Invitation No.: EKU 94-19 Eastern Kentucky University 521 Lancaster Avenue Richmond, KY 40475 Begley Building Press Box Roof Replacement THIS IS NOT AN ORDER Non-Mandatory Pre-Bid Conference: April 8, 2019, 1:00 PM (ET) Outside of Begley Building (Beside Roy Kidd Statue on North East End of Football Field) Bid Opening: April 17, 2019, 10:00 AM (ET) Commonwealth Building, Room 1411 Eastern Kentucky University (EKU) hereby requests sealed bids for the materials, supplies, equipment or services set forth herein, subject to all conditions outlined in this Bid Package, including : Invitation to Bid ................................................................................................................. 1 EKU General Terms and Conditions ...........................................................................19 Project Specifications.................................................................................................. 57 Project Drawings. ....................................................................................................... ..73 Note: If you require a larger format set of plans, you may download them from our website at: http://purchasing.eku.edu/solicitations . If you would like to purchase a hard copy set of project documents, contact Builder's Exchange of Kentucky at (502) 459-9800, or email at [email protected].

Transcript of EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS...

Page 1: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Invitation No.: EKU 94-19 Eastern Kentucky University

521 Lancaster Avenue Richmond, KY 40475

Begley Building Press Box Roof Replacement THIS IS NOT AN ORDER

Non-Mandatory Pre-Bid Conference: April 8, 2019, 1:00 PM (ET) Outside of Begley Building (Beside Roy Kidd Statue on North East End of Football Field)Bid Opening: April 17, 2019, 10:00 AM (ET) Commonwealth Building, Room 1411

Eastern Kentucky University (EKU) hereby requests sealed bids for the materials, supplies, equipment or services set forth herein, subject to all conditions outlined in this Bid Package, including :

Invitation to Bid ................................................................................................................. 1

EKU General Terms and Conditions ...........................................................................19 Project Specifications .................................................................................................. 57 Project Drawings. ....................................................................................................... ..73

Note: If you require a larger format set of plans, you may download them from our website at: http://purchasing.eku.edu/solicitations . If you would like to purchase a hard copy set of project documents, contact Builder's Exchange of Kentucky at (502) 459-9800, or email at [email protected].

Page 2: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

EKU Invitation to Bid Return Original Copy of Bid To: Eastern Kentucky University Purchasing Division Room 1411, Commonwealth Bldg.

Eastern Kentucky University Bid No: 94-19 Issue Date: April 3, 2019Purchasing Officer: Justin IngramPhone: 859-622-1483 Project Name: Begley Press Roof Replacement Richmond, KY 40475

IMPORTANT: BIDS MUST BE RECEIVED BY: April 17, 2019, 10:00 AM (ET) Bids for competitive negotiation shall not be subject to public inspection until negotiations between the purchasing agency and all Offerors have been concluded and a contract awarded to the responsible offeror submitting the proposal determined in writing to be the most advantageous to the University, price and the evaluation factors set forth in the advertisement and solicitations for proposals will be considered. An award of contract may be made upon the basis of the initial written proposals received without written or oral discussions. Contracts resulting from this Bid must be governed by and in accordance with the laws of the Commonwealth of Kentucky. The University reserves the right to request proposal amendments or modifications after the bid receiving date. THE TERMS AND CONDITIONS OF THIS INVITATION TO BID INCLUDE ALL GENERAL CONDITIONS, AS SET FORTH BY EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN.

NOTICE Any agreement or collusion among Offerors or prospective Offerors, which restrains, tends to restrain, or is reasonably calculated to restrain competition by agreement to bid at a fixed price or to refrain from offering, or otherwise, is prohibited. Any person who violates any provisions of KRS 45A.325 shall be guilty of a felony and shall be punished by a fine of not less than five thousand dollars nor more than ten thousand dollars, or be imprisoned not less than one year nor more than five years, or both such fine and imprisonment. Any firm, corporation, or association who violates any of the provisions of KRS 45A.325 shall, upon conviction, may be fined not less than ten thousand dollars or more than twenty thousand dollars.

AUTHENTICATION OF BID AND STATEMENT OF NON-COLLUSION AND NON-CONFLICT OF INTEREST I hereby swear (or affirm) under the penalty for false swearing as provided by KRS 523.040: That I am the offeror (if the offeror is an individual), a partner, (if the offeror is a partnership), or an officer or employee of the bidding corporation having authority to sign on its behalf (if the offeror is a corporation); That the attached proposal has been arrived at by the offeror independently and has been submitted without collusion with, and without any agreement, understanding or planned common course of action with, any other Contractor of materials, supplies, equipment or services described in the Request for Proposal, designed to limit independent bidding or competition; That the contents of the proposal have not been communicated by the offeror or its employees or agents to any person not an employee or agent of the offeror or its surety on any bond furnished with the proposal and will not be communicated to any such person prior to the official closing of the RFP: That the offeror is legally entitled to enter into contracts with the Eastern Kentucky University and is not in violation of any prohibited conflict of interest, including those prohibited by the provisions of KRS 45A.330 to .340, 164.390, and That I have fully informed myself regarding the accuracy of the statement made above.

SWORN STATEMENT OF COMPLIANCE WITH CAMPAIGN FINANCE LAWS In accordance with KRS45A.110 (2), the undersigned hereby swears under penalty of perjury that he/she has not knowingly violated any provision of the campaign finance laws of the Commonwealth of Kentucky and that the award of a contract to a bidder will not violate any provision of the campaign finance laws of the Commonwealth of Kentucky.

CONTRACTOR REPORT OF PRIOR VIOLATIONS OF KRS CHAPTERS 136, 139, 141, 337, 338, 341 & 342 The Contractor by signing and submitting a proposal agrees as required by 45A.485 to submit final determinations of any violations of the provisions of KRS Chapters 136, 139, 141, 337, 338, 341 and 342 that have occurred in the previous five (5) years prior to the award of a contract and agrees to remain in continuous compliance with the provisions of the statutes during the duration of any contract that may be established. Final determinations of violations of these statutes must be provided to the University by the successful Contractor prior to the award of a contract.

CERTIFICATION OF NON-SEGREGATED FACILITIES The Contractor, by submitting a proposal, certifies that he/she is in compliance with the Code of Federal Regulations, No. 41 CFR 60-1.8(b) that prohibits the maintaining of segregated facilities.

SMOKE FREE ZONE POLICY The Offeror, by signing and submitting a Proposal, agrees to comply with the University’s Smoke Free Zone Policy. See:

http://policies.eku.edu/sites/policies.eku.edu/files/policies/tobacco-free_policy_bor_41414.pdf SUSTAINABILITY POLICY

The University is committed to reducing the adverse environmental impact of its purchasing decisions; it is committed to buying goods and services from contractors who share its environmental concern and commitment. The University encourages bidders to include in their responses economical and environmentally friendly products and service options that serve to minimize waste, reduce excess packing, recycle, reduce, reuse, prevent pollution, and/or offer resource efficiency. It’s the University’s goal to maximize environmental responsibility on its campuses.

SIGNATURE REQUIRED: This proposal cannot be considered valid unless signed and dated by an authorized agent of the Offeror. Type or print the signatory's name, title, address, phone number and fax number in the spaces provided. Offers signed by an agent are to be accompanied by evidence of his/her authority unless such evidence has been previously furnished to the issuing office.

Company Name: Authorized Signature: Address: Typed or Printed Name:

City, State, Zip: Title: Phone No: Federal ID No: Fax: Date:

8 BID FORMS

Page 3: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

1 BID FORMS

EASTERN KENTUCKY UNIVERSITY DIVISION OF PURCHASES & STORES

RICHMOND, KY

THIS IS NOT AN ORDER

INVITATION NUMBER: 94-19

PROJECT: Begley Building Press Box Roof Replacement

PURCHASING INSTRUCTIONS TO BIDDERS

1. Bids must be received in the Division of Purchases and Stores, Commonwealth Building, Room1411, Richmond, KY in a sealed envelope no later than 10:00 AM (ET) on April 17, 2019, atwhich time all bids received will be publicly opened and read in the Bid Opening Room.

2. Bid envelope shall be addressed as indicated herein below. No responsibility will attach to the Division ofPurchases the premature opening of, or the failure to open a bid not properly addressed or identified.

Address bids as follows:- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -Name & Address of Bidder Eastern Kentucky University

Division of Purchases & Stores Commonwealth Bldg. 14th Floor, Room 1411 Richmond, KY 40475

PRE-BID CONFERENCE: April 8, 2019, 1:00 PM (ET) Outside of Begley Building (Beside Roy Kidd Statue on North East End of Football Field)

Questions Due By: April 9, 2019, 4:00 PM (ET) – Submit all questions electronically to [email protected]

Temporary parking permits are available thru EKU Parking and Transportation, Commonwealth Hall, 2nd Floor 521 Lancaster Avenue, Richmond, KY 40475, (859) 622-1063. Please request parking permits at least (72) hours prior to campus visit.

3. No bidder may withdraw his bid for a period of thirty (30) calendar days after the date set for the opening ofbids. Clerical errors and omissions in the computation of the lump sum bid shall be cause for withdrawal ofthe bid without forfeit of the bid bond. Bids may be withdrawn in person only prior to the closing date of thereceipt of bids.

4. Bids, upon their receipt, are stamped showing the hour and date received. Bids received after the scheduledclosing time will not be considered, provided legal and acceptable bids have been received.

5. The right is reserved to reject any and all bids and to waive all informalities and/or technicalities where thebest interest of the University may be served.

6. Facsimile bids, or modification of bids by fax, are not permissible and/or not acceptable.

7. Bids may be rejected unless filled out in ink or typewritten and signed in ink.

8. For any clarification of this Invitation to Bid, contact:Justin Ingram, [email protected], 859-622-1483

Page 4: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

2 BID FORMS

ARTICLE 1 – INVITATION Bids are requested by the Division of Purchases & Stores from eligible firms for the furnishing of all labor, materials, tools, equipment, services, supplies, and related items necessary for the construction of Begley Building Press Box Rood Replacement for Eastern Kentucky University complete and in accordance with the terms, conditions, specifications as contained herein, and as shown on drawings and amended by any Addendum which may be issued.

ARTICLE II - METHOD OF BIDDING

Bidders shall submit bids as indicated in the form. No other method of bidding will be considered and the bidder must use the Form of Proposal which is included in and made a part of this Invitation. All data and other information requested in said Form of Proposal must be supplied.

ARTICLE 3 - AWARD OF CONTRACT

The award will be made based on BEST VALUE. In determining the lowest responsible and responsive bidder, the following elements will be considered: If the bidder involved maintains a permanent place of business, has adequate plant equipment to perform properly and expeditiously, suitable financial status to meet obligations incidental to the work and has appropriate technical experience. Such information as may be required to make an award determination shall be supplied by apparent low bidder. (A) The "Owner" reserves the right to reject any and all bids to waive all informalities and/or

technicalities of a bid when in the judgment the best interest of Eastern Kentucky University maybe served.

(B) In the event the bidder's proposal is accepted by the owner and such bidder shall fail to execute thecontract and to furnish satisfactory performance bond within ten (10) calendar days from the date ofnotification of the award of the contract, the owner may at its option, determine that the awardee hasabandoned the contract. Thereupon the proposal shall become null and void and the bid guaranteewhich accompanied it shall be forfeited to and become the property of the owner as liquidateddamaged from such failure. If the bidder shall execute the contract and furnish satisfactory bond, thebid guarantee will be returned to the bidder by the owner.

(C) That a contract is legally entered into will be indicated by the issuance and release of the EasternKentucky University purchase order.

ARTICLE 4 - INSURANCE

The contractor shall provide and include in his bid price the cost of the following minimum insurance coverage: (a) Workman’s Compensation $1,000,000 (b) General Liability $1,000,000 ($2,000,000 Aggregate) (c) Business Automobile Liability $1,000,000 (each occurrence, any auto owned, hired, or borrowed)

Contractor agrees to furnish Certificates of Insurance for each insurance policy to the Purchasing Official. Eastern Kentucky University, its regents, and employees must be added as Additional Insured on the General Liability policies with regard to the scope of this Contract. Any deductibles or self-insured retentions in the insurance policies must be paid by and are the sole responsibility of the Contractor. Coverage is to be primary and non-contributory with other coverage, if any, purchased by the University. All required insurance policies must include a Waiver of Subrogation in favor of Eastern Kentucky University, its regents, and employees.

ARTICLE 5 –CONSTRUCTION AND SAFETY DEVICES

Refer to Eastern Kentucky University’s General Terms and Conditions below.

ARTICLE 6 - TAXES, WORKMEN'S COMPENSATION, ETC.

The contractor shall be required to accept liability, make payment and include in bid amount all payroll taxes, sales and use tax, and all other taxes or deductions required by federal, state, or local laws such as old age pensions, social security or annuities measured by wages. Provisions of the current Kentucky Sales or Use Tax must be included in the bid amount and paid by the contractor.

Page 5: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

3 BID FORMS

ARTICLE 7 - INSPECTION OF WORK

Refer to Eastern Kentucky University’s General Terms and Conditions below.

ARTICLE 8 - PERMITS AND CODES

Refer to Eastern Kentucky University’s General Terms and Conditions below.

ARTICLE 9- ADDENDA

Any Addenda or Instruction to Bidder issued by the Division of Purchases prior to the time for receiving bids shall be covered in thereof. Such Addenda shall be acknowledged in the Bid Proposal. No instructions or changes shall be binding unless documented by a proper and duly issued Addendum.

Eastern Kentucky University is entitled to exemption from Federal Excise Tax. Exemption certificates will be furnished to cover excise tax exemption where applicable and when requested by the contractor.

ARTICLE 10 - WITHDRAWAL OF BIDS

(a) Prior to closing date for receipt and opening of bids, any bidder may withdraw his bid in persononly, at any time prior to the scheduled time for closing and receipt of bids.

(b) After receipt and opening of bids, withdrawal of bids will not be permitted for a period of thirty(30) Calendar days from the date of receipt and opening of bids.

ARTICLE 11 - OR EQUAL

If any material or equipment and/or specifications, unless specifically designated "no substitution" appear in this Invitation which restrict any bidder from bidding whose product is equal in performance, construction, efficiency, etc., to that specified, then, and in that event the bidder may submit a bid on the lowest and best bid here from. The burden of proof of equality shall be the responsibility of the bidder. If the architect/engineer judges the material or equipment not equal to that named in the specifications, the bidder/contractor shall provide material or equipment that is judged to be in compliance with the specifications. The architect/engineer's decision shall be final.

ARTICLE 12 - ALTERNATES

The owner reserves the right to reject any or all alternate bids if provided for in the bid documents. The determination as to the responsive and responsible bid will be made on the basis of the lump sum base bid plus and/or minus any alternate that may be accepted by the owner. Alternates to be used in sequence set forth in the proposal if considered for acceptance.

ARTICLE 13 - AUT HENTICAT ION OF BID AND STATEMENT OF NON-COLLUSION AND NON- CONFLICT OF INTEREST

This document or the Form of Proposal document where applicable, must be executed and signed for the bid to be valid.

ARTICLE 14 - LIQUIDATED DAMAGE (IF APPLICABLE)

See schedule of liquidated damage in attached Project specifications. The contractor affected will be held responsible for any loss to the owner on account of unnecessary delays or failure on his part to prosecute his work in the proper manner.

ARTICLE 15 - BID AND PERFORMANCE AND PAYMENT BOND

(a) Bids shall be accompanied by a bid guarantee of not less than five percent (5%) of the amount of theBase Bid executed by a Surety Company authorized to do business in the state of Kentucky.(Certified check is acceptable)It is agreed in the event that this proposal is accepted by the owner and the contractor shall fail toexecute a contract within ten (10) consecutive calendar days from the date of notification of theAward of Contract, the owner shall determine that the contractor has abandoned the contract;thereupon, the proposal shall become null and void, and the bid guarantee, check, or bid bond whichaccompanied it shall be forfeited and become the property of the owner as liquidated

Page 6: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

4 BID FORMS

damages for such failure and no protest pursuant to such action will be allowed. (b) The contractor shall furnish a surety bond in an amount equal to one hundred percent (100%) of the

contract price as security for the faithful performance of this contract and for the payment of allpersons performing labor, including payment of all unemployment contributions which become dueand payable under the Kentucky Unemployment Insurance Law furnishing materials in connectionwith this contract.

(c) This bond and all insurance coverage required by this Invitation and Laws of this State shall beexecuted by a Surety Company authorized to do business in the state of Kentucky

(d) There shall be an endorsement in each policy, reading as follows: "It is hereby agreed that in eventof a claim arising under this policy, the company will not deny liability by reason of the insuredbeing a state, county, Municipal Corporation or governmental agency."

ARTICLE 16 - GENERAL GUARANTY

Refer to Eastern Kentucky University’s General Terms and Conditions below.

ARTICLE 17 - CHANGES IN THE WORK

Refer to Eastern Kentucky University’s General Terms and Conditions below.

ARTICLE 18 - INDEMNITY

Refer to Eastern Kentucky University’s General Terms and Conditions below.

ARTICLE 19 - EMPLOYMENT PRACTICE

(a) The contractor, per State Executive Order 72-51, dated January 18, 1972, shall register from time totime with the State Department Service Office nearest the construction a complete list of all jobrequirements and positions necessary to perform this contract.

(b) Where persons referred to the contractor, by the State Employment Service, are found to be qualifiedthe contractor is urged to utilize and employ said persons for such jobs.

(c) It is the policy of Eastern Kentucky University to utilize minority vendors and subcontractorswhenever possible in order to help bring them into the main stream of the American economy.Therefore, the contractor, when looking for subcontractors, should make full faith efforts to locateminority business persons. For assistance in identifying minority vendors or subcontractors, thecontractor may contact the Kentucky Procurement Assistance Program; 500 Metro Street; CapitalPlaza Tower, 23rd Floor; Frankfort, Kentucky 40601-1978; telephone 800.838-3266 or 502-564-2064; fax (502)-564-5932, or e-mail [email protected].

(d) Apprentices shall be permitted to work only under an apprenticeship agreement approved by theKentucky Supervisor of Apprenticeship and by the Kentucky Apprenticeship Council, which isrecognized by the Bureau of Apprenticeship and Training, United States Department of Labor.

ARTICLE 20 - NON-DISCRIMINATION IN EMPLOYMENT

During the performance of this contract, the contractor agrees as follows: (a) The contractor will not discriminate against any employee or applicant for employment because of

race, creed, color, or national origin. The contractor will take affirmative action to ensure thatapplicants are treated during employment without regard to their race, creed, color, or national origin.Such action shall include, but not be limited to the following: employment, upgrading, demotion, ortransfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms ofcompensation; and selection for training, including apprenticeship. The contractor agrees to post inconspicuous places, available to employees and applicants for employment, notices to be provedsetting forth the provisions of this non-discrimination clause.

(b) The contractor will, in all solicitation or advertisements placed by or on behalf of the contractor, statethat all qualified applicants will receive consideration for employment without regard to race, creed,color, or national origin.

(c) The contractor will send to each labor union or representative of workers with which he has acollective bargaining agreement or other contracts or understanding, a notice to be provided advisingthe said labor union or worker's representative of the contractor's commitment under this section, andshall post copies of the notice in conspicuous places available to employees and applicants foremployment. The contractor will take such action with respect to any subcontractor

Page 7: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

6 BID FORMS

or purchase order as the administrating agency may direct as a means of enforcing such provisions, including sanctions for noncompliance. In case the work to be performed is paid for in whole or in part with funds obtained from the federal government or borrowed on the credit of the federal government pursuant to a grant, loan, insurance or guarantee, during the performance of this contract, the contractor, in addition, agrees to the following:

(d) The contractor will comply with all provisions of Executive Order No. 11246 of September 24,1965, or as amended, and by the rules, regulations and relevant orders of the Secretary of Labor.

(e) The contractor will furnish all information and reports required by Executive Order No. 11246 ofSeptember 24, 1965, or as amended, and by the rules, regulations, and orders of the Secretary ofLabor, or pursuant thereto and will permit access to his books, records, and accounts by theapplicable federal agency and/or agencies and the Secretary of Labor for purpose of investigation toascertain compliance with such rules, regulations, and orders.

(f) In the event of the contractor's non-compliance with non- discrimination clauses of this contract orwith any such rules, regulations or orders, this contract may be canceled, terminated or suspended inwhole or in part and the contractor may be declared ineligible for further government contracts orfederally-assisted construction contracts, in accordance with procedures authorized in ExecutiveOrder No. 11246 of September 24, 1965, or as amended, and by the rules, regulations and orders ofthe Secretary of Labor, or as otherwise provided by law.

(g) The contractor will include the provisions of paragraphs (a) through (g) in every subcontract orpurchase order unless exempted by rules, regulations or orders of the Secretary of Labor, issuedpursuant to Section 204 of Executive Order No. 11246 of September 24, 1965, so that suchprovisions will be binding upon each subcontractor or vendor. The contractor will take such actionwith respect to any subcontract or purchase order as the federal agency or Secretary of Labor maydirect as a means of enforcing such provisions, including actions for non-compliance.Provided, however, that in the event the contractor becomes involved in, or is threatened with,litigation with a subcontractor or vendor as a result of such direction by the federal agency orSecretary of Labor, the contractor may request the United States to enter into such litigation to protectthe interest of the United States.

ARTICLE 21 - PUBLIC WORKS

21.1 Under KRS337 the University or any State Agency shall not have the authority to require any employer to pay to an employee a certain wage or fringe benefit other than as determined by the employer and or hourly rates (Minimum Wage) as established by Federal, State, Local or Agency itself.

22.2 DAVIS BACON ACT (Applicable to federally funded construction projects exceeding $2,000) Contractor agrees to pay wages to mechanics and laborers at a rate not less than the prevailing wages specified in a wage determination made by the Secretary of Labor. Supplier agrees to pay wages and meet the other requirements as specified by Davis-Bacon Act, as amended (40 U.S.C. 3141-3148) as supplemented by the Department of Labor regulations (29 CFR Part 5). Supplier acknowledges that University affiliated entity’s decision to make a Contract with Supplier is conditioned upon the acceptance of the wage determination.

ARTICLE 22- RECIPROCAL PREFERENCE

In accordance with KRS 45A.494, a resident Offeror of the Commonwealth of Kentucky shall be given a preference against a non-resident Offeror. In evaluating proposals, the University will apply a reciprocal preference against an Offeror submitting a proposal from a state that grants residency preference equal to the preference given by the state of the nonresident Offeror. Residency and non-residency shall be defined in accordance with KRS 45A.494 (2) and 45A.494 (3), respectively. Any Offeror claiming Kentucky residency status shall submit with its proposal the notarized affidavit affirming that it meets the criteria as set for in the above referenced statute.

