ECONOMIC EVALUATION UNIT FINAL REPORT TSI … ECONOMIC EVALUATION UNIT 140514 ERA-EE- Report CCS TSI...
Transcript of ECONOMIC EVALUATION UNIT FINAL REPORT TSI … ECONOMIC EVALUATION UNIT 140514 ERA-EE- Report CCS TSI...
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 1/78
ECONOMIC EVALUATION UNIT
FINAL REPORT
TSI CCS SCOPE EXTENSION
Reference: Visibility: Extranet
Version: 4.7
Date: 14/05/2014
Prepared by Reviewed by Approved by
Name Wouter MALFAIT Angelo CHIAPPINI
Torben HOLVAD
Pio GUIDO
Position Project Officer Project Officers Head of Units
Date
&
Signat.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 2/78
AMENDMENT RECORD
Version Date Section number
Modification/description Author
1.0 24.04.2012 All First issue Wouter Malfait
1.1 31.05.2012 All Comments AC, HB Wouter Malfait
1.2 01.06.2012 All Comments from ERA-meeting Wouter Malfait
2.0 04.10.2012 All Update with paragraphs 7.3 and Annex 5 (migration) and conclusions in paragraph 7.4
Wouter Malfait
2.1 15/10/2012 All Integration of comments from AC Wouter Malfait
2.2 16/10/2012 7.2.1.3 Trackside systems – ETCS L2 & L3 Wouter Malfait
2.3 30/10/2012 Section 1 & annex 10.4 & 10.5
Delete annex 10.4 & 10.5 (migration models > shifted to separate document) and add executive summary
Wouter Malfait
2.4 21/11/2012 Section 1 & 8.4 Modify 2nd
alinea of provisions within chapter 7
Wouter Malfait
2.5 30/11/2012 All Comments from AM Wouter Malfait
3.0 16/01/2013 Section 1, 8.1.5, 8.3
- Executive summary (1520,
- Executive summary (new structure in chapter 7 / main comment UNISIG)
- new section 8.1.5 (related to 1520)
- section 8.3 (migration costs / main comments CER)
Wouter Malfait
3.1 25/01/2013 All - Executive summary (compensation scheme / comment CER)
- Comments from AC
Wouter Malfait
3.2 30/01/2013 Executive Summary
- Add chapter 1 and chapter 7 with track changes
Wouter Malfait
3.3 04/02/2013 Executive Summary
- Chapter 7 (editorial) Wouter Malfait
3.4 09/04/2013 Executive Summary
- Chapter 7 (change of existing vehicles running on high-speed network by existing high-speed vehicles)
Wouter Malfait
3.5 29/05/2013 Executive Summary
- Delete legal text from Executive Summary
Wouter Malfait
3.6 07/08/2013 Executive Summary
- Proposal without additional requirement on lines outside the European deployment plan
Wouter Malfait
4.6 30/04/2014 All - Comments from CER Position Paper +Comments EC
Wouter Malfait
4.7 14/05/2014 All - Comments EC Torben Holvad
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 3/78
CONTENTS
1 EXECUTIVE SUMMARY ........................................................................................................... 5
2 REFERENCE, TERMS AND ABBREVIATIONS ..................................................................... 9
2.1 Reference .............................................................................................................................. 9
2.2 Units ...................................................................................................................................... 9
2.3 Definitions and abbreviations ............................................................................................. 9
3 INTRODUCTION: CONTEXT ................................................................................................. 11
4 PROBLEM DESCRIPTION ...................................................................................................... 14
5 DEFINITION OF OBJECTIVES .............................................................................................. 19
6 DESCRIPTION OF POLICY OPTIONS .................................................................................. 20
6.1 Introduction........................................................................................................................ 20
6.2 Option 0: baseline scenario ............................................................................................... 20
6.3 Option 1: evolutionary approach: scope extension to OFF-TEN-T without strict
migration requirements ............................................................................................................... 22
6.4 Option 2: revolutionary approach: scope extension to OFF-TEN-T with strict
migration requirement ................................................................................................................ 23
7 ANALYSIS OF OPTIONS: ASSESSMENT OF IMPACT ...................................................... 24
7.1 Introduction........................................................................................................................ 24
7.2 Analysis of option 0: baseline scenario ............................................................................ 24
7.3 Impact of option 1: scope extension to OFF-TEN-T without strict migration
requirements ................................................................................................................................ 25
7.3.1 Qualitative analysis ..................................................................................................................................... 25 7.3.2 Cost impacts - Quantitative analysis ........................................................................................................... 28 7.3.3 Stakeholders’ opinion .................................................................................................................................. 36
7.4 Impact of option 2: scope extension to OFF-TEN-T with strict migration
requirements ................................................................................................................................ 37
7.4.2 Overview of stakeholders’ opinions on option 2 - migration requirements ................................................. 37
8 STAKEHOLDERS OPINIONS .................................................................................................. 39
8.1 Processes ............................................................................................................................. 39
8.2 Overview of questionnaire ................................................................................................ 39
8.2.1 introduction ................................................................................................................................................. 39 8.2.2 Overview of stakeholders’ opinions on option 1 ......................................................................................... 39 8.2.3 Overview of stakeholders’ opinions on option 2 - migration requirements ................................................. 41
8.3 Overview of internal consultation process ...................................................................... 44
8.3.1 Introduction ................................................................................................................................................. 44
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 4/78
8.3.2 results from consultation process related to scope extension ...................................................................... 44
8.4 Overview of workshops ..................................................................................................... 45
8.4.1 Introduction ................................................................................................................................................. 45 8.4.2 Stakeholders’ remaining comments on Scope extension ............................................................................. 45
9 CONCLUSION: COMPARISON OF OPTIONS & PREFERRED POLICY OPTION ..... 48
9.1 Effectiveness & efficiency of the policy options .............................................................. 48
9.2 Preferred policy option ...................................................................................................... 48
10 MONITORING ............................................................................................................................ 49
11 ANNEXES .................................................................................................................................... 50
11.1 Annex 1: List of Class B-systems on TEN-network .................................................... 50
11.2 Annex 2: Infrastructure data (TEN and off-TEN Network)...................................... 52
11.3 Annex 3: Voluntary extension of TSI ........................................................................... 53
11.4 Annex 4: Rolling stock data (TEN and off-TEN Network) ........................................ 56
11.5 Annex 5: Functional analysis & Member States’ view ............................................... 57
11.5.1 Signalling systems ....................................................................................................................................... 57 11.5.2 Radio communication systems .................................................................................................................... 58 11.5.3 Train detection systems ............................................................................................................................... 58 11.5.4 Findings related to scope extension ............................................................................................................. 59
11.6 Annex 6: Rolling stock model ....................................................................................... 60
11.7 Annex 7: Qualitative Analysis of migration ................................................................ 77
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 5/78
1 EXECUTIVE SUMMARY
1.1.1.1 ERTMS (European Rail Traffic Management System) creates a single Europe-
wide standard for train control and command signalling (CCS) systems. The two
main components of ERTMS are the European Train Control System (ETCS, a
standard for in-cab train control), and GSM-R (the GSM mobile communications
standard for railway operations). Directive 2008/57/EC aims to establish the
conditions to be met to achieve interoperability within the European Union’s rail
system. In view of this, Technical Specifications for Interoperability (TSIs) are
developed. This initiative links to the TSI related to control and command
signalling subsystems (CCS) which is currently only applicable to the TEN-T. The
current legal framework provides that new/upgraded high-speed lines and some
railway freight lines (corridors) have to be equipped with ERTMS. On other parts
of the trans-European network national systems called "class B" systemsa can
continue to exist under certain conditions. If there is a need for upgrade of “Class
B” systems, ERTMS/ETCS should be installed. The current TSI CCS is however
not applicable on the off-TEN-T.
1.1.1.2 The main problem identified is that the geographical scope of the TSI relating to
CCS is hindering a cost-effective functioning of the European Union’s railway
system by maintaining technical barriers. Technical barriers still exist today as
there are still more than 20 different CCS-systems deployed within Europe. The
current TSI related to CCS foresee a phasing-out of these legacy systems on the
TEN-T, which represents 40% of the total rail network. Around 10% of the rolling
stock never operates on TEN-T. However, on the off-TEN-T, which represents
around 60% of the network, currently this is not foreseen yet. This implies that the
legacy systems could keep on being divergent, without any prospect of
convergence in the future. The consequence is that trains running on different
networks would need to continue to be compliant with a multiple set of
specifications and have to be equipped with multiple systems. This is hindering
the internal rail market, as it is made more difficult for trains to pass (regional)
borders. Moreover, this is also hindering the development of the internal market in
rail equipment and services.
1.1.1.3 There are varying starting positions in the Member States. In several Member
States, all rolling stock at least partially operates on the TEN-T and has to be
a The Agency has listed in the technical document ‘List of CCS Class B systems’ the national legacy control-command and
signalling systems (‘Class B systems’). Those systems may still be requested on board locomotives and traction units to run
on certain lines.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 6/78
already TSI CCS compliant in the future. This is for example the case in Austria,
Belgium, Finland, Hungary, Ireland, Italy, Luxemburg, Poland, Slovenia,
Netherlands, Sweden. Other Member States could however be more significantly
affected as they still have a part of their rolling stock which only operates on off-
TEN-T and is therefore not yet expected to be TSI CCS compliant. This mainly
concerns the Czech Republic, Denmark, Germany, Latvia, Portugal, Slovakia,
Spain and the United Kingdom.
1.1.1.4 In view of the above, the general objective of this initiative is to stimulate gradual
convergence in command and control systems deployed in the European Union’s
rail system by removing technical barriers in order to increase the cost-
effectiveness of the European Union’s rail system.
1.1.1.5 In order to achieve this goal three policy options are put forward:
Option 0: baseline scenario: no extra action at EU level: no mandatory
scope extension to off-TEN-T, only voluntary migration on the off-TEN-T
Option 1: evolutionary approach: scope extension to OFF-TEN-T without
strict migration requirements
Option 2: revolutionary approach: scope extension to OFF-TEN-T with
strict migration requirements
1.1.1.6 In the baseline scenario (option 0) the main problem as identified will not
completely disappear. Although certain countries are and will be planning to fully
migrate to ERTMS and to get rid of legacy systems, for certain parts of the
railway network, the risk for RUs of further divergence still exists. There is no
guarantee of convergence towards a single EU train control system.
1.1.1.1 Option 1: Compared to the baseline, the positive impact for railway undertakings is
being protected from the risk of future changes to national legacy systems by
freezing the Class B-systems. It is difficult to compare the retrofitting costs in option
1 to future potential retrofitting costs in the baseline scenario, as costs for retrofitting
legacy systems are varying depending on the number of legacy systems needed to be
retrofitted and to the functional upgrades (changes) needed to the system. The
ERTMS retrofitting of an existing single locomotive is today rather costly, as the
costs range between 200.000 EUR and 2.5 million EUR (adding some 20-40% to
their cost). The authorisation cost of an upgraded system is an important part of the
retrofitting cost. Having 1 single EU-target will lead to less cases of retrofitting in
option 1 compared to the baseline scenario due to the avoidance of further
divergence of Class B-systems. Therefore, the impact of freezing Class B-systems
for RUs is expected to be positive.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 7/78
The main impact for infrastructure managers in option 1 is not to be allowed to
upgrade the functionality of existing Class B-systems or to develop new systems,
but to use only TSI compliant CCS systems in case of necessary upgrades. The
investment costs for ETCS trackside systems will not impose any significant
additional costs compared to the baseline scenario (investment costs of upgraded
Class B-systems or newly developed systems). The Member States may also apply
a derogation process in case the “freezing of Class B-systems” would compromise
the economic viability of the rail system in a Member State. This will however
entail some administrative costs.
A long term benefit-cost ratio has been calculated taking into account the traffic
flows between TEN-T and off-TEN-T in order to verify that if ERTMS is the long
term target for TEN-T, this is also valid for the off-TEN-T. In the case of
“simple” train protection systems, long term financial benefits do not yet exceed
long term financial costs with today’s cost figures (benefit-cost ratio is only 0.37).
In the case of “complex” train protection systems, long term financial benefits do
exceed largely the long term financial costs (in 99% of the cases according to a
simulation model). In such case, the benefit-cost ratio is 7.
Therefore, in line with the results of the stakeholder’s consultation, ETCS appears
to be already a viable alternative (in the same order of magnitude) as complex
legacy systems. For simple legacy systems the life cycle costs are still lower than
for ETCS. The proposed legal framework in option 1 is to avoid future upgrades
of legacy systems, but not to limit the further installation of the listed Class B-
systems applicable on the off-TEN-T, so simple as well as complex Class B-
systems may still be installed. Upgrades of simple legacy systems are expected to
be done in case of shifting towards a higher performance level, so moving into the
category of complex legacy systems, resulting in this evolutionary approach also
being applicable for simple legacy systems. Therefore, in reality, it is to be
expected that in most cases there is a positive benefit-cost ratio.
Option 2: In option 2, a more revolutionary approach could be envisaged by
defining some strict migration requirements (as for the corridors and high-speed
lines on the TEN-T network). From the analysis of long term benefits and costs, it
could appear interesting to investigate fast migration scenarios at EU-level, at
least for some complex legacy systems. However, most of the Member States
answering to the public consultation are of the opinion that migration scenarios
should be optimised at national level. The main reasoning is that the optimal
migration scenario depends on different national parameters (such as remaining
lifetime of Class B-systems, remaining lifetime of interfaced systems such as
interlocking systems, required capacity and safety performance level). Moreover,
as the ERTMS migration scenarios are covered by other more suitable EU-
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 8/78
initiatives (including appropriate financial mechanisms), option 2 is not further
developed and is not retained for a detailed cost-benefit analysis including
migration costs.
1.1.1.2 Overall conclusion: It can therefore be concluded that option 1 is the preferred policy
option: the scope of the TSI related to CCS should be extended to the off-TEN-T.
This is not a revolutionary approach, but rather an evolutionary approach which aims
to stimulate convergence in CCS subsystems deployed in the EU towards ERTMS
and TSI compliant train detection systems. It does so by freezing existing legacy
systems and by prohibiting the development of new legacy systems. Only if a
Member State itself decides to take the step to upgrade / change its system, ERTMS
will be imposed.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 9/78
2 REFERENCE, TERMS AND ABBREVIATIONS
2.1 REFERENCE
The documents listed below are referred to by numbers in round brackets, e.g. (5). Footnotes
use letters, such as: (a)
.
