Economic Evaluation of Investment Projects Under...
Transcript of Economic Evaluation of Investment Projects Under...
1
Ref. No: SCI-1801-1599
Economic Evaluation of Investment Projects Under
Uncertainty: A Probability Theory Perspective
Hadi Mokhtari *, Saba Kiani, Seyed Saman Tahmasebpoor
Department of Industrial Engineering, Faculty of Engineering, University of Kashan, Kashan, Iran Hadi Mokhtari
Postal code: 8731753153, Tel.: +98 031 55912476, email: [email protected]
Saba Kiani
Postal code: 8731753153, Tel.: +98 031 55912476, email: [email protected]
Seyed Saman Tahmasebpoor Postal code: 8731753153, Tel.: +98 031 55912476, email: [email protected]
Abstract. In the current competitive economy, the investors are facing
increased uncertainty while evaluating new investment projects. This
uncertainty caused from existence of insufficient information, oscillating
markets, unstable economic conditions, obsolescence of technology and so on,
and hence uncertainty is inevitable in reality. In such conditions, the
deterministic models, while easy to use, do not perfectly represent the real
situations and might lead to misleading decisions. When the cash flows for an
uncertain investment project, over a number of future periods, are discounted
using the traditional deterministic approaches, it may not provide investors
with an accurate estimation of the project value. Therefore, this paper utilizes
2
the probability theory tools to derive closed-form probability distribution
function (PDF) and related expressions of the net present worth (NPW), as a
useful and frequently used criterion, for cost-benefit evaluation of projects.
The random cash flows follow normal, uniform or exponential distributions in
our analysis. The probability distribution function of the NPW is an important
tool that helps investors to accurately estimate the probability of being
economic for projects, and hence, it is important tool for investment decision-
making under uncertainty.
Keywords: Investment Projects; Economic Evaluation; Net Present Worth;
Probability Distributions; Probability Theory
1. Introduction
Appropriate evaluation and selection of investment projects is the most important
financial factor for success of investors and is vital to be economic in current
competitive environment [1]. The investors aim to not only prevent projects'
failures, but also select the best alternatives among available investment projects
so as to gain more benefits and reach better results. In the economic evaluation of
investment projects, the important parameters such as prices and quantities have
been treated so far based on the deterministic and pre-known values. The values of
these parameters used in the analysis and the resulting outcomes are single values
with perfect certainty. An investor expects to achieve positive results from an
investment projects. Under deterministic settings, these results can be determined
unambiguously. However, under uncertainty in the real-world conditions, there
are usually lack of reliable information [2], and most investment parameters are
uncertain [3]. The future outcomes have uncertainties especially for long-term
planning horizons and variability in the value of future items is inevitable. In real-
world, uncertainty is always present and, in some especial cases, due to lack of
scientific information and existence of technological innovation, it is more difficult
to make reliable decisions. For example, the new products supplied to market
might not gain sales at the expected levels; the profits expected from international
investments might not be gained satisfactorily; or an investment might have
unexpectedly delay to a long time to achieve efficiency. The source of this
3
uncertainty might be the behaviors of customers, suppliers or employees, or
technical problems in processes. Due to complex and fast-changing factors in
decision making, many investment decisions contain remarkable uncertainty and,
hence, suffer high risks in outcomes. Therefore, these uncertainties should be take
into account in economic evaluation of investment projects, in order to ensure
reliable decisions and long-term achievements.
The cash flow analysis has been utilized to assess the differences among
investment projects and to provide a basis for project evaluation. In order to
financially evaluate investment projects, it is needed to assess beneficiary due to
their cash flows. In evaluation of investment projects, the cash flow analysis is
carried out by the classic methods like net present worth (NPW), net future worth
(NFW), net equivalent uniform annual (NEUA), internal rate of return
(ROR/IRR), payback period (PB) and etc. Among them, the NPW is one of the
most useful one for finding the economic desirability of the projects. The
appropriate criterion for monitoring and evaluating such projects is NPW [4-5]. It
is considered to be a major tool for analyzing the cash flow of projects during a
long period [6]. It is the most common methods used by banks and large-sized
organizations to compare projects select most economic among them. To perform
such analysis, the NPW of an investment project is defined as sum of present
income cash flow minus present cost cash flow during the project's time horizon.
Hence, NPW criterion can be calculated via:
1 1
nt t
t
t
R CNPW
i
(1)
where tr and tc indicate the value of income and cost during the period t
respectively, i indicates the discount rate (minimum attractive rate of return), and
n indicates the project's planning horizon. If the value of NPW is equal or bigger
than zero, the project will be economic and acceptable, and if it is smaller than
zero, the project will be uneconomic and hence unacceptable. To incorporate NPW
in uncertain environment, different approaches have been used in literature. The
most used methods are based on soft computing approaches like Fuzzy sets and
simulation [2]. The fuzzy mathematical optimization [7], the fuzzy data
envelopment analysis [8], and the fuzzy AHP and ANP [9] have attracted most
attentions. Moreover, different hybrid approaches [9-10] tries to combine these
methods to reach better results. As another frequently used approach, the
4
simulation has been utilized in different ways. Some researchers have used
simulation tool incorporated with the transformation of fuzzy numbers to
probability distributions [4], others utilized Monte-Carlo simulation to achieve
sample sizes [11] and others have used fuzzy simulation directly [12]. Naimi
Sadigh et al., [13] proposed a hybrid approach based on particle swarm
optimization and Hopfield neural network to a cardinality constrained portfolio
optimization problem. Salmasnia et al., [14] proposed a robust approach to
project evaluation with time, cost, and quality considerations. Liu and Wu [15]
presented a portfolio evaluation and optimization in electricity markets. Afshar-
Nadjafi et al., [16] proposed a generalized resource investment problem with
discounted cash flows and progress payment. Rębiasz and Macioł [17] employed a
multi-criteria decision making methods and a fuzzy rule-based approach for
investment projects evaluation. Dai et al., [18] discussed a model for renewable
energy investment project evaluation based on improved real option approach.
Kilic and Kaya [19] investigated a decision making methodology for an investment
project evaluation by based on type-II fuzzy sets. Kirkwood et al. [20] evaluated
uncertainty in an integrated maintenance of the UK rail industry by net present
value calculations. Tabrizi et al., [21] a novel project portfolio selection by using a
fuzzy DEMATEL and goal programming. Fathallahi and Naja [22] designed a
hybrid genetic algorithm to maximize net present value of fuzzy project cash flows
in resource-constrained project scheduling problem. In addition, Dutta and
Ashtekar [23] considered a system dynamics simulation tool for project evaluation
issue. Etemadi, et al., [24] A goal programming capital budgeting model under
uncertainty in construction industry. Mohagheghi et al., [25] suggested a new
interval type-II fuzzy optimization approach for R&D project evaluation and
portfolio selection. Awasthi and Omrani [26] developed a scenario simulation
approach for sustainable project evaluation based on fuzzy concepts.
All above soft methods can be applied if essential assumptions such as existence of
large sample and data accuracy are assured. However, another useful approach to
handle uncertainty in economic evaluation is estimating some prediction functions
like probability distribution function (PDF). It is an analytical approach, in
contrast to soft approaches, to evaluate investment projects based on the
probability and statistical theory principles. In this way, the probability
distribution functions (PDFs) for estimation and prediction of economic
5
desirability MPW can be derived [27]. In this paper, we propose to derive the
probability distribution function of economic desirability NPW for two classes of
investment projects: (i) one-period cash flows (three cases), and (ii) two-period
cash flows (six cases). In deterministic environment, under certainty, a project is
evaluated as "economic" or "uneconomic". However, in stochastic environment,
under uncertainty, we can just talk about the "probability of being economic" or "
probability of being uneconomic" which can be calculated using the analytical PDF
of performance criterion NPW. In deterministic economic evaluation problems,
the investor has his/her own minimum attractive rate of return (MARR) which is
used in his/her evaluations. In our stochastic problems, we calculate the
probability of being economic for an uncertain cash flow. When this parameter is
calculated, the investor compares this parameter with his/her minimum
probability of being economic. If the minimum probability of being economic is
satisfied, the project is selected as economic, and otherwise, it is rejected. Hence,
this paper helps the investor to achieve the analytical function for estimating the
economic performance of investment projects. The probability theory tools like
moment generating function (MGF) and transformation method will be used, to
derive the analytical and closed-form function for probability distribution function
(PDF) of the net present worth (NPW) in investment projects. This analysis will be
performed for three classes of investment projects: (i) one-period cash flows, (ii)
two-period cash flows and (iii) multiple period cash flows, all with normal,
exponential and uniform distributions of cash flows. The probability distribution
functions of NPW will be derived for each cases separately, which can helps
investors to accurately estimate the economic desirability of investment projects
under uncertain cash flows. Since the cash flows follow continuous numbers, we
should consider continuous random distribution functions. For this purpose, we
consider normal, exponential and uniform distributions as well-known and most
frequently used continuous distributions for addressing random cash flows.
