Economic Production Quantity (EPQ).pptx

54
Economic Production Quantity (EPQ) Production done in batches or lots production capacity > usage or demand rate for a part for the part 1 Assumptions of EPQ similar to EOQ except orders are received incrementally during production

description

financeoperations management

Transcript of Economic Production Quantity (EPQ).pptx

Page 1: Economic Production Quantity (EPQ).pptx

Economic Production Quantity (EPQ)

• Production done in batches or lots

production capacity > usage or demand ratefor a part for the part

1

Assumptions of EPQsimilar to EOQexcept orders are received

incrementally during production

Page 2: Economic Production Quantity (EPQ).pptx

Economic Production Quantity (EPQ)

2

Page 3: Economic Production Quantity (EPQ).pptx

Economic Production Quantity (EPQ)

3

dpp

QI

p

Q

d

Q

SQ

DH

I

max

max

;lengthRun ;length Cycle

2Cost

Setup

Annual

Cost

Holding

Annual

TC

dp

p

H

DSQ

20TC = Total annual cost

Q = Order quantity (units)H = Annual holding cost

per unitD = Annual DemandS = Ordering (or setup) cost per order

Q0 = Optimal run or order quantityp = Production rated = Usage or demand rateImax = Maximum inventory level

Page 4: Economic Production Quantity (EPQ).pptx

EPQ ExampleHoldit Inc. produces reusable shopping bags. Demand is 20,000 bags per day, 5 days per week, 50 weeks per year. Production is 50,000 per day. The setup cost is $200 and the annual holding cost rate is $.55 per bag. Calculate the EPQ, the total cost, the cycle length and optimal production run length.

4

H = $0.55 per bag S = $200 D = 20,000 bags x 50 wks x 5 days

d = 20,000 bags per day p = 50,000 bags per day

dp

p

H

DSQ

20

850,772050

50

55.

)200)(000,000,5(20

GG

GQ

Page 5: Economic Production Quantity (EPQ).pptx

EPQ Example

5

H = $0.55 per bag d = 20,000 bags per day p = 50,000 bags per day

S = $200 D = 20,000 bags x 50 wks x 5 days

dpp

QIS

Q

DH

I

max

max 2

TC

bags 46,710 30000000,50

850,77max I

$25,690 002850,77

5)55(.

2

710,46TC

million

Holdit Inc. produces reusable shopping bags. Demand is 20,000 bags per day, 5 days per wk, 50 wks per yr. Production is 50,000 per day. Setup cost is $200 and annual holding cost rate is $.55 per bag. Calculate total cost.

Page 6: Economic Production Quantity (EPQ).pptx

EPQ ExampleHoldit Inc. produces reusable shopping bags. Demand is 20,000 bags per day, 5 days per week, 50 weeks per year. Production is 50,000 per day. The setup cost is $200 and the annual holding cost rate is $.55 per bag. Calculate cycle length and optimal production run length.

6

H = $0.55 per bag S = $200 D = 20,000 bags x 50 wks x 5 days

d = 20,000 bags per day p = 50,000 bags per day

p

Q

d

Q lengthRun ;length Cycle

days 3.89every 000,20

850,77length Cycle

orderper days 56.1000,50

850,77lengthRun

Page 7: Economic Production Quantity (EPQ).pptx

EOQ with Quantity Discounts• Price reductions are often offered as incentive to buy

larger quantities• Weigh benefits of reduced purchase price against

increased holding cost

R = per unit price of the itemD = annual demand

Annualholdingcost

PurchasingcostTC = +

Q2

H DQ

STC = +

+Annualorderingcost

RD +

Page 8: Economic Production Quantity (EPQ).pptx

Total Cost with Purchase Cost

8

Cost

EOQ

TC with PD

TC without PD

PD

0 Quantity

Adding Purchasing costdoesn’t change EOQ

Page 9: Economic Production Quantity (EPQ).pptx

Total Cost with Quantity Discounts

9

Page 10: Economic Production Quantity (EPQ).pptx

Best Purchase Quantity Procedure

begin with the lowest unit price

compute the EOQ for each price range

stop when find a feasible EOQ

Is EOQ for the lowest unit price

feasible?Yes:

it is the optimal order

quantity

No: compare total cost at

all break

quantities

larger than

feasible EOQ

10

The quantity that yields the lowest total cost is optimum

Page 11: Economic Production Quantity (EPQ).pptx

Carrying Cost are Constant

• There will be a single minimum point.• All curves will have their minimum point

at the same quantity.

