the
relationship has been very productive. Both parties believed that the time
and effort spent have been worthwhile, and both are very satisfied with the
relationship. However, both QDMR and Other Units found the equality of
transactions below average, suggesting the give-and-take relationship with
other party was unbalanced. Both parties felt ‘we get somewhat less than
we ought’ from the relationship.
Table 6.89 shows a positive correlation is found between the extent of
commitment by QDMR and Other Units, suggesting that there is the
potential to increase the extent of commitment by other parties if more
evidence of commitment is made apparent by either QDMR or Other Units.
The same positive correlation is also found in the QDPW survey.
CHAPTER 6 CULTURE SURVEY
116
Positive correlations are also found between the extent of commitment by
both parties, the degree of productive relationship and the relationship
satisfaction level, suggesting these variables are interrelated. High
commitment from both parties would result in a more productive
relationship. During the follow up interview, one comment which appeared
from time to time is that a high level of commitment from all parties is
needed in order for the relationship and the project to be successful. All
unsuccessful relationship management/partnering projects have one
common theme – lack of commitment from all levels. The significant
influence of commitment by project parties on a productive relationship is
verified in this survey by QDPW and QDMR.
Positive correlations are also found with equality of transactions and the
extent of a productive and satisfactory relationship. Also, a positive
correlation is found between equality of transactions and personal
acquaintance, implying the better both parties know each other on a
personal basis, the higher the degree of transaction equality. It was
pointed out by various interviewees that personal relationships are very
important for successful partnering/relational contracting. Parties became
more cooperative, problems are discussed rather than disputed, there is
positive problem solving rather than confrontation, and there is sharing of
information which leads to reduction of risks and unreasonable claims.
The observation was reflected by the positive correlation between
consensus and resource dependence. The power of informal relations as
identified earlier in the QDPW survey result is verified.
CHAPTER 6 CULTURE SURVEY
117
Commit-ments (OU)
Commit-ments
(QDMR) Productive
Relationship Time & Effort
RelationshipSatisfaction
Equality of Transactions
Relationship Clearly
Specified Standardised Relationship
Resource Flow to QDMR
Resource Flow from
QDMR
Poor Commu-nication Quality
Freq. of Commu-nication
Domain Similarity
Resource Dependence Awareness
Personal Acquain-
tance Consensus
Commitments (OU)
Sig. 1 -
0.571** 0.005
0.567** 0.006
0.233 0.297
0.543** 0.009
0.386 0.076
0.333 0.130
0.115 0.609
-0.028 0.902
-0.303 0.170
-0.091 0.688
0.065 0.773
-0.317 0.151
0.231 0.302
-0.068 0.764
0.250 0.261
0.031 0.893
Commitments (QDMR)
Sig. 0.571** 0.005
1 -
0.558** 0.007
0.484* 0.022
0.648** 0.001
0.154 0.494
-0.130 0.564
-0.117 0.605
0.172 0.443
-0.364 0.096
-0.168 0.455
-0.066 0.771
0.251 0.260
0.254 0.254
0.101 0.653
0.369 0.091
0.114 0.614
Productive Relationship
Sig. 0.567** 0.006
0.558** 0.007
1 -
0.610** 0.003
0.824** 0.000
0.508* 0.016
0.081 0.721
0.203 0.364
0.096 0.670
-0.403 0.063
-0.566** 0.006
-0.148 0.511
-0.082 0.718
-0.066 0.769
-0.012 0.957
0.551** 0.008
0.090 0.692
Time & Effort
Sig. 0.233 0.297
0.484* 0.022
0.610** 0.003
1 -
0.696** 0.000
0.331 0.132
-0.112 0.621
0.133 0.556
0.197 0.380
-0.165 0.464
-0.585** 0.004
0.280 0.207
0.145 0.519
0.145 0.519
0.262 0.238
0.746** 0.000
0.404 0.062
Relationship Satisfaction
Sig. 0.543** 0.009
0.648** 0.001
0.824** 0.000
0.696** 0.000
1 -
0.474* 0.026
-0.206 0.358
0.025 0.911
0.100 0.657
-0.421 0.051
-0.563** 0.006
-0.199 0.374
-0.083 0.715
-0.175 0.436
-0.159 0.479
0.533* 0.011
-0.022 0.923
Equality of Transactions
Sig. 0.386 0.076
0.154 0.494
0.508* 0.016
0.331 0.132
0.474* 0.026
1 -
-0.049 0.829
-0.003 0.989
0.146 0.516
-0.077 0.734
-0.437* 0.042
-0.058 0.798
-0.254 0.254
-0.412 0.057
-0.019 0.925
0.433* 0.044
0.068 0.764
Relationship Clearly Specified
Sig. 0.333 0.130
-0.130 0.564
0.081 0.721
-0.112 0.621
-0.206 0.358
-0.049 0.829
1 -
0.457* 0.033
-0.275 0.215
0.072 0.749
0.231 0.300
0.551** 0.008
-0.186 0.407
0.362 0.097
0.308 0.163
-0.050 0.826
0.328 0.136
Standardised Relationship
Sig. 0.115 0.609
-0.117 0.605
0.203 0.364
0.133 0.556
0.025 0.911
-0.003 0.989
0.457* 0.033
1 -
0.202 0.368
0.255 0.252
-0.216 0.335
0.323 0.143
-0.056 0.804
0.255 0.253
0.430* 0.046
-0.271 0.223
0.190 0.396
Resource Flow to QDMR
Sig. -0.028 0.902
0.172 0.443
0.096 0.670
0.197 0.380
0.100 0.657
0.4\146 0.516
-0.275 0.215
0.202 0.368
1 -
0.033 0.884
-0.120 0.595
-0.059 0.796
0.218 0.330
0.166 0.461
0.157 0.486
0.030 0.895
0.008 0.972
Resource Flow from QDMR
Sig. -0.303 0.170
-0.364 0.096
-0.403 0.063
-0.165 0.464
-0.421 0.051
-0.077 0.734
0.072 0.749
0.255 0.252
0.033 0.884
1 -
0.248 0.267
0.189 0.400
0.054 0.813
-0.018 0.937
0.178 0.428
-0.246 0.269
0.052 0.818
Communication Quality
Sig. -0.091 0.688
-0.168 0.455
-0.566* 0.006
-0.585** 0.004
-0.563** 0.006
-0.437* 0.042
0.231 0.300
-0.216 0.335
-0.120 0.595
0.248 0.267
1 -
0.033 0.884
-0.228 0.307
0.284 0.200
-0.215 0.377
-0.454* 0.034
-0.140 0.535
Freq. of Communication
Sig. 0.065 0.773
-0.066 0.771
-0.148 0.511
0.280 0.207
-0.199 0.374
-0.058 0.798
0.551** 0.008
0.323 0.143
-0.059 0.796
0.189 0.400
0.033 0.884
1 -
0.137 0.545
0.514* 0.014
0.591** 0.004
0.110 0.625
0.716** 0.000
Domain Similarity
Sig. -0.317 0.151
0.251 0.260
-0.082 0.718
0.145 0.519
-0.083 0.715
-0.254 0.254
-0.186 0.407
-0.056 0.804
0.218 0.330
0.054 0.813
-0.228 0.307
0.137 0.545
1 -
0.082 0.717
0.365 0.095
0.181 0.421
0.379 0.082
Resource Dependence
Sig. 0.231 0.302
0.254 0.254
-0.066 0.769
0.145 0.519
-0.175 0.436
-0.412 0.057
0.362 0.097
0.255 0.253
0.166 0.461
-0.018 0.937
0.284 0.200
0.514* 0.014
0.082 0.717
1 -
0.308 0.163
-0.059 0.793
0.432* 0.045
Awareness
Sig. -0.068 0.764
0.101 0.653
-0.012 0.957
0.262 0.238
-0.159 0.479
-0.019 0.935
0.308 0.163
0.430* 0.046
0.157 0.486
0.178 0.428
-0.215 0.337
0.591** 0.004
0.362 0.095
0.308 0.163
1 -
0.089 0.693
0.701** 0.000
Personal Acquaintance
Sig. 0.250 0.261
0.369 0.091
0.551** 0.008
0.746** 0.000
0.533* 0.011
0.433* 0.044
-0.050 0.826
-0.271 0.223
0.030 0.895
-0.246 0.269
-0.454* 0.034
0.110 0.625
0.181 0.421
-0.059 0.793
0.089 0.693
1 -
0.308 0.163
Consensus
Sig. 0.031 0.893
0.114 0.614
0.090 0.692
0.404 0.062
-0.022 0.923
0.068 0.764
0.328 0.136
0.190 0.396
0.008 0.972
0.052 0.818
-0.140 0.535
0.716** 0.000
0.379 0.082
0.432* 0.045
0.701** 0.000
0.308 0.163
1 -
* Correlation is significant at the 0.05 level (2-tailed). ** Correlation is significant at the 0.01 level (2-tailed) (n=22)
Table 6.89: Correlation between Perceived Effectiveness of Relationship and Relationship Indices (QDMR)
119
CHAPTER 6 CULTURE SURVEY
6.3.4 Culture
Results on Hofstede’s culture indices are presented in Table 6.44 below.
PDI UAI IDV MAS
Hofstede 36 51 90 61
Survey Findings 16 42 90 33
Keys: PDI – Power Distance Index UAI – Uncertainty Avoidance Index IDV – Individualism Index MAS – Masculinity Index
(n=16)
Table 6.44: Scores for Australian Professionals on Hofstede Indices
Mean Median Standard Deviation Personal Time 1.90 2.00 0.57 Challenge 1.80 2.00 0.63 Stress 2.90 3.00 0.99 Physical Condition 2.60 3.00 0.70 Relationship with Superior 2.00 2.00 0.47 Employment Security 2.60 2.00 0.84 Freedom 1.90 2.00 0.57 Cooperation 1.90 2.00 0.57 Consult by Superior 2.10 2.00 0.74 Contribution to Company 1.70 2.00 0.68 High Earning 2.30 2.00 4.80 Serve the Country 3.10 3.00 0.88 Desirable Living Area 2.00 2.00 0.67 Opportunity for Advancement 2.20 2.00 0.79 Job Adventure 2.00 2.00 0.82 Successful Company 3.10 3.00 0.88 Help the Others 2.40 2.50 0.97 Job Definition 3.20 3.00 0.63
(n=10) * Concepts are measured on a scale of 1 to 5, with 1 indicating utmost importance and 5
indicating little to no importance on the criterion for an ideal job.
Table 6.90: Importance of Criteria for an Ideal Job (QDMR)
It is interesting to find from Table 6.91 below that both QDPW and QDMR
professionals have similar ratings on the same tested criteria for an ideal
job. Both QDMR and QDPW professionals rate personal time, desirable
living area and cooperation with team members very important for an ideal
120
CHAPTER 6 CULTURE SURVEY
job. Cooperation with team members is a fundamental requirement for
relational contracting. Good working relationship in the project team is one
of the main philosophies in relational contracting. As shown in Table 6.90
above, it is interesting to see QDMR professionals rated contribution to
company’s success utmost importance for an ideal job (the most important
criteria), yet working in a successful company and the size of the
organisation is considered to be not so important or desirable. These
results actually indicate a strong linkage with the high score on the
affective commitment dimension. QDMR professionals have a strong
emotional attachment to the organisation, and they also find contributing to
the company’s success highly important in a job. It appears that QDMR
professionals and the organisation have a common and positive goal
alignment to the company success. In any successful project, it is not
uncommon to find ‘goal alignment in the project team’ as one of the major
criteria. Likewise, relational contracting might not be implemented as
effectively if project team members at all levels have no common goal.
Survey results also show that working in a well-defined job situation where
the requirements are clear is not considered to be as important by QDMR
professionals.
121
CHAPTER 6 CULTURE SURVEY
t-value Standard Deviation
Null Hypothesis
Personal Time -0.250 0.516 0.810 Challenge 1.260 0.563 0.230 Stress -0.483 0.935 0.640 Physical Condition -0.619 0.834 0.550 Relationship with Superior -1.320 0.488 0.210 Employment Security -0.258 0.751 0.800 Freedom 2.070 0.561 0.057 Cooperation 0.327 0.592 0.750 Consult by Superior 0.174 0.743 0.860 Contribution to Company 1.520 0.594 0.150 High Earning -0.564 0.458 0.580 Serve the Country 1.430 0.767 0.170 Desirable Living Area 0.000 0.535 1.00 Opportunity for Advancement 0.367 0.704 0.720 Job Adventure 0.462 0.699 0.650 Successful Company -0.243 0.797 0.810 Help the Others 0.564 0.915 0.580 Job Definition -1.47 0.704 0.160
(n=10)
Table 6.91: Difference between the Means of QDPW and QDMR on the Importance of Criteria for an Ideal Job using t-test
Mean Median Standard Deviation Organisation’s rule should not be broken under any circumstances 2.80 2.00 1.14 Trust 1.80 2.00 0.42 Dislike of work 3.90 4.00 0.32 More desirable to work in a large corporation 4.00 4.00 0.47
(n=10) * Concepts are measured on a scale of 1 to 5, with 1 indicating strongly agree with statement
and 5 strongly disagree.
Table 6.92: Level of Agreement on Statements (QDMR)
Both QDPW and QDMR respondents reported that they do not often feel
stress at work. Also, the majority disagree that a large corporation is a
more desirable place to work than a small company, and theory X is
strongly rejected – these all match well with what Hofstede suggested
would be found in an organisation with a low masculinity index. Both
QDPW and QDMR respondents agree that personal relationships are
122
CHAPTER 6 CULTURE SURVEY
important in managing a project/contract; respondents strongly disagree
that personal relationships should be sacrificed for meeting personal
objectives, which again goes with an organisation with a low masculinity
index as suggested by Hofstede. However, it is interesting to see the
diverse opinions in QDMR and QDPW on sacrificing personal relationships
with project team members to ensure successful project completion.
Mean Median Standard Deviation Personal relationship are important in managing project/contract 1.50 1.50 0.53 Formal procedures are necessary for the successful management of a project 1.70 2.00 0.48 Informal arrangements are necessary for the successful management of a project 2.50 2.00 1.08 Personal relationships amongst the project members are more important than those in your employer’s organisation 2.70 3.00 0.95 One must be willing to sacrifice personal relationships with members of the project team to ensure the successful completion of the project 3.90 4.00 0.74 One must be willing to sacrifice personal relationships with members of the project team to ensure their firm’s objectives are met 4.00 4.00 0.47 On must be willing to sacrifice personal relationships with members of the project team to ensure one’s personal objectives are met 4.20 4.00 0.42 One must be prepared to disregard formal procedures in order to ensure the successful completion of the project 3.40 4.00 1.08 One must be prepared to disregard formal procedures in order to ensure one’s firm’s objectives met 3.60 4.00 0.97 One must be prepared to disregard formal procedures in order to ensure one’s own objectives are met 3.70 4.00 0.95
(n=10) * Concepts are measured on a scale of 1 to 5, with 1 indicating strongly agree with the
statement and 5 strongly disagree.
Table 6.93: Agreement to Statements in Relation to Project Success or Achieving Objectives (QDMR)
According to questionnaire responses and in subsequent interviews, both
formal procedures and informal arrangements are considered necessary
for the successful management of a project. The majority’s view was that
relationship management is more successful in projects when it has been
123
CHAPTER 6 CULTURE SURVEY
made formal in contract documents. This finding gives an excellent
example of the importance of embedding informal arrangements in formal
mechanisms.
6.3.5 Overview of QDMR Data
Levels of commitment found in QDMR are generally middling, except
affective commitment, which was relatively strong. Affective commitment
is developed through perceptions of satisfactions and trust. This finding is
very positive because strong affective commitment means participants
strongly identify themselves with the organisation. They feel comfortable
working in the organisation and are happy with the membership. They are
unwilling to leave the organisation regardless of attractive packages
offered outside. QDMR professionals should be following a developmental
group mode and do prefer working in a task culture but are actually in a
mix between role/task culture and follow the systematised/discretionary
mode. The mismatch between the parent organisation culture and the
project culture is apparent.
The degree of personal acquaintance with the other party is rated slightly
higher by Other Units than QDMR. During a number of interviews, it was
pointed out by contractors that on some occasions, they would identify
specific members to be put in the project team, based upon the choice of
Superintendent from QDMR. Such behaviour advocates the degree of
personal acquaintance is crucial in choosing the right mix of people in a
project .
The most frequently used resolution method was by an open exchange of
information when disagreements arise. The resolution of disagreements
reflects an intra-organisational relationship management approach within
QDMR. One of the criteria for successful relationship management or
alliancing is open and honest communication between project team
124
CHAPTER 6 CULTURE SURVEY
members – by confronting issues. This suggests that a social
infrastructure already exists within QDMR which is in harmony with
relational contracting approaches and this should be further nurtured and
documented as a learning and skills issue.
It was surprising to find both parties believe their performances are
hindered by each other to a low degree. It was expected with the nature
of construction work, that the degree of performance is hindered by the
other party’s responses on for example design or quality of material
problems. Perhaps with civil construction works, as the site is often very
long, work can still continue even if a problem has arisen on one of the
sections. Work on site does not need to stop; whereas in building
construction, the site area is more restricted and all works are interrelated.
A typical example is brick works at level four cannot start before the floor
has been constructed.
A strong correlation is found between the greater difficulties in get ideas
across to Other Units, and the more the performance of QDMR is hindered
by Other Units and vice versa. This is purely a consequence of the nature
of construction because all works are interrelated. An example is constant
reminders from QDMR on issues such as site tidiness – by covering
manholes everyday after work. Should the messages/ideas not be
received by the other party(s), rework is required such as cleaning out the
debris every time, especially after a storm, or the asphalt base may even
be damaged. The consequences may not just be a delay of work by a day
or so, there may also be an additional cost on labour and materials.
Quality of information flow has always been crucial in the project team.
This is again confirmed by the positive correlation between difficulty in
getting ideas across and frequency of dispute, suggesting a poor quality of
communication often leads to a higher frequency of dispute.
125
CHAPTER 6 CULTURE SURVEY
Resource dependence was found to have a positive correlation with
frequency of communication as expected. Constant communication is
needed for the exchange of knowledge, such as QDMR’s expertise and
Other Units’ technical and practical knowledge. A strong correlation was
also found between frequency of communication and the level of
awareness. Also, it is shown that the higher level of awareness of the
other party, the higher degree of consensus. Positive correlation between
frequency of communication and degree of consensus suggests ‘keep
talking’ helps to bring about agreement and resolve problems, which is
one of the crucial elements in relational contracting – open and continuous
communication.
Communication quality has significant correlations with relationship
satisfaction and productive relationship, suggesting better communication
quality would improve relationship productivity and result in a more
satisfied relationship. Higher level of personal acquaintance has an effect
on better communication quality. One common issue pointed out by the
participants from QDMR is the sense of urgency seems to be often
neglected. The urgent need for better communication was raised by over
50% of the participants in follow-up interviews. Communication quality
and frequency are significant issues for both QDMR and QDPW.
6.4 Discussion
This survey has investigated the impact of the various cultural variables on
project performance. The basic concepts and variables relating to
cooperation, collaboration, organisational issues and performance were
examined through questionnaire survey and follow-up interviews with
QDPW and QDMR respondents. Cultural barriers to change exist at both
management and operation levels. There was a mismatch in both
departments between the organisational culture as perceived by the
professionals and the organisational structure that was being
126
CHAPTER 6 CULTURE SURVEY
implemented. Professionals in the departments preferred working in a
task culture, but in fact they were working in a role culture. Matrix
organisation is particularly suitable to construction project environment
(Bresnen 1990; Rowlinson 2001), and such an organisation will only work
effectively with a task culture. In the Hong Kong study conducted by
Rowlinson, the mismatch between the actual organisation culture and
organisation structure is one of the factors that created barriers against
implementing changes in the department.
Relational contracting suits the Australian culture very well. Professionals
were not afraid to express their ideas or disagreements. Direct
confrontation between individuals was accepted and preferred for
collaboration as well as conflict resolution. Australian professionals have
strong individualist attitudes; open discussion of matters is preferred,
which has an implication for decision-making styles and problem-solving
techniques. Further support for this argument is the finding that being
consulted by one’s direct supervisor is very important. Australian
professionals are not afraid to express disagreements with their
supervisors. However, uncertainty avoidance was an issue that might
impact the efficiency of implementing relational contracting. Ineffective
rules and procedures might be imposed to satisfy people’s emotional need
for formal structure. This study has demonstrated Australian professionals
prefer a flat organisation structure and have a strong desire for
decentralisation, yet also a medium level of formality. Both QDPW and
QDMR professionals were actually working in a role culture and
systematised structure mode. Although having roles clearly specified
assists the relationships between parties, excessive formalisation, rules
and procedures do not necessarily contribute to relationship productivity
and might in fact have a negative effect on the decision-making process.
Decision-making processes were prolonged due to extensive layers of
procedures that affected work efficiency. The importance on having both
formal and informal mechanisms in place was highlighted in the study.
127
CHAPTER 6 CULTURE SURVEY
Findings showed that should one’s level of commitment increase, the other
party’s commitment level would also increase significantly. Strong support
and commitment from project parties is crucial for project success and
implementation of changes. Also, findings showed that the more the
parties are satisfied with their relationships, the more productive their
relationships would be; and both levels of relationship satisfaction and
productivity would increase with the degree of personal acquaintance.
Australian professionals strongly agreed personal relationships are
important in managing projects. The importance of personal relationship
in the project process is agreed by the respondents and shown in
statistical analysis.
Low to medium levels of commitment were found in the professionals,
except the high level of affective commitment that was found in the QDMR
work group. Commitment to the goals and objectives of an organisation is
crucial in facilitating successful implementation of relational contracting.
As noted earlier, one party’s commitment levels have a significant effect
on the others’. The mismatches on organisation culture and structure
were more apparent in QDPW than QDMR. It is suggested the degree of
match and mismatch between organisation culture and structure has an
impact on the staff’s commitment levels.
The advantages and importance of face-to-face and continuous open
communication were identified in both the survey and interviews.
However, finding time for communication seemed to be a major problem in
QDPW. This is clearly an issue QDPW needs to investigate. The effect of
communication quality and frequency on parties’ relationships was clearly
shown in this study, and both QDPW and QDMR professionals clearly
stated better communication is needed. This is obviously an issue both
departments should address promptly.
128
CHAPTER 6 CULTURE SURVEY
QDPW professionals need to go through an extensive amount of
procedures when attempting to resolve or discuss an issue, yet the
decision might be overruled, which subsequently leads to more meetings
for discussing the issue and the way forward. Professionals are not
empowered to make decisions and this might be a possible reason why
QDPW professionals appear to be unwilling to take up responsibilities and
‘forever prolong the decision-making process’. This observation is a clear
example of power culture and role culture mix.
129
CHAPTER 7
CASE STUDIES
7.1 Introduction
This chapter presents the findings from seven case studies collected from
QDPW and QDMR. Different types of information were collected including
meeting minutes and written material documenting the purpose and nature
of relationship contracting. Interviews were conducted with key project
team members – both contractor and client staff. Individuals including
project manager, project director, Principal, consultant, superintendent,
superintendent representative, engineer, foreman and site inspector were
interviewed. Observation of a number of monthly site and relationship
management meetings in Case Studies 2 and 6 was carried out in order to
examine team dynamics and communication processes in the project
teams.
7.2 Findings
Details of each case study can be found in Appendix V.
130
CHAPTER 7 CASE STUDIES
7.2.1 Case Study 1
The contract was awarded based on the lowest bid win tender system.
The project was seriously underbid; which led to a lack of money in the
contract prior to project construction. A Relationship Management (RM)
process was adopted throughout the project. Both client and contractor
staff in the project team, from inspectors/foremen to client’s
Principal/contractor’s Project Manager, attended the RM Foundation
Workshop. There was a lack of collaboration and open communication in
the project team. The Contractor refused discussion with the Client while
setting the project charter objectives; all proposed items were drafted by
the Contractor Project Manager, while disagreements from the Client on
the objectives were not taken into account. One major disagreement
between project parties was whether or not the finance issue was to be
part of the charter objectives. Communication and relationships in the
project team started poorly from the first day.
There was a lack of buy-in on relationship management at the Contractor’s
senior management level. The existence of ‘us and them’ attitudes
became apparent as the project progressed. There was poor
communication in the project team; issues and ideas were not raised or
discussed openly during meetings. There was no open or informal
communication; all matters were communicated through formal letters with
strong references to contractual clauses. During project construction, the
Contractor put in an excessive amount of claims, attempting to increase
the project income. Such behaviour forced the Client to spend a large
amount of time and resources on checking and responding to the
Contractor’s claims. Rather than working towards ‘best for project’, both
parties were working towards their self-interest, reflecting zero goal
alignment in the project team. There was no appropriate platform for the
RC culture to develop. Further, there were strong personality clashes
131
CHAPTER 7 CASE STUDIES
between project team members, especially at the senior management
level, putting pressure on project team relationships.
The lack of empowerment from both Contractor and Client senior
management levels was clearly identified in this case study. Engineers
were not empowered to make any decisions; all discussions carried out at
engineer levels were ‘reviewed’ and disrupted by senior management
levels, with issues remaining unresolved and accumulating. The decision-
making process was prolonged; project members at the operational level
were put under pressure on problem resolutions and were unable to close
up issues.
There was a high staff turnover in the project, suggesting a lack of
commitment from the parent organisation to relational contracting
principles and the project. Project staff were taken away from the project
and put into other projects by the organisation. In this project, only two
Contractor staff were involved from the beginning till project completion;
staff including the Project Manager were pulled out from the project. Also,
newcomers to the project were not given induction courses to RM. In
consequence, the sense of unity and working as a team were largely
affected. The declining project team relationship was reflected in monthly
relationship process assessments. The project team relationship went
downhill from the beginning of the project. Although a partnering facilitator
was commissioned halfway into the project and held a partnering
workshop with the project team, and the project team relationship did
improve (as reflected in the assessment) in the following month, but
gradually declined again for the remaining period. There were ongoing
contractual disputes in the project and the project team relationships
turned sour.
132
CHAPTER 7 CASE STUDIES
7.2.2 Case Study 2
The contract was awarded based on the lowest bid win system. In this
case, the contract was not underbid and the RM process was adopted in
the project. Prior to the RM Foundation Workshop, the Contractor
nominated the major Subcontractor (asphalt) for the workshop and on-
going involvement in RM process. Client, Contractor and Subcontractor
staff from various levels attended the RM Foundation Workshop, carried
out monthly relationship process assessment and attended follow-up
monthly RM meetings. Project charter objectives were discussed in a
team fashion and were set with consent by all participants. Goal
alignment in the project team was established at the beginning. There
was strong commitment from the parties’ parent organisations and there
was little staff turnover in the project.
Open communication took place between project team members since the
project began. Team members identified open communication as a crucial
element in relationship effectiveness. Direct communication methods such
as telephone conversation and face-to-face talk were preferred. An
expression used was ‘if the issue can be talked through in a few minutes,
why spend two hours writing a two page letter?’ Project team members
made use of both formal and informal communication channels. All issues
and disagreements were raised during meetings and were discussed. The
Project team believed issues must be dealt with speedily in order to avoid
project delay and extra costs. There was buy-in of relationship
management at all levels. The principles of relational contracting were
practised and promoted to all levels; the Subcontractor was also exposed
to the relational contracting system and experienced relational contracting
in practice. There was open communication at all levels and parties’
relationships were proven to be highly effective.
133
CHAPTER 7 CASE STUDIES
The decision-making matrix was strictly followed at all levels. If any issues
could not be resolved promptly in the monthly meetings, they were taken
aside for further discussion between the Client and the Contractor at the
senior management level; the work relationship at the project level was not
affected and was maintained throughout the project. Project team
members at the operational level were able to work in a task culture and
focus on their works as well as closing up issues.
The Contractor in this project had a long working relationship with the
Client and was very familiar with the relationship management process.
There was a high degree of personal acquaintance between both Client
and Contractor senior management. Individuals at the senior
management levels understood each organisation’s policy and each
individual’s working style, which helped in developing the effective working
relationship in the project team.
7.2.3 Case Study 3
The consequences of not having a sufficient amount of money in the
contract were apparent. The project was broken down into three contracts
(packages). On the contract that was seriously underbid, work did not
finish on time, and there was high staff turnover including bankruptcy of
two Contractor firms. Both Contractors tried to recover cost throughout the
construction process. A Relationship Management Foundation Workshop
was held at the beginning of the project for the project team; however,
there was a lack of goal alignment. Contractors focused on minimising
loss during work, whereas the Client spent extra time ensuring the quality
and schedule of work, resulting in diverse interests in the project team.
Upon each Contractor bankruptcy, most workers at the operational level
were re-employed, by the second Contractor and by the Client at the later
stage. The work process was significantly affected during each transition
134
CHAPTER 7 CASE STUDIES
period. However, it was interesting to find that the relationship remained
satisfactory through the project. There was strong commitment from the
Client’s senior management to relational contracting principles. They tried
to keep the direct impact on the project team to a minimum by re-
employing the Contractor’s staff. Although the project team was exposed
to relational contracting principles and there was strong commitment from
the Client side, the project team was in distress and the team spirit was
damaged. A relational contracting culture was not able to fully develop in
the project team.
The other two contracts in the project were not underbid. Good
relationships were established in the project team on the first day. Strong
commitment to relational contracting principles was received from both
Client and Contractor organisations and there was buy-in at all levels. The
major subcontractor was nominated by the Contractor to be involved in the
relational contracting process, including the Relationship Management
Foundation Workshop, monthly partnering assessment and partnering
meetings. The same Contractor won both contracts, and therefore the
same project team worked through both contract works. There was a right
mix of people in the project team. Open and informal communication
happened at all levels throughout the project. The relationship remained
at a satisfactory level in the project team.
Only one workshop was held for each package. The partnering facilitator
was involved only in the foundation workshops. It was pointed out that
relational contracting was useful in ice-breaking and getting
communication going in the project team; yet the benefits of relational
contracting in the project were constrained by the limited involvement of
the partnering facilitator. Although the relationship management process
and team relationship were reviewed by project team members monthly
throughout the project, the involvement of an external facilitator (not part of
the project team) would have allowed missing/unseen issues to be
135
CHAPTER 7 CASE STUDIES
identified. A mid-project workshop should be held, run by the same
facilitator (foundation workshop), to capture third person opinions; and to
refocus and raise the project team spirit on relationship management and
to improve the project team skills, such as communication and problem
solving skills. Interviewees commented that relational contracting
principles were like an adjunct to the project rather than part of the project.
This statement reinforces the importance and value of further relationship
management workshops in a project, with a partnering facilitator. It was
also suggested that a financial element, such as bonus sharing, should be
inserted into relationship management contracts, to encourage stronger
commitment from Contractors.
7.2.4 Case Study 4
The contract was awarded based on the lowest bid win system. The
contract was not underbid and there was sufficient money in the contract.
A partnering foundation workshop was held at the beginning of the project;
stakeholders from all parties (Client, Client’s Representative and
Contractor) attended. The workshop provide an ice-breaking platform for
the parties, where open communication was established with problems
and issues discussed in an open manner, shortening the decision-making
process and saving both time and money. Monthly partnering meetings
were held amongst parties’ senior management levels only, with
partnering assessment carried out prior to each meeting. Participants
from project parties were given opportunities to discuss project issues
including project process and team relationships in face-to-face meetings.
Project team members were chosen in order to get the right mix for the
project team, which provided a good platform for building good
relationships in the project team. The decision making matrix was strictly
followed in the project. Disturbances to project progress at the operational
level were kept to a minimum, which helped to maintain good project team
136
CHAPTER 7 CASE STUDIES
relationships as there was little pressure from the parent organisations.
There was continuous strong commitment on the relational contracting
process from all parties at the senior management level, however, project
team members at the operational level were not involved in the relational
contracting process (foundation workshop and monthly partnering
meetings). It was pointed out that relational contracting is a strategy issue
and therefore should involve the senior management level only.
It was noticed there was a miscalculation in the project cost by the
Contractor early in the project. However, the project finished on schedule
and within budget, without receiving excess claims from the Contractor. It
was suggested the Contractor saw the benefits of relationship contracting
and wanted to establish a good relationship with both the Client and
Client’s Representative for future job opportunities. Rather than
concentrating on personal interests, project parties worked towards the
same goal, best for project, where issues were openly discussed and work
was conducted in a collaborative manner.
7.2.5 Case Study 5
Relational contracting principles were introduced to potential Contractors
in the tendering stage. Short-listed Contractors went through a selection
workshop facilitated by the Client and Client Consultant individually with
future project team members. Contractors were given a better
understanding of the project, which subsequently reduced the risk of an
underbid tender due to misunderstandings. Potential project team
members were given an opportunity to meet and assess each other’s
capacity and personality for future work cooperation. The workshop
allowed project members to openly discuss and communicate any
foreseeable project issues before construction, and to have a deeper
understanding of the project.
137
CHAPTER 7 CASE STUDIES
All workshop attendees found the workshop useful and that materials
produced during the workshop might be of assistance in the project.
Attendees were exposed to relational contracting principles and put the
principles into practice. Feedback was received from Contractors on
further improvements to the relational contracting process. Good
relationships between the nominated Contractor and Client were built prior
to project construction. Upon contract award, a Relationship Foundation
Workshop was held within the project team, where relational contracting
principles were reinforced.
The project was evaluated base on the tender price, and with a strong
focus on non-price criteria. A strong foundation was built at a pre-contact
stage, which allowed the relational contracting culture to develop promptly
in the project team, with a united and correct mindset. Because issues
were raised prior to the project start day, the project team could focus on
the same goal – best for project. There were strong commitments from
the Client and Client’s consultant on relational contracting; the principles
were put forward to the industry, achieving an industry training objective
through the selection workshop. Also, both Client (and Client’s consultant)
and Contractor sides were able to gain a greater understanding of
relational contracting from a different point of view as well as refine the
process for the future.
7.2.6 Case Study 6
Relational contracting principles were adopted in the project since the
project began. Project team members at all levels (from senior
management level to the foremen) attended the Relationship Management
Foundation Workshop, which was run by a partnering facilitator.
Relational contracting principles were introduced to the project team,
which also acted as an ice-breaking platform; project team members were
exposed to each other’s personalities and established open
138
CHAPTER 7 CASE STUDIES
communication. Project charter objectives were developed through team
discussion and consent. Although the contract was awarded based on the
lowest bid win system, there was enough money in the contract. Strong
commitment was received from the senior management level on both
Client and Contractor side; the Contractor would ensure half of its staff
would attend the monthly relationship management meeting, where either
or both Project Manager and Deputy Project Manager would be present.
A good relationship in the project team was established in the first day. All
issues and matters were openly discussed and ideas were exchanged
within the team, which minimised the chance for hidden agendas. Both
formal and informal communication channels, such as a monthly project
bulletin email sent by the Project Manager, were used across the team.
Team relationships and communication were developed through social
events such as barbeques and lunches. The contractor was very
proactive in the relational contracting process, indicating a strong buy-in of
relational contracting principles.
News (both project and organisation) and incidents were shared during
monthly meetings. Project team members at the operational level were
allowed to see the big picture of the project; whereas team members from
the senior management level were made aware of issues which had
impacts on the operational levels. Acknowledgements and respect were
shown from the project team on comments and suggestions raised during
meetings. Such behaviour encouraged continuous open communication
and collaboration amongst team members. Also, follow-up actions took
place on issues raised in each meeting. Such behaviour is very important
for project work to be conducted effectively, and to develop a relational
contracting culture, where actions were taken rather than just paying lip
service to issues.
