ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of...
-
Upload
dora-robbins -
Category
Documents
-
view
215 -
download
0
Transcript of ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of...
![Page 1: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/1.jpg)
ECE 530 – Analysis Techniques for Large-Scale Electrical Systems
Prof. Tom Overbye
Dept. of Electrical and Computer Engineering
University of Illinois at Urbana-Champaign
[email protected]/21/2015
1
Lecture 8: Power System Operation
![Page 2: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/2.jpg)
Power System Operations Overview
• Goal is to provide an intuitive feel for power system operation
• Emphasis will be on the impact of the transmission system
• Introduce basic power flow concepts through small system examples
2
![Page 3: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/3.jpg)
Power System Basics
• All power systems have three major components: Generation, Load and Transmission/Distribution.
• Generation: Creates electric power.• Load: Consumes electric power.• Transmission/Distribution: Transmits electric
power from generation to load. –Lines/transformers operating at voltages above
100 kV are usually called the transmission system. The transmission system is usually networked.
–Lines/transformers operating at voltages below 100 kV are usually called the distribution system (radial).
3
![Page 4: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/4.jpg)
Metro Chicago Electric Network
4
![Page 5: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/5.jpg)
Small PowerWorld Simulator Case
Bus 2 Bus 1
Bus 3Home Area
204 MW
102 MVR
150 MW
150 MW 37 MVR
116 MVR
102 MW 51 MVR
1.00 PU
-20 MW 4 MVR
20 MW -4 MVR
-34 MW 10 MVR
34 MW-10 MVR
14 MW -4 MVR
-14 MW
4 MVR
1.00 PU
1.00 PU
106 MW 0 MVR
100 MWAGC ONAVR ON
AGC ONAVR ON
Load withgreenarrows indicatingamountof MWflow
Usedto controloutput ofgenerator
Direction of arrow is used to indicatedirection of real power (MW) flow
Note thepower balance ateach bus
PowerWorld Case: B3NewSlow 5
![Page 6: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/6.jpg)
Basic Power Control
6
• Opening a circuit breaker causes the power flow to instantaneously (nearly) change.
• No other way to directly control power flow in a transmission line.
• By changing generation we can indirectly change this flow.
• Power flow in transmission line is limited by heating considerations
• Losses (I^2 R) can heat up the line, causing it to sag.
![Page 7: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/7.jpg)
Overloaded Transmission Line
7
![Page 8: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/8.jpg)
Interconnected Operation
• Power systems are interconnected across large distances. For example most of North America east of the Rockies is one system, with most of Texas and Quebec being major exceptions
• Individual utilities only own and operate a small portion of the system; this paradigm is nowmore complex withthe advent of ISOs 8
![Page 9: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/9.jpg)
Balancing Authority (BA) Areas
• Transmission lines that join two areas are known as tie-lines.
• The net power out of an area is the sum of the flow on its tie-lines.
• The flow out of an area is equal to
total gen - total load - total losses = tie-flow
9
![Page 10: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/10.jpg)
Area Control Error (ACE)
• The area control error is the difference between the actual flow out of an area, and the scheduled flow–ACE also includes a frequency component that we
will probably consider later in the semester
• Ideally the ACE should always be zero• Because the load is constantly changing, each
utility (or ISO) must constantly change its generation to “chase” the ACE
• ACE was originally computed by utilities; increasingly it is computed by larger organizations such as ISOs
10
![Page 11: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/11.jpg)
Area Control Error (ACE)
• The area control error is the difference between the actual flow out of an area, and the scheduled flow–ACE also includes a frequency component that we
will probably consider later in the semester
• Ideally the ACE should always be zero• Because the load is constantly changing, each
utility (or ISO) must constantly change its generation to “chase” the ACE
• ACE was originally computed by utilities; increasingly it is computed by larger organizations such as ISOs
11
![Page 12: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/12.jpg)
Automatic Generation Control
• Most utilities (ISOs) use automatic generation control (AGC) to automatically change their generation to keep their ACE close to zero.
• Usually the control center calculates ACE based upon tie-line flows; then the AGC module sends control signals out to the generators every couple seconds.
12
![Page 13: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/13.jpg)
Three Bus Case on AGC
Bus 2 Bus 1
Bus 3Home Area
266 MW
133 MVR
150 MW
250 MW 34 MVR
166 MVR
133 MW 67 MVR
1.00 PU
-40 MW 8 MVR
40 MW -8 MVR
-77 MW 25 MVR
78 MW-21 MVR
39 MW-11 MVR
-39 MW
12 MVR
1.00 PU
1.00 PU
101 MW 5 MVR
100 MWAGC ONAVR ON
AGC ONAVR ON
Net tie flow is close to zero
Generationis automaticallychanged to matchchange in load
13
![Page 14: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/14.jpg)
Generator Costs
• There are many fixed and variable costs associated with power system operation
• The major variable cost is associated with generation.