ARTICLE 23 – SERVICE AND SUPPORT PERSONNEL

The University reserves the right of acceptance of all personnel assigned by the Offeror under this Contract. All company personnel of the Successful Offeror must be in appropriate company uniform which includes the company name visibly displayed at all times while on the campus of the University, and in all University buildings. The personnel must be cordial, well-groomed, and cognizant of the fact that they may be entered student living buildings. If, for any reason, the University believes that these guidelines are not being followed, the University will request intervention from appropriate supervisory personnel. If inappropriate behavior occurs,

Page 8: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

6 BID FORMS

the University shall be entitled to a change in personnel serving the campus.

The Successful Offeror agrees that it will company with the University policy regarding registered sex offenders, and shall not knowingly permit any employee who is a registered sex offender to service the Grand Campus, University residence halls, Model Laboratory School, the basement of the Burrier Building where the Child Development Center is currently located, or any areas of campus or University’s buildings. The Successful Offeror will provide the University with verification of all assigned personnel background check clearance.

ARTICLE 24 - DISBARMENT

Vendor’s signature on this solicitation response certifies that the vendor, and where applicable subcontract vendor, or any other person performing service under this agreement (a) is not now nor have ever been excluded, suspended, disbarred or otherwise deemed ineligible to participate in governmental procurement or other programs (b) and if disbarred, suspended or excluded during the life of the contract, the vendor will notify the University buyer of record within seventy two(72) hours of the vendor becoming aware of the governmental ineligibility.

ARTICLE 25 - KEY EVENT DATES

KEY EVENT DATES DATE TIME PLACE

Pre-Bid Meeting 04/8/19 1:00 PM ET

Questions Deadline 04/9/19 04:00 PM ET

Bid Opening 04/17/19 10:00 AM ET

Begley Building (Near Roy Kidd Statue)

[email protected]

Commonwealth Bldg., Rm 1411

Project Notes: - Final Date for Completion: 08/01/19

Liquidated Damages: - $190 until Final Completion

- On a separate sheet to be included in your sealed bid, as requested in the Bid Specifications, please provide a list of five (5) similar jobs in size and complexity. (Please provide current phone number and name of client’s contact.) These documents must be provided in order to be considered.

Page 9: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

11 BID FORMS

BIDDER'S CHECK LIST

The following checklist is provided for the convenience of both you and Eastern Kentucky University to help eliminate errors or omissions which may render your bid non-responsive. Please check all appropriate boxes and submit this page with your bid.

1. Sworn Statement Regarding Campaign Finance Laws & Non Collusion.

2. Affidavit Regarding Workers’ Compensation Insurance. (Notarized)

3. Vendor Report of Prior Violations of KRS Chapters, 136, 139, 141,337, 338, 341, and 342.

4. Bidder’s Qualifications.

5. Bid Guaranty in the amount of no less than five percent (5%) of theTOTAL BID AMOUNT. (Vendor Provided)

6. List of Proposed Subcontractors (Vendor Provided)

7. Vendor Identification Form

8. Vendor Insurance Form (ACORD)

9. Resident Bidder Status Affidavit. (Notarized)

10. Bid Sheet

11. Performance Bond (To be provided at time of award.)

12. Payment Bond (To be provided at time of award.)

Page 10: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

9 BID FORMS

SWORN STATEMENT REGARDING CAMPAIGN FINANCE LAWS

PURSUANT TO KRS 45A.110 AND KRS 45A.115, AS AMENDED, A DETERMINATION OF RESPONSIBILITY OF A BIDDER OR OFFEROR CANNOT BE MADE UNTIL THE BIDDER OR OFFEROR PROVIDES A SWORN STATEMENT THAT HE HAS NOT KNOWINGLY VIOLATED ANY PROVISION OF THE CAMPAIGN FINANCE LAWS OF THE COMMONWEALTH AND THAT THE AWARD OF A CONTRACT TO A BIDDER OR OFFEROR WILL NOT VIOLATE ANY PROVISION OF THE CAMPAIGN FINANCE LAWS OF THE COMMONWEALTH. TO COMPLY WITH THESE STATUTES THE SWORN STATEMENT REGARDING CAMPAIGN FINANCE LAWS INCLUDED WITH THIS INVITATION FOR BID SHOULD BE SIGNED AND RETURNED WITH YOUR BID. THESE STATUTES CURRENTLY READ AS FOLLOWS:

KRS 45A.110:

(1) A written determination of responsibility of a bidder or offeror shall be made and it shall be made in accordancewith administrative regulations promulgated by the secretary of Finance and Administration Cabinet. Areasonable inquiry to determine the responsibility of a bidder or offeror may be conducted. The failure of abidder or offeror to promptly supply information in connection with such an inquiry may be grounds for adetermination of non-responsibility with respect to such a bidder or offeror.

(2) A written determination of responsibility of a bidder or offeror shall not be made until the bidder or offerorprovides the Secretary of the Finance and Administration Cabinet with his sworn statement made underpenalty of perjury that he has not knowingly violated any provisions of the campaign finance laws of theCommonwealth and that the award of a contract to a bidder or offeror will not violate any provision of thecampaign finance laws of the Commonwealth. “Knowingly” means, with respect to conduct or to acircumstance described by a statute defining an offense, that a person is aware or should have been aware thathis conduct is of that nature or that the circumstance exists.

(3) Except as otherwise provided by law, information furnished by a bidder or offeror pursuant to this section maynot be disclosed outside of the Division of State Purchasing or the purchasing agency administering the contractwithout prior written consent of the bidder or offeror.

KRS 45A.115:

Eastern Kentucky University at this time does not prequalify suppliers. Refer to KRS 45A.115 for qualification requirements for bid opportunities with the Finance and Administration Cabinet.

(SIGNATURE)

(TITLE)

(NAME OF COMPANY)

State of ) County of ) The foregoing statement was acknowledged and sworn to before me this

day , 20 , by

(Title) (Company).

Notary Public My commission expires:

Page 11: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

12 BID FORMS

COMMONWEALTH OF KENTUCKY AFFIDAVIT REGARDING WORKER’S COMPENSATION

INSURANCE AND UNEMPLOYMENT INSURANCE

Pursuant to KRS 45A.480, the undersigned hereby swears or affirms, under penalty of perjury, that all contractors and subcontractors employed, or that will be employed, under the provisions of this contract shall be in compliance with the requirements for worker’s compensation insurance under KRS Chapter 342 and unemployment insurance under established KRS Chapter 341.

(SIGNATURE)

(TITLE)

(NAME OF COMPANY)

State of )

County of )

The foregoing statement was acknowledged and sworn to before me this

day , 20 , by

(Title) (Company).

Notary Public

My commission expires:

Page 12: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

13 BID FORMS

COMMONWEALTH OF KENTUCKY

VENDOR REPORT OF PRIOR VIOLATIONS OF KRS CHAPTER

136, 139, 141, 337, 338, 341 AND 342

Pursuant to 1994’s Senate Bill 258, the Bidder/Offeror shall reveal to the Commonwealth, prior to this award of a contract, any final determination of a violation by the contractor within the previous five (5) year period of the provisions of KRS Chapters 136, 139, 141, 337, 341, and 342.

For the purpose of complying with the provisions of Senate Bill 258, please list any final determination (s) of violation (s) of KRS Chapters 136, 139, 141, 337, 338, 341 and 342, which have been rendered against the bidder or Offer within the five (5) years preceding the award of this contract.

Please include the date of the determination and the state agency issuing the determination.

KRS VIOLATION DATE STATE AGENCY

The Contractor is further notified that 1994’s Senate Bill 258 requires that for the duration of this contract, the Contractor shall be in continuous compliance with the provisions of KRS Chapters 136, 139, 141, 337, 338, 341 and 342, which apply to the Contractor’s operations. Senate Bill 258, further provides that the Contractor’s failure to reveal a final determination of a violation of KRS Chapters 136 , 139, 141, 337, 338, 341, and 342, or failure to comply with the above-cited statutes for the duration of the contract, shall be grounds for the Commonwealth’s disqualification from eligibility to bid or submit proposals to the Commonwealth for a period of two (2) years.

Page 13: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

14 BID FORMS

BIDDER'S QUALIFICATIONS

The Bidder’s qualifications are required by the Owner to be submitted as set forth herewith:

1. This firm is a Corporation or a Partnership or a Proprietorship .

2. A Permanent place of business is maintained at:

STREET CITY STATE ZIP CODE

TELEPHONE NUMBER AREA CODE

3. In the event the contract is awarded, the undersigned, Surety Bonds will be furnished by:

4. Experience of Contractor on other similar work: List contact information for list projects.

5. We now have the following jobs under contract and bonded:

JOB LOCATION $ TOTAL CONTRACT PERCENT COMPLETED

Page 14: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

TAXPAYER IDENTIFICATION NUMBER REQUEST

Eastern Kentucky University requires a Federal Tax Identification number or Social Security number for all vendors or persons doing business with the University in order to comply with Federal Regulations and tax reporting requirements. Completion of this vendor form does not guarantee receipt of competitive bid solicitations. If you are interested in obtaining University solicitations, please visit http://purchasing.eku.edu/bids-and-quotes IF SENDING A W-9, PLEASE RETURN THIS FORM ALSO. For your convenience, you may return the information one of the following ways: FAX: Vendor File @ 859-622-2170 Mail:

EMAIL: [email protected]

Phone # (859)622-2246

Purchasing Division Eastern Kentucky University Commonwealth Bldg., 14th Floor,Room 1401 521 Lancaster Avenue Richmond, Kentucky 40475

Please type or print legibly VENDOR INFORMATION Name of Firm * (Company or Individual) Phone Number * Make Checks Payable To *

Address * Fax Number * Payment Address *

Address Web Site Address or E-mail Payment Address

Address Vendor Representative Name on Invoice *

City * State * Zip* Federal Tax ID Number * Social Security Number *

Willing to accept ACH payments * Yes No Bank Name & Routing # Bank Account #

Willing to accept credit card payments*

Yes No

Payment Terms *

Type of Ownership (Check Appropriate Box(es)) * Business Classification (Check Appropriate Box(es)) * (1) Individual/Sole Proprietorship (2) Partnership (3) Corporation-Incorporated in

(State) (4) Non-profit/Education

(5) Non-Resident Alien(6) Exempt from backup

withholding Other:

(SM) Small Business (LG) Large Business (CT) In County (MN) Minority Owned (WO) Women Owned

(SD) Small Disadvantaged Business (GA) Government Agency (NP) Non-Profit (AL) Alumni Owned (HZ) Hub Zone Small Business Other (Specify)

*Required Fields Business Classification Reference Links: www.ccr.gov/sizestandard.asp, https://eweb1.sba.gov/hubzone/internet/general/whoweare.cfm, and

http://app1.sba.gov/faqs/faqindex.cfm?areaID=11 Printed Name of Authorizing Official:

Authorized Signature: Date:

*REGISTRATION Any foreign corporation (outside the State of Kentucky) must obtain a certificate of authority from the Secretary of State as is required by KRS 271B.15-010 Certificate #: (https://secure.kentucky.gov/sos/ftbr/Welcome.aspx)

• Claimed exemption: Any “person” (business or individual) making retail sales in the state are to be registered to collect Kentucky sales and use tax. If the foreign individual (or business) is making retail sales they should be registered for Kentucky sales and use tax purposes by completing a Tax Registration Application (form 10A100), available at the link below. If they are under contract to perform services that do not include the sale of tangible personal property or digital property, or do not perform services subject to tax per KRS 139.200 (such as admissions, provision of telecommunication services, sewer services, and so on), then they are not required to register per .KRS 14A.9-010-14A.9-090

• Consumer Use Tax Account number: (http://revenue.ky.gov/) • Sales Tax Account Number:

Federal Debarment Status By checking the box above, you certify that your company and its principals have not been disbarred, suspended, proposed for debarment, declared ineligible, are not in the process of being disbarred or are voluntarily excluded from doing business with a federal department or agency of the federal government.

CERTIFICATION Under penalties of perjury. I certify that: 1. The number shown on this form is my correct taxpayer identification number (or I am waiting for a number to be issued to me) and 2. I am not subject to backup withholding because:(a) I am exempt from backup withholding, or (b) I have not been notified by the Internal Revenue Service (IRS)

that I am subject to backup withholding as a result of a failure to report all interest or dividends, or (c) the IRS has notified me that I am no longer subject to backup withholding, and

3. I am a U. S. person (including a U.S. resident alien). Certification instructions. You must cross out item 2 above if you have been notified by the IRS that you are currently subject to backup withholdings because you

have failed to report all interest and dividends on your tax return. For real estate transactions, item 2 does not apply. For mortgage interest paid, acquisition or abandonment of secured property, cancellation of debt, contributions to an individual retirement arrangement (IRA), and generally, payments other than interest and dividends, you are not required to sign the certification, but you must provide your correct Taxpayer Identification Number.

Signature of U.S. Person Date

Page 15: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

16 BID FORMS

Bid #: 94-19

REQUIRED AFFIDAVIT FOR BIDDERS, OFFERORS AND CONTRACTORS CLAIMING RESIDENT BIDDER STATUS

FOR BIDS AND CONTRACTS IN GENERAL: The bidder or offeror hereby swears and affirms under penalty of perjury that, in accordance with KRS 45A.494(2), the entity bidding is an individual, partnership, association, corporation, or other business entity that, on the date the contract is first advertised or announced as available for bidding:

1. Is authorized to transact business in the Commonwealth;2. Has for one year prior to and through the date of advertisement

a. Filed Kentucky corporate income taxes;b. Made payments to the Kentucky unemployment insurance fund established in

KRS 341.49; andc. Maintained a Kentucky workers’ compensation policy in effect.

The BIDDING AGENCY reserves the right to request documentation supporting a bidder’s claim of resident bidder status. Failure to provide such documentation upon request shall result in disqualification of the bidder or contract termination.

Signature Printed Name

Title Date

Company Name

Address

Subscribed and sworn to before me by (Affiant) (Title)

of this day of ,20 . (Company Name)

Notary Public

[seal of notary] My commission expires:

Page 16: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

10 BID FORMS

FORM OF PROPOSAL-BID SHEET

BID: 94-19

PROJECT NAME: Begley Building Press Box Roof Replacement

LUMP SUM BASE BID:

The Bidder agrees to furnish all materials, supplies, and services required to complete the above referenced job for Eastern Kentucky University, in accordance with the drawings, specifications and contract documents, and any duly issued Addenda for the LUMP SUM BASE BID AMOUNT set forth below:

Bidder’s Name:

Dollars (USE WORDS)

and Cents

($ ).

Alternate (if applies): ($ ).

(USE FIGURES)

The Bidder, in compliance with your Invitation to Bid # 94-19 and having carefully examined the drawings and complete contract documents as defined in the specifications hereby proposes to furnish all labor, materials, supplies, and services required to perform the specifics of this project within the time set forth therein and for the stated lump sum bid amount.

The Bidder hereby acknowledges receipt of the following Addenda:

(IF NO ADDENDUM HAS BEEN ISSUED AND RECEIVED, INSERT THE WORD, “NONE”)

ADDENDUM NO. DATED

ADDENDUM NO. DATED

ADDENDUM NO. DATED

Page 17: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

EASTERN KENTUCKY UNIVERSITY BID # 94 - 19

LIST OF MATERIALS AND EQUIPMENT

Every item listed under the different phases of construction must be clearly identified so that the Owner will definitely know what the bidder proposes to furnish. Bidders are hereby advised that this list shall be required to be filled out completely by the apparent low bidder within TWENTY-FOUR (24) HOURS from the close of the official reading of the bids.

The above requirement does not preclude any bidder from submitting this list, fully executed, at the time the bids are submitted. The use of the manufacturer's / dealers name only, or stating "as per plans and specifications", will not be considered as sufficient identification. Where more than one "Make or Brand" is listed for any one item, the Owner has the right to select the one to be used.

Failure to submit a proper list may result in rejection of the Bidder's Proposal.

ITEMS MANUFACTURER / SUPPLIER

Siplast (or approved equivalent) Johns Manville (or approved equivalent)Garland (or approved equivelant)

Page 18: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

EASTERN KENTUCKY UNIVERSITY BID# 94 - 19

LIST OF SUBCONTRACTORS

List subcontractors you intend to hire as a part of this project and the work they will be performing.

List on the lines below each major branch of work and major material category for this project and the subcontractor involved with that portion of work. If the branch of work is to be done by the General Contractor, so indicate.

The listing of more than one subcontractor in a work category may invalidate the bid.

The listing of the bidder as the subcontractor for a work category certifies that the bidder has in current employment, skilled staff and necessary equipment to complete that category. The Project Team will evaluate the ability of all listed subcontractors to complete the work. Listing of the bidder as the subcontractor may invalidate the bid should the architect’s review indicate bidder does not have skilled staff and equipment to complete the work category at the time the bid was submitted.

The following section to be completed and submitted within (24) hours.

SECTION SUBCONTRACTOR

(If Applicable)

Page 19: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Eastern Kentucky University General

Conditions

Page 20: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Revised 11-18-18

EASTERN KENTUCKY UNIVERSITY GENERAL CONDITIONS

TABLE OF CONTENTS

1. Definitions of Terms ....................................................................................................................4

2. Intent and Interpretation ...............................................................................................................5

3. The Architect ...............................................................................................................................7

4. Conduct ........................................................................................................................................8

5. Tobacco-Free Campus .................................................................................................................9

6. Safety ...........................................................................................................................................9

7. Green Purchasing Policy ............................................................................................................10

8. Recycling and Waste Management Policy ................................................................................10

9. Parking .......................................................................................................................................10

10. Traffic Control .........................................................................................................................11

11. Pedestrian and Property Protection ..........................................................................................11

12. Concrete and Landscaping requirements .................................................................................11

13. Hazardous Material ..................................................................................................................11

14. Site Conditions .........................................................................................................................12

15. Facilities Usage ........................................................................................................................12

16. Occupancy .................................................................................................................. 12

17. General Work Hours ................................................................................................................13

18. Storage and Staging .................................................................................................................13

Page 21: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

2 General Conditions

19. Signs .........................................................................................................................................13

20. Administrative..........................................................................................................................13

21. Subcontractor ...........................................................................................................................13

22. Changes in the Work/Change Orders ......................................................................................14

23. Key Checkout Procedure .........................................................................................................16

24. Site Visit ............................................................................................................................. 16

25. Measurements ..........................................................................................................................16

26. Labor and Materials .................................................................................................................16

27. Indemnification ........................................................................................................................17

28. Insurance ..................................................................................................................................17

29. Performance and Payment Bonds ............................................................................................19

30. Claims by the Contractor/Concealed Conditions/Disputes......................................................19

31. Liens .........................................................................................................................................21

32. Assignments ........................................................................................................................ 21

33. Separate Contracts ...................................................................................................................21

34. Cash Allowances ......................................................................................................................21

35. Schedules .................................................................................................................................22

36. Delays and Extensions of Time ...............................................................................................22

37. Shop Drawings; Submittals......................................................................................................23

38. Supervision and Construction Procedures ...............................................................................23

39. Payment....................................................................................................................................25

Page 22: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

3 General Conditions

40. Quality of Work .................................................................................................................. 27

41. Code Compliance .....................................................................................................................28

42. Inspection, Tests, Permits, and License Fees ...........................................................................28

43. Correction of Work ..................................................................................................................29

44. Suspension of Work .................................................................................................................29

45. Termination ..............................................................................................................................30

46. Project Completion and Record Drawings ..............................................................................32

47. Miscellaneous Provisions Regarding Contractor’s Work ........................................................34

48. Davis-Bacon Act ......................................................................................................................34

49. Apprentices ..............................................................................................................................35

50. Nondiscrimination in Employment ..........................................................................................35

51. Affirmative Action: Reporting Requirements .........................................................................36

52. Access to Records ....................................................................................................................36

53. Campus Map ............................................................................................................................37

Page 23: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

4 General Conditions

1. Definitions of Terms. Whenever used in these General Conditions or in other ContractDocuments, the following terms have the meaning indicated, which are applicable to both the singular and plural thereof: 1.1 Architect is the person or entity, either architect, engineer, or consultant, who is

identified as such in the Contract Documents and on the drawings or any replacement architect, engineer, or consultant identified by the Owner.

1.2 Certification of Payment is the Owners Progress Payment form, Invoice and Receiving Report for Technical Services and Construction Contracts.

1.3 Change Order means a written order to the Contractor from the Owner and the Architect after execution of the Contract, which directs a change in the Work and may include a change in the Contract Price or the Contract Completion Time, or any combination thereof.

1.4 Contract is the legal relationship, duties and obligations between the Owner and Contractor as shown by the Contract Documents for the Project.

1.5 Contract Completion Time is the number of calendar days between the Date of Commencement and the dates set for Substantial Completion and Final Completion of the Work. This includes any adjustments established in the Contract between the Owner and Contractor.

1.6 Contract Documents include the Invitation for Bids, the Instructions to Bidders, the Payment and Performance Bonds, the General Conditions, the Special or Supplemental Conditions, the drawings, specifications, solicitation addenda, the contractors response to the solicitation, any written clarification of the response, the award document containing the Agreement between Owner and Contractor, and modifications issued after execution of the Contract. Modifications include (1) Change Orders issued as provided in Article 22, and (2) Field Orders for minor changes in the work issued by the Architect as provided in Article 22. Documents not included or expressly contemplated in this Paragraph, 1.6, do not, and shall not, form any part of the Contract between the Owner and the Contractor.

1.7 Contract Sum means the sum stated in the Contract including any authorized adjustments thereto and is the total amount payable by the Owner to the Contractor for the performance of the Work under the Contract Documents.

1.8 Contractor means the person or entity with whom the Owner has executed the Contract for construction.

1.9 Date of Commencement is the date specified in the Contract as the date upon which the Contractor is authorized to begin work.

1.10 Direct Expenses is defined as “All items of expenses directly incurred by or attributable to a specific project, assignment or task” and “Direct costs consist of direct materials, direct labor, subcontract costs, and other miscellaneous direct costs such as bonding and equipment rentals, that are directly related to and can be specifically attributed to an individual contract.”

1.11 Drawings are the graphic and pictorial portions of the Contract Documents, wherever located and whenever issued, showing the design, location and dimensions of the Work, generally including plans, elevations, sections, details, schedules and diagrams.