Page 12: Economic Production Quantity (EPQ).pptx
Page 13: Economic Production Quantity (EPQ).pptx

1. Compute the minimum point.

2. Only one of the unit prices will have the minimum point in its feasible range since ranges do not overlap. Identify the range.

a) If the feasible minimum point is on the lowest price range, that is the optimal order quantity

b) If on any other range, compute the total cost for the minimum point and for the price breaks of all lower unit costs.

Page 14: Economic Production Quantity (EPQ).pptx

Example: Fixed Carrying CostThe maintenance department of a large hospital uses

about 816 cases of liquid cleanser annually. Ordering costs are $12, carrying costs are $4 per case a year, and the new price schedule indicates that orders of less than 50 cases will cost $20 per case, 50 to 79 case will cost $18 per case, 80 to 99 cases will cost $17 per case, and larger orders will cost $16 per case. Determine the optimal order quantity and the total cost.

Page 15: Economic Production Quantity (EPQ).pptx

Order Quantity(units) Price/unit($)

0 to 2,499 $1.20

2,500 to 3,999 1.00

4,000 or more .98

D = 816 S = $12 H = $4 case per year

1. Compute the common minimum

cases 7069.97 = 4

2(816)(12) =

H

2DS = QO

Page 16: Economic Production Quantity (EPQ).pptx

2.

TC (70) = (70/2)4 + (816/70)12 + 18(816) = $14 968 Since there are lower cost ranges, each must be checked against the minimum cost generated by 70 cases at $18.

TC (80) = (80/2)4 + (816/80)12 + 17(816) = $14 154

TC (100) = (100/2)4 + (816/100)2 + 16(816) = $13 354

Page 17: Economic Production Quantity (EPQ).pptx

Example: Quantity DiscountsBelow is a quantity discount schedule for an item with

an annual demand of 10,000 units that a company orders regularly at an ordering cost of $4. The annual holding cost is 2% of the purchase price per year. Determine the optimal order quantity.

17

Order Quantity(units) Price/unit($)0 to 2,499 $1.202,500 to 3,999 1.004,000 or more .98

Page 18: Economic Production Quantity (EPQ).pptx

D = 10,000 units S = $4

units 2,000 = 0.02(1.00)

4)2(10,000)( =

H

2DS = QO

units 2,020 = 0.02(0.98)

4)2(10,000)( =

H

2DS = QO

H = .02R R = $1.20, 1.00, 0.98

Interval from 0 to 2499, the Qo value is feasible

Interval from 2500-3999, Qo value is NOT feasible

Interval from 4000 & up, Qo value is NOT feasible

Example: Quantity Discounts

18

Order Quantity Price/unit($)0 to 2,499 $1.202,500 to 3,999 1.004,000 or more .98

units 1,826 = 0.02(1.20)

4)2(10,000)( =

H

2DS = QO

Page 19: Economic Production Quantity (EPQ).pptx

Quantity Discount Models

19

2500 4000

An

nu

al cost

0 Quantity

EOQs (not feasible)

1st break quantity

2nd break quantity

1st range total cost

curve

2nd range total cost curve

3rd range total cost curve

EOQ

Page 20: Economic Production Quantity (EPQ).pptx

TC(0-2499) = (1826/2)(0.02*1.20) + (10000/1826)*4+(10000*1.20) = $12,043.82

TC(2500-3999)= $10,041

TC(4000&more)= $9,949.20

Therefore the optimal order quantity is 4000 units

Example: Quantity Discounts

20

Q2H D

QSTC = + RD +

Page 21: Economic Production Quantity (EPQ).pptx

Concept CheckWhich of the following is FALSE about EOQ?

A. It determines how many to order.B. The EOQ always results in the lowest total

cost.C. The model minimizes total cost by

balancing carrying and order costs.D. The model is robust and works even if all

assumptions are not exact.

21

Page 22: Economic Production Quantity (EPQ).pptx

Concept CheckWhich is NOT a difference between EOQ and

EPQ?

A. A different formula is used.B. EPQ is used mainly for producing batches,

and EOQ is for receiving orders.C. Quantity is received gradually in EPQ.D. Demand can be variable for EPQ but not for

EOQ.