The rest of this paper is organized as follows. Section 2 provides one-period cash
flow analysis, while Section 3 discussed two-period cash flow analysis and Section
4 investigated a multiple-period project cash flow under uncertainty. In Sections
2-4, the probability distribution functions are derived for NPW in three
distributions, i.e., Normal, Exponential and Uniform, separately. Moreover, some
lemmas are proved to address the special cases of PDFs. Section 5 presents the
6
analysis and simulation results to evaluate the performance of PDFs derived and
calculate the probability of being economic for case examples in different
situations. Finally, Section 6 concludes the paper and suggests some directions for
future studies.
2. One-Period Cash Flow Analysis
This section introduces and investigates an investment problem consisting of a
one-period project with an initial cost 0A and an income at the end of the period 1 A
. The value of income 1A is usually bigger than that of cost 0A , but at continue, our
analysis let 1A to be smaller than 0A . The economic desirability of this project
NPW is a function of both cash flows 1A and 0A , which can be calculated as
follows:
1
01
ANPW A
i
(2)
If the income 1A is random, the economic desirability NPW will be random too,
and the mean and the variance of economic desirability NPW can be calculated as
follows:
1 1
2
0 2,
1 1
A AE NPW A Var NPW
i i
(3)
where1
A and 1
2
A indicate, respectively, the mean and the variance of the random
income 1A .
2.1. Fixed Cost 0A and Variable Income 1 A with Normal Distribution
In this case, by taking into account the assumptions 2
0 1 1 10, ~ , A A Normal , it
can be concluded that the economic desirability of project NPW is also a random
variable, with mean and variance as follows:
2
1 10 2
, 1 1
E NPW A Var NPWi i
(4)
7
So according to the normal distribution, probability distribution function ( PDF )
of income 1 A can be calculated as follows:
1
2
1 1
1 1 2
11
1:
22A
aPDF A f a EXP
(5)
And also its moment generating function ( MGF ) can be calculated as follows:
1
22
1 1 12
A
tMGF t E EXP tA EXP t
(6)
By considering the fact that the economic desirability of this project NPW is a
function of variable 1 A , the moment generating function of NPW can be therefore
calculated as follows:
1
01
NPW AA
i
MGF t MGF t
(7)
According to the knowledge of probability theory, it has been proved for one
random variable like Y and two fixed numbers like a and b that:
.aY b Y
tMGF t EXP bt MGF
a
(8)
Therefore, by using the above equation, moment generating function of economic
desirability of this project NPWMGF t is obtained as follows:
10 .
1NPW A
tMGF t EXP A t MGF
i
(9)
By substituting the moment generating function of income 1A in the above
equation, the NPWMGF t can be re-written as follows:
22
1 10
1 2 1NPW
tMGF t EXP t A
i i
(10)
By comparing the above NPWMGF t to the moment generating function of the
normal distribution, and by using the fact that moment generating function is
unique for every random variable, it can be concluded that:
2
1 10~ ,
1 1NPW Normal A
i i
(11)
8
Therefore, the probability distribution function of the economic desirability of this
project NPW is estimated as follows:
2
1 0
2
11
1 11:
22NPW
v i A iiPDF NPW f v EXP
(12)
The importance of this function is that it can help the investors to estimate the
economic desirability of such projects by calculating the probability of being
economic. When the minimum attractive rate of return (MARR) of investor is i ,
this probability can be calculated as follows:
0 1
1
1( 0 | ) 1
A iP NPW i
(13)
where . indicates the cumulative distribution function (CDF ) of the standard
normal distribution. Obviously, the projects with higher value of ( 0 | )P NPW i
are more economic and preferable.
2.2. Fixed Cost 0 A and Variable Income 1 A with Exponential
Distribution
In this case, by taking into account the assumptions 0 1 10, ~ A A EXP , the mean
and the variance of income 1A are 1 1E A and 2
1 1Var A , and consequently
the mean and the variance of the economic desirability of project NPW can be
calculated as follows:
2
1 10 2
, 1 1
E NPW A Var NPWi i
(14)
In addition, the probability distribution function of the income 1A , according to the
probability distribution function of the exponential random variable, is obtained
as follows:
1
11 1
1 1
1: A
aPDF A f a EXP
(15)
And the moment generating function of the income 1A is achieved as follows:
9
1 1
1
1
1AMGF t E EXP tA
t
(16)
By considering the fact that the economic desirability of the project NPW is a
function of random variable 1A , so by using the equation (9), moment generating
function of the economic desirability NPW can be derived as follows:
0
1
1
1NPW
iMGF t EXP A t
i t
(17)
Since this function does not adopt to any of the known random variables, so it can
be understood that the economic desirability of such project does not have a
standard pattern. But for the purpose of economic evaluation, we are looking for
this unknown pattern. So we use another probability theory analysis, i.e.,
transformation method in sequel [28]. To adopt this method, the reverse function
of economic desirability 1NPW is calculated as follows:
1
1 0: 1NPW A NPW A i (18)
And also derivative of the reverse function is calculated as '
1 1NPW i . So
according to the transformation method, the probability distribution function of
the economic desirability of project can be extracted as follows:
1
'1 1: .NPW APDF NPW f v f NPW NPW (19)
After the mathematical simplification, the above probability distribution function
NPWf v can be re-written in its final form as follows:
0
1 1
11: NPW
v A iiPDF NPW f v EXP
(20)
According to this, it can be concluded that if the income 1A has its least amount
which is zero, economic desirability of project NPW will be in its least amount
which is – 0A . It means that the range of NPW variations is as follows:
0A NPW (21)
Therefore, the condition of being economic for such a project, when investor have
a particular minimum attractive rate of return i , can be calculated as follows:
10
0
( 0 | ) NPWP NPW i f v dv
(22)
This probability is calculated and re-written as follows:
0
1
1( 0 | )
A iP NPW i EXP
(23)
By using the above equation, investors can easily predict the economic desirability
of such projects and take the appropriate economic decision.
2.3. Fixed Cost 0A and Variable Income 1A with Uniform Distribution
In this case, it has been assumed that 0 1 1 1 0, ~ , A A Uniform and, then the mean
and the variance of income 1A can be calculated as follow:
2
1 11 11 1,
2 12E A Var A
(24)
Therefore, the mean and the variance of the economic desirability of project NPW
is achieved as follows:
2
1 1 1 10
1 1,
2 1 12 1E NPW A Var NPW
i i
(25)
Moreover, the probability distribution function of the income 1A can be attained as
follows:
11 1 1 1 1
1 1
1: , APDF A f a a
(26)
And the moment generating function of the income 1A can be computed by:
1
1 1
1
1 1
A
EXP t EXP tMGF t E EXP tA
t
(27)
So, by using the equation (9), the moment generating function of the economic
desirability of the project NPW is gained as:
1 10 0
1 1
1 1
1 1
NPW
EXP t A EXP t Ai i
MGF t
ti i
(28)
11
By comparing the above NPWMGF t to the moment generating function of the
uniform distribution, and by considering the fact that the moment generating
function is unique for every random variable, it is revealed that:
1 10 0 ~ ,
1 1NPW Uniform A A
i i
(29)
and the probability distribution function of the economic desirability of this
project is estimated as follows:
1 10 0
1 1
1: ,
1 1NPW
iPDF NPW f v A v A
i i
(30)
Consequently, the probability of being economic for such projects, when investor
have a particular maximum attractive rate of return i , is calculated as follows:
0
( 0 | ) NPWP NPW i f v dv
(31)
This probability can be calculated and re-written as follows:
1 0
1 1
1( 0 | )
A iP NPW i
(32)
Further analysis of above equation reveals that it is not valid for two special cases
and it requires more investigation. For this purpose, two lemmas are presented
and discussed in sequel.
Lemma 1: In a one-period project with a fixed cost 0A and a variable income 1A
which follows uniform distribution 1 1 1 ~ , A Uniform , if 1 0 1A i , then we can
conclude that this project is certainly uneconomic.
Proof: If the assumption of this lemma is true, it can be concluded that
10 0
1A
i
and by using the fact 1 1 , it yields that 1
0 01
Ai
. So, both the
upper bound and the lower bound of NPW are negative and there is no chance for
the economic viability of this project. We can represent the result of this lemma in
mathematical form as given below:
1 0( 0 | ) 0 if 1P NPW i A i (33)
12
Lemma 2: In a one-period project with a fixed cost 0A and a variable income 1A
which follows uniform distribution 1 1 1 ~ , ,A Uniform if 1 0 1 ,A i then we can
conclude that the project is certainly economic.
