Economizer Procedure

download Economizer Procedure

of 32

Transcript of Economizer Procedure

  • 7/31/2019 Economizer Procedure

    1/32

    CxTPL Upgrade Project Oct. 31, 2001

    GENERAL COMMISSIONING PROCEDURE FOR ECONOMIZERS

    Prepared for:

    Pacific Gas & Electric Company,Customer Energy Management Non-Residential New Construction Program

    Development of a Commissioning Test Protocol Library Project

    Alyssa Newman, Project ManagerKen Gillespie, Project Lead

    Prepared by:

    Pacific Gas & Electric Company,

    Technical and Ecological Services, Performance Test and Analysis UnitRichard Fromberg

    The project Development of a Commissioning Test Protocol Library is funded by California

    utility customers and administered by Pacific Gas & Electric Company under the auspices of theCalifornia Utilities Commission.

    Legal Notice

    Pacific Gas and Electric Company (PG&E) makes no warranty or representation, expressed orimplied, with respect to the accuracy, completeness, or usefulness of the information contained in

    this report, or that the use of any information, apparatus, method, or process disclosed in this reportmay not infringe upon privately owned rights. Nor does PG&E assume any liability with respect

    to use of, or damages resulting from the use of, any information, apparatus, method, or processdisclosed in this procedure.

  • 7/31/2019 Economizer Procedure

    2/32

    CxTPL Upgrade Project Oct. 31, 2001

    CONTENTS

    General Commissioning Procedure for Economizers

    FOREWORD .1

    I. PROJECT / BUILDING DESCRIPTION...2

    II. SEQUENCES OF OPERATION...4III. ACCEPTANCE AND RESPONSIBILITIES...5

    IV. VERIFICATION CHECKS FOR REQUIRED DOCUMENTATION AND

    TRAINING.6

    V. VERIFICATION NAMEPLATE DATA CHECKS..7VI. VERIFICATION INSTALLATION CHECKLIST.10

    VII. VERIFICATION CONTROLS SENSOR CALIBRATION CHECKS.....13

    VIII. VERIFICATION BALANCE REPORT CHECKS. 14

    IX. VERIFICATION OPERATIONAL CHECKS1) EXERCISE DAMPERS15

    2) FIRE ALARM ECONOMIZER DAMPER POSITIONS.173) ECONOMIZER MODE CHECKS....18

    4) CONTROLS PROGRAM CHECKS.20

    X. FUNCTIONAL CHECKS FORCED RESPONSE AND SEQUENCE OFOPERATION TESTING FANS ON/OFF, MORNING COOL-DOWN OR

    WARM-UP, NORMAL OPERATING MODES, FIRE/SMOKE ALARM,

    FREEZE PROTECTION AS-BUILT RECORDS ..21

    XI. FUNCTIONAL TESTS ECONOMIZER PERFORMANCE TEST....25XII. FUNCTIONAL TESTS ECONOMIZER OPERATIONAL TREND TEST..26

    XIII. FUNCTIONAL TESTS M&V SAVINGS CALCULATION USING

    PERFORMANCE TRENDING TESTS ..27XIV. COMMISSIONING REPORT OUTLINE29

    XV. REFERENCES USED TO DEVELOP THE ECONOMIZER PROTOCOL30

  • 7/31/2019 Economizer Procedure

    3/32

    General Commissioning Procedure for Economizers October 31, 2001

    FOREWORD

    This procedure provides example protocols for two fictitious buildings (one located in Sacramento

    and the other in San Francisco) for steps that need to be taken to fully commission their air

    handling systems economizers. Variations are provided when requirements between the twoexamples differ. Each building has integrated, built-up economizers, with return, exhaust and

    outside air dampers, but different sequences of operation and designs.

    In commissioning an economizer, the intent is to optimize the use of outside air for cooling a

    building, in order to minimize energy use, while maintaining good indoor air quality. Our primary

    goal is to verify that the economizer is working as specified, while looking for opportunities toimprove upon its intended operation. This procedure was developed with the assistance of

    PG&Es Commissioning Test Protocol Librarys Templates. Following is an outline of what

    protocols are included here:

    Project/Building DescriptionDescription of Systems Under Test

    Equipment Covered by this ProtocolSequences of Operation

    Acceptance and Responsibilities

    Verification ChecksChecks for Documentation and Training

    Nameplate Data Checks

    Installation ChecklistControls Sensor Calibration Checks

    Balance Report Checks

    Operational Checks -1) Exercise dampers2) Fire Alarm Economizer Damper Positions

    3) Economizer Mode Checks

    4) Controls Program ChecksFunctional Tests

    Forced Response and Sequence of Operation Testing Fans On/Off, Morning Cool-down or

    Warm-up, Normal Operating Modes, Fire/Smoke Alarm, Freeze ProtectionEconomizer Performance Test

    Economizer Operational Trend Test

    M&V Savings Calculation using Performance Trending Tests Outline of Procedure

    References Used to Develop the Economizer ProtocolResults and Recommendations Report

    Richard Fromberg 3 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    4/32

    General Commissioning Procedure for Economizers October 31, 2001

    I. PROJECT / BUILDING DESCRIPTION

    BUILDING NAME and ADDRESS: APPLICATION #: 1Case 1) Sacs Service Center (SSC)

    4444 Perk Road, Sacramento CA 95826

    and

    Case 2) Petes Excellent Cuisine (PEC)185 Energy Street, San Francisco, CA 94102

    BUILDING CONTACT PERSONS and PHONE NUMBERS: 1)Zachery Sac, 916-123-4567

    2) Peter Cook, 415-123-4567

    NAME & FIRM OF PERSON(S) DOING TESTS:JR Doolittle, Hotwire Commissioning Services

    PLANNED DATE(S) OF TEST:December 21-23, 2001

    Description of Systems Under Test:

    1) The SSC has three air handler units (AHUs) #1, #2 and #3, which serve the north, south, and southeast sections of the

    main building. Supply and return fans are VFD controlled. A DDC system controls separate actuators on the outside

    air, return air and exhaust air dampers. AHU#1 and AHU#2 are roof mounted; AHU#3 is floor mounted at the east end

    of the building.

    The air handlers are designed to provide hot and cold duct air flows that will maintain 0.25 wg supply air duct static

    pressures and a supply air temperature set point of 55F. Minimum supply air rate is limited to 25% of the total

    capacity. The sequence of operation for each AHU is the same, except for scheduling differences. The environment is a

    hot/dry central valley climate with seasonal temperatures ranging from 15F -105F and the cooling load is ~75 tons @

    40,000 cfm per AHU.

    2) The PEC has one air handler unit, AHU-1, which serves a multi-zone, single duct, reheat system that conditions the

    whole building. AHU-1 is a central station, pull-thru type, roof mounted air handling unit complete with economizer

    (return, outside, exhaust) damper section, filter section, chilled water cooling coil section and fan section with variablefrequency drive (VFD) control of the supply fan motor. Exhaust fans are propeller type fans within the air handler

    exhaust section.