22

Page 23: Economic Production Quantity (EPQ).pptx

Concept CheckWhich is NOT an assumption of both EOQ and EPQ?

A. Demand is known with certainty and is constant over time

B. No shortages are allowedC. Order quantity is received all at onceD. Lead time for the receipt of orders is constant

23

Page 24: Economic Production Quantity (EPQ).pptx

What’s next?• EOQ models give HOW MANY to order• Now look at WHEN to order

– Reorder Point (ROP)

24

d = Demand rate (units per day or week)LT = Lead time (in days or weeks)Note: Demand and lead time must have the same time units.

ROP = d LT

Page 25: Economic Production Quantity (EPQ).pptx

Example: ROPAnnual Demand = 1,000 units

Days per year = 365

Lead time = 7 days

25

units/day 2.74 = days/year 365

units/year 1,000 = d

units 20or 19.18=(7days)units/day 2.74=L =ROP d

When inventory level reaches 20 units, place the next order.

Page 26: Economic Production Quantity (EPQ).pptx

Fixed Order Quantity/Reorder Point Model

Safety Stock1. Variability of

demand and lead time 2. Service Level2a. Lead time service level

2b. Annual service level

26

Reorder Point = Expected demand + Safety Stock (ROP) during lead time

Page 27: Economic Production Quantity (EPQ).pptx

When to Reorder with EOQ Ordering

• Reorder Point – When inventory level drops to this amount, the item is reordered.

• Safety Stock - Stock that is held in excess of expected demand due to variability of demand and/or lead time.

• Service Level – Probability demand will not exceed supply.– Lead time service level: probability that demand will not exceed

supply during lead time. – Annual service level: percentage of annual demand filled.

27

Page 28: Economic Production Quantity (EPQ).pptx

Determinants of the Reorder PointRate of

demandLead time

Demand and/or lead

time variability

Stockout risk (safety stock)

28

ROP Expected demandSafety stockduring lead time

Page 29: Economic Production Quantity (EPQ).pptx

Safety Stock

29

LT Time

Expected demandduring lead time

Maximum probable demandduring lead time

ROP

Qu

an

tity

Safety stock

Safety stock reduces risk ofstockout during lead time

Page 30: Economic Production Quantity (EPQ).pptx

Reorder Point

30

z = Safety factor; number of standard deviations above expected demanddLT = The standard deviation of demand during lead time

Safety Stock = z.dLT

The ROP based on a normalDistribution of lead time demand

Page 31: Economic Production Quantity (EPQ).pptx

Demand During Lead Time

31

Page 32: Economic Production Quantity (EPQ).pptx

ROP with Lead Time Service Level• variable demand during a lead time

32

ROP = expected demand during lead time + safety stock

z = Safety factor; number of standard deviations above expected demanddLT = The standard deviation of demand during lead time

ROP = + z.dLT

Page 33: Economic Production Quantity (EPQ).pptx

ROP with Lead Time Service Level• variable demand and constant lead time

33

ROP = (average demand x lead time) + z x st. dev. of demand

during lead time(demand and lead time measures in same time units)

sd = standard deviation of demand per day

sdLT = sd LT

Page 34: Economic Production Quantity (EPQ).pptx

ROP with Lead Time Service Level• both demand and lead time are variable

34

ROP = (avg. demand x avg. lead time) + z x st. dev. of demand

in lead time(demand and lead time measures in same time units)

sd= standard deviation of demand per day

sLT= standard deviation of lead time

sdLT = (average lead time x sd2)

+ (average daily demand) 2sLT2

Page 35: Economic Production Quantity (EPQ).pptx

Example 1: ROP with Lead Time Service Level

Calculate the ROP required to achieve a 95% service level for a product with average demand of 350 units per week and a standard deviation of demand during lead time of 10. Lead time averages one week.

35

From Table 12-3 (p434), z for 95% = 1.65

ROP = 350 + ZsdLT

= 350 + 1.65 (10)

= 350 + 16.5 = 366.5 ≈ 367

A new order should be placed when inventory level reaches 367 units.

Page 36: Economic Production Quantity (EPQ).pptx

Example 2: ROP with Lead Time Service Level

Calculate the ROP and amount of safety stock required to achieve a 90% service level for a product with variable demand that averages 15 units per day with a standard deviation of 5. Lead time is consistently 2 days.