1.12 Extra Work is Work not part of the existing Contract Documents which is being added to the Contract by Change Order.

1.13 Field Order is a written order issued by the Architect which clarifies or interprets the Contract Documents, or orders minor changes in the Work which does not require a change under Article 22.

1.14 Final Completion is defined as the Work being acceptable under the Contract Documents and the Contract fully performed in accordance with the terms and

Page 24: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

5 General Conditions

conditions of the Contract Documents and the entire payment balance due the Contractor is due and payable.

1.15 Final Completion Date shall have the meaning as described to it in Paragraph 46.3.

1.16 Notice of Intent to Award is a written letter issued to the apparent successful Contractor after acceptance of bid price, unit prices, subcontractors and equipment and materials to inform them of such acceptance and request the required additional documentation to initiate the Contract. This is NOT an authorization to proceed.

1.17 Owner means Eastern Kentucky University, acting through the Division of Capital Construction and Project Administration.

1.18 The Project is the total construction of which the Work performed under the Contract Documents may be the whole or a part and which may include construction by the Owner or by separate Contractors.

1.19 Resident Observer means an individual who has a direct contract with the Architect to observe and report on activities at the work site. A Resident Observer employed by the Architect is not authorized to serve as the Owners Representative, unless so designated by the Owner in writing.

1.20 Retainage means money earned by a contractor for work accepted by the Owner, but withheld to ensure proper performance by the contractor

1.21 Shop Drawings means drawings, completion diagrams, schedules, and other data specially prepared for the Work by the Contractor or any Subcontractor, lower tier subcontractors, manufacturer, supplier, or distributor to illustrate some portion of the Work.

1.22 Subcontractor means the person or entity having a direct contract with the Contractor for the performance of a part of the Work.

1.23 Substantial Completion is the point at which, as certified in writing by the Architect, the Project is at a level of completion in strict compliance with the Contract, and necessary approval by public authorities has been given, such that the Owner or the Agency can enjoy beneficial use or occupancy and can use, operate and maintain (the Owner has received all required warranties and documentation) it in all respects, for its intended purpose. Partial use or occupancy of the Project shall not result in the Project being deemed substantially complete and such partial use or occupancy shall not be evidence of Substantial Completion.

1.24 Substantial Completion Date shall have the meaning as described to it in Paragraph 46.2.

1.25 The Work includes the construction and services required by the Contract Documents, whether completed or partially completed, and includes all labor, supervision, materials, equipment, services, and things provided or to be provided by the Contractor to fulfill the Contractor’s obligations.

2. Intent and Interpretation2.1 Anything that may be required, implied or inferred by the documents which make up

the Contract, or any one or more of them, shall be provided by the Contractor for the Contract Sum;

2.2 Nothing contained in the Contract Documents shall create, nor be interpreted to create, privity or any other relationship whatsoever between the Owner and any person except the Contractor;

2.3 When a word, term, or phrase is used in the Contract Documents, it shall be interpreted or construed first, as defined herein; second, if not defined, according to its generally accepted meaning in the construction industry; and third, if there

Page 25: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

6 General Conditions

is no generally accepted meaning in the construction industry, according to its common and customary usage;

2.4 The words “include”, “includes”, or “including”, shall be deemed to be followed by the phrase, “without limitation”.

2.5 The specification herein of any act, failure, refusal, omission, event, occurrence or condition as constituting a material breach of the resulting Contract shall not imply that any other, non-specified act, failure, refusal, omission, event, occurrence or condition shall be deemed not to constitute a material breach of the resulting Contract;

2.6 In the event of any conflict, discrepancy, or inconsistency, the following shall control: 2.6.1 As between figures given on plans and scaled measurements, the figures

shall govern; In the event of a conflict between figures on the plans, the Contractor shall obtain clarification from the Architect prior to proceeding with the related work.

2.6.2 As between large scale plans and small scale plans, the large scale plans shall govern;

2.6.3 As between plans and specifications, the requirements of the specifications shall govern;

2.7 Meaning of Execution. Execution of the Contract Documents by the Contractor is a representation that the Contractor has thoroughly examined the site of the Work, become familiar with the local conditions under which the Work is to be performed, and correlated personal observations with the requirements of the Contract Documents. Execution of the Contract Documents is a further representation that Contractor has received, reviewed and carefully examined all of the Contract Documents, and has found them in all respects to be complete, accurate, adequate, consistent, coordinated and sufficient for construction, the Contractor is fully qualified to act as the contractor for the Project and has, and shall maintain, any and all licenses, permits or other authorizations necessary to act as the contractor for, and to construct the Project.

2.8 Prior Agreements. The Contract Documents supersede any and all prior discussions, communications, representations, understandings, negotiations or agreements between the Owner and the Contractor and the Agency and the Contractor.

2.9 Contractor’s Performance. The Contractor shall perform all of the Work required, implied or reasonably inferable from the Contract including, but not limited to, the following: 2.9.1 Construction of the Project; 2.9.2 The furnishing of any required surety bonds and insurance; 2.9.3 The provision or furnishing, and prompt payment therefor, of labor,

supervision, services, materials, supplies, equipment, fixtures, appliances, facilities, tools, transportation, storage, power, fuel, heat, light, cooling, or other utilities, required for construction and all necessary building permits and other permits required for the construction of the Project;

2.9.4 The creation and submission to the Owner of detailed and comprehensive as-built drawings, depicting all as-built construction. Said as-built drawings shall be submitted to the Owner upon final completion of the Project and receipt of same by the Owner shall be a condition precedent to final payment to the Contractor.

2.10 Time. All limitations of time set forth in the Contract Documents are material and are of the essence of the Contract. The Contractor shall make reasonable

Page 26: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

7 General Conditions

progress on the completion of the Work on a continual and consistent basis. 2.11 Intent of Contract Documents. The intent of the Contract Documents is to include

all items necessary for the proper completion of the Work by the Contractor. Labor or materials which are evidently necessary to produce the desired results, even though not specifically mentioned in the Contract Documents, shall be included in the Work.

2.12 Contract Documents Complementary, etc. The Contract Documents are complementary, and what is required by one shall be as binding as if required by all. In case of conflicts between the various Contract Documents, the order of precedence shall be as follows: (1) Addenda, (2) Division 1 - General Requirements of the Specifications; (3) Special Conditions, (4) General Conditions, (5) Technical provisions of the Specifications; (6) Drawings.

2.13 Questions to Architect. In the event a question arises regarding the meaning or intent of the drawings and specifications, the Contractor shall report it at once to the Architect. The Architect shall furnish, with reasonable promptness, additional instructions, by means of drawings or otherwise, necessary for the proper execution of the work, consistent with the requirements of Article 3.

2.14 Paragraph, titles or headings are for convenience only and form no operative part of the Contract.

3. The Architect Unless otherwise directed by the Owner in writing, the Architect shall performthose duties and discharge those responsibilities allocated to the Architect in the Contract Documents. The duties, obligations and responsibilities of the Architect shall include, but are not limited to, the following: 3.1 Owner’s Representative. The Architect will be the Owner’s Agent during

construction and until final payment has been made. The Architect will advise and consult with the Owner. In the event the Owner should find it necessary or convenient to replace the Architect, the Owner shall retain a replacement architect and the role of the replacement architect shall be the same as the role of the Architect.

3.2 Communication Through Architect. Except as otherwise provided in the Contract Documents, the Owner’s instructions to the Contractor shall be forwarded through the Architect, and the Contractor’s communications with the Owner shall be through the Architect.

3.3 Review of Work. The Architect shall approve, or respond otherwise as necessary concerning shop drawings or other submittals received from the Contractor. The Architect shall be authorized to refuse to accept work which is defective or otherwise fails to comply with the requirements of the Contract. If the Architect deems it appropriate, the Architect shall be authorized to call for extra inspection or testing of the work for compliance with requirements of the Contract. The Architect shall review the Contractor’s Payment Requests and shall approve in writing those amounts which, in the opinion of the Architect, are properly owing to the Contractor as provided in the Contract. The Architect shall perform those inspections required by the Owner. The Architect shall have authority to reject Work which does not conform to the Contract Documents. In the event of rejection, the Architect may recommend withholding payment to the Contractor for the rejected Work, and such recommendation shall give the Owner the authority to withhold payment for such Work.

3.4 Interpretation of Contract Documents. The Architect shall be the interpreter of the requirements of the Contract Documents and the judge of the performance thereunder by the Contractor, subject to the provisions of Article 32. Claims,

Page 27: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

8 General Conditions

disputes, and other matters in question that arise relating to the execution or progress of the Work shall be referred initially to the Architect for decision, which (s)he will render in writing within a reasonable time. Either party may appeal theArchitect’s decision to the VP of Finance and Administration in accordance withthe provision of Article 30.

3.5 Review of Shop Drawings, etc. The Architect shall review and approve, or take other appropriate action upon Contractor’s submittals (such as Shop Drawings, product data, and samples) for conformance with the design concept and the information given in the Contract Documents. Such action shall be taken with reasonable promptness so as to cause no delay. The Architect’s approval of a specific item shall not indicate approval of an assembly of which the item is a component. The Architect’s approval of Shop Drawings or samples shall not relieve the Contractor from his/her responsibility for any deviations from the requirements of the Contract Documents unless the Contractor has in writing called the Architect’s attention to such deviation at the time of submission and the Architect has given written approval to the specific deviation, nor shall any approval by the Architect relieve the Contractor from responsibility for errors or omissions in the Shop Drawings.

3.6 Preparation of Change Orders. The Architect, in consultation with the Owner, shall prepare Change Orders. The Architect shall also have authority to order minor changes in the Work as provided in Article 22.11.

3.7 Final Inspections, Certification. The Architect shall conduct inspections to determine the dates of Substantial Completion and Final Completion. The Architect shall also receive and forward to the Owner, for the Owner’s review, written warranties and related documents required by the Contract and assembled by the Contractor.

3.8 Payment Requests. The Architect shall review the Contractor’s Payment Requests and shall approve in writing those amounts which, in the opinion of the Architect, are properly owing to the Contractor as provided in the Contract. The Architect’s approval of payment requests shall not relieve the Contractor from his responsibility for any deviations from the requirements of the Contract Documents

3.9 The Architect shall be authorized to require the Contractor to make changes which do not involve a change in the Contract Sum or in the Contract Completion Time for the Contractor’s performance consistent with the intent of the Contract.

3.10 The duties, obligations and responsibilities of the Contractor under the Contract shall in no manner whatsoever be changed, altered, discharged, released, or satisfied by any duty, obligation or responsibility of the Architect. The Contractor is not a third-party beneficiary of any Contract by and between the Owner and the Architect. It is expressly acknowledged and agreed that the duties of Contractor to the Owner are independent of, and are not diminished by, any duties of the Architect to the Owner.

3.11 The duties, obligations and responsibilities of both the Architect and the Contractor, under their respective Contracts, shall in no manner whatsoever be changed, altered, discharged, released, or satisfied by any duty, obligation or responsibility of the Resident Observer. It is expressly acknowledged and agreed that the duties of Contractor and/or Architect to the Owner are independent of, and are not diminished by, any duties of the Resident Observer to the Owner.

4. Conduct4.1 General The conduct of all personnel performing work or operations related to the

work is the responsibility of the Contractor. The consumption of alcohol and/or

Page 28: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

9 General Conditions

drugs, and the carrying of firearms on the job by any worker are strictly prohibited. Any workmen apprehended under the influence of alcohol and/or drugs, or carrying firearms, on the premises at any time shall be subject to automatic dismissal by the Contractor. Improper conduct of any kind will not be permitted and may result in the offending workmen, Subcontractor and/or Contractor being barred from the university premises.

4.2 Any interaction with the students, faculty, staff or visitors of EKU shall be professional. Unprofessional conduct including, but not limited to, dress, general harassment, sexual harassment, or using obscenities can and shall be grounds for immediate removal of perpetrator from campus.

4.3 The University reserves the right of acceptance of all personnel assigned by the Offeror under this contract. The personnel must be cordial, well-groomed and cognizant of the fact that they may be entering student living buildings. If for any reason, the University believes that these guidelines are not being followed, it will request intervention from appropriate supervisory personnel. If inappropriate behavior occurs, the University shall be entitled to a change in personnel serving the campus.

4.4 The successful Offeror agrees that it will comply with the university Policy regarding Registered Sex Offenders and shall not knowingly permit any employee who is a registered sex offender to service the University residence halls, Model Laboratory School, the basement of the Burrier Building where the Child Development Center is currently located, or any areas of campus or University’s buildings. The University at any time can ask for personnel background check report to be provided by successful Offeror.

4.5 No University garbage containers shall be used by contractor for disposal of any debris.

4.6 Many Buildings on Campus are open to the public. The Contractor shall ensure that its employees and subcontractors access University property only when necessary and appropriate.

5. Tobacco-Free Campus 5.1The use of all tobacco is prohibited on all property that is owned, leased, occupied, or

controlled by the University. This includes buildings and structures, residence halls, housing facilities operated by Employee Housing, grounds, exterior open spaces, parking lots, and garages, on-campus sidewalks, streets, driveways, stadiums, recreational spaces, practice fields, University property outside the main campus such as regional campuses, farm facilities, art galleries, performance venues, and sporting venues and functions that are held in these facilities and venues.

5.2 The use of tobacco is prohibited in vehicles owned, leased or rented by the University, including maintenance Vehicles, automobiles, shuttles, utility vehicles, and golf carts as well as while in personal vehicles on University property.

5.3 Tobacco includes all forms of tobacco including, but not limited to, cigarettes, cigars, pipes, water pipes (hookah), electronic cigarettes, bidis, clove cigarettes and smokeless tobacco products (snuff, chewing tobacco, and dipping tobacco). Tobacco does not include nicotine replacement therapies such as patches, gum or prescription medication intended to assist an individual in quitting the use of tobacco.

6. Safety 6.1 Safety Data Sheets must be kept at the job site at all times.

Page 29: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

10 General Conditions

6.2 The Contractor shall be responsible for initiating, maintaining, and supervising all safety precautions and programs in connection with the performance of the Project.

6.3 The Contractor shall take all necessary precautions for the safety of employees on the Work site, and shall comply with all applicable provisions of federal, state, and municipal safety laws and building codes to prevent accidents or injury to persons on, about, or adjacent to the premises where the Work is being performed. The Contractor shall designate a responsible member of his/her organization on the Work site as safety officer whose duty shall be to enforce safety regulations. The name and position of the person so designated shall be reported to the Architect by the Contractor.

6.4 Fire protection must be maintained at job site at all times. Contractors must carry maintained and useable portable fire extinguishers on all work trucks.

6.5 If an emergency occurs affecting the safety of life, or of the work, or of adjoining property, the contractor shall act at his own discretion to prevent such threatening loss or injury without special instruction or authorization from the Owner.

7. Green Purchasing PolicyThe University is committed to reducing the adverse environmental impact of its

purchasing decisions; it is committed to buying goods and services from contractors who share its environmental concern and commitment. The University encourages bidders to include in their responses economical and environmentally friendly products and service options that serve to minimize waste, reduce excess packing and packaging, recycle, reduce, reuse, prevent pollution, and/or offer resource efficiency. It is the University’s goal to maximize environmental responsibility on its campuses.

8. Recycling and Waste Management Policy8.1 The University recognizes the need to be good stewards for its waste management

practices and policies and recognizes the importance of having vendors and/or their subcontractors be cognizant of the same practices and policies. Some jobs may, upon discretion of the university, require a waste and recycling plan, while others may consist of individual considerations for a particular job on means and methods of handling of various discarded material. The University encourages each vendor to be proactive in reviewing all avenues available to them for reducing the waste stream and encourage recycling to the greatest extent possible and practical.

8.2 KRS 45A.520 mandates that every state agency require a minimum recycled content for those materials it purchases. All materials provided for the completion of the Work shall conform with the requirements of 200 KAR 5:330, except as provided for in KRS 45A.510. Construction related materials requiring a minimum recycled content include building insulation, aluminum products, concrete, cement and steel products. For a complete listing of those items requiring minimum recycled content, please refer to 200 KAR 5:330 http://www.lrc.ky.gov/kar/200/005/330.pdf

9. Parking9.1 Ensure proper parking permits are obtained before commencing work. Under normal

circumstances, the contractor will be allowed two vehicles at the work site. All other vehicles will be given permits to park in a Commuter Lot. See Special Conditions for Project-specific parking instructions.

9.2 No leaking vehicles are allowed to park on campus.

Page 30: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

11 General Conditions

9.3 The University reserves the right to remove contractor’s vehicles from university property due to leaking of any fluids and charge contractor for any cleanup.

9.4 No parking on sidewalks or grass. 10. Traffic Control

10.1 Vehicles shall be parked in a manner that will not interfere with any required emergency exit, or the traffic of the campus.

10.2 EKU shall receive 48 hour advanced notice of any deliveries that will affect others on campus.

10.3 Contractor shall not block fire truck access unless approved in advance and only in extreme circumstances. (48 hour advanced notice to owner must be given).

11. Pedestrian and Property Protection11.1 Provide temporary barricades and other forms of protection to protect EKU's

personnel, students and general public from injury due to the Work. These barricades are to be maintained daily and kept in orderly manner. EKU will not provide any barricades. A barricade plan shall be discussed at the preconstruction meeting.

11.2 The Contractor shall continuously maintain adequate protection of all Work from damage and shall protect the Owner’s property from injury or loss arising in connection with this Contract. The Contractor shall make good any such damage, injury, or loss, except such as may be directly due to errors in the Contract Documents or caused by agents or employees of the Owner. (S)He shall adequately protect adjacent property as provided by law and the Contract Documents.

11.3 It is the contractor’s responsibility to protect their work from vandalism. 11.4 Provide protection of the Work and all University property during dust producing

operations. 11.5 Damages to any existing Buildings, including the University roads, parking lots,

drives, walks, and grass, etc., resulting from the Work or related operations whether caused by the Contractor's personnel, his/her Subcontractors or his/her material suppliers, shall be repaired or replaced, at no additional cost to the University, and to the satisfaction of the Owner.

11.6 Protect all roads and sidewalks from damage by equipment such as cranes or dump trucks when stationed for long periods of time by appropriate methods.

11.7 Contractor shall notify EKU at least three (3) business days prior to the commencement of any excavation. Once EKU approved excavation, contractor shall call 811 before dig.

12. Concrete and Landscaping requirementsRefer to concrete (03 3000 & 32 1300) and landscape (32 9300) owner’s project

requirements in the Technical Guidelines documents. 13. Hazardous Material-Call Project Manager Immediately if Suspicious

13.1 In the event the Contractor suspects or unexpectedly encounters on the site material reasonably believed to be asbestos, lead, polychlorinated biphenyl (PCB) or other classified hazardous substances/materials which have not been rendered harmless, the Contractor shall immediately stop Work in the area affected and report the condition to the Owner and Architect in writing. The Work in the affected area shall not thereafter be resumed except by written agreement of the Owner and Contractor if in fact the material is asbestos, lead, polychlorinated biphenyl (PCB), or other classified hazardous substances/materials which have not been rendered harmless. The Work in the affected area shall be resumed in the absence of any classified hazardous substances/materials or when it or they have been rendered harmless.

Page 31: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

12 General Conditions

13.2 The Project Manager shall then contact the proper university officials to take samples, conduct tests and report back to the contractor within a few days.

13.3 If the material is determined to be positive on test, the University will take appropriate action to remove the material before the contractor can continue work in the affected area.

14. Site Conditions14.1 No parking on grass or sidewalks. 14.2 The Contractor shall maintain all materials and organize the Work in such a manner

as to minimize any inconvenience to persons using or working in the Work site and adjacent areas.

14.3 The Contractor shall restrict his/her operations and movements in areas of the buildings, grounds that are strictly necessary to his/her work.

14.4 Contractor shall assume complete responsibility for disposing of equipment removed from the site during the work. Contractor shall remove, transport, and dispose of all debris. Contractor shall maintain a conveyance adjacent to the work in which debris shall be deposited as it is removed from the work. (S)He shall cause the conveyance to be emptied on a regular basis. Contractor shall not use building elevators for transporting any material or debris unless authorized in the Special Conditions.

14.5 Contractor shall not use owner’s trash cans for disposal of waste. 14.6 EKU assumes no responsibility for actual condition of items, grounds or structures

at areas of work. Conditions existing at time of inspection for bidding purposes will be maintained by EKU insofar as practicable. Photograph or videotape existing conditions that might be misconstrued as damage related to contractor’s activity. File with Project Manager prior to start of work.

14.7 No utility services are to be interrupted without the consent of the University. Contractor shall protect any known utilities against damage during construction. This includes but not limited to fire, water, gas, communications, and electricity.

15. Facilities Usage15.1 Owner will determine a use of toilet facilities per contract (See Special Conditions).

If contractor is required to provide temporary toilet facilities, they shall be in quantities necessary to adequately service workers and contractor’s personnel. Portable toilets on site shall be serviced regularly and used in accordance with good, clean sanitary practice. Contractor shall obtain portable toilets from an established firm regularly providing the same.

15.2 No cleaning of tools, buckets, vehicles etc. in any facilities or on grounds without prior agreement by the University.

15.3 The contractor shall provide communication devices, such as telephones, for use by their employees or subcontractors and shall not be permitted the free use of the existing EKU systems.

15.4 In the event the Owner elects to make available electric power or domestic water, at no cost, to the Contractor for construction purposes, the election to do so will be spelled out in the Special Conditions for this project. Electric power provided by the Owner, shall not be utilized as a means for temporary heat without specific approval from the Owner in writing. Contractor shall furnish all labor and devices required to convey these temporary services from point of connection to point of use desired by Contractor or his/her Subcontractors.

16. Occupancy16.1 EKU will occupy adjacent buildings at areas of work. Contractor shall conduct work

in a manner that will minimize need for disruption of EKU's normal operations. Contractor shall provide minimum of 48 hours advance notice to EKU of activities

Page 32: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

13 General Conditions

that will affect the normal operations of the building and/or area of work. Coordinate all work with EKU, including daily work schedules and areas of work.

16.2 Any work that may impact the normal operations of the fire alarms system shall be coordinated with EKU personnel with a minimum of a three (3) day notice.

16.3 Protect smoke detectors at all times. Any detector that gets painted, damaged, altered, or defaced will be replaced by a certified fire alarm contractor at no additional cost to the Owner.