• Cost to generate a MWh can vary widely• For some types of units (such as hydro and
nuclear) it is difficult to quantify• More others such as wind and solar the marginal
cost of energy is essentially zero (actually negative for wind!)
• For thermal units it is straightforward to determine
• Many markets have moved from cost-based to price-based generator costs
14
![Page 15: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/15.jpg)
Economic Dispatch
• Economic dispatch (ED) determines the least cost dispatch of generation for an area.
• For a lossless system, the ED occurs when all the generators have equal marginal costs.
IC1(PG,1) = IC2(PG,2) = … = ICm(PG,m)
15
![Page 16: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/16.jpg)
Power Transactions
• Power transactions are contracts between areas to do power transactions.
• Contracts can be for any amount of time at any price for any amount of power.
• Scheduled power transactions are implemented by modifying the area ACE:
ACE = Pactual,tie-flow - Psched
16
![Page 17: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/17.jpg)
100 MW Transaction
Bus 2 Bus 1
Bus 3Home Area
Scheduled Transactions
225 MW
113 MVR
150 MW
291 MW 8 MVR
138 MVR
113 MW 56 MVR
1.00 PU
8 MW -2 MVR
-8 MW 2 MVR
-84 MW 27 MVR
85 MW-23 MVR
93 MW-25 MVR
-92 MW
30 MVR
1.00 PU
1.00 PU
0 MW 32 MVR
100 MWAGC ONAVR ON
AGC ONAVR ON
100.0 MW
Scheduled 100 MWTransaction from Left to Right
Net tie-lineflow is now100 MW
17
![Page 18: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/18.jpg)
Security Constrained ED
• Transmission constraints often limit system economics.
• Such limits required a constrained dispatch in order to maintain system security.
• In three bus case the generation at bus 3 must be constrained to avoid overloading the line from bus 2 to bus 3.
18
![Page 19: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/19.jpg)
Security Constrained Dispatch
Bus 2 Bus 1
Bus 3Home Area
Scheduled Transactions
357 MW
179 MVR
194 MW
448 MW 19 MVR
232 MVR
179 MW 89 MVR
1.00 PU
-22 MW 4 MVR
22 MW -4 MVR
-142 MW 49 MVR
145 MW-37 MVR
124 MW-33 MVR
-122 MW
41 MVR
1.00 PU
1.00 PU
0 MW 37 MVR100%
100%
100 MWOFF AGCAVR ON
AGC ONAVR ON
100.0 MW
Dispatch is no longer optimal due to need to keep line from bus 2 to bus 3 from overloading
19
![Page 20: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/20.jpg)
Multi-Area Operation
• If Areas have direct interconnections, then they may directly transact up to the capacity of their tie-lines.
• Actual power flows through the entire network according to the impedance of the transmission lines.
• Flow through other areas is known as “parallel path” or “loop flows.”
20
![Page 21: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/21.jpg)
Seven Bus Case: One-line
Top Area Cost
Left Area Cost Right Area Cost
1
2
3 4
5
6 7
106 MW
168 MW
200 MW 201 MW
110 MW 40 MVR
80 MW 30 MVR
130 MW 40 MVR
40 MW 20 MVR
1.00 PU
1.01 PU
1.04 PU1.04 PU
1.04 PU
0.99 PU1.05 PU
62 MW
-61 MW
44 MW -42 MW -31 MW 31 MW
38 MW
-37 MW
79 MW -77 MW
-32 MW
32 MW-14 MW
-39 MW
40 MW-20 MW 20 MW
40 MW
-40 MW
94 MW
200 MW 0 MVR
200 MW 0 MVR
20 MW -20 MW
AGC ON
AGC ON
AGC ON
AGC ON
AGC ON
8029 $/MWH
4715 $/MWH 4189 $/MWH
Case Hourly Cost 16933 $/MWH
System hasthree areas
Area Lefthas onebus
Area Right has one bus
Area Tophas fivebuses
PowerWorld Case: B7Flat 21
![Page 22: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/22.jpg)
Seven Bus Case: Area View
System has40 MW of“Loop Flow”
Actualflowbetweenareas
Loop flow can result in higher losses
Area Losses
Area Losses Area Losses
Top
Left Right
-40.1 MW
0.0 MW
0.0 MW
0.0 MW
40.1 MW
40.1 MW
7.09 MW
0.33 MW 0.65 MW
Scheduledflow
22
![Page 23: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/23.jpg)
Seven Bus - Loop Flow?