36

From Table 12-3 (p434), z for 90% = 1.28

ROP = (15 units x 2 days) + ZsdLT

= 30 + 1.28 ( 2) (5)

= 30 + 8.96 = 38.96 ≈ 39

Safety stock is about 9 units and a new order should be placed when inventory level reaches 39 units.

Page 37: Economic Production Quantity (EPQ).pptx

Example 3: ROP with Lead Time Service Level

Calculate the ROP for a product that has an average demand of 150 units per day and a standard deviation of 16. Lead time averages 5 days, with a standard deviation of 2. The company wants no more than 5% stockouts.

37

service level = 1 – 5% = 95%From Table 12-3 (p434), z for 95% = 1.65

Place a new order when inventory level reaches 1004 units

ROP = (150 units x 5 days) + 1.65sdlt

= (150 x 5) + 1.65 (5 days x 162) + (1502 x 12)

= 750 + 1.65 (154) = 1,004 units

Page 38: Economic Production Quantity (EPQ).pptx

ROP Using Annual Service Level1. Calculate

2. Use a table to find the z value associated with E(z)

3. Use the z value in the appropriate ROP formula,

38

dLT

annualSLQzE

)1(

)(

dLTzROP timeleadduringdemandexpected

SLannual = annual service level E(z) = standardized expected number of units short during an order cycle.

Page 39: Economic Production Quantity (EPQ).pptx

Min/Max model• similar to fixed order-quantity/reorder point

(ROP) model• difference:

– if at order time, Q on hand < min (ROP), then order quantity = max – Q on hand(max EOQ + ROP)

39

Page 40: Economic Production Quantity (EPQ).pptx

Inventory Models• EOQ/ROP model

– Order size constant, time between orders changes

• Fixed Order Interval/Order up to Level Model– orders placed at fixed time intervals– determine how much to order to bring inventory level up

to a predetermined point (order up to level)– used widely for retail– consider expected demand during lead time, safety

stock, and amount on hand– demand or lead time can be variable

40

Page 41: Economic Production Quantity (EPQ).pptx

Comparing Inventory Models

41

EOQ/ROP

Fixed Interval/

Order up to

Page 42: Economic Production Quantity (EPQ).pptx

Disadvantagesrequires a larger safety stockincreases carrying costcosts of periodic reviews

Fixed Order Interval: Benefits and Disadvantages

• Benefits– grouping items from same supplier

can reduce ordering/shipping costs– practical when inventories

cannot be closely monitored

42

Page 43: Economic Production Quantity (EPQ).pptx

Fixed Order Interval/Order up to Level Model

Determining the order interval

43

OI = order interval (in fraction of a year)S = fixed ordering cost per purchase orders = variable ordering cost per SKU included in the order (line item)

(assume s is the same for every SKU)

n = n number of SKUs purchased from the supplierRj = unit cost of SKUj , j = 1, …, ni = annual holding cost rateDj = annual demand of SKUj , j = 1, …., n

Total Annual Inventory Cost:

TC =

Optimal Order Interval:

OInsSiR

OIDj

j 1)(.

2

.

jj RDi

nsSOI

)(2*

Page 44: Economic Production Quantity (EPQ).pptx

Fixed Order Interval/Order up to Level Model

Determining the Order up to Level

44

LTOIzLTOId d

Stock

Safety

interval

protection during

demand Expected

I

handon Amount IQ

max

max

= Average daily or weekly or monthly demand OI = Order interval (length of time between ordersLT = Lead time in days or weeks or monthsz = Safety factor; # of standard deviations above expected demandd = Standard deviation of daily or weekly or monthly demand

Page 45: Economic Production Quantity (EPQ).pptx

= 20 (30 + 10) + (2.32) (4) 30 + 10 = 800 + 2.32 (25.298) = 858.7 or 859 units stock up to level

Example: Fixed Order Interval ModelAverage daily demand for a product is 20 units, with a standard deviation of 4 units. The order interval is 30 days, and lead time is 10 days. Desired service level is 99%. If there are currently 200 units on hand, how many should be ordered?

