Effective Project Cost & Scheduling
Transcript of Effective Project Cost & Scheduling
WELCOME....WELCOME....Effective Project Cost &
Scheduling7 – 9 October 20087 – 9 October 2008
Etisalat - Dubai, U.A.E.Etisalat - Dubai, U.A.E.
Dr. Jamal AlBahar, AVS, PMPPROMIS - Dubai, U.A.E.
PROMISDelegates
Project Cash Flow Analysis& Budget
Estimating Cash Flow Profiles
& Developing a Project
The Importance of Project Budget The importance of Project Cost Control was
recognized as early as the 60’s, when DOD and NASA have successfully developed and implemented a guide for incorporating the cost control into PERT/CPM.
The theme is the integration and interrelation of project time and cost functions for the purpose of the planning and control functions.
Cost control cannot be achieved without a baseline budget against which actual cost performance is measured and compared, deviations are detected, causes are investigated, and proper actions are implemented.
The Importance of Project Budget In addition, the integration of time and cost enables
us to: Analyze the cash flow and prepare financial plans for
ensuring proper funds throughout the project duration. Detect and estimate financial deficits, and estimate the
cost of financing. This presentation focuses on integrating time and
cost for cash flow analysis and project planning. Project cost control and time cost relationship will be
the subject of subsequent presentations.
Types of Budgets
There are three types of budget that are usually used:
Strategic.
Tactical.
Operational.
Strategic Budgets Strategic budget defines the long-term activity of an
organization.
It’s generally updated annually.
Once the projects are underway, actual cost data are collected and compared to the budget in order to monitor the project performance.
Budget review helps control both goal setting and resource allocation.
Tactical Budgets Tactical – midrange - budget details the strategic
budget and usually covers a period ranging from one to two years.
It details the monthly expenditures in labor, materials, and overhead costs of each activity.
Updates are typically carried on a quarterly basis.
Operational Budgets Operational budget deals with costs of specific
activities that are being performed.
It usually spans a period of at most one year, and
covers the costs of resources required for the completion of each activity.
Preparing the Budget Preparing a budget usually is performed in
one of three ways: a top-down approach, a bottom-up approach, or an iterative approach.
Preparing the BudgetThe Top-Down Approach How ?
The top-down approach starts with the strategic budget as this defines the organization goals developed by top management.
It is then passed down to the functional managers to develop both the midrange (tactical) and the short-range (operational) budgets.
Problems: The difficulty in translating the strategic budget into tactical
and operational budgets. The reason behind that is that usually top management is not aware of every aspect of these projects when preparing these budgets.
Lower-level managers will compete instead of cooperating to secure their share of the budget.
Preparing the BudgetThe Bottom-Up Approach How ?
Letting each project manager develop his/her own proposal.
These proposals are then handed to functional managers to prepare the budget for their units, and finally
These are handed over to top management to integrate these budgets into a strategic one.
Problems: Reduces the top management control over the whole
process of budgeting.
Preparing the BudgetThe Iterative Approach How ?
This approach tries to alleviate the problems of previous approaches in an iterative way.
It starts at the top management level that sets a budget framework serving as a guideline for project managers as they prepare their budgets.
This process can undergo several iterations in order to fine-tune the process.
It increases the cooperation between different levels of management.
Problems: its duration, since going through different iterations
may take a long time.
Cost Budgeting: Aggregate individual activity estimates. Establish a total cost baseline. Used to measure and control cost over the project
time.
The S-curve: A time phased budget that is used to measure cost
performance against.
Cu
mu
lati
ve v
alu
e (
$)
Time
Budgeting throughTime-Cost Integration
5A4
10B8
15C3
20D3
25E7
35G1
30F6
0 2019
1610
1912
107
74
124
4TF = 0FF = 0
TF = 0FF = 0
TF = 0FF = 0
TF = 5FF = 3
TF = 3FF = 3
TF = 2FF = 0
TF = 0FF = 0
2019
1912
1913
124
12940
129
Name T(Wk.)