Number References
(1) Economic Evaluation: Methodology Guidelines
(2) Compendium on ERTMS, edited by UIC, under the coordination of Peter
Winter, 1st Edition 2009
(3) ERTMS Benchmark Project – Update 2011 Final Report, UIC – April 2012
(4) Extension of field of application of TSIs. Annex 3. Existing extensions of
the geographical scope, 2009
(5) ERA_TD_2011-11– List of Class B systems, 19/03/2012
(6) Report from the Commission to the European Parliament, the Council, the
European Economic and Social Committee and the Committee of the
Regions on the progress made towards achieving interoperability of the rail
system, 30/01/2013
(7) ERA/REP/03-13/ERTMS
Quotations from the above are in italics.
2.2 UNITS
International units and metric system have been used. Kilometres per hour are km/h, never
kph. For thousands, millions and billions (= thousands of millions), the letters k, M and G are
prefixed; for instance: 1 M€ = one million Euros.
For numbers, the decimal separator is a dot “.” ; thousands are separated by spaces “ “ (neither
“,” nor “.”).
2.3 DEFINITIONS AND ABBREVIATIONS
Term or abbreviation Definition
CBA Cost-Benefit Analysis
CCS Control-Command and Signalling subsystems
CR Conventional rail
ESG Economic Survey Group. The group has been set up by ERA and is
managed by its Economic Evaluation Unit. ESG is considering the
Agency impact assessment work undertaken for the different
recommendations of ERA from the point of view of consistency and
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 10/78
Term or abbreviation Definition
correctness of methodology.
EIM European Rail Infrastructure Managers
ERTMS European Rail Traffic Management System
ETCS European Train Control System
GSM-R Global System for Mobile communication - Railway
HS High speed rail
IM Infrastructure Manager (as defined in Directive 2001/14/EC)
NSA National Safety Authority
RISC Rail Interoperability and Safety Committee
RU Railway Undertaking (as defined in Directive 2001/14/EC)
RST Rolling Stock
TSI Technical Specification for Interoperability
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 11/78
3 INTRODUCTION: CONTEXT
3.1.1.1 The diversity of signalling systems in Member States has long been recognised as a
barrier to international rail traffic. What is clear is that Member States have
committed themselves to European Rail Traffic Management System (ERTMS).
ERTMS creates a single Europe-wide standard for train control and command
systems (CCS). The two main components of ERTMS are the European Train
Control System (ETCSb, a standard for in-cab train control), and GSM-R (the GSM
mobile communications standard for railway operations). The equipment can further
be subdivided between on-board and infrastructure equipment.
In 1996 the Council agreed by unanimity that ERTMS should be a key part of
European rail interoperability. Subsequent decisions have deepened Member
States’ commitment to ERTMS. The primary purpose was to contribute to the
completion of the single European railway area, improving the competitive
position of rail transport and stimulating a single market in signalling equipment.
3.1.1.2 The development and deployment of ERTMS in Europe have both progressed over
timec. According to figures from UNIFE, ERTMS has emerged as the system of
choice for railways worldwide, based on the performance of the system, and on the
advantage offered by a multi-supplier system. The figure below demonstrates the
commitment of Member States and industry stakeholders in relation to ERTMS: the
numbers, both for delivered and contracted tracks and vehicles, are increasing over
time within Europe.
b ETCS works as follows: With ETCS, the track sends information to the train enabling it to calculate
continuously its maximum permitted speed. On lines where there is trackside signalling (lights and traffic signs
allowing the driver to know the permitted speed), this information can be forwarded by standard beacons
(Eurobalises) located along the track. This is what is known as ETCS level 1. For ETCS level 2, information can
also be forwarded by radio (GSM-R) and it is no longer necessary to retain trackside signals. This allows
substantial savings in investment and in maintenance. The position of trains is still detected by trackside systems.
Lastly, for ETCS level 3, the train itself sends its rear end location, making it possible to optimise line capacity
and further reduce the trackside equipment. For all levels, a train-based computer, the Eurocab, compares the
speed of the train with the maximum permitted speed and slows down the train automatically if the latter is
exceeded. c SWD(2014)48, Commission staff working document on the state of play of the implementation of the ERTMS
Deployment Plan
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 12/78
Figure: Evolution of ERTMS equipped tracks and vehicles in Europe
Source: Unife
3.1.1.3 Directive 2008/57/EC of the European Parliament and the Council on the
interoperability of the rail system within the Community aims to establish the
conditions to be met to achieve interoperability within the Community rail system in
a manner compatible with the provisions of Directive 2004/49/EC (railway safety
directive). These conditions concern inter alia the design, construction, placing in
service, upgrading, renewal, operation and maintenance of the parts of this system.
The pursuit of this objective must lead to the definition of an optimal level of
technical harmonisation and make it possible to:
(a) Facilitate, improve and develop international rail transport services
within the European Union and with third countries
(b) Contribute to the progressive creation of the internal market in
equipment and services for the construction, renewal, upgrading and
operation of the rail system within the European Union;
(c) Contribute to the interoperability of the rail system within the European
Union.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 13/78
Article 8 of Directive 2008/57 stipulates that the Commission shall adopt
mandates aiming at the development of new Technical Specifications for
Interoperability (TSIs) and/or the review of TSIs already covered with a view to
covering lines and vehicles not yes covered.
3.1.1.4 To this end, the Commission has given a mandate to investigate the extension of scope
to the whole rail system for all the systems of the rail system (energy, infrastructure,
train control and command, wagons, rolling stock and operational rules). The scope
extension of the TSI CCS should also include the definition of viable implementation
strategies for the off-TEN. The Commission Mandate of 29.04.2010d includes the
following part related to TSI CCS:
3.1.1.5 What does scope extension mean?
3.1.1.6 A previous study indicated the intentions of the Member States concerning the
voluntary extension of CCS TSI. The results of this study are described in [4]. You
will find a summary in Annex 1, addressing following question:
“Has the geographical scope of the TSI been extended by the Member State?”
3.1.1.7 It is to be noted that for TSIs relating to other structural subsystems such as
infrastructure (TSI INF), energy (TSI ENE), wagons (TSI WAG) and rolling stock
(TSI LOC&PAS), the extension of scope to the off-TEN-T has already taken place.
This initiative therefore only relates to the scope extension of the TSI relating to CCS
subsystems.
d http://www.era.europa.eu/Document-Register/Documents/TSIs-scope-extention-Mandate-
2010.pdf
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 14/78
4 PROBLEM DESCRIPTION
4.1.1.1 The main problem identified is that the geographical scope of the TSI relating to CCS
is hindering a cost-effective functioning of the European Union’s railway system by
maintaining technical barriers. Technical barriers still exist today as there are still
more than 20 different CCS-systems (“Class B” systems) deployed within Europe.
The current TSI related to CCS foresee a phasing-out of these legacy systems on the
TEN-T. However, on the off-TEN-T currently this is not foreseen yet. This implies
that the legacy systems could keep on being divergent, without any prospect of
convergence in the future. New legacy systems and upgrades of existing legacy
systems could continue to be developed. The consequence is that trains running on
different networks would need to continue to be compliant with a multiple set of
specifications and have to be equipped with multiple systems. This is hindering the
internal rail market, as it is made more difficult for trains to pass (regional) borders,
and as it is technically more complicated for rail operators to establish itself in other
regions/Member States. Moreover, these technically diverging standards are also
hindering the further development of the internal market in rail equipment and
services.
4.1.1.2 The inefficiency of the co-existence of more than 20 “Class B” legacy systems is
recognized by the industry, as in the 2012 Memorandum of Understandinge the
European Rail sector Associations have re-iterated their support for the discussions
between Member States and the European Commission on the setting-up of a global
framework for the de-commissioning of Class B systems.
4.1.1.3 Below a description of the current system is given which further illustrates the main
problem.
4.1.1.4 Functional scope of TSI CCS: the control and command signalling subsystem ‘CCS’
consists of 3 systems, being the train protection system (ETCS), the radio
communication system (GSM-R) and the train detection system.
In the past, products have been developed based on national specifications or
based on suppliers’ specifications. The consequence is that trains running on
different networks need to be compliant with a multiple set of specifications and
have to be equipped with multiple systems. Today, there are more than 20
e http://www.era.europa.eu/Document-Register/Documents/MoU-betweenEC-ERA-and-
Sector-Associations-on-ERTMS.pdf
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 15/78
different CCS-systems within Europe (see Annex 1: List of Class B-systems on
TEN-networkT).
European specifications have been developed for CCS-systems with the aim of
contributing to the establishment of one single European railway area. These
European specifications are included within chapter 4 of the technical
specifications of interoperability of the control and command subsystem (TSI
CCS). ERTMS is the set of European specifications which specifies the train
protection system (ETCS) and the radio communication system (GSM-R).
Besides ERTMS-specifications, the TSI CCS contains also ‘TSI compliant train
detection system’ specifications.
The current legal frameworkf provides that new (or upgraded) high-speed lines
have to be equipped with ERTMS and some key railway freight lines (‘ERTMS
corridors of the European Deployment Plan’) will be equipped by 2015 or 2020
(25000km). Other parts of the trans-European network will be equipped with
ERTMS in the following way: national systems called "class B" systems can
continue to exist under certain conditions on the TEN-T. These systems are clearly
identified and may not be upgraded (they are “freezed”). If there is a need for
upgrade, ERTMS/ETCS should be installed, according to the rules of the TSI
CCS. This avoids further divergence of train protection, radio communication and
train detection systems.
4.1.1.5 Geographical scope of TSI CCS: Today, TSI CCS only applies on the TEN-T, and
does not apply to the lines outside the TEN-T. Therefore, Member States are
currently free to choose which CCS-system can be installed on the off-TEN-T.
Outside the TEN-T, some IMs still use CCS legacy systems due to historical reasons
or better ‘local’ and/or short term cost efficiency. On-board cost differences between
ETCS and existing legacy systems may appear and could influence the economic
viability of the general implementation of ETCS on the off-TEN network. In
addition, trackside overlays (ETCS superimposed on a legacy system) mean added
costs, and trackside changeovers from legacy to ETCS imply rolling stock retrofits.
The most advantageous scenario may be line dependent.
4.1.1.6 Relative importance of TEN-T versus off-TEN-T: The characteristics of the off-
TEN-T consists of more regional lines, less used by cross-border traffic and with
f Commission Decision 2012/88/EU of 25 January 2012 on the technical specification for interoperability
relating to the control-command and signalling subsystems of the trans-European rail system, OJ L 51,
23.2.2012, p. 1.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 16/78
potentially more use of simple signalling systems (with lower performance
requirements) compared to the TEN-T.
- Trackside: The TEN-T covers 40% of the whole rail system according to a
survey held in 2009 (see (4) and Annex 4: Rolling stock data (TEN and off-
TEN Network)). The other part of the European railway network, further on
called off-TEN-T, covers the remaining 60% of the whole rail system. Country
specific figures can be found in Annex 2. The data available suggest that on the
off-TEN-T trackside, ETCS is only very limited implemented, and that legacy
systems are still frequently used.
Figure: Importance of TEN-T and off-TEN-T: infrastructure (length of lines)
Source: ERA - IU-ExtScope-20090807-FinalReport-Annex01_1-Inf.xls
- Rolling stock: Data shows that the relative share of rolling stock which solely
operates on the off-TEN-T and never operates on the TEN-T is very small
(average 2% for locomotives and 9 % for multiple units). The table below
demonstrates that although 60% of the network is off-TEN-T, almost 10% of
the rolling stock is solely operating on the off-TEN-T. 90% of the rolling stock
thus already falls within the scope of the current legal framework on TSI CCS.
It is only the remaining 10,29% of the rolling stock which never operates on
the TEN-T that would therefore be affected by this scope extension initiative.
Table: Quantitative comparison of TEN-T and OFF-TEN-T Rolling Stock (data mainly from year 2005 - see (4))
Rolling stock which is never operated on
TEN lines Global fleet
Percentage of rolling stock which is never operated
on TEN lines
Locomotives 714 30 642 2.33%
Multiple Units 5 280 27 615 19.12%
TOTAL 5 994 58 257 10.29%
Source: ERA - IU-ExtScope-20090807-FinalReport-Annex01_2-LocPas.xls
Moreover, the figure below provides some country specific estimates of the
relative importance of rolling stock never operating on TEN-T. It can be
deducted that most likely railway undertakings operating in only 9 Member
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 17/78
States will significantly be affected by this scope extension initiative to off-
TEN-T: Bulgaria, Czech Republic, Denmark, Germany, Latvia, Portugal,
Slovakia, Spain and the United Kingdom. For some of these countries the
percentage of the rolling stock never operating on TEN-T is rather small (e.g.
Bulgaria, Denmark, Latvia, United Kingdom). For other countries, for certain
categories of rolling stock this percentage is higher than 20 % (e.g. Czech
Republic, Germany, Portugal, Slovakia, Spain). Several Member States will not
be significantly affected, as they have indicated that no trains solely run on the
off-TEN-T (e.g.Austria, Belgium, Finland, Hungary, Ireland, Italy, Luxemburg,
Poland, Slovenia, Netherlands, Sweden).
Figure: Quantitative comparison of TEN-T and off-TEN-T rolling stockg
Source: ERA - IU-ExtScope-20090807-FinalReport-Annex01_2-LocPas.xls
4.1.1.7 Conclusion: The current TSI related to CCS is not yet applicable to the off-TEN-T,
which represents 60% of the total rail network. Around 10% of the rolling stock
g The figures of France have been questioned during a WP-meeting
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 18/78
never operates on TEN-T. This means that for the off-TEN-T, infrastructure
managers can still freely choose the CCS legacy systems to be deployed in the
future, thereby endangering 90% of the rolling stock fleet from running on the off-
TEN-T. This free choice for Member States is the reason that today there are more
than 20 different CCS-systems within Europe. This has a negative impact on the
interoperability of the rail system within the European Union, as trains running on
different networks, need to be compliant with a multiple set of specifications and
have to be equipped with multiple systems. Furthermore, this situation is hindering
the further development of international rail transport services and the internal
market in rail equipment and services.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 19/78
5 DEFINITION OF OBJECTIVES
5.1.1.1 The general objective of this initiative is to stimulate gradual convergence in
command and control systems deployed in the European Union’s rail system by
removing technical barriers in order to increase the cost-effectiveness of the
European Union’s rail system.
5.1.1.2 This will be done by exploring the option to extend the benefits identified for the
TEN-T into a wider geographical scope, as trains cross the border between the TEN-
T and off-TEN-T and may profit from one single legal framework for the whole rail
system.