    The air handler is designed to provide conditioned air at the temperature and pressure required by the variable volume

    (VAV) terminal units and outside air as required for (IAQ) ventilation. It also provides exhaust air as required to

    maintain a slight building positive pressure during economizer operation. The environment is a coastal climate with

    typically mild temperatures ranging from 35F to 95F and the cooling load is ~60 tons max @ 32,000 cfm.

    The air handler is designed to provide air flow that will maintain between 1 and 2wg supply air duct static pressure

    and supply air temperature set point between 65 and 55F.

    Richard Fromberg 4 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    5/32

    General Commissioning Procedure for Economizers October 31, 2001

    Equipment Covered by this Protocol:Economizers of AHUs 1, 2, and 3 at the SSC and AHU-1 at the PEC.

    General Notes:

    1. This commissioning procedure addresses verification checks and functional testing of moderately sized packaged or

    built-up air handlers.

    2. In all test sections, circle or highlight any results that indicate deficiencies (i.e. responses that dont meet the criteria foracceptance). Acceptance requires correction and retest of all deficiencies, as defined in each test section under Criteria

    for Acceptance or Acceptance. Attach all retest data sheets.

    3. This Commissioning Procedure does not comprehensively address fire and life safety or basic equipment safety controls.

    4. To ensure that this Commissioning Procedure will not damage any equipment or affect any equipment warranties, havethe equipment manufacturers representative(s) review all test procedures prior to execution, and be present if possible.

    Richard Fromberg 5 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    6/32

    General Commissioning Procedure for Economizers October 31, 2001

    II. SEQUENCES OF OPERATION

    Case #1 - The economizer air dampers (outside, return and exhaust) shall be modulated by an analog output from the DDC system

    to maintain the desired cold deck temperature set point. A minimum of 45F mixed air temperature will be maintained at all times.

    Cooling supply air temperature shall be maintained by first modulating the outdoor air damper open via the economizer mode andthen secondly modulating the chilled water valve open. When the outdoor air temperature is within 2F (adjustable) below the

    warmest zone space temperature, the outside air damper shall go to the minimum position setting and the return damper shall

    open to maximum position. The heating supply air temperature shall be reset downwards to the return air temperature as required

    to maintain a zone temperature of 70F(adjustable) in the coldest room.

    A photoelectric duct smoke detector shall be installed in the supply duct and shall provide a digital input to the DDC system.

    When smoke is detected by the smoke detector, the air handler supply fan shall be de-energized via its variable frequency drive, the

    return fan shall be de-energized via its VFD, and the outside air damper shall be fully closed.

    All damper actuators shall be programmed to achieve full range adjustability (closed to 100% open) in 60 seconds (adjustable).

    Case #2 AHU-1 is programmed to operate (on/off) on a predetermined building occupancy schedule (adjustable).

    When the supply fan is de-energized, the outside damper shall close and the cooling coil chilled water control valve TCV-1 shall

    open to the full bypass position.

    The supply fan is energized one hour (adjustable) prior to scheduled occupancy to provide a warm-up cycle. The outside air

    damper shall remain closed and the cooling coil chilled water control valve shall remain open to the full bypass position during

    the warm-up. The warm-up cycle shall be terminated when return air temperature TS-4 reaches 70F.

    The supply air temperature TS-3 shall be controlled by modulating the economizer dampers and then the cooling coil chilled

    water control valve TCV-1 in sequence to maintain the supply air temperature at set point. Outside air via the economizer

    dampers shall be the primary source of cooling when outside air temperature TS-1 is below 72F and less than the return air

    temperatureTS-4, otherwise cooling shall be provided by chilled water via TCV-1. No chilled water shall be supplied to TCV-1when outside air temperature TS-1 is below 61F. Supply Air Temperature TS-3 setpoint shall be reset by greatest cooling

    demand from 55F to 65F. When outside air temperature TS-1 is greater than 72F or greater than the return air temperature

    TS-4 the economizer dampers shall be positioned to provide the minimum design outside air CFM.

    Building static pressure DPX-1 shall be maintain at 0.03wg for economizer operating mode only. No set point control is

    required for minimum outside air operating mode. Supply Air Duct Static Pressure DPX-2 setpoint shall be reset via AHU-1

    supply fan VFD by greatest cooling demand from 1.0 wg to 2.0 wg.

    ALARM SETPOINTS:Building Static Pressure DPX-1: 0.07 wg.

    Supply Air Duct Static Pressure, High: 2.4 wg, Low: 0.06 wg

    Supply Air Temperature TS-3, Low: 50F

    Return Air Temperature TS-4, High: 76F, Low: 60F

    Mixed Air Temperature TS-2, Low: 50F

    Filter (Dirty) Differential Pressure DPS-2: 1.0 wg.

    Richard Fromberg 6 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    7/32

    General Commissioning Procedure for Economizers October 31, 2001

    III. ACCEPTANCE AND RESPONSIBILITIES:

    We the undersigned participated in this commissioning effort, and acknowledge that the processes for which we were

    responsible have been checked and all required corrections have been made.

    1. Name: Joe Contractor

    Company name: Installation Contractor Associates

    Responsibilities:

    Verification Checks: Installation quality, dampers must match position commanded by DDC

    Functional Testing: Dampers must respond to DDC commands in time, reliably, and accurately.

    Signature:

    2. Name: John Programmer

    Company name: DDC Inc.

    Responsibilities:

    Verification Checks: DDC must be capable of commanding dampers to the required positions based on operating

    mode. Pre-operational forced response testing must be verified.

    Functional Testing: DDC must be capable of commanding dampers to the required positions based on operating

    mode, OAT conditions, and as specified in the sequence of operation

    Signature:

    3. Name: JR Doolittle

    Company name: Hotwire Commissioning Services

    Responsibilities:

    Verification Checks: Complete the commissioning plan, ensure that all corrections are made, retest if necessary,

    use best engineering judgement to achieve design intent.

    Functional Testing: Complete the commissioning plan, ensure that all corrections are made, retest if necessary,

    use best engineering judgement to achieve design intent.

    Signature:

    4. Name: Zachary Sac

    Company name: Sacs Service Center

    Responsibilities: The building owners representatives are to facilitate the commissioning process, to help ensure that

    corrections are made, and to work with all parties to achieve an optimum product.

    Verification Checks:

    Functional Testing:

    Signature:

    Richard Fromberg 7 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    8/32

    General Commissioning Procedure for Economizers October 31, 2001

    IV. VERIFICATION - CHECKS FOR REQUIRED DOCUMENTATION AND TRAINING:

    Requested documentation to be submitted. (This section to be completed by Commissioning Authority (CA).)

    Documentation Equipment Dampers Actuators Control

    Wiring

    Programming

    Equipment manufacturers submittals, shop drawings, as-builts

    Manufacturers performance sheets (i.e. flow coefficient versusdamper position)

    Installation manual

    Test and Balance report

    Sequences of Operation

    O&M manuals

    Warranties

    Documentation complete as per contract documents ___ YES ___ NO

    Required training. (This section to be completed by CA.)

