Effect of Autonomous Maintenance (AM) on Plant Reliability ...
Transcript of Effect of Autonomous Maintenance (AM) on Plant Reliability ...
EFFECT OF AUTONOMOUS MAINTENANCE ON PALNT RELIABILITY AND
OVERALL EQUIPMENT EFFICIENCY (A CASE STUDY OF LAFARGE SURMA
CEMENT LIMITED, BANGLADESH)
BY
PROSENJIT DAS
A Thesis work submitted in partial fulfillment of the requirements for the degree of Master of
Advanced Engineering Management
Department of Industrial and Production Engineering
Bangladesh University of Engineering & Technology
APRIL, 2011
ii
CERTIFICATE OF APPROVAL
The thesis work titled " Effect of Autonomous Maintenance on Plant Reliability and Overall
Equipment Efficiency (A case study of Lafarge Surma Cement Ltd., Bangladesh)", submitted
by Prosenjit Das, Roll No.- 100508135, Session- April, 2005 has been accepted as
satisfactory in partial fulfillment of the degree of Master of Advanced Engineering
Management on 16 April, 2011
BOARD OF EXAMINERS
Dr. A. K. M. Masud Professor & Head Department of Industrial and production Engineering BUET, Dhaka-1000
Chairman(Supervisor)
Dr. Abdullahil Azeem Professor Department of Industrial and production Engineering BUET, Dhaka-1000
Member
Dr. Zohrul Kabir Professor Department of MCE, IUT, Gazipur-1704
Member
Department of Industrial and Production Engineering Bangladesh University of Engineering & Technology
Dhaka-1000, Bangladesh.
APRIL, 2011
iii
CANDIDATE’S DECLARATION
It is hereby declared that this thesis or any part of it has not been submitted elsewhere for the
award of any degree or diploma.
Prosenjit Das
iv
ACKNOWLEDGEMENT
It is a great pleasure for me to acknowledge the assistance and contributions of many
individuals in making this dissertation a success.
First and foremost, I would like to thank my supervisor, Dr.A.K.M. Masud, Professor &
Head of IPE, for his assistance, ideas, and feedbacks during the process in doing this
dissertation. Without his guidance and support, this dissertation can not be completed on
time.
Secondly, it is a pleasure to express my thanks to all employees of LSC for their cooperation
and heartiest support to collect all the data. I also like to convey my special thanks to Mr.
Harpal Singh, Sr. Manager- Maintenance and Mr. Ashim K Mondal, Asst. Manager-
Methods, for their constant effort to make me knowledgeable about the incident management
system in LSC. Without their support it was not possible to collect the incident data and
analyze them and understand the total maintenance process that is in practice. I also like to
express my gratitude to Mr. Arun K Saha for his cordial help to access the production budget
which is also considered a confidential document form the company business point of view.
I also like to express my gratitude to Mr. Chang J Song, Plant Manager for his kind approval
to access all the data those are use for internal performance management and allow me to
participates in the reliability committee meetings as well
Lastly, I wish to express my sincere gratitude to my family for their encouragement and
moral support.
v
ABSTRACT
This thesis work highlights one of the powerful approaches to improve reliability and
predictability of the plant using Autonomous Maintenance (AM), a pillar of Total Productive
Maintenance (TPM). This explains the underlying concepts, issues, and benefits of AM
implementation through a case study. The company discussed in this study is a Multinational
Company (MNC), manufacturing cement in Bangladesh. Lafarge Surma Cement Limited
(LSCL) has a good organizational structure to support the AM but lack of understanding they
are paying a lot. In this thesis work I collected all the stoppages and segregated them in
different classes. Then all the incidental stoppages were analyzed and identified the stoppages
which could be avoided if the AM was in place. It was also highlighted what is the effect of
those incidental stoppages on Plant Reliability and on Overall Plant Effectiveness. Some
tools were developed to support the LSCL for better management of the stoppages and also
provided some tools to help them implementing the AM. Finally some recommendations
were made based on the findings.
vi
TABLE OF CONTENTS
CERTIFICATE OF APPROVAL ...................................................................................................................................... II
CANDIDATE‘S DECLARATION ................................................................................................................................... III
ACKNOWLEDGEMENT ............................................................................................................................................... IV
ABSTRACT ..................................................................................................................................................................... V
TABLE OF CONTENTS ................................................................................................................................................ VI
LIST OF TABLES .......................................................................................................................................................... IX
LIST OF FIGURES .......................................................................................................................................................... X
CHAPTER-1: INTRODUCTION .......................................................................................................................................1
INTRODUCTION .............................................................................................................................................................1
1.1 BACKGROUND .................................................................................................................................................1
1.2 PRESENT STATE OF THE PROBLEM ..............................................................................................................1
1.3 IDENTIFICATION AND ASSESSMENT OF OPTION .......................................................................................2
1.4 OBJECTIVE AND SCOPE OF THE STUDY .......................................................................................................4
1.4.1 OBJECTIVE ...................................................................................................................................................4
1.4.2 SCOPE............................................................................................................................................................4
CHAPTER-2: LITERATURE REVIEW .............................................................................................................................6
2.1 OVERVIEW OF TPM IN PROCESS INDUSTRY ...............................................................................................6
2.2 PILLARS OF TPM ..............................................................................................................................................8
2.3 AUTONOMOUS MAINTENANCE ................................................................................................................... 14
2.3.1 EQUIPMENT SELECTION AND TEAM FORMATION .............................................................................. 16
2.3.2 INITIAL CLEANING ................................................................................................................................... 19
2.3.3 ELIMINATE SOURCES OF CONTAMINATION AND INACCESSIBLE AREAS ....................................... 19
2.3.4 ESTABLISH CLEANING AND INSPECTION STANDARDS ...................................................................... 20
2.3.5 ESTABLISHING BASIC EQUIPMENT CONDITIONS ................................................................................ 20
2.3.6 EDUCATION/TRAINING TO OPERATORS AND TECHNICIANS ............................................................ 22
2.4 FEATURES OF PROCESS INDUSTRIES ......................................................................................................... 22
2.5 MAXIMIZING PRODUCTION EFFECTIVENESS IN PROCESS INDUSTRIES .............................................. 25
2.5.1 PRODUCTION EFFECTIVENESS IN PROCESS INDUSTRY ..................................................................... 25
vii
2.5.2 PROCESSING LOSSES ................................................................................................................................ 25
2.5.3 OVERALL EQUIPMENT EFFECTIVENESS ............................................................................................... 27
2.5.4 MAXIMIZING THE EFFECTIVENESS OF PRODUCTION INPUTS ........................................................... 29
CHAPTER-3: OVERVIEW OF LSCL.............................................................................................................................. 30
3.1 LAFARGE SURMA CEMENT- AT A GLANCE ............................................................................................... 30
3.2 PROCESS DESCRIPTION ................................................................................................................................ 30
3.2.1 CRUSHING SYSTEM .................................................................................................................................. 31
3.2.2 RAW GRINDING SYSTEM ......................................................................................................................... 31
3.2.3 BURNING SYSTEM .................................................................................................................................... 33
3.2.4 FINISH GRINDING SYSTEM ...................................................................................................................... 34
3.2.5 PACKING & DISPATCH ............................................................................................................................. 35
3.3 MAINTENANCE DEPARTMENT-LSC ............................................................................................................ 35
3.4 MAINTENANCE PHILOSOPHY ...................................................................................................................... 39
3.5 DOWNTIME AND KPI IN LSCL ...................................................................................................................... 40
3.5.1 DOWN TIME RECORDING ......................................................................................................................... 40
3.5.2 OPERATING HOURS .................................................................................................................................. 41
3.5.3 HOURS OF STOPPAGE ............................................................................................................................... 41
3.5.4 PERFORMANCE INDICATORS FOR LSC .................................................................................................. 42
3.5.5 CLASSIFICATION OF DOWNTIME ........................................................................................................... 44
CHAPTER-4: DATA COLLECTION AND ANALYSIS .................................................................................................. 48
4.1 DATA COLLECTION ....................................................................................................................................... 48
4.2 STOPPAGES ANALYSIS ................................................................................................................................. 50
4.2.1 STOPPAGES DISTRIBUTION BY DISCIPLINE.......................................................................................... 50
4.2.2 PARETO ANALYSIS ................................................................................................................................... 50
4.2.3 ROOT CAUSE ANALYSIS (RCA) ............................................................................................................... 57
4.3 EFFECT OF AM ON RELIABILITY ................................................................................................................. 59
4.3.1 BURNING SYSTEM .................................................................................................................................... 59
4.3.2 RAW GRINDING SYSTEM ......................................................................................................................... 59
4.3.3 FINISH GRINDING SYSTEM (LINE-1) ....................................................................................................... 60
4.3.4 FINISH GRINDING SYSTEM (LINE-2) ....................................................................................................... 61
4.4 EFFECT OF AM ON OEE ................................................................................................................................. 62
viii
4.4.1 BURNING SYSTEM .................................................................................................................................... 62
4.4.2 RAW GRINDING SYSTEM ......................................................................................................................... 62
4.4.3 FINISH GRINDING SYSTEM (LINE-1) ....................................................................................................... 63
4.4.4 FINISH GRINDING SYSTEM (LINE-2) ....................................................................................................... 64
CHAPTER-5: RESULTS AND DISCUSSIONULTS AND DISCUSSION ........................................................................ 65
5.1 RESULTS.......................................................................................................................................................... 65
5.2 DISCUSSION .................................................................................................................................................... 66
CHAPTER-6: CONCLUSION AND RECCCOMMENDATION ...................................................................................... 77
6.1 CONCLUSION.................................................................................................................................................. 77
6.2 RECOMMENDATION ...................................................................................................................................... 82
REFERENCES ................................................................................................................................................................ 83
APPENDIX ..................................................................................................................................................................... 85
ix
LIST OF TABLES
Table No. Title Page
3.1 Example of RF & UF Calculation 44
4.1 Sample data analysis for proper allocation of incidental stoppages 49
4.2 Pareto analysis of stoppages in Burning System 52
4.3 Pareto analysis of stoppages in Raw Grinding System 53
4.4 Pareto analysis of stoppages in Finish Grinding System (Line-1) 54
4.5 Pareto analysis of stoppages in Finish Grinding System (Line-2) 56
5.1 Present status of plant performance and effect of AM 67
6.1 Checkpoints for Nut & Bolts Inspection 74
6.2 Checkpoints for Electrical Equipment Inspection 74
6.3 Checkpoints for Hydraulic Equipment Inspection 76
6.4 Checkpoints for Pneumatic Equipment Inspection 77
6.5 Checkpoints for Transmission Equipments Inspection 78
6.6 Lubrication points inspection checkpoints 78
6.7 Checkpoints for General Purpose Equipment Inspection 79
x
LIST OF FIGURES
Figure No. Title Page
2.1 Pillars of TPM 9
2.2 Causes and accelerated deterioration 21
2.3 Production Effectiveness in Process Industries 25
2.4 Eight Major Losses 27
3.1 Raw Material Extraction and Crushing 32
3.2 Vertical Raw Mill 33
3.3 Raw Mill Feed Preparation 33
3.4 Kiln 35
3.5 Coolax Cooler 35
3.6 Finish Grinding Process 36
3.7 Organizational Structure 37
3.8 Maintenance Function 38
3.9 Organization Chart-Maintenance 39
3.10 Organization Chart-Mechanical Maintenance 39
3.11 Organization Chart- Methods 40
3.12 Organization Chart-Instrumentation & Controls and Maintenance 40
3.13 ADAP 42
4.1 Distribution of Stoppages by percentage among different departments 51
4.2 Pareto Analysis for Burning System 52
4.3 Pareto Analysis for Raw Mill Grinding System 54
4.4 Pareto Analysis for Finish Grinding System (Line-1) 55
4.5 Pareto Analysis for Finish Grinding System (Line-2) 57
4.6 RCA Sample 59
5.1 Present status of plant RF and effect of AM 70
5.1 Present status of plant OEE and effect of AM 70
6.1 Distribution of maintenance activities within the discipline 81
xi
DEFINITIONS AND ABBREVIATIONS
AM Autonomous Maintenance
Apparent Cause The Equipment which causes the stoppages of the
process system CHSIM Cummulitative hours of stoppages due to Mechanical
incidents CHSIE Cummulitative hours of stoppages due to Electrical
incidents CHSIF Cummulitative hours of stoppages due to Production
incidents CHSIO Cummulitative hours of stoppages due to others
incidents Cause Underlying reason that cause the equipment stoppage
CHS Cummulitative hours of Stoppages
CHSI Cummulitative hours of stoppages due to incident
CHSP Cummulitative hours of Planned Stoppages
CHSC Cummulitative hours of stoppages due to Circumstance
WH Working Hours
LSCL Lafarge Surma Cement Limited
MTTR Mean Time To Repair
MTBF Mean Time Between Failure
MMT Million Metric Ton
NS Number of Stoppages
NSFI Number of Stoppages due to Incident
NSFP Number of Scheduled stoppages
NSFC Number of stoppages due to Circumstances
NSFIM Number of stoppages due to Mechanical Incident
NSFIE Number of stoppages due to Electrical Incident
NSFIF Number of stoppages due to Production Incident
NSFIO Number of stoppages due to Other Incident
OEE Overall Equipment Efficiency.
OH Operating Hours
PD Work Generated by Predictive Maintenance)
PG Work Generated by Preventive Maintenance
PF Performance Factor.
PM Preventive Maintenance
xii
RF Reliability Factor
RCA Root Cause Analysis
TPM Total Productive Maintenance
TQM Total Quality management
SOP Standard Operating Procedure
UF Utilization Factor
316FA01, 416LU01 Primary Air Fan, Lubrication Unit for Cement Mill 1
Drive (Lafarge codification system)
1
CHAPTER-1: INTRODUCTION
INTRODUCTION
1.1 Background
Lafarge Surma Cement Ltd. (LSCL) is an integrated cement manufacturing company in
Bangladesh. Lafarge Group of France, one of the world leaders in building materials is the
majority shareholder of LSCL. Although LSCL competes with a large number of cement
manufacturers in the country, it has a few unique advantages. While all other manufacturers
import clinker, only LSCL has the capacity to manufacture clinker in-house using limestone
from a owned quarry. [1]
In terms of cement production, Bangladesh ranks about 40th in the world. Cement
manufacturing is a highly fragmented business in Bangladesh. During the 1990s, many small
cement companies entered the market as soon as the government started encouraging local
production with favorable tariff differential. Currently 123 companies are listed as cement
manufacturers in the country. Of them 63 have actual production capacity while about 30 do
not have any production at all. The current installed capacity is 22.0 MMT. However,
because of supply constraints for power and clinkers, the actual capacity is about 17.0
MMT.[2] Bangladesh is one of the few sizable producers of cement that does not have its
own supply of limestone and cannot produce clinkers domestically. Except for LSCL, all
other cement manufacturers of Bangladesh are in essence grinders of clinkers. There is a
strong tax-support for local cement manufacturers in Bangladesh. They receive a significant
import tax advantage over finished cement (about 15% for raw-materials versus 100% for
finished cement). This tariff differential helps most to operate profitably. A change in the
tariff structure is not anticipated in the near future [2].