139
CHAPTER 7 CASE STUDIES
To ensure a right mix of people in the project team, an unsuitable member
was identified and removed from the team, with the role immediately
replaced. There was a high staff turnover in the project and signs of early
crisis warning were detected at the first quarter of the project period. The
partnering facilitator was immediately contacted and attended the following
monthly meeting. Early signs of crisis were identified and pointed out to
the project team. The project team was also reminded about the
relationship management process and principles. This was particularly
important to the project newcomers, to understand the system and be
introduced with the right mindset. The Relational contracting culture was
developed in the project team with buy-in and benefits were seen at all
levels.
7.2.7 Case Study 7
Relational contracting principles were applied in the project at project
design stage. Both Client and the design team (Consultant) attended a
relationship workshop facilitated by an external facilitator early in the
design stage, where relational contracting principles were introduced. The
workshop also provided a platform for the group to establish open
communication, which encouraged face-to-face discussions and
clarification of any queries relating to the project design, as well as revision
of the Client design brief in a team manner.
A second relationship workshop was held during tender selection. Each of
the two short-listed Contractors attended a relationship workshop
facilitated by an external facilitator with the Client, Client’s Representative
and Consultant. Contractors were able to gain a better understanding of
the project, which subsequently reduced the risk of underbid tender due to
misunderstandings. Also, potential project team members were given an
opportunity to meet and be familiar with each other’s capacity and
personalities prior to project construction, providing a strong foundation for
140
CHAPTER 7 CASE STUDIES
the future project relationship. The workshop allowed the project group to
openly communicate and point out any foreseeable project issues before
construction. Rather than spending time to identify and correct mistakes
during construction, all matters concerned were addressed at the planning
stage, with solutions implemented to ensure a smooth run and minimise
extra cost in the project process.
The first step for building a successful project team requires the right mix
of people. During the tender review process, Contractors were asked to
raise any concerns or past unsatisfactory experiences with the proposed
consultant, allowing views from all parties to be captured and evaluated
while forming a project team. The Consultant was working alongside the
Contractor as part of the project team. All issues in relation to the project
design were discussed openly and resolved promptly with the direct
involvement of the Consultant. Genuine effort on putting in the best and
right team for the project was made by both Contractor and Client.
There were frequently face-to-face meetings between the Client (Client’s
Representative), Contractor and Consultant at senior management level
during the project. The Contractor recognised establishing good
relationships with project parties also meant future job opportunities.
There was no hidden agenda between the parties. An open book system
was adopted in the project; the Client and Project Director had access to
the Contractor’s financial situation, putting further weight on open
communication and development of trust. There were effective working
relationships between Client’s Representative and Contractor in the
project, especially for exploring innovative solutions and bringing down
costs due to the overheated market. Subcontractors were also brought
onboard for both relationship management workshops and monthly
meetings during construction. The Subcontractors’ technical expertise
was shared amongst the team, and coordination issues which had great
141
CHAPTER 7 CASE STUDIES
impact on the project process were examined and included in the project
plan.
There was strong buy-in of relational contracting at all levels. Clauses with
strong references to relational contracting philosophy were stated in the
contract. Different project levels saw how they were benefited from
relational contracting principles and process in practice. Because of the
strong support and commitment from all parties’ senior management level
during the project construction, there were speedy decisions from the
higher level; project team members on-site were able to focus on getting
the job done. Common goal alignment on ‘best for project’ was apparent
at all levels.
There was open and honest communication in the project team at all
levels. Knowledge and ideas were shared between all parties including
Subcontractors. Relationships between Contractor and Subcontractors
were good, and better than on projects delivered under traditional
contracts. The relational contracting culture in the project team was
developed and maintained through on-going workshops, where major
relationship management workshops were facilitated by an external
facilitator for the best outcome for all parties. The importance of a third
party facilitator was identified in the project. With all project parties’
genuine effort, the project finished on time, within project budget and at
top quality.
7.3 Discussion
The research study identified common characters for successful and failed
relationship contracts arising from the case studies. In Australia, there are
four levels (namely the Inspector, Engineer, Project Manager and Director
levels) at which relational contracting (RC) needs to operate, and each
level has its own issues.
142
CHAPTER 7 CASE STUDIES
Different issues at different levels
At the Inspector/Foreman level, the issue in the relationship is getting the
job done. At the Engineer level, the issue is quality and claims, and
keeping the job moving. However, the Engineers are not empowered to
make final decisions such as claim issues, and are sandwiched between
inspectors/foremen and Superintendent/Project Manager. The main focus
for the individuals is actually the quality of work life and, similarly to
inspectors/foreman, getting the job done. At the Superintendent
(Representative)/Project Manager level, the major issue is performance
measures and claims, and contract administration. Lastly, at the
Principal/Director level, the major issue is strategy and claims
management. It can be seen that the relationships within the project team
are focused on very different issues at these four different levels. The
benefits of RC need to be recognised at all levels for it to be applied
effectively. On the other hand, the RC process needs to be set up in a
way that would benefit the project team.
Understanding RC principles
Good project team relationships were found in all successful RC contracts;
where strong support and commitment were received from all levels in the
project team. In most cases, RC principles were introduced to participants
through RC foundation workshops and their observations during monthly
RC meetings, when project construction was taking place. In some
instances, the RC arrangement was applied from the tender selection
stage, where participants believed their knowledge of RC had increased
during the process. RC workshops in the tender selection and
construction stages allowed foreseeable issues to be raised and solved.
The project team was alerted and took precautions while dealing with the
143
CHAPTER 7 CASE STUDIES
potential issues, rather than spending extra resources including time and
money to rectify mistakes.
Tender system
Having sufficient money in the contract was identified as a fundamental
characteristic of successful RC contracts. Contractors’ positive or
negative behaviours were found to have strong relationships with meeting
the project profit line or not. Contractors tend to bid low when submitting a
tender, and focus on recovering cost during construction. It was pointed
out in chapter 4 that the current tender selection/evaluation process in the
Queensland Government depends largely on the lowest bid win, while
non-cost criteria have been neglected. The system has driven some
Contractors to put in unreasonably low tender prices in order to secure the
job; and aim to recover profit through on-going claims during the project.
Such behaviour was reflected in various case studies and subsequently
led to a lack of goal alignment in the project team. Projects finished after
their due date, with a long battle on legal provisions, where additional time,
cost and human resources were spent. A strategic issue arises here – the
tender evaluation/selection process needs to be reviewed; where the
value of non-cost criteria should be increased by including relationship
aspects such as the Contractor’s past performance, their relationship with
Subcontractors, and attitude towards and experience with RC .
Commitment at all levels
RC would not succeed without continuous and strong support from the
senior management level in parent organisations. Many participants were
new to RC, and therefore did not understand the RC principles and
system. Also, RC was often misunderstood by the Contractor as a ‘mates
rates’ approach. It is crucial for project participants to be exposed to the
right concept of RC and the system. Relationship foundation workshops
144
CHAPTER 7 CASE STUDIES
should be held upon contract award for the whole project team, including
both senior management and operational levels; newcomers to the project
team should be given induction to RC principles and operation. As was
pointed out earlier, different levels in the project team have different
issues, buy-in of RC at all levels would only be strong when each level
understands and benefits from the RC process. Most importantly,
participants at operational level will become participants at senior
management level in future. This also raises an education and training
issue, where RC principles should be introduced at an early stage, before
entering the industry. The benefits of practising RC principles prior to
construction stage were highlighted in the case studies.
Education and training
During interviews, it became apparent that the endorsement of the RC
arrangement depends mostly on the client body. Clients must be
educated to recognise the benefits of RC. They must be weaned away
from the practice of letting projects to the lowest tender submission. They
must have the right attitude towards RC; and must acknowledge that the
Contractor is entitled to a reasonable profit. The perception of RC as a
one-off approach was also observed. RC should not be seen as a one-off
approach which can be switched on and off as necessary. It is in fact an
overriding philosophy and a sea-change in the industry’s culture, leading
to changed attitudes and collaborative, proactive project management.
There is a need to promote the concept of RC as ‘business as usual’ and
effectively drag the industry into a new era. This is an education and
training issue that needs to be addressed at trades and
tertiary/professional levels; and needs to be driven by the involvement of
the construction industry groups – clients, contractors’ and suppliers’
associations, professional institutions and consultants associations.
145
CHAPTER 7 CASE STUDIES
Short-term benefits
Short-term benefits need to appear and be recognised at project level to
retain continuous commitment from the project participants. The RC
process provides more opportunities for open and face-to-face
communication and discussion between participants. When the ‘protective
barrier’ of ‘paper warfare’ is broken down by a collaborative approach, the
need to formally document every discussion or event disappears and the
traditional, contract specified route for resolution of discrepancies is
circumvented. Participants are more comfortable at devolving decision-
making to appropriate levels within the organisation and greater job
satisfaction ensues.
‘More enjoyable to go to work’ was a commonly cited view of RC. When
the adversarial nature of the conventional contract is replaced by
collaborative, proactive working, participants find work more rewarding and
enjoyable - people enjoy going to work in an atmosphere which allows
each to make a positive contribution to moving the project forward; where
a sense of accomplishment is obtained.
Right mix of people
Getting the right mix of people in the project team is crucial for the success
of RC. Project participants need to have the right personalities and
attitude towards the application of RC. Strong commitment from the senior
management levels is needed. In some instances the author came across
examples embodied in the phrase ‘one bad apple can ruin the barrel’, this
reinforces the importance of getting the right mix of project team
participants. Both Client and Contractor must be prepared to replace the
unsuitable participant in the project team as soon as possible to relieve
stress being placed on project team relationships and project progress.
146
CHAPTER 7 CASE STUDIES
RC process and benefits
Through formal RC processes such as RC workshops and monthly RC
meetings, participants were exposed to issues arising from different levels,
allowing the big picture to be seen. Project participants became more
proactive, cooperative and collaborative in solving problems and
exchanging ideas. Trusting relationships amongst project participants
were enriched through informal process such as social functions
(barbeques, lunches) and informal communications. It is noted that the
informal RC process was not practised in any of the unsuccessful projects.
By building a level of trust and being convinced of the Contractor’s
competence and trustworthiness, the Client’s staff can be freed from the
chore of being on the spot all the time in order to supervise. When the
situation arises, not only is work more enjoyable but time can be spent on
more creative issues and more focus can be given to creating an excellent
project.
In a similar manner, the Contractor can usefully make savings also. The
Client is capable of providing assistance on the technical and knowledge
aspects of the project and can, in a RC approach, provide faster, better
and more solutions to construction problems. More harmonious working
relationships allow both parties to focus on work issues rather than other
contractual issues. The Client becomes more proactive in helping the
Contractor, saving both cost and time, so Contractor staff can move onto
another project. The lower level of necessity to use formal channels and
documentation allows for more focus on project problem-solving, but this
new regime is dependant on trust being established. Undoubtedly, the
sources of claims and variations still need to be documented, but this is
not the main focus of either party.
In situations where external circumstances, such as an overheated
market, adversely affect a Contractor’s ability to perform to the highest
147
CHAPTER 7 CASE STUDIES
standard, RC focuses on maintaining project performance whilst accepting
that a commercial solution to problems will be sought. Project participants
are allowed to focus on attaining timely, quality completion and
maintaining reputation and honesty, which then allows commercial issues
to be resolved in a more appropriate setting whilst maintaining a proactive
attitude on site.
RC encourages open and honest communication in the project team. RC
processes, such as the relationship selection workshop and relationship
foundation workshop, provide an ice-breaking platform for project
participants. The role of facilitator is crucial in this process. By facilitating
from the outset an atmosphere that promotes open communication and
willing cooperation, a brainstorming approach to project solving and a
value engineering approach can be brought to bear on project issues and
solutions. To maintain and develop non-adversarial attitudes and RC
culture, continuous RC workshops should be used throughout the life of a
project, ensuring open and continuous communication in the project team.
RC was successful where there was a strong sense of acknowledgement
and respect in the project team, and there were lots of positive
communications in the project team during monthly RC meetings. In
cases where RC failed, there was negative communication and a strong
blame culture. There was a lack of forward planning; former issues and
past incidents were focused on and repeated. Another common
characteristic found during relationship downturn or in failed RC projects
was a lack of prompt follow-up actions. Even where there was high
frequency of open communication and discussion during project team
meetings, if problems identified were not taken care off or reacted upon, it
created frustrations in the team, especially at the foreman and engineer
levels. The RC arrangement was perceived to be an adjunct to the
project, and lip service was paid rather than constructive actions. This not
only limits RC benefits, but a negative impression towards RC in practice
might be gained due to extra time and efforts that were spent in
148
CHAPTER 7 CASE STUDIES
arrangements such as monthly RC meetings, without any evident concrete
improvements in the project delivery process. Training and education
needs to be focused on the skills and techniques and philosophy of RC, in
order to facilitate the move from adversarial to proactive relationships in
the project team.
Role of facilitator
The role of facilitator is crucial in the RC process. However, the cost of
employing an external facilitator is also very high, which subsequently
affects the frequency of the facilitator’s involvement in the process. Most
participants felt that the facilitator should be a neutral party to the project
but there are situations where one or other party has supplied a facilitator
and the process has been successful. Either employing a third party as a
facilitator or a Contractor supplying its own facilitator are scenarios which
can work successfully.
7.3.1 Postscripts
RC and Subcontractors
The roles of Contractor and Client in successful RC implementation are
clear in this study. However, implementation of RC also requires
involvements from the supply chain to be truly effective. Participants
realise the benefits of a Subcontractor’s involvement in project process,
including knowledge exchange, innovative construction methods and
integration of design. However, some participants disagree that
Subcontractors should be brought into the RC process because
Subcontractors have difficulties in accepting RC, due to different culture
and interpersonal skills, and would expect to be paid extra for sharing
expertise. Recent studies by Dainty, Briscoe and Millett (2001) indicate
that Subcontractors held generally negative views of partnering and supply
chain management. Those Subcontractors believed some Main
149
CHAPTER 7 CASE STUDIES
Contractors did not understand the principles of partnering and alliancing
fully, and their motivations for adopting such approaches were not for
engaging mutual trust, support and benefit throughout the supply chain
(Ibid, p. 844); so there was a lack of integration of Subcontractors in the
project organisation structure.
This takes us back to square one. Subcontractors would keep having
difficulties and negative views on adapting RC culture and process if they
were not integrated into the project organisation structure at all. Major
Subcontractors’ engagement in the RC process has also proven beneficial
and successful (see case studies 2 & 3).
The involvement of a Subcontractor in the RC process is voluntary in the
current system, and it depends solely on the Contractor. Clients need to
take the lead on formal Subcontractor engagement in project organisation
structure; for example, by stating in contract documents that the Main
Contractor is required to involve major Subcontractor(s) in the RC process.
This allows Subcontractors to be exposed to the project structure and
immediate knowledge sharing as well as minimising error during
information transfer. For effective integration between project parties,
Subcontractors need to be familiar with RC principles and RC in practice,
and this raises the training and education issue. Continuous training and
education is needed to promote the concept of RC as ‘business as usual’
effectively in the industry.
Project parties must have the right attitude to RC. The Client must
acknowledge the Contractor is entitled to a reasonable profit; and the
same principle also needs to be applied between Main Contractor and
Subcontractors. The Contractor should treat Subcontractors fairly, where
all parties are on a level playing field. An appropriate attitude from the
Contractor may be encouraged by an inclusion of non-price criterion
150
CHAPTER 7 CASE STUDIES
during tender evaluation regarding the Main Contractor’s relationship with
Subcontractors.
Inflexible Contract
Research in case studies shows a relationship contract is still inflexible.
The situation is apparent when it is the Client’s money, the Client’s
Representative’s contract. The Client needs to have the right mindset
about RC and understand RC principles, which raise the importance of
client management. Whether RC will be adopted in projects or not
depends mostly on the Client. One major role of the Client’s
Representative is to safeguard the Client’s interest. The mindset of selling
all project risks to the Contractor/delivery team, which subsequently leads
to unfair risk sharing, is still strong in Clients and Client’s Representatives.
One must be aware that this is the major driver of an adversarial
relationship between Client and Contractor (see Chapter 4). There must
be mutual obligations for the Client in RC; risks cannot be transferred to
the Contractor solely but need to be shared between project parties for
effective RC application. Incentive systems based upon risk/reward
mechanisms have been adopted for a level playing field, and to encourage
positive cooperation behaviour between project parties, through
formalising a RC arrangement in the contract. This prompts concern
about whether the RC arrangement would supersede the contract; or on
the other hand if a formal RC contract can safeguard against any
breakdown of the RC arrangement. Although different types of contract
might have different implications for project parties’ behaviour and attitude,
the formality of a contract provides a structured framework of RC process
and arrangement. Case studies presented earlier in this chapter show
that, through RC arrangements and an on-going maintenance process (for
example project participants were put in the same office), proactive and
collaborative behaviours between project participants were developed and
151
CHAPTER 7 CASE STUDIES
maintained throughout the project, suggesting the driver of project parties’
behaviour and attitude is not contract formality but on-going process.
A RC arrangement was found successful in some cases, but unsuccessful
in others. Where RC has failed, RC principles were not fully endorsed in
the project and not all project participants held the right attitude towards
RC. One may argue RC is not suitable for all projects, and not everyone is
suited to the RC culture. One might even find a RC arrangement a waste
of time and it should be abolished at once when the system is not working.
Yet, without relationship management, the project could have been worse!
Through monthly relationship process meetings, project participants at all
levels are placed in a structured setting for face-to-face communication.
Although communications and information transfers are carried out in
formal settings as opposed to proactive collaboration, communication
channels are still open and project members at the operational level can
focus on keeping the job going. The relationship might not be good, but
people are bound in a RC environment and they are still talking. Project
team members are exposed to project issues at all levels. However, in a
traditional contract environment, there would be no direct communication
between project parties, only through legal proceedings. In consequence,
it creates an adversarial environment in the project team and extra
pressure at the operational level. Engineers are sandwiched in the
middle, unable to provide quick decisions and directions to the workers
due to the long wait in the ‘paper-war’, preventing foremen/inspectors from
getting their jobs done.
Based on the research findings, an Input-Process-Output map is
presented overleaf.
152
CHAPTER 7 CASE STUDIES
Figure 7.1: Input-Process-Output Map based on Research Findings
Parent Organisation Culture � Leadership and
Management • Commitment
� Internal Factors
• Selection of project team members
• Filtration of RC concept to all levels
� Process Set-up
• Relationship management process structure
• Relationship maintenance process
� Tender System
• Documentation • Evaluation
(Process Maintenance)
Relational Contracting Environment � Project Culture
• Commitment • Goal alignment • Communication • Relationship
management understanding
� Relationship Start-
up • Foundation
workshop • RM process
attendees • Involvement of
major sub-contractor(s)
� Relationship
Process Evaluation • Monthly
relationship meeting
� Process
Maintenance • On-going
facilitations • Training and
education • On-going
Workshops � Learning Register
• Problem solving techniques
• Team building � Physical site
location
Outcomes � Organisation Level
• Fast track project problem resolutions and variations
• Staff up-skilling • Future job
opportunities � Individual Level
• Job satisfaction • Relational
contracting culture
• Ability to meet or close up issues at own level
� External Factors • Market
condition e.g. over-heated market
• Resource and materials availabilities
• Political influence
INPUT PROCESS OUTPUT
153
CHAPTER 8
CONCLUSION
8.1 Introduction
The aim of this research has been to identify the key determinants of
effectiveness in relational contracting in the construction industry.
Based on the research findings, the following conclusions are drawn.
Relational contracting appears to suit the Australian culture very well.
Continuous commitment to relational contracting is required at all levels for
successful implementation. This leads to a third finding, that
organisational culture and structure must be matched if participants are to
retain commitment to the organisation. Relational contracting
implementation should be a continuous process, which needs to be
constantly maintained and facilitated to retain effectiveness. Lastly, this
research suggests that, through education and training, relationship
management culture is embedded in people’s mindset, shifting the
industry culture towards a more proactive and collaborative nature.
154
CHAPTER 8 CONCLUSION
8.2 Research Hypotheses
In general, the results of this research support the research hypotheses
listed below.
Hypothesis 1: Organisational culture and organisati on structure
must be matched if participants are to retain commi tment to the
organisation.
Findings in chapter 6 suggest the degree of match and mismatch between
organisation culture and structure has an impact on staff’s commitment
levels. Hypothesis 1 is accepted. Findings also point out mismatches
exist between actual and perceived organisational culture and structure.
The reasons for these mismatches appear to be different cultures between
parent organisation and intra-organisation (project); which leads to
hypothesis 2 below.
Hypothesis 2: Parent organisation culture affects t emporary
project culture.
Senior management set the tone for relational contracting and must
provide infrastructure for relational contracting to succeed. Findings in
chapter 6 and 7 also point out strong and continuous commitment from
senior management is crucial for relational contracting to be successful at
the project level. Parent organisation culture, whether it is adversarial or
collaborative in nature, directly affects how the project team operates and
its temporary project culture.
Hypothesis 3: Encouragement by organisation to exhi bit
cooperative behaviour amongst employees leads to gr eater
cooperation between individuals.
Findings in chapter 7 shows formalised relational contracting
arrangements in project organisations increase the frequency of
cooperation and collaboration between project participants. Project
155
CHAPTER 8 CONCLUSION
participants become more proactive, cooperative and collaborative in
solving problems. Hypothesis 3 is accepted.
8.3 Conclusions
The research findings suggest relational contracting suits the Australian
culture very well. Australian professionals prefer physical interactions and
direct confrontation when dealing with matters. Well-run relational
contracting projects are satisfying to work in; they make work enjoyable
and lead to enhanced professional development. However, not everyone
is suited to relational contracting. Getting the right mix of people in a
project team has been identified as one of the most crucial elements for
the success or failure of a relationship contract. In order to maintain
harmony and an effective working atmosphere, senior management and/or
the parent organisation must be prepared to remove unsuitable member(s)
from the project team. Through a structured context, relational contracting
increases both formal and informal communications amongst team
members. Higher frequency of communication does not necessarily lead
to better team relationships or more collaborative problem solving
behaviour. Instead, good team relationships and collaborative behaviour
are found where respect and acknowledgment are expressed amongst
team members. The range participants from across the organisation who
take part in meetings in relational contracting projects appears to have a
positive impact on the quality of communication and information flow, and
is a stimulus to timely and appropriate action. Informal communication is
essential for relational contracting but it needs to be undertaken in an
appropriately structured environment with appropriate procedures.
This research suggests the degree of match and mismatch between
organisation culture and structure has an impact on staff’s commitment
levels. This study corroborates previous work in that the fundamental
element for successful implementation of changes is strong buy-in from
156
CHAPTER 8 CONCLUSION
top management. This research indicates buy-in is not only crucial at the
senior management level, but at all levels for successful implementation.
In this case, the relational contracting concept needs to filter down to all
levels in the project team if team members are to retain commitment and
buy-in to relational contracting. This research identifies there are four
levels in Australia at which relational contracting needs to operate and that
each level has its own issues which must be reflected upon. Research
findings show that a lack of prompt follow-up actions or not closing up
issues leads to downturn or failure in relational contracting.
This research points out that mismatches between organisation and
project (temporary intra-organisation) cultures must be recognised and
accepted by organisation staff. The parent organisation obviously
influences project culture; commitment to the goals and objectives of an
organisation is crucial in facilitating successful implementation of relational
contracting or organisational changes. Having sufficient money in a
contract remains vital for project success. The tender selection/evaluation
process needs to be reviewed; where the value of non-cost criteria should
be increased by including relationship aspects.
Relational contracting should not be seen as a one-off approach which
can be switched on and off as one wishes. It is an overriding philosophy
and sea-change in the industry culture. Concepts of relational contracting
should be promoted as ‘business as usual’. Relational contracting needs
to be constantly maintained and facilitated to retain effectiveness.
Relational contracting maintenance and review process should be set up
before a project begins. Facilitation is needed to enable open, blame-free
communication and this facilitation must be ongoing throughout the life of
a project. The role of facilitator in achieving a relational contracting culture
is highlighted in this research.
157
CHAPTER 8 CONCLUSION
A relationship contract can be inflexible. This situation is apparent when it
is the Client’s money and the Client’s Representative’s contract. The
Client’s Representative acts as a gatekeeper in the project to safeguard
the Client’s interest by transferring all project risks to the
Contractor/delivery team. The unfair risk sharing mindset remains strong
in both Clients and Client’s Representatives. Also, whether to adopt a
relational contracting approach in a contract depends highly on the Client.
The Client needs to be educated on the benefits of relational contracting
and to adopt the right attitude towards relational contracting. Client
management is a crucial issue for the prosperity of relational contracting.
The involvement of Subcontractors in the relational contracting process
has proven highly valuable for knowledge exchange and innovations.
However, the participation of the Subcontractor in the relational contracting
process is voluntary in the current system and it depends solely on the
Contractor. Major Subcontractors should be introduced to the relational
contracting process and be formally engaged in the project organisation
structure. Project parties must have the right attitude to relational
contracting. The Client must acknowledge that the Contractor is entitled to
a reasonable profit; and the Contractor should treat Subcontractors fairly,
where all parties are on a level playing field. This research suggests an
appropriate attitude from the Contractor may be encouraged by an
inclusion in tender evaluation of a non-price criterion on the Main
Contractor’s relationship with Subcontractors.
Project parties need to be familiar with relational contracting principles and
relational contracting in practice for effective integrations. This brings us to
the last conclusion of this research, that education and training is an
imperative element for achieving effective relational contracting.
Relationship management culture must be championed in organisations
through in-house workshops. Relationship management culture and
correct principles should be embedded in people’s mindset at an early
158
CHAPTER 8 CONCLUSION
stage. This research suggests the relational contracting concept should
be promoted through continuous training and education in universities and
institutions.
8.4 Limitations of the Research
A limitation of this research is the dearth of private sector data. The
findings from the questionnaire survey and interviews rely heavily on the
public organisational members. Observations and interviews at
multidiscipline levels as a methodology nevertheless provide some
protection from biased data when examining the project team as a whole.
However, the findings on organisation culture and structure only reflect the
public sector, rather than both public and private sectors in the
construction industry.
Due to time and resource constraints, the study of both sectors at multiple
multidiscipline levels remained a challenge for the researcher. In
achieving an overall prospective of the industry on relational contracting, it
is acknowledged that some depth and reliability achievable through
researching the private sector has been foregone. The findings from this
research have provided a significant platform on relational contracting
process for further research.
8.5 Areas for Future Research
Although this research focused on the public sector in Queensland, the
data collected from interviews and case studies also captured the
contractor side. An attempt has been made to develop a relational
contracting process framework. However, further research is required to
test the proposed framework by connecting with the key findings that
relational contracting much be constantly maintained and facilitated in
159
CHAPTER 8 CONCLUSION
order to be successful and turn it into an acceptable model for practical
application.
Although it is widely accepted that the client is the driver of change, this
research argues strong commitment and support are equally important
from all levels in the project team, which includes members from the
contracting side. As has been pointed out extensively in Chapter 6, there
is a strong relationship between the degree of personal acquaintance and
relationship productiveness. Similar research should also be conducted in
the private sector. By comparing and contrasting both sets of results, a
360-degree perspective on relational contracting will be generated, which
should enhance better understanding and more proactive collaborations
between both sectors.
APPENDIX I TRANSACTIONAL & RELATIONAL CONTRACTING
161
(adapted from Darwin et al. 2000 – p.41)
Transactional pole Relational pole
Communication is limited and formal Communication is extensive, and is both formal and informal
Everything is measured in monetary terms Many aspects are difficult to measure, either in monetary or in other terms. Parties do not measure them
The beginning and end of the contract relationship are clearly defined
The beginning and end, if any, of the contract relationship are gradual
Initial planning is complete and specific – only remote contingencies are not covered
There is limited specific planning at the beginning
There is little or no bargaining as the contract proceeds
The contract involved extended mutual planning – a “joint creative effort”
The contract agreement binds the partners totally
The agreement is tentative
Almost no cooperation is required after the start of the contract
The success of the contract is entirely dependent on further cooperation in both performance and further planning
Each particular benefit and burden is specifically assigned to one party
There is undivided sharing of both benefits and burdens
Specific rules and rights are applicable, based on agreement. These are usually measured in monetary terms
Rules and benefits are non-specific and non-measurable
No altruistic behaviour is expected or occurs
There is significant expectation of altruistic behaviour
Problems in performance or among the participants are not expected, except perhaps those planned for. If they occur, they are expected to be governed by specific rights
The possibility of trouble is anticipated and is dealt with by cooperation
AP
PE
ND
IX II
D
EF
INIT
ION
S O
F P
AR
TN
IER
ING
, AL
LIA
NC
ING
& R
C
16
3
PARTNERING ALLIANCING RELATIONAL CONTRACTING
Queensland Government – Dept. of Main Roads
• not a form of contract • a process applied outside the contract to
align the goals and objectives of the contract parties
• to facilitate good communication, teamwork and joint problem solving
• can be used in conjunction with any form of contract
• not necessarily legally binding • a way of conducting business in which two or
more organizations make long-term commitments to achieve mutual goals
• (project alliance) an agreement between two or more entities that undertake to work co-operatively
• share project risk and reward between parties
• achieve agreed outcomes based on principles of good faith and trust, with an open book approach towards cost
• a purpose built contract in which the client and the contractor form an alliance to build the works
• both parties develop and agree on the target cost estimate for the project
• a board drawn from both organizations manages the contract
• not a form of contract • a good relationship between two or more
parties that contributes towards the successful completion of a contract
• the provision of a collaborative or team approach to the achievement of project outcomes that are best for the project
Construction Best Practice Programme
Bronder & Pritzl
Cheung
• a structured management approach to facilitate team working across contractual boundaries
• fundamental components include mutual objectives, agreed problem resolution methods and an active search for continuous measurable improvements
• exists when the value chain between at least two organizations with compatible goal structures are combined for the purpose of sustaining and achieving significant competitive advantages
• can be collaborative or cooperative
• cooperative and proactive contracting environment
• flexibility and adjustments provisions to cater for unanticipated contingencies
• relation dispute resolution • parties are mutually dependent to each other • trust and cooperation are greatly heightened
AP
PE
ND
IX II
D
EF
INIT
ION
S O
F P
AR
TN
IER
ING
, AL
LIA
NC
ING
& R
C
16
4
PARTNERING ALLIANCING RELATIONAL CONTRACTING
Construction Industry Institute
Howarth, Gillin & Bailey
Alsagoff & McDermott, Jones, Rahman & Kumaraswamy
• experimental partnering, packaged partnering and committed partnering
• a long-term commitment between two or more organizations for the purpose of achieving specific business objectives by maximizing the effectiveness of each participant’s resources
• requires changing traditional relationships to a shared culture without regard to organizational boundaries
• relationship is based on trust, dedication to common goals and an understanding of each other’s individual expectations and values
• service alliances • requires the lowest level of interdependence
between partners with the smallest amount of changes and the lowest level of joint commitment
• provide economies of scale • provide the ability for the partners to
undertake large-scale projects with a limited purpose
• difficulties arise due to the diversity of the interests and goals of the partners
• result in a loss of commitment from members
• opportunistic alliances • Provide access to the resources of the
partner organization • Motivated by the existence and recognition
of a market opportunity • Partners might exploit one \another’s
resources and then move on to pursue the opportunity alone
• stakeholder alliance • the closest link between member
organizations of all • seek to build strong, long-term relationships • assist in achieving the organizational goals
by major stakeholders
• based on recognition of mutual benefits and win-win scenarios through more cooperative relationships between parties
• embrace and underpin various approaches such as:
• partnering • alliancing • joint venturing • collaborative working arrangements • better risk sharing mechanisms • long-term • develop and change over time • involve substantial relations between parties • the norm for complex transactions to be
conducted in high complexity environments, where complete contingency arrangements are impossible
AP
PE
ND
IX II
D
EF
INIT
ION
S O
F P
AR
TN
IER
ING
, AL
LIA
NC
ING
& R
C
16
5
PARTNERING ALLIANCING RELATIONAL CONTRACTING
European Construction Institute, Liu & Fellows
Wood & Gray
Blau, MacNeil, Rousseau & Parks, Darwin, Darwin et al.
• a method of improving communication mechanisms and technologies
• a method of responding to innovative construction
• creates a less stressful working environment • reduces transaction costs resulting from
uncertainty, competition and information asymmetry
• organizations enter collaborative relations • to reduce the complexity of their
environment • to gain more control over environmental
factors • may create new dependencies • may increase environmental complexity and
turbulence • may therefore increase transaction costs
• entails long-term social exchange between parties
• mutual trust • interpersonal attachment • commitment to specific partners • altruism • cooperative problem solving
Green
Hamel
Darwin, Jorde & Teece, Kanter, Lynch, Bolton et al.
• concerns with maximizing effectiveness • demands each project exceeds the
performance of the previous one • measure of success hinges on cost
improvement • more onto the buying power than to any
independent appraisal • to exercise increased control over the
construction supply chain • common goal with TQM – continuous
improvement
• can be collaborative or cooperative • collaborative alliances • organizations aware that their partners are
capable of disarming them • clear objectives • understand partner’s objective will affect
their success
• closely associated with partnerships and strategic alliances
• especially with contractors who avoid adversarial approaches to contract management
• entail long-term collaborative based on • informality • shared problem solving • reciprocity • high trust
AP
PE
ND
IX II
D
EF
INIT
ION
S O
F P
AR
TN
IER
ING
, AL
LIA
NC
ING
& R
C
16
6
PARTNERING ALLIANCING RELATIONAL CONTRACTING
Bennett and Jayes
Love & Gunasekaran
MacNeil
• a management approach used by two or more organizations to achieve specific business objectives by maximizing the effectiveness of each participant’s resources
• mutual objectives between organizations • agreed method of problem resolution • an active search for continuous measurable
improvements
• can be collaborative or cooperative • collaborative alliancing • help to establish the inter-organizational
relations • organizations engage in collaborative
behaviour for a specific purpose • a “psychological barrier” may exist between
partners • may fear that their partners may out-learn or
deskill them • cooperative alliances • encourage partners to commit their resources
to the relationship to gain mutual learning • lower level of competition • partners feel more committed to work
together • partners exchange their knowledge and
resources
• construction contracts are typical relational contracts
• involve numerous parties and subcontracts with heavy informational exchange in the construction activities
• parties are mutually depend to each other • provides the means to sustain ongoing
relations in long and complex contracts by adjustment processes of a more thoroughly transaction-specific, ongoing administrative kind
DETR
Hutchinson & Gallagher
Rahman & Kumaraswamy
• involves two or more organizations working together to improve performance through agreeing mutual objectives
• devises a way for resolving disputes • commits themselves to continuous
improvement • measures progress • shares the gains • a tool to tackle fragmentation
• an integrated high performance team selected on a best person for the job basis
• sharing all project risks with incentives to achieve gamebreaking performance in pre-aligned project objectives
• a framework of no fault, no blame and no dispute
• uncompromising commitments to trust, collaboration, innovation and mutual support
• objective is to achieve outstanding results
• “ongoing dynamic state” of relations among the contracting parties
• promises to do something in the future, in the process of “exchange” to the future
• involve transactional discreteness • partnering practices relational contracting
principles
AP
PE
ND
IX II
D
EF
INIT
ION
S O
F P
AR
TN
IER
ING
, AL
LIA
NC
ING
& R
C
16
7
PARTNERING ALLIANCING RELATIONAL CONTRACTING
Construction Industry Board
Hampson & Kwok
• establishment of agreed and understood mutual objectives
• methodology for quick and cooperative problem resolution
• culture of continuous, measured improvement
• successful strategic alliances • trust • commitment • interdependence • cooperation • communication • joint problem solving
Peters, Walker & Hampson
• relies solely on the commitment of individuals • not legally binding • aims and goals are agreed • dispute resolution and escalation plans are
established • partners retain independence • partners may suffer or gain from the
relationship individually
• 2 types of alliancing – strategic alliancing and project alliancing
• parties form a cohesive entity • parties shares risks and rewards according
to an agreed formula • strategic alliance • inter-organisational arrangement • relationship between parties extends beyond
a specific project • ongoing mutually beneficial business • project alliancing • defined end • parties brought together for a specific project • legally enforceable
AP
PE
ND
IX II
D
EF
INIT
ION
S O
F P
AR
TN
IER
ING
, AL
LIA
NC
ING
& R
C
16
8
PARTNERING ALLIANCING RELATIONAL CONTRACTING
Gaede, Reading Construction Forum, Matthews, Matthe ws & Rowlinson, Kumaraswamy & Matthews
• categorized as project partnering and strategic partnering
• project partnering • undertaken on a single project • partnering relationship terminated at the end
of project and new relationship commenced on the next project
• strategic partnering • takes place when two or more firms use
partnering on a long-term basis • usually undertaken in more than one project
or continuing construction activity
Watson, Reading Construction Forum
Manivong & Chaaya
• second generation partnering • “seven pillars” – strategy, membership,
equity, integration, benchmarks, project processes, feedback
• strategic decision
• project alliancing • a project delivery method • several participants join together to share
risks and outcomes on a project
Kubal
Kwok et al.