    Documentation Equipment Dampers Actuators Control

    Wiring

    Programming

    Controls and equipment training

    EMS training

    Documentation complete as per contract documents ___ YES ___ NO

    Richard Fromberg 8 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    9/32

    General Commissioning Procedure for Economizers October 31, 2001

    V. VERIFICATION - NAMEPLATE DATA CHECKS:

    Instructions:Enter information available from design specifications, submittals and installed equipment nameplates.

    Criteria for Acceptance:Nameplate data must be in accordance with submittals as approved by Designer.

    DESCRIPTION Outside Air Damper

    As specified As submittedAs installed

    Manufacturer

    Model #

    Serial #

    Type

    Maximum CFM

    Minimum CFM

    Damper Size (_____ x _____)

    Maximum Velocity (fpm)

    Maximum Pressure Differential (in. Wg.)

    Comments on Nameplate Data Checks (add more sheets if needed):

    # COMMENT

    DESCRIPTION Exhaust Air Damper

    As specified As submittedAs installed

    Manufacturer

    Model #

    Serial #

    Type

    Maximum CFM

    Minimum CFM

    Damper Size (_____ x _____)

    Maximum Velocity (fpm)

    Maximum Pressure Differential (in. Wg.)

    Richard Fromberg 9 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    10/32

    General Commissioning Procedure for Economizers October 31, 2001

    Comments on Nameplate Data Checks (add more sheets if needed):

    # COMMENT

    DESCRIPTION Return Air Damper

    As specified As submittedAs installed

    Manufacturer

    Model #

    Serial #

    Type

    Maximum CFM

    Minimum CFM

    Damper Size (_____ x _____)

    Maximum Velocity (fpm)

    Maximum Pressure Differential (in. Wg.)

    Comments on Nameplate Data Checks (add more sheets if needed):

    # COMMENT

    DESCRIPTION Outside Air Damper Actuator

    As specified As submittedAs installed

    Manufacturer

    Model #

    Serial #

    Type

    Electrical Data (i.e. signal range)

    Maximum Position

    Minimum Position

    Comments on Nameplate Data Checks (add more sheets if needed):

    # COMMENT

    Richard Fromberg 10 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    11/32

    General Commissioning Procedure for Economizers October 31, 2001

    DESCRIPTION Exhaust Air Damper Actuator

    As specified As submittedAs installed

    Manufacturer

    Model #

    Serial #

    Type

    Electrical Data (i.e. signal range)

    Maximum Position

    Minimum Position

    Comments on Nameplate Data Checks (add more sheets if needed):

    # COMMENT

    DESCRIPTION Return Air Damper Actuator

    As specified As submittedAs installed

    Manufacturer

    Model #

    Serial #

    Type

    Electrical Data (i.e. signal range)

    Maximum Position

    Minimum Position

    Comments on Nameplate Data Checks (add more sheets if needed):

    # COMMENT

    Richard Fromberg 11 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    12/32

    General Commissioning Procedure for Economizers October 31, 2001

    VI. VERIFICATION - INSTALLATION CHECKLIST:

    Instructions:Under each unit write "Y" for yes, "N" for no, "NA" for not applicable, and a number to refer to any needed

    comments. Identify responsible contractor. If issues or concerns arise, number and note in comment section below.

    Criteria for Acceptance:Answers of Y (or NA, where not relevant) except where other criteria are noted.

    Caution:Only qualified personnel familiar with the operation of the installed economizers, and the hazards involved, should

    adjust, operate, test, and/or service the equipment. The commissioning agent should become familiar with the installation,

    operation, and maintenance manuals prior to starting commissioning work. Failure to observe proper safety precautions could

    result in damage to equipment, severe bodily injury, and/or loss of life.

    Check SSC

    AHU1

    SSC

    AHU2

    SSC

    AHU3

    PEC

    AHU1

    Comments

    General Installation

    General appearance good, no apparent damage

    Environment clean

    Good access for maintenance

    Access doors close tightly no leaksEquipment labels affixed properly

    Economizer installed in accordance with manufacturers specs anddrawings

    The installation and location of the economizer are in a neutral

    zone of the building (i.e. there are no undo pressure restrictions

    or drops that hinder air movement)

    Outside air intake is located away from pollutant sources and

    exhaust outlets

    Damper Installation

    Dampers and linkages installed in accordance with drawings

    Dampers are properly linked, and move in the right directions

    Linkages have minimum play

    Installed dampers match specifications

    Dampers move freely without binding and are fully operational.There are no unusual noises when operating.

    Actuators are mounted to maximize torque available to the damper

    and to maximize linearity between the blade position and theactuator stroke.

    Multiple section dampers with multiple actuators need to have

    identical actuators and linkages to make each sectionscharacteristics consistent.

    Blade lengths of 48 inches or less are desirable, to reduce flutterand improve sealing.

    Dampers close tightly

    Dampers are lubricated. Vertical blades have thrust bearings.Outside air and return air dampers mounted to promote thoroughmixing of the two airstreams prior to entering coils

    Dampers are pointing in the direction that facilitates efficient air

    movement

    Verify that damper actuators are marked as follows: 0% position

    where the damper is closed, XX% position for the damper

    minimum air flow position, and 100% position where the damper

    is fully open.

    Richard Fromberg 12 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    13/32

    General Commissioning Procedure for Economizers October 31, 2001

    Check SSCAHU1

    SSCAHU2

    SSCAHU3

    PECAHU1

    Comments

    Ductwork

    Ductwork installed in accordance with design drawings

    All duct and boot connections to economizer are complete and in

    good condition

    Fittings in ductwork properly specified and appropriate for theapplication

    Ductwork complete and leak tested

    Mixing

    Is there enough space between the mixing section and the coils foradequate mixing?

    Are baffles installed and are damper blades rotating in thedirections that facilitate mixing?

    Sensors

    Outside air temperature sensor installed in correct location, out of

    direct sunlight and away from economizer inlet or outlet.

    Outside air sensor matches specification

    Return air sensor installed in correct locationReturn air sensor matches specification

    Mixed air sensor installed in correct location, to ensure propermixing of airstream ahead of sensor, and/or enough sampling

    points.