Direct cost($)
Direct cost$/Week
A 4 36,000 9,000
B 8 48,000 6,000
C 3 30,000 10,000
D 2 24,000 12,000
E 7 56,000 8,000
F 6 60,000 10,000
G 1 6,000 6,000
Total 20 260,000
Consider The following project schedule network and the activities direct costs table below.
Direct cost of each activity is assumed to be uniformly distributed over activity duration.
Indirect cost is estimated at $ 2,000 per week.
Early Schedule Cash Flow Diagram
0
50
100
150
200
250
300
0 5 10 15 20
Time (weeks)
Co
st
($ 1
,00
0)
Σ Direct $
Σ Indirect $
Σ Total $
Time (Working Days)Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Sum
A 9 9 9 9 36
B 6 6 6 6 6 6 6 6 48
E 8 8 8 8 8 8 8 56
G 6 6
C 10 10 10 30
D 12 12 24
F 12 12 12 12 12 60
Direct $ 9 9 9 9 28 28 16 18 18 18 18 18 8 8 8 8 8 8 8 6 260Indirect 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 40Total $ 11 11 11 11 30 30 18 20 20 20 20 20 10 10 10 10 10 10 10 8 300Σ Direct $ 9 18 27 36 64 92 108 126 144 162 180 198 206 214 222 230 238 246 254 260Σ Indirect $ 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40Σ Total $ 11 22 33 44 74 104 122 142 162 182 202 222 232 242 252 262 272 282 292 300
0
50
100
150
200
250
300
0 5 10 15 20
Late Schedule Cash Flow Diagram
0
50
100
150
200
250
300
0 5 10 15 20
Time (weeks)
Co
st
($ 1
,00
0)
Σ Direct $
Σ Indirect $
Σ Total $
Time (Working Days)Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Sum
A 9 9 9 9 36
B 6 6 6 6 6 6 6 6 48
E 8 8 8 8 8 8 8 56
G 6 6
C 10 10 10 30
D 12 12 24
F 12 12 12 12 12 60
Direct $ 9 9 9 9 6 6 6 6 6 16 28 28 8 8 20 20 20 20 20 6 260Indirect 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 40Total $ 11 11 11 11 8 8 8 8 8 18 30 30 10 10 22 22 22 22 22 8 300Σ Direct $ 9 18 27 36 42 48 54 60 66 82 110 138 146 154 174 194 214 234 254 260Σ Indirect $ 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40Σ Total $ 11 22 33 44 52 60 68 76 84 102 132 162 172 182 204 226 248 270 292 300
Baseline Schedule Cash Flow Diagram
0
50
100
150
200
250
300
0 5 10 15 20
Time (weeks)
Co
st
($ 1
,00
0)
Σ Direct $
Σ Indirect $
Σ Total $
Time (Working Days)Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Sum
A 9 9 9 9 36
B 6 6 6 6 6 6 6 6 48
E 8 8 8 8 8 8 8 56
G 6 6
C 10 10 10 30
D 8 8 8 24
F 6 6 12 12 12 12 60
Direct $ 9 9 9 9 16 16 16 14 14 14 12 12 20 20 20 20 8 8 8 6 260Indirect 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 40Total $ 11 11 11 11 18 18 18 16 16 16 14 14 22 22 22 22 10 10 10 8 300Σ Direct $ 9 18 27 36 52 68 84 98 112 126 138 150 170 190 210 230 238 246 254 260Σ Indirect $ 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40Σ Total $ 11 22 33 44 62 80 98 114 130 146 160 174 196 218 240 262 272 282 292 300
Cash Flow Diagrams
Cumulative Cost Vs Time
0
50
100
150
200
250
300
0 5 10 15 20
Time (weeks)
Cu
mu
lati
ve t
ota
l co
st (
$ 1,
000) Baseline
Early Schedule
Late Schedule
Time/Cost Analysis
It is standard practice in any project to estimate resource demands and activity duration in the most economical way.
These estimates are usually determined from the past experience or historical data obtained from similar projects.