1.2 Present state of the problem
The industry realized about 20% sales growth in 2009, mostly because of the latent demand
from last years. On a secular basis, ongoing demand growth is expected to be about 8%, the
outlook for the cement industry seems positive for a number of reasons. First, the government
seems to be on a war footing to increase both the amount and the efficiency of spending in
2
social and physical infrastructure under the Annual Development Programs (ADP). Second,
the private sector is also energized because of certain tax advantages for undeclared funds if
they are invested in real estate. Third, a number of large infrastructure construction projects
(such as the Padma Bridge) are on the horizon. Both the government and the private sector
are soliciting funds for such projects. If implemented, these projects would significantly
improve demand for construction materials.
The largest 10 cement manufacturers hold about 70% of the market share. While Heidelberg,
Holcim and Cemex are the leaders among multinational cement manufacturers; Shah, Akij
and MI are the leading domestic manufacturers. Shah cement is the market leader with close
to 12% of the market share, closely followed by Heidelberg with about 10% of the market
share.[2]
Being the market leader in the building material on the glove LSCL is having only 8% (2008)
market share in the Bangladesh cement market. To cost recovery they need more revenue
which can be achieved by lowering the production cost or/and increasing the sales i.e.
capturing more market share. Lafarge is enjoying a superior supply change system specially
in the distribution system as the plant is located on the bank of Surma river with a
experienced and well structured marketing team which can ensure the creating demand for
their product ―SuperCreate‖ in near future. So now the challenge is to increase the
production to meet the increasing market demand as well as lowering the manufacturing cost
[1].
1.3 Identification and assessment of option
Although LSCL competes with a large number of cement manufacturers in the country, it has
a few unique advantages. While all other manufacturers import clinker, only LSCL has the
capacity to manufacture clinker in-house using limestone from a owned quarry. This provides
the company the benefit of significantly higher gross margins. Because of its affiliation with
Lafarge worldwide, LSCL is considered a leading brand in a competitive market, and it
enjoys price premium because of a perceived quality leadership. Lastly, Lafarge has one of
the largest production plant in the industry (1.2MT, expandable to 1.5MT) [1]. In a
fragmented industry where smaller producers are being gradually squeezed out of the market,
LSCL has the advantage of scale. As and when consolidation starts in the market, LSCL
stands prepared to benefit because of its staying power [2].
3
Demand for cement was particularly weak in 2007-08 for several reasons. First, the anti-
corruption drive of the military-backed caretaker government subdued expenditure of
undeclared funds. Most of these funds usually go to the construction sector. Second, a rapid
climb of raw materials and shipping costs in the global market escalated the price in the local
market for cement and other construction materials, further squeezing consumers out of the
market. Third, government spending in construction under the annual development programs
(ADP), which constitutes a large part of the cement market, was particularly slow in these
years. Consequently, many of the smaller and some major cement manufacturers operated at
less than 50% capacity and incurred large losses during these years [2].
The industry realized about 20% sales growth in 2009, mostly because of the latent demand
from last years. On a secular basis, ongoing demand growth is expected to be about 8%. The
outlook for the cement industry seems positive for a number of reasons. First, the government
seems to be on a war footing to increase both the amount and the efficiency of spending in
social and physical infrastructure under the Annual Development Programs (ADP). Second,
the private sector is also energized because of certain tax advantages for undeclared funds if
they are invested in real estate. Third, a number of large infrastructure construction projects
(such as the Padma Bridge) are on the horizon. Both the government and the private sector
are soliciting funds for such both the government and the private sector are soliciting funds
for such projects. If implemented, these projects would significantly improve demand for
construction materials [1, 2].
So to meet the increased the demand it is essential to increase the productivity. The
approaches that are applicable at the shop-floor level are the ones that have direct impact on
the productivity. The second industrial revolution that was triggered in 1970s saw the advent
of automation in the shop floor. Automation became popular among Japanese manufacturers.
Automation eliminates the drudgery of manual labor, improves the quality, and reduces costs.
However, automation fails if the equipments are not maintained properly. Japanese
manufacturers started to move towards an approach that would guarantee Zero Accidents,
Zero Defects, and Zero Breakdowns [3, 4].
Thus, TPM (Total Productive Maintenance) came into existence. One of the main pillars of
TPM is Autonomous Maintenance (Tajiri and Gotoh, 1992). The uniqueness of Autonomous
Maintenance is that the maintenance is carried by the Production Department (shop-floor
4
personnel) [4] and not by the conventional Maintenance Department. The success of TPM
depends upon the success of the Autonomous Maintenance program.
1.4 Objective and Scope of the study
1.4.1 Objective The main objective of this study is to evaluate the effect of AM on the plant
reliability, utilization factor as well as on overall plant effectiveness which will also
includes-
Management of the stoppages (unwanted plant shutdown)
Study and identification of the incidental stoppages which are manageable by
implementing AM
1.4.2 Scope The scope of the study includes
(i) The cement manufacturing process
(ii) Maintenance Management System of LSCL
(iii) Performance Criteria of LSCL
(iv) Collection of the data for all the stoppages
(v) Analyzing the data
(vi) Calculation of reliability factor
(vii) Calculation of utilization factor
(viii) Calculation of performance factor
(ix) Calculation of overall equipment efficiency
The following steps were carried out to complete the project was sequentially:
(a) Data Collection
In LSCL the stoppages are automatically log in into a software named ADAP (Advance
Downtime Analysis program), and then manually segregated the stoppages in their
different types. I collected all the data and segregate the incidental stoppages.
(b) Data Analysis /RCA
Data Analysis phase includes to identify the stoppages in different categories and to select
the stoppages which are due to lack of autonomous maintenance i.e. which can be
5
avoided by implementing the Autonomous Maintenance by the means of RCA. I also find
the duration of the stoppages and justify how those stoppages can be avoided by
implementing AM.
(c) Pareto Analysis
After that I carried out the Pareto analysis to find the main contributor in the loss of
reliability. Only the major incidents those who are contributor in the 80% of total loss in
reliability will be addressed.
(c) Calculating Effect on Reliability
Then I calculated the effect of individual stoppage on the Reliability of the particular shop
and as well as the plant reliability. In LSC the shops are VRM (Vertical Raw Mill),
KILN, CM1 (Cement Mill-1), CM2 (Cement Mill-2).
(d) Calculating Effect on OEE
I also calculated the OEE relating with RF, PF and UF. So an increase in RF will
definitely affect the OEE of a plant. Here I calculated the increased OEE resulting from
the increase in RF.
6
CHAPTER-2: LITERATURE REVIEW
LITERATURE REVIEW
2.1 Overview of TPM in Process Industry
Japan‘s process industries introduced preventive maintenance (PM) relatively early because
production output and rate, quality, safety, and the environment depend almost entirely on the
state of plant and equipment. The preventive and productive maintenance systems introduced
by Japanese process industries played a major role in improving product quality and
productivity [4].
They contributed significantly to overall process in maintenance management and expertise
in such areas as setting up specialized maintenance organizations, creating equipment
management systems, improving equipment technology, and raising maintenance
productivity.
While the process industries focused on preventive and productive maintenance, the
fabrication and assembly industries invested heavily in new equipment in an effort to become
less labor intensive. The equipment used by these industries has become increasingly
automated and sophisticated, and Japan is now the world leader in the use of industrial
robots. This trend toward automation, combined with the trend toward just-in-time
production, stimulated interest in improving maintenance management in the fabrication and
assembly industries [3].
This gave birth to a uniquely Japanese approach called total productive maintenance (TPM),
a form of productive maintenance involving all employees.
TPM first took root in the automobile industry and rapidly became part of the corporate
culture in companies such as Toyota, Nissan, and Mazda, and their suppliers and affiliates. It
has also been introduced by other industries, such as consumer appliances, microelectronics,
machine tools, plastics, film, and many others [5].
Having introduced preventive maintenance, the process industries then began to implement
TPM. An increasing number of process plants have introduced TPM over the past few years
in industries such as food, rubber, oil refining, chemicals, pharmaceuticals, gas, and cement,
papermaking, iron and steel, and printing [3].
7
Initially, corporate TPM activities were limited to departments directly involved with
equipment, such as production, however, administrative and support departments, while
actively supporting TPM in production, are now applying TPM to enhance the effectiveness
of their own activities, TPM improvement methods and activities are also being adopted in
production development and sales departments.
This last trend underlines the increasing tendency to consider production process as
equipment at the product development stage in an effort to simplify production, improve
quality assurance, and enhance and reduce the startup period for new production. These
issues are of particular concern in process industries today as product diversification
continues and product life cycles shorten. Interest in TPM outside Japan has also expanded in
recent years. Many companies in the United States, Europe, Asia, and South America are
Planning to or are actively pursuing TPM.
There are three main reasons why TPM has spread so rapidly throughout Japanese industry
and why companies outside Japan are becoming interested: It guarantees dramatic results,
visibly transforms the workplace, and raises the level of knowledge and skill in production
and maintenance workers.
Companies practicing TPM invariably achieve starting results, particularly in reducing
equipment break-downs, minimizing idling and minor stops (indispensable in unmanned
plants), lessening quality defects and claims, boosting productivity, trimming labor and costs,
shrinking inventory, cutting accidents, and promoting employee involvement.
Through TPM, a filthy, rusty plant covered in oil and grease, leaking fluids, and spilt
powders can be reborn as a pleasant, safe working environment. Customers and other visitors
are impressed by these changes, and their confidence in the plant‘s products increases.
As TPM activities begin to yield concrete results (improving the working environment,
minimizing breakdowns, improving quality, reducing changeover times, and so on), workers
become motivated, involvement increase, and improvement suggestions proliferate. People
begin to think of TPM as part of their Job.TPM helps operators understand their equipment
and widen the range of maintenance and other tasks they can handle. It enables them to make
new discoveries, acquire fresh knowledge, and enjoy new experiences. It strengthens
motivation, engenders interest in and concern for equipment, and fosters the desire to
maintain equipment in peak condition [6~10].
8
2.2 Pillars of TPM
There are three mainly eight pillars in the TPM. Which are-
1. Pillar-1: Focused Improvement
2. Pillar-2: Autonomous Maintenance
3. Pillar-3: Planned Maintenance
4. Pillar-4: Training
5. Pillar-5: Early Management
6. Pillar-6: Quality Maintenance
7. Pillar-7: Office TPM
8. Pillar- 8: Safety and Environmental Management
Pillar-1: Focused Improvement
Focused improvement is an improvement activity performed by cross-functional project
teams composed of people such as production engineers, maintenance personnel, and
operators, these activities are designed to minimize targeted losses that have been carefully
measured and evaluated.
In addition to the seven major losses experienced in fabrication and assembly industries,
process industries sustain three additional types of loss: people related losses such as work
and mis-operation losses; raw-materials losses such as yield, unit-consumption, and recycling
losses; and management losses such as shutdown maintenance and energy losses.
In process industries, focused improvement activity is directed at a specific object such as a
process, a flow system an item of equipment, or an operating procedure. For example,
process design must be an integral part of product development and improvement. A focused
improvement project can address vital, related issues such as establishing criteria for
selecting processes and their conditions, discovering deficiencies in process conditions, and
finding and closing gaps between actual and ideal process conditions.
The trend toward unattended operation is well advanced in process industries and will
probably be taken even further in the future. For this reason, ideas for stabilizing processes
and eliminating equipment breakdowns, idling, and minor stops are also important topics for
focused improvement.
When the focus is strictly on equipment, project teams follow a similar approach to that
developed in fabrication and assembly industries. They document and analyze the major
9
equipment-related losses, then study the equipment carefully to identify the process
conditions it is required to provide and to ensure that it can fulfill them.
Whether the focus is on the process, work flow, equipment, or operation procedures,
however, focused improvement activity is founded on effective use of cause analysis
methods, such as why-why analysis and P-M analysis [11]
Fig 2.1: Pillars of TPM
Pillar-2: Autonomous Maintenance
Autonomous maintenance is one of the most distinctive activities in TPM. After preventive
maintenance was introduced into Japan, Operation and maintenance were formally separated,
as operators lost ownership of their equipment; they gradually lost their sense of
responsibility for maintaining it.
10
The autonomous maintenance practiced in TPM reverses this tendency. Operators become
involved in routine maintenance and improvement activities that declined the deterioration
rate by halves, control contamination, and help prevent equipment problems.
Because process plants employ a small number of operators in relation to the number and size
of equipment units, strategies for achieving autonomous maintenance goals must be adapted
somewhat from the traditional approach followed in fabrication and assembly industries.
When tailoring autonomous maintenance to individual process environments, planning teams
must consider
how autonomous maintenance steps can be conducted most effectively on different
types of equipment
Investigate the relative importance of different equipment items and determine
appropriate maintenance approaches.
Prioritize maintenance tasks
Allocate responsibilities appropriately between production and specialized
maintenance personnel
Autonomous maintenance activities are typically implemented in steps and are only effective
if the progression form one step to the next is strictly controlled. To manage this, appoint
official auditing groups and lay down pass/fail standards. A plant‘s top management should
give final approval for groups to graduate from one step and move on to the next.
Why is close control so important? Initial cleaning (pillar-1), for example, involves much
more than merely cleaning and tidying the equipment and adjacent areas. If team efforts are
not focused on identifying and treating problems found in the course of thorough cleaning,
the goals of eliminating and controlling deterioration cannot be achieved.
Similarly, depending on the plant‘s location, salt spray, rain, snow, and so on, liquids, solids,
gases, etc can also accelerated deterioration of equipment, through scattering, leaking, blocks
and so forth. How such deterioration is treated will depend in part on the environment, the
equipment, or form of the product. However, if Step 2 of an autonomous maintenance
program (action against contamination sources and inaccessible places) is not properly
implemented, the program will slip right back to step 1 or step 1 or even further. Step-by-
step auditing of team activities to keep them properly focused is essential for successful
implementation of autonomous maintenance [1, 2, 11]
11
Pillar-3: Planned Maintenance
Planned or scheduled maintenance, embraces three forms of maintenance: breakdown,
preventive, and predictive. Like other TPM activities, building a planned-maintenance system
can be done systematically, one step at a time.