    Mixed air sensor matches specification

    Calibrations are covered in the next section

    Low limit freeze stat installed in correct location, not affected by

    stratification and bypass

    Low limit freeze stat matches specification

    Smoke detectors installed in correct location(s)

    Smoke detectors match specifications

    Filter differential pressure device installed in correct location,

    functional

    Filter diff pressure sensor matches specification

    Air Filters

    Construction filters removed

    Air filters are installed and clean and new

    Air filters match specifications

    Air filters are tight fitting

    Replacement filter type and efficiency permanently affixed to AHUhousing

    Electrical

    Electrical connections are tight

    Duct penetrations are waterproofPower disconnects, connection boxes and conduit are watertight

    Panels and boxes are properly labeled

    Fuse rating is correct for electrical equipment

    Power is available to panels

    Shielded wiring used on electronic controls

    Ductwork and penetrations

    Verify that wall and floor penetrations are properly sealed

    Richard Fromberg 13 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    14/32

    General Commissioning Procedure for Economizers October 31, 2001

    Check SSCAHU1

    SSCAHU2

    SSCAHU3

    PECAHU1

    Comments

    Verify that pressure relief doors are installed

    Verify that duct insulation is installed

    Verify that sound attenuation sections are installed

    The checklist items are all successfully completed for given trade.___ YES ___ NO

    Comments on Installed Characteristics Checks (add more sheets if needed):

    # COMMENT

    Richard Fromberg 14 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    15/32

    General Commissioning Procedure for Economizers October 31, 2001

    VII. VERIFICATION - CONTROLS SENSOR CALIBRATION CHECKS:

    Instructions: For each sensor listed below, collect the following information:

    1. Instrument description/identification

    2. Manufacturers calibration requirements

    3. Copy of the most recent calibration certificates

    4. Date of most recent calibration and the calibration data

    5. Description of the calibration procedure

    Installation: Check that all sensor installations and locations are correct, in order to attain an accurate measurement of the

    process. Make sure that they are installed out of direct sunlight, and in the ductwork where the process is mixed and uniform.

    Sensor elements should not touch any surfaces. The outdoor air sensor should be located away from the economizer inlet or

    exhaust, so that it is not affected by natural drafts when the AHU is off. If sensor location is improper, explain in comments, and

    have it relocated. Verify that sensors with shielded cable, are grounded only at one end. It is not necessary to repeat any full

    calibration procedure, but we recommend that through-system calibration checks be made, as follows:

    Differential paired sensors. For sensor pairs that are used to determine a temperature or pressure difference, place both sensors

    into a uniform temperature bath or expose them to the same pressure. Make sure that they are reading within 0.2F of each otherfor temperature and within a tolerance equal to 2% (of the reading) of each other for pressure. Tolerances for critical

    applications may be tighter.

    Sensors. Take a reading of the process with a calibrated test instrument close to the site sensor. Verify that the readings are

    within the tolerances in the table below. If not, install an offset in the BAS, recalibrate, or replace the sensor. If a second

    instrument cannot be installed to take a second reading, remove the sensor and subject it to a temperature bath or pressure source

    along with a calibrated sensor, and compare the readings. Record the readings in the table below.Criteria for Acceptance: Temperature and pressure sensors should agree with the calibrated instrument within the tolerances

    listed below.

    CONTROL

    TYPE

    CAL

    SENSORLOCATION

    EMS

    SENSORLOCATION.

    IS IT

    OKAY?

    EMS

    MEASUREDVALUE

    CALIBRATION

    SENSORVALUE

    DIFFERENCE ACCEPTABLE

    DIFFERENCE

    ACCEPTABLE? /

    COMMENTS

    Outdoor air temp SF(.5F),Sac(1F)

    Mixed air temp 1F

    Return air temp SF(.5F),Sac(2F)

    Filter Differential

    Pressure

    0.2 inH2O

    Comments on Calibration Items (add more sheets if needed):

    # COMMENT

    Richard Fromberg 15 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    16/32

    General Commissioning Procedure for Economizers October 31, 2001

    VIII. VERIFICATION - BALANCE REPORT CHECKS:

    Instructions: Compare the maximum supply air flow (outside air damper open) documented in the TAB report with the design

    flow specifications for the economizer dampers. From the TAB report, record the minimum outside air flow when the outside air

    damper is at its minimum position with both the supply fan operating at full and at minimum. Compare TAB report flows with

    economizer specifications and with the HVAC system design specifications.Criteria for Acceptance: Test and balance report outside air flows must meet the following criteria: the measured flow must be

    greater than the specified flow, and less than 110% of the specified flow. Also, the measured flows must be less than the damper

    design maximum flows.

    Check MeasuredFlow (from

    TAB)

    Specificationand Damper

    Design Flows

    % Diff Acceptable?

    Maximum outside air flow with outside air damper full open,100% supply air flow

    Minimum outside air flow with outside air damper at minimumand supply fan at 100%

    Minimum outside air flow with outside air damper at minimum

    and supply fan at minimum RPM

    Test and balance report is verified to be in agreement with economizer design specifications? ___ YES ___ NO

    Test and balance report is verified to be in agreement with system minimum outside air design specifications?

    ___ YES ___ NO

    Richard Fromberg 16 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    17/32

    General Commissioning Procedure for Economizers October 31, 2001

    IX. VERIFICATION - OPERATIONAL CHECKS 1) EXERCISE DAMPERS:

    Instructions:These verification checks augment the manufacturers instructions. These checks are done prior to functional

    testing, which are performed while the system is operating normally. Fill in the appropriate values if other information is

    requested, such as damper position (%) or temperature. Identify responsible contractor.

    Damper Stroke Check

    This test is to verify that the dampers can operate throughout their full expected range, and that the damper position matches the

    position called for in the BAS. Follow the steps in the table below for each damper and economizer.

    Criteria for Acceptance:Answers of Y (or NA, where not relevant) except where other criteria are noted.

    Caution: Only qualified personnel familiar with the operation of the installed air handler, and the hazards involved, should

    adjust, operate, test, and/or service the equipment. The commissioning agent should become familiar with the installation,

    operation, and maintenance manuals prior to starting commissioning work. Failure to observe proper safety precautions could

    result in damage to equipment, severe bodily injury, and/or loss of life.

    Enter Y, N, NA, or data as requested. Enter comment or note number if deficient.

    Check Equipment-> SSCAHU1

    SSCAHU2

    SSCAHU3

    PECAHU1

    Contractor

    Value/

    Comments

    Air handler fans are off.

    Command outside air damper to 100% open.

    Is outside air damper fully open?

    Is outside air damper position indicator pointing to 100%.

    Make sure that the scale is labeled to indicate the 100% position.

    Is exhaust air damper fully open?

    Is exhaust air damper position indicator pointing to 100%.

    Make sure that the scale is labeled to indicate the 100% position.

    Is return air damper fully closed?

    Is return air damper position indicator pointing to 0%.Make sure that the scale is labeled to indicate the 0% position.

    Command outside air damper to 0% open.

    Is outside air damper fully closed?

    Is outside air damper position indicator pointing to 0%.

    Make sure that the scale is labeled to indicate the 0% position.

    Is exhaust air damper fully closed?

    Is exhaust air damper position indicator pointing to 0%.

    Make sure that the scale is labeled to indicate the 0% position.

    Is return air damper fully open?

    Is return air damper position indicator pointing to 100%.

    Make sure that the scale is labeled to indicate the 100% position.

    Command outside air damper to its minimum operating position.

    Is outside air damper at 20% (as specified)?

    Is outside air damper position indicator pointing to 20%.

    Make sure that the scale is labeled to indicate the 20% position.

    Is exhaust air damper at 20% open?

    Is exhaust air damper position indicator pointing to 20%.

    Make sure that the scale is labeled to indicate the 20% position.

    Is return air damper at 80%?

    Richard Fromberg 17 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    18/32

    General Commissioning Procedure for Economizers October 31, 2001

    Enter Y, N, NA, or data as requested. Enter comment or note number if deficient.