Crashing a Project
CPM includes a way of relating the project schedule to the level of physical resources allocated to the project.
This allows the project manager to trade time for cost, or vice versa.
Two activity times & two costs are specified, if appropriate, for each activity
Critical Path Method - Crashing a Project/Cont.
The first time/cost combination is called normal, and the second set is referred to as crash
Normal times are “normal” time required to accomplish activity within normal conditions.
Crash times result from an attempt to expedite the activity by the application of additional resources.
Critical Path Method - Crashing a Project/Cont.
Careful planning is critical when attempting to expedite (crash) a project.
Expediting tends to create problems; and the solution to one problem often creates several more problems that require solutions.
Some organizations have more than one level of crashing.
The Time/Cost curve
Describes the reduction effect in the duration of an activity has on the cost of the activity.
The method of reducing the duration of an activity (normal point) to a crashed point is known as crashing.
Normal Point –The cost & time when the activity is performed in the normal way without extra resources such as overtime, improved equipment or other materials that could expedite the activity.
Crash Point - The cost & time when the activity is expedited by the use of extra resources, manpower, etc. No cost is spared to reduce the duration of the activity as much as possible
Example
A manual painting operation requiring 4 days at $400 per day.
With a special compressed airflow system, however, two workers can complete the job in 2 days for $1,000 per day.
The Normal point: the activity can be performed in 4 days for $400 x 4 = $1,600
The Crash point: in 2 days for $1,000 x 2 = $2,000.
Normal duration is associated with the lowest-cost option for the activity.
It is this value that is used in the preparation of the initial budget.
Time/Cost Curve
Cost
Time
Normal Point
Crash Point
NTCT
NC
CC
Minimum cost
Minimum time
Cost Slope = CC – NC / NT - CT
What is Crashing and How?
The process of reducing the project duration either to comply with contractual requirements, external constraints, and/or to reduce the project cost.
Accomplished by reducing the duration of one or more critical activities by assigning more resources to the activities or by adopting more productive technique/method for accomplishing the work.
What is Crashing and How?/Cont.
Crashing a critical activity means moving from the activity normal point towards the crash point. I.e., additional direct cost.
Among all the activities that can be crashed, the activity or combination of activities having minimum crashing cost are selected for crashing.
As critical activities are crashed, the critical path may change. None critical activities may become critical. If this takes place, then activities on the new critical path have also to be crashed.
Effect of Crashing a Project on the Project Cost Project cost consists of Direct & Indirect costs. Indirect costs are usually periodic costs which
is directly related to project duration. Delay in project completion time will increase the indirect costs.
When project is delayed, liquidated damages may be applied.
Some contracts call for incentives for early completion time.
Effect of Crashing a Project on the Project Cost/Cont.
Crashing or reducing the project duration increases the direct costs as we move from the normal time towards the crash time of the crashed activities.
The total project cost is thus sensitive to the project completion time.
There exists a project completion time at which the total project cost is minimum.
Project Time-Cost Relation
Point b is the project time at which the total project cost is minimum
Cost
Time
Indirect CostsDirect Costs
b
Total Costs
Crashing a Project Case Study (20)
Consider the following network of a project consisting of nine activities with a scheduled project duration of 32 weeks.
and the following table of time-cost data.
A7
70
1 8
101 0
B8
80
0 8
200 0
D11
187
8 19
401 0
E8
168
11 19
503 2
F10
188
6 18
600 0
H13
3118
19 32
801 1
I14
3218
18 32
900 0
Fin0
3232
32 32
1000 0St.