17. General Work HoursWork Hours must be agreed upon and discussed prior to bidding and will be noted in the

Special Conditions. 18. Storage and Staging

18.1 Storage and staging areas (if needed) will be as described in the Special Conditions and will be discussed at the preconstruction meeting.

18.2 The contractor is responsible for the security of their materials and equipment. 19. Signs

The Contractor shall not display any sign, trademark, etc. except by the approval of EKU.

20. Administrative20.1 If applicable, a preliminary construction meeting will be held at a time and place

designated by the Owner, for the purpose of identifying responsibilities of Contractor and Owner. A date will be set at time of bid opening for the meeting. 20.1.1 Topics to be discussed include:

>Construction Schedule>Use of areas of the site>Delivery and storage>Safety>Post clean-up>Submittals>Change orders>Applications for payment>Record documents

20.1.2 Meeting attendees shall include: >The Owner>The Contractor and its Superintendent (All Must Be Present)>Subcontractor representative (if applicable)>Manufacturer representative

21. Subcontractor21.1 Contractor Fully Responsible for Subcontractors. The contractor is fully

responsible to the Owner for the acts and omissions of his/her Subcontractors and of persons and entities either directly or indirectly employed by them. Nothing contained in the Contract Documents shall create any contractual relationship between the Owner and a Subcontractor.

21.2 Subcontractors listed on the bid form shall not be changed without written permission from the University.

21.3 Flow-down Requirement. By contract, the Contractor shall require each Subcontractor: 21.3.1 to be bound to the Contractor by the terms of the Contract Documents

insofar as they apply to the Work to be performed by the Subcontractor; and

21.3.2 to assume toward the Contractor all the obligations which the Contractor, by the Contract Documents, assumes toward the Owner.

Page 33: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

14 General Conditions

21.4 All subcontractors are required to follow the same schedule and guidelines outlined by the contract documents. Sub-contractor shall have a minimum of three consecutive years’ of experience in related job.

21.5 Contracts with Subcontractors. The Contractor shall contract with those Subcontractors listed in the Contractors Bid Response and deemed acceptable by the Owner in accordance with the procedure outlined in the Instruction to Bidders. All subcontracts shall afford the Contractor rights against the Subcontractor which correspond to those rights afforded to the Owner against the Contractor herein, including those rights of Contract termination as set forth herein.

21.6 Substitution of Subcontractors. The Contractor shall not contract with any substitute Subcontractor or change a Subcontractor without providing timely written notice of the proposed substitution to the Architect, Project Engineer and Purchasing Officer. The substitution shall not be made if the Owner, Architect, Project Engineer, or Purchasing Officer object in writing to such change.

22. Changes in the Work/Change Orders22.1 Change Order means a written order to the Contractor executed by the Owner and

the Architect after execution of the Contract, directing a change in the Work and may include a change in the Contract Price, or the Contract Completion Time, or any combination thereof.

22.2 Any change in the Contract Sum resulting from a Change Order shall be determined by one of the following methods: 22.2.1 by mutual agreement of a lump sum amount between the Owner and the

Contractor as evidenced by (a) the Change in the Contract Sum being set forth in the Change Order, (b) such change in the Contract Sum, together with any conditions or requirements relating thereto, being initialed by both parties and (c) the Contractor’s execution of the Change Order;

22.2.2 by unit prices stated in the Contract Documents or subsequently agreed upon; or

22.2.3 if no mutual agreement occurs between the Owner and the Contractor, the Change in the Contract Sum, if any, shall be derived by determining the reasonable actual costs or savings achieved resulting from revisions in the Work.

22.3 Items (22.2.1) and (22.3.3) above shall include a component for all overhead, profit, indirect costs or other items not to exceed fifteen percent (15%). Any such costs or savings shall be documented in the format, and with such content and detail as the Owner or the Architect requires. The Contractor shall only receive one fifteen percent (15%) for the “jobsite overhead and profit” component whether such work be done by the Contractor or by his/her Subcontractor.

22.4 For all charges relating to any Change Order, whether determined under subparagraph 22.2.1, 22.2.2 or 22.2.3 above, the following provisions shall apply: 22.4.1 The Contractor shall keep and present in such form as the Architect may

direct, a correct account of all items in such form comprising the net cost of such Work, together with vouchers. The determination of the Architect shall be final upon all questions of the amount and cost of Changes in the Work, and it shall include in such cost, the cost to the Contractor of all materials used, of all labor, common and skilled, or foremen, trucks and teams, and the fair rental of all machinery used and for the period of such use. If said Work requires the use of machinery not already upon the work or to be otherwise used upon the Work, then the cost of transportation of such machinery to and from the Work shall be added to the fair rental, but

Page 34: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

15 General Conditions

said transportation shall not cover a distance exceeding one hundred (100) miles.

22.4.2 The Architect shall not include in the net cost of Work any cost or rental or small tools, or any portion of time of the Contractor or his/her Superintendent, or any allowance for the use of capital, or any additional bond premium, insurance cost applicable to the Work or any actual or anticipated profit, or any job or office overhead not previously mentioned, these items being considered as being covered by the added fifteen (15%) percent for the jobsite overhead and profit component.

22.4.3 In all cases where Changes in the Work are covered by unit prices set forth in the Contract, the value of such Work shall be determined only upon the basis of such unit prices.

22.4.4 Pending final determination of value, payments on Changes in Work shall be made only upon the estimate of the Architect.

22.5 If the Contractor claims that any instructions by the Architect involve additional cost and/or time extension, (s)he shall give the Architect written notice thereof within a reasonable time after the receipt of such instructions and before proceeding to execute the change in Work.

22.6 On all Change Orders that exceed $25,000, the Contractor shall submit the following certification: “I (the Contractor) certify to the best of my knowledge and belief, the cost or

pricing data submitted is accurate, complete and current as of the date of the proposed change.”

22.7 If the Owner and Contractor cannot agree on the effect of an ordered change on the adjustment to the Contract Sum or Contract Completion Time, this matter may also be referred to the Architect for determination.

22.8 If the Owner and/or Contractor do not agree with the Architect’s determination regarding the valuation of a change, the related adjustment to the Contract Sum or to the Contract Completion Time, the matter shall be subject to the disputes procedure set out in Article 30.

22.9 The execution of a Change Order by the Contractor shall constitute conclusive evidence of the Contractor’s agreement to the ordered changes in the Work, the resulting Contract as thus amended, the Contract Sum and the time for performance by the Contractor. The Contractor, by executing the Change Order, waives and forever releases any claim against the Owner for additional time or compensation for matters relating to or arising out of or resulting from the Work included within or affected by the executed Change Order.

22.10 The Contractor shall notify and obtain the consent and approval of the Contractor’s Payment and Performance Bond sureties with reference to all Change Orders if such notice, consent or approval are required by the Owner, the Architect, the Contractor’s sureties or by law. The Contractor’s execution of the Change Order shall constitute the Contractor’s warranty to the Owner that the sureties have been notified of, and consent to, such Change Order and the sureties shall be conclusively deemed to have been notified of such Change Order and to have expressly consented thereto.

22.11 Minor Changes. The Architect may authorize minor changes in the Work which do not involve additional cost or extension of the Contract Completion Time, and which are not inconsistent with the intent of the Contract Documents. Such changes shall be effected by a Field Order issued by the Architect, which shall be binding on the Owner and Contractor. The Contractor shall carry out such orders promptly. However, if the Contractor claims that a Field Order involves additional

Page 35: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

16 General Conditions

cost or a delay to completion of the Work, (s)he shall give the Architect written notice thereof within a reasonable time after receipt of the Field Order. Otherwise, (s)he shall be deemed to have waived any right to claim an adjustment to the Contract Sum or to the Contract Completion Time.

23. Key Checkout ProcedureKeys will be issued upon approval by Capital Construction and Project Administration or

Facilities Services. Unless prior approval is granted, all keys must be signed in and out daily. If prior approval is granted to keep a key for the duration of a project, the key must be returned at the end of the project. Master and series sub-master keys will only be provided if the scope of the project requires the key. Contractors are responsible for all the expenses created by lost or misused keys.

24. Site VisitAll Contractors, before submitting bids, shall visit and examine the site as necessary to

satisfy themselves as to the nature and scope of required work, including any and all dimensional measurements, and any difficulties attending the execution of the work as hereinafter specified and as indicated on the drawings. The submission of a bid will be construed as evidence that a visit and examination has been made. Later claims for labor, equipment, or materials required or difficulties encountered which could have been foreseen had such an examination been made, will not be recognized. No consideration will be given to any claim based on lack of knowledge of existing conditions.

25. MeasurementsEach Contractor shall be responsible for verification of all measurements and

dimensions at the site before ordering any materials or doing any work. No extra compensation shall be allowed due to difference in actual dimensions and measured dimensions. NOTE: DO NOT SCALE THE DRAWINGS. EKU will not be responsible for deviations in drawing measurements, even if listed on a drawing provided by EKU.

26 Labor and Materials 26.1 Unless otherwise stipulated, the Contractor shall provide and pay for all materials,

supervision, labor, water, tools, equipment, light, power, temporary heat, hoist, supplies, appliances, transportation, and other facilities and things necessary for the execution and completion of the Work. In the event the Owner elects to make available the electric power, at no cost, to the Contractor for construction purposes, it shall not be utilized as a means for temporary heat.

26.2 Contractor Warranty. The Contractor warrants to the Owner and Architect that materials and equipment furnished under the Contract will be of good quality and new unless otherwise required or permitted by the Contract Documents, that the Work will be free from defects not inherent in the quality required or permitted, and that the Work will strictly conform with the requirements of the Contract Documents. Work not conforming to these requirements, including substitutions not properly approved and authorized, may be considered defective. The Contractor’s warranty excludes remedy for damage or defect caused by abuse, modifications not executed by the Contractor, improper or insufficient maintenance, improper operation, or normal wear and tear under normal usage. If required by the Architect, the Contractor shall furnish satisfactory evidence as to the kind and quality of materials and equipment.

26.3 If an “or equal” is submitted, other than a product specified within these contract documents, the Contractor shall submit general product data at the time of bid opening. These documents will not be accepted at a later date. Not submitting such shall indicate that all items bid are “as specified.”

Page 36: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

17 General Conditions

26.4 Unless otherwise noted in the contract documents, EKU will not furnish any materials, labor, equipment or services to the Contractor for completion of the work.

26.5 Substitution-Materials and Equipment. Substitution of previously approved equipment and materials shall be considered only for the following reasons: 29.5.1 Unavailability of the material or equipment due to the conditions beyond

the control of the Contractor; 29.5.2 Inability of the supplier to meet Contract schedule; or 29.5.3 Technical and immaterial noncompliance to specifications.

26.6 Inclusion of a certain make or type of materials or equipment by the Contractor shall not obligate the Owner to accept such material or equipment if it does not meet the requirements of the plans and specifications. Substitutions not properly approved and authorized may be considered defective work. The Contractor shall, if required, furnish satisfactory evidence as to the kind and quality of materials and equipment.

26.7 The Owner shall not and will not be responsible for accepting, unloading and/or storing any material delivered to the site.

27. IndemnificationThe Contractor shall indemnify and hold the Owner harmless from any and all claims,

liability, damage, loss, cost and expense of every type whatsoever, regardless of whether such liability, claim, damage, loss, cost or expense is caused in part by the Owner, including, without limitation, attorneys’ fees and expenses, in connection with the Contractor’s performance of this Contract, provided that such claims, liability, damage, loss, cost or expense is due to sickness, personal injury, disease or death, or to loss or destruction of tangible property (other than the Work itself), including loss of use resulting therefrom, to the extent caused by the Contractor, or anyone for whose acts the Contractor may be liable.

28. Insurance28.1 The Contractor is required to provide proof of insurance coverage prior to beginning

contracted work. Contractor must keep current certificates on file with owner until contract work is completed. Contractor must also provide copies of complete insurance policy of required insurance upon the Owner’s request.

28.2 Contractor shall procure and maintain for the duration of the contract insurance against claims for injuries to persons or damages to property which may arise from or in connection with the performance of the work hereunder by Contractor, its agents, representatives, employees or subcontractors.

28.3 Minimum Scope of Insurance: >Insurance Services Officer commercial general liability coverage (“occurance”

Form CG 0001, Ed. 10/93) >Insurance Services Office Form CA 0001 (Ed. 12/93) covering automobile

liability, Code 1 “any auto” >Workers’ compensation insurance as required by the Workers’ Compensation

Act (as contained in KRS Chapter 342) and employers liability insurance 28.4 Minimum Limits of Insurance:

>Refer to the instructions in the Purchasing Instructions to Bidders for thespecific project.

28.5 Other Insurance Provisions: The policies are to contain, or be endorsed to contain, the following provisions: >Commercial General Liability and Automobile Liability Coverages

Owner, its officers and employees are to be covered as insureds as respects: liability arising out of activities performed by or on behalf

Page 37: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

18 General Conditions

of the Contractor; general supervision of the work by Owner; products and completed operations of the Contractor; premises owned, occupied or used by the Contractor, or automobiles owned, leased, hired or borrowed by the Contractor. The coverage shall contain no special limitations on the scope of protection afforded to Owner, its officers or employees.

The Contractor’s insurance coverage shall be primary insurance as respects Owner, its officers and employees. Any insurance of self-insurance maintained by Owner shall be excess of the Contractor’s insurance and shall not contribute to it.

Any failure to comply with reporting provisions of the policies shall not affect coverage provided to Owner, its officers or employees.

The Contractor’s insurance shall apply separately to each insured against whom claim is made or suit is brought except with respect to the limits of the insurer’s liability.

>All Coverages. Each insurance policy required by this clause shall be endorsedto state that coverage shall not be suspended, voided, canceled by either party, reduced in coverage or in limits except after thirty (30) days’ prior written notice by certified mail, return receipt requested, has been given to Owner.

28.6 Acceptability of Insurers Insurance. Insurance is to be placed with insurers with an A.M. Best’s rating of no less than A VII, authorized to write insurance in the Commonwealth of Kentucky.

28.7 Verification of Coverage. The Contractor shall furnish the Owner with certificates evidencing the required insurance coverage prior to commencing work. Contractor shall keep up-to-date copies of such certificates on file with Owner until work is completed. Owner may require Contractor to submit policy endorsements or complete policy copies of the required insurance.

28.8 Subcontractors. Contractor shall include all subcontractors as insureds under its policies or shall furnish separate certificates and endorsements for each subcontractor. All coverages for subcontractors shall be subject to all of the requirements stated herein.

28.9 The Contractor shall provide all Risks Insurance in an amount of not less than one hundred percent (100%) of the insurable value of all the work. The coverage, is to be written on CP 00 20 06 95 or equivalent acceptable to the University. All coinsurance clauses in the Risks Insurance policy will be waived. All rights of subrogation against the Owner (i.e. the University) will be waived by the insurer. Such insurance shall be for the benefit of the Contractor, Owner and any Subcontractor engaged on this project, as the Owner shall find their respective interest may appear. The Risks Insurance must be dated and in force on the date indicated in the Contract to begin work.

28.10 The insurance coverage required by the Contract Documents shall be in compliance with the laws of the Commonwealth of Kentucky and shall be placed with a licensed resident or non-resident agent who represents insurance companies authorized to do business in Kentucky.

28.11 The Certificate of Insurance or Certificates of Insurance will have the following endorsements as an attachment to the Certificate or Certificate’s: 28.11.1 Eastern Kentucky University, Division of Capital Construction and Project

Administration will be named as an additional insured. 28.11.2 The policy is primary coverage and any insurance or self-insurance

maintained by the University shall be excess.

Page 38: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

19 General Conditions

28.11.3 Any failure of the named insured to comply with the reporting provisions of the policy shall not affect coverage provided to the University, its officers or employees.

28.11.4 All Coverages. Each insurance policy required by this clause shall be endorsed to state that coverage shall not be suspended, voided, cancelled by either party, reduced in coverage or in limits except after thirty (30) days’ prior written notice by certified mail, return receipt requested, has been given to Owner.

29. Performance and Payment Bonds29.1 The Contractor shall furnish separate performance and payment bonds to the

Owner. The Contractor shall furnish a performance bond satisfactory to the Owner in an amount equal to one hundred percent (100%) of the Contract Sum as security for the faithful performance of the Contract. The Contractor shall also furnish a payment bond satisfactory to the Owner in an amount equal to one hundred percent (100%) of the Contract Sum for the protection of all persons performing labor or furnishing materials, equipment or supplies for the Contractor or his/her Subcontractor for the performance of the Work provided for in the Contract, including security for payment of all unemployment contributions which become due and payable under Kentucky Unemployment Insurance Law.

29.2 Each bond furnished by the Contractor shall incorporate by reference the terms of the Contract as fully as though they were set forth verbatim in such bonds. In the event the Contract Sum is adjusted by Change Order executed by the Contractor, the penal sum of both the performance bond and the payment bond shall be deemed increased by like amount.

29.3 The performance and payment bonds shall be executed by a surety company authorized to do business in this Commonwealth, and the contract instrument of bonds must be countersigned by a duly appointed and licensed resident agent.

30. Claims by the Contractor/Concealed Conditions/Disputes30.1Claims by the Contractor against the Owner are subject to the following:

30.1.1 All Contractor claims against the Owner shall be initiated by a written claim submitted to the Owner and the Architect. Such claim shall be filed with the Owner and the Architect no later than seven (7) calendar days after the event, or the first appearance of the circumstances, causing the claim, and same shall set forth in detail all known facts and circumstances supporting the claim;

30.1.2 The Contractor and the Owner shall continue their performance regardless of the existence of any claims submitted by the Contractor.

30.1.3 In the event the Contractor discovers previously concealed and unknown site conditions which differ materially from those indicated in the Contract Documents, or unknown site conditions which are materially at variance from those typically and ordinarily encountered in the general geographical location of the Project, the Contract Sum shall be modified, either upward or downward, upon the written claim made by either party within seven (7) calendar days after the first appearance to such party of the circumstances. As a condition precedent to the Owner having any liability to the Contractor due to concealed and unknown conditions, the Contractor must give the Owner and the Architect written notice of, and an opportunity to observe, such condition prior to disturbing it. The failure by the Contractor to give the written notice and make the claim as provided by this paragraph shall constitute a waiver by the Contractor of

Page 39: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

20 General Conditions

any rights arising out of or relating to such concealed and unknown condition;

30.1.4 In the event the Contractor seeks to make a claim for an increase in the Contract Sum, as a condition precedent to any liability of the Owner therefor, the Contractor shall strictly comply with the requirements of the first paragraph of this Article and such claim shall be made by the Contractor before proceeding to execute any additional or changed Work. Failure of the condition precedent to occur shall constitute a waiver by the Contractor of any claim for additional compensation;

30.1.5 In connection with any claim by the Contractor against the Owner for compensation in excess of the Contract Sum, any liability of the Owner for the Contractor’s cost shall be strictly limited to direct cost incurred by the Contractor and shall in no event include indirect cost or consequential damages of the Contractor.

30.1.6 The Owner shall not be liable to the Contractor for claims of third-parties including subcontractors, unless and until liability of the Contractor has been established therefor in a court of competent jurisdiction;

30.2 In the event the Contractor should be delayed in performing any task which at the time of the delay is then critical, or which during the delay becomes critical, as the sole result of any act or omission by the Owner or someone acting in the Owner’s behalf, or by Owner-authorized Change Orders, unusually bad weather not reasonably anticipatable, fire or other Acts of God, the date for achieving Substantial Completion, or, as applicable, final completion, shall be appropriately adjusted by the Owner upon the written claim of the Contractor to the Owner and the Architect. An extension of time shall not mean that the Contractor is entitled to additional compensation. A task is critical within the meaning of this paragraph if, and only if, said task is on the critical path of the Project schedule so that a delay in performing such task will delay the ultimate completion of the Project. Any claim for an extension of time by the Contractor shall strictly comply with the requirements of the first paragraph of this Article above. If the Contractor fails to make such claim as required in this paragraph, any claim for an extension of time shall be waived.

30.3 All claims under this Contract shall be made in accordance with KRS 45A.225 to 45A.290. The provisions of these statutes do not toll the running of the Statute of Limitations set forth in KRS 45A.260. Any suit pursuant to KRS 45A.245 shall be commenced within one (1) year of the Substantial Completion Date specified in the Contract. If the Contractor does not commence suit within one (1) year of the date specified in the Contract, the Contractor shall be foreclosed from proceeding in court pursuant to KRS 45A.245.

30.4 The Owner and Contractor agree that any suit, action or proceeding with respect to this Contract may only be brought in or entered by the courts of the Commonwealth of Kentucky situated in Frankfort, Franklin County, Kentucky, or the United States District Court for the Eastern District of Kentucky, Frankfort Division, and the parties hereby submit to the non-exclusive jurisdiction of such courts for the purpose of any such suit, action, proceeding or judgment and waive any other preferential jurisdiction by reason of domicile or location. The parties hereby agree that any such legal action shall be tried by the court sitting without a jury. The parties hereby irrevocably waive any objection that they may now or hereafter have to the laying of venue of any suit, action or proceeding arising out of or related to this Contract brought in the courts of the Commonwealth of Kentucky situated in Frankfort, Franklin County, Kentucky, or

Page 40: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

21 General Conditions

the United States District Court for the Eastern District of Kentucky, Frankfort Division, and also hereby irrevocably waive any claim that any such suit, action or proceeding brought in any one of the above-described courts has been brought in an inconvenient forum.

31. Liens31.1 The filing and perfection of liens for labor, materials, supplies and rental equipment

supplied on the work are governed by KRS 376.195 to 376.260. 31.2 The lien shall attach only to any unpaid balance or retainage due the Contractor for

the improvement from the time a copy of statement of lien, attested by the County Clerk, is delivered to the Owner, pursuant to the provisions of KRS 376.240. Statements of lien shall be filed with the Madison County Clerk and action to enforce the same must be instituted in the Madison Circuit Court, Richmond, Kentucky, pursuant to KRS 376.250(2).

32. AssignmentsNeither party to the Contract shall assign the Contract, or any portion thereof without the

written consent of the other, nor shall the Contractor assign any monies due or to become due to him/her hereunder without notification to the Owner. Notification of Assignments, shall be given in accordance with the procedures and regulations of Eastern Kentucky University.

33. Separate Contracts33.1 Owner’s Right to Perform Construction and to Award Separate Contracts. The

Owner reserves the right to let other contracts in connection with the Project or to perform Work with its own forces. The Contractor shall afford other contractors reasonable opportunity for the introduction and storage of their materials and the execution of their Work and shall properly connect and coordinate his/her Work with theirs.