    Check Equipment-> SSC

    AHU1

    SSC

    AHU2

    SSC

    AHU3

    PEC

    AHU1

    Contract

    or

    Value/

    Comments

    Air handler fans are off.

    Is return air damper position indicator pointing to 80%.

    Make sure that the scale is labeled to indicate the 80% position.

    Determine damper opening speed.

    Command the outside air damper to 0%

    Command the outside air damper to 100% open and record the time it takesto fully open. Note any unusual noises or problems.

    Record the time it takes for the exhaust damper to open and note any unusualnoises or problems.

    Record the time it takes for the return damper to close and note any unusualnoises or problems.

    Determine damper closing speed.

    Command the outside air damper to 0% open and record the time it takes tofully close. Note any unusual noises or problems.

    Record the time it takes for the exhaust damper to close and note any unusual

    noises or problems.Record the time it takes for the return damper to open and note any unusualnoises or problems.

    Return outside air damper to its normal position.

    The checklist items are all successfully completed for given trade.___ YES ___ NO

    Comments on Operational Checks (add more sheets if needed):

    # COMMENT

    Richard Fromberg 18 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    19/32

    General Commissioning Procedure for Economizers October 31, 2001

    IX. VERIFICATION - OPERATIONAL CHECKS 2) FIRE ALARM ECONOMIZER DAMPER

    POSITIONS:

    Instructions:These verification checks augment the manufacturers instructions. These checks are done prior to functional

    testing, which are performed while the system is operating normally. Fill in the appropriate values if other information is

    requested, such as damper position (%) or temperature. Identify responsible contractor.

    Check Damper Response to a Fire/Smoke Alarm

    This test is to verify that the dampers respond properly to a fire or smoke alarm. Follow the steps in the table below for each

    economizer.

    Criteria for Acceptance:Answers of Y (or NA, where not relevant) except where other criteria are noted.

    Caution: Only qualified personnel familiar with the operation of the installed air handler, and the hazards involved, should

    adjust, operate, test, and/or service the equipment. The commissioning agent should become familiar with the installation,operation, and maintenance manuals prior to starting commissioning work. Failure to observe proper safety precautions could

    result in damage to equipment, severe bodily injury, and/or loss of life.

    Enter Y, N, NA, or data as requested. Enter comment or note number if deficient.

    Check Equipment-> SSCAHU1

    SSCAHU2

    SSCAHU3

    PECAHU1

    Contractor

    Value/

    Comments

    Verify that the air handler fans are off.

    Command the outside air damper to 100% open. The exhaust damper shouldbe full open and the return damper should be closed.

    Set the fire/smoke detection system input signal to ON.

    Does the outside air damper close completely?

    Does the return air damper close completely?

    Does the exhaust air damper close completely?

    Reset the fire/smoke detector input signal to OFF.

    Do all dampers return to their normal position?

    The checklist items are all successfully completed for given trade.___ YES ___ NO

    Comments on Operational Checks (add more sheets if needed):

    # COMMENT

    Richard Fromberg 19 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    20/32

    General Commissioning Procedure for Economizers October 31, 2001

    IX. VERIFICATION - OPERATIONAL CHECKS 3) ECONOMIZER MODE CHECKS

    Instructions:These verification checks augment the manufacturers instructions. These checks are done prior to functional

    testing, which are performed while the system is operating normally. Fill in the appropriate values if other information is

    requested, such as damper position (%) or temperature. Identify responsible contractor.

    Check Economizer Damper Responses in Different Operating Modes

    This test is to verify that the dampers respond properly to various input conditions in different operating modes. Follow the steps

    in the table below for each economizer.

    Criteria for Acceptance:Answers of Y (or NA, where not relevant) except where other criteria are noted.

    Caution: Only qualified personnel familiar with the operation of the installed air handler, and the hazards involved, should

    adjust, operate, test, and/or service the equipment. The commissioning agent should become familiar with the installation,

    operation, and maintenance manuals prior to starting commissioning work. Failure to observe proper safety precautions could

    result in damage to equipment, severe bodily injury, and/or loss of life.

    Enter Y, N, NA, or data as requested. Enter comment or note number if deficient.

    Check Equipment-> SSCAHU1

    SSCAHU2

    SSCAHU3

    PECAHU1

    Contractor

    Value/

    Comments

    Disconnect power to supply and exhaust fans to make sure that they do notturn on throughout the following tests.

    Set BAS to Unoccupied (Fan Off) Mode

    Verify that outside air damper is closed.

    Verify that return air damper is open.

    Verify that exhaust air damper is closed.

    Set BAS to warm-up mode.

    Outside and exhaust air dampers closed?

    Return air damper open?

    Set BAS to cool-down mode.

    Set outside air temp to 65F

    Outside and exhaust air dampers are full open?

    Return air damper is closed?

    Set outside air temp to 75F.

    Outside damper is at minimum and exhaust damper is closed?

    Return air damper is full open?

    Set BAS to Occupied Mode

    (For the SSC) Set outside air temp to 3F less than the warmest zone

    temperature.

    (For the PEC) Set the outside air temp to 71F or 1F less than the return airtemp, whichever is less.

    Verify that outside air damper is full open.

    Verify that return air damper is closed.

    Verify that exhaust air damper is full open.

    (For the SSC) Set outside air temp to 1.5F less than the warmest zone temp

    (For the PEC) Set the outside air temperature to 73F.

    Verify that outside air damper is at minimum.

    Verify that return air damper is full open.

    Verify that exhaust air damper is closed.

    Richard Fromberg 20 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    21/32

    General Commissioning Procedure for Economizers October 31, 2001

    Enter Y, N, NA, or data as requested. Enter comment or note number if deficient.

    Check Equipment-> SSC

    AHU1

    SSC

    AHU2

    SSC

    AHU3

    PEC

    AHU1

    Contract

    or

    Value/

    Comments

    Disconnect power to supply and exhaust fans to make sure that they do notturn on throughout the following tests.

    (For the SSC) Check that the minimum mixed air temperature is

    maintained. Set the mixed air temp to 2F less than the minimum set pointfor mixed air temp of 45F.

    (For the PEC) Check that the supply air temp set point can be controlled.

    Set the supply air temp to supply air temp set point minus 2F.

    Set the outside air temperature to 40F and the return air temperature to70F.

    Verify that outside air damper is closed.

    Verify that return air damper is open.

    Verify that exhaust air damper is closed.

    (For the SSC) Set the mixed air temp to 47F.

    (For the PEC) Set the supply air temp to supply air temp set point plus 2F.

    Verify that outside air damper is full open.

    Verify that return air damper is closed.Verify that exhaust air damper is full open.

    Release the mixed, supply, and outdoor air temperature overrides and the

    BAS to its normal state.

    The checklist items are all successfully completed for given trade.___ YES ___ NO

    Comments on Operational Checks (add more sheets if needed):

    # COMMENT

    Richard Fromberg 21 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    22/32

    General Commissioning Procedure for Economizers October 31, 2001

    IX. VERIFICATION - OPERATIONAL CHECKS 4) CONTROLS PROGRAM CHECKS

    Enter Y, N, NA, or data as requested. Enter comment or note number if deficient.