These benefits are linked to the following specific objectives:
- Providing technical interoperability leading to less equipment costs for trains
when running on different networks;
- Providing operational interoperability leading to less training costs for train
drivers when running on different networks;
- Providing an open market for train protection, radio communication and train
detection systems leading to decreased equipment costs due to the increased
competition and avoidance of single supplier markets (vendor lock-in) for
trackside and on-board equipment;
5.1.1.3 By pursuing these objectives for the rail system, railway undertakings operating both
on TEN-T and on off-TEN-T will be protected from
- having to comply with a different legal framework for off-TEN-T compared to
the TEN-T in order to be authorized for running on the TEN-T and on the off-
TEN-T;
- avoiding to require different national CCS-systems for the off-TEN compared
to the ones on the TEN-T;
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 20/78
6 DESCRIPTION OF POLICY OPTIONS
6.1 INTRODUCTION
6.1.1.1 Three policy options are put forward:
Option 0: baseline scenario: no extra action at EU level: no mandatory
scope extension to off-TEN-T, only voluntary migration on the off-TEN-T
Option 1: evolutionary approach: scope extension to OFF-TEN-T without
strict migration requirements
Option 2: revolutionary approach: scope extension to OFF-TEN-T with
strict migration requirements
6.2 OPTION 0: BASELINE SCENARIO
6.2.1.1 Co-existence of legacy and ETCS signalling systems: in the baseline scenario, half of
the Member States in practice already voluntary extend the scope of the TSIs towards
the whole rail system (see an overview in Annex 3: Voluntary extension of TSI). In
these countries, a combination of legacy and ETCS systems are deployed. The main
reason is that most rolling stock operates both on the TEN-T and on the off-TEN-T.
So, this means that scope extension has no impact for those Member States.
6.2.1.2 Voluntary full ERTMS migration trends in some Member States (ETCS only): Some
Member States (Belgium, Denmark, Switzerland and potentially the Netherlands)
already plan to (voluntary) migrate towards ERTMS on their whole national railway
network (off-TEN-T network and TEN-T), eliminating also the co-existence of the
legacy systems and the ETCS systems. As such, trains running on different networks
would no longer need to comply with a multiple set of specifications and would not
have to be equipped with multiple systems anymore.
6.2.1.3 Affected rolling stock: Data showed that the relative share of rolling stock which
operates on the off-TEN-T and never operates on the TEN-T is very small (average
2% for locomotives and 9 % for multiple units), with a minimum of 0% in several
Member States (e.g. Austria, Belgium, Finland, Hungary, Ireland, Italy, Luxemburg,
Poland, Slovenia, Netherlands, Sweden) up to a maximum of 49% for multiple units
in Czech Republic (see Annex 4: Rolling stock data (TEN and off-TEN Network)).
This shows that most trains running on the European rail system already will have to
fulfill the legal requirements of the TSI CCS in order to receive an authorization for
placing into service. It is to be expected that the leasing vehicles will increase in
importance. Due to this it is very likely that more vehicles will be made ERTMS
compatible as leasing vehicles are supposed to be operational on several networks.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 21/78
6.2.1.4 Member States’ view on the likely evolution of ERTMS deployment on the off-TEN-
T: The questionnaire targeted to Member States has tried to identify the likely
evolutions with regard to scope extension to the off-TEN-T for signalling (ETCS),
radio communication (GSM-R) and train detection systems. 17 answers from
Member States have been received:
With regard to signalling systems: Almost half of the respondents will
have ERTMS as target for their off-TEN network. The other half indicates
following reasons to justify the current legacy system as target or to justify
the postponement of the decision of implementing ERTMS on their off-
TEN-T:
- Low performance lines needs simpler system;
- On-board migration costs are currently still too high;
- The number of vehicles currently equipped with ERTMS is low (“too
early to decide”);
Examples of signalling systems that are still seen as target system are:
ASFA, EVM, LS, PZB/Indusi, SHP.
With regard to radio GSM-R: The questionnaire shows that GSM-R is
used and further rolled out as specific radio communication system. The
answers did not reveal elements which question GSM-R as target system
for the off-TEN network, in the case a specific radio communication
system would be required for the off-TEN network, with one sole
exceptionh. During the EC-workshop, some additional information is
requested relating to the possible use of the public GSM-network for some
lines (see 8.4.2.2).
With regard to train detection systems: 11 out of 14 answers indicate that
track circuits or axle counters compliant with TSI requirements will be
installed off-TEN-T.
From the above it can be concluded that scope extension of TSI CCS to the off-
TEN-T is in general being done on a voluntary base for radio communication
systems and train detection systems. More details on the Member States position
can be found in Annex 5. The provisions related to radio and train detection
systems of the CCS TSI are already suitable for off-TEN-T too, so no additions
are necessary. With regard to signalling systems, almost half of the respondents
will have ERTMS as target for their off-TEN-T. The other half indicate that
mandatory migration towards ERTMS at a certain date is not economic viable yet.
In these Member States, Class B-systems are still required on the railway network.
h one answer indicates a small extension of the existing specific railway radio system (450 MHz) to cover a part of the off-
TEN network.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 22/78
6.3 OPTION 1: EVOLUTIONARY APPROACH: SCOPE EXTENSION
TO OFF-TEN-T WITHOUT STRICT MIGRATION REQUIREMENTS
6.3.1.1 Scope extension: Option 1 extends the scope of the TSI CCS to the off-TEN-T with
the objective of avoiding further divergence of train protection, radio communication
and train detection systems on the off-TEN-T.
6.3.1.2 “Freezing of Class-B systems”: This is NOT a new, general obligation to install ETCS
on off-TEN-T (by a certain date), but only applies in case a Member States decides
itself that changes are needed to its system because either its national Class B-system
has become obsolete or because an upgrade of the national Class B-systems would
be required (due to the need of additional functional requirements). Only under these
circumstances, which are to be decided upon by the Member States only, the scope
extension to the off-TEN-T would imply that Member States would be obliged to
migrate towards the TSI CCS compliant systems (being ERTMS and TSI compliant
train detection systems). They would thus no longer be able to install new Class B-
systems or upgrades of existing Class-B systems (~ “freezing of Class B-systems”).
This reasoning is in line with the TSI CCS requirements currently applicable to
certain parts of the TEN-T.
6.3.1.3 No additional migration timing requirements: in this option, it is to be noted that the
legal framework does NOT include additional strict migration requirements for
ERTMS at trackside or at rolling stock side. As mentioned above, Member States
may decide themselves when off-TEN trackside installations are migrated to the
European target solution based upon their national business case.
6.3.1.4 Possibility of derogations: The Member States may also apply a derogation process in
case the “freezing of Class B-systems” would compromise the economic viability of
the rail system in a Member State according to article 9 – point (d) (derogation
procedure) of the Interoperability Directive 2008/57/EU. The same is true for
projects which are in an advanced stage of development or the subject of a contract
in the course of performance when this initiative is published and enters into force.
Below an extract of article 9 is given.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 23/78
Conclusion: Option 1 is not a revolutionary approach, but rather an evolutionary
approach which aims to stimulate convergence in CCS subsystems deployed in
the European Union. It does so by freezing existing legacy systems and by
prohibiting the development of new legacy system. Only if a Member States itself
decides to take the step to upgrade / change its Class B-system, an interoperable
ERTMS will be imposed.
6.4 OPTION 2: REVOLUTIONARY APPROACH: SCOPE EXTENSION
TO OFF-TEN-T WITH STRICT MIGRATION REQUIREMENT
6.4.1.1 Strict timing requirements for ERTMS migration: Similar to option 1, option 2 extends
the scope of the TSI CCS to the off-TEN-T with the objective of avoiding further
divergence of train protection, radio communication and train detection systems on
the off-TEN network. However, compared to option 1, in addition (faster)
convergence is imposed by adding strict timeline requirements for ERTMS migration
(e.g. as for core network corridors: 2020 or 2025). This in analogy with the current
TSI CCS applicable to the Corridors on the TEN-T, where migration timelines are set
for certain parts of the TEN-T.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 24/78
7 ANALYSIS OF OPTIONS: ASSESSMENT OF IMPACT
7.1 INTRODUCTION
7.1.1.1 Focus on economic analysis: In this section the impact of the baseline scenario is
recapitulated (option 0). Afterwards, the impact of option 1 and 2 will be compared
to that of the baseline scenario. The main focus will be on economic impacts.
7.2 ANALYSIS OF OPTION 0: BASELINE SCENARIO
7.2.1.1 In the baseline scenario the main problem as identified will not completely disappear.
Although certain countries are and will be planning to fully migrate to ERTMS and
to get rid of legacy systems, for certain parts of the railway networkthe risk for RUs
of further divergence of the current situation still exists. Estimates on affected rolling
stock and trackside systems are given in section 6.2. However, no exact estimates are
available, as everything depends on the future decisions of Member States and
railway undertakings on ERTMS migration, which are currently insufficiently
certain.
7.2.1.2 In the baseline scenario, there is no guarantee of convergence towards a single EU
train control system. Member States are free to choose which legacy CCS-systems
are upgraded and required on-board on the off-TEN-T. New legacy systems and
upgrades of existing legacy systems could continue to be developed. The
consequence is that trains running on different networks would need to continue to
be compliant with a multiple set of specifications and have to be equipped with
multiple systems. Train drivers running on networks with different requirements and
signalers will need more training, resulting in higher training costs for railway
undertakings and infrastructure managers. Moreover, CCS-product suppliers would
maintain their “position of national legacy suppliers due to historical reasons,
thereby often providing suboptimal solutions to railway undertakings and
infrastructure managers (e.g. systems becoming obsolete due to the lack of
upgrades/maintenance operations available from the supplier side; difficulties for
other suppliers to offer Class B systems in certain countries). Technical barriers thus
remain and will continue to hinder a cost-effective functioning of the European
Union’s railway system. Moreover, these technically diverging standards are also
hindering the further development of the internal market in rail equipment and
services.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 25/78
7.3 IMPACT OF OPTION 1: SCOPE EXTENSION TO OFF-TEN-T
WITHOUT STRICT MIGRATION REQUIREMENTS
7.3.1 QUALITATIVE ANALYSIS
7.3.1.1 Impact for railway undertakings: In comparison to the baseline scenario, the main
positive impact for railway undertakings is being protected from the risk of future
changes to national legacy systems. However, the railway undertakings have no
overall migration target date when off-TEN-T lines will be equipped with TSI CCS
compliant systems. The freezing of Class B-systems protects the railway operators
from further upgrades of Class B-systems and further divergence within Europe. The
quantification of this positive impact requires a prediction of how many Class B-
systems would change or would be introduced during next years in Europe compared
to not having this EU-framework and the associated additional cost of each upgrade
or change of new Class B-system. As in the past, having no EU-legal framework has
led to more than 20 different CCS-systems, we may assume that new or upgrades to
national systems could appear to suboptimise local situations, to support a national
supplier or incumbent railway operator. The development and upgrade costs for on-
board equipment depends on the change itself and the number of vehicles impacted,
but the cost impact for retrofitting of Class B-systems or developping new systems
are far above the negative potential cost impact of freezing Class B-systems (see also
next point), taking into account the multiple design, installation and re-authorisation
costs for each of the changed Class B-systems. If a Member State itself takes the
decision to migrate towards ERTMS, railway undertakings will based on this
decision have to make their rolling stock ERTMS compatible. Compared to the
baseline scenario, the positive effect for railway undertakings, and especially for
small undertakings, will be that they no longer have to comply with several different
CCS-systems and their possible upgrades.
7.3.1.2 Impact for infrastructure managers: The main impact for infrastructure managers is not
to be allowed to upgrade the existing Class B-systems or to develop new non TSI
compliant systems, but to use TSI compliant CCS systems. The Member States may
apply for a derogation in case this “freezing of Class B-systems” would compromise
the economic viability of the rail system in a Member State or in case of a project in
an advanced stage according to article 9 – point (a) and (d) (derogation procedure)
of the Interoperability Directive 2008/57/EU. Therefore, the main negative impact
are the administrative public costs to apply this derogation process (see below
section 7.3.2.5 for a quantification). If however the choice for a TSI compliant CCS
system is made, the infrastructure manager will benefit from positive scale effects
from the internal market: as there are multiple suppliers of ERTMS products,
infrastructure managers do no longer run the risk of their system becoming
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 26/78
obsolescent. In the past, but also looking into the baseline scenario, “preferred”
national suppliers have not offered or will not offer the necessary
maintenance/upgrade products for legacy systems. This has resulted/ will result in
legacy systems becoming obsolete or outdated, thereby threatening the efficient
continuity of the railway network. In option 1 infrastructure managers will no longer
be exposed to this risk.
7.3.1.3 Impact on local lines: In the scenario where the capacity and safety performance level
is already adequate with the existing legacy system, option 1 poses no risk to the
existence of local lines, as the existing “Class B” systems may still be used, and as
there are no strict migration requirements. If an infrastructure managers decides that
an upgrade of its existing system or a new system is needed however due to
obsolsence of Class B-system and not requiring the full functionality of ETCS (full
supervision), infrastructure managers can decide to install ETCS L1 (with Limited
Supervision) which are seen as suitable variants for Class B-systems also offering
‘Limited Supervision’ train protection levels. Another alternative is ETCS L3 (which
is already available for low densitly lines under the name ‘ERTMS Regional’).
Besides this, Member States (e.g. Denmark) may decide to have a homogeneous
network (ETCS L2 – Full Supervision), profiting from scale effects and having a
similar deployment for the whole network as most cost-efficient strategy.
7.3.1.4 Impact for the different Member States: the countries already voluntarily fully
migrating towards ERTMS on the off-TEN-T are e.g. Belgium, Denmark,
Switzerland, Luxembourg and potentially the Netherlands. These countries are not
impacted at all. As in total almost half of the Member States will have ERTMS as
target for their off-TEN-T, only the other half that does do not intend to freeze the
existing Class B-systems on the off-TEN-T will be affected (see Annex 5 and section
6.2). As most of the Class B-systems are similar to the off-TEN-T and to the TEN-T,
and as Class B-systems on the TEN-T are already frozen by the current TSI CCS, we
moreover assume that the impact of freezing the Class B-systems for the off-TEN-T
will only have a limited impact. This because Member States will most likely not
upgrade a system only for the off-TEN-T as the functional requirements for the off-
TEN-T and TEN-T are mostly similar (see point below and Annex 5: Functional
analysis).
7.3.1.5 Impact on functionality: the stakeholder’s consultation (questionnaire) has
demonstrated that the functionality provided by the TSI CCS systems is applicable
for the use on the off-TEN-T, and that chapter 4 of the TSI CCS requires in general
no significant changes for train protection, radio communication and train detection
systems. The detailed stakeholders’ analysis on functional applicability for the off-
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 27/78
TEN-T can be found in ‘Annex 5: Functional analysis’. Two comments from France
are made (see 8.4.2.2 and 8.4.2.3) related to the radio communication functional
requirements for low density traffic and very dense traffic areas. These are currently
investigated in order to be further integrated in the future ERTMS specifications
(interference topic and ETCS-over-GPRS topic) in order to avoid derogation requests
(specific national developments) for these requests.