0
00
0 0
00 0
400
0
0
0
0
0 0
0
2
0
1
C9
167
11 20
304 0 G
12
2816
20 32
704 4
Name
Duration
EFES
LS LF
Number
TF FF None drivingRelationship
DrivingRelationship
Critical Path
Activity
Legend
ActivityActivity ttnn ttcc CnCn CcCc Allowable Allowable CrashCrash
Cc/weekCc/week
A 7 6 600 750 1 150
B 8 6 750 900 2 75
C 9 7 900 1100 2 100
D 11 8 1100 1400 3 100
E 8 5 850 1200 3 116.67
F 10 7 1000 1300 3 100
G 12 10 1300 1500 2 100
H 13 11 1400 1500 2 50
I 14 10 1500 2000 4 125
week/100$710
000,1300,1 day per cost Crashing
thatmeans Factivity for which,
tt
CC per week cost Crashing
cn
nc
Crashing a Project Crashing by 1 Wk Critical Path = B-F-I Project time = 32 weeks. Direct Cost = $ 9,400 Crashing options =
B @ $75/wk F @ $100/wk I @ $125/wk
A7
70
1 8
101 0
B8
80
0 8
200 0
D11
187
8 19
401 0
E8
168
11 19
503 2
F10
188
6 18
600 0
H13
3118
19 32
801 1
I14
3218
18 32
900 0
Fin0
3232
32 32
1000 0St.
0
00
0 0
00 0
400
0
0
0
0
0 0
0
2
0
1
C9
167
11 20
304 0 G
12
2816
20 32
704 4
Name
Duration
EFES
LS LF
Number
TF FF None drivingRelationship
DrivingRelationship
Critical Path
Activity
Legend
Activity t Allowable Crash
Cc/week
A 7 1 150
B 8 2 75
C 9 2 100
D 11 3 100
E 8 3 116.67
F 10 3 100
G 12 2 100
H 13 2 50
I 14 4 125
Decision: Crash B by 1 week @ $75/wkDecision: Crash B by 1 week @ $75/wk
Crashing a Project Crashing by Another 1 Wk. Critical Path(s) = B-F-I, A-D-H Project time = 31 weeks. Direct Cost = $ 9,475 Crashing should be of activities on
both critical paths. On each critical path, select the
activity of minimum crashing cost.
Name
Duration
EFES
LS LF
Number
TF FF None drivingRelationship
DrivingRelationship
Critical Path
Activity
Legend
Activity t Allowable Crash
Cc/week
A 7 1 150
B 8 1 75
C 9 2 100
D 11 3 100
E 8 3 116.67
F 10 3 100
G 12 2 100
H 13 2 50
I 14 4 125
Decision: Crash B & H by 1 week @ $125/wkDecision: Crash B & H by 1 week @ $125/wk
A7
70
0 7
100 0
B7
70
0 7
200 0
D11
187
7 18
400 0
E8
157
10 18
503 3
F10
177
6 18
600 0
H13
3118
18 31
801 1
I14
3117
18 32
900 0
Fin0
3131
31 31
1000 0St.
0
00
0 0
00 0
300
0
0
0
0
0 0
0
3
0
0
C9
167
10 19
303 0 G
12
2816
19 31
703 3
Crashing a Project Crashing B & H by 1 Wk. Critical Path(s) = B-F-I, A-D-H Project time = 30 weeks. Direct Cost = $ 9,600 Crashing should be of activities
on both critical paths. B cannot be further crashed.
Name
Duration
EFES
LS LF
Number
TF FF None drivingRelationship
DrivingRelationship
Critical Path
Activity
Legend
Activity t Allowable Crash
Cc/week
A 7 1 150
B 8 0 75
C 9 2 100
D 11 3 100
E 8 3 116.67
F 10 3 100
G 12 2 100
H 13 1 50
I 14 4 125
Decision: Crash F & H by 1 week @ $150/wkDecision: Crash F & H by 1 week @ $150/wk
A7
70
0 7
100 0
B6
60
0 6
200 0
D11
187
7 18
400 0
E8
146
10 18
504 4
F10
166
6 16
600 0
H12
3018
18 30
800 0
I14
3016
16 30
900 0
Fin0
3030
30 30
1000 0St.