Area Losses
Area Losses Area Losses
Top
Left Right
-4.8 MW
0.0 MW
100.0 MW
0.0 MW
104.8 MW
4.8 MW
9.44 MW
-0.00 MW 4.34 MW
100 MW Transactionbetween Left and Right
Transaction has actually decreasedthe loop flow
Note thatTop’s Losses haveincreasedfrom 7.09MW to9.44 MW
23
![Page 24: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/24.jpg)
POWER TRANSFER DISTRIBUTION FACTORS (PTDFS)
24
• PTDFs are used to show how a particular transaction will affect the system
• Power transfers through the system according to the impedances of the lines, without respect to ownership
• All transmission players in network could be impacted, to a greater or lesser extent
• Later in the semester we’ll consider techniques for calculating PTDFs
![Page 25: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/25.jpg)
PTDF EXAMPLE - NINE BUS CASE ACTUAL FLOWS
25
17%
58% 41%
51%
45%
42%
34%
6%
54%
29%
32%
A
G
B
C
D
E
I
F
H
400.0 MWMW 400.0 MWMW 300.0 MWMW
250.0 MWMW
250.0 MWMW
200.0 MWMW
250.0 MWMW
150.0 MWMW
50.0 MW
39%
PowerWorld Case: B9
![Page 26: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/26.jpg)
PTDF EXAMPLE - PTDFS: TRANSFER FROM A TO I
26
44%
56% 13%
30%
35%
20%
10%
2%
34%
34%
32%
A
G
B
C
D
E
I
F
H
400.0 MWMW 400.0 MWMW 300.0 MWMW
250.0 MWMW
250.0 MWMW
200.0 MWMW
250.0 MWMW
150.0 MWMW
50.0 MW
34%
Values now tell percentage of flow that will go on line
![Page 27: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/27.jpg)
PTDF EXAMPLE - PTDFS: TRANSFER FROM G TO F
27
6%
6% 12%
18%
61%
12%
6%
19%
21%
21%
A
G
B
C
D
E
I
F
H
400.0 MWMW 400.0 MWMW 300.0 MWMW
250.0 MWMW
250.0 MWMW
200.0 MWMW
250.0 MWMW
150.0 MWMW
50.0 MW
20%
![Page 28: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/28.jpg)
Wisconsin to TVA Line PTDF Contour
28
Contours show lines that would carry at least 2% of a power transfer from Wisconsin to TVA
![Page 29: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/29.jpg)
NERC Flowgates
• A convenient glossary of terms used for power system operations in North America is available at http://www.nerc.com/files/glossary_of_terms.pdf
• One common term is a “flowgate,” which is a mathematical construct to measure the MW flow on one or more elements in the bulk transmission system–Sometimes they include the impact of contingencies,
something we will consider later in the semester
• A simple flowgate would be the MW flow through a single transmission line or transformer
29
![Page 30: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/30.jpg)
NERC TLRs
• In the North American Eastern Interconnect (EI) transmission loading relief procedures (TLRs) are used to mitigate the overloads on the bulk transmission system
• TLRs consider the PTDFs associated with transactions on flowgates if there is a flowgate violation
30
![Page 31: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/31.jpg)
Loop Flow Impact: Market Segmentation
31
T V A
SOUTHERN
AEP
CPLW
AP
JCP&LPECO
AE
PSE&G
AEC
SMEPA
CEI
CINCIPS
CONS
DECO
CPLE
DLCO
DPL
DUKE
EKPC
IMPA
IP
IPL
KU
NI
NIPS
OE
OVEC
TE
VP
METED
PENELEC
PEPCO
PJM500
BG&E
PP&L
BREC
LGE
SIGE
SIPC
CILCO
CWLP
HE
EEI
EMO
NYPP
SCE&GSCPSA
ONT HYDR
DOE
DPL
ENTR
NEPOOL
WPLWEP
WPS
UPP
MGE
YADKIN
HARTWELL
SEPA-JST
SEPA-RBR
TAL
FPC
FPL
JEA
SECCELE
LAFA
CAJN
SWEP
SWPA
PSOK
GRRD
OKGE
KAMO
SWPS
WEFA
OMPA
EQ-ERCOT
WERE
NSP
MP
IPW
DPC
MEC
IESC
MPW
OTP
NPPD OPPD
SMP
UPA
WAPA
MIPUSTJOKACY
KACP
ASEC
SPRM
INDN
EMDE
MIDWSUNC
WEPL
During summerof 1998 con-gestion on justtwo elementspushed Midwestspot marketprices up by afactor of 200:from $ 20/MWhto $ 7500/MWh!
Large price rises have occurred in 1999 and 2000 as well
![Page 32: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/32.jpg)
Pricing Electricity
• Cost to supply electricity to bus is called the locational marginal price (LMP)
• Presently some electric makets post LMPs on the web
• In an ideal electricity market with no transmission limitations the LMPs are equal
• Transmission constraints can segment a market, resulting in differing LMP
• Determination of LMPs requires the solution on an Optimal Power Flow (OPF)
32
![Page 33: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/33.jpg)
3 BUS LMPS - OVERLOAD IGNORED
Bus 2 Bus 1
Bus 3
Total Cost
0 MW
0 MW
180 MWMW
10.00 $/MWh
60 MW 60 MW
60 MW
60 MW120 MW
120 MW
10.00 $/MWh
10.00 $/MWh
180 MW120%
120%
0 MWMW
1800 $/hr
Line from Bus 1 to Bus 3 is over-loaded; all buses have same marginal cost
Gen 1’scostis $10per MWh
Gen 2’scostis $12per MWh
PowerWorld Case: B3LP 33
![Page 34: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/34.jpg)
LINE OVERLOAD ENFORCED
Bus 2 Bus 1
Bus 3
Total Cost
60 MW
0 MW
180 MWMW
12.00 $/MWh
20 MW 20 MW
80 MW
80 MW100 MW
100 MW
10.00 $/MWh
14.01 $/MWh
120 MW 80% 100%
80% 100%
0 MWMW
1921 $/hr
Line from 1 to 3 is no longer overloaded, but nowthe marginal cost of electricity at 3 is $14 / MWh 34
![Page 35: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/35.jpg)
MISO LMPs
35
Five minuteLMPs areposted onlinefor the MISOfootprint
Source: https://www.misoenergy.org/LMPContourMap/MISO_MidWest.html
![Page 36: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/36.jpg)
MISO LMP Volatility!