45

LTOIzLTOId d maxI

maxI

Amount to order = 859 – 200 = 659 units

Page 46: Economic Production Quantity (EPQ).pptx

Coordinated Periodic Review Model

• determines an order interval (OI) and order up to level for reviewing every stock keeping unit (SKU)– calculate a multiple (mi ) of OI for each SKUi

– use this to determine the optimal OI for each SKUi

46

To use:Compare on hand inventory of each SKU to its ROP

(forecast demand for next OI + lead time + safety stock)if on hand is less: order a quantity that brings the on

hand level to SKU’s order up-to levelthe order up-to level is enough for the next OI + LT.

Page 47: Economic Production Quantity (EPQ).pptx

Single Period Model• Single period model

– model for ordering of perishables and other items with limited useful lives

• Shortage cost Cs

– generally the unrealized profits per unit– Revenue per unit – Cost per unit

• Excess cost Ce

– cost per unit - salvage per unit for items left over at the end of a period

47

GOAL = find order quantity (stock level) that minimizes total excess and shortage costs.

Page 48: Economic Production Quantity (EPQ).pptx

Single Period Model• Continuous stocking levels

– Identifies optimal stocking levels– Optimal stocking level balances unit

shortage and excess cost

• Discrete stocking levels– Desired service level is equaled or

exceeded• Compare service level to cumulative probability of

demand48

Page 49: Economic Production Quantity (EPQ).pptx

Optimal Stocking Level

49

Service Level

So

Quantity

Ce

Cs

Balance point

Service level (SL) =Cs

Cs + CeCs = Shortage cost per unitCe = Excess cost per unit

So = Optimum stocking level (i.e., order quantity

Page 50: Economic Production Quantity (EPQ).pptx

Example 1: Single Period Model

• Ce = $0.20 per unit• Cs = $0.60 per unit• Service level = Cs/(Cs+Ce) = .6/(.6+.2)• Service level = .75

50

Service Level = 75%

Quantity

Ce

Cs

Stockout risk = 1.00 – 0.75 = 0.25

Page 51: Economic Production Quantity (EPQ).pptx

Example 2: Single Period Model

The Poisson table (App. B, Table C) Cs is unknown    Ce = $500

provides these values for a mean of 2.0: Number of FailuresCumulative Probability0 .1351 .4062 .6773 .8574 .9475 .983

51

s.406, so .406($500 )$500s

ss

CC C

C

Optimum stock level = 2, then SL between

Cs = $343.17

The range of shortage cost is $343.17 to $1,047.99.

.677, so .677($500 )$500s

s ss

CC C

C

Cs = $1,047.99.

A company usually carries 2 units of a spare part that costs $500 and has no salvage value. Part failures can be modeled by a Poisson distribution with a mean of 2 failures during the useful life of the equipment. Estimate the range of shortage cost for which stocking 2 units of this spare part is optimal.

Page 52: Economic Production Quantity (EPQ).pptx

Review: Inventory Models• EOQ models used to determine order size

– Simple model for many types of inventory– Trade-off between carrying and ordering costs– Quantity discount model adds purchasing costs

and compares total cost for various order sizes (that is still a feasible EOQ)

• EPQ models used to determine production lot size– Used when producing and depleting items at

same time– Trade-off between carrying and setup costs– Consider production and usage rate

52

Page 53: Economic Production Quantity (EPQ).pptx

Review: Inventory Models• ROP (reorder point)

– Determines at what quantity (when) to re-order – Consider expected demand during lead time and safety stock – Trade-off cost of carrying safety stock & risk of stockout

• Fixed Order Interval Model– Used when orders placed at fixed time intervals – determine

how much to order– Used widely for retail– Consider expected demand during lead time, safety stock,

and amount on hand– Demand or lead time can be variable – Need more safety stock, but not continuous monitoring

• Single-Period Model– Determines at what quantity (when) to re-order – Used when can’t carry goods to next period (e.g.. perishables)– Trade-off cost of shortages & of excess (wasted) inventory

53

Page 54: Economic Production Quantity (EPQ).pptx

Define the term inventory and list the major reasons for holding inventories.

Discuss the objectives of inventory management. List the main requirements for effective inventory

management. Describe the A-B-C approach and perform it.Describe Basic Inventory Control SystemsBe able to describe and solve problems using:

EOQ, EPQ, ROP, Fixed Order Interval Model, Single Period Model.

54