33.2 If any part of the Contractor’s Work depends for proper execution or results upon the Work of any other contractor, the Contractor shall promptly report to the Architect any observed defects in such Work that render it unsuitable for proper execution or connection. His/her failure to inspect and report shall constitute an acceptance of the other contractor’s Work as fit and proper for the reception of his/her Work, except as to defects which may develop in the other contractor’s Work after the execution of his/her Work.

33.3 Whenever Work being done by the Owner’s forces or by other contractors is contiguous to Work covered by this Contract, the respective rights of the various interests involved shall be established by the Architect to secure the completion of the various portions of the Work in general harmony.

33.4 Mutual Responsibility of Contractors. Should the Contractor cause damage to any separate contractor on the Work, the Contractor agrees, upon due notice, to settle with such contractor if (s)he will so settle. If such separate contractor sues the Owner on account of any damage alleged to have been so sustained, the Owner shall notify the Contractor who shall defend such proceedings at the Contractor’s expense and if any judgment against the Owner arises therefrom, the Contractor shall pay or satisfy it and pay all costs incurred by the Owner.

34. Cash AllowancesThe Contractor shall have included in the Contract Sum all allowances stated in the

Contract Documents and shall cause the Work so designated to be done as the Owner may direct. If the actual price for purchasing the “allowed material” is more or less than the “cash allowance,” the Contract Sum shall be adjusted accordingly. The adjustment in Contract Sum shall be made on the basis of the purchase price without additional charges for overhead, profit, insurance or any

Page 41: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

22 General Conditions

other incidental expenses. The cost of installation of the “allowed materials” shall be included in the applicable sections of the Contract specifications covering this Work.

35. Schedules35.1 The Contractor, within fifteen (15) days of the Date of Commencement shall

prepare and submit for the Owner and Architect’s approval a construction schedule for completing the Work. The schedule shall indicate the starting and completion dates of the various stages of the Work, shall not exceed time limits established by the Contract Documents for the various stages of Work, shall be updated monthly and furnished to the Owner and Architect, shall be related to the Work of any other contractors on the Project to the extent required by the circumstances, and shall provide for expeditious and practicable execution of the Work. The original schedule shall be accompanied by a proposed schedule of values as described in Article 39.1. The Contractor shall promptly notify the Architect and Owner if the Contractor is materially ahead of, or behind the updated construction schedule. Failure to so notify the Architect and Owner shall relieve the Owner from liability for damages caused by delay or impact. Strict compliance with the requirements of this paragraph shall be a condition precedent to payment to the Contractor, and failure by the Contractor to strictly comply with said requirements shall constitute a material breach of the Contract.

35.2 For projects with a contract amount of $1,000,000 or greater, the schedule shall be in critical path method (CPM) format. The schedules shall include all activities necessary for performance of the work showing logic (sequences, dependencies, etc.) duration of each activity with the critical path highlighted. The schedules shall include, but not be limited to, submittal processing, fabrication and delivery of materials, construction, testing clean-up, work and/or materials to be provided by the Owner, dates and durations for major utility outages requiring coordination with the Owner and the Owner’s operations, and significant milestones related to the completion of the Project.

35.3 The Contractor acknowledges that all floats (including Total Float, Free Float, and Sequestered Float) are shared commodities available to the Project and are not for the exclusive benefit of any party; floats are expiring resources available to accommodate changes in the Work, however originated, or to mitigate the effect of events that may delay performance or completion of all or part of the Work.

36. Delays and Extensions of Time36.1 It is agreed that time is of the essence for each and every portion of the resulting

Contract and where under the Contract an additional time is allowed for the completion of any Work, the new time limit fixed by such extension shall be of the essence of the Contract. Provided, that the Contractor shall not be charged with liquidated damages or any excess cost when the delay in completion of the Work is due to: 36.1.1 any preference, priority, or allocation order duly issued by the government; 36.1.2 unforeseeable cause beyond the control and without the fault or

negligence of the Contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Owner, acts of another contractor in the performance of a contract with the Owner, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather; or

36.1.3 any delays of Subcontractors or suppliers occasioned by any of the causes specified in subsections 36.1.1 and 36.1.2 of this Article.

Page 42: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

23 General Conditions

36.2 The Contractor shall, within fifteen (15) calendar days of the occurrence of the event, notify the Architect in writing. The Architect shall ascertain the facts and extent of the delay and notify the Contractor within a reasonable time of its decision in the matter. Any change in the Contract Completion Time resulting from any such claim shall be incorporated in a Change Order. An extension of time shall not be construed as cause for extra compensation under the Contract. Extensions of time relating to concealed conditions as defined in Article 30 shall be governed by the provisions of that Article.

37. Shop Drawings; Submittals37.1 Schedule of Submittals. Prior to submission of the first application for payment

and in sufficient time to allow the Architect reasonable time for review, the Contractor shall submit to the Architect a schedule of submittals which shall be coordinated with the construction schedule. The Contractor shall keep the schedule of submittals current.

37.2 Submittals of Shop Drawings, Samples, etc.The Contractor shall review, approve, and submit Shop Drawings, samples, and product data in accordance with the approved schedule as herein detailed. The Contractor’s stamp of approval on any Shop Drawing or sample shall constitute a representation to Owner and Architect that the Contractor has either determined and verified all quantities, dimensions, field construction criteria, materials, catalog numbers, and similar data, or (s)he assumes full responsibility for doing so, and that (s)he has reviewed or coordinated each Shop Drawing or sample with the requirements of the Work and the Contract Documents.

37.3 The Architect shall review and approve, with reasonable promptness, the Shop Drawings, or return for corrections as required. The review and approval shall be for conformance with the design concept of the Project and for compliance with the information given in the Contract Documents. The approval of a separate item will not indicate approval of the assembly in which the item functions.

37.4 The Contractor shall make any corrections required by the Architect for compliance to the Contract and shall return the required number of corrected copies of Shop Drawings and resubmit new samples until approved. The Contractor shall direct specific attention, in writing, or on resubmitted Shop Drawings, to revisions other than the corrections called for by the Architect on previous submissions.

37.5 Where a Shop Drawing or sample submission is required by the specifications, no related work shall be commenced until the submission has been approved by the Architect. A copy of each approved Shop Drawing and each approved sample shall be kept in good order by the Contractor at the site and shall be available to the Architect.

37.6 The Architect’s approval of Shop Drawings or samples shall not relieve the Contractor from his/her responsibility for any deviations from the requirements of the Contract Documents unless the Contractor has in writing called the Architect’s attention to such deviation at the time of submission and the Architect has given written approval to the specific deviation, nor shall any approval by the Architect relieve the Contractor from responsibility for errors or omissions in the Shop Drawings.

37.7 The Contractor shall maintain a submittal log which shall include, at a minimum, the date of each submittal, the date of any resubmittal, the date of any approval or rejection, and the reason for any approval or rejection.

38. Supervision and Construction Procedures38.1 Supervision of the Work. The Contractor shall supervise and direct the Work,

using the Contractor’s best skill and attention so as to ensure expeditious,

Page 43: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

24 General Conditions

workmanlike performance in accordance with the requirements of the Contract Documents. The Contractor shall be solely responsible for and have control over construction means, methods, techniques, sequences, and procedures. (S)He shall be responsible for the acts and omissions of persons directly employed by him/her, as (s)he is for Subcontractors and others under Article 21. (S)He shall be responsible for coordinating all portions of the Work under the Contract unless the Contract Documents give other specific instructions concerning these matters.

38.2 Obligations to Follow Contract Requirements. The Contractor shall not be relieved of obligations to perform the Work in accordance with the Contract Documents by the activities or duties of the Architect in the Architect’s administration of the Contract or by tests, inspections or approvals required or performed by persons other than the Contractor.

38.3 The Contractor shall not perform Work without adequate plans and specifications, or, as appropriate, approved Shop Drawings, or other submittals. If the Contractor performs Work knowing or believing it involves an error, inconsistency or omission without first providing written notice to the Architect and Owner, the Contractor shall be responsible for such Work and pay the cost of correcting same.

38.4 All work shall strictly conform to the requirements of the Contract Documents. 38.5 The Work shall be continually supervised, the Contractor bearing full responsibility

for any and all acts or omissions of those engaged in the Work on behalf of the Contractor.

38.6 The Contractor shall at all times enforce strict discipline and good order among his/her employees and Subcontractors and shall not employ in the Work any person not skilled in the Work assigned to him/her.

38.7 The Contractor shall employ and maintain at the Project site only competent supervisory personnel.

38.8 The Contractor shall have a continuing duty to read, examine, review, compare and contrast each of the Contract Documents, Shop Drawings, and other submittals and shall give written notice to the Owner and the Architect of any potential conflict, ambiguity, error or omission which the Contractor may find with respect to these documents and their adequacy and sufficiency for construction as required by the Contract before proceeding with the affected Work. The express or implied approval by the Owner or the Architect of any Shop Drawings or other submittals shall not relieve the Contractor of the continuing duties imposed hereby, nor shall any such approval be evidence of the Contractor’s compliance with the resulting Contract. The Owner has relied upon the Architect to prepare documents for the Project, including the plans and specifications for the Project, which are accurate, adequate, consistent, coordinated and sufficient for construction, and in issuing the Contract to the Contractor, the Owner’s established legal duties to the Contractor notwithstanding, the Owner has relied upon the Architect’s professional expertise in fulfilling its legal duty to the Owner in addition to the Contractor’s full and good faith compliance with its duties set forth above.

38.9 Superintendent. The Contractor shall employ a qualified, competent superintendent and any necessary assistants who shall be in attendance at the Project site during performance of the Work. The University reserves the right to approve the Superintendent selected by the Contractor. The superintendent shall have full authority to act in behalf of the Contractor and all instructions given to the superintendent shall be considered as given to the Contractor. It shall be the

Page 44: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

25 General Conditions

responsibility of the Contractor’s superintendent to coordinate the work of all the Subcontractors. The superintendent shall not be changed except under the following circumstances: 38.9.1 where the superintendent proves to be unsatisfactory to the Contractor or

ceases to be in his/her employ, in which case the Contractor shall give timely prior written notice to the Owner of the impending change in superintendent and a reasonable explanation for the change; or

38.9.2 where the Owner has reasonable grounds for dissatisfaction with the performance of the superintendent and gives written notice to the Contractor of these grounds. The Contractor, upon receiving such written notice, shall replace the existing superintendent with a successor, to whom the Owner has no objection.

39. Payment The Owner shall make payments, less retainage, to the Contractor on the amount of the

Work performed or materials furnished for the Work in accordance with the following procedures:

39.1 Schedule of Values. At the same time it submits a construction schedule, within fifteen (15) days of the Date of Commencement, as provided in Article 35, the Contractor shall submit a Schedule of Values apportioning the Contract Sum among the different elements of the Project for purposes of periodic and final payment, prepared in such form and supported by such data to substantiate its accuracy as the Architect may require. The Contractor shall not imbalance its Schedule of Values, nor artificially inflate any element thereof. The violation of this provision by the Contractor shall constitute a material breach of the Contract. Upon written approval by the Architect and the Owner, the Schedule of Values and construction schedule shall become the basis for the Contractor’s Payment Requests during construction.

39.2 Application for Progress Payment. Not more often than once a month, the Contractor shall submit to the Architect a signed application for payment (sometimes referred to as Payment Request), for the Work completed as of the date of the application and accompanied by such data and schedules as the Architect may reasonably require. Therein, the Contractor may request payment less retainage for that part of the Contract Sum allocable to Contract requirements properly provided, labor, materials and equipment properly incorporated in the Project. If payment is requested on the basis of materials and equipment not incorporated in the Project, but delivered and suitably stored at the Project site or at another location agreed to in writing by the Owner, the application for payments shall also be accompanied by such data, satisfactory to Owner, as will establish the Owner’s title to the material and equipment and protect his/her interest therein, including written documentation of full insurance against loss or damage and the bonding of the storage sites. Storage sites must be bonded. Each subsequent application for payment shall include an affidavit of the Contractor stating that all previous progress payments received on account of the Work have been applied to discharge in full all of the Contractor’s obligations reflected in prior applications for payment. Each Payment Request shall be signed by the Contractor and shall constitute the Contractor’s representation that the quantity of Work has reach the level for which payment is requested, that the Work has been properly installed or performed in strict compliance with this

Page 45: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

26 General Conditions

Contract, and that the Contractor knows of no reason why payment should not be made as requested.

39.3 Approval of Payments. The Architect shall review the application for payment and shall review the Work at the project site or elsewhere to determine whether the quantity and quality of the Work is as represented in the application for payment and is as required by this Contract. The Architect shall, within ten (10) business days after receipt of each application for payment, approve in writing the amount which, in the opinion of the Architect, is properly owing to the Contractor. The Owner shall make payment to the Contractor within twenty (20) business days following the Architect’s written approval of each application for payment. A reasonable delay on the part of the Owner in making payment to the Contractor for any given payment shall not be a breach of contract. The amount of each such payment shall be the amount approved for payment by the Architect less such amounts, if any, otherwise owing by the Contractor to the Owner or which the Owner shall have the right to withhold as authorized by this Contract. The Architect’s approval of the Contractor’s application for payment shall not preclude the Owner from the exercise of any of its rights as set forth herein. The Contractor warrants and represents that, upon payment of the application for payment, title to all Work included in such payment shall be vested in the Owner.

39.4 Contractor’s Warranty of Title. The Contractor warrants and guarantees that title to all Work, materials and equipment covered by any application for payment, whether incorporated in the project or not, will pass to Owner at the time of payment free and clear of all encumbrance.

39.5 Retainage Reduction. Until fifty percent (50%) of the construction work has been completed in accordance with the contract, the Owner may withhold no more than ten percent (10%) retainage from the amount of any undisputed payment due, and retainage held after fifty-one percent (51%) of the construction project has been completed shall not be more than five percent (5%) of the total contract amount.

39.6 Completion, Acceptance, and Final Payment. Upon certification by the Architect of Substantial Completion of the Work, the Contractor shall continue to make normal pay requests as defined within this document. Within thirty (30) days after substantial completion, the Owner shall release the retainage less an amount equal to two hundred percent (200%) of the Owner’s reasonably estimated cost of the balance of any contractor’s contractually obligated, yet uncompleted, work remaining.

39.7 Final payment, shall be made by the Owner to the Contractor when the Contract has been fully performed by the Contractor in accordance with the Contract Documents and a final Certificate of Payment is issued by the Architect. Such final payment shall be made by the Owner not more than thirty (30) business days after the issuance of the final Certificate of Payment. The Contractor shall submit with the application for final payment an affidavit that all payrolls, bills for materials, supplies and equipment, and other indebtedness connected with the Work have been paid or otherwise satisfied, along with such supporting evidence of payment as the Architect requires. Final payment is conditioned on satisfactory compliance with this requirement.

39.8 Waiver of Claims. The making of final payment shall constitute a waiver of all claims by the Owner except those arising from: >unsettled liens; >faulty or defective Work appearing after Substantial Completion;

Page 46: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

27 General Conditions

>failure of the Work to comply with the requirements of the Contract Documents;or

>terms of any special warranties required by the Contract Documents.39.9 The acceptance of final payment by the Contractor shall constitute a waiver of all

claims except those previously made in writing and identified by the Contractor as unsettled at the time of the final application for payment

39.10 Contractor’s Payment to Subcontractors. When payment is received from the Owner, the Contractor shall immediately pay all Subcontractors, materialmen, laborers, and suppliers the amounts they are due for the Work covered by such payment. In the event the Owner becomes informed that the Contractor has not paid a Subcontractor, materialman, laborer, or supplier as provided herein, the Owner shall have the right, but not the duty, to issue future checks and payment to the Contractor of amounts otherwise due hereunder naming the Contractor and any such Subcontractor, materialman, laborer, or supplier as joint payees. Such joint check procedure, if employed by the Owner, shall create no rights in favor of any person or entity beyond the right of the named payees to payment of the check and shall not be deemed to commit the Owner to repeat the procedure in the future. The Contractor shall, by an appropriate agreement with each Subcontractor, require each Subcontractor to make payment to his/her subcontractors in similar manner.

39.11 The Architect may, on request, furnish to any Subcontractor information regarding the percentage of completion of the amounts applied for by the Contractor and the action thereon by the Architect.

39.12 Neither the Owner nor the Architect shall have any obligation to make payment to any Subcontractor except as may otherwise be required by law.

39.13 Owner’s Rights Relating to Payments. Neither payment to the Contractor, utilization of the project for any purpose by the Owner, nor any act or omission by the Owner shall be interpreted or construed as an acceptance of any Work of the Contractor not strictly in compliance with this Contract.

39.14 The Owner shall have the right to refuse to make payment and, if necessary, may demand the return of a portion of all of the amount previously paid to the Contractor due to: >The quality of a portion, or all, of the Contractor’s Work not being in accordance

with the requirements of this Contract; >The quantity of the Contractor’s Work not being as represented in the

Contractor’s Payment Request, or otherwise; >Claims made, or likely to be made, against the Owner;>Loss caused by the Contractor;>The Contractor’s failure or refusal to perform any of its obligations to the owner.

39.15 In the event that the Owner makes written demand upon the Contractor for amounts previously paid by the Owner as contemplated in the Paragraph, the Contractor must promptly comply with such demand.

40. Quality of Work40.1 Workmen or supervisors judged by EKU to be incapable of performing their trade in

a manner commensurate with quality of workmanship required by these specifications and accompanying drawings shall be immediately removed from this project when directed by EKU. Work that is not satisfactorily installed shall be removed and replaced at contractor’s expense.

40.2 The Architect shall approve, or respond otherwise as necessary concerning shop drawings or other submittals received from the Contractor. The Architect shall be authorized to refuse to accept work which is defective or otherwise fails to

Page 47: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

28 General Conditions

comply with the requirements of the Contract. If the Architect deems it appropriate, the Architect shall be authorized to call for extra inspection or testing of the Work for compliance with requirements of the Contract. The Architect shall review the Contractor’s Payment Requests and shall approve in writing those amounts which, in the opinion of the Architect, are properly owing to the Contractor as provided in the Contract. The Architect shall perform those inspections required by the Owner.

40.3 Materials determined by the Owner to be defective or unsuitable and not in conformance with the contract documents shall immediately be removed from the project site. Work shall cease immediately once a conflict arises. The contractor will be responsible to make corrections that are in conformance with the contract documents. Any deviations from the contract document must be approved in writing by the Owner prior to installation.

41. Code Compliance (if applicable)The following codes and/or Standards, but not limited to, are to be adhered to during this

project. Contractor shall comply with all codes to local jurisdiction. >Kentucky Building Code>National Electrical code>Occupational Safety and Health Administration>Environmental Protection Agency>State fire Marshals Code>National Fire Protection Association>Underwriters Laboratories

42. Inspection, Tests, Permits, and License Fees42.1 Inspection fees by other agencies and responsibility for payment should be

discussed prior to bid submission. If prior arrangements are not made, the contractor will be held accountable for all fees.

42.2 Tests of the materials, products, and equipment in place, required by the Owner or Architect, to prove quality standards shall be paid by the Contractor. If the results of testing indicate that construction is not in compliance with contract documents, the Contractor is responsible for the cost of any additional tests of materials, products, or equipment. The Contractor shall give timely notice of readiness of the work for all inspections, tests, or approvals.

42.3 Regulatory agencies of the government having jurisdiction may require any work to be inspected, tested, or approved. The Contractor shall assume full responsibility therefore, including related costs, unless otherwise noted in the contract. The Contractor shall provide the Owner and Architect the required certifications of inspection, testing, or approval.

42.4 Any delays by governmental agencies in obtaining permits, notices, required regulatory tests, and inspections that are not at the fault of either of the parties shall be shared by the Contractor and the Owner with appropriate time extensions. Liquidated damages and Contractor compensation for such delays or impact are not applicable and shall not be payable.

42.5 Building, sewer, and water permits and similar kinds of permits required by local ordinances shall be obtained by the Contractor. The Contractor is responsible for the payment of any fees associated with these permits.

42.6 The contractor shall pay all royalties and license fees that may be required to complete a project. The contractor is also responsible to defend all claims or suits for the infringement of any patent rights, and shall save the Owner harmless from loss on account thereof.

Page 48: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

29 General Conditions

43. Correction of Work 43.1 Prior to the final payment, the Contractor shall promptly correct work which is

rejected by the Owner or Architect as failing to conform to the requirements of the Contract Documents. Such correction shall be required regardless of whether or not the nonconformities are observed before or after Substantial Completion, or whether or not the Work has been fully fabricated.

43.2 After the final payment is received, the Contractor is still responsible for correcting any work that fails to conform to the requirements of the contract documents. If within one year after the date of Substantial Completion of the work, or after the date for commencement of warranties, or by terms of an applicable special warranty required by the contract documents, any of the Work is found to be not in accordance with the requirements of the contract documents, the Contractor shall correct is promptly after receipt of written notice from the owner to do so unless the owner has previously given the contractor a written acceptance of such condition. This period of one year shall be extended with respect to portions of work first performed after substantial completion by the period of time between substantial completion and the actual performance of the work.

43.3 In addition to correcting all nonconforming work and removing all nonconforming work or materials from the jobsite, the Contractor is responsible for all other costs of bringing the affected work into compliance with the contract documents. This includes costs of any additional required testing or inspection services, Architect’s or Engineer’s services, and any resulting damages to property.

43.4 Even after the Contractor is no longer specifically obligated to perform corrective work itself, the Contractor shall still be held liable for nonconforming work and for other breaches of his/her obligations under the contract documents.

43.5 If the Contractor fails to correct the nonconforming work within a reasonable time, the Owner may take the appropriate step to correct the work itself. If within ten (10) days after receiving written notice to correct a nonconformity, the Contractor has not made suitable arrangements, the Owner may proceed to correct the nonconforming work. In such cases a Change Order shall be issued by the Owner with the approval of the Architect/Engineer with a reasonable deduction from the contract sum due to the need to correct nonconforming work. The amount difference of the Change Order will be deducted from the remaining payments to the Contractor.

43.6 If the Owner deems it impractical to correct work which is not in accordance to the requirements in the contract documents, a Change Order shall be issued by the Owner with the approval of the Architect/Engineer with a reasonable deduction from the contract sum due to the incorrect work. The amount of the Change Order will be deducted from the remaining payments to the Contractor.

43.7 Ongoing liability of Contractor for defective work. The foregoing provisions establishing the specific obligation of the Contractor to perform corrective work do not establish a period of limitations on other obligations of the Contractor under the contract documents.