0
00
0 0
00 0
200
0
0
0
0
0 0
0
4
0
0
C9
167
9 18
302 0 G
12
2816
18 30
702 2
Crashing a Project Crashing F & H by 1 Wk. Critical Path(s) = B-F-I, A-D-H Project time = 29 weeks. Direct Cost = $ 9,750 Crashing should be of activities
on both critical paths. H & B cannot be further crashed
Name
Duration
EFES
LS LF
Number
TF FF None drivingRelationship
DrivingRelationship
Critical Path
Activity
Legend
Activity t Allowable Crash
Cc/week
A 7 1 150
B 8 0 75
C 9 2 100
D 11 3 100
E 8 3 116.67
F 10 2 100
G 12 2 100
H 13 0 50
I 14 4 125
Decision: Crash D & F by 1 week @ $200/wkDecision: Crash D & F by 1 week @ $200/wk
A7
70
0 7
100 0
B6
60
0 6
200 0
D11
187
7 18
400 0
E8
146
10 18
504 4
F9
156
6 15
600 0
H11
2918
18 29
800 0
I14
2915
15 29
900 0
Fin0
2929
29 29
1000 0St.
0
00
0 0
00 0
100
0
0
0
0
0 0
0
4
0
0
C9
167
8 17
301 0 G
12
2816
17 29
701 1
Crashing a Project Crashing D & F by 1 Wk.
Critical Path(s) = B-F-I, A-D-H, and A-C-G
Project time = 28 weeks. Direct Cost = $ 9,950 Crashing should be of activities
on the three critical paths. A is located on 2 critical paths.
Name
Duration
EFES
LS LF
Number
TF FF None drivingRelationship
DrivingRelationship
Critical Path
Activity
Legend
Activity t Allowable Crash
Cc/week
A 7 1 150
B 8 0 75
C 9 2 100
D 11 2 100
E 8 3 116.67
F 10 1 100
G 12 2 100
H 13 0 50
I 14 4 125
Decision: Crash A & F by 1 week @ $250/wkDecision: Crash A & F by 1 week @ $250/wk
A7
70
0 7
100 0
B6
60
0 6
200 0
D10
177
7 17
400 0
E8
146
9 17
503 3
F8
146
6 14
600 0
H11
2817
17 28
800 0
I14
2814
14 28
900 0
Fin0
2828
28 28
1000 0St.
0
00
0 0
00 0
000
0
0
0
0
0 0
0
3
0
0
C9
167
7 16
300 0 G
12
2816
16 28
700 0
Crashing a Project Crashing A & F by 1 Wk.
Critical Path(s) = B-F-I, A-D-H, and A-C-G
Project time = 27 weeks. Direct Cost = $ 10,200 Crashing should be of activities
on the three critical paths. A & F cannot be further crashed
Name
Duration
EFES
LS LF
Number
TF FF None drivingRelationship
DrivingRelationship
Critical Path
Activity
Legend
Activity t Allowable Crash
Cc/week
A 7 0 150
B 8 0 75
C 9 2 100
D 11 2 100
E 8 3 116.67
F 10 0 100
G 12 2 100
H 13 0 50
I 14 4 125
Decision: Crash I, D, & (C or G)Decision: Crash I, D, & (C or G) by 1 week @ $325/wkby 1 week @ $325/wk
A6
60
0 6
100 0
B6
60
0 6
200 0
D10
166
6 16
400 0
E8
146
8 16
502 26
F7
136
6 13
600 0
H11
2716
16 27
800 0
I14
2713
13 27
900 0
Fin0
2727
27 27
1000 0St.
0
00
0 0
00 0
000
0
0
0
0
0 0
0
2
0
0
C9
156
6 15
300 0 G
12
2715
15 27
700 0
Example Project Time-Cost Trade-offs
Consider: Indirect Cost of $200
per week, Liquidated damages
of $500 per week for project duration beyond 30 weeks, and
No incentive plan
Project Duration (wk) 26 27 28 29 30 31 32
Direct Cost ($) 10,525 10,200 9,950 9,750 9,600 9,475 9,400
Indirect Cost ($) 5,200 5,400 5,600 5,800 6,000 6,200 6,400
Liquidated Damages ($) 0 0 0 0 0 500 1,000
Incentives ($) 0 0 0 0 0 0 0
Total Cost ($) 15,725 15,600 15,550 15,550 15,600 16,175 16,800
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
25 26 27 28 29 30 31 32
Project Duration (w eeks)
Pro
ject C
ost ($
)
Direct Cost ($)Indirect Cost ($)Liquidated Damages ($)Total Cost ($)
Earned Value Management (EVM)
EVM is a project performance measurement technique that integrates scope, time, and cost data.