    Check Equipment-> SSCAHU1

    SSCAHU2

    SSCAHU3

    PECAHU1

    Contractor

    Value/

    Comments

    Have flow charts and/or other documentation of the software specific to theSSC and PEC been provided?

    Check the logic diagrams for the economizers. Do they accurately model

    the sequences of operation, as follows:

    Shut down?

    Warm-up?

    Cool-down?

    Occupied Mode?

    Economizer Mode (free cooling)? Is the logic set up to modulate theeconomizer to maintain supply air temp (PEC) or a minimum mixed airtemp (SSC)?

    Minimum Outside Air Mode?

    Fire/Smoke Alarm Mode?

    Freeze Protection?

    Check the building occupancy schedules. Is the PEC M to F 7:00A to 6:00P

    and is the SSC M to F 6:30A to 5:30P, with AHU#3 24-7?

    Is the warm-up or cool-down mode scheduled to begin 1 hour beforeoccupancy?

    Are there alarms set for economizer malfunctions?

    Have graphics screens of the economizer and associated temperatures and

    damper positions been set up?

    Are the graphics screens easy to access from other graphics screens?

    Are trends set up to store economizer data?

    Can 48 hours of data be retrieved and plotted conveniently from the BAS

    for each economizer?Is the % outside air to total air calculated?

    The checklist items are all successfully completed for given trade.___ YES ___ NO

    Comments on DDC Program Checks (add more sheets if needed):

    # COMMENT

    Richard Fromberg 22 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    23/32

    General Commissioning Procedure for Economizers October 31, 2001

    X. FUNCTIONAL CHECKS FORCED RESPONSE AND SEQUENCE OF OPERATION

    TESTING - FANS ON/OFF, MORNING COOL-DOWN OR WARM-UP, NORMAL OPERATING

    MODES, FIRE/SMOKE ALARM, FREEZE PROTECTION

    The functional tests that follow include forced response tests and sequence of operation tests. Protocols for operational

    trend tests follow.

    General Instructions: The following sections are a series of field tests that are intended to verify that the economizer, as

    installed, operates as it was intended to operate by the designer. In general, these tests are best done with the building unoccupied

    or lightly occupied. Environmental conditions will be affected. If that is not possible, the commissioning agent must devise tests

    that are not intrusive. Some tests may involve trending normal operation over a long enough period to observe the conditions and

    modes of operation desired.

    Attach to this form all relevant field data, monitored data, graphs, trend logs, and so forth. Annotate any data and graphs so that it

    is clear what the data are proving. EMS trend logs of EMS outputs, program print-outs, or schedule and setpoint print-outs are not

    acceptable as proof of operation, unless the information is first verified to be accurate and documentation is attached. Trend logs

    of sensor inputs to the EMS are acceptable. If you were not able to complete a test, explain in a comment.

    Instructions:These functional checks augment the manufacturers instructions, and are to be performed when the system is

    operational. Fill in the appropriate values if other information is requested, such as damper position (%) or temperature.Identify responsible contractor.

    Check Economizer Damper Responses when the Fans are Turned On and Off, then during Morning Cool-down and Warm-up,

    then during Normal Occupied Operating Modes

    These tests are to verify that the dampers respond properly to various input conditions in different operating modes. Follow the

    steps in the table below for each economizer.

    Criteria for Acceptance:Answers of Y (or NA, where not relevant) except where other criteria are noted.

    Caution: Only qualified personnel familiar with the operation of the installed air handler, and the hazards involved, should

    adjust, operate, test, and/or service the equipment. The commissioning agent should become familiar with the installation,

    operation, and maintenance manuals prior to starting commissioning work. Failure to observe proper safety precautions couldresult in damage to equipment, severe bodily injury, and/or loss of life.

    Enter Y, N, NA, or data as requested. Enter comment or note number if deficient.

    Check Equipment-> SSCAHU1

    SSCAHU2

    SSCAHU3

    PECAHU1

    Contractor

    Value/

    Comments

    Make sure that the AHU is ready for functional testing.

    Verify stable operation of the AHU and fans before commissioning.

    Set BAS to Unoccupied (Fan Off) Mode

    Are the supply and exhaust fans off?

    Verify that outside air damper is closed.

    Verify that return air damper is open.

    Verify that exhaust air damper is closed.

    Set BAS to Occupied mode to turn the fans back on.

    Verify that the outside and exhaust air dampers (or the return air dampers)

    are open before the fans start.

    Do the fans start after the dampers are open?

    Record fan speed.

    Set fan speed to 100%.

    Richard Fromberg 23 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    24/32

    General Commissioning Procedure for Economizers October 31, 2001

    Enter Y, N, NA, or data as requested. Enter comment or note number if deficient.

    Check Equipment-> SSC

    AHU1

    SSC

    AHU2

    SSC

    AHU3

    PEC

    AHU1

    Contract

    or

    Value/

    Comments

    Make sure that the AHU is ready for functional testing.

    Record the filter differential pressure at 100% supply air flow.

    Is the differential pressure close to what was specified in the AHU design.

    Set BAS to cool-down mode.

    Record the return air temperature.

    Set outside air temp to 2F below the RAT.

    Outside and exhaust air dampers are full open?

    Return air damper is closed?

    Record the return air temperature again.

    Set outside air temp to 2F above the RAT.

    Outside damper is at minimum and exhaust damper is closed?

    Return air damper is full open?

    Set BAS to warm-up mode.Record the return air temperature.

    Set outside air temp to 2F below the RAT.

    Outside damper is at minimum and exhaust damper is closed?

    Return air damper is open?

    Record the return air temperature again.

    Set outside air temp to 2F above the RAT.

    Outside damper and exhaust damper are open?

    Return air damper is full closed?

    Test the Economizers normal operating modes

    Set BAS to Occupied Mode

    Are the fans running?

    For the PEC:

    Set the supply air temperature set point to 55F.

    Set the return air temperature to 73F.

    Set the outside air temperature to 74F.

    Is the outside air damper at minimum, the return air damper full open,and the exhaust air damper closed?

    Set the outside air temperature to 72F.

    Is the outside air damper at minimum, the return air damper full open,

    and the exhaust air damper closed?

    Set the outside air temperature to 71F.

    Are the outside and exhaust air dampers full open and return air damperclosed?

    Set the supply air temperature reading to 50F (below the SA set point).

    Do the outside and exhaust air dampers modulate closed, and return airdamper modulate open to try to raise the supply air temperature up to55F?

    Set the mixed air temperature reading to 35F, to check for freezeprotection.

    Are the outside and exhaust air dampers fully closed, and return airdamper fully open, to protect the coil against freezing?

    Richard Fromberg 24 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    25/32

    General Commissioning Procedure for Economizers October 31, 2001

    Enter Y, N, NA, or data as requested. Enter comment or note number if deficient.

