East Fork of Fountain Creek Mandatory Pre Bid Meeting
description
Transcript of East Fork of Fountain Creek Mandatory Pre Bid Meeting
![Page 1: East Fork of Fountain Creek Mandatory Pre Bid Meeting](https://reader036.fdocuments.in/reader036/viewer/2022062519/56814f49550346895dbced84/html5/thumbnails/1.jpg)
14 May 2013
![Page 2: East Fork of Fountain Creek Mandatory Pre Bid Meeting](https://reader036.fdocuments.in/reader036/viewer/2022062519/56814f49550346895dbced84/html5/thumbnails/2.jpg)
Aerial of Flood Insurance Rate Map (FIRM)
East Fork of
Fountain Creek
![Page 3: East Fork of Fountain Creek Mandatory Pre Bid Meeting](https://reader036.fdocuments.in/reader036/viewer/2022062519/56814f49550346895dbced84/html5/thumbnails/3.jpg)
Aerial View of Existing Creeks
![Page 4: East Fork of Fountain Creek Mandatory Pre Bid Meeting](https://reader036.fdocuments.in/reader036/viewer/2022062519/56814f49550346895dbced84/html5/thumbnails/4.jpg)
April 11, 2013
Photos looking North – Upstream
![Page 5: East Fork of Fountain Creek Mandatory Pre Bid Meeting](https://reader036.fdocuments.in/reader036/viewer/2022062519/56814f49550346895dbced84/html5/thumbnails/5.jpg)
![Page 6: East Fork of Fountain Creek Mandatory Pre Bid Meeting](https://reader036.fdocuments.in/reader036/viewer/2022062519/56814f49550346895dbced84/html5/thumbnails/6.jpg)
April 11, 2013
Confluence of Main Stem and East Fork of Fountain Creek
South of the Confluence of
Fountain Creek
![Page 7: East Fork of Fountain Creek Mandatory Pre Bid Meeting](https://reader036.fdocuments.in/reader036/viewer/2022062519/56814f49550346895dbced84/html5/thumbnails/7.jpg)
Administrative NotesBid Opening will be 3:00 PM,
Thursday 30 May 2013 at City HallBid Bonds requiredPlease include completed CDOT
Forms 605, 606 and 621CDOT funded projectDBE & OJT Goal = zeroDavis Bacon wages not required
Substantial completion by 30 Sep 2013
All RFI’s should be in writing and sent via e-mail to: [email protected] or [email protected]
Staging area – TBD and negotiated between the Contractor and property owner
![Page 8: East Fork of Fountain Creek Mandatory Pre Bid Meeting](https://reader036.fdocuments.in/reader036/viewer/2022062519/56814f49550346895dbced84/html5/thumbnails/8.jpg)
Channel Fill and ReclamationWithin the Easement:
Per plans and specsCity Engineering Specs (Title 7;
Section 7.5.2.1. Utility Mains – available on line)
95% Modified Proctor (ASTM D-1557) unless otherwise directed
Contractor is responsible for all QC & soils testing
City may do some QA testing
Outside the Easement:Will require special attentionSee supplemental plans
![Page 9: East Fork of Fountain Creek Mandatory Pre Bid Meeting](https://reader036.fdocuments.in/reader036/viewer/2022062519/56814f49550346895dbced84/html5/thumbnails/9.jpg)
Alternative Pipe MaterialsProposals will be evaluated
separatelyDecision to use alternative pipe
materials will be collaboratively evaluated and approved by the City, the property owner and CDOT
Must include:Recent experience with similar
72” and 84” pipe diametersCrew shall also have recent
experience with large diameter pipe installations (i.e. Project Superintendent, Foreman, etc.)
Provide referencesProvide QC plan
![Page 10: East Fork of Fountain Creek Mandatory Pre Bid Meeting](https://reader036.fdocuments.in/reader036/viewer/2022062519/56814f49550346895dbced84/html5/thumbnails/10.jpg)
![Page 11: East Fork of Fountain Creek Mandatory Pre Bid Meeting](https://reader036.fdocuments.in/reader036/viewer/2022062519/56814f49550346895dbced84/html5/thumbnails/11.jpg)
![Page 12: East Fork of Fountain Creek Mandatory Pre Bid Meeting](https://reader036.fdocuments.in/reader036/viewer/2022062519/56814f49550346895dbced84/html5/thumbnails/12.jpg)
![Page 13: East Fork of Fountain Creek Mandatory Pre Bid Meeting](https://reader036.fdocuments.in/reader036/viewer/2022062519/56814f49550346895dbced84/html5/thumbnails/13.jpg)
![Page 14: East Fork of Fountain Creek Mandatory Pre Bid Meeting](https://reader036.fdocuments.in/reader036/viewer/2022062519/56814f49550346895dbced84/html5/thumbnails/14.jpg)
![Page 15: East Fork of Fountain Creek Mandatory Pre Bid Meeting](https://reader036.fdocuments.in/reader036/viewer/2022062519/56814f49550346895dbced84/html5/thumbnails/15.jpg)
Trail Ridge Apartments – Grading Plan