Given a baseline (original plan plus approved changes), you can determine how well the project is meeting its goals.
You must enter actual information periodically to use EVM.
More and more organizations around the world are using EVM to help control project costs.
The EV System
To set up the EV system
1. Establish the WBS to divide the project into manageable portions.
2. Identify the activities to be scheduled that represent the entire project.
3. Allocate the costs to be expended on each activity.
4. Schedule the activities over time.
5. Tabulate, plot & analyze the data to confirm that the plan is acceptable.
To use the information generated by the EV calculations:
1. Update the schedule by reporting activity progress.
2. Enter the actual costs on the activities.
3. Execute the Earned Value calculations, print and plot the reports and charts.
4. Analyze the data & write the performance narrative.
Earned Value Technique:
Compares reality to what was planned originally (baseline).
Used for cost and schedule control. Given project status today, report actual
progress variances. Forecast future outcomes
(expectations). Used for ETC and EAC.
Output is performance measurements values.
Earned Value Management Terms
The planned value (PV), formerly called the budgeted cost of work scheduled (BCWS), also called the budget, is that portion of the approved total cost estimate planned to be spent on an activity during a given period.
Actual cost (AC), formerly called actual cost of work performed (ACWP), is the total of direct and indirect costs incurred in accomplishing work on an activity during a given period.
The earned value (EV), formerly called the budgeted cost of work performed (BCWP), is an estimate of the value of the physical work actually completed.
EV is based on the original planned costs for the project or activity and the rate at which the team is completing work on the project or activity to date.
Rate of Performance
Rate of performance (RP) is the ratio of actual work completed to the percentage of work planned to have been completed at any given time during the life of the project or activity.
Brenda Taylor, Senior Project Manager in South Africa, suggests using this approach for estimating earned value.
For example, suppose the server installation was halfway completed by the end of week 1. The rate of performance would be 50 percent (50/100) because by the end of week 1, the planned schedule reflects that the task should be 100 percent complete and only 50 percent of that work has been completed.
TRADITIONAL COST ANALYSIS
Back to our S-curveC
um
ula
tive v
alu
e (
$)
Time
Actual cost (AC)
Earned Value (EV)
Planned Value (PV)
Budget At Completion (BAC)
Earned Value Performance Measurement
EV measurement should enable a: Clearer measure of the project work
accomplished, Better forecasts of the likely task &
project completion dates & associated costs.
Earned Value Principles
EV also known as the Budgeted Cost of Work Performed (BCWP).
EV is based on assigning a value to the achievement of project work. Ideally, achievement is in terms of milestones &
deliverables. The value is usually monetary but can be expressed
in any appropriate units such as man-hours.
Cost Performance Analysis
Cost Variance (CV) = EV - AC
Cost Performance Index (CPI) =
Where: AC is the actual cost of work performed; and EV = Planned Value to Date * RP
AC
EV
Schedule Performance analysis
Schedule Variance (cost-based) = EV - PV Schedule Variance (time-based) = OD - ATE Schedule Performance Index (SPI)
Cost based SPI =
Time based SPI =
Where: PV is the budgeted (planned) cost of work scheduled. OD is the Original Duration planed for the work to
date; ATE is the Actual Time Expended for the work to
date.
PV
EV
ATE
OD
Forecasting CostBased on Earned Value Statistics
EAC = AC +
Where: EAC is the estimated cost at completion BAC is the budget at completion
(total planned cost of work).