7.3.1.6 Impact on the internal market: ERTMS creates an open competitive market as it is
based on a common open set of specifications. Today, this open set of specifications
has opened the market with multiple suppliers for ERTMS products, while the
number of suppliers for Class B-systems is mainly limited from 1 up to 3 suppliers
for a Class B-system. Therefore, the internal open market for ERTMS-products is
expected to increase the cost efficiency of ERTMS in comparison to the cost
efficiency of Class B-systems.
7.3.1.7 Impact on the competitiveness of the European industry: the positive impact on the
European industry is already visible by the use of ERTMS outside Europe.
According to figures from UNIFE, ERTMS has emerged as the system of choice for
railways worldwide, based on the performance of the system, and on the advantage
offered by a multi-supplier system. As the ERTMS industry is dominated by
European players, it is expected that the increased use of ERTMS inside and outside
of Europe, will significantly increase the competiveness of the European ERTMS
industry.
Figure: ERTMS investments worldwide by geographical area (trackside (km))
Source: UNIFE – presentation at UIC-ERTMS conference in Istanbul
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 28/78
7.3.1.8 Impact on safety: Class B-systems also provide for different train protection levels.
However, for convention rail, when migrating towards ERTMS, Member States often
take the decision to invest in higher safety performance levels compared to the
legacy system. This may indirectly lead to safety benefits. Additionally, the safety
impact of moving towards a single EU-train control and communication system may
indirectly lead to safety benefits by having less systematic technical and operational
hazards due to exchange of knowledge of hazards between Member States using the
same interoperable system, and having overall less complexity due to limiting the
divergence.
7.3.1.9 Impact on training of personnel: avoiding divergence in signaling systems will
decrease the overall training cost for maintenance and operational (train-drivers,
signalers) staff in the long term. This will have a positive impact both for the railway
operators and the infrastructure managers.
7.3.1.10 Impact on the environment: the environment is indirectly positively affected by a
more efficient railway market with less technical barriers. A more efficient railway
market will attract more freight traffic and passengers, and will further stimulate
railway transport, which is less polluting than certain other frequently used modes of
transport.
7.3.2 COST IMPACTS - QUANTITATIVE ANALYSIS
7.3.2.1 In the following sections estimates are provided for the additional costs/benefits option
1 entails compared to the baseline scenario. As option 1 is not imposing a general
obligation to install ETCS on off-TEN-T (by a certain date), but only applies in case
a Member States decides itself that changes are needed to its system, it is uncertain
which Member States and railway undertakings will migrate to ETCS at what
moment in time. Therefore, Europe wide calculations cannot be provided. Recourse
is taken to individual life cycle/short term investment costs and long term benefit-
cost ratios for individual projects under certain circumstances. The total EU impact
will depend on the speed and degree of convergence of CCS subsystems.
7.3.2.2 Life cycle costs for trackside systems (for infrastructure managers):
The actual cost comparison between Class B legacy systems and ETCS systems
depends largely on the actual state of the Class B system and the actual cost of costs
of the ETCS system. From the answers to the questionnaire addressed to Member
States it appears that some Class B-systems are already more costly compared to
ETCS-systems (especially for complex systems), while some other Class B-systems
are still less costly (e.g. for simple legacy systems).
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 29/78
However, it is expected by the industry and infrastructure managers that the life
cycle costs of Class B-systems will increase more than the life cycle costs of ETCS-
systems due to following aspects:
- More suppliers offering ETCS-products compared to the number of
suppliers offering Class B-systems;
- More research initiatives in the field of ERTMS compared to limited
initiatives for upgrades of Class B-systems or other new legacy
systems. ETCS Level 3 is expected to be beneficial for the
infrastructure manager with further reduction of costs due to not
needing train detection systems. ERTMS Regional (used for low
density lines) is based on ETCS L3 (however with the current
limitation of using it on low density lines). ETCS L3 is an important
part of the Shift2Rail- research program which aims at reducing further
life cycle costs and improving capacityi.
Today, the cost figures at trackside of ERTMS are already cost competitive
compared to most of the Class B-systems. The fact that 3 Member States have
already decided to migrate voluntary on their complete network provides support
to this statement.
Cost figures depend also on the procurement strategy (framework contract for the
complete network versus project contracts) and the required interfaced
interlocking systems (being included or not in the overall cost figures). Therefore,
cost figures provided by the UIC-Benchmarking study (based on individual
projects) differ substantially from cost figures provided by Banedanmark (the
Danish infrastructure manager), using 2 framework contracts for trackside
deployment on the complete network. They indicate particularly low costs for the
delivery and maintenance of the trackside systems. The figure below provides a
comparison with the UIC benchmark:
i See: http://www.shift2rail.org
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 30/78
Figure: Banedanmark cost comparison with standardized European benchmarks
Source: Slide taken from a presentation by Banedanmark on 17/04/12 on the ERTMS Conference
organized by the EC
During the ERA/EIM (European Rail Infrastructure Managers) workshop of 05th
September 2012, it was confirmed that ETCS provides sufficient economically
viable variants (e.g. ETCS Regional (L3), Limited Supervision, Level 2) to cover
the requirements of the different configurations of the off-TEN network.
Therefore, we may assume similar trackside costs as infrastructure managers will
choose for migrating from Class B-systems towards ETCS until ETCS is at least
cost neutral compared to Class B-systems. This assumption will also be used in
the calculation of the long term benefit-cost ratio (see 0 ).
7.3.2.3 Investment on-board costs for vehicles (for railway undertakings):
Following estimates for the today’s average on-board costs for new vehicles are used
in the rolling stock model, in case of legacy systems, ETCS systems and a
combination of both:
Figure: Average on-board costs for new vehicles
System Estimated average investment
cost
Sensitivity (triangular
distribution)
Simple legacy system 10 k€/on-board unit +/- 5k€
Complex legacy system 100 k€/on-board unit +/- 50k€
ETCS system 200 k€/on-board unit +/- 50k€
ETCS and legacy
system
210 k€/on-board unit (simple
legacy system)j
Sum of investment cost of
ETCS and investment cost of
j The development cost of the integration of the Class B and ETCS –system is not included as this development
is expected to take place in all scenarios (for vehicles running on TEN-network or as part of migration scenario)
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 31/78
300 k€/on-board unit (complex
legacy system)
legacy system
Source: Estimates based on data cost figures from questionnaire
In the baseline scenario the most plausible scenarios for the on-board costs for new
vehicles on the off-TEN-T are 1) a simple legacy system (10 k€/on-board unit), or 2) a
complex legacy system (100 k€/on-board unit) or lastly 3) a combination of ETCS and
a legacy system (210 k€/on-board unit for a combination with a simple legacy system,
and 300 k€/on-board unit for a combination with a complex legacy system). Option 1
would only entail the systems encompassing ETCS for the putting into place of new
vehicles (costs ranging from 200 to 300 k€/on-board unit). This would thus be more
costly than the scenario of having a simple or complex legacy system only. However,
one could assume that if one wants to upgrade or change a simple legacy system, one
would automatically migrate to a complex legacy system. This because in most cases
upgrades are needed for extra functionalities which are not supported by simple legacy
systems. Taking into account the “natural” evolution of simple legacy systems towards
complex legacy systems, the most relevant significant costs difference between option
1 and the baseline scenario, is therefore the difference in costs with complex legacy
systems only. As the internal market for ERTMS-products is expected to increase the
cost-efficiency of ERTMS in comparison to the Class B-systems, this cost difference is
expected to decrease over time and eventually become positive for ETCS systems.
Short term investment on-board costs for existing vehicles (retrofitting costs):
Retrofitting a single locomotive is rather costly, as the costs range between 200.000
EUR and 2.5 million EUR (adding some 20-40% to their cost). The major costs of
retrofitting are linked to the re-design of the type and to the re-verification and
authorisation process. It is difficult to compare the retrofitting costs in option 1 to
possible retrofitting costs in the baseline scenario, as costs for retrofitting legacy
systems are varying depending on the number of systems needed to be retrofitted and
on the changes needed to the system. Leasing companies will however have less cases
of retrofitting in option 1 compared to the baseline scenario due to the avoidance of
further divergence of Class B-systems. In the baseline scenario, railway undertakings
risk that the Member States upgrade their CCS-systems not towards the single EU-
target, being ERTMS.
Comparison of on-board costs for new versus existing vehicles (retrofitting)
The figure below - provided by UIC – compares on-board costs of ERTMS in function
of new versus retrofitting of vehicles:
Figure: Comparison on-board costs for new versus existing vehicles (retrofitting
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 32/78
Source: UIC
Retro-fitment is expensive in any case independent if it is ETCS or a retro-fitment
towards a new or upgraded legacy system. Therefore, in option 1, the legal
framework requires that in case of migration (and required retro-fitment), it has to be
towards ETCS and not towards an upgraded Class-B or new legacy system. This will
limit the number of retro-fitments, especially for RUs currently operating on
different networks, requiring different legacy systems.
7.3.2.4 Long term benefit-cost ratio: A long term benefit-cost ratio is calculated for option 1,
compared to both the situations where a simple legacy system is currently in use or
where a complex legacy system is currently in place. It is simulated that in the long
term, all vehicles running on TEN-T are equipped with ETCS as the TSI CCS is
already applicable for the TEN-T network.
The long term benefits are defined as follows: due to the presence of single
trackside ETCS-system, for trainsk running both on-TEN-T and off-TEN-T, no
additional legacy systems have to be installed on board;
Long term Benefits =
(number of trains running both on TEN-T and off-TEN-T) x (“ETCS+legacy”
on-board cost - ETCS on-board cost)
Long term additional costs: trains running solely off-TEN-T have to be equipped
with ETCS instead of a legacy system. Due to the supposedly higher on-board
k Here used (improperly) as shorthand for “locomotives” or “EMUs” etc.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 33/78
cost for ETCS-system in comparison to legacy system, additional costs appear for
the fleet running solely off-TEN-Tl.
Long term Costs =
(number of trains running solely off-TEN-T) x (ETCS on-board cost - legacy on-
board cost)
The long term benefit cost ratio is calculated by dividing the long term benefits by
the long term costs. The formula can be regrouped into 2 parameters, parameter
‘P1’ related to traffic flows and parameter ‘P2’ related to the cost of on-board
signalling systems:
Long term benefits / Long term costs = P1 x P2
P1 = (number of trains running both on TEN-T and off-TEN-T) / (number of trains
running solely off-TEN-T);
P2 = (“ETCS + legacy’’ on-board cost - ETCS on-board cost)/ (ETCS on-board cost -
legacy on-board cost);
Additional long term benefits due to a higher performance (more capacity, more
functionality or higher safety level) are not taken into account in the benefit-cost
ratio. Further explanations and detailed assumptions for this benefit-cost ratio
calculation can be found in annex 11.6. The results are the following:
In case of comparison with “simple” train protection systems
Long term benefits do not exceed long term costs in case of “simple” train
protection systems. In such case, the benefit-cost ratio is only 0.37. Sensitivity
analyses have been carried out:
- Sensitivity in function of cost price of Class B- on-board system: benefit-cost
ratio = 1
- Sensitivity in function of integration costs: benefit-cost ratio = 1
- Sensitivity in function of percentage of trains running solely on-TEN-T:
benefit-cost ratio = 1
- Simulation model based on triangular distribution model for all parameters
above: in only 8.6% of cases within the simulation model, long-term benefits
l ETCS on board assemblies are generally speaking more complex, hence more expensive. Only large scale production could
induce bring the prices down. Such effects have not been observed so far.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 34/78
exceed long-term costs. A sensitivity analysis demonstrates that the main
influencing parameter is related to the percentage of vehicles running solely
off-TEN-T (and not the price level of the simple legacy system).
In case of comparison with “complex” train protection systems:
Long term benefits do largely exceed the long term costs in case of “complex”
train protection systems. In such case, the benefit-cost ratio is 7. Sensitivity
analyses have been carried out:
- Sensitivity in function of cost price of Class B- on-board system: benefit-cost
ratio = 1
- Sensitivity in function of percentage of trains running solely on-TEN-T:
benefit-cost ratio = 1
- Simulation model based on triangular distribution model for all parameters
above: in 99.99% of cases within the simulation model, the long-term benefits
exceed long-term costs. A sensitivity analysis demonstrates that the main
influencing parameter is related to the percentage of vehicles running solely
off-TEN-T (and not the price level of the complex legacy system).
Conclusion on the long term benefit-cost ratio:
On the comparison of option 1 with “simple” train protection systems: the
percentage of vehicles running only off-TEN-T will mainly determine if
long term benefits exceed long term costs. For low integrated off-TEN-T
lines, simple legacy systems can still be a more economically viable target
than the ETCS-system. However, this is under the condition that these
simple legacy systems would further provide sufficient performance and
safety for the off-TEN-T lines.
On the comparison of option 1 with complex train protection systems:
long term benefits exceed long term costs (in 99.99% of the cases
according to the simulation model). Therefore, ETCS-systems are a more
economic viable solution as long term target than the complex legacy
systems for the off-TEN-T mainly due to the decrease of on-board
systems. The appropriate time for migration has to be taken into
consideration. Migration costs have to be evaluated (at local level) to
verify if these one-time costs do not exceed the overall long term revenues.
Therefore, in line with the results of the stakeholder’s consultation, ETCS (as train
protection system) appears to be a viable alternative (in the same order of
magnitude) as complex legacy systems, which are providing discrete or
continuous speed supervision as train protection functionality. For simple legacy
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 35/78
systems, which are providing a warning/warning-stop functionality, the life cycle
costs are still lower (mainly for on-board systems) than for ETCS. The proposed
legal framework in option 1 is to avoid future upgrades of legacy systems, but not
to limit the further installation of the listed Class B-systems applicable on the off-
TEN-T, so the listed simple and complex Class B-systems may still be used.
Upgrades of simple legacy systems are mostly done in case of shifting towards a
higher performance level, so moving into the category of complex legacy systems.
Therefore, this evolutionary approach is also applicable for simple legacy
systems. According to the simulation model this would be the case in 99.99% of
the situations. Therefore, in reality, it is to be expected that in most cases there is a
positive benefit- cost ratio, which is in line with the results of the stakeholder’s
consultation and which is based on a similar evolutionary approach as for the
major part of the TEN-T.