• required national lobbying in order for partnering to be used across industry
• project alliance • a cooperative arrangement between two or
more organizations • forms part of the organisations’ overall strategy • contributes to achieving their major goals and
objectives for a particular project
AP
PE
ND
IX II
D
EF
INIT
ION
S O
F P
AR
TN
IER
ING
, AL
LIA
NC
ING
& R
C
16
9
PARTNERING ALLIANCING RELATIONAL CONTRACTING
Watson, Kumaraswamy & Matthews, Matthews & Rowlinso n
• third generation partnering • construction industry should be building
virtual organizations with its supply chain to provide a complete service that is efficient, creative and innovative
• collaborative in producing and marketing a range of services that clients are eager to invest in
• cost saving construction time reducing
Wood & McDermott, Wilson & Wilson
• single-source, long-term relationships • business-focused • directed a t solving problems, rather than
simply selling products • trust is a key component • industry moves from competitive, adversarial
to cooperative relations based on reciprocity and solidarity
• encourages parties to adopt higher ethical standards with trust-based partnering
APPENDIX III CULTURE QUESTIONNAIRE
171
1 QUESTIONNAIRE 1
1.1 Description
Handy, C. (1985) Understanding Organisations , 3rd, Edition, Penguin, London. Handy defines 4 types of organisation: "Each organization, each part of an organization, has a culture, and a structure and systems appropriate to that culture. Individuals will each have a preferred culture.
Cultures Structures
power web
role temple
task net
person cluster
The choice of the appropriate structure will be determined by: • History and ownership; • Size; • Technology; • Goals and objectives; • The environment; • The people.
Within each organization the activities can be divided roughly into four sets:
• Steady state; • Innovation; • Breakdown; • Policy.
Each of these sets has its appropriate culture, structure and systems. Organizations that are differentiated in their cultures and who control that differentiation by integration are likely to be more successful. The management of differentiated organizations is not easy. Part Two will be mainly concerned with drawing attention to some of the problems. The problem is aggravated by the tendency of many management theorists and writers to remain rooted in their preferred culture. For instance:
1. Classical management theory was talking about role cultures - the management of the steady state.
APPENDIX III CULTURE QUESTIONNAIRE
172
2. Modern management thinkers concentrate on the task culture and have found their favourite organizations among the project-based companies of the US aerospace industry and the innovative ends of more traditional organizations.
3. Journalists, historians, and biographers have found the power cultures, centred around a key figure or figures, easier to focus on, more tempting to describe.
4. Sociologists, religious and youth leaders, have been concerned with the clash between the organization and the individual with a 'person' orientation.
Adapted from a questionnaire compiled by Dr Roger Harrison" By using Handy’s paradigms, the team can map where the organisation culture and organisation structure lie. If there is a mismatch, then this will have to be addressed before the change in the organisation can be successful – see Rowlinson’s paper on the HK Government organisation for an example of this. Reference: Rowlinson, S.M. (2001) “Matrix Organizational Structure, Culture and Commitment: a Hong Kong Public Sector Case Study of Change”, Construction Management and Economics, 19, 669-673.
APPENDIX III CULTURE QUESTIONNAIRE
173
1.2 Instructions Please complete this questionnaire individually.
(a) For yourself, your own values and beliefs; (b) For your own organisation.
Rank each statement in order of salience, put ‘1’ against the statement which best represents the dominant view in your own beliefs, ‘2’ for the next closest. Then go back and do the same for your organisation.
APPENDIX III CULTURE QUESTIONNAIRE
174
1.3 Questionnaire
Own Ranking
Organisation’s Ranking
1. A good boss
is strong, decisive and firm but fair. He/She is protective, generous and indulgent to loyal subordinates.
is impersonal and correct, avoiding the exercise of his/her authority for her/his own advantage. She/He demands from subordinates only that which is required by the formal system.
is egalitarian and influenceable in matters concerning the task. He/She uses his/her authority to obtain the resources need to get on with the job.
is concerned and responsive to the personal needs and values of others. She/He uses her/his position to provide satisfying and growth stimulating work opportunities for subordinates.
2. A good subordinate
is compliant, hard-working and loyal to the interests of his/her superior.
is responsible and reliable, meeting the duties and responsibilities of her/his job and avoiding actions which surprise or embarrass her/his superior.
is self-motivated to contribute his/her best to the task and is open with his/her ideas and suggestions. He/She is nevertheless willing to give the lead to others when they show greater expertise or ability.
is vitally interested in the development of her/his own potentialities and is open to learning and receiving help. She/He also respects the needs and values of others and is willing to give help and contribute to their development.
3. A good member of the organisation gives first prior ity to
the personal demands of the boss.
the duties, responsibilities and requirements of her/his own role, and the customary standards of personal behavior.
the requirements of the task for skill, ability, energy and material resources.
the personal needs of the individual involved.
APPENDIX III CULTURE QUESTIONNAIRE
175
Own Ranking
Organisation’s Ranking
4. People who do well in the organisation
are shrewd and competitive with a strong drive for power.
are conscientious and responsible with a strong sense of loyalty to the organisation.
are technically competent and effective, with a strong commitment to getting the job done.
are effective and competent in personal relationships, with a strong commitment to the growth and development of people.
5. The organisation treats the individual
as though his/her time and energy were at the disposal of the persons higher in the hierarchy.
as though her/his time and energy were available through a contract having rights and responsibilities on both sides.
as a co-worker who has committed his/her skills and abilities to the common cause.
as an interesting and worth-while person in her/his own right.
6. People are controlled and influenced by
the personal exercise of economic and political power (rewards and punishments).
impersonal exercise of economic and political power to enforce procedures and standards of performance.
communication and discussion of task requirements leading to appropriate action motivated by personal commitment to goal achievement.
intrinsic interest and enjoyment in the activities to be done; and/or concern and caring for the needs of the other persons involved.
7. It is legitimate for one person to control another’ s activities
if he/she has more authority and power in the organisation.
if her/his role prescribes that she/he is responsible for directing the other.
if he/she has more knowledge relevant to the task at hand.
if the other accepts that the first person’s help or instruction can contribute to the other’s learning and growth.
APPENDIX III CULTURE QUESTIONNAIRE
176
Own Ranking
Organisation’s Ranking
8. The basic of task assignment is
the personal needs and judgment of those in authority.
the formal divisions of functions and responsibility in the system.
the resource and expertise requirements of the job to be done.
the personal wishes and needs for learning and growth of the individual organisation members.
9. Work is performed out of
hope of reward, fear of punishment or personal loyalty towards a powerful individual.
a respect for contractual obligations backed up by sanctions and personal loyalty towards the organisation or system.
satisfaction in excellence of work and achievement and/or personal commitment to the task or goal.
enjoyment of the activity for its own sake and concern and respect for the needs and values of the other persons involved.
10. People work together
when they are required to by higher authority or believe they can use each other for personal advantage.
when coordination and exchange are specified by the formal system.
when their joint contribution is needed to progress the task.
when the collaboration is personally satisfying, stimulating or challenging.
11. Competition
is for personal power and advantages.
is for high status position in the formal system.
is for excellence of contribution to the task.
is for attention to one’s own personal needs.
APPENDIX III CULTURE QUESTIONNAIRE
177
Own Ranking
Organisation’s Ranking
12. Conflict
is controlled by the intervention of higher authority and often fostered by them to maintain their own power.
is suppressed by reference to rules, procedures and definitions of responsibility.
is resolved through full discussion of the merits of the work issues involved.
is resolved by open and deep discussion of personal needs and values involved.
13. Decisions
are made by the person with the higher power and authority.
are made by the person whose job description carries the responsibility.
are made by the persons with most knowledge and expertise about the problem.
are made by the persons most personally involved and affected by the outcome.
14. The appropriate control and communication structure
command flows from the top down in a simple pyramid so that anyone who is higher in the pyramid has authority over anyone who is lower. Information flows up through the chain of command.
directives flow from the top down and information flows upwards within functional pyramids which meet at the top. The authority and responsibility of a role is limited to the roles beneath it in its own pyramid. Cross functional exchange is constricted.
information about task requirements and problems flows from the center of task activity upwards and outwards, with those closest to the task determining resources and support needed from the rest of the organisation. A coordinating function may set priorities and overall resource levels based on information from all task centers. The structure should shift with the nature and location of the tasks.
information and influence flow from person to person, based on relationships which are voluntarily entered into for purposes of work, learning, mutual support and enjoyment, and shared values. A coordinating function may establish overall levels of contribution needed for maintenance of the organisation. These tasks are assigned by mutual agreement.
APPENDIX III CULTURE QUESTIONNAIRE
178
Own Ranking
Organisation’s Ranking
15. The environment 1 is responded to as though it were
a competitive jungle in which all are against all and those who do not exploit others are themselves exploited.
an orderly and rational system in which competition is limited by law and conflicts yield to negotiation and compromise.
a complex of imperfect forms and systems which are to be re-shaped and improved by the achievements of the organisation.
a complex of potential threats and support. It is to be manipulated by the organisation to extract nourishment from it, pull its teeth and use it as a play and work space for the enjoyment and growth of member.
Thank you for your time.
Please turn over for Questionnaire 2.
1 Environment here refers to your work environment.
APPENDIX III CULTURE QUESTIONNAIRE
179
2 QUESTIONNAIRE 2
2.1 Description Allen, N.J. & Meyer, J.P. (1990), The Measurement a nd Antecedents of Affective, Continuance and Normative Commitment to the Organis ation, Journal of Occupational Psychology , 63, 1-18. In studying commitment, the team will be able to draw conclusions as to where strengths and weaknesses lie in the organisation at present and to develop plans to address these. An alliancing approach cannot succeed if the collab orating organisations do not accept its ethos. Hence, commitment to the goals and objectives of the organisation is crucial in implementing new approaches to contract strategy. Allen and Meyer define three “types” of commitment:
• Affective commitment is an emotional attachment to the organisation • Normative commitment is based on acceptance of the organisation’s set of
values • Continuance commitment dimension is based on the idea that the costs of
leaving the organisation outweigh the opportunity costs of staying
APPENDIX III CULTURE QUESTIONNAIRE
180
2.2 Affective, Continuance and Normative Commitment Scales 2.2.1 Affective Commitment Scale Please use the scaling below to rate the following items. 1 – Strongly disagree
2 – Moderately disagree 3 – Slightly disagree 4 – Neither agree nor disagree 5 – Slightly agree 6 – Moderately agree 7 – Strongly agree Note: Please check only one box for each item. 1 2 3 4 5 6 7
1. I would be very happy to spend the rest of my career in this organisation.
2. I really feel as if this organisation’s problems are my own.
3. I do not feel like “part of the family” at my organisation.
4. I do not feel “emotionally attached” to this organisation.
5. This organisation has a great deal of personal meaning for me.
6. I do not feel a strong sense of belonging to my organisation.
APPENDIX III CULTURE QUESTIONNAIRE
181
2.2.2 Continuance Commitment Scale Please use the scaling below to rate the following items. 1 – Strongly disagree
2 – Moderately disagree 3 – Slightly disagree 4 – Neither agree nor disagree 5 – Slightly agree 6 – Moderately agree 7 – Strongly agree Note: Please check only one box for each item. 1 2 3 4 5 6 7
1. It would be very hard for me to leave my organisation right now, even if I wanted to.
2. Too much of my life would be disrupted if I decided I wanted to leave my organisation right now.
3. Right now, staying with my organisation is a matter of necessity as much as desire.
4. I believe that I have too few options to consider leaving this organisation.
5. One of the few negative consequences of leaving this organisation would be the scarcity of available alternative.
6. If I had not already put so much of myself into this organisation, I might consider working elsewhere.
APPENDIX III CULTURE QUESTIONNAIRE
182
2.2.3 Normative Commitment Scale Please use the scaling below to rate the following items. 1 – Strongly disagree
2 – Moderately disagree 3 – Slightly disagree 4 – Neither agree nor disagree 5 – Slightly agree 6 – Moderately agree 7 – Strongly agree Note: Please check only one box for each item. 1 2 3 4 5 6 7
1. I do not feel any obligation to remain with my current employer.
2. Even if it were to my advantage, I do not feel it would be right to leave my organisation now.
3. I would feel guilty if I left my organisation now.
4. This organisation deserves my loyalty.
5. I would not leave my organisation right now because I have a sense of obligation to the people in it.
6. I owe a great deal to my organisation.
Thank you for your time.
Please turn over for Questionnaire 3.
APPENDIX III CULTURE QUESTIONNAIRE
183
3 QUESTIONNAIRE 3
3.1 Description Van de Ven A.H. and Ferry, D.L. (1980) Measuring and Assessing Organisation s. Wiley, New York. This instrument measures a whole series of organisational parameters including individual motivation, work processes and organisational structure. Winch et al found autonomy at work, work coordination and work control along with job satisfaction, motivation and feedback instrumental in ensuring effective cooperation and collaboration. Some of these dimensions relate to how an organisation structures itself and how others relate to how individuals manage and are managed. It is anticipated that the dimensions investigated here will pinpoint weaknesses and strengths in organisation structure and also help in determining the skill sets required for successful alliance team building. This questionnaire will be targeted at specific individuals who have been identified as holding key positions in the project management process as it is very detailed and will take quite some time to complete. It is anticipated that it will be used in conjunction with interviews of these individuals. Some of the information collected here mirrors information collected in QPASS, the QMR annual employee survey. However, the objective in this research is to target projects and project participants and their relationships throughout the organisation. Hence, the general overview provided by QPASS, although providing a very good overview, cannot assist in collecting this very specific data.
APPENDIX III CULTURE QUESTIONNAIRE
184
3.2 OAI Focal Unit Questionnaire 3.2.1 General Instructions Definitions: This questionnaire asks many questions about your unit and other units.
• Your unit includes you (as the supervisor) and all individuals who report directly to you. If you are not a supervisor, then your unit includes your immediate supervisor and all individuals (your co-workers) who directly report to your immediate supervisor.
• Other units refer to any other groups, departments, levels, or divisions within or outside of your organisation that your unit coordinates with.
This questionnaire asks you to answer each question five times, once for each of the five most important other units that your unit coordinates with. These other units are listed in the columns to the right of the questions. For each question there is a five-point answer scale with brief descriptions of what the numbers on the scale represent. You are to descriptions of what the numbers on the scale represent. You are to choose one number that most accurately reflects your answer to each question for each other unit and write it in the appropriate column. For example, if you were asked the following question, and your answers were “daily”, “monthly”, “hourly”, “never” and “weekly” for other units 1 – 5, respectively, then you would write the numbers “4”, “2”, “5”, “1” and “3” in the appropriate columns for the other units like this:
How often were you in contact with this other unit during the past six months?
YEARLY MONTHLY WEEKLY DAILY HOURLY Unit 1 Unit 2 Unit 3 Unit 4 Unit 5
1 2 3 4 5 4
2
5
1
3
If you do not understand any question, BE SURE TO ASK US FOR HELP. We realise that not all questions are simple, and that is why we are here to answer any questions you have.
APPENDIX III CULTURE QUESTIONNAIRE
185
3.2.2 Introductory Questions The following questions are very important for properly coding and analysing the data. As indicated before, all responses will be kept strictly confidential.
1. Name of the ORGANISATION in which you work:
2. Name of DIVISION in which you work:
3. Name of OFFICE or CITY in which you work:
4. Name of UNIT in which you work:
5. YOUR NAME:
6. Your present JOB TITLE or POSITION:
APPENDIX III CULTURE QUESTIONNAIRE
186
3.2.3 The External Relations of Your Unit
In varying degrees your unit does not exist in isolation. As the figure illustrates, your unit may have to maintain many relationships with other units, levels, and divisions within your organisation, as well as with various groups and agencies outside of your organisation. These relationships may exist for a variety of purposes, such as: coordinating work flows; obtaining money, personnel, equipment, and technical services and responding to or initiating administrative directives and rules. This questionnaire focuses on these external relationships your unit maintained during the past six months. In the space below, draw a picture that indicates the major units, levels and groups within and outside your organisation that your unit had contact with during the past six months. Identify these other units by name. Use the figure above as a guide for drawing your picture below.
PICTURE OF EXTERNAL RELATIONS MAINTAINED BY MY UNIT We now focus on the most important ”other units” that your unit maintained or developed contacts with during the past six months to accomplish your unit’s goals and responsibilities.
MY UNIT
Higher Admin. Levels
YOUR UNIT
Lower Operating Levels
Other Divisions
Other Units
Gov’t & Civic
Agencies
Suppliers Outside Firms
Customers Clients
Labor & Trade Unions
APPENDIX III CULTURE QUESTIONNAIRE
187
In all questions, the term “other units” refers to any other groups, offices, levels, or divisions within or outside of your organisation that your unit coordinates with.
1. NAMES OF OTHER KEY UNITS
2. REASONS FOR RELATIONSHIP WITH OTHER UNIT
3. IMPORTANCE
From the picture you drew, write the names of the most important other units that your unit had to coordinate with during the past 6 months. (Select up to five of the most important other units.)
State as clearly as possible the reasons why your unit had to coordinate or work with this other unit during the past six months.
How important was this other unit in attaining the goals of your unit the past 6 months? (Write a number from scale below) 1 – NOT VERY IMPORTANT 2 – SOMEWHAT IMPORTANT 3 – QUITE IMPORTANT 4 – VERY IMPORTANT 5 – ABSOLUTELY CRUCIAL
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
APPENDIX III CULTURE QUESTIONNAIRE
188
UNIT 1 UNIT 2 UNIT 3 UNIT 4 UNIT 5
In the columns on the right, please write the name of the five other units that you selected on the previous page. Then answer the following questions for each other unit individually by writing in the appropriate column the most accurate number from the answer scale for each question.
NAME:
NAME:
NAME:
NAME:
NAME:
(please tick) NO
YES
NO
YES
NO
YES
NO
YES
NO
YES
4. Does this other unit exist within your organisation?
If Yes: a. Do you supervise this other
unit in your organisation’s hierarchy?
b. Do you formally report to this other unit in your organisation’s hierarchy?
If No: c. Do you have a contractual
relationship with this other unit?
d. Is it mandatory by government or trade regulations that you coordinate with this other unit?
5. During the past six months, how much was your unit involved with this other unit for each of the following reasons: (use scale below)
a. To receive or send work or clients (e.g. customers, raw materials, or work objects)?
b. To receive or send resources (money, personnel, equipment, office space)?
c. To receive or send technical assistance (e.g. consultation or staff services in functional areas)?
d. To receive or send information for purpose of coordination, control, planning or evaluation?
NOT AT ALL
A LITTLE
SOME WHAT
QUITE A BIT
VERY MUCH
1 2 3 4 5
APPENDIX III CULTURE QUESTIONNAIRE
189
UNIT 1 UNIT 2 UNIT 3 UNIT 4 UNIT 5
6. To what extent have the terms of the relationship between your unit and this other unit:
Extent: Extent: Extent: Extent: Extent:
a. Been explicitly verbalized or discussed?
b. Been written down in detail?
TO NO EXTENT
LITTLE EXTENT
SOME EXTENT
CONSID-ERABLE EXTENT
GREAT EXTENT
1 2 3 4 5
7. For how many years has your unit been directly involved in some fashion with this other unit?
yrs yrs yrs yrs yrs
8. Prior to the past six months, to what extent has your unit had effective working relationships with this other unit? (write best scale no. in each column)
NO PRIOR CONTACT
TO NO EXTENT
LITTLE EXTENT
SOME EXTENT
CONSID-ERABLE EXTENT
GREAT EXTENT
0 1 2 3 4 5
9. For this other unit to accomplish its goals and responsibilities, how much does it need the services, resources, or support from your unit?
NOT AT ALL
VERY LITTLE SOME
QUITE A BIT
VERY MUCH
1 2 3 4 5
10. For your unit to accomplish its goals and responsibilities, how much do you need the services, resources, or support from this other unit? (use scale for Q.9)
11. How well informed are you about the specific goals and services of this other unit?
NOT AT ALL
LITTLE IN-FORMED
SOME-WHAT IN-FORMED
QUITE IN-FORMED
VERY WELL IN-FORMED
1 2 3 4 5
12. How much say or influence does this other unit have on the internal operations of your unit?
NONE LITTLE SOME QUITE A
BIT VERY MUCH
1 2 3 4 5
APPENDIX III CULTURE QUESTIONNAIRE
190
13. How much say or influence does your unit
have on the internal operations of this other unit? (use scale for Q.12)
14. Write your name and address of the primary individual that you contact or communicate with when dealing with
this other unit.
UNIT 1:
Name:
Contact No.:
Address:
UNIT 2:
Name:
Contact No.:
Address:
UNIT 3:
Name:
Contact No.:
Address:
UNIT 4:
Name:
Contact No.:
Address:
UNIT 5:
Name:
Contact No.:
Address:
APPENDIX III CULTURE QUESTIONNAIRE
191
UNIT 1 UNIT 2 UNIT 3 UNIT 4 UNIT 5
15. How many years and months have you personally known the contact person in this other unit?
Y
M
Y
M
Y
M
Y
M
Y
M
16. How well are you personally acquainted with the contact person in this other unit?
NOT PERSONAL ACQUAINT-
ANCE
NOT VERY WELL
SOME-WHAT WELL
QUITE WELL
VERY WELL
1 2 3 4 5
17. How much do you and this contact person agree or disagree on:
a. The goal priorities of your unit?
b. The specific ways work is done or services are provided by your unit?
c. The specific terms of the relationship between your unit and this other unit?
DON’T KNOW
DIS-AGREE MUCH
AGREE A LITTLE
AGREE SOME-WHAT
AGREE QUITE A BIT
AGREE VERY MUCH
0 1 2 3 4 5
18. To what extent does this other unit:
a. Obtain its funding from the same source as your unit does?
b. Do the same kind of work as your unit does?
c. Have the same clients or customers as your unit?
d. Have operating goals similar to your unit’s goals?
e. Have employees with similar professional or trade skills as those required of personnel in your unit?
f. Use the same technology, equipment, or information sources as your unit in doing its work?
DON’T KNOW
TO NO EXTENT
LITTLE EXTENT
SOME EXTENT
CONSID-ERABLE EXTENT
GREAT EXTENT
0 1 2 3 4 5
19. To what extent did individuals in this other unit hinder your unit in performing its functions during the past six months?
(use scale for Q.18)
APPENDIX III CULTURE QUESTIONNAIRE
192
UNIT 1 UNIT 2 UNIT 3 UNIT 4 UNIT 5
20. Consider now the equality of the give-and-take relationship with each unit. Compared to other units that you are involved with, how fair do you feel are the “payoffs” to your unit from this unit?
WE GET MUCH LESS
THAN WE OUGHT
WE GET SOME-WHAT
LESS THAN WE OUGHT
BALANCED
WE GET SOME-WHAT MORE
THAN WE OUGHT
WE GET MUCH MORE
THAN WE OUGHT
1 2 3 4 5
21. During the past 6 months, how frequently have people in your unit communicated or been in contact with people in the other unit?
NOT ONCE
1-2 TIMES
ABOUT MON-THLY
ABOUT EVERY 2 WKS
ABOUT WEEKL
Y
AOUT DAILY
MANY TIMES DAILY
0 1 2 3 4 5 6
22. Specially, how frequently did your unit communicate with this other unit through each of the following ways during the past 6 months: (use scale for Q.21)
a. Through written letters, memos, or reports of any kind?
b. Through personal face-to-face discussions?
c. Through telephone calls?
d. Through group or committee meetings between three or more people from your unit and this other unit?
23. In general, what percent of all these communications with this other unit were initiated by people in your unit during the past 6 months?
% % % % %
24. Overall, how much difficulty do you experience in getting ideas clearly across to individuals in this other unit when you communicate with them?
NO CONTACT NONE LITTLE SOME
QUITE A BIT
VERY MUCH
0 1 2 3 4 5
25. When you wanted to communicate with individuals in this unit, how much difficulty have you had getting in touch with them? (use scale for Q.24)
APPENDIX III CULTURE QUESTIONNAIRE
193
UNIT 1 UNIT 2 UNIT 3 UNIT 4 UNIT 5
The next 2 questions may be difficult to answer. Make the most approximate estimate you can. Write “0” if your answer is none or not applicable.
26. During the past 6 months:
a. What percent of your total working hours did you spend on matters directly related to the operations, work or projects of this other unit?
% % % % %
b. What percent of all the work done by your unit came from this other unit? % % % % %
c. What percent of all technical assistance and services did you receive from this other unit?
% % % % %
d. What percent of your unit’s operating budget (money, personnel, supplies, equipment) was obtained from this other unit?
% % % % %
27. During the past 6 months:
a. What percent of all the work completed by your unit was sent to this other unit? % % % % %
b. What percent of all resources allocated by your unit was given to this other unit? % % % % %
c. What percent of all person-hours of technical assistance or services provided by your unit was given to this other unit?
% % % % %
28. During the past 6 months, how much the same were these work materials, resources or services each time they were sent to or received from this other unit?
ALMOST ALL THE
SAME EACH TIME
MOSTLY THE SAME EACH TIME
ABOUT HALF THE
SAME EACH TIME
MOSTLY DIFFERENT EACH TIME
ALMOST ALL
DIFFERENT EACH TIME
1 2 3 4 5
29. To what extent did your unit encounter interruptions or delays to the normal flows of work, resources or services from or to this other unit during the past six months?
TO NO EXTENT
LITTLE EXTENT
SOME EXTENT
MUCH EXTENT
VERY GREAT EXTENT
1 2 3 4 5
APPENDIX III CULTURE QUESTIONNAIRE
194
UNIT 1 UNIT 2 UNIT 3 UNIT 4 UNIT 5
30. During the past 6 months, how often did exceptions or problems arise in sending or receiving work, resources or services to / from this other unit?
NOT ONCE
1 OR 2 TIMES
ABOUT MONTHLY
ABOUT WEEKLY
ABOUT DAILY
SEVERAL TIMES A
DAY
1 2 3 4 5 6
31. To coordinate activities with this other unit during the past six months, to what extent:
a. Have standard operating procedures been established (e.g. rules, policies, forms etc.)?
b. Are formal communication channels followed?
TO NO EXTENT
LITTLE EXTENT
SOME EXTENT
MUCH EXTENT
VERY GREAT EXTENT
1 2 3 4 5
32. During the last six months, how often were there disagreements or disputes between people in your unit and this other unit?
NOT ONCE
ABOUT ONCE A MONTH
ABOUT EVERY 2 WEEKS
ABOUT ONCE A WEEK
SEVERAL TIMES A WEEK
EVERY DAY
1 2 3 4 5 6
33. When these disagreements or disputes occurred, how often were they handled in each of the following ways during the past 6 months?
a. By ignoring or avoiding the issues?
b. By smoothing over the issues?
c. By bringing the issues out in the open and working them out among the parties involved?
d. By having a higher level manager or authority resolves the issues between the parties involved?
ALMOST NEVER
SELDOM ABOUT
HALF THE TIME
OFTEN ALMOST ALWAYS
1 2 3 4 5
34. How well are any differences worked out at this time between your unit and this other unit?
VERY POORLY
POORLY ADEQUATE
-LY QUITE WELL
VERY WELL
1 2 3 4 5
APPENDIX III CULTURE QUESTIONNAIRE
195
To conclude this section, please answer the following questions using the scale below:
TO NO EXTENT
LITTLE EXTENT
SOME EXTENT
CONSID-ERABLEEXT
ENT
GREAT EXTENT
1 2 3 4 5
UNIT 1 UNIT 2 UNIT 3 UNIT 4 UNIT 5
35. To what extent has this unit carried out its responsibilities and commitments in regard to your unit during the past 6 months?
36. To what extent has your unit carried out your responsibilities and commitments in regard to this other unit during the past 6 months?
37. To what extent do you feel the relationship between your unit and this other unit is productive?
38. To what extent is the time and effort aspect in developing and maintaining the relationship with this other unit worthwhile?
39. Overall, to what extent were you satisfied with the relationship between your unit and this other unit during the past 6 months?
40. During the past 6 months, to what extent has your unit changed or influenced the services or operations of this other unit?
41. During the past 6 months, to what extent has this other unit changed or influenced the services or operations of your unit?
APPENDIX III CULTURE QUESTIONNAIRE
196
3.2.4 A Self-Appraisal of You Unit’s External Relat ions Now make a self-assessment of the relationships your unit maintains with each of the other units. Hopefully, the questions you have answered so far have stimulated you to make such a self-assessment.
Describe the major problems you have encountered in relating or coordinating with each of the other units during the past 6 months.
Suggest some specific ways for overcoming these problems with each of the other units.
UNIT 1 Problems:
Suggestions:
UNIT 2 Problems:
Suggestions:
UNIT 3 Problems:
Suggestions:
UNIT 4 Problems:
Suggestions:
UNIT 5 Problems:
Suggestions:
APPENDIX III CULTURE QUESTIONNAIRE
197
Thank you for your time.
Please turn over to the last questionnaire, Questionnaire 4.
APPENDIX III CULTURE QUESTIONNAIRE
198
3.3 OAI Other Unit Questionnaire 3.3.1 General Instructions This questionnaire focuses on the relationships your organisational unit has had during the past 6 months with one or more other units from the XYZ Firm. These other units are designated on the next page. You are asked to answer the questions for only the units specified. For most questions there is a five-point answer scale with brief descriptions of what the numbers on the scale. Represent. You are to choose one number that most accurately reflects your answer to the question for each designated other unit and write it in the appropriate column. For example, if you were asked the following question, and your answers were “daily” and “monthly” for units 1 and 2 from the XYZ Firm, then you would write the numbers “4” and “2” in the respective columns like this:
How often were you in contact with this other unit during the past six months? YEARLY MONTHLY WEEKLY DAILY HOURLY Unit 1 Unit 2 Unit 3 Unit 4 Unit 5
1 2 3 4 5 4
2
If you do not understand any question, BE SURE TO ASK US FOR HELP. We realize that not all questions are simple, and that is why we are here to answer any questions you have.
APPENDIX III CULTURE QUESTIONNAIRE
199
3.3.2 Introductory Questions The following questions are very important for properly coding and analysing the data. As indicated before, all responses will be kept strictly confidential.
1. Your NAME:
2. Your ADDRESS:
3. Name of ORGANISATION in which you work:
4. Name of OFFICE or DIVISION in which you work:
5. Name of UNIT in which you work:
6. Your present JOB TITLE or POSITION:
7. How many years and months have you held this position? Years, Months.
8. How many years and months have you worked in your organisation?
Years, Months.
APPENDIX III CULTURE QUESTIONNAIRE
200
3.3.3 Inter-Unit Relations In a previous survey, the contact persons from the following unit(s) in XYZ firm reported they coordinated in some way with your organisational unit during the past 6 months.
UNIT 1: Name
Contact Person
UNIT 2: Name
Contact Person
UNIT 3: Name
Contact Person
UNIT 4: Name
Contact Person
UNIT 5: Name
Contact Person
We would like your perspective on these inter-unit relations. Please answer the questions for each of the designated other units individually. Put in the appropriate columns the number from the answer scale that reflects your most accurate answer to each question for each other unit. Be sure to use the column with the same unit number as that designated above to answer the questions for each of the other units. If no names are shown above for units 2 – 5, then leave those columns blank. UNIT 1 UNIT 2 UNIT 3 UNIT 4 UNIT 5
1. How well are you personally acquainted with the contact person in this other unit?
NO
PERSONAL ACQUAIN-
TANCE
NOT VERY WELL
SOMEWHAT WELL
QUITE WELL
VERY WELL
1 2 3 4 5
2. How much do you and this contact person
agree or disagree on:
a. The goal priorities of your unit? b. The specific ways work is done or
services are provided by your unit? c. The specific terms of the relationship
between your unit and this other unit?
DON’T KNOW
DES-AGREE MUCH
AGREE A LITTLE
AGREE SOME-WHAT
AGREE QUITE A
BIT
AGREE VERY MUCH
0 1 2 3 4 5
3. How well informed are your about the specific goals and services of this other unit?
NOT AT ALL LITTLE
INFORMED SOMEWHAT INFORMED
QUITE INFORMED
VERY WELL INFORMED
1 2 3 4 5
APPENDIX III CULTURE QUESTIONNAIRE
201
UNIT 1 UNIT 2 UNIT 3 UNIT 4 UNIT 5
4. Prior to the past 6 months, to what extent has your unit had effective working relationships with this other unit?
NO PRIOR CONTACT
TO NO EXTENT
LITTLE EXTENT
SOME EXTENT
CONSID-ERABLE EXTENT
GREAT EXTENT
0 1 2 3 4 5
5. During the past 6 months, how much was your unit involved with this other unit for each of the following reasons:
a. To received or send work or clients (e.g. customers, raw materials, or work objects)?
b. To received or send resources (money, personnel, equipment, office space)?
c. To receive or send technical assistance (e.g. consultation or staff services in functional areas)?
d. To receive or send information for purpose of coordination, control, planning or evaluation?
NOT AT ALL
A LITTLE SOME-WHAT
QUITE A BIT
VERY MUCH
1 2 3 4 5
6. Consider now the equality of the give-and-take relationship with each unit. Compare to other units that you are involved with, how fair do you feel are the “payoffs” to your unit from this unit?
WE GET MUCH LESS
THAN WE OUGHT
WE GET SOMEWHAT LESS THAN WE OUGHT
BALANCED
WE GET SOMEWHAT MORE THAN WE OUGHT
WE GET MUCH
MORE THAN WE OUGHT
1 2 3 4 5
7. For this other unit to accomplish its goals and responsibilities, how much does it need the services, resources, or support from your unit?
NOT AT ALL
VERY LITTLE SOME
QUITE A BIT
VERY MUCH
1 2 3 4 5
8. For your unit to accomplish its goals and responsibilities, how much do you need the services, resources or support from this other unit? (use scale for Q.7)
9. How much say or influence does this other
unit have on the internal operations of your unit?
NONE LITTLE SOME QUITE A
BIT VERY MUCH
1 2 3 4 5
10. How much say or influence does your unit have on the internal operations of this other unit? (use scale for Q.9)
APPENDIX III CULTURE QUESTIONNAIRE
202
UNIT 1 UNIT 2 UNIT 3 UNIT 4 UNIT 5
11. To what extent have the terms of the relationship between your unit and this other unit:
a. Been explicitly verbalized or discussed? b. Been written down in detail?
TO NO EXTENT
LITTLE EXTENT
SOME EXTENT
CONSID-ERABLE EXTENT
GREAT EXTENT
1 2 3 4 5
12. During the past 6 months, what percent of your total working hours did you spend on matters directly related to the operations, work or activities of this other unit? (indicate percent)
% % % % %
13. During the past 6 months, how frequently
have people in your unit communicated or been in contact with people in this other unit?