CPI
EV-BAC
Forecasting TimeBased on Earned Value Statistics
Planned Total Project Time = PTPT Schedule Variance (time) = OD - ATE Planned Time to Complete (PTC) = PTPT - OD
Estimated Actual Time to Complete =
Estimated Total Project Time = ATE +
SPI
PTC
SPI
PTC
Time & Cost Forecasting
ECTC = Estimated Cost To Complete
BAC = Budget At Completion
BCWP = Budget Cost of Work Performed
ACWP = Actual Cost of Work Performed
BCWS = Budget Cost of Work Scheduled
OD = Original Duration planned for work to date
ATE = Actual Time Expended for work to date
PTPT = Planned Total Project Time
Project Portfolio Management
Many organizations collect and control an entire suite of projects or investments as one set of interrelated activities in a portfolio.
Project portfolio management has five levels:1. Put all your projects in one database.
2. Prioritize the projects in your database.
3. Divide your projects into two or three budgets based on type of investment.
4. Automate the repository.
5. Apply modern portfolio theory, including risk-return tools that map project risk on a curve.
Benefits of Portfolio Management
Schlumberger saved $3 million in one year by organizing 120 information technology projects into a portfolio.
Using Software to Assist in Cost Management
Spreadsheets are a common tool for resource planning, cost estimating, cost budgeting, and cost control.
Many companies use more sophisticated and centralized financial applications software for cost information.
EV Analysis - ExampleTarget Schedule:
Activity Start Duration % CompleteA 0 2 100B 2 8 60C 6 4 50D Total =EFG
Total =
Activity BT BC % BCWP BTWP ATWP ACWP ST BCWS Time Cost Schedule TV CV SVA 2 1,000 100 1,000 2 2 900 2 1,000 100% 111% 100% 0 -100 0B 17 3,400 60 2,040 10 8 2,000 8 1,600 128% 102% 128% -2.2 -40 -440C 3 9,000 0 0 0 0 0 2 6,000 0% 6000D 5 5,000 50 2,500 3 4 3,200 5 5,000 63% 78% 50% 1.5 700 2500E 6 12,000 0 0 0 0 0 0 0F 2 1,000 0 0 0 0 0 0 0G 1 1,000 0 0 0 0 0 0 0
Totals: 32,400 5,540 6,100 13,600 91% 41% 560 8060
Actual at end of day 10
Activity C is expected to start after 3 days from
Cost
12,0001,000
6,100
1,00032,400
Efficiency Variance
now and is expected to last for 5 days at a costof 2,000 $ per day .
Table of Efficiencies and Variances of Activities and of the Project.
Budget
1,0003,4009,0005,000
Cost900
2,0003,200
E5
13 19
TF=FF=0
G1
19 20
TF=FF=0
C3
118
TF=FF=2
0 2
D5
94
TF=4, FF=2
F2
1311
TF=FF= 6
B17
2 19
TF=FF= 0
TF=FF=0
A2
EV Forecast - Example
0
G1
C5
DD0
E5
130 83* 8 13 14
TF=FF=0 TF=FF=0
64 40
TF=4, FF=0 TF=FF=7
TF=FF=0
B5
0 5
TF=FF=8
Time to complete the project = 14Cost to complete the project =
= 1,333+10,000+2,000+12,000+1,000+1,000 = 27,333
D4
F2
Performance Analysis Plot
A useful way of using earned value data is to plot CPI as a function of SPI (cost based) through time, to:
• reveal the direction of the task and of the whole project.
• demonstrate the effect of recovery action.
Projects Selection
Remember: PM are not accountants! But…
Need to do some cost related duties.
Selection between alternatives techniques are very useful to know.
Uncertainty makes risk management an essential and important task from onset of project to finishing date.
Some Project Selection Methods
1. Net Present Value (NPV)
2. Internal Rate of Return (IROR)
3. Payback Period (PBP)
4. Benefit Cost Ratio (BCR)
Selection Methods
Net Present Value (NPV)
Considers the time value of money.
NPV= PV (income)- PV (cost).
Always chose the one with higher NPV.