44. Suspension of Work 44.1 Suspension by the Owner. The Owner shall have the right at any time to direct

the contractor to suspend its performance, or any portion thereof for a period of not more than thirty (30) calendar days. The notice of suspension shall be in writing and shall set forth the reason for the suspension. The written notice shall fix the approximate date on which Work is contemplated to be resumed. The Owner shall pay the Contractor as full compensation for such suspension the Contractor’s Direct Job Expenses.

Page 49: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

30 General Conditions

44.2 Other Suspension. In the event the Owner should be prevented or enjoined by court order from proceeding with the Work or from authorizing its prosecution, either before or after the award, for a period up to ninety (90) days, the delay shall not constitute cause for termination by the Contractor and the Contractor shall not be entitled to make or assert claim for damage by reason of said delay, but time for completion of Work shall be extended to such reasonable time as the Owner may determine will compensate for time lost by such delay. Such determination shall be set forth in a Change Order shall be final and binding upon both parties, and shall not require the signature of the Contractor to be in effect.

44.3 The Owner shall pay the Contractor as full compensation for such suspension the Contractor’s reasonable costs actually incurred and paid as follows: 44.3.1 Demobilization and remobilization, including such costs paid to

subcontractors; 44.3.2 Preserving and protecting work in place; 44.3.3 Storage of materials or equipment purchased for the Project, including

insurance thereon; 44.3.4 Performing in a later, or during a longer, time frame than contemplated by

this contract. 44.4 Suspension by the Contractor. If, through no act or fault of the Contractor, the

Work is suspended for a period of more than thirty (30) days by the Owner, or more than ninety (90) days under an Order of the Court or other public authority, then the Contractor may, after ten (10) days from delivery of a written notice to the Owner and the Architect, terminate the Contract and recover from the Owner payment for all Work executed and reasonable expenses sustained. If the Architect has failed to act on a request for payment within thirty (30) days of submission or if the Owner has failed to make any payment within forty-five (45) working days or receipt of an approval application for payment, the Contractor may, upon ten (10) days written notice to the owner and the Architect stop the work until (s)he has been paid all amounts due. In this incidence and upon resumption of the work, a Change Order shall be issued adjusting the contract price or extending the contract completion time, or both to compensate the costs and delays attributable to stopping the work. Any such compensation is subject to the provisions, conditions and limitations outlined in Article 30.

45. Termination45.1 Termination of Contract for Convenience of Owner. The Owner, for any reason

whatsoever, may terminate the Contract for its own convenience when it determines that such termination will be in the best interest of the University. The Owner shall give written notice of such termination to the Contractor specifying when termination becomes effective. The Contractor shall incur no further obligations in connection with the Work and the Contractor shall stop Work when such termination becomes effective. The Contractor shall also terminate outstanding orders and subcontracts. The Contractor shall settle the liabilities and claims arising out of the termination of Subcontracts and orders. The Owner may direct the Contractor to assign the Contractor’s right, title and interest under termination orders or subcontracts to the Owner or its designee. The Contractor shall transfer title and deliver to the Owner such completed or partially completed Work and materials, equipment, parts, fixtures, information and Contract rights as the Contractor has. The University shall negotiate a fair and just settlement with the Contractor in accordance with 200 KAR 5:312 Section 2. In such event, the following procedure shall be required:

Page 50: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

31 General Conditions

45.1.1 The Contractor shall submit a termination claim to the Owner and the Architect specifying the amounts due because of the termination for convenience together with costs, pricing or other data required by the Owner or the Architect. If the Contractor fails to file a termination claim within one (1) year from the effective date of termination, the Owner shall pay the Contractor, an amount derived in accordance with paragraph (45.1.3) below;

45.1.2 The Owner and the Contractor may agree to the compensation, if any, due to the Contractor hereunder pursuant to 200 KAR 5:312 Section 2;

45.1.3 Absent agreement to the amount due to the Contractor, the Owner shall pay the Contractor the following amounts: 45.1.3.1 Contract prices for labor, materials, equipment and other

services accepted under this Contract; 45.1.3.2 Reasonable costs incurred in preparing to perform and in

performing the terminated portion of the Work and in terminating the Contractor’s performance, plus a fair and reasonable allowance for direct jobsite overhead and profit thereon (such profit shall not include anticipated profit or consequential damages); provided however, that if it appears that the Contractor would have not profited or would have sustained a loss if the entire Contract would have been completed, no profit shall be allowed or included and the amount of compensation shall be reduced to reflect the anticipated rate of loss, if any;

45.1.3.3 Reasonable costs of settling and paying claims arising out of the termination of subcontracts or orders pursuant to the initial Paragraph of 45.1. These costs shall not include amounts paid in accordance with other provisions hereof. The total sum to be paid the Contractor under 45.1 shall not exceed the total Contract Sum, as properly adjusted, reduced by the amount of payments otherwise made, and shall in no event include duplication of payment.

45.2Termination of Contract for Cause If the Contractor should be adjudged as bankrupt, or if (s)he should make a general assignment for the benefit of his/her creditors, or if a receiver should be appointed on account of his/her insolvency or, if the Contractor does not perform the Work, or any part thereof, in a timely manner, supply adequate labor, supervisory personnel or proper equipment or materials, or if it fails to timely discharge its obligations for labor, equipment and materials, or proceeds to disobey applicable law, or otherwise commits a violation of a material provision of the resulting Contract, then the Owner, in addition to any other rights it may have against the Contractor or others, may terminate the performance of the Contractor upon ten (10) days written notice by registered mail of declaration of default and assume possession of the Project site and of all materials and equipment at the site and may complete the Work. In such case, the Contractor shall not be paid further until the Work is complete. After final completion has been achieved, if any portion of the Contract Sum, as it may be modified hereunder, remains after the cost to the Owner of completing the Work, including all costs and expenses of every nature incurred, has been deducted by the Owner, such remainder shall belong to the Contractor. Otherwise, the Contractor shall pay and make whole the Owner for such cost. This obligation for payment shall survive the termination of the Contract. In the event the employment of the Contractor is terminated by the Owner for cause

Page 51: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

32 General Conditions

pursuant to this Paragraph 45.2 and it is subsequently determined by a Court of competent jurisdiction that such termination was without cause, such termination shall thereupon be deemed a Termination for Convenience under Paragraph 45.1, and the provisions of Paragraph 45.1 shall apply.

46. Project Completion and Record Drawings 46.1 Commencement and Completion of Work The Contractor shall begin the Work

on the Date of Commencement as specified in the Contract issued by the Owner. (S)He shall diligently and expeditiously continue the performance of the Contract to and until Substantial Completion and Final Completion of the Project. The Contractor shall accomplish the Work in accordance with the construction schedule so as to achieve Substantial Completion and Final Completion dates as defined in the Contract Documents. All time limits stated in the Contract Documents are the essence of the Contract.

46.2 Substantial Completion of the WorkThe Substantial Completion Date shall be that date certified by the Architect in accordance with the following procedures: 46.2.1 When the Contractor determines that Substantial Completion has been

achieved, the Contractor shall notify the Owner and the Architect in writing. The notification shall be accompanied by a Contractor prepared list of those items of Work still to be completed or corrected. The failure of the Contractor to include any item or items on such list not completed or needing correction shall not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents.

46.2.2 The Architect shall, within a reasonable time after receipt of notification from the Contractor of Substantial Completion, make such inspection to confirm that the Work has achieved Substantial Completion.

46.2.3 Upon its confirmation that the Contractor’s work is substantially complete, the Architect shall prepare a Certificate of Substantial Completion which shall establish the Substantial Completion Date and the responsibilities between the Owner and Contractor for security, maintenance, heat, utilities and insurance, if not otherwise provided for in the Contract Documents, and a tentative list of items to be completed or corrected, within thirty (30) calendar days from the Substantial Completion Date. The Certificate of Substantial Completion shall be submitted to the Owner and Contractor for their written acceptance of the responsibilities assigned to them in the certificate.

46.2.4 All Operation and Maintenance (O&M) manuals and warranties must be provided to the Owner before the Certificate of Substantial Completion can be awarded.

46.2.5 If, after making the inspection, the Architect fails to find that the Contractor’s Work has achieved Substantial Completion, (s)he will notify the Contractor in writing, giving the reasons therefore.

46.2.6 If the Architect through its inspection fails to find that the Contractor’s Work has achieved Substantial Completion and is required to repeat all, or any portion, of its, the Contractor shall bear the cost of such repeat inspections which cost may be deducted by the Owner from any payment then or thereafter due the Contractor.

46.2.7 The warranty on the entire project begins at Substantial Completion (upon warranty delivery and inspection) for all components of the project regardless of when the components (or systems, parts, pieces, equipment, etc.) were delivered or installed.

Page 52: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

33 General Conditions

46.3 Final Completion of the Work. The Architect, upon receipt of written notice from the Contractor that the Work is finally complete and is ready for final inspection and acceptance, will promptly make such inspection and when (s)he finds the Work completed and acceptable under the Contract Documents and the Contract fully performed, (s)he will so notify the Contractor in writing and promptly issue a final Certificate of Payment to the Owner. If the Architect is unable to issue its final Certificate of Payment and is required to repeat its final inspection of the Project, the Contractor shall bear the cost of such repeat inspection(s), which costs may be deducted by the Owner from the Contractor’s final payment; When the Owner accepts and occupies a building, all operations, maintenance, utilities and insurance become the responsibility of the Owner.

46.4 Use of Substantially Complete Portions. The Owner may use or occupy a specified portion of the Work at any stage, provided that: 46.4.1 such use or occupancy is consented to by insurers and 46.4.2 it is authorized by public regulatory bodies having jurisdiction over the

Work; 46.4.3 prior to such use or occupation, the affected portion of the Work is jointly

inspected by the Owner, Contractor, and Architect to determine the precise stage of completion.

46.4.4 Such possession and use shall not be deemed an acceptance of any Work not completed in accordance with the Contract Documents.

46.5 The Contractor shall keep one copy of all Contract Documents, drawings, specifications and shop drawings on the site, in good condition, and a qualified representative of the Contractor and each Subcontractor shall record on these prints, from day to day as the Work progresses, all changes and deviations from the Contract Documents. This set will be delivered to EKU upon completion of the project. Approval of final payments will be contingent upon compliance with these provisions.

46.6 At the completion of work the contract area shall be complete, clean and free of all damage, dirt and other imperfections with all operable equipment functioning properly.

46.7 The Contractor shall remove all materials, temporary barriers, services, devices, or rubbish resulting from his/her work and leave the site clean to the satisfaction of EKU upon completion of the work and before final acceptance of the job can be made.

46.8 The Contractor shall submit all warranties and guarantees requested by this contract.

46.9 After all work is completed, EKU and in conjunction with manufacturer’s representative (if applicable) shall make a final inspection. Any work not up to standard shall be removed and replaced before final payment is made.

46.10 Project Records. All documents relating in any manner whatsoever to the Project, or any designated portion thereof, which are in the possession of the Contractor, or any Subcontractor of the Contractor, shall be made available to the Owner or the Architect for inspection and copying upon written request by the Owner. Furthermore, said documents shall be made available, upon request by the Owner, to any state, federal or other regulatory authority and any such authority may review, inspect and copy such records. Said records include, but are not limited to all drawings, plans, specifications, approved submittals, correspondence, minutes, memoranda, tape recordings, videos, or other writings or things which document the Project, its design, and its construction. Said records expressly include those documents reflecting the cost of construction to

Page 53: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

34 General Conditions

the Contractor. The Contractor shall maintain and protect these documents for no less than ten (10) years after final completion of the Project, or for any longer period of time as may be required by law or good construction practice.

46.11 In no event is the Contractor permitted to use any portion of the contract documents for other projects without written authorization of Eastern Kentucky University.

47. Miscellaneous Provisions Regarding Contractor’s Work47.1 Project Site Limits The Contractor shall confine his/her apparatus, the storage of

materials, and the operations of his/her workmen to Project site limits indicated by the Contract Documents.

47.2 Points of Reference The Contractor shall carefully preserve bench marks, reference points and stakes, and in case of willful or careless destruction, (s)he shall be charged with the resulting expense of replacement and shall be responsible for any mistake that may be caused by their unnecessary loss or disturbance.

47.3 Cutting and Patching The Contractor shall be responsible for cutting, fitting or patching required to complete the Project or make its parts fit together in a proper manner. The Contractor shall not endanger other parts of the Project, including work by the Owner or other contractors as provided in Article 33, by cutting, patching, or excavation. The Contractor shall not cut or otherwise alter construction by the Owner or a separate contractor without written consent of the Owner or such separate contractor. Such consent shall not be unreasonably withheld.

47.4 Cleanup The Contractor shall at all times keep the Project premises and surrounding area free from the accumulation of waste materials or rubbish caused by his/her operations in connection with the Project. Upon completion of the Work, and prior to final inspection and acceptance, the Contractor shall remove all remaining waste materials, rubbish, Contractor’s construction equipment, tools, machinery, and surplus materials and leave the Project (including but not limited to glass, hardware, fixtures, masonry, tile and marble) in a clean and usable condition satisfactory to the Architect. Floors shall be cleaned and waxed in accordance with the requirements of the Contract specifications. If the Contractor fails to clean up as provided in the Contract Documents, the Owner may perform the cleaning tasks and charge the cost to the Contractor.

47.5 Guarantees, Warranties, and “As-Built” Drawings Prior to final payment for the Work, the Contractor shall assemble and present to the Architect all guarantees and warranties required by the Contract Documents. Additionally the Contractor shall provide “Record” Drawings prior to final payment.

47.6 Governing Law The Contract shall be governed by the laws of the Commonwealth of Kentucky.

47.7 Statutory Limitation Periods Statutes of Limitations are governed by KRS 45A.260(2).

47.8 Written Notice Written notice shall be deemed to have been given if delivered in person to the individual or to a member of the organization or entity or to an officer of the corporation for which it was intended, or if delivered at or sent by registered or certified mail to the last known business address known to the notifying party.

48. Davis-Bacon Act (Applicaple to federally funded construction projects exceeding $2,000).48.1 Contractor agrees to pay wages to mechanics and laborers at a rate not less than

the prevailing wages specified in a wage determination made by the Secretary of Labor. Supplier agrees to pay wages and meet the other requirements as

Page 54: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

35 General Conditions

specified by Davis-Bacon Act, as amended (40 U.S.C. 3141-3148) as supplemented by the Department of Labor regulations (29 CFR Part 5). Supplier acknowledges that the University affiliated entity’s decision to make a Contract with Supplier is conditioned upon the acceptance of the wage determination.

48.2 On covered contracts, the Trade Contractor shall post and keep posted in a conspicuous place or places at the site of the work, a copy or copies of prevailing rates of wages and the working hours as prescribed in the contract documents.

48.3 Any laborer, workman, or mechanic worked in excess of eight (8) hours per day for forty (40) hours per week, except in cases of emergency caused by fire, flood, or damage to life or property shall be paid not less than one and one half (1 1/2) times the basic hourly rate of pay as fixed by law for all overtime worked. The determination of when an emergency exists shall be made by the public authority letting the contract as provided for by law.

48.4 On covered contracts, the contractor shall keep full and accurate payroll records covering all disbursements of wages to their employees to whom they are required to pay not less that the federal prevailing rate of wages. Records shall indicate the hours worked each day by each employee in each classification of work and amount paid each employee for his/her work in each classification. Payroll records are to be maintained for one year after completion of the contract. These records are to be open for inspection and transcript by the US Secretary of Labor at any reasonable time. These records may also be audited upon request by the Owner.

49. Apprentices Apprentices (for all classifications of work) shall be permitted to work onlyunder an apprenticeship agreement approved by the Kentucky Supervisor of Apprenticeship and by the Kentucky Apprenticeship Council which is recognized by the Bureau of Apprenticeship and Training, U. S. Department of Labor.

50. Nondiscrimination in Employment During the performance of the Contract, the Contractoragrees as follows: 50.1 The Contractor shall not discriminate against any employee or applicant for

employment because of race, color, religion, sex, age, national origin, or disability in employment.

50.2 The Contractor will take affirmative action in regard to employment, upgrading, demotion, transfer, recruitment, recruitment advertising, layoff, termination, rates of pay or other forms of compensation, and selection for training, so as to ensure that applicants are employed and that employees during employment are treated without regard to their race, color, religion, sex, age, or national origin; however, when layoffs occur, employees shall be laid off according to seniority with the youngest employees being laid off first. When employees are recalled, this shall be done in the reverse way the employees were laid off;

50.3 The Contractor shall, in all solicitations or advertisements for employees placed by or on behalf of the Contractor, state that all qualified applicants will receive consideration for employment without regard to race, color, religion, sex, age, or national origin;

50.4 The Contractor will post notices in conspicuous places, available to employees and applicants for employment, setting forth the provisions of the nondiscrimination clauses required by this section;

50.5 The Contractor shall send to each labor union or representatives of workers with which (s)he has a collective bargaining agreement or other contract or understanding, a notice advising the labor union or workers’ representatives of the Contractor’s commitments under this section.

Page 55: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

36 General Conditions

50.6 Failure to comply with the above nondiscrimination clause constitutes material breach of Contract.

51. Affirmative Action: Reporting Requirements The Contractor and Subcontractors areexempt from any affirmative action or reporting requirements, under the Kentucky Equal Employment Act of 1978, KRS 45.560 to 45.640 hereinafter referred to as The Act, if any of the following conditions are applicable: 51.1 The Contractor and Subcontractors are exempt from any affirmative action or

reporting requirements, under the Kentucky Equal Employment Act of 1978, KRS 45.560 to 45.640 hereinafter referred to as The Act, if any of the following conditions are applicable: 51.1.1 The Contract or Subcontract awarded is in the amount of five hundred

thousand dollars ($500,000) or less, and the amount of the contract is not a subterfuge to avoid compliance with the provisions of The Act; or

51.1.2 The Contractor or Subcontractor utilizes the services of fewer than eight (8) employees during the course of the Contract; or

51.1.3 The Contractor or Subcontractor employs only family members or relatives; or

51.1.4 The Contractor or Subcontractor employs only persons having a direct Ownership interest in the business and such interest in not a subterfuge to avoid compliance with the provisions of The Act.

51.2 The Contractor or Subcontractor not otherwise exempted shall for the duration of the Contract, hire minorities from within the drawing area to satisfy the agreed upon goals and timetables set out in addenda to the Contract. Should the union with which the Contractor has collective bargaining agreements be unwilling to provide sufficient minorities to satisfy the goals and timetables, the Contractor shall hire minorities from other sources within the drawing area to satisfy the goals and timetables in the addenda to the Contract.

51.3 The equal employment provisions of The Act may be met in part by the Contractor subcontracting to a minority contractor or subcontractor. A minority contractor or subcontractor shall be defined by the addenda to this Contract, or if none, by the Act.

51.4 Each Contractor shall, for the length of the Contract, furnish such information as required by The Act and by such rules, regulations and orders issued pursuant thereto and will permit access to all books and records pertaining to his/her employment practices and work sites by the contracting agency and the department for purposes of investigation to ascertain compliance with The Act and such rules, regulations and orders issued pursuant thereto.

51.5 If the Contractor is found to have committed an unlawful practice against a provision of The Act during the course of performing under this Contract, (if covered by The Act), the Owner may cancel or terminate the Contract, conditioned upon a program for future compliance approved by the Owner. The Owner may also declare such Contractor ineligible to bid on further contracts until such time as the Contractor complies in full with the requirements of The Act.

51.6 The Contractor shall not be required to terminate an existing employee, upon proof that employee was employed prior to the date of the Contract nor hire anyone who fails to demonstrate the minimum skills required to perform a particular job.

52. Access to RecordsThe contractor, as defined in KRS 45A.030(7), agrees that EKU, the Finance and

Administration Cabinet, the Auditor of Public Accounts, and the Legislative Research Commission, or their duly authorized representatives, shall have

Page 56: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

37 General Conditions

access to any books, documents, papers, records, or other evidence, which are directly pertinent to this contract for the purpose of financial audit or program review. Furthermore, any books, documents, papers, records, or other evidence provided to the EKU, the Finance and Administration Cabinet, the Auditor of Public Accounts, or the Legislative Research Commission which are directly pertinent to the contract shall be subject to public disclosure regardless of the proprietary nature of the information, unless specific information is identified and exempted and agreed to by the Secretary of the Finance and Administration Cabinet as meeting the provisions of KRS 61.878(1)(c) prior to the execution of the contract. The Secretary of the Finance and Administration Cabinet shall not restrict the public release of any information which would otherwise be subject to public release if a state government agency was providing the service (22 Ky.R. 1510; eff. 5-16-96.).

53. Campus MapFor a digital copy of our updated map see http://parking.eku.edu/.

Page 57: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Bid Number: 94-19

Project: Begley Building Roof Replacement

Project Specifications

Page 58: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Page 1 of 18

CAPITAL CONSTRUCTION AND PROJECT ADMINISTRATIONBEGLEY BUILDING PRESS BOX ROOF REPLACEMENT

2019PROJECT SCOPE

1. This project is located on the Eastern Kentucky University Campus, in Richmond Kentucky. It will consist of re-roofing an existing roof in the manner as specified herein. Roof area is approximately 1,860 sq. ft. (Contractor to verify)

2. The owner representative of this project is Kishore Acharya @ 859-622-2966.

3. As noted in the attached documents, the company that bids these projects must have successfully completed similar projects in both size and complexity. It must also be noted and emphasized that the above referenced jobs must have been completed to the satisfaction of the owner both administratively and physically. Eastern will review the roofing contractor’s past roofing projects based on both criteria and Eastern retains the right to reject the low bidder based on either or both of these.

4. All work attached (unless otherwise noted) shall include labor, material, equipment, and services necessary for the installation and completion of the roofs as indicated on the attachments.

5. This building will be in continuous use and daily roofing activities shall maintain the roof integrity such that all areas beneath the roof deck remain dry.

6. All roof drains must be inspected by contractor to insure of no STOPPAGE before work shall commence. Owner shall be contacted immediately by WRITTEN notice. All drains are declared to be fully functional and the contractor is responsible for maintaining full function through the term of contract unless the owner is notified in writing prior to start of work.

7. The following information must be submitted at time of bid opening and contains information that is pertinent to company submission bid:

A. 5 similar jobs in size and complexity. (Please provide current phone number and name of client’s contact.)

B. 5 years experience in installing modified roof systems.

C. Letter from the proposed primary roofing manufacturer confirming that the bidder is an acceptable contractor authorized to install the proposed system.