36
Thisis howthe LMPcontourlookedfor the next 5minuteupdate!
![Page 37: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/37.jpg)
37 Bus Example Design Case
This is Design Case 2 From Chapter 6 of Power System Analysis andDesign by Glover, Sarma, and Overbye, 4th Edition, 2008
Metropolis Light and Power Electric Design Case 2SLACK345
SLACK138
RAY345
RAY138
RAY69
FERNA69
A
MVA
DEMAR69
BLT69
BLT138
BOB138
BOB69
WOLEN69
SHI MKO69
ROGER69
UI UC69
PETE69HI SKY69
TI M69
TI M138
TI M345
PAI 69
GROSS69
HANNAH69
AMANDA69
HOMER69
LAUF69
MORO138
LAUF138
HALE69
PATTEN69
WEBER69
BUCKY138
SAVOY69
SAVOY138
J O138 J O345
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
1.03 pu
1.02 pu
1.03 pu
1.03 pu
1.01 pu
1.00 pu1.01 pu
1.00 pu
1.02 pu
1.01 pu
1.00 pu
1.01 pu
1.01 pu
1.01 pu
1.01 pu
1.02 pu
1.00 pu
1.00 pu
1.02 pu
0.99 pu
0.99 pu
1.00 pu
1.02 pu
1.00 pu1.01 pu
1.01 pu
1.00 pu 1.00 pu
1.01 pu
1.02 pu 1.02 pu
1.02 pu 1.03 pu
A
MVA
1.02 pu
A
MVA
A
MVA
LYNN138
A
MVA
1.02 pu
A
MVA
1.00 pu
A
MVA
System Losses: 10.70 MW
220 MW 52 Mvar
12 MW 3 Mvar
20 MW 12 Mvar
124 MW 45 Mvar
37 MW
13 Mvar
12 MW 5 Mvar
150 MW 0 Mvar
56 MW
13 Mvar
15 MW 5 Mvar
14 MW
2 Mvar
38 MW 3 Mvar
45 MW 0 Mvar
25 MW 36 Mvar
36 MW 10 Mvar
10 MW 5 Mvar
22 MW 15 Mvar
60 MW 12 Mvar
20 MW 28 Mvar
23 MW 7 Mvar
33 MW 13 Mvar
15.9 Mvar 18 MW 5 Mvar
58 MW 40 Mvar
60 MW 19 Mvar
14.2 Mvar
25 MW 10 Mvar
20 MW 3 Mvar
23 MW 6 Mvar 14 MW
3 Mvar
4.9 Mvar
7.3 Mvar
12.8 Mvar
28.9 Mvar
7.4 Mvar
0.0 Mvar
55 MW 25 Mvar
39 MW 13 Mvar
150 MW 0 Mvar
17 MW 3 Mvar
16 MW -14 Mvar
14 MW 4 Mvar
KYLE69A
MVA
PowerWorld Case: TD_2012_Design2 37
![Page 38: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/38.jpg)
Good Power System Operation
• Good power system operation requires that there be no reliability violations for either the current condition or in the event of statistically likely contingencies–Reliability requires as a minimum that there be no
transmission line/transformer limit violations and that bus voltages be within acceptable limits (perhaps 0.95 to 1.08)
–Example contingencies are the loss of any single device. This is known as n-1 reliability.