Proof: If the assumption of this lemma is true, it can be concluded that
10 0
1A
i
and by using the fact 1 1 , it yields that 1
0 01
Ai
. So both the
upper bound and the lower bound of the NPW are positive and the economic this
project is economic certainly. It means:
1 0( 0 | ) 1 if 1P NPW i A i (34)
So according to both Lemmas 1 and 2, the probability of being economic for such
projects is re-written in general form as follows:
( 0 | )P NPW i (35)
1 0
1 0
1 0 1 0
1 1
1 0
0 1
1 1 & 1
1 1
if A i
A iif A i A i
if A i
By using the above equation, the economic desirability of such project can be
simply estimated.
The aim of this section was to determine the probability of being economic for
investment projects with one-period cash flow through deriving the analytical
equation of the NPW distribution function. For this purpose, three cases were
analyzed. These cases are applicable in reality where the cost parameter 0A was a
fixed positive number and income 1A was a random variable with three distinct
cases: (i) normal, (ii) exponential, and (iii) uniform distributions. For all of cases,
analytical PDF of NPW were derived mathematically, which are useful tools for
investors in evaluation of uncertain projects over one period cash flow.
3. Two-Period Cash Flow Analysis
13
This section investigates an investment problem consisting of a two-period project
with an initial cost 0A , an income at the end of first period 1A , and another income
at the end of second period 2A . In this project, the economic desirability NPW is a
function of 0 A , 1A and 2A cash flows, which can be calculated as follows:
1 2
0 21 1
A ANPW A
i i
(36)
By taking into account the assumptions that incomes 1A and 2A are random and
independent variables, the economic desirability NPW will be therefore random
with the mean and the variance as follows:
1 2 1 1
2 2
0 2 2 4,
1 1 1 1
A A A AE NPW A Var NPW
i i i i
(37)
where 1A and
1
2
A indicate the mean and variance of first random income 1A
respectively, and 2A and
1
2
A indicate the mean and variance of second random
income 2A . The aim is to determine the economic desirability of such project
through the determination of analytical equation for the probability distribution
function of NPW. To this end, six cases are analyzed in sequel. In all of these cases,
initial cost 0A is a fixed positive number and incomes 1A or 2 A are random
variables with (i) normal, (ii) exponential, and (iii) uniform distributions.
3.1. Fixed Cost 0A , Fixed Income 1 A , and Variable Income 2 A with
Normal Distribution
In this case, by considering the assumptions 0 10, 0, A A and 2
2 2 2~ , A Normal ,
it can be concluded that economic desirability of such project NPW is also
variable, and then the mean and variance of NPW can be calculated as follows:
2
1 2 20 2 4
, 1 1 1
AE NPW A Var NPW
i i i
(38)
Moreover, the moment generating function of income 2A can be calculated as:
2
22
2 2 22
A
tMGF t E EXP tA EXP t
(39)
14
and the moment generating function of NPW is a function of variable income 2A as
given below:
1 2
0 21 1
NPWA A
Ai i
MGF t MGF t
(40)
Therefore, by utilizing the probability theory principles, NPWMGF t can be
calculated as follows:
2
10 2
.1 1
NPW A
A t tMGF t EXP A t MGF
i i
(41)
which can be re-written by mathematical simplification as:
22
1 2 20 2 2
1 21 1NPW
A tMGF t EXP t A
i i i
(42)
So by comparing this function to the moment generating function of the normal
distribution, it can be understood that:
2
1 2 20 2 2
~ , 1 1 1
ANPW Normal A
i i i
(43)
Consequently, the probability of being economic for such projects with minimum
attractive rate of return i is calculated as follows:
2
0 1 2
2
1 1( 0 | ) 1
A i A iP NPW i
(44)
3.2. Fixed Cost 0A , Variable Income 1 A with Normal Distribution, and
Fixed Income 2 A
In this case, we have the assumptions 2
0 1 1 1 20, ~ , , 0A A Normal A and, as the
similar way we had at the previous part, it can be resulted that:
2
1 2 10 2
~ , 1 11
ANPW Normal A
i ii
(45)
15
Moreover, the probability of being economic for this project with minimum
attractive rate of return i can be estimated as follows:
20 1
1
11( 0 | ) 1
AA i
iP NPW i
(46)
3.3. Fixed Cost 0A , Fixed Income 1 A , and Variable Income 2 A with
Exponential Distribution
In this case, it is assumed that 0 1 2 20, 0, ~ A A A EXP , so according to this we
have:
2
1 2 20 2 4
, 1 1 1
AE NPW A Var NPW
i i i
(47)
In addition, according to the exponential distribution, moment generating
function of the income 2A can be calculated as follows:
2 2
2
1
1AMGF t E EXP tA
t
(48)
By taking into account the equation (9), the moment generating function of the
economic desirability of the project NPW can be computed as follows:
2
10 2
.1 1
NPW A
A tMGF t EXP A t MGF
i i
(49)
By using mathematical simplification, this function can be expressed as follows:
2
10 2
2
1.
1 1NPW
iA tMGF t EXP A t
i i t
(50)
Since the above function is not similar to any known moment generating
functions, it can be resulted that, in this case, the economic desirability of projects
NPW do not follow a standard known distribution. So, to reach the analytical
probability distribution function of NPW at this case, we use the transformation
method in sequel. For this purpose, the reverse function of NPW and its derivative
is derived as follows:
16
1 20 2
1 1
A ANPW A
i i
(51)
21 1
2 0: 11
ANPW A NPW A i
i
' 21 1NPW i
So according to the transformation method, the final form of probability
distribution function for the economic desirability NPW can be obtained as:
22
0 1
2 2
1 11: NPW
v A i A iiPDF NPW f v EXP
(52)
Since the value of the random income 2 A varies on interval 20 A , so the
economic desirability of such project NPW is also variable on following interval:
1
01
AA NPW
i
(53)
and the probability of being economic with minimum attractive rate of return i
can be calculated for such projects as follows:
0
( 0 | ) NPWP NPW i f v dv
(54)
By performing mathematical computations, this probability can be simplified as
follows:
2
1 0
2
1 1( 0 | )
A i A iP NPW i EXP
(55)
Additional investigation shows that the above equation is not valid in one special
case, which is expressed in Lemma 3.
Lemma 3: In a two-period project with fixed cost 0A , fixed income 1A and
variable income 2A which follows exponential distribution 2 2~ A EXP , if
1
0
1A
iA
, then we can conclude that the project is certainly economic.
17
Proof: If the assumption of this lemma is true, it can be understood that the lower
bound of the economic desirability of the project NPW is always nonnegative
1
0 01
AA
i
. So always 0NPW and then this project is certainly economic.
As further analysis of this lemma, it can be mentioned that if we have 1
0
1A
iA
it
means income 1A would be itself enough for the economic viability of the project
and the economic viability of the project is independent from the amount of
income 2A . By increasing the value of income 2A , economic desirability will
increase, but with decreasing that, the project do not quit from economic range at
all.
By using the result from lemma 3, the probability of being economic for such
project would be re-written as follows:
( 0 | )P NPW i (56)
2
1 0 1
2 0
1
0
1 1 1
1 1
A i A i AEXP if i
A
Aif i
A
By using above equation, investors can predict the economic desirability of such
two-period projects.
3.4. Fixed Cost 0A , Variable Income 1 A with Exponential Distribution,
and Fixed Income 2 A
In this case, it is assumed that 0 1 1 20, ~ , 0A A EXP A and so we have:
2
1 2 10 2 2
, 1 1 1
AE NPW A Var NPW
i i i
(57)
In this case, similar to the previous case, for using the transformation method, the
reverse function 1 NPW and its derivative can be derived as follows:
18
1 20 2
1 1
A ANPW A
i i
(58)
1 21 0 2
: 11
ANPW A NPW A i
i
'
1 1NPW i
So by adopting the transformation method, the probability distribution function of
the economic desirability NPW will be simplified in its final form as follows:
0 2
1 1
1 / 11: NPW
v A i A iiPDF NPW f v EXP
(59)
Since the income 1A varies on interval 10 A , the economic desirability NPW
varies on the following range:
2
0 21
AA NPW
i
(60)
Moreover, the probability of being economic with minimum attractive rate of
return i , can be calculated and simplified as follows:
0
( 0 | ) NPWP NPW i f v dv
(61)
2 0
1
/ 1 1A i A iEXP
However, additional analysis show that the above equation is not valid in one
special case which is expressed in Lemma 4.
Lemma 4: In a two-period project with fixed cost 0A , variable income 1A with
exponential distribution 1 1~ A EXP , and fixed income 2A , if 22
0
1A
iA
, we can
conclude that this project is certainly economic.
Proof: If the assumption of this lemma is true, it can be concluded that the lower
bound of the economic desirability NPW is always nonnegative
20 2
01
AA
i
.