Formula
P P ==FF
(1 +(1 + r r))nn
wherewhere
F = future value of the investment at the end of n periods
P = amount invested at the beginning, called the principal
r = periodic interest rate (discount rate)n = number of time periods for which the
interest compounds
Selection Methods Cont….
Internal Rate of Return Maths is complex. i at which
PV of inflows = PV of outflows. Always chose the one with highest IRR
975.57 20
-745.03 18NPV = 77.82
-360.47 151815.77 32005
77.82 12762.62 12004
404.61 101067.67 15003
763.008717.679002
1368.55714.298001
26000-5000 - 50000
NPVIR (i)PV ( i = 12% )
CASHFLOW
EOY
Selection Methods Cont….
Payback Period (PBP) Simple method. When do I get my money back? Ignores the time value of money.
Chose the one with shortest PBP.
Inflows above $2m/month to break even
Benefit to Cost Ratio (BCR) Usually used for public projects.
Calculate all benefits and costs and work out the ratio between them.
BCR could be =, > or <1
Would like a BCR = 1.3
Selection Methods Cont….
The Exit Strategy
Steps in completing the project Controlling costs & schedule late in the
project Scope verification Schedule Control Cost Control Contract closeout Administrative closure
Contract Closure
Completing & settling each contract Resolution of any open items Closing each project or project phase
contract
Contract Closure
Involves both product verification & administrative closeout.
During contract closeout, the PM must perform: Product verification: insuring that all of the
work was completed. Administrative closure: documenting &
archiving final results.
Procurement Audits (tools & Techniques)
Can provide valuable lessons learned by identifying successes & failures that warrant transfer to other procurements within the project & other projects.
Contract Administration
Managing the contract & relationships between the buyer & seller
Reviewing & documenting how a seller is performing or has performed
Managing contract-related changes
Managing contractual relationship with the project outside buyers
Contract Change Control System (tools & Techniques)
Includes: Supporting paperwork Tracking systems (such as the change control
log) Dispute resolution procedures (such as when
to escalate) Approval levels required (based on cost of the
change, impact, etc.)
Buyer-Conducted Performance Review (tools & Techniques)
This is a meeting where all the available data is brought together to see if the seller is performing.
Often the seller is present to review the data and most importantly talk about what the buyer can do differently to help the work along.
The purpose of this review is to determine & recommend needed corrective & preventive actions and to request formal changes.
Claims Administration (tools & Techniques)
A claim is an assertion that the buyer did something that has hurt the seller and the seller asking for compensation.
Another way of looking at claims is that they are a form of seller’s change requests. Claims can get nasty.
Many claims are not resolved until the work is completed.
Record Management System (tools & Techniques)
On many projects, every e-mail, every payment, every written and oral communication must be recorded, kept and stored.
On other projects the weather each day & the number of people on the buyer’s property each day may also be required.
Whatever is appropriate for the particular industry and project is kept.
Helpful to unresolved claims, legal actions, or even to satisfy insurance needs.
Administrative Closure
Must be done any time a project or phase ends.
For example, if a project is canceled prior to completion, the project needs to enter administrative closure.
This is often a good test as to how committed an organization is to the disciplines of project management.
Administrative Closure
Several key things must happen in this process, including: Documenting performance Assembling all project documentation, memos,
communications, etc. Finalizing all payments Collecting and documenting lessons learned Releasing resources
Administrative Closure Includes:
Project Archives
Creating a complete set of indexed project records for the project.
Project Closure
Verifying that the project has met all or the customer's requirements.
Lessons Learned
Lessons Learned Include:
Documenting what variances occurred on the project, and what the underlying causes were.
Documentation should also include what was done to correct the project, and
what was learned by the performing organization to avoid the problems that were encountered.
Results from Lessons Learned Include:
Update of the lessons learned knowledge base
Input to knowledge management system
Updated corporate policies, procedures, & processes
Improved product & service improvements
Update to the risk management plan
Over time, lessons learned are often incorporated into
best practices.
THANK YOU ALL …