The purpose of performing predictive and preventive maintenance is to eliminate
breakdowns, but even when systematic maintenance practices are carried out, unexpected
failures still occur, of maintenance plans and highlight ineffective recurrence-prevention
measures. In TPM, Planned maintenance a activities emphasize monitoring mean times
between failures (MTBF) and using that analysis to specify the intervals for tasks in annual,
monthly, and weekly maintenance calendars [9~12]
A classic example of planned maintenance activity is shutdown maintenance. To make
them more effective, companies are preparing for shutdown earlier and earlier. Their goal is
to lay out reliable plans before the job begins. Because the tasks performed during shutdown
maintenance follow a set pattern, it is helpful to base the work plan on a work breakdown
structure (WBS) diagram. This diagram facilitates accurate estimation of the tasks to be
performed during shutdown maintenance, along with their sizes. It can be used to gauge the
staff and materials needed for the job and to monitor the budget and the achievement of the
objectives [5, 9, 10 ].
Pillar-4: Training
A company‘s workforce is a priceless asset, and all companies must train their employees
systematically. Process-industry Workers are becoming increasingly elite, and more multi
skilled. So training must be an integral part of a career development system.
Visualize the type of people you want your training programs to produce. In other words,
identify the specific knowledge, skills, and management abilities you want them to have and
then design training that will achieve your vision.
Training must also be tailored to serve the individual‘s needs. Assess each person to measure
his or her grasp of the required knowledge and skills and pinpoint weaknesses, the use the
results to make the general training more effective. Workers and their supervisors should
discuss the results of this assessment annually and use them to set the next year‘s targets and
plan the next phase.
Also set firm schedules for achieving program targets. Decide the king of people you want to
have in how many year‘s time, the draw up comprehensive plans for on-the-job and off-the-
job training (including seminars and courses) designed to achieve this [5, 11]
12
Pillar-5: Early Management
Early management includes both early product management and early equipment
management. The purpose of these activities is to achieve - quickly and economically -
products that are easy to make and equipment that is easy to use. This section highlights early
equipment management.
Early equipment management concerns equipment users, engineering companies, and
equipment manufactures, and addresses the following areas-
Equipment investment planning
Process design
Equipment design, fabrication, and construction
Test operation
Startup management.
All activities from the initial design of a piece of equipment to its installation and test
operation can view as a single, giant project. The project starts with process design, basic
plant design, and detailed design and unfolds to include procurement, fabrication,
construction, and test operation. In planning such a project, the project team determines the
plant and equipment‘s required technical levels (functions and performance) together with its
availability levels (reliability, maintainability, etc.) and then establishes budgets and
schedules to achieve them.
In designing a plant, various designs are performed: functional design, reliability and
maintainability design, safety design, and economy design. Establishing maintenance
prevention (MP) specifications and performing MP design, in particular, help ensure that the
plant and equipment are reliable and easily maintained. Several design reviews should be
performed in the course of designing, fabricating, and constructing a plant.
After completing these activities, teams install the equipment, perform test operation, and
initiate the startup management phase. Startup management is an activity designed to achieve
as quickly as possible the conditions for its own termination, that is, conditions that enable
the plant to start producing stable quality product with zero failures. In TPM this efficient
approach to stable, full scale production is known as ―vertical startup‖ [3, 9,11]
13
Pillar-6: Quality Maintenance
Quality maintenance (QM) is a method for building in quality and preventing quality defects
through the process and through the equipment, in quality maintenance, variability in a
product quality characteristic is controlled by controlling the condition of equipment
components that affect it.
Quality characteristics are mainly influenced by the four production inputs: equipment,
materials, people‘s actions (skills), and methods used. The first step in quality maintenance is
to clarify the relationships between these factors and a product‘s quality characteristics by
analyzing quality defects. In process industries, the effect of equipment on quality
characteristics is particularly important.
In process industries, the process determines the type of equipment needed. Therefore, teams
should focus first on the process, then on the equipment. In other words, first clarify the
relationships between product quality and process conditions and ascertains the precise
process conditions required for producing perfect product.
Equipment is a means of implementing a process. Therefore, applying a QM approach in
equipment design, teams begin by identifying the components that will affect the product‘s
quality characteristics. These are called ―quality components.‖
Next, they pinpoint the quality component conditions required to maintain the quality
characteristics. Quality maintenance used in this way assures quality at the very beginning of
the production process [5, 7, 11].
Pillar-7: Office TPM
Administrative and support departments play an important role in backing up production
activities. The quality and timeliness of the information supplied by administrative and
support has a major impact on these activities.
TPM activities performed by administrative and support departments must not only support
TPM in the workplace; they should also strengthen the functions of the departments
themselves by improving their own organization and culture. Compared with production,
however, it is not as easy for administrative and support departments to measure the effects of
their activities. [4, 8 , 10].
A TPM program in such a department must aim to create an ―information factory‖ and apply
process analysis to streamline the information flow. Think of administrative and support
departments as process plants whose principal tasks are to collect, process, and distribute
14
information. This understanding makes it easier to promote and measure maintenance,
focused improvement, and other TPM activities in an office environment.
Autonomous maintenance in administrative departments aims for efficient, trouble-free work
execution from two angles: administrative function and administrative environment.
Implemented step by step, the first set of activities reduces costs and boost efficiency by
improving administrative processes.
The second set of activities removes obstacles to effective work hidden in the physical and
psychological environment. Focused improvement of administrative tasks aims to improve
their efficiency and speed and reduce the number of staff required. To achieve this, automate
office tasks and install electronic data-processing system. At the same time, increase
administrative efficiency to support the planning and decision-making of executives and
managers.
Pillar- 8: Safety and Environmental Management
Assuring safety and preventing adverse environmental impacts are important issues in
process industries.
Operability studies combined with accident prevention training and near-miss analysis are
effective way of addressing these concerns. Safety is promoted systematically as part of TPM
activities. As with all TPM activities, safety activities are implemented step by step. Certain
issues are of particular importance in the process environment. For example, it is particularly
important to incorporate fail-safe mechanisms - that is, to design equipment that will remain
safe even when people do not take the proper precautions. Assuring safety during shutdown
maintenance is also important. In process industries, shutdown maintenance requires
considerable assistance from outside subcontractors, as do operation such as cleaning. This
makes it doubly important to ensure safety during such operations. Check the skills and
qualifications of subcontract workers well in advance whenever possible. Take every
practicable step to assure safety, including giving rigorous safety training and carefully
supervising the work itself [11].
2.3 Autonomous Maintenance
TPM refers to small group activities calling for total employee involvement and implemented
primarily by the production, maintenance, and plant engineering departments to maximize
15
productivity. In short, it is a strategy to realize Zero Accidents, Zero Defects, and Zero
Breakdowns (Gotoh, 1991; Tajiri and Gotoh, 1992).
TPM implementation must take into account the conditions that exist in each company or
factory, such as plant configuration, organization, local history, and culture at the plant site.
In today‘s industrial scenario huge losses/wastage occur in the manufacturing shop floor.
This waste is due to operators, maintenance personal, process, tooling problems and non-
availability of equipment in time etc. Other forms of waste includes idle machines, idle
manpower, break down machine, rejected parts etc are all examples of waste. The quality
related waste are of significant importance as they matter the company in terms of time,
material and the hard earned reputation of the company. There are also other invisible wastes
like operating the machines below the rated speed, start up loss [4], break down of the
machines and bottle necks in process. Zero oriented concepts such as zero tolerance for
waste, defects, break down [7] and zero accidents are becoming a pre-requisite in the
manufacturing and assembly industry. TPM is the revolutionary concept in this aspect. One
of the important pillars of the TPM is Autonomous maintenance [3], by which the machine
downtime and unavailability related loss can be eliminated.
In another version, autonomous maintenance is called self maintenance. Self maintenance
which geared towards developing production operators to be able to take a care of small
maintenance task, thus freeing up the skilled maintenance people to spend time on more
value added activity and technical repairs. The operators are responsible for upkeep of their
equipment to prevent it from deteriorating. This feeling can appear with joining all level
management starting from top management to bottom management. They work together to
solve machine problem, then give a thrust to operator to maintain by himself after they pass a
kind of machine operation setting skill test. On its development, many tools and methods are
used to speed up the skill level of operator to take a good care for machine. In the next step of
self maintenance, FMEA (Failure Mode Effect Analysis) [6,7,12] method has been started to
analyze the problem. It is held by maintenance together with production and engineering, and
its impact really felt to reduce machine problem moreover reach no breakdown machine on
production time. Moreover, another method to level up production side to do well self
maintenance is using Production-Maintenance mechanism. This motto does not only raise up
the spirit of production to do maintain their machine hardly but also on maintenance side
which feel that they have to study more and more to level up their skill because the next
demand will be different whereas maintenance not just stand to fixed up a simple problem but
drive to be a specialist one [9].
16
AM implementation process may be interpreted as a process of organizational change (Fruin,
1997). One model of organizational change is based on cycles of compliance which refers to
the conforming or nonconforming behavior of those who are in the midst of organizational
change, measured against the expectations and performance goals of those in charge of
planning and managing change. The model predicts that large-scale change activities move
through a predictable sequence of four phases: education and promotion; commitment;
performance; decline and withdrawal.
The main goal of Autonomous Maintenance is as follows.
Prevent equipment deterioration through correct operation and daily checks
Bring equipment to its ideal state through restoration and proper management
Establish the basic conditions needed to keep equipment well-maintained
The steps to be followed in the AM program are (Motorola Internal Document, 1999):
2.3.1 Equipment selection and team formation
Selection of the right equipment during the initial stages of implementation of AM is very
important. A quick success in the initial stages will always provide sufficient momentum
to the whole TPM program. TPM emphasizes on cross-functional teams. The team members
must be from departments like Engineering, Equipment, and Manufacturing. By having a
cross-functional team all aspects can be looked into and each team member is given a specific
task to accomplish.
Today, the relationship between production and maintenance departments is often
adversarial. When production stops due to equipment failure, production departments
complain bitterly:‖Maintenance doesn‘t know its job‖; ―It takes too long to fix the
equipment‖; or, ―this equipment is so antiquated, no wonder it breaks down.‖ Then they say
they are too busy to do vital daily checks. [11]
17
Maintenance Techniques and Activities
The maintenance activities can be classified in different ways but the most effective away is
as mentioned below.
Normal Operation Correct operation, correct adjustment, correct setting
(prevention of human errors)
Preventive Maintenance Daily maintenance (basic equipment conditions, checking,
minor servicing)
Periodic maintenance (periodic checking, periodic overhaul
inspection, periodic servicing)
Predictive Maintenance Condition monitoring, medium-interval and long-interval
servicing
Breakdown Maintenance Prompt abnormality detection, emergency repairs,
recurrence prevention (troubleshooting)
Improvement Activities:
Extend Equipment life
Shorten the time require to perform maintenance
Make maintenance unnecessary
All the maintenance activities are the responsibility of all the personnel in the organization
and they are can be listed as below…
Activities of the Production Department
1. Preventing deterioration:
Correct operation — preventing human errors
Correct adjustment — preventing process defects (quality defects)
Basic housekeeping (establishing basic equipment conditions) — cleaning,
lubricating, and tightening
Early prediction and prompt detection of abnormalities — forestalling failures and
accidents
Keeping maintenance records — feeding back information for recurrence prevention
and maintenance-prevention design
18
2. Measuring deterioration:
Daily inspection — patrol checks and five-senses checks during operation
Periodic inspection — part of overhaul inspection during plant shutdown or
shutdown maintenance
3. Predicting deterioration:
Minor servicing — emergency measures when abnormal conditions arise and simple
parts replacement
Prompt, accurate reporting of failures and problems
Assistance with repairing unexpected failures
Maintenance Department Activities
Provide instruction in inspection skills and help operators prepare inspection
standards (checkpoints, checking intervals, and so on
Provide training in lubrication techniques, standardize lubricant types, and help
operators to formulate lubrication standards (lubrication points, lubricant types,
intervals, and so on)
Deal quickly with deterioration, minor flaws in equipment conditions, and
deficiencies in basic equipment conditions (I.e., carry out maintenance work
identified by operators promptly)
Contribute technical assistance in improvement activities such as eliminating
contamination sources, making areas more accessible for cleaning, lubrication, and
inspection and boosting equipment effectiveness.
Organize routine activities (morning meetings, rounds to take orders for maintenance
tasks, and so on).
Research and develop new maintenance technologies
Prepare maintenance standards manuals
Build systems for keeping maintenance records, handling maintenance data, and
measuring results
19
Develop and use failure-analysis techniques and implement measures to prevent the
recurrence of serious failures Assist equipment design and development departments
(participate in MP design and early equipment management activities)
Control spares, jigs, tools, and technical data
2.3.2 Initial cleaning
This step emphasizes on hands-on activity. First, the surrounding area is cleaned and all
unnecessary items around the equipment are removed. Once the surrounding area is clean, the
team can start focusing on the equipment itself. Initial cleaning of the machine consists of
cleaning of dust, dirt, grime, oil, grease, and other contaminants in order to expose the hidden
defects inside the equipment. All covers, guards, and compartments should be opened up to
expose the actual condition of the machine. Based on the TPM philosophy ―cleaning is
inspection‖, inspection is a step to detect any abnormalities or ―Fuguai‖. The process of
combing through the machine and identifying all the abnormalities is called ―Fuguai
mapping‖. Figure 1 shows an example of Fuguai mapping. A sketch of the machine is drawn
by hand and fuguais are tagged and classified as long and short-term fuguais. The fuguais are
removed and the progress is monitored closely. The mapping and the removal processes
enable the team to identify the critical cleaning points. Then proper cleaning procedures and
the time taken for cleaning can be established and monitored. The task is explained with a
diagram to facilitate easy understanding to the operator. The ―Cleaning check sheets‖ lists all
the tasks that need to be carried out by the technicians and operators in a very systematic
way. The operators and technicians must be trained and educated on the significance of
cleaning and its impact on the safety. At this stage of AM minor flaws like excessive play,
deformation and wear can be detected and corrected.
2.3.3 Eliminate sources of contamination and inaccessible areas
The basic objective of this step is to identify the sources of contamination and to provide
solutions to permanently correct these sources. This could be done by either eliminating the
source or by containing the contamination in such a way that it does result in losses. This is
done by ―Why Why‖ analysis method. This type of analysis starts with a current problem
being faced and goes through each level of analysis with a ―Why?‖ question. Subsequently
all answers are treated with ―Why?‖ question again. The series of ―Why?‖ helps in
20
identifying the root cause of the problem. The other objective of this step is to identify the
hard-to-access areas for the operator to do the cleaning. The solutions are worked out to make
these areas accessible for cleaning [8].
2.3.4 Establish Cleaning and Inspection Standards
In this step, the focus is on the mechanics of equipment. This step emphasizes on prevention
of any malfunction by studying the lubrication system of the equipment and the equipment as
a whole. Proper lubrication guarantees smooth running of the equipment and reduces the
wear and tear on the equipment. The AM standards are set describing the tasks to be
performed, the tools to be used in performing the task, standard time to be taken to perform
the task, and the frequency of performing the task (daily, weekly etc.). The critical inspection
points on the equipment like gauges, levels are identified and these critical points are added
to the AM standards on cleaning and inspection. However, please note that these standards
are developed after working on preventive solutions to minimize/eliminates cleaning and
inspection time by preventing abnormalities. AM standards are institutionalized and
displayed on the equipment. The technicians and operators can follow this checklist in
maintaining the equipment. It is also important to record the observations made during
cleaning and inspection. The operators must be trained in recording the observations. This
data can be further analyzed to predict any impending problem [11,13]
2.3.5 Establishing Basic Equipment Conditions
Establishing Basic Equipment Conditions Eliminates Causes of Accelerated Deterioration. To
establish the basic condition we need to be familiarized with the different types of failures.
