EDS 3 Release 5
description
Transcript of EDS 3 Release 5
http://nodal.ercot.com 1Lead from the front
Texas Nodal
EDS 3 Release 5
Monday / Friday Market Updates
April 04, 2008
http://nodal.ercot.com 2Lead from the front
Texas Nodal
Agenda
• Antitrust Admonition• Submissions Update
– This Week’s Activities– Submissions Status
• Updates / Questions / Reminders• LFC Update• Q&A / Open Forum• Roll Call
http://nodal.ercot.com 3Lead from the front
Texas Nodal
Antitrust Admonition
ANTITRUST ADMONITION
ERCOT strictly prohibits Market Participants and their employees who are participating in ERCOT activities from using their participation in ERCOT activities as a forum for engaging in practices or communications that violate the antitrust laws. The ERCOT Board has approved guidelines for members of ERCOT Committees, Subcommittees and Working Groups to be reviewed and followed by each Market Participant attending ERCOT meetings. If you have not received a copy of these Guidelines, copies are available at the Client Relations desk. Please remember your ongoing obligation to comply with all applicable laws, including the antitrust laws.
http://nodal.ercot.com 4Lead from the front
Texas Nodal
Submissions Status / Submission Times for 04/04/08
3/28/2008 3/29/2008 3/30/2008 3/31/2008
95% 93% 10 96% 27% 11 46% 92% 0 46% 92% 10
COPTPOIDO OS COP
TPOIDO OS COP
TPOIDO OS COP
TPOIDO OS
• Activities for Week of 04/07/08– Submit the following during the 12:00 – 4:00pm submission
window:• COP• TPO for trade date +2 (Note: we expect to have this fixed next week –
market notice will be distributed)• Output Schedule (open to all resources)• INC/DEC (DSR resources only)
– Submit RT COP adjustments during business hours– Submit RT OS adjustments during business hours
4/1/2008 4/2/2008 4/3/2008
99% 96% 11 95% 92% 9 92% 94% 1
COPTPOIDO OS COP
TPOIDO OS COP
TPOIDO OS
http://nodal.ercot.com 5Lead from the front
Texas Nodal
Updates / Questions / Reminders
• FIP / FOP for week of 4/07/08:
– FIP: 9.515
– FOP: 21.43
• EDS Environment Outages
– MMS3 Migration Delayed (stability issues still occurring)
– Outages:• MMS Instability – Known issue to be mostly corrected with MMS3
• Occurrences: 4/7 and 4/8 (brief outages)
– Credit Limit Error• Data Set up Issue
• Have a proven resolution
• Most QSE’s are repaired. Outliers will be resolved by Monday
• QSE’s will be able to submit TPO’s day ahead again (rather than Flow Date – 2)
• Desired Offer Curve Testing – complete (only 2 make-up sessions requested)
http://nodal.ercot.com 6Lead from the front
Texas Nodal
Updates / Questions / Reminders
• Reminder – 24x7 contacts– Starting April 15th ERCOT will man the Nodal systems 24x7 and
require contacts at the MPs facility in case ERCOT sees data issues that hamper State Estimator or Transmission Constraint Management
– If the Market Participant does not want ERCOT to contact their normal shift operators they need to provide an alternate contact. Alternate contacts should be provided by email to [email protected] by April 11, 2008
http://nodal.ercot.com 7Lead from the front
Texas Nodal
LFC 6.3 pre-Test
• Prior to R6.3 (total system test) the market desires an open loop test to validate SCED dispatch. Approach to accomplish this:– QSEs w/ Resources submit Excel files with EOC, OS, INC/DEC on
4/8 that deconstruct Zonal activities for Operating period 4/7 7-9am– Perform open loop test on 4/25 from 7-9am– Perform open loop test on 5/5 from 10-noon– Perform open loop test on 4/12 from 4-6pm
• ERCOT to provide QSEs with settlement impact resulting from OOME and Local Balancing had units followed SCEB BP
• Please refer to details provided during the 3/14 workshop: http://www.ercot.com/calendar/2008/03/20080314-EDS3-6.html
http://nodal.ercot.com 8Lead from the front
Texas Nodal
Target Dates for 6.3 Tests
• Week of June 16th – 2 hour test
• Week of July 7th – 8 hour test
• Week of July 28th – 48 hour test
http://nodal.ercot.com 9Lead from the front
Texas Nodal
LFC Phase II Testing
• Results for week of 3/31
– LFC 6.2 pre-test• AEP Tuesday
• LCRA Wednesday
• OXY Thursday
– LFC 6.2 test• NRG Tuesday Rescheduled
• Scheduled Test: week of 4/07
– LFC 6.2 pre-test• Exelon Tuesday 9:00 AM
• APX Thursday 9:00 AM
– LFC 6.2 test• Suez Tuesday 1:00 PM
• Remember to submit test forms 2 business days before Test• The Date & Time Format for the test file is MM/DD/YYYY HH:MM• Submit to [email protected]
http://nodal.ercot.com 10Lead from the front
Texas Nodal
Q&A
Q&A / Open Forum