NOT ONCE
1-2 TIMES
ABOUT MONTH-
LY
ABOUT EVERY 2 WKS
ABOUT WEEKLY
ABOUT DAILY
MANY TIMES DAILY
0 1 2 3 4 5 6
14. When you want to communicate with individuals in this unit, how much difficulty have you had getting in touch with them?
NO CONTACT NONE LITTLE SOME
QUITE A BIT
VERY MUCH
0 1 2 3 4 5
15. Overall, how much difficulty do you experience in getting ideas clearly across to individuals in this other unit when you communicate with them? (use scale for Q.14)
16. During the past 6 months, how often were
there disagreements or disputes between people in your unit and this other unit?
NOT ONCE
ABOUT ONCE A MONTH
ABOUT EVERY 2 WEEKS
ABOUT ONCE A WEEK
SERVAL TIMES A WEEK
EVERY DAY
1 2 3 4 5 6
17. To what extent did individuals in this other unit hinder your unit in performing its functions during the past 6 months?
DON’T KNOW
TO NO EXTENT
LITTLE EXTENT
SOME EXTENT
CONSID-ERABLE EXTENT
GREAT EXTENT
0 1 2 3 4 5
18. How well are any differences worked out at this time between your unit and this other unit?
VERY POORLY POORLY
ADEQUATE-LY
QUITE WELL VERY WELL
1 2 3 4 5
APPENDIX III CULTURE QUESTIONNAIRE
203
UNIT 1 UNIT 2 UNIT 3 UNIT 4 UNIT 5 19. Overall, how important was this other unit in
attaining the goals of your unit during the past 6 months?
NOT VERY IMPORTANT
SOMEWHAT IMPORTANT
QUITE IMPORTANT
VERY IM;PORTANT
ABSOLUTE-LY CRUCIAL
1 2 3 4 5
Finally please answer the following questions using the scale below:
TO NO EXTENT
LITTLE EXTENT
SOME EXTENT
CONSID-ERABLE EXTENT
GREAT EXTENT
1 2 3 4 5
UNIT 1 UNIT 2 UNIT 3 UNIT 4 UNIT 5
20. To what extent has this unit carried out its
responsibilities and commitments in regard to your unit during the past 6 months?
21. To what extent has your unit carried out
your responsibilities and commitments in regard to this other unit during the past 6 months?
22. To what extent do you feel the relationship
between your unit and this other unit is productive?
23. To what extent is the time and effort spent
in developing and maintaining the relationship with this other unit worthwhile?
24. Overall, to what extent are you satisfied
with the relationship between your unit and this other unit during the past 6 months?
25. During the past 6 months, to what extent
has your unit changed or influenced the services or operations of this other unit?
26. During the past 6 months, to what extent
has this other unit changed or influenced the services or operations of your unit?
APPENDIX III CULTURE QUESTIONNAIRE
204
4 QUESTIONNAIRE 4 4.1 Description
Hofstede, G.H. (1980) Culture ’’’’ s Consequence s. Sage, Beverly Hills. Two key objectives have emerged in this study:
• to provide information which makes for a better understanding of the way culturally produced attitudes towards team members and perceptions of co-workers behaviour impede or facilitate communication, collaboration and effectiveness;
• to explore the impact that conditions of contract have on communication, collaboration and effectiveness and to examine the link, if any exists, between contracts and the evolution of a project culture.
Hofstede's established methodology provides a basis for identifying patterns of differences in orientations amongst employees (which together with the role of the individual as a function of his/her professional background in the case of Engineer or Architect or QS) gives a guide towards the existence and relative importance of national (and occupational) sub-cultures, together with an indication of their relative strength in relation to any industry wide "common-culture", so important to an 'adaptive system' which aims to change approaches to collaboration. This questionnaire will be distributed to specifically targeted project participants whose experience is directly relevant to partnering and alliancing issues. The final part of the questionnaire investigates specifically cooperative behaviours in the project context. The four psychological dimensions or axes used to differentiate between cultures are: Power Distance (PDI) - This dimension deals with the issue of human inequality and how within different groups power is resolved. Within the work environment, this is generally evidenced in the superior-subordinate relationship. The Power Distance Index is a measure of the interpersonal power or influence between (boss) and (subordinate)?(Hofstede 1984:71). Hofstede suggests that the there is a socially determined equilibrium between subordinates seeking to reduce the size of the power distance between themselves and their boss, whilst their superior seeks to maintain it. A low PDI indicates a perceived equality of ability, autonomy and independence being highly valued, whilst a high PDI indicates prevalence for authoritarian behaviour, conformity and centralised decision making. Uncertainty Avoidance (UAI) - Different groups have learnt to deal with uncertainty in different ways, often because they find themselves faced with different levels of uncertainty. Adams (1995) writes of the risk thermostat in relation to individuals’ ability to deal with, and be comfortable when exposed to, risk. The principle behind uncertainty avoidance is that at a societal level, the environment people are exposed to results in societies adopting a socially determined risk thermostat, reflected in the values of the group and the norms of behaviour etc. which are an expression of the group values.
APPENDIX III CULTURE QUESTIONNAIRE
205
Masculinity (MAS) - Men and women are different. This is a fundamental biological fact which different societies cope with in different ways. The issue investigated here is whether this biological difference has (as opposed to should have) an effect on their roles in social activities (and hence their work values). Individualism (IDV) - The final dimension looks at the relationship between the individual and the collective. Within sociology, this aspect is often referred to as Gemeinschaft (low individualism) at one extreme and Gesellschaft (high individualism) at the other. Within the work environment this is often explicitly linked to the individual relationship with his employing organisation. The Values Survey Module (VSM) will be supplemented by a series of questions addressing attitudes to contracts and contract procedures in order to investigate how culture, situation (context) and contract interact to produce responses to typical situations experienced on site in relation to potential areas of dispute. This approach was adopted previously in the study in Hong Kong by Rowlinson (2001). Reference: Rowlinson, S.M. (2001) “Matrix Organizational Structure, Culture and Commitment: a Hong Kong Public Sector Case Study of Change”, Construction Management and Economics, 19, 669-673.
APPENDIX III CULTURE QUESTIONNAIRE
206
4.2 Introduction The questionnaire is divided into 3 parts: Part I - Asks about yourself and your work background to enable us to classify your
answers to the following parts. Part II - Asks your views on your ideal job and how you like to work. Part III - Asks some questions on how you work on projects and how you perceive the
used of standard forms of contracts on projects. How to Complete This Questionnaire:
1. Please read through the following questions carefully. The questionnaire should not take more than 10 minutes to complete.
2. Answer each question by checking the box representing your answer. 3. Only check one box unless otherwise instructed. 4. Please give answers that represent your views not those of your employer.
APPENDIX III CULTURE QUESTIONNAIRE
207
4.3 Questionnaire 4.3.1 Part I 1. Are you:
Male
Female
2. How old are you?
Under 20
20 – 24
25 – 29
30 – 34
35 – 39
40 – 49
50 – 59
60 or over
3. How long have you been working in the construction industry; include any industrial experience forming part of a “sandwich” degree course but exclude any time spent as a student in full-time education.
Less than 2 years
2 – 4 years
5 – 9 years
10 – 19 years
20 – 29 years
More than 30 years
4. How many years of formal school education did you complete? (Starting with primary school; count only the number of years each course should officially take, even if you spent less or more years on it; if you took part-time or evening courses, count the number of years the same course would have taken you full-time but do not count periods of industrial experience on sandwich courses.)
10 years or less
11 years
12 years
13 years
14 years
15 years
16 years
17 years
18 years or more
APPENDIX III CULTURE QUESTIONNAIRE
208
5. Which one of the following most closely represents your professional background?
Architect
Civil Engineer
Structural Engineer
Services Engineer
Quantity Surveyor
Builder
Project Manager
Building Surveyor
Other (please specify)
6. Which of the following professional bodies are you a member of (you may check more than one)? If you are not a member of any body, which professional association best represents your interests as an individual?
RICS
AIB
AIQS
IEAust
AIPM
RAIA
AILA
Other (please specify)
7. In which one of the following roles have you gained the majority of your experience in the construction industry?
Client
Consultant
Main Contractor
Sub-Contractor
Supplier
Other (please specify)
APPENDIX III CULTURE QUESTIONNAIRE
209
4.3.2 Part II Please think of an ideal job – disregarding your present job. In choosing an ideal job, how important would it be to you to consider the following criteria? Note: Please check only one box for each item.
Of U
tmos
t Im
port
ance
Ver
y Im
port
ant
Of M
oder
ate
Impo
rtan
ce
Of L
ittle
Im
port
ance
Of V
ery
Littl
e or
N
o Im
port
ance
1 2 3 4 5 8. Have sufficient time left for your personal or
family life?
9. Have challenging tasks to do, from which you can get a personal sense of accomplishment?
10. Have little tension and stress on the job?
11. Have good physical working conditions (good ventilation and lighting, adequate work space, etc)?
12. Have a good working relationship your direct superior?
13. Have security of employment?
14. Have considerable freedom to adopt your own approach to the job?
15. Work with people who cooperated well with one another?
16. Be consulted by your direct superior in his/her decisions?
APPENDIX III CULTURE QUESTIONNAIRE
210
Of U
tmos
t Im
port
ance
Ver
y Im
port
ant
Of M
oder
ate
Impo
rtan
ce
Of L
ittle
Im
port
ance
Of V
ery
Littl
e or
N
o Im
port
ance
1 2 3 4 5 17. Make a real contribution to the success of
your company or organisation?
18. Have an opportunity of high earnings?
19. Serve your country?
20. Live in an area desirable to you and your family?
21. Have an opportunity for advancement to higher level jobs?
22. Have an element of variety and adventure in the job?
23. Work in a prestigious, successful company or organisation?
24. Have an opportunity for helping other people?
25. Work in a well-defined job situation where the requirements are clear?
26. How frequently, in your work environment, are subordinates afraid to express disagreement with their superiors?
Very frequently
Frequently
Sometimes
Seldom
Very seldom
APPENDIX III CULTURE QUESTIONNAIRE
211
The descriptions below apply to four different types of managers. First, please read through these descriptions:
Manager 1 Usually makes his/her decisions promptly and communicates them to his/her subordinates clearly and firmly. Expects them to carry out the decisions loyally and without raising difficulties.
Manager 2 Usually makes her/his decisions promptly, but, before going ahead, tries to explain them fully to his/her subordinates. Gives them the reasons for the decisions and answers whatever questions they may have.
Manager 3 Usually consults with his/her subordinates before he/she reaches his/her decisions. Listens to their advice, considers it, and then announces his/her decision. He/she then expects all to work loyally to implement it whether or not it is in accordance with the advice they gave.
Manager 4 Usually calls a meeting of her/his subordinates when there is an important decision to be made. Puts the problem before the group and invites discussion. Accepts the majority viewpoint as the decision.
27. Now, for the above types of manager, please mark the one which you would prefer to
work under:
Manager 1
Manager 2
Manager 3
Manager 4
28. And, to which one of the above four types of managers would you say your own superior most closely corresponds?
Manager 1
Manager 2
Manager 3
Manager 4
He/she does not correspond closely to any of them.
29. What kind of work do you do?
a. I am a manager (that is, I have at least one hierarchical subordinate) – go to f .
b. I am not a manager and I work most the time in an office – go to e .
c. I am not a manager and I do not work most of the time in an office – go to d .
d. If you are not a manager and you do not work most of the time in an office, what do you do:
Work for which normally no vocational training, other than on-the-job training, is required (unskilled or semi-skilled work).
Work for which normally up to four years of vocational training is required (skilled worker, technician, non-graduate engineer, nurse, etc.).
Work for which normally a higher-level professional training is required
APPENDIX III CULTURE QUESTIONNAIRE
212
(graduate engineer, doctor, architect, etc.).
e. If you are not a manager and you work most of the time in an office, what do you do:
Work for which normally no higher-level professional training is required (clerk, typist, secretary, non-graduate accountant).
Work for which normally a higher-level professional training is required (graduate accountant, lawyer, etc.).
f. If you are a manager, are you:
A manager of people who are not managers themselves (that is, a first-line manager).
A manager of other managers.
Str
ongl
y A
gree
Agr
ee
Und
ecid
ed
Dis
agre
e
Str
ongl
y D
isag
ree
1 2 3 4 5
30. A company or organisation’s rules should not be broken – even when the employee thinks it is in the organisation’s best interests.
31. Most people can be trusted.
32. Quite a few employees have an inherent dislike of work and will avoid it if they can.
33. A large corporation is generally a more desirable place to work than a small company.
34. How often do you feel nervous or tense at work?
I always feel this way
Usually
Sometimes
Seldom
I never feel this way
35. How long do you think you will continue working for this company or organisation?
Two years at the most
From two to five years
More than five years (but I probably will leave before I retire)
Until I retire
APPENDIX III CULTURE QUESTIONNAIRE
213
4.3.3 Part III Please indicate your degree of agreement or disagreement with the following statements: Note: Please check only one box for each item.
Str
ongl
y A
gree
Agr
ee
Und
ecid
ed
Dis
agre
e
Str
ongl
y D
isag
ree
1 2 3 4 5
36. Personal relationships are important in managing projects/contracts.
37. Formal procedures are necessary for the successful management of a project.
38. Informal arrangements are necessary for the successful management of a project.
39. Personal relationships amongst the project members are more important than those in your employer’s organisation.
Please indicate how frequently you believe the following statements to be true:
Str
ongl
y A
gree
Agr
ee
Und
ecid
ed
Dis
agre
e
Str
ongl
y D
isag
ree
1 2 3 4 5
40. One must be willing to sacrifice personal relationships with members of the project team to ensure the successful completion of the project.
41. One must be willing to sacrifice personal relationships with members of the project team to ensure their firm’s objectives are met.
42. One must be willing to sacrifice personal relationships with members of the project team to ensure one’s personal objectives are met.
APPENDIX III CULTURE QUESTIONNAIRE
214
Str
ongl
y A
gree
Agr
ee
Und
ecid
ed
Dis
agre
e
Str
ongl
y D
isag
ree
1 2 3 4 5
43. One must be prepared to disregard formal procedures in order to ensure the successful completion of the project.
44. One must be prepared to disregard formal procedures in order to ensure one’s firm’s objectives met.
45. One must be prepared to disregard formal procedures in order to ensure one’s own objectives are met.
Please think of the projects you have been involved with during your career – not just in your present job. How important are the following factors.
Str
ongl
y A
gree
Agr
ee
Und
ecid
ed
Dis
agre
e
Str
ongl
y D
isag
ree
1 2 3 4 5
46. To be seen to be using the prescribed procedures when dealing with;
a. Valuations
b. Changes to Design and Specification
c. Changes to Program
d. Settlement of final Account
47. To be able to develop informal arrangements when dealing with;
a. Valuations
b. Changes to Design and Specification
c. Changes to Program
d. Settlement of final Account
48. What importance does the Standard Form of Contract have on the following;
a. Determining your role
APPENDIX III CULTURE QUESTIONNAIRE
215
Str
ongl
y A
gree
Agr
ee
Und
ecid
ed
Dis
agre
e
Str
ongl
y D
isag
ree
1 2 3 4 5
b. Determining your personal relationships with the rest of the project team
c. Your expectations of the likelihood of disputes occurring
d. Control of your behavior
e. Control of the client’s behavior
f. Control of the other members of the project team
49. Which family of Standard Forms of Contract do you most prefer to work with?
AS2124 and variants
AS4305 and variants
General Conditions of Contract for design and construction (AS4300 & variants)
Construction Management Conditions of Contract (AS4910)
Other (please specify)
50. Which of the following contracts do you perceive is most likely to avoid conflicts and disputes? (you do not need to have had direct experience of the contract to hold a valid opinion)
AS2124 and variants
AS4305 and variants
General Conditions of Contract for design and construction (AS4300 & variants)
Construction Management Conditions of Contract (AS4910)
Other (please specify)
They have no effect.
51. Which of the following contracts do you perceived is most likely to lead to conflicts and disputes? (you do not need to have had direct experience of the contract to hold a valid opinion)
AS2124 and variants
AS4305 and variants
General Conditions of Contract for design and construction (AS4300 & variants)
Construction Management Conditions of Contract (AS4910)
Other (please specify)
They have no effect.
217
APPENDIX IV SURVEY RESULTS
QDPW Survey Results
Organisational Culture Organisational Culture Preferred Culture Perceived Culture
Power 0 0.5* Role 0 4 Task 6 1.5* Person 0 0
(n=6) * Same score for Power and Task Culture was calculated from one of the returned
questionnaires.
Table 6.1: Organisational Culture (QDPW)
Commitment Type of Commitment Mean Median Standard
Deviation Affective 23.2 23.5 4.4 Normative 22.0 22.5 1.5 Continuance 19.0 19.0 1.9
(n=6) * Concepts are measured on a scale of 1 to 7, with 1 indicating low levels of commitment
and 7 indicating high levels, for six variables giving, for each scale, maximum scores of 42 and minimum scores of 6.
Table 6.2: Commitment Levels (QDPW)
218
APPENDIX IV SURVEY RESULTS
Organisational Assessment Systematized
Impersonal Mode
Discretionary Personal Mode
Developmental Group Mode
Difficulty & Variability of Tasks, Problems, Issues Encountered by subsystem –
Low Medium High
Salient Dimensions of Managerial Subsystem
1. Organizational Referent Central information
systems Hierarchy & staff Coordination
committees
2. Coordination and Control by: Rules, plans, schedules
Exceptions to hierarchy
Mutual group adjustments
3. Resource & Information Flows among Organizational Levels, Units, & Positions:
a. Direction Diffuse Vertical Horizontal b. Amount High Medium Low c. Standardization & Codification High Medium Low
4. Perceived Interdependence among Components Low Medium High
5. Frequency of conflict among Components Low Medium High
Table 6.3: Hypothesised Patterns of Systematized, Discretionary and Developmental Modes in Complex Organisations (extracted from Van de Ven and Ferry, 1980, p. 368-369)
Systematized
Impersonal Mode
Discretionary Personal Mode
Developmental Group Mode
Salient Dimensions of Managerial Subsystem
1. Organizational Referent Central information systems?
Hierarchy & Staff?
2. Coordination and Control by: Rules, plans, schedules
3. Resource & Information Flows among Organizational Levels, Units, & Positions:
a. Direction Diffuse? b. Amount Low c. Standardization & Codification High Medium
4. Perceived Interdependence among Components High
5. Frequency of conflict among Components Low
Table 6.4: Hypothesised Patterns of Design Mode in QDPW
219
APPENDIX IV SURVEY RESULTS
Resource Dependence * Concepts are measured on a scale of 1 to 5, with 1 indicating no resources were received
and 5 indicating large amount of resources received Mean Median Standard
Deviation QDPW 4.10 4.00 1.02 Other Units 3.75 4.00 1.21
(n=19)
Table 6.5: Other Units Resource Dependence on QDPW
Mean Median Standard Deviation QDPW 4.10 4.00 1.17 Other Units 3.55 4.00 1.19
(n=19)
Table 6.6: QDPW Resource Dependence on Other Units
* Concepts are measured on a scale of 1 to 5, with 1 indicating the importance of the other
party is not very important and 5 indicating it is absolutely crucial Mean Median Standard Deviation To QDPW 3.24 4.00 0.67 To Other Units 3.40 3.00 0.94
(n=20)
Table 6.7: Resource Importance between QDPW and Other Units
Awareness of Relationship
* Concepts are measured on a scale of 1 to 5, with 1 indicating goals and services are not informed at all and 5 indicating they are very well informed
Mean Median Standard Deviation QDPW 3.60 4.00 1.10 Other Units 4.00 4.00 0.92
(n=20)
Table 6.8: Goals Informed between QDPW and Other Units
* Concepts are measured on a scale of 1 to 5, with 1 indicating there is no personal
acquaintance and 5 indicating the personal acquaintance is very well Mean Median Standard Deviation QDPW 2.80 3.50 1.54 Other Units 4.25 4.00 0.85
(n=20)
Table 6.9: Degree of Personal Acquaintance (QDPW & Other Units)
220
APPENDIX IV SURVEY RESULTS
Consensus/Conflict * Concepts are measured on scale of 0 to 5, with 0 indicating no knowing if the other party
agrees on goal priorities/way of work or services provided/terms of relationship/hindered performance, and 5 indicating knowing the other party agree very much on items
Mean Median Standard Deviation
Goal Priorities QDPW 2.40 3.00 1.86 Other Units 4.35 4.00 0.49
Way of Work/Services are Provided
QDPW 2.90 3.50 1.62 Other Units 4.05 4.00 0.61
Terms of Relationship QDPW 3.10 4.00 1.65 Other Units 4.45 5.00 0.69
(n=20)
Table 6.10: Consensus and Conflict between QDPW and Other Units
Mean Median Standard Deviation
QDPW 1.85 2.00 0.99 Other Units 4.45 5.00 0.69
(n=20)
Table 6.11: Hindered Performance by Other Parties (QDPW & Other Units)
* Concepts are measured on scale of 1 to 6, with 1 indicating no disagreement or dispute
during the last six month, and 6 indicating they happen everyday Mean Median Standard Deviation
QDPW 2.15 2.00 1.04 Other Units 1.70 2.00 0.66
(n=20)
Table 6.12: Frequency of Conflict (QDPW & Other Units)
221
APPENDIX IV SURVEY RESULTS
Personal
Acquaintance (QDPW)
Personal Acquaintance (Other Units)
Frequency of Conflict (QDPW)
Frequency of Conflict
(Other Units) Personal Acquaintance (QDPW)
Sig. 1.00
- 0.241 0.307
-0.210 0.374
-0.374 0.104
Personal Acquaintance (Other Units)
Sig. 0.241 0.307
1.00 -
-0.104 0.662
-0.141 0.552
Conflict (QDPW)
Sig. -0.210 0.374
-0.104 0.662
1.000 -
-0.008 0.974
Conflict (Other Units)
Sig. -0.374 0.104
-0.141 0.552
-0.008 0.974
1.000 -
(n=20)
Table 6.13: Correlations between QDPW and Other Units on Personal Acquaintance and Frequency of Conflict
Methods of Conflict Resolution * Concepts are measured on a scale of 1 to 5, with 1 indicating the conflict resolution was
almost never and 5 indicating it was used almost always Mean Median Standard
Deviation Avoiding Issues 0.70 1.00 0.57 Smoothing Over Issues 0.80 1.00 0.77 Confronting Issues 3.40 5.00 2.30 Hierarchy 0.75 0.50 1.16
(n=20)
Table 6.14: Frequency on Use of Methods of Conflict Resolution (QDPW)
222
APPENDIX IV SURVEY RESULTS
Working Relationship Effectiveness
(QDPW)
Working Relationship Effectiveness (Other Units)
Avoiding Issues
Smoothing Over Issues
Confronting Issues Hierarchy
Working Relationship Effectiveness (QDPW)
Sig. 1 -
0.537** 0.007
-0.216 0.180
-0.375 0.052
-0.405(*) 0.038
0.000 0.500
Working Relationship Effectiveness (Other Units)
Sig. 0.537** 0.007
1 -
-0.141 0.276
-0.187 0.215
0.202 0.196
0.212 0.185
Avoiding Issues
Sig. -0.216 0.180
-0.141 0.276
1 -
0.816(**) 0.000
0.176 0.229
0.435(*) 0.028
Smoothing Over Issues
Sig. -0.375 0.052
-0.187 0.215
0.816(**) 0.000
1 -
0.226 0.169
0.471(*) 0.018
Confronting Issues
Sig. -0.405(*)
0.038 0.202 0.196
0.176 0.229
0.226 0.169
1 -
0.432(*) 0.029
Hierarchy
Sig. 0.000 0.500
0.212 0.185
0.435(*) 0.028
0.471(*) 0.018
0.432(*) 0.029
1 -
* Correlation is significant at the 0.05 level (1-tailed) ** Correlation is significant at the 0.01 level (1-tailed) (n=20)
Table 6.15: Correlation between Working Relationship Effectiveness and Methods of Conflict Resolution (QDPW)
Domain Similarity * Concepts are measured on scale of 0 to 5, with 0 indicating no knowing the extent of
domain similarity, and 5 indicating great extent of domain similarity Mean Median Standard
Deviation Funding Source 3.20 4.00 1.77 Work Kind 2.55 3.00 1.00 Clients or Customers 3.35 3.50 1.35 Operating Goals 2.85 3.50 1.63 Employee Skills 3.15 3.50 1.31 Technology 3.20 3.50 1.28
(n=20)
Table 6.16: Domain Similarity (QDPW)
223
APPENDIX IV SURVEY RESULTS
Funding Source Work Kind
Clients or Customers
Operating Goals
Employee Skills Technology
Funding Source
Sig. 1 -
0.143 0.547
0.455(*) 0.044
0.669(**) 0.001
0.214 0.365
0.493(*) 0.027
Work Kind
Sig. 0.143 0.547
1 -
0.319 0.171
0.473(*) 0.035
0.739(**) 0.000
0.403 0.078
Clients or Customers
Sig. 0.455(*) 0.044
0.319 0.171
1 -
0.719(**) 0.000
0.386 0.093
0.749(**) 0.000
Operating Goals
Sig. 0.669(**)
0.001 0.473(*) 0.035
0.719(**) 0.000
1 -
0.529(*) 0.017
0.745(**) 0.000
Employee Skills
Sig. 0.214 0.365
0.739(**) 0.000
0.386 0.093
0.529(*) 0.017
1 -
0.609(**) 0.004
Technology
Sig. 0.493(*) 0.027
0.403 0.078
0.749(**) 0.000
0.745(**) 0.000
0.609(**) 0.004
1 -
* Correlation is significant at the 0.05 level (2-tailed) ** Correlation is significant at the 0.01 level (2-tailed) (n=20)
Table 6.17: Correlation between Types of Domain Similarity (QDPW)
Communications * Concepts are measured on scale of 0 to 6, with 0 indicating not once the other party was
contacted 6 indicating many times daily Mean Median Standard
Deviation Written Report 4.40 4.00 1.23 Face-to-Face Talks 4.45 4.00 1.19 Telephone Calls 4.30 4.50 1.26 Group Meetings 2.55 3.00 1.15
(n=20)
Table 6.18: Frequency of Communication (QDPW)
224
APPENDIX IV SURVEY RESULTS
Working Relationship Effectiveness
(QDPW)
Working Relationship Effectiveness (Other Units)
Written Reports
Face-to-Face Talks
Telephone Calls
Group Meetings
Working Relationship Effectiveness (QDPW)
Sig. 1 -
0.537(*) 0.015
0.301 0.198
0.574(**) 0.008
0.315 0.176
0.227 0.335
Working Relationship Effectiveness (Other Units)
Sig. 0.537(*) 0.015
1 -
0.015 0.951
0.232 0.324
0.135 0.570
0.168 0.478
Written Reports
Sig. 0.301 0.198
0.015 0.951
1 -
0.366 0.113
0.665(**) 0.001
0.395 0.084
Face-to-Face Talks
Sig. 0.574(**)
0.008 0.232 0.324
0.366 0.113
1 -
0.467(*) 0.038
0.336 0.147
Telephone Calls
Sig. 0.315 0.176
0.135 0.570
0.665(**) 0.001
0.467(*) 0.038
1 -
0.536(*) 0.015
Group Meetings
Sig. 0.227 0.335
0.168 0.478
0.395 0.084
0.336 0.147
0.536(*) 0.015
1 -
** Correlation is significant at the 0.01 level (2-tailed) * Correlation is significant at the 0.05 level (2-tailed) (n=20)
Table 6.19: Correlation between Working Relationship Effectiveness and Methods of Communication (QDPW & Other Units)
Mean Median Standard Deviation
QDPW 4.60 5.00 1.19 Other Units 5.05 5.00 0.89
(n=20)
Table 6.20: Frequency of Contacts between QDPW and Other Units
Mean Median Standard Deviation
QDPW 31% 10% 35% Other Units 34% 15% 36%
(n=20)
Table 6.21: Percent of Time Spent between QDPW and Other Units
Mean Median Standard Deviation
QDPW 0.61 0.55 0.19 (n=20)
Table 6.22: Contacts Initiated by QDPW
225
APPENDIX IV SURVEY RESULTS
* Concepts are measured on scale of 0 to 5, with 0 indicating no contact, 1 indicating little
difficulty and 5 indicating high difficulty Mean Median Standard Deviation
QDPW 2.60 3.00 1.00 Other Units 1.55 1.50 0.61
(n=20)
Table 6.23: Difficulty on Getting in Touch (QDPW & Other Units)
Mean Median Standard Deviation
QDPW 1.95 2.00 0.76 Other Units 1.80 2.00 0.70
(n=20)
Table 6.24: Difficulty on Getting Ideas Across (QDPW & Other Units)
Consensus Difficulty Getting in Touch Difficulty Getting Ideas
Across
Consensus Sig.
1 -
-0.125 0.599
-0.594(**) 0.006
Difficulty Getting in Touch Sig.