Failures are the consequent of deterioration. This deterioration is normally prevented by the
means of corrective maintenance or by establishment of equipment basic condition. The total
sequence is shown in the figure below.
21
Fig 2.2: Causes of Accelerated Deterioration
For establishment of the Equipment basic condition we need to understand the failure,
defects, deterioration, loss and importance of cleaning and inspection.
Failure
Dirt and foreign matter penetrates rotating parts, sliding parts, pneumatic and hydraulic
systems, electrical control systems, and sensors, etc., causing loss of precision, malfunction,
and failure as a result of wear, blockage, frictional resistance, electrical faults, etc.
Quality Defects
Quality defects are caused either directly by contamination of the product with foreign matter
or indirectly as a result of equipment malfunction.
Accelerated Deterioration
Accumulated dust and grime make it difficult to find and rectify cracks, excessive play,
insufficient lubrication, and other disorders, resulting in accelerated deterioration.
Speed Losses
Dust and dirt increase wear and frictional resistance, causing speed losses such as idling and
under performance.
Key points of Cleaning
1. Clean equipment regularly as part of daily work.
2. Clean deeply - remove all the layers of grime and scale built up over many years.
22
3. Open previously ignored covers, guards, and so on, to expose and remove every speck of
dirt from every corner and crevice.
4. Clean attachments and accessories as well as main units, e.g. conveying equipment, control
boxes, and lubricant tanks (both inside and out).
5. Do not give up when a part gets dirty again soon after cleaning. Instead, carefully note how
long it takes the part to become contaminated again, where the contamination is coming from,
and how severe it is?
Key Points for Inspection
1. Search for invisible as well as visible defects, such as looseness, subtle vibrations, and
slight overheating that only touch can detect.
2. Search carefully for worn pulleys and belts, dirty drive chains, blocked suction filters, and
other problems likely to lead to malfunctions.
3. Note whether equipment is easy to clean, lubricates, inspect, operate and adjust. Identify
hindrances such as large, obstructive covers, ill-positioned lubricators, and so on
4. Ensure that all meters operate correctly and are clearly marked with the specified values.
5. Investigate any leak of product, steam, water, oil, compressed air, and so on.
6. Also hunt for hidden problems such as corrosion inside insulating materials on pipes,
columns, and tanks, and blockages inside chutes and dusts
2.3.6 Education/Training to Operators and Technicians
Unless the operators are trained and educated about the impact the autonomous maintenance
on the quality of the product, scrap rate, and ultimately the cost of production, they will never
be able to appreciate its importance. This step helps in developing ―knowledgeable‖ operators
who can solve/avoid most of the equipment and quality related problems on the shop floor.
AM attempts to achieve Zero Breakdowns, Zero Accidents, and Zero Defects situation on the
shop floor. If AM is implemented in a systematic and phased manner in the shop floor, it can
bring in substantial benefits [7,9,11]
2.4 Features of Process Industries Certain unique features and concerns distinguish process industries from the fabrication and
assembly industries where TPM was born.
23
Diverse production systems
The term ―process industry‖ covers a wide variety of industries including oil refining, patriot-
chemicals, general chemicals, iron and steel, power generation, gas, papermaking, cement,
food, pharmaceuticals, and textiles. Process Plants in these industries employ a mixture of
different production regimes, ranging from completely continuous integrated production to
pure batch production. Also, the trend toward increased product diversification and high-
variety, small-lot production has led in many cases to both process and fabrication/assembly
production in the same plant.
Diverse equipment
In process industries, production processes consist of a combination of unit operations such
as pulverization, dissolution, reaction, filtration, adsorption, concentration, crystallization,
separation, molding, drying, cooling, and screening, together with the handling and
transportation of various substances. Equipment includes static units such as pumps,
compressors, motors, and turbines, and the piping, electrical, and instrumentation systems
that connect them.
Use of static equipment
Static equipment is a particularly noteworthy feature of process industries. The special nature
of such equipment requires TPM quality and includes techniques for diagnosing corrosion,
cracking, burning, blocks, leaks, and so on.
Centralized control and few operators
Unlike in fabrication and assembly industries, control in process industries is centralized.
Many process industries employ continuous, integrated production with centralized control of
large equipment complexes. A wide range of equipment is often controlled by a handful of
operators [13]
Diverse equipment-related problems
In addition to blocks, leaks, and other process problems, process industry equipment is often
plagued by faults such as cracking, rupture, corrosion, seizure, fatigue, slack, parts falling off,
wear, distortion, burning, short-circuiting, faulty insulation, wire breaks,misoperation, current
24
leaks, and overheating. The most common problems, however, are corrosion, leaks, and
blocks.
High energy consumption
Many processes in process industries, such as dissolution, reaction, crystallization, baking,
and drying, are energy intensive and consume large amounts of electrical power, fuel, water,
and so on.
Standby units and bypasses commonly used
To alleviate the effects of breakdowns, it is standard practice to install standby equipment,
bypasses, and so on.
High accident and pollution risk
Some processes handle hazardous or poisonous substances and are operated at high
temperatures and pressures, risking explosion and pollution of the plant and its surroundings.
This makes strict plant management essential, as well as careful adherence to various
statutory regulations
Poor working environment
Intermediate and final products handled in process industries usually consist of bulk powders,
or solids. While it is considered inevitable that the working environment will become dirty as
a result of these being scattered, overflowing, leaking, and so on, such conditions frequently
cause equipment problems.
Shutdown maintenance
Shutdown maintenance is a major feature of process industries. Carefully planned,
systematically implemented shutdown maintenance is considered the most effective way of
preventing breakdowns. However, since shutdown maintenance is time-consuming and labor-
intensive, it is also expensive. Finding the most effective way of performing shutdown
maintenance in view of its cost and the losses it incurs is therefore a perennial concern in
process industries [7].
25
2.5 Maximizing Production Effectiveness in Process Industries 2.5.1 Production Effectiveness in process industry
Production effectiveness in the process industry depends on different input variables. The different input variables and their outputs are shown in the figure 2.3.
Fig 2.3: Production Effectiveness in Process Industry
2.5.2 Processing Losses
The major losses in the process industry are the processing loss. During the processing phase
different types of losses occurs in different stages which are mainly categories into eight
classes. The different process losses are explained below with the help of examples.
The 8 Major Plant Losses
1. Shutdown Loss 2. Production Adjustment Loss 3. Equipment Failure Loss - Function: Failure Loss - Function: Reduction Loss 4. Process Failure Losses 5. Normal Production Losses 6. Abnormal Production Losses 7. Quality Defect Losses 8. Reprocessing
Failure zero Defect zero Problem zero Trouble zero
26
Loss Definition Units Example
1 Shutdown
Loss
Time loss when production
stops for planned annual
shutdown maintenance or
periodic servicing
Days Shutdown work, periodic
servicing, statutory
inspections, autonomous
inspections, general repair
works, etc.
2 Production
Adjustment
Loss
Time lost when changes in
supply and demand require
adjustment to production plans
Days Production adjustment,
shutdown inventory-
reduction, etc
3 Equipment
failure Loss
Time lost when equipment
suddenly losses
Hours Failed pumps, burned
motor, damaged bearings,
broken shafts, etc.
4 Process
failure Loss
Time lost in shutdown due to
external factors such as changes
in chemical or physical
properties of materials being
processed, operating errors,
defective raw material, etc.
Hours Leaks, spills, blocks,
corrosion, erosion, mis-
operation, etc.
5 Normal
Production
Loss
Rate and time losses at plant
startup, shutdown or
changeover
Rate
decreas
e hours
Loss during plat start up,
cool down, shutdown
process
6 Abnormal
Production
Loss
Rate loss due to
underperformance caused by
malfunctions and abnormalities
Rate
decreas
es
Low load operation,
operation at lower than
rated capacity
7 Quality
defect loss
Losses due to producing reject
product, physical losses due to
product downgrading
Hrs,
tons,
dollars
Defective product
manufacture
8 Processing
loss
Recycling losses due to passing
material back through the
process
Hrs,
tons,
dollars
Recycling defective
products
Definition & Example of different losses
27
Those losses have a close relationship with the production duration. Normally startup loss
occurs during the start up of the production. The different losses related to the production
time are presented graphically in below.
Fig 2.4: Eight Major Losses
2.5.3 Overall Equipment Effectiveness
To determine the overall Equipment Effectiveness we need to know about the different terminologies which are described step by step below.
1. Opening Hours
Number of hours on the calendar
=365D X 24H = 8,760 hours in a year
30D X 24H = 720 hours in a 30-day month
28
2. Working Hours
No of hours available for work
=Opening Hours — Production Adjustment — Periodic Servicing — Shut down
Maintenance
3. Operating time
=Working Hours – Shut down as a result of equipment – Process failures
4. Net Operating Times
=Standard Production Rate – Product rate reductions due to startup – Shutdown –
Change over
5. Valuable Operating Time
=Working Hours – wasted reprocessing – producing reject product
6. Availability
= X 100 (%)
Shutdown losses = shutdown maintenance loss + Production adjustment loss
Major stoppage loss = equipment failure loss + Production failure loss
7. Performance Rate
= X 100%
29
8. Quality Rate
Quality rate is expressed as the amount of acceptable product which equals to total
production less downgraded product, scrap, and reprocessed product as a percent of total
production.
Quality rate=
X100%
9. Overall plant Effectiveness (OEE)
= Availability x performance rate x Quality rate
2.5.4 Maximizing the effectiveness of production inputs To maximize the effectiveness of the production inputs we need to deploy the following
strategies…
1. Reducing raw material & Energy losses
2. Production costs and unit consumption
3. Control of unit consumption by production
4. Control of unit consumption by season
5. Control of unit consumption by product
6. Reducing Raw Material Losses
7. Preventing Raw Material Losses & saving Energy
8. Process Simplification
9. Reducing Maintenance Materials
10. Reducing work Losses
11. Reducing cleaning Losses
12. New control systems for personnel Reduction
13. Process centralization & Simplification
14. Reducing Distribution Losses
15. Reducing Administrative Losses
16. Reducing Testing & Inspection.
30
CHAPTER-3: OVERVIEW OF LSCL
OVERVIEW OF LSCL
3.1 Lafarge Surma Cement- At a glance
Lafarge Surma Cement (LSC), incorporated in January 2003 is the first multinational cement
manufacturer in the country with a fully integrated cement plant set up at a cost of US$
225mn at Sunamgong in the North East of the country. The company is promoted by Lafarge
of France and Cementos Molins the concrete & construction aggregates manufacturer in
Spain. The company commenced commercial production in October of 2006 and has a 10%
market share of the domestic cement market excluding its supply of clinker to other local
manufacturers.
Lafarge Surma Cement Limited‘s (LSC) integrated cement manufacturing plant has an
annual capacity of 1.5 million tonnes of grey cement and 1.15 million tonnes of clinker. The
Company extracts and processes the basic raw materials like limestone & shell from its own
quarry in Meghalaya, India. A 17km cross-border conveyor belt links the quarry with the
cement plant for transportation of raw materials. A separate 30 MW gas engine power
generation plant has been setup to supply uninterrupted power to the cement plant. The
company is now operating at full capacity after a court injunction in India resulted in a
temporary halt to the production of clinker in 2007. Legal proceedings are however ongoing
over a dispute over quarrying on forest land.
3.2 Process Description
The total manufacturing process is divided into 5 stages which are listed below from
upstream to downstream sequences…
1. Crushing System
2. Raw Grinding System
3. Burning System
4. Finish Grinding System
5. Packing & Dispatch System
31
3.2.1 Crushing System
The main raw materials used in Lafarge Surma Cement (LSC) for cement manufacturing
process are limestone, sand, shale, clay, and iron ore. The main material, limestone and shale
stone, is mined from their own quarry in Meghalaya, India.
Mining of limestone requires the use of drilling and blasting techniques. The blasting
techniques use the latest technology to insure vibration, dust, and noise emissions are kept at
a minimum. Blasting produces materials in a wide range of sizes from approximately 1-2
meters in diameter to small particles less than a few millimeters in diameter.
Material is loaded at the blasting face into trucks for transportation to the crushing plant.
Then the size of limestone is reduced using the primary & secondary crusher in India side.
And maximum size is 90-100mm which should not be more than more than 1% of the total
production. Then those raw materials are transferred to LSC plant located in Sunamgong by
the 17 km long cross boarder conveyor belt which capacity is 800 tph. The belt is operated
with 3 synchronizing motors among which two are located in Bangladesh side and another is
in the query side which is in India.
Fig 3.1: Raw material extraction & Crushing
3.2.2 Raw Grinding System
LSC has a vertical raw mill which is branded as ATOX 47.5 with RAR LVT 47.5 Separator
which is capable to produce 270 tpd dry powder raw meal at the fineness 90µm ( Max 12%
of the total production). Power requirement for the RAW Mill motor is 12.2Kwh/t where as
total requirement for the RAW Mill department is 24.6 Kwh/t.
Max. 1% on 90 – 100 mm
Silt Stone
Lime Stone
32
Fig 3.2: Vertical Raw Mill
The raw material for the RAW Mill feed is limestone, shale stone, sand & iron ore. Among
them limestone and shale comes from its own query in India and sand and iron ore are either
locally purchased or imported from India. The RAW Mill feed preparation are shown below.
Fig 3.3: Raw Mill feed preparation
33
Apron feeder and weigh feeder is most critical equipment here to achieve the quality product.
After the feed in the RAW mill the raw material are grinded into fine powder and transported
into Controlled Flow (CF) silo by the means of Separator and Air slides where the main
process parameter is differential pressure. The dry materials exiting mill are called "kiln
feed". The kiln feed is pneumatically blended to insure the chemical composition of the kiln
feed is well homogenized and then stored in silos until required.
From the CF Silo the raw meal is fed to Kiln where clinker the main constituent of cement is
produced.
3.2.3 Burning System
Burning system of LSC consists of Kiln with duplex burner, ESP, Coolax cooler, Pre-heater,
Calciner & Silo.
The raw meal is fed into Kiln from the CF silo with an uniformity index (KFUI) and then
undergoes a combination of physical / chemical process which includes drying of raw mix,
removal of water of crystallization, calcining of raw mix (expulsion of CO2), formation of
compounds, C2S, C3A, C4AF, Formation of C3S, nodulisation and cooling.