    Check Equipment-> SSC

    AHU1

    SSC

    AHU2

    SSC

    AHU3

    PEC

    AHU1

    Contract

    or

    Value/

    Comments

    Make sure that the AHU is ready for functional testing.

    Set the fire/smoke detection signal to ON.

    Do the fans turn off?

    Do the outside air and exhaust air dampers close?

    Return the BAS and AHU to their normal operating modes, and releasethe OAT, SAT, MAT, and set point overrides.

    Are the fans on?

    Are the dampers in their expected operating positions based on outsideair and return air temperatures? Record the OAT and RAT.

    For the SSC:

    Set the supply air temperature set point to 55F.

    Set the return air temperature to 72F.

    Set the outside air temperature to 74F.

    Is the outside air damper at minimum, the return air damper full open,

    and the exhaust air damper closed?

    Set the outside air temperature to 70F.

    Are the outside and exhaust air dampers full open and return air damper

    closed?

    Set the mixed air temperature reading to 43F (below the minimum mixedair temperature set point of 45F).

    Do the outside and exhaust air dampers modulate closed, and return air

    damper modulate open to try to raise the mixed air temperature up to45F?

    Set the mixed air temperature reading to 35F, to check for freezeprotection.

    Are the outside and exhaust air dampers fully closed, and return airdamper fully open, to protect the coil against freezing?

    Set the fire/smoke detection signal to ON.

    Do the fans turn off?

    Do the outside air and exhaust air dampers close?

    Return the BAS and AHU to their normal operating modes, and release

    the OAT, SAT, MAT, and set point overrides.

    Are the fans on?

    Are the dampers in their expected operating positions based on outsideair and return air temperatures? Record the OAT and RAT.

    Both Cases:

    Set the BAS to heating mode.

    Does the outside air damper go to its minimum position?

    Is the exhaust damper closed and the return damper full open?

    Return the BAS to its normal operating mode.

    The checklist items are all successfully completed. ___ YES ___ NO

    Richard Fromberg 25 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    26/32

    General Commissioning Procedure for Economizers October 31, 2001

    Comments on Operational Checks (add more sheets if needed):

    # COMMENT

    Richard Fromberg 26 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    27/32

    General Commissioning Procedure for Economizers October 31, 2001

    XI. FUNCTIONAL TESTS - ECONOMIZER PERFORMANCE TEST

    Instructions:This functional/performance test augments the manufacturers instructions, and is to be performed when the system

    is operational. Fill in the appropriate values if other information is requested, such as damper position (%) or temperature.

    Identify responsible contractor.

    Criteria for Acceptance:Answers of Y (or NA, where not relevant) except where other criteria are noted.

    Caution: Only qualified personnel familiar with the operation of the installed air handler, and the hazards involved, should adjust,operate, test, and/or service the equipment. The commissioning agent should become familiar with the installation, operation, and

    maintenance manuals prior to starting commissioning work. Failure to observe proper safety precautions could result in damage to

    equipment, severe bodily injury, and/or loss of life.

    Check Equipment-> SSC

    AHU1

    SSC

    AHU2

    SSC

    AHU3

    PEC

    AHU1

    Contract

    or

    Value/

    Comments

    Mixing Box Performance Test

    Perform the following stratification test in cold weather. The outside airtemperature should be below 40F and the outside air damper should be at

    its minimum opening. Repeat the measurements during minimum andmaximum supply air flow rate conditions.

    Measure the air temperature profile upstream of the filter. Take a

    temperature measurement at the center of each square yard of filter area.

    Record the mixed air temperature from the ECMS.

    Determine the difference between the minimum and maximum temperatures.

    Is the difference between the minimum and maximum temperatures less than5F?

    Average all of the temperatures for each profile.

    Is the difference between the ECMS mixed air temperature and the averageprofile temperature less than 3F?

    Notes to Economizer Performance Test:

    Comments, notes, deficiencies:

    Richard Fromberg 27 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    28/32

    General Commissioning Procedure for Economizers October 31, 2001

    XII. FUNCTIONAL TESTS - ECONOMIZER OPERATIONAL TREND TEST

    Test Procedure:Trends are useful for verifying that the economizer is operating properly when the commissioner cannot be present (such asevenings, weekends, or extended periods of time). Following is a test procedure that will help verify proper operation of the economizers undernormal system control. Trend graphs are produced which can be used to check that sequences of operation are followed. Economizer temperatures

    will be logged for about two weeks. Plots will indicate if the AHU is scheduled correctly and if the economizer dampers are functioning properly.

    Follow the steps below for each economizer.

    Criteria for Acceptance: Items #1 - 12 require answers of Y (or NA, where relevant) except where other criteria are noted.

    Check Equipment-> SSCAHU1

    SSCAHU2

    SSCAHU3

    PECAHU1

    Contractor

    Value/

    Comments

    Set up EMS trends or install temperature data logging equipment for the

    following measurements:

    Supply Air Temperature downstream of cooling coil, where air stream iswell mixed

    Mixed Air Temperature as far downstream from the mixing dampers as

    possible without being too close to the cooling coils. A multipoint probemay be useful for more accurate measurements.

    Return Air Temperature upstream of the return air dampers

    Outside Air Temperature place in a protected location near the outside

    air grill, away from direct sunlight. If it must be placed in direct sunlight,shield the sensor with aluminum foil, allowing air to flow around thesensor, without touching the sensor.

    Fasten the temperature sensors securely, and do not allow the sensors totouch any surfaces.

    Collect temperature data (and a timestamp) for a two-week period, while theHVAC system is in normal use. Try to capture a period of time with a wideswing in operating conditions, or outside air temperatures. Store

    instantaneous data at 5-minute intervals.

    Download all data into a spreadsheet, and line up all of the data with time.Use a program such as PG&Es Universal Translator (UT) if you need helplining up the data.

    Plot all four temperatures versus time. Does the plot demonstrate the

    following:Hours of operation are limited to occupied building hours plus an hour ortwo before building occupancy.

    With the AHU is running, does the mixed air temperature track the outsideair temperature when the outside air temperature is between the supply air

    temperature and the return air temperature?

    When the outside air temperature is above the return air temperature, doesthe mixed air temperature track the return air temperature plus a few

    degrees (due to minimum outside air flow entering the air handler)?

    When the outside air temperature is below the minimum supply airtemperature set point, does the mixed air temperature stay close to the

    minimum supply air temperature set point.

    Notes to Operational Trend Test:1 Attach the time plots to this test form to document your test results.

    Comments, notes, deficiencies:

    Richard Fromberg 28 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    29/32

    General Commissioning Procedure for Economizers October 31, 2001

    XIII. FUNCTIONAL TESTS - M&V SAVINGS CALCULATION USING PERFORMANCE

    TRENDING TESTS

    Introduction: The following procedure should be used to estimate the savings due to improvements in economizer performance.