38
![Page 39: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/39.jpg)
Looking at the Impact of Line Outages
slack
Metropolis Light and Power Electric Design Case 2SLACK345
SLACK138
RAY345
RAY138
RAY69
FERNA69
A
MVA
DEMAR69
BLT69
BLT138
BOB138
BOB69
WOLEN69
SHI MKO69
ROGER69
UI UC69
PETE69HI SKY69
TI M69
TI M138
TI M345
PAI 69
GROSS69
HANNAH69
AMANDA69
HOMER69
LAUF69
MORO138
LAUF138
HALE69
PATTEN69
WEBER69
BUCKY138
SAVOY69
SAVOY138
J O138 J O345
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
1.03 pu
1.02 pu
1.03 pu
1.03 pu
1.01 pu
1.00 pu1.01 pu
1.00 pu
1.02 pu
1.01 pu
1.00 pu
1.01 pu
1.01 pu
1.01 pu
1.01 pu
1.02 pu
1.01 pu
1.00 pu
1.02 pu
0.90 pu
0.90 pu
0.94 pu
1.01 pu
0.99 pu1.00 pu
1.00 pu
1.00 pu 1.00 pu
1.01 pu
1.01 pu 1.02 pu
1.02 pu 1.03 pu
A
MVA
1.02 pu
A
MVA
A
MVA
LYNN138
A
MVA
1.02 pu
A
MVA
1.00 pu
A
MVA
System Losses: 17.61 MW
227 MW 43 Mvar
12 MW 3 Mvar
20 MW 12 Mvar
124 MW 45 Mvar
37 MW
13 Mvar
12 MW 5 Mvar
150 MW 4 Mvar
56 MW
13 Mvar
15 MW 5 Mvar
14 MW
2 Mvar
38 MW 9 Mvar
45 MW 0 Mvar
25 MW 36 Mvar
36 MW 10 Mvar
10 MW 5 Mvar
22 MW 15 Mvar
60 MW 12 Mvar
20 MW 40 Mvar
23 MW 7 Mvar
33 MW 13 Mvar
16.0 Mvar 18 MW 5 Mvar
58 MW 40 Mvar
60 MW 19 Mvar
11.6 Mvar
25 MW 10 Mvar
20 MW 3 Mvar
23 MW 6 Mvar 14 MW
3 Mvar
4.9 Mvar
7.2 Mvar
12.8 Mvar
28.9 Mvar
7.3 Mvar
0.0 Mvar
55 MW 32 Mvar
39 MW 13 Mvar
150 MW 4 Mvar
17 MW 3 Mvar
16 MW -14 Mvar
14 MW 4 Mvar
KYLE69A
MVA
80%A
MVA
135%A
MVA
110%A
MVA
Opening one line (Tim69-Hannah69) causes an overload. This would not be allowed 39
![Page 40: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/40.jpg)
Contingency Analysis
Contingencyanalysis providesan automaticway of lookingat all the statisticallylikely contingencies. Inthis example thecontingency setIs all the single line/transformeroutages
40
![Page 41: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/41.jpg)
Power Flow And Design
• One common usage of the power flow is to determine how the system should be modified to remove contingencies problems or serve new load–In an operational context this requires working with
the existing electric grid–In a planning context additions to the grid can be
considered• In the next example we look at how to remove the
existing contingency violations while serving new load.
41
![Page 42: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/42.jpg)
An Unreliable Solution
slack
Metropolis Light and Power Electric Design Case 2SLACK345
SLACK138
RAY345
RAY138
RAY69
FERNA69
A
MVA
DEMAR69
BLT69
BLT138
BOB138
BOB69
WOLEN69
SHI MKO69
ROGER69
UI UC69
PETE69HI SKY69
TI M69
TI M138
TI M345
PAI 69
GROSS69
HANNAH69
AMANDA69
HOMER69
LAUF69
MORO138
LAUF138
HALE69
PATTEN69
WEBER69
BUCKY138
SAVOY69
SAVOY138
J O138 J O345
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
1.02 pu
1.01 pu
1.02 pu
1.03 pu
1.01 pu
1.00 pu1.01 pu
1.00 pu
1.02 pu
1.01 pu
1.00 pu
1.01 pu
1.01 pu
1.01 pu
1.01 pu
1.02 pu
0.99 pu
1.00 pu
1.02 pu
0.97 pu
0.97 pu
0.99 pu
1.02 pu
1.00 pu1.01 pu
1.01 pu
1.00 pu 1.00 pu
1.01 pu
1.02 pu 1.02 pu
1.02 pu 1.03 pu
A
MVA
1.02 pu
A
MVA
A
MVA
LYNN138
A
MVA
1.02 pu
A
MVA
1.00 pu
A
MVA
System Losses: 14.49 MW
269 MW 67 Mvar
12 MW 3 Mvar
20 MW 12 Mvar
124 MW 45 Mvar
37 MW
13 Mvar
12 MW 5 Mvar
150 MW 1 Mvar
56 MW
13 Mvar
15 MW 5 Mvar
14 MW
2 Mvar
38 MW 4 Mvar
45 MW 0 Mvar
25 MW 36 Mvar
36 MW 10 Mvar
10 MW 5 Mvar
22 MW 15 Mvar
60 MW 12 Mvar
20 MW 40 Mvar
23 MW 7 Mvar
33 MW 13 Mvar
15.9 Mvar 18 MW 5 Mvar