-0.125 0.599
1 -
0.470(*) 0.037
Difficulty Getting Ideas Across
Sig. -0.594(**)
0.006 0.470(*) 0.037
1 -
** Correlation is significant at the 0.01 level (2-tailed) * Correlation is significant at the 0.05 level (2-tailed)
Table 6.25: Correlation between Consensus and Quality of Communication (QDPW)
226
APPENDIX IV SURVEY RESULTS
Difficulty Getting in
Touch (QDPW)
Difficulty Getting in
Touch (Other Units)
Difficulty Getting Ideas
Across (QDPW)
Difficulty Getting Ideas
Across (Other Units)
Other Units
Hindered QDPW
QDPW Hindered
Other Units
Dispute (QDPW)
Dispute (Other Units)
Difficulty Getting in Touch (QDPW)
Sig. 1 -
-0.140 0.556
0.390 0.089
0.182 0.441
-0.225 0.340
0.222 0.346
0.061 0.798
0.290 0.215
Difficulty Getting in Touch (Other Units)
Sig. -0.140 0.556
1 -
0.063 0.792
0.400 0.080
0..586(**) 0.007
-0.046 0.848
0.113 0.635
0.305 0.192
Difficulty Getting Ideas Across (QDPW)
Sig. 0.390 0.089
0.063 0.792
1 -
0..379 0.100
-0.151 0.526
0.036 0.879
0.262 0.265
0.496(*) 0.026
Difficulty Getting Ideas Across (Other Units)
Sig. 0.182 0.441
0.400 0.080
0.379 0.100
1 -
0.107 0.653
0.424 0.063
0.366 0.112
0.783(**) 0.000
Other Units Hindered QDPW
Sig. -0.225 0.340
0.586(**) 0.007
-0.151 0.526
0.107 0.653
1 -
-0.009 0.969
-0.079 0.739
0.089 0.708
QDPW Hindered Other Units
Sig. 0.222 0.346
-0.046 0.848
0.036 0.879
0.424 0.063
-0.009 0.969
1 -
-0.080 0.738
0.533(*) 0.016
Dispute (QDPW)
Sig. 0.275 0.241
-0.223 0.345
0.257 0.274
0.139 0.560
-0.507(*) 0.023
-0.077 0.746
1 -
-0.116 0.625
Dispute (Other Units)
Sig. 0.290 0.215
0.305 0.192
0.496(*) 0.026
0.783(**) 0.000
0.089 0.708
0.533(*) 0.016
-0.008 0.974
1 -
** Correlation is significant at the 0.01 level (2-tailed) * Correlation is significant at the 0.05 level (2-tailed) (n=20)
Table 6.26: Correlation between Quality of Communication, Frequency of Conflict and Hindered Performance between Parties
Resource Flows * Concepts are measured on scale of 1 to 5, with 1 indicating almost all the same resources
each time and 5 indicating almost all different each time Mean Median Standard Deviation
Work 0.29 0.20 0.35 Money or Budget 0.16 0.00 0.30 Technical Assistance 0.23 0.08 0.34
(n=17)
Table 6.27: Resource Flows from Other Units to QDPW
227
APPENDIX IV SURVEY RESULTS
Mean Median Standard Deviation
Work 0.34 0.20 0.32 Money or Budget 024 0.01 0.36 Technical Assistance 0.28 0.20 0.30
(n=17)
Table 6.28: Resource Flows from QDPW to Other Units
Variability of Resource Flows
Mean Median Standard Deviation Same Each Time* 2.40 2.50 1.35 Problems Encountered** 2.05 2.00 1.15 Interruptions*** 2.00 2.00 1.17
(n=17)
* Concepts are measured on scale of 1 to 5, with 1 indicating resources received/sent were almost all the same each time and 5 indicating almost all different each time
** Concepts are measured on scale of 1 to 6, with 1 indicating no problem was encountered and 6 indicating several times a day
*** Concepts are measured on scale of 1 to 5, with 1 indicating interruptions encountered were to no extent and 5 indicating to very great extent
Table 6.29: Variability of Resource Flows (QDPW)
Resource Flows Same Each Time
Resource Flow Problems
Encountered Resource Flow Interruptions
Relationship Clearly Specified
Standardised Relationship
Resource Flows Same Each Time
Sig. 1 -
0.835(**) 0.000
0.731(**) 0.000
0.133 0.577
0.665(**) 0.001
Resource Flow Problems Encountered
Sig. 0.835(**)
0.000 1 -
0.707(**) 0.000
0.008 0.974
0.624(**) 0.003
Resource Flow Interruptions
Sig. 0.731(**)
0.000 0.707(**)
0.000 1 -
0.138 0.561
0.649(**) 0.002
Relationship Clearly Specified
Sig. 0.133 0.577
0.008 0.974
0.138 0.561
1 -
0.084 0.724
Standardised Relationship
Sig. 0.665(**)
0.001 0.624(**)
0.003 0.649(**)
0.002 0.084 0.724
1 -
** Correlation is significant at the 0.01 level (2-tailed) (n=20)
Table 6.30: Correlation between Variability of Resource Flow and Relationship Formalisation (QDPW)
228
APPENDIX IV SURVEY RESULTS
Formalisation of Interunit Relationship * Concepts are measured on scale of 1 to 5, with 1 indicating to no extent and 5 indicating
great extent Mean Median Standard Deviation
QDPW 3.35 3.00 0.81 Other Units 3.50 3.00 0.89
(n=20)
Table 6.31: Relation Explicitly Verbalised (QDPW & Other Units)
Mean Median Standard Deviation
QDPW 3.90 4.00 1.12 Other Units 2.75 2.50 1.45
(n=20)
Table 6.32: Relation Written Down in Detail (QDPW & Other Units)
Interunit Influence * Concepts are measured on scale of 1 to 5, with 1 indicating no influence and 5 indicating
very much influence Mean Median Standard Deviation
QDPW 2.00 1.50 1.17 Other Units 2.40 2.00 1.00
(n=20)
Table 6.33: Other Units' Operations Influenced by QDPW
* Concepts are measured on scale of 1 to 5, with 1 indicating to no extent and 5 indicating
great extent Mean Median Standard Deviation
QDPW 2.90 3.00 0.91 Other Units 2.25 2.00 0.79
(n=20)
Table 6.34: QDPW Changed Other Units' Goals/Services
* Concepts are measured on scale of 1 to 5, with 1 indicating no influence and 5 indicating
very much influence Mean Median Standard Deviation
QDPW 2.85 3.00 1.31 Other Units 2.30 2.00 1.34
(n=20)
Table 6.35: QDPW's Operations Influenced by Other Units
229
APPENDIX IV SURVEY RESULTS
* Concepts are measured on scale of 1 to 5, with 1 indicating to no extent and 5 indicating
great extent Mean Median Standard Deviation
QDPW 2.80 3.00 1.15 Other Units 2.00 2.00 0.56
(n=20)
Table 6.36: Other Units Changed QDPW Goals/Services
Perceived Effectiveness of Relationship * Concepts are measured on scale of 1 to 5, with 1 indicating to no extent and 5 indicating
great extent Mean Median Standard Deviation
QDPW 4.20 4.00 0.41 Other Units 4.25 4.00 0.64
(n=20)
Table 6.37: Extent of Commitments Carried Out by Other Units (QDPW)
Mean Median Standard Deviation
QDPW 4.20 4.00 0.52 Other Units 4.30 4.00 0.57
(n=20)
Table 6.38: Extent of Commitments Carried Out by QDPW
Mean Median Standard Deviation
QDPW 4.10 4.00 0.447 Other Units 4.30 4.00 0.66
(n=20)
Table 6.39: Productive Relationship (QDPW & Other Units)
Mean Median Standard Deviation
QDPW 4.20 4.00 0.52 Other Units 4.30 4.00 0.73
(n=20)
Table 6.40: Time and Effort (QDPW & Other Units)
Mean Median Standard Deviation
QDPW 4.15 4.00 0.49 Other Units 4.35 4.50 0.81
(n=20)
Table 6.41: Relationship Satisfaction (QDPW & Other Units)
230
APPENDIX IV SURVEY RESULTS
* Concepts are measured on scale of 1 to 5, with 1 indicating “we get much less than we ought” and 5 indicating “we get much more than we ought”
Mean Median Standard Deviation QDPW 2.35 3.00 1.23 Other Units 3.15 3.00 0.75
(n=20)
Table 6.42: Transaction Equality (QDPW & Other Units)
231
APPENDIX IV SURVEY RESULTS
Commitments (OU)
Commitments (QDPW)
Productive Relation-ship Time & Effort
Relationship Satisfaction
Equality of Transact-ions
Relationship Clearly
Specified Standardised Relationship
Resource Flow to QDPW
Resource Flow from QDPW
Poor Communi-
cation Quality
Freq. of Communi-
cation Domain
Similarity Resource
Dependence Awareness Personal
Acquaintance Consensus
Commitments (OU)
Sig.N
1 -
20
0.466(*) 0.038
20 0.419 0.066
0.371 0.108
20
0.223 0.344
20
-0.106 0.657
20
-0.316 0.175
20
0.032 0.893
20
-0.054 0.831
18
-0.284 0.268
17
-0.456(*) 0.043
20
-0.331 0.153
20
0.141 0.552
20
-0.222 0.361
19
-0.097 0.683
20
0.183 0.440
20
0.282 0.228
20 Commitments (QDPW)
Sig.N
0.466(*) 0.038
20
1 -
20
0.866(**) 0.000
20
0.313 0.179
20
0.533(*) 0.016
20
0.236 0.316
20
0.222 0.346
20
-0.179 0.451
20
0.002 0.994
18
0.104 0.691
17
-0.661(**) 0.002
20
-0.059 0.804
20
0.055 0.817
20
0.354 0.137
19
-0.038 0.874
20
0.444(*) 0.050
20
0.397 0.083
20 Productive Relationship
Sig.N
0.419 0.066
20
0.866(**) 0.000
20
1 -
20
0.475(*) 0.035
20
0.769(**) 0.000
20
0.128 0.591
20
0.263 0.263
20
-0.215 0.363
20
0.246 0.325
18
0.294 0.252
17
-0.625(**) 0.003
20
0.138 0.563
20
0.046 0.848
20
0.462(*) 0.046
19
0.253 0.281
20
0.650(**) 0.002
20
0.562(**) 0.010
20 Time & Effort
Sig.N
0.371 0.108
20
0.313 0.179
20
0.475(*) 0.035
20
1 -
20
0.612(**) 0.004
20
-0.185 0.435
20
0.209 0.377
20
0.093 0.696
20
0.335 0.174
18
0.415 0.098
17
-0.198 0.404
20
0.225 0.340
20
-0.198 0.402
20
0.351 0.140
19
0.248 0.291
20
0.418 0.067
20
0.234 0.321
20 Relationship Satisfaction
Sig.N
0.223 0.344
20
0.533(*) 0.016
20
0.769(**) 0.000
20
0.612(**) 0.004
20
1 -
20
0.000 1.000
20
0.180 0.448
20
-0.124 0.604
20
0.172 0.495
19
0.199 0.443
17
-0.507(*) 0.022
20
0.211 0.373
20
-0.065 0.784
20
0.357 0.134
19
0.268 0.253
20
0.558(*) 0.011
20
0.381 0.097
20 Equality of Transactions
Sig.N
-0.106 0.657
20
0.236 0.316
20
0.128 0.591
20
-0.185 0.435
20
0.000 1.000
20
1 -
20
0.131 0.581
20
-0.457(*) 0.043
20
-0.039 0.878
18
0.277 0.282
17
0.036 0.882
20
0.352 0.127
20
0.255 0.278
20
0.109 0.655
19
0.223 0.345
20
0.045 0.850
20
-0.097 0.684
20 Relationship Clearly Specified
Sig.N
-0.316 0.175
20
0.222 0.346
20
0.263 0.263
20
0.209 0.377
20
0.180 0.448
20
0.131 0.581
20
1 -
20
0.084 0.724
20
0.195 0.439
18
0.489(*) 0.046
17
-0.255 0.277
20
0.517(*) 0.020
20
0.000 1.000
20
0.502(*) 0.029
19
0.366 0.112
20
0.497(*) 0.026
20
0.352 0.128
20 Standardised Relationship
Sig.N
0.032 0.893
20
-0.179 0.451
20
-0.215 0.363
20
0.093 0.696
20
-0.124 0.604
20
-0.457(*) 0.043
20
0.084 0.724
20
1 -
20
-0.315 0.203
18
-0.406 0.106
17
-0.009 0.970
20
-0.235 0.319
20
-0.145 0.542
20
0.000 0.999
19
-0.169 0.477
20
-0.251 0.286
20
-0.011 0.963
20 Resource Flow to QDPW
Sig.N
-0.054 0.831 18
0.002 0.994
18
0.246 0.325
18
0.335 0.174
18
0.172 0.495
18
-0.039 0.878
18
0.195 0.439
18
-0.315 0.203
18 1 -
0.623(**) 0.008
17
0.254 0.309
18
0.510(*) 0.031
18
0.357 0.146
18
0.400 0.111
18
0.568(*) 0.014
18
0.488(*) 0.040
18
0.590(*) 0.010
18 Resource Flow from QDPW
Sig.N
-0.284 0.268
17
0.104 0.691
17
0.294 0.252
17
0.415 0.098
17
0.199 0.443
17
0.277 0.282
17
0.489(*) 0.046
17
-0.406 0.106
17
0.623(**) 0.008
17 1 -
0.016 0.952
17
0.549(*) 0.023
17
-0.107 0.683
17
0.432 0.095
17
0.219 0.398
17
0.468 0.058
17
0.081 0.758
17 Communication Quality
Sig.N
-0.456(*) 0.043
20
-0.661(**) 0.002
20
-0.625(**) 0.003
20
-0.198 0.404
20
-0.507(*) 0.022
20
0.036 0.882
20
-0.255 0.277
20
-0.009 0.970
20
0.254 0.309
18
0.016 0.952
17
1 -
20
0.210 0.374
20
-0.064 0.789
20
0.015 0.951
19
0.225 0.341
20
-0.510(*) 0.022
20
-0.442 0.051
20 Freq. of Communication
Sig.N
-0.331 0.153
20
-0.059 0.804
20
0.138 0.563
20
0.225 0.340
20
0.211 0.373
20
0.352 0.127
20
0.517(*) 0.020
20
-0.235 0.319
20
0.510(*) 0.031
18
0.549(*) 0.023
17
0.210 0.374
20
1 -
20
0.281 0.231
20
0.454 0.051
19
0.533(*) 0.016
20
0.453(*) 0.045
20
0.143 0.546
20 Domain Similarity
Sig.N
0.141 0.552
20
0.055 0.817
20
0.046 0.848
20
-0.198 0.402
20
-0.065 0.784
20
0.255 0.278
20
0.000 1.000
20
-0.145 0.542
20
0.357 0.146
18
-0.107 0.683
17
-0.064 0.789
20
0.281 0.231
20
1 -
20
-0.054 0.825
19
0.387 0.092
20
0.223 0.346
20
0.483(*) 0.031
20 Resource Dependence
Sig.N
-0.222 0.361
19
0.354 0.137
19
0.462(*) 0.046
19
0.351 0.140
19
0.357 0.134
19
0.109 0.655
19
0.502(*) 0.029
19
0.000 0.999
19
0.400 0.111
18
0.432 0.095
17
0.015 0.951
19
0.454 0.051
19
-0.054 0.825
19
1 -
19
0.695(**) 0.001
19
0.354 0.137
19
0.194 0.426
19 Awareness
Sig.N
-0.097 0.683
20
-0.038 0.874
20
0.253 0.281
20
0.248 0.291
20
0.268 0.253
20
0.223 0.345
20
0.366 0.112
20
-0.169 0.477
20
0.568(*) 0.01 18
0.219 0.398
17
0.225 0.341
20
0.533(*) 0.016
20
0.387 0.092
20
0.695(**) 0.001
19
1 -
20
0.406 0.076
20
0.486(*) 0.030
20 Personal Acquaintance
Sig.N
0.183 0.440
20
0.444(*) 0.050
20
0.650(**) 0.002
20
0.418 0.067
20
0.558(*) 0.011
20
0.045 0.850
20
0.497(*) 0.026
20
-0.251 0.286
20
0.488(*) 0.040
18
0.468 0.058
17
-0.510(*) 0.022
20
0.453(*) 0.045
20
0.223 0.346
20
0.354 0.137
19
0.406 0.076
20
1 -
20
0.730(**) 0.000
20 Consensus
Sig. N
0.282 0.228
20
0.397 0.083
20
0.562(**) 0.010
20
0.234 0.321
20
0.381 0.097
20
-0.097 0.684
20
0.352 0.128
20
-0.011 0.963
20
0.590(*) 0.010
18
0.081 0.758
17
-0.442 0.051
20
0.143 0.546
20
0.483(*) 0.031
20
0.194 0.426
19
0.486(*) 0.030
20
0.730(**) 0.000
20
1 -
20
** Correlation is significant at the 0.01 level (2-tailed) * Correlation is significant at the 0.05 level (2-tailed)
Table 6.43: Correlation between Perceived Effectiveness of Relationship and Relationship Indices (QDPW)
233
APPENDIX IV SURVEY RESULTS
Culture
PDI UAI IDV MAS
Hofstede 36 51 90 61
Survey Findings 16 42 90 33
Keys: PDI – Power Distance Index UAI – Uncertainty Avoidance Index IDV – Individualism Index MAS – Masculinity Index
(n=16)
Table 6.44: Scores for Australian Professionals on Hofstede Indices
Mean Median Standard Deviation
Personal Time 1.83 2.00 0.41 Challenge 2.17 2.00 0.41 Stress 2.67 2.50 0.82 Physical Condition 2.33 2.00 1.03 Relationship with Superior 1.67 2.00 0.52 Employment Security 2.50 2.50 0.55 Freedom 2.50 2.50 0.55 Cooperation 2.00 2.00 0.63 Consult by Superior 2.17 2.00 0.75 Contribution to Company 2.17 2.00 0.41 High Earning 2.17 2.00 0.41 Serve the Country 3.67 4.00 0.52 Desirable Living Area 2.00 2.00 0.00 Opportunity for Advancement 2.33 2.00 0.52 Job Adventure 2.17 2.00 0.41 Successful Company 3.00 3.00 0.63 Help the Others 2.67 2.50 0.82 Job Definition 2.67 2.50 0.82
(n=6) * Concepts are measured on a scale of 1 to 5, with 1 indicating utmost importance and 5
indicating little to no importance on the said criteria for an ideal job.
Table 6.45: Importance of Criteria for an Ideal Job (QDPW)
234
APPENDIX IV SURVEY RESULTS
Mean Median Standard Deviation
Organisation’s rule should not be broken under any circumstances
3.17
3.00
0.75
Trust 2.00 2.00 0.00 Dislike of work 4.00 4.00 0.00 More desirable to work in a large corporation
3.33
3.00
0.82
(n=6) * Concepts are measured on a scale of 1 to 5, with 1 indicating strongly agree with the
statement and 5 strongly disagree.
Table 6.46: Levels of Agreement on Statements (QDPW)
Mean Median Standard Deviation Personal relationship are important in managing project/contract
1.67
2.00
0.52
Formal procedures are necessary for the successful management of a project
2.00
2.00
0.63
Informal arrangements are necessary for the successful management of a project
2.67
2.50
0.82
Personal relationships amongst the project members are more important than those in your employer’s organization
2.33
2.50
0.82
One must be willing to sacrifice personal relationships with members of the project team to ensure the successful completion of the project
2.67
2.50
0.82
One must be willing to sacrifice personal relationships with members of the project team to ensure their firm’s objectives are met
2.83
2.50
0.98
On must be willing to sacrifice personal relationships with members of the project team to ensure one’s personal objectives are met
3.50
4.00
0.84
One must be prepared to disregard formal procedures in order to ensure the successful completion of the project
2.67
2.00
1.03
One must be prepared to disregard formal procedures in order to ensure one’s firm’s objectives met
3.17
3.00
0.75
One must be prepared to disregard formal procedures in order to ensure one’s own objectives are met
3.50
4.00
0.84
(n=6) * Concepts are measured on a scale of 1 to 5, with 1 indicating strongly agree with the
statement and 5 strongly disagree.
Table 6.47: Agreement to Statements in Relation to Project Success or Achieving Objectives (QDPW)
235
APPENDIX IV SURVEY RESULTS
QDMR Survey Results
Organisational Culture Organisational Culture Preferred Culture Perceived Culture
Power 0 2.5b Role 0.5a 4b,c Task 8.5a 3.5c Person 1 0
(n=10) a Same score for Role and Task Culture was calculated from one of the returned
questionnaires. b Same score for Power and Role Culture was calculated from one of the returned
questionnaires. c Same score for Role and Task Culture was calculated from one of the returned
questionnaires.
Table 6.48: Organisational Culture (QDMR)
Commitment
Type of Commitment Mean Median Standard Deviation
Affective 48.7 48.0 2.5 Normative 36.0 35.5 8.5 Continuance 35.0 37.5 6.2
(n=10) * Concepts are measured on a scale of 1 to 7, with 1 indicating low levels of commitment and
7 indicating high levels, for six variables giving, for each scale, maximum scores of 56 and minimum scores of 9.
Table 6.49: Commitment Levels (QDMR)
236
APPENDIX IV SURVEY RESULTS
Organisational Assessment Systematized
Impersonal Mode
Discretionary Personal Mode
Developmental Group Mode
Salient Dimensions of Managerial Subsystem
1. Organizational Referent Hierarchy & staff 2. Coordination and Control by: Rules, plans,
schedules
3. Resource & Information Flows among Organizational Levels, Units, & Positions:
a. Direction Diffuse b. Amount Medium c. Standardization &
Codification Medium
4. Perceived Interdependence among Components High
5. Frequency of conflict among Components Low Medium
Table 6.50: Hypothesised Patterns of Design Mode in QDMR
Resource Dependence
* Concepts are measured on a scale of 1 to 5, with 1 indicating no resources were received and 5 indicating large amount of resources received
Mean Median Standard Deviation
QDMR 3.50 3.00 1.06 Other Units 4.00 4.00 0.82
(n=22)
Table 6.51: Other Units Resource Dependence on QDMR
Mean Median Standard
Deviation QDMR 3.91 4.00 0.75 Other Units 4.32 4.00 0.72
(n=22)
Table 6.52: QDMR Resource Dependence on Other Units
* Concepts are measured on a scale of 1 to 5, with 1 indicating the importance of the other
party is not very important and 5 indicating it is absolutely crucial Mean Median Standard Deviation
To QDMR 3.95 4.00 0.79 To Other Units 3.50 3.50 1.06
(n=22)
Table 6.53: Resource Importance between QDMR and Other Units
237
APPENDIX IV SURVEY RESULTS
Awareness of Relationship * Concepts are measured on a scale of 1 to 5, with 1 indicating goals and services are not
informed at all and 5 indicating they are very well informed Mean Median Standard Deviation
QDMR 3.82 4.00 0.85 Other Units 3.82 4.00 0.91
(n=22)
Table 6.54: Goals Informed between QDMR and Other Services
* Concepts are measured on a scale of 1 to 5, with 1 indicating there is no personal
acquaintance and 5 indicating the personal acquaintance is very well Mean Median Standard Deviation
QDMR 3.18 3.00 1.01 Other Units 4.00 4.00 0.93
(n=22)
Table 6.55: Degree of Personal Acquaintance (QDMR & Other Units)
Consensus/Conflict * Concepts are measured on scale of 0 to 5, with 0 indicating no knowing if the other party
agrees on goal priorities/way of work or services provided/terms of relationship/hindered performance, and 5 indicating knowing the other party agree very much on items
Mean Median Standard Deviation
Goal Priorities QDMR 3.82 4.00 1.14 Other Units 3.55 3.50 0.96
Ways of Work/Services Are Provided
QDMR 3.59 4.00 1.05 Other Units 3.55 4.00 0.91
Terms of Relationship QDMR 3.82 4.00 0.85 Other Units 3.68 4.00 1.00
(n=22)
Table 6.56: Consensus and Conflict between QDMR and Other Units
238
APPENDIX IV SURVEY RESULTS
Mean Median Standard Deviation
QDMR 2.14 2.00 0.94 Other Units 1.55 1.00 1.01
(n=22)
Table 6.57: Hindered Performance by Other Parties (QDMR & Other Units)
* Concepts are measured on scale of 1 to 6, with 1 indicating no disagreement or dispute
during the last six month, and 6 indicating they happen everyday Mean Median Standard Deviation
QDMR 2.09 2.00 0.92 Other Units 2.09 2.00 1.34
(n=22)
Table 6.58: Frequency of Conflict (QDMR & Other Units)
Personal
Acquaintance (QDMR)
Personal Acquaintance (Other Units)
Frequency of Conflict
(QDMR)
Frequency of Conflict
(Other Units) Personal Acquaintance (QDMR)
Sig. 1 -
0.409 0.059
-0.327 0.138
-0.260 0.243
Personal Acquaintance (Other Units)
Sig. 0.409 0.059
1 -
-0.391 0.072
-0.230 0.303
Frequency of Conflict (QDMR)
Sig. -0.327 0.138
-0.391 0.072
1 -
0.378 0.083
Frequency of Conflict (Other Units)
Sig. -0.260 0.243
-0.230 0.303
0.378 0.083
1 - (n=22)
Table 6.59: Correlations between QDMR and Other Units on Personal Acquaintance and Frequency of Conflict
239
APPENDIX IV SURVEY RESULTS
Methods of Conflict Resolution
* Concepts are measured on a scale of 1 to 5, with 1 indicating the conflict resolution was almost never and 5 indicating it was used almost always
Mean Median Standard Deviation
Avoiding Issues 1.27 1.00 0.63 Smoothing Over Issues 1.68 1.00 0.89 Confronting Issues 3.50 4.00 0.86 Hierarchy 1.95 2.00 0.90
(n=22)
Table 6.60: Frequency on Use of Methods of Conflict Resolution (QDMR)
Working Relationship Effectiveness
(QDMR)
Working Relationship Effectiveness (Other Units)
Avoiding Issues
Smoothing Over Issues
Confronting Issues Hierarchy
Working Relationship Effectiveness (QDMR)
Sig. 1 -
-0.181 0.421
-0.438* 0.041
-0.525* 0.012
-0.258 0.246
0.157 0.485
Working Relationship Effectiveness (Other Units)
Sig. -0.181 0.421
1 -
0.112 0.619
0.198 0.376
-0.151 0.501
-0.158 0.483
Avoiding Issues
Sig. -0.438* 0.041
0.112 0.619
1 -
0.752** 0.000
-0.351 0.109
0.023 0.919
Smoothing Over Issues
Sig. -0.525* 0.012
0.198 0.376
0.752** 0.000
1 -
-0.155 0.491
-0.078 0.730
Confronting Issues
Sig. -0.258 0.246
-0.151 0.501
-0.351 0.109
-0.155 0.491
1 -
-0.216 0.335
Hierarchy
Sig. 0.157 0.485
-0.158 0.483
0.023 0.919
-0.078 0.730
-0.216 0.355
1 -
* Correlation is significant at the 0.05 level (2-tailed) (n=22) ** Correlation is significant at the 0.01 level (2-tailed)
Table 6.61: Correlation between Working Relationship Effectiveness and Methods of Conflict Resolution (QDMR)
240
APPENDIX IV SURVEY RESULTS
Domain Similarity
* Concepts are measured on scale of 0 to 5, with 0 indicating no knowing the extent of domain similarity, and 5 indicating great extent of domain similarity
Mean Median Standard Deviation
Funding Source 4.18 5.00 1.50 Work Kind 2.00 2.00 1.11 Clients or Customers 3.23 3.00 1.11 Operating Goals 3.45 3.00 0.91 Employee Skills 3.55 3.50 1.14 Technology 3.68 4.00 0.78
(n=22) * Concepts are measured on scale of 0 to 5, with 0 indicating no knowing of the extent of
domain similarity, and 5 indicating great extent of domain similarity.
Table 6.62: Domain Similarity (QDMR)
Funding Source Work Kind
Clients or Customers
Operating Goals
Employee Skills Technology
Funding Source
Sig. 1 -
0.371 0.089
0.260 0.243
0.180 0.422
-0.061 0.789
0.337 0.126
Work Kind
Sig. 0.371 0.089
1 -
0.540** 0.010
0.563** 0.006
0.299 0.176
0.494* 0.019
Clients or Customers
Sig. 0.260 0.243
0.540** 0.010
1 -
0.175 0.435
0.048 0.833
0.363 0.097
Operating Goals
Sig. 0.180 0.422
0.563** 0.006
0.175 0.435
1 -
0.162 0.471
0.347 0.114
Employee Skills
Sig. -0.061 0.789
0.299 0.176
0.048 0.833
0.162 0.471
1 -
0.364 0.096
Technology
Sig. 0.337 0.126
0.494* 0.019
0.363 0.097
0.347 0.114
0.364 0.096
1 -
* Correlation is significant at the 0.05 level (2-tailed) (n=22) ** Correlation is significant at the 0.01 level (2-tailed)
Table 6.63: Correlation between Types of Domain Similarity (QDMR)
241
APPENDIX IV SURVEY RESULTS
Communication * Concepts are measured on scale of 0 to 6, with 0 indicating not once the other party was
contacted 6 indicating many times daily Mean Median Standard
Deviation Written Report 3.73 3.00 1.49 Face-to-Face Talks 4.27 4.50 1.55 Telephone Calls 4.41 5.00 122 Group Meetings 2.50 2.50 1.26
(n=22)
Table 6.64: Frequency of Communication (QDMR)
Working Relationship Effectiveness
(Project Services)
Working Relationship Effectiveness (Other Units)
Written Reports
Face-to-Face Talks
Telephone Calls
Group Meetings
Working Relationship Effectiveness (Project Services)
Sig. 1 -
-0.181 0.421
0.143 0.524
-0.260 0.242
-0.106 0.638
-0.226 0.312
Working Relationship Effectiveness (Other Units)
Sig. -0.181 0.421
1 -
0.171 0.447
0.298 0.179
0.247 0.268
0.206 0.358
Written Reports
Sig. 0.143 0.514
0.171 0.447
1 -
0.427* 0.047
0.720** 0.000
0.457* 0.033
Face-to-Face Talks
Sig. -0.260 0.242
0.298 0.179
0.427* 0.047
1 -
0.568** 0.006
0.633** 0.002
Telephone Calls
Sig. -0.106 0.638
0.247 0.268
0.720** 0.000
0.568** 0.006
1 -
0.479* 0.024
Group Meetings
Sig. -0.226 0.312
0.206 0.358
0.457* 0.033
0.633** 0.002
0.479* 0.024
1 -
* Correlation is significant at the 0.05 level (2-tailed) ** Correlation is significant at the 0.01 level (2-tailed) (n=22)
Table 6.65: Correlation between Working Relationship Effectiveness and Methods of Communication (QDMR & Other Units)
Mean Median Standard Deviation QDMR 4.61 5.00 1.07 Other Units 4.91 5.00 1.02
(n=22)
Table 6.66: Frequency of Contact between QDMR and Other Units
242
APPENDIX IV SURVEY RESULTS
Mean Median Standard Deviation
QDMR 14% 8% 0.21 Other Units 22% 10% 0.26
(n=22)
Table 6.67: Percent of Time Spent between QDMR and Other Units
Mean Median Standard Deviation
QDMR 0.55 0.50 0.11 (n=22)
Table 6.68: Percent of Contact Initiated by QDMR
* Concepts are measured on scale of 0 to 5, with 0 indicating no contact, 1 indicating little
difficulty and 5 indicating high difficulty Mean Median Standard Deviation
QDMR 1.55 1.00 0.74 Other Units 2.18 2.00 0.91
(n=22)
Table 6.69: Difficulty on Getting in Touch (QDMR & Other Units)
Mean Median Standard Deviation
QDMR 1.95 2.00 0.79 Other Units 2.36 2.00 0.66
(n=22)
Table 6.70: Difficulty on Getting Ideas Across (QDMR & Other Units)
Consensus Difficulty Getting in Touch Difficulty Getting Ideas
Across
Consensus Sig.
1 -
-0.249 0.263
0.000 0.999
Difficulty Getting in Touch Sig.
-0.249 0.263
1 -
0.382 0.080
Difficulty Getting Ideas Across
Sig. 0.000 0.999
0.382 0.080
1 -
(n=22)
Table 6.71: Correlation between Consensus and Quality of Communication (QDMR)
243
APPENDIX IV SURVEY RESULTS
Difficulty Getting in
Touch (QDMR)
Difficulty Getting in
Touch (Other Units)
Difficulty Getting Ideas
Across (QDMR)
Difficulty Getting Ideas
Across (Other Units)
Other Units
Hindered QDMR
QDMR Hindered
Other Units
Dispute (QDMR)
Dispute (Other Units)
Difficulty Getting in Touch (QDMR)
Sig. 1 -
-0.297 0.179
-0.037 0.869
0.258 0.246
-0.044 0.847
0.157 0.487
-0.076 0.736
0.188 0.403
Difficulty Getting in Touch (Other Units)
Sig. -0.297 0.179
1 -
0.213 0.342
0.283 0.202
0.304 0.168
-0.009 0.967
0.321 0.145
-0.171 0.447
Difficulty Getting Ideas Across (QDMR)
Sig. -0.037 0.869
0.213 0.342
1 -
0.218 0.330
0.653** 0.001
-0.027 0.904
0.203 0.364
0.049 0.828
Difficulty Getting Ideas Across (Other Units)
Sig. 0.258 0.246
0.283 0.202
0.218 0.330
1 -
0.147 0.514
0.762** 0.000
0.493* 0.020
0.446* 0.037
Other Units Hindered QDMR
Sig. -0.044 0.847
0.304 0.168
0.653** 0.001
0.147 0.514
1 -
-0.032 0.888
0.370 0.090
-0.048 0.832
QDMR Hindered Other Units
Sig. 0.157 0.487
-0.009 0.967
-0.027 0.904
0.762** 0.000
-0.032 0.888
1 -
0.507* 0.016
0.804** 0.000
Dispute (QDMR)
Sig. -0.076 0.736
0.321 0.145
0.203 0.364
0.493* 0.020
0.370 0.090
0.507* 0.016
1 -
0.378 0.083
Dispute (Other Units)
Sig. 0.188 0.403
-0.171 0.447
0.049 0.828
0.446* 0.037
-0.048 0.832
0.904** 0.000
0.378 0.083
1 -
* Correlation is significant at the 0.05 level (2-tailed) (n=22) ** Correlation is significant at the 0.01 level (2-tailed)
Table 6.72: Correlation between Quality of Communication, Frequency of Conflict and Hindered Performance between Parties (QDMR & Other Units)
244
APPENDIX IV SURVEY RESULTS
Resource Flows
* Concepts are measured on scale of 1 to 5, with 1 indicating almost all the same resources each time and 5 indicating almost all different each time
Mean Median Standard Deviation
Work 0.24 0.10 0.32 Money or Budget 0.05 0.00 0.21 Technical Assistance 0.18 0.10 025
(n=22)
Table 6.73: Resource Flows from Other Units to QDMR
Mean Median Standard Deviation
Work 0.09 0.01 0.20 Money or Budget 0.03 0.00 0.06 Technical Assistance 0.12 0.08 0.18
(n=22)
Table 6.74: Resource Flows from QDMR to Other Units
Variability of Resources Flows
Mean Median Standard Deviation Same Each Time 2.82 3.00 1.56 Problems Encountered 2.50 2.00 0.96 Interruptions 2.05 2.00 1.09
(n=22) * Concepts are measured on scale of 1 to 5, with 1 indicating resources received/sent were
almost all the same each time and 5 indicating almost all different each time ** Concepts are measured on scale of 1 to 6, with 1 indicating no problem was encountered and
6 indicating several times a day *** Concepts are measured on scale of 1 to 5, with 1 indicating interruptions encountered were to
no extent and 5 indicating to very great extent
Table 6.75: Variability of Resource Flows (QDMR)
245
APPENDIX IV SURVEY RESULTS
Resource Flows Same Each Time
Resource Flow Problems
Encountered Resource Flow Interruptions
Relationship Clearly Specified
Standardised Relationship
Resource Flows Same Each Time
Sig. 1 -
-0.221 0.322
0.396 0.068
0.008 0.972
-0.072 0.749
Resource Flow Problems Encountered
Sig. -0.221 0.322
1 -
0.295 0.183
0.089 0.695
0.000 1.000
Resource Flow Interruptions
Sig. 0.396 0.068
0.295 0.183
1 -
0.326 0.139
-0.120 0.595
Relationship Clearly Specified
Sig. 0.008 0.972
0.089 0.695
0.326 0.139
1 -
0.457* 0.033
Standardised Relationship
Sig. -0.072 0.749
0.000 1.000
-0.120 0.595
0.457* 0.033
1 -
* Correlation is significant at the 0.05 level (2-tailed) (n=22)
Table 6.76: Correlation between Variability of Resource Flow and Relationship Formalisation (QDMR)
Formalisation of Interunit Relationship * Concepts are measured on scale of 1 to 5, with 1 indicating to no extent and 5 indicating
great extent Mean Median Standard Deviation
QDMR 3.64 4.00 0.90 Other Units 3.64 4.00 0.79
(n=22)
Table 6.77: Relation Explicitly Verbalised (QDMR & Other Units)
Mean Median Standard Deviation
QDMR 3.32 3.00 1.09 Other Units 2.59 3.00 1.10
(n=22)
Table 6.78: Relation Written Down in Detail (QDMR & Other Units)
Interunit Influence * Concepts are measured on scale of 1 to 5, with 1 indicating no influence and 5 indicating
very much influence Mean Median Standard Deviation
QDMR 2.27 2.00 1.08 Other Units 2.45 2.00 1.01
(n=22)
Table 6.79: Other Units' Operations Influenced by QDMR
246
APPENDIX IV SURVEY RESULTS
* Concepts are measured on scale of 1 to 5, with 1 indicating to no extent and 5 indicating great extent
Mean Median Standard Deviation QDMR 2.45 2.00 0.67 Other Units 2.45 2.00 0.74
(n=22)
Table 6.80: QDMR Changed Other Units' Goals/Services
* Concepts are measured on scale of 1 to 5, with 1 indicating no influence and 5 indicating
very much influence Mean Median Standard Deviation
QDMR 2.45 2.00 1.10 Other Units 2.09 2.00 0.75
(n=22)
Table 6.81: QDMR's Operations Influenced by Other Units
* Concepts are measured on scale of 1 to 5, with 1 indicating to no extent and 5 indicating
great extent Mean Median Standard Deviation
QDMR 2.18 2.00 0.66 Other Units 2.50 2.00 0.86
(n=22)
Table 6.82: Other Units Changed QDMR Goals/Services
Perceived Effectiveness of Relationship * Concepts are measured on scale of 1 to 5, with 1 indicating to no extent and 5 indicating
great extent Mean Median Standard Deviation
QDMR 4.32 4.00 0.72 Other Units 4.05 4.00 0.79
(n=22)
Table 6.83: Extent of Commitments Carried out by Other Units (QDMR)
Mean Median Standard Deviation
QDMR 4.27 4.00 0.55 Other Units 3.86 4.00 0.83
(n=22)
Table 6.84 Extent of Commitments Carried out by QDMR
247
APPENDIX IV SURVEY RESULTS
Mean Median Standard Deviation
QDMR 4.23 4.00 0.69 Other Units 4.09 4.00 0.81
(n=22)
Table 6.85: Productive Relationship (QDMR & Other Units)
Mean Median Standard Deviation
QDMR 4.36 4.00 0.58 Other Units 4.27 4.00 0.70
(n=22)
Table 6.86: Time and Effort (QDMR & Other Units)
Mean Median Standard Deviation
QDMR 4.18 4.00 0.85 Other Units 3.91 4.00 1.02
(n=22)
Table 6.87: Relationship Satisfaction (QDMR & Other Units)
* Concepts are measured on scale of 1 to 5, with 1 indicating “we get much less than we
ought” and 5 indicating “we get much more than we ought” Mean Median Standard Deviation
QDMR 2.91 3.00 0.53 Other Units 2.91 3.00 0.61
(n=22)
Table 6.88: Transaction Equality (QDMR & Other Units)
249
APPENDIX IV SURVEY RESULTS
Commit-ments (OU)
Commit-ments
(QDMR) Productive
Relationship Time & Effort
Relationship Satisfaction
Equality of Transactions
Relationship Clearly
Specified Standardised Relationship
Resource Flow to QDMR
Resource Flow from
QDMR
Poor Commu-nication Quality
Freq. of Commu-nication
Domain Similarity
Resource Dependence Awareness
Personal Acquain-
tance Consensus
Commitments (OU)
Sig. 1 -
0.571** 0.005
0.567** 0.006
0.233 0.297
0.543** 0.009
0.386 0.076
0.333 0.130
0.115 0.609
-0.028 0.902
-0.303 0.170
-0.091 0.688
0.065 0.773
-0.317 0.151
0.231 0.302
-0.068 0.764
0.250 0.261
0.031 0.893
Commitments (QDMR)
Sig. 0.571** 0.005
1 -
0.558** 0.007
0.484* 0.022
0.648** 0.001
0.154 0.494
-0.130 0.564
-0.117 0.605
0.172 0.443
-0.364 0.096
-0.168 0.455
-0.066 0.771
0.251 0.260
0.254 0.254
0.101 0.653
0.369 0.091
0.114 0.614
Productive Relationship
Sig. 0.567** 0.006
0.558** 0.007
1 -
0.610** 0.003
0.824** 0.000
0.508* 0.016
0.081 0.721
0.203 0.364
0.096 0.670
-0.403 0.063
-0.566** 0.006
-0.148 0.511
-0.082 0.718
-0.066 0.769
-0.012 0.957
0.551** 0.008
0.090 0.692
Time & Effort
Sig. 0.233 0.297
0.484* 0.022
0.610** 0.003
1 -
0.696** 0.000
0.331 0.132
-0.112 0.621
0.133 0.556
0.197 0.380
-0.165 0.464
-0.585** 0.004
0.280 0.207
0.145 0.519
0.145 0.519
0.262 0.238
0.746** 0.000
0.404 0.062
Relationship Satisfaction
Sig. 0.543** 0.009
0.648** 0.001
0.824** 0.000
0.696** 0.000
1 -
0.474* 0.026
-0.206 0.358
0.025 0.911
0.100 0.657
-0.421 0.051
-0.563** 0.006
-0.199 0.374
-0.083 0.715
-0.175 0.436
-0.159 0.479
0.533* 0.011
-0.022 0.923
Equality of Transactions
Sig. 0.386 0.076
0.154 0.494
0.508* 0.016
0.331 0.132
0.474* 0.026
1 -
-0.049 0.829
-0.003 0.989
0.146 0.516
-0.077 0.734
-0.437* 0.042
-0.058 0.798
-0.254 0.254
-0.412 0.057
-0.019 0.925
0.433* 0.044
0.068 0.764
Relationship Clearly Specified
Sig. 0.333 0.130
-0.130 0.564
0.081 0.721
-0.112 0.621
-0.206 0.358
-0.049 0.829
1 -
0.457* 0.033
-0.275 0.215
0.072 0.749
0.231 0.300
0.551** 0.008
-0.186 0.407
0.362 0.097
0.308 0.163
-0.050 0.826
0.328 0.136
Standardised Relationship
Sig. 0.115 0.609
-0.117 0.605
0.203 0.364
0.133 0.556
0.025 0.911
-0.003 0.989
0.457* 0.033
1 -
0.202 0.368
0.255 0.252
-0.216 0.335
0.323 0.143
-0.056 0.804
0.255 0.253
0.430* 0.046
-0.271 0.223
0.190 0.396
Resource Flow to QDMR
Sig. -0.028 0.902
0.172 0.443
0.096 0.670
0.197 0.380
0.100 0.657
0.4\146 0.516
-0.275 0.215
0.202 0.368
1 -
0.033 0.884
-0.120 0.595
-0.059 0.796
0.218 0.330
0.166 0.461
0.157 0.486
0.030 0.895
0.008 0.972
Resource Flow from QDMR
Sig. -0.303 0.170
-0.364 0.096
-0.403 0.063
-0.165 0.464
-0.421 0.051
-0.077 0.734
0.072 0.749
0.255 0.252
0.033 0.884
1 -
0.248 0.267
0.189 0.400
0.054 0.813
-0.018 0.937
0.178 0.428
-0.246 0.269
0.052 0.818
Communication Quality
Sig. -0.091 0.688
-0.168 0.455
-0.566* 0.006
-0.585** 0.004
-0.563** 0.006
-0.437* 0.042
0.231 0.300
-0.216 0.335
-0.120 0.595
0.248 0.267
1 -
0.033 0.884
-0.228 0.307
0.284 0.200
-0.215 0.377
-0.454* 0.034
-0.140 0.535
Freq. of Communication
Sig. 0.065 0.773
-0.066 0.771
-0.148 0.511
0.280 0.207
-0.199 0.374
-0.058 0.798
0.551** 0.008
0.323 0.143
-0.059 0.796
0.189 0.400
0.033 0.884
1 -
0.137 0.545
0.514* 0.014
0.591** 0.004
0.110 0.625
0.716** 0.000
Domain Similarity
Sig. -0.317 0.151
0.251 0.260
-0.082 0.718
0.145 0.519
-0.083 0.715
-0.254 0.254
-0.186 0.407
-0.056 0.804
0.218 0.330
0.054 0.813
-0.228 0.307
0.137 0.545
1 -
0.082 0.717
0.365 0.095
0.181 0.421
0.379 0.082
Resource Dependence
Sig. 0.231 0.302
0.254 0.254
-0.066 0.769
0.145 0.519
-0.175 0.436
-0.412 0.057
0.362 0.097
0.255 0.253
0.166 0.461
-0.018 0.937
0.284 0.200
0.514* 0.014
0.082 0.717
1 -
0.308 0.163
-0.059 0.793
0.432* 0.045
Awareness
Sig. -0.068 0.764
0.101 0.653
-0.012 0.957
0.262 0.238
-0.159 0.479
-0.019 0.935
0.308 0.163
0.430* 0.046
0.157 0.486
0.178 0.428
-0.215 0.337
0.591** 0.004
0.362 0.095
0.308 0.163
1 -
0.089 0.693
0.701** 0.000
Personal Acquaintance
Sig. 0.250 0.261
0.369 0.091
0.551** 0.008
0.746** 0.000
0.533* 0.011
0.433* 0.044
-0.050 0.826
-0.271 0.223
0.030 0.895
-0.246 0.269
-0.454* 0.034
0.110 0.625
0.181 0.421
-0.059 0.793
0.089 0.693
1 -
0.308 0.163
Consensus
Sig. 0.031 0.893
0.114 0.614
0.090 0.692
0.404 0.062
-0.022 0.923
0.068 0.764
0.328 0.136
0.190 0.396
0.008 0.972
0.052 0.818
-0.140 0.535
0.716** 0.000
0.379 0.082
0.432* 0.045
0.701** 0.000
0.308 0.163
1 -
* Correlation is significant at the 0.05 level (2-tailed). (n=22) ** Correlation is significant at the 0.01 level (2-tailed)
Table 6.89: Correlation between Perceived Effectiveness of Relationship and Relationship Indices (QDMR)
APPENDIX IV SURVEY RESULTS
251
Culture
Mean Median Standard Deviation Personal Time 1.90 2.00 0.57 Challenge 1.80 2.00 0.63 Stress 2.90 3.00 0.99 Physical Condition 2.60 3.00 0.70 Relationship with Superior 2.00 2.00 0.47 Employment Security 2.60 2.00 0.84 Freedom 1.90 2.00 0.57 Cooperation 1.90 2.00 0.57 Consult by Superior 2.10 2.00 0.74 Contribution to Company 1.70 2.00 0.68 High Earning 2.30 2.00 4.80 Serve the Country 3.10 3.00 0.88 Desirable Living Area 2.00 2.00 0.67 Opportunity for Advancement 2.20 2.00 0.79 Job Adventure 2.00 2.00 0.82 Successful Company 3.10 3.00 0.88 Help the Others 2.40 2.50 0.97 Job Definition 3.20 3.00 0.63
(n=10) * Concepts are measured on a scale of 1 to 5, with 1 indicating utmost importance and 5
indicating little to no importance on the criterion for an ideal job.