All those chemical & physical changes are occurs in the kiln where the raw meal are burned
form 100-1450°C. This results in a final black, nodular product known as "clinker" which has
the desired hydraulic properties.In LSC, kiln feed is fed to a preheater tower, which is about
150.0 meters. Material from the preheater tower is discharged to a rotary kiln which diameter
is 4.55 m and 58 meter long. The preheater tower and rotary kiln are made of steel and lined
with special refractory materials to protect it from the high process temperatures. The rotary
kiln is fired with an intense flame, produced by natural gas supplied from Jalalbad gas.
Preheater towers is also equipped with firing as well.
The rotary kiln discharges the red-hot clinker under the intense flame into a clinker cooler.
The clinker cooler recovers heat from the clinker and returns the heat to the pyroprocessing
system thus reducing fuel consumption and improving energy efficiency. Clinker leaving the
clinker cooler is at a temperature conducive to being handled on standard conveying
equipment.
34
Fig 3.4: Kiln Fig 3.5: Coolax Cooler
3.2.4 Finish Grinding System
The finish grinding section consists of 2 lines. Each line is having a Ball Mill (grinding),
Separator, Vent Fan, Separator fan & Silo. Clinker (94 - 97%) and Gypsum (3 -6%) is
grinded together to get Ordinary Portland Cement (OPC).
During the final stage of cement production, the clinker is ground with other materials (which
impart special characteristics to the finished product) into a fine powder. Up to 3-6% gypsum
is added to regulate the setting time of the cement. LSC also add some percentage of
limestone to prepare the composite limestone cement.LSC use hammer crusher to achieve a
preliminary size reduction of the clinker and gypsum. These materials are then sent through
ball (rotating, horizontal steel cylinders containing steel alloy balls) which performs the
remaining grinding. The grinding process occurs in a closed system with an air separator that
divides the cement particles according to size. Material that has not been completely ground
is sent through the system again for regrinding
35
Fig 3.6: Finish Grinding Process
3.2.5 Packing & Dispatch
The finish product is transferred using bucket elevators and conveyors to two large, storage
silos in the shipping department. There the cement is packed into 50 kg bags using three
rotary packers. Then the cement is distributed to the dealers and retailers by the means of
barges & trucks. LSC is having two barge loaders with the loading capacity of 3600 tpd.
3.3 Maintenance Department-LSC
World leader in building materials, Lafarge is now operating in 78 countries all over the
world and they structured their organization from the experience of 170 years of operation
which is almost same in all the plants. The prescribed organization structure is as below.
Lafarge Surma Cement is following the chart-1 with the splitting Electrical and
Instrumentation maintenance department in two separate departments which are electrical
maintenance department and Instrumentation maintenance department.
36
Fig 3.7: Organizational Structure
The six functions on the organization is based on are-
01. Management:
Organise and manage the department's human, financial and material resources to optimise
the quality of its services and its technical and economical performance
Ensure in the short, medium and long term the optimum equipment availability and
performance at minimum cost
02. Inspection:
Follow and measure equipment condition, analyse trends, and identify the needs for
maintenance (for mechanical/electrical/ mobile/instrumentation equipment and civil works),
taking into account production constraints
02. Planning:
Define the methodology, the manpower, the spares and the other resources necessary to
achieve efficient and safe maintenance in line with technical standards
37
04. Scheduling
Define the work program according to operational priorities, manpower, resources and
equipment availability
05. Execution:
Complete maintenance jobs with the highest level of quality, safety and effectiveness at
minimum cost to maximise equipment availability
Fig 3.8: Maintenance Function
06. Improvement:
Reduce maintenance repair work throughout equipment life cycle by upgrading materials and
practices to improve technical and economical performance
The maintenance department in LSC is as in the next pages…..
38
Fig 3.9: Organization Chart-Maintenance
Fig 3.10: Organization Chart- Mechanical Maintenance
39
Fig 3.11: Organization Chart-Methods
Fig 3.12: Organization Chart- Instrument & Control and Electrical maintenance
3.4 Maintenance Philosophy
Mainly the structure was defined in the basis of
Priority should be given to condition-based preventive maintenance;
An organisational structure based on 6 functions, three of which form the main pillars:
Inspection, Planning and Implementation;
Scheduling of tasks which call for co-ordination between the different departments
within the Works;
40
Willingness by all players to propose on-going Improvements to equipment and
practices, with results that can be measured in terms of cost and reliability, driven and
encouraged by the Management …continuously;
The development of common methods and tools (risk analysis, Best Practices, ADAP,
MAXIMO, Lafarge Codification) promoting capitalisation and making good use of
experience within the Division … to ensure progress is made more quickly.
The main goal of the maintenance department is to increase the availability of the plant
equipment as well as plant reliability. To achieve the best performance some criteria was
defined which are as below.
MTTR : Mean Time To Repair
MTBF : Mean Time Between Failure
OEE : Overall Equipment Effectiveness = Availability x Performance x Quality. Key
performance indicator in the TPM approach.
PG (Work Generated by Preventive Maintenance): maintenance based on
significant equipment condition parameters analysis using five senses and simple
measurement techniques. Examples: replacement of liners, replacement of V-belt, of
conveyor belts.
PD (Work Generated by Predictive Maintenance) : maintenance activities based
on significant equipment condition parameters analysis using advanced detection
techniques. Examples : replacement of bearings using vibration analysis, oil
replacement using oil analysis, tightening of bolts of bus bar using thermo graphic
inspection.
SOP : Standard Operating Procedure
But it was noticed that although having a structured maintenance organization LSC failed to
meet the set KPI (Key Performance Indicator). So it is essential to find the hole which is
responsible for the low performance.
3.5 Downtime and KPI in LSCL
3.5.1 Down Time Recording
In LSC (Lafarge Surma Cement) the stoppages are automatically logon through a software
named ADAP (Advance Downtime Analysis program), and then manually segregated into
different types. ADAP is connected to all the major drive of all process area i.e. Crusher,
41
LBC, VRM, Kiln, Cement Mill-1, and Cement Mill-2. When any of them tripped a stoppage
is logged on into ADAP automatically and ends when the equipment starts again. To
evaluate the stoppages in different stoppage category the following reliability definitions are
used throughout the thesis work.
Fig 3.13: ADAP
3.5.2 Operating Hours
For kiln, Operating hours as counted from feed starts to feed-off
Other equipment, hours of operation for system‘s main motor (ex: mill motor for
grinding system)
3.5.3 Hours of Stoppage
There are 3 types of stoppages in LSC which are Circumstantial stoppage, Scheduled stoppege and incidental stoppege.
42
3.5.3.1 Circumstantial stoppage hours
Stoppages due to external factors such as strikes, market, full inventories, etc. Events on
which the plant has no or limited control.
3.5.3.2 Scheduled stoppage hours
Actual stoppage as scheduled at budget preparation.
For a kiln, if the scheduled stoppage is moved up more than 15 days, the first 5 days are
considered as incident stoppages. If the stoppage is extended for technical reasons, the
excess time is also considered as an incident.
For other equipment such as mills, downtime is deemed scheduled when planned at least one
month in advance.
3.5.3.3 Incident stoppage hours
Defined as unscheduled stoppages due to electrical, mechanical, production, process, etc.
Events on which the plant can impact.
3.5.3.4 Other Type of Hours
Available Hour
Available hours in month of January=31 x 24 = 744 hours
Available hours in 2005= 365 x 24 = 8760 hours
3.5.3.5 Budgeted scheduled downtime
For a kiln, a stoppage is deemed scheduled when planned during preparation of the annual
budget. Budgeted scheduled downtime can cover downtime for technical (overhaul) or
economical (market, etc.) reasons.
For other equipment, the scheduling has to be made at least one month in advance.
3.5.4 Performance Indicators for LSC
3.5.4.1 Number of Incident Stoppages
Number of times the equipment is stopped for incident.
43
3.5.4.2 Reliability
For a given equipment, operating hours divided by (operating hours + hours for incident
stoppages).
RF = Operating hours / [Operating hours + Incident stoppage hours]
3.5.4.3 Utilization
For a given system, operating hours divided by available hours.
UF = operating hours / avalable hours
Table 3.1: Example of RF & UF calculation
Type of Hours year(a) year(b) Month
Available hours 8760 8760 720
Circumstance stoppage hour 24 48 80
Stoppage for scheduled downtime 672 672 16
Incident stoppage hours 168 144 6
Operating hours 7896 7896 618
Utilization (%) 0.901 0.901 0.858
Reliability (%) 0.979 0.982 0.99
3.5.4.4 Overall Plant Effectiveness
OEE = Availability x performance rate x Quality rate
= Reliability x Utilization Factor x Quality rate (In LSC term)
As the reliability is the same representative of the Availability in the Lafarge doctrine is used
for calculating the OEE. On the other hand as Lafarge doctrine use to calculate the UF and
this actually represents the performance of the equipment in terms of time ratio instead of
capacity ratio.
44
3.5.5 Classification of Downtime
All the stoppages logged on into the ADP has to be classified into different stoppages time as
described earlier. For different process stages the stoppages classification are descrived
below.
3.5.5.1 Crushing System
For calculating the reliability LSC use the equipment which represents the true state of
production. In LSC the primary crusher represents the true picture of the crushing system.
But unfortunately it experienced a major breakdown within the 1Q of the commissioning and
stored data are not the true representative, Hence this process stage is left out from our
analysis.
3.5.5.2 Raw grinding system
Separator, product adjustment.
Stoppage in order to adjust the separator for a product change, is considered a Scheduled
stoppage when performed on a regular basis.
Situation 1:
At 2 a.m., an incident occurred on the mill. Production was not required to meet kiln feed.
The corrective actions (duration 1 hour) were performed the following morning at 6 a.m.
Mill was put back into operation by 10 a.m.
Incident Stoppage hours: 1 hour
Circumstance stoppage hours: 7 hours (4 + 3)
If cooling and reheating periods were required before and after the corrective actions, it
should be part of the Incident Stoppage Hours.
3.5.5.3 Burning System
Situation 1:
45
Change of budget dates done for circumstance reasons: remains Scheduled or Circumstance.
Kiln shutdown initially beginning on March 1st for 21 days is moved to accommodate a
market change. Actual date is February 1st and it lasts for 21 days. The 15 day criteria does
not apply.
Stoppage for scheduled downtime: 21 days
Situation 2:
Scheduled shutdown is longer than expected for technical reasons like an unexpected
equipment damage or longer period of time required to perform the activity: the extra
duration is considered Incident stoppage.
Situation 3:
Shutdown is extended for circumstance reason: the extra duration is Circumstance stoppage
hours (the work is performed on one shift instead of two).
Situation 4:
Anticipating the market conditions, at budget time, the shutdown dates are scheduled.
Budgeted Scheduled Downtime should cover the required time to perform the work under
normal conditions. If conditions allow to stretch the duration of downtime by using less
overtime, etc., then the additional time is considered Circumstance stoppage hours.
Due to a weak market, the kiln is going to be down for 9 weeks. That opportunity is taken to
perform a major repair on the precipitator (critical path task). The kiln shutdown for repairs
lasts 5 weeks. Under good market condition, this would have taken 3 weeks using overtime
and contractors.
Stoppage for scheduled downtime: 504 hours (3 weeks)
Circumstance stoppage hours: 1008 hours (6 weeks)
Situation 5:
Duration of shutdown is shorter than budgeted: Scheduled Downtime duration is equal to
actual.
Situation 6:
Budgeted/actual stoppage date (15 day criteria)
May 1st is the budgeted stoppage date. Due to nose ring failure, actual date is April 1st. The
first 5 days are considered Incident Stoppage hours, the following days are Scheduled.
May 1st is the budgeted stoppage date. Due to nose ring failure, actual date is April 16th.
The total downtime is considered Scheduled Downtime.
46
May 1st is the budgeted stoppage date. Due to nose ring failure, actual date is April 13th.
The first 2 days are Incident Stoppage hours.
May 1st is the budgeted stoppage date. Actual scheduled down day is June 1st and lasts 15
days: total duration is considered Scheduled.
Situation 2:
2 weeks in advance a 16 hour kiln shutdown is scheduled to replace grates in the cooler, the
downtime is considered Incident Stoppage Hours.
3.5.5.4 Finish grinding system
Situation 1:
Type of incident, product adjustment
Stoppages in order to adjust the separator for a change of product is considered a Scheduled
Stoppage when done on a regular basis.
Situation 2:
At 11 p.m., an incident occurred on the mill. Production was not required to meet market
demand. The corrective actions (duration 3 hours) were performed the following morning at
8 a.m. The mill was back in production by 11 a.m.
Incident Stoppage hours: 3 hours
Circumstance stoppage hours: 9 hours
If a cooling and reheating period was required before and after the corrective actions, it
should be part of the Incident Stoppage Hours.
Situation 3:
A mill must be stopped due to cement quality problems, downtime is recorded as Incident.
3.5.5.5 Impact of an incident from one system to another
If an upstream incident caused the shutdown of a downstream system due to lack of
material or hot air, the downtime on the downstream system is deemed Incident
Stoppage Hours.
The raw mill is down for lack of material feed. A failure occurred on the quarry
crusher. The mill downtime is recorded as Incident Stoppage Hours except in the
case of a subcontracted quarry over which you have no control.
47
Hot clinker from the kiln must be diverted to the hot bin via an equipment which is
part of the mill system. Therefore, the mill has to be stopped. The mill was able to
run, but the shift foreman decided to divert the production to keep the kiln in
operation. Mill downtime is Circumstance Stoppage.
3.5.5.6 Power downtime
Power contract
If the power contract is such that a piece of equipment has to be down for a certain period of
time during the day or during the year, there are two possibilities in case of Stoppages:
a) no work is performed on the equipment (yard, maintenance. . . ), the downtime is a
Circumstance type.
b) the stoppage is used to perform some work, then it becomes Scheduled or Incident
downtime depending on the degree of Scheduling. Most of the time it should be considered
as Scheduled
A power stoppage occurs on a piece of equipment which belongs to the plant. It is an
Incident stoppage. If, however, the failure is due to an «Act of God», over which the plant
has no control, or is not expected to have protection from, it is a Circumstance.
Note: Each plant must develop an envelope of circumstances which would apply here.
Plant generates its own electricity
When the incident on a piece of equipment from one system (e.g. kiln or boiler) results in the
shutdown of another system (e.g. mill #1) to match the power generation, the downtime of
the last system (mill #1) is Circumstance Stoppage. The plant could have avoided the
situation by purchasing electricity for production.
However in the case of an incident on a piece of equipment due to a switch from plant power
station to the local electricity distributor, the event would be considered as an incident
stoppage.