So always 0NPW and the probability of being economic will be one. As more
19
analysis of the result of this lemma, it can also be mentioned that if we have
22
0
1A
iA
it means that the income 2A would be itself enough for the economic
viability of the project, and the economic viability of the project is independent
from the value of income 1A . In other words, with any increase at the value of 1A
the desirability will increase, but with its decrease, the project will not quit from
economic range at all.
By using the result from lemma 4, the probability of being economic of such
project is re-written as follows:
( 0 | )P NPW i (62)
22 0 2
1 0
22
0
/ 1 1 1
1 1
A i A i AEXP if i
A
Aif i
A
The above equation predicts the economic desirability of project and help the
investor for appropriate decision making.
3.5. Fixed Cost 0A , Fixed Income 1 A , and Variable Income 2 A with
Uniform Distribution
In this case, it is assumed that 0 1 2 2 20, 0, ~ , A A A Uniform , so the mean and
variance of economic desirability project NPW can be calculated as follows:
2
2 2 2 210 2 4
1, .
1 122 1 1
AE NPW A Var NPW
i i i
(63)
Furthermore, the moment generating function of the income 2A can be achieved as
follows:
2
2 2
2
2 2
A
EXP t EXP tMGF t E EXP tA
t
(64)
According to the equation (9), the moment generating function of the economic
desirability can be calculated and summarized as follows:
20
2
10 2
.1 1
NPW A
A tMGF t EXP A t MGF
i i
(65)
2 1 2 10 02 2
1 12 2
1 11 1
1 1
A AEXP t A EXP t A
i ii i
ti i
By comparing NPWMGF t to the moment generating function of the uniform
distribution, and by utilizing the fact that the moment generating function is
unique for every random variable, it can be realized that:
2 1 2 10 02 2
~ , 1 11 1
A ANPW Uniform A A
i ii i
(66)
and the probability distribution function of NPW can be estimated as follows:
2
2 2
1: , NPW
iPDF NPW f v
(67)
2 1 2 10 02 2
1 11 1
A AA v A
i ii i
So the probability of being economic for such projects, with a particular minimum
attractive rate of return i , is calculated as follows:
0
( 0 | ) NPWP NPW i f v dv
(68)
This probability can be computed and summarized as follows:
2
2 1 0
2 2
1 1( 0 | )
A i A iP NPW i
(69)
However, further analysis of above formula reveals that it is not valid in two
special cases. The following lemmas 5 and 6 discuss these cases analytically.
Lemma 5: In a two-period project with fixed cost 0A , fixed income 1A and
variable income 2A which follows uniform distribution 2 2 2~ , A Uniform , if
2
2 0 1 1 1A i A i , we can conclude that the project is certainly uneconomic.
21
Proof: If the assumption of this lemma is true, it can be understood that
2 1
020
11
AA
ii
, and by adopting the fact that 2 2 , it resulted that
2 1
02 0
11
AA
ii
. So both the upper bound and the lower bound of NPW are
negative and therefore there is no possibility for the economic viability of such
project. It means that:
2
2 0 1( 0 | ) 0 if 1 1P NPW i A i A i (70)
Lemma 6: In a two-period project with fixed cost 0A , fixed income 1A and
variable income 2A with uniform distribution 2 2 2 ~ , A Uniform , if
2
2 0 11 1A i A i , we can conclude the project is certainly economic.
Proof: If the assumption of this lemma is true, it can be understood that
2 1
020
11
AA
ii
, and by adopting the fact that 2 2 , it resulted that
2 1
02 0
11
AA
ii
. So both the upper bound and the lower bound of NPW are
positive and the project is certainly economic. It means:
2
2 0 1( 0 | ) 1 if 1 1P NPW i A i A i (71)
So according to the results of both lemmas 5 and 6, the probability of being
economic for such project is re-written as follows:
( 0 | )P NPW i (72)
2
2 0 1
2
2 22 1 0
2 0 1 2 0 1
2 2
2
2 0 1
0 if 1 1
1 1 if 1 1 & 1 1
1 if 1 1
A i A i
A i A iA i A i A i A i
A i A i
22
3.6. Fixed Cost 0A , Variable Income 1 A with Uniform Distribution, and
Fixed Income 2 A
In this case, it is assumed that 0 1 1 1 2 0, ~ , , 0 A A Uniform A , and so we have:
2
1 1 1 120 2 2
1, .
2 1 121 1
AE NPW A Var NPW
i i i
(73)
Similar to the previous case, the moment generating function of the economic
desirability can be calculated and summarized as follows:
1
20 2
.11
NPW A
A tMGF t EXP A t MGF
ii
(74)
2 1 2 10 02 2
1 1
1 11 1
1 1
A AEXP t A EXP t A
i ii i
ti i
By comparing NPWMGF t to the moment generating function of the uniform
distribution and by utilizing the fact that moment generating function is unique
for every random variable, it can be resulted that:
2 1 2 10 02 2
~ , 1 11 1
A ANPW Uniform A A
i ii i
(75)
So the probability distribution function of NPW can be estimated as follows:
1 1
1: , NPW
iPDF NPW f v
(76)
2 1 2 10 02 2
1 11 1
A AA v A
i ii i
Consequently, when we have an investor with a particular minimum attractive rate
of return i , the probability of being economic for such project can be calculated
and simplified as follows:
2 1 0
1 1
/ 1 1( 0 | )
A i A iP NPW i
(77)
However, further analysis of above formula shows that it is not valid for two
special cases which are presented in following lemmas 7 and 8.
23
Lemma 7: In a two-period project with fixed cost 0A , variable income 1 A with
uniform distribution 1 1 1~ , A Uniform , and fixed income 2A , if
1 0 2 1 / 1A i A i , we can conclude that this project is certainly uneconomic.
Proof: If the assumption of this lemma is true, it can be understood that
2 1
02 0
11
AA
ii
. By utilizing this result and the fact that 1 1 , we result that
2 1
020
11
AA
ii
.so both the upper bound and the lower bound of NPW are
negative and, therefore, there is no chance that this project would be economic.
This lemma can be represented in mathematical form as follows.
1 0 2( 0 | ) 0 if 1 / 1P NPW i A i A i (78)
Lemma 8: In a two-period project with fixed cost 0A , variable income 1A with
uniform distribution 1 1 1~ , A Uniform and fixed income 2 A , if
1 0 21 / 1A i A i , then we can conclude that this project is certainly
economic.
Proof: If the assumption of this lemma is true, it can be understood that
2 1
020
11
AA
ii
. Utilizing this result and the fact that 1 1 reveals that
2 1
020
11
AA
ii
. So both the upper bound and the lower bound of NPW are
positive and the project is certainly economic. It means:
1 0 2( 0 | ) 1 if 1 / 1P NPW i A i A i (79)
So according to results obtained from lemmas 7 and 8, the probability of being
economic for such project can be re-written as following form:
( 0 | )P NPW i (80)
24
1 0 2
2 1 0
1 0 2 1 0 2
1 1
1 0 2
0 if 1 / 1
/ 1 1 if 1 / 1 & 1 / 1
1 if 1 / 1
A i A i
A i A iA i A i A i A i
A i A i
The above equation can help the investor to simply estimate the economic
desirability of projects in this case.
The aim of this section was to determine the probability of being economic for
investment projects with two-period cash flow through deriving the analytical
equation of the NPW distribution function. For this purpose, six cases were
analyzed. These cases are applicable in reality where initial cost 0A is a fixed
positive number and incomes 1A or 2 A are random variables with (i) normal, (ii)
exponential, and (iii) uniform distributions. For all of cases, analytical PDF of
NPW were derived mathematically, which are useful tools for investors in
evaluation of uncertain projects over two periods cash flow.
4. Multiple-Period Cash Flow Analysis
This section extends the one and two periods problems discussed in previous
sections to a general case, and studies an investment problem consisting of a
multiple-period project with an initial cost 0A and incomes at the end of k th
period kA 1, 2, , k n . The cash flow of such project is shown in Figure 1.
>> Please insert Figure 1 here <<
In this project, the economic desirability NPW is a function of 0 A , 1A , 2A , ...,
nA cash flows, which can be calculated as follows:
0
1 1
n
k
k
k
ANPW A
i
(81)
By taking into account the assumptions that incomes 1A , 2A , ..., nA are
random and independent variables, the economic desirability NPW is
therefore random with the mean and the variance as follows:
25
2
0 2
1 1
, 1 1
k k
n nA A
k k
k k
E NPW A Var NPWi i
(82)
where kA and 2
kA denote the mean and variance of k th random income kA
respectively. The aim is to determine the economic desirability of such
project through the deriving of analytical equation for the probability
distribution function of NPW. To this end, three cases are analyzed in
sequel. In these cases, initial cost 0A is a fixed positive number and incomes
kA are random variables with (i) normal, (ii) exponential, and (iii) uniform
distributions.