7.3.2.5 Costs - administrative (public) costs related to the derogation process. A derogation
process consists of mainly 2 administrative steps (step 1 ‘drafting of derogation
request at Member State level’ and step 2 ’verification of derogation request at EU-
level’). These 2 steps induce administrative public costs. The number of derogation
requests is estimated to be limited taking into account the results of the functional
and cost benchmarking analysis (both for TEN-T as for off-TEN-T). Between the
year 2007 and 31 August 2012, the Commission received 90 derogation notifications
from 17 Member States (see (6)) for all TSIs. The repartition by TSI is summarized
in the following diagram:
The highest numbers of derogations were received for the TSIs on safety in
railway tunnels (27 derogations), noise (22) and freight wagons (16).
7.3.2.6 As most Class B-systems are similar for the off-TEN-T and for the TEN-T, the
number of derogation requests only applicable for the off-TEN-T network (and not
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 36/78
for the TEN-T network) is estimated to be even more limited. So, the estimate is to
have maximum 10 cases for the off-TEN-T in Europe in upcoming 10 years.
7.3.2.7 The administrative cost of making at national level and evaluating at EU-level a
derogation file is estimated not to exceed 100 kEUR (+/- 6 man months’ workload in
total), so the total additional administrative (public) costs are expected not to exceed
1 MEURm
during a period of 10 years.
7.3.3 STAKEHOLDERS’ OPINION
7.3.3.1 Stakeholders’ opinion on option 1 (see overview in 8.2.2); Most of the stakeholders
support option 1 in order to protect RUs:
- DE: The more new legacy systems get introduced on the lines, the more different OBUs (on
board units) are necessary for RUs. This will increase the costs for homologation, maintenance
and OBUs.
- DK: It seems not reasonable to introduce new CCS legacy systems outside the TEN-network
and the train operating companies cannot be interested in this as it would increase costs for
onboard equipment.
- PL: Due to the necessity of developing the STM modules, it should not be allowed to functional
change Class B systems; (STM modules are modules which are interfaced with ETCS on-board
system and which allow to operate on lines fitted with Class B trackside system using the Class
B data)
7.3.3.2 In cases of disagreement to extend the scope to off-TEN-T, the reasons are not related
to option 1, but refer already to option 2 and strict migration requirements:
- ES: The versions of the legacy systems should be frozen, except where modifications are
needed to mitigate safety-related flaws in those systems. (as already included in the CCS TSI).
- SK: On the lines outside TEN-Network without CCS systems, safety of transport usually
depends on the proper work of the person managing traffic on the line. It is therefore
appropriate to equip these lines with technical devices excluding human factor mistakes.
Implementation of TSI CCS with extended scope should be based on the decision of MS or IM.
- UK: If it applies to a new type B system development then we strongly agree. If it applies to
the application of existing type B systems then we strongly disagree.
m Maximum administrative cost : 10 (derogation requests in period of 10 years) x 100 [kEUR/derogation
request] equals 1 MEUR
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 37/78
7.4 IMPACT OF OPTION 2: SCOPE EXTENSION TO OFF-TEN-T
WITH STRICT MIGRATION REQUIREMENTS
7.4.1.1 From the analysis of long term benefits and costs in option 1 and annex 6, it may
appear interesting to define migration scenarios at EU-level for complex legacy
systems. However, most of the Member States answering to the public consultation
are of the opinion that the installation of existing (‘freezed’) legacy systems is still
required (examples of signalling systems that are still seen as target system are:
ASFA, EVM, LS, PZB/Indusi, SHP) and that migration scenarios should be
optimised at national level. The main reasoning is that the optimal migration
scenario depends on different national parameters (such as remaining lifetime of
Class B-systems, remaining lifetime of interfaced systems such as interlocking
systems, required capacity and safety performance level). More details can be found
in annex 7 on migration scenarios.
7.4.1.2 Risk for small railway undertakings and the risk of certain lines to be closed due to
high investments costs: several stakeholders have highlighted the risk that fast
obligatory ERTMS migration (=option 2) may lead to financial difficulties for small
railway undertakings and the closure of certain lines due to high investment costs
that this scenario entail. In the scenario where the capacity and safety performance
level is already adequate with the existing legacy system, the benefits of a strict
migration requirement would not outweigh the costs. Therefore, option 2 could entail
risks for some small railway undertakings and local lines.
7.4.1.3 Therefore, in the stakeholders’ view a harmonised migration approach would not be
advisable, nor for complex legacy systems as for simple legacy systems.
7.4.1.4 The detailed stakeholders’ opinions can be found in section 8.2.3
7.4.2 OVERVIEW OF STAKEHOLDERS’ OPINIONS ON OPTION 2 - MIGRATION
REQUIREMENTS
7.4.2.1 The following question has been asked to verify the opinion of stakeholders on
additional migration requirements for the off-TEN-T.
7.4.2.2 The opinions are mostly in the direction of defining migration strategies/requirements
at national level (option 1) and are NOT in favour of option 2 which would introduce
strict migration timelines:
- ES: It should be performed by steps, not only TEN/all the network. In Spain, the scope of this
CCS TSI has been extended for all the lines with international traffic, for the high speed
vehicles and network and for those implementations were an improvement in the performance
was needed.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 38/78
- FI: National IM plans with the ERTMS migration strategies according to costs and benefits.
- DE:
Infrastructure:
It depends on the costs and operational needs. Areas with no or minor links to other parts of
the rail net, like some regional operations, do not need to be touched until the end of the life
cycle of their signalling infrastructure assets. The strategy is directly connected to the arising
costs for the infrastructure manager.
Additionally there are constraints not covered by the TSI CCS, which influence the strategy of
the infrastructure manager (e.g. given by NSA).
Rolling Stock:
It makes sense to control the migration of existing legacy systems for the harmonization of the
railway sector and the opening of national tracks for foreign RUs
The cost situation of small RUs has to be considered.
7.4.2.3 Meanwhile, the optimisation of migration scenarios at EU-level is covered by other
EU-initiatives (including appropriate financial mechanisms) such as:
- The TEN-T Regulation 13/16 of 2013 for migration on the Core Network
(target date: 2030) and Comprehensive Network (target date: 2050);
- The use of differentiated infrastructure charges described in Access Directive
2012/34/EU establishing a single European railway area;
These initiatives cover some of the problems mentionned by stakeholders related
to migration scenarios such as
- appropriate financial mechanisms to solve the problem of lack of investment
funds at Member State level;
- overall migration strategy involving the whole rail system which include
besides the TSI CCS, also the TSI INF (infrastructure) and TSI ENE (energy)
subsystems;
- application of differentiated track access charges to address the problem of
further deployment of ERTMS on-board of vehicles;
7.4.2.4 Conclusion: as the optimal migration scenario on the off-TEN-T depends on national
parameters and as the ERTMS migration scenarios are covered by other more
suitable EU-initiatives (including appropriate financial mechanisms), and as there is
no support of stakeholders, option 2 is not further developed and is not retained for a
detailed cost-benefit analysis.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 39/78
8 STAKEHOLDERS OPINIONS
8.1 PROCESSES
8.1.1.1 The process of consultation included following main stakeholders consultations:
- Explorative questionnaire addressed to Member States mainly to evaluate
option 1 and option 2;
- Working Party CCS at ERA followed by recommendation including internal
consultation process for the recommendation;
- Workshops at EC (DG Move) with RISC-members and sector representatives;
8.2 OVERVIEW OF QUESTIONNAIRE
8.2.1 INTRODUCTION
8.2.1.1 The questionnaire has addressed for signalling, radio communication and train
detection systems the identification of the reference scenario (if already known) and
the potential modifications of functional requirements (chapter 4 within the TSI CCS
framework) and implementation/migration requirements (chapter 7 within the TSI
CCS framework) for its applicability outside the TEN-T. 17 answers from Member
States have been received.
8.2.2 OVERVIEW OF STAKEHOLDERS’ OPINIONS ON OPTION 1
8.2.2.1 The following question has been addressed to verify if Member States support the
avoidance of further divergence of CCS-systems.
8.2.2.2 Question: Do you agree that the TSI CCS scope extension should limit the introduction
of new CCS legacy systems outside the TEN-network?
Number MS Who
RU;IM;NSA Do you agree that
the TSI CCS
scope extension
should limit the
introduction of
new CCS legacy
systems outside
the TEN-
network?
Explanation
1 LU NSA somewhat agree /
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 40/78
2 ES NSA somewhat disagree The versions of the legacy systems should be frozen, except
where modifications are needed to mitigate safety-related flaws in
those systems (as already included in the CCS TSI).
In Spain the legacy system is ASFA which is installed in all the
vehicles and the RFIG network. There are 3 different suppliers
implementing this system.
ASFA will be maintained in the network to allow trains that are
only equipped with this system to run on the network.
3 FI NSA somewhat agree Yes, if brand new systems are not allowed
4 DE NSA strongly agree The more new legacy systems get introduced on the lines, the
more different OBUs are necessary for RU´s. This will increase
the costs for homologation, maintenance and OBUs.
5 PL
(PKP)
IM strongly agree Due to the necessity of developing the new STM modules, there
should not be allowed for functional changes in class B system.
RU neither agree nor
disagree
Positive results (unification and increase security level of build in
systems) are achieved with high costs of implementation.
NSA strongly agree Extending the scope of the TSI CCS should limit the introduction
of outside TEN new existing signaling systems due to high costs.
Newly-built and upgraded lines should be gradually adjusted to
the TSI in order to unification of the conditions of movement of
railway transport.
RU somewhat agree This would allow the upgrading railway lines and standardize
control system.
6 NO NSA strongly agree Scope extension will ensure installation of ETCS when systems
are renewed.
7 AT IM (OBB
Infrastruktur)
somewhat agree
8 SE NSA strongly agree
9 LT NSA ?
10 SL NSA strongly disagree I don't see where this extension should limit the introduction of
new legacy systems outside the TEN network.
11 PT NSA somewhat agree It could be necessary to keep in service existing CCS legacy
systems, taking in account the life cycle of existing signalling
installations and the migration process.
12 CZ NSA somewhat agree It is necessary to equip lines with speed more than 100 km/h by
ATP. The positive result would be only if the equipment of
vehicles was compulsory.
We should find cheaper solution and less complicated - reduced
system. (ETCS LS).
Main requirements :
- safety (not to allow pass signal without permission)
- compatibility with all ETCS vehicles
- EU harmonised system
- reasonable costs for track system and for vehicles
The decision of installation would be left to the member state.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 41/78
13 SK NSA somewhat disagree On the lines outside TEN-Network without CCS systems, safety
of transport usually depends on the proper work of the person
managing traffic on the line. It is therefore appropriate to equip
these lines with technical devices excluding human factor
mistakes. Implementation of TSI CCS with extended scope
should be based on the decision of MS or IM.
14 HU NSA somewhat disagree At the moment the CCS TSI installation costs are non-scaleable,
therefore they cannot be rolled out even to the "traditional new"
systems ( we cannot install a "little bit of" ETCS or GSM-R)
15 EE NSA somewhat agree It should give more overview of different systems and make list
shorter. It should give us a shortlist (3-5 different systems) of
legacies. That would more unify strategies and practices over
whole Europe.
16 DK NSA strongly agree It seems not reasonable to introduce new CCS legacy systems
outside the TEN-network and the train operating companies
cannot be interested in this as it would increase costs for onboard
equipment.
17 UK IM Other We do not understand the term “legacy system” in the context of
this question. If it applies to a new type B system development
then we strongly agree. If it applies to the application of existing
type B systems then we strongly disagree.
8.2.3 OVERVIEW OF STAKEHOLDERS’ OPINIONS ON OPTION 2 - MIGRATION
REQUIREMENTS
8.2.3.1 The following question has been asked to verify the opinion of stakeholders on
additional migration requirements for the off-TEN-T.
8.2.3.2 Question: Do you agree that the TSI CCS scope extension should have an impact on
the national migration strategies for existing CCS legacy systems outside the TEN-
network?
Number MS Who Your opinion - Q 8.1.6
RU;IM;NSA Do you agree that the TSI
CCS scope extension
should have an impact on
the national migration
strategies for existing
CCS legacy systems
outside the TEN-
network?
Explanation
1 LU NSA somewhat agree /
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 42/78
2 ES NSA somewhat disagree The vehicles and network corresponding to the RFIG are
all equipped with ASFA. Only the network is of nearly
13.000 km of lines (and the vehicles running on them)
which only over 1500km are now within the scope of the
TSI.It is clear now that the technical specifications
included in the CCS TSI are consolidated, as stated by
the fact that a reference version of the specifications has
been agreed in the ERTMS MoU. However, there is still
not enough experience in the implementation of this TSI
with different scenarios of networks, not enough
experience with the procedures to place in service and
not real project experience coming from the ERTMS
corridors. We would therefore propose to first take into
account the return of experience of the real projects and
then analyse the extension of scope.
It should be performed by steps, not only TEN/all the
network. In Spain, the scope of this CCS TSI has been
extended for all the lines with international traffic, for
the high speed vehicles and network and for those
implementations were an improvement in the
performance was needed. An analysis should be made in
which scenarios the extension of the scope of the TSI is
useful.
3 FI NSA neither agree nor disagree National IM plans the ERTMS migration strategies
according to costs and benefits.
4 DE NSA strongly disagree Infrastructure
It depends on the costs and operational needs. Areas with
no or minor links to other parts of the rail net, like some
regional operations, do not need to be touched until the
end of the life cycle of their signalling infrastructure
assets.
The strategy is directly connected to the arising costs for
the infrastructure manager.
Additionally there are constraints not covered by the TSI
CCS, which influence the strategy of the infrastructure
manager (e.g. given by NSA).
Rolling Stock
It makes sense to control the migration of existing legacy
systems for the harmonization of the railway sector and
the opening of national tracks for foreign RUs
The cost situation of small RUs has to be considered.
5 PL
(PKP)
IM strongly agree The new migration strategy has to be extended to railway
lines that have been outside the TEN-network so far.
RU neither agree nor disagree Question in the area of responsibility of State
Administration.
NSA strongly agree Ultimately, the TSI system should include the whole
network because it will facilitate the transport
organization, will unify the construction of vehicles and
infrastructure, and first of all will improve safety.
Migration of existing systems for traffic control and
radio system in the direction for systems compliant with
the TSIs shall take place gradually during the upgrade or
major repair of the existing rail infrastructure outside the
TEN.
RU somewhat agree Extending scope of the TSI will involves necessity big
investments Freighters in new system.
6 NO NSA somewhat agree Off-TEN lines are already planned to be included in
existing migration strategy
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 43/78
7 AT IM (OBB
Infrastruktur)
? ?
8 SE NSA somewhat agree
9 LT NSA ?
10 SL NSA strongly agree If these systems would be installed on off-TEN tracks,
then we can expect duplication of system or driving all
vehicles that are consistent with TSI CCS.