58 MW 40 Mvar
60 MW 19 Mvar
13.6 Mvar
25 MW 10 Mvar
20 MW 3 Mvar
23 MW 6 Mvar 14 MW
3 Mvar
4.9 Mvar
7.3 Mvar
12.8 Mvar
28.9 Mvar
7.4 Mvar
0.0 Mvar
55 MW 28 Mvar
39 MW 13 Mvar
150 MW 1 Mvar
17 MW 3 Mvar
16 MW -14 Mvar
14 MW 4 Mvar
KYLE69A
MVA
96%A
MVA
Case now has nine separate contingencies with reliability violations 42
![Page 43: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/43.jpg)
A Reliable Solution
slack
Metropolis Light and Power Electric Design Case 2SLACK345
SLACK138
RAY345
RAY138
RAY69
FERNA69
A
MVA
DEMAR69
BLT69
BLT138
BOB138
BOB69
WOLEN69
SHI MKO69
ROGER69
UI UC69
PETE69HI SKY69
TI M69
TI M138
TI M345
PAI 69
GROSS69
HANNAH69
AMANDA69
HOMER69
LAUF69
MORO138
LAUF138
HALE69
PATTEN69
WEBER69
BUCKY138
SAVOY69
SAVOY138
J O138 J O345
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
1.03 pu
1.01 pu
1.02 pu
1.03 pu
1.01 pu
1.00 pu1.01 pu
1.00 pu
1.02 pu
1.01 pu
1.00 pu
1.01 pu
1.01 pu
1.01 pu
1.01 pu
1.02 pu
1.00 pu
0.99 pu
1.02 pu
0.99 pu
0.99 pu
1.00 pu
1.02 pu
1.00 pu1.01 pu
1.01 pu
1.00 pu 1.00 pu
1.01 pu
1.02 pu 1.02 pu
1.02 pu 1.03 pu
A
MVA
1.02 pu
A
MVA
A
MVA
LYNN138
A
MVA
1.02 pu
A
MVA
A
MVA
System Losses: 11.66 MW
266 MW 59 Mvar
12 MW 3 Mvar
20 MW 12 Mvar
124 MW 45 Mvar
37 MW
13 Mvar
12 MW 5 Mvar
150 MW 1 Mvar
56 MW
13 Mvar
15 MW 5 Mvar
14 MW
2 Mvar
38 MW 4 Mvar
45 MW 0 Mvar
25 MW 36 Mvar
36 MW 10 Mvar
10 MW 5 Mvar
22 MW 15 Mvar
60 MW 12 Mvar
20 MW 38 Mvar
23 MW 7 Mvar
33 MW 13 Mvar
15.8 Mvar 18 MW 5 Mvar
58 MW 40 Mvar
60 MW 19 Mvar
14.1 Mvar
25 MW 10 Mvar
20 MW 3 Mvar
23 MW 6 Mvar 14 MW
3 Mvar
4.9 Mvar
7.3 Mvar
12.8 Mvar
28.9 Mvar
7.4 Mvar
0.0 Mvar
55 MW 29 Mvar
39 MW 13 Mvar
150 MW 1 Mvar
17 MW 3 Mvar
16 MW -14 Mvar
14 MW 4 Mvar
KYLE69A
MVA
Kyle138A
MVA
Previous case was augmented with the addition of a 138 kV Transmission Line
43PowerWorld Case: TD_2012_Design2_ReliableDesign
![Page 44: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/44.jpg)
Generation Changes and The Slack Bus
• The power flow is a steady-state analysis tool, so the assumption is total load plus losses is always equal to total generation–Generation mismatch is made up at the slack bus
• When doing generation change power flow studies one always needs to be cognizant of where the generation is being made up–Common options include system slack, distributed
across multiple generators by participation factors or by economics
44
![Page 45: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/45.jpg)
Generation Change Example 1
slack
SLACK345
SLACK138
RAY345
RAY138
RAY69
FERNA69
A
MVA
DEMAR69
BLT69
BLT138
BOB138
BOB69
WOLEN69
SHI MKO69
ROGER69
UI UC69
PETE69
HI SKY69
TI M69
TI M138
TI M345
PAI 69
GROSS69
HANNAH69
AMANDA69
HOMER69
LAUF69
MORO138
LAUF138
HALE69
PATTEN69
WEBER69
BUCKY138
SAVOY69
SAVOY138
J O138 J O345
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
0.00 pu
-0.01 pu
0.00 pu
0.00 pu
0.00 pu
-0.03 pu-0.01 pu
0.00 pu
0.00 pu
0.00 pu
-0.03 pu
-0.01 pu0.00 pu
0.00 pu
0.00 pu
0.00 pu
0.00 pu
0.00 pu
0.00 pu
-0.002 pu
0.00 pu
0.00 pu
0.00 pu
0.00 pu0.00 pu
0.00 pu
0.00 pu 0.00 pu
0.00 pu
0.00 pu0.00 pu
0.00 pu0.00 pu
A
MVA
-0.01 pu
A
MVA
A
MVA
LYNN138
A
MVA
0.00 pu
A
MVA
0.00 pu
A
MVA
162 MW 35 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
-157 MW -45 Mvar
0 MW
0 Mvar
0 MW 0 Mvar
0 MW 2 Mvar
0 MW
0 Mvar
0 MW 0 Mvar
0 MW
0 Mvar
0 MW 3 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 4 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