4.1. Variable Income with Normal Distribution
In this case, by considering the assumptions 0 0, 0, kA A and for a special
period l , 2~ , l l lA Normal , it can be concluded that economic desirability of
such project NPW is also variable. By utilizing an approach similar to
previous sections, we conclude that:
2
0 0 2
1 1
~ , 1 1 1 1
l l
n nA Ak k
k l k l
k k k l
A ANPW A Normal A
i i i i
(83)
Consequently, the probability of being economic for such projects with
minimum attractive rate of return i is calculated as follows:
0 1 | 1
1( 0 | ) 1
l
l
nl kAk lk k l
A
AA i
iP NPW i
(84)
4.2. Variable Income with Exponential Distribution
26
In this case, by considering the assumptions 0 0, 0, kA A and for a special
period l , ~ l lA EXP , it can be concluded that economic desirability of such
project NPW is also variable. So we have:
0
1 |
, 1 1
n
l k
l k
k k l
AE NPW A
i i
2
2
1
l
lVar NPW
i
(85)
In this case, similar to the previous exponential cases, for using the
transformation method, the reverse function 1 NPW and its derivative can be
derived as follows:
0
1
1
n
k
k
k
ANPW A
i
(86)
1
0
1 |
: 11
nlk
l k
k k l
ANPW A NPW A i
i
'
1 1l
NPW i
So by adopting the transformation method, the probability distribution
function of the economic desirability NPW will be simplified in its final form
as follows:
0 1 | 1
11:
nl kk ll k k l
NPW
l l
Av A i
iiPDF NPW f v EXP
(87)
Since the income lA varies on interval 0 lA , the economic desirability
NPW varies on the following range:
0
1 | 1
n
k
k
k k l
AA NPW
i
(88)
27
Moreover, the probability of being economic with minimum attractive rate of
return i , can be calculated and simplified as follows:
0
( 0 | ) NPWP NPW i f v dv
(89)
01 |
11
n lkk lk k l
l
AA i
iEXP
However, additional analysis show that the above equation is not valid in
one special case which is expressed in Lemma 9.
Lemma 9: In a multiple-period project with fixed cost 0A , and incomes
1 2, , , nA A A which 1, 2, , lA l n is variable with exponential distribution
~ l lA EXP , and fixed income ( 1, 2, , | )kA k n k l , if
0
1 | 1
n
k
k
k k l
AA
i
, we
can conclude that this project is certainly economic.
Proof: If the assumption of this lemma is true, it can be concluded that the
lower bound of the economic desirability NPW is always nonnegative
0
1 |
01
n
k
k
k k l
AA
i
. So always 0NPW and the probability of being
economic will be one. As more analysis of the result of this lemma, it can also
be mentioned that if we have
0
1 | 1
n
k
k
k k l
AA
i
it means that the incomes
1 2 1 1, , , , , , l l nA A A A A would be enough for the economic viability of the
project, and the economic viability of the project is independent from the
value of income lA . In other words, with any increase at the value of lA the
28
desirability will increase, but with its decrease, the project will not quit from
economic range at all.
By using the result from lemma 9, the probability of being economic of such
project is re-written as follows:
( 0 | )P NPW i (90)
01 |
0
1 |
0
1 |
11
if 1
1 if 1
n lkk lk k l n
k
k
k k ll
n
k
k
k k l
AA i
i AEXP A
i
AA
i
The above equation predicts the economic desirability of project and help
the investor for appropriate decision making.
4.3. Variable Income with Uniform Distribution
In this case, by considering the assumptions 0 0, 0, kA A and for a special
period l , ~ ,l l lA Uniform , it can be concluded that economic desirability of
such project NPW is also variable. Therefore we have:
0
1 |
, 2 1 1
nl l k
l k
k k l
AE NPW A
i i
2
2
1 .
12 1
l l
lVar NPW
i
(91)
Furthermore, the moment generating function of the income 2A can be
achieved as follows:
l
l l
A l
l l
EXP t EXP tMGF t E EXP tA
t
(92)
29
Therefore the moment generating function of the economic desirability can
be calculated and summarized as follows:
0
1 |
.1 1
l
n
kNPW Ak l
k k l
A tMGF t EXP A t MGF
i i
(93)
0 01 | 1 |
1 1 1 1
1 1
n nk l k l
k l k lk k l k k l
l ll l
A AEXP t A EXP t A
i i i i
ti i
By comparing NPWMGF t to the moment generating function of the uniform
distribution and by utilizing the fact that moment generating function is
unique for every random variable, it can be resulted that:
0 0
1 | 1 |
~ , 1 1 1 1
n n
k l k l
k l k l
k k l k k l
A ANPW Uniform A A
i i i i
(94)
So the probability distribution function of NPW can be estimated as follows:
1
: ,
l
NPW
l l
iPDF NPW f v
(95)
0 0
1 | 1 |
1 1 1 1
n n
k l k l
k l k l
k k l k k l
A AA v A
i i i i
Consequently, when we have an investor with a particular minimum
attractive rate of return i , the probability of being economic for such project
can be calculated and simplified as follows:
01 | 1
1( 0 | )
n lklk lk k l
l l
AA i
iP NPW i
(96)
30
However, further analysis of above formula shows that it is not valid for two
special cases which are presented in following lemmas 10 and 11.
Lemma 10: In a multiple-period project with fixed cost 0A , and incomes
1 2, , , nA A A in which 1, 2, , lA l n is variable with uniform distribution
~ , l l lA Uniform , if
0
1 |
1 1
nl k
l k l
k k l
AA i
i
, we can conclude that this
project is certainly uneconomic.
Proof: If the assumption of this lemma is true, it can be understood that
0
1 |
01 1
n
k l
k l
k k l
AA
i i
. By utilizing this result and the fact that l l ,
we result that
0
1 |
01 1
n
k l
k l
k k l
AA
i i
. So both upper and lower bounds
of NPW are negative and, therefore, there is no chance that this project
would be economic. This lemma can be represented in mathematical form as
follows.
0
1 |
( 0 | ) 0 if 1 1
nl k
l k l
k k l
AP NPW i A i
i
(97)
Lemma 11: In a multiple-period project with fixed cost 0A , and incomes
1 2, , , nA A A in which 1, 2, , lA l n is variable with uniform distribution
~ , l l lA Uniform , if
0
1 |
1 1
nl k
l k l
k k l
AA i
i
, we can conclude that this
project is certainly economic.
Proof: If the assumption of this lemma is true, it can be understood that
0
1 |
01 1
n
k l
k l
k k l
AA
i i
. Utilizing this result and the fact that l l
31
reveals that
0
1 |
01 1
n
k l
k l
k k l
AA
i i
. So both upper and lower bounds of
NPW are positive and the project is certainly economic. It means:
0
1 |
( 0 | ) 1 if 1 1
nl k
l k l
k k l
AP NPW i A i
i
(98)
So according to results obtained from lemmas 10 and 11, the probability of
being economic for such project can be re-written as following form:
( 0 | )P NPW i (99)
1 0
1 |
0
1 |
0 0
1 | 1 |
0
1 |
0 if 1 1
11
if 1 , 11 1
1 if 11
nl k
k lk k l
nlk
lk ln n
k k l l lk kl lk l k l
k k l k k ll l
nl k
l k lk k l
AA i
i
AA i
i A AA i A i
i i
AA i
i
The above equation can help the investor to simply estimate the economic
desirability of projects in this case.
The aim of this section was to determine the probability of being economic for
investment projects with two-period cash flow through deriving the analytical
equation of the NPW distribution function. For this purpose, three cases were
analyzed. These cases are applicable in reality where initial cost 0A is a fixed
positive number and income at lth period lA is random variables with (i) normal,
(ii) exponential, and (iii) uniform distributions. For all of cases, analytical PDF of
32
NPW were derived mathematically, which are useful tools for investors in
evaluation of uncertain projects over multiple periods cash flow.
5. Analyses and Simulation Results
This section investigates the validity of proposed analytical equations derived in
previous sections through comparing them to the results of simulation approach.
For this purpose, numerical examples at each following sections are discussed
separately.
One-period cash flows:
Fixed cost 0 A and variable income 1A with normal distribution
Fixed cost 0 A and variable income 1A with exponential distribution
Fixed cost 0 A and variable income 1A with uniform distribution
Two-period cash flows:
Fixed cost 0 A , fixed income 1 A and variable income 2 A with normal
distribution
Fixed cost 0 A , variable income 1 A with normal distribution and fixed income
2 A
Fixed cost 0 A , fixed income 1 A and variable income 2 A with exponential
distribution
Fixed cost 0 A , variable income 1A with exponential distribution and fixed
income 2 A
Fixed cost 0 A , fixed income 1 A and variable income 2 A with exponential
distribution
Fixed cost 0 A , variable income 1 A with uniform distribution and fixed
income 2 A
5.1. Numerical Examples for One-Period Cash Flows
Fixed cost 0 A and variable income 1 A with normal distribution: Assume that in a
project with one-period cash flow, the initial cost is 0 125A , the variable income is
2
1 1 1 ~ 150, 2A Normal , and an investor with a minimum attractive rate of
return 0.1i is evaluating such project. In this case, the economic desirability of
33
such project will be a function of variable income as 1125 0.9091NPW A .