48
CHAPTER-4: DATA COLLECTION
AND ANALYSIS DATA COLLECTION AND ANALYSIS
4.1 Data collection
All the stoppages are logged on in software named ADAP (Advanced Downtime Analysis
program). All these data are entered into the software automatically and the CCRO (Central
Control Room Operator) segregate the stoppages in the different types as per the guideline
described in chapter 3.Then the incidental stoppages are classified into the 4 different
subtypes. Subtypes are classified according the discipline i.e. Mechanical, Electrical,
Production and Others. The stoppages which are caused by Mechanical fault is denoted by
―M‖ and by ‗F‖, ―E‖ & ―O‖ which are caused by production, electrical and others reason
respectively. In most of the cases CCRO segregate the stoppages into their subtypes and
method manager validate them. Although LSC has an excellent system in-place to classify
the stoppages, it was noticed that most of the stoppages was not segregated properly to their
types and subtypes. To eliminate this problem a tool was developed as below and the CCRO
was educated on the stoppages classification guideline. The most important thing a guideline
was developed so that all the stoppages can be segregated effectively and scope was also
generated so that discipline heads can provide their feedback in the monthly reliability
meeting as well as any time within the month.
Table 4.1: Sample data analysis for proper allocation of different incidental stoppages
FINISH GRINDING SYSTEM (LINE- 1)
Total Stoppage Hrs Incident Planned Circumstance Description total hrs Frequenc
y total hrs
Frequency total hrs Freque
ncy CM-1 99.91 15 0 0 368.68 3
49
Incident Stoppage Hrs/Dept
total hrs
Frequency total days
Cement Loss (KT)
CM-1 mechanical 67.34 3 2.81 5.66
CM-1 electrical 10.65 7 0.44 0.89
CM-1 production 9.13 2 0.38 0.77 Others (Incident) 12.7
9 3 0.53 1.07 Not Considered 0 0 0.00 0.00 Total 99.9
1 15 4.16 8.39
Causes for Incident Stoppage
Apparent Causes Designation frequency
hours %
Clinker transport belt to hooper (402BC01) Belt torn out 2 55.4 55.4
Power failure/Dip (External) Gas engine maintenance 3 12.8 12.8
Power distribution site Insulation of 6.6 KV power line damage 2 5.97 6.0
Gypsum/Additive apron feeder (403AF01)
Input pinion of geared motor damage 1 12 12.0
Clinker weigh feeder (416WF02) Load cell replacement 2 1.77 1.8 Separator gearbox lubrication unit (416LU03) Low temperature 1 8.09 8.1
Separatoe fan (416FA04) RTD malfunctioning 1 1.64 1.6 Slide shoe bearing outlet lubrication unit (416LU02)
Cooling water LL level malfunctioning 1 1.04 1.0
Silo feed bucket elevator (418BE01) Belt sway 1 0.72 0.7
Mill Venting fan (416FA07) Damper Electrical feedback missing 1 0.56 0.6
Total 15 99.9 100.0
After evaluating all the stoppages in their right types and subtypes a study was carried out to
identify the incident which are most likely to be considered as avoidable my the means of
Autonomous Maintenance i.e. by implementing proper inspection, cleaning, restoring the
equipments in their original state and providing the proper training to the operators and
50
technician and all establishing the involvement of all departments i.e. maintenance,
production and process in maintaining the equipments. Collected data and actions where AM
are suggested are included in appendix A, B, C & D for different process systems.
4.2 Stoppages Analysis
4.2.1 Stoppages distribution by discipline For identifying the discipline strength, weakness in the system and better understanding of
the causes all the incidental stoppages were divided into the subtypes which are presented in
the figure 4.1. It was distributed as a percentage of stoppages hours caused by the particular
discipline to the total stoppages hours. It was also calculated after eliminating the stoppages
by the means of AM how they are distributed.
Fig 4.1: Distribution of stoppages by percentage among different discipline
4.2.2 Pareto Analysis
Pareto analysis is a statistical technique in decision making that is used for selection of a
limited number of tasks that produce significant overall effect. It uses the Pareto principle –
the idea that by doing 20% of work, 80% of the advantage of doing the entire job can be
generated
Pareto analysis is a formal technique useful where many possible courses of action are
competing for attention. In essence, the problem-solver estimates the benefit delivered by
each action, then selects a number of the most effective actions that deliver a total benefit
reasonably close to the maximal possible one.
Pareto analysis is a creative way of looking at causes of problems because it helps stimulate
thinking and organize thoughts. However, it can be limited by its exclusion of possibly
30%
27%
19%
24%
Stoppages before AM
CHSIM
CHSIE
CHSIF
CHSIO
29%
26%21%
24%
Stoppahes after AM
CHSIM
CHSIE
CHSIF
CHSIO
51
important problems which may be small initially, but which grow with time. It should be
combined with other analytical tools such as failure mode and effects analysis and fault tree
analysis for example
4.2.2.1 Burning System
Table 4.2: Pareto Analysis of stoppages in Burning System
App. Causes Code
Cause Code Designation Hours % Frequ
ency % Average %
8 0 137.46 36.77 18 18.18 27.47 1 0 66.87 17.89 4 4.04 10.96 312SM01 0 9.56 2.56 19 19.19 10.88 316BP01 9 Refractory 28.41 7.6 1 1.01 4.3 313XY01 0 3.26 0.87 7 7.07 3.97 317CC01 3 Plugging 17.33 4.63 3 3.03 3.83 5 0 5.4 1.45 6 6.06 3.75 26 0 12.11 3.24 4 4.04 3.64 317CC01 4 Snowmen 18.57 4.97 2 2.02 3.49 314FA01 7 Bearings 21.63 5.79 1 1.01 3.4 314FA01 6 Motor 7.04 1.88 4 4.04 2.96 313CA01 5 Sensors / Instrumentation 2.74 0.73 5 5.05 2.89 312XY01 0 2.48 0.66 5 5.05 2.86 312BE01 4 Sensors / Instrumentation 4.6 1.23 4 4.04 2.63
317CR01 4 Internals (Hammers, Jaws, Cone…) 14.84 3.97 1 1.01 2.49
317CC01 0 6.61 1.77 3 3.03 2.4 6 0 1 0.27 4 4.04 2.15 317CR01 8 Overloading 12.16 3.25 1 1.01 2.13 316DR02 12 Vibrations 0.6 0.16 4 4.04 2.1 312FA07 7 Bearings 1.22 0.33 3 3.03 1.68
Fig 4.2: Pareto Analysis for Burning System
0
5
10
15
20
25
30
8 1
312
SM0
1
316B
P01
313
XY0
1
317
CC
01
5
26
317C
C01
314F
A01
314F
A01
313C
A01
312
XY0
1
312B
E01
317
CR
01
317
CC
01
6
317
CR
01
316
DR
02
312F
A07
%
Apparent Causes
52
4.2.2.2 Raw Grinding System
Table 4.3: Pareto Analysis of stoppages in Burning System
App. Causes Code
Cause Code
Designation Hours % Frequency % Average %
216FE04 0 127.19 19.25 40 11.83 15.54 216VV01 0 23.62 3.57 40 11.83 7.7 216SP01 4 Casing 93.46 14.14 2 0.59 7.37 216HO02 0 38.52 5.83 25 7.4 6.61 5 0 32.2 4.87 25 7.4 6.13 8 0 50.43 7.63 10 2.96 5.3 216BC02 1 Alignment 12.56 1.9 24 7.1 4.5 216PU01 0 32.39 4.9 11 3.25 4.08 19 0 39.22 5.93 6 1.78 3.86 212QR01 0 19.17 2.9 9 2.66 2.78
216BE01 4 Sensors / Instrumentation 8.78 1.33 13 3.85 2.59
216WF02 7 Drum assembly 24.72 3.74 3 0.89 2.31 212BC05 3 Plugging 14.93 2.26 6 1.78 2.02 212QR02 0 6.63 1 10 2.96 1.98 216WF02 3 Plugging 8.03 1.22 9 2.66 1.94 216WF02 0 8.01 1.21 9 2.66 1.94 216BE01 3 Plugging 14.85 2.25 5 1.48 1.86
216LU04 3 Sensors / Instrumentation 4.73 0.72 9 2.66 1.69
216FA05 0 19.68 2.98 1 0.3 1.64 9 0 3.81 0.58 7 2.07 1.32 216HO01 0 7.29 1.1 5 1.48 1.29 212BC04 3 Plugging 7.12 1.08 5 1.48 1.28
216MV01 6 Sensors / Instrumentation 5.1 0.77 5 1.48 1.13
216BC02 5 Slippage 3.1 0.47 6 1.78 1.12 216WF02 2 Belt 8.21 1.24 3 0.89 1.06 212DG02 5 Chain / Links 6.03 0.91 4 1.18 1.05 216MV01 0 3.25 0.49 5 1.48 0.99 216MV01 12 Overloading 3.01 0.46 5 1.48 0.97
216LU01 3 Sensors / Instrumentation 2.91 0.44 5 1.48 0.96
216FA05 8 Temperature 2.87 0.43 5 1.48 0.96 216DR01 0 2.11 0.32 5 1.48 0.9
216FA05 2 Sensors / Instrumentation 5.97 0.9 3 0.89 0.9
212HO01 0 3.73 0.56 4 1.18 0.87 216AW01 0 5.61 0.85 3 0.89 0.87
216BC02 4 Sensors / Instrumentation 3.6 0.55 4 1.18 0.86
216LU03 8 Oil / Grease 3.15 0.48 4 1.18 0.83 216WF01 11 Transmission 4.82 0.73 3 0.89 0.81
53
Fig 4.3: Pareto Analysis for Raw Grinding System
4.2.2.3 Finish Grinding System (Line-1)
Table 4.4: Pareto Analysis of stoppages in Finish Grinding System (line-1)
App. Causes Code
Cause Code
Designation Hours % Frequency % Average %
5 0 65.73 8.28 27 11.44 9.86 403CR01 0 67.08 8.45 4 1.69 5.07 416LU02 6 Filter 52.73 6.64 8 3.39 5.01 416LU02 8 Oil / Grease 48.14 6.06 8 3.39 4.73 403CR01 8 Overloading 54.09 6.81 6 2.54 4.68 402BC01 6 Belt assembly 55.36 6.97 2 0.85 3.91
416MB01 10 Rings, Slide shoe bearings 23.04 2.9 11 4.66 3.78
416MB01 11 Bearing temperature 19.8 2.49 11 4.66 3.58 418VV01 0 22.74 2.86 10 4.24 3.55 416HO03 0 26.78 3.37 7 2.97 3.17 416WF01 5 Sensors / Instrumentation 26.49 3.34 7 2.97 3.15 416FA07 12 Damper 15.59 1.96 8 3.39 2.68 416LU02 10 Pump 17.73 2.23 6 2.54 2.39 416WF02 3 Plugging 22.61 2.85 4 1.69 2.27 416FA02 2 Sensors / Instrumentation 15.46 1.95 6 2.54 2.24 26 0 9.26 1.17 6 2.54 1.85 416VN03 0 8.84 1.11 6 2.54 1.83 416LU01 1 Automation 8.81 1.11 6 2.54 1.83 921CM04 0 24.55 3.09 1 0.42 1.76 416DC02 4 Sensors / Instrumentation 10.66 1.34 5 2.12 1.73 416WF01 3 Plugging 3.83 0.48 7 2.97 1.72 403AF01 10 Motor 21.42 2.7 1 0.42 1.56 416LU01 3 Sensors / Instrumentation 3.51 0.44 6 2.54 1.49
0
2
4
6
8
10
12
14
16
18%
Apparent Causes
54
App. Causes Code
Cause Code
Designation Hours % Frequency % Average %
418AS03 0 9.86 1.24 4 1.69 1.47 19 0 8.47 1.07 4 1.69 1.38 9 0 6.46 0.81 4 1.69 1.25
416LU02 7 Leakage (Gasket, Bolting…) 12.87 1.62 2 0.85 1.23
0 0 4.53 0.57 4 1.69 1.13 416SP01 3 Sensors / Instrumentation 7.38 0.93 3 1.27 1.1 416DC02 1 Automation 5.96 0.75 3 1.27 1.01 428VV01 0 2.35 0.3 4 1.69 1 403AF01 12 Reducer 11.98 1.51 1 0.42 0.97 921CM04 8 Motor 11.76 1.48 1 0.42 0.95 416SC02 2 Plugging 4.49 0.56 3 1.27 0.92 426DC02 6 Bags 11.16 1.4 1 0.42 0.91 416DR01 5 Gearbox lubrication 4.34 0.55 3 1.27 0.91 416LU02 0 3.96 0.5 3 1.27 0.88 416HO02 0 7.13 0.9 2 0.85 0.87 416SP01 2 Plugging 3.17 0.4 3 1.27 0.84 416AW01 0 3.16 0.4 3 1.27 0.83 416FA02 0 6.39 0.8 2 0.85 0.83 416VV03 0 3.02 0.38 3 1.27 0.83 416DC01 2 Plugging 9.36 1.18 1 0.42 0.8 418AS03 3 Plugging 2.4 0.3 3 1.27 0.79 416WF01 4 Calibration 5.56 0.7 2 0.85 0.77 416WF02 5 Sensors / Instrumentation 2.19 0.28 3 1.27 0.77 416LU01 0 2.17 0.27 3 1.27 0.77 416LU01 10 Pump 2.04 0.26 3 1.27 0.76 416LU02 3 Sensors / Instrumentation 1.94 0.24 3 1.27 0.76 416LU03 4 Heat exchanger 8.09 1.02 1 0.42 0.72 402VV02 0 7.9 0.99 1 0.42 0.71
Fig 4.4: Pareto Analysis for Finish Grinding System (Line-1)
0
2
4
6
8
10
12
5
416L
U0
2
403C
R01
416M
B0
1
41
8VV
01
416
WF0
1
416L
U0
2
416F
A02
41
6VN
03
921
CM
04
416
WF0
1
416L
U0
1
19
416L
U0
2
41
6SP
01
42
8VV
01
921
CM
04
426D
C02
416L
U02
41
6SP
01
416F
A02
416
DC
01
416
WF0
1
416L
U0
1
416L
U0
2
40
2VV
02
%
Apparent Causes
55
4.2.2.4 Finish Grinding System (Line-2)
Table 4.5: Pareto Analysis of stoppages in Finish Grinding System (line-2)
App. Causes Code
Cause Code
Designation Hours % Frequency % Average %
5 0 46.38 5.56 22 11.6 8.57 428VV01 0 37.59 4.5 15 7.89 6.2 403CR01 0 62.59 7.5 6 3.16 5.33 403CR01 8 Overloading 55.87 6.69 6 3.16 4.92 426DC02 2 Plugging 27.23 3.26 8 4.21 3.74 426WF01 5 Sensors / Instrumentation 37.59 4.5 4 2.11 3.3 402BC01 6 Belt assembly 45.99 5.51 1 0.53 3.02 9 0 19.34 2.32 7 3.68 3 19 0 17.67 2.12 7 3.68 2.9 426MB01 0 23.27 2.79 5 2.63 2.71 402BC01 0 37.22 4.46 1 0.53 2.49 426LU02 8 Oil / Grease 8.78 1.05 7 3.68 2.37 426DC02 6 Bags 27.35 3.28 2 1.05 2.16 426DR01 3 Sensors / Instrumentation 13.58 1.63 5 2.63 2.13
426DC02 5 Leakage (Gasket, Bolting…) 15.54 1.86 4 2.11 1.98
426DR01 5 Gearbox lubrication 14.02 1.68 4 2.11 1.89 426WF01 4 Calibration 17.56 2.1 3 1.58 1.84 426HO03 0 12.16 1.46 4 2.11 1.78 426FA04 13 Vibrations 23.47 2.81 1 0.53 1.67 26 0 5.66 0.68 5 2.63 1.65 403AF01 10 Motor 22.68 2.72 1 0.53 1.62 426MB01 11 Bearing temperature 9.35 1.12 4 2.11 1.61 428BE01 0 13.73 1.64 3 1.58 1.61 426DC02 0 8.66 1.04 4 2.11 1.57 426DR01 7 Motor 11.43 1.37 3 1.58 1.47 426FA04 0 19.71 2.36 1 0.53 1.44 426MB01 12 Mill shell, Doors 17.24 2.07 1 0.53 1.3 426BE01 13 Overloading 8.43 1.01 3 1.58 1.29 428BE01 1 Alignment 7.62 0.91 3 1.58 1.25 420DH03 0 2.73 0.33 4 2.11 1.22 416DR01 7 Motor 5.62 0.67 3 1.58 1.13 921CM04 8 Motor 12.63 1.51 1 0.53 1.02 426LU03 8 Oil / Grease 3.63 0.44 3 1.58 1.01 426FA04 2 Sensors / Instrumentation 3.6 0.43 3 1.58 1 426DR01 10 Bearings 3.34 0.4 3 1.58 0.99 402BC02 3 Plugging 11.54 1.38 1 0.53 0.95 426DC02 4 Sensors / Instrumentation 2.55 0.31 3 1.58 0.94 403BC03 3 Plugging 11.15 1.33 1 0.53 0.93 418FA07 0 11.08 1.33 1 0.53 0.93 426VV03 0 1.77 0.21 3 1.58 0.9 428BE01 4 Sensors / Instrumentation 5.85 0.7 2 1.05 0.88 403AF01 3 Plugging 5.18 0.62 2 1.05 0.84 402VV02 0 9.51 1.14 1 0.53 0.83 426SM01 0 4.83 0.58 2 1.05 0.82 402PA01 0 8.71 1.04 1 0.53 0.78
56
App. Causes Code
Cause Code
Designation Hours % Frequency % Average %
6 0 4.25 0.51 2 1.05 0.78 402PA01 0 8.32 1 1 0.53 0.76 402FV06 0 3.83 0.46 2 1.05 0.76 403AF01 5 Slippage 8.04 0.96 1 0.53 0.74 426DC02 8 Cleaning system 7.98 0.96 1 0.53 0.74 426RA08 2 Plugging 3.44 0.41 2 1.05 0.73 418AS01 3 Plugging 7.74 0.93 1 0.53 0.73 426LU03 6 Filter 3.31 0.4 2 1.05 0.72 426LU04 8 Oil / Grease 3.09 0.37 2 1.05 0.71 403CR01 3 Casing 7.12 0.85 1 0.53 0.69 403BC01 0 6.36 0.76 1 0.53 0.64
Fig 4.5: Pareto Analysis for Finish Grinding System (Line-2)
0
1
2
3
4
5
6
7
8
9
5
403C
R01
402B
C01
426M
B01
426D
C02
426D
R01
426F
A04
426M
B01
426D
R01
426B
E01
416D
R01
426F
A04
426D
C02
426V
V03
402V
V02
6
403A
F01
418A
S01
403C
R01
%
Apparent Causes
57
4.2.3 Root Cause Analysis (RCA)
Root cause analysis (RCA) is a class of problem solving methods aimed at identifying the
root causes of problems or events. The practice of RCA is predicated on the belief that
problems are best solved by attempting to address, correct or eliminate root causes, as
opposed to merely addressing the immediately obvious symptoms. By directing corrective
measures at root causes, it is more probable that problem recurrence will be prevented.