Table 6.90: Importance of Criteria for an Ideal Job (QDMR)
APPENDIX IV SURVEY RESULTS
252
t-value Standard Deviation
Null Hypothesis
Personal Time -0.250 0.516 0.810 Challenge 1.260 0.563 0.230 Stress -0.483 0.935 0.640 Physical Condition -0.619 0.834 0.550 Relationship with Superior -1.320 0.488 0.210 Employment Security -0.258 0.751 0.800 Freedom 2.070 0.561 0.057 Cooperation 0.327 0.592 0.750 Consult by Superior 0.174 0.743 0.860 Contribution to Company 1.520 0.594 0.150 High Earning -0.564 0.458 0.580 Serve the Country 1.430 0.767 0.170 Desirable Living Area 0.000 0.535 1.00 Opportunity for Advancement 0.367 0.704 0.720 Job Adventure 0.462 0.699 0.650 Successful Company -0.243 0.797 0.810 Help the Others 0.564 0.915 0.580 Job Definition -1.47 0.704 0.160
(n=10)
Table 6.91: Difference between the Means of QDPW and QDMR on the Importance of Criteria for an Ideal Job using t-test
Mean Median Standard Deviation
Organisation’s rule should not be broken under any circumstances 2.80 2.00 1.14 Trust 1.80 2.00 0.42 Dislike of work 3.90 4.00 0.32 More desirable to work in a large corporation 4.00 4.00 0.47
(n=10) * Concepts are measured on a scale of 1 to 5, with 1 indicating strongly agree with statement
and 5 strongly disagree.
Table 6.92: Level of Agreement on Statements (QDMR)
APPENDIX IV SURVEY RESULTS
253
Mean Median Standard Deviation
Personal relationship are important in managing project/contract 1.50 1.50 0.53 Formal procedures are necessary for the successful management of a project 1.70 2.00 0.48 Informal arrangements are necessary for the successful management of a project 2.50 2.00 1.08 Personal relationships amongst the project members are more important than those in your employer’s organisation 2.70 3.00 0.95 One must be willing to sacrifice personal relationships with members of the project team to ensure the successful completion of the project 3.90 4.00 0.74 One must be willing to sacrifice personal relationships with members of the project team to ensure their firm’s objectives are met 4.00 4.00 0.47 On must be willing to sacrifice personal relationships with members of the project team to ensure one’s personal objectives are met 4.20 4.00 0.42 One must be prepared to disregard formal procedures in order to ensure the successful completion of the project 3.40 4.00 1.08 One must be prepared to disregard formal procedures in order to ensure one’s firm’s objectives met 3.60 4.00 0.97 One must be prepared to disregard formal procedures in order to ensure one’s own objectives are met 3.70 4.00 0.95
(n=10) * Concepts are measured on a scale of 1 to 5, with 1 indicating strongly agree with the
statement and 5 strongly disagree.
Table 6.93: Agreement to Statements in Relation to Project Success or Achieving Objectives (QDMR)
APPENDIX IV SURVEY RESULTS
254
QDPW Survey Results
Organisational Assessment Reasons for Relationship
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Rel
atio
nshi
p V
alue
5
4
3
2
1
0
Other Units
Project Services
Figure 6.1: Reasons for Relationship – Work (QDPW & Other Units)
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Rel
atio
nshi
p V
alue
5
4
3
2
1
0
Other Units
Project Services
Figure 6.2: Reasons for Relationship – Resources (QDPW & Other Units)
QDPW
QDPW
APPENDIX IV SURVEY RESULTS
255
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Rel
atio
nshi
p V
alue
5
4
3
2
1
0
Other Units
Project Services
Figure 6.3: Reasons for Relationship - Technical Assistance (QDPW & Other Units)
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Rel
atio
nshi
p V
alue
5
4
3
2
1
0
Other Units
Project Services
Figure 6.4: Reasons for Relationship – Information (QDPW & Other Units)
Note: Relationship value received or sent between organisation units is measured on a scale of 1 to 5, with 1 indicating no relationship during the past six months and 5 indicating lots of interactions.
QDPW
QDPW
APPENDIX IV SURVEY RESULTS
256
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Re
latio
nsh
ip E
ffect
iven
ess
5
4
3
2
1
0
Other Units rate
Project Services
Project Services
rate Other Units
Figure 6.5: Effectiveness of Working Relationship (QDPW & Other Units)
Resource Dependence
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Dep
ende
nce
5
4
3
2
1
0
Other Units
Project Services
Figure 6.6: Other Units Resource Dependence on QDPW
QDPW
QDPW
QDPW
APPENDIX IV SURVEY RESULTS
257
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Dep
end
ence
5
4
3
2
1
0
Other Units
Project Services
Figure 6.7: QDPW Resource Dependence on Other Units
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Impo
rtan
ce
5
4
3
2
1
0
Other Units
Project Services
Figure 6.8: Resource Importance between Other Units and QDPW
QDPW
QDPW
APPENDIX IV SURVEY RESULTS
258
Awareness of Relationship
40%
15%5%
10%
25%
5%
>10
108
7
2
1
Figure 6.9: Length of Relationship between QDPW and Other Units
Project Services Informed Other Units
Very w ell informed
Quite informed
Somew hat informed
Little informed
Not at all
Fre
quen
cy
14
12
10
8
6
4
2
0
Figure 6.10: Goals Informed by QDPW to Other Units
QDPW informed Other Units
APPENDIX IV SURVEY RESULTS
259
Other Units Informed Project Services
Very w ell informed
Quite informed
Somew hat informed
Little informed
Fre
quen
cy
8
6
4
2
0
Figure 6.11: Goals Informed by Other Units to QDPW
Degree of Personal Acquaintance
Very w ell
Quite w ell
Somew hat w ell
Not very w ell
missing
Fre
que
ncy
10
8
6
4
2
0
Figure.6.12: Degree of Personal Acquaintance Rated by QDPW to Other Units
Other Units informed QDPW
APPENDIX IV SURVEY RESULTS
260
Degree of Personal Acquaintance
Very w ellQuite w ellSomew hat w ellNot very w ell
Fre
quen
cy
10
8
6
4
2
0
Figure 6.13: Degree of Personal Acquaintance Rated by Other Units to QDPW
Consensus/Conflict
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Goa
l Prio
rity
5
4
3
2
1
0
Other Units
Project Services
Figure 6.14: Agree on Goal Priorities (QDPW & Other Units)
QDPW
APPENDIX IV SURVEY RESULTS
261
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Way
s of
Wor
k/S
ervi
ces
Pro
vide
d
5
4
3
2
1
0
Other Units
Project Services
Figure 6.15: Agree on Ways of Work/Services Provides (QDPW & Other Units)
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Te
rms
of R
elat
ions
hip
5
4
3
2
1
0
Other Units
Project Services
Figure 6.16: Agree on Terms of Relationship (QDPW & Other Units)
QDPW
QDPW
APPENDIX IV SURVEY RESULTS
262
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Ext
ent
5
4
3
2
1
0
Other Units
Project Services
Figure 6.17: Hindered Performance by Other Parties (QDPW & Other Units)
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Fre
quen
cy
5
4
3
2
1
0
Other Units
Project Services
Figure 6.18: Frequency of Conflict (QDPW & Other Units)
QDPW
QDPW
APPENDIX IV SURVEY RESULTS
263
Methods of Conflict Resolution
5%
60%
35%
Seldom
Almost never
No dispute
Figure 6.19: Conflict Resolution - Avoiding Issues (QDPW)
5%
5%
55%
35%
About half the time
Seldom
Almost never
No dispute
Figure 6.20: Conflict Resolution - Smoothing over Issues (QDPW)
APPENDIX IV SURVEY RESULTS
264
60%
10%
30%
Almost alw ays
Often
No dispute
Figure 6.21: Conflict Resolution - Confronting Issues (QDPW)
5%
5%
40%
50%
Almost alw ays
Seldom
Almost never
No dispute
Figure 6.22: Conflict Resolution – Hierarchy (QDPW)
APPENDIX IV SURVEY RESULTS
265
Domain Similarity
35%
20%
10%
35%
Great extent
considerable extent
Some extent
To no extent
Figure 6.23: Domain Similarity on Funding Source (QDPW)
35%
20%
10%
35%
Great extent
considerable extent
Some extent
To no extent
Figure 6.24: Domain Similarity on Kind of Work (QDPW)
APPENDIX IV SURVEY RESULTS
266
20%
30% 30%
10%
5%
5%
Great extent
considerable extent Some extent
Little extent
To no extent
Don't know
Figure 6.25: Domain Similarity on Clients/Customers (QDPW)
20%
30% 30%
10%
5%
5%
Great extent
considerable extent Some extent
Little extent
To no extent
Don't know
Figure 6.26: Domain Similarity on Operating Goals (QDPW)
APPENDIX IV SURVEY RESULTS
267
10%
40%
20%
20%
5%
5%Great extent
considerable extent
Some extent
Little extent
To no extent
Don't know
Figure 6.27: Domain Similarity on Employee Skills (QDPW)
5%
45%
35%
5%
10%Great extent
considerable extent
Some extent
Little extent
Don't know
Figure 6.28: Domain Similarity on Technology (QDPW)
APPENDIX IV SURVEY RESULTS
268
Communications
25%
15%
45%
5%
10%
Many times daily
About daily
About w eekly
About every 2 w eeks
About monthly
Figure 6.29: Frequency of Written Reports (QDPW)
25%
15%
45%
5%
10%
Many times daily
About daily
About w eekly
About every 2 w eeks
About monthly
Figure 6.30: Frequency of Race-to-Face Talks (QDPW)
APPENDIX IV SURVEY RESULTS
269
15%
35%
30%
5%
15%
Many times daily
About daily
About w eekly
About every 2 w eeks
About monthly
Figure 6.31: Frequency of Telephone Calls (QDPW)
5%
10%
40%
30%
10%
5%
About daily
About w eekly
About every 2 w eeks
About monthly
1-2 times
Not once
Figure 6.32: Frequency of Group Meetings (QDPW)
APPENDIX IV SURVEY RESULTS
270
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Fre
que
ncy
6
6
5
5
4
4
3
3
2
2
1
1
0
Other Units
Project Services
Figure 6.33: Frequency of Contacts (QDPW & Other Units)
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Pe
rcen
t of T
ime
Spe
nt
100
80
60
40
20
0
Other Units
Project Services
Figure 6.34: Percent of Time Spent between QDPW and Other Units
QDPW
QDPW
APPENDIX IV SURVEY RESULTS
271
Percent of Contacts Initiated (%)
90807570605010
Fre
quen
cy
10
8
6
4
2
0
Figure 6.35: Percent of Contacts Initiated by QDPW
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Diff
icul
ty
5
4
3
2
1
0
Other Units
Project Services
Figure 6.36: Difficulty on Getting in Touch (QDPW & Other Units)
QDPW
APPENDIX IV SURVEY RESULTS
272
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Diff
icul
ty
5
4
3
2
1
0
Other Units
Project Services
Figure 6.37: Difficulty on Getting Ideas Across (QDPW & Other Units)
Resource Flows
Figure 6.38: Work Received from Other Units by QDPW
0%, 6%
1% - 10%, 38%
11% - 40%, 33%
41% - 70%, 6%
>70%, 17%
QDPW
APPENDIX IV SURVEY RESULTS
273
0%, 64%1% - 10%, 6%
11% - 40%, 18%
>70%, 12%
Figure 6.39: Money/Budget Received from Other Units by QDPW
0%, 38%
1% - 10%, 28%
11% - 40%, 11%
41% - 70%, 6%
>70%, 17%
Figure 6.40: Technical Assistance Received from Other Units by QDPW
APPENDIX IV SURVEY RESULTS
274
0%, 6%
1% - 10%, 29%
11% - 40%, 35%
41% - 70%, 12%
>70%, 18%
Figure 6.41: Work Received from QDPW to Other Units
0%, 40%
1% - 10%, 24%
11% - 40%, 12%
>70%, 24%
Figure 6.42: Money/Budget Received from QDPW to Other Units
APPENDIX IV SURVEY RESULTS
275
0%, 12%
1% - 10%, 35%
11% - 40%, 29%
41% - 70%, 6%
>70%, 18%
Figure 6.43: Technical Assistance Received from QDPW to Other Units
Variability of Resource Flows
25%
25%
30%
5%
15%Mostly different eac
About half the same
Mostly the same each
Almost all the same
missing
Figure 6.44: Resource Flows Same Each Time Transacted (QDPW)
APPENDIX IV SURVEY RESULTS
276
5%
35%
35%
10%
15%
About Weekly
About Monthly
1 or 2 Times
Not Once
missing
Figure 6.45: Resource Flow Problems Encountered(QDPW)
5%
35%
30%
15%
15%
Much Extent
Some Extent
Little Extent
To No Extent
missing
Figure 6.46: Resource Flow Interruptions (QDPW)
APPENDIX IV SURVEY RESULTS
277
Formalisation of Interunit Relationship
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Va
lue
5
4
3
2
1
0
Other Units
Project Services
Figure 6.47: Relation Explicitly Verbalised (QDPW & Other Units)
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Va
lue
5
4
3
2
1
0
Other Units
Project Services
Figure 6.48: Relation Written Down in Detail (QDPW & Other Units)
QDPW
QDPW
APPENDIX IV SURVEY RESULTS
278
20%
55%
10%
15%Great extent
Considerable extent
Some extent
missing
Figure 6.49: Standard Operation Procedures Established (QDPW)
50%
30%
5%
15%
Considerable extent
Some extent
Little extent
missing
Figure 6.50: Formal Channels Followed (QDPW)
APPENDIX IV SURVEY RESULTS
279
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Va
lue
5
4
3
2
1
0
Other Units
Project Services
Figure 6.51: Other Units' Operations Influenced by QDPW
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Va
lue
5
4
3
2
1
0
Other Units
Project Services
Figure 6.52: QDPW Changed Other Units' Goals/Services
QDPW
QDPW
APPENDIX IV SURVEY RESULTS
280
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Va
lue
5
4
3
2
1
0
Other Units
Project Services
Figure 6.53: QDPW's Operations Changed by Other Units
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Va
lue
5
4
3
2
1
0
Other Units
Project Services
Figure 6.54: Other Units Changed QDPW's Goals/Services
QDPW
QDPW
APPENDIX IV SURVEY RESULTS
281
Perceived Effectiveness of Relationship
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Ext
ent
5
4
3
2
1
0
Other Units
Project Services
Figure 6.55: Extent of Commitments Carried Out by Other Units (QDPW)
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Ext
ent
5
4
3
2
1
0
Other Units
Project Services
Figure 6.56: Extent of Commitments Carried Out by QDPW
QDPW
QDPW
APPENDIX IV SURVEY RESULTS
282
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Ext
ent
5
4
3
2
1
0
Other Units
Project Services
Figure 6.57: Productive Relationship (QDPW & Other Units)
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Ext
ent
5
4
3
2
1
0
Other Units
Project Services
Figure 6.58: Time and Effort (QDPW & Other Units)
QDPW
QDPW
APPENDIX IV SURVEY RESULTS
283
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Ext
ent
5
4
3
2
1
0
Other Units
Project Services
Figure 6.59: Relationship Satisfaction (QDPW & Other Units)
Case Number
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Ext
ent
5
4
3
2
1
0
Other Units
Project Services
Figure 6.60: Transaction Equality (QDPW & Other Units)
QDPW
QDPW
APPENDIX IV SURVEY RESULTS
284
QDMR Survey Results
Organisational Assessment
Reasons for Relationship
Case Number
21191715131197531
Rel
atio
nshi
p V
alue
5
4
3
2
1
0
Other Units
QDMR
Figure 6.61: Reasons for Relationship – Work (QDMR & Other Units)
Case Number
21191715131197531
Rel
atio
nshi
p V
alue
5
4
3
2
1
0
Other Units
QDMR
Figure 6.62: Reasons for Relationship – Resources (QDMR & Other Units)
APPENDIX IV SURVEY RESULTS
285
Case Number
21191715131197531
Rel
atio
nshi
p V
alue
5
4
3
2
1
0
Other Units
QDMR
Figure 6.63: Reasons for Relationship - Technical Assistance (QDMR & Other Units)
Case Number
21191715131197531
Rel
atio
nsh
ip V
alu
e
5
4
3
2
1
0
Other Units
QDMR
Figure 6.64: Reasons for Relationship – Information (QDMR & Other Units)
APPENDIX IV SURVEY RESULTS
286
Case Number
21191715131197531
Re
latio
nshi
p E
ffect
ive
ness
5
4
3
2
1
0
Other Units
rates QDMR
QDMR rates
Other Units
Figure 6.65: Effectiveness of Working Relationship (QDMR & Other Units)
Resource Dependence
Case Number
21191715131197531
Dep
end
ence
5
4
3
2
1
0
Other Units
QDMR
Figure 6.66: Other Units Resource Dependence on QDMR
APPENDIX IV SURVEY RESULTS
287
Case Number
21191715131197531
Dep
end
ence
5
4
3
2
1
0
Other Units
QDMR
Figure 6.67: QDMR Resource Dependence on Other Units
Case Number
21191715131197531
Impo
rta
nce
5
4
3
2
1
0
Other Units
QMDR
Figure 6.68: Resource Importance between QDMR and Other Units
APPENDIX IV SURVEY RESULTS
288
Awareness of Relationship
9%
36%
45%
9%
21 or more
11 - 20
6 - 10
1 - 5
Figure 6.69: Length of Relationship between QDMR and Other Units
QDMR Informed Other Units
Very w ell informed
Quite informed
Somew hat informed
Little informed
Fre
que
ncy
14
12
10
8
6
4
2
0
Figure 6.70: Goals Informed by QDMR to Other Units
APPENDIX IV SURVEY RESULTS
289
Other Units Informed QDMR
Very w ell informed
Quite informed
Somew hat informed
Little informed
Fre
que
ncy
12
10
8
6
4
2
0
Figure 6.71: Goals Informed by Other Units to QDMR
Degree of Personal Acquaintance
Very w ell
Quite w ell
Somew hat w ell
Not very w ell
No personal acquaint
Fre
que
ncy
10
8
6
4
2
0
Figure 6.72: Degree of Personal Acquaintance Rated by QDMR to Other Units
Degree of Personal Acquaintance
Very w ellQuite w ellSomew hat w ell
Fre
que
ncy
10
8
6
4
2
0
Figure 6.73: Degree of Personal Acquaintance Rated by Other Units to QDMR
APPENDIX IV SURVEY RESULTS
290
Consensus/Conflict
Case Number
21191715131197531
Goa
l Prio
rity
5
4
3
2
1
0
Other Units
QDMR
Figure 6.74: Agree on Goal Priorities (QDMR & Other Units)
Case Number
21191715131197531
Way
s o
f Wor
k/S
ervi
ce P
rovi
de
5
4
3
2
1
0
Other Units
QDMR
Figure 6.75: Agree on Way of Work/Services Provides (QDMR & Other Units)
APPENDIX IV SURVEY RESULTS
291
Case Number
21191715131197531
Ter
ms
of R
ela
tion
ship
5
4
3
2
1
0
Other Units
QDMR
Figure 6.76: Agree on Terms of Relationship (QDMR & Other Units)
Case Number
21191715131197531
Ext
ent
5
4
3
2
1
0
Other Units
QDMR
Figure 6.77: Hindered Performance by Other Parties (QDMR & Other Units)
Case Number
21191715131197531
Fre
que
ncy
5
4
3
2
1
0
Other Units
QDMR
Figure 6.78: Frequency of Conflict (QDMR & Other Units)
APPENDIX IV SURVEY RESULTS
292
Methods of Conflict Resolution
9%
9%
82%
About half the time
Seldom
Almost never
Figure 6.79: Conflict Resolution - Avoiding Issues (QDMR)
5%
14%
27%
55%
Often
About half the time
Seldom
Almost never
Figure 6.80: Conflict Resolution - Smoothing over Issues (QDMR)
APPENDIX IV SURVEY RESULTS
293
5%
55%
32%
5%
5%Almost alw ays
Often
About half the time
Seldom
Almost never
Figure 6.81: Conflict Resolution - Confronting Issues (QDMR)
5%
23%
36%
36%
Often
About half the time
Seldom
Almost never
Figure 6.82: Conflict Resolution – Hierarchy (QDMR)
APPENDIX IV SURVEY RESULTS
294
Domain Similarity
73%
5%
5%
5%
14%
Great extent
Considerable extent
Some extent
Little extent
To no extent
Figure 6.83: Domain Similarity on Funding Source (QDMR)
5%
5%
18%
32%
41%
Great extent
Considerable extent
Some extent
Little extent
To no extent
Figure 6.84 Domain Similarity on Kind of Work (QDMR)
APPENDIX IV SURVEY RESULTS
295
9%
36%
32%
14%
9%
Great extent
Considerable extent
Some extent
Little extent
To no extent
Figure 6.85 Domain Similarity on Client/Customers (QDMR)
14%
32%
41%
14%
Great extent
Considerable extent
Some extent
Little extent
Figure 6.86 Domain Similarity on Operating Goals (QDMR)
APPENDIX IV SURVEY RESULTS
296
23%
27%
41%
9%
Great extent
Considerable extent
Some extent
To no extent
Figure 6.87 Domain Similarity on Employee Skills (QDMR)
14%
45%
36%
5%
Great extent
Considerable extent
Some extent
Little extent
Figure 6.88 Domain Similarity on Technology (QDMR)
APPENDIX IV SURVEY RESULTS
297
Communication
9%36%
32%
18%
5%
Many times dailyAbout daily
About every 2 w eeks
About monthly
1-2 times
Figure 6.89: Frequency of Written Reports (QDMR)
27%
23%
23%
9%
14%5%
Many times daily
About daily
About w eekly
About every 2 w eeks
About monthly1-2 times
Figure 6.90: Frequency of Face-to-Face Talks (QDMR)
APPENDIX IV SURVEY RESULTS
298
18%
36%23%
14%
9%Many times daily
About dailyAbout w eekly
About every 2 w eeks
About monthly
Figure 6.91: Frequency of Telephone Calls (QDMR)
27%
23%
32%
9%9%
About w eekly
About every 2 w eeks
About monthly
1-2 timesNot once
Figure 6.92: Frequency of Group Meetings (QDMR)
APPENDIX IV SURVEY RESULTS
299
Case Number
21191715131197531
Fre
que
ncy
6
5
4
3
2
1
0
Other Units
QDMR
Figure 6.93: Frequency of Contact between QDMR and Other Units
Case Number
21191715131197531
Per
cen
t of T
ime
Spe
nt
100
80
60
40
20
0
Other Units
QDMR
Figure 6.94: Percent of Time Spent between QDMR and Other Units
Percent of Contact Initiated (%)
807570605040
Fre
que
ncy
14
12
10
8
6
4
2
0
Figure 6.95: Percent of Contact Initiated by QDMR
APPENDIX IV SURVEY RESULTS
300
Case Number
21191715131197531
Diff
icul
ty
5
4
3
2
1
0
Other Units
QDMR
Figure 6.96: Difficulty on Getting in Touch (QDMR & Other Units)
Case Number
21191715131197531
Diff
icul
ity
5
4
3
2
1
0
Other Units
QDMR
Figure 6.97: Difficulty on Getting Ideas Across (QDMR & Other Units)
APPENDIX IV SURVEY RESULTS
301
Resource Flows
14%
5%
23%
36%
23%
>80%,
51% - 70%,
11% - 50%,
1% - 10%,
0%,
Figure 6.98: Work Received from Other Units by QDMR
5%
95%
>80%,
0%,
Figure 6.99: Money/Budget Received from Other Units by QDMR
APPENDIX IV SURVEY RESULTS
302
5%
9%
14%
55%
18%>80%,
51% - 70%,
11% - 50%,
1% - 10%,
0%,
Figure 6.100: Technical Assistance Received from Other Units by QDMR
9%
5%
36%
50%
51% - 70%,
11% - 50%,
1% - 10%,
0%,
Figure 6.101: Work Received from QDMR to Other Units
APPENDIX IV SURVEY RESULTS
303
9%
23%
68%
11% - 50%,
1% - 10%,
0%,
Figure 6.102: Money/Budget Received from QDMR to Other Units
5%23%
45%
27%
51% - 70%,11% - 50%,
1% - 10%,
0%,
Figure 6.103: Technical Assistance Received from QDMR to Other Units
APPENDIX IV SURVEY RESULTS
304
Variability of Resources Flows
18%18%
23%
14%
23%
5%
Almost all differentMostly different eac
About half the same
Mostly the same each
Almost all the same
missing
Figure 6.104: Resource Flows Same Each Time Transacted (QDMR)
18%
27%
41%
14%Aout Weekly
About Monthly1 or 2 Times
Not Once
Figure 6.105: Resource Flow Problems Encountered (QDMR)
APPENDIX IV SURVEY RESULTS
305
9%
27%
27%
32%
5%
Much Extent
Some Extent
Little Extent
To No Extent
missing
Figure 6.106: Resource Flow Interruptions (QDMR)
Formalisation of Interunit Relationship
Case Number
21191715131197531
Val
ue
5
4
3
2
1
0
Other Units
QDMR
Figure 6.107: Relation Explicitly Verbalised (QDMR & Other Units)
APPENDIX IV SURVEY RESULTS
306
Case Number
21191715131197531
Val
ue
5
4
3
2
1
0
Other Units
QDMR
Figure 6.108: Relation Written Down in Detail (QDMR & Other Units)
9%
55%
27%
9%
Great extent
Considerable extent
Some extent
To no extent
Figure 6.109: Standard Operation Procedures Established (QDMR)
APPENDIX IV SURVEY RESULTS
307
9%
36%
41%
14%
Great extent
Considerable extent
Some extent
Little extent
Figure 6.110: Formal Channels Followed (QDMR)
Interunit Influence
Case Number
21191715131197531
Val
ue
5
4
3
2
1
0
Other Units
QDMR
Figure 6.111: Other Units' Operations Influenced by QDMR
APPENDIX IV SURVEY RESULTS
308
Case Number
21191715131197531
Val
ue
5
4
3
2
1
0
Other Units
QDMR
Figure 6.112: QDMR Changed Other Units' Goals/Services
Case Number
21191715131197531
Val
ue
5
4
3
2
1
0
Other Units
QDMR
Figure 6.113: QDMR's Operations Influenced by Other Units
Case Number
21191715131197531
Val
ue
5
4
3
2
1
0
Other Units
QDMR
Figure 6.114: Other Units Changed QDMR's Goals/Services
APPENDIX IV SURVEY RESULTS
309
Perceived Effectiveness of Relationship
Case Number
21191715131197531
Ext
ent
5
4
3
2
1
0
Other Units
QDMR
Figure 6.115: Extent of Commitments Carried out by Other Units
Case Number
21191715131197531
Ext
ent
5
4
3
2
1
0
Other Units
QDMR
Figure 6.116: Extent of Commitments Carried out by QDMR
APPENDIX IV SURVEY RESULTS
310
Case Number
21191715131197531
Ext
ent
5
4
3
2
1
0
Other Units
QDMR
Figure 6.117: Productive Relationship (QDMR & Other Units)
Case Number
21191715131197531
Ext
ent
5
4
3
2
1
0
Other Units
QDMR
Figure 6.118: Time and Effort (QDMR & Other Units)
Case Number
21191715131197531
Ext
ent
5
4
3
2
1
0
Other Units
QDMR
Figure 6.119: Relationship Satisfaction (QDMR & Other Units)
APPENDIX IV SURVEY RESULTS
311
Case Number
21191715131197531
Ext
ent
5
4
3
2
1
0
Other Units
QDMR
Figure 6.120: Transaction Equality (QDMR & Other Units)
APPENDIX V CASE STUDIES
313
Case Study 1 Bruce Highway 1, Brisbane
Client: Queensland Department of Main Roads
Contractor: National Organisation
Contract Strategy AS 2124 with Extended Partnering
Tender Price AU$25M
Final Project Cost AU$40M
Project Background Case Study 1 is a 6 lanes upgrade project of the Bruce Higway between Gateway Motorway and Dohles Rocks Road. The project was to widen the highway section from 4 lanes to 6 lanes, with the existing flow of traffic maintained. The major issues were the complicated staging and the construction sequencing. Traffic needed to be switched from side to side due to lane closure during construction. The contract was awarded based on the lowest bid wins mechanism. Although the contractor was awarded the contract, the tender price for the project was seriously underbid, which led to a chain of problems including 15 months of on-going claims between the Client and the Contractor, on top of the actual construction period. Extended-Partnering was applied on top of the contract. It is a QDMR departmental policy for all projects with project cost above AU$5M to adopt Extended-Partnering. A one-day workshop was run by an external partnering facilitator, and was attended by all project team members. A follow-up partnering meeting was carried out within the first three months of the project. Attendees of the one-day Partnering workshop are listed in Table CS1.1.
Client Contractor
• Principal • Superintendent • Superintendent
Representative • Two Inspectors
• Project Manager • Three Project Engineers • Environmental Engineer • Two Supervisors • Two Foremen
Table CS1.1 Attendees of the Initial One-Day Partnering Workshop
APPENDIX V CASE STUDIES
314
One of the major items on the workshop agenda was discussions between project team members to produce a mission statement and charter objectives (see Table CS1.2) However, the project manager in this case drafted the charter objectives for his staff and was unwilling for any further discussion with the rest of the project team. There were disagreements on the list of objectives the project manager drafted. The opinion on financial issues should not be brought in and assessed as one of the partnering components was raised.