According to this, the mean and the variance of economic desirability of project
are calculated as 11.3636E NPW and 1.6529Var NPW . Using the analytical
equations derived in Section (3.1), NPW of this project is a random variable with
distribution ~ 11.3636,1 .6529NPW Normal and probability distribution function
PDF NPW as follows:
21.1 12.5
: 0.3103*4
NPW
vPDF NPW f v EXP
Figure 2 indicates the behavior of this analytical equation graphically, and Figure 3
depicts the simulation results. To achieve the simulation results, 200000 number of
random sample has simulated for income 1 A from distribution
2
1 1150, 2Normal and the values of economic desirability NPW are calculated
according to the observed values for 1 A , through 0 1 / 1NPW A A i . Finally
the frequency of simulated NPW values, called SimulatedNPW, are drawn in format
of histogram diagram. The pseudo code of simulation procedure is given below.
A1=zeros(200000,1); SimulatedNPW=zeros(200000,1); for j=1:200000 A1(j,1)=normrnd(mu1, sigma1); SimulatedNPW(j,1)=-A0+A1(j,1)/(1+i); end hist(SimulatedNPW,20)
As it is obvious, the pattern of simulation results in Figure 2 is completely
coincides to the analytical equation depicted in Figure 3. It confirms the
appropriateness of analytical equation derived in Section (3.1) from both aspects:
(i) the type of probability distribution and (ii) the mean and variance values.
>> Please insert Figure 2 here <<
>> Please insert Figure 3 here <<
Furthermore, the probability of being economic for such project by considering the
assumption of having a minimum attractive rate of return 0.1i can be achieved
as follows:
( 0 | 0.1 ) 1 8.8388 1P NPW i
34
Fixed cost 0 A and variable income 1 A with exponential distribution: Assume that
in a project with one-period cash flow, the initial cost is 0 125A , the variable
income is 1 1~ 135A EXP and an investor with a minimum attractive rate of
return 0.2i is evaluating such project. In this case, the economic desirability
function will be computed as 1 125 0.4545NPW A . According to this, the mean
and the variance of economic desirability of this project are calculated as
12.50E NPW and 12656Var NPW . Also according to the analytical equation
derived in Section (3.2), the NPW of this project is a random variable with
probability distribution function PDF NPW as follows:
: 0.0089* 0.0089 125NPWPDF NPW f v EXP v
where the variation range of NPW is 125 v . Figure 4 depicts the analytical
equation of NPWf v derived in Section (3.2), and Figure 5 indicates pattern of
simulation results for 200000 random samples. As it is obvious from figures, both
analytical and simulated diagrams are completely adopted to each other which
confirms the validity of our analytical equation. The pseudo code of simulation
procedure is shown below.
A1=zeros(200000,1); SimulatedNPW=zeros(200000,1); for j=1:200000 A1(j,1)=exprnd(Beta1); SimulatedNPW(j,1)=-A0+A1(j,1)./(1+i); end hist(SimulatedNPW,30)
>> Please insert Figure 4 here <<
>> Please insert Figure 5 here <<
And also the probability of being economic for such project with taking into
account the assumption of having a minimum attractive rate of return 0.2i can
be computed as follows:
125 1 0.2
( 0 | 0.2 ) 0.3292135
P NPW i EXP
35
As it is obvious from Figures 4 and 5, the economic desirability of this project
NPW is less than zero in some cases 125, 0 , and for this reason, the probability
of being economic for this project is computed as 32.92%.
Fixed cost 0 A and variable income 1 A with uniform distribution: In this case, we
take into account a project with an initial cost 0 100A , a variable income
1 1 1~ 125, 155A Uniform and an investor with minimum attractive rate of
return 0.35i . In this case, the function of economic desirability will be as
1 100 0.7407NPW A . Therefore, the mean and the variance of economic
desirability of this project are calculated as 3.7037E NPW and
41.1523Var NPW . Also according to the analytical equation derived in Section
(3.3), the NPW of this project has a uniform distribution with probability
distribution function PDF NPW as follows:
1 10 0 ~ 7.4074, 14.8148
1 1NPW Uniform A A
i i
: 0.0450, 7.4074 14.8148NPWPDF NPW f v v
To validate this analytical equation, the simulation approach is utilized. Figures 6
and 7 confirm the adoption of analytical equation of NPWf v and the simulated
results for 200000 samples. The pseudo code for simulation procedure is shown as
follows.
A1=zeros(200000,1); SimulatedNPW=zeros(200000,1); for j=1:200000 A1(j,1)=random('unif',Alfa1,Beta1); SimulatedNPW(j,1)=-A0+A1(j,1)./(1+i); end hist(SimulatedNPW,10)
>> Please insert Figure 6 here <<
>> Please insert Figure 7 here <<
Moreover the probability of being economic for such project is gained as:
36
1 0
1 1
1( 0 | ) 0.6667
A iP NPW i
In this project, if 0.6i , since 1 0 1A i , therefore according to lemma 1, it is
certainly uneconomic and the probability of being economic equals to 0. Also if
0.2i , since 1 0 1A i , therefore according to lemma 2, this project is certainly
uneconomic and the probability of being economic equals to 1.
5.2. Numerical Examples for Two-Period Cash Flows
Fixed cost 0A , fixed income 1 A and variable income 2 A with normal distribution:
Assume that in a two-period project, the cash flow is as
2
0 1 2 2 2160, 130, ~ 100, 20A A A Normal and the minimum attractive rate of
return equals to 0.25i . In this project, the function of economic desirability NPW
derived as follows:
1 20 22
56 0.64 1 1
A ANPW A A
i i
8, 8.1920E NPW Var NPW
and, according to the results derived in Section (4.1), it can be concluded that:
~ 8, 8.1920NPW Normal
Similar to one-period cases, the comparison between derived analytical equation
and simulation results was carried out, and the results confirm the existence of
this equation completely. For simplicity and with the aim of preventing the
repetitive materials, we discard the simulation procedure hereafter. Also the
probability of being economic for this project with having minimum attractive rate
of return 0.25i is obtained as follows:
( 0 | 0.25 )P NPW i
2
0.5
160 1 0.25 130 1 0.25 1001 0.9974
20
37
Fixed cost 0 A , variable income 1 A with normal distribution and fixed income 2 A :
Assume, in the previous example, the cash flow would be as
2
0 1 1 1 2 160, 130, 20 , ~100A A Normal A and the minimum attractive rate of
return would be 0.25i . In this case, the function of economic desirability NPW
can be achieved as follows:
1 20 12
96 0.8 1 1
A ANPW A A
i i
8, 12.80E NPW Var NPW
So, according to the analytical results derived in Section (4.2), it can be concluded
that:
~ 8,1 2.80NPW Normal
Similar to the previous cases, the simulation results confirm the existence of this
equation completely. Also the probability of being economic for this project with
having minimum attractive rate of return 0.25i , is attained as follows:
( 0 | 0.25 )P NPW i
0.5
160 1 0.25 130 100 / 1 0.25 1 0.9873
20
Fixed cost 0 A , fixed income 1 A and variable income 2 A with exponential
distribution: Consider a two-period project with cash flow as
0 1 2 2160, 130, ~ 100A A A EXP and a minimum attractive rate of return as
0.25i . In this case, the function of economic desirability would be as
2NPW 56 0.64 A with 8E NPW and Var NPW 4096 . So according to the
analysis performed in Section (4.3), it can be concluded that:
1.5625 160 162.5
: 0.0156* ,100
NPW
vPDF NPW f v EXP
where the variation range of NPW is 56 v . Similar to the one-period cases,
the simulation results confirm the existence of this equation. Furthermore, the
probability of being economic for this project with having minimum attractive rate
of return 0.25i can be gained as:
38
2130 1 0.25 160 1
( 0 | 0.25 ) 0.4169100
iP NPW i EXP
But if the initial cost would be 0 A 100 instead of 0 A 160 , according to lemma 3,
since we have 1
0
1A
iA
, so this project is certainly economic in this case and the
probability of being economic will be 1.