11 PT NSA somewhat agree It would be important, in our opinion, within the TSI
CCS scope extension studies, to evaluate the impact of
applicability of basic parameters of CCS TSI in case of
off-TEN network when compared with existing CCS
legacy systems.
12 CZ NSA somewhat agree It is equipped only 2,1 % OFF TEN lines by legacy
system.
13 SK NSA strongly agree
14 HU NSA somewhat disagree In our opinion the question is inaccurate therefore the
answer will be inaccurate as well. As far as off-TEN
ETCS provisioning is reasonable in economic terms, it
must have an impact on the migration concepts as well.
Unless there is a clear evidence of payback, it should not
be made mandatory. Nevertheless, the players of railway
industry normally do not have high reliability, 5-10-year
forecasts relating to the off-TEN network and the parts
thereof. At this stage we do not see that extension of the
CCS TS scope is timely. Before such roll-out the
requirements should be made scalable, It would not be
reasonable, anyway, to make ETCS and GSM-R
mandatory on the off-TEN lines, as such installation
beyond the corridors is not efficient enough in most of
the cases, while these lines are featured by local,
developments affecting a station or a line section.
15 EE NSA somewhat agree There are a lot of national signaling systems, which are
in use on non-public railways. This list should be better
explained and possible strategies should there be set
(also 3 till 5 target systems should be set).
16 DK NSA somewhat agree Seen from a Danish point of view, this change gives no
impact as the national strategy has been to introduce
ERTMS on all lines (in- and outside the TEN-network).
17 UK IM strongly disagree There are other business drivers associated with notn
TENs routes which may result in more readily available
solutions to be implemented; If the TEN routes were
selected on the basis of maximum traffic or importance, I
could support this. However, the UK TEN is such a
mixed bag of routes that this doesn’t hang together. If the
statement had been that it is possible that some lightly
used routes are unlikely to have a business case for using
TSI conformant equipment, that would be different.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 44/78
8.3 OVERVIEW OF INTERNAL CONSULTATION PROCESS
8.3.1 INTRODUCTION
8.3.1.1 The relevant activities have been carried out by the Agency together with the Working
Party already established for the drafting of the CCS TSI currently in force (CCS
WP); such Working Party is involved on a permanent basis for all aspects related
to the maintenance of CCS TSI and mandatory specifications referenced therein.
8.3.1.2 The members of the Working Party that have contributed to this proposal include
experts from CER, EIM, UNIFE, NSAs, Notified Bodies and also experts of GSM-R
suppliers. NSAs have been involved also through the “Focus group on ERTMS” and
the Notified Bodies through the “ad hoc group on ERTMS”.
8.3.1.3 After the Working Party activity, the resulting proposal for a recommendation on
revision of the CCS TSI has been submitted for internal and external consultation
before being sent to the EC. The internal consultation took place from August 7th
to
September 8th
2012, followed by an external consultation with social partners,
expiring December 9th
2012n. The results of this consultation are described below.
8.3.2 RESULTS FROM CONSULTATION PROCESS RELATED TO SCOPE
EXTENSION
8.3.2.1 The proposed amendments to the CCS TSI are unchanged, with respect to the
outcome of the internal and external consultation; only some additional clarifications
have been added in the accompanying report (see (7)). Following comments have
been received on the scope extension part:
8.3.2.2 According to the request from ES, also the CCS TSI is not applicable to metric gauge
networks.
8.3.2.3 There are no divergent opinions to mention, with the exception of letters sent by LV
and LT NSAs related to parameters for compatibility of train detection systems in
1520 mm track gauge systems. The specification referenced as Index 77 in the CCS
TSI has been updated according to needs of LV and LT.
n The consultation documents can be found on: http://www.era.europa.eu/Document-
Register/Pages/Consultation-of-recommendation-on-revised-TSI-CCS.aspx
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 45/78
8.4 OVERVIEW OF WORKSHOPS
8.4.1 INTRODUCTION
8.4.1.1 After the consultation process, the EC has organised different workshops with the
Member States and representative organisations (industry players, infrastructure
managers and railway undertakings) and bilateral meetings in relation to the TSI
CCS Scope Extension.
- Workshop on 04th
June 2013 (based on draft recommendation);
- Workshop on 28th
January 2014;
- Workshop on 29th
April 2014;
8.4.1.2 In the last workshop held on 29th
April, the stakeholders’ did confirm the strategy of
option 1 related to off-TEN T.Almost all of the comments and requested changes to
the TSI CCS do not relate to the scope extension to the off-TEN-T network, but refer
to specific changes in the ERTMS specifications (valid both for TEN-T and off-
TEN-T).
8.4.1.3 The main aspects related to the Agency’s impact assessment are handled below.
During the last workshop held, the majority of stakeholders’ supported the scope
extension part. Remaining requests for clarification are listed below.
8.4.2 STAKEHOLDERS’ REMAINING COMMENTS ON SCOPE EXTENSION
8.4.2.1 Comment from Poland related to gauges 1520 mm
Comment received ERA-answer
CCS TSI should not apply for lines with gauge 1520 mm
and vehicles running on lines with gauge different from the
gauge of the main network in the MS.
Application of TSI in such cases does not influence
interoperability and safety at level of MS and EU.
In case of PL such lines are 5% of the rail infrastructure at
the border with third countries.
Maintenance of cross border trackside is frequently made
by third counties’ railway companies.
Application of CCS TSI would face also the difficulties
connected with existing lack of clear ownership rights and
setting the borders between IMs.
If the PL proposal is not accepted, ERTMS should be
ERA has been working with “1520 countries” (LV, LT,
EE and FI) with significant progress in the definition of
basic parameters. PL has a cross border connection to
LT.
The harmonisation at EU level of parameters is also a
basis for better coordination in the context of OSJD.
Other TSIs (LOC&PAS and Infrastructure) already
apply to 1520 mm track gauge.
Problems with ownership and setting of borders are not
due to application or non-application of CCS TSI.
The amended CCS TSI does not mandate
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 46/78
installed also in sections belonging to third countries.
implementation of ERTMS off-TEN; the
implementation rules are not modified in this respect.
8.4.2.2 Comment from CER and France related to use of public roaming (instead of use of
GSM-R network):
Comment received ERA-answer
CER fear that the modification from (MI) to (M) of SRS
clause §3.5.1 table 3-A may hinder the access to public
network through roaming which is widely used in Europe.
An interoperable approach to roaming compliant with the
interference resolution plan is to be proposed in the scope
of GSM-R specifications and, in the future, of FRMCS.
As a majority of the IMs
- do not require to receive the public GSM-band
or the GSM-E band for running on a part of their
network or on their complete network
or
- do allow the use of public (commercial) GSM-
handhelds in case of requiring the reception of
public GSM (instead of CAB-mobiles receiving
public GSM-band), most CAB-mobiles do not
need to be capable to work outside the GSM-R
band;
Therefore, a change request is proposed to have as
‘MI’-requirement that the CAB-mobiles are working in
the GSM-R band (while keeping the public GSM-band
and E-band as optional), rather than vice-versa (all
CAB-mobiles working in the GSM + GSM-E band +
GSM-R band, while allowing exceptions for those only
working in GSM-R band).
ERA-IMPACT ASSESSMENT (change request
approved on Control Group Meeting of 03/10/2013):
Impact IM: this change request does not have a
significant impact on Infrastructure Managers as it
does not question the use of public GSM on the
network. The limited impact for the Infrastructure
Manager should be to be transparent to RUs which
lines require the GSM-R, the GSM-E band or the
public GSM-band.
Impact RU: it gives more freedom to RUs in order
to decide which CAB-mobiles have to be installed,
including which appropriate protective measures
are needed. This change request allows opening the
market for finding the most efficient protective
measures for 1 of the 2 causes related to
interferences, being intermodulation.
- In case the technical evolution demonstrate
that filters as protective measure are more
efficient than the improved GSM-R receiver
Comment FR:
the restraining of the frequency band requirements should
not prevent GSM-R roaming towards public GSM band.
Indeed, the restraining of frequency band will hinder the
possibility to use GSM-R roaming because the GSM-R
mobile, which supports the functioning of the GSM
roaming, will not receive any longer the transmission from
the public GSM network. However for lines with very low
trafic, GSM-R is not affordable and economically viable.
Then, the use of GSM-R roaming provides the opportunity
to enhance the safety of the railway system by make
available train radio communications for these lines.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 47/78
with better linearity, than this change request
will have a significant positive impact for RUs.
- Vice-versa, in case the technical evolution
demonstrate that improved GSM-R receivers are
more efficient as protective measure than filters,
than this change request will have no impact as
railway undertakings will prefer the most
efficient solution for their situation.
8.4.2.3 Comment from CER and France related to very dense areas:
non-ERTMS CCS might be necessary for ensuring very
dense levels of traffic, at least until high performance
ERTMS L3 implementations are available (situation similar
to Crossrail).
Very dense levels/capacity:
• Work is in progress to extend current ERTMS
functionality (e.g., connection to ATO, use of
communication systems other than GSM-R),
so all effort should be based on current
ERMTS specifications related to development
of new systems, as the technical challenges
are similar. ERA is ready to take into
consideration requirements coming from
experience and real implementation needs (see
CCM-process) in order to avoid new legacy
systems.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 48/78
9 CONCLUSION: COMPARISON OF OPTIONS &
PREFERRED POLICY OPTION
9.1 EFFECTIVENESS & EFFICIENCY OF THE POLICY OPTIONS
9.1.1.1 In can be concluded that the baseline scenario (option 0) is ineffective in ensuring a
cost-effective functioning of the European Union’s railway system as technical
barriers will remain and CCS systems will continue to diverge in the future.
Therefore, option 0 can be excluded as preferred policy option. The contrary is true
for option 1 (scope extension to OFF-TEN-T without strict migration requirements)
and option 2 (scope extension to OFF-TEN-T with strict migration requirements):
both options would be effective in removing technical barriers. For option 1 an
evolutionary approach is foreseen towards gradual ERTMS convergence. For option
2 strict timing migration scenarios would be foreseen.
9.1.1.2 Based on a quantitative analysis it was demonstrated that option 1 is cost-efficient in
the long run: with today’s cost figures, it provides for a positive benefit-cost ratio in
99,99% in case of complex legacy systems. In case of “simple” train protection
systems, in only 8.6% of cases, long-term benefits exceed long-term costs. However,
this is under the condition that these simple legacy systems would further provide
sufficient performance and safety levels. Upgrades of simple legacy systems are
mostly done in case of shifting towards a higher performance level, so moving into
the category of complex legacy systems. Therefore, in reality, it is to be expected
that in most cases there is a positive benefit- cost ratio.
9.1.1.3 With regard to option 2 stakeholders emphasised that the optimal migration scenario
depends on different national parameters. The installation of existing (‘freezed’)
legacy systems could still be required and more cost-effective in het short-run,
depending on the national circumstances (such as remaining lifetime of Class B-
systems and interlocking systems, required capacity and safety performance level).
Furthermore, stakeholders highlight the risk for small railway undertakings and for
certain lines to be closed due to high investments costs in case of mandatory
migration at a suboptimal timing. For these reasons, option 2 is judged not to be
cost-effective.
9.2 PREFERRED POLICY OPTION
9.2.1.1 From the above it is concluded that option 1 is the preferred policy option:
evolutionary approach: scope extension to OFF-TEN-T without strict migration
requirements. The proposed legal framework in option 1 is to avoid future upgrades
of legacy systems, but not to limit the further installation of the listed Class B-
systems applicable on the off-TEN-T, so the listed simple and complex Class B-
systems may still be used.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 49/78
10 MONITORING
10.1.1.1 It is important to monitor the cost trends of ETCS and identify the underlying cost
drivers in order to monitor the CCS-systems and potential activities to be undertaken
in order to maintain the system. Further on, the migration models for the complete
network (or part of the network) will give useful information in order also to
prioritise potential activities in the field of ERTMS.
10.1.1.2 Moreover, in order to monitor the general objective of this intiativeo, it would be
useful for ERA to monitor the following indicators:
Changes in the planned date of switch off of national legacy systems
Total train-km operated on ERTMS equipped infrastructure on the off-TEN-T
Total number / or percentage of retrofitted locomotives on the off-TEN-T
Total number / or percentage of retrofitted locomotives operating on ERTMS
equipped infrastructure on the off-TEN-T
o As a reminder: the general objective is to stimulate gradual convergence in command and control systems
deployed in the European Union’s rail system by removing technical barriers in order to increase the cost-
effectiveness of the European Union’s rail system
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 50/78
11 ANNEXES
11.1 ANNEX 1: LIST OF CLASS B-SYSTEMS ON TEN-NETWORK
Extract from file ERA_TD_2011-11 v10
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 51/78
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 52/78
11.2 ANNEX 2: INFRASTRUCTURE DATA (TEN AND OFF-TEN
NETWORK)
Data mainly from year 2005 - see (4)
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 53/78
11.3 ANNEX 3: VOLUNTARY EXTENSION OF TSI
Extension of the field of application of TSIs - Extensions existing in the MS - Questionnaire Summary (24-June-2009)
AT BE BG CZ DK EE FI FR DE GR HU
HS INF No In pract. No NA NA NA Planned
(N-FI-1)
In pract.
(N-FR-1) No No In practice
CR INF No No No No No Planned Planned
(N-FI-1) No No No
Planned, in
pract.
HS ENE No In pract. No NA NA NA Planned
(N-FI-1)
In pract.
(N-FR-1) No No In pract.
CR ENE No No No No No No Planned
(N-FI-1) No No
Planned,
in pract.
HS CCS No In pract. No NA NA NA Planned
(N-FI-1)
In pract.
(N-FR-1) No No In pract.
CR CCS No Yes Partially
(N-BG-1) No
Yes.
Partially
(N-DK-1)
No Planned
(N-FI-1)
ERTMS:
Corridors
GSM-R: Y
No No In pract.
HS OPE Planned In pract. No NA NA NA Planned
(N-FI-1)
In pract.
(N-FR-1) No No In pract.
CR OPE Planned Yes Partially
(N-BG-1) Planned
In pract.
Partially
(N-DK-2)
No Planned
(N-FI-1) Yes No No Planned
HS RST No In pract. No NA NA NA Planned
(N-FI-1)
In pract.
(N-FR-1) No No In pract.
CR RST No In pract. No No No Planned Planned
(N-FI-1) No No
Planned, in
pract.
WAG No In pract. Partially
(N-BG-2) No No No
Planned
(N-FI-1) In pract.
Partially
(N-DE-1) No In pract.