Table CS1.2 Charter Objectives of QDMR Case Study 1
An interviewee commented that communication in the project team was insufficient; problems or ideas were not brought out by the Contractor and would communicate mainly through letters. There was no informal communication or initial communication before receiving the letter from the Contractor, with references to various clauses in the contract. Eventually, the project team only communicated to each other via formal letters and a lot of time was spent on studying the contract and referencing relevant clauses in order to protect self interests, rather than working cooperatively and working towards project objectives. Yet, the objectives for this project might be different between project team members at the beginning of the project, and throughout the whole project. Due to the serious underbid of the contract; the Contractor’s major objective might be to increase the project income through claims in order to reduce the amount of loss. Yet the Client’s aim was to ensure both time and quality are met in the project. However, the Contractor’s behaviour impelled the project team relationship to turn sour; project team members were forced to work for one’s self interest. One particular incident in the project was one of the foremen
Charter Objectives
• A safe project for the workforce, the environment and the travelling public
• Quality achieved first time • No unplanned traffic disruptions • Proactive management of community issues • Expand skills and capabilities of project staff and workforce • Fair commercial dealings • Create flexibility and innovation through energy and teamwork • A cooperative work environment based on honesty, trust and
mutual respect • Timely resolution of issues through effective communication • Progress ahead of program • An enjoyable place to work
APPENDIX V CASE STUDIES
315
refused to communicate with any members in the project team for 3 months after an argument broke out. Another major problem in this project was high turnover of Contractor staff, which is also one of the major but common issues in the construction industry. Only 2 Contractor’s staff were involved throughout the whole project. The Project Manager left at the early stage of the project and returned to the project at the very end when the project (including relationship in project team) has turned sour. During the ‘Project Manager free period’, the Project Engineer became the acting Project Manager because he had the best knowledge of the project history and process, although he did not fulfil all the criterions of taking up the Project Manager position. Unfortunately, the Project Engineer also left the project before it finished. Usually, a post-construction partnering assessment would be carried out by the project team upon project completion. Due to the lack of original staff from the contractor side, the post-construction partnering assessment was thence not carried out in this project. Partnering assessments were carried out on a monthly basis, each individual scored against each charter objectives and a partnering summary report with a graph based on the scores was produced monthly. The partnering report showed the average score on partnering assessment has been declining since the project began, meaning the charter objectives were not met and the relationship in project team was turning bad. The same partnering facilitator was contacted by the Client after reviewing the problems encountered in the project team and the partnering assessment report in the 7th partnering meeting (project had been running for seven months). The partnering facilitator was then invited for a partnering workshop with the project team. The Client party found the workshop beneficial and helped the project team to focus on the project objectives again. An overall summary and an action plan were produced after the meeting. The partnering assessment for period 8 showed the average score has improved by nearly one point (the point scale is 1-7) since the last period. Unfortunately, the relationship of the project team did not improve and was not maintained for the remaining project period. There were lots of contractual disputes in this project since the project began; disputes were not resolved until 15 months later after the project construction was completed.
Lessons Learnt Relationship contracting was not successful in this project. Project team atmosphere and project process were greatly affected by the parent company policy and culture. Because of the parent organisation
APPENDIX V CASE STUDIES
316
influences on the project team, there was a high turnover of Contractor staff in the project. Relationship in the project team did not start off well at the beginning of the project. Project objectives were not developed in a team manner, which consequently lead to a lack of common goals between all parties – the major criterion in relationship contracting. Instead of an open and frank communication, it was a close system communication in the project team. The tender selection was purely based on price – the lowest bid win. In this case, the contract was underbid which resulted in insufficient money in the contract since the beginning. There was not a right mix of project team members. Some team members were uncooperative and there was a lack of collaboration. Although a subsequent workshop was held during the project construction with an external partnering facilitator involved, problems in the team were deeply rooted and the relationship continued to turn sour.
APPENDIX V CASE STUDIES
317
Case Study 2 Bruce Highway 2, Brisbane
Client: Queensland Department of Main Roads
Contractor: Regional Contractor (Bielby Holdings)
Contract Strategy: AS 2124 with Extended Partnering
Tender Price: AU$30M
Final Project Cost: AU$43M (as at July 2004 due to project resumption)
Project Background Case Study 2 is a highway upgrade project. The project was awarded to the Contractor based on the lowest bid wins system. The type of contract used was AS2124 with Extended-Partnering. A designer team is brought into the project due to the lack of in-house expertise in QDMR. A one-day Relationship Management Review Workshop was taken place at the beginning of the project. Key project participants from the Client, Contractor and Subcontractor were invited to attend. Attendees of the one-day workshop are listed in Table CS2.1.
Client Contractor Subcontractor
• Principal • Superintendent • Superintendent
Representative • 3 Inspectors
• Project Manager • Project Engineer • Senior Foreman
• Project Manager • Supervisor • CQR
Table CS2.1 Attendees of the One-Day Initial Workshop
When the workshop date was set by the Client, the Contractor was asked to nominate anyone he/she thinks would be crucial for the project. In this case, 3 members from a major Subcontractor were invited because large amount of asphalt was needed in the project. The quantity and quality of asphalt and on time delivery were crucial for the project. An outline of the partnering process is presented in Figure CS2.1.
APPENDIX V CASE STUDIES
318
Figure CS2.1 Structure of Partnering Process
Attendees of the Relationship Management workshop would also attend the Review and Evaluation meetings (also known as partnering meetings) which were held monthly. Each project team members would score against each charter objective on a performance assessment sheet which would be collected for data assessment prior to each partnering assessment meeting. A sample of the partnering assessment summary is shown in Figure CS2.2.
1st (foundation) workshop to be held at the very beginning of the project
2nd (follow-up) workshop to be held after three months when the project has commenced
Monthly Review and Evaluation Meeting to be carried out by the project team
Post-Construction Partnering Review at the end of the project
Additional Partnering Workshop if necessary
APPENDIX V CASE STUDIES
319
Figure CS2.2 Sample of Partnering Assessment Summary Filled by Individuals
APPENDIX V CASE STUDIES
320
Charter Objectives
• A safe project • Maintain good working relationships • High level of honesty and openness in dealings • Speedy identification and resolution of all issues • Manage impact on traffic • Effective planning of all parties • Construct a quality project • Timeliness of project completion • A cost-efficient project • Gains positive industry recognition • Minimal impact on environment
Table CS2.2 Charter Objectives of QDMR Case Study 2
All problems or comments received were discussed in each monthly partnering meeting. The charter objectives (see Table CS2.2) were the principle objectives stated on the scoring sheet for performance assessment. It was pointed out that scores given to two consecutive periods by the same person could be very different. For example, a score of 2 was given for item 1 in period 8. Issues were raised in the partnering meeting and discussed. For the following period, a score of 6 would be given for the same item. Open communication in the project team was found very important. Not only it affected the work relationship, it also affected the effectiveness of problem solving. Relationships between project team members were constantly maintained at a good level; communication between the project participants had been opened since the project began. A typical example was the Contractor would talk openly and raise concerns when any problems or risks were foreseen. Informal communication channels such as telephone conversations, face-to-face talks, emails and faxes were also taken place in this project. Written correspondents were still used on specific issues for documentations; issues were often discussed on the telephone or in face-to-face meetings. This attitude was best expressed using the following quote from an interviewee, “if the issue can be talked through in a few minutes, why spending two hours writing a two pages letter?” A resolution matrix, presented in Table CS2.3 below, was developed in the initial workshop. Also, issues which might affect the project progress were made apparent and flagged. Project team realised those issues must be dealt with speedily in order to avoid any project delays and costs, as well as affecting the relationships between parties adversely.
APPENDIX V CASE STUDIES
321
LEVEL CLIENT CONTRACTOR TIME
1. Foreman
Inspector
C1 C2 C3
c1 c2
3 hours
2. Superintendents’ Representative
Site Engineer
C4 C5
c3 c4
2 days
3. Project Manager
Superintendent
C6 c4 5 days
4. Principals’ Delegates
Contractors Representative
C7 c4 10 days
Ground Rules 1. Resolve issues at the lowest level 2. Unresolved issues to be escalated upwards by both/all members
prior to causing project delays or costs. 3. No jumping levels of authority 4. Ignoring the issue or “no decision” is unacceptable. 5. Time frame may be extended by mutual agreement at any level, for
data gathering. 6. Change to personnel can be notified at site meetings.
Table CS2.3 Resolution Matrix
The ground rules were strictly followed by the project team. Any unresolved issues were escalated upwards by both parties within a set timeframe in order to minimise project delays or costs. All issues were able to be resolved at level 2 or below. The work relationship between both parties was maintained at a good level throughout the project. Also, the Contractor had an incentive of early completion, though there was no bonus or financial reward for early completion in this project. One reason suggested was early project completion would help the Contractor’s cash flow and would also allow his team to move onto another project. This project was finished early and within budget.
Lessons Learnt Relationship management was very successful in this project. Relationship in the project team started off well since the project began. Although this project was awarded base on price and the lowest bid win, the contract was not underbid i.e. there was money in the contract. Also,
APPENDIX V CASE STUDIES
322
strong commitment from both Client and Contractor at senior management level was received throughout the project. Philosophy of relationship management was understood and adopted at all levels. There were lots of open and informal communications between project team members. Partnering meetings were carried out in a very relax atmosphere and were finished within half an hour in most cases. All parties worked towards the same goal and objectives in the project were strictly followed. The project charter objectives were set with all parties’ consent. Unlike many construction projects, there were only two staff turnovers during the whole project period. The major Subcontractor was brought into the partnering meetings by the Contractor. Certain project issues, asphalt in this case, were able to be discussed and solved with the Subcontractor’s expertise. Both foreman and site inspector from the operation level also attended all partnering meetings, once again reinforcing the level of commitment from both parties on relational contracting. There were not many major disagreements between project parties and when such situations arose and when arguments had reached a certain level, the senior management (Project Manager and Superintendent and the Principal) would take the issues away from the partnering meetings. Separate meetings were held amongst the senior management members for further discussions. One of the aims of partnering meetings was to make all levels award of all project issues without affecting the work progressing at the operation level.
APPENDIX V CASE STUDIES
323
Case Study 3 Gatton Bypass, Toowoomba
Client: Queensland Department of Main Roads
Contractor: Package 1&3:Bielby Holdings Package 2: 2 local contractors +
QDMR commercial arm
Contract Strategies: Package 1: Design and Management Contract with Extended-Partnering
Package 2: AS 2124 with Extended-Partnering
Package 3: AS 2124 with Extended-Partnering
Project Background The existing Gatton Bypass, on the Warrego Highway between Ipswich and Toowoomba, was opened to traffic in 1989. The 21km bypass forms part of the Brisbane – Darwin corridor of the National Highway. The section of highway between Brisbane and Toowoomba was the only section which did not have four lanes but two. Case Study 3 is therefore a duplication project of the Gatton Bypass to 4 lanes. Gatton Bypass duplication was carried out in 3 packages, with separate tenders issued for each package. The main reason for the project to be broken down into 3 separate packages was space limitation on site. Extended partnering was applied on all 3 packages because it is the QDMR policy for any project with a project value above $5M to have partnering applied on top of the project.
Figure CS3.1 Outline of QDMR Case Study 3
Package 3 Package 2 Package 1
5 km 5 km 10 km
Brisbane Toowoomba
APPENDIX V CASE STUDIES
324
Package 2 was the first contract for tender and tender documents were issued in December 2001. The intention was allow work on the middle section to be finished as early as possible for the connection of package 1 and 3. Both package 1 and 3 went out for tender at the same time in early 2002. An outline of the project background is presented in Table CS3.1.
Project Background Package 2 was tendered twice during construction. Both contractors went bankrupted during construction and QDMR took over at the last stage and completed the work. QDMR employed most of the on-site staff. It was commented that the relationship on-site remained satisfactory, despite the previous 2 contractors went broke.
Package 1 Package 2 Package 3
Tender Issued
Early 2002 December 2001 Early 2002
Type of Contract
Design and Management Contract (intended for innovation and fast tracking the project)
AS 2124 with partnering on top
AS 2124 with partnering on top
Tender Sum
11M 9.5M 8.9M
Complexity
Complicated – connection with existing highway and roundabouts
Straight forward Straight forward
Contractor
Bielby Holdings (brought in subcontractor for the bridge)
Stockport Northern Queensland (Jun 2002) Globle (Apr-May 2003) QDMR to finish the project
Bielby Holdings (brought in subcontractor for the bridge)
Table CS3.1 Project Background of QDMR Case Study 3
APPENDIX V CASE STUDIES
325
Although it was aimed to complete the work in package 2 first, package 2 turned out to be completed last mainly due to the said incidents. Yet, the duplication project was completed in November 2003, one month ahead of schedule. Budget: AU$46M
AU$44M (current – with package 4 undergoing on up-grading the original 2 lanes by Roadtek)
QDMR role: Provide own team of administration Superintendent, Engineer, Inspector The principle has a strong view on relationship contract
Superintendent, Superintendent Representative and Inspector went directly into Partnering
Relationship Management (Extended-Partnering) Proce dures • 3 partnering workshops were held which ran separately for all 3
packages • The first partnering workshop for all 3 packages was held as a one-
day workshop (QDMR intended to run a 1.5 day workshop but Contractors refused)
• Monthly partnering meeting was held for all packages • Relationship assessment remained satisfactory for all 3 packages • QDMR was responsible for the cost of partnering facilitator and the
cost for running partnering workshops. Contractors were responsible to provide staff for workshops and meetings.
• The role of chairman was rotated. A different person was asked to take up the chairman role in all partnering meetings. Such arrangement was initiated by the project team.
Partnering Philosophy • There is no change on contract terms (i.e. no financial element) • It is a communication tool (share experience talk) • Matrix system must be set up for dispute/problem resolution
QDMR commented there is no change from traditional roles. The Principal (Client) did not involve very much during the partnering process, but more like an observer.
Comments and Suggestions by Project Participants Comments from Contractors:
• Partnering is useful. It is a way of getting the communication going. • The downside of partnering is the lack of financial aspect/contract
significant.
APPENDIX V CASE STUDIES
326
General Comments from project participants:
• There was only one partnering workshop – It is not enough. • Partnering facilitator was only involved in the first day workshop,
and therefore there was limited benefit for the team relationship – Partnering is like an adjunct for the project at the moment
Suggestions:
• Insert financial aspect – pay/gain mechanism (increase the incentive from Contractor on raising problems, innovations, win-win situation for all)
• Suggestion for financial incentive mechanism e.g. bonus sharing (cost reimbursable)
• Partnering facilitator should be involved in monthly meetings (might get more value from it)
Lessons Learnt Contracts of packages 1 & 3 happened to be awarded to the same contractor. Good relationship between project parties (packages 1 & 3) was established on the first day. There was continuous and open communication in the project team. Strong commitment and involvements were received from both parties’ top management throughout the project. Major Subcontractor was brought into partnering meetings by Contractor. There was little turnover of staff in both packages and the same team of people worked through both packages. There was a right mix of people in the project team since the project began. Package 2 was tendered twice and both Contractors went bankrupted. The major reason for both bankruptcies was both times the contract was seriously underbid – there was not enough money in the contract. Both Contractors tried to recover loss during the whole project period, and there was no goal alignment since the project began. One of the major philosophies of relationship management is working towards the same goal and project team members in package 2 has gone to the completely different direction. There was a high turnover of staff (Contractor and Client staff). Although senior management levels tried minimising distress upon the operation level through strong involvements, the project progress and project team spirit were damaged. The value of partnering facilitator was flagged and general comments on more facilitation carried out by the facilitator would benefit the project team more.
APPENDIX V CASE STUDIES
327
Case Study 4 Royal Brisbane Hospital (East Block), Brisbane
Client: Queensland Health
Client’s Representative Queensland Department of Public Works
Contractor: National Organisation
Contract Strategy Traditional Lump Sum AS 2124 with Bonus
Tender Price Approx. AU$60M
Final Project Cost AU$60M
Project Background Queensland Health engaged with QDPW for the hospital redevelopments. The redevelopment of Royal Brisbane and Royal Women’s Hospital was divided into 5 phases. One major reason for breaking the redevelopment project into 5 phases is because quality health services were needed to be provided continuously during the redevelopment process, and site constrains issues. Phase 1C at East block formed the second major construction component of the hospital complex. The building houses significant elements of the Royal Brisbane Hospital. East Block (now knows as the Dr. James Mayne Building), Phase 1C was the construction of the second major component of the hospital complex. The building houses significant elements of the Royal Brisbane Hospital including the new Emergency Services, Intensive Care, Burns Unit and other clinical care services. The East Block redevelopment contract was awarded to the contractor in February 2001, with completion achieved in August 2002. The total project cost for East Block was AU$60M. The chosen project delivery system was Traditional Lump Sum AS2124 with variations, where relationship components were applied in the contract. Financial incentive was engaged in this project where Contractor would receive a bonus upon early completion, AU$35k per week, and AU$200k being the maximum amount of bonus. Another variation was Client’s Representative provided consultants for the project. Any missing documents or claims would go through Superintendent Representative; and all claims and variations needed to be approved by the client before taken places.
APPENDIX V CASE STUDIES
328
Partnering Arrangement Upon the appointment of Contractor, a partnering workshop was held at the beginning of the project. Stakeholders from all parties were invited to attend the partnering workshop. Project participants found the workshop worthwhile. It allowed open communication with problems placed on the table. Decisions were made in a much more direct way, costing less time and money when compare with projects using traditional contracting approach. Good relationship in the project team was established on the first day and was sustained. Monthly partnering meetings were held with the partnering group at senior management level. Each project participant would score against 12-15 items in relation to satisfactory level on work progress, team member relationships etc. on a partnering assessment sheet. All sheets would bee collected for data assessment prior to each monthly meeting, where scores and relationship issues were discussed. The decision matrix of an Escalation Tree was adopted in this project. Escalation Tree is a ‘risk transfer’ method. When problems could not be solved at the site level (or lower level) within a certain amount of time, they were transferred to the higher management level and so on. Escalation Tree prevents problems from grounded on site, minimising disturb on project progress. The project team could concentrate on work and the site relationship remained good all the way throughout the project.
One major risk Client’s Representative foreseen in the project was a miscalculation of AU$1.5M in the project cost by the Contractor. The common practice in the industry is the Contractor would try to make unreasonable and excess claims during work or to minimise cost by using second stream of subcontractors and lower quality tradesmen. In order to avoid poor quality of work due to workmanship, the Client’s Representative required an increase of site supervision by the Contractor. The Clerk of Work also picked up many quality issues on site, which helped to maintain a high standard of quality. The project was found successful and there were no excess claims by the Contractor. One reason suggested was the Contractor recognised the benefits of relationship contracting and wanted to establish a good relationship with for future job opportunities.
Lessons Learnt In order to establish a successful partnering relationship, it is important to have sufficient amount of money in the contract i.e. contract is not underbid and there is money to run partnering workshops and meetings. Also, there needs to be a good start on the relationship in project team or pressure would be put onto the relationship between parties. It is also necessary to bear in mind that ‘one can ruin all’. A good project team relationship can be ruined by one person. Getting the whole team to work
APPENDIX V CASE STUDIES
329
together is very important. It is therefore crucial to choose the right mix of team members before pursuing the contract as well as building a good relationship on the first day. After building a good relationship in the project team, maintain the relationship is equally important. One comment obstacle of maintaining a good project team relationship identified in this case study is team members were often pressured from their home offices as well as from work on site. Although the project cost was miscalculated by the Contractor, the Contractor did not try to recover loss through unreasonable claims. Relational contracting was treated with the right attitude by all parties and they all worked towards the same goal.
APPENDIX V CASE STUDIES
330
Case Study 5 Tasmanian Prisons Infrastructure Redevelopment Prog ram – Risdon Prison Project
Client: Department of Justice and Industrial Relations in Tasmania (DoJIR)
Client’s Representative: Queensland Department of Public Works
Contract Strategies: Managing Contractor
Project Background DoJIR engaged with QDPW to assist them the procurement of the Risdon Prison redevelopment project. The role of QDPW was to provide advices on contract administration (and master plan) before the contract was granted to any contractor. The type of contract DoJIR chose to use for this project is Managing Contractor. The chosen strategy involves engaging consultants, developing a schematic design, engaging a Managing Contract (MC) and novating the consultants to the MC. The project was only at its tender selection while this case study was being written. An initial workshop was held with the project team (participants from client, clien’ts representative, consultant and managing contractor organisations), with the concept of relational contracting introduced and the project objectives were developed.
Managing Contractor’s Responsibilities The MC will complete design development, documentation, contract letting, construction and handover phases. Because the project funding is spread over approximately 5 years, the MC will be required to finance the project in part until subsequent funding is made available. The MC’s responsibilities may be extended if the Client chooses the MC to deliver maintenance services for the redeveloped prison for 15 years.
APPENDIX V CASE STUDIES
331
Tender Process
Figure CS5.1 Tender Evaluation Process for Managing Contractor
Tenders received
Interview with each tenderer
Desktop review of tenders by Tender Evaluation panel
Moderation meeting
Calculate overall score for Stage 1
(preferably only two tenders proceed to
Stage 2)
1
2
3
4
5
STEP
Selection Workshop (facilitated outcomes)
Moderation meeting & selection of preferred
tender
Successful Tenderer appointed
6
7
8
Unsuccessful Tender(s)
Unsuccessful Tender(s)
STAGE 1
STAGE 2
APPENDIX V CASE STUDIES
332
Figure CS5.1 presents an outline of the tender evaluation process used in this case study. Two tenders were short listed after stage 1 in the tender evaluation process. A full day workshop was held with two short-listed companies individually. The workshop focused on capturing greater understanding of the contractor’s capability of delivering the desired outcomes in a collaborative environment, which was one of the most important considering criteria. The workshops helped both the client and the client’s consultant to explore tenderers’ responses on relationship contracting. A start-up workshop would be held after the Manager Contractor is selected. The Selection Workshop was facilitated by the Client’s Representative. The workshop objectives were to provide an opportunity for potential team members to meet and assess their capacity for work cooperation, as well as allowing the team members to have a greater understanding of the project. The workshop was divided into 2 sessions. The first session was structured using a number of questions relating to relationship contracting in individuals. Questions were discussed in sub-groups and outcomes were collected from all groups to develop a whole group list. The second session focused on 4 case studies that required participants to develop strategies under hypothetical problem situations. Attendees were divided into 3 sub-groups, where each group was a mix between 3 bodies: at least one member from the tender assessment panel, consultants and members of the Contractor team. The proposed MC representative in each group was asked to led the discussion. A meeting was held after each workshop between the tender assessment panel and the consultant and feedback was provided to the Tender Assessment Committee. All attendees of the workshop agreed the workshop objectives were achieved and materials produced during workshop might be of assistance in the project. Contractors were encouraged to submit views on relational contracting and how relational contracting would be useful during project construction. Feedbacks from Contractors on the process and relational contracting were generally positive. Relationships between Client and MC started off well at the beginning of the project. However, other than the relationship management workshop held during the tender stage, no formal partnering or relational contracting approach was adapted in project construction. One reason given was the project and the relationship started off well and the project team found there was no need of formalising the relationship management process (i.e. no follow-up relationship management workshop or meetings).
APPENDIX V CASE STUDIES
333
Interviewee commented that the philosophy of partnering has been adapted in the project.
Benefits from the Managing Contractor Tender Evalua tion Process • It allows potential project team members to meet and assess their
capacity for future work cooperation • Team members (Client, Client’s Representative, Contractor) are
able to have a greater understanding of the project. • The process imports Relational Contracting components into
potential project team members • It helps to promote Relational Contracting in the construction
industry • It allows a 2-way communication and exchange of ideas on
relational contracting
Lessons Learnt Relationship contracting was introduced to potential contractors at an early stage (during tender assessment). Contractors were given an opportunity for a better understanding of the project. Problems and issues concerned were raised in the workshops, reducing the risk of misunderstanding which might subsequently lead to an underbid tender. There was high profile from the Client with the assistance of Client’s Representative on adapting concepts of relational contracting, promoting relational contracting in the construction industry. The philosophy of relational contracting was made clear and rooted in the potential project team before the project started. During the tender evaluation process, Client and Client’s Representative were able to learn from the attendees how they perceived relational contracting, the benefits and what could be improved to make relational contracting work (or better). With the strong commitment from both Client and Client’s Representative, correct concepts of relational contracting were introduced to the project team.
APPENDIX V CASE STUDIES
334
Case Study 6 Mt. Lindesay Highway, Brisbane
Client: Queensland Department of Main Roads
Contractor: National Contractor
Contract Strategy: AS 2124 with Extended Partnering
Project Background Case Study 6 is a highway upgrade project between Camp Cable Road and South Street. The project included upgrades from one-lane to two-lanes in each traffic direction, construction of pedestrian and local traffic underpass, highway overpass, roundabouts and installations of traffic lights. The project began in early 2004 and was expected to complete by mid 2005. The project was awarded to the Contractor based on the lowest bid wins mechanism. The type of contract used was AS2124 with Extended-Partnering. A one-day foundation workshop facilitated by an external facilitator was held in the first month of the project. Although it was not stated explicitly in any specification, there was consent between the Client and the Contractor that the Client would be responsible for all the relationship management incurring costs such as the employment of facilitator and equipments hire; whereas the Contractor would provide informal gathering such as barbeques or drinks. A project charter was set up by project participants in the foundation workshop, both long-term and short-term issues were raised and an action plan was set up for issue resolutions. During the foundation workshop, the facilitator gave an induction to project participants on the function and elements of relationship management. The major purpose of the workshop was to explore project team members’ personalities and to act as an ice-breaker. Attendees of the foundation workshop and the project charter are shown in Table CS6.1 and Table CS6.2.
Client Contractor
• Principal • Superintendent • Superintendent
Representative • 3 Inspectors
• Deputy Project Manager on Civil Work
• Project Manager • 2 Supervisors • 2 Foremen
Table CS6.1 Attendees of the One-Day Foundation Workshop
APPENDIX V CASE STUDIES
335
Charter Objectives
• Timely issue resolution • Maintaining a high level of open, honest and effective
communication • Plan and execute the works in an effective manner • Minimise the environmental impact • Maintaining target program • Quality right the first time • To ensure the safety of the project workforce and the
community • A proactive approach keeping all stakeholders informed and
resolving issues promptly • Achieving a balance between work and lifestyle • Genuine commitment to up-skilling all levels of project team
Table CS6.2 Charter Objectives of QDMR Case Study 6
Relationship Management in the Project Monthly relationship management meetings were chaired by the Principal and the deputy Project Manager (Contractor) alternatively. Project team members rated each charted objectives prior to each monthly meeting. A graph showing the trend of project team relationship was also produced (see Figure CS6.1 for example). Relationship in the project team started off well; open communication was established within the project team since the first day. There was no hidden agenda from both parties. Observations and suggestions on construction techniques were shared during relationship management meetings. Client staff were also invited to Contractor’s weekly program meetings, where comments and suggestions were encouraged.
APPENDIX V CASE STUDIES
336
Figure CS6.1 Partnering Assessment History by Project Period
Although project team relationship was generally well in the project, data generated from monthly Relationship Management assessments indicated the overall scores on project team relationship deteriorated gradually in the first four months, tension in the project team was becoming a concern. Project participants commented the Superintendent Representative was unsuitable for the project due to one’s personality and the insufficiency of on-site experiences, resulting delays in decision making and confirmation, causing interruptions in work progress. The Superintendent Representative was soon replaced and the project team relationship had been improving steadily. Delegation of power was also identified being a problem, and was dealt with readily at the project early stage. High turnover of project staff is not uncommon in the construction industry. In this project, other than the change over of Superintendent Representative, 50% of Contractor staff in the project team were replaced and no induction courses on relationship management were provided. The philosophy of relationship management and the decision matrix was not well understood by some project team members who did not attend the foundation workshop. Having identified the issue, the same facilitator was invited to the 6th relationship management meeting, where observations and recommendations on the relationship management process were presented to the project team. Project team was also reminded and introduced (newcomers) to the relationship management structure and philosophy. Early signs of crisis were pointed out to the project team for actions. Project team members became more alert to recurring issues such as quality of subcontractor staff, especially in safety. Contractor
APPENDIX V CASE STUDIES
337
attempted to resolve the safety issues by giving trainings and induction courses on the safety standards and systems and requirements on site to subcontractor staff. It is often Subcontractors have their own systems and work ethics, such arrangement helped standardising the safety system amongst all staff in the project. The subcontractor staff would be dismissed from the project, if there was no improvement upon the receipt of first written warning. Parties including the Contractor, Subcontractor and Client could also exercise the right. Subcontractors’ behaviour of safety on site improved significantly since the arrangement was in place. During the project period, there was an increasing shown of appreciations and acknowledgments by both parties explicitly. Open and effective communication was developed in the project team. An electronic monthly bulletin was circulated by the Project Manager to the project team. The bulletin namely detailed big and small project issues and reported progress to-date, providing an alternative channel of information transfer. Problems and concerns were raised during relationship management meetings, and were discussed in a team fashion. Project parties paid respects to all issues rose, which were taken onboard as team matters. Despite there was a high staff turnover in the project, the project process was not greatly affected, communication and relationship in the project team remained at a good level. Contractor staff were encouraged to attend monthly relationship management meetings. Project participants pointed out relationship management helped to understand individual’s personality and help to break down the ice. One project participant shared her view on relationship management. Her first impression on relationship management was just another nametag and ‘touchy feeling’ appliance. She was dubious on the benefits from such arrangement. After experienced a number of relationship management projects, she found relationship management arrangement enhanced the development of team working environment. Project participants were exposed to the true philosophy of relationship management and different type of personalities in foundation workshops. In this project, team members became more open and willing with sharing information/knowledge (including each organisation’s internal procedures) and resources as the project progressed. Project participants expressed that monthly relationship meetings allowed big and small pictures in the project to be seen. The project team maintained a sense of humour which helped to ease the pressure at various stages of the project. There was increasing team discussion and positive communication, resolving problems as a team rather than looking for ‘who to blame’, working towards best for project.
APPENDIX V CASE STUDIES
338
Lessons Learnt Relationship management was a success in this project. There was strong commitment from senior management level in both client and contractor organisations. There was a right mix of people in the project team. Individual was removed from the project team when found unsuitable. Good relationship in the project team was established at all levels since the beginning of the project. An external facilitator was employed for the foundation workshop which allowed correct mindset on relationship management to be introduced to the project team since the start of the project. The facilitator was again invited to give an opinion on the project team relationship, and the team became more conscious on early crisis warning. The importance of communication between the project team at all levels was stressed since the first day. Other than formal communication channels such as monthly meetings and written correspondents, team members’ relationship was enhanced through social functions. An innovative communication channel was used in this project, where monthly project bulletin was emailed to the project team. Contractor staff were given the opportunity and were encouraged to attend relationship management meetings. Other than openly discussion of issues, follow-up actions were also taken place. High level of respects and acknowledgements were shown between parties in all matters.
APPENDIX V CASE STUDIES
339
Case Study 7 Brisbane Magistrates Court
Client: Department of Justice and Attorney-General
Client’s Representative: Queensland Department of Public Works
Managing Contractor: National Contractor
Contract Strategy: Managing Contractor (D&C) with Relationship Management
Tender Price: AU$135.5M
Project Background Case Study 7 is a building project, construction of a new courthouse in Brisbane city centre over a period of 28 months. It was set to be a landmark of the western end of the central business district. The contract strategy chosen was Managing Contractor (Design and Construction) Contract with Relationship Management, where a risk/reward mechanism was also engaged. Managing Contractor would receive bonus payment for achievements of extra works in an incremental way. A guaranteed contract sum was in place to secure the top margin of actual construction sum. This project was the first public sector building project in Queensland which used a full Managing Contractor Contract with Relationship Management. An outline of the project background is presented in Table CS7.1 below.
Tender Price $135.5 million
QDPW Role Project Director Principal Representative
Project Description Ten floor building with two basement levels. Facilities include:
• Hearing rooms; • Detention facilities; • Conference rooms; • Interview rooms; • Prisoner transfer facilities; and • Car parking
Table CS7.1 Project Background
APPENDIX V CASE STUDIES
340
Project Design and Tender Process The project design was carried out via a design competition, which is a common practice for landmark construction. Consultants were short listed and a refinement process was carried out through workshops, where the design was refined and the project brief produced by Client was reviewed. The project design was signed off by Client at the final workshop. Potential MCs were not involved during the refinement process until the very late stage of Schematic Design. Schematic Design was completed during the tender review period. MC was given the formal schematic design (including specification and a detailed client brief) before the appointment. 4 Managing Contractor tenders were submitted and an interview and review process was carried out for the four contractors. Contractors were given the opportunity to raise their concerns or if they had any unsatisfactory experience with the proposed consultants during the review process. 2 tenders were short-listed. A full day workshop was held with both Contractors separately, facilitated by an external facilitator and the full project team (QDPW, consultant, client). A one day review process was carried out following the workshop and the Contractor was appointed.
Contract Strategy The choice of contract strategy was determined upon the project complexity, high profile, and the needs to meet various Government agencies expectations. Managing Contractor (MC) was engaged at the end of schematic design when the Client has signed off the project design at the final workshop. Due to the design complexity and time constrain, the consultants were novated to the MC since the development design (construction) stage until project completion. Due to the project nature, the Project Director was keen to get Managing Contractor on broad as soon as possible before the development design stage and to receive advices from the Subcontractors during the process. The list of attendees is presented in Table CS7.2 below. Client’s Representative commented such approach is very common for larger size projects, and similar approach has also been adopted in traditional projects e.g. TAFE. In this project, four relationship management workshops were.
APPENDIX V CASE STUDIES
341
Prior to Appointment of MC
Value Management Relationship Workshop (Refinement Stage)
With external facilitator Client + Consultant
Value Management Relationship Workshop
With external facilitator Client + Consultant + Managing Contractor Tenders
Value Management Relationship Workshop (Schematic Design Stage)
With external facilitator Client + Client’s Rep. + Consultant
Upon Appointment of MC
1st Workshop with Potential Managing Contractor
With external facilitator Client + Client’s Rep. + 2 Short-listed Managing Contractor (separately)
Value Management Relationship Workshop (Development Design Stage)
With external facilitator Client + Client’s Rep. + Managing Contractor + Consultant
2 x larger Value Management Relationship Workshop
Client + Client’s Rep. + Managing contractor + Consultant + major Subcontractors (looked at both technical and coordination issues)
Several in-house half day workshops
Table CS7.2 Major Workshops Attendees
An interviewee found the maximum benefit of RC was gained from the full-day workshops held during the construction period. Full-day workshops were considered unnecessary for the rest of the construction period but half-day workshops were held throughout the project.
Relationship Management in the Project Interviewees found the major principle of relationship management is about focussing on teamwork. Also, everyone must work as ONE team, including Client, Client’s Representative, Contractor (MC in this case) and Consultant. There ought to be open and honest communication during
APPENDIX V CASE STUDIES
342
work, not covering up any issues, such as claims. Also, team should work in a positive way where MC would also be rewarded for. In this case, stretch scope with risk/reward mechanism was adapted. An interviewee pointed out the biggest problem faced in this project was the over heated market during construction. Although there was strong buy-in of relationship managing from all project participants, the overheated market during the construction stage pushed both labour and material costs high, putting the MC in a very difficult financial situation. Also, the lack of resources available put pressure on meeting the project schedule, in this case, the glass supplier for example, which would subsequently delay product delivery. As a relational contracting approach was applied in the project, the contractor undertook an open book strategy, giving the client full access to the project finance. This level of trust not only triggered frequent communication between the parties on problem resolution; there were also lots of brainstorming and innovative ideas to keep the project cost down and to improve the project performance, in a team fashion.
Formal system Essence of relationship management can be found in the contract documents. Relationship management in the project was structured and formed part of the contract documents, such as general clauses on relationship management workshops and meetings. Monthly meetings were held where team relationship was assessed and discussed. It was also stated in the contract that there would be no liquidated damage between project parties and no extension of time until target completion date. Consultant was novated to Managing Contractor upon its appointment. In order to maintain Managing Contractor’s buy-in on relationship management, a risk /reward mechanism was used in the project, forming one of motivation incentives. Client’s mutual obligation was also stated in the contract document, aiming to develop a collaborative and harmony team relationship between all project partners. The relationship management philosophy was particularly addressed by 2 clauses in the contract documents. One of the clauses detailed what the essences of a relationship contract are; whereas the other clause stated all project participants must work with good faith.