Fixed cost 0 A , variable income 1 A with exponential distribution and fixed income
2 A : Assume that the cash flow of a two-period project is
0 1 1 2160, ~ 130 , 100A A EXP A and the minimum attractive rate of return is
0.25i . In this case, the function of economic desirability would be as
196 0.8 NPW A with 8E NPW and 10816Var NPW . So according to the
analysis performed in Section (4.4), it can be concluded that:
1.25 160 80
: 0.0096* ,100
NPW
vPDF NPW f v EXP
where variation range of the NPW would be 96 v . Similar to the previous
cases, simulation analysis was carried out and the results confirm the existence of
this equation. Additionally, the probability of being economic with having
minimum attractive rate of return 0.25i can be calculated for this project as
follows:
100 / 1 0.25 160 1 0.25
( 0 | 0.25 ) 0.3973130
P NPW i EXP
However, according to what has been proved in lemma 4, if the initial cost would
be 0 60A instead of 0 160A , we have 22
0
1A
iA
, so the project is certainly
economic and the probability of being economic is 1.
Fixed cost 0 A , fixed income 1 A and variable income 2 A with uniform distribution:
Consider a two-period project with cash flow as 0 1 160, 130, A A
2 2 2~ 80, 120A Uniform and the minimum attractive rate of return as 0.25i .
39
In this case, the economic desirability function would be as 2 56 0.64 NPW A
with 8E NPW and 54.6133Var NPW . According to the analyses performed in
Section (4.5), it can be concluded that:
2 1 2 10 02 2
~ 4.80, 20.801 11 1
A ANPW Uniform A A
i ii i
: 0.0391, 4.8 10.80NPWPDF NPW f v v
Similar to the one-period cases, the simulation analysis was carried out and the
results confirm the existence of such function completely. In addition, the
probability of being economic for this project with having minimum attractive rate
of return 0.25i is calculated as:
2120 130 1 0.25 160 1 0.25
( 0 | ) 0.8125120 80
P NPW i
But according to what has been presented in lemma 5, if the upper bound of the
income 2 A would be 2 87 , then we have 2
2 0 11 1A i A i , and the project
is certainly uneconomic with probability of being economic as 0 . In the other
hand, if the lower bound of income 2 A would be 2 90 , in this case we have
2
2 0 1 1 1A i A i and then according to lemma 6, project is certainly
economic with the probability of being economic as 1.
Fixed cost 0 A , variable income 1 A with uniform distribution and fixed income 2 A :
Consider the cash flow of a two-period project would be as
0 1 1 1 2160, ~ 110, 150 , 100A A Uniform A and the minimum attractive rate of
return is 0.25i . In this case, the function of economic desirability would be
196 0.8 NPW A with 8E NPW and 85.3333Var NPW . In this case, according
to the results derived in Section (4.6), it can be concluded that:
2 1 2 10 02 2
~ 8, 241 11 1
A ANPW Uniform A A
i ii i
: 0.0313, 8 24NPWPDF NPW f v v
40
Similar to one-period cases, the simulation results confirm the existence of this
function completely. In addition, the probability of being economic for this project
with minimum attractive rate of return 0.25i is obtained as:
100 / 1 0.25 150 160 1 0.25
( 0 | ) 0.75150 110
P NPW i
However, according to what has been proved in lemma 7, if the upper bound of
income 2 A would be 1 115 , then we have 1 0 2 1 / 1A i A i , and the project
is certainly uneconomic. In the other hand, if the lower bound of income 2 A would
be 3 130 , we have 1 0 21 / 1A i A i and, according to lemma 8, the
project is certainly economic and the probability of being economic would be 1.
5.3. Numerical Examples for Multiple-Period Cash Flows
Variable income with normal distribution: Consider an investment project
with five periods, where the cash flow is as
2
0 1 2 3 3 3400, 150, 200, ~ 100, 10A A A A Normal , 4 50A and 5 150A . In
addition, assume that the minimum attractive rate of return equals to 0.25i
. In this project, the function of economic desirability NPW derived as
follows:
5
0 3
1
82.4 0.51 1
k
k
k
ANPW A A
i
31.16, 2.62E NPW Var NPW
and, according to the results derived in Section (5.1), it can be concluded
that:
~ 31.16, 2.62NPW Normal
Similar to one and two period cases, the comparison between derived NPW
equation and simulation results was done, and the results confirm this NPW
equation completely. Also the probability of being economic for this project
41
for an investor with minimum attractive rate of return 0.25i is obtained as
follows:
( 0 | 0.25 )P NPW i
3
1 3 2 3 4 3 5 3
150 200 50 150400 1 0.25 100
1 0.25 1 0.25 1 0.25 1 0.251 0.00
10
That means this project has no chance to be economic.
Variable income with exponential distribution: Assume, in the previous
example, the cash flow at third period is 3 3 ~ 350A EXP and all other
parameters are unchanged. In this case, the mean and variance of economic
desirability NPW are achieved as follows:
96.83, 32112.64E NPW Var NPW
So, according to the analytical results derived in Section (5.2), it can be
concluded that:
3
1 3 2 3 4 3 5 33
150 200 50 150400 1 0.25
1 0.25 1 0.25 1 0.25 1 0.251 0.25:
350 350NPW
v
PDF NPW f v EXP
Similar to the previous cases, the simulation results confirm the existence of
this equation completely. Also the probability of being economic for this
project is attained as follows:
( 0 | 0.25 )P NPW i
42
3
1 3 2 3 4 3 5 3
150 200 50 150400 1 0.25
1 0.25 1 0.25 1 0.25 1 0.250.6315
350EXP
Since the condition
0
1 | 1
n
k
k
k k l
AA
i
(317.63 400) is true for this example, we
can conclude that the probability of being economic for this project is 0.6315 .
Variable income with uniform distribution: Consider previous example, in
which the cash flow at third period is 3 3 3 ~ 500, 600A Uniform and all
other parameters are unchanged. In this case, the mean and variance of
economic desirability NPW are achieved as follows:
199.23, 218.45E NPW Var NPW
So, according to the analytical results derived in Section (5.3), the PDF of
NPW can be concluded that:
31 0.25
: 0.0195, 1 73.63 224.83600 500
NPWPDF NPW f v v
As can be seen, both upper and lower bounds of NPW are greater than zero
and then ( 0 | 0.25 )P NPW i is 1. That means this project is certainly
economic.
6. Conclusions
This paper utilized the probability theory tools like moment generating function
(MGF) and transformation method, to derive the analytical and closed-form
function for probability distribution function (PDF) of the net present worth
(NPW) in investment projects. The random cash flows follow normal, uniform and
exponential distributions in our analysis. This analysis was performed for three
classes of investment projects: (i) one-period cash flows including three different
cases (fixed cost 0 A and variable income 1A with normal, exponential and uniform
distributions), (ii) two-period cash flows including six different cases (fixed cost 0 A
43
, fixed income 1 A and variable income 2 A with normal, exponential and uniform
distributions, and fixed cost 0 A , variable income 1 A with normal, exponential and
uniform distributions and fixed income 2 A ) and (iii) multiple period cash flows
with normal, exponential and uniform distributions of incomes. The probability
distribution functions of NPW are derived for each cases separately. To validate
the analytical PDFs derived, numerical examples are presented and a set of
comprehensive simulation analysis was conducted. The comparisons performed
between simulation results and analytical functions. The simulated results
demonstrated that both analytical and simulated results of derived PDFs are
completely adopted to each other, which confirms the validity of our analytical
equations. The importance of such PDF functions is that the investor can simply
calculate the probability of being economic for investment projects and get more
reliable decisions. In deterministic economic evaluation problems, the investor has
his/her own minimum attractive rate of return (MARR) which is used in project
evaluations. In our stochastic problems, we calculate the probability of being
economic for an uncertain cash flow. When this parameter is calculated, the
investor can compare this parameter with his/her minimum probability of being
economic. If the minimum probability of being economic is satisfied, the project is
selected as economic, and otherwise, it is rejected. In other words, this paper
presented a decision-making tool for evaluation of investment projects with
uncertain cash flows.
An interesting direction for future study is to consider other performance criteria
like NFW, NEUA, or even payback period, with other probability distributions like
Weibull or Gamma.
References
1. Cleland, D., and Ireland, L. "Project management: Strategic design and implementation". New york: McGraw Hill (2002).
2. Carlsson, C., Fuller, R., Heikkila, M., and Majlender, P. "A fuzzy approach to R&D project portfolio selection". International Journal of Approximate Reasoning, 44(2), pp. 93–105 (2007).
3. Chen, T., Zhang, J., and Lai, K. "An integrated real options evaluating model for information technology projects under multiple risks". International Journal of Project Management, 27(8), pp. 776-786 (2009).
44
4. Armaneri, Ö., Özdagoglu, G., and Yalçinkaya, Ö. "An integrated decision support approach for project investors in risky and uncertain environments". Journal of Computational and Applied Mathematics, 234(8), pp. 2530-2542 (2010).