D. Sample of 20 years of roof membrane guarantee.

E. Letter from the primary roofing manufacturer stating that the proposed application will comply with the owner’s requirements in order to qualify the project for the specified guarantee.

F. If a “approved equivalent” is submitted, other than a product specified within these contract documents, the contractor shall submit general product data at time of bid opening.

Page 59: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Page 2 of 18

These documents will not be accepted at a later date. Not submitting such willindicate that all items bid, are “as specified”. Other specific submittals (see RoofingSpecification 1.06) will be required and reviewed before a purchase order is issued.

8. Work can commence after approval of submittals and shop drawings and purchaseorder releases and shall be completed by August 1, 2019. (Final completion is reachedwhen all punch list items for the completion of the roof have been corrected to the owner’sand factory representative’s satisfaction.)

9. Liquidated damages will be $190.00 for each day the project exceeds the final completion.

10. Once the job has begun, it is the responsibility of the contractor to notify, via e-mail or fax,any day that there is progress delay due to weather or other unforeseen circumstancesbeyond the contractor’s control. This record will be used by the owner in determining if therewill be any time extensions given to the contractors. Substantiated requests for extensionsdue to weather shall be reasonably granted. “Substantiated” means the National WeatherService has recorded more than “trace” precipitation on its closest rain gage station.

11. Two (2) interim field inspections will be required by the owner by the roofing manufacturer.This inspection shall be performed by a field tech with the owner receiving a 48-houradvance notice. These inspections shall take place Monday through Friday. Owner’srepresentative must be present. Interim inspection must be done before applying capsheet. (No exception)

12. Contractor must keep sets of Specifications and details, Material Safety Data Sheet (MSDS)at construction site all time and must be able to furnish those documents to authority uponrequest.

13. Attached roof details are for assisting in bidding. Contractor shall submit shop drawing forapproval from the owner before commencement of work.

ATTACHEMENTS:

1. Roofing Specification2. Roof Details

Page 60: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Page 3 of 18

EASTERN KENTUCKY UNIVERSITYBEGLEY PRESSBOX BUILDING ROOF REPLACEMENT

ROOFING SPECIFICATION

PART 1 GENERAL

1.01 GENERAL REQUIREMENTS

A. Deviations: In the event this Specification deviates from the manufacturer's currentspecification, this specification prevails, except where they conflict with themanufacturer's requirements for the specified guarantee. In this case, the manufacturer'sspecification prevails.

B. Specification Amendments: Drawings, addenda and modifications may be issuedsubsequent to the publishing of this Specification for bidding.

C. Contractor Acceptance: Prior to the project start, ascertain that all aspects of thisSpecification and possible modifications are workable and do not conflict with themanufacturer's requirements for the specified guarantee. Upon commencement of thework, it will be presumed that this Specification and drawings, addenda andmodifications are satisfactory to both the Contractor and the manufacturer in theirentirety.

D. Supplied Materials: Supply all materials of the roofing system, including accessoryproducts. The bidding Contractor, by making his bid, represents that his bid price isbased on the use of the materials listed in Part 2 Products. Refer to Part 1.03Description of Work for specific use within each roofing assembly outlined.

1.02 REFERENCE STANDARDS

References in these specifications to standards, test methods, and codes, are implied to mean thelatest edition of each such standard adopted. The following is an abbreviated list of associations,institutions, and societies which may be used as references throughout these specifications.

ASTM American Society for Testing and MaterialsPhiladelphia, PA

FM Factory Mutual Engineering and ResearchNorwood, MA

NRCA National Roofing Contractors AssociationRosemont, IL

OSHA Occupational Safety and Health AdministrationsWashington, DC

SMACNA Sheet Metal and Air Conditioning Contractors National AssociationChantilly, VA

UL Underwriters LaboratoriesNorthbrook, IL

Page 61: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Page 4 of 18

1.03 DESCRIPTION OF WORK

The basic work descriptions (components, layering and attachment methods) required in thisspecification are referenced below.

Project Type: Tear-off existing roof and replace Specification #: 2030 IA /2FID-CAwith complete roofing system

Deck: Concrete Slope: Flat roof deck

Rigid Insulation: Polyisocyanurate, having a thickness of 2” inches double layer, adheredwith Para-Stik or JM MBR Bonding or equal insulation adhesive on concretedeck.

Tapered Insulation: Polyisocyanurate, tapered insulation with a minimum of 1/8” per ftslope, saddles and crickets with a minimum of ¼” per ft slope applied in Para-Stik insulation adhesive or JM MBR Bonding Adhesive or equal.

Recover Board: Siplast High density fiberboard or JM Duraboard or equal, having athickness of 1/2” adhered with Para-Stik or JM MBR Bonding or equalinsulation adhesive on concrete deck.

Roof system: Paradiene 20, applied in PA-311R Adhesive or Johns Manville DynaBaseinstalled in Johns Manville MBR Cold Adhesive or equal.

Paradiene 30 FR, applied in PA-311R Adhesive or Johns ManvilleDynaGlass FR installed in Johns Manville MBR Cold Adhesive or equal.

Flashing system: Siplast Veral Aluminum or Johns Manville DynaClad, or equal torchapplied or as recommended by manufacturer.

1.04 QUALITY ASSURANCE

A. Acceptable Products: Primary roofing products, including each type of sheet, allmanufactured in the United States, shall be supplied by a single manufacturer which hasbeen successfully producing the specified types of primary products for not less than 25years. The primary roofing products shall have maintained a consistent composition for aminimum of five years.

> Manufacturers –

1. Siplast or approved equivalent2. Johns Manville or approved equivalent3. Garland or approved equivalent

B. Agency Approvals: The proposed roof system shall conform to the followingrequirements. No other testing agency approvals will be accepted.

1. Underwriters Laboratories Class A acceptance of the proposed roofing system(including cold adhesive) without additional requirements for gravel or coatings.

2. Factory Mutual Approval Standard 4470 listing or letter of acceptance from FM for theproposed membrane system. The roof membrane configuration shall be approved byFM for Class 1. The roof configuration (including fastening of base sheet or insulation)shall be approved by FM for minimum 1-90 windstorm construction.

Page 62: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Page 5 of 18

C. Acceptable Contractor: Contractor shall have a minimum of 5 years experience insuccessfully installing the same or similar roofing materials and be certified in writing bythe roofing materials manufacturer to install the primary roofing products.

D. Scope of Work: The work to be performed under this specification shall include but isnot limited to the following: Attend necessary job meetings and furnish competent andfull time supervision, experienced roof mechanics, all materials, tools, and equipmentnecessary to complete, in an acceptable manner, the roof installation in accordance withthis specification. Comply with the latest written application instructions of themanufacturer of the primary roofing products. In addition, application practice shallcomply with requirements and recommendations contained in the latest edition of theHandbook of Accepted Roofing Knowledge (HARK) as published by the NationalRoofing Contractors Association, amended to include the acceptance of a phased roofsystem installation.

E. Local Regulations: Conform to regulations of public agencies, including any specificrequirements of the city and/or state of jurisdiction.

F. Manufacturer Requirements: Ensure that the primary roofing materials manufacturerprovides direct trained company personnel to attend necessary job meetings, performperiodic inspections as necessary, and conducts a final inspection upon successfulcompletion of the project.

1.05 GUARANTEE/WARRANTY

Roof System Guarantee: Upon successful completion of the project, and after all post installation procedures have been completed, furnish the Owner with the roof system manufacturer's 20 year labor and materials roof system guarantee. The roof system guarantee shall include both the roofing and flashing membranes, and rigid insulation system (Ployisocyanurarte and fiberboard). All repair or replacement costs covered under the guarantee shall be borne by the roofing membrane manufacturer. The guarantee shall be a term type, without deductibles or limitations on coverage amount, and be issued at no additional cost to the Owner.

> Siplast 20 Year Roof System Guarantee or a Johns Manville 20 year NDL or a Garland20 year NDL.

1.06 SUBMITTALS

All submittals which do not conform to the following requirements will be rejected.

A. Submittals Prior to Contract Award:

1. Letter from the proposed primary roofing manufacturer confirming that the bidder isan acceptable Contractor authorized to install the proposed system.

2. Letter from the primary roofing manufacturer stating that the proposed application willcomply with the manufacturer's requirements in order to qualify the project for thespecified guarantee.

Page 63: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Page 6 of 18

C. Submittals Prior to Project Close-out (Also see General Conditions):

1. Certificate Of Analysis from the testing laboratory of the primary roofing materialsmanufacturer, confirming the physical and mechanical properties of the roofingmembrane components. Testing shall be in accordance with the parameterspublished in ASTM D 5147 and ASTM D 6298* and indicate QualityAssurance/Quality Control data as required to meet the specified properties:

a) Material typeb) Dimensions and Mass (indicate the lowest values recorded during the production run);

- Roll length- Roll width- Selvage width- Total thickness- Thickness at selvage (coating thickness)- Weight

c) Physical and Mechanical Properties;- Low temperature flexibility- Maximum load- Elongation @ 5% Maximum Load (ultimate elongation)- Dimensional stability- High Temperature Stability- Granule embedment- Resistance to thermal shock* (foil faced products)

2. Manufacturer's printed recommendations for proper maintenance of the specifiedroof system including inspection frequencies, penetration addition policies, temporaryrepairs, and leak call procedures.

1.07 PRODUCT DELIVERY STORAGE AND HANDLING

A. Delivery: Deliver materials in the manufacturer's original sealed and labeled containersand in quantities required to allow continuity of application.

B. Storage: Store materials out of direct exposure to the elements. Store roll goods on aclean, flat and dry surface. All material stored on the roof overnight shall be stored onpallets. Rolls of roofing must be stored on ends. Store materials on the roof in a mannerso as to preclude overloading of deck and building structure. Store materials such assolvents, adhesives and asphalt cutback products away from open flames, sparks orexcessive heat. Cover all material using a breathable cover such as a canvas.Polyethylene or other non-breathable plastic coverings are not acceptable.

C. Handling: Handle all materials in such a manner as to preclude damage andcontamination with moisture or foreign matter. Handle rolled goods to prevent damage toedges or ends.

D. Damaged Material: Any materials that are found to be damaged or stored in anymanner other than stated above will be automatically rejected, removed and replaced atthe Contractor's expense.

Page 64: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Page 7 of 18

1.08 PROJECT/SITE CONDITIONS

A. Requirements Prior to Job Start

1. Notification: Give a minimum of 10 days notice to the Owner and manufacturerprior to commencing any work and notify both parties on a daily basis of any changein work schedule.

2. Permits: Obtain all permits required by local agencies and pay all fees which may berequired for the performance of the work.

3. Safety: Familiarize every member of the application crew with all fire and safetyregulations recommended by OSHA, NRCA and other industry or local governmentalgroups.

B. Environmental Requirements

1. Precipitation: Do not apply roofing materials during precipitation or in the eventthere is a probability of precipitation during application. Take adequate precautions toensure that material, applied roofing, and building interiors are protected frompossible moisture damage or contamination.

2. Temperature Restrictions - cold adhesive: At low temperatures, the specified coldadhesive becomes more viscous, making even distribution more difficult. The optimaltemperature of the adhesive at point of application is 70F (21C). To facilitateapplication when ambient temperatures are below 50F (10C), store the adhesiveand roll goods in a warm place immediately prior to use. Roll or broom the sheets toensure contact with the underlying adhesive. Suspend application in situations wherethe adhesive cannot be kept at temperatures allowing for even distribution.

C. Protection Requirements (also see General Condition)

1. Membrane Protection: Provide protection against staining and mechanical damagefor newly applied roofing and adjacent surfaces throughout this project.

2. Torch Safety: Designate one person on each crew to perform a daily fire watch. Thedesignated crew member shall watch for fires or smoldering materials on all areas ofroof construction Continue the fire watch after roofing material application has beensuspended for the day.

3. Limited Access: Prevent access by the public to materials, tools and equipmentduring the course of the project.

4. Debris Removal: Remove all debris daily from the project site and take to a legaldumping area authorized to receive such materials.

5. Site Condition: Complete, to the owner's satisfaction, all job site clean-up includingbuilding interior, exterior and landscaping (see General Condition) where affected bythe construction.

PART 2 PRODUCTS

2.01 ROOFING SYSTEM ASSEMBLY/PRODUCTS

A. Rigid Roof Insulation: Roof insulation shall be UL and FM approved. Insulation shall beapproved in writing by the insulation manufacturer for intended use and for use with the

Page 65: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Page 8 of 18

specified roof assembly. Maintain a maximum panel size of 4 feet by 4 feet whereinsulation is specified to be installed in insulation adhesive.

1. Polyisocyanurate: A closed cell, rigid polyisocyanurate foam core material, integrallylaminated to facers, in full compliance with ASTM C 1289, Type II, Class 1, Grade 2.Panels shall have a thickness of 2 inches double layer. Acceptable types are asfollows:

> H-Shield by Hunter Panels, LLC, Portland, ME> Siplast Paratherm> Johns Manville or approved equivalent

2. Fiberboard: A high density panel composed of interlocking wood fibers andwaterproofing binders, having a top surface that is pre-treated with an asphalt basedcoating. Fiberboard panels shall be in full compliance with ASTM C 208, Type II,Grade 2, and ASTM C 209 (water absorption - 10% volume maximum) requirements.Panels shall have a thickness of ½ inch. Acceptable types are as follows:

> Siplast Paratherm Wood Fiberboard by Siplast; Irving, TX> Johns Manville Duraboard or manufacturer approved ½” High-density wood fiber

board by Johns Manville, Denver, CO> Structodeck by the Knight/Celotex; Chicago, IL or equal

2.02 DESCRIPTION OF SYSTEMS

A. Roofing Membrane Assembly: A roof membrane assembly consisting of two plies of aprefabricated, reinforced, homogeneous Styrene-Butadiene-Styrene (SBS) blockcopolymer modified asphalt membrane, applied over a prepared substrate. Bothreinforcement mats shall be impregnated/saturated and coated each side with an SBSmodified bitumen blend. The roof system shall pass 500 cycles of ASTM D 5849Resistance to Cyclic Joint Displacement (fatigue) at 14F (-10C). Passing results shallshow no signs of membrane cracking or interply delamination after 500 cycles. The roofsystem shall pass 200 cycles of ASTM D 5849 after heat conditioning performed inaccordance with ASTM D 5147. The assembly shall possess waterproofing capability,such that a phased roof application, with only the modified bitumen base ply in place,can be achieved for prolonged periods of time without detriment to the watertightintegrity of the entire roof system.

> Siplast Paradiene 20/30 FR roof system or Johns Manville DynaBase/DynaGlass FRroof system or equal

1. Modified Bitumen Base and Stripping Ply

a) Thickness (avg): 90 mils (2.3 mm) (ASTM D 5147)b) Thickness (min): 87 mils (2.2 mm) (ASTM D 5147)c) Weight (min per 100 ft² of coverage): 62 lb (3.0 kg/m²)d) Maximum filler content in elastomeric blend - 35% by weighte) Low temperature flexibility @ -13ºF (-25ºC): PASS (ASTM D 5147)f) Maximum Load (avg) @ 73ºF (23ºC): 30 lbf/inch (5.3 kN/m) (ASTM D 5147)g) Maximum Load (avg) @ 0ºF (-18ºC): 70 lbf/inch (12.3 kN/m) (ASTM D 5147)h) Elongation @ 5% Maximum Load (avg.) @ 73ºF (23ºC): 50% (ASTM D 5147)

Page 66: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Page 9 of 18

i) Dimensional Stability (max): 0.1% (ASTM D 5147)j) High Temperature Stability (min): 250ºF (121ºC) (ASTM D 5147)k) Approvals: UL Class listed, FM Approved (products shall bear seals of approval)l) Reinforcement: fiberglass mat or other meeting the performance and dimensional

stability criteria

> Siplast Paradiene 20 or Johns Manville DynaBase or equal

2. Modified Bitumen Finish Ply

a) Thickness (avg): 130 mils (3.3 mm) (ASTM D 5147)b) Thickness at selvage (coating thickness) (avg): 98 mils (2.5 mm) (ASTM D 5147)c) Thickness at selvage (coating thickness) (min): 94 mils (2.4 mm) (ASTM D 5147)d) Weight (min per 100 ft² of coverage): 90 lb (4.4 kg/m²)e) Maximum filler content in elastomeric blend: 35% by weightf) Low temperature flexibility @ -13º F (-25º C): PASS (ASTM D 5147)g) Maximum Load (avg) @ 73ºF (23ºC): 30 lbf/inch (5.3 kN/m) (ASTM D 5147)h) Maximum Load (avg) @ 0ºF (-18ºC): 75 lbf/inch (13.2 kN/m) (ASTM D 5147)i) Elongation @ 5% Maximum Load (avg.) @ 73ºF (23ºC): 55% (ASTM D 5147)j) Dimensional Stability (max): 0.1% (ASTM D 5147)k) High Temperature Stability (min): 250ºF (121º C) (ASTM D 5147)l) Granule Embedment (max loss): 2.0 grams per sample (ASTM D 5147)m) Approvals: UL Class listed, FM Approved (products shall bear seals of approval)n) Reinforcement: fiberglass mat or other meeting the performance and dimensional

stability criteriao) Surfacing: ceramic granules

> Siplast Paradiene 30 FR or Johns Manville DynaGlass FR or equal

B. Flashing Membrane Assembly: A flashing membrane assembly consisting of aprefabricated, reinforced, Styrene-Butadiene-Styrene (SBS) block copolymer modifiedasphalt membrane with a continuous, channel-embossed metal-foil surfacing. The finishply shall conform to ASTM D 6298 and the following physical and mechanical propertyrequirements.

> Siplast Veral or JM DynaClad flashing system, aluminum finish or equal

1. Metal-Clad Modified Bitumen Flashing Sheet

a) Thickness (avg): 150 mils (3.6 mm) (ASTM D 5147)b) Thickness (min): 146 mils (3.5 mm) (ASTM D 5147)c) Weight (min per 100 ft² of coverage): 96 lb (4.5 kg/m²)d) Coating Thickness – back surface (min): 40 mils (1 mm) (ASTM D 5147)e) Maximum filler content in elastomeric blend: 35% by weightf) Low temperature flexibility @ 0º F (-18º C): PASS (ASTM D 5147)g) Maximum Load (avg) @ 73ºF (23ºC): 85 lbf/inch (15 kN/m) (ASTM D 5147)h) Maximum Load (avg) @ 0ºF (-18ºC): 180 lbf/inch (31.7 kN/m) (ASTM D 5147)i) Elongation @ 5% Maximum Load (avg) @ 73ºF (23ºC): 45% (ASTM D 5147)j) Tear-Strength (avg): 120 lbf (0.54 kN) (ASTM D 5147)k) Dimensional Stability (max): 0.2% (ASTM D 5147)l) High Temperature Stability (min): 225ºF (107ºC) (ASTM D 5147)

Page 67: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Page 10 of 18

m) Cyclic Thermal Shock Stability (maximum): 0.2% (ASTM D 6298)n) Approvals: UL Approved, FM Approved (products shall bear seals of approval)o) Reinforcement: fiberglass scrim mat or other meeting the performance and

dimensional stability criteriap) Surfacing: aluminum metal foil

> Siplast Veral Aluminum or Johns Manville DynaClad or equal

2. Flashing Reinforcing Ply - (Same as roof system base ply)

C. Catalyzed Acrylic Resin Flashing System: (“liquid flashing” as required) Aspecialty flashing system consisting of a liquid-applied, fully reinforced, multi-componentacrylic membrane installed over a prepared or primed substrate. The flashing systemconsists of a catalyzed acrylic resin primer, basecoat and topcoat, combined with a non-woven polyester fleece. The resin and catalyst are pre-mixed immediately prior toinstallation. The use of the specialty flashing system shall be specifically approved inadvance by the membrane manufacturer for each application.

> Parapro 123 Flashing System by Siplast; Irving, TX or Johns Manville Permaflash orequal (shall be covered under roofing warranty).

2.03 ROOFING ACCESSORIES

A. Roofing Adhesives

1. Insulation Adhesive: A single component, moisture cured, polyurethane foamadhesive, dispensed from a portable, pre-pressurized container used to adhereinsulation panels to the substrate as well to other insulation panels.

> Para-Stik Insulation Adhesive by Siplast; Irving, TX or equal

2. Membrane Cold Adhesive: A blend of special adhesive asphalts and safe, high-flash, quick drying solvents that meets or exceeds ASTM D 4479, Type IIrequirements.

> Siplast PA-311R Adhesive by Siplast; Irving, TX or Johns Manville MBR ColdApplication Adhesive or equal

3. Flashing Adhesive: A slump resistant, asphalt cutback flashing adhesive, reinforcedwith non-asbestos fibers, conforming to ASTM D 4586 Type II requirements.

> Siplast PA-828 Flashing Cement or Johns Manville MBR Flashing Cement orequal

4. Solvent-Free Flashing Adhesive: A single-component, solvent-free modifiedadhesive. The adhesive blend shall be formulated in a grade for application offlashing materials.

> Siplast SFT Cement by Siplast; Irving, TX or Johns Manville MBR FlashingCement or equal

Page 68: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Page 11 of 18

B. Bituminous Cutback Materials

1. Asphalt Primer: A high flash, quick drying, asphalt solvent blend which meets orexceeds ASTM D 41 requirements.

> Siplast PA-1125 Asphalt Primer by Siplast; Irving, TX or Johns Manville Primer orequal

2. Mastics: An asphalt cutback mastic, reinforced with non-asbestos fibers, used as abase for setting metal flanges conforming to ASTM D 4586 Type II requirements.

> Siplast PA-1021 Plastic Cement by Siplast; Irving, TX or Johns Manville FlashingCement or equal

C. Sealant: A moisture-curing, non-slump elastomeric sealant designed for roofingapplications. The sealant shall be approved by the roof membrane manufacturer for usein conjunction with the roof membrane materials. Acceptable types are as follows:

> Siplast PS-715 Elastomeric Sealant by Siplast; Irving, TX or Johns Manville TopGardor equal

D. Ceramic Granules: No. 11 grade specification ceramic granules of color schemematching the granule surfacing of the finish ply.

E. Metallic Powder: A finely graded metal dust as supplied or approved by the membranemanufacturer, used for covering of bitumen overruns over the foil surfaced membrane.

F. Fasteners

1. Wood Nailer FastenersAll fasteners and plates shall be FM Approved, and/or approved by the manufacturerof the primary roofing products.