-0.1 Mvar 0 MW 0 Mvar
0 MW 0 Mvar 0 MW
0 Mvar
-0.1 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar 0 MW
0 Mvar
-0.1 Mvar
0.0 Mvar
-0.1 Mvar
-0.2 Mvar
0.0 Mvar
0.0 Mvar
0 MW 51 Mvar
0 MW 0 Mvar
0 MW 2 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
45PowerWorld Case: TD_2012_37Bus_GenChange
![Page 46: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/46.jpg)
Generation Change Example 1
slack
SLACK345
SLACK138
RAY345
RAY138
RAY69
FERNA69
A
MVA
DEMAR69
BLT69
BLT138
BOB138
BOB69
WOLEN69
SHI MKO69
ROGER69
UI UC69
PETE69
HI SKY69
TI M69
TI M138
TI M345
PAI 69
GROSS69
HANNAH69
AMANDA69
HOMER69
LAUF69
MORO138
LAUF138
HALE69
PATTEN69
WEBER69
BUCKY138
SAVOY69
SAVOY138
J O138 J O345
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
0.00 pu
-0.01 pu
0.00 pu
0.00 pu
0.00 pu
-0.03 pu-0.01 pu
0.00 pu
0.00 pu
0.00 pu
-0.03 pu
-0.01 pu0.00 pu
0.00 pu
0.00 pu
0.00 pu
0.00 pu
0.00 pu
0.00 pu
-0.002 pu
0.00 pu
0.00 pu
0.00 pu
0.00 pu0.00 pu
0.00 pu
0.00 pu 0.00 pu
0.00 pu
0.00 pu0.00 pu
0.00 pu0.00 pu
A
MVA
-0.01 pu
A
MVA
A
MVA
LYNN138
A
MVA
0.00 pu
A
MVA
0.00 pu
A
MVA
162 MW 35 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
-157 MW -45 Mvar
0 MW
0 Mvar
0 MW 0 Mvar
0 MW 2 Mvar
0 MW
0 Mvar
0 MW 0 Mvar
0 MW
0 Mvar
0 MW 3 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 4 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
-0.1 Mvar 0 MW 0 Mvar
0 MW 0 Mvar 0 MW
0 Mvar
-0.1 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar 0 MW
0 Mvar
-0.1 Mvar
0.0 Mvar
-0.1 Mvar
-0.2 Mvar
0.0 Mvar
0.0 Mvar
0 MW 51 Mvar
0 MW 0 Mvar
0 MW 2 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
Display shows “Difference Flows” between original 37 bus case, and case with a BLT138 generation outage; note all the power change is picked up at the slack 46
![Page 47: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/47.jpg)
Generation Change Example 2
slack
SLACK345
SLACK138
RAY345
RAY138
RAY69
FERNA69
A
MVA
DEMAR69
BLT69
BLT138
BOB138
BOB69
WOLEN69
SHI MKO69
ROGER69
UI UC69
PETE69
HI SKY69
TI M69
TI M138
TI M345
PAI 69
GROSS69
HANNAH69
AMANDA69
HOMER69
LAUF69
MORO138
LAUF138
HALE69
PATTEN69
WEBER69
BUCKY138
SAVOY69
SAVOY138
J O138 J O345
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
0.00 pu
-0.01 pu
0.00 pu
0.00 pu
0.00 pu
-0.03 pu0.00 pu
0.00 pu
0.00 pu
0.00 pu
-0.03 pu
-0.01 pu-0.01 pu
0.00 pu
0.00 pu
0.00 pu
0.00 pu
0.00 pu
0.00 pu
-0.003 pu
0.00 pu
0.00 pu
0.00 pu
0.00 pu0.00 pu
0.00 pu
0.00 pu 0.00 pu
0.00 pu
0.00 pu0.00 pu
0.00 pu0.00 pu
A
MVA
0.00 pu
A
MVA
A
MVA
LYNN138
A
MVA
0.00 pu
A
MVA
0.00 pu
A
MVA
0 MW 37 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
-157 MW -45 Mvar
0 MW
0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW
0 Mvar
0 MW 0 Mvar
0 MW
0 Mvar
42 MW -14 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
99 MW -20 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
-0.1 Mvar 0 MW 0 Mvar
0 MW 0 Mvar 0 MW
0 Mvar
-0.1 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar 0 MW
0 Mvar
0.0 Mvar
0.0 Mvar
-0.1 Mvar
-0.2 Mvar
-0.1 Mvar
0.0 Mvar
19 MW 51 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
0 MW 0 Mvar
Display repeats previous case except now the change in generation is picked up by other generators using a participation factor approach 47
![Page 48: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/48.jpg)
Generator Reactive Limits
• Generators are P-V buses (P and V are specified).
