East Davis Street Reconstruction Virtual Public Involvement ......Phone: 920-887-4600x326 Email:...
Transcript of East Davis Street Reconstruction Virtual Public Involvement ......Phone: 920-887-4600x326 Email:...
East Davis Street Reconstruction
Virtual Public Involvement Meeting
City of Beaver Dam
August 13, 2020
Presentation Overview
• Project Team
• Project Overview
• Proposed Improvements
• Construction
• Costs
• Schedule
• City of Beaver Dam• Todd Janssen, PE – Director of Engineer
• Wisconsin Department of Transportation• Zachary Pearson, PE – SW Region Local Program Project Manager
• Project Design Consultant – MSA Professional Services• Jaime Kurten, PE – Project Manager
Project Team
Project Overview
Existing Typical Section
• Storm Sewer
• Sanitary Sewer & Water Main
• Lighting
• Sidewalks
• Signage and Pavement Marking
Proposed Improvements
Proposed Typical Section
• Right of Way/Temporary Easements will be minimized to the maximum extent possible. Easements could be needed for the following
• Grading behind new sidewalk
• Driveway tie in construction
• Construction Staging
• Closed During Construction
• Detour Route via Stone Street
• Local Access will be maintained during construction
Real Estate & Construction
Detour RouteProject
Location
• STP – Urban Funding• Eligible for 80% State/Federal and 20% Local
• 100% Local Funding for non-participating items
• Sanitary Sewer and Water Utility Improvements
• Special Assessments
• City of Beaver Dam typically assesses for a portion of the replacement of non-compliant sidewalks, replacement of driveway aprons, and street lighting to the adjacent landowner
• Preliminary Cost Estimate: $2.5 million
Project Costs and Funding
Preliminary Plan Submittal May 2020
Public Involvement August 2020
Environmental Document September 2020
60% Plans/Right of Way Plat Fall 2020
Final Plans August 1, 2021
Bid Letting December 14, 2021
Construction Summer 2022
Schedule
• Comments on the proposed design are encouraged
• Email or mail comments by August 28, 2020
• For more information contact:
City of Beaver Dam
Todd Janssen, PE – Director of Engineering
Phone: 920-887-4600x326
Email: [email protected]
Project Design Consultant – MSA Professional Services
Jaime Kurten, PE – Project Manager
Phone: 608-242-6619
Email: [email protected]
Public Input and Comments