NOISE No In pract. Partially
(N-BG-2) No No
Planned,
partially
N-EE-1
Yes
(N-FI-1)
In pract.
Partially
(N-FR-2)
No No In pract.
SRT No No No No No No Yes No No No In pract.
PRM No No No No No Planned Yes
(N-FI-1)
Plan. (only
Spec., not
Conf. As.)
No No In pract.
- INF part
- RST part
Comments
All
HS
lin
es a
re p
art
of
TE
N.
All
roll
ing
sto
ck
oper
ate
on
TE
N
at
leas
t
occ
asio
nal
ly
No
HS
lin
es i
n t
his
MS
No
HS
lin
es i
n t
his
MS
No
HS
lin
es i
n t
his
MS
All
HS
lin
es a
re p
art
of
TE
N
Dec
isio
n
abou
t th
e ex
tensi
on
of
the
sco
pe
of
the
TS
Is i
s ta
ken
in t
he
pro
cess
of
tran
sfo
rmat
ion
of
the
TS
Is
into
nat
ional
law
; not
by t
he
NS
A.
Th
e T
SIs
are
ap
pli
ed o
n t
he
TE
N a
nd
on
the
bra
nch
lin
es u
p t
o 5
0 k
m f
rom
the
TE
N
lines
. T
his
m
akes
up
nea
rly
th
e
wh
ole
net
work
.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 54/78
IT IE LV LT LU NL NO PL PT RO SK
HS INF NA No No NA Yes In pract.
(N-NO-1) No In pract. NA NA
CR INF No No No No Planned Planned, in
pract. No
Planned,
partially
(N-PT-1)
Planned,
partially
(N-RO-1)
No
HS ENE NA No No NA Yes In pract.
(N-NO-1) No In practice NA NA
CR ENE No No No Planned Planned Planned, in
pract. No
Planned,
partially
(N-PT-1)
Planned,
partially
(N-RO-1)
No
HS CCS NA No No NA Yes In pract.
(N-NO-1) No In practice NA NA
CR CCS No No No Partially
(N-LU-1) Yes In pract. No
In pract.,
partially
(N-PT-1)
No No
HS OPE NA No No NA Yes In pract.
(N-NO-1) No In pract. NA NA
CR OPE In pract. Yes No Partially
(N-LU-1) Yes In pract. No
Planned,
partially
(N-PT-2)
No No
HS RST NA No No NA Yes In pract.
(N-NO-1) No In pract. NA NA
CR RST Planned, in
pract. No No
Planned
Planned, in
pract. No
Planned,
partially
(N-PT-1)
No No
WAG In pract. No No Partially
(N-LU-2) Yes
Planned, in
pract. No In pract. No No
NOISE In pract. No No Yes Yes In pract. No In pract. No No
SRT No No No Partially
(N-LU-3) Yes In pract. No
In pract.,
partially
(N-PT-1)
No No
PRM Yes (only
Spec., not
Conf. As.)
No Yes Yes Planned, in
pract. No
In pract.,
partially
(N-PT-1)
No No
- INF part No
- RST part In pract.
Comments
No H
S l
ines
in t
his
MS
The
scope
of
appli
cati
on o
f th
e T
SI
is
exte
nde
to t
he
who
le m
ain
net
wo
rk (
i.e.
net
work
w
her
e pub
lic
serv
ices
ar
e
oper
ated
).
The
Norw
egia
n p
art
of
the
TE
N m
akes
up a
lmost
the
enti
re n
atio
nal
net
wo
rk.
No H
S l
ines
in t
his
MS
. F
utu
re l
ines
wil
l
be
buil
t ac
cord
ing t
o t
he
TS
Is
No H
S l
ines
in t
his
MS
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 55/78
SI ES SE UK
HS INF NA In pract. Yes No
CR INF No No Planned No
HS ENE NA In pract. Yes No
CR ENE No No Planned No
HS CCS NA In pract. Yes No
CR CCS No No Yes No
HS OPE NA Planned Yes In pract.
CR OPE Yes Planned Yes In pract.
HS RST NA Planned Yes In pract.
CR RST No Planned,
partially
(N-ES-1)
Planned In pract.
WAG No Planned,
partially
(N-ES-1)
Yes In pract.
NOISE No Planned Yes In pract.
SRT No No Yes NA
PRM No Planned Yes
- INF part
Yes (only
Spec., not
Conf. As.)
- RST part
In pract.
Comments
No H
S l
ines
in t
his
MS
All
HS
lin
es a
re p
art
of
TE
N.
If o
ff-T
EN
HS
is
buil
t, T
SI
wil
l be
appli
ed.
All
HS
lin
es a
re p
art
of
TE
N.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 56/78
11.4 ANNEX 4: ROLLING STOCK DATA (TEN AND OFF-TEN
NETWORK)
11.4.1.1 Quantitative comparison of TEN and OFF-TEN Rolling Stock (data mainly from
year 2005 - see (4))
Rolling stock which is never operated
on TEN lines Global fleet
Percentage of rolling stock which is never operated on TEN lines
Locomotives 714 30 642 2.33%
Multiple Units 5 280 27 615 19.12%
TOTAL 5 994 58 257 10.29%
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 57/78
11.5 ANNEX 5: FUNCTIONAL ANALYSIS & MEMBER STATES’ VIEW
11.5.1 SIGNALLING SYSTEMS
11.5.1.1 From the answers on the questionnaire, following elements are derived. Almost half
of the respondents will have ERTMS as target for their off-TEN network. The other
half indicates following reasons to justify the current legacy system as target or to
justify the postposal of the decision of implementing ERTMS on their off-TEN
network:
- Low performance lines needs simpler system;
- On-board migration costs are too high;
- The number of vehicles currently equipped with ERTMS is low (“too
early to decide”);
Examples of signalling systems that are still seen as target system are: ASFA,
EVM, LS, PZB/Indusi, SHP.
11.5.1.2 Question: Are there any technical aspects in chapter 4 of the current CCS TSI,
related to ETCS specifications, which would require modifications for the
applicability of ETCS outside the TEN-network?
11.5.1.3 One reply on the questionnaire indicated following remark:
“ERTMS level 3 is technically fully specified in chapter 4, but the safety level
need to be specified, i.e. extend the scope of subset-91 and make requirements on
level 3.”
11.5.1.3.1 ERA answer:
Trackside: the possibility of having different SIL (Safety Integrity Levels) for
track-side equipment is already foreseen in the TSI and no modifications are
necessary – no action needed;
On-board: if the revised TSI accept a lower SIL for the common functions of
the ETCS on-board equipment (used in ETCS L1, L2 & L3), it will not
anymore be interoperable and will become de facto a new European system;
Specifications for the safety level of the train integrity function (only
applicable in ETCS L3) shall be added within subset 091 in order to avoid
multiple on-board solutions for cross-border operation;
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 58/78
11.5.2 RADIO COMMUNICATION SYSTEMS
11.5.2.1 The questionnaire shows that GSM-R is used and further rolled out as specific radio
communication system. The answers from the Agency’s impact assessment did not
reveal elements which question GSM-R as target system for the off-TEN network, in
the case a specific radio communication system would be required for the off-TEN
network, with one sole exceptionp.
11.5.2.2 Question: Are there any technical aspects in chapter 4 of the TSI CCS, related to
GSM-R voice or data specifications, which would require modifications for their
applicability outside the TEN-network?
11.5.2.3 One reply on the questionnaire indicated following remark: “The TSI demands on
the coverage level and QoS for ETCS L2 lines are too high for off-TEN lines.”
11.5.2.3.1 ERA answer: no mandatory requirements are set for the conventional rail and high-
speed rail related to the coverage level and Quality of Service requirements
(already deleted from Annex A in previous TSI revision). Therefore, it is not an
issue of scope extension.
11.5.3 TRAIN DETECTION SYSTEMS
11.5.3.1 Question: Would you install track circuits/axle counters meeting the frequency
management requirements as specified in the TSI also outside the TEN-network?
11.5.3.2 11 out of 14 answers indicate that track circuits or axle counters compliant with TSI
requirements will be installed off TEN. Following question addresses and clarifies
the answers which didn’t clearly express the installation of TSI compliant track
circuits/axle counters.
11.5.3.3 Question: “Are there aspects in the interface document (see [5]), related to train
detection systems specifications, which would require modifications for their
applicability outside the TEN-network (e.g. modification of frequency
management)?”
11.5.3.4 Answers received from questionnaire:
11.5.3.4.1 Include DC Track circuits in the TSI frequency management;
11.5.3.4.2 More investigation needed related to the existing systems (including track circuits
from CLC/TS 50238-2:2010) including their impact on rolling stock costs;
p one answer indicates a small extension of the existing specific railway radio system (450 MHz) to cover a part of the off-
TEN network.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 59/78
11.5.3.4.3 Secondary utilization (re-deployment) of the traditional non-interoperable
equipment dismounted from the TEN lines to be used on off-TEN lines;
11.5.3.4.4 ERA answer: this topic is in progress in order to close the open point within one of
the next revisions of the TSI CCS.
11.5.4 FINDINGS RELATED TO SCOPE EXTENSION
11.5.4.1 Scope extension of TSI CCS is in general being done on a voluntary base for radio
communication systems and train detection systems. The provisions related to radio
and train detection systems in chapter 7 of the CCS TSI are already suitable for off-
TEN too, so no additions are necessary.
11.5.4.2 Half of the answers indicate that option 2 (with mandatory migration towards
ERTMS) is not economic viable yet. In these Member States, Class B-systems are
still required on the railway network.
11.5.4.3 These conclusions do also apply for the Member States representing the 1520
network (see table below).
The train detection systems currently in use on the 1520 network are included
within the definition of TSI compliant train detection systems.
11.5.4.4 In Finland (having 25kV energy system), the vehicle design is similar as vehicles
designed for 1435mm track gauge (with similar requirements related to EMC and
train detection systems). In such case, only the bogies are replaced to run on the
broader 1520/1524 network. Therefore, Member States within the 1520 network
have also potential benefits in having similar EMC-requirements and train detection
systems requirements as in the 1435mm network in order to make use of similar
vehicle designs.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 60/78
11.6 ANNEX 6: ROLLING STOCK MODEL
11.6.1.1 The rolling stock model has the objective to verify if the target is desirable, which
means if long term benefits exceed long term costs once migration has taken place
based on the assumption that ETCS provides sufficient viable implementation
strategies for infrastructure managers in the long term (ETCS Limited Supervision,
ETCS L3). The second question “Is the target reachable” will be addressed in the
section related to migration costs.
11.6.1.2 Following elements are used to estimate long term benefits and long term additional
costs between scenario 1 and the reference scenario:
11.6.1.3 Assumption: in the long term, all vehicles running on TEN are equipped with ETCS.
11.6.1.4 Long term benefits: due to the presence of single trackside ETCS-system, for trainsq
running both on-TEN and off-TEN, no additional legacy systems have to be installed
on board;
Long term Benefits =
(number of trains running both on TEN and off-TEN) x (“ETCS+legacy” on-
board cost - ETCS on-board cost)
11.6.1.5 Long term additional costs: trains running solely off-TEN have to be equipped with
ETCS instead of legacy system. Due to the supposedly higher on-board cost for
ETCS-system in comparison to legacy system, additional costs appear for the fleet
running solely off-TENr.
Long term Costs =
(number of trains running solely off-TEN) x (ETCS on-board cost - legacy on-
board cost)
11.6.1.6 The long term benefit cost ratio is calculated by dividing the long term benefits by
the long term costs. The formula can be regrouped into 2 parameters, parameter ‘P1’
related to traffic flows and parameter ‘P2’ related to the cost of on-board signalling
systems:
q Here used (improperly) as shorthand for “locomotives” or “EMUs” etc.
r ETCS on board assemblies are generally speaking more complex, hence more expensive. Only large scale production could
induce bring the prices down. Such effects have not been observed so far.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 61/78
Long term benefits / Long term costs = P1 x P2
P1 = (number of trains running both on TEN and off-TEN) / (number of trains running
solely off-TEN);
P2 = (“ETCS + legacy’’ on-board cost - ETCS on-board cost)/ (ETCS on-board cost -
legacy on-board cost);
11.6.1.7 Assumption: although the long term benefit cost ratio does not depend upon the total
yearly number of vehicles placed into service, this number is estimated at 2 000
vehicles per year (on-TEN and off-TEN network). This figure allows us to calculate
the absolute values of long term costs and benefits for the European network. This is
based upon 60 000 vehicles into service, and a lifetime of 30 years.
11.6.1.7.1 Assumption: additional long term benefits due to a higher performance (more
capacity, more functionality or higher safety level) are not taken into account in the
model. The justification is based upon the reasoning that 1) the current legacy
systems provide sufficient performance; 2) the model focuses on interoperability
benefits and costs; 3) supplemental benefits (e.g. capacity) that would be enabled
by the more expensive ETCS implementations would also require additional
investment before they can materialize. In other words; “enablers” provide
opportunities, but opportunities cannot be valued the same as benefits.
11.6.1.8 Trackside systems
11.6.1.8.1 Assumptions: no trackside cost differences are taken into account in the model
between legacy systems and ERTMS-systems for newly installed trackside systems.
Justification for this assumption is based upon the elements provided in 7.3.2.2 and
following reasoning:
Table: Cost impact analysis of short term investment costs for trackside systems
Case Reference
scenario
Scenario in
case of scope
extension
Qualitative cost impact
analysis
1 No train
protection system
installed
No train
protection
system
None
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 62/78
installed
2 Legacy system -
discrete / spot
supervision
ETCS –
Limited
Supervision
No significant cost difference
expected in comparison to
upgrade or new legacy system
using other spot-technologies
than balises (simple legacy
system) under the prerequisite of
adapted interlocking:
Life cycle costs of balises are
similar to life cycle costs of
other spot- technologies such as
coils, …)
3 Legacy system -
continuous
supervision using
track circuits
ETCS L2/L3 Positive cost impact expected n
comparison to upgrade or new
legacy system using track
circuits (complex legacy
system):
GSM-R data transmission is needed (-);
No lineside signals (+);
Free choice of TSI compliant train
detection system (+);
11.6.1.8.2 Case 2 concerns systems in which transmission systems of legacy systems are
using galvanic contacts, inductive coils, electronic transponder devices or cable
loops. These devices are comparable to transmission systems using switchable
‘ETCS’-balises or Euro loops, with cabling and connecting to the signal.
Therefore, we assume similar life cycle costs for these types of trackside systems.
Answers from the questionnaire indicate cost figures between 15-20 k€/signal (EBICAB,
PZB, ETCS). An exception is made for simple legacy systems (warning; warning-stop) where
lower cost figures are mentioned.