• QGi of generator i must be within specified limits
• During the PF solution process
• the bus is now a P-Q bus and the originally specified V at this bus is relaxed and calculated.
maxGG
minG iii
QQQ
maxGG ii
QQ If
minGG ii
QQ If minGG ii
QQ then
maxGG ii
QQ then
48
![Page 49: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/49.jpg)
Voltage Regulation Example: 37 Buses
Display shows voltage contour of the power system, demo will show the impactof generator voltage set point, reactive power limits, and switched capacitors
slack
SLACK345
SLACK138
RAY345
RAY138
RAY69
FERNA69
A
MVA
DEMAR69
BLT69
BLT138
BOB138
BOB69
WOLEN69
SHI MKO69
ROGER69
UI UC69
PETE69
HI SKY69
TI M69
TI M138
TI M345
PAI 69
GROSS69
HANNAH69
AMANDA69
HOMER69
LAUF69
MORO138
LAUF138
HALE69
PATTEN69
WEBER69
BUCKY138
SAVOY69
SAVOY138
J O138 J O345
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVAA
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
A
MVA
1.03 pu
1.01 pu
1.02 pu
1.03 pu
1.01 pu
1.00 pu1.00 pu
0.99 pu
1.02 pu
1.01 pu
1.00 pu
1.01 pu1.01 pu
1.01 pu
1.01 pu
1.02 pu
1.00 pu
1.00 pu
1.02 pu
0.997 pu
0.99 pu
1.00 pu
1.02 pu
1.00 pu1.01 pu
1.00 pu
1.00 pu 1.00 pu
1.01 pu
1.02 pu1.02 pu
1.02 pu 1.03 pu
A
MVA
1.02 pu
A
MVA
A
MVA
LYNN138
A
MVA
1.02 pu
A
MVA
1.00 pu
A
MVA
219 MW 52 Mvar
21 MW 7 Mvar
45 MW 12 Mvar
157 MW 45 Mvar
37 MW
13 Mvar
12 MW 5 Mvar
150 MW 0 Mvar
56 MW
13 Mvar
15 MW 5 Mvar
14 MW
2 Mvar
38 MW 3 Mvar
45 MW 0 Mvar
58 MW 36 Mvar
36 MW 10 Mvar
0 MW 0 Mvar
22 MW 15 Mvar
60 MW 12 Mvar
20 MW 9 Mvar
23 MW 7 Mvar
33 MW 13 Mvar 15.9 Mvar 18 MW
5 Mvar
58 MW 40 Mvar 51 MW
15 Mvar
14.3 Mvar
33 MW
10 Mvar
15 MW 3 Mvar
23 MW 6 Mvar 14 MW
3 Mvar
4.8 Mvar
7.2 Mvar
12.8 Mvar
29.0 Mvar
7.4 Mvar
20.8 Mvar
92 MW 10 Mvar
20 MW 8 Mvar
150 MW 0 Mvar
17 MW 3 Mvar
0 MW 0 Mvar
14 MW 4 Mvar
1.010 pu 0.0 Mvar
System Losses: 11.51 MW
49PowerWorld Case: TD_2012_37Bus_Voltage
![Page 50: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/50.jpg)
Remote Regulation and Reactive Power Sharing
• It is quite common for a generator to control the voltage for a location that is not its terminal–Sometimes this is on the high side of the generator step-up
transformer (GSU), sometimes it is partway through the GSU
• It is also quite common for multiple generators to regulate the same bus voltage– In this case only one of the generators can be set as a PV bus;
the others must be set as PQ, with the total reactive power output allocated among them
–Different methods can be used for allocating reactive power among multiple generators
50
![Page 51: ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois.](https://reader033.fdocuments.in/reader033/viewer/2022051417/5697c0221a28abf838cd33d5/html5/thumbnails/51.jpg)
Multiple PV Generator Regulation
51
Top Area Cost
Left Area Cost Right Area Costslack
0.98 pu
1.00 pu
1.04 pu1.04 pu
1.03 pu
0.97 pu1.05 pu
A
MVA
A
MVA
A
MVAA
MVA
A
MVA
A
MVA A
MVA
A
MVA
A
MVA
A
MVA
64 MW
63 MW
44 MW 42 MW 32 MW 32 MW
37 MW
36 MW
79 MW 77 MW
31 MW
31 MW
14 MW
39 MW
40 MW 20 MW 21 MW
40 MW
39 MW
A
MVA
21 MW 20 MW
8043 $/h
4677 $/h 4222 $/h
Case Hourly Cost 16943 $/h
Bus 1 Bus 3 Bus 4
Bus 2 Bus 5
Bus 6 Bus 7
MW108
MW164
MW202 MW199
110 MW
80 MW
130 MW 40 MW
MW 96
200 MW
0 Mvar200 MW
0 Mvar
AGC ON
AGC ON
AGC ON
AGC ON
AGC ON
PowerWorld Case: B7Flat_MultipleGenReg
In this caseboth theBus 2 andBus 4 gensare set to regulatethe Bus 5voltage. Note, theymust regulate itto the samevalue!!