5. Zhang, W. G., Me, Q., Lu, Q., and Xiao, W. L. "Evaluating methods of investment project and optimizing models of portfolio selection in fuzzy uncertainty". Computers and Industrial Engineering, 61(3), pp. 721-728 (2011).
6. Hanafizadeh, P., and Latif, V. "Robust net present value", Mathematical and Computer Modelling, 54(1-2), pp. 233-242 (2011).
7. Wang, J., and Hwang, W. L. "A fuzzy set approach for R&D portfolio selection using a real options valuation model". Omega, 35(3), pp. 247-257 (2007).
8. Zuojun, P., Yuhong, C., and Lei, S. "Applied research on improved fuzzy chance-constrained model in engineering project comparison and selection". Procedia Engineering, 12(1), pp. 184-190 (2011).
9. Ebrahimnejad, S., Mousavi, S., Tavakkoli-Moghaddam, R., Hashemi, H., and Vahdani, B. "A novel two-phase group decision making approach for construction project selection in a fuzzy environment". Applied Mathematical Modelling, 36(9), pp. 4197-4217 (2011).
10. Chiang, T. A., and Che, Z. "A fuzzy robust evaluation model for selecting and ranking NPD projects using Bayesian belief network and weight-restricted DEA". Expert Systems with Applications, 37(11), pp. 7408-7418 (2010).
11. Shakhsi-Niaei, M., Torabi, S., and Iranmanesh, S. "A comprehensive framework for project selection problem under uncertainty and real-world constraints". Computers & Industrial Engineering, 61(1), pp. 226-237 (2011).
12. Huang, X. "Optimal project selection with random fuzzy parameters". International Journal Production Economics, 106(2), pp. 513-522 (2007).
13. Naimi Sadigh, A. Mokhtari, H., Iranpoor, M., and Ghomi, S. M. T. "Cardinality constrained portfolio optimization using a hybrid approach based on particle swarm optimization and Hopfield neural network". Advanced Science Letters, 17(1), pp. 11-20 (2012).
14. Salmasnia, A., Mokhtari, H., and Abadi, I. N. K. "A robust scheduling of projects with time, cost, and quality considerations". The International Journal of Advanced Manufacturing Technology, 60(5-8), pp. 631-642 (2012).
15. Liu, M., and Wu, F. F. "Portfolio optimization in electricity markets". Electric Power systems research, 77(8), pp. 1000-1009 (2007).
16. Afshar-Nadjafi, B., Parsanejad, A., Hajipour, V., and Nobari, A. "Solution procedure for generalized resource investment problem with discounted cash flows and progress payment". Scientia Iranica, 21(6), pp. 2436-2447 (2014).
45
17. Rębiasz, B., and Macioł, A. "Comparison of Classical Multi-Criteria Decision Making Methods with Fuzzy Rule-Based Methods on the Example of Investment Projects Evaluation". In Intelligent Decision Technologies , pp. 549-561). Springer, Cham (2015).
18. Dai, C. Y., Wang, Y. X., Li, D., and Zhou, Y. L. "Renewable Energy Investment Project Evaluation Model Based on Improved Real Option. In Low-carbon City and New-type Urbanization" (pp. 43-53). Springer, Berlin, Heidelberg (2015).
19. Kilic, M., and Kaya, İ. "Investment project evaluation by a decision making methodology based on type-2 fuzzy sets". Applied Soft Computing, 27(1), pp. 399-410 (2015).
20. Kirkwood, L., Shehab, E., Baguley, P., and Starr, A. "Uncertainty of Net Present Value calculations and the impact on applying integrated maintenance approaches to the UK rail industry". Procedia CIRP, 38(1), pp. 245-249 (2015).
21. Tabrizi, B. H., Torabi, S. A., and Ghaderi, S. F. "A novel project portfolio selection framework: An application of fuzzy DEMATEL and multi-choice goal programming". Scientia Iranica, 23(6), pp. 2945-2958 (2016).
22. Fathallahi, F., and Naja, A. A. "A hybrid genetic algorithm to maximize net present value of project cash flows in resource-constrained project scheduling problem with fuzzy parameters". Scientia Iranica, 23(4), pp. 1893-1903 (2016).
23. Dutta, G., and Ashtekar, M. "A system dynamics simulation model of a blast furnace for project evaluation". International Journal of Business and Systems Research, 11(3), pp. 325-343 (2017).
24. Etemadi, S., Koosha, H., and Salari, M. "A goal programming capital budgeting model under uncertainty in Construction industry". Scientia Iranica, 25(2), pp. 841-851 (2018).
25. Mohagheghi, V., Mousavi, S. M., Vahdani, B., and Shahriari, M. R. "R&D project evaluation and project portfolio selection by a new interval type-2 fuzzy optimization approach". Neural Computing and Applications, 28(12), pp. 3869-3888 (2017).
26. Awasthi, A., and Omrani, H. "A scenario simulation approach for sustainable mobility project evaluation based on fuzzy cognitive maps". International Journal of Modelling and Simulation, pp. 1-11 (2018).
27. Montgomery, D. C., and Runger, G. C. "Applied statistics and probability for engineers". New York: John Wiley And Sons (2010).
28. Ross, S. "A First Course in Probability", 7th edition. Upper Saddle River, NJ: Pearson (2005).
46
Hadi Mokhtari is currently an Assistant Professor of Industrial Engineering in
University of Kashan, Iran. His current research interests include the
applications of operations research and artificial intelligence techniques to the
areas of project scheduling, production scheduling, manufacturing supply
chains, and engineering economic problems. He also published several papers
in international journals such as Computers and Operations Research,
International Journal of Production Research, Applied Soft Computing,
Neurocomputing, International Journal of Advanced Manufacturing Technology,
IEEE Transactions on Engineering Management, and Expert Systems with
Applications.
Saba Kiani is currently a B.Sc. student of Industrial Engineering in University
of Kashan, Iran. Her current research interests include the applications of
operations research and applied statistics to the areas of engineering
economics problems.
Seyed Saman Tahmasebpoor is currently a B.Sc. student of Industrial
Engineering in University of Kashan, Iran. His current research interests
include the applications of operations research and applied statistics to the
engineering economics problems.
Captions:
Figure 1: A multiple-period cash flow diagram
Figure 2: The NPW distribution function according to the analytical equation derived for project with fixed cost 0 A and variable income 1 A with normal distribution
Figure 3: The NPW distribution histogram according to the simulation results for project with fixed cost 0A and variable income 1 A with normal distribution
Figure 4: The NPW distribution function according to the analytical equation derived for project with fixed cost 0 A and variable income 1 A with exponential distribution
Figure 5: The NPW distribution histogram according to the simulation results for project with fixed cost 0 A and variable income 1 A with exponential distribution
Figure 6: The NPW distribution function according to the analytical equation derived for project with fixed cost 0 A and variable income 1 A with exponential distribution
Figure 7: The NPW distribution histogram according to the simulation results for project
with fixed cost 0 A and variable income 1 A with exponential distribution
47
Tables: −
Figure 1: A multiple-period cash flow diagram
Figure (3): The NPW distribution histogram according to the simulation results for project with
fixed cost 0A and variable income 1 A with normal
distribution
Figure (2): The NPW distribution function according to the analytical equation derived
for project with fixed cost 0 A and variable
income 1 A with normal distribution
4 6 8 10 12 14 16 180
1
2
3
4x 10
4
Sim
ula
ted P
DF
4 6 8 10 12 14 16 180
0.05
0.1
0.15
0.2
0.25
0.3
Ana
lytical P
DF
-175 -75 25 125 225 325 425 525 625 725 8000
1
2
3
4
5
6x 10
4
Sim
ula
ted P
DF
-175 -75 25 125 225 325 425 525 625 725 8000
0.002
0.004
0.006
0.008
0.01
Analy
tical P
DF
𝐴0
𝐴1
0
1
𝐴2
2
𝐴𝑛
𝑛
48
Figure (5): The NPW distribution histogram according to the simulation results for project
with fixed cost 0 A and variable income 1 A with
exponential distribution
Figure (4): The NPW distribution function according to the analytical equation derived for
project with fixed cost 0 A and variable income 1 A
with exponential distribution
Figure (7): The NPW distribution histogram according to the simulation results for project
with fixed cost 0 A and variable income 1 A with
exponential distribution
Figure (6): The NPW distribution function according to the analytical equation derived for
project with fixed cost 0 A and variable income
1 A with exponential distribution
Tables: −
-10 -8 -6 -4 -2 0 2 4 6 8 10 12 14 16170
0.5
1
1.5
2
2.5x 10
4
Sim
ula
ted P
DF
-10 -8 -6 -4 -2 0 2 4 6 8 10 12 14 16170
0.01
0.02
0.03
0.04
0.05
0.06
Analy
tical P
DF