11.6.1.8.3 Case 3 concerns systems in which track-circuits are not only used for vacancy
proving, but also for data transmission from track to train. These systems are used
with following geographical scope in Europe (data derived from (2)):
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 63/78
- Netherlands (system ATB-EG);
- Czech Republic (system LS);
- Hungary (system EVM);
- Slovakia (system LS);
- Italy (BACC);
- France (TVM, mainly on high-speed network)
In such a case, we assume the system will be probably replaced by ETCS L2. Additional
costs for GSM-R data transmission (+5 to +10 k€/single track.km in comparison to GSM-R
voice only) versus benefits of having no signals (about 10 to 20 k€/signal - with an average of
one lineside signal per single track.km) will balance each other. Therefore, we also assume
similar investment costs for these types of trackside systems. Lower maintenance costs of
ETCS L2 (due to less equipment within the track) could further lead to lower life cycle costs
in case of ETCS L2.
11.6.1.8.4 ETCS L2: UIC-benchmarking study (last updated in 2011) provides the most recent
data quantifying ETCS life cycle costs. This report indicates that observed ETCS
L2 life cycle costs are higher than ETCS L1 (or existing legacy systems) life cycle
costs. During a workshop (held on 05/09/2012 at EIM), most EIM-participants
expect that in future ETCS L2 trackside life cycle costs will decrease due to the
lower density of trackside equipment under certain conditions (no overlay of line
side signalling system).
11.6.1.8.5 ETCS L3: the long term potential benefits of ETCS L3 (not needing train detection
systems) can further lower the trackside life cycle costs of ETCS. The migration
models should include these additional benefits at IM-side.
11.6.1.9 Input data 1 - on-board cost data
11.6.1.9.1 Following on-board cost data concerns new vehicles. These are based on answers
received via the questionnaire.
11.6.1.9.2 Definition of simple legacy system: train protection system with warning or
warning-stop functionality. A limited number of bits or statuses are transferred
from trackside to on-board equipment.
Definition of complex legacy system: train protection system with discrete
supervision, continuous supervision or CAB-signalling functionality.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 64/78
11.6.1.9.3 Model - on-board cost data for new vehicles (see also (3)):
System Mean investment cost Sensitivity (triangular
distribution)
Simple legacy
system
10 k€/on-board unit +/- 5k€
Complex legacy
system
100 k€/on-board unit +/- 50k€
ETCS system 200 k€/on-board unit +/- 50k€
ETCS and legacy
system
210 k€/on-board unit (simple
legacy system)s
300 k€/on-board unit
(complex legacy system)
Sum of investment cost
of ETCS and investment
cost of legacy system
Table 1: input data for on-board investment cost used in basic model
Input data: Simple Class B –systemt
s The development cost of the integration of the Class B and ETCS –system is not included as this development
is expected to take place in all scenarios (for vehicles running on TEN-network or as part of migration scenario);
t $ in the figures must always be replaced by € (shortcoming of the software used)
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 65/78
Input data: Complex Class B –system
Input data: ETCS –system
11.6.1.10 Input data 2 – percentage of fleet running solely off-TEN, solely on-TEN
and both on-TEN and off-TEN
11.6.1.10.1 Trains running solely off-TEN are derived from a previous report (see Annex
2) in which data is mentioned for vehicles running solely off-TEN.
11.6.1.10.2 Assumption: as off-TEN represents 60% and TEN-network represents 40% of
the network (see Annex 2), a similar reasoning could be used to estimate the
percentage of trains running solely on TEN-network. Taken into account that TEN-
network are more centralised lines, while off-TEN network are more on the outside
connections of the integrated TEN-network, we estimate the percentage of trains
running solely TEN at 20% of the total fleet. This value is estimated on the high
side in order not to overestimate long term benefits. However, this parameter as a
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 66/78
lower sensitivity in the overall conclusion as the most influential parameter is the
percentage of trains running both on-TEN and off-TEN (a 50% decrease of the
percentage solely on-TEN (e.g. 20% to 10%) leads to 14% increase of long term
benefits (e.g. 70% to 80%)).
11.6.1.10.3 Percentage of fleet running solely off-TEN, solely on-TEN and both on-TEN
and off-TEN:
Fleet running... Percentage of
trains
Sensitivity
Solely off-TEN 10% +/- 100%
Solely on-TEN 20% +/- 100%
Both on-TEN
and off-TEN
70%
=100%
- fleet running solely off-TEN
- fleet running solely on-TEN
Table 2: input data for fleet running solely off-TEN, solely
on-TEN and both on- TEN and off-TEN
Input data: percentage of fleet running solely off-TEN
Input data: percentage of fleet running solely on-TEN
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 67/78
11.6.1.11 Assumption: we assume that for vehicles running off-TEN and on TEN only
one additional legacy system has to be taken into account.
11.6.1.12 Training: one single system will lead to diminished risks and training
requirements for train drivers due to a reduction in the number of legacy systems and
fewer transitions between systems.
11.6.1.13 Output data: following scenarios will be simulated using the above data
- Benefit Cost ratio in scenario of simple legacy systems
- Sensitivity analysis in scenario of simple legacy systems in function of cost
price of Class B- on-board system;
- Sensitivity analysis in scenario of simple legacy systems in function of
percentage of trains running solely on-TEN;
- Sensitivity analysis (using Monte Carlo simulation) based on triangular
distribution model for all parameters above.
- Benefit Cost ratio in scenario of complex legacy systems
- Sensitivity analysis in scenario of complex legacy systems in function of cost
price of Class B- on-board system;
- Sensitivity analysis in scenario of complex legacy systems in function of
percentage of trains running solely on-TEN;
- Sensitivity analysis (using Monte Carlo simulation) based on triangular
distribution model for all parameters above.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 68/78
11.6.1.14 Analysis 1: Legacy system with “simple” train protection functionality
(warning; warning-stop)
11.6.1.15 Standard analysis: using the input data from the previous section, long term
benefits do not exceed long term costs in case of “simple” train protection systems.
In such case, benefit-cost ratio is 0.37.
11.6.1.16 Sensitivity analysis - parameter ‘Legacy on-board cost’: long term benefits
equal long term costs in case legacy on-board cost equals 25 k€.
11.6.1.17 Sensitivity analysis – integration cost: one of the elements is the integration
cost of ETCS + legacy on-board cost. In the case of simple Class B-systems, the
mere addition of investment cost of both systems leads to an underestimation of
costs. Analysis shows that an integration cost of 17k€ (per vehicle, integrating a
share of type testing and approval costs) leads to long term benefits exceeding long
term cost. This parameter should therefore be verified.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 69/78
11.6.1.18 Sensitivity analysis - parameter ‘Percentage of vehicles running only off-
TEN’: long term benefits equals long term costs if percentage of vehicles running
only off-TEN decreases to 4%. This shows the importance of integration between
off-TEN and TEN-network. The higher the percentage of vehicles running both on
TEN and off-TEN, the more importance to have one single target.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 70/78
11.6.1.19 Output from simulation model:
11.6.1.19.1 Model using Risk Solver Platform software:
11.6.1.19.2 Output: in only in 8.6% of cases within the simulation model, long-term
benefits exceed long-term costs.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 71/78
11.6.1.19.3 Sensitivity: main influencing parameter is related to the percentage of vehicles
running solely off-TEN (and not the price level of the simple legacy system).
11.6.1.20 Provisional conclusion 1: in case of simple train protection systems, the
percentage of vehicles running only off-TEN, will mainly determine if long term
benefits exceed long term costs. For low integrated off-TEN lines, simple legacy
systems can still be a more economically viable target than the ETCS-system. This
is under the condition that these simple legacy systems would further provide
sufficient performance and safety for the off-TEN lines.
11.6.1.21 Analysis 2: Legacy system with “complex” train protection functionality
(discrete speed supervision, continuous speed supervision or CAB-signalling)
11.6.1.22 Standard analysis: using the input data from the previous section, long term
benefits do exceed long term costs in case of “complex” train protection systems. In
such case, benefit-cost ratio is 7.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 72/78
11.6.1.23 Sensitivity analysis - parameter ‘legacy system on-board cost: long term
benefits equal long term costs in case legacy system on-board cost equals 25 k€u.
u 2 answers from the questionnaire mention cost prices for ‘complex’ on-board systems below
this value (system LS; EVM).
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 73/78
11.6.1.24 Sensitivity analysis - parameter ‘Percentage of vehicles running only on-TEN’:
long term benefits equals long term costs if percentage of vehicles running only on-
TEN increases to 80%. Such a high percentage of powered vehicles running only
on-TEN does not seem realistic.
11.6.1.25 Output from simulation model:
11.6.1.25.1 Model using Risk Solver Platform software:
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 74/78
11.6.1.25.2 Output: in 99.99% of cases of the simulation model, the long-term benefits
exceed long-term costs.
11.6.1.25.3 Sensitivity: main influencing parameter is related to the percentage of vehicles
running solely off-TEN (and not the price level of the complex legacy system).
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 75/78
11.6.1.26 Provisional conclusion: in case of complex train protection systems, long term
benefits exceed long term costs. Therefore, ETCS-systems are a more economic
viable solution as long term target than the complex legacy systems for the off-TEN
network. Migration costs have to be evaluated (at local level) to verify if these one-
time costs do not exceed the overall long term revenues.
11.6.1.27 Summary of long term benefits and costs related to ETCS
11.6.1.27.1 The analysis showed that long term benefits of scope extension exceed long
term costs for complex legacy systems, while this is not the case for simple legacy
systems. An estimation of the number of trackside systems and units equipped with
these systems can be found in (2):
Roughly, 25 to 35% of vehicles are equipped with simple train protection
functionality, while 65 to 75% of vehicles are equipped with complex train
protection functionality.
11.6.1.27.2 During the EIM-workshop of 05th
September 2012, it was confirmed that
ETCS provides sufficient economically viable variants (e.g. ETCS Regional (L3),
Limited Supervision, Level 2) to cover the requirements of the different
configurations of the off-TEN network. This is also confirmed by the answers from
the questionnaire on following question (“Are there any technical aspects in
chapter 4 of the current CCS TSI, related to ETCS specifications, which would
require modifications for the applicability of ETCS outside the TEN-network?”).
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 76/78
11.6.1.27.3 Opportunity: scale effects of ETCS and obsolescence effects of legacy system
will further reduce the current cost differences between legacy on-board systems
and ETCS systems used. Recently signed contracts also seem to demonstrate the
importance of scale effects. These effects will impact parameter P2. Therefore, it is
recommended to further monitor the cost evolution.
11.6.1.27.4 Risk: scope extension of CCS for the off-TEN network could even have a
negative impact (cost increase of ETCS-implementations) as this could provoke an
imbalance between demand and supply of ETCS signalling resources.
11.6.1.27.5 Risk: this analysis is based on the assumption that the TEN-network (and fleet
running on TEN and off TEN) will be equipped with ERTMS;
11.6.1.27.6 Risk: this global analysis could however hide some local particularities.
Looking to following table, the percentage of fleet running solely off-TEN is
particularly high (>20% for locomotives or vehicles in DMUs &EMUs) for
following Member States: Czech Republic, Germany and Slovakia.
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 77/78
11.7 ANNEX 7: QUALITATIVE ANALYSIS OF MIGRATION
11.7.1.1 Migration costs depend on local situations and these one-time costs should be
evaluated in relation with the long term benefits and costs.
11.7.1.2 Some elements play a role in the migration strategy which are not included within
the economic model or which set certain maximum values on parameters within the
model (e.g. as maximum retrofit rate). Examples of such elements are:
11.7.1.2.1 Insufficient availability of investment funds can lead to the exclusion of fast
migration scenarios.
11.7.1.2.2 The time needed to retrofit a vehicle (out of service time) can lead to a constraint
on the maximum migration rate of rolling stock in order to be able to execute the
required traffic volumes.
11.7.1.2.3 Safety incidents/accidents could lead to the adoption of fast migration scenarios or
possible ETCS changes.
11.7.1.3 Migration costs for each individual network are not included within the report as the
above analysis of long term benefits and costs is sufficient to state that the overall
economic outcome will not be positive in some cases. Therefore, the conclusion for
ETCS will remain the same as for the TEN-network (but outside corridors), meaning
not yet imposing ETCS on all lines.
11.7.1.4 Opportunity: There might be cases where the local CBA is positive for IMs (due to
significant savings at trackside) and negative for RUs (due to high migration costs
for retrofitting). In such cases, an appropriate compensation scheme should be
applied in order to achieve positive CBA both at RU and at IM-side when
implementing ETCS.
11.7.1.5 Following elements demonstrate why migration scenarios can be different between
the networks.
11.7.1.6 Rolling stock / trackside migration: the end target (being e.g. ETCS L2 without line
side signalling- scenario 1 or ETCS L1/Limited supervision-scenario 2) can have an
impact on the type of migration scenario. Rolling stock migration (RST equipped
with ETCS+STMs/legacy system) will have a more positive case when the end target
is set to be without line side signalling (mostly the case in scenario 1) in comparison
ERA ECONOMIC EVALUATION UNIT
140514 ERA-EE- Report CCS TSI - Scope extension - v4 7 PAGE 78/78
to an end target with line side signalling (scenario 2). This is due to the fact that in
the first scenario renewing/upgrading and maintaining the line side signalling system
(at trackside) can be avoided in case of rolling stock migration, while in the second
scenario, renewing/upgrading and maintaining the line side signalling system (at
trackside) will not be avoided by rolling stock migration.
11.7.1.7 Rolling stock / trackside migration: the ratio of number of signals (depending on the
network configuration) versus the number of rolling stock to be migrated can have an
impact on the migration scenario.
11.7.1.8 Fast/slow migration: the optimal migration scenario depends also on the age of the
existing legacy systems at trackside and vehicle side. In case of ‘old’ legacy systems
reaching their end of lifetime, the residual value is low and migration (based on the
renewal rate) can be more easily performed. In such scenario, fast migration will be
less costly than in a scenario where legacy systems have a high remaining lifetime
(more retrofit costs).
11.7.1.9 Fast/slow migration: during the migration period, there is a need for additional
human resources. A shorter migration period leads to a higher peak in human
resources (leading to higher training or salary costs) which will lead to additional
migration costs in case of fast migration scenarios. Following examples demonstrate
the existence of differences in migration strategies:
11.7.1.9.1 A fast rolling stock migration scenario, meaning rolling stock gets ETCS
+STMs/legacy systems, and when all rolling stock is retrofitted, trackside gets
converted to ETCS without overlay. This scenario will be implemented by the
major RUs currently operating in DK and NL (still under discussion);
11.7.1.9.2 Independent migration scenarios are implemented in Belgium and France.