    It follows ASHRAEs retrofit isolation approach for determining M&V savings. The assumption is that other commissioning

    efforts do not affect the economizers performance or our estimate of savings. The improvements could come from a

    commissioning effort on new or old equipment or from repair, replacement, or retrofit of existing equipment. Measurements of

    pre- and post-retrofit data will be needed, in order to characterize the economizers performance improvement as a function of

    outside air temperature. To determine the energy savings, a model of the fan supply air flow as a function of outside air

    temperature will also be needed. The following procedure does not yet comply with ASHRAE 14P, since an uncertaintyanalysis of the results has not been performed, and we do not know if the results fall within the criteria of the guidelines.

    ASHRAEs criteria for the application of the retrofit isolation approach involves the following steps:

    1. Select independent variables and develop model

    2. Select and document Baseline conditions

    3. Select duration and frequency of monitoring for Baseline and Post Retrofit periods

    4. Project Baseline usage to Post Retrofit conditions

    Determine savings by: Savings = Projected Baseline (usage, demand) - Post Retrofit (usage, demand)

    Test Procedure:

    1. Set up and collect pre-retrofit performance trend data using the Economizer Operational Trend Test protocol (above).

    Collect enough data to be able to model the economizer over as wide a range of ambient temperatures as possible.

    We suggest several weeks of data collected during a transitional season, such as spring or fall. Preferred baseline

    data would ideally cover a one-year period before the implementation of the ECM (energy conservation measure),even though this is rarely achieved.

    2. After the retrofit is completed, collect the same economizer data as well as supply fan RPM data. Data collected

    during a wide range of outside air temperature conditions is preferable. Collect data for at least one month, for use

    as an estimate of the savings. Collect data for one year for use in determining ESCO payments or utility rebates.

    3. Create a model of the mixed air temperature minus what the MAT should be versus outside air temperature, for

    both pre- and post-retrofit data.

    4. Using fan performance curves, estimate the fan flow (in lbs/hour) from the RPM data that was collected during the

    post-retrofit period.

    5. Create a model of the fan flow as a function of ambient temperature for the post-retrofit period, for when the building

    was occupied.

    6. If a full year of data is not available, estimate how much energy will be saved from short-term data in a normal year.Load TMY2 data for your site into a spreadsheet, and use the models to predict MAT deviations and supply airflows

    using expected ambient temperatures.

    7. Filter the ambient temperature data to include only data for when the building is occupied.

    8. For each hourly reading of ambient temperature, calculate the energy saved due to the economizer retrofit, using thefollowing formula:

    Energy saved(kWh) = [(MATdevpre

    MATdevpost

    ) * Supply Air Flow(lbm/hr) * 0.24 (Btu/lb

    m*F)] /

    [12,000 (Btu/hr/ton) * Nominal Chiller Efficiency (kW/ton)]

    Richard Fromberg 29 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    30/32

    General Commissioning Procedure for Economizers October 31, 2001

    For each economizer, follow this procedure for determining annual energy and dollar savings:

    Criteria for Acceptance: The calculated estimate of monthly savings meets the required minimum level and range of uncertainty.

    Check Equipment-

    >

    SSC

    AHU1

    SSC

    AHU2

    SSC

    AHU3

    PEC

    AHU1

    Contractor Value/

    Comments

    Sum up the hourly energy savings for the nominal weather year to

    calculate the expected annual energy savings (kWh/yr).

    If actual savings are to be determined for ESCO payments or utilityrebates, repeat the above calculation using actual monitored data (for

    one year of the post-retrofit period) and the model from the pre-retrofittest period applied to the post-retrofit data.

    To calculate the energy dollar savings, repeat the energy savingscalculation on an hourly basis, and apply actual electrical energy rates(either TOU or other applicable schedule). Sum up the dollar savings for

    the year for an annual amount.

    Calculate the uncertainty (and confidence interval) in the results usingmethods outlined in ASHRAE 14P.

    Comments, notes, deficiencies:

    Richard Fromberg 30 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    31/32

    General Commissioning Procedure for Economizers October 31, 2001

    XIV. COMMISSIONING REPORT OUTLINE:

    Report:The following outline should be used to prepare the commissioning report for these economizers.

    Executive Summary of Test Results

    Commissioning Plan Outline

    List Deficiencies Found

    List Corrective Actions Taken

    List Deficiencies that were not Corrected

    Conclusions How will remaining deficiencies be Corrected

    Appendix A Completed Test Protocols

    Appendix B Data Sheets

    Appendix C Performance Trend Plots

    Richard Fromberg 31 Economizer Procedure.docPacific Gas and [email protected]

  • 7/31/2019 Economizer Procedure

    32/32

    General Commissioning Procedure for Economizers October 31, 2001

    XV. REFERENCES USED TO DEVELOP THE ECONOMIZER PROTOCOL:

    ASHRAE Proposed Guideline 14P, Measurement of Energy and Demand Savings. Post 1stPublic Review. Atlanta, Georgia. January 17,

    2001.

    ASHRAE Guideline 1-1996, The HVAC Commissioning Process. Atlanta, Georgia. 1996.

    Ellis, Rebecca and McKew, Howard. Back to Basics Series V, Topic: Central Air with Return Air System. Originally printed in July,

    August, and September 1997 issues of Engineered Systems.

    Katipalumula, S.; Pratt, R.G.; et. al. Automated Fault Detection and Diagnostics for Outdoor-Air Ventilation Sysems and Economizers:

    Methodology and Results from Field Testing. ASHRAE Transactions 1999, V. 105, Pt. 1.

    Montgomery County, Maryland. Building Commissioning Program & Contractor Quality Control Guidelines & Specifications. Paul

    Tseng, Montgomery Engineering Institute, Division of Facilities and Services, Dept. of Public Works and Transportation. July 1998.

    University of Washington, Commissioning Specifications, Facilities Services, Facility Design Information. Volume 2, Appendix 17C, pages1 to 27, Check-off Sheets: Air Handling Systems. September 1995.

    Austin, S.B. HVAC System Trend Analysis. ASHRAE Journal page 44. February, 1997.

    National Environmental Balancing Bureau (NEBB). Procedural Standards for Building Systems Commissioning. Gaithersburg,

    Maryland. Section 6 and Appendix A pages 11.1.1 to 11.3.2. Rev 2.0, November 1999

    Pacific Energy Center (Pacific Gas and Electric), Tool Lending Library, Toolbox. Assessing Economizer Performance. Website:

    http://www.pge.com/003_save_energy/003c_edu_train/pec/toolbox/tll/app_notes/asses_econ.shtml. Ryan Stroupe (PEC).

    Sacramento Service Center, Building A, HVAC System Renovation, Sequences of Operation, Johnson Controls, Date 7/27/99.

    Pacific Energy Center, Draft Systems Manual, Sherrill Engineering (San Francisco, CA), Sections 1 and 3. April 2, 2001.

    http://www.pge.com/003_save_energy/003c_edu_train/pec/toolbox/tll/app_notes/asses_econ.shtmlhttp://www.pge.com/003_save_energy/003c_edu_train/pec/toolbox/tll/app_notes/asses_econ.shtmlhttp://www.pge.com/003_save_energy/003c_edu_train/pec/toolbox/tll/app_notes/asses_econ.shtml