Informal system The need to choose the right mix of people was recognised. Team members needed to have the right attitude or adopt the right attitude i.e. not a hard-dollar attitude. There were strong believes on relationship management and commitment from senior management between Client and Managing Contractor. Although there was no mechanism on the choice of team members, both organisations put in the best/right team for the project. Relationship management concepts were filtered down to the
APPENDIX V CASE STUDIES
343
operation level and were strongly supported. By having the right mix of team members, good relationships were developed between project team members since the project began. Major subcontractors were brought into relationship meetings and workshops by Managing Contractor where professional advices were given.
Comments and Suggestions by Project Participants • Risks were not shared amongst the project participants. • There was good spirit of relationship management throughout the
project between all parties at all levels. • The contract was still inflexible because it is Client’s money, Client’s
Representative’s contract. • Everyone was protected by the contract other than the delivery
team (Managing Contractor and Consultant); all risks were ‘sold’ to the delivery team.
• A risk sharing mechanism is needed for the project to be fair. • The Client has a reasonable and right attitude towards the project. • There were continuous open discussions including the financial
difficulties the Contractor was facing. • Relational contracting is a great way to associate in building
business. • There were forever meetings. • Subcontractors had difficulties on accepting relational contracting
due to their interpersonal skills. • Subcontractors expected extra payment from Managing Contractor
in exchange for sub-contractors’ knowledge sharing and professional advices.
• Relationship between Managing Contractor and sub-contractors was good (and better compare with most projects under traditional contracting).
• There were lots of innovation in the project because of bringing sub-contractors onboard and pressure from the over-heated market.
• All parties were strongly committed to the project. • Fluctuations and risks were one-sided – there needs to be a clause
in the contract where project problems are shared between all parties.
• Managing Contractor should be brought in earlier (before DD) to the project for active involvement and professional advices.
• Parties were exposed to the different attitudes and way of dealing with issues by other parties.
• Project team was more collaborative and cooperative (compare with projects carried out using traditional contracting approach).
• Consultant was more collaborative and would discuss about design issues with sub-contractor directly.
APPENDIX V CASE STUDIES
344
Lessons Learnt The project was tendered before the real estate boom. Although the contract was not underbid, MC struggled with the availability and cost of labour and materials during construction. Because relational contracting was applied in the project, there was frequent open and honest communication between all parties. There was an open book system where the financial situation of the project was discussed frequently between parties during project construction. There was strong cooperation and collaboration between project parties and there were lots of innovations in the project. External facilitator was engaged in all major relationship management workshops. Subcontractors were brought onboard since the relationship management workshop and were invited to all monthly relationship management meetings, where their knowledge and expertise were shared. On-going minor workshops were also held for the project team. Good relationships between project team members were established on the first day and there was goal alignment in the project – which is a critical element in relational contracting. Also, there was a strong buy-in on relational contracting at all levels as well as a right mix of people in the project team. Clauses with strong references to the philosophy of relational contracting were stated in the contract and a risk/reward mechanism was employed. However, MC should be brought into the project at an earlier stage, where collaborations with their professional expertise could be carried out to a greater extent.
AP
PE
ND
IX V
I
R
C S
UC
CE
SS
& F
AIL
UR
E F
AC
TO
RS
34
5
Case Studies Failure Reasons Success Reasons
Case Study 1 • Parent company policy and culture • Lots of change over of staff in project • Close communication (as opposed to open
communication) • Selection of project team members • Uncooperative team member(s) • Money in the contract • Selection of tender (depends on the selection
criteria – not just the lowest bid wins) • Objectives of the project • Lack of common goals between all parties (the
major criterion in partnering) • Financial item as part of charter objectives
Case Study 2 • Company policy and culture • No/little change over of staff in project • Open and informal communication between project
team members • Money in the contract • Project was not underbid • Objectives in the project • All parties work towards the same goal • Charter objectives were set with all parties consent • Major subcontractor was brought into partnering
meetings
34
6
AP
PE
ND
IX V
I
R
C S
UC
CE
SS
& F
AIL
UR
E F
AC
TO
RS
Case Studies Failure Reasons Success Reasons
Case Study 3 (Package 2) • Contract was seriously underbid • Contractors tried to recover cost during the whole
project period • Parties were working towards different goals at the
beginning • High turnover of staff (2 different contractors +
QDMR personnel at the last stage to finish the project)
(Packages 1 & 3) • There was money in the contract • Right mix of people • Open communication in the project team • Good relationship between Contractor and QDMR
was established at the first day • Strong commitment (and involvements) from top
management on both sides • Main Subcontractor was brought to partnering
meetings
Case Study 4 • There is sufficient amount of money in the contract • Good relationship established in project ream from
the beginning of the project • Right mix of people in project team • Open communication with risks and issues
exposed on the table • Constructor did not put in unreasonable claims
Case Study 5 • Relationship contracting was introduced to potential contractors at an early stage (during tender assessment)
• Allow tenderers to have a better understanding of the project, reducing the risk of misunderstand which subsequently leads to an underbid tender
• High profile from the Client with the assistance of Client Consultant on adopting the concept of relationship contracting
AP
PE
ND
IX V
I
R
C S
UC
CE
SS
& F
AIL
UR
E F
AC
TO
RS
34
7
Case Studies Failure Reasons Success Reasons
Case Study 6 • Right mix of people – remove if one is not right • Good relationship at all levels • Strong commitment from senior management level • Financial was not part of the project charter • Open and frank communication at all levels • Innovative communication channel – monthly
project bulletin to project team • Respect and acknowledgment at all matters • Follow-up actions were taken place (not just paying
lip services) • Involvement of facilitator during project to refocus
team on communication and early crisis warning • Contractor threw in BBQs & drinks – informal
communication • Buy-in of RM at all levels • Opportunities for contractor staff to attend RM
meetings • Delegation of power
AP
PE
ND
IX V
I
R
C S
UC
CE
SS
& F
AIL
UR
E F
AC
TO
RS
34
8
Case Studies Failure Reasons Success Reasons
Case Study 7 • Relational contracting was introduced to contractors at tendering stage
• Project team had a goal alignment • Strong and continuous commitment by the Client,
Project Director and the Contractor • Right mix of people – Contractor staff were put
together specially for the Client and the project • Buy-in of relational contracting at all levels • Continuous good working relationship at operation
level • Financial incentive (risk/reward mechanism) for the
Contractor • Open and honest communication between parties • Open book system – Client and Project Director
had access to Contractor’s financial situation • Sub-contractors were brought onboard in the
relationship management workshop • External facilitator was employed for the major
workshops • On-going smaller scale workshops for project team • Clauses with strong references to relational
contracting philosophy were stated in the contract
349
REFERENCES
Adler, N. (2002) International Dimensions of Organizational Behavior. Ohio: South Western.
Allen, N. J., and Meyer, J. P. (1990) The Measurement and Antecedents
of Affective, Continuance and Normative Commitment to the Organisation, Journal of Occupational Psychology, 63, 1-18.
Alsagoff, S. A., and McDermott, P., (1994) Relational Contracting: A
Prognosis for the Uk Construction Industry? In: S. Rowlinson ed. of Conference Relational Contracting: A Prognosis for the UK Construction Industry?, CIB W92 Symposium, Hong Kong. University of Hong Kong pp. 11-19.
Angle, H. L., and Lawson, M. B. (1994) Organizational Commitment and
Employees; Performance Ratings: Both Type of Commitment and Type of Performance Count, Psychological Reports, 75 1539-1551.
Argyris, C. (1973) On Organizations of the Future. Beverly Hills, CA: Sage. Ashforth, B. E., and Saks, A. M. (1996) Socialization Tactics: Longitudinal
Effects on Newcomer Adjustment, Academy of Management Review, 39 149-178.
Barney, J. B., and Hansen, M. H. (1994) Trustworthiness as a Source of
Competitive Advantage, Strategic Management Journal, 7 175-190. Bennett, J., and Jayes, S. (1995a) Trusting the Team: The Best Practice
Guide to Partnering in Construction. Reading, England: Center for Strategic Studies in Construction/Reading Construction Forum.
Bennett, J., and Jayes, S. (1995b) Trusting the Team: The Best Practice
Guide to Partnering in Construction. Reading: Reading Construction Forum.
Bennett, J., and Jayes, S. (1998) The Seven Pillars of Partnering.
Reading, England: Reading Construction Forum. Blau, P. M. (1963) The Dynamics of Bureaucracy. Chicago: University of
Chicago Press. Blau, P. M., and Schoenherr, R. H. (1971) The Structure of Organizations.
New York: Basic Books.
350
Bodley, J. H. (1994) Culture Anthropology: Tribes, States, and the Global System. Mayfield.
Bolton, M., Malmrose, R., and Ouchi, W. (1994) The Organization of
Innovation in the USA and Japan: Neoclassical and Relational Contracting, Journal of Management Studies, 21 (no. 5), pp. 653-679.
Brenkert, G. G. (1998) Trust, Morality and International Business,
Business Ethics Quarterly, 8 (no. 2), pp. 293-317. Bresnen, M. (1990) Organising Construction. London: Routledge. Bresnen, M., and Marshall, N. (2000a) Building Partnerships: Case
Studies of Client-Contractor Collaboration in the UK Construction Industry, Construction Management and Economics, 18 (no. 7), pp. 819-832.
Bresnen, M., and Marshall, N. (2000b) Motivation, Commitment and the
Use of Incentives in Partnerships and Alliances, Construction Management and Economics, 18 (no. 5), pp. 587-598.
Bresnen, M., and Marshall, N. (2000c) Partnering in Construction: A
Critical Review of Issues, Problems and Dilemmas, Construction Management and Economics, 18 (no. 5), pp. 229-237.
Bronder, C., and Pritzl, R. (1992) Developing Strategic Alliances: A
Successful Framework for Cooperation, European Management Journal, 10 (no. 4), pp. 412-420.
Bycio, P., Hyackett, R. D., and Allen, J. S. (1995) Further Assessments of
Bass's (1985) Conceptualization of Transactional and Transformational Leadership, Journal of Applied Psychology, 80, 468-478.
Cheung, S. O. (2001) Relationalism: Construction Contracting under the
People's Republic of China Contract Law, Cost Engineering, 43 (no. 11), pp. 38-43.
Construction Best Practice Programme. (1998) Fact Sheet on Partnering.
Watford, Herts, UK: The Construction Best Practice Programme. Construction Clients' Forum. (1998) Construction Improvement. London:
Construction Clients' Forum.
351
Construction Industry Board. (1997) Partnering in the Team. Report by Working Group 12 of the Construction Industry Board, London: Thomas Telford.
Construction Industry Institute. (1991) In Search of Partnering Excellence.
Austin, TX: Construction Industry Institute. Construction Industry Institute. (1996) The Partnering Process - Its
Benefits, Implementation, and Measurement. Austin, TX: Construction Industry Institute.
Construction Industry Research and Information Association. (1983)
Management Contracting. London: The Association. Cunningham, I., and Hyman, J. (1999) The Poverty of Empowerment? A
Critical Case Study, Personnel Review, 28 (no. 3), pp. 192-207. Dainty, A. R. J., Briscoe, G. H., and Millett, S. J. (2001) Subcontractor
Perspectives on Supply Chain Alliances, Construction Management and Economics, 19 841-848.
Darwin, J. (1994) Networks, Partnerships and Strategic Alliances.
Sheffield Hallam University: Sheffield Business School. Darwin, J., Duberley, J., and Johnson, P. (2000) Contracting in Ten
English Local Authorities: Preferences and Practice, The international Journal of Public Sector Management, 13 (no. 1), pp. 38-57.
Das, T. K., and Teng, B. S. (1998) Resource and Risk Management in the
Strategic Alliance Making Process, Journal of Management, 24 (no. 1), pp. 21-42.
Deal, T., and Kennedy, A. (1982) Corporate Cultures: The Rites and
Rituals of Corporate Life. Reading: Addison-Wesley. Deming, W. E. (1994) The New Economics for Industry, Government,
Education. Cambridge: Massachusetts Institute of Technology, Center for Advanced Engineering Study.
Department of Commerce (2003) C21 Construction Contract [online].
Accessed on 12 November 2005, Available from World Wide Web: <http://www.c21.dpws.nsw.gov.au>.
Dirks, K. T. (1999) The Effects of Interpersonal Trust on Work Group
Performance, Journal of Applied Psychology, 84, pp. 445-455.
352
Earle, T. C., and Cvetkovich, G. (1995) Social Trust: Towards a Cosmopolitan Society. Praeger: Westport.
Easterby-Smith, M., Thorpe, R., and Lowe, A. (1991) Management
Research: An Introduction. London: Sage. Egan, J. (1998) Rethinking Construction. London: Department of the
Environment, Transport and the Regions. European Construction Institute. (1997) Partnering in the Public Sector: A
Toolkit for the Implementation of Post Award. Project Specific Partnering on Construction Projects. Loughborough, UK: ECI, Loughborough University.
Fang, T. (2001) Culture as a Driving Force for Interfirm Adaptation: A
Chinese Case, Industrial Marketing Management, 30 51-63. Fawcett, S. B., White, G. W., Balcazar, F. E., Suarez-Nalcazar, Y.,
Mathews, R.M., Paine-Andrews, A., Seekins, T., and Smith, J. F. (1994) A Contextual-Behavioral Model of Empowerment: Case Studies Involving People with Physical Disabilities, American Journal of community Psychology, 22 471-496.
Fellows, R., and Liu, A. (1997) Research Methods for Construction.
Australia: Blackwell Science Ltd. Fisher, R., and Ury, W. (1981) Getting to Yes: Negotiating Agreement
without Giving In. London: Houghton Mifflin Company. Flores, F., and Solomon, R. C. (1998) Creating Trust, Business Ethics
Quarterly, 8 (no. 2), pp. 205-232. Foster-Fishman, P. G., and Keys, C. B. (1997) The Person/Environment
Dynamics of Employee Empowerment: An Organizational Culture Analysis, American Journal of community Psychology, 25 (no. 3), pp. 345-369.
Fukuyama, F. (1995) Trust: The Social Virtues and the Creation of
Prosperity. Harmondsworth: Penguin Books. Gaedo, A. H. (1995) Partnering: A Common Sense Approach to
Preventing and Managing Claims, International Construction Law Review, 72 (no. 12), pp. 72-83.
Galbraith, J. R. (1977) Organization Design. Reading: Addison-Wesley.
353
Galbraith, J. R., and Nathanson, D. A. (1978) Strategy Implementation: The Role of Structure and Process. St. Paul: West Publishing Company.
Gambetta, D. (1998) Trust: Making and Breaking Cooperative Relations.
Basil Blackwell. Ganesan, S. (1994) Determinants of Long-Term Orientation in Buyer-
Seller Relationships, Journal of Marketing, 58 (April), pp. 1-19. General Contractors of America Associated. (1991) Partnering: A Concept
for Success. Washington, D.C.: Associated General Contractors of America.
Goodman, R., and Chinowsky, P. (1996) Managing Interdisciplinary
Project Teams through the Web, Journal of Universal Science, 2 (no. 9), pp. 597-609.
Goodstein, L., and Boyer, R. (1972) Crisis Intervention in a Municipal
Agency. A Conceptual Case Study, Journal of applied Behavioral Science, 8, pp. 318-340.
Green, S. D. (1999) Partnering: The Propaganda of Corporatism?, Journal
of Construction Procurement, 5 (no. 2), pp. 177-186. Griffin, A., and Hauser, J. R. (1996) Integrating Mechanisms for Marketing
and R&D, Journal of Product Innovation Management, 13 (no. 3), pp. 191-215.
Gruber, J., and Trickett, E. J. (1987) Can We Empower Others: The
Paradox of Empowerment in the Governing of an Alternative Public School, American Journal of community Psychology, 15, pp. 353-371.
Hamel, G. (1989) Collaborate with Your Competitors - and Win, Harvard
Business Review, January/February, pp. 133-139. Hampson, K., and Kwok, T. (1997) Strategic Alliances in Building
Construction: A Tender Evaluation Tool for the Public Sector, Journal of Construction Procurement, 3 (no. 1), pp. 28-41.
Handy, C. (1985) Understanding Organisations. London: Penguin. Hofstede, G. H. (1980) Culture's Consequences: International Differences
in Work-Related Values. Beverly Hills: Sage.
354
Hofstede, G. H., and Bond, M. H. (1988) The Confucius Connections: From Cultural Roots to Economic Growth, Organization Dynamics, 16 (no. 4), pp. 4-21.
Hosmer, L. T. (1994a) Strategic Planning as If Ethics Mattered, Strategic
Management Journal, 15 (no. 17-34). Hosmer, L. T. (1994b) Why Be Moral? A Different Rationale for Managers,
Business Ethics Quarterly, 4 (no. 2), pp. 191-204. Howarth, C. S., Gillin, M., and Bailey, J. (1995) Strategic Alliances:
Resource-Sharing Strategies for Smart Companies. Australia: Pearson Professional (Australia) Pty. Ltd.
Hutchinson, A., and Gallagher, J. (2003) Project Alliances - an Overview.
Australia: Alchimie Pty. Ltd and Philips Fox. Ingram, T. N., Lee, K. S., and Skinner, S. (1989) An Empirical Assessment
of Salesperson Motivation, Commitment and Job Outcomes, Journal of Personal Selling and Sales Management, 9, pp. 25-33.
Jackson, T. (1993) Organizational Behaviour in International Management.
Oxford: Butterworth-Heinemann. Jassawall, A. R., and Sashittal, H. C. (1998) An Examination of
Collaboration in High-Technology New Project Development Processes, Journal of Product Innovation Management, 15, pp. 237-254.
Jenks, C. (1993) Culture. London: Routledge. Johnson, D. W., and Johnson, R. T. (1989) Cooperation and Competition:
Theory and Research. Edina: Interaction Book Company. Jones, D., (2000) Project Alliances. In: Conference of Project Alliances,
Hong Kong. Association for Project Management, pp. 24. Jorde, T. M., and Teece, D. J. (1989) Competition and Cooperation:
Striking the Right Balance, California Management Review, 31 (no. 3), pp. 25-37.
Kanter, R. M. (1989) When Giants Learn to Darn to Dance: Mastering the
Challenges of Strategy, Management and Careers in the 1990s. London: Unwin Hyman.
Kanter, R. M. (1994) Collaborative Advantage: The Art of Alliances,
Harvard Business Review, 72 (no. 4), pp. 96-108.
355
Kerfoot, D., and Knight, D. (1995) Empowering the 'Quality' Worker?: The
Seduction and Contradiction of the Total Quality Phenomenon. In: A. Wilkinson and H. Willmott, (eds.) Making Quality Critical. London: Routledge. pp. 219-239.
Ketelholm, W. (1993) What Do We Mean by Cooperative Advantage?,
European Management Journal, 11 (no. 1), pp. 30-37. Konovsky, M. A., and Cropanzano, R. (1991) Perceived Fairness of
Employee Drug Testing as a Predictor of Employee Attitudes and Job Performance, Journal of Applied Psychology, 76, pp. 698-707.
Kroeber, A. L., and Kluckhohn, C. (1952) Culture: A Critical Review of
Concepts and Definitions. Boston: Harvard University. Kubal, M. T. (1994) Engineering Quality in Construction: Partnering and
Tqm. USA: McGraw-Hill. Kumaraswamy, M. M., and Matthews, J. D. (2000) Improved
Subcontractor Selection Employing Partnering Principles, Journal of Management in Engineering, ASCE, 16 (no. 3), pp. 47-57.
Kwok, A., and Hampson, K. (1996) Building Strategic Alliances in
Construction, AIPM Special Publication. Latham, M. (1994) Construction the Team. London: the Stationery Office:
Joint review of procurement and contractual arrangements in the United Kingdom Construction Industry.
Lau, H. L., (1999) Trust as a Human Factor in Management in General
and in Construction. In: S. O. Ogunlana ed. of Conference Trust as a Human Factor in Management in General and in Construction, CIB W92/TG23 Symposium, Thailand. E&FN Spon pp. 117-126.
Laurent, A. (1986) The Cross-Cultural Puzzle of International Human
Resource Management, Human Resource Management, 25 (no. 1), pp. 91-102.
Lee, T. W. (1999) Using Qualitative Methods in Organizational Research.
Thousand Oaks: Sage. Leong, S. M., Randall, D. M., and Cote, J. A. (1994) Exploring the
Organizational Commitment-Performance Linkage in Marketing: A Study of Life Insurance Salespeople, Journal of Business Research, 29, pp. 57-63.
356
Lewicki, R., Saunders, D., and Minton, J. (1999) Negotiation. Boston: McGraw-Hill.
Liu, A. M. M., and Fellows, R. (2001) An Eastern Perspective on
Partnering, Engineering, Construction and Architectural Management, 8 (no. 1), pp. 9-19.
Liu, A. M. M., and Fellows, R. F., (1996) Towards an Appreciation of
Cultural Factors in the Procurement of Construction Projects. In: R. Taylor ed. Conference of Towards an Appreciation of Cultural Factors in the Procurement of Construction Projects, CIB W92 Symposium, Durban, South Africa. pp. 301-310.
Loraine, R. (1993) Partnering in the Public Sector. London: Business
Round Table. Lorenz, E. (1991) Neither Friends nor Strangers: Informal Networks of
Subcontracting in French Industry. In: G. Thompson, J. Frances, R. Levacic, and J. Mitchell, (eds.) Markets, Hierachies and Networks: The Co-Ordination of Social Life. London: Sage.
Love, P. E. D., and Gunasekaran, A. (1999) Learning Alliances: A
Customer-Supplier Focus for Continuous Improvement in Manufacturing, Industrial and Commercial Training, 31 (no. 3), pp. 88-96.
Luhmann, M. (1979) Trust and Power. Chichester: Wiley. Lynch, R. P. (1993) Business Alliances Guide. Chichester: Wiley. MacNeil, I. R. (1974) The Many Futures of Contracts, Southern California
Law Review, 47, pp. 691-816. MacNeil, I. R. (1978) Contracts: Adjustment of Long-Term Economic
Relations under Classical, Neoclassical and Relation Contract Law, Northwestern University Law Review, pp. 854-905.
MacNeil, I. R. (1980) The New Social Contract: An Inquiry into Modern
Contractual Relations. New Haven, NJ: Yale University Press. MacNeil, I. R. (1985) Relational Contract: What We Do and Do Not Know,
Wisconsin Law Review, pp. 483-525. Magee, B. (1988) Men of Ideas. London: BBC Books. Manivong, K., and Chaaya, M., (2000) Life Cycle Project Management. In:
L. Crawford ed. of Conference Life Cycle Project Management, The
357
International Research Network on Organizing by Projects, 9-12 January, Sydney. Sydney University of Technology, pp. 221-229.
Manley, K., and Hampson, K. (2000) Relationship Contracting on
Construction Projects. Brisbane, Australia: QUT/CSIRO construction Research Alliance.
Matthews, J. (1996) A Project Partnering Approach to the Main Contractor-
Subcontractor Relationship. PhD Thesis, Loughborough University. Matthews, J., and Rowlinson, S. (1999) Partnering: Incorporating Safety
Management, Engineering, Construction and Architectural Management, 6 (no. 4), pp. 347-357.
Maxwell, J. A. (1996) Qualitative Research Design: An Interactive
Approach. USA: Sage. Mayer, R. C., and Davis, J. H. (1999) The Effect of the Performance
Appraisal System on Trust in Management: A Field Quasi-Experiment, Journal of Applied Psychology, 84 (no. 1), pp. 123-136.
McAllister, D. J. (1995) Affect and Cognition Based Trust as a Foundation
for Interpersonal Cooperation in Organizations, Academy of Management Review, 38 (no. 1), pp. 24-59.
McDonough III, E. F. (2000) An Investigation of Factors Contributing to the
Success of Cross-Functional Teams, Journal of Product Innovation Management, 17 (no. 3), pp. 211-235.
McDonough III, E. F., and Barczak, G. (1991) Speeding up New Product
Development: The Effects of Leadership Style and Source of Technology, Journal of Product Innovation Management, 8 (no. 3), pp. 203-211.
McGregor, D. (1960) The Human Side of Enterprise. New York: McGraw-
Hill. Mead, R. (1998) International Management: Cross-Cultural Dimensions.
Oxford: Blackwell. Meyer, J. P., and Allen, N. J. (1991) A Three-Component
Conceptualization of Organizational Commitment, Human Resource Management Review, 1, pp. 61-89.
Meyer, J. P., and Allen, N. J. (1997) Commitment in the Workplace:
Theory, Research and Application. London: Sage Publications.
358
Meyer, J. P., Paunonen, S. V., Gellatly, I. H., Goffin, R. D., and Jackson, D. N. (1989) Organizational Commitment and Job Performance: It's the Nature of the Commitment That Counts, Journal of Applied Psychology, 74, pp. 152-156.
Misztal, B. A. (1996) Trust in Modern Societies. Cambridge: The Polity
Press. Mittal, B., (1996) Trust and Relationship Quality: A Conceptual Excursion.
In: A. Parvatiyar and J. N. Sheth eds. of Conference Trust and Relationship Quality: A Conceptual Excursion, Contemporary Knowledge of Relationship Marketing, Center for Relationship Marketing. Emory University, pp. 230-240.
Moenaert, R. K., Souder, W., De Meyer, A., and Deschoolmeester, D.
(1994) R&D-Marketing Integration Mechanisms, Communication Flows and Innovation Success, The Journal of Product Innovation Management, 11, pp. 31-45.
Mohamed, S. (2003) Determinants of Trust and Relationship Commitment
in Supply Chain Partnerships. Moorman, C., Deshand? R., and Zaltman, G. (1993) Factors Affecting
Trust in Market Research Relationships, Journal of Marketing, 57 (January), pp. 81-101.
Moorman, R. H., Niehoff, B. P., and Organ, D. W. (1993) Treating Employees Fairly and Organizational Citizenship Behavior: Sorting the Effects of Job Satisfaction, Organizational Commitment, and Procedural Justice, Employee Responsibilities and Rights Journal, 6, pp. 209-225. Morrill, R. L. (1980) Teaching Values in College. San Francisco: Jossey Bass. Niebuhr, H. R. (1960) Radical Monotheism and Western Culture. New York: Harper & Row. Oakland, J. S. (1993) Total Quality Management. Oxford: Butterworth-Heinemann. Owens, R. (1987) Organisational Behaviour in Education. Eaglewood Cliffs: N.J. Prentice Hall. Parson, T., and Smelser, N. J. (1984) Economy and Society: A Study in the Integration of Economic and Social Theory. London: Routledge & Kegan Paul.
359
Patton, M. Q. (1990) Qualitative Evaluation and Research Methods. California: Sage. Perry, R. B. (1954) Realms of Value. Cambridge: Harvard University Press. Peters, R., Walker, D., and Hampson, K. (2001) Case Study of the Acton Peninsula Development. Australia: Research and Case Study of the Construction of the National Museum of Australia and Australian Institute of Aboriginal and Torres Strait Islander Studies, School of Construction Management and Property, Queensland University of Technology. Pirsig, R. M. (1974) Zen and the Art of Motorcycle Maintenance. London: The Bodley Head. Prabhu, V. B., and Robson, A. (2000) Achieving Service Excellence - Measuring the Impact of Leadership and Senior Management Commitment, Managing Service Quality, 10 (no. 5), pp. 307-317. Punnett, B. J. (1998) Cross-National Culture. In: M. Poole and M. Warner, (eds.) The Handbook of Human Resource Management. London: International Business Press. pp. 9-26. Queensland Government Department of Main Roads. (2003) Main Roads Project Delivery System: Volume 1 - Selection of Delivery Options. Australia: Queensland Government Department of Main Roads. Rahman, M., and Kumaraswamy, M. M. (2002) Joint Risk Management through Transactionally Efficient Relational Contracting, Construction Management and Economics, 20 (no. 1), pp. 45-51. Rahman, M. M., Palaneeswaran, E., and Kumaraswamy, M. M., (2001) Applying Transaction Costing and Relational Contracting Principles to Improved Risk Management and Contractor Selection. In: Conference of Applying Transaction Costing and Relational Contracting Principles to Improved Risk Management and Contractor Selection, International Conference on Project Cost Management, Beijing, PRC. pp. 171-181. Randall, D. M., Fedor, D. B., and Longenecker, C. O. (1990) The Behavioral Expression of Organizational Commitment, Journal of Vocational Behaviour, 36, pp. 210-224. Robinson, J. (1964) Economic Philosophy. Middlesex: Penguin Books. Rogers, C. R., and Stevens, B. (1967) Person to Person: The Problem of Being Human, a New Trend in Psychology. Souvenir Press.
360
Root, D. S. (2000) The Influence of Professional and Occupational Cultures on Project Relationships Mediated through Standard Forms and Conditions of Contract. PhD Thesis, University of Bath. Rousseau, D. M., and Parks, J. M. (1993) The Contracts of Individuals and Organizations, Research in Organizations' Behaviour, 55, pp. 1-43. Rowlinson, S. (2001) Matrix Organisation Structure, Culture and Commitment - a Hong Kong Public Sector Case Study of Change, Construction Management and Economics, 19 (no. 7), pp. 669-673. Ruppel, C. P., and Harrington, S. J. (2000) The Relationship of Communication, Ethical Work Climate, and Trust to Commitment and Innovation, Journal of Business Ethics, 25, pp. 313-328. Sako, M. (1992) Prices, Quality and Trust: Interfirm Relations in Britain and Japan. Cambridge: Cambridge University Press. Sanders, S. R., and Moore, M. M. (1992) Perceptions of Partnering in the Public Sector, Project Management Journal, XXII (no. 4), pp. 13-19. Schein, E. (1990) Organisational Culture, American Psychologist, 45 (no. 2), pp. 109-119. Serrano-Garcia, I. (1984) The Illusion of Empowerment: Community Development within a Colonial Context. In: J. Rappaport, C. Swift, and R. Hess, (eds.) Studies in Empowerment: Steps toward Understanding and Action. New York: Haworth. pp. 9-35. Shaw, R. B. (1997) Trust in the Balance. San Francisco: Jossey-Bass Publishers. Skinner, D. G., (2001) Relationship Contracting: Is It the Way of the Future or Just Another Passing Fad? In: Conference of Relationship Contracting: Is It the Way of the Future or Just Another Passing Fad?, 20th ARRB Conference, Melbourne, Australia.. Stinchcombe, A. (1986) Contracts as Hierachical Arrangements. In: A. Stinchocombe and C. A. Heimer, (eds.) Organization Theory and Project Management. Oslo: Norwegian University Press. Strauss, A., and Corbin, J. (1990) Basics of Qualitative Research: Grounded Theory Procedures and Techniques. London: Sage. Terpstra, V., and David, K. (1985) The Cultural Environment of International Business. Southwestern Publishing.
361
Teubner, G. (1991) The Many-Headed Hudra: Networks as Higher Order Collective Actors. In: S. McCahery, S. Picciotto, and C. Scott, (eds.) Coporate Control and Accountability: Changing Structures and Dynamics. Authority F.: Authority F university Press. Thompson, P. J., and Sanders, S. R. (1998) Partnering Continuum, Journal of Management in Engineering, ASCE, 14 (no. 5), pp. 73-78. Thorsdottir, T. (2001) Merging Organizational Culture: Lessons for International Joint Ventures. In: M. H. Tayeb, (ed. International Business Partnership: Issues and Concerns. New York: Palgrave. Tierney, W. (1988) Organisation Culture in Higher Education, Journal of Higher Education, 59 (no. 1), pp. 2-21. Trompenaars, F. (1994) Riding the Waves of Culture: Understanding Diversity in Global Business. Chicago: Irwin. Tuchman, J. (1995) Technology Shift on the Way, Engineering News-Record, 19 June, pp. 9-10. Van de Ven, A. H., and Ferry, D. H. (1980) Measuring and Assessing Organizations. New York: Wiley. Vecchio, R. P., Hearn, G., and Southey, G. (1992) Organisational Behaviour: Life at Work in Australia. Sydney: Harcourt Brace Jovanovich. Walker, D., and Hampson, K. (2003) Enterprise Networks, Partnering and Alliancing. In: D. Walker and K. Hampson, (eds.) Procurement Strategies: A Relationship-Based Approach. UK: Blackwell Science Ltd. pp. 30-70. Walton, R. (1985) From Control to Commitment in the Workplace. In: Mange People, Not Personnel: Motivation and Performance Appraisal. Boston, MA: Harvard Business Review. pp. 89-106. Watson, K. (1999) Is Partnering Starting to Mean All Things to All People, Contract Journal, 397 (no. 6212), pp. 14-16. Weston, D. C., and Gibson, G. E. (1993) Partnering Project Performance in Us Army Corps of Engineers, Journal of Management in Engineering, ASCE, 9 (no. 4), pp. 410-425. Westwood, R. I. (1993) Organisational Behaviour: South East Asian Perspectives. Hong Kong: Longmans Asia.
362
Wikipedia (2005) Correlation Coefficient. Accessed on 12 November 2005, Available from World Wide Web: <http://en.wikipedia.org/wiki/Correlation_coefficient>. Williams, R. (1988) Keywords: A Vocabulary of Culture and Society. London: Fontana. Williamson, O. E. (1975) Markets and Hierarchies: Analysis and Antitrust Implications. New York: The Free Press. Williamson, O. E. (1985) The Economic Institutions of Capitalism: Firms, Markets, Relational Contracting. New York: The Free Press. Williamson, O. E. (1993) Calculativeness, Trust, and Economic Organization, Journal of Law and Economics, 36 (April), pp. 453-486. Wilson, L., and Wilson, H. (1994) Stop Selling, Starting Partnering: The New Thinking About Finding and Keeping Customers. New York: John Wiley and Sons. Winch, G. (2000) Innovativeness in British and French Construction: The Evidence from Transmanche-Link, Construction Management and Economics, 18, pp. 807-817. Winch, G., Millar, C., and Clifton, N. (1997) Culture and Organisation: The Case of Transmanche-Link, British Journal of Management, 8, 237-249. Wolfe, R. N. (1976) Trust, Anomie and the Locus of Control: Alienation of U.S. College Students in 1964, 1969, 1974, Journal of Social Psychology, 100, 151-172. Wong, E. S., Then, D., and Skitmore, M. (2000) Antecedents of Trust in Intra-Organizational Relationships within Three Singapore Public Sector Construction Project Management Agencies, Construction Management and Economics, 18 (no. 7), pp. 797-806. Wood, D. J., and Gray, B. (1991) Towards a Comprehensive Theory of Collaboration, Journal of applied Behavioral Science, 27 (no. 2), pp. 139-162. Wood, G., and McDermott, P. (1999a) Building on Trust: A Co-Operative Approach to Construction Procurement, Journal of Construction Procurement, 7 (no. 2), pp. 4-14. Wood, G., and McDermott, P., (1999b) Searching for Trust in the UK Construction Industry: An Interim View. In: S. O. Ogunlana ed. Conference of Searching for Trust in the UK Construction Industry: An Interim View,
363
CIB W92/TG23 Symposium - Profitable Partnering in Construction Procurement, Thailand. City: E&FN Spon. Wood, G., McDermott, P., and Swan, W. (2002) The Ethical Benefits of Trust-Based Partnering: The Example of the Construction Industry, Business Ethics: A European Review, 11 (no. 1), pp. 4-13. Wood, J., Wallace, J., and Zeffane, R. M. (2001) Organisational Behaviour: A Global Perspective. Australia: John Wiley & Sons Australia Ltd. Zairi, M. (1999) Managing Excellence Leadership, The TQM Magazine, 11 (no. 4), pp. 215-220. Zineldin, M., and Jonsson, P. (2000) An Examination of the Main Factors Affecting Trust/Commitment in Supplier-Dealer Relationships: An Empirical Study of the Swedish Wood Industry, The TQM Magazine, 12 (no. 4), pp. 245-265.