Causes of all the data collected is not readily identified on site. The apparent cause i.e the
equipment which is responsible for the particular incident can by identified easily, but the
underlying cause is often stayed hidden and for better management of the down time it is
essential to identify all of them. In LSC RCA is used to identify those all possible root causes
using APPOLP RCA methodology. Basically RCA was conducted for the causes identified
by Pareto analysis.
Here is an example (part of RCA conducted for the incident of Kiln stoppages due to
313FA01
58
Fig 4.6: RCA Sample (Flow diagram)
59
4.3 Effect of AM on Reliability
4.3.1 Burning System
Opening hour (year 2008)
Number of total days in 2008 is 366
So, Opening hour in 2008 = 366X24 = 8784 hours
Cummulitative hours of stoppages in 2008 is 402.81 hrs
RF = Operating hours / [Operating hours + Incident stoppage hours]
= Hours Worked / [Hours Worked + Incident stoppage hours]
RF= 8784/ (8784+402.81)
= 95.03 %
UF = Operating hours / Avialable hours
= Working Hours/ Opening Hours
= 7704.38/8784
=87.71%
After proposed AM
Cummulitative hours of stoppages in 2008 after AM is202.27 hrs
RF= 8784/ (8784+202.27)
= 97.51 %
UF = 7904.9/8784
=89.99%
4.3.2 Raw Grinding System
Opening hour (year 2008)
Number of total days in 2008 is 366
So, Opening hour in 2008 = 366X24 = 8784 hours
Cummulitative hours of stoppages in 2008 is 774.56 hrs
60
RF = Operating hours / [Operating hours + Incident stoppage hours]
= Hours Worked / [Hours Worked + Incident stoppage hours]
RF= 8784/ (8784+774.56)
= 89.97 %
UF = Operating hours / Avialable hours
= Working Hours/ Opening Hours
= 6944.43/8784
=79.06%
After proposed AM
Cummulitative hours of stoppages in 2008 after AM is 334.07 hrs
RF= 8784/ (8784+334.07)
= 95.67 %
UF = 7384.92/8784
= 84.07%
4.3.3 Finish Grinding System (Line-1)
Opening hour (year 2008)
Number of total days in 2008 is 366
So, Opening hour in 2008 = 366X24 = 8784 hours
Cummulitative hours of stoppages in 2008 is 928.21 hrs
RF = Operating hours / [Operating hours + Incident stoppage hours]
= Hours Worked / [Hours Worked + Incident stoppage hours]
RF= 8784/ (8784+928.21)
= 81.23 %
UF = Operating hours / Avialable hours
= Working Hours/ Opening Hours
= 4018.14/8784
=45.74%
61
After proposed AM
Cummulitative hours of stoppages in 2008 after AM is 298.79 hrs
RF= 8784/ (8784+298.79)
= 93.96 %
UF = 4647.56/8784
= 52.91%
4.3.4 Finish Grinding System (Line-2)
Opening hour (year 2008)
Number of total days in 2008 is 366
So, Opening hour in 2008 = 366X24 = 8784 hours
Cummulitative hours of stoppages in 2008 is 937.13 hrs
RF = Operating hours / [Operating hours + Incident stoppage hours]
= Hours Worked / [Hours Worked + Incident stoppage hours]
RF= 8784/ (8784+937.13)
= 84.67 %
UF = Operating hours / Avialable hours
= Working Hours/ Opening Hours
= 5174.43/8784
=58.91%
After proposed AM
Cummulitative hours of stoppages in 2008 after AM is 349.92 hrs
RF= 8784/ (8784+349.92)
= 94.27 %
UF = 5761.65/8784
= 65.59%
62
4.4 Effect of AM on OEE
4.4.1 Burning System
Rated capacity of the kiln= 3600 tpd
Total production in year 2008 = 1371762 ton
Actual Average Output=3438 tpd
Performance Rate
= X 100%
= (3438/3600) X 100%
=95.05%
Overall Equipment Efficiency
= Availability x performance rate x Quality rate
= Reliability x performance rate x Quality rate (In LSC term)
=95.03%X95.50%X1
=.91
Note: (As rejection rate for quality problem is almost zero quality rate is considered 1)
After proposed AM
Overall Equipment Efficiency
=97.51%X95.50%X1
=.93
4.4.2 Raw Grinding System
Rated capacity of the kiln= 278 tph
Total production in year 2008 = 2160864 ton
Actual Average Output=246 tph
Performance Rate
63
= X 100%
= (246/278) X 100%
=88.49%
Overall Equipment Efficiency
= Availability x performance rate x Quality rate
= Reliability x performance rate x Quality rate (In LSC term)
=89.97%X88.49%X1
=.80
Note: (As rejection rate for quality problem is almost zero quality rate is considered as
1.
After proposed AM
Overall Equipment Efficiency
=95.67%X88.49%X1
=.85
4.4.3 Finish Grinding System (Line-1)
Rated capacity of the kiln= 120 tph
Total production in year 2008 = 746640 ton
Actual Average Output=85 tph
Performance Rate
= X 100%
= (85/120) X 100%
=70.83%
Overall Equipment Efficiency
= Availability x performance rate x Quality rate
64
= Reliability x performance rate x Quality rate (In LSC term)
=81.23%70.83%X1
=.58
Note: (As rejection rate for quality problem is almost zero quality rate is considered as
1)
After proposed AM
Overall Equipment Efficiency
=93.96%X70.83%X1
=.67
4.4.4 Finish Grinding System (Line-2)
Rated capacity of the kiln= 120 tph
Total production in year 2008 = 878400 ton
Actual Average Output=100 tph
Performance Rate
= X 100%
= (100/120) X 100%
=83.33%
Overall Equipment Efficiency
= Availability x performance rate x Quality rate
= Reliability x performance rate x Quality rate (In LSC term)
=84.67%X83.33%X1
=.71
Note: (As rejection rate for quality problem is almost zero quality rate is considered as
1)
After proposed AM
Overall Equipment Efficiency
=94.27%X83.33%X1
=.79
65
CHAPTER-5: RESULTS AND DISCUSSIONULTS AND DISCUSSION
RESULTS AND DISCUSSION 5.1 Results
Table 5.1: Present status of plant performance and effect of AM
Present Status After proposed AM
Kiln VRM CM1 CM2 Kiln VRM CM1 CM2 OEE 0.91 0.80 0.58 0.71 0.93 0.85 0.67 0.79
PF (%) 95.50 88.49 70.83 83.33 95.50 88.49 70.83 83.33
RF (%) 95.03 89.97 81.23 84.67 97.51 95.67 93.96 94.27
UF (%) 87.71 79.06 45.74 58.91 89.99 84.07 52.91 65.59
OH (Hrs) 8784 8784 8784 8784 8784 8784 8784 8784
HW (Hrs) 7704.36 6944.43 4018.14 5174.43 7904.9 7384.92 4647.56 5761.65
Output (Tph) 3438 246 85 100 3438 246 85 100
Rated Capacity (Tph) 3600 278 120 120 3600 278 120 120
CHS (hrs) 1079.64 1839.57 4765.86 3609.57 879.1 1399.08 4136.44 3022.35
NS (nos) 194 518 398 333 106 247 232 215
CHSI (hrs) 402.81 774.56 928.21 937.13 202.27 334.07 298.79 349.92
CHSP (hrs) 611.98 704.88 236.88 200.71 611.98 704.88 236.88 200.71
CHSC (hrs) 64.85 360.13 3600.77 2471.72 64.85 360.13 3600.77 2471.72
NSFI (Nos) 147 435 295 238 58 172 143 140
NSFP (Nos) 37 16 13 12 37 16 13 12
NSFC (Nos) 11 59 76 63 11 59 76 63
CHSIM (%) 44.88 48.3 27.75 39.65 39.69 58.68 32.24 25.11
CHSIE (%) 13.12 23.06 32.74 32.23 11.56 29.30 42.20 52.77
CHSIF (%) 38 28.64 39.51 28.12 45.65 12.02 25.50 22.07
CHSIO (%) 4.00 0.00 0.00 0.00 3.10 0 0 0
NSFIM (Nos) 24 124 83 63 8 39 43 24
NSFIE (Nos) 69 132 137 107 23 90 74 79
NSFIP (Nos) 45 179 75 68 18 43 26 37
NSFIO (Nos) 9 0 0 0 9 0 0 0
66
The result shows that performance of the plant is not meeting the group standard which is
98% in terms of reliability.
Above table represents all the calculations for OEE for the different process systems. It
shows the different types of stoppages and their duration. It also shows the subtypes of
the incidental stoppages with duration and frequency. This table also represents the rated
production capacity for each section and as well achieved rate and ultimately the
performance rate.
5.2 Discussion
From the analysis and calculation it found that the performance of the plant is not meeting
the group standard which is 98% in terms of reliability. These triggered to the
requirement of better management of all the equipment as well as the plant. As LSCL is a
cement manufacturing company which raw material is shale, sand , iron ore, limestone ,
gypsum etc. it is a real challenge to achieve the cleaning standard and maintain the basic
equipment condition without having the underneath goal of those. A better team effort is
the key to be successful in achieving the target by implementing AM. Management also
needs to pay more concern for managing the stoppages in better way and addressing the
recurrence stoppages.
Fig 5.1: Present status of plant RF and effect of AM
Kiln VRM CM1 CM2
Before 95.03 89.97 81.23 84.67
After AM 97.51 95.67 93.96 94.27
0
20
40
60
80
100
120
%
RF for Diiferent Process System
67
The figure shows the effect of AM on the reliability factor. It shows that the reliability factors
for the burning systems can be increased with out putting to much effort but implementing
the AM by 2.48% i.e the down time can be reduced by 200.54 hours. This also increase the
reliability factor of the Raw Grinding Systems, Finish Grinding System (Line-1) & Line 2 by
5.7%, 12.73% and 9.6% respectively which are equivalent to reducing the downtime by
440.49 hrs, 629.42 hrs and 587.21 hrs respectively.
Fig 5.2: Present status of plant OEE and effect of AM
The figure 5.2 shows the effect of AM on the Overall Plant Effectiveness. It shows that OEE
for the burning systems can be increased with out putting to much effort but implementing
the AM by 0.02 and by .05, 0.09 and 0.08 for the process stages Raw Grinding Systems,
Finish Grinding System (Line-1) & Finish Grinding (Line 2) respectively.
The analysis also revealed that competency of the present staffs is quite impressive to meet
the requirement for better management of the stoppages but need specific training on this
particular issue. The management level also need to provide more emphasis so that all the
data are managed in the proper way otherwise the reliability of the data will be questionable.
And wit out reliable data any sort of analysis will present a false impression. So all the
relevant staffs need to achieve better understanding of the stoppage guideline and ADAP.