2. Wood AnchorageProvide galvanized bolts, nuts, washers, shims, pins, fasteners, screws, straps,nails and other type anchors, which may be required by job conditions to secure thework permanently in place, whether or not specifically called or shown on drawings.

G. Pitch Pocket: A pre-fabricated inter-locking pitch pan system that is easily assembledon site and filled with fast setting, solvent free, multi-use that becomes waterproof inminutes of application and covered with 20 year performance warranty.

2.04 RELATED COMPONENTS

A. Fabricated Metal: Fabricate all metal components to be used in conjunction with theroof system using 22 gauge galvanized steel, and a Kynar 500 finish (from manufacturerstandard coil coated colors), meeting ASTM A 526 specifications. Standard length ofproduct shall be 10 ft. with concealed splice plates at joints. All cleats to be 20 gauge.No “oil canting” will be accepted on perimeter flashing. Joint of cleat and fascia shall bestaggered by at least 2’. Nails on cleat should be less than 12” on center.

Page 69: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Page 12 of 18

PART 3 EXECUTION

3.01 FIELD QUALITY CONTROL

A. Pre-Job Conference: Conduct a pre-job conference to include the designer, Owner,roofing Contractor and manufacturer's representative prior to application of roofing.

B. Superintendent: Provide the roofing superintendent with a copy of these specificationsto be available at the job site at all times. The presence of specifications and aninspector shall not relieve the Contractor of strict compliance with the manufacturer'sspecifications, detail drawings, and/or approved material requirements.

C. Deck Penetrations: Verify that work penetrating the roof deck, or which may otherwiseaffect the roofing application, has been properly completed.

D. Final Inspection – post installation meeting: Arrange a meeting at the completion ofthe project to be attended by all parties that were present at the pre-job conference. Apunch list of items required for completion shall be compiled by the Contractor and themanufacturer's representative. Complete, sign, and mail the punch list form to themanufacturer's headquarters.

3.02 PREPARATION

A. General: Sweep or vacuum all surfaces, removing all loose aggregate and foreignsubstances prior to commencement of roofing.

B. Remove All Existing:Existing roof consists of 2 ply modified bitumen roof over 3 layers of fiberglass insulationboard adhered to flat concrete deck (approximate thickness of roof system is 2.75” andcontractor is responsible for measuring exact thickness of the system.)- Roof membrane- Insulation- Base flashings- Edge metal- Flanged metal flashings- Non functional penetrations/curbs- Cants- Drain assemblies- Vapor retarder- Metal trim, counter flashing etc.

C. Wall Preparation: Repair minor cracks, surface irregularities, and open joints inconcrete walls using a quick dry grout mix to ensure a smooth, even surface forapplication of the roofing/flashing membranes.

3.03 SUBSTRATE REQUIREMENTS

Repair concrete deck that damaged during roof removal using a cementatious product thatis compatible and meets industry standard for such repair.

Page 70: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Page 13 of 18

3.04 SUBSTRATE PREPARATION

A. Perimeter Wood Nailers: Install perimeter wood nailers in accordance with theguidelines set forth in latest edition of Factory Mutual Loss Prevention Bulletin 1-49.

B. Insulation: Install insulation panels and fiberboard with end joints offset; edges of thepanels shall be in moderate contact without forcing applied in strict accordance with theinsulation manufacturer's requirements and the following instructions:

Stagger joints between two layers of Insulation and fiber board. Fully adhere all layersusing a single-component polyurethane adhesive (Para-Stik or equal) on concrete deck.Fastener or adhesive must be applied in accordance with guidelines set forth by FM 1-90.

Polyisocyanurate ⅛” per foot minimum slope Tapered insulation should be attached tobase layer of polyisocyanurate to provide positive roof slope to avoid ponding of water.Saddle and Cricket shall have minimum of ¼” per foot slope.

3.05 ROOF MEMBRANE INSTALLATION - GENERAL

A. Membrane Application: Apply roofing in accordance with roofing systemmanufacturer's instructions and the following requirements. Application of roofingmembrane components shall immediately follow application of base sheet and/orinsulation as a continuous operation.

B. Aesthetic Considerations: An aesthetically pleasing overall appearance of the finishedroof application is a standard requirement for this project. Make necessary preparations,utilize recommended application techniques, apply the specified materials includinggranules and metallic powder, and exercise care in ensuring that the finished applicationis acceptable to the Owner.

C. Priming: Prime metal and concrete and masonry surfaces with a uniform coating of thespecified asphalt primer.

D. Membrane Adhesive Application: Membrane adhesive can be applied by roller,squeegee or spray unit. Apply cold adhesive in a smooth, even, continuous layer withoutbreaks or voids. Utilize an application rate of 2 to 2 1/2 gal/sq (0.6 to 1.0 l/m²) overirregular or porous substrates. Utilize an application rate of 1 1/2 to 2 gal/sq (0.6 to 0.8kg/m²) for interply applications. Double the adhesive application rate at the end laps ofgranule surfaced sheets. In the areas surrounding details that shall receive the catalyzedacrylic resin primer and flashing system, apply membrane plies in a full coating of thespecified elastomeric sealant in lieu of the solvent based adhesive a minimum 8 inchesfrom the base of the penetration or curb.

E. Bitumen Consistency: Cutting or alterations of bitumen, primer, and sealants will notbe permitted.

F. Roofing Application: Apply all layers of roofing free of wrinkles, creases or fish mouths.Exert sufficient pressure on the roll during application to ensure prevention of airpockets.

Page 71: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Page 14 of 18

1. Apply all layers of roofing perpendicular to the slope of the deck.

2. Fully bond the base ply to the prepared substrate, utilizing minimum 3 inch side andend laps. Apply each sheet directly behind the cold adhesive applicator. Cut a dogear angle at the end laps on overlapping selvage edges. Using a clean trowel, applytop pressure to top seal T-laps immediately following sheet application. Stagger endlaps a minimum of 3 feet.

3. Fully bond the finish ply to the base ply, utilizing minimum 3 inch side and end laps.Apply each sheet directly behind the cold adhesive applicator. Stagger end laps ofthe finish ply a minimum 3 feet. Cut a dog ear angle at the end laps on overlappingselvage edges. Using a clean trowel, apply top pressure to top seal T-lapsimmediately following sheet application. Stagger side laps of the finish ply aminimum 12 inches from side laps in the underlying base ply. Stagger end laps of thefinish ply a minimum 3 feet from end laps in the underlying base ply.

G. Granule Embedment: Broadcast mineral granules over all bitumen overruns on thefinish ply surface, while the bitumen is still hot or the adhesive is soft, to ensure amonolithic surface color.

H. Catalyzed Acrylic Resin Flashing System: Install the liquid-applied primer andflashing system in accordance with the membrane system manufacturer’s printedinstaller’s guidelines and other applicable written recommendations as provided by themanufacturer.

I. Use of Metallic Powder: Broadcast metallic powder over all bitumen overruns on themetal foil membrane surface while the bitumen is still hot to ensure a monolithic surfacecolor.

J. Water Cut-Off: At end of day's work, or when precipitation is imminent, construct awater cut-off at all open edges. Cut-offs can be built using asphalt or plastic cement androofing felts, constructed to withstand protracted periods of service. Cut-offs must becompletely removed prior to the resumption of roofing.

3.06 RELATED COMPONENTS - INSTALLATION

A. Sealant: Caulk all exposed finish ply edges at the transition to metal flashingsincorporated into the roof system with a smooth continuous bead of the specifiedsealant.

B. Roof Drain Dome: Replace roof drain cover with new one if existing cover is broken andcannot be reused.

3.07 SPECIAL CONDITIONS

A. Site Condition: Leave all areas around job site free of debris, roofing materials,equipment and related items after completion of job.

B. Notification of Completion: Notify the manufacturer by means of manufacturer'sprinted Notification of Completion form of job completion in order to schedule a finalinspection date.

Page 72: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Page 15 of 18

C. Issuance of the Guarantee: Complete all post installation procedures and meet themanufacturer's final endorsement for issuance of the specified guarantee.

Page 73: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Bid Number: 94-19 Project: Begley Building Roof Replacement

Project Drawings

Page 74: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Page 16 of 18

Existing drawings from 1967 as-built are provided below only for reference. Field verification is required for the accuracy.

Page 75: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Page 17 of 18

Page 76: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Page 18 of 18

Page 77: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Details Page 1 of 10

AcharyaK
Callout
Remove and dispose off
AcharyaK
Architect
Remove and dispose off existing flashing, roof edge, air conditioning unit, wood blocking and pipes. Note: Refrigerant lines and electric lines will be disconnected by other before roofing project starts.
AcharyaK
Callout
Refer typical detail 4.
AcharyaK
Callout
Refer typical detail 3.
AcharyaK
Callout
Refer typical detail 2.
AcharyaK
Callout
Refer typical detail 1 for parapet walls.
AcharyaK
PolyLine
AcharyaK
Callout
Refer typical detail 1.
AcharyaK
PolyLine
AcharyaK
PolyLine
AcharyaK
Cloud+
AcharyaK
Cloud+
Extend Coping Metal assembly of detail 1 on all fins.
AcharyaK
Cloud+
AcharyaK
Cloud+
Liquid flashing to a minimum of 8" hight before applying coping metal assembly (Typical).
AcharyaK
Engineer
4'-1"
AcharyaK
Text Box
8" Min.
AcharyaK
PolyLine
AcharyaK
PolyLine
AcharyaK
Architect
Create a positive slope using tapered insulation as specified in specification. Ponding of water is not acceptable. Minimum slope of tapered insulation shall be 1/8" per foot and saddle & cricket shall be 1/4" per foot.
Page 78: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Details Page 2 of 10

AcharyaK
Polygon
AcharyaK
Architect
Remove and dispose off existing flashing, roof edge, air conditioning unit, wood blocking and pipes. Note: Refrigerant lines and electric lines will be disconnected by other before roofing project starts.
AcharyaK
Callout
Install Walkpad. Refer typical detail 6.
AcharyaK
Engineer
feet 6'-10 1/8"
AcharyaK
Engineer
feet 19'-6 1/8"
AcharyaK
Engineer
feet 14'-7 1/2"
AcharyaK
Engineer
feet 18'-1/8"
AcharyaK
Text Box
5'
AcharyaK
Text Box
4'
AcharyaK
Text Box
10'
AcharyaK
Text Box
2'-6"
AcharyaK
Callout
Replace existing pipe with 4" PVC pipe. For additional information refer typical detail 5.
AcharyaK
Callout
Refer typical detail 4.
AcharyaK
Callout
Refer typical detail 3.
Page 79: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Details Page 3 of 10

AcharyaK
Callout
Remove and dispose off air conditioning unit, wood blocking and pipes. Note: Refrigerant lines and electric lines will be disconnected by other before roofing project starts.
AcharyaK
Callout
Refer typical detail 4.
Page 80: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

Details Page 4 of 10

AcharyaK
Callout
Remove and dispose off existing anchors.
AcharyaK
Callout
Existing electrical boxes stay. Apply liquid flashing as specified in specification.
Page 81: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

PARADIENE 30 FR

(fully adhere, prepare granule surfaces)

PARADIENE 20

(nail to plywood surface 12" o.c., fully adhere

to cant and roof surface areas)

PARADIENE 20

(dry on cant, fully adhere to roof surfaces)

VERAL

(torch to prepared surfaces)

1"3"

COPING METAL ASSEMBLY

ATTACH 2X DOUGLAS FIR OR EQUAL TO CONCRETE

PARAPET WITH CONSTRUCTION ADHESIVE AND POWER

FASTENERS

1

4

"X3

1

4

" WITH PHILLIPS HEAD AND SHALL BE

COUNTERSUNK

2 1

/2

" M

IN

. B

EL

OW

BL

OC

KIN

G

NON-COMBUSTIBLE CANT

N.T.S.

TYPICAL DETAIL - 1

NOTES: 1. PREPARE GRANULE SURFACES UNDER VERAL FLASHING BY TORCH PREPARATION.

2. THE CARPENTRY AND METAL WORK SHOWN DEPICTS SHOP FABRICATION AND JOB-SITE ASSEMBLY. THESE COMPONENTS SHOULD BE

DESIGNED/FABRICATED/INSTALLED ACCORDING TO GENERALLY ACCEPTED INDUSTRY PRACTICES, STANDARDS AND APPROVALS.

3. DISSIMILAR METAL TYPES SUBJECT TO ELECTROLYTIC REACTION SHOULD BY PHYSICALLY SEPARATED.

4. REQUIREMENTS AND RECOMMENDATIONS DETAILED IN SPECIFICATIONS SHALL APPLY IN ADDITION TO THE ABOVE DRAWING.

5. THIS DETAIL IS BASED ON SIPLAST. FOR OR EQUAL ROOFING PRODUCT, CONTRACTOR SHALL SUBMIT THE DETAIL FOR APPROVAL BY

THE OWNER AND SHALL MEET MANUFACTURER'S REQUIREMENT TO RECEIVE THE WARRANTY.

PARAPET WITH DENSDECK OR FIRE TREATED PLYWOOD SHEATHING

Details Page 5 of 10

Page 82: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

4" 4"

PARADIENE 20

(fully adhere, extend dry

down vertical face)

METAL EDGE (prime metal flange, set in

mastic & fasten 3" o.c. staggered)

PARADIENE 20

(fully adhere)

PARADIENE 30 FR

(fully adhere)

PS-715 SEALANT

RIGID INSULATION

CONTINUOUS CLEAT FOR METAL EDGE

2 1

/2

" M

IN

. B

EL

OW

B

LO

CK

IN

G

WOOD BLOCKING AS

REQUIRED TO

ACCOMMODATE

INSULATION

ROOF EDGE TYPICAL DETAIL - 2

N.T.S.

NOTES: 1. PA-1021 PLASTIC CEMENT AND PA-1125 PRIMER ARE REQUIRED WHERE MASTIC AND PRIMER ARE INDICATED.

2. THE CARPENTRY AND METAL WORK SHOWN DEPICTS SHOP FABRICATION AND JOB-SITE ASSEMBLY. THESE COMPONENTS

SHOULD BE DESIGNED/FABRICATED/INSTALLED ACCORDING TO GENERALLY ACCEPTED INDUSTRY PRACTICES, STANDARDS

AND APPROVALS.

3. DISSIMILAR METAL TYPES SUBJECT TO ELECTROLYTIC REACTION SHOULD BE PHYSICALLY SEPARATED.

4. REQUIREMENTS AND RECOMMENDATIONS DETAILED IN SPECIFICATIONS SHALL APPLY IN ADDITION TO THE ABOVE DRAWING.

5. THIS DETAIL IS BASED ON SIPLAST. FOR OR EQUAL ROOFING PRODUCT, CONTRACTOR SHALL SUBMIT THE DETAIL FOR

APPROVAL BY THE OWNER AND SHALL MEET MANUFACTURER'S REQUIREMENT TO RECEIVE THE WARRANTY.

Details Page 6 of 10

Page 83: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

4" 4"

1

2

3

4

5

6

7

8

6

8

7

5

4

3

2

RIGID INSULATION

SUMPED ROOF DRAIN DETAIL

TYPICAL DETAIL - 3

1. TAPERED INSULATION IN DRAIN SUMP

2. PARADIENE 20 (fully adhere)

3. LEAD FLASHING (4 lb/sq. ft., 30" X 30" - prime and set in mastic)

4. PARADIENE 20 (39" X 39" - fully adhere, extend 4" beyond lead)

5. VERAL (48" X 48" - torch apply, prime foil around edge min. 4 ")

(lap Veral outside of drain bowl)

6. PARADIENE 30 FR (fully adhere, set in mastic over Veral sheet)

7. MASTIC (set Paradiene layers in mastic 6" around drain perimeter)

8. STRAINER AND CLAMPING RING

NOTES: 1. PA-1021 PLASTIC CEMENT AND PA-1125 PRIMER ARE REQUIRED WHERE MASTIC AND PRIMER ARE INDICATED.

2. ROOF DRAIN COMPONENTS AND INSTALLATION GUIDELINES ARE SUPPLIED BY THE DRAIN MANUFACTURER.

3. VERAL ALUMINUM OR STAINLESS STEEL MUST BE USED IN DRAIN SUMP APPLICATIONS.

4. REQUIREMENTS AND RECOMMENDATIONS DETAILED IN SPECIFICATIONS SHALL APPLY IN ADDITION TO THE ABOVE DRAWING.

5. THIS DETAIL IS BASED ON SIPLAST. FOR OR EQUAL ROOFING PRODUCT, CONTRACTOR SHALL SUBMIT THE DETAIL FOR APPROVAL

BY THE OWNER AND SHALL MEET MANUFACTURER'S REQUIREMENT TO RECEIVE THE WARRANTY.

N.T.S.

OVERHEAD VIEW

Details Page 7 of 10

Page 84: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

PS-715 SEALANT

PARADIENE 30 FR

(fully adhere)

PARADIENE 20

(fully adhere)

LEAD FLANGE

(prime and set in mastic)

PARADIENE 20

(fully adhere)

LEAD FLASHING (4 lb./sq. ft., roll into pipe 1" min.)

RIGID INSULATION

4"4"

VENTILATION THROUGH ROOF

NOTES: 1. PA-1021 PLASTIC CEMENT AND PA-1125 PRIMER ARE REQUIRED WHERE MASTIC AND PRIMER ARE INDICATED.

2. REQUIREMENTS AND RECOMMENDATIONS DETAILED IN SPECIFICATIONS SHALL APPLY IN ADDITION TO THE ABOVE

DRAWING.

3. IF HEIGHT OF VENTILATION THROUGH ROOF IS LESS THAN 8", EXTEND MINIMUM OF 8" ABOVE ROOF FINISH SURFACE

BEFORE INSTALLING LEAD FLASHING.

4. THIS DETAIL IS BASED ON SIPLAST. FOR OR EQUAL ROOFING PRODUCT, CONTRACTOR SHALL SUBMIT THE DETAIL FOR

APPROVAL BY THE OWNER AND SHALL MEET MANUFACTURER'S REQUIREMENT TO RECEIVE THE WARRANTY.

N.T.S.

8" M

IN

IM

UM

TYPICAL DETAIL - 4

Details Page 8 of 10

Page 85: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

PARADIENE 30 FR

(fully adhere)

PARADIENE 20

(fully adhere)

TAPERED INSULATION

(with recover board)

PARAPRO FLASHING

MEMBRANE (fully adhere)

ROOF DECK

PS-715 SEALANT

8"

8"

PRO PASTE OR

INSTALL 4" PVC PIPE, FASTEN

SECURELY ON CONCRETE DECK, AND

CLOSE PIPE TOP END WATER TIGHT

WITH A PLUG.

PARAPRO 123 FLASHING

N.T.S.

NOTES: 1. BEFORE APPLICATION OF PARAPRO FLASHING MEMBRANE, PRO PASTE OR PS-715 ELASTOMERIC SEALANT SHOULD BE USED TO FILL VOIDS WHERE ROOFING

MEMBRANES TERMINATE AT PENETRATIONS.

2. REFER TO SIPLAST PREPARATION GUIDELINES FOR PROPER SURFACE TREATMENT OF ALL MATERIALS PRIOR TO APPLICATION OF PARAPRO FLASHING.

3. PARAPRO CANNOT BE APPLIED OVER MEMBRANES CONTAINING PA-311 ADHESIVES OR OTHER MATERIALS CONTAINING UNCURED, SOLVENT-BASED MATERIALS.

IN SUCH CASES, MEMBRANES TO BE COVERED WITH PARAPRO MUST BE ADHERED WITH SFT ADHESIVE, SFT CEMENT OR PS-715 ELASTOMERIC SEALANT.

CONTACT SIPLAST FOR INFORMATION.

4. REFER TO SIPLAST FLEECE CUTTING RECOMMENDATIONS FOR CONFIGURATIONS, CUTTING, FOLDING AND LAPPING TECHNIQUES.

5. THIS DETAIL IS BASED ON SIPLAST. FOR OR EQUAL ROOFING PRODUCT, CONTRACTOR SHALL SUBMIT THE DETAIL FOR APPROVAL BY THE OWNER AND SHALL

MEET MANUFACTURER'S REQUIREMENT TO RECEIVE THE WARRANTY.

TYPICAL DETAIL - 5

Details Page 9 of 10

Page 86: EASTERN KENTUCKY UNIVERSITY€¦ · EASTERN KENTUCKY UNIVERSITY, PLUS ANY SPECIAL CONDITIONS ENUMERATED HEREIN. NOTICE Any agreement or collusion among Offerors or prospective Offerors,

2" minimum

5"

PA-1021 PLASTIC CEMENT

30

"

5' MAX LENGHT PARATREAD PANELS - BACK SIDE SHOWN

5"

NOTES: 1. PARATREAD IS APPLIED WITH PA-1021 PLASTIC CEMENT TO GRANULE SURFACED, PARAPRO AND FOIL FINISHED MEMBRANES. THE PANELS

MUST BE PRE-CUT FROM THE ROLL IN MAXIMUM 5 FOOT LENGTHS AND ALLOWED TO RELAX PRIOR TO APPLICATION. COLD WEATHER

APPLICATION MAY REQUIRE PRE-WARMING PANELS TO ALLOW THE MATERIAL TO LAY FLAT. THE PA-1021 PLASTIC CEMENT IS APPLIED TO

THE BACK SIDE OF THE PARATREAD IN APPROX. 5" SQUARES, SPACED APPROX. 11" O.C. AT THE OUTER EDGES AND 14" O.C. DOWN THE

MIDDLE OF THE PANELS. THE PARATREAD PANEL IS SET OVER THE ROOF MEMBRANE SURFACE WITH THE GRANULE SURFACE SIDE UP.

PRESSURE SHOULD BE EXERTED ON THE PANEL TO ENSURE POSITIVE CONTACT OF THE PLASTIC CEMENT TO THE ROOF SURFACE.

2. REQUIREMENTS AND RECOMMENDATIONS DETAILED IN SPECIFICATIONS SHALL APPLY IN ADDITION TO THE ABOVE DRAWING.

3. APPLY PARATREAD AS NOTED ON THE ROOF PHOTOS.

4. THIS DETAIL IS BASED ON SIPLAST. FOR OR EQUAL ROOFING PRODUCT, CONTRACTOR SHALL SUBMIT THE DETAIL FOR APPROVAL BY THE

OWNER AND SHALL MEET MANUFACTURER'S REQUIREMENT TO RECEIVE THE WARRANTY.

TYPICAL DETAIL - 6

N.T.S.

WALKPAD APPLICATION

Details Page 10 of 10