CHSIM CHSIE CHSIF CHSIO
Before 0.91 0.80 0.58 0.71
After AM 0.93 0.85 0.67 0.79
0.000.100.200.300.400.500.600.700.800.901.00
OEE of different process systems
68
From the analysis result it is highly recommended to implement the Autonomous
Maintenance involving all the respective discipline. For implementing the AM following
steps are recommended which will well adjust with the existing LSCL organization.
Perform Initial Cleaning
The goal of the initial cleaning should include
o Eliminate dust and dirt from main body of equipment
o Expose irregularities such as slight defects, contamination sources,
inaccessible places,
o Sources of quality defects
o Eliminate unnecessary and seldom-used items, and simplify equipment
Address contamination source and inaccessible places
The goal of the addressing contamination source and inaccessible places is to reduce
housekeeping time by eliminating, sources of dust and dirt, preventing scatter, and improving
parts that are hard to clean, check, lubricate, tighten, or manipulate
Establish cleaning and checking standard
The activities for this step includes
o Formulate work standards that help maintain cleaning, lubricating, and
tightening levels with minimal time and effort
o Improve the efficiency of checking work introducing visual controls
Conduct general equipment inspection
The activities for this step includes
o Provide inspection skills training based on inspection manuals
o Get individual equipment items into peak condition by subjecting them to
general inspection
o Modify equipment to facilitate checking. Make extensive use of visual
controls
Perform general process inspection
The activities for this step includes
o Provide instruction in process performance, operation, and adjustment and in
methods of handling abnormalities in order to improve operational reliability
by developing process competent operators
69
o Prevent inspection duplications and omissions by incorporating provisional
cleaning and inspection standards for individual equipment items into periodic
inspection and replacement standards for entire processes or systems
Systematic autonomous maintenance
The activities for this step includes
o Achieve quality maintenance and safety by establishing clear procedures and
standards for dependable autonomous maintenance
o Improve setup procedures and reduce work-in-process
o Establish a system of self-management for workplace flow, spares, tools,
work-in-process, final products, data, et
Practice full self-management
The activities for this step includes
o Evolve activities and standardize improvements in line with company and
plant policies and objectives, and reduce costs by eliminating workplace waste
o Improve equipment further by keeping accurate maintenance records (e.q.,
MTBF) and analyzing the data in them
For implementing the steps 3, 4 and 5 some generic standard are presented in below…
Table 6.1: Checkpoints for Nuts and Bolts
Slight Defects
Are any nuts or bolts loose?
Are any nuts or bolts missing?
Bolt Lengths Do all bolts protrude from nuts by 2-3 thread length
Washers
Are flat washers used on long holes?
Are tapered washers used on angle bars and channels?
Are spring washers used where parts are subject to vibration?
Are identical washers used on identical parts?
Attachment of
Nuts and Bolts
Are bolts inserted from bottom, and visible from the outside?
Are devices such as limit switches secured by at least two bolts?
Are wing nuts on the right way around?
70
Table 6.2: Checkpoints for Electrical Equipments
Control
Panels
Are the interiors of distribution boards, switchboards, and control
panels kept clean, tidy, and well-organized by the application of the
5S principles?
Have any extraneous objects or flammable materials been left
inside?
Is the wiring inside control panels in good condition?
Are any wires coiled or trailing?
Are all ammeters and voltmeters operating correctly and clearly
marked?
Are any instruments or display lamps broken? Are any bulbs
faulty?
Are any switches broken? Do all switches work correctly?
Are control panel doors in good condition? Do they open and close
easily?
Are there any unused holes? Are control panels waterproof and
dustproof?
Electrical
Equipment
Are all motors free of overheating, vibration, and unusual noise and
smells?
Are all motor cooling fans and fins clean?
Are any attachment bolts loose? Are pedestals free of cracks and
other damage?
Sensors Are all limit switches clean and free of excessive play?
Are the interiors of all limit switches clean?
Are any wires trailing? Are all covers in good condition?
Are any limit switches incorrectly installed?
Are any limit switch dogs worn, deformed, or the wrong shape?
Are all photoelectric switches and proximity switches clean and
free of excessive play?
Are any sensors out of position? Are correct positions clearly
indicated?
Are all lead wires unchafed, and is insulation intact at entry points?
71
Switches Are all manual switches clean, undamaged, and free of excessive
play?
Are all switches installed in the correct position?
Are emergency stop switches installed in appropriate locations, and
are they working correctly?
Piping and
Wiring
Are any pipes, wires, or power leads loose or unsecured?
Are any ground wires damaged or disconnected?
Are any pipes corroded or damaged? Are there any bare wires or
wires with damaged insulation?
Are any wires coiled on the floor or dangling overhead?
Table 6.3: Checkpoints for Hydraulic Equipments
Hydraulic
Units
Is the correct quantity of fluid in hydraulic reservoirs, and is the
correct level indicated?
Is fluid at the correct temperature? Are the maximum and minimum
permissible temperatures indicated?
Is fluid cloudy (indicating air entrainment)?
Are all fluid inlets and strainers clean?
Are any suction filters blocked?
Are any fluid reservoir breather filters blocked?
Are all fluid pumps operating normally without any unusual noise
or vibration?
Are hydraulic pressures correct, and are operating ranges clearly
displayed?
Heat
Exchangers
Is any fluid or water leaking from fluid coolers or pipes?
Are temperature differences between fluid and water inlets and
outlets correct?
Are any tubes blocked?
Hydraulic
Equipment
Are there any fluid leaks?
Are hydraulic devices properly secured without any makeshift
fastenings?
72
Are hydraulic devices operating correctly without speed losses or
breathing?
Are hydraulic pressures correct, and are all pressure gauges
working correctly (zero points, deflection) ?
Piping and
Wiring
Are all pipes and hoses securely attached?
Are there any fluid leaks?
Are any hoses cracked or damaged?
Are all valves operating correctly?
It is easy to see whether valves are open or shut?
Are any pipes, wires, or valves unnecessary?
Table 6.4: Checkpoints for Pneumatic Equipments
FRLs Are FRLs always kept clean?
Is it easy to see inside them?
Are they fitted the right way around?
Is there sufficient oil, and are the drains clear?
Is the oil drip rate correct (approximately 1 drop for every 10
strokes)?
Are FRLs installed no more than 3m from the pneumatic
equipment?
Are pressures adjusted to the correct value and are operating ranges
clearly indicated?
Pneumatic
Equipment
Is any compressed air leaking from pneumatic cylinders or solenoid
valves?
Are all pneumatic cylinders and solenoid valves firmly attached?
Are any makeshift fixings in use (wire, adhesive tape, etc.)?
Is speed controllers installed the right way around?
Is there any abnormal noise or overheating of solenoid valves, and
are any lead wires chafed or trailing?
73
Piping and
Wiring
Are there any places in pneumatic pipes or hoses where fluid is
liable to collect?
Are all pipes and hoses clipped firmly into place?
Are there any compressed-air leaks?
Are any hoses cracked or damaged?
Are all valves operating correctly?
Is it easy to see whether valves are open or closed?
Are any pipes, wires, or valves unnecessary?
Table 6.5: Checkpoints for Transmission
V-belts and
Pulleys
Are any belts cracked, swollen, worn, or contaminated by oil or
grease?
Are any belts twisted or missing?
Are any belts stretched or slack?
Are multiple belts under uniform tension and all of the same type?
Are top surfaces of belts protruding above the pulley rims?
Are the bottoms of any pulley grooves shiny (indicating a worn belt
or pulley)?
Are pulleys correctly aligned?
Roller Chains Are any chains stretched (indicating worn pins or bushings)?
Are any sprocket teeth worn, missing, or damaged?
Is lubrication between pins and bushings sufficient?
Are sprockets correctly aligned?
Shafts,
Bearings, and
Couplings
Is there any overheating, vibration, or abnormal noise due to
excessive play or poor lubrication?
Are any keys or set bolts loose or missing?
Are any couplings misaligned or wobbly?
Are any coupling seals worn? Are any bolts slack?
Gears Are gears properly lubricated with the right amount of lubricant?
Are the surroundings clean?
Are any teeth worn, missing, damaged, or jammed?
Is there any unusual noise or vibration?
74
Table 6.6: Lubrication Checkpoints
Lubricant
Storage
Are lubricant stores always kept clean, tidy, and well-organized by
thorough application of the 5S principles? *
Are lubricant containers always capped?
Are lubricant types clearly indicated and is proper stock control
practiced?
Lubricant
Inlets
Are grease nipples, speed-reducer lubricant ports, and other
lubricant inlets always kept clean?
Are lubricant inlets dust proofed?
Are lubricant inlets labeled with the correct type and quantity of
lubricant?
Oil-level
Gauges
Are oil-level gauges and lubricators always kept clean, and are oil
levels easy to see?
Is the correct oil level clearly marked?
Is equipment free of oil leaks, and are oil pipes and breathers
unobstructed?
Automatic
Lubricating
Devices
Are automatic lubricating devices operating correctly and supplying
the right amount of lubricant?
Are any oil or grease pipes blocked, crushed or split?
Lubrication
Condition
Are rotating parts, sliding parts, and transmissions (e.g. chains)
always clean and well-oiled?
Are the surroundings free of contamination by excess lubricant?
Table 6.7: Checkpoints for General-Purpose Equipment
Pumps Are pumps and their stands free of unusual noise, vibration,
and play?
Are pedestal bolts tight, corrosion-free, and undamaged?
Are stands and pedestals free of corrosion, cracking, and other
damage?
Is any liquid leaking or spraying from gland packings?
75
Is any liquid leaking or spraying from pipes or valves?
Are any pipes or valves blocked?
Are all pressure gauges, vacuum gauges, flow meters,
thermometers, and other measuring instruments working
properly and marked with the correct operating ranges?
Are starting current and operating current values correct? Are
these clearly indicated?
Are all valves operating correctly?
Is it easy to see whether valves are open or closed?
Fans Are fans and their stands free of unusual noise, vibration, and
play?
Are all pedestal bolts tight, corrosion-free, and undamaged?
Are all stands and pedestals free of corrosion, cracking, and
other damage?
Are any gland packings leaking air or gas?
Are any ducts or dampers leaking air or gas?
Are any ducts blocked or clogged?
Are all pressure gauges, vacuum gauges, flow meters,
thermometers, and other measuring instruments working
properly and marked with the correct operating ranges?
Are starting current and operating current values correct? Are
these clearly indicated?
Are all dampers operating correctly?
Is it easy to see whether dampers are opened or closed?
A general guideline was also produce to eliminate the conflict among the different
departments. It is always subjected to the review of the HODs and need their approval and
recommended to implement in daily activities.
76
Fig 6.1: Distribution of maintenance activities within the discipline
77
CHAPTER-6: CONCLUSION AND
RECOMMENDATION CONCLUSION AND RECOMMENDATION
6.1 Conclusion Demand for high quality products at a reasonable cost is driving most of the manufacturers
worldwide to embrace equipment management programs like TPM. As can be seen from the
case study, TPM/AM has significantly: (1) reduced the yield loss, (2) reduced the downtime
of equipment, and (3) reduced the cost of operations and improved profitability. There is no
doubt that TPM/AM provides tremendous competitive edge to the manufacturers.
If we consider the case of Lafarge we will find that there is huge improvement in the
reliability i.e. availability of the equipment but little improvement in the overall plant
efficiency especially for both the cement mills. The reason behind this is, Lafarge don‘t
consider equipment performance as a business unit KPI (key performance indicators) rather
than only considered as a production team‘s KPI. Rather than they give more emphasis on the
utilization factor which also subjected to the better plan. For the year of 2008 utilization for
both the cement mill was very less which was due to less demand in the market as they were
fairly new in the business in Bangladesh. Both the mill was also run with a lower capacity as
that was sufficient to meet the market demand. But it is sure that if autonomous maintenance
is implemented properly LSCL will enjoy a greater benefit from this.
82
6.2 Recommendation In this project I tried to analyze the existing system in the Lafarge Surma Cement Limited. I concentrated more in the maintenance side than that of the production side. From the result it is evident that the analysis did not show any increase in the production rate as that time I did not consider the factor which are responsible for the degraded output rate. Further work on this sector is recommended. In this project the human factor also not included and I did not counted the human factor which can also effect the down time as well as the production rate. This is also another sector which can be included in further study. All the calculation was made on the basis of hypothetical assumption, so it is highly recommended to impellent the recommendations which are proposed in the result section and calculate the effects from the real life. Man-machine hour was also not analyzed in the thesis work, this is also another sector on which we can focus and analyze the financial benefit from this.
83
REFERENCES [1] Lafarge Surma Cement Ltd., Internal documents, 2008.
[2] Lafarge Surma Cement Limited, March4, 2010
http://eplbangladesh.com/brokerage/research/1297916433Lafarge%20Surma%20Cement%20
(March%204,%202010).pdf (Accessed 25 April, 2010)
[3] Total productive maintenance, Industrial Press Inc., 2004, 2nd Edition, by Terry Wireman
C H A P T E R 1, The History and Impact of Total Productive Maintenance,
[4] Lungberg.O (1998), Mearsument of overall equipment effectiveness as a basic for TPM
activities. International Journal of operation.and production management 18 (5):495-507.
[5] Hananto,‖ Production‘s Maintenance, A way to speed up Autonomous Maintenance,‖
Jakarta December 2004
http://www.migas-indonesia.com/files/article/%5BMaintenance%5DZero_Breakdown.pdf
(Accessed 05 January, 2009)
[6] Leading manufacturing excellence: a guide to state-of-the-art manufacturing, Published
by John Wiley and Sons, 1997, Illustrated Edition, By Patricia E. Moody.
[7] Maintenance Engineering Handbook, McGraw Hill, 2008, Seventh Edition, By R. Keith
Mobley.
[8] W. Mark Fruin1 and Masao Nakamura (1997), ―Top-down Production Management: A
Recent Trend in the Japanese Productivity-enhancement Movement‖, Managerial and
decision economics, VOL. 18(7): 131–139
[9] TPM, total productive maintenance, Tokyo: Asian Productivity Organization, 1990,
English version, by Yoshikazu Takahashi.
[10] OEE-Overall Equipment Efficiency, ABB, by Francis Wauters and Jean Mathod
84
http://library.abb.com/global/scot/scot296.nsf/veritydisplay/4581d5d1ce980419c1256bfb006
399b9/$File/3BUS094188R0001.pdf_-_en_OEE_Whitepaper_-
_Overall_Equipment_Effectiveness.pdf (Accessed 20 April, 2010).
[11] TPM Seminar for Management, BASF, KMAC, http://lo.lafarge.com (Accessed 11 July
April, 2009)
[12] Reliability in automotive and mechanical engineering, Springer,1985,2nd Edition, by
Berned Bertsche,
[13] Electronic Reliability Design handbook, MIL-HDBK-338B, 1 October 